OBJECTIVESAfter studying this chapter, the student will be able to:
• Review process diagram symbols.
• Describe the use of process diagrams and the information they contain.
• Draw a process flow diagram.
• Draw a process and instrument drawing.
• Describe the various process equipment relationships.
251
MASTER ➁
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 251
MASTER ➁
Key TermsElectrical drawings—symbols and diagrams that depict an electrical process.
Elevation drawings—a graphical representation that shows the location of process equipment inrelation to existing structures and ground level.
Equipment location drawings—show the exact floor plan for location of equipment in relation tothe plan’s physical boundaries.
Flow diagram—a simplified sketch that uses symbols to identify instruments and vessels and todescribe the primary flow path through a unit.
Foundation drawings—concrete, wire mesh, and steel specifications that identify width, depth,and thickness of footings, support beams, and foundation.
Legends—a document used to define symbols, abbreviations, prefixes, and specialized equipment.
Process and instrument drawing (P&ID)—a complex diagram that uses process symbols todescribe a process unit; also called piping and instrumentation drawing.
Chapter 12 ● Process Diagrams
252
Types of Process Diagrams
Process diagrams can be broken down into two major categories: processflow diagrams (PFDs) and process and instrument drawings (P&IDs),sometimes called piping and instrumentation drawings. A flow diagram is asimple illustration that uses process symbols to describe the primary flowpath through a unit. A process flow diagram provides a quick snapshot ofthe operating unit. Flow diagrams include all primary equipment and flows.A technician can use this document to trace the primary flow of chemicalsthrough the unit. Secondary or minor flows are not included. Complex con-trol loops and instrumentation are not included. The flow diagram is usedfor visitor information and new employee training.
A process and instrument drawing is more complex. The P&ID includes agraphic representation of the equipment, piping, and instrumentation. Mod-ern process control can be clearly inserted into the drawing to provide aprocess technician with a complete picture of electronic and instrumentsystems. Process operators can look at their process and see how the en-gineering department has automated the unit. Pressure, temperature, flow,and level control loops are all included on the unit P&ID.
Basic Instrument Symbols
Process technicians use P&IDs to identify all of the equipment, instru-ments, and piping found in their units. New technicians use these drawings
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 252
Basic Instrument Symbols
253
MASTER ➁
GlobeValve
GateValve
Reboiler
Three-WayValve
Check Valve
Shell & Tube Heat Exchanger
BleederValves
PneumaticOperated
CentrifugalPumps
RotaryCompressor
ManualOperated
Valve
Gauge
VacuumPumpReciprocating
Compressor
Turbine
Orifice
PneumaticOperated
Butterfly Valve
Compressor &Silencers
Single PassHeat Exchanger
U-TubeHeat Exchanger
SafetyPSV
Butterfly
Ball
SolenoidValve
CLOSED
S
VALVES
PUMPS & TURBINECOMPRESSORS
HEAT EXCHANGERS
Bin
Tank
Tower
Drum or Condenser
Mixer
Mixing Reactor
Minor Process
Pneumatic
Hydraulic
Capillary Tubing
Electromagnetic Signal
Electric
X X X X XX
L L L
VESSELS
Furnace
Liquid RingCompressor
Hairpin Exchanger
CondenserHeater
Centrifugal Compressor
Towerwith Packing
Centrifugal Compressor(Turbine Driven)
T
Gear Pump
Vertical
Screw Pump
Rotameter
Four-WayNeedle Angle
LINE SYMBOLS
Major Process
Future Equipment
Plug
Diaphragm
M
H
Hydraulic BackPressureRegulator
BackPressureRegulator
MotorReliefPRV
Induced-Draft Cooling Tower
Forced-Draft Cooling Tower Flow Indicator
Flow Transmitter
Flow Recorder
Pressure Indicator
Pressure Transmitter
Pressure Recording Controller
FI
FT
FR
PI
PT
PRC
Temp Indicator
Temp Transmitter
Temp Recorder
Level Indicator
Level Transmitter
Level Controller
TI
TT
TR
LI
LT
LC
Figure 12.1a Process and Instrument Symbols
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 253
during their initial training period. Knowing and recognizing these symbolsis important for a new technician.The chemical processing industry has as-signed a symbol for each type of valve, pump, compressor, steam turbine,heat exchanger, cooling tower, basic instrumentation, reactor, distillationcolumn, furnace, and boiler (Figure 12.1). There are symbols to representmajor and minor process lines and pneumatic, hydraulic, or electric lines,and there is a wide variety of electrical symbols.
