Environmental Monitoring Report This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Project Number: 49310-002 Loan Number: 3759 Period: July-September 2021 Document Date: November 2021 People’s Republic of China: Yunnan Lincang Border Economic Cooperation Zone Development Project Prepared by Lincang Project Management Office with the assistance of China Urban Construction Design & Research Institute Co., Ltd. for the Lincang Municipal Government and the Asian Development Bank.

Transcript of Yunnan Lincang Border Economic Cooperation Zone ...

Environmental Monitoring Report

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Number: 49310-002 Loan Number: 3759Period: July-September 2021 Document Date: November 2021

People’s Republic of China: Yunnan Lincang Border Economic Cooperation Zone Development Project

Prepared by Lincang Project Management Office with the assistance of China Urban Construction Design & Research Institute Co., Ltd. for the Lincang Municipal Government and the Asian Development Bank.

Environmental Monitoring Report

Loan Number: 3759-PRC #7 Quarterly Report Period: 3nd Quarter 2021 (July to September 2021)

PRC: Yunnan Lincang Border Economic Cooperation Zone Development Project Prepared by Lincang Project Management Office with the assistance of China Urban Construction Design & Research Institute Co., Ltd. for the Lincang Government and the Asian Development Bank This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of the ADB’s Board of Director, Management or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Asian Development Bank

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

i

TABLE OF CONTENTS

ABBREVIATION ......................................................................................................................... 1

1.0 EXECUTIVE SUMMARY .............................................................................................. 4

2.0 INTRODUCTION............................................................................................................. 5

2.1 Report Purpose and Rational .................................................................................. 5

2.2 Project Objective and Components ......................................................................... 5

2.3 Project Background ................................................................................................. 7

2.4 Project Implementation Progress .................................................................................. 7

3.0 INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION AND SUPERVISION .............................................................. 19

3.1 Institutional Responsibilities for Environmental Management ............................ 19

3.2 Incorporation of Environmental Requirements into Project Contractual Arrangements ........................................................................................................ 20

4.0 COMPLIANCE WITH PROJECT COVENANTS RELATING TO ENVIRONMENTAL MANAGEMENT ....................................................................... 21

5.0 ENVIRONMENTAL MITIGATION MEASURES IMPLEMENTED IN THIS REPORTING PERIOD .................................................................................................. 25

5.1 C-RD04 Nanting River Bridge and Access Roads ..................................................... 40

5.2 C-SS05 Qingshuihe Guomen No.2 Elementary School ............................................. 43

5.3 C-RD01a Qingshuihe No.1 Road ............................................................................... 44

5.5 COVID-19 Risk Prevention ........................................................................................ 45

6.0 SUMMARY OF ENVIRONMENTAL MONITORING ............................................. 48

6.1 Environment Monitoring Plan and Responsibilities ............................................. 48

6.2 Environmental Monitoring Results ............................................................................. 49

6.3 Ecological monitoring ................................................................................................. 59

7.0 GRIEVANCE REDRESS MECHANISM AND IMPLEMENTATION ................... 62

8.0 INSTITUTIONAL STRENGTHENING AND TRAINING ....................................... 66

9.0 ISSUES AND CORRECTIVE ACTIONS .................................................................... 68

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

1

ABBREVIATION

ADB Asian Development Bank 亚洲发展银行

CCG Cangyuan County Government 沧源县政府

CSC Construction supervision company 建设监理公司

CUCD China Urban Construction Design & Research Co., Ltd 中国城市

建设研究院有限公司

CYC Cangyuan County 沧源县

DI Design Institute 设计院

EA Executing Agency 执行机构

EDDR Environmental Due Diligence Report 环境尽职调查报告

EIA Environmental Impact Assessment 环境影响评价

EMP Environmental Management Plan 环境管理计划

EME External Monitoring Experts 外部监测专家

EMA External Monitoring Agency 外部监测机构

EMS Environmental Monitoring Station 环境监测站

EMRs Environment progress and Monitoring Reports 环境进展监测报告

EEB Ecological Environmental Bureau 生态环境局

FTZ Free Trade Zone 自贸区

GRM Grievance Redress Mechanism 申诉响应机制

IA Implementing Agency 实施机构

IEM Internal Environmental Monitoring 内部环境监测

ICA International Cooperation Area 国际合作区

LA Loan Agreement 贷款协议

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

2

LAR Land Acquisition and Resettlement 征地安置

LBECZ Lincang Border Economic Cooperation Development Zone 临沧边

境经济合作区

LIEC Loan Implementation Environmental Consultant 贷款实施环境顾

LMEEB Lincang Municipal Ecology and Environmental Bureau 临沧市生

态环境局

LMG Lincang municipal government 临沧市政府

LPMO Lincang Project Management Office (the PMO) 临沧市项目办

MOU memorandum of understanding 备忘录

O&M operations and maintenance 运行和维护

PA Project Agreement 项目协议

PAM Project Administration Manual 项目管理手册

PCR Project Completion Report 项目竣工报告

PIA Project Implementing Agency 项目实施机构

PIU Project Implementation Unit 项目实施单位

PLG Project Leading Group 项目领导小组

PMO Project Management Office 项目办

PPTA Project Preparation Technical Assistance 项目准备和技术协助

PRC People’s Republic of China 中华人民共和国

RCI Regional Cooperation and Integration 区域合作整合

SPS ADB safeguards policy statement. 亚行安保政策

ToR terms of reference 任务大纲

WWTP wastewater treatment plant 污水处理厂

YLBECZDP Yunnan Lincang Border Economic Cooperation Zone Development

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

3

Project (the Project) 云南临沧边境经济合作区发展项目

YPG

ZCG

Yunnan Provincial Government 云南省人民政府

Zhenkang County Government 镇康县政府

ZKC Zhenkang County 镇康县

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

4

1.0 EXECUTIVE SUMMARY

1. As of September 2021, total of nine subprojects of Yunnan Lincang Border Economic Cooperation Zone Development Project (the Project) were under construction, namely Nanting River Bridge and Access Road Subproject (C-RD04), Qingshuihe No.1 Road (C-RD01a), No. 2 Road (C-RD02) and No. 6 Road (C-RD02-1), Qingshuihe Guomen Elementary School Upgrading (C-SS05), International Production Capacity Phase I (C-ICA01), Zhenkang Hospital (C-SS01), Water Supply (C-ENV01) and river rehabilitation (C-ENV04). C-RD02 and C-RD02-have passed the completion acceptance inspection. For the C-ICA01, the dynamic compaction scheme has not been determined yet, no construction activity in this reporting period. The construction of water supply subproject and river rehabilitation subproject was mobilized at the end of this reporting period. Zhenkang Hospital had no major civil construction activities during this period as the high voltage corridor on site was not relocated yet. Therefore, monitoring during this period is mainly focused on the Nanting River Bridge and access road subproject(C-RD04), Qingshuihe Road No. 1 (C-RD01a) and Qingshuihe Guomen Elementary School Upgrading (C-SS05). 2. From the establishment of the GRM mechanism to the end of September 2021, the project management office, the contractors and construction supervision company of the nine subprojects under construction have not received any environment-related complaint or comments. 3. From August to September 2021, the external monitoring unit Yunnan Kunfa Environmental Technology Co., Ltd. organised air quality, water environment, sound environment and ecological monitoring. All monitoring indicators met the corresponding standards, except for the dissolved oxygen at upstream and downstream of the Nanting River Bridge, which did not meet the standards. The non-compliance was mainly due to high temperatures during the monitoring period, not construction activities. During the ecological survey, a second-class protected tree was found near the construction access road of the Nanting Bridge, and it was suggested that the construction unit should set up a fence for protection. The planting plan for the Qingshui River rehabilitation is not diversified and the gerbera (Cosmos bipinnata) is an invasive alien species. In order to protect the local terrestrial ecological environment, it is recommended to use native species if possible. 4. Overall, the environmental management work in the third quarter of 2021 is progressing Training on the implementation of the environmental management plan for the all contractors and construction supervision companies under construction is scheduled on 19 October 2021.

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

5

2.0 INTRODUCTION

2.1 Report Purpose and Rational 5. As required by the EIA & PA for the Yunnan Lincang Border Economic Cooperation Zone Development Project (YLBECZDP), the borrower is required to prepare quarterly EMRs for submission to the ADB. There is an inconsistency between PAM and the PA regarding the frequency of the EMR that should be prepared and submitted to ADB. The PAM requires the EMR to be submitted on a semi-annual basis, while the PA requires the EMR to be prepared and submitted on a quarterly basis. Hence, the LPMO decided that quarterly EMR shall be prepared and submitted to ADB as required in the PA. 6. This report is prepared by the Lincang Project Management Office (LPMO), with assistance from the LIEC, China Urban Construction Design & Research Institute Co., Ltd (CUCD). Environmental monitoring reports (EMRs) are required in order to evaluate and assess overall project activities to ensure the effective implementation of the environmental management plan (EMP). 7. The purpose of this Environmental Monitoring Report (EMR) is to document environmental management activities undertaken and environmental impacts as a result of project implementation, as well as identifying issues and suggesting corrective actions. This environmental monitoring report is the seventh quarterly EMR, covering the period from July to September 2021. 8. This seventh quarterly EMR is intended not only to cover the construction phase, but also demonstrate compliance with the EMP for the design, bidding, construction preparation stages and physical construction phase. In line with targets aimed at reducing any negative environmental impacts of the Project, and in accordance with relevant specifications and standards of the PRC, and policies of the Asian Development Bank (ADB), this report emphasizes the following areas: (i) progress made in implementing the EMP, (ii) implementation of mitigation measures, (iii) environmental monitoring and compliance, (iv) Grievance redress mechanism,(v) institutional strengthening and training, and (vi) problems that have occurred and corrective actions taken.

2.2 Project Objective and Components 9. The objective of the Project is that the competitiveness of urban centers, logistics and industrial parks, and land ports in the project counties and LBECZ be enhanced. 10. The Project is aligned with the following impacts: (i) economic growth potential for LBECZ and border areas of Myanmar enhanced; (ii) benefits of RCI in LBECZ and border areas of Myanmar realized; and (iii) living conditions and public health of residents of LBECZ and border areas of Myanmar improved. 11. There are 3 outputs involving civil works in the Project and one output that involves no civil works as defined in the loan agreement (LA) as follows, and referred thereto as Outputs 1 to 4 respectively, being.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

6

12. Output 1: Cross-border trade infrastructure improved A. construction and operationalization of a border resident trade market, with a total

building area of 107,454 square meters (m2); B. construction of an international border cooperation area with a total building area of

171,633 m2; C. construction of five urban secondary roads of 4.55 km and a new 350 meter-long

bridge over Nanting River with approach roadway; D. Rehabilitation of a 523-meter Class II road to link Qingshuihe and Mangka border

port. 13. Output 2: Integrated urban environment infrastructure in Mengding and Qingshuihe National Port areas improved.

A. construction of a water supply system in Qingshuihe, including a treatment plant with a total capacity of 20,000 cubic meters per day, a water intake structure and water transmission line of 35 km, and a water distribution network of 28.1 km;

B. construction of a wastewater treatment system in Qingshuihe, including a treatment plant with a total treatment capacity of 10,000 cubic meters per day and wastewater collection pipe network of 7.26 km;

C. establishment of a MSW management system with six collection stations with a capacity of 7 tons per day (t/d), and toilets, in Mengding; two transfer stations (capacity of 27 t/d and 21 t/d) and one collection station (capacity of 7 t/d), and a toilet, in Qingshuihe; and MSW handling equipment for both towns;

D. rehabilitation of 2.38 km of Qingshui River and 1.00 km of Nanpa River, including ecological embankments and landscaping;

E. Delivery of six electric buses and construction of electric charging stations (one each in Mengding and Qingshuihe) for urban public transportation.

