Ministry of Transport Myanma Port Authority Inland Water ...
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of Ministry of Transport Myanma Port Authority Inland Water ...
JREI
16-024
Ministry of TransportMyanma Port AuthorityInland Water TransportThe Republic of The Union of Myanmar
The Projectfor
Rehabilitation of Yangon Portand
Main Inland Water Transportin
The Republic of The Union of Myanmar(Follow-Up)
Final Report
February 2016
JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)
Nippon Koei Co., Ltd. (NK)
Ministry of TransportMyanma Port AuthorityInland Water TransportThe Republic of The Union of Myanmar
The Projectfor
Rehabilitation of Yangon Portand
Main Inland Water Transportin
The Republic of The Union of Myanmar(Follow-Up)
Final Report
February 2016
JAPAN INTERNATIONAL COOPERATION AGENCY (JICA)
Nippon Koei Co., Ltd. (NK)
BM 59007
BM
BM
BM
BM
BM
BM
BM
BM
1011
1213
12
34
56
78
9
22232425
2627
2829
3031
3233
34353637
1415161718192021
PROJECT AREAPROJECT AREA
YangonInternational
Airport
YangonInternational
Airport
Geodetic station
Dock yard
Survey Dept.
Yangon Central RS
IBC
YIT
MPF
GTC
Estate
MRTV
NationalStadium No.1
Mingalardon
DALLA
MITT
Shwepyithar
Mayangon
Hlaing
Sanchaung
Kamayut
Bahan
Dagon
Lanmadaw
AhlonePabedan
Latha
Kyauktada
Seikkan
Pazundaung
Botataung
Thaketa
Dawbon
Thingangyun
South Okkalapa
Dagonmyothit(North)
Yankin
Seikkyikanaungdo
Kyimyindaing
Hlaingtharyar
North Okkalapa
Insein
Mingalataungnyunt
Tarmway
Dagonmyothit(East)
Dagonmyothit(South)
Dagonmyothit(Seikkan)
Kyimyindaing
Dagonmyothit(East)
Dagonmyothit(Seikkan)
Dagonmyothit(South)
Taw kyaik
Ma yan
Myauk su
Taw paung sein
Kyun bin
Ale kyun
Taw pa lweKya dan
Oak aw lan
Byu gyaung
Htan daw
Shan gan
Toe kwin
Bo te gon
Khon hnet ein dan
INYA LAKE
KAN DAW GYI LAKE
Ta ma ta kawC
Lat that Y
To gyaung ga lay C
Kyaik ka san C
Bogyok C
Ko po C
Ta gu gyan C
Ata
ik y
o C
U pe yo
Da
niyo
C
In k
yan
C
Kun
ta C
Letpan
binC
Tam
an
gyiC
Tadagki Y
Yab aukkyi C
Nga moe yeik C
TWA NTE C ANAL
PAZUNDAUNG C
Ka naung do
Creek
S hwe lin bam C
HLAING
RIVER
Ky it
an Y
Phyat lan Y
Sin pon C
Alat C
Wela C
Let p
an gw
a C
Htone C
Min ga iun C
Nyaung C
Su la kan C
Pa ya C
BalaC
Pet inn C
Htain hn
api
nC
Yewe
C
Sobo
nC
Lwin
gyi C
Kaka
iuC
Konyw
a C
Gya
ung
wine
Ye ng
anY
ThaunggyiC
Ka sin C
Kon daing C
Kaw hm
u C
Apyauk C
Sa daing mut C
Yan
gon
bauk
C
Shit pe C
Pa ya gyi C
Let p
an go
n C
Ohn bin C
Kyaik tha le C
Pein ne gon C
Ywa dan she C
Ta da C
Seik gyi C
Ayun
zok
C
Pa ya gyi C
Nyau
ng le
bin
C
Kun gyan gon C
Myauk C
Let kaik C
Ka bin Y
Kyon da ye C
Tan
ma
nain
g C
Ano gyaung CYe byu dwin C
Htan ma naing C
Chaung gauk C
Tha kut pin (B assein)
Creek
Ka ma aung
Pyaw bwe C
Kha ya C
Po
mau
ng C
In ga bo Y
Ko daun C
Le b
o C
Ma-e-myaung C
Htaw auk C
Nyan gyaung C
YANGON RIVER
Ka wet C
Chaung gyi C
Taw kha yan C
Taw
ku
C
Hnget kyi daung C
Nyaung bin C
Pa kauk C
Kya bin gan C
Sapa
gan
C
Let kalk C
Da y e lu
C
Taw
dun
C
Kyo
ngya
n C
Ale gya u ng C
Ze po thwe ga le C
Ze po thwe ga le C
Taung gon C
Sa g
yin C
Dat taw C
Minga lun C
Ye ngan C
Taw
pa lw
e C
Thon
gw
a C
Tha
kut p
in C
TOE RIVER
Tawthur C
Nga pa C
We gyi Y
Ninbaing C
Kamon C
Myoyo C
Be in daw C
Aie
ywa C
Ma
so Y
Towthur C
Baw C
Kondan C
Kamataw Y
Thon gwa C
La ha
yet C
Min gyaung C
Pet let Yo
Min ga lun Y
Hle lan Yo
Nyaung ni C
Ma gyi gan C
Win yo C
Min we C
Ka wet C
Maung m
a ga le Y
Pauk pin C
Win ka ni C
Maung m
a C
Ba yet C
Win
gau
k C
Ka yan C
Pa gan daung C
Baw C
BAGO R
IVER
BAGO RI V
E R
Kayin gyaung C
Kan byaung C
Ye-nwe C
Pyin ma gan C
Hie
Yo
Zwe ka na C
Kyon pe C
Kayat C
Pa lan C
Shwe byauk C
Seikgyi C
Myoyo C
Thon
gw
a Y
Pa-aung gyi Y
Pi la kat C
Da min zeik C
Ka ia ma C
Baw ka lut C
Ka lauk swe C
San di CChaung bya C
Ase-m
in ga lun C
Kam
akan
a C
Ka ma ian C
Kon da
n C
Kya gan C
Aingnla Y
Kaw dun
C
Kam
apayon C
Ka ma ka lok Y
Kyon don C
San di C
Kya win C
Sin m
a kaw C
Be in daw C
Kunhnl C
Tu myaung C
Pa da gyi C
Ayun zok C
SIN KAN LAKE
Ta taik chaung
Hmaw wun
C
Ka naung C
Hmaw wun C
Pi la kat C
Taw ka laik C
Pa
kauk C
YANGON RIVER
Y A N G O N R I V E R
HLAING RIVER
PANHLAING RIV E R
Twan te Canal
Za Ma Ni Dam
Thi la wa Dam
Ban bwe gon Dam
2.0
3.0
6.4
1.3
4.1
3.3
3.2
2.5
1.6
3.7
3.7
3.5
2.63.3
3.1
2.4
1.9
1.7
0.32.1
0.8
4.0
2.8
1.9
2.0
5.3
3.1
5.5
3.8
2.9
3.5
3.2
6.5
4.7
4.2
4.7
4.5
2.0
5.2
4.6
3.0
3.7
4.5
3.5
2.4
2.8
1.5
2.1
1.9
1.1
1.1
1.4
2.9
3.1
2.5
2.3
2.7
0.9
1.7
1.2
2.1
2.2
2.2
3.0
3.0
3.12.4
3.8
2.3
2.7
1.6
3.5
2.3
3.0
2.5
3.1
2.7
4.2
3.1
1.9
0.4
12.6
9.9
25.9
28.0
20.4
24.0
27.3
14.3
19.0
14.4
26.5
16.9
12.0
4.0
2.5
2.6
4.7
7.1
4.8
8.8
12.6
6.6
3.6
3.3
3.2
4.6
4.8
15.3
24.2
3.7
4.8
4.4
3.5
4.9
5.2
4.4
1.1
3.6
2.1
2.5
3.1
2.8
4.5
3.2
4.5
4.2
4.8
6.5
2.7
1.0
4.03.0
3.7
3.2
3.7
4.7
3.2
1.6
3.1
2.1
3.3
3.8
4.0
3.2
5.4
4.54.83.4
2.8
2.9
2.1
1.1
2.5
2.4
3.9
4.5
21.2
8.0
3.0
1.6
2.9
5.7
5.03.5
5.9
5.2
5.3
4.1
5.0
4.6
4.8
5.4
10.3
3.2
3.7
4.0
4.6
4.6
4.6
6.9
4.9
8.3
5.5
4.33.7
4.03.0
3.6
3.8
3.96.3
4.4
6.1
4.2
2.2
11.0
18.07.7
8.5
14.7
22.4
22.4
16.0
8.7
3.92.8
6.3
5.2
5.3
4.8
5.0
2.2
4.2
4.8
3.6
4.5
6.3
4.5
1.4
23.4
20.7
29.2
26.7
19.7
14.5
13.2
14.5
7.43.2
5.7
9.6
4.7
1.4
0.5
2.0
2.2
1.9
4.0
3.6
6.6
2.32.3
4.8
3.7
2.6
2.5
2.3
4.8
5.5
5.7
4.5
2.9
2.8
1.8
2.4
3.92.2
4.3
1.8
4.1
3.9
14.3
2.7
6.8
9.7
10.9
18.3
14.2
31.9
26.3
0.9
2.6
2.0
3.9
3.2
2.4
3.0
4.2
5.2
4.5
3.1
2.5
4.7
6.3
22.0
1.1
1.5
1.7
1.3
1.6
1.8
0.70.6
1.51.4
1.7
0.6
1.2
1.6
1.7
0.6
1.8
1.7
1.8
1.6
0.8
1.1
1.6
1.5
1.3
1.7
1.2
4.4
4.4
2.0
3.3
2.3
2.4
2.5
3.2
2.7
4.5
3.5
5.0
6.0
5.3
5.4
6.3
5.4
6.3
7.7
7.9
8.0
1.8
4.5
2.8
2.6
2.1
3.4
1.9
2.4
2.0
2.1
2.5
1.9
2.9
2.9
3.1
2.1
2.5
2.5
2.3
2.6
2.3
2.0
1.9
2.2
1.9
2.4
2.5
2.6
1.9
1.9
3.0
3.3
2.7
3.1
2.9
2.7
3.5
4.0
4.8
4.3
3.8
3.5
4.0
3.5
3.5
4.6
4.7
3.6
4.1
3.8
3.7
4.5
2.2
2.3
2.6
2.2
2.0
2.6
2.0
2.6
2.4
2.3
2.4
2.4
2.9
3.0
3.1
2.9
3.4
3.2
2.7
2.7
2.6
2.5
3.3
2.7
3.3
3.4
2.0
2.2
1.9
2.6
2.5
2.7
3.5
3.3
3.1
2.9
2.7
3.9
3.9
4.0
3.5
4.0
3.7
3.9
4.4
4.5
4.9
4.5
3.5
4.7
3.8
4.1
4.2
3.7
3.6
4.1
5.8
5.2
6.2
7.3
1.6
1.6
1.0
1.4
1.1
1.6
1.3
1.5
1.2
1.8
1.7
1.7
2.5
1.9
2.6
3.2
2.4
2.0
2.9
2.8
3.1
3.2
3.4
2.9
3.1
3.2
3.0
2.2
2.2
2.6
3.2
2.5
2.3
2.9
3.3
3.3
4.5
3.8
3.8
4.0
3.6
3.7
3.8
4.5
4.9
4.4
4.8
4.3
4.4
5.4
5.4
12.1
8.8
8.9
10.6
11.6
11.2
14.1
20.5
21.2
20.9
16.6
18.8
16.1
26.6
22.6
24.6
24.5
23.6
28.2
29.0
28.8
29.1
31.0
31.3
32.6
34.0
35.1
36.3
42.3
9.0
3.8
4.2
4.0
7.2
5.8
3.4
3.9
3.3
13.94.1
3.1
3.9
3.9
3.72.8 3.0
4.24.0
4.0
4.14.7 3.7
3.44.5
2.8 2.6
2.9
3.2
3.3
4.1
4.8
3.2
5.14.0
3.7
4.6
4.9
3.4
3.5
3.2
3.4 2.0
3.2
1.5
2.7
3.2
2.9 3.9
3.6
2.5
2.1
1.7
3.0
3.3
5.3 3.53.4
3.43.2
2.62.9
1.12.2
1.2
1.4
1.31.5
2.9 2.8
2.63.0 3.0 2.8
1.62.4
0.70.3
4.1
1.6 1.3
1.31.1 0.7 1.4
0.91.51.3
1.4
1.1
2.9
4.9
1.6
4.5
1.6
3.0
2.2
3.8
2.1
4.0
0.7
2.8 4.3
3.6
3.7
2.8
4.1
3.7
4.3
3.4
1.7
2.1
2.6
2.2
1.4
2.3
2.9
2.2
1.9
2.7
3.6
3.4
3.3
4.3
4.8
3.9
3.6
2.1
3.5
4.1
2.52.7
4.3
4.2 4.3
1.6
3.8
3.9
3.1
2.2
4.1
1.4
3.3
3.8
3.3
1.4
3.1
4.6
4.8
4.3
4.1
4.5
4.8
2.2
3.1
3.6
3.8
1.5
1.7
3.8
4.4
4.8
2.0
4.0
2.0
2.8
4.3
3.3
4.1
2.9
2.5
2.8
4.7
3.6
4.2
3.9
3.2
3.3
2.6
3.5
2.5
2.6
2.2
0.8
3.73.7
2.9
2.7
2.0
1.3
1.2
4.2
2.6
4.2
4.6
4.8
3.8
0.5
1.2
1.6
4.0
5.7
5.5
3.5
2.2
4.7
4.2
3.7
2.9
3.5
3.6 2.6
1.50.4
0.7
1.3
4.5 3.4
4.2
5.3
4.4
4.9
2.0
2.8
2.2
2.8
2.4
3.3
3.85.7
5.8
4.8
3.7
2.4
2.7
4.2
5.0
24.3
23.3
3.7
2.1
3.8
4.0
2.8
4.0
3.7
3.9
3.7
5.51.2
1.1
2.2
2.6
3.1
5.2
3.0
3.2
1.7
3.3
3.2
3.2
2.6
3.03.5
4.8
5.3
4.9
2.5
1.6
24.6
1.5 2.5
1.3
1.4
1.0
1.1
3.0
3.1
0.6
0.9
1.4
1.1
13.7
22.5
25.6
9.2
6.0
6.0
1.9
3.8
2.3
1.9
1.2
3.9
2.0
3.5
3.8
1.5
1.0
3.3
2.2
3.7
2.8
2.3
0.4
1.6
3.8
8.012.8
21.9
12.7
2.6
4.5
5.3
2.8
6.5
1.99.9
22.9
16.7
25.9
3.3
1.1
2.2
3.6
2.4
2.94.2
2.8
1.6
1.9
2.4
1.92.0
0.9
4.5
3.9
1.1
3.8
2.6
2.1
1.1
2.92.6
3.9
2.1
2.1
2.7
1.7
0.9
1.4
3.9
2.3
3.0
1.9
4.2
4.2
2.6
2.1
3.9
2.1
4.9
4.3
2.9
3.7
2.7
3.5
6.2
4.6
6.6
3.3
3.6
4.7
10.28.15.4
1.5 5.0
4.5
4.7
4.5
3.44.4
3.6
4.4
4.6
3.3
3.1
2.6
2.8
4.9
3.6
1.3
