Copy of Perhitungan Tebal Perkerasan Wahyu

21
1. Data LHR a. Mobil penumpang = 2002 kend/hari b. Mobil Pick up (6 ton) = 46 kend/hari c. Bus sedang (6 t0n) = 44 kend/hari d. Bus besar (9ton) = 57 kend/hari e. Truck sedang (13 ton) = 74 kend/hari f. Truck 2 As (18 ton) = 96 kend/hari g. Truck 3 As (25 ton) = 119 kend/hari h. Trailler (40 ton) = 58 kend/hari 2496 494 Tekanan angin ban rata-rata (Ta) = 5.65 Pertumbuhan lalu lintas selama masa konstruksi = 7 % Pertumbuhan lalu lintas selama masa layan (mulai 2013) = 5 % Data CBR No Nilai CBR 1 5.6 2 2 3 2.4 4 4 5 4.7 6 7.6 7 8.2 8 4.9 9 3.8 10 2.9 11 4.5 12 6.9 13 4.7 14 4.3

description

mama saya

Transcript of Copy of Perhitungan Tebal Perkerasan Wahyu

Page 1: Copy of Perhitungan Tebal Perkerasan Wahyu

1. Data LHRa. Mobil penumpang = 2002 kend/harib. Mobil Pick up (6 ton) = 46 kend/haric. Bus sedang (6 t0n) = 44 kend/harid. Bus besar (9ton) = 57 kend/harie. Truck sedang (13 ton) = 74 kend/harif. Truck 2 As (18 ton) = 96 kend/harig. Truck 3 As (25 ton) = 119 kend/harih. Trailler (40 ton) = 58 kend/hari

2496 494Tekanan angin ban rata-rata (Ta) = 5.65

Pertumbuhan lalu lintas selama masa konstruksi = 7 %Pertumbuhan lalu lintas selama masa layan (mulai 2013) = 5 %

Data CBRNo Nilai CBR1 5.62 23 2.44 45 4.76 7.67 8.28 4.99 3.8

10 2.911 4.512 6.913 4.714 4.3

Page 2: Copy of Perhitungan Tebal Perkerasan Wahyu

15 7.716 8.517 3.918 4.819 5.520 3.521 422 3.223 4.524 7.5

Jenis Tanah = Butir KasarNilai PI tanah = 14 %

Curah hujan = 693 mm/tahunKondisi air tanah = Dalam

Pengolahan LHRdianggap kondisi medan datar, sehingga :

kendaraan koef SMPa. Mobil penumpang = 2018 kend/hari 1 2018 SMP/hari VLHR = 5917.774b. Mobil Pick up (6 ton) = 109 kend/hari 2 218 SMP/hari = 5918c. Bus sedang (6 t0n) = 50 kend/hari 2 100 SMP/harid. Bus besar (9ton) = 52 kend/hari 2.5 130 SMP/harie. Truck sedang (13 ton) = 77 kend/hari 2 154 SMP/harif. Truck 2 As (18 ton) = 92 kend/hari 3 276 SMP/harig. Truck 3 As (25 ton) = 113 kend/hari 4 452 SMP/harih. Trailler (40 ton) = 57 kend/hari 5 285 SMP/hari

Total SMP = 3633 SMP/hari

dengan SMP = 5918 SMP/hari maka lebar jalur = 7 mdengan Lebar jalur = 7 m

Page 3: Copy of Perhitungan Tebal Perkerasan Wahyu

maka faktor distribusi :kendaraan berat = 0.5kendaraan ringan = 0.5

Menghitung ESAL

Kendaraan berat beban sumbu(ton) depan 1 depan 2 belakang 1

a. Mobil penumpang 4 2 2 50 50b. Mobil Pick up 6 2.04 3.96 34 66c. Bus sedang 6 2.04 3.96 25 75d. Bus besar 9 3.06 5.94 12.5 37.5 50e. Truck sedang 13 4.42 8.58f. Truck 2 As 18 6.12 11.88g. Truck 3 As 25 6.25 18.75h. Trailler 40 5 15 20