14. Output 3: Social infrastructure and services improved A. construction of a new PRC–Myanmar Friendship Hospital with 499 bed capacity and

a total building area of 56,009 m2; B. construction of a new Qingshuihe Hospital with 99 bed capacity and a total building

area of 9,006 m2; C. construction of a new Cangyuan Guomen No. 2 Elementary School with 1,080

student capacity and a total building area of 13,194 m2; D. upgrading and expansion of the existing Qingshuihe Guomen Elementary School to

1,080 student capacity; and construction of new classroom building, student dormitory, and cafeteria, with a total building area of 7,721 m2.

15. Output 4: Institutional capacity of involved agencies improved A. project implementation management and support and safeguards monitoring for the

implementation of the environmental management plan (EMP), resettlement plans, ethnic minority development plan, and gender and social development action plans;

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

7

B. cross-border trade and logistics capacity building; C. development of SMEs; D. teacher training and border elementary school curriculum enhancement; E. TVET school leadership; F. health care services and hospital management improvement; G. RCI development and capacity building; H. LBECZ master plan development and improvement study; and I. Policy dialogue on water tariff system.

2.3 Project Background 16. Since the engagement of the CUCD as the LIEC, the CUCD has mobilized its project team on 8th November 2019. The first introductory EMP training session was conducted by the national environmental specialist from CUCD on the 3rd December, 2019.The CUCD specialists conducted field work during the inception period. Two major objectives have been achieved by the CUCD team through these useful site visits: i) an understanding of the implementation progress and status; and ii) a first-hand appreciation of the environmental and social problems and issues to be addressed during project implementation. The consulting services inception report was submitted to LPMO on 31st December, 2019. 17. Handover of material from the start-up consultant who supported the early stages of project implementation since March 2019, to CUCD. The CUCD received from the LPMO a final package covering all work accomplished by the start-up consultant. The list of information received was shown in the first quarterly EMR report, covering the period before end of December 2019.

2.4 Project Implementation Progress 18. Project components include civil works in three counties (Mengding, Cangyuan & Zhengkang) in the Province of Yunnan. As of 30 September 2021, there were nine subprojects under construction. Status of Contractor Engagement and Project Progress has been summarized in the following table 2.4-1, table 2.4-2 and table 2.4-3. The International Capacity Phase I subproject has no construction activities during this period because the scope of ramming has not been determined. The Qinngshuihe No. 2 and 6 Road subprojects passed the completion acceptance inspection.

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

8

Table 2.4-1 Yunnan Lincang Border Economic Cooperation Zone Development Project –Mengding County

Status of Contractor Engagement and Project Progress

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

LBECZ PIU(Mengding County)

C-MKT01

− Description: Qingshuihe Border Trade Area.

− Scope & Content: the total land area is 320.44 mu, with construction area of 156,698.4 m2. Border resident trade market include market shed structure with area of 56,958 m2, warehouse with area of 14,592 m2, administration building with area of 8,684 m2, and service building with area of 76,464.4 m2.

/ / / / Not yet mobilized.

− Description: Cargo Connection Area

− . Scope & Content: the total land area is 320.44 mu, with construction area of 156,698.4 m2. Border resident trade market include market shed structure with area of 56,958 m2, warehouse with area of 14,592 m2, administration building with area of 8,684 m2, and service building with area of 76,464.4 m2.

− Description: General Trade Area. − Scope & Content: the total land area is

320.44 mu, with construction area of 156,698.4 m2. Border resident trade market include market shed structure with area of 56,958 m2, warehouse with area of 14,592 m2, administration building with area of 8,684 m2, and service building with area of 76,464.4 m2.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

9

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

C-ICA01

− Description: Qingshuihe ICA Phase I. − Scope & Content: the total land area of

project is 533.4 mu, with total building area of 297,917.08 m2. The ICA include FTZ manufacturing area, FTZ warehouse and logistics area, FTZ operation area, custom joint inspection area, service and supporting area, and site development.

/ / / /

The contractor was mobilized on October 16, 2020. As of June 2021, total of 285003.8 m3 excavation works have been completed. No construction activity in this reporting period.

C-ICA02

− Description: Qingshuihe ICA Phase II. − Scope & Content: the total land area of

project is 533.4 mu, with total building area of 297,917.08 m2. The ICA include FTZ manufacturing area, FTZ warehouse and logistics area, FTZ operation area, custom joint inspection area, service and supporting area, and site development. / / / /

Not yet mobilized. Preliminary design has been completed on 20th April, 2020. Bidding

documents were submitted to ADB on December

2020. The contract award is expected to be completed in the fourth quarter of 2021.

− Description: Qingshuihe ICA Phase III. − Scope & Content: the total land area of

project is 533.4 mu, with total building area of 297,917.08 m2. The ICA include FTZ manufacturing area, FTZ warehouse and logistics area, FTZ operation area, custom joint inspection area, service and supporting area, and site development.

C-RD01a

− Description: Qingshuihe No. 1 Road. − Scope & Content: Secondary Road with

899.829m length, 24m red line width, and 30 km/h design speed; Corresponding supporting water supply and drainage, greening, transportation, lighting works.

Yunnan Zhenghao Construction Limited Company

May 2021 /

Yunnan Supervision Association Engineering Consulti

Mobilized on May 30, 2021. Completed works: CFG piles completed 1538, cement mixing piles completed 1878; fill: 2522.32m³

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

10

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

ng Firm

C-RD01b

− Description: Qingshuihe No. 3 Road. − Scope & Content: Secondary Road

with 1260m length, 24m red line width, and 30 km/h design speed; Corresponding supporting water supply and drainage, greening, transportation, lighting works.

/ / / /

Not yet mobilized. Advertisement was released on September 7, 2020. It is expected to award the contract in the fourth quarter of 2021.

C-RD02

− Description: Qingshuihe No.2 Road. − Scope & Content: Branch Road with

788.28m length, 18m red line width, and 20 km/h design speed; Corresponding supporting water supply and drainage, greening, transportation, lighting works.

Yunnan Road and Bridge Co. Ltd.

April 27th 2020

Yunan Zhongke Testing Technology Co. Ltd.

Yunnan Supervisory Association Consulting Co. Ltd.

Completed in 18 September 2021.

C-RD02-1

− Description: Qingshuihe No.6 Road. − Scope & Content: Secondary Road with

523m length, 24m red line width, and 60 km/h design speed; Corresponding supporting water supply and drainage, greening, transportation, lighting works.

Yunnan Road and Bridge Co. Ltd.

April 22nd 2020

Yunan Zhongke Testing Technology Co. Ltd.

Yunnan Supervisory Association Consulting Co. Ltd.

Completed in 18 August 2021.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

11

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

C-RD03

− Description: Qingshuihe No. 4 and No. 5 Road.

− Scope & Content: Branch Road with 644.125m length (No.4) and 1303.995m length (No.5), 18m red line width (No.4) and 15m redline width (No.5), and 20 km/h design speed; Corresponding supporting water supply and drainage, greening, transportation, lighting works.

/ / / / Not yet mobilized. It is plan to release the advertisement in the Q1 of 2022.

C-RD04

− Description: Nanting Bridge and Approach Road.

− Scope & Content: 3 span twin tower cable stayed bridge with 350 m (70+140+70) ; Approach Road is secondary road with 1.866km length, 16.5m width, and 60km/h design speed.

China Construction Road & Bridge Co., Ltd.

October 15th 2019

Yunan Zhongke Testing Technology Co. Ltd.

Yunnan Lutong Construction Consulting& Supervising Company

The project was mobilized on 13th Nov, 2019. As of September 30, 2021, the Nanting River Bridge project has completed the clearing of the roadbed on the south bank, tree cutting and root digging, the leveling and hardening of the construction right-of-way, the completion of all roadbed filling and excavation, the completion of all roadbed filling and excavation, the completion of 95% of roadbed drainage

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

12

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

and protection works, the completion of the construction of roadbed side ditch cover, the completion of K1+233-K1+865.612 pavement sub-base graded gravel and grass-roots water-stabilized gravel paving, the completion of K1+233-K1+865.612 pavement sub-base graded gravel and grass-roots water-stabilized gravel paving. K1+233-K1+865.612 completed the construction of pavement underlayment, steel trestle bridge erection was completed, 64 pile foundations were poured, 4# cylindrical pier construction was completed, 5# bridge abutment construction was completed.

This month, the concrete pouring of 0# bearing platform was completed and the construction of 0# bridge platform reinforcement was in progress; the concrete pouring of the second section of the lower

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

13

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

crossbeam of 1# bridge tower and the tenth section of the bridge tower (37-39m) was completed, the tensioning of the steel strand of the lower crossbeam was in progress and the steel tying of the tenth section of the bridge tower (39-41.5m) was in progress; the concrete pouring of the fourteenth section of the 2# bridge tower (52-55.86m) was completed and the steel pipe column of the middle crossbeam was in progress 3# portal pier cover beam is being dismantled.

C-ENV01

− Description: Qingshuihe water supply treatment plant.

− Scope & Content: including a water intake work with a capacity of 21,000m3/d, a water treatment plant with a capacity of 60,000 m3/d, water transmission pipe lines with total length of 31.8km, and water distribution pipe line with total length of 33km.

Hebei Second Construction Engineering Co.

2 September 2021

/

Yunnan Engineering Construction Supervision Co

Mobilized in September 2021

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

14

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

C-ENV03

− Description: Qingshuihe waste water treatment plant and associated civil works.

− Scope & Content: including WWTP with capacity of 10,000 m3/d (land area: 2.38 mu) and sewage pipe network with the total length of 16.5km.

/ / / / Not yet mobilized. It is expected to award the contract in the Q4 of 2021.

C-ENV04

− Description: Qingshui River and Nanpa River Rehabilitation

− Scope & Content: Planned River regulation work covers 5 km, which includes channel improvement, sludge dredging, sewage interception and river landscaping works.

Yunnan Construction First Hydraulic and Hydropower Construction Co.

September 2021 /

Yunnan Engineering Construction Supervision Co.

Entered the site on 1 September 2021. Major works completed during the period.

(1) Project camp construction: completion of site gravel paving, site foundation concrete pouring and main slab construction.

(2) Section Z0+000-Z0+631 on the left bank of Nampa River: completion of corn field clearance, original geomorphological survey, excavation of construction right-of-way for excavators to enter the site.

(3) Section K0+000-K1+400 on the left bank of the Qingshui River: completion of site clearance, red line release, original geomorphological survey and excavation of

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

15

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

the construction right-of-way for the excavator.

C-SS03

− Description: Qingshuihe hospital civil works

− Scope & Content: Total building area is 14,400 m2 with 9,600 m2of above area and 4,800 m2of the underground area. The main works include medical building, infectious disease building, administration building, service buildings and facilities.

/ / / /

Not yet mobilized. The original site is located in karst zone with complex geological conditions, which is not suitable for personnel-intensive structures. The new site was determined and environmental due diligence is required.

C-SS05

− Description: Qingshuihe Guomen Elementary School Upgrade Civil Works

− Scope & Content: including a new classroom building with area of 3150.0 m2, a new student dormitory with area of 3000.0 m2, and a new cafeteria with area of 1050.0 m2.

China Railway Ninth Bureau Group Limited

July 2020 /

Kunming Construction Consulting Management Co.

Construction started on 22 September 2020 and is expected to be completed in November 2021. Major works completed during the period: completion of the main structure of the cafeteria, completion of the masonry structure and completion of the plastering of the interior and exterior walls.

− Completion of the main structure of the

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

16

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

boys' dormitory, completion of the masonry of floors 1-5 and plastering of floors 1-3.

− Completion of the main structure on the third floor of the women's dormitory and the installation of the beam slab formwork on the fourth floor, and the installation and tying of the beam slab reinforcement.

− Completion of the main structure of the school building and 80 per cent of the masonry work on floors 1-4.