3.2
1.0
3.2
3.7
2.8
4.3
3.31.5
4.7
4.7
1.9
2.2
2.7
2.0
0.8
3.5
3.7
2.7
2.1
1.4
4.8
1.5
2.3
2.2
1.6
1.7
2.9
5.2
3.1
1.5
3.1
3.0
0.9
1.9
5.4
4.3
1.9
3.2
1.3
3.3 1.2
0.6
1.0
3.2
1.7
0.8
2.3
1.0
1.5
1.3
1.0
1.2
1.4
1.1
1.0
1.4
1.7
1.3
1.3
1.2
1.3
1.5
1.3
1.4
1.3
1.3
1.5
1.61.6
1.21.6
1.9
1.9
2.0
2.02.1
2.2
2.1
2.2
2.3
2.5
2.5
2.6
2.6 2.6
2.7
2.7
2.9
3.0
2.9
3.3
4.3 3.4
5.5
GULF OF MOTTAMA
MYET SEIN KYUN
KYUN GYA
YELE KYUN
KYUN GYA
MYET SEIN KYUN
Creek Point
Entail Point
Elephant Point
Rattery Point
Than lyin Point
Bago Point
Monkey Point
Thi la wa Jetty
Thi la wa Jetty
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
Ferry
10
20
10
10
20
10
10
20
30
20
10
5
5
30
5
5
5
5
5
5
10
10
10
5
5
5
10
5
5
5
5
52020
10
20
20
5
10
5
5
5
5
5
5
5
5
5
5
5
55
5
5
5
5
5
25
25
5
5
25
15
15
15
5
5
5
5
5
5
5
5
5
5
15
5
25
5
5
5
5
5
20
20
20
20
10
10
30
20
20
20
20
20
20
20
10
10
10
10
10
10
10
10
10
10
10
10
20
10
15
15
25
35
35
25
25
25
5
5
5
5
5
15
15
15
15
15
15
5
5 10 15
10 515
5
5
5
5
55
5
5
30
5
5
5
5
10 10
10
10
10
5
5
5
5
5
5
10
5
5
5
5
Shwe pyi tha Bridge
Ba yint naung Bridge
Aung ze ya Bridge
Yangon-Than Lyin Bridge
Wa ta ya ashe
Wa ta ya anauk
Ye dwin gon
Deik kon
Ya kaing yo gyiAle ywa
Htein gon
Tu gyaung
Kha yan wa
Kha yan gyi
Kha lauk chaik
Wa yon zeik
Kha yan ga lay
Ta man gyiAlat chaung
Gyaung waing
Kyun ka layPyauk yo
Kan ywa
Kyi dan
Let pan gwa
Ta ma ta kaw atet
Pa ya gyi
Pyaw bwe ga le
Pa yar ngok to
Peik swe
Kan be
San ywa
Pauk taw
Yan gon bauk
Tha yaw dan
Pein ne gon
Ywa dan she
Apyauk
Nat sin gon
Kaw hmu myauk gyaung
Kaw hmu taung gyaung
San kauk
La wa di Wa ba lauk thauk
Ka yaik ka ni
Kyu daw chaung
Kha ma kha ni
Da not
Tha kut pin
Nyaung gyaung
Ya kaing gyaung
Ton tin kan taung
Kha naung
Kha naung shan su
Ta da chaung
Tha bye gon
Nuaung ngok to
Ye gyaung gyiYe gyaung wa
Htwe auk
Tu gyi
Pyaw bwe gyi
Shwe hle gyaung
Kywe lu aing
Nyaung bin
Myat san ni
Ko daung
Kan thon gan
Pha yon chaung
Tan ma naing
Kywe lu aing
Ma-wun
Kya gan
Ye byu dwin
Kyon da ye
Bo gyoke
Ma gyi gan
Seik kyi
In ga lon
De da naw
Nyaung ngu
Ka ma ba
Ma yan
Taung gon
Chaung gyi
Ka wet
Ta ma ta kaw
Taw pya
Taw lan anauk
Me ya gon
Hnget kyi daung
Kya khat kon gyi
Wet kaik
Kan ya she
Let kok kon
Ka nyin gon
Hmaw bi
Bo din
Nyaung bin tha
Pya mut
Pyi daw tha
Taw kha yan anauk
Mya le yon
Kya khat kon lay
Kant ma larTaw kha yan ashe
Kaw dun
Hna khaung gyaung
Pauk pin
Maung ma
Kyu daw
Ka mar chaik
Hla ba lu
Ma gyi gan
Zwe ka daw
Nyaung ni
Pa le
Aye ywaPa gan daung
Ale ywaTha bye gon
Ka yin zeik
Baw tha bye gan
Ka dat pya
De zat
Tha yet pin chaung
Nyaung binPha gu anuk
Pha gu ashe
Win ka ni
Le daung gan
Thon gwa
Ywa tha gyi
Ka la we
Nga bye ma
Tha nat pin
Ba yet Sit pin kwin
Nyaung thon bin
Nyaung le bin
Tha bye gan
Tha htay gwin
Yo gyi
Pein kan
Min gyaung
Pa ya gonKyaung gon seik gyi
Let yet san
Ayun zok
Nyaung waing
Pa da gyi
Shwe pyi tha ya
Se lon gyi
Baw ka lut
Chaung wa
Mi bya
Chaung zauk
Kan myin
Kan byaung
Ye gyaw
Kya gan
Pan daw
Kyan bin
Ywa thit ga le
Ka ma ka lok
Zwe ba kon dan
Thaik tu gan
Pyin ma gan
Kya win
Ban bwe
Nyaung waing
We gyi
Ywa thit gyi
Min ga lun
Aye mya thi da
Kyon gan
Taw ka lu
Kha lauk ta
Thaung khon
Si pin tha gyi
Si pin tha lay
Bon she gon
Zie gon
Sit pin myauk
Sit pin taung (Ahtet)
Sit pin taung (Auk)
Akauk yone
Wai bar gi myo thit
Apyin padan
Le ein
Awa set ga le
Nga zin Seik kyi
Kha naung to
Ta gyi
Pauk tan
Sin pon
Shwe pauk kan myo thit
Nin gyan
Ya kaing yo ga lay
Kon ta li
Ye ta li
Ka byo
Kin ywa
Ka lauk ka lu
Pa ya ngu
Hting zu
Mi gyaung wa
Ma myo asu
Ma nge
Ale ywa
Htein gon
Ta man gyi ka naung
Ta gun daing
Ye gyaw ohn bin zu
Ye gyaw
Kan ywa ka yin zu Kun ta
Aing gyi
Myet ni gon
U-pelaw-asu
Daing zu
Aye ywa
Set ga lay
Kon ywa
Kayin zu
Kan hla
Ka naung do
Kan gyi gon
Seik kyi
Pyin ma gon
Aye myo ywa
Ta ma ta kaw auk
Pa le myo thit
Pauk ngu
Thin gan gyun
Tan bin gan
Let kaik
Ka mar pat
The ganThe gon
Pa ya lay ngu
Tha yet thon bin Le bo
Kwin waing
Za lok kyi
Nyaung le bin
Don nyo zu We gyi gwa
Kyi zu
Kon dan
That kai kwin
Shan gan
Ya gyaw zu
Than byu yonThan ban gyaung
Sat chaung
Po myat ni su
E-ywa
Tha min gon
Sin gyan Chaw le
We gyi
Gat ywa Leik kon
Ano gyaung ga le
Shwe ga byan
Ano gyaung gyiNga phaw
Ze gon
Za yat gon
Be zu
Da ni daw
Gat kon
Ka bin
Ywa thit ga lay
Hle zeik
Kya byu gan
Nga dan ta yar
Ka la asuGwa Seik gyi
Pyin ma gon
Let pan gon
Wet su
Daung gwe
Tha zi
Ka la dan
Than byu yon
Thon ein
Chaung oo
Shan su
Ta gu gyan
Htan pin gyaung
Bi lin
Banbwe ngu
Kun gyan su
Ye da sheChaung kaw gyan
Tar taik
Set su
Kha naung chaung wa
Min su
Taung than gyo
Hin tha gon
Taung ma yo gon
A kauk yone
Pa ya gyi
Kha lauk ka le
Pain ne gan
Tha yet taw
Hla ka bon
Pauk kon
Hle seik
Ale ywa
Tha ya gon
Yo kant lant
Ma ke
Ya khaing chaung wa
Ta gyi
Kyaik tha le
O bo
Chaung wa
Kya bin gan
Shan kan
Taw ku ashe
Taw ku anauk
Ka lauk ta ya
Pauk taw
Gu gyi gonYe dwin kon
Sun pa lun kon
Ye ngan chaung zu
Kyi zu
Kyauk sa rit (Ase le)
Pa zun myaung
Ale ywa Se ein dan
Chaung wa auk seik
Pi kon
Pin le kon
Ain hint kon
Aung ze yaMyaing tha ya
Ye da gar
Kan gyi kwin
Abyit kon
Anauk kon
Kha ye gon
Myo nwe gon
Let kok kan
Tan bin ganTar taikBi lin
Kyaik pat
Myo gon
Ta yoke kon
Sa pa gan
Ka lauk ka me
Ye de in
Ka ya zu
Hnget kwa
Kye ta ya
Htan ta binTha min gyan
Po thi gon
Taw lan ashe
Taw ya gon
The kon dan
Pon gyi gon
Taik kon
Baw sa gaingAle gyaung
Dat taw
Da ye lu
Awaing gyaung
Po loung
Myauk zu
Kya gaik
Taw twin gon
Ta man gyi
Ywa thit
Seik gyi
Kyun gyaung
Kan waing
Ka nyin bin
Kya khat wa
Tha ya gon
Ywa thit kon
Taik kon
Kyaung gon
Kywe gyan kwin
Tu myaung
Ka thit kon
Thit kya gon
Yan gyi aung
Mye ni gon
Htan taw
Taw da ye gon
Adat ywa
Seik kan tha
Baw di gon
Hle seik
Pa zun chaung
U-do
Tha ya ayeAhtet seik
Sa gyin
Toe kwinKyon ka nan chaung wa
Nyaung bin
Shwe hle
Kyu chaung
Taung ta lok
Kya ni gan
Tha ya gonKyaung ywa
Min we
Da la ban
Aye ywa
Maung gwe
Kyaung sha kan
Ok pho
Ka ma sein
Ma so
Kyi zu
La ha yet
Ka ma ka leik
Win gyi
Ta ma ta kaw
Nyaung bin
Chaung wa
Let pan
Ywa thit
Kywe gu zeik
Nga pa
Nyaung lan gan
Tan bin chaung
Nyaung gale
Ma U ta thi
Ywa thit ga le
Tha yet kon
Ka lar te waing gyi
U yin daw
On hne gan
Ma gyi pauk gan
Auk te zu
Kyon ma yan
Ywa thit gyi
Nyaung pin gyi su
Kan hla
U yin
Kan gyi su
Hla kyu win
Taung ywa
Se gon
Pyi taw tha
Ka mar ka lok
Nan yaw in
Htaw thun
Kan tha myint
Pauk taw
Kun daing
Nyaung Waing
Ma gyi gan
Ye kyaw Te su
Pa don gyaung
The byu gyaung
Nat sin gon
Kan nyin bin gyaung
Kyauk ye dwin
Kun gyan gonKyaik ain
Pyin daung gyaung
Ale ywa
Ohn hne gon
Kun bo dein
Ta man gyi
U yin
Kwin bauk
Pan chaung
Kayin gyaung Zwe ka na
Ase ywa
Kwa hne
Ka ma lan
Ka la htan
Kyaung kan
Shan zu
Shwe byauk
A dut taw
Kya gan deikKyaik ka maw
Pa da wa
Kyauk ma ye
Thaung gyi
Kun ga lay
A ngu
Tha nat pin gyin
Ka me
Pa ya ngok to
Ka lauk swe
Sa daing hmu
Pi la kat
San di
Kya gan
The gon
Tha yet taw
Min ya za
Htan pin zeik
Hta ma lon
Kya kan gyi gon
Te waing gyi
Ka lar tan
Taung gon lay
Taw ta lok
Tan te zu
Myaing tha ya
Thi da myaing
Ka la pi la khat
Kon gyi
Tan te zu Gar te zu
Ashe swe taw
Ngwe thaung yan
Anauk swe taw
Ze gon
Pi la kat
Ale gon
Taw ka laik
Taw ka
Taw ka sauk
Pa kauk
Shan gyi gon
Ywa thit kon
Kywe kan gon
Aung ze ya
Thanlyin
Kawhmu
Kungyangon
Thanlyin
Thanlyin
Kyauktan
YANGON CITY
SOUTHERN YANGON DISTRICT
WESTERN
YANGO
NDISTRICT
NORTHERN
YANGO
NDISTRICT
NORT
HERN
YANGON DISTRICT
EAST
ERN
YANG
ON DIS TRICT
NORTHERN YANGON DISTRICT
PYAPON DISTRICT
SOUTHERN YANGON DISTRICT
BAGO DISTRICTSOUTHERN YANGON DISTRICT
SOU
THERN YANGO
N D
ISTRIC
T
NORTHER N YANGON DISTRICT
EASTERN YANGON DISTRICT
WES
TERN
CH
ANN
EL
THILAWATHILAWAAREA PORTAREA PORT
YANGONYANGONMAIN PORTMAIN PORT
YANGONYANGONPort L
imit
Port Limit
Port Limit
Port Limit
0 2 10 km4 6 8
SCALE
China
Thailand
Laos
Vietnam
Cambodia
Bangladesh
Bhutan
Malaysia
Naypyidaw
Yangon
MYANMAR
N
Copyright © 2010-2016 NIPPON KOEI CO., LTD. All right reserved.
