“Expansion of Angle, Flat, Bar Channel" - Environmental ...

68
PROPOSAL FOR OBTAINING TERMS OF REFERENCE FOR Expansion of Angle, Flat, Bar Channel" {Category A (Due to presence of Nahargarh Wildlife Sanctuary at a distance of 0.84 Km and Eco Sensitive Zone boundary at a distance of 0.76 km) under Item 3(a)-Metallurgical industries (Ferrous &Non-Ferrous) of Schedule of EIA Notification, 2006 and its subsequent amendments } Location:- A-241, A 242 (b) & (c) A-242 (A), Vishwakarma Industrial Area, Road No.6 D, Jaipur, Rajasthan Project Capacity:-Existing: 75,000 TPA; Proposed: 75,000 TPA; Total: 1,50,000 TPA; Area: -21,017.5 Sq. m Baseline Data Generation : March’2021 to May’2021(Summer) Project Cost : Rs.72.0Crores (ExistingRs. 59.0 Crore, Proposed- Rs. 13 Crore) PROMOTER ENVIRONMENTAL CONSULTANT R.S. Infra-Transmission Limited A-241 (242-B), Vishwakarma Industrial Area, Road No.6 D, Jaipur Rajasthan 302013 Project In charge:- Devendra Gupta (Executive Director) E-mail:- [email protected] Gaurang Environmental Solutions Pvt. Ltd. #102, SNG Shree Ratna Apartment, Peetal Factory, Jhotwara Road, Bani Park, Jaipur-302016 E-mail: [email protected] NABET Accreditation: NABET/EIA/2023/RA 0192 dated 01.02.2021 valid up to 19.01.2023. August’2021

Transcript of “Expansion of Angle, Flat, Bar Channel" - Environmental ...

PROPOSAL FOR OBTAINING

TERMS OF REFERENCE

FOR

“Expansion of Angle, Flat, Bar Channel" {Category A (Due to presence of Nahargarh Wildlife Sanctuary at a distance of 0.84 Km and Eco Sensitive

Zone boundary at a distance of 0.76 km) under Item ‘3(a)’-Metallurgical industries (Ferrous &Non-Ferrous)

of Schedule of EIA Notification, 2006 and its subsequent amendments }

Location:- A-241, A 242 (b) & (c) A-242 (A), Vishwakarma Industrial Area, Road No.6 D,

Jaipur, Rajasthan

Project Capacity:-Existing: 75,000 TPA; Proposed: 75,000 TPA; Total: 1,50,000 TPA;

Area: -21,017.5 Sq. m

Baseline Data Generation : March’2021 to May’2021(Summer)

Project Cost : Rs.72.0Crores (Existing–Rs. 59.0 Crore, Proposed- Rs. 13 Crore)

PROMOTER ENVIRONMENTAL CONSULTANT

R.S. Infra-Transmission Limited

A-241 (242-B), Vishwakarma Industrial Area,

Road No.6 D, Jaipur Rajasthan 302013

Project In charge:- Devendra Gupta (Executive

Director)

E-mail:- [email protected]

Gaurang Environmental Solutions Pvt. Ltd.

#102, SNG Shree Ratna Apartment, Peetal Factory,

Jhotwara Road, Bani Park, Jaipur-302016

E-mail: [email protected]

NABET Accreditation: NABET/EIA/2023/RA 0192

dated 01.02.2021 valid up to 19.01.2023.

August’2021

Project : Expansion of Angle, Flat, Bar Channel, Jaipur

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

INDEMNIFICATION

Project : Expansion of Angle, Flat, Bar Channel, Jaipur

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

INDEMNIFICATION

Utmost care has been taken in preparation of this Report vis a vis proposed expansion of Angle,

Flat, Bar Channel from 75,000 TPA to 1,50,000 TPA at VKI Area, Jaipur promoted by R.S.

Infra-Transmission Limited. The data incorporated in the report is generated through

information received from clients in form of their project report received through e-mail,

secondary information, besides stakeholder’s interaction and inputs. Due care has been taken to

represent facts and figures and sources acknowledged. The purpose of this document is to

facilitate environmental appraisal of the proposal and as such the exercise has been scientifically

carried out. The Consultant stand indemnified against any consequences arising out of any

inadvertent omissions.

REVISION HISTORY

Report No. GESPL_397/2021 /ToR/87

Type of report Proposal for obtaining Terms of Reference

Revision No. 01

Issue to R.S. Infra-Transmission Limited

Issue Date 10.08.2021

************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Details of Studies

Conducted for the Project Promoter :R.S.Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

DETAILS OF STUDIES

CONDUCTED

FOR THE PROJECT

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Details of Studies

Conducted for the Project Promoter :R.S.Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

DETAILS OF STUDIES CONDUCTED FOR THE PROJECT

Name of the Project:-Expansion of Angle, Flat, Bar Channel from 75,000 TPA to 1,50,000 TPA at

VKI Area, Jaipur

Location:-A-241, A 242 (b) & (c) A-242 (A), Vishwakarma Industrial Area, Road No.6 D, Jaipur,

Rajasthan

Nature of

consultancy

Name and address of the

Consultant/Expert

Approvals, if any from

(NABL/DGMS/IBM/

NRBPT/MOEF/CPCB/others

etc)*, give reference

EIA/ EMP

Organization

Gaurang Environmental Solutions Pvt. Ltd.

#102SNG Shri Ratna Apartment, Peetal

Factory, Jhotwara Road, Jaipur-302016

E-mail:- [email protected]

NABET/EIA/2023/RA 0192

dated 01.02.2021 valid up to

19.01.2023.

EIA Coordinator Sanagapati C. Babu

FAE-LU Vinod Kumar Verma

FAE-AP Sanjay Palnitkar

Nidhi Bhardwaj

FAE-AQ MallikarjunaGuttula

Neha Bhargava

FAE-WP Sanjay Palnitkar

Pooja Yadav

FAE-SC Ratnakumar V Mudliar

FAE-EB Dr. Yati Kachhawa

Ginni Barotia

FAE-NV Sanagapati C. Babu

Mallikarjuna Guttula

FAE-SE Gajendra Singh Rathore

FAE-HG Mukesh Suroliya

Vidya Bhushan Trivedi

FAE-GEO Mukesh Suroliya

Vidya Bhushan Trivedi

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Details of Studies

Conducted for the Project Promoter :R.S.Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

FAE-RH Sanjay Palnitkar

Ginni Barotia

FAE-SHW Sanjay Palnitkar

Nidhi Bhardwaj (BMW & HW)

Environmental

Monitoring &

analysis

Nakshatra Enviro Services

66/ 40, Heera Path, Mansarovar,

Jaipur, Rajasthan, India, 302020

NABL certificate no. – TC –

7334 dated 28.08.2020 valid up

to 08.12.2021.

Hydro geological

study

Gaurang Environmental Solutions Pvt. Ltd.

#102 SNG Shri Ratna Apartment, Peetal

Factory, Jhotwara Road, Jaipur-302016

NABET/EIA/2023/RA 0192

dated 01.02.2021 valid up to

19.01.2023.

Soil Investigation Not Applicable --

Mining Plan Not Applicable --

Rainwater

Harvesting

Gaurang Environmental Solutions Pvt. Ltd.

#102 SNG Shri Ratna Apartment, Peetal

Factory, Jhotwara Road, Jaipur-302016

NABET/EIA/2023/RA 0192

dated 01.02.2021 valid up to

19.01.2023.

Risk Assessment Gaurang Environmental Solutions Pvt. Ltd.

#102 SNG Shri Ratna Apartment, Peetal

Factory, Jhotwara Road, Jaipur-302016

NABET/EIA/2023/RA 0192

dated 01.02.2021 valid up to

19.01.2023.

Architectural Plan Not Applicable

Ground Vibration

Study

Not Applicable

Subsidence Study Not Applicable

Services (STP/ETP

design) etc.

Not Applicable

Others, such as

project consultants

etc.

Not Applicable

* Only Govt. /Statutory Approvals to be mentioned. Put NA where not applicable.

