Tariff Order for FY 2015-16 - Delhi Electricity Regulatory ...
-
Upload
khangminh22 -
Category
Documents
-
view
6 -
download
0
Transcript of Tariff Order for FY 2015-16 - Delhi Electricity Regulatory ...
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 1
September 2015
CONTENTS A1: INTRODUCTION.................................................................................................................... 8 New Delhi Municipal Council (NDMC) .................................................................................................. 8 Delhi Electricity Regulatory Commission .............................................................................................. 8 Multi Year Tariff Regulations ................................................................................................................ 9 Filing of Petition for True-Up of Expenses for FY 2013-14 and approval of ARR for FY 2015-16 ......... 9 Filing and Acceptance of Petition ......................................................................................................... 9 Layout of the Order ............................................................................................................................. 14 Approach for FY 2013-14 .................................................................................................................... 15 Approach for FY 2014-15 .................................................................................................................... 17 Approach for FY 2015-16 .................................................................................................................... 17 A2: RESPONSE FROM STAKEHOLDERS ....................................................................................... 19 Introduction ........................................................................................................................................ 19 Issue 1: Tariff Rates ............................................................................................................................. 19 Issue 2: Fixed Charges ......................................................................................................................... 20 Issue 3: Tariff Rate for Doctor’s Clinics ............................................................................................... 21 Issue 4: Separate sub-category for Telecom Towers .......................................................................... 22 Issue 5: Time of Day Metering and Net Metering .............................................................................. 23 Issue 6: Payment of Electricity Bill by Credit Card .............................................................................. 24 Issue 7: Audit of NDMC Accounts ....................................................................................................... 25 Issue 8: Tariff for DMRC ...................................................................................................................... 26 A3: True up of FY 2013-14 ........................................................................................................ 28 Background ......................................................................................................................................... 28 True-up of FY 2013-14 ........................................................................................................................ 35 AT&C Losses ........................................................................................................................................ 36 Power Purchase Quantum .................................................................................................................. 40 Power Purchase Cost .......................................................................................................................... 41 Review of Controllable Parameters .................................................................................................... 45 Operation & Maintenance Expenses .................................................................................................. 47 Administrative and Civil Engineering Departments Expenses ............................................................ 48 Capital Expenditure & Capitalization .................................................................................................. 49 Depreciation ........................................................................................................................................ 50 Working Capital ................................................................................................................................... 51 Review of Regulated Rate Base and Return on Capital Employed ..................................................... 52 Non Tariff Income ............................................................................................................................... 54 Renewable Purchase Obligations........................................................................................................ 56 Aggregate Revenue Requirement ....................................................................................................... 57 Revenue available towards ARR ......................................................................................................... 58 Revenue (Gap)/ Surplus ...................................................................................................................... 58 Net (Gap)/Surplus at the end of FY 2013-14 ....................................................................................... 59 A4: Analysis of Aggregate Revenue Requirement (ARR) for FY 2015-16 ...................................... 60 Energy Sales ........................................................................................................................................ 60 Estimated Sales for FY 2015-16 ........................................................................................................... 62 Domestic Consumers .......................................................................................................................... 63 Non-Domestic Consumers .................................................................................................................. 63 Mixed Load Consumers ....................................................................................................................... 63 Small Industrial Power ........................................................................................................................ 64
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 2
September 2015
Public Lighting ..................................................................................................................................... 64 Delhi Metro Rail Corporation (DMRC) ................................................................................................ 64 Other Categories ................................................................................................................................. 64 Approved Sales for FY 2015-16 ........................................................................................................... 65 Revenue in FY 2015-16 at Existing Tariff ............................................................................................. 65 AT&C Losses ........................................................................................................................................ 67 Energy Requirement ........................................................................................................................... 68 Power Purchase Quantum .................................................................................................................. 68 Allocation of Power from Generating Stations ................................................................................... 69 Energy Availability from Central Generating Station (CSGS) .............................................................. 70 Power Purchase Cost .......................................................................................................................... 70 Cost of Power Purchase from other Sources (Short term Purchase) ................................................. 72 Renewable Power Purchase Obligation (RPO) .................................................................................... 73 Transmission Losses and Charges ....................................................................................................... 75 Energy Balance .................................................................................................................................... 76 Sale of Surplus Power ......................................................................................................................... 78 Total Power Purchase Cost ................................................................................................................. 79 Power Purchase Cost Adjustment Charge (PPAC) .............................................................................. 80 Operation and Maintenance (O&M) Expenses ................................................................................... 83 Administrative Expenses and Civil Engineering Department Expenses .............................................. 84 Capital Expenditure and Capitalization ............................................................................................... 85 Depreciation ........................................................................................................................................ 86 Working Capital ................................................................................................................................... 87 Regulated Rate Base (RRB) ................................................................................................................. 88 Weighted Average Cost of Capital (WACC) ......................................................................................... 89 Return on Capital Employed (RoCE).................................................................................................... 90 Non Tariff Income ............................................................................................................................... 91 Carrying Cost on Revenue Gap ........................................................................................................... 92 Aggregate Revenue Requirement (ARR) ............................................................................................. 93 A5: Tariff Design ...................................................................................................................... 94 Components of Tariff Design .............................................................................................................. 94 Consolidated Revenue (Gap)/ Surplus for NDMC till FY 2013-14 ....................................................... 94 Revenue (Gap)/ Surplus for FY 2015-16 at Existing Tariffs ................................................................. 94 Treatment of Revenue (Gap)/Surplus ................................................................................................. 95 Tariff Structure .................................................................................................................................... 98 A6: DIRECTIVES ...................................................................................................................... 117 Annexure-I ............................................................................................................................. 123 Annexure-II ............................................................................................................................ 124 Annexure-III ........................................................................................................................... 129 Annexure-IV .......................................................................................................................... 136 Annexure-V ........................................................................................................................... 139 Annexure VI ........................................................................................................................... 145 Annexure-VII ......................................................................................................................... 151 Annexure-VIII ........................................................................................................................ 158 Annexure-IX ........................................................................................................................... 162 Annexure-X ............................................................................................................................ 185
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 3
September 2015
LIST OF TABLES
Table 1.1: List of Correspondence with the Petitioner ....................................................................... 11 Table 3.1: Impact of Revised GFA on Depreciation during FY 05-06 to FY 12-13 .............................. 31 Table 3.2: Revised RRB (Capital Base) during FY 2005-06 to FY 2012-13 ........................................... 32 Table 3.3: Revised RoE during Policy Direction period (FY 05-06 and FY 06-07) ................................ 32 Table 3.4: Revised RoCE during FY 2007-08 to FY 2012-13 ................................................................ 33 Table 3.5 (a): Impact of True up during PDP along with Carrying Cost .............................................. 34 Table 3.5 (b): Impact of True up during FY 07-08 to FY 12-13 along with Carrying Cost .................... 34 Table 3.6: Trued Up Energy Sales for FY 2013-14 ............................................................................... 36 Table 3.7: Collection efficiency for FY 2013-14 submitted by the Petitioner ..................................... 36 Table 3.8: AT&C loss computation for FY 2013-14 as submitted by the Petitioner ........................... 36 Table 3.9: Additional submission of the Petitioner ............................................................................ 37 Table 3.10: Trued up AT&C loss for FY 2013-14 approved by the Commission ................................. 38 Table 3.11: AT&C loss for FY 2013-14 approved by the Commission ................................................. 39 Table 3.12: Computation of penalty due to Under Achievement in AT&C loss targets for FY 2013-14
.................................................................................................................................................. 39 Table 3.13: Power Purchase Quantum submitted by the Petitioner for FY 2013-14 ......................... 40 Table 3.14: Power Purchase Cost for FY 2013-14 as submitted by the Petitioner ............................. 41 Table 3.15: Computation of Normative Rebate ................................................................................. 43 Table 3.16: Power Purchase Quantum from long term sources for FY 2013-14 approved by the
Commission .............................................................................................................................. 44 Table 3.17: Power Purchase Quantum from short term sources for FY 2013-14 approved by the
Commission .............................................................................................................................. 44 Table 3.18: Power Sales Quantum from short term sources for FY 2013-14 approved by the
Commission .............................................................................................................................. 45 Table 3.19: Trued-Up Power Purchase Cost for FY 2013-14 .............................................................. 45 Table 3.20: O&M Expenses approved by the Commission for FY 2013-14 ........................................ 47 Table 3.21: Administrative & Civil Engineering Expenses projected by the Petitioner ...................... 48 Table 3.22: CWIP and capitalization proposed by Petitioner for FY 2013-14 ..................................... 50 Table 3.23: Addition during the year approved for FY 2013-14 ......................................................... 50 Table 3.24: Depreciation submitted by the Petitioner for FY 2013-14 ............................................... 51 Table 3.25: Approved Depreciation for FY 2013-14 ........................................................................... 51 Table 3.26: Working capital requirement projected by the Petitioner for FY 2013-14 ...................... 52 Table 3.27: Change in Working Capital approved by Commission for FY 2013-14 ............................. 52 Table 3.28: RRB approved for True Up for FY 2013-14 ....................................................................... 53 Table 3.29: RoCE approved for True Up for FY 2013-14 ..................................................................... 54 Table 3.30: Non tariff income projected by the Petitioner for FY 2013-14 ........................................ 54 Table 3.31: Trued-up Non Tariff Income approved for FY 2013-14 .................................................... 56 Table 3.32: Targets & Achievements for Renewable Purchase Obligations and REC ......................... 56 Table 3.33: Cost of RE Certificates ...................................................................................................... 57 Table 3.34: Aggregate Revenue Requirement now approved for FY 2013-14 ................................... 57 Table 3.35: Revenue Surplus/ (Gap) for FY 2013-14 ........................................................................... 58 Table 3.36: Net Revenue Surplus/ (Gap) at the end of FY 2013-14 .................................................... 59 Table 4.1: Sales for FY 2015-16 submitted by the Petitioner ............................................................. 60 Table 4.2: Energy sales from FY 2008-09 to FY 2014-15 ..................................................................... 61 Table 4.3: CAGR from FY 2008-09 to FY 2014-15 ................................................................................ 62 Table 4.4: No. of Consumers and Connected Load (kW) for FY 2015-16 as submitted by the Petitioner
.................................................................................................................................................. 62 Table 4.5: Category-wise Energy Sales approved by the Commission for FY 2015-16 ....................... 65 Table 4.6: Power Factor considered by the Commission for FY 2015-16 ........................................... 66
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 4
September 2015
Table 4.8: AT&C Loss proposed by the Petitioner for FY 2015-16 ....................................................... 67 Table 4.9: AT&C Loss for FY 2015-16 .................................................................................................. 67 Table 4.10: Estimated energy requirement proposed by the Petitioner for FY 2015-16 ................... 68 Table 4.11: Approved Energy Requirement for FY 2015-16 ................................................................ 68 Table 4.12: Power Purchase details submitted by the Petitioner for FY 2015-16 .............................. 69 Table 4.13: Allocation of Power from Delhi Stations to Petitioner for FY 2015-16 ............................ 69 Table 4.14: Energy available from Generating Stations to NDMC as approved by the Commission . 70 Table 4.16: Approved Power Purchase Cost by the Commission for FY 2015-16 ............................... 72 Table 4.17: RPO Obligation ................................................................................................................. 73 Table 4.18: Approved Renewable Energy to be procured by the Petitioner ...................................... 73 Table 4.19: Solar & Non-Solar Rate as per CERC Order ...................................................................... 74 Table 4.20: Approved Cost of Power purchase to meet RPO for FY 2015-16..................................... 74 Table 4.21: Transmission Charges and Losses submitted by Petitioner for FY 2015-16 .................... 75 Table 4.22: Transmission Charges and Losses approved by the Commission for FY 2015-16 ............ 76 Table 4.23: Energy Balance projected by the Petitioner for FY 2015-16 ............................................ 76 Table 4.24: Energy Balance approved by the Commission for FY 2015-16 ........................................ 77 Table 4.25: Approved Sale of Surplus Power for FY 2015-16 ............................................................. 78 Table 4.26: Rebate on Power purchase and Transmission Charges approved for FY 2015-16 .......... 79 Table 4.27: Total Power purchase Cost approved by the Commission for FY 2015-16 ...................... 79 Table 4.28: Schedule – Base cost for FY 2015-16 ............................................................................... 81 Table 4.29: O&M Expenses submitted by Petitioner for FY 2015-16 ................................................. 83 Table 4.30: Gross O&M Expenses approved for FY 2015-16 .............................................................. 84 Table 4.31: O&M Expenses approved by Commission for FY 2015-16 ............................................... 84 Table 4.32: Administrative and Civil Engineering Department Expenses proposed for FY 2015-16 .. 85 Table 4.33: Capital Expenditure and Capitalization projected for FY 2015-16 ................................... 85 Table 4.34: Capitalization approved for FY 2015-16 ........................................................................... 86 Table 4.35: Depreciation projected by the Petitioner for FY 2015-16 ................................................ 86 Table 4.36: GFA and Depreciation considered for FY 2015-16 ........................................................... 87 Table 4.37: Working Capital projected for FY 2015-16 ....................................................................... 87 Table 4.38: Working Capital considered for FY 2015-16 .................................................................... 88 Table 4.39: RRB projected by the Petitioner for FY 2015-16 .............................................................. 88 Table 4.40: RRB considered by the Commission for FY 2015-16 ........................................................ 89 Table 4.41: WACC projected by the Petitioner for FY 2015-16 .......................................................... 90 Table 4.42: Approved Weighted Average Cost of Capital (WACC) for FY 2015-16 ............................. 90 Table 4.43: RoCE Projected by Petitioner for FY 2015-16................................................................... 91 Table 4.44: RoCE approved for FY 2015-16 ........................................................................................ 91 Table 4.45: Non Tariff Income projected for FY 2015-16 ................................................................... 91 Table 4.46: Non Tariff Income approved for FY 2015-16 .................................................................... 91 Table 5.1: Net Revenue (Gap)/ Surplus of NDMC for FY 2013-14 ...................................................... 94 Table 5.2: Approved Revenue Gap for FY 2015-16 at existing Tariff .................................................. 94 Table 5.3: Revenue at existing and revised tariffs for FY 2015-16...................................................... 95
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 5
September 2015
List of Abbreviations
Abbreviation Explanation
ARR Aggregate Revenue Requirement
A&G Administrative and General
AAD Advance Against Depreciation
ABT Availability Based Tariff
ACD Advance Consumption Deposit
AMR Automated Meter Reading
APDRP Accelerated Power Development and Reforms Program
AT&C Aggregate Technical and Commercial
ATE Appellate Tribunal for Electricity
BEST Birhanmumbai Electric Supply and Transport
BHEL Bharat Heavy Electricals Limited
BIS Bureau of Indian Standards
BPTA Bulk Power Transmission Agreement
BRPL BSES Rajdhani Power Limited
BST Bulk Supply Tariff
BTPS Badarpur Thermal Power Station
BYPL BSES Yamuna Power Limited
CAGR Compounded Annual Growth Rate
CCGT Combined Cycle Gas Turbine
CEA Central Electricity Authority
CERC Central Electricity Regulatory Commission
CFL Compact Fluorescent Lamp
CGHS Cooperative Group Housing Societies
CGS Central Generating Stations
CIC Central Information Commission
CISF Central Industrial Security Force
CoS Cost of Supply
CPI Consumer Price Index
CPRI Central Power Research Institute
CPSUs Central Power Sector Utilities
CSGS Central Sector Generating Stations
CWIP Capital Work in Progress
DA Dearness Allowance
DDA Delhi Development Authority
DERA Delhi Electricity Reform Act
DERC Delhi Electricity Regulatory Commission
DIAL Delhi International Airport Limited
DISCOMs Distribution Companies (BRPL, BYPL, TPDDL & NDMC)
DMRC Delhi Metro Rail Corporation
DPCL Delhi Power Company Limited
DTL Delhi Transco Limited
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 6
September 2015
Abbreviation Explanation
DVB Delhi Vidyut Board
DVC Damodar Valley Corporation
EHV Extra High Voltage
EPS Electric Power Survey
FBT Fringe Benefit Tax
FPA Fuel Price Adjustment
GFA Gross Fixed Assets
GIS Geographical Information System
GoNCTD Government of National Capital Territory of Delhi
GTPS Gas Turbine Power Station
HEP Hydro Electric Power
HPSEB Himachal Pradesh State Electricity Board
HRA House Rent Allowance
HT High Tension
HVDS High Voltage Distribution System
IDC Interest During Construction
IGI Airport Indira Gandhi International Airport
IPGCL Indraprastha Power Generation Company Limited
JJ Cluster Jhugghi Jhopadi Cluster
KSEB Kerala State Electricity Board
LED Light Emitting Diode
LIP Large Industrial Power
LT Low Tension
LVDS Low Voltage Distribution System
MCD Municipal Corporation of Delhi
MES Military Engineering Service
MLHT Mixed Load High Tension
MMC Monthly Minimum Charge
MoP Ministry of Power
MTNL Mahanagar Telephone Nigam Limited
MU Million Units
MYT Multi Year Tariff
NABL National Accreditation Board for Testing and Calibration of Laboratories
NAPS Narora Atomic Power Station
NCT National Capital Territory
NCTPS National Capital Thermal Power Station
NDLT Non Domestic Low Tension
NDMC New Delhi Municipal Council
NEP National Electricity Policy
NGO Non Government Organisation
NHPCL National Hydroelectric Power Corporation Limited
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 7
September 2015
Abbreviation Explanation
NPCIL Nuclear Power Corporation of India Limited
NRPC Northern Regional Power Committee
NTI Non Tariff Income
NTP National Tariff Policy
O&M Operations and Maintenance
OCFA Original Cost of Fixed Assets
PGCIL Power Grid Corporation of India Limited
PLF Plant Load Factor
PLR Prime Lending Rate
PPA Power Purchase Agreement
PPAC Power Purchase Cost Adjustment Charges
PPCL Pragati Power Corporation Limited
PPS Pragati Power Station
PTC Power Trading Corporation
PWD Public Works Department
R&M Repair and Maintenance
RAPS Rajasthan Atomic Power Station
REA Regional Energy Account
RoCE Return on Capital Employed
ROE Return on Equity
RRB Regulated Rate Base
RTI Right to Information
RWA Resident Welfare Association
SBI State Bank of India
SERC State Electricity Regulatory Commission
SIP Small Industrial Power
SJVNL Satluj Jal Vidyut Nigam Limited
SLDC State Load Despatch Centre
SPD Single Point Delivery
SPUs State Power Utilities
SVRS Special Voluntary Retirement Scheme
THDCL Tehri Hydro Development Corporation Limited
ToD Time of Day
TOWMCL Timarpur Okhla Waste Management Company (P) Limited
TPDDL Tata Power Delhi Distribution Limited
TPS Thermal Power Station
UI Unscheduled Interchange
UoM Units of Measurement
WACC Weighted Average Cost of Capital
WC Working Capital
WPI Wholesale Price Index
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 8
September 2015
A1: INTRODUCTION
1.1 This Order relates to the Petition filed by New Delhi Municipal Council (hereinafter
referred to as ‘NDMC’ or the ‘Petitioner’) for True-Up of FY 2013-14, Review for FY
2014-15 and approval of Aggregate Revenue Requirement for FY 2015-16, in terms of
Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of
Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 (hereinafter referred to as
the ‘2nd MYT Regulations’), extended for one year upto 31st March, 2016 vide order
dated 22.10.2014.
New Delhi Municipal Council (NDMC)
1.2 New Delhi Municipal Council (NDMC) is a Municipal Council engaged in the
distribution of electricity to the consumers in the New Delhi area under Sections 195
to 201 of the New Delhi Municipal Council Act, 1994. NDMC is a Deemed Licensee
under the Electricity Act, 2003 in respect of the specified area in New Delhi.
Delhi Electricity Regulatory Commission
1.3 Delhi Electricity Regulatory Commission (hereinafter referred to as ‘DERC’ or the
Commission’) was constituted by the GoNCTD on 3.03.1999 and it became
operational from 10.12.1999.
1.1 The Commission’s approach to Regulation is driven by the Electricity Act, 2003, the
National Electricity Plan, the National Tariff Policy and the Delhi Electricity Reform
Act, 2000 (hereinafter referred to as ‘DERA’). The Electricity Act, 2003 (EA 2003)
mandates the Commission to take measures conducive to the development and
management of the electricity industry in an efficient, economic, and competitive
manner which inter-alia includes tariff determination.
The Co-ordination Forum
1.2 The Commission has, since constitution of the Co-ordination Forum on 16.03.2005,
held 28 meetings so far. In the 28th Co-ordination Forum Meeting held on
27.02.2015, the Commission discussed the following:
S. No. Issues Discussed
i. Status of GIS mapping of network & integration with SAP and SCADA by DISCOMs
ii. Summer preparedness
iii. Surrender/Re-allocation of Long term Power, considering the Demand-Supply
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 9
September 2015
scenario.
iv. Progress of DSM initiatives
v. Progress of projects under Net Metering Regulations, 2014
vi. Schemes to be taken under Integrated Power Development Scheme (IPDS)
vii. Proposal for disposal of DTs inherited from DVB, which are beyond repair
viii. Review of progress of replacement of oil filled transformers by dry type transformers.
Multi Year Tariff Regulations
1.3 The Commission issued ‘2nd MYT Regulations’ vide Order dated 2.12.2011 specifying
Terms and Conditions for Determination of Tariff for Generation, Transmission and
Distribution of electricity under the Multi Year Tariff (MYT) framework for the period
FY 2012-13 to FY 2014-15 after going through the public hearing process following
due process of law. The MYT Regulations, amendment to Regulations and extension
for another year were notified in the Official Gazette of Delhi on 19.1.2012,
15.3.2012 and 22.10.2014 respectively.
Filing of Petition for True-Up of Expenses for FY 2013-14 and approval of ARR for FY 2015-
16
Filing and Acceptance of Petition
1.4 NDMC has filed its Petition before the Commission on 20.02.2015 for True-Up of
FY 2013-14 and approval of Aggregate Revenue Requirement (ARR) for FY 2015-16.
The Commission admitted the Petition vide its Order dated 3.3.2015 subject to
clarifications/additional information, if any, which would be sought from the
Petitioner from time to time. A copy of the Admission Order dated 3.3.2015 is
enclosed as Annexure-I to this Order.
1.5 However, NDMC has withdrawn the Tariff Petition submitted on 20.02.2015 and
submitted the revised petition on 12.03.2015 to substitute original petition with the
revised petition, which has been examined to issue this tariff order.
1.6 Further, as requested by stakeholders/consumers, the Commission directed all the
Power Utilities to submit a Hindi version of the Petition filed by them. The English
versions of the Petition were uploaded on the website of the Commission as well as
on the website of the Petitioner for the benefit of stakeholders/consumers.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 10
September 2015
Interaction with the Petitioner
1.7 The Order has referred at numerous places to various actions taken by the
“Commission.” It may be mentioned for the sake of clarity, that the term
“Commission” in most of the cases refers to the Staff of the Commission and the
Consultant appointed by the Commission for carrying out the due diligence on the
Petition filed by the Petitioner, obtaining and analysing information/clarifications
received from the Petitioner and submitting all issues for consideration by the
Commission.
1.8 For this purpose, the Commission Staff and Consultant held discussions with the
Petitioner, obtained information/clarifications wherever required and carried out
technical validation with regard to the information provided.
1.9 The Commission held public hearings to take a final view with respect to various
issues concerning the principles and guidelines for tariff determination. The
Commission has considered due diligence conducted by the Staff of the Commission
and the Consultant in arriving at its final decision. The use of the term “Commission”
may, therefore, be read in the context of the above clarification.
1.10 A preliminary scrutiny/analysis of the Petition submitted by the Petitioner was
conducted and certain deficiencies were observed. Accordingly, deficiency notes
were issued to the Petitioner. Further, additional information/clarifications were
solicited from the Petitioner as and when required. The Commission and the
Petitioner also discussed key issues raised in the Petition, which included
Condemnation of delay in submitting the tariff petition owing to initiatives being
undertaken to segregate the accounts at NDMC being done by SBI Caps, examine the
proposal of NDMC for a favourable dispensation, request regarding pension trust
payment as NDMC is not a Successor Company of the erstwhile DVB, consider
allocation of power to NDMC in twelve-hour duration instead of existing twenty four
hour duration, consider retaining of rebate amount by NDMC in lieu of payment of
bills of Power Purchase and Transmission Charges, etc. The Petitioner submitted
additional information through various letters, as listed in Table 1.1.
1.11 The Commission also conducted multiple validation sessions with the Petitioner
during which discrepancies in the Petition were pointed out and additional
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 11
September 2015
information required by the Commission was sought. Subsequently, the Petitioner
submitted replies to the issues raised in these sessions and provided documentary
evidence to substantiate its claims regarding various submission.
1.12 The replies of the Petitioner, as mentioned in the Table 1.1 as follows, have been
considered for approval of the ARR of the Petitioner, :
Table 1.1: List of Correspondence with the Petitioner
S. No. Date Letter No. Subject
1 27.02.2015 D-17(Dir.)/Power/14 Draft public notice for public response
2 12.03.2015 - Revised Petition submitted
3 17.03.2015 D-727/EE/Power/15 Public Notice published in newspapers
4 08.04.2015 D-24/Dir/power/14 Prudence Check true up for FY 2013-14
5 10.04.2015 Email Response on data gaps
Public Notice
1.13 The Petitioner published a Public Notice indicating the salient features of its Petition
inviting comments from the stakeholders and requesting to submit response on the
petition on or before 10.04.2015 in the following newspapers on the respective
dates mentioned alongside:
a) The Hindustan Times (English) – 17.03.2015
b) The Times of India (English) – 17.03.2015
c) Hindustan (Hindi) – 17.03.2015
d) Quami Patrika (Punjabi) – 17.03.2015
e) The Daily Milap (Urdu) – 17.03.2015
1.14 Copies of the above Public Notice in English, Hindi, Punjabi and Urdu are enclosed as
Annexure II to this Order. A copy of the Petition was also made available for
purchase from the head-office of the Petitioner on any working day from 16.03.2015
to 10.04.2015 between 11 A.M. and 4 P.M. on payment of Rs 100/-. A copy of the
complete Petition was also uploaded on the website of the Commission, as well as
that of the Petitioner, requesting for comments of the stakeholders thereon.
1.15 The Commission also published a Public Notice in the following newspapers on
18.03.2015 inviting comments from stakeholders on the Tariff Petition filed by the
Petitioner latest by 10.04.2015.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 12
September 2015
a) The Times of India (English) 18.03.2015
b) The Hindu (English) 18.03.2015
c) The Hindustan Times (English) 18.03.2015
d) The Pioneer (English) 18.03.2015
e) Dainik Jagran (Hindi) 18.03.2015
f) Quami Patrika (Punjabi) 18.03.2015
g) Jadid in Dinon (Urdu) 18.03.2015
1.16 Copies of the above Public Notice in English, Hindi, Punjabi and Urdu are enclosed as
Annexure III to this Order.
1.17 In order to extend help to the consumers in understanding the ARR Petition and
filing their comments, the Commission prepared an Executive Summary highlighting
salient features of the revised Petition filed by the Petitioner, which was uploaded
on the Commission’s website. In this regard, two officers of the Commission viz. Joint
Director (Tariff-Finance) and Joint Director (Tariff-Engineering) were nominated for
discussion on the ARR Petitions. This was duly highlighted in the Public Notices
brought out by the Commission.
1.18 At the request of the stakeholders, the Commission extended the last date for filing
objections and suggestions upto 17.04.2015 for which the Public Notice was issued
in the following newspapers on the respective dates mentioned alongside:
a) Times of India (English) – 07.04.2015
b) Hindustan Times (English) – 07.04.2015
c) Hindustan( Hindi) --07.04.2015
d) The Educator, New Delhi (Punjabi) – 07.04.2015
e) Daily Milap (Urdu) – 07.04.2015
f) Amar Ujala( Hindi) – 07.04.2015
1.19 Copies of the above Public Notice in English, Hindi, Punjabi and Urdu are attached as
Annexure IV to this Order.
1.20 At the request of the stakeholders, the Commission extended the last date for filing
objections and suggestions 2nd time upto 24.04.2015 for which the Public Notice
was issued in the following newspapers on the respective dates mentioned
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 13
September 2015
alongside:
a) Times of India (English) – 18.04.2015
b) Hindustan Times (English) – 18.04.2015
c) Hindustan( Hindi) – 18.04.2015
d) The Educator, New Delhi (Punjabi) – 18.04.2015
e) Daily Milap (Urdu) – 18.04.2015
f) Amar Ujala( Hindi) – 18.04.2015
1.21 Copies of the above Public Notice in English, Hindi, Punjabi and Urdu are attached as
Annexure V to this Order.
1.22 The Commission published a Public Notice indicating the venue, date and time of
public hearings on 04.08.2015 in the following newspapers on the respective dates
mentioned alongside:
a) The Hindu (English) --23.07.2015
b) The Pioneer (English) --23.07.2015
c) The Hindustan Times (English) --23.07.2015
d) Nav Bharat Times( Hindi) --23.07.2015
e) Dainik Jagran (Hindi) --23.07.2015
f) Quami Patrika (Punjabi) --23.07.2015
g) Pratap(Urdu) --23.07.2015
1.23 Copies of the above Public Notice in English, Hindi, Urdu and Punjabi are enclosed as
Annexure VI to this Order.
1.24 The Commission published a Corrigendum on Public Notice indicating the venue,
date and time of public hearing on 04.08.2015 in the following newspapers on the
respective dates mentioned alongside:
a) The Hindu (English) --01.08.2015
b) The Pioneer (English) --01.08.2015
c) The Hindustan Times (English) --01.08.2015
d) Nav Bharat Times( Hindi) --01.08.2015
e) Dainik Jagran (Hindi) --01.08.2015
f) Quami Patrika (Punjabi) --01.08.2015
g) Pratap(Urdu) --01.08.2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 14
September 2015
1.25 Copies of the above Public Notice in English, Hindi, Urdu and Punjabi are enclosed as
Annexure VII to this Order.
1.26 The Commission received comments from 269 stakeholders/consumers. The
comments of the stakeholders/consumers were forwarded to the Petitioner. The
Petitioner responded to the comments of the stakeholders/consumers with a copy
of its replies to the Commission. The Commission invited all stakeholders/consumers
including those who had filed their objections and suggestions to attend the Public
Hearing.
1.27 The public hearings were held at the Siri Fort Auditorium, New Delhi for all
stakeholders/consumers on 04.08.2015 for consumers to discuss the issues related
to the petition filed by the Petitioner. The issues and concerns voiced by various
stakeholders/consumers have been examined by the Commission. The major issues
discussed during the public hearing and/or written comments made by the
stakeholders/consumers, the responses of the Petitioner thereon and the views of
the Commission, have been summarized in Chapter 2.
Layout of the Order
1.28 This Order is organised into six Chapters:
a) Chapter 1 provides details of the tariff setting process and the approach of the
Order.
b) Chapter 2 provides a brief of the Public Hearing including the details of
comments of various stakeholders/consumers, the Petitioner’s response and
views of the Commission thereon.
c) Chapter 3 provides details/analysis of the True-Up for FY 2013-14.
d) Chapter 4 provides analysis of the Petition for determination of the Aggregate
Revenue Requirement for FY 2015-16.
e) Chapter 5 provides details of the possible options for determination of Wheeling
and Retail Supply Tariff for all consumer categories for FY 2015-16 and the
approach adopted by the Commission in its determination.
f) Chapter 6 provides details of the Directives of the Commission for compliance of
the Petitioner.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 15
September 2015
1.29 The Order contains the following Annexure, which are an integral part of the Tariff
Order:
a) Annexure I - Admission Order.
b) Annexure II - Copies of Public Notices published by the Petitioner.
c) Annexure III - Copies of the Public Notice published by the Commission inviting
comments from the stakeholders/consumers.
d) Annexure IV - Copies of the Public Notice published by the Commission regarding
extension of last date of submission of comments.
e) Annexure V Copies of the Public Notice published by the Commission regarding
2nd extension of last date of submission of comments.
f) Annexure VI- Public Notice for Public hearing held on 4th August, 2015 at Siri Fort
Auditorium, New Delhi.
g) Annexure VII- Copies of Corrigendum on Public Notice for Public hearing held on
4th August, 2015 at Siri Fort Auditorium, New Delhi.
h) Annexure VIII - List of stakeholders/consumers who submitted their comments
on True-up for FY 2013-14 and approval of ARR for FY 2015-16.
Approach for FY 2013-14
1.28 On the basis of the MYT Regulations, 2011, a detailed MYT Order specifying AT&C
loss trajectory, controllable expenses, etc. during the period FY 2012-13 to FY 2014-
15 was issued along with the Tariff Order dated 13.07.2012.
1.29 Accordingly, under the MYT Framework, the Commission has projected the ARR for
the Petitioner for each year of the Control Period in the MYT Order 2012-15 issued
on 13.07.2012. Under MYT Regulations 2011, the components of ARR have been
segregated into controllable and un-controllable parameters. As per the regulation
4.21 of the MYT Regulation 2011, various controllable and un-controllable
parameters shall be trued-up as per the principles stated as follows:
a) Variation in revenue / expenditure on account of uncontrollable sales / power
purchase respectively shall be trued-up every year;
b) For controllable parameters,
i. Any surplus or deficit on account of Operation and Maintenance (O&M)
expenses shall be to the account of the Licensee and shall not be trued-up in
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 16
September 2015
ARR; and
ii. Depreciation and Return on Capital Employed shall be trued-up every year
based on the actual capital expenditure and actual capitalization vis-à-vis
capital investment plan (capital expenditure and capitalisation) approved by
the Commission.
Provided that any surplus or deficit in Working Capital shall be to the
account of the Licensee and shall not be trued-up in ARR.
Provided further that the Commission shall not true-up interest rate, if
variation in State Bank of India Base Rate as on 01.04.2012, is within ±1%
during the Control Period. Any increase/decrease in State Bank of India Base
Rate beyond ±1% only shall be trued-up.
1.30 The Petitioner was directed to submit asset wise capitalization details for the FY
2005-06 to FY 2013-14 within two months from the date of issue of order in the
Tariff Order dated 31.07.2013. The Petitioner has not submitted the requisite details
related to capitalisation including audited financial statements for electricity
distribution business from FY 2005-06 till date
1.31 The true-up of Capitalization involves physical verification of assets with the
procurement and accounting records of the utilities. The true-up, therefore, will be
possible only after the exercise of physical verification is complete. For physical
verification, a linkage needs to be established between equipments installed at site
and Fixed Asset Register being maintained by the distribution licensees. The
Commission is of the view that capitalization review for any year cannot be taken up
in isolation before completion of the exercise for previous years, as there are
overlapping issues like completion of schemes, MAP, IDC etc. The Petitioner has
been committing to provide the list of capitalised schemes, but never sought
approval for new schemes or provided the desired information on completed
schemes or audited accounts. In view of the excess Capitalization considered by the
Commission in past Tariff Orders based on the Petitioner’s submission without
adequate details and comparing the GFA of Electricity Distribution Business with
total GFA as per Annual Financial Statement of FY 2013-14, the Commission has now
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 17
September 2015
decided to restrict the GFA addition on provisional basis from FY 2005-06 to FY 2013-
14 subject to the actual details submitted by the Petitioner. Accordingly the
treatment of each parameter has been given in Chapter 3.
1.32 The Commission has accordingly, trued up the uncontrollable parameters viz. Power
Purchase Cost, Energy Sales and Revenue based on the information submitted by the
Petitioner for FY 2013-14 after exercising prudence check. The true up of
controllable parameters is governed by Regulation 4.21 of the 2nd MYT Regulations
as mentioned above. The detailed treatment of each component of uncontrollable
and controllable parameters is provided in Chapter 3 of this Order.
Approach for FY 2014-15
1.33 The Petitioner requested for a review of ARR for FY 2014-15 which had been
determined earlier by the Commission in its Order dated 23.07.2014. The mechanism
for True up as specified in the MYT Regulations envisages that variations on account
of uncontrollable items like energy sales and power purchase cost shall be trued up.
Truing up shall be carried out for each year based on actual/audited accounts and
prudence checks undertaken by the Commission. Accordingly, the Commission is of
the opinion that in accordance with the MYT Regulations, 2011 the True up of FY
2014-15 can only be considered based on the audited financial statement once the
Petitioner makes a regular tariff Petition for True up of FY 2014-15.
