Procurement of PROJECTS - Philippine Ports Authority
-
Upload
khangminh22 -
Category
Documents
-
view
5 -
download
0
Transcript of Procurement of PROJECTS - Philippine Ports Authority
1
PHILIPPINE BIDDING DOCUMENTS
Procurement of INFRASTRUCTURE
PROJECTS
Government of the Republic of the Philippines
REPAIR/REPLACEMENT OF DAMAGED PCC PAVEMENT AND MOORING BOLLARD OF FERRY LANDING AT PORT CAPINPIN, ORION, BATAAN
(NRP-BAA-02-21)
Sixth Edition
July 2020
2
TABLE OF CONTENTS
Glossary of Terms, Abbreviations, and Acronyms ........................................ 4
Section I. Invitation to Bid ............................................................................... 7
Section II. Instructions to Bidders ................................................................ 10
1. Scope of Bid ..................................................................................................... 111
2. Funding Information ......................................................................................... 111
3. Bidding Requirements ....................................................................................... 111
4. Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices ................. 111
5. Eligible Bidders .................................................................................................. 12
6. Origin of Associated Goods .............................................................................. 122
7. Subcontracts ..................................................................................................... 122
8. Pre-Bid Conference ........................................................................................... 122
9. Clarification and Amendment of Bidding Documents ....................................... 122
10. Documents Comprising the Bid: Eligibility and Technical Components ............ 133
11. Documents Comprising the Bid: Financial Component ....................................... 13
12. Alternative Bids ................................................................................................ 144
13. Bid Prices ......................................................................................................... 144
14. Bid and Payment Currencies ............................................................................. 144
15. Bid Security ...................................................................................................... 144
16. Sealing and Marking of Bids ............................................................................. 144
17. Deadline for Submission of Bids ....................................................................... 155
18. Opening and Preliminary Examination of Bids .................................................. 155
19. Detailed Evaluation and Comparison of Bids .................................................... 155
20. Post Qualification ............................................................................................. 155
21. Signing of the Contract ..................................................................................... 166
Section III. Bid Data Sheet .......................................................................... 177
Section IV. General Conditions of Contract ................................................. 20
1. Scope of Contract................................................................................................ 21
2. Sectional Completion of Works .......................................................................... 21
3. Possession of Site................................................................................................ 21
4. The Contractor’s Obligations .............................................................................. 21
5. Performance Security .......................................................................................... 22
6. Site Investigation Reports ................................................................................... 22
3
7. Warranty ............................................................................................................. 22
8. Liability of the Contractor ................................................................................... 22
9. Termination for Other Causes ............................................................................. 22
10. Dayworks............................................................................................................ 23
11. Program of Work ................................................................................................ 23
12. Instructions, Inspections and Audits .................................................................... 23
13. Advance Payment ............................................................................................... 23
14. Progress Payments .............................................................................................. 23
15. Operating and Maintenance Manuals ................................................................ 244
Section V. Special Conditions of Contract .................................................... 25
Section VI. Specifications ............................................................................ 277
Section VII. Drawings .................................................................................... 42
Section VIII. Bill of Quantities ...................................................................... 45
Section IX. Checklist of Technical and Financial Documents ..................... 48
Section X. Bidding Forms .............................................................................. 51
4
Glossary of
Terms, Abbreviations, and Acronyms
ABC – Approved Budget for the Contract.
ARCC – Allowable Range of Contract Cost.
BAC – Bids and Awards Committee.
Bid – A signed offer or proposal to undertake a contract submitted by a bidder in response to
and in consonance with the requirements of the bidding documents. Also referred to as
Proposal and Tender. (2016 revised IRR, Section 5[c])
Bidder – Refers to a contractor, manufacturer, supplier, distributor and/or consultant who
submits a bid in response to the requirements of the Bidding Documents. (2016 revised IRR,
Section 5[d])
Bidding Documents – The documents issued by the Procuring Entity as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the Goods,
Infrastructure Projects, and/or Consulting Services required by the Procuring Entity. (2016
revised IRR, Section 5[e])
BIR – Bureau of Internal Revenue.
BSP – Bangko Sentral ng Pilipinas.
CDA – Cooperative Development Authority.
Consulting Services – Refer to services for Infrastructure Projects and other types of projects
or activities of the GOP requiring adequate external technical and professional expertise that
are beyond the capability and/or capacity of the GOP to undertake such as, but not limited to:
(i) advisory and review services; (ii) pre-investment or feasibility studies; (iii) design; (iv)
construction supervision; (v) management and related services; and (vi) other technical
services or special studies. (2016 revised IRR, Section 5[i])
Contract – Refers to the agreement entered into between the Procuring Entity and the
Supplier or Manufacturer or Distributor or Service Provider for procurement of Goods and
Services; Contractor for Procurement of Infrastructure Projects; or Consultant or Consulting
Firm for Procurement of Consulting Services; as the case may be, as recorded in the Contract
Form signed by the parties, including all attachments and appendices thereto and all
documents incorporated by reference therein.
Contractor – is a natural or juridical entity whose proposal was accepted by the Procuring
Entity and to whom the Contract to execute the Work was awarded. Contractor as used in
these Bidding Documents may likewise refer to a supplier, distributor, manufacturer, or
consultant.
5
CPI – Consumer Price Index.
DOLE – Department of Labor and Employment.
DTI – Department of Trade and Industry.
Foreign-funded Procurement or Foreign-Assisted Project – Refers to procurement whose
funding source is from a foreign government, foreign or international financing institution as
specified in the Treaty or International or Executive Agreement. (2016 revised IRR, Section
5[b]).
GFI – Government Financial Institution.
GOCC – Government-owned and/or –controlled corporation.
Goods – Refer to all items, supplies, materials and general support services, except
Consulting Services and Infrastructure Projects, which may be needed in the transaction of
public businesses or in the pursuit of any government undertaking, project or activity,
whether in the nature of equipment, furniture, stationery, materials for construction, or
personal property of any kind, including non-personal or contractual services such as the
repair and maintenance of equipment and furniture, as well as trucking, hauling, janitorial,
security, and related or analogous services, as well as procurement of materials and supplies
provided by the Procuring Entity for such services. The term “related” or “analogous
services” shall include, but is not limited to, lease or purchase of office space, media
advertisements, health maintenance services, and other services essential to the operation of
the Procuring Entity. (2016 revised IRR, Section 5[r])
GOP – Government of the Philippines.
Infrastructure Projects – Include the construction, improvement, rehabilitation, demolition,
repair, restoration or maintenance of roads and bridges, railways, airports, seaports,
communication facilities, civil works components of information technology projects,
irrigation, flood control and drainage, water supply, sanitation, sewerage and solid waste
management systems, shore protection, energy/power and electrification facilities, national
buildings, school buildings, hospital buildings, and other related construction projects of the
government. Also referred to as civil works or works. (2016 revised IRR, Section 5[u])
LGUs – Local Government Units.
NFCC – Net Financial Contracting Capacity.
NGA – National Government Agency.
PCAB – Philippine Contractors Accreditation Board.
PhilGEPS - Philippine Government Electronic Procurement System.
Procurement Project – refers to a specific or identified procurement covering goods,
infrastructure project or consulting services. A Procurement Project shall be described,
detailed, and scheduled in the Project Procurement Management Plan prepared by the agency
which shall be consolidated in the procuring entity's Annual Procurement Plan. (GPPB
Circular No. 06-2019 dated 17 July 2019)
6
PSA – Philippine Statistics Authority.
SEC – Securities and Exchange Commission.
SLCC – Single Largest Completed Contract.
UN – United Nations.
8
INVITATION TO BID
FOR THE:
REPAIR/REPLACEMENT OF DAMAGED PCC PAVEMENT AND MOORING BOLLARD OF
FERRY LANDING AT PORT CAPINPIN, ORION, BATAAN (NRP-BAA-02-21)
1. The Philippine Ports Authority – Port Management Office-Bataan/Aurora, through the PPA Corporate Budget of the Authority for CY 2021, intends to apply the sum of Twenty Eight Million Nine Hundred Sixty Eight Thousand Two Hundred Forty One Pesos (P 28,968,241.00) being the Approved Budget for the Contract (ABC) to payments under the contract for the Repair/Replacement of Damaged PCC Pavement and Mooring Bollard of Ferry Landing at Port Capinpin, Orion, Bataan. Bids received in excess of the ABC shall be automatically rejected at bid opening.
2. The Philippine Ports Authority- PMO-Bataan/Aurora now invites bids for the following Scope of Works: A. General Expenses B. Demolition, Excavation and Disposal C. Repair of PCC Pavement along Roadway and Ferry Landing D. Mooring Fixtures
Completion of the Works is required in One Hundred Fifty (150) Calendar Days. Bidders
should have completed a contract similar to the project. The description of an eligible
bidder is contained in the Bidding Documents, particularly, in Section II. Instructions to
Bidders.
3. Bidding will be conducted through open competitive bidding procedures using non-discretionary “Pass/Fail” criterion as also specified in the 2016 Revised IRR of R.A. 9184, otherwise known as the “Government Procurement Reform Act.”
Bidding is restricted to Filipino citizens/sole proprietorships, cooperatives, and
partnerships or organizations with at least seventy five percent (75%) interest or
outstanding capital stock belonging to citizens of the Philippines.