** Team Member

***************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

S. No Particular Page No.

PRE-FEASIBILITY REPORT

1 SECTION 1 - EXECUTIVE SUMMARY 1

1.1 Executive Summary 2

2 SECTION-II INTRODUCTION TO THE PROJECT/

BACKGROUND INFORMATION

6

2.1 Identification Of Project And Project Proponent 7

2.1.1 Identification Of Project 7

2.1.2 Project Proponent 7

2.2 Brief Description Of Nature Of The Project 8

2.3 Need for the project and its importance to the Country and or region 8

2.4 Demand And Supply Gap 9

2.5 Imports Versus Indigenous Production 10

2.6 Export Possibility 10

2.7 Domestic/Export Market 10

2.8 Employment Generation (Direct And Indirect) Due To The Project 10

3 SECTION-III PROJECT DESCRIPTION 12

3.1 Type of project including interlinked and Interdependent projects, if

any

13

3.2 Location (map showing general location, specificLocation, and project

boundary and project siteLayout) with coordinates

13

3.3 Details Of Alternate Sites Considered And The Basis Of Selecting The

Proposed Site, Particularly The Environmental Considerations Gone

Into Should Be Highlighted

17

3.4 Size / Magnitude Of Operation 18

3.5 Project description with process details (aSchematic diagram/flow

chart showing theProject layout, components of the project etc.Should

be given)

18

3.6 Raw material required along with estimatedQuantity, likely source,

marketing area of finalProduct/s, mode of transport of raw material

29

Project : Expansion of Angle, Flat, Bar Channel, Jaipur

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

andfinished product

3.6.1 Raw Material 29

3.6.2 Product 30

3.7 Resource optimization/recycling and reuseEnvisaged in the project, if

any, should be brieflyOutlined

31

3.8 Availability of water, its source, energy / powerRequirement and

sourceshould be given

31

3.8.1 Water Availability & Its Source 31

3.8.2 Energy / Power Requirement& Its Source 34

3.9 Quantity of wastes to be generated (liquid andSolid) and scheme for

their management / disposal

34

3.9.1 Quantity of liquid waste to be generated & itsManagement / disposal 34

3.9.1.1 Domestic Waste Water 34

3.9.1.2 Industrial Waste Water 35

3.9.2 Quantity of solid waste to be generated & itsManagement / disposal 35

3.10 Schematic representations of the feasibilityDrawing which give

information of EIA purpose

36

4 SECTION-IV SITE ANALYSIS 37

4.1 Connectivity 38

4.2 Land Form, Land Use And Land Ownership 38

4.3 Topography (Along With Map) 39

4.4 Existing land use pattern (agriculture, non-Agriculture, forest, water

bodies (including areaUnder crz)), shortest distances from the

peripheryof the project to periphery of the forest, NationalPark, Wild

life sanctuary, Eco sensitive area, waterbodies (distance from the HFL

of the river), CRZ.

40

4.5 Existing Infrastructure 41

4.5.1 Basic Amenities 42

4.5.2 Industries 42

4.6 Soil Classification 43

Project : Expansion of Angle, Flat, Bar Channel, Jaipur

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

***************

4.7 Climatic Data From Secondary Sources 44

4.8 Social Infrastructure Available 44

5 SECTION –V PLANNING BRIEF 45

5.1 Planning concept (type of industries, facilities, Transportation etc)

town and country planning/Development authority classification

46

5.2 Population Projection 46

5.3 Land Use Planning (Breakup Along With Green Belt (Etc.) 46

5.4 Assessment Of Infrastructure Demand (Physical &Social) 48

5.5 Amenities / Facilities 48

6 SECTION-VI PROPOSED INFRASTRUCTURE 49

6.1 Proposed Infrastructure 50

7 SECTION –VII REHABILITATION AND RESETTLEMENT (R

& R) PLAN

52

7.1 Policy to be adopted (central/ state) in respect of the project affected

persons including home oustees, land oustees and landless laborers (a

brief outline to be given).

53

8 SECTION –VIII PROJECT SCHEDULE & COST ESTIMATES 54

8.1 Likely date of start of construction and likelyDate of completion 55

8.2 Project Cost Estimation 56

9 SECTION-IX ANALYSIS OF PROPOSAL 57

9.1 Financial And Social Benefits With Special Emphasis On The benefit

To The Local People Including Tribal population, If Any, In The Area

58

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-I

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 1

Report Ref: GESPL_397/2021/ToR/87 Rev. No. 00

SECTION-I

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-I

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 2

Report Ref: GESPL_397/2021/ToR/87 Rev. No. 00

SECTION-I

EXECUTIVE SUMMARY

1.1 EXECUTIVE SUMMARY

R.S. Infra-Transmission Limited is in operational since 1985 and situated at A-241, A

242 (b) & (c) A-242 (A), Vishwakarma Industrial Area, Road No.6 D, Jaipur, Rajasthan,

which involves production of Angle, Flat, Bar Channel to the tune of 75,000 TPA. The

company enhance the production of Angle, Flat, Bar Channel from 75,000 TPA to

1,50,000 TPA. The details of production are as under:-

Table 1.1: Details of Production

S. No. Name of Products Production Capacity (TPA)

Existing Proposed Total

1 Angle, Flat, Bar Channel 75,000 75,000 1,50,000

Reheating Furnace

(Capacity)

10 TPH x 1 no

and 20 TPH

1 No

No additional Re-

heating furnace will

be required

10 TPH x 1 no

and 20 TPH

1 No

Number of Hour One shift

(8 Hour)

Two Shifts

(14 Hour)

Three Shifts

(20 Hour)

No of working Days Per Year 300 days

The total plot area of the existing unit is 21,017.5 Sq.m and proposed expansion is coming

up within the same premises. Hence, no additional land is required for the proposed

expansion. There will be additional machineries will be installed after expansion. The

total cost of the project after proposed expansion will be Rs.72.0 Crores. (Existing–Rs.

59.0 Crore, Proposed- Rs. 13 Crore).

Table 1.2: Chronology of Consent to Establish and Consent to Operate

S.

No.

Particulars Production

Capacity

Letter No and Date Validity

Consent To Establish-HSD Steel Bar/Angle/Channel

1. Angle, Flat, Bar

Channel

115 TPD F(Tech)/Jaipur(Jaipur

(VKIA))/304(1)/2011-2012/11889-

11891 dated 28.03.2017

03.08.2016

to

31.07.2019

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-I

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 3

Report Ref: GESPL_397/2021/ToR/87 Rev. No. 00

Consent To Operate - Angle, Flat, Bar Channel

1. Angle, Flat, Bar Channel

The capacity will remain the same

as per CTO issued vide letter no

RPCB/RO/JP(N)/JP-VKIA-

081/1711-1713 dated 06.08.2004

Air and Water Act –

RPCB/RO/JP(N)/JP-VKIA-

081/3809 dated 21.03.2007

Valid up to

31.07.2011

2. Angle, Flat, Bar Channel

135 TPD Air and Water Act -

F(Tech)/Jaipur(Jaipur

VKIA))/304(1)/2011-2012/2478-

2479 dated 18.01.2012

01.08.2011

to

31.07.2016

3. Angle, Flat, Bar Channel

250 TPD Air and Water Act -

F(Tech)/Jaipur(Jaipur

(VKIA))/304(1)/2011-2012/11892-

11894 dated 28.03.2017

05.09.2016

to

31.08.2021

The Chronology of Consent to Establish and Consent to Operate are enclosed as Annexure-I.

As per NGT order of I.A. No. 04/2020 in O.A. No. 55/2019(WZ) dated 16/01/2020 on the

regulation of project requires environment clearance. Copy of NGT Order is enclosed as

Annexure-II.

The project activity is listed at category-‘B’ under item 3(a)-Metallurgical industries

(Ferrous &Non-Ferrous) as per the EIA Notification dated 14th September’ 2006 and

its subsequent amendments. Due to presence of Nahargarh Wildlife Sanctuary is at a

distance of 0.84 Km towards E from the site and Eco Sensitive Zone boundary at a

distance of 0.76 km towards ESE thus the project will be categorized as A and

considered at MoEF&CC, New Delhi.

The application regarding distance authentication has been applied to Forest Department,

Jaipur Division on dated 06.08.2021. Enclosed as Annexure-III.

NBWL application has been applied vide proposal no FP/RJ/IND/6000/2021

dated09.08.2021 for requisite clearance. Copy of the same is enclosed as Annexure-IV.

The project details are summarized as under:-

Table 1.3: Project Details

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-I

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 4

Report Ref: GESPL_397/2021/ToR/87 Rev. No. 00

S.

No.

Description Details

1 Name of the Project R.S. Infra-Transmission Limited

2 Address/ Location/

land details (Khasra

no.)

A-241, A 242 (b) & (c) A-242 (A), Vishwakarma Industrial Area,

Road No.6 D, Jaipur, Rajasthan

3 Total Plot area Area (Sq.m)

Existing Proposed Total

21,017.5 -- 21,017.5

4 Production Capacity Name of Products Production Capacity(TPA)

Existing Proposed Total

Angle, Flat, Bar

Channel

75,000 75,000 1,50,000

5 Water Requirement

and Source

S. No.

Water Consumption

Existing (KLD)

Proposed (KLD)

Total (KLD)

1. Domestic 4.0 7.0 11.0 2. Gardening 2.0 5.0 -

recycled water from

STP

7.0 – recycled

water from STP

3. Industrial Process (Cooling and quenching purposes)

150.0 150.0 300.0

Total 156.0 157.0 313 Fresh Water demand

9.0 10.0 17.0

*In existing unit 2 KLD fresh water demand is required for Gardening purposes. After expansion, STP treated water will be used for gardening purposes. Recycled water 146.0 147.0 294.0

Source RIICO/Tanker water suppy

Ground water supply (Bore well – proposed 1 no.)

Ground water supply (Bore well – proposed 1 no.)

6 Power Requirement

and Source

Power Demand

(kVA)

Existing Proposed Total

3000 1500 4500

Source Jaipur Vidyut Vitran Nigam Limited (JVVNL )

7 Back Up Source and Back Up Source Existing Proposed Total

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-I

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 5

Report Ref: GESPL_397/2021/ToR/87 Rev. No. 00

Fuel (DG set) 250 kVA- 1no -- 250 kVA- 1no

Fuel, Consumption HSD - 60 l/hr -- HSD – 60 l/hr

Source Local Traders

8 Re-heating Furnace Re-

Heating

Furnace

Existing Proposed Total

10 TPH x 1 no

and 20 TPH

1 No

No additional

Re-heating

furnace will be

required

10 TPH x 1 no

and 20 TPH

1 No

Fuel Requirement Fuel Requirement (Coal)

Existing Proposed Total

21 T/day 4 T/day 25 T/day

Source Tuna /Kandla Port Storage for 7 days

147 T 28 T 175 T

10 Employment

Generation

Existing (Nos.) Proposed (Nos.) Total (Nos.)