− The outdoor anchor cable rib beam slab for the women's dormitory was poured.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

17

Name of PIU

Civil works

contract Nature of Civil works Name of

Contractor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

Table 2.4-2 Yunnan Lincang Border Economic Cooperation Zone Development Project –Zhengkang County

Status of Contractor Engagement and Project Progress

Name of PIU

Civil works

contract Nature of Civil works

Name of Contrac

tor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

Zhengkang PIU

C-SS01

− Description: PRC-Myanmar Friendship Hospital CW

− Scope & Content: The project covers an area of 40 mu (60,000 m2), total building area 56,009 m2, where floor area 41,409 m2, basement size 14,600 m2. Class 2A general hospital with 499 inpatient beds, medical equipment and devices.

Guizhou Construction Group Third Construction Engineering Co.

7 July 2021 /

Kunming Construction Consulting & Supervision Co.

Site entry in August 2021. There was no major civil construction activity during the reporting period owing to the relocation of the high-voltage corridor involved.

− Description: PRC-Myanmar Friendship Hospital Road

− Scope & Content:

Table 2.4-3 Yunnan Lincang Border Economic Cooperation Zone Development Project –Cangyuan County

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

18

Status of Contractor Engagement and Project Progress

Name of PIU

Civil works

contract Nature of Civil works

Name of Contrac

tor

Date of Contract

signed

Name of

EMS

Name of CSC Status of Project Progress

Cangyuan PIU

C-SS04

− Description: Cangyuan Guomen No. 2 Elementary School Civil Works

− Scope & Content: The total building area is 31059.05m2, including two student dormitories with area of 3644.0 m2, one teaching building with area of 5627.55 m2, one general building with area of 5075.0 m2, cafeteria and gymnasium with area of 3884.4 m2, security room and garbage room with total area of 80.0 m2.

/ / / /

Not yet mobilized. The new site was confirmed by Cangyuan County Government on June 2, 2020. Environmental due diligence was completed in July 2020. The revised environmental due diligence report was submitted to ADB on early August 2021. Contract award expected to be completed in Q4 2021.

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

19

3.0 INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION AND SUPERVISION

3.1 Institutional Responsibilities for Environmental Management 19. The Lincang Municipal Government (LMG) is the Executive Agency (EA) of the project. As the EA, LMG is responsible for communication with ADB, loan repayment, as well as supervision and guidance of the LPMO and the Project Implementation Units (PIUs) for project implementation in three project counties. Lincang Border Economic Cooperation Zone (LBECZ), Cangyuan Wa County Government (CCG), and Zhenkang County Government (ZCG) are the project implementing agencies. 20. At the Prefecture level, LMG has established a project leading group (PLG), comprising members from concerned government agencies to facilitate the government interagency coordination for the project preparation and implementation. The PLG is headed by the mayor of LMG and with representatives from Lincang Municipal Finance Bureau, Lincang Municipal Development and Reform Commission, and other key bureaus of Lincang municipality. 21. However, LMG has largely delegated this role to the Management Committee of the Lincang Border Economic Cooperation Development Zone (LBECZ) where the majority of the project components are located. A project management office (PMO) has therefore been established within the LBECZ Management Committee, headed by the director, with staff from other units and offices of LBECZ. The PMO will be responsible in providing overall guidance, supervision, coordination, and management support for project preparation and implementation on behalf of LMG. In CCG and ZCG, a PLG has been established, headed by the implementing agency government head, for government interagency coordination and leadership during project preparation and implementation. In each of the implementing agency, a project implementation unit (PIU) has been established for interagency coordination, and management and implementation of its components. For LBECZ, the project PMO will also serve as the PIU for its components. 22. CCG implements the Cangyuan Guomen No. 2 Elementary School subproject, whilst ZCG implements the PRC–Myanmar Friendship Hospital subproject. All other physical subprojects are implemented by LBECZ, which also implements the capacity building component of the Project (as defined as output 4 of the project scope). LPMO is also responsible for engaging specialist domestic service providers such as design institutes needed to implement the project, although each PIU will appoint its own internal environmental monitoring services. At this time, there is one designated person, Environmental Management Coordinator (Mr. Li Hailiang) in the LPMO, responsible for the implementation of EMP and preparation of EMRs. This Environmental Management Coordinator will also be responsible for coordinating the environmental management activities in the PIUs at LBECZ. The environmental management coordinators in the PIUs at CYC & ZKC were not nominated right now. 23. The Project’s institutional structure of environmental management is shown in Figure 3.1.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

20

Figure 3.1 Institutional Structure of Environmental Management

24. Institutional responsibilities for EMP implementation have been covered in the updated EMP. Roles and responsibilities for major tasks assigned to EA, PLG, LPMO, ADB and IA were listed in the table 2-1 of updated EMP.

3.2 Incorporation of Environmental Requirements into Project Contractual Arrangements 25. CUCD has advised the LPMOs and PIUs that the content of the specific EMP documents must be fully incorporated into all bid documents and in the actual contract agreements to be signed with respective parties. It is also of critical importance that the bid prices from potential contractors, CSCs and EMS or certified environmental entity have taken into consideration of EMP requirements and the cost for EMP implementation is fully included in the total contract prices. 26. By the end of September 2021, LPMO has signed nine civil contract packages. The requirements for EMP implementation and specific tasks and mitigation measures were included in the five bid documents.

LPMO

LMG/PLG

LMEEB

ADB

CUCD PIAs and their PIUs

Contractors Monitoring Agencies

Domination

Supervision Companies

Management & Coordination

Cooperation Consultancy & Feedback

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

21

4.0 COMPLIANCE WITH PROJECT COVENANTS RELATING TO ENVIRONMENTAL MANAGEMENT

27. To date, all covenants in the Loan Agreement and Project Agreement have been executed as stipulated, while some are still to be enacted. A list of covenants and compliance status related to the environmental aspect is shown in the following table.

Table 4.1-1 Compliance with Environment Related Project Covenants

Schedule Para No.

Environment Related Specific Covenants

Schedule/Due Date

Status of Compliance

PA

Article II 2.01a

YPG and LMG shall, and shall cause the Project Implementing Agencies to, carry out the Project with due diligence and efficiency, and in conformity with sound applicable technical, financial, business, and development practices and in accordance with the provisions of the PA and the PAM.

Ongoing throughout the project

Being complied with

PA Schedule 1.

Implementation Arrangements: YPG and LMG shall ensure that the Project is implemented in accordance with the detailed arrangements set forth in the PAM. Any subsequent change to the PAM shall become effective only after approval of such change by YPG, LMG and ADB. In the event of any discrepancy between the PAM and this Project Agreement, the provisions of this Project Agreement shall prevail.

Ongoing throughout the project

Being complied with

PA Schedule 2.

Conditions for Award of Contracts:

LMG shall, and shall cause the Project Implementing Agencies and PIUs not to award any works or non-consulting services contract which involves environmental impacts until:

(a) It obtained ADB’s clearance to the final EIA, updated based on the project’s detailed design;

(b) Lincang Environmental Protection Bureau has granted final approval to the EIA, and

(c) LMG has incorporated the relevant provisions from the EMP into the Works or non-consulting services contract.

Before construction commences

Being complied with

PA Schedule 5

Environment:

LMG shall, and shall cause the Project Implementing Agencies and PIUs to, ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the EIA, the EMP, and any corrective or preventative actions (i) set forth in a Safeguards Monitoring Report, or (ii) which are subsequently agreed between ADB on the one part, and YPG and LMG on the other part.

Ongoing throughout the project

complied with to date

PA 10 Safeguards-Related Provisions in Bidding Documents Ongoing until the

In compliance

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

22

Schedule Para No.

Environment Related Specific Covenants

Schedule/Due Date

Status of Compliance

Schedule and Works Contracts

LMG shall ensure, and cause the Project Implementing Agencies and PIUs to ensure, that all bidding documents and contracts for Works contain provisions that require contractors to:

(a) comply with the measures relevant to the contractor set forth in the EIA, the EMP, the RPs and the EMDP (to the extent they concern impacts on the respective affected people under the Environmental Safeguards, the Involuntary Resettlement Safeguards, and the Indigenous Peoples Safeguards during construction), and any corrective or preventative actions set forth in (i) a Safeguards Monitoring Report or (ii) subsequently agreed between ADB and YPG or LMG;

(b) make available a budget for all such environmental and social measures;

(c) provide the Project Implementing Agencies and LMG with a written notice of any unanticipated environmental, or resettlement and social risks or impacts that arise during construction, implementation or operation of the project that were not considered in the EIA, the EMP, the RPs and the EMDP;

(d) adequately record the condition of roads, agricultural land, physical cultural resources and other infrastructure prior to starting to transport materials and construction; and

(e) Reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

completion of procurement

to date

PA Schedule 11

Safeguards Monitoring and Reporting

LMG shall do, or cause the Project Implementing Agencies to do, the following:

(a) submit Safeguards Monitoring Reports to ADB:

(i) in respect of implementation of and compliance with Environmental Safeguards and the EMP, quarterly during construction and the implementation of the Project and the EMP and thereafter annually during operations until the issuance of ADB’s Project completion report unless a longer period is agreed in the EMP; and

(ii) in respect of implementation of and compliance with Involuntary Resettlement Safeguards and Indigenous Peoples Safeguards and of the RPs and the EMDP, semi-annually during the implementation of the Project, the RPs and the REMDP until the issuance of ADB’s Project completion report unless a longer period is agreed in the RPs or EMDP;

and disclose relevant information from such reports to respective affected people under Environmental Safeguards,

Quarterly from January 2020

Semi-annually from January 2020

Being complied with

Being complied with

Will be complied with whenever and wherever requited.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

23

Schedule Para No.

Environment Related Specific Covenants

Schedule/Due Date

Status of Compliance

Involuntary Resettlement Safeguards and Indigenous Peoples Safeguards promptly upon submission;

(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the EIA, the EMP, the RPs and the EMDP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan;

(c) no later than the start of construction, engage qualified and experienced external experts or qualified consulting firms through a selection process and with a TOR acceptable to ADB, to verify information produced through the project monitoring process, and to facilitate the carrying out of any verification activities of those experts and consulting firms; and

(d) report any actual or potential breach of compliance with the measures and requirements set forth in the EMP, the RPs or the RMDP promptly after becoming aware of the breach.

Ongoing throughout the project

Ongoing throughout the project

By December 2019

Ongoing throughout the project

Being complied with

Compliance.

Compliance. The external environmental monitor was mobilized on December 26, 2020.

PA Schedule 13

LMG shall ensure that separate safeguards grievance redress mechanisms acceptable to ADB are established in accordance with the provisions of the EIA, RPs and EMDP at its project management office, within the timeframes specified in the relevant EIA, RPs and EMDP, to consider safeguards complaints.

Note: PA Schedule para 14 defines how such a grievance system is to operate.

Ongoing throughout the project

Being complied with. GRM is in place

PA Schedule 15

YPG and LMG shall, and LMG shall cause the Project Implementing Agencies, PIUs, and contractors and service providers to ensure that the core labor standards and the Borrower’s applicable laws and regulations are complied with during Project implementation. LMG and the Project Implementing Agencies shall include specific provisions in the bidding documents and contracts financed by ADB under the Project requiring that the contractors, among other things: (a) comply with the Borrower’s applicable labor law and regulations and incorporate applicable workplace occupational safety norms; (b) do not use child labor; (c) do not discriminate workers in respect of employment and occupation; (d) do not use forced labor; and (e) disseminate, or engage appropriate service providers to disseminate, information on the risks of sexually transmitted diseases, including HIV/AIDS, to the employees of contractors engaged under the Project and to members of the local communities surrounding the Project area, particularly women.

Ongoing throughout the project

Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

24

Schedule Para No.

Environment Related Specific Covenants

Schedule/Due Date

Status of Compliance

PA Schedule 16

LMG and the Project Implementing Agencies shall strictly monitor compliance with the requirements set forth in paragraph 15 above and provide ADB with regular reports.

