REKAPITULASI TOTAL PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN RSUD PROVINSI KEPULAUAN RIAU JL. Baru Sungai Carang Km 8 - Tanjung Pinang NO. URAIAN PEKERJAAN 1 2 A PEKERJAAN SIPIL DAN ARSITEKTUR 1 PEKERJAAN PERSIAPAN 2 LANTAI 3 ( RUANG OK ) 3 LANTAI 5 ( RUANG RAWAT INAP KELAS 3B ) 4 LANTAI 6 ( RUANG RAWAT INAP KELAS 3A ) 5 LANTAI 7 ( RUANG RAWAT INAP KELAS 1 & 2 ) 6 LANTAI 8 ( RUANG RAWAT INAP KELAS VIP ) 7 LANTAI 9 ( ROOF ) 8 PEKERJAAN LAIN - LAIN B PEKERJAAN MEP 1 PERALATAN UTAMA EXISTING 2 PERALATAN UTAMA MEKANIKAL ELEKTRIKAL 3 PEKERJAAN INSTALASI MEKANIKAL ELEKTRIKAL JUMLAH PPN 10% TOTAL DIBULATKAN Terbilang : …………………………………………………………………………………………………………………….. Rupiah

description

kn;

Transcript of Rab Me Tanjung Pinang6

Page 1: Rab Me Tanjung Pinang6

REKAPITULASI TOTALPENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN JUMLAH

1 2 3

A PEKERJAAN SIPIL DAN ARSITEKTUR

1 PEKERJAAN PERSIAPAN

2 LANTAI 3 ( RUANG OK )

3 LANTAI 5 ( RUANG RAWAT INAP KELAS 3B )

4 LANTAI 6 ( RUANG RAWAT INAP KELAS 3A )

5 LANTAI 7 ( RUANG RAWAT INAP KELAS 1 & 2 )

6 LANTAI 8 ( RUANG RAWAT INAP KELAS VIP )

7 LANTAI 9 ( ROOF )

8 PEKERJAAN LAIN - LAIN

B PEKERJAAN MEP

1 PERALATAN UTAMA EXISTING

2 PERALATAN UTAMA MEKANIKAL ELEKTRIKAL

3 PEKERJAAN INSTALASI MEKANIKAL ELEKTRIKAL

JUMLAH

PPN 10%

TOTAL

DIBULATKAN

Terbilang : …………………………………………………………………………………………………………………….. Rupiah

……………….. , Juli 2014

PT……………………………………

…………………………………………. Direktur / Pimpinan

Page 2: Rab Me Tanjung Pinang6

REKAPITULASI BQ PEKERJAAN MEPPENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. REKAPITULASI PEKERJAAN MEKANIKAL ELEKTRIKAL JUMLAH

1 2 3I PERALATAN UTAMA SYSTEM MEKANIKAL ELEKTRIKAL A PERALATAN UTAMA EXISTING1 RE KONDISI PERALATAN UTAMA PEMADAM KEBAKARAN2 RE KONDISI PERALATAN UTAMA SYNCRONISING GENSET3 RE KONDISI CAPASITOR BANK 1.000 KVAR4 RE KONDISI TRANSFORMER 2000 KVA5 PERALATAN UTAMA SYNCRONISING TRANSFORMER 2000 KVA6 KABEL FEDEER SYNCRONISING TRANSFORMER7 RE KONDISI PERALATAN UTAMA FIRE ALARM8 RE KONDISI PERALATAN VENTILASI LANTAI 9

TOTAL RE KONDISI PERALATAN UTAMA EXISTING B PERALATAN UTAMA MEKANIKAL ELEKTRIKAL 1 PENJERNIHAN AIR BERSIH / WATER TREATMENT LANTAI 3 2 PEKERJAAN CENTRAL WATER TREATMEN LANTAI 9 3 SYSTEM DAN PERALATAN UTAMA AIR PANAS4 SYSTEM DAN PERALATAN BOOSTER PUMP ( LANTAI 9 )5 PERALATAN UTAMA CAPASITOR BANK 420 KVA6 PERALATAN UTAMA CCTV7 PERALATAN UTAMA MATV8 PERALATAN UTAMA FIRE ALARM9 PERALATAN UTAMA SOUND SYSTEM ( BGM ) ( REKONDISI)

10 PERALATAN PENUMATIC TUBE SYSTEM11 PEKERJAAN UPS 30 KVA12 PERALATAN UTAMA GAS MEDIS13 PEKERJAAN CHILLER 225 TR & INSTALASI POMPA

TOTAL PERALATAN UTAMA MEKANIKAL ELEKTRIKAL

II PEKERJAAN INSTALASI MEKANIKAL ELEKTRIKALA PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 3 OK1 PEKERJAAN MEKANIKAL2 PEKERJAAN ELEKTRIKAL

B PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 51 PEKERJAAN MEKANIKAL2 PEKERJAAN ELEKTRIKAL

C PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 61 PEKERJAAN MEKANIKAL2 PEKERJAAN ELEKTRIKAL

D PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 71 PEKERJAAN MEKANIKAL2 PEKERJAAN ELEKTRIKAL

E PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 81 PEKERJAAN MEKANIKAL2 PEKERJAAN ELEKTRIKAL

F PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 91 PEKERJAAN MEKANIKAL RE KONDISI 2 PEKERJAAN ELEKTRIKAL

G PENANGKAL PETIR WWTPTOTAL PEKERJAAN INSTALASI MEKANIKAL ELEKTRIKAL

REKAPITULASI PEKERJAAN MEKANIKAL ELEKTRIKAL

Page 3: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAU

JL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT VOL

II PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 3 OKA PEKERJAAN MEKANIKAL

A1 SISTEM PENGKONDISIAN UDARA( HVAC RUANG OK ) 1 AC Single (Positif full Fresh Air lengkap pipa Refrigrant , isolasi & pipa drain)1.1 Tipe : Air Handling Unit ( AHU)

1 AHU + CU 3-1,3-5 ( OK 1, OK 5 ) unit 2.00 Kapasitas : 170.000 BTU/hAir Flow : 4600 CFM , SP 6 inwg

2 AHU + CU 3- 2 ( OK 2 ) unit 1.00 Kapasitas : 170.000 BTU/hAir Flow : 4000 CFM , SP 6 inwg

3 AHU + CU 3-3, 3-4 ( OK 3 , OK 4) unit 2.00 Kapasitas : 170.000 BTU/hAir Flow : 5300 CFM , SP 6 inwg

4 AHU + CU 3- 6 ( OK 6 ) unit 1.00 Kapasitas : 170.000 BTU/hAir Flow : 5800 CFM , SP 6 inwg

5 AHU + CU 3- 7 ( Jantung ) unit - Kapasitas : 170.000 BTU/hAir Flow : 3500 CFM , SP 3,5 "wg

6 FCU + CU 3- 8, 9, 10 ( Corridor 1 ,2 & 3 ) unit 3.00 Kapasitas : 200.000 BTU/hAir Flow : 2700 CFM

7 Rangka dan Pengantung ls 1.00

1.2 Exhust fan Ruang OK type CentrifugalLengkap Dog House ukuran :

1 EF 3-1 & 3-5 + Inverter unit 2.00 Air Flow : 1400 CFM

2 EF 3-2 + Inverter unit 1.00 Air Flow : 1250 CFM

3 EF 3-3, 3-4 + Inverter unit 2.00 Air Flow : 1600 CFM

4 EF 3-6+ Inverter unit 1.00 Air Flow : 1700 CFM

5 EF 3-7 + Inverter unit 1.00 Air Flow : 1100 CFM

1.3 lengkap pipa Refrigrant , isolasi & pipa drainPekerjaan Pipa Refrigrant, lengkap isolasi gantungan

1 Pipa Refrigrant 1 3/8"X5/8" m' 350.00 2 Stop valve 1 3/8" bh 20.00 3 Stop valve 5/8" bh 20.00 4 Solonoid bh 14.00 5 Filter Dryer bh 7.00 6 Sight Glass bh 7.00 7 Drain pun bh 10.00 8 Drain pipa + isolasi 1" m' 105.00

Sub Total Pekerjaan AC Single

2 Pekerjaan Ducting AC2.1 Plenum Duct Supply (OK)

Polyuretane lengkap rangka & penggantung Plenum Duct Supply - ukuran :

1 38"x38" unit 1.00 2 36"x36" unit 2.00 3 34"x34" unit 1.00 4 34"x32" unit 1.00 5 32"x32" unit 1.00 6 30"x30" unit 1.00 7 Duct Plenum Hepa (PxLxT) 48"x24X40" Polyurethane unit 24.00 8 Rangka dan Pengantung ls 1.00

2.2 Plenum Duct Supply (Corridor OK FCU 8, 9, 10)Polyuretane lengkap rangka & penggantung Plenum Duct Supllay - ukuran :

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 4: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1 22"x22" unit 3.00

2.3 Supply Ducting ( Ruang OK )Polyuretane lengkap rangka & penggantung ukuran :

1 36"x20" m' 9.00 2 36"x18" m' 18.00 3 32"x18" m' 18.00 4 30"x18" m' 9.00 5 28"x18" m' 9.00 6 24"x18" m' 9.00 7 26"x20" m' 3.00 8 26"x18" m' 6.00 9 24"x18" m' 6.00

10 22"x18" m' 3.00 11 20"x18" m' 3.00 12 18"x18" m' 3.00 13 20"x18" m' 8.00 14 18"x18" m' 16.00 15 18"x16" m' 16.00 16 18"x14" m' 8.00 17 16"x14" m' 8.00 18 14"x14" m' 91.00 19 14"x12" m' 224.00 20 12"x12" m' 168.00 21 Rangka dan Pengantung ls 1.00

2.4 Supply Ducting ( Corridor Lantai 3 OK )Polyuretane lengkap rangka & penggantung ukuran :

1 20"x18" m' 21.00 2 20"x16" m' 21.00 3 18"x18" m' 24.00 4 18"x16" m' 21.00 5 16"x16" m' 21.00 6 14"x12" m' 28.00 7 10"x10" m' 30.00 8 Rangka dan Pengantung ls 1.00

2.5 Returnt Duct FCU ( Corridor Latani 3 OK)Polyuretane lengkap rangka & penggantung ukuran :

1 18"x18" m' 30.00 2 16"x16" m' 45.00 3 14"x14" m' 48.00 4 14"x12" m' 48.00 5 10"x10" m' 45.00

2.6 Flexible duct, ukuran :1 dia. 10" m' 16.00 2 dia. 8" m' 10.00

2.7 Volume Damper/VD, ukuran :1 20"x18" bh 21.00 2 20"x16" bh 21.00 3 18"x18" bh 2.00 4 18"x16" bh 24.00 5 16"x16" bh 24.00 6 16"x14" bh 4.00 7 14"x12" bh 24.00 8 10"x10" bh 60.00

2.8 Supply Air Difuser/SAD, ukuran:1 12"x12" bh 4.00 2 10"x10" bh 28.00

2.9 Filter dan Hepa Filter lengkap gantungan, penyanggaukuran:

1 Box Hepa 24"x48"x40" ( 60x120x100) bh 28.00 2 Box Medium Filter bh 14.00 3 Box Pre Filter Plenum duct bh 14.00 4 Hepa 24"x48"x6" ( 60x120x15) ( RUANG OK ) bh 28.00

Page 5: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

5 Hepa 24"x48"x6" ( 60x120x15) ( INDOOR UNIT ) bh 14.00 6 Medium filter bh 14.00 7 Pre filter bh 14.00 8 Magnhelic digital bh 7.00 9 Pressure switch dan indikator blocking bh 7.00

10 Thermostat digital bh 7.00 11 Inverter + control unit bh 7.00 12 Temperatur Indikator Control bh 7.00 13 Velocity Indikator Control bh 7.00 14 Pressure Indikator Control bh 7.00 15 Humidity Indikator Control digital bh 7.00 16 Duct Thermostat bh 7.00 17 Duct Humidity Tranmister bh 7.00 18 Duct Temperatur Tranmister bh 7.00 19 Velocity Tranmister bh 7.00 20 Heater 5000 watt dan sensor bh 6.00

2.10 Relum Air Grille/RAG, ukuran:1 20"x8" bh 30.00 2 Box Pre Filter Return Duct bh 28.00 3 24"x12" perforated stainliss bh 28.00

2.11 Fresh Air Duct: FCU 3 (8,9,10)1 20"x14" m' 90.00

2.13 Fresh Air Grille/FAG, ukuran:

1 20"x10" bh 30.00 2 Start-up dan Balancing system test unit 10.00

Sub Total Pekerjaan Ducting AC 3 Pekerjaan Kabel Kontrol AC OK

1 Kabel dari MDP 5 ke PP OU 3 - OK (1,2,3,4,5,6,7) m' 34.00 NYY 4 x 95 mm + BC 50 mm

1 Kabel dri PP OU 3 OK ke OU 1,2,3,4,5,6,7 m' 371.00 NYY 4 x 16 mm + BC 16 mm

2 Kabel dri PP IU OK ke IU 1,2,3,4,5,6,7 m' 234.00 NYY 4 x 6 mm + BC 6 mm

3 Kabel dri PP IU OK ke EF U 1,2,3,4,5,6,7 m' 234.00 NYY 4 x 6 mm + BC 6 mm

4 Kabel Contol dari OU 1,2,3,4,5,6,7 m' 371.00 NYY 4 x 2.5 mm

5 Panel Control IU ( untuk mesuplay 7 unit) ls 1.00 6 Testing & commissioning unit 10.00

Sub Pekerjaan Kabel Kontrol AC OK 4 Pekerjaan Sistem Ventilasi

4.1 Exhust fan Scrub up+ Toilet Ruang OK type CentrifugalSuplay dan Instal EF 3-10 & 3-11 + InverterAir Flow : 2400 CFM

1 18"x16" m' 36.00 2 16"x16" m' 60.00 3 14"x12" m' 36.00 4 10"x10" m' 48.00

Sub Total pekerjaan Ventilasi SUB TOTAL SISTEM PENGKONDISIAN UDARA( HVAC RUANG OK )

A2 SISTEM INSTALASI AIR BERSIH & AIR PANAS lantai 3 ( OK )1.1 Polypropylene(PPR-Pipe) PN-10 incl.Support

1 dia. 100 mm(4") m' 8.00 2 dia. 80 mm(3") m' 12.00 3 dia. 80 mm(2 1/2") m' 154.00 4 dia. 50 mm(2") m' 54.00 5 dia. 40 mm(1 1/2") m' 99.00 6 dia. 25 mm(1") m' 34.00 7 dia. 20 mm(3/4") m' 41.00 8 dia. 15 mm(1/2") m' 102.00 9 Fitting & aksesories is 1.00

1.2 Polypropylene Pipe (PPR-Pipe) klas PN-20 incl. Isolasi support ( Air Panas) Tidak dikerjakan 1 dia. 80 mm(3") m' - 2 dia. 65 mm (2 1/2") m' - 3 dia. 50 mm (2") m' - 4 dia. 40 mm(1 1/2") m' - 5 dia. 25 mm(1") m' -

Page 6: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

6 dia. 20 mm(3/4") m' - 7 dia. 15 mm(1/2") m' - 8 Fitting & aksesories is -

Page 7: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.3 Valve & aksesories1.3.1 Gate valve :

1 dia 50 mm(2") bh 2.00 2 dia 40 mm(1 1/2") bh 2.00 3 dia 25 mm(1") bh 1.00 4 dia 20 mm(3/4") bh 11.00 5 dia 15 mm(1/2") bh 7.00

1.3.2 Chek valve : 1 Chek valve : 65 mm ( 2 1/2" ) bh 1.00 2 Chek valve : 25 mm ( 1" ) bh 6.00

1.4 Testing & Commissioning Ls 1.00 SUB TOTAL SISTEM INSTALASI AIR BERISH & AIR PANAS LANTAI 3 ( OK )

A3 SISTEM INSTALASI AIR KOTOR1 Pompaan Air Kotor & Air Buangan

1.1 Polivinyl Chlorida pipe (PVC) klas 10kg/cm2 incl. Support1 dia 150mm (6") m' 9.00 2 dia 100mm (4") m' 116.00 3 dia 80mm (3") m' 116.00 4 dia 50mm (2") m' 116.00 5 Fitting & aksesories is 1.00

1.2 Pemipaan VentPolivinyl Chlorida Pipe(PVC) klass 10kg/cm2 incl. Support

1 dia 80mm (3") m' 9.00 2 dia 50mm (2 1/2") m' 116.00 3 dia 50mm (2") m' 54.00 4 Fitting & aksesories is 1.00

1.3 Sanitair1 Clean Out(CO) dia 4" bh 6.00 2 Clean Out(CO) dia 2.1/2" bh 8.00 3 Floor Drain(FD) 4" bh 6.00

1.4 Testing & Commissioning Ls 1.00 SUB TOTAL SISTEM INSTALASI AIR KOTOR

A4 SISTEM PEMADAM KEBAKARAN1 Pekerjaan Instalasi Hidrant

1.1 PemipaanPemipaan BSP sch 40 termasuk support

1 dia. 150mm(6") m' - 2 dia. 100mm(4") m' 8.00 3 dia. 80mm(3") m' 66.00 4 dia. 65mm(2 1/2") m' 24.00 5 dia. 50mm(2") m' 78.00 6 Fitting & aksessories is 1.00

1.2 Valve1 Gate valve,dia. 80mm(3") bh 2.00

1.3 Hydrant box(Tipe B/indoor) Lengkap accsories unit 2.00 Roll fire, Hydrant Valve, Jet Nosle,Hose Rack 1,5"

1.4 Tabung kebakaran fire extinguisherFE, Tipe ABC Dry ChemicalKapasitas: 4 kg bh 11.00

1.5 Testing & commissioning is 1.00

2 Pekerjaan Instalasi Sprinkler2.1 Head Sprinkler

Tipe pendant bh 18.00

2.2 PemipaanBlack steel pipe(BSP) ach. 40 termasuk support

1 dia. 150mm(6") m' - 2 dia. 100mm(4") m' - 3 dia. 80mm(3") m' - 4 dia. 65mm(2 1/2") m' 30.00

Page 8: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

5 dia. 50mm(2") m' 113.40 6 dia. 40mm(1 1/2") m' 66.30 7 dia. 32mm(1 1/4") m' - 8 dia. 25mm(1") m' 72.00 9 Fitting & aksessories is 1.00

2.3 ValveButterfly valve,dia. 100mm(4") bh -

2.4 Flow Switch bh 1.00

2.5 Pipa drainPolivinyl Chloride Pipe(PVC) klas 10kg/cm2

1 dia. 50mm(2") m² 4.00 2 dia. 25mm(1") m² 24.00 3 Fitting & aksessories Ls 1.00

2.6 Valve1 Gate valve dia. 25mm(1") bh -

2.7 Testing & Commisioning is 1.00 SUB TOTAL SISTEM PEMADAM KEBAKARAN

A5 SISTEM INSTALASI GAS, VACUUM & CIMPRESSED AIR LANTAI 3 ( RUANG OK ) DALAM BANGUNANA PEKERJAAN INSTALASI DALAM BANGUAN1 Instalasi Jaringan Oxygen

Pipa Tembaga ASTM 819 Type L1 Diameter3/8" m' 21.00 2 Diameter 1/2" m' 63.00 3 Diameter 5/8" m' 83.00 4 Diameter 3/4" m' 29.00 5 Fitting da Accessories Ls 1.00

2 Instalasi Jaringan Nitrous OxidePipa Tembaga ASTM 819 Type L

1 Diameter3/8" m' 21.00 2 Diameter 1/2" m' 63.00 3 Diameter 5/8" m' 83.00 4 Diameter 3/4" m' 29.00 5 Fitting da Accessories Ls 1.00

3 Instalasi Jaringan Comp AirPipa Tembaga ASTM 819 Type L

1 Diameter3/8" m' 21.00 2 Diameter 1/2" m' 63.00 3 Diameter 5/8" m' 83.00 4 Diameter 3/4" m' 29.00 5 Fitting da Accessories Ls 1.00

4 Instalasi Jaringan VacuumPipa Tembaga ASTM 819 Type L

1 Diameter3/8" m' 21.00 2 Diameter 1/2" m' 63.00 3 Diameter 5/8" m' 83.00 4 Diameter 3/4" m' 29.00 5 Fitting da Accessories Ls 1.00

