Risk Management for PPP Highway Infrastructure Projects: An Investors Review
Transcript of Risk Management for PPP Highway Infrastructure Projects: An Investors Review
1
Cairo University
Faculty of Engineering
Department of Construction Management
Paper Titled:
Risk Management for PPP Highway
Infrastructure Projects: An Investors Review
By: Mahmoud Ali Elhisnawi
Supervised by:
Dr.
2012
2
Introduction:
Public private partnerships (PPP) are, in general, agreements between two
parties, the public and the private sector, for delivery of services which were
traditionally provided by the public sector. These partnerships serve as a model for
overcoming budgetary shortfalls, i.e. for filling the gap between services required by
the society and available funds for delivery of those services [1].
Transport is one of major sectors in which the implementation of these types
of agreements has become a common approach in resolving the infrastructure
issues Revenue generating projects like toll roads were usually funded by the
public sector, while the private sector was involved mainly in several phases of
project’s life like construction of the highway section or scheduled
maintenance work. However, PPP agreements enable the private sector to
participate in the project delivery through several crucial phases like design,
building, finance, and operation or build-operate-transfer (BOT) scheme which
is one of common PPP models. For providing these services, the private sector
is usually entitled to collect tolls from users, although the public sector may
provide an annual payment directly to the private sector proportional to the
highway traffic volumes [2].
Considering long term obligations between contract parties, which are
for highway PPP projects, i.e. concessions, usually 25 to 30 years, and complex
nature of this type of projects with number of associated risks, there is a need
for contractual flexibility which will provide a right for a change in investment
decision depending on the project’s future performance. Application of real
options theory in road PPP projects enables this kind of flexibility thus increasing the
project value, and better share between parties of project’s risks.
In this paper, focus is on risk management for PPP Highway Infrastructure
Projects from investors prospective. It also, presents a process model for risk
management including identification, assessment, allocation, monitoring and control
of risks over the whole lifecycle.
Goals and Objectives:
3
1. To identify the risks occurred through the partnership of Public – Private
Sectors work.
2. To identify the types of risks.
3. To propose the optimal solutions might help the decision makers involved
in the partnership to avoid the risks.
The PPP Concepts:
Governments in most developing countries face the challenge to meet the
growing demand for new and better infrastructure services. As available funding from
the traditional sources and capacity in the public sector to implement many projects at
one time remain limited, governments have found that partnership with the private
sector is an attractive alternative to increase and improve the supply of infrastructure
services. The partners in a PPP, usually through a legally binding contract or some
other mechanism, agree to share responsibilities related to implementation and/or
operation and management of an infrastructure project. This collaboration or
partnership is built on the expertise of each partner that meets clearly defined public
needs through the appropriate allocation of [5].:
Resources
Risks
Responsibilities, and
Rewards
The term of Public-Private Partnerships (PPPs) has been interpreted widely in
the literature to encompass any arrangement between the government and private
sector to deliver services to the public. Although there is no unified definition of
PPPs, all definitions have common features or characteristics [1], such as the potential
for synergy, the development and delivery of a strategy or a set of projects or
operations, and the social partnership [4]. In this study, PPPs refer to a complex long-
term contractual arrangement involving the provision of services that require the
construction of infrastructure assets (Anonymous, 2004). The PPP has also defined as
a long-term contractual arrangement between the public and private sector where
4
mutual benefits are sought and where the private sector provides operating services
and/or puts private finance at risk [6].
What advantages PPPs may provide?
Governments worldwide have increasingly turned to the private sector to
provide infrastructure services in energy and power, communication, transport and
water sectors that were once delivered by the public sector. There are several reasons
for the growing collaboration with the private sector in developing and providing
infrastructure services, which include:
• Increased efficiency in project delivery, and operation and management;
• Availability of additional resources to meet the growing needs of investment
in the sector; and
• Access to advanced technology (both hardware and software).
How a PPP project is different from a conventional project?
There are significant differences between a conventional construction procurement
project and a PPP project that need to be clearly understood. The main differences
include:
• PPP projects are different from conventional construction projects in terms
of project development, implementation, and management. The
administrative and approval processes in the case of PPP projects are also
different.