4. Interested bidders may obtain further information from the Bids and Awards Committee, Philippine Ports Authority, Port Management Office- Bataan/Aurora and inspect the Bidding Documents at the address given below from 8:00 a. m. to 5:00 p.m., Monday to Friday.
5. A complete set of Bidding Documents may be acquired by interested Bidders starting August 19, 2021 f rom the address below and upon payment of the applicable fee for the B i dd ing Docum ent s , pu r suant to the l a tes t Gui del i nes i ssued by the GPP B, i n t he am ount o f TW E NTY F IVE THO USAND P ESO S ( P 25 , 000. 00) .
It may also be downloaded free of charge from the website of the Philippine Government
Electronic Procurement System (PhilGEPS) and the website of the Philippine Ports
Authority, provided that bidders shall pay the applicable fee for the Bidding Documents
not later than the submission of their bids.
6. The Philippine Ports Authority- PMO-Bataan/Aurora Bids and Awards Committee for Engineering Projects will hold a Pre-Bid Conference on August 27, 2021 at 3:00 p.m. at PPA-PMO-Bataan, Aurora Conference Hall, Port of Lamao, Limay, Bataan, which shall be
9
open to prospective bidders. All Interested parties who will participate in the Pre-bid Conference and Opening of Bid should possess a proper authorization and company ID.
7. B ids m ust be dul y receiv ed by the BAC Secretar i at on or before 1:30 p .m. o f September 8, 2021 at the Bids and Awards Committee, Philippine Ports Authority, Port Management Office- Bataan/Aurora, POB Bldg, Port of Lamao, Limay, Bataan. All bids must be accompanied by a Bid Security in accordance with Section 27.2 of the Revised IRR of R.A. 9184.
Bid opening shall be on September 8, 2021, 3:00 p.m. at PMO- Bataan/Aurora
Conference Room, Admin. Bldg, Port of Lamao, Limay, Bataan. Bids will be opened in
the presence of the Bidder’s representatives who choose to attend at the address
below. Late bids shall not be accepted.
8. Required PCAB Registration: Small B – General Engineering
Submission of Company Prof i l e i s requi red for new interested bidders whose legal
documents are not yet on file with the PMO-Bataan/Aurora Bids and Awards Committee.
9. The Philippine Ports Authority reserves the right to accept or reject any bid, to annul the bidding process, and to reject all bids at any time prior to contract award in accordance with Section 41 of RA 9184 and its IRR, without thereby incurring any liability to the affected bidder or bidders.
10. For further information, please refer to:
BAC Secretariat, Ms. Alona V. Yumol
Bids and Awards Committee, PPA PMO-Bataan/Aurora
POB Bldg, Port of Lamao, Limay, Bataan
Tel. Nos. (047) 2446936 / (047) 2446246;
PPA Website: www.ppa.com.ph
(SIGNED) NILO RIENZIE H. DEPASUCAT
Chairperson, BAC
Date of Posting: August 19-26, 2021
11
1. Scope of Bid
The Procuring Entity, PHILIPPINE PORTS AURHORITY, PMO –
BATAAN/AURORA invites Bids for the “REPAIR/REPLACEMENT OF
DAMAGED PCC PAVEMENT AND MOORING BOLLARD OF FERRY
LANDING AT PORT OF CAPINPIN, ORION, BATAAN” with Project
Identification Number NRP-BAA-02-21.
The Procurement Project (referred to herein as “Project”) is for the construction of
Works, as described in Section VI (Specifications).
2. Funding Information
2.1. The GOP through the source of funding as indicated below for CY 2021 in the
amount of ₱ 28,968,241.00
2.2. The source of funding is the Corporate Operating Budget.
3. Bidding Requirements
The Bidding for the Project shall be governed by all the provisions of RA No. 9184
and its 2016 revised IRR, including its Generic Procurement Manual and associated
policies, rules and regulations as the primary source thereof, while the herein clauses
shall serve as the secondary source thereof.
Any amendments made to the IRR and other GPPB issuances shall be applicable only
to the ongoing posting, advertisement, or invitation to bid by the BAC through the
issuance of a supplemental or bid bulletin.
The Bidder, by the act of submitting its Bid, shall be deemed to have inspected the
site, determined the general characteristics of the contracted Works and the conditions
for this Project, such as the location and the nature of the work; (b) climatic
conditions; (c) transportation facilities; (c) nature and condition of the terrain,
geological conditions at the site communication facilities, requirements, location and
availability of construction aggregates and other materials, labor, water, electric
power and access roads; and (d) other factors that may affect the cost, duration and
execution or implementation of the contract, project, or work and examine all
instructions, forms, terms, and project requirements in the Bidding Documents.
4. Corrupt, Fraudulent, Collusive, Coercive, and Obstructive Practices
The Procuring Entity, as well as the Bidders and Contractors, shall observe the
highest standard of ethics during the procurement and execution of the contract. They
or through an agent shall not engage in corrupt, fraudulent, collusive, coercive, and
obstructive practices defined under Annex “I” of the 2016 revised IRR of RA No.
9184 or other integrity violations in competing for the Project.
12
5. Eligible Bidders
5.1. Only Bids of Bidders found to be legally, technically, and financially capable
will be evaluated.
5.2. The Bidder must have an experience of having completed a Single Largest
Completed Contract (SLCC) that is similar to this Project, equivalent to at
least fifty percent (50%) of the ABC adjusted, if necessary, by the Bidder to
current prices using the PSA’s CPI, except under conditions provided for in
Section 23.4.2.4 of the 2016 revised IRR of RA No. 9184.
A contract is considered to be “similar” to the contract to be bid if it has the
major categories of work stated in the BDS.
5.3. For Foreign-funded Procurement, the Procuring Entity and the foreign
government/foreign or international financing institution may agree on another
track record requirement, as specified in the Bidding Document prepared for
this purpose.
5.4. The Bidders shall comply with the eligibility criteria under Section 23.4.2 of
the 2016 IRR of RA No. 9184.
6. Origin of Associated Goods
There is no restriction on the origin of Goods other than those prohibited by a
decision of the UN Security Council taken under Chapter VII of the Charter of the
UN.
7. Subcontracts
7.1. The Bidder may subcontract portions of the Project to the extent allowed by
the Procuring Entity as stated herein, but in no case more than fifty percent
(50%) of the Project.
The Procuring Entity has prescribed that:
a. Subcontracting is not allowed.
8. Pre-Bid Conference
The Procuring Entity will hold a pre-bid conference for this Project on August 27,
2021 at 3:00 PM at PPA, PMO-Bataan/Aurora Conference Hall, Port of Lamao,
Limay, Bataan, as indicated in paragraph 6 of the IB.
1. Clarification and Amendment of Bidding Documents
Prospective bidders may request for clarification on and/or interpretation of any part
of the Bidding Documents. Such requests must be in writing and received by the
Procuring Entity, either at its given address or through electronic mail indicated in the
13
IB, at least ten (10) calendar days before the deadline set for the submission and
receipt of Bids.
2. Documents Comprising the Bid: Eligibility and Technical
Components
10.1. The first envelope shall contain the eligibility and technical documents of the
Bid as specified in Section IX. Checklist of Technical and Financial
Documents.
10.2. If the eligibility requirements or statements, the bids, and all other documents
for submission to the BAC are in foreign language other than English, it must
be accompanied by a translation in English, which shall be authenticated by
the appropriate Philippine foreign service establishment, post, or the
equivalent office having jurisdiction over the foreign bidder’s affairs in the
Philippines. For Contracting Parties to the Apostille Convention, only the
translated documents shall be authenticated through an apostille pursuant to
GPPB Resolution No. 13-2019 dated 23 May 2019. The English translation
shall govern, for purposes of interpretation of the bid.
10.3. A valid PCAB License is required, and in case of joint ventures, a valid
special PCAB License, and registration for the type and cost of the contract for
this Project. Any additional type of Contractor license or permit shall be
indicated in the BDS.
10.4. A List of Contractor’s key personnel (e.g., Project Manager, Project
Engineers, Materials Engineers, and Foremen) assigned to the contract to be
bid, with their complete qualification and experience data shall be provided.
These key personnel must meet the required minimum years of experience set
in the BDS.
10.5. A List of Contractor’s major equipment units, which are owned, leased, and/or
under purchase agreements, supported by proof of ownership, certification of
availability of equipment from the equipment lessor/vendor for the duration of
the project, as the case may be, must meet the minimum requirements for the
contract set in the BDS.
3. Documents Comprising the Bid: Financial Component
11.1. The second bid envelope shall contain the financial documents for the Bid as
specified in Section IX. Checklist of Technical and Financial Documents.
11.2. Any bid exceeding the ABC indicated in paragraph 1 of the IB shall not be
accepted.
11.3. For Foreign-funded procurement, a ceiling may be applied to bid prices
provided the conditions are met under Section 31.2 of the 2016 revised IRR of
RA No. 9184.
14
4. Alternative Bids
Bidders shall submit offers that comply with the requirements of the Bidding
Documents, including the basic technical design as indicated in the drawings and
specifications. Unless there is a value engineering clause in the BDS, alternative Bids
shall not be accepted.