Ongoing throughout the project

Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

25

5.0 ENVIRONMENTAL MITIGATION MEASURES IMPLEMENTED IN THIS REPORTING PERIOD

28. There were nine contracts awarded by the end of September 30 2021, and Cangyuan County have not been mobilized yet.

A. China Construction Road & Bridge Co., Ltd. was awarded the contract of C-RD04 (Nanting Bridge and Approach Road); the contract was signed on October 19th 2019, and mobilized on November 13th 2020.

B. Yunnan Road and Bridge Co. Ltd. was awarded the contract of C-RD02 (Qingshuihe No.2 Road); the contract was signed on April 27th 2020, and mobilized on April 30th 2020.

C. Yunnan Road and Bridge Co. Ltd. was awarded the contract of C-RD02-1 (Qingshuihe No.6 Road); the contract was signed on April 22nd 2020, and mobilized on April 25th 2020.

D. China Railway Ninth Bureau Group Co., Ltd. was awarded the contract of C-SS05 (Qingshuihe Guomen No.2 Elementary School Upgrading) subproject. The contract was signed on July 9, 2020, and mobilized on September 22, 2020.

E. Longsheng International Construction Group Co., Ltd. was awarded the contract of C-ICA01 (International Production Capacity Phase I sub-project). The contract was signed on October 16, 2020, and mobilized on October 26, 2020.

F. Yunnan Zhenghao Construction Co., Ltd. was awarded the contract of C-RD01a (Qingshuihe No.1 Road). The contract was signed on March 5, 2021, and mobilized on May 30, 2021.

G. Yunnan Construction First Hydraulic and Hydropower Construction Co., Ltd. was awarded contract C-ENV04 (Qingshui River rehabilitation), with entry on September 1, 2021 and completion expected on February 28, 2023.

H. Hebei Province Second Construction and Engineering Company Limited was awarded contract C-ENV01 (Water Supply), which was signed on 2 September 2021.

I. Guizhou Construction Group Third Construction Engineering Co. was awarded the civil contract C-SS01 (Zhenkang Hospital) on July 7, 2021.

29. Qingshuihe No.2 and No. 6 were completed and accepted during this reporting period. International Capacity Phase I had no construction activity during this period due to the undetermined extent of ramming. The Zhenkang Hospital site involves the relocation of the high voltage corridor, and there is no large-scale construction activity during this reporting period except for local surface clearance at the site. The water supply and river rehabilitation subprojects were mobilized on later September 2021, and no large-scale construction activities have been carried out during this reporting period. The implementation of environmental mitigation measures is focused on Qingshuihe No.1 Road, the Nanting River Bridge, and the Qingshuihe Primary School. The following summarizes the implementation of environmental

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

26

protection mitigation measures for the contract packages under construction during the period and compliance with the EMP of the Environmental Management Plan.

Table 5.1 Summary of Potential Impacts & Implementation of Mitigation Measures

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

A. Pre-construction Phase

Implementation Support

Establish implementation support positions

1. Contract a Loan Implementation Environmental Consultant (LIEC), river ecology specialists, and various sectorial specialists (water and wastewater, solid waste);

2. Contract a tendering Agency to ensure that the provisions of this EMP are included in bidding documents

3. Contract Environmental Monitoring Station for external monitoring of construction and operations Contract Environmental Monitoring Station for external monitoring of construction and operations

1. Being complied with 2. Being complied with 3.In the process of procuring appropriate service provider.

Construction Support

Update EMP

Review EMP to assess if the current mitigation measures need to be updated due to any changes in the final engineering design. For changes in project locations, sites, or other changes that may cause affected people: the PMO will conduct additional environmental assessment and public consultation. The revised environmental assessment reports will be submitted to the PMO, EPB and ADB for approval and disclosure. New or greater environmental impacts or involve additional.

Being complied with. The construction sites of four sub-projects need to change, there is no need for EIA addendum because potential environmental impacts are insignificant. And the EDDR was being prepared. Mitigations in the original EMP were updated by adding the occupational health relating to Covid-19 prevention; meanwhile the environmental monitoring planning was updated by identifying the sensitive receptors of each sub-project.

Contract documents

1. Include clauses referencing this EMP in the terms of reference for bidders for construction contracts.

2. Prepare environmental contract clauses for contractors, especially the EMP and monitoring plan.

1. Being complied with 2. Being complied with

Grievance Redress Mechanism (GRM)

1. Implement the GRM described in EIA/EMP document.

2. Establish complaints recording procedures within PMO.

3. Publicize GRM at all construction sites.

1. Being complied with 2. Being complied with 3. Being complied with; GRM boards were set up at the construction sites of C-RD04, C-RD02 & C-RD02-1

Construction site planning

1. Construction contractor/PIU prepare Site-specific

1. Being complied with; the contractors of C-RD04, C-

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

27

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

environment management plan and monitoring, health and safety plan

2. Contractor to assign onsite environment engineer to be direct contact person for PIU.

3. PIU review and approve contractor SEMP

RD02&C-RD02-1 have prepared the CS-EMP. 2. Being complied with 3. Being complied with

Environmental Protection Training

Provide training on implementation of this EMP to all relevant agencies, especially the PIU, IAs and contractors. Includes training in GRM and environmental protection and monitoring

1. Being complied with

B. Construction Phase

2.1 Water

Domestic wastewater from construction sites

Contractor to provide portable toilets at construction sites. Toilets to be emptied regularly and sewage transported to WWTP

1. Being complied with; the contractor of C-RD04 provide portable toilet at construction site.

Construction wastewater (washing aggregates, pouring / curing concrete, machinery repairs) is managed

Site planning, management and safeguards:

1. Interception of all construction wastewater and site runoff water

2. Sediment from construction wastewater and site runoff water to be separated in sedimentation traps before discharge of water

3. Sediment to be disposed at suitable spoil dumping site

4. Site runoff water containing hazardous and harmful materials (if any) to be treated separately from site runoff.

1. Being complied with 2. Being complied with 3. Being complied with 4. Not applicable or relevant

Handling of hazardous and harmful materials

Site planning, management and safeguards:

1. Storage facilities for fuels, oil, and other hazardous materials within secured areas on impermeable surfaces, and provided with bunds and cleanup installations;

2. Fuel supplier is properly licensed and follows the proper protocol for transferring fuel, and complies with JT 3145-88 (Transportation, Loading and Unloading of

1. Being complied with ; There is no hazardous and harmful material storing at the construction site. 2. Being complied with 3. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

28

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

Dangerous or Harmful Goods); 3. Vehicles and equipment are

properly parked in designated areas to prevent contamination of soil and surface water;

4. Vehicle, machinery, and equipment maintenance and refueling are carried out so that spilled materials do not seep into the soil or into water bodies;

5. Fuel storage and refilling areas are located at least 300 m from stormwater drains, Nanting River and Qingshuihe River;

6. Oil traps for service areas, and parking areas.

4. Being complied with 5. Being complied with 6. Not applicable or relevant

2.2 Air

Generation of dust by construction activities

1. Transport containers and vehicles carrying soil, sand or other fine materials to and from the sites must be covered;

2. Materials storage and stockpile sites are covered or sprayed with water;

3. Water is sprayed on bare earth surfaces at construction sites and access roads twice daily;

4. All roads and tracks used by vehicles of the contractors or any subcontractors or supplier are kept clean and clear of all dust, mud, or extraneous materials dropped by vehicles.

1. Being complied with 2.Being complied with 3. Being complied with 4. Being complied with

Air emission from vehicles and equipment

1. Equipment and machinery is maintained to a high standard to ensure efficient running and fuel-burning;

2. Avoid leaving machinery running or trucks and other vehicles idling when not in use;

3. A regular inspection and certification system for equipment and machinery is required.

1. Being complied with 2.Being complied with 3. Being complied with

Toxicity and air contamination inside building

Use of low or no volatile organic compounds – water based nontoxic etc. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

29

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

2.3 Noise

Noise from vehicles and construction machinery

1. Noise levels from equipment and machinery conform to PRC standard GB12523-2011;

2. Install portable noise shields near sensitive receptors;

3. When work is planned near sensitive receptors, residents will be notified by the PIU and/or contractors and any site-specific concerns or working arrangements addressed;

4. Prohibit noise-generating construction work between 2000 and 0600 hours. v. Avoid minority religious activities or festivals (i.e., no construction allowed within 500 meters of any schools, hospitals.;

5. If construction noise needs to continue into the night, the contractor must first consult with the PIU, ES, and local communities and obtain their agreement.

1. Being complied with 2. Being complied with; the two sensitive receptors were far away from the construction sites. 3. Being complied with 4. Being complied with 5. Being complied with

Noise and vibrations

Selection of construction techniques and machinery to minimize ground disturbance.

Being complied with

2.4 Soil

River bed cleanings

The soil extracted from river channel shall only be reused on-site if it complies with Class II of Soil Environmental Quality Standard (GB15618-1995), which is the equivalent soil quality for the adjoining agricultural lands.

Not being involved yet

Foundation soil Excavations

1. All spoil material will be stacked at a location near designated green belt area or storage areas;

2. Land will be reinstated following completion of construction;

3. Contract clauses specifying careful construction practices.

1. Being complied with 2. Not being involved yet 3. Being complied with

2.5 Soil erosion and stability

Erosion from construction sites

1. Construct interception ditches and drains to prevent runoff entering construction sites, and to divert runoff from sites to existing drainage;

1. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

30

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

2. Limit construction and material handling during periods of rains and high winds;

3. Stabilize all cut slopes, embankments, and other erosion-prone working areas while works are going on;

4. All earthwork disturbance areas shall be stabilized within 30 days after earthworks have ceased at the sites;

5. Preserve existing vegetation where no construction activity is planned.

2.Being complied with 3. Being complied with 4. Being complied with 5. Being complied with

Green Belt establishment

1. On sloping lands, all preparation for plantations must be conducted according to technical specifications of soil and water conservation for sloping land set in Soil and Water Conservation Law of PRC (2010). In particular, soil tillage on terraces must be carried out along contours, keeping any existing vegetation between contour terraces to prevent soil erosion;

2. Geotextile or hessian matting will be laid and pegged over exposed slopes.

1. Being complied with 2. Being complied with

2.6Solid Waste

Domestic waste from construction site

1. Provide appropriate waste storage containers;

2. Trash collection bins are regularly sprayed with pesticides to reduce flies;

3. Wastes are stored away from water bodies and regularly hauled to a suitable landfill or designated dumping site.

1. Being complied with 2.Being complied with 3. Being complied with

Construction wastes causing adverse impacts on surrounding environments

Construction wastes that cannot be reused will be regularly transported off-site for disposal, and not allowed to accumulate on site over long periods.

Being complied with

2.7 Flora and Fauna

Habitat retention

1. Loss of existing native trees and shrubs in embankment construction will be replaced by the

1. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

31

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

same species in landscaping and in habitat re-establishment in embankments.

2. To minimize impacts on existing riverside:

i. prohibit construction activities or use of noise-intensive machinery during fish spawning season (April-June) and migration season (June to September);

ii. prohibit construction activities at night; iii. avoid water pollution from

construction spoils and oil leakage; iv. locate construction camp at least

500-m away from rivers; v. Awareness building and training of

construction workers. In all cases, the poaching or harming of any wildlife by construction workers will be strictly prohibited.

3. At the construction site of the water supply pipeline for WTP, ensure protection of vegetation along river bank.

2. i Not being compiled with ii Being complied with iii Being complied with iv Being complied with v Being complied with 3. Not being involved yet

Invasive species

Prohibit the use of any plant species classified in the PRC as weeds, as defined by the China National Invasive Plant Database (http://www.agripests.cn and by the Ministry of Environment Protection and Chinese Academy of Sciences.

Being complied with

Loss of vegetation and deforestation

Marking of trees, vegetation to be removed prior to clearance, and strict control on clearing activities to ensure minimal clearance. Construction contractor will replant trees to be cut within the subproject premises along green belts.

