GAMBARAN UMUM PROYEK PENGURUGAN JALAN TOLL PEJAGAN - PEMALANG OWNER : BAKRIE BROTHERS MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA) PT. TRI MANUNGGAL PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI) VOLUME KONTRAK : 5.000.000 M3. ATAU 250,000 DUMP HARGA KONTRAK : Rp. 72,000.00 / M3. PADAT VIBRO RENCANA ANGGARAN PELAKSANAAN ( PER M3. ) BIAYA RITASI DT & QUARRY : 1. SEWA DUMP TRUCK = Rp. 8,910 2. BIAYA BBM DT = Rp. 6,000 3. BIAYA SUPIR DT = Rp. 2,255 4. DEPOSIT TANAH = Rp. 6,250 5. SEWA EXCAVATOR = Rp. 935 6. BIAYA BBM ALAT = Rp. 802 7. BIAYA OPERATOR ALAT = Rp. 167 BIAYA PEMADATAN : 1. SEWA VIBRO & BULDOZER = Rp. 1,007 2. BIAYA BBM ALAT = Rp. 807 3. BIAYA OPERATOR ALAT = Rp. 203 BIAYA UMUM & ADMIN. : 1. PEMOTONGAN OLEH MAIN KONTRAKTOR ( UNTUK BIAYA PAJAK & ADMINISTRASI ) = Rp. 12,000 2. BIAYA PERSIAPAN/PENDAHULUAN = Rp. 2,000 JUMLAH = Rp. 41,336 PROFIT = Rp. 30,665 JUMLAH = Rp. 72,000 CATATAN : PROFIT Rp 30,665 /M3. BELUM TERMASUK UNTUK FEE SUKSES PHK MEDIASI ASUMSI - ASUMSI : WAKTU PELAKSANAAN : VOLUME KONTRAK : 5,000,000 M3. 1. EXCAVATOR (BEKO) KEMAMPUAN ALAT (EXCAVATOR) 50 M3./JAM GALI/MUAT PER HARI = 10 JAM 500 M3. JML PEMAKAIAN ALAT 10 UNIT GALI/MUAT PER HARI = 10 JAM 5,000 M3. JML WAKTU PELAKSANAAN 1,000 HARI 33 BULAN 2. DUMP TRUCK : Kapasitas Dump truk 20 Frequensi Dump Truk 250 trip/hari Jumlah armada 8 DT Frequensi tiap 1 DT 33 trip WAKTU SIKLUS ALAT/DT : 1. EXCAVATOR (BEKO) Kapasitas Bucket 1.2 M3. Kapasitas Produksi Per Jam 50 M3. Jumlah Jam Kerja 10 Jam Jumlah Produksi/Alat 500 M3. Jumlah Pemakaian Alat 10 Unit m 3 /DT

Transcript of Proyek Pengurugan Toll Pejagan-Pemalang (Rev).xls

Page 1: Proyek Pengurugan Toll Pejagan-Pemalang (Rev).xls

GAMBARAN UMUM PROYEK PENGURUGANJALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA) PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)

VOLUME KONTRAK : 5.000.000 M3. ATAU 250,000 DUMP

HARGA KONTRAK : Rp. 72,000.00 / M3. PADAT VIBRO

RENCANA ANGGARAN PELAKSANAAN ( PER M3. )

BIAYA RITASI DT & QUARRY :1. SEWA DUMP TRUCK = Rp. 8,910 2. BIAYA BBM DT = Rp. 6,000 3. BIAYA SUPIR DT = Rp. 2,255 4. DEPOSIT TANAH = Rp. 6,250 5. SEWA EXCAVATOR = Rp. 935 6. BIAYA BBM ALAT = Rp. 802 7. BIAYA OPERATOR ALAT = Rp. 167 BIAYA PEMADATAN :1. SEWA VIBRO & BULDOZER = Rp. 1,007 2. BIAYA BBM ALAT = Rp. 807 3. BIAYA OPERATOR ALAT = Rp. 203 BIAYA UMUM & ADMIN. :1. PEMOTONGAN OLEH MAIN KONTRAKTOR ( UNTUK BIAYA PAJAK & ADMINISTRASI ) = Rp. 12,000 2. BIAYA PERSIAPAN/PENDAHULUAN = Rp. 2,000

JUMLAH = Rp. 41,336

PROFIT = Rp. 30,665

JUMLAH = Rp. 72,000

CATATAN : PROFIT Rp 30,665 /M3. BELUM TERMASUK UNTUK FEE SUKSES PHK MEDIASI

ASUMSI - ASUMSI :

WAKTU PELAKSANAAN :

VOLUME KONTRAK : 5,000,000 M3.

1. EXCAVATOR (BEKO)KEMAMPUAN ALAT (EXCAVATOR) 50 M3./JAMGALI/MUAT PER HARI = 10 JAM 500 M3.JML PEMAKAIAN ALAT 10 UNITGALI/MUAT PER HARI = 10 JAM 5,000 M3.

