JFE Steel transforms IT and core business processeswith S/4HANA
2
JFE Steel Corporation
JFE Steel transforms IT and core business processes with S/4HANA
Japan Mill Products
“ This project makes it possible to standardize business processes and build foundation of a global accounting system. SAP S/4HANA enables us to analyze whole group’s business performance more efficiently and effectively.”
▪ We decided to renovate accounting system providing IFRS
compliance and supporting our global growth strategy,
thus increasing participation by global investor community.
Our project is designed to standardize and modernize the
conventional business processes of a traditional Steel
company using SAP S/4HANA.
▪ Steel industry, being highly asset-intensive, requires higher
capacity fixed asset accounting. Our accounting system has
been redesigned along with SAP S/4HANA.
▪ The project covers JFE steel and its 80 subsidiaries. We
completed the roll-out to 80 subsidiaries within 11 months,
and achieved standard processes without customization.
Toshihiro Tanaka - Chief Financial Officer
80
11
75%off
Subsidiaries
Went-Live in
Months
Reduced the numberof servers
JFE
HD
JFE
Steel
JFEEngi-
neering
Total 80Companies
Other System
(Corporate)
- Emphasize Enterprise Governance
- Almost ZERO Add-on
- IFRS Compliance
- Simplify System & Operation
- Simplify Accountancy Service
- Implement Best Practices
- Standardized Business ProcessesUsers Users Users
Expectations (Business)
Other System
(Each Subsidiary)
SAP S/4HANA (Finance) Expectations (System)
17%off
Saved IT supportscost
3
Participant Information
↑ Click here (corporate profile video)
JFE Steel transforms IT and core business processes with S/4HANA
http://www.jfe-steel.co.jp/en/index.html
Mill Products
Yuko Tamura, JFE Steel Corporation
JFE Steel is one of the world’s leading integrated
steel producers*. A strong international player with
a sophisticated production system consisting of
two major steelworks, one each in eastern and
western Japan.
*We are the 8th largest steel manufacturer in the
world and the second largest in Japan.
(source of reference : World Steel Figures 2017)
Yuko Tamura, Staff Manager of “IT Innovation Leading
Department” and the Project Leader for SAP S/4HANA
implementation at JFE Steel.
4
Issues that we have been facing
Global expansion had become crucial for JFE Steel, as Steel Market had reached mature stage and overseas competitors had undergone aggressive growth. Corresponding to IFRS compliance was important for our global operations and being demanded by investors community.
Standardization of business processes was important. Though, many of our core competences were in the field, we needed to secure organization skills and human resource inheritances from senior workforce, for preparing generational changes in near future.
Increasing visibility across group subsidiaries was important, as we operate business with functionally branched subsidiaries. We needed to look at the data in horizontal skewer and communicate in the same manner for operating One-JFE group.
5
Solution Overview
We started to transform ourselves from a traditional manufacturing company
to a more global and digitalized company in order to survive competitive
market, by using S/4HANA. Objectives were as follows:
▪ Contributing to global growth strategy such as attracting worldwide investors by
showing high governance, operating all the group companies as One-JFE company.
▪ Improving business visibility and transparency that enables quick decision-making,
we standardized business processes and let our employees access and analyze
the data in real-time.
▪ Building up centralized business operations on S/4HANA foundation, within planned
financial budget and original project schedule without any overruns.
▪ Realizing a simple and single architecture/platform, which includes one
consolidated server, unified storages and highly optimized user management,
which serves JFE Steel and all 80 subsidiaries.
6
Solution Details
We completed S/4HANA implementation, with almost no add-ons. Implementation for JFE steel was completed within just 9 months and roll-out for 80 subsidiaries was achieved within 11 months.
Key success factors of project management were as follows:
▪ Strong governance model, supported by board members.
▪ Standardization and reduction in the number of reports from legacy application, thus, providing flexible and real-time reports through S/4HANA to the end-users.
▪ Proposal of substitute and better business operations and processes in parallel.