Construction Phase-NA

Operation Phase- 90

Construction Phase -30

Operation Phase-160

Construction Phase -30

Operation Phase-250

***************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-II

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 6

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-II

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-II

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 7

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-II

INTRODUCTION TO THE

PROJECT/BACKGROUNDINFORMATION

2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT

2.1.1 IDENTIFICATION OF PROJECT

R.S. Infra-Transmission Limited is situated at situated at A-241, A 242 (b) & (c) A-242

(A), Vishwakarma Industrial Area, Road No.6 D, Jaipur, Rajasthan involves production

of Angle, Flat, Bar Channel to the tune of 75,000 TPA. Now unit undergoes expansion of

Angle, Flat, Bar Channel from 75,000 TPA to 1,50,000 TPA.

2.1.2 IDENTIFICATION OF PROJECT PROPONENT

R.S. Infra-Transmission Limited is a Public incorporated on 22nd July’ 1985. It is

classified as Non-Govt Company and is registered at Registrar of Companies, Jaipur.

R.S. Infra-Transmission Limited manufactures steel products. The Company offers hot

rolled profiles and structural steel, as well as provides pre-heating, straightening, billet

cutting, and rolling services. Directors of R.S. Infra-Transmission Limited are Devendra

Gupta, Anil Vijay, Abhinav Gupta, Anil Kumar Gupta, Pulkit Chhabra and Rishabh

Gupta.

Name of the Promoter R.S. Infra-Transmission Limited

Name and Address of the

Promoter

Devendra Gupta (Executive Director)

A-241 (242-B), Vishwakarma Industrial Area, Road No.6 D,

Jaipur Rajasthan 302013

Corporate Identification

Number is (CIN)

U27107RJ1985PLC003362

Registration Number 3362

Status of Project Brownfield Project (Freshly applied for Environmental Clearance)

E-mail Id [email protected]

Contact Number +91-9829047715

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-II

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 8

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

2.2 BRIEF DESCRIPTION OF NATURE OF THE PROJECT

It is an expansion of Angle, Flat, Bar Channel from 75,000 TPA to 1,50,000 TPA

capacity.

2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE

COUNTRY AND OR REGION

India is the world’s third-largest producer of crude steel (up from eighth in 2003) and is

expected to become the second-largest producer by 2016. The growth in the Indian steel

sector has been driven by domestic availability of raw materials such as iron ore and cost-

effective labor. Consequently, the steel sector has been a major contributor to India’s

manufacturing output.

The Indian steel industry is very modern with state-of-the-art steel mills. It has always

strived for continuous modernization and up-gradation of older plants and higher energy

efficiency levels. While plant closures and privatization are rare in India, the private

sector is considered to be the engine of growth in the steel industry and technological

changes and modernization are taking place in both public and private sector integrated

steel plants in India.

The proposed expansion project will provide potential growth opportunity for the

company. We have identified the demand for the proposed products of “Metallurgical

industries (Ferrous & non-ferrous)”.It can be developed in-house and produce

commercially for the domestic market as well as for the International market. Its export

can also increase the foreign revenue. India being a developing country having huge

scope for being a lead exporter of Mild Steel & alloy Steel products in the global

markets. The products are well established and acceptable in the international markets.

Hence, the proposed project will significantly help the country’s economy by supplying

the products against the very high demand replacing supply from imported materials. In

addition to this, company has a plan for secure business by developing a business circle

and the circle industries require significant quantity of these products. Hence, the

company will have highly feasible & viable operation & business potential. The

industrial sector in the past few years has seen a drastic boom and also the keeping in

mind the globalization trend. Keeping in view on all above points, company have

determined market potential for the selected products & their demand and with valuable

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-II

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 9

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

R&D efforts by fully integrated and testing laboratory with advanced instruments.

Company is confident that it can develop the product in very economical route of

production and supply at very competitive price and will help the buyer company.

Company has also noticed that the products will be able to replace the demand of the

imported & costly products which in turn will provide a growth potential opportunity to

the company & buyers. Besides, there will be very good opportunity of employment

generation directly and indirectly due to proposed expansion project. The demand of such

products is tremendous in our country and there is a huge gap in the demand supply.

2.4 DEMAND AND SUPPLY GAP

Steel production of India accounted for 14.33 million tons in 1990-91, which gradually

increased to 36.12 million tons in 2003-04. Rapid rise in production has resulted in India

becoming the 3rd largest producer of crude steel in 2015 and the country continues to be

the largest producer of sponge iron or DRI in the world. As per the report of the Working

Group on Steel for the 12th Five Year Plan, there exist many factors which carry the

potential of raising the per capita steel consumption in the country. These include among

others, an estimated infrastructure investment of nearly a trillion dollars, a projected

growth of manufacturing from current 8% to 11-12%, increase in urban population to 600

million by 2030 from the current level of 400 million, emergence of the rural market for

steel currently consuming around 10 kg per annum. At the time of its release, the

National Steel Policy 2005 had envisaged steel production to reach 110 million tonnes

(mt) by 2019-20. However, based on the assessment of the current ongoing projects, both

in Greenfield and Brownfield, the Working Group on Steel for the 12th Five Year Plan

has projected that domestic crude steel capacity in the county is likely to be 140 MT by

2016-17 and has the potential to reach 149 MT if all requirements are adequately met.

The National Steel Policy 2005 is currently being reviewed keeping in mind the rapid

developments in the domestic steel industry (both supply and demand side) as well as the

stable growth of the Indian economy since the release of the Policy in 2005. India is

expected to become the world's second largest producer of crude steel in the next 10

years, moving up from the third position, as its capacity is projected to increase about 300

MT by 2025. Huge scope for growth is offered by India’s comparatively low per capita

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-II

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 10

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

steel consumption and the expected rise in consumption due to increased infrastructure

construction and the thriving automobile and railways sectors.

2.5 IMPORTS VERSUS INDIGENOUS PRODUCTION

Based on the assessment of the current ongoing projects, both in Greenfield and

brownfield, the Working Group on Steel for the 12th Five Year Plan has projected that

domestic crude steel capacity in the county is likely to be 140 MT by 2016-17 and has the

potential to reach 149 MT if all requirements are adequately met. The National Steel

Policy 2005 is currently being reviewed keeping in mind the rapid developments in the

domestic steel industry (both on the supply and demand sides) as well as the stable

growth of the Indian economy since the release of the Policy in 2005.India is expected to

become the world's second largest producer of crude steel in the next 10 years, moving

up from the third position, as its capacity is projected to increase to about 300 MT by

2025. Huge scope for growth is offered by India’s comparatively low per capita steel

consumption and the expected rise in consumption due to increased infrastructure

construction and the thriving automobile and railways sectors.`

2.6 EXPORT POSSIBILITY

Product will be supplied in domestic market. Also, export is envisaged as per market

demand.

2.7 DOMESTIC/EXPORT MARKET

The finished goods will be sold in domestic market and would be largely exported to the

Regulated International Market as per demand all over the world.

2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE

TO THE PROJECT

The proposed expansion project will provide direct employment during construction &

operational phase. Local workers will be hired from the nearby villages based on the

requirement and its fulfillment criteria. The details are given below:-

Table 2.1: Employment Details

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-II

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 11

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

S.

No.

Particulars Existing

(Nos.)

Proposed

(Nos.)

Total

(Nos.)

1 During Construction Phase NA 30 30

2 During Operation Phase 90 160 250

Total 90 190 280

*****************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 12

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-III

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 13

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-III

PROJECT DESCRIPTION

3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND

INTERDEPENDENT PROJECTS, IF ANY.

The proposed expansion project is a Rolling Mill Unit and enhance the production

capacity of Angle, Flat, Bar Channel from 75,000 TPA to 1,50,000 TPA situated at A-

241, A 242 (b) & (c) A-242 (A), Vishwakarma Industrial Area, Road No.6 D, Jaipur,

Rajasthan.

There is no interlinked project. The proposed expansion project is an individual project.

3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC

LOCATION AND PROJECT BOUNDARY & PROJECT SITE

LAYOUT) WITH COORDINATES

The existing unit is situated at A-241, A 242 (b) & (c) A-242 (A), Vishwakarma

Industrial Area, Road No.6 D, Jaipur, Rajasthan. The project site falls on Geological

Survey of India Toposheet No. 45N/13. The latitude and longitude of the project site are

as given below:-

Table 3.1 : Geographical Coordinates of the Project Site

1.Point 1

Latitude : 26°59'1.05"N

Longitude : 75°46'46.57"E

2.Point 2

Latitude : 26°58'55.97"N

Longitude : 75°46'46.40"E

3.Point 3

Latitude : 26°58'55.92"N

Longitude : 75°46'41.33"E

4.Point 4

Latitude : 26°59'1.13"N

Longitude : 75°46'41.38"E

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 14

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure 3.1: Location Map

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 15

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure 3.2: Topographical Map of 10 Km Radius.