5. Bid Prices
All bid prices for the given scope of work in the Project as awarded shall be
considered as fixed prices, and therefore not subject to price escalation during
contract implementation, except under extraordinary circumstances as determined by
the NEDA and approved by the GPPB pursuant to the revised Guidelines for Contract
Price Escalation guidelines.
6. Bid and Payment Currencies
14.1. Bid prices may be quoted in the local currency or tradeable currency accepted
by the BSP at the discretion of the Bidder. However, for purposes of bid
evaluation, Bids denominated in foreign currencies shall be converted to
Philippine currency based on the exchange rate as published in the BSP
reference rate bulletin on the day of the bid opening.
14.2. Payment of the contract price shall be made in:
a. Philippine Pesos.
7. Bid Security
15.1. The Bidder shall submit a Bid Securing Declaration or any form of Bid
Security in the amount indicated in the BDS, which shall be not less than the
percentage of the ABC in accordance with the schedule in the BDS.
15.2. The Bid and bid security shall be valid until One Hundred Twenty (120)
days from the date set for Bid Opening. Any bid not accompanied by an
acceptable bid security shall be rejected by the Procuring Entity as non-
responsive.
8. Sealing and Marking of Bids
Each Bidder shall submit one copy of the first and second components of its Bid.
The Procuring Entity may request additional hard copies and/or electronic copies of
the Bid. However, failure of the Bidders to comply with the said request shall not be a
ground for disqualification.
15
If the Procuring Entity allows the submission of bids through online submission to the
given website or any other electronic means, the Bidder shall submit an electronic
copy of its Bid, which must be digitally signed. An electronic copy that cannot be
opened or is corrupted shall be considered non-responsive and, thus, automatically
disqualified.
9. Deadline for Submission of Bids
The Bidders shall submit on or be fo re 1:30 p.m. of September 8, 2021 at the
Bids and Awards Committee, Philippine Ports Authority, Port Management
Office- Bataan/Aurora, POB Bldg, Port of Lamao, Limay, Bataan, as indicated in
paragraph 7 of the IB.
10. Opening and Preliminary Examination of Bids
18.1. The BAC shall open the Bids in public at September 8, 2021, 3:00 p.m. at
PMO- Bataan/Aurora Conference Room, Admin. Bldg, Port of Lamao,
Limay, Bataan. The Bidders’ representatives who are present shall sign a
register evidencing their attendance. In case videoconferencing, webcasting or
other similar technologies will be used, attendance of participants shall
likewise be recorded by the BAC Secretariat.
In case the Bids cannot be opened as scheduled due to justifiable reasons, the
rescheduling requirements under Section 29 of the 2016 revised IRR of RA
No. 9184 shall prevail.
18.2. The preliminary examination of Bids shall be governed by Section 30 of the
2016 revised IRR of RA No. 9184.
11. Detailed Evaluation and Comparison of Bids
19.1. The Procuring Entity’s BAC shall immediately conduct a detailed evaluation
of all Bids rated “passed” using non-discretionary pass/fail criteria. The BAC
shall consider the conditions in the evaluation of Bids under Section 32.2 of
2016 revised IRR of RA No. 9184.
19.2. If the Project allows partial bids, all Bids and combinations of Bids as
indicated in the BDS shall be received by the same deadline and opened and
evaluated simultaneously so as to determine the Bid or combination of Bids
offering the lowest calculated cost to the Procuring Entity. Bid Security as
required by ITB Clause 15 shall be submitted for each contract (lot)
separately.
19.3. In all cases, the NFCC computation pursuant to Section 23.4.2.6 of the 2016
revised IRR of RA No. 9184 must be sufficient for the total of the ABCs for
all the lots participated in by the prospective Bidder.
12. Post Qualification
16
Within a non-extendible period of five (5) calendar days from receipt by the Bidder of
the notice from the BAC that it submitted the Lowest Calculated Bid, the Bidder shall
submit its latest income and business tax returns filed and paid through the BIR
Electronic Filing and Payment System (eFPS), and other appropriate licenses and
permits required by law and stated in the BDS.
13. Signing of the Contract
The documents required in Section 37.2 of the 2016 revised IRR of RA No. 9184
shall form part of the Contract. Additional Contract documents are indicated in the
BDS.
18
Bid Data Sheet ITB Clause
5.2 For this purpose, contracts similar to the Project refer to contracts which have
the same major categories of work, which shall be:
Description/Clarification Unit of Measure Quantity
(at least)
Demolition Works sq.m 3000
Concreting Works cu.m 900
7.1
Portion of Works allowed to be
subcontracted:
Subcontracting is not allowed
Maximum Percentage allowed to be
subcontracted:
Subcontracting is not allowed
10.3 No Further instructions.
10.4
The key personnel must meet the required minimum years of experience set
below:
Key Personnel
a. Project Manager
b. Project Engineer
c. Materials Engineer
d. Construction Safety
and Health Officer
e. Foreman
General Experience Relevant Experience
(Minimum)
Five (5) years
Three (3) years
One (1) year
One (1) year
Five (5) years
10.5 The minimum major equipment requirements are the following:
Equipment Capacity Number of Units
Hydraulic Breaker N/A 1 unit
Concrete Cutter 7.5HP 1 unit
Backhoe 1.0cu.m – 128HP 1 unit
Oxy/Acetylene Cutting
Outfit
N/A 1 unit
Portable Jack Hammer N/A 1 unit
Dump Truck 12cu.m – 290HP 1 unit
Boom Truck 10 Tons 1 unit
Road Roller 3.5 Tons 1 unit
Road Grader 125HP 1 unit
Plate Compactor 5HP 1 unit
Water Truck 1000Gal 1 unit
Concrete Screeder N/A 1 unit
Concrete Vibrator N/A 1 unit
Welding Machine N/A 1 unit
Electric Grinder N/A 1 unit
Electric Drill N/A 1 unit
Electric Bar Cutter N/A 1 unit
Electric Bar Bender N/A 1 unit
19
H-Frame Scaffolding N/A 1 lot
12 Value Engineering Clause:
Not Allowed.
15.1 The bid security shall be in the form of a Bid Securing Declaration or any of
the following forms and amounts:
a. The amount of not less than ₱ 579,364.82 if bid security is in cash,
cashier’s/manager’s check, bank draft/guarantee or irrevocable letter of
credit;
b. The amount of not less than ₱ 1,448,412.05 if bid security is in Surety
Bond.
16 Each bidder shall submit One (1) original and Two (2) hard copies of the
Technical and Financial components envelope of its bid. The original and the
copies of the bid documents should be properly labeled on the cover indicating
thereon the name of the project, contact number, name and address of the
contractor and name and address of the implementing agency and which
should be book bound with cover.
19.2 Partial bids:
Not allowed.
20 Other appropriate license and permits required:
None
21
Additional contract documents are as follows:
1. Construction Schedule and S-curve
2. Manpower Schedule
3. Construction Methods
4. Equipment Utilization Schedule
5. Construction Safety and Health Program approved by the
Department of Labor and Employment, and PERT/CPM.
6. Other acceptable tools of project scheduling
21
1. Scope of Contract
This Contract shall include all such items, although not specifically mentioned, that
can be reasonably inferred as being required for its completion as if such items were
expressly mentioned herein. All the provisions of RA No. 9184 and its 2016 revised
IRR, including the Generic Procurement Manual, and associated issuances, constitute
the primary source for the terms and conditions of the Contract, and thus, applicable
in contract implementation. Herein clauses shall serve as the secondary source for the
terms and conditions of the Contract.
This is without prejudice to Sections 74.1 and 74.2 of the 2016 revised IRR of RA
No. 9184 allowing the GPPB to amend the IRR, which shall be applied to all
procurement activities, the advertisement, posting, or invitation of which were issued
after the effectivity of the said amendment.
2. Sectional Completion of Works
If sectional completion is specified in the Special Conditions of Contract (SCC),
references in the Conditions of Contract to the Works, the Completion Date, and the
Intended Completion Date shall apply to any Section of the Works (other than
references to the Completion Date and Intended Completion Date for the whole of the
Works).
3. Possession of Site
3.1 The Procuring Entity shall give possession of all or parts of the Site to the
Contractor based on the schedule of delivery indicated in the SCC, which
corresponds to the execution of the Works. If the Contractor suffers delay or
incurs cost from failure on the part of the Procuring Entity to give possession
in accordance with the terms of this clause, the Procuring Entity’s
Representative shall give the Contractor a Contract Time Extension and certify
such sum as fair to cover the cost incurred, which sum shall be paid by
Procuring Entity.
3.2 If possession of a portion is not given by the above date, the Procuring Entity
will be deemed to have delayed the start of the relevant activities. The
resulting adjustments in contract time to address such delay may be addressed
through contract extension provided under Annex “E” of the 2016 revised IRR
of RA No. 9184.
4. The Contractor’s Obligations
The Contractor shall employ the key personnel named in the Schedule of Key
Personnel indicating their designation, in accordance with ITB Clause 10.3 and
specified in the BDS, to carry out the supervision of the Works.
The Procuring Entity will approve any proposed replacement of key personnel only if
their relevant qualifications and abilities are equal to or better than those of the
personnel listed in the Schedule.
22
5. Performance Security
5.1. Within ten (10) calendar days from receipt of the Notice of Award from the
Procuring Entity but in no case later than the signing of the contract by both
parties, the successful Bidder shall furnish the performance security in any of
the forms prescribed in Section 39 of the 2016 revised IRR.
