Tender Document - Indore - MPAKVN
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of Tender Document - Indore - MPAKVN
1
M.P. INDUSTRIAL DEVELOPMENT CORPORATION
LTD., REGIONAL OFFICE, INDORE (A Government of Madhya Pradesh undertaking)
(FIRST CALL)
Tender Document FOR
Design , Supply, Erection, Testing & Commissioning of 200
KLD Common Effluent Treatment Plant (CETP) based on ZLD
Process, on Turn-key basis and its Operation and Maintenance
for five years at I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore (M.P.)
THE EXECUTIVE DIRECTOR
M.P. INDUSTRIAL DEVELOPMENT CORPORATION LTD.,
REGIONAL OFFICE, INDORE (M.P.)
(A Govt. of Madhya. Pradesh undertaking)
“ATULYA IT PARK”, FIRST FLOOR,
NEAR CRYSTAL IT PARK, KHANDWA ROAD, INDORE (M.P.)
Phone: 0731-2970363, 2970611 Fax : 0731-2972629
E-mail : [email protected]
2
M.P. INDUSTRIAL DEVELOPMENT CORPORATION LTD.,
REGIONAL OFFICE, INDORE
(A GOVT. OF MADHYA PRADESH UNDERTAKING)
NAME OF WORK : Design , Supply, Erection, Testing & Commissioning
of 200 KLD Common Effluent Treatment Plant (CETP) based on ZLD
Process, on Turn-key basis and its Operation and Maintenance for five years
at I/A Confectionary Cluster, in front of IIM Indore Village Rangwasa,
Indore (M.P.)
TENDER NOTICE NO :- 19321 Dated 31.03.2022
DATE : 31.03.2022
Authorized Signatory
Authorized Signatory
3
M.P Industrial Development Corporation Ltd.
Regional Office, Indore
Tender Document
For Lump-Sum Rate Tender Office of the : Executive Director,
M.P Industrial Development Corporation Ltd,
Regional Office, Indore
NIT Number and Date : No./MPIDC/R.o./IND/2022/19321 Dt. 31.03.2022
Agreement Number and Date :
Name of Work: Design, Supply, Erection, Testing &
Commissioning of 200 KLD Common
Effluent Treatment Plant (CETP) based on
ZLD Process, on Turn-key basis and its
Operation and Maintenance for five years at
I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore (M.P.)
Name of the Contract agency :
Probable Amount of Contract
(Rs. In Figure) : Rs. 4.00 Crs.
(Rs. In Words) : Rs. Four Crore Only.
Contract Amount
(Rs. In Figure) :
(Rs. In Words) :
Stipulated Period of Completion : 6 (six) months for Design Construction, 3
months Trial Run, and 5 years for Operation
and Maintenance.
4
Appendix 2.10
Tender Document
Table of Contents
Section No/
Sheet No.
No
Particulars
Section 1 NIT
Section 2 Instructions to Bidders (ITB)
Bid Data Sheet
Annexure -A to M
Section 3 Part - I General Conditions of Contract (GCC)- Table of Clauses
General Conditions of Contract (GCC)
Contract Data
Annexure - N to W
Part - II Special Conditions of Contract (SCC)
Section 4 Bill of Quantities (BOQ)
Section 5 Agreement Form
Sheet : 1 Break up schedule for payment
Sheet : 2 Proforma for Application for Extension of Time Period
Sheet : 3 List of Acceptable Makes of Equipment
Sheet : 4 Basic Design Criteria
Sheet : 5 Scope of work- construction, operation & maintenance of CETP
Sheet : 6 Operation, Maintenance and Requirement
5
M.P Industrial Development Corporation Ltd.
Regional Office, Indore
Notice Inviting e-Tenders (First Call)
No. MPIDC/R.O.I./TECH/2022/19321 Dated: 31/03/2022
Online Lump-Sum rate tender for the following works is invited from registered
Contract agencys or firms of repute having eligibility criteria as given in tender documents:
S. No. Name of Work District Estimated
Amount
(Rs. in
Crores)
Completion
Period
(months)
1
Design, Supply, Erection, Testing &
Commissioning of 200 KLD Common
Effluent Treatment Plant (CETP) based on
ZLD Process, on Turn-key basis and its
Operation and Maintenance for five years at
I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore (M.P.)
Indore Rs. 4.00
Crores
6 (six) months
for Design
Construction,
3 months Trial
Run, and 5
years for
Operation and
Maintenance.
1. Interested bidders can view the NIT on website http:// www.mpetenders.gov.in and
website of MPIDC, R.O., Indore www.mpakvnindore.com – Organisation MPIDC
Ltd, Bhopal.
2. The Bid Document can be purchased only online from Date 05/04/2022
3. Amendments to NIT, if any, would be published on website
http://www.mpetenders.gov.in only, and not in newspaper.
4. GST will be paid extra at the applicable rates to the Contract agency. Rest of the other
taxes, cess, levies, fee toll etc shall be the responsibility of the Contract agency to pay.
5. Form fee and EMD exemptions for MSE are not applicable.
Executive Director
MPIDC Ltd., R.O. Indore
6
SECTION I
Notice Inviting Tender
MP Industrial Development Corporation Ltd.
Regional Office, Indore (M.P.) “ATULYA IT Park” first floor, near Crystal IT Park, Khandwa Road Indore
No. MPIDC/R.O.I./TECH/2022/19321 Dated: 31/03/2022
Online Lump-Sum rate tender for the following works is invited from registered Contract
agencys or firms of repute having eligibility criteria as given in tender documents:
S.
No.
Name
of
Work
District Estimated
Amount of
Contract (Rs.
in Crores)
Earnest
Money Deposit
(EMD)
Cost of Bid
Document
(In Rupees)
Category
of Contract
agency
Period of
Completion
(in Months)
1
Design , Supply,
Erection, Testing &
Commissioning of
200 KLD Common
Effluent Treatment
Plant (CETP) based
on ZLD Process, on
Turn-key basis and
its Operation and
Maintenance for five
years at I/A
Confectionary
Cluster, in front of
IIM Indore Village
Rangwasa, Indore
(M.P.)
Indore Rs. 4.00
Crores
Rs. 4,00000/-
Rs.17700 /-
( i/c GST)
Registered in
Centralized
Registration
System of
MP PWD or
under
process of
registration
of MP PWD
(provided
the
registration
is completed
before
agreement)
6 (six)
months for
Design
Construction
including
rainy season
and 3
months Trial
Run, and 5
years for
Operation
and
Maintenance
.
1. All details relating to the Bid Document (s) can be viewed and downloaded from the
website https://mpetenders.gov.in –MPIDC.
2. Bid Document can be purchased after making online payment of portal fees.
3. At the time of submission of the Bid the eligible bidder shall be required to:
i) P ay the cost of Bid Document.
ii) Deposit the Earnest Money.
iii) Submit all the documents as per tender document.
Details can be seen in the Bid Data Sheet.
4. ELIGIBILITY FOR BIDDERS:
(a) At the time of submission of the Bid the bidder should have registration with the
Government of Madhya Pradesh, PWD / any Govt Dept. in Centralized
Registration System in appropriate class.. However, such bidders who are not
7
registered with the Government of Madhya Pradesh and are eligible for
Centralized Registration System can also submit their bids after having applied
for registration with aforesaid appropriate authority.
(b) The bidder would be required to have aforesaid registration at the time of
signing of the Contract, within 15 days of issue of acceptance letter.
(c) Failure to sign the contract by the selected bidder within the
specified/aforesaid period, and for whatsoever reason, shall result in forfeiture
of the earnest money deposit.
5. Pre Qualification – Qualification conditions, wherever applicable, are given in the
tender document.
6. Special Eligibility - Special Eligibility Conditions, if any, are given in the tender
document.
7. The Bid Document can be purchased only online from 05/04/2022
8. Amendments to NIT, would be published on website only, and not in newspaper.
Executive Engineer
8
SECTION 2
INSTRUCTIONS TO BIDDERS (ITB)
A. GENERAL 1. Scope Of Bid The detailed description of work, hereinafter referred as ‗work‘, is given in the Bid
Data Sheet.
2. General Quality of Work
The work shall have to be executed in accordance with the technical specifications
specified in the Bid Data sheet/ Contract Data, and shall have to meet high standards
of workmanship, safety and security of workmen and works. 3. Procedure For Participation in E-Tendering The procedure for participation in e-tendering is given in the Bid Data Sheet. 4. One Bid Per Bidder
4.1 The bidder can be an individual entity as per Bid Data Sheet.
4.2 No bidder shall be entitled to submit more than one bid whether jointly or
individually. If he does so, all bids wherein the bidder has participated shall stand
disqualified. 5. Cost of Bidding
The bidder shall bear all costs associated with the preparation and submission of his
bid, and no claim whatsoever for the same shall lie on the MPIDC.
6. Site Visit and examination of works
The bidder is advised to visit and inspect the Site of Works and its surroundings and
obtain all information that may be necessary for preparing the bid and entering into a
contract for execution of the work "as is where is condition". All costs in this
respect shall have to be borne by the bidder. Submission of the tender means the
Contract agency has visited the site and has gethered all information related to the
contract.
B. Bid Documents 7. CONTENT OF BID DOCUMENTS
The Bid Document comprises of the following documents: 1. NIT with amendments.
2. Instructions to Bidders, Bid Data Sheet with all Annexure
3. Conditions of Contract:
i. Part I General Conditions of Contract and the Contract Data with all
Annexure and
ii. Part II Special Conditions of Contract.
4. Specifications
5. Drawings
6. Priced Bill of Quantities
7. Technical and Financial Bid
8. Letter of Acceptance
9
9. Agreement, and
10. Any other document (s), as specified. 8. The bidder is expected to examine carefully all instructions, conditions of contract,
the contract data, forms, terms and specifications, bill of quantities, forms and
drawings in the Bid Document. Bidder shall be solely responsible for his failure to do
so. 9. Pre-Bid Meeting –
Where the BID Data Sheeet provides for pre bid meeting –
9.1 Details of venue, date and time would be mentioned in the Bid Data Sheet. Any
change in the schedule of pre-bid meeting would be communicated on the website
only, and intimation to bidders would not be given separately.
9.2 Any prospective bidder may raise his queries and/or seek clarifications in
writing before or during the pre-bid meeting. The purpose of such meeting is to
clarify issues and answer questions on any matter that may be raised at that stage. The
Employer may, at his option, give such clarifications as are felt necessary.
9.3 Minutes of the pre-bid meeting including the l ist of the questions raised and the
responses given together with any response prepared after the meeting will be hosted
on the website.
9.4 Pursuant to the pre-bid meeting if the Employer deems it necessary to amend the
Bid Document, it shall be done by issuing amendment to the online NIT.
10. Amendment of Bid Documents
10.1 Before the deadline for submission of bids, the Employer may amend or modify
the Bid Documents by publication of the same on the website.
10.2 All amendments shall form part of the Bid Document.
10.3 The Employer may, at its discretion, extend the last date for submission of bids
by publication of the same on the website.
C. Preparation of Bid
11. The bidders have to prepare their bids online, encrypt their Bid Data in the Bid Forms
and submit Bid Seals (Hashes) of all the envelopes and documents related to the Bid
required to be uploaded as per the time schedule mentioned in the key dates of the
Notice Inviting e-Tenders after signing of the same by the Digital Signature of their
authorized representative.
12. Documents Comprising the Bid The bid submitted online by the bidder shall be in the following parts: Part 1 – This shall be known as Online Envelope A and would apply to all bids and
required to submit online only as per keydate mentioned in tender document. Envelop
A shall contain the following as per details given in Bid Data Sheet.:
i) Copy of Applied Registration/Registration with the govt. of MP, PWD in
centralized registration system.
ii) P roof of payment of the cost of Bid Document;
iii) Proof of Earnest Money Deposit; and
iv) An affidavit duly notarized
v) Copy of PAN no., GST Registraion no. & EPF Registration.
10
Part 2 – This shall be known as Online Envelope B and required to be submitted
only in works where pre qualification conditions and/or special eleigibilty conditions
are stipulated in the tender document. Envelop B shall contain a certificate duly
supported by documents to demonstrate fulfillment of qualification conditions.
1) Technical document.
2) Financial documents. (Turnover etc).
3) Other documents.
Part 3 – This shall be known as Online Envelope C and required to be submitted
online only. Envelop C shall contain financial offer in the prescribed format enclosed
in tender document. 13. Language
The bid as well as all correspondence and documents relating to the bid exchanged
by the Bidder and the Employer shall be in English or Hindi. Supporting documents
and printed literature that are part of the Bid may be in another language provided
they are accompanied by an accurate translation of the relevant passages in English.
In such case, for the purposes of interpretation of the bid, such translation shall
govern.
14. TECHNICAL PROPOSAL
14.1 Only, in case of bids with pre-qualification conditions defined in the Bid Data Sheet,
the Technical Proposal shall comprise of formats and requirements given in the
Bid Data Sheet.
14.2 All the documents/ information enclosed with the Technical Proposal should be
self-attested and certified by the bidder. The Bidder shall be liable for forfeiture of
his earnest money deposit, if any document / informations are found false/fake/
untrue before acceptance of bid. If it is found after acceptance of the bid, the
bid sanctioning authority may at his discretion forfeit his performance security/
guarantee, security deposit, enlistment deposit and take any other suitable action. 15. FINANCIAL BID
15.1 The bidder shall have to quote rates i n Format referred in tender document, on
turn key contract basis .
15.2 The Lump-Sum offer shall be quoted in figures as well as in words. If any
difference in figures and words is found, lower of the two shall be taken as valid and
correct.
15.3 The bidder shall have to quote rates inclusive of all duties, taxes, royalties and other
levies but exclusive of GST and which shall be payable if applicable.
15.4 The operation and maintenance rate would apply for its duration after successful
commissioning and acceptance by Employer 16. PERIOD OF VALIDITY OF BIDS The bids shall remain valid for a period specified in the Bid Data Sheet after the
date of ―close for biding‖ as prescribed by the Employer. The validity of the bid can
be extended by mutual consent in writing. 17. EARNEST MONEY DEPOSIT (EMD)
17.1 The Bidder shall furnish, as part of the Bid, Earnest Money Deposit (EMD), in the
amount specified in the Bid Data Sheet.
17.2 EMD of bidders whose bids are not accepted will be returned.
11
17.3 Bid not accompanied by EMD shall be liable for rejection as non responsive .
17.4 EMD of the successful Bidder will be discharged/Released when the Bidder has
signed the Agreement after furnishing the required Performance Security.
17.5 Failure to sign the contract by the selected bidder, within the specified period, for
whatsoever reason, shall result in forfeiture of the earnest money deposit and shall be
debarred from participating in the same bid again or shall be liable for any other
action as decided by the authority.
D. Submission of Bid
18. The bidder is required to submit online bid duly signed digitally.
E. Opening and Evaluation of Bid 19 PROCEDURES
19.1 Envelope ‗A‘ shall be opened first online in presence of the bidders or their
authorised representative who choose to be present at the time and date
notified and its contents shall be checked. In cases where Envelop ‗A‘ does not
contain all requisite documents, such bid shall be treated as non-responsive, and
Envelop B and/or C of such bid shall not be opened. .
19.2 Wherever Envelop ‗B‘(Technical Bid) is required to be submitted, the same shall be
opened online at the time and date notified. The bidder shall have freedom to witness
opening of the Envelop ‗B‘. Envelop ‗C‘ (Financial Bid) of bidders who are not
qualified in Technical Bid (Envelop ‗B‘ ) shall not be opened.
19.3 Envelope ‗C‘ (Financial Bid) shall be opened online in presence of the bidders
or their authorised representative who choose to be present at the time and
date notified. The bidder shall have freedom to witness opening of the Envelop ‗C‘.
19.4 After opening Envelop ‗C‘ all responsive bids shall be compared to determine the
lowest evaluated bid.
19.5 The Employer reserves the right to accept or reject any bid, and to annul the bidding
process and reject all the bids at any time prior to contract award, without incurring
any liability. In all such cases reasons shall be recorded.
19.6 The Employer reserves the right of accepting the bid for the whole work or for a
distinct part of it or may reduce the contract amount.
19.7 Further, the client can ask specific clarification about the submitted documents in bid,
but clarification should not be deliberately shielded or tricked to put any new
document in a manner of clarification asked by the client.
20. Confidentiality
20.1 Information relating to examination, evaluation, comparison and recommendation of
contract award shall not be disclosed to bidders or any other person not officially
concerned with such process until final decision on the bid.
20.2 Any attempt by a bidder to influence the Employer in the evaluation of the bids or
contract award decisions may result in the rejection of his bid.
F. Award of Contract 21. Award of Contract
The Employer shall notify the successful bidder by issuing a ‗Letter of
Acceptance‘ (LOA) that his bid has been accepted.
12
22. Performance Security
22.1 Prior to signing of the Contract the bidder to whom LOA has been issued shall have
to furnish performance security of the amount in the form and for the duration, etc.
as specified in the Bid Data Sheet.
22.2 Additional performance security, if applicable, is mentioned in the Bid Data Sheet
and shall be in the form and for the duration, etc. similar to Performance Security.
23. Signing of Contract Agreement 23.1 The s u c c e s s f u l b i d d e r s h a l l h a v e to furnish Performance Security and
Additional Performance Security, if any, and sign the contract agreement within
15 days of issue of LOA.
23.2 The s i g n i n g o f contract agreement shall be reckoned as intimation to
commencement of work. No separate work order shall be issued by the Employer to
the Contract agency for commencement of work.
23.3 In the event of failure of the successful bidder to submit Performance Security and
Additional Performance Security, if any or sign the Contract Agreement, his EMD
shall stand forfeited without prejudice to the right of the employer for taking any
other action against the bidder.
24. CORRUPT PRACTICES The Employer requires that bidders observe the highest standard of ethics during the
procurement and execution of contracts. In pursuance of this policy, the Employer:
i. may reject the bid for award if it determines that the bidder recommended for
award has, directly or through an agent, engaged in corrupt, fraudulent,
collusive, or coercive practices in competing for the Contract; and
ii. may debar the bidder declaring ineligible, either indefinitely or for a stated
period of time, to participate in bids, if it at any time determines that the bidder
has, directly or through an agent, engaged in corrupt, fraudulent, collusive, or
coercive practices in competing for, or in executing, a contract.
For the purposes of this provision, the terms set forth above are defined as
follows:
a. ―corrupt practice‖ means the offering, giving, receiving, or soliciting,
directly or indirectly, anything of value to influence improperly the actions of
another party;
b. ―fraudulent practice‖ means any act or omission, including a
misrepresentation, that knowingly or recklessly misleads, or attempts to
mislead, a party to obtain a financial or other benefit or to avoid an
obligation;
c. ―coercive practice‖ means impairing or harming, or threatening to impair or
harm, directly or indirectly, any party or the property of the party to influence
improperly the actions of a party;
d. ―collusive practice‖ means an arrangement between two or more parties
designed to achieve an improper purpose, including influencing
improperly the actions of another party.
[End of ITB]
13
Bid Data Sheet
GENERAL
SR. No. PARTICULARS DATA
1 Office Inviting Tender Executive Director, M.P. Industrial Development
Corporation Ltd. Regional Office, Indore
2 NIT No. No. MPIDC/R.O./IND/2022/ 19321
3 Date of NIT Date: 31.03.2022
4
Bid document download
available from date &
time
From 05/04/2022
17:31 PM
To 01/05/2022
17.30 PM
5 Website link http:// www.mpetenders.gov.in
SECTION 1 – NIT
NIT CLAUSE PARTICULARS DATA
2 Portal Fees
(also known as processing fee)
As notified in e-Tendering Website
http:// www.mpetenders.gov.in
3
Cost of Bid Document Rs. 17700/- (i/c GST)
Cost of Bid Document Payable at online
Cost of Bid Document In favor of MP Industrial Development Corporation
Limited.
4 Affidavit Format As per 'Annexure- B'
5 Qualifications required Yes
If Yes, details As per' Annexure- C'
6 Special Eligibility No
If Yes, details As per 'Annexure -D'
7 Key dates As per 'Annexure -A'
SECTION 2 – ITB
ITB
CLAUSE PARTICULARS DATA
1 Name of the ‗Work‘
Design, Supply, Erection, Testing &
Commissioning of 200 KLD Common Effluent
Treatment Plant (CETP) based on ZLD Process,
on Turn-key basis and its Operation and
Maintenance for five years (Phase-I) at I/A
Confectionary Cluster, in front of IIM Indore
Village Rangwasa, Indore (M.P.)
14
2 Specifications As per 'Annexure – E'
3
Procedure for participation in e-
tendering0 As per 'Annexure – F'
4 Whether Joint Venture
is allowed. No
9
Pre bid meeting to be held YES
If Yes, Date, Time and Place
Date :- 18/04/2022
Time from :- 15.00 PM
Place :- Office of the Executive Engineer,
M.P. Industrial Development Corporation Ltd.,
Regional Office, Indore, Atulya IT Park, 101, first
floor, near Crystal IT Park, Khandwa Road, Indore
(M.P.).
ITB
CLAUSE PARTICULARS DATA
12 Envelope-A Online only, As per ITB 12, Part 1.
14 Envelope-B Online only, As per ITB 12, Part 2
15 Envelope-C Financial Bid Online only, As per ITB 12, Part 3
Materials to be issued by the
department Not Applicable.
16 Period of Validity of Bid 180 Days
17
17
Earnest Money Deposit Rs. 4,00000/-
18 Forms of Earnest Money
Deposit Online only
19 EMD valid for a period of 180 days or more
20 Letter of Acceptance (LoA) As per 'Annexure -L'
21
Amount of Performance
Security Deposit
a) 5% security deposit amount of contract amount (+/-
tender percentage) to be deposited before execution
of agreement. It should be in the form of BG/FDR
of nationalized bank vailid upto completion period
plus defact liability period of three months trail &
run which shall be released after successful
completion of the contract.
b) 5% security deposit amount to be deducted from
running bills which shall be released after
successful completion of the contract.
15
Additional Performance
Security
If bid of the successful bidder is found to be more
than 15% (Fifteen Percent) below the probable
contract amount, then the bidder shall have to
deposit additional performance security equal to
the difference of amount quoted by the bidder
beyond below 15% and 15% below contract
amount i.e. Quoted percentage by the bidder
(Beyond below 15%) minus 15% of the contract
amount.
For e.g. if the bidder has quoted 17% below the
Probable amount of contract (PAC) then the
additional performance Security will have to be
deposited by the bidder equal to =
(17%-15%) x Contract amount.
It will be released after issuing of physical
completion certificate.
or as directed by the Authorities from time to
time.
Performance Security in the
format As per 'Annexure - M
Performance Security in
favour of MP Industrial Developent Corporation Limited.
Performance Security valid
up to
The upfront Bank Guarantee against performance
security shall be taken for a period as mentioned
below-
Construction Period + 5 Years+ 3 Months.
It is clarified that in case the construction period of
the work is extended beyond the stipulated
completion period, the bank guarantee against PG
shall have to be got extended by the Contract
agency for the relevant period so as to satisfy the
validity criteria mentioned above.
Additional Performance
security valid up to
The additional performance Security if applicable
shall be taken for a period mentioned below :-
Construction period.
It is clarified that in case the construction period
of the work is extended beyond the stipulated
physical completion period, the bank guarantee
against PG shall have to be got extended by the
Contract agency for the relevant period + 3
months so as to satisfy the validity criteria
mentioned above.
16
Annexure – A
(See clause 1, 7 of Section 1 -NIT )
KEY DATES
S.
No.
Works
Department
Stage
Bidder’s
Stage
Start Expiry
Envelopes Date Time Date Time
1 Purchase of
Tender –
Online
05/04/20
22
17.31 01/05/20
22
17.30
2 Pre-Bid
Meeting
18/04/20
22
15.00 18/04/20
22
17.00
3 Bid
Submission
– Online
01/05/20
22
17.30
4 Mandatory
submission
Open
(Envelope-A)
04/05/20
22
11.30 Envelope-A
5 Technical
Proposal open
(PQ
Envelope-B)
04/05/20
22
11.30 Envelope-B
6 Financial Bid
open
(Envelope-C)
Only
Online
06/05/20
22
11.30 Envelope-C
Note: Pre-Bid meeting will be held at “MPIDC Regional Office, “ATULYA IT
PARK”, 101, FIRST FLOOR, NEAR CRYSTAL IT PARK, KHANDWA ROAD,
INDORE (M.P.)
17
Annexure – B
(See clause 3 of Section 1 - NIT )
|| AFFIDAVIT ||
(To be contained in Envelope A)
(On Non-Judicial Stamp of Rs. 100)
1. I/we …………………………………… who is/ are …………………………….
(status in the firm/ company) and competent for submission of the affidavit on
behalf of M/S (Contract agency) do solemnly affirm an
oath and state that: 2. I/we am/are fully satisfied for the correctness of the certificates/records submitted in
support of the following information in bid documents which are being submitted in
response to notice inviting e-tender No …… for …….... (Name of Work) dated ……….
issued by Executive Director, M.P. Industrial Development Corporation Ltd., Regional
Office, Indore (M.P.).
3. I/we am/ are fully responsible for the correctness of following self-certified
information / documents and certificates :
(i) That the self-certified information given in the bid document is fully true
and authentic.
(ii) That:
a. Term deposit receipt deposited for cost of bid document, earnest money and
other relevant documents provided by the Bank are authentic.
b. Information regarding financial qualification and annual turnover are correct.
c. Information regarding various technical qualifications are correct.
