Sri Lanka: Wind Power Generation Project

199
External Environmental Monitoring Report Project No. 49345-002 Quarterly Report November 2019 Sri Lanka: Wind Power Generation Project Prepared by the Ceylon Electricity Board, Government of Sri Lanka for the Asian Development Bank.

Transcript of Sri Lanka: Wind Power Generation Project

External Environmental Monitoring Report

Project No. 49345-002 Quarterly Report November 2019

Sri Lanka: Wind Power Generation Project

Prepared by the Ceylon Electricity Board, Government of Sri Lanka for the Asian

Development Bank.

This external environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

i

Environmental & Biodiversity Monitoring Report

Report: 02 Quarterly Report: Period: From July 01,2019 to September 30, 2019

Project No. 49345-002

Sri Lanka: Wind Power Generation Project

Project No. 47037-005

SRI: Green Power Development and Energy Efficiency Improvement Investment Program – Tranche 2

Package 2: Lot A - Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33 kV Grid Substation

Package 2: Lot B1 - Construction of Mannar - Nadukuda 220 kV, 30 km Transmission Line

Prepared by the Ceylon Electricity Board (CEB), Government of Sri Lanka for the Asian Development Bank

ii

CURRENCY EQUIVALENTS (as of 01 May 2019)

Currency Unit = Sri Lanka Rupees (SLR) SLR 1.00 = US $ 0.0057 US $1.00 = SLR 176.22

ABBREVIATIONS

ADB – Asian Development BankAMSL – Above Mean Sea LevelBMP – Biodiversity Management PlanCEA – Central Environmental AuthorityDS – Divisional SecretaryDWLC – Department of Wildlife ConservationEA – Executing AgencyEHS – Environment, Health & SafetyEIA – Environmental Impact AssessmentEMP – Environmental Management PlanEMoP – Environmental Monitoring PlanEPL – Environmental Protection LicenseGPD&EEIIP – Green Power Development and Energy Efficiency Improvement

Investment ProgramGoSL – Government of Sri LankaGRM – Grievance Redress MechanismH&SP – Health and Safety PlanIFC – International Finance CorporationNEA – National Environmental ActO&M – Operation and MaintenancePAC – Project Appraisal CommitteePD – Project DirectorPIU – Project Implementation UnitPMU – Project Management UnitPPE – Personal Protective EquipmentRDA – Road Development AuthorityREA – Rapid Environmental AssessmentRoW – Right of WaySPS – Safeguard Policy Statement

WEIGHTS AND MEASURES

km – kilometerkm2 – square kilometerm2 – square metermm – millimeterkV – kilovoltkW – kilowattMW – Mega Watt

iii

NOTES (i) In this report, "$" refers to US dollars. (ii) The fiscal year (FY) of the Government of Sri Lanka and its agencies is the Calendar Year

External Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

iv

Contents

1.0 Introduction .................................................................................................................... 1

1.1 Project description ..................................................................................................... 1

1.2 Objectives of the project ............................................................................................ 1

1.3 Environmental category as per ADB Safeguard Policy Statement (2009) ............ 2

1.4 Monitoring requirement ............................................................................................. 2

1.5 Objectives of the Assignment ................................................................................... 2

1.6 Objectives of this Report ........................................................................................... 2

1.7 External Monitoring of the implementation of the EMP .......................................... 3

2.0 Implementation of the EMP and the BMP .................................................................... 4

2.1 Methodology ............................................................................................................... 4

2.2 Project EMP/BMP Readiness Assessment ............................................................... 5

2.3 Compliance Report ..................................................................................................... 6

2.3.1 Compliance with National/Local statutory environmental requirements ............ 7

2.3.1.1 Wind Power Generation Project .................................................................... 7

2.4 Project Progress ......................................................................................................... 8

2.4.1 Wind Power Generation Project .......................................................................... 8

2.4.2 Construction of the Transmission Line and the Grid Sub-Stations ..................... 10

2.4.2.1 Progress Status of the Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line .............................................................................................. 10

2.4.2.2 Augmentation at Mannar 220/33kV Grid Substation ................................... 11

2.5 Implementation arrangement of the EMP /BMP ..................................................... 11

2.6 Implementation of the Environmental Management Plan ..................................... 12

2.6.1 Wind Power Generation Project ...................................................................... 12

2.6.2 Construction of the Transmission Line and the Grid Sub-Stations .................. 26

2.7 Implementation of the Biodiversity Management Plan ......................................... 36

3.0 Implementation of Monitoring Plans.......................................................................... 39

3.1 Implementation of the Environmental Monitoring Plan ........................................ 39

3.1.1 Wind Power Generation Project ...................................................................... 39

3.1.2 Construction of the Transmission Line and the Grid Sub-Stations .................. 42

3.2 Implementation of the Biodiversity Monitoring Plan (BMP) ................................. 44

3.2.1 Wind Power Generation Project ...................................................................... 44

3.2.2 Construction of the Transmission Line ................................................................. 46

3.3 Marine Environmental Monitoring ........................................................................... 48

4.0 Summary ...................................................................................................................... 51

Annexes

1. Photographs taken during field visits2. Summary of consultations3.1 Monitoring Reports and other data- Wind Farm

4.1 Summary of Environmental Safeguard Monitoring Reports Received 4.2 Comments on Environmental Safeguard Monitoring Report

3.2 Monitoring Reports and other data- Transmission Line and Grid Substation

v

LIST OF FIGURES

Figure 2.1 Flow chart for the environmental monitoring process 4

Figure 2.2 Status of Project Implementation 9

LIST OF TABLES

Table 2.1 Project EMP/BMP Readiness Assessment 5

Table 2.2 Compliance status with environmental loan covenants 6

Table 2.3 Approvals/Clearances/Permits obtained for the Wind Power Generation Project

7

Table 2.4(a.1) Proposed Sequence for Project Implementation 8

Table 2.4(a.2) Summary of the Project Implementation Schedule 10

Table 2.4(b.1) Summary of the Project Contracts 10

Table 2.4(b.2) Project Progress Status and Implementation Schedule- Transmission Line

11

Table 2.4(b.3) Project Progress Status and Implementation Schedule- Grid Substation

11

Table 2.5 Project Implementation/safeguard team 11

Table 2.6 Monitoring of implementation of Environmental mitigation measures – Wind Farm (Environment Management Plan (EMP)

12

Table 2.7 Monitoring of the implementation of Environmental mitigation measures – Transmission Line and the Grid Sub-Stations

26

Table 2.8 Mitigating potential impacts to Marine biology- Wind Power Generation Project

37

Table 2.9 Monitoring mitigating of potential impacts to Marine biology- Transmission Line

38

Table 3.1 Environmental Parameters and Periodicity for Environmental Monitoring Plan- Wind Power Generation Project

39

Table 3.2 Environmental Parameters and Periodicity for Environmental Monitoring Plan- Transmission Line and the Grid Sub-Stations

42

Table 3.3 Monitoring of implementation of Biodiversity Monitoring Plan (BMP) for Wind Farm

44

Table 3.4 Monitoring of implementation of Biodiversity Monitoring Plan (BMP) for Transmission line (Vankalalai sanctuary)

46

Table 3.5 Monitoring of Marine Environment 48

Table 4.1 Overall Compliance with EMP/ EMoP 52

1

1.0 Introduction

1.1 Project description

The Ceylon Electricity Board (CEB) is planning to build and operate a semi-dispatchable wind farm of 100 MW capacity and associated 220 kV transmission line (29.1 km) in the Mannar region under financial assistance of the Asian Development Bank (ADB) under (i) Wind Power Generation Project, and (ii) Green Power Development and Energy Efficiency Improvement Investment Program – Tranche 2. The wind energy conversion systems (WECS) would be selected for the proposed wind farm to generate clean electrical energy sustainably. The proposed Wind Power Park will be located in the southern part of Mannar Island from Thoddaveli for a length of about 12 km along the coast. A row of 30 (+3 locations set aside for the time being) turbines will be installed parallel to the shoreline. The proposed wind farm has excluded the areas belongs to Adam’s Bridge Marine National Park which has been declared in 2015. The nearest village is located about 800 m away from the second row of wind turbines. Also, several Navy camps/ Navy observation points, boat landing sites, Ma-del hauling sites, and fishermen vaadi/camps (seasonal) and a tourist hotel are found within the wind farm block.

1.2 Objectives of the project

The components of the project are as follows:

1. Sri Lanka: Wind Power Generation Project (Project No. 49345-002): Integrate the 100 MW power from the Mannar Wind Power Generation Project to National Grid network of Sri Lanka.

2. Green Power Development and Energy Efficiency Improvement Investment Program (GPD&EEIIP) - Tranche 2 (Project No. 47037-005)

- Package 2: Lot A - Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation

- Package 2: Lot B1 - Construction of 30 km long Mannar–Nadukuda 220 kV transmission line

The impact of the investment project will be increased access to clean and reliable power supply enhanced by 2025. The outcome will be clean power generation increased. The outputs of the investment project are:

(i) Wind power generation increased. This output consists of three subcomponents: (i) 100 MW wind farm constructed in Mannar Island in the Northern Province; (ii) wind park infrastructure developed that involves construction of the wind park's internal medium voltage infrastructure, internal cabling, access roads, and other arrangements; and (iii) a renewable energy dispatch control center established to forecast, control, and manage intermittent 100 MW wind power generation.

(ii) System reactive power management improved. This includes installation of 100 megavolt-ampere reactive (MVAr) reactors at the 220 kilovolt (kV) level at the Anuradhapura grid substation in the North Central Province and a 50 MVAr reactor at the 220 kV level at the Mannar grid substation in the Northern Province to manage voltage levels within the planning limits and practical operational requirements, and ensure reliable operation of the wind park.

(iii) The capacity of CEB in project engineering design review and supervision strengthened. Expert consultancy services will be procured to strengthen CEB's capacity in project engineering design, review, and supervision. These advisory consultancy services will assist CEB in ensuring engineering oversight of wind turbine installation, commissioning and testing activities, and technical certification of contractor's activities throughout the construction period.

2

1.3 Environmental category as per ADB Safeguard Policy Statement (2009)

ADB is extending loan assistance to Sri Lanka’s power sector for Green Power Development and Energy Efficiency Improvement Investment Program with a focus to identify the transmission and distribution projects for the evacuation of renewable energy (wind and solar) parks/ projects and overall improvement of network efficiency. The following are the Project Categorization based on the ADB SPS (2009):

Safeguard Categories

Environment A

Involuntary Resettlement B

Indigenous Peoples C

1.4 Monitoring requirement

The proposed project is located close to the three protected areas: viz., Vankalai Sanctuary, Adams Bridge Marine National Park and Vidathalathivu Nature Reserve. The transmission line passes through Vankalai Sanctuary (7.5 km) which is legally protected under the Fauna and Flora Protection Ordinance and is also designated as a wetland of international importance (Ramsar Sites) under the Ramsar Convention. Due to the location sensitivity of the proposed project, it is considered as a ‘Category A’ project under the ADB Environmental Safeguard project categorization (ADB SPS, 2009). Accordingly, an Environmental Impact Assessment (EIA) was carried out by the Ceylon Electricity Board (CEB), who is the project proponent. In the EIA report, applicable laws/legislation and policy framework have been reviewed, and environmental mitigation measures have been recommended for implementation during construction and operation stages of the project and its associated facilities. Accordingly, a comprehensive Environmental Management Plan (EMP), and Environmental Monitoring Plan (EMoP) were provided with guidelines for detailed construction method statement to be prepared by the Contractor (and sub-contractors). Also, a Biodiversity Management Plan (BMP) has been formulated to ensure no net loss of biodiversity. This Biodiversity Management Plan (BMP) falls under the EMP and is a part of the package of activities designed to meet the requirements of ADB’s Safeguards Policy Statement (SPS) 2009.

1.5 Objectives of the Assignment

The objective of this assignment is to monitor the implementation of relevant mitigation measures recommended by the EMPs/EMoPs and implementation of measures proposed in the BMP for three years during construction and further two years during the operations.

1.6 Objectives of this Report

The Environmental Specialist and the Biodiversity Specialist have now mobilized and commenced the work on External Monitoring of implementing the EMP, BMP and the EMoP by the Project Proponent, Contractors, and sub-contractors of the Mannar Wind Power Generation Project and Package 2 Lot A and Lot B1 of the GPD&EEIIP. The Consultants first met the officials of the Ceylon Electricity Board and collected the documents prepared which described the EMP, BMP and the EMoP for each of the main components of the project. Subsequently, they visited the project areas in Mannar on 19th and 20th October 2019.

This report serves as the Quarterly Report No. 2 (covering the period of 1 July 2019 to 30 September 2019) of the External Monitoring of the implementation of the EMP, BMP and EMoP. The Quarterly report submitted for 1 April 2019 to 21 June 2019 mainly concerned

3

about the project readiness and compliance of project interventions with local environmental regulations, implementation of the EMP and the EMoP. However, this report and the subsequent ones will mainly focus on the implementation of the EMP and the EMoP. However, any compliance requirements that arises during construction stage will also be included when and where they are pertinent.

1.7 External Monitoring of the implementation of the EMP

The scope of the work of the Environmental specialist / Biologist for external monitoring of the implementation of the EMP includes:

(i) Perform independent third-party monitoring on the implementation of mitigation and monitoring activities on the physical and ecological environmental components.

(ii) Development of the appropriate methodology and tools for monitoring process, design appropriate forms, formats, schedules and prepare other documents required for successful monitoring activities. Conduct field visits before construction, during project construction and operational period to monitor the implementation of relevant mitigation measures recommended by EMPs/EMoPs.

(iii) Review of mitigation measures and provide advice and guidance on improvements, corrective measures for any shortcomings.

(iv) Assist the implementing agency and Project Implementation Units (PIUs) in making sure the project development is in compliance with the environmental management plan (EMP) and environment protection requirements.

(v) Verify whether the set environmental targets are achieved and recommend remedial measures are adopted.

(vi) Conduct field investigation and monitoring on project environment protection and management regularly.

Submission of environmental monitoring reports to the CEB and ADB, quarterly during the construction phase.

4

2.0 Implementation of the EMP and the BMP

2.1 Methodology

The general approach for external monitoring of the implementation of the EMP/BMP and the EMoP. The monitoring approach for environmental monitoring will comprise of the preparation phase, field phase, and desk phase. In the preparation phase, project EMP and BMP readiness will be carried out at the preparation phase by reviewing the EIA reports and the BMP Report, EMPs/EMoPs and provide a recommendation for improvements (Figure 2.1).

During the field phase, implementation of mitigation measures for physical environmental components will be monitored based on major project components which are identified as:

1. Sri Lanka: Wind Power Generation Project: 100 MW power from the Mannar Wind Power Generation Project

2. Green Power Development and Energy Efficiency Improvement Investment Program (GPD&EEIIP) - Tranche 2

• Package 2: Lot A - Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation

• Package 2: Lot B1 - Construction of 29.1 km long Mannar–Nadukuda 220 kV transmission line

Figure 2.1: Flow chart for the environmental monitoring process (quarterly during the construction phase and semi-annually during the operational phase)

Desk Phase

Oversee implementation of necessary corrective actions and highlight good practice

Provide technical guidance/ feedback to improve and implementation of mitigation

measures in EMPs/ EMoPs.

Field Phase

Monitor the implementation of mitigation of physical and biological/ecological

environmental impacts

Assess the consistency and accuracy with site conditions and compliances.

Preperation Phase

Review the EIA reports, EMPs, BMP and EMoPs

Adequacy checking and provide recommendations for improvement

5

2.2 Project EMP/BMP Readiness Assessment

The Consultants have first assessed whether project proponent is ready to proceed with the proposed construction of the Mannar Wind Power Generation Project and construction of the Transmission Line and the Grid Sub-Station. The Indicators and Criteria are listed below (See Table 2.1).

Table 2.1: Project EMP/BMP Readiness Assessment

Indicator Criteria Assessment

Remarks

EMP - Mannar Wind Power Generation Project

EIA approval and disclosure

The EIA was cleared by ADB and disclosed on ADB’s project website

Yes/No

Mitigation measures as described in the EMP adopted during detailed design and construction, preparation and implementation

Measures defined in EIA and EMP are included in detailed designs for each component.

Yes/No EMP and the EMoP have been included as part of Tender/Contract Documents

EMP update Whether the EMP is updated after detailed design and cleared by ADB.

Yes/No An update was not needed

Compliance with loan covenants

The borrower complies with loan covenants related to project design and environmental management planning.

Yes/No

Environmental Monitoring The monitoring parameters, locations, and methods for the ambient air, noise and surface water defined in the EMoP.

Yes/No

EMP - Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation; Construction of 29.1 km long Mannar–Nadukuda 220 kV transmission line EIA approval and disclosure

The EIA was cleared by ADB and disclosed on ADB’s project website

Yes/No

Mitigation measures as described in the EMP adopted during detailed design and construction, preparation and implementation

Measures defined in EIA and EMP are included in detailed designs for each component.

Yes/No EMP and the EMoP have been included as part of Tender/Contract Documents

EMP update Whether the EMP is updated after detailed design and cleared by ADB.

Yes/No An update was not needed

Compliance with loan covenants

The borrower complies with loan covenants related to project design and environmental management planning.

Yes/No

Environmental Monitoring The monitoring parameters, locations, and methods for the ambient air, noise and surface water defined in the EMoP.

Yes/No

6

BMP

BMP approval and disclosure

The BMP was cleared by ADB and disclosed on ADB’s project website

Yes/No updated BMP reviewed by CEB, and discussions had with DWC, DWC agreed to give the approval.

Measures during detailed design and construction, preparation and implementation

Measures defined in EIA and BMP are included in detailed designs for each component.

Yes/No Complied

BMP update Whether the BMP is updated after detailed design and cleared by ADB.

Yes/No Updated, Complied

Monitoring of implementation of the BMP

The monitoring parameters, locations, and methods defined in the BMP and/or EMoP.

Yes/No Complied

2.3 Compliance Report

The compliance status of the project implementation has two aspects: Compliance status with environmental loan covenants (Table 2.2) Compliance status with National/State/Local statutory environmental requirements (Table 2.3) The purpose of compliance report is to check whether there are any deviations from conditions provided in loan covenants and environmental legislation. If there are any deviations, the action required will be described, in consultation with the PMU. All the consent, approvals, permits, and clearances that are needed for implementation of the project and its interventions have been reviewed and checked as outlined in Table 2.3.

Table 2.2: Compliance status with environmental loan covenants

Activity/Description Status of Compliance/Action Required

Additional Pre-construction (bird) survey

A bird monitoring programme for the development should include continuation of pre-construction base-line surveys for a further year to provide more detailed information about bird activity within the wind farm site.

Hence, a pre-construction (bird) survey has been continued for one-year period until February 2019 to cover full migrating /breeding season by the National Consultant

Photographic Records of the Birds within Wind Farm

The PMU has continued the biweekly photographic records of the birds in the vicinity of the wind farm area. The records are being continued during the migration period and non-migration period.

Consultancy Procurement for Recruitment of a Local Consultancy firm to Monitor the implementation of BMP and EMP

A consultancy firm has been selected for Monitoring the Implementation of BMP and EMP.

This Monitoring Report has been prepared by the Team of External Monitoring Consultants thus selected (Environmental Specialist and Ecologist/Ornithologist)

Photographic records during the site clearance for the wind turbine

A complete surveillance photographic records have been kept during the land cleaning process

7

The Borrower shall ensure that the preparation, design, construction,

implementation, operation and decommissioning of the Project and all Project facilities comply with (a) all applicable laws and regulations of the Guarantor relating to environment, health, and safety; (b) the Environmental Safeguards; (c) the EARF; and (d) all measures and requirements set forth in the respective IEE or EIA, EMP and BMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report

The CEB has indicated that they are taking every effort to comply with the ADB requirement while NOT affecting the completion of the Project.

2.3.1 Compliance with National/Local statutory environmental requirements

2.3.1.1 Wind Power Generation Project

Table 2.3: Approvals/Clearances/Permits obtained for the Wind Power Generation Project

Clearance/ Permit Status

1 Provisional approval from Sri Lanka Sustainable Energy

Authority

Obtained

2 Letter of Intent from CEB to develop the Project N/A

3 Approval from the Coast Conservation Department Obtained

4 Approval from the Divisional Secretary, Divisional Secretariat,

Mannar

Obtained

5 National Water Supply and Drainage Board Approval Obtained

6 Irrigation Department Approval Obtained

7 Mannar District Coordination Committee approval N/A

8 District Land Utility Committee Approval N/A

9 District Environmental Committee Approval N/A

10 District Agricultural Committee approval N/A

11 Approval from the Mannar Pradeshiya Sabah Obtained

12 Generating License To be obtained

13 Civil Aviation Authority Approval for Wind Mast Construction Obtained

14 Approval from Road Development Authority for transportation of

heavy vehicles and equipment

N/A

15 Approval from Department of Agrarian Development, Mannar Obtained

16 Approval from Coconut Cultivation Board N/A

17 Approval from the Ministry of Tourism N/A

18 Approval from the Survey Department of Sri Lanka N/A N/A

19 Approval from the Department of Wildlife Conservation Obtained

20 Approval from the Forest Department N/A

21 Approval from the Ministry of Defense N/A

22 Approval from the Department of Archaeology N/A

23 Solid waste disposal arrangement with Mannar Pradeshiya

Sabha during the operational phase of the project

SWM Plan will be implemented

with the consultation of the PS

8

2.4 Project Progress

2.4.1 Wind Power Generation Project

Table 2.4(a.1): Proposed Sequence for Project Implementation

9

Status of Project Implementation as of 30 September 2019

On-going work

• Main access road works

• Accommodation building column work

• Administration building column work

• Piling work: ongoing -Tower 24 , Completed – Tower 23

• Site clearing for yards and soil storage activities

Main access road works Administration building column work

Ongoing piling work – Tower 24 Soil storage activities

Figure 2.2: Status of Project Implementation

10

Table 2.4(a.2): Summary of the Project Implementation Schedule – Wind Farm

2.4.2 Construction of the Transmission Line and the Grid Sub-Stations

The contract details, including the contract price of the following two lots under Package 2, are as follows.

Table 2.4(b.1): Summary of the Project Contracts

Package 2: Lot B1 Package 2: Lot A

Scope

Construction of Mannar – Nadukuda 220 kV Transmission

Line

Construction of Nadukuda 220/33 kV

Grid Substation & Augmentation at

Mannar 220/33 kV Grid Substation.

Contractor KEC International Limited. Siemens Limited, India

Contract Price including change orders (Equivalent MLKR)

1,379.94 2,697.96

Contract Effective Date October 04, 2017 March 16, 2018

Expected Completion Date January 23, 2020 (with time extension)

March 16, 2020

2.4.2.1 Progress Status of the Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line

The updated status of environment activities during the period of July 1, 2019 to September 30, 2019 is given below for the Transmission Line.

11

Table 2.4(b.2): Project Progress Status and Implementation Schedule

Description Status

Mannar - Nadukuda 22 0kV, 30 km transmission line

1. Profile & Tower designs were completed.

2. 90% of Equipment Procurement is completed

3. Erection of towers are in progress – 56 completed

4. 74 foundations were completed

Source: ADB Loan No: 3483/3484 SRI Quarterly Progress Report, Q3, July-September 2019

2.4.2.2 Augmentation at Mannar 220/33kV Grid Substation

The updated status of environment activities during the period of July 1, 2019 to September 30, 2019 is given below for the Grid Substation.

Table 2.4(b.3): Project Progress Status and Implementation Schedule

Description Status

Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33 kV Grid Substation

1. Design works are in progress up to 70%

2. Equipment procurement is in progress

3. Construction works of Engineer’s accommodation and Control room building are in progress.

4. Transformer foundation works are in progress.

Source: ADB Loan No: 3483/3484 SRI Quarterly Progress Report, Q3, July-September 2019

2.5 Implementation arrangement of the EMP /BMP

Table 2.5: Project Implementation/safeguard team

Name Designation/Office Email Address Contact Number

1. PMU (Transmission)

Eng. H.K.Illeperuma Project Director [email protected] 0714150724

Eng. Anuruddha Tilakaratne

Project Manager [email protected] 0714150634

Eng. K.Ramjee Project Engineer (Electrical)

[email protected] 0718740954

Eng. P.G.W.P.Manjula Project Engineer (Civil) [email protected] 0712309381

2. PMU (Wind Farm)

Eng. D.D.U. Dompage Project Director [email protected] 0714115587

Eng. Ajith Alwis Project Manager (WFS) [email protected] 0714150639

Eng. Thusitha Eranjeewa

Project Engineer (Electrical)

[email protected] 0714150597

Eng. Randula Wijeratne

Project Engineer (Electrical)

[email protected] 0712075174

V. Chandrasegaran ESSS [email protected] 0777253047

12

2.6 Implementation of the Environmental Management Plan

2.6.1 Wind Power Generation Project

Table 2.6: Monitoring of implementation of Environmental mitigation measures – Wind Farm (Environmental Management Plan (EMP)

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

Pre-construction

Temporary use of lands

Impact on the existing environment

39 turbine locations are available for the EPC contractor to use provided they can demonstrate that the impact at receptors will be same or less than that presented in this EIA

Selection of lands adhering to local laws and regulations and in close consultation with LAs

Restrictions on location of temporary infrastructure: Tower foundations should be placed at least 140 m away from the coastline, 25 m from water channels, natural flow paths, important ecological habitats and residential areas.

Air, Water, Noise and Soil quality

The baseline for air pollution, water pollution levels (Air quality Standards, CEA water quality standards and Noise standards etc.)

CEB

Detailed design

This condition/mitigation measure has been complied with.

The locations for the wind turbines have been finalized, and all the locations are at least 140 m away from the coastline.

The selection has been made in compliance to and in accordance with the local laws.

The contract has already measured the baseline parameters on air quality, surface and groundwater and noise and vibration.

All these reports have been submitted

Annex 3.1: Air Quality (Baseline)

Annex 3.2: Noise and vibration (Baseline)

Annex 3.3: Water quality

Annex 3.4: Soil investigation report

Wind turbine generator location and design

Noise generation Exposure to noise, Nuisance to neighboring properties

EPC Contractor to develop communications plan and appoint a fisheries liaison officer and community liaison officer

Undertake pre-construction noise monitoring following IOA and ETSU methodology and collate concurrent wind data at 10 m height for a minimum period of two weeks during the SW and NE monsoon in order that background

Expected noise emissions based on wind turbine generator design, noise levels

Turbine design and

CEB

Detailed Design

EPC contractor has not yet developed the communications plan

Pre-construction noise monitoring has not yet completed.

Detailed designs are not available yet to confirm noise minimization.

Protocol for the operation of low noise mode

13

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

noise levels correlated to wind speed are available during both high and low wind speed seasons

Noise levels should first be minimized through design. Turbines to be sited to ensure noise limits (turbines + background) can be met and minimize the magnitude of change in noise level at adjacent properties Noise assessment following good international practice (assess octave frequencies as well as broadband sound) to be run for final turbine design and layout. The noise modelling assessment must demonstrate that during all months of the year (including the low wind speed season when low noise environment occurs) that the noise limits (B+T) can be met. Turbines must not have a tonal component unless this is included in the noise modelling assessment, and it is demonstrated that the noise limits can be met with it included.

layout and accompanying noise assessment to be cleared by CEB and receive no objection from ADB before CEB can approve the Contractor’s design /

Noise control regulations in 1994 Noise levels to be specified in EIA

(shut down) has to be prepared for implementation during the operational phase

The contract has already measured the baseline parameters on noise and vibration.

All these reports have been submitted (Annex 2)

However, it has to be noted that the Noise levels measurements have been carried out in accordance with the methods laid down In ISO 1996 Part 1, 2 and 3, and BS 4142:1990, as stipulated in National Environmental Noise Control Regulations of 1996.

As suggested in the EMP, the noise levels have to be measured following IOA (Institute of Acoustics) and ETSU-R-97 procedures.