Approach for FY 2015-16
1.33 The ARR for the FY 2015-16 shall be determined inter alia based on the following
provisions of the MYT Regulations, etc. pertaining to Distribution business:
(a) Regulation 3.2 - ARR and Tariff for Wheeling Business and Retail Supply
business separately.
(b) Regulations 4.5 and 4.6 - Base line values (operating and cost parameters) and
performance targets.
(c) Regulations 4.7 and 4.8 - Targets for controllable Parameters including AT&C
loss, Distribution losses, Collection efficiency, O&M expenditure, Return on
capital employed, Depreciation and quality of supply and conditions for
eligibility for higher rate of incentive.
(d) Regulations 4.10, 4.11 and 4.12 - Sales forecast.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 18
September 2015
(e) Regulations 5.28 and 5.29 - AT&C loss reduction trajectory for each year of the
Control Period.
(f) Regulation 5.30 - Transmission and Load Dispatch Charges and Wheeling
charges.
(g) The allocation from the unallocated quota of Power at the disposal of GoNCTD
may change from time to time and needs to be considered based on the latest
available data or the Commission may have to make reasonable assumptions
with respect to allocation of power from the unallocated quota.
(h) Availability of power from the new sources of generation, based on their actual
/revised Commissioning schedule.
1.34 The Commission has evaluated the ARR submitted by the Petitioner on the basis of
the 2nd MYT Regulations extended for one year and other factors considered
appropriate by the Commission.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 19
September 2015
A2: RESPONSE FROM STAKEHOLDERS
Introduction
2.1 Section 64(3) of the Electricity Act, 2003, stipulates that the Commission shall
determine tariff under Section 62 of the Electricity Act, 2003 for the distribution
licensees, after consideration of all suggestions received from the public and the
response of the DISCOMs to the objections/suggestions of stakeholders, issue a tariff
order accepting the applications with such modifications or such conditions as may
be specified in the order. Public hearing, being a platform to understand the
problems and concerns of various stakeholders, the Commission has encouraged
transparent and participative approach in hearings to obtain necessary inputs
required for tariff determination. Accordingly public hearings was held in Siri Fort
Auditorium, New Delhi on 04.08.2015 with consumers to discuss the issues related
to the Petitions filed by NDMC for true up of expenses for FY 2013-14, Review for FY
2014-15 and ARR for FY 2015-16.
2.2 In the Public Hearings, the stakeholders offered their comments and
suggestions before the Commission in the presence of the Petitioners.
2.3 The Commission has examined the issues taking into consideration the
comments/suggestions offered by the various stakeholders in their written
statements and during the public hearings and also the response of the Petitioners
thereon.
2.4 The comments/suggestions of various stakeholders, the replies/response by the
Petitioners and the views of the Commission thereon are summarized under
following subheads:
Issue 1: Tariff Rates
Stakeholder’s comments
2.5 Proposed new rates are unfair to soldiers/veteran. Tariff rate should be Rs. 2 per unit
upto 400 units and Rs. 4 per unit for 401 to 800 units.
2.6 Proposed Tariff hike is not justifiable. Rates for electricity in Delhi are already very
high. It is not easy for a common man to bear them. Electricity rates are to be
reduced by 70%.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 20
September 2015
Petitioner’s Submission
2.7 Cost of Power Procurement and transmission charges are very high. If same are
reduced, increase in Tariff may not be required.
2.8 NDMC Tariff is lowest in Delhi and Tariff hike is the need of the hour. Tariff
rationalization is required to cover the regulatory assets.
2.9 Aggregate Revenue Requirement for NDMC is justified in the tariff petition.
Commission’s View
2.10 The Commission determines the ARR for the DISCOMs as per the provisions of the
Regulations. The Commission in its Tariff Order has provided the details of the
breakup of major components considered for projecting costs of supply during FY
2015-16, like power purchase cost, O&M costs, CAPEX, financing cost, gap in true up
of FY 2013-14 and carrying cost for the regulatory assets etc. This forms the basis for
projection of the gap between present requirement in terms of ARR and revenue
available at existing tariff. The gap between these two figures has to be filled by
increasing the tariffs and this is in consumer interest because failure to increase tariff
will only result in an increase in accumulated revenue gap/Regulatory Assets and
thus impose an additional burden on the average consumer. The Tariff Order is
issued after prudence check of the Petitions submitted by the DISCOMs and after
considering each element of their petitions with due analysis and ensuring proper
justification.
2.11 Further, the tariff for NDMC is relatively lower as compared to other DISCOMs. The
Commission has also retained the tariff for FY 2014-15 in FY 2015-16 as well.
Issue 2: Fixed Charges
Stakeholders’ View
2.12 Fixed charges to be reduced to reasonable level. Load is increased on the basis of
three highest KW readings in a year but it is not decreased on the same pattern.
Petitioner’s Submission
2.13 Load is increased because consumer consumes more than the sanctioned load
burdening the feeders and transformers. In case a consumer decides to use less load
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 21
September 2015
than sanctioned he/she can approach the DISCOM office for getting the load
reduced.
Commission’s View
2.14 The Commission is of view that the fixed cost in the Tariff has to be recovered so as
to meet the fixed cost element of the distribution business.
2.15 Tariff includes both Fixed and Energy charges. If Fixed charges are reduced, the
Energy charges are to be correspondingly increased to meet the ARR. When only
energy charge is levied or energy charge as well as fixed charge is levied, the same
would have to be recovered from the consumers. The Commission has already
initiated revision in Standard of Performance Regulation, 2007 and the stakeholder’s
comments/suggestions regarding revision of Sanctioned Load based on the three
highest MDI has been noted.
2.16 Further, the Commission has retained the existing practice of different fixed charges
slab for load upto 2 KW and between 2-5 KW
Issue 3: Tariff Rate for Doctor’s Clinics
Stakeholders’ View
2.17 Doctors who have their clinics at their residencies, which is allowed by law, should
not be charged at commercial rates for the electricity consumed, as this is a service
to the community.
Petitioner’s Submission
2.18 In Tariff Order issued by the Commission for FY 2014-15 for NDMC, under “Other
Terms and Conditions of Tariff”, it is mentioned that;
“Professionals i.e. individuals engaged in those activities involving services based
on professional skills including Doctors may utilize the domestic connection at
their residence for carrying out their professional work, provided the area used
for professional activity does not exceed the area permitted to be used for such
activity in residential area under the Master Plan for Delhi, 2021 (MPD-2021),
which as per MPD-2021 is permissible on any one floor only but restricted to less
than 50% of the permissible or sanctioned FAR whichever is less on that plot or
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 22
September 2015
dwelling unit.”
2.19 Applicability of category for Tariff shall be decided by the Commission through Tariff
Order for FY 2015-16.
Commission’s View
2.20 The Commission has already covered Doctors under the domestic tariff category as
per the tariff schedule approved, therefore if they are charged under non domestic
tariff category, stakeholders should approach to the Petitioner for charging under
the correct tariff category.
2.21 The Commission is of the view that extending concessional tariff to clinics/hospital,
etc. run by private parties would be a retrograde step and will increase the cross
subsidy element.
Issue 4: Separate sub-category for Telecom Towers
Stakeholders’ View
2.22 Telecom towers have been categorized under commercial category by Delhi utilities.
Telecom towers continuously consumed Power all around the day, thereby
maintaining a high load factor. Around 86% of electricity consumption is fairly
constant over a 24 hours period. Due to their telecom towers do not contribute
significantly to the peak hour consumption of the DISCOMs and are part of the base
load of distribution utility. Such a load profile does not pressure out the distribution
utility to buy additional short term power at higher prices there by leading to overall
lower ‘cost to serve’ for such consumers. Hence, a new sub-category for telecom
towers within commercial category with timer Tariff has to be introduced.
Petitioner’s Submission
2.23 Telecom towers are commercial establishments and should be treated at commercial
category. However, direction of DERC shall be accepted.
Commission’s View
2.24 The Commission is of the view that in most of the states, telecom towers are covered
under commercial Tariff Category only. For example MERC and UPERC etc. also do
not recognize Telecom Service Sector as a separate category for electricity Tariff
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 23
September 2015
Purpose. Therefore, creation of a separate Tariff category for Telecom Tower
Operators is not considered necessary.
Issue 5: Time of Day Metering and Net Metering
Stakeholders’ View
2.25 Time of Day Metering: DISCOMs have proposed to cover all consumers under ToD
having sanctioned load of 10KW and above in order to flatter the load curve. It may
be ensured that the smart meters procured by DISCOMs should have all these
features like ToD, net metering etc and all these features should be activated so that
undue burden on consumers is avoided.
2.26 Net Metering: DISCOMs have proposed that consumers opting for net metering for
installing Solar PV plants on their roof tops should pay in single slab of 400-800 units
(Rs. 7.80 per unit) this will discourage solar power which is a clean and sustainable
source of power.
Petitioner’s Submission
2.27 NDMC has implemented ToD and net metering as per DERC Regulations.
Commission’s View
2.28 The Commission is of the view that ToD tariff is an important Demand Side
Management (DSM) measure to flatten the load curve of the DISCOMs. Surcharge
has been introduced under ToD tariff during the peak hours consumption to offset
the costly power purchase during the peak hours and rebate is given to consumers
for shifting the demand from peak to off peak hours.
2.29 The Commission has reviewed the ToD time slots as per the suggestions/comments
received from various stakeholders including GoNCTD and the latest available trend
for demand and supply of power.
2.30 It is observed that during the months of October - April, the maximum demand is less
than the available base supply of power. Accordingly, the ToD Tariff has been
modified and shall be applicable for remaining five (5) months i.e., May – September
of the year as follows:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 24
September 2015
a. The Rebate during the Off Peak hours has been reduced from 25% to 20%,
whereas for Peak hours Surcharge shall continue at existing 20%.
b. For other than Peak and Off Peak period, Normal charges as defined shall be
applicable.
c. It shall be now applicable for all consumers (other than domestic) whose
sanctioned load/ MDI is 25kW/ 27kVA and above instead of 50kW/ 54kVA.
d. Option of TOD tariff is also available for all consumers (other than Domestic)
whose sanctioned load/MDI (whichever is higher) is 11kW/12kVA to
25kW/27kVA. Such ToD Consumers will have the option to move back to non-ToD
regime only once within one Financial Year.
Issue 6: Payment of Electricity Bill by Credit Card
Stakeholders’ View
2.31 Payment of Electricity bill above Rs. 5000/- to be allowed through credit card.
Petitioner’s Submission
2.32 In NDMC, payment of any amount can be made through net banking. For payment of
collection centres, directions of DERC are complied.
Commission’s View
2.33 Regarding payment of electricity bills of more than Rs. 4000/- not by cash, the
Commission has taken a conscious decision that in case the bill for consumption of
electricity is more than Rs. 4000/-, payment of the bill be accepted by the Petitioner
by means of Account Payee Cheque/DD. However, payment of any amount can be
made through net banking payment. The Commission has in its tariff order for FY
2009-10 also directed the Petitioner to accept the cash payment of more than Rs.
4000/- for payment of electricity bill in the case of visually impaired consumers only.
Months Peak Hours Surcharge on
Energy Charges Off-Peak Hours
Rebate on Energy Charges
May- September
1300-1700 hrs and
2100-2400 hrs 20% 0300-0900 hrs 20%
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 25
September 2015
Issue 7: Audit of NDMC Accounts
Stakeholders’ View
2.34 Warning should be given to NDMC that if they do not comply with directives, their
License shall be revoked. NDMC does not have separate accounts since inception 13
years have been passed. NDMC shall be directed to do the same in 6 months,
otherwise License revocation proceeding should be started. No expenses shall be
allowed this year if NDMC has not complied with the directive.
Petitioner’s Submission
2.35 NDMC is not an exclusive electricity utility as others are. NDMC is a municipality
formed under Parliament Act for providing general services to the residents of NDMC
area. Electricity distribution is one of the many obligations of NDMC. Most of the
directives of DERC are compiled by NDMC. Separation of accounts is extremely
difficult. Except the Engineers, all other posts in NDMC are transferable from one
department to another. However, for separating accounts, NDMC has appointed a
consultant and shall be able to separate accounts.
Commission’s View
2.36 The Commission observed that NDMC has not been maintaining separate records/
accounts for the electricity business as a separate entity for supplying electricity in
the NDMC area. The Commission has already directed NDMC to separate the
accounts of the electricity business from other activities latest by April, 2010 to
which NDMC has not complied with till date. Due to non-availability of this critical
data, the Commission could not carry out detailed analysis/periodic review of various
elements of expense and revenue. Therefore, the Commission once again directs the
Petitioner to maintain regulatory accounts and expedite the process of segregation
of accounts for its electricity business.
2.37 Further, the Commission has revised the provisional GFA from FY 2005-06 onwards
for the Petitioner due to non submission of audited financial statement and other
details and carrying cost, if any, shall not be allowed to the Petitioner on
substantiating the additional impact based on the audited financial statement on
account of GFA revision.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 26
September 2015
Issue 8: Tariff for DMRC
Stakeholders’ View
1. Tariff Increase:
2.38 NDMC proposed to increase the tariff for DMRC i.e. fixed charges from Rs. 125/KVA
to Rs. 164/KVA (31% increase) and energy charges from Rs. 6.10/KVAh to Rs.
7.99/KVAh (31% increase). The unit rate is fixed over and above the power purchase
of DISCOMs instead of fixing unit rate based on purchase cost by DISCOM at 66
KV/220 KV. Thereby even after taking supply at 220KV/66 KV, DMRC is made to bear
energy losses of the distribution net work as well as paying to DISCOMs at the tariff
which is higher than Power Purchase Cost.
2. Effect of increase in Tariff:
2.39 There is an effective increase of almost 178% in last 5 years (i.e from Rs. 2.50 to 6.94
per unit). This has resulted in increase in working expenses of DMRC by 647.7% (i.e.
from Rs. 51.5 Crore in 2007-08 to Rs. 399 Cr in 2013-14), whereas increase in energy
consumption is only 186% (22 Cr units in 2007-08 to 63 Cr units in 2013-14). DMRC
will not be in a position to sustain any additional increase in tariff without passing on
to the consumer.
3. Distribution Losses
2.40 DISCOMs have not disclosed voltage wise losses in its ARR Petition for FY 2015-16.
The purchase cost at 66 KV without considering distribution losses of lower voltage
will be much lower than Rs. 5.77/unit. Since DMRC takes power at 220kV/66KV and
does not contribute to distribution losses, separate power purchase costs may be
given by DISCOMs at various voltage levels (i.e. 220KV 66KV and L.T. level) after
taking into consideration losses at corresponding voltage levels along with
declaration of power purchase cost at each of the above voltage levels, clearly
accounting for the losses for respective voltage levels.
4. Change in contract demand twice in a year
2.41 DMRC may be allowed to change the contract demand twice in a year as the
maximum demand in summer due to high Air Conditioners in service is nearer to
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 27
September 2015
contract demand and it is much lower in winter. DMRC is paying every month for
contract demand same amount throughout the year.
5. Fixed Charges
2.42 As per agreed principle in November 2002, there is no provision of fixed charges.
Hence, fixed charges are not applicable to DMRC and withdrawal of the same to be
considered by DERC.
6. Revenue Deficit Surcharge
2.43 DMRC may be exempted from payment of Revenue Deficit surcharge (8%
Surcharge).
Petitioner’s Submission
2.44 No response.
Commission’s View
2.45 The DMRC has already been considered as a special tariff category in the tariff orders
issued by the Commission year on year. The issue of drawing power at higher voltage
and rebate thereon has been inbuilt in the Tariff design and addressed appropriately
in the Tariff Order.
2.46 The revision in load can be carried out as per the Provisions of Delhi Electricity
Supply Code and Performance Standards Regulations, 2007.
2.47 The commission is of the view that any increase in tariff for DMRC is on account of
increase in power purchase cost and other components forming part of the ARR of
the distribution licensees.
2.48 The Commission has already directed to the Petitioner for energy audit to determine
the voltage wise loss in the network of the Petitioner.
2.49 The Tariff determined by the commission in respective tariff order was also fixed by
considering all the factors discussed above.
2.50 The Commission has already directed Petitioner for restricting the outages so that
they do not exceed 1% in its area. Therefore, the losses have also been factored in
determining tariff of relevant category.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 28
September 2015
A3: True up of FY 2013-14
Background
3.1 The Commission had approved the Aggregate Revenue Requirement (ARR) of the
Petitioner i.e., New Delhi Municipal Council (NDMC) for FY 2013-14 in its tariff order
dated 31.07.2013. The Delhi Electricity Regulatory Commission (Terms and
Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations,
2011, which are extended for further one year up to FY 2015-16 vide order dated
22.10.2014, provide for truing up of controllable components i.e. Depreciation and
Return on Capital Employed based on review of actual investment during the control
period and uncontrollable components of the ARR at the end of each year of the
Control Period based on audited accounts and prudence check by the Commission.
3.2 NDMC in its Petition has sought for truing up of uncontrollable components for
FY 2013-14. It was informed by the Petitioner that figures in the petition are based
on the budget book for FY 2013-14.
3.3 The Commission would like to reiterate that the Petitioner is not complying with the
directives issued by the Commission in its earlier tariff orders since the first Tariff
Order for FY 2005-06. The Commission in its earlier Tariff Orders for FY 2005-06 and
FY 2006-07 had given directives to NDMC to submit audited information regarding
break-up of assets, separate records for Repair & Maintenance and Administration &
General Expenses incurred for electricity business in its annual petitions. The
Petitioner is yet to comply the directives issued by the Commission.
3.4 The Commission observed that NDMC has not been maintaining separate records/
accounts for the electricity business as a separate entity for supplying electricity in
the NDMC area to the Commission. The Commission directed NDMC to segregate
the accounts of the electricity business from other activities latest by April 1, 2010
and extended the deadline in subsequent Tariff Orders, to which NDMC has not
complied with till date.
3.5 Further, the Commission had directed the Petitioner to take prior approval of capital
expenditure from the Commission in its Tariff Order dated 31.07.2013 as follows:
“3.19 However, for truing up purpose the Commission has provisionally retained
the capitalisation for the first Control Period as approved by the Commission in
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 29
September 2015
its MYT Order for FY 2007-08 to FY 2010-11 and as approved in Tariff Order for
FY 2011-12. The Commission will carry out the truing up of the actual
capitalisation for the first Control Period once the Petitioner submits scheme wise
details of asset capitalisation with cost benefit analysis to the satisfaction of the
Commission. The Commission accordingly directs the Petitioner to submit
scheme wise asset capitalisation details within two months from the date of
issue of this Order.
.........
3.83 The Commission re-iterates that the consideration of capital investment
including capitalization of interest and establishment expenses during the
Control Period for the purpose of determination of ARR does not imply approval
of schemes and the Petitioner has to obtain the scheme wise approval for the
capital expenditure to be incurred during each year of the Control Period as per
the annual investment plan drawn for the purpose. The Annual investment plan
should be submitted prior to commencement of the respective Financial Year.
The Petitioner is directed to submit the complete DPRs along with cost benefit
analysis for schemes more than Rs 2 Cr for obtaining investment approval of the
Commission. The Petitioner shall also obtain the approval from the Commission
for individual schemes less than Rs 2 Cr but aggregating to Rs 20 Cr. The
Petitioner is advised to submit the quarterly progress report of actual capital
investment in the format prescribed by the Commission within one month of the
respective quarter. The Commission would also True-up the capital investment
for each year at the end of the Control Period based on the actual capital
investment carried out by the Petitioner.
3.84 In the absence of the afore-mentioned information, it is not possible to carry
out final once again directed to comply with directions stipulated in the MYT
Order so that the Commission can carry out due prudence check before
approving the same.”
3.6 The Commission has commented in its Tariff Order dated 23.07.2014 regarding
audited accounts and relevant data for capitalisation as follows:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 30
September 2015
“The Commission is constrained to remark that despite the assurance given by
the Petitioner every year that it would furnish all relevant data and audited
accounts for the relevant Financial Year/s to the Commission, it has never
submitted separate records/accounts for electricity business as a separate entity
in any of its Petition. Further, the Petitioner has not provided the requisite
information in all the detailed formats prescribed by the Commission under the
2nd MYT Regulations.”
3.7 The Petitioner was directed to submit asset wise capitalization details for the FY
2005-06 to FY 2013-14 within two months from the date of issue of order in the
Tariff Order dated 31.07.2013. NDMC has not submitted the requisite details related
to capitalisation including audited financial statements for electricity distribution
business from FY 2005-06 till date.
3.8 The Commission officers have visited the office of the Petitioner to examine the
details for true up of capitalisation from FY 2005-06 onwards. The Petitioner
provided Annual Financial Statement for FY 2013-14 during the Technical Validation
Session at the office of the Petitioner. It is observed from Annual Financial Statement
(signed by Chairperson, NDMC) that indicates Gross Fixed Asset for NDMC as a whole
as on 01.04.2013 is Rs. 277.51 Crore as against GFA of Rs. 1080.07 Crore
provisionally recognized in Tariff Order dated 23.07.2014.
3.9 The Commission had recognized the opening GFA of Electricity Business for NDMC in
Tariff Order dated 02.11.2005 as follows:
“2.13.2…the Commission asked the Petitioner to submit the write-up on
methodology adopted for arriving at total value of assets for Electricity
Department. The salient features of details provided by the Petitioner are as
follows:
· Asset Value as on 31st March 2004 has been arrived at based on book value of
material and erection as per the information obtained from all the divisions
· The land and buildings belong to NDMC and therefore not allocated to
electricity department
· The original value of assets includes the value of assets taken over from DVB
and the investments made by NDMC since 1989.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 31
September 2015
· Asset Register is being maintained by the concerned divisions of electricity.
Assets valuation is being done on the basis of the cost of its acquisition and other
elements to be capitalised as per the norms
The Commission has considered the value of Gross Fixed Assets at the end of
March 2004 as provided by the Petitioner.”
3.10 In view of the excess Capitalization considered by the Commission in past Tariff
Orders based on the Petitioner’s submission without adequate details and
comparing the GFA of Electricity Distribution Business with total GFA as per Annual
Financial Statement of FY 2013-14, the Commission has now decided to restrict the
GFA addition from FY 2005-06 to FY 2012-13.
3.11 The GFA addition during FY 2005-06 to FY 2012-13 has been restricted provisionally
on the basis of minimum of GFA addition submitted by the Petitioner and maximum
of Rs. 20 Crore GFA addition allowed without approval of the Commission during a
year till the time the Petitioner submits the scheme wise details of Capitalisation for
True up of Capitalisation.
3.12 The Petitioner is directed to submit the actual claim on account of GFA addition from
FY 2005-06 to FY 2013-14 with scheme wise details on yearly basis. Further, no
carrying cost shall be allowed on difference if any in the provisional capitalisation
and actual capitalisation.
Revision in GFA and Depreciation in Past period up to FY 2012-13
3.13 The revised GFA and Depreciation due to change in GFA from FY 2005-06 to FY 2012-
13 is as follows:
Table 3.1: Impact of Revised GFA on Depreciation during FY 05-06 to FY 12-13 (Rs. Crore)
Sl. No.
Particulars FY
2006 FY
2007 FY
2008 FY
2009 FY
2010 FY
2011 FY
2012 FY
2013
A Opening GFA 311.55* 327.57 343.14 363.14 383.14 403.14 423.14 443.14
B Addition during the year considered in relevant T.O.
16.02 15.57 81.60 228.64 174.88 109.82 112.50 68.71
C
Max. Addition allowed without approval during the year
20.00 20.00 20.00 20.00 20.00 20.00 20.00 20.00
D Min. of (B,C) 16.02 15.57 20.00 20.00 20.00 20.00 20.00 20.00
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 32
September 2015
Sl. No.
Particulars FY
2006 FY
2007 FY
2008 FY
2009 FY
2010 FY
2011 FY
2012 FY
2013
E Closing GFA (A+D) 327.57 343.14 363.14 383.14 403.14 423.14 443.14 463.14
F Avg. GFA ((A+E)/2) 319.56 335.36 353.14 373.14 393.14 413.14 433.14 453.14
G Depreciation @ 3.6 % on ‘F’
11.50 12.07 12.71 13.43 14.15 14.87 15.59 16.31
H Depreciation allowed in relevant Orders
11.50 12.07 13.49 17.43 23.85 30.04 34.63 37.89
I Difference (H-G) 0.00 0.00 0.78 4.00 9.70 15.17 19.04 21.58
*As per T.O. dated 02.11.2005
Revision in RoCE in Past period up to FY 2012-13 3.14 Due to revision in GFA and depreciation, RRB and RoCE from FY 2005-06 to FY 2012-
13 has also been revised as follows:
Table 3.2: Revised RRB (Capital Base) during FY 2005-06 to FY 2012-13 (Rs. Crore)
S.N.
Particulars FY
2005-06
FY 2006-
07
FY 2007-
08
FY 2008-
09
FY 2009-
10
FY 2010-
11
FY 2011-
12
FY 2012-
13
I OCFA 311.55 327.57 343.14 363.14 383.14 403.14 423.14 443.14
II Opening Working Capital
0.00 8.63 16.81 34.07 45.04 49.24 60.24 87.23
III Accumulated Depreciation
227.18 238.68 250.76 263.47 276.90 291.06 305.93 321.52
A Regulated Rate Base (RRB) (Opening)
84.37 97.52 109.19 133.74 151.28 161.32 177.45 208.85
B Depreciation 11.50 12.07 12.71 13.43 14.15 14.87 15.59 16.31
C Security Deposit 18.99 24.34 0.00 0.00 0.00 0.00 0.00 0.00
D Working Capital 8.63 8.18 17.26 10.97 4.20 11.00 26.99 (16.54)
E RRB (Closing) 62.51 69.28 113.74 131.28 141.32 157.45 188.85 175.99
F Change in RRB (ΔRB)
(6.62) (10.03) 10.90 4.25 (2.88) 3.56 19.19 (24.70)
G Regulated Rate Base (RRB)(i)
77.75 87.49 120.10 137.99 148.40 164.89 196.64 184.15
Table 3.3: Revised RoE during Policy Direction period (FY 05-06 and FY 06-07) (Rs. Crore)
S.N. Particulars FY 2005-06 FY 2006-07
A Capital Base 77.75 87.49
B Equity 77.75 87.49
C Debt 0.00 0.00
D Rate of return on Equity 16.00% 16.00%
E Return on Equity (RoE) 12.44 14.00
F Already Trued Up in previous Order 13.97 14.74
G Recovery 1.53 0.74
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 33
September 2015
Table 3.4: Revised RoCE during FY 2007-08 to FY 2012-13 (Rs. Crore)
Sl. N.
Particulars FY 2007-
08 FY 2008-
09 FY 2009-
10 FY 2010-
11 FY 2011-
12 FY 2012-
13
A Regulated Rate Base (RRB)
120.10 137.99 148.40 164.89 196.64 184.15
B Equity 36.03 41.40 44.52 49.47 58.99 55.25
C Debt 84.07 96.60 103.88 115.42 137.65 128.91
D Rate of return on Equity
16.00% 16.00% 16.00% 16.00% 16.00% 16.00%
E Rate of Return on Debt
11.50% 11.50% 11.50% 11.50% 11.50% 11.50%
F Weighted Avg. Cost of Capital (WACC)
12.85% 12.85% 12.85% 12.85% 12.85% 12.85%
G Return on Capital Employed (RoCE)
15.43 17.73 19.07 21.19 25.27 23.66
H Already Trued Up in previous Order
18.67 30.82 57.38 76.75 92.80 97.06
I Recovery 3.24 13.09 38.31 55.56 67.53 73.40
Revision in Administrative and Civil Engineering Dept. Expenses for FY 2012-13 3.15 The Commission has directed the Petitioner in the Tariff Order dated 13.07.2012 to
furnish the details of Administrative and Civil Engineering Department as follows:
“4.123 The Commission directs the Petitioner to separately book the cost of
works carried out by civil engineering department for electricity department and
provide complete details of such works and associated costs at the end of the
year bringing out clearly the percentage expenditure of Civil Engineering
Department booked to electricity department vis-à-vis all other departments.”
3.16 Further, the Commission observed in its Tariff Order dated 23.07.2014 is as follows:
“3.63 The Petitioner has furnished neither the information in respect of General
Administrative Expenses of Rs.433.89 Crore nor audited accounts for FY 2012-13.
3.64 In this regard, the Commission had directed vide Para 4.123 of 2nd MYT
Order to the Petitioner to separately book the cost of works carried out by Civil
Engineering Department for Electricity Department and provide the complete
details of such works and associated costs at the end of the year bringing out
clearly the percentage expenditure of Civil Engineering Department booked to
Electricity Department vis-à-vis other departments. However, the Petitioner has
not complied with this directive.”
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 34
September 2015
3.17 The Commission observes that the O&M Expenses per unit of Sale is highest of the
Petitioner among all Delhi Distribution Licensees indicated as follows:
DISCOM O&M expenses approved in FY
2012-13 (Rs. Crore)
Sales approved in FY 2012-13 (MU)
O&M Expenses (Rs./kWh)
BRPL 445.95 9348.83 0.48
BYPL 325.55 4971.92 0.65
TPDDL 389.52 6944.02 0.56
NDMC (Excluding Administrative and Civil Engineering Dept. Expenses)
141.95 1291.25 1.10
3.18 In view of the above, the Commission has not considered the amount of Rs. 45.37
Crore on account of Administrative and Civil Engineering Dept. Expenses in FY 2012-
13 due to highest O&M Expenses per unit of Sale of the Petitioner in comparison to
other distribution licensees operating in the area of GoNCTD and allows only
Normative O&M Expenses as approved in 2nd MYT Order for FY 2012-13.
Past Period True up with Carrying Cost
3.19 Based on the above discussions, the impact of Revised GFA, Revised Depreciation,
RoE, RoCE and Administrative & Civil Engg. Dept. Expenses along with Carrying Cost
is as follows:
Table 3.5 (a): Impact of True up during PDP along with Carrying Cost (Rs. Crore)
Sl. No. Particulars FY 2005-06 FY 2006-07 Remarks
A Opening Revenue Gap 0.00 1.53 B Recovery from Depreciation 0.00 0.00 Table 3.1
C Recovery from RoE 1.53 0.74 Table 3.3
D Total Adjustment during the year 1.53 0.74 B+C
E Carrying cost Rate 9.50% 9.50%
Relevant Tariff Order
F Carrying cost on opening balance 0.00 0.14 G Closing RG 1.53 2.41 A+F+G
Table 3.5 (b): Impact of True up during FY 07-08 to FY 12-13 along with Carrying Cost (Rs. Crore)
Sl. No. Particulars FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013
A Opening Revenue Surplus/(Gap) 21.89 201.66 536.88 510.60 431.23 155.01
B Adjustment on account of PDP 2.41
C ARR as earlier approved (July 2013 Order)
(i) Annual Revenue Requirement for the year 322.35 241.53 650.76 799.74 1055.73 1015.58
(ii) Revenue for the year 483.46 519.67 519.76 598.64 661.19 866.09
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 35
September 2015
Sl. No. Particulars FY 2008 FY 2009 FY 2010 FY 2011 FY 2012 FY 2013
Adjustment in ARR
1 Reduction in Depreciation 0.78 4.00 9.70 15.17 19.04 21.58
2 Reduction in RoE/RoCE 3.24 13.09 38.31 55.56 67.53 73.40
3 Admn. and Civil Engg. Dept. Expenses 45.37
4 Net Adjustments 4.01 17.08 48.01 70.73 86.57 140.34
5 Revised ARR for every year 318.34 224.45 602.75 729.01 969.16 875.24
6 Revised Revenue Surplus/(Gap) 165.12 295.22 (82.99) (130.37) (307.97) (9.15)
7 Closing Revenue Surplus/(Gap) 189.42 496.88 453.88 380.23 123.26 145.86
8 Avg. gap 106.86 349.27 495.38 445.42 277.25 150.43
9 Rate of Carrying Cost 11.45% 11.45% 11.45% 11.45% 11.45% 12.85%
10 Amount of Carrying Cost 12.24 39.99 56.72 51.00 31.74 19.33
D Closing 201.66 536.88 510.60 431.23 155.01 165.19
True-up of FY 2013-14
Energy Sales
Petitioner’s Submission
3.20 The Petitioner has submitted total sales of 1307.23 MU for FY 2013-14 in its True up
petition as against 1346.88 MU approved by the Commission in the tariff order dated
31.07.2013.
Commission’s Analysis
3.21 The Commission analyzed the category wise annual sales data submitted by the
Petitioner for FY 2013-14.
3.22 The Commission noted that Form 2.1 (a) received along with petition is not audited
and no other information is made available by the Petitioner to the Commission.
3.23 The Commission, for truing up of sales, conducted the prudence check and received
the figures from the Petitioner. The Commission officers have visited the office of
the Petitioner to collect the data pertaining to Sales and Revenue for FY 2013-14.
and the Petitioner submitted revised Form 2.1 a. The Commission noted that the
Petitioner has submitted revised month-wise sales, revenue billed data in Form 2.1
(a) as per which the revenue billed is at Rs. 978.34 Crore for FY 2013-14 including
Electricity Duty of Rs.42.82 Crore. Therefore as per the claim of the Petitioner, the
revenue billed is approved at Rs. 935.52 Crore after deduction of Electricity Duty and
other adjustments.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 36
September 2015
3.24 and accordingly the category wise trued up sales and the revenue collected for FY
2013-14 as approved by the Commission are as follows:
Table 3.6: Trued Up Energy Sales for FY 2013-14
Sl. No.
Category
Approved in Tariff Order dated
31.07.2013
Petitioner’s Submission
Now Approved
Sales (MU)
Revenue (Rs. Cr)
Sales (MU)
Revenue (Rs. Cr)
Sales (MU)
Revenue (Rs. Cr)
1 Domestic 273.28 135.34 251.62 251.61 119.85
2 Non- Domestic 1019.47 790.00 1001.11 991.32 778.46
(I) NDLT 260.44 375.65 249.16 239.37 177.96
(II) Mixed Load 759.03 414.35 751.95 751.95 600.50
3 Small Industrial Power 0.25 0.16 0.21 0.21 0.13
4 Public Lighting 8.33 5.91 8.32 8.32 6.17
5 DMRC 35.00 21.10 36.23 36.23 20.86
6 Others 10.55 4.68 9.74 19.49 10.05
7 Total 1346.88 957.19 1307.23 931.87* 1307.18 935.52*
*Petitioner Submission and Commission approved figures exclude Electricity Duty.
AT&C Losses
Petitioner’s Submission
3.25 The Petitioner has submitted that its AT&C loss level for FY 2013-14 was at 9.58%
against 10.10% approved for the FY 2013-14 in the tariff order dated 31.07.2013.
3.26 The Petitioner has submitted that the actual collection efficiency for FY 2013-14 was
98.61% against target of 100% approved in the Tariff Order dated 31.07.2013 as
follows:
Table 3.7: Collection efficiency for FY 2013-14 submitted by the Petitioner
Particulars Approved in the Order
dated 31.07.2013 Petitioner’s Submission
AT&C Losses 10.10% 9.58%
Distribution Losses 10.10% 8.31%
Collection Efficiency 100% 98.61%
3.27 The Petitioner has submitted its computation for AT&C loss level of 9.58% achieved
during FY 2013-14, summarized below:
Table 3.8: AT&C loss computation for FY 2013-14 as submitted by the Petitioner
Particulars Unit Petitioner’s Submission
Net Power Available for Sale to NDMC Consumers MU 1425.69
Energy Sold to the Consumers MU 1307.23
Distribution Losses MU 8.31%
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 37
September 2015
Particulars Unit Petitioner’s Submission
Revenue Billed (Excluding Electricity Duty @ 5%) Rs. Cr 931.87
Revenue Realized (Excluding Electricity Duty @ 5%) Rs. Cr 918.92
Average Billing Rate Rs. 7.13
Collection Efficiency % 98.61%
AT&C Losses % 9.58%
3.28 The Petitioner has submitted additional information wherein the energy balance
indicating the energy availability, transmission & distribution loss and surplus energy
vide letter No. D-25/Dir(Power)/15 dated 10.04.2015 which is shown below:
Table 3.9: Additional submission of the Petitioner
Sl. No.