▪ Education for end-users from the beginning, encompassing IT perspectives, project objectives and required employee mindset change. S/4HANA working model facilitated this prototyping approach.
▪ Good use of the collaboration portal site, where incidents can be shared with all project members and encourage communication for early resolution.
7
Solution Details
▪ People EmpowermentWe had recognized the education for users is a Key for our project success. So, we had started the education at
an early stage in the project.
Corporate
Strategy
Project
Objective
StandardizedBusinessProcess
System
Operation
Education + Fully Understand
Education + Fully Understand
Assigning Key Users in each End-User division. Key Users understand not only the system operation, but also
Corporate Strategy, Project Objective and Standardized Business Process earlier. Then, they disseminated them
to End-Users. This activities greatly contributed to Project Success.
Penetrate
Governance
Purpose Led
Thinking
MasteredStandardized
Process
ImprovedSystem
Operation
Reduction of
Add-on
Shorten the duration
of deployment to 80
Subsidiaries
Satisfy Business
and System
Expectations Early
BenefitAchievement
Apr. May Jun. Jul. Aug Sep. Oct. Nov. Dec. Jan. Feb. Mar. Apr.
2016 2017
Requirement Definition Design Development / TestingPrep.
Migration
Education PolicyDefinition
EducationPlanning
Develop Education Tools End User Training
Extend the
method to 80
companies
8
Architecture
JFE
HD
JFE
Steel
JFEEngi-
neeringTotal 80Companies
Other System*(Corporate)
Users Users Users
Other System*(Each Subsidiary)
SAP S/4HANA (Finance)
Single Sign-On
Unified Master Management System
* SAP S/4HANA connects to from more than 120 other systems.
Interface Management
Electronic BooksMaintenance
9
Deployment details
◇ This project:
• Our system went live for JFE Steel Corporate on April 17, 2017 (in 9 months).
• After that, we deployed S4/HANA for 80 subsidiaries which were located all over
Japan (in 11 months). In order to promote system introduction and consolidation of
operations to many subsidiaries, we staggered go-live into three groups, viz., August
2017, November 2017, February 2018
• Utilizing the standard functionalities of SAP solutions enabled us to shorten the
period of POC, Prototype and development.
• We did not customize and modify anything, except for some interfaces and very few
reports.
• About 700 employees in JFE Steel and subsidiaries are now using SAP S/4HANA.
10
Deployment details
◇ Subsequent projects:
• Standardize and integrate business processes and IT
systems of all steel plants for information and knowledge
sharing across all the plants in order to create an integrated
manufacturing foundation.
• Initiatives are being taken to improve work efficiency and to
realize the workstyle reforms.
• Planning to implement PS for optimizing greenfield and
brownfield plant projects and S/4HANA is a strong candidate
product.
• We will continue to promote business process
standardization, innovation and workstyle reforms. This
project is first step towards that grand vision.
11
Benefits
Business value:
Human empowerment:
▪ Saved IT support costs by 17%.
▪ Reduced the number of servers and storages by 75%, still maintaining high performance.
▪ Complied with reporting standards like IFRS for more global operation.
▪ Increased the quality of reporting and gives users in accounting flexible and real-time access to data.
▪ Brought wide management visibility at each group company’s performance and status.
▪ Impacted the other Japanese manufacturing companies by showing our success to be able implement
S4/HANA, utilizing best practices. Gartner made a case report for out project.
▪ Standardized and improved the business processes for human resource inheritance.
▪ Empowered the accessibility and usability's in the field, increasing efficiency at all levels and plan
effectiveness along with also eliminating human errors automatically with S4/HANA.
▪ Established robust and simplified user authentication for all the users and master management system
in order to ease user authority management and gain confidence from IT audit.
▪ Improved the maintenance of user authorizations and codes update that could rationalize the
maintenance workload under multi-company environment, especially considering future global
operations. This makes it easier for us.
12
Quote
“ This project makes it possible to standardize business processes and build foundation of a global accounting system. SAP S/4HANA enables us to analyze whole group’s business performance more efficiently and effectively.”