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 16

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure 3.3: Map showing location of project site on Google Map of 1.0Km radius

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 17

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure3.4: Photographs showing Existing Plant

3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS

OF SELECTING THE PROPOSED SITE, PARTICULARLY THE

ENVIRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE

HIGHLIGHTED

No alternative site has been examined, as the proposed expansion is coming up within the

same premises.

The site is having required infrastructure facilities in form of water, electricity and Road

available for the expansion activities.Land Chronology is as under:-

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 18

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Table 3.2 : Chronology of Land Ownership

Plot Number Land Ownership Area

(Sq.m)

Date

A 241-A242 (b) & (c) RS Industries (Rolling Mill) Limited 17,325 13.09.1988

B-242 (A) RS Industries (Rolling Mill) Limited 3,692.50 2.06.2007

Total Area 21,017.5

The chronology of the land documents is as enclosed as Annexure –V.

3.4 SIZE OR MAGNITUDE OF OPERATION

The size and magnitude is as given below:-

Table 3.3: Size/Magnitude of Operation

S.

No.

Name of Products Production Capacity (TPA)

Existing Proposed Total

1 Angle, Flat, Bar Channel 75,000 75,000 1,50,000

Reheating Furnace

(Capacity)

10 TPH x 1

no and 20

TPH

1 No

No additional Re-

heating furnace will be

required

10 TPH x 1

no and 20

TPH

1 No

Number of Hour One shift

(8 Hour)

Two shift

(14 Hour)

Three Shift

(20 Hour)

No of working Days Per Year 300 days

3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A

SCHEMATIC DIAGRAM/FLOW CHART SHOWING THE

PROJECT LAYOUT, COMPONENTS OF THE PROJECT ETC.

SHOULD BE GIVEN)

The existing plant is involved in manufacturing of Angle, Flat, Bar Channel (75,000

TPA) by usingRe-heating furnace (10 TPH and 20 TPH-1 no x 1 no).Now unit is

undergoes expansion from 75,000 TPA to 1,50,000 TPA. After expansion existing

Reheating furnace capacity will remain the same.

PRODUCTION PROCESS OF STRUCTURAL SECTION

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 19

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

RE HEATING FURNACE

Reheating furnaces are used in hot rolling mills to heat the steel stock (Billets/Ingots) to

the rolling temperatures of around 1200 deg C which is suitable for plastic deformation of

steel and hence for rolling in the mill. The heating process in a reheating furnace is a

continuous process where the steel stock is charged at the furnace entrance, heated in the

furnace, and discharged at the furnace exit. Heat is transferred to the steel stock during its

traverse through the furnace mainly by means of convection and radiation from the

burner gases and the furnace walls.

Figure 3.5:Heat Transfer Mechanism In A Reheating Furnace

The charging temperature of the steel stock can range from ambient temperature to 800

deg C. The target exit temperature of the steel stock is governed by the requirement of the

process of rolling which is dependent on the rolling speed, stock dimension and steel

composition. Steel quality aspects put constraints on temperature gradient and surface

temperature. Fuel used in furnaces is being/will be coal. The schematic diagram of a

pusher type reheating furnace is shown at Figure 3.6

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 20

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure 3.6:Schematic Diagram of a Pusher Type Reheating Furnace

The size of reheating furnace is usually expressed as the capacity to supply hot steel stock

to the rolling mill from the cold stock and is expressed in tons per hour. The energy

efficiency of reheating furnace is usually defined as increase of steel stock heat content

when heated from 10 deg C to 1200 deg C divided by the fuel energy (latent heat plus

sensible heat) used for it. Typical longitudinal section of a reheating furnace is shown in

Figure 3.7.

Figure 3.7:Typical Longitudinal Section of A Reheating Furnace

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 21

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Many design features of the furnace affects the energy efficiency. These include

(i) Type of burners,

(ii) Furnace dimensions

(iii) Number of furnace zones

(iv) Type of wall and roof insulation

(v) Skid design

(vi) Preheating of fuel and combustion air in recuperators by the hot flue gases coming

out from the furnace exit.

An efficient furnace is designed in such a way so that in a given time the steel stock as

per furnace capacity is heated to a uniform temperature with the least possible fuel and

man-hours. The parameters important for furnace design include

(i) The quantity of heat to be imparted to the charge

(ii) Generation of sufficient heat which is is available within the furnace to heat the

steel stock as well as to overcome all steel losses

(iii) Transfer of generated heat to the surface of the steel stock to be heated

(iv) Equalization of temperature within the steel stock

(v) Loss of heat from the furnace to the minimum.

In the pusher type of furnace, cold steel stock is pushed forward with the help of pushers

at the charging side. Earlier, these furnaces were designed for heating billets or smaller

sections of blooms. The hearth of earlier furnaces was short in length and sloped

downward longitudinally towards the discharge end in order to permit easy passage of

steel stock through the furnace. Presently pusher furnaces are longer with hearths of

around 25 m to 30 m in length. These furnaces are equipped with either top firing or top

and bottom firing. These furnaces normally have three zones namely

(i) Preheating zone,

(ii) Heating zone, and

(iii) Soaking zone.

(iv) Multiple zone furnaces such as five zone slab reheating furnace have also been

designed and operated.

Cold steel stock can be charged in such furnace either from the end or through a side

door. In either case, the steel stock is moved forward by pushing the last piece charged

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 22

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

with a pusher at the charging end. With each pushing of the cold steel stock against the

continuous line of material, a heated piece is discharged at the discharge end either by

gravity through an end door upon a roller table feeding the rolling mill, or pushed through

a side door to the mill roller table by suitable manual or mechanical means, or withdrawn

through the end door by a mechanical extractor.

Re heating furnace process includes unloading and shifting of thebillets/ingots for the

inspections. After inspection cutting and charging to the reheating furnace is done. In the

furnace billets/ingots are heated to1200°C. Molten material is discharged to the six stands

cross country type rolling mill of 325mm size for Angle, Shape, and section an

dimensionalinspection than cooling below 100°C is done. Stacksare made for cooling.

After cooling the cutting to the desired length by shearing machine is done. After cutting

sections are shifted to straightening machine for straightening. After the test and

inspection sections are ready to dispatch.

Figure3.8: Prosess Flow Chart (Structural Section )

Reheating around 1200oC in Pusher

type furnace

End cutting by Shearing Machine &

Cutting length as pre requirement

Raw Material

Billets/Ingots

Unloading, Shifting

and Inspection

Cutting and Charging in Re-Heating

Furnace

Discharge from

furnace by ejector Addition of Micro

Alloys Components

Rolling in six stand cross country type 325 mm mill for Angle, Shape and Sections and

Dimensional Inspection

Manual Shifting on cooling bed and cooling

to below 1000c

Stacking manually on cooling side and

stacking for cooling

Manually Shifting on straitening

Machine for Straitening

Testing and

Inspection

Dispatch

Bundling and Storage

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 23

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

1. PRODUCT: TMT Bars, Round & Square Bars Manufacturing process:

➢ Heating of Billets/Ingots into Billets/Ingots Heating Chamber at the 11000C to 1200 0C temperature.

➢ The heated billets / ingots are ejected cut of the heating chamber in to a roll table by

the side of the heating chamber one by one and are pushed on to the main roller table

by a turning device.

➢ In case of hot charging, hot billet produced is directly transferred through conveyer to

rolling mill.

The discharged heated billets will be fed in to the first stand of roughing mills. The

number of passes are given depend on the section to be produced. After this the rolled

bar is fed in to successive stands to repeaters situated in lines. The front end of the

rolled bar is then cut to facilitate entry in to intermediate stand.

The rolling will be done in a continuous mill.

➢ Snap shears are used between each group of stands for taking samples to control the

mill looping and final section rolled.

➢ The hot rolled bar (called the ribbed bar) is automatically cut into length of upto

required length by shearing machine and transferred to a cooling bed.

➢ After cooling of the ribbed bar, it is again cut by a separate shearing machine in to

marketable lengths of generally 12 meter.

➢ Finally the TMT Steel is bundled and dispatch.

➢ For making TMT the hot rod is passed through a tube where water is counter flowing

under very high pressure. From cooling platform the TMT bars are taken to shearing

machine and cut individually to the required length and bundled for dispatch.

➢ During the manufacturing or products, there is no any metal surface treatment which

can generate polluted waste water and there is no any process gas emission during the

manufacturing of products.

➢ Water will be used for cooling purpose only and water requirement is only to

compensate the evaporation loss in the cooling system.

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 24

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure3.9: Prosess Flow Chart (Bar Mill)

3.5.1 PLANT & MACHINERY

The existing unit has Two Reheating Furnace of capacity 10 TPH and 20 TPH each,

which will be remain the same after expansion. Ther will be additional machineries will

be installed after expansion. The details of existing and proposed machineries &

equipment are as given below:-

Table 3.4 : Existing List of Machineries & Equipments

Sr.

No. Name of Machine Capacity Motor power rating

1

Mill-2 Roughing stand 20'' ( 3 Hi)- 2 nos

equipped with Reduction Gear Box,

Pinion stand, Flywheel 10 mt with 1500

HP Motor.