(iii) No close relative of the undersigned and our firm/company is working in
the department/Nigam. OR Following close relatives are working in the
department:
Name ……………………… Post ……………………. Present Posting…………..
4. I/we ………………………………… also do solemnly affirm an oath and state that
aforesaid firm/company M/s……………………………….. at the time of tendering, has
not been black listed or debarred from any department/undertaking/subsidiary, working
under Government of India or Government of all states of India including Government of
Madhya Pradesh.
Signature with Seal of the Deponent (Bidder)
I/ We, ………………………… above deponent do hereby certify that the facts mentioned in
above para 1 to 4 (with their sub paras) are correct to the best of my knowledge and belief. Verified today ……………………………. (dated) at …………………… (place).
Signature with Seal of the Deponent (Bidder)
Note : Affidavit should be duly notarized.
18
Annexure – C
(See clause 5 of Section 1 -NIT )
PRE- QUALIFICATIONS CRITERIA
The bidder should have:
A. Financial
i. Experience of having successfully executed/completed :
a) One project of 150 KLD common effluent treatment plant / effluent treatment plant
with succesfull Operation and Maintenanace for at least one (1) year during the last
5 years duly certified by the principal employer.
or
b) Two similar project of 100 KLD common effluent treatment plant / effluent
treatment plant each with Operation and maintenance for at least one year during the
last five (5) years duly certified by the principal employer ;
‗Similar Works‘ means completion of project of Design and Construction of Common
Effluent Treatment Plant/ effluent treatment plant.
ii. Average annual turnover during the last three year should be atleast 30% of the
estimate cost. If the bidder has not got audited his account for the financial year 2021-
22, then in that case 3 financial year may be reckoned from 2018-19 to 2020-21,
Attach Audited copy of Balance sheets.
iii. Executed similar items of work in the last 3 financial years under single contract,
which should not be less than the minimum, physical requirement as prescribed in
Clause ―D‖of the prequalification‘s criteria (Annexure-C), if any, fixed for the work.
iv. The applicant/Firm should not have incurred any loss in consecutive two years
during the last 3 years ending 31st March 2022, duly certified by the chartered
Accountant.
v. The bidder should not have been black listed by any Central/State Government
institutions. An undertaking (Self-Certificate) in this regard that the bidder hasn‘t
been blacklisted by any central/state government institutions mustbe submitted.
B. JointVenture: Not Allowed as per Annexure G
C. Base Year Escalation for calculation of cost of works.
The base year shall be taken as financial year 2021-22
Following enhancement factors will be used for the costs of works executed as per
para (I) and the financial figure as para (II) to a common base value for works
completed.
FinancialYear MultiplyingFactor
2021-22 1.10
2020-21 1.21
2019-20 1.33
Bidders should indicate actual figures of costs and amount for the works executed by
them without accounting for the above-mentioned factors.
19
D. Physical
Physical qualifications for the work shall be as below
S. No. Particulars Quantity Period
Physical qualification required Yes During The Last 5 Financial Years
1 Turnkey Project of CETP At least one project of CETP/ETP, based on ZLD
concept
Note :
Experience Certificates issued by the principal employer (Not below the rank of Executive
Engineer/General Manager/Plant Manager) should be submitted as proof in support of the
above Physical/Financial requirement.
Experience Certificate should be comprises of
1. Name of work,
2. Amount of work,
3. Date of work order,
4. Date of completion/ substantial completion,
5. Bidders role must be either of Contract agency/ sub Contract agency/ partner.
Bidders not fulfilling the above criteria, liable to be rejected.
21
ANNXURE – E
(See clause 2 of Section 2 – ITB & Clause 18 of GCC)
Specifications
1. MoRTH Specification (Vth
Revision) for Road and Bridge Works.
2. CPWD Specification.
3. Central Public Health and Environmental Engineering
Organisation(CPHEEO) Specification for water Supply & Treatment
Works. CPCB guide lines/specification.
4. PWD E&M Specification for Electrical Works.
5. MPPKVV co. Ltd. Specification for Electrical Works
6. Part II Special condition of contract (SCC)
7. Specifications as mentioned in the Schedule of Rates of following SOR‘s as amended upto date of issue of NIT;
a. Schedule of rates for building works in PWD, MP.(w.e.f. 03/12/2020),
b. Schedule of rates for Road&Bridge works in PWD, MP.(w.e.f 25/03/2022),
c. Unified Schedule of rates for Water supply&Sewerage works in PHE,MP.-
(w.e.f. 03/07/2018)
d. Schedule of rates for E&M works in PWD,MP.(w.e.f 01/12/2020).
Note : All ammendement shall be applicable upto the date of issue of NIT.
The provision of general/ special conditions of contract, those specified elsewhere in the bid
document, as well as execution drawings and notes, or other specifications issued in writing
by the Employer shall form part of the technical specifications of this work.
22
Annexure –F
GUIDELINES TO CONTRACT AGENCYS FOR IMPLEMENTATION OF E-
PROCUREMENT SYSTEM IN MPIDC, GOVERNMENT OF MADHYA PRADESH
https://www.mpetenders.gov.in
Note: These will over rule the stated in the tender documents, wherever relevant and
applicable.
1. Registration of Bidders on e-procurement System:
All the Bidders registered / intending to work with MPIDC, are required to register on the e-
procurement System on the website https://www.mptenders.gov.in and get empanelled on
https://www.mptenders.gov.in in order to participate in tenders processed by MPIDC, using
the e-procurement System.
The Bidders registered with other departments who are also eligible to participate in tenders
processed by MPIDC, are also required to be registered on the e-procurement System on
https://www.mptenders.gov.in
3. Digital Certificate:
The bids submitted online should be signed electronically with a Class III Digital Certificate
to establish the identity of the Bidder submitting the Bid online. The bidders may obtain
Class III Digital Certificates issued by an approved certifying Authority authorized by the
Controller of Certifying Authorities, Government of India.
A Class III Digital Certificate is issued upon receipt of mandatory identity proofs along with
an Application Form. Only upon the receipt of the required documents, a Digital Certificate
can be issued.
Note : It may take up to 7 working days for issuance of Class III Digital Certificate; hence the
bidders are advised to obtain them at the earliest.
Important Note : Bid for a particular tender can be submitted during the ONLINE BID
SUBMISSION stage only using the Digital Certificate that is used to encrypt the data and
Upload their bids.
In case, during the process of a particular tender, the bidder loses his Digital Certificate
because of any problem (such as misplacement, virus attack, hardware problem, operating
system problem, etc); he may not be able to submit his bid online.
Hence, the bidders are advised to keep their Digital Certificates in a safe place under proper
security to be used whenever required.
The digital certificate issued to the Authorized User of a Partnership Firm / Private Limited
Company / Public Limited Company / used for online bidding will be considered as
equivalent to a no-objection certificate / power of attorney to that user.
In case of Partnership Firm, majority of the Partners have to authorize a specific individual
through Authority Letter signed by majority of the Partners of the Firm.
In case of Private Limited Company, Public Limited Company, the Managing Director/ any
other person (having designated authority to authorize a specific individual) has to
authorize a specific individual through Authority Letter.
23
Unless the certificate is revoked, it will be assumed to represent adequate authority of the
specific individual to bid on behalf of the Organization for online tenders as per Information
Technology Act 2000. This Authorized User will be required to obtain a Digital Certificate.
The Digital Signature executed through the use of Digital Certificate of this Authorized User
will be binding on the firm. It shall be the responsibility of Management / Partners of the
concerned firm to inform the certifying authority, if the authorized User changes, and apply
for a fresh digital certificate for the new authorized User.
3. Set Up of Bidders’ Computer System:
In order for a Bidder to operate on the e-procurement System, the computer system of the
bidder is required to be set up for Latest version of Java, Operating System, Internet
Connectivity, Utilities Fonts, etc. A help file on setting up of the Computer System can be
obtained from the portal.
4. Publishing of NIT
For the tenders processed using the e-procurement system, only a brief Advertisement related
to the tender shall be published in the newspapers and the Detailed Notice shall be uploaded
only on the e-procurement system. The bidders can view the Detailed Notice and the time
schedule for all the tenders‘ processes using the e-procurement System on the website
https://www.mptenders.gov.in
5. Key Dates
The bidders are strictly advised to follow the time schedule (Key Dates) of the Tender for
their side for tasks and responsibilities to participate in the tender, as all the stages of each
Tender are locked before the start time and date and after the end time and date for the
relevant stage of the Tender as set by the concerned Department Official.
6. Purchase of Tender Documents:
The tender document can be purchased ONLY online. The tender shall be available for
purchase to concerned eligible bidders immediately after online release of the tender and upto
scheduled date and time as set in the key dates. Arrangements have been made for the
Bidders to make payments online via Credit Card / Internet Banking. In case of online
tendering, the application form for the purchase of tender documents shall not be required.
The bidder can purchase the tender documents online by making online payment of tender
document fees using the service of the secure electronic payments gateway (see point 7 below
for further details), and should print out the system generated receipt of their reference which
can be produced whenever required.
7. Electronic Payment Account:
As the tender documents shall be available for purchase only online, bidders are required to
pay the tender document fees online using the Online Payments Gateway Service integrated
into the e-Procurement System. For the list of available modes of electronic payments that are
presently accepted on the Online Payments Gateway Service, please check the link ‗List of e-
payments accepted online‘ on https://www.mptenders.gov.in
24
8. Preparation of Bids and Submission of Bid Online by the Bidders:
The Bidders have to prepare their Bids online, encrypt their bid data in the Bid Forms and
submit Bid Seals (Hashes) of all the envelopes and documents required to be uploaded related
to the Tender as per the time schedule mentioned in the key dates of the Notice Inviting
Tenders after signing of the same by the Digital Signature of their authorized representative.
9. Submission of Earnest Money Deposit : Online, MP Industrial Developent Corporation
Ltd.
10. Opening of Tenders:
The concerned Department Official receiving the tenders or his duly authorized Officer shall
first open the online Earnest Money Deposit and copy of Tender Purchase Receipt envelope
of all the Bidders and verify the scanned copy of the Earnest Money Deposit and copy of
Tender Purchase Receipt uploaded by the Bidders. He shall check for the validity of Earnest
Money Deposit as required. He shall also verify the scanned documents uploaded by the
bidders, if any, as required. In case, the requirements are incomplete, the commercial and
other envelopes of the concerned Bidders received online shall not be opened.
The concerned official shall then open the Technical Proposal envelopes submitted online
and physical by the Bidders in the presence of the Bidders or their authorized representatives
who choose to be present in the order of opening. He will match the Bid seal (Hash) of each
envelope and the documents uploaded, during the respective opening, with the hash
submitted by the Bidders during the Bid Preparation stage. In the event of a mismatch, the
Bid data in question shall be liable for a due process of verification by the Nodal Officer of e-
procurement System of Public Works Department. For more details you may contact
Contact : MPIDC LTD., Regional Office, Indore : Tel. 0731-2970611, 2971311, 2974363.
26
Format for Power of Attorney for Signing of Bid
(Refer Clause 2.2.5)
Know all men by these presents, We…………………………………………….. (name of
the firm and address of the registered office) do hereby irrevocably constitute, nominate,
appoint and authorize Mr/ Ms (name), …………………… son/daughter/wife of
……………………………… and presently residing at
…………………., who is presently employed with us/ the Lead Member of our Joint
Venture and holding the position of ……………………………. , as our true and lawful
attorney (hereinafter referred to as the ―Attorney‖) to do in our name and on our behalf,
all such acts, deeds and things as are necessary or required in connection with or
incidental submission of our bid for the ***** Project proposed or being developed
by the
***** (the ―Employer‖) including but not limited to signing and submission of allbids
and other documents and writings, participate in Bids and other conferences and
providing information/ responses to the Employer, representing us in all matters before
the Employer, signing and execution of all contracts including the EPC A g r e e m e n t
and undertakings consequent to acceptance of our bid, and generally dealing with the
Employer in all matters in connection with or relating to or arising out of our bid for the
said Project and/ or upon award thereof to us and/or until the Appointed Date under
EPC Agreement
AND we hereby agree to ratify and confirm and do hereby ratify and confirm all acts,
deeds and things done or caused to be done by our said Attorney pursuant to and in
exercise of the powers conferred by this Power of Attorney and that all acts, deeds and
things done by our said Attorney in exercise of the powers hereby conferred shall and shall
always be deemed to have been done by us.
IN WITNESS WHEREOF WE, …………… THE ABOVE NAMED PRINCIPAL HAVE
EXECUTED THIS POWER OF ATTORNEY ON THIS ……… DAY OF …………. 2021
For
……………………(Signature, name, designation and address)
Witnesses:
1.
(Notarised)
2.
Accepted
……………………………
(Signature)
(Name, Title and Address of the Attorney)
27
Notes: The mode of execution of the Power of Attorney should be in accordance with the
procedure, if any, laid down by the applicable law and the charter documents of
the executant(s) and when it is so required, the same should be under common
seal affixed in accordance with the required procedure. Wherever required, the Bidder should submit for verification the extract of the
charter documents and documents such as a board or shareholders‘ resolution/
power of attorney in favour of the person executing this Power of Attorney for the
delegation of power hereunder on behalf of the Bidder. For a Power of Attorney executed and issued overseas, the document will also
have to be legalised by the Indian Embassy and notarised in the jurisdiction where
the Power of Attorney is being issued. However, the Power of Attorney provided
by Bidders from countries that have signed the Hague Legislation Convention
1961 are not required to be legalised by the Indian Embassy if it carries a
conforming Appostille certificate.
29
Annexure - H (See clause 12 of Section 2 –ITB & clause 4 of GCC)
ORGANIZATIONAL DETAILS
(To be Contained in Envelope - A) S. No.
Particulars
Details
1.
Registration number issued by Centralized Registration System of Govt. of M.P. or Proof of application for registration.
Registration No…………….Date______
(Scanned copy of Registration to be
uploaded, if any) 2.
Registration of bidder through Centralized
Registration of Govt. of MP
Registration No…………….Date_______
(Scanned copy of Registration to be
uploaded, if any) 3.
Name of Organization/ Individual/ Proprietary Firm/ Partnership Firm
4.
Entity of Organization Individual/ Proprietary Firm/ Partnership
Firm (Registered under Partnership Act)/
Limited Company (Registered under the
Companies Act–1956)/ Corporation/ Joint
Venture
5. Address of Communication
6. Telephone Number with STD Code
7. Fax Number with STD Code
8. Mobile Number
9. E-mail Address for all communications
Details of Authorized Representative
10. Name
11. Designation
12. Postal Address
13. Telephone Number with STD Code
14. Fax Number with STD Code
15. Mobile Number
16. E-mail Address
Note: In case of partnership firm and limited company certified copy of partnership deed/
Articles of Association and Memorandum of Association along with registration
certificate of the company shall have to be enclosed.
Signature of Bidder with Seal
Date :-____________
Annexure – I (See clause 14 of Section 2 -ITB)
Envelope – B
Envelop B shall comprise the following documents:
S. No
Particulars
Details to be submitted
1 Experience Annexure - I (Format: I-1)
2 Annual Turnover Annexure - I (Format: I-2)
Note:
1. Technical Proposal should be uploaded duly page numbered and indexed.
2. Technical Proposal uploaded otherwise bid will not be considered.
Annexure - I (Format: I-1) (See clause 14 of Section 2 -ITB)
FINANCIAL & PHYSICAL EXPERIENCE DETAILS
a) The bidder should have:
A . Financial
i) Experience of having successfully executed/completed :
a) One project of 150 KLD common effluent treatment plant / effluent treatment plant
with succesfull Operation and Maintenanace for at least one (1) year during the last
5 years duly certified by the principal employer.
or
b) Two similar project of 100 KLD common effluent treatment plant / effluent
treatment plant each with Operation and maintenance for at least one year during the
last five (5) years duly certified by the principal employer ;
To be filled in by the Contract agency:
i. Details of successfully completed / executed similar works shall be furnished in the following format.
ii. Certificate duly signed by the employer shall also be enclosed for each completed similar work.
Agreement Number & Year
Name of Work Date of Work Order
Date of Completion
Amount of Contract
Employer's Name and Address
Existing commitments:
Agreement Number & Year
Name of Work
Date of Work Order
Date of Completion
Amount of Contract
Amount of balance work
Employer's Name and Address
B. Physical Requirement:
Execution of similar items of work in any one financial year during the last 3 financial years
should not be less than the minimum physical requirement fixed for the work.
S.
No. Particulars
Actual Project Executed
(To be filled in by the Contract agency )
Year-1 Year-2 Year-3 Year-4 Year-5
Physical qualification required Yes
1 Turnkey Project of CETP/ETP based
on ZLD
2 O & M of CETP/ETP for any
industrial area
Note:
1. Certificates issued by the principal employer (Not below the rank Executive Engineer
rank) should be submitted as proof in support of the above physical requirement.
2. Similar works: Complete construction of CETP/ETP based on ZLD process with
Infrastructure Development for any industrial area & operation & maintenance of
CETP/ETP for any industrial area .
Annexure - I (Format: I -2) (See clause 14 of Section 2 –ITB)
ANNUAL TURN OVER
Requirement:
i. Average annual turnkey project execution on CETP/ETP not less than 30% of the
probable amount of contract during the last 3 financial years..
To be filled in by the Contract agency:
Financial Year Payments received for contracts in progress or completed
2019-20
2020-21
2021-22
Note:
Annual turnover of CETP/ETP construction projects should be certified by the
Chartered Accountant.
Annexure - I (Format: I -3) (See clause 14 of Section 2 –ITB & Clause 6 of GCC)
List of Technical Personnel for the Key Positions
Requirement during execution
irement
Available with the bidder
S. N
o.
Key
Posi
tion
Min
imum
req
uir
emen
t M
inim
um
Qu
alif
icat
ion
Age
Sim
ilar
wo
rk e
xper
ien
ce
Req
uir
ed
Tota
l W
ork
E
xper
ience
(Min
imum
)
Yea
rs
S. N
o.
Nam
e of
Per
son
nel
Key
Posi
tion
Qual
ific
atio
n
Age
Sim
ilar
wo
rk e
xper
ien
ce
Tota
l W
ork
Exper
ience
1
Project
Manager 01
B.E.
chemical
/Mech
50 3 7
2
Site
Engineer
civil
01 BE Civil 50
3
5
3
Site
Engineer
(MEP)
01 B.E. Elect <50 3 5
4 Plant
Operator 1
ITI/
experience
d
<50 3 5
5
Supervisor
cum Lab
Chemist
Diploma
chemical
engg/ M.
Sc.
Env/Chemi
stry
<50 3 5
6 Helper
Unskilled
/semiskille
d
<50
List of staff is to be given by the Contract agency to the Employer‘s Engineer and advance
intimation to be given before deputing/removing any staff from site during the period of
contract. Not more than one of the Contract agency's key staff shall be absent from the
project site at any given time. In case it is necessary for more than one of the key personnel to
be absent at a given time, the Contract agency shall provide replacement of equivalent or
better qualifications. The CVs of such replacements shall be got pre-approved from
Employer/ Employer‘s Engineer in advance.
Employer‘s Engineer shall be authorized to direct the contracting agency to remove any or all
staff employed in the plant if in his opinion continued presence of such staff is detrimental to
safety or proper O&M of the plant. The Contract agency shall comply with such directions &
post suitable substitute(s) thereof. Whenever the Employer‘s Engineer has to inform the
Contract agency in writing that any person on the work is in his opinion unsatisfactory
or/incompetent or unfaithful or dishonest untruthful or disorderly or to be otherwise
unsuitable/such person shall be discharged by the Contract agency from the work and shall
not be employed again on it.
Annexure I (Format: I -4) (See clause 14 of Section 2 -ITB)
List of Key Equipments/ Machines for Quality Control Labs
Note: Equipment/machines required for proper testing of materials. Equipments / machines
will have to be provided at testing lab as per norms and instructions of EIC. Tentative list is
given in bid document.
Annexure - I (Format: I -5)
(See clause 14 of Section 2 -ITB)
List of Key Construction Equipments/ Machines for Construction Work
The Contract agency shall arrange plants and machineries at site for execution of the
work. Sufficient quantity of construction equipment shall have to be provided at site.
The Contract agency may have to deploy more Equipments and Plants depending upon
his Work Programme and Methodology, he/she has to ensure the same to complete the
work in stipulated period.
Annexure – J
FINANCIAL BID
(To Be Contained in Envelope-C)
(Only Online)
NAME OF WORK :- Design, Supply, Erection, Testing & Commissioning of 200 KLD
Common Effluent Treatment Plant (CETP) based on ZLD Process, on Turn-key basis and its
Operation and Maintenance for five years at I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore (M.P.)
I/We hereby bid for the execution of the above work within the time specified at the rate (in
figures) _ (in words) Lump Sum based on turnkey
basis as per scope of work given therein in all respects and in accordance with the
specifications, designs, drawings and instructions in writing in all respects in accordance
with such conditions so far as applicable. I/We have visited the site of work and am/ are fully
aware of all the difficulties and conditions likely to affect carrying out the work. I/We have
fully acquainted myself/ourselves about the conditions in regard to accessibility of site and
quarries/kilns, nature and the extent of ground, working conditions including stacking of
materials, installation of tools and plant conditions effecting accommodation and movement
of labour etc. required for the satisfactory execution of contract.
Should this bid be accepted, I/We hereby agree to abide by and fulfill all the terms and
provisions of the said conditions of contract annexed hereto so far as applicable, or in default
thereof to forfeit and pay to the Executive Director, M.P. Industrial Development
Corporation Ltd., Regional Office, Indore or his successors in office the sums of money
mentioned in the said conditions.
Note: i. Only one rate shall be quoted.
ii. Rates shall be quoted in figures as well as in words. If any difference in figures and
words is found lower of the two shall be taken as valid and correct rate. If the bidder
is not ready to accept such valid and correct rate and declines to furnish performance
security and sign the agreement his earnest money deposit shall be forfeited.
iii. All duties, taxes, and other levies payable by the bidder shall be included in the
percentage quoted by the bidder but exclusive of Goods and Service Tax (GST) to be
levied on Works/Service Contract and GSTshall be paid separately as applicable.
Signature of Bidder
Name of Bidder
The above bid is hereby accepted by me on behalf of the M.P. Industrial Development Corporation Ltd., Regional Office, Indore dated the day of 20
Signature of Officer by whom accepted
Executive Director
Annexure – L
(See clause 21 of Section 2 -ITB )
M.P Industrial Development Corporation Ltd.,
Regional Office, Indore
LETTER OF ACCEPTANCE (LOA)
No. ……………………… Dated :- …………..
To,
M/s .............................. (Name and address of the Contract agency)
Subject :- ………………………………………..
(Name of the work as appearing in the bid for the work)
Dear Sir(s),
Your bid for the work mentioned above has been accepted on behalf of the Executive
Dirctor, M.P. Industrial Development Corporation Ltd., Regional Office, Indore at your
bided Lump Sum ratesas per Bill of Quantities given therein.
You are requested to submit within 15 (Fifteen) days from the date of issue of this
letter :
a. The performance security/performance guarantee including additional of Rs.
…………….. (in figures) (Rupees
……………………………………………………………………… in words only).
Nationalized/schedule commercial bank valid up to three months after the expiry of
defects liability period.
b. Sign the contract agreement.
Please note that the time allowed for carrying out the work as entered in the bid is
……. ……months including rainy season with defect liability period of ……. months after
physical completion of work, shall be reckoned from the date of signing the contract
agreement.
Signing the contract agreement shall be reckoned as intimation of commencement of
work and no separate letter for commencement of work is required. Therefore, after signing
of the agreement, you are directed to contact concerned Assistant Engineer for taking the
possession of site and necessary instructions to start the work.
Yours faithfully,
Chief General Manager
Annexure – M
(See clause 22 of Section 2 –ITB)
PERFORMANCE SECURITY
To,
……………………… (Name of Employer)
……………………… (Address of Employer)
WHEREAS ………………………………………………(Name and address of
Contract agency) (Hereinafter called "the Contract agency") has undertaken, in
pursuance of Letter of Acceptance No. ………. Date …………… to execute
………………. (Name of Contract and description of Works) (hereinafter called ―the
Contract‖)
AND WHEREAS it has been stipulated by you in the said Contract that the Contract
agency shall furnish you with a Bank Guarantee by a recognized bank for the sum specified
therein as security for compliance with his obligation in accordance with the Contract;
AND WHEREAS we have agreed to give the Contract agency such a Bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to
you on behalf of the Contract agency, up to a total of [amount of guarantee]*
(in words), such sum being payable in the types and proportions of currencies in which the
Contract Price is payable, and we undertake to pay you, upon your first written demand
and without cavil or argument, any sum or sums within the limits of
[amount of guarantee] as aforesaid without your needing to prove or to show grounds or
reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contract
agency before presenting us with the demand.
We further agree that no change or addition to or other modification of the terms of
the Contract of the Works to be performed there under or of any of the Contract
documents which may be made between you and the Contract agency shall in any way
release us from any liability under this guarantee, and we hereby waive notice of any such
change, addition or modification.
Our liability under this Bank Guarantee shall not exceed Rs. .......................( Rs.