Being complied with

2.8 Social and Culture

Traffic management – all components

1. A traffic control and operation plan must be prepared by the contractor in consultation with the local traffic management authority prior to any construction the plan will include:

i. Selection of haulage routes to reduce disturbance to regular traffic;

1.Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

32

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

ii. Trucks hauling construction material and waste to be fully covered;

iii. Divert or limit construction traffic at peak traffic hours. Construction traffic at the school site will be avoided during critical periods such as school drop off and pick up times;

iv. project owner to work with local highways authority and traffic police to carry out road maintenance work during the construction process;

v. Construction units to strengthen traffic safety education for vehicle drivers. Training and licensing operators and drivers in the safe operation of specialized vehicles such as forklifts, excavators, trucks, loaders, etc. (including safe loading/unloading, load limits, and other safe operating procedures);

vi. Establishing rights-of-way, site speed limits, vehicle inspection requirements, operating rules and procedures (e.g. prohibiting operation of forklifts with forks in down position), and control of traffic patterns or direction. Construction vehicles on designated routes or locations such as in the crossing of villages, densely populated areas and near sensitive locations (schools, health facilities and other social services) to drive slowly and according to designated speed limits (e.g. 30 km/h).

vii. Restricting the circulation of delivery and private vehicles to defined routes and areas, giving preference to “one-way” circulation, where appropriate。

2.Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

33

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

2. Meanwhile, contractor shall:

i. hire fully trained and experienced operators or drivers for industrial and delivery vehicles for construction activities;

ii. Ensure drivers are in reasonably good medical condition;

iii. Ensuring moving equipment with restricted rear visibility is outfitted with audible back-up alarms.

Work camp health and hygiene

1. The Contractor shall provide Occupational Health and Safety orientation training to all workers and to all new employees, prior to any work assignment, to ensure they are apprised of the basic rules of work at the construction site and of personal protection and preventing injuries to fellow workers. Training shall consist of basic hazard awareness, site specific hazards, safe work practices and emergency procedures for fire, evacuation, and, where applicable, natural disasters. Any site-specific hazard or color coding in use at the construction site shall be thoroughly reviewed as part of the orientation training.

2. Ensure awareness of communicable diseases for the construction work forces and nearby communities. conducting regular information, education and communication (IEC) campaigns addressed to all site staff and labor (including truck drivers and delivery crews) and the immediate local communities concerning project risks and impacts, and appropriate preventative behaviors with respect to STIs, including Covid-19, HIV, malaria, dengue and other vector-borne diseases, vaccine-preventable diseases, tuberculosis and other infectious diseases;

1. Being complied with 2. Being complied with 3. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

34

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

3. Inform workers about where they can go to for diagnosis and treatment of various conditions (camp site medical facilities, Qingshuihe Health Center, nearest hospital), vaccination services, voluntary counseling and treatment. Develop peer educator program for workers and providing work time for peer educator’s activities. Distribute condoms to project workers and educating them regarding use;

4. Ensure worker accommodations meet international health and safety standards to mitigate environmental, health and safety risks. Ensure construction sites, canteens, food, water and food handling, and toilets, are maintained under hygienic conditions as outlined by international standards for worker accommodations;

5. Adequate supplies of potable drinking water shall be provided for workers and at food preparation area;

6. Adequate clean area shall be provided at rest or eating area for workers, away from potential exposure to hazardous substances;

7. Construction site operations comply with PRC State Administration of Worker Safety Laws and Regulations. In collaboration with local health services, construction workers can be screened and treated for infectious diseases such as Covid-19, malaria, dengue, and sexually transmitted infections upon recruitment and before leaving to their home communities. Periodic examinations by occupational health physicians should be available to all construction workers for screening, early

4. Being complied with 5. Being complied with 6. Being complied with 7. Being complied with 8. Being complied with 9. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

35

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

diagnosis and treatment of occupational diseases and key infectious diseases. PRC State Administration of Worker Safety Laws and Regulations.

8. The contractor shall ensure that qualified first-aid can be provided at all times. Appropriately equipped first-aid stations shall be easily accessible throughout the construction site;

9. Eye-washing stations and/or emergency showers shall be provided in close proximity where hazardous chemicals may be used. Where the type of activity being carried out so requires, dedicated and appropriately equipped first-aid room or station shall be provided. First aid stations and rooms shall be equipped with gloves, gowns and masks for protection against direct contact with blood and other body fluids;

10. Where the construction activities are remote, written emergency procedures shall be in place for dealing with cases of trauma or serious illness up to the point at which patient care can be transferred to an appropriate medical facility.

10. Being complied with

Community safety(all sites)

1. At all times during construction, safe and convenient passage must be given for community vehicles, and pedestrians to and from side roads;

2. Place signs around the construction areas to facilitate traffic movement, provide directions to various components of the works, and provide safety advice and warnings;

3. At the end of each day, all sites and equipment will be made secure (through fencing and/or lock-down of equipment) to prevent public access;

1. Being complied with 2. Being complied with 3. Being complied with 4. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

36

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

4. Establish regular engagement and discuss with Qingshuihe Health Center capacity to ensure capacity of the center to provide medical services to the construction workforce and strengthen health staff at the center or at the worker camps medical facilities.

Construction site safety (all sites)

1. All structures on construction site shall be designed and constructed with sufficient integrity for the intended purpose. All buildings or structures of any type shall be structurally safe, provide appropriate protection against local climatic conditions, and have acceptable light and noise conditions;

2. Standard Operating Procedure (SOPs) shall be prepared for emergency evacuation of workers. Evacuation instructions shall be fully communicated to all workers on site. Workers shall be fully trained in evacuation procedures. Drills for SOP shall be undertaken, at an annual basis where appropriate;

3. Construction sites, especially buildings and structures shall be provided with adequate fire detectors, alarm systems and fire-fighting equipment. All fire-fighting equipment shall be maintained in good working order and be readily accessible, and be of adequate and appropriate capacity for use at the location with full consideration to the physical and chemical properties of chemicals or other materials and the number of workers that may be present at the location;

4. Fire and emergency alarm systems shall be both audible and visible;

5. Passageways for pedestrians and vehicles within and in the vicinity of construction activities shall be

1. Being complied with 2. Being complied with 3. Being complied with 4. Being complied with 5. Being complied with 6. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

37

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

segregated to provide for easy, safe and appropriate access with clear signs, including adequate detours for pedestrians;

6. Adequate measures shall be taken to prevent unauthorized access to dangerous areas and areas containing hazardous materials;

7. Training of workers in lifting and materials handling techniques at construction site, including the placement of weight limits above which mechanical assists or two-person lifts are necessary;

8. Train workers to adopt good housekeeping measures to reduce slips and falls, that may result from loose construction materials, excessive debris, liquid spills and uncontrolled use of electrical cords and ropes on the ground – e.g. sorting and placing loose construction materials and debris in established areas away from foot paths; cleaning up excessive debris and liquid spills regularly; locating electrical cords and ropes in common areas and marked corridors; and wearing of slip resistant footwear;

9. To the extent possible, protect all persons and nearby property from construction accidents;

10. Comply with all national and local safety requirements and any other measures necessary to avoid accidents;

11. Provide protective equipment and clothing (goggles, gloves, respirators, dust masks, hard hats, steel-toed boots, Hearing protectors) for construction workers and enforce their use. All PPE are in good condition and properly maintained. All PPE shall be replaced immediately when damaged, worn out or unsuitable

7. Being complied with 8. Being complied with 9. Being complied with 10. Being complied with 11. Being complied with 12. Being complied with 13.Not being involved 14. Being complied with

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

38

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

for the individual worker. All workers shall be fully trained in the proper use of PPE;

12. Ensure sites and machinery are sealed or closed at night and off-limits to the general public;

13. For residents next to construction (especially loud noise), erection of noise barriers, ensure residents are aware of the duration and nature of works, potential hazards, and offer to provide ear plugs/dust masks/other basic safety equipment;

14. During heavy rains / emergencies, suspend all work.

15. Hazardous areas, and/or hazardous material storage areas (e.g. electrical or compressor rooms, installation, hazardous materials storage areas, safety measures and emergency exits) shall be marked and posted appropriately. Signage shall be in accordance with local requirements and/or international best practices and be well known to, and easily understood by workers, visitors and the general public as appropriate.

16. All vessels that may contain substances that are hazardous as a result of the physical, chemical or biological properties shall be labeled as to the contents and hazard, and/or appropriate color coded. Furthermore, where piping system is used at construction site that may contain hazardous substances shall be labeled with the direction of flow and contents of the pipe and/or color coded. Copies of the hazard coding system shall be posted in the vicinity of the hazardous areas and entrance to the construction site where they are likely to come to the attention of emergency

15. Not applicable or relevant 16. Not applicable or relevant 17. Not applicable or relevant 18. Not applicable or relevant.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

39

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

services personnel. 17. Information regarding types

of hazardous materials stored, handled or used at the construction site, including typical maximum inventories and storage locations shall be shared proactively with emergency services and security personnel to expedite emergency response when needed.

18. Where workers may be required to perform work under lone or isolated circumstances, the following procedure shall be implemented:

• A standard Operating Procedure (SOP) shall be prepared and implemented to ensure all PPE and safety measures are in place before the worker starts work;

• The SOP (SOPs) shall establish, at a minimum, verbal contact with the worker at least once every hour, and ensure the worker has a capability for summoning emergency aid;

• If the worker may potentially be exposed to highly toxic or corrosive chemicals, emergency eye-wash and shower facilities shall be equipped with audible and visible alarms to summon aid whenever the eye-wash or showers is activated by the worker and without intervention by the worker.

Construction site safety (pipe-laying)

Trenches will be dug, pipes laid, and the trenches closed, in the same operation. This will ensure that open trenches are not left over an extended period to pose a safety risk or to erode and cave-in.

Not applicable at this time

Loss of power Advance notice to the public about Not applicable at this time

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

40

Subject Potential Impact Mitigation Measures Implementation Status &

Compliance with EMP

supply to the local community when distribution lines crossing the new subprojects are switched off

the time and the duration of the utility disruption. Restore the utilities immediately to overcome public inconvenience

Cultural, physical and natural heritage protection

If a chance find or a cultural artifact is unearthed, stop work and immediately report the matter to the IAs, PMO and local Cultural Relics Preservation Bureau for guidance on next steps.

Noted – not applicable at this time.

2.9 Capacity Building

Improve standards of implementation and monitoring

Training of PMO Being complied with

2.10 Unexpected environmental impacts

If unexpected environmental impacts occur during project construction phase, immediately inform the PMO; assess the impacts; and update the EMP.

Noted – not applicable at this time

5.1 C-RD04 Nanting River Bridge and Access Roads 30. During the construction period, the contractor has carefully implemented the mitigation measures proposed in the EIA phase, such as. Temporary retaining facilities are set up on the side slopes; the amount of production

wastewater generated during construction is small and is used for dust sprinkling after sedimentation and does not flow directly into the river; construction waste and soil are piled and set up retaining walls, etc., effectively reducing the impact of road construction on water bodies along the road.

The construction camp is rented the former highway department house, and mobile toilets were purchased on site and cleaned regularly.

Construction waste is collected separately and reused as possible; appropriate waste storage containers are provided, and construction waste is regularly transported off-site for disposal.

Trash bins are set up at construction sites and cleaned regularly. To prevent the breeding of flies and mosquitoes during the high temperature season, spraying treatment is used.

Construction site construction interception ditches and drainage ditches to prevent runoff from entering the construction site; dust nets to cover all side slopes to prevent mudslides and landslides; construction spoils to be disposed of in designated locations to avoid rainwater washout.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

41

The construction area is far away from residential areas, and construction is prohibited at night. Noise-reducing shelters are set up at construction sites to reduce noise dispersion; radio intercoms are used for on-site communication.