SUB TOTAL INSTALASI DALAM BANGUANN

5 PERALATAN DALAM RUANGAN OK1 Ceiling Outlet, Spring Hose Type 4 Gases buah 7.00 2 Zona Valve 4 Gas (O, N, A, V) set 7.00 3 Area Alarm 4 Gas (O, N, A, V) set 7.00 4 Excess Gas Purging System ( AGSS) unit 7.00 5 Testing & Kommisioning ls 1.00

SUB TOTAL PERALATAN DALAM BANGUANN

SUB TOTAL SISTEM INSTALASI GAS, VACUUM & CIMPRESSED AIR LANTAI 3 ( RUANG OK ) SUB TOTAL PEKERJAAN MEKANIKAL LANTAI 3 (OK)

B PEKERJAAN ELEKTRIKALB1 PEKERJAAN PANEL DAYA1.1 Panel LP 3-OK unit 1.00

Page 9: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.2 Panel PP UPS 1 DAN 2 unit 2.00 1.3 Panel PP AC INDOOR OK unit 1.00 1.4 Panel PP AC OUTDOOR OK unit 1.00 1.5 Panel SDP -3 OK unit 1.00 1.6 Panel PPS -3 OK unit 1.00 1.7 Panel MDP - 3 OK unit 1.00 1.8 Panel SDP Pompa Filter 3 OK unit 1.00

SUB TOTAL PEKERJAAN PANEL DAYA B2 PEKERJAAN KABEL3.1 Kabel dari Panel MDP - 5 ke MDP 3 OK m' 50.00

NYY 2X 4 x 1x185 mm2 +NYA 70 mm23.2 Kabel dari Panel MDP - 3 ke SDP 3 OK m' 29.00

NYY 4 x 95 mm2 +NYA 70 mm23.3 Kabel dari Panel SDP -3 ke LP 3 OK, m' 10.00

NYY 4 x 16 mm2 +NYA 16 mm23.4 Kabel dari Panel SDP -3 ke PP UPS 1+2 OK, m' 44.00

NYY 4 x 25 mm2 +NYA 25 mm23.5 Kabel dari Panel MDP -3 ke PP AC Indoor OK m' 57.00

NYY 4 x 70 mm2 +NYA 70 mm23.6 Kabel dari Panel MDP -3 ke PP AC Outdoor OK m' 92.00

NYY 4 x 1x 240 mm2 +NYA 70 mm23.7 Kabel dari Panel SDP -3 ke PP Filter OK , m' 30.00

NYY 4 x 10mm2 +NYA 6 mm23.8 Kabel dari Panel SDP -3 ke PP IU Control OK , m' 25.00

NYY 4 x 25 mm2 +NYA 25 mm23.9 Kabel dari Panel MDP -3 ke OU AC multi Lantai 5, m' 24.00

NYY 4 x 16 mm2 +NYA 16 mm2 SUB TOTAL PEKERJAAN KABEL

B3 PEKERJAAN KABEL TRAY & KABEL LADDERLengkap gantungan, Rak kabel dan support

4.1 Kabel ladder elektrikal 300x100 mm m' 60.00 4.2 Kabel ladder elektronik 200x100 mm m' 60.00

SUB TOTAL PEKERJAAN KABEL TRAY DAN KABEL LADDER

B4 PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR 1 RM 300 AP( Prismatic) 2x36 TL LED Ess 16 W bh 51.00 2 RM 300 AP( Prismatic) 4x18 TL LED Ess 10 W bh 120.00 3 Theme 150 -70- E 27 LED Bulb 10 W bh 24.00 4 Theme 150 -70- E 27 LED Bulb 10 W + Batt bh 20.00 5 Theme 150 -70- E 27 LED Bulb 7 W bh 26.00 6 Exit Green LED H 1+ Battery bh - 7 BL CG 1X 36 TL LED ESS 16 W bh 26.00 8 Grid Switch 9 gang bh - 9 Saklar Tunggal 16 A, 1 phasa bh 18.00

10 Saklar Ganda 16 A, 1 phasa bh 4.00 11 Presence light ( Pasiveinfrared ) bh 7.00 12 Saklar Hotel Tunggal 16 A, 1 phasa bh - 13 Stop kontak 16 A, 1phasa ( Lantai ) bh - 14 Stop kontak 16 A, 1phasa ( Ceilling) bh - 15 Stop kontak 16 A, 1 phasa bh 6.00 16 Stop kontak 16 A, 3 phasa bh 7.00 17 Instalasi Penerangan bh 80.10 18 Instalasi stop kontak 1 phase bh 1.80 19 Instalasi stop kontak 3 phase bh 7.00

SUB TOTAL PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR SUB TOTAL PEKERJAAN LISTRIK LANTAI 3 (OK)

B5 PEKERJAAN SISTEM FIRE ALARM1 Photo Electronic Smoke Detector bh 18.00 2 Rate of Rise heat detector bh 4.00 3 Fixed Temp Heat Detector bh 2.00 4 Alarm Bell 6" bh 1.00 5 Manual Push Bulton bh 1.00 6 Indicator lamp bh 1.00 7 Jack Fireman Intercom bh 1.00 8 Zone addres monitor Module bh 1.00 9 Sounder addres Module bh 1.00

10 Short circuit Isolator bh 1.00 11 Dual I/O Module bh 1.00 12 Terminal Box - FA, F 30 pars unit 1.00 13 Kabel dari Semi addressable ke TB - FA, ttk 24.00

STP 16 AWG 2 pair = NYM 2 x 1,5 mm214 Instalasi Detector ttk 24.00

Page 10: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm 15 Instalasi Bell+ indicator lamp ttk 3.00

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm 16 Instalasi Jeck fireman intercom ttk 1.00 17 Instalasi Addressable Break Glass ttk 1.00

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm18 Instalasi Flow Switch Sprinkler ttk 1.00

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm SUB TOTAL PEKERJAAN SISTEM FIRE ALARM

B6 PEKERJAAN SISTEM TELEKOMUNIKASI1 Outlet Telepon tidak langsung bh 8.00 2 Instalasi Telepon ttk 8.00 3 Handset/Pesawat telephone bh 8.00 4 Terminal Box - T.F 20 pairs unit 1.00 5 Kabel dari MDF - FF ke TB -3 m' 104.00

20 x 2 x 2 x 0,6 mm SUB TOTAL PEKERJAAN SISTEM TELEKOMUNIKASI

B7 PEKERJAAN SISTEM TATA SUARA1 Ceiling Speaker 3 watt bh 16.00 2 Wall speaker 6 watt bh 2.00 3 Volumn kontrol bh 16.00 4 Instalasi Speaker ttk 18.00 5 Instalasi Volume Control ttk 16.00 6 Terminal box TS.F 10 pairs unit 1.00 7 Kabel MDF SS ke TB TS. NYMHY 2 x 3 x 2,5mm2 m' 108.00

SUB TOTAL PEKERJAAN SISTEM TATA SUARA B8 PEKERJAAN CCTV

1 Fixed Dome Camera With Housing unit 4.00 2 Camera Rotary With Housing unit 2.00 3 Instalasi power listrik ( NYYHY 2x1,5 mm) ttk 6.00 4 Instalasi kabel Coaxial RG 11 ttk 6.00 5 Instalasi power listrik ( NYMHY 3x2,5 mm) dari Lt 5 ke Ba m' 54.00 6 Instalasi kabel Coaxial RG 11 dari Lt 5 ke Basement m' 324.00

SUB TOTAL PEKERJAAN CCTV B9 PEKERJAAN MATV

1 Spliter MATV 2 way bh 1.00 2 Spliter MATV 3 way bh 1.00 3 Spliter MATV 4 way bh 1.00 4 Tap Off unit 2 way bh 1.00 5 Tap Off unit 3 way bh 1.00 6 Tap Off unit 4 way bh 1.00 7 Booster MATV bh 1.00 8 Outlet TV bh 8.00 9 TV LCD 21 inchi monitoring unit 2.00

10 Instalasi kabel distribusi dari spliter ke Outlet ttk 8.00 11 Instalasi Power ttk 8.00 12 Instalasi kabel Coaxial RG 11 dari Lt 5 ke Basement m' 54.00

SUB TOTAL PEKERJAAN MATV B10 PEKERJAAN SISTEM KABEL DATA/LAN - OK

1 Outlet Data, incl. Trimping Patch Cord RJ 45 ( dinding) bh 14.00 2 Outlet Data, incl. Trimping Patch Cord RJ 45 ( lantai ) bh 7.00 3 Outlet Power UpS Ceilling (Dinding ) bh 88.00 4 Outlet Power UpS Ceilling (Pendan+Lamp OK + Jam dinding bh 21.00 5 Outlet Power UpS Ceilling (Lantai ) bh 14.00 6 Switch HUB 48 Port unit 1.00 7 Instalasi kabel data ttk 21.00 8 Instalasi kabel Power ttk 123.00 9 Instalasi kabel data cat 6 dr Lantai 3 ke Central m' 756.00

SUB TOTAL PEKERJAAN SISTEM KABEL DATA/LAN

SUB TOTAL PEKERJAAN ELEKTRIKAL LANTAI 3 (OK)

REKAPITULASI PEKERJAAN MEP LANTAI 3 ( OK dan Corridor 1,2,3 )1 SISTEM PENGKONDISIAN UDARA OK2 SISTEM INSTALASI AIR BERISH & AIR PANAS3 SISTEM INSTALASI AIR KOTOR4 SISTEM PEMADAM KEBAKARAN5 SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR

### PEKERJAAN ELEKTRIKAL### PEKERJAAN SISTEM FIRE ALARM### PEKERJAAN SISTEM TELEKOMUNIKASI### PEKERJAAN SISTEM TATA SUARA### PEKERJAAN CCTV

Page 11: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT VOL HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

### PEKERJAAN MATV### PEKERJAAN SISTEM KABEL DATA/LAN

JUMLAH

Page 12: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT. VOL.

III PEKERJAAN MEKANIKAL / ELEKTRIKAL LANTAI 3 OK

A PEKERJAAN MEKANIKALA1 SISTEM PENGKONDISIAN UDARA ( VRF =MULTI SYSTEM)

1 AC MULTI Ceilling consealed ( High static) dan Split Wall termasuk pengkabelan, Pipa Refrigrant isolasi pipa, Nampan & pipa drain1.1 Tipe : Split Duct (Ceilling concealed- High Static)

a Indoor Unit Multi - wall mountedKapasitas : 7500 BTU/h unit 6.00

b Indoor Unit Multi - wall mountedKapasitas : 9600 BTU/h unit 2.00

c Indoor Unit Multi - wall mountedKapasitas : 12 300 BTU/h unit 4.00

d Indoor Unit Multi Ceilling Concealed High staticKapasitas : 24 200 BTU/h unit 20.00

e Indoor Unit Multi Ceilling Concealed High staticKapasitas : 36 200 BTU/h unit 4.00

f Indoor Unit Multi Ceilling Concealed High staticKapasitas : 54 600 BTU/h unit 2.00

g Outdoor Unit Multi V - IVKapasitas : 286 700 BTU/h unit 2.00

h Outdoor Unit Multi V - IVKapasitas : 229 600 BTU/h unit 1.00

1.2 Pekerjaan Pipa Refrigrant1 Y-Branch ARBLN01621 unit 3.00 2 Y-Branch ARBLN03321 unit 8.00 3 Y-Branch ARBLN07121 unit 16.00 4 Y-Branch ARBLN14521 unit 14.00 5 Outdoor Pipe Connection unit 3.00 6 Standard Wired Remote Control unit 26.00 7 Wireless Remocon unit 34.00 8 ACP unit 1.00 9 Penambahan Refrigerant Gas R-410A Kg 120.00

10 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 6.35 mm mtr 106.00 11 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 9.52 mm mtr 186.00 12 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 12.7 mm mtr 133.00 13 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 15.88 mm mtr 224.00 14 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 19.05 mm mtr 102.00 15 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 22.2 mm mtr 184.00 16 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 25.4 mm mtr 12.00 17 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 28.58 mm mtr 15.00 18 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 31.8 mm mtr 133.00 19 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 34.9 mm mtr 65.00 20 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 38.1 mm mtr 172.00 21 Pemipaan Drain AW + Isolasi uk / Dia 1" mtr 228.00 22 Pemipaan Drain AW + Isolasi uk / Dia 2" mtr 216.00 23 Pemipaan Drain AW + Isolasi uk / Dia 3" mtr 15.00 24 Kabel Transmisi Data + Power IU OU mtr 880.00 25 Kabel Power Indoor unit uk NYY 3 x 2,5 mm mtr 860.00 26 Kabel Power Outdoor unit uk 4 x 10 mm mtr 70.00 27 Kabel Power Outdoor unit uk 4 x 16 mm mtr 140.00 28 SAD uk 10"X 10" bh 61.00 29 FAG uk 20"X20" bh 26.00 30 RAG uk 20"x 8" bh 124.00 31 Material Bantu ls 1.00 32 Commisioning (Flushing N2, Vacuum, Pressure Test) unit 36.00

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 13: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.3 Pekerjaan Ducting ACa. Supply Ducting Poliuretane lengkap Isolasi & rangka penggantung ukuran : - 14"x16" m' 12.00 - 14"x14" m' 12.00 - 14"x12" m' 16.00 - 12"x12" m' 44.00 - 12"x10" m' 128.00 - 10"x10" m' 124.00 - Rangka dan Pengantung ls 1.00

b.Return Ducting Puliuretane lengkap Isolasi & rangka penggantung ukuran : Duct Plenum (PxLxT) 32"x26"x14" Polyurethane unit 2.00 Duct Plenum (PxLxT) 32"x20"x14" Polyurethane unit 4.00 Duct Plenum (PxLxT) 28"x16"x14" Polyurethane unit 20.00 - 12"x10" m' 64.00 - 10"x10" m' 146.00 - 10"x8" m' 80.00 - 8"x8" m' 240.00 - 8"x6" m' 160.00 - Rangka dan Pengantung ls 1.00

c.Flexible duct, ukuran : - dia. 10" m' 152.50 - dia. 8" m' 60.00

d.Volume Damper/VD, ukuran : - 14"x16" bh 4.00 - 14"x14" bh 2.00 - 14"x12" bh 4.00 - 12"x12" bh 4.00 - 12"x10" bh 4.00 - 10"x10" bh 46.00

e.Supply Air Difuser/SAD, ukuran: - 12"x12" bh 69.00

f.Relum Air Grille/RAG, ukuran: - 20"x8" bh 124.00 - 16"x8" bh 52.00 - 12"x12" bh 52.00

g.Linear Diffuser/LD, ukuran: - 30"x8" bh 20.00

h.Fresh Air Duct: - 14"x12" m' 4.00 - 12"x10" m' 18.00 - 10"x10" m' 120.00 i.Fresh Air Grille/FAG, ukuran: - 20"x10" bh 131.00 - 14"x12" bh 4.00

Sub Total Pekerjaan Air Condition & Ducting AC B SISTEM VENTILASI

1 Pekerjaan exhaust ducting (termasuk di core)a. Puly uretane lengkap Isolasi & rangka penggantung ukuran:- 20"x14" m' 4.00 - 18"x14" m' 4.00 - 12"x10" m' 39.00 - 8"x6" m' 25.25 - 6"x6" m' 26.50 - 6"x4" m' 68.50

Page 14: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

b.Exhaust Air Grille(EAG),ukuran:- 10"x10" bh 1.00 - 10"x8" bh 33.00

e. Fire Damper(FD), ukuran:- 20"x5" bh 4.00

2 Pekerjaan Exhaust Fan(EF), termasuk pengkabelan2.1 Tipe: In Line Centritugal, dilengkapi dg Automatic

shutter Dumpera. EF 5-2 bh 1.00 Kapasitas :400 CFM Daya :1Ph/220v/50Hz/200Watt

b.EF 5-3 bh 1.00 Kapasitas :600CFM Daya: 1Ph/220v/50Hz/40Watt

2.2 Tipe: Ceiling Mounteda. EF 5 bh 9.00 Kapasitas: 600 CFM Daya: 1Ph/220v/50Hz/40Watt

b. EF 5-1 bh 1.00 Kapasitas: 250 CFM Daya: 1Ph/220v/50Hz/40Wattc. Instalasi EF ttk 12.00

2.3 Testing & commissioning is 1.00 Sub Total Pekerjaan Ventilasi AC

SUB TOTAL SISTEM PENGKONDISIAN UDARA( HVAC LANTAI 5 )

C SISTEM INSTALASI AIR BERISH & AIR PANAS1 Pompa air bersih

1.1 Polypropylene(PPR-Plpe) PN-10 incl.Support1 - dia. 100 mm(4") m' - 2 - dia. 80 mm(3") m' 0.60 3 - dia. 50 mm(2") m' 36.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 282.00 8 - Fitting & aksesories is 1.00

Polypropylene Piep (PPR) klas PN-20 incl. Isolasi support1 - dia. 80 mm(3") m' 14.00 2 - dia. 65 mm (2 1/2") m' 152.00 3 - dia. 50 mm (2") m' 4.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 282.00 8 - Fitting & aksesories is 1.00

1.2 Valve & aksesories1.2.1 Gate valve :

1 - dia 65 mm(2 1/2") bh 4.00 2 - dia 50 mm(2") bh 12.00 3 - dia 40 mm(1 1/2") bh 6.00 4 - dia 25 mm(1") bh 56.00 5 - dia 20 mm(3/4") bh 28.00 6 -dia 15 mm(1/2") bh -

1.2.1 Chek valve : 1 Chek valve : 65 mm ( 2 1/2" ) bh 2.00 2 Chek valve : 25 mm ( 1" ) bh 4.00 3 Chek valve : 25 mm ( 3/4" ) bh 20.00

1.3 Testing & Commissioning is 1.00 SUB TOTAL SISTEM INSTALASI AIR BERISH & AIR PANAS LANTAI 5 )

Page 15: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

B SISTEM INSTALASI AIR KOTOR1 Pompaan Air Kotor & Air Buangan

1.1 Polivinyt Chlorida pipe(PVC) klas 10kg/cm2 incl. Support1 - dia 150mm (6") m' 0.90 2 - dia 100mm (4") m' 15.60 3 - dia 80mm (3") m' 9.40 4 - dia 50mm (2") m' 139.50 5 '- Fitting & aksesories m' 1.00

is1.2 Pemipaan Vent

Polivinyt Chlorida Pipe(PVC) klass 10kg/cm2 incl. Support1 - dia 80mm (3") m' 10.00 2 - dia 50mm (2") m' 82.00 3 - Fitting & aksesories is 1.00

1.3 Sanitair1 -Clean Out(CO) 4" air kotor bh 37.00 2 -Clean Out(CO) 2 1/2" air bekas bh 37.00 3 -Floor Drain(FD) 2 1/2" bh 52.00 4 Testing & Commissioning is 1.00

SUB TOTAL SISTEM INSTALASI AIR KOTOR 5

D SISTEM PEMADAM KEBAKARANPekerjaan Instalasi Hidrant dan Springkler

1 Pemipaan1.1 Pemipaan BSP, nch 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 60mm(3") m' 0.40 -dia. 65mm(2 1/2") m' 5.80 -dia. 50mm(2") m' 105.00 Fitting & aksessories is 1.00

1.2 Valve- Gate valve,dia. 80mm(3") bh 1.00

1.3 Hydrant box(Tipe B/indoor) Tanpa box, accsories lengkap unit 4.00 Roll fire, Hydrant Valve, Jet Nosle,Hose Rack 1,5"

1.4 Tabung kebakaran fire extinguisher1.4.1 FE, Tipe ABC Dry Chemical

-Kapasitas: 4kg bh 11.00

1.5 Testing & commissioning is 1.00

Pekerjaan Instalasi Sprinkler2.1 Head Sprinkler

-Tipe pendant bh 125.00

2.2 Pemipaan2.2.1 Black steel pipe(BSP) ach. 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 100mm(4") m' 0.40 -dia. 80mm(3") m' 3.60 -dia. 65mm(2 1/2") m' 3.00 -dia. 50mm(2") m' 11.34 -dia. 40mm(1 1/2") m' 66.30 -dia. 32mm(1 1/4") m' 122.40 -dia. 25mm(1") m' 228.25 -Fitting & aksessories is 1.00