• A PPP project is viable essentially when a robust business model can be
developed.
• The focus of a PPP project should not be on delivering a particular class/type
of assets but on delivering specified services at defined quantity and levels.
• The risk allocation between the partners is at the heart of any PPP contract
design and is more complex than that of a conventional construction
project. Both partners should clearly understand the various risks involved
and agree to an allocation of risks between them.
• A PPP contract generally has a much longer tenure than a construction
contract. Managing the relationship between the private company and the
5
implementing agency over the contract tenure is vital for the success of a
PPP project.
Models of PPP :
A wide spectrum of PPP models has emerged. These models vary mainly by:
• Ownership of capital assets;
• Responsibility for investment;
• Assumption of risks; and
• Duration of contract.
The PPP models can be classified into five broad categories in order of
generally (but not always) increased involvement and assumption of risks
by the private sector. The five broad categories are:
• Supply and management contracts
• Turnkey contracts
• Afterimage/Lease
• Concessions
• Private Finance Initiative (PFI) and Private ownership.
The basic features of these five categories of PPP models are shown in figure (1).
6
Fig.(1): Basic Feature of PPP Models [3]
RISK CATEGORIES
Identifying and sharing risk in PPP projects are essential for the success of the
partnership and project. Risk is something that creates or suggests a hazard, which
might include delays in construction schedule and cost overruns. A significant feature
of the PPP approach is that while the allocation of risk is to the partner (private or
public) most able to manage that risk, however no party is immune from risks
entirely. Understanding and addressing the risks of a PPP project early on is essential
for the success of the partnership both (Public and Private sector) in PPP Project.
Here some of the risks involved and actions that can be taken to mitigate them.
Investors would desire to invest in a project only if the risks in the project are less
than the reward which the project fetches.
PPP projects carry several risks that are unique to this type of delivery system
in addition to the risks associated with more traditional assignments. Some of the risks
in PPP are [7]:
1. Market and revenue risks.
2. Design risks
3. Construction risks
4. Operating risks
5. Financial risks
6. Political risks
7. Legal risks
8. Environment risks
9. Force Majeure risks.
7
These above risks were categorized in following figure (2):
Fig. (2): Risks in PPP Projects
Source: designed by the Author
1. Market and Revenue risks:
Revenue risk is the uncertainty in relation to the revenue that a project would
actually generate. The market and revenue risks that a PPP project may face can be
grouped into the three broad areas discussed below.
Force
Majeure
risks
Environment
risks
Legal risks
Political risks
Financial risks
Operating risks
Construction
risks
Design risks
Market and
revenue risks
Risks
8
i. Insufficient Income from Fares or Tolls:
In the case of a PPP project operating under a government concession, it
would be expected that the concession company would request a cash
compensation from the government for a deficiency in income from fares or tolls,
request authority to increase tolls or fares, or extend the concession period. Here
it is necessary to identify its risks clearly with respect to cash flow or its returns,
as they may be affected by an extended concession period.
ii. Insufficient Income from Other Operations:
In this risk, similar opportunities exist for requesting the government to
provide cash compensation for deficiencies and/or extending the concession
period. In addition, the concession company would have opportunities to increase
rents or pursue different business strategies, including alternate uses of major
portions of the concession facility.
iii. Insufficient Traffic:
It is important for the PPP contractor to obtain a commitment from the
government, to the extent possible, with respect to anticipated traffic levels and to
negotiate a sufficient compensation arrangement for deficiencies. In the event
that the government has not offered to provide such additional compensation,
needs review its role carefully as it relates to traffic and earnings forecasts for a
PPP project.
2. Design Risks:
This risk relates to any defect in the design of the infrastructure facility or the
design requirements stipulated for the project. This is an inherent risk in the project as
it is very difficult to conclusively ascertain that damage to the facility is actually
caused due to the defect in the design parameters or the very design itself. Generally it
is the design contractor who is responsible for the design aspects of the project. In the
event of the design parameters being stipulated by the grantor of the concession or
license, the risk would be within the control of the grantor.
