DETAILED FEASIBILITY STUDY REPORT
FOR
POLY PROPYLENE UNIT
OF
NUMALIGARH REFINERYEXPANSION PROJECT
AT
NUMALIGARH REFINERY LTD, ASSAM
REPORT NO. B394-RP-79-41-0001 VOLUME 1 OF 1
OCTOBER 2021
This report is prepared for M/s NRL and it is for use by M/s
NRL or their assigned representatives/organizations only.
The matter contained in the report is confidential.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 1
Copy right for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
COPYRIGHT
This document is copyright protected by EIL and is produced for the client M/s
NRL. Neither of this document or any extract from it may be produced, stored
or transmitted in any form for any purpose by any party without prior written
permission from EIL.
Request for additional copies or permission to reproduce any part of document
for any commercial purpose should be addressed as shown below:
Head of the Department (Process - 2)
5th Floor, Tower II
R&D Complex, Engineers India Limited
Sector-16, Gurgaon- 122001
India
Telephone: 0124-380-2901
EIL reserves the right to initiate appropriate legal action against any
unauthorized use of its Intellectual Property by any entity.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyright EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 1
Table of Content for DFR Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP) NRL
TABLE OF CONTENTS
SECTION CONTENTS
1. EXECUTIVE SUMMARY
2. INTRODUCTION
3. SCOPE
4. DESIGN BASIS
5. MARKET STUDY
6. PROJECT LOCATION
7.
7.1
7.2
7.3
7.4
7.5
7.6
7.7
PROJECT DESCRIPTION
PROJECT CONFIGURATION
PROCESS DESCRIPTION
MATERIAL BALANCE
UTILITIES DESCRIPTION
OFFSITES DESCRIPTION
PRODUCT EVACUATION SYSTEM
LOGISTICS
8. ENVIRONMENTAL CONSIDERATIONS
9.
10.
11.
12.
13.
PROJECT IMPLEMENTATION AND
SCHEDULE
PROJECT COST ESTIMATE
FINANCIAL ANALYSIS
HEALTH SAFETY AND ENVIRONMENT
RECOMMENDATIONS
ANNEXURE
1 OVERALL PLOT PLAN
2 SCHEMATIC FLOW DIAGRAM
3
EQUIPMENT LIST
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
SECTION 1.0
EXECUTIVE SUMMARY
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
1.0 EXECUTIVE SUMMARY
1.1 Introduction
Numaligarh Refinery Limited (NRL) is planning to set up a Polypropylene Unit along with
its associated facilities at Numaligarh beside the existing refinery in the state of Assam to
meet the increasing demand of polypropylene in the North eastern region.
1.2 Background
Numaligarh Refinery Limited (NRL), a subsidiary of M/s OIL India Limited is a public sector
undertaking under the Ministry of Petroleum and Natural Gas. The refinery located at
Golaghat District in Assam was commissioned in the year 2000 with a crude processing
capacity of 3 million tonnes per annum (MMTPA) to process indigenous crude of Assam.
The refinery primarily produces MS & HSD conforming to BS-VI specification.
NRL is installing a parallel new refinery of crude processing capacity of 6 MMTPA to
expand its capacity from present 3 MMTPA to 9 MMTPA. The project is integrated with a
new crude oil pipeline from Paradip (Odisha) to Numaligarh (Assam) and a product pipeline
from Numaligarh to Siliguri where NRL has its own Marketing Terminal for distribution of
product. The crude oil considered for the design of new refinery train is Arabmix crude. MS
(Gasoline) & HSD produced from the new train shall meet the BS-VI specification. The
project has been named as Numaligarh Refinery Expansion Project (NREP).
Under this NREP project a high severity PFCCU unit with a capacity of 1.955 MMTPA is
being implemented. The LPG that will be generated in the high severity mode will contain a
significant potential of propylene which can be recovered for value addition. Potential exists
to explore the possibilities of setting up of a Poly-Propylene Unit to produce high value
polymers by considering feed stocks available from the refinery PFCCU.
Considering the above and in view of expected growth in demand for petrochemicals
products in India and to remain competitive in the market with products self sufficiency,
NRL planned to set up a PP Unit along with its associated facilities at Numaligarh beside
the NREP refinery.
NRL has entrusted EIL as a consultant to carry out the job of preparation of Detail
Feasibility Study for PP with cost estimate accuracy of ±20%.
For Estimating the capital investment within the accuracy of ±20%, preparation of DFR is
performed based on licensor input, in-house process data and year of expertise with in EIL.
B
B
B
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
1.3 Project Objectives
The broad objectives of the Poly propylene unit of Numaligarh Refinery Expansion Project
are as follows:
PP unit Capacity: 360KTPA of homo polymer polypropylene production
Maximization of on-spec poly propylene product and minimize the transition time
in shifting between different grades of production.
Minimize hydrogen consumption
Minimise Capex through Integration of Streams
Maximise Return on Investment
1.4 Scope of Work
The scope of DFR is to estimate capital cost of the project with accuracy of ±20%, financial
analysis and schedule for overall project implementation to achieve the processing
objective. In addition environmental consideration, overall plot plan and implementation
philosophy for the project are also studied and included in the report.
Yield and utility estimate for the PP Unit is considered based on licensor input
supplemented with in-house data.
1.5 PP Unit Configuration with NREP
The Polymer Grade Propylene produced in the PRU section of the PFCC Unit of NREP is
further processed in the downstream unit i.e. PP unit to produce Homo-polymer grade
Polypropylene product.
Schematic diagram of integrated Polypropylene project with ongoing NREP is provided in
figure 1.1 below
Fig 1.1: Refinery Schematic Diagram
1.6 Basic Design Parameter
Basic Design parameters are summarized below:
PF
CC
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
1.6.1. Feed Definition
Polymer Grade Propylene
Polymer grade propylene from PFCC unit has 99.6 wt% (min.) propylene and 0.4 wt%
(max) of propane.
Hydrogen Gas
Hydrogen Gas is available from existing hydrogen header of NREP.
1.6.2. Product Specification
The PP unit will be designed to produce four different grades of homo-polymer PP with the
MFI specification as per the table below:
Table 1.1: Different grades of Homopolymer produced in PP Unit
Sl.No. Description Specification
MFI (230 degC @ 2.16 kg), gm/10 min
1 Raffia Grade 3.4
2 Non–Woven Spun Bond Grade 38
3 Non-Woven Melt Blown Grade 100
4 Injection Moulding Homo-polymer
Grade
25
1.6.3. PP Unit Capacity
Polypropylene Unit design capacity is 360 KTPA of homo-polymer PP with an annual
product slate as per the table below:
Table 1.2: Annual slate of 4 different homo-polymers from PP Unit
Sl.No. Homo-polymer PP Grade description Annual Product Slate
(MT/Annum)
1 Raffia Grade 190000
2 Non–Woven Spun Bond Grade 90000
3 Non-Woven Melt Blown Grade 25000
4 Injection Moulding Homo-polymer Grade 55000
1.6.4. On-stream Hours
The stream hour considered for the study is 8000 hours per annum
1.6.5. Feed and Product prices
Feed, Product and utility prices which will be considered for the DFR are tabulated below:
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Table 1.3: Feed, Product & Utility Prices
Description Price, INR/Ton
Feed (5 years average price from April 2016 to March 2021)
Arab Light 31872
Arab Heavy 29902
Natural Gas 36487
VR of Existing Refinery 29735
Coker Distillate 32303
naphtha 35575
Product (5 years average price from April 2016 to March 2021)
LPG 38662
Poly Propylene 87041.0
BS VI Gasoline 43188
BS VI HSD 39496
RUF Bottoms to Ex Coker 24815
Sulphur 4744
Utility
Power Rs 6.5/ KWH
Treated Raw Water Rs 17.0/ m3
1.6.6. Case definition
Base Case: Base case corresponds to 6 MMTPA Refinery with PFCCU operating in low
severity mode and propylene produced from PRU is absorbed in the LPG product stream
and no propylene sale is envisaged. No Polypropylene unit.