Particulars UoM FY 2013-14
A Energy Availability
I Total Energy Available (excluding BTPS, SGS, TOWMCL & Solar)
MU 742.71
II Inter-state Transmission Loss % 3.36
MU 24.96
III Energy available from BTPS and SGS MU 1355.87
IV Short term purchase MU 13.17
V Surplus power sold MU 651.28
VI Energy available at state transmission periphery
MU 1435.52
VII UI purchase MU 29.44
VIII Net energy available at state periphery
MU 1464.96
B Energy Requirement
I Energy sales MU 1307.23
II Distribution Losses % 9.73
MU 140.92
III Energy Injected from RE source at DTL periphery
MU 0.33
IV Energy requirement at distribution periphery
MU 1448.15
V Intra-state transmission loss % 1.17%
MU 17.14
VI Energy requirement at transmission periphery
MU 1464.96
C Surplus Energy MU 651.28
Commission’s Analysis
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 38
September 2015
3.29 The Commission in its 2nd MYT Order dated 13.07.2012 had fixed AT&C loss
reduction target for NDMC at 10.10% for FY 2013-14.
3.30 The Commission has considered 1400.12 MU as the energy input to the NDMC
periphery as submitted by SLDC through letter number F./DTL/207/14-15/GM
(SLDC)/F-41/01 dated 06.04.2015 against 1425.69 MU as submitted by the Petitioner
earlier in its petition, which later on was revised as 1448.15 MU by the Petitioner
vide their letter dated 10.04.2015.
3.31 The Commission noted that the Petitioner has submitted revised month-wise sales,
revenue billed data in Form 2.1 (a) as per which the revenue billed is at Rs. 978.34
Crore for FY 2013-14 including Electricity Duty of Rs.42.82 Crore. Therefore as per
the claim of the Petitioner, the revenue billed is approved at Rs. 935.52 Crore after
deduction of Electricity Duty and other adjustments.
3.32 The Petitioner has submitted that revenue realised during FY 2013-14 from sale of
electricity is Rs. 951.34 Crore. During the prudence check, the Petitioner submitted
figures of Rs. 42.82 Crore and Rs. 6.89 Crore and Rs. 15.49 Crore realized as
Electricity Duty, Non Tariff Income (NTI) and arrears of previous years respectively. In
view of this, the Commission considered Rs. 886.14 Crore as revenue realised net of
Electricity Duty, NTI and arrears of previous years.
3.33 Accordingly, the revised AT&C loss of the Petitioner for FY 2013-14 as approved by
the Commission is summarized as follows:
Table 3.10: Trued up AT&C loss for FY 2013-14 approved by the Commission
Sl. No.
Particular Unit Now
Approved Reference
A Energy input at NDMC periphery MU 1400.12
B Units billed MU 1307.18
C Revenue Billed (excluding Electricity Duty) Rs. Crore 935.52
D Average billing rate Rs./unit 7.16 D=C/B*10
E Distribution Loss MU 92.94 E= A-B
F Distribution Loss % 6.64% F=E*100/A
G Revenue Realized (excluding Electricity Duty and other charges)
Rs. Crore 886.14
H Collection Efficiency % 94.72% H=(G/C)*100
I Energy Units Realized MU 1238.18 I=B*H
J AT&C Losses % 11.57% J={ 1-(I/A)}*100
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 39
September 2015
3.34 The AT&C loss level of 11.57% achieved is higher than the target AT&C loss level of
10.10% for the Petitioner as specified in the Tariff Order dated 13.07.2012 for FY
2013-14. As per Regulation 4.8 of the MYT Regulations, 2011,
“The Distribution Licensee will be eligible for incentive by the way of higher rate
of Return on Equity (to be considered while calculating RoCE) as shown below for
achieving lower AT&C loss level than specified in the loss reduction trajectory:
Additional Return on Equity (%) = (Xi-Yi)/Xi-1-Xi)
Where, Xi = Target AT&C loss level for ith year,
Xi-1 = Target AT&C loss level for (i-1)th year
Yi = Actual AT&C Loss level for ith year
Provided that any financial loss on account of underperformance with respect to
AT&C loss targets shall be to the Licensee’s account.”
3.35 Therefore, Distribution loss, AT&C loss and Collection efficiency calculated by the
Commission while truing up for FY 2013-14 are as follows:
Table 3.11: AT&C loss for FY 2013-14 approved by the Commission
Sl. No.
Particulars Approved in the Tariff
Order dated 31.07.2013
Petitioner’s submission
Now Approved
A AT&C Loss 10.10% 9.58% 11.57%
B Distribution Loss 10.10% 8.31% 6.64%
C Collection Efficiency 100% 98.61% 94.72%
Table 3.12: Computation of penalty due to Under Achievement in AT&C loss targets for FY 2013-14
(%)
Sl. No.
Particulars Unit
As per AT&C loss approved for FY 2013-14 in MYT Order
Now Approved
A AT&C Loss % 10.10% 11.57%
B Under achievement (A-B) %
1.47%
C Energy Input MU 1,400.12 1,400.12
D Units realised MU 1,258.71 1,238.15
E Average Billing Rate Rs/Unit 7.16 7.16
F Amount realised Rs Crore 900.83 886.12
G Financial impact on account of under achievement which has to be borne by the Petitioner
Rs Crore (14.71)
H Total revenue available towards ARR Rs Crore 900.83
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 40
September 2015
for FY 2013-14 (Excluding Electricity Tax & 8% Surcharge)
3.36 As per the AT&C loss computation shown above, the Petitioner has to bear the
amount of Rs. 14.71 Crore due to Underachievement of AT&C target.
Power Purchase Quantum
Petitioner’s Submission
3.37 Against the actual sales of 1307.23 MU during FY 2013-14, the Petitioner has claimed
a net power purchase requirement of 1489.91 MU.
3.38 The Petitioner further submitted that it has considered the Inter-State transmission
losses of 24.96 MU on Power Purchased from NTPC-Dadri and Intra-State
transmission losses of 1.17% as per SLDC for calculation of energy available at the
periphery of NDMC based on actual data for FY 2013-14 as per the following details:
Table 3.13: Power Purchase Quantum submitted by the Petitioner for FY 2013-14 (MU)
Source Approved in Tariff
Order dated 31.07.2013
Petitioner’s Submission
(Revised as per letter dated 10.4.2015)
Gross Power Purchase Quantum 2204.89 2141.19
Power Sold to Other Sources 657.63 651.28
Net Power Purchase 1547.26 1489.91
Transmission Losses
Inter-state Transmission Losses (%) 3.36% 3.36%
Inter-state Total Transmission Losses (MU) 30.71 24.96
Energy at GT Periphery 1516.55 1464.96
Intra-state Transmission Losses (%) 1.21% 1.17%
Intra-state Total Transmission Losses (MU) 18.35 17.14
Energy injected from RE source at DTL periphery
- 0.33
Energy at distribution Periphery (MU) 1498.20 1448.15
Commission’s Analysis
3.39 The Commission in its tariff order dated 31.07.2013 for FY 2013-14 had approved a
net power purchase quantum of 1547.26 MU for the Petitioner from all sources
including Central Sector Generating Stations and Delhi Generating Stations from
which power was allocated for FY 2013-14.
3.40 The Commission directed the Petitioner to submit month-wise, station-wise power
purchase details along with the bills vide letter no. F.3 (396)/Tariff-Fin/DERC/2015-
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 41
September 2015
16/4673/4844 dated 18.03.2015, which were submitted by the Petitioner vide letter
No. D-25/Dir(Power)/15 dated 10.04.2015.
3.41 However, the Commission approves the power purchase quantum based on the
information received from SLDC. For FY 2013-14, SLDC informed Power Purchase
quantum at the NDMC periphery to be at 1400.12 MU (Para 3.17), which has been
approved by the Commission.
Power Purchase Cost
Petitioner’s Submission
3.42 The Petitioner has submitted a gross power purchase cost of Rs. 926.96 Crore
including transmission charges of Rs. 73.72 Crore, in the table as follows :
Table 3.14: Power Purchase Cost for FY 2013-14 as submitted by the Petitioner*
Station
FY 2013-14
Units (MU)
Total Charges (Rs. Cr.)
Average Rate (Rs/kWh)
NTPC BTPS 635.41 293.41 4.618
NTPC-Dadri 742.71 326.85 4.40
Rajghat 0.50 0.20 4.11
GTPS 1.14 0.59 5.22
Pragati I 671.71 285.82 4.26
PPS-III (Bawana) 47.12 67.60 14.35
Solar 0.33 Total 2098.92 974.47 4.64
Short term purchase
Bilateral 12.43 5.08 4.09
Exchange Purchase - - -
Inter-DISCOM Purchase 0.74 0.45 6.09
Banking - - -
UI 29.10 1.78 0.61
Sub-total 42.27 7.31 1.73
Total purchases 2141.19 981.78 44.59
Short term sale
Bilateral Sale 7.49 0.35 0.461
Exchange Sale 626.08 135.31 2.16
Inter-DISCOM Sale 7.41 3.08 4.16
Sub-total 651.28 138.90 2.13
Transmission Charges
Inter State Transmission loss & charges 24.96 24.35 Intra State Transmission loss & charges 17.14 49.37 Total Transmission Charges 73.72
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 42
September 2015
Station
FY 2013-14
Units (MU)
Total Charges (Rs. Cr.)
Average Rate (Rs/kWh)
Rebate
Power Purchase Rebate @2% 17.41 Transmission Rebate @2% 1.50 Total Rebate 18.91 Energy at distribution Periphery including rebate
1448.15 897.69
*Revised figures as per the re-submission by NDMC vide letter dated 10.4.2015
Commission’s Analysis
3.43 The Commission in its Tariff Order dated 31.07.2013 had approved gross power
purchase cost of Rs. 978.67 Crore for FY 2013-14. Further, the Commission had
approved Inter-State Transmission charges of Rs. 18.90 Crore, Intra-State
Transmission charges including SLDC charges of Rs. 28.55 Crore, Rebate on
Transmission charges at Rs. 0.95 Crore and Power Purchase rebate at 2% of
Rs. 19.20 Crore.
3.44 The Commission had estimated revenue from sale of surplus power at Rs. 263.05
Crore and net power purchase cost (inclusive of cost for RPO obligations,
transmission charges & previous years truing up surplus) at Rs. 730.70 Crore for
FY 2013-14 vide tariff order dated 31.07.2013 (Table 49).
3.45 In paragraph 5.24 of DERC (Terms and conditions for Determination of Wheeling
Tariff and Retail Supply Tariff) Regulations, 2011 it is specified that:
“Distribution licensee shall be allowed to recover the net cost of power it
procures from sources approved by the Commission, viz. Intra-State and Inter-
State Trading Licensees, Bilateral Purchases, Bulk Suppliers, State generators,
Independent Power Producers, Central generating stations, non-conventional
energy generators, generation business of the Distribution Licensee and others,
assuming maximum normative rebate available from each source for payment
of bills through letter credit on presentation of bills for supply to consumers of
Retail Supply Business”.
3.46 The Commission on the basis of prudence check, noted that the Power Purchase
Cost from long term sources is Rs. 974.47 Crore and Transmission Charges (including
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 43
September 2015
SLDC charges) at Rs 48.41 Crore for FY 2013-14.
3.47 In the absence of actual rebate, the normative rebate to be considered at maximum
rate of 2% in the Power Purchase Cost as per the Regulation 5.24 of 2nd MYT
Regulations. The Commission has therefore considered maximum normative rebate
allowable to the Petitioner from long term power purchase and transmission
charges at the rate of 2% as follows:
Table 3.15: Computation of Normative Rebate (Rs. Crore)
Particulars Rebate
Rebate on Gross Power Purchase Cost from long term sources 19.49
Rebate on Total Transmission charges (Inter State + Intra State) (Rs. 48.41 Crore*@2%) 0.97
Total 20.46
3.48 Hence, the Commission has considered the Normative Rebate as Rs. 20.46 Crore
while computing the net Power Purchase Cost for FY 2013-14. The Petitioner is
directed to furnish the details of rebate along with supporting documents within 2
months. However, no carrying cost shall be allowed to the Petitioner on account of
revision in the amount of normative rebate, if any, from the date of this tariff order
to the date of submission of relevant documents.
3.49 The Petitioner claimed a total of Rs. 73.72 Crore as Transmission Charges consisting
of Rs. 24.35 Crore as Inter State Transmission Charges and Rs. 49.37 Crore towards
Intra State Transmission Charges (including SLDC Charges) for FY 2013-14. The
Commission officers have visited the office of the Petitioner to examine the Power
Purchase and Transmission Charges Bills for FY 2013-14 and the Petitioner submitted
Transmission Charges of observes that of Rs. 48.41 Crore comprising Rs. 24.34 Crore
towards Inter-State transmission Charges and Rs. 24.07 Crore for Intra-State
Transmission Charges including SLDC Charges. Thus, the Commission considers the
total Transmission Charges of Rs. 48.41 Crore for FY 2013-14.
3.50 The quantum of UI i.e. 57.41 MU has been considered as per the information
received from SLDC against 29.10 MU considered by the Petitioner. Further, it has
also been observed that the Petitioner has shown amount of Rs. 1.78 Crore against
UI sale of 29.10 MU at an average rate of 61 paisa per unit.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 44
September 2015
3.51 However, the Commission has considered the rate of UI at Rs. 1.08 per unit which is
the least UI rate among other three DISCOMs. Hence, the amount computed on sale
of 57.41 MU at Rs. 1.08/unit is Rs. 6.20 Crore.
3.52 Therefore the Commission approves net power purchase quantum based on SLDC
certification as per the following details:
Table 3.16: Power Purchase Quantum from long term sources for FY 2013-14 approved by the
Commission
Station
Submitted by Petitioner (as per letter dated
10.04.2015) Approved by the Commission
Quantum (MU)
Amount (Rs. Cr)
Quantum (MU)
(as per SLDC)
Amount (Rs. Crore)
Average Rate
(Rs./kWh)
Long term purchase
a. Central Generating Stations
NTPC-Dadri 742.71 326.85 742.71 326.85 4.40
b. State Generating Stations
NTPC BTPS 635.41 293.41 635.41 293.41 4.62
Rajghat 0.50 0.2 0.50 0.20 4.00
GTPS 1.14 0.59 1.14 0.59 5.18
Pragati I 671.71 285.82 671.71 285.82 4.26
PPS-III (Bawana) 47.12 67.6 47.12 67.6 14.35
Solar 0.33 0 0.33 0 0.00
Total 2098.92 974.47 2098.92 974.47 4.64
Table 3.17: Power Purchase Quantum from short term sources for FY 2013-14 approved by the
Commission
Particulars
Submitted by Petitioner*
Approved by the Commission
Quantum (MU)
Amount (Rs. Cr)
Quantum (MU)#
Amount (Rs. Crore)
Avg. Rate (Rs./kWh)
Short term purchase
Bilateral 12.43 5.08 12.9 5.08 3.94
Inter-DISCOM transfer 0.74 0.45
UI 29.10 1.78
Total 42.27 7.31 12.9 5.08 3.94 *as per letter dated 10.04.2015 #as per SLDC
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 45
September 2015
Table 3.18: Power Sales Quantum from short term sources for FY 2013-14 approved by the
Commission
Particulars
Submitted by Petitioner Approved by the Commission
Quantum (MU)
Amount (Rs. Crore)
MU Amount
(Rs. Crore) Avg. Rate (Rs./kWh)
Short term sale
Bilateral Sale 7.49 0.35 7.56 0.35 0.46
Exchange Sale 626.08 135.31 628.85* 135.31 2.15
Intra-DISCOM Sale 7.41 3.08 7.41 3.08 4.16
Banking 10.30 0.174 10.45 0.17 0.17
UI 57.41* 6.20 1.08
Total 651.28 138.90 711.68 145.11 2.04
*as per the details furnished by SLDC.
3.53 The Commission approves net power purchase cost including transmission charges
for FY 2013-14 at Rs. 862.39 Crore as per the following table:
Table 3.19: Trued-Up Power Purchase Cost for FY 2013-14 (Rs. Crore)
S. No. Source
Approved in Tariff Order
dated 31.07.2013
Petitioner’s Submission
Now Approved
Reference
A Power Purchase Cost from Long term Sources
940.57 974.47 974.47 Table 3.16
B Short term purchase 7.31 5.08 Table 3.17
C Gross Power Purchase Cost 981.78 979.55 C=A+B
D Less: Power Sold to Other Sources 257.79 138.90 145.11 Table 3.18
E Less: Power Purchase Rebate @ 2% (on Long term Sources)
13.93 17.41 19.49 Table 3.15
F Net Power Purchase Cost 825.47 814.95 F=C-D-E
G Transmission Charges including SLDC charges
48.08 73.72 48.41 Para 3.45
H Less: Transmission Charges Rebate @ 2%
0.98 1.50 0.97 Table 3.15
I Net Transmission Charges including SLDC Charges
47.10 72.22 47.44 I=G-H
J Net Power Purchase Cost including Transmission Charges
715.94 897.69 862.39 J=F+I
Review of Controllable Parameters
Petitioner’s Submission 3.54 As per Section 7.8 and Section 10.2 of the 2nd MYT Regulations, the Petitioner is
required to submit information as part of annual review on actual performance to
assess the performance vis-à-vis the targets approved by the Commission. The
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 46
September 2015
Petitioner submitted in its petition that it has restricted itself to submission of actual
expenses for FY 2013-14 for controllable factors.
Commission’s Analysis
3.55 As per Regulation 4.7 of the 2nd MYT Regulations 2011, the Commission has specified
targets for controllable parameters which inter-alia include Operation &
Maintenance expenses (comprising Employee Expenses, Repair & Maintenance
Expenses, Administrative & General Expenses and other Miscellaneous Expenses, viz.
Audit Fee, Rent, Legal Fees etc.), Return on Capital Employed and Depreciation.
3.56 Further, as per Regulation 4.21(b) of 2nd MYT Regulations 2011, for controllable
parameters, any surplus or deficit on account of O&M expenses shall be to the
account of the Licensee and shall not be trued up in the ARR and Depreciation and
RoCE shall be trued up every year based on the actual capital expenditure and
capitalization vis-à-vis capital investment plan (Capital Expenditure and
Capitalization) approved by the Commission.
3.57 The Commission has reviewed the Controllable components in the subsequent
paragraphs based on inter alia 2nd MYT Regulations. The Commission has observed
that the petition filed by the Petitioner had several discrepancies with respect to the
provisions of the 2nd MYT Regulations and the tariff order dated 31.07.2013. The
Commission issued a deficiency note to the Petitioner on 18.03.2015 highlighting the
deficiencies observed in the petition, and directed the Petitioner to submit
clarifications and/or further information. The Petitioner replied to the observations
of the Commission vide its letter dated 10.04.2015. However, the Petitioner has not
submitted scheme-wise details of capitalization and segregation of accounts based
on audited accounts for FY 2013-14 for electricity business relevant to some of the
issues mentioned in the deficiency note for the consideration of the Commission.
3.58 In consideration of the non-availability of the audited accounts for the electricity
business for the FY 2013-14, the Commission did prudence check of expenses for the
True-up of FY 2013-14.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 47
September 2015
Operation & Maintenance Expenses
Petitioner’s Submission
3.59 Operation & Maintenance (O&M) Expense is total of Expenses incurred towards
Employee, A&G and R&M Expenses. The Petitioner has claimed net O&M Expenses
of Rs. 148.12 Crore as approved in the tariff order dated 31.07.2013.
Commission’s Analysis
3.60 Regulation 4.21(b)(i) of DERC Tariff Regulations, 2011 specify “any surplus or deficit
on account of O&M expenses shall be to the account of licensee and shall not be
trued up in ARR.”
3.61 The Petitioner has erroneously considered the net O&M expenses (after efficiency
improvement) at Rs. 151.14 Crore as gross O&M expenses and adjusted for
efficiency improvement at 2% and net O&M expenses claimed at Rs. 148.12 Crore
for FY 2013-14 in true up.
3.62 Further, it has been observed by the Commission that the per unit O&M Expenses
for the Petitioner is higher than the other 3 DISCOMs which works out to Rs. 1.16 per
unit. The Petitioner has not provided any details for the high O&M expenses incurred
during FY 2013-14.
3.63 The Commission in terms of Regulation 4.21(b)(i) has considered the O&M expenses
at Rs. 151.14 Crore in true up for FY 2013-14 as approved in MYT Order dated
13.07.2012 as per the following Table:
Table 3.20: O&M Expenses approved by the Commission for FY 2013-14 (Rs. Crore)
Sl. No
Particulars
Approved in MYT Order
dated 13.07.2012
Petitioner’s Submission
(as per Petition)
Now Approved
Reference
A Employee Expenses 84.78
84.78
MYT Order dated 13.07.2012
B A&G Expenses 16.79 16.79
C R&M Expenses 54.25 54.25
D Gross O&M Expenses 155.82 151.14 155.82 D=A+B+C
E Less: Efficiency improvement factor
3.0% 2.0% 3.0% Tariff Order dated
31.07.2013
F Less: Efficiency improvement Amount
4.67 3.02 4.67 F=D*E
G Net O&M expenses 151.14 148.12 151.14 G=D - F
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 48
September 2015
Administrative and Civil Engineering Departments Expenses
Petitioner’s Submission
3.64 The Petitioner has submitted that the services of the Administration & Civil
Engineering Department are common to all the functions carried out by it and the
expenditure pertaining to these departments should be allocated to all functions of
the Petitioner.
3.65 The Petitioner has quoted the Commission’s decision in Tariff Order for FY 2005-06
which states that “……..as the exact details of the cost of the works carried out by the
Civil Engineering department for Electricity Department are not available at this
stage, the Commission, for the purpose of determination of ARR for FY 2005-06 has
considered a lump-sum amount of Rs.10.00 Crore on provisional basis towards this
expenditure. The Commission will consider the actual cost of works carried out by
Civil Engineering Department for electricity appropriately during the truing up
process at the end of the year…..”. Since the Petitioner is yet to segregate the
expenses shared by its Civil Engineering Department on account of electricity
distribution business, it has requested the Commission to consider an amount of Rs.
10.00 Crore under this head, which it claims is the same as approved in the Tariff
Order for FY 2005-06 as well as in the MYT Order.
3.66 Further, in respect of Administrative Department expenses, the Petitioner has
quoted the decision of the Commission in Tariff Order for FY 2005-06 which states
that “……thus, while 19% of total administrative department expenses have been
considered to be allocated to electricity department, an amount…...”.
3.67 Accordingly, the Petitioner has requested the Commission to approve the actual
Administrative and Civil Engineering Department Expenses of Rs. 143.54 Crore for FY
2013-14 for the electricity business as per the following Table:
Table 3.21: Administrative & Civil Engineering Expenses projected by the Petitioner (Rs. Crore)
SI. No.
Particulars Approved in the
tariff order dated 31.07.2013
Petitioner’s submission
1 General Administration expenses as per NDMC Budget
186.16 143.54
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 49
September 2015
SI. No.
Particulars Approved in the
tariff order dated 31.07.2013
Petitioner’s submission
2 Allocation of admin related expenses to electricity Supply Business of NDMC @19%
35.37 -
3 Cost of Civil Engineering Department 10.00 -
4 Total (2+3) 45.37 143.54
Commission’s Analysis
3.68 The Petitioner has furnished neither the information in respect of General
Administrative Expenses nor audited accounts for FY 2013-14 for claiming Rs. 143.54
Crore, being 19% of the amount as the allocation for Administrative and Civil
Engineering Expenses purported to be spent by the Petitioner.
3.69 In this regard, the Commission had directed vide Para 4.62 of tariff order dated
31.07.2013 to the Petitioner to separately book the cost of works carried out by Civil
Engineering Department for Electricity Department and provide the complete details
of such works and associated costs at the end of the year bringing out clearly the
percentage expenditure of Civil Engineering Department booked to Electricity
Department vis-à-vis other departments. However, the Petitioner has not complied
with this directive.
3.70 Further, as discussed earlier, the per unit rate of O&M Expenses of the Petitioner is
highest among all the DISCOMs. The Commission is of the view that since the
segregated audited accounts of electricity business of the Petitioner are not
available, the exact details of the cost of works carried out by the Civil Engineering
Department and Administrative Department for electricity business cannot be
identified.
3.71 In view of the above, the Commission has decided to disallow the Administrative and
Civil Engg. Department Expenses for FY 2013-14.
Capital Expenditure & Capitalization
Petitioner’s Submission
3.72 The Petitioner has submitted capital expenditure of Rs. 9.56 Crore and capitalization
of Rs. 9.56 Crore in the truing up for FY 2013-14. The Petitioner has furnished the
Opening Gross Fixed Assets (GFA), opening Capital Works in progress (CWIP), Capital
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 50
September 2015
Expenditure during the year and closing capital work in progress and closing fixed
assets for FY 2013-14 on actual basis as per the following Table:
Table 3.22: CWIP and capitalization proposed by Petitioner for FY 2013-14 (Rs. Crore)
Particulars Approved in the
tariff order dated 31.07.2013
Petitioner’s submission
Opening GFA 1086.94 1086.94
Addition during the year 31.64 9.56
Closing GFA 1118.58 1096.50
Opening CWIP 39.30 -
Add: Capital expenditure during the year 17.68 -
Less: Capitalization 31.64 -
Closing CWIP 25.34 -
Commission’s Analysis
3.73 As detailed in Para 3.9, the Commission has decided to discard previous provisional
GFA and adopt revised provisional GFA for FY 2013-14. The Petitioner has not
submitted the audited financial statement and detailed information regarding
capitalisation including consumer contribution. Therefore, the Commission has
considered the maximum ceiling for GFA addition during each year at Rs. 20 Crore
and the amount of capitalisation submitted by the Petitioner. The impact on account
of consumer contribution shall be considered based on the actual data to be
submitted by the Petitioner in the subsequent years for true up of ARR. Accordingly,
closing GFA worked out for FY 2013-14 is as follows:
Table 3.23: Addition during the year approved for FY 2013-14 (Rs. Crore)
Sl. No. Particulars FY 2013-14 Remarks
A Opening GFA 463.14 Table 3.1
B Addition during the year without approval of the Commission
9.56 As per petition
C Closing GFA 472.70 A+B
D Average GFA 467.92 (A+C)/2
Depreciation
Petitioner’s Submission
3.74 The Petitioner has submitted that depreciation is charged on straight-line method on
average GFA at the beginning and at the end of FY 2013-14. The rate of depreciation
is adopted as approved by the Commission in the MYT Order. As per the
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 51
September 2015
methodology adopted by the Commission, depreciation has been computed at
3.60% of average GFA of FY 2013-14 by the Petitioner as per the following Table:
Table 3.24: Depreciation submitted by the Petitioner for FY 2013-14 (Rs. Crore)
Particulars Approved in 2nd
MYT Order Petitioner’s submission
Opening Assets 1086.94 1086.94
Additions during the year 31.64 9.56
Closing Assets 1118.58 1096.50
Average assets 1102.76 1091.72
Average Depreciation rate as above 3.60% 3.60%
Depreciation 39.70 39.10
Commissions Analysis
3.75 As per Regulation 4.21 (b)(ii) of the 2nd MYT Regulations, Depreciation and Return on
Capital Employed shall be trued up every year based on the Capital Expenditure and
Actual Capitalisation vis-à-vis Capital Investment plan (Capital Expenditure and
Capitalisation) approved by the Commission.
3.76 The Regulation 5.16 of the 2nd MYT Regulations, specify that “…… Provided that
depreciation shall not be allowed on assets funded by consumer contribution and
capital subsidy/ grant”.
3.77 The Commission has considered rate of depreciation @ 3.60% for FY 2013-14.
Hence, in view of the prudence check, the Commission approves Depreciation for FY
2013-14 as follows:
Table 3.25: Approved Depreciation for FY 2013-14 (Rs. Crore)
Sl. No. Particulars FY 2013-14 Remarks
A Average GFA 467.92 Table 3.23
B Rate of depreciation 3.60%
C Depreciation 16.85 A*B
Working Capital
Petitioner’s Submission
3.78 The Petitioner has submitted that working capital requirement is calculated as per
the norms specified for determining working capital requirement in 2nd MYT
Regulations. The Petitioner has computed working capital requirement for FY 2013-
14 as per the following Table:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 52
September 2015
Table 3.26: Working capital requirement projected by the Petitioner for FY 2013-14 (Rs. Crore)
Particulars Tariff Order
dated 31.07.2013
Petitioner’s projections
Receivables from sale of electricity 935.52
Receivables equivalent to 2 months 155.92
Power purchases 926.96
Less: 1/12th of Power purchases including transmission charges 77.25
Total working capital 113.83 78.67
Less: Opening WC 105.27 101.59
Change in working capital 8.56 (22.92)
Commission’s Analysis
3.79 The Commission has determined the change in working capital for FY 2013-14 as
follows:
Table 3.27: Change in Working Capital approved by Commission for FY 2013-14 (Rs. Crore)
Review of Regulated Rate Base and Return on Capital Employed
3.80 As per Regulation 4.7 of the 2nd MYT Regulations, Return on Capital Employed (RoCE)
is based on Regulated Rate Base (RRB) and is a controllable parameter, for which the
Commission has set targets for each year of the Control Period. Further, as per
Regulations 4.17 and 4.21(b)(ii) of the MYT Regulations 2011, adjustment to
Sl. No.
Particulars
Approved in MYT order
dated 13.07.2012
Petitioner’s submission
(as per petition)
Now Approved
Remarks
A Revenue Receivable from sale of electricity
1055.98 935.52 935.52
B Receivables equivalent to 2 months
176.00 155.92 155.92 B=A/6
C Net Power purchase Cost including Transmission and SLDC charges
749.20 926.96 862.39 Table 3.16
D Net Power purchase Cost for One month
62.43 77.25 71.87 D=C/12
E Total working capital 113.56 78.67 84.05 E=B-D
F Less: Opening Working Capital 105.26 101.59 85.05 Closing of
FY 2012-13
G Change in working capital 8.30 (22.92) (1.00) G=F-E
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 53
September 2015
Depreciation and RoCE for the actual investment vis-à-vis approved Capital
Investment shall be done at the end of the Control Period.
3.81 The Commission had approved an amount of Rs. 102.82 Crore towards RoCE in the
tariff order dated 31.07.2013 for FY 2013-14. However, the Petitioner has claimed
Rs. 95.64 Crore towards RoCE and Rs. 4.61 Crore on account of reduction in AT&C
loss, amounting to Rs. 100.25 Crore for FY 2013-14 in its True-up Petition.
3.82 Working Capital requirement has changed due to annual truing up of uncontrollable
expenses as compared to the expenses approved in the MYT order dated
13.07.2012. The Commission therefore uses Working Capital figures calculated as
per Table 3.24 of this order.
3.83 Accordingly, RRB computed in accordance with the provisions of the 2nd MYT
Regulations is as follows:
Table 3.28: RRB approved for True Up for FY 2013-14 (Rs. Crore)
Sl. No.
Particulars
Approved in MYT Order
dated 13.07.2012
Petitioner’s Submission
Now Approved
Remarks
A Original Cost of Fixed Assets 1086.94 1086.94 463.14
B Opening Working Capital 105.26 101.59 85.05
C Accumulated Depreciation 396.58 399.77 337.84
D Accumulated Consumer Contribution
- 2.63 2.63
E Regulated Rate Base (RRB) (Opening)
795.62 786.13 207.72 E=A+B-C-D
F Capitalisation allowed during the Year
31.64 9.56 9.56 Table 3.23
G Depreciation 39.70 39.10 16.85 Table 3.25
H Consumer Contribution - 8.34
I Change in Working Capital 8.30 (22.92) (1.00) Table 3.27
J RRB (Closing) 795.86 725.33 201.44 J=E+F-G-H-I
K Change in RRB (∆ RB) (8.06) (41.86) (4.64) (F-G-H)/2+I
L Regulated Rate Base (RRB)(i) 799.89 744.27 203.09 L=E+K
3.84 Prior to tariff order dated 31.07.2013, RoCE was calculated on average Regulated
Rate Base (RRB) assumed to be funded through 100% debt. As per the MYT
regulations 2011, RoCE is a controllable parameter which will be Trued-up at the end
of the Control Period. The Commission has changed the system of calculating RoCE
from the Tariff order dated 31.07.2013 onwards. Normative 70:30 Debt-Equity is
considered, as NDMC has funded the Capital Expenditure through internal sources.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 54
September 2015
The actual scheme wise funding details, Equity, Loans, Grants and Consumer
Contribution are not made available by NDMC. Thus, the Commission has computed
the RoCE as shown in table 3.29.
3.85 Regulation 4.21 of the 2nd MYT Regulations, states that “the Commission shall not
true up the interest rate, if variation in State Bank of India Base Rate as on April 1,
2012, is within ±1% during the Control Period. Any increase/decrease in State Bank of
India Base Rate beyond ± 1% only shall be trued up.” Since Base rate of SBI as on
01.04.2013 was 9.70% and remained within the range of 1% during FY 2013-14 i.e. @
9.70% from 01.04.2013 to 18.09.2013, @ 9.80% during 19.09.2013 to 06.11.2013
and @ 10.00% from 07.11.2013 to 31.03.2014, the Commission has not trued up the
interest rate.
3.86 Accordingly, RoCE calculation for FY 2013-14 for Petitioner is as follows:
Table 3.29: RoCE approved for True Up for FY 2013-14 (Rs. Crore)
Sl. No.
Particulars
Approved in MYT order
dated 13.07.2012
Petitioner’s Submission
Now Approved
Remarks
A Regulated Rate Base (RRB) 799.89 744.27 203.09 Table 3.28
B Equity 276.46 223.28 60.93 B= A*30%
C Debt 645.08 520.99 142.16 C= A*70%
D Rate of return on Equity 16.00% 16.00% 16.00% -
E Rate of Return on Debt 11.50% 11.50% 11.50% -
F Weighted Average Cost of Capital (WACC)
11.50% 12.85% 12.85% F=
(D*30%+E*70%)
G Return on Capital Employed (RoCE)
91.99 95.64 26.10 G= A*F
Non Tariff Income
Petitioner’s Submission
3.87 The Petitioner in its True up Petition has considered Non-Tariff Income of Rs. 6.89
Crore for FY 2013-14 against the amount of Rs. 21.41 Crore approved for FY 2013-14
in the tariff order dated 31.07.2013 as per the following Table:
Table 3.30: Non tariff income projected by the Petitioner for FY 2013-14 (Rs. Crore)
SI. No
Particulars Approved in tariff
order dated 31.07.2013
Petitioner’s submission
1 Late Payment charges 1.18
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 55
September 2015
SI. No
Particulars Approved in tariff
order dated 31.07.2013
Petitioner’s submission
2 MDI 0.61
3 Misuse 4.21
4 New connection/re-connection fees 0.00
5 Meter testing charges 0.00
6 Meter Rent 0.00
7 Service Administrative charges
8 Sale & Hire charges
9 Burnt Meter 0.05
10 Recovery of Deposit Work
11 Other income from lapsed deposit and other receipts 0.34
12 Other receipts (petty commercial items) 0.50
13 Total : Non Tariff Income 21.41 6.89
Commission’s Analysis
3.88 The Regulation 5.36 of the 2nd MYT Regulations states that “the amount received by
the licensee on account of Non Tariff Income shall be deducted from the Aggregate
Revenue Requirement in calculating the net revenue requirement of such licensee”.
3.89 As per Regulation 5.24 of the 2nd MYT Regulations, the distribution licensee shall be
allowed to recover the net cost of power and transmission assuming maximum
normative rebate available from each source for payment of bills through Letter of
Credit (LC) on presentation of bills for supply to consumers of Retail Supply Business.
The Petitioner has not offered any income on account of Rebate earned on payment
of power purchase and transmission charges bills.
3.90 As per the 2nd MYT Regulations, only two sets of parameters are recognized i.e.
controllable and uncontrollable. The uncontrollable parameters include revenue/
expenditure on account of sales and power purchase and the MYT Regulations
provide for their annual True Up. On the other hand, the controllable parameters
include O&M expense, Capex related expenses and RoCE, but does not specifically
include Non Tariff Income. The MYT Regulations specifically provide for True Up of
controllable expenses of Capex related expenditure i.e. RoCE and Depreciation every
year. The Non-tariff Income is influenced by various factors and is uncontrollable
parameter even though the Regulations are silent and hence shall be trued up based
on the actual Non-Tariff Income every year.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 56
September 2015
3.91 Further, the arrear amount of Rs. 15.49 Crore collected during FY 2013-14 has been
treated as Non Tariff Income for FY 2013-14.