Flow Diagrams
New technicians are required to study a simple flow diagram of their as-signed operating system. Process flow diagrams typically include the majorequipment and piping path the process takes through the unit. As operatorslearn more about symbols and diagrams, they graduate to the much morecomplex P&IDs.
Chapter 12 ● Process Diagrams
254
MASTER ➁
Flow Indicator
Flow Transmitter
Flow Recorder
Pressure Indicator
Pressure Transmitter
FI
FT
FR
PI
PT
Temp Indicator
Temp Transmitter
Temp Recorder
Level Indicator
Level Transmitter
Level Controller
TI
TT
TR
LI
LT
LC
F I C
55
Variable BeingMeasured
Remote Location(board mounted)Control Loop
Instrument
Remote Location(behind control panel)
Field Mounted
LR Level Recorder
TC Temp Controller
PR Pressure Recorder
Pressure ControllerPC
65 55
5565
65 55
Flow ControllerFC
PIC
PRC
LA
105
40
25
IP
Transducer
Pressure IndicatingController
Pressure RecordingController
Level Alarm
FE Flow Element
TE Temperature Element
LG Level Gauge
AT Analyzer Transmitter
What It Does
Figure 12.1b Process and Instrument Symbols (continued)
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 254
Some symbols are common among plants; others differ from plant to plant.Some standardization of process symbols and diagrams is taking place.The symbols used in this chapter reflect a wide variety of petrochemicaland refinery operations.
Figure 12.2 is a PFD that shows the basic relationships and flow pathsfound in a process unit. It is easier to understand a simple flow diagram if itis broken down into sections: feed, preheating, the process, and the finalproducts. This simple left-to-right approach allows a technician to identifywhere the process starts and where it will eventually end. The feed sectionincludes the feed tanks, mixers, piping, and valves. In the second step, theprocess flow is gradually heated for processing. This section includes heatexchangers and furnaces. In the third section, the process is included. Typ-ical examples found in the process section could include distillationcolumns or reactors.The process area is a complex collection of equipmentthat works together to produce products that will be sent to the final section.
Flow Diagrams
255
MASTER ➁
Furnace
Feed Tank
Bottoms Tank
Boiler
Cooling Tower
Reactors
ProductTank
2
ProductTank
1
Vacuum Pump
Column
Drum
Figure 12.2 Process Flow Diagram (PFD)
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 255
Process and Instrument Drawings
A P&ID is a complex representation of the various units found in a plant(Figure 12.3). It is used by people in a variety of crafts. The primary usersof the document after plant startup are process technicians and instrumentand electrical, mechanical, safety, and engineering personnel.
In order to read a P&ID, the technician needs an understanding of theequipment, instrumentation, and technology. The next step in using a P&IDis to memorize your plant’s process symbol list. This information can befound on the process legend. Process and instrument drawings have a va-riety of elements, including flow diagrams, equipment locations, elevationplans, electrical layouts, loop diagrams, title blocks and legends, and foun-dation drawings. The entire P&ID provides a three-dimensional look at thevarious operating units in a plant.
