The application process of fusion-bonded epoxy as field joint ...
-
Upload
khangminh22 -
Category
Documents
-
view
2 -
download
0
Transcript of The application process of fusion-bonded epoxy as field joint ...
The application process of fusion-bonded epoxy
as field joint coating
Geert Jan Kap
Faculty of Mechanical, Maritime and Materials Engineering
Faculty of Civil Engineering and Geosciences
Faculty of Technology, Policy and Management
Delft University of Technology
Allseas Engineering BV
Thesis
Master of Science - Transport, Infrastructure and Logistics
August 2013
Preface
This report marks the final steps towards my graduation. It describes my thesis
work, which I completed at Allseas Engineering BV in corporation with Delft
Technical University. During this masters thesis I enjoyed the combination of
scientific knowledge with hands on experimenting. One day I would be reading
about the chemical cross linking of thermosetting polymers. The next day I would
build a machine and clean the excess epoxy powder out of a fluidised bed with a
shop vac. To me this is the definition of being a true engineer.
A wise man once said: when thanking people you should mention everybody or
nobody at all. True words, but with the risk of forgetting a couple I will give it
a try. First off I would like to thank my graduation committee for their support,
comments and guidance throughout the process. Professor Rijsenbrij for his enthu-
siasm on the subject. Wouter van den Bos for helping me stay on topic. Professor
Heijnen for her help with getting my thoughts on paper. Kirill and Erik, for their
vast knowledge and discussions on the topic of field joint coating. Manuel, Jos,
Mark, Warner and everybody else from PPD and the yard in IJmuiden for their
support during the tests. My roommates in C3.27 and the colleagues I shared a
pool-car with or shared a small break with by the coffee machine. My parents
Aaldrik and Marianne, my family and my parents-in-law Wolter and Arina for
their never ending support. My close friends for the good times we had besides
our studies and Arne in particular for his tips on writing the final report.
I would like to thank Allseas for the chance they gave me to do my thesis work
at their exciting company. I am grateful for the chances given and I am looking
forward to continue my career within the company.
Finally I would like to thank my lovely girlfriend Fenna for sticking by my side
for all these years and especially these final weeks. Your love and support were of
great significance for the completion of this thesis and the successful ending of my
career as a student.
Delft University of Technology
FACULTY MECHANICAL, MARITIME AND
MATERIALS ENGINEERING Department Marine and Transport Technology
Mekelweg 2 2628 CD Delft the Netherlands Phone +31 (0)15-2782889 Fax +31 (0)15-2781397 www.mtt.tudelft.nl
This report consists of 99 pages. It may only be reproduced literally and as a whole. For commercial purposes only with written authorization of Delft University of Technology. Requests for consult are only taken into consideration under the condition that the applicant denies all legal rights on liabilities concerning the contents of the advice.
Specialization: Transport Infrastructure and Logistics Report number: 2013.TIL.7786 Title: The application process of fusion-
bonded epoxy as field joint coating
Author: G.J. Kap
Title (in Dutch) Het applicatie proces van fusion-bonded epoxy als field joint coating
Assignment: Master thesis
Confidential: yes
Initiator (university): Prof. ir. J.C. Rijsenbrij (Delft University of Technology)
Initiator (company): Dr. K. Kavelin, Ir. E. Kramer (Allseas Engineering BV, Delft)
Supervisor: ir. W. van den Bos, Dr.ir. P.W. Heijnen
Date: August 23, 2013
Student: G.J. Kap Assignment type: Master thesis
Supervisor (TUD): ir. W. van den Bos, Dr.ir.
P.W. Heijnen (TU Delft)
Creditpoints (EC): 30
Supervisor (Company) Dr. K. Kavelin, Ir. E.
Kramer (Allseas Engineering BV)
Specialization: TIL
Report number: 2013.TIL.7786
Confidential: Yes
Subject: The application process of fusion-bonded epoxy as field joint coating
Allseas is one of the leading offshore pipeline installation contractors in the business. For the
installation of pipes, it uses the so called S-lay method, a method where pipe sections, called joints,
are assembled into a continuous pipeline at the firing line, on-board the pipe lay vessel. Subsequent
stations perform welding, non-destructive testing and coating tasks in this firing line. Since the
founding of the company in 1985, much of the equipment to perform these tasks was designed,
developed and built in-house. A lot of effort was put into improving installation time. Allseas and its
clients mainly focused on the welding and NDT testing stations while the coating process drew
relatively less attention.
In recent years the attention of the clients of Allseas shifted to the coating stations. There were also
signals that on some projects the process time of individual coating stations negatively affected the
overall installation time. This has triggered Allseas to also improve the coating process, with a focus
on process times, while coating quality should not suffer. A combined machine for heating and coating
was used, a mechanical blaster was installed in the firing line and the grit blast equipment was scaled
up with the addition of more blast heads. Some of these improvements were more successful than
others.
The assignment of this master’s thesis is to make an analysis of the current coating process and find
possible improvements. These improvements should be tested on process times and coating quality.
Finally an advice should be given about the implementation of these improvements within the current
pipeline installation process.
The report should comply with the guidelines of the section. Details can be found on the website.
The professor,
Prof. ir. J.C. Rijsenbrij
Summary
Allseas is one of the leading offshore pipeline installation contractors in the busi-
ness. For the installation of pipes, it uses the so called S-lay method, a method
where pipe sections are assembled into a continuous pipeline at the firing line, on-
board the pipe lay vessel. Subsequent stations perform welding, non-destructive
testing and coating tasks in this firing line.
Since the founding of the company in 1985, much of the equipment to perform
these tasks was designed, developed and built in-house. A lot of effort was put
into improving installation time. Allseas and its clients were mainly focused on the
welding and NDT testing stations while the coating process drew relatively less
attention.
In recent years the attention is shifted to the coating stations. There were also sig-
nals that on some projects the process time of individual coating stations negatively
affected the overall installation time.
Although some effort was made in the past to improve the coating process the re-
sults were disappointing. The need for reducing overall process times while main-
taining coating quality still remains. Therefore Allseas initiated this research,
exploring possible changes to the coating process.
A preliminary research showed that fusion-bonded epoxy is the most used coating
type. Based on that the choice was made to focus the research on the application
process of fusion bonded epoxy.
The goal of the research was formulated as a research question: What are the
possibilities to change the current process of field joint coating application, in
order to achieve faster cycle times while maintaining the current coating quality,
while taking into account requirements for changes to the process?
To answer the research question the current process of pipeline production was
analysed. From this analysis it was concluded that there were three possibilities
for changes to the process:
• The order of steps within the process
• Combination of steps within the process
• Alternative methods within the process step
A research into the current cycle times showed that for some projects the field
joint coating stations could be critical. From the limited amount of data available
it could be seen that the most time was used at the station where the joint is
heated and coated. Analysis of cycle times did not show the surface preparation
station to be critical. Interviews with Allseas employees however confirmed that
for some projects the surface preparation station was critical.
The analysis of the current equipment used for the application process of fusion-
bonded epoxy was done. This research showed that the current method of surface
preparation, grit blasting, could be improved. The current method gives good
results, but due to a limitation in space for the grit handling units it is difficult to
optimise this method.
The method of heating the joint with induction heating is the most efficient and
clean way. The shape of the coil however could be changed in order to combine
the heating coil with other equipment.
A research into possible alternatives was done, based on the conclusions of the
analysis of the current process and equipment. A number of possible alternatives
were found.
The order of steps within the process:
• Pre-blasting with mechanical blasting followed by cleaning with laser or dry
ice
• Pre-blasting with grit blasting followed by cleaning with laser or dry ice
Combination of steps within the process:
• Shockwave Induced Spray Painting
• Combined Heat & Coat machine with alternative heating coil
Alternative methods within the process step:
• Dry ice with grit blasting instead of grit blasting
• Pick brush instead of grit blasting
• Low application temperature FBE instead of FBE
• Surface treatment with laser blasting instead of grit blasting
Based on found requirements for new equipment and the change of the process, a
number of these alternatives were chosen to further research:
• Pre-blasting with mechanical blasting followed by cleaning with laser or dry
ice
• Dry ice with grit blasting instead of grit blasting
• Low application temperature FBE instead of FBE
• Surface treatment with laser blasting instead of grit blasting
Practical tests were performed to see whether these possible alternatives could
lead to the reduction of cycle times while maintaining the coating quality. A test
setup was designed and built in-house. The test setup replicated the process in the
firing line. Steel plates were used, which were treated with the different surface
treatment methods. After that they were heated in an industrial oven. After
heating they were coated with FBE. Once the FBE was fully cured, destructive
tests were performed to evaluate the level of the quality of the coating.
During the tests different measurements were taken. The time each of the surface
treatment methods took was recorded. The noise levels of the surface treatment
were recorded as part of the safety aspect. During the destructive test the degra-
dation of the coating was measured.
Based on the test result it was concluded that there are three alternatives that can
be identified as prominent alternatives for FBE application:
• Pre-blasting with mechanical blasting followed by cleaning with laser
• Dry ice with grit blasting
• The application of LAT FBE
Based on the conclusions some further recommendations can be made for each of
the three possible alternatives.