Hazardous materials are stored in ventilated storage room, strictly isolated from fire sources and power sources, and equipped with fire extinguishing equipment.

No vehicles are allowed to park on the construction roadway during construction. All vehicles on site are restricted to the speed limit as required by the signs.

Organize regular safety meetings for work teams. All workers are licensed to work; safety technical briefing and necessary protection knowledge training are given to new staff, and the necessary safety belts, protective glasses, protective gloves, protective masks, etc. are provided during construction.

Emergency organization and emergency plan was developed, trains on electric shock on injury, mechanical injury, fall from height, etc., were organized and emergency medical rescue materials were provided on site.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

42

Figure 5-1: Construction site photo of C-RD04 (Nanting River Bridge)

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

43

5.2 C-SS05 Qingshuihe Guomen No.2 Elementary School

Enclosed construction, full-time gate management, entry and exit personnel registration, temperature measurement, health code.

Covering of materials temporarily not in use

Temporary toilets at construction sites

Safety construction information board

sprinkle daily depending on weather conditions to keep the site clean and sanitary.

Figure 5.2: Construction Site Photos for C-SS05

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

44

5.3 C-RD01a Qingshuihe No.1 Road

Drainage ditch

Three-stage sedimentation tank

Stacking of construction waste

Domestic garbage cans

Grass spreading on side slopes to prevent erosion

Regular safety meeting of the team

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

45

Site sweeping Emergency medical response system Figure 5.3: Construction site plan for C-RD01a

5.5 COVID-19 Risk Prevention

31. As of October 31, 2021, there are 125,979 cumulative confirmed cases and 2,733 existing confirmed cases nationwide. 1,563 cumulative confirmed cases in Yunnan Province, of which 1,164 are imported from abroad, and 91 existing confirmed cases, including 86 imported from abroad. In Lincang City, there is one cumulative confirmed case, which was cured in February 2020. There were no new confirmed cases in Lincang during this reporting period. On August 20, August 21-22, and September 3 2021, the Gengma Autonomous County Response to the Epidemic Leading Group Command organized full nucleic acid testing of key prevention and control areas, including seven border villages in Mengding Township, and all the test results were negative.

32. In September 2020, the loan implementation environmental consultant assisted the Lincang City Project Office in developing a health and safety plan for responding to the New Crown epidemic as a supplementary document to the environmental management plan. On 13 August 2021, the Lincang City Leading Group Command for Response to the Epidemic issued Announcement No. 8 on further improving the regular prevention and control of the New Crown pneumonia epidemic, insisting on the principle of no travel to the border 3 counties (Zhenkang County, Gengma Autonomous County, Cangyuan Autonomous County), and the principle that people in the border 3 counties should not go out unless necessary, and that those who do need to enter or leave the border 3 counties should hold a certificate of consent to enter (leave) from the border county epidemic prevention and control command and provide proof of a valid negative nucleic acid test within 72 hours, as well as check the Yunnan Health Code.

33. The construction units have taken a number of measures on site to strengthen the prevention and control of the epidemic on site. Prepare sufficient medical masks, stock up on disinfectant and know how to prepare and

use it, and ensure that other epidemic prevention supplies are in place.

Conduct disinfection of the construction site, living areas, office areas, machinery and equipment and take adequate house-keeping practices.

Workers were provided with information on the prevention and control of the epidemic, disseminated knowledge on pneumonia prevention, and educated to guide them to pay attention to personal hygiene, wash their hands regularly and wear masks.

Closed management of construction sites, strict implementation of the real-name system, registration and verification of real names entering and leaving the sites. Body temperature testing points are set up at the entrances and exits of construction sites, living areas and office areas, and all personnel must wear masks and have their body temperature tested before entering.

All vehicles entering the site are registered. When external vehicles such as those distributing materials and supplies and hauling spoil enter the construction site, body

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

46

temperature must be taken and masks worn by the personnel on board, and goods, materials and waste are arranged by the construction unit to be received and unloaded by the personnel on site.

Cooking utensils and tableware should be cleaned and disinfected in a timely manner, and a system of meal sharing and staggered meal times should be implemented. At the same time, construction workers should be provided with the necessary cleaning facilities and hand-washing liquid for washing before meals to ensure food safety.

Registration of access to construction sites (Qingshuihe No.1 Road)

Disinfection of office areas (Qingshuihe No.1 Road)

Site entry and exit personnel temperature checking and r (river rehabilitation)

Epidemic prevention substances (river rehabilitation)

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

47

Site entrants and exits were measured for temperature, registered, scanned and workers were urged to implement personal safety measures. (Qingshuihe Guomen Elementary School)

Temperature checking point (Nanting River Bridge)

Visitor Registration Form (Nanting River Bridge)

Figure 5.5: COVID-19 risk prevention on construction site

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

48

6.0 SUMMARY OF ENVIRONMENTAL MONITORING

6.1 Environment Monitoring Plan and Responsibilities 34. The environmental monitoring plan required by ADB and specified in the EIA for this project is summarized in table 3-2, 3-3, 3-4, 3-5, 3-6, 3-7 and table 3-8 in the updated EMP, covering various stages of project progress, including pre-construction and design stage, construction stage and operation stage respectively, that are to be carried out by LPMO, the contractors, the CSCs, and EMA. 35. Baseline monitoring prior to construction. Local Design Institute was retained to conduct the existing environmental monitoring during pre-construction and design stage according to the requirement of the EIA. The responsibility was to monitor the quality of water, air, noise and soil at each constructive site for one time in order to gain baseline information. A good understanding of the background information of the constructive sites will be achieved from the monitoring results. The LPMO has engaged a licenced monitoring agency and conducted baseline monitoring in the middle of June 2020. The monitoring results were presented in the 3rd quarterly environmental monitoring report.

36. External environmental monitoring. According to the ADB EIA requirements, during the construction period, the LMP shall hire an external monitoring agency to conduct quarterly impact monitoring on each construction site to evaluate the implementation effectiveness of the environmental management plan. During the reporting period, the environmental consultants and biodiversity consultants of the consulting company updated the external environmental monitoring and biodiversity external monitoring plan during the construction period according to the project site conditions. For details, see Table 3-5 and Table 3-6 in the updated EMP report. The external environmental monitoring agency was mobilized on December 26, 2020 and conducted the 2nd quarterly monitoring in May 2021 and the 3rd monitoring in August 2021. The 3rd quarter monitoring results for 2021 are presented in Section 6.2.

37. Internal Environmental Monitoring by the contractors for construction phase. Monitoring of the quality of water, air, noise and soil during the construction period is a responsibility of the contractor which is defined in the EIA. The construction supervision company (CSC) shall carry out visual inspections at the construction site, including daily, weekly, monthly and quarterly observations, such as weekly inspections of dust reduction measures (sprinkling, transportation means coverage, etc.), maintenance of vehicles and construction equipment, construction waste management; sanitation and safety status, clean water availability and emergency response plan; quarterly inspection of slope stability, surface soil stacking and restoration of construction sites, borrow pits compensatory planting and vegetation restoration, leakage disposal sites and construction sites; random inspection of the intensity of soil erosion and vegetation reconstruction after heavy rains. As of the end of June 2021, Yunnan Lutong Construction Supervision Consulting Co., Ltd. is responsible for the environmental supervision of the C-RD04 project construction site, and Yunnan Supervisory Association Consulting Co., Ltd. is responsible for the environmental supervision of C-RD01a,

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

49

C-RD02 and C-RD02-1. Kunming Construction Consulting Management Co., Ltd. is responsible for the supervision of C-SS05 Qingshuihe Guomen Primary School Upgrading and C-SS01 Zhenkang Hospital. Yunnan Engineering Construction Supervision Co., Ltd. is responsible for C-ENV01 Water Supply subproject and C-ENV04 River Rehabilitation subproject. 38. Environmental Monitoring Plan for operation phase. The O&M operator and PMO were retained to monitor the quality of water, air, noise and soil during the operation period which is defined in the EIA. The monitoring parameters, monitoring frequency and sampling locations were updated in table 3-7 in the updated EMP. This part will be implemented one time during commissioning which will be supervised by PIU and LCEEB. 39. Environmental Monitoring Performed by Construction Supervision Company. The responsibilities of CSCs at the constructive sites is to supervise the contractor’s EMP implementation performance, prepare the contractor’s environmental management performance section in monthly project progress reports, and ensure occupational health and safety management at work sites. The key points of specific monitoring description for CSCs was listed in table 3-4 in the updated EMP. CSCs need to do daily, weekly, monthly, quarterly visual inspection and recording. Yunnan Lutong Construction Consulting& Supervising Company is responsible for the C-RD04. Yunnan Supervisory Association Consulting Co. Ltd is the engaged for C-RD01a, C-RD02 and C-RD02-1. Kunming Construction Consulting and Management company is engaged for construction supervision of C-SS05. 40. Environmental Reporting Plan. Environmental reporting plan was listed in table 3-9 in the updated EMP. During this reporting period, the monthly monitoring reports for July to September 2021 were submitted to PIU in LBECZ by the CSCs of C-RD04, C-RD01a, C-SS05 and C-ENV04. C-ICA01, C-RD02 and C-RD02-1 have no construction activities during this reporting period so the CSCs did not prepare environmental monitoring report. C-RD02-1, C-RD02-1, and C-ICA01 had no construction activity during this reporting period and did not prepare monthly environmental Progress Report.C-SS01 Zhenkang Hospital has no intensive construction activities and no Supervisory Environmental Report has been prepared for this reporting period as the high voltage corridor has not yet been relocated.C-ENV01 Water Supply Project entered the site at the end of September and no Supervisory Environmental Report has been submitted for this reporting period.

6.2 Environmental Monitoring Results 41. Noise. Yunnan Kunfa Environmental Technology Co., Ltd. monitored the noise around the project construction site and sensitive points from 11 August 2021 to 12 August 2021. The daytime and nighttime noise on two consecutive days could meet the Sound Environment Quality Standard (GB3096-2008) Class 2 and Class 4a standards. The impact of the project construction on the surrounding residents is not significant. It is recommended that the contractors continue to strengthen the management of construction vehicles, reasonably configure construction machinery activities and reduce the pollution of sudden noise. Table 6.1-1: Noise monitoring results at environmentally sensitive sites in August 2021 (unit: dB(A))

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

50

Subproject

Location Monitoring date

Monitoring Time

(Hours: minutes)

Daytime

Monitoring Time

(Hours: minutes)

Nighttime

Qingshuihe No.1 Road C-RD01a

Nanpahe Shantuzhai

Village

2021.08.13 09:10 47.2 22:47 39.4

2021.08.14 09:14 46.6 22:58 38.9

Nanting River Bridge and

Access Road C-RD04

Mangka Border Checkpoint

2021.08.13 10:48 52.1 00:10 38.7

2021.08.14 10:53 53.0 00:20 37.9

Ban Gui village 2021.08.13 08:34 50.0 22:13 39.5

2021.08.14 08:39 49.2 22:21 39.0

Qingshuihe Guomen

Elementary School (C-SS05)

Qingshuihe Customs

Dormitory

2021.08.11 09:20 54.1 22:00 42.4

2021.08.12 09:00 54.5 22:00 43.0

Qingshuihe Village Council

2021.08.11 09:35 54.4 22:14 40.0

2021.08.12 09:13 54.9 22:15 39.4

Qingshuihe Crossing Service

Company Complex

2021.08.11 09:50 53.7 22:28 39.4

2021.08.12 09:27 54.1 22:29 39.8

Villagers' homes east of

Qingshuihe Primary School

2021.08.11 10:04 54.6 22:42 38.9

2021.08.12 09:42 55.2 22:43 39.1

Qingshuihe Primary School

2021.08.11 10:18 55.2 22:57 37.4

2021.08.12 09:56 56.0 22:59 38.0

Little Sun Kindergarten

2021.08.11 10:52 46.7 23:11 37.2

2021.08.12 10:28 47.2 23:13 37.7

Applicable standards 60 50

Table 6.1-1: Construction site noise monitoring results for August 2021 (in dB(A))

Location Monitoring date

Monitoring Time

(Hours: minutes)

Daytime

Monitoring Time

(Hours: minutes)

Nighttime

East of the site boundary of the Nanting River Bridge and

Access Road

2021.08.13 11:22 54.2 00:35 37.4

2021.08.14 11:44 53.9 00:51 37.8

South of the site boundary of the 2021.08.13 11:47 53.7 01:03 38.2

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

51

Nanting River Bridge and Access Road 2021.08.14 12:10 53.2 01:16 37.6

West of the site boundary of the Nanting River Bridge and

Access Road

2021.08.13 12:13 55.0 01:27 36.9

2021.08.14 12:37 54.8 01:40 37.7

North of the site boundary of the Nanting River Bridge and

Access Road

2021.08.13 12:40 55.4 01:52 37.1

2021.08.14 13:03 55.1 02:06 36.8

Applicable standards 70 50

42. Air quality. According to "Ambient Air Quality Standards" (GB3095-2012), the 24-hour average concentration secondary standards of TSP, PM10, PM2.5, NOx, SO2 and hourly CO are 300 ug/m3, 150 ug/ m3, 75 ug/ m3, 80 ug/ m3, 150 ug/ m3 and 10 mg/ m3.