Max Propylene + PP Case: Expansion case corresponds to 6 MMTPA Refinery with
PFCCU operating in propylene maximization mode or high severity mode and with Poly
propylene (PP) unit in operation. PP Unit taking feed propylene from upstream PFCC unit
and producing poly propylene which will be sold as final product
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 6 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
1.7 Detail Feasibility Report- Key findings
1.7.1 Material Balance
Material balance for the base case and the expansion case which are considered for the
IRR estimation is provided in the table below:
Table 1.4: Material Balance of NREP integrated with PP
Description Base case, 6 MMTPA
refinery, KTPA
Max Propylene + PP case ,
6 MMTPA refinery + PP, KTPA
Feed
Arab Light 1800 1800
Arab Heavy 4200 4200
Natural Gas 468 473
VR of Existing Refinery 310 310
Coker Distillate 110 110
Naphtha 45.0 45.0
Total Feed 6933 6938
Product
LPG 674.0 496.0
Poly Propylene 0.0 346.0
BS VI Gasoline 1592.0 1518.0
BS VI HSD 3256.0 3160.0
RUF Bottoms to Ex Coker 555.0 555.0
Sulphur 145.0 145.0
Fuel and Loss 711 718
Total Product 6933 6938
1.7.2 Utility System
The utility requirements for the PP unit and its associated facilities have been worked out
based on licensor data and in-house estimate. Following utilities shall be required for the
PP Project -
Steam, DM, IA, PA, Nitrogen, Power, Raw water and cooling water
Following utilities shall be generated – Condensate, flare and effluent
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 7 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
The utility summary for the PP project was shared with NRL and after detailed deliberation
it was concluded that all the above required utilities except for cooling water and power can
be met from the NREP utility system. Also all the utility streams generated can be
accommodated in the NREP utility system
Power for the PP project will be imported from grid, adequacy of the existing switch yard for accommodating this additional requirement have been confirmed by NRL. To cater to the cooling water demand new cooling water system is proposed. Following new utility system is proposed in the PP complex
Table 1.5: Utility System Details
Description Specifications Remarks
Cooling Water System
Cooling Tower Cells Capacity : 4000 m3/hr each
Number : 2w+ 1 s
New cooling tower along with
new re-circulating cooling water
pump to meet the cooling water
demand of PP unit
Re-circulating Cooling
Water Pumps
Capacity : 4000 m3/hr each
Number : 2 w+1 s
Rest of the utilities as tabulated below shall be catered from the NREP utility system
Table 1.6: Utility System Details
Description Specifications Remarks
Treated Raw Water System
Treated Raw Water Normal: 210 m3/hr
Peak :250 m3 /Hr
Demand to be met from the
NREP RWTP.
Demineralized Water System
DM Water Normal: 2 m3/hr
Peak : 95 m3/hr
Demand to be met from the
NREP RODM
Nitrogen System
Nitrogen Normal : 990 Nm3/hr
Peak :3740 Nm3/hr
Demand to be met from the
NREP Nitrogen Plant
Compressed Air System
Plant Air Normal : 340 Nm3/hr Peak : 1050Nm3/hr
Demand to be met from the NREP Compressed Air system
Instrument Air Normal: 1300 Nm3/hr
Steam and Power System
Power Normal: 26 MW Demand to be met from Grid
LP Steam Normal: 12.5 TPH Peak:16.5 TPH
Demand to be met from NREP utility Boiler
MP steam Normal: Nil Peak: 9 TPH
HP steam Normal : 1.05 TPH Peak: 1.7 TPH
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 8 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Description Specifications Remarks
MP BFW Normal: 0.5 TPH Peak: 1 TPH
Flare System
Flare Peak: 130TPH To be connected to NREP flare header
Effluent Treatment
Effluent 50 m3/hr To be routed to NREP ETP
Condensate
Suspect condensate Normal: 12.5 TPH Design: 13.9 TPH
To be routed to NREP CPU
Pure condensate Normal: 1.05 TPH Peak : 4 TPH
To be routed to NREP CPP
1.7.3 Offsite Storage Facilities
The offsite facilities are divided into two sections:
Feed/ Intermediate storage and transfer
Finished Product storage and transfer
1.7.3.1 Feed/ Intermediate Storage and Transfer
PPU receives polymer grade propylene as feed from the upstream PFCC unit. Normally,
PPU will receive 100 % of feed directly from the PFCC unit. However, in case of
emergency shutdown of the PP Unit, provision has been kept to store polymer grade
propylene in the offsite storage. Three (3) no. of mounded bullets (MB) each with a
pumpable capacity of 1620 MT have been considered for storing propylene. Three (3) days
of storage requirement have been considered while working out the bullet capacity.
List of Mounded Bullets for Polymer Grade Propylene storage is provided in Table 1.7 below:
Table 1.7 Polymer Grade Propylene Mounded Bullet Summary
Mounded Bullet Service
Bullet Pumpable Capacity
No of Bullet
Diameter Height Remarks
Propylene 1620 MT 3
8 m 80 m 2 working + 1 spare
1.7.3.2 Finished Product Storage & Transfer
The objective of providing product storage is to ensure receipt of unit rundown, testing of
product, and evacuation of on-spec product to consumer end. Additionally this will also
help to ensure availability of product in case of emergency shutdown of unit or continued
running of unit in the event of interruption in product transfer or dispatch for a period. The
PP is produced in pellet form and is stored in warehouse before dispatch. The warehouse
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 9 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
will be sized corresponding to twenty one (21) days of storage requirement corresponding
to 100% throughput of the unit.
1.7.4 Land Requirement
The proposed PP unit will be set up at a Green field land located at North side of the
Numaligarh Refinery. The proposed site is well connected by road network and rail
network. The proposed PP plant will be integrated with NREP complex
Total plot area required for the PP Unit and its associated facility is 348093 SQM. Of this,
Plant area is 232821 SQM and Green belt area is 115272 SQM (>33 % of total area).
The PP Product will be evacuated via truck from the north side of the plot through a 3.5 km
road which connects to the nearest national highway.
1.8 Economic Evaluation for the PP Project
The financial results for the PP Project (based on 5 years average price) is worked out and
tabulated below:
Table 1.8 Financial evaluation
Note-1: Differential Opex = Expansion Case Opex- Base case Opex
Note-2: Differential Sale Revenue = Expansion Case Revenue- Base case Revenue
Sensitivity Analysis
Sensitivity analysis has been carried out to check the impact on Internal Rate of Return
(IRR) considering changes in capex, opex and GRM. IRR for all these cases habe been
tabulated below:
Description Cost
Rs. Crore
Capital Cost with Financing
Charges 4515.00
Differential Variable Operating
Cost 320.98
Fixed Operating Cost 197.87
Total Operating Cost 518.85
Differential Sales Revenue 1624.68
IRR Results (Revamp Case) IRR Before Tax IRR After Tax
IRR on Total Capital 20.57% 18.24%
IRR on Equity 25.56% 21.52%
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 10 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Table 1.9: Sensitivity analysis for 5 years average price of feed and product:
1.9 PROJECT SCHEDULE AND IMPLEMENTATION PLAN
The implementation schedule for the subject project has been established based on
following considerations:
1. Zero Date of the Project is considered as receipt of Licensor BEDP
2. Mechanical completion of the PP complex is considered as 36 months from the zero
date. Pre Commissioning & Commissioning activities will be done progressively as
indicated in the schedule.
3. EPCM Mode of execution is considered
4. It is considered that construction water and power will be considered from NREP
source
5. Environmental Clearance (EC) is considered under NRL scope and shall be
available on start of site enabling/ grading action.
