status of bridge design works as on 14-05-2018 - Kerala PWD

16
Sl. No Name of bridge Constituency Design file No. Remarks/Status DD AD KASARGOD DISTRICT 1 ORCHA Bridge Thikkarippur 14/2011 Design Completed in Feb 2013 BE3 AD9 2 NELLIKKUNNU bridge Kasaragod 53/2012 Design Completed in Nov 2013 BE1 AD8 3 PADAMCODE bridge Uduma 66/2012 Design Completed in Jan 2014 BE3 AD2 4 BAKILAPADAVU Bridge Manjeswar 64/2013 Design Completed in Mar 2015 BE3 ABE4 5 PAINIKKARA bridge 34/2015 Design Completed in Aug 2016 BE1 AD2 6 KANNAMKAI bridge Thrikkarippur 60/2014 Design Completed in Oct 2016 BE4 AD6 7 KOTTEKANNI Bridge Kasaragod 86/2013 Design Completed in Oct 2016 BE1 AD2 8 THOTTUKARA bridge Thrikkarippur 11/2011 Design Completed in Nov 2016 BE2 AD4 9 VIDYAGIRI Bridge 06/2015 Design completed in Dec 2016 BE1 AD5 10 VANHANGAD bridge Uduma 66/2014 Design Completed in Jan 2017 BE1 AD3 11 KALLAR Bridge Kanhangad 68/2012 DD prepared. Awaiting feasibility report from CE(R&B) BE4 AD9 12 ATHANADI bridge Uduma 68/2013 TGAD completed in Apr 2014. BE1 AD9 13 ARILKADAVU Bridge Thrikkarippur 43/2014 GAD completed in Sep 2015. Awaiting AS BE1 AD8 14 Bridge in UDUMA-MULLACHERI road Uduma 65/2014 GAD completed in Sep 2015. Awaiting AS BE3 AD4 15 PERUMBATTA Bridge Thikkarippur 76/2013 GAD completed in Jan 2016. Awaiting AS BE3 AD2 16 ODANKAL bridge 58/2015 TGAD under preparation BE1 AD8 17 PALLATHUMPARA bridge 61/2015 GAD completed in Sept2017. DD under review BE2 ABE10 18 KUTHUPULLU bridge Manjeswar 20/2013 Proposal Dwg completed in Mar 2013. Awaiting feasibility report from CE(R&B) BE2 ABE12 19 MUNNIPADI bridge Manjeswar 88/2013 Proposal Dwg completed in Dec 2013. Awaiting feasibility report from CE(R&B) BE3 ABE12 20 THUPPAKKAL Bridge 26/2016 Proposal Dwg completed in Nov 2016. Awaiting feasibility report from CE(R&B) BE1 ABE12 21 ARAMANAPADY bridge 31/2016 TGD despatched BE1 AD9 22 POTHANKANDAM bridge 41/2016 TGD completed in March 2018 BE3 ABE12 23 MUNAMBAM Udma 10/2015 Awaiting reply for clarification sent to CE(R&B) on 16.11.15 regarding shifting of alignment. BE3 ABE12 24 AYAMKADAVU Bridge Uduma 02/2015 Proposal drawing completed in Feb 2015. Awaiting feasibility & clarification BE4 ABE12 25 RAMANCHIRA Bridge 56/2017 TGD completed in DEc2017 BE4 ABE12 26 KILTAKKAYAM Bridge 55/2017 TGD completede Feb 2017 BE4 ABE10 27 KALIKKADAVU Bridge 57/2017 TGD to be revised BE4 ABE11 28 Bridge at KILIYALAM 52/2017 TGD completed Mar 2018 BE4 ABE12 29 PALATHARA Bridge 27/2018 TGD completed in April 2018 BE4 ABE12 30 CHERANAMTHALA Bridge 26/2018 TGD putup. BE4 ABE12 KANNUR DISTRICT 1 MAMBARAM Bridge(Revision) 4/2007 DD despatched. BE4 ABE11 2 MANDAMCHERY Bridge 8/2012 Design Completed in Jan 2014 BE1 AD8 3 MANIYANKOLLY Bridge 11/2013 Design Completed in Apr 2015 BE3 AD1 4 MANIKKAL bridge Thaliparambu 19/2013 Design Completed in Nov 2015 BE3 AD7 5 ARENGAD bridge Mattanoor- peravoor 14/2013 Design Completed in Mar 2016 BE2 AD1 6 THUNDI (Thundiyil) Bridge Peravoor 12/2012 Design Completed in Jul 2016 BE1 AD6 7 KACHERIKADAVU bridge Peravoor 51/2012 DD despatched in Jan 2018. BE4 ABE11 8 Kottakkeel Kadavu-Pattuvam bridge 46/2012 GAD completed in Feb 2013. Awaiting AS. BE1 AD6 9 KOOLIKKADAVU bridge Mattanoor 16/2013 GAD completed in Jul 2013. Awaiting AS. BE1 AD6 STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018 Page 1