Process LegendThe process legend (Figure 12.4) provides the information needed to inter-pret and read the P&ID. Process legends are found at the front of the P&ID.The legend includes information about piping, instrument and equipment
Chapter 12 ● Process Diagrams
256
MASTER ➁
F-105
Tk-10
Tk-16
B-105
CT-105
Rx-105C-105
FCV
I/P
TT TC
I/P
PT
PC
PCV
I/P
LT
LC
I/P
I/PLT LC
TE TT TC I/P
P-10
P-11
Rx-106
P-12
V-1
D-105
Tk-12
Tk-14
P-13
P-14
V-2 V-3
V-4
V-5
V-6
EX-105
V-7
P-15
FT
FC
Figure 12.3 Process and Instrument Diagram (P&ID)
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 256
Process and Instrument Drawings
257
MASTER ➁
GlobeValve
GateValve
Three-WayValve
BleederValves
ManualOperated
Valve
Gauge
Orifice
SAFETY (Gases)
Ball
Solenoid ValveCLOSED
S
Rotameter
Four-Way
Angle Plug
Diaphragm
Butterfly
CheckValve
ReliefValve
Pneumatic
Pneumatic
Pinch Valve
Stop Check
Knife Valve INDUCED DRAFTCrossflow
NATURAL DRAFTCounterflow
FURNACE
BOILER
VacuumPump
Centrifugal
Drum
GearPump Positive
Displacement
Dome RoofTank
Sphere
Rotary ScrewCompressor
Progressive Cavity
Screw Pump
ReciprocatingPump
Sump Pump
Horizontal
Vertical
Internal FloatingRoof Tank
Cone RoofTank
Plate and FrameHeat Exchanger
Air Cooled Exchanger(Louvers Optional)
Double-PipeHeat Exchanger
CC
Spiral Heat Exchanger
Condenser
Heater
SinglePass
Chimney
Two Pass
Draw Off
GenericTray
Demister
SprayNozzle
PackedSection
Manway
VortexBreaker
VALVE SYMBOLS
EQUIPMENT SYMBOLS
Minor Process
Pneumatic
Hydraulic
Capillary Tubing
Electromagnetic, SonicOptical, Nuclear
X X X X
L L L
Major ProcessFuture Equipment
Connecting Line
Non-Connecting Line
Non-Connecting Line
Jacketed or Double Containment
Mechanical Link
Software or Data Link
• • • •
Electric
Flow Indicator
Flow Transmitter
Flow Recorder
Pressure Indicator
Pressure Transmitter
FI
FT
FR
PI
PT
Temp. Indicator
Temp. Transmitter
Temp. Recorder
Level Indicator
Level Transmitter
Level Controller
TI
TT
TR
LI
LT
LC
LR Level Recorder
TC Temp. Controller
PR Pressure Recorder
Pressure ControllerPC
65 55
5565
65 55
Flow ControllerFC
PIC
PRC
LA
105
40
25
IP
Transducer
Pressure IndicatingController
Pressure RecordingController
Level Alarm
FE Flow Element
TE Temperature Element
LG Level Gauge
AT Analyzer Transmitter
APPROVED
GENERAL LEGEND
DRAWING NUMBER
REVISION 1
PC
E
DATE 10-6-99
PAGE 1 OF 30
OO6543
DISTILLATION UNIT
LINE SYMBOLSEQUIPMENT CONT.
INSTRUMENT SYMBOLS
PREFIXES ABBREVIATIONSCW- cooling waterMU- makeupFW- feed waterSE- sewer
RX- reactorUT- utilitiesCA- chemical additionIA- instrument air
D- drumC- columnCT- cooling tower
TK-tankF- furnaceEX- exchanger
P- pumpV- valve
Figure 12.4 Process Legend
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 257
symbols, abbreviations, unit name, drawing number, revision number,approvals, and company prefixes. Because symbol and diagram standard-ization is not complete, many companies use their own symbols in unitdrawings. Unique and unusual equipment will also require a modified sym-bols file.