Description IRR Before Tax IRR After Tax
On Total Capital
Base Case 20.57% 18.24%
Capex +10% 18.80% 16.73%
Opex +10% 19.98% 17.75%
Sales +10% 23.34% 20.61%
On Equity
Base Case 25.56% 21.52%
Capex +10% 22.21% 18.66%
Opex +10% 24.44% 20.58%
Sales +10% 31.08% 26.19%
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 11 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
1.10 HEALTH, SAFETY AND ENVIRONMENT
1.10.1 Health and Safety
In order to ensure identification of any hazards associated with the project, which could
adversely affect the health and safety of personnel both within and outside the complex,
and the environment, a sound Health, Safety and Environment (HSE) policy is proposed to
be adopted during the course of project execution with primary objectives as under .
a) Provide clearly defined safety system goals for the design aspects of the project.
b) Ensure a safe working environment for all plant personnel.
c) Through intrinsic safety in design, eliminate the potential for occurrence of
hazardous scenarios that can result in injuries, environmental damage, business
interruptions or loss of assets.
d) Minimize the risk and consequences of an accident which cannot be eliminated
by intrinsic safety in design.
e) Maintain satisfactory means of escape and evacuation from any conceivable
incident.
f) Minimize the potential for pollution of the environment from accidental spills,
venting or flaring of hazardous materials.
In order to ensure the above, it is proposed to carry out the following HSE related studies
during the engineering stage:
- Hazard identification (HAZID) study
- Hazard and Operability Study (HAZOP)
- Quantitative Risk Assessment (QRA) Study
- Hazardous Area Classification
Other health hazards that are proposed to be studied are as follows:
a) Lighting
b) Noise
c) Thermal Environment
1.10.2 Environment
Wastes are streams that are not produced for sale or internal consumption. Some of
these wastes may be toxic, poisonous, flammable and harmful to the environment.
Hence, it is of utmost importance that the wastes generated are disposed off safely.
When waste production cannot be avoided, the following design principles shall be
adopted to achieve environmental compliance:
a) Minimise the waste generation
b) Safe disposal facilities within development boundary
c) Safe disposal facilities outside the unit.
Wastes generated are of three types:
a) Solid
b) Liquid
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 12 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
i. Aqueous
ii. Non-aqueous
c) Gaseous
i. Point source gaseous emissions
ii. Fugitive emissions
Adequate care will be taken in process design to minimize the quantity of waste
produced. In addition, solid, liquid and gaseous wastes generated from various
processes in the refinery will be handled in a manner that minimizes their impact on the
environment.
1.11 SOCIO-ECONOMIC BENEFITS
The proposed project would generate some direct and indirect employment
opportunities during construction and operation phases, which will benefit the local
people. A significant nos. of manpower is required during construction and operation.
Local skilled and unskilled labour will be provided employment during construction and
operation phase. Tentative employment of skilled/unskilled workforce during
construction phase will be around 1750. Improvement in the overall socio-economic
status of the vicinity of project area, in the thematic areas of health, education, livelihood
and infrastructure is expected.
1.12 RECOMMENDATION
Based on the analysis detailed out in the previous sections, the following is concluded:
The project having capital cost of Rs 4515 Crores (with accuracy of ±20% and valid as of
Oct 2021) can achieve viability with a return of 18.24% post tax based on the product
prices.
Setting of PP Project, for which NRL has land in possession as well as its good
connectivity to the existing refinery for feed and utilities, proximity to highways and
ease of getting environmental clearance, will meet the petrochemical demand of
north eastern region which is expected to grow in future.
Also Polypropylene complex will accelerate development of downstream petrochemicals
industry for polymer processing like packaging, fibre and filament, automotive, health care
and personal care.
The development of clusters of small and medium industrial units associated with
petrochemical industry will not only improve the general infrastructure by improvement of
roads, education and health facilities but also generate tremendous employment
opportunities. This project will thereby improve the economic status of the people in the
area surrounding the Refinery/ petrochemical hub.
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 13 of 13
Executive Summary for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
The Economic analysis portrays a robust and attractive rate of return for refinery
configuration with PP, this is primarily due to the high value polymer product. Hence it is
recommended that since the PP project results in a significant return on investment, same
can be taken forward for implementation.
Considering the high IRR, the pre-project activities may be taken up on immediate basis
after having internal approval within NRL. This will give an opportunity to NRL to almost
match PP Project with the implementation of existing NREP project and realise the full
potential of PFCCU from day one, ensuring high profitability.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 2
Introduction for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 2.0
INTRODUCTION
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 2
Introduction for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
2.0 INTRODUCTION
Numaligarh Refinery Limited (NRL), a subsidiary of M/s OIL India Limited is a public
sector undertaking under the Ministry of Petroleum and Natural Gas. The refinery located
at Golaghat District in Assam was commissioned in the year 2000 with a crude
processing capacity of 3 million tonnes per annum (MMTPA) to process indigenous crude
of Assam. The refinery primarily produces MS & HSD conforming to BS-VI specification.
Further Numaligarh Refinery Limited (NRL) is implementing a parallel new refinery of
crude processing capacity of 6 MMTPA to expand its capacity from present 3 MMTPA to
9 MMTPA.
The project is integrated with a new crude oil pipeline from paradip (odisha) to
Numaligarh (Assam) and a product pipeline from Numaligarh to siliguri, where NRL has
its own marketing terminal for distribution of product. MS(Gasoline) & HSD produced from
the new train shall meet the BS-VI specification. The project has been named as
Numaligarh Refinery Expansion Project (NREP).
Under this NREP project a high severity PFCCU unit with a capacity of 1.955 MMTPA is
being implemented. The LPG that will be generated in the high severity mode will contain
a significant potential of propylene which can be recovered for value addition. Potential
exists to explore the possibilities of setting up of a Poly propylene Unit to produce high
value polymers by considering feed stocks available from the refinery PFCCU.
Considering the above and in view of expected growth in demand for petrochemical
products in India and to remain competitive in the market with product self-sufficiency,
NRL intends to explore the feasibility of putting up a PP unit in the refinery complex from
Polymer grade propylene feed from PFCC unit along with associated utilities and offsite
facilities.
The Polypropylene Unit is to be designed as a single train with a capacity of 360,000 TPA
of Homo-polymer grades of Polypropylene (PP) product with a target annualized product
split discussed elsewhere in the report. The capacity stated is inclusive of off spec (low
value) products produced during transition from one grade to another.
NRL engaged EIL as a consultant for selection of process licensor for new poly-
Propylene Unit (PPU), conduct a detailed feasibility study with cost estimate accuracy of
±20% and review of Licensor’s Basic Engineering & Design Package (BEDP) of PPU.
B
B
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 3
Scope for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 3.0
SCOPE
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 2 of 3
Scope for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
3.0 SCOPE
For the present Poly Propylene Unit of Numaligarh Refinery Expansion Project (NREP),
following activities shall be performed by EIL in line with agreed Scope of Work.
3.1 Licensor Selection
EIL shall select Process Licensor for the Polypropylene unit (PPU).
3.2 Detailed Feasibility Report (DFR)
Apart from the licensor selection activity, EIL shall also prepare the Detailed Feasibility
Report for this project to estimate capital cost of project with accuracy of ± 20%, financial
analysis and tentative schedule for overall project implementation to achieve the objective
of setting up a new Poly Propylene Unit of 360KTPA along with associated utilities offsite
facilities. This part of EIL’s scope of services shall include the following activities:
a) Design basis finalization for DFR
b) Preparation of project description, process description, and process flow schematic of
the new process unit.
c) Establishing utility requirements for the proposed project based on licensor’s utility
summary
d) Preparation of cost estimate with ±20 % accuracy.
e) Financial analysis (IRR Computation)
f) Preparation of project schedule
g) Preparation of suggested plot plan
h) Assessment of tankages/ ware house requirement for immediate and final products
i.e. propylene, poly-propylene etc
i) Assessment of OSBL facilities including dispatch facilities for PP products
j) The DFR report will consists of the following:
1. Executive summary
2. Introduction
3. Scope of work.
4. Design basis
5. Market Study
6. Project location
7. Project Description
8. Process Description of new process Unit
9. Overall Material balance
10. Utilities and Off-sites facilities assessment.
11. Capital Cost Estimate with ±20% accuracy.
12. Financial and sensitivity analysis
13. Detailed Project Implementation Plan and Schedule
14. Environmental considerations
15. Conclusions and Recommendations
16. Overall Plot Plan
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 3 of 3
Scope for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
3.3 Review of Licensor’s BEDP for (PPU)
EIL shall associate with NRL/Licensor during preparation of Process Package by Licensor.
