Post on 25-Jul-2015
Pembangkit listrik batu bara vs pembangkit listrik panas bumi
“Sharing” PT Rekayasa Industri untukStrategi Penyediaan Tenaga Listrik
Jangka Panjangpada Sistem Jawa-Bali
Agenda presentasi
• Pengalaman PLTU (Batu bara)
• Pengalaman PLTP (Panas bumi)
• Berbagai kemudahan akhir-akhir ini
• Ringkasan
• Usulan & Permohonan
LAMPUNG
PADANG
CERENTI MINE (PT BA)Resources : 1,340 million tonMineable : 569 million ton
OMBILIN MINE (PT BA) Resources : 91 million ton Mineable : 27 million ton
TANJUNG ENIM MINE (PT BA)Resources : 5,931 million tonMineable : 870 million ton
TARAHAN PORT (PT BA)Stockpile (1,2,3): 560,000 tonDesign: 12 mio tpa (riil: 8,8 mio tpa)Vessel : Max. 80,000 DWT
KERTAPATI PIER (PT BA)Stockpile : 50,000 tonThroughput : 2,5 million tpaBarge : Max. 8,000 DWT
TELUK BAYUR PORT (PT BA)Stockpile : 90,000 tonThroughput : 2,5 million ton/yearVessel : Max. 40,000 DWT
PLTU BANJARSARI (PT BA+NAVIGAT+PJB)Capacity : 2 x 100 MWCoal Consumption: 1,15 million tpaCoal Source : Ext. Muara Tiga Besar UtaraPLTU BANKO TENGAH (Huadian+PTBA+IIE)Capacity : 4 x 600 MWCoal Consumption: 10 million tpaCoal Source : New Banko Tengah Mine
PLTU PERANAP (IP+PTBA+GOV.RIAU)Capacity : 2 x 250 MWCoal Consumption: 3,5 million tpaCoal Source : New Peranap Mine
PLTU TARAHAN (IP)Capacity (1-4) : 4 x 110 MWCoal Consumption: 2 x 1,2 million tpaCoal Source : Tanjung Enim Mine
PLTU BATURAJA (Cogindo)Capacity : 2 x 100 MWCoal Consumption: 1,15 mio tpaCoal Source : Tanjung Enim Mine
PLTU Mulut Tambang yang dikembangkan oleh PT Bukit Asam
• PLTU Tarahan - Pendanaan JBIC (Jepang)
• PLTU Peranap - Pendanaan tidak jelas
• PLTU Baturaja - Dimenangkan oleh Priamanaya
• PLTU Banjarsari - Sindikasi pinjaman Lokal
• PLTU Bangko tengah – Mayoritas China
Power Purchase Agreement January 07
PLTU 2 x 100 MW Banjarsari, Lahat, Sumsel milik PT Bukit asam
• Mei 2005 Tender IPP oleh PLN• Pemenang PT Bukit Pembangkit Innovative (BPI) - PT Bukit asam 41 % - PT Navigat Innovative Indonesia 39 % - PT Pembangkitan Jawa Bali 20 %• Nilai proyek US $ 239 juta• Januari 2007 sign Power Purchase Agreement (PPA)• Oktober 2007 tanda tangani EPC contract dengan
Jiangxi electric power – US $ 175 juta dan PT Cita contract untuk transmisi 26 km
• Februari 2008 BPI mendapat pinjaman sindikasi dari PT Bank Mandiri dan PT Bank Ekspor Indonesia sebesar Rp 1.64 Triliun (US $ 180 juta)
• Nilai proyek US $ 2,18 Milyard• Kepemilikan saham - Hua Dian (China) 55% - PT Bukit Asam 28%, - PLN 8% - Indika 8% - Pemerintah Kabupaten Muara Enim 1%• Masih negosiasi Power Purchase Agreement
dengan PLN
PLTU 4 x 600 MW Bangko tengah, Lahat, Sumsel milik PT Bukit asam
Program percepatan 10.000 MWpada Sistem Jawa – Bali
(yang memakai jaminan pemerintah)
• PLTU Suralaya, Banten - 1 x 625 MW• PLTU Labuan, Banten - 2 x 316 MW • PLTU Teluk naga, Banten - 2 x 300 MW• PLTU Pelabuhan ratu - 3 x 300 MW• PLTU Indramayu - 3 x 330 MW• PLTU Paiton baru - 1 x 660 MW• PLTU Pacitan - 2 x 300 MW Total di tahun 2010 - 5007 MW