Transcript of status of bridge design works as on 14-05-2018 - Kerala PWD

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

KASARGOD DISTRICT

1 ORCHA Bridge Thikkarippur 14/2011 Design Completed in Feb 2013 BE3 AD9

2 NELLIKKUNNU bridge Kasaragod 53/2012 Design Completed in Nov 2013 BE1 AD8

3 PADAMCODE bridge Uduma 66/2012 Design Completed in Jan 2014 BE3 AD2

4 BAKILAPADAVU Bridge Manjeswar 64/2013 Design Completed in Mar 2015 BE3 ABE4

5 PAINIKKARA bridge 34/2015 Design Completed in Aug 2016 BE1 AD2

6 KANNAMKAI bridge Thrikkarippur 60/2014 Design Completed in Oct 2016 BE4 AD6

7 KOTTEKANNI Bridge Kasaragod 86/2013 Design Completed in Oct 2016 BE1 AD2

8 THOTTUKARA bridge Thrikkarippur 11/2011 Design Completed in Nov 2016 BE2 AD4

9 VIDYAGIRI Bridge 06/2015 Design completed in Dec 2016 BE1 AD5

10 VANHANGAD bridge Uduma 66/2014 Design Completed in Jan 2017 BE1 AD3

11 KALLAR Bridge Kanhangad 68/2012DD prepared. Awaiting feasibility report from CE(R&B)

BE4 AD9

12 ATHANADI bridge Uduma 68/2013 TGAD completed in Apr 2014. BE1 AD9

13 ARILKADAVU Bridge Thrikkarippur 43/2014 GAD completed in Sep 2015. Awaiting AS BE1 AD8

14 Bridge in UDUMA-MULLACHERI road Uduma 65/2014 GAD completed in Sep 2015. Awaiting AS BE3 AD4

15 PERUMBATTA Bridge Thikkarippur 76/2013 GAD completed in Jan 2016. Awaiting AS BE3 AD2

16 ODANKAL bridge 58/2015 TGAD under preparation BE1 AD8

17 PALLATHUMPARA bridge 61/2015 GAD completed in Sept2017. DD under review BE2 ABE10

18 KUTHUPULLU bridge Manjeswar 20/2013Proposal Dwg completed in Mar 2013. Awaiting feasibility report from CE(R&B)

BE2 ABE12

19 MUNNIPADI bridge Manjeswar 88/2013Proposal Dwg completed in Dec 2013. Awaiting feasibility report from CE(R&B)

BE3 ABE12

20 THUPPAKKAL Bridge 26/2016Proposal Dwg completed in Nov 2016. Awaiting feasibility report from CE(R&B)

BE1 ABE12

21 ARAMANAPADY bridge 31/2016 TGD despatched BE1 AD9

22 POTHANKANDAM bridge 41/2016 TGD completed in March 2018 BE3 ABE12

23 MUNAMBAM Udma 10/2015Awaiting reply for clarification sent to CE(R&B) on 16.11.15 regarding shifting of alignment.

BE3 ABE12

24 AYAMKADAVU Bridge Uduma 02/2015Proposal drawing completed in Feb 2015. Awaiting feasibility & clarification

BE4 ABE12

25 RAMANCHIRA Bridge 56/2017 TGD completed in DEc2017 BE4 ABE12

26 KILTAKKAYAM Bridge 55/2017 TGD completede Feb 2017 BE4 ABE10

27 KALIKKADAVU Bridge 57/2017 TGD to be revised BE4 ABE11

28 Bridge at KILIYALAM 52/2017 TGD completed Mar 2018 BE4 ABE12

29 PALATHARA Bridge 27/2018 TGD completed in April 2018 BE4 ABE12

30 CHERANAMTHALA Bridge 26/2018 TGD putup. BE4 ABE12

KANNUR DISTRICT

1 MAMBARAM Bridge(Revision) 4/2007 DD despatched. BE4 ABE11

2 MANDAMCHERY Bridge 8/2012 Design Completed in Jan 2014 BE1 AD8

3 MANIYANKOLLY Bridge 11/2013 Design Completed in Apr 2015 BE3 AD1

4 MANIKKAL bridge Thaliparambu 19/2013 Design Completed in Nov 2015 BE3 AD7

5 ARENGAD bridge Mattanoor-peravoor

14/2013 Design Completed in Mar 2016 BE2 AD1

6 THUNDI (Thundiyil) Bridge Peravoor 12/2012 Design Completed in Jul 2016 BE1 AD6

7 KACHERIKADAVU bridge Peravoor 51/2012 DD despatched in Jan 2018. BE4 ABE11

8 Kottakkeel Kadavu-Pattuvam bridge 46/2012 GAD completed in Feb 2013. Awaiting AS. BE1 AD6

9 KOOLIKKADAVU bridge Mattanoor 16/2013 GAD completed in Jul 2013. Awaiting AS. BE1 AD6

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

Page 1

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

10 NUCHIYAD bridge (Revision) Irikkur 01/2014 GAD completed in Feb 2014. Awaiting AS. BE4 AD1

11 NANICHERKADAVU BRIDGE Azhikode 69/2013 GAD completed in Jul 2014. Awaiting AS. BE1 AD9

12 ALAKKATT bridge Kaliissery 87/2013 GAD completed in Jan 2015. Awaiting AS. BE4 AD2

13 KOLANTHAKKADAVU bridge Irikkur 45/2014 GAD completed in Apr 2015. Awaiting AS. BE1 AD3

14 CHUNGAKUNNU bridge Peravoor 51/2014 DD despatched in Dec 2017 BE4 ABE11

15 VALAYAMCHAL bridge 69/2014 GAD completed in Sep 2015. Awaiting AS. BE3 AD7

16 VANNATHIKKADAVU bridge 11/2015 GAD completed in Sep 2015. Awaiting AS. BE3 AD7

17 ALEX NAGAR-KANHILERI bridge Payyannur 60/2015 DD despatched Jan2018 BE4 ABE11

18 CHANOKUNDU bridge (Revision) 17/2013 GAD completed in Sept 2016. Awaiting AS. BE2 AD4

19 CHENGALYI bridge 3/2016 GAD completed in Nov 2016. Awaiting AS. BE4 AD7

20 CHOVVA Bridge 16/2016 Work completed. BE1 AD9

21 CHEKKUPALAM 06/2014 TGAD completed in Nov 2016. Awaiting AS. BE1 AD8

22 KUNDUCHIRA Bridge 10/2005 GAD completed in Dec 2016. Awaiting AS. BE4 AD7

23 MANKARA Bridge 38/3016 GAD completed in Dec 2016. Awaiting AS. BE4 AD7

24 ALAKKODE bridge (Revision) Irikkur 13/2013 Revised TGAD completed in Dec 2016. BE4 AD7

25 KARUVANCHAL Bridge (Revision) Irikkur 15/2013 GAD completed in Jan 2017. Awaiting AS. BE3 AD2

26 Puthur Bridge 02/2017 Revised TGDdespatched Feb 2018 BE4 ABE11

27 VATTOLI Bridge Mattannur 21/2014 Revised TGAD completed in Mar 2017. BE4 AD6

28 VADAVANTHOOR Bridge 17/2016TGAD completed in Mar 2017. Feasibility from EE received

BE4 ABE11

29 CHOOLAKADAVU bridge Payyannur 05/2016 Revised TGD despatched on Oct 2017 BE4 ABE11

30 ODENTHODU bridge (Rev) Peravoor 52/2014 Revised TGAD completed in Apr 2017. BE2 AD6

31 THATTARI bridge Darmadom 26/2014 TGD completed in Apr 2017 BE3 AD1

32Dilapidated condition of Pazhayangadi Bridge(Repair &rehabitation)

28/2017 Rehabilitation report despatched BE4 AD7

33 MOOLAKEEL KADAVU Bridge Payyannur 26/2010 TGD to be revised. BE3 ABE11

34 KALLACHERIKADAVU bridgeKoothuparamb

u67/2012 TGD completed on Aug 2017 BE4 ABE11

35 PONNIYAM RANDAMKADAVU Bridge 54/2014Proposal Dwg completed in Nov 2014. Awaiting feasibility report from CE(R&B)

BE1 ABE11

36 MANNAMKUNDU KADAVU Bridge 10/2016Proposal Dwg completed in May 2016. Awaiting feasibility report from CE(R&B)

BE4 ABE11

37Bridge across Kundoor puzha on Anapanthi-Angadikadavu road

03/2017 TGD to be prepared BE4 ABE11

38 KALLIKANDY BridgeKoothuparamb

u04/2017 TGD despatched on April 2018 BE4 ABE11

39 KUNDOORPUZHA bridge Peravoor 20/2014Awaiting reply of clarification regarding alignmentt plan, design data, soil report sent to CE(R&B) in Mar 2014.

BE3 ABE11

40Bridge in St Jude Nattel road at Ayyankunnu

56/2014Awaiting reply of clarification sent to CE(R&B) in Oct 2014 regarding bore hole and design data.

BE3 ABE11

41 MEENKUNNU NEERKADAVU bridge Azhikode 28/2015Awaiting reply of clarification sent to CE(R&B) in Jun 2015 regarding investigation report and approved alignment plan.

BE2 ABE11

Page 2

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

42 Vengara ROB Kallyaseri 37/2016 TGD despatched on March 2018 BE4 ABE11

43 Thuruthy bridge(Revision) Design completed in Jan 2007. To be revised .

44 PULINJOLI KADAVU Bridge Dharmadam 71/2017 TGD despatched Feb 2018 BE4 ABE11

45 Bridge across NEDUVOT River 72/2017 TGD UP BE4 ABE11

46 THURUTHIMUKKU Bridge Kuthuparambu 74/2017 TGD despatched on Feb 2018 BE4 ABE11

47Cherikkal-Kottam bridge across Anjarakkandi river

Dharmadam 2018/08 TGD despatched on March 2018 BE4 ABE11

WAYANAD DISTRICT

1 POLLAMPARA Bridge 41/2012 Design Completed in Dec 2013 BE3 AD1

2 THALIPPARAKKADAVU Bridge(Rev) 41/2013Design Completed in Aug 2014. Letter mentioning revised concrete mix despatched on Apr.2017.

BE3 AD2

3 PANANTHARA Bridge 18/2015 Design Completed in Feb 2016 BE2 AD2

4 CHERUPUZHA Bridge 16/2015 Design Completed in Feb 2016 BE1 AD7

5 PATHIRI bridge (NH Dvn) 49/2014 Design Completed in Jan 2017 BE3 AD1

6 MAMBILICHIKADAVU Bridge(Rev.) 80/2013GAD completed in Dec 2014. Revised GAD to be prepared..

BE1 AD9

7 VALLERY PARAKKADAVU Bridge 05/2014 GAD completed in Dec 2014. Awaiting AS. BE2 AD4

8 PULIKKATTUKADAVU Bridge 62/2017 Clarification received. TGD under prep. BE4 ABE12

KOZHIKODE DISTRICT

1 ELENTHKADAVU bridge 22/2013 Design Completed in Aug 2014 BE4 AD4

2 KORAPUZHA Bridge in NH 17 (Bypass) 8/2014 Design Completed in Nov 2014 BE4 AD7

3PURAKKATTIRI Bridge in NH 17 (Bypass)

9/2014 Design Completed in Nov 2014 BE4 AD7

4 CHEDIALAKKADAVU bridge 63/2012 Design Completed in Feb 2016 BE2 ABE4

5 PALLIPADI bridge 26/2015 Design Completed in Dec 2016 BE3 AD5

6 MARAPPALAM Bridge 106/2013 Revised GAD &DD completed in Feb 2017. BE3 AD9

7 PUTHIYAPALAM Bridge 08/2013GAD completed in May 2014. Revised TGD completed in Oct 2017

BE4 ABE10

8 PATHAYAPARA Bridge 25/2013 GAD completed in Jul 2014. Awaiting AS. BE2 AD4

9 ULLOORKADAVU bridge 7/2006 GAD completed in Jun 2015. Awaiting AS. BE2 AD4

10 ERUDE Bridge 2/2014 GAD completed in Feb 2016. Awaiting AS. BE4 AD5

11 Bridge across Neelithodu 31(2)/2015 Work completed.. BE2 AD9

12 KURIKKALTHODIKA KADAVU bridge 43/2015 GAD completed in Mar 2016. Awaiting AS. BE3 AD1

13 Flyover at THONDAYAD (NH 17) 27/2015 Work completed. BE4 AD7

14 Flyover at RAMANATTUKARA (NH17) 31(1)/2015 Work completed. BE2 AD9

15 Bridge at AZHEEKKAL KADAVU 08/2011Draft GAD approved. Kept in abeyance till further request for design

BE4 ABE11

16 THONDAYAD Flyover 62/2015GAD completed in May 2016. Detailed Dwg of sub structure despatched.

BE4 AD7

17 Bridge at NADUTHURUTHY 17/2015TGD completed in Jul 2016.TGD revised as per CE(R&B)s request

BE1 AD6

18 Bridge at THORAYILKADAVU 21/2015 Revised GAD completed in Mar 2017. BE1 AD8

19 KOOLIMADU Bridge(rev) 15/2005 Revised TGAD completed in Mar 2017 BE1 AD9

20 AKALAPUZHA bridge (Rev.) 15/2015 Revised GAD completed in Apr 2017 BE4 ABE11

21 CHEMPUKKADAVU bridge(rev.) 40/2013 Revised GAD despatched on Apr 2017 BE1 AD9

Page 3

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

22 THOTTUMUKKOM bridge 31/2013GAD completed in May 2017.DD completed OCT 2017

BE4 ABE10

23 KORAPUZHA bridge (Reconstruction) 59/2015 TGAD completed in May 2017 BE4 ABE3

24 THONDILAKADAVU bridge(Rev) 60/2013GAD completed in Nov 2013. Revised TGD despatched on July 2017.Further clarification letter despatched.