8000 Ton 1500hp,740 Rpm

Raw Material

Billets/Ingots Unloading Cutting and Charging

in Re-Heating Furnace

Reheating around 1200oC in

Pushertype furnace

Discharge from

furnace by ejector Rolling Water Quenching in TMT

Cutting by Flying Shear Shifting on cooling bed and

cooling below 1000c

Cutting Bars into fixed length

by cold shear

Shifting bars in yard for Building

Testing and Inspection

Dispatch

Bundling and Storage

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 25

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

2

Mill-2 16'' Intermediate Stands (3 Hi) - 5

nos. equipped with Reduction gear

box,pinion stand , flywheel 10 mt with

1500 HP Motor.

1500 hp,740 Rpm

3

Reheating Pusher Furnace for 20'' Mill

Fully Equipped with Oil and Coal

Pulvarisation system, Batch type

Furnace,with pusher & Ejector, Furnace

dimension 27 mtr x 5 mtr

20 Ton/hr

Blower Motor 75 HP,

2900 RPM.

Pusher 40 hp,960 Rpm

coal pulverizer (P3)75

hp,1440 Rpm

Coal Pulveriser (P4)

75 Hp, 1440 RPM

4 Automatic conveyor from Discharge

Zone to Colling Bed. (12" Mill)

5

Automatic Cooling Bed Walking Beam

type fitted with Pneumatic Cylinders.

(20" Mill)

6 Conveyor tilting table of Rough stand

(20" Mill)

Hydraulic Motor 20

HP, 960 rpm

7 Overhead EOT Crane (20'' Mill) 10 Ton

8 Overhead EOT Crane (16'' Mill) 10 Ton

9

Mill-1 Roughing stands 14.5'' (3 Hi) - 2

nos Fully equipped with Reduction gear

box, Pinion stands & 1000 HP Motor.

4000 Ton 1000 hp,740 Rpm

10

Mill-1 Intermediate Stands 12'' (3 Hi) -

4 stands equipped Flywheel , Reduction

gear box, Pinion stands, 800 HP motor.

4000 Ton

800 hp,740 Rpm

11

Mill-1 Finishing Stand 12'' (2 Hi)- 1 no.

fully equipped Flywheel , Reduction

gear box, Pinion gear box , 500 HP

motor.

500 hp,740 Rpm

12

Reheating Furnace for 12'' Mill

Fully Equipped with Coal Pulvarisation

system with pusher & Ejector, Furnace

dimensions 24 mtr x 5 mtr.

10 Ton/hr

Blower Motor 60 HP,

2900 rpm

pusher 40 hp,960 Rpm

Coal pulverizer (P1)

75 hp,1440 Rpm

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 26

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Coal pulverizer (P2)

75 hp,1440 Rpm

13 Overhead EOT Crane (14.5'' Mill) 7.5 Ton

14 Overhead EOT Crane (12'' Mill) 10 Ton

15 Conveyor System of 12'' Mill -

16 Conveyor System of 20'' Mill -

17 EOT crane (20'' Mill Straightening

Machine) 2 MT

18 EOT Crane (CNC Room) 5 MT

19 EOT crane For Straightening Machine 10 Ton

20

Descaling system for 20'' & 12'' mill for

primary & secondary descaling

consisting of

Water Jet Pressure

265 Bar

180 hp,1440 Rpm

(3 nos. of Motor)

Centrifugal Pumps 15

Hp, 1440

(2 nos of Pump

&Motor)

a) High pressure plunger pump InoxiHP

with flow rate 234 LPM & working

pressure 265 bar with electric motor of

132 KW

b) Descaling valves with hot metal

detector

c) Primary & secondary descaling Box ,

Headers with nozzles

d) High pressure pipe lines with

filteration system.

e) Electric Control Panel

21 Straightening Machine 260 CTR (12''

Mill) – Old 260 CTR 40 hp,1440 Rpm

22 Straightening Machine 260 CTR (12''

Mill) – New 260 CTR 40 hp,1440 Rpm

23 Straightening Machine 400 CTR (12''

Mill) 400 CTR 75 hp,1440 Rpm

24 Straightening Machine 700 CTR (20''

Mill) 700 CTR 200 hp,1440 Rpm

25 Straightening Machine 450 CTR (20''

Mill) 450 CTR 100 hp,1440 Rpm

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 27

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

26 Billet Shearing Machine 5'' Upto Square (125x125

mm) 120 hp,960 Rpm

27 Shearing Machine -20'' Mill Upto 200X200X25 Sections 40 hp,1440 Rpm

28 Shearing Machine - 12'' Mill Upto 90x90x10 Sections 10 hp,960 Rpm

29

Mill-1 Air pollution Control Device

(APCD) Consisting of

1. Multi cyclonic Seperator

2. Centrifugal Spray Scrubber

3. ID Fan

10 Mt/hr

Emission generation: Upto

10000Nm3/hr

ID Fan motor 30 HP,

1440 RPM

Pump 3 HP ,2900

RPM

Pump 5 HP, 2900

RPM

30

Mill-2 Air pollution Control Device

(APCD) Consisting of

1. Multi cyclonic Seperator

2. Centrifugal Spray Scrubber

3. ID Fan

20 Mt/hr

Emission generation: Upto

18000Nm3/hr

ID Fan motor 50 HP,

1440 RPM

Pump 3 HP ,2900

RPM

Pump 7.5 HP, 2900

RPM

Table 3.5 : Proposed List of Machineries & Equipments

1

CNC Lathe machine for Roll

Turning Model Contur Dialoh H-

110/3000 (Year of manufacturing

2008) Controls ; Siemens 840 D SL

+ Shop turn

Swing over bed; 780 mm

Swing over cross slide;

535

Cross slide travel; 430

mm

Maximum cutting length;

2900

2 Air Compressor Model GA37VSD

FF Sr. No.- PNA309187

FAD; 84.1 lps, Max.

Pressure; 13 Bar

Motor Power; 37

KW/50HP

Year of Manufacture ;

2013

50 hp,2900 Rpm

3 Air Compressor Model GA 55VSD

FF Sr. No.- PNE610905

FAD; 175.2 lps, Max.

Pressure; 12.75

Bar, Motor Power; 55

KW/75 HP

75 hp,290 Rpm

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 28

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Year of manufacture;

2016 H

4

CNC Lathe machine

Make - GMW

Type ( Model) - CPT-36, GMW/HL

1070X2000/2019

Swing over bed; 940 mm

Swing over cross slide;

550 mm

Swing over gap; 1200

mm

5

CNC Lathe Machine

Make; Pinacho

Model STH-500-130X3000 2 Axis-

FANUC 01TF + TURNMATE

Center Height; 500 mm

Swing over the bed;

Ø1010 mm

Swing over the carriage ;

Ø 935

Distance between

centers; 3000 mm

6

CNC Vertical Machining Center

Make; Haas

Model; VF-5/40-I

TRAVEL LENGTHS -

1270 MM

WIDTH - 660 MM

Height -635 MM

10,000 RPM SPINDLE ,

40 TAPER,

30HP Vector Drive

7 Hot Saw Machine

Modal - HS 1200

Blade 1200 MM

Blade Thickness -7 MM

No of Teeth -320

Blade motor - 75 hp,1440

Rpm,

Hydraulic motor- 5

hp,1440 Rpm

8

Mill-1 Air pollution Control Device

(APCD) Consisting of

1. Multi cyclonic Seperator

2. Centrifugal Spray Scrubber

3. ID Fan

10 Mt/hr

Emission generation:

Upto 10000Nm3/hr

ID Fan motor 30 HP, 1440

RPM

Pump 3 HP ,2900 RPM

Pump 5 HP, 2900 RPM

9

Mill-2 Air pollution Control Device

(APCD) Consisting of

1. Multi cyclonic Seperator

2. Centrifugal Spray Scrubber

3. ID Fan

20 Mt/hr

Emission generation:

Upto 18000Nm3/hr

ID Fan motor 50 HP, 1440

RPM

Pump 3 HP ,2900 RPM

Pump 7.5 HP, 2900 RPM

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 29

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

# Existing APCD will be replaced after expansion.

Figure3.10: Plant Layout

3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED

QUANTITY, LIKELY SOURCE, MARKETING AREA OF FINAL

PRODUCT/S, MODE OF TRANSPORT OF RAW MATERIAL AND

FINISHED PRODUCT

3.6.1 RAW MATERIAL

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 30

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

All raw materials required for manufacturing of products are easily available

indigenously in local market, which will be transported through road. The details of the

raw material requirement are presented below:-

Table 3.5: Product wise List of Raw Material and its Consumption

S.No. Name of the Product Raw

materials

Quantity (MT/Annum)

Existing Proposed Total

1. Angle, Flat, Bar

Channel

Billets/Bloom 77,250 77,250 1,54,500

Coal for Re-

Heating

Furnace

6,300 1,200 7,500

Table 3.6: Details of Source, Transportation & Storage Raw Materials

S.No. Raw

Material

Storage Capacity for

7 days (T)

Physical

State

Modeof

Transport

Storage Type of

Linkage

Existing Proposed Total

1. Billets/Bloom 1,803 1,803 3,606 Solid Road Designated

Finished

yard under

shed

SAIL

Copy of MoU is

enclosed as

Annexure-VI.