5.2. The Contractor, by entering into the Contract with the Procuring Entity,
acknowledges the right of the Procuring Entity to institute action pursuant to
RA No. 3688 against any subcontractor be they an individual, firm,
partnership, corporation, or association supplying the Contractor with labor,
materials and/or equipment for the performance of this Contract.
6. Site Investigation Reports
The Contractor, in preparing the Bid, shall rely on any Site Investigation Reports
referred to in the SCC supplemented by any information obtained by the Contractor.
7. Warranty
7.1. In case the Contractor fails to undertake the repair works under Section 62.2.2
of the 2016 revised IRR, the Procuring Entity shall forfeit its performance
security, subject its property(ies) to attachment or garnishment proceedings,
and perpetually disqualify it from participating in any public bidding. All
payables of the GOP in his favor shall be offset to recover the costs.
7.2. The warranty against Structural Defects/Failures, except that occasioned-on
force majeure, shall cover the period from the date of issuance of the
Certificate of Final Acceptance by the Procuring Entity. Specific duration of
the warranty is found in the SCC.
8. Liability of the Contractor
Subject to additional provisions, if any, set forth in the SCC, the Contractor’s liability
under this Contract shall be as provided by the laws of the Republic of the
Philippines.
If the Contractor is a joint venture, all partners to the joint venture shall be jointly and
severally liable to the Procuring Entity.
9. Termination for Other Causes
Contract termination shall be initiated in case it is determined prima facie by the
Procuring Entity that the Contractor has engaged, before, or during the
implementation of the contract, in unlawful deeds and behaviors relative to contract
acquisition and implementation, such as, but not limited to corrupt, fraudulent,
collusive, coercive, and obstructive practices as stated in ITB Clause 4.
23
10. Dayworks
Subject to the guidelines on Variation Order in Annex “E” of the 2016 revised IRR of
RA No. 9184, and if applicable as indicated in the SCC, the Dayworks rates in the
Contractor’s Bid shall be used for small additional amounts of work only when the
Procuring Entity’s Representative has given written instructions in advance for
additional work to be paid for in that way.
11. Program of Work
11.1. The Contractor shall submit to the Procuring Entity’s Representative for
approval the said Program of Work showing the general methods,
arrangements, order, and timing for all the activities in the Works. The
submissions of the Program of Work are indicated in the SCC.
11.2. The Contractor shall submit to the Procuring Entity’s Representative for
approval an updated Program of Work at intervals no longer than the period
stated in the SCC. If the Contractor does not submit an updated Program of
Work within this period, the Procuring Entity’s Representative may withhold
the amount stated in the SCC from the next payment certificate and continue
to withhold this amount until the next payment after the date on which the
overdue Program of Work has been submitted.
12. Instructions, Inspections and Audits
The Contractor shall permit the GOP or the Procuring Entity to inspect the
Contractor’s accounts and records relating to the performance of the Contractor and to
have them audited by auditors of the GOP or the Procuring Entity, as may be
required.
13. Advance Payment
The Procuring Entity shall, upon a written request of the Contractor which shall be
submitted as a Contract document, make an advance payment to the Contractor in an
amount not exceeding fifteen percent (15%) of the total contract price, to be made in
lump sum, or at the most two installments according to a schedule specified in the
SCC, subject to the requirements in Annex “E” of the 2016 revised IRR of RA No.
9184.
14. Progress Payments
The Contractor may submit a request for payment for Work accomplished. Such
requests for payment shall be verified and certified by the Procuring Entity’s
Representative/Project Engineer. Except as otherwise stipulated in the SCC,
materials and equipment delivered on the site but not completely put in place shall not
be included for payment.
24
15. Operating and Maintenance Manuals
15.1. If required, the Contractor will provide “as built” Drawings and/or operating
and maintenance manuals as specified in the SCC.
15.2. If the Contractor does not provide the Drawings and/or manuals by the dates
stated above, or they do not receive the Procuring Entity’s Representative’s
approval, the Procuring Entity’s Representative may withhold the amount
stated in the SCC from payments due to the Contractor.
26
Special Conditions of Contract
GCC Clause
2 Sectional Completion
None.
4.1 The Procuring Entity shall give possession of all parts of the Site to the
Contractor upon commencement of the project.
6 The site investigation reports:
None.
7.2 Buildings of types 1, 2, and 3 as classified under the National Building
Code of the Philippines, concrete/asphalt roads, concrete river control,
drainage, irrigation lined canals, river landing, deep wells, rock
causeway, pedestrian overpass, and other similar semi-permanent
structures: Five (5) years.
10 No dayworks are applicable to the contract.
11.1 The Contractor shall submit the Program of Work to the Procuring
Entity’s Representative within _________ days of delivery of the Notice
of Award.
11.2 The amount to be withheld for late submission of an updated Program of
Work is __________.
13 The provision on advance payments or mobilization fees in the terms
and conditions of all contracts/ purchase orders/ job orders for goods,
services and infrastructure projects that will be signed or executed shall
henceforth be excluded.
14 No further instructions.
15.1 The date by which operating and maintenance manuals are required is
__________.
The date by which “as built” drawings are required is __________.
15.2 The amount to be withheld for failing to produce “as built” drawings
and/or operating and maintenance manuals by the date required is
amount of final billing.
29
REINFORCED CONCRETE
GENERAL
All works falling under this category shall include reinforced concrete for all kinds and parts
of any reinforced concrete structure.
MATERIALS
a. Cement
Cement used shall be Type I Portland conforming to the requirements of the
latest revision of ASTM C 150 “Standard Specifications for Portland cement”.
b. Coarse Aggregates
Coarse Aggregates shall be washed, well graded, hard pieces of gravel,
crushed gravel or rock conforming to the requirements of ASTM C 33
“Standard Specification for Concrete Aggregates”.
c. Fine Aggregates
Fine Aggregates shall be washed sand, stone screenings or other inert
materials of same characteristics, or any combination thereof composed clean,
hard, strong, uncoated grains and free from injurious amount of dust, lumps of
clay, shale, alkali, and organic matter. It shall conform to the requirements of
ASTM C33 “Standard Specifications for Concrete Aggregates”. Beach sand
shall not be used unless approved by the Engineer.
d. Admixtures
Unless otherwise required by field conditions admixtures may be used subject
to the expressed approval of the Engineer. The cost thereof shall be
considered as already included in the unit cost bid of the Contractor for the
concrete.
STORAGE OF MATERIALS
a. Cement shall be stockpiled as closely as possible in weatherproof storage
sheds, stacks suitably elevated above ground to prevent cement absorption of
moisture.
b. Aggregates shall be placed in stockpile in a manner preventing segregation
thereof and contamination with foreign materials.
c. Reinforcing steel bars shall be stored properly, covered and protected from
humidity to prevent rusting and contamination with oil, dirt or other
objectionable matters.
DESIGNED STRENGTH OF CONCRETE
Concrete for non-structural parts or members such as partition walls and slab on fill
shall develop a minimum 28-day cylinder strength of 3,500 psi. unless otherwise
indicated in the drawings.
TRIAL BATCH FOR CONCRETE
30
Thirty (30) calendar days before the start of concreting works, the Contractor shall
submit design mixes and the corresponding test result made on sample thereof.
Sampling and testing shall be in accordance with the ASTM Standard procedures for
sampling and testing, for the particular design strength(s) required.
The particulars of the mix such as the slump and the proportionate weights of cement,
saturated surface dry aggregates and water used shall be stated. Test results shall
show 28-day strength(s) fifteen (15%) percent higher than the ultimate strength(s)
required.
CONCRETE PROPORTION AND CONSISTENCY
Concrete proportion should produce mix consistencies that will work readily into
angles and corners of the forms and around reinforcements irrespective of the method
of placing employed, without permitting the materials to segregate or excess water to
collect on the surface of the concrete and with separated individual particles of
aggregates showing coating of mortar with proportionate amount of sand. The total
aggregate in the proportion used shall be such that when sieved, the weight passing
the No. 4 standard sieve shall be thirty percent (30%) of the total.
The methods used for measuring materials going into the concrete mix shall permit
easy checking and control of proportions at any time during the work.
MIXING OF CONCRETE
All concrete used shall be machine-mixed at the site. Each batch shall be mixed at the
mixer’s design speed, for at least 1-1/2 minutes after all concrete materials are
simultaneously placed in the mixer. The ideal rotation speed of the mixer shall be
between 14 and 20 rpm.
All mix contents of the mixer shall be thoroughly removed before any succeeding
batch is placed.
The materials for the first batch shall contain sufficiently excess cement, sand and
water to coat the inside walls of the mixer without reducing the required mortar
content of the mix.
The mixer shall be provided with devices for accurately measuring and controlling the
amount of water used in each batch and for automatically recording the number of
revolutions of the mixer.
Hand mixing of concrete will only be allowed in case of mixer breakdown, in which
case it shall be stopped as soon as pouring for the particular section is completed, or at
a construction joint as directed by the Engineer.
Retempering or remixing of partially hardened concrete with the addition of water
will not be permitted.