3.92 Accordingly, the Commission has approved the amount of Non Tariff Income as per
the submissions made by the Petitioner for FY 2013-14 as follows:
Table 3.31: Trued-up Non Tariff Income approved for FY 2013-14 (Rs. Crore)
Renewable Purchase Obligations
Commission’s Analysis
3.93 The year wise targets for the licensees as per the per DERC (Renewable Purchase
Obligation and Renewable Energy Certificate Framework Implementation)
Regulations, 2012 (RPO Regulations, 2012) issued on 01.10.2012 and achievement
reported by the Petitioner are as follows:
Table 3.32: Targets & Achievements for Renewable Purchase Obligations and REC
Defined minimum quantum of Purchase (in percentage) from
Renewable Energy Sources (in terms of energy equivalent in
kWh) of Total Consumption in year
Achievement
reported by the
Petitioner
Year Solar Total
2012-13 0.15% 3.40% Nil
2013-14 0.20% 4.80% 0.02% (Solar)
2015-16 0.25% 6.20% -
2015-16 0.30% 7.60% -
2016-17 0.35% 9.00% -
3.94 The Petitioner submitted vide its letter No.232/Dir(Power)/14 dated 11.7.2014 that
“NDMC have entered into PPA between Ministry of Environment and NDMC for
930 kWP solar power project at roof top of Indira Paryavaran Bhavan at Aligung,
Jorbagh for a period of 25 years and procurement of 6.5 MW green power from
Timarpur Okhla Waste Management Company Pvt. Limited through Mittal
Processor Private Limited for the period from 19th May 2014 to 30th September
2014 on RTC basis. Therefore, NDMC would like to request the Hon’ble
Particulars Approved in MYT order
dated 13.07.2012 Petitioner
submission Now Approved
Non Tariff Income 21.41 6.89 22.38
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 57
September 2015
Commission to carry forward the RPO compliance requirement of NDMC for
FY 2013-14 and FY 2013-14 to FY 2015-16 based on these agreements”.
3.95 During the year, the energy sales are at 1307.18 MU and the Solar purchases shall be
at 2.61 MU (0.2% of total sales) and the non solar purchase shall be at 60.13 MU
(4.60% of the total sales). The Commission has observed that the Petitioner has
bought only 0.33 MU of solar and no quantum of non solar purchase. Hence, there is
a shortfall of 62.41 MU (Solar – 2.28 MU and Non solar – 60.13 MU). Accordingly, the
REC to be purchased as per the DERC RPO Regulations is worked out as shown in the
table below:
Table 3.33: Cost of RE Certificates (Rs. Crore)
Particulars Floor Price Amount
Solar – 2.28 MU Rs. 3500/MWh Rs. 0.80 Crore
Non-Solar- 60.13 MU Rs.1500/MWh Rs. 9.02 Crore
Total- 62.41 MU Rs. 9.82 Crore
3.96 BRPL & BYPL has requested reconsideration of compliance of RPO for FY 2012-13 and
FY 2013-14 in Petition No. 30 & 31 of 2015. The Commission will decide regarding
levy of penalty, if any, for non-compliance of RPO in the final Order of the Petition
No. 30 & 31 of 2015. The impact as per the Order in the said petition shall be
considered in the subsequent Tariff Order and the same will be applicable for the
Petitioner as well.
Aggregate Revenue Requirement
Commission’s Analysis
3.97 The Commission, based on detailed analysis of cost parameters detailed in the above
paragraphs, approves the Annual Revenue Requirement (ARR) in true up for FY 2013-
14 as given in the table below:
Table 3.34: Aggregate Revenue Requirement now approved for FY 2013-14 (Rs. Crore)
Sl. No.
Particulars Approved in MYT
Order dated 13.07.2012
Petitioner’s Submission
Now Approved
Remarks
A Net Power Purchase Cost 658.28
897.69 862.39 Table 3.19 B Inter –State Transmission Charges 22.10
C Intra-State Transmission Charges 68.82
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 58
September 2015
Revenue available towards ARR
Petitioner’s submission
3.98 The Petitioner has submitted that based on the tariff rates approved by the
Commission and the monthly consumption, it has raised bills of Rs. 935.52 Crore to
its consumers against energy and demand charges. The total revenue realized from
consumers in FY 2013-14 is submitted to be Rs. 886.12 Crore after deducting the
Electricity Duty, arrears of previous years and NTI.
Commission’s Analysis
3.99 The total amount collected as approved by the Commission is Rs. 886.12 Crore.
Therefore, Commission has computed the total revenue of the Petitioner available
towards ARR to be Rs. 886.12 Crore. However, due to the impact of Rs.14.71 Crore
on account of underachievement by the Petitioner, the amount to be taken as
revenue available towards ARR for FY 2013-14 900.83 Crore.
Revenue (Gap)/ Surplus
3.100 The revenue surplus/(gap) for FY 2013-14 as approved in the MYT Order dated
31.07.2013, submitted by the Petitioner and Trued up by the Commission is
summarised as follows:
Table 3.35: Revenue Surplus/ (Gap) for FY 2013-14 (Rs Crore)
Sl. No.
Particulars Approved in Tariff
Order dated 31.07.2013
Petitioner’s Submission
Now Approved
Reference
A ARR for FY 2013-14 1048.31 1342.27 1034.09 Table 3.34
B Revenue available towards ARR
957.19 918.92 900.83 Table 3.12
(including SLDC charges)
D Operations & Maintenance Cost 151.14 148.12 151.14 Table 3.20
E Administrative & Civil Engineering Department Expenses allocated to electricity business
45.37 143.54 - Para 3.70
F Depreciation 39.70 39.10 16.85 Table 3.25
G Income Tax 0.00 20.46 - -
H Return on Capital Employed (RoCE) 91.99 100.25 26.10 Table 3.29
I Less: Non Tariff Income 21.41 6.89 22.38 Table 3.31
K Aggregate Revenue Requirement 1055.98 1342.27 1034.09 Sum (A to H) – I
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 59
September 2015
Sl. No.
Particulars Approved in Tariff
Order dated 31.07.2013
Petitioner’s Submission
Now Approved
Reference
C Surplus/ (Gap) 91.12 (423.35) (133.26) B-A
Net (Gap)/Surplus at the end of FY 2013-14
3.101 The net (gap)/surplus at the end of FY 2013-14 that is available with the Petitioner is
as follows:
Table 3.36: Net Revenue Surplus/ (Gap) at the end of FY 2013-14 (Rs Crore)
Sl. No. Particulars FY 2013-14
A Opening Revenue Surplus/(Gap) 165.19
1 Annual Revenue Requirement for the year 1,034.09
2 Revenue for the year 900.83
3 Revised Revenue Surplus/(Gap) (133.26)
4 Closing Revenue Surplus/(Gap) 31.94
6 Average gap 98.56
7 Rate of Carrying Cost 12.85%
8 Amount of Carrying Cost 12.67
B Closing Revenue Surplus/(Gap) 44.60
3.102 Hence, the closing revenue surplus at the end of FY 2013-14 is Rs. 44.60 Crore as
shown in the table above.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 60
September 2015
A4: Analysis of Aggregate Revenue Requirement (ARR) for FY 2015-16
Introduction
4.1 The Petitioner has filed the petition for determination of Aggregate Revenue
Requirement (ARR) for FY 2015-16. The Commission has analysed the petition
submitted by the Petitioner for ARR for FY 2015-16 as required under the Delhi
Electricity Regulatory Commission (Terms and Conditions for Determination of
Wheeling Tariff and Retail Supply Tariff) Regulations, 2011 (hereinafter referred to as
DERC Regulations, 2011) extended for another year up to FY 2015-16.
4.2 In the process of ARR determination, the Commission held several technical
discussions to validate the information submitted by the Petitioner and wherever
required, sought clarification on various issues. The Commission has considered all
information submitted by the Petitioner as part of tariff petition, response to queries
raised during discussions and also during the public hearing for determination of ARR
and Tariff FY 2015-16.
4.3 This chapter contains detailed analysis of the petition submitted by the Petitioner for
determination of ARR for FY 2015-16.
Energy Sales
Petitioner’s Submission
4.4 The Petitioner has submitted that the energy sales for the FY 2015-16 have been
projected at 3 year CAGR for different consumer categories. For the year 2015-
16 the energy sales in the licensed area have been projected at 1375.19 MU and
the Petitioner has requested the Commission to approve the same in Order to
provide reliable and quality power to key installations in the licensee area.
4.5 The category-wise sales from FY 2008-09 to FY 2013-14, estimated category wise
sales for FY 2014-15 and the category wise sales projected for FY 2015-16 are as
indicated in the Table below:
Table 4.1: Sales for FY 2015-16 submitted by the Petitioner (MU)
Sl. No.
Category FY
2008-09 FY
2009-10 FY
2010-11 FY
2011-12 FY
2012-13 FY
2013-14
FY 2014-15
(Est.)
3 year CAGR
FY 2015-16 (Proj.)
1 Domestic 208.98 223.41 239.13 243.89 259.01 251.62 265.43 1.71% 269.97
2 Non-Domestic
839.92 902.09 944.41 961.47 975.50 1001.11 1025.67 1.96% 1045.80
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 61
September 2015
Sl. No.
Category FY
2008-09 FY
2009-10 FY
2010-11 FY
2011-12 FY
2012-13 FY
2013-14
FY 2014-15
(Est.)
3 year CAGR
FY 2015-16 (Proj.)
3 SIP 0.27 0.35 0.32 0.31 0.26 0.21 0.21 -13.10% 0.18
4 Public Lighting
8.73 9.19 8.37 12.95 8.21 8.32 8.32 -0.20% 8.30
5 DMRC 0.00 0.00 0.00 20.23 38.70 36.23 18.00 - 41.10
6 Others 6.50 7.08 9.50 7.69 9.53 9.74 9.75 0.84% 9.83
Total 1064.40 1142.12 1201.73 1246.55 1291.25 1307.23 1337.15 2.84% 1375.19
4.6 The Petitioner has not provided the details of the number of consumers and
sanctioned load (kW) details in their petition for FY 2015-16.
Commission’s analysis
4.7 The Commission has sought the actual sales for FY 2014-15 vide email dated
22.04.2015 and the Petitioner has submitted the same vide email dated 23.04.2015.
4.8 The actual category wise sales for FY 2008-09 to FY 2014-15 submitted by the
Petitioner are shown in the Table as follows:
Table 4.2: Energy sales from FY 2008-09 to FY 2014-15 (MU)
Sl. No.
Category FY
2008-09 FY
2009-10 FY
2010-11 FY
2011-12 FY
2012-13 FY
2013-14 FY
2014-15$
1 Domestic 208.98 223.41 239.13 243.89 259.01 251.61 251.60
2 Non-Domestic 250.81 249.63 250.84 247.70 253.99 239.37 247.56
3 Mixed Load 589.10 652.45 693.58 713.78 721.51 751.95 757.47
Sub-total (2+3) 839.91 902.08 944.42 961.48 975.50 991.32 1005.03
4 Industrial (SIP) 0.27 0.35 0.32 0.31 0.26 0.21 0.05
5 Public Lighting 8.73 9.19 8.37 12.95 8.21 8.32 8.08
6 DMRC 0.00 0.00 0.00 20.23 38.70 36.23 29.84
7 Others* 6.50 7.08 9.50 7.69 9.57 19.49 18.25
Total 1064.39 1142.11 1201.74 1246.55 1291.25 1307.18 1312.84 *Others include temporary supply, advertisement & hoardings etc. $ As per Form 2.1a submitted by the Petitioner for FY 2014-15
4.9 The various years CAGR (1 year to 6 years) with respect to FY 2014-15 are as per the
following Table:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 62
September 2015
Table 4.3: CAGR from FY 2008-09 to FY 2014-15 (%)
Sl. No.
Particulars
6 year CAGR
FY 14-15 to
FY 08-09
5 year CAGR
FY 14-15 to
FY 09-10
4 year CAGR
FY 14-15 to
FY 10-11
3 year CAGR
FY 14-15 to
FY 11-12
2 year CAGR
FY 14-15 to
FY 12-13
1 year CAGR
FY 14-15 to
FY 13-14
1 Domestic 3.14% 2.41% 1.28% 1.04% -1.44% 0.00%
2 Non-Domestic -0.22% -0.17% -0.33% -0.02% -1.27% 3.42%
3 Mixed Load 4.28% 3.03% 2.23% 2.00% 2.46% 0.73%
CAGR of Sub-Total 3.04% 2.18% 1.57% 1.49% 1.50% 1.38%
4 Industrial (SIP) -24.76% -32.51% -37.45% -45.93% -56.18% -76.33%
5 Public Lighting -1.29% -2.55% -0.88% -14.56% -0.82% -2.90%
6 DMRC 0.00% 0.00% 0.00% 13.83% -12.20% -17.65%
7 Others 18.78% 20.85% 17.73% 33.39% 38.07% -6.36%
4.10 The Commission has considered the number of consumers and sanctioned load of
the Petitioner as per the details of Form 2.1 (a) of FY 2014-15 submitted by the
Petitioner as follows:
Table 4.4: No. of Consumers and Connected Load (kW) for FY 2015-16 as submitted by the Petitioner
SI. No.
Category No. of
Consumers Sanctioned Load (kW)
1 Domestic 53130 159123
2 Non-Domestic 22853 499590
3 Mixed Load (NDHT) 446 230996
3 Small Industry Power 11 145
4 Public Lighting 75 1654
5 DMRC 2 20963
6 Others 1806 -
Total 77877 681475
Estimated Sales for FY 2015-16
4.11 For projecting the sales, the Commission has adopted an Adjusted Trend Analysis
method of demand forecasting for FY 2015-16 which assumes that the underlying
factors which drive the demand for electricity are expected to follow the same trend
as in the past. The forecast is also based on the assumption that the past
consumption trend will continue in future.
4.11 The trend based approach has to be adjusted based on judgment of the
characteristics of the specific consumer categories.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 63
September 2015
4.12 The strength of the method, when used with balanced judgment lies in its ability to
reflect recent changes and therefore, probably best suited as a basis for a short term
projections as used for the ARR/Tariff in the context of ARR determination.
4.13 The category-wise sales forecast for FY 2015-16 is discussed as follows:
Domestic Consumers
4.14 The consumption of energy by Domestic consumer’s category constitutes to about
19% of total sales in FY 2014-15. The Petitioner has projected Domestic sales of
269.97 MU for FY 2015-16 considering 3 Year CAGR of 1.71% (FY 2010-11 to FY 2013-
14) against the estimated sales of 265.43 MU for FY 2014-15. The Commission
considers the growth rate of 3.14% i.e. 6 year CAGR (FY 2008-09 to FY 2014-15) on
the actual sales of FY 2014-15 (i.e. 251.60 MU) for projecting sales in FY 2015-16.
Thus, the Commission approves the sales of 259.50 MU for FY 2015-16 for Domestic
consumer’s category.
Non-Domestic Consumers
4.15 In the present petition, the mixed load consumers are clubbed into Non-Domestic
consumers and the total sales are considered under Non-Domestic category. The
Petitioner has projected sales of 1045.80 MU for FY 2015-16 considering 3 Year
CAGR of 1.96% (FY 2010-11 to FY 2013-14) against the estimated sales of 1025.67
MU for FY 2014-15.
The sales to Non-Domestic consumer’s category alone constitutes to about 19% of
total sales in FY 2014-15. The sale for this category has shown negative growth in the
past. However, 1 year CAGR (FY 2013-14 to FY 2014-15) shows a growth of 3.42%.
The sale during FY 2014-15 is at 247.56 MU. Thus, the Commission approves the
sales of 256.03 MU considering 1 year CAGR of 3.42% for FY 2015-16 for Non-
Domestic consumer’s category.
Mixed Load Consumers
4.16 The consumption of energy by Mixed Load category constitutes to about 58% of total
sales in FY 2014-15. The Commission considers the growth rate of 4.28% i.e. 6 year
CAGR (FY 2008-09 to FY 2014-15) on the actual sales of FY 2014-15 (i.e. 757.47 MU)
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 64
September 2015
for projecting sales in FY 2015-16. Thus, the Commission approves the sale of 789.88
MU for FY 2015-16 for mixed load consumer’s category.
Small Industrial Power
4.17 The consumption of energy by small industrial power category was only 0.05 MU in
FY 2014-15, where as the sales are 0.26 MU in FY 2012-13 and 0.21 MU in FY 2013-
14. The maximum and minimum sales during the period FY 2008-09 to FY 2013-14
were 0.35 MU and 0.21 MU respectively. Thus, the Commission approves 0.21 MU
sales to Small Industrial Power for FY 2015-16 at the same level of actual sales of
FY 2013-14.
Public Lighting
4.18 The consumption of energy by Public Lighting constitutes less than 1% of total sales
in FY 2014-15 at 8.08 MU. It is observed that CAGR varies from 0.82% (FY 2007-08 to
FY 2014-15) to (-)14.56% (FY 2011-12 to FY 2014-15). It has been further observed
that the actual sales in this category for FY 2013-14 is 8.32 MU and for FY 2014-15 is
8.08 MU, which is almost constant. Thus, the Commission approves 8.08 MU sales to
Public Lighting for FY 2015-16 at the same level of actual sales of FY 2014-15.
Delhi Metro Rail Corporation (DMRC)
4.19 The consumption of energy by DMRC constitutes about 2.27% of total sales in
FY 2014-15. The Petitioner has projected the sales at 41.10 MU for FY 2015-16.
The Commission inquired from DMRC about its projected quantum of sales in the
Petitioner’s area of supply. DMRC vide its letter No. DMRC/O&M/Tr./VK/T-4/DERC
dated 22.04.2015 has intimated the projected purchase of 33 MU during FY 2015-16
from NDMC. Thus, the Commission has considered the quantum of sale at 33 MU for
NDMC as projected by DMRC for FY 2015-16.
Other Categories
4.20 Other categories consist of enforcement, temporary connections etc. The Petitioner
has projected the sale of 9.83 MU for FY 2015-16. The sale to this category during
FY 2014-15 was 18.25 MU and the sales in FY 2012-13 and FY 2013-14 was 9.57 MU
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 65
September 2015
and 9.74 MU respectively. The sales recorded during FY 2014-15 at 18.25 MU may
not sustain in future. The nature of sale in this category may not follow the past
CAGR trends in future. Thus, the Commission has considered the quantum of sales to
such other categories at 19.49 MU as actual of FY 2013-14.
Approved Sales for FY 2015-16
4.21 The energy sales for FY 2015-16 as approved by the Commission are as shown in the
following Table:
Table 4.5: Category-wise Energy Sales approved by the Commission for FY 2015-16 (MU)
Sl. No.
Category Petitioner’s Submission
Approved for FY 2015-16
Reference
1 Domestic 269.97 259.50 Para 4.14
2 Non-Domestic 1045.80
256.03 Para 4.15
3 Mixed Load 789.88 Para 4.16
4 Small Industrial Power 0.18 0.21 Para 4.17
5 Public Lighting 8.32 8.08 Para 4.18
6 DMRC 41.10 33.00 Para 4.19
7 Others 9.83 19.49 Para 4.20
Total 1375.19 1366. 19 Sum (1 to 7)
Revenue in FY 2015-16 at Existing Tariff
Petitioner’s Submission
4.23 The Petitioner has projected the revenue billed at Rs 977.96 Crore for FY 2015-16 at
existing tariff on the projected quantum of sales of 1375.19 MU.
Commission’s Analysis
4.24 As per two-part tariff principle followed in the NCT of Delhi, the tariff for each
category consists of fixed charges as well as Energy Charges. The fixed charges are
specified for different categories as a fixed amount per month, or as a fixed amount
per kW of connected load per month. The Energy Charges on the other hand are
always usage-based and are specified per unit of electricity consumed.
4.25 The Power Factor considered by the Commission for different categories is as
follows:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 66
September 2015
Table 4.6: Power Factor considered by the Commission for FY 2015-16
Sl. No. Consumer Slab Power Factor
1 Non Domestic Low Tension (NDLT)
A Up to 10 kW 0.89
B 10-100 kW 0.93
C Above 100 kW 0.93
2 Non Domestic High Tension (NDHT) 0.95
3 Small Industrial Power (SIP)
A 10-100 kW 0.91
B Above 100 kW 0.93
4 DMRC 1.00
4.26 Hence, taking into account the sales, number of consumers and sanctioned load
approved for each tariff category for FY 2015-16 and the connected load for each
slabs, the Commission has projected revenue to be billed by the Petitioner in
FY 2015-16 at Rs. 1080.18 Crore. Since the Collection Efficiency for FY 2015-16 was
approved at 100% in the MYT Order dated 13.07.2012, the revenue realized in FY
2015-16 is projected to be equal to the amount of revenue billed i.e., Rs. 1080.18
Crore. This amount is excluding Electricity Duty.
4.27 It is observed that the past revenue gap of Rs. 324.08 Crore up to FY 2012-13 as
approved in T.O. dated 13.07.2014, has been liquidated in current truing up exercise
as discussed in past period truing up in chapter 3 of this order. The Commission is of
the view that 8% additional surcharge which had been introduced in case of the
Petitioner for gradual liquidation of the principle of the revenue, should be
withdrawn. Therefore, the revenue realised by the Petitioner through 8% additional
surcharge on existing tariff collected by the Petitioner from April'15 to September'15
has been considered against the ARR of FY 2015-16 which amounts to Rs. 43.21
Crore. Hence, the total revenue computed is Rs. 1123.39 Crore. The category wise
estimated revenue for FY 2015-16 is shown in the Table below:
Table 4.7: Revenue estimated by the Commission for FY 2015-16 at the existing tariff
(Rs. Crore) Sl. No. Category Fixed Charges Energy Charges Total Revenue
1 Domestic 3.82 143.34 147.16 2 Non-Domestic 66.81 816.83 883.64
3 Small Industry Power 0.01 0.16 0.17
4 Public Lighting 5.90 5.90
5 DMRC 3.14 20.13 23.27 6 Others
20.03 20.03
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 67
September 2015
Sl. No. Category Fixed Charges Energy Charges Total Revenue
Total 73.79 1006.39 1080.18
7 Estimated Revenue collected due to 8% surcharge for 6 months (Apr’15 to Sep’15)
43.21
8 Total Revenue 1123.39
AT&C Losses
Petitioner’s submission
4.27 The Petitioner has projected the transmission and distribution losses for FY 2015-16
at the same level as the actual T&D loss for FY 2013-14. Further, the Petitioner has
projected the collection efficiency at 100% as projected in the 2nd MYT Order. The
AT&C loss as projected by the Petitioner for FY 2015-16 is given n the Table below:
Table 4.8: AT&C Loss proposed by the Petitioner for FY 2015-16 (%)
Particulars Approved in 2nd
MYT Order Estimated for
FY 2014-15 Projected
for FY 2015-16
AT&C Loss Target 9.85% 8.31% 8.31%
Collection Efficiency Target 100.00% 100.00% 100%
Distribution Loss Target 9.85% 8.31% 8.31%
Commission’s analysis
4.28 The Commission has considered the Distribution loss targets for FY 2015-16
considering the second MYT control period trajectory for reduction of distribution
loss of 0.25% loss reduction every year due to extension of MYT Regulations, 2011 in
the MYT Order dated 13.07.2012. Hence, the Commission has considered 9.60%
distribution loss for FY 2015-16 against the distribution loss target of 9.5% in FY
2014-15 and collection efficiency at 100% as specified in the 2nd MYT Order for
projection for FY 2014-15 and also as proposed by the Petitioner for FY 2015-16,
which is indicated in the Table as follows:
Table 4.9: AT&C Loss for FY 2015-16 (%)
Particulars Now approved
AT&C Loss Target 9.60%
Collection efficiency target 100.00%
Distribution Loss target 9.60%
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 68
September 2015
Energy Requirement
Petitioner’s Submission
4.29 The Petitioner has estimated the energy requirement of 1499.80 MU at Distribution
Periphery for FY 2015-16 against projected sales of 1375.19 MU. The Petitioner has
considered the Distribution Loss at 8.31% as shown in the following Table:
Table 4.10: Estimated energy requirement proposed by the Petitioner for FY 2015-16
Sl. No. Particulars Unit Proposed Energy
Requirement
1 Energy Sales MU 1375.19
2 Distribution Loss % 8.31%
3 Energy requirement MU 1499.80
Commission’s Analysis
4.31 The Commission has computed the energy requirement for FY 2015-16 as per the
approved sales of 1366.19 MU. The Distribution Loss is considered as arrived at in
the true up of FY 2013-14 i.e., 9.60%. The approved energy requirement for FY 2015-
16 is summarised as follows:
Table 4.11: Approved Energy Requirement for FY 2015-16
Sl. No Particulars Unit Approved Energy
Requirement Reference
A Energy sales MU 1366.19 Table No. 4.5
B Distribution Loss % 9.60% Table No. 4.9
C Energy requirement MU 1511.27 C=A/(1-B)
D Distribution Loss MU 145.08 C-A
Power Purchase Quantum
Petitioner’s Submission
4.32 The Petitioner has submitted that it has allocations from Rajghat Power House, Gas
Turbine, Dadri TPS, Badarpur TPS and Pragati Power Stations. The Petitioner has
further submitted that the rate for power purchase for FY 2015-16 has been kept
same as actual rate of power purchase during FY 2013-14 to determine the power
purchase cost for FY 2015-16.
4.33 The total power purchase cost of NDMC for FY 2015-16 consists of power purchase
cost from various sources and the transmission charges payable to transmission
utilities including SLDC.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 69
September 2015
4.34 The Petitioner has projected the revenue from sale of surplus power available for
external sale at Rs. 4.20/kWh for FY 2015-16.
4.35 The Petitioner has accordingly requested the Commission to allow the power
purchase cost (including transmission charges) of Rs. 952.23 Crore for FY 2015-16
(net of rebate) as shown in the following Table:
Table 4.12: Power Purchase details submitted by the Petitioner for FY 2015-16
Station Quantity
(MU) Amount
(Rs. Crore) Avg. Rate (Rs./kWh)
BTPS 598.84 650.03 5.14
NCCP- Dadri - I 664.89
Rajghat 0.496 0.92 5.63
Gas Turbine 1.14
Pragati-I 545.03 290.18 4.32
PPS-III (Bawana) 127.186
Gross Power Purchase 1937.58 941.13 4.86
Power from solar 1.58 1.22 7.72
Power from waste to energy 23.25 9.88 4.25
Power from RE 24.83 11.10 4.47
Grand Total 1962.41 952.23 4.85
Commission’s Analysis
4.36 Power purchase cost is the single largest component of ARR of a Distribution Utility.
It is pertinent to estimate the power purchase cost with utmost care based on the
most optimum method of procuring power from the generating stations.
Allocation of Power from Generating Stations
4.37 The Commission with regards to power purchase allocation from various sources
has considered the allocation from firm as well as unallocated share as shown in the
following Table :
Table 4.13: Allocation of Power from Delhi Stations to Petitioner for FY 2015-16
Sl. No
Delhi State Generating Stations
Installed Capacity (MW)
NDMC Share (% )
NDMC (MW)
Reference
A Badarpur TPS 705.00 17.73 125.00
As per the Allocation
B NCPP – Dadri 840.00 21.70 125.00
C Pragati – I * 330.00 30.30 100.00
D PPS-III, Bawana 1,371.20 4.13 100.10
E Total 3,246.20 450.10 Sum ( A to D) *Total installed capacity of Pragati 330 MW. However, 230MW is allocated to BRPL, BYPL and TPDDL. Remaining100 MW is allocated to NDMC.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 70
September 2015
Energy Availability from Central Generating Station (CSGS)
4.38 The Commission has examined the quantum of energy projected as available for
purchase by Petitioner from CSGS, SGS and others.
4.39 The Commission has considered the notification of NRPC on the availability of power
from various Central and State generating stations in Load Generation Balance
Report (LGBR) for FY 2015-16. The Commission had sought SLDC to provide the
availability of power for DISCOMs in Delhi from various Central, State and other
generating stations from which DISCOMs in Delhi propose to purchase power for
FY 2015-16.
4.40 The anticipated availability estimated by SLDC for all the Delhi DISCOMs is about
35291 MU and out of which the share for the Petitioner is 2183.14 MU.
4.41 The availability of power to the Petitioner from Central and State Generating
Stations and Other Generating Stations approved for FY 2015-16 is as shown in the
following table:
Table 4.14: Energy available from Generating Stations to NDMC as approved by the Commission for FY 2015-16 (MU)
Sl. No. Generating Stations Energy Available Reference
Central Generating Stations
A NCPP - Dadri I 851.60 As per SLDC
State Generating Stations
B Badarpur TPS 612.85 As per SLDC
C Rajghat Power Station -
D IP GTPS -
E Pragati Power Station – I 527.88
As per SLDC F PPS-III Bawana 159.69
G TOWMCL 27.72
H Solar (SECI) 1.82
I Petitioner’s Solar 1.58 As per petition
J Sub-total of SGS 1331.53 Sum (B to I)
K Total Energy Available 2183.14 (A+ J)
Power Purchase Cost
Petitioner’s Submission
4.42 The Petitioner has submitted that the net Power Purchase Cost for FY 2015-16 at
Rs. 875.45 Crore (including Transmission Charges) as given below:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 71
September 2015
Table 4.15: Power purchase cost for FY 2015-16 proposed by the Petitioner
Sl. No.
Particulars Quantity
(MU) Amount
(Rs. Crore) Avg. Rate (Rs./kWh)
1 Power purchase from NTPC (including Dadri and BTPS)
1263.73 650.03 5.14
2 Inter-state Loss/ Transmission charges 22.34 26.09 3 Power Available at Delhi Periphery 1241.39
4 Power Purchase from SGS (including renewable)
698.36 302.20 4.33
5 Intra-state Loss/ State Transmission charges including SLDC charges
14.15 63.35
6 Short term Power Purchase - 7 Power available to DISCOM 1925.61 8 Sales 1375.19 9 Distribution loss 8.31%
10 Required Power for the DISCOM 1499.80
11 Surplus power available at DISCOM boundary
426.12 178.97 4.20
12 Additional cost of RPO 12.76 13 Less: Power purchase rebate 19.43 14 Less: Transmission charges rebate 1.83
15 Net power purchase cost including transmission charges and RPO
875.45
Commission’s Analysis
4.43 The following methodology has been adopted by the Commission for estimation of
power purchase cost for FY 2015-16.
(a) The Commission has considered the fixed charges and energy charges as per
the petition of the NTPC stations (BTPS and NCPP-Dadri) filed before CERC in
line with the CERC Tariff Regulation FY 2014-19. Further, the Commission has
considered an escalation of 5% on the Energy Charges of these stations.
(b) For Pragati-I, the Commission has considered the rate as approved in Tariff
Order of PPCL for FY 2015-16.
(c) The cost of power purchase from Solar Energy Corporation of India (SECI) has
been considered at Rs. 5.50/kWh based on the allocation of power from SECI to
Petitioner.
(d) The Commission has also considered 1.58 MU of Solar power as proposed by
the Petitioner at the Average Power Purchase Cost of the Petitioner.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 72
September 2015
(e) The cost of power purchase from TOWMCL is considered at Rs. 2.83/kWh
which is the levelised rate of this station.
4.44 The total power purchase cost approved by the Commission is summarized in the
Table as follows:
Table 4.16: Approved Power Purchase Cost by the Commission for FY 2015-16
Sl. No.
Particulars Energy (MU)
Fixed Rate
(Rs./kWh)
Fixed Charge (Rs. Cr.)
Variable Rate
(Rs./kWh)
Variable Charge (Rs. Cr.)
Total Charge (Rs. Cr.)
Average Rate
(Rs./kWh) Reference
CSGS 1 NCPP - DADRI 851.60 0.70 59.39 3.44 293.29 352.68 4.14
Para 4.43 Table 4.14
SGS
2 BTPS 612.85 1.16 71.16 4.62 283.14 354.29 5.78
3 Pragati - I 527.88 1.09 57.54 4.42 233.32 290.86 5.51
4 Pragati - III, BAWANA
159.69 4.95 79.05 3.08 49.23 128.28 8.03
5 Sub-Total 1300.41 1.60 207.75 4.35 565.69 773.44 5.95
6 TOWMCL 27.72 0.00 0.00 2.83 7.84 7.84 2.83
7 Solar 1.82 0.00 0.00 5.50 1.00 1.00 5.50
8 Petitioner's Solar
1.58 5.20 0.82 0.82 5.20
9 Sub-Total 31.12 0.00 0.00 13.53 9.67 9.67 3.11 10 Grand Total 2183.14 1.22 267.14 3.98 868.65 1135.79 5.20 1+5+8
Cost of Power Purchase from other Sources (Short term Purchase)
Petitioner’s Submission
4.45 The Petitioner has not shown any purchase of power from the short term sources.
Commission’ Analysis
4.46 The Commission directs the Petitioner that in case of excess demand, the Petitioner
may first utilize the quantum of Banked Energy and in case of further shortage they
may purchase from Bilateral/Exchange etc. so as to keep the short term power
purchase cost at minimum level.
4.47 The Commission directs to adhere strictly the principle of merit order dispatch while
scheduling of power from long term and short term transactions of power. As per
Merit Order Dispatch principle, the plants are stacked in least cost approach of their
Variable Cost. The demand is then met through stations in ascending order of their
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 73
September 2015
Variable Cost subject to various Technical Constraints and the balance power from
the left over stations after meeting the required demand, are not scheduled.
Renewable Power Purchase Obligation (RPO)
4.48 The Commission has notified the Delhi Electricity Regulatory Commission
(Renewable Purchase Obligation and Renewable Energy Certificate Framework
Implementation) Regulations, 2012 with effect from October, 2012 and it states as
follows:
“Every obligated entity shall meet its RPO target by way of its own
generation or by way of purchase from other licensee(s) or by way of
purchase of Renewable Energy Certificate(s) or by way of combination of any of
the above options.”
4.49 The Commission has prescribed the following year-wise Solar and Non-solar
Renewable Obligations for the Distribution Companies for the period FY 2013-14 to
FY 2016-17 in the above said Regulations:
Table 4.17: RPO Obligation (%)
Financial Year Solar Total 2012-13 0.15% 3.40% 2013-14 0.20% 4.80% 2014-15 0.25% 6.20% 2015-16 0.30% 7.60% 2016-17 0.35% 9.00%
4.50 As per the above said Regulations, the NDMC has to purchase 7.60% of total energy
consumption approved by the Commission for FY 2015-16 from Renewable Energy
(i.e., 0.30% from Solar and 7.30% from Non-Solar Renewable Energy Sources).
4.51 The Commission has approved the total energy sales of 1366.19 MU for the
Petitioner for FY 2015-16. Based on the sales approved, the Petitioner has to
purchase a minimum of 103.83 MU from Renewable Energy sources for FY 2015-16
indicated in the Table as follows:
Table 4.18: Approved Renewable Energy to be procured by the Petitioner for FY 2015-16 (MU)
Power Source Approved Energy
Sales (MU)
% of Total Energy Sales Approved in
Regulations
Renewable Energy to be procured
(MU)
1 2 3 4 = 2*3
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 74
September 2015
Power Source Approved Energy
Sales (MU)
% of Total Energy Sales Approved in
Regulations
Renewable Energy to be procured
(MU)
Solar
1366.19
0.30% 4.10 Non Solar 7.30% 99.73 Total 7.60% 103.83
4.52 The Commission considers that the Petitioner has to purchase the Renewable Energy
or purchase Renewable Energy Certificate(s) or combination of both to meet the RPO
targets for FY 2015-16.
4.53 In case the Petitioners is not able to procure additional power from RE sources to
meet RPO obligation, the Petitioner has to purchase the certificates for 0.70 MU
(4.10 MU – 1.82 MU – 1.58 MU) Solar and 72.01 MU Non-Solar (99.73 MU – 27.72
MU). CERC has fixed Floor Price and Forbearance Price for the period up to FY 2016-
17 in its Suo Motu Order in the Petition No. SM/016/2014 dated 30.12.2014
indicated in the Table as follows:
Table 4.19: Solar & Non-Solar Rate as per CERC Order
Sl. No. Particulars Floor Price Forbearance Price
1 Non-Solar Rs. 1500/MWh Rs. 3500/MWh
2 Solar Rs. 3300/MWh Rs. 5800/MWh
4.54 However, the Commission computes the additional cost to be incurred to meet RPO
obligation by considering that the Petitioner will procure the RE certificates to meet
the RPO during FY 2015-16.