This has been communicated to the Contractor.

The turbine design has yet to be finalized.

Cut and fill operations

Disturbance to the adjacent lands and the people due to cut and fill operations

Maintain clearance, construction of retaining structures, minimize cut and fill operations adjoining to the dwellings

Proximity to houses and other structures / Technical specification

CEB

Detailed Design

This is not applicable, as there are no structures adjoining land plots identified for wind turbines

There are no cuts and fill operations envisaged, other than excavations and trenching for foundations and footings

Location of Wind turbines and their alignment on coast and design

Exposure to safety-related risks

Turbines to be sited to achieve set back of 1.5 x turbine height If 1.5 x turbine height cannot be achieved, RP to be updated to include for resettlement of the affected properties Turbines to be designed with vibration sensors that can react to any imbalance in the rotor blades and shut down the turbine

Turbines to be designed with a lightning

Wind turbine location with respect to nearest dwellings / Setback distances to nearest houses

Review of turbine design and layout including updated blade throw

CEB

Part of detailed survey and design

These conditions have to be confirmed after designs are finalized.

However, there is no resettlement involved in the project.

14

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

protection system

Turbines selected to be subject to independent design verification/certification (IEC 61400-1) and surveillance of manufacturing quality

assessment and operational protocol / No injury or loss of life as a result of blade throw (as per IFC-WB EHS Guidelines on Wind Energy)

Impact on water channels/land/ residences

Consideration of Wind turbine location where they could be located to avoid avian breeding areas, water channels by a minimum of 25 m. Follow IFC-WB EHS Guidelines for avoiding water pollution.

Site location selection (distance to dwelling, water channels and/or agricultural land)/

CEB

Part of detailed project sighting and survey and design

Wind turbine locations have been selected to comply with this provision

Encroachment into precious ecological areas

Loss of precious ecological values/ damage to precious species

Qualified Ecologist will be engaged by the EPC contractor.

The ecologist will mark out and record the location all endemic and locally EN plants as well as Palmyra and coconut in and adjacent the construction working area. Hard standing area and access roads to be pegged out to minimize loss of these species. If T3 and T36 used, then hard standing design to be given careful attention to see if fewer than 5 endemic Neralu trees can be lost.

At each turbine location, no more than 0.7 ha will be cleared permanently for the activities of construction of wind turbine and the vegetation (herbs, shrubs and trees) in the rest of the area (2.25ha-0.7ha) used for the hard standing area will be allowed to grow back.

The ecologist will record the baseline situation and monitor the continued presence of vegetation, especially the endemics and locally EN plants during the construction.

Floral and faunal habitats loss in coastal area / Flora and Fauna Protection Ordinance.

CEB

Detailed design

EPC contractor has already appointed a qualified Environmental Safeguard officer.

The mitigation measures stated in the EIA are being implemented.

No proper records have been maintained regarding the flora of turbine locations.

15

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

Interference with drainage patterns/water channels

Temporally flooding hazards/loss of ecology in water channels

Siting of Wind turbines at least 5-10 m away from Thonas (water channels) to avoid disturbing habitats in water channels.

Site location Selection

Sri Lanka Land Reclamation and Development Corporation (SLLRDC) recommended measures to avoid adverse effects on the natural drainage system within the area from project construction /

Irrigation Act, 1933. Consultation with local authorities and design engineers SLLRCD recommendation

CEB

Detailed alignment survey and design

This condition has been complied with.

Explosions/Fire Hazards to life Provision of firefighting equipment to be located close to sub-transformers, power generation equipment.

Sub-transformer design compliance with fire prevention and control codes /

Tender document to mention detailed specifications

CEB

Part of detailed layout and design /drawings

The detailed design has been completed to verify this condition.

Wind Farm layout of its facilities

Temporary Jetty impact on marine flora and fauna

Collate daily and monthly fish catch data for 2-year prior for fishermen in the project area and a representative control site.

Survey and undertake a translocation of any trans-locatable marine flora and fauna located within the working area of the jetty to similar habitat away from the working area

Undertaken nightly survey the beach working

Fish Catch Survey Visual Survey of beach for turtle nests Visual Survey of the jetty area to observe any marine flora/fauna /

CEB together with Department of Coastal Conservation

Part of detailed layout and design /drawings

This is not applicable as the jetty will not be constructed.

16

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

area for at least 60-days prior construction (depending on the time of year in relation to nesting season) to identify any turtle nests and if found fence off the nest and buffer zone from construction working area to avoid disturbance

No bright or white lighting to be installed on turbines and the design of associated infrastructure to ensure no light spill onto the beach

None

Healthy and Safety Environment (HSE)

Occupational and community health and safety

Turbines selected to be designed to international good practice standards (IEC 61400) and have means of working at height systems fitted to them.

EPC contractor to ensure all staff have received appropriate health and safety training and are competent for their role before the commencement of work, including working at height, working over water, and lifting operations. EPC contractor to develop a traffic management plan covering the import of materials and staff by road and use of local access roads for construction of the wind farm. Undertake a baseline survey to determine the condition of existing roads which will be used for importation.

No injury or loss of life to construction staff or members of the public (records of near-miss, minor, major and fatal health and safety incidents to be maintained and monitored during the construction phase)

Part of detailed layout and design /drawings

Designers have to confirm that the turbine designs conform to good international practice.

EPC contractor has to provide details of the proposed training module on Health and Safety at work.

Construction

Construction at the wind farm

Adverse impacts to flora/fauna/receptors in the area

EPC contractor to develop detailed site-specific Construction Method Statement based on the outline construction management plan and measures set out in the general EHS Guidelines for construction and demolition and the sector IFC-WB EHS guidelines for Wind Energy.

Project area/

EIA document and all regulatory requirements of Sri Lanka and IFC-WB EHS guidelines

CEB and EPC Contractor

Prepare before the start of construction

EPC contractor has developed a detailed site-specific Construction Method Statement.

Acquisition of plantations and

Loss of agricultural productivity

Avoid bird’s migration/breeding season wherever possible for the project activities.

The land area of agriculture loss

CEB, Contractor through contract

The land plots identified for wind turbines are not agricultural land. Acquisition of plantations

17

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

other lands Ensure existing water channels/ irrigation facilities are maintained in working condition

Protect /preserve topsoil and reinstate after construction completed

Repair /reinstate damaged areas etc. after construction completed

Compensation for loss in agricultural production

Usage of existing Utilities

Implementation of compensation (amount paid, dates, etc.)

Agrarian Service Act. Regular monitoring compliance with regulations

provisions

Throughout the construction period

is not needed.

No loss of agricultural productivity is envisaged.

Wind turbine foundation construction

Dumping of excess soil

Excess soil from the foundations to be disposed of off-site after permission of local authorities. All construction material to be kept within the footprint of the area acquired. Loose construction material to be covered to avoid being carried into adjoining areas by the wind.

The volume of soil to be disposed of (area of site in m2 and estimated volume in m3)

Laws and regulations of respective LAs

CEB, Contractor through contract provisions

Construction period

Construction of foundations has started for Tower 24

It was noted that:

(i) All the construction material have been kept within the footprint of the tower area

(ii) Excess soil has been levelled and compacted within the site

(iii) No soil piles (loose soil) were noted.

Water pollution Storage facilities for fuels, oil, chemicals and cement will be within secured areas on impermeable surfaces, provided with bunds of at least 110% volume with clean up equipment immediately available for use

All vehicles, machinery, and equipment maintenance and re-fuelling will be carried out on impermeable surfaces and in such a way that spilt materials do not seep into the adjacent soil. Fuel storage and refilling areas will be located at least 100 m from sea and water channels and will be protected by temporary drainage bunds of at least 110% volume to contain spills. Construction

Seasonal start and finish of major earthworks (pH, BOD/COD, Suspended solids, other)

Sri Lanka’s National Environment Act and IFC-WB EHS guidelines 2007 (under revision)

Timing of major disturbance activities - prior to starting of construction activities Construction period

The following were noted:

Storage facilities for fuels, oil, chemicals and cement have been provided as suggested.

All vehicles, machinery, and equipment maintenance and re-fuelling are carried out satisfactorily. No oil/fuel spills were noted.

Fuel storage and refilling areas are located well-away from the seacoast.

The contractor has provided garbage collection bins at each turbine construction site as described in the EMP. The garbage management procedure is satisfactory.

18

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

wastewater will not be discharged directly onto the surrounding soil or into the surface water system, all wastewater to be passed through silt traps or temporary sedimentation screens.

Oil-interceptors will be installed, and oil-containing wastewater will be intercepted, collected and transported to the central location for further treatment and disposal.

The contractor will provide sufficient garbage bins at each turbine location and ensure that they are (i) protected from birds and vermin; (ii) emptied regularly (using the nearest licensed solid waste landfill); and (iii) are not left to overflow.

Construction activities involving significant ground disturbance (i.e. foundation land forming) not undertaken during the monsoon season.

Do not undertake any works within 100 m of a water channel during the wet season

Arrangement for stormwater management during the construction period to be made to avoid sediment runoff from the site.

So far only piling work has been undertaken. The contractor has assured that no heavy construction will be carried out during monsoons and no work will be carried out within 100 m of a water bodies during the wet season

Stormwater management measures are in place at construction sites.

Construction schedules

Noise nuisance to neighbouring properties

Construction activities were undertaken during the day and local communities informed of the construction schedule. In the vicinity of Shell Coast Resort (cabanas are now exempt), no piling or other noisy construction works to be undertaken for more than a 6-hour period or at any time on the weekend or public holiday

Timing of construction (noise emissions, [dB (a)]) Daytime construction Only

CEB, Contractor through contract provisions

Construction period

The only activities that are being carried out at the moment are pile foundation construction and access road construction. No significant noise levels were observed due to these activities.

Nuisance to birds from wind turbine construction

Restrict construction work during the known period of migration (Oct-January) by the birds. Construction period to be finalized in keeping with the construction method statement (CMS). Work must be undertaken from 1 hour

Timing of Construction/

Biodiversity

CEB, Contractor

Construction

This will be checked during the construction.

19

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

after sunrise to 1 hour before sunset. Management Plan, Construction Timing - the period of migration of birds

period

Provision of facilities for construction workers

Contamination of receptors (land, water, air)

Construction workforce facilities to include proper sanitation, water supply and waste disposal facilities in accordance with IFC-WB EHS Guidelines. Solid waste and hazardous waste to be disposed of offsite to a suitably licensed landfill. No waste to be disposed of to an unlicensed dumpsite. No water well will be located within minimum 100 m of a toilet facility and vice versa.

Contractor to prepare and implement pollution prevention and emergency response plan in accordance with IFCWB EHS Guidelines.

Amenities for Workforce facilities/

National Solid Waste Management Policy and IFCWB EHS guidelines 2007 (under revision)

CEB, Contractor through contract provisions

Construction period

Only small teams of workers are engaged in piling and road construction work.

Surplus earthwork/soil

Runoff to cause water pollution, solid waste disposal

Any excess inert spoil material will only be used as fill material onsite or offsite after permission from local bodies. The disposal site restored in a manner that prevents erosion and does not block any drainage path. No solid or hazardous waste to be disposed of alongside excess inert spoil.

Location and amount (m3) of fill disposal. Soil disposal locations and volume (m3) /

Appropriate fill disposal and dispersal locations. Pollution Prevention as per International best practices133

CEB, Contractor through contract provisions

Construction period

This was not observed at piling construction sites. However, surface runoff along access road construction was observed to carry heavy loads of sediments.

The contractor was advised not to carry out earth works during rainy days (periods).

Tree cutting/ vegetation harvesting, cut and fill operations

Loss of vegetation and deforestation

Construction workers prohibited from harvesting trees in the project area during their employment. Get approval for cutting female Palmyra trees from Divisional Secretary. During the construction, CEB/EPC contractor to record the exact number of trees/ shrubs removed from the hardstand, access roads and other areas cleared for building and other facilities etc. Replanting/ restoration

Illegal tree/ vegetation harvesting (area in m2, number of incidents reported) Monitoring for all tree/shrubs to be cut by EPC contractor

CEB, Contractor through Contract provisions External monitoring would be done by Forest Department and Dept. of Wildlife Conservation

The sites are already cleared for wind turbine locations, access roads, yards and offices, etc.

Awareness programme regarding the conservation of flora, fauna and habitats is continuing by the contractor for workforce.

The Contractor admitted that this condition has

20

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

programmes to compensate for the loss of trees/ shrubs and the habitat can be enriched134 once the project activities are completed.

Complaints by local people or other evidence of illegal harvesting

Construction period

been complied with.

The uprooting of EN and endemic species of plants and vegetation

To ensure EPC contractor does not remove any locally EN or endemic variety of flora/trees at any hard-standing area. The ecologist will be engaged by EPC contractor to oversee the above. The ecologist will mark out and record the location all endemic and local EN plants in and adjacent the construction working area. EPC Contractor staff will be given guidance on their identification through toolbox talks and notices in site offices and instructed not to clear them. The ecologist will monitor the continued presence of the endemics and EN plants during the construction.

No more than 5 endemic Neralu trees, 9 palmyra trees and 37 coconuts will be removed from the project area.

Hard standing Area

The ecologist will ensure endemic, and EN plants are not removed

EPC contractor through contract provisions

Construction period

Observation of the ecologist will be recorded once such information is available.

This will be checked during the construction phase.

Effect on fauna Prevent workforce from disturbing to the flora, fauna including hunting of fauna and fishing in water channels. No poaching allowed in the birds habitat area (Vankalai sanctuary, Adam’s Bridge National Park, Vedithalativu Nature Reserve.)

Proper awareness programme regarding the conservation of flora, fauna including ground vegetation to all drivers, operators and other workers

Habitat loss /

Fauna and flora protection Act.

CEB/ DWC/ CCD/DoF

Construction period

This will be checked during the construction phase.

Site clearance Vegetation removal Marking of vegetation to be removed prior to clearance, and strict control on clearing activities to ensure minimum clearance. The localized sprinkling of water at areas where vegetation is removed shall be undertaken for the entire duration of construction. Private

Vegetation marking and clearance control (area in m2) /

Felling of trees (Amendment Act. Nº 01 of 2000 and act of

CEB, Contractor through contract provisions

Construction period Re-vegetation cost

Vegetation has been removed in some sites already. The contractor has been instructed to record any tree species prior to clearance and to exercise strict control on clearing activities to ensure minimum clearance.

Activities such as the sprinkling of water in areas

21

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

trees/plantations will be compensated as per GoSL norms.

felling of trees control). Clearance strictly limited to target vegetation

will have limited capital cost as seedlings can be obtained from Horticulture/ Forest Department

where vegetation is removed will be checked during construction.

Soil erosion and surface runoff

Construction in erosion-prone areas should be restricted to the dry season. Outline construction Method Statement shall be the basis for construction practice by the EPC contractor.

Treat clearing and filling areas against flow acceleration and foundation/road construction work should be carefully designed to minimize obstruction or destruction to natural drainage.

All earthwork disturbance areas shall be stabilized within 30 days after earthworks have ceased at the construction site

Soil erosion

Reengineering of drainage channels wit 25 m of the Wind turbine foundation as well as along access roads /

Visual inspection (Turbidity and sedimentation).

CEB, Contractor Through contract Provisions

Construction period

There are no erosion-prone areas. However, earthwork during heavy rains causes erosion of loose soil.

The contractor has been advised not to carry out earth works during rainy days to minimize such erosion of loose soil.

Mechanized construction

Noise, vibration and operator safety, efficient operation, equipment wear and tear

Construction equipment to be well maintained. Check for pollution prevention and oil dripping etc. from vehicles while working in bird habitat and other areas. Adopt pollution prevention measures in accordance with IFC-WB EHS Guidelines.

Use of inherently quiet plant and equipment as far as reasonably practicable and regular maintenance to ensure noise emissions are maintained at design levels. Turning off plant, not in use. Noise sources to be acoustically treated, for example with silencers, acoustic louvres and enclosures. Provision of rubber paddings/noise isolators at equipment/machinery used for construction.

Construction equipment - estimated noise emissions and operating schedules / Technical specifications, safety regulations, Noise control regulations (1994), Pollution Prevention as per International best practices

CEB, Contractor through contract provisions

Construction period

The contractor has been advised to keep the construction equipment well maintained.

The site supervisor has been advised to check for any oil dripping etc. from vehicles/equipment/machinery

Noise emissions are to be monitored continuously by the contractor to be maintained below regulatory levels.

22

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

Construction of roads for accessibility

Increase in airborne dust particles Increased land requirement for temporary accessibility

Existing roads and tracks used for construction and maintenance access to the site wherever possible. New access ways restricted to 8m carriageway width. Access road shall be planned to cause minimal disturbance to the terrain topography.

Existing surface drainage pattern to be retained to the extent possible.

All equipment will be maintained to a high standard to ensure efficient running and fuel-burning. All vehicle emissions will be in compliance with relevant Sri Lankan emission standards.

All vehicles carrying soil, sand, or other fine materials to and from the construction sites will be covered.

Access roads (length and width of new access roads to be constructed) /

Use of established roads wherever possible

CEB, Contractor through contract provisions

Construction period

Most of the sites are accessed using existing roads. However, some sections of the access roads need extensive rehabilitation.

New access roads are being constructed, and other are being rehabilitated. The contractor had been advised to maintain existing surface drainage pattern be retained to the extent possible.

All the vehicles are screened for the Emission Certificates, and it is mandatory for trucks to cover any material during transportation.

Transportation and storage of materials

Nuisance to the general public

Hazardous waste from machinery, generators etc. (lube oil, hydraulic oil, waste oil etc. from cranes etc.)

Transport loading and unloading of construction materials should not cause nuisance to the people by way of noise, vibration and dust.

Avoid storage of construction materials beside the road, around water bodies, residential or public sensitive locations No storage of construction material near waterways and beach area. Construction materials should be stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment-friendly and nuisance free manner. Random stocking of raw material, storage of debris, piling of loose soil etc. to be strictly controlled. Other wastes like wood packaging material, metal, etc. will be sold to scrap dealers. Housekeeping of the area to be maintained by deputing sweepers to remove dirt/debris from the sites on a daily basis in case of any accidental spill the soil to

Soil, water and air quality Every 3 months after commencement of construction /

National Environment Act Laws and regulations of respective LAs National Emission Standards, Hazardous waste laws and CEA water quality standards Weekly

CEB/LAs

Construction period Storage: No additional cost is envisaged. Water quality

monitoring cost – SLR 3,500 per sample Performance

parameters – Suspended Solids (SS), Total dissolved solids (TDS), oil, grease, Biological oxygen demand (BOD), Total coliforms,

The current practice of loading and unloading of construction materials do not cause nuisance to the people and noise, vibration and dust have not posed any inconvenience.

Storage of construction materials has avoided road-sides, water bodies/beach, residential or public sensitive locations

The contractor has given strict instruction to keep the construction materials covered to prevent wind-borne dust, emissions.

Monitoring requirements are discussed later.

23

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

be cut and stored securely for disposal with hazardous waste. Hazardous waste will be stored at a secure location and only be sold to authorized vendors.

Fecal coliforms

Trimming/cutting of trees

Loss of vegetation and deforestation

Felled trees and other cleared or pruned vegetation to be disposed of as authorized by the statutory bodies. Forest trees, if any, would be planted on the basis of 1:1 replacement. Any trees that die within 5 years are to be replaced.

Species-specific tree retention as approved by statutory authorities (average and maximum tree height at maturity, in meters) Disposal of cleared vegetation as approved by the statutory authorities (area cleared in m2) /

Felling of trees (Amendment Act. No 01, of 2000 and Act of felling of trees control) Presence of target species following vegetation clearance.

CEB, Contractor through contract provisions

Construction period

Vegetation has been already removed in some sites. The contractor has been instructed to record any tree species prior to clearance and to exercise strict control on clearing activities to ensure minimum clearance.

The contractor will be advised to submit a tree planting program within the wind farm areas and elsewhere as a compensatory reforestation program and also as a CSR project

Health and safety Injury and sickness of workers and members of the public

EPC contractor to undertake risk assessment (named person assigned for management of all medium and above risks) and develop detailed site-specific Occupational Health and Safety Plan (including emergency response plan) based on measures set out in the IFC-WB general EHS Guidelines for occupational and community health and safety and the sector IFC-WB EHS guidelines for Wind Energy including procedures for eliminating and reducing working at height, working over water, and lifting operations and use of appropriate working methods and equipment where elimination is not possible. Construction site to have a well-stocked first aid box at each

Contract clauses (number of incidents and total lost-work days caused by injuries and sickness)

Health and safety regulations and IFC-WB EHS guidelines 2007 (under revision)

CEB (Contractor through contract provisions)

Construction period

The EPC contractor has prepared Occupational Health and Safety Plans as part of policies and procedures followed by Vestas.

The sub-contractor (Access) who carried out piling work is apparently following their safety procedures, which are deemed satisfactory.

The rest of the safety procedures will be checked once the erection of each wind turbine is commenced.

Construction staff is provided with clean drinking water (bottled water) which is supplied by reputed companies and the water meets Sri

24

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

turbine location and be staffed by qualified first-aid trained personnel Construction site around each turbine to be securely fenced to prevent public access with 24-hour security when deep excavations are left open overnight Establish exclusion zone for all members of the public and workforce during working at height and lifting operations No construction staff to be exposed to a noise level greater than 85 dB(A) for more than 8 hours per day without hearing protection. No unprotected ear should be exposed to a peak sound pressure level (instantaneous) of more than 140 dB(C). Hearing protective devices provided should be capable of reducing sound levels at the ear to at least 85 dB(A).

Construction staff to be provided with a source of clean drinking water (groundwater not suitable due to saline intrusion) that is tested weekly to confirm meets Sri Lankan Drinking Water standards. Sufficient quantity of drinking water available to construction staff and toilet/sanitation facilities provided at the construction site in accordance with EHS general guidelines on occupational H&S Contract provisions specifying minimum requirements for construction of day-time camps including sanitation and welfare facilities in accordance with IFC-WB EHS Guidelines Contractor to prepare and implement a health and safety plan in accordance with IFC-WB EHS Guidelines.

Arrangement for fire control measures. Display of phone numbers of the city/local fire services, etc. at site. Ensure good housekeeping at the construction site to avoid slips and falls. Contractor to arrange for health and safety awareness programmes.

Lankan Drinking Water standards.

Sufficient amounts of water is available for washing and sanitation/toilets.

Arrangement for fire control measures are satisfactory. Phone numbers of the city/local fire services, etc. are displayed at site.

Housekeeping at the construction sites is satisfactory.

The contractor is conducting regular health and safety awareness programmes.

25

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope/Standard

Responsibility of Implementation

& schedule

Observations and Remarks

Working at heights

Operation of heavy Machinery

Accidents leading to injuries fatalities

Occupational health hazards

All personal protective equipment like gloves, helmets, earmuffs, safety belts, etc.) for construction workers through the contractors.

Ensure effective work permit system for hot work, electrical work, working at height, working in confined space etc. Lifting /Dropping/lowering of construction material or tool to be restricted and undertaken only under strict supervision, if required.

Contract clauses (number of incidents and total lost-work days caused by injuries and sickness). Operation of Cranes to follow a Crane Safety Plan

Health and safety regulations and IFC-WB EHS guidelines 2007 (under revision)

CEB (Contractor through contract provisions)

Throughout the construction phase

Still the piling construction is in progress.

This will be checked once the construction has commenced

Nuisance to nearby properties

Losses to neighbouring land uses/ values

Contract clauses specifying careful construction practices in accordance with IFC-WB EHS Guidelines. Incorporating good construction management, design engineering practices.

Productive land will be reinstated following completion of construction

Contract clauses Design basis and layout Reinstatement of land status (area affected, m2) Implementation of Tree/Crop compensation (amount paid)

Public Nuisance Ordinance No.: 15 of 1862. IFC-WB EHS guidelines 2007

CEB (Contractor through contract provisions) EPC Contractor

Construction period Consultation with affected parties immediately after completion of construction

This will be checked once the construction has commenced

There is no apparent impact on productive land.

Road infrastructure

The possible crossing of ecological and ornithologically habitat. Access to local population to roads infrastructure

Ensure wind turbines and access roads are constructed so as to avoid any critical habitats

Villages will get access to all approach roads to the coast/shore built for accessing the project facilities.

Site Plan to minimize such occurrence and facilitate community convenience. /

IFC’s GN6 and

incorporation of good construction management, design engineering practices

CEB and EPC Contractor

Construction period

The wind turbine locations have been selected so as not to disturb any critical habitats.

The access roads and village roads used by inhabitants are not obstructed.

26

2.6.2 Construction of the Transmission Line and the Grid Sub-Stations

Table 2.7: Monitoring of the implementation of Environmental mitigation measures – Transmission Line and the Grid Sub-Stations

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

Pre-construction

Temporary use of lands

Impact on the existing environment

Selection of lands adhering to local laws and regulations and in close consultation with LAs

Construction facilities should be placed at least 100 m away from water bodies, natural flow paths, important ecological habitats and residential areas. No temporary land use in Vankalai Sanctuary.

Water and air quality

Air Quality Standards and CEA water quality standards

CEB

Contractor

Detailed design

The following reports have been submitted:

- Air quality (Annex 3.5)

- Noise (Anne3.x 3.6)

- Soil (Annex 7)

Water quality reports have not been received.

Substation location and design

Noise generation Exposure to noise, Nuisance to neighboring properties

Disturbance to the adjacent lands and the people due to cut and fill operations

Substation designed to ensure noise will not be a nuisance (i.e. less than 55dBA LAeq daytime and less than 45dBA LAeq nighttime at nearest receptor).

Maintain adequate clearance, construction of retaining structures, minimize cut and fill operations adjoining to the dwellings

Expected noise emissions based on substation design, noise levels

Proximity to houses and other structures

Noise control regulations in 1994 Noise levels to be specified in tender documents

Technical specification

CEB

Detailed Design

Summary of existing noise levels are reported in the quarterly environmental monitoring (Annex 3.6)

Location of transmission towers and transmission line alignment and design

Line traversing across environmentally sensitive areas with possible impacts to biodiversity and excessive clearance of vegetation

The setback of dwellings to transmission line route designed in accordance with permitted level of power frequency and the regulation of supervision at sites.

Tower location and line alignment selection with respect to nearest dwellings

Setback distances to nearest houses -

CEB

Part of tower sighting survey and detailed alignment survey and design

The transmission line has been routed through areas with low-grown vegetation and agriculture, such as paddy and low grown vegetables

A detailed design, including tower type, location, profile

27

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

Excessive requirements for clearance of way-leaves and land-use restrictions in areas of high population density

Exposure to safety-related risks

already been submitted.

Trees have been removed, and compensation has been paid for the identified owners.

Impact on water bodies (Vankalai sanctuary wetland)/land/ residences

Consideration of tower location where they could be located to avoid avian breeding areas, water bodies or agricultural land as much as possible. Follow EHS Guidelines on avoiding water pollution.

Careful site selection to avoid existing avian/marine settlements and negative impacts to the sanctuary area.

Increase the height of towers, adopt measures to reduce possible collision with birds during flight.

EPC contractor to implement mitigation measures according to Biodiversity Management Plan and Construction Method statement outlining construction precautions in the Vankalai Sanctuary area.

Site location, line alignment selection (distance to dwelling, water and/or agricultural land)

Improve tower design and measures

Consultation with local authorities Biodiversity Management Plan, Dept of Wildlife Conservation

CEB

Part of detailed project sighting and survey and design

This condition has been complied with.

Equipment specifications and design parameters

Release of chemicals and harmful gases in receptors (air,

Ensure equipment design must be sound to avoid emissions for oil, gases etc.

Compliance with setback distances (as-built” diagrams)

Setback distances to nearest houses

CEB

Detailed design

No significant amounts of emissions (release of chemicals and harmful gases) are envisaged.