LOCATION MAP OF YANGON PORT
-10m
-10m
-10m
-10m
-5m
-10m-5m-1
5m
-15m
-10m
-10m
-10m
-5m
-10m
-15m
-5m
-15m
-20m
-15m
-20m
-30m
-20m
-15m
-15m
-10m
-5m
-15m
-10m
-15m-10m
-5m-20m-25m
-30m
-25m
-20m
-15m
-15m
-10m
-15m
-15m
-10m
-5m
-20m
-25m
-25m-20m
-15m-10m
-5m
-15m-10m
-15m
-10m
-5m
-10m
-10m
-10m-10m
-10m
-10m
-15m
-15m
-10m
-5m
-5m
-5m
-5m
-10m
-5m
-5m 0m
0m
-5m
-5m
-10m -10m
-5m
-10m-5m
-10m-5m
0m
-5m
-5m
-5m -5m
-5m
-10m
-10m-5m
-5m
-5m
-15m
-0m-5m
-15m
-15m
-15m
0m
-5m
-20m
-5m
-5m-10m
-15m
-5m
-10m
-13m
-14m
-12m
-17m
-9m
-3m
-12m
-11m
-16m
-7m
-23m
-3m
-4m
-2m
-4m
-7m
-6m
-6m-7m
-8m
-9m
-9m
-6m
-6m
-6m
-6m
-7m
-8m
-7m
-8m
-9m
-4m
-3m
-2m
-13m
-7m
-3m -2m-1m
-4m
-6m
-12m-8m
-9m
-9m
-8m -7m -6m
P
A
N
H
L
A
I
N
G
R
I
V
E
R
K
A
N
A
U
N
G
ID
T
W
A
N
T
E
C
A
N
A
L
P
A
Z
U
N
D
A
U
N
G
C
R
E
E
K
B
A
G
O
R
I
V
E
R
C
R
E
E
K
Y
A
N
G
O
N
R
IV
E
R
Y
A
N
G
O
N
R
I
V
E
R
S
U
L
E
W
H
A
R
V
E
S
M
Y
A
N
M
A
R
F
I
V
E
S
T
A
R
L
I
N
E
I
W
T
D
O
C
K
Y
A
R
D
M
E
C
W
H
A
R
F
M
E
C
W
H
A
R
V
E
S
A
N
T
G
Y
I
D
O
C
K
Y
A
R
D
N
Y
A
U
N
G
D
A
N
J
E
T
T
Y
N
1000 2000 m0
SCALE
8
B
A
Z
A
R
J
E
T
T
Y
(
K
Y
E
E
M
Y
I
N
D
I
N
E
)
A
H
L
O
N
E
W
H
A
R
F
(
A
S
I
A
W
O
R
L
D
)
M
Y
A
N
M
A
R
I
N
D
U
S
T
R
I
A
L
P
O
R
T
(
M
I
P
)
M
P
A
O
F
F
I
C
E
T
O
W
E
R
P
O
R
T
H
E
A
L
T
H
J
E
T
T
Y
2
B
O
A
U
N
G
G
Y
A
W
C
O
N
T
A
I
N
E
R
Y
A
R
D
MONKEY
POINT
S
E
I
K
G
Y
I
T
R
A
I
N
I
N
G
W
A
L
L
P
O
R
T
H
E
A
L
T
H
J
E
T
T
Y
3
N
A
N
T
H
I
D
A
2
N
A
N
T
H
I
D
A
3
&
4
T
H
E
I
N
B
Y
U
J
E
T
T
Y
M
P
A
(
S
H
I
P
Y
A
R
D
)
M
P
A
(
C
I
V
I
L
D
E
P
T
.
D
O
C
K
Y
A
R
D
)
B
O
T
A
H
T
A
U
N
G
3
B
O
T
A
H
T
A
U
N
G
4
B
O
T
A
H
T
A
U
N
G
5
H
O
T
E
L
(
V
I
N
T
A
G
E
L
U
X
U
R
Y
)
A
N
T
G
Y
I
J
E
T
T
Y
K
I
N
G
'
S
B
A
N
K
J
E
T
T
Y
C
R
A
N
E
J
E
T
T
Y
M
I
N
Y
E
K
Y
A
W
T
H
U
J
E
T
T
Y
M
.
O
.
G
.
E
J
E
T
T
Y
W
A
D
A
N
J
E
T
T
Y
1
&
2
,
3
&
4
,
5
&
6
,
Y
O
Y
O
J
E
T
T
Y
S
I
N
O
H
D
A
N
G
1
S
H
W
E
T
A
U
N
G
D
A
N
1
H
L
E
D
A
N
1
L
A
N
T
H
I
T
K
A
I
N
G
D
A
N
J
E
T
T
Y
2
K
A
I
N
G
D
A
N
J
E
T
T
Y
1
H
L
E
D
A
N
2
S
H
W
E
T
A
U
N
G
D
A
N
2
S
I
N
O
H
D
A
N
G
2
F
I
S
H
E
R
Y
D
E
P
T
.
J
E
T
T
Y
B
A
G
A
Y
A
J
E
T
T
Y
1
&
2
&
3
C
E
N
T
R
A
L
F
I
S
H
M
A
R
K
E
T
J
E
T
T
Y
P
A
N
S
O
D
A
N
J
E
T
T
Y
L
A
N
M
A
D
A
W
1
&
2
P
H
O
E
G
Y
I
L
A
N
1
&
2
K
Y
E
E
M
Y
I
N
D
I
N
E
J
E
T
T
Y
3
&
5
C
H
A
U
N
G
W
A
M
Y
A
N
M
A
R
S
H
I
P
Y
A
R
D
J
E
T
T
Y
T
H
E
I
N
B
Y
U
D
O
C
K
Y
A
R
D
S
A
T
S
A
N
D
O
C
K
Y
A
R
D
(
M
P
A
L
I
G
H
T
H
O
U
S
E
D
E
P
T
.
J
E
T
T
Y
)
D
A
L
A
P
O
R
T
J
E
T
T
Y
B
A
G
A
Y
A
C
O
N
C
R
E
T
E
S
H
O
R
T
J
E
T
T
Y
C
O
N
C
R
E
T
E
J
E
T
T
Y
N
o
.
4
C
O
N
C
R
E
T
E
J
E
T
T
Y
N
o
.
5
(
P
R
I
V
A
T
E
:
S
H
W
E
P
Y
I
T
A
N
)
(
B
O
T
A
H
T
A
U
N
G
6
)
D
A
L
A
Y
O
Y
O
J
E
T
T
Y
(
B
O
T
A
H
T
A
U
N
G
2
)
(
W
O
R
K
S
H
O
P
P
O
N
T
O
O
N
J
E
T
T
Y
)
C
O
N
C
R
E
T
E
J
E
T
T
Y
(
B
A
G
A
Y
A
N
o
.
4
)
Project Site for Defect Inspection
LEGEND
Project Site for Pre-survey
Project Site for On-site Training
LOCATION AND NAME OF PORT FACILITIES IN YANGON MAIN PORT
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
i
The Project for Rehabilitation of
Yangon Port and Main Inland Water Transport in
the Republic of the Union of Myanmar (Follow-Up)
Final Report
Location Map of Yangon Port Location and Name of Port Facilities in Yangon Main Port Abbreviation
TABLE OF CONTENTS
CHAPTER 1 INTRODUCTION ........................................................................................................... 1-1 1-1 Background of the Project ............................................................................................................. 1-1 1-2 Objectives of the Project ............................................................................................................... 1-1 1-3 Project Area, Scope and Schedule ................................................................................................. 1-1
1-3-1 Project Area ................................................................................................................... 1-1 1-3-2 Project Scope ................................................................................................................. 1-2 1-3-3 Schedule of the Project .................................................................................................. 1-3
1-4 Counterpart Agency ...................................................................................................................... 1-4 1-5 JICA Project Team ........................................................................................................................ 1-4
CHAPTER 2 DEFECT INSPECTION.................................................................................................. 2-1 2-1 Summary of Pilot Project .............................................................................................................. 2-1 2-2 Implementation of Defect Inspection ............................................................................................ 2-3
2-2-1 Schedule and Participants of Defect Inspection ............................................................ 2-3 2-2-2 Technical Transfer of Defect Inspection ........................................................................ 2-3 2-2-3 Steel Structures .............................................................................................................. 2-4 2-2-4 Concrete Facilities ......................................................................................................... 2-5 2-2-5 Buildings ........................................................................................................................ 2-7
2-3 Result of Defect Inspection ......................................................................................................... 2-10 2-4 Maintenance System for the Facilities of Pilot Project ............................................................... 2-15
CHAPTER 3 TECHNICAL TRANSFER ON MAINTENANCE AND REPAIR ................................ 3-1 3-1 Summary of the Technical Transfer .............................................................................................. 3-1 3-2 Pre-Survey ..................................................................................................................................... 3-1
3-2-1 Method and Object of the Survey .................................................................................. 3-1 3-2-2 Result of the Pre-Survey ................................................................................................ 3-2 3-2-3 Consideration ................................................................................................................. 3-7
3-3 On-Site Training ............................................................................................................................ 3-8 3-3-1 Outline of the Training................................................................................................... 3-8 3-3-2 Outline of the Program .................................................................................................. 3-8 3-3-3 Details of On-site Training ............................................................................................ 3-9 3-3-4 Result of On-site Training ........................................................................................... 3-13 3-3-5 Result of Questionnaire Survey ................................................................................... 3-14
3-4 Classroom Lecture ...................................................................................................................... 3-15 3-4-1 Outline of the Classroom Lecture ................................................................................ 3-15 3-4-2 Outline of the Program and Display ............................................................................ 3-16
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
ii
3-4-3 Contents of Classroom Lecture ................................................................................... 3-17 3-4-4 Result of Classroom Lecture ....................................................................................... 3-19 3-4-5 Result of Questionnaire Survey ................................................................................... 3-20
3-5 Recommendation for the Maintenance Method .......................................................................... 3-21 3-5-1 Current Situation Related to the Maintenance of Port Facilities ................................. 3-21 3-5-2 Recommendation for the Maintenance Method ........................................................... 3-21
CHAPTER 4 PUBLIC ANNOUNCEMENT ........................................................................................ 4-1
CHAPTER 5 SUMMARY (OUTPUT AND EVALUATION) .............................................................. 5-1 5-1 Background ................................................................................................................................... 5-1 5-2 Defect Inspection .......................................................................................................................... 5-2 5-3 Recommendation for the Maintenance Method ............................................................................ 5-3 5-4 Public Announcement ................................................................................................................... 5-4 5-5 Output and Evaluation of Other Work .......................................................................................... 5-5
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
iii
LIST OF TABLES Table 1.1 Schedule of the Project ........................................................................................................ 1-3 Table 1.2 Team Members and Position ............................................................................................... 1-4 Table 2.1 Major Scope of Pilot Project and Owner ............................................................................. 2-2 Table 2.2 Numbers of Participants of Each Organization ................................................................... 2-3 Table 2.3 Situation Before and After the Repair of the Defects ........................................................ 2-11 Table 3.1 Summary of the Technical Transfer ..................................................................................... 3-1 Table 3.2 List of Trainees .................................................................................................................... 3-8 Table 3.3 Conditions of Jetties selected for On-site Training ............................................................. 3-8 Table 3.4 List of Participants............................................................................................................. 3-15
LIST OF FIGURES Figure 1.1 Location Map of Yangon Main Port .................................................................................... 1-2 Figure 1.2 Flowchart for the Implementation of the Project................................................................. 1-3 Figure 2.1 Project Implementation Structure ........................................................................................ 2-1 Figure 2.2 Project Facilities .................................................................................................................. 2-2 Figure 2.3 MPA Maintenance Division............................................................................................... 2-15 Figure 2.4 IWT Civil Engineering Department .................................................................................. 2-16 Figure 3.1 Accuracy Rate for Questions (Understanding of Site Training) ........................................ 3-14 Figure 3.2 Ability Improved by the Classroom Lecture ..................................................................... 3-20 Figure 3.3 Contents of Lecture that the Participants Want in the Future ............................................ 3-20 Figure 3.4 Cycle of Maintenance Management .................................................................................. 3-22 Figure 4.1 International Development Journal (January 2016) ............................................................ 4-1 Figure 5.1 Implemented Programs of the Project ................................................................................. 5-2
LIST OF PHOTOS Photo 2.1 Busy Terminal Operation .................................................................................................... 2-3 Photo 2.2 Two Pontoons ...................................................................................................................... 2-4 Photo 2.3 Steel Bridges (East and West) ............................................................................................. 2-4 Photo 2.4 East Porter Way ................................................................................................................... 2-5 Photo 2.5 Walkway .............................................................................................................................. 2-5 Photo 2.6 Slipway ................................................................................................................................ 2-6 Photo 2.7 Staircase at Slipway ............................................................................................................. 2-6 Photo 2.8 Revetment ............................................................................................................................ 2-7 Photo 2.9 Fence ................................................................................................................................... 2-7 Photo 2.10 Passenger Terminal Building ............................................................................................... 2-8 Photo 2.11 Toilet (Male and Female) .................................................................................................. 2-10 Photo 3.1 View and Survey of Nan Thi Da 3 ...................................................................................... 3-2 Photo 3.2 Defective Part of Nan Thi Da 3 ........................................................................................... 3-2 Photo 3.3 View and Survey of Nan Thi Da 4 ...................................................................................... 3-3 Photo 3.4 Defective Part of Nan Thi Da 4 ........................................................................................... 3-3 Photo 3.5 View and Survey of Sin Oh Dang 1 .................................................................................... 3-4 Photo 3.6 Damaged Part on Sin Oh Dang 1 ........................................................................................ 3-4 Photo 3.7 View and Repaired Part of Sin Oh Dang 2 .......................................................................... 3-5 Photo 3.8 Damaged Part of Sin Oh Dang 2 ......................................................................................... 3-5 Photo 3.9 View and Repaired Part of Hledan 2 ................................................................................... 3-6 Photo 3.10 Damaged Part of Hledan 2 .................................................................................................. 3-6 Photo 3.11 View and Repaired Part of Kaingdon Jetty 1 ...................................................................... 3-7
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
iv
Photo 3.12 Repaired Part of Kaingdon Jetty 1....................................................................................... 3-7 Photo 3.13 Overall and Repaired Part of Kaingdan Jetty 1 ................................................................... 3-9 Photo 3.14 Overall and Deteriorated Part (Rebar Exposure) of Wadan Jetty 6 ..................................... 3-9 Photo 3.15 On-site Orientation ............................................................................................................ 3-10 Photo 3.16 Explanation of Sound Survey and Trial by the Trainees ................................................... 3-10 Photo 3.17 Explanation and Demonstration of the Schmidt Hammer Test ......................................... 3-11 Photo 3.18 Demonstration of Core Drilling and Participant’s Operation ............................................ 3-11 Photo 3.19 Rebar Detector (Radar System) ......................................................................................... 3-12 Photo 3.20 Demonstration of Rebar Detection and the Trainees’ Operation of the Equipment .......... 3-12 Photo 3.21 Condition of Deteriorated Jetty and Demonstration of Chipping ...................................... 3-13 Photo 3.22 Explanation and Demonstration about the Beam Repair ................................................... 3-13 Photo 3.23 Expert and Trainees ........................................................................................................... 3-14 Photo 3.24 Display of Equipment for Survey ...................................................................................... 3-16 Photo 3.25 Orientation ......................................................................................................................... 3-17 Photo 3.26 Explanation by Projector ................................................................................................... 3-17 Photo 3.27 Explanation of Concrete Materials and Corrosion Model ................................................. 3-18 Photo 3.28 Participants at the Display ................................................................................................. 3-18 Photo 3.29 Awarding of Certificates to Participants ............................................................................ 3-19 Photo 3.30 Photo of All Participants .................................................................................................... 3-19 Photo 4.1 Situation of Interview .......................................................................................................... 4-1
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
v
ABBREVIATION
ICB Interlocking Concrete Block
IWT Inland Water Transport
JB Press Japan Business Press Co. Ltd
JFE JFE Engineering Corporation
JICA Japan International Cooperation Agency
MMU Myanmar Maritime University
MOT Ministry of Transport
MOU Memorandum of Understanding
MPA Myanma Port Authority
NK Nippon Koei Co., Ltd.