k tunggal = 1 k tandem = 0.086 k triple = 0.031

Kendaraan berat ESAL Sumbu ESAL(ton) depan 1 depan 2 belakang 1 Kendaraan

a. Mobil penumpang 4 0.00360877 0.00360877 0.007218 14.450b. Mobil Pick up 6 0.00390625 0.05546514 0.0594 2.731c. Bus sedang 6 0.00390625 0.05546514 0.0594 2.612d. Bus besar 9 0.01977539 0.28079227 0.3006 17.132e. Truck sedang 13 0.08608519 1.22233013 1.3084 96.823f. Truck 2 As 18 0.31640625 4.49267629 4.8091 461.672g. Truck 3 As 25 0.34415924 2.39741327 2.7416 326.247h. Trailler 40 0.14096762 0.9819804745 1.11871907 2.2417 130.017 1051.684

Menghitung LEPmassa konstruksi 2013 - 2010 = 3 tahun

Page 4: Copy of Perhitungan Tebal Perkerasan Wahyu

pertumbuhan kendaraan massa konstruksi (i) = 7 %

Kendaraan LHR ESAL C Faktor Pertumbuhan LEPa. Mobil penumpang 2018 0.007218 0.5 1.225 8.921b. Mobil Pick up 109 0.0594 0.5 1.225 3.964c. Bus sedang 50 0.0594 0.5 1.225 1.818d. Bus besar 52 0.3006 0.5 1.225 9.573e. Truck sedang 77 1.3084 0.5 1.225 61.710f. Truck 2 As 92 4.8091 0.5 1.225 271.001g. Truck 3 As 113 2.7416 0.5 1.225 189.758h. Trailler 57 2.2417 0.5 1.225 78.265

TOTAL LEP = 625.011

Menghitung LEAumur rencana = 10 tahunpertumbuhan selama masa layan = 5 %

(1+r)^n = 1.629LEA = LEP x (1+r)^10LEA = 1018.078

Menghitung LETLET = 0.5*(LEP+LEA)LET = 821.5445

Menghitung LERLER = LET*FPLER = 821.5445

Perhitungan CBR secara grafisSegmen 1 segmen 1

1 5.6 R 2.83 CBR jumlah > CBR %

Page 5: Copy of Perhitungan Tebal Perkerasan Wahyu

2 2 CBR rata-rata 4.929 2 7 1003 2.4 CBR max 8.2 3 5 71.434 4 CBR min 2 4 5 71.435 4.7 CBR segmen 2.738 5 3 42.866 7.6 6 2 28.577 8.2 7 2 28.57

8 1 14.29Segmen 2

1 4.9 R 3.18 Segmen 22 3.8 CBR rata-rata 5.356 CBR jumlah > CBR %3 2.9 CBR max 8.5 2 9 1004 4.5 CBR min 2.9 3 8 88.895 6.9 CBR segmen 3.595 4 7 77.786 4.7 5 3 33.337 4.3 6 3 33.338 7.7 7 2 22.229 8.5 8 1 11.11

Segmen 31 3.9 R 2.96 Segmen 32 4.8 CBR rata-rata 4.613 CBR jumlah > CBR %3 5.5 CBR max 7.5 3 8 1004 3.5 CBR min 3.2 4 5 62.505 4 CBR segmen 3.160 5 2 25.006 3.2 6 1 12.507 4.5 7 1 12.508 7.5

Mencari nilai hekP 8160 faktor drainase 1.3Ta 5.65 faktor ling. & curah hujan 2.5π 3.14

