Contoh RAB Bongkar Rel Transfer

7
PEKERJAAN : PASANG REL TRANSFER CARRIAGE L O K A S I : MUARA TEWEH HARGA ( Rp ) 1 3 MESS KARYAWAN I PEKERJAAN PERSIAPAN 3.617.668,50 Rp II PEKERJAAN GALIAN DAN BOBOKAN 2.335.593,49 Rp III PEKERJAAN BETON 10.840.957,13 Rp 16.794.219,11 Rp 1.679.421,91 Rp 18.473.641,02 Rp 18.474.000,00 Rp Banjarbaru, 24 Nopember 2012 CV. Wahyu Abadi Yuli Winnarti, SE. Direktris TOTAL HARGA DIBULATKAN Terbilang : ## Delapan belas juta empat ratus tujuh puluh empat ribu rupiah ## REKAPITULASI NO URAIAN PEKERJAAN 2 JUMLAH PPn (10 %) Rekapitulasi Lembar 1

description

Berisikan Contoh Perhitungan dan Penawaran Pembongkaran Rel Transfer

Transcript of Contoh RAB Bongkar Rel Transfer

Page 1: Contoh RAB Bongkar Rel Transfer

PEKERJAAN : PASANG REL TRANSFER CARRIAGEL O K A S I : MUARA TEWEH

HARGA( Rp )

1 3

MESS KARYAWAN

I PEKERJAAN PERSIAPAN 3.617.668,50Rp

II PEKERJAAN GALIAN DAN BOBOKAN 2.335.593,49Rp

III PEKERJAAN BETON 10.840.957,13Rp

16.794.219,11Rp

1.679.421,91Rp

18.473.641,02Rp

18.474.000,00Rp

Banjarbaru, 24 Nopember 2012CV. Wahyu Abadi

Yuli Winnarti, SE.Direktris

TOTAL HARGA

DIBULATKAN

Terbilang : ## Delapan belas juta empat ratus tujuh puluh empat ribu rupiah ##

REKAPITULASI

NO URAIAN PEKERJAAN

2

JUMLAH

PPn (10 %)

RekapitulasiLembar 1

Page 2: Contoh RAB Bongkar Rel Transfer

PEKERJAAN : PASANG REL TRANSFER CARRIAGELOKASI : MUARA TEWEH

No. HARGA SATUAN (Rp)ANALISA BAHAN + UPAH

1 3 5 6

I1 Pembersihan lokasi awal dan akhir pekerjaan 1 31,50 M2 3.030,00 95.445,00 2 Pengukuran 2 67,00 M' 52.570,50 3.522.223,50

Sub Total 3.617.668,50

II1 Membongkar lantai beton 3 2,84 M3 760.489,50 2.155.987,73 2 Galian Tanah 4 2,84 M3 63.353,00 179.605,76

Sub Total 2.335.593,49

III1 Pengecoran Beton Dudukan Rel 5 5,67 M3 1.911.985,38 10.840.957,13

Sub Total 10.840.957,13

PEKERJAAN GALIAN DAN BOBOKAN

PEKERJAAN BETON

2 4

PEKERJAAN PERSIAPAN

RENCANA ANGGARAN BIAYA

No. URAIAN PEKERJAANVOLUME/

JUMLAH HARGA (Rp)SATUAN

Page 3: Contoh RAB Bongkar Rel Transfer

Harga SatuanRp.

1 1 M2 Pembersihan lapangan dan peralatan 3.030,00 2 1 M' Pengukuran dan pemasangan bouwplank 52.570,50 3 1 M3 Membongkar Beton 760.489,50 4 1 M3 Galian tanah 63.353,00 5 1 M3 Membuat beton mutu K - 350 1.911.985,38

No Analisa Pekerjaan

REKAP ANALISA

Page 4: Contoh RAB Bongkar Rel Transfer

1 1 M2 Pembersihan lapangan dan peralatan1. Tenaga

- Pekerja 0,0120 OH X 75.000,00 = 900,00 - Mandor 0,0200 OH X 106.500,00 = 2.130,00 +

Jumlah ( 1 ) = 3.030,00

2 1 M' Pengukuran dan pemasangan bouwplank1. Bahan

- Kayu 5/7 0,0120 M3 X 1.760.000,00 = 21.120,00 - Paku biasa 2" - 5" 0,0200 Kg X 48.400,00 = 968,00 - Papan lanan 3/20 0,0070 M3 X 1.760.000,00 = 12.320,00 +

Jumlah ( 1 ) = 34.408,00

2. Tenaga - Pekerja 0,1000 OH X 75.000,00 = 7.500,00 - Tukang kayu 0,1000 OH X 90.800,00 = 9.080,00 - Kepala Tukang 0,0100 OH X 105.000,00 = 1.050,00 - Mandor 0,0050 OH X 106.500,00 = 532,50 +