Foundation DrawingThe construction crew pouring the footers, beams, and foundation usesfoundation drawings (Figure 12.5). Concrete and steel specifications aredesigned to support equipment, integrate underground piping, and providesupport for exterior and interior walls. Process technicians do not typicallyuse foundation drawings, but these drawings are useful when questionsarise about piping that disappears under the ground and when new equip-ment is being added.
Elevation DrawingElevation drawings (Figure 12.6) show the location of process equipmentin relation to existing structures and ground level. In a multistory structure,the elevation drawing provides the technician with information about
Chapter 12 ● Process Diagrams
258
MASTER ➁
N
WE
S
64' 0"
28' 0"
28' 0"
6' 0"
8' 0"
10' 0"
6-8-10 Method
2' x 64' x 18"Load-Bearing
Beam
18"4"
12"
Estimating Materials: cu. yds. = width x length x thickness
27
Remesh RemeshOver Plastic
Remesh
Rebar in All Beams
32' 0"
90
Figure 12.5 Foundation
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 258
equipment location.This information is important for making rounds, check-ing equipment, developing checklists, catching samples, and performingstartups and shutdowns.
Electrical DrawingElectrical drawings (Figure 12.7) include symbols and diagrams that de-pict an electrical system. Electrical drawings show unit electricians wherepower transmission lines run and places where power is stepped down orup for operational purposes.
A process technician typically traces power to the unit from a motor controlcenter (MCC). The primary components of an electrical system are theMCC, motors, transformers, breakers, fuses, switchgears, starters, andswitches. Specific safety rules are attached to the operation of electricalsystems. The primary safety system is the isolation of hazardous energy“lock-out, tag-out.” Process technicians are required to have training in thisarea. Figure 12.7 shows the basic symbols and flow path associated withan electrical drawing. Electrical lines are typically run in cable trays toswitches, motors, ammeters, substations, and control rooms.
A transformer is a device used by industry to convert high voltage to lowvoltage. The electric department always handles problems with transform-ers. Electric breakers are designed to interrupt current flow if design condi-tions are exceeded. Breakers are not switches and should not be turned on
Process and Instrument Drawings
259
MASTER ➁
EL 16' 0"
EL28' 0"
EL-40' 0"
TK-105
RX-105
TK-200
TK-300
RX-106
RX-300 C-300
D-56
Figure 12.6Elevation Drawing
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 259
Chapter 12 ● Process Diagrams
260
MASTER ➁
V Voltmeter: measures voltage Vs Voltmeter Switch
27
Power Transformer: reduces high voltage
Potential Transforming Symbol
Under Voltage Relay
M Motor MCC Motor Control Center
Switch
Fuse
Circuit Breaker: a protective devicethat interrupts current flow through anelectric circuit
A
As
50
51
Ammeter: measures electric current Ammeter switch
Transformer Overcurrent Relay (Instantaneous)
Transformer Overcurrent Relay (Time delay)
Motor Circuit Contacts
Current Transformer: reduces high voltage to instrumentation.
BOILERSteamTurbine
Generator
69,000 Volts
69 KV
13,200 V13, 800 V2,300 V
13.2 KV13.8 KV2.3 KV
OnOff
Motor
2.3 KV or480 Volts
51
MAINTRANSFORMER
As
A
27
V
Vs
MCC #1
480V BUS MAIN POWER DISTRIBUTION
ELECTRIC POWER PLANT
M M
MotorStarter
MotorStarter
Figure 12.7 Electrical Drawing
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 260
or off. If a tripping problem occurs, the technician should call for an electri-cian. Fuses are devices designed to protect equipment from excess cur-rent. A thin strip of metal will melt if design specifications are exceeded.During operational rounds, technicians check the ammeters inside theMCC for current flow to their electrical systems. Voltmeters, electricaldevices used to monitor voltage in an electrical system, are also checkedduring routine rounds.
