PEKERJAAN : PASANG REL TRANSFER CARRIAGEL O K A S I : MUARA TEWEH
HARGA( Rp )
1 3
MESS KARYAWAN
I PEKERJAAN PERSIAPAN 3.617.668,50Rp
II PEKERJAAN GALIAN DAN BOBOKAN 2.335.593,49Rp
III PEKERJAAN BETON 10.840.957,13Rp
16.794.219,11Rp
1.679.421,91Rp
18.473.641,02Rp
18.474.000,00Rp
Banjarbaru, 24 Nopember 2012CV. Wahyu Abadi
Yuli Winnarti, SE.Direktris
TOTAL HARGA
DIBULATKAN
Terbilang : ## Delapan belas juta empat ratus tujuh puluh empat ribu rupiah ##
REKAPITULASI
NO URAIAN PEKERJAAN
2
JUMLAH
PPn (10 %)
RekapitulasiLembar 1
PEKERJAAN : PASANG REL TRANSFER CARRIAGELOKASI : MUARA TEWEH
No. HARGA SATUAN (Rp)ANALISA BAHAN + UPAH
1 3 5 6
I1 Pembersihan lokasi awal dan akhir pekerjaan 1 31,50 M2 3.030,00 95.445,00 2 Pengukuran 2 67,00 M' 52.570,50 3.522.223,50
Sub Total 3.617.668,50
II1 Membongkar lantai beton 3 2,84 M3 760.489,50 2.155.987,73 2 Galian Tanah 4 2,84 M3 63.353,00 179.605,76
Sub Total 2.335.593,49
III1 Pengecoran Beton Dudukan Rel 5 5,67 M3 1.911.985,38 10.840.957,13
Sub Total 10.840.957,13
PEKERJAAN GALIAN DAN BOBOKAN
PEKERJAAN BETON
2 4
PEKERJAAN PERSIAPAN
RENCANA ANGGARAN BIAYA
No. URAIAN PEKERJAANVOLUME/
JUMLAH HARGA (Rp)SATUAN
Harga SatuanRp.
1 1 M2 Pembersihan lapangan dan peralatan 3.030,00 2 1 M' Pengukuran dan pemasangan bouwplank 52.570,50 3 1 M3 Membongkar Beton 760.489,50 4 1 M3 Galian tanah 63.353,00 5 1 M3 Membuat beton mutu K - 350 1.911.985,38
No Analisa Pekerjaan
REKAP ANALISA
1 1 M2 Pembersihan lapangan dan peralatan1. Tenaga
- Pekerja 0,0120 OH X 75.000,00 = 900,00 - Mandor 0,0200 OH X 106.500,00 = 2.130,00 +
Jumlah ( 1 ) = 3.030,00
2 1 M' Pengukuran dan pemasangan bouwplank1. Bahan
- Kayu 5/7 0,0120 M3 X 1.760.000,00 = 21.120,00 - Paku biasa 2" - 5" 0,0200 Kg X 48.400,00 = 968,00 - Papan lanan 3/20 0,0070 M3 X 1.760.000,00 = 12.320,00 +
Jumlah ( 1 ) = 34.408,00
2. Tenaga - Pekerja 0,1000 OH X 75.000,00 = 7.500,00 - Tukang kayu 0,1000 OH X 90.800,00 = 9.080,00 - Kepala Tukang 0,0100 OH X 105.000,00 = 1.050,00 - Mandor 0,0050 OH X 106.500,00 = 532,50 +
Jumlah ( 2 ) = 18.162,50 Jumlah ( 1+2 ) = 52.570,50
3 1 M3 Membongkar Beton1. Alat
- Alat Bantu 1,0000 Ls X 225.000,00 = 225.000,00 Jumlah ( 1 ) = 225.000,00
2. Tenaga - pekerja 6,6670 OH X 75.000,00 = 500.025,00 - Mandor 0,3330 OH X 106.500,00 = 35.464,50 +
Jumlah ( 2 ) = 535.489,50 Jumlah ( 1+2 ) = 760.489,50
4 1 M3 Galian tanah1. Tenaga
- pekerja OH X 75.000,00 = - - Tukang gali 0,6250 OH X 90.800,00 = 56.750,00 - Kepala Tukang OH X 105.000,00 = - - Mandor 0,0620 OH X 106.500,00 = 6.603,00 +
Jumlah ( 1 ) = 63.353,00
5 1 M3 Membuat beton mutu K - 3501. Bahan
- Semen Portland 448,0000 Kg X 2.800,00 = 1.254.400,00 - Pasir cor 0,4941 m3 X 280.000,00 = 138.340,74 - Koral 0,7143 m3 X 396.000,00 = 282.857,14 - Air 215,0000 Liter X 150,00 = 32.250,00