JML WAKTU PELAKSANAAN 1,000 HARI 33 BULAN

2. DUMP TRUCK :

Kapasitas Dump truk 20Frequensi Dump Truk 250 trip/hariJumlah armada 7 DTFrequensi tiap 1 DT 33 trip

WAKTU SIKLUS ALAT/DT :

1. EXCAVATOR (BEKO)Kapasitas Bucket 1.2 M3.Kapasitas Produksi Per Jam 50 M3.Jumlah Jam Kerja 10 JamJumlah Produksi/Alat 500 M3.Jumlah Pemakaian Alat 10 Unit

m3/DT

Page 2: Proyek Pengurugan Toll Pejagan-Pemalang (Rev).xls

GAMBARAN UMUM PROYEK PENGURUGANJALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA) PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)Jumlah Produksi Per Hari 5,000 M3.

Page 3: Proyek Pengurugan Toll Pejagan-Pemalang (Rev).xls

GAMBARAN UMUM PROYEK PENGURUGANJALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA) PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)2. DUMP TRUCK :

Jarak Tempuh 2 kmWaktu muat dan manouver 6 menitKecepatan (dgn muatan) 20 km/jamWaktu tempuh (dgn muatan) 6 menitWaktu bongkar dan manouver 2 menitKecepatan (tanpa muatan) 30 km/jamWaktu tempuh (tanpa muatan) 4 menitJml Waktu Bongkar/Muat/Perjalanan 18 menit/tripJumlah trip tiap jam 3.33 trip/jam

0.30 jam/trip Jam kerja per hari 10 jam/hari Total trip per hari (real time) 33 trip/hari

Total daya angkut per hari/DT 667

Target Volume Angkut per hari 5,000 Jumlah Dump Truk yg diperlukan 7 Unit DT

PREDIKSI PELAKSANAAN PEKERJAAN PENGURUGAN :

1 PEKERJAAN PERSIAPAN :

- DIREKSI KEET / SITE OFFICE - MOBILISASI DAN DEMOBILISASI PERLATAN & PERSONIL - PENGUKURAN LEVELING TANAH DASAR - PEMBUATAN JALAN AKSES DARI QUARRY KE JALAN UMUM

2 PEKERJAAN PEMATANGAN LAHAN SEPANJANG DAERAH TIMBUNAN TANAH :

- PEMBONGKARAN TERHADAP PENGHALANG YANG MUNGKIN ADA - MEMINDAHKAN DAN MENANGANI AIR YANG ADA AGAR TIDAK TERHENTI - MEMBUANG DAN MENANGANI LOKASI TIMBUNAN TANAH YANG BERLUMPUR - MENGHENTIKAN / MENYUMBAT SUMBER AIR TANAH YANG TIMBUL APABILA ADA

3 PEKERJAAN PEMADATAN TANAH DASAR SEPANJANG LOKASI KERJA

4 PEKERJAAN PENIMBUNAN TANAH DAN PEMADATAN

- SETIAP PENGHAMPARAN 30 CM. ATAU SESUAI KETENTUAN YANG ADA DALAM SPESIFIKASI YANG DIKELUARKAN PIHAK OWNER DAN ATAU STANDAR PT. JASA MARGA

5 PEKERJAAN COMMISIONING TEST PEMADATAN DENGAN MENGGUNAKAN PERALATANSAND CONE DAN ATAU SHEEP FOOT ROLLER SAMPAI DENGAN MEMENUHI TINGKATKEPADATAN DAN DAYA DUKUNG YANG DITETAPKAN SESUAI PERATURAN UNTUK JALAN TOLL.

PERALATAN YANG DIGUNAKAN :

1 EXCAVATOR 5 MOTOR GRADER2 DUMP TRUCK 6 SHEEP FOOT ROLLER3 BULDOZER 7 TRUCK TANGKI AIR4 COMPACTOR / VIBRO ROLLER 8 PERALATAN PENDUKUNG LAINNYA

CILEGON, 12 DESEMBER 2009S E & O

m3 /hr/DT

m3

Page 4: Proyek Pengurugan Toll Pejagan-Pemalang (Rev).xls

GAMBARAN UMUM PROYEK PENGURUGANJALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA) PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)J A U H A R Y

Page 5: Proyek Pengurugan Toll Pejagan-Pemalang (Rev).xls

RENCANA ANGGARAN PENDAPATAN DAN BIAYA OPERASIONALPROYEK PENGURUGAN JALAN TOLL PEJAGAN - PEMALANG

I. PENDAPATAN :

NILAI KONTRAK PENGURUGAN TANAH MERAH : 5.000.000 M3. x Rp. 72.000,- = Rp. 360,000,000,000

II. BIAYA OPERASIONAL (PENGELUARAN PROYEK) :

A. BIAYA RITASE DUMP TRUCK DAN QUARRY :

1 DUMP TRUCK :

SEWA : 135 UNIT x Rp. 30.000.000,- x 11 BULAN = Rp. 44,550,000,000 BBM : 20 LTR/TRIP x 250.000 TRIP x Rp. 6.000,- = Rp. 30,000,000,000 SUPIR : Rp. 250.000,-/HARI x 334 HARI x 135 UNIT = Rp. 11,272,500,000