ODA Official Development Assistance
RC Reinforced Concrete
US$ United States Dollars
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
1-1
CHAPTER 1 INTRODUCTION
1-1 BACKGROUND OF THE PROJECT
In Yangon Port, there are about 100 jetties and many of them are owned by Myanma Port Authority (MPA). However, there are many deteriorated jetties since the maintenance is not sufficient. In 2013, the Dalla Jetty has deteriorated significantly. As a result of the inspection and evaluation in order to verify the necessity of repairing, it was found that there is a high risk of immediate collapse if an earthquake occurs due to deterioration and that the structure is beyond repair. Therefore, it was decided to remove and construct a new jetty. The inspection and evaluation have been implemented by MPA and Inland Water Transport (IWT). Also, training and lecture have been carried out for the technical transfer.
Defect inspection was necessary one year after the completion of the construction of “The Pilot Project of Restoration of the Dalla Ferry Terminal Jetty at Dalla Side” under “The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar”. Furthermore, follow-up of the technical transfer implemented in 2013 had been required for further improvement of the knowledge about the maintenance method and inspection of the reinforced concrete.
This Project (Phase 3) is the final compilation of the “The Urgent Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar”. As the restoration project of the port that was affected by Cyclone Nargis, JICA Project Team commenced the services in February 2009, and completed the last Phase in February 2015. Please refer to Chapter 5 for the detailed the background.
1-2 OBJECTIVES OF THE PROJECT
The objectives of the Project are:
Objective 1: To implement defect inspection and check whether there are construction defects one year after the completion of the construction of the Dalla Terminal Jetty.
Objective 2: To achieve the maintenance capacity in Myanmar by illustrating the considerations of future maintenance with reference to the defect inspection result.
1-3 PROJECT AREA, SCOPE AND SCHEDULE
1-3-1 PROJECT AREA
The Project area covers the jetties owned by MPA including the Dalla area in Yangon City.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
1-2
Source: JICA Project Team
Figure 1.1 Location Map of Yangon Main Port 1-3-2 PROJECT SCOPE
The scope of work of the Project is composed of the following major items:
Preparation and Discussion of the Inception Report - The inception report was prepared and submitted to JICA (Head Office) and the consultation
was conducted with JICA (Myanmar Office), MPA and IWT.
Implementation of Defect Inspection (Final Report: Chapter 2) - One year after the completion of construction of the Dalla Jetty Terminal, defect inspection
had been implemented on December 23, 2015 to check whether there are construction defects. Then the defect inspection was summarized and reported to JICA after confirmation that the Contractor had completed the repair woks, which the Contractor is responsible for.
- Facilities to be inspected are the following: Steel Structures: pontoon, movable steel bridge Concrete Facilities: porter way, walkway, slipway, revetment, fence Buildings: passenger terminal building, toilet
Technical Transfer on Maintenance and Repairing (Final Report: Chapter 3)
- The maintenance methods should be considered based on the defect inspection result, with reference to the repair method in Japan. Then, the optimal maintenance method of the Dalla Jetty Terminal had been proposed.
- In 2013, technical transfer about the inspection and evaluation of the soundness of concrete was conducted for the engineers/staff of MPA and IWT. A follow-up training in order to enhance the level of the engineers/staff had been carried out in this Project.
Public Announcement (Final Report: Chapter 4)
- The Dalla Ferry Terminal is an important means of transportation for people commuting between Yangon and Dalla. In light of this situation, the information had been disseminated in Myanmar for the public announcement of the Project as a good example of Japanese official development assistance (ODA).
Preparation of the Final Report
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
1-3
1-3-3 SCHEDULE OF THE PROJECT
The work schedule of the Project is shown in Table 1.1 below while the flowchart for the implementation of the Project is shown in the next page.
Table 1.1 Schedule of the Project
Source: JICA Project Team
Source: JICA Project Team
Figure 1.2 Flowchart for the Implementation of the Project
1 2
1Preparation and Discussion of theInception Report
12
2015 2016
5 Preparation of the Final Report
2 Implementation of Defect Inspection
3Proposal for the Future MaintenanceMethod
4 Public Announcement
Preparation and Discussion of the Inception Report
Implementation of Defect Inspection
Public Announcement
Technical Transfer on Maintenance and Repair
Preparation of the Final Report
Preparation of the Inception Report
Explanation and Discussion of the Inception Report
Preparation of the Inspection Plan
Inspection of Steel Structure
Inspection of Concrete Facilities
Inspection of Buildings
Preparation of the Defect Inspection Result
Reflection of Result
Recommendation for Maintenance Method
Implementation of Pre-survey (Confirmation of Current Situation of
Technical Transfer Conducted in 2013)
Implementation of Classroom Lecture
Implementation of On-site Training
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
1-4
1-4 COUNTERPART AGENCY
The counterpart agencies of the JICA Project Team are as follows:
Myanma Port Authority (MPA) Inland Water Transport (IWT)
1-5 JICA PROJECT TEAM
The members of the JICA Project Team are shown in Table 1.2 below.
Table 1.2 Team Members and Position No. Position Name
1 Team Leader Expert of Inland Water Transport Facilities
Mr. Kazuhisa IWAMI
2 Senior Marine Civil Engineer of Steel Structure Mr. Toshihiro KATO
3 RC Maintenance Expert Dr. Kimitoshi MATSUYAMA
4 Building Engineer Mr. Kei SAWAMURA
5 Public Announcement Ms. Mitsue TAMAGAKE Source: JICA Project Team
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-1
CHAPTER 2 DEFECT INSPECTION
2-1 SUMMARY OF PILOT PROJECT
(1) Summary of Pilot Project as a Target of Inspection
The contract data of the Pilot Project are summarized as follows:
Name of the Project : The Urgent Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Phase 2)
Name of the Pilot Project : The Pilot Project of Restoration of the Dalla Ferry Terminal Jetty ad Dalla Side
The Client : Japan International Cooperation Agency (JICA), Myanmar Office
The Consultant : Nippon Koei Co., Ltd. (NK)
The Contractor : JFE Engineering Corporation (JFE)
The Counterparts : Myanma Port Authority (MPA) Inland Waterway Transport (IWT),
Construction Duration : 240 days (all the Works, except installation of the new pontoons and steel bridges) 270 days (whole of the Works)
(2) Implementation Structure of Pilot Project
The Project Implementation Structure is summarized in the following flowchart:
Source: JICA Project Team Figure 2.1 Project Implementation Structure
JICA and JFE signed the contract on January 31, 2014 and JICA (Myanmar Office) issued a
notice to proceed on February 1, 2014. The whole of the Works was completed on October 28, 2014 which was the 270th day from the date of the commencement of the Project. The facilities were handed over to MPA and IWT on November 15, 2014.
(3) Major Scope of Pilot Project and Owner
The scope of the Pilot Project and an owner of each facility have been summarized in the following Table 2.1 and Figure 2.2.
Counterpart
IWT Client
JICA
Counterpart
MPA
Consultant
NIPPON KOEI
Contractor
JFE Engineering
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-2
Table 2.1 Major Scope of Pilot Project and Owner No. Item Dimension Owner
1 Two moveable steel bridges Truss Type Steel Bridge (Length: 22.78 m, Width: 3.25 m)
MPA
2 Concrete coating of two pontoons Sides and tops of 2 nos. of steel pontoons MPA
3 Porter way (West) 14 nos. of concrete piles (0.5 m x 0.5 m x 19.4 m) Concrete deck slab (24.85 m x 4.5 m x 0.3 m thick)
MPA
4 Porter way (East) 14 nos. of concrete piles (0.5 m x 0.5 m x 19.4 m) Concrete deck slab (25.45 m x 4.5 m x 0.3 m thick)
MPA
5 Walkway with interlocking concrete pavement Length of pavement: 67 m (Area: 448 m2) MPA
6 Slipway with pile
18 nos. of concrete piles (2.5 m x 38 m) MPA
7 Passenger terminal building and toilet Single storey building (18.5 m x 21.6 m) IWT
8 Revetment and fence Length: about 50 m and 70 m each MPA
9 Demolition works Existing porter way, terminal building, and existing toilet
-
10 Supply of materials for pontoons manufactured by IWT
Steel plate, welding rod, paint, anode -
Source: JICA Project Team
Source: JICA Project Team
Figure 2.2 Project Facilities (4) Utilization of the Facilities
The Photo below, taken from the slipway, shows that two pedestrian bridges are used simultaneously for embarking and disembarking. Therefore the usage situation was improved including the safety. Though the number of the passengers using the ferry boats has increased, and the travel time has decreased due to the following reasons:
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-3
Embarking and disembarking times have decreased because of the two bridges and pontoons
system. The navigation time has decreased because of the Japanese granted boats named Cherry.
Source: JICA Project Team
Photo 2.1 Busy Terminal Operation 2-2 IMPLEMENTATION OF DEFECT INSPECTION
2-2-1 SCHEDULE AND PARTICIPANTS OF DEFECT INSPECTION
The joint inspection to identify the defective facilities was carried out on December 23, 2015. JICA (the Client), NK (the Consultant), and JFE (the Contractor) carried out the joint inspection. MPA and IWT (Counterparts and Owners) attended as witnesses. The numbers of participant of each organization are shown in the following Table 2.2.
Table 2.2 Numbers of Participants of Each Organization
Organization Number of Participants
JICA Client 2
MPA Counterpart and Owner 2
IWT Counterpart and Owner 3
NK Consultant 10
JFE Contractor 4 Source: JICA Project Team 2-2-2 TECHNICAL TRANSFER OF DEFECT INSPECTION
The followings are explained to MPA and IWT on joint inspection. - Procedure from the Construction Completion to Warranty Security Return - Responsibility of Client, Consultant and Contractor - Defects that are not attributable to the Contractor - Defects that the Contractor shall repair - Items to be inspected
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-4
2-2-3 STEEL STRUCTURES
(1) Pontoons
The concrete coated surface is in good condition. No serious defects or damages occurred. Handrails, bollards, fenders, and anchor chains are in good condition.
Some bolt connections of fenders and pontoons became loose. About 5 cm of water was found inside the pontoon because rain water had leaked through the manhole hatch covers.
Source: JICA Project Team
Photo 2.2 Two Pontoons (2) Steel Bridges
The steel bridge structure, roof truss, and roofing of both bridges are in good condition. Some portions of the longitudinal beam floor had been rusty. Some timber planks of the timber floor had become loose.
Source: JICA Project Team
Photo 2.3 Steel Bridges (East and West)
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-5
2-2-4 CONCRETE FACILITIES
(1) Porter Ways
The structure, roofing, and roof truss of both porter ways are in good condition. No serious defects or damages occurred after the completion of construction. Paint on the handrail had slightly faded because it was exposed to public use.
Source: JICA Project Team
Photo 2.4 East Porter Way (2) Walkway
The interlocking concrete block (ICB) walkway is in good condition. Concrete pavement beside the passenger terminal building is in good condition. Some ICB had sunk down at some places.
Source: JICA Project Team
Photo 2.5 Walkway (3) Slipway
The concrete structure of the slipway is in good condition. Small damages occurred along the edge of the slipway because of the berthing of small boats. Rubble stones for slope protection had been
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-6
washed away by tide and river flow at some places.
Source: JICA Project Team
Photo 2.6 Slipway And the staircase at the slipway is in good condition. Passenger can pass through conveniently.
Some nosing edge had been damaged because of the berthing of small boats during high tide. Also, some plaster damages had occurred at some thread surface and side wall.
Source: JICA Project Team
Photo 2.7 Staircase at Slipway (4) Revetment
The revetment has firmly protected the slope of the riverbank. Some rubble stones had been taken away at the toe in some places. Small cracks have occurred in some places.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-7
Source: JICA Project Team
Photo 2.8 Revetment (5) Fence
The fence structure is in good condition. Some concrete blocks had been damaged that were probably hit by motorbikes or trishaws. Cracks had occurred at connection joints between the concrete column and the brick capping on the top of the concrete blocks.
Source: JICA Project Team
Photo 2.9 Fence 2-2-5 BUILDINGS
(1) Passenger Terminal Building
a. Floor The non-slip ceramic tiles are in good condition. No defects or damages were found.