4.55 The Commission has considered the floor prices of REC rates for purchasing solar and
Non solar RE certificates to meet RPO in FY 2015-16.
4.56 The cost of Renewable Energy/RECs to be purchased by the Petitioner for FY 2015-16
is given in the Table as follows:
Table 4.20: Approved Cost of Power purchase to meet RPO for FY 2015-16
Sl. No. Sources of
Renewable Energy Quantity to
be Purchased (MU) Avg. Rate (Rs/kWh)
Total Cost (Rs. Cr.)
Remarks
1 Non-solar RECs 72.01 1.50 10.80 Para 4.52 Table 4.19 2 Solar RECs 0.70 3.30 0.23
3 TOWMCL 27.72 2.83 7.84
4 Solar 1.82 5.50 1.00
5 Petitioner's solar 1.58 5.20 0.82
6 Total 103.83 1.99 20.70 Sum (1 to 5)
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 75
September 2015
4.57 The Commission approves the purchase cost to the extent of Rs. 20.70 Crore for the
Petitioner to meet the Renewable Power Purchase Obligation for FY 2015-16. The
Commission directs that the Petitioner should endeavour to procure actual
Renewable Energy for FY 2015-16 instead of purchasing RE certificates in Order to
meet its total RPO to the level of 103.83 MU as indicated in the Table above.
Transmission Losses and Charges
Petitioner’s Submission
4.57 The Petitioner has submitted that it has pro-rated the transmission charges for
FY 2014-15 based on actual payments made up to January 2015. The transmission
charges for FY 2015-16 have been projected at an increased rate of 5% with respect
to transmission charges calculated for FY 2014-15. The cost is calculated net of
rebate. The transmission losses and charges claimed by the Petitioner is indicated in
the table as follows:
Table 4.21: Transmission Charges and Losses submitted by Petitioner for FY 2015-16
Particulars UoM Amount
Inter-state Transmission Loss % 3.36%
Inter-state Transmission Loss MU 22.34
Inter-state Transmission charges Rs. Crore 26.09
Intra State Transmission Loss % 0.95%
Intra State Transmission Loss MU 14.15
Intra State Transmission charges Rs. Crore 63.35
Total Transmission Charges Rs. Crore 89.44
Commission’s Analysis
Intra-State and Interstate Losses
4.58 The Commission has considered the Intra-State Transmission losses at 0.70% for
FY 2015-16 at the same level of FY 2014-15 as projected by SLDC.
4.59 The Commission has considered the weighted average Inter-State Transmission loss in
the Northern region and Eastern Region at 3.14% for FY 2015-16 based on the actual
Point of Connection (PoC) losses during April 2015 to July 2015.
Transmission charges
4.60 The Commission has considered the Inter-state Transmission charges for FY 2015-16
at Rs. 18.56 Crore as intimated by the Petitioner during the Technical Validation
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 76
September 2015
Session for FY 2013-14.
4.61 The Intra-State Transmission charges has been considered based on
a) ARR approved by the Commission for DTL for FY 2015-16 which is amounting to
Rs. 51.14 Crore as per the share of the Petitioner.
b) The Commission has considered SLDC charges of Rs. 0.62 Crore for the Petitioner
for FY 2015-16 as per ARR approved by the Commission vide its Order dated
05.12.2013 for Petition No. 38/2012 for FY 2011-12.
Transmission Losses and Charges
4.61 The Inter State and Intra State Transmission Losses and Charges as approved by the
Commission for FY 2015-16 are summarized in the table as follows:
Table 4.22: Transmission Charges and Losses approved by the Commission for FY 2015-16
Sl. No.
Particulars Now Approved for FY 2015-16
Reference
A Transmission losses (%) 1 Inter-State Transmission 3.14
Table 4.25 2 Intra-State Transmission 0.70 B Transmission Charges (Rs Crore) 1 Inter-state Transmission Charges 18.56 Para 4.61
2 Intra-state Transmission Charges 51.14 Para 4.61
3 SLDC Charges 0.62 C Total Transmission Charges (Rs. Crore) 70.31 B (1+2+3)
Energy Balance
Petitioner’s submission
4.63 The energy balance submitted by the Petitioner for FY 2015-16 is summarized as
follows:
Table 4.23: Energy Balance projected by the Petitioner for FY 2015-16
Sl.
No. Particulars UoM FY 2015-16
A Energy Availability
I Total Energy Available (excluding
BTPS, SGS, TOWMCL & Solar) MU 664.89
II Inter-state Transmission Loss % 3.36
MU 22.34
III Energy available from BTPS and SGS MU 1272.69
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 77
September 2015
Sl.
No. Particulars UoM FY 2015-16
IV Short term purchase MU 0.00
V Surplus power sold MU 426.12
VI Energy available at state transmission
periphery MU 1489.13
VII UI purchase MU 0.00
VIII Net energy available at state
periphery MU 1489.13
B Energy Requirement
I Energy sales MU 1375.19
II Distribution Losses % 8.31
MU 124.62
III Energy Injected from RE source at DTL
periphery MU 24.83
IV Energy requirement at distribution
periphery MU 1499.80
V Intra-state transmission loss % 0.95%
MU 14.15
VI Energy requirement at transmission
periphery MU 1489.13
C Surplus Energy MU 426.12
Commission’s Analysis
4.64 Based on the Energy Sales, Distribution Losses and Transmission Losses approved by
the Commission in the above paragraphs, the energy balance approved by the
Commission is summarised in the Table as follows:
Table 4.24: Energy Balance approved by the Commission for FY 2015-16
Sl. No.
Particulars UoM Quantity
(MU) Remarks
Energy Availability
A Energy available from CSGS (Dadri-I) MU 851.60 Table 4.14
B Inter- State Transmission Losses % 3.14% Para 4.59
MU 26.74 Table 4.22
C Energy available from Delhi Stations (SGS,BTPS, TOWMCL & Solar)
MU 1331.53 Table 4.14
D Energy available at State Transmission Periphery MU 2156.40 (A-B+C+D)
Energy Requirement
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 78
September 2015
Sl. No.
Particulars UoM Quantity
(MU) Remarks
E Energy Sales 1366.19 Table 4.5
F Distribution Loss % 9.60%
Table 4.11 MU 145.08
G Energy requirement at distribution periphery 1511.27 Table 4.11
H Intra state Transmission Loss % 0.70% Para 4.58
MU 10.65 Table 4.21
I Energy requirement at Transmission Periphery 1521.92 (G+H)
J Surplus Energy 634.48 (D-I)
Sale of Surplus Power
Petitioner’s Submission
4.65 The Petitioner has projected to sell the surplus power of 426.12 MU for FY 2015-16
at Rs. 4.20/kWh amounting to Rs. 178.97 Crore.
Commission’s Analysis
4.66 The quantum of Surplus Power of 634.48 MU has been computed as indicated in the
above Table 4.25.
4.67 The Commission has considered rate of sale of surplus Power at Rs.4.20/kWh, as
submitted by the Petitioner.
4.68 Accordingly, the Commission approves the total sale of Surplus Power of 634.48 MU
at Rs. 4.20/kWh indicated in the Table as follows:
Table 4.25: Approved Sale of Surplus Power for FY 2015-16
Particulars Surplus Energy
(MU) Average Rate
(Rs /kWh) Total Cost (Rs. Crore)
Bilateral Sale of Surplus Power 634.48 4.20 266.48
Rebate on Power Purchase and Transmission Charges
4.69 With regard to rebate on Power Purchase and Transmission charges the MYT
Regulations, 2011 states that:
“Distribution Licensee shall be allowed to recover the net cost of power it
procures from sources approved by the Commission viz. Intra-state and Inter-
state Trading Licensees, Bilateral Purchases, Bulk Suppliers, State generators,
Independent Power Producers, Central generating stations, non-conventional
energy generators, generation business of the Distribution Licensee and others,
assuming maximum normative rebate available from each source for payment of
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 79
September 2015
bills through letter of credit on presentation of bills for supply to consumers of
Retail Supply Business.”
4.70 Accordingly, the Commission has been considering Power Purchase Rebate @ 2% of
the gross power purchase cost and Transmission Rebate @ 2% of the total
Transmission and SLDC Charges for projection of the normative rebate on the power
purchase cost:
Table 4.26: Rebate on Power purchase and Transmission Charges approved for FY 2015-16 (Rs. Crore)
Sl. No Particulars Total Amount
(Rs. Crore) Rebate (%) FY 2015-16
A Power Purchase Rebate 1135.49 2% 22.72
B Transmission Charges Rebate 70.31 2% 1.41
C Total Rebate 1205.80 24.12
Total Power Purchase Cost
4.71 Based on the analysis above the total power purchase cost for FY 2015-16 approved
by the Commission is summarized in the Table as follows:
Table 4.27: Total Power purchase Cost approved by the Commission for FY 2015-16
Sl. No.
Source Quantity
(MU) Amount
(Rs. Crore) Avg. Rate (Rs./kWh)
A Power Purchase from CSGS* 851.60 352.68 4.14 B Inter State Transmission Loss 26.74 18.56 C Power Purchase from Delhi Stations# 1331.53 773.44 5.81 D Cost towards REC 20.70 E Power Available at NDMC Periphery 2156.40 1165.38 5.40
F Intra State Transmission Loss & Including SLDC charges etc.
10.65 51.75
G Less: Power Purchase Rebate @ 2% 22.72
H Less: Rebate on Transmission Charges (@ 2%)
1.41
I Power available to DISCOM 2145.74 1193.01 5.56 J Sales 1366.19 K Distribution Loss 145.08 L Required Power 1511.27 926.53 6.13
M Surplus Power Available at DISCOM boundary
634.48 266.48 4.20
*Includes Dadri-I # Includes PPCL, Rajghat, GTPS, BTPS, TOWMCL and Solar
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 80
September 2015
Power Purchase Cost Adjustment Charge (PPAC)
4.72 The Commission had approved the formula for Power Purchase Cost Adjustment
Charge vide its tariff Order dated 31.07.2013.
4.73 The Power Purchase Adjustment would be according to the formula as follows:
Power Purchase Adjustment (PPA) formula
PPA for nth Qtr. (%) = (A-B)*C + (D-E)-F
{Z * (1- Distribution losses in %)} * ABR Where,
A = Total units procured in (n-1)th Qtr (in kWh) from power stations having long term Power Purchase Agreements (To be taken from the bills of the GENCOs issued to distribution licensees)
B = Proportionate bulk sale of power from Power stations having long term Power Purchase Agreements in (n-1)th Qtr (in kWh)
=
Total bulk sale in (n-1)th Qtr (in kWh) * A
Gross Power Purchase including short term power in (n-1)th Qtr (in kWh)
Total bulk sale and gross power purchase in (n-1)th Qtr to be taken from provisional
accounts to be issued by SLDC by the 10th of each month.
C = Actual average Power Purchase Cost (PPC) from power stations having long term Power Purchase Agreements in (n-1)th Qtr (Rs./ kWh) (Projected average Power Purchase Cost (PPC) from power stations having long term Power Purchase Agreements (Rs./ kWh)
D = Actual Transmission Charges paid in the (n-1)th Qtr
E = Base Cost of Transmission Charges for (n-1)th Qtr = (Approved Transmission Charges/4)
F = Net revenue billed from ToD i.e. (Revenue billed on account of Surcharge-Rebate)
Z = [{Actual Power purchased from Central Generating Stations having long term PPA in (n-1)th Qtr (in kWh)*(1- INTERSTATE TRANSMISSION LICENSEE losses in %) + Power from Delhi GENCOs including BTPS (in kWh)}*(1 - DTL losses in %) – B] in kWh
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 81
September 2015
ABR = Average Billing Rate for the year Distribution Losses (in %) = Target Distribution Losses
INTER STATE TRANSMISSION
LICENSEE Losses (in %)
=
100* Approved INTER STATE TRANSMISSION LICENSEE (kWh)
Approved long term power purchase from central generating stations having long term PPA (kWh)
DDTL Losses (in %)
=
100 * Approved DTL Losses (from the Tariff Order)
Power available at Delhi periphery
4.74 The base Power Purchase Cost for various generating stations over which any
increase has to be taken during FY 2015-16 is as follows:
Table 4.28: Schedule – Base cost for FY 2015-16
Sl. No.
Particulars Energy (MU)
Total Charge
(Rs. Crore)
Avg. Rate (Rs./kWh)
1 NCPP – DADRI 851.60 352.68 4.14
2 BTPS 612.85 354.29 5.78
3 Pragati – I 527.88 290.86 5.51
4 Pragati – III, BAWANA 159.69 128.28 8.03
5 TOWMCL 27.72 7.84 2.83
6 Solar 1.82 1.00 5.50
7 Petitioner’s Solar 1.58 0.82 5.20
8 Grand Total 2183.14 1135.79 5.20
4.75 NDMC may claim the increase in the power purchase cost in accordance with the
formula approved by the Commission and recover from the consumers on approval
of the Commission.
4.76 In Order to give effect to PPAC on quarterly basis the following directives are to be
implemented:
(a) The PPAC will be charged to all categories of consumers.
(b) The PPAC for any quarter would be charged only after it is approved by the
Commission.
(c) The weighted average base cost in Rs/kWh shall be as approved in this Tariff
Order for FY 2015-16 is Rs 5.20/kWh for Petitioner. Detailed computation is
given in Table 4.29 above. The Schedule will be revised in every subsequent
Tariff Order.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 82
September 2015
(d) The Distribution licensee shall submit to the Commission the details in
respect of changes in power purchase cost of plants having long term PPAs, as
listed in Table for (n-1)th quarter. Further, Auditor’s Certificate along with
statement indicating plant-wise details of fixed charges, variable charges,
other charges and units purchased from each plant having long term PPAs, as
listed in Table for (n-1)th quarter along with actual transmission charges for
(n-1)th quarter, revenue realised from surcharge and rebate given during (n-1)th
quarter on account of ToD shall be furnished along with the proposal of PPAC
surcharge submitted for the Commission’s approval. Further, similar
information in respect of current bills should also be furnished in the Auditor’s
certificate.
(e) The percentage of PPAC will be rounded off to two decimal places.
(f) The percentage increase on account of PPA will be applied as a surcharge on
the total energy and fixed charges (excluding theft bills, arrears, LPSC,
Electricity duty etc.) billed to a consumer of the utility.
(g) The bill format shall clearly identify the PPA percentage and amount of PPAC
billed as separate entries.
(h) The PPAC calculated for any quarter, the first quarter being July-September
2013, shall be applied prospectively for 3 months after approval is received
from the Commission.
(i) In view of the fact that PPAC computed for any quarter will be applied after a
time delay for a subsequent 3 month period, there would necessarily be a
difference between the actual power purchase cost increase and the recovery
by the distribution utility through the quarterly adjustments. The difference
will be adjusted at the time of annual true-up undertaken by the Commission
for that year.
(j) The PPAC claim of any quarter submitted by the Petitioner shall be examined
by the Commission every quarter and abnormal increase in PPAC claim in any
quarter will be carried forward to the subsequent quarter to avoid tariff shock
and to normalize the PPAC burden on to the consumer.
(k) This PPAC formula shall remain applicable till it is amended, reviewed or revised.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 83
September 2015
Operation and Maintenance (O&M) Expenses
Petitioner’s Submission
4.77 The Petitioner has submitted that O&M expenses for FY 2015-16 have been
projected at the same level as that approved for FY 2014-15 in the MYT Order dated
13.07.2012 as given in the following Table:
Table 4.29: O&M Expenses submitted by Petitioner for FY 2015-16 (Rs. Crore)
Particulars Petitioner's submission
Gross O&M expenses 151.14
Efficiency Factor 4%
Efficiency improvement 6.05
O&M Expenses 145.09
Commission’s Analysis
4.78 The Commission vide Order dated 22.10.2014 has extended the MYT period of FY
2012-13 to FY 2014-15 for a further period of one year i.e. FY 2015-16, ordered vide
clause 23 that
“.......... Further in Order to avoid any doubt or ambiguity, the Commission in its
wisdom considers it appropriate that the MYT Regulations 2011 be extended in
totality i.e. the control period should be extended for one year i.e. FY 2015-16.
Therefore the Commission is of the considered view that public interest is best
served by extending the MYT regulations 2011 by one year i.e. FY 2015-16”.
4.79 The Commission has approved inflationary increase at 8.00% in the MYT Order dated
13.07.2012 and accordingly, approved the O&M expenses for the MYT period with
year on year escalation for inflationary increase over the base expenses.
4.80 The Commission, in terms of ruling at Clause 23 in its Order dated 22.10.2014, has
considered year on year growth rate of 8.00% on the O&M expenses considered for
FY 2014-15 (as per MYT Order dated July 13, 2012) and approves the O&M expenses
for FY 2015-16.
4.81 The Commission has approved net O&M expenses at Rs.158.99 Crore (after
efficiency improvement of 4%) for FY 2014-15 in the MYT Order dated 13.07.2012.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 84
September 2015
4.82 It is observed that the Petitioner has projected the O&M expenses for FY 2015-16 at
the same level of FY 2013-14 without escalation for year on year inflationary
increase.
4.83 The Commission has considered the O&M expenses of FY 2014-15 as base O&M
expenses in accordance with the MYT Order dated 13.07.2012 and escalated with
8.00% for inflationary increase and projected the O&M expenses for FY 2015-16. The
efficiency factor is considered at 4% in line with the efficiency factor considered for
FY 2014-15 due to higher per unit of O&M expenses of the Petitioner in comparison
of other distribution licensee in the area of GoNCTD.
4.84 The Commission, accordingly, has considered the O&M expenses for FY 2015-16 as
given in the table below:
Table 4.30: Gross O&M Expenses approved for FY 2015-16 (Rs. Crore)
Particulars
O&M Expenses for FY 2014-15
(as per MYT Order dated July 13, 2012)
Growth rate adopted for inflationary
increase for FY 2015-16
Now Approved for FY 2015-16
1 2 3 4=2*3
Gross O&M Expenses 158.99 8.00% 171.80
4.85 Therefore, the O&M expense approved by the Commission is Rs. 171.80 Crore, which
is shown in the table below:
Table 4.31: O&M Expenses approved by Commission for FY 2015-16 (Rs. Crore)
Sl. No. Particulars Petitioner's Submission
Now Approved
Reference
A Gross O&M Expenses 151.14 171.80 Table 4.31
B Efficiency Factor % 4% 4.00% Para 4.83
C Less: Efficiency improvement 6.05 6.87 C = A*B
D Net O&M expenses 145.09 164.92 D = A - C
Administrative Expenses and Civil Engineering Department Expenses
Petitioner’s Submission
4.86 The Petitioner has stated that it is yet to segregate the expenses shared by its Civil
Engineering Department on account of electricity distribution business and hence
considered the same amount as approved by the Commission for FY 2015-16 in the
tariff Order dated 31.07.2013 provided in the Table as follows:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 85
September 2015
Table 4.32: Administrative and Civil Engineering Department Expenses proposed for FY 2015-16 (Rs. Crore)
Particulars Petitioner's submission
Administrative and Civil engineering Department Expenses
45.37
Commission’s Analysis
4.87 As discussed in chapter 3 of this Order, the O&M Expenses per unit of the Petitioner
is highest among all the DISCOMs. Further, addition of Administrative and Civil
Engineering Department Expenses increases the O&M Expenses to about 3 times
than the other DISCOMs. Hence, in view of the high O&M Expenses of the Petitioner
in comparison of other distribution licensee operating in the area of GoNCTD, the
Commission has not considered the cost of Administrative and Civil Engineering
Department Expenses over and above the normative O&M expenses of the
Petitioner for FY 2015-16.
Capital Expenditure and Capitalization
Petitioner’s Submission
4.88 The Petitioner has proposed Capital expenditure and Capitalization for FY 2015-16
with escalation of 5% over the capex and capitalisation approved for FY 2014-15 in
the MYT Order dated 13.07.2012 as given in the Table below:
Table 4.33: Capital Expenditure and Capitalization projected for FY 2015-16 (Rs. Crore)
Particulars Petitioner’s Projections
Capital expenditure 12.00
Capitalisation 15.29
Commission’s Analysis
4.89 Regulation 4.21(b)(ii) specifies that Depreciation and Return on Capital employed
shall be trued up every year based on the actual Capital investment plan (Capital
expenditure and capitalization) approved by the Commission. The actual financial
and physical performance of Capex for FY 2014-15 are not yet available for the
Petitioner to arrive at the actual Capital Expenditure, Capitalization, Depreciation,
the closing balance of GFA and the Regulated Rate Base that need to be carried
forward as opening balances for FY 2015-16 for considering any changes/revision of
these expenses for FY 2015-16. The Petitioner has projected the Capital Expenditure
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 86
September 2015
and Capitalisation for FY 2014-15 at the same level as approved in the MYT Order
dated July 13, 2012 and for FY 2015-16 with escalation of 5% over the capex and
capitalisation of FY 2014-15. The Commission accordingly, provisionally considers
the capex and capitalisation for FY 2015-16 as given in the Table below:
Table 4.34: Capitalization approved for FY 2015-16 (Rs. Crore)
Particulars Petitioner’s submission
Approved for FY 2015-16
Capital expenditure 12.00 12.00
Capitalisation 15.29 15.29
Depreciation
Petitioner’s Submission
4.89 The Petitioner has submitted that Depreciation is charged on straight line method on
the average GFA. The rate of Depreciation is adopted at 3.60% as approved in the
MYT Order dated July, 13, 2012. The Petitioner has projected the Depreciation at
Rs.39.88 Crore for FY 2015-16 in accordance with MYT Regulations, 2011 as given in
the Table below:
Table 4.35: Depreciation projected by the Petitioner for FY 2015-16 (Rs. Crore)
Particulars Petitioners submission
Opening GFA 1111.06
Additions during the year 15.29
Closing GFA 1126.35
Opening consumer contribution 10.97
Additions during the year --
Closing consumer contribution 10.97
Opening GFA (net of consumer contribution) 1100.09
Closing GFA (net of consumer contribution) 1115.38
Average GFA (net of consumer contribution) 1107.74
Rate of Depreciation 3.60%
Depreciation 39.88
Commission’s Analysis
4.90 The Commission has provisionally approved closing GFA of Rs. 472.70 Crore for
FY 2013-14 and further updated with the capitalisation of Rs.11.43 Crore for FY
2014-15 and Rs.15.29 Crore for FY 2015-16. The Commission shall consider the
amount of consumer contribution for FY 2015-16 after receiving the actual audited
financial statements.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 87
September 2015
4.91 The Commission, subject to true up, considers the Depreciation for FY 2015-16 as
per the following Table:
Table 4.36: GFA and Depreciation considered for FY 2015-16 (Rs. Crore)
Sl. No.
Particulars Petitioner’s submission
Approved for FY 2015-16
Reference
A Opening GFA 1111.06 484.13 Closing of
FY 2014-15
B Additions during the year 15.29 15.29 C Closing GFA 1126.35 499.42 C = A + B
D Opening consumer contribution 10.97 E Additions during the year - F Closing consumer contribution 10.97 F = D + E
G Opening GFA (net of consumer contribution)
1100.09 484.13 G = A – F
H Closing GFA (net of consumer contribution) 1115.38 499.42 H = C – F
I Average GFA (net of consumer contribution)
1107.74 491.78 I = (G+H)/2
J Rate of Depreciation 3.60% 3.60% K Depreciation 39.88 17.70 K = I * J
Working Capital
Petitioners’ Submission
4.92 The Petitioner has submitted that Working Capital requirement has been computed
as per MYT Regulations 2011. The Petitioner has calculated the working capital
requirement for FY 2015-16 as given in the Table below:
Table 4.37: Working Capital projected for FY 2015-16 (Rs. Crore)
Particulars Petitioner’s Submission
Receivables from Transmission charges 977.96
Receivables equivalent to two months 162.99
Net purchase expenses (incl. transmission charges) 875.45
Less: 1/12th of Transmission charges 72.95
Total working capital 90.04
Less: Opening working capital 85.70
Change in working capital 4.34
Commissions’ Analysis
4.93 The Regulation 5.14 and 5.15 of the MYT Regulations 2011 specifies that working
capital shall consist of:
For wheeling business
Receivables for two months of wheeling charges
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 88
September 2015
For Retail supply business
(a) Receivables for two months of revenue from sale of electricity
(b) Less: Power purchase costs for one month
(c) Less: Transmission charges for one month, and
(d) Less: Wheeling charges for two months
4.94 The Commission has examined the working capital computations furnished by the
Petitioner. The power purchase expenses includes transmission charges, REC
purchases and power purchases from other sources net of power sold to others and
normative rebate.
4.95 The Commission has approved the working capital for FY 2015-16 given in the Table
as follows:
Table 4.38: Working Capital considered for FY 2015-16 (Rs. Crore)
Sl. No Particulars Petitioner’s Submission
Now Approved
Reference
A Receivables from sale of electricity 977.96 1123.39 Table 4.7
B Receivables equivalent to 2 months 162.99 187.23 (A/6)
C Net Power purchase expenses (including Transmission Charges, SLDC Charges, RPO and Normative Rebate)
875.45 926.53 Table 4.28
D Less: 1/12th Power purchase expenses 72.95 77.21 (C/12)
E Total Working Capital 90.04 110.02 B – D
F Less: Opening WC 85.70 115.00 T.O. dated 23.07.2014
G Change in Working Capital 4.34 (4.98) E - F
Regulated Rate Base (RRB)
Petitioner’s Submission
4.96 The Petitioner has submitted RRB computations for FY 2015-16 as given in the
following Table:
Table 4.39: RRB projected by the Petitioner for FY 2015-16 (Rs. Crore)
Sl. No.
Particulars Petitioner’s Submission
1 RRB – Base
a. Opening Balance of OCFA 1111.06
b. Opening Balance of working capital 85.70
c. Opening Balance of Depreciation 478.22
d. Opening Balance of AAD 0.00
e. Opening Balance of Consumers contributions/grants 0.00
Opening RRB 707.58
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 89
September 2015
Sl. No.
Particulars Petitioner’s Submission
2 RRB - for the Year
f. Investments Capital Expenditure during the year 15.29
g. Depreciation for the year 39.88
h. Advance Against Depreciation 0.00
i. Consumers Contributions, Grants, etc. for the year 0.00
j. Change in working capital 4.34
3 Change in Regulated Rate Base [(f - (g+h+i)/2) + j]
(7.96)
4 Regulated Rate Base – Closing (1+2f+2j) - (2g+2h+2i)
687.32
5 Regulated Rate Base (i) (1 + 3) 699.62
Commissions’ Analysis
4.97 The RRB has been considered based on investment capitalised, depreciation and
working capital requirements for FY 2015-16 as detailed in the Table as follows:
Table 4.40: RRB considered by the Commission for FY 2015-16 (Rs. Crore)
Sl. No.
Particulars Petitioner’s Submission
Now Approved Reference
1 RRB – Base
A Opening Balance of GFA 1111.06 484.13
Table 4.37
B Opening Balance of Working Capital 85.70 115.00
C Opening Balance of Depreciation 478.22 372.38
D Opening Balance of Consumers Contributions/Grants
10.97
E Opening RRB 707.58 226.75 (A+B) - (C+D)
2 RRB - for the Year
F Investments capital expenditure during the year
15.29 15.29 Table 4.35
G Depreciation for the year 39.88 17.70 Table 4.37
H Change in working capital 4.34 (4.98) Table 4.39
3 Change in Regulated Rate Base (7.96) (6.19) (F-G)/2 +H
4 Regulated Rate Base – Closing 687.32 219.35 E+F+H-G
5 Regulated Rate Base (i) 699.62 220.56 (E+3)
Weighted Average Cost of Capital (WACC)
Petitioner’s Submission
4.98 The Petitioner has considered the rate of interest for FY 2015-16 at 11.50% equal to
the rate of interest considered for FY 2015-16 in the tariff Order dated 31.07.2013
and RoE is considered at 16% as per DERC Tariff Regulations, 2011. The Petitioner
has computed the WACC as detailed in the following Table:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 90
September 2015
Table 4.41: WACC projected by the Petitioner for FY 2015-16 (Rs. Crore)
Commissions’ Analysis
4.99 As per the Regulation 5.11 of the MYT Regulations 2011,
“For the purpose of determination of tariff, debt equity ratio for the asset
capitalised shall be 70 : 30. Where equity employed is in excess of 30%, the
amount of equity for the purpose of tariff shall be limited to 30% and balance
amount shall be considered as notional loan. Where actual equity employed is
less than 30%, the actual equity and debt shall be considered. The working
capital shall be considered 100% debt financed for the calculation of Weighted
Average Cost of Capital.
4.100 The Commission has considered the weighted average cost of debt at 11.50% equal
to the cost of debt considered for FY 2015-16 in the tariff Order dated 31.07.2013.
4.101 The Commission has accordingly, computed the weighted average cost of capital as
shown in the Table as follows:
Table 4.42: Approved Weighted Average Cost of Capital (WACC) for FY 2015-16
Sl. No.
Particulars Petitioner’s projections
Now approved Remarks
A RRB (i) 697.45 220.56 Table 4.41
B Debt 70% 70% MYT Regulations 2011 C Equity 30% 30%
D Cost of Debt 11.50% 11.50% Tariff Order dated
23.07.2014
E Return on Equity 16.00% 16.00% MYT Regulations
2011
F Weighted average cost of Capital 12.85% 12.85% ((B*D) + (C*E))
Return on Capital Employed (RoCE)
Petitioner’s Submission
4.102 The Petitioner has submitted that Return on equity is considered at 16% as per the
MYT Regulations, 2011 and the cost of debt at 11.50% in line with earlier tariff
Orders. RoCE proposed for FY 2015-16 is as given in the Table below:
Sl. No.
Particulars Petitioner
submission
1 RRB 697.45
2 Cost of debt 11.50%
3 Return on Equity 16.00%
4 Weighted average cost of Capital 12.85%
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 91
September 2015
Table 4.43: RoCE Projected by Petitioner for FY 2015-16 (Rs. Crore)
Sl. No.
Particulars Petitioner’s projections
1 RRB(i) 699.62
2 Rate of Return on Equity 16.00%
3 Rate of Return on Debt 11.50%
4 WACC 12.85%
5 RoCE (on 1) 89.90
Commissions’ Analysis
4.103 The return on capital employed considered by the Commission based on the RRB(i)
and WACC discussed above for FY 2015-16 is as given in the Table below:
Table 4.44: RoCE approved for FY 2015-16
Sl. No.
Particulars Petitioners Projections
Now Approved
Remarks
A RRB (i) 699.62 220.56 Table 4.41
B Rate of Return on Equity 16.00% 16.00%
Table 4.43 C Rate of Return on Debt 11.50% 11.50%
D WACC 12.85% 12.85%
E RoCE 89.90 28.34 A*D
Non Tariff Income
Petitioner’s Submission
4.104 The Petitioner has submitted that Non Tariff Income at the level as approved by the
Commission for FY 2015-16 in the tariff Order dated 31.07.2013 as given in the
following Table:
Table 4.45: Non Tariff Income projected for FY 2015-16 (Rs. Crore)
Particulars Petitioner’s Submission
Non Tariff Income 7.58
Commission’s Analysis
4.105 The Commission considers the Non Tariff Income as uncontrollable and subject to
true up as per MYT Regulations, 2011. Therefore, the Commission considers the non-
tariff income as proposed by the Petitioner for FY 2015-16 as given in the Table
below:
Table 4.46: Non Tariff Income approved for FY 2015-16 (Rs. Crore)
Particulars Petitioner’s Submission Now Approved
Non Tariff Income 7.58 7.58
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 92
September 2015
Carrying Cost on Revenue Gap
Petitioner’s submission:
4.106 The Petitioner has submitted opening gap is considered as per the Tariff Order for FY
2013-14, while determining the carrying cost. The rate of carrying cost is considered
at 11.50% and surcharge also been taken into account for calculation.
4.107 The Petitioner has calculated the carrying cost for FY 2014-15 and FY 2015-16
as detailed in the Table below:
Table 4.47: Carrying cost projected for FY 2014-15 and FY 2015-16 (Rs. Crore)
Sl. No. Particulars 2014-15 2015-16
1 Opening Gap for FY (n-2) 148.87 121.46
2 Revenue Requirement for FY (n-2) 1015.58 1371.54
3 Revenue during FY (n-2) 866.09 918.92
4 Gap / (Surplus) for FY (n-2) (3-2) 149.49 452.62
5 Surcharge for FY (n-2) 0.00 0.00
6 Net Gap / (Surplus) for FY (n-2) (4-5) 149.49 452.62
7 Rate of carrying cost for the year 11.50% 11.50%
8 Carrying cost (1*7)+((6*7)/2) 25.72 39.99
9 Closing balance of Gap / (Surplus) at the end of FY (n-2) (1+6+8)
324.08 614.07
10 Revenue requirement for the year ‘n’ 1196.63 1188.12
11 Rate of carrying cost for the year 11.50% 11.50%
12 Total Revenue Requirement including 8% Surcharge and carrying cost for FY ‘n’ (10+(9*11))/(1+(8%/2)*11)
1228.25 1252.97
13 Carrying cost (12-10) 31.62 64.86
Commission’s Analysis:
4.108 The Commission observed that past accumulated revenue gap has been liquidated
by the impact of past period truing up as discussed in chapter 3 of this Order.
4.109 Further, the Commission had introduced 8% additional surcharge in the Tariff Order
dated 23.07.2014 towards liquidation of accumulated revenue gap at the end of FY
2012-13. The expected revenue had been estimated from 8% additional surcharge
during FY 2014-15 was Rs. 67.23 Crore which will be adjusted in the Truing up of
ARR of FY 2014-15 against Revenue Gap, if any, of the Petitioner.
4.110 In view of the above, the Commission has decided that carrying cost on account of
accumulated revenue gap is not required to be allowed in the ARR for FY 2015-16.
Therefore, the Commission has not considered any amount of carrying cost in the
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 93
September 2015
ARR of FY 2015-16 of the Petitioner.
Aggregate Revenue Requirement (ARR)
4.111 Based on the detailed analysis of the cost parameters of the ARR, the Commission
has considered the ARR for FY 2015-16 as given in the Table below:
Table 4.48: Approved Aggregate Revenue Requirement for FY 2015-16 (Rs. Crore)
Sl. No.
Particulars Petitioners Projections
Now Approved
Reference
A Power Purchase Cost 875.45 926.53 Table 4.28
B O&M Expenses 145.09 164.92 Table 4.32
C Administrative Department & Civil Engineering Department Expenses
45.37 0.00
D Depreciation 40.08 17.70 Table 4.37
E Return on Capital Employed (RoCE) 89.89 28.34 Table 4.45
F Sub-total 1195.88 1137.49 Sum (A to E)
G Less: Non-tariff income 7.58 7.58 Table 4.47
H Aggregate Revenue Requirement 1188.30 1129.92 H=F-G
I Carrying Cost 64.86 0.00
J Aggregate Revenue Requirement (including Carrying Cost)
1253.16 1129.92 J=H+I
4.112 The Commission therefore approves Aggregate Revenue Requirement of Rs.1129.92
Crore for FY 2015-16.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 94
September 2015
A5: Tariff Design
Components of Tariff Design
5.1 The Commission has considered the following components for tariff designing of the
petitioner.
a. Cross-subsidization in tariff structure
b. Cost of Service
c. Consolidated Sector Revenue Gap/(Surplus)
Consolidated Revenue (Gap)/ Surplus for NDMC till FY 2013-14
5.2 The Commission has approved the revenue (gap)/surplus for the Petitioner for FY
2013-14 (as discussed in detail in Chapter A3 of this Order) as summarised in the
Table as follows:
Table 5.1: Net Revenue (Gap)/ Surplus of NDMC for FY 2013-14 (Rs. Crore)
Sl. No.