......................only) & we further declare that this Bank Guarantee will be valid from
.................to ....................... and we declare that this Bank Guarantee will be renewed
automatically; (Only upto actual work completion period + defect liability period of 3 month
Tr.&Run + 5 year O&M) we undertake to renew this Bank Guarantee on our own till the
matter is settled & fully discharged by the Executive Director, M.P. Industrial Development
Corporation Ltd., Regional Office, Indore. The liability of the importer shall not be
discharged in any account without the consent of the Executive, M.P. Industrial
Development Corporation Ltd., Regional Office, Indore in writing.
This guarantee shall be valid until 5 year from the date of expiry of the Defect
Liability Period.
Signature, Name and Seal of the guarantor _____________________________
Name of Bank _______________ Address
Phone No., Fax No., E-mail Address, of Signing Authority Date ____________
* An amount shall be inserted by the Guarantor, representing the percentage the
Contract Price specified in the Contract including additional security for unbalanced
Bids, if any and denominated in Indian Rupees.
Clause
No Particulars Clause
No Particulars
A. General 21 Payments for Variations and / or Extra Quantities
1 Definitions 22 No compensation for alterations in or restriction
of work to be carried out.
2 Interpretations and Documents 23 No Interest Payable
3 Language and Law 24 Recovery from Contractors
4 Communications 25 Tax
5 Subcontracting 26 Check Measurements
6 Personnel 27 Termination by Engineer in Charge
7 Force Majeure 28 Payment upon Termination
8 Contractor's Risks 29 Performance Security
9 Liability For Accidents To Person 30 Security Deposit
10 Contractor to Construct the Works 31 Price Adjustment
11 Discoveries 32 Mobilization and Construction Machinery Advance
12 Dispute Resolution System 33 Secured Advance
B. Time Control 34 Payments Certificates
13 Programme E. Finishing the Contract
14 Extension of Time 35 Completion Certificate
15 Compensation for Delay 36 Final Account
16 Contractor‘s quoted percentage F. Other Conditions of Contract
C. Quality Control 37 Currencies
17 Tests 38 Labour
18 Correction of Defects noticed
during the Defect Liability Period
39 Compliance with Labour Regulations
D. Cost Control 40 Audit and Technical Examination
19 Variations - Change in original Specifications, Designs, Drawings
etc.
41 Death or Permanent Invalidity of Contractor
20 Extra Items 42 Jurisdiction
SECTION 3
CONDITIONS OF CONTRACT
Part – I General Conditions of Contract [GCC] Table of Clauses
A. General 1. DEFINITIONS
1.1. Bill of Quantities: means the priced and completed Bill of Quantities forming part of
the Bid.
1.2. Chief Engineer: means Chief Engineer of the M.P. Industrial Development
Corporation Ltd., Bhopal or Other authorized Officer.
1.3. Completion: means completion of the work as certified by the Employer , in
accordance with provisions of agreement.
1.4. Contract: means the Contract between the Employer and the Contract agency to
execute, complete and/or maintain the work. Agreement is synonym of Contract
and carries the same meaning wherever used.
1.5. Contract Data: means the documents and other information which comprise of the
Contract.
1.6. Contract agency: means a person or legal entity whose bid to carry out the work
has been accepted by the Employer.
1.7. Contract agency's bid: means the completed bid document submitted by the
Contract agency to the Employer.
1.8. Contract amount: means the amount of contract worked out on the basis of accepted
bid.
1.9. Completion of work: means completion of the entire contracted work. Exhaustion of
quantity of any particular item mentioned in the bid document shall not imply
completion of work or any component thereof.
1.10. Day: means the calendar day.
1.11. Defect: means any part of the work not completed in accordance with the
specifications included in the contract.
1.12. Department: means M.P. Industrial Development Corporation Ltd., Regional
Office, Indore who adopts this document written in short as MPIDC Ltd., Bhopal.
1.13. Drawings: means drawings including calculations and other information provided
by Competent Authority
1.14. Employer: means the party as defined in the Contract Data, who employs the
Contract agency to carry out the work. The Employer may delegate any or all
functions to a person or body nominated by him for specified functions. The executed
agreement will be effective in full essence with the successor company of M.P.
Industrial Development Corporation Ltd., Regional Office, Indore if incase change
any constitutional/formation changes happens in the status of MPIDC, Ltd.,
R.O.Indore.
1.15. Engineer: means the person named in the Contract Data.
1.16. Engineer in charge: means the person named in the Contract Data.
1.17. Equipment: means the Contract agency's machinery and vehicles brought
temporarily to the Site for execution of work.
1.18. Government: means Government of Madhya Pradesh.
1.19. In Writing: means communicated in written form and delivered.
1.20. Material: means all supplies, including consumables, used by the Contract
agency for incorporation in the work.
1.21. Executive Engineer : means executive engineer in charge of MPIDC , Indore
1.22. Stipulated period of completion: means the period in which the Contract
agency is required to complete the work. The stipulated period is specified in the
Contract Data.
1.23. Assistant Engineer :- means Assistant Engineer of M.P. Industrial Development
Corporation Ltd.(Regional Office, Indore).
1.24. Junior Engineer :- Means Junior Engineer of M.P. Industrial Development
Corporation Ltd. (Regional Office, Indore).
1.25 Specification: means the specification of the work included in the Contract and any
modification or addition made or approved by the Competent Authority.
1.26. Start Date: means the date of signing of agreement for the work.
1.27. Sub-Contract agency: means a person or corporate body who has a Contract
with the Contract agency, duly authorised to carry out a part of the construction work
under the Contract.
1.28. Temporary Work: means work designed, constructed, installed, and removed by the
Contract agency that are needed for construction or installation of the work.
1.29. Tender/Bid, Tenderer/Bidder: are the synonyms and carry the same meaning where
ever used.
1.30. Variation: means any change in the work which is instructed or approved as variation
under this contract.
1.31. Work: The expression "work" or "works" where used in these conditions shall unless
there be something either in the subject or context repugnant to such construction, be
construed and taken to mean the work by virtue of contract, contracted to be executed,
whether temporary or permanent and whether original, altered, substituted or
additional.
2. INTERPRETATIONS AND DOCUMENTS
2.1 Interpretations
In the contract, except where the context requires otherwise:
a. words indicating one gender include all genders;
b. Words indicating the singular also include the plural and vice versa.
c. provisions including the word ―agree‖, ―agreed‖ or ―agreement‖ require the
agreement to be recorded in writing;
d. written‖ or ―in writing‖ means hand-written, type-written, printed or
electronically made, and resulting in a permanent record;
2.2 Documents Forming Part of Contract:
1. NIT with all amendments.
2. Instructions to Bidders (ITB, Bid Data Sheet with all Annexures)
3. Conditions of Contract:
i. Part I General Conditions of Contract and the Contract Data; with all
Annexures
ii. Part II Special Conditions of Contract.
4. Specifications
5. Drawings
6. Bill of Quantities
7. Technical and Financial Bid
8. Agreement, and
9. Any other document(s), as specified.
3. Language and Law
The language of the Contract and the law governing the Contract are stated in the Contract Data.
4. Communications
All certificates, notice or instruction to be given to the Contract agency by Employer/Engineer shall be sent to the address or contact details given by the Contract agency in [Annexure H of ITB]. The address and contact details for communication with the Employer/Engineer shall be as per the details given in the Contract Data. Communication between parties that are referred to in the conditions shall be in writing. The notice sent by facsimile (fax) or other electronic means (email) shall also be effective on confirmation of the transmission. The notice sent by registered post or speed post shall be effective on delivery or at the expiry of the normal delivery period as undertaken by the postal service. In case of any change in address for communication, the same shall be immediately notified to Engineer-in- Charge.
5. Subcontracting
Subcontracting shall be permitted for contracts of value more than amount specified in the Contract Data with following conditions.
a. The Contract agency may subcontract up to 25 percent of the contract price
with the approval of the Employer in writing, but will not assign the Contract.
Subcontracting shall not alter the Contract agency's obligations.
b. Following shall not form part of subcontracting:
i. Hiring of labour through a labour Contract agency.
ii. The purchase of Materials to be incorporated in the works.
iii. Hiring of plant& machinery
c. The sub-Contract agency will have to be registered in the centralized
registration system for Contract agencys of the GoMP.
6. Personnel
6.1 The Contract agency shall employ for the construction work and routine
maintenance the technical personnel as provided in the Annexure I-3 of Bid Data
Sheet, if applicable. If the Contract agency fails to deploy required number of
technical staff, recovery as specified in the Contract Data will be made from the
Contract agency.
6.2 If the Engineer asks the Contract agency to remove a person who is a member of
the Contract agency's staff or work force, stating the reasons, the Contract agency
shall ensure that the person leaves the Site within three days and has no further
connection with the Works in the Contract.
7. Force Majeure
7.1 The term ―Force Majeure‖ means an exceptional event or circumstance:
(a) Which is beyond a Party‘s control,
(b) Which such Party could not reasonably have provided against before entering
into the Contract,
(c) Which, having arisen, such Party could not reasonably have avoided or
overcome, and
(d) Which is not substantially attributable to the other Party. Force Majeure may
include, but is not limited to, exceptional events or circumstances of the kind
listed below, so long as conditions (a) to (d) above are satisfied:
(i) War, hostilities (whether war be declared or not), invasion, act of
foreign enemies,
(ii) Rebellion, t e r r o r i s m , s a b o t a g e by persons other than the
Contract agency‘s Personnel, revolution, insurrection, military or usurped
power, or civil war,
(iii) Riot, commotion, disorder, strike or lockout by persons other than
the Contract agency‘s Personnel,
(iv) Munitions of war, explosive materials, ionising radiation or contamination
by radio-activity, except as may be attributable to the Contract agency‘s
use of such munitions, explosives, radiation or radio-activity, and
(v) Natural catastrophes such as earthquake, hurricane, typhoon or volcanic
activity.
7.2. In the event of either party being rendered unable by force majeure to perform any
duty or discharge any responsibility arising out of the contract, the relative obligation
of the party affected by such force majeure shall upon notification to the other party
be suspended for the period during which force majeure event lasts. The cost and loss
sustained by either party shall be borne by respective parties.
7.3 For the period of extension granted to the Contract agency due to Force Majeure the
price adjustment clause shall apply but the penalty clause shall not apply. It is
clarified that this sub clause shall not give eligibility for price adjustment to contracts
which are otherwise not subject to the benefit of price adjustment clause.
7.4 The time for performance of the relative obligation suspended by the force majeure
shall stand extended by the period for which such cause lasts. Should the delay
caused by force majeure exceed twelve months, the parties to the contract shall be at
liberty to foreclose the contract after holding mutual discussions.
8. Contract agency's Risks
8.1 All risks of loss or damage to physical property and of personal injury and death
which arise during and in consequence of the performance of the Contract are the
responsibility of the Contract agency.
8.2 All risks and consequences arising from the inaccuracies or falseness of the
documents, drawing, designs, other documents and/or information submitted by the
Contract agency shall be the responsibility of the Contract agency alone,
notwithstanding the fact that the designs/ drawings or other documents have
been approved by the department/Nigam.
9. Liability for Accidents to Person
The Contract agency shall be deemed to have indemnified and saved harmless the
Government/Nigam against all action, suits, claims, demands, costs etc. arising in
connection with injuries suffered by any persons employed by the Contract agency or
his subContract agency for the works whether under the General law or under
workman's compensation Act, or any other statute in force at the time of dealing with
the question of the liability of employees for the injuries suffered by employees and
to have taken steps properly to ensure against any claim there under. Necessary claim
or insurance charges or premium shall be payable by the Contract agency only.
10. Contract agency to Construct the Works
10.1 The Contract agency shall construct, install and maintain the Works in accordance
with the Specifications and Drawings as specified in the Contract Data.
10.2 In the case of any class of work for which there is no such specification as is
mentioned in Contract Data, such work shall be carried out in accordance with the
instructions and requirement of the site SOR and site conditions etc.
10.3 The Contract agency shall supply and take upon himself the entire responsibility of
the sufficiency of the scaffolding, timbering, machinery, tools and implements, and
generally of all means used for the fulfillment of this contract whether such means
may or may not be approved or recommended by the Engineer.
11. Discoveries
Anything of historical or other interest or of significant value unexpectedly
discovered on the Site shall be the property of the Employer. The Contract agency
shall notify the Engineer of such discoveries and carry out the Engineer's instructions
for dealing with them.
12. Dispute Resolution System
12.1 No dispute can be raised except before the Competent Authority as defined in Contract
Data in writing giving full description and grounds of dispute. It is clarified that
merely recording protest while accepting measurement and/or payment shall not be
taken as raising a dispute.
12.2 No dispute can be raised after 45 days of its first occurrence. Any dispute raised after
expiry of 45 days of its first occurrence shall not be entertained and the Employer
shall not be liable for claims arising out of such dispute.
12.3 The Competent Authority shall decide the matter within 45 days.
12.4 Appeal against the order of the Competent Authority can be preferred within 30 days
to the Appellate Authority as defined in the Contract data. The Appellate Authority
shall decide the dispute within 45 days.
12.5 Appeal against the order of the Appellate Authority can be preferred before the
Madhya Pradesh Arbitration Tribunal constituted under Madhya Pradesh
MadhyasthamAdhikaranAdhiniyam, 1983.
12.6 The Contract agency shall have to continue execution of the Works with due diligence
Not with standing pendency of a dispute before any authority or forum.
B. Time Control 13. Programme
13.1 Within the time stated in the Contract Data, the Contract agency shall submit to
the Engineer for approval a Programme showing the general methods, arrangements,
order and timing for all the activities for the construction of works.
13.2 The program shall be supported with all the details regarding key personnel,
equipment and machinery proposed to be deployed on the works for its
execution. The Contract agency shall submit the list of equipment and machinery
being brought to site, the list of key personnel being deployed, the list of
machinery/equipment being placed in field laboratory and the location of field
laboratory along with the Programme.
13.3 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of the progress achieved on the timing of the
remaining Works, including any changes to the sequence of the activities.
13.4 The Contract agency shall submit to the Engineer for approval an updated
Programme at intervals no longer than the period stated in the Contract Data.
If the Contract agency does not submit an updated Programme within this
period, the Engineer may withhold the amount stated in the Contract Data from
the next payment certificate and continue to withhold this amount until the next
payment after the date on which the overdue Programme has been submitted.
13.5 The Engineer ‘ s approval of the Programme shall not alter the Contract
agency's obligations.
14. Extension of Time
The contract is for completion of works and therefore non approval of extension of
time shall not in any way invalidate the contract. The Contract agency will have to
complete the works. In the event of delays attributable to the Contract agency, the
EOT shall not be given by the engineer-in-charge and the liquidated damages shall be
levied from the Contract agency in accordance with the provisions of the contract. In
the event, the delays are not attributable to the Contract agency the EOT may be
issued by the Engineer-in-Charge without imposition of the liquidated damages either
suo-motto or on a written request of the Contract agency. It is clarified that out of the
total delays in completion of works, the EOT shall be issued only for the part, which
is not attributable to the Contract agency. Before issuing the EOT, Engineer Incharge
shall obtain the prior approval of competent authority.
14.1 If the Contract agency desires an extension of time for completion of the work on the
ground of his having been unavoidably hindered in its execution or on any other
grounds, he shall apply, in writing, to the Engineer-in-Charge, on account of which he
desires such extension. Engineer-in-Charge shall forward the aforesaid application to
the Competent Authority as prescribed.
14.2 The competent authority shall grant such extension at each such occasion within a
period of 30 days of receipt of application from Contract agency and shall not wait for
finality of work. Such extensions shall be granted in accordance with provisions under
clause-15 of this agreement.
14.3 In case the work is already in progress, the Contract agency shall proceed with the
execution of the works, including maintenance thereof, pending of the decision of the
competent authority as aforesaid with all due diligence.
15. Compensation for delay
15.1 The time allowed for carrying out the work, as entered in the agreement, shall be
strictly observed by the Contract agency.
15.2 The time allowed for execution of the contract shall commence from the date of signing of the agreement. It is clarified that the need for issue of work order is dispensed with.
15.3 In the event milestones are laid down in the Contract Data for execution of the
works, the Contract agency shall have to ensure strict adherence to the same.
15.4 Failure of the Contract agency to adhere to the timelines and/or milestones shall attract such liquidated damages as is laid down in the Contract Data.
15.5 In the event of delay in execution of the Works as per the timelines mentioned in the
Contract Data the Nigam shall retain from the bills of the Contract agency amount
equal to the liquidated damages leviable until the Contract agency makes such delays
good. However, the Nigam shall accept bankable security in lieu of retaining such
amount.
15.6 If the Contract agency is given extension of time after liquidated damages have
been paid, the Engineer in Charge shall correct any over payment of liquidated
damages by the Contract agency in the next payment certificate.
15.7 In the event the Contract agency fails to make good the delay until completion of
the stipulated contract period (including extension of time) the sum so retained shall
be adjusted against the liquidated damages levied.
16. Contract agency's quoted Rates
(i) The Contract agency‘s quoted r a t e referred to in the "Bid for works" will be
paid as per the price schedule given in the tender document
(ii) Work’s completeness
It is not the intent to specify completely herein all details of the work.
Nevertheless, work shall be complete and operative in all aspects.Any material or
accessories which may not have been specifically mentioned but which is necessary
for usual, satisfactory and trouble free operation of the system, shall be furnished by
the supplier without extra charge.
C. Quality Control
17. Tests
17.1 The Contract agency shall be responsible for:
a. Carrying out the tests prescribed in specifications, and
b. For the correctness of the test results, whether preformed in his laboratory or
elsewhere.
c. At least 20% test of material of prescribed frequencies should be carried out by
Govt. Engineering College/MPPWD acredited Lab/ LUN lab as directed by
Engineer-in- Charge. The charges for the same shall be paid by the Contract
agency otherwise will be deducted from the Contract agency‘s RA bill.
d. For cement concrete roads 20% of payment shall be withheld, which shall be
released after satisfactory core cutting test results, the payment of core cutting.
test shall be paid by Contract agency, and the same can be deducted from the
running bills of the Contract agency.
17.2 The Contract agency shall have to establish field laboratory within the time
specified and having such equipments as are specified in the Contract Data.
17.3 Failure of the Contract agency to establish laboratory shall attract such penalty as
is specified in the Contract Data.
18. Correction of Defects noticed during the Defect Liability Period
18.1 The Defect Liability Period of work in the contract shall be as per the Contract
Data.
18.2 The Contract agency shall promptly rectify all defects pointed out by the Engineer
well before the end of the Defect Liability Period. The Defect Liability Period shall
automatically stand extended until the defect is rectified.
18.3 If the Contract agency has not corrected a Defect pertaining to the Defect
Liability Period to the satisfaction of the Engineer, within the time specified by
the Engineer, the Engineer will assess the cost of having the Defect corrected, and the
cost of correction of the Defect shall be recovered from the Performance Security or
any amount due or that may become due to the Contract agency and other
availablesecurities.
D. Cost Control 19. Variations - Change in original Specifications, Designs, and Drawings etc.
19.1 The Employer shall have power to make any alterations, omissions or additions to
or substitutions in the original specifications, drawings, designs and instructions, that
may appear to him to be necessary during the progress of the work and the Contract
agency shall carry out the work in accordance with any instructions which may be
given to him in writing signed by the Engineer-in- charge, and such alterations,
omission, additions or substitutions shall not invalidate the contract and any
altered, additional or substituted work, which the Contract agency may be directed
to do in the manner above specified, as part of the work, shall be carried out by
the Contract agency on the same conditions in all respects on which he agrees to do
the main work.
19.2 The time for the completion of the work shall be adjusted in the proportion that the
altered, additional or substituted work bears to the original contract work and the
certificate of the Assistant Engineer, Executive Engineer shall be conclusive as to such
proportion.
20. Extra items
20.1 All such items which are not included in the priced BOQ shall be treated as extra
items.
21. Payments for Variations and / or Extra Quantities
21.1 The rates for such additional (Extra quantity), altered or substituted work / extra
items under this clause shall be worked out in accordance with the following
provisions in their respective order:-
a. The Contract agency is bound to carry out the additional (Extra quantity),
work at the same rates as are specified in the contract for the work.
b. If the item is not in the priced BOQ and is included in the SOR, the
rate shall be arrived at by applying above or below percentage of the the
quoted rates and PAC amount.
c. If the rates for the altered or substituted work are not provided in
applicable SOR - such rates will be derived from the rates for a similar class
(type) of work as is provided in the contract (priced BOQ) for the work.
d. If the rates for the altered, substituted work cannot be determined in the
manner specified in the sub clause (c) above - then the rates for such
composite work item shall be worked out on the basis of the concerned
Schedule of Rates minus/plus the percentage quoted by the Contract agency.
e. If the rates for a particular part or parts of the item is not in the Schedule of
Rates and the rates for the altered, or substituted work item cannot be
determined in the manner specified in sub clause (b) to (d) above, the rate for
such part or parts will be determined by the Competent Authority as defined in
the Contract Data on the basis of the rate analysis derived out of prevailing
market rates when the work was done.
f. But under no circumstances, the Contract agency shall suspend the work on
the plea of non-acceptability of rates on items falling under sub clause (a)
to (d). In case the Contract agency does not accept the rate approved by
the Engineer in Charge for a particular item, the Contract agency shall
continue to carry out the item at the rates determined by the Competent
Authority. The decision on the final rates payable shall be arrived at through
the dispute settlement procedure.
Note : All SOR listed as per Annexure E.
22. No compensation for alterations in or restriction of work to be carried out.
22.1 If at any time after the commencement of the work, the Nigam, for any reason
whatsoever, not require the whole or any part of the work as specified in the bid to
be carried out; the Nigam shall give notice in writing of the fact to the Contract
agency and withdraw that whole or any part of the work.
22.2 The Contract agency shall have no claim to any payments or compensation
whatsoever, on account of any profit or advantage which he might have derived from
the execution of work in full or on account of any loss incurred for idle men and
machinery due to any alteration or restriction of work for whatsoever reason.
22.3 The Employer may supplement the work by engaging another agency to execute such portion of the work, without prejudice to his rights.
23. No Interest Payable
No interest shall be payable to the Contract agency on any payment due or awarded
by any authority.
24. Recovery from Contract agencys
Whenever any claim against the Contract agency for the payment arises under the
contract, the Employer may be entitled to recover such sum by:
(a) Appropriating, in part or whole of the Performance Security and Additional Performance Security, if any; and/or Security Deposit and / or any sums payable under the contract to the Contract agency.
(b) If the amount recovered in accordance with (a) above is not sufficient, the balance sum may be recovered from any payment due to the Contract agency under any other contract of the Nigam, including the securities which become due for release.
(c) The Employer shall, further have an additional right to effect recoveries as arrears of land revenue under the M.P. Land Revenue Code.
25. Tax 25.1 Please refere Annexure J.
25.2 The liability, if any, on account of quarry fees, royalties, octroi and any other taxes and
duties in respect of materials actually consumed on public work, shall be borne by the
Contract agency.
25.3 Any changes in the taxes due to change in legislation or for any other reason shall not
be payable to the Contract agency.
25.4 GST for all civil, electrical, water supply etc. items shall be payable as per prevailing
rules by department.
25.5 Good & Service Tax (GST) for work contract service
The Contract agency/successful bidder shall be abide by the GST laws, the following
conditions are required to be fulfilled :-
a) Contract agency must have valid GST registration.
b) As per PWD manual financial bid will inclusive of all taxes except GST. TDS shall
be deducted as applicable by the law in force at the time being.
c) Financial bid should be excluded GST, GST is additionally payable, if not exempted
under GST laws.
d) Contract agency will have to be raised proper GST invoice, mentioning clear-cut
bifurcation like different value of road and building separately basic amount, SGST,
CGST and IGST tax amount if applicable etc. in pursuance to invoicing rules
prescribed in GST law alongwith SAC/HSNcode.
e) Financial comparison for determination of L1, L2 shall be done deemed to be
excluding applicable GST amount. But other all taxes amount will be inclusive.
f) GST, TDS shall be deducted if applicable under GST law at the time of bill passing
date.
g) Successful bidder will have to file applicable GST return within scheduled time frame
under GST law (GSTR01,02,03 etc.), if failure in filing such return within schedule
time frame is found, MPIDC Ltd., Regional Office, Indore shall have the right to
deduct/recover such involved GST amount, Interest penalty etc. accordingly, and
none of any excuse shall be considered.
h) In situation of non-compliance of GST provisions, MPIDC-RO Indore may hold the
due payments of Contract agency.
i) Contract agency will have to follow changes of GST law if any done by the GST
department.
j) Contract agency will have to follow order‘s/instructions or any changes by the
Central/State Govt. pertaining to this works taxes.
26. Check Measurements
26.1 The Employer reserves to itself the right to prescribe a scale of check
measurement of work in general or specific scale for specific works or by other
special orders. 100% measurement of work done shall be recorded or checked by
concerning Assistant Engineer of the Contract work and 10% measurement of
contract amount shall be checked by Executive Engineer of the Contract work.
26.2 Checking of measurement by superior officer shall supersede measurements by
subordinate officer (s), and the former will become the basis of the payment.
26.3 Any over/excess payments detected, as a result of such check measurement or
otherwise at any stage up to the date of completion of the defect liability period
specified in this contract, shall be recoverable from the Contract agency, as per
clause 24 above.
27. Termination of Contract
27.1 If the Contract agency fails to carry out any obligation under the Contract, the
Executive Director/Engineer in Charge may by notice require the Contract agency to
complete the work/make good the failure and to remedy it within a specified
reasonable time.