Pre-blasting with mechanical blasting followed by cleaning with laser:
• Research the possibilities for the incorporation of a mechanical blaster in the
bevelling station
• Further test the use of laser equipment in the current process and with the
current equipment
• Investigate possible safety issues related to the use of laser equipment
Dry ice with grit blasting:
• Research the logistics of dry ice pellets
• Research the possibility of producing of dry ice on board the vessels
• Execute more tests with different types of blast media added to the dry ice
• Research the possibilities for the reduction of noise levels
• Investigate the possible safety issues with CO2
The application of LAT FBE:
• Research the possible time reduction when applying LAT FBE with current
equipment
• Research the cost aspect of applying LAT FBE powder with respect to the
reduction of time (cost versus gain)
Contents
Preface x
Summary x
List of Figures xi
List of Tables xv
Glossary xvii
1 Introduction 1
1.1 General introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.2 Problem definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.3 Relevance of the research . . . . . . . . . . . . . . . . . . . . . . . . . . 6
1.4 Goal of research . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
1.5 Structure of the report . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2 Analysis - process 13
2.1 Requirements for the pipeline production process . . . . . . . . . . . . . 13
2.2 Process description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
2.3 Cycle time analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.4 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
3 Analysis - equipment 23
3.1 Requirements for equipment . . . . . . . . . . . . . . . . . . . . . . . . . 23
3.2 Surface preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
3.3 Coating application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.4 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
ix
CONTENTS
4 Alternative application methods 35
4.1 Process alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
4.2 Surface preparation alternatives . . . . . . . . . . . . . . . . . . . . . . . 39
4.3 Coating application alternatives . . . . . . . . . . . . . . . . . . . . . . . 45
4.4 Choice of alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
4.5 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
5 Tests 49
5.1 Goal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
5.2 Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
5.3 Validation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
5.4 Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
5.5 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
6 Conclusions & Recommendations 73
6.1 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
6.2 Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
Bibliography 77
x
List of Figures
1.1 S-lay method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.2 Firing line on board PLV Solitaire . . . . . . . . . . . . . . . . . . . . . 4
1.3 Schematic overview of the firing line of the Solitaire . . . . . . . . . . . 5
1.4 Percentage of field joints per surface preparation method . . . . . . . . . 7
1.5 Percentage of field joints per coating type . . . . . . . . . . . . . . . . . 8
2.1 Scematic overview of the process . . . . . . . . . . . . . . . . . . . . . . 15
2.2 Process of pre-production . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.3 Example of a J-bevel and a K-bevel . . . . . . . . . . . . . . . . . . . . 17
2.4 Process of welding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
2.5 Build-up of welds in the pipeline wall . . . . . . . . . . . . . . . . . . . . 18
2.6 Schematic process overview of Field Joint Coating . . . . . . . . . . . . 20
2.7 Typical field joint . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
3.1 Anchor profiles on substrate; left is shallow, right is deep[1] . . . . . . . 25
3.2 Sample of blast media: steel shot and grit mix . . . . . . . . . . . . . . 26
3.3 Grit blast frame in operation on the pipe . . . . . . . . . . . . . . . . . 27
3.4 Grit handling unit - LTC . . . . . . . . . . . . . . . . . . . . . . . . . . 28
3.5 Green mile of PLV Solitaire . . . . . . . . . . . . . . . . . . . . . . . . . 29
3.6 Heating coil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3.7 Heat profile along the field joint[2] . . . . . . . . . . . . . . . . . . . . . 31
3.8 FBE coating frame . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
3.9 Inside of the coating ring of the application frame . . . . . . . . . . . . . 32
3.10 Fluidised bed together with control panel . . . . . . . . . . . . . . . . . 33
4.1 Pre-blast process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
xi
LIST OF FIGURES
4.2 FBE application dishes . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
4.3 Combined steps process for heat and coat machine . . . . . . . . . . . . 38
4.4 Contact blocks of heat and coat machine . . . . . . . . . . . . . . . . . . 38
4.5 Spacing between the heating coil and pipe . . . . . . . . . . . . . . . . . 39
4.6 Mechanical blasting machine [3] . . . . . . . . . . . . . . . . . . . . . . . 40
4.7 Bauhaus mechanical blaster in FL . . . . . . . . . . . . . . . . . . . . . 41
4.8 Surface preparation with laser beam . . . . . . . . . . . . . . . . . . . . 42
4.9 Laser treatment of steel piece . . . . . . . . . . . . . . . . . . . . . . . . 42
4.10 Pellets of dry ice used for blasting . . . . . . . . . . . . . . . . . . . . . 43
4.11 Principle of dry ice blasting [4] . . . . . . . . . . . . . . . . . . . . . . . 44
4.12 Power wire brush with hardend bent ends [5] . . . . . . . . . . . . . . . 44
4.13 Power wire brush frame . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
4.14 Schematic overview SISP process [6] . . . . . . . . . . . . . . . . . . . . 46
5.1 Test plates blasted and put outside . . . . . . . . . . . . . . . . . . . . . 51
5.2 Corroded test plates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
5.3 Test setup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
5.4 Grit blast head fitted in test setup . . . . . . . . . . . . . . . . . . . . . 53
5.5 Test plates in industrial oven . . . . . . . . . . . . . . . . . . . . . . . . 54
5.6 FBE application nozzle fitted in test setup . . . . . . . . . . . . . . . . . 54
5.7 Mechanical blaster test setup . . . . . . . . . . . . . . . . . . . . . . . . 55
5.8 Simulating FL conditions with heat and NDT water . . . . . . . . . . . 56
5.9 Dry ice blasting method . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
5.10 Laser treatment test setup . . . . . . . . . . . . . . . . . . . . . . . . . . 57
5.11 Surface comparator with mechanical blasted test plate . . . . . . . . . . 60
5.12 Measuring of the Testex tape . . . . . . . . . . . . . . . . . . . . . . . . 61
5.13 Surface after mechanical blasting . . . . . . . . . . . . . . . . . . . . . . 62
5.14 Surface after laser blasting . . . . . . . . . . . . . . . . . . . . . . . . . . 62
5.15 Test setup Noise level measurement . . . . . . . . . . . . . . . . . . . . . 63
5.16 Cured coating on a test plate . . . . . . . . . . . . . . . . . . . . . . . . 64
5.17 Adhesion test - resistance to removal . . . . . . . . . . . . . . . . . . . . 65
5.18 Pull-off tester and 20mm dollies glued to test plate . . . . . . . . . . . . 66
5.19 Pull-off results 14mm: three failure types for batch D . . . . . . . . . . 68
xii
LIST OF FIGURES
5.20 Cathodic disbondment test setup at Element, Amsterdam . . . . . . . . 69
5.21 Cathodic disbondment on test plate . . . . . . . . . . . . . . . . . . . . 70
xiii
List of Tables
2.1 Firing line stations overview . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.2 Joint types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.3 Cycle times of the three main steps . . . . . . . . . . . . . . . . . . . . . 21
2.4 Cycle times per station . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
5.1 Anchor profile measurements . . . . . . . . . . . . . . . . . . . . . . . . 61
5.2 Cycle time measurements . . . . . . . . . . . . . . . . . . . . . . . . . . 63
5.3 Noise level measurements . . . . . . . . . . . . . . . . . . . . . . . . . . 63
5.4 Dry film thickness measurements . . . . . . . . . . . . . . . . . . . . . . 64
5.5 20mm dolly pull-off test measurements . . . . . . . . . . . . . . . . . . . 67
5.6 14mm dolly pull-off test measurements . . . . . . . . . . . . . . . . . . . 67
5.7 Cathodic disbondment test results . . . . . . . . . . . . . . . . . . . . . 70
5.8 Test results summarised . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
6.1 Test results summarised . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
xv
Glossary
DJF Double Joint Factory
FBE Fusion-bonded Epoxy
FJ Field Joint
FJC Field Joint Coating
FL Firing Line
HSS Heat Shrink Sleeve
LE Liquid Epoxy
NDT Non-Destructive Testing
OD Outside Diameter
PLV Pipelay Vessel
PP Pipeline Production
PPD Pipeline Production Departement
PQT Procedure Qualification Trial
PWB Power Wire Brush
QHSE Quality, Health, Safety and Environment
WT Wall Thickness
xvii
1
Introduction
This chapter introduces the topic of this masters thesis. Section 1.1 will give a general
introduction of the topic. In section 1.2 the problem definition is stated. In section 1.3
the relevance of the research is stated. In section 1.4 the goal of the research is sketched.
Finally in section 1.5 the structure of the report is given.
1.1 General introduction
Around the world many offshore platforms extract hydrocarbons in the form of oil
and natural gas. One way to transport these hydrocarbons between platforms wells
and onshore is by means of pipelines. This method of transportation is a low cost
alternative with respect to tons per kilometre. Before transportation can commence
the pipeline needs to be produced and installed.
Allseas is a company that installs those pipelines. As a commercial company their
goal is to lay the best pipeline possible in the shortest amount of time. To be able to do
this, they have to constantly monitor and improve their method of pipeline installation
and production. With this in mind Allseas has been the originator of this research.
Before the research is further explained an introduction to Allseas and the installation
and production of pipelines is given.
1.1.1 Allseas
The Swiss-based Allseas Group S.A. is a global leader in offshore pipeline installation
and subsea construction. The company employs over 2,000 people worldwide and oper-
1
1. INTRODUCTION
ates a versatile fleet of specialized pipelay and support vessels, designed and developed
in-house [7].
The basis of this fleet, are the pipelay vessels (PLVs):
• Solitaire (300 m)
• Audacia (225 m)
• Lorelay (182.5 m)
• Tog Mor (111 m)
All vessels are capable of handling pipelines with outside diameters (OD) ranging
from 2 inch to 60 inch, except for PLV Lorelay, which is limited to a maximum OD of
28 inch. PLV Solitaire has achieved pipelay speeds in excess of 9 km/day [7].
Currently Allseas is building her fifth PLV, the Pieter Schelte. She will be commis-
sioned in 2014. The Pieter Schelte will then be the biggest PLV in the world with an
overall length of 382 meter. She will be capable of laying pipelines up to a maximum
OD of 68 inch.
The philosophy within Allseas has always been to develop and design its own equip-
ment, ranging from the Phoenix welding system up to the biggest pipelay vessel thus
far, the Pieter Schelte. From this philosophy the department of Innovations has tried
and tested numerous different methods of pipeline production and continues to perfect
and adapt its equipment. The main reason to apply this philosophy is to stay ahead of
the competition and to be independent from (sub) contractors. Allseas uses a specific
method of pipeline installation which is explained in the next section.
1.1.2 Pipeline installation
There are a number of different methods for the offshore installation of pipelines. The
choice for each one of these methods relies on a number of factors. The most important
being water depth and the OD of the pipe. For Allseas two methods are suited. The
first method is the so called S-lay method. The second is the so called J-lay method
[8]. The letters S and J, describe the shape of the pipeline from the PLV to the ocean
floor.
2
1.1 General introduction
With the J-lay method the pipeline is produced in a vertical tower. At the deck level
al the steps to produce the pipeline are performed in the same station. S-lay describes
the method of pipeline installation where the pipeline is produced horizontally.
The main advantage of S-lay is the fact that it is possible to simultaneously conduct
several steps needed for pipeline production. These are done in multiple stations along
the length of the ship. There are different stations for welding, non-destructive testing
(NDT) and field joint coating (FJC).
The pipeline follows the shape of the letter S, from the vessel to the bottom of the
sea as seen in figure 1.1. To support the pipeline while leaving the vessel a stinger is
attached. The stinger is a support structure that limits the bend radius of the pipeline
and prevents buckling of the pipeline.
Figure 1.1: S-lay method
Several tensioners fitted with tracks hold the pipeline in the vessel. The tensioners
are controlled to move the pipeline in and out of the vessel. This is done automatically
to compensate for vessel motions due to waves. The deeper the pipeline needs to be
installed the higher tension is needed to hold the pipeline with the tensioners.
Allseas has designed and developed systems for J-lay and S-lay installation. The
choice was made for the S-lay method because this method provides fast installation
for all pipeline ODs over a large range of water depths in comparison with the J-lay
method [8]. The choice for the S-lay method resulted in a specific layout of the pipeline
production, which is described in the next section.
3
1. INTRODUCTION
1.1.3 Pipeline production
The production process of a pipeline can be compared to a standard production process
in a factory. A piece of pipe, called a joint, enters the factory. During the production
process joints are connected to form a continuous pipeline. The factory is the firing
line (FL). Production rates can be increased with the addition of a double joint factory
(DJF) to the FL. In the DJF two single joints are connected to form a double joint
before entering the FL.
Firing line
In each of the four PLV’s of Allseas the joints are transformed in a continuous pipeline
in the firing line. The FL is situated along the length of the vessel. It is divided in a
number of work stations. There are a number of consecutive stations where the welding
of the joints takes place. In figure 1.2 the firing line of PLV Solitaire is presented.
Figure 1.2: Firing line on board PLV Solitaire
When two joints are welded together both cut-back sections together are called a
field joint (FJ). A cut-back is the bare section on both ends of the joint. In the next
station the weld is checked with ultrasonic sound, this station is called the NDT station.
4
1.1 General introduction
Finally there are a number of stations that together perform the task of coating the
FJ.
During each production cycle each station performs its individual task. When the
task is completed the operator gives a signal. Once all stations have signalled they are
ready, the pipeline can move to the next station. The distance that the pipeline moves
between stations is called a pull. The vessel moves forward in the lay direction and the
tensioner pays out the length of one pull. Each FJ then arrives at the next station,
while the last FJ moves to the stinger.
In figure 1.3 a schematic overview of the FL of the Solitaire is presented. On the
bow of the vessel the FL starts with the welding stations. At the stern of the vessel,
the stinger is situated.
Figure 1.3: Schematic overview of the firing line of the Solitaire
Double joint factory
In order to increase lay rates the Solitaire is equipped with a Double Joint Factory
(DJF). In the DJF single joints are welded together to form a double joint. The firing
line of the Solitaire is therefore twice as long as that of the other vessels. The newly
build Pieter Schelte will also be equipped with a double joint factory. In the DJF joints
are welded and the weld is inspected with NDT. Coating of the welded double joint
does not take place in the DJF. Coating takes place in the FL where more FJC stations
are available.
5
1. INTRODUCTION
1.2 Problem definition
During the pipeline production process it is important to minimize the time that each
joint has to be in a single station (cycle time), whether it is one of the welding stations,
NDT or FJC stations. Furthermore it is important to synchronise the cycle times
of the stations with each other. This results in an optimal usage of the production
potential. The reduction in cycle times lead to lower overall production process times
and minimizes project costs.
To achieve this, a lot of attention over the past years was given to the welding and
NDT process. Welding over the years has become more reliable with the introduction
of the automated Phoenix welding system and cycle times have thus been reduced and
became more constant. With the automation of non-destructive testing and welding
the chances on defects and repairs have also been greatly reduced [9].