28

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

water, land) Poly Chlorinated Biphenyls (PCBs) has not been used in substation transformers or any other equipment. Exclusion of PCBs in transformers stated in tender specifications.

Encroachment into precious ecological areas

Loss of precious ecological values/ damage to precious species

Minimize the need for tower base disturbance in sanctuary wherever possible

Floral and faunal habitats loss in the sanctuary area

Flora and fauna protection act. Biodiversity Management Plan

CEB

Detailed design

This condition has been complied with mitigation actions.

Interference with drainage patterns/water channels

Temporally flooding hazards/loss of agricultural production

Appropriate siting of towers (use longer spans) to avoid putting towers in the water channel to avoid disturbing aquatic habitats in sanctuary area.

Site location and line alignment selection

Irrigation Act of 1933. Consultation with local authorities and design engineers

CEB

Detailed alignment survey and design

The contractor has selected tower locations in consultation with the CEB and other authorities. No loss of agricultural land and disturbances to aquatic habitats have been observed.

Explosions/Fire Hazards to life Design of substations to include modern fire control systems/firewalls.

Provision of firefighting equipment to be located close to transformers, power generation equipment.

Substation design compliance with fire prevention and control codes

Tender document to mention detailed specifications

CEB

Part of detailed substation layout and design /drawings

Provision of firefighting equipment has been planned. This has to be verified prior to commissioning.

Construction

Removal or disturbance to other public utilities

Public inconvenience

Advance notice to the public about the time and the duration of the utility disruption.

Use of well trained and experienced machinery operators to reduce accidental damage to the public utilities and specifically any natural habitats

Disruption of other commercial and public activities / Public complaints

Technical specification

CEB/ PRDA / NWSDB/SLT

Throughout the construction period

No public utilities have been disturbed as yet.

The contractor has employed well trained and experienced machinery operators.

Natural habitats in Vankalai Sanctuary have not been

29

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

in Vankalai Sanctuary. Restore the utilities immediately to overcome public inconvenient

permanently damaged.

Temporary outage of the electricity

Loss of power supply to the local community when distribution lines crossing the new transmission line are switched off

Advance notice to the public about the time and the duration of the utility disruption

Restore the utilities immediately to overcome public inconvenience.

Houses and commercial premises of power disruption

Regular monitoring during the period of strengthening the conductors

Contractor CEB

Throughout the construction period

Temporary outages of electricity should be monitored, especially during stringing.

Acquisition of paddy fields and other lands

Loss of agricultural productivity

Avoid farming and bird’s migration/breeding season wherever possible for the project activities.

Ensure existing irrigation facilities are maintained in working condition

Protect /preserve topsoil and reinstate after construction completed Repair /reinstate damaged areas etc. after construction completed

Compensation for temporary loss in agricultural production

The land area of agriculture loss

Usage of existing Utilities

Status of facilities (earthwork in m3)

Implementation of crop compensation (amount paid, dates, etc.)

Agrarian Service Act.

Regular monitoring compliance

with regulations

CEB, Contractor through contract provisions

Throughout the construction period

No acquisition of lands required for tower foundation or line; Construction of transmission towers is in progress, and some towers have been completed. The contractor, in consultation with the CEB, has

avoided/minimized the cultivation seasons, and bird migratory seasons to the extent as possible.

The contractor has been able to satisfactorily reinstate the damaged construction areas to the satisfaction of all the parties concerned.

Payment of compensation for crop damages of paddy area is in progress.

Equipment layout and installation

Noise and vibrations

Selection of construction techniques and machinery to minimize ground disturbance

Construction techniques and machinery/

Minimal ground disturbance

CEB, Contractor through contract provisions

Construction period

Disturbances have been kept to a minimum. No significant noise and vibration impacts recorded and no complaints.

30

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

Substation construction

Loss of soil Fill for the substation foundations obtained by creating or improving a local drain system.

Borrow area sighting (area of the site in m2 and estimated volume in m3)

Laws and regulations of respective LAs

CEB, Contractor through contract provisions

Construction period

Filling of the site is complete. Road-side drains adjoining the site area and the access road have been maintained properly.

No local drainage problems have been observed so far.

Water pollution Construction activities involving significant ground disturbance (i.e. substation land forming) not undertaken during the monsoon season. No work in lagoon areas during high tide periods.

Seasonal start and finish of major earthworks (pH, BOD/COD, Suspended solids, other)

Sri Lanka’s National Environment Act and IFC’s EHS guidelines 2007 (under revision)

Timing of major disturbance activities - prior to starting of construction activities Construction period

Much of the earthwork and filling activities are completed now, and these works have been carried out during the dry season.

According to the contractor, no earthworks are planned during the forthcoming rainy season.

No surface water bodies found within or around the substation area.

Construction schedules

Noise nuisance to neighboring properties

Construction activities only undertaken during the day and local communities informed of the construction schedule.

Timing of construction (noise emissions, [dB (a)])

Daytime construction only

CEB, Contractor through contract provisions

Construction period

There are no dwelling units located close to the grid station site.

Tower construction near dwelling units (e.g., close to the Mannar Railway Station) has now been completed

No significant noise and vibration impacts recorded and no complaints.

Nuisance to birds if the line construction crosses their migratory path

Restrict construction work during the known period of

migration/breeding period by the birds. Construction period in the sanctuary to be finalized in

Timing of Construction

Biodiversity Management Plan, Construction Timing - period of migration of birds

CEB, Contractor

Construction period

All construction activities are conducted during off migratory season; February 2019 to September 2019.

31

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

keeping with the CMS. Work inside the sanctuary must be undertaken from 1 hour after sunrise to 1 hour before sunset.

Provision of facilities for construction workers

Contamination of receptors (land, water, air)

Construction workforce facilities to include proper sanitation, water supply and waste disposal facilities at substation site in accordance with EHS Guidelines. No facilities to be set up within the Sanctuary. Solid waste and hazardous waste to be disposed of offsite to a suitably licensed landfill. No waste to be disposed of to an unlicensed dumpsite. Contractor to prepare and implement pollution prevention and emergency response plan in accordance with EHS Guidelines.

Amenities for Workforce facilities/

National Solid Waste Management Policy and IFC’s EHS guidelines 2007 (under revision)

CEB, Contractor through contract provisions

Construction period

Construction workforce has been provided with proper facilities to include proper sanitation, water supply and waste disposal facilities (for both transmission tower workers and at substation site) in accordance with EHS Guidelines.

No labor camps have been set up within the Sanctuary.

Solid waste and hazardous waste is handed over to the Pradeshiya Sabha.

Wood/ Vegetation harvesting, cut and fill operations

Loss of vegetation and deforestation

Effect on fauna

Construction workers prohibited from harvesting wood in the project area

Prevent workforce from disturbing to the flora, fauna including hunting of fauna and fishing in water bodies. No poaching allowed in Sanctuary or bird habitat area.

Proper awareness programme regarding the conservation of flora, fauna including ground vegetation to all drivers, operators and other workers

Illegal wood/ Vegetation harvesting (area in m2, number of incidents reported)

Habitat loss

Complaints by local people or other evidence of illegal harvesting

Fauna and flora protection Act.

CEB, Contractor through contract provisions

CEB/ DWC/ DoF

Construction period

Clearing for the transmission towers and line is done with minimum impact to the vegetation. Existing roads are mainly used for the transportation. Storage of material without clearing of vegetation.

Awareness program regarding the conservation of flora, fauna and habitats is being conducted by the contractor for workforce.

Strict instructions have been given to construction workers prohibiting from harvesting

32

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

wood in the project area, disturbing to the flora, fauna including hunting and fishing.

Poaching in the sanctuary or bird habitat areas has been strictly prohibited.

Site clearance Vegetation Marking of vegetation to be removed prior to clearance, and strict control on clearing activities to ensure minimum clearance. Minimum vegetation clearance to be done in the sanctuary area.

No tree felling in Sanctuary required. Private trees/plantations will be compensated as per GoSL norms.

Vegetation marking and clearance control (area in m2)

Felling of trees (Amendment Act. Nº 01 of 2000 and act of felling of trees control). Clearance strictly limited to target vegetation

CEB, Contractor through contract provisions

Construction period

Vegetation has been already removed in some sites. The contractor has been instructed to record any tree species prior to clearance and to exercise strict control on clearing activities to ensure minimum clearance.

The contractor will be advised to submit a tree planting program within the grid station area and elsewhere as compensatory reforestation, and also as a CSR project

Soil erosion and surface runoff

Construction in erosion-prone mudflats, lagoon areas should be restricted to the dry season. Outline construction Method Statement shall be the basis for construction practice in Sanctuary area. Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimize obstruction or destruction to natural drainage

Soil erosion

.

Visual inspection (Turbidity and sedimentation)

CEB, Contractor Through contract Provisions

Construction period

The contractor has been instructed to clear any construction debris, spoil, excavated soil from the site areas prior to commencement of the rainy season.

Mechanized construction

Noise, vibration and operator safety, efficient operation, equipment wear

Construction equipment to be well maintained.

Check for pollution prevention and oil dripping etc. from

Operating schedules

Noise control regulations (1994), Pollution Prevention as per International

CEB, Contractor through contract provisions

The contractor is maintaining records of the status of construction equipment and machinery.

33

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

and tear vehicles while working in bird habitat and other areas. Adopt pollution prevention measures in accordance with EHS Guidelines

Proper maintenance and turning off plant, not in use.

best practices43 Construction period No oil dripping has been observed during site visits

Construction of roads for accessibility

Increase in airborne dust particles

Increased land requirement for temporary accessibility

Existing roads and tracks used for construction and maintenance access to the site wherever possible.

New access ways restricted to a single carriageway width within the RoW. Avoid construction of permanent access routes in sanctuary area by use of mats etc.

Access roads, routes (length and width of new access roads to be constructed)

Use of established roads wherever possible

Access restricted to single carriageway width within RoW

CEB, Contractor through contract provisions

Construction period

The contractor has been using existing roads for accessing tower locations. Some of the tower locations have been accessed, and material transportation has been done with the use of a railway carriage.

Increased air-borne dust was not observed at transmission tower locations during the site visit. Even though air-borne dust occurs at the grid sub-station site frequent water spray along the road and construction site is observed.

Transportation and storage of materials

Nuisance to the general public

Transport loading and unloading of construction materials should not cause nuisance to the people by way of noise, vibration and dust.

Avoid storage of construction materials beside the road, around water bodies, residential or public sensitive locations

No storage of construction material in the sanctuary area.

Construction materials should be

Water and air quality

National Environment Act Laws and regulations of respective LAs National Emission Standards and CEA water quality standards

CEB/LAs

Construction period

There have been no complains related to the public nuisance caused by noise, vibration and dust due to transport loading and unloading of construction materials

The contractor has avoided storage of construction materials beside the road, around water bodies, residential or public sensitive locations such as the

34

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

stored in covered areas to ensure protection from dust, emissions and such materials should be bundled in environment-friendly and nuisance free manner.

sanctuary area.

However, the contractor has failed to cover construction material at the grid substation site. Airborne dust emissions were observed during the site visit.

Trimming/ cutting of trees within RoW

Fire hazards

Loss of vegetation and deforestation

Trees allowed growing up to a height within the RoW by maintaining adequate clearance between the top of the tree and the conductor as per the regulations.

Trees that can survive pruning to comply should be pruned instead of cleared.

Felled trees and other cleared or pruned vegetation to be disposed of as authorized by the statutory bodies. Forest trees, if any, would be planted on the basis of 1:1 replacement. Any trees that die within 5 years are to be replaced.

Species-specific tree retention as approved by statutory authorities (average and maximum tree height at maturity, in meters)

Disposal of cleared vegetation as approved by the statutory authorities (area cleared in m2)

Felling of trees (Amendment Act. No 01, of 2000 and act of felling of trees control)

Presence of target species in RoW following vegetation clearance.

CEB, Contractor through contract provisions

Construction period

Selective tree cutting and trimming were adopted.

No trees were cut or trimmed within Vankalai sanctuary.

Tower location have been selected to minimize the tree cutting.

Health and safety Injury and sickness of workers and members of the public

Contract provisions specifying minimum requirements for day-time construction camps including sanitation and welfare facilities in accordance with EHS Guidelines

Contractor to prepare and implement a health and safety plan in accordance with EHS Guidelines.

Contractor to arrange for health

Contract clauses (number of incidents and total lost-work days caused by injuries and sickness)

Health and safety regulations and IFC’s EHS guidelines 2007 (under revision)

CEB (Contractor through contract provisions)

Construction period

Health and safety procedures are well-established. Health and Safety plans have been prepared and implemented by both the contractors: grid sub-station and the transmission tower.

H&S officers have been mobilized by both the contractors.

35

Project Activity Potential Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of Implementation &

schedule

Observations and Remarks

and safety awareness programmes.

Nuisance to nearby properties

Losses to neighboring land uses/ values

Contract clauses specifying careful construction practices in accordance with EHS Guidelines.

As much as possible, existing access ways will be used.

Productive land will be reinstated following completion of construction

Compensation will be paid for loss of production if any.

Contract clauses Design basis and layout Reinstatement of land status (area affected, m2) Implementation of Tree/Crop compensation (amount paid)

Public Nuisance Ordinance No.: 15 of 1862. And IFC’s EHS guidelines 2007 (under revision). Incorporating good construction management, design engineering practices

CEB (Contractor through contract provisions)

Construction Period

Consultation with affected parties immediately after completion of construction and after the first harvest

This condition has been complied with.

Avian Collision The possible collision of migrant birds with transmission line

Install Swan-Flight Divertor or Aerial Marker Spheres at the stated separations on the length of the transmission line that crosses through Vankalai sanctuary and Mannar island.

Installations on transmission lines

on Birdlife International (2012) and APLIC (2012) guidance

CEB and EPC Contractor

Construction period

Construction work of the transmission line is too early to consider the proposed activities

Rail and road infrastructure

The possible crossing of ecological and ornithologically habitat

Ensure route avoids such habitats outside the sanctuary area

Route alignment to minimize such occurrence

IFC’s GN6 and incorporation of good construction management, design engineering practices

CEB and EPC Contractor

Construction period

This condition has been complied with.

36

2.7 Implementation of the Biodiversity Management Plan

The BMP falls under the Environment Management Plan (EMP) and is part of the package of activities designed to meet the requirements of ADB’s Safeguards Policy Statement (SPS) 2009 which sets out policy principles and outlines the delivery process for ADB’s safeguard policy in relation to environmental safeguards. The main objective of the BMP is reduction of impacts to Vankalai Sanctuary from the transmission line and Adam’s Bridge Marine National Park from wind park. The BMP adopts a ‘whole environment’ approach to safeguard existing environment of wind park and Vankalai Sanctuary from construction of transmission line, maintain its biodiversity values and provide for its future management, as well as promoting actions to safeguard other critical habitats on Mannar Island and environs.

The request of approval for the implementation of BMP of Mannar–Nadukuda 220 kV transmission line project submitted by the CEB to the DWC and approval is given on 11th March 2019, under several concerns and recommendations.

The request of approval for the implementation of BMP of 100 MW Wind Park project submitted by the CEB to the DWC and approval is given on 20th August 2019, under several concerns and recommendations.

37

Table 2.8: Mitigating potential impacts to Marine biology (Wind Power Generation Project)

Project Phase

Feature Mitigation Methods Benefit of mitigation Compliance with the requirements in the field level

Construction Phase

Timing Constructing during dry period to minimize impacts to wetland habitat and erosion.

Reduce turbidity due to loosen soil from water runoff (if any).

The ongoing construction schedule is followed by the Contractor as agreed with the Client/DWC and the Department of Coastal Conservation. Construction activities within the wind park area restricted to the dry season.

Pier Construction Equipment

Reduce excessive impact for drilling in the Pier foundation to reduce soil vibration and rutting in sensitive soils and natural areas.

• Booms, which are floating barriers to oil.

• Sorbents, which are big sponges used to absorb oil.

• Skimmers, which are boats that skim (scoop) spilled oil from the water surface.

Not applicable due to omission of pier construction

Erosion Control Installing and maintaining proper erosion controls during construction to minimize run-off of topsoil and disturbances to natural areas.

If some hatchery is found, the EPC Contractor will ensure the approach to the area is sealed off.

Construction activities in erosion-prone areas are restricted to the dry season. However, actions taken to control erosion in construction sites of turbine footings.

Some issues not applicable due to omission of pier construction

Barge Operations

Oil Spillage from Barge engines, lubes from gearboxes of cranes used for unloading etc.

Increase in invasive species in the water channels will damage the marine and avifauna sensitive ecosystem in the area.

Not applicable due to omission of pier construction

38

Habitats Hire services of Ecologist to ensure there are not nesting of turtles in the construction area.

To restore any natural habitat to original condition for avifauna and marine species

Periodic surveys have been done by the Client and the Contractor to identified nesting areas of the turtles. Service from the marine ecologist should be carried out for the project.

Table 2.9: Monitoring mitigating of potential impacts to Marine biology (Transmission line (Vankalalai sanctuary)

Project Phase

Feature Mitigation Methods Benefit of mitigation Compliance with the requirements in the field level

Construction Phase

Timing Constructing during dry period to minimize impacts to wetland habitat and erosion.

Reduction in disturbance to critical habitats

The ongoing construction schedule is followed by the Contractor as agreed with the Client/DWC and the Department of Coastal Conservation. Construction activities within the Sanctuary area and other marine habitats restricted to the dry season as mentioned in the CMS. No excavation and foundation work during the rainy season in field level.

Specific Construction Equipment

Using low pressure wide- track vehicles and matting to reduce soil compaction and rutting in sensitive soils and natural areas.

Reduce damage to seagrass meadows and soil

All machinery and equipment use within the sanctuary and other sensitive locations with the view to mitigate the anticipated impacts.

Erosion Control Installing and maintaining proper erosion controls during construction to minimize run-off of topsoil and disturbances to natural areas.

Reduce turbidity due to loosen soil from water runoff (if any).

Actions taken to control erosion in construction sites depending on ground and the severity of the erosion.

39

3.0 Implementation of Monitoring Plans

3.1 Implementation of the Environmental Monitoring Plan

3.1.1 Wind Power Generation Project

Table 3.1: Environmental Parameters and Periodicity for Environmental Monitoring Plan

Environmental component

Project stage Parameters to be monitored Location Frequency Comments/Remarks

1. Air Quality Preconstruction stage (The project after assigning to the contractor)

CO, PM10, PM2.5, SPM Inside and outside (0.5 km) of the proposed wind farm

A single time Annex 1: Air Quality (Baseline)

Construction Stage

CO, Pb, PM10, TSPM Inside and outside (0.5 km) of the proposed wind farm

Daily visual inspections, overall monthly monitoring

Will be complied with during construction

Format for monthly monitoring has been given to the contractor.

2. Surface Water Quality

Preconstruction stage (The project after assigning to the contractor)

EC, TSS (turbidity & suspended sediment), DO, BOD, COD, pH Oil and grease, E Coli (faecal coliforms), hydrocarbon

All water channels within 100 m of the working area

A single time Annex 3: Water quality

Construction Stage

EC, TSS (turbidity & suspended sediment), DO, BOD, COD, pH, Oil and grease, E Coli (faecal Coliforms), hydrocarbon

One each from water channels inside the wind farm.

1 time/3 months This is needed during construction.

The contractor agreed to carry out water quality testing towards the end of the year.

3. Ground Water Quality

Preconstruction stage (The project after assigning to the contractor)

EC, TSS (turbidity & suspended sediment), DO, BOD, COD, pH Oil and grease, E Coli (faecal Coliforms), , hydrocarbon

All wells within 100m of the working area

A single time Will be complied with during construction

Construction EC, TSS (turbidity & suspended sediment), DO,

One from nearest well around the wind farm

1 time/ 3 months This is needed during construction

40

Stage BOD, COD, pH Oil and grease, E Coli (faecal Coliforms), hydrocarbon

and one from well near coast

The contractor agreed to carry out water quality testing towards the end of the year.

4. Noise/ Vibration

Preconstruction stage (The project after assigning to the contractor)

Noise level (dB level) Inside park and at the nearest receptor of the wind farm

The single time during NE and one single time during SW monsoon

Annex 2: Noise and vibration (Baseline)

Construction Stage

Noise level (dB level) Inside and outside (0.5 km) of the proposed wind farm

Every month for construction noise Weekly during Piling for temporary pier

This is needed during construction

Format for weekly monitoring has been given to the contractor.

5. Soil Preconstruction stage (The project after assigning to the contractor)

pH, Sulfate (SO3), Chloride, ORP, Salinity, Resistively, Organic Matter, Moisture Content

Inside and outside (just close to the proposed site, 2 locations) of the proposed wind farm

A single time Annex 4: Soil investigation report

Construction Stage

pH, Sulfate (SO3), Chloride, ORP, Salinity, Resistively, Organic Matter, Moisture Content

Inside and outside (just close to the proposed site, 2 locations) of the proposed wind farm

1 time/ 3 months This is needed during construction

7. Bird and bat collision’s

Preconstruction stage (The project after assigning to the contractor)

Bird and bat monitoring survey Near wind farm boundary as per Collision Risk Assessment Report (adopt the same methodology for bats and birds)

Once Preconstruction survey has been completed up to February 2019

8. EMI Preconstruction stage (The project after assigning to the contractor)

Electric Field (kV/m), Magnetic

Field (μT) and Antenna Field

Electric strength dBμV/m

TV/radio signal at the property on the boundary in line of sight of wind farm

Once Not Applicable at this stage.

9. Fish catch Preconstruction, construction,

Collate daily (for fish catch data (amount of catch, no fishers, no of boats, the value of catch etc.)) and monthly fish catch data for 2-year prior

Madels in front of the wind farm

Daily data The contractor agreed to carry the survey during next season.

41

for fishermen in the project area and a representative control site and continue through construction and 3 years of operation

10. Health and Safety

Construction, operation

Monitoring of accidents to workers and community in construction and operation

Wind turbine locations, access roads, staff quarters

Weekly The H&S Plans are available. Risk assessment has been done; Monthly field visits, HAS committee has been established;

Note:

GRM has been established. Awareness to be conducted in the near future for GRC. The GN has agreed to make the communities and the villagers aware of the project and project-related activities.

No complains have been received by the GRC so far.

42

3.1.2 Construction of the Transmission Line and the Grid Sub-Stations

Table 3.2: Environmental Parameters and Periodicity for Environmental Monitoring Plan

Environmental component

Project stage Parameters to be monitored

Location Frequency Remarks/Comments

1. Air Quality Preconstruction stage (The project after assigning to the contractor)

CO, Pb, PM10, TSPM

Inside and outside (0.5 km) of the proposed substation

A single time Reports yet to be received.

Construction Stage

CO, Pb, PM10, TSPM

Inside and outside (0.5 km) of the proposed substation

1 time/ 3 months Air Quality measurement report received for the period from July 01,2019 to September 30, 2019, For Grid Substation (GSS);

(Measured parameters are CO, PM10, PM2.5, Pb); TSPM has not been measured.

According to the report, data was measured on 18th & 19th Sep 2019, but the results table in the same report depicts CO was measured on 10/04/2019 and analyzed on 10/04/2019 whereas PM 10, PM 2.S, Pb were measured on 09-10/04/2019 and analyzed on

12/04/2019. Therefore, these dates are contradicting.

2. Water Quality

Preconstruction stage (The project after assigning to the contractor)

EC, TSS (turbidity & suspended sediment), DO, BOD, COD, pH, Oil and grease, Pb, E Coli (faecal Coliforms), , hydrocarbon

One from nearest well and one from surface water source around the substation

A single time Reports yet to be received.

Construction Stage

EC, TSS (turbidity & suspended

One from nearest well and one from

1 time/ 3 months Water quality reports have not been received for this quarter.

43

sediment), DO, BOD, COD, pH, Oil and grease, Pb, E Coli (fecal Coliforms), , hydrocarbon

surface water source around the substation

3. Noise/ Vibration

Preconstruction stage (The project after assigning to the contractor)

Noise level (dB level)

Inside and outside (0.5 km) of the proposed substation

A single time Reports yet to be received.

Construction Stage

Noise level (dB level)

Inside and outside (0.5 km) of the proposed substation

1 time/ 3 months Noise report has been received. Noise measurement was taken on 19th Sep 2019 at four locations identified by the client.

(Continuous time-integrated noise level was taken at 15 sec time intervals for 15 min every hour and then averaged for 24hours)

Vibration levels have not been measured.

4. Soil Preconstruction stage (The project after assigning to the contractor)

pH, Sulfate (SO3), Chloride, ORP, Salinity, Resistively, Organic Matter, Moisture Content155

Inside and outside (just close to the proposed site, 2 locations) of the proposed substation

A single time The sample for Soil testing has been collected on 10thApril at Grid Sub Station site.

Location 1: Inside GSS Location 2: Outside GSS The sample was collected on 10/04/2019 but tested on 02/10/2019 according to the report.

Construction Stage

PH, Sulfate (SO3), Chloride, ORP, Salinity, Resistively, Organic Matter, Moisture Content

Inside and outside (just close to the proposed site, 2 locations) of the proposed substation

1 time/ 3 months Reports yet to be received.

44

3.2 Implementation of the Biodiversity Monitoring Plan (BMP)

3.2.1 Wind Power Generation Project

Table 3.3: Monitoring of implementation of Biodiversity Monitoring Plan (BMP) for Wind Farm

Project

activity

Potential

impact

Locations

Time Responsibility of

Implementation

Parameters Observations and Remarks

Construction

Bird monitoring surveys

Impact on birds

Within 100m of turbine locations

Monthly during the construction stage

Consultant, Contractor

Block counts by sector CEB is in the process of procuring the services to initiate this study. Still not started

Vantage point count

Broad-scale flight counts

Fine-scale flight counts

monitoring

Bird collision monitoring

Impact on bird collision

The whole area of wind park

Monthly during the construction stage

Consultant, Contractor

Carcasses searching

Land clearing completed by the contractor and construction of turbine footings just started. Therefore, it is too early to initiate this study as the construction work at the wind farm is still at an early stage.

Radar monitoring Impact on bird activity

Impact on bird activity

The whole area of wind park

Daily and seasonal

Consultant, Contractor

Radar and field observations Field inspection for the installation of radar was carried out by the experts with the help of the engineers of the CEB and currently in the design stage.

45

The radar is still not installed, and therefore this study has been deferred until the radar is installed and properly calibrated by the experts from the company that will be supplying the radar.

Monitoring of surface and groundwater

impact on surface and groundwater

All thonas within the wind park, groundwater from well nearest to wind park and from one near to cost

Quarterly during the construction period

Consultant, Contractor

Water quality parameters; DO, BOD/, COD, PH, turbidity, TSS, oil content, E. coli

Ground and surface water quality monitoring survey has been conducted by the Contractor during this quarter including 13 surface water bodies and 5 water wells.

Included as per the contractors’ response.

Report yet to be received.

Monitoring of aquatic fauna

Impact on aquatic fauna

Survey of all 9 thonas within the wind park

Quarterly during the construction period

Consultant, Contractor

Fish and invertebrate surveys Monitoring of aquatic fauna fish and invertebrate survey has not been started.

46

3.2.2 Construction of the Transmission Line

Table 3.4: Monitoring of implementation of Biodiversity Monitoring Plan (BMP) for Transmission line (Vankalalai sanctuary)

Project activity Potential impact Locations Time Responsibility of Implementation

Parameters Observations and Remarks

Pre-Construction

Pre-construction bird monitoring surveys

Impact on birds

Throughout the Vankalai sanctuary

Up to January 2019

Consultant, Contractor

Block counts by sector Survey has been conducted throughout the Vankalai Sanctuary from March 2018 to March 2019. This survey included block counts throughout the Vankalai Sanctuary and along the area identified for installation of wind turbines (twice a month), vantage point (VP) surveys including four VPs to cover the area that will be used for establishment of wind turbines and three VPs to cover the section of the transmission line that traverses through the Vankalai Sanctuary using broad-scale flight counts and fine-scale flight mapping. The survey was completed, and the data were sent to Dr Steven Percival to carry out the Collision modelling and the report was to be submitted to the ADB directly by Dr Percival.