PLACING OF CONCRETE
31
a. Concrete shall be placed in the presence of the Engineer only after the forms,
reinforcing bars and other spaces to receive the concrete have been inspected
and approved by him.
b. Concrete shall be placed only when wind and weather conditions will allow
proper placement and curing of the concrete. Notice of any concreting
operations shall be served to the Engineer at least three (3) days ahead of each
schedule.
c. Mixed concrete shall be deposited in its final position within a practicable
time. Each succeeding fresh deposit for particular structural member shall be
placed at a practicable rate to prevent cold joints. Each successive fresh
deposit of concrete shall be vibrated vertically at uniformly spaced points and
levels, of such duration and intensity to compact the concrete thoroughly but
shall be discontinued the moment segregation of materials is noticed.
d. Where concreting operations involve a fall more than 1.50meters (4.92 feet),
the fresh concrete shall be poured through approved sheet metal conduit or
pipes. The pipes shall be kept full of concrete and its lower end kept below
the surface of concrete throughout the pouring operations.
e. Deposition of concrete shall be in such a way as to prevent segregation of the
materials and the displacement of the reinforcement. Placing shall be done
preferably with the use of buggies, buckets or wheel-borrows. Troughs,
conveyors and pipes and the manner of use of each one shall be with the
expressed permission of the Engineer.
f. Each layer of concrete shall be placed approximately normal as possible in
uniform layers not exceeding 0.30 meter, unless otherwise ordered. The rate
of placing concrete in the forms shall preferably be 0.025 meter (0.082 feet)
vertical rise per minute.
FORMS AND FALSEWORK
All forms and falsework to be used in the work must be designed, and constructed by
the Contractor for rigidity and adequacy for carrying the loads of the fresh concrete
and/or additional superimposed construction loads. The Authority may from time to
time verify the adequacy and safety of such temporary works and may require the
Contractor to submit detailed designed drawings of forms and falseworks proposed to
be used. Approval of such drawings or design of forms, however, shall not relieve the
Contractor of his liability on resulting imperfections or damages to the finished
concrete, or other damages which may directly result therefrom.
Forms may be re-used but shall be scrapped by a wire brush of all clinging mortar.
Bulges should be planed and realigned prior to its use.
Prior to placing concrete form surfaces should be oiled for easy form removal.
However, the oil coating should not be so thick as to stain and soften the concrete
surface. Oil coatings should be applied before rebars are placed.
CURING AND WATERPROOFING
All concrete shall be cured for at least 14 days after the date of placing in accordance
with the approved and accepted methods.
32
FINISHING OF CONCRETE SURFACES
Concrete surfaces shall conform accurately to the form, alignment, grades and
sections shown in the drawings or as prescribed by the Engineer. It shall be free from
bulges, ridges, honeycombing or roughness of any kind, and shall be of a reasonably
smooth wood float finish.
TREATMENT OF SURFACE DEFECTS
All irregular concrete surfaces, voids, holes, honeycombs exposed after removal shall
be repaired by the Contractor in such a way that the repaired surface will be
acceptable.
PLACING OF REINFORCEMENT
Metal reinforcement shall be placed as accurately detailed on drawings and properly
secured by approved means.
All bars shall be cold bent unless approved otherwise by the Engineer. Minimum
distance between parallel bars shall be one and one half (1 1/2) times the diameter for
round bars and twice the side dimension for square bars. The clear distance between
bars shall not be less that 30 cm. (1 ft.) nor less that one and one third (1 1/3) times
the maximum size of the coarse aggregate, whichever is bigger.
All reinforcing steel shall be cleaned of all rust or scale and deleterious materials
which tend to destroy the bond between the concrete and the steel.
REINFORCING BAR SPLICES
Generally, splice/s of reinforcement at points of maximum stress especially in slabs,
beams and girders shall be avoided. Such splice/s may however be approved by the
Engineer in writing provided the lap if bonded or butt welded is sufficient to transfer
tensile stress between bars by at least 125% of the specified yield strength of the
reinforcing bar. For adjacent bars splices shall be staggered.
READY-MIXED CONCRETE
Where ready-mixed concrete is used, the requirements specified for batching, mixing
and transporting shall be in accordance with the requirements set forth in ASTM C94
Specifications for Ready-Mixed Concrete unless otherwise specified.
1. The Contractor shall notify the Engineer seven (7) days in advance before any
continuous phase of concreting operations is started. Upon notification, the
Engineer shall have the right to inspect the ready-mixed concrete supplier’s
plant/equipment and all materials and/or sources thereof. The Contractor must
coordinate with the supplier and must provide safe and adequate guidance for
the Engineer or his representative in conducting such examinations.
2. For all ready-mixed concrete delivered to site of work, discharge shall be
completed within one hour after the addition of cement to the aggregates or
33
before the drum is revolved 25 times, whichever comes first. Under
conditions contributing to the stiffening of concrete especially during hot
weather, the time required between the introduction of cement to the
aggregates and discharge of the mix may still be reduced by the Engineer.
3. Truck mixers shall be equipped with counters indicating the number of
revolutions of the drums which shall be automatically actuated at the time of
starting mixers at mixing speed.
4. Each batch or truck delivery of concrete shall be mixed inside the drum for not
less than 70 revolutions of the drum at the rate of rotation designated by the
equipment manufacturer. Additional mixing if ordered by the Engineer shall
be at the speed designated as agitating speed by the manufacturer of the
equipment.
5. Concrete for individual batches or deliveries should be of uniform
consistency, mix and grading. If slump tests of a minimum 2 samples taken
within 15 minutes of each other at approximately 15% and 85% discharge load
give values differing more than 2.54 cm. (1 in.) when the specified slump is 76
mm. (3 in.) , use of the particular mixer in the work shall be stopped until
corrections are made to prevent such conditions, which shall be confirmed by
further slump tests.
6. Every batch of ready-mixed concrete delivered at the job site shall be
accompanied by a ticket furnished in accordance with Section 15 of ASTM
94. The time when the materials were batched shall also be indicated.
7. Non-agitating equipment or combination truck and trailer equipment for
transporting concrete will not be permitted.
8. The Authority reserves the right to verify from time to time the quality and
quantity of materials used in every cement batch from the batching plant. The
Contractor shall be aware of this provision and make the proper arrangement
with the concrete supplier.
TEST ON CONCRETE
Test on concrete shall be in accordance with the following:
a. Concrete samples for tests shall be secured and molded in accordance with
ASTM C172 - “Method of sampling Concrete”, and ASTM C31 -
“Method of making Curing, Concrete Compression and Flexure Test
specimens in the field”.
b. Strength tests on samples shall be made in accordance with ASTM C39 -
“Standard Method of Test for Compressive Strength of Molded Concrete
Cylinder”.
Not less than four (4) cylindrical specimens shall be made for each test of
which at least two (2) shall be reserved for 28-day test. Not less than one (1)
34
test shall be made for every fifty (50) cubic meters of concrete but in no case
less than one (1) test for each day’s concreting.
Samples shall be taken by the Contractor under close supervision of the
Engineer; and shall be delivered as soon as practicable for testing, at his
expense, to the designated laboratories.
The average strength of test samples representing any definite class of
concrete used as well as the average of any five (5) consecutive strength tests
representing the class of concrete shall be equal to or greater than the specified
strength and not more than one (1) strength test in ten (10) shall have an
average value less than 90% of the specified strength.
If the test results indicate strength values less than the required, the Project
Manager shall have the right to order a change in the concrete proportion used
for the remaining work, or in the procedure of curing the concrete.
FIELD TESTS
Field tests as may be deemed necessary to check on the quantity of the materials and mixtures
and the manner of construction employed shall be conducted by the Project Engineer
assigned to the project. And when such tests result to values less than that tolerated by
standards set in applicable provisions of the ASTM Specifications referred to herein, or
contrary to accepted good Engineering practice, the Contractor shall comply to any
instructions given by the Project Engineer to upgrade the materials used and method of
construction employed.
METAL WORKS
SCOPE OF WORK
The work includes the furnishing and installation of miscellaneous metal necessary to
complete the work in accordance with this specification unless required otherwise on
the plans.
2.1 GENERAL PROVISIONS
The AISC Specification for the Design, Fabrication and Erection of Structural Steel
for Buildings, Association of Structural Engineers of the Philippines (ASEP)
Handbook of Structural Steel Shapes and Sections shall govern the Work. Welding
shall be in accordance with the AWS Code and as herein specified or any other
welding standard, approved by the Engineer.
Certification: Two (2) certified copies of mill test reports including names and
locations of mills and shops shall be furnished for all structural steel.
Responsibility for Errors: The Contractor shall be responsible for all errors of
detailing, fabrication and for the correct fitting of the structural members.
35
Storage of Materials: The materials shall be stored out of contract with the ground in
such manner and location as will minimize contamination and deterioration.
2.2 MATERIALS
Structural steel shall conform to ASTM A 36. All materials shall be of new stock,
free from surface imperfections and shall conform to the applicable ASTM, API
Specifications or other equivalent standards.
Steel Plates, Bars and Rods - Plates, bars and rods shall be local standard commercial
steel of sizes as indicated on the plans and approved by the Engineer.
Fastener and Anchor Bolts - Fasteners, anchor bolts necessary for the installation of
the work shown on the plans shall be of a standard commercial grade as approved by
the Engineer.
Bolts, Nuts and Washers - Bolts, nuts and washers shall be local standard commercial
grade of size as indicated on the plans conforming to ASTM A 325 or AASHTO
M164.