Passengers enjoy safe and pleasant environment. No serious slip injuries occurred after the completion of construction.
b. Wall
The acrylic emulsion paints on the cement mortar in both the interior and exterior walls are in good condition. The structure of the wall has the same condition before and after the completion of construction. Although the wall structure is in good condition, some defects (cracks) had occurred at the bottom of many windows. Crack lines occurred at every connection joint of the two
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-8
different materials.
c. Door and Window The aluminium frames of the sliding windows, wooden frames of the swing wooden doors,
steel frames of the rolled up shutter steel doors, and the iron concertina sliding door are all in good condition. One of the six glass window leaves became loose and moved out of frame because the frames of the window leaf were not strong enough to withstand the strong sliding movement. One of the mosquito nets at the window also became loose and out of frame. IWT kept the six window leaves and one mosquito net in the storage.
d. Ceiling
The aluminium frames and cement fiberboard are in good condition. However, some defects had occurred in the mineral fiber acoustic tile in some places.
e. Roof
The roof structure and roofing sheets appears to be in a good condition. The nailing points at the sheet lapped areas also appear to be in a good condition. Gutters and downspout are functioning well. Some brackets at the downspout became loose.
f. Ceiling Fans and Lighting
All ceiling fans and lighting are still effective and in good condition.
g. Lightning Rod and Cable Metal rods mounted on top of the roof and conductor cables are in good condition.
h. Miscellaneous Items The benches, diorama, revolving gate, and service counter are in good condition. Some
handrail posts at the side of the portico (entrance porch) were broken due to the misuse by the passengers.
Source: JICA Project Team
Photo 2.10 Passenger Terminal Building
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-9
(2) Toilet
a. Floor The non-slip ceramic tiles are in good condition. No defects or damages were found. Toilet
users have a safe environment. No serious slip injuries occurred after the completion of construction.
b. Wall
The emulsion paints on the cement mortar in the exterior wall and on the waterproof gypsum board in the interior wall are in good condition. The ceramic tile on the cement mortar plaster is in good condition. The structure of the wall is strong and robust.
c. Door and Window
The aluminium frames of windows and wooden frames of wooden doors are in good condition except the locks at the toilet door which were loosened and damaged because of improper usage of the toilet users.
d. Roof
The roof structure and roofing sheets are in good condition. Nailing or screwing points at lapped areas of the roofing sheets are in good condition. Gutters and downspout are functioning well.
e. Exhaust Fans and Lighting
All exhaust fans and lighting are still effective and in good condition.
f. Toilet Accessories Toilet cubicles, urinal bowls, sinks, mirrors, and other toilet accessories are almost in good
condition. One water tap in the male toilet and one tap in the female toilet have stopped operation.
g. Water Pump The compressor pump for pumping water from the tube well to the ground tank is in a
good working condition. Whereas, the pump for raising water from the ground tank to the elevated tank is not working.
h. Wooden Fence
The wooden post and planks are in good condition.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-10
Source: JICA Project Team
Photo 2.11 Toilet (Male and Female) 2-3 RESULT OF DEFECT INSPECTION
(1) List of Facilities to be Inspected
The following facilities were inspected to determine whether they have defects (please refer to Appendix 1 for more details):
a. Steel Structures
- West Porter Way Roof Truss - East Porter Way Roof Truss - West Steel Bridge - East Steel Bridge - Two Pontoons made by IWT
b. Concrete Facilities
- Slipway - Fence - Walkway - West Porter Way - East Porter Way - Revetment - Pontoon Coating Concrete
c. Buildings
- Terminal Building - Toilet
(2) Repair of Defects
The summary of the situation before and after the repair of the defects is shown in the following Table 2.3. For detailed contents of the repair of the defects, please refer to Appendix 2.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-11
The Contractor commenced the repair works on 2 January 2016 and completed them in two weeks. Joint inspection was carried out on 21 January 2016 by NK and JFE with the presence of MPA and IWT to confirm the completion of the repair works. As a result of this inspection, it was confirmed that the Contractor had completed the repair works, which the Contractor is responsible for.
Table 2.3 Situation Before and After the Repair of the Defects
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
West Steel B
ridge
Timber floor connection is loosed and mounted.
Rust and Paint defected.
East Steel Bridge
Timber floor longitudinal member is mounted and cracked.
Timber floor longitudinal member is mounted.
Pontoons
Steel angle is deformed and concrete is defected.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-12
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Slipway
Surface plaster defected.
Concrete is defected.
Fence
Top portion of fence column is cracked and rebar is appeared. Top portion of fence column is cracked and rebar is appeared (Total 4 places).
W
alkway
ICB paver blocks have been sunken and damaged. ICB are sunk and damaged.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-13
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
West Porter W
ay
Pile cap bottom surface connection defected (Total 3 places).
Edge of Porter Way slab (vertical surface) defected.
East Porter Way
Concrete surface is defected.
Abutment concrete surface (vertical side) is defected.
Revetm
ent
Some rubble stone in bottom portion are missing and crack appeared.
Revetment is cracked base of Porter Way west.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-14
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Terminal B
uilding
Ceiling 4 numbers need to repair.
Ceiling one number need to repair.
Buildings (C
rack line)
Crack line is occurred.
B
uildings (Rain W
ater Dow
n Pipe)
Downpipe brackets are damaged.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-15
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Toilet
Defected urinal bowl water tap and need to repair.
Defected and need to repair.
Source: JICA Project Team 2-4 MAINTENANCE SYSTEM FOR THE FACILITIES OF PILOT PROJECT
(1) Organization Chart of the Counterpart (MPA and IWT)
The organization chart of the MPA Maintenance Division, which is in charge of construction and maintenance for this Pilot Project, is depicted as follows. The Divisional Engineer participated in the Pilot Project as the representative of MPA during the construction stage.
Source: Prepared by JICA Project Team based on data from MPA Figure 2.3 MPA Maintenance Division
The organization chart of the IWT Civil Engineering Department, which is in charge of
construction and maintenance for this Pilot Project, is depicted as follows. The Executive Engineer participated in the Pilot Project as the representative of IWT during the construction stage.
Divisional Engineer
Daily Inspection
Team of
Pontoon/Sponson
(4) Persons
Inspection/Renovation
Team of
Mooring Work
(4) Persons
Inspection/Renovation
Team of
Porter Way
(4) Persons
Emergency Pumping
and
Renovation Team
(4) Persons
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
2-16
Source: Prepared by JICA Project Team based on data from IWT Figure 2.4 IWT Civil Engineering Department
The Executive Engineer participated in the Pilot Project as the representative of IWT during the
construction stage.
(2) Current Situation of Repair by the Counterpart (MPA and IWT)
After the completion of construction, the buildings, walkway, fence, and revetment were handed over to IWT, and the porter ways, steel bridges, pontoons, and slipway were handed over to MPA. However, both parties cannot carried out proper maintenance due to budget constraints and insufficient manpower allocation. For example, IWT can only use as much as US$ 500 per year as budget for maintenance of its facilities on the Yangon River including the Dalla Ferry Terminal, Pansondan Terminal, and Delta branch office.
(3) Recommendation for Effective Use
The facilities shall be regularly inspected before minor damages result in major repair works. Especially, for the facilities used by many users such as Dalla Ferry Terminal, it is expected that each component of the facilities is careful inspected regularly. Major repair may become necessary without the regular inspection, and may obstruct the passenger services severally.
The owner should clean the facilities regularly or on a daily basis to enhance the environment around the facilities.
Admin/
Account Cluster Construction and
Renovation Cluster Estimate and
Drafting Cluster
Executive Engineer
(Civil)
Assistant
Engineer
Worker
Assistant
Engineer
(Head Quarter)
Junior Engineer
(1)
Junior Engineer
(2)
Junior Engineer
(1)
Junior Engineer
(2)
Electrician
(3)
Worker
Junior Engineer
(2)
Mason
(4)
Assistant
Engineer
Junior Engineer
(1)
Draftsman
(4)
Office
Superintendent
Divisional Clerk
Upper
Division Clerk
Lower
Division Clerk
Junior Typist
Office Assistant
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-1
CHAPTER 3 TECHNICAL TRANSFER ON MAINTENANCE AND REPAIR
3-1 SUMMARY OF THE TECHNICAL TRANSFER
In order for MPA and IWT to maintain the port facilities made from reinforced concrete properly, to have knowhow of the survey (soundness test) and repair of concrete are inevitable.
Technical transfer regarding these knowhow was conducted through on-site training and classroom lecture as summarized in Table 3.1. Further details are described in Section 3-3 and 3-4. And Section 3-5 presents the recommendation for the technical development regarding maintenance and repair for MPA and IWT.
Table 3.1 Summary of the Technical Transfer
On-site Training Classroom Lecture
Visual inspection and sketches Sound survey Schmidt Hammer Test Coring survey Rebar detection Repair of deteriorated concrete
Properties of reinforced concrete and maintenance
Inspection and evaluation of RC Results of inspection and evaluation of jetties Repair and maintenance of RC
Source: JICA Project Team 3-2 PRE-SURVEY
JICA Project Team surveyed the same jetties that were surveyed in 2013 in the previous Phase of the Project (The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in The Republic of The Union of Myanmar - Phase 2). This was to check the conditions of the concrete aging during this elapsed time, and/or to see whether or not maintenance to the jetties was conducted by the counterparts. The results of the survey are summarized in this section.
3-2-1 METHOD AND OBJECT OF THE SURVEY
JICA Project Team first confirmed the jetties that were repaired by the counterparts after 2013. Then the Expert of JICA Project Team (hereinafter “the Expert”) chose the jetties for the pre-survey, comparing the conditions of repair around 2013. The following six jetties were targeted on this survey.
- Nan Thi Da 3 - Nan Thi Da 4 - Sin Oh Dang 1 - Sin Oh Dang 2 - Hledan 2 - Kaingdon Jetty 1 The methods of the survey on the site were the visual inspection and the sound test using a
hammer by the Expert. The result of the survey was reflected to the contents of the lecture as well as the selection of the site for on-site training. Also this result was used as the base information for the recommendation of maintenance management.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-2
3-2-2 RESULT OF THE PRE-SURVEY
The conditions of the six jetties are as follows:
(1) Nan Thi Da 3
A part of Nan Thi Da 3 and its condition during the survey are shown Photo 3.1. There were no cracks and peeling off of the concrete surface. The repaired part was in good condition.
Source: JICA Project Team
Photo 3.1 View and Survey of Nan Thi Da 3 One of the slanted beams of Nan Thi Da 3 that was previously repaired was defective. The Expert
suggested that this defect would be repaired as soon as possible.
Source: JICA Project Team
Photo 3.2 Defective Part of Nan Thi Da 3
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-3
(2) Nan Thi Da 4
A part of Nan Thi Da 4 and its condition during the survey are shown in Photo 3.3. There were no cracks and peeling off of the concrete. The repaired part was in good condition. There were rock pockets in a few parts but they were slight and they do not need to be repaired soon.
Source: JICA Project Team
Photo 3.3 View and Survey of Nan Thi Da 4
One part of Nan Thi Da 4 that was previously repaired has defective concrete cover and rebar. The Expert suggested that this defect would be repaired as soon as possible.
Source: JICA Project Team
Photo 3.4 Defective Part of Nan Thi Da 4
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-4
(3) Sin Oh Dang 1
A part of Sin Oh Dang 1 and its condition during the survey are shown in Photo 3.5. The concrete cover of the underside of the repaired part was peeled off and the rebar was corroded.
Source: JICA Project Team
Photo 3.5 View and Survey of Sin Oh Dang 1 Other parts that were not repaired have peeled-off concrete cover and rebar corrosion. The
underside has tensile stress so the Expert suggested that this part would be repaired as soon as possible. On the porter way, there are some exposed rebars. These rebars may not cause a structural problem but these are obstacles for carriage on the porter way. The Expert suggested that this part would be repaired soon.
Source: JICA Project Team Note: Rebar exposure at the underside and on the Porter Way
Photo 3.6 Damaged Part on Sin Oh Dang 1
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-5
(4) Sin Oh Dang 2
A part of Sin Oh Dang 2 and a repaired part are shown in Photo 3.7. The repaired part, where new mortar was refilled, is in good condition.
Source: JICA Project Team
Photo 3.7 View and Repaired Part of Sin Oh Dang 2
There was a defective part on the support of the porter way. There were peeled-off concrete cover and rebar exposure. The Expert suggested that these parts would be repaired as soon as possible.
Source: JICA Project Team
Photo 3.8 Damaged Part of Sin Oh Dang 2
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-6
(5) Hledan 2
A part of Hledan 2 and its condition during the survey are shown in Photo 3.9. A repaired part where new mortar was refilled is in good condition (no crack).
Source: JICA Project Team
Photo 3.9 View and Repaired Part of Hledan 2
There was a defective part at the underside of Hledan 2. There were peeled-off concrete cover and rebar exposure. The Expert suggested that these parts would be repaired as soon as possible.
Source: JICA Project Team
Photo 3.10 Damaged Part of Hledan 2 (6) Kaingdon Jetty 1
A part of Kaingdon Jetty 1 and a repaired part are shown in Photo 3.11. The repaired part that was broken due to boat collision was reconstructed. There was no crack and it was in good condition.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-7
Source: JICA Project Team
Photo 3.11 View and Repaired Part of Kaingdon Jetty 1
There were some repaired parts at the underside of Kaingdon Jetty 1. The refilled mortar in the repaired parts was damaged. These parts were just refilled with new mortar. There was no chipping off of deteriorated concrete and no anti-rust painting on the rebar.
Source: JICA Project Team
Photo 3.12 Repaired Part of Kaingdon Jetty 1
3-2-3 CONSIDERATION
(1) Condition of Repaired Parts
For the parts repaired after the previous technology transfer was conducted in 2013, there were no cracks and peeling off and they were in good condition. The repaired parts lasted for two or three years at least.
On the other hand, on the parts repaired before 2013, there were cracks, damaged concrete cover, and exposed rebars. Repair method by refilling with new mortar was simple.
It is important to chip off deteriorated concrete, put anti-rust paint on the rebar, and refill new mortar or concrete on it.