Vantage point count

Broad-scale flight counts

Fine-scale flight counts

Invasive species The impact of invasive species

100m radius around each tower footing

Up to January 2019

Consultant, Contractor

Existing population and distribution of species

Invasive species survey has been conducted by the contractor and some invasive species recorded.

Construction

Brid monitoring surveys

Impact on birds Throughout the Vankalai sanctuary

Monthly Consultant, Contractor

Block counts by sector A field trial to determine the appropriate methodology for carcass searching along the whole length of transmission line through Vankalai Sanctuary is to be carried out. This study cannot be undertaken as the

Vantage point count

Broad-scale flight

47

counts transmission line has not been completed yet and therefore, the probability of collision does not exist.

Fine-scale flight counts

Bird collision monitoring

Impact on bird collision

The whole length of Transmission line Vankalai sanctuary

The wet and dry season

Consultant, Contractor

Carcasses searching

A field trial to determine the appropriate methodology for carcass searching along the whole length of transmission line through Vankalai Sanctuary is to be carried out. This study cannot be undertaken as the transmission line has not been completed yet and therefore, the probability of collision does not exist.

48

3.3 Marine Environmental Monitoring

Table 3.5: Monitoring of Marine Environment

Potential Impact Proposed Mitigation measures

Monitoring Means and frequency

Responsibility Performance Indicator

Compliance with the requirements in the field level

Construction Phase

Sedimentation in sensitive coastal environments due to dredging and disposal of excavated material

Any disposal of excavated material should be done outside of the sanctuary away from sensitive fisheries or breeding grounds. Disposal should be timed to be outside of the upwelling period.

Scientific investigation should be undertaken downstream delineate the area impacted by the plume.

Once before, regularly during

and once after construction

EPC Contractor

Siltation of soil in the lagoon, salt marshes from construction activities.

No significant impact due to omission of pier construction. All type of disposal materials disposes to the approved site by the LA.

Soils excavated for the erection of towers should be used for re- filling and should not be left exposed to wind or water for long periods. Sediment control measures such as retention weirs will be used, as necessary, to minimize sediment transport offsite. Silt fencing must also be implemented to minimize erosion of soil stockpiles.

Inspection, Routine monitoring

Once before, regularly during and once after construction

EPC Contractor

Physical Water Quality (TSS, soil texture)

Complied with

necessary mitigation

measures.

Soil erosion due to loss of vegetation

Mangrove vegetation should be minimally disturbed during the construction phase to reduce soil erosion and safeguard waterbody protection

Inspection

Once before, regularly during and once after construction

EPC Contractor

Status of ground cover in constructed areas

Complied with necessary mitigation measures

Re-plant degraded areas with local species common in the area to Complement natural vegetation regeneration to improve ground cover.

Routine Maintenance Supervising engineer

Revegetation per sq. m)- Costing will be done by ecologist

Will be complied with

proposed tree planting

process.

Not applicable in this stage

49

Water Pollution Maintenance of construction vehicles should be carried out in the Contractor's day-time camp.

Routine inspection,

Maintenance records

Consultant Supervising

Engineer and

Contractor

Water quality

parameters DO, BOD, COD,

Water transparency, oil

content, coliforms

Complied with

Impact on aquatic fauna Strict measures should be taken to minimize the impact on aquatic life

Scientific investigation should be undertaken downstream delineate the area impacted by the plume.

Once before, regularly during and once after construction

Consultant Contractor

• Ichthyo-plankton surveys

• Zooplankton and phytoplankton surveys

Not Applicable due to

omission of pier

construction.

Impact on aquatic resources

A survey should be carried out to assess any impact on marine resources. Changes in fish Catch in particular. It is likely that complaints may be received from local fishermen regarding decreasing catches after the project.

Once before, regularly during and once after construction

Consultant Contractor

Records of fish and

shellfish impingement:

number and weight by species

fish catch data

No records regarding

the impact on marine

resources.

Impact on seagrass meadows

A survey should be carried out to assess any impact on seagrass meadows.

Once before, regularly during and once after construction

Consultant Contractor

Underwater survey for diversity and extent of seagrasses within direct Impact Zone

Not Applicable due to

omission of pier

construction.

50

Invasive species

A survey should be carried out to assess any invasion of invasive species.

Once before, regularly during and once after construction

Consultant Contractor

Surveying for new populations of invasive species resulted from Construction.

complied with

Management of Solid Waste

The contractor must dispose solid wastes away from the site to

an approved licensed waste disposal

site.

Routine Maintenance Contractor, Supervising Engineer

Complied with

Solid soil

Waste and stone debris

Transportation of

waste from site & safe disposal

Project Duration Contractor

Supervising

Engineer

Complied with

Drainage construction Of pylons may interfere with the natural drainage systems and modify the flow of surface water

In sections along watercourses, earth and construction waste will be properly disposed of so as not to block waterways, resulting in adverse impact on water quality.

Properly disposed waste Contractor

Supervising

Engineer

Will be complied with

All necessary measures will be taken to prevent earthworks from Impeding cross drainage at rivers/ streams, canal/existing irrigation and drainage systems

51

4.0 Summary

The overall evaluation of the Environmental Monitoring Programme will be assessed based on Table 3.1 and 3.2.

Sub-Project Name Environm- ental screening is carried out? (Yes or No)

Environment category of the project / subproject (A/B/C/FI)

EIA/IEE/ DDR with EMP is prepared (Yes/No)

ADB approved EIA/IEE with EMP (Yes / Under Review/ Not Yet Due/Overdue)

Government approved EIA/IEE with EMP (Yes / Under Review / Not Yet Submitted)

Safeguard monitoring and coordination mechanism established (Yes/No)

GRC is establ- ished (Yes /No)

Automated safeguard monitoring system customized (Yes/No)

EMP cost in approved document is included in BOQ as an individual item (Yes/No)

Wind Power Generation Project (Project No. 49345-002):

Integrate the 100 MW power from the Mannar Wind Power Generation Project to National Grid network of Sri Lanka.

Yes A Yes Yes Yes Yes Yes Yes Yes

Green Power Development and Energy Efficiency Improvement Investment Program (GPD&EEIIP) - Tranche 2 (Project No. 47037-005)

Package 2: Lot A - Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation

Yes A

Yes Yes Yes Yes Yes Yes Yes

Package 2: Lot B1 - Construction of 30 km long Mannar–Nadukuda 220 kV transmission line

Yes Yes Yes Yes Yes Yes Yes Yes

52

Table 4.1: Overall Compliance with EMP/ EMoP

No. Sub-Project Name EMP/ CEMP Part of Contract Documents

(Y/N)

CEMP/ EMP Being Implemented (Y/N)

Status of Implementation

(Excellent/ Satisfactory/ Partially Satisfactory/ Below

Satisfactory)

Action Proposed and Additional Measures

Required

Wind Power Generation Project (Project No. 49345-002):

Integrate the 100 MW power from the Mannar Wind Power Generation Project to National Grid network of Sri Lanka.

Y Y Satisfactory Only site clearing has been done for wind turbine sites. Pile construction is in progress at 4 sites. No additional measured are required for the time being.

Green Power Development and Energy Efficiency Improvement Investment Program (GPD&EEIIP) - Tranche 2 (Project No. 47037-005)

Package 2: Lot A - Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation

Y Y Satisfactory Site preparation for grid sub-station is complete. Measures for dust control should be improved.

Package 2: Lot B1 - Construction of 30 km long Mannar–Nadukuda 220 kV transmission line

Y Y Satisfactory More than 90% of towers have been erected. Others have been partially erected. No particular additional measures are required.

53

Annex 1: Photographs taken during field visits

Land clearing and preparation for the yard

for wind turbines

Soil for filling of the land (partially covered)

Large trees have been left uncut in the yard

area

Site office built at the yard area

Boundary fenced and access roads are being

built

Shrubland has been cleared for the yard

area

54

Warning signs erected at appropriate

locations

Safety and warning signs erected at

appropriate locations

Muddy areas due to erosion of topsoil and

poor local drainage

Muddy areas due to erosion of topsoil and

poor local drainage

Poor storage of raw material Poor storage of raw material

55

Topsoil erosion at Grid sub-

station/Administration building site

Soil erosion at Grid sub-

station/Administration building site

Solid waste (garbage) disposed at nearby

lands

Solid waste (garbage) disposed at nearby

lands

Pipe construction in progress (tower 23) Pipe construction in progress (tower 23)

56

Bentonite collection Leveling of excavated soil/sand

Pile construction in progress (tower 24) Pile construction in progress (tower 24)

Transmission tower construction in

waterlogged area

Transmission tower construction in

waterlogged area

57

Stringing in progress

58

Annex 2: Summary of consultations

Date Venue Description

20.03.2019 Wind Farm, Transmission line, Grid Substation, Mannar

Reconnaissance surveys, field visits, discussions with field personnel

28.03.2109 Asian Development Bank Discussions with the ABD staff and the CEB staff

29.06.2019 Wind Farm, Grid Substation, Mannar

Detailed surveys, field visits, discussions with field personnel

30.06.2019 Transmission Line, Mannar Detailed surveys, field visits, discussions with field personnel

19.10.2019 Wind Farm, Grid Substation, Mannar

Detailed surveys, field visits, discussions with field personnel

20.10.2019 Transmission Line, Mannar Detailed surveys, field visits, discussions with field personnel

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 1

Environmental Monitoring Report - July 2019

Reporting Period July 1st to 31st 2019

Date 1st August 2019

Mannar Wind Power Project

Construction of 100MW Semi Dispatchable Wind Farm in Mannar Island

Ceylon Electricity Board

Prepared by Vestas for the Ceylon Electricity Board

Environmental Monitoring Report (July 2019)- Wind Farm

Annex 3.1 : Monitoring Reports and other data- Wind Farm

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 2

Version History

Revision Date Changes Overview Remarks

A 01/08/2019 First Issue

This version,

Main Contractor

(Vestas Asia Pacific

A/S)

Prepared By: V. Ravi Environmental & Social

Safeguard Officer

Approved By: Sivaprakash

Mohan Assistant Project Manager

Paper Size (for printing)

Main Document (Page 1 to 10) A4

Document Type Monthly Progress Report

Discipline HSE

Area Project Wide

Document Classification Restricted

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 3

Contents Executive Summary ................................................................................................................................. 4

1.0 Introduction ................................................................................................................................ 5

1.1 Brief Project Description ......................................................................................................... 5

1.2 Project Progress Status and Implementation Schedule .......................................................... 5

Implementation Schedule ............................................................................................................... 5

2.0 Compliance to National Regulations ........................................................................................... 6

2.1 Applicable National Laws, regulation and policies ....................................................................... 6

3.0 Compliance to Environmental Covenants from the ADB Loan Agreement ................................ 7

4.0 Compliance to Environmental Management Plan ...................................................................... 8

4.0 Safeguards Monitoring Results and Unanticipated Impacts ...................................................... 8

6.0 Implementation of Grievance Redress Mechanism and Complaints Received from

Stakeholders ......................................................................................................................................... 10

7.0 Conclusion and Recommendations........................................................................................... 10

Annex 1; Photo sheet ............................................................................................................................ 10

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 4

Executive Summary

The Environmental Impact Assessment (EIA) of this project has carefully reviewed by the Vestas. As

first step to comply the EIA recommendations, the Construction Method Statement (CMS) has

prepared and submitted to the CEB. Further, the SEMP submitted to CEB.

This monthly report is prepared as per the request and outline provided by the contractor for civil

activities for the month of July 2019. An environmental and social safeguard officer with the HSE

team has established to perform this task. Around 65 site induction meetings have conducted to the

staffs during this period. One collective program conducted to a sub-contractor on the

environmental and social safeguard aspects, ten staff officers has participated.

Preparatory works of main access road, accommodation building and admin building area and soil

stocking were the main civil activities during July 2019. No any exceedance of environmental

standards was identified.

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 5

1.0 Introduction

1.1 Brief Project Description

Ceylon Electricity Board is implementing a semi-dispatchable 100 MW wind power project in Mannar

with the loan assistance of Asian Development Bank. The main benefit from the project is electricity

generation from wind power of about 345 gigawatt hours (GWh) per year, which will be avoiding

electricity generation from conventional power plants such as thermal power.

The project is comprised the construction of the following major components:

1. A total of 30 wind turbines with a turbine specification and layout to comply with

environmental and social aspects;

2. A collector substation and control building;

3. The collector cables, step-up transformers and switchgears and accessories;

4. Supporting infrastructure will consist of access roads, temporary storage facilities, building

and staff accommodation facilities, etc.

The proposed wind power farm is in the southern part of Mannar Island from Thoddaveli to Pesalai

South, with a length of about 12.5 kilometers (km) along the coast. The first row of up to 30 turbines

will be placed about 150 meters (m) to 160 m from the shoreline. The proposed wind farm has

excluded the areas coming under the Adam’s Bridge Marine National Park (by approximately 1 km)

declared in 2015 by the Government of Sri Lanka (GoSL). The nearest village is about 800 m away

from the second row of wind turbines. Several Navy camps and Navy observation points, boat

landing sites, ma-del hauling sites, and fishermen vaadi/camps (seasonal), two investment cabanas,

and a tourist hotel are found within the wind farm block. Access roads to the Navy camps, fishermen

camps and fish landing sites from Mannar- Thalaimannar highway, and roads parallel to the coastline

are also found within the wind farm.

VESTAS ASIA PACIFIC A/S as a main contractor has awarded to construct the wind farm in Mannar by

the CEB during November 2018.

1.2 Project Progress Status and Implementation Schedule

Implementation Schedule

The Implementation period of the MWPP is from March 2019 to September 2020. The major activity

of this project includes, construction of access roads, rehabilitation of roads, construction of 30 nos.

of wind towers, construction of buildings, bird collision detection system, community roads and

sanitary facility for fishing community.

During the reporting period, mainly three activities are in-progress. Those are test bore hole works,

surveying of access roads and batching plant construction. The following table is giving the summary

of the civil work status as on 31st July 2019.

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 6

Activity Unit Total

Qty Act Qty

WTG

Geotech Investigation for WTG Location Nos 30 30

WTG Clearance Nos 30 27

Roads

Geotech Investigation for Roads m 25600 15000

Main Access Road

Subgrade Preparation m 12500 4050

Embankment m 12500 3790

Admin building excavation M3 170 24.6

Admin building RR work M3 70 23.3

Table 1 Summary of work progress as on 31st July 2019

Man Power

In addition, an Environmental and Social safeguard officer, HSE manager, HSE officers are appointed

by Vestas and one HSE manager, three safety officers are appointed by sub-contractors. This team is

executing the environmental and social related matters in addition to the health and safety aspects.

2.0 Compliance to National Regulations

2.1 Applicable National Laws, regulation and policies

Following national Laws, regulations and policies are identified as applicable to the MWPP in the EIA

report.

• National Environmental Act (NEA) No 47 of 1980, and its amendment Act No. 56 of 1988

and Act No. 53 of 2000

• Flora and fauna Protection Ordinance (FFPO) amended by Act No. 38 of 1949Agrarian

Services Act No. 58 of 1979

• Forest Act No. 34 of 1951Control of Pesticide Act No. 33 of 1980

• PradeshiyaSabha Act No. 15 of 1987Crown Land Ordinance (Chapter 454)

• Sri Lanka Electricity Act No. 20/2009 and 2013 (as amended)

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 7

• Felling of trees Act No. 9 of 1951

• The Ma-del (beach seine) Regulations of 1984

• Fisheries and Aquatic Resources Act No. 2 of 1996 (and subsequent amendments, No 22 of

2006, 35 of 2013)

• Coast Conservation Act No 57, of 1981, amended by Act no 4 of 1996

• Marine Pollution Prevention Act No 35 of 2008

• Soil Conservation Act No 25 of 1951 subsequent amendments:

• Land Acquisition Act No 9 of 1950 and Local Authority Regulations of 2008

• Explosive Act No. 34 of 1976

• Felling of Trees Control Act No. 09 of 1951 as amended through Act No. 30 of 1953

• Public Utilities Commission of Sri Lanka Act No 35 of 2002.

• Sri Lanka Sustainable Energy Authority Act No. 35, 2007

• Agrarian Services Act (N0 58 of 1979)

• Flood Act N0 22 of 1955

• Monuments and Archaeological Sites and remains Act, 1958. Act No24 of 1958

• Motor Traffic Act No 60 of 1979

• National Involuntary Resettlement Policy

• National Institute of Occupational 1 Safety and Health Act, No. 38 Of 2009

• Geological Survey and Mines Bureau (GSMB) Act no. 33 of 1992

• Irrigation Act No. 1 of 1951

• Land Acquisition Act No. 9 of 1950

• National water Supply and Drainage Board (NWS&DB) Act No. 2 of 1974

• State Land (Recovery Possession) Act No 7 of 1979

• Urban Development Authority (UDA) Act No. 7 of 1978

3.0 Compliance to Environmental Covenants from the ADB Loan

Agreement

ADB loan agreement of schedule 5 para 2 stated as, ‘The burrower shall ensure that (a) all applicable

laws and regulations of the Guarantor relating to environment, health, and safety; (b) the

Environmental Safeguards; (c) the Environmental Assessment Results Framework (EARF); and (d) all

measures and requirements set forth in the respective IEE or EIA, EMP and BMP, and any corrective

or preventative actions set forth in a safeguards monitoring report.

In addition to this Vestas will ensure that the preparation, design, construction, implementation and

operation and commissioning of the project and all project facilities pertaining to the tender

document will comply with;

a. All applicable laws and regulations of the country relating to environment, health and safety,

b. Environmental safeguards,

c. Requirements outlined in the EIA, EMP, EMoP, BMP and any corrective or preventive actions

mentioned in this monitoring report.

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 8

4.0 Compliance to Environmental Management Plan

Construction Environmental Management Plana and Site-Specific Environmental Management Plan

had developed and submitted to CEB.

In addition, three ways of approach has developed to implement the EMP;

1. A daily progress review meeting organized with the civil work sub-contractor it includes the

discussion of environmental issues based on the previous day observation.

2. Independent inspection – The Environmental & Social Safeguard Officer of Vestas will inspect

the work sites regularly.

3. Environmental patrol (not yet established) – Collective inspection with CEB, Vestas and sub-

contractor will be organized on monthly basis to observe the level of implementation and

report the same.

5.0 Safeguards Monitoring Results and Unanticipated Impacts

ADB consultant has visited to the wind farm site and the admin building area to monitor the

environmental & social safeguard measures.

Testing of Environmental parameter prior to the construction activity is scheduled on the

Environmental Monitoring Plan of EIA. Currently, the vendor registration completed and expected to

do the field work by August.

The following table outlined the quality rank for the environmental and social safeguard effort

during the reporting period.

No Activity / Task Excellent

Very

Good Good Poor

Very

Poor Remarks

1 Land Survey & Clearance √

2 Geotechnical Investigation completed

3 Pile Foundation NA

4 Excavation for WTG Foundation NA

5 Excavation of UG Cable Trench & Cable Laying NA

6 WTG Components Shifting / Transportation NA

7 PCC NA

8 Anchor Cage Assembly & Installation NA

9 Steel Reinforcement NA

10 UG Cable Laying NA

11 Trans Mixer Movement NA

12 Tower Sections Installation NA

13 Nacelle Assembly & Installation NA

14 Blade Assembly & Installation NA

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 9

15 Main Access Road Development & Construction √

16 Access Road 1 Development & Construction √

17 Access Road 2 Development & Construction √

18 Access Road 3 Development & Construction √

19 Development of Culverts in Access Roads √ NA

20 Accommodation Building Construction √

21 Admin Building Construction NA

22 Storage Yard Development √

23 Crane Pad & Hard Stand Development NA

24 Loading & Unloading of Components √

25 Commissioning of Feeder NA

26 Commissioning of Switch Gears NA

27 Batching Plant Development, Construction & Operation √

28 Labor Camp facilities at Construction site √

29 Driving in Windfarm Roads √

30 Working at Night NA

31 Social safeguard activites (5.13) NA

No Activity / Task Excellent Very GoodGood Poor Very Poor Remarks

1 Land Survey & Clearance √2 Geotechnical Investigation completed

3 Pile Foundation NA

4 Excavation for WTG Foundation NA

5 Excavation of UG Cable Trench & Cable Laying NA

6 WTG Components Shifting / Transportation NA

7 PCC NA

8 Anchor Cage Assembly & Installation NA

9 Steel Reinforcement NA

10 UG Cable Laying NA

11 Trans Mixer Movement NA

12 Tower Sections Installation NA

13 Nacelle Assembly & Installation NA

14 Blade Assembly & Installation NA

15 Main Access Road Development & Construction √16 Access Road 1 Development & Construction NA

17 Access Road 2 Development & Construction NA

18 Access Road 3 Development & Construction NA

19 Development of Culverts in Access Roads NA

20 Accommodation Building Construction √21 Admin Building Construction √ NA

22 Storage Yard Development √23 Crane Pad & Hard Stand Development NA

24 Loading & Unloading of Components √25 Commissioning of Feeder NA

26 Commissioning of Switch Gears NA

27 Batching Plant Development, Construction & Operation √28 Labor Camp facil ities at Construction site √29 Driving in Windfarm Roads √30 Working at Night √31 Social safeguard activites (5.13) NA

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 10

6.0 Implementation of Grievance Redress Mechanism and Complaints

Received from Stakeholders

Complaint boxes prepared with record books at the following locations are identified to install the

compliant boxes, will be checked daily and keep recording if any by the safety officers and by Vestas.

➢ Sub-contractors site office & Laboratory - Puthukudiyiruppu

➢ Sub-contractor’s storage yard - Thoddavely

➢ Batching plant – Periya Karisal

➢ Vestas office/ Storage area – Nadukkuda

➢ Admin building area - Nadukuda

➢ Accomodation building area - Thoddavely

So far, no grievances were received from public or any agencies.

7.0 Conclusion and Recommendations

During the reporting period, Main access road formation works, accommodation area preparatory

works, admin area preparatory works, and soil stocking works were carried out. All the works are

aligned with the recommendation of EMP, CMS and SEMP.

Annex 1; Photo

Weekly safety meeting Construction of bypass road

MWPP-VAPC-HSE-MPR-0001 1 August 2019

Environmental Monitoring Report - July 2019 11

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 1

Environmental Monitoring Report - August 2019

Reporting Period August 1st to 31st August 2019

Date 1st September 2019

Mannar Wind Power Project

Construction of 100MW Semi Dispatchable Wind Farm in Mannar Island

Ceylon Electricity Board

Prepared by Vestas for the Ceylon Electricity Board

Environmental Monitoring Report (August 2019)- Wind Farm

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 2

Version History

Revision Date Changes Overview Remarks

A 01/09/2019 First Issue

This version,

Main Contractor

(Vestas Asia Pacific

A/S)

Prepared By: V. Ravi Environmental & Social

Safeguard Officer

Approved By: Sivaprakash

Mohan Assistant Project Manager

Paper Size (for printing)

Main Document (Page 1 to 10) A4

Document Type Monthly Progress Report

Discipline HSE

Area Project Wide

Document Classification Restricted

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 3

Contents Executive Summary ................................................................................................................................. 4

1.0 Introduction ................................................................................................................................ 5

1.1 Brief Project Description ......................................................................................................... 5

1.2 Project Progress Status and Implementation Schedule .......................................................... 5

Implementation Schedule ............................................................................................................... 5

2.0 Compliance to National Regulations ........................................................................................... 6

2.1 Applicable National Laws, regulation and policies ....................................................................... 6

3.0 Compliance to Environmental Covenants from the ADB Loan Agreement ................................ 7

4.0 Compliance to Environmental Management Plan ...................................................................... 8

4.0 Safeguards Monitoring Results and Unanticipated Impacts ...................................................... 8

6.0 Implementation of Grievance Redress Mechanism and Complaints Received from

Stakeholders ......................................................................................................................................... 10

7.0 Conclusion and Recommendations........................................................................................... 10

Annex 1; Photo sheet ............................................................................................................................ 10

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 4

Executive Summary

The Environmental Impact Assessment (EIA) of this project has carefully reviewed by the Vestas. As

first step to comply the EIA recommendations, the Construction Method Statement (CMS) has

prepared and submitted to the CEB. Further, the SEMP submitted to CEB.

This monthly report is prepared as per the request and outline provided by the contractor for civil

activities for the month of August 2019. An environmental and social safeguard officer with the HSE

team has established to perform this task. Around nine site induction and 74 tool box meetings

have conducted to the staffs during this period. One collective program conducted to a sub-

contractor on the environmental and social safeguard aspects, ten staff officers has participated.

Preparatory works of main access road, accommodation building foundation work, test piling works

and admin building soil filing and soil stock works are the main civil activities during August 2019. No

any exceedance of environmental standards was identified.

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 5

1.0 Introduction

1.1 Brief Project Description

Ceylon Electricity Board is implementing a semi-dispatchable 100 MW wind power project in Mannar

with the loan assistance of Asian Development Bank. The main benefit from the project is electricity

generation from wind power of about 345 gigawatt hours (GWh) per year, which will be avoiding

electricity generation from conventional power plants such as thermal power.

The project is comprised the construction of the following major components:

1. A total of 30 wind turbines with a turbine specification and layout to comply with

environmental and social aspects;

2. A collector substation and control building;

3. The collector cables, step-up transformers and switchgears and accessories;

4. Supporting infrastructure will consist of access roads, temporary storage facilities, building

and staff accommodation facilities, etc.

The proposed wind power farm is in the southern part of Mannar Island from Thoddaveli to Pesalai

South, with a length of about 12.5 kilometers (km) along the coast. The first row of up to 30 turbines

will be placed about 150 meters (m) to 160 m from the shoreline. The proposed wind farm has

excluded the areas coming under the Adam’s Bridge Marine National Park (by approximately 1 km)

declared in 2015 by the Government of Sri Lanka (GoSL). The nearest village is about 800 m away

from the second row of wind turbines. Several Navy camps and Navy observation points, boat

landing sites, ma-del hauling sites, and fishermen vaadi/camps (seasonal), two investment cabanas,

and a tourist hotel are found within the wind farm block. Access roads to the Navy camps, fishermen

camps and fish landing sites from Mannar- Thalaimannar highway, and roads parallel to the coastline

are also found within the wind farm.

VESTAS ASIA PACIFIC A/S as a main contractor has awarded to construct the wind farm in Mannar by

the CEB during November 2018.

1.2 Project Progress Status and Implementation Schedule

Implementation Schedule

The Implementation period of the MWPP is from May 2019 to November 2020. The major activity of

this project includes, construction of access roads, rehabilitation of roads, construction of 30 nos. of

wind towers, construction of buildings, bird collision detection system, community roads and

sanitary facility for fishing community.

During the reporting period, mainly three activities are in-progress. Those are test bore hole works,

surveying of access roads and batching plant construction. The following table is giving the summary

of the civil work status as on 31st July 2019.

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 6

Activity Unit Total

Qty Act Qty

WTG

Geotech Investigation for WTG Location Nos 30 Completed

WTG Clearance Nos 30 Completed

Roads

Geotech Investigation for Roads m 25600 15000

Main Access Road

Subgrade Preparation m 12500 9750

Embankment m 12500 3790

Admin building excavation M3 170 125

Admin building RR work M3 70 50.6

Screed concerts M2 170 141

Accommodation building- sand filling M3 8900 1830

WTG foundation – Piling work Nos 451 3

Table 1 Summary of work progress as on 31st August 2019

Man Power

In addition, an Environmental and Social safeguard officer, HSE manager, HSE officers are appointed

by Vestas and one HSE manager, three safety officers are appointed by sub-contractors. This team is

executing the environmental and social related matters in addition to the health and safety aspects.