3. Construction Risks:
9
The construction risks are essentially a bundle of various individual risk
factors that adversely affect the construction of a project within the time frame and
costs projected and at the standards specified for the facility. Construction risks are
associated with PPP projects, more traditional construction projects and the simpler
forms of design/build projects. They include:
i. Land Expropriation.
These risks may flow to both the government and concession company.
Available actions include claims under expropriation legislation or claims by the
concession company of liquidated damages from the contractor.
ii. Cost Overruns and Time and Quality:
These risks affect the concession company directly. The available actions
are to either claim liquidated damages from the contractor or draw down standby
finance from the project lenders. (A major issue is that design requirements in
PPP projects are different than those for a traditional owner.)
iii. Cost and Scope of Identified but Unspecified Work and Variations:
These risks flow directly to the contractor and the concession company
and represent a potential area of future disputes.
iv. Increased Financing Costs:
This risk flows directly to the concession company, which may attempt to
mitigate the risk either by a new injection of equity or subordinated debt from the
sponsors. Alternatively, the concession company may draw down standby finance
from project lenders.
v. Contractor Default:
This is a risk to the concession company, which may claim liquidated
damages from the contractor or make a claim against the contractor’s
performance bond and bonding company.
11
vi. Default by Concession Company:
This is the flip side of the prior risk. This risk is to the contractor, with
the primary mitigating measure being claim of liquidated damages from the
concession company.
vii. Environmental Damage:
This risk accrues to the concession company primarily and may result
in claims on insurers or the party causing the damage.
viii. Force Majeure Event:
This risk accrues to the concession company primarily and would
result typically in a claim to the project insurers.
4. Operating Risks:
Some of the risks that we may face in a PPP project apply also when we are
providing operations and maintenance (O&M) -type services. Except for termination
of the concession by the concession company, these risks flow directly to the
concession company. Some of the risks and actions available to the concession
company include:
a. Performance risk: The completed facility cannot be effectively operated or
maintained to produce the expected capacity, output or efficiency.
b. Operation cost overrun: The operating costs exceed the original estimates
c. Operating Contractor Default: The concession company may terminate the
operations and maintenance contract and appoint a new O&M contractor
d. Force Majeure or Environmental Damage: In this type of event, the
concession company would most likely place a claim with its insurers because
risks of this type would be normally insurable.
e. Default: The default may be caused by the actions of a third party, in which
case the concession company could make claims of damages against that
party.
f.
11
5. Financial Risks:
a. Exchange rate risk:
Relates to the possibility that changes in foreign exchange rates alter the
exchange value of cash flows from the project. Prices and user fees charged to
local users or customers will most likely be paid for in local currency, while the
loan facilities and sometimes also equipment or fuel costs may be denominated in
foreign currency. This risk may be considerable, since exchange rates are
particularly unstable in many developing countries or countries whose economies
are in transition. In addition to exchange rate fluctuations, the project company
may face the risk that foreign exchange control or lowering reserves of foreign
exchange may limit the availability in the local market of foreign currency
needed by the project company to service its debt or repay the original
investment.
b. Interest rate risk:
Force the project to bear additional financing costs. This risk may be
significant in infrastructure projects given the usually large sums borrowed and
the long duration of projects, with some loans extending over a period of several
years. Loans are often given at a fixed rate of interest (for example, fixed-rate
bonds) to reduce the interest rate risk. In addition, the finance package may
include hedging facilities against interest rate risks, for example, by way of
interest rate swaps or interest rate caps.
6. Political Risks:
The project company and the lenders face the risk that the project
execution may be negatively affected by acts of the contracting authority
(Government), another agency of the Government or the host country’s legislature.
Such risks are often referred to as political risks
12
Nationalization of project
Changes in law
Development approvals
Adverse government action or inaction
Payment failure by government
Increases in taxes
Political force majeure (including changes in government)
Termination of concession by government (or unplanned competition).
7. Legal Risks:
Some of the legal risks that a PPP project can face are related to:
Title/lease of property
Ownership of assets
Corporate and security structure
Financial failure or insolvency of concession company
Breach of financing documents
Enforceability of security.