EIL’s broad scope of services for review of licensor’s BEDP shall be as under:
a) Preparation of Design Basis (Part A) for PP Unit.
b) Finalization of design basis for PPU Part A and Part B with Licensor, Part B as
obtained from NRL.
c) Review of PFD & Material Balance
d) Participation in PFD review meeting.
e) Review of Equipment layout
f) Participation in P&ID review meeting.
g) Review of P&ID, equipment datasheets, instrument datasheet, control scheme,
cause & effect diagram, utility, chemical and flare load summary
h) Resolution of licensor queries during licensor package preparation
i) Compilation of process package.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
SECTION 4.0
DESIGN BASIS
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
4.0 DESIGN BASIS
Design basis, considered for preparation of DFR for setting up a new Poly Propylene unit and
its required associated facilities at Numaligarh Refinery for NRL , is detailed below.
4.1 Basic Design Parameter
Study to be done by EIL DFR FR Other
Project Execution Methodology LSTK CONV
√ HYBRID
Project Duration Required In
Months
48 Months from the selection of EPCM consultant
and 36 months from the receipt of Basic Engineering
Design Package. BEDP is considered to be received
within 12 months of selection of EPCM consultant.
Of the 12 months, 6 months have been considered
for Licensor selection of PP unit followed by 6
months for receipt of BEDP form Licensor.
4.2 Other Studies
1
Market survey/study report (Demand and
supply analysis)
Excluded from present job scope.
2 Rapid Environmental impact study Excluded from present job scope.
3 Site evaluation/selection Greenfield site located adjacent to the
existing Refinery.
Site evaluation/selection is excluded from
present job scope.
4 Evaluation/Selection of licensors Included in present job scope.
5 Rapid Risk analysis Excluded from present job scope.
6 Soil investigation Excluded from present job scope.
7 Hydrological survey Excluded from present job scope.
Contour survey Excluded from present job scope.
Route survey (for transport of ODC materials
from various ports / industrial areas of the
country.)
Excluded from present job scope.
Marine Survey-effluent dispersion study Excluded from present job scope.
8 Health assessment /inspection reports
(For Revamp)
Not applicable
9 Downtime assessment report (For Revamp) Not applicable
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
4.3 Plant Location
Village Nearest City (Kms) State Nearest Railway Station (kms)
Ponkagrant
Village
Golaghat (25 Kms) Assam Furkating Jn, 35 km from NRL
4.4 Land availability details
Plot Area
1. Soil investigation, site details
like Extent/cost of land filling/
piling data, if available may be
furnished
Greenfield land adjacent to existing Refinery Complex. Soil
investigation is excluded from present Job scope. Land
cost shall be excluded from DFR cost. Only site
development cost to be included.
2. Land Availability Greenfield land adjacent to the existing refinery complex.
Land availability for the PP and its associated facilities is
confirmed by NRL.
3. Rerouting Requirement
Rerouting of any existing
facilities like road, power lines,
drains etc. required/ not required
(if required, details of the same
may be furnished)
Not applicable.
Greenfield land adjacent to existing Refinery Complex
4. Grid Power Availability The Captive Power Plant of the Refinery will be saturated
post refinery expansion. Hence, incremental power
requirement for the PP unit and its associated facilities
shall be sourced from grid.
Nearest Dist Level
4.5 Raw Material
Name/Composition Polymer Grade Propylene: 99.6 wt% min.
Detailed feed composition is provided in Annexure 1.
Source Petro FCC Unit of NREP
Capacity to be considered 360 KTPA
On stream Hours 8000 Hours/annum
Crude Assay Not applicable
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
4.6 Products
Name Homopolymer Poly Propylene product with an annual production
split as follows:
1. Raffia grade : 190 KTPA
2. Non-woven spun bond grade: 90 KTPA
3. Non-woven melt blown grade: 25 KTPA
4. Injection moulding-Homopolymer grade: 55 KTPA
Feed, Product and Utility price is provided in Annexure 2.
Annual Capacity
Market Place (preferred)
4.7 Plant Units
Process
Units
Capacity Utilities to be
generated
Capacity Catalyst / chemicals
Name Quantity Unit Rate
Poly
Propylene
Unit
360
KTPA
Cooling water
(Note 1)
8000 m3/hr
(Note 1): It is envisaged that some utilities like steam, fuel, DM water, BFW, condensate,
Treated Raw water, Instrument Air, Plant Air, Nitrogen required for the PP complex shall be
completely met from the refinery existing facilities, for others like cooling water new utility
facilities shall be required in the PP complex to cater to the incremental requirement.
Additional power shall be imported from Grid.
4.8 Offsite, Raw Material/ Product & Other Storage
Offsite, raw material/ product and other storages (Note 2)
Raw Material Intermediate Products Finished Products
Name
State
Liquid/
solid
No of
days of
storage
Name
State
Liquid/
solid
No of days
of storage:
Name
State
Liquid/
solid:
No of days
of storage:
Polymer
Grade
Propylene
(Note 1)
Liquid 3 days
PP Solid
21 days
Note 1: Details of mounded bullets considered for propylene in the NRL PP project is provided in
Annexure 3.
Note 2: Storage facility for intermediate products (i.e. Propylene bullets) and storage
requirement for the final product(i.e. PP warehouse) shall be located in the new land.
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
4.9 Product Evacuation By Railway / Truck / Pipeline
PP dispatch facilities shall be considered as per NRL requirement.
Product
Name
% of product to
be moved by rail
% of product to
be moved by
road
% of product to
be evacuated
through Pipeline
% of product to be
evacuated through Coastal
movement sea tankers.
PP (89%) (11%)
NA NA
Length of rail to be laid/ distance between plant and railway siding NIL
Details of any major crossing (river/road/rail) coming on the way to
Railway station to be considered as part of Project cost.
NIL
4.10 Utilities
New utility systems are envisaged for the Refinery complex. Details of new systems are
discussed below.
4.10.1. Raw Water For Plant Operation
Source As per existing refinery
Distance from river/sea As per existing refinery
Raw water Analysis (if available) As per existing refinery
4.10.2. Electric Power For Plant Operation
Source Grid import
Volts 6.6 KV
Frequency 50 Hz
Rate Rs./kWH 6.5
Distance ____________ km from
Back up source of Power Not applicable
Level of Generation Not applicable
Contract Demand Charges Not applicable
Energy charges Not applicable
Minimum energy charges (as % of
Contract Demand)
Not applicable
In case this is not available, whether a
system is to be designed/included in
execution
Not applicable
4.10.3. Construction Power
Available Yes
Volts 415 V
KM away Within existing refinery.
Rate (Rs./KWH)
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 6 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Contract Demand Charges Power available within the existing refinery
shall be used as construction power Energy charges
Minimum energy charges (as % of
Contract Demand)
4.10.4. Construction Water
Available Yes.
KM away Within existing refinery.
4.10.5. Cooling water New facilities will be considered for the PP
complex within the Refinery area.
4.10.6. Nitrogen system To be met from existing refinery
4.10.7. Air system To be met from existing refinery
4.10.8. Steam system To be met from existing refinery
4.10.9. DM Water To be met from existing refinery
4.10.10. Condensate system To be met from existing refinery
4.10.11. Flare To be accommodated in existing refinery
4.10.12. ETP To be accommodated in existing refinery
4.10.13. Sour Water Stripping Units Not applicable
4.10.14. Amine Recovery Unit (ARU) Not applicable
4.11 Environmental Requirement
4.11.1 Effluent Specifications
Liquid Effluent MINAS Standards.
Gaseous Effluent MOE&F guidelines / APCB
Standards.
Solid Waste As per CPCB/APCB requirements
Stack height (Limitation to be specified) As per CPCB / APCB
requirements
– No nearby Airbase / airports.
Location of effluent discharge
& its distance from B/L of plant
As per existing refinery
Note: Details to be furnished below in case State Pollution Board specifications exist
4.11.2 Green Belt Requirement*
As advised by State Government during site
selection visit.
Proposed site would be in the newly
acquired land by NRL adjacent to
existing refinery site.
Green belt requirement shall be as
per MOE&F norms.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 7 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
* In absence of this data 100 M all around shall
be included.