Jumlah ( 1 ) = 1.707.847,88
2. Tenaga - pekerja 2,1000 OH X 75.000,00 = 157.500,00 - Tukang Batu 0,3500 OH X 90.800,00 = 31.780,00 - Kepala Tukang 0,0350 OH X 105.000,00 = 3.675,00 - Mandor 0,1050 OH X 106.500,00 = 11.182,50 +
Jumlah ( 2 ) = 204.137,50 Jumlah ( 1+2 ) = 1.911.985,38
DAFTAR ANALISA PEKERJAAN
PEKERJAAN :PASANG REL TRANSFER CARRIAGELOKASI :MUARA TEWEH
NO JENIS MATERIAL HARGA SATUAN
1 Semen Portland 2.800,00 Kg2 Pasir pasang 280.000,00 m33 Kerikil 396.000,00 m34 Kayu 5/7 1.760.000,00 M35 Paku biasa 2" - 5" 48.400,00 Kg6 Papan lanan 3/20 1.760.000,00 M3
- -
DAFTAR HARGA SATUAN BAHAN/MATERIAL
PEKERJAAN :PASANG REL TRANSFER CARRIAGELOKASI :MUARA TEWEH
NO JENIS PEKERJAAN HARGA SATUAN
1 Pekerja 75.000,00 OH2 Tukang Kayu 90.800,00 OH3 Tukang Cat 90.800,00 OH4 Tukang Besi 90.800,00 OH5 Tukang Batu 90.800,00 OH6 Kepala Tukang 105.000,00 OH7 Mandor 106.500,00 OH
DAFTAR HARGA SATUAN UPAH
#REF!#REF!#REF!
#REF!#REF!
Cara pembayaran yang kami usulkan adalah dengan sistem termin dengan pelaksanaan sebagai berikut :
1. Uang Muka sebesar 30% (tiga puluh persen) dari Nilai KontrakUang Muka dibayarkan paling lambat 7 hari setelah ditandatanganinya kontrak
2. Termin I : Progres Fisik mencapai 35% (tiga puluh lima persen)Termin I dibayarkan sebesar 35% (tiga puluh lima persen) dikurangi dengan angsuran pengembalianUang Muka sebesar 10% (sepuluh persen). Jadi yang dibayarkan Owner kepada Penyedia Jasa sebesar 25% (dua puluh lima persen)Termin dibayarkan paling lambat 7 hari setelah Surat Permintaan Pembayaran Termin I diterima oleh Owner
3. Termin II : Progres Fisik mencapai 70% (tujuh puluh persen)Termin II dibayarkan sebesar 70% (tujuh puluh persen) dikurangi dengan progres fisik sd. Termin I sebesar 35% (tiga puluh lima persen) dan dikurangi dengan angsuran pengembalian Uang Muka sebesar 10% (sepuluh persen). Jadi yang dibayarkan Owner kepada Penyedia Jasa sebesar 25% (dua puluh lima persen)Termin dibayarkan paling lambat 7 hari setelah Surat Permintaan Pembayaran Termin II diterima oleh Owner
4. Termin III : Progres Fisik mencapai 100% (seratus persen)Termin III dibayarkan sebesar 100% (seratus persen) dikurangi dengan progres sd. fisik Termin II sebesar 70% (tujuh puluh persen) dan dikurangi dengan angsuran pengembalian Uang Muka sebesar 10% (sepuluh persen) serta Jaminan pemeliharaan sebesar 5% (lima persen). Jadi yang dibayarkan Ownerkepada Penyedia Jasa sebesar 25% (dua puluh lima persen)Termin dibayarkan paling lambat 7 hari setelah Surat Permintaan Pembayaran Termin II diterima oleh Owner
5. Retensi sebesar 5% (lima persen)Retensi dibayarkan setelah masa pemeliharaan selesai.
Banjarbaru, 24 Nopember 2012CV. Wahyu Abadi
Yuli Winnarti, SE.Direktris
CARA PEMBAYARAN
RekapitulasiLembar 1