Equipment Location DrawingEquipment location drawings (plot plans) show the exact location ofequipment in relation to the plant’s physical boundaries (Figure 12.8). Oneof the most difficult concepts to explain to a new process technician is thescope and size of modern chemical processing. Most chemical plants andrefineries closely resemble small cities; they have well-defined blocks andareas connected by a highway of piping and equipment. Equipment loca-tion drawings provide information about the neighborhood.
Loop DiagramsA loop diagram traces all instrument connections between the field instru-ment and the control room panel. This includes instrument air lines, wiringconnections at field junction boxes, and control room panels and frontconnections.
Electrical One-Line DiagramsLike the piping in process systems, the wiring in a unit follows a path. Electri-cal diagrams show a flow path for distributing power throughout the unit and
Process and Instrument Drawings
261
MASTER ➁
TK-100TK-100
P-100P-200
P-300P-400
D-200
P-500A
EX-200
EX-202
TK-1 TK-2
TK-3 TK-4
TK-1 TK-2
TK-3 TK-4
P-201
20' 0"
10' 0
"
20' 0
"
18' 0" 8' 0"
20' 0
"
8' 0
"
6' 0
"
18' 0"
8' 0"
16' 0"
20' 0"
C-200C-200
TK-200TK-200
TK-400TK-400TK-300TK-300
Figure 12.8Equipment Location
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 261
to all electrical equipment. These diagrams show the different voltage levelsin the unit, electrical equipment such as transformers, circuit breakers, fuses,and motors and horsepower required. It also includes start/stop switches,emergency circuits, and motor control centers. Process technicians can usethese diagrams to trace a system from the power source to the load.
Review of Basic and Specialized Symbols
Piping and ValvesEach plant will have a standardized file for their piping symbols. Processtechnicians should carefully review the piping symbols for major and minorflows; electric, pneumatic, capillary, and hydraulic elements; and futureequipment (Figure 12.9). The major flow path through a unit illustrates the
Chapter 12 ● Process Diagrams
262
MASTER ➁
Y-type Strainer
Duplex Strainer
Basket Strainer
D Detonation Arrestor
F Flame Arrestor
T Steam Trap
S In-Line Silencer
DS Desuperheater
Ejector / Eductor
Exhaust Head
S Vent Silencer
RSRemovable Spool
Flexible Hose
Expansion Joint
XXX Breather
Vent Cover
In-Line Mixer
Diverter Valve
Rotary Valve
Pulsation Dampener
Flange
Minor Process
Pneumatic
Hydraulic
Capillary Tubing
Electromagnetic, SonicOptical, Nuclear
X X X X
L L L
Major Process
Future Equipment
Connecting Line
Non-Connecting Line
Non-Connecting Line
Jacketed or Double Containment
Mechanical Link Software or Data Link• • • •
Electric
Figure 12.9Piping Symbols
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 262
critical areas a new technician should concentrate on. A variety of othersymbols are included on the piping. These include valves (Figure 12.10),strainers, filters, flanges, spool pieces, insulation, piping size, pressure rat-ing, material codes, and steam traps.
Pumps and TanksPumps and tanks come in a variety of designs and shapes. Common pumpand tank symbols are shown on Figure 12.11.
Compressors, Steam Turbines, and MotorsBecause compressors and pumps share a common set of operating prin-ciples and are classified as dynamic or positive displacement, the sym-bols for compressors may closely resemble those for pumps (compare
Review of Basic and Specialized Symbols
263
MASTER ➁
GlobeValve
GateValve
Three-WayValve
BleederValves
PneumaticOperated
ManualOperated
Valve
Gauge Orifice
SAFETY (Gases)
Butterfly
Ball
Solenoid ValveCLOSED
S
Rotameter
Four-Way
Needle
Angle
Plug
Diaphragm
Butterfly Butterfly
CheckValve
CheckValve
ReliefValve
M
Pneumatic Motor Hydraulic
M H
M H M
Ball
H M
Pneumatic Motor HydraulicMotor
Motor orHydraulic
Pneumatic
Motor
M
GATE VALVES
GLOBE VALVES
BALL VALVES
BUTTERFLY VALVES
DIAPHRAGM VALVES CHECK VALVES
PLUG VALVES
Motor orHydraulic
Motor orHydraulic
Plug
Pinch Valve
Stop Check
Knife Valve
RELIEF (Liquids)
Figure 12.10Valves
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 263
Figures 12.11 and 12.12). In most cases, the compressor symbol is slightlylarger than the pump symbol.