BE1 AD8

25 PADANILAM bridge 59/2013 TGD completed in Dec 2017. BE4 ABE10

26 KAKKAD KADAVU bridge 26/2013Proposal Dwg completed in Mar 2013. Awaiting feasibility report from CE(R&B)

BE4 ABE10

27 MOONAMPUZHA Bridge 50/2013Proposal Dwg completed in Jun 2013. Awaiting feasibility report from CE(R&B)

BE4 ABE10

28 POOLAKKADAVU bridge 57/2013Proposal Dwg completed in Jun 2013. Feasibility from EE received.

BE4 ABE10

29 MUKKATHKADAVU bridge 07/2014Proposal Dwg completed in Aug 2014. Awaiting feasibility report from CE(R&B)

BE4 ABE10

30 PARAKKADAVATHU bridge Perambra 58/2014Proposal Dwg completed in Oct 2014. Awaiting feasibility report from CE(R&B)

BE4 ABE10

31 KOTTAKKADAVU Bridge 40/2014Proposal Dwg completed in Mar 2015. Awaiting feasibility report from CE(R&B)

BE4 ABE10

32 Bridge at OLAVANA PALLIKADAVU 29/2015Proposal Dwg completed in Sep 2015. Awaiting feasibility report from CE(R&B)

BE4 ABE10

33 NADUTHODU bridge Nadapuram 57/2015Proposal Dwg completed in Jan 2016. Awaiting feasibility report from CE(R&B)

BE4 ABE10

34 PUZHAMBURAM bridge 36/2015Proposal Dwg completed in Jul 2016. Awaiting feasibility report from CE(R&B)

BE4 ABE10

35 PULIMOOTTIL Bridge 24/2016TGD to be prepared. Kept pending as no urgency reporetd by AEE

BE4 ABE10

36 CHENAYI KADAVU Bridge 17/2017 TGD completed in Oct 2017 BE4 ABE10

37Grade separator Eranhipalam on NH 766

40/2016 TGD completed in Oct 2017 BE4 ABE10

38 OTTATHANNIPALAM Bridge 18/2017 TGD under preparation BE4 ABE10

39 KARIKUTTY KADAVU Bridge 22/2017 TGD to be prepared. BE4 ABE10

40Bridge at KOYAMBRATHKANDI KADAVU

14/2015Awaiting reply of clarification sent to CE(R&B) in Jun 2015.

BE3 ABE10

41 Bridge at PADERIKADAVU Kunnamangalam 20/2015Awaiting reply of clarification sent to CE(R&B) in Jun 2015.

BE4 AD2

42 NADERIKKADAVU bridge 48/2014 TGD completed in May-2018 BE4 ABE10

43 THRIKUTTISERRY Bridge 42/2017 TGD completed in August 2017 BE4 ABE10

44 MUZHAPPALAM bridge 41/2017 TGD completed in Oct 2017. BE4 ABE10

45 Subways - 2 Nos NIT Calicut 58/2017TGDcompleted in Feb 2018.GD finalized in May-2018

BE4 ABE10

46 Poonoor Bridge 59/2017 TGD completed in January 2018. BE4 ABE10

47 Chavaramuzhi Bridge 70/2017 TGD under preparation. BE4 ABE10

48 Moorad Bridge 75/2017 TGD completed Feb 2018 BE4 ABE10

49 Munnamannilkadavu Bridge 2018/07 TGD completed Mar 2018 BE4 ABE10

50 Iringal - Moorad ROB 2018/13 TGD completed in April 2018 BE4 ABE10

MALAPPURAM DISTRICT

1 CHEERPUNGALTHODU Bridge Thirungadi 46/2010 Design Completed in Aug 2013 BE4 AD5

2 VADAPURAM bridge Nilambur 15/2012 Design Completed in Aug 2013 BE2 AD9

3 MELATTUR(Ucharakadavu) Bridge Perinthalmanna 7/2012 Design Completed in May 2014 BE2 AD3

4 THAZHEPALAM bridge Thirur 63/2013Design Completed in Nov 2014.Design of the retaining wall - RE wall recommended.

BE4 AD4

5 THALIYANKUNDU Bridge Wandoor 105/2013 Design completed in Dec 2014 BE3 AD3

6 CHEBRAPALLIYALIl bridge 55/2014 Design completed in Jan 2015 BE2 AD1

Page 4

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

7 MAMPURAM BridgeVengara/Thirur

angadi59/2012 Design Completed in Jan 2015 BE4 AD7

8 PATHIKUZHI bridge Kondotti 24/2012 Design Completed in Apr 2015 BE3 AD1

9 KOOTAPADI Bridge Nilambur 57/2012 Design completed in Sep 2015 BE1 AD7

10 MANNATHIKADAVU Bridge Perinthalmanna 92/2013 Design completed in Feb 2016 BE4 AD9

11 KOOJOOLIKADAVU Tirur 28/2011 Design Completed in Mar 2016 BE3 AD1

12 PERUMKADAVU bridge Eranadu 27/2012 Design completed in Apr 2016 BE2 AD4

13PARAPPANANGADI- PALATHINGAL bridge

Thirurangadi 89/2013 Revised GD UP BE1 ABE8

14 CHOTTUKADAVU Bridge Eranadu 43/2012 Design completed in Nov 2016 BE1 AD7

15 MANANTHALAKADAVU bridge Kondotti 38/2012 Design completed in Jan 2017 BE2 AD7

16 PUTHUR bridge Kottakkal 67/2014 Design completed in May 2017 BE2 AD6

17 ELAMARAM KADAVU bridger Kondotti 28/2012 GAD completed in Dec 2012. Awaiting AS. BE1 AD1

18 ARYANTHODIKA bridge Eranadu 44/2012 Revised TGD despatched BE 3 ABE 8

19 MARATHINKADAVU bridge Nilambur 49/2012 GAD completed in Jun 2013. Awaiting AS. BE2 AD9

20 KALIKADAVU Bridge a/s Kadalundi river Vengara 83/2013 GAD completed in Oct 2013. Awaiting AS. BE2 AD9

21 KARIYANNUR bridge 79/2013 GAD completed in Jul 2014. Awaiting AS. BE2 AD4

22 Bridge at CHENDI Mangada 09/2015 GAD completed in Aug 2015. Awaiting AS. BE1 AD9

23 KAKKATHODU Bridge Wandoor 12/2008 GAD completed in Sep 2015. Awaiting AS. BE3 AD2

24 CHETHU PALAM bridge 50/2015 GAD completed in Jan 2016. Awaiting AS. BE3 AD4

25 PANNIKOTTUMUNDA bridge Malappuram 53/2014 GAD completed in Aug 2016. Awaiting AS. BE1 AD7

26 PANAMPALAM Bridge(Revision) 42/2009 GAD completed in Oct 2016. Awaiting AS. BE4 AD7

27 Bridge at BADHARPALLI 12/2015 GAD completed in Nov 2016. Awaiting AS. BE2 AD1

28 OLAMPAKADAVU bridge(Revision) Ponnani 17/2012 TGAD completed in Nov 2016. Awaiting AS. BE4 AD7

29PARAPPANANGADI - NEW CUTT bridge

13/2015 GAD completed in Dec 2016. Awaiting AS. BE1 AD2

30 AALAM bridge(Revision) Ponnani 9/2012 Revised TGD Despatched in Dec 2016. BE3 AD1

31 KALIKADAVU bridge a/s Thootha river Perinthalmanna

84/2013 GAD completed in Jan 2017. BE3 AD1

32 Enathi Bridge 39/2016 TGD completed in Feb. 2017. BE2 AD4

33 POOKAITHAKADAVU Bridge (NH Dvn) 29/2013 GAD despatched in Mar 2017. BE2 AD5

34 ROB at TIRUR 45/2015 TGAD completed in Apr. 2017. BE1 AD9

35 PATTARKADAVU Bridge Malappuram 28/2014 GD approved. BE4 ABE8

36 Flyover at JASEELA JUNCTION Manjeri 90/2013 Awaiting clarification BE1 ABE8

37Bridge at CHAMRAVATTOM (Karma road Bridges)

Ponnani 37/2017 TGD despatched Nov 2017 BE3 AD9

38Bridge across CANOLI canal (Karma road Bridges)