Particulars Earlier
Approved FY 2012-13
Now approved
FY 2012-13 FY 2013-14
1 Closing (Gap) to end of FY 2012-13 (148.87) 155.01 165.19
2 Revenue requirement for the year 1015.58 1015.58 1034.09
3 Revenue at the existing tariff 866.09 866.09 900.83
4 (Gap) / Surplus for the year (2-3) (149.49) (149.49) (133.26)
5 Adjustment during the year 140.34
6 Net (Gap) / Surplus for the year (4+5) (149.49) (9.15) (133.26)
7 Closing (Gap)/Surplus (324.08) 145.86 31.94
8 Rate of carrying cost for the year 11.50% 12.85% 12.85%
9 Carrying cost (1*7)+((6*7)/2) (25.72) 19.33 12.67
10 Closing balance of (Gap) / Surplus at the end of the year (1+6+8)
(324.08) 165.19 44.60
5.3 It can be seen from the above that the accumulated revenue surplus till FY 2013-14
for NDMC is Rs 44.60 Crore.
Revenue (Gap)/ Surplus for FY 2015-16 at Existing Tariffs
5.4 The Summary of net revenue (gap)/ surplus approved for NDMC at existing
tariffs for the current year, FY 2015-16 is as follows:
Table 5.2: Approved Revenue Gap for FY 2015-16 at existing Tariff (Rs. Crore)
Particulars FY 2015-16
Revenue Requirement for the year (incl. carrying cost) 1129.92
Revenue available at existing tariffs (incl. PPAC) 1123.39
(Gap)/ Surplus for the year (6.54)
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 95
September 2015
Treatment of Revenue (Gap)/Surplus
Petitioner’s Submission
5.5 The revenue deficit for FY 2015-16 as submitted by the Petitioner is Rs. 365.64 Crore
at existing tariff. The Petitioner projected gross gap of Rs. 636.56 Crore as on
31.03.2014. The Petitioner proposed an increase of 37.39% flat tariff increase for
different categories of consumer to get additional revenue of Rs. 365.64 Crore
during FY 2015-16. The Petitioner has not submitted any proposal for liquidation of
closing gap upto FY 2013-14.
Commission’s analysis
Revenue (Gap)/Surplus at Existing and Revised Tariffs
5.6 The summary of revenue billed at existing tariffs for NDMC for FY 2015-16 is as
follows:
Table 5.3: Revenue at existing and revised tariffs for FY 2015-16 (Rs. Crore)
Category Revenue Billed
Domestic 147.16
Non Domestic
Supply on Low Tension 239.11
Supply on 11kV 644.53
Small Industrial Power 0.17
Public Lighting 5.90
DMRC 23.27
Others 20.03
Total 1080.18
Revenue from 8% surcharge for 6 months 43.21
Total Revenue Realized @ 100% Collection Efficiency
1123.39
5.7 The Commission has revised the tariff with effect from 01.10.2015.
5.8 The Commission observes that the Revenue surplus till FY 2013-14 is Rs. 44.60 Crore,
while revenue gap for FY 2015-16 is Rs. 6.54 Crore at existing tariff. The surcharge
approved by the Commission in the last Tariff Order collected by the Petitioner will
enable them to generate additional revenue of Rs. 43.21 Crore for FY 2015-16.
5.9 The impact of past true-up upto FY 2013-14 has resulted into a revenue surplus at
the end of FY 2013-14. Since there is only minimal revenue gap projected during FY
2015-16 which will be offset against the current surplus available at the end of FY
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 96
September 2015
2013-14. Therefore, the Commission decides that there is no need to levy 8%
surcharge in the area of NDMC.
5.10 The Commission is also encouraging the Petitioner to take various DSM measures
which would have the impact of reducing the peak demand of Delhi and
consequently reduction in the purchase of costly peak power.
5.11 Considering the factors listed above, the Commission has decided not to increase the
tariff in FY 2015-16.
5.12 Further, the Commission in this Tariff Order has made an effort to reduce the
prevailing cross subsidy level in the existing tariff structure. The prevailing tariff
structure in Delhi contains a large degree of cross subsidy, with some categories of
consumers paying well above the cost of supply. It has to be recognized that low and
subsidised tariffs initiate inefficient high demand for power, which puts pressure on
the system capacity and the quality of service. As per Section 61(g) of the Electricity
Act 2003, the tariff should progressively reflect the cost of supply of electricity
and also reduce and eliminate cross-subsidies within the period to be specified by
the Commission.
Cross-Subsidization in Tariff Structure
5.13 The Electricity Act, 2003 provides for reduction of cross subsidies by moving the
category wise tariffs towards cost of supply. The Commission also recognizes the
need for reduction of cross subsidy. However, it is equally incumbent on the
Commission to keep in mind the historical perspective for the need to continue with
cross-subsidy for some time.
5.19 Regarding cross subsidy, clause 8.3 of the National Tariff Policy states,
“… Direct subsidy is a better way to support the poorer categories of consumers
than the mechanism of cross subsidizing the tariff across the board. Subsidies
should be targeted effectively and in transparent manner. As a substitute of
cross subsidies, the State Government has the option of raising resources
through mechanism of electricity duty and giving that subsidy to only needy
consumers. This is a better way of targeting subsidies effectively.”
5.14 In line with the above provision of the National Tariff Policy, Regulation 8.1 of the
Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 97
September 2015
Wheeling Tariff and Retail Supply Tariff) Regulations, 2011, states that any
consumer desirous of getting subsidized tariff shall approach the appropriate
Government and if the request for subsidy is found justified, the appropriate
Government may give subsidy to that class of consumers so that these consumers
get electricity at concessional tariff.
5.15 At present, there are a number of consumer classes such as some slabs of domestic
consumers, Government Schools/Colleges, Hospitals, etc. which are being cross
subsidized by other consumers. Several stakeholders have raised serious concern
over cross subsidization of some categories and argued that electricity distribution is
purely commercial operation and there is no justification for making some
consumers pays for others. If any class of consumers is to be given concessional tariff
on socio-economic ground, the State Government shall bear the cost on this count as
supporting weaker sections of society is the responsibility of the government and
this responsibility cannot be thrust upon other sections of consumers.
5.16 The Commission is of the view that in an ideal case, electricity tariff for all
categories of consumers should be fixed on cost to serve basis. In accordance
with the Act and the policies prescribed from time to time, the Commission has
made an attempt in this Tariff Order to maintain the prevailing cross-subsidy.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 98
September 2015
Tariff Structure
Domestic Tariff
5.17 Domestic tariff is applicable for power consumption of residential consumers,
hostels of recognized/aided educational institutions and staircase lighting in
residential flats, compound lighting, lifts and water pumps or drinking water supply
and fire-fighting equipment, etc. in Cooperative Group Housing Societies (CGHS),
bona fide domestic use in farm houses, etc. as per the revised tariff schedule.
5.18 All the Cattle/ Dairy Farms and Dhobi Ghat across Delhi with a total consumption of
not more than 400 units in a month and connected load of up to 2 kW shall be
charged domestic tariff. However, in case the consumption in a month exceeds 400
units, the total consumption including the first 400 units shall be charged non-
domestic rates as applicable to the consumers falling under the Non Domestic
category.
5.19 The Commission in its Tariff Order dated June 26, 2003 introduced two part tariff for
domestic consumers, i.e., fixed charges and energy charges and abolished minimum
charges and meter rent. The fixed charge in two-part tariff represents the fixed
component of charges, which is independent of consumption level and depends on
the fixed cost incurred by the Utility in supplying electricity.
5.20 The Commission has considered the views expressed by the stakeholders and after
considering various options, the Commission proposes to continue with the existing
methodology of levying fixed charges on slab system, based on the sanctioned load
till sanctioned load of 5 kW and for sanctioned load above 5 kW, the fixed charges
shall be applicable in Rs/kW terms.
5.21 Under Domestic category, the slab above 800 units has further been changed to 801-
1200 units and above 1200 units.
Domestic single delivery point for CGHS
5.22 In last order dated July 31, 2013 the Commission has revised the slab structure for
co-operative group housing societies (CGHS) complexes and considered first 55% of
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 99
September 2015
the consumption at the rate of 201-400 units slab rate of Domestic Category, next
40% of the consumption at the rate of 401-800 units slab rate of Domestic Category,
and balance 5% of the consumption at the rate of 801 units and above slab rate of
Domestic Category.
5.23 In this order the Commission has revised the slab structure for co-operative group
housing societies (CGHS) complexes and considered first 40% of the consumption at
the rate of 201-400 units slab rate of Domestic Category, next 30% of the
consumption at the rate of 401-800 units slab rate of Domestic Category, next 20%
of the consumption at the rate of 801-1200 units slab rate of Domestic Category, and
balance 10% of the consumption at the rate of 1201 units slab rate of Domestic
Category. Further the Commission has clarified that the energy charges for
independent connection for common facilities through separate shall be billed as per
respective slabs of CGHS instead of highest of the Domestic rates as in the earlier
Tariff Schedule.
Non-Domestic Tariff
5.24 Non-domestic category of consumers comprises two sub-categories viz., Supply on
low Tension and Supply on High Tension (11 kV and above).
Non-Domestic Low Tension (NDLT)
5.25 This category covers LT Non-Domestic consumers having contract demand or
sanctioned load (whichever is applicable) up to 100 kW/108 kVA.
5.26 For the consumers with sanctioned load up to 10 kW in this category, the
Commission had specified the kWh based tariff only. The Commission has decided to
continue with the existing practice.
5.27 For Non-domestic consumers having contract demand or sanctioned load more than
10 kW (11 kVA) and up to 100 kW (108 kVA), the Commission has specified kVAh
based energy charges.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 100
September 2015
5.28 For Non-Domestic low tension (NDLT) category, the slab between 10 kW (11 kVA)
and up to 100 kW (108 kVA), the Commission has specified kVAh based energy
charges.
5.29 For Non Domestic consumers having contract demand or sanctioned load (whichever
is lower) more than 100 kW/108 kVA and up to 200 kW/215 kVA and availing supply
on LT will also be charged kVAh tariff which will be higher than tariff for non
domestic consumers having contract demand or sanctioned load more than 10 kW
and up to 100 kW/(108 kVA). This has been done in view of the fact that the lower
the voltage of supply, higher will be the system losses and hence the consumers with
connected load more than 100 kW (108 kVA) at LT voltage (400 V) have to be
discouraged.
5.30 The Commission believes that with gradual movement towards voltage linked tariff,
irrespective of load of the consumer, the tariff for consumption at higher voltages
will be lower than that for lower voltages, which will discourage consumers to opt
for LT connections particularly for loads higher than 100 kW.
5.31 For existing consumers having sanctioned load/contract demand, whichever is
applicable, in kW, the actual power factor of the consumer in the relevant billing
cycle shall be considered for converting kW to kVA for computing the fixed charges.
For new consumers, the sanctioned load/contract demand shall be in terms of kVA
only.
Non-Domestic High Tension (NDHT)
5.32 Non-domestic consumers with contract demand or sanctioned load more than 100
kW/108 kVA shall avail supply on 11 kV.
5.33 Non domestic consumers availing supply on 33 kV/66 kV or 220 kV will be entitled
for rebate of 2.5% and 4% respectively on the applicable energy charges on 11 KV
tariff.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 101
September 2015
5.34 For existing consumers having sanctioned load/contract demand, whichever is
applicable, in kW, the actual power factor of the consumer in the relevant billing
cycle shall be considered for converting kW to kVA for computing the fixed charges.
For new consumers, the sanctioned load/contract demand shall be in terms of kVA
only.
Industrial Tariff
5.35 Industrial category of consumers consists of two sub-categories, viz., Small Industrial
Power (SIP) and Large Industrial Power (LIP).
Small Industrial Power (SIP)
5.36 This category covers industrial consumers having contract demand or sanctioned
load, whichever is applicable, up to 200kW/215kVA.
5.37 For the consumers with sanctioned load up to 10 kW in this category, the
Commission had specified the kWh based tariff only. The Commission has decided to
continue with the existing practice.
5.38 For Small Industrial Power (SIP less than 200 kW/215 kVA) category, the slab
between 10 kW (11 kVA) up to 100 kW (108 kVA), the Commission has specified the
kVAh based tariff.
5.39 Industrial consumers having contract demand or sanctioned load more than
100 kW/108 kVA and up to 200 kW/215 kVA and availing supply on LT will also be
charged kVAh tariff which will be higher than the tariff for Industrial consumers
having contract demand or sanctioned load more than 11 kVA and up to 108 kVA.
This has been done in view of the fact that lowers the voltage of supply, higher the
system losses and hence consumers with connected load more than 108 kVA at LT
voltage (415 V) have to be discouraged.
5.40 For existing consumers of 10 kW and above having sanctioned load/contract
demand, whichever is applicable, in kW, the actual power factor of the
consumer in the relevant billing cycle shall be considered for converting kW to kVA
for computing the fixed charges. For new consumers, the sanctioned load/contract
demand shall be in terms of kVA only.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 102
September 2015
Large Industrial Power (LIP)
5.41 Industrial consumers with contract demand or sanctioned load more than 108 kVA
shall avail supply on 11 kV.
5.42 The Commission believes that with gradual movement towards voltage linked tariff,
irrespective of load of the consumer, the tariff for consumption at higher voltages
will be lower than that for lower voltages, which will discourage consumers to opt
for LT connections particularly for loads higher than 100 kW.
5.43 For supply at 33/66 kV, consumers will get a rebate of 2.5% on the energy charges
applicable for supply at 11 kV and a rebate of 4% for supply at 220 kV.
5.44 For existing consumers having sanctioned load/contract demand, whichever is
applicable, in kW, the actual power factor of the consumer in the relevant billing
cycle shall be considered for converting kW to kVA for computing the fixed charges.
For new consumers, the sanctioned load/contract demand shall be in terms of kVA
only.
Agriculture
5.45 Agriculture connections are available for tube wells for irrigation, threshers and
kutty cutting in conjunction with pumping load for irrigation purpose for loads up to
Mushroom Cultivation
5.46 This category is applicable to the consumers who are engaged in mushroom
cultivation/processing.
Public Lighting
5.47 Tariff for this category is applicable to all street light consumers including MCD, DDA,
PWD/CPWD, CGHS, Slums, DSIIDC and certain civilian pockets of MES. The share of
MCD, however is dominating as most of the street lights in the city are owned by the
MCD.
5.48 The Commission has decided that tariff for public lighting which is metered will be
lower than tariff for public lighting which is unmetered. Therefore, the Commission
has prescribed different tariff for metered and unmetered public lighting.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 103
September 2015
5.49 As regard to the maintenance charges for street lighting, the Commission would like
to clarify that the maintenance charges and other conditions of maintenance of
street lights as approved in the Commission’s Order dated September 22, 2009 will
continue till such time it is amended. Further, it is to clarify that the maintenance
charges are exclusive of applicable taxes and duties.
Railway Traction
5.50 This category is applicable to Indian Railways for traction purposes for loads more
than 100 kW/108 kVA.
DMRC
5.51 This category is available to Delhi Metro Rail Corporation (DMRC) to run its
operations (other than construction projects).The Commission has decided to
increase the applicable energy charges for DMRC to meet the cost of supply. The
commercial load at DMRC stations shall be metered and billed separately as per the
relevant tariff category.
Advertisement and Hoardings
5.52 The Commission, in its last Tariff Order dated July 31, 2013 has created a separate
category to cover the consumption for the advertisements and Hoardings. This
category will be applicable for supply of electricity for lighting external
advertisements, external hoardings and displays at departments stores, malls,
multiplexes, theatres, clubs, hotels, bus shelters, Railway/Metro Stations, Airport
and shall be separately metered and charged at the tariff applicable for
“Advertisements and Hoardings‟ category, except such displays which are for the
purpose of indicating/displaying the name and other details of the shop, commercial
premises itself. Such use of electricity shall be covered under the prevailing tariff for
such shops or commercial premises.
Temporary Supply
5.53 The Commission does not propose any change in the existing tariff methodology for
temporary supply as mentioned in the Tariff Schedule.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 104
September 2015
Time of Day (ToD) Tariff
5.54 It is observed that the cost of power purchase during peak hours is quite high. Time
of Day (ToD) tariff is an important Demand Side management (DSM) measure to
flatten the load curve and avoid such high cost peaking power purchases.
Accordingly, the Commission had introduced Time of Day (ToD) tariff wherein peak
hour consumption is charged at higher rates which reflect the higher cost of power
purchase during peak hours. At the same time, a rebate is being offered on
consumption during off-peak hours. This is also meant to incentivise consumers to
shift a portion of their loads from peak time to off-peak time, thereby improving the
system load factor and flatten the load curve. The ToD tariff is aimed at optimizing
the cost of power purchase, which constitutes over 80% of the tariff charged from
the consumers. It also assumes importance in the context of propagating and
implementing DSM and achieving energy efficiency. This is important in Delhi
situation where wide variations in load especially in summer causes problem of
shortages during Peak hours and surplus during off peak hours.
5.55 Introduction of higher peak hour tariff would initially generate additional revenue
which would compensate for the reduction in revenue on account of lower tariff
during off-peak hours.
5.56 In the long run, this would provide signals to the consumers to reduce load during
peak hours and, wherever possible, shift this consumption to off-peak hours. Any
loss of revenue to the utility on account of shifting of load from peak to off-peak
hours in the long run would by and large get compensated by way of reduction of
off-peak surplus to the extent of increase in off-peak demand.
5.57 The ToD Tariff would thus have immediate as well as long term benefits for both,
consumers as well as the utility and contribute towards controlling the rise in power
purchase costs.
5.58 The Commission in its MYT Order for second Control Period dated July 13, 2012 had
decided to introduce ToD Tariff on a pilot basis for large industrial and non domestic
consumers (300 kW and above). This was targeted to the consumer segment which
has capacity to bear a higher burden for peak hour consumption and also at least
partly (if not fully) offset the impact of this increase through higher off-peak
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 105
September 2015
consumption at lower rates. The Commission as a progressive step in this direction
and to further encourage demand shift from peak hours to off-peak hours has
decided to lower the applicability limit for ToD Tariff.
5.59 In the Tariff order dated July 31, 2013, the Time of Day (ToD) Tariff# - ToD Tariff was
made applicable on all consumers (other than domestic) whose sanctioned load/MDI
(whichever is higher) is 100 kW / 108 kVA and above.
5.60 In the Tariff order dated July 23, 2014, the Time of Day (ToD) Tariff# - ToD Tariff was
made applicable on all consumers (other than domestic) whose sanctioned load/MDI
(whichever is higher) is 50kW / 54 kVA and above. Also Optional TOD tariff was made
available for all consumers (other than domestic) whose sanctioned load/MDI
(whichever is higher) was between 25kW/27kVA to 50kW/54kVA.
5.61 In this Tariff Order, the Commission has decided changes in Time of Day (ToD) Tariff#
as follows:
a) TOD tariff shall be applicable on all consumers (other than Domestic) whose
sanctioned load/MDI (whichever is higher) is 25kW/27kVA and above as shown in
the table below.
b) Option of TOD tariff shall also be available for all consumers (other than Domestic)
whose sanctioned load/MDI (whichever is higher) is 11kW/12kVA to 25kW/27kVA.
If the consumer who has opted for TOD of sanctioned load between 11kW/12kVA
to 25kW/27kVA, the charges for up-gradation of meters , if any, shall be borne by
respective consumers.
c) The Commission has decided to reduce the Rebate during the Off Peak hours from
25% to 20% whereas for Peak hours Surcharge shall continue at 20%. Optional
ToD Consumers will have the option to move back to non-ToD regime only once
within one Financial Year.
d) The Commission has reviewed the ToD time slots as per the suggestions/
comments received from various stakeholders including GoNCTD and the latest
available trend for demand and supply of power. It is observed that during the
months of October - April, the maximum demand is less than the available base
supply of power. Accordingly, the revised the time slots for Peak and Off-Peak
hours is as follows:
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 106
September 2015
# For other than peak and off-peak hours, normal energy charges will be applicable. Note: The additional impact due to ToD tariff on the bill received by the management of commercial complexes may be recovered by the SPD manager by spreading this component of tariff on pro-rata basis on the users of the complex.
Months Peak Hours Surcharge on
Energy Charges Off-Peak Hours
Rebate on Energy Charges
May- September
1300-1700 hrs and
2100-2400 hrs 20% 0300-0900 hrs 20%
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 107
September 2015
TARIFF SCHEDULE: Sl.
No. CATEGORY FIXED CHARGES1 ENERGY CHARGES2
1 DOMESTIC
1.1 INDIVIDUAL CONNECTIONS
0-200 units 20 Rs /kW/month 325 Paisa/kWh
201-400 units 20 Rs /kW/month 460 Paisa/kWh
401-800 units 20 Rs /kW/month 600 Paisa/kWh
801-1200 Units 20 Rs /kW/month 675 Paisa/kWh
Above 1200 Units 20 Rs /kW/month 800 Paisa/kWh
1.2 SINGLE DELIVERY POINT FOR GROUP HOUSING SOCIETY (GHS) (GHS as defined in para 1.2 of other terms & conditions of the Tariff Schedule herewith)
Supply at 11kV 600 Paisa/kWh
The Single Point Delivery Supplier (Group Housing Societies) shall charge the Domestic tariff as per slab rate of 1.1 to its Individual Members. Any Deficit/Surplus due to sum total of the billing to the Individual Members as per slab rate of tariff schedule 1.1 and the billing as per the tariff schedule 1.2 including the operational expenses of the Single Point Delivery Supplier shall be passed on to the members of the Group Housing Societies on pro rata basis of consumption.
2 NON-DOMESTIC
2.1 Non- Domestic (Low Tension) up to 100kW/108KVA
A Up to 10 kW 75 Rs/kW/month 760 Paisa/kWh
B Between 10 kW/11kVA - 140 kW/150 kVA 90 Rs/kVA/month 805 Paisa/kVAh
C Greater than 140 kW / 150 kVA (400 volts)
(No Supply on LT for load > 200kW/215 kVA)
i Where supply is given from NDMC sub-station
150 Rs/kVA/month 835 Paisa/kVAh
ii Where applicant provides built up space for sub-stations
135 Rs/kVA/month 785 Paisa/kVAh
2.2 Non-Domestic High Tension (NDHT)
For supply at 11 KV and above (for load greater than 100kW/108 kVA)
125 Rs/kVA/month 715 Paisa/kVAh3
The Single Point Delivery Supplier shall charge the NDHT tariff to its LT consumers and in addition shall be entitled to charge an extra upto 5% of the bill amount at NDHT tariff to cover losses and all it’s expenses.
3 SMALL INDUSTRIAL POWER (SIP) 5
50 Rs/kW/month 695 Paisa/kVAh
4 PUBLIC LIGHTING
4.1 Metered
A Street Lighting4 730 Paisa/kWh
B Signals and Blinkers 730 Paisa/kWh
4.2 Unmetered
A Street Lighting4 780 Paisa/kWh
B Signals and Blinkers 780 Paisa/kWh
5 RAILWAY TRACTION 150 Rs/kVA/month 680 Paisa/kVAh3
6 DELHI METRO RAIL CORPORATION (DMRC) 3
DMRC (Supply at 220 kV and 66 kV) 125 Rs/kVA/month 610 Paisa/kVAh3
7 ADVERTISEMENTS AND HOARDINGS 500 Rs/month/hoarding 1120 Paisa/kVAh
8 TEMPORARY SUPPLY
8.1 For a total period of
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 108
September 2015
Notes on Superscripts 1. For all categories other than Domestic, Fixed/demand charges are to be levied on billing demand on per
kW/kVA or part thereof, basis. Where the MDI reading exceeds sanctioned load/contract demand a
surcharge of 30% shall be levied on the fixed charges corresponding to excess load in kW/kVA for such
billing cycle only. Wherever, sanctioned load/ contract demand is in kW/HP, the kVA shall be calculated
on basis of actual power factor of the consumer, for the relevant billing cycle.
2. Time of Day (TOD) Tariff#
a. TOD tariff shall be applicable on all consumers (other than Domestic) whose sanctioned
load/MDI (whichever is higher) is 25kW/27kVA and above as shown in the table below.
b. Option of TOD tariff shall also be available for all consumers (other than Domestic) whose
sanctioned load/MDI (whichever is higher) is 11kW/12kVA to 25kW/27kVA. If the consumer
who has opted for TOD of sanctioned load between 11kW/12kVA to 25kW/27kVA, the
charges for up-gradation of meters , if any, shall be borne by respective consumers.
c. The Commission has decided to reduce the Rebate during the Off Peak hours from 25% to
20%, whereas, for Peak hours Surcharge shall continue at 20%. Optional ToD Consumers will have
the option to move back to non-ToD regime only once within one Financial Year.
d. Further, the Commission has reviewed the latest available Demand and Supply of Delhi and has
revised the time slots for Peak and Off-Peak hours as follows:
# For other than Peak and Off-Peak hours normal Energy Charges shall be applicable.
Note: The additional impact due to ToD tariff on the bill received by the management of commercial
complexes may be recovered by the Single Point Delivery (SPD) manager by spreading this component of tariff
on pro-rata basis on the users of the complex.
3. Additional rebate of 2.5% on the Energy Charges for supply at 33/66 kV and 4% for supply at 220 kV
shall be admissible.
4. Maintenance Charges on street lights would be additional to the specified tariff @ Rs. 84/light
point/month and material cost at the rate of Rs.19/light point/month as per the Commission’s Order
dated 22 September 2009 till further Orders. These charges will be payable to the DISCOM only if
A
Less than 16 Days 50% of the relevant category other than
Domestic
Higher by 30% (Temporary Surcharge) of the relevant category
other than Domestic
B More than or equal to 16 days Same as that of relevant
category Higher by 30%
(Temporary Surcharge) of the relevant category
8.2 For Residential Group Housing connections and other Residential connections
Same as that of relevant category without
Temporary Surcharge
Same as Domestic Category without
Temporary Surcharge
8.3 For religious functions of traditional and established characters and cultural Activities
Same as Domestic Category
Same as Domestic Category without
Temporary Surcharge
8.4 For Construction projects Same as that of relevant
category Higher by 30%
(Temporary Surcharge) of the relevant category
Months Peak Hours Surcharge on
Energy Charges Off-Peak Hours
Rebate on Energy Charges
May-September 1300-1700 hrs
and 2100-2400 hrs
20% 0300-0900 hrs 20%
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 109
September 2015
maintenance services are provided by the DISCOM and these are exclusive of applicable taxes and
duties.
5. The Tariff Schedule under category 3 shall be applicable to Industrial consumers having valid Factory License.
Note:
(i) The distribution licensee shall levy PPAC after considering rebate/surcharge on
energy charges available to the customers.
(ii) In case of prepaid consumers, the rebate is applicable on the basic Energy Charges,
Fixed Charges and all other charges should be calculated on the tariff applicable
after rebate.
(iii) Individual Consumers availing the supply at single delivery point through Group
Housing Society, shall claim the benefit of subsidy, applicable if any, as per the
Order of GoNCTD. Group Housing Society shall submit the details of eligible
consumers with consumption details and lodge claim of subsidy on behalf of
individual members from NDMC.
(iv) The commercial consumers of DMRC who have sanctioned load above 215 kVA but
served at LT (415 Volts) such consumers shall be charged the tariff applicable to
Non-domestic LT (NDLT) category greater than 100kW/108kVA (415 Volts).
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 110
September 2015
Other Terms and Conditions of the Tariff
Sl. No. Category Availability Character of
Service
1. Domestic 1.1 Domestic Lighting/Fan and Power (Single Delivery Point and Separate Delivery Points/Meters)
A) Available to following categories of consumers a. Residential consumers b. Hostels of recognized/
aided institutions which are being funded more than 90% by Municipal Corporation of Delhi or Government of the NCT of Delhi or any other Government/local bodies [local bodies include NDMC and MCDs (North, South & East)].
c. Staircase lighting in residential flats separately metered.
d. Compound lighting, lifts and water pumps etc., for drinking water supply and fire-fighting equipment in residential complexes, if separately metered.
e. In group housing societies etc. for bonafide use of lighting/fan and power, subject to the provision that the supply is at single delivery point for combined lighting/fan & power.
B) Available to following consumers: a. Dispensary/Hospitals/
Public Libraries / School/ College/Working Women’s Hostel / Orphanage / Charitable homes run and funded by more than 90% by Municipal Corporation of Delhi or Government of the NCT of Delhi or any other Government/local bodies.
b. Small Health Centre’s approved by the Department of Health,
AC 50 Hz, single phase, 230 Volts for load up to 10 kW & AC 50 Hz, three phase, 400 Volts for loads beyond 10 kW AC 50 Hz, 3 phase, 11 kV beyond 140 kW/150 kVA
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 111
September 2015
Sl. No. Category Availability Character of
Service
Government of NCT of Delhi for providing Charitable Services only.
c. Recognized Centre’s for welfare of blind, deaf and dumb, spastic children, physically handicapped persons, mentally retarded persons, as approved by the Government of NCT of Delhi and other Government.
d. Public parks except temporary use for any other purpose.
C) Bed and Breakfast
Establishments (Residential Premises) registered u/s 3 of the National Capital Territory of Delhi (Incredible India) Bed and Breakfast Establishments (Registration & Regulations) Act, 2007.
D) Places of worship. E) Cheshire homes/orphanage F) Shelter Homes (including Night
Shelters) approved by Delhi Urban Shelter Improvement Board, GoNCTD
G) Electric crematoriums H) Professionals i.e. individuals
engaged in those activities kinvolving services based on professional skills, viz Doctor, Lawyer, Architect, Chartered Accountant, Company Secretary, Cost & Works Accountant, Engineer, Town Planner, Media Professional and Documentary Film Maker may utilize the domestic connection at their residence for carrying out their professional work in the nature of consultancy without attracting non-domestic tariff for the electricity consumed, provided the area used for
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 112
September 2015
Sl. No. Category Availability Character of
Service
professional activity does not exceed the area permitted to be used for such activity in residential area under the Master Plan for Delhi, 2021 (MPD-2021), which as per MPD-2021 is permissible on any one floor only but restricted to less than 50% of the permissible or sanctioned FAR whichever is less on that plot or dwelling unit.
I) Available, for loads up to 21 kW, to farm houses for bonafide domestic self use.
J) The consumers running small commercial establishments from their households in JJ Clusters shall be charged domestic tariff provided that the total consumption of electricity does not exceed 400 units/month.
K) Cattle / Dairy Farms / Dhobi Ghat with a total consumption of not more than 400 units/month.
1.2 Domestic Connection on 11 kV single delivery point
Same as 1.1(A) - For GHS flats and for individuals having sanctioned load above 100 kW/108kVA Group Housing Society(GHS) shall mean a residential complex owned/managed by a Group Housing Society registered with Registrar, Cooperative Societies, Delhi / registered under Societies Act, 1860 and for sake of brevity the definition shall include residential complex developed by a Developer and approved by appropriate authority.
AC 50 Hz, three phase, 11 kV; on single delivery point
2. Non-domestic 2.1 Non- Domestic (Low Tension) – NDLT
A) Available to all consumers having load (other than the industrial load) up to 140 kW/150 kVA for lighting, fan & heating/cooling power appliances in all non-domestic
AC 50 Hz, single phase, 230 Volts up to 10 kW load; AC 50 Hz, 3 phase, 400 Volts for
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 113
September 2015
Sl. No. Category Availability Character of
Service
establishments as defined below:
B) Hostels/Schools/Colleges (other than those covered under domestic category)
C) Auditoriums, Lawyer Chambers in Court Complexes, Hospitals, nursing homes / diagnostic centres other than those run by the Government of NCT of Delhi.
D) Railway's (other than traction) Hotels and restaurants
E) Cinemas F) Banks /Petrol pumps G) All other establishments, i.e.,
shops, chemists, tailors, washing, dyeing etc. which do not come under the Factories Act.
H) Cattle farms, fisheries, piggeries, poultry farms, floriculture, horticulture, plant nursery Farm houses being used for commercial activity.
I) DMRC for its commercial activities other than traction.
J) Ice-cream parlours and K) Any other category of
consumers not specified/covered in any category in this Schedule
loads above 10 kW and up to 140 kW /150 kVA.
2.2 Non-Domestic High Tension (NDHT) Non-Domestic Power on
11 kV Single Delivery Point NDHT for Commercial Complexes
A) Available to consumers having load (other than industrial load) above 100 kW/108 kVA Non- Domestic establishments including pumping loads of Delhi Jal Board /DDA/NDMC and supply to Delhi Metro Rail Corporation (DMRC) Ltd. for their on-going construction projects etc and for commercial purposes other than traction.
B) Available to commercial complexes having load more than 100kW/108kVA for group of consumers for non-domestic use
AC 50 Hz, 3 phase, 11 kV
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 114
September 2015
Sl. No. Category Availability Character of
Service
3. Industrial
Small Industrial Power (SIP)
Available to Industrial consumers with load up to 140 kW/150 kVA including lighting, heating and cooling load.
AC 50 Hz, single phase, 230 Volts; AC 50 Hz, 3 phase, 400 Volts
4. Public Lighting Street Lighting Available to all street lighting consumers including NDMC, DDA, PWD/CPWD, Slums department/DSIIDC /MES/GHS etc.
AC 50 Hz, Single /three Phase, 230/400 Volts
Signals and Blinkers
Available for traffic signals and blinkers of Traffic Police
AC 50 Hz, Single Phase, 230 Volts
5. Railway Traction (other than DMRC)
Available for railway traction for connected load above 100 kW/108kVA.
AC 50 Hz, Three phase, 220/66/33 kV
6. Delhi Metro Rail Corporation
Available to Delhi Metro Rail Corporation(DMRC) (not for construction projects)
AC 50 Hz, 3 phase, 220/66/33 kV
7. Advertisement/ Hoardings
Electricity for lighting external advertisements, external hoardings and displays at departments stores, malls, multiplexes, theatres, clubs, hotels, bus shelters, Railway/Metro Stations, airport which shall be separately metered and charged at the tariff applicable for “Advertisements and Hoardings‟ category, except such displays which are for the purpose of indicating/displaying the name and other details of the shop, commercial premises itself. Such use of electricity shall be covered under the prevailing tariff for such shops or commercial premises.
AC 50 Hz, single phase, 230 Volts for loads up to 10 kW; AC 50 Hz, 3 phase, 400 Volts for loads more than 10 kW and up to 140 kW/150 kVA
8. Temporary Supply
8.1(A) For less than 16 days
Available as temporary connection under the respective category
AC 50 Hz, single phase, 230 Volts; AC 50 Hz, 3 phase, 400 Volts; AC 50 Hz, three phase, 11 kV
8.1(B) For more than or equal to 16 days
8.2 For residential Group Housing Connections
Same as that of relevant category
8.3 For religious functions of traditional and established characters and cultural activities
Provided for religious functions of traditional and established characters like Ramlila, Dussehra, Janmashtami, Nirankari Sant Samagam, Gurupurb, Durga Puja, Eid, Christmas celebrations, Easter, Pageants and
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 115
September 2015
Sl. No. Category Availability Character of
Service
cultural activities like NCC camps, scouts & guides camps etc.
8.4 For construction projects
With loads more than 10 kW
8.5 For threshers With loads more than 10 kW
NOTE
ELECTRICITY TAXES AND OTHER LEVIES
1) The rates stipulated in the Schedule are exclusive of electricity tax and other taxes and
charges, as levied from time to time by the Government or any other competent
authority, which are payable extra.
SURCHARGE
2) All surcharges shall be levied on the basic tariff applicable to the category of use or
category of sanction, whichever has higher tariff.
PAYMENT
3) In the event of the electricity bill rendered by the licensee, not being paid in full within
the time specified on the bill, a surcharge @ 1.5% per month shall be levied. The LPSC
shall be charged for the number of days of delay in receiving payment from the
consumer by NDMC, until the payment is made in full without prejudice to the right of
NDMC to disconnect the supply after due date, in the event of non-payment in
accordance with section 56 of Electricity Act, 2003. This will also apply to temporary
connections, where payment of final bill amount after adjustment of consumption
deposit, is not made by due date.
4) The Commission directs the Petitioner, that in case the bill for consumption of
electricity is more than Rs. 4000, payment for the bill shall only be accepted by the
Petitioner by mode other than Cash. Violation of this directive shall attract penalty to
the level of 10% of total Cash collection exceeding Rs. 4000/-.
However, visually challenged consumers shall be allowed to make payment of
electricity bills for any amount through cash.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 116
September 2015
BILLING IN kVAh
5) Wherever the fixed or energy charges are specified in Paisa per kVAh, for the
purpose of billing, the kVAh as read from the meter in the relevant billing cycle shall
be used.