= Rp. 85,822,500,000 2 EXCAVATOR :

SEWA : 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM = Rp. 4,676,000,000 BBM : 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,- = Rp. 4,008,000,000 OPERATOR : Rp. 250.000,-/HARI x 334 HARI x 10 UNIT = Rp. 835,000,000

= Rp. 9,519,000,000 3 PEMBELIAN TANAH MERAH :

: 250.000 DUMP (RIT) x Rp. 125.000,-/DUMP = Rp. 31,250,000,000

JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY : = Rp. 126,591,500,000

B. BIAYA PEMADATAN :

1 SEWA ALAT :

- BULDOZER D6 : 6 UNIT x 3.340 JAM x Rp. 135.000,-/JAM = Rp. 2,705,400,000 - COMPACTOR/VIBRO R. : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM = Rp. 911,820,000 - MOTOR GRADER : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM = Rp. 911,820,000 - SHEEP FOOT ROLLER : 1 UNIT x 500 JAM x Rp. 135.000,-/JAM = Rp. 67,500,000 - TRUK TANGKI AIR : 2 UNIT x Rp. 20.000.000,- x 11 BULAN = Rp. 440,000,000

= Rp. 5,036,540,000 2 BBM ALAT :

- BULDOZER D6 : 20 LTR x 3.340 JAM x 6 UNIT x Rp. 6.000,- = Rp. 2,404,800,000 - COMPACTOR/VIBRO R. : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- = Rp. 631,260,000 - MOTOR GRADER : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- = Rp. 631,260,000 - SHEEP FOOT ROLLER : 15 LTR x 500 JAM x 1 UNIT x Rp. 6.000,- = Rp. 45,000,000 - TRUK TANGKI AIR : 80 LTR x 334 HARI x 2 UNIT x Rp. 6.000,- = Rp. 320,640,000

= Rp. 4,032,960,000 3 OPERATOR ALAT :

- BULDOZER D6 : Rp. 250.000,-/HARI x 334 HARI x 6 UNIT = Rp. 501,000,000 - COMPACTOR/VIBRO R. : Rp. 250.000,-/HARI x 224 HARI x 3 UNIT = Rp. 168,000,000 - MOTOR GRADER : Rp. 250.000,-/HARI x 224 HARI x 3 UNIT = Rp. 168,000,000 - SHEEP FOOT ROLLER : Rp. 250.000,-/HARI x 50 HARI x 1 UNIT = Rp. 12,500,000 - TRUK TANGKI AIR : Rp. 250.000,-/HARI x 334 HARI x 2 UNIT = Rp. 167,000,000

= Rp. 1,016,500,000

JUMLAH BIAYA PEMADATAN : = Rp. 10,086,000,000

C. BIAYA PEMOTONGAN DARI MAIN KONTRAKTOR :

UNTUK BIAYA PPH PAJAK KONSTRUKSI DAN BIAYA ADMINISTRASI : 5.000.000 M3. x Rp. 12.000,-/M3. = Rp. 60,000,000,000

D. BIAYA PERSIAPAN / PENDAHULUAN PROYEK :

1 BIAYA BIKIN DIREKSI KIT / SITE OFFICE = Rp. 75,000,000 2 BIAYA MOBILISASI DAN DEMOBILISASI PERALATAN & PERSONIL = Rp. 230,000,000 3 BIAYA PENGUKURAN LEVELING TANAH DASAR = Rp. 100,000,000 4 BIAYA BIKIN JALAN AKSES DARI QUARRY KE JALAN UMUM = Rp. 3,500,000,000 5 BIAYA PEMATANGAN LAHAN SEPANJANG LOKASI KERJA = Rp. 2,750,000,000 6 BIAYA OVERHEAD PROYEK, BIAYA COMMISIONING TEST PEMADATAN DAN BIAYA TAK TERDUGA LAINNYA = Rp. 3,345,000,000

JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK : = Rp. 10,000,000,000

REKAPITULASI :

PENDAPATAN : = Rp. 360,000,000,000

BIAYA OPERASIONAL (PENGELUARAN PROYEK) :

A. JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY = Rp. 126,591,500,000 B. JUMLAH BIAYA PEMADATAN = Rp. 10,086,000,000 C. JUMLAH PEMOTONGAN OLEH MAIN KONTRAKTOR = Rp. 60,000,000,000 D. JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK = Rp. 10,000,000,000

= Rp. 206,677,500,000

KEUNTUNGAN KOTOR PROYEK : = Rp. 153,322,500,000

NOTE : BELUM TERMASUK FEE SUKSES UNTUK PIHAK MEDIASI.-