4.11.3 REIA (In case of DFR) / Rapid Risk Analysis
(In case of FR)
Excluded in the present scope of
work
4.12 Building Required (Plant & Non Plant)
Name Type Area in M2
Administrative Building Existing facilities. To meet
Requirements of the PP
unit and its associated
facilities.
Warehouse(Chemical,
Spares, Product, Cement)
New warehouse for PP product shall
be considered.
Workshop Existing facilities.
Canteen New facilities.
Lab New facilities shall be considered.
Control room with rooms for
operating supervisors and
conference rooms
New facilities.
Training Centre Existing facilities.
Substations New facilities for PP and its
associated facilities shall be
considered.
Fire station New facilities shall be considered.
Operator Cabins New facilities.
Service Buildings New facilities.
Security Cabins New facilities.
Any other building as required SRR for PP and its associated
facilities.
Township – Existing facility. No augmentation of township due to the PP project is
considered.
% of staff to be provided accommodation
Health care facility Yes/No Existing facilities
School up to primary/secondary education Yes/No Existing facilities
Socio cultural facility Yes/No Existing facilities
Open space Yes/No NA
Commercial facility Yes/No Existing facilities
Provision for power, water and sewage
Disposal
Yes/No Existing facilities
Swimming pool Yes/No Existing facilities
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 8 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
4.13 Construction Aids:
Heavy crane to be purchased by owner No
(If yes, please specify capacity of range proposed and hiring
charges)
Capacity range ----N/A-------
Hiring charges -----N/A------
Whether Hydra, and medium size crane By erection contractor
(up to 35 Tons can be brought by Erection Contractor)
4.14 Project Cost Related Parameters
Expenditure Heads To be Included in report
Applicability of taxes & duties As per standard practice
Requirement of Piling As per standard practice
Land Cost Excluded.
Land Development Charges As per standard practice
Complex Boundary wall Excluded
Construction Period Expenditure As per standard practice
Dismantling cost of existing facilities
Not applicable. New greenfield
Plot
4.15 Owner Expenses During Project Implementation ..As considered in NREP FR (EIL Job No:B265)
Expenditure Heads To be Included in report
Expenses Towards Public Issue Yes
Salaries Yes
Perks And Facilities To Be Provided By Owner To People
Employed On This Job
Yes
Communication Yes
Travel Yes
Training Yes
Legal Expenses Yes
EPCM Fees Yes
Contingency Yes
Any Other
Total Amount For All The Above Heads Yes
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 9 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
4.16 Additional Information, For Margin Money Calculation
Item Days
Salaries and wages and operating man-hours/manpower
envisaged
Refer Annexure 5
Repairs and maintenance spare inventory As per normal operating
requirement
Goods in process 4 days of sales
Finished goods 20 days of sales
Bills Receivable (Outstanding) 21 days of sales
Cash in hand 15 days of salary
Trade Credits 30 days of feedstock cost
Inventory level for Catalysts 7 days of catalyst cost
Inventory level for Chemicals 7 days of chemical cost
4.17 Information For Financial Analysis (To be read in conjunction with Annexure 4)
Project Funding % Grant -
Equity 30%
Debt 70%
Expenditure Pattern
(Grant Terms Required)
Equity before debt or concurrent 10% upfront
Equity,
subsequent
expenditure in
Debt Equity
Ratio
Equity Contribution % Promoter 100%
Financial Institution -
Public -
Debt Composition % Foreign
Currency
Financial Institutions 100%
Suppliers Credit -
Financial Institutions -
Rupee Portion Debentures to Financial
Institutions
-
Debentures to Public 100%
Terms and Conditions of
Debts / Debentures
From FII’s and
Suppliers’
Credits
(Foreign
Currency and
Rupee)
Front end processing fees 0.50%
Exposure fees -
Commitment fees -
Guarantee fees -
Interest Rates and Calculation
Methodology
8%
Loan
Repayment
Moratorium (from Commercial
Operations commencement)
12 Months
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 10 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Terms Number of instalments 20 (5 Years)
Frequency of Instalments Quarterly
For Debentures
to Fis and
Public
Coupon rate -
Redemption Terms -
Interest rate on Short Term Loan 8%
Capacity Build-up 1st year 80%
2nd year 90%
3rd year 100%
Owner Philosophy for
Payment terms
Project Construction
period from zero date
to be counted from
Prices for feed, product, utility streams: To be considered as per Annexure 2.
Applicable Tax Benefits Will be provided during financial
appraisal analysis stage.
4.18 Key Considerations
1. Project cost estimate to be done with ±20% accuracy.
2. PP and its associated new facilities shall be located in a green field land adjacent to the
existing refinery.
3. The utility requirement for the proposed Poly propylene complex will be studied with respect to
the refinery utility system already envisaged in the new 6 MMTPA refinery complex. The
margins available in the refinery utility system capacity after meeting the refinery requirement
will be utilized for catering to the PP complex. It is expected that other than Cooling water all
other utilities like Steam, Condensate, DM water, BFW, Treated Raw water, Instrument air,
Plant air, Nitrogen, Effluent & flare shall be met from the existing NREP utility system, for
Cooling water new utility facilities will be envisaged in the PP complex to cater to the delta
requirement.
All the utilities except for power shall be met either from the Refinery utility system or from the
new utility system envisaged for PP. Power required for the PP complex shall be imported from
Grid
There will be a net increase of raw water intake to the Refinery due to the PP complex.
Adequacy of the existing RWTP and its pump capacity will be checked for the incremental
requirement.
Delta increase in the net power and water intake will be considered in the operating
expenditure.
4. The DFR cost estimate will include cost for the following facilities.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 11 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
i. Plant and Machinery cost for the Process units as listed below.
Sl. No Process unit Capacity,
KTPA
Licensor
1 Poly Propylene 360 Selection not yet completed
ii. Utility and Offsite facilities.
iii. Lab and Warehouse.
iv. SRR and sub stations.
v. Cost towards CSR and community development.
vi. Construction site requirement and Owner’s construction period expense shall be
considered in line with NREP FR (EIL Job no: B265).
vii. Start up and commissioning expense-as per standard practise.
viii. LF, BDEP fee and any other fee.
5. Cost towards the following heads will be excluded from the DFR cost estimate
i. Cost towards any Statutory clearance
ii. Any augmentation required in the existing refinery facilities
iii. Cost for market survey, EIA, RRA, Route survey, soil investigation.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 12 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Annexure-1
Table 1.1: Polymer grade propylene composition
Component Specification Test Method
Propylene 99.6 wt.% (min) ASTM
D2163/D5273
Propane 0.4 wt% (max) ASTM D2712
Methyl-Acetylene 2 wt ppm (max) ASTM D2712
Propadiene 2 wt ppm (max) ASTM D2712
Methane 100 ppm vol (max) ASTM D2712
Ethane 200 ppm vol (max) ASTM D2712
Ethylene 10 ppm vol (max) ASTM D2712
Acetylene 2 wt ppm (max) ASTM D2712
1,3 Butadiene 3 wt ppm (max) ASTM D2712
Total C4´s 10 wt ppm (max) ASTM D2712
C5+ 10 wt ppm (max) ASTM D2712
H2 1 wt ppm (max) ASTM D2504
CO 0.03 ppm vol (max) ISO 6381
O2 1 wt ppm (max) ASTM D2504
COS 20 wt ppb (max) ASTM D6228
CO2 1 wt ppm (max) ISO 6381
Water 1 wt ppm (max) online
Ammonia 0.2 wt ppm (max) ASTM D5273
Total Sulphur 0.5 wt ppm (max) ASTM D6228
Arsine 20 wt ppb (max) By Licensor
Phosphine 0.03 ppm vol (max) By Licensor
Methanol 1 wt ppm (max) ASTM D4864
H2S 500 wt ppb (max) By Licensor
Hexane + Nonene 5 wt ppm (max) By Licensor
Cyclopentadiene 0.05 ppm vol (max) By Licensor
Isopropanol 1 wt ppm (max) By Licensor
Butenes 10 vol ppm (max) By Licensor
Pentenes 10 vol ppm (max) By Licensor
Inert (N2, CH4, C2H6, N-
Butane, I-Butane) 500 wt ppm (max) By Licensor
Non Condensables (N2,
NH3) 100 ppm vol (max) By Licensor
C4, C5 saturated 200 ppm vol (max) By Licensor
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 13 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Component Specification Test Method
hydrocarbons
Green Oil ( C8 – C12) 20 ppm vol (max) By Licensor
Oxygenated solvents
(methanol, ethanol,
propanol, acetone,
acetaldehyde)
10 wt ppm (max) ASTM D4864
Total non C3 unsat.