Ponnai 36/2017 TGD despatched Nov 2017 BE4 AD7

39 PERUMTHURUTHY KADAVU Bridge 10/2017 Revised TGD UP. BE3 ABE8

40 THOOTHAPUZHA Bridge Perintalmanna 14/2008Proposal Dwg completed in Nov 2008. Awaiting feasibility report from CE(R&B)

BE4 ABE8

41 PUZHAKKATHARA Bridge Tirur 21/2008Proposal Dwg completed in Mar 2012. Awaiting feasibility report from CE(R&B)

BE1 ABE8

42 MARANCHERI bridge Ponnani 14/2012Proposal Dwg completed in Jul 2013. Awaiting feasibility report from CE(R&B)

BE1 ABE8

43 Bridge acrossTHUVAKKADU thodu Malappuram 85/2013Proposal Dwg completed in Nov 2013. Awaiting feasibility report from CE(R&B)

BE3 ABE8

44 AKUMBAR bridge Wandoor 93/2013Proposal Dwg completed in Dec 2013. Awaiting feasibility report from CE(R&B)

BE3 ABE8

45 PARUTHIPPATTA-PERIYANGAD Bridge Wandoor 100/2013Proposal Dwg completed in Dec 2013. Awaiting feasibility report from CE(R&B)

BE2 ABE8

Page 5

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

46 IRUMBOTHINGAL KADAVU Bridge Vallikkunnu 91/2013Proposal Dwg completed in Dec 2013. Awaiting feasibility report from CE(R&B)

BE2 ABE8

47KOOTTILATHARA - MANJUKADAVU Bridge

Thirur 101/2013Proposal Dwg completed in Jan 2014. Awaiting feasibility report from CE(R&B)

BE3 ABE8

48 AKKIPURAM bridge 39/2015Feasibility report received. GD under preparation.

BE3 ABE8

49 CHOORIYODU bridge 13/2016Proposal Dwg completed in Jul 2016. Awaiting feasibility report from CE(R&B)

BE3 ABE8

50 Bridge at THUPPANAD 14/2016Proposal Dwg completed in Oct 2016. Awaiting feasibility report from CE(R&B)

BE2 ABE8

51 POORAPUZHA Bridge Thirurangadi 29/2011Awaiting reply of clarification sent to CE(R&B) in Jan 2012 regarding Approval from CRZ, requirement of Bridge cum regulator.

BE1 ABE8

52 MUDHIYAM BEACH Bridge Vallikunnu 48/2013Awaiting reply of clarification sent to CE(R&B) in May 2013 regarding CRZ.

BE4 ABE8

53 PUTHIYAKADAPPURAM bridge Thirur 94/2013Awaiting reply of clarification sent to CE(R&B) in Nov 13, regarding vertical clearance, capacity of friction piles, etc.

BE1 ABE8

54 Mampadu Bridge 16/2005 Proposal despatched. Awaiting feasibility ABE8

55 Nayarthodu Bridge 68/2017 TGD UP BE 3 ABE8

56 Parappanagaadi - Paalatthingal 89/2013 DD UP BE 3 ABE8

57 Kundukadavu Bridge 2018/4 TGD despatched BE 3 ABE8

58 KAKKATHODU Bridge 2018/11 TGD despatched BE 3 ABE8

59 Kariyamthodu Bridge 2018/09 TGD despatched BE 3 ABE8

57 Thirur-Kadalundy RoB 2018/10 CL Despatched BE 3 ABE8

58 Muttikadavu bridge 24/2018 TGD despatched BE3 ABE8

59 Kadavanad bridge 50/2018 TGD UP BE3 ABE8

PALAKKAD DISTRICT

1 KOOLIYATTUKADAVU Bridge (Rev) 31/2010 Design Completed in Jun 2014 BE1 AD9

2 PALOLIKUNDU bridge 34/2014 Design Completed in Feb 2016 BE1 AD8

3 NJETTARAKKADAVU Bridge 49/2010 GAD completed in Jun 2013. Awaiting AS. BE4 AD5

4 Bridge b/w MAPPATTUKARA & ELADU 33/2014 GAD completed in Apr 2016. Awaiting AS. BE1 ABE9

5 Bridge at PALLIKADAVU 42/2015 GAD completed in Jul 2016. Awaiting AS. BE3 AD2

6 PUZHAKKALPADI Bridge (Revision) 48/2010 GAD completed in Dec 2016. Awaiting AS. BE3 ABE9

7 KANNANKUNDU KADAVU bridge(Rev) 62/2012 Revised TGD completed in May 2017 BE3 ABE9

8Bridge across Mulanjoorthode in Palappuram-Kuthiravazhi road

25/2017 TGD despatched on Jan 2018 BE2 ABE5

9 Arangattukadavu Bridge 29/2017 TGD completed. Revised GD despatched BE1 AD9

10 OOTTARA Bridge 32/2015 TGD completed in Aug 2017 BE4 AD3

11 CHULLIMAD Bridge 31/2017 Revised TGD putup BE3 ABE9

12Bridge at Kampa over Kalpathi River (Rev.)

50/2010 Revised TDG despatched Dec 2017 BE4 ABE8

13 MENONPARA bridge 25/2012Proposal Dwg completed in Jul 2012. Awaiting feasibility report from CE(R&B)

BE1 ABE9

14 CHETTIKKAD - AMBZHAKODE Bridge 22/2015Proposal Dwg completed in Sep 2015. Awaiting feasibility report from CE(R&B)

BE1 ABE9

15 NJAVALKKADU Bridge 66/2017 TGD despatched ABE8

16 Bridge across KPIP canal 82/2017 TGD despatched ABE8

17 Bridge at Malampuzha ring road 2/2018 TGD despatched. BE3 ABE7

Page 6

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

18 East Ottappalam bridge 12/2018 TGD despatched. BE3 ABE7

19 Kanniyampuram Bridge 12/2018 TGD despatched BE3 ABE7

20 Korayar Bridge 30/2018 TGD despatched BE3 ABE8

21 Thennilapuram Bridge TGD despatched BE3 ABE8

22 Thorapuram 34/2018 TGD UP BE3 ABE8

23 Odannur Fair TGD putup. BE3 ABE8

24 Ezhuthampara 40/2018 TGD UP BE3 ABE8

25 Mangalam Bridge 43/2018 TGD UP BE3 ABE8

26 Chira Bridge 49/2018 TGD UP BE3 ABE8

27 Kodathur Bridge 48/2018 TGD UP BE3 ABE8

THRISSUR DISTRICT

1 KOLANGATTUKARA Bridge 12/2014 Design Completed in Aug 2014 BE3 AD1

2 KACHERIKADAVU Bridge 55/2010 Design Completed in Oct 2016 BE1 AD9

3 Bridge at AZHIKKODE-MUNAMBAM 13/2009 Revised TGD under preparation BE4 AD9

4 PERUMPUZHA BRIDGE - II 10/2011 GAD completed in Apr 2014. Awaiting AS. BE4 AD7

5 Bridge at PERUMPUZHA 09/2011 GAD completed in Aug 2014. Awaiting AS. BE4 AD3

6 SREEDHARIPALAM Bridge 16/2014Revised TGAD completed in Mar 2017. Fair GD despatched

BE4 AD7

7 KADAMTHODU Bridge 14/2014 GAD completed in Dec 2014. Awaiting AS. BE4 AD4

8 CHALAPADAM - KOOTTALA Bridge 13/2014 GAD completed in Dec 2014. Awaiting AS. BE1 AD8

9 CHAKKALAKADAVU 107/2013 GAD completed in Jan 2015. Awaiting AS. BE1 AD6

10 ARAPPA bridge 63/2014 GAD completed in Apr 2015. Awaiting AS. BE3 AD9

11 PARANOOR - KURITHICHAL Bridge 15/2014 GAD completed in Jun 2015. Awaiting AS. BE3 AD1

12 CHOTTILAPARA - VETTUKAVU Bridge 17/2014 GAD completed in Oct 2015. Awaiting AS. BE2 ABE4

13 KARIMKULAMKADAVU bridge 68/2014 GAD completed in Jan 2016. Awaiting AS. BE2 AD5

14 PULAKKATTUKARA bridge 62/2014 GAD completed in Feb 2016. Awaiting AS. BE3 AD1

15Bridge across MANALIPUZHA in PEECHI

18/2014Alignment revised as per request. Revised GD despatched

BE4 AD9

16 PUZHAKKAL 2nd bridge 29/2016 GAD completed in Dec 2016.DD UP BE3 AD9

17 PUZHAKKAL 1st bridge 30/2016 GAD completed in Dec 2016.DD UP BE3 AD9

18 KETCHERY bridge 27/2016 GAD completed in Dec 2016. Awaiting AS. BE2 AD9

19 GOTHURUTH - PULLUT Bridge 59/2014 GAD completed in Jan 2017. Awaiting AS. BE1 AD8

20 EDATHARAKAVU KADAVU bridge 61/2014Revised TGAD completed in Apr 2017. Clarification letter despatched

BE4 ABE11

21 CHOONDAL para bridge 28/2016 TGAD completed in Mar 2017.DD UP BE4 AD6

22 Parallel bridge to PULLUT BRIDGE 64/2014GD revision requested after site visit. Revised GD despatched.

BE4 AD7

23KONDAZHY - KUTHAMPULLY Bridge (Revision)