There is a tendency now to pay more attention to FJC. During recent projects it
has been observed that cycle times of FJC stations were not coherent with welding
and NDT. One of the approaches from Allseas was to build the combined heat and
coat machine. The machine was capable of performing two steps in one. The machine
however was bulky and not optimised, which resulted in a bad coating quality. Another
step was the introduction of a wheelabrator (mechanical grit blast machine) in the FL.
The principle was promising but the fixed nature of the machine was not ideal for use
in the FL.
Although an effort was made in the past to improve the coating process the results
were disappointing. The need for reducing overall process times while maintaining
coating quality however remains. Therefore Allseas initiated this research, exploring
possible changes to the coating process.
1.3 Relevance of the research
The coating process within Allseas has a number of variables depending on the project.
For each project the FJ has to be coated to protect it against corrosion. This first
layer of coating is called the anti-corrosion coating and is always applied to the FJ.
Optionally a second coating can be applied to protect the pipeline against mechanical
damage or to insulate the pipeline.
6
1.3 Relevance of the research
For each project the client in cooperation with Allseas decides on the type of anti-
corrosion coating that will be applied. The choice for the type of coating also decides
the type of surface preparation that must be done. Three types of anti-corrosion coat-
ing can be distinguished: liquid epoxy (LE), fusion-bonded epoxy (FBE) and a heat
shrink sleeve (HSS). Two types of surface preparation can be distinguished: power wire
brushing (PWB) and air pressured grit blasting. When FBE is chosen, this automat-
ically means that grit blasting is used for surface preparation. For LE and HSS both
types of surface preparation can be chosen.
A preliminary research in to the choice for each of these types was done to establish
the relevance of the research. With the results from this preliminary research a scope
can be defined for the actual research.
1.3.1 Field joint coating project data
Analysis of available project data gives an indication of the relevance of the research
of FJC application. The analysis is based on track records Allseas has of past projects
and the known characteristics of planned projects. Due to missing data in this track
record the overview is based on data from 2008 up until 2014. The overview is based
on the number of FJs made in each of the pipeline installation projects for al PLVs
combined.
Figure 1.4: Percentage of field joints per surface preparation method
7
1. INTRODUCTION
In figure 1.4 it can be seen that PWB was used for a great part in past. This has
changed however. The use of grit blasting has risen. This can be explained by the rise
in use of FBE as a FJC, which requires grit blasting. This can be seen in figure 1.5.
In that figure it can also be seen that the use of HSS has diminished. LE is still used,
but for limited amount of projects.
Figure 1.5: Percentage of field joints per coating type
From interviews with coating engineers from Allseas it became clear that in the
future the use of HSS and LE will further diminish. The demand from clients of
Allseas will mainly be FBE. As a result grit blasting will be the predominant choice
for surface preparation.
1.3.2 Scope of research
Based on section 1.3.1 it can be concluded that FBE will be the most used field joint
coating for the coming years within Allseas. The scope of this research will therefore
lie on the application process of FBE. Another reason for this scope is the practical
implementation. If changes to the process can be found which reduce the overall process
times it will be possible for Allseas to benefit from these changes on a short term.
Completely new forms of coating could possibly require more time to fully research and
implement and are therefore out of the scope of this research.
8
1.4 Goal of research
Because the FBE coating application process only takes place in the FL, the DJF
on Solitaire lies outside of the scope. The scope of the research will be on the FL itself.
The application process of secondary coatings lies outside of the scope because the
choice for secondary coatings is not as regularly as the application of anti-corrosion
coating.
1.4 Goal of research
With the scope of the research defined in section 1.3.2 and the problem definition from
section 1.2 the goal of the research can be set. This is done by first formulating the
main research question, after which the approach of the research can be defined.
1.4.1 Research question
The main research question is formulated as follows: ’What are the possibilities to
change the current process of field joint coating application, in order to achieve faster
cycle times while maintaining the current coating quality, while taking into account
requirements for changes to the process?’
To answer the main research question there are a number of sub-questions to be
answered. These questions are:
I What is the current process of FJC application?
II What equipment is used in the current process?
III What are the cycle times within the whole process of pipeline production?
IV What defines the level of quality of field joint coating?
V What changes could be made to the current process?
VI What are the requirements for changes to the process?
VII What alternatives are available for the process and the equipment?
VIII Which of these alternatives can lead to faster cycle times?
IX Can these alternatives maintain the current quality level of field joint coating?
X How can alternatives be implemented in the current process of pipeline installation?
9
1. INTRODUCTION
1.4.2 Approach
To answer each of the sub questions a certain approach is necessary. The approach for
each of the question will be as follows:
I Analyse the current FBE application process through in-house literature and inter-
views with Allseas employees to find possibilities for changes.
II Analyse the current FBE application equipment through in-house literature, inter-
views with Allseas employees and a visual inspection of the equipment at the
storage facility to find possibilities for changes.
III Analyse the project data that is available within the Pipeline Production depart-
ment to get cycle times for different projects and to find which possibilities for
change would have to most effect on overall cycle times.
IV Study publications and in-house literature on the topic of coating to find the pa-
rameters which define the level of quality of coating and the methods to asses
this level.
V List the possibilities for changes based on the findings of I, II and III.
VI Study publications and in-house literature and interview employees to find the
requirements for changes to the process.
VII Find alternatives for the possibilities for changes as found in V through a literature
study, interviews with Allseas employees and interviews with suppliers of coating
equipment.
VIII Measure the cycle times of alternatives found in VII trough practical tests and
project these times on the real-time process.
IX Measure the quality of the coating that has been made through practical tests
based on the findings of IV.
X Give an advise on the implementation of the alternatives based on the findings of
VI, VIII and IX.
10
1.5 Structure of the report
1.5 Structure of the report
The structure for the report will be as follows; In chapter 2 an analysis of the pipeline
production process is given. In chapter 3 an analysis of the equipment used within the
FJC process is given. In chapter 4 alternative application methods for the FJC process
are researched. Based on found requirements the most promising ones are chosen. In
chapter 5 the chosen alternatives are tested. Finally in chapter 6 the results of the tests
are discussed and conclusions are drawn.
11
2
Analysis - process
In this chapter an analysis will be made of the current process of pipeline production
and the application of FBE as a field joint coating in particular. The whole process is
analysed to give an indication of the role of the FJC process in the whole pipeline pro-
duction process. The analysis should point out which possibilities there are to change
the process of pipeline production. The analysis starts with stating the requirements
for the pipeline production process in section 2.1. The process is described in sec-
tion 2.2. In section 2.3 an indication of the cycle times of the stations is given. Finally
in section 2.4 conclusions are drawn with respect to possibilities for changes of the
process.
2.1 Requirements for the pipeline production process
To get an insight in the pipeline production (PP) process the requirements for the
process are researched in this section. Requirements for the PP process in a certain
project can be given from one actor to another actor. They can also be discussed
and agreed upon by multiple actors. Four different actors can be distinguished in this
process:
1. Allseas
2. Clients
3. Suppliers
4. Independent parties
13
2. ANALYSIS - PROCESS
Clients are oil and gas companies who contract Allseas to install pipelines. Suppliers
are companies who supply Allseas with equipment and / or consumables. Equipment
can range from components to whole machines. Consumables can be grit for the grit
blaster or FBE powder used in the coating machine. Independent parties can be gov-
ernments or organisations like ISO, DNV or Lloyds. They standardise and formalise
the requirements for pipeline construction and installation.
Requirements for a project are driven by the client and determined in detail in
corporation with Allseas. These requirements can be categorized in three themes;
Time For Allseas to be competitive and be successful as a commercial company the
main goal for the process of PP is to make as much pulls as possible in a given amount
of time. To achieve this goal the cycle time of each of the individual work stations needs
to be as low as possible. Next to that the cycle times per station need to be as close
together as possible to use the production capacity to a maximum. The station that
uses to most time to perform its individual task is called critical. The time needed for
this station is the governing time for the total process time and the amount of pipeline
that can be installed per day.
Quality The process needs to result in a pipeline that adheres to the agreed level of
quality. This means that the process is designed in a certain way. Surface preparation
for instance needs to take place before coating can be applied. It may be possible to
make changes to the process while still adhering to the level of quality.
Safety and Health Within Allseas there is a Quality, Health, Safety and Environ-
ment (QHSE) department. This QHSE department has the specific task of monitoring
all the processes that take place within Allseas. One of their main tasks is the safety
and wellbeing of employees. The PP process therefore needs to be designed in such a
way that the safety and wellbeing of employees is guaranteed. Where possible, safety
measures should be incorporated in the process.
2.2 Process description
In this section the complete process of pipeline production is described. In the PP
process four main steps can be distinguished: pre-production, welding, NDT, and FJC.
14
2.2 Process description
A schematic overview of these four steps can be seen in figure 2.1. The first step
pre-production takes place before the FL. The other three steps combined form the FL.
Pipeline production process
Firing Line
Non distructive testing
WeldingField Joint
CoatingPre-production
Figure 2.1: Scematic overview of the process
Each of the steps is performed in a separate work station. Table 2.1 gives an
overview of the number of stations on each of the PLV’s of Allseas. The number of
stations used depends on the project. For smaller pipeline OD’s with smaller wall
thicknesses (WT) less welding stations could be used than there are available.
Vessel Welding stations NDT stations FJC stations
Pieter Schelte 6 1 6
Solitaire 5 1 4
Audacia 7 1 3
Lorelay 6 1 3
Tog Mor 3 1 1
Table 2.1: Firing line stations overview
In the next sections the processes during pre-production and in stations in the FL
are further explained.
2.2.1 Pre-production
The pipeline is produced in the FL, before the FL there is a pre-production process.
In this pre-production process the joints that form the pipeline are prepared for the
process of the firing line.
The steps in the pre-production process are bevelling of the joint, cleaning of the
inside of the joint and finally heating of the ends of the joint. These steps can be seen
15
2. ANALYSIS - PROCESS
in the schematic overview in figure 2.2.
Pre-production
Pro
cess
st
ep
CleaningBeveling Heating
Figure 2.2: Process of pre-production
Joints come in a standard length of 40 feet (12.2 meter). Joints come in different
sizes with respect to OD and WT [8]. The choice for OD and WT are based on the
function of the pipeline. These functions can be roughly divided into three categories
as shown in table 2.2. These are not set values. Other combinations are possible as
well.
Type OD [inch] Length [km]
Infield 6 - 12 1 - 30
Trunk lines 10 - 24 10 - 70
Export lines 24 - 42 100 - 1000
Table 2.2: Joint types
Joints are made of steel and WT ranges from 12 to 41 mm. Joints are supplied with
a factory applied coating which is called the parent coating. The ends of the joints are
left bare for welding and NDT. This bare end is called a cut-back. The length of the
cut-back ranges from 100 to 250 mm.
Joints are supplied by different companies depending on the job location. The way
joints are transported, stored and handled form supplier to the vessel has led to many
different surface conditions of the cut-back. These conditions can range from mild rust
to severe pitting. Severe corrosion on the cut-back has a negative effect on the time
needed to prepare it for the FL.
The first step is making a bevel. Depending on the type of weld two different bevels
can be made. If the joint is welded from the inside and the outside a so called K-bevel
is made. Welding from the inside can only be done in the DJF. If the joint is only
16
2.2 Process description
welded from the outside a so called J-bevel is made. In the FL the FJ is only welded
from the outside. In figure 2.3 an example of both bevels can be seen.
Figure 2.3: Example of a J-bevel and a K-bevel
To make the bevel a machine is inserted in the pipe. It machines the edge of the
cutback in the required bevel. The machine also brushes the cutback to prepare it for
welding.
After bevelling the joint is cleaned from the inside. This is done to prevent foreign
objects being left in the pipeline during or after production.
Once the joint is cleaned the cut-back is heated with a heating coil. This is done
to prepare for the welding process in the FL. After heating the joint can enter the FL.
2.2.2 Welding
Welding
Sta
tio
n
Pro
cess
st
ep
Intermediate stations (2-4/
5/6)
Bead stall (Line-up
station 1)
Final station (5/6/7)
Filler (hot) passRoot pass Cap weld
Figure 2.4: Process of welding
Before welding starts, the new joint is lined up against the existing pipeline. This
is done with a line-up car. The line-up car is controlled by an operator. The operator
17
2. ANALYSIS - PROCESS
can manoeuvre the joint in all directions. When the joint is lined-up correctly the first
weld is made. The first weld is called the root pass. The root pass is a full pass around
the circumference of the pipe. This weld must be strong enough to withstand the forces
of a pull. After the root pas, the next stations make the filler (hot) pass. In the final
welding station the last weld is laid which is called the cap. The steps of the welding
process can be seen in figure 2.4. The build-up of the welds can be seen in figure 2.5.