INTERPRETATION / CLARIFICATION
6) In case of doubt or anomaly, if any, in the applicability of tariff or in any other
respect, the matter will be referred to the Commission and Commission’s decision
thereon shall be final and binding.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 117
September 2015
A6: DIRECTIVES
6.1. The Commission directs the Petitioner to make timely payment of bills/dues to
central & state generating stations and transmission utilities. No Late Payment
Surcharge shall be allowed as a pass through in the ARR, on account of delayed
payments.
6.2. The Commission directs the Petitioner to optimise its cost of a procurement of
power. No fixed cost on account of regulated power will be allowed as a pass
through in the ARR.
6.3. If the distribution licensee purchases any expensive power to meet the demand
during any time zone for which cheaper power has been regulated due to non-
payment of dues, in such an eventuality, the cost of such expensive power
purchases will be restricted to the cost of regulated cheaper power to that extent
at the time of true up.
6.4. In case the power is regulated by DTL/Interstate Transmission Licensee due to non-
payment of their dues, then in that case the transmission charges borne by the
Petitioner besides the treatment of regulated power as detailed in above directive
will also not be allowed.
6.5. The Commission directs the Petitioner to ensure that asset capitalization takes
place within a reasonable time and the approved cost so that IDC does not increase
disproportionately. Before start of work, the utility is aware of the actual approved
cost of completion of the scheme. As a norm, the Commission would consider the
completion period indicated by the utility at the time of seeking approval of the
scheme from the Commission at the approved capital cost by the Commission. In
exceptional cases where completion of a project gets delayed or there is a change
in cost of completion beyond 15% of approved cost, for reasons beyond the
control of the utility, the utility will take prior approval of the Commission of any
additional amount that needs to be capitalized in excess of the cost of completion.
This can only be an exception but not the rule and the utility would need to justify
delay in capitalization in each case where delay and/or cost overrun takes place.
Failing this or pending receipt of satisfactory explanation, the Commission would
go by the completion period indicated in the Commission’s approval to the scheme
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 118
September 2015
and provide for IDC accordingly.
6.6. The Commission directs the Petitioner to ensure availability of power supply for
meeting the demand. The licensee shall ensure that the electricity which could not
be served due to any reason what-so-ever shall not exceed 1% of the total energy
supplied in units (kWh) in any particular month except in the case of force-majeure
events which are beyond the control of the Petitioner.
6.7. The Commission directs the Petitioner that there will be a cash limit of Rs.4000/-
while accepting billing dues from consumers. Any bill above Rs.4000/- must be paid
by any mode other than cash. This limit is also applicable in case of recovery of all
types of dues including LPSC, Misuse charges, theft charges etc. No authority in the
DISCOM is permitted to waive this condition pertaining to cash collection. Violation
of this directive shall attract penalty to the level of 10% of total Cash collection
exceeding Rs. 4000/-.
6.8. The Commission directs the Petitioner that for DMRC, Railways, DJB and DIAL, the
Security deposit charges against contract demand shall be allowed to deposit
through irrevocable bank guarantee to be renewed/revised, as and when required
depending on the billing demand as against prevailing practice of actual payment.
6.9. The Commission directs the Petitioner that RPO requirements for green power for
the year 2015-16, must be met along with requirements carried over from the
previous year, and if so required by way of purchase of REC’s from the exchange.
Non compliance of Renewable Purchase Obligation (RPO) shall attract penalty of
10% of the cost of REC for quantum of shortfall in RPO.
6.10. In case the consumer’s cheque is dishonoured, then he may be warned and given a
final opportunity for payment of cheque along with LPSC. If a second case of
dishonouring of the cheque occurs with the same consumer within next three
months, it shall be stipulated that payment in future will be received only by DD up
to a period of next six months.
6.11. The Commission has already decided to provide relief to those consumers whose
industries are non-functional for the period when it is either under shut down or
not functional and who utilize up to 5% of the sanctioned load (not available for
part use of the load), then the conversion from kW to kVA for the purpose of
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 119
September 2015
calculation of fixed charges may be done considering 0.9 power factor.
6.12. The Commission directs the distribution licensee not to undertake any transactions
relating to purchase/sale of power with their related parties without open
tendering process. If any purchases/sales are affected through agent/ middleman
or a trader other than the power exchange (s), then any trading margin paid to
such agents/ middleman or trader will also not be admissible as a pass through in
the ARR.
6.13. The Commission further directs the distribution licensee
a. to conduct a safety audit and carry out preventive maintenance as per
schedule and submit a compliance report within three months;
b. to submit the information in respect of Form 2.1 (a) as per revised format
issued by the Commission to the utilities on monthly basis latest by 21st day
of the following month;
c. to submit the compliance report of 100% metering within a month from the
issuance of the said Tariff Order.
d. to submit the Auditor’s certificate in respect of Form 2.1(a) on quarterly basis
within the following month;
e. to submit monthly report to the Commission giving details of category wise
consumer addition and their details latest by 21st day of the following month;
f. to submit monthly report to the Commission giving details of number of
connections disconnected / reconnected and their details latest by 21st day
of the following month;
g. to submit monthly report to the Commission on change of consumer
category latest by 21st day of the following month;
h. to incorporate the following information in the annual audited financial
statements:-
i. Category-wise Revenue billed and Collected,
ii. Category-wise Surcharge billed and Collected,
iii. Category-wise PPAC billed and collected,
iv. Category- wise Electricity Duty billed and collected
v. Category-wise subsidy passed on to the consumers during the financial
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 120
September 2015
year, if any,
vi. Category-wise details of the surcharge billed on account of ToD,
vii. Category-wise details of the rebate given on account of ToD,
viii. Revenue billed on account of Own Consumption,
ix. Revenue collected on account of enforcement/theft cases,
i. to submit the energy audit report in respect of their network at HT level
and above within three months;
j. to submit annual auditor certificate in respect of power purchase details of
the previous year by 30th July of the next financial year. The power
purchase invoices received upto April month of the next financial year but
pertaining to the previous year only will be considered towards power
purchase cost of the said financial year;
k. to submit the reconciliation statement in respect of power purchase
cost/Transmission cost on a quarterly basis with respective Generation/
Transmission companies;
l. to strictly adhere to the guidelines on short-term power purchase/sale of
power issued by the Commission from time to time;
m. to raise the bills for their own consumption of all their installations
including offices at the Non-Domestic tariff for actual consumption
recorded every month. The licensee may avail credit at zero tariffs to the
extent of the normative self consumption approved by the Commission at
the end of the financial year;
n. to submit the auditors’ certificate incorporating monthly bill details by 30th
June of next financial year;
o. to avoid transactions with their related parties. The Commission will not
approve any transaction for purchase/sale of power where open tendering
process has not been followed. If any purchases/sales are affected through
agent/ middleman or a trader other than the power exchange (s), then any
trading margin paid to such agents/middleman or trader will also not be
admissible;
p. to take necessary steps to restrict the cost of power procured through short
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 121
September 2015
term contracts at Rs.5 per kWh. Further in case of short term power
purchase at a rate higher than the above ceiling rate (of Rs.5 per kWh), the
impact of such purchase on total short term power purchase shall not
exceed 10 Paise /kWh during the financial year. In case the cost of power
proposed to be procured exceeds the above limits, this may be brought to
the notice of the Commission within 24 hours detailing the reasons or
exceptional circumstances under which this has been done. The
Commission reserves the right to restrict allowance to the permissible limit
if proper justification is not provided;
q. to submit the quarterly progress reports for the capital expenditure
schemes being implemented during each year of the Control Period within
15 days of the end of each quarter.
r. to submit the actual details of capitalization for each year for the Control
Period by June 30 of the following year for consideration of the
Commission. All information regarding capitalization of assets is to be
furnished in the formats prescribed by the Commission. These formats are
to be submitted along with the requisite statutory clearances/ certificates
of the appropriate authority/ Electrical Inspector, etc. as applicable for all
EHV & HV works etc., and certificate of SLDC for commissioning/
commercial operation.
s. to submit the capital expenditure schemes strictly in accordance with the
Commission’s “Guidelines for approval of Capital Investment Schemes”
dated April 23, 2012.
t. to ensure that the petitions are filed in the prescribed format.
u. to maintain segment wise audit report for each identifiable business
segment other than the regulated business in the audited financial
statement of the Petitioner.
6.14. Save and except the penalty as specifically provided in these directives, in all other
cases, the Petitioner shall be liable to pay penalty, at the rate of Rs. 1 lakh for
violation of any of the directions or part thereof. In addition, the Petitioner shall
also be liable to pay a penalty at the rate of Rs 10,000 per day for each day of delay
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 122
September 2015
with respect to the time schedule stated herein above.
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 123
September 2015
Annexure-I
Admission Order dated 03.03.2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 124
September 2015
Annexure-II
Hindustan Times (English) dated 17th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 125
September 2015
Times of India, 17th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 126
September 2015
Hindustan (Hindi) dated 17th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 127
September 2015
Milap (Urdu) dated 17th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 128
September 2015
Quami Patrika (Punjabi) dated 17th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 129
September 2015
Annexure-III
Hindustan Times (English) dated 08th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 130
September 2015
The Hindu (English) dated 08th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 131
September 2015
The Pioneer (English) dated 08th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 132
September 2015
Times of India (English) dated 08th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 133
September 2015
Dainik Jagaran (Hindi) dated 08th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 134
September 2015
Jadid in Dinon (Urdu) dated 08th March 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 135
September 2015
Quami Patrika (Punjabi) dated 08th March 2015
f
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 136
September 2015
Annexure-IV
Hindustan Times dated 07th April, 2015
The Hindu dated 10th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 137
September 2015
Times of India dated 07th April, 2015
Dainik Jagaran dated 10th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 138
September 2015
Jadid in Dinon dated 07th April, 2015
Quami Patrika dated 10th March, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 139
September 2015
Annexure-V
Times of India dated 07th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 140
September 2015
Hindustan Times dated 07th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 141
September 2015
Hindustan (Hindi) dated 07th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 142
September 2015
Daily Educator, New Delhi (Punjabi) dated 07th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 143
September 2015
Milap (Urdu) dated 07th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 144
September 2015
Amar Ujala (Hindi) dated 07th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 145
September 2015
Annexure VI
Times of India dated 18th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 146
September 2015
Hindustan Times dated 18th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 147
September 2015
Hindustan (Hindi) dated 18th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 148
September 2015
The Educator, New Delhi (Punjabi) dated 18th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 149
September 2015
Daily Milap (Urdu) dated 18th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 150
September 2015
Amar Ujala (Hindi) dated 18th April, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 151
September 2015
Annexure-VII
The Hindu (English) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 152
September 2015
The Pioneer (English) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 153
September 2015
Hindustan Times (English) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 154
September 2015
Navbharath Times (Hindi) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 155
September 2015
Dainik Jagaran (Hindi) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 156
September 2015
Quami Patrika (Punjabi) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 157
September 2015
Pratap (Urdu) dated 23rd July, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 158
September 2015
Annexure-VIII
The Hindu dated 01st August, 2015
The Pioneer dated 1st August, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 159
September 2015
The Hindustan Times dated 01st August, 2015
Dainik Jagaran dated 01st August, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 160
September 2015
Nav Bharat Times dated 01st August, 2015
Quami Patrika dated 01st August, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 161
September 2015
Quami Patrika dated 01st August, 2015
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 162
September 2015
Annexure-IX
LIST OF RESPONSES RECEIVED FROM STAKEHOLDERS ON THE TRUE UP OF EXPENSES UP TO FY 2013-14, REVIEW AND PROVISIONAL TRUE UP FOR FY 2014-15 AND ANNUAL REVENUE REQUIREMENT (ARR) FOR FY 2015-16.
S. No. R.
No. Name Address Category
Company/ Licensee
Date of Receipt
No. of
Pages
1. 1
Sh. Vinod Kumar
East Sagar Pur, New Delhi 110 046 [email protected]
Domestic
BRPL
11.03.2015
02
2. 2 Sh. Shish Pal [email protected] Domestic DISCOMs 16.03.2015 01
3. 3 Ms. Yashoda Singh
[email protected] Domestic DISCOMs 16.03.2015 01
4. 4 Sh. P.C. Gupta
[email protected] Domestic DISCOMs 16.03.2015 02
5. 5 Sh. Rudranand Thakur
Indian Institute of Public Adminstration C-103, IIPA CGHS Ltd. Dwarka, Sector 6, Plot No. 26 Delhi
Domestic DISCOMs 17.03.2015 01
6.
6
6A
Sh. Ashok Bhasin Sh. Ashok Bhasin
North Delhi Resident’s Welfare Federation 1618, Main Chandraval Road, Delhi 110 007 [email protected] North Delhi Resident’s Welfare Federation 1618, Main Chandraval Road, Delhi 110 007 [email protected]
RWA DISCOMs 17.03.2015 02
7. 7 Sh. S.K. Goel
153 Sandesh Vihar Pitampura, Delhi 110 034 [email protected]
Domestic DISCOMs 15.03.2015 05
8. 8 Sh. B.S. Sachdev President
Akhil Bhartiya Grahak Panchyat 45, North Avenue New Delhi 110 001 [email protected] [email protected]
RWA DISCOMs 19.03.2015 02
9. 9 Sh. Ashok Gupta President
Udyog Nagar Factory Owners Association unfoa_office
Domestic BRPL 19.03.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 163
September 2015
10. 10 Sh. Ajay Kumar
J-12/35, Rajouri Garden, New Delhi 110 027 [email protected]
Domestic BRPL 20.03.2015 02
11. 11 Dr. N.K. Garg Chairman
Maharaja Agrasen Technical Education Society Keshav Kunj, 10/4 East Punjabi Bagh, Delhi 110 026 [email protected]
Industrial/ Commercial
DISCOMs 23.03.2015 02
12. 12 Sh. Suresh Kamara
H.No. 2286, Hudson Lane, G.T.B. Nagar, Kingsway Camp Delhi 110 009 [email protected]
Domestic TPDDL 23.03.2015 04
13. 13 Sh. Deepak Rana
[email protected] Domestic TPDDL 23.03.2015 01
14. 14 General Manager
Mother Dairy Fruit & Vegetable Pvt. Ltd. Mother Dairy Patparganj, Delhi 110 092 [email protected]
Industrial/ Commercial
DISCOMs 23.03.2015 01
15. 15 Sh. Vijender Singh Verma
B-56, Sunder Apartment Sector 14, Rohini Delhi 110 085
Domestic TPDDL 24.03.2015 04
16. 16 Sh. Mahendra Gupta
DU-131, Pitampura, Delhi 110 034 [email protected]
Domestic TPDDL 24.03.2015 04
17. 17 Sh. Kuldeep Kumar Jain
C-9, Ahinsa Vihar, Sector-9, Rohini, Delhi 110 085 [email protected]
Domestic TPDDL 26.03.2015 02
18. 18 Sh. Anil Kumar Sharma
Flat No. D32, Delhi Citizen Society Sector-13, Rohini Delhi 110 085
Domestic TPDDL 26.03.2015 03
19. 19 Sh. Surender Babar Secretary
DVB Employees Terminal Benefit Fund 2002 (Pension Trust) Rajghat Power House Complex, New Delhi – 110 002.
Government
DISCOMs 27.03.2015 17
20. 20 Sh. Rajinder Lal Kapoor
[email protected] Domestic DISCOMs 27.03.2015 01
21. 21 Sh. Mahesh Chandra Gurani
170/C-9, Sector -7 , Rohini, Delhi 110 085 [email protected]
Domestic TPDDL 31.03.2015 04
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 164
September 2015
22. 22
Sh. Ram Phal Mangal Gen. Secretary
Keval Park Agarwal Sabha A-244/1, Shivaji Marg, Keval Park, Azadpur, Delhi 110 033
NGO TPDDL 01.04.2015 03
23. 23 Sh. Nanak Chand Mallah President
DVB Pensioners Association (Regd.) Rajghat Power House, New Delhi 110 002
Domestic
DISCOMs 01.04.2015 02
24. 24 Sh. L.D. Takhtani
E-350. Ramesh Nagar, New Delhi 110 015
Domestic DISCOMs 06.04.2015 07
25. 25 Sh. Shiv Kumar
H. NO. 20A, Shahpur Jat New Delhi 110049
Domestic DISCOMs0 06.04.2015 08
26. 26 Sh. Avtar Singh Chandhok
BQ-160, 2nd
Floor, Shalimar Bagh, New Delhi 110 088
Domestic DISCOMs 06.04.2015 09
27. 27 Sh. Naved Yar Khan
House No. 5182 Ballimaran, Chandni Chowk New Delhi 110 006
Domestic DISCOMs 06.04.2015 08
28. 28 Sh. C.L. Raw 2002 Tirthankar Nagar, New Delhi 110 081
Domestic DISCOMs 06.04.2015 08
29. 29 Sh. S.L. Diwan
E-25, Masjid Moth Greater Kailash-III New Delhi 110 048
Domestic DISCOMs 06.04.2015 09
30. 30 Sh. M.L. Sharma
D-224, Ashok Vihar, New Delhi 110 052
Domestic DISCOMs 06.04.2015 09
31. 31 Sh. D.D. Gupta
4/32 A, East Punjabi Bagh, New Delhi 110 026
Domestic DISCOMs 06.04.2015 07
32. 32 Ms. P.S. Sharda
109, M.M. House, 59, Rani Jhansi Road, New Delhi 110 055
Domestic DISCOMs 06.04.2015 07
33.
33
33A
Sh. Sarbajit Roy National Convener Sh. Sarbajit Roy National Convener
B-59, Defence Colony New Delhi 110 024 B-59, Defence Colony New Delhi 110 024 [email protected]
Domestic
Domestic
DISCOMs
DISCOMs
06.04.2015
29.04.2015
01
01
34. 34 Sh. Rohit Sharma Advocate
Supreme Court of India C-99, East of Kailash New Delhi 110 065 [email protected]
Domestic TPDDL 06.04.2015 01
35. 35 Sh. Inderjeet Singh
[email protected] Domestic DISCOMs 06.04.2015 01
36. 36 Sh. Kartik Singh
[email protected] Domestic DISCOMs 16.03.2015 01
37. 37 Sh. Ashok Deshpande
[email protected] Domestic DISCOMs 16.03.2015 01
38. 38 Sh. Ishwar Dutt Kashyap
[email protected] Domestic DISCOMs 16.03.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 165
September 2015
39. 39 Sh. Yogesh Kumar
[email protected] Domestic DISCOMs 16.03.2015 01
40. 40 Sh. Mohan Singh
[email protected] Domestic DISCOMs 16.03.2015 01
41. 41 Sh. M.L. Khan Extn. J3/49, Krishan Kunj, Laxmi Nagar, New Delhi 110 092
Domestic DISCOMs 07.04.2015 07
42. 42 Sh. Kharati Lal Juneja
Quarter No. 20, Hakikat Nagar, Delhi 110 009
Domestic DISCOMs 07.04.2015 03
43. 43. Sh. Anil Kumar Bajpai
AC-61, Gandhi Nagar, Vidhan Sabha
Domestic DISCOMs 07.04.2015 01
44. 44 Sh. Adarsh Shastri
Dwarka Domestic DISCOMs 07.04.2015 01
45. 45 Ms. Bhavna Gaur
Palam, AC-37 Domestic DISCOMs 07.04.2015 01
46. 46 Sh. Rituraj Govind MLA
H.No. 6, Surat Vihar, Mubarakpur Dabas Kirari
Domestic DISCOMs 07.04.2015 01
47. 47 Sh. Akhilesh Pati Tripathi MLA
Model Town, AC-18, N-25/A-277 Lal Bagh Azadpur, Delhi 110 033
Domestic DISCOMs 07.04.2015 01
48. 48 Sh. Fatesingh A/C-68, Gokal Pur Domestic DISCOMs 07.04.2015 01
49. 49 Sh. Amanat Ullah Khan MLA
AC-54, Okhla Domestic DISCOMs 07.04.2015 02
50. 50 Sh. Rajeshi Rishi
E-3/5 & 6, Chankakya Place-I Pankha Road, Janakpur, New Delhi 110 059
Domestic DISCOMs 07.04.2015 01
51. 51
Sh. Pawan Kumar Sharma MLA
A-13, Street No. 36, Adarsh Nagar Mahendra Park
Domestic DISCOMs 07.04.2015 01
52. 52 Sh. S.K. Bagga MLA
12/46, Geeta Colony Delhi 110 031
Domestic DISCOMs 07.04.2015 01
53. 53
Sh. Dhananjay Kumar Mishra Energy Controller
10, Tower-B, 9th
Floor, DLF Cyber City, Gurgaon-122 002
Industrial/ Commercial
DISCOMs 07.04.2015 26
54. 54
Sh. Tej. B, Khattar Vice President
The Mother Dairy Employee CGHS Ltd. Plot No. 6, Sector, 5 Dwarka, New Delhi 110 075 [email protected]
Domestic DISCOMs 07.04.2015 19
55. 55 Sh. Jagdish Kumar
D-2/44, Janakpuri, New Delhi 110 058 [email protected]
Domestic DISCOMs 16.03.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 166
September 2015
56. 56 Sh. Jarnail Singh MLA
Tilak Nagar Domestic DISCOMs 08.04.2015 01
57. 57 Sh. S.S. Dalal MLA
Mundka Domestic DISCOMs 08.04.2015 01
58. 58 Sh. Avtar Singh Kalra
Vidhan Sabha Kalkaji
Domestic DISCOMs 08.04.2015 01
59. 59 Sh. Naresh Yadav MLA
Mehrauli Domestic DISCOMs 07.04.2015 01
60. 60 Sh. Gulab Singh MLA
Matiyalal Domestic DISCOMs 06.04.2015 01
61.
61
61A
61B
Sh. Rajiv Kakria Co Chairman Sh. Rajiv Kakria Sh. Rajiv Kakria
E-230, Greater Kailash-1, New Delhi 110 048 E-230, Greater Kailash-1, New Delhi 110 048 E-230, Greater Kailash-1, New Delhi 110 048 [email protected]
RWA
RWA
RWA
DISCOMs
DISCOMs
DISCOMs
13.04.2015
13.04.2015
17.04.2015
03
04
03
62. 62 Sh. Nitin Tyagi MLA
Laxmi Nagar, AC-58
Domestic DISCOMs 10.04.2015 01
63. 63 Ranbir Singh Flying Officer (Retd.)
H. No. 3111 Jis Sarai New Delhi 110 016
Domestic DISCOMs 10.04.2015 01
64. 64 Sh. Vivek Bagga
78, South Anarkali, Street No. 4 Near Chander Nagar, Delhi 110 051 [email protected]
Domestic DISCOMs 13.04.2015 01
65. 65 Sh. Krishan Gopal Sharma
H. No. 51, Mandir Wali Gali Azadpur (Village) Delhi 110 033 [email protected]
Domestic DISCOMs 13.04.2015 01
66. 66 Sh. Vikash Bhagchandka President
M2K Entertainment Pvt. Ltd. E13/29, Ist Floor, Harsha Bhawan, Connought Circus, New Delhi 110 001
Industrial/ Commercial
TPDDL 13.04.2015 37
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 167
September 2015
67.
67
67A
67B
67C
67D
67E
Sh. B.B. Tiwari Sh. B.B. Tiwari Sh. B.B. Tiwari Sh. B.B. Tiwari Sh. B.B. Tiwari Sh. B.B. Tiwari
[email protected] [email protected] [email protected] [email protected] [email protected] [email protected]
RWA
RWA
RWA
RWA
RWA
RWA
DISCOMs
DISCOMs
DISCOMs
DISCOMs
DISCOMs
DISCOMs
13.04.2015
21.04.2015
21.04.2015
28.04.2015
05.05.2015
05.05.2015
02
01
21
10
03
02
68. 68 Sh. Naveen Goel
[email protected] Domestic DISCOMs 13.04.2015 02
69. 69 Sh. S.P. Shaha
RZ-8N/1, Gali No. 3 Indra park, Palam Cly. S. W. Delhi, Delhi 110 045 [email protected]
Domestic DISCOMs 13.04.2015 01
70. 70 Sh. Jaswinder Singh
[email protected] Domestic DISCOMs 13.04.2015 01
71. 71 Sh. R.P. Jindal Rohini East RWA [email protected]
RWA DISCOMs 13.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 168
September 2015
72.
72
72A
72B
Sh. Anil Sood Hony President CHETNA Sh. Anil Sood Hony President CHETNA Sh. Anil Sood Hony President CHETNA
A417-418, Somdutt Chamber-1 5 Bhikajicam Place, New Delhi [email protected] A417-418, Somdutt Chamber-1 5 Bhikajicam Place, New Delhi [email protected] A417-418, Somdutt Chamber-1 5 Bhikajicam Place, New Delhi [email protected]
RWA
RWA
RWA
DISCOMs
DISCOMs
DISCOMs
13.04.2015
13.04.2015
23.04.2015
03
14
09
73. 73
Sh. Rajesh Agrawal Gen. Secretary
Shahdara Resident Welfare Association (Regd.) 356, Farsh Bazar, Shahdara, Delhi 110 032 [email protected]
RWA DISCOMs 13.04.2015 01
74. 74 Sh. Vipin Jain Director
M/s Negolice India Ltd. E-34, 2
nd Floor,
Connaught Circus, New Delhi 110 001 [email protected]
Domestic TPDDL 06.04.2015 161
75. 75 Sh. Ujjwal [email protected] Domestic DISCOMs 16.04.2015 01
76. 76
Sh. S. Krishnan, IAAS (Retired) Advisor
Consumer Online Foundation F-9, 2
nd Floor, Kailash Colony New
Delhi 110 048 [email protected]
Domestic DISCOMs 16.04.2015 10
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 169
September 2015
77.
77
77A
77B
77C
Sh. Vivek Agarwal General Manager/ Electrical Sh. Vivek Agarwal General Manager/ Electrical Sh. Vivek Agarwal General Manager/ Electrical Sh. Vivek Agarwal General Manager/ Electrical
Delhi Metro Rail Corporation Metro Bhawan, Fire Brigade lane, Barakhamba Road, New Delhi 110 001 Delhi Metro Rail Corporation Metro Bhawan, Fire Brigade lane, Barakhamba Road, New Delhi 110 001 Delhi Metro Rail Corporation Metro Bhawan, Fire Brigade lane, Barakhamba Road, New Delhi 110 001 Delhi Metro Rail Corporation Metro Bhawan, Fire Brigade lane, Barakhamba Road, New Delhi 110 001
Government
Government
Government
Government
BRPL
BYPL
TPDDL
NDMC
16.04.2015
16.04.2015
16.04.2015
16.04.2015
45
45
44
34
78. 78 Sh. Rajender Munjal
[email protected] Domestic DISCOMs 16.04.2015 01
79. 79 Sh. Nikhil Chauhan
[email protected] Domestic DISCOMs 17.04.2015 01
80. 80 Sh. Jaidev Bhattacharya
[email protected] Domestic DISCOMs
81.
81
81A
Sh. Sanjay Gupta Sh. Sanjay Gupta
C-4/15, Model Town-3 Delhi 110 009 C-4/15, Model Town-3 Delhi 110 009
Domestic
Domestic
BYPL
BRPL
17.04.2015
29.04.2015
14
22
82. 82 Sh. B.S. Vohra President
[email protected] RWA DISCOMs 02
83. 83 Sh. Arun Kumar Datta
222, Pocket E Mayur Vihar-II Delhi 110 091
Domestic BYPL 17.04.2015 43
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 170
September 2015
84. 84
Ms. Kiran Saini General Manager (C&RA)
Delhi Transco Ltd. Shakti Sadan, Kotla Road New Delhi 110 002 [email protected]
Government
BRPL BYPL
TPDDL NDMC
17.04.2015 07
85. 85 Sh. Shanu Ahluwalia
[email protected] Domestic DISCOMs 17.04.2015 08
86. 86
Sh. Faiyaz Muhammed Pasha CEO
Arslan Scientific, Physical and Industrial Research D-601, 605, Pocket -11 DDA, Jasola Vihar New Delhi 110 025 [email protected]
Industrial/ Commercial
DISCOMs 17.04.2015 02
87.
87
87A
87B
87C
87C
Sh. B.P. Agarwal Advocate Sh. B.P. Agarwal Advocate Sh. B.P. Agarwal Advocate Sh. B.P. Agarwal Advocate Sh. B.P. Agarwal Advocate
A-106, Prashant VIhar, Delhi 110 085 A-106, Prashant VIhar, Delhi 110 085 A-106, Prashant VIhar, Delhi 110 085 A-106, Prashant VIhar, Delhi 110 085 A-106, Prashant VIhar, Delhi 110 085
Industrial/ Commercial
Industrial/
Commercial
Industrial/ Commercial
Industrial/
Commercial
Industrial/ Commercial
TPDDL
TPDDL
BYPL
BRPL
TPDDL
17.04.2015
17.04.2015
17.04.2015
17.04.2015
29.04.2015
07
07
07
06
04
88. 88 Sh. S. Babbar
DVB Employees Terminal Benefits Fund 2002 (Pension Trust) Rajghat Power House, New Delhi 110 002
Government DISCOMs 16.04.2015 04
89. 89 Sh. Chander Pal
A-101, Sharma Market, Pul Pehlad Pur, (M.B. Road) New Delhi 110 044 [email protected]
Industrial/ Commercial
DISCOMs 13.04.2015 02
90. 90
Sh. Kuldeep Kumar General Secretary
Delhi State Electricity Workers Union GENCO, TRANSCO DISCOM I,II, III L-2, Main Road, Brahmpuri, Delhi 10053
Domestic DISCOMs 16.04.2015 15
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 171
September 2015
91. 91
Sh. Rajan Gupta Former Member,
Delhi Electricity Consultative Council, 355 Udyan, Narela, Delhi 110 040
Domestic DISCOMs 17.04.2015 21
92. 92
Sh. V.K. Malhotra General Secretary
DVB Engineers Association D-3, Vikas Puri, New Delhi 110 018
Domestic
TPDDL 16.04.2015 25
93.
93
93A
Sh. Saurabh Gandhi Gen. Secretary Sh. Saurabh Gandhi Gen. Secretary
United Residents of Delhi C-6/7, Rana Pratap Bagh Delhi 110 007 [email protected] United Residents of Delhi C-6/7, Rana Pratap Bagh Delhi 110 007 [email protected]
RWA
RWA
BYPL
BRPL
17.04.2015
17.04.2015
43
03
94. 94
Sh. G.S. Shuklas Sr. Citizen and Social Advisor
DDA- F1/72 Sultan Puri Delhi 110 086
Domestic DISCOMs 15.04.2015 01
95.
95
95A
95B
Sh. Madan Lal Bhasin President Sh. Madan Lal Bhasin President Sh. Madan Lal Bhasin President
Delhi Electricity Consumer Society Patron, RWA D Block, Ashok Vihar, D-163 Ashok Vihar, Phase-I Delhi 110 052 [email protected] Delhi Electricity Consumer Society Patron, RWA D Block, Ashok Vihar, D-163 Ashok Vihar, Phase-I Delhi 110 052 Delhi Electricity Consumer Society Patron, RWA D Block, Ashok Vihar, D-163 Ashok Vihar, Phase-I Delhi 110 052 [email protected]
RWA
RWA
RWA
DISCOMs
DISCOMs
DISCOMs
15.04.2015
21.04.2015
22.04.2015
04
02
10
96. 96
Sh. Meena Chand Joint Secretary
Green Valley Cooperative group Housing Society Ltd. Plot No. 18, Sector-22, Dwarka, New Delhi 10077 [email protected]
Domestic DISCOMs 12.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 172
September 2015
97.
97
97A
Sh. Deepak Goyal Secretary Sh. Deepak Goyal Secretary
Bawana Food Processors Association (Regd.) H-7, Sector-3, DSIDC, Bawana, New Delhi 110 039 Delhi Dal Mills (Millers) Association (Regd.) 4122, Naya Basar, Delhi 110 006
Industrial/ Commercial
Industrial/ Commercial
DISCOMs
DISCOMs
15.04.2015
15.04.2015
02
02
98. 98 Sh. H.H. Bhardwaj Secy. General
207 United Plaza, DDA Community Centre Karkardooma Delhi 110 092 [email protected]
Industrial/ Commercial
DISCOMs 15.04.2015
99. 99 Sh. Raj Kumar Sharma
[email protected] Domestic DISCOMs - 01
100. 100 Ms. Geeta Devi
Ambedkar Jan Kalyan Smiti E-10/444 Pratap Nagar, Saboli Delhi 110 093
Domestic DISCOMs - 04
101. 101
Sh. S.K. Maheshwari General Secretary
Patparganj F.I. E. Enterpreneurs Association Opp. Plot No. 157, Patparganj Industrial Area, Delhi 110 092 [email protected]
Industrial/ Commercial
DISCOMs 17.04.2015 04
102. 102 Sh. K.C. Jain
Plot No. A-1, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
103. 103 Sh. S.N. Mittal
Plot No. 363, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
104. 104 Sh. Sunil Kapoor
Plot No. 345, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
105. 105 Sh. Satender Jain
Plot No. 374, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 173
September 2015
106. 106 Sh. I.S. Bedi
Plot No. 115, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
107. 107 Sh. K.C. Jain
Plot No. 451, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
108. 108 Sh. Sanjay Rastogi
Plot No. 169, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
109. 109 Sh. S.K. Tyagi
Plot No. 220, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
110. 110 Sh. Vikram Sngh Rawat
Plot No. 324, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
111. 111 Sh. Ashutosh Kapoor
Plot No. 379, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
112. 112 Sh. Madhur Goel
Plot No. 233, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
113. 113 Sh. Sagar Anand
Plot No. 266, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
114. 114 Sh. Sarvjit Singh
Plot No. 295, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
115. 115 Sh. N. K. Mehra
Plot No. C-28, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
116. 116 Sh. Rajeev Chawla
Plot No. 199, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
117. 117 Sh. Jitendra Kumar
Plot No. 200, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
118. 118 Sh. Dinesh Kumar
Plot No. 398, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
119. 119 Sh. K.R. Misra
Plot No. 65, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 174
September 2015
120. 120 Sh. Ravinder Kachru
Plot No. 291, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
121. 121 Sh. Virender Kumar
Plot No. 130, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
122. 122 Sh. Sunil Puri
Plot No. 18, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
123. 123 Sh. Tara Chand
Plot No. B-21, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
124. 124 Sh. Sanjay Gaur
Plot No. 150, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
125. 125 Sh. O.P. Sharma
Plot No. 198, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
126. 126 Sh. Anurag Garg
Plot No. 216, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
127. 127 Sh. Vivek Bagga
Plot No. B-14, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
128. 128 Sh. Rajeev Kapoor
Plot No. 189, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
129. 129 Sh. Deepak Gaba
Plot No. 125, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
130. 130 Sh. Pawan Kumar yagi
Plot No. 535, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
131. 131 Sh. Sanjeev Anand
Plot No. 261, Patparganj Industrial Area, Delhi 110 092
Industrial/ Commercial
DISCOMs 17.04.2015 03
132. 132 Ms. Usha Batra
Flat No. 6027, C-6/7 Vasant Kunj, New Delhi 110 070
Domestic DISCOMs 21.04.2014 01
133. 133
Sh. Ompal Singh Former President
Resident Welfare Association B-219, Chhattarpur Extn. New Delhi 110 074
RWA DISCOMs 21.04.2015 02
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 175
September 2015
134. 134 Sh. Naresh Tehran
Maharana Bagh, Cooperative Housing Building, New Delhi 110 054
Domestic DISCOMs 21.04.2015 01
135. 135
Sh. Triloki Singh Vice President
Nav Nirman Welfare Association Meetha Pur Part-2 Sai Nagar, New Delhi 110 044
RWA DISCOMs 21.04.2015 01
136. 136 Sh. Hari Ram Bhardwaj President
DVB Pensioners Assocation Rajghat Power House, New Delhi 110 002
Domestic DISCOMs 21.04.2015 13
137.