Harga pembangkit PLTU
No Lokasi MWAsing
($ x 1000)Lokal
(Rp x 1000)Total dalam (Rp x 1000)
Price per KW dalam Rp
Price per KW $
1 Pacitan Dongfang Dalle
2x315 630 344.971 1,230,000,000 4,403,733,200 6,990,053 760
2Pelabuhan
ratu ShanghaiMaxima
infrastruktur
3x350 1050 566.984 2,250,000,000 7,466,252,800 7,110,717 773
3 Teluk naga Dongfang Dalle
3x315 945 547.459 1,890,000,000 6,926,622,800 7,329,760 797
Program 30.000 MW IPP (Independent Power Producer) status Oktober 2007
Proyek 30.000 MW IPP mencakup
• 127 paket pembangunan pembangkit
• 37 paket berkapasitas 12.527 MW sedang tahap evaluasi dan usulan studi
• 22 paket berkapasitas 8.760 MW pada tahap perundingan
• 16 paket berkapasitas 1.753 MW pada tahap finalisasi PPA
Program pembangkit listrik di Jawa Independent Power Producer (IPP)
Program pembangkit listrik di Bali Independent Power Producer (IPP)
Ringkasan PLTU Batu bara
• Proyek PLTU sangat tergantung dari skema pendanaan & tersedianya jaminan pendanaan
• Proyek percepatan 10.000 MW dijamin oleh pemerintah sehingga dapat berjalan dengan cepat
• Proyek IPP yang berjalan nampaknya yang mempunyai jaminan aset.
• Proyek IPP di Jawa merupakan kombinasi dari PLTU & PLTP
• Harga investasi PLTU sekitar US $ 760 / KW
Agenda presentasi
• Pengalaman PLTU (Batu bara)
• Pengalaman PLTP (Panas bumi)
• Berbagai kemudahan akhir-akhir ini
• Ringkasan
• Usulan & Permohonan
PAPUANEW GUINEA
SUM
ATE
RA
KALIMANTAN
SULAWESI
IRIAN JAYA
BALI
NUSATENGGARA
TIMOR
MALUKU
JAVA
N
500 Km
CAMBODIA
THAILAND
MALAYSIA
BRUNEI
PHILIPPINES
SINGAPORE
Semarang
Medan
Tanjung Karang
Bandung
Manado
Kapasitas Terpasang: 2300 MW (9 %)Atau setara dengan : 98.000 BOPD
Jawa – Bali (1695 Jawa – Bali (1695 MW)MW)
Kamojang 260 MWKamojang 260 MWDarajat 330 MWDarajat 330 MW
Gn.Salak 375 MWGn.Salak 375 MWWayang-Windu 220 MWWayang-Windu 220 MW
Dieng 180 MWDieng 180 MWPatuha 180 MWPatuha 180 MW
Bedugul 120 MWBedugul 120 MWKaraha Bodas 30 MWKaraha Bodas 30 MW
Jawa – Bali (1695 Jawa – Bali (1695 MW)MW)
Kamojang 260 MWKamojang 260 MWDarajat 330 MWDarajat 330 MW
Gn.Salak 375 MWGn.Salak 375 MWWayang-Windu 220 MWWayang-Windu 220 MW
Dieng 180 MWDieng 180 MWPatuha 180 MWPatuha 180 MW
Bedugul 120 MWBedugul 120 MWKaraha Bodas 30 MWKaraha Bodas 30 MW
Sumatera(395MSumatera(395MW)W)
Sibayak 10 MWSibayak 10 MWSarulla 220 MWSarulla 220 MW
Ulubelu 220 MWUlubelu 220 MWLumut Balai 110 MWLumut Balai 110 MW
Sumatera(395MSumatera(395MW)W)
Sibayak 10 MWSibayak 10 MWSarulla 220 MWSarulla 220 MW
Ulubelu 220 MWUlubelu 220 MWLumut Balai 110 MWLumut Balai 110 MW
Sulawesi (80 Sulawesi (80 MW)MW)
Lahendong 80 MWLahendong 80 MW
Sulawesi (80 Sulawesi (80 MW)MW)
Lahendong 80 MWLahendong 80 MW13,820 MWe
1,996 MWe
584 MWe1,487 MWe
9,253.5 MWe
KOB68%
32%
PERTAMINA OWN930 MW ~ 35.000 BOPD
Rencana pengembangan PLTP (panas bumi) sampai tahun 2010