(2) Repair Range
Based on the results of the survey by the Expert, there were defective parts close to the repaired part. Some parts were defective members (no concrete and rebar). Therefore, the Expert suggested that the whole jetty would be checked and other deteriorated parts, if any, would be repaired at the same time.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-8
3-3 ON-SITE TRAINING
3-3-1 OUTLINE OF THE TRAINING
Outline of the training is summarized below:
Title of training : Site Training on Maintenance of Reinforced Concrete Yangon Port Jetties
Date and time : 22 December 2015, 8:30 to 12:00
Place : IWT Meeting Room, Kaingdan Jetty 1 and Wadan Jetty 6
Trainees : Total of six engineers from MPA and IWT (hereinafter “the Trainees”)
Trainer : Expert of JICA Project Team with Myanmar assistant engineers (hereinafter “the Expert”)
Table 3.2 List of Trainees No. Name Department Designation
1 ***** IWT :Inland Water Transport Assistant Engineer
2 ***** IWT :Inland Water Transport Assistant Engineer
3 ***** MPA :Myanma Port Authority Assistant Engineer
4 ***** MPA :Myanma Port Authority Foreman
5 ***** MPA :Myanma Port Authority Divisional Engineer
6 ***** MPA :Myanma Port Authority Assistant Engineer Source: JICA Project Team 3-3-2 OUTLINE OF THE PROGRAM
The main program of the on-site training is as follows: - Introduction of the Project and purpose of the training at the IWT Meeting Room - On-site orientation - Inspection of the concrete at the Kaingdan Jetty 1 - Repair of the deteriorated concrete at the Wadan Jetty 6 - Question and answer Two jetties were selected for the training based on the results of the pre-survey shown in Section
3-2. The conditions of the two jetties are below:
Table 3.3 Conditions of Jetties selected for On-site Training Jetty Conditions Remarks
Kaingdan Jetty 1 Many damaged parts. Repaired part is damaged again.
Please refer to Photo 3.13.
Wadan Jetty 6 Damaged part is good for the demonstration of repair.
Please refer to Photo 3.14.
Source: JICA Project Team
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-9
The condition of the selected jetties is shown in following Photo.
Source: JICA Project Team
Photo 3.13 Overall and Repaired Part of Kaingdan Jetty 1
Source: JICA Project Team
Photo 3.14 Overall and Deteriorated Part (Rebar Exposure) of Wadan Jetty 6 3-3-3 DETAILS OF ON-SITE TRAINING
(1) On-site Orientation
The outline of the on-site training was explained at the site by the Expert. The contents of the on-site training are the following:
- Visual inspection and sketches, - Sound survey, - Schmidt Hammer Test, - Sampling of concrete core, - Rebar detection, and - RC beam repair.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-10
Source: JICA Project Team
Photo 3.15 On-site Orientation (2) Visual Inspection and Sketches (Kaingdan Jetty 1)
The Expert explained about the deterioration and damages of Kaingdan Jetty 1 and how to carry out the visual inspection and sketches. The Expert showed how to use crack scale and draw cracks. After that, the Trainees tried to make sketches of crack and other deterioration. Most of the Trainees made sketches and became acquainted with it.
(3) Sound Survey
The Expert explained about the sound survey using a hammer. The sound survey is being done to detect peeled off concrete covering. From the sound made by the hammer upon hitting the concrete surface, it is possible to judge the concrete cover conditions such as peeling off. After the explanation by the Expert, the Trainees tried the sound survey using a hammer.
Source: JICA Project Team
Photo 3.16 Explanation of Sound Survey and Trial by the Trainees
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-11
(4) Schmidt Hammer Test
The Expert explained the principle and method of the Schmidt Hammer Test. The Schmidt Hammer Test aims to measure the value of rebounding at the concrete surface and to calculate the concrete strength through a formula. The Trainees used the Schmidt Hammer Test and estimated the concrete strength of the jetty.
Source: JICA Project Team
Photo 3.17 Explanation and Demonstration of the Schmidt Hammer Test (5) Sampling of Concrete Core
The Expert set a core drill in the pillar of the jetty and made a demonstration of core sampling. The Trainees operated the core drill for core sampling under the Expert’s instruction.
Also the Expert explained about the method of the compressive strength test of the core sample.
Source: JICA Project Team
Photo 3.18 Demonstration of Core Drilling and Participant’s Operation (6) Rebar Detection
Before core sampling, rebar detection is needed to avoid cutting the rebar by core drill. Rebar detection is also needed for repairing structural design. The Expert explained the method of rebar detection and demonstrated the test by using the equipment as shown in Photo 3.19. The rebar detector is a non-destructive test, which uses radar system. The Trainees operated the rebar detector under the Expert’s instruction.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-12
Source: JICA Project Team
Photo 3.19 Rebar Detector (Radar System)
Source: JICA Project Team
Photo 3.20 Demonstration of Rebar Detection and the Trainees’ Operation of the Equipment (7) Repair of the RC Beam
Cracks and rebar exposure occurred due to rebar corrosion at some beams at the Wadan Jetty 6. The Expert selected this jetty as a suitable site for the on-site training because the deterioration by rebar corrosion is popular in Yangon port.
The Expert removed the concrete covering and the rusted rebar, painted it with anti-rust paint, added a new rebar, and refilled new mortar. Time was limited to show how to repair the RC Beam during the training. Therefore, the Expert showed the repair process and explained the important points about the repair of the RC beam.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-13
Source: JICA Project Team
Photo 3.21 Condition of Deteriorated Jetty and Demonstration of Chipping
Source: JICA Project Team
Photo 3.22 Explanation and Demonstration about the Beam Repair (8) Question and Answer
The Expert answered questions from the Trainees during the on-site training. The main questions from the Trainees are as follows.
1) How to make sketches of deteriorated concrete 2) How to use hammer for sound survey 3) Points to note about Schmidt Hammer Test 4) Rebar detection and core drilling 5) Depth of rebar detector 6) How to repair wide area
3-3-4 RESULT OF ON-SITE TRAINING
The Trainees actively studied and tried to carry out the tests. They understood that concrete survey and repair, which were explained by the Expert, are very useful to maintain the jetties. Since the Expert donated the test equipment of crack scale, Schmidt Hammer, and test anvil, the Trainees were determined to continue doing the test using these equipment. The on-site training was successfully and safely completed.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-14
Source: JICA Project Team
Photo 3.23 Expert and Trainees 3-3-5 RESULT OF QUESTIONNAIRE SURVEY
The results of the questionnaire survey, which was conducted after site training, are shown below.
(1) Confirmation of Understanding of Site Training
Understanding of the site training has been confirmed through the following eight items. The correct answers for each item are shown in the figure below. It was found that almost all of the participants understood each item.
1) What characteristics does concrete have? 2) Why do you put rebar (reinforcing bar) into concrete? 3) Why does rebar not rust in good concrete? 4) Why will rebar rust in concrete under long time use and severe condition? 5) What damages will occur on reinforced concrete under long time use and severe condition? 6) How do you survey damages of reinforced concrete? 7) What do you need to take care when you repair damaged reinforced concrete? 8) Why do you need to maintain reinforced concrete structure for a long time?
Source: JICA Project Team
Figure 3.1 Accuracy Rate for Questions (Understanding of Site Training)
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
8)
7)
6)
5)
4)
3)
2)
1)Correct
Incorrect
Unanswered
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-15
(2) Contents of Training that the Participants Want in the Future
- How to use the checking equipment for inspection, such as hammer, by all engineers concerned with maintenance.
- Maintenance methods, except for the jetties, such as for buildings. - Maintenance methods for deteriorated concrete facility.
(3) Opinions about the Training from the Trainees
- It was a very good opportunity because we have acquired the knowledge and gained experiences related to maintenance of reinforced concrete structures.
- We were able to get not only knowledge about repair of damaged reinforced concrete structure but also experience during the site training.
- We got lots of beneficial knowledge about concrete structure from this training. 3-4 CLASSROOM LECTURE
3-4-1 OUTLINE OF THE CLASSROOM LECTURE
Title of training : Classroom Lecture on Maintenance of Reinforced Concrete Yangon Port Jetties
Date and time : 24 December 2015, 9:00 to 12:00
Place : Meeting Room at MPA Shipping Agency Department (Ahlone)
Number of participants : Total of 36 from MPA and IWT (hereinafter “the Participants”)
Trainer : Expert of JICA Project Team with Myanmar assistant engineers
Table 3.4 List of Participants
No. Name Department Designation
1 ***** MPA :Myanma Port Authority Chief Engineer 2 ***** MPA :Myanma Port Authority Deputy Chief Civil Engineer 3 ***** MPA :Myanma Port Authority Deputy Chief Civil Engineer 4 ***** MPA :Myanma Port Authority Divisional Engineer 5 ***** MPA :Myanma Port Authority Divisional Engineer 6 ***** MPA :Myanma Port Authority Divisional Engineer 7 ***** MPA :Myanma Port Authority Assistant Engineer 8 ***** MPA :Myanma Port Authority Assistant Engineer 9 ***** MPA :Myanma Port Authority Assistant Engineer 10 ***** MPA :Myanma Port Authority Assistant Engineer 11 ***** MPA :Myanma Port Authority Assistant Engineer 12 ***** MPA :Myanma Port Authority Assistant Engineer 13 ***** MPA :Myanma Port Authority Assistant Engineer 14 ***** MPA :Myanma Port Authority Assistant Engineer 15 ***** MPA :Myanma Port Authority Assistant Engineer 16 ***** MPA :Myanma Port Authority Foreman 17 ***** MPA :Myanma Port Authority Foreman 18 ***** MPA :Myanma Port Authority Foreman 19 ***** MPA :Myanma Port Authority Foreman 20 ***** MPA :Myanma Port Authority Foreman 21 ***** MPA :Myanma Port Authority Foreman 22 ***** MPA :Myanma Port Authority Foreman
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-16
No. Name Department Designation
23 ***** MPA :Myanma Port Authority Foreman 24 ***** MPA :Myanma Port Authority Foreman 25 ***** MPA :Myanma Port Authority Foreman 26 ***** MPA :Myanma Port Authority Senior Overseer 27 ***** MPA :Myanma Port Authority Senior Overseer 28 ***** MPA :Myanma Port Authority Senior Overseer 29 ***** MPA :Myanma Port Authority Senior Overseer 30 ***** MPA :Myanma Port Authority Senior Overseer 31 ***** MPA :Myanma Port Authority Concrete Technician 32 ***** MPA :Myanma Port Authority Foreman 33 ***** IWT :Inland Water Transport Assistant Engineer 34 ***** MPA :Myanma Port Authority Chief Concrete Technician 35 ***** MPA :Myanma Port Authority Manager 36 ***** MPA :Myanma Port Authority Supervisor
Source: JICA Project Team 3-4-2 OUTLINE OF THE PROGRAM AND DISPLAY
The main topics of the program are as follows: - Properties and characteristics of RC - Survey and diagnosis for RC - Results of pre-survey and on-site training - Repair and maintenance of RC - Question and answer
Concrete materials, rebar corrosion, and survey equipment were displayed during the training.
And the concrete materials that are used in Myanmar were confirmed by tour of the local concrete plant. - Concrete material (cement, aggregate, and admixture) - Model of rebar corrosion - Equipment for RC survey (test hammer, Schmidt hammer, core drill, rebar detector)
Source: JICA Project Team
Photo 3.24 Display of Equipment for Survey
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-17
3-4-3 CONTENTS OF CLASSROOM LECTURE
(1) Orientation
Mr. Iwami, the Team Leader of the JICA Project Team, explained to the Participants about the Project and the purpose of the lecture.
Source: JICA Project Team
Photo 3.25 Orientation (2) Lecture
The Expert explained the properties of reinforced concrete and maintenance. Then lecture was conducted about the survey method, diagnosis, technology of maintenance and also the results of the field survey at Yangon Port. The contents of the lecture are shown below.
- Properties of Reinforced Concrete and Maintenance - Inspection and Evaluation of Reinforced Concrete - Results of Inspection and Evaluation of Jetties in Yangon Port - Repair and Maintenance of Reinforced Concrete
Source: JICA Project Team
Photo 3.26 Explanation by Projector
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-18
(3) Explanation of Display
The Expert explained the materials of concrete (cement, aggregate, and admixture). The Expert also showed the model of rebar corrosion and explained the mechanism of corrosion.
Source: JICA Project Team
Photo 3.27 Explanation of Concrete Materials and Corrosion Model
During break time, the Participants inspected the display, which was very interesting for the Participants.
Source: JICA Project Team
Photo 3.28 Participants at the Display (4) Question and Answer
At the end of the lecture, the expert answered several questions from the Participants regarding the design for concrete structure under salt attack, how to maintain deteriorated jetties where the concrete cover has been peeled off and corroded.
And there were other specific questions regarding the actual problem, such as the maintenance method of the deteriorated building made from reinforced concrete.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-19
(5) Awarding Certificate
Finally, the Expert awarded certificates for completion of the lecture and crack scale to the Participants.
Source: JICA Project Team
Photo 3.29 Awarding of Certificates to Participants 3-4-4 RESULT OF CLASSROOM LECTURE
Many Participants took part in the lecture. They were very interested in concrete materials and survey equipment. They asked many questions about maintenance of concrete structures. In the classroom lecture, the topic of the Expert ranged from the basic of the concrete to the repair method of deteriorated and damaged concrete. The Expert, showing the illustrative cases, explained the practical methods extensively. It is hoped that the lecture will help them in the maintenance of the jetties.
Source: JICA Project Team
Photo 3.30 Photo of All Participants
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-20
3-4-5 RESULT OF QUESTIONNAIRE SURVEY
The results of the questionnaire survey, which was conducted after classroom lecture, are shown below.
(1) Ability Improved by the Classroom Lecture
Improvement of the following three items through the lecture was confirmed using four categories. The percentage of those who “improved” for each item is above half. Especially, the ratio of those who “improved very much” their ability on the “Characteristics of Reinforced Concrete and Maintenance” is over 30% and it seems that sufficient achievement has been obtained.
Source: JICA Project Team
Figure 3.2 Ability Improved by the Classroom Lecture (2) Contents of Lecture that the Participants Want in the Future
The contents of the lecture that participants want in the future were confirmed through multiple-choice questionnaire. The topic which has the largest quantity of responses is “how to repair damaged jetties in detail”, and the topic with the second largest response is “how to make new concrete structure more durable”.
Source: JICA Project Team
Figure 3.3 Contents of Lecture that the Participants Want in the Future (3) Opinions about the Lecture from the Participants
Out of the 36 people who attended the lecture, 25 people provided other comments on the lecture. According to the following main comments, it seems that almost all participants were satisfied with the lecture.
