Gantt Chart PA DEPOK

download Gantt Chart PA DEPOK

of 3

Transcript of Gantt Chart PA DEPOK

  • 8/15/2019 Gantt Chart PA DEPOK

    1/3

    ID Task

    Mode

    Task Name Duration Start Finish

    1 START 1 day Wed 20 /07 /1 Wed 20 /07 /16

    2 PEKERJAAN TEMBOK PENAHAN TANAH 53 days Thu 21/07/1 Sun 11/09/16

    3 Pekerjaan Pasang Bouwplank & Pengukuran 1 day Thu 2 1/0 7/1 6Thu 21 /07 /1 6

    4 Pek.GalianTanah Pondasi Batu Kali 7 days Thu 21/07/16Wed 27/07/16

    5 Pek.Urugan Pasir 1 day Wed 27/07/1Wed 27/07/16

    6 Pek.Aanstamping Batu Kali 2 days Wed 27/07/1Thu 28/07/16

    7 Pek.Pasangan Batu Kali 1:4 35 days Fri 29/07/16 Thu 01/09/16

    8 Pek.Plester dan Acian 7 days Fri 26/08/16 Thu 01/09/16

    9 Pek.Suling-Suling PVC Dia1“ Dan Injuk 35 days Fri 29/07/16 Thu 01/09/16

    10 Pek.Pengecatan 10 days Fri 02/09/16 Sun 11/09/1611 PEKERJAAN PAGAR BRC 9 day s Tu e 0 6/ 09 /1 We d 1 4/ 09 /1 6

    12 Pekerjaan Galian Dudukan Tiang 8 days Tue 06/09/16Tue 13/09/16

    13 Pekerjaan BetonTumbuk 5 days Wed 07/09/1Sun 11/09/16

    14 Pekerjaan Pemasangan Pagar BRC P.240 X T.90 Dia8" 7 days Thu 08/09/16Wed 14/09/16

    15 PEKERJAAN DINDING PAGAR SAMPING BANGUNAN 13 days Wed 03/08/1Mon 15/08/16

    16 Pekerjaan Sloof 15/20 1 day Wed 03/08/1Wed 03/08/16

    17 -Cor Beton K-175 (betonpraktis) 1 day Wed 03/08/1Wed 03/08/16

    18 -Tulangan Pembesian dengan Besi polos Atau BJTD24 1 day Wed 03/08/1Wed 03/08/16

    19 -Bekisting 1 day Wed 03/08/1Wed 03/08/16

    20 Pekerjaan Kolom 20/20 1 day Thu 04/08/1 Thu 04/08/16

    21 -Cor Beton K-175(betonpraktis) 1 day Thu 04/08/16Thu 04/08/16

    22 -Tulangan Pembesian dengan Besi polos Atau BJTD24 1 day Thu 04/08/16Thu 04/08/16

    23 -Bekisting 1 day Thu 04/08/16Thu 04/08/16

    24 Pekerjaan Ring Balok15/20 1 day Sat 06/08/16Sat 06/08/16

    25 -Cor Beton K-175(betonpraktis) 1 day Sat 06/08/16 Sat 06/08/16

    26 -Tulangan Pembesian dengan BesipolosAtauBJTD24 1 day Sat 06/08/16Sat 06/08/16

    27 -Bekisting 1 day Sat 06/08/16 Sat 06/08/16

    28 Pek.Pasangan Bata 1PC:3PP 3 days Fri 05/08/16 Sun 07/08/16

    29 Pek.Plester 1PC:3PS 3 days Sun 07/08/16Tue 09/08/16

    30 Pek.Acian 5 days Tue 09/08/16Sat 13/08/16

    31 Pek.Plester Ciprat / Kasar 2 days Tue 09/08/16Wed 10/08/16

    32 Pek.Profilan Kolom 5 days Thu 11/08/16Mon 15/08/16

    33 Pek.Pengecatan Dinding 3 days Tue 09/08/16Thu 11/08/16

    34 PEKERJAAN PAGAR & PINTU GERBANG 9 days Tue 09/08/1 Wed 17/08/16

    35 Pekerjaan Bongkaran 1 day Tue 09/08/16Tue 09/08/16

    36 Pek.Kolom Praktis 25/25, BetonK-175 1 day Wed 10/08/1Wed 10/08/16

    37 -Cor Beton K-175(betonpraktis) 1 day Wed 10/08/1Wed 10/08/16

    38 -Tulangan Pembesian dengan Besi polos Atau BJTD24 1 day Wed 10/08/1Wed 10/08/16