2.2.2 Valve-Butterfly valve,dia. 100 mm(4") PN 16 bh 1.00 Branch Control Valve ( BCV) 4" lengkap : bh 1.00 Pressure Reducing Valve 4 " ( PRV ) bh 2.00

2.2.3 Flow Switch bh 1.00

Page 16: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

2.3 Pipa drain :Pollyint Chloride Pipe(PVC) klas 10kg/cm2-dia. 50mm(2") m' 4.00 -dia. 25mm(1") m' 82.00 -Fitting & aksessories is 1.00

2.3.2 Valve:-Gate valve dia. 25mm(1") bh 2.00

2.4 Testing & Commisioning is 1.00 SUB TOTAL SISTEM PEMADAM KEBAKARAN 5

E SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR LANTAI 5A PEKERJAAN INSTALASI DALAM BANGUAN1 Instalasi Jaringan Oxygen

Pipa Tembaga ASTM 819 Type L1 Diameter3/8" m' 312.00 2 Diameter 1/2" m' 285.00 3 Diameter 5/8" m' 66.00 4 Diameter 3/4" m' 64.00 5 Diameter 7/8" m' 68.00 6 Diameter 1 1/8" m' 12.00 7 Fitting da Accessories Ls 1.00

4 Instalasi Jaringan VacuumPipa Tembaga ASTM 819 Type L

1 Diameter 1/2" m' 312.00 2 Diameter 5/8" m' 285.00 3 Diameter 3/4" m' 66.00 4 Diameter 7/8" m' 64.00 5 Diameter 1 1/8" m' 68.00 6 Diameter 1 3/8" m' 12.00 7 Fitting da Accessories Ls 1.00

SUB TOTAL INSTALASI DALAM BANGUANN

5 PERALATAN DALAM RUANGAN 1 Wall Outlet Oxygen (O), pin index, push type buah 104.00 2 Wall Outlet Vacuum (V), pin index, push type, slide base buah 104.00 3 Zona Valve 2 Gas (O, V) set 2.00 4 Area Alarm 2 Gas (O,V) unit 2.00 5 Bedhead Unit, Aluminium, L=1200 mm buah 104.00 6 Testing & Kommisioning Ls 1.00

SUB TOTAL PERALATAN DALAM BANGUANN

SUB TOTAL SISTEM INSTALASI GAS, VACUUM & CIMPRESSED AIR LANTAI 5 SUB TOTAL PEKERJAAN MEKANIKAL LANTAI 5

II PEKERJAAN ELEKTRIKAL1 PEKERJAAN PANEL DAYA1.1 Panel LP -5A unit 1.00 1.2 Panel LP -5B unit 1.00 1.3 Panel LP -5C unit 1.00 1.4 Panel PPS -5A unit 1.00 1.5 Panel PPS -5B unit 1.00 1.6 Panel PPS -5C unit 1.00 1.6 Panel SDP -5 unit 1.00 1.7 Panel MDP -5 unit 1.00 1.8 Panel Indoor AC 5 unit 1.00 1.9 Panel Outdoor AC 5 unit 1.00

1. 10 Panel MDP 9 AC unit 1.00 1.11 Panel Outdoor AC 9 Multi Lantai atap LT 4 unit 1.00 1.12 Panel Outdoor AC 9 Emergency Lantai atap lantai 4 unit 1.00

SUB TOTAL PEKERJAAN PANEL DAYA Lt 5 2 PEKERJAAN KABEL2.1 Kabel dari Panel LVMDP ke panel MDP 5,

NYFGBY 4 x ( 4x300 mm2) +NYA 300 mm2 m' 164.00 2.2 Kabel dari Panel MDP - 5 ke panel SDP 5,

Page 17: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

NYY 4 x 70 mm2 +NYA 50 mm2 m' 10.00 2.3 Kabel dari Panel SDP - 5 ke panel LP 5A,

NYY 4 x 10 mm2 +NYA 10 mm2 m' 62.00 2.4 Kabel dari Panel SDP - 5 ke panel LP 5B,

NYY 4 x 10 mm2 +NYA 10 mm2 m' 6.00 2.5 Kabel dari Panel SDP - 5 ke panel LP 5C,

NYY 4 x 10 mm2 +NYA 10 mm2 m' 62.00 2.6 Kabel dari Panel SDP - 5 ke panel PP ST 5A,

NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00 2.7 Kabel dari Panel SDP - 5 ke panel PP ST 5B

NYY 4 x 16 mm2 +NYA 16 mm2 m' 6.00 2.8 Kabel dari Panel SDP - 5 ke panel PP ST 5C

NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00 2.9 Kabel dari Panel MDP - 5 ke panel PP AC Outdoor 5

NYY 4 x 70 mm2 +NYA 50 mm2 m' 48.00 2.1 0 Kabel dari Panel MDP - 5 ke panel PP AC Outdoor 5( Emergency)

NYY 4 x 70 mm2 +NYA 50 mm2 m' 48.00 2.11 Kabel dari Panel MDP 5 ke Panel MDP 9 AC

NYY 2x4x1 x185 mm2 +NYA 185 mm2 m' 40.00 2.12 Kabel dari Panel MDP 9 ke Panel AC OUTOOR Multi Lt 5

NYY 4 x 150 mm2 +NYA 150 mm2 m' 35.00 2.13 Kabel dari Panel MDP 9 ke Panel AC OUTOOR Emergency Lt 5

NYY 4 x 50 mm2 +NYA 50 mm2 m' 35.00

SUB TOTAL PEKERJAAN KABEL Lt 5

3 PEKERJAAN KABEL TRAY & KABEL LADDERRak kabel termasuk support

3.1 -Kabel ladder elektrikal 300x100 mm m' 27.50 3.2 -Kabel ladder elektronik 200x100 mm m' 27.50

SUB TOTAL PEKERJAAN KABEL TRAY DAN KABEL LADDER Lt 5 4 PEKERJAAN LAMPU PENERANGAN, TITIK

OUTLET, STOP KONTAK DAN SAKLARTERMASUK KONDUIT

1 RM 300 2x36 M4, TL LED ESS 16 W bh 27.00 2 RM 300 2x36 M4, TL LED ESS 16 W+ Batt ( On 1 lamp) bh 11.00 3 RM 300 1x36 ACR TL LED ESS 16 W bh 102.00 4 BL T4 1X 20 W bh 102.00 5 Weatherproof Elektra 2x 36 PC TL LED 16 W bh 14.00 6 RMO 2X36 TL LED ESS 16 W bh 8.00 7 GMS TP 1X 36 ACR, TL LED ESS 16 W bh 3.00 8 GMS TP 1X 36 ACR, TL LED ESS 16 W + Batt bh 3.00 9 Theme 150 -70- E 27 LED Bulb 10 W bh 78.00

10 Theme 150 -70- E 27 LED Bulb 10 W + Batt bh 24.00 11 Theme 150 -70- E 27 LED Bulb 7 W bh 61.00 12 BL CG 1X 36 TL LED ESS 16 W bh 6.00 13 Exit Green LED H 1+ Battery bh 3.00 14 Grid Switch 6 gang bh 2.00 15 Saklar Tunggal 16 A, 1 phasa bh 90.00 16 Saklar Ganda 16 A, 1 phasa bh 82.00 17 Saklar Ganda 16 A, 1 phasa ( Bed head ) bh 102.00 18 Saklar Hotel Tunggal 16 A, 1 phasa bh 3.00 19 Stop kontak 16 A, 1phasa (Bed Head ) bh 204.00 20 Stop kontak 16 A, 1phasa (dinding/Kantor Corridor)) bh 61.00 21 Instalasi Penerangan ttk 176.80 22 Instalasi stop kontak 1 phase ttk 106.00

SUB TOTAL PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR SUB TOTAL PEKERJAAN LISTRIK LANTAI 5

5 PEKERJAAN SISTEM FIRE ALARM1 Photo Electronic Smoke Detector bh 62.00 2 Rate of Rise heat detector bh 4.00 3 Fixed Temp Heat Detector bh 2.00 4 Alarm Bell 6" bh 3.00 5 Manual Puab Bulton bh 3.00 6 Indicator lamp bh 3.00 7 Jack Fireman Intercom bh 3.00

Page 18: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

8 Zone addres monitor Module bh 4.00 9 Sounder addres Module bh 4.00

10 Short circuit Isolator bh 2.00 11 Dual I/O Module bh 2.00 12 Terminal Box - FA, F 30 pars unit 1.00 13 Kabel dari Semi addressable ke TB - FA,

STP 16 AWG 2 pair + NYM 2 x 1,5 mm2 ttk 6.00 14 Instalasi Detector

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 68.00 15 Instalasi Bell+ indicator lamp

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 9.00 16 Instalasi Jeck fireman intercom ttk 3.00 17 Instalasi Addressable Break Glass

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 3.00 18 Instalasi Flow Switch Sprinkler

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 2.00 SUB TOTAL PEKERJAAN SISTEM FIRE ALARM 5

6 PEKERJAAN SISTEM TELEKOMUNIKASI1 Outlet Telepon tidak langsung bh 4.00 2 Instalasi Telepon ttk 0.80 3 Hanset/Pesawat telephone bh 4.00 4 Terminal Box - T.F 20 pairs unit 1.00 5 Kabel dari MDF - FA ke TB - T, E Steal K 011 m' 66.00

20 x 2 x 2 x 0,6 mm SUB TOTAL PEKERJAAN SISTEM TELEKOMUNIKASI 5

7 PEKERJAAN SISTEM TATA SUARA1 Ceiling Speaker 3 watt bh 50.00 2 Wall speaker 6 watt bh 3.00 3 Volumn kontrol 3 watt bh 38.00 4 Volumn kontrol 30 watt bh 2.00 5 Instalasi Speaker ttk 10.60 6 Instalasi Volume Control ttk 10.60 7 Terminal box TS.F 10 pairs unit 1.00 8 Kabel MDF SS ke TB TS. NYMHY 2 3 x 2,5mm2 m' 132.00

SUB TOTAL PEKERJAAN SISTEM TATA SUARA 5 8 PEKERJAAN SISTEM NURSE CALL ( ONE WAY )a NURSE STATION A

1 Bedcall Socket c/w Reset Button - BCB107RUE unit 50.00 2 Handheld Call Pendant - RCB822 unit 50.00 3 Bathroom c/w Pullcord with cancel -BCT302ZRE/BCR302AE unit 20.00 4 Lampu Indikator / Lamp Indicator 1 Color -BLC673UE8 unit 30.00 5 Central Processor with power Supplay 40 CH ICRC - 40E unit 1.00 6 Central Processor with power Supplay 10 CH ICRC - 10E unit 1.00 7 Reset Button unit 10.00 8 Nurse call Instalasion ttk 150.00

b NURSE STATION B1 Bedcall Socket c/w Reset Button - BCB107RUE unit 50.00 2 Handheld Call Pendant - RCB822 unit 50.00 3 Bathroom c/w Pullcord with cancel -BCT302ZRE/BCR302AE unit 20.00 4 Lampu Indikator / Lamp Indicator 1 Color -BLC673UE8 unit 30.00 5 Central Processor with power Supplay 40 CH ICRC - 40E unit 1.00 6 Central Processor with power Supplay 10 CH ICRC - 10E unit 1.00 7 Reset Button unit 10.00 8 Nurse call Instalasion ttk 150.00

SUB TOTAL PEKERJAAN SISTEM NURSE CALL 5 9 PEKERJAAN CCTV

1 Fixed Dome Camera With Housing unit 6.00 2 Camera Rotary With Housing unit 2.00 3 Instalasi power listrik ( NYM 2x1,5 mm) ttk 8.00 4 Instalasi kabel Coaxial RG 11 ttk 8.00 5 Instalasi power listrik ( NYM 3x2,5 mm) drLt 5 ke BS m' 66.00 6 Instalasi kabel Coaxial RG 11 dari Lt 5 ke BS m' 528.00

SUB TOTAL PEKERJAAN CCTV 5

Page 19: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

10 PEKERJAAN MATV1 Spliter MATV 2 way bh 1.00 2 Spliter MATV 3 way bh 2.00 3 Spliter MATV 4 way bh 3.00 4 Tap Off unit 2 way bh 1.00 5 Tap Off unit 3 way bh 2.00 6 Tap Off unit 4 way bh 3.00 7 Booster MATV bh 5.00 8 Outlet TV bh 28.00 9 TV LCD 17 inch Monitoring ( Rawat inap ) unit - - By Owner

10 TV LCD 21 inch Monitoring ( Nurse StationRawat inap ) unit 2.00 11 Instalasi kabel distribusi dari spliter ke Outlet ttk 28.00 12 Instalasai Power ttk 28.00 13 Instalasai Coaxial RG 11 dr LT 5 ke Lt BS m' 66.00

SUB TOTAL PEKERJAAN MATV 5 11 PEKERJAAN SISTEM KABEL DATA/LAN

1 Outlet Data, icl. Trimping Patch Cord RJ 45 ( dinding) bh 6.00 2 Outlet Data, icl. Trimping Patch Cord RJ 45 ( ltai) bh - 3 Outlet Power UPS ( dinding) bh 6.00 4 Outlet Power UPS ( lantai ) bh - 5 Switch HUB 48 Port unit 1.00 6 Instalasi kabel data ttk 6.00 7 Instalasi kabel Power bh 6.00 8 Instalasi kabel data cat 6 dari lantai 5 ke Lt Central unit 396.00

SUB TOTAL PEKERJAAN SISTEM KABEL DATA/LAN 5SUB TOTAL PEKERJAAN ELEKTRIKAL LANTAI 5

REKAPITULASI PEKERJAAN MEP LANTAI 51 SISTEM PENGKONDISIAN UDARA ( VRF /MULTI SYSTEM)2 SISTEM INSTALASI AIR BERISH & AIR PANAS3 SISTEM INSTALASI AIR KOTOR4 SISTEM PEMADAM KEBAKARAN5 SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR6 PEKERJAAN ELEKTRIKAL7 PEKERJAAN SISTEM FIRE ALARM

8 PEKERJAAN SISTEM TELEKOMUNIKASI9 PEKERJAAN SISTEM TATA SUARA

10 PEKERJAAN SISTEM NURSE CALL11 PEKERJAAN CCTV12 PEKERJAAN MATV13 PEKERJAAN SISTEM KABEL DATA/LAN

JUMLAH

Page 20: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT. VOL.

LANTAI 6I PEKERJAAN MEKANIKAL

A1 SISTEM PENGKONDISIAN UDARA ( VRF =MULTI SYSTEM)1 AC MULTI Ceilling consealed ( High static) dan Split Wall termasuk pengkabelan, Pipa Refrigrant isolasi pipa, Nampan & pipa drain

1.1 Tipe : Split Duct (Ceilling concealed- High Static) a Indoor Unit Multi - wall mounted

Kapasitas : 7500 BTU/h unit 6.00 b Indoor Unit Multi - wall mounted

Kapasitas : 9600 BTU/h unit 2.00 c Indoor Unit Multi - wall mounted

Kapasitas : 12 300 BTU/h unit 4.00 d Indoor Unit Multi

Ceilling Concealed High staticKapasitas : 24 200 BTU/h unit 18.00

e Indoor Unit Multi Ceilling Concealed High staticKapasitas : 36 200 BTU/h unit 4.00

f Indoor Unit Multi Ceilling Concealed High staticKapasitas : 54 600 BTU/h unit 2.00

g Outdoor Unit Multi V - IVKapasitas : 267.000 BTU/h unit 2.00

h Outdoor Unit Multi V - IVKapasitas : 229 600 BTU/h unit 1.00

1.2 Pekerjaan Pipa Refrigrant1 Y-Branch ARBLN01621 unit 3.00 2 Y-Branch ARBLN03321 unit 8.00 3 Y-Branch ARBLN07121 unit 16.00 4 Y-Branch ARBLN14521 unit 14.00 5 Outdoor Pipe Connection unit 5.00 6 Standard Wired Remote Control unit 8.00 7 Wireless Remocon unit 34.00 8 ACP unit 1.00 9 Penambahan Refrigerant Gas R-410A Kg 120.00

10 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 6.35 mm mtr 106.00 11 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 9.52 mm mtr 186.00 12 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 12.7 mm mtr 133.00 13 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 15.88 mm mtr 224.00 14 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 19.05 mm mtr 102.00 15 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 22.2 mm mtr 184.00 16 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 25.4 mm mtr 12.00 17 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 28.58 mm mtr 15.00 18 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 31.8 mm mtr 133.00 19 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 34.9 mm mtr 60.00 20 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 38.1 mm mtr 172.00 21 Pemipaan Drain AW + Isolasi uk / Dia 1" mtr 216.00 22 Pemipaan Drain AW + Isolasi uk / Dia 2" mtr 275.00 23 Pemipaan Drain AW + Isolasi uk / Dia 3" mtr 16.00 24 Kabel Transmisi Data + Power IU OU mtr 840.00 25 Kabel Power Indoor unit uk NYY 3 x 2,5 mm mtr 812.00 26 Kabel Power Outdoor unit uk 4 x 10 mm mtr 112.00 27 Kabel Power Outdoor unit uk 4 x 16 mm mtr - 28 SAD uk 10"X 10" bh 61.00 29 FAG uk 20"X20" bh 26.00 30 RAG uk 20"x 8" bh 124.00 31 Material Bantu ls 1.00 32 Commisioning (Flushing N2, Vacuum, Pressure Test) unit 36.00

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 21: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.3 Pekerjaan Ducting ACa. Supply Ducting Puly uretane lengkap Isolasi & rangka penggantung ukuran : - 14"x16" m' 12.00 - 14"x14" m' 12.00 - 14"x12" m' 16.00 - 12"x12" m' 44.00 - 12"x10" m' 128.00 - 10"x10" m' 124.00 - Rangka dan Pengantung ls 1.00

b.Retum Ducting Puly uretane lengkap Isolasi & rangka penggantung ukuran : Duct Plenum (PxLxT) 32"x26"x14" Polyurethane unit 2.00 Duct Plenum (PxLxT) 32"x20"x14" Polyurethane unit 4.00 Duct Plenum (PxLxT) 28"x16"x14" Polyurethane unit 20.00 - 12"x10" m' 64.00 - 10"x10" m' 146.00 - 10"x8" m' 80.00 - 8"x8" m' 240.00 - 8"x6" m' 160.00 - Rangka dan Pengantung ls 1.00

c.Flexible duct, ukuran : - dia. 10" m' 152.50 - dia. 8" m' 60.00

d.Volume Damper/VD, ukuran : - 14"x16" bh 4.00 - 14"x14" bh 2.00 - 14"x12" bh 4.00 - 12"x12" bh 4.00 - 12"x10" bh 4.00 - 10"x10" bh 46.00

e.Supply Air Difuser/SAD, ukuran: - 12"x12" bh 69.00

f.Relum Air Grille/RAG, ukuran: - 20"x8" bh 124.00 - 16"x8" bh 52.00 - 12"x12" bh 52.00

g.Linear Diffuser/LD, ukuran: - 30"x8" bh 20.00

h.Fresh Air Duct: - 14"x12" m' 4.00 - 12"x10" m' 18.00 - 10"x10" m' 120.00 i.Fresh Air Grille/FAG, ukuran: - 20"x10" bh 131.00 - 14"x12" bh 4.00

Sub Total Pekerjaan Air Condition & Ducting AC Lt 6 B SISTEM VENTILASI

1 Pekerjaan exhaust ducting (termasuk di core)a. Puly uretane lengkap Isolasi & rangka penggantung ukuran:- 20"x14" m' 4.00 - 18"x14" m' 4.00 - 12"x10" m' 39.00 - 8"x6" m' 25.25 - 6"x6" m' 26.50 - 6"x4" m' 68.50

b.Exhaust Air Grille(EAG),ukuran:- 10"x10" bh 1.00 - 10"x8" bh 33.00

Page 22: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

e. Fire Damper(FD), ukuran:- 20"x5" bh 4.00

2 Pekerjaan Exhaust Fan(EF), termasuk pengkabelan2.1 Tipe: In Line Centritugal, dilengkapi dg Automatic

shutter Dumpera. EF 5-2 bh 1.00 Kapasitas :400 CFM Daya :1Ph/220v/50Hz/200Watt

b.EF 5-3 bh 1.00 Kapasitas :600CFM Daya: 1Ph/220v/50Hz/40Watt

2.2 Tipe: Ceiling Mounteda. EF 5 bh 9.00 Kapasitas: 600 CFM Daya: 1Ph/220v/50Hz/40Watt

b. EF 5-1 bh 1.00 Kapasitas: 250 CFM Daya: 1Ph/220v/50Hz/40Wattc. Instalasi EF ttk 12.00