5%
56%
33%
6%
Characteristics of Reinforced Concrete and Maintenance
Not improved Improved littleImproved Improved very muchUnanswered
3%6%
72%
11%8%
Inspection and Evaluation of Reinforced Concrete
Not improved Improved littleImproved Improved very muchUnanswered
14%
61%
17%
8%
Repair and Maintenance od Reinforced Concrete
Not improved Improved littleImproved Improved very muchUnanswered
21%
11%
10%31%
22%
5%
Contents of Lecture that want to participate in the Future
How to inspect damaged jetties in detail
How to inspect many jetties effectively
How to fix an order of priority for many damaged jetties
How to repair damaged jetties in detail
How to make new concrete structure durability up
Other commnets
Other main comments
- More detailed method and technical lecture about rebar on old reinforced concrete
structure - Lecture on port design and calculation
- Inspection for checking of the actual condition, management of many deteriorated
jetties, effective maintenance of jetties, repair of salted concrete and corroded rebar, concrete quality in the construction site.
- Visual test like hammering and repair method (crack, concrete cover, and rebar
corrosion) - Common grade of concrete for construction of a jetty
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-21
- Today’s lecture is useful for me. I would like to invite you to hold lecture again. - Please lecture more about repair and maintenance of marine structure made of reinforced
concrete. - We could obtain a lot of knowledge for the maintenance of reinforced concrete through this
lecture. - We would appreciate it if you could give us more knowledge and technique about repair and
maintenance of deteriorated jetty. - I’m satisfied with this lecture because I could learn much knowledge about the maintenance of
reinforced concrete. 3-5 RECOMMENDATION FOR THE MAINTENANCE METHOD
3-5-1 CURRENT SITUATION RELATED TO THE MAINTENANCE OF PORT FACILITIES
Through the implementation of defect inspection, on-site training, classroom lecture, and follow-up on the technical transfer implemented in 2013, the following matters related to maintenance management have been identified and are discussed below.
(1) Implementation of Defect Inspection
The concrete quality of the Dalla Ferry Terminal is generally good and initial defects such as cracks have not been found. Since filling defect of the concrete has been observed, repair has been implemented (for the detailed contents, refer to Chapter 2).
(2) Implementation of Pre-survey
The repair method used after 2013, for which technical transfer was done, was appropriate. However, the scope of repair was not sufficient since there were some areas that had been left unattended and had been damaged significantly. As for the areas that had been repaired before 2013, appropriate method was not used and there were some cases where the facilities had deteriorated again.
Although MPA conducts visual inspection regularly, detailed inspection in the lower part of the facilities such as the abutment or slab of the porter way has not been conducted enough. Furthermore, although recording is performed on the inspection, effective utilization of these data may also be recommended as a task in the future.
(3) Technical Transfer (On-site Training and Classroom Lecture)
For the engineers/staff from MPA and IWT, although their knowledge about concrete is enough to some extent, the technology related to maintenance (inspection, survey, diagnosis, and countermeasure) is inadequate.
Not only those with management posts such as Chief Engineer and Deputy Chief Civil Engineer, but also officials in charge of maintenance such as Assistant Engineer and Divisional Engineer and workers such as foreman and overseer have participated in the site training and classroom lecture. The positive attitude of trying to absorb new knowledge and skills has been observed in performing the actual maintenance in the field. 3-5-2 RECOMMENDATION FOR THE MAINTENANCE METHOD
For proper maintenance management, it is important to repeat the cycle of “inspection and survey”, “diagnosis”, and “countermeasure”. Also, recording and preserving each data are important. The flowchart for proper maintenance is shown in the figure below.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
3-22
Source: JICA Project Team
Figure 3.4 Cycle of Maintenance Management
The recommendations for the implementation of proper maintenance management are discussed below. (1) Implementation of Proper Inspection, Survey, and Recording
During the technical transfer (on-site training), the visual inspection and recording have been explained, and cracks and other deterioration were sketched by the participants. In addition, explanation and practical training for other survey methods (hammering, rebar detection, core sampling) have also been conducted.
It is very important to implement the inspection, survey, and recording continuously.
(2) Implementation of the Proper Countermeasure
During the site training at the Wadan Jetty 6, the explanation and practical training of the repair of cracks and rebar exposure due to rebar corrosion were carried out. Although this is an example of repair method for a typical damage observed in the site, technical transfer had also been conducted in 2013 such as for crack repair and concrete cover repair. Inspection, survey and Countermeasure are important and The JICA Project Team suggests to be implemented continuously.
(3) Establishment of Maintenance Management Method and Effective Operation
The following are necessary in order to establish the proposed maintenance management method (“Proper Inspection, Survey and Record” and “Proper Countermeasure”) and to operate it effectively:
- Standards and manual of inspection, survey, and recording; - Standards and manual of the proper countermeasure and - Continued implementation of training and lecture.
(4) Other Recommendation (Repair Material)
In Myanmar, there is a case in which the working time could not be secured sufficiently because of the sea level fluctuations or climate change. Therefore, it is desirable that the repair material that can be cured in a relatively short period (mortar and cement for the repair section) can be procured in Myanmar.
Inspection and Survey
Record
Diagnosis
Record
Record
Countermeasure (Repair and Reinforcement)
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
4-1
CHAPTER 4 PUBLIC ANNOUNCEMENT
An expert of the Public announcement of the member of JICA Project Team accompanied the JICA, MPA, IWT, the other JICA Project Team, and the contractor and observed the defect inspection of the pilot project for restoration of Dalla Ferry Terminal Jetty. Inspection process was recorded, and interview to the participants of the inspection was conducted. The participants from MPA and IWT learned the importance of the inspection of the facilities as well as its design. Interview to the ferry passengers proved that the new ferry terminal had dramatically improved the convenience of the ferry service.
The Expert then covered the classroom lecture on the maintenance of reinforced concrete facilities and the on-site training on how to check the soundness of the facilities at the Yangon Port conducted by JICA Project Team. The lecture and training were held to improve the skills of MPA and IWT engineers/staff. The enthusiasm of the trainees indicates the importance of the appropriate training scheme to Myanmar.
The Expert will run an article in the “International Development Journal” this coming March regarding the above joint defect inspection and training including other various projects related to inland water transport facilities in the Yangon Port under JICA cooperation in the past eight years. It can reach many readers such as consultants, JICA staffs, researchers, and students or youngsters who want to be
professionals in the field of international cooperation. Furthermore, in two or three months, the article will
appear on the online news site called “JB Press (http://jbpress.ismedia.jp/)” run by the Japan Business Press, Co. Ltd. in its website.
It is expected that a number of business persons will know about the projects.
The JICA Project Team is also asking for the cooperation of the editor of “MYANMAR JAPON”, a free paper magazine in Myanmar, to introduce the cooperation not only to the local people but also Japanese people living and working in Myanmar.
Three ferry boats are now being used to provide transport services between the central part of Yangon City and the Dalla District and more than thirty thousand people use them every day. These ferry boats were also donated under Japanese grant aid in 2014.
Both ferry boats and port restoration projects are very good examples of Japanese official development assistance (ODA) whose outcome can be directly seen by the Yangon people. Recalling these projects and calling the public attention at the time of the joint inspection are indeed important from the point of view of improving the Japanese
presence in Myanmar.
Source: JICA Project Team
Photo 4.1 Situation of Interview
Source: International Development Journal (January 2016) Figure 4.1 International Development
Journal (January 2016)
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
5-1
CHAPTER 5 SUMMARY (OUTPUT AND EVALUATION)
5-1 BACKGROUND
On 2 and 3 May 2008, Cyclone Nargis struck the coastal areas of Myanmar and moved inland across the Ayeyarwady Delta, causing considerable human loss and damage to properties. The disaster caused widespread destruction of houses and vital infrastructures, including roads and port facilities. The facilities and fleets of inland water transport were also battered severely, paralyzing its operation and the distribution of basic human needs and commodities. As the restoration project of the port that was affected by Cyclone Nargis, “The Urgent Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar” was commenced the services by JICA Project Team from February 2009 and it was completed the last Phase in February 2015.
The past phases of the Project covered the areas damaged by Cyclone Nargis: Yangon Port, four main inland waterways and hub ports in the Ayeyarwady Delta. The counterpart agencies to the JICA Team were MPA (Myanma Port Authority) and IWT (Inland Water Transport). MPA is responsible for providing terminal facilities and necessary services such as pilotage, water supply, fuel bunkering and cargo handling. IWT is responsible for providing inland transport services, including cargo and passenger transport, ship building and repair. The steering committee was established and chaired by the Vice Minister of the Ministry of Transport (hereinafter referred to as “MOT”). The member of the steering committee includes the representatives of MPA, IWT, Embassy of Japan, JICA Myanmar Office, and the JICA Project Team and the steering committee have been held four times.
The Project scope were as follows;
Recommendation of Urgent Measure in Securing Safety Navigation in Yangon Port Preparation of Recovery Plan of Port Facilities in Yangon Port Preparation of Recovery Plan of Main Inland Waterways in the Project Area Capacity Development of Ship Crew and Navigation Capacity Development of Repairing Ships and Metal Structure Study of Tide Observation System Enhancement Study of Marine Disaster Risk Management Enhancement Social and Environmental Considerations Preparation and Implementation of Pilot Project
This Project (Phase 3) is the final compilation of the previous project (Phase 2) and it included
the following services:
Conducted the defect inspection after the 1-year defect notification period of the pilot project “The Pilot Project of Restoration of the Dalla Ferry Terminal Jetty ad Dalla Side”.
Conducted pre-survey, on-site training and classroom lecture about inspection and repair method of the concrete facilities.
Conducted seminar about ship and metal structure repairs at MMU. Implemented programs from 2009 including this Project (Phase 3) are depicted in the following
chart.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
5-2
Source: JICA Project Team
Figure 5.1 Implemented Programs of the Project 5-2 DEFECT INSPECTION
One year has passed since the completion of the construction of the Dalla Ferry Terminal Jetty, defect inspection was conducted to check whether or not there were defects, which were attributable to the workmanships of the Contractor. The defect inspection was summarized and reported to JICA upon confirmation of the completion of the repair woks. The following facilities were inspected:
Steel Structures: pontoon, movable steel bridge Concrete Facilities: porter way, walkway, slipway, revetment, fence Buildings: passenger terminal building, toilet
JICA Myanmar Office and JFE Engineering Cooperation signed the contract on January 31, 2014.
The whole of the Works was completed on October 28, 2014 which was the 270th day from the date of the commencement of the Pilot Project. The facilities were handed over to IWT and MPA on November 15, 2014.
The facilities, one year passed since completion, are generally in good conditions. No major defects or damages were found except for the minor ones such as sinking of concrete blocks at pedestrian walkway.
The joint inspection to identify the defective facilities was carried out on December 23, 2015. JICA (the Client), NK (the Consultant), and JFE (the Contractor) are the inspection members, and MPA and IWT (Counterparts and Owners) attended as witnesses. Not only items to be inspected and judgment rule of the defects by the Contractor but also procedure before and after the defect inspection and responsibility of the Client, the Consultant and the Contractor are explained at the joint inspection.
The Contractor commenced the repair works on 2 January 2016 and completed them in two weeks. Joint inspection was carried out on 21 January 2016 by NK and JFE with the presence of MPA and IWT to confirm the completion of the repair works. As a result of this inspection, it was confirmed that the Contractor had completed the repair works, which the Contractor is responsible for.
Phase 1
2009 2010 2011 2012 2013 2014 2015 2016
[Training]
Capacity Development of the
Ship Crew and Navigation
[Training]
Capacity Development of
Reparing Ships and Metal
Structures
[Study]
Supplemental Study on
Maritime Disaster Risk
Management
[Sutudy]
Study of Tide Observation
System
[Pilot Project]
Restoration Work for the Dalla
Jetty
Steering Committee
Phase 2 Phase 3
Step-1Ship manuvering
(1)
Step-2Leading & Sector Light
Step-1Arc Welding (Basic)
Step-2Sustainable Arc Welding
Step-3CO2 Welding & Test
Design (1)
PQ (1)
Tender(1)
Tender (2)
PQ (2)
Relocation(Botahtaung to Dalla)
PQ & Tender
(3)
Construction
Defect liability period
Seminar
Design (2)
Step-3Ship manuvering
(2)
Step-4Pontoon Building
Installation of 2 ATG at MP & MITT
Analysis for 1 year's data
Analysis for confirmation for Yangon and Tide Analysis for Delta
Tide Observation in Yangon
Tide Observation in Delta3 time for 3 month
Simulation of Nargis
Analysis of Future Cyclone &
Tsunami(Yangon)
Analysis of Future Cyclone & Tsunami (Delta Area)
Defect Inspection
Lecture for Marine Engineering
Seminar Seminar
Tide Observation in Yangon
Tide Observation in Delta3 time for 3 month
SC1 SC4SC3SC2
MainenanceTechnical Transfer
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
5-3
The Dalla Ferry Terminal is now equipped with two bridges and porter ways. The embarking and
disembarking ferry passengers do not cross at the same line, resulted in time saving and safety improvement. It is apparently observed that the number of passengers who choose the IWT ferry for commuting has increased. However, the maintenance management of the facilities by the counterparts (MPA and IWT) appears to be not efficient. Appropriate maintenances have not been carried out due to the lack of budget and work forces. For example, IWT can only use as much as US$ 500 per year as budget for maintenance of its facilities on the Yangon River including the Dalla Ferry Terminal, Pansondan Terminal, and Delta branch office.
It is desirable that regular inspections of the facilities are carried out such that the minor damages will not become the major damages that require the major repair works. The regular inspections will reduce the maintenance cost, which will also result in reduction of life cycle cost of the facility. Especially, for the facilities used by many users such as Dalla Ferry Terminal, it is expected that each component of the facilities is careful inspected regularly. Major repair may become necessary without the regular inspection, and may obstruct the passenger services severally.
MPA and IWT were not familiar about the international standard of defect inspection. They gained a better comprehension of the rule. The experience on the defect inspection in this Project will be useful for their future work. 5-3 RECOMMENDATION FOR THE MAINTENANCE METHOD
The pre-survey, on-site training and classroom lecture were conducted, with regard to the maintenance of RC structure.
As for the pre-survey, JICA Project Team first confirmed the jetties that had been repaired after the previous technical transfer conducted in 2013. Then the Expert of the JICA Project Team chose six jetties for the pre-survey, comparing the conditions of repairs before and after 2013. The methods of the survey on the site by the Expert were the visual inspection and the sound test using a hammer. The result of the survey was reflected to the contents of the lecture as well as the selection of the site for on-site training. Also this result was used as the base information for the recommendation of maintenance management.