24/2011 TGD despatched.October 2017.Fair GD UP BE4 AD9

24 PALAKKADAVU Bridge 19/2014Proposal Dwg completed in Apr 2014. Awaiting feasibility report from CE(R&B)

BE1 AD9

25 CHAKKARAPADAM bridge 08/2016Proposal Dwg completed in Apr 2016. Awaiting feasibility report from CE(R&B)

BE2 AD9

Page 7

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

26 UPPUMTHURUTHY bridge 56/2015Proposal Dwg. completed in Aug 2016.Awaiting feasibility report from CE(R&B)

BE3 AD9

27 Parallel bridge at KANDASAMKADAVU 09/2016 Proposal Dwg. completed in Dec 2016 BE1 AD9

28 ARANGALI KADAVU bridge 53/2015 TGD despatched. BE4 AD9

29 THRIPRAYAR Bridge 54/2017 TGD despatched. Dec 2017 BE3 AD9

30 PARAYANKADAVU Bridge 60/2017 TGD despatched. Dec 2017 BE3 AD9

31 PARAYANTHODU Bridge 3/2018 TGD despatched. BE3 AD9

32 Bridge across Canoli canal 45/2018 BE3 AD9

ERNAKULAM DISTRICT

1 NEERICODE bridge 30/2012 Design Completed on May 2013 BE2 AD5

2 KORANKADAVU Bridge 26/2011 Design Completed on Jun 2013 BE1 AD9

3 NETTOOR-KUNDANNUR Bridge 10/2012 Design Completed on Jun 2013 BE1 AD4

4 THADIKKAKADAVU Bridge Kalamasseri 04/2012 Design Completed on Aug 2013 BE4 AD5

5 KOTHAITHODU Bridge 21/2010 Design completed on Dec 2014 BE2 ABE4

6 ALUNGALKADAVU bridge 35/2012 Design completed on Jan 2016 BE1 AD8

7 VALLUVALLY-THATHAPILLY bridge 47/2012 Design completed on Apr 2016 BE1 ABE6

8 New bridge across PANAMKUTTY river 2/2010Reminder 3 dtd 11.04.14.,CS, position of bore hole, allignment plan etc missing

BE4 ABE6

9Perumbalam-Mukathurkari Ferry - Vattavayalthuruthu bridge

03/2011Work held up as per EE's letter.Work Outsourced.

BE4 ABE6

10KANNEGATTU - WILLINGTONISLAND Bridge across Kumbalom kayal

11/2012 Work outsourced BE2 AD3

11 Foot Bridge at ALUVA MANAPPURAM 25/2014 Design Tender.Work Outsourced. BE4 ABE6

8 NEDUNGAD NAYARAMBALAM 03/2002 Design completed on Nov 2016 BE4 ABE11

9 KEEZHMURIKADAVU Bridge(Rev.) 99/2013 Revised Design completed on May 2017. BE2 ABE4

10CHERANALLUR-ELOOR CHOWKA bridge

02/2016DD dwg. split up into two.2/2(a)&2/2(b). 2/2(a) completed in Mar 2017. Revised GD UP.

BE3 AD9

11 KARIPUZHA Bridge 34/2012 GAD completed in Aug 2012. Awaiting AS. BE3 AD1

12 KURUVAPALLAM bridge 36/2012 GAD completed in Aug 2012. Awaiting AS. BE2 AD9

13 KALATHILKADAVU bridge 31/2012 GAD completed in Aug 2012. Awaiting AS. BE1 AD8

14 AIYROOR bridge 56/2012 GAD completed in Dec 2012. Awaiting AS. BE3 AD2

15 EXCISEKADAVU bridge (MVPA) 54/2013 GAD completed in Dec 2013. Awaiting AS. BE4 AD1

16 KOOVALLUR bridge 30/2015 GAD completed in Sep 2015. Awaiting AS. BE1 AD4

17 KUMBALANGI Bridge (Revision) 30/2010 Revised GD despatched BE2 AD4

18KUTHIATHODU-KUNDOOR Bridge(Revision)

33/2012 Revised GD completed Aug 2017 BE4 ABE6

19 CONVENT BEACH Bridge 24/2010Design Completed in Feby 2012. Revised TGAD despatched Aug 2017

BE4 ABE11

20 MANJERIKUZHY Bridge 15/2016 DD despatched BE2 ABE6

21 RAMANCHIRA Bridge 08/2006Proposal Dwg completed in Nov 2006. Awaiting feasibility report from CE(R&B)

BE1 ABE6

22Bridge b/w POOTHOTTA & VATTAVAYALTHURUTHU

01/2011Proposal Dwg completed in Feb 2011. Awaiting feasibility report from CE(R&B)

BE3 ABE6

23 VALLIKKADA Bridge 19/2012Proposal Dwg completed in Jun 2012. Awaiting feasibility report from CE(R&B)

BE1 ABE6

24 THALIKKATUKADAVU bridge 21/2012Proposal Dwg completed in Jul 2012. Awaiting feasibility report from CE(R&B)

BE4 ABE6

25 Bridge at KETTEZHUTHU KADAVU 28/2013Proposal Dwg completed in Mar 2013. Awaiting feasibility report from CE(R&B)

BE3 ABE6

Page 8

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

26 VADUTHALA - PERANDOOR Bridge 23/2014 TGD despatched. BE1 ABE6

27 ALUPURAM - KAYATHINKARA Bridge 27/2014Proposal Dwg completed in May 2014. Awaiting feasibility report from CE(R&B)

BE1 ABE6

28 PUTHUSSERITHAZHAM Bridge 32/2014Proposal Dwg completed in July 2014. Awaiting feasibility report from CE(R&B)

BE2 ABE6

29 MOOZHIKADAVU Bridge 30/2014Proposal Dwg completed in Aug 2014. Awaiting feasibility report from CE(R&B)

BE1 ABE6

30 MANGALYA KADAVU bridge 35/2015Proposal Dwg completed in Oct 2015. Awaiting feasibility report from CE(R&B)

BE3 ABE6

31Foot bridge EAST MANJANKKAD TO MANJANKKAD

38/2015Proposal Dwg completed in Nov 2015. Awaiting feasibility report from CE(R&B)

BE1 ABE6

32 MARADU-VALANTHAKADU bridge 24/2015

Awaiting reply of clarification sent to CE(R&B) in Jun 2015 regarding possibility of 2 lane bridge. Lr from EE received to give 6m vertical clearance. Clarifications sought regarding alignment and curves

BE2 ABE5

33New Bridge across Periyar river in Kalady

07/2016 TGD completed BE2 ABE6

34 THEVARA-KUMBALAM Bridge 53/2017 Revised. TGD despatched BE1 AD7

35 NAYARAMBALAM-HERBERT Bridge 49/2017Feasibility report received. Final GD under preparation.

BE2 ABE6

36Culverts and retaining walls in the new bye-pass road from Chitrappuzha-Mamala

61/2017 TGD despatched in Dec 2017 BE2 ABE5

37 CHENNAMANGALAM Bridge 67/2017 TGD despatched.. BE2 ABE6

38 Culvert across Mucheripallam thodu 28/2018 GD completed. BE2 ABE6

39 Thuthiyoor Bridge 41/2018 File received on 23/04/2018. TGD UP BE2 ABE6

40 Thevara- Chakkalakkal 42/2018 File received on 23/04/2018. TGD UP BE2 ABE6

IDUKKI DISTRICT

1 Rehabilitation of POOPARA bridge (NH) 04/2013 Design Completed in May 2013 BE4 AD9

2 KSRTC BRIDGE at Munnar(NH) 03/2013 Design Completed in Jan 2014 BE4 ABE6

3 Reconstruction of KALLAR Bridge 22/2014 Design Completed in Mar 2016 BE2 AD7

4Bridge in ANGAMVETTY MADAKKATHANAM road

38/2014 Fair DD despatched in Dec 2017 BE2 ABE4

5 CHERUTHONI bridge 55/2015Awaiting reply of clarification sent to CE(R&B) regarding possibility of 2 lane bridge.

BE4 ABE6

6

Improvements to Udumbamchola 2nd Mile Road (Mangathotty, 40 acre, Tea company,Chappath, & Deshiyam bridges)

45/2017TGD Despatched in 2017.Revision in design (Desiyam & Mangathotty)is required and is under preparation.