In the multistage, centrifugal compressors, the narrowing of the symbol fromleft to right denotes compression of the gas before it is released. This is insharp contrast to the steam turbine symbol, which illustrates the opposite ef-fect as the steam expands while passing over the rotor. Modern P&IDs showthe motor symbol connected to the driven equipment. This equipment maybe a pump, compressor, mixer, or generator. Figure 12.12 illustrates thestandardized symbols for compressors, steam turbines, and motors.
Heat Exchangers and Cooling TowersHeat exchangers and cooling towers are two types of industrial equipmentthat share a unique relationship. A heat exchanger is a device used to
Chapter 12 ● Process Diagrams
264
MASTER ➁
Vacuum Pump
CENTRIFUGAL PUMPS
Bin Tank
Drum
GearPump
Vertical
Screw Pump
POSITIVE DISPLACEMENT PUMPS
Positive Displacement
Dome RoofTank
Open TopTank
Tank
Sphere Onion Tank
STORAGE SYMBOLS
Progressive Cavity
PositiveDisplacement
Screw Pump
Vertical CanPump
Reciprocating Pump
Sump Pump
Horizontal
Vertical
Vertical
Internal FloatingRoof Tank
Cone RoofTank
Double WallTank
External FloatingRoof
Figure 12.11 Pumps and Tanks
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 264
transfer heat energy between two process flows. The cooling tower per-forms a similar function, but cooling towers and heat exchangers use dif-ferent scientific principles to operate. Heat exchangers transfer heat energythrough conductive and convective heat transfer, whereas cooling towerstransfer heat energy to the outside air through the principle of evaporation.Figures 12.13 and 12.14 illustrate the standard symbols used for heatexchangers and cooling towers.
The symbol for a heat exchanger clearly illustrates the flows throughthe device. It is important for a process technician to be able to recog-nize the shell inlet and outlet and the tube inlet and outlet flow paths. Aheat exchanger with an arrow drawn through the body illustrateswhether the tubeside flow is being used to heat or cool the shellsidefluid. The downward direction indicates heating; the upward direction il-lustrates cooling.
Review of Basic and Specialized Symbols
265
MASTER ➁
Figure 12.12 Compressors, Steam Turbines, and Motors
STEAM TURBINE
Doubleflow Turbine
RotaryCompressor
ReciprocatingCompressor Rotory
Compressor & Silencers
CENTRIFUGAL COMPRESSORS
Centrifugal Compressor
Centrifugal Compressor(Turbine Driven)
PD COMPRESSORS
Rotary ScrewCompressor
PositiveDisplacement
Blower
Liquid RingVacuumCentrifugal
Blower
CentrifugalCompressor
Reciprocating Compressor
Motor
MOTORS
Turbine Driver
Diesel Motor
Agitator or Mixer
Axial Compressor
T
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 265
Chapter 12 ● Process Diagrams
266
MASTER ➁
Plate and FrameHeat Exchanger
Air Cooled Exchanger(Louvers Optional)
Double-PipeHeat Exchanger
CC
Spiral Heat Exchanger
Shell and Tube Heat Exchanger
Single PassHeat Exchanger
U-TubeHeat Exchanger
Hairpin Exchanger
CondenserHeater
Reboiler
Figure 12.13Heat Exchangers
INDUCED DRAFTCrossflow FORCED DRAFT
Counterflow
HYPERBOLICChimney Tower
NATURAL DRAFTCounterflow
Figure 12.14Cooling Towers
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 266
The symbol for a cooling tower is designed to resemble the actual devicein the process unit. Cooled product flows out of the bottom of the tower andto the processing units. Hot water returns to a point located above the fill.The symbol will not show all of the various components of the cooling towersystem, but it will provide a technician with a good foundation in coolingtower operation and enough information to clearly see the process.