2.3 Testing & commissioning is 1.00 Sub Total Pekerjaan Ventilasi AC

SUB TOTAL SISTEM PENGKONDISIAN UDARA( HVAC LANTAI 6 )

C SISTEM INSTALASI AIR BERISH & AIR PANAS1 Pompa air bersih

1.1 Polypropylene(PPR-Plpe) PN-10 incl.Support1 - dia. 100 mm(4") m' - 2 - dia. 80 mm(3") m' 2.40 3 - dia. 50 mm(2") m' 36.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 276.00 8 - Fitting & aksesories is 1.00

Polypropylene Piep (PPR) klas PN-20 incl. Isolasi support1 - dia. 80 mm(3") m' - 2 - dia. 65 mm (2 1/2") m' 158.00 3 - dia. 50 mm (2") m' 4.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 72.00 8 - Fitting & aksesories is 1.00

1.2 Valve & aksesories1.2.1 Gate valve :

1 - dia 65 mm(2 1/2") bh 4.00 2 - dia 50 mm(2") bh 12.00 3 - dia 40 mm(1 1/2") bh 6.00 4 - dia 25 mm(1") bh 56.00 5 - dia 20 mm(3/4") bh 28.00 6 -dia 15 mm(1/2") bh -

1.2.1 Chek valve : 1 Chek valve : 65 mm ( 2 1/2" ) bh 2.00 2 Chek valve : 25 mm ( 1" ) bh 4.00 3 Chek valve : 25 mm ( 3/4" ) bh 20.00

1.3 Testing & Commissioning is 1.00 SUB TOTAL SISTEM INSTALASI AIR BERISH & AIR PANAS LANTAI 6

B SISTEM INSTALASI AIR KOTOR1 Pompaan Air Kotor & Air Buangan

1.1 Polivinyt Chlorida pipe(PVC) klas 10kg/cm2 incl. Support1 - dia 150mm (6") m' 0.90 2 - dia 100mm (4") m' 15.60 3 - dia 80mm (3") m' 94.00 4 - dia 50mm (2") m' 139.50

Page 23: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

5 '- Fitting & aksesories m' 1.00 is

Page 24: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.2 Pemipaan VentPolivinyt Chlorida Pipe(PVC) klass 10kg/cm2 incl. Support

1 - dia 80mm (3") m' 10.00 2 - dia 50mm (2") m' 82.00 3 - Fitting & aksesories is 1.00

1.3 Sanitair:-Clean Out(CO) 4" air kotor bh 37.00 -Clean Out(CO) 2 1/2" air bekas bh 37.00 -Floor Drain(FD) 2 1/2" bh 52.00 Testing & Commissioning is 1.00

SUB TOTAL SISTEM INSTALASI AIR KOTOR 6

D SISTEM PEMADAM KEBAKARANPekerjaan Instalasi Hidrant dan Springkler

1 Pekerjaan Instalasi Hidrant1.1 Pemipaan BSP, nch 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 60mm(3") m' 0.40 -dia. 65mm(2 1/2") m' 5.80 -dia. 50mm(2") m' 105.00 Fitting & aksessories is 1.00

1.2 Valve- Gate valve,dia. 80mm(3") bh 1.00

1.3 Hydrant box(Tipe B/indoor) Tanpa box, accsories lengkap unit 4.00 Roll fire, Hydrant Valve, Jet Nosle,Hose Rack 1,5"

1.4 Tabung kebakaran fire extinguisher1.4.1 FE, Tipe ABC Dry Chemical

-Kapasitas: 4kg bh 11.00

1.5 Testing & commissioning is 1.00

2 Pekerjaan Instalasi Sprinkler2.1 Head Sprinkler

-Tipe pendant bh 125.00

2.2 Pemipaan2.2.1 Black steel pipe(BSP) ach. 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 100mm(4") m' 0.40 -dia. 80mm(3") m' 3.60 -dia. 65mm(2 1/2") m' 3.00 -dia. 50mm(2") m' 11.34 -dia. 40mm(1 1/2") m' 66.30 -dia. 32mm(1 1/4") m' 122.40 -dia. 25mm(1") m' 228.25 -Fitting & aksessories is 1.00

2.2.2 Valve:-Butterfly valve,dia. 100 mm(4") PN 16 bh 1.00 Branch Control Valve ( BCV) 4" lengkap : bh 1.00 Pressure Reducing Valve 4 " ( PRV ) bh 2.00

2.2.3 Flow Switch bh 1.00

2.3 Pipa drain :Pollyint Chloride Pipe(PVC) klas 10kg/cm2-dia. 50mm(2") m' 4.00 -dia. 25mm(1") m' 82.00 -Fitting & aksessories is 1.00

2.3.2 Valve:-Gate valve dia. 25mm(1") bh 2.00

2.4 Testing & Commisioning is 1.00 SUB TOTAL SISTEM PEMADAM KEBAKARAN 6

Page 25: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

E SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR LANTAI 6A PEKERJAAN INSTALASI DALAM BANGUAN1 Instalasi Jaringan Oxygen

Pipa Tembaga ASTM 819 Type L1 Diameter3/8" m' 228.00 2 Diameter 1/2" m' 101.00 3 Diameter 5/8" m' 88.00 4 Diameter 3/4" m' 44.00 5 Diameter 7/8" m' 41.00 6 Diameter 1 1/8" m' 12.00 7 Fitting da Accessories Ls 1.00

4 Instalasi Jaringan VacuumPipa Tembaga ASTM 819 Type L

1 Diameter 1/2" m' 228.00 2 Diameter 5/8" m' 101.00 3 Diameter 3/4" m' 88.00 4 Diameter 7/8" m' 44.00 5 Diameter 1 1/8" m' 41.00 6 Diameter 1 3/8" m' 12.00 7 Fitting da Accessories Ls 1.00

SUB TOTAL INSTALASI DALAM BANGUANN

5 PERALATAN DALAM RUANGAN 1 Wall Outlet Oxygen (O), pin index, push type buah 94.00

2 Wall Outlet Vacuum (V), pin index, push type, slide base buah 94.00

3 Zona Valve 2 Gas (O, V) set 2.00

4 Area Alarm 2 Gas (O,V) unit 2.00

5 Bedhead Unit, Aluminium, L=1200 mm buah 94.00 6 Testing & Kommisioning Ls 1.00

SUB TOTAL PERALATAN DALAM BANGUANN

SUB TOTAL SISTEM INSTALASI GAS, VACUUM & CIMPRESSED AIR LANTAI 6 SUB TOTAL PEKERJAAN MEKANIKAL LANTAI 6

II PEKERJAAN ELEKTRIKAL1 PEKERJAAN PANEL DAYA1.1 Panel LP -6A unit 1.00 1.2 Panel LP -6B unit 1.00 1.3 Panel LP -6C unit 1.00 1.4 Panel PPS -6A unit 1.00 1.5 Panel PPS -6B unit 1.00 1.6 Panel PPS -6C unit 1.00 1.6 Panel SDP -6 unit 1.00 1.7 Panel Indoor AC 6,7,8 AC Multi unit 1.00

SUB TOTAL PEKERJAAN PANEL DAYA 6

2 PEKERJAAN KABEL 2.1 Kabel dari Panel LVMDP ke panel MDP 6 m' -

NYFGBY 4 x ( 4x300 mm2) +NYA 300 mm22.2 Kabel dari Panel MDP - 5 ke panel SDP 6 m' 10.00

NYY 4 x 70 mm2 +NYA 50 mm2

2.3 Kabel dari Panel SDP - 6 ke panel LP 6A, m' 62.00 NYY 4 x 10 mm2 +NYA 10 mm2

2.4 Kabel dari Panel SDP - 6 ke panel LP 6B, m' 6.00 NYY 4 x 10 mm2 +NYA 10 mm2

2.5 Kabel dari Panel SDP - 6 ke panel LP 6C, m' 62.00 NYY 4 x 10 mm2 +NYA 10 mm2

2.6 Kabel dari Panel SDP - 6 ke panel PP ST 6A,NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00

2.7 Kabel dari Panel SDP - 6 ke panel PP ST 6BNYY 4 x 16 mm2 +NYA 16 mm2 m' 6.00

2.8 Kabel dari Panel SDP - 6 ke panel PP ST 6CNYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00

2.9 Kabel dari Panel SDP - 6 ke panel PP AC Indoor multi 6NYY 4 x 6 mm2 +NYA 6 mm2 m' 48.00

SUB TOTAL PEKERJAAN KABEL 6

Page 26: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

3 PEKERJAAN KABEL TRAY & KABEL LADDERRak kabel termasuk support

3.1 -Kabel ladder elektrikal 300x100 mm m' 27.50 3.2 -Kabel ladder elektronik 200x100 mm m' 27.50

SUB TOTAL PEKERJAAN KABEL TRAY DAN KABEL LADDER 6

4 PEKERJAAN LAMPU PENERANGAN, TITIKOUTLET, STOP KONTAK DAN SAKLARTERMASUK KONDUIT

1 RM 300 2x36 M4, TL LED ESS 16 W bh 27.00 2 RM 300 2x36 M4, TL LED ESS 16 W+ Batt ( On 1 lamp) bh 11.00 3 RM 300 1x36 ACR TL LED ESS 16 W bh 82.00 4 BL T4 1X 20 W bh 82.00 5 Weatherproof Elektra 2x 36 PC TL LED 16 W bh 14.00 6 RMO 2X36 TL LED ESS 16 W bh 8.00 7 GMS TP 1X 36 ACR, TL LED ESS 16 W bh 3.00 8 GMS TP 1X 36 ACR, TL LED ESS 16 W + Batt bh 3.00 9 Theme 150 -70- E 27 LED Bulb 10 W bh 78.00

10 Theme 150 -70- E 27 LED Bulb 10 W + Batt bh 24.00 11 Theme 150 -70- E 27 LED Bulb 7 W bh 61.00 12 BL CG 1X 36 TL LED ESS 16 W bh 6.00 13 Exit Green LED H 1+ Battery bh 3.00 14 Grid Switch 6 gang bh 2.00 15 Saklar Tunggal 16 A, 1 phasa bh 88.00 16 Saklar Ganda 16 A, 1 phasa bh 76.00 17 Saklar Ganda 16 A, 1 phasa ( Bed head ) bh 92.00 18 Saklar Hotel Tunggal 16 A, 1 phasa bh 3.00 19 Stop kontak 16 A, 1phasa (Bed Head ) bh 184.00 20 Stop kontak 16 A, 1phasa (dinding/Kantor Corridor)) bh 56.00 21 Instalasi Penerangan ttk 160.80 22 Instalasi stop kontak 1 phase ttk 96.00

SUB TOTAL PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR SUB TOTAL PEKERJAAN LISTRIK LANTAI 6

5 PEKERJAAN SISTEM FIRE ALARM1 Photo Electronic Smoke Detector bh 62.00 2 Rate of Rise heat detector bh 4.00 3 Fixed Temp Heat Detector bh 2.00 4 Alarm Bell 6" bh 3.00 5 Manual Puab Bulton bh 3.00 6 Indicator lamp bh 3.00 7 Jack Fireman Intercom bh 3.00 8 Zone addres monitor Module bh 4.00 9 Sounder addres Module bh 4.00

10 Short circuit Isolator bh 2.00 11 Dual I/O Module bh 2.00 12 Terminal Box - FA, F 30 pars unit 1.00 13 Kabel dari Semi addressable ke TB - FA,

STP 16 AWG 2 pair + NYM 2 x 1,5 mm2 ttk 6.00 14 Instalasi Detector

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 68.00 15 Instalasi Bell+ indicator lamp

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 9.00 16 Instalasi Jeck fireman intercom ttk 3.00 17 Instalasi Addressable Break Glass

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 3.00 18 Instalasi Flow Switch Sprinkler

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 2.00 SUB TOTAL PEKERJAAN SISTEM FIRE ALARM LANTAI 6

6 PEKERJAAN SISTEM TELEKOMUNIKASI1 Outlet Telepon tidak langsung bh 4.00 2 Instalasi Telepon ttk 4.00 3 Hanset/Pesawat telephone bh 4.00 4 Terminal Box - T.F 20 pairs unit 1.00 5 Kabel dari MDF - FA ke TB - T, E Steal K 011 m' 72.00

20 x 2 x 2 x 0,6 mm SUB TOTAL PEKERJAAN SISTEM TELEKOMUNIKASI 6

Page 27: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

7 PEKERJAAN SISTEM TATA SUARA1 Ceiling Speaker 3 watt bh 50.00 2 Wall speaker 6 watt bh 3.00 3 Volumn kontrol 3 watt bh 38.00 4 Volumn kontrol 30 watt bh 2.00 5 Instalasi Speaker ttk 53.00 6 Instalasi Volume Control ttk 41.00 7 Terminal box TS.F 10 pairs unit 1.00 8 Kabel MDF SS ke TB TS. NYMHY 2 3 x 2,5mm2 m' 144.00

SUB TOTAL PEKERJAAN SISTEM TATA SUARA LANTAI 6 8 PEKERJAAN SISTEM NURSE CALL ( ONE WAY )a NURSE STATION A

1 Bedcall Socket c/w Reset Button - BCB107RUE unit 45.00 2 Handheld Call Pendant - RCB822 unit 45.00 3 Bathroom c/w Pullcord with cancel -BCT302ZRE/BCR302AE unit 18.00 4 Lampu Indikator / Lamp Indicator 1 Color -BLC673UE8 unit 27.00 5 Central Processor with power Supplay 40 CH ICRC - 40E unit 1.00 6 Central Processor with power Supplay 10 CH ICRC - 10E unit 1.00 7 Reset Button unit 9.00 8 Nurse call Instalasion ttk 135.00

b NURSE STATION B1 Bedcall Socket c/w Reset Button - BCB107RUE unit 45.00 2 Handheld Call Pendant - RCB822 unit 45.00 3 Bathroom c/w Pullcord with cancel -BCT302ZRE/BCR302AE unit 18.00 4 Lampu Indikator / Lamp Indicator 1 Color -BLC673UE8 unit 27.00 5 Central Processor with power Supplay 40 CH ICRC - 40E unit 1.00 6 Central Processor with power Supplay 10 CH ICRC - 10E unit 1.00 7 Reset Button unit 9.00 8 Nurse call Instalasion ttk 135.00

SUB TOTAL PEKERJAAN SISTEM NURSE CALL LANTAI 6 9 PEKERJAAN CCTV

1 Fixed Dome Camera With Housing unit 6.00 2 Camera Rotary With Housing unit 2.00 3 Instalasi power listrik ( NYM 2x1,5 mm) ttk 6.00 4 Instalasi kabel Coaxial RG 11 ttk 6.00 5 Instalasi power listrik ( NYM 3x2,5 mm) drLt 6 ke BS m' 72.00 6 Instalasi kabel Coaxial RG 11 dari Lt 6 ke BS m' 576.00

SUB TOTAL PEKERJAAN CCTV LANTAI 6 10 PEKERJAAN MATV

1 Spliter MATV 2 way bh 1.00 2 Spliter MATV 3 way bh 2.00 3 Spliter MATV 4 way bh 3.00 4 Tap Off unit 2 way bh 1.00 5 Tap Off unit 3 way bh 2.00 6 Tap Off unit 4 way bh 3.00 7 Booster MATV bh 5.00 8 Outlet TV bh 28.00 9 TV LCD 17 inch Monitoring ( Rawat inap ) unit - By Owner

10 TV LCD 21 inch Monitoring ( Nurse StationRawat inap ) unit 2.00 - 11 Instalasi kabel distribusi dari spliter ke Outlet ttk 28.00 12 Instalasai Power ttk 28.00 13 Instalasai Coaxial RG 11 dr LT 5 ke Lt BS m' 72.00

SUB TOTAL PEKERJAAN MATV LANTAI 6 11 PEKERJAAN SISTEM KABEL DATA/LAN

1 Outlet Data, icl. Trimping Patch Cord RJ 45 ( dinding) bh 6.00 2 Outlet Data, icl. Trimping Patch Cord RJ 45 ( ltai) bh - 3 Outlet Power UPS ( dinding) bh 6.00 4 Outlet Power UPS ( lantai ) bh - 5 Switch HUB 48 Port unit 1.00 6 Instalasi kabel data ttk 6.00 7 Instalasi kabel Power bh 6.00 8 Instalasi kabel data cat 6 dari lantai 5 ke Lt Central unit 432.00

SUB TOTAL PEKERJAAN SISTEM KABEL DATA/LAN LANTAI 6 SUB TOTAL PEKERJAAN ELEKTRIKAL LANTAI 6

Page 28: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

REKAPITULASI PEKERJAAN MEP LANTAI 61 SISTEM PENGKONDISIAN UDARA ( VRF /MULTI SYSTEM)2 SISTEM INSTALASI AIR BERISH & AIR PANAS3 SISTEM INSTALASI AIR KOTOR4 SISTEM PEMADAM KEBAKARAN5 SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR6 PEKERJAAN ELEKTRIKAL7 PEKERJAAN SISTEM FIRE ALARM8 PEKERJAAN SISTEM TELEKOMUNIKASI9 PEKERJAAN SISTEM TATA SUARA

10 PEKERJAAN SISTEM NURSE CALL11 PEKERJAAN CCTV12 PEKERJAAN MATV13 PEKERJAAN SISTEM KABEL DATA/LAN

JUMLAH

Page 29: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT. VOL.

