Time schedule for biogas process

Transcript of Rekayasa Kotoran Sapi Gantt Chart

Sheet1Gantt-Chart PhDNo.Task/AssignmentStart DateEnd DateDurationTask/AssignmentStart DateDuration1Survei lokasi peternakan sapi rakyat01/04/1414/04/1413Task 101/04/14132Studi literatur dan observasi07/04/1430/04/1423Task 207/04/14233Pematangan konsep07/04/1431/05/1454Task 307/04/14544Pengambilan sampel 01/05/1414/05/1413Task 401/05/14135Analisa unsur-unsur kimia pada kotoran sapi15/05/1431/05/1416Task 515/05/14166Perekayasaan teknologi secara teoritis01/06/1415/07/1444Task 601/06/14447Disain RekTek & Simulasi16/07/1416/10/1492Task 716/07/14928Rancang Bangun RekTek 16/10/1415/01/1591Task 816/10/14919Pengujian RekTek16/01/1531/01/1515Task 916/01/151510Analisa Hasil Rektek01/02/1515/02/1514Task 1001/02/1514