Energi panas bumi dapat digunakan untuk membangkitkan tenaga listrik
100 MW Installed capacity
4.250 Barrel of
Oil per day
100 MWInstalled capacity
864Ton of Coal
Per day
Geothermal vs CoalGeothermal vs Oil
PLTP 20 MW Lahendong-2 yang kami bangun & selesai tepat waktu Juni 07
Turbin dan generator di Proyek Lahendong-2 masih import
Perbandingan Konsumsi Bahan Bakar• PLTD (Diesel)
– Fuel Specific Consumption :• 0,21 liter / kWh
– Fuel consumption per year :• 0,21 (l/kwh) x 8700 (hrs/year)• 1827 liter / kW-year• 1,82 juta-liter/MW-year
• PLTP (Panas Bumi)– Steam specific consumption :
• 7,5 ton/MW-hour– Steam consumption per year :
• 7,5 (ton/MW-h) x 8700 (hrs/year)• 65250 ton / MW-year
Perbandingan biaya energi
– Harga Solar (tanpa subsidi) = US $ 0.5 per liter– Harga Steam = US $ 3 per ton– Conversion Rate : 1 USD = Rp.9.200,-
Perbandingan biaya bahan bakar
PLTDPLTP
Tanpa Subsidi
Specific Fuel Consumption
0,21 liter/kW-h 7,5 kg/kW-h
Fuel consumption per MW-year
1,82 juta-liter 61875 ton
Harga satuan 0.5 USD/liter 3 USD/ton
Fuel Cost per MW-year
US $ 913.500 US $ 185.625
Subsidi fuel per MW-year
0 0
Unit Cost per kWh 10.5 c/kWh 2.25 c/kWh
Catatan :Conversion Rate Rp. 9.200 / USDPLN Selling Price = 4.5 c/kWh
Perbandingan penghematan PLTP Lahendong-2 vs PLTD
PLTD PLTP
Tanpa Subsidi
Specific Fuel Consumption
0,21 liter/kW-h 7,5 kg/kW-h
Fuel consumption per MW-year
1,82 juta-liter solar 61875 ton steam
Fuel consumption for 2000 MW-year
36,54 juta-liter 1,23 juta ton
Harga satuan US $ 0.5 /liter US $ 3 /ton
Fuel Cost for 20 MW-year
US $ 18,270,000 US $ 3,712,500
Saving 0 USD 14,557,500
Proyek PLTP 60MW yang kami bangun & selesai tepat waktu Jan 08
Turbine & Generator di Proyek PLTP Kamojang-4 juga masih import
Perbandingan harga investasi PLTP di Indonesia akhir-akhir ini
• PLTP Kamojang-4 60 MW – US $ 60 juta
harga per KW = US $ 1.000
• PLTP Darajat-3 100MW – US $ 84 juta
harga per KW = US $ 840
Agenda presentasi
• Pengalaman PLTU (Batu bara)
• Pengalaman PLTP (Panas bumi)
• Berbagai kemudahan akhir-akhir ini
• Ringkasan
• Usulan & Permohonan
Kemudahan pemerintah untuk pembangunan PLTP
1. November 2007 – Pemerintah telah mengeluarkan PP No 57 tentang kepemilikan WKP Panas Bumi
2. Desember 2007 – beberapa WKP telah diserahkan oleh Menteri ESDM ke para gubernur di seluruh Indonesia
3. Desember 2007 – Karbon kredit telah diperoleh oleh beberapa PLTP di Indonesia
4. Januari 2008 – Investasi PLTP Bebas bea masuk
5. Feb 2008 – Gubernur undang investor PLTP
Sebuah informasi menarik tentang Carbon credit PLTP Darajat-3
1. Investasi drilling – US $ 30 juta
2. Investasi pembangkit & sistem perpipaan proyek PLTP Darajat-3 – US $ 84 juta
3. Total investasi (diluar IDC) – US $ 114 juta
4. Carbon credit yang diperoleh Chevron untuk proyek Darajat-3 – US $ 124 juta
5. Chevron praktis tidak mengeluarkan biaya untuk membangun PLTP Darajat-3
Berapa uang yang hilang dari PLTP 100 MW Darajat-3 ?