43. From the monitoring data of Yunnan Kunfa Environmental Technology Co., Ltd. from August 10, 2021 to August 12, 2021 and from August 14, 2021 to August 16, 2021, the concentration of pollutants at each monitoring point meets the Ambient Air Quality Standard (GB3095-2012) Class II standard. Road construction dust has a certain impact on the air environment along the route, and the air pollution mitigation measures proposed in the EIA should be implemented seriously, and the site should be sprinkled with water to reduce dust and covered with tarpaulins and other measures.

Table 6.2-1 Atmospheric TSP, PM 10, and PM 2.5Monitoring Results for August 2021

Subproject Location Date of sampling

Monitoring results

TSP

(µg/m3)

PM 10

(µg/m3)

PM 2.5

(µg/m3)

Qingshuihe No.1 Road C-RD01a

Nanpahe, Shantuzhai Village

2021.08.14 85 47 31

2021.08.15 98 54 23

2021.08.16 94 56 29

Nanting River

Bridge and Access Road C-RD04

Mangka Checkpoint

2021.08.14 149 125 24

2021.08.15 183 130 26

2021.08.16 192 140 29

Ban Gui village

2021.08.14 149 100 25

2021.08.15 172 90 27

2021.08.16 185 80 29

Qingshuihe Guomen

Elementary School C-

SS05

Qingshuihe Customs Dormitory

2021.08.10 149 59 24

2021.08.11 170 63 29

2021.08.12 181 61 27

Qingshuihe Village Council 2021.08.10 167 53 29

2021.08.11 167 50 30

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

52

2021.08.12 160 57 29

Qingshuihe Crossing Service Company Complex

2021.08.10 181 55 30

2021.08.11 154 56 30

2021.08.12 167 61 29

Villagers' homes east of Qingshuihe Primary School

2021.08.10 174 50 32

2021.08.11 160 46 31

2021.08.12 154 51 34

Qingshuihe Primary School

2021.08.10 160 57 32

2021.08.11 167 53 33

2021.08.12 142 53 34

Applicable Standard 300 150 75

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

53

Table 6.2-1 Monitoring results of atmospheric nitrogen oxides and sulfur dioxide in August 2021 Unit: µg/m 3

Subproject Location Date of sampling

Sampling period

Testing Items Implementation standards

NOx SO2 NOx SO2

Qingshuihe No.1 Road C-RD01a

Nanpahe, Shantuzhai

Village

2021.08.14

02:00~03:00 17 14 250 500

08:00~09:00 21 17 250 500

14:00~15:00 27 24 250 500

20:00~21:00 23 20 250 500

2021.08.15

02:00~03:00 15 13 250 500

08:00~09:00 19 18 250 500

14:00~15:00 26 23 250 500

20:00~21:00 23 21 250 500

2021.08.16

02:00~03:00 19 15 250 500

08:00~09:00 21 17 250 500

14:00~15:00 25 24 250 500

20:00~21:00 24 21 250 500

Nanting River

Bridge and Access Road C-RD04

Mangka Checkpoint

2021.08.14

02:00~03:00 16 21 250 500

08:00~09:00 22 25 250 500

14:00~15:00 30 29 250 500

20:00~21:00 21 27 250 500

2021.08.15

02:00~03:00 17 22 250 500

08:00~09:00 24 25 250 500

14:00~15:00 33 30 250 500

20:00~21:00 26 28 250 500

2021.08.16

02:00~03:00 15 20 250 500

08:00~09:00 19 23 250 500

14:00~15:00 26 27 250 500

20:00~21:00 23 24 250 500

Ban Gui village

2021.08.14

02:00~03:00 15 17 250 500

08:00~09:00 19 21 250 500

14:00~15:00 26 26 250 500

20:00~21:00 23 23 250 500

2021.08.15 02:00~03:00 15 18 250 500

08:00~09:00 19 22 250 500

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

54

14:00~15:00 26 26 250 500

20:00~21:00 21 23 250 500

2021.08.16

02:00~03:00 17 16 250 500

08:00~09:00 19 20 250 500

14:00~15:00 25 24 250 500

20:00~21:00 22 22 250 500

Qingshuihe Guomen

Elementary School (C-

SS05)

Qing Shui He Customs Dormitory

2021.08.10

02:00~03:00 22 16 250 500

08:00~09:00 28 29 250 500

14:00~15:00 33 25 250 500

20:00~21:00 30 22 250 500

2021.08.11

02:00~03:00 22 14 250 500

08:00~09:00 28 18 250 500

14:00~15:00 32 27 250 500

20:00~21:00 29 21 250 500

2021.08.12

02:00~03:00 22 12 250 500

08:00~09:00 27 18 250 500

14:00~15:00 36 24 250 500

20:00~21:00 31 21 250 500

Qingshuihe Village Council

2021.08.10

02:00~03:00 24 12 250 500

08:00~09:00 27 17 250 500

14:00~15:00 34 22 250 500

20:00~21:00 30 19 250 500

2021.08.11

02:00~03:00 20 13 250 500

08:00~09:00 26 17 250 500

14:00~15:00 33 23 250 500

20:00~21:00 31 21 250 500

2021.08.12

02:00~03:00 25 15 250 500

08:00~09:00 28 18 250 500

14:00~15:00 36 24 250 500

20:00~21:00 31 21 250 500

Qingshuihe Crossing Service

Company Complex

2021.08.10

02:00~03:00 21 12 250 500

08:00~09:00 25 16 250 500

14:00~15:00 29 22 250 500

20:00~21:00 27 20 250 500

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

55

2021.08.11

02:00~03:00 19 14 250 500

08:00~09:00 24 18 250 500

14:00~15:00 30 24 250 500

20:00~21:00 26 21 250 500

2021.08.12

02:00~03:00 23 15 250 500

08:00~09:00 27 19 250 500

14:00~15:00 34 25 250 500

20:00~21:00 23 22 250 500

Villagers' homes east

of Qingshuihe

Primary School

2021.08.10

02:00~03:00 21 14 250 500

08:00~09:00 25 17 250 500

14:00~15:00 32 25 250 500

20:00~21:00 27 22 250 500

2021.08.11

02:00~03:00 21 14 250 500

08:00~09:00 26 18 250 500

14:00~15:00 33 27 250 500

20:00~21:00 28 22 250 500

2021.08.12

02:00~03:00 28 16 250 500

08:00~09:00 28 19 250 500

14:00~15:00 34 25 250 500

20:00~21:00 31 23 250 500

Qingshuihe Primary School

2021.08.10

02:00~03:00 22 12 250 500

08:00~09:00 26 17 250 500

14:00~15:00 32 23 250 500

20:00~21:00 28 20 250 500

2021.08.11

02:00~03:00 18 16 250 500

08:00~09:00 24 21 250 500

14:00~15:00 30 27 250 500

20:00~21:00 28 24 250 500

2021.08.12

02:00~03:00 22 13 250 500

08:00~09:00 27 18 250 500

14:00~15:00 34 25 250 500

20:00~21:00 30 22 250 500

Table 6.2-3 Atmospheric carbon monoxide monitoring results (Unit: mg/m 3)

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

56

Report number/item

title Location Date of

sampling Sampling

period carbon

monoxide Applicable standards

Qingshuihe No.1 C-RD01a

Nanpahe, Shantuzhai

Village

2021.08.14

02:00 <0.3 10

08:00 0.375 10

14:00 <0.3 10

20:00 <0.3 10

2021.08.15

02:00 <0.3 10

08:00 <0.3 10

14:00 <0.3 10

20:00 <0.3 10

2021.08.16

02:00 <0.3 10

08:00 <0.3 10

14:00 <0.3 10

20:00 <0.3 10

Nanting River Bridge and

Access Road C-RD04

Mangka Checkpoint

2021.08.14

02:50 <0.3 10

08:51 0.750 10

14:52 0.500 10

20:51 <0.3 10

2021.08.15

02:50 <0.3 10

08:49 0.875 10

14:52 0.625 10

20:53 <0.3 10

2021.08.16

02:49 <0.3 10

08:51 0.500 10

14:53 <0.3 10

20:51 <0.3 10

Ban Gui village

2021.08.14

02:26 <0.3 10

08:26 0.500 10

14:27 <0.3 10

20:28 <0.3 10

2021.08.15

02:25 <0.3 10

08:25 0.625 10

14:26 <0.3 10

20:27 <0.3 10

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

57

2021.08.16

02:25 <0.3 10

02:26 0.500 10

02:27 0.375 10

02:27 <0.3 10

Qingshuihe Guomen

Elementary School C-SS05

Qing Shui He Customs

Dormitory

2021.08.10

02:00 <0.3 10

08:00 0.875 10

14:00 0.625 10

20:00 <0.3 10

2021.08.11

02:01 <0.3 10

08:00 0.750 10

14:00 0.500 10

20:00 <0.3 10

2021.08.12

02:00 <0.3 10

08:01 0.875 10

14:00 0.750 10

20:00 <0.3 10

Qingshuihe Village Council

2021.08.10

02:05 <0.3 10

08:04 0.625 10

14:06 0.500 10

20:05 <0.3 10

2021.08.11

02:06 <0.3 10

08:05 0.625 10

14:05 0.375 10

20:04 <0.3 10

2021.08.12

02:05 <0.3 10

08:06 0.750 10

14:05 0.625 10

20:05 <0.3 10

Qingshuihe Crossing Service

Company Complex

2021.08.10

02:10 <0.3 10

08:09 0.750 10

14:11 0.500 10

20:10 <0.3 10

2021.08.11 02:11 <0.3 10

08:10 0.625 10

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

58

14:10 0.375 10

20:09 <0.3 10

2021.08.12

02:10 <0.3 10

08:11 0.750 10

14:10 0.500 10

20:10 <0.3 10

Villagers' homes east of Qingshuihe

Primary School

2021.08.10

02:17 <0.3 10

08:16 0.625 10

14:18 <0.3 10

20:17 <0.3 10

2021.08.11

02:18 <0.3 10

08:17 0.625 10

14:17 <0.3 10

20:16 <0.3 10

2021.08.12

02:17 <0.3 10

08:18 0.875 10

14:17 <0.3 10

20:17 <0.3 10

Qingshuihe Primary School

2021.08.10

02:23 <0.3 10

08:21 0.375 10

14:23 <0.3 10

20:22 <0.3 10

2021.08.11

02:24 <0.3 10

08:25 <0.3 10

14:23 <0.3 10

20:22 <0.3 10

2021.08.12

02:25 <0.3 10

08:25 0.500 10

14:24 <0.3 10

20:24 <0.3 10

45. Surface Water Quality. The monitoring points for surface water include 100 m upstream of the C-RD04 construction bridge section (control section) and 500 m downstream of the C-RD04 construction bridge section. From the monitoring data of Yunnan Kunfa Environmental Technology Co., Ltd. for three consecutive days from August 13 to August 15, 2021, the monitoring data of both upstream and downstream of the C-RD04 construction bridge

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

59

section of the Nanting River met the Class III standard of the Environmental Quality Standard for Surface Water (GB3838-2002) except for dissolved oxygen, and the exceedance of dissolved oxygen was not obvious. The main reason for the exceedance was due to the high temperature on the monitoring day.