BE2ABE6& ABE4

7 ANAKKAYAM Bridge 48/2017 TGD Despatched BE2 ABE6

8 ELLACKAL BRIDGE 73/2017 TGD completed BE2 ABE5

9 VALLAKADAVU BRIDGE 73/2017 TGD completed BE2 ABE5

10 Parathodu Bridge 05/2018 TGD Despatched on March 2018 BE2 ABE4

11 Moolamattom - Vandiperiyar Road

a)Bridge at chainage 14/575 in Moolamattom - Vandiperiyar Road

33/2018(a) BE2 ABE6

b)Bridge at chainage 15/575 in Moolamattom - Vandiperiyar Road

33/2018(b) BE2 ABE4

c)Bridge at chainage 47/075 in Moolamattom - Vandiperiyar Road

33/2018(c) BE2 ABE4

d)Bridge at ULUPOONI in Moolamattom - Vandiperiyar Road

33/2018(d) BE2 ABE6

.File received on 19/.3/2018. TGD under preparation

Page 9

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

e)Bridge at chainage 51/200 in Moolamattom - Vandiperiyar Road

33/2018(e) BE2 ABE4

f)Bridge at chainage 56/650 in Moolamattom - Vandiperiyar Road

33/2018(f) BE2 ABE6

14g)Bridge at ch:60/350 in Moolamattom - Vandiperiyar Road

33/2018(g) BE2 ABE6

KOTTAYAM DISTRICT

1 Bridge at GRAMINCHIRA 55/2012 Design Completed in Jul 2013 BE2 ABE5

2 Bridge at PARACHAL 60/2012 Design Completed in Nov 2013 BE4 AD9

3 ERATTUPETTA bridge 23/2013 Design Completed in Mar 2014 BE3 AD2

4 THARAPPEL KADAVU Bridge 15/2010 Design Completed in Apr 2014 BE4 AD6

5 COMPANYKKADAVU Bridge 03/2013 Revised TGD despatched 03/2018 BE3 ABE5

6 MUTTEDATHUKARIPALAM Bridge 20/2012 Design Completed in Nov 2014 BE2 ABE4

7MUNDAKKAYAM bypass - design of gravity retaining wall

42/2014 Stability check completed in Dec 2014 BE4 AD7

8 MUNDOLIKKADAVU Bridge 61/2013 Design Completed in Mar 2015 BE3 AD2

9Proof checking of RCC box type approach for KANJIRAM Bridge

36/2009 Proof checking Completed in Sep 2015 BE3 AD9

10 KADUTHURUTHY Bridge 62/2010 Design Completed in Jul 2016 BE3 AD2

11Bridge across THENPUZHA AT PULLAKKAYAR

18/2011 GAD completed in Jun 2012. Awaiting AS. BE3 AD2

12 Bridge at PUNNAKKAL KADAVU 61/2012 GAD completed in Apr 2013. Awaiting AS. BE1 AD9

13FLY OVER IN BYEPASS road connecting Kanjirapally town

29/2010 GAD completed in Mar 2014. Awaiting AS. BE2 AD4

14 KOKKATTUKADAVU Bridge 50/2012 GAD completed in Apr 2015. Awaiting AS. BE3 AD3

15 AKKARAPPADAM bridge (Rev) 42/2013GAD completed in Jun 2015. Revied TGD despatched

BE1 AD8

16 VALAYIL KADAVU bridge(Revision) 06/2011 Revised GAD completed in Feb 2017. BE2 AD4

17 MOOLEKADAVU Bridge 03/2005TGAD completed in May 2017.letter fr approved modified alignment sent

BE4 ABE5

18 CHERPUNKAL Bridge(revision) 28/2004 Revised GAD despatched 03/2018 BE1 ABE5

19 ANCHUMANA Bridge 16/2017. TGD despatched in 2017 BE4 ABE5

20 CHUVANNAPLAVU Bridge 27/2013 TGD despatched in 2017 BE2 ABE5

21 MOOLAKKAYAM Bridge 52/2013Proposal Dwg completed in May 2013. Awaiting feasibility report from CE(R&B)

BE1 ABE5

22CHAZHUVELATHUKARY cartable bridge

01/2015Proposal Dwg completed in Jan 2015. Awaiting feasibility report from CE(R&B)

BE1 ABE5

23 MATTATHILKADAVU Bridge 44/2014Proposal Dwg completed in Aug 2016. Awaiting feasibility report from CE(R&B)

BE2 ABE5

24 ERATHUPUZHA Bridge 24/2013

Awaiting reply of clarification sent to CE(R&B) in Mar 2013 regarding chainages of boreholes &sides of the bridges, necessity of foot path,vertical clearance etc.

BE4 ABE5

25 Ret. Wall RIVER VIEW ROAD extn. 51/2015 TGD despatched BE2 AD9

26Bridge b/w Ch. 1/290 & 1/650 of Parakkulam-Thrikkothamangalam road

46/2014Awaiting reply of clarification sent to CE(R&B) in Aug 2016 .

BE2 AD4

27 26th mile bridge 80/2017 TGD despatched 03/2018 BE2 ABE5

28Retaining wall in Kottayam Kumarakom road

32/2016 DD despatched BE2 ABE1

29 Kariyil Thodu 21/2018 TGD despatched 28/03/2018 BE2 ABE5

Page 10

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

ALAPPUZHA DISTRICT

1 MADANASSERIKADAVU bridge 06/2001 Design Completed in Apr 2013 BE3 AD2

2 VAISHAMBHAGAM bridge (revision) 20/2010 Design Completed in Jan 2014 BE1 AD4

3 MUTHALA KURICHIKKAL Bridge 38/2013 Design Completed in Mar 2016 BE3 AD7

4 MUNDAKKAL bridge 22/2011 Design Completed in Aug 2016 BE2 AD3

5 MAKKEKADAVU Bridge 56/2010 Outsourced BE2 AD5

6 VALIAZHEEKAL Bridge 24/2014 Outsourced BE4 AD7

7

Retaining Wall at Parakulam-Ennasserikadavu Thirikothamangalam-Kadamuri-Chakkanchira-Toottachadu Road

File returned Aug 2014

8 AARATTUKADAVU Bridge 32/2011 GAD completed in Jul 2012. Awaiting AS. BE1 AD9

9 K.C BRIDGE upgradation 65/2012 Request for revision of GAD received BE1 AD6

10 IRANIKUDY BRIDGE 29/2014 GAD completed in Oct 2014. Awaiting AS. BE1 AD9

11KOTHARATHODU BRIDGE at Pullangadi

50/2012 GAD completed in Jan 2016. Awaiting AS. BE3 AD3

12 VAKKAYIL bridge 82/2013 GAD completed in Feb 2016. Awaiting AS. BE1 AD7

13 VAZHUVADIKADAVU bridge (rev.) 13/2006Revised TGD despatched and DD for substructure despatched

BE1 ABE3

14 KODUMTHUR-MEPPALAM bridge Harippad 39/2014 TGD despatched on Aug 2017 BE4 AD8

15 KAVAALAM-THATTASSERY Bridge Kuttanad 11/2014 Revised TGD despatched BE1 ABE3

16 PADAHARAM bridge 33/2016 Revised TGD despatched BE4 ABE3

17 KAIPALAKKADAVU bridge 24/2011Final GAD despatched and DD for substructure despatched on April 2018

BE1 AD9

18 PUNNAMADA Bridge 17/2011 TGAD completed in Mar 2017. BE1 AD8

19 KOMMADY Bridge 07/2017 Revised TGD despatched BE1 AD9

20 POWER HOUSE Bridge 06/2017 Revised TGD despatched BE1 AD8

21 KORAMKUZHI Bridge 19/2011 Revised TGD despatched BE1 AD8

19Pathiyoor and Cheriya pathiyoor Bridge

24/2017 TGAD completed in Jun 2017. BE1 AD8

20 Madathilkadavu Bridge Chennithala 35/2017 Revised TGD despached BE1 ABE3

21 PALLATHURUTHY out post Bridge 34/2017 TGD despatched BE1 AD8

22 P. S. KADAVU Bridge 09/2006Proposal Dwg completed in Mar 2007. Awaiting feasibility report from CE(R&B)

BE3 AD8

23Cartable bridge across OLAVAIPU KAYAL

57/2014Proposal Dwg completed in Feb 2015. Awaiting feasibility report from CE(R&B)

BE2 AD8

24 AYYAPARAMBU Bridge Harippad 44/2015Proposal Dwg completed in Jan 2016. Awaiting feasibility report from CE(R&B)

BE1 AD8

25KAINAKARY PANCHAYATHU KADAVU Bridge

06/2016Proposal Dwg completed in Jul 2016. Awaiting feasibility report from CE(R&B)

BE2 AD8

26ROB at Level cross No 43A/E2 across KANICHUKULANGARA Beach Road

04/2014Awaiting reply of clarification sent to CE(R&B) in Jan 2014 regarding GAD of railway portion

BE3 AD2

27Cartable bridge across PANAVALLY KAYAL IN ANJUTHURUTHU

41/2014Awaiting reply of clarification sent to CE(R&B) in Jul 2014

BE2 AD5

28KRISHNAPURAM VADAKKAN VELIYANAD bridge

07/2015Awaiting reply of clarification sent to CE(R&B) in Mar 2015 regarding foundation recommendation