Figure 2.5: Build-up of welds in the pipeline wall
The number of welding stations used is based on the amount of welding that needs
to be done. This in turn depends on the WT and OD of the pipeline. The first (root
pass) and the final (cap) welding station are a given. The number of stations in between
depends on the amount of welding that has to be done. It is distributed over these
stations so none of them can be critical. Cycle times of the first or last welding station
are leading. In each station welding is done until the pull can be made. When a pull
can be made the particular station stops welding and marks the end point. The next
weld station then resumes welding from the spot the previous station has marked. Once
the final weld is made, the whole weld has to be checked for defects in the next station.
2.2.3 Non-destructive testing
After welding the quality of the weld must be checked. This is done in the NDT station.
In the past this was done with X-ray, when photos were made of the weld. These photos
were then inspected. The downside of these photos was their size: they were the same
scale as the weld itself.
18
2.2 Process description
X-ray testing has now been replaced with automatic ultrasonic testing (AUT). With
AUT the images appear on computer screens and can be enhanced for a more detailed
view. AUT works with sound waves that penetrate the metal trough water as a coupling
medium. This water also cools the FJ, which is still hot from the welding process. After
leaving the NDT station the FJ temperature is around 120 degrees Celsius.
The AUT device moves on a rail along the circumference of the pipe. The results
can be seen instantly on computer screens. If unacceptable weld defects are detected
they must be repaired. A partial section or the whole joint can be cut out for repairs.
If a repair has to be made, overall production time is greatly affected. The pipeline
has to be pulled in and the repair has to be made. This results in the loss of valuable
production time.
If the weld passes NDT it can progress to the next station where the FJC application
process starts.
2.2.4 Field joint coating - FBE
The application of FBE as a field joint coating is a three step process. In the first step
the surface area of the FJ is prepared. In the second step the FJ is heated. The final
step is the application of the FBE coating. These steps can be seen in figure 2.6. In
figure 2.7 a typical layout of a FJ can be seen.
Multiple stations are available for coating application. The first station is for surface
preparation. The second station is for the application of the anti-corrosion coating.
Other stations can be used for secondary coatings. As mentioned in chapter 1 these
lay outside of the scope of this research.
Grit blasting is the process where a blast medium is accelerated by compressed air
against the FJ. This takes place in the first FJC station. Once the FJ has been blasted
a protective sleeve is applied around the FJ. This is done to protect the cleaned surface
while it goes through the tensioner to the next station.
In the next FJC station the FBE coating is applied. This is a two-step process that
takes place in the same station.
For the application of FBE coating the FJ needs to be heated to a certain temper-
ature. This is done with an induction coil. Once the required temperature is reached
the coil is taken off. The coating frame is then put on the pipe. This switching of
equipment takes time. Once the coating is applied the coating frame can be taken off.
19
2. ANALYSIS - PROCESS
Field Joint Coating (FBE)
Sta
tio
nP
roce
ss s
tep Station
Coating application 1
Surface preparation
FBE coating application
Induction heating
Grit blasting
Figure 2.6: Schematic process overview of Field Joint Coating
Figure 2.7: Typical field joint
If necessary the coating can be cured by pouring water over the FJ. This is done by
placing a clamp with a water hose on top of the pipe.
2.3 Cycle time analysis
When a new tender for a project is prepared within Allseas, employees from the Pipeline
Production Departement (PPD) make an estimate of the total process time. This
estimate is based on the cycle times of each of the process steps as described in this
20
2.3 Cycle time analysis
chapter. From interviews with employees from PPD it became clear that the estimate
is not really based on databases with project data but more on experience. This meant
it was difficult to obtain data regarding cycle times.
Based on the limited available date from a number of projects the cycle times per
process step are summarised in table 2.3. Projects are named letters A to G. From this
data it can be seen that the FJC process step can become critical.
( critical ) OD Welding NDT FJC
Project [inch] [sec] [sec] [sec]
A 24 501 180 505
B 18 215 150 156
C 18 145 150 156
D 18 142 135 136
E 18 178 150 178
F 13 233 150 175
G 20 188 150 178
Table 2.3: Cycle times of the three main steps
From the projects in table 2.3 where FJC station were critical there was more data
available regarding cycle times of the individual stations. For two other projects H and
I also data was available with respect to cycle times of the FJC stations. These cycle
times are summarised in table 2.4.
( critical ) OD Surface prep Coating Heat Coat
Project [inch] [sec] [sec] [sec] [sec]
A 24 180 230 160 70
C 18 96 95 55 40
E 18 143 178 104 74
H 36 200 285 180 105
I 18 151 134 67 67
Table 2.4: Cycle times per station
From the cycle times from tabel 2.4 it can be seen that both the surface preparation
station and the coating application station can become critical.
21
2. ANALYSIS - PROCESS
From this limited amount of data it can be concluded that changes to the FJC
process and its stations could have an effect on overall process times.
2.4 Conclusions
From the analysis of the current method of pipeline production it can be concluded
that there are three possibilities for changes to the process that could have an effect on
the overall process time.
• The order of steps within the process
• Combination of steps within the process
• Alternative methods within the process step
Although limited, an analysis of cycle times showed that this would indeed have an
effect.
The three possibilities for change are further researched in chapter 4. Before this
can be done an analysis of the current methods within each of the process steps of FJC
must be made, which is done in the next chapter.
22
3
Analysis - equipment
In this chapter an analysis is made of the current equipment that is used for the
application of FBE as a FJC. In section 3.1 requirements are given for the application
equipment. Surface preparation is analysed in section 3.2. Coating application is
analysed in section 3.3. Finally in section 3.4 conclusions on possibilities for changes
are drawn based on the analysis.
3.1 Requirements for equipment
In this section the requirements for existing equipment are described. These require-
ments can also be used when developing new equipment.
Quality As with the process, the use of specific equipment should result in a agreed
level of coating quality. This level of quality is agreed upon by clients of Allseas and
Allseas themselves. It is described in client specifications. In these client specifications
it is stated which equipment should be used and which procedures should be followed
to assure an acceptable quality level of the coating.
Before the project is executed offshore, Allseas performs a Procedure Qualification
Trial (PQT). During a PQT Allseas shows the client in which manner the coating is
applied. After the coating is applied it must be shown that the agreed level of coatin
quality is achieved. For this purpose the applied coating is subjected to quality tests
as described in specific norms and standards. For FBE coating the quality tests as
described in ISO norms 21809 and 8501-1 are performed.
23
3. ANALYSIS - EQUIPMENT
Practical The available space on board the vessels is limited. This means equipment
must be kept within certain dimensions to fit inside the FL or storage areas. The same
holds for consumables used by the equipment.
The possibility to implement a new alternative based on current machinery and
infrastructure is an advantage. Extensive changes to the vessels layout to fit equipment
are not desirable, unless this could be justified with the performance of the equipment.
Financial Operational costs for equipment should be minimised. These costs come
from:
• Building the equipment: cost of development and costs of components
• The transport and use of consumables
• Operators of the equipment
• Energy consumption of the equipment
With new equipment, investments must be made. If operators have to operate new
equipment, investment in training must be done as well.
Safety and Health Operator safety is an important issue when using equipment.
The QHSE department has the specific task to ensure equipment can be used in a safe
manner. When designing or buying new equipment the safety aspect must be kept in
mind.
3.2 Surface preparation
Prior to the application of the anti-corrosion coating, the surface of the FJ needs to be
cleaned. In this preparation the surface is cleaned and corrosion is removed. Depending
on the type of coating there are different methods with different results. Anchor profile
and surface cleanliness are leading in the choice for which method. Allseas uses two
methods, power wire brushing or grit blasting.
Currently for the application of FBE the surface is always prepared with grit blast-
ing. Grit blasting is the process in which grit is propelled at a high velocity by way of
pressurized air against the substrate. Due to the shape and speed of the grit this has
24
3.2 Surface preparation
an abrasive effect. Depending on the conditions of the FJ the grit blaster is capable of
cleaning up to 20 m2/hr [10].
The goal of grit blasting is to get a surface that is:
• clean: cleanliness of SA 2.5
• rough: anchor profile created of 32-100 microns
These are two important requirements. The cleanliness is defined by the ISO norm
8501-1, where SA 2.5 stands for: Mill scale, rust paint and foreign matter are removed
completely. Any remaining traces are visible only as slight stains or discoloration in
the form of spots or stripes. The anchor profile is a measurement of the roughness of
the surface. This is measured from the lowest point to the highest point of the surface.
In figure 3.1 two examples of surface roughness can be seen.
Figure 3.1: Anchor profiles on substrate; left is shallow, right is deep[1]
Clients of Allseas for the most part specifically request for the grit blaster to be
used as a method of surface preparation if FBE is used as a coating.
3.2.1 Blast media
The blast media used for grit blasting is a mix between shot and grit. Shot particles
have a rounder shape and act as a cleaner. Grit particles have sharper edges that create
the required anchor profile. The correct mix between the two components is important.
Blast media has a limited life time as it deteriorates due to impact forces. This means
that during a project Allseas has to carry sufficient blast media on board the vessel.
25
3. ANALYSIS - EQUIPMENT
Since the blast media that Allseas uses is made of steel particles it has to be stored
under controlled circumstance to prevent corrosion.
A sample of the blast media Allseas uses can be seen in figure 3.2.
Figure 3.2: Sample of blast media: steel shot and grit mix
3.2.2 Blast frame
Allseas developed an automatic frame in which two grit blasting heads are mounted.
The blast heads are positions opposite of each other. Each cleans one half of the FJ.
The heads can rotate and translate around the FJ [11]. This is done with electric
motors which are controlled by a control panel where the speed in both directions can
be pre-set. The frame is presented in figure 3.3.
The blast head is a closed loop system: a combination a nozzle and a suction part.
The nozzle ejects the grit; the suction part surrounding the nozzle removes the grit
mixed with dust particles. The used grit is sucked away to be filter and re-used.
During a noise survey on board PLV Lorelay measurements were taken on multiple
locations in the FL during production. These measurements were taken by a third
party. Results from these measurement show that for the grit blaster noise levels of
97 dB were reached [12]. To protect operators double hearing protection was advised.
The QHSE department within Allseas also expressed their wishes for a reduction of
noise levels from the grit blast equipment.
26
3.2 Surface preparation
Figure 3.3: Grit blast frame in operation on the pipe
In recent projects there were signals that the grit blast process would be critical.
To speed up the cycle time of grit blasting two additional heads were fitted to the blast
frame. This led to lower cycle times but created another problem which is described
in section 3.2.3. Exact cycle times could not be found, but interviews with Allseas
employees confirmed the reduction of cycle times when using four blast heads instead
of two.
3.2.3 Grit handling units
The grit is processed in the grit handling units. These units are made by LTC. Therefore
they are named LTCs. In figure 3.4 an LTC can be seen.
In the LTC dust and rust particles are separated from returning stream of grit. The
cleaned grit is then mixed with the compressed air and fed back to the blast heads in
blast frames.
With the addition of more blast heads, more LTCs were needed. The capacity of
the existing LTCs was not sufficient. This created a problem since the LTCs are placed
in the so called Green Mile where space is already limited.
27
3. ANALYSIS - EQUIPMENT
Figure 3.4: Grit handling unit - LTC
The Green Mile is a hallway situated alongside the FL. It is used by personnel to
reach the different stations. It is also used to store other equipment and consumables.
During pipeline production this normally is a crowded area. In figure 3.5 the green
mile of PLV Solitaire can be seen.
When new equipment is introduced within the PP process the availability of space
is an important matter to take into account.
28
3.3 Coating application
Figure 3.5: Green mile of PLV Solitaire
3.3 Coating application
After the surface preparation mentioned in section 3.2 the anti-corrosion coating can
be applied in the next station. In the coating station, multiple machines are used in a
sequence.