(Acetylene, Ethylene,
Methyl Acetylene,
Propadiene, Butadiene,
Butene)
50 wt ppm (max) By Licensor
Annexure-2
Table 2.1: Feed, Product and Utility prices
Streams UOM for
price
Price
Feed
Polymer grade propylene Rs/MT 55915.00
Product
Raffia grade Rs/MT 81500.00
Non-woven spun bond
grade
Rs/MT 85900.00
Non-woven melt blown
grade
Rs/MT 95000.00
Injection moulding homo
polymer grade
Rs/MT 85900.00
Utilities
Power Rs/Kwh 6.5
Treated Raw Water Rs/m3 17
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 14 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Annexure-3
Table 3.1: List of offsite tankages for PP
Sl. No Service Each Tank
capacity,
Pumpable, MT
No of Bullets Height/
Length, m
Dia, m Type
1 Propylene 1620 3
(2 w + 1 spare)
Note-1
80 8 Mounded
Bullet
Note-1: 3 Number of new propylene bullet each with capacity 1620 MT is considered, with 2
Working + 1 Spare operating philosophy which corresponds to 3 days storage requirement.
Annexure-4
Table 4.1: Information for financial analysis
1 Construction Period 36 months
2 Project Life 15 years
3 Loan Repayment period 5 years
4 Moratorium Period 1 Years
5 Interest on Long Term
Debt
12%
6 Capital Phasing (Total Capital)
1 Year 20%
2 Year 45%
3 Year 35%
7 Capacity Build – up
1st year 80%
2nd year 90%
3rd year onwards 100%
8 Corporate Tax Rate @ 22% X 1.10 X 1.04
9 MAT Not Applicable
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 15 of 15
Design Basis for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Annexure-5
Table 5.1: Manpower requirement
Management - Average salary is Rs. 38.17 lakhs pa.
Non Management - Average salary is Rs. 29.94 lakhs pa.
Unit Management Non Management
Number of Person Number of Person
PP 10 24
Cooling
tower/Offsite/Warehouse
7 12
Total 17 36
.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 2
Market Study for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 5.0
MARKET STUDY
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 2 of 2
Market Study for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
5.0 MARKET STUDY
This section is excluded from the report as per the scope of the work.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 2
Project Location for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 6.0
PROJECT LOCATION
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 2
Project Location for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
6.0 PROJECT LOCATION
The Proposed PP Unit will be set up at Greenfield land adjacent to the existing refinery
complex which is located in Ponkagrant Village at a distance from 25 kms from golaghat
city. The distance of the project site from nearest station/ port/ airport/ city is as given
below:
Furkating Railway Station : 35 km
Jorhat Airport: 44 km
Refer annexure -1 for overall plot plan of PP Unit and its associated facilities and Land
details required for PP Unit in table 6.1 below:
Table 6.1: Land Details
Total area, SQM Plant area, SQM Green belt, SQM
348093 232821 115272
Fig 6.1: Project location
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 5
Project Configuration for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 7.1
PROJECT CONFIGURATION
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 5
Project Configuration for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.1 PROJECT CONFIGURATION
The various facilities envisaged under this project are briefly explained in this section.
7.1.1 Integration of Polypropylene Unit with Existing Numaligrah Refinery Expansion Project
Under NREP a high severity PFCC unit with a capacity of 1.955MMTPA is being
implemented. The LPG that will be generated in the high severity mode will contain a
significant potential of propylene which can be recovered for value addition. The Polymer
Grade Propylene produced in the PRU section of the PFCC Unit is further processed in the
downstream unit i.e. PP unit to produce Homo-polymer grade Polypropylene product.
Schematic diagram of integrating Polypropylene project with ongoing NREP is provided in
figure 7.1.1 below:
Fig 7.1.1: Refinery Schematic Diagram
7.1.2 Basis of DFR
PPU capacity: 360KTPA
Turn Down ratio: The unit is capable of minimum turndown of 50% of design capacity
except for the extruder system for which minimum turndown ratio is 60%.
Feed to PP Unit
1) Polymer Grade Propylene from PFCC
Polymer grade propylene shall be made available from the refinery PFCC unit.
2) Hydrogen
Hydrogen Gas shall be made available from existing NREP header and to be utilized
in the polypropylene unit.
PF
CC
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 5
Project Configuration for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Products Homo-polymer Poly propylene product with an annual grade split is as follows:
Sl.No. Description Annual Product Slate
(MT/Annum)
1 Raffia Grade 190000
2 Non–Woven Spun Bond Grade 90000
3 Non-Woven Melt Blown Grade 25000
4 Injection Moulding Homo-polymer
Grade
55000
Annual Product slate is inclusive of on-spec & off spec (transition) material generated.
By Products
1) Propylene Rich Purge Gas to PFCC
Propylene Rich purge gas from the PP unit is send to PFCC for the recovery of
propylene monomer.
On Stream factor : 8000 hrs /annum
7.1.3 Process Units
Design Capacities of Process units & Licensors names are listed in Table 7.1.1 below:
Table 7.1.1: Process Unit Capacities
Sl No Process unit Design Capacity, KTPA
1 Poly Propylene 360
7.1.4 Utilities System
Major utility systems which shall be implemented as part of the PP project are tabulated in
Table 7.1.2 below.
Table 7.1.2: Utility System Details
Description Specifications Remarks
Treated Raw Water System
Treated Raw Water Normal: 210 m3/hr
Peak :250 m3 /Hr
Demand to be met from the
NREP RWTP.
Cooling Water System
Cooling Tower Cells Capacity : 4000 m3/hr each
Number : 2w+ 1 s
New cooling tower along with new
re-circulating cooling water pump
to meet the cooling water demand
of PP unit
Re-circulating Cooling
Water Pumps
Capacity : 4000 m3/hr each
Number : 2 w+1 s
Demineralized Water System
DM Water Normal: 2 m3/hr
Peak : 95 m3/hr
Demand to be met from the
NREP RODM
Nitrogen System
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 5
Project Configuration for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Description Specifications Remarks
Nitrogen Normal : 990 Nm3/hr
Peak :3740 Nm3/hr
Demand to be met from the
NREP Nitrogen Plant
Compressed Air System
Plant Air Normal : 340 Nm3/hr Peak : 1050Nm3/hr
Demand to be met from the NREP Compressed Air system
Instrument Air Normal: 1300 Nm3/hr
Steam and Power System
Power Normal: 26 MW Demand to be met from Grid
LP Steam Normal: 12532 kg/hr Peak:16532 kg/hr
Demand to be met from NREP utility Boiler
MP steam Normal: Nil Peak: 9000 kg/hr
HP steam Normal : 1050 kg/hr Peak: 1700 kg/hr
MP BFW Normal: 500 kg/hr Pea k: 1000 kg/hr
Demand to be met from existing
Flare System
Hydro Carbon Flare Peak: 130TPH To connected to NREP existing header
Effluent Treatment
Effluent 50 m3/hr To be routed to NREP ETP
Condensate
Suspect condensate Normal: 12532 kg/hr Peak: 13900 kg/hr
To be routed to NREP CPU
Pure condensate Normal: 1050 kg/hr Peak : 4000 kg/hr
To be routed to NREP CPP
7.1.5 Offsite Facilities
Summary of various offsite facilities envisaged are described below:
7.1.5.1 Intermediate Feed/ Product Storage and Transfer
1) Polymer Grade Propylene
3 number of propylene mounded bullets (new), having dimension of 80 m length and 8 m
dia. Each bullet is having pump able capacity of 1620MT
Out of the 3 mounded bullets 2 shall be in operation with one spare.