Page 6: Copy of Perhitungan Tebal Perkerasan Wahyu

pengulangan bebann1 2998637.36n2 4487645.48 maka digunakan n2 (terbesar)

jari-jari bidang kontak = 15.16

segmen 1a1 (aspal beton kelas A) = 2 d1 = 5a2 (base course CBR) = 1 d2 = 15a3(base course CBR) = 0.75CBR = 2.738itung sendiri = 49080.21h ek = 44.57d3 = 26.0937531 27

segmen 2a1 (aspal beton kelas A) = 2 d1 = 5a2 (base course CBR) = 1 d2 = 15a3(base course CBR) = 0.75CBR = 3.595itung sendiri = 49080.21h ek = 36.97d3 = 15.956 16

segmen 3a1 (aspal beton kelas A) = 2 d1 = 5a2 (base course CBR) = 1 d2 = 15a3(base course CBR) = 0.75CBR = 3.160itung sendiri = 49080.21h ek = 40.44d3 = 20.584 21

Page 7: Copy of Perhitungan Tebal Perkerasan Wahyu

Perhitungan Bina Marga Konstruksi Langsung

Perhitungan DDTsegmen 1CBR = 2.97 log CBR = 0.472756DDT = 3.732853

segmen 2CBR = 3.19 log CBR = 0.503791DDT = 3.866

segmen 3CBR = 3.1 log CBR = 0.491362DDT = 3.813

Faktor RegionalTotal LHR = 2592 kend/haritotal kend berat = 534 kend/hari% kend berat = 20.60 %kemiringan medan = 1.037 %FR = 0.5IPt = 2.5IPo = ≥4menggunakan nomogram no 1

ITP dengan trial n errorsegmen 1 ITP = 12.210CBR = 2.97 ruas kiri = ruas kananDDT = 3.733 6.352 = ruas 1 6.880FR = 0.5 = ruas 2 -0.255 0.519 -0.492IPt = 2.5 = ruas 3 0.301 0.272IPo = 4 = total 6.359LER = 616.852UR = 10

segmen 2 ITP = 11.97CBR = 3.19 ruas kiri = ruas kananDDT = 3.866 6.35247 = s1 6.81421FR = 0.5 = s2 -0.25527 0.52914 -0.48243IPt = 2.5 = s3 0.30103 0.32140IPo = 4 = total 6.35214LER = 616.852UR = 10

Page 8: Copy of Perhitungan Tebal Perkerasan Wahyu

segemn 3 ITP = 12.065CBR = 3.1 ruas kiri = ruas kananDDT = 3.813 6.3525 = s1 6.8406FR = 0.5 = s2 -0.2553 0.5248 -0.4864IPt = 2.5 = s3 0.3010 0.3016IPo = 4 = total 6.3547LER = 616.852UR = 10

Tebal perkerasan lapisanberdasarkan tabel 3.11a1 = 0.4 (laston)a2 = 0.14 (batu pecah kela s A)a3 = 0.13 (sirtu kelas A)

segmen 1berdasarkan nilai ITP, sesuai dengan tabel 3.16 dan 3.17d1 = 10 (laston)d2 = 25 (batu pecah kelas A)ITP = 13.344

d3 = 44.95385 = 45 cm

segmen 2ITP = 12.956

d3 = 41.96923 = 40 cm

segmen 3ITP = 12.9900

d3 = 42.23077 = 40 cm

Page 9: Copy of Perhitungan Tebal Perkerasan Wahyu
Page 10: Copy of Perhitungan Tebal Perkerasan Wahyu

Perhitungan Bina Marga Konstruksi Bertahap

LEPtotal = 624.770

Tahap 1 (selama 5 tahun)UR = 4 tahunr = 3 %

LEA = 703.184

LET = 663.977

LER = 265.591

akhir tahap 1, struktur perkerasan dianggap masih memiliki sisa umur 40 %x = 1.67