27.2 The Executive Director shall be entitled to terminate the Contract if the
Contract agency
a) Abandons the Works or otherwise plainly demonstrates the intention not
to continue performance of his obligations under the Contract;
b) The Contract agency is declared as bankrupt or goes into liquidation other
than for approved reconstruction or amalgamation;
c) without reasonable excuse fails to comply with the notice to correct a
particular defect within a reasonable period of time;
d) The Contract agency does not maintain a valid instrument of financial
security as prescribed;
e) The Contract agency has delayed the completion of the Work.
f) If the Contract agency fails to deploy machinery and equipment or personnel
or set up a field laboratory as specified in the Contract;
g) If the Contract agency, in the judgment of the Engineer‘ s has engaged in
corrupt or fraudulent practices in competing for or in executing the contract;
h) Any other fundamental breaches as specified in the Contract .
27.3 In any of these events or circumstances, the Nigam may, upon giving 30 day‘s notice
to the Contract agency, terminate the Contract and expel the Contract agency from the
Site. However, in the case of sub-paragraph (b) or (g) of clause 27.2, the Executive
Director may terminate the Contract immediately.
27.4 Not with standing the above, the Executive Director may terminate the Contract for
convenience by giving notice to the Contract agency.Risk and cost means amount
recoverable from Contract agency to get remaining work completed at his risk and
cost.
28. Payment upon Termination
28.1 If the contract is terminated under clause 27.3, the Engineer shall issue a
certificate for value of the work accepted on final measurements, less Advance
Payments and Penalty as indicated in the Contract. The amount so arrived at shall
be determined by the Engineer and shall be final and binding on both the parties.
28.2 Payment on termination under clause 27. 4 above -
If the Contract is terminated under clause 27.4 above, the Engineer shall issue a
certificate for the value of the work done, the reasonable cost of removal of
Equipment, repatriation of the Contract agency's personnel employed solely on the
Works and the Contract agency's costs of protecting and securing the Works and less
advance payments received up to the date of the certificate, less other recoveries due
in terms of the contract and less taxes due to be deducted at source as per applicable
law.
28.3 If the total amount due to the Employer exceeds any payment due to the
Contract agency, the difference shall be recovered as per clause 24 above.
29. Performance Security
29.1 The Contract agency shall have to submit performance security and additional
performance security, if any, as specified in Contract at the time of signing of the
contract. The Contract agency shall have to ensure that such performance security
and additional performance security, if any, remains valid for the period as specified
in the Contract Data.
29.2 The performance security shall be released as mentioned in tender document
29.3 Additional performance security shall be released as mentioned in tender document
30. Security Deposit and EMD
30.1 Security Deposit shall be deducted from each running bill at the rate as specified in
the Contract Data. The total amount of Security Deposit so deducted shall not exceed
the percentage of Contract Price specified in the Contract Data. Perofrmance security
shall be released as mentioned in contract data .
31. Price Adjustment – NOT APPLICABLE
32. Mobilization and Construction Machinery Advance – NOT APPLICABLE
33. Secured Advance –NOT APPLICABLE
34. Payment Certificates
The payment to the Contract agency will be as follows for construction work:
(a) The Contract agency shall submit to the Engineer monthly statements of the value of
the work executed less the cumulative amount certified previously, supported with
detailed measurement of the items of work executed.
(b) The Engineer shall check the Contract agency‘s monthly statement and certify
the amount to be paid to the Contract agency.
(c) The value of work executed shall be determined, after submission of bill by
bidder, based on the measurements approved by Engineer.
(d) The value of work executed shall comprise the value of the quantities of the items in
the Bill of Quantities completed.
(e) The value of work executed shall also include the valuation of Variations and
Compensation Events.
(f) All payments shall be adjusted for deductions for advance payment, security
deposit, other recoveries in terms of contract and taxes at source as applicable
under the law.
(g) The Engineer may exclude any item certified in a previous certificate or reduce the
proportion of any item previously certified in any certificate in the light of later
information.
(h) Payment of intermediate certificate shall be regarded as payments by way of advance
against the final payment and not as payments for work actually done and completed.
(i) Intermediate payment shall not preclude the requiring of bad, unsound and
imperfect or unskilled work to be removed and taken away and reconstructed or be
considered as an admission of the due performance of the Contract agency any part
thereof, in any respect or the occurring of any claim.
(j) The payment of final bill shall be governed by the provisions of clause 36 of
GCC.
D. Finishing the Contract 35. Completion Certificate
35.1 A Completion Certificate in the prescribed format in Contract shall be issued by
Engineer in charge after physical completion of the Work.
35.2 After final payment to the Contract agency, a Final Completion Certificate shall
be issued in the prescribed format as given in the Contract data shall be issued by
the engineer in charge. .
36. Final Account
36.1 The Contract agency shall supply the Engineer with a detailed account of the
total amount that the Contract agency considers payable for works under the Contract
within 21 days of issue of certificate of physical completion of works. The Engineer
shall issue a Defects Liability Certificate and certify any payment that is due to the
Contract agency within 45 days of receiving the Contract agency‘s account if it is
correct and complete. If the account is not correct or complete, the Engineer shall
issue within 45 days a schedule that states the scope of the corrections or additions
that are necessary. If the Account is still unsatisfactory after it has been resubmitted,
the matter shall be referred to the Competent Authority as defined in the Contract
Data, who shall decide on the amount payable to the Contract agency after hearing the
Contract agency and the Engineer in charge..
36.2 In case the account is not received within 21 days of issue of Certificate of
Completion as provided in clause 35.1 above, the Engineer shall proceed to
finalize the account and issue a payment certificate within 28 days.
F. Other Conditions of Contract 37. Currencies
All payments will be made in Indian Rupees.
38. Labour
38.1 The Contract agency shall, unless otherwise provided in the Contract, make his
own arrangements for the engagement of all staff and labour, local or other, and
for their payment, housing, feeding and transport.
38.2 The Contract agency shall, if required by the Engineer, deliver to the Engineer a
return in detail, in such form and at such intervals as the Engineer may
prescribe, showing the staff and the numbers of the several classes of labour from
time to time employed by the Contract agency on the Site and such other information
as the Engineer may require.
39. Compliance with Labour Regulations
39.1. During continuance of the Contract, the Contract agency and his sub-Contract
agencys shall abide at all times by all existing labour enactments and rules made
there under, regulations, notifications and bye laws of the State or Central
Government or local authority and any other labour law (including rules),
regulations, bye laws that may be passed or notification that may be issued under
any labour law in future either by the State or the Central Government or the local
authority. Salient features of some of the major labour laws that are applicable to
construction industry are given in the Contract Data. The Contract agency shall keep
the Employer indemnified in case any action is taken against the Employer by the
competent authority on account of contravention of any of the provisions of any Act
or rules made their under, regulations or notifications including amendments. If the
Employer is caused to pay or reimburse, such amounts as may be necessary to cause
or observe, or for non-observance of the provisions stipulated in the
notifications/byelaws/Acts/Rules/ regulations including amendments, if any, on the
part of the Contract agency, the Engineer/Employer shall have the right to deduct
from any money due to the Contract agency including his amount of
performance security. The Employer/Engineer shall also have right to recover from
the Contract agency any sum required or estimated to be required for making good
the loss or damage suffered by the Employer. The employees of the Contract agency
and the Sub-Contract agency in no case shall be treated as the employees of the
Employer at any point of time.
40. Audit and Technical Examination
Nigam/Government shall have the right to cause an audit and technical
examination of the works and the final bill of the contract including all supporting
vouchers, abstract etc. to be made after payment of the final bill and if as a result of
such audit and technical examination any sum is found to have been overpaid in
respect of any work done by the Contract agency under the contract or any work
claimed by him to have been done under the contract and found not to, have been
executed, the Contract agency shall be liable to refund the amount of overpayment
and it shall be lawful for Nigam to recover the same from him in the manner
prescribed in clause 24 above and if it is found that the Contract agency was paid less
than what was due to him, under the contract in respect of any work executed by him
under it, the amount of such under payment shall be duly paid by Nigam/Government
to the Contract agency.
41. Death or Permanent Invalidity of Contract agency If the Contract agency is an individual or a proprietary concern, partnership concern,
dies during the currency of the contract or becomes permanently incapacitated, where
the surviving partners are only minors, the contracts shall be closed without levying
any damages/ compensation as provided for in clause 28.2 of the contract agreement.
However, if the competent authority shall enter into a fresh agreement for the
remaining work strictly on the same terms and conditions under which the contract
was awarded.
42. Jurisdiction
This contract has been entered into the State of Madhya Pradesh and its validity,
construction, interpretation and legal effect shall be subjected to the courts at the place
where this agreement is entered into. No other jurisdiction shall be applicable.
[End of GCC]
Contract Data
GCC Clause
Particulars
Data
1.14 Employer Executive Director, M.P. Industrial Development Corporation Ltd., R.O. Indore
1.15 Engineer Junior Engineer/Assistant Engineer, M.P. Industrial Development Corporation Ltd., R.O. Indore
1.16 Engineer in Charge Executive Engineer, M.P. Industrial Development Corporation Ltd., R.O. Indore
1.22 Stipulated Period of
Completion
6 (six) months including 3 months Trial Run + 5
Years O & M.
3 Language & Law of Contract English
4 Address & contact details of
the Contract agency
As per 'Annexure-H'
Address & contact details of
the Employer –
phone, Fax, e-mail.
Executive Director, M.P. Industrial Development
Corporation Ltd., Regional office, Indore
Atulya IT Park, 101, First floor, near Crystal IT
Park, Khandwa Road, Indore.
Ph. 0731-2970611, 2974363, 2971311
e-mail : [email protected]
5 Subcontracting permitted for
the Contract Value
No
6 Technical Personnel to be
provided by the Contract
agency
As per 'Annexure-I' (Format I-3)
Penalty, if Technical Personnel not employed during original execution of work
As per contract agreement
10 Specifications As per 'Annexure-E'
Drawings As per 'Annexure - N'
GCC Clause
Particulars
Data
12 Competent Authority for
deciding dispute under
Dispute Resolution System
Executive Director, M.P. Industrial
Development Corporation Ltd., R.O. Indore
Appellate Authority for
deciding dispute under
Dispute Resolution System
Managing Director, M.P. Industrial
Development Corporation Ltd. Bhopal
13 Period for submission of
updated construction
program
As per approved PERT chrat/contract
agreement
Amount to be withheld
for not submitting
construction program in the
prescribed period
As per decision of engineer in charge
14 Competent Authority for
granting Time Extension
Executive Director, MPIDC, R.O.Indore
15 Milestones laid down for
the contract
Contract
Yes
If Yes, details of
Milestones
As per 'Annexure - O'
Liquidated damage As per 'Annexure - P'
16 List of equipment for lab As per annexure -Q
Time to establish Site lab 15 days from date of signing of the Agreement
Penalty for not
establishing field
Laboratory
1% of Contract Amount per month,
17 Defect Liability Period 3 months from the date of completion of construction work.
Note :- In accordance with clause 18.3 (GCC),
the Engineer in Charge shall intimate the
Contract agency about the cost assessed, for
making good the defects and if the Contract
agency has not corrected defects, action for
correction of defects shall be taken by the
Engineering in Charge as below at the risk &
cost of Contract agency:-
(a) Deploy department labour and material
Or
(b) Engage a Contract agency by issuing a work
order at contract rate / SOR rate
Or
(c) Sanction supplementary work in a existing
agreement to a Contract agency for zonal works
or similar other work.
Or
(d) Invite open tender
Or
(e) Combination of above
18 Competent Authority for
determining the rate
Executive Director, M.P. Industrial
Development Corporation Ltd., R.O. Indore
19
Any other condition for
breach of contract
Yes as below:
If the Contract agency fails to achieve 50%
financial progress in any milestone and /or fails
to achieve 75% financial progress in two
consecutive mile stones
20 Penalty Penalty Shall include :
(a) Security deposit as per clause 30 of General Conditions of Contract, and
(b) Liquidated Damages imposed as per clause 15 or
Performance Security (Guarantee) including
Additional Performance Security (Guarantee),
if any, as per clause 29 of General Conditions
of Contract, whichever is higher
21
Performance guarantee
(Security) shall be valid up
to
5 year beyond the Completion of Defect Liability
Period / O&M Period
22
Security Deposit to be
deducted from each
running bill
At the rate of 5% of Gross Amount of Running Bill
Maximum limit of deduction of Security Deposit
5% of Final Gross Amount of Final Bill.
23 Clause 31.1(1) Price
adjustment shall be
applicable
Not Applicable
Clause 31.2.4 Weightages of Component in the work
Not Applicable
24 Clause 32.1 Mobilization and Construction Machinery Advance Applicable
No
Clause 32.2 If yes,
Unconditional Bank
Guarantee
No
Clause 32.3 If yes, Rate of
interest chargeable on
advances
No
Clause 32.4 If yes, Type &
Amount of Advance
payment that can be paid
No
Clause 32.5 If yes,
Recovery of advance
payment
No
33 Clause 33.1 Secured
Advance Applicable
No
Clause 33.2 if yes,
Unconditional Bank
Guarantee
Not Applicable
Clause 33.2 if yes,
Amount of Secured
Advance
Not Applicable
Clause 33.3 if yes,
Conditions for secured
advance
Not Applicable
Clause 33.4 if yes,
Recovery of Secured
advance
Not Applicable
35
Completion Certificate –
after physical completion of
the Work
As per 'Annexure - U'
Final Completion
Certificate – after final
payment on completion of
the Work
As per 'Annexure- V'
36
Competent Authority Executive Director, M.P. Industrial
Development Corporation Ltd., R.O. Indore
39
Salient features of some of
the major labour laws that
are applicable
As per 'Annexure-W'
40 Apeallant Authority Managing Director, M.P. Industrial
Development Corporation Ltd., R.O. Indore
ANNEXURE – N (See clause 10 of Section 3 -GCC )
Drawings
Note : Drawings are annexed
S.no. Drawing Title
1 Tentative Layout of Effluent Tretment Plant (CETP/ETP)
2 Tentative Process Flow Diagram of Effluent Treatment Plant (CETP/ETP)
3 Master plan of Confectionary cluster
ANNEXURE – O (See clause 15 of Section 3 -GCC )
Details of Milestone
Sl. No.
Milestone
Duration
Physical Achievement
1 1st Upto 2 months from
commencement of work
20% of the Contract Amount
2 2nd
Upto 4 months from
commencement of work
50% of the Contract Amount
3 3rd
Upto 6 months from
commencement of work
100% of the Contract Amount
ANNEXURE – P (See clause 15 of Section 3 –GCC)
Compensation for Delay
If the Contract agency fails to achieve the milestones, and the delay in execution of
work is attributable to the Contract agency, the Employer shall retain an amount from
the sums payable and due to the Contract agency as per following scale -
i. Slippage up to 25% in financial target during the milestone under
consideration — 2.5% of the work remained unexecuted in the related time span. ii. Slippage exceeding 25% but Up to 50% in financial target during the
milestone under consideration
- 5% of the work remained unexecuted in the related time span.. iii. Slippage exceeding 50% but Up to 75% in financial target during the
milestone under consideration
-7.5% of the work remained unexecuted in the related time span.. iv. Slippage exceeding 75% in financial target during the milestone under
consideration
-10% of the work remained unexecuted in the related time span. Note: For arriving at the dates of completion of time span related to different milestones,
delays which are not attributable to the Contract agency shall be considered. The
slippage on any milestone is if made good in subsequent milestones or at the time of
stipulated period of completion, the amount retained as above shall be refunded.
In case the work is not completed within the stipulated period of completion along
with all such extensions which are granted to the Contract agency with penalty, the
compensation shall be levied on the Contract agency at the rate of 0.5% of contract
amount per monthfor first 3 months, 0.75% per month for 3 to 6 months ,and 1% per
month beyond 6 months of delay limited to a maximum of 10% of contract price.
(See clause 32 of Section 3 –GCC)
Bank Guarantee Form for Mobilization and Construction
Machinery Advance
To,
…………………………… (name of Employer)
…………………………… (address of Employer)
…………………………… (name of Contract agency)
In accordance with the provisions of the General Conditions of Contract, clause
31 ("Mobilization and Construction Machinery Advance") of the above-
mentioned Contract …………………………… (name and address of Contract
agency) (hereinafter called "the Contract agency") shall deposit with
................................. (name of Employer) a bank guarantee to guarantee his proper
and faithful performance under the said Clause of the Contract in an amount of
…………………….. (amount of Guarantee)* …………………………… (in words).
We, the …………………… (bank of financial institution), as instructed by the
Contract agency, agree unconditionally and irrevocably to guarantee as primary
obligator and not as surety merely, the payment to ………………. (name of
Employer) on his first demand without whatsoever right of obligation on our part and
without his first claim to the Contract agency, in the amount not exceeding
……………… (amount of guarantee)* ……………………………….. (in words).
We further agree that no change or addition to or other modification of the terms of
the Contract agency or Works to be performed there under or of any of the Contract
documents which may be made between …………………… (name of Employer) and
the Contract agency, shall in any way release us from any liability under this
guarantee, and we hereby waive notice of any such change, addition or modification.
This guarantee shall remain valid and in full effect from the date of the
advance payment under the Contract until ……………………. (Name of Employer)
receives full repayment of the same amount from the Contract agency.
Yours truly,
Signature and Seal :- ………………….
Name of Bank/Financial Institution :- ………………….
Address : ………………………………………………...
Date :- …………………………..
* An amount shall be inserted by the Bank of Financial Institution representing
the amount of the Advance Payment, and denominated in Indian Rupees.
Annexure – T (See clause 33 of Section 3 –GCC)
Bank Guarantee Form for Secured Advance
INDENTURE FOR SECURED ADVANCES
(Not Applicable)
Annexure – U (See clause 35 of Section 3 –GCC)
Physical Completion Certificate
Name of Work:
……………………………………………….…………………………………………………
……………………………………………….…………………………………………………
……………………………………………….…………………………………………………
Agreement No. ………..……………..…………. Date ………………………..……………..
Amount of Contract Rs. ………………………………………………………………….…….
Name of Agency : ………………………………………………………………………….…
Used MB No. ------------------------------------
Last measurement recorded
a. Page No & MB No. …………………………..
b. Date ……………………….
Certified that the above mentioned work was physically completed on ……………….
(date) and taken over on ……………….. (date) and that I have satisfied myself
to best of my ability that the work has been done properly.
Date of issue
S.Q.C. Agency
Assistant Engineer Executive Engineer
…..................................... ………………………
…..................................... ………………………
…..................................... ………………………
Annexure – V (See clause 35 of Section 3 –GCC)
Final Completion Certificate
Name of Work:
……………………………………………….…………………………………………………
……………………………………………….…………………………………………………
……………………………………………….…………………………………………………
Agreement No. ………………………………………….… Date……………………………
Name of Agency : ……………………………………………………………………………
Used MB No. ----------------------------------------
Last measurement recorded
a. Page No & MB No. …………………………..
b. Date ……………………….
Certified that the above mentioned work was physically completed on ………………. (date)
and taken over on ……………….. (date).
Agreement amount Rs. …………………..
Final Amount paid to Contract agency Rs. ---------------------- Incumbency of officers for the
work
I have satisfied myself to best of my ability that the work has been done properly.
Date of issue
Assistant Engineer Executive Engineer
…..................................... ……………………….
…..................................... ……………………….
…..................................... ……………………….
Annexure – W (See clause 39 of Section 3 –GCC)
Salient Features of Some Major Labour Laws Applicable
a) Workmen Compensation Act 1923: - The Act provides for compensation in case of
injury by accident arising out of and during the course of employment.
b) Payment of Gratuity Act 1972: - Gratuity is payable to an employee under the Act
on satisfaction of certain conditions on separation if an employee has completed the
prescribed minimum years (say, five years) of service or more or on death the rate of
prescribed minimum days‘(say, 15 days) wages for every completed year of service.
The Act is applicable to all establishments employing the prescribed minimum
number (say, 10) or more employees.
c) Employees P.F. and Miscellaneous Provision Act 1952: The Act Provides for
monthly contributions by the Employer plus workers at the rate prescribed (say, 10%
or 8.33%). The benefits payable under the Act are:
i. Pension or family pension on retirement or death as the case may be. ii.
Deposit linked insurance on the death in harness of the worker.
iii. Payment of P.F. accumulation on retirement/death etc.
d) Maternity Benefit Act 1951: - The Act provides for leave and some other benefits to
women employees in case of confinement or miscarriage etc.
e) Contract Labour (Regulation & Abolition) Act 1970: - The Act provides for
certain welfare measures to be provided by the Contract agency to contract labour
and in case the Contract agency fails to provide, the same are required to be
provided, by the Principal Employer by Law. The principal Employer is required to
take Certificate of Registration and the Contract agency is required to take
license from the designated Officer. The Act is applicable to the establishments or
Contract agency of Principal Employer if they employ prescribed minimum (say 20)
or more contract labour.
f) Minimum Wages Act 1948: - The Employer is to pay not less than the Minimum
Wages fixed by appropriate Government as per provisions of the Act if the
employment is a scheduled employment. Construction of buildings, roads, runways is
scheduled employment.
g) Payment of Wages Act 1936: - It lays down as to by what date the wages are to be
paid, when it will be paid and what deductions can be made from the wages of the
workers.
h) Equal Remuneration Act 1979: - The Act provides for payment of equal wages for
work of equal nature to male and female workers and for not making discrimination
against female employees in the matters of transfers, training and promotions etc.
i) Payment of Bonus Act 1965: - The Act is applicable to all establishments employing
prescribed minimum (say, 20) or more workmen. The Act provides for payments of
annual bonus within the prescribed range of percentage of wages to employees
drawing up to the prescribed amount of wages, calculated in the prescribed manner.
The Act does not apply to certain establishments. The newly set-up establishments are
exempted for five years in certain circumstances. States may have different number of
employment size.
j) Industrial Disputes Act 1947: - The Act lays down the machinery and procedure for
resolution of industrial disputes, in what situations a strike or lock-out becomes illegal
and what are the requirements for laying off or retrenching the employees or closing
down the establishment.
k) Industrial Employment (Standing Orders) Act 1946: - It is applicable to
all establishments employing prescribed minimum (say, 100, or 50). The Act
provides for laying down rules governing the conditions of employment by the
Employer on matters provided in the Act and gets these certified by the designated
Authority.
l) Trade Unions Act 1926: - The Act lays down the procedure for registration of trade
unions of workmen and Employers. The Trade Unions registered under the Act have
been given certain immunities from civil and criminal liabilities.
m) Child Labour (Prohibition & Regulation) Act 1986: - The Act prohibits
employment of children below 14 years of age in certain occupations and processes
and provides for regulations of employment of children in all other occupations and
processes. Employment of child labour is prohibited in building and construction
industry.
n) Inter-State Migrant Workmen’s (Regulation of Employment & Conditions of
Service) Act 1979: - The Act is applicable to an establishment which employs
prescribed minimum (say, five) or more inter-state migrant workmen through an
intermediary (who has recruited workmen in one state for employment in the
establishment situated in another state). The Inter-State migrant workmen, in an
establishment to which this Act becomes applicable, are required to be provided
certain facilities such as Housing, Medical-Aid, Travelling expenses from home up to
the establishment and back etc.
o) The Building and Other Construction workers (Regulation of Employment and
Conditions of Service) Act 1996 and the Cess Act of 1996: - All the establishments
who carry on any building or other construction work and employs the prescribed
minimum (say, 10) or more workers are covered under this Act. All such
establishments are required to pay cess at the rate not exceeding 2% of the cost of
construction as may be modified by the Government. The Employer of the
establishment is required to provide safety measures at the building or construction
work and other welfare measures, such as canteens, first-aid facilities, ambulance,
housing accommodations for workers near the work place etc. The Employer to
whom the Act applies has to obtain a registration certificate from the Registering
Officer appointed by the Government.
p) Factories Act 1948: - The Act lays down the procedure for approval of plans before
setting up a factory, health and safety provisions, welfare provisions, working hours,
annual earned leave and rendering information regarding accidents or dangerous
occurrences to designated authorities. It is applicable to premises employing the
prescribed minimum (say, 10) persons or more with aid of power or another
prescribed minimum (say, 20) or more persons without the aid of power engaged in
manufacturing process.
Part – II Special Conditions of Contract [SCC]
1. Tender must be quoted on turnkey basis including design, supply, construction, erection &
commissioning, operation & maintenance of proposed CETP with complete infrastructure
including 100 KL capacity over head water tank for recycled water. Basic specifications,
process flow diagram/ layout of proposed CETP is provided in tender document.
2. CETP is being constructed for confectionary units. Effluent received will be from
confectionary industries, accordingly parameters of inlet effluent and outlet treated water
shall be considered for design.
3. Lump Sum tender shall be inclusive of Material , Labour including Statuary permissions etc
complete so as to commission, operate & maintain the plant in all respect.
4. Interested bidders may visit the project site before bidding to understand the volume of
work. The tenderer shall acquaint himself with the proposed site of work, its sub soil strata,
soil investigation reports, underground water tables and its approach roads before quoting his
rates. In the site proposed for the construction of CETP already some structures are present
which may have to dismentaled and the dismental materials to be diposed off as per
instruction of the incharge. No extra charge will admissible in this account. The bidder may
use this construction if it fits in his design with all his responsibility. It is prferrable to
incorporate this partial RCC foundation work of earlier planned STP in the design of CETP
work.