Table 7.1.3 List of Bullets for Propylene storage
S.No Bullet Capacity MT (Stored) No. of Bullet
Diameter , m
Height, m
Remarks
1 1620 3 8 80 New
This provides a total storage of approximately ~3 days operation based on the design
capacity of PP unit.
B
B
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 5
Project Configuration for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Table 7.1.4 Propylene Transfer Pump
S.No.
Service
Rated Capacity (m3)/hr
Number
Type
Remarks
1. Propylene 115 2 (1w+1s)
Centrifugal (Vertical Can)
7.1.5.2 Finished Product Storage and Transfer
Blending, pellet storage facility and bagging section has been considered within the PP unit.
Product warehouse considered in OSBL is corresponding to 21 days storage.
7.1.6 Land Requirement
Total plot area required to accommodate proposed process units, offsites, utilities and other
infrastructure facilities, control room, electrical substation, mandatory green belt etc of this
project is 348093 SQM
7.1.7 Township
Existing facility of NREP, no augmentation on the township for PP project is considered.
B
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyright EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 4
Process description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 7.2
PROCESS DESCRIPTION
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyright EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 2 of 4
Process description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.2 PROCESS DESCRIPTION
7.2.0 Introduction
A brief process description along with a flow schematic for the polypropylene unit
envisaged is provided in this section.
7.2.1 Poly Propylene Unit
For typical scheme of PPU is provided in Annexure-2
Polymer grade propylene having 99.6 wt% of propylene and 0.4 wt% of propane is
provided from OSBL at 39 kg/cm2(g) and 40 deg C.
Polypropylene unit is divided in 8 sections i.e :
a) Propylene Purification Section
b) Hydrogen purification Section
c) Nitrogen Purification Section
d) Reaction section
e) Resin Degassing Section
f) Vent Recovery Section
g) Extruder and pelleting section
h) Pellet Conveying and homogenization section
A) Propylene Purification Section:
Facilities are provided to purify and pump propylene to reaction section. Traces
amount of components such as water; arsine, oxygen, CO2, CO, ammonia, alcohols
and ketones are reduced to acceptable concentrations in the propylene purification
system to avoid polymerization catalyst poisons. Purification section comprises of:
I. Propylene Arsine removal Vessel
II. Propylene Dryer: To remove water
III. Propylene CO Treater: To remove CO
IV. MAP Removal: To remove acetylene
V. Propylene filter
B) Hydrogen Purification Section:
Hydrogen is added to control the size of the polymer molecule and sets the MFR of
the final product. Low pressure Hydrogen is supplied from OSBL with a battery limit
pressure of 18 kg/cm²(g) and 45 deg C.
Facilities are provided to purify and compress hydrogen to reaction section. Traces
amount of CO, CO2 and water compounds poisons the polymerization catalyst. In
the purification system CO, CO2 and water is reduced to acceptable concentrations
in the purification system.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyright EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 3 of 4
Process description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
C) Nitrogen Purification section:
Nitrogen is supplied from OSBL with a battery limit pressure of 4.0 kg/cm2(g) and at
amb. temperature. Facilities are provided to compress nitrogen and to fed reaction
section which is to be used during reactor shutdown and for designated high
pressure consumer.
Low pressure Nitrogen provided at Battery limit is used for regenerable bed treaters
i.e Hydrogen dryer, Propylene Dryer and CO removal bed. Following major
equipments are provided in the nitrogen purification section:
I. Nitrogen compressor
II. Nitrogen Heater : To heat Nitrogen during regeneration of dryer beds
III. Nitrogen Filter
D) Reaction section :
Fresh propylene is fed to the reactor along with the required catalyst, co-catalyst,
hydrogen and stereo-modifier (donar) for production of four different grades of
homopolymer i.e
I. Raffia Grade : Annual production 190KTPA (*)
II. Non-woven spun Bond grade : Annual Production 90 KTPA (*)
III. Non-woven melt blown grade : Annual Production 25 KTPA (*)
IV. Injection Moulding homopolymer grade : Annual Production 55KTPA (*)
(*)Quantity specified above including off-spec (transition) material generated.
The reaction take place in a gas phase reactor, the heat of polymerization is
removed by evaporative cooling supplied by liquid propylene feed. Reaction gas is
continuously removed from the top of the reactor. Reactor overhead vapor (“Recycle
Gas”) is partially condensed and recycled backed to the reactor. The products are
discharged from the reactor to the resin degassing section.
E) Resin Degassing Section :
A mixture of entrained hydrocarbons and nitrogen separates from the resin in the
resin degassing section. The un-reacted monomer and nitrogen from degassing
vessel top is sent to the vent recovery section for separation of un-reacted monomer
and nitrogen.
F) Vent Recovery Section
Un-reacted monomer from the degassing section is further compressed and Nitrogen
is separated from un-reacted monomer by using propylene as a refrigerant.
Recovered nitrogen rich stream is further used as a conveying gas. Un-reacted
monomer recycled back to the reactor and a part of un-reacted stream which is rich
in propylene content is send to PFCC for propylene recovery.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyright EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 4 of 4
Process description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
G) Extruder and pelleting section
The main flow of granular resin, solid additives and liquid additive from the resin
additive handling system are fed to the extruder. In the extruder the polymer powder
together with solid additives is melted and homogenized through the shear induced
by the co-rotating intermeshing screws.
Gases, nitrogen and devolatilized hydrocarbons are vented from the extruder. The
melt then enters the underwater pelletizer through a die plate where rotating knife
blade cut the melt into pellets. The pellet water slurry is pumped into an agglomerate
remover and pellet dryer. The water returns to the pellet water system consisting of a
pelleting water tank, a pelleting water pump and a pelleting water cooler.
Losses from the pellet water loop are compensated with demineralized water. The
dry pellets are screened (removal of possible oversize pellet agglomerates or
undersize pellets) and pneumatically conveyed to the pellet blending silos for
homogenization.
H) Pellet Conveying and homogenization section
Within the pellet pneumatic conveying system, pellets are conveyed by air in a
conveying system that is suitable to minimize dust and angel hair formation during
the conveying process. The air compressors supply the air for:
• pneumatic conveying of pellets from extrusion to blending silos
• pneumatic conveying of pellets from blending silos to bagging units
• blending air and purge air for homogenization silos
Conveying air is filtered before compression. Downstream of the compressors the air
is cooled. Condensed water is separated, and the air is again filtered.
Within the pellet homogenization process, polymer pellets are homogenized by re-
circulating the pellets around the pellet blending silos. In addition, the silos are
designed with internals that permit pellets to flow at different rates within the body of
the silo. This ensures a homogeneous blend of pellets at the silo discharge point.
Pellets from the blending silos are conveyed to the bagging system. Pellets from the
blending silos are fed by conveying air to the elutriator. Air for elutriators is supplied
by elutriator blower which is equipped with elutriator blower filter. Pellets flow by
gravity via elutriator rotary feeders to the pellets bagging lines and storage.
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 4
Material Balance for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 7.3
MATERIAL BALANCE
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 4
Material Balance for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.3.1 MATERIAL BALANCE
The material balance for the 6 MMTPA refinery with and without Poly Propylene (PP)
unit is compared below.
Table 7.3.1: Material Balance
Description Price,
INR/Ton
Base case, 6
MMTPA refinery,
KTPA
(Note 1)
Max Propylene +
PP case,
6 MMTPA refinery
+PP, KTPA
(Note 2)
Feed
Arab Light 31872 1800 1800
Arab Heavy 29902 4200 4200
Natural Gas 36487 468 473
VR Of Existing Refinery 29735 310 310
Coker Distillate 32303 110 110
Naphtha 35575 45.0 45.0
Total Feed 6933 6938
Product
LPG 38662 674.0 496.0
Poly Propylene 87041.0 0.0 346.0
BS VI Gasoline 43188 1592.0 1518.0
BS VI HSD 39496 3256.0 3160.0
RUF Bottoms To Ex Coker 24815 555.0 555.0
Sulphur 4744 145.0 145.0
Fuel and Loss
711 718
Total Product 6933 6938
Note 1: Base case corresponds to 6 MMTPA Refinery with PFCCU operating in low
severity mode and propylene produced from PRU is absorbed in the LPG product stream
and no propylene sale is envisaged. No PP unit.