2.0 Compliance to National Regulations

2.1 Applicable National Laws, regulation and policies

Following national Laws, regulations and policies are identified as applicable to the MWPP in the EIA

report.

• National Environmental Act (NEA) No 47 of 1980, and its amendment Act No. 56 of 1988

and Act No. 53 of 2000

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 7

• Flora and fauna Protection Ordinance (FFPO) amended by Act No. 38 of 1949Agrarian

Services Act No. 58 of 1979

• Forest Act No. 34 of 1951Control of Pesticide Act No. 33 of 1980

• PradeshiyaSabha Act No. 15 of 1987Crown Land Ordinance (Chapter 454)

• Sri Lanka Electricity Act No. 20/2009 and 2013 (as amended)

• Felling of trees Act No. 9 of 1951

• The Ma-del (beach seine) Regulations of 1984

• Fisheries and Aquatic Resources Act No. 2 of 1996 (and subsequent amendments, No 22 of

2006, 35 of 2013)

• Coast Conservation Act No 57, of 1981, amended by Act no 4 of 1996

• Marine Pollution Prevention Act No 35 of 2008

• Soil Conservation Act No 25 of 1951 subsequent amendments:

• Land Acquisition Act No 9 of 1950 and Local Authority Regulations of 2008

• Explosive Act No. 34 of 1976

• Felling of Trees Control Act No. 09 of 1951 as amended through Act No. 30 of 1953

• Public Utilities Commission of Sri Lanka Act No 35 of 2002.

• Sri Lanka Sustainable Energy Authority Act No. 35, 2007

• Agrarian Services Act (N0 58 of 1979)

• Flood Act N0 22 of 1955

• Monuments and Archaeological Sites and remains Act, 1958. Act No24 of 1958

• Motor Traffic Act No 60 of 1979

• National Involuntary Resettlement Policy

• National Institute of Occupational 1 Safety and Health Act, No. 38 Of 2009

• Geological Survey and Mines Bureau (GSMB) Act no. 33 of 1992

• Irrigation Act No. 1 of 1951

• Land Acquisition Act No. 9 of 1950

• National water Supply and Drainage Board (NWS&DB) Act No. 2 of 1974

• State Land (Recovery Possession) Act No 7 of 1979

• Urban Development Authority (UDA) Act No. 7 of 1978

3.0 Compliance to Environmental Covenants from the ADB Loan

Agreement

ADB loan agreement of schedule 5 para 2 stated as, ‘The burrower shall ensure that (a) all applicable

laws and regulations of the Guarantor relating to environment, health, and safety; (b) the

Environmental Safeguards; (c) the Environmental Assessment Results Framework (EARF); and (d) all

measures and requirements set forth in the respective IEE or EIA, EMP and BMP, and any corrective

or preventative actions set forth in a safeguards monitoring report.

In addition to this Vestas will ensure that the preparation, design, construction, implementation and

operation and commissioning of the project and all project facilities pertaining to the tender

document will comply with;

a. All applicable laws and regulations of the country relating to environment, health and safety,

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 8

b. Environmental safeguards,

c. Requirements outlined in the EIA, EMP, EMoP, BMP and any corrective or preventive actions

mentioned in this monitoring report.

4.0 Compliance to Environmental Management Plan

Construction Environmental Management Plana and Site-Specific Environmental Management Plan

had developed and submitted to CEB.

In addition, three ways of approach has developed to implement the EMP;

1. A daily progress review meeting organized with the civil work sub-contractor it includes the

discussion of environmental issues based on the previous day observation.

2. Independent inspection – The Environmental & Social Safeguard Officer of Vestas will inspect

the work sites regularly.

3. Environmental patrol (not yet established) – Collective inspection with CEB, Vestas and sub-

contractor will be organized on monthly basis to observe the level of implementation and

report the same.

5.0 Safeguards Monitoring Results and Unanticipated Impacts

Environmental parameter testing carried out by NBRO, the result report will be submitted with the

next month report or separately as per the CEBs request. The following table outlined the quality

rank for the environmental and social safeguard effort during the reporting period.

No Activity / Task Excellent Very Good Good Poor Very Poor Remarks

1 Land Survey & Clearance Completed

2 Geotechnical Investigation Completed

3 Pile Foundation √

4 Excavation for WTG Foundation NA

5

Excavation of UG Cable Trench & Cable

Laying NA

6 WTG Components Shifting / Transportation NA

7 PCC NA

8 Anchor Cage Assembly & Installation NA

9 Steel Reinforcement NA

10 UG Cable Laying NA

11 Trans Mixer Movement NA

12 Tower Sections Installation NA

13 Nacelle Assembly & Installation NA

14 Blade Assembly & Installation NA

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 9

15

Main Access Road Development &

Construction √

16 Access Road 1 Development & Construction NA

17 Access Road 2 Development & Construction NA

18 Access Road 3 Development & Construction NA

19 Development of Culverts in Access Roads NA

20 Accommodation Building Construction √

21 Admin Building Construction √ NA

22 Storage Yard Development √

23 Crane Pad & Hard Stand Development NA

24 Loading & Unloading of Components √

25 Commissioning of Feeder NA

26 Commissioning of Switch Gears NA

27

Batching Plant Development, Construction &

Operation √

28 Labor Camp facilities at Construction site √

29 Driving in Windfarm Roads √

30 Working at Night √

31 Social safeguard activites (5.13) NA

The following CMS checklist attached accordance with the contract requirement.

SNo. Procedure to be followed Yes/No Impact Action Taken

A

1Site induction for each workman prior to commencing activities on site. Penalties of violating any EMP/regulatory

requirements must be explained and agreed. Y

Every workers have inducted and it is

continuing with the intensive monitoring

monthly safety committee meeting is

ongoing

B Pre-Construction & Site Preparation

1

Mark work areas, exclusion areas that are situated in the coastal/private areas. Make arrangement as per design and

location finalized by CEB/CCD for toilets at site. No water well will be located within minimum 100 m of a toilet facility

or vice versa. Y

Work area is marked, sign boards are in

place Continuous monitoring & reporting

2Designate and fence using sheets all laydown areas, material storage area, personnel area Y

Storage yards and workers

accommodations are arranged accordingly Continuous monitoring & reporting

3

Provide orientation training to construction staff on working methods that relate to air, water, noise and soil pollution,

avian, avifauna and mammal life in the area. Instructions on not to damage any property of local fishermen should

also be given. Fishing is not allowed by construction staff within project area. Y

Awareness program and safety induction

included the aspects and related notice

boards were displayed Continuous monitoring & reporting

4Designated area can only be used for storage of water, oil, construction material etc. with marked area for

construction. Park equipment within the same area specified by CEB as per design. Y

Related areas were selected with the

clients concurrence Continuous monitoring & reporting

C Access Road to each Wind turbine site in the coastal area

1 Ensure minimal disturbance to flora and fauna during construction of access route to Wind turbine footing NA Only temporary roads constructed

2 Ensure water channels are not blocked. Make use of culverts as required NA

3Remove extra sand/soil from site and store it in areas of depression. Do not throw any waste into the waterways to

pollute ecosystem NA

D Laydown areas next to each Wind turbine site in the coastal area

1 Ensure minimal disturbance to flora and fauna during construction of laydown area next to Wind turbine footing Y Only the hardstand area shrub cleared

2Make arrangements to reroute water channels near the construction areas if avoidance is not possible in consultation

with the project Ecologist. Y Channel diversion Only one location identified

3Remove extra sand/soil from site and store it in areas of depression until it is disposed of at locations specified by local

authorities offsite. NA

E Wind turbine Foundation construction

1 Excavator must not disturb flora and fauna while working on Wind turbine foundation site NA

2Planning for stacking of dugout sand/soil from foundation. Sheet piles to be used to avoid caving in of the sand sides

into the wind turbine foundation before concreting. NA

3 Dewatering of the area excavated for Wind turbine foundation erection into a pit for sedimentation and any oil

removal before letting of to the sea- prevention of pollution and damage to marine flora and fauna NA

4 Pre-cut/bent steel to be brought to Wind turbine site for fixing in the dugout foundation NA

5 Usage of premix concrete lorry with long boom to fill concrete. NA

6 Backfilling and compaction at foundation to be followed by removal of excess soil to designated offsite location while

ensuring no marine flora or fauna is damaged/killed NA

F Wind turbine, Nacelle and Blades Erection

1 Crane should not traverse directly over water course – use culverts NA

2 Carefully position heavy cranes and structures inside hard standing area for Wind turbine to ensure no damage NA

G Construction/Decommissioning of Pier for equipment

1Noise for digging of piles to be monitored. Construction only during prescribed working timing of the area. Night time

working not allowed. NA

2 Decommissioned pier to be removed entirely from the project site and the piles will be cut at least 1 m below the

coast sand to ensure that the fishing nets do not entangle into its protruding edges NA

H Digging/Construction of Cable Trenches

1To ensure minimum water course crossing in the coastal area. Trenches to run along the access roads and be covered

to avoid soil erosion. NA

2 Construct sheet piles at corners of waterways areas to avoid damage to waterways NA

I Removal of construction waste material

1Remove all waste material from coastal area including excess soil preventing water flow to designated waste

containment areas specified by the local body. NA

2 Remove all liquid waste material from coastal area NA

General Procedures

(The EPC contractor shall comply with Annexure 4 on Construction Method Statement for compliance with ADB SPS 2009.)

The EMP (Annexure 3), the EMoP (Annexure 5), and the Construction method statement (Annexure 4) shall be read together for environmental safeguards compliance for working within the wind farm project area by the EPC contractor. The following

checklist will be reviewed by CEB and more details may be added as deemed suitable.

CONSTRUCTION METHOD STATEMENT CHECKLIST - August 2019

MWPP-VAPC-HSE-MPR-0001 1 September 2019

Environmental Monitoring Report - August 2019 10

6.0 Implementation of Grievance Redress Mechanism and Complaints

Received from Stakeholders

Complaint boxes prepared with record books at the following locations are identified to install the

compliant boxes, will be checked daily and keep recording if any by the safety officers and by Vestas.

➢ Sub-contractors site office & Laboratory - Puthukudiyiruppu

➢ Sub-contractor’s storage yard - Thoddavely

➢ Batching plant – Periya Karisal

➢ Vestas office/ Storage area – Nadukkuda

➢ Admin building area - Nadukuda

➢ Accomodation building area - Thoddavely

So far, no grievances were received from public or any agencies.

7.0 Conclusion and Recommendations

During the reporting period, Main access road formation works, accommodation area foundation,

admin area soil filing works, test filing works and soil stocking works were carried out. All works are

strictly following the recommendation of EMP, CMS and SEMP.

Annex 1; Photo

Watering effort at Nadukuda road

Fuel storage area Safety award event to mark 100,000safe hours

Water sample collection by NBRO

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 1

Environmental Monitoring Report - September 2019

Reporting Period September 1st to 30th September 2019

Date 1st October 2019

Mannar Wind Power Project

Construction of 100MW Semi Dispatchable Wind Farm in Mannar Island

Ceylon Electricity Board

Prepared by Vestas for the Ceylon Electricity Board

Environmental Monitoring Report (September 2019)- Wind Farm

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 2

Version History

Revision Date Changes Overview Remarks

A 01/10/2019 First Issue

This version,

Main Contractor

(Vestas Asia Pacific

A/S)

Prepared By: V. Ravi Environmental & Social

Safeguard Officer

Approved By: Sivaprakash

Mohan Assistant Project Manager

Paper Size (for printing)

Main Document (Page 1 to 10) A4

Document Type Monthly Progress Report

Discipline HSE

Area Project Wide

Document Classification Restricted

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 3

Contents Executive Summary ................................................................................................................................. 4

1.0 Introduction ................................................................................................................................ 5

1.1 Brief Project Description ......................................................................................................... 5

1.2 Project Progress Status and Implementation Schedule .......................................................... 5

Implementation Schedule ............................................................................................................... 5

2.0 Compliance to National Regulations ........................................................................................... 6

2.1 Applicable National Laws, regulation and policies ....................................................................... 6

3.0 Compliance to Environmental Covenants from the ADB Loan Agreement ................................ 7

4.0 Compliance to Environmental Management Plan ...................................................................... 8

4.0 Safeguards Monitoring Results and Unanticipated Impacts ...................................................... 8

6.0 Implementation of Grievance Redress Mechanism and Complaints Received from

Stakeholders ......................................................................................................................................... 10

7.0 Conclusion and Recommendations........................................................................................... 10

Annex 1; Photo sheet ............................................................................................................................ 10

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 4

Executive Summary

The Environmental Impact Assessment (EIA) of this project has carefully reviewed by the Vestas. As

first step to comply the EIA recommendations, the Construction Method Statement (CMS) has

prepared and submitted to the CEB. Further, the SEMP submitted to CEB.

This monthly report is prepared as per the request and outline provided by the contractor for civil

activities for the month of September 2019. An environmental and social safeguard officer with the

HSE team has established to perform this task. Around nine site induction and 84 tool box meetings

have conducted to the staffs during this period. A collective program conducted to a sub-

contractor’s piling team on the environmental and social safeguard aspects, twelve staff officers has

participated.

Preparatory works of main access road, accommodation building column work, piling works and

admin building foundation and soil stock works are the main civil activities during September 2019.

Environmental parameter testing report has received and submitted to CEB. No any exceedance of

environmental standards was identified.

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 5

1.0 Introduction

1.1 Brief Project Description

Ceylon Electricity Board is implementing a semi-dispatchable 100 MW wind power project in Mannar

with the loan assistance of Asian Development Bank. The main benefit from the project is electricity

generation from wind power of about 345 gigawatt hours (GWh) per year, which will be avoiding

electricity generation from conventional power plants such as thermal power.

The project is comprised the construction of the following major components:

1. A total of 30 wind turbines with a turbine specification and layout to comply with

environmental and social aspects;

2. A collector substation and control building;

3. The collector cables, step-up transformers and switchgears and accessories;

4. Supporting infrastructure will consist of access roads, temporary storage facilities, building

and staff accommodation facilities, etc.

The proposed wind power farm is in the southern part of Mannar Island from Thoddaveli to Pesalai

South, with a length of about 12.5 kilometers (km) along the coast. The first row of up to 30 turbines

will be placed about 150 meters (m) to 160 m from the shoreline. The proposed wind farm has

excluded the areas coming under the Adam’s Bridge Marine National Park (by approximately 1 km)

declared in 2015 by the Government of Sri Lanka (GoSL). The nearest village is about 800 m away

from the second row of wind turbines. Several Navy camps and Navy observation points, boat

landing sites, ma-del hauling sites, and fishermen vaadi/camps (seasonal), two investment cabanas,

and a tourist hotel are found within the wind farm block. Access roads to the Navy camps, fishermen

camps and fish landing sites from Mannar- Thalaimannar highway, and roads parallel to the coastline

are also found within the wind farm.

VESTAS ASIA PACIFIC A/S as a main contractor has awarded to construct the wind farm in Mannar by

the CEB during November 2018.

1.2 Project Progress Status and Implementation Schedule

Implementation Schedule

The Implementation period of the MWPP is from May 2019 to November 2020. The major activity of

this project includes, construction of access roads, rehabilitation of roads, construction of 30 nos. of

wind towers, construction of buildings, bird collision detection system, community roads and

sanitary facility for fishing community.

During the reporting period, mainly three activities are in-progress. Those are test bore hole works,

surveying of access roads and batching plant construction. The following table is giving the summary

of the civil work status as on 31st July 2019.

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 6

Activity Unit Total

Qty Act Qty

Roads

Geotech Investigation for Roads m 25600 15000

Sub base 1st layer Preparation - Main Access

Road m 12500 430

Culvert road – Main access road Nos 24 0.5

Admin building screed concrete M3 180 174

Admin building RR work M3 103 73

Construction columns & 1st floor slab – Admin

building M3 180 14

Accommodation building- sand filling M3 1540 1179

Subgrade preparation - Accommodation M2 22000 2276

Boundary wall – RR work - Accommodation M3 275 100

WTG foundation – Piling work Nos 451 31

Table 1 Summary of work progress as on 30th September 2019

Man Power

In addition, an Environmental and Social safeguard officer, HSE manager, HSE officers are appointed

by Vestas and one HSE manager, three safety officers are appointed by two sub-contractors. This

team is executing the environmental and social related matters in addition to the health and safety

aspects.

2.0 Compliance to National Regulations

2.1 Applicable National Laws, regulation and policies

Following national Laws, regulations and policies are identified as applicable to the MWPP in the EIA

report.

• National Environmental Act (NEA) No 47 of 1980, and its amendment Act No. 56 of 1988

and Act No. 53 of 2000

• Flora and fauna Protection Ordinance (FFPO) amended by Act No. 38 of 1949Agrarian

Services Act No. 58 of 1979

• Forest Act No. 34 of 1951Control of Pesticide Act No. 33 of 1980

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 7

• PradeshiyaSabha Act No. 15 of 1987Crown Land Ordinance (Chapter 454)

• Sri Lanka Electricity Act No. 20/2009 and 2013 (as amended)

• Felling of trees Act No. 9 of 1951

• The Ma-del (beach seine) Regulations of 1984

• Fisheries and Aquatic Resources Act No. 2 of 1996 (and subsequent amendments, No 22 of

2006, 35 of 2013)

• Coast Conservation Act No 57, of 1981, amended by Act no 4 of 1996

• Marine Pollution Prevention Act No 35 of 2008

• Soil Conservation Act No 25 of 1951 subsequent amendments:

• Land Acquisition Act No 9 of 1950 and Local Authority Regulations of 2008

• Explosive Act No. 34 of 1976

• Felling of Trees Control Act No. 09 of 1951 as amended through Act No. 30 of 1953

• Public Utilities Commission of Sri Lanka Act No 35 of 2002.

• Sri Lanka Sustainable Energy Authority Act No. 35, 2007

• Agrarian Services Act (N0 58 of 1979)

• Flood Act N0 22 of 1955

• Monuments and Archaeological Sites and remains Act, 1958. Act No24 of 1958

• Motor Traffic Act No 60 of 1979

• National Involuntary Resettlement Policy

• National Institute of Occupational 1 Safety and Health Act, No. 38 Of 2009

• Geological Survey and Mines Bureau (GSMB) Act no. 33 of 1992

• Irrigation Act No. 1 of 1951

• Land Acquisition Act No. 9 of 1950

• National water Supply and Drainage Board (NWS&DB) Act No. 2 of 1974

• State Land (Recovery Possession) Act No 7 of 1979

• Urban Development Authority (UDA) Act No. 7 of 1978

3.0 Compliance to Environmental Covenants from the ADB Loan

Agreement

ADB loan agreement of schedule 5 para 2 stated as, ‘The burrower shall ensure that (a) all applicable

laws and regulations of the Guarantor relating to environment, health, and safety; (b) the

Environmental Safeguards; (c) the Environmental Assessment Results Framework (EARF); and (d) all

measures and requirements set forth in the respective IEE or EIA, EMP and BMP, and any corrective

or preventative actions set forth in a safeguards monitoring report.

In addition to this Vestas will ensure that the preparation, design, construction, implementation and

operation and commissioning of the project and all project facilities pertaining to the tender

document will comply with;

a. All applicable laws and regulations of the country relating to environment, health and safety,

b. Environmental safeguards,

c. Requirements outlined in the EIA, EMP, EMoP, BMP and any corrective or preventive actions

mentioned in this monitoring report.

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 8

4.0 Compliance to Environmental Management Plan

Construction Environmental Management Plana and Site-Specific Environmental Management Plan

had developed and submitted to CEB.

In addition, three ways of approach has developed to implement the EMP;

1. A daily progress review meeting organized with the civil work sub-contractor it includes the

discussion of environmental issues based on the previous day observation.

2. Independent inspection – The Environmental & Social Safeguard Officer of Vestas will inspect

the work sites regularly.

3. Monthly Environmental & Safety committee – Collective inspection with CEB, Vestas and sub-

contractor has organized by Vestas and the monthly inspection and discussion is in progress.

5.0 Safeguards Monitoring Results and Unanticipated Impacts

Environmental parameter testing carried out by NBRO, the result report is received the same is

submitted to the CEB. The following table outlined the quality rank for the environmental and social

safeguard effort during the reporting period.

No Activity / Task Excellent Very Good Good Poor Very Poor Remarks

1 Land Survey & Clearance Completed

2 Geotechnical Investigation Completed

3 Pile Foundation √

4 Excavation for WTG Foundation NA

5

Excavation of UG Cable Trench & Cable

Laying NA

6 WTG Components Shifting / Transportation NA

7 PCC NA

8 Anchor Cage Assembly & Installation NA

9 Steel Reinforcement NA

10 UG Cable Laying NA

11 Trans Mixer Movement NA

12 Tower Sections Installation NA

13 Nacelle Assembly & Installation NA

14 Blade Assembly & Installation NA

15

Main Access Road Development &

Construction √

16 Access Road 1 Development & Construction NA

17 Access Road 2 Development & Construction NA

18 Access Road 3 Development & Construction NA

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 9

19 Development of Culverts in Access Roads NA

20 Accommodation Building Construction √

21 Admin Building Construction √ NA

22 Storage Yard Development √

23 Crane Pad & Hard Stand Development NA

24 Loading & Unloading of Components √

25 Commissioning of Feeder NA

26 Commissioning of Switch Gears NA

27

Batching Plant Development, Construction &

Operation √

28 Labor Camp facilities at Construction site √

29 Driving in Windfarm Roads √

30 Working at Night √

31 Social safeguard activites (5.13) NA

The following CMS checklist attached accordance with the contract requirement.

SNo. Procedure to be followed Yes/No Impact Action Taken

A

1 Site induction for each workman prior to commencing activities on site. Penalties of violating any EMP/regulatory

requirements must be explained and agreed. Y

Every workers have inducted and it is

continuing with the intensive monitoring

Weekly mass tool box meeting and

monthly safety committee meetings are in

progress

B Pre-Construction & Site Preparation

1

Mark work areas, exclusion areas that are situated in the coastal/private areas. Make arrangement as per design and

location finalized by CEB/CCD for toilets at site. No water well will be located within minimum 100 m of a toilet facility

or vice versa. Y

Work area is marked, sign boards are in

place Continuous monitoring & reporting

2Designate and fence using sheets all laydown areas, material storage area, personnel area Y

Storage yards and workers

accommodations are arranged accordingly Continuous monitoring & reporting

3

Provide orientation training to construction staff on working methods that relate to air, water, noise and soil pollution,

avian, avifauna and mammal life in the area. Instructions on not to damage any property of local fishermen should

also be given. Fishing is not allowed by construction staff within project area. Y

Awareness program and safety induction

included the aspects and related notice

boards were displayed Continuous monitoring & reporting

4Designated area can only be used for storage of water, oil, construction material etc. with marked area for

construction. Park equipment within the same area specified by CEB as per design. Y

Related areas were selected with the

clients concurrence Continuous monitoring & reporting

C Access Road to each Wind turbine site in the coastal area

1 Ensure minimal disturbance to flora and fauna during construction of access route to Wind turbine footing Y Some works are started

2Ensure water channels are not blocked. Make use of culverts as required Y

Appropriate bypass has constructed with

the concurrence of client

3Remove extra sand/soil from site and store it in areas of depression. Do not throw any waste into the waterways to

pollute ecosystemY

Strict measures has implemented. An

Environmental rules sheet prepared and

read out at every TBM Tracking the TBM sheets

D Laydown areas next to each Wind turbine site in the coastal area

1 Ensure minimal disturbance to flora and fauna during construction of laydown area next to Wind turbine footing Y Only the hardstand area shrub cleared

2Make arrangements to reroute water channels near the construction areas if avoidance is not possible in consultation

with the project Ecologist. Y Channel diversion Only one location identified

3Remove extra sand/soil from site and store it in areas of depression until it is disposed of at locations specified by local

authorities offsite. NA

E Wind turbine Foundation construction

1 Excavator must not disturb flora and fauna while working on Wind turbine foundation site NA

2Planning for stacking of dugout sand/soil from foundation. Sheet piles to be used to avoid caving in of the sand sides

into the wind turbine foundation before concreting. NA

3 Dewatering of the area excavated for Wind turbine foundation erection into a pit for sedimentation and any oil

removal before letting of to the sea- prevention of pollution and damage to marine flora and fauna NA

4 Pre-cut/bent steel to be brought to Wind turbine site for fixing in the dugout foundation NA

5 Usage of premix concrete lorry with long boom to fill concrete. NA

6 Backfilling and compaction at foundation to be followed by removal of excess soil to designated offsite location while

ensuring no marine flora or fauna is damaged/killed NA

F Wind turbine, Nacelle and Blades Erection

1 Crane should not traverse directly over water course – use culverts NA

2 Carefully position heavy cranes and structures inside hard standing area for Wind turbine to ensure no damage NA

G Construction/Decommissioning of Pier for equipment

1Noise for digging of piles to be monitored. Construction only during prescribed working timing of the area. Night time

working not allowed. NA

2 Decommissioned pier to be removed entirely from the project site and the piles will be cut at least 1 m below the

coast sand to ensure that the fishing nets do not entangle into its protruding edges NA

H Digging/Construction of Cable Trenches

1To ensure minimum water course crossing in the coastal area. Trenches to run along the access roads and be covered

to avoid soil erosion. NA

2 Construct sheet piles at corners of waterways areas to avoid damage to waterways NA

I Removal of construction waste material

1 Remove all waste material from coastal area including excess soil preventing water flow to designated waste

containment areas specified by the local body. Y

All site wastes are segregated and collected

at site. The final disposal is according to

the recommendation of EMP

2 Remove all liquid waste material from coastal area NA

CONSTRUCTION METHOD STATEMENT CHECKLIST -September 2019

General Procedures

(The EPC contractor shall comply with Annexure 4 on Construction Method Statement for compliance with ADB SPS 2009.)

The EMP (Annexure 3), the EMoP (Annexure 5), and the Construction method statement (Annexure 4) shall be read together for environmental safeguards compliance for working within the wind farm project area by the EPC contractor. The following

checklist will be reviewed by CEB and more details may be added as deemed suitable.

MWPP-VAPC-HSE-MPR-0001 1 October 2019

Environmental Monitoring Report - August 2019 10

6.0 Implementation of Grievance Redress Mechanism and Complaints

Received from Stakeholders

Complaint boxes prepared with record books at the following locations are identified to install the

compliant boxes, will be checked daily and keep recording if any by the safety officers and by Vestas.

Sub-contractors site office & Laboratory - Puthukudiyiruppu

Sub-contractor’s storage yard - Thoddavely

Batching plant – Periya Karisal

Vestas office/ Storage area – Nadukkuda

Admin building area - Nadukuda

Accommodation building area - Thoddavely

So far, no grievances were received from public or any agencies.

7.0 Conclusion and Recommendations

During the reporting period, Main access road works, accommodation building column work, admin

area column works, piling works, and soil storage activities were carried out. All works are strictly

following the recommendation of EMP, CMS and SEMP.