Welding - Employ only welding equipment electrodes welding wire and fluxes
capable of producing satisfactory welds when used by a qualified welder or welding
operator using qualified welding procedures. It shall conform to this AWS D1.1-183,
E70XX Series.
2.3 DELIVERY OF MATERIALS
Deliver anchor bolts and other anchorage devices which are embedded in cast-in-
place concrete construction to the project site in time to be installed before the start of
work.
Provide setting drawings, templates, and directions for installation of anchor bolts and
other devices.
Number in accordance with shop drawings the materials tested and approved by the
Engineer before delivery to the site. Prepare a list showing number, size, quality and
quantities of materials.
Transport materials in accordance with material list and transportation. Schedule
approved by the Engineer.
Protect materials to prevent damage during transportation. Package and label small
parts such as bolts or rivets.
2.4 FABRICATION
Fabricate structural steel in the shop to the greatest extent possible for transporting in
accordance with the AISC Building Code and ASEP Handbook with the modification
and additional specified in this section.
36
The Contractor shall verify all measurements in the field, submit shop drawings to the
Engineer showing sizes, gauges, detailed of construction, method of assembly and
installation.
Fabrication of work shall not commence until all shop drawings are approved by the
Engineer.
Shop connections: As detailed on the drawings or as approved by the Engineer.
a. Provide for bolted or welded connections as shown on the Drawings or as
approved by the Engineer.
b. Use high strength threaded fasteners for bolted connections, except where
standard threaded fasteners are permitted.
High Strength bolted construction assembly shall be tightened in accordance with
Specification for Structural Joints, AISC.
2.5 FIELD ERECTION
Steel erection shall conform to the requirements of this specification and to the
applicable requirements of AISC “Specification for the Design, Fabrication and
Erection of Structural Steel for Buildings”, and the AISC “Code of Structural Practice
for Steel Buildings and Bridges”.
2.6 FIELD ASSEMBLY
Assemble structural steel frames accurately to the lines and elevations indicated
within the specified tolerance.
Align and adjust accurately various members forming parts of a complete frame or
structure before fastening.
Fasten splices of compression members after the abutting surfaces have been brought
completely into contact.
Clean bearing surfaces and surfaces in permanent contact, of rust and scale before
members are assembled.
Splices shall be permitted only where indicated.
Bolt and weld field connections as specified in “Fabrication”.
Remove weld backing strips from welds designated for ultrasonic testing.
Remove run-off tabs and grind surfaces where requested by the Engineer.
Clean weld spatter from surfaces contacted.
Field correction of fabrication by gas cutting not permitted on any major member in
the structural framing without prior approval of the Engineer.
37
Mark structural steel members of high strength steels to permit visual verification of
the grade of steel used.
PAINTING WORKS
Color and Samples - All finish colors shall be as selected by the Owner. In multicoat work
using color pigmented paints, each coat shall have sufficient variation of color to easily
distinguish it from preceding coat.
Using specified or approved materials, 3 sample panels of each finish, including all coats
thereof shall be prepared and submitted for the Owner’s approval. Complete work shall
match approved colors and samples.
PREPARATION OF SURFACES
a) General - Except as otherwise specified, surfaces to be painted shall be clean,
smooth and dry. The Constructor shall report to the Engineer in writing any
surface which cannot be properly prepared for painting. If work is commenced
before defects have been reported and corrected, any resulting unsatisfactory
finish shall be rectified at no cost to the PPA.
b) Concrete and Masonry - All concrete and masonry surfaces shall be cured
thirty days prior to painting. Dirt, dust, oil, grease, efflorescences and other
deleterious matter shall be removed and surface roughened when necessary to
insure good paint adhesion. The method of surface preparation shall be left to
the discretion of the Constructor, but results obtained shall be satisfactory to
the Engineer. Before application of resin emulsion paint, surfaces shall be
prepared in accordance with manufacturer’s directions. Before application of
oil base or latex paints, surfaces shall be tested for presence of alkali; if alkali
is present, neutralize as recommended by the manufacturer of the paint
materials to be applied.
c) Plaster - Dirt, dust, loose plaster and other deleterious matter which would
prevent good paint adhesion shall be removed. All holes, cracks and
depression shall be neatly filled with patching plaster, mixed and applied to
match existing plaster. Patches shall be sanded flush and smooth and properly
sealed before applying prime coat. After priming surfaces, suction spots shall
be touched up with additional prime coat material until surfaces evidence a
uniform coating. Enamel undercoats on smooth plaster shall be sandpapered
by hand (with No. 00 sandpaper) and dusted clean before applying succeeding
coat.
d) Metal - Dirt, scale and rust shall be removed by scraping, wire brushing and
sanding or sandblasting as required. Oil and grease shall be removed with
mineral spirits or appropriate solvent. Before painting ferrous metal surfaces,
including galvanized ferrous metal, surfaces shall be pre-treated with approved
phosphoric acid etching cleaner in accordance with the manufacturer’s
direction to produce a chemically clean surface. Unless already performed in
accordance with specifications of other sections, abrasions and bare spots in
38
shop prime coatings shall be touched up with metal primer matching the shop
coatings. Enamel undercoats shall be sandpapered by hand (with No. 00
sandpaper) and dusted clean before applying succeeding coat.
e) Woodwork - Unless already properly sanded, woodwork shall be sandpapered
smooth by hand. Before priming surfaces, knots, pitch pockets and sap streaks
shall be thoroughly cleaned of residue and touched up with shellac varnish
coating. After priming surface, nail holes, cracks and depressions shall be
neatly filled with putty or other approved filler, colored to match required
finish. Enamel undercoats shall be sanded by hand (with No. 00 sandpaper)
and dusted clean before applying succeeding coat.
APPLICATION OF PAINT
a) General - All painting and finishing shall be performed by skilled craftsmen.
Each coat of paint shall be applied with the right consistency, evenly, free of
laps, sags and runs and cut sharply to required lines. Paint shall be applied
only under dry and dust free conditions that will insure properly finished
surfaces, free of defects and blemishes unless otherwise directed by the
engineer. Paint shall not be applied when temperature is likely to be above
90F. Sufficient time shall be allowed between applications of coats. All
primer and intermediate coats shall be unscarred and completely integral at
time of application of each succeeding coat. The Engineer shall be notified
when each coat has been applied and is ready for inspection; until coat is
inspected and approved by the Engineer, no succeeding coats shall be applied.
Whenever the coats of a dark colored paint are specified the first coat shall
contain sufficient powdered aluminum to act as an indicator for proper
coverage when applying the second coat.
b) Method of Application - Paint should be applied by brush, spray, or other
application method approved by the Engineer.
Priming and Back painting
1) Priming - Before installation, all surfaces of millwork which are to be
painted shall be primed giving particular attention to sealing of cross
grained surfaces. In all cases, all work shall be primed as soon as
possible after installation, as required, or in case of prefabricated items,
at fabricators shop or mill before shipment, if practicable. Except as
otherwise specified, priming shall consist of first coat herein after
specified under “Finishes”.
2) Back-Painting - Woodwork, millwork and casework to be
installed against concrete masonry or plaster shall be back painted with
one coat of exterior oil paint.
46
Checklist of Technical and Financial Documents
I. TECHNICAL COMPONENT ENVELOPE
Class “A” Documents
Legal Documents
⬜ (a) Valid PhilGEPS Registration Certificate (Platinum Membership) (all pages);
or
⬜ (b) Registration certificate from Securities and Exchange Commission (SEC),
Department of Trade and Industry (DTI) for sole proprietorship, or
Cooperative Development Authority (CDA) for cooperatives or its equivalent
document;
and
⬜ (c) Mayor’s or Business permit issued by the city or municipality where the
principal place of business of the prospective bidder is located, or the
equivalent document for Exclusive Economic Zones or Areas;
and
⬜ (e) Tax clearance per E.O. No. 398, s. 2005, as finally reviewed and approved by
the Bureau of Internal Revenue (BIR).
Technical Documents
⬜ (f) Statement of the prospective bidder of all its ongoing government and
private contracts, including contracts awarded but not yet started, if any,
whether similar or not similar in nature and complexity to the contract to be
bid; and
⬜ (g) Statement of the bidder’s Single Largest Completed Contract (SLCC) similar
to the contract to be bid, except under conditions provided under the rules;
and
⬜ (h) Philippine Contractors Accreditation Board (PCAB) License;
or
Special PCAB License in case of Joint Ventures;
and registration for the type and cost of the contract to be bid; and
⬜ (i) Original copy of Bid Security. If in the form of a Surety Bond, submit also a
certification issued by the Insurance Commission;
or
Original copy of Notarized Bid Securing Declaration; and
(j) Project Requirements, which shall include the following:
⬜ a. Organizational chart for the contract to be bid;
⬜ b. List of contractor’s key personnel (e.g., Project Manager, Project
Engineers, Materials Engineers, and Foremen), to be assigned to the
contract to be bid, with their complete qualification and experience
data;
⬜ c. List of contractor’s major equipment units, which are owned, leased,
and/or under purchase agreements, supported by proof of ownership
or certification of availability of equipment from the equipment
lessor/vendor for the duration of the project, as the case may be; and
⬜ (k) Original duly signed Omnibus Sworn Statement (OSS);
and if applicable, Original Notarized Secretary’s Certificate in case of a
47
corporation, partnership, or cooperative; or Original Special Power of
Attorney of all members of the joint venture giving full power and authority
to its officer to sign the OSS and do acts to represent the Bidder.