LANTAI 7I PEKERJAAN MEKANIKAL

A1 SISTEM PENGKONDISIAN UDARA ( VRF =MULTI SYSTEM)1 AC MULTI Ceilling consealed ( High static) dan Split Wall termasuk pengkabelan, Pipa Refrigrant isolasi pipa, Nampan & pipa drain

1.1 Tipe : Split Duct (Ceilling concealed- High Static) a Indoor Unit Multi - wall mounted

Kapasitas : 7500 BTU/h unit 6.00 b Indoor Unit Multi - wall mounted

Kapasitas : 9600 BTU/h unit 2.00 c Indoor Unit Multi - wall mounted

Kapasitas : 12 300 BTU/h unit 4.00 d Indoor Unit Multi

Ceilling Concealed High staticKapasitas : 24 200 BTU/h unit 18.00

e Indoor Unit Multi Ceilling Concealed High staticKapasitas : 36 200 BTU/h unit 4.00

f Indoor Unit Multi Ceilling Concealed High staticKapasitas : 54 600 BTU/h unit 2.00

g Outdoor Unit Multi V - IVKapasitas : 267.800 BTU/h unit 2.00

h Outdoor Unit Multi V - IVKapasitas : 229 600 BTU/h unit 1.00

1.2 Pekerjaan Pipa Refrigrant1 Y-Branch ARBLN01621 unit 3.00 2 Y-Branch ARBLN03321 unit 8.00 3 Y-Branch ARBLN07121 unit 16.00 4 Y-Branch ARBLN14521 unit 14.00 5 Outdoor Pipe Connection unit 5.00 6 Standard Wired Remote Control unit 8.00 7 Wireless Remocon unit 34.00 8 ACP unit 1.00 9 Penambahan Refrigerant Gas R-410A Kg 120.00

10 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 6.35 mm mtr 106.00 11 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 9.52 mm mtr 186.00 12 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 12.7 mm mtr 133.00 13 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 15.88 mm mtr 224.00 14 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 19.05 mm mtr 102.00 15 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 22.2 mm mtr 184.00 16 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 25.4 mm mtr 12.00 17 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 28.58 mm mtr 15.00 18 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 31.8 mm mtr 133.00 19 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 34.9 mm mtr 60.00 20 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 38.1 mm mtr 172.00 21 Pemipaan Drain AW + Isolasi uk / Dia 1" mtr 216.00 22 Pemipaan Drain AW + Isolasi uk / Dia 2" mtr 256.00 23 Pemipaan Drain AW + Isolasi uk / Dia 3" mtr 16.00 24 Kabel Transmisi Data + Power IU OU mtr 813.00 25 Kabel Power Indoor unit uk NYY 3 x 2,5 mm mtr 785.00 26 Kabel Power Outdoor unit uk 4 x 10 mm mtr 112.00 27 Kabel Power Outdoor unit uk 4 x 16 mm mtr - 28 SAD uk 10"X 10" bh 61.00 29 FAG uk 20"X20" bh 26.00 30 RAG uk 20"x 8" bh 124.00 31 Material Bantu ls 1.00 32 Commisioning (Flushing N2, Vacuum, Pressure Test) unit 36.00

1.3 Pekerjaan Ducting ACa. Supply Ducting Puly uretane lengkap Isolasi & rangka penggantung ukuran : - 14"x16" m' 12.00 - 14"x14" m' 12.00 - 14"x12" m' 16.00 - 12"x12" m' 44.00 - 12"x10" m' 128.00 - 10"x10" m' 124.00 - Rangka dan Pengantung ls 1.00

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 30: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

b.Retum Ducting Puly uretane lengkap Isolasi & rangka penggantung ukuran : Duct Plenum (PxLxT) 32"x26"x14" Polyurethane unit 2.00 Duct Plenum (PxLxT) 32"x20"x14" Polyurethane unit 4.00 Duct Plenum (PxLxT) 28"x16"x14" Polyurethane unit 20.00 - 12"x10" m' 64.00 - 10"x10" m' 146.00 - 10"x8" m' 80.00 - 8"x8" m' 240.00 - 8"x6" m' 160.00 - Rangka dan Pengantung ls 1.00

c.Flexible duct, ukuran : - dia. 10" m' 152.50 - dia. 8" m' 60.00

d.Volume Damper/VD, ukuran : - 14"x16" bh 4.00 - 14"x14" bh 2.00 - 14"x12" bh 4.00 - 12"x12" bh 4.00 - 12"x10" bh 4.00 - 10"x10" bh 46.00

e.Supply Air Difuser/SAD, ukuran: - 12"x12" bh 69.00

f.Relum Air Grille/RAG, ukuran: - 20"x8" bh 124.00 - 16"x8" bh 52.00 - 12"x12" bh 52.00

g.Linear Diffuser/LD, ukuran: - 30"x8" bh 20.00

h.Fresh Air Duct: - 14"x12" m' 4.00 - 12"x10" m' 18.00 - 10"x10" m' 120.00 i.Fresh Air Grille/FAG, ukuran: - 20"x10" bh 131.00 - 14"x12" bh 4.00

Sub Total Pekerjaan Air Condition & Ducting AC 7 B SISTEM VENTILASI

1 Pekerjaan exhaust ducting (termasuk di core)a. Puly uretane lengkap Isolasi & rangka penggantung ukuran:- 20"x14" m' 4.00 - 18"x14" m' 4.00 - 12"x10" m' 39.00 - 8"x6" m' 25.25 - 6"x6" m' 26.50 - 6"x4" m' 68.50

b.Exhaust Air Grille(EAG),ukuran:- 10"x10" bh 1.00 - 10"x8" bh 33.00

e. Fire Damper(FD), ukuran:- 20"x5" bh 4.00

2 Pekerjaan Exhaust Fan(EF), termasuk pengkabelan2.1 Tipe: In Line Centritugal, dilengkapi dg Automatic

shutter Dumpera. EF 5-2 bh 1.00 Kapasitas :400 CFM Daya :1Ph/220v/50Hz/200Watt

b.EF 5-3 bh 1.00 Kapasitas :600CFM Daya: 1Ph/220v/50Hz/40Watt

2.2 Tipe: Ceiling Mounteda. EF 5 bh 9.00 Kapasitas: 600 CFM Daya: 1Ph/220v/50Hz/40Watt

b. EF 5-1 bh 1.00 Kapasitas: 250 CFM Daya: 1Ph/220v/50Hz/40Wattc. Instalasi EF ttk 12.00

Page 31: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

2.3 Testing & commissioning is 1.00 Sub Total Pekerjaan Ventilasi AC

SUB TOTAL SISTEM PENGKONDISIAN UDARA( HVAC LANTAI 7

C SISTEM INSTALASI AIR BERISH & AIR PANAS1 Pompa air bersih

1.1 Polypropylene(PPR-Plpe) PN-10 incl.Support1 - dia. 100 mm(4") m' - 2 - dia. 80 mm(3") m' 2.40 3 - dia. 50 mm(2") m' 36.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 256.00 8 - Fitting & aksesories is 1.00

Polypropylene Piep (PPR) klas PN-20 incl. Isolasi support1 - dia. 80 mm(3") m' 14.00 2 - dia. 65 mm (2 1/2") m' 152.00 3 - dia. 50 mm (2") m' 4.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 66.00 8 - Fitting & aksesories is 1.00

1.2 Valve & aksesories1.2.1 Gate valve :

1 - dia 65 mm(2 1/2") bh 4.00 2 - dia 50 mm(2") bh 12.00 3 - dia 40 mm(1 1/2") bh 6.00 4 - dia 25 mm(1") bh 56.00 5 - dia 20 mm(3/4") bh 28.00 6 -dia 15 mm(1/2") bh -

1.2.1 Chek valve : 1 Chek valve : 65 mm ( 2 1/2" ) bh 2.00 2 Chek valve : 25 mm ( 1" ) bh 4.00 3 Chek valve : 25 mm ( 3/4" ) bh 20.00

1.3 Testing & Commissioning is 1.00 SUB TOTAL SISTEM INSTALASI AIR BERISH & AIR PANAS LANTAI 7

B SISTEM INSTALASI AIR KOTOR1 Pompaan Air Kotor & Air Buangan

1.1 Polivinyt Chlorida pipe(PVC) klas 10kg/cm2 incl. Support1 - dia 150mm (6") m' 0.90 2 - dia 100mm (4") m' 31.20 3 - dia 80mm (3") m' 94.00 4 - dia 50mm (2") m' 139.50 5 '- Fitting & aksesories m' 1.00

1.2 Pemipaan VentPolivinyt Chlorida Pipe(PVC) klass 10kg/cm2 incl. Support

1 - dia 80mm (3") m' 10.00 2 - dia 50mm (2") m' 82.00 3 - Fitting & aksesories is 1.00

1.3 Sanitair:-Clean Out(CO) 4" air kotor bh 31.00 -Clean Out(CO) 2 1/2" air bekas bh 31.00 -Floor Drain(FD) 2 1/2" bh 44.00 Testing & Commissioning is 1.00

SUB TOTAL SISTEM INSTALASI AIR KOTOR 7

D SISTEM PEMADAM KEBAKARANPekerjaan Instalasi Hidrant dan Springkler

1 Pemipaan1.1 Pemipaan BSP, nch 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 60mm(3") m' 0.40 -dia. 65mm(2 1/2") m' 5.80 -dia. 50mm(2") m' 105.00 Fitting & aksessories is 1.00

1.2 Valve:- Gate valve,dia. 80mm(3") bh 1.00

1.3 Hydrant box(Tipe B/indoor) Tanpa box, accsories lengkap unit 4.00 Roll fire, Hydrant Valve, Jet Nosle,Hose Rack 1,5"

1.4 Tabung kebakaran fire extinguisher1.4.1 FE, Tipe ABC Dry Chemical

-Kapasitas: 4kg bh 11.00

Page 32: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.5 Testing & commissioning is 1.00

Page 33: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Pekerjaan Instalasi Sprinkler2.1 Head Sprinkler

-Tipe pendant bh 125.00

2.2 Pemipaan2.2.1 Black steel pipe(BSP) ach. 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 100mm(4") m' 0.40 -dia. 80mm(3") m' 3.60 -dia. 65mm(2 1/2") m' 3.00 -dia. 50mm(2") m' 11.34 -dia. 40mm(1 1/2") m' 66.30 -dia. 32mm(1 1/4") m' 122.40 -dia. 25mm(1") m' 228.25 -Fitting & aksessories is 1.00

2.2.2 Valve:-Butterfly valve,dia. 100 mm(4") PN 16 bh 1.00 Branch Control Valve ( BCV) 4" lengkap : bh 1.00 Pressure Reducing Valve 4 " ( PRV ) bh 2.00

2.2.3 Flow Switch bh 1.00

2.3 Pipa drain :Pollyint Chloride Pipe(PVC) klas 10kg/cm2-dia. 50mm(2") m' 4.00 -dia. 25mm(1") m' 82.00 -Fitting & aksessories is 1.00

2.3.2 Valve:-Gate valve dia. 25mm(1") bh 2.00

2.4 Testing & Commisioning is 1.00 SUB TOTAL SISTEM PEMADAM KEBAKARAN 7

E SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR LANTAI 7A PEKERJAAN INSTALASI DALAM BANGUAN1 Instalasi Jaringan Oxygen

Pipa Tembaga ASTM 819 Type L1 Diameter3/8" m' 228.00 2 Diameter 1/2" m' 101.00 3 Diameter 5/8" m' 88.00 4 Diameter 3/4" m' 44.00 5 Diameter 7/8" m' 41.00 6 Diameter 1 1/8" m' 12.00 7 Fitting da Accessories Ls 1.00

4 Instalasi Jaringan VacuumPipa Tembaga ASTM 819 Type L

1 Diameter 1/2" m' 228.00 2 Diameter 5/8" m' 101.00 3 Diameter 3/4" m' 88.00 4 Diameter 7/8" m' 44.00 5 Diameter 1 1/8" m' 41.00 6 Diameter 1 3/8" m' 12.00 7 Fitting da Accessories Ls 1.00

SUB TOTAL INSTALASI DALAM BANGUANN

5 PERALATAN DALAM RUANGAN 1 Wall Outlet Oxygen (O), pin index, push type buah 84.00

2 Wall Outlet Vacuum (V), pin index, push type, slide base buah 84.00

3 Zona Valve 2 Gas (O, V) set 2.00

4 Area Alarm 2 Gas (O,V) unit 2.00

5 Bedhead Unit, Aluminium, L=1200 mm buah 84.00 6 Testing & Kommisioning Ls 1.00

SUB TOTAL PERALATAN DALAM BANGUANN

SUB TOTAL SISTEM INSTALASI GAS, VACUUM & CIMPRESSED AIR LANTAI 7 SUB TOTAL PEKERJAAN MEKANIKAL LANTAI 7

II PEKERJAAN ELEKTRIKAL1 PEKERJAAN PANEL DAYA1.1 Panel LP -6A unit 1.00 1.2 Panel LP -6B unit 1.00 1.3 Panel LP -6C unit 1.00 1.4 Panel PPS -6A unit 1.00 1.5 Panel PPS -6B unit 1.00 1.6 Panel PPS -6C unit 1.00 1.6 Panel SDP -6 unit 1.00 1.7 Panel Indoor AC 6,7,8 AC Multi unit 1.00

SUB TOTAL PEKERJAAN PANEL DAYA 7

Page 34: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

2 PEKERJAAN KABEL 2.1 Kabel dari Panel LVMDP ke panel MDP 7 m' -

NYFGBY 4 x ( 4x300 mm2) +NYA 300 mm22.2 Kabel dari Panel MDP - 5 ke panel SDP 6 m' 10.00

NYY 4 x 70 mm2 +NYA 50 mm22.3 Kabel dari Panel SDP - 6 ke panel LP 6A, m' 62.00

NYY 4 x 10 mm2 +NYA 10 mm22.4 Kabel dari Panel SDP - 6 ke panel LP 6B, m' 6.00

NYY 4 x 10 mm2 +NYA 10 mm22.5 Kabel dari Panel SDP - 6 ke panel LP 6C, m' 62.00

NYY 4 x 10 mm2 +NYA 10 mm22.6 Kabel dari Panel SDP - 6 ke panel PP ST 6A,

NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00 2.7 Kabel dari Panel SDP - 6 ke panel PP ST 6B

NYY 4 x 16 mm2 +NYA 16 mm2 m' 6.00 2.8 Kabel dari Panel SDP - 6 ke panel PP ST 6C

NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00 2.9 Kabel dari Panel SDP - 6 ke panel PP AC Indoor multi 6

NYY 4 x 6 mm2 +NYA 6 mm2 m' 48.00 SUB TOTAL PEKERJAAN KABEL 7

3 PEKERJAAN KABEL TRAY & KABEL LADDERRak kabel termasuk support

3.1 -Kabel ladder elektrikal 300x100 mm m' 82.50 3.2 -Kabel ladder elektronik 200x100 mm m' 82.50

SUB TOTAL PEKERJAAN KABEL TRAY DAN KABEL LADDER 7

4 PEKERJAAN LAMPU PENERANGAN, TITIKOUTLET, STOP KONTAK DAN SAKLARTERMASUK KONDUIT

1 RM 300 2x36 M4, TL LED ESS 16 W bh 27.00 2 RM 300 2x36 M4, TL LED ESS 16 W+ Batt ( On 1 lamp) bh 11.00 3 RM 300 1x36 ACR TL LED ESS 16 W bh 82.00 4 BL T4 1X 20 W bh 82.00 5 Weatherproof Elektra 2x 36 PC TL LED 16 W bh 14.00 6 RMO 2X36 TL LED ESS 16 W bh 8.00 7 GMS TP 1X 36 ACR, TL LED ESS 16 W bh 3.00 8 GMS TP 1X 36 ACR, TL LED ESS 16 W + Batt bh 3.00 9 Theme 150 -70- E 27 LED Bulb 10 W bh 78.00

10 Theme 150 -70- E 27 LED Bulb 10 W + Batt bh 24.00 11 Theme 150 -70- E 27 LED Bulb 7 W bh 61.00 12 BL CG 1X 36 TL LED ESS 16 W bh 6.00 13 Exit Green LED H 1+ Battery bh 3.00 14 Grid Switch 6 gang bh 2.00 15 Saklar Tunggal 16 A, 1 phasa bh 88.00 16 Saklar Ganda 16 A, 1 phasa bh 76.00 17 Saklar Ganda 16 A, 1 phasa ( Bed head ) bh 92.00 18 Saklar Hotel Tunggal 16 A, 1 phasa bh 3.00 19 Stop kontak 16 A, 1phasa (Bed Head ) bh 184.00 20 Stop kontak 16 A, 1phasa (dinding/Kantor Corridor)) bh 56.00 21 Instalasi Penerangan ttk 241.20 22 Instalasi stop kontak 1 phase ttk 144.00

SUB TOTAL PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR 7 SUB TOTAL PEKERJAAN LISTRIK LANTAI 7

5 PEKERJAAN SISTEM FIRE ALARM1 Photo Electronic Smoke Detector bh 62.00 2 Rate of Rise heat detector bh 4.00 3 Fixed Temp Heat Detector bh 2.00 4 Alarm Bell 6" bh 3.00 5 Manual Puab Bulton bh 3.00 6 Indicator lamp bh 3.00 7 Jack Fireman Intercom bh 3.00 8 Zone addres monitor Module bh 4.00 9 Sounder addres Module bh 4.00

10 Short circuit Isolator bh 2.00 11 Dual I/O Module bh 2.00 12 Terminal Box - FA, F 30 pars unit 1.00 13 Kabel dari Semi addressable ke TB - FA,

STP 16 AWG 2 pair + NYM 2 x 1,5 mm2 ttk 6.00 14 Instalasi Detector

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 68.00 15 Instalasi Bell+ indicator lamp

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 9.00 16 Instalasi Jeck fireman intercom ttk 3.00 17 Instalasi Addressable Break Glass

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 3.00 18 Instalasi Flow Switch Sprinkler

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 2.00 SUB TOTAL PEKERJAAN SISTEM FIRE ALARM LANTAI 7

Page 35: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

6 PEKERJAAN SISTEM TELEKOMUNIKASI1 Outlet Telepon tidak langsung bh 4.00 2 Instalasi Telepon ttk 4.00 3 Hanset/Pesawat telephone bh 4.00 4 Terminal Box - T.F 20 pairs unit 1.00 5 Kabel dari MDF - FA ke TB - T, E Steal K 011 m' 72.00

20 x 2 x 2 x 0,6 mm SUB TOTAL PEKERJAAN SISTEM TELEKOMUNIKASI 7

7 PEKERJAAN SISTEM TATA SUARA1 Ceiling Speaker 3 watt bh 50.00 2 Wall speaker 6 watt bh 3.00 3 Volumn kontrol 3 watt bh 38.00 4 Volumn kontrol 30 watt bh 2.00 5 Instalasi Speaker ttk 53.00 6 Instalasi Volume Control ttk 41.00 7 Terminal box TS.F 10 pairs unit 1.00 8 Kabel MDF SS ke TB TS. NYMHY 2 3 x 2,5mm2 m' 144.00

SUB TOTAL PEKERJAAN SISTEM TATA SUARA LANTAI 7 8 PEKERJAAN SISTEM NURSE CALL ( ONE WAY )a NURSE STATION A

1 Bedcall Socket c/w Reset Button - BCB107RUE unit 45.00 2 Handheld Call Pendant - RCB822 unit 45.00 3 Bathroom c/w Pullcord with cancel -BCT302ZRE/BCR302AE unit 18.00 4 Lampu Indikator / Lamp Indicator 1 Color -BLC673UE8 unit 27.00 5 Central Processor with power Supplay 40 CH ICRC - 40E unit 1.00 6 Central Processor with power Supplay 10 CH ICRC - 10E unit 1.00 7 Reset Button unit 9.00 8 Nurse call Instalasion ttk 135.00

b NURSE STATION B1 Bedcall Socket c/w Reset Button - BCB107RUE unit 45.00 2 Handheld Call Pendant - RCB822 unit 45.00 3 Bathroom c/w Pullcord with cancel -BCT302ZRE/BCR302AE unit 18.00 4 Lampu Indikator / Lamp Indicator 1 Color -BLC673UE8 unit 27.00 5 Central Processor with power Supplay 40 CH ICRC - 40E unit 1.00 6 Central Processor with power Supplay 10 CH ICRC - 10E unit 1.00 7 Reset Button unit 9.00 8 Nurse call Instalasion ttk 135.00

SUB TOTAL PEKERJAAN SISTEM NURSE CALL LANTAI 7 9 PEKERJAAN CCTV

1 Fixed Dome Camera With Housing unit 6.00 2 Camera Rotary With Housing unit 2.00 3 Instalasi power listrik ( NYM 2x1,5 mm) ttk 6.00 4 Instalasi kabel Coaxial RG 11 ttk 6.00 5 Instalasi power listrik ( NYM 3x2,5 mm) drLt 7 ke BS m' 72.00 6 Instalasi kabel Coaxial RG 11 dari Lt 7 ke BS m' 576.00

SUB TOTAL PEKERJAAN CCTV LANTAI 7 10 PEKERJAAN MATV

1 Spliter MATV 2 way bh 1.00 2 Spliter MATV 3 way bh 2.00 3 Spliter MATV 4 way bh 3.00 4 Tap Off unit 2 way bh 1.00 5 Tap Off unit 3 way bh 2.00 6 Tap Off unit 4 way bh 3.00 7 Booster MATV bh 5.00 8 Outlet TV bh 28.00 9 TV LCD 17 inch Monitoring ( Rawat inap ) unit - By Owner

10 TV LCD 21 inch Monitoring ( Nurse StationRawat inap ) unit 2.00 11 Instalasi kabel distribusi dari spliter ke Outlet ttk 28.00 12 Instalasai Power ttk 28.00 13 Instalasai Coaxial RG 11 dr LT 5 ke Lt BS m' 72.00

SUB TOTAL PEKERJAAN MATV LANTAI 7 11 PEKERJAAN SISTEM KABEL DATA/LAN

1 Outlet Data, icl. Trimping Patch Cord RJ 45 ( dinding) bh 6.00 2 Outlet Data, icl. Trimping Patch Cord RJ 45 ( ltai) bh - 3 Outlet Power UPS ( dinding) bh 6.00 4 Outlet Power UPS ( lantai ) bh - 5 Switch HUB 48 Port unit 1.00 6 Instalasi kabel data ttk 6.00 7 Instalasi kabel Power bh 6.00 8 Instalasi kabel data cat 6 dari lantai 5 ke Lt Central unit 468.00

SUB TOTAL PEKERJAAN SISTEM KABEL DATA/LAN LANTAI 7 SUB TOTAL PEKERJAAN ELEKTRIKAL LANTAI 7

Page 36: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

REKAPITULASI PEKERJAAN MEP LANTAI 71 SISTEM PENGKONDISIAN UDARA ( VRF /MULTI SYSTEM)2 SISTEM INSTALASI AIR BERISH & AIR PANAS3 SISTEM INSTALASI AIR KOTOR4 SISTEM PEMADAM KEBAKARAN5 SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR

6 PEKERJAAN ELEKTRIKAL7 PEKERJAAN SISTEM FIRE ALARM8 PEKERJAAN SISTEM TELEKOMUNIKASI9 PEKERJAAN SISTEM TATA SUARA

10 PEKERJAAN SISTEM NURSE CALL11 PEKERJAAN CCTV12 PEKERJAAN MATV13 PEKERJAAN SISTEM KABEL DATA/LAN

JUMLAH

Page 37: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT. VOL.