BE1 AD8

29 Muttel Bridge 01/2017 TGD despatched BE3 ABE3

30 Widening of GILLA Court Bridge 05/2017 TGD despatched BE4 ABE3

31 Naluchira Bridge 43/2017 TGD despatched BE1 ABE3

32 THYCHERYTHODU Bridge 47/2017 TGD despatched BE1 ABE3

33 NEDUMBARAKADU Bridge 50/2017 TGD despatched BE1 ABE3

Page 11

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

34 PARK Bridge 78/2017 TGD despatched BE1 ABE3

35 MARKET Bridge 76/2017 TGD despatched BE1 ABE3

36 KOYIKKALPADI Bridge 77/2017 TGD despatched BE1 ABE3

37 KANNISAKADAVU Bridge 83/2017 TGD despatched BE1 ABE3

38 NEDUMUDI CULVERT 01/2018 TGD despatched BE1 ABE3

39 MUTTAR Bridge 25/2018 TGD despatched BE1 ABE3

40 Mukkoduthodu Bridge 29/2018 TGD putup BE1 ABE3

41 Muttel bridge(kayamkulam) 37/2018 TGD despatched BE1 ABE3

PATHANAMTHITTA DISTRICT

1 Bridge at KANAMALA 16/2009 Design Completed in Apr 2013 BE3 AD5

2 ANJILIMOOTTILKADAVU Bridge 48/2012 Design Completed in Feb 2016 BE4 AD5

3 Vadasserikkara Foot overbridge 17/2010 GAD completed in May 2012. Awaiting AS. BE1 AD1

4 VAYARAPPUZHA KADAVU Bridge 39/2009 Revised TGD Despatched. BE2 ABE6

5 NEW KOZHENCHERY bridge 35/2014 GAD completed in Apr 2015. Awaiting AS. BE4 AD7

6 VADASSERIKKARA bridge 20/2016 GAD completed in Dec 2016. Awaiting AS. BE1 AD8

7 Bridge at Pandalam by-pass road 09/2017 TGD completed in Mar 2017 BE3 AD1

8 PARAKADAVU bridge 12/2016 TGD completed in Feb 2017 BE1 AD8

9 MUTHOOR-KUTHUR Bridge 11/2017 TGD completed in Mar 2017. BE2 AD4

10 RANNI VALIYA Bridge 08/2017 TGD completed in Mar 2017 BE4 ABE3

11 KAVUM BHAGAM IDINJILLAM Bridge 12/2017 TGD (REVISION) despatched 03/2018 BE2 ABE4

12 ADOOR TOWN Bridge 13/2017 TGD completed in Mar 2017.DD UP BE2 ABE4

13 CONCORD Bridge 52/2015 Feasibility received. Final GAD putup. BE2 ABE5

14Single lane bridge at Varambinakathu Malikadavu

35/2016 Proposal despatched BE2 ABE4

15 UPADESIKADAVU Bridge 34/2016 Proposal under preparation BE2 ABE6

16Kottappuram Bridge across KIP Canal in Adoor - Anandapally Road

2018/18 TGD despatched on 03/2018 BE2 ABE4

17 KISUMAM Bridge Ranni 32/2018 Insufficient details . Letter despatched BE2 ABE4

KOLLAM DISTRICT

1 KOORYKKUZHY bridge Kunnathur 16/2012 Design Completed in Jul 2013 BE4 AD6

2 EZHAVAPPALAM Bridge Kollam 46/2013 Design Completed in Nov 2013 BE4 AD7

3 Bridge at PALLIKKAMANNADI Chattannur 39/2010Design Completed in Mar 2014. Revision of TGD to be taken up.

BE3 ABE2

4 PALLIMON Bridge Kundara 44/2013 Design Completed in Mar 2014 BE2 AD6

5 Reconstruction of KANDANCHIRA CHEEP Bridge

Kollam 69/2012 Design Completed in May 2014 BE2 AD2

6Bridge connecting ISLANDS IN SAKTHIKULANGARA

51/2010 LA issues -- dropped. Current status asked BE3 AD3

7 Bridge at MARAKKULAMKADAVU Chatthannur 01/2013Awaiting reply of clarification sent to CE(R&B) in Dec 2012 - Work outsourced

BE1 AD8

8 PARAPPAYAM Bridge (Rev) 9/2005 Design Completed in Jun 2015 BE1 AD1

9PADAPPAKARA-KUTHIRAMUNAMPU-MANAKKADAVU bridge

Kundara/Kunnathur

64/2012 GAD completed in Jun 2014. Awaiting AS. BE4 AD4

10 KALCHIRAPPALLY Bridge Kottarakkara 59/2010 GAD completed in Jun 2011. Awaiting AS. BE4 ABE11

11 KOZHIPPALAM Bridge Punalur 66/2013 TGD Completed. BE3 ABE2

12 KANNANKADU Bridge Kunnathur 75/2013 TGD despatched BE4 ABE2

Page 12

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

13 ARAKKADAVU Bridge Kottarakkara 74/2013 DD despatched(substructure). BE2 ABE3

14 KONNAYIL KADAVU Bridge(Revision) Kunnathur 57/2010 Revised GAD completed in Feb 2017. BE4 ABE5

15CHETTIYARAZHIKATHU KADAVU bridge (Rev)

Kottarakkara 39/2013GAD completed in Jul 2013. Revised TGAD completed in Jun 2017.

BE1 AD8

16 KAKKATTUKADAVU Bridge Kunnathur 77/2013Proposal Dwg completed in Sep 2013. Awaiting feasibility report from CE(R&B)

BE1 AD8

17 CHELONGOTTU KULANGARA BridgeKunnathur/Kar

unagappally73/2013

Proposal Dwg completed in Jul 2013. Awaiting feasibility report from CE(R&B)

BE2 AD3

18 Bridge at ARULAPPANTHURUTHU Chavara 47/2014 TGD despatched. BE2 AD4

19 KACHIKADAVU bridge Eravipuram 37/2014Proposal Dwg completed in Oct 2014. Awaiting feasibility report from CE(R&B)

BE3 AD9

20 Extension of ASRAMAM LINK ROAD Kollam 07/2014Proposal Dwg completed in Jan 2016. Awaiting feasibility report from CE(R&B)

BE4 AD1

21 ELAVOOR bridge Kundara 49/2015 TGD putup BE2 AD3

22 CHITTUMOOLA ROB 04/2016Awaiting reply of clarification sent to CE(R&B) reg railway consent,approved alignment,in Jan 2016

BE1 AD8

23 Construction of gabbion wall - NH744 18/2016Poof checking of the design completed in Sep 2016

BE4 ABE3

24Extension of Asramam link road - Phase 4 extension upto Thoppilkadavu

Kollam 23/2016Authenticated details not received, Clarification reg consent from IWA, approved alignment plan etc

BE1 ABE3

25 Fathima island Mukkathukadavu bridge 30/2017 TGD Despatched BE1 ABE3

26 PERUMON MANROETHURUTHU bridge 33/2017 Revised TGD Despatched BE1 ABE3

27 PONMANA bridge 32/2017 Clarification reg height of bridge sought. BE1 ABE2

28 Vettiyathode bridge 11/2008 TGD despatched on Oct 2017 BE1 ABE1

29 Kazhuthuruthi bridge 79/2017 Proof checking letter despatched BE1

30Extension of Asramam link road - Phase 3

81/2017 Proof checking letter despatched BE1 ABE3

31 Rehabilitation of Ayoor Bridge 6/2018 Rehabiltation Scheme despached BE1 ABE3

32 Sree Sastha Amalakadavu Bridge 20/2018 TGD despatched BE1 ABE3

THIRUVANANTHAPURAM DIST.

1Bridge at KEEZHAPALOOR PARANDODE - MEENANKAL road

Aruvikkara 43/2013 Design Completed in Apr 2013 BE1 AD7

2 Bridge at PANNIKKUZHI Aruvikkara 34/2013 Design Completed in May 2013 BE2 AD1

3 10TH MILE STONE Bridge at Karakulam. Nedumangadu 41/2010 Design Completed in Jun 2013 BE3 AD9

