Transcript of An. Pek Kunci Dan Kaca Kota Ternate
-
1 1 buah pasang kunci tanam 2 Slag Kualitas Baik
a. Bahan
- kunci tanam 2 Slag 1.000 Bh x Rp. 250,000.00 = Rp. 250,000.00
JUMLAH = Rp. 250,000.00
b. Tenaga
- Pekerja 0.060 Oh x Rp. 43,120.00 = Rp. 2,587.20
- Tukang Kayu 0.600 Oh x Rp. 57,840.00 = Rp. 34,704.00
- Kepala Tukang 0.060 Oh x Rp. 61,600.00 = Rp. 3,696.00
- Mandor 0.003 Oh x Rp. 64,400.00 = Rp. 193.20
JUMLAH = Rp. 41,180.40
JUMLAH (a) + (b) = Rp. 291,180.40
2 1 buah pasang kunci tanam 1 Slag Kualitas Baik
a. Bahan
- kunci tanam 1 Slag Kw Baik 1.000 Bh x Rp. 175,000.00 = Rp. 175,000.00
JUMLAH = Rp. 175,000.00
b. Tenaga
- Pekerja 0.060 Oh x Rp. 43,120.00 = Rp. 2,587.20
- Tukang Kayu 0.600 Oh x Rp. 57,840.00 = Rp. 34,704.00
- Kepala Tukang 0.060 Oh x Rp. 61,600.00 = Rp. 3,696.00
- Mandor 0.003 Oh x Rp. 64,400.00 = Rp. 193.20
JUMLAH = Rp. 41,180.40
JUMLAH (a) + (b) = Rp. 216,180.40
3 1 buah pasang kunci tanam 1 Slag kamar mandi Kualitas Baik
a. Bahan
- kunci tanam KM Kw. Baik 1.000 Bh x Rp. 175,000.00 = Rp. 175,000.00
JUMLAH = Rp. 175,000.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 204,604.60
4 1 buah pasang engsel pintu Kualitas Baik
a. Bahan
- Engsel pintu 1.000 Bh x Rp. 96,800.00 = Rp. 96,800.00
JUMLAH = Rp. 96,800.00
b. Tenaga
- Pekerja 0.015 Oh x Rp. 43,120.00 = Rp. 646.80
- Tukang Kayu 0.150 Oh x Rp. 57,840.00 = Rp. 8,676.00
- Kepala Tukang 0.015 Oh x Rp. 61,600.00 = Rp. 924.00
- Mandor 0.00075 Oh x Rp. 64,400.00 = Rp. 48.30
JUMLAH = Rp. 10,295.10
JUMLAH (a) + (b) = Rp. 107,095.10
PEKERJAAN KUNCI DAN KACA
-
PEKERJAAN KUNCI DAN KACA
5 1 buah pasang engsel jendela Kualitas Baik
a. Bahan
- Engsel jendela 1.000 Bh x Rp. 47,800.00 = Rp. 47,800.00
JUMLAH = Rp. 47,800.00
b. Tenaga
- Pekerja 0.010 Oh x Rp. 43,120.00 = Rp. 431.20
- Tukang Kayu 0.100 Oh x Rp. 57,840.00 = Rp. 5,784.00
- Kepala Tukang 0.010 Oh x Rp. 61,600.00 = Rp. 616.00
- Mandor 0.0005 Oh x Rp. 64,400.00 = Rp. 32.20
JUMLAH = Rp. 6,863.40
JUMLAH (a) + (b) = Rp. 54,663.40
6 1 buah pasang Kait angin Kualitas Baik
a. Bahan
- Engsel angin 1.000 Bh x Rp. 36,500.00 = Rp. 36,500.00
JUMLAH = Rp. 36,500.00
b. Tenaga
- Pekerja 0.020 Oh x Rp. 43,120.00 = Rp. 862.40
- Tukang Kayu 0.200 Oh x Rp. 57,840.00 = Rp. 11,568.00
- Kepala Tukang 0.020 Oh x Rp. 61,600.00 = Rp. 1,232.00
- Mandor 0.001 Oh x Rp. 64,400.00 = Rp. 64.40
JUMLAH = Rp. 13,726.80
JUMLAH (a) + (b) = Rp. 50,226.80
7 1 buah pasang kait angin Kualitas Baik
a. Bahan
- Kait angin 1.000 Bh x Rp. 36,500.00 = Rp. 36,500.00
JUMLAH = Rp. 36,500.00
b. Tenaga
- Pekerja 0.015 Oh x Rp. 43,120.00 = Rp. 646.80
- Tukang Kayu 0.150 Oh x Rp. 57,840.00 = Rp. 8,676.00
- Kepala Tukang 0.015 Oh x Rp. 61,600.00 = Rp. 924.00
- Mandor 0.00075 Oh x Rp. 64,400.00 = Rp. 48.30
JUMLAH = Rp. 10,295.10
JUMLAH (a) + (b) = Rp. 46,795.10
-
PEKERJAAN KUNCI DAN KACA
8 1 buah pasang kunci selot Kualitas Baik
a. Bahan
- Kunci selot 1.000 Bh x Rp. 29,600.00 = Rp. 29,600.00
JUMLAH = Rp. 29,600.00
b. Tenaga
- Pekerja 0.020 Oh x Rp. 43,120.00 = Rp. 862.40