LANTAI 8I PEKERJAAN MEKANIKALA SISTEM PENGKONDISIAN UDARA ( VRF =MULTI SYSTEM)

1 AC MULTI Ceilling consealed ( High static) dan Split Wall termasuk pengkabelan, Pipa Refrigrant isolasi pipa, Nampan & pipa drain

1.1 Tipe: Split Duct ( Ceilling concealed- High static ) a. Indoor Unit Multi - wall mounted- Kapasitas : 7500 BTU/h unit 6.00 b. Indoor Unit Multi - wall mountedKapasitas : 9600 BTU/h unit 2.00 c. Indoor Unit Multi - wall mounted- Kapasitas : 15 400 BTU/h unit 4.00 d. Indoor Unit Multi Ceilling Concealed High static- Kapasitas : 24 200 BTU/h unit 18.00 e. Indoor Unit Multi Ceilling Concealed High static- Kapasitas : 36 200 BTU/h unit 4.00 f. Indoor Unit Multi Ceilling Concealed High static- Kapasitas : 54 600 BTU/h unit 2.00 g.Outdoor Unit Multi V - IV- Kapasitas : 229 400 BTU/h unit 1.00 h.Outdoor Unit Multi V - IV- Kapasitas : 210 600 BTU/h unit 2.00

1.2 Pekerjaan Pipa Refrigrant1 Y-Branch ARBLN01621 unit 3.00 2 Y-Branch ARBLN03321 unit 8.00 3 Y-Branch ARBLN07121 unit 16.00 4 Y-Branch ARBLN14521 unit 14.00 5 Outdoor Pipe Connection unit 5.00 6 Standard Wired Remote Control unit 8.00 7 Wireless Remocon unit 34.00 8 ACP unit 1.00 9 Penambahan Refrigerant Gas R-410A Kg 120.00

10 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 6.35 mm mtr 106.00 11 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 9.52 mm mtr 186.00 12 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 12.7 mm mtr 133.00 13 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 15.88 mm mtr 224.00 14 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 19.05 mm mtr 102.00 15 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 22.2 mm mtr 184.00 16 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 25.4 mm mtr 12.00 17 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 28.58 mm mtr 15.00 18 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 31.8 mm mtr 133.00 19 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 34.9 mm mtr 50.00 20 Pemipaan Refrigerant ASTM B-280 + Isolasi uk / Dia 38.1 mm mtr 172.00 21 Pemipaan Drain AW + Isolasi uk / Dia 1" mtr 216.00 22 Pemipaan Drain AW + Isolasi uk / Dia 2" mtr 256.00 23 Pemipaan Drain AW + Isolasi uk / Dia 3" mtr 16.00 24 Kabel Transmisi Data IU - OU NYY 4x 25 mm mtr 793.00 25 Kabel Power Indoor unit uk NYY 3 x 2,5 mm mtr 785.00 26 Kabel Power Outdoor unit uk 4 x 10 mm mtr 112.00 27 Kabel Power Outdoor unit uk 4 x 16 mm mtr - 28 SAD uk 10"X 10" bh 61.00 29 FAG uk 20"X20" bh 26.00 30 RAG uk 20"x 8" bh 124.00 31 Material Bantu ls 1.00 32 Commisioning (Flushing N2, Vacuum, Pressure Test) unit 36.00

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 38: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

1.3 Pekerjaan Ducting ACa. Supply Ducting Puly uretane lengkap Isolasi & rangka penggantung ukuran : - 14"x16" m' 12.00 - 14"x14" m' 12.00 - 14"x12" m' 16.00 - 12"x12" m' 44.00 - 12"x10" m' 128.00 - 10"x10" m' 124.00 - Rangka dan Pengantung ls 1.00

b.Retum Ducting Puly uretane lengkap Isolasi & rangka penggantung ukuran : Duct Plenum (PxLxT) 32"x26"x14" Polyurethane unit 2.00 Duct Plenum (PxLxT) 32"x20"x14" Polyurethane unit 4.00 Duct Plenum (PxLxT) 28"x16"x14" Polyurethane unit 20.00 - 12"x10" m' 64.00 - 10"x10" m' 146.00 - 10"x8" m' 80.00 - 8"x8" m' 240.00 - 8"x6" m' 160.00 - Rangka dan Pengantung ls 1.00

c.Flexible duct, ukuran : - dia. 10" m' 152.50 - dia. 8" m' 60.00

d.Volume Damper/VD, ukuran : - 14"x16" bh 4.00 - 14"x14" bh 2.00 - 14"x12" bh 4.00 - 12"x12" bh 4.00 - 12"x10" bh 4.00 - 10"x10" bh 46.00

e.Supply Air Difuser/SAD, ukuran: - 12"x12" bh 69.00

f.Relum Air Grille/RAG, ukuran: - 20"x8" bh 124.00 - 16"x8" bh - 12"x12" bh

g.Linear Diffuser/LD, ukuran: - 30"x8" bh 20.00

h.Fresh Air Duct: - 14"x12" m' 4.00 - 12"x10" m' 18.00 - 10"x10" m' 120.00 i.Fresh Air Grille/FAG, ukuran: - 20"x10" bh 131.00 - 14"x12" bh 4.00

Sub Total Pekerjaan Air Condition & Ducting AC 8

B SISTEM VENTILASI1 Pekerjaan exhaust ducting (termasuk di core)

a. Puly uretane lengkap Isolasi & rangka penggantung ukuran:- 20"x14" m' 4.00 - 18"x14" m' 4.00 - 12"x10" m' 39.00 - 8"x6" m' 25.25 - 6"x6" m' 26.50 - 6"x4" m' 68.50

b.Exhaust Air Grille(EAG),ukuran:- 10"x10" bh 1.00 - 10"x8" bh 33.00

Page 39: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

e. Fire Damper(FD), ukuran:- 20"x5" bh 4.00

2 Pekerjaan Exhaust Fan(EF), termasuk pengkabelan2.1 Tipe: In Line Centritugal, dilengkapi dg Automatic

shutter Dumpera. EF, 8 - 2A bh 1.00 Kapasitas: 400 CFM Daya: 1Ph/220v/50Hz/300Watt

b. EF,8-2B bh 1.00 Kapasitas: 600 CFM Daya: 1Ph/220v/50Hz/40Watt

2.2 Tipe: Celing Mounteda. EF, 8-1A bh 9.00 Kapasitas: 600 CFM Daya: 1Ph/220v/50Hz/40Watt

b.EF,8-2B bh 1.00 Kapasitas: 250 CFM Daya: 1Ph/220v/50Hz/40Wattc. Instalasi EF Ttk 12.00

2.3 Testing & commissioning is 1.00 Sub Total Pekerjaan Ventilasi AC

SUB TOTAL SISTEM PENGKONDISIAN UDARA( HVAC LANTAI 8

C SISTEM INSTALASI AIR BERISH & AIR PANAS1 Pompa air bersih

1.1 Polypropylene(PPR-Plpe) PN-10 incl.Support1 - dia. 100 mm(4") m' - 2 - dia. 80 mm(3") m' 6.00 3 - dia. 50 mm(2") m' 36.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 282.00 8 - Fitting & aksesories is 1.00

Polypropylene Piep (PPR) klas PN-20 incl. Isolasi support1 - dia. 80 mm(3") m' 14.00 2 - dia. 65 mm (2 1/2") m' 152.00 3 - dia. 50 mm (2") m' 4.00 4 - dia. 40 mm(1 1/2") m' 17.00 5 - dia. 25 mm(1") m' 4.00 6 - dia. 20 mm(3/4") m' 42.00 7 - dia. 15 mm(1/2") m' 282.00 8 - Fitting & aksesories is 1.00

1.2 Valve & aksesories1.2.1 Gate valve :

1 - dia 65 mm(2 1/2") bh 4.00 2 - dia 50 mm(2") bh 12.00 3 - dia 40 mm(1 1/2") bh 6.00 4 - dia 25 mm(1") bh 56.00 5 - dia 20 mm(3/4") bh 28.00 6 -dia 15 mm(1/2") bh -

1.2.1 Chek valve : 1 Chek valve : 65 mm ( 2 1/2" ) bh 2.00 2 Chek valve : 25 mm ( 1" ) bh 4.00 3 Chek valve : 25 mm ( 3/4" ) bh 20.00

1.3 Testing & Commissioning is 1.00 SUB TOTAL SISTEM INSTALASI AIR BERISH & AIR PANAS LANTAI 8

B SISTEM INSTALASI AIR KOTOR1 Pompaan Air Kotor & Air Buangan

1.1 Polivinyt Chlorida pipe(PVC) klas 10kg/cm2 incl. Support1 - dia 150mm (6") m' 0.90 2 - dia 100mm (4") m' 31.20 3 - dia 80mm (3") m' 94.00 4 - dia 50mm (2") m' 139.50

Page 40: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

5 '- Fitting & aksesories m' 1.00

1.2 Pemipaan VentPolivinyt Chlorida Pipe(PVC) klass 10kg/cm2 incl. Support

1 - dia 80mm (3") m' 10.00 2 - dia 50mm (2") m' 82.00 3 - Fitting & aksesories is 1.00

1.3 Sanitair:1 -Clean Out(CO) 4" air kotor bh 26.00 2 -Clean Out(CO) 2 1/2" air bekas bh 26.00 3 -Floor Drain(FD) 2 1/2" bh 36.00 4 Testing & Commissioning is 1.00

SUB TOTAL SISTEM INSTALASI AIR KOTOR 8

D SISTEM PEMADAM KEBAKARANPekerjaan Instalasi Hidrant dan Springkler

1 Pemipaan1.1 Pemipaan BSP, nch 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 60mm(3") m' 0.40 -dia. 65mm(2 1/2") m' 5.80 -dia. 50mm(2") m' 105.00 Fitting & aksessories is 1.00

1.2 Valve:- Gate valve,dia. 80mm(3") bh 1.00

1.3 Hydrant box(Tipe B/indoor) Tanpa box, accsories lengkap unit 4.00 Roll fire, Hydrant Valve, Jet Nosle,Hose Rack 1,5"

1.4 Tabung kebakaran fire extinguisher1.4.1 FE, Tipe ABC Dry Chemical

-Kapasitas: 4kg bh 11.00

1.5 Testing & commissioning is 1.00

Pekerjaan Instalasi Sprinkler2.1 Head Sprinkler

-Tipe pendant bh 125.00

2.2 Pemipaan2.2.1 Black steel pipe(BSP) ach. 40 termasuk support

-dia. 150mm(6") m' 0.60 -dia. 100mm(4") m' 0.40 -dia. 80mm(3") m' 3.60 -dia. 65mm(2 1/2") m' 3.00 -dia. 50mm(2") m' 11.34 -dia. 40mm(1 1/2") m' 66.30 -dia. 32mm(1 1/4") m' 122.40 -dia. 25mm(1") m' 228.25 -Fitting & aksessories is 1.00

2.2.2 Valve:-Butterfly valve,dia. 100mm(4") bh 1.00 Branch Control Valve ( BCV) 4" lengkap : bh 1.00

2.2.3 Flow Switch bh 1.00

2.3 Pipa drain :Pollyint Chloride Pipe(PVC) klas 10kg/cm2-dia. 50mm(2") m' 4.00 -dia. 25mm(1") m' 82.00 -Fitting & aksessories is 1.00

2.3.2 Valve:-Gate valve dia. 25mm(1") bh 2.00

2.4 Testing & Commisioning is 1.00 SUB TOTAL SISTEM PEMADAM KEBAKARAN LANTAI 8

Page 41: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

E SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR LANTAI 8A PEKERJAAN INSTALASI DALAM BANGUAN1 Instalasi Jaringan Oxygen

Pipa Tembaga ASTM 819 Type L1 Diameter3/8" m' 228.00 2 Diameter 1/2" m' 101.00 3 Diameter 5/8" m' 88.00 4 Diameter 3/4" m' 44.00 5 Diameter 7/8" m' 41.00 6 Diameter 1 1/8" m' 12.00 7 Fitting da Accessories Ls 1.00

4 Instalasi Jaringan VacuumPipa Tembaga ASTM 819 Type L

1 Diameter 1/2" m' 228.00 2 Diameter 5/8" m' 101.00 3 Diameter 3/4" m' 88.00 4 Diameter 7/8" m' 44.00 5 Diameter 1 1/8" m' 41.00 6 Diameter 1 3/8" m' 12.00 7 Fitting da Accessories Ls 1.00

SUB TOTAL INSTALASI DALAM BANGUANN

5 PERALATAN DALAM RUANGAN 1 Wall Outlet Oxygen (O), pin index, push type buah 18.00

2 Wall Outlet Vacuum (V), pin index, push type, slide base buah 18.00

3 Zona Valve 2 Gas (O, V) set 2.00

4 Area Alarm 2 Gas (O,V) unit 2.00

5 Bedhead Unit, Aluminium, L=1200 mm buah 18.00 6 Testing & Kommisioning Ls 1.00

SUB TOTAL PERALATAN DALAM BANGUANN

SUB TOTAL SISTEM INSTALASI GAS, VACUUM & CIMPRESSED AIR LANTAI 8 SUB TOTAL PEKERJAAN MEKANIKAL LANTAI 8

II PEKERJAAN ELEKTRIKAL1 PEKERJAAN PANEL DAYA1.1 Panel LP -8A unit 1.00 1.2 Panel LP -8B unit 1.00 1.3 Panel LP -8C unit 1.00 1.4 Panel PPST -8A unit 1.00 1.5 Panel PPST -8B unit 1.00 1.6 Panel PPST -8C unit 1.00 1.6 Panel SDP -8 unit 1.00

SUB TOTAL PEKERJAAN PANEL DAYA 8

2 PEKERJAAN KABEL 2.1 Kabel dari Panel LVMDP ke panel MDP 8 m' -

NYFGBY 4 x ( 4x300 mm2) +NYA 300 mm22.2 Kabel dari Panel MDP - 5 ke panel SDP 8, m' 10.00

NYY 4 x 70 mm2 +NYA 50 mm22.3 Kabel dari Panel SDP - 8 ke panel LP 8A, m' 62.00

NYY 4 x 10 mm2 +NYA 10 mm22.4 Kabel dari Panel SDP - 8 ke panel LP 8B, m' 6.00

NYY 4 x 10 mm2 +NYA 10 mm22.5 Kabel dari Panel SDP - 8 ke panel LP 8C, m' 62.00

NYY 4 x 10 mm2 +NYA 10 mm22.6 Kabel dari Panel SDP - 8 ke panel PP ST 8A,

NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00 2.7 Kabel dari Panel SDP - 8 ke panel PP ST 8B

NYY 4 x 16 mm2 +NYA 16 mm2 m' 6.00 2.8 Kabel dari Panel SDP - 8 ke panel PP ST 8C

NYY 4 x 16 mm2 +NYA 16 mm2 m' 62.00 SUB TOTAL PEKERJAAN KABEL 8

3 PEKERJAAN KABEL TRAY & KABEL LADDERRak kabel termasuk support

3.1 -Kabel ladder elektrikal 300x100 mm m' 110.00 3.2 -Kabel ladder elektronik 200x100 mm m' 110.00

SUB TOTAL PEKERJAAN KABEL TRAY DAN KABEL LADDER 8

Page 42: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

4 PEKERJAAN LAMPU PENERANGAN, TITIKOUTLET, STOP KONTAK DAN SAKLARTERMASUK KONDUIT

1 RM 300 2x36 M4, TL LED ESS 16 W bh 27.00 2 RM 300 2x36 M4, TL LED ESS 16 W+ Batt ( On 1 lamp) bh 11.00 3 RM 300 1x36 ACR TL LED ESS 16 W bh 18.00 4 BL T4 1X 20 W bh 18.00 5 Weatherproof Elektra 2x 36 PC TL LED 16 W bh 14.00 6 RMO 2X36 TL LED ESS 16 W bh 8.00 7 GMS TP 1X 36 ACR, TL LED ESS 16 W bh 3.00 8 GMS TP 1X 36 ACR, TL LED ESS 16 W + Batt bh 3.00 9 Theme 150 -70- E 27 LED Bulb 10 W bh 158.00

10 Theme 150 -70- E 27 LED Bulb 10 W + Batt bh 24.00 11 Theme 150 -70- E 27 LED Bulb 7 W bh 45.00 12 BL CG 1X 36 TL LED ESS 16 W bh 6.00 13 Exit Green LED H 1+ Battery bh 3.00 14 Grid Switch 6 gang bh 2.00 15 Saklar Tunggal 16 A, 1 phasa bh 86.00 16 Saklar Ganda 16 A, 1 phasa bh 54.00 17 Saklar Ganda 16 A, 1 phasa ( Bed head ) bh 18.00 18 Saklar Hotel Tunggal 16 A, 1 phasa bh 3.00 19 Stop kontak 16 A, 1phasa (Bed Head ) bh 36.00 20 Stop kontak 16 A, 1phasa (dinding/Kantor Corridor)) bh 127.00 21 Instalasi Penerangan ttk 202.80 22 Instalasi stop kontak 1 phase ttk 97.80

SUB TOTAL PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR 8 SUB TOTAL PEKERJAAN LISTRIK LANTAI 8

5 PEKERJAAN SISTEM FIRE ALARM1 Photo Electronic Smoke Detector bh 62.00 2 Rate of Rise heat detector bh 4.00 3 Fixed Temp Heat Detector bh 2.00 4 Alarm Bell 6" bh 3.00 5 Manual Puab Bulton bh 3.00 6 Indicator lamp bh 3.00 7 Jack Fireman Intercom bh 3.00 8 Zone addres monitor Module bh 4.00 9 Sounder addres Module bh 4.00

10 Short circuit Isolator bh 2.00 11 Dual I/O Module bh 2.00 12 Terminal Box - FA, F 30 pars unit 1.00 13 Kabel dari Semi addressable ke TB - FA,

STP 16 AWG 2 pair = NYM 2 x 1,5 mm2 ttk 6.00 14 Instalasi Detector

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 68.00 15 Instalasi Bell+ indicator lamp

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 9.00 16 Instalasi Jeck fireman intercom ttk 3.00 17 Instalasi Addressable Break Glass

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 3.00 18 Instalasi Flow Switch Sprinkler

NYA 2 x 1 x 1,5 mm2 + uPVC Conduit dia. 20 mm ttk 2.00 SUB TOTAL PEKERJAAN SISTEM FIRE ALARM LANTAI 8

6 PEKERJAAN SISTEM TELEKOMUNIKASI1 Outlet Telepon tidak langsung bh 4.00 2 Instalasi Telepon ttk 4.00 3 Hanset/Pesawat telephone bh 4.00 4 Terminal Box - T.F 20 pairs unit 1.00 5 Kabel dari MDF - FA ke TB - T, E Steal K 011 m' 84.00