2. Coal 147 28 175 Solid Road Designated

Finished

yard under

shed

Tuna /Kandla Port

1. Material balance for TMT bar and Sections (Rolling Mill)

S. No. Raw Material Quantity (Tons)

Output Quantity (Tons)

1. Ingots/Billets 103 TMT 97 2.

Waste fines and gases 6

Total 103 Total 103

3.6.2 PRODUCTS

Table 3.7: Details of Production

S.No. Name of Products Production Capacity(TPA) Existing Proposed Total

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 31

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

1 Angle, Flat, Bar Channel 75,000 75,000 1,50,000

3.7 RESOURCE OPTIMIZATION/RECYCLING AND REUSE

ENVISAGED IN THE PROJECT, IF ANY, SHOULD BE BRIEFLY

OUTLINED

The water is mainly required for cooling purposes in Rolling Mill.The water will be used

in closed cooling circuit where 100% water will be recycled. 100% of waste water is and

will be recycled and Zero discharge condition will be maintained. The raw material used

in the project is mainly billets/ingots which is a solid waste generated from most of the

activities / operations come across in our day to day life. Thus the project is being/will be

reusing the waste iron scarps. By this way, the project will conserve a significant quantity

of iron ore and coal.

3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER

REQUIREMENT AND SOURCE SHOULD BE GIVEN

3.8.1 WATER AVAILABILITY & ITS SOURCE

Total water demand for existing unit is 156 KLD. Out of which industrial purposes

(cooling and quenching) 150 KLD water is being required. For domestic purposes 4.0

KLD and plantaion 2.0 KLD water is required. Existing water demand is met from

RIICO water supply and Tanker water supply. After expansion total water demand will

be 311 KLD. Water demand after expansion will be met through Ground water supply.

The application for the ground water abstraction will be submitted to the Office of CGWA.

Water balance for existing, proposed and total are shown as under:-

Table 3.8 : Water Requirement

S. No.

Water Cosnumption

Existing (KLD)

Proposed (KLD)

Total (KLD)

1. Domestic 4.0 7.0 11.0 2. Gardening 2.0 5.0 - recycled water

from STP 7.0 – recycled water

from STP 3. Industrial Process

(Cooling and quenching purposes)

150.0 150.0 300.0

Total 156.0 157.0 313 Fresh Water demand 9.0 10.0 17.0 *In existing unit 2 KLD fresh water demand is required for Gardneing purposes. After expansion, STP trtetaed water will be used for gardening purposes. Recycled water 146.0 147.0 294.0

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 32

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Source: RIICO/Tanker water suppy

Ground water supply (Borewell – proposed 1 no.)

Ground water supply (Borewell – proposed 1 no.)

Figure 3.11: Water Balance-Existing

Daily Fresh water Demand

9.0 KLD

Total Water Requirement 156 KLD

(Recycled water - 147 + 9 KLD -

Fresh water)

Domestic water

4.0 KLD

Industrial Purposes (Cooling and quenching)

– 150 KLD

Greenbelt/ Plantation

2.0 KLD

Settling Water Tank

147 KLD

Recycled

147 KLD Septic Tank followed

by Soak Pit - 3.0 KLD

Evaporation loss

3.0 KLD

Consumption

1.0 KLD

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 33

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure 3.12: Water Balance– Proposed

Daily Fresh water Demand

10.0 KLD

Total Water Requirement - 157 KLD

(Recycled Water -147 KLD +

Fresh Water – 10 KLD

Domestic water

7.0 KLD

Industrial Purposes

(Cooling and quenching) – 150 KLD

Settling Water Tank

147 KLD

Recycled water

147 KLD

STP – 10 KLD

Waste water –6.0 KLD

Evaporation loss

3.0 KLD

Consumption

1.0 KLD

Sludge used as manure

Green Belt 5.0 KLD

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 34

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Figure 3.13: Water Balance - Total

3.8.2 ENERGY / POWER REQUIREMENT& ITS SOURCE

S. No. Particulars Unit Existing Proposed Total Source

1 Power kVA 3000 1500 4500 JVVNL

2 DG Set (Number

and capacity)

kVA 250 –

1 no

-- 250 –

1 no

From

manufacture

3 HSD (for DG Set) l/hr 60 -- 60 Local Traders

4 Coal (for Re-

heating furnace)

T/day 21

4

25 Tuna /Kandla

Port

3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND

SOLID) AND SCHEME FOR THEIR MANAGEMENT / DISPOSAL

3.9.1 QUANTITY OF LIQUID WASTE TO BE GENERATED & ITS

MANAGEMENT / DISPOSAL

3.9.1.1 Domestic Waste Water

Approximatly 3.0 KLD Domestic wastewater is being generated from the existing unit,

which is disposed off into septic tank followed by soak pit. After expansion to the tune of

Sludge used as manure

Green Belt

7 KLD

Daily Fresh water Demand

17.0 KLD

Total Water Requirement 311 KLD

(Recycled Water -294 KLD +

Fresh water - 17 KLD)

Domestic water

11.0 KLD

Industrial Purposes

(Cooling and quenching) –

300 KLD

Settling Water Tank

294 KLD

Recycled - 294 KLD

STP – 10 KLD

Waste water –9.0 KLD

Evaporation loss

6.0 KLD

Consumption - 2 KLD

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 35

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

9.0 KLD will be generated. Which will be treated into STP (10 KLD). Treated water

from STP will be reused in greenbelt/plantation purposes. Sludge will be generated and

utilized as manure for greenbelt development/ plantation within the plant premises.

3.9.1.2 Industrial Waste Water

There will be no industrial effluent generation, as the water from cooling will be

recycled. Hence, there will be no any discharge of wastewater outside the company

premises;thus the unit will achieving ZLD.

3.9.2 QUANTITY OF SOLID WASTE TO BE GENERATED & ITS

MANAGEMENT / DISPOSAL

1. Solid Waste Generation

Table 3.9: Solid Waste Generation

S.

No.

Particulars Quantity Mode of Disposal

Existing Proposed Total

1. Domestic solid

waste

45

Kg/day

80

Kg/day

125

Kg/day

Will be handled by

Regiona Municipal

Corporation Jaipur

2. Coal ash 4.0

kg/day

1.0

kg/day

5.0

kg/day

Sent to brick

manufacturing units

3. Construction waste -- -- -- There will be no major

construction activity

carried out. Only

fabrication and

installation of additional

machineries will be

carried out.

2. Hazardous Waste

Table 3.10: Hazardous Waste Generation

Particulars Category Management

Used/Spent oil 5.1 Sold to register users

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-III

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 36

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

3.10 SCHEMATIC REPRESENTATION OF THE FEASIBILITY

DRAWING WHICH GIVE INFORMATION OFEIA PURPOSE

The project activity is listed at category-‘B’ under item 3(a)-Metallurgical industries

(ferrous & non-ferrous) would require environmental clearance as per the EIA

Notification dated 14th September’ 2006 and its subsequent amendments till date.

**************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 37

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION -IV

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 38

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION -IV

SITE ANALYSIS

4.1 CONNECTIVITY

R.S. Infra-Transmission Limited is a proposed expansion of Expansion of Angle,

Flat, Bar Channel Unit. The existing unit has all possible amenities that are feasible

for industrial projects viability.

Table 4.1: Connectivity

S. No. Name Distance (Km) Direction

(From project site)

Nearest Railway Station

1 Jaipur Junction 6.8 S

Nearest Airport

2 Jaipur International Airport 17.7 SSE

Nearest Highway

3 NH 8 1.7 NW

SH 19 3.4 NNW

SH 2C 6.6 WSW

SH 55 9.5 ESE

Sikar Road 0.45 W

Nearest Fire Station

4. Agnishaman Kendra, VKI 0.98 S

4.2 LAND FORM, LAND USE AND LAND OWNERSHIP

Land Form: The existing unit is situated over an area of 21,017.5 Sq.m, which is an

industrial area (VKI).

Land Use: The land use breakup (internal) is summarized as under:-

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 39

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Table 4.2: Land use Breakup

S.

No.

Particulars Existing Proposed Total

Area (Sq. m.)

1 Plant Area/Work Shed 8196.8

(39%)

-- 8196.8

(39%)

2 Built-up (excluding work

shed)

840.7

(4%)

-- 840.7

(4%)

3 Roads & paved areas

(including parking)

2,732.3

(13%)

-- 2,732.3

(13%)

4 Green Belt 2,522.1

(12%)

2,732.3

(13%)

5,254.4

(25%)

5 Open area 6,725.6

(32%)

-- 3,993.3

(19%)

Outside the plant area 10% green belt will be provided

Total 21,017.5 -- 21,017.5

Land Ownership: -The details of land ownership is as given below:-

Table 4.3: Chronology of Land Ownership

Plot Number Land Ownership Area (Sq.m)

Date

A 241-A242 (b) & (c) RS Industries (Rolling Mill) Limited 17,325 13.09.1988 B-242 (A) RS Industries (Rolling Mill) Limited 3,692.50 2.06.2007

Total Area 21,017.5

The chronology of the land documents is as enclosed as Annexure –V.

4.3 TOPOGRAPHY (ALONG WTH MAP)

The general slope of the Jaipur city and its surroundings is from north to south and then

to south-east. Nearly all the ephemeral streams flow in this direction. Higher elevations in

the north exist in the form of low, flat-topped hills of Nahargarh (587 meters). Jaigarh,

Amber and Amargarh, which are deeply dissected and eroded. An isolated hillock called

“Moti Dungari” upon which an old royal castle exists, is near the Rajasthan University.