Annex 1; Photo

Soil stock with dust cover at Wind farm area

Waste collection system at the Piling site Condition of bypass road at wind farm area

Awareness session to the piling team of sub-contractors

Page: Page 1 of 27 Report on the Geotechnical Investigations and

Recommendations at BH22

MWPP-ACCSS-GEO-RPT-0023

Date & Version: 06 June 2019, Rev. A

Author: Access Engineering PLC

REPORT ON THE GEOTECHNICAL

INVESTIGATIONS AND

RECOMMENDATIONS AT BH22

CONSTRUCTION OF 100MW SEMI DISPATCHABLE WIND

FARM IN MANNAR ISLAND SRI LANKA

Access Engineering PLC Ceylon Electricity Board Vestas Asia Pacific A/S

Client: Main Contractor: BoP Sub Contractor

Geotechnical Investigations and Recommendations Report

Page: Page 2 of 27 Report on the Geotechnical Investigations and

Recommendations at BH22

MWPP-ACCSS-GEO-RPT-0023

Date & Version: 06 June 2019, Rev. A

Author: Access Engineering PLC

Version History

Revision Date Changes Overview Remarks

A 06/06/2019 Initial issue

This version,

BoP Civil Contractor (Access Engineering

PLC)

Checked By: Dinidu Priyankara QA/QC Manager

Approved By: Achala Kalinga Contractor’s Representative

Main Contractor (Vestas Asia Pacific

A/S)

Checked By: Ononbaatar Jigjidsuren Civil Engineer

Approved By: Syed Sadathulla Nizamuddin Construction Manager

Page Size (for printing)

Main document A4

Report on the Geotechnical

Investigations and Recommendations

at B H22(726767.2s4,341844.321)

MANNAR WIND POWER PROJECT - PHASE 01 CONSTRCUTION OF lOOMW SEMI DISPATCHABLE WIND FARM IN MANNAR ISLAND

Client - Ceylon Electricity Board Main Contractor - Vestas Asia Pad.fie A/S Sub-Contractor - Access Engineering PLC

Prepared by Dr. U. P. Nawagamuwa BScEng.Hons(Moratuwa), MEng (AIT), DrEng(YNU), CEng, FIE(SL)

i----------'------ --- - -~ ~--

Report on the Geotechnical

Investigations and Recommendations

at B H22(726767.2s4,341844.321)

MANNAR WIND POWER PROJECT - PHASE 01 CONSTRCUTION OF lOOMW SEMI DISPATCHABLE WIND FARM IN MANNAR ISLAND

Client - Ceylon Electricity Board Main Contractor - Vestas Asia Pacific A/S Sub-Contractor - Access Engineering PLC

Prepared by

Dr. U. P. Nawagamuwa BScEng.Hons(Moratuwa), MEng (AIT), DrEng(YNU), CEng, FIE(SL)

CONTENT I

Page No

_,,

Introduction 3 1.

2. Structure information and site description 3

3. Field investigations 4

4. Subsurface conditions 4

5. Laboratory tests 5

6. Interpretation of the results of the site investigations 6

7. Recommendations 11

ppendix

A. Borehole record at BH no 22

B. Laboratory test reports

2

I .0 INTRODUCTION

With a national goal to increase the share of the nonconventional energy in S ·

Lanka by about 20%- of"the total generated power by 2020, Ceylon Electrici-

Board initiated the construction and operation of a semi-dispatchable wind farm

of lOOMW capacity along with the financial assistance of ADB funding.

Launched as the first phase of harnessing the wing electric potential in the

Mannar region, this electrical power generating project of 375 MW capacity will

be developed under four phases. The engineering, procurement and construction

(EPC) of the project was awarded to Vestas Wind Systems A/S; a Danish

manufacturer, seller, installer, and servicer of wind turbines. Vestas is to provide

the delivery, installation and commissioning of 30 V126-3.45 Mw wind turbines

as well as civil and electrical works.

The civil works of the plant is subcontracted to Access Engineering PLC b

Vestas and the scope of the project includes dilapidation survey and geo-

technical investigations, architectural and structural design of buildings, roads

and tower foundation, pilling, construction of foundation for wind turbines,

installation of medium voltage cables, design, supply and installation of optical

fibre cables, CCTV and intercom systems, road infrastructure works, etc.

The undersigned was requested by Access Engineering PLC to provide the Site

investigation reports and to propose foundation recommendations.

2. STRUCTURE INFORMATION AND SITE DESCRIPTION

Windmills will be installed in Mannar region in beach sandy soil. Foundation will comprise -,

of Cast in-situ bored piles of 800mm diameter.

3

3.0 FIELD INVESTIGATIONS I

.Field investigation consisted of drilling at least one borehole at each "\vindIT'ill

location. The boreholes were advanced down to the hanuner bounce level (SPT >50)

for at least 3 continuous layers. Mobilization of drilling rigs, equipment and

personnel to the site was borne by ACCESS Engineering PLC and the undersigned

observed the investigation procedure at those sites on random basis. ACCESS

Engineering PLC was responsible to present the BH records to the undersigned with

core boxes for sample observations and further investigations.

In all overburden formations Standard Penetration Test (SPT) was conducted at an

interval of 1.5m. In those soil formations, the visual classification was carried out for

each soil type encountered.

4.0 SUBSURFACE CONDITIONS

Details descriptions of subsurface condition encountered in the site during the field

investigation is presented in the borehole longs of BH 22at 726767.254,341844.321(Appendix

A). From the results of the borehole investigations at borehole location BH 22, five major soil

layers could be identified depending on the particle size distribution and SPT values as

shown in Figure 1.

Five basic layers were identified as follows.

Layer 1 - Fine to medium sand with shell

Layer 2 - Clayey sand with shell

Layer 3 -Fine to medium clayey sand with sandstone

Layer 4 - Fine to medium clayey sand

Layer 5 - Fine to medium clayey sand with limestone

Idealized profile and assumed properties are discussed in chapter 6.

4

I

·-.o LABORATORY TESTS

ils Mechanics Laboratory of University of Moratuwa conducted the laboratory tests on the

core boxes handed over to the laboratory. All the samples handed over were tested on

_ article size distribution, natural moisture content and specific gravity tests. Those results

e attached as Appendix B. It was noted that all the samples do not contain more than 5 %

::mes. Therefore, the general classification for the entire stratum would be sand.

5

16.0 INTERPRET A TI ON OF THE RES UL TS OF THE SITE INVESTIGATIONS

6.1 Soil Properties

6.1.1 Soil strength and compressibility parameters

To estimate the soil strength parameters of the soil layers, ' the energy method of SPT

correction was used (Bowels, 2002). The standard blow count Nf0

can be computes as

follows.

where, CN - adjustment for effective overburden pressure

CN = (95

·;6

)112 Pc{- Effective overburden pressure at the test level

Po

T/c Modification factors (Bowels, 1996)

T/l = Er Er - Efficiency of the hammer used (taken as 55 % ) 70

Nj 0- Adjusted N using the subscript for the standard energy ratio

The estimated Nf0 together with particle size could be used to estimate the soil strength

parameters at respective depths. The estimated parameters are drained parameters for sand

and undrained parameters for clay. Conservatively the cohesion of sand arid friction angle

of clay is assumed as 0 as the above method as well as most of the other methods have been

developed either for the estimation of friction angle in sandy soil or cohesion in clayey

soil.For the soils with SPT greater than 50 (hammer rebounding soils), the field SPT N was

assumed as 50. The estimated shear strength parameters for the soil at borehole BH 22 is

given in the Ta"Qle 1.

6

I

Table 1: Soil strength parameters with depth for borehole BH 22

Soil e Field Cl DI Cu <l>u Fine clayey sand with shell 34 0 38

Fine to medium sand with shell 31 0 38

Clayey silty sand 38 0 41

Silty loose sand 34 0 38

Fine to medium loose sand 39 0 38

Clayey sand with shell 7 0 30

Fine clayey sand with shell 1 0 26

Fine clayey sand with sandstone 45 0 38

Fine to medium clayey sand with sandstone 41 0 37

Fine to medium clayey sand with sandstone 14 0 31

Hard sandstone particles 20 0 34

Fine clayey sand with sandstone 50 0 38

Fine to medium clayey sand 50 0 37

Fine to medium clayey sand 50 0 36

Fine to medium clayey sand 50 0 36

Silty dense sand with sandstone 50 0 36

Fine to clayey sand 50 0 35

Fine to medium clayey sand with limestone 43 0 34

Silty clayey sand 50 0 36

Fine to medium clayey sand with sandstone 50 0 35

Fine to medium clayey sand with hard sandstone 50 0 35

From the results of the borehole investigations at borehole location BH 22, five major soil

layers could be identified depending on the particle size distribution and SPT values as

shown in Figure 1. The different sublayer thicknesses and properties for the borehole BH 22

are given in Table 2. The elastic modulus and the Poisson's ratio were from the local field

experience and using empirical correlations given in Bowels (2002) based on SPT values.

Furthermore, soil strength parameters for each layer depending on the local experience and

SPT values are r-ecommended for a conservative design in Table 2.

Layer 1 - Fine to medium sand with shell

Layer 2 - Clayey sand with shell

Layer 3 - Fine to medium clayey sand with sandstone

Layer 4 - Fine to medium clayey sand

Layer 5 - Fine to medium clayey sand with limestone

7

I

Pir.e to medium sand

with shell

Clayey sand with shell

Fine to medium clayey sand with sandstone

Fine to medium clayey sand

Fine clayey 1 •

to medium sand with

Depth (m)

0.00 m

8.7m

11.7m

17.7 m

26.7 m

31.95 m

SPTN Avg = 35

Y sat= 19kN / m3

SPTNAvg = 4 Ysat= 19kN/m3

SPT N Avg= 30 Y sat= 21kN / m3

SPTN Avg=50 Y sat= 20kN / m3

SPT N Avg = 48 Ysat= 19 kN/m3

Figure 1: Subsurface soil profile for BH 22

Table 2: Thickness of the sublayers and properties for BH 22

Calculated Recomrn Elastic

Depth Field ended . odul

Soil type N (m)

us

Avg Cl cpl Cu <Du Cl ¢ / (k I m2)

Fine to medium 35 0 38 0 35 25000 s~nd with shell

Clayey sand 4 0 28 0 26 9500 with shell

Fine to medium 30 0 35 0 32 22500 clayey sand

with sandstone

Fine to medium 50 0 36 0 35 32500 clayey sand

Fine to medium 48 0 35 0 35 31500 clayey sand

with limestone

8

Po·

s ra ·o

0.3

0.35

0.3

0.3

0.3

6.2Foundation Recommendations I

Due to the lateral forces and pull-out forces on the foundation due to wind forces acting on

the. blades and the tower of the windmill, when designing a foundation significant attribute

should be given to the resistance against lateral forces. Therefore, shallow foundations are

not suitable under these conditions. Hence, bored and cast in-situ piles may be used to

support the structure. ACCESS Engineering PLC further informed that the pile construction

would be cast in-situ bored piles.

6.2.1 Deep Foundations

6. 2.1.1 Estimation of static pile capacity

The general expression to determine the ultimate load capacity of a single pile in

compressionPu, canbe given according to the equation given below (Poulos& Davis, 1980).

Pu = P su + Pbu - W

Psu - ultimate shaft resistance Pbu - ultimate base resistance W -weight of the pile

where,

C -pile perimeter Ca - adhesion <Jv- vertical stress Ks- coefficient of lateral earth pressure 4>a- angle of friction between soil and pile L -length of pile shaft

Ab- area of pile base c- cohesion of soil <Jvb-vertical stress at the level of pile base y-unit weight d-pile diameter N0 Nq and Ny- bearing capacity factors

The allowable pile capacity can be obtained from the following relationship:

Ps Pbu p =~+

a SFs SFb

9

where, I

SF- safety factor commonly ranging from 2-4 or more depending on the uncertainty

The recommended design parameters (ultimate skin friction coefficient, fu and net allowable

bearing capacity, qa11) for the piles near the borehole BH 22 are presented in Table 3.The piles

shall be terminated in a strong soil layer considering the applied loads. In calculating the

skin friction in sandy soils, the overburden reduction closer to the pile due to soil arching

was considered beyond a critical depth. The calculation of the critical depth was done

considering a depth of 15B wherea pile having a diameter (B) of 0.8 m was considered in this

regard. No safety factors were considered in providing the ultimate skin friction coefficient

(f u) in Table 3. A safety factor of 1.5 for the ultimate shaft resistance is recommended. A

safety factor of 3 has been utilized in calculating the allowable base resistance from the

ultimate base resistance.

Table 3: Design parameters for piles around BH 22

Depth Field N Cast-in-situ bored iles

(m) Soil type

Avg fu (kN/m2) qa11

kN/m2

Fine to medium sand with shell 35 12

Clayey sand with shell 4 26

Fine to medium clayey sand with 30 35 sandstone

Fine to medium clayey sand 50 36 1 00

Fine to medium clayey sand with 48 36 1600 limestone

6. 2.1.2. Estimation of settlements in deep foundations

The elastic settlement of deep foundations due to the load at the tip of the pile can be

determined based on the elastic theory. The settlement at the top of an incompressible pile in

half space pile can be expressed to a sufficient accuracy using the equation below according

to Poulos & Davis (1980).

PI p=-

Esd

where,

10

I= IoRkRhRv(floating piles) I

I = IoRkRbRv (end bearing piles) p - settlement of the pile head

P - axial load Io -settlement influence factor for vs=0.5 Rk - correction factor for pile compressibility Rh -correction factor for finite depth of layer on a rigid base Rb- correction factor for stiffness of bearing stratum Rv - correction factor for Poisson's ratio Vs

7.0 RECOMMENDATIONS

Due to the lateral forces and pull-out forces on the foundation due to wind forces acting on

the blades and the tower of the windmill, when designing a foundation, a significant

attribute should be given to the resistance against lateral forces. Therefore, shallow

foundations are not suitable under these conditions. Hence, bored and cast in-situ piles may

be used to support the structure.

During the site investigation, there was some evidence of presence of limestone fragments in

the sandy soil. However, at the depth of hammer bounce with more than SPT N 50 for three

consecutive layers, the site investigation process was terminated. At that level, there was no

such continuous presence of limestone layers with problematic cavities. In such case, design

and construction of foundations in limestone areas can possess various problems such as

subsidence and sinkholes.

Since there was no indication of very loose sandy soils and no presence of soft clay la ers in

the site, the potential for negative skin friction would be minimal.

Due to the huge bending moments and lateral forcesfrom the wind, when desi<:> g e

foundation,tensile forces and lateral forces on piles should also be taken into considera ·a

Pile testing is recommended and depending on the results recommended values ma be

revised.

Prepared by,

THE INSTITUTION OF ENGINEERS, SRI LANKA • .. , ... , ..

. 1•11•111•. ~~--~,., ri~IV l!:ti

Eng. (Dr) U P NAWAGAMUWA ••r."laa lllUWa&

I E'S L CHARTERED ENGINEER MEM BERSHIP No F _ 1036

THIS SEAL WILL BE VALID ON LY If THE HOLDER 'S NAME IS ON THE ROLL OF MEMBE RS

-Dr. U. P. Nawagamuwa BScEng.Hons(Moratuwa), MEng (AIT), DrEng(YNU), CEng, FIE(SL)

11

I

APPENDIX A

I

APPENDIX B

UNIVERSITY OF MORATUWA Depa1tment of Civil Engineering Moratuwa, Sri Lanka

Tel: J Head of Department - 2645422

L General - 2650567, 2650568

Fax : 2651216

Date of testing: 02°d May 2019

Type of testing: Gradation Test (mechanical sieve analysis) Client: ACCESS Engineering PLC

Description: Sample provided - BH22 ( 4.50-4 .95m)

Project: IOOMW Semi Dispatchable Wind Farm in Mannar Island Project

Address : Access Towers, Level 11 , 278, Union Place, Colombo 02

Sieve Size (mm) Percentage Passing (%)

25 100.0

19 100.0

12.7 100.0

10 100.0

5 100.0

3.35 100.0

2.360 99.3

1.1 80 98.7

0.600 95.9

0.300 90.6

0.150 19.6

0.075 2.2

BH22- 4.50-4.95m

100.0

90.0

80.0 .... QI 70.0 c i:i: 60.0 QI Ill)

50.0 111 ... c

40.0 QI u ....

30.0 QI a.

20.0

10.0

0.0

I I~ I! I ! i /!"" ! !

' ~ I' 11 ~ i : ---+:' ii / ! i I

i I i I

I I I

I I I i I I Ii I I I

I I I Ii I I !

' I ! : Ii I

I W--I

I I I I

11 I i I - I I I ·-----I

I!! J I

i I

! 1

1, / I I

i '

I I

~~ I j I I

i

Specific Gravity of Soil solids - 2.60 Natural Moisture Content - 25.9%

Prepared by,

Dr (Eng). U.P. Nawagamuwa BScEng.Hons(Moratuwa), MEng(Al1) , DrEng(YNU), CEng, FIE(SL)

Senior Lecturer/Chartered Engineer (Civil)

I I

i

' i

1 I t

I

I'

I I I

I 11' I

I' I I ,

03rd May 2019

UNIVERSITY OF MORATUWA Depa~tment of Civil Engineering Moratuwa, Sri Lanka

Tel: J Head of Department - 2645422

l General - 2650567, 2650568

Fax : 2651216

Date of testing: 02nct May 2019

Type of testing: Gradation Test (mechanical sieve analysis)

Client: ACCESS Engineering PLC Description: Sample provided - BH22 (28.50-28.95m)

Project: 1 OOMW Semi Dispatchable Wind Farm in Mannar Island Project Address: Access Towers, Level 11 , 278, Union Place, Colombo 02

Sieve Size (mm) Percentage Passing (%)

25 100.0

19 100.0

12.7 100.0

10 100.0

5 98.8

3.35 98.3

2.360 97.2

1.180 91 .9

0.600 77.0

0.300 51.3

0.150 7.6

0.075 1.1

BH22- 28.50-28.95m

100.0

90.0

80.0 ... CIJ 70.0 c i! 60.0 Cll tlO

50.0 C'G ... c

40.0 Cl) u ...

30.0 CIJ a.

20.0

10.0

0.0

I • J 1

, 11 ' ' i I I I ' \ lj ~ i

: ! I i I '1i I

i i I

1--f l: : I I ; .

! . ! ii ! /1

11

1 !

i ' I

: ' ___ 1 ! , I I ' I !

' -·--·-- ' I , i ! f : 11, il I 11

'I --

/ I ! ii I

I I 1! ---+ I .

I i ! I I i : i I I i ' I i

! I I I ! 1 ·

!

l I i

: l J../ ' ill ! ' '

. . I I I

I'' I

I I i I I

I i I I I' I I

I Ii i I

i I I I : I

03rd May 2019

0 .01 0 .1 1 10 100

Particle Size (mm)

Specific Gravity of Soil solids - 2.60 Natural Moisture Content - 24.8%

Prepared by,

Dr (Eng). U.P. Nawagamuwa BScEng.Hons(Moratuwa), MEng(AIJ) , DrEng(YNU), CEng, FIE(SL) Senior Lecturer/Chartered Engineer (Civil) ·

UNIVERSITY OF MORATUWA :pepartment of Civil Engineering Moratuwa, Sri Lanka

Tel : JHead of Department - 2645422

L General - 2650567, 2650568

Fax : 2651216

Date of testing: 02°d May 2019

Type of testing: Gradation Test (mechanical sieve analysis)

Client: ACCESS Engineering PLC

Description: Sample provided - BH22 (22.50-22.95m)

Project: lOOMW Semi Dispatchable Wind Farm in Mannar Island Project

Address: Access Towers, Level 11, 278, Union Place, Colombo 02

Sieve Size (mm) Percentage Passing (%)

25 100.0

19 100.0

12. 7 100.0

10 100.0

5 100.0

3.35 99.1

2.360 97. 5

1.180 91.4

0.600 73. 1

0.300 32.8

0. 150 12.4

0.075 3. 0

03rd May 2019

·- ---- --~-------------- ---- ---·

BH22- 22.50-22.95m

100.0

90.0

80.0 ... QI 70.0 c ~ 60.0 GI llO

50.0 IV ... c

40.0 QI u ...

30.0 QI 0..

20.0

10.0

0.0

! ' 'I ~ I l l in ' 'I i ! '

, I l I i 11 ' I ' ' / i i ! '

I i '

. ' ;

' '

ii I : I J

' i l i i I 1 Ii ' .

' ' I/ I !f l 'I

I / I I''

' I i 1[ i

I .,.. ~ I I

I I

·-

0.01 0.1 1

Particle Size (mm}

Specific Gravity of Soil solids - 2.50 Natural Moisture Content -15.3%

Prepared by,

Dr (Eng). U .P. Nawagamuwa BScEng.Hons(Moratuwa), MEng(A11), DrEng(YNU), CEng, FIE(SL)

Senior Lecturer/Chartered Engineer (Civii)

. I

' '

i : I ! I I I! I '

11 ' I ' I

I

I I i

i

··'--1-- H-

10 100

UNIVERSITY OF MORATUWA pepartment of Civil Engineering Moratuwa, Sri Lanka

Tel: JHead of Department - 2645422

l General - 2650567, 2650568

Fax : 2651216

Date of testing: 02nd May 2019

Type of testing: Gradation Test (mechanical sieve analysis)

Client: ACCESS Engineering PLC

Description: Sample provided - BH22 (15.00-15.45m)

Project: 1 OOMW Semi Dispatchable Wind Farm in Mannar Island Project

Address: Access Towers, Level 11, 278, Union Place, Colombo 02

Sieve Size (mm) Percentage Passing (%)

25 100.0

19 100.0

12.7 100.0

10 96.1

5 88.3

3.35 79.7

2.360 69.4

1.180 53.9

0.600 46.1

0.300 30.8

0.150 10.1

0.075 2.3

BH22- 15.00-15.45m

100.0

90.0

80.0 ... GI 70.0 c:

i:i: 60.0 GI

llO 50.0 J!

c: 40.0 GI

u ... 30.0 GI

Q.

20.0

10.0

0.0

. i '

!

I I I j i f'"

t--- --- i .... ---------, I l ! i I y i

I 1 I I I / i i

I 11 I I

I I )( i I i i

I 11 i I i 11 1 / i I ! i

I I! j.f 1 I I I !

I i I / I ! l ' ' I I I/ I

! !

I I ./ i i I !

'--·---- i ,.j. v i i I i

. I

I

I I

! J_ ..... -~

03rd May 2019

0.01 0.1 1 10 100 I

____ - --------- P - art _ i~ cl ~ e - S - iz _ e _ (m _ m _ ) ______ _J Specific Gravity of Soil solids - 2.59 Natural Moisture Content -13.2%

Prepared by,

Dr (Eng). U.P. Nawagamuwa BScEng.Hons(Moratuwa), MEng(Al1) , DrEng(YNU), CEng, FIE(SL)

Senior Lecturer/Chartered Engineer (Civil)

UNIVERSITY OF MORATUWA

1 Department of Civil Engineering Moratuwa, Sri Lanka

Tel : jHead of Department - 2645422

l General - 2650567, 2650568

Fax : 2651216

Date of testing: 02"d May 2019

Type of testing: Gradation Test (mechanical sieve analysis) Client: ACCESS Engineering PLC

Description: Sample provided- BH22 (10.50-10.95m)

Project: lOOMW Semi Dispatchable Wind Farm in Mannar Island Project Address: Access Towers, Level 11 , 278, Union Place, Colombo 02

Sieve Size (mm) Percentage Passing (%)

25 100.0

19 100.0

12.7 100.0

10 100.0

5 100.0

3.35 100.0

2.360 100.0

1.180 94. 8

0.600 65.9

0.300 29.7

0. 150 3.7

0.075 0.1

BH22- 10.S0-10.9Sm

100.0

90.0

80.0 .... QI 70.0 c:

Li: 60.0 ell bO

50.0 C'G ... c:

40.0 QI .... .... 30.0 ell

Cl.

20.0

10.0

0 .0

~ ~ ~

I i 11 i i 'i I ii !..'" i

I, I I I 1-····· ' : I' I 'ii

I

I Ii! ' / ! ;

I I l ! ! j ! ' I i I I I I i I ii I

' I ; I

L. I i I l' I i i ! I

I I I ; i

i ' ! I i l 1-··-··-· !

-·-·-

' I J/ I: I [ ! ' I I r------: I I l ii! I I ; ' .

i I! r I ' i I! I I '

, i I u ~ I : I I I

~ ~

!

! I

I j

--.--

u I

·-'-

i

H-.. IJ.

03rd May 2019

0.01 0.1 1 10 100

Particle Size (mm)

-···------···---·---·····-- ··-- -··--·- ~--- --- -- ---------------_]

Specific Gravity of Soil solids - 2.64 Natural Moisture Content - 24.0%

Prepared by,

Dr (Eng). U.P. Nawagamuwa BScEng.Hons(Moratuwa), MEng(A11), DrEng(YNU), CEng, FIE(SL)

Senior Lecturer/Chartered Engineer (Civil)

UNIVERSITY OF MORATUWA ,Department of Civil Engineering Moratuwa, Sri Lanka

Date of testing: 02nct May 2019 Type of testing: Natural Moisture Content

Client: ACCESS Engineering PLC

Description: Sample provided - BH22

Tel : ]Head of Department - 2645422

l General - 2650567, 2650568

Fax : 2651216

Project: lOOMW Semi Dispatchable Wind Farm in Mannar Island Project

Address: Access Towers, Level 11 , 278, Union Place, Colombo 02

Depth Natural

Moisture

content{%)

4.50-4.95m 25.9

10.50-10.95m 24.0

15.00-15.45m 13.2

22.50-22.95m 15.3

28.50-28.9Sm 24.8

Prepared by,

Dr (Eng). U.P. Nawagamuwa BScEng.Hons(Moratuwa) , MEng(Al1), DrEng(YNU), CEng, FIE(SL) Senior Lecturer/Chartered Engineer (Civil)

03rct May 2019

UNIVERSITY OF MORATUWA

1 Department of Civil Engineering Moratuwa, Sri Lanka

Date of testing: 02nd May 2019

Type of testing: Specific Gravity

Client: ACCESS Engineering PLC Description: Sample provided - BH22

Tel : JHead of Department - 2645422

l General - 2650567, 2650568

Fax : 2651216

Project: I OOMW Semi Dispatchable Wind Farm in Mannar Island Project

Address: Access Towers, Level 11 , 278, Union Place, Colombo 02

Depth Specific Gravity

4.50-4.95m 2.60

10.50-10.95m 2.64

15.00-15.45m 2.59

22.50-22.95m 2.50

28.50-28.95m 2.60

Prepared by,

Dr (Eng). U.P. Nawagamuwa BScEng.Hons(Moratuwa) , MEng(A17), DrEng(YNU), CEng, FIE(SL)

Senior Lecturer/Chartered Engineer (Civil)

Ambient Air Quality Monitoring Report - Wind Farm

Noise Level Monitoring Report - Wind Farm

Vibration Level Monitoring Report - Wind Farm

Water Quality Monitoring Report - Wind Farm

Environmental Safeguard Monitoring Report

ADB Loan 3483/3484 SRI

Reporting Period Date

{From July 01,2019 to September 30, 2019} {November 15,2019}

Green Power Development and Energy Efficiency Improvement Investment

Programme (Tranche 2)

Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line

Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid

Substation

Prepared by the Ceylon Electricity Board for the Asian Development Bank

Annex 3.2 : Monitoring Reports and other data- Transmission Line and Grid SubstationEnvironmental Safeguard Monitoring Report - Transmission Line and Grid Substation

GPDEEIIP Tr 2 P1&P2 P a g e | 1

TABLE OF CONTENTS

Page

Abbreviations 2 Executive Summary

• Brief status of environmental compliance during the coverage period 3 1.0 Introduction 3

2.0 Compliance to National Regulations 7 3.0 Compliance to Environmental Covenants from the ADB Loan Agreement 8 4.0 Compliance to Environmental Management Plan 8 5.0 Safeguards Monitoring Results and Unanticipated Impacts 25 6.0 Implementation of Grievance Redress Mechanism and Complaints Received from

Stakeholders 28 7.0 Conclusion and Recommendations 28

GPDEEIIP Tr 2 P1&P2 P a g e | 2

Abbreviations

ADB – Asian Development BankCCD – Coast Conservation DepartmentCEA – Central Environment Authority, Government of Sri LankaCEB – Ceylon Electricity BoardDC or D/C – Double CircuitDPR – Detailed Project ReportDSD – Divisional Secretariat DivisionsEA – Executing AgencyEARF – Environmental Assessment and Review FrameworkEIA – Environmental Impact AssessmentEMoP – Environmental Monitoring PlanEMP – Environmental Management PlanEHV – Extra High VoltageGHG – Green House GasGND – Gram Niladhari DivisionsGoSL – Government of Sri LankaGRC – Grievance Redress CommitteeGRM – Grievance Redress MechanismIA – Implementing AgencyIEE – Initial Environmental ExaminationLILO – Line – in- Line- outMFF – Multi-tranche Financing FacilityMOPE – Ministry of Power and Energy. Government of Sri LankaPAA – Project Approving AuthorityPCB – Poly Chlorinated BiphenylPMU – Project Management UnitREA – Rapid Environment AssessmentROW – Right of WayRP – Resettlement PlanSC or S/C – Single CircuitSF6 – Sulphur HexafluorideSPS GPD&EEIIP1-2

– –

Safeguard Policy StatementGreen Power Development & Energy Efficiency ImprovementInvestment Programme (Tranche 1) Part 2

WEIGHTS AND MEASURES

ha (hectare) – Unit of area

km (kilometer) – 1,000 meters

kV – kilovolt (1,000 volts)

kW – kilowatt (1,000 watts)

MW – Mega Watt

NOTE{S}

In this report, "$" refers to US Dollars.