Financial Documents
⬜ (l) The prospective bidder’s audited financial statements, showing, among
others, the prospective bidder’s total and current assets and liabilities,
stamped “received” by the BIR or its duly accredited and authorized
institutions, for the preceding calendar year which should not be earlier than
two (2) years from the date of bid submission; and
⬜ (m) The prospective bidder’s computation of Net Financial Contracting Capacity
(NFCC).
Class “B” Documents
⬜ (n) If applicable, duly signed joint venture agreement (JVA) in accordance with
RA No. 4566 and its IRR in case the joint venture is already in existence;
or
duly notarized statements from all the potential joint venture partners stating
that they will enter into and abide by the provisions of the JVA in the
instance that the bid is successful.
II. FINANCIAL COMPONENT ENVELOPE
⬜ (o) Original of duly signed and accomplished Financial Bid Form; and
Other documentary requirements under RA No. 9184
⬜ (p) Original of duly signed Bid Prices in the Bill of Quantities; and
⬜ (q) Duly accomplished Detailed Estimates Form, including a summary sheet
indicating the unit prices of construction materials, labor rates, and equipment
rentals used in coming up with the Bid; and
⬜ (r) Cash Flow by Quarter.
49
_________________________________________________________________________
BID FORM
Date : _________________
Project Identification No. : _________________
To: [name and address of Procuring Entity]
Having examined the Philippine Bidding Documents (PBDs) including the Supplemental
or Bid Bulletin Numbers [insert numbers], the receipt of which is hereby duly acknowledged,
we, the undersigned, declare that:
a. We have no reservation to the PBDs, including the Supplemental or Bid Bulletins,
for the Procurement Project: [insert name of contract];
b. We offer to execute the Works for this Contract in accordance with the PBDs;
c. The total price of our Bid in words and figures, excluding any discounts offered
below is: [insert information];
d. The discounts offered and the methodology for their application are: [insert
information];
e. The total bid price includes the cost of all taxes, such as, but not limited to: [specify
the applicable taxes, e.g. (i) value added tax (VAT), (ii) income tax, (iii) local taxes,
and (iv) other fiscal levies and duties], which are itemized herein and reflected in the
detailed estimates,
f. Our Bid shall be valid within the a period stated in the PBDs, and it shall remain
binding upon us at any time before the expiration of that period;
g. If our Bid is accepted, we commit to obtain a Performance Security in the amount of
[insert percentage amount] percent of the Contract Price for the due performance of
the Contract, or a Performance Securing Declaration in lieu of the the allowable
forms of Performance Security, subject to the terms and conditions of issued GPPB
guidelines1 for this purpose;
h. We are not participating, as Bidders, in more than one Bid in this bidding process,
other than alternative offers in accordance with the Bidding Documents;
50
i. We understand that this Bid, together with your written acceptance thereof included
in your notification of award, shall constitute a binding contract between us, until a
formal Contract is prepared and executed; and
j. We understand that you are not bound to accept the Lowest Calculated Bid or any
other Bid that you may receive.
k. We likewise certify/confirm that the undersigned, is the duly authorized
representative of the bidder, and granted full power and authority to do, execute and
perform any and all acts necessary to participate, submit the bid, and to sign and
execute the ensuing contract for the [Name of Project] of the [Name of the Procuring
Entity].
l. We acknowledge that failure to sign each and every page of this Bid Form, including
the Bill of Quantities, shall be a ground for the rejection of our bid.
Name: ___________________________________________________________________
Legal Capacity: ____________________________________________________________
Signature: ________________________________________________________________
Duly authorized to sign the Bid for and behalf of: __________________________________
Date: ___________________
51
Omnibus Sworn Statement (Revised)
_________________________________________________________________________
REPUBLIC OF THE PHILIPPINES )
CITY/MUNICIPALITY OF ______ ) S.S.
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of
Affiant], after having been duly sworn in accordance with law, do hereby depose and state that:
1. [Select one, delete the other:]
[If a sole proprietorship:] I am the sole proprietor or authorized representative of [Name of
Bidder] with office address at [address of Bidder];
[If a partnership, corporation, cooperative, or joint venture:] I am the duly authorized and
designated representative of [Name of Bidder] with office address at [address of Bidder];
2. [Select one, delete the other:]
[If a sole proprietorship:] As the owner and sole proprietor, or authorized representative of
[Name of Bidder], I have full power and authority to do, execute and perform any and all
acts necessary to participate, submit the bid, and to sign and execute the ensuing contract for
[Name of the Project] of the [Name of the Procuring Entity], as shown in the attached duly
notarized Special Power of Attorney;
[If a partnership, corporation, cooperative, or joint venture:] I am granted full power and
authority to do, execute and perform any and all acts necessary to participate, submit the bid,
and to sign and execute the ensuing contract for [Name of the Project] of the [Name of the
Procuring Entity], as shown in the attached [state title of attached document showing proof
of authorization (e.g., duly notarized Secretary’s Certificate, Board/Partnership Resolution,
or Special Power of Attorney, whichever is applicable;)];
3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the
Philippines or any of its agencies, offices, corporations, or Local Government Units, foreign
government/foreign or international financing institution whose blacklisting rules have been
recognized by the Government Procurement Policy Board, by itself or by relation,
membership, association, affiliation, or controlling interest with another blacklisted
person or entity as defined and provided for in the Uniform Guidelines on Blacklisting;
4. Each of the documents submitted in satisfaction of the bidding requirements is an authentic
copy of the original, complete, and all statements and information provided therein are true
and correct;
52
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized
representative(s) to verify all the documents submitted;
6. [Select one, delete the rest:]
[If a sole proprietorship:] The owner or sole proprietor is not related to the Head of the
Procuring Entity, members of the Bids and Awards Committee (BAC), the Technical
Working Group, and the BAC Secretariat, the head of the Project Management Office or the
end-user unit, and the project consultants by consanguinity or affinity up to the third civil
degree;
[If a partnership or cooperative:] None of the officers and members of [Name of Bidder] is
related to the Head of the Procuring Entity, members of the Bids and Awards Committee
(BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project
Management Office or the end-user unit, and the project consultants by consanguinity or
affinity up to the third civil degree;
[If a corporation or joint venture:] None of the officers, directors, and controlling
stockholders of [Name of Bidder] is related to the Head of the Procuring Entity, members of
the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC
Secretariat, the head of the Project Management Office or the end-user unit, and the project
consultants by consanguinity or affinity up to the third civil degree;
7. [Name of Bidder] complies with existing labor laws and standards; and
8. [Name of Bidder] is aware of and has undertaken the responsibilities as a Bidder in
compliance with the Philippine Bidding Documents, which includes:
a. Carefully examining all of the Bidding Documents;
b. Acknowledging all conditions, local or otherwise, affecting the implementation of the
Contract;
c. Making an estimate of the facilities available and needed for the contract to be bid, if
any; and
d. Inquiring or securing Supplemental/Bid Bulletin(s) issued for the [Name of the Project].
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or
any form of consideration, pecuniary or otherwise, to any person or official, personnel or
representative of the government in relation to any procurement project or activity.
10. In case advance payment was made or given, failure to perform or deliver any of the
obligations and undertakings in the contract shall be sufficient grounds to constitute criminal
liability for Swindling (Estafa) or the commission of fraud with unfaithfulness or abuse of
confidence through misappropriating or converting any payment received by a person or
53
entity under an obligation involving the duty to deliver certain goods or services, to the
prejudice of the public and the government of the Philippines pursuant to Article 315 of Act
No. 3815 s. 1930, as amended, or the Revised Penal Code.
IN WITNESS WHEREOF, I have hereunto set my hand this __ day of ___, 20__ at
____________, Philippines.
[Insert NAME OF BIDDER OR ITS AUTHORIZED
REPRESENTATIVE]
[Insert signatory’s legal capacity]
Affiant
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
54
_________________________________________________________________________
REPUBLIC OF THE PHILIPPINES)
CITY OF _______________________) S.S.
BID SECURING DECLARATION
Project Identification No.: [Insert number]
To: [Insert name and address of the Procuring Entity]
I/We, the undersigned, declare that:
1. I/We understand that, according to your conditions, bids must be supported by a Bid
Security, which may be in the form of a Bid Securing Declaration.
2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any
procurement contract with any procuring entity for a period of two (2) years upon receipt of
your Blacklisting Order; and, (b) I/we will pay the applicable fine provided under Section 6
of the Guidelines on the Use of Bid Securing Declaration, within fifteen (15) days from
receipt of the written demand by the procuring entity for the commission of acts resulting to
the enforcement of the bid securing declaration under Sections 23.1(b), 34.2, 40.1 and 69.1,
except 69.1(f),of the IRR of RA No. 9184; without prejudice to other legal action the
government may undertake.
3. I/We understand that this Bid Securing Declaration shall cease to be valid on the following
circumstances:
a. Upon expiration of the bid validity period, or any extension thereof pursuant to your
request;
b. I am/we are declared ineligible or post-disqualified upon receipt of your notice to such
effect, and (i) I/we failed to timely file a request for reconsideration or (ii) I/we filed a
waiver to avail of said right; and
c. I am/we are declared the bidder with the Lowest Calculated Responsive Bid, and I/we
have furnished the performance security and signed the Contract.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this ____ day of [month]
[year] at [place of execution].