Further in the south, topographical levels of the plain areas varies between 280 meters

along Bandi and Dhund rivers in the south to some 530 meters in the north east of Chomu

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 40

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

near Samod hills. The overall trend is a decline of level from the areas bordering the hills

in the north to plain in the south slopes of the plain areas are in general gentle.

Figure 4.1: Topographical Map of 10 km radius

4.4 EXISTING LAND USE PATTERN (AGRICULTURE, NON-

AGRICULTURE, FOREST, WATER BODIES (INCLUDING AREA

UNDER CRZ)), SHORTEST DISTANCES FROM THE PERIPHERY

OF THE PROJECT TO PERIPHERY OF THE FOREST, NATIONAL

PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREA, WATER

BODIES (DISTANCE FROM THE HFL OF THE RIVER), CRZ.

Existing Land use:-Land use pattern is given in Table 4.2.

The details of Forests, National Park, Wild Life Sanctuary, Eco Sensitive Area, Water

Bodies within 15 km area are as mentioned below:-

S. No. Particulars Distance (Km) Direction

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 41

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Conservation plan of Schedule species found within study area will be mentioned during

preparation of Final EIA.

The proposed expansion project is situated within notified industrial Area (VKI, Jaipur).

4.5 EXISTING INFRASTRUCTURE

There is an existing unit, which is situated an industrial land. The proposed expansion is

coming up within the same premises. The area is well connected by NH-8, which is 1.7

(From Project Boundary)

P.F/R.F

1. Papad ka R.F. 3.0 ESE

2. Nindhar P.F. 3.3 NW

3. Amer R.F. 4.2 E

4. Nahargarh R.F. 4.0 SE

5. Bhagawali Kalojar R.F. 7.6 ESE

6. Kilangrah R.F. 8.8 SE

7. Ambagarh R. F. 11.3 SE

8. Dalreri Ka Bir 13.8 SE

9. Jhalana bani R.F. 11.5 SE

10. R.F.(Malviya Nagar) 12.9 SSE

11. R. F. (Govindpura) 9.2 WSW

National Park

1. None within 10Km radius -- --

Wildlife Sanctuary

1. Nahargarh Wildlife Sanctuary 0.84 E

Eco Sensitive Area

1. Eco Sensitive zone Boundary 0.76 ESE

Water Bodies

1. Amanishah Nala 5.2 S

2. Sagar Talav 7.0 E

3. Jal Mahal 8.0 ESE

4. Bandi Nadi 11.4 NW

Source: - All distance are taken with respect to Toposheet.

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 42

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

km towards NNW from the site. SH-19, which is 3.4 km towards NNW from the site.

The study area is having facilities for Primary Educational and Health Care, Drinking

Water, Post and Telegraph Offices, Approach Roads etc.

4.5.1 BASIC AMENITIES

The details of basic amenities like Schools, Hospitals and Medical Center located in 10.0

km of project site is given as under:-

Table 4.4: Basic Amenities

S. No. Particulars Distance (Km) & Direction

(From Project Boundary)

Medical facility

1. Govt. Hospital 2.6, WSW

2. Rajkiye Chikitsalya 3.1, SSW

3. PHC 2.0, SSE

Schools

4. Govt. Senior School 1.0, SE

5. Government School 2.4, NNW

6. Government Secondary School 1.7, SSW

Place of Worship

7. Shri Tat Kaleshwer Mahadev Temple 1.2, W

8. Maha Shiv Temple 1.0, SE

9. Shiva temple 1.3, NNE

*Source: - All distances are taken with respect to Toposheet.

4.5.2 INDUSTRIES

This is an existing unit situated within notified industrial area, VKI, Jaipur. The proposed

expansion is coming up within the same premises. There are Alloy casting, Food

processing, Batteries, Pharma, Dye, Electroplating, Engineering services, fabrication

(Iron and Steel), Re-rolling, Pesticides etc types of industries situated with well-

developed infrastructure facilities within study area.

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 43

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

4.6 SOIL CLASSIFICATION

According to soil taxonomical classification, there are six categories of classification i.e.

i. Order (the broadest category) ii. Suborder, iii. Great group, iv. Subgroup, v. Family and

vi. Series (the most specific category). The soil of the Rajasthan state have been grouped

under five orders, namely, Aridosols, Alfisols, Entisols, Inceptisols and Vertisols. Soils

have further been subdivided at suborder and great group levels under these five orders.

The names of the soils orders occurring in the state and their subdivisions up to the great

group level are given in table below.

Table4.5: Classification of Soils found in Jaipur

S. No. Order Suborder Great group Occurrence

1. Aridisols Orthids a. Camborthids Parts of Jalore, Churu, Jodhpur, Pali, Barmer,

Sikar and Jhunjhunu districts.

b. Calciorthids

Parts of Jalore, Jodhpur, Pali, Barmer, Nagaur,

Sikar, Churu, Sriganganagar and Jhunjhunu

districts.

c. Salorthids

Found scattered in Ghaggar floodplain in

Sriganganagar; Near sambhar, Pachpadra,

Deedwana lakes, little Rann of Kutch area in

Jalore and in Barmer districts

d. Paleorthids Scattered and cover a small area in Jaisalmer,

Barmer and Nagaur districts.

2. Alfisols Ustalfs a. Haplustalfs Eastern and south-eastern part of Rajasthan in

Udaipur, Chittorgarh, Bhilwara, Ajmer and Jaipur

districts.

3. Entisols Psamments a. Torripsamments Cover up to 80% of the area at many places in

western Rajasthan. Also cover a part of Jaipur,

Alwar and Ajmer districts.

b.

Quartzipsamments

Small part of Jaisalmer and barmer districts.

Fluvents c. Torrifluvents Occur in Ghaggar floodplain area of

Sriganganagar district.

d. Ustifluvents Occur on the north-eastern and eastern portion of

Rajasthan covering parts of Alwar and almost

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IV

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 44

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

whole of Bharatpur districts.

4. Inceptisols Ochrepts a. Ustochrepts Occur along the foothill slopes and cover

extensive areas in Bhilwara, Udaipur, north-

eastern Sawaimadhopur and in parts of Sirohi,

Pali, Jaipur and Chittorgarh districts.

5. Vertisols Usterts a. Chrom usterts

Parts of Bundi, Kota & Jhalawar districts in south-

eastern part of Rajasthan and to a lesser extent in

Chittorgarh, Dungarpur, Banswara & Bharatpur

districts.

b. Pellusterts

Cover a large are of Bundi, Kota, Jhalawar,

Chittorgarh, Dungarpur, Banaswara and Bharatpur

districts.

4.7 CLIMATIC DATA FROM SECONDARY SOURCES

The Jaipur is located in the semi-Arid Zone of India. It has characterized by high

temperature, low rainfall and mild winter. The mean temperature of Jaipur is 360C

varying from 180C in winter (January) to 400C in summer (June). Thus the January and

June are the coldest and hottest months. The normal rainfall of Jaipur is 600 mm; nearly

90 percent of which takes place in the summer monsoon period i.e. from June to

September, the rest comes from the winter cyclones.

4.8 SOCIAL INFRASTRUCTURE AVAILABLE

The well-established social infrastructure like hospitals, temple, schools, roads, and

others similar are available/ existing within 15 km radius which is tabulated in point no

4.5 of PFR.

*********

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-V

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 45

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-V

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-V

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 46

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-V

PLANNING BRIEF

5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES,

TRANSPORTATION ETC) TOWN AND COUNTRY

PLANNING/DEVELOPMENT AUTHORITY CLASSIFICATION

The existing unit is operational since 1985 manufacture Angle, Flat, Bar Channel to the

tune of 75,000 TPA situated at A-241, A 242 (b) & (c) A-242 (A), Vishwakarma

Industrial Area, Road No.6 D, Jaipur, Rajasthan. The company enhance the production of

Angle, Flat, Bar Channel from 75,000 TPA to 1,50,000 TPA. Raw material

(Billets/Bloom) is being/ will be procured from SAIL. Coal used for Re-heating furnace

is being/will be met from Tuna /Kandla Port.

Transportation of Raw Material and finished product will be done through road only as it

is well-connected and in the centre of neighboring states. The land for the project is

owned by R.S. Infra-Transmission Limited.

5.2 POPULATION PROJECTION

As per the Census of India 2011, the proposed expansion project is situated in Jaipur

District, Rajasthan which has total population of 66,26,178 of which males are 52.34%

and females are 47.56%. The population growth has been of 26.90%. The sex ratio of the

district is 910 females over thousand males. The average literacy rate is 75.51% with

respect to total population, male literacy rate is 86.05% and female literacy rate is

64.02% with respect to male & female population. The 0-6 year’s population sex ratio is

861 females over thousand males. The employment is increasing in the tertiary sector and

primary sector are dominant. The proposed expansion project will provide employment to

120 persons of whom 40 persons are for construction Phase and 80 persons for operation

phase. It is likely that the population of the project area will not be significantly impact.

5.3 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT

ETC.)

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-V

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 47

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

The existing green belt has been done over an area of 2,522.1 sq.m (12%). Additional

2,732.3 sq.m (13%) of open area will be used for green belt development. Thus, the

total land area in the green belt will be 5,254.4 Sq. m. (25%) after proposed

expansion. Additional 10% green belt will be provided outside the plant area.

The main aim of the green belt development is to improve the ecosystem to a

maximum possible extent by designing the green cover with the same native species.