20 x 2 x 2 x 0,6 mm SUB TOTAL PEKERJAAN SISTEM TELEKOMUNIKASI 8

7 PEKERJAAN SISTEM TATA SUARA1 Ceiling Speaker 3 watt bh 50.00 2 Wall speaker 6 watt bh 3.00 3 Volumn kontrol 3 watt bh 38.00 4 Volumn kontrol 30 watt bh 2.00 5 Instalasi Speaker ttk 53.00 6 Instalasi Volume Control ttk 41.00 7 Terminal box TS.F 10 pairs unit 1.00 8 Kabel MDF SS ke TB TS. NYMHY 3 x 2,5mm2 m' 36.50

Page 43: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

SUB TOTAL PEKERJAAN SISTEM TATA SUARA LANTAI 8

Page 44: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

8 PEKERJAAN SISTEM NURSE CALL ( TWO WAY )a NURSE STATION A

1 Bedcall socket w/ Speaker and Mic - BCA304RUE unit 9.00 2 Handheld call pendant - RCBB 22 unit 9.00 3 Bathroom c/w pullcord with cancel - BCT302ZRE/BCR302AE unit 9.00 4 Lampu Indikator / lamp indicator 2 color - BLC 673UE8W unit 9.00 5 Central processor with power Supplay 40 CH - BCRC20AE unit 1.00 6 Reset Button unit 9.00 7 Nurse call Instalation ttk 36.00

NURSE STATION B1 Bedcall socket w/ Speaker and Mic - BCA304RUE unit 9.00 2 Handheld call pendant - RCBB 22 unit 9.00 3 Bathroom c/w pullcord with cancel - BCT302ZRE/BCR302AE unit 9.00 4 Lampu Indikator / lamp indicator 2 color - BLC 673UE8W unit 9.00 5 Central processor with power Supplay 40 CH - BCRC20AE unit 1.00 6 Reset Button unit 9.00 7 Nurse call Instalation ttk 36.00 8 Mobilisasi dan Akomodasi ls 1.00 9 Test dan Commisioning ls 1.00

SUB TOTAL PEKERJAAN SISTEM NURSE CALL LANTAI 8 9 PEKERJAAN CCTV

1 Fixed Dome Camera With Housing unit 6.00 2 Camera Rotary With Housing unit 2.00 3 Instalasi power listrik ( NYM 2x1,5 mm) ttk 6.00 4 Instalasi kabel Coaxial RG 11 ttk 6.00 5 Instalasi power listrik ( NYM 3x2,5 mm) drLt 8 ke BS m' 84.00 6 Instalasi kabel Coaxial RG 11 dari Lt 8 ke BS m' 672.00

SUB TOTAL PEKERJAAN CCTV LANTAI 8 10 PEKERJAAN MATV

1 Spliter MATV 2 way bh 1.00 2 Spliter MATV 3 way bh 2.00 3 Spliter MATV 4 way bh 3.00 4 Tap Off unit 2 way bh 1.00 5 Tap Off unit 3 way bh 2.00 6 Tap Off unit 4 way bh 3.00 7 Booster MATV bh 5.00 8 Outlet TV bh 28.00 9 TV LCD 17 inch Monitoring ( Rawat inap ) unit - By Owner

10 TV LCD 21 inch Monitoring ( Nurse StationRawat inap ) unit 2.00 11 Instalasi kabel distribusi dari spliter ke Outlet ttk 28.00 12 Instalasai Power ttk 28.00 13 Instalasai Coaxial RG 11 dr LT 5 ke Lt BS m' 84.00

SUB TOTAL PEKERJAAN MATV LANTAI 7 12 PEKERJAAN SISTEM KABEL DATA/LAN

1 Outlet Data, icl. Trimping Patch Cord RJ 45 ( dinding) bh 6.00 2 Outlet Data, icl. Trimping Patch Cord RJ 45 ( ltai) bh - 3 Outlet Power UPS ( dinding) bh 6.00 4 Outlet Power UPS ( lantai ) bh - 5 Switch HUB 48 Port unit 1.00 6 Instalasi kabel data ttk 6.00 7 Instalasi kabel Power bh 6.00 8 Instalasi kabel data cat 6 dari lantai 5 ke Lt Central unit 504.00

SUB TOTAL PEKERJAAN SISTEM KABEL DATA/LAN LANTAI 8 SUB TOTAL PEKERJAAN ELEKTRIKAL LANTAI 8

REKAPITULASI PEKERJAAN MEP LANTAI 81 SISTEM PENGKONDISIAN UDARA ( VRF /MULTI SYSTEM)2 SISTEM INSTALASI AIR BERISH & AIR PANAS3 SISTEM INSTALASI AIR KOTOR4 SISTEM PEMADAM KEBAKARAN5 SISTEM INSTALASI GAS, VAUUM & CIMPRESSED AIR6 PEKERJAAN PENUMETIC TUBE7 PEKERJAAN ELEKTRIKAL8 PEKERJAAN SISTEM FIRE ALARM9 PEKERJAAN SISTEM TELEKOMUNIKASI

10 PEKERJAAN SISTEM TATA SUARA11 PEKERJAAN SISTEM NURSE CALL12 PEKERJAAN CCTV13 PEKERJAAN MATV14 PEKERJAAN SISTEM KABEL DATA/LAN

Page 45: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

JUMLAH

Page 46: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT. VOL.

LANTAI 9I PEKERJAAN MEKANIKALA SISTEM PENGKONDISIAN UDARA ( VENTILASI )B SISTIM VENTILASI

1 Pekerjaan exhaust ductinga. Duct BJLS termasuk rangka penggantungukuran:- 40"x35" m' 4.50 - 25"x12" m' 3.30 - 23"x17" m' 2.10 -16"x15" m' 4.20 -16"x14" m' 2.10 -16"x10" m' 3.60 -15"x12" m' 3.60 -14"x36" m' 6.90 -10"x11" m' 1.80 -10"x10" m' 12.60 -10"x9" m' 1.80 - 9"x8" m' 1.80

b. Grille, ukuran:- 40"x36" bh 2.00 - 38"x14" bh 1.00 - 25"x14" bh 1.00 - 16"x14" bh 2.00

Sub Total Pekerjaan Ventilasi Lantai 9

PEKERJAAN REKONDISI EXHUSTE FAN2 Pekerjaan Instalasi Listrik dan Rekondisi Exhaust Fan (EF)

2.1 Tipe: in Line Centrifugal

a. EF 9-T1 bh 1.00 Kapasitas : 2850 CFM Daya : 1Ph/220v/50Hz/200watt

b. EF 9-T2 bh 1.00 Kapasitas: 2350 CFM Daya: 1ph/220v/50Hz/200watt

c. EF 9-T3 bh 1.00 Kapasitas: 3500 CFM Daya: 1ph/220v/50Hz/200watt

e. EF 9 - T4 bh 1.00 Kapasitas: 2000 CFM Daya: 1ph/220v/50Hz/200watt

Sub Total Pekerjaan Exhouse Lantai 9

PEKERJAAN REKONDISI PRESURRE FAN2 Re Kondisi Pressure Fan

2.2 Tipe: Axial a. SPF 1 bh 1.00 Kapasitas: 13.000 CFM Daya: 3Ph/380v/50Hz/5000Watt

b.SPF 2 bh 1.00 Kapasitas: 13.000 CFM Daya: 3Ph/380v/50Hz/5000Watt

c.SPF 3 bh 1.00 Kapasitas: 13.000 CFM Daya: 3Ph/380v/50Hz/5000Watt

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 47: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

2.3 Tipe: Inline CentrifugalDumpera. SPF C 1 bh 1.00 Kapasitas: 13.000 CFM Daya: 3Ph/380v/50Hz/7500Watt

b. SPF C 2 bh 1.00 Kapasitas: 13.000 CFM Daya: 3Ph/380v/50Hz/7500Watt

c. SPF C 3 bh 1.00 Kapasitas: 13.000 CFM Daya: 1Ph/380v/50Hz/7500Watt

2.4 Tipe: Celing Mounteda. EF 9-TA bh 1.00 Kapasitas: 250 CFM Daya: 1Ph/220v/50Hz/100Watt

Sub Total Pekerjaan Presure Fan Lantai 9

2.5 Supply dan pemasangan Sentral Exhaust Fan untuk shaft(lantai roof)a. EF Tipe Inline Centrifugal Kapasitas 1.000 CFM unit 4.00 b. EF Tipe Inline Centrifugal Kapasitas 1.400 CFM unit 4.00 c. EF Tipe Inline Centrifugal Kapasitas 2.000 CFM unit 2.00 d. EF Tipe Inline Centrifugal Kapasitas 2.100 CFM unit 1.00 e. EF Tipe Inline Centrifugal Kapasitas 3.200 CFM unit 1.00 a. EF Tipe Inline Centrifugal Kapasitas 6.500 CFM unit 6.00 b. EF Tipe Inline Centrifugal Kapasitas 7.200 CFM unit 2.00 c. EF Tipe Inline Centrifugal Kapasitas 11.000 CFM unit 2.00 d. EF Tipe Inline Centrifugal Kapasitas 8.500 CFM unit 2.00

f. Pekerjaan ducting BJLS 60 (16"x10") m' 70.00 g. Pekerjaan Dumper (18"X18") unit 6.00

Sub Total Pekerjaan Fan di Shaft SUB TOTAL PEKERJAAN VENTILASI LANTAI 9

C SISTIM PEMADAM KEBAKARANPekerjaan Instalasi HYdrant

1 Pemipaan1.1 Pemipaan BSP, sch. 40 termasuk support

- dia. 100mm(4") m' 0.60 - dia. 65mm(2 1/2") m' 0.40 - dia. 50mm(2") m' 37.00 - Fitting & aksessories ls 1.00

1.2 valve- Gate valve, dia. 65mm(2 1/2") bh 1.00 - Air Release valve (AHV), dia 50 mm (2") bh 2.00

1.3 Hydrant box(Tipe B/indoor) Tanpa box, accsories lengkapRoll fire, Hydrant Valve, Jet Nosle,Hose Rack 1,5" unit 2.00

1.4 Tabung kebakaran fire extinguisher1.4.1 FE, tipe ABC Dry Chemical

- Kapasitas: 4kg bh 3.00 1.5 Testing & commissioning ls 1.00

2 Pekerjaan Instalasi Sprinkler2.1 Head sprinkler

- Tipe pendent bh 9.00

2.2 Pemipaan2.2.1 Black Steel Pipe(BSP) sch. 40 termasuk support

- dia. 100mm(4") m' 4.00 - dia. 65mm(2 1/2") m' 1.00 - dia.40 mm(1 1/2") m' 21.00 - dia. 25mm(1") m' 33.00 - Fitting & aksessories ls 1.00

Page 48: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

2.2.2 Valve- Butterfly valve,dia. 100mm(4") bh - - Air Relief Valve (RAV), dia. 50mm(2") bh 1.00 - Presure gauge bh 1.00

2.3 - Flow Switch bh 1.00

2.4 Pipa drain2.4.1 Polivinyt Chlorida Pipe (PVC) klas 10 kg/cm2

- dia. 50mm(2") m' 4.00 - dia. 25mm(1") m' 50.00 - Fitting & aksessories m' 1.00

2.4.2 valve:- Gate valve dia. 25mm(1") bh 1.00

2.5 Testing & commissioning ls 1.00 SUB TOTAL SISTEM PEMADAM KEBAKARAN LANTAI 9

SUB TOTAL PEKERJAAN MEKANIKAL LANTAI 9 II PEKERJAAN ELEKTRIKAL

PEKERJAAN PANEL DAYA1 Panel Exhust Fan unit 1.00 2 Panel Exhust Fan ( Pressure Fan ) Existing unit 1.00 3 Panel Booster Pump unit 1.00 4 Panel Pompa Air Panas unit 2.00

SUB TOTAL PEKERJAAN PANEL DAYA 9 4 PEKERJAAN KABEL POWER1 Kabel dari Panel MDP 9 ke Panel Exhust Fan,

NYY 4 x 50 mm2 +NYA 50 mm2 m' 25.00 2 Kabel dari Panel MDP 9 ke Panel Exhust ( Pressure Fan )

NYY 4 x 25 mm2 +NYA 25 mm2 m' 35.00 7 Kabel dari Panel MDP 9 ke Panel Booster Pump

NYY 4 x 6 mm2 +NYA 6 mm2 m' 19.00 8 Kabel dari Panel MDP 9 ke Panel Heat Pump ( Air Panas)

NYY 4 x 25 mm2 +NYA 25 mm2 m' 26.00 9 Kabel dari Panel EF ke Panel Exhust Ke EF 9 - T1 ttk 1.00

10 Kabel dari Panel EF ke Panel Exhust Ke EF 9 - T2 ttk 1.00 11 Kabel dari Panel EF ke Panel Exhust Ke EF 9 - T3 ttk 1.00 12 Kabel dari Panel EF ke Panel Exhust Ke EF 9 - T4 ttk 1.00 13 Kabel dari Panel EF ke Panel Exhust Ke SPF - 1

NYY 4 x 6 mm2 +NYA 6 mm2 m' 70.00 14 Kabel dari Panel EF ke Panel Exhust Ke SPF - 2

NYY 4 x 6 mm2 +NYA 6 mm2 m' 70.00 15 Kabel dari Panel EF ke Panel Exhust Ke SPF - 3

NYY 4 x 6 mm2 +NYA 6 mm2 m' 70.00 16 Kabel dari Panel PF ke Panel Exhust Ke SPF - C 1

NYY 4 x 6 mm2 +NYA 6 mm2 m' 70.00 17 Kabel dari Panel PF ke Panel Exhust Ke SPF - C 2

NYY 4 x 6 mm2 +NYA 6 mm2 m' 70.00 18 Kabel dari Panel PF ke Panel Exhust Ke SPF - C 3

NYY 4 x 6 mm2 +NYA 6 mm2 m' 70.00 SUB TOTAL PEKERJAAN KABEL POWER LANTAI 9

19 PENERANGAN LANTAI 91 BL CG 1X 36 TL LED ESS 16 W bh 31.00 2 Grid Switch 6 gang bh 1.00 3 Saklar Tunggal 16 A, 1 phasa bh 10.00 4 Stop kontak 16 A, 1phasa bh 4.00 5 Instalasi Penerangan ttk 31.00 6 Instalasi stop kontak 1 phase ttk 4.00 7 Testing & Commissioning ls 1.00

SUB TOTAL PEKERJAAN LAMPU PENERANGAN, TITIK LAMPU , STOP KONTAK, SAKLAR 9 SUB TOTAL PEKERJAAN LISTRIK LANTAI 9

Page 49: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

REKAPITULASI PEKERJAAN MEP LANTAI 91 SYSTEM VENTILASI

PEKERJAAN EXHUSTE FAN 2 PEKERJAAN PRESURRE FAN3 PEKERJAAN EXHUSTE FAN SHAFT4 SISTEM PEMADAM KEBAKARAN5 PEKERJAAN PANEL DAYA6 PEKERJAAN KABEL POWER7 PEKERJAAN INSTALASI PENERANGAN

JUMLAH

Page 50: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN VOL. SAT.

I PERALATAN UTAMA PNEUMATIC TUBE SYSTEM

A. TRANSFER ROOM, MAIN CONTROL & CABLES

1 Central Control Unit Dual Line System and Power Supply Unit 1.00 Set

2 Blower incl. assesories :1 Blower 3-Phase 2.00 Unit2 Blower Connecting Set 2.00 Set3 Blower Mounting Buffer 4.00 Buah4 Blower Sound Absorber 2.00 Buah5 Blower Controller 2.00 Buah6 Air/Transfer Diverter 4.00 Unit7 Bypass 2.00 Buah8 Cable YMM-J 4x2.5 gr 20.00 M9 Pressure Switch 2.00 Buah

10 Hilti Pipe Clamp 10.00 Buah11 Hose Clamp 50-70 8.00 Buah12 Air Hose 2.00 M13 Air Lid 2.00 Buah14 Air Bow 10.00 Buah15 Reduction Air Diverter 4.00 Buah16 Connecting Tube 2.00 Buah

SUB TOTAL PEKERJAAN BLOWER TOTAL PERALATAN TRANSFER ROOM & CENTRAL CONTROL

B. STATIONS & DIVERTERS AND ACCESSORIES1 Diverter 3-Way 6.00 Unit2 Bottom Loading Station 6.00 Unit3 Top Loading Station 10.00 Unit4 Multisendstation with Automatic Sending 1.00 Unit5 Multireceivingstation 2.00 Unit6 MultiLab Station with Automatic Sending 1.00 Unit

All Stations incl.: Basket, Cushion and Carrier Rack SUB TOTAL PEKERJAAN STATION DIVERTER

C. TUBE AND LINE SYSTEM1 Tubes PVC - Diam. 110 MM RAL 7000 737.00 M2 Tubes PVC - Diam. 110 MM Transparent 50.00 M3 Bend R=800, RAL 7001, Grey 93.00 Buah4 Sleeve 450.00 Buah5 Cable 2x2x0.23 + 3x2.5F 930.00 M

SUB TOTAL PEKERJAAN TUBE AND LINE

D. CARRIERS AND ACCESSORIES1 Long Carrier With Swivel Red Lid 330x72 MM With Chip 18.00 Buah2 Short Carrier With Swivel Yellow Lid 230x80 MM With Chip 72.00 Buah3 Test Tube Bag For Carrier 230x80 MM 90.00 Buah

SUB TOTAL PEKERJAAN CARRIER

E. CODE-TAG OPERATION AND PC-MONITORING1 PC-Monitoring and Programing System RFID, 2-Line System 1.00 Buah

SUB TOTAL PEKERJAAN MONITORING & PROGRAM SYSYTEM

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 51: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN VOL. SAT. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

F. VARIOUS INSTALLATION MATERIAL1 Supporting Mateial terdiri dari:

1 Clutch Clamp Stainless Steel 60.00 bh2 Endpiece Above / Below 10.00 bh3 PVC Conduit 20 MM 1,000.00 m'4 Sikla Base Plate 400.00 bh5 Pipe clamp 400.00 bh6 Sikla Screw Bolt 200.00 bh7 Screw Bolt 200.00 bh8 Cable Clip 1,800.00 bh9 Hose Clamp 100-120 40.00 bh

10 Air Lid (Silicon Flap) 20.00 bh11 Adhesive Glue 12.00 bh12 Cleaner For PVC-Tube 4.00 bh13 Dowel M10 400.00 bh

SUB TOTAL PEKERJAAN INSTALASI

II TEST AND COMMISIONING1 Biaya Test dan Komisioning 1.00 Ls

REKAPITULASI PEKERJAAN PNEUMATIC TUBE SYSTEM

Page 52: Rab Me Tanjung Pinang6

BILL OF QUANTITY (BQ)PENYELESAIAN KONSTRUKSI FISIK PEMBANGUNAN

RSUD PROVINSI KEPULAUAN RIAUJL. Baru Sungai Carang Km 8 - Tanjung Pinang

NO. URAIAN PEKERJAAN SAT. VOL.