“LKR” refers to Sri Lankan Rupees

GPDEEIIP Tr 2 P1&P2 P a g e | 3

EXECUTIVE SUMMARY

In the efforts to harness renewable energy in the country, wind has been identified as a source of significant

potential to generate electricity. Studies carried out by both local and international experts envisaged that 375

MW of wind capacity with 35~45% plant factor could easily be developed in the Mannar island. Accordingly,

CEB has planned to set up a 220/33kV GSS at Nadukuda in the Mannar island and a 220kV transmission line

from Nadukuda to Mannar in order to evacuate the wind power generation in the Mannar island under the

Green Power Development and Energy Efficiency Improvement Program (Tranche II) which will be funded by

ADB.

Under this project component, it is proposed; (1) to construct 220/33kV Grid Substation (GSS) at Nadukuda in

Mannar island and the augmentation of Mannar GSS. This GSS will able to absorb entire 375 MW of wind power

at this stage only 2 X 63MVA capacity transformers will be installed with the provision to install further 4 X

63MVA transformers in the future. (2) to construct a 30km of 220kV transmission line from Nadukuda GSS to

the Mannar GSS. The Nadukuda GSS will interconnect the clusters of wind plants at 33kV level and transmit the

power & energy to Mannar Grid Substation via the 30km long 220kV transmission Line.

Green Power Development and Energy Efficiency Improvement Investment Program (Tranche II) has been

launched with a focus to develop transmission and distribution projects for evacuation of renewable energy

(wind) parks/ projects and overall improvement of energy efficiency and capacity development.

Green Power Development and Energy Efficiency Improvement Investment Program is

intended to finance a series of investments in Sri Lanka. It includes generation capacity enhancement,

transmission capacity addition and distribution system strengthening installation energy efficiency measures.

The Investment Program will also finance a number of “softer” activities, including operational capacity

building and implementation supervision. The objective of the investment is to achieve increased adequacy

and efficiency of power system, including renewable energy in Sri Lanka.

1.0 Introduction

1.1 Brief Project Description

The Green Power Development & Energy Efficiency Improvement Investment Programme (Tranche 2)

Package 1 & 2 Transmission Infrastructure Capacity Enhancement Project, consists of following Lots

with the estimated costs:

Package Lot Project Total

(MUSD)

1 Lot A Hambantota Grid Substation 220kV development 15.5

Lot B New Polpitiya-Hambantota 220kV, 150km transmission line 57.3

GPDEEIIP Tr 2 P1&P2 P a g e | 4

The contract details including the contract price of the following two lots under Package 2 are as follows.

Package 2: Lot B1 Package 2: Lot A

Scope Construction of Mannar – Nadukuda

220kV Transmission Line

Construction of Nadukuda 220/33 kV Grid

Substation & Augmentation at Mannar

220/33kV Grid Substation.

Contractor KEC International Limited Siemens Limited, India.

Contract Price

including change

orders

Contract Amount

LKR 426,309,080.00 +USD 6,477,201.00

Change Order 01

LKR 8,240,000.00 +USD 88,638.00

Contract Amount

LKR 932,903,081.57 + USD 11,901,167.32

Change Order 01

LKR 5,660,000.00 + USD 476,988.00

Contract Effective

Date October 04, 2017 March 16, 2018

Expected Completion

Date

January 23, 2020

{an extension of time has been granted

as per the Change Order No 01}

March 16, 2020

1.2 Project Progress Status and Implementation Schedule

A. Progress Status of the Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission

Line

The updated status of environment activities during the period of October 2018 to December 2018

is given below for the Transmission Line.

Description Status

2B1

Mannar - Nadukuda 220kV, 30km

transmission line

1. Profile & Tower designs were completed.

2. 90% of Equipment Procurement is completed

3. 56 Erection of towers were completed

4. 74 foundations were completed

Site Photos of Construction of Mannar – Nadukuda 220kV Transmission Line

GPDEEIIP Tr 2 P1&P2 P a g e | 5

Note: Completion of foundation in most of the locations acquired more time than estimated due

to heavy rainfall in the northern region. Hence the work progress is slightly low during this

quarter.

Construction in vankalai bird sanctuary

The work has been started in the Vankalai from Febreuary 2019 onwards. The Progress was slow and

Contractor unsuccessful to finnish the all construction activities due to collapsible soil, more time taken

to manual excavation process ( removal of existing foundation at N1 & O0 locations taken additional

time) and delay in obtaining the transport facilities from Sri Lanka Railways as schedule to transfort the

Materials inside the Vankalai. All construction activities are under strict supervission of CEB as per the

BMP.

GPDEEIIP Tr 2 P1&P2 P a g e | 6

B. Progress Status of Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation &

Augmentation at Mannar 220/33kV Grid Substation

The updated status of environment activities during the period of October 2018 to December 2018

is given below for the Grid Substation.

Description Status

2A

Construction of Nadukuda 220/33 kV

Grid Substation & Augmentation at

Mannar 220/33kV Grid Substation

1. Designs works were completed up to 70% .

2. Equipment Procurement are in progress

3 Engineers accommodation & Control room building works are

in progress

4. Transformer foundation works are in progress

Site Photos of Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar

220/33kV Grid Substation

Note: The detailed Implementation Schedule for both lots are attached as Annex- I.

GPDEEIIP Tr 2 P1&P2 P a g e | 7

2.0 Compliance to National Regulations

The relevant Acts and Legislations to the project is given in the Table No. 2.0 Table No. 2.0: Applicable Acts and Legislations to the Project

Act/Rule/Notification Year Objective Compliance

Schedule Agrarian Services Act (Nº 58 of 1979)

Agrarian Development Act Nº 46 of 2000 1979 &

2000 To provide secure background to

farmers and their agricultural premises

Being complied.

Electricity Act 2009 2009 To provide reliable and affordable

electrical energy Being complied.

Fauna and Flora Protection (Amendment) Act

1993 (Nº 49 of 1993) 1993 To provide greatest protection to fauna

and flora Being complied.

Felling of Trees (Amendment Act Nº 01 of

2000 and Act to Amend felling oanuaryf trees

control)

2000 The control removal of trees. Trees have been

removed in the

GSS area.

Act/Rule/Notification Year Objective Compliance

Schedule

Fisheries and Aquatic Resources Act 1996 1996 To provide for the management,

regulation, conservation and

development of fisheries and aquatic

resources in the main land.

Being complied.

Flood Act Nº 22 of 1955 1955 Protection of areas subject to flood Being complied.

Forest Ordinance Act Nº 13 of 1966

Forest (Amendment) Act Nº 65 of 2009 1966 &

2009 Conservation, protection and

management of forest and forest

resources for control of felling and

transport of timber.

Being complied.

Irrigation Clauses Act 1973 1973 To provide regulations for the

construction of structures across the

irrigation canals and water resources.

Being complied.

Land Acquisition (Amendment) Act, Nº 13 of

1986 1986 Establishes the procedure to be

followed by the competent authorities

for the acquisition of land for public

purpose.

Being complied.

Monuments and Archaeological Sites and

remains Act, 1958. Act Nº24 of 1958.

Antiques Ordinance, 1960

1958

&1960 An Act to provide for the preservation of

ancient and historical monuments and

archaeological sites and remains of

national importance.

Being complied.

Motor Traffic Act Nº 60 of 1979 1979 To provide sustainable approach for

vehicle traffic. Being complied.

National Environmental Act Nº 47 of 1980,

amendment Nº 56 of 1988, and other

amendments.

1980 To provide protection, management,

enhancement of the environment with

prevention and control of pollution.

Being complied.

National Environmental (Protection &

Quality) Regulations, No 01 1990. 1990 To provide for the prevention and

control of water pollution and

enhancing the quality of water.

Being complied.

National Environmental (Ambient Air Quality)

Regulations, 1994. 1994. To provide for the prevention and

control of air pollution. Being complied.

National Environmental (Noise Control)

Regulations Nº1 1996. 1996. To provide maximum allowable noise

levels. Being complied.

National Involuntary Resettlement Policy. Land Acquisition Act does not deal with

the broader social and economic

impacts of the project. Thus, this policy

was established to overcome these

impacts.

Being complied.

GPDEEIIP Tr 2 P1&P2 P a g e | 8

3.0 Compliance to Environmental Covenants from ADB Loan Agreement

The applicable Environmental Covenants from the ADB Loan Agreement

Public Utilities Commission of Sri Lanka Act ,

Nº 35 of 2002. 2002 To create an environment for all

inhabitants of Sri Lanka and the

contributors to its development, to have

access to essential infrastructure and

utility services in the most economical

manner within the boundaries of the

sustainable development agenda.

Being complied.

Soil Conservation (Amendment) Act Nº 24 of

1996. 1996 Act for conservation of soil resources

and productive capacity of land. Being complied.

Product Description Remarks/Issues

ADB Loan

3483/3484 SRI

The Borrower shall ensure that the

preparation, design, construction,

implementation, operation and

decommissioning of the Project and all

Project facilities

comply with (a) all applicable laws and

regulations of the Guarantor relating to

environment,

health, and safety; (b) the Environmental

Safeguards; (c) the EARF; and (d) all measures

and requirements set for the in the

respective IEE or EIA, EMP and BMP, and any

corrective or

preventative actions set forth in a Safeguards

Monitoring Report.

CEB is taking every effort to

comply ADB requirement

while NOT effecting the

completion of the Project.

4.0 Compliance to Environmental Management Plan

The Environmental Management Plan (EMP) has been prepared for the sub-project that

discusses the anticipated impacts, monitoring requirements, and development of mitigation

measures with respect to the following stages: (i) pre-construction, (ii) construction, and (iii)

operation and maintenance. Detailed, site-specific mitigation measures and monitoring plans

were developed and are being implemented during the project implementation phase.

GPDEEIIP Tr 2 P1&P2 P a g e | 9

GPD&EEIIP1-2 P a g e | 11

Monitoring of the implementation of Environmental mitigation measures – Transmission Line and the Grid Sub-Stations

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

Pre-construction

Temporary use

of lands

Impact to the

existing

environment

Selection of lands adhering to

local laws and regulations and

in close consultation with LAs

Construction facilities should

be placed at least 100 m away

from water bodies, natural flow

paths, important ecological

habitats and residential areas.

No temporary land use in

Vankalai Sanctuary.

Water and air

quality

Air quality

Standards and CEA

water quality

standards

CEB

Contractor

Detailed design

summary of Ambient air quality, water

quality reports enclosed

Substation

location and

design

Noise generation

Exposure to noise,

Nuisance to

neighboring

properties

Disturbance to the

adjacent lands and

the people due to

cut and fill

operations

Substation designed to ensure

noise will not be a nuisance

(i.e. less than 55dBA LAeq

daytime and less than 45dBA

LAeq nighttime at nearest

receptor).

Maintain adequate clearance,

construction of retaining

structures, minimize cut and fill

operations adjoining to the

dwellings

Expected noise

emissions based on

substation design,

noise levels

Proximity to houses

and other structures

Noise control

regulations in 1994

Noise levels to be

specified in tender

documents

Technical

specification

CEB

Detailed Design

summary of existing noise level reports

enclosed

Location of

transmission

towers and

transmission line

alignment and

design

Line traversing

across

environmentally

sensitive areas with

possible impacts to

biodiversity and

excessive clearance

of vegetation

Excessive

requirements for

Setback of dwellings to

transmission line route

designed in accordance with

permitted level of power

frequency and the regulation of

supervision at sites.

Tower location and

line alignment

selection with

respect to nearest

dwellings

Setback distances

to nearest houses -

CEB

Part of tower

sighting survey and

detailed alignment

survey and design

The transmission line has been routed

through areas with low-grown

vegetation and agriculture, such as

paddy and low grown vegetables

A detailed design including tower type,

location, profile already been submitted.

Trees have been removed and

compensation has been paid for the

identified owners.

GPD&EEIIP1-2 P a g e | 12

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

clearance of way-

leaves and land use

restrictions in areas

of high population

density

Exposure to safety

related risks

Impact on water

bodies (Vankalai

sanctuary

wetland)/land/

residences

Consideration of tower location

where they could be located to

avoid avian breeding areas,

water bodies or agricultural

land as much as possible.

Follow EHS Guidelines on

avoiding water pollution.

Careful site selection to avoid

existing avian/marine

settlements and negative

impacts to sanctuary area.

Increase the height of towers,

adopt measures to reduce

possible collision with birds

during flight.

EPC contractor to implement

mitigation measures according

to Biodiversity Management

Plan and Construction Method

statement outlining

construction precautions in the

Vankalai Sanctuary area.

Site location, line

alignment selection

(distance to

dwelling, water

and/or agricultural

land)

Improve tower

design and

measures

Consultation with

local authorities

Biodiversity

Management Plan,

Dept of Wildlife

Conservation

CEB

Part of detailed

project sighting

and survey and

design

complied

Equipment

specifications

and design

parameters

Release of

chemicals and

harmful gases in

receptors (air,

water, land)

Ensure equipment design must

be sound to avoid emissions for

oil, gases etc.

Compliance with

setback distances

(as-built” diagrams)

Setback distances

to nearest houses

CEB

Detailed design

No significant amounts of emissions

(release of chemicals and harmful gases)

are envisaged.

Poly Chlorinated Biphenyls (PCBs) will

not be used in substation transformers

GPD&EEIIP1-2 P a g e | 13

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

or any other equipment. Exclusion of

PCBs in transformers stated in tender

specifications.

Encroachment

into precious

ecological areas

Loss of precious

ecological values/

damage to precious

species

Minimize the need for tower

base disturbance in sanctuary

wherever possible

Floral and faunal

habitats loss in

sanctuary area

Flora and fauna

protection act.

Biodiversity

Management Plan

CEB

Detailed design

complied

Interference

with drainage

patterns/water

channels

Temporally flooding

hazards/loss of

agricultural

production

Appropriate siting of towers

(use longer spans) to avoid

putting towers in water

channel to avoid disturbing

aquatic habitats in sanctuary

area.

Site location and

line alignment

selection

Irrigation Act 1933.

Consultation with

local authorities

and design

engineers

CEB

Detailed alignment

survey and design

The contractor has selected tower

locations in consultation with the CEB

and other authorities. No loss of

agricultural land and disturbances to

aquatic habitats have been observed.

Explosions/Fire Hazards to life Design of substations to include

modern fire control

systems/firewalls.

Provision of firefighting

equipment to be located close

to transformers, power

generation equipment.

Substation design

compliance with fire

prevention and

control codes

Tender document

to mention detailed

specifications

CEB

Part of detailed

substation layout

and design

/drawings

Provision of firefighting equipment has

been planned. This has to be verified

prior to commissioning.

Construction

Removal or

disturbance to

other public

utilities

Public

inconvenience

Advance notice to the public

about the time and the

duration of the utility

disruption.

Use of well trained and

experienced machinery

operators to reduce accidental

damage to the public utilities

and specifically any natural

habitats in Vankalai Sanctuary.

Restore the utilities

immediately to overcome

public inconvenient

Disruption of other

commercial and

public activities /

Public complaints

Technical

specification

CEB/ PRDA /

NWSDB/SLT

Throughout the

construction

period

No public utilities have been disturbed

as yet.

He contractor has employed well trained

and experienced machinery operators.

Natural habitats in Vankalai Sanctuary

have not been permanently damaged.

GPD&EEIIP1-2 P a g e | 14

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

Temporary

outage of the

electricity

Loss of power

supply to the local

community when

distribution lines

crossing the new

transmission line

are switched off

Advance notice to the public

about the time and the

duration of the utility

disruption

Restore the utilities

immediately to overcome

public inconvenience.

Houses and

commercial

premises of power

disruption

Regular monitoring

during the period of

strengthening the

conductors

Contractor CEB

Throughout the

construction

period

Temporary outages of electricity

monitored, during stringing & Erection.

Acquisition of

paddy fields and

other lands

Loss of agricultural

productivity

Avoid farming and bird’s migration/breeding season

wherever possible for the

project activities.

Ensure existing irrigation

facilities are maintained in

working condition

Protect /preserve topsoil and

reinstate after construction

completed Repair /reinstate

damaged areas etc. after

construction completed

Compensation for temporary

loss in agricultural production

Land area of

agriculture loss

Usage of existing

Utilities

Status of facilities

(earthwork in m3)

Implementation of

crop compensation

(amount paid,

dates, etc.)

Agrarian Service

Act.

Regular monitoring

compliance

with regulations

CEB, Contractor

through contract

provisions

Throughout the

construction

period

No acquisition of lands required for

tower foundation or line; Construction

of transmission towers is in progress,

and most of the tower erection have

been completed. The contractor, in

consultation with the CEB, has

avoided/minimized the cultivation

seasons, and bird migratory seasons to

the extent as possible.

The contractor has been able to

satisfactorily reinstate the damaged

construction areas to the satisfaction of

all the parties concerned.

Payment of compensation for crop

damages of paddy area are in progress.

Equipment

layout and

installation

Noise and

vibrations

Selection of construction

techniques and machinery to

minimize ground disturbance

Construction

techniques and

machinery/

Minimal ground

disturbance

CEB, Contractor

through contract

provisions

Construction

period

Disturbances have been kept to a

minimum. No significant noise and

vibration impacts recorded and no

complaints.

Substation

construction

Loss of soil Fill for the substation

foundations obtained by

creating or improving local

drain system.

Borrow area

sighting (area of site

in m2 and estimated

volume in m3)

Laws and

regulations of

respective LAs

CEB, Contractor

through contract

provisions

Construction

period

Filling of the site is complete. Road-side

drains adjoining the site area and the

access road have been maintained

properly.

No local drainage problems have been

observed so far.

GPD&EEIIP1-2 P a g e | 15

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

Water pollution Construction activities involving

significant ground disturbance

(i.e. substation land forming)

not undertaken during the

monsoon season. No work in

lagoon areas during high tide

periods.

Seasonal start and

finish of major

earthworks (pH,

BOD/COD,

Suspended solids,

other)

Sri Lanka’s National Environment Act

and IFC’s EHS guidelines 2007

(under revision)

Timing of major

disturbance

activities - prior to

start of

construction

activities

Construction

period

Much of the earthwork and filling

activities are completed now, and these

works have been carried out during the

dry season.

According to the contractor, no

earthworks are planned during the

forthcoming rainy season.

No surface water bodies found within or

around the substation area.

Construction

schedules

Noise nuisance to

neighboring

properties

Construction activities only

undertaken during the day and

local communities informed of

the construction schedule.

Timing of

construction (noise

emissions, [dB (a)])

Daytime

construction only

CEB, Contractor

through contract

provisions

Construction

period

There are no dwelling units located close

to the grid station site.

Tower construction near dwelling units

(e.g., close to the Mannar Railway

Station) has now been completed

No significant noise and vibration

impacts recorded and no complaints.

Nuisance to birds if

the line

construction

crosses their

migratory path

Restrict construction work

during the known period of

migration/breeding period by

the birds. Construction period

in the sanctuary to be finalized

in keeping with the CMS. Work

inside the sanctuary must be

undertaken from 1 hour after

sunrise to 1 hour before

sunset.

Timing of

Construction

Biodiversity

Management Plan,

Construction Timing

- period of

migration of birds

CEB, Contractor

Construction

period

All construction activities are conducted

during off migratory season; February

2019 to September 2019.

Note: Contractor not finished the all

construction activities by Sept 2019 due

to collapsible soil, more time taken to

manual excavation process ( removal of

existing foundation at N1 & O0 locations

taken additional time) and delay in

obtaining the transport facilities from Sri

Lanka Railways as schedule to transfort

the Materials inside the Vankalai.

Provision of

facilities for

construction

workers

Contamination of

receptors (land,

water, air)

Construction workforce

facilities to include proper

sanitation, water supply and

waste disposal facilities at

Amenities for

Workforce facilities/

National Solid

Waste

Management Policy

and IFC’s EHS

CEB, Contractor

through contract

provisions

Construction workforce has been

provided with proper facilities to include

proper sanitation, water supply and

waste disposal facilities (for both

GPD&EEIIP1-2 P a g e | 16

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

substation site in accordance

with EHS Guidelines. No

facilities to be setup within the

Sanctuary. Solid waste and

hazardous waste to be

disposed of offsite to a suitably

licensed landfill. No waste to be

disposed of to an unlicensed

dump site. Contractor to

prepare and implement a

pollution prevention and

emergency response plan in

accordance with EHS

Guidelines.

guidelines 2007

(under revision)

Construction

period

transmission tower workers and at

substation site) in accordance with EHS

Guidelines.

No labor camps have been setup within

the Sanctuary.

Solid waste and hazardous waste is

handed over to the Pradeshiya Sabha.

Wood/

Vegetation

harvesting, cut

and fill

operations

Loss of vegetation

and deforestation

Effect on fauna

Construction workers

prohibited from harvesting

wood in the project area

Prevent work force from

disturbing to the flora, fauna

including hunting of fauna and

fishing in water bodies. No

poaching allowed in Sanctuary

or bird habitat area.

Proper awareness programme

regarding conservation of flora,

fauna including ground

vegetation to all drivers,

operators and other workers

Illegal wood/

Vegetation

harvesting (area in

m2, number of

incidents reported)

Habitat loss

Complaints by local

people or other

evidence of illegal

harvesting

Fauna and flora

protection Act.

CEB, Contractor

through contract

provisions

CEB/ DWC/ DoF

Construction

period

Strict instructions have been given to

construction workers prohibiting from

harvesting wood in the project area,

disturbing to the flora, fauna including

hunting and fishing.

Poaching in the sanctuary or bird habitat

areas has been strictly prohibited.

Monthly awareness programme for

contractor carried out on conservation

of flora, fauna including ground

vegetation

Site clearance Vegetation Marking of vegetation to be

removed prior to clearance,

and strict control on clearing

activities to ensure minimal

clearance. Minimum vegetation

Vegetation marking

and clearance

control (area in m2)

Felling of trees

(Amendment Act.

Nº 01 of 2000 and

act of felling of

trees control).

Clearance strictly

CEB, Contractor

through contract

provisions

Construction

period

Vegetation has been removed in some

sites already. The contractor has been

instructed to record any tree species

prior to clearance and to exercise strict

control on clearing activities to ensure

minimal clearance.

GPD&EEIIP1-2 P a g e | 17

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

clearance to be done in the

sanctuary area.

No tree felling in Sanctuary

required. Private

trees/plantations will be

compensated as per GoSL

norms.

limited to target

vegetation

The contractor will be advised to submit

a tree planting programme within the

grid station area and elsewhere as

compensatory reforestation, and also as

a CSR project

Soil erosion and

surface runoff

Construction in erosion prone

mudflats, lagoon areas should

be restricted to the dry season.

Outline construction Method

Statement shall be the basis for

construction practice in

Sanctuary area. Treat clearing

and filling areas against flow

acceleration and construction

work should be carefully

designed to minimize

obstruction or destruction to

natural drainage

Soil erosion

.

Visual inspection

(Turbidity and

sedimentation)

CEB, Contractor

Through contract

Provisions

Construction

period

Construction of towers will be over prior

to the rainy season of 2019.

The contractor has been instructed to

clear any construction debris, spoil,

excavated soil from the site areas prior

to commencement of the rainy season.

Mechanized

construction

Noise, vibration and

operator safety,

efficient operation,

equipment wear

and tear

Construction equipment to be

well maintained.

Check for pollution prevention

and oil dripping etc. from

vehicles while working in bird

habitat and other area. Adopt

pollution prevention measures

in accordance with EHS

Guidelines

Proper maintenance and

turning off plant not in use.

Operating schedules

Noise control

regulations (1994),

Pollution

Prevention as per

International best

practices43

CEB, Contractor

through contract

provisions

Construction

period

The contractor is maintaining records of

the status of construction equipment

and machinery.

NO oil dripping has been observed

during site visits

Construction of

roads for

accessibility

Increase in airborne

dust particles

Existing roads and tracks used

for construction and

Access roads, routes

(length and width of

Use of established

roads wherever

possible

CEB, Contractor

through contract

provisions

The contractor has been using existing

roads for accessing tower locations.

Some of the tower locations have ben

GPD&EEIIP1-2 P a g e | 18

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

Increased land

requirement for

temporary

accessibility

maintenance access to the site

wherever possible.

New access ways restricted to a

single carriageway width within

the RoW. Avoid construction of

permanent access routes in

sanctuary area by use of mats

etc.

new access roads to

be constructed)

Access restricted to

single carriageway

width within RoW

Construction

period

accessed, and material transportation

has been done with the use of a railway

carriage.

Increased air-borne dust was not

observed at transmission tower

locations during the site visit.

Eventhough air-borne dust occur at the

grid sub-station site frequent water

spray along the road and construction

site is observed.

Transportation

and storage of

materials

Nuisance to the

general public

Transport loading and

unloading of construction

materials should not to cause

nuisance to the people by way

of noise, vibration and dust.

Avoid storage of construction

materials beside the road,

around water bodies,

residential or public sensitive

locations

No storage of construction

material in the sanctuary area.

Construction materials should

be stored in covered areas to

ensure protection from dust,

emissions and such materials

should be bundled in

environment friendly and

nuisance free manner.

Water and air

quality

National

Environment Act

Laws and

regulations of

respective LAs

National Emission

Standards and CEA

water quality

standards

CEB/LAs

Construction

period

There have been no complains related

to the public nuisance caused by noise,

vibration and dust due to transport

loading and unloading of construction

materials

The contractor has avoided storage of

construction materials beside the road,

around water bodies, residential or

public sensitive locations such as the

sanctuary area.

However, the contractor has failed to

cover construction material at the grid

substation site. Air borne dust emissions

were observed during the site visit.

Trimming/

cutting of trees

within RoW

Fire hazards

Loss of vegetation

and deforestation

Trees allowed growing up to a

height within the RoW by

maintaining adequate

clearance between the top of

Species-specific tree

retention as

approved by

statutory

Felling of trees

(Amendment Act.

No 01, of 2000 and

CEB, Contractor

through contract

provisions

Selective tree cutting and trimming was

adopted, however within vankalai no

trees were cut or trimmed other than the

tower location; further tower locations

GPD&EEIIP1-2 P a g e | 19

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

tree and the conductor as per

the regulations.

Trees that can survive pruning

to comply should be pruned

instead of cleared.

Felled trees and other cleared

or pruned vegetation to be

disposed of as authorized by

the statutory bodies. Forest

trees, if any, would be planted

on basis of 1:1 replacement.

Any trees that die within 5

years are to be replaced.

authorities (average

and maximum tree

height at maturity,

in meters)

Disposal of cleared

vegetation as

approved by the

statutory

authorities (area

cleared in m2)

act of felling of

trees control)

Presence of target

species in RoW

following

vegetation

clearance.

Construction

period

have been selected to minimize the tree

cutting.