8. Environment Risk:
These are risks relating to occurrence of environmental incidents during the
course of implementation of the project. These risks are generally within the control
of the construction, and the operation and maintenance consortium. This risk has
increased due to the presence of strict legal liability in relation to such environmental
incidents, which can result not only in adverse affects on the financials of a project
but may also cause a closure of any work or operations of and in relation to the
facility.
9. Force Majeure Risks:
These risks are regarding the events that are outside the control of any party and
cannot be reasonably prevented by the concerned party. These risks generally arise
due to causes extraneous to the project. The defining of force majeure events, these
include:
13
Natural force majeure events
Direct political force majeure events
Indirect political force majeure events
a. Natural force majeure events: It comprise of all events that can be attributed to
natural conditions or acts of God such as earthquakes, floods, cyclones and
typhoons. These risks should be shared equally among the parties.
b. Direct political force majeure events: They are events attributable to political
events that are specific to the project itself such as exploration, nationalization.
c. Indirect political force majeure events: They are events that have their origins
in political events but are not project specific such as war, riots etc.
However, the mechanism of managing and mitigating such risks cannot be
categorically stated as they vary with each project and the circumstances surrounding
each project.
PEST framework of risk factors could play an important role for developing
risk management strategies. To develop a risk framework (PEST) by categorizing PPP
risk factors into four groups: Political, Economic, Socio-Cultural and Technical
The risks can be properly allocated by preplanning and sharing resources
between the parties involved. The public agencies primarily assumes risk during the
project scope and definition and are primarily responsible for activities associated
with environmental clearance, right of way acquisition, conceptual engineering,
forecasting demand and revenue, financial feasibility analysis, agency permitting,
political and stakeholder commitment and any necessary enabling legislation.
Li et al. (2005) has conducted a survey on risk allocation FROM Investor's
View showed that the political risks should be retained by the public partner and most
of the project-specific risks should be allocated to the private partner. The risk factors
such as force majeure and changes in law should be shared by both parties. The risk
allocation strongly depends on specific project circumstances like the level of the
public support, project approval and permit, the contract variation and the lack of
experience with PPP. A standard model of risk allocation is not possible, because
projects differ widely [3].
14
Table (1) shows the risk factors categorized in the PEST framework. This
table also shows which party (public, private or both) bears the risks. For example,
direct political risk is categorized under Political (P) risks which the public sector is
mostly responsible for. Most of the technical risks related to project management lie
in the contractor's part, hence the private party bears these technical risks. This may
vary according to project type and size. For example, in the 772 Malaysian Highway
Project, the construction risk was shared due the complexity and geotechnical risk of
the project. Both the public and private parties bear the risks categorized under the
socio-cultural, for example risk factors such as moral hazard, environmental and
environmental justice. This will allow the different parties to know where most of the
risks lie, and which party the risks are associated with.
Table (1): Categorization of risks under PEST along with party
bearing the risk [8]
PEST RISK PUBLIC PRIVATE SHARED
Po
liti
ca
l R
isks
(P)
Direct political X
Political Decision making X
Competing facilities X
Regulatory Protectionism X X
Legislation change X
Eco
no
mic
Ris
ks
(E)
Pre-investment X
Tolls Revenue X
Financial X
Cost overrun X
So
cio
-Cu
ltu
ral R
isks
(S)
Public opinion X
Environmental X
Moral Hazard X
Partnering X
15
Environmental Justice X T
ech
nic
al
Ris
ks
(T)
Project management X
Construction X
Design and latent defect X
Environmental X
Technology X
Force majeure X
Physical X
As the PEST framework suggests, the risk factors as shown in Table (1), can
also be categorized according to which phase the risk lies in. The four phases of
construction are Planning, Pre-construction, Construction and Operation and
Maintenance [9]. Table (2) shows the categorization of risk factors into phases of
construction where the risk is most likely to occur. The Planning phase is the first
stage of construction project which includes the identification of the location and pre-
design of the building or facility. In this stage, the project details are not yet defined
and environmental reviews are incomplete. The public support and funding is also not
committed in this stage. The risks include uncertain political and public support and
competing interests and competing projects. The Pre-construction phase involves
defining project goals (project scope, cost and schedule well defined), environmental
reviews, initial approvals such as those of construction approvals, including permits
and agreements. The issues include the land uses risks, changes in design
requirements, environmental issues that could build up during the project, funding
uncertainty, market conditions and permit requirements. The Construction phase starts
when the design is complete along with the funding and policy. There could be issues
of contractor performance, construction quality, technological advancement, final
permitting, and changes in design and unanticipated site/working conditions. Once all
construction is complete, the operation and maintenance phase of a construction
project begins. This is a stage where there could be risk of whether the toll revenues
16
will be enough to recover the cost of the highway project or not and risk of
environmental issues lie.