Jumlah ( 2 ) = 18.162,50 Jumlah ( 1+2 ) = 52.570,50

3 1 M3 Membongkar Beton1. Alat

- Alat Bantu 1,0000 Ls X 225.000,00 = 225.000,00 Jumlah ( 1 ) = 225.000,00

2. Tenaga - pekerja 6,6670 OH X 75.000,00 = 500.025,00 - Mandor 0,3330 OH X 106.500,00 = 35.464,50 +

Jumlah ( 2 ) = 535.489,50 Jumlah ( 1+2 ) = 760.489,50

4 1 M3 Galian tanah1. Tenaga

- pekerja OH X 75.000,00 = - - Tukang gali 0,6250 OH X 90.800,00 = 56.750,00 - Kepala Tukang OH X 105.000,00 = - - Mandor 0,0620 OH X 106.500,00 = 6.603,00 +

Jumlah ( 1 ) = 63.353,00

5 1 M3 Membuat beton mutu K - 3501. Bahan

- Semen Portland 448,0000 Kg X 2.800,00 = 1.254.400,00 - Pasir cor 0,4941 m3 X 280.000,00 = 138.340,74 - Koral 0,7143 m3 X 396.000,00 = 282.857,14 - Air 215,0000 Liter X 150,00 = 32.250,00

Jumlah ( 1 ) = 1.707.847,88

2. Tenaga - pekerja 2,1000 OH X 75.000,00 = 157.500,00 - Tukang Batu 0,3500 OH X 90.800,00 = 31.780,00 - Kepala Tukang 0,0350 OH X 105.000,00 = 3.675,00 - Mandor 0,1050 OH X 106.500,00 = 11.182,50 +

Jumlah ( 2 ) = 204.137,50 Jumlah ( 1+2 ) = 1.911.985,38

DAFTAR ANALISA PEKERJAAN

Page 5: Contoh RAB Bongkar Rel Transfer

PEKERJAAN :PASANG REL TRANSFER CARRIAGELOKASI :MUARA TEWEH

NO JENIS MATERIAL HARGA SATUAN

1 Semen Portland 2.800,00 Kg2 Pasir pasang 280.000,00 m33 Kerikil 396.000,00 m34 Kayu 5/7 1.760.000,00 M35 Paku biasa 2" - 5" 48.400,00 Kg6 Papan lanan 3/20 1.760.000,00 M3

- -

DAFTAR HARGA SATUAN BAHAN/MATERIAL

Page 6: Contoh RAB Bongkar Rel Transfer

PEKERJAAN :PASANG REL TRANSFER CARRIAGELOKASI :MUARA TEWEH

NO JENIS PEKERJAAN HARGA SATUAN

1 Pekerja 75.000,00 OH2 Tukang Kayu 90.800,00 OH3 Tukang Cat 90.800,00 OH4 Tukang Besi 90.800,00 OH5 Tukang Batu 90.800,00 OH6 Kepala Tukang 105.000,00 OH7 Mandor 106.500,00 OH

DAFTAR HARGA SATUAN UPAH

#REF!#REF!#REF!

#REF!#REF!

Page 7: Contoh RAB Bongkar Rel Transfer

Cara pembayaran yang kami usulkan adalah dengan sistem termin dengan pelaksanaan sebagai berikut :

1. Uang Muka sebesar 30% (tiga puluh persen) dari Nilai KontrakUang Muka dibayarkan paling lambat 7 hari setelah ditandatanganinya kontrak

2. Termin I : Progres Fisik mencapai 35% (tiga puluh lima persen)Termin I dibayarkan sebesar 35% (tiga puluh lima persen) dikurangi dengan angsuran pengembalianUang Muka sebesar 10% (sepuluh persen). Jadi yang dibayarkan Owner kepada Penyedia Jasa sebesar 25% (dua puluh lima persen)Termin dibayarkan paling lambat 7 hari setelah Surat Permintaan Pembayaran Termin I diterima oleh Owner

3. Termin II : Progres Fisik mencapai 70% (tujuh puluh persen)Termin II dibayarkan sebesar 70% (tujuh puluh persen) dikurangi dengan progres fisik sd. Termin I sebesar 35% (tiga puluh lima persen) dan dikurangi dengan angsuran pengembalian Uang Muka sebesar 10% (sepuluh persen). Jadi yang dibayarkan Owner kepada Penyedia Jasa sebesar 25% (dua puluh lima persen)Termin dibayarkan paling lambat 7 hari setelah Surat Permintaan Pembayaran Termin II diterima oleh Owner

4. Termin III : Progres Fisik mencapai 100% (seratus persen)Termin III dibayarkan sebesar 100% (seratus persen) dikurangi dengan progres sd. fisik Termin II sebesar 70% (tujuh puluh persen) dan dikurangi dengan angsuran pengembalian Uang Muka sebesar 10% (sepuluh persen) serta Jaminan pemeliharaan sebesar 5% (lima persen). Jadi yang dibayarkan Ownerkepada Penyedia Jasa sebesar 25% (dua puluh lima persen)Termin dibayarkan paling lambat 7 hari setelah Surat Permintaan Pembayaran Termin II diterima oleh Owner

5. Retensi sebesar 5% (lima persen)Retensi dibayarkan setelah masa pemeliharaan selesai.

Banjarbaru, 24 Nopember 2012CV. Wahyu Abadi

Yuli Winnarti, SE.Direktris

CARA PEMBAYARAN

RekapitulasiLembar 1