I PERALATAN UTAMA SYSTEM MEKANIKAL ELEKTRIKAL A PENJERNIHAN AIR BERSIH / WATER TREATMENT LANTAI 3

(perlengkapan lengkap dan Automatic )1 Sand Filter - Aquatech SA 66 0 AD unit -

Kapasitas : 15.000 ltr/ jamMedia : Green SandMaterial : Polly glassSystem : Automatic back wash

2 Organic Removal Filter ; Aquatech - OR 66.0. AD unit - Kapasitas : 15.000 ltr/jam, Media : Activated CaebonMaterial : Polly glass, System : Automatic Back wash

3 Tanki SS unit 2.00 Kapasitas 1500 liter, Material Stainless steel

4 Tanki PE unit 2.00 Kapasitas 2000 liter, Material PE

5 Softener Filter, Aquatech SO 6.0 AD unit 1.00 Kapasitas : 1300 ltr /jam, Media : Resin Cation Material : Polly glass, System : Automatic Back wash

6 Reverse Osmosis - Aquatech -TRO 3000 S unit 1.00 Kapasitas : 10.000 ltr /hari Membrane : TW 30- 40 X 2Accesories : TDS Monitor, Smart control, High & Low pressureAutomatic Flasing, Permeate AlarmLegalitas : Izin Produksi Kemenkes

7 Ultra Violet ; Mightypure MP 22 unit 6.00 Kapasitas : 22 ltr/mntMave length : 249 nano meterIntensitas : 10.000 uw/square/1 CmAccessories ; intensitas meter monitor

8 Ultra Violet ; Mightypure MP 36 unit - Kapasitas : 45 ltr/mntMave length : 249 nano meterIntensitas : 10.000 uw/square/1 CmAccessories ; intensitas meter monitor

9 Mixed bed Filter : Aquatech - MB .2.0 M unit 1.00 Kapasitas : 450 ltr/jam

10 Housing dan Cartidge Filter unit 9.00 Ukuran : 20 "Kapasitas : 5 m

11 Feed Pump ; CM 15 - 4 unit - Kapasitas : 15.000 ltr/jamTotal Head : 32 m, System : Automatic pressure Switch

12 Feed Pump ; CM 3- 4 unit 2.00 Kapasitas : 3.000 ltr/jamTotal Head : 22 m, System : Automatic pressure Switch

13 Distributon Pump 1 ; CM 3 - 8 unit 2.00 Kapasitas : 3.000 ltr/jamTotal Head : 56m, System : Automatic pressure Switch

14 Distributon Pump 2 ; CM 5 - 8 unit - Kapasitas : 5.000 ltr/jamTotal Head : 62m, System : Automatic pressure Switch

15 Panel Kontrol pompa (PP WT) unit 1.00 16 Pressure Tank 300 Liter unit 1.00 17 Instalasi Peralatan utama pompa ls 1.00 18 Pondasi Pompa Filter + Pressure Tank unit 8.00 19 Instalasi Filter Air bersih ls 1.00 20 Sampling Fis kim Mikro buah 2.00 21 Test dan Commisioning ls 1.00

Sub Total Penjernihan Air Bersih/Water treatment LANTAI 3B PEKERJAAN CENTRAL WATER TREATMEN LANTAI 9 1 Tank Kapasitas 15000 Liter ( FRP) unit 2.00 2 Sand Filter - Aquatech SA 66 0 AD unit 1.00

Kapasita : 15.000 ltr/ jamMedia : Green SandMaterial : Polly glassSystem : Automatic back wash

HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

Page 53: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

3 Organic Removal Filter ; Aquatech - OR 66.0. AD unit 1.00 Kapasita : 15.000 ltr/jamMedia : Activated CarbonMaterial : Polly glassSystem : Automatic back wash

4 Feed Pump ; CM 15 - 4 unit 2.00 Kapasita : 15.000 ltr/jamTotal He : 32 mSystem : Automatic pressure Switch

4 Instalasi System pipa Distribusi water treatment Ls 1.00 5 Test dan Commisioning Ls 1.00

Sub Total Pekerjaan Central Water Treatment (Lantai 9)

C SYSTEM DAN PERALATAN UTAMA AIR PANAS1 Heat Pump Water Heater unit 3.00

Heating Ca: 42 KWHot water : 0,52 m3/ hrCOP : 3,0Power inpu: 5.2 KW (380 V/50 HZ)

2 Hot Water Storage Tank lengkap : unit 1.00 Pondasi, man hole, sensor + fitting - Stainless 6 mm - Water Ca: 10 000 liter - Insulatio : Poly uretane - Insulati : 0,6 mm alumunium sheet - Pressure: 4 0 5 bar - Dimensi : 5, 2 m x 1,9 m

3 Hot Water Circulation Pump lengkap : unit 2.00 Gate valve, non Return ValveCapasity : 100 l/mnt - 5 m3 /hrHead : 15 mPower inpu: 0.37 KW ( 380/50HZ )

4 Hot Water Pump lengkap : ( Distribution ) unit 3.00 Gate valve, non Return ValveCapasity : 150 l/mnt 9 m3/ hrHead : 65 mPower inpu: 2,5 KW ( 380/50HZ )

5 Piping + Instalation :Elektric Control Panel unit 1.00 Piping + System Instalation ls 1.00 Water Hummer 2 1/2" unit 2.00 Water Control Valve 2 1/2" unit 4.00 Water Level Control(WLC) + kabel unit 4.00 Chek Valve 2 1/2" unit 4.00 Akomodasi + mobilisasi mesin+ Tanki ls 1.00 Pressure Tank 500 liter ls 1.00 Pondasi Unit unit 8.00 Test dan Commisioning ls 1.00 Total System dan Peralatan Utama Air Panas

D SYSTEM DAN PERALATAN BOOSTER PUMP ( LANTAI 9 )1 Packaged Booster Pump

Capasity : 130 l/mnt 8 m3/ hr unit 2.00 Head : 30 mPower inpu: 2 KW ( 380/50HZ )Lengkap Panel kontrol

2 Pressure Tank 300 liter unit 1.00 3 Header 5" lengkap Chek Valve 1 1/2" ( Sealent) unit 2.00 4 Instalasi Pipa :

Polypropylene (PPR Pipe) PN-10 incl. Support- dia. 100 mm (4") m' 80.00 - dia. 80mm (3") m' 60.00 - dia. 65mm (2 1/2") m' 40.00 - Pondasi Unit unit 2.00

Page 54: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

5 Valve & aksessories:a. Gate valve, dia. 100 mm (4"), 10 Kg bh 18.00 b. Gate valve, dia. 80 mm(3"), 10 Kg bh 6.00 c. Check valve, dia. 80 mm(3"), 16 Kg bh 6.00 d. Strainer, dia. 65 mm(2 1/2") bh 2.00 e. Flexible joint, dia. 65 mm(2 1/2") bh 4.00 f. Pressure gauge bh 4.00 g. Water Level Control (WLC) + kabel unit 2.00 h. Water Hummer 4 " unit 1.00 Total System dan Peralatan Utama Booster Pump

E SYSTEM DAN PENGOLAHAN AIR LIMBAH /STP1 Dosing Pump Chlorine - LMI Unit -

Power -220 -230V 50 HZ- 230 W2 Submersible pump - Ebara Groundfs Unit -

Kapasitas: 200 ltr/mntHead : 6mMotor : 0.75 KW / 220 V , 1 Phase - 2 Pole

3 Roots Blower - Rotor Unit - Power : 220 /380V 50 HZ- 3 P 4 000 WModel : TSC 80Speed : 1400 Rpm, Pressure : 0,3 Kg/cm2Lengkap : Safety Valve,, Chek Valve,Base plate V

4 Screen- Bahan Stainless steel Unit - 5 Biocap Tank - lengkap Hytube diffuser, media bakteri Unit -

Material : FRP -Resin Iso ptalik inner LayerSize : 2,75 m x 12 m

6 BalanceTank Unit - Material : FRP -Resin Iso ptalik inner LayerSize : 2,75 m x 10 m

7 Elektrik Panel Kontrol Unit - Type : Automatic /manual , Indoor

8 Ph Controller - LMI Unit - Model DP 5000

9 Pekerjaan Instalasi listrik Ls - 10 Pelaksaaan Instalasi plumbing Ls - 11 Test dan Commisionung Ls - 12 Mobilisasi dan Demobilisasi Ls -

Sub Total System dan Pengolahan Air LimbahF RE KONDISI PERALATAN UTAMA PEMADAM KEBAKARAN 1 Re Kondisi Diesel Hydrant pump unit 1.00 2 Re Kondisi Elektrik Hydrant pump unit 1.00 3 Re kondisi Jocky pump unit 1.00 4 Fire Extinguiser 25 Kg ( Trolly) bh - 5 Pipa BSP Sech 40 medium class

a. Pipa Header 8" ls - b. dia 6 " m' - c. dia 4 " m' - d. dia 3" m' - e dia 2 1/2" m' -

6 Flexible joint 6" bh 1.00 7 Flexible joint 4" bh 1.00 8 Flexible joint 2 1/2 " bh 1.00 9 Gate valve 6" 10 K bh 2.00

10 Gate valve 4" 10 K bh 2.00 11 Gate valve 2 1/2 " 10 K bh 1.00 12 Strainer 6" 10 K bh 1.00 13 Strainer 2 1/2" 10 K bh 1.00 14 Chek valve 4" 10 K bh 1.00 15 Chek valve 2 1/2" 10 K bh 1.00 16 Foot Valve 6" bh 1.00 17 Foot Valve 2 1/2" bh 1.00 18 Safety valve 4" bh 1.00 19 Pressure Reducing valve 4" ( PRV) ( Lt BS s/d lt 4 ) unit 5.00 20 Pressure switch bh 2.00 21 Pressure gauge bh 2.00 22 System Panel Utama Pemadam Kebakaran ( Re kondisi ) ls 1.00 23 Test dan comissioning ls 1.00

Total Re Kondisi Peralatan Utama Pemadam Kebakaran

Page 55: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

G RE KONDISI PERALATAN UTAMA SYNCRONISING TRANSFORMER DAN GENSET I Syncronising Transformer 2000 KVA1 ACB 4000 A 3 p 65 KA unit 2.00 2 Motor mechanis unit 4.00 3 UVT 220 v unit 2.00 4 Closing coil unit 2.00 5 Power meter unit 2.00 6 MCB 6A 1 p bh 4.00 7 Under + Over Voltage unit 2.00 8 Over Current Relay unit 2.00 9 Reverse Power Relay unit 2.00

10 Syncronoscope Circutor unit 1.00 11 Double Volt meter unit 1.00 12 Double Frequency meter unit 1.00 13 Bus bar 4000 A ls 1.00 14 Selector AOM unit 1.00 15 Selector Syncrone unit 1.00 16 Emergency Stop unit 2.00 17 Phus button On Off unit 4.00 18 Pilot lump 220 V bh 16.00 19 Contactor Relay 220 V unit 2.00 20 Aux Contac Contactor unit 2.00 21 Relay 220 V + Socet ls 1.00 22 Time Swicht 220 V bh 2.00 23 Zero Volt meter ls 1.00 24 LBS 4000 A unit 2.00 25 Box Panel unit 1.00 26 Test dan Commisioning unit 1.00

Subtotal Re Kondisi Syncronising Transformer I Pekerjaan Syncronising Genset 1000 KVAI ACB 3200 A 4 p 65 KA ( distribusi ke MDP 5 ) unit 1.00 1 Motor mechanis unit 4.00 2 UVT 220 v unit 2.00 3 Closing coil unit 2.00 4 Power meter unit 2.00 5 MCB 6A 1 p bh 4.00 6 Under + Over Voltage unit 2.00 7 Over Current Relay unit 2.00 8 Reverse Power Relay unit 2.00 9 Syncronoscope Circutor unit 1.00

10 Double Volt meter unit 1.00 11 Double Frequency meter unit 1.00 12 Selector AOM unit 1.00 13 Selector Syncrone unit 1.00 14 Emergency Stop unit 2.00 15 Phus button On Off unit 4.00 16 Pilot lump 220 V bh 16.00 17 Contactor Relay 220 V unit 2.00 18 Aux Contac Contactor unit 2.00 19 Relay 220 V + Socet ls 1.00 20 Time Swicht 220 V bh 2.00 21 Zero Volt meter ls 1.00 22 Test dan Commisioning unit 1.00

Subtotal Re Kondisi Genset 1000 KVA Total Re Kondisi SyncroneisingTransformer dan Genset

H TEGANGAN RENDAH DAN CAPASITOR BANKa Re Kondisi Capasitor Bank 1.000 KVA ls 1.00

SUB TOTAL KAPASITOR BANK EXISTING 1 Capasitor Bank 420 KVAR2 Capasitor Bank 420 KVAR ls 1.00 3 Instalasi utama capasitor bank ls 1.00 4 Box panel capasitor set 1.00

SUB TOTAL KAPASITOR BANK b Sekat Ruang Transformer1 Sekat Ruang PLN dan Transformer ls 1.00 2 Pintu besi Ruang Transformer set 1.00

Sub Totalc RE KONDISI TRANSFORMER 2000 KVA

Re Kondisi Transformer 2000 KVA ( 20 KV/380 V) ls 1.00 SUB TOTAL RE KONDISI TRANSFORMER 2000 KVA

Page 56: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

d Instalasi Kabel Power Tegangan Rendah 1 Kabel dari Transformer ke LVMDP dan Capasitor Bank m' 20.00

NYY 20 x 1 x300 mm2 + NYA 1 x 300 mm22 Kabel ladder elektrikal 300x100 mm m' 20.00 3 Test dan Commisioning ls 1.00

Sub Total SUB TOTAL RE KONDISI KABEL POWER TEGANGAN RENDAH

I PERALATAN UTAMA CCTV1 DVR standalone PDR 6160A 2 Teta byte unit 1.00 2 30 Chanel DVR unit 2.00 3 Module unit 3.00 4 Rack Monitor LCD 21 unit 1.00 5 Video distribution 2 in 16 out unit 3.00 6 Monitor LCD 21 " dan Instalasi Central Utama unit 8.00 7 Keyboard control TX 1200 unit 3.00 8 Sofware dan Training ls 1.00 9 Cable Ladder 30 x 10 Cm (Elektrikal) m' 60.00

10 Cable Ladder 20 x 10 Cm (Elektronika) m' 60.00 11 Fixed Dome Camera With Housing unit 2.00 12 Camera Rotary With Housing unit 2.00 13 Instalasi peralatan utama ls 1.00 14 Test dan Commisioning ls 1.00

Sub TotalJ PERALATAN UTAMA MATV

1 Spliter MATV 2 way bh 1.00 2 Spliter MATV 3 way bh 2.00 3 Spliter MATV 4 way bh 3.00 4 Tap Off unit 2 way bh 1.00 5 Tap Off unit 3 way bh 2.00 6 Tap Off unit 4 way bh 3.00 7 Booster MATV bh 8.00 8 Outlet TV bh 6.00 9 Decoder unit 16.00

10 Modulator unit 17.00 11 Combiner unit 3.00 12 Devider unit 6.00 13 LNB dual double unit 3.00 14 Antena Parabola unit 1.00 15 TV LCD 21 inch Monitoring unit 5.00 16 Instalasi kabel distribusi Utama ls 1.00 17 Instalasi kabel distribusi dari spliter ke Outlet ttk 6.00 18 Instalasai Power ttk 6.00 19 Test dan Commisioning ls 1.00

Sub Total MATVK PERALATAN UTAMA FIRE ALARMa Re Kondisi Peralatan Utama Fire Alarm ls 1.00

b PERALATAN UTAMA FIRE ALARM lt 5 s/d 91 Master Control Fire Alarm 2 loop semi adressable unit 1.00

( 484 addres devices )2 Annunciator LCD 2 loope unit 1.00 3 Zone addres monitor Module bh 4.00 4 Sounder addres Module bh 4.00 5 Short circuit Isolator bh 4.00 6 Dual I/O Module bh 4.00 7 Terminal Box - FA, F 30 pars unit 2.00 8 Instalasi peralatan utama ls 1.00 9 Grounding ls 1.00

10 Test dan Commisioning ls 1.00 Sub Total Fire Alarm

L PERALATAN UTAMA SOUND SYSTEM ( BGM )1 Rack cabinet dan accesiries Unit - 2 Radio Tuner Modulle AM/FM w/Ant. Unit - 3 DVD Player/MP3 SONY Unit - 4 Monitor panel Unit 1.00 5 Mixer Pre-amplifiyer w/ module Unit - 6 Sirine w/Relay switch Modulle Unit - 7 Program Selector Modulle Unit 1.00 8 Graphic Equalizer 2 ch Unit - 9 Power switch panel Unit 1.00

10 Junction box panel Unit 1.00 11 Speaker Selector 10 Chanel Unit 1.00

Page 57: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

12 Power amplifier 600W Unit 1.00 13 Blower panel Unit - 14 Change Over Switch Unit - 15 Remote Microphone Unit 1.00 16 Emergency Paging Microphone Unit 1.00 17 Main Distriution Frame Unit - 18 Speaker monitor 15" Unit 1.00 19 Terminal box SS Unit 1.00 20 Instalasi peralatan utama m' 250.00 21 Test dan Commisioning Ls 1.00

SUB TOTAL PEKERJAAN SOUND SYSTEM

M PENANGKAL PETIR WTP1 Head penangkal petir non Radio aktif Radius proteksi 100 m unit 1.00 2 Down Conductor cable NYA 50 mm m' 40.00 3 Dudukan tiang penangkal petir unit 1.00 4 Lightning Strike counter - Analog unit 1.00 5 Bak kontrol 40x40 Cm unit 2.00 6 Grounding penangkal petir/Ground rood ls 1.00 7 Obstruction lamp ( phillip) ls 1.00 8 Pipa GIP medium 1 1/2" m' 3.00 9 Gali tanah m' 10.00

10 Testing & Commisioning Ls 1.00 SUB TOTAL PEKERJAAN PENANGKAL PETIR

N PEKERJAAN UPS 30 KVA2.1 UPS 30 KVA In put 3 P, Output 3 P back up 30 menit unit 2.00 2.2 Trafo Isolasi 30 KVA unit 2.00 2.3 Biaya Instalasi ( NYY 4 X35 MM2 ) m' 90.00 2.4 Grounding set 1.00 2.5 Biaya Pemasangan unit 2.00 2.6 Biaya testing+ training ls 1.00 2.7 Biaya transfortasi + Mobilisasi ls 1.00

SUB TOTAL PEKERJAAN UPS

O PEKERJAAN PERALATAN UTAMA GAS MEDIS1 Oxygen Generator System, Kapasitas 200 LPM unit 1.00 2 Medical Gas Manifold Oxygen , Kapasitas 2 x 10 Cylinder unit 1.00 3 Pemasangan peralatan Utama ls 1.00

SUB TOTAL PEKERJAAN PERALATAN UTAMA GAS

P PEKERJAAN INSTALASI UTAMA GAS MEDISPipa Tembaga ASTM B 819 Type L

Diameter 7/8" m' 12.00 Diameter 1 1/8" m' 18.00 Diameter 1 3/8" m' 18.00 Diameter 1 5/8" m' 18.00 Diameter 2 1/8" m' 95.00 Diameter 2 5/8" m' 82.00 Rangka dan Pengantung ls 1.00

SUB TOTAL PEKERJAAN INSTALASI PIPA SUB TOTAL PEKERJAAN PERALATAN UTAMA GAS MEDIS

Q PEKERJAAN PERALATAN UTAMA CHILLERa Pekerjaan instalasi Pipa Chiller

1 Chiller type Air cool, Kapasitas 225 TR - 306 KW/ 382 KVA unit 1.00 2 Pompa Chiller 540 GPM, Head 45 m, Centrifugal - Terpasnag unit 1.00 3 Biaya Pasang Chiler unit 1.00 4 Biaya Angkutan chiller unit 1.00 5 Pipa BSP Shec 40 c/w isolasi , metal jacketing

dia 6^ m' 6.00 dia 5^ m' 6.00

6 Batterfly Valve 5" bh 2.00 7 Balancing Valve 5" bh 2.00 8 Chek Valve 5" bh 1.00 9 Flexibel Joint 5 " bh 1.00

10 Flow Switch bh 1.00 11 Thermometer bh 4.00 12 Pressure Gauge bh 4.00

Page 58: Rab Me Tanjung Pinang6

NO. URAIAN PEKERJAAN SAT. VOL. HARGA SATUAN(Rp.)

JUMLAH HARGA(Rp.)

b Pekerjaan instalasi Pompa Chillera Gate Valve 6" bh 2.00 b Batterfly Valve 6" bh 2.00 c Chek Valve 6" bh 1.00 d Strainer 6 " bh 1.00 e Flexible Joint 6 " bh 2.00 f Pressure Gauge bh 2.00 g Air Vent dia 1" bh 1.00 h Drain Valve 2 " bh 2.00

c Pekerjaan instalasi Power Chiller dan pompa Chillera NYY 2x 4 x 1 x240 mm + NYA 70 ( LVMDP ke MDP Chiller m' 80.00 b NYY 2x4 x 1 x185 mm + NYA 70 (MDP Chiller ke chiller 2) m' 50.00 c NYY 4x50 mm + NYA 35 mm ( MDP Chiller ke Pompa Ciller 3) ls 50.00 d MCCB 800 Ampere ( Chiller 2 ) bh 2.00 e MCCB 100 Ampere ( Pompa Chiller 3 ) bh 2.00 f Test dan Commisionung ls 1.00

SUB TOTAL PEKERJAAN PERALATAN UTAMA CHILLER