Furnaces and BoilersThe standard symbols file for furnaces and boilers is shown in Fig-ure 12.15. If a proprietary process includes several types of equipment nottypically found on a standard symbol file, the designer will draw the deviceas it visually appears in the unit.
Distillation ColumnsDistillation columns come in two basic designs, plate and packed (Fig-ure 12.16). Flow arrangements vary from process to process. The sym-bols allow the technician to identify primary and secondary flow paths.Distillation is a process designed to separate the various components ina mixture by their boiling points. (See Chapter 15.) A distillation column isthe central component of a much larger system. This system typically in-cludes all of the equipment symbols found in this chapter. Plate distillationcolumns include sieve trays, valve trays, and bubble-cap trays. Packedcolumns are filled with packing material, rings, saddles, sulzer, androsette.
ReactorsReactors (Figure 12.17) are stationary vessels and can be classified asbatch, semibatch, or continuous. A reactor is designed to allow chemi-cals to mix together under specific conditions to make chemical bonds,break chemical bonds, or make and break chemical bonds to form newproducts.
Review of Basic and Specialized Symbols
267
MASTER ➁
Furnace Boiler
Figure 12.15Furnace and Boiler
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 267
Sources of Informationfor Process Technicians
Information used by process technicians comes from a variety of sources.Some of these sources are:
• Operating training manuals• Process descriptions• Process control manuals• Equipment summaries• Safety, health, and environment regulations• Operating procedures• Startup and shutdown procedures
Chapter 12 ● Process Diagrams
268
MASTER ➁
PLATE TOWERBubble-cap, Sieve, Valve
PACKED TOWERSaddle, Ring, Sulzer, Rosette
Single Pass
Chimney
Two Pass
Draw Off
Generic Tray
Demister
Spray Nozzle
Packed Section
Manway
Vortex Breaker
Figure 12.16Distillation Symbols
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 268
• Emergency procedures• Process diagrams• Technical data books• Detailed equipment vendor information
Summary
Process flow diagrams (PFDs) and process and instrument drawings(P&IDs) are used to outline or explain the complex flows, equipment, in-strumentation, electronics, elevations, and foundations that exist in aprocess unit. A PFD is a simple flow diagram that describes the primaryflow path through a unit. A P&ID is a complex representation of the variousunits found in a plant. Standardized symbols and diagrams have beendeveloped for most pieces of industrial equipment, process flows, andinstrumentation.
Summary
269
MASTER ➁
Hydrocracking Hydrodesulfurization Reformer
Fluid CatalyticCracking
Fluid Coking TubularReactor
FluidizedReactor
Mixing Reactor Alkylation
Figure 12.17Reactor Symbols
30678_12_ch12_p251-270.qxd 06/09/2006 11:14 Page 269
Chapter 12 ● Process Diagrams
270
MASTER ➁
Review Questions1. Describe a process flow diagram and a process and instrument drawing.
2. Draw the symbols for a gate, globe, and automatic valve.
3. Draw the symbols for a centrifugal pump and positive displacement pump.
4. Draw the symbols for a blower and a reciprocating compressor.
5. Draw the symbols for a steam turbine and centrifugal compressor.
6. Draw the symbols for a heat exchanger and a cooling tower.
7. Draw the symbols for a packed distillation column and plate distillation column.
8. Draw the symbols for a furnace and a boiler.
9. Draw a simple process flow diagram using the symbols from questions 2–8.
10. What information is obtained from a loop diagram?
11. What information is available on electrical one-line diagrams?
12. What information is contained on a plot plan drawing?