3.3.1 Heating coil
Prior to the application of FBE and HSS it is necessary to heat up the FJ. FBE requires
a temperature in the order of 230 degrees Celsius, while the application of HSS needs
a lower temperature of 180 degrees Celsius.
To achieve this temperature an induction heating coil [2] is used. This coil is wound
around the FJ and a large AC current goes through. The AC current has a frequency
of 2000 to 3000 Hz. The power is in the order of 100 to 500 kW.
The generated heat comes from the eddy currents which flow through the pipe as
a reaction on the electromagnetic field the coil creates. In figure 3.6 a heating coil can
29
3. ANALYSIS - EQUIPMENT
be seen. The thick red leads form the actual coil. The frame encloses the leads around
the FJ.
Figure 3.6: Heating coil
Induction heating is the most efficient and clean way of heating the pipe[13]. The
shape of the coil determines the heating profile generated in the pipe. Due to the
parent coating (factory applied coating) on the joint it is necessary to maintain the
heated zone within the FJ. If the heated zone is greater than the width of the FJ the
parent coating can be damaged by the generated heat. This will result in bad adhesion
of parent coating to the pipe or parent coating to the applied coating. A schematic
overview of the heat profile along the FJ can be seen in figure 3.7.
3.3.2 Fusion-bonded epoxy
Fusion-bonded epoxy is a one-part thermosetting epoxy resin powder that uses heat
to melt, crosslink and adhere to the metal substrate [14]. FBE being one part means
no solvents are involved. During the manufacturing of FBE the resin and the curing
agent are pre-mixed. The reaction between the two is incomplete and continues when
the resin is reheated during the FJC application process.
FBE has a number of properties which are suited for pipeline coating:
• Physical and chemical stability
• Resistance to soil stress and loads
30
3.3 Coating application
Figure 3.7: Heat profile along the field joint[2]
• Adhesion and resistance to impact
• Resistance to cathodic disbondment
When FBE is used as a coating the required thickness can vary between 300 and 500
microns. The choice for the applied thickness depends on the function of the coating.
FBE can be the only coating which will be applied to the FJ. The thickness of choice
will then be in the order of 500 microns. If FBE is applied as an anti-corrosion coating
where more layers of other types of coating will be applied, the thickness will be in the
order of 300 microns.
3.3.3 Coating machine
The coating machine is used to apply coating. The complete coating machine is made
up of two parts. The first part is the automatic spraying frame. The second part is the
fluidised bed, which supplies the frame with FBE powder.
Application frame
The spraying of FBE powder is done by standard spray nozzles. These nozzles are
fitted in a ring that spans over the circumference of the FJ[15]. The ring moves along
31
3. ANALYSIS - EQUIPMENT
the pipe and rotates with increments. The movement is controlled by a program, which
is set to apply the required coating thickness.
In figure 3.8 the frame can be seen.
Figure 3.8: FBE coating frame
Due to the lay-out of the nozzles in the ring there is an overlap in powder streams.
This ensures a full coverage of the FJ, but more FBE powder is sprayed than necessary.
The ring is equipped with an extraction system for the excess powder. The inside of
the ring can be seen in figure 3.9. In the centre the nozzles are placed. On both sides
the extraction hoses are placed. The problem of excess spraying will not be further
investigated in this research. From interviews with Allseas employees it became clear
that this problem does not have a negative effect on cycle times.
Figure 3.9: Inside of the coating ring of the application frame
32
3.4 Conclusions
Fluidised bed
The fluidised bed gives the FBE powder the characteristics of a fluid so it can be applied
to the FJ. A fluidized bed is a drum where pressurised air (2.5 bars) is blown in from
the bottom through a mesh. The mix of air and powder has fluid properties. Via a
venturi pump the powder is transported through hoses to the spray nozzles. When
FBE application starts the operator opens the electromagnetic controlled valves on top
of the barrel so the powder can flow to the nozzle.
Figure 3.10 shows the fluidised bed together with the control panel. The barrel can
be seen behind the control panel in this figure.
Figure 3.10: Fluidised bed together with control panel
3.4 Conclusions
From the analysis of the equipment used for FJC application of FBE a number of
conclusions can be drawn.
For surface preparation grit blasting is an effective method for reaching the de-
sired anchor profile and cleanliness. However there are a number of possibilities for
improvements:
33
3. ANALYSIS - EQUIPMENT
• Noise level of the grit blaster
• Usage of consumables (blast media)
• The required space for supporting equipment (LTCs)
Regarding the heating of the FJ, the principle of induction heating is the most
suitable. A possibility for change could lie in the shape of the coil. If the shape of the
current induction coil could be changed it could be possible to combine the coil with
other process steps.
These possibilities for change will be further explored in the next chapter. There
they will be combined with the conclusions regarding the process from chapter 2 to
find possible alternative application methods.
34
4
Alternative application methods
In this chapter possible alternative application methods are explored. The alternatives
are based on the possibilities for improvement as identified in chapter 2 and chapter 3.
Alternatives for the process of FJC are explored in section 4.1. Alternatives for
surface preparation are given in section 4.2. In section 4.3 alternatives for coating
application are given. In section 4.4 alternatives application methods are formed based
on the findings of section 4.1 , section 4.2 and section 4.3. Finally in section 4.5
conclusions are drawn based on the formed alternative application methods.
4.1 Process alternatives
From the analysis of chapter 2 two possibilities for changes of the process were found.
The order of steps within the process or the combination of steps within the process
could be changed. In this section both options are further explored.
4.1.1 The order of steps within the process
Following the dismantling of the mechanical blast installation there were ideas within
Allseas to re-use the equipment in a different way. The main idea was to salvage the
parts of the old machine and come up with a machine that could blast the cutbacks of
the joints prior to the entry in the FL. In the FL the joint would be blasted again with
the conventional air pressured grit blaster. This would effectively mean a two stage
blasting process. A schematic overview of the process can be seen in figure 4.1.
35
4. ALTERNATIVE APPLICATION METHODS
Pipeline production – two stage blasting
Firing Line
Non distructive testing
WeldingField Joint
CoatingPre-production
Surface preparation – anchor profile
Surface preparation -
clean
Figure 4.1: Pre-blast process
In this process the pre-blast would create an anchor profile. During the processes
of the FL the FJ gets contaminated with weld spatter and NDT water. So therefore
just before heating and coating another blast sequence should be implemented to clean
the FJ again. As the anchor profile was already created this second blast step could
be done quicker. The parts of the old mechanical grit blast machine proved not to be
useful again.
Tests were done with the pre-blasting concept. In these tests the conventional air
pressured grit blaster was used for both stages. In these tests it was concluded that a
time reduction of up to 30 % was achievable[10]. After these tests there has not been
a follow up with the actual application of coating or the research of the possibility of
implementing this.
Therefore the option of pre-blasting should be further explored. It could be possible
to use different methods for creating the anchor profile and cleaning of the field joint.
An important factor that must be incorporated within the pre-blast process is the weld
surface. When the joint is pre-blasted there is an anchor profile on the cut-back. Once
two joints are welded there is no anchor profile on the weld surface. During cleaning in
the FL it should therefore be possible to make an anchor profile.
Possible methods that could be used in the pre-blast process are further explored
in section 4.2.
36
4.1 Process alternatives
4.1.2 Combination of steps within the process
In the application process of FBE there are three steps that can be distinguished,
surface preparation, heat and coating. Due to the layout of each of the FL it is only
possible to combine the heat and coat steps. In the FL the surface preparation station
lies before the tensioner while the heat and coat station lies after the tensioner. Coating
before the tensioner is impossible due to the fact that the tensioner would destroy the
freshly applied coating. Heating before the tensioner would melt the friction pads and
possibly more components of the tensioner itself.
Figure 4.2: FBE application dishes
The possible combination of heat and coat has been tried by Allseas in 2004. A
combined heat and coat machine was designed and built. A schematic view of the
process with the combined heat and coat machine can be seen in figure 4.3.
At that time FBE was applied by oval dishes instead of the now used nozzles. These
oval dishes had an advantage of being low profile and thus could be positioned between
the pipe and the heating coil as can be seen in figure 4.2. The dishes however had a
negative effect on coating quality. They were incapable of applying a constant quality
of FBE coating.
Next to that the dishes deteriorated during operation because of friction between
the FBE powder and the dishes. This resulted in unwanted downtime due to repair and
maintenance. Another downside of this combination was the overspray of FBE which
37
4. ALTERNATIVE APPLICATION METHODS
Field Joint Coating
Sta
tio
n
Pro
cess
st
ep
Coating application 1
Surface preparation
Coating application 2
Combined Heat & coat
machine
Figure 4.3: Combined steps process for heat and coat machine
nested itself on the heating coil and its parts. Mainly affecting the copper contact blocks
that close the current loop of the induction coil as shown in figure 4.4. The build-up
of FBE rendered them useless after a number of cycles, leading to more downtime due
to replacement.
Figure 4.4: Contact blocks of heat and coat machine
Two distinct upsides to this combination however were the elimination of the
change-over time from the heating coil to the coating frame. Next to that the heating
38
4.2 Surface preparation alternatives
coil could be set to a lower temperature as it was not necessary to compensate for the
heat loss during change-over.
Recently Allseas has changed the application of coating from dishes to nozzles. From
interviews with Allseas personnel it became clear that dishes are no longer preferred
as the nozzles perform much better. This makes building a combined heat and coat
machine impossible. Nozzles need a certain distance from the object on which they
spray for a cone to form which applies an even layer of coating. This distance is not
present between the heating coil and the pipe as can be seen in figure 4.5.
Figure 4.5: Spacing between the heating coil and pipe
It can be concluded that with the adaptation of current equipment it is not possible
to build a combined heat and coat machine. For this purpose new methods of heating
and coating application should be further explored.
4.2 Surface preparation alternatives
Based on the conclusions from section 4.1 in this section possible alternative methods
are further explored with respect to surface preparation.
4.2.1 Mechanical blasting
Mechanical grit blasting is a method of surface preparation in which the abrasive media
is propelled to the substrate. This is done by wheel that is driven by either an electric
39
4. ALTERNATIVE APPLICATION METHODS
or a hydraulic motor. The flow of blast media is regulated with an impeller in the
centre of the throwing wheel. The blast media is fed into the impeller through a chute.
A mechanical blaster can be seen in figure 4.6. The main advantage of mechanical
blasting is the simplicity of the machine with respect to a conventional air pressured
grit blaster.
Figure 4.6: Mechanical blasting machine [3]
Allseas has tried to incorporate such a system in 2005. This mechanical blaster was
fitted in the firing line as a permanent installation. It used six electric motors driving
six wheels that propelled the blast media at the FJ. This can be seen in figure 4.7
Although a good anchor profile was created, the system was not a success. Due to
difficulties with reclaiming of the blast media and the stationary character in de FL
in which the pipe could move to a certain degree with respect to ship motions, the
machine was discontinued.
When incorporated before the firing line it can be possible to make a stationary
mechanical blaster where the joint rotates. This approach will result in a simpler
mechanical blaster than the one used in the FL. This would make the mechanical
blaster an option for the pre-blast process.
40
4.2 Surface preparation alternatives
Figure 4.7: Bauhaus mechanical blaster in FL
4.2.2 Laser blasting
Surface treatment with laser is a technique which is mostly applied in the aviation
industry. It is possible to clean metal surfaces with a powerful laser. The principle
behind this is shown in figure 4.8. The pulsating energy of the laser beam makes it
possible to treat the surface area. The amount of substrate material that is removed
depends on the intensity and the frequency of the pulsations of the beam.
This technique was introduced to Allseas in the past through a demonstration. In
the demonstration a limited number of steel plates cut from actual joints were treated
as shown in figure 4.9. The demonstration showed that it would be possible to clean
rusted steel surfaces although it was mentioned that it was not possible to create an
anchor profile.
These conclusions were later backed by a research done by Mitraco, another com-
pany involved in laser blasting. Mitraco did a study into the implementation of laser
blasting within Allseas. In the study it was stated that it was not possible to achieve a
certain anchor profile, but it would still be possible to get the desired coating quality[16].