Toshihiro Tanaka -Chief Financial Officer, JFE steel Corp.
“ JFE steel is a Japanese company that represents highest quality, and innovative performance. JFE takes on a leader role in S/4HANA implementation, to showcase best practices to build simple, and flexible management bases through the group companies. Not only have they showcased best practice, but they have proved that innovation is key, and at the heart and base for the whole company. ”
Yasushi Suzuka -Chairman, JSUG (Japan SAP Users’ group)
“ This is the best S4/HANA implementation project in Japan, in terms of achieving projects’ quality, cost and schedule.The success of this project have strong market influence and impact in Japan”
Yuzuru Fukuda -President, SAP Japan
13
Additional information
TOKYO - SAP Japan Co., Ltd announced today that JFE Steel Corporation Introduced SAP
S/4 HANA® as an application in the core system (accounting domain) and announced that it
began operation in April this year.
JFE Steel is the representative steel company in Japan which was born in 2003 when NKK
Corporation and Kawasaki Steel Corporation merged and integrated. Under the corporate
philosophy of "always contributing to society with the world's best technology", we are
contributing widely to the development of society as the world's leading manufacturer of steel
products, which is the basic material supporting industrial society. For further development,
JFE Steel is working on "improvement of domestic manufacturing infrastructure", "promotion
of overseas business" and "improvement of product mix through upgrading variety," and we
are working on "aggressive IT management" as a measure to support them.
https://news.sap.com/japan/2017/05/25/jfe%E3%82%B9%E3%83%81%E3%83%BC%E3%83%AB%E3%80%81sap-
s4hana%E3%81%A7%E6%9C%AC%E4%BD%93%E3%81%8A%E3%82%88%E3%81%B3%E3%82%B0%E3%83%AB%E3%83
%BC%E3%83%97%E4%BC%9A%E7%A4%BE%E3%81%AE%E4%BC%9A%E8%A8%88/
SAP Press release (May 25, 2017)
14
Additional information
JFE Steel has adopted SAP S/4HANA “advanced management analysis", “future IFRS
response and shortening of accounts", in order to support continuous business growth in
domestic and overseas business environment, , “standardization of work and personnel
succession", and "further global expansion".
JFE Steel has been using domestic individual packages for more than 10 years, but in order to
realize offensive IT management, in order to develop further domestic and foreign business
including M&A, deal with future IFRS, to review the IT infrastructure that supports the
simplification and efficiency of the project, and we began considering revamping the core
system from the fall of 2015. As a result of examining the products of several companies, we
evaluated the abundance of standard functions of SAP S/4 HANA, future extensibility,
stability ,flexibility and innovation that make maximum use of SAP HANA® in-memory
technology, worldwide. We evaluated points with many achievements and decided to adopt
SAP S/4HANA in June 2016.
Under the support of ABeam Consulting Ltd. and JFE Systems, Inc., the system construction
was advanced with the policy of "New business and system construction that make maximum
use of the characteristics of packages", and eventually almost nine months without add-ons.
We completed the project between April 2017 and full-scale operation started.
15
Additional information
“Japanese manufacturing industries, especially metals production, are extremely complex and being able to consistently produce and deliver high quality products requires the most sophisticated approach to blending the best people, processes and technologies. Considering this, it is a great achievement for JFE to have been able to standardize on best practice business processes that enable the company to compete effectively in the global market”
Eckhardt Siess -Head of Industry Business Unit Mill Products & Mining, SAP SE
“My mission and goal was to change JFE to a global top-level company, both in IT as well as business processes. The success of this project is one of the big steps towards my goal.”
Akira Nitta - General Manager of IT Innovation Leading Dept. JFE steel Corp.
16
Additional information
Contribution
Japan SAP Users’ Group
Nobumitsu Kambe
SAP Japan
Takeshi Kawanaka, Nikhil Chaturvedi, Hidetoshi Fujimoto