Table 6.3: Surface water monitoring results for August 2021

Detection points 100m upstream of the C-RD04

construction bridge section in the Nanting River

500m upstream of the C-RD04 construction bridge section in the Nanting

River

Class III

Date of sampling 2021.08.13 2021.08.14 2021.08.15 2021.08.13 2021.08.14 2021.08.15

pH (dimensionless) 7.14 7.16 7.20 7.17 7.15 7.18 6 to 9

Dissolved oxygen (mg/L) 4.02 4.10 4.08 4.06 4.11 4.06 ≥5

Electrical conductivity

(µS/cm) 207 210 208 207 205 209 /

Ammonia nitrogen (mg/L) 0.219 0.230 0.265 0.298 0.320 0.285 ≤1.0

Five-day biochemical

oxygen demand (mg/L)

3.1 3.3 3.0 3.8 3.7 3.4 ≤4

Chemical oxygen demand (mg/L) 17 15 16 18 19 18 ≤20

Petroleum (mg/L) 0.02 0.02 0.02 0.03 0.03 0.03 ≤0.05 Animal and

vegetable oils (mg/L)

0.14 0.10 0.14 0.27 0.22 0.22 /

Suspended matter (mg/L) 812 836 856 988 960 987 /

Lead (mg/L) <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 ≤0.05

6.3 Ecological monitoring 46. In September 2021, Yunnan Kunfa Environmental Technology Co., Ltd. organized ecological experts to conduct the third quarter ecological monitoring. The survey used several methods such as site survey, data collection, consultation with relevant departments and interviews with local residents. As the sub-projects involved in ecological monitoring were under construction at the time of the survey, only the Nanting River Bridge was under construction and the Qingshui River Rehabilitation subproject has design document, so this survey mainly conducted a detailed survey of the construction area of the Nanting River Bridge and the Qingshui River rehabilitation area, and a baseline survey for the remaining sub-projects. The main findings of the ecological survey are as follows.

(1) Flora: The natural vegetation within the construction area of the Nanting River Bridge consists of seasonal rainforests, oyster forests, and shrubs and grasses. The natural vegetation distributed within the construction area of the Qingshui River rehabilitation subproject is mainly sparse shrubby grasses.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

60

A total of 114 families, 382 genera and 612 species of terrestrial vascular plants were identified in and around the construction area of Nanting River Bridge and Qingshui River rehabilitation, including: ferns, 17 families, 23 genera and 32 species (according to the Qin Renchang 1978 system); gymnosperms, 3 families, 4 genera and 5 species (according to the Zheng Wanjun system); angiosperms, 94 families, 355 genera and 575 species (according to the Hachinsong system). One Tetrameles nudiflora is distributed along the right bank of the downstream haul road in the construction area of the Nanting River Bridge, which is a national Grade II protected plant. According to the field monitoring, from January 2021 to April 2021, the construction of the Nanting River Bridge did not take up any over-extended area, the plant species surveyed remained unchanged, and the construction did not affect the plant resources and plant species. However, a Tetrameles nudiflora tree along the downstream transport road on the right bank has not been specially protected and is likely to be damaged by side slope runoff during the rainy season. It is recommended that the Tetrameles nudiflora tree be protected.

Figure 6-1No special protection for the protected tree beside the construction road

(2) Terrestrial vertebrates: According to the monitoring, 101 species, belonging to 21 orders, 48 families and 79 genera, have been investigated in and around the construction area of Nanting River Bridge and Qingshui River rehabilitation area. There are 8 species of national protected animals, namely Tylototriton verrucoosus, Milvus migrans, Falco tinnunculus, Accipiter nisus, Glaucidium cuculoides, Centropus sinensis, Felis cat, Glaucidium cuculoides, and Glaucidium cuculoides. Centropus sinensis, Felis bengalensis, and Prionodon pardicolor. based on comparative monitoring, the species of terrestrial vertebrates did not change during the construction of the Nanting River Bridge. With the increase in construction workers and human activity, the number of rodents, especially small rodents, in the survey area has increased; the number of the four protected raptor species has increased due to the increase in the number of rodent small rodents. The number of protected birds has also increased.

(3) Fish: According to the monitoring, 40 species of fish were surveyed in the construction area of the Nanting River Bridge sub-project, belonging to 28 genera in 11 families and 5 orders. The composition of fish species in the construction area did not change significantly from the

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

61

second quarter survey, and the number of fish caught in the river increased due to the flood season. Two orders, three families, five genera and five species of fish were found in the Qingshui River rehabilitation area. All were small fish common to the Nanting River basin.

(4) The Qingshui River water system management project occupies mainly rubber plantations, and the forest land occupied is mainly artificial teak forest, and no natural forest is involved. The occupation of the project will reduce the area of sparse shrubs and grasses, but the sparse shrubs and grasses are widely distributed around the project area, so it can be considered that the impact of the Qing Shui particular River system management project on the area and function of terrestrial vegetation is relatively small. The plant species selected for the plant design proposed in the preliminary design are relatively single, and gerbera (Autumn Ying Cosmos bipinnata) is an exotic species, and the project area is suitable for its growth, and has been listed as an invasive alien species, so it is recommended to use native species in order to protect the local terrestrial ecological environment. February orchid as a flower is an excellent landscape plant, but under the annual temperature conditions of the project construction area, it is extremely difficult to vernalize and bloom, and it is a one-year-old herbaceous plant, so it is difficult to carry out subsequent management and care, so it is recommended to use other species.

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

62

7.0 GRIEVANCE REDRESS MECHANISM AND IMPLEMENTATION

47. Grievance Redress Mechanism (GRM) has been established at PMO level. The GRM provided specific guidance and procedure in handling complaints from individuals living nearby the construction sites, groups or institutes influenced by the construction activities. Figure 7.1-1 illustrates GRM five steps and timeframe. 48. The Project Public Complaint Units (PPCU) was established in the PIU in LBECZ and GRM was developed to handle complaints from individuals, groups or institutes influenced by the construction activities on June 1st 2020. Cai Shengquan (菜胜泉) was nominated as the team leader in PPCU, and three members, Li Hailiang (李海量), Wu Peijun (吴沛军) and Bai Guangneng (白光能), were nominated. The contact information including name, phone number, address, and email was published to the public through website of LBECZ ( http://www.lincang.gov.cn/lcsrmzf/lcbjjjhzqglwyh/tztg38/529346/index.html see Figure 7.1-2). 49. The four contractors of C-RD04, C-RD02 & C-RD02-1 and C-SS05 set up GRM boards at the construction sites respectively; and the procedure of GRM and the contact information of PPCU was disclosed to the public (see Figure 7.1-3). C-RD01a has set up a public notice board, but it focuses more on the payment of workers and does not contain an environmental grievance channel. C-RD01a, C-SS01, C-ENV01, C-ENV04 and C-ICA01 will set up a special notice board for environmental grievance mechanism as required. 50. There has been no complaint received by the PPCUs and contractors in LBECZ since GRM established in Lingcang.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

63

Figure 7.1-1 Environmental Grievance Redress Mechanisms

(Source: EIA)

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

64

Figure 7.1-2 GRM disclosure through website

C-RD02

C-RD02-1

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

65

C-SS05

C-RD04

C-RD01a

Figure 7.1-3 GRM Boards at construction site

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

66

8.0 INSTITUTIONAL STRENGTHENING AND TRAINING

51. On August 16, 2021, ADB organized an online environmental safeguards training for ADB loan projects under implementation. The training was attended by environmental-related staff from the Lincolnshire Project Office. Detailed training on the implementation of the environmental management plan is planned to be organized by contractors, supervisors, project offices and implementation units of all subprojects under construction on October 19, 2021.

Figure 8-1: ADB Environmental Safeguards Policy Training

52. In addition, the contractor has organized several safety education sessions during the daily work.

Subproject Date Subproject

Number of people trained

Photos

Nanting River Bridge and Access

Road C-RD04

2021.9.21 Safety education 7

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

67

2021.8.10 Fire

extinguisher operation procedure

7

Qingshui River

Rehabilitation(C-ENV04)

September 2021

Safety training 5

Qingshuihe No.1 Road(C-RD01a)

15 August 2021

Safety training 8

Qingshuihe Guomen Elementary School

(C-SS05)

July 2021 Safety training 15 persons

August 2021

Safety training 8

Yunnan Lincang Border Economic Cooperation Zone Development Project (3759 PRC)

68

9.0 Issues and Corrective Actions

(1) Water environment 53. The monitoring data for three consecutive days from August 13, 2021 to August 13, 2021 show that the monitoring data for both the upper and lower reaches of the C-RD04 bridge section of the Nanting River meet the Environmental Quality Standard for Surface Water (GB3838-2002) Class III standard except for dissolved oxygen, which was caused by high temperature at the day of sampling.

(2) Atmospheric environment 54. The monitoring results show that the concentration of pollutants at each monitoring point meets the Ambient Air Quality Standard (GB3095-2012) Class II standard, from August 10, 2021 to August 16, 2021. Road construction dust has a certain impact on the air environment along the route, and the air pollution mitigation measures proposed in the EIA should be implemented seriously, and the site should be sprinkled with water to reduce dust and covered with a tarp.

(3) Sound environment 55. The monitoring data from August 11, 2021 to August 14, 2021 at the monitoring points around the project construction site and sensitive points for two consecutive days at daytime and nighttime can meet the sound environment quality standard (GB3096-2008) class 2 and class 4a standards. The impact of the construction on surrounding residents is not significant. It is recommended that all contractors continue to strengthen the management of construction vehicles and reasonably allocate construction machinery activities to reduce sudden noise.

(4) Ecological environment 56. A second-class protected tree, along the transport road downstream of the right bank of the Nanting River Bridge is not specially protected and is susceptible to damage from side slope runoff during the rainy season. Protective fence is recommended. 57. The greening and restoration plant species selected for the preliminary design of the Qing Shui River rehabilitation is relatively single, and gerbera (Cosmos bipinnata) is an exotic species. The project area is suitable for its growth and it has been listed as an invasive alien species. I n order to protect the local terrestrial ecological environment, it is recommended to use other native species. Orychophragmus violaceu as a flower is an excellent landscape plant, but under the annual accumulation conditions of the project area, it is extremely difficult to vernalize and bloom, and it is a 1-year-old herbaceous plant, which is difficult to maintain subsequently. It is recommended to use the combination of trees, shrubs and grasses for landscape greening and revegetation, and the plants selected should be native species. (5) Grievance mechanism 1) C-ICA01 Contractor has no construction activity during this reporting period and shall

prepare a site environmental management plan and establish a grievance mechanism notice board prior to resuming construction.

2) C-RD01a was mobilized in May 2021 and it is required to install a notice board for the grievance mechanism as soon as possible.

Yunnan Lincang Border Economic Cooperation Zone Development Project(3759 PRC )

69

(6) Capacity-building 58. The loan implementation environmental consultant plans to conduct environmental management training for all contractors and supervisors on October 19, 2021, especially providing training on the preparation of a construction site environmental management plan, installation of an environmental complaint response mechanism notice board at the construction site, and the implementation of appropriate environmental protection and mitigation measures.