Table (2): Risk factors from PEST framework into different phases of construction
Planning Pre-Construction Construction
Operation &
Maintenance
Political Risks
Direct Political
Political Decision Making
Protectionisms
Legislation Change
Regulatory
Competing Facilities
Economic Risks
Pre-Investment
Tolls Revenue
Financial
Cost Overrun
Socio-cultural
Risks
Public Opinion
Land Uses
Moral Hazard Environmental
Partnering
Environmental Justice
Technical Risks
Project Management
Construction
Design and Latent Effect
Technology
Force Majeure
Physical
Table (2) shown the Risk factors from PEST framework into different phases
of construction. The PEST framework also proposes that the risk factors can show
risk dependencies within the category. The state diagram has been implemented to
show the dependencies of each risk factor within the category. State diagrams are
used to describe the behavior of a system [10]. State diagrams describe all of the
possible states of an object as events occur. State diagrams are mostly used in
computer science to describe behavior of systems.
17
CONCLUSIONS
The primary motivation for using PPP is due to the failing of the traditional
approach to adequately fund transportation project delivery. One of the major benefits
of using PPP projects is that the risks involved can be managed by allocating expected
risks to the party who is best able to manage them. The risks identified during the PPP
highway construction projects are categorized in PEST framework based on Political,
Economic, Socio-cultural and Technical risks. The PEST framework categorizes the
different risk factors according to parties responsible for risk management; different
phases of construction: planning, pre-construction, construction, or operation and
maintenance or; project types: greenfield or brownfield; and according to risk
dependencies: independent, contingent or mutually exclusive. By illustrating risks
according to types of projects, phases of construction and risk dependencies gives
visual understanding of risk distribution for contingency planning. The risk
categorization can help practitioners on evaluating risks as a category and devise
common risk mitigation strategies adding value to risk analysis.
The analytical tools such as influence diagram and state diagram further expands in
analyzing the risks identified by visual representation. The PEST framework when
analyzed based on these tools helps identify the risks impact and dependencies. This
categorization of risk factors can also help identify the parties involved (public or
private) that assume the most risk based on different phases of highway construction
and the type of risk involved within it.
Due to the lack of substantial project quantitative data, this paper is limited to
assumption of possible risks and its dependencies during a PPP project. Mixed
methods of data collections including surveys can be used to quantify the risk factors
and determine the probabilities of risk occurrence. Further studies could also include
the risk analysis of the data that are outcome of the risk factors which have been
categorized in the four groups in this research.
References:
1. Nevena Vajdić. (2011), " Risk Management in Public – Private Partnership
Road Projects using the Real Options Theory", International Symposium
18
Engineering Management And Competitiveness, June 24-25, 2011, Zrenjanin,
Serbia.
2. Mustafa.A. Benhkoma & Mahmoud Elhisnawi, "The Contractual
Arrangements in Construction Projects and the new trends towards the
execution of the project using B.O.T", Tripoli: Dar Elfusiafasa, 2011.
3. Li, B., Akintoye, A., and Cliff, A. (2001). “Value for money and Risk
Allocation Models in Construction Public Private Partnerships Projects.
4. http://www.pppcouncil.ca/aboutPPP_definition.asp). Accessed: 2012.04.13.
5. McQuaid, R.W., 2000, The theory of partnership: Why have partnerships. In:
Public private partnerships: theory and practice in international perspective,
edited by Osborne, S., (New York; London: Routledge), 9-35.
6. Garvin, M. J. and Bosso, D. J. (2008). “Assessing the Effectiveness of
Infrastructure Public-Private Partnership Programs and Projects”, forthcoming
in Public Works Management & Policy.