Pertemuan 26 Activity Network

15
1 Pertemuan 26 Activity Network Matakuliah : T0026/Struktur Data Tahun : 2005 Versi : 1/1

description

Pertemuan 26 Activity Network. Matakuliah: T0026/Struktur Data Tahun: 2005 Versi: 1/1. Learning Outcomes. Pada akhir pertemuan ini, diharapkan mahasiswa akan mampu : Mahasiswa dapat menjelaskan konsep aplikasi graph dalam activity network. Outline Materi. - PowerPoint PPT Presentation

Transcript of Pertemuan 26 Activity Network

Page 1: Pertemuan 26 Activity Network

1

Pertemuan 26Activity Network

Matakuliah : T0026/Struktur Data

Tahun : 2005

Versi : 1/1

Page 2: Pertemuan 26 Activity Network

2

Learning Outcomes

Pada akhir pertemuan ini, diharapkan mahasiswa

akan mampu :

• Mahasiswa dapat menjelaskan konsep aplikasi graph dalam activity network

Page 3: Pertemuan 26 Activity Network

3

Outline Materi

• Activity on vertex (AOV) network • AOV network(cont.) • An AOV network • Topology sort • Example of topology sort • Activity on edge (AOE) network • Earliest time • Latest time • Other factors • Critical paths • Calculation of earliest times • Calculation of Latest times • Early and late and critical values

Page 4: Pertemuan 26 Activity Network

4

Activity on vertex (AOV) network

• Activity on vertex (AOV) network– An activity on vertex(AOV)network, is a digraph G in which

the vertices represent tasks or activities and the edges represent precedence relations between tasks.

• Predecessor : – Vertex i in an AOV network G is a predecessor of vertex j iff

there is a directed path from vertex i to vertex j – Vertex i is an immediate predecessor of vertex j iff <i, j> is an

edge in G

• Successor : – If i is a predecessor of j, then j is a successor of i. – If i is an immediate predecessor of j, then j is an immediate

successor of i

Page 5: Pertemuan 26 Activity Network

5

AOV network(cont.)

• Transitive – A relation " " is transitive iff for all triples i, j,k, i j and j k => i k ‧ ‧ ‧ ‧

• Irreflexive – A relation" "is irreflexive on a set S if i i is false for all elements, i, ‧ ‧

in S.

• Partial order – A partial order is a precedence relation that is both transitive and

irreflexive

• Topological order – A topological order is a linear ordering of the vertices of a graph

such that, for any two vertices, i, j, if i is a predecessor of j in the network then i precedes j in the linear ordering.

Page 6: Pertemuan 26 Activity Network

6

An AOV network

Page 7: Pertemuan 26 Activity Network

7

Topology sort

for (i = 0; i<n; i++) { if every vertex has a predecessor {

fprintf(stderr,"Network has a cycle. \n"); exit(1);

} pick a vertex v that has no predecessors; output v; delete v and all edges leading out of v from the network;

}

Page 8: Pertemuan 26 Activity Network

8

Example of topology sort

•Topological order generated : V0,V3,V2,V5,V1,V4

Page 9: Pertemuan 26 Activity Network

9

Activity on edge (AOE) network

• AOE network – Edge represents task or activity to be performed on a project

– Vertex represents event which signal the completion of certain activities

• Remarks on AOE – Determine the minimum amount of time required to complete a project

– An assessment of the activities whose duration should be shortened to reduce the overall completion time

• Evaluate performance – activity whose duration time should be shortened

– minimum amount of time

• Critical path – A path that has the longest length

– Minimum time required to complete the project

Page 10: Pertemuan 26 Activity Network

10

Earliest time

• The earliest time an event, vi, can occur is the length of the longest path from the start vertex v0 to vertex vi – i.e., the earliest start time for all activities represented by edges leaving

that vertex

– denote the time by e(i) for activity ai

• Example : v4 is 7, e(6)= e(7)= 7

Page 11: Pertemuan 26 Activity Network

11

Latest time

• Latest time : – l(i) of activity, ai, is the latest time the activity may start without

increasing the project duration

• Projection duration : – length of the longest path from start to finish

• Example : e(5)= 5 and l(5)= 8, e(7)= 7 and l(7)= 7

Page 12: Pertemuan 26 Activity Network

12

Other factors

• Critical activity : – An activity for which e(i)= l(i)

• Remarks on critical : – The difference between l(i) and e(i) is a measure of

how critical an activity is – Identify critical activities so that we may concentrate

our resources to reduce a project's duration

• Determine critical paths : – Delete all noncritical activities – Generate all the paths from the start to finish vertex.

Page 13: Pertemuan 26 Activity Network

13

Critical paths

•Critical paths: •v0, v1, v4, v7, v8 , length= 18 ; v0, v1, v4, v6, v8 , length= 18

Page 14: Pertemuan 26 Activity Network

14

Calculation of earliest times

• earliest[j]: the earliest event occurrence time for all event j in the network.

• latest[j]: the latest event occurrence time for all event j in the network.

• If activity ai is represented by edge <k, l> – early(i) = earliest[k] – late(i) = latest[l] - duration of activity ai

• We compute the times earliest[j] and latest[j] in two stages: a forward stage and a backward stage.

• During the forwarding stage, we start with earliest[0] = 0 and compute the remaining start times using the formula: – earliest[j] = max{ earliest[i] + duration of <i, j> }

Page 15: Pertemuan 26 Activity Network

15

Calculation of Latest times

• In the backward stage, we compute the values of latest[i] using a procedure analogous to that used in the forward stage.

• We start with latest[n-1] = earliest[n-1] and use the equation: – latest[j] = min{ latest[i] - duration of <j, i> }