Health and

safety

Injury and sickness

of workers and

members of the

public

Contract provisions specifying

minimum requirements for

construction day-time camps

including sanitation and

welfare facilities in accordance

with EHS Guidelines

Contractor to prepare and

implement a health and safety

plan in accordance with EHS

Guidelines.

Contractor to arrange for

health and safety awareness

programmes.

Contract clauses

(number of

incidents and total

lost-work days

caused by injuries

and sickness)

Health and safety

regulations and

IFC’s EHS guidelines 2007 (under

revision)

CEB (Contractor

through contract

provisions)

Construction

period

Health and safety procedures are well-

established. Health and Safety plans

have been prepared and implemented

by both the contractors: grid sub-station

and the transmission tower.

H&S officers have been mobilized by

both the contractors.

Nuisance to

nearby

properties

Losses to

neighboring land

uses/ values

Contract clauses specifying

careful construction practices

in accordance with EHS

Guidelines.

As much as possible existing

access ways will be used.

Contract clauses

Design basis and

layout

Reinstatement of

land status (area

affected, m2)

Implementation of

Tree/Crop

Public Nuisance

Ordinance No.: 15

of 1862. And IFC’s EHS guidelines 2007

(under revision).

Incorporating good

construction

management,

CEB (Contractor

through contract

provisions)

Construction

Period

Consultation with

affected parties

immediately after

Being complied

GPD&EEIIP1-2 P a g e | 20

Project Activity Potential

Environmental

Impact

Mitigation Action Monitoring Scope Standard Responsibility of

Implementation &

schedule

Observations and Remarks

Productive land will be

reinstated following

completion of construction

Compensation will be paid for

loss of production, if any.

compensation

(amount paid)

design engineering

practices

completion of

construction and

after the first

harvest

Avian Collision Possible collision of

migrant birds with

transmission line

Install Swan-Flight Divertor or

Aerial Marker Spheres at the

stated separations on the

length of the transmission line

that crosses through Vankalai

sanctuary and Mannar island.

Installations on

transmission lines

on Birdlife

International (2012)

and APLIC (2012)

guidance

CEB and EPC

Contractor

Construction

period

Construction work of the transmission

line is too early to consider the proposed

activities

Rail and road

infrastructure

Possible crossing of

ecological and

ornithologically

habitat

Ensure route avoids such

habitats outside the sanctuary

area

Route alignment to

minimize such

occurrence

IFC’s GN6 and incorporation of

good construction

management,

design engineering

practices

CEB and EPC

Contractor

Construction

period

GPD&EEIIP1-2 P a g e | 21

Environmental Parameters and Periodicity for Environmental Monitoring Plan

Environmental

component

Project stage Parameters to

be monitored

Location Frequency Remarks/Comments

1. Air Quality Preconstruction

stage (The

project after

assigning to

contractor)

CO, Pb, PM10,

TSPM

Inside and

outside (0.5

km) of the

proposed

substation

A single time Complied

Construction

Stage

CO, Pb, PM10,

TSPM

Inside and

outside (0.5

km) of the

proposed

substation

1 time/ 3 months Samples for Air Quality Testing have been

collected on 18th & 19th Sep 2019 within the

Grid Sub Station

2. Water Quality Preconstruction

stage (The

project after

assigning to

contractor)

EC, TSS

(turbidity &

suspended

sediment), DO,

BOD, COD, pH,

Oil and grease,

Pb, E Coli (fecal

Coliforms), ,

hydrocarbon

One from

nearest well

and one from

surface water

source

around

substation

A single time Complied

Construction

Stage

EC, TSS

(turbidity &

suspended

sediment), DO,

BOD, COD, pH,

Oil and grease,

Pb, E Coli (fecal

Coliforms), ,

hydrocarbon

One from

nearest well

and one from

surface water

source

around

substation

1 time/ 3 months Water Samples have been collected on 19 th Sep

2019 from within the Grid Sub Station

Water Samples have been collected within the

Proposed Tower Location

GPD&EEIIP1-2 P a g e | 22

3. Noise/

Vibration

Preconstruction

stage (The

project after

assigning to

contractor)

Noise level (dB

level)

Inside and

outside (0.5

km) of the

proposed

substation

A single time Complied

Construction

Stage

Noise level (dB

level)

Inside and

outside (0.5

km) of the

proposed

substation

1 time/ 3 months Noise levels have been measured on 19th Sep

2019 at all the 4 boundaries of the Grid Sub

Station

(Continuous time integrated noise level taken at

1 sec time intervals for 15 min every hour and

then averaged for 24hours)

Noise levels have been measured on 14th Jan

2019 at the Vankalai Area

(Continuous time integrated noise level was

taken at 15 sec time intervals for 15 min every

hour and then averaged for 24hours)

4. Soil Preconstruction

stage (The

project after

assigning to

contractor)

pH, Sulfate

(SO3),

Chloride, ORP,

Salinity,

Resistively,

Organic

Matter,

Moisture

Content155

Inside and

outside (just

close to the

proposed site,

2 locations) of

the proposed

substation

A single time The sample for Soil testing has been collected on

10thApril at Grid Sub Station site.

Construction

Stage

PH, Sulfate

(SO3),

Chloride, ORP,

Salinity,

Resistively,

Organic

Matter,

Moisture

Content

Inside and

outside (just

close to the

proposed site,

2 locations) of

the proposed

substation

1 time/ 3 months Complied

GPD&EEIIP1-2 P a g e | 23

GPD&EEIIP1-2 P a g e | 24

Note: Refer the Annex -II for the Vankalai Sanctuary design details.

Environmental Safeguard Measures

Project activity

Potential impact Mitigation measure Location Duration Institutional responsibility

Implementation schedule

Taken Action To Mitigate

Construction

Design of Tr Line

in Vankalai

Sanctuary

Impact to the

Environment

• Tower heights

increased to protect

the trees (CEB will

not cut any Trees in

Vankalai Sanctuary .

• Tower Location is

selected to avoid the

foundation in water

logged area.

• Any pile foundation

will not be

encountered.

Location

of Towers

in

Vankalai

Sanctuary

During the

Design &

construction

stage

CEB and

Contractor

Construction

period

Complied.

GPD&EEIIP1-2 P a g e | 25

5.0 Safeguards Monitoring Results and Unanticipated Impacts

5.1 Water Quality at Mannar-Nadukuda TL – During construction stage

Water Samples were collected on 21th May 2018 by boring within the Proposed Tower Location

Parameter Method Unit Result Maximum Limit

pH at 26.1 ºC ASTM D 1293-

99 - 7.3 ≥ 4

Turbidity USEPA 180.1 NTU NT (8 Jackson Turbidity units as per

SLS (No value as per WHO)

Chloride (Cl) Content ASTM D 512-04 mg/L 3696 (1200 as per SLS (No value as per

WHO)

Sulphate (SO3) Content ASTM D 516-07 mg/L 510 2000 (400 as per SLS (No value as

per WHO)

Humic matter BS EN

1008:2002 -

Colour is

lighter

than

Yellowish

brown

Total Dissolved Solid

(TDS) APHA-2540-C mg/L NT

2000 (500 as per SLS, 1000 as per

WHO)

5.2 Air Quality at Mannar- Nadukuda TL – Pre construction stage

Samples for Air Quality Testing were collected over a period 14th & 15th Jan 2019 within the Proposed

Vankalai Area

Sr No Parameter Method

Recorded

Values

(μg/m3)

Permissible level (μg/m3)

(as per Min of

Environment, Govt of SL)

1 Particulate Matter (PM10) ASTM D 4096-82 82 100

(24 hr Average)

2 Particulate Matter (PM2.5) ASTM D 4096-82 43 50

(24 hr Average)

3 Carbon Monoxide (CO) ASTM D 3162-78 2679 30000

(1 hr Average)

5.3 Noise Level at Mannar-Nadukuda TL – Pre construction stage

Noise Samples were collected on 14th Jan 2019 At the Vankalai Area

Continuous time integrated noise level was taken at 15 sec time intervals for 15 min every hour and

then averaged for 24hours.

GPD&EEIIP1-2 P a g e | 26

Sr No Parameter Method Corrected

Noise

Level dB

(A)

Permissible Noise Level dB (A) (As

per Central Environmental

Authority, SL)

1 Noise Level Sound level meter

(RION NL-52)

57 75 (during day time)

5.4 Test on Soil at Mannar-Nadukuda TL – Pre construction stage

Layer description Average

SPT

Shear strength

parameters

Ultimate bearing

capacity (kN/m2)

Elastic Modulus

E (kN/m2)

Medium dense sand 14 c' = 0 kPa, φ' = 30 250 1800

0Very dense sand > 50 c' = 0 kPa, φ' = 43 2000 2500

0Dense sand 30 c' = 0 kPa, φ' = 35 750 2200

0

Completely weathered

rock

> 50 c' = 10 kPa, φ' = 38 1500 2500

5.5 Water Quality at Nadukuda GSS – Pre-construction stage

Water Samples were collected on 19th Sep 2019 from in the Grid Sub Station area.

Parameter Method Unit Result Maximum Limit

pH at 26.1 ºC ASTM D 1293-99 - 7.0 ≥ 4

Turbidity USEPA 180.1 NTU 0.4 (8 Jackson Turbidity units as per

SLS

Chloride (Cl) Content ASTM D 512-04 mg/L 90.22 (1200 as per SLS

Sulphate (SO3) Content ASTM D 516-07 mg/L 92.4 (400 as per SLS

Humic matter BS EN 1008:2002 - Colour is

Clear

GPD&EEIIP1-2 P a g e | 27

5.6 Air Quality at Nadukuda GSS – Construction stage

Samples for Air Quality Testing were collected over a period 18th & 19th Sep 2019 within the Grid

Sub Station.

Sr No Parameter Method

Recorded

Values

(μg/m3)

Permissible level (μg/m3)

(as per Min of

Environment, Govt of SL)

1 Particulate Matter (PM10) ASTM D 4096-82 13 100

(24 hr Average)

2 Particulate Matter (PM2.5) ASTM D 4096-82 21 50

(24 hr Average)

3 Carbon Monoxide (CO) ASTM D 3162-78 2900 10000

(8 hr Average)

5.7 Noise Level at Nadukuda GSS – Construction stage

Noise Samples were collected on 19th Sep 2019 at all the 4 boundaries of the Grid Sub Station

Continuous time integrated noise levels were taken at 1 sec time intervals for 15 min every hour and

then averaged for 24hours.

Sr No Parameter Method Corrected

Noise

Level dB

(A)

Permissible

Noise Level dB

(A)

(As per Central

Environmental

Authority, SL)

1 Noise Level – Boundary 1 Sound level meter

(RION NL-52)

54 75 (during day

time)

2 Noise Level – Boundary 2 Sound level meter

(RION NL-52)

43 75 (during day

time)

3 Noise Level – Boundary 3 Sound level meter

(RION NL-52)

46 75 (during day

time)

4 Noise Level – Boundary 4 Sound level meter

(RION NL-52)

59 75 (during day

time)

5.8 Test on Soil at Nadukuda GSS – Pre construction stage

Soil Samples were collected from Inside and outside the Substation area on 10th April 2019 and the

results are as follows

GPD&EEIIP1-2 P a g e | 28

PARAMETERS

RESULTS

LOCATION 1

(INSIDE GSS)

LOCATION 2

(OUTSIDE GSS)

pH 6.9 6.9

Moisture Content 5.20% 5.80%

Sulphate Content (SO3) 2900 ppm 3000 ppm

Chloride Content (Cl) 122 ppm 154 ppm

Organic Matter 21% 34%

6.0 Implementation of Grievance Redress Mechanism and Complaints Received from

Stakeholders

No any Grievance Redress Mechanism have been implemented during the reporting period.

7.0 Conclusions and Recommendations.

The Green Power Development and Energy Efficiency Improvement Investment Programme

(Tranche 2) Package 2 which consists of two major projects components namely Lot B1

Construction of Mannar – Nadukuda 220kV Transmission Line and: Lot A Construction of

Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation

are already commenced. It has been identified the project activities associated with the

environment during implementation phase as clearing of trees along the route alignment,

excavation for installation of towers, erection of towers, civil works related to transmission

line and line stringing, excavation for building and equipment foundations in substations, civil

works and erection of equipment especially in the Vankalai sanctuary.

The impacts on the environment from aforesaid activities of the project can be categorised

as follows:

• Impact on Physical Resources (Impact on Topography, Impact on Climate)

• Impact on Environmental Resources (Impact on Air Quality, Impact on Noise Levels,

Impact on Surface Water Quality, Impact on Ground Water Quality, Impact on Soils and

Geology)

• Impact on Ecological Resources (Terrestrial Ecology, Aquatic Ecology, Ornithology)

• Impact on Human Environment (Health and Safety, Agriculture, Socio-economics,

Resettlement and Rehabilitation Cultural sites, Traffic and Transport, Interference with

other utilises and traffic)

• Waste Disposal (Solid waste disposal, Liquid waste disposal)

Environmental Safeguard Measures are being adopted to mitigate the aforementioned

impacts during the construction period in compliance with the applicable acts and the

legislation to this Project.

CLIENT : CEYLON ELECTRICITY BOARD, SRI LANKA CONTRACTOR : KEC INTERNATIONAL LTD.

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

YEAR'20

QTY UNIT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN'20

A MOBILISATION

B SURVEY WORKS

1 Route Alignment 30 Km

2 Detail Survey & Profile 30 Km

3 Check Survey & Pegging Out 30 Km

C ENGINEERING & DESIGN

1 Coductor 1 No.

2 Earthwire 1 No.

3 OPGW 1 No.

4 Insulator 1 No.

5 Hardware Fittings 1 No.

6 Tower Design 5 No.

7 Earthing Materials 1 No.

8 Tower Accessories 1 No.

9 Testing of Suspension Tower 1 No.

10 Testing of Angle Tower 1 No.

11 Soil Investigation 90 No

12 Foundation Design 90 No

C MANUFACTURING AND DELIVERY

1 Conductor 384 Km

2 Earthwire 32 Km

3 Stubs & Towers 90 No

4 Insulator 18896 No.

5 OPGW & Fittings 30 Km

6 Hardware Fittings 90 Sets

7 Earthing Material 90 Sets

8 Tower Accessories 90 Sets

D CONSTRUCTION

1 Tower Foundation & Earthing 66 No

2 Tower Foundation & Earthing(Vankalai) 24 No

2 Tower Erection 66 No

2 Tower Erection (Vankalai) 24 No

3 Stringing of Conductor & Earthwire 30 Km

4 Stringing of OPGW 30 Km

CONSTRUCTION OF MANNAR TO NADIKUDA 220KV D/C TRANSMISSION LINE UNDER GREEN POWER DEVELOPMENT NAD ENERGY EFFICIENCY IMPROVEMENT INVESTMENT

PROGRAMME (TRANCHE-2) PACKAGE 2 (LOT B1)

CONSTRUCTION SCHEDULECONTRACT COMMENCEMENT DATE : 19th Oct'2017 REVISED COMPLETION DATE : 23rd Jan'2020

YEAR - 2019Sl No ActivityMonths

YEAR - 2017 YEAR - 2018

CLIENT : CEYLON ELECTRICITY BOARD, SRI LANKA CONTRACTOR : KEC INTERNATIONAL LTD.

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

YEAR'20

QTY UNIT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN'20

CONSTRUCTION OF MANNAR TO NADIKUDA 220KV D/C TRANSMISSION LINE UNDER GREEN POWER DEVELOPMENT NAD ENERGY EFFICIENCY IMPROVEMENT INVESTMENT

PROGRAMME (TRANCHE-2) PACKAGE 2 (LOT B1)

CONSTRUCTION SCHEDULECONTRACT COMMENCEMENT DATE : 19th Oct'2017 REVISED COMPLETION DATE : 23rd Jan'2020

YEAR - 2019Sl No ActivityMonths

YEAR - 2017 YEAR - 2018

5 Tower Accessories 90 No

6 Final Checking 90 No

E TESTING AND COMMISSIONING

F T.C.C

ID Task Name

1 CEB - 220/33kV GIS Substation at Nadukuda and Augmentation of 220kV AIS Substation at Mannar

2 Project 1: 220/33kV GIS SUBSTATION AT NADUKUDA

3 Handing Over of Encumbrance free Site with Access Road

4 Site Studies

15 Providing Services

18 Substation Engineering

93 Equipments: Design, Engineering, Procurement & Supply

230 Civil Works

289 Installation

304 Testing & Comissioning

315 Final Commissioning & Handover

316 Project 2 : AUGMENTATION OF 220kV AIS SUBSTATION AT MANNAR

317 Existing Substation Drawings and Details of Mannar SS from Customer

318 Handing over of Encumbrance free Site with Access Road

319 Engineering

369 Equipments Supply

483 Civil

501 INSTALLATION ,TESTING & COMMISSIONING

Mar 16 '18 Mar 14 '20

Mar 16 '18 Mar 14 '20

Mar 17 '18 Mar 17 '18

Feb 27 '20 Mar 14 '20

Mar 16 '18 Feb 15 '20

Mar 16 '18 Apr 19 '18

Mar 19 '18 Mar 19 '18

1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27 2/17 3/10 3/31 4/21 5/12 6/2 6/23 7/14 8/4 8/25 9/15 10/6 10/27 11/17 12/8 12/29 1/19 2/9 3/1 3/22 4/12 5January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1 February 21 April 11 June 1 July 21 September 11 November 1 December 21 February 11 April 1

Normal

Milestone

Summary

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Manual Progress

SIEMENS CEB - 220/33kV GIS Substation at Nadukuda and Extn. of 220kV AIS at Mannar, Sri Lanka

SUNDAY IS CONSIDERED AS NON WORKING DAY IN SCHEDULE. Page 1 of 1

Date: Tue 9/18/18

Rev ‐B

/(m) /(m) /(m) /(m) /(m)  /(m)  /(Deg) /(m)

01 N1 TDL 9 17,272.580               403,534.048             716,787.001                0.529                  209.37            0 Pad & Cheminy 43.2

02 N2 TDL 6 17,481.947               403,642.173             716,607.714                1.769                  294.63            0 Pad & Cheminy 40.2

03 N3 TDL 6 17,776.576               403,794.329             716,355.416                0.598                  275.74            0 Pad & Cheminy 40.2

04 N4 TDL 6 18,052.319               403,936.732             716,119.289                (0.650)                 326.90            0 Pad & Cheminy 40.2

05 N5 TDL 0 18,379.217               404,105.553             715,839.358                (0.038)                 213.86            0 Pad & Cheminy 34.2

06 O0 TD3 6 18,593.081               404,216.000             715,656.220                0.590                  437.99            ‐28.9283 Pad & Cheminy 39.4

07 O1 TDL 9 19,031.066               404,595.389             715,437.371                (0.341)                 396.30            0 Pad & Cheminy 43.2

08 P0 TD1 0 19,427.369               404,938.672             715,239.350                (0.836)                 408.31            10.61 Pad & Cheminy 36.65

09 P1 TDL 9 19,835.680               405,248.745             714,973.694                (0.613)                 430.76            0 Pad & Cheminy 43.2

10 P2 TDL 6 20,266.437               405,575.863             714,693.435                0.394                  401.13            0 Pad & Cheminy 40.2

11 P3 TDL 3 20,667.567               405,880.483             714,432.452                0.707                  351.65            0 Pad & Cheminy 37.2

12 P4 TDL 0 21,019.212               406,147.523             714,203.665                (0.654)                 356.64            0 Pad & Cheminy 34.2

13 P5 TDL 3 21,375.854               406,418.359             713,971.627                (0.371)                 382.05            0 Pad & Cheminy 37.2

14 P6 TDL 9 21,757.903               406,708.488             713,723.058                0.890                  250.51            0 Pad & Cheminy 43.2

15 P7 TDL ‐3 22,008.417               406,898.729             713,560.069                0.630                  227.81            0 Pad & Cheminy 31.2

16 Q0 TD3 0 22,236.228               407,071.730             713,411.850                0.769                  220.51            ‐26.3132 Pad & Cheminy 33.4

17 Q1 TDL 9 22,456.742               407,285.435             713,357.476                0.950                  370.63            0 Pad & Cheminy 43.2

18 Q2 TDL 9 22,827.372               407,644.621             713,266.087                1.859                  251.53            0 Pad & Cheminy 43.2

19 Q3 TDL 3 23,078.897               407,888.380             713,204.066                1.859                  325.70            0 Pad & Cheminy 37.2

20 Q4 TDL 3 23,404.597               408,204.023             713,123.756                1.147                  385.15            0 Pad & Cheminy 37.2

21 Q5 TDL 6 23,789.742               408,577.276             713,028.787                0.733                  412.65            0 Pad & Cheminy 40.2

22 Q6 TDL 6 24,202.395               408,977.187             712,927.036                1.542                  218.24            0 Pad & Cheminy 40.2

23 R0 TD6 0 24,420.636               409,188.690             712,873.223                1.738                  323.77            44.6391 Pad & Cheminy 33.3

24 R1 TDL 0 24,744.401               409,355.856             712,595.952                1.761                  331.34            0 Pad & Cheminy 34.2

25 R2 TDL 0 25,075.742               409,526.934             712,312.193                2.033                  329.10            0 Pad & Cheminy 34.2

26 R3 TDL 0 25,404.838               409,696.853             712,030.356                2.677                  311.92            0 Pad & Cheminy 34.2

27 S0 TD6 ‐3 25,716.753               409,857.901             711,763.234                2.733                  250.58            37.7967 Pad & Cheminy 33.3

28 S1 TDL 6 25,967.332               409,828.618             711,514.372                1.597                  336.28            0 Pad & Cheminy 40.2

Note : 01)  Survey Coordinate syaytem SLD 99 (Sri Lanka National Coordinate System)

02) Number of Towers in Vankalai Sanctuary are 23

Remarks

Not in Vankalai Sanctuary/Ramsar Site

Mannar ‐ Nadukuda 220kV Transmission Line

Line Schedule

Tower No.

Tower HeightStation X ‐ Easting Y ‐ Northing Z ‐ Ground Elevation Line AngleAhead Span Tower  

Type

Tower Body Ext. Foundation TypeSe. 

No.

Annex -II

Weekly Environmental Monitoring Report - Transmission Line

Soil Testing Report - Grid Substation

Ambient Air Quality Monitoring Report - Grid Substation

Noise Level Monitoring Report - Grid Substation

60

Annex 4.1:Summary of Environmental Safeguard Monitoring Reports Received

Component Report Status and comments

ADB Loan 3483/3484 SRI: Green Power Development and Energy Efficiency Improvement Investment Programme (Tranche 2)

Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line

Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation

Q1 (January 1 – March 31, 2019)

Environmental Safeguard Monitoring Report Received.

Comments submitted to the CEB.

Response matrix pending

Q2 (April 1 – June 30, 2019) Environmental Safeguard Monitoring Report NOT Received.

Q3 (July 1 – September 30, 2019)

Environmental Safeguard Monitoring Report Received.

Comments are submitted to the CEB as part of this External Monitoring Report (See Annex 4.2)

Two weekly checklists (#21 and #25) have been forwarded by the Contractor

(Annex 4.3)

Wind Power Generation Project (Project No. 49345-002)

No quarterly Environmental Safeguard Monitoring Reports have been received so far.

Monthly Environmental Monitoring Reports submitted by Vestas have been forwarded.

(for July, August and September 2019)

(Annex 4.4 for Report submitted for September)

61

Annex 4.2

ADB Loan 3483/3484 SRI: Green Power Development and Energy Efficiency Improvement Investment Programme (Tranche 2)

₋ Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission

Line

₋ Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation &

Augmentation at Mannar 220/33kV Grid Substation

Comments on Environmental Safeguard Monitoring Report

Reporting Period: Q3 of 2019 (From July 01, 2019 to September 30,2019)

1. Section 1.2: The progress status of the project is given for October 2018 – December

2018. It is more appropriate to provide the progress at the end of the period that is

reported in the Environmental Safeguard Monitoring Report, i.e., end of Q3 of 2019.

2. Site Photos of Construction of Mannar – Nadukuda 220kV Transmission Line: It is

always good to provide a short description for each photograph (location, tower

number, what is the main feature that is intended to be highlighted, etc.), and the

date the photo was taken.

3. Page 5 (bottom): Indicate the number of days lost due to inclement weather, and the

implication of such incidents on the environment (e.g., flooding of the footings,

trenches, drainage problems, erosion of topsoil, etc.). Then describe what the

contracts have done to mitigate such environmental incidents.

4. Page 6 (top): Progress status of the GS: the comment (#1) that has been given

above for Section 1.2 applies here, too.

5. Site photos of the construction of the Nadukuda GS: comment #2 given above

applies here.

6. Table 2.0: Applicable Acts and Legislations to the Project:

₋ The Compliance Schedule to be corrected as the Compliance Status.

₋ It had been indicated that the Act/Rule/Notification has ‘being complied’ for all

the entries (other than for felling of trees). More explanation is required for

each entry as to how each Regulation has being complied with.

7. Section 4.0: Compliance to Environmental Management Plan

Check whether all the Project Activities and Potential Impacts for both Pre-construction and Construction Periods match with the EMP given in the EIA Report approved by the ADB.

If they do not match, please add all other entries given in the EMP proposed in the EIA Report.

8. EMP and EMoP – Pre-construction

The following are missing (baseline monitoring reports):

• Water Quality

62

• Air Quality

• Noise and Vibration Levels

• Soil testing results

Include the following:

₋ The location where the samples were taken

₋ Who collected, and who tested the samples

₋ Test Reports to be attached to the Report.

9. Explosions/Fire as included in the EMP

Check whether the following statement needs any updating:

‘Provision of firefighting equipment has been planned. This has to be verified prior to commissioning’

10. Equipment layout and installation, Noise and vibrations included in the EMP

Check whether the following statement needs any updating:

‘Disturbances have been kept to a minimum. No significant noise and vibration impacts recorded and no complaints.’

11. Transportation and storage of materials: Nuisance to the general public as included

in the EMP

It has been stated that:

“the contractor has failed to cover construction material at the grid substation site. Air borne dust emissions were observed during the site visit.”

It is advisable to provide proper guidance and directions for the contractor to mitigate this impact.

Subsequent monitoring is also needed.

12. Avian Collision as included in the EMP.

It has been stated that:

“Construction work of the transmission line is too early to consider the proposed activities”

It has to be noted that the stringing is now in progress. Therefore, bird collisions monitoring should be commenced without any further delay.

13. Check whether the Safeguard Monitoring is followed according to the EMoP

proposed in the EIA Report. Check the locations, frequency, parameters, etc.

14. EMoP – Monitoring Reports for Grid Sub-station

(i) Air Quality monitoring report conducted by the NBRO

Air Quality measurement report received for the period from July 01,2019 to September 30, 2019, For Grid Substation (GSS);

(Measured parameters are CO, PM10, PM2.5, Pb); TSPM has not been measured.

According to the report, data was measured on 18th & 19th Sep 2019, but the results table

63

in the same report depicts CO was measured on 10/04/2019 and analyzed on 10/04/2019 whereas PM 10, PM 2.S, Pb were measured on 09-10/04/2019 and analyzed on 12/04/2019. Therefore, these dates are contradicting.

(ii) Water Quality report not received

(iii) Noise measurement report received Noise report has been received. Noise measurement was taken on 19th Sep 2019 at four locations identified by the client. Vibration levels have not been measured.

(iv) Soil report received. Location 1: Inside GSS

Location 2: Outside GSS The sample was collected on 10/04/2019 but tested on 02/10/2019 according to the report. Samples have not been collected during July–September period. The report that has been sent is for a soil sample collected in April!

15. Add a section on Unanticipated Impacts

16. Add a short write-up on any deviations from the EMP, and the EMoP as suggested in

the EIA Report.

17. Add a section on any ‘Lessons Learnt.’

18. It is not clear how you have received any Environmental Reports from the Contractor.

It is suggested that the Contractors are advised to maintain environmental monitoring

records to comply with the procedures using a standard template.