Pendapatan • Harga per kwh, misal $ 0.05/kwh• Selama 1 jam = US $ 5.000• Selama 1 hari = US $ 120.000• Selama 1 bulan = US $ 3.600.000• Selama 1 tahun = US $ 43.200.000 (A)Biaya• Biaya steam per kwh, misal $ 0.025/kw• Selama 1 tahun = US $ 26.600.000 (B)
Keuntungan PLTP Darajat-3 = US $ 26.6 juta per tahun
Agenda presentasi
• Pengalaman PLTU (Batu bara)
• Pengalaman PLTP (Panas bumi)
• Berbagai kemudahan akhir-akhir ini
• Ringkasan
• Usulan & Permohonan
Ringkasan1. Biaya investasi PLTP saat ini sudah “comparable”
dengan biaya investasi PLTU (US $ 800/KW)
2. Biaya operasi (pembangkitan listrik) PLTP sangat murah (20 % dari PLTD)
3. Di Jawa & bali masih ada cadangan 9253 MW atau ekivalen dengan 388.626 Barrel oil/hari
4. PLTP “renewables energy” (terbarukan)
5. PLTP sangat “environmental friendly” & telah peroleh Carbon credit contoh Darajat-3 – “zero”
6. Pemerintah saat ini telah memberikan banyak sekali kemudahan untuk pembangunan PLTP seperti Pembebasan bea masuk, & WKP
Agenda presentasi
• Pengalaman PLTU (Batu bara)
• Pengalaman PLTP (Panas bumi)
• Berbagai kemudahan akhir-akhir ini
• Ringkasan
• Usulan & Permohonan
Permohonan kepada Kementerian Ristek, BPPT & Lembaga penelitian
• Mohon Kementerian Ristek dan BPPT membantu kami untuk bersama-sama mengembangkan PLTP (energi panas bumi)
• Bahan baku PLTP sangat melimpah coba bandingkan dengan bahan baku PLTN & PLTU
• PLTP sangat environmental friendly, coba bandingkan dengan PLTN yang belum jelas sistem pembuangan limbahnya & limbah PLTU
• Biaya investasi PLTP relatif sudah murah, coba bandingkan dengan PLTN ($ 1300/KW)
Apa peran Kementerian Ristek dan BPPT dalam pembangunan PLTP ?
• PP No 57 memberikan kesempatan untuk kepemilikan WKP Panas bumi
• Metodanya serupa dengan tata-cara kepemilikan WKP Batu bara dimana kepemilikan diberikan prioritas kepada mereka yang mampu membuat Feasibility study dan pengeboran.
• Sehingga nota bene pemodal besar yang akan menguasai WKP Panas bumi sebagaimana WKP Batu bara
• Siklus ini harus “dipotong” sebelum energi terakhir yang kita miliki dikuasai oleh pihak asing.
Usulan dan permohonan kami• Pemerintah Daerah (Pemda) ataupun Pemerintah
Kabupaten (Pemkab) melakukan pengeboran bersama dengan para teknolog dari BPPT
• Dana untuk studi dan pengeboran menggunakan APBD ataupun APBN yang diperoleh dari PAD ataupun dari pusat
• Bila kandungan energi panas bumi terkonfirmasi cadangannya, maka sebenarnya pendanaan proyek relatif lebih mudah untuk diperoleh
• Pemerintah daerah dapat bekerja sama dengan investor untuk pengembangan PLTP-nya dimana Pemda akan memiliki sebagian besar sahamnya
Silahkan kunjungi www.rekayasa.com dan www.triharyo.com