Another company (SLCR) however claims that an anchor profile can be created.
Due to recent developments in laser technology, faster cleaning process time can also
41
4. ALTERNATIVE APPLICATION METHODS
Figure 4.8: Surface preparation with laser beam
Figure 4.9: Laser treatment of steel piece
be achieved. If that is the case, laser treatment would be an interesting alternative to
incorporate in the firing line as a cleaning method.
4.2.3 Dry Ice blasting
Dry ice blasting is a blasting technique that is based on air pressured blasting where
the steel grit is replaced as the blasting media with dry ice pellets. These pellets are
42
4.2 Surface preparation alternatives
shown in figure 4.10. Dry ice is a solid form of carbon dioxide.
Figure 4.10: Pellets of dry ice used for blasting
The priniciple of dry ice blasting can be seen in figure 4.11. The cleaning effects of
dry ice blasting are realised by:
• Kinetic energy: impact of the dry ice on the substrate
• Explosive sublimation: the rapid expansion of the ice into CO2 gas accelerates
the contaminate removal process
• Thermo shock: the sudden cooling creates an intense thermal tension
• Embrittlement: the material hardens under cooling and can easily fracture and
be removed
This technique has already proven itself in other fields as an effective method of
substrate cleaning [4]. With dry ice it is possible to clean metal substrates. An advan-
tage of this method is the fact that there are no consumables left after impact. The
dry ice pellets sublimate into CO2 gas on impact.
Methods were developed by Cryotech in which an abrasive is added to the flow of
dry ice, making it possible to create an anchor profile. This would make dry ice blasting
suited for replacing the grit blaster. If blasting is only done with dry ice it could be
suitable for use as a cleaning method.
43
4. ALTERNATIVE APPLICATION METHODS
Figure 4.11: Principle of dry ice blasting [4]
4.2.4 Power wire brush
The standard PWB is only suited for the application of HSS and LE as it is not capable
of creating a proper anchor profile for the application of FBE. There are however new
types of brushes available. The wires in these brushes have a bend at the end. This
results in a picking action when the brush hits the substrate. In figure 4.12 such a
brush can be seen.
Figure 4.12: Power wire brush with hardend bent ends [5]
If the picking action of the brush results in the creation of an anchor profile, it
could be suitable for replacing the grit blaster. The pick brush could be placed in the
existing PWB frame, which can be seen in figure 4.13.
44
4.3 Coating application alternatives
Figure 4.13: Power wire brush frame
4.3 Coating application alternatives
Based on the conclusions from section 4.1 in this section possible alternative methods
are further explored with respect to coating application.
4.3.1 Heating coil
As mentioned in chapter 2 the heating coil is very effective. The principle of heating
by induction coil should not be changed. The geometry of the coil however could be
changed.
If a different geometry of the coil is used it might be possible to combine the function
of the heating coil with another function like coating application. Another shape of coil
that can be used is the pancake type coil. The pancake type is similar to the heating
coil in a household cooking plate. Multiple coils could then surround and scan the pipe.
Spray nozzles could be fitted between the pancake coils.
4.3.2 Shockwave induced spraying
Shockwave induced spraying (SISP) is a relatively new solid state spray process. It
was developed in 2001[6]. With SISP it is possible to deposit metals, alloys, cements
and polymers on many types of substrates. Fast opening and closing of a valve creates
45
4. ALTERNATIVE APPLICATION METHODS
shockwaves of gas. Powder is added to the flow of gas which exits the nozzle at a
very high velocity. The powder adheres to the substrate on impact. Because of these
characteristics it might be possible to grit blast and apply coating using the same
equipment. The SISP process does not require any pre-heating of the substrate.
After contact with a supplier it became clear that it has never been tested with
FBE. Due to developing heat in the gun it could get clogged up with reacting FBE. At
the moment no practical experience with the technique is available.
Figure 4.14: Schematic overview SISP process [6]
4.3.3 Low application temperature FBE
Beside conventional FBE powder, manufacturers offer a low application temperature
(LAT) FBE. This FBE can cure at a lower temperature of 180 degrees Celsius than
standard (230 degrees Celsius). This means less time is needed for the heating coil to
heat up the FJ and for the FBE to cure.
From interviews with coating engineers and Innovations personnel it became clear
that this option has not yet been fully explored. The price of LAT FBE could play an
important part in that decision. Compared to normal FBE it is twice as expensive.
The higher costs of LAT FBE could be justified if the use would lead to shorter
overall process times.
46
4.4 Choice of alternatives
4.4 Choice of alternatives
With all the alternatives explored it is now possible to combine the alternatives for the
process with the alternatives for the process steps. This gives the following combina-
tions of alternatives;
The order of steps within the process:
• Pre-blasting with mechanical blasting followed by cleaning with laser or dry ice
• Pre-blasting with grit blasting followed by cleaning with laser or dry ice
Combination of steps within the process:
• Shockwave Induced Spray Painting
• Combined Heat & Coat machine with alternative heating coil
Alternative methods within the process step:
• Dry ice with grit blasting instead of grit blasting
• Pick brush instead of grit blasting
• LAT FBE instead of FBE
• Surface treatment with laser blasting instead of grit blasting
The most promising alternatives can be found when the requirement found in chap-
ter 2 and chapter 3 are applied.
It can be concluded that the following alternatives are not a possible alternative at
this moment:
• Pre-blasting with grit blasting followed by cleaning with laser or dry
ice. This alternative would transfer the existing problems in the FL with the grit
blaster to the location of pre-blasting.
• Shockwave Induced Spray Painting. This technique has not yet been proven
with the use of FBE. Incorporation of this technique would require more funda-
mental research.
47
4. ALTERNATIVE APPLICATION METHODS
• Combined Heat & Coat machine with alternative heating coil. This al-
ternative would require more research into the different shapes of heating coils and
alternative methods of applying FBE. This requires more fundamental research.
• Pick brush instead of grit blasting. From experience with the regular PWB
frame it is known that the brushes must be changed regularly. This means down-
time and lower overall process times. This means that this alternative is not
suited for further research.
4.5 Conclusions
Based on the combined alternatives of the process and the equipment there are a number
of alternatives that should be further researched:
• Pre-blasting with mechanical blasting followed by cleaning with laser or dry ice
• Dry ice with grit blasting instead of grit blasting
• Low application temperature FBE instead of FBE
• Surface treatment with laser blasting instead of grit blasting
To further asses their possibilities within the FJC process more data is required.
For each of these alternatives it must be know what the process times are and if it
is possible to obtain a quality coating. To acquire this data, practical tests must be
performed. These tests are described in the next chapter.
48
5
Tests
In the previous chapter alternative application methods were pre-selected. The pre-
selection was based on requirements that originated from literature research and in-
terviews with suppliers and Allseas employees. In this chapter these alternatives are
further tested on criteria which where estimated beforehand but can be confirmed with
the help of practical tests.
Section 5.1 describes the goal of the tests. In section 5.2 the method of testing is
explained. In section 5.3 the validation of the tests is discussed. In section 5.4 the
results of the tests are presented. Finally in section 5.5 conclusions are drawn based
on the test results.
5.1 Goal
The goal of the tests is to get an idea of the performance of the alternatives with respect
to the existing FJC process. The research and selection of alternatives was based on
literature and discussions with suppliers. This resulted in a number of claims and ideas.
These can be summarised as follows:
• It is possible to create an anchor profile with laser blasting
• Mechanical blasting is faster than grit blasting
• Two stage blasting results in lower overall process times
• Two stage blasting results in a coating of an acceptable quality level for mechan-
ical pre-blasting and laser cleaning
49
5. TESTS
• Two stage blasting results in a coating of an acceptable quality level for mechan-
ical pre-blasting and dry ice cleaning
• LAT FBE results in a coating of an acceptable quality level
• Dry ice blasting with the addition of grit is faster than grit blasting
• Dry ice blasting with the addition of grit results in a coating of an acceptable
quality level
The main goal of these tests is to see whether these claims hold true or not.
5.2 Method
To reach the goal of these tests a practical test was designed. In this test the actual
process of FJC was replicated as close as possible.
5.2.1 Test subjects
During PQTs whole joints are used or pieces cut from joints. In order to simplify
testing the joints are replaced by flat metal plates. The size of the plates was based on
the standard for laboratory tests as prescribed in ISO norm 21809-2. In the norm the
minimum dimensions of 100 x 100 x 6.3 mm are prescribed. Based on availability of
steel plates for this test, plates with dimensions of 100 x 100 x 8 mm were used. Test
plates were cut from the same plate. This ensures the same grade of steel was used for
all the plates.
The plates were treated to simulate the condition of joints as mentioned in sec-
tion 2.2.1. They were blasted to SA 2.5 to remove the mill scale. They were then
sprayed with water and left outside for the duration of two weeks. During this time
the surface of the plates started to corrode again. This can be seen in figure 5.1
This resembles the condition that joints can be in before entering production. Joints
are sometimes stored for a period of time on a yard before leaving on a supply vessel to
the PLV. This exposes the bare ends of the joint to the elements, resulting in corrosion.
In figure 5.2 the corroded test plates can be seen after the duration of two weeks.
50
5.2 Method
Figure 5.1: Test plates blasted and put outside
Figure 5.2: Corroded test plates
5.2.2 Setup
The test setup was designed and built in-house. Its purpose was to replicate the actual
coating process as close as possible. For a controlled movement the linear motor of
the blast frame was used. This linear motor can be controlled with a control panel.
On the control panel the speed and distance that the motor travels can be set. This
type of control panel is also used during production on the PLVs. The motor is fitted
with a clamp. In this clamp either the nozzle for the application of FBE powder can
be fitted or the grit blaster head. With the FBE nozzle connected the fluidized beds
which control the flow of FBE powder can be switched on and off with the control
panel. With the grit blaster head connected, the LTC grit handling unit is connected
51
5. TESTS
to the panel. The flow of grit can then be controlled. The finished test setup can be
seen in figure 5.3
Figure 5.3: Test setup
To hold the test plates in place a jig was constructed. In this jig the test plate lies
enclosed and an even surface is created. To heat the plates an industrial oven was used.
This temperature of the oven could be set with an accuracy of 1.0 degrees Celsius. The
initial plan for heating the plates was to use an induction cooking plate. Practical
problems with the plate however prevented this, as the plate failed during validation
tests.
5.2.3 Execution
In total nine batches of six plates were made. Each batch underwent the following
steps:
Batch A Current process: grit blasting - heat - FBE
Batch B Current process with delay: Grit blasting - one day delay - heat - FBE
Batch C Current process with LAT FBE: Grit blasting - heat - LAT FBE
Batch D Mechanical blasting - heat - FBE
52
5.2 Method
Batch E Mechanical blasting - FL conditions - laser cleaning - heat - FBE
Batch F Mechanical blasting - FL conditions dry ice cleaning - heat - FBE
Batch G Dry ice + grit blasting - heat - FBE
Batch H Laser (quality) blasting - one day delay - heat - FBE
Batch I Laser (time) blasting - one day delay - heat - FBE
Each of the individual steps was done in a certain manner. Grit blasting was done
in the test setup. The grit blast head could automatically move over the plate in the
X-direction. The Y-direction was manually controlled by an operator. Air pressure
was set at 8 bars. Figure 5.4 shows the grit blast head fitted in the test setup.
Figure 5.4: Grit blast head fitted in test setup
Heating was done in the oven. For normal FBE the oven was set at 240 degrees
Celsius. For LAT FBE the oven was set at 190 degrees Celsius. Plates were then put
in the oven for 15 minutes. When placed in the coating frame, test plate temperatures
were then 230 degrees Celsius for the normal FBE batch. For the LAT FBE batch the
test plate temperature was 180 degrees Celsius. In figure 5.5 the plates can be seen
laying in the oven.
FBE and LAT FBE application was done in the test setup. In figure 5.6 the FBE
powder application nozzle can be seen as fitted in the test setup. The heated test plates
were placed in the jig in the test setup. The FBE nozzle was moved automatically over
53
5. TESTS
Figure 5.5: Test plates in industrial oven
the test plate. Settings of the fluidised beds were the same as during production (2.5
bars). The nozzle made four passes over the plate. Plates were taken out of after 60
seconds with a spatula. They were then placed on racks for further curing.
