Rab Perumahan Type 36

download Rab Perumahan Type 36

of 1

Transcript of Rab Perumahan Type 36

  • 8/18/2019 Rab Perumahan Type 36

    1/1

    Harga Sat. Jumlah TOTAL

    (Rp.) (Rp.) (Rp.)

    1. PEKERJAAN PENGUKURAN DAN BOWPLANG 36.00 m 16,688  600,750 

    600,750 

    2. PEKERJAAN PONDASI PASANGAN BATU KALI 1 pc : 5 ps 2.072 m³ 595,845  1,234,591 

    1,835,340.84 

    3. PEKERJAAN RING BALK BETON BERTULANG ( 0,15 x 0,10 )

    a. Bahan Besi sloof dan Begisting 36 m' 48,958.34  1,762,500 

    b. Bahan Beton K-175 komposisi 1 : 2 : 3 0.540 m³ 881,945  476,250 

    c. Bahan Besi Steek = 3 mtr ke atas 12 btg 60,000  720,000 

    4,794,091.29 

    4. PEKERJAAN PEMASANGAN BATA BRICK LOCK SYSTEM 4236 pcs 3,750  15,885,000 

    20,679,091.29 

    5. PEKERJAAN PASANG KERAMIK 30cm X 30cm 36 m2 100,778  3,627,990 

    24,307,081.29 

    6. PEKERJAAN ATAP DAN RANGKA BAJA RINGAN + GENTENG METAL + LISPLANK 64.80  m2 156,173  10,120,000 

    34,427,081.16 

    7. PEKERJAAN PLAFOND DAN RANGKA 36 m2 73,958  2,662,500 

    37,089,581.31 

    8. PEKE RJAAN KAMAR MANDIa. Bak Mandi dan Kloset jongkok 1 unit 422,875  422,875 

    b. Acian dan Lantai Floor Hardener 4.50 m2 17,889  80,499 

    c. Septitank 1.000 unit 525,000  525,000 

    38,117,956 

    9. PEKERJAAN PEMASANGAN PIPA PVC TIPE AW Ø 2"

    a. Pipa PVC 2" 4 m' 33,750  135,000 

    b. Pipa PVC 2" 4 m' 33,750  135,000 

    c. Pipa PVC 1/2" 4 m' 8,438  33,750 

    38,421,706 

    10. PEKERJAAN ELEKTRIKAL PENERANGAN

    5 titik 5 pcs 84,375  421,875 

    38,843,581 

    11. UPAH PEKERJA BANGUNAN

    Upah Pekerja Harian 10 hr 625,000  6,250,000 

    45,093,581 

    12. KUSEN ,PINTU DAN JENDELA

    a. kusen dan pintu + Kunci 4 bh 937,500  3,750,000 

    b. Kusen dan Pintu Kamar Mandi PVC + kunci slot 1 bh 250,000  250,000 

    c. kusen jendela dan kaca + kunci slot 4 bh 250,000  1,000,000 

    JUMLAH 50,093,581 

    Per m 2 1,391,488.35 

    Pembulatan 1,400,000.00 

    RANCANGAN ANGGARAN BIAYA KONSTRUKSI PEKERJAAN RUMAH TYPE 36

    No. Sat.VolumeUraian Pekerjaan