- Tukang Kayu 0.200 Oh x Rp. 57,840.00 = Rp. 11,568.00
- Kepala Tukang 0.020 Oh x Rp. 61,600.00 = Rp. 1,232.00
- Mandor 0.001 Oh x Rp. 64,400.00 = Rp. 64.40
JUMLAH = Rp. 13,726.80
JUMLAH (a) + (b) = Rp. 43,326.80
9 1 buah pasang pegangan pintu / door holder Kualitas Baik pada Pintu 1x bukaan
a. Bahan
- Door holder 1.000 Set x Rp. 225,000.00 = Rp. 225,000.00
JUMLAH = Rp. 225,000.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 254,604.60
10 1 Set pasang pegangan pintu Kualitas Baik pada Pintu 2x bukaan (Pintu Kebaya)
a. Bahan
- Door holder 2.000 Set x Rp. 225,000.00 = Rp. 450,000.00
JUMLAH = Rp. 450,000.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 479,604.60
11 1 Buah pasang Kunci pintu Kebaya Kualitas Baik
a. Bahan
- Kunci Pintu Kebaya 1.000 Bh x Rp. 275,000.00 = Rp. 275,000.00
JUMLAH = Rp. 275,000.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 304,604.60
-
PEKERJAAN KUNCI DAN KACA
12 1 buah pasang Grendel Pintu Kebaya Kualitas Baik
a. Bahan
- Grendel Tanam 1.000 Set x Rp. 75,000.00 = Rp. 75,000.00
JUMLAH = Rp. 75,000.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 104,604.60
13 1 buah pasang Grendel Pintu biasa Kualitas Baik
a. Bahan
- Grendel Tempel 1.000 Set x Rp. 23,600.00 = Rp. 23,600.00
JUMLAH = Rp. 23,600.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 53,204.60
14 1 buah pasang Grendel Jendela Kualitas Baik
a. Bahan
- Grendel Tempel Kecil 1.000 Set x Rp. 22,400.00 = Rp. 22,400.00
JUMLAH = Rp. 22,400.00
b. Tenaga
- Pekerja 0.005 Oh x Rp. 43,120.00 = Rp. 215.60
- Tukang Kayu 0.500 Oh x Rp. 57,840.00 = Rp. 28,920.00
- Kepala Tukang 0.005 Oh x Rp. 61,600.00 = Rp. 308.00
- Mandor 0.0025 Oh x Rp. 64,400.00 = Rp. 161.00
JUMLAH = Rp. 29,604.60
JUMLAH (a) + (b) = Rp. 52,004.60
-
PEKERJAAN KUNCI DAN KACA
15 1 m2 pasang kaca, tebal 3 mm
a. Bahan
- Kaca 3 mm 1.100 m2 x Rp. 193,700.00 = Rp. 213,070.00
JUMLAH = Rp. 213,070.00
b. Tenaga
- Pekerja 0.015 Oh x Rp. 43,120.00 = Rp. 646.80
- Tukang Kayu 0.150 Oh x Rp. 57,840.00 = Rp. 8,676.00
- Kepala Tukang 0.015 Oh x Rp. 61,600.00 = Rp. 924.00
- Mandor 0.00075 Oh x Rp. 64,400.00 = Rp. 48.30
JUMLAH = Rp. 10,295.10
JUMLAH (a) + (b) = Rp. 223,365.10
16 1 m2 pasang kaca, tebal 5 mm
a. Bahan
- Kaca 5 mm 1.100 m2 x Rp. 282,800.00 = Rp. 311,080.00
JUMLAH = Rp. 311,080.00
b. Tenaga
- Pekerja 0.015 Oh x Rp. 43,120.00 = Rp. 646.80
- Tukang Kayu 0.150 Oh x Rp. 57,840.00 = Rp. 8,676.00
- Kepala Tukang 0.015 Oh x Rp. 61,600.00 = Rp. 924.00
- Mandor 0.00075 Oh x Rp. 64,400.00 = Rp. 48.30
JUMLAH = Rp. 10,295.10
JUMLAH (a) + (b) = Rp. 321,375.10
17 1 m2 pasang kaca buram tebal 5 mm
a. Bahan
- Kaca buram 1.100 m2 x Rp. 371,700.00 = Rp. 408,870.00
- Sealent 0.050 kg x Rp. 12,500.00 = Rp. 625.00
JUMLAH = Rp. 409,495.00
b. Tenaga
- Pekerja 0.025 Oh x Rp. 43,120.00 = Rp. 1,078.00
- Tukang Kayu 0.250 Oh x Rp. 57,840.00 = Rp. 14,460.00
- Kepala Tukang 0.025 Oh x Rp. 61,600.00 = Rp. 1,540.00
- Mandor 0.00125 Oh x Rp. 64,400.00 = Rp. 80.50
JUMLAH = Rp. 17,158.50
JUMLAH (a) + (b) = Rp. 426,653.50