    39 -Bekisting 1 day Wed 10/08/1Wed 10/08/16

    40 Pek.Dinding & Finishing 7 days Thu 11/08/1 Wed 17/08/16

    41 Pek.Pasangan Bata (Dinding Pagar) 4 days Thu 11/08/16Sun 14/08/16

    17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18

      May '16 Jun '16 Jul '16 Aug '16 Sep '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 1

    Project: network planning

    Date: Fri 03/06/16

    Pembangunan Talud Dan Sarana Luar Pengadilan Agama Depok

  • 8/15/2019 Gantt Chart PA DEPOK

    2/3

    ID Task

    Mode

    Task Name Duration Start Finish

    42 Pek.Plester dan Acian(Dinding&Kolo m) 3 days Thu 1 1/0 8/1 6Sat 1 3/0 8/1 6

    43 Pek.Profilan Kolom 4 days Sun 14/08/16Wed 17/08/16

    44 Pek.Pasang dinding Keramik40X40 1 day Sun 14/08/16Sun 14/08/16

    45 Pek.Pengecatan Dinding 2 days Sun 14/08/16Mon 15/08/16

    46 Pek.Pemasangan Kembali Pintu Gerbang (Diperbaiki

    Sesuai Dgn Gambar) lengkap

    2 days Thu

    11/08/16

    Fri 12/08/16

    47 Pek Pemasangan Kembali PagarDepan (Pagar Besi

    Exsisting Di Cat Ulang)

    2 days Sun

    14/08/16

    Mon 15/08/16

    48 PEKERJAAN PEMBUATAN POS JAGA 19 days Tue 26/07/1 Sat 13/08/16

    49 Pek.Pasang Papan Bouwplang 1 day Tue 26/07/16Tue 26/07/16

    50 Galian tanah pondasib atukali 1 day Tue 26/07/16Tue 26/07/16

    51 Uruganpasirurugt=10cm 1 day Tue 26/07/16Tue 26/07/16

    52 Pekerjaan aanst amping batu koso ngt=15cm 1 day Tue 2 6/0 7/1 6Tue 2 6/0 7/1 6

    53 Pek.Pondasi Batukali camp.1Pc:4Psr 1 day Tue 26/07/16Tue 26/07/16

    54 Urugan tanah Tanah Kembali Untuk Peningan 1 day Wed 27 /07 /1 Wed 27 /07 /16

    55 Pek.Sloof 15/20 1 day Tue 26/07/1 Tue 26/07/16

    56 -Cor Beton K-175(betonpraktis) 1 day Tue 26/07/16Tue 26/07/16

    57 -Tulangan Pembesian dengan Besipolos Atau BJTD24 1 day Tue 26/07/16Tue 26/07/16

    58 -Bekisting 1 day Tue 26/07/16Tue 26/07/16

    59 Beton Kolom15/15 1 day Wed 27/07/1Wed 27/07/16

    60 -Cor BetonK-175(betonpraktis) 1 day Wed 27/07/1Wed 27/07/16

    61 -Tulangan Pembesian dengan Besipolos Atau BJTD24 1 day Wed 27/07/1Wed 27/07/16

    62 -Bekisting 1 day Wed 27/07/1Wed 27/07/16

    63 BetonBalokDak15/20 2 days Sat 30/07/16Sun 31/07/1664 -CorBetonK-175(betonpraktis) 1 day Sun 31/07/16Sun 31/07/16

    65 -Tulangan Pembesian dengan Besipolos Atau BJTD24 1 day Sat 30/07/16Sat 30/07/16

    66 -Bekisting 1 day Sat 30/07/16 Sat 30/07/16

    67 BetonPlatDakAtapt=10cm. 2 days Sat 30/07/16Sun 31/07/16

    68 -Cor Beton K-175(betonpraktis) 1 day? Sun 31/07/16Sun 31/07/16

    69 -Tulangan Pembesian dengan BesipolosAtauBJTD24 1 day? Sat 30/07/16Sat 30/07/16