5. Contract agency will be responsible for obtaining the Environmental Clearance (EC) and all
statutory clearences of proposed CETP from SIEEA/MoEF followed by CTE/CFE from
MPPCB before starting the construction of CETP.
6. Contract agency will obtain pollution legal liability insurance of CETP during O & M period
for take care to adverse effect of industrial area/surrounding environment due to CETP
operational activities. Failure to submit copy of insurance policy under pollution legal
liability insurance, Contract agency will be responsible to pay compensation of damage to
environment & penalty imposed by MPPCB/CPCB/MoEF, if any.
7. Contract agency will be responsible EIA studies and for all permission / clearance / NOC
from Govt authorities for establishment of CETP & further operation of CETP like Boiler,
DG set, fire fighting system etc if required.
8. Any violation of Environmental norms, non-renewal of consent / authorization, Contract
agency will stop the O & M of CETP & intimate to MPIDC immediately with corrective
action plan. Non-compliances of consent conditions imposed by MPPCB, Contract agency
will be responsible for paying fine / penalty & termination of contract by recurrence of such
kind of events.
9. Cost of Consumables, wear and tear parts/ spare parts,for Operation & Maintenance period of
CETP shall be in the scope of Contract agency however electricity & water shall be provided
by MPIDC free of cost during operation and maintenance period.
10. Contract agency will be responsible for disposal of waste generated from CETP as per
norms.
11. Contract agency will explore maximum possibilities for re-use / recycle of waste to generate
revenue to reduce per KL of cost of effluent treatment. In this connection, Contract agency
will require to submit quantities of reusable / resalable / recyclable waste along with revenue
generated from resale of waste.
12. Proposed CETP will be developed with complete infrastructure as mentioned in bid
document.
13. Effluent treatment plant will be operated by Contract agency for units of Confectionary
cluster. In this connection, Contract agency will be responsible for maintaining readings of
effluent received from individual units on day to day basis. These data will be submitted to
MPIDC and Concerning units.
14. Contract agency will depute competent supervisor for day to day operation & maintenance
of common CETP, so that supervisor can monitor the incoming effluent daily basis for any
deviation / disputes in effluent quantity & quality.
15. MPIDC will authorize to Contract agency for taking samples of effluent from user industry
premises, in case of deviation circumstances.
16. Contract agency will send the sample in well packed, sealed & labelled manner to MoEF
approved laboratory / MPPCB laboratory immediately with intimation to MPIDC.
17. Contract agency will maintain daily log sheet, deviation, observations, flow coming to
CETP, effluent discharges by user units.
18. Contract agency will submit complete data of CETP operation & maintenance to MPIDC on
monthly basis.
19. Contract agency will make ensure regular uses of personnel protective equipments, uniform,
medical records of his deployed site staff. Contract agency will maintain the record of health
& safety management for submission to MPIDC on his demand.
20. Contract agency will make ensure smooth operation & maintenance of CETP by close
monitoring of operational parameters. In this regard any sampling & analysis of incoming
effluent from user industries required for maintaining ZLD, it will be carried out by Contract
agency on his cost.
21. Contract agency may also need to trouble shoot the problems of CETP during routine
operation of common CETP, if any occurs, so that zero liquid discharge concept always
meet the requirements of MPPCB.
22. In addition to qualified / experience supervisor, Contract agency will depute skilled operator
in all three shift, so that common CETP can be run round the clock as emergency services
for facilitating to user industries.
23. Contract agency will make ensure to ZLD concept, at any circumstances. Violation of this
condition will attract penalty and / or termination of contract in terms of agreement of
MPIDC with Contract agency for this work.
24. The Contract agency has to deploy skilled, experienced staff for operation of plant, One
Reliever operator to shift operators to avoid absence condition in any conditions.
25. Contract agency has to deploy qualified Supervisor in general shift for liaison with
MPIDC/MPPCB/User Units of Industrial Area.
26. All spares /consumables/ wear-tear/ applicable items testing equipments ,drain valves etc to
be arranged and used by the Contract agency as per manufacturer‘s recommendations and
good engineering practices.
27. All tools and tackles required for Electrical and Mechanical Maintenance/Cleaning
/Removing grass and vegetation etc such as Brooms/ Forks /Bamboos/Spades /Pick axe
/Pans/ Grass cutting tools or Machine etc. shall be provided by the Contract agency.
28. The Contract agency, his staff engaged shall abide with safety rules and regulations,
Environment policy provisions and the prevailing regulations, guidelines framed by the
Central / State Pollution Control Boards.
29. The Contract agency should deployed manpower experience in Operation and Maintenance
of CETP of industrial area.
30. The ZLD conditions, if not found within CETP premises, the remedial measures are to be
taken immediately by the operating agency, till rectification is done and correct result is
obtained. Any penalty on this account shall be borne by the Contract agency.
31. The instructions of inspecting officer from MPIDC and Pollution Control Board shall be
binding on the Contract agency for compliance.
32. The agency has to depute a Supervisor capacity person to take instructions from
MPIDC/Pollution board officers and comply the same from Contract agency staff. The
operators should be well qualified and experienced in the field operate such capacity plants.
33. Payment to the staff has to be made strictly in accordance to minimum wages Act.
34. The following terms of Contract shall supplement the General conditions of Contract,
wherever there is a conflict the provision herein shall prevail over those in the General
conditions of Contract.
35. Any disposal of material outside CETP shall be prohibited. The waste/disposed material
shall be disposed from CETP in environmentally & legally manner by the Contract agency at
his own cost.
36. The plant shall include such guards,hand-railing,access steelwork,walkways,etc,as may be
required to meet the current relevant regulations for the safety of personnel and of the plant,
and to afford adequate and safe access to all parts of it. All shall be of substantial design and
construction. All moving parts shall be covered with safetyguards. Where corrosion or
abrasion of materials may be expected from contact with water or sediment or from any
other cause, the Contract agency shall supply suitably resistant materials. The Contract
agency shall make all reasonable efforts to reduce noise and vibration to aminimum. All
rotating parts of the plant shall be statically and dynamically balanced so that they operate
over all specified conditions without undue vibration.The equipment and system involved
shall be designed such that noise level at any operating time shall not exceed the limit as per
norms .
37. Platforms, ladders, walkways and railings for the safe and easy access to the units shall be
provided. CI rungs shall be provided for safe and easy maintenance of all chambers,
manholes and CETP units.
38. During commissioning of CETP, the Contract agency shall arrange at his own cost, analysis
of the composite effluent samples all the effluent parameters required form an external
laboratory approved by MoEF under EPA act 1986 or from the MPPCB laboratory. The
results shall conform to the performance guarantee for the plant which shall be a pre requisite
for the takeover of the plant. In case of non-compliance to the guaranteed ZLD for given
design input conditions, the Contract agency shall take necessary measures to bring the plant
to the desired performance.
39. In case during the guarantee test run, the effluent flow or pollution load shall be found to be
less than the rate input, the Contract agency shall undertake that as and when rated
throughput and organic load conditions are available, the Contract agency shall extend
necessary assistance to achieve the guaranteed output quality, through re-deputation of his
personnel at a later date at mutually agreed terms.
40. The Contract agency shall depute plant personnel in the Operation & Maintenance practice
for the common Effluent Treatment Plant units during the operation & maintenance period
for following aspect:
Familiarization with operational procedures and testing parameters.
Hands on experience on Operation of Equipment & chemical consumptions.
Routine preventive maintenance activities of the facilities.
Knowledge of emergency and breakdown systems.
Operational control & parameters to achieve treated output within norms.
Data sheet/ log book & record keeping as per norms of MPPCB & Standard
practices
Safety regulations and accident prevention.
41. The scope of services shall include the Preparation and Submission of Operation &
Maintenance Manual (One soft copy and 3 sets of hard copies) prior to plant commissioning.
The Manual shall cover the following aspects: Brief process description & flow sheet. Unit
wise function and description, equipment details with sizes and as build drawings, operational
instructions, maintenance procedures. Plant start-up, commissioning, normal operations,
effluent parameters testing procedures, emergency operation steps etc required for smooth
operation & maintenance of CETP units.
42. All electrical works including electrical motors, for the various equipment, cabling, Motor
Control centre, starters, earthing conductors and earth pits etc. are to be provided by the
Contract agency. The scope of work includes all necessary civil works like panel foundations,
cable trenches, cable supports, unit lighting, etc. complete. Electrical Substation shall be
provided by MPIDC all electrical work needed for electrical system of plant from the
substation shall be responsibility of Contract agency.It is advised to visit the site to see the
location of temporaray and permanent connection .
43. The manufacturer‘s guarantee for design, workmanship and performance for all bought out
items shall be made available to the MPIDC. In the event of failure of any particular
equipment which fails more than three times during the performance period as mentioned in
bid document, the Contract agency shall replace at his own cost that equipment.
44. Bidder has to make ensure himself by visiting Industrial Area to understand the requirements
of proposed CETP for confectionary units..
45. Bidder has to design the CETP as per specification and process specified in the bid document.
The submitted designs and drawings shall be got checked from IIT/NIT/Govt. Engineering
college. The charges for the same shall be paid by Contract agency. The Contract agency
shall have to execute the work as per approved designs and drawings.
46. Bidder will be responsible for all the Legal and registration compliances (including
permission / consent to establishment, consent to operate, hazardous waste authorization etc
from MPPCB including Environmental Clearance (EC) etc.) on behalf of MPIDC, legal ,
departmental Fee will be paid/ reimbursed by MPIDC. MPIDC will support to the bidder for
the required documentation and presentation as a principal client of a project. Construction
period includes the clearance and compliance time required. In case of substantial delay, not
attributable to Contract agency, shall be considered for time extension.
47. Bidder has to take all legal permission for DG set installation & operation, & associated
NOC/ permission required for CETP establishment & operation from Govt authorities.
48. It will be the responsibility of Bidder to bear the cost of chemical consumption, power, and
disposal wastes from CETP.
49. Bidder has to consider all environmental &safety standards for development of CETP units
equipment‘s as per IS standards under factories act.
50. Bidder has to mention quantities of such type of waste with possibilities of reusable /
recyclable waste like organic residue if any which would be source of revenue to owner /
MPAKVN through successful bidder,
51. Bidder has to take consideration of pollution legal liability insurance during operation phase
of proposed CETP.
52. Bidder has to mention require manpower with qualification & experience for Operation &
Maintenance period for successfully services to industries Industrial Area
53. Royalty clearance certificate from the concerned Mining Department of the concerned
District is must before payment of Final Bill.
54. If, for any reasons, any part of the site is not available temporarily for some time, for part of
the work under the contract, the agreed construction schedule shall be suitably modified and
Contract agency shall diligently divert his men and materials to utilize them appropriately,
profitably and no claim of damages whatsoever shall be entertained on this account.
However, the Contract agency shall be allowed extension of time for completing the work as
deemed fit by the competent authority. The Contract agency shall also not be entitled for any
compensation for any loss suffered by him and revision in the rates quoted by him:- a) On account of delay in commencing the work by the Contract agency.
b) On account of reduction in the scope of work.
c) On account of suspension of work or abandoned after award of work.
55. The Contract agency shall make his own arrangement for obtaining electric connection
required for execution of work and make necessary payments directly to the concerned
departments and nothing extra shall be payable on this account. The Contract agency shall
make his own arrangement for water required for construction
56. Subletting shall be allowed only for specialized works like Electrical, Water supply work
such as over head tank, with prior intimation/permission of ED M.P. Industrial Development
Corporation Ltd R.O. Indore, but the Principal Contract agency shall not be relieved of any
responsibilities as per agreement.
57. The water for construction work shall be got tested quarterly from the laboratory stalled at
site and approved by the assistant engineer to ensure its suitability for construction. The
charges for these tests and related arrangements shall be borne by the Contract agency. In the
event of water found unsuitable for construction, the Contract agency shall make alternative
arrangement for suitable water from any other source to the satisfaction of the Engineer-in-
charge. However, the Contract agency shall not be paid any extra on this account.
58. On account of security consideration, some restrictions may be imposed by the security staff
on the working movement of men and materials etc. The Contract agency shall be bound to
follow all such restrictions/ instructions and he shall organize his work accordingly. No claim
on this account, whatsoever, shall be entertained.
59. The Contract agency shall take all precautions to avoid accidents by exhibiting necessary
caution boards day and night, speed limit boards, red flags, red lights and providing barriers.
He shall be responsible for all damages and accidents caused to existing/ new work due to
negligence on his part. No hindrance shall be caused to traffic during the execution of the
work. The Contract agency will have to work out and take approval of any diversion plan
needed for execution of work from appropriate authority.
60. The Contract agency shall take all preventive measures against any damage caused by rain,
snowfall, floods or any other natural calamity, whatsoever during the execution of the work.
The Contract agency shall be fully responsible for any damage to the Owners property and to
the work for which the payment has been advanced to him under the contract. This will also
cover the defect liability period. Nothing extra on this account shall be payable to the
Contract agency on this account.
61. The work shall be carried out, complying in all respects, with the requirements of relevant
bye-laws of the local body under the jurisdiction of which the work is to be executed,
specifications, condition of contract, drawings or as directed by Engineer-in-charge.
62. The Contract agency shall comply with proper and legal orders and directions of the local or
public authority or municipality and abide by their rules and regulations and pay all fees and
charges which are liable to be paid.
63. All materials to be incorporated in the work shall be arranged by the Contract agency and
shall be in accordance with the specifications laid down and as directed by the Engineer-in-
charge.
64. The Contract agency shall submit samples of material to the MPIDC, R.O Engineer for
approval. Such samples of materials which affect aesthetics of the work shall also be got
approved from the Engineer-in-charge of the project before procuring bulk supplies. These
approved samples shall be preserved and retained in the custody of the Engineer-in-charge as
standards of materials till the completion of the work. The cost of such samples shall be
borne by the Contract agency and nothing shall be payable on this account over the
Agreement rates.
65. In order to ensure quality of work during its execution the Contract agency shall be required
to get all the necessary mandatory and other tests as per specifications / IS codes, carried out
on materials / work from the site laboratory as per the direction of the Assistant
Engineer/Junior Engineer . The cost of all material, testing charges and conveyance from the
site may be borne by the Contract agency. In addition to it, MPIDC Ltd., Regoinal office
Indore shall conduct a random of 20% tests as instructed by , which shall be conducted at in
MPPWD approved Lab / LUN Lab / Government Engineering college as instructed by
Assistant Engineer/Junior Engineer and the cost of the same shall be borne by Contract
agency.
66. In case any material at work is found sub-standard the same shall be rejected by Assistant
Engineer/Junior Engineer representative and the same shall be removed from the site of work
within 48 hours, failing which the same shall be got removed by the Assistant
Engineer/Junior Engineer at the risk and cost of the Contract agency without giving any
further notice and time.
67. The Contract agency shall procure 43 grade (conforming to IS: 8112)/53 grade Ordinary
Portland Cement only as required for the work from the reputed manufacturers of cement, i.e.
from A.C.C., Ultratech, J.K., or Birla only. Supply of cement shall be taken in 50 kg bags
bearing manufacturers name and ISI marking. Samples of cement arranged by the Contract
agency shall be taken by the Engineer-in-charge and got tested in accordance with provisions
of relevant IS codes. In case test results indicate that the cement arranged by the Contract
agency does not conform to the relevant IS codes, the same shall stand rejected and shall be
removed from the site by the Contract agency at his own cost within a week‗s time of written
order from the Engineer-in-charge, to do so. Portland Pozzolana Cement will not be
permitted.
68. The Contract agency shall procure steel reinforcement bars TMT-FE-415/500 (Thermo
Mechanically Treated bars) conforming to relevant IS codes IS- 32, IS- 1139 and IS-1786
from SAIL, TISCO, VIZAG RINL, GOYAL, ZINDAL, AMBA, SURYA. Structural steel of
main Producer only shall be permitted for use. The Contract agency shall have to obtain and
furnish test certificates to the Engineer‘s in respect of all supplies of steel brought by him to
the site of work. Samples shall also be taken and got tested by the Engineer as per the
provision in this regard in relevant IS codes. In case the test results indicate that the steel
arranged by the Contract agency does not conform to BIS codes the same shall stand rejected
and shall be removed from the site of work by the Contract agency at his cost within a week's
time from the written orders from the Engineer-in-charge to do so. The cost of steel, testing
charges and to & fro cartage shall be borne by the Contract agency.
The steel reinforcement shall be stored by the Contract agency at site of work in such a way
as to prevent distortion and corrosion and nothing extra shall be paid on this account. Bars of
different sizes and lengths shall be stored separately to facilitate easy counting and checking
at any time as and when desired by the Engineer-in-charge.
69. Signboard size 2‘ x 4‘ in angle Iron 50 x 50 x 5 mm MS sheet i/c civil work Painting, Writing
work as per direction of Nigam shall be supplied and installed at site free of cost before start
of work. Location of signboard shall be decided by Nigam.
70. Necessary test report on the expense of Contract agency performed by PWD accredit
laboratory / Govt. Engineering college / LUN laboratory will be accepted before preparation
of bill in addition to field test to be conducted at work site by own installed lab of Contract
agency.
71. The Contract agency shall be responsible for completing the work and for satisfying all terms
and conditions of the Contract without any extra payment over his quoted rates unless
otherwise specified. The Contract agency shall quote his rate for various items of work
accordingly and no claim whatsoever shall be entertained for any incidental or extra work
involved in the execution of the work as per nomenclature of the item and the specifications
indicated in the tender documents.
72. The Contract agency shall provide, at his own cost instruments for surveying, weighing and
measuring purpose at the site of work as may be necessary for execution of the work.
73. The Contract agency shall conduct Total Station Survey of the site, including, Bench
Marking Pillars, DTM, GTS Bench Triangulation, 3d-Polylines, etc., as per IRC-SP-19, IRC-
5 and MORT&H specifications and soil investigations as required. The Contract agency shall
get the methodology and output model approved by the Engineer-in-charge. The survey shall
include validation wherever required. The Contract agency shall use Digital GPS if required;
Total Station based Method for layout of proposed work including vertical profiling as per
approved Design and Drawings.
74. LT/HT Panel, IMCC panel and all other required end to end associated accessories shall be
provided for CETP/ETP. LT/HT power supply shall be provided for operation included in the
scope of this contract and power connection need to be obtained by the Contract agency in
coordination with MPPKVVCL. The power connetion will be in the name of the Executive
Director MPIDC Indore MP.
75. Submission of Completion Drawings/as built drawings and Coloured photographs of
completed works in Hard copy and Soft Copy to the Indore regional office. Any other item as
directed by the Engineer-in-charge including appropriate Indemnity and Insurance policies as
specified and as required.
76. All stipulated measures regarding labour employment and their welfare are to be complied
with. Contract agency will pay the minimum wages to workers according to the rates fixed
by Collector, Rangwasa Indore.
77. Cleaning of site before handing over of the Works to the Employer.
78. Traffic Management and Safety
a) The Traffic Management Plan shall be evolved in close co-ordination with Assistant
Engineer/Junior Engineer and Suitable precautions shall be taken to ensure safety of Road
Users and work Personnel during execution by all proper means.
b) The Contract agency shall prepare traffic diversion plan and provisions for smooth flow
of traffic during execution at site..
c) The Contract agency has to arrange for complete safety of the persons working for the
project, users of the Road, i.e. Public and vehicles. The Contract agencys Personnel shall
ensure the safety by provision of Traffic Diversion where ever necessary by using
diversion signs, traffic drums traffic cones, blinkers, safety tapes, and thermoplastic paint
markings etc. securing the area of work from traffic flow. No extra payment shall be
given for the same.
d) For night working, necessary florescent Marking on Traffic Signs/barricading to be
provided that it should be visible at night. The safety in charge Personnel shall be
provided with florescent jackets. Proper illumination of the work site shall be ensured by
the Contract agency during night working.
79. Insurance
The Contract agency shall provide, in the joint names of the MPIDC and the Contract agency,
insurance cover from the Start Date to the end of the O&M Period, in the amounts and
deductibles stated in the Contract Data for the following events which are due to the Contract
agency‘s risks:
i. Loss of or damage to the Works, Plant and Materials and equipment;
ii. Loss of or damage of property (except the Works, Plant, Materials and Equipment) in
connection with the Contract; and
Policies and Certificates for Insurance shall be delivered by the Contract agency to the ED-
MPIDC Ltd., R.O. Indore before the Start Date. All such insurance shall provide for
compensation to be payable in the types and proportions of currencies required to rectify the
loss or damage incurred.
If the Contract agency does not provide any of the policies and certificates required, the ED-
MPIDC Indore may affect the insurance which the Contract agency should have provided and
recover the premiums the ED has paid from payments otherwise due to the Contract agency
or, if no payment is due, the payment of the premiums shall be a debt due.
Alterations to the terms of insurance shall not be made without the approval of the E.D.,
MPIDC Indore.
The Contract agency shall take photographs of site prior to the commencement of work,
during construction fortnightly and at the end of Completion of Work and shall submit soft
and hard copies to the MPIDC Ltd., Indore.
80. All DI pipes shall be supplied at site after Engineer‘s inspection at manufacturing plant. Only
Jindal Saw Ltd. or Electro Steel Casings, or Tata Make DI Pipes /as mentioned in tender will
be used in the Contract.
81. Electrical Works
a) Connection, testing, charging etc, of electrical works from the concerned authorities
of MPPKVVCL & electrical Inspector and obtaining necessary permission will be
responsibility of the Contract agency only. No extra payment/fees will be payable in
this regard.
b) To provide and use standard make of all materials & equipments as approved by
MPPKVVCL
c) To contact and pursue the concerning authorities to arrange necessary shut downs as
& when required to execute the work and final handling over to them with all
necessary formalities, testing and commissioning as per procedure under rules and
regulation of MPPKVVCL & MPERC Bhopal etc.
d) The Electrical Works shall be carried out by a Contract agency or his authorised
person holding ‗A‘ Class License issued by the office of Chief Electrical Inspector
Bhopal (Madhya Pradesh) or equivalent as required. The Contract agency shall
appoint licensed electrical supervisors and wiremen to carry out all the electrification
work.
e) All material used by the Contract agency in Installation of Street Lighting works, shall
be of specified make.
f) Contract agency shall submit test certificates from the manufactures in four copies for
all the materials/Equipment. Guarantee report shall be jointly in the name of MD
MPPKVVCL and Contract agency.
g) After completion of work, test report should be submitted to MPPKVVCL and NOC
is to be obtained from MP Licensing Board if necessary, one copy of the report to be
submitted to client alos.
h) The scope includes permanent electrical power connection for the effluent treatment
plant and obtaining necessary permissions from the concern authorities will be
responsibility of Contract agency only.
82. (a) Degree of specials shall be decided at the time of layout of the work
(b) Necessary pipe connection of Individual plot for effluent collection and Delivery of
Recycled water will be responsibility of the Contract agency, Location of such connection
work will be decided during execution of the contract work.
83. The Contract agency shall make his own arrangement for obtaining electric connection
required for execution of work and make necessary payments directly to the concerned power
supply compley and nothing extra shall be payable on this account. The Contract agency shall
make his own arrangement for water required during construction period.
84. All stipulated measures regarding labour employment and their welfare are to be complied
with. Contract agency will pay the minimum wages to workers according to the rates fixed
by Collector, Indore
85. For night working, necessary florescent Marking on Traffic Signs/barricading to be provided
that it should be visible at night. The safety in charge Personnel shall be provided with
florescent jackets. Proper illumination of the work site shall be ensured by the Contract
agency during night working.
86. The Engineer-in-charge shall give the possession of the Site to the Contract agency. The
Contract agency shall be responsible to co-ordinate with the engineer‘s and Concerned
Authorities for cutting of trees, shifting of utilities, Removal of Encroachments etc. (if any)
and making the site unencumbered from the project construction area required for completion
of the Work. The Contract agency will not be entitled for any additional compensation for
delay in cutting of Trees, Shifting of utilities and removal of Encroachments by the
Employer. The Engineer-in-charge shall consider extension of time to such delays.
87. The Contract agency shall construct and maintain such sufficient store houses, yards etc. as
directed by the Assistant Engineer/Junior Engineer for proper up keep of the Material, Plant
and Machinery and records for due discharge of Contract agencys Obligations towards the
Contract. Space for these works will have to be made available by Contract agency himself as
per his own convenience at his own costs. Engineer-In-Charge will be provided free access to
these premises, the site handed over to the Contract agency will have to be vacated in the
same condition within 1 (one) months of the completion of the contract.
88. The Contract agency shall maintain a SITE ORDER BOOK (issued by Employer) at the site
of work. As far as possible all orders regarding the works are to be entered in the book. The
following officials during inspection, shall record their observations in it.
i) Any Authorized representative of MPIDC Ltd.,
ii) Engineer-In-Charge of MPIDC Ltd., Regional Office, Indore
iii) Any other Senior Official.
89. The Works are liable for inspection/checking by CTE (Chief Technical Examiner) or any
other Authority from concerned State Government Departments. Any defects pointed out by
CTE or any other Authority mentioned above shall have to be made good by the Contract
agency at his cost.
90. All serviceable material obtained from excavation shall be the property of MPIDC Ltd., RO,
Indore Contract agency shall deposit the same in MPIDC Ltd., RO, Indore Store at his own
cost.