Greenbelt with in project site/ core zone will be developed for proposed expansion for

4-5 years while buffer zone plantation will be continued up to 5 years. Estimated

budget for same is as follows:-

Total Plot Area : 21,017.5 Sq. m

Greenbelt area : 5,254.4 Sq. m

Total trees required : 5,254.4 / 9 = 583.8 Nos. says 584 Nos.

Total trees provided : 600 Nos

• Trees for proposed expansion = 600 trees will be planted at the existing plant site and

both side of the Road connecting to the industry and divider of front road of Industry

• Further around 1500 trees will be planted in nearby areas like:-

• Nearby govt. schools

• Nearby Panchayat Bhwan/ Atal Sewa Kendra

A total of 1500 trees for the next 5 years will be planted for the green area

development in the close proximity of the proposed project.

Table 5.1: Green Belt Development Programme

S. No. Botanical Name Common Name No. of Tree

1 Azadirachta indica Neem 50

2 Dalbergia sissoo Shisham 80

3 Delonix regia Gulmohar 300

4 Albizia lebbeck Siris 170

Total 600

The detailed green belt programme along with budgetary allocation will be elaborated in

EIA/ EMP Report

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-V

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 48

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL &

SOCIAL)

On the basis of the preliminary site visit, the infrastructure demands in the villages are

assessed on the basis of need and priority. The health infrastructure, drinking facilities are

the primary requirements analyzed. The lack of modern and specialist facilities in

hospitals needs improvement. The assessment will be identified in the socio-economic

survey, after the grant of TOR and final assessment will be submitted in final

presentation of EC.

5.5 AMENITIES / FACILITIES

The project envisages the facilities provided to workers. Provision for the same has been

made as given below: -

Table 5.2: Facilities provided to workers

S. No. Activities Capital Cost

(Rs. In Lacs)

Recurring Cost

(Rs. In Lacs)

1. Health Facility 8.00 5.00

2. Drinking Water Facility 7.00 3.00

3. Sanitation Facilities 2.00 1.00

4. Education 6.00 3.00

Total 23.00 12.00

Presently the requirements are based on the preliminary visit which will be modified and

presented during final submissions. All the basic facilities like sanitation & drinking

water, labour quarters, dining areas are provided within premises. First aid box, free

medicines &professional medical assistance/service (on call basis) will be provided.

Adequate PPE’s will be provided to all workers. Land is in the possession of R.S. Infra-

Transmission Limited. This is the existing project with all the amenities and facilities for

the project process and works.

***********

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VI

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 49

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-VI

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VI

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 50

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-VI

PROPOSED INFRASTRUCTURE

S.

No.

Particulars Details

1. Industrial Area (processing

Area)

Total plot area of existing unit is 21,017.5 sq. m. The proposed

expansion is coming up within the same premises.

2. Residential Area

(Non Processing Area)

No

3. Green Belt Particulars Existing Proposed Total

Green Belt 2,522.1

(12%)

2,732.3

(13%)

5,254.4

(25%)

10% green belt will be provided Outside the plant area

4. Social Infrastructure Social infrastructure available within 10-15 km from project site.

5. Connectivity S. No. Highways Distance (Km) & Direction

(From Project Boundary)

1. NH 8 1.7, NW

2. SH 19 3.4, NNW

3. SH 2C 6.6, WSW

4. SH 55 9.5, ESE

5. Sikar Road 0.45,W

*Source: - All Distances are taken with respect to

Toposheet.

6. Drinking Water Management

(Source and Supply of water)

Adequate water facility is being/will be provided.

Source of water –Existing water demand is met from

RIICO/Tanker water supply. After Expansion water demand will

be met through Ground water supply. (Borewell-1 no proposed).

The application for the ground water abstraction will be

submitted to the Office of CGWA.

7. Sewerage System Industrial waste water–No waste water is being/will be

generated from industrial process. There is water required for

cooling and quenching process. Water from the cooling operation

is left in the cooling tank. After cooling, the water will be re-used

for the processes.

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VI

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 51

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

Domestic waste water - Approximately 3.0 KLD Domestic

wastewater is being generated from the existing unit, which is

disposed off into septic tank followed by soak pit. After

expansion to the tune of 9.0 KLD will be generated. Which will

be treated into STP (10 KLD). Treated water from STP will be

reused in greenbelt/plantation purposes. Sludge will be generated

and utilized as manure for greenbelt development/plantation

within the plant premises

8. Industrial Waste Management There is no industrial waste generated from the process.

Particulars Existing Proposed Total Mode of

Disposal

Municipal

Waste

45

Kg/day

80

Kg/day

125

Kg/day

Regional

Municipal

Corporation,

Jaipur

Coal ash 4.0

kg/day

1.0

kg/day

5.0

kg/day

Sent to brick

manufacturing

units

9. Solid Waste Management

10. Power Requirement & Supply

/ Source

Phase Demand Expected

Source

Existing Proposed Total

Operational

Phase

(kVA)

3000 1500 4500 JVVNL

D. G. Set

(kVA)

250 – 1

no

-- 250 – 1

no

From

manufacture

Fuel (For DG set/Re-Heating Furnace)

Fuel (HSD) 60 l/hr -- 60 l/hr Nearby

Petrol Pump

Coal for

Re-heating

Furnace

21

T/day

4

T/day

25

T/day

Tuna /Kandla Port

**********

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VII

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 52

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-VII

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VII

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 53

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-VII

REHABILITATION AND RESETTLEMENT (R & R) PLAN

7.1 POLICY TO BE ADOPTED (CENTRAL/ STATE) IN RESPECT OF THE

PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND

OUSTEES AND LANDLESS LABORERS (A BRIEF OUTLINE TO BE GIVEN).

There is no habitation in the existing project land and is an industrial land. The expansion

project is proposed to be expanded on the existing industry land premises. Thus, R & R

policy is not applicable to this project. There shall not be displacement of any population

in expansion project land. The expansion of project will slightly increase the commercial

and economical status locally.

*******************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VIII

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 54

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-VIII

Project : : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VIII

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 55

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-VIII

PROJECT SCHEDULE & COST ESTIMATES

8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY

DATE OF COMPLETION (TIME SCHEDULE FOR THE PROJECT

TO BE GIVEN)

Proposed expansion project will be completed within twelve months after getting

Environmental Clearance from MoEF&CC and consents from RSPCB, Jaipur.

Table 8.1: Expected Time Schedule for the Project

Activities Completed

activities

Months

1 2 3 4 5 6 7 8 9 10 11 12 13

Submission of

Terms of

Reference

Application

August’2021

Terms of

Reference

Baseline Study March to May’

2021

Preparation of

Draft EIA/EMP

report

Submission of

Draft EIA to

SPCB, Raj. for

Public Hearing

Public Hearing

Submission of

Final EIA/ EMP

report for EC

Environmental

Clearance

Project : : Expansion of Angle, Flat, Bar Channel, Jaipur Section-VIII

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 56

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN

TERMS OF ECONOMIC VIABITITY OF THE PROJECT.

The total cost of the project after expansion will be Rs.72.0 Crores. (Existing–Rs. 59.0

Crore, Proposed- Rs. 13 Crore).

Table 8.2: Expenditure Proposed for Environmental Protection Activities

S.

No.

Description of Item Existing (Rs. In Lacs) Proposed (Rs. In Lacs)

Capital Cost

Recurring

Cost

Capital Cost Recurring

Cost

1 Air Pollution Control

Equipment

28.00 1.5 35.0 2.0

2. Rain water

Harvesting Structure

3.0 0.50 3.0 0.5

2 Water Pollution

Control

0.50 -- 15.0 0.5

3 Environmental

Monitoring and

Management

-- 2.0 -- 6.5

4 Green Belt

Development

1.5 0.80 3.0 1.25

5 Occupational Health

& Safety

2.5 0.50 3.0 0.50

Total 35.5 53 59.5 11.25

******************

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IX

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 57

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-IX

Project : Expansion of Angle, Flat, Bar Channel, Jaipur Section-IX

Promoter : R.S. Infra-Transmission Limited

Gaurang Environmental Solutions Pvt. Ltd. Page 58

Report Ref: GESPL_397/2021 /ToR/87 Rev. No. 00

SECTION-IX

ANALYSIS OF PROPOSAL

9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS

ON THEBENEFIT TO THE LOCAL PEOPLE INCLUDING TRIBAL

POPULATION, IFANY, IN THE AREA

There will be social benefits due to the proposed expansion project. Due to expansion

project, it is expected that employment will increase for people who reside nearby project

area. Approximately 280 persons will get employment after expansion (30 people during

construction phase and 250 people during operation phase). Ancillary units will also be

benefitted in the project area. The local economy will be uplifted in the project area.

Locals will get employment their expenditure and saving power will increase which will

result in better living standards. Due to green belt development, aesthetic value of local

environment will improve. Detailed Environmental management plan will be submitted

during EIA stage.

***********

GAURANG ENVIRONMENTAL SOLUTIONS PVT.LTD.

SIMPLIFYING SUSTAINABILITY

Accredited EIA Consultant Organization by NABET, QCI, New Delhi at S. No. 108 in list of

Accredited EIA Consultant Organizations (as on June’2021)

#102, SNG Shree Ratna Apartment, Peetal Factory, Banipark, Jhotwara Road, Jaipur-302016

E-mail: [email protected]