LER = 443.537

Tahap 2 (selama 5 tahun)UR = 6 tahunr = 3 %

LEA = 839.639

LET = 771.412

LER = 462.847

nilai total yg diperlukan utk memikul beban lalin (2.5 LER2)y = 2.5

LER = 1157.118

Tebal perkerasansegmen 1CBR = 2.6DDT = 3.480FR = 0.5IPt = 2.5IPo = 4

tahap 1x.LER = 443.537ITP = 10.340ruas kiri = ruas kanan

5.811 = ruas 1 6.333018= ruas 2 -0.255273 0.639686 -0.399059

Page 11: Copy of Perhitungan Tebal Perkerasan Wahyu

= ruas 3 0.30103 0.17808= total 5.811

a1 = 0.4 (laston)a2 = 0.14 (batu pecah kelas A)a3 = 0.13 (sirtu kelas A)

d1 = 10d2 = 20

d3 = 27.231 = 34

tahap 2y.LER = 1157.1180ITP = 12.810ruas kiri = ruas kanan

6.404 = ruas 1 7.041508= ruas 2 -0.255273 0.496428 -0.514219= ruas 3 0.30103 0.17808= total 6.404

ITP2 = 2.47

d0 = 6.175 = 3

segmen 2CBR = 3.3DDT = 3.930FR = 0.5IPt = 2.5IPo = 4

tahap 1x.LER = 443.537ITP = 9.695ruas kiri = ruas kanan

5.811 = ruas 1 6.125417= ruas 2 -0.255273 0.712926 -0.358063= ruas 3 0.30103 0.34503= total 5.811

a1 = 0.4 (laston)a2 = 0.14 (batu pecah kelas A)a3 = 0.13 (sirtu kelas A)

d1 = 10d2 = 20

Page 12: Copy of Perhitungan Tebal Perkerasan Wahyu

d3 = 22.269 = 28

tahap 2y.LER = 1157.1180ITP = 12.090ruas kiri = ruas kanan

6.404 = ruas 1 6.847472= ruas 2 -0.255273 0.523734 -0.487409= ruas 3 0.30103 0.34503= total 6.404

ITP2 = 2.39

d0 = 5.9875 = 3

segmen 3CBR = 3.14DDT = 3.840FR = 0.5IPt = 2.5IPo = 4

tahap 1x.LER = 443.537ITP = 9.822ruas kiri = ruas kanan

5.811 = ruas 1 6.167125= ruas 2 -0.255273 0.696596 -0.366457= ruas 3 0.30103 0.31164= total 5.811

a1 = 0.4 (laston)a2 = 0.14 (batu pecah kelas A)a3 = 0.13 (sirtu kelas A)

d1 = 10d2 = 20

d3 = 23.2461538 = 30

tahap 2y.LER = 1157.1180ITP = 12.230ruas kiri = ruas kanan

6.404 = ruas 1 6.885939= ruas 2 -0.255273 0.517766 -0.493027

Page 13: Copy of Perhitungan Tebal Perkerasan Wahyu

= ruas 3 0.30103 0.31164= total 6.404

ITP2 = 2.408

d0 = 6.02 = 3

Page 14: Copy of Perhitungan Tebal Perkerasan Wahyu

menentukan W18W18 = Dd x Dl x w18

Dl = 90 (dari tabel hal 6)Dd = 0.5 (rentang 0.3-0.7)

Menentukan w 18 (pd tahun pertama)kendaraan LHR ESAL LHR*ESALa. Mobil penumpang 2018 0.007218 14.565b. Mobil Pick up 109 0.05937 6.471c. Bus sedang 50 0.05937 2.969d. Bus besar 52 0.30057 15.630e. Truck sedang 77 1.30842 100.748f. Truck 2 As 92 4.80908 442.436g. Truck 3 As 113 2.74157 309.798h. Trailler 57 2.24167 127.775

w18 1020.39

W18 = 45917.589 45917.595 (ITUNGAN KALKULATOR)g = 5 % 1.05 1.62889 0.62889n (UR) = 10 tahun

pada akhir umur rencana (tahun ke 10)Wt = W18 x ((1+g)^n-1)/gWt = 577546.5754