During on-site training, inspection and repair of the RC structure were lectured. The contents of this training were visual inspection and sketches, sound survey, Schmidt Hammer test, sampling of concrete core, rebar detection and RC beam repair. The Expert answered questions from the Trainees during the on-site training. The main questions from the Trainees are “How to make sketches of deteriorated concrete”, “How to use hammer for sound survey”, “Points to note about Schmidt Hammer Test”, “Rebar detection and core drilling” and “How to repair wide area”.
Concrete materials, rebar corrosion, and survey equipment were displayed during the classroom lecture. The Expert introduced the technology of maintenance and explained the properties of RC concrete, the survey method, diagnosis, and the results of pre-survey and on-site training.
For the parts repaired after the previous technical transfer conducted in 2013, there were no
cracks and peeling off and they were in good condition. On the other hand, on the portions repaired before 2013, there were cracks, damaged concrete cover, and exposed rebars. Repair method by refilling with fresh mortar was simple. It is important to chip off deteriorated concrete, put anti-rust paint on the rebar, and refill fresh mortar or concrete on it.
The Trainees actively studied and tried to carry out the tests. They understood that concrete survey and repair, which were explained by the Expert, are very useful to maintain the jetties. Since the Expert donated the test equipment of crack scale, Schmidt Hammer, and test anvil, the Trainees were determined to continue doing the test using the equipment. Understanding the contents of the on-site training has been confirmed from the result of the questionnaire survey. It was found that almost all the trainees were satisfied with the training.
During the classroom lecture, the Expert replied the questions from the Participants. One of the
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
5-4
interesting questions was the difference between normal and salt attack environments. The Participant understood their working environment, and was eager to solve the indigenous problem in Yangon. Over 30 staff of MPA and IWT participated in the seminars, and the level of the Participants ranged from foreman to director. Especially, the site level staff vigorously participated in the site training and classroom lecture. They understood the importance of the maintenance management, and were determined to apply the learned skills for their works. According to the questionnaire survey after the lectures, almost all the Participants answered that they had learned new technology and they were very satisfied with the lectures. Many Participants replied that they wanted “more detailed method of repair RC concrete” as the next subject of the lecture. The seminars in the Project are very useful, it is expected that the similar seminars are carried out in future.
Results of the defect inspection of the pilot project of Dalla Ferry Terminal and the pre-survey of six jetties in Yangon Port were taken into account, and the JICA Project Team proposed a practical maintenance management method for RC concrete referring to repair methods in Japan. Although MPA conducts visual inspection regularly, detailed inspection at the lower parts of the facilities such as the abutment or slab of the porter way has not been conducted. The effective use of the recorded data in the inspections is expected. Though the knowledge of concrete is sufficient for MPA and IWT technical staff, the knowledge of maintenance (inspection, survey, diagnosis, and countermeasure) appears to be insufficient. The level of the Participants to the site training and classroom lecture in this Project ranged from foreman to director, and Participants were very eager to learn new technologies. For proper maintenance management, it is important not only repeating the cycle of “inspection and survey”, “diagnosis”, and “countermeasure”, but also keeping the records. Thus, in the Project a technique for sketching concrete damages was lectured. In order to establish and apply the proposed maintenance management method (inspection and survey, diagnosis, countermeasure, and record) in Myanmar prevalently, the followings will be important:
- Standardization and manual preparation of inspection and survey, diagnosis, and record - Standardization and manual preparation of countermeasure. - Continuous implementation of training and lecture.
5-4 PUBLIC ANNOUNCEMENT
An expert of the Public announcement accompanied the JICA, MPA, IWT, JICA Project Team, and the contractor and observed the defect inspection of the pilot project for rehabilitation of Dalla Ferry Terminal. Inspection process was recorded, and interview to the participants of the inspection was conducted. The participants from MPA and IWT learned the importance of the inspection of the facilities as well as its design. Interview to the ferry passengers proved that the new ferry terminal had dramatically improved the convenience of the ferry service. The Expert then covered the classroom lecture on the maintenance of reinforced concrete facilities and the site training on how to check the soundness of the facilities at the Yangon Port conducted by JICA Project Team.
The Expert will run an article in the “International Development Journal” this coming March regarding the above joint defect inspection and training including other various projects related to inland water transportation facilities in the Yangon Port under JICA cooperation in the past eight years. It can reach many readers such as consultants, JICA staffs, researchers, and students or youngsters who want to be professionals in the field of international cooperation. Furthermore, in two or three months, the article will appear on the online news site called “JB Press” run by the Japan Business Press, Co. Ltd. in its website. The JICA Project Team is also asking for the cooperation of the editor of “MYANMAR JAPON”, a free paper magazine in Myanmar, to introduce the cooperation not only to the local people but also Japanese people living and working in Myanmar.
It would be very important to announce publically the Japanese assistances to Yangon Port at the completion of the Project. The publication will increase the presence of Japan in Myanmar, which attract attentions of both Japanese and foreigners.
The Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union of Myanmar (Follow-Up) Final Report
Nippon Koei Co., Ltd.
5-5
5-5 OUTPUT AND EVALUATION OF OTHER WORK
Since this Project duration was only 1.5 month, utmost cautions was necessary in the preparation stage, such as smooth purchase and import of equipment or close communications with the counterparts.
An associate professor of marine engineering at TOKAI University had a seminar on ship building at the Myanmar Maritime University (MMU). This was to enhance the contents of this Project. The number of the participant was 200 over, which was far exceeded the expected number of 60. The popularity of the seminar would be probably due to the success of the previous Phase 2 seminar on disaster prevention.
One of the outcomes of this seminar is that TOKAI University and MMU will make a MOU (Minutes of Understanding) for exchange program. Project Team is confident that this will contribute to the development of human resources in the ship building, which MPA and IWT has been anxious for.
During this Project (Phase 3), it was confirmed that the scopes of the JICA Project Team in the previous Phases have contributed to the increase of the capacities of the counterparts. Among the scopes are capacity development of Ship Crew and Navigation, Capacity Development of Repairing Ships and Metal Structure, Study of Tide Observation System Enhancement, Study of Marine Disaster Risk Management Enhancement, and Preparation and Implementation of Pilot Project.
An example of the improvement of the technical skill is inspection and repair of the concrete structure. This Project conducted advanced seminar in continuation to the seminar in 2103, and it was confirmed that the counterparts have sufficient basic skills for concrete inspection and repair. The JICA Project Team is confident that the counterparts will conduct regular inspections on the concrete structures by the method learned from the Project. The Team also hope that inspection methods learned from defect inspection, field study, or seminar, will be applied to the counterparts’ new facilities, which will result in reduction of life cycle costs and in improvement of their financial status.
“The Urgent Project for Rehabilitation of Yangon Port and Main Inland Water Transport in the Republic of the Union on Myanmar” started in February 2009, and this Project (Phase 3) is the last series of the Project. Total 43 expatriates were assigned to their specific areas. Due to this diversity, technical assistances were conducted interdisciplinary, and the JICA Project Team received a high evaluation from the counterparts, other related authorities, and MOT.
The JICA Project Team hope that the counterparts will maintain and transfer the skill and knowledge learned from the Project, and develop them by themselves.
APPENDICES
APPENDIX 1 Photos of the Facilities to be Inspected APPENDIX 2 Photos of the Repaired Items
A1 - 1
APPENDIX 1 PHOTOS OF THE FACILITIES TO BE INSPECTED
Date. 23th December, 2015
1. STEEL STRUCTURE
1.1 Porter Way Roof Structure
Inspected Photo Remark
West Porter Way Roof Structure
East Porter Way Roof Structure
A1 - 2
1.2 Steel Bridge
Inspected Photo Remark
West Steel Bridge Structure Roofing Lighting
Steel Bridge Roof Structure and Lighting (West Steel Bridge)
Underneath of Steel Bridge (West Steel Bridge)
A1 - 3
Inspected Photo Remark
East Steel Bridge Structure Roofing Lighting
Steel Bridge Roof Structure and Lighting (East Steel Bridge)
Underneath of Steel Bridge (East Steel Bridge)
A1 - 4
1.3 Pontoon Made by IWT
Inspected Photo Remark
Pontoons made by IWT Pontoon Structure Hand Rail Stainless Steel Fender Bollard Manhole Cover Anchorage
Outside of Pontoon Pontoon Structure Hand Rail
Outside of Pontoon Pontoon Structure Bollard Stainless Steel Fender
A1 - 5
Inspected Photo Remark
Outside of Pontoon Manhole Hatch Cover
Outside of Pontoon Anchorage
Inside Pontoon (West Pontoon)
A1 - 6
Inspected Photo Remark
Inside Pontoon (East Pontoon)
Pontoon Connection (Land Side)
Pontoon Connection (River Side)
A1 - 7
2. CONCRETE FACILITIES
2.1 Slipway
Inspected Photo Remark
Stair Case at Slipway
Top Surface of Slipway
Side of Slipway
A1 - 8
2.2 Fence
Inspected Photo Remark
Fence Column Capping Concrete block
Connection at Column and Capping
Concrete Block
A1 - 9
2.3 Walkway
Inspected Photo Remark
Walkway around Terminal Building
Walkway from East Porter Way to Slipway
Walkway around Toilet
A1 - 10
2.4 West Porter Way
Inspected Photo Remark
Porter Way Pile Pile Cap Beam Slab
Underneath of Porter Way (Pile, Pile Cap, Beam, Slab, Abutment)
Slab of Porter Way
A1 - 11
2.5 East Porter Way
Inspected Photo Remark
Porter Way Pile Pile Cap Beam Slab
Underneath of Porter Way (Pile, Pile Cap, Beam, Slab, Abutment)
Slab of Porter Way
A1 - 12
2.6 Revetment
Inspected Photo Remark
Revetment (between Slipway and West Porter Way)
Revetment (between West Porter Way and East Porter Way)
Revetment (between East Porter Way and Fence Boundary)
A1 - 13
2.7 Pontoon Coating Concrete
Inspected Photo Remark
Concrete Coating of Pontoon by JFE Top Surface Longitudinal Side Surfaces Traverse Side Surfaces
Top Surface
Top Surface
A1 - 14
Inspected Photo Remark
Longitudinal Side Surface (River Side)
Longitudinal Side Surface (Land Side)
Traverse Side Surface (Outer Side)
A1 - 16
3. BUILDING
3.1 Terminal Building
Inspected Photo Remark
Passenger Terminal Building Interior facilities Exterior facilities
Interior Facilities (Ceiling, Lighting, Ceiling Fan) Passenger Waiting Area Passenger Service Office Manager’s Office I-Pay Service Shop
Interior Facilities (Doors) Passenger Waiting Area Passenger Service Office Manager’s Office I-Pay Service Shop
A1 - 17
Inspected Photo Remark
Interior Facilities (Window) Passenger Waiting Area Passenger Service Office Manager’s Office I-Pay Service Shop
Interior Facilities (Wall) Passenger Waiting Area Passenger Service Office Manager’s Office I-Pay Service Shop
Exterior Facilities Ventilation Louver Gutter and Downspout Roofing
A1 - 19
3.2 Toilet
Inspected Photo Remark
Toilet Interior Facilities Exterior Facilities Wooden Fence
Interior Facilities (Male Toilet) Ceramic Tile Wall Toilet Accessories
Interior Facilities (Male Toilet) Ceramic Tile Wall Toilet Accessories
A1 - 20
Inspected Photo Remark
Interior Facilities (Male Toilet) Ceramic Tile Wall Door
Interior Facilities (Female Toilet) Ceramic Tile Wall Toilet Accessories
Interior Facilities (Female Toilet) Ceramic Tile Wall Toilet Accessories
A1 - 21
Inspected Photo Remark
Interior Facilities (Female Toilet) Door
Exterior Facilities Wall Roofing Ventilation Louver
Wooden Fence
A2 - 1
APPENDIX 2 PHOTOS OF THE REPAIRED ITEMS
1. STEEL STRUCTURE
1.1 West Steel Bridge
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Timber plank is defected.
Timber floor connection is loosed and mounted.
Rust and Paint is defected.
One number of light bulb is defected.
A2 - 2
1.2 East Steel Bridge
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Rust and Paint is defected.
Timber floor longitudinal member is mounted and cracked.
Timber floor longitudinal member is mounted.
All lights are not working.
A2 - 3
2. CONCRETE FACILITIES
2.1 Slipway
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Surface plaster is defected.
Surface plaster is defected.
Concrete is defected, so rebar is come out.
Concrete is defected.
A2 - 4
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Concrete surface is defected and rebar is exposed.
A2 - 5
2.2 Fence
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
Top portion of fence column is cracked and rebar is appeared.
Top portion of fence column is cracked and rebar is appeared (Total 4 places).
A2 - 6
2.3 Walkway
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
ICB paver blocks are sunken.
ICB paver blocks are sunken and damaged.
ICB are sunk and damaged.
ICB are sunk and damaged.
A2 - 7
2.4 West Porter way
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
Pile cap bottom surface connection is defected (Total 3 places).
Edge of Porter Way slab (vertical surface) is defected.
All lights are not working.
A2 - 8
2.5 East Porter Way
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
5 numbers of light bulb are defected.
Concrete surface is defected.
Concrete surface of abutment (vertical side) is defected.
A2 - 9
2.6 Revetment
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
Some rubble stone in bottom portion are missing and crack appeared.
Revetment cracked base of Porter Way west.
A2 - 10
2.7 Pontoon Coating Concrete
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Steel angle is deformed and concrete is defected.
A2 - 11
3. BUILDING
3.1 Terminal Building
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
4 numbers of ceiling are defected.
Ceiling is defected.
Ceiling is defected.
A2 - 12
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Door is defected (bottom of the door close to floor level and difficult to swing).
6 numbers of glass window leaf are defected.
Mosquito net leaf is defected.
Door lock is defected.
Ceiling is defected.
A2 - 13
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016) Remark
Brackets are loosed.
Roof fascia is defected on one side .
Lightning cable middle bracket is loosed.
One number of lightning pole is loosed from bottom side.
A2 - 14
3.2 Overall Defects
3.2.1 Crack line
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
Crack line is occurred.
Crack line is occurred.
Crack line is occurred.
Crack line is occurred.
A2 - 15
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
Crack line is occurred.
Crack line is occurred.
Crack line is occurred.
Crack line is occurred.
Crack line is occurred.
A2 - 17
3.2.2 Rain Water Down Pipe
Defects Photo (23.12.2015)
Repaired Photo (21.1.2016)
Remark
Downpipe brackets are damaged.
Downpipe brackets are damaged.
Downpipe brackets are damaged.