91. The Contract agency has to arrange for complete safety of the persons working for the
project, users of the Road, i.e. Public and vehicles. The security Personnel shall ensure the
safety by provision of Traffic Diversion where ever necessary by using diversion signs,
traffic drums traffic cones, blinkers, safety tapes, and thermoplastic paint markings etc.
securing the area of work from traffic flow. No extra payment shall be given for the same.
92. All external electrical work shall be subjected to approval of MPPKVVCL, Indore. It shall be
responsibility of the Contract agency to get the require approval of Estimates, Drawing &
Design from MPPKVVCL before the execution of work. Work shall be paid to the Contract
agency as per actual work done based on MPPKVVCL‗s approval. No extra payment shall be
made for this. The supervision charges (all statutory charges levied by MPPKVVCL) against
sanctioned estimates/charging permissions/permanent connection of CETP will be paid by
the MPIDC Ltd.
93. The Contract agency shall submit the mix design all different grade of concrete etc. material
to be used by the Contract agency from Govt. Engineering college/MPPWD approved Lab at
his own cost.
94. In case of Electricity Power failure, DG set shall be provided by the Contract agency at his
own cost and no claim is allowed for the same.
95. The drawings, Data etc. given in the tender documents are just for the guidance of the
Contract agency. The Contract agency is advised to visit the site and collect all information
required for competative bidding. No extra claim will be admissible in this account.
96. During Operation & Maintenance period additional staff/worker in addition as mentioned in
contract be employed/engaged to complete the job at the earliest so that works may not
disturbed for longer period.Daily attendance of above mentioned manpower shall be
maintained by client MPIDC Ltd., R.O. Indore during working days and government holidays
which shall be verified from Concern Junior Engineer/Assistant Engineer. In the case of
absent or leave beyond 2 days per month, deduction in bills of O&M, security period shall be
made by client field staff at the rate of Rs. 2000/- per day and for above grade at the rate Rs.
5000/- per day.
SECTION 4
BILL OF QUANTITIES (BOQ)
Name of Work - Design, Supply, Erection, Testing & Commissioning of 200 KLD
Common Effluent Treatment Plant (CETP) based on ZLD Process, on Turn-key basis and its
Operation and Maintenance for five years at I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore (M.P.)
Probable Amount of Contract: Rs. 4.00 crs.
(Rs. In Figure) – Rs. 4.00 Crores
(Rs. In Words) – Rupees Four Crore only
S. N. Description Unit Amount
(INR)
A Survey, Investigation Design, Construction, Supply,
Erection, Testing Commissioning of proposed Effluent
Treatment Plant of Capacity 200 KLD based on 100%
ZLD concept as per norms of CPBC/MOEF/MPPCB
including complete infrastructure, campus boundary,
approach road, campus development , utilities, staff quarter,
in-house laboratories, all necessary Civil, Piping,
Mechanical, DG set and Electrical & Instrumentation
works, recycled water network & plantation wherever
required by industries etc. complete including 3 months trial
run and Five Years Operation & Maintenance of complete
facility after successful commissioning on turnkey basis.
Plant shall be fully automated. (Rates to be quoted
including consultancy cost of all necessrry permissions as
mentioned in bid document, Operation & maintenanace
and cost with all material & Manpower etc. Complete.)
Total Turnkey Execution Cost
LS
Total Quoted Amount in Words-------------------------------------------------------------------
1. The bidder shall fill in rates on turnkey basis as per scope of work given in bid
document.
2. GST will be paid extra at the applicable rates to the Contract agency. Rest of the other
taxes, cess, levies, fee toll etc. shall be the responsibility of Contract agency to pay.
Signature of Bidder with seal
Name: ---------------------------
Designation------------------
Address--------------------------
Assistant Engineer Executive Engineer
SECTION 5
AGREEMENT FORM
AGREEMENT
This agreement, made on the ……………. Day of …………………………… between
…………….. (name and address of Employer) (hereinafter called " the Employer) and
……………… (name and address of Contract agency) hereinafter called "the Contract
agency" of the other part.
Whereas the Employer is desirous that the Contract agency execute
…………………… (and identification number of Contract) (hereinafter called "the Works")
and the Employer has accepted the Bid by the Contract agency for the execution and
completion of such Works and the remedying of any defects therein, at a cost of Rs.
………………………………………
NOW THIS AGREEMENT WITNESSED AS FOLLOWS:
1. In this Agreement, words and expression shall have the same meanings as are respectively assigned to them in the conditions of contract hereinafter referred to and they shall be deemed to form and be read and construed as part of this Agreement.
2. In consideration of the payments to be made by the Employer to the Contract agency as hereinafter mentioned, the Contract agency hereby covenants with the Employer to execute and complete the Works and remedy any defects therein in conformity in all aspects with the provisions of the contract.
3. The Employer hereby covenants to pay the Contract agency in consideration of the execution and completion of the Works and the remedying the defects wherein Contract Price or such other sum as may become payable under the provisions of the Contract at the times and in the manner prescribed by the Contract.
4. The following documents shall be deemed to form and be ready and construed as part of this Agreement viz. The following list of the documents will form the priority in case of dispute.
i. Letter of Acceptance
ii. Contract agency's Bid
iii. Condition of Contract: General and Special
iv. Contract Data
v. Bid Data
vi. Drawings
vii. Bill of Quantities and
viii. Any other documents listed in the Contract Data as forming part of the
Contract.
In witnessed whereof the parties there to have caused this Agreement to be executed
the day and year first before written.
The common Seal of …………………… was hereunto affixed in the presence of :
Signed, Sealed and Delivered by the said …….... in the presence of :
Binding Signature of Employer ……………………………………..
Binding Signature of Contract agency ……………………………………
Sheet : 1
Break up schedule for payment
Name of work : Design , Supply, Erection, Testing & Commissioning of 200 KLD
Common Effluent Treatment Plant (CETP) based on ZLD Process, on Turn-key basis and
its Operation and Maintenance for five years at I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore (M.P.)
Sr.
No. Stages of Work
Corresponding total
payment up to 100%
A Turnkey Project Execution Phase- Common CETP 85% of the agreement
value
Sub break up of A
1 On approval of Design of CETP including overhead tank
and submission of TOR for EC
2% of total cost
2 Completion of Civil Works including over head tank 13% of total cost
3 Supply of Electro-Mechanical Equipments Electrical,
Piping, Instrumentation, Utilities items, Laboratory
Equipment and all miscellaneous Items
30% of total cost
4 Complete Installation of Electro- Mechanical Equipments,
Electrical, Piping, Instrumentation, Utilities and all
miscellaneous Items
40% of total cost
5 Commissioning and Testing of Common CETP with
complete infrastructure including all permission /
clearance / NOC from Govt authorities
10% of total cost
6 Balance amount of turnkey execution after three months
trail run from the date of successful commissioning of
CETP
5% of total cost
Total 100%
B Operation and Maintenance of CETP for 5 years (the
amount will be paid in monthly instalment)
15% of the agreement
value
Sub break up of B
1 1st Year 10%
2 2nd
Year 15%
3 3rd
year 20%
4 4th
year 25%
5 5th
year 30%
Total- 100%
Total A (85%) +B (15%) 100%
Note:- For Item A- payments on sub break-up can be done on prorata basis. Contract agency
should submit the detailed list with cost of mechanical and electrical part at the time of
submission of Project Planning Schedule. However, the Decision of Engineer-in-charge in
regard of payment of sub break-up shall be final.
Sheet : 2
PROFORMA FOR APPLICATION FOR EXTENSION OF TIME
PERIOD
PROFORMA FOR APPLICATION FOR EXTENSION OF TIME PERIOD
1. Name of the Contract agency :
2. Name of the work as given in the agreement :
3. Agreement no :
4. Estimated tender amount :
5. Date of commencement of work as per :
Agreement
6. Period allowed for completion of works as :
Per agreement
7. Date of completion stipulated in agreement :
8. Period for which extension of time has been :
given previously
9. Reasons for which extensions have been :
previously given.(Copies of the previous
extensions to be attached).
10. Period for which extension is applied for :
11. Hindrances on account of which extension :
is applied for with dates on which
hindrances occurred and the period for which
these are likely to last.
a) Serial no :
b) Nature of hindrance
c) Whether Contract agency is responsible for delay: :
d) Date of occurrence :
e) Period for which it is likely to last :
f) Period for which extension required :
for this particular hindrance
g) Overlapping period if any, with :
h) Reference to item(e) above :
i) Net extension applied for :
j) Amount of penalty i/e to be levied if Contract agency is responsible for delay.
:
12. Extension of time required for extra work :
13. Details of extra works and amount involved
a) Total value of extra works :
b) Proportionate period of extension of time :
on estimated amount put to tender.
Total extension of time required for 11 & 12 :
Assistant Engineer Executive engineer
Sheet : 3 (Appendix D I) List of Acceptable Makes of Equipment
LIST OF APPROVED MAKE FOR MECHANICAL AND ELECTRICAL
EQUIPMENTS:
The following is the list of products and name of the approved manufacturer against each
product. The bidder shall quote rates using these products:
Recommended Make of Equipment’s for CETP
Sr.
No. Equipments Make
1 Stripper Shivlac / Mazda / Praj / Equivalent
2 Agitated Thin Film Drier (ATFD) Shivlac / Mazda / Praj / Equivalent
3 Cooling Tower Thermax / Unimod/ GEA/ Equivalent
4 Boiler Thermax / IAEC/Cether
Vessels/Thyssenkrupp/ Equivalent
5 DG Sets Kirloskar/Cummins/ Mahindra/ Equivalent
6 pH meter/ pH sensor Rosemont /Hach/Equivalent
7 Flow Meter ABB/MARCK/IVC/E&H / Rosemount /
Equivalent
8 PLC Delta/L&T / Siemens / ABB/ Equivalent
9 Electrical Cables Finolex / RR Cable/Havel‘s / Polycab /
Equivalent
10 Electrical Components for MCC
Panel
L&T / Siemens / ABB/ Equivalent
11 HDPE / PP Tanks Supreme/Kisan/Syntax /Ganga/Equivalent
12 MS Pipies Tata / Jindal / Surya/ Equivalent
13 HDPE Pipes Hasti / Supreme/Kisan /Supreme/ Phenolex/
Equivalent
14 PVC Pipes Supreme/Kisan/Astral / Finolex/ Supreme
15 CI/CS Valves Marck/karan/utam/Zoloto/Kirloskat / Sant /
Kor / Equivalent
16 PP Valves Supreme/Kisan/Astral/Prashit/ Equivalent
17 Waste water Pumps Kirloskar / Wilo/ CG/KSB/ Beacon /
Equivalent
18 Dosing Pumps Asia LMI/ E Dose/Positive/ Swellor /
Equivalent
19 Agitators / Flash Mixers / Flocculator Geo Miller / HDO/ Distington/ Equivalent
20 Gear Boxes Greaves/ Elecon/ Radicon / Equivalent
21 Steel Material TISCO/ SAIL / Equivalent
22 Cement ( OPC Grade-53) ACC/ Grasim/Ultratech/ Ambuja
23 Fire Extinguisher ABC/ Minimax/ Equivalent
24 Laboratory Instruments Hach/ WTW/ Other Standard Brands
25 Evoprator Integro Engg./ Janvik Engineers / Fintek
Engineers / Equivalent
S. No. Items List of Vendors
1. Mechanical Bar Screens HUBER, Johnson, Voltas, Jash
2. Belt Conveyor V oltas, Triveni, Geo, Miller
3. Mechanical grit scrapper
mechanism Voltas Triveni Geo Miller
4. Clarifier/Reactor Clarifier
Mechanism Voltas Triveni Geo Miller
5. Air Blowers (Screw Type) AERZENAtlas Copco Gardner
Denver
6. Electric Hoist / Chain Pulley Indef W.H. Brady & Co ,Hercules
Hoists
7. Gear Box Radicon – Greaves ,Elecon
8. Submersible Pumps Grundfos, ABS, ITT
9. Horizontal Centrifugal
Pumps
Mather & Platt (I) Ltd., Wier Ltd.,
KSB, Grundfos, Sulzer
10. Screw Pump ROTO, UT Pump, Netzsch, Wilo
11. Dosing Pumps Milton Roy, Grundfos
12. Diffusers OTT, EDI USA, REHAU, ITT USA
13. Centrifuge
Alfa Laval India Ltd.,
Pennwalt Ltd.,
Humboldt and Wedag
14. Agitators Jash, Geo Miller, Triveni
15. Submersible Mixers KSB, ABS, Grundfos
16. Chlorinators
Metito, Chlorocontrol
(CHLOROCONTROL)
Pennwalt India Ltd.
Perfect chloro (PENNWALT)
17. CI / Aluminum Open
Channel Gate Jash, Shivpad, Yaswant
18. Butterfly Valves Inter Valves, VAG, IVC
19. Knife Gate Valves Jash, Bray, Flowtek
20. Sluice Valves
Kirloskar Brothers Ltd.
Indian Valve Company,
VAG
21. Non return valves
Kirloskar Brothers Ltd.
Indian Valve Company (IVC)
VAG
22. Sluice Gates
Jash Engineering (P) Ltd.
The Indian Valve Co.
Oriental Castings
Upadhaya
23. Diaphragm Valves BDK, Flowteck, CRANE
24. Gun Metal Gate Valve Leader, Zoloto
25. Dash Fasteners Hilti,Fischer
S. No. Items List of Vendors
26. Motors
Kirloskar Electric Co. Ltd.
Siemens Limited
Crompton Greaves
ABB
27. Cast Iron Pipes & Fittings
and Dismantling Joints
Baroda Rollings Mills
The Indian Iron & Steel Company
Ltd.
Bharat Industrial Corporation
Oriental Castings
Electro Steel Castings
Jindal
Kejriwal
28. DI Pipes Electro Steel Castings, Jindal,
Kejriwal, SriKalahasti pipes
29. MS Pipe Tata Pipes, Jindal Pipes, SAIL
30. Stainless Steel Pipe Jindal, Parkash, SumiTomo
31. HDPE/DWC Pipe Finolex, Supreme, Duraline
32. uPVC Pipes Supreme, Finolex, Astral, George
Fisher
33. Online DO Analyser and
Transmitter
HACH/ Endress Hauser/
Yokogawa
34. On Line pH / Residual
Chlorine Measuring System HACH / Endress & Hauser
35. Pressure Gauge H Guru Instruments Pvt. Ltd. ,
Waaree, FEIBIG
36. Actuator AUMA, Rotork, Marsh
37. Soft Starter for motors Rockwell, Schneider, Siemens,
Danfoss, ABB, L&T
38. DOL Starters for motors L&T, Siemens, ABB, Schneider
C&S
39. LT Variable Frequency
Drive (VFD)
Schneider, Danfoss, Siemens, ABB,
L&T
40. SMPS Pheonix, Schneider, ABB., Rockwell
41. Computers for DCS & Office HP, Compaq, Dell
42. Cables(Power & Control) Havells, Gloster, KEI, KEC
International
43. Intelligent MCC
Panel/MPCB Panel/ L.T
Panels / PDB / LDB Panel
L&T, Siemens, Schneider, ABB
44. Switchgear L&T, Siemens, Schneider, ABB
GE
45. Control Gear L&T, Siemens, Schneider, ABB
GE
46. Contactor L&T, Siemens, Schneider, ABB
47. Over Load Relay L&T, Siemens, Schneider, ABB
48. PUSH BUTTONS and Push
Button Station L&T, Siemens
S. No. Items List of Vendors
49. LT Electronic Over current/
Overload Relay L&T, ABB, Siemens
50. MV/HT Electronic Motor
Protection Relay L&T, ABB, Siemens
51. Vacuum Circuit Breakers Siemens, ABB, CGL, L&T
52. Air Circuit Breaker L&T, Siemens, Schneider
53. Moulded Case Circuit
Breaker (MCCB) /MCB /
RCBO
L&T, Siemens, Schneider, ABB ,
GE, Legrand
54. Street Light / Flood Light
Fixtures CGL, Wipro, Phillips, Osram, Bajaj
55. Selector Switch L&T, Leader, Salzer
56. Air Conditioners Samsung, LG, Voltas, Carrier, Daikin
57. LT Capacitors L&T, ABB, BCH
58. UF Membrane SUEZ, Toray, DOW, Hydranautics
59. 415 V Type Tested Low
Voltage Switch- gear,
Control gear and Panel
Larsen & Toubro Ltd – L&T
Siemens Limited, Schneider, ABB
60. Lighting Fixtures Crompton Greaves Ltd., Bajaj,
Philips, Osram, Wipro Ltd.
61. Cables / Wires
Universal Cables, KEI, Gloster
Cables, Grandlays, Finolex
Cable Corporation of India, Polycab,
RPG
62. Power Capacitors, APFC
Relay, Detuned Filters
Crompton Greaves Ltd., Schneider,
EPCOS, Siemens, L&T
63. Dry type Transformers
VOLTAMP Transformer Ltd.
Crompton Greaves Ltd., ABB
Schneider
64. 11 kV Shielded Solid
Switchgear
Switchgear Panel
ABB, Schneider Electric, BHEL
Siemens India, L&T
65. Relays (for 415 V /
11KVswitchgear)
ABB, Schneider Electric, Siemens
L&T
66. Instrument Transformers
(CT‘s & PT‘s)
Automatic Electric Pvt. Ltd. ,
Kappa Electricals,
Advance Engineering Co.,
ELMEX, L&T
67. Wiring Conduits NECBEC, Kalinga, Duraline
68. Automatic Power Factor
Control (APFC) Panel
Crompton, Larsen & Toubro Ltd.,
Schneider, EPCOS
69. Electrical Actuators with
Motor Control & Control
Panel
Rotork Control (India) Ltd.
AUMA
70. Distributed Control System
(DCS)
Honey well, Yokogawa, Invensys
ABB, Rockwell
71. Gear box Greaves, Elcon, Alen Berry, Mazda
S. No. Items List of Vendors
72. Instrument & Meters
Automatic Electric Ltd.
Meco Instruments (P) Ltd.
SECURE
Industrial Motors Pvt. Ltd.
Universal Electric Ltd.
L&T
73. Multimeter Escorp, Motwane, Megger
74. Online Turbidity Analyser ABB, E&H, Yokogawa, Hach
75. DC Power Pack Siemens, ABB, L & T, Alstom
76. Mechanical Flow Meter Kent, Schlumberger, Capstan
77. Mechanical Flow Meter
(Turbine Type)
Kent, Schlumberger, Capstan,
Nivo Control
78. Magnetic insertion flowmeter
Crone, Marshal, Nivo Control,
Ultraline, IEPL, Rose Mount,
Letrotek Crystal, ODNI
79. DG Set Sudhir, Cummins, Sterling, Cater
Pillar, Perkins
80. Electric Poles
Jindal, Tata, Bajaj
81. VFD Schneider, Siemens, ABB, Allen
Bradley, L&T, Danfoss
82. Flame Proof Push Button
Station & Lighting Fittings
Siemens, Schneider, BCH, Havells
Osram, Crompton Greaves Ltd.
Philips, Wipro Ltd., FCG, Flexpro,
Baliga, PIECO
83.
Ultra-sonic/ Electromagnetic
flowmeter, Ultrasonic level
transmitter, Pressure
transmitter, Level Switch
Endress & Hauser (India) Pvt. Ltd.,
Siemens, Yokogawa
84. RTUs
Siemens, Yokogawa, ABB,
Endress & Hauser (India) Pvt. Ltd.,
Schneider, Honeywell
85. Motorised Control valves Endress & Hauser (India),
Yokogawa, ABB
86. Level Sensors/Float Switch FLYGT, SBM, Punetechtrol
87. Sandwiched Bus duct ABB, Legrand, Schneider
88. Multifunction Meter (MFM) Siemens, Schneider, ABB, L&T
89. UPS Schneider (APC), Emerson, EATON
90. Battery Standard Batteries Ltd.,
Amco Batteries Ltd., Exide
91. Battery Charger Expo Lobotek Rotromi / Chhabi
Gould Electronics BCH
92. Connectors/ Terminal
Blocks Elmex, Schneider Electric, Phoenix
93. Timers, Indicating Lamps Siemens, ABB, Schneider, L&T
94. CC TV Cameras Axis camera, Honeywell, Bosch,
Cisco
S. No. Items List of Vendors
95. CPVC pipes Astral ,Finolex, Jain
96. RO Membranes SUEZ, Hydranautics, DOW, Toray
97. MVR/Crystallizer SUEZ/Veolia/GEA/MAZDA
98. Cement A.C.C., Ultratech, J.K., Birla
99. Reinforcement Steel SAIL, TISCO, VIZAG RINL,
GOYAL, ZINDAL, AMBA, SURYA
100. RCC Hume Pipe As per I.S Code n0 458
101. Joint Sealant Pidilite, Choksey, Shalimar
Note:
1. Apart from these listed makes, all makes provided in the relevant SOR shall be allowed/
as per approval of Engineer-in-charge..
2. Please refer all orders, circulars and amendments of the concerned department up to the
date of tender which shall be applicable.
3. Contract agency can propose equivalent makes with the approvals of the Employer and/or
of Employer‘s Engineer. The Contract agency shall obtain the prior approval of
Employer‘s Engineer before procurement of items in the list of acceptable makes of
equipment.
Sheet: 4 Basic Design Criteria
Design , Supply, Erection, Testing & Commissioning of 200 KLD Common
Effluent Treatment Plant (CETP) based on ZLD Process, on Turn-key basis and its
Operation and Maintenance for five years at I/A Confectionary Cluster, in front of IIM
Indore Village Rangwasa, Indore M.P. (Rate to be quoted including O & M cost with
all material & Manpower etc. Complete in all respect)
1. Brief Information of Project Site:
Confectionary cluster is about 20 km from Indore district on Rau Pithampur road near Agra
Mumbai Highway. Confectionary cluster has a land area around 28 hectare for industrial
development. This is a new Industrial area which accommodates around 58 no‘s industries.
Most of them are confectionary units. Infrastructure development works are under progress.
1. CETP design Criteria:
It is planned to develop the Common Effluent Treatment plant of 200 KLD with MBR
technology on ZLD concept to facilitate industries of Confectionary Cluster at Rangwasa,
Dist Indore (M.P.). Rate should be quoted by the bidder accordingly. The Contract agency
shall comply with the Specifications and Standards set forth in this Schedule for Design and
Construction of Project Works CETP should be designed, such that the proposed process
is meeting Treated Effluent requirement as per PCB norms:
All components (including but not limited to equipment such as pumps, blowers,
screens, diffusers, inline devices; instruments such as flow meters; and distribution
and collection channels or pipes) shall be provided with appropriate isolation devices
such as valves, gates, or other devices in order to allow isolation, drainage, cleaning,
calibration, servicing, and maintenance of such components.
Cranes, hoists, or other appropriate devices and means shall be provided to permit safe
and easy removal of all equipment for maintenance or any other purpose.
All concrete structures in contact with Effluent and/or sludge upstream of the Aeration
Basins shall be provided with full interior corrosion protection linings and/or coatings
of appropriate material and thickness – to be approved by Employer/Employer‘s
Engineer. This also applies to all concrete structures in contact with any type of Effluent
sludge anywhere in the plant.
All channels carrying process liquid shall be fully covered with solid non-skid SFRC
cover plates/ manhole covers designed for human traffic live loads at a minimum,
and heavy vehicle live loads wherever the channel crosses traffic paths.
Inlets into tanks, reactors, or other structures via pipes, channels, valves, or gates
shall be designed such that the incoming flow does not cause any damage or excessive
wear whatsoever to the structure or any equipment in the vicinity under any hydraulic
condition, including but not limited to the condition when the structure is empty.
All piping shall be of corrosion–resistant material appropriate for the service and shall
be provided with interior lining, exterior coating, and other corrosion protection as
appropriate.
All pipes shall be colour banded and suitably labelled with the stream designation and
direction of flow to enable individual lines to be identified throughout their run.
Appropriate restrained flexible connections and/or joints shall be provided for all pipes
where they connect to any and all of the following:
o Equipment such as pumps, blowers, or inline devices
o Valves
o Wall, floor, or roof penetrations
The influent flow meter and influent sampling location shall be selected such that the true
influent flow and characteristics will be measured without inclusion of in-plant recycles
or other extraneous streams. Separate flow measurement and sampling shall be provided
for the recycle streams.
Foam, scum, fats, oil, grease, or any other floating material removed from any location
in the CETP shall be completely removed from the process flow path along with waste,
digested, and/or dewatered solids leaving the CETP and shall under no circumstances be
recycled or returned to any location in the plant.
Sluice valves/ Knife gate valves shall be provided for effluent and sludge application.
No untreated / partly treated effluent shall be disposed from the plant.
For efficiently working of CETP if any extra facility /Unit is required for construction,
commissioning including Operation & Maintenance for 5 years, the Contract agency will
accommodate the same at his own cost.
The plants and equipment will be inspected by the consultant appointed by MPIDC
Indore at factory/manufacturing site.
An indicative process flow diagram of the CETP is provided in bid document
The structure should be designed as per actual safe bearing capacity (SBC) of trial pit at
site. The Contract agency should carryout Safe Bearing Capacity test at his own cost.
The tank should be designed for required storage capacity with suitable arrangement for
inlet, and scour.
For the purpose design the stress in steel and concrete shall be adopted as specified in the
relevant in the Indian standard code.
Suitable size of aluminum ladder shall be provided inside the tank. The provision of
ladder should be as per instruction of Engineer- in – charge.