Figure 5.6: FBE application nozzle fitted in test setup
One day delay is explained in section 5.3.2
Mechanical blasting was done by manually moving the machine over plate. The test
plate was placed in the jig. The mechanical blaster then made one pass back and forth
over the test plate. The test plate was then turned 180 degrees and again one pass
54
5.2 Method
back and forth was made. The jog was turned because of two reasons. The throwing
wheel propels the blast media to one side due to layout of the wheel and the direction
it spins. To guarantee both edges of the test plate receive the same treatment the jig
was turned. The jig and mechanical blaster can be seen in figure 5.7.
Figure 5.7: Mechanical blaster test setup
FL conditions were a simulation of the effects of heating the pipe during welding
and cooling it again with NDT coupling water. With two-stage blasting the FJ is prone
to corrosion between the first and the second blast step. It was expected that the NDT
water would induce the corrosion process. This was simulated by heating the test plates
in the oven to 90 degrees Celsius. Then they were sprayed with water and laid to rest
for the duration of 10 minutes. This can be seen in figure 5.8.
Dry ice cleaning was done manually. The dry ice blast gun was manually moved
over the test plate. The test plate was fitted in the jig. Air pressure was set at 8 bars.
For the dry ice plus grit surface treatment the blast gun was manually moved over
the test plate. The test plate was fitted in the jig. Air pressure was set at 8 bars. The
valve controlling the feed of Cryosand was opened halfway. In figure 5.9 the method of
dry ice blasting can be seen.
Each of the three variants of laser treatment were done one the same machine.
The test piece was placed in a jig with a set distance to the laser as can be seen in
figure 5.10. The laser was set to certain settings for each of the three variants. For the
leaser cleaning the fastest speed was used. For laser quality the laser was set to make
55
5. TESTS
Figure 5.8: Simulating FL conditions with heat and NDT water
an anchor profile of 100 micrometre. For the laser time variant the laser was set to
make a lower anchor profile and thus aiming for a faster cycle time.
5.2.4 Measurements
During tests the following measurements were taken using the following equipment:
Pre-test:
• Temperature - Fluke thermometer
• Dew point - Elcometer dew point meter
Surface preparation noise level (safety):
• Surface cleanliness - Elcometer 125 Surface Comparator
• Surface profile - Testex tape with Elcometer micrometre
• Time - Stopwatch
56
5.2 Method
Figure 5.9: Dry ice blasting method
Figure 5.10: Laser treatment test setup
• Noise - Rion NL20 noise level meter
Coating application:
• Temperature - Fluke thermometer
• Coating thickness - Elcometer 456 thickness meter
57
5. TESTS
Destructive tests:
• Adhesion - tape measure
• Pull-off force - Elcometer 506 pull-off tester
5.3 Validation
Before the main tests a number of validation tests have to be performed to check
whether the test devices and methods are performing as expected. Next to that some
batches were made only for comparison reasons.
5.3.1 Setup
Extra test plates used to test the test setup:
• Set grit blaster (speed, position)
• Set mechanical blaster (speed, position)
• Coating thickness
• Pre-set temperature of the oven
• Cooling (cure) of test plate
Once the test setup was working two batches of plates were done. These batches
were:
• Mechanical blasting
• Grit blasting
Both batches act as the baseline measurement. The other batches can be compared
against them.
58
5.4 Results
5.3.2 Delay
Three batches of test plates were laser blasted. This could not be done at the test site
in IJmuiden but was done at SLCR in Germany. Because of practical reasons it was
not possible to coat the plates directly after laser blasting. This was done the next day.
It was expected that this delay would have negative effects on the surface. If moisture
or other contaminates come in contact with the surface, the corrosion process could
start.
To minimize these effects the plates were individually wrapped in aluminium foil.
This was also the practice of SLCR if they would have to ship laser blasted samples.
The batch was then packed in thick PE bags which were sealed. To eliminate moisture,
sachets of silica gel were also put in the bag.
To check whether this delay affects coating quality, a batch that was grit blasted
was treated in the same manner. The batch was grit blasted, packed and put aside for
24 hours. After 24 hours it was heated and coated.
5.4 Results
The results of the measurements and the quality tests are given in the next sections.
The results are split up in tree blocks; Surface preparation, coating application and
destructive tests.
5.4.1 Surface preparation
These measurements were taken during surface preparation.
Cleanliness
Cleanliness cannot actually be measured. It is assessed with the Elcometer 125 Surface
Comparator. This disc has four different samples of surface cleanliness conditions. The
disc is hold against the treated surface. The one closest to the actual surface condition
gives the measured value. In figure 5.11 the assessment of a mechanical blasted test
plate can be seen.
For each of the surface preparations, the surface cleanliness could be compared to
SA 2.5 in my opinion. Exemptions are the two laser treatments (quality and time). I
was not able to make a good comparison with either of the samples on the disc.
59
5. TESTS
Figure 5.11: Surface comparator with mechanical blasted test plate
Because of the subjective nature of this test the results must be seen as indicative
results. This test was done for the sake of comparison between the different surface
treatment alternatives.
Anchor profile
The anchor profile after each of the surface treatments was measured with Testex tape
and an Elcometer micrometre. The Testex tape was rubbed against the treated surface.
This leaves an indentation in the tape. This indentation is the height of the surface
profile. This height can be measured by pressing the Testex tape in the Elcometer
micrometre as can be seen in figure 5.12. The measurements are given in table 5.1.
Because of the limited availability of Testex tapes during tests it was only possible
to do one measurement per batch. The measured values therefore must be interpreted
is indicative results.
A visual inspection of the treated surfaces showed an interesting comparison be-
tween the surfaces treated with grit and those with laser. Laser treatment gives a very
ordered anchor profile as can be seen in figure 5.14. The other methods show a chaotic
(random) profile. An example of this can be seen in figure 5.13.
60
5.4 Results
Surface treatment [microns]
Grit blasting 100
Mechanical blasting 80
Dry ice cleaning 70
Laser cleaning 74
Dry ice with grit blasting 68
Laser blasting (quality) 100
Laser blasting (time) 65
Maximum allowable 100
Minimum allowable 32
Table 5.1: Anchor profile measurements
Figure 5.12: Measuring of the Testex tape
Time
During each of the surface preparation methods the time was monitored. Because each
of the test plates has the same dimension, the times can be compared. In table 5.2 the
times are given.
Noise
Because of QHSE requirements the noise levels for each of the surface treatment meth-
ods was measurement. Noise level measurements during laser treatment were not taken
61
5. TESTS
Figure 5.13: Surface after mechanical blasting
Figure 5.14: Surface after laser blasting
as this method produces no abnormal noise levels. During laser tests no hearing pro-
tection was needed. The results can be seen in table 5.3.
Noise levels where measured from a distance of 1.0 meter as can be seen in fig-
ure 5.15. With respect to the result of the dry ice measurements a remark must be
made. There was no suction brush surrounding the nozzle as is the case with the grit
blaster. It could be possible that this would have a dampening effect. For safety reasons
it was not possible to measure the grit blaster without the brush or the dry ice nozzle
with a brush.
62
5.4 Results
Surface treatment T[sec] [m2/hr] [hr/m2] [min/m2]
Grit blasting 21 1.71 0.58 35
Mechanical blasting 68 0.53 1.89 113
Dry ice cleaning 36 1.00 1.00 60
Laser cleaning 20 1.80 0.56 33
Dry ice with grit blasting 14 2.57 0.39 23
Laser blasting (quality) 187 0.19 5.19 312
Laser blasting (time) 94 0.38 2.61 157
Table 5.2: Cycle time measurements
Surface treatment dB
Grit blasting 108
Mechanical blasting 98
Dry ice cleaning 112
Dry ice with grit blasting 117
Table 5.3: Noise level measurements
Figure 5.15: Test setup Noise level measurement
5.4.2 Coating application
The following measurements were taken directly after coating application.
Observation
According to ISO 21809-2 the coating must look uniform, feel smooth and free of
orange peel. This was the case for all the batches. This was checked and confirmed by
63
5. TESTS
experienced coating applicators on site. An example can be seen in figure 5.16
Figure 5.16: Cured coating on a test plate
Thickness
The coating thickness was measured for every plate. Measurements were taken on 9
points per plate. The average of all the measurement per batch is given in table 5.4.
Batch [microns]
A: Current process 426
B: Current process with delay 444
C: Current process with LAT FBE 414
D: Mech blasting 392
E: Pre-blast mech + laser cleaning 476
F: Pre-blast mech + dry ice cleaning 443
G: Dry ice with grit blasting 458
H: Laser blasting (quality) 453
I: Laser blasting (time) 456
Maximum allowable 500
Minimum allowable 300
Table 5.4: Dry film thickness measurements
Measurements were taken with the Elcometer 456 thickness meter. The meter was
64
5.4 Results
calibrated before use.
5.4.3 Destructive tests
After the coating of all the batches was fully cured, the quality of the coating was tested
with destructive tests. The tests were done in the below presented order.
Adhesion
The adhesion test is a test from ISO norm 21809-3. Two cuts were made in the coating
with a sharp knife. These two cuts have to form an X with an angle of approximately 30
degrees at the intersection point. A levering action with the knife was then performed
at the intersection of the cuts. The knife was used to try to prise the coating off. In
figure 5.17 an example of the adhesion test on one of the plates is given. The amount
of coating that came of was then measured. For each batch this test was performed on
two different plates. This was done three times per plate. For all of the batches the
amount of coating that came loose was no less than 2mm. All batches therefore were
considered as a pass.
Figure 5.17: Adhesion test - resistance to removal
65
5. TESTS
Pull-off
Pull-off tests were performed with the Elcometer 506 pull-off tester. During a pull-off
test aluminium dollies are glued to the coating. A device then tries to pull off the dolly.
In figure 5.18 the pull-off tester and dollies can be seen.
Figure 5.18: Pull-off tester and 20mm dollies glued to test plate
If the dolly cannot be pulled of when a minimum amount of 10 MPa of pulling force
is exerted on the dolly it is considered a pass. Of the glue fails below 10 MPa the test
is invalid. If the coating fails below 10 MPa, the coating is of bad quality. Of all the
coating comes loose with the dolly it is called an adhesion failure. Table 5.5 gives the
results for the pull-off tests with 20mm dollies.
For all measurements there was a glue failure. But al pull-off force measurements
were above 10 MPa. Based on these results all coatings can be considered a pass.
66
5.4 Results
Batch MPa
A: Current process 24.5
B: Current process with delay 14.0
C: Current process with LAT FBE 23.0
D: Mech blasting 18.5
E: Pre-blast mech + laser cleaning 20.5
F: Pre-blast mech + dry ice cleaning 17.5
G: Dry ice with grit blasting 14.3
H: Laser blasting (quality) 19.5
I: Laser blasting (time) 17.3
Minimum required 10.0
Table 5.5: 20mm dolly pull-off test measurements
Because there was only one pull-off test done per batch these results must be interpreted
as indicative results.
To gather more results 14mm dollies were also used to perform pull of tests. With
these dollies a better quality adhesive was used in order to see if a coating or adhesion
failure could be found. With 14mm dollies it was possible for the pull-off device to
exert more pulling force. The results of these tests can be seen in table 5.6.
(c=coating, a=adhesive, m=mix) mid 2 3
Batch MPa fail MPa fail MPa fail
A: Current process 31.5 c 42,5 c 41,0 m
B: Current process with delay 36.0 c 36.5 c 37.0 c
C: Current process with LAT FBE 45.5 c 48.0 a 48.0 a
D: Mech blasting 48.0 c 47.5 a 40.0 m
E: Pre-blast mech + laser cleaning 26.0 c 35.5 c 36.0 c
F: Pre-blast mech + dry ice cleaning 34.5 c 42.0 c 32.0 c
G: Dry ice with grit blasting 30.0 c 38.0 c 39.5 m
H: Laser blasting (quality) 35.0 c 42.0 c 37.0 c
I: Laser blasting (time) 48.0 m 47.0 a 47.5 m
Minimum required 10.0 10.0 10.0
Table 5.6: 14mm dolly pull-off test measurements
67
5. TESTS
From the results it can be seen that not a single pull-off was below the minimum
pull-off force of 10 MPa. Also none of the tests were a failure of adhesion between
substrate and coating. Therefore it can be concluded that based on these measurements
all coatings can be considered a pass.