55
[Insert NAME OF BIDDER OR ITS AUTHORIZED
REPRESENTATIVE]
[Insert signatory’s legal capacity]
Affiant
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
56
CONSTRUCTION METHODOLODY
Name of Project :________________________________________________
Proposed Project Duration:____________________________________________
Location :________________________________________________
SCOPE OF CONSTRUCTION METHODOLOGY
NOTES:
The narrative construction method will guide and familiarize the Contractor and the PPA
on how the project shall be carried out in accordance with the highest standard of
workmanship.
The construction method shall be consistent with the Bar Chart/S-curve Schedule,
Equipment Schedule and manpower Schedule.
_______________________
Signature
(Authorized Signing Official)
57
FINANCIAL DATA
A. Summary of the Applicant Firm’s/Contractor’s assets and liabilities on the basis of the
attached audited financial statements, stamped “RECEIVED” by the Bureau of Internal
Revenue or BIR authorized collecting agent, for the immediately preceding calendar year.
Year 2020
1. Total Assets
2. Current Assets
3. Total Liabilities
4. Current Liabilities
5. Net worth (1-3)
6. Net Working Capital (2-4)
B. The Net Financial Contracting Capacity (NFCC) must be at least equal to the approved
budget for the contract to be bid.
NFCC = 15 (current asset - current liabilities) minus value of all outstanding works under
ongoing contracts including awarded contracts
NFCC = ___________________________________
Attached herewith are certified true copies of the audited financial statements stamped received
by the BIR or BIR authorized collecting agent for the latest/immediately preceding calendar
year.
__________________________
Name of Firm/Applicant
____________________________
Authorized Signing Official
Date:_______________________
NOTES:
1. If Partnership or Joint Venture, each Partner or Member Firm of Joint venture shall submit separate financial statements.
58
STATEMENT OF ALL ON-GOING GOVERNMENT AND PRIVATE CONTRACTS, INCLUDING CONTRACTS AWARDED BUT
NOT YET STARTED, WHETHER SIMILAR OR NOT SIMILAR IN NATURE
Names of the Contract or Title
Of the Project
Owner’s Name
And Address
Nature/ Scope
of Work
Contractor’s Role
(in percentage)
Total Contract Value At
Date of
Award
Value of
Outstanding Works
Estimated
Time of Completion
% of Accomplishment
Contract Duration
Award Project
Completion Date
Escalated
Value to Present
Prices
Planned
Actual
Start
Completed
a) Government
Contracts i. On-going
ii. Awarded but not yet started
b) Private
Contracts
i. On – going ii. Awarded but
not yet started
NOTES: 1] As appearing or defined in the contract entered/executed by the parties
2] With special reference to the Scope of Works as described/enumerated in the advertised Invitation to Bid. 3] Indicate whether as Sole Contractor, Sub-Contractor or Member in a Joint Venture/Consortium
4] Indicate the FOREX used if Contract Value is expressed in a currency other than the Philippine Peso. Specify the “Escalation Factor” used to escalate the Contract Value from completion date to the advertisement date of the Invitation to Bid per section 23.11.2(3) of R.A. 9184.
5] State Month and Year
________________________ ____________________
Name of Firm/Applicant Authorized Signing Official Date: ______________________
59
STATEMENT OF THE BIDDER’S SINGLE LARGEST COMPLETED CONTRACT (SLCC) SIMILAR TO THE CONTRACT TO BID
Names of the
Contract or Title
Of the Project
Owner’s
Name And Address
Nature/
Scope of Work
Contractor’s
Role and Percentage of
Completion
Total Contract Value At
Date of Award
Value of Outstanding
Works
Contract Duration
Award Completion Escalated
Value to Present Prices
Start
Completed
NOTES:
1. The prospective bidder must completed an SLCC that is similar to the contract to be bid and whose value, adjusted to current price using the PSA consumer price, must be at
…………least fifty.percent (50%) of the ABC to be bid. 2. This statement shall be supported by:
a. Notice of Award and/or Notice to Proceed b. Project Owner’s Certificate of Final Acceptance issued by the owner other than the Contractor or Constructors Performance Evaluation System (CPES) Final
…………………… Rating, must be at least satisfactory.
________________________ ____________________
Name of Firm/Applicant Authorized Signing Official Date: ________________________
60
EXPERIENCE RECORD ON SIMILARLY COMPLETED PROJECTS
(To be Filled-up by the Contractor/Applicant)
Major Operations of Work
Unit of
Measure
Quantity
Similar Major Operations of Works
Unit of
Measure
Quantity
Project. No. 1
Project No. 2
Project No. 3
Project No. 4
Project No. 5
NOTE: 1] Submit the Certificate of Completion/Certificate of Acceptance by the project owner, Final Recapitulation/Bill of Quantities and/or Constructors Performance Evaluation System (CPES) ratings, 1st, 2nd & final visit (If applicable). Projects with no Certificate of Completion/Acceptance and
Recapitulation/Bill of Quantities shall not be considered.
2] The Owner’s Certificate of Final Acceptance; or the Constructors Performance Evaluation Summary (CPES) Final Rating and/or the Certificate of
Completion, must be satisfactory.
______________________ __________________ Name of Firm/Applicant Authorized Signing Official Date: ____________________
61
STATEMENT ON AVAILABILITY OF KEY PERSONNEL
I hereby declare that the following key personnel enumerated below for the various positions/functions, namely:
Project Manager, Project Engineer, Materials Engineer, Construction Safety and Health Officer, and Foreman are available for the project applied for:
Position of Key
Personnel Name
No. of Key
Personnel
Experience in
the Position (Years) Attachments Annexes
Project Manager -PRC License (CE Preferred) -Complete Qualifications & Experience Data -Certificate of Commitment
Annex “__”
Project Engineer -PRC License (CE Preferred)
-Complete Qualifications & Experience Data -Certificate of Commitment
Annex “__”
Materials Engineer -PRC License (CE Preferred) -Submit valid & Renewed DPWH Cert. of Accreditation -Complete Qualifications & Experience Data -Certificate of Commitment
Annex “__”
Safety Officer -Cert. of Safety & Health Const. Related Course issued by DOLE accredited Trainings -Complete Qualifications & Experience Data -Certificate of Commitment
Annex “__”
Foreman -Complete Qualifications & Experience Data
-Certificate of Commitment Annex “__”
Other Position(s) -Complete Qualifications & Experience Data
-Certificate of Commitment Annex “__”
NOTE: Minimum qualification requirement: (work experience is similar in nature and complexity to the project to be bidded-out with regards to Registration Particulars of the ……………………Contractor’s License)
Project Manager - Five (5) years Materials Engineer – One (1) year
Project Engineer - Three (3) years Foreman - Five (5) years
________________________ _____________________
Name of Firm/Applicant Authorized Signing Official Date:_______________________
62
STATEMENT ON AVAILABILITY OF CONSTRUCTION EQUIPMENT/TOOLS (Please use separate Sheets if necessary)
I hereby declare that the following equipment listed below which are owned, under lease or under purchase agreement are in good operating condition and are available
for the project applied for, to wit:
No. of
Unit(s)
DESCRIPTION
(Type, Model, Make)
Capacit
y Output
Owned/Leased
and/or under purchase
agreement
Submitted Proof of
Ownership/Leased/Purchase
Agreement
(Mark as Annex “A…….Z”)
Manufacturer
Engine Serial No.
Chassis No.
(if applicable)
Location
Status
Note:
1] Indicate if owned or leased. If owned, state proof of ownership (i.e. deed of sale, sales invoice, official receipt). For Owned equipment, as required submit proof
of ownership (i.e.deed of sale, sales invoice, official receipt, LTO Registration).
2] the unit of each equipment shall be indicated in the list of equipment (i.e. Cu.m. for dump truck; HP for Concrete Vibrator, Backhoe, Grader,
Plate Compactor, Payloader, Compressor; Ton for Crane; Bagger for Concrete Mixer, Amp. For Welding Machine, etc.). ___________________________
Authorized Signing Official
63
CASH FLOW AND PAYMENT SCHEDULE
Name of Project:
______________________________________________________________________________
Project Duration (Days or Months) Payment Schedule (Monthly, in Pesos) Cash Flow (in Pesos)
TOTAL:
NOTES:
- The Cash Flow and Payment Schedule should be consistent with the Bar Chart and S-Curve.
- Advance Payment should be specified if contractor wants to avail - Payment Schedule shall not be more than once a month
_______________________
Authorized Signing Official
64
MANPOWER SCHEDULE
Name of project:
______________________________________________________________________________
MANPOWER (Minimum) Contract Duration (___ Calendar Days)
D A I L Y/WEEKLY
Project Manager (CE)
Project Engineer (CE)
Materials Engineer
Construction Safety and
Health Officer
General Foreman
Specify Other Applicable
Positions, etc.
___________________________
Authorized Signing Official
65
EQUIPMENT UTILIZATION SCHEDULE
Name of project:
______________________________________________________________________________
Item
No. DESCRIPTION
No.
of
Units
Owned /
Leased Contract Duration ( __ Calendar Days)
_____________________________
Authorized Signing Official