SOAL JAWAB2

download SOAL JAWAB2

of 14

Transcript of SOAL JAWAB2

  • 7/30/2019 SOAL JAWAB2

    1/14

    Latihan

    Soal-soal

  • 7/30/2019 SOAL JAWAB2

    2/14

    = failure rate, maka = 1/MTBF

    m = repair rate, maka m = 1/MTTR

    Availability = MTBF/(MTBF+MTTR)MTBF tak hinggaMTTR 0

    Maintenance Ratio,economic;

    MC total maintenance cost---- = -----------------------------PC total production cost

    MC total maintenance cost---- = -----------------------------IE value of idle equipment maintained

    RUMUS-RUMUS PENTING DALAM PENYELESAIAN SOALMANAJEMEN PEMELIHARAAN

  • 7/30/2019 SOAL JAWAB2

    3/14

    Operating Ratio

    number of good items producedProduction Ratio = -----------------------------------------

    number theoritically possible

    number of good items producedProductivity ratio = --------------------------------------

    tinme taken

    number of good items producedTrue productivity = ------------------------------------------

    machine runing time + downtime

  • 7/30/2019 SOAL JAWAB2

    4/14

    Availability Ratios.

    Time required for productionEquipment duty ratio = -------------------------------------------

    total time

    total machine timeOperational availability = -----------------------------------------

    Time required for production

    total machine timeTrue Availability = --------------------------------------

    machine time + down time

    total machine time

    Over all Availability = -----------------------------------------------------machine running time + maintenance time

  • 7/30/2019 SOAL JAWAB2

    5/14

    MTBF = Mean Time Between FailureMTTR = Mean Time to RepairMTTF = Mean Time To Failure

    MUT = Mean Up TimeMDT = Mean Down Time

    MUTMTTR

    MDT

    MTBF

    t

    Running

    Stopped

  • 7/30/2019 SOAL JAWAB2

    6/14

    1. Menghitung Productivity suatu kebijakan pemeliharaan.

    Rumus :

    Productivity = Utilization X Methods X Performance.

    2. Menghitung Overall equipment Effectiveness (OEE).Rumus :

    OEE = Availability X Efficiency X Quality

  • 7/30/2019 SOAL JAWAB2

    7/14

    1. Menghitung Maintenance Productivity (produktivitas pemeliharaan).

    Rumus :

    Productivity = Utilization X Methods X Performance.

    Keterangan :

    Utilization, Methods dan Performance umumnya dinyatakan dalam bentukprosentase dari kriteria yang diinginkan,sebagai contoh, bila diketahui tingkatutilization, methods dan performance suatu perangkat berturut-turut adalah65 %, 50 % dan 75 %, maka

    Productvity = 0.65 X 0.50 X 0.75 = 0.24 atau 24 %

  • 7/30/2019 SOAL JAWAB2

    8/14

    2. Menghitung Overall equipment Effectiveness (OEE).

    Rumus :

    OEE = Availability X Efficiency X Quality

    Keterangan :

    a. Availability.

    Operation timeAvailability = ------------------------

    Net Available time

    Net available time = Total available time Planned Down timeIf Unplanned down time occurs (Uncontrolled)Net available time =

    Total available time Planned down time Unplanned down time.

  • 7/30/2019 SOAL JAWAB2

    9/14

    Keterangan :

    b. Efficiency.

    Theoretical Production timeEfficiency = -----------------------------------

    Actual Production time.

    c. Quality .

    Acceptable partsQuality = -------------------------------

    Total Parts produced

    Number of accepted parts = Total Parts Produced Rejected Parts.

  • 7/30/2019 SOAL JAWAB2

    10/14

    Contoh Soal :

    1. Suatu perangkat produksi mempunyai data catatan kinerja sebagaiberikut :Loading time = 20 jam.Down time = 120 menit.Waktu siklus = 0.50 menit per unitJumlah produk yang dproses = 2000 unit,

    Jumlah produk cacat = 100 unit

    Hitung :a. Overall Equipment Effectivenessb. Dengan penerapan program PM, ternyata

    memperoleh peningkatan proses yaitu pengurangan

    set-up time peralatan 60 menit, dan produk yangcacat menjadi hanya 50 unit saja. Berapa OEE sekarang?

  • 7/30/2019 SOAL JAWAB2

    11/14

    Jawaban a OEE = Availability x efficiency x quality 1.Availability

    Loading time = 20 jam operating time = Downtime = 2 jam 20 2 = 18 jam AV = 18 jam = 0.9 = 90 %

    20 jam 2. Efficiency

    Waktu siklus = 0,5 menit / unit produksi = 2 unit/menit Operaing time = 18 jam P18 jam = 18 x 60 x 2 = 2160 unit

    Output ( jumlah produk yang diproses) = 2000 unit Performance eff = 2000 unit = 0,93 % = 93 %

    2160 3. Quality

    Produk cacat = 100 unit Produk seluruhnya = 2000 unit Rate of quality ( ROQ) = 2000-100 = 0,95 = 95 %

    2000 OEE = AV X EFF X ROQ = 0,90 x 0,93 x 0,95 = 0,79 = 79 %

  • 7/30/2019 SOAL JAWAB2

    12/14

    OEE = Availability x efficiency x quality 1.Availability

    Loading time = 20 jam operating time = Downtime = 1 jam 20 1 = 19 jam AV = 19 jam = 0.9 = 95 %

    20 jam 2. Efficiency

    Waktu siklus = 0,5 menit / unit

    produksi = 2 unit/menit Operaing time = 19 jam P19 jam = 19 x 60 x 2 = 2280 unit Output ( jumlah produk yang diproses) = 2000 unit Performance eff = 2000 unit = 0,87 % = 87 %

    2280 3. Quality

    Produk cacat = 50 unit Produk seluruhnya = 2000 unit Rate of quality ( ROQ) = 2000-50 = 0,97 = 97 %

    2000 OEE = AV X EFF X ROQ = 0,95 x 0,87 x 0,97 = 0,80 = 80 %

  • 7/30/2019 SOAL JAWAB2

    13/14

    Contoh Soal :

    2. Suatu perangkat produksi mempunyai data catatan kinerja sebagai berikut :Kebutuhan persediaan berdasarkan data biaya, pemesanan, harga,

    kerusakan yang terjadi,dll, diperoleh kebutuhan komponen KK007 untukkegaiatan operasi dan pemeliharaan sebagai berikut :

    Hitung :a. Berapa jumlah persediaan optimal komponen ?b. Berapa biaya persediaan?

    Bila diketahui biaya kelebihan persediaan per unit =$ 20.-dan biaya kekurang persediaan per unit = $ 50.-

    Kebutuhan komponen perbulan

    Kejadian (kali)

    10 10

    20 20

    30 15

    35 15

    40 20

    65 20

  • 7/30/2019 SOAL JAWAB2

    14/14