    70 -Bekisting 1 day? Sat 30/07/16 Sat 30/07/16

    71 Pekerjaan Pasangan Dinding Bata1:5 3 days Wed 27/07/1Fri 29/07/16

    72 Pekerjaan plester dan acian dinding1:5 3 days Sat 30/07/16 Mon 01/08/16

    73 Pekerjaan Ban-banan 2 days Sat 30/07/16 Sun 31/07/16

    74 Pek.Finishing Sudut Ovening Sudut Pintu Dan Jendela 3 days Tue 02/08/16Thu 04/08/16

    75 Pek. Plester dan Acian Plat Dak Beton 3 days Sat 06/08/16 Mon 08/08/16

    76 Pasang Kusen dan Daun Pintu+ Accessories Type P1 1 day Tue 09/08/16Tue 09/08/1677 Pasang Kusen dan Daun Jendela+ AccessoriesType J1 1 day Tue 09/08/16Tue 09/08/16

    78 Urugan pasir bawah lantait=10cm 1 day Tue 09/08/16Tue 09/08/16

    79 Lantai kerjat=5cm 1 day Tue 09/08/16Tue 09/08/16

    80 Pekerjaan lantai keramik 40/40 1 day Tue 09/08/16Tue 09/08/16

    81 Pekerjaan pengecatan dinding( Exterior) 1 day Wed 10/08/1 Wed 10/08/16

    17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18

      May '16 Jun '16 Jul '16 Aug '16 Sep '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 2

    Project: network planning

    Date: Fri 03/06/16

  • 8/15/2019 Gantt Chart PA DEPOK

    3/3

    ID Task

    Mode

    Task Name Duration Start Finish

    82 Pekerjaan pengecatan dinding (Interior) 1 day Wed 10/08/1 Wed 10/08/16

    83 Pekerjaan pengecatan plafo nd Bet on Expose 1 day Wed 10 /08 /1 Wed 10 /08 /16

    84 Pekerjaan Waterproofing Dak atap 1 day Sat 13/08/16 Sat 13/08/16

    85 Pe ke rj aan Scr ed P enut up W at erprooi ng +Ram 1 day? Fri 12/08/16 Fri 12/08/16

    86 Pekerjaan Mekanikal dan Elektrikal 2 days Sat 30/07/16 Sun 31/07/16

    87 Lampu SL14W 1 day Sun 31/07/16Sun 31/07/16

    88 Saklar Seri 1 day? Sat 30/07/16 Sat 30/07/16

    89 Stop kontak 1 day? Sun 31/07/16Sun 31/07/16

    90 Instalasi titik Lampu Penerangan 1 day? Sat 30/07/16 Sat 30/07/16

    91 Instalasi st opkontak 1 fasa, 250 VA,22 0V 1 day? Sat 3 0/0 7/1 6 Sat 3 0/0 7/1 692 Kabel Penyambungan Daya 1 day? Sun 31/07/16Sun 31/07/16

    93 PEKERJAAN TAMAN 1 day Thu 01/09/1 Thu 01/09/16

    94 Tanam Dan Lenskep 1 day Thu 01/09/1 Thu 01/09/16

    95 Tanah Subur (Humus)

    96 Rumput

    97 Bunga Dan Pohon

    98 Kolam

    99 PEKERJAAN ELEKTRIKAL (PJU) 11 days Wed 31/08/1Sat 10/09/16

    100 Lampu PJU 3 days Wed 31/08/1Fri 02/09/16

    101 Termasuk didalamnya pekerjaan pemasangan Tiang

    listrik, lampuPJU,

    102 dan cor beton untuk dudukan tiang+ Baseplate

    103 Instalasi penerangan Lampu Luar 2 days Wed 31/08/1Thu 01/09/16

    104 Saklar Seri 1 day? Wed 31/08/1Wed 31/08/16

    105 Instalasi stopkontak 1fasa, 250VA, 220V 1 day? Wed 31/08/1 Wed 31/08/16

    106 Kabel Penyambungan Daya 1 day? Sat 03/09/16 Sat 03/09/16

    107 FINISH 1 day Sat 1 7/0 9/1 6 Sat 1 7/0 9/1 6

    17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18

      May '16 Jun '16 Jul '16 Aug '16 Sep '16

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    Page 3

    Project: network planning

    Date: Fri 03/06/16