The scour pipe will be 150 mm dia. meter. The works involve excavation in trenches
providing laying & jointing scour from the bottom of tank to the nearby drain by pipe.
The C.I. 150 mm, dia. class ―LA‖ pipe should be provided with 150mm dia C.I. sluice
valve. (All fitting and valves of IS standard and provision for of chamber with heavy duty
RCC cover and frame). Provision for 2m wide plinth protection as per design is also part
of work.
The submitted designs and drawings shall be got checked from IIT/ NIT/ Govt.
Engineering college. The charges for the same shall be paid by Contract agency. The
Contract agency shall have to execute the work as per approved designs and drawings.
Provision for lightening arrestor with copper strip as conductor earth electrode.
The RCC overhead tank should be designed in circular shape. Staging means the height
from plinth beam to the beam of bottom dome.
Suitable size of RCC stair from plinth beam to bottom dome and MS stair bottom dome
to roof and stair protected by MS railing. A suitable size of aluminum ladder with railing
shall be provided inside the tank.
The proposed Industries in confectionary cluster are for confectioary manufacturing and
Non-polluting Industries. The expected quality of inlet effluent (including Sewage)
should be considered accordingly by the bidder The above Industrial Effluent quality is
mentioned for reference only. Contract agency has to assume the Industrial effluent
qualities at his own risk to meet guaranteed quality as per norms and Treated outlet
parameters shall adhere guidelines issued by State Pollution Control Board, Central
Pollution Control Board and MoEF.
The treatment losses shall be restricted to 2% in the chemical & biological treatment
units design
2. Process Treatment of Proposed CETP:
The common effluent treatment scheme has been divided into three major steps which are
discussed below. The schematic view is also provided in process flow diagram for getting
clear picture of the common effluent treatment scheme.
i) Primary Treatment ( Physico-chemical Treatment)
ii) Biological treatment
iii) Tertiary treatment
Primary treatment of incoming effluent is necessary to meet out input criteria (limitation) as
under:
pH- 7 to 7.5
TSS- less than 100 mg/ L
Primary treatment has been designed for neutralization & removal of suspended solids as
following treatment process.
Effluent will be received at inlet receive chamber. Here online pH sensor will be provided to
check pH of incoming effluent. From inlet chamber effluent will be taken in to equalization
tank through screen chamber followed by oil trap unit. Equalization tank will be provided in
two parts to work as batch type treatment by using one working & one standby. Here lime/
alkali solution will be dosed for neutralization with help of dosing pump & agitator for
mixing of lime/ alkali solution. Neutralized effluent will be pumped to flash mixing tank,
where coagulant (alum/ poly) will be dosed by using dosing pump. From mixing tank
effluent will be taken into flocculation tank and then primary settling tank for solid liquid
separation. Chemical sludge from settling tank will be drained to sludge drying beds for
solar evaporation. Dried sludge will be disposed into authorized disposal facility.
Concentrate effluent filter from sludge drying bed will be taken back to equalization tank for
re-treatment.
3. MBR Tank
The membrane modules are fully submerged in mixed liquor inside the membrane tank for
direct outside to inside filtration. The membrane modules are made up of hybrid membranes.
The nominal pores size of 0.04 microns and made up of PVDF/PET material. Membrane
system is equipped with pump to create suction insider the membrane and draw water
through the permeate collection tank. Continuous Airflow is to be introduced to the bottom
of the membrane cassettes producing turbulence that scours the surfaces of the membranes to
scour solids from the membrane surfaces. The membrane air scour blowers will be operated
continuously as long as a train is operating in Production mode. Dedicated blowers shall be
for each train. The blowers will normally run on VFD‘s and have adjustable speeds. A
programmable logic controller PLC automatically control the filtration and membrane
cleaning operation. Human machine interface (HMI) continuously monitors the system
performance. The PLC is Ethernet capable to interact with other plant PLC.
Train will have a dedicated permeate pump, this may be a reversible rotary lobe type pump.
The permeate pump will create a vacuum to draw clean water through the membranes and
discharge it to the disinfection stage of the plant. Permeate pumps will be located near their
respective train and will run for a set production cycle length. Reversible pumps will change
direction / Separate Backwash Pumps will run for a set length of time to perform the
backwash after the production cycle.
Pneumatic valves as well as pressure and flow measuring instrument provides continuous
monitoring and control of system operation. When cleaning is required to restore the desired
flux, a train of membrane module is isolated from normal operation and sodium hypochlorite
and citric acid are sequentially injected into the membrane module for in-situ chemical
cleaning.
The MBR tanks shall be fully covered with solid / chequered non-skid GRP cover plates.
The design shall provide for easy isolation of each MBR basin and shall include all required
facilities for complete and automatic clean-in-place (CIP) functionality.
An electric overhead bridge crane or monorail chain pulley block with travelling trolley shall
be provided for easy removal of the membrane modules. The crane or block shall provide
adequate vertical clearance to safely lift the membrane modules above all piping, equipment,
or other items that may be located in the travel path from the module location in the tank to
an adequately-sized adjacent membrane ―lay-down‖ area designated for membrane
maintenance.
The crane coverage shall include the entire MBR basin area plus the lay-down area, if
required . The scope of supply for the MBR system shall consist of, but not limited to the
following :
1. MBR Tank
2. Membrane Modules
3. Permeate pumps/back pulse pumps (process pumps) with VFD
4. Air blower for membrane scouring
5. Backwash or permeate tank
6. Membrane (CIP) Cleaning system
7. Return Sludge Pumps
4. Membrane Module
The MBR process use integrated hollow fiber flat plate membranes for ultrafiltration. The
membrane modules are combined into the cassettes where the collection of clean permeate
from all modules is combined within the cassette permeate collection header.
A cassette becomes the basic building block of the membrane system. Each cassette is
designed as an integrated self-supporting unit to including the membrane air scour system.
Integrated into the cassette are hangers to be supported on the sides of the tank wall
and be able to support tank grating or covers. All access is above the water level and the
cassette can be removed as a single unit.
Individual modules can be accessed and removed if required. The cassettes, piping and
aerators are made of 316 SS.
Backwash : This step of the production cycle is a regularly occurring step to mitigate solids
build- up on the membrane surface as well as membrane pore fouling. Periodically, a
positive pressure is applied so flow direction is reversed through the membrane, and clean
water (permeate) is pushed from the inside-out. During this step there is a net flow of mixed
liquor away from the membrane surface due to the introduction of clean water, a positive
pressure from the inside-out on the membrane surface as well as aeration.
The membranes will require chemical cleaning (CIP) periodically depending on the fouling
properties of the wastewater. Once initiated by the operator the chemical clean and rinse
procedure of the selected module stream will be carried out automatically whilst the
remaining module stream(s) continue in normal operation.
A. Civil components of CETP:
S.
N.
Description Technical Specifications/ Dimension MOC Qty
1 Effluent Receive Chamber 1.0 (L) x 1.0 (W) x 0.50 (LD) + 0.50 FB RCC-
M25
1
2 Screen Chamber 1.0 (L) x 1.5 (W) x 0.30 (LD) + 0.70 FB RCC-
M25
1
3 O & G Trap Unit 4.0 (L) x 1.0 (W) x 1.00 (LD) + 0.50 FB RCC-
M25
1
4 Equalization Tank 6.20 mt Dia x 2.0 mt LD + 5.0 FB RCC-
M25
1
5 Flash Mixer Tank 1.0 (L) x 1.0 (W) x 1.00 (LD) + 0.50 FB MSFRP 1
6 Flocculation Unit 1.0 (L) x 1.0 (W) x 1.00 (LD) + 0.50 FB MSFRP 1
7 Primary Tube Settling Tank 3.0 (L) x 3.0 (W) x 2.50 (LD) + 0.50 FB MSFRP 1
8 Intermittent Storage
(Anaerobic tank)
3.5 (L) x 6.6 (W) x 5.00 (LD) + 1.00 FB RCC-
M25
1
9 Aerobic Tank 6.0 (L) x 3.5 (W) x 3.00 (LD) + 0.50 FB RCC-
M25
1
10 MBR Tank 2.5 (L) x 3.5 (W) x 3.00 (LD) + 0.50 FB RCC-
M25
1
11 Chlorine Contact Tank 2.5 (L) x 3.5 (W) x 2.50 (LD) + 0.50 FB RCC-
M25
1
11 Sludge Holding Tank 2.0 (L) x 3.5 (W) x 1.50 (LD) + 2.00 FB RCC-
M25
1
1
Other Civil Works of Proposed
CETP
Specification Qty-Sq
Mt / RM
1 Admin Office cum Lab
Building
7.0 mt x 3.50 mt x 3.0 mt
2 MCC Panel & machine
Room
5.0 mt x 3.50 mt x 3.0 mt
3 Boundary for CETP
Premises
200 mm Thick-BW & 2 mt Height periphery of
CETP premises
4 Chemical & Hazardous
Waste Storage Room
3.0 mt x 3.50 mt x 3.0 mt
5 Security Guard Room 3.0 mt x 3.50 mt x 3.0 mt
6 Internal Road 2.0 mt wide with WBM base
B. Electro-mechanical components of Proposed CETP
Sr.
No.
Mechanical Items
of CETP
Qty
Unit
Technical Specification
1 Manual Bar Screen 1 No. 2.50 mt x 1.50 mt SS Bar Screen,
10 mm spacing c/c of Flat bars
2 Raw Effluent Pumps 2 No. Capacity: 2 HP, Non Clog Submercible
Flow: 12 M3/Hour- 14 mt head
3 Agitator for Flash
Mixer 1 No.
Capacity: 1-HP, 80 RPM Paddle Type with suitable
gear box
4 Agitator for
Flucculator 1 No.
Capacity: 1-HP, 20-30 RPM Paddle Type with
suitable gear box
5
Agitators for
Chemical Solution
tanks
3 No.
Capacity: 0.50 -HP, 100 RPM Paddle Type with
suitable gear box
6 Dosing Pumps with
HDPE Dosing Tanks 3 No.
Type: Diaphragm Pumps, Discharge-0 to 10 LPH,
Pressure-4 kg/ CM2
Tank: 100 Ltr HDPE tank
7 Tube Media 10 m3
Virgin PP material, 650 mm Vertical Height, shevron
shape with FRP grating as base plate for tube media
holding
8 Agitator for Anoxic
tank 1 No.
Capacity: 1-HP, 20-30 RPM Paddle Type with
suitable gear box
9 Twin Lob Air Blower
with Motor 2 No.
Supply, Installation, Testing & Commissioning of 2
Nos. (One working & one standby) twin Lobe VFD
based Air Blower capable of delivering 300 M3/hour
of free air each at 0.40 Kg/cm2 driven through ‗V‘
belt or directly coupled through flexible coupling to a
TEFC motor of suitable HP (Approve motor rating as
per manufacture recommendation suitable for 415 +
10% volts, 3 phase, 50 cycle AC Supply.
10 Diffusre for Areation
tank and MBR tank 30 No.
Supply, installation, testing & commissioning of
63x600 mm EPDM Tubler air diffusers in
Equalisation tank, Aeration Tank, MBR Tank and
sludge holding tank for providing aeration.
11 MBR Module 7 No.
Hollow fibre membrane with Skid,
Material: PVDF
Por Size: 0.02 Micro meter
Housing Material: ABS
Model: DFX 30 model or equiv.
12 MBR Permeate pump 2 No. Cap.: 10-15 m3/hr, Vacuum Upto 600 mm of mercury,
Protection : IP 44, Rotor(Impeller) : Stainless Steel
13 Backwash Pump 2 No. 3 M3/Hour- 30 mt head, Mono-block
14 Sludge Recirculation
Pump 2 No.
5 m3/hr, 20 mt head.mono block type
15
MBR CIP Dosing
tank, Flocculator and
Dosing Pump
1 No.
Pump Type: Diaphragm Pumps, Discharge-20 LPH,
Mixer Capacity: 0.50 -HP, 20-30 RPM Paddle Type
with suitable gear box
Tank: 100 Ltr HDPE
16
Sodium Hypo Dosing
pump with
Flocculator and
Dosing tank
1 No.
Pump Type: Diaphragm Pumps, Discharge-20 LPH,
Mixer Capacity: 0.50 -HP, 20-30 RPM Paddle Type
with suitable gear box
Tank: 100 Ltr HDPE
17 Treated water
Transfer Pump 2 No.
15 M3/Hour- 30 mt head, Mono-block
18 Centrifuge Feed
Pump 2 No.
2 m3/hr, Screw type Effluent and sewage pump
19 Sludge Dewatering
System 1 No.
Supply, installation, testing and commissioning of
mechanically operated Basket Centrifuge of Suitable
Capacity with CI frame, SS Body complete with all
Asseseries complete with Basket centrifuge feed pump
(Mono Block Type) – 2 No. (1 working + 1 standby)
with 1 No. standby stator, interconnecting piping
complete as required.
20 Laboratory
Instruments 1 Set
Testing Parameter : BOD, COD, TDS, TSS, pH, Oil &
Grease
21 Piping/Valves &
Accessorie 1 No.
Providing and fixing all piping (as described below)
and isolation control valves, Check valves, multiport
valves for making the system complete. Air piping
HDPE/UPVC/CPVC: Air piping & pumped effluent
riser (non-submerged) HDPE: Pumped effluent
(submerged) & tank overflow pipe line HDPE:
Interconnecting pipe line after delivery header of
pump.
22 Lifting Arrangment 1 No. Suitable Lifting arranment for MBR Module
23
Complete MCC
Control panel with
electrical cables &
associated
instrumentation of
system requirements
for proposed CETP
1 No.
Wall mounted / Floor mounted (including base stand),
415V,3PH, 50Hz extensible and fully
compartmentalized Control panels Including PLC
system. The indoor panels shall be IP 42 and outdoor
panels shall be IP 54 type.The Panel shall have proper
space with required clearance for cables, incoming /
outgoing switchgear, CTs, PTs, ammeter, Voltmeter,
selector switches, Insulated and properly supported
compartmentalized bus bars with heat shrinkable
sleeves along with the other control circuit accessories
within the panel and any other electrical component
mentioned in the Panel SLD.The panel shall be
fabricated out of CRCA not less than 2.0 mm thick for
load bearing members and 1.6mm for the doors of LT
panel.The Panel shall have seven tank pre treatment
process comprising of degreasing, rinsing, de- rusting,
rinsing, phosphatising, rinsing and passivation
followed by powder coat painting having a paint
thickness of 60 microns or as specified.The Panel shall
be Dust/Vermin poof with earth studs as per the SLD
and specifications, Panel should be BAS compatible.
Notes: Necessary cable alleys, internal wiring, and
interlocking, earthing for all equipment shall also be
included. All MCCBs shall be of 25 KA breaking
capacity and suitable for motor duty application. All
motor starter shall be provided with Automatic level
controller. Adequate number of spares to be left in
conjunction with the engineer in charge. Provision
shall be made for providing potential free contacts to
all pumps starters for connection to BAS.
24 Online pH sensor 1 No. Online pH sensor with sensor & digital display of pH
range 1 to 14
25 Flow Meter 2 No.
Providing & fixing of flow meter of 80-100 mm sizes
with preamplifier & microprocessor based electronic
flow meter mounted in plumbing plant room electrical
control panel with the following features. Monitoring
the total flow, Flow rate, high low arm batching and
blending etc. Including electrical wiring from
preamplifier to microprocessor based flow meter.
Complete with all type of Plumbing & Electrical
connections, accessories, wiring, conduits & supports
complete with all respect. The signal from read out
shall be 4-20 m.amps to be received on BAS.
Flow Rate Range : upto 1000 LPM Temperature
Range : upto 85 degree celcius. Pressure Range : upto
50 bar
26 Approvels 1 Job
Approval from pollution board at initial & various
other stages of works including preparation of report /
drawings as per pollution board requirement,
arrangement of raw Effluent and sewage for testing &
commissioning. Contract agency shall include the cost
of all chemicals (consumed during testing &
commissioning and the cost of such items of works
which are not explicitly mentioned above, but are
mendatory to have pollution board approval.
27
MS-FRP made
Fabricated STP
Structure
1 No.
As per detailed Design and Drawing, Including Flash
Mixer, Flocculator and Primery tube Settler with
Supporting Skid, Ledders, Platform on Structure with
out-side red oxide primer and Inside 3 mm thick FRP
Coating.
MS sheet thickness: 5-6 mm
FRP Coating thickness : 3 mm
28 Installation &
Commissioning 1 Job
Successful Testing , Installation & Commissioning of
STP plant for a period of 2 Months
29 Operation &
maintenance of STP 1 Job
Operation & maintnance of STP plant for 3 no. of
Skilled Operators for all three shifts and one No. of
Helper for general shift for a period of 60 months.
30
Waste water
Evoprator with
Suitable heating
Arrangment
1 No.
Evaporation rate: 300 Ltr/hr
Tank capacity : 2000 Ltr
Tank MOC: Inner tank 3mm thick SS316 , outer skin
1.2mm CRC powder coated, thermal insulation 50mm
LRB wool
Heating type: LPG/HSD
Operating voltage (V): 415V, 3 phase, 50HZ
Optional accessories: Feed pump for auto fill, flexible
hose for drain, flexible hose for feed water, KWH
meter on the panel
C. List of Laboratory Instruments for Proposed CETP components
The laboratory will be provided. The Laboratory shall be well-equipped with all the latest
equipment‘s as per the test specified to be carried out for waste water and water samples.
The laboratory shall be provided at First floor of administration & control room. The
laboratory in the Administration and Control Building shall have the instruments,
equipment, storage space and chemicals for all the chemical and bacteriological
routine analyses. Laboratory shall have a RCC platform projecting 900 mm from the wall at
about 900 mm height from floor level along the walls of room which will be used for
keeping the instruments and equipment for testing the water. The plate form shall be
provided with glazed tiles. The white glazed tiles shall be provided on the walls all along
the RCC platform up to 60 cm height above the platform. The space underneath the platform
is provided with shutters with door fittings. There shall be minimum three laboratory sinks
in the stainless steel of reputed make of good quality installed in the RCC platform. The
floor of laboratory shall be provided with glaze tiles. The center of laboratory a platform of
minimum 12 M2 with minimum 900 heights from the floor level shall be provided for carry
out the various analyses. This platform shall be provided with acid resistance white glaze
tiles. The laboratory shall have a chemist office room and a cabin for chief chemist/
manager. A toilet shall be provided. Minimum 2 nos. 1.5 T capacity air conditioners shall be
provided in the laboratory. Computer for maintain the record with following specification
shall be provided in the Laboratory.
Computer: 01 No of latest Configuration, with latest Microprocessors, 17" Screen Monitor
Printer : 01 No of HP or equivalent - All in one
The Laboratory equipment‘s are, not limited to following:
List of laboratory equipment’s
Sr. No. Name Of Equipment Quantity
1 pH meter 1
2 COD Digester 1
3 BOD Incubator 1
4 Oven 1
5 Single Pan Analytical Balance 1
6 Digital balance 1
7 Hot Plates 2
8 Kjeldahl‘s digestion unit 2
9 Refrigerator 1
10 Magnetic Stirrer 1
11 UV - Visible Spectrophotometer 1.
12 Vacuum Pump 1
13 Water Bath 1
14 DO Meter 1
15 Noise Meter 1 set
16 Glassware‘s, chemicals and reagents 1
Laboratory for analyzing the wastewater and sludge samples is proposed at the Treatment
Plant. The laboratory shall be equipped with the required equipment so as to analyze the
parameters like pH / BOD / COD / TSS / TDS / TS / VSS / TKN/ Ammoniacal
Nitrogen/Nitrate/ Alkalinity / Sludge Stability etc. as per CPBC guidelines.
Sheet : 5
SCOPE OF WORK
CONSTRUCTION , OPERATION & MAINTENANCE OF CETP
(A) Design & Construction :
Design & Construction of 200KLD CETP.
Design & Construction of 100KL Overhead water Tank .
Plot area of CETP is 1734 Sqm.
Design & Construction of Boundary Wall (200mm thick Brick wall with RCC framed
structure). Length of Boundary wall is 193m .
Plantation within the premises consist of Planting of Trees at periphery and grassing .
All necessary Plumbing work required for watering of Plants.
Street light with LED lamps for proper illumination.
Compacted Murrum Filling of Premises upto Road Level (approximately 3.5 m
height).
Electrical connection from Transformer.
All Civil, Mechanical, Electrical works required for construction of 200KLD CETP.
All the required works necessary to complete the project successfully.
All the electrical & instrumentation works including supply, erection &
commissioning of Motor Control Centre (MCC) panel, Programmable Logic
Controller (PLC) control panel, field instruments, transformers, DG sets, with suitable
outgoing feeder, automatic power factor controlling panel and power factor improving
capacitors, local push buttons stations, etc., as per standards. The scope also includes
all necessary civil works like construction of foundation for panels, cable trenches,
cable supports, yard lighting poles, earth pits, fencing around the transformer yard,
lighting fixtures and required number of sockets in indoor areas as required.
Installation and operation of required CCTV camera covering treatment facility area.
Balance work of recycled water network as per industries demand (100mm dia
HDPE pipe) Approx. length 1.5 Km.
The structure should be designed as per actual safe bearing capacity (SBC) of trial pit
at site. The Contract agency should carryout Safe Bearing Capacity test at his own
cost.
The tank should be designed for required storage capacity with suitable arrangement
for inlet, and scour.
For the purpose design the stress in steel and concrete shall be adopted as specified in
the relevant in the Indian standard code.
Suitable size of aluminum ladder shall be provided inside the tank. The provision of
ladder should be as per instruction of Engineer- in – charge.
The scour pipe will be 150 mm dia. meter. The works involve excavation in trenches
providing laying & jointing scour from the bottom of tank to the nearby drain by pipe.
The C.I. 150 mm, dia. class ―LA‖ pipe should be provided with 150mm dia C.I. sluice
valve. (All fitting and valves of IS standard and provision for of chamber with heavy
duty RCC cover and frame). Provision for 2m wide plinth protection as per design is
also part of work.
The submitted designs and drawings shall be got checked from IIT/NIT/ Govt.
Engineering college. The charges for the same should be paid by Contract agency.
The Contract agency shall have to execute the work as per approved designs and
drawings.
Provision for lightening arrestor with copper strip as conductor earth electrode.
The RCC overhead tank should be designed in circular shape. Staging means the
height from plinth beam to the beam of bottom dome.
Suitable size of RCC stair from plinth beam to bottom dome and MS stair bottom
dome to roof and stair protected by MS railing. A suitable size of aluminum ladder
with railing shall be provided inside the tank.
An indicative process flow diagram of the CETP is provided in bid document .
The CETP is designed for 200 KLD only, but environmental clearence (EC) will be
taken for 750 KLD (for expected future industrial effluent demand).
It is planned to convey the industrial effluent from the industrial area to the proposed
CETP. The CETP shall treat the industrial effluent up to PCB specifications. The
treated water from the CETP shall be lead to recycled water distribution network.
The project components for the industrial effluent collection system will be as
follows -
Effluent treatment plant to treat industrial effluent up to ZLD.
Balancing Reservoir / Overhead tank for recycled water & recycled
water Pumping station.
Balance recycled water supply network (100 mm)
All the environment related permissions including environment clearance, Consent to
establish, and Consent to operate clearance, renewal of consent every year from the
CPCB / MPPCB will be the the responsibility of the Contract agency.
DG sets arrangements system shall be provided in accordance with the Standards and
Specifications as per requirement.
Electrical System including all power feeding equipment, lighting, lightening
Protection system, etc. complete.
Instrumentation & control system with 100% power backup by UPS.
Silting chamber.
Fine screen chamber (Mechanical/Manual) and approach channel.
Grit chamber / Aerated grit chamber/ Vortex type & Parshall flume with flow
measuring device
Oil & grease removal system- Manual oil trap/Tilted plate separator/Corrugated plate
interceptor / Belt skimmer.
Equalization tank.
Chemical treatment- coagulation, flocculation and sedimentation units (flash mixer
& settling tank)
Division chamber.
Biological treatment units.
Chlorine contact tank.
ZLD system.
Gravity sludge thickener.
Sludge dewatering units-centrifuge.
Polyelectrolyte solution preparation tanks and dosing system comprising dosing
pumps.
Backwash water recovery tank & Wastewater recycling system.
Blending tank to Balancing Reservoir-Recycled water.
Vacuum feed type chlorination system with provision of both pre-chlorination as
well as post-chlorination.
Store house for chemicals, spare parts etc.
Laboratory.
Monitoring the quality of effluent at the inlet and outlet of the CETP as per guideline
of CPCB/PCB.
Service water supply system.
DG set of appropriate capacity shall be provided to run all facilities.
Electrical System including all power feeding equipment, lighting, lightening
Protection system, etc. complete including temporary and permanent power
connection.
All Inter-connecting plant piping and appurtenant works etc.
The Contract agency has to dispose solid dry sludge/ silt/screened material/ grit from
treatment plants and effluent pumping stations to nearby landfill site as directed by
the Employer.
Additional process units and facilities required based on selection of process
technology by the Contract agency to meet the treated effluent (Recycled water)
quality.
No disposal of untreated or partly treated effluent is allowed.
The Contract agency shall provide a complete, fully functional facility designed for
proper and easy operation and to meet the stated performance requirements. This
shall include any and all additional, ancillary, supporting, or other processes,
components, equipment, or other items necessary to meet all requirements as per
PCB specification at his own cost.