137
137A
Sh. H.M. Sharma Sh. H.M. Sharma
E-8(SF), Lajpat Nagar,-2 New Delhi 110 024 E-8(SF), Lajpat Nagar,-2 New Delhi 110 024 [email protected]
Domestic
Domestic
DISCOMs
BRPL
21.04.2015
21.04.2015
12
11
138. 138
Sh. Dushyant Kumar Vice President
Nagar Market Harsh Vihar Hari Nagar, Part III, Welfare Society C-408, Harsh Vihar, Hari Nagar, Extp-III, Badarpur New Delhi 110 044
RWA DISCOMs 21.04.2015 01
139. 139 Sh Ajay Kumar
170B, Govind Puri, Kalkaji Delhi
Domestic DISCOMs 21.04.2015 01
140. 140 Sh. B.D. Sharma
Mundka Division RWA DISCOMs 21.04.2015 01
141. 141
Sh. A.K. Upadhyay Vice President
C-9, Vasant Kunj, New Delhi
RWA DISCOMs 21.04.2015 14
142. 142 Ms. Mamta Arya
M-95, Near Pratap Market Munirka, Delhi
Domestic DISCOMs 21.04.2015 01
143. 143 Sh. Amar Lal 206, Ist Floor, Jeevan Nagar, Ashram, New Delhi
Domestic DISCOMs 21.04.2015 01
144. 144 Sh. Rajan Kumar
Sarita Vihar, New Delhi 110 076
Domestic DISCOMs 21.04.2015 01
145. 145 Ms. Garima Bishawas
F-244A, Raj Nagar, Part – 2 Palam, New Delhi 110 003
Domestic DISCOMs 21.04.2015 01
146. 146 Sh. Rajiv Agarwal
E-290, Ramesh Nagar, Delhi 110 015
Domestic DISCOMs 21.04.2015 01
147. 147 Sh. Rajeev Sharma
172 B, Govindpuri Kalkaji Delhi
Domestic DISCOMs 21.04.2015 01
148. 148 Sh. Deshraj Yadav
Sector-4 R.K. Puram, Delhi
RWA DISCOMs 21.04.2015 01
149. 149 Sh. B.S. Goel Mundka Domestic DISCOMs 21.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 176
September 2015
150. 150 Ms. Savita Swami
H.No. 150, C/15, Ward No. 02 Mehrauli, New Delhi 110 030
Domestic DISCOMs 21.04.2015 01
151. 151 Sh. JK Kheterpal
D-2/39, Hari Nagar, New Delhi 110 058
Domestic DISCOMs 21.04.2015 01
152. 152 Sh. B. L Ratnakar
Lawerance Road, Keshave Puri, Delhi 110 035
Domestic DISCOMs 21.04.2015 01
153. 153
Fit Lt. (Retd.) ID Sharma General Secretary
Arjun Nagar, House Owners Welfare Association (Regd.) 150, Arjun Nagar, New Delhi 110 029
RWA DISCOMs 21.04.2015 01
154. 154 Sh. Sandeep C-18, Amar Colony Domestic DISCOMs 21.04.2015 01
155. 155 Sh. Akhilesh 18, Pragati Appartment Paschim VIhar, New Delhi
Domestic DISCOMs 21.04.2015 01
156. 156 Sh. Kapil Dev
Plot No. DIC & D2A, Adhyapak Nagar, Near Narayan Dharam Kanta Nangloi, New Delhi
Domestic DISCOMs 21.04.2015 01
157. 157 Sh. Mukesh Kumar
P No-47-old-103-A Naresh Park Nangloi New Delhi 110041
Domestic DISCOMs 21.04.2015 02
158. 158 Sh. Kaushal Kishore
H.No. 64, Kirlokari, Hari Nagar, Delhi
Domestic DISCOMs 21.04.2015 01
159. 159 Sh. P.C. Maurya
Manch Publications Domestic DISCOMs 21.04.2015 01
160. 160
Sh. R.K. Atoliya Chief Electrical Distribution Engineer
Northern Railway Baroda House, New Delhi 110 001
Government DISCOMs 21.04.2015 21
161. 161 Dr. Pradeep Saini
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
162. 162 Sh. Chote Lal Yadav
Purvanchal Vikas Samiti(Regd.) H.No. 13, Gali No. 5/2 Shakti Vihar, A-Block Meethapur Chowk, Badarpur, New Delhi 110 014
RWA DISCOMs 21.04.2015 01
163. 163 Dr. Navin Dang
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
164. 164 Dr. Vijay Kinra
C-29, C.C. Colony Delhi 110 007 [email protected]
Industrial/ Commercial
DISCOMs 21.04.2015 01
165. 165 Dr. Rajiv Aggarwal
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
166. 166 Sh. Shrikant Kaushik
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 177
September 2015
167. 167 Dr. Rohit Rajput
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
168. 168 Dr. R.M. Chhabra
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
169. 169 Dr. Ashish Rohatgi
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
170. 170 Dr. Samir Grover
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
171. 171 Dr. Varun Tyagi
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
172. 172 Ms. Manish Kukreja
[email protected] Industrial/
Commercial DISCOMs 21.04.2015 01
173. 173 Mrs. Neeta Gupta
A-17, Antriksh Apartments, Opp. Rohini District Courts, Sector, 14-Extn, Rohini, Delhi 110 085 [email protected]
Domestic DISCOMs 21.04.2015 01
174. 174 Sh. H.R. Sarin President
Mangla Apartments, G-Block, Kalkaji, New Delhi
RWA DISCOMs 21.04.2015 01
175. 175 Dr. Puneet Kumar
Kumar Child Clinic, Dwarka [email protected]
Industrial/ Commercial
DISCOMs 24.04.2015 01
176. 176 Dr. B.L. Jain
Delhi Heart Hospital Advanced Critical Care Center 176, Jagriti Enclave Delhi [email protected]
Industrial/ Commercial
DISCOMS 24.04.2015 01
177. 177 Sh. Anil Goswami
GH-1/360, Paschim Vihar, New Delhi 110 063
Domestic BRPL 21.04.2015 01
178. 178 Sh Yog Raj Goswami
GH-1 Resident Welfare Association GH-1/231, Archna Apartments, Paschim Vihar, New Delhi 110 063
RWA BRPL 21.04.2015 01
179. 179 Ms. Jyotsna Tiwari
Dr. Jyotsna Tiwari Type IV/19, NCERT Campus Sri Aurobindo Marg New Delhi 110 016
Domestic DISCOMs 21.04.2015 01
180. 180 Sh. Manoj Nootiyal
Shri Ganga Vihar Residents Welfare Association Regd. Village Dindar Pur, Najafgarh, New Delhi 110 043
Domestic BRPL 21.04.2015 01
181. 181 Sh. S.R. Abrol L-2, 91B, DDA, LIG Flats Kalkaji, New Delhi 110 019
Domestic DISCOMs 21.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 178
September 2015
182. 182
Sh. I.K. Ramani Gen. Secretary
Residents Welfare Association 1, Mini Market, E-Block, East of Kailash, New Delhi 110 065 [email protected]
RWA BRPL 21.04.2015 01
183. 183 Ms. Geeta Mahor
Aman Vihar Resident Welfare Association C-568, Aman Vihar, Kiradi, Suleman Nagar, Delhi 110 086
RWA TPDDL 23.04.2015 01
184.
184
184A
184B
Sh. Jeet Singh Sh. Jeet Singh Sh. Jeet Singh
R2-5/262, J Block West Sagar Pur, New Delhi 110 046 R2-5/262, J Block West Sagar Pur, New Delhi 110 046 R2-5/262, J Block West Sagar Pur, New Delhi 110 046
Domestic
Domestic
Domestic
DISCOMs
DISCOMs
DISCOMs
22.04.2015
22.04.2015
22.04.2015
01
01
01F
185. 185 Sh. Jeet Suneja
RZ – 5/262, J-Block West Sagar Pur, New Delhi 110 046
Domestic DISCOMs 22.04.2015 01
186. 186 Sh. Vipin Gupta
A-17, Antriksh Apartments, Opp. Rohini District Courts, Sector 14, Extn. Rohini, Delhi 110 085
Domestic DISCOMs 23.04.2015 04
187. 187 Sh. Rajesh Dhotre
[email protected] Domestic DISCOMs 23.04.2015 01
188. 188 Sh. Jagdish Bhartiya Member
Tagore Garden Resident Welfare Association ID, 143/1, Tagore Garden, New Delhi 110 027
RWA DISCOMs 23.04.2015 02
189. 189
Sh. C.M. Bhagat (MD) Chairman, DMA NH & MEF
DMA Nursing Home & Medical Establishment Forum DMA House, Medical Association Road [email protected]
Industrial/ Commercial
DISCOMs 23.04.2015 02
190. 190
Sh. Davinder Kumar Mehendiratta President kalkaji vypar Mandal
BSES Rajdhani Power Limited BSES Bhawan, Nehru Place, New Delhi 110 019
Domestic BRPL 22.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 179
September 2015
191. 191 Dr. Dudani [email protected] Industrial/
Commercial DISCOMs 22.04.2015 01
192. 192 Sh. Pratik Banerjee
[email protected] Domestic DISCOMs 22.04.2015 01
193. 193 Dr. Pardeep Gupta
Plot No. 4, Sukhbir Nagar, Karala, Delhi 110 081 [email protected]
Domestic TPDDL 21.04.2015 02
194. 194
Sh. Raghuvansh Arora Vice President
Apex Chamber of Commerce & Industry of NCT of Delhi A-8, Naraina Industrial Area, Phase II, New Delhi 110 028 [email protected]
Industrial/ Commercial
DISCOMs 23.04.2015 05
195. 195
Sh. Ashu Gupta Office In-charge
Green Energy Association Sargam, 143, Taqdir Terrace, Near Shirodkar High School [email protected]
Industrial/ Commercial
DISCOMs 22.04.2015 09
196. 196 Sh. R.S. Wadhwa
New Friends Resident Welfare Association New Friends Colony Opp. A297, Delhi
RWA DISCOMs 22.04.2015 01
197. 197 Sh. J.N. Rawal President
Resident Welfare Association Pocket-‘G’ Sarita Vhiar Delhi
RWA DISCOMs 22.04.2015 01
198. 198 Sh. N.S. Dagar President
Resident Welfare Association RWA Gopal Nagar, B-Block, Najafgarh New Delhi
RWA DISCOMs 21.04.2015 01
199. 199 Sh. Sanjay Puri Chairman
AAm Aadmi Party A1A/51-A, Janak Puri, New Delhi 110 058
Political Party
DISCOMs 17.04.2015 13
200. 200 Sh. Sman Panwar
201. 201 Sh. Satyavir Singh
Resident Welfare Association, Druga VIhar-II (Sainik Colony) Dinpur Najafgarh, New Delhi 110 043
Domestic DISCOMs 21.04.2015 01
202. 202 Sh. K.K. Singh President
Shakti VIhar, A-Block, Rehayasi Welfare Association Office No. 15, Street No. 5/2 A-Block, Shakti Vihar Badarpur, New Del;hi 110 044
RWA DISCOMs 21.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 180
September 2015
203. 203 Sh. Hari Singh K-272 Shahi Bhagat Singh Marg Mundka Delhi 110 041
Domestic DISCOMs 21.04.2015 01
204. 204
Sh. S.K. Narula General Secretary
AC Block Welfare Association AC-27, Tagore Garden New Delhi 110 027
RWA DISCOMs 21.04.2015 01
205. 205 Sh. M.S. Ahluwalia
C-20 (G. Floor) Somani Nagar,
Domestic DISCOMs 22.04.2015 01
206. 206 Sh. Sodaan Singh
Nand Nagri Sangharsh Simiti B-3/8, Nand Nagri, Delhi 110 093
RWA DISCOMs 22.04.2015 02
207. 207 Dr. Shalabh Sharma
[email protected] Industrial/
Commercial DISCOMs 23.04.2015 01
208. 208 Dr. Ranjit Gulati
[email protected] Industrial/
Commercial DISCOMs 22.04.2015 01
209. 209 Dr. Majoj Goel
[email protected] Industrial/
Commercial DISCOMs 22.04.2015 01
210. 210 Dr. Nitin Agarwal
[email protected] Industrial/
Commercial DISCOMs 22.04.2015 01
211. 211 Sh. J.L. Johar [email protected] Domestic DISCOMs 22.04.2015 01
212. 212 Dr. Jagdeep Chugh
[email protected] Industrial/
Commercial DISCOMs 22.04.2015 01
213. 213 Sh. Chetan Sharma Chairman
[email protected] RWA DISCOMs 22.04.2015 01
214. 214 Sh. Suresh Tiwari
[email protected] Domestic DISCOMs 22.04.2015 01
215. 215 Sh. Kishore Rajurkar
[email protected] Domestic DISCOMs 21.04.2015 01
216. 216 Sh. Dinesh Kumar Gupta
[email protected] Domestic DISCOMs 21.04.2015 01
217. 217 Sh. Gaurav Nand
Indian Energy Regulatory Services T-44, Karampura, New Delhi 110 015
Industrial/ Commercial
DISCOMs 17.04.2015 02
218. 218 Sh. Dharminder Kumar
Federation of Vikas Nagar RWA DISCOMs 27.04.2015 03
219. 219 Dr. Sunil Dargar
[email protected] Industrial/
Commercial DISCOMs 27.04.2015 01
220. 220 Sh. Sudhir Gupta
E-5, Amar Colony Lajpat Nagar IV New Delhi 110 024
Domestic DISCOMs 21.04.2015 01
221. 221 Sh. R.S. Dixit President
Sourabh Vihar Resident Welfare Assocation (Regd.) N-349/13 Sourabh Vihar, Hari Nagar Extn. Jait PUr Badar Pur New Delhi 110 044
- DISCOMs 21.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 181
September 2015
222. 222 Sh. Sanjay Jain
10, Brothers Apartments 16, I.P. Extn. Patparganj Delhi 110 092 [email protected]
- BYPL 21.04.2015 21
223. 223 Sh. S.K. Puri AE Block AE/59, Tagore Garden New Delhi 110 027
- DISCOMs 23.04.2015 01
224. 224 Sh. Jagjit Singh
Isapur Gram Vikas Simiti Gaun Isapur New Delhi 110 073
RWA DISCOMs 21.04.2015 01
225. 2 225 Prof. Pandav Nayak President,
Indian Institute of Public Administration CGHS Plot No. 26, Sector-6, Dwarka, New Delhi 110 075
Domestic TPDDL 21.04.2015 02
226. 226 Sh. Gaurav Nand Coordinator
Assocaition of Power Traders Ground Floor, Central Board of Irrigation & Power Malcha Mar, Chankyapuri, New Delhi 110 021
Industrial/ Commercial
DISCOMs 27.04.2015 03
227. 227
Ms Meghna Aggarwal Executive Director
National Medical Forum 24, Ansari Road, Daryaganj New Delhi 110 002 [email protected]
Industrial/ Commercial
DISCOMs 28.04.2015 01
228. 228
Dr. Prem Aggarwal Managing Director
Sanjeevan Hospitals 24, Ansari Road, Daryaganj, New Delhi 110 002 [email protected]
Industrial/ Commercial
DISCOMs 24.04.2015 14
229. 229
Sh. Paramjeet Singh President
Vikas Puri Welfare Society
RWA DISCOMs 27.04.2015 03
230. 230 Sh. Rajesh Garg
Engineers Association Okhla Y-35, Okhla Industrial Area, Phase-II, New Delhi
Industrial/ Commercial
DISCOMs 27.04.2015 02
231. 231 Sh. S.C. Dua President
Kailash Hills Market Assocaition 21 Kailash Hills Market, New Delhi 110 065
Industrial/ Commercial
DISCOMs 21.04.2015 01
232. 232 Sh. Rakesh Kumar
RWA Sector-1 R.K. PUram Delhi
Domestic DISCOMs 21.04.2015 01
233. 233 Sh. Ved Prakash Arya
895 A 1, W No. 8, Mehrauli New Delhi 110 030
Domestic DISCOMs 21.04.2015 01
234. 234 Sh. S.K. Sharma
C-34, ODS Lajpat Nagar New Delhi 110 024
Domestic DISCOMs 21.04.2015 01
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 182
September 2015
235. 235 Ms. Anita
H. No. 41, G/F, Killa No. 44 Adhopak Nagar, Behind Narayan Dhoom Kanta Delhi 110 041
Domestic DISCOMs 21.04.2015 01
236. 236 Sh. Rajesh Kumar
C-19, Amar Colony Delhi 110 024
Domestic DISCOMs 21.04.2015 01
237. 237 Sh. Raj Kumar C-27, Amar Colony Delhi 110 024
Domestic DISCOMs 21.04.2015 01
238. 238 Sh. Raj Kumar C-17, Amar Colony Delhi 110 024
Domestic DISCOMs 21.04.2015 01
239. 239 Sh. Jawal Singh
C-28 Amar Colony Delhi 110 024
Domestic DISCOMs 21.04.2015 01
240. 240 Sh. Rajeev Chowdhary
BSES Rajdhani Power Ltd. BSES Bhawan, Nehru Place, New Delhi 110 019
DISCOMs 27.04.2015 15
241. 2 241 Sh. Aditya Pyasi
DISCOMs 28.04.2015 15
242. 242 Dr. Yashpaul Jindal
C-49, Ground Floor Yojna VIhar Delhi 110 092
Industrial/ Commercial
DISCOMs 28.04.2015 01
243. 243 Dr. Uppal [email protected] Industrial/
Commercial DISCOMs 28.04.2015 01
244. 244 Dr. J.C. Pathak Ex President
[email protected] Industrial/
Commercial DISCOMs 27.04.2015 01
245. 245 Dr. V.S. Gogia [email protected] Industrial/
Commercial DISCOMs 27.04.2015 01
246. 246 Sh. P.K. Jalali Treasurer
Satisar Cooperative Group Housing Society Ltd. Plot No. – 6, Sector -7 Dwarka New Delhi 110 075 [email protected]
Domestic BRPL 27.04.2015 01
247. 247 Sh. Girish Jain [email protected] Industrial/
Commercial DISCOMs 28.04.2015 01
248. 248 Sh. Balvinder Singh Thapar
Delhi State Resident Welfare Council (Regd.)
Domestic DISCOMs 27.04.2015 03
249. 249 Sh. Rajiv Kumar Bhagat
Shop #06, DDA Market “QD”, Block, Pitampur Delhi 110 034
Industrial/ Commercial
TPDDL 27.04.2015 03
250. 250 Sh. Ashwani Kumar
Vijay Nagar Welfare Association A-23/A First Floor, Single Storey, Vijay Nagar, Delhi
Domestic BYPL 29.04.2015 21
251.
251
251A
Ms. Rama Chhabra Ms. Rama Chhabra
[email protected] [email protected]
Domestic
Domestic
BRPL
BRPL
29.04.2015
29.04.2015
02
03
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 183
September 2015
252.
252
Sh. Sanjay Gupta
[email protected] Domestic BRPL 29.04.2015 03
253. 253 Sh. Davinder Kumar Gupta
J-302, Green Valley CGHS Sector 22, Dwarka, New Delhi 110 077 [email protected]
Domestic DISCOMs 28.04.2015 01
254. 254
Sh. Buhpinder Singh Coordinator Sh. Rajiv Kumar Coordinatory
Confederation Relocated Industries Bawana E-57, Sector-2, DSIIDC, Bawana Industrial Complex, Bawana, Delhi 110 039 [email protected]
Industrial/ Commercial
DISCOMs 29.04.2015 12
255. 255 Sh. Atul Mehra
Resident Welfare Assocaition Block FFA & FB FB 24, Tagore Garden, New Delhi 110 027
RWA DISCOMs 29.04.2015 01
256. 256 Sh. Harmit Singh Director
Heat Exchange (P) Ltd. 349, FIE Patparganj Delhi 110 092 [email protected]
Industrial/ Commercial
DISCOMs 29.04.2015 01
257.
257
257A
Sh. Padam Chand Jain Sh. Padam Chand Jain
19, Navyug Appartments Sector 9, Rohini 19, Navyug Appartments Sector 9, Rohini [email protected]
RWA DISCOMs 29.04.2015 02
258. 258 Sh. Jyotish Kumar Sinha
Tata Power Delhi Distribution Ltd. NDPL House Hundson Lines Kingsway Camp Delhi 110 009
TPDDL DTL 28.04.2015 07
259. 259 Sh. Bharat Kumar Gohel
[email protected] RWA DISCOMs 24.04.2015 03
260.
260
260A
Sh. Atul Kumar Goyal Sh. Atul Kumar Goyal
[email protected] [email protected]
RWA
RWA
BYPL
BRPL
25.04.2015
25.04.2015
14
10
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 184
September 2015
261. 261 Sh. A.S. Chauhan
D.V.B. Pensioners Association Rajghat Power House New Delhi 110 002
Domestic DISCOMs 16.04.2015 85
262. 262 Sh. Manoj Jain
MCT-290, Gautam Puri Delhi 110 053
RWA DISCOMs 05.05.2015 01
263. 263 Ms. Ganga Saini
Bhagwal Park Resident’s Welfare Association 91, Gali No. 3, Bhagwan Park Jharoda Marja, Burari Delhi 110 084
RWA DISCOMs 05.05.2015 09
264.
264
264A
Sh. Amit Kumar Ojha Sh. Amit Kumar Ojha
58C, B-4 Salhapur Khera Bijwasan, New Delhi 110 061 58C, B-4 Salhapur Khera Bijwasan, New Delhi 110 061 [email protected]
RWA
RWA
BYPL
BRPL
27.04.2015
14
265.
265
265A
Sh. S.K. Bhatia Sh. S.K. Bhatia
[email protected] 3/102 Subhash Nagar, New Delhi 110 027 [email protected]
Domestic
Domestic
DISCOMs
DISCOMs
06.05.2015
12.05.2015
01
01
266. 266 Sh. Anil Sharma
[email protected] Domestic DISCOMs 24.06.2015 16.06.2015
01
267. 267
Sh. S.R. Sangar General Secretary
Federation of Indraprastha Extn.-II, Housing Societies, 71, Kiran Vihar, New Delhi-92
Domestic DISCOMs 20.05.2015
268. 268 Suresh Abrol [email protected] Commercial DISCOMs 12.05.2015 01
269. 269 Sh. Manju Vishnu Lal
Domestic DISCOMs 12.05.2015 04
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 185
September 2015
Annexure-X
Stakeholders who have attended the Hearing for the petition filed by DISCOMs for Approval of FY 2013-14, Review for FY 2014-15 and ARR for FY 2015-16
S.No. Name Address
1. Mr. Ashok Bhasin RWA, North Delhi
2. Mr. R.S. Jarout DMRC
3. Mr. Ved Prakash RWA, Mehrauli
4. Ms. Savita Swami RWA
5. Mr. Pawan DMRC
6. Mr. Vivek Aggarwal DMRC
7. Mr. Sharad Sharma DMRC
8. Mr. Sarbajit Roy B-59, Defence Colony
9. Mr. M.S. Ahluwalia C-20, FG, Soami Nagar
10. Mr. Subodh Pandey DMRC
11. Mr. Kapil Dev 3/23, Damruddin Nagar, Nangloi, N.Delhi
12. Mr. Jagmohan DMRC
13. Mr. Om Pal Singh E186, E-Block, Cattarpur, Ext. Delhi
14. Mr. Sukhdev Raj Abrol New Delhi, Bar Association, Patiala House Courts N.Delhi 110 001
15. Mr. Mahender Singh RWA, Ranjit Nagar
16. Mr. Kuldeep Kumar DSEW Union, Delhi Workers Union
17. Mr. K.L. Katyal G-3, Block-G, Rattan Park Basai Darapur, Delhi
18. Mr. Harswroop Bakshi H-18/74, Sec.-7, Rohini, Delhi 110 085
19. Mr. S.K. Bhatia 3/102, Subhash Nagar, N.Delhi
20. Ms. Firdous Jahan
21. Ms. Renu
22. Ms. Ravinder Kaur School of open learning
23. Mr. Satyavan Singh P-1, Sultan Puri, Delhi-86
24. Mr. Dharmendra G-43, Jailerwala Bagh, Delhi
25. Mr. Tej Khatar Mother Dairy GCHS
26. Mr. Sanjay Gaur Patpargang, FIE Association, 149,150 FIE IA Delhi-92
27. Mr. B.B. Tiwari A-2/149, Safdarjung Enclave
28. Mr. Himanshu Arora 11/141, Malviya Nagar
29. Mr. Girish Deveshwar Indus Tower Gurgaon
30. Mr. H.M. Sharma Lajpat Nagar
31. Mr. ANish Garg Delhi Government
32. Mr. Bhupender Chawla RWA Bhaipur Parmanand
33. Mr. Ramesh Berwa RWA, Manak Pura, Karol Bagh
34. Mr. Vijay Jain Industrial and Commercial
35. Mr. Dharminder Kumar CU-143, Pitampura, Delhi 110 034
36. Mr. Tilak Mitra Industrial/Commercial
37. Mr. Praveen Dhamija RWA, Parmanand Colony
38. Mr. Rakesh Kumar Billa 174, Bhai Permanand Colony
39. Mr. Meghraj Goyal Industrial and Commercial
40. Mr. Bharat Bhatia Industrial and Commercial
41. Mr. R.L. Kamboj RWA, Rohini
42. Mr. Jitender Aggarwal Industrial and Commercial
43. Mr. Rajiv Kumar Industrial and Commercial
44. Mr. Rohit Banjamin Ramesh Tyagi Colony Burari
45. Mr. Sidharth NDPL House
46. Mr. Rashid Anwar 554/14, Zakir Nagar, Delhi 25
47. Mr. B.S. Gujral Janakpuri, RWA
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 186
September 2015
48. Mr. Yankush Industrial and Commercial
49. Ft. Lt. I.D. Sharma Gen. Secretary
150, Arjun Nagar, Delhi
50. Mr. Samant Bhushan BQ Block, Shalimar Bagh
51. Mr. Ajay Chhabra B-117, Sarvodaya Enclave
52. Mr. Rishi Prakash 79, Gali No. 15, Sanjay Nagar, Delhi 110 033
53. Mr. Chandra Bhan Jain A-60, Gali No. 21, Mahendra Park, Adarsh Nagar
54. Mr. Avtar Singh Chandhok B-Q1/160, Shalimar Bagh
55. Mr. Varun Mathur A-904/Exotica , Indrapuram
56. Mr. Rajeev Kakria E-230, Greater Kailash-1, New Delhi 110 048
57. Mr. R.C. Sharma B-4/43, Phase-II, Ashok Vihar
58. Ms. Sheetal Jain T-15, Budh Vihar
59. Ms. Anil Sood 1056, C-1, Vasant Kunj
60. Mr. A.K. Datta 222, Pocket E, Mayur Vihar-II, Delhi 110 091
61. Mr. Sunil Shekhawat Industrial and Commercial
62. Mr. Vijay Kumar Singh 342/1, Sector-6, Rohini
63. Mr. Subhash RWA
64. Mr. Sanjey Puri Delhi Vidhan Sabha, AIA/34 A, Janakpuri
65. Mr. Yogesh Shani C-6/B, Block RWA
66. Mr. Narendra Kumar Singal 347 B/28, Onkar Ngr, B-Trinagar, Delhi-35
67. Mr. Roshan Lal Garg PVC Compound & Footwear Mgr. Association, 2682/199, (First Floor) Mangol Puri
68. Mr. Gaurav Arora C-48, Mintro Road Complex, New Delhi 02
69. Mr. Gaurav Nand Indian Energy Regulatory Services,T-44, Karampura, New Delhi 110 015
70. Mr. Satveer Singh RZ-284, Durga Vihar, Najafgarh Delhi-43
71. Mr. Akbar Basha C-49, Ganga Vihar Deenpur, Najafgar
72. Mr. Abhijeet Kumar Consultant
73. Mr. Vaibhav Saini Indian Energy Regulatory Services,T-44, Karampura, New Delhi 110 015
74. Mr. Rajnesh M-172/Pashchim Vihar,
75. MR. Suresh Joshi B-798, MIG DDA Flats East Loni Road Delhi-93
76. Mr. Saurabh Gandhi C-6/7, Rana Pratap Bagh, Delhi 110 007
77. Mr. Vijay Kr. Malhotra 68, RPS Flats, Shekih Sarai, PH-I, N.D-17
78. Mr. Anmol Indus Tower
79. Mr. Samson Josef Fedrick CR-247, Lalita Park, Central Road, Laxmi Nagar
80. Mr. P.K. Malhotra DVB Engineers Association
81. Mr. Yograj Goswami RWA, Punjabi Bagh
82. Mr. Deepak Shankar 42/First Floor Gagan Vihar
83. Dr. M.K. Agarwal RWA, Balbir Nagar
84. Mr. Rajan Gupta Former, DECC Member
85. Mr. B.S. Vohra East Delhi RWA
86. Mr. Jitender Tyagi President URD
87. Mr. S.K. Maheshwari Patparganj, FIA
88. Mr. Surender Arora Industrial / Commercial
89. Mr. Amit Kumar Industrial / Commercial
90. Mr. Purushottam Patparganj Association, RWA
91. Mr. K.R. Misra 65, Patpargaj, Industrial Estate
92. Mr. Sanjay Jain C-574, Gali No. 25, Bhajan Pura
93. Mr. Anshuman Roy 3610 Khala phase-3
94. Mr. Om Prakash Sharma Patparganj Industrial Area, D-115, Block D, Surajmal Vihar
95. Mr. Damodar Kashyap
96. Mr. Sunil Kumar All Delhi, RWA
97. Mr. Naresh Bhati RWA, Aruna Ngr, Civil Lines
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 187
September 2015
98. Mr. Prashant Kamal A-96, Madhuban, Vikas Marg, Delhi -92
99. Mr. Balbir Singh 15/3, Indra Vikas Colony, Kukherjee Nagar,
100. Mr. Jagjeet Singh RWA, Hudson Line GTB Nagar
101. Mr. Shivander Yadav RWA Kotla Village Mayur Vihar, Phase I
102. Mr. Mahender Pal Singh 1188, Shora Kothi, Subzi Mandi, Delhi
103. Mr. Harish Kumar D-528, Block-D, Ranjeet Vihar, Nalothi Ext. Nangloi
104. Mr. Sushil Kumar RWA Nangloi
105. Ms. Ravinder Singh Bisht J-60, S-5 Dilshad Colony
106. Mr. P. Gopalan A-501, Thiruvzha Apartment, Plot No. 37, Sec. 10, Dwarka (RWA)
107. Mr. Harmeet Singh Sarna RWA, Basti Punjabian Subji Mandi, Delhi 110 007
108. Mr. Shajan Pailo Paul Thiruvizha Apartment Dwarka
109. Mr. Arvind Mehta RWA Double Store New Rajender Nagar
110. Mr. Prem Nagpal P-21, West Patel Nagar, N.D. 18
111. Mr. Sanjeev Bhatnagar RWA, Prasad Nagar, Karol Bagh, Delhi 110 005
112. Mr. M.S. Dhaka G.B.S.S.S Krishna Nagar, Delhi
113. Mr. C.P. Singh RWA, Jyoti Sadan Welfare Association West Jyoti Nagar, Delhi-94
114. Mr. Kanwar Pratap Singh D-408, Gali No. 9, D-Block, Bhajanpura
115. Mr. Jagdish Kumar RWA, D-2 Block Janak Puri
116. Mr. Rampat 139, Village Auchandi Bawana, Delhi
117. Mr. Anwesha Edelman Gurgaun
118. Mr. Rajender Kr. Munjal B-832, Panchvati SOC F-Block, Vikas Puri, N. Delhi-18
119. Mr. Mukesh Yadav RWA Naresh park, Nagaloi
120. Mr. S.L. Gosain RWA, Raja Park
121. Mr. Praveen Kumar H-22, Shakarpur, Delhi 110 034
122. Mr. Rohit Sharma Negolice India Ltd. E-34, 2nd Floor,Connaught Circus, New Delhi 110001
123. Mr. Amarjeet Singh
124. Mr. Rajesh RWA, Vasant Kunj
125. Mr. Thaneshwer Dutt
126. Mr. Satvir Singh RWA, Narela
127. Mr. Rajesh Rishi MLA, Janakpuri
128. Mr. Jarnail Singh MLA, Rajouri Garden
129. Mr. Satish Yadav Janakpuri
130. Mr. Rajeev Rishi Janakpuri
131. Mr. Alka Lamba, MLA, Chandni Chowk
132. Mr. Sukhbir Singh, MLA
133. Mr. Sandeep Mundka
134. Dr. Devender Mundka
135. Mr. Virender Singh Mundka
136. Mr. Amit Dalal Mundka
137. Mr. Gulab Singh MLA, Matiyala
138. Mr. Devender Singh Matiyala
139. Ms. Bhawana Gaur, MLA , Palam Colony
140. Mr. Onkar (With Bhawna Gaur)
141. Mr. Mamta Kundu Dwarka
142. Ms. Pooja Badola Patparganj
143. Ms. Anju Singh Chattarpur
144. Mr. Ajay Rai G-70/4
145. Mr. Naresh Yadav MLA, D-7, 7399, Vasant Kunj, Mehrauli
146. Mr. Shivraj Vasant Kunj
147. Mr. Jagdeep Singh MLA, Hari Nagar
148. Mr. Karnal Singh Rajouri Garden
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 188
September 2015
149. Mr. Nitin Tyagi MLA, Laxmi Nagar
150. Mr. S.K. Bagga MLA, Krishna Nagar
151. Mr. Avtar Singh MLA, Kalkaji
152. Mr. Ajesh Yadav MLA, Badali
153. Mr. Lokesh Laxmi Nagar
154. Mr. Vikas Bagga Krishna Nagar
155. Mr. Kapil Arora Krishna Nagar
156. Mr. Inder Gupta Rohini Sec. 7
157. Mr. P.K. Bhardwaj Sector 63, Noida
158. Mr. Faiyaz Muhammed Pasha 2/Block-D, Okhla, Delhi
159. Mr. Shiv Charan Goel MLA, Parliament Secretary (Fin.)
160. Mr. Mahender SinghYadav MLA , Vikaspuri,
161. Mr. S.S. Yadav Vikas Puri
162. Mr. Rajenda Pal Gautam MLA, Seemapuri
163. Mr. Suresh Saxena
164. Mr. Pawan Sharma MLA Adarsh Nagar,
165. Mr. Kamlesh Chandev H.No. 102, Part-1, Rohini, Sec-21, ND-86
166. Mr. Anand Prakash Sharma Mangesur, Delhi 39
167. Mr. Ritu Raj MLA, Kirari
168. Mr. Deepak N-93, Kirari
169. Mr. Choudhary Fateh Singh MLA Gokulpur
170. Mr. R. Swaroop Vasant Kunj
171. Mr. M.P. Singh
172. Mr. Vaibhav Sharma
173. Mr. Akhilesh Tripati MLA, Model Town
174. Mr. Jitender Kumar F-14/34, Model Town
175. Mr. Yash Upadhaya Model Town
176. Mr. Amit Arora F-8, Model Town
177. Mr. Vikas Model Town
178. Ms. Geeta Mahaur RWA Kirari
179. Ms. Radha Bhardwaj RWA, Rohini
180. Mr. Dashrath Kumar RWA, Rohini
181. Mr. Ravinder Singh Mehrauli
182. Mr. Yusuf Khan Mehrauli
183. Mr. Navdeep Singh Kalkaji
184. Mr. Raja Singh Mehrauli
185. Mr. Mashesh Chand Sharma Mehrauli
186. Mr. Mustkeen Khan Mehrauli
187. Mr. B.P. Agarwal North, MC Delhi, Bar Association
188. Mr. Brij Mohan Verma D-14/104, Sec-3, Rohini, Delhi 110 085
189. Mr. Ajit Kumar D-14/107, Sec-3 Rohini, Delhi 110 085
190. Mr. S.C. Dhupar E-19, 20/10, Sec-3, Rohini
191. Mr. Tarminder Singh B-2C/4A, Janakpuri
192. Mr. Gurmeet 150, Punjabi Bagh, ND-26
193. Ms. Gargi HD-87, Sec-135, Noida
194. Ms. Geeta Bhardwaj BD 87, Sec-135, Noida
195. Mr. Gautam Sharma K-290, Kangara Niketan, Vikas Puri
196. Mr. Anil Chadha K-288, Kangra Niketan, Vikas Puri
197. Mr. Rajesh Gautam E-57/B-217, Sunder Ngr. North East
198. Mr. Chiranjilal Bawana
199. Mr. Shabhit WZ-27, Golden Park Rampura
200. Mr. Shahid Khan 3770, Shah Jungi, Ajmeri Gate
201. Mr. Naeem Bharti RWA, Nai Subha, Chandni Chowk
202. Mr. Surender Babbar, GM (Fin.) DTL
Tariff Order for FY 2015-16 New Delhi Municipal Council
Delhi Electricity Regulatory Commission Page 189
September 2015