During the 14mm pull-off tests three failure types were reached on a single test
plate. These can be seen in figure 5.19. Because these failures were not am adhesion
failure en the exerted pull-off force was well above the minimum of 10 MPa this plate
was also considered a pass.
Figure 5.19: Pull-off results 14mm: three failure types for batch D
Cathodic disbondment
CD tests were performed by Element in Amsterdam. Element is an independent test
lab. To test the cathodic disbondment the procedure as described in ISO 21809-3
Annex C has been followed.
A hole was drilled in the centre of the test plate through the coating. A plastic
cylinder was then glued onto the plate. The cylinder was filled with a solution of 3
% sodium chloride in distilled water. A 0.8 mm. platinum wire electrode was hanged
68
5.4 Results
in the cylinder above the drilled hole. The plate itself was earthed to a power supply
which put a voltage of 3.5 V on the platinum electrode. The setup then was heated
to 65 degrees Celsius and kept in that state for 24 hours. The setup with all the nine
plates can be seen in figure 5.20.
Figure 5.20: Cathodic disbondment test setup at Element, Amsterdam
After the period of 24 hours the plates were taken out and all the equipment was
removed. Then 8 cuts were made with a sharp knife. The knife was used to try to prise
the coating off. In figure 5.21 the disbondment of the coating of one of the plates can
be seen.
According to the ISO norm no more than an average of 8 mm. of coating should
come loose. This is measured from the edge of the drilled hole to the edge of the
remaining coating. The results can be seen in table 5.7. It can be seen that al plates
are well below the maximum allowable loss of coating. However the results must be
interpreted as indicative results, as the CD test was performed on just one test plate
per batch.
69
5. TESTS
Figure 5.21: Cathodic disbondment on test plate
Batch [mm]
A: Current process 1.250
B: Current process with delay 1.625
C: Current process with LAT FBE 1.000
D: Mech blasting 0.125
E: Pre-blast mech + laser cleaning 0.125
F: Pre-blast mech + dry ice cleaning 1.125
G: Dry ice with grit blasting 1.000
H: Laser blasting (quality) 0.125
I: Laser blasting (time) 0.000
Maximum allowable 8.000
Table 5.7: Cathodic disbondment test results
5.5 Conclusions
To conclude this chapter the most important test results are summarised in table 6.1.
On the basis of the summarised test results a number of conclusions can be drawn;
• All of the processes resulted in a coating with a quality level that passed the tests.
• The delay of one day did not have an effect on the passing of the quality level
tests.
70
5.5 Conclusions
• For all surface preparation methods it was possible to create an anchor profile of
at least 32 microns.
• It was possible to create an anchor profile with laser blasting, but this took a
longer time than with any of the other surface preparation methods.
• Cleaning with dry ice takes a longer time than grit blasting and the noise level is
higher
• Dry ice blasting with grit takes a shorter time than grit blasting but the noise
level was the highest of all the surface preparation methods.
Anchor Noise Capacity Dry film Quality
Batch [microns] [dB] [min/m2] [microns]
A: Current process 100 108 35 426 pass
B: Current process with delay 100 108 35 444 pass
C: Current process with LAT FBE 100 108 35 414 pass
D: Mech blasting 80 98 113 392 pass
E: Pre-blast mech + laser cleaning 74 98 33 476 pass
F: Pre-blast mech + dry ice cleaning 70 112 60 443 pass
G: Dry ice with grit blasting 68 117 23 458 pass
H: Laser blasting (quality) 100 - 312 453 pass
I: Laser blasting (time) 65 - 157 456 pass
Table 5.8: Test results summarised
Regarding the scale of the test equipment there are some remarks to be made with
respect to the obtained test results. For mechanical blaster a longer time was needed
to clean the test piece than with grit blasting. The mechanical blaster however was
a small scale test unit, where the grit blaster was the full scale unit as used during
production. For the actual use in production a larger mechanical blast setup could be
obtained. According to the supplier of such equipment it is possible to create an anchor
profile in a shorter time than with grit blast equipment. This should be verified with
tests using such equipment.
For laser blasting a similar remark can be made. During tests a laboratory scale
laser was used. For actual production higher powered laser equipment is available.
According to the supplier of this equipment faster process times than those of the test
should be available. This however should be verified with test using such equipment.
71
5. TESTS
The use of LAT FBE resulted in a coating of a level that passed the quality tests.
Because an industrial oven was used it was not possible to get data regarding process
times, which could be used for comparison. A lower overall process time can be expected
with the use of LAT FBE. Exact data should be verified with further tests using a
heating coil, which would make comparison possible.
Based on the above conclusion and with the mentioned remarks in mind there are
three processes that can be identified as possible alternatives for the application process
of FBE as field joint coating:
• Mechanical pre-blasting followed by cleaning with laser in the FL
• Dry ice with grit blasting in the FL
• The use of LAT FBE
These alternatives could lead to lower overall process times while maintaining the cur-
rent quality level of coating.
72
6
Conclusions & Recommendations
In this closing chapter all the conclusion that were made during the research are gath-
ered and summarised. The conclusions are presented in section 6.1. Based on the
conclusions a number of recommendations can be made. They are given in section 6.2.
6.1 Conclusions
From the analysis of the current method of pipeline production it was concluded that
there are three possibilities for changes to the process that could have an effect on the
overall process time.
• The order of steps within the process
• Combination of steps within the process
• Alternative methods within the process step
From the analysis of the equipment used for FJC application of FBE a number of
conclusions were drawn.
For surface preparation grit blasting is an effective method for reaching the de-
sired anchor profile and cleanliness. However there are a number of possibilities for
improvements:
• Noise level of the grit blaster
• Usage of consumables (blast media)
73
6. CONCLUSIONS & RECOMMENDATIONS
• The required space for supporting equipment (LTCs)
Regarding the heating of the FJ, the principle of induction heating is the most
suitable. A possibility for change could lie in the shape of the coil. If the shape of the
current induction coil could be changed it could be possible to combine the coil with
other process steps.
Based on the combined alternatives of the process and the equipment it was con-
cluded that there are a number of alternatives that should be further researched:
• Pre-blasting with mechanical blasting followed by cleaning with laser or dry ice
• Dry ice with grit blasting instead of grit blasting
• Low application temperature FBE instead of FBE
• Surface treatment with laser blasting instead of grit blasting
The combined alternatives where further researched with practical tests. The test
results are summarised in table 6.1.
Anchor Noise Capacity Dry film Quality
Batch [microns] [dB] [min/m2] [microns]
A: Current process 100 108 35 426 pass
B: Current process with delay 100 108 35 444 pass
C: Current process with LAT FBE 100 108 35 414 pass
D: Mech blasting 80 98 113 392 pass
E: Pre-blast mech + laser cleaning 74 98 33 476 pass
F: Pre-blast mech + dry ice cleaning 70 112 60 443 pass
G: Dry ice with grit blasting 68 117 23 458 pass
H: Laser blasting (quality) 100 - 312 453 pass
I: Laser blasting (time) 65 - 157 456 pass
Table 6.1: Test results summarised
On the basis of the summarised test results a number of conclusions were drawn;
• All of the processes resulted in a coating with a quality level that passed the tests.
• The delay of one day did not have an effect on the passing of the quality level
tests.
74
6.2 Recommendations
• For all surface preparation methods it was possible to create an anchor profile of
at least 32 microns.
• It was possible to create an anchor profile with laser blasting, but this took a
longer time than with any of the other surface preparation methods.
• Cleaning with dry ice takes a longer time than grit blasting and the noise level is
higher
• Dry ice blasting with grit takes a shorter time than grit blasting but the noise
level was the highest of all the surface preparation methods.
The final conclusion of this research should answer the research question as stated in
chapter 1: ’What are the possibilities to change the current process of field joint coating
application, in order to achieve faster cycle times while maintaining the current coating
quality, while taking into account requirements for changes to the process?’
Three alternatives can be identified as possible alternatives for the application pro-
cess of FBE as field joint coating that could lead to lower overall process times while
maintaining the current coating quality:
• Mechanical pre-blasting followed by cleaning with laser in the FL
• Dry ice with grit blasting in the FL
• The use of LAT FBE
6.2 Recommendations
Before the alternatives for FJC application can be implemented more research is needed.
First a research should be conducted into which of these three alternatives would be
the most promising or worthwhile to pursue.
For each of the separate alternative methods a number of further research topics
can also be identified;
Mechanical pre-blasting followed by cleaning with laser in the FL:
• Research the possibilities for the incorporation of a mechanical blaster in the
bevelling station
75
6. CONCLUSIONS & RECOMMENDATIONS
• Further test the use of laser equipment in the current process and with the current
equipment
• Investigate possible safety issues related to the use of laser equipment
Dry ice with grit blasting:
• Research the logistics of dry ice pellets
• Research the possibility of producing of dry ice on board the vessels
• Execute more tests with different types of blast media added to the dry ice
• Research the possibilities for the reduction of noise levels
• Investigate the possible safety issues with CO2
The application of LAT FBE:
• Research the possible time reduction when applying LAT FBE with current equip-
ment
• Research the cost aspect of applying LAT FBE powder with respect to the re-
duction of time (cost versus gain)
76
Bibliography
[1] Norton Sandblasting Equipment. Norton coroporate website, 2013. URL http:
//www.nortonsandblasting.com/nsbabrasives-anchr.html. xi, 25
[2] Kirill Kavelin. Fbe induction heating machine users manual. Technical Report
IN-300-02-R-06, Allseas Engineering BV, 01 2008. xi, 29, 31
[3] Wheelabrator. Wheelabrator autoblast wheel, 2013. URL http://www.
wheelabratorgroup.com/en/sites/wheelabrator_plus/content/parts_and_
services/wheelblast_parts/wheelabrator_autoblast_wheel.aspx. xii, 40
[4] HoekLoos. Droogijsstralen met het oog op het milieu, uw gemak en efficiency.
2010. xii, 43, 44
[5] Tool Supermarket. Commercial website, 2013. URL http://www.
toolsupermarket.co.uk/product-detail.asp?PMPartID=70502. xii, 44
[6] Julio Villafuerte M.A.Sc P.h.D P.Eng. Shockwave induced spraying: A new solid-
state spraying process. Technical report, CenterLine (Windsor) Ltd., Windsor,
Ontario, Canada,, 2009. xii, 45, 46
[7] Allseas Group S.A. Allseas coroporate website, 2012. URL http://http://www.
allseas.com/uk. 2
[8] Allseas Engineering BV. Introduction to pipelaying. Allseas Engineering BV, Delft,
the Netherlands, 2004. 2, 3, 16
[9] Jeroen Regelink. Scope of work for the heat coat machine. Technical Report
TBA-RD-11-R01, Allseas Engineering BV, 12 2004. 6
77
BIBLIOGRAPHY
[10] Erik Kramer. Pre blast test results. Technical Report IN-300-02-M-51-01, Allseas
Engineering BV, 10 2010. 25, 36
[11] Harm Reinink. Grit blasting frame mk1 users manual. Technical Report IN-300-
02-R-11, Allseas Engineering BV, 03 2011. 26
[12] Coffey Environments. Noise survay plv lorelay. Technical Report ENAU-
PERT03398AA, Coffey Environments, 07 2012. 26
[13] Author. Induction Heating in Industry. Publisher, USA, 1952. 30
[14] J.A. Kehr. Fusion-Bonded Epoxy (FBE): A Foundation for Pipeline Corrosion
Protection. NACE International, 2003. ISBN 1-57590-148-X. URL http://books.
google.nl/books?id=Pl9DOwAACAAJ. 30
[15] Richard Martinu. Users manual fbe coating machine series ii. Technical Report
IN-300-02-R-53-A, Allseas Engineering BV, 09 2011. 31
[16] Mitraco. Haalbaarheid laserreiniging allseas engineering. Technical report, Mi-
traco, 08 2011. 41
78