(B) Operation : -
The scope of workfor the operation will include following :-
Operate the CETP as per standard operating procedures & norms of MPPCB/ CPCB/
MoEF for round the clock i.e. 24x7
Periodical monitoring & testing of incoming effluent sample, and controlling the
parameters of incoming effluent from user units, so that common CETP can be
operated on standard operating conditions & rectify the operational / treatment
process disorders, if any occurs.
Maintaining flow / effluent discharges of user units & total effluent coming to
common CETP on daily basis.
Collections of effluent from inlet pit of CETP received from user unit and/ or other
concerned sampling point and test in-house laboratory for analysis, maintain deviation
of inlet design criteria parameters of proposed CETP, if any financial impact
occurred.
Maintaining quantity & quality of effluent received from user industries on day to day
basis. The record keeping / formats / log sheets of CETP operation should be
maintained & submitted to MPAKVN.
Maintain record of plant performance data, plant maintenance data, Inventory and
consumables at plant in the prescribed log books at CETP.
There shall be no discharge of effluent outside industrial area i.e.―Zero Liquid
Discharge condition ―to be maintained for all the time.
Collect user charges from industrial units towards treatment of their wastewater,
charges for supply of recycled water, as per the Tariff structure firmed up by Nigam
Committee.
(C) Maintenance
Mechanical /Electrical Maintenance
All Equipment/pumps/Motors/ pipe lines/valves/ flow meters/stirrers installed should
alway be in working condition.
Preventive Maintenance: - Daily cleaning of pumps, motors. , Weekly oiling
greasing, testing of drain valves .Once in six month cleaning and changing of
filter material of pressure sand filter unit and Changing filter of Air compressors.
Break Down Maintenance :- Attending Mechanical and electrical break downs
such as burnt motor winding Replacing damaged bearings, leakage of pipelines,
replacement of defective valves, Gland packing change if leakage is there or worn
out.
Periodical cleaning of units
Twice a year (once in six months) cleaning of Process tank/Inlet Collection
well/ associated units.
Regular disposal of waste in every 90 days to authorized disposal facility.
(D) Housekeeping :-
Daily Cleaning of lab, pump room etc and open area around the units ,valve chambers,
drains removing tree leaves from pond in addition to above the house Keeping of the CETP
premises includes cutting and cleaning grass vegetation , landscape etc. on daily basis. The
cut grass and vegetation to be disposed safely and directed places.
(E) Workmanship:
a. All works pertaining to the contract shall be carried out as per specifications given in
bid document .
b. After satisfactory completion of construction work and water tightness testing, the
water tanks shall be the roughly cleaning with brushes and cleaning agents as
permitted by the engineer in charge to remove dust, dist, loose concrete, chips and
scales or any other undesirable material. The tank shall be filled with water upto the
full storage level and mixed thoroughly with a solution of high strength hypochlorite
(HTH) of any other disinfection solution as approved by the engineer in charge. The
solution shall have strength of at least 0.5m p.m. residual chlorine. The water shall
stand for a period of 48 hours. It shall then be flushed out by opening the scour valves
and shall then be ready for commissioning. The test shall be certified by the engineer-
in-charge before it is ready for commissioning.
(F) Excavation
The depth of excavation will generally be guided by the underground strata and
accordingly the safe bearing capacity of the foundation soil shall be decided. This shall
be verified by the Contract agency by Actual site investigation and test of underground
strata at his own cost. Test result shall be submitted along with design calculation. The
Contract agency shall keep the site clear of water at all times. This end he shall provide
Arrangement as required.
(G) Filling Foundation with Bed Concrete:
a. Any excavation be done below the specified levels, Contract agencys shall fill in
such excavation at his own cost with M-10 grade of concrete below foundation
well rammed in position up to the level.
b. The Contract agency shall notify when the excavation is completed
c. The Contract agency is to carry out necessary soil testing at his own cost. And the
test results dully approved by the engineer-in-charge.
(H) Shoring:
All sides of excavation shall be adequately supported to prevent subsidence or
movement of Material in which the excavation is being carried out and to ensure the
safety of persons and hereby quality shall be used for shoring. The Contract agency
shall take all necessary precautions to prevent slips on excavations with adequate
shoring and strutting shall be at his expenses make good any damage or defect and
removed to spoil dumps any surplus materials caused by slips. No extra payment for
shoring will be made.
(I) Concrete :
a. Applicable provisions of general Rules and direction shall govern work under this
section. All concrete work, plain or reinforced shall be carried out in strict
according with this specification and any working drawing or instructions given
from time to time to the Contract agency. Works shall be strictly as per I. S. 456 an
I.S. 3370 as applicable.
b. Reinforced cement concrete M.30 with reinforcement as per the approval of
IIT/regional engineering collage.. A minimum clear cover of 40mm and 25mm
shall be provided on water retaining face to other faces respectively. The code of
practice should be referred in this respect.
c. The Contract agency shall submit mix design for each strength.
d. The proportion of the concrete shall be such as to work readily into the form angles
and grout the reinforcement without excessive manipulations, segregation or water
gain. The water content shall not be increased from the amount required by the
design mix unless cement at required water cement ratio is added. The engineer –
in- charge may require additional cement without extra compensation to the
Contract agency if the mix adopted does not produce the required strength.
(J) Steel :-
a. Steel reinforcing bars for concretes shall be of TMT steel.
b. Soft iron binding wire shall comply with requirements of I.S.280.
c. The reinforcement shall be bent to the shapes shown on the drawings prior to
placing. The steel shall be placed in such a way that it is rigidly held in position
while concrete is being poured. The correct clearance shall be maintained by either
mortar blocks or by metal supporting chairs to be supplied by the Contract agency
free of charge.
d. The Contract agency shall require getting tested random samples of the steel
brought at site to see whether they confirm so as per I.S. specifications. The cost of
such tests shall be borne by the Contract agency.
e. All railing, ladders, manhole covers ,air vents, pipes and specials etc, shall be
supplied with 2 coats of approved quality and make enamel paint over a primer
coat and as directed by the Engineer-in-charge.
f. Steel for reinforcement shall confirm to IS 432-1966 (with upto date revision) and
IS 1139-1966 (with upto date revision) the Contract agency shall be required to
produce the test certificate of the manufacturers to the department before use of
steel for the work. No untested steel shall be used. The department however
reserves right to get the received steel tested at the cost of Contract agency.
(K) Testing of Water Tightness
a. The tank will have be tested for the water tightness as per IS-3370 and it will be
responsibility of the Contract agency to make it water tight. The arrangements for
water shall be done by the Contract agency at his own cost of testing purposes.
The Contract agency will have to give a test of water tightness of reservoir to the
entire satisfaction of the Nigam. The responsibility of structural suitability shall
also rest solely with the Contract agency.
b. Outside plastering of structures is to be done.
c. Snowcem or durocem painting of the tank shall be done only after tank is tested
for water tightness only on the outside portion above ground level.
d. The Nigam shall not be responsible for providing water require for construction
and other purposes. The Contract agency shall make his own arrangements for the
same at his own cost.
Sheet : 6
Operation and Maintenance Requirements The Contract agency shall, at all times maintain the Project Works in accordance with
the provision of this Agreement, Applicable Laws and Applicable Permits.
1. Scope of Works for O&M
The contract includes 5 Years (60 Months) Operation & Maintenance (O&M) of Effluent
Treatment Plant complete in all respect after successful commissioning, completion of 3
months trial run and acceptance for all works by Employer‘s Engineer. O&M shall be based
on CPHEEO Manuals and Other Standards as specified below:
(a) CPHEEO Manual for Water Supply & Treatment -1999- MoUD, GoI
(b) CPHEEO Manual on Operation and Maintenance of water supply systems, 2005
MoUD, GoI
(c) CPHEEO Manual on Sewerage and Effluent Treatment Systems (Part A;
Engineering (3rd
edition) revised and updated) , 2013
(d) CPHEEO Manual on Operation and Maintenance Sewerage and Effluent Treatment
Systems (Part B ; Operation and Maintenance (1st edition) -2013
(e) CPHEEO Manual on Operation and Maintenance Sewerage and Effluent Treatment
Systems (Part C ; Management (1st edition) -2013
(f) Guidelines provided by Central Pollution Control Board (CPCP)
(g) Guidelines provided by Madhya Pradesh Pollution Control Board (MPPCB)
(h) The Environment (Protection) Rules, 1986
All spare parts and Tools & tackles as necessary for operation
of the project works, for the entire O&M period, List of spare parts and Tools & tackles shall
be based on above CPHEEO manuals and international Standards. The List of spare parts and
Tools& tackles shall be approved by the Employer‘s Engineer before procurement. All
unused spare parts and Tools & tackles will be the property of Employer at the end of the
Contract Period.
2. General
Major components and works shall include the following but not limited to:
(a) Contract agency shall operate and maintain Effluent Treatment Plant, Effluent
Pumping Station, Balancing Reservoir ,OHT & pumping station for recycled water
and pumping main for waste disposal etc complete for 5 years on 24 hours/day basis
throughout the year and operation of pumps shall be 24 hrs.
(b) Contract agency shall operate and maintain all instruments and mechanical,
electrical, Instrumentation and automation equipment‘s in accordance with the aim
and purpose of treatment and recycled water supply. The plant & equipment will be
totally attended to, by the Contract agency including any ―Troubleshooting‖ to
ensure smooth and trouble-free operation.
(c) Contract agency has to incur all the cost, taxes & duties for transportation, labour,
repairing & replacing equipment, making good any part or all part of equipment,
consumables, motors, pumps, gear unit, Capacitor, HT/LT Switchgear, Control
Panel filter media, valves, chemical and laboratory equipment etc. Complete
excluding Electricity Charges.
(d) The Contract agency shall be responsible for procuring all spares, all tools &
tackles, parts or components, Consumable chemicals (Chlorine, Polyelectrolyte etc.)
and all consumables including grease, lubricating oil, cleaning agents, equipment,
laboratory instruments, glassware and chemicals, laboratory reagents, labour
transportation and other charges, etc. Further the Contract agency will plan
about the requirement well in advance and procure the material from the
market. Power cost would be borne by the Employer.
(e) Contract agency shall prepare O&M Manual for the Effluent Treatment Plant,
Effluent Pumping station (Terminal), recycle water pumping station for recycled
water. The Contract agency shall monitor the performance of the Effluent Treatment
Plant, conduct the analysis for the inlet industrial Effluent & treated Effluent on
daily basis. Contract agency shall initiate and take adequate actions to ensure
smooth and satisfactory performance/ running of the plants on a 24 hours/ round the
clock basis. Operate and maintain all units and equipment of the Effluent Treatment
Plant as per the requirement of the process to meet continuously and consistently
desired quality of recycled water (Treated Effluent) as per the contract.
(f) The operation and maintenance service provided by the Contract agency for the
period specified in the Contract shall ensure the continuous operation of the Plant
and that the breakdown or deterioration in performance, under normal operating
conditions, of any items of Plant and equipment and component parts thereof is
kept to a minimum.
(g) The Contract agency will determine operating parameters, select Chemical doses
etc. and optimize the process, and working of the Effluent Treatment Plant.
Excessive chemical dozing i.e. dose more than normal should be avoided.
(h) The Contract agency shall prepare and implement an effective plant maintenance
program in consultation with the Employer‘s Engineer/ Employer. It is Contract
agency‘s responsibility to look after all sorts of maintenance whether preventive,
Minor, Major, or break-down. The Contract agency will be responsible to carry
out day to day as well as periodic maintenance necessary to ensure smooth
and efficient performance/running of all equipment. Contract agency shall attend
all the breakdown of civil, mechanical, electrical, piping, automation and
instrumentation works and maintain the plant and equipment throughout the
Contract Period.
(i) The Contract agency shall keep additional spares, Tools and consumables in any
time during O&M period.
(j) No structure of any kind will be allowed to be constructed/ altered within the plant
premises, without the approval of Employer. Nothing is to be paid by Employer for
any addition if allowed. In case of damages to the building/machines and
shortcoming to the machines, the same has to be made good as per original
shape/good running condition by the Contract agency. The decision of Employer‘s
Engineer/ Employer in this regard shall be final and binding.
(k) In case, the motor or any other equipment is burnt or damage due to negligence of
the Contract agency or due to faulty operation it shall be sole responsibility of the
Contract agency to rewind/replace/repair it as per standards of the equipment free of
cost. In case of any fault in operation and performance of the plant, Contract agency
or his staff at duty will immediately report to the Employer‘s Engineer about it.
(l) The Contract agency will be responsible for keeping up-to-date record of
documents including History Card for equipment and maintaining every day log
book relating to various analysis performed. The Contract agency shall maintain
and update logbook, in which details of operational parameters are recorded
in every shift and at regular interval say hourly or as decided mutually. Contract
agency shall take the approval of the format of logbooks and records from
Employer.
(m) The Contract agency will prepare and submit daily, fortnightly and monthly reports
of plant performance and will assist the Employer in preparing the necessary
documents for their purpose and records. Carry out regular and frequent sampling,
analysis and result recording of industrial effluent and treated effluent as per the
procedures laid out by the Owner and in conformity with standard methods.
(n) The Contract agency shall employ appropriate and skilled manpower. The Contract
agency shall have to issue identity cards with photographs to all the staff employed
for Operation and Maintenance. The list of the same shall be submitted to the
Employer mentioning qualification & experience.
(o) The scope of works for operation & maintenance includes the calibration of
all meters e.g. pressure gauge, Ammeter, voltmeter, relay, Energy meters, temp
scanners, flow meters etc. for measurement of accurate readings, 11 KV
incoming line, Lighting Arrestors, D.O. fuse, earthing works, or any other
maintenance required on two/four pole D P structure etc .
(p) The Contract agency shall be responsible for maintaining the lighting and other
equipment. The premises of various works shall be provided with LED energy
efficient industrial Indoor fixtures and also ceiling fans/exhaust fans inside the
various structures. Daily on/off operation and routine cleaning of all type of
electric fixtures. Replacement of lamps / Tubes / Fans in case of failure at Contract
agency‘s cost.
(q) The Contract agency shall be responsible for the maintenance of Garden, lawn,
green belt etc. work shall include the watering, grass cutting, removal of shrubs,
weed cutting of braches of tree/ plant, growth of garden, Plantation etc.
(r) The Contract agency shall be responsible for the maintenance of all buildings in the
treatment plant. The Contract agency shall be responsible to keep watch on
overflowing of sumps/ reservoirs/ wet wells for pumping stations etc. If such
overflow takes place the Contract agency shall have to bear the damages caused to
surrounding properties.
(s) The Contract agency shall carryout cement paint/ enamel paint/ white wash for
exterior finish of civil units twice during in five year of O & M of the plant and
shall also carry out painting on mechanical equipment/ above ground pipe lines/
hand railing twice in five years of O & M of the plant. On the expiry date of his
contract operation and maintenance, the Contract agency shall hand over the plant
back to employer in fully working condition satisfying the requirement of treated
Effluent. All the electrical, mechanical and instrumentation including standby shall
be in perfect working condition.
(t) The Contract agency shall be responsible for safety on Site during the O & M of the
Works by the Contract agency. Health of workers shall be protected against
infectious and contagious diseases. Environmental protection shall also be given
priority so as to conserve the environment.
(u) The Contract agency shall at his own cost provide and maintain at the Site of Works
standard first aid boxes as directed and approved by the Employer for the use of his
own as well as the Employer's staff on Site as stipulated by local regulations.
The Contract agency shall arrange to train all their staff in first aid treatment within
3 months.
(v) The Contract agency shall provide a Notice Boards/Display Boards at appropriate
locations detailing precautions to be taken by operation and maintenance
personnel in work in conformity with Industries and Labour Regulations and
Department of Explosives.
(w) All materials, works and construction operations for the roads works shall conform
to the Specifications for Road and Bridge Works (Fifth Revision, April 2013),
issued by the Ministry of Road Transport & Highways (MoRT & H) and the
relevant IRC publications. Where the Standards and Specifications for a work are
not given, Good Industry Practice shall be adopted to the satisfaction of the
Employer‘s Engineer.
(x) Operate the CETP as per standard operating procedures & norms of MPPCB/
CPCB/ MoEF for round the clock i.e. 24x7.
(y) Periodical monitoring & testing of incoming effluent sample, and controlling the
parameters of incoming effluent from user units, so that common CETP can be
operated on standard operating conditions & rectify the operational / treatment
process disorders, if any occurs.
(z) Maintaining flow / effluent discharges of user units & total effluent coming to
common CETP on daily basis.
(aa) Collections of effluent from inlet pit of CETP received from user unit and/ or other
concerned sampling point and test in-house laboratory for analysis, maintain
deviation of inlet design criteria parameters of proposed CETP, if any financial
impact occurred.
(bb) Maintaining quantity & quality of effluent received from user industries on day to
day basis. The record keeping / formats / log sheets of CETP operation should be
maintained & submitted to MPIDC.
(cc) Maintain record of plant performance data, plant maintenance data, Inventory and
consumables at plant in the prescribed log books at CETP.
(dd) There shall be no discharge of effluent outside industrial area i.e.―Zero Liquid
Discharge condition ―to be maintained for all the time.
(ee) All Equipment/pumps/Motors/pipe lines/valves/ flow meters/stirrers installed
should always be in working condition.
(ff) Daily cleaning of pumps, motors, Weekly oiling greasing, testing of drain valves.
Once in six month cleaning and changing of filter material of pressure sand filter
unit and Changing filter of Air compressors.
(gg) Attending Mechanical and electrical break downs such as burnt motor winding
Replacing damaged bearings , leakage of pipelines, replacement of defective valves,
Gland packing change if leakage is there or worn out.
(hh) Dense plantation is to be done along the periphery of the CETP premises. Plantation
done by the Contract agency during construction period shall also be maintained
during operation and maintenece period. Number of plants planted during
construction period will be the same as at the end of performance guarantee period
with sufficient growth. Water, manure, pesticides, labour, civil work etc. required
during plantation work and its maintenance work shall be arranged by the contract
agency. During 1st to 5
th year maintenance replacement of plant casualties, soil
conservation work, weeding of plants, protections of plants safety measures of
plants are included in the contract.
(ii) 24 Hrs Security of facility shall be provide by the Contract agency. The Contract
agency shall designate necessary security personnel to ensure safety and security
of all fittings and fixtures of all components of various items of executed work as
per contract document for entire period, The Contract agency shall be liable for
losses due to theft and shall be liable to repair/ replace or refit the concerned item.
3. Housekeeping:-
Daily Cleaning of lab, pump room etc and open area around the units ,valve
chambers, drains removing tree leaves from pond in addition to above the house Keeping
of the CETP premises includes cutting and cleaning grass vegetation , landscape etc. on
daily basis. The cut grass and vegetation to be disposed safely and directed places.
The Contract agency shall provide experienced administrative, managerial, technical
personnel, duly approved by the Employer‘s Engineer/Employer including supervisory,
non- technical personnel and labour necessary to operate and maintain the plant properly,
safely and efficiently on a continuous 24 hours basis for the full term of the O & M
Contract Period. During O & M period if any expert person, special persons or manpower
needed, the Contract agency shall arrange at his own cost.
4. Treated effluent Quality for CETP
The Contract agency shall operate the Effluent Treatment Plant in such a way that the
recycled water (treated effluent) quality attains the parameters as per PCB norms.
If the Contract agency fails to achieve the recycled water (treated Effluent) quality, he
will be responsible for all modification without extra cost. The proposal submitted by the
Contract agency should be suitable to work round the year and supported by the
documents as satisfactorily tested and tried. Documentary proof in this regard from the
employer engineer needs to be submitted along with the proposal.
No toxic chemical shall be used by the Contract agency at any stage of treatment, he will
submit the toxicity test report from any govt. recognized laboratory at his own cost before
using such chemical.
The Contract agency shall operate the Effluent Treatment Plant such that the
sludge produced is of a spade-able consistency and the volume of sludge produced
after necessary process, is minimum. The Contract agency shall dispose off the sludge
cake at his own cost, through proper approved means of transport to the disposal site and
necessary clearance, if required for this purpose, from the regulatory authority, is to be
obtained by the Contract agency. The Contract agency has to dispose solid dry sludge/silt
/ screened material/ grit from Treatment plants to nearby approved landfill site as directed
by the Employer. The Contract agency needs to check the quality of the sludge before
disposal and get the approval of Employer‘s Engineer.
5. Tests to be carried out during O&M Period The testing of industrial Effluent and treated Effluent at CETP site shall be as per the
CPHEEO manual for Effluent Treatment and CPCP/MPPCB regulations. The frequency
of testing of parameter shall be submitted by the Contract agency and approved by the
Employer‘s Engineer.
The minimum requirement of sampling and testing is to be carried out is at the points
given below. This schedule shall also be maintained during the O&M period.
All costs associated with the taking and analysis of samples shall be met by the Contract
agency.
Minimum of 80% of the tests shall be carried out in house laboratories and remaining part
of 20% of the tests shall be conducted in MPPWD approved Lab / LUN Lab /
Government Engineering college.
6. Staffing for the operation of Effluent Treatment Plant
The work shall be carried out on a 24 hr. basis, without intermission and the staff
deployed by the Contract agency shall be in accordance with this contract. The Contract
agency shall give or provide all necessary superintendence during the O&M period and as
long thereafter as the Employer‘s Engineer may consider necessary. Such
superintendence shall be given by a competent person having adequate knowledge of the
operation and maintenance to be carried out (including the methods and techniques
required), the hazards likely to be encountered and methods of preventing accident) as
may be required for the satisfactory working of the entire plant.
List of staff is to be given by the Contract agency to the Employer‘s Engineer and
advance intimation to be given before deputing/removing any staff from site during the
period of contract. Not more than one of the Contract agency's key staff shall be absent
from the project site at any given time. In case it is necessary for more than one of the key
personnel to be absent at a given time, the Contract agency shall provide replacement of
equivalent or better qualifications. The CVs of such replacements shall be got pre-
approved from Employer/ Employer‘s Engineer in advance.
7. Reporting
The Contract agency will prepare daily / monthly reports of project performance and
submit to the Employer‘s Engineer and will assist the department in preparing the
necessary documents for their purpose and record. The reports shall contain, inter-alia,
the following:
Industrial Effluent quality
Treated Effluent quality
A description of the maintenance work carried out in the reporting period.
A report on major failures, if any, their causes and remedial actions taken.
Sludge cake quality and quantity (daily basis) in the reporting period.
Power and chemicals consumed in the reporting period.
An inventory of the chemicals and spare parts available at the end of the
reporting period.
O&M staff deployed by the Contract agency during the reporting period.
Record of daily readings of flow meter at upstream and downstream end of
pipeline,
Pressure reading of the pipeline.
Record on when the pipeline leaks were repaired or pipe changed and the cost of
materials and labour cost there of.
Any major repair works, if any.
The Contract agency is required to maintain separate register/computerized records at
site of following information:
Pump register
CETP performance register
Working hours register
Power break down register
Maintenance register
Staff attendance register
Equipment breakdown, repair record and extent of repair
8. As Built Drawings” and “Operation and Maintenance Mannual”
On Completion of the Inspection and Tests for the various facilities the Contract
agency would be required to make the ―As Built drawings‖ of the equipment,
pipeline, appurtenances and all the components and works involved. The drawings
would be on long lasting material along with tracings and blueprints. Soft copies of the
same are also to be included.
The Contract agency shall submit the O & M Manual for approval of Employer, which
may be modified, if required by Employer and this manual shall be approved from
Employer prior to commissioning. The Contract agency shall be modified the operation
and maintenance manual as per the modification in the Effluent Treatment plant if any.
9. Operation and Maintenance Manual
The Contract agency shall provide draft O&M Manual to Employer, at the time of
the commissioning of the project and on approval of draft, 4 copies of operation
& maintenance manual shall be supplied by the Contract agency.
The O&M Manual shall include in elaborate detail, all operating and
maintenance procedures and policies which are required, advisable and / or
necessary for the Facility to achieve full compliance with the operational
guarantees and to achieve maintenance and repair standard for the Facility
which will ensure compliance with the maintenance specifications.
Without limiting the generality of the foregoing the O&M Manual shall
include descriptions, procedures, and shall comply with the requirements, set
forth in the provisions of the Bid Documents.
The draft of the O&M Manual shall be subject to the review and approval of
Employer, which shall have the right to make any changes and revisions to the
O&M Manual as it may deem appropriate. The Contract agency shall revise such
draft O&M Manual prior to the commencement of the O&M period.
During the term of this Agreement, the Contract agency shall promptly notify
Employer of any revisions, additions or modifications which he, in his
professional opinion, believes should be made to the O&M Manual, whether as a
result of additional experience in operating and maintaining the Facility, changes
in influent quality or volume, changes or modifications to any equipment, part,
component or structure incorporated in the Facility. Such notification shall set
forth the reason for the proposed revision. Any proposed revision shall be subject
to the approval of the Employer. In addition, during the term of this
Agreement, Employer shall have the right to require relevant changes,
revisions, or additions to the O&M Manual as it, shall deem appropriate to
ensure full compliance with the O&M Standards.
Tentative List of Drawings
S. no. Drawing Title
1 Layout of Confectionary Cluster
2 Key Plan of Recycle water distribution pipe network
3 Tentative Process Flow Diagram of Effluent Treatment Plant (CETP)
All the documents provided are for reference only and bidder has to carry-out their own
assessment for required details.