4 KEEZHAROORKADAVU bridge Kattakada 32/2012 Design Completed in Nov 2013 BE3 AD6

5 Bridge at ANIYILAKADAVU 5/2011 Design Completed in Feb 2014 BE1 AD8

6 Reconstruction of MOOLAYAM bridge Nedumangadu 7/2013 Design Completed in Feb 2014 BE3 AD2

7Reconstruction of PUTHUKURICHY Bridge

58/2013 Revised TGD despatched. BE1 AD7

9 Reconstruction of PONNARA bridge 09/2013 Design Completed in Mar 2014 BE1 AD6

10 KOOVAKKUDI Bridge Aruvikkara 45/2013 Design Completed in Mar 2014 BE3 AD3

11 ROB at KAZHAKKUTTOM Kazhakkuttom 15/2009 Design Completed in May 2014 BE4 AD5

12 KANNIPURAM bridge Neyyattinkara 33/2013 Revised TGAD completed in Mar 2017. BE4 ABE2

14 PONGUMOODU- PUNNAVOOR bridge Nemam 12/2011 Design Completed in Aug 2014 BE2 AD4

15 VENKODE bridge Parassala 05/2013 GD Despatched in Dec2017 BE1 ABE1

Page 13

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

16 PANCHIKKATTUKADAVU bridge Neyyattinkara 06/2013 Design Completed in Dec 2014 BE2 AD4

17 MULLARAVILA Bridge Neyyattinkara 38/2004 Revised TGD despatched. BE1 ABE1

18 Ret Wall in NETTICHIRA-VELLANAD road

01/2016 Proof checking completed in Feb 2016 BE1 AD4

19Construction of compound wall, RCC wall etc. at Mannanthala Govt. Press

22/2016 Design Completed in Oct 2016 BE2 ABE4

20 NEYYAR bridge Parassala 70/2013 Design Completed in May 2016 BE4 AD7

21 Bridge at PARUTHOOR 62/2013 Design Completed in Jul 2016 BE2 AD1

22 MYLOTTUMOOZHY bridge Aruvikkara 72/2013 Design Completed in May 2016 BE1 AD4

23 PONNAM CHUNDU bridge Aruvikkara 32/2013 DD completed in Jul 2016. BE4 AD6

24 ROB at CHIRAYINKEEZHU

Chirayinkeezh 52/2010 GAD completed in Dec 2010. Awaiting AS. BE2 AD6

25 MOOTHALA bridge 18/2013 GAD completed in Mar 2013. Awaiting AS. BE1 AD6

26 THIRUVALLAM PANATHURA bridge 30/2013 GAD completed in Mar 2013. Awaiting AS. BE2 AD1

27 New bridge near MADHUPALAM 37/2013 GAD completed in Apr 2013. Awaiting AS. BE4 AD7

28 VALIKODE bridge Nedumangadu 52/2012 TGD Despatched in Jan 2018 BE1 ABE1

29 CHANGADAKADAVU bridge Parassala 29/2012 GAD completed in Jul 2013. Awaiting AS. BE1 AD7

30 KATTUMURACKAL bridge 67/2013 GAD completed in Jul 2013. Awaiting AS. BE4 AD1

31Bridge at CHETTACHAL SOORYAKANTHI

Aruvikkara 49/2013 GAD completed in Aug 2013. Awaiting AS. BE2 AD1

32 Bridge at THOTTATHINKADAVU Aruvikkara 47/2013 GAD completed in Aug 2013. Awaiting AS. BE3 AD2

33 PLAMPAZHINJI bridge Parassala 103/2013 TGD despatched. BE1 ABE1

Page 14

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

34 PUTHENTHOPPU bridge 10/2014 GAD completed in Dec 2014. Awaiting AS. BE4 AD2

35 Bridge at MUDAVANMUGHAL 51/2013 GAD completed in Jul 2015. Awaiting AS. BE1 AD6

36 CHITTAR Bridge 03/2015 GAD completed in Oct 2015. Awaiting AS. BE2 AD4

37 MANGOTTUMOOLA PERAKAM bridge 54/2015 TGAD completed in Dec 2015. Awaiting AS. BE2 AD9

38Construction of Retaining wall at Pulayanarkotta old age home.

42/2016 Design completed Mar 2017. BE3 AD1

39 Bridge at ARUVIKKARA-CHANICHALKADAVU

Aruvikkara 35/2013 GD up BE1 ABE1

40 KUDUVEETTIL KADAVU bridge Parassala 21/2016 GAD completed in Oct 2016. Awaiting AS. BE4 AD7

41CHERKKRAM bridge at Nagaroor-Karette road

46/2015 Fair TGD put up BE3 ABE8

42 Improvements of Palode -Brimore road 21/2017 DD despatched on April 18 BE2 AD6

43 MURINJA PALAM Bridge(Rev) 13/2011 GD Despatched BE1 ABE1

44Bridge at Amaravila-Ottasekharamangalam road

19/2017DD despatched and revised GD and DD for footbridge putup

BE1 ABE3

45 Bridge across THETTIYARTHODU 39/2012 GAD under preparation BE1 AD9

46 KUMBICHAL KADAVU Bridge Parassala 15/2017 GD despatched in July 2017 BE4 AD6

47 KALLADI MUKHAM Bridge 04/2005 TGD despatched. BE3 AD1

48 Cherukayalkara Bridge 20/2017 GD & DD despatched in Dec 2017 BE2 AD4

49KIIFB- Four laning at Vazhayila-

Pazhakutty-Kacherinada- 11 th stone26/2017 TGD despatched. BE4 AD7

50 Bridge at THENNOOR Vamanapuram 2/2012Proposal Dwg completed in Feb 2012. Awaiting feasibility report from CE(R&B)

BE1 ABE1

51 MEENMOODU Bridge Vamanapuram 96/2013 TGD Despatched BE1 ABE1

52Bridge at CHERUPALODE-MENAMCODE VAZHAYILA Vattiyurkavu

41/2015Proposal Dwg completed in Oct 2015. Awaiting feasibility report from CE(R&B)

BE2 ABE1

53 NAGAROOR bridge 33/2015Proposal Dwg completed in Nov 2015. Awaiting feasibility report from CE(R&B)

BE1 ABE1

54Bidge at KOCHUPALAM in Kilimanoor-Attingal road

40/2015Proposal Dwg completed in Dec 2015. Awaiting feasibility report from CE(R&B)

BE1 ABE1

55 New bridge in THIRUVALLAM EDAYAR 25/2015Proposal Dwg completed in Jan 2016. Awaiting feasibility report from CE(R&B)

BE1 ABE1

56Bridge b/w BEEMAPALLY-PARUTHIKUZHI (NH bypass)

Thiruvananthapuram

14/2009Awaiting reply of clarification sent to CE(R&B) in Apr 2009 regarding Design detais, allignment plan, etc.

BE2 ABE1

57 Bridge over KADINAMKULAM KAYAL 09/2010Awaiting reply of clarification sent to CE(R&B) in Apr 2010 regarding bore holes.

BE3 ABE1

58 POZHIYOOR Foot Bridge 34/2011Awaiting reply of clarification sent to CE(R&B) in Jan 2012.

BE4 AD1

59 ROB at CITY ROAD, Karamana 12/2013Awaiting reply of clarification sent to CE(R&B) in Feb 2013 regarding alignment plan, Borehole, chainages.

BE1 ABE1

60 KALLUPALAM bridge Kattakada 98/2013 TGD despatched in March 2018 BE1 ABE1

61 KEEZHARANOOR Bridge 19/2016Awaiting reply of clarification sent to CE(R&B) in Jul 2016 regarding foot path.

BE3 ABE1

62VISL-Vizhinjam international terminal bridge on 2Km connectivity road

07/2011 No Action BE2 ABE1

63 Re-construction of Attipara Bridge 39/2012 Awaiting Feasibility report. ABE1

64 Retaining wall at Adupukuttanpara 39/2017 Tentative GD despatched in Oct 2017 BE1 ABE1

65Flyover between Karakulam Jn & Keltron Jn

Nedumangad 40/2017 GD despatched in Sept 2017 BE1 AD7

66Retaining wall at Medical College Pangappara

51/2017 TGD despatched in Dec 2017 BE1 AD7

Page 15

Sl. No Name of bridge ConstituencyDesign file

No.Remarks/Status DD AD

STATUS OF BRIDGE DESIGN WORKS AS ON 14-05-2018

67 Retaining wall at Govt. M.C Hostel 63/2017 DD despatched in Dec 2017 BE1 AD7

68Proof Checking of Mangottukadavu Steel Bridge

GL/2017 Comments despatched BE3 AD9

69 Pallathukadavu Bridge 05/2012 Revision request received,UP BE1 ABE1

70 Anappadu Bridge 95/2013 TGDdespatched in March 18 BE1 ABE1

71 Kulashekharam Bridge 20/2005 TGD Despatched in Jan 2018 BE1 ABE1

72 Vallakkadavu Bridge 8/2000 New alignment received. UP BE1 ABE1

73RICK-SRIP KARAMANA-VELLARADA ROAD IPRMNT

64/2017Clariffication letter Despatched on Nov 2017.Design completed(TGD)

BE1 ABE1

74 KALLIKKADU BRIDGE 16/2018 TGD despatched BE1 ABE1

75 VENJARAMOODU BYPASS 17/2018 TGD UP BE1 ABE1

76PAZHAKUTTY MANGALAPURAM ROAD

19/2018 TGD UP BE1 ABE1

77Improvements to TVM-Neyyar dam road(3 bridges)

39/2018 TGD UP BE1 ABE1

78NH 47 Fouur laning. Phase I -Reach II Karamana-kaliyikkavila(pallichal)(2

44/2018 TGD UP BE1 ABE1

79Improvements to Killy-EMS Academy(2 bridges)

47/2018 Reconstruction not required BE1 ABE1

AD1 AD9(Addl. Charge) BE1

AD2 Smt. Helena BE2 Sri. Suju P S

AD3 AD2 (addl. charge) BE3

ABE4 Smt.Silpa C Sreedharan BE4

ABE5 Smt. Lekshmi P V

ABE6 Smt. Suma R Nair

AD7 Sri. Arun K V

AD8 Sri. Sujith P R TGAD

AD9 Sri. Sony J S D GAD

ABE8 Sri. Kannan P DD

ABE1 Sri. Deepak P S UP

ABE11 Sri Remil K

ABE10 Sri Arun K S

Assistant Directors Deputy Directors

Smt. Anithakumari K

Smt. Divya J Satheesh

-Sd/- Saju S.

Joint Director

Asst. Engineers or Asst. Executive Enginees of the concerned work shall call the concerned Assistant Director (AD) / Deputy Director (DD) listed below through Landline No.: 0471-2322029 or email to [email protected] for

clarifications or suggestions, if any, regarding the design of the above bridge works.

Smt. Phoenix S S

Tentative General Arrangement Drawing

General Arrangement Drawing

Detailed Design Drawing

Under preparation

Page 16