Note 2: This case corresponds to 6 MMTPA Refinery with PFCCU operating in propylene
maximization mode or high severity mode and with Poly propylene (PP) unit in operation.
PP taking feed propylene from upstream PFCC unit and producing poly propylene which
will be sold as final product.
B
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 4
Material Balance for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.3.2 Product Pattern
A comparison of product yield (wt %) and products’ percentage contribution in sales
revenue (%) with and without PP unit provided below:
Fig 7.3.1: % Product Yield without PP Unit
Fig 7.3.2: % Product Yield with PP Unit
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 4
Material Balance for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Fig 7.3.3: Product contribution in sales revenue without PP Unit (%)
Fig 7.3.4: Product contribution in sales revenue with PP Unit (%)
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 7.4
UTILITIES DESCRIPTION
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.4.0 Utility System Facilities
This section gives the Utility requirement for the new facilities envisaged in this DFR.
While most of the utility demand for the PP complex shall be met from the NREP existing
utility system, for the rest new dedicated utility system shall be installed in the PP complex
at adjacent to the location of the NREP, Numaligarh Assam.
The Normal and peak utility requirement for the PP complex has been identified and
presented in the following sections.
The broad details of the utility systems are identified in this section. A suitable overdesign
margin has been considered to arrive at the system. This design margin is provided to
take care of the uncertainties in the utility consumption figures that are estimated in the
DFR and shall be firmed up/validated during detailed engineering. Utility consumption
figures have been arrived at considering the requirements in process units, utility systems
and others (Offsite area, leakages, hose stations etc).
All analysis presented in this DFR is made on NORMAL utility consumption / generation,
unless specifically mentioned.
Utility consumption for the PP complex is tabulated in Table 7.4.1 below:
Table 7.4.1: Utility Requirements for PP complex
Utility Utilty Requirements
Treated Raw Water,m3/h 210
Re-Circulating cooling water,m3/hr 6780
Instrument Air Nm3/hr 1300
Plant Air, Nm3/hr 340
Nitrogen, Nm3/hr 990
DM Water, m3/hr 2
HP Steam , TPH 1.05
LP Steam, TPH 12.53
Power (MW) 26
MP BFW, TPH 0.5
Pure Condensate generated ,TPH 1.05
Suspect Condensate generated, TPH 12.53
Cooling water Blow-down, m3/hr 50
Effluent ,m3/hr 50
Flare Peak Load ,TPH 135
Brief write up for each utilities are given in the following sections.
7.4.1 Treated Raw Water System
Treated Raw water for the PP complex will be provided from existing NREP treated raw
water header.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Fig 7.4.1: Typical Scheme of Treated Raw Water System
7.4.1.1. Treated Raw water Requirements of the PP complex
The estimated treated water requirement for various purposes in the complex is
summarized in the following table:-
Table 7.4.2: Treated Raw Water Consumption
S.No Unit Normal
m3/hr
Maximum
m3/hr
1. Cooling water Make up 205 244 (Note-1)
2 PP Unit 5 6
Total Treated Raw Water Demand; m3/hr 210 250 (Note-2)
Notes:
1. Maximum cooling water makeup corresponds to the installed capacity of the cooling
tower.
2. Maximum raw water demand is considering 20% Design margin on normal raw
water requirement. This will also take care of the maximum requirement of any of
the above stream at a time along with the normal requirements of other streams.
7.4.2 Recirculating Cooling Water System
Cooling water, an essential utility in process units is required to remove heat from process
fluids for cooling.
A typical scheme of re-circulating cooling water system is shown in figure below
Fig 7.4.2: Typical Scheme of Recirculating Cooling Water System
PROCESS UNITS
PROCESS UNITS
Cooling Tower
Re-circulating CW pumps
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
The cooling water requirements of the PP Unit and associated facilities will be met
through separate re-circulating cooling water systems operating with treated raw water as
makeup. Cooling water requirement for all the facilities in the PP complex will be entirely
met through one new cooling water systems as mentioned below:-
Cooling water system (Cooling tower): This cooling water system will meet total cooling
water demand of PP unit and its associated facilities such as Lab, PP Substation, and PP
SRR. The cooling water system includes cooling towers, cooling water circulating pumps,
cooling water treatment facilities viz. chemical dosing for quality control, Sulphuric acid for
pH control etc. and other auxiliary items.
The make-up water for the cooling water system shall be taken from the NREP existing
treated raw water system header.
7.4.2.1. Cooling water requirement of the PP Complex
The normal consumption of cooling water in the PP Unit and its associated facility are as
follows:
Table 7.4.3: Cooling Water Requirement
Case Cooling Water Requirement
(m3/hr)
PP 6480
Lab 100
PP S/S 100
PP SRR 100
Total 6780
Total with 10% over design margin 7458
To meet the CW requirement of the complex, quantity as tabulated above, the following
set of equipments have been envisaged as part of the CW system design.
Table 7.4.4: Cooling Water System Configuration
Equipment
Description
Capacity of each
item Quantity required
Cooling Tower System
Cooling Tower
Cell 4000 m3/hr 2W+1S
Cooling water
Pump 4000 m3/hr 2W+1S
Additionally, suitably sized auxiliaries like formulation dosing system, biocide dosing
system, sulphuric acid dosing system, chlorinator, Polymeric Dispersant dosing system,
side stream filter, etc. will be provided.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.4.3 Steam, Power and BFW System
7.4.3.1 Power demand for the PP complex
Power is used in the PPU Unit and its associated facility mainly for the following main
purposes:
a) For driving motors to run various rotating machinery (pumps, compressors,
blowers, etc.) in the complex
b) For meeting the power demand of instruments in the entire complex
c) For operating electric heaters (like instrument air dryer heater, electric tracing of
lines if specified, etc.)
d) For plant lighting and other miscellaneous purposes, etc
Tables below give the power requirement of various units/ facilities in the PP complex:
Table 7.4.5: Power demand (Note-2)
Units/Facilities Capacity, Net Power Consumption, KW
(Note-1)
PP 360 KTPA 23000
Cooling tower 8000 m3/hr 1900
Miscellaneous 1000
Total 26000
Notes:
1. Power demand is based on utility data available in licensor proposal or licensor utility
summary and considering sufficient margin over the licensor data to meet the detail
engineering requirement.
2. The power demand shall be imported from the grid.
7.4.3.2 Steam demand for the PP complex
Tables below give the steam requirement at various levels
Table 7.4.6: Steam demand at various levels
Sl.No. Description Net Steam Demand (TPH)
Normal Peak
1 HP steam 1.05 1.7
2 MP Steam 0 9
3 LP Steam 12.53 16.53
The above Steam demand shall be met from the NREP refinery steam header.
7.4.3.3 Boiler Feed Water demand for the PP complex
Tables below give the BFW (MP) requirement of PPU unit
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 6 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Table 7.4.7:MP Boiler Feed Water (Note-1)
Description Normal
(TPH)
Peak
(TPH)
MP BFW 0.5 1
Note-1: The BFW demand shall be met from the NREP BFW system
7.4.4 DM Water System
DM water for the PP Unit and its associated facility is required for the following purposes:
- As process water for dilution, under water pelletizer and washing
Demand of DM water shall be met from the existing NREP header.
7.4.4.1. DM water Demand of the PP Complex
The estimated DM water requirements of various process units & utilities area are as
given in the following Table:-
Table 7.4.8: DM water requirement
Unit Capacity
KTPA
Continuous Demand,
M3/HR
Note-1
Intermittent demand,
M3/HR
Note-1
Poly Propylene
Unit
360 2.0 95 Start-up filling of
pellet water tank
Total 2 95
Notes:-
1) Continuous & intermittent requirement are based on licensor utility summary.
7.4.5 Condensate System
Steam is being used in the complex as process steam, motive fluid for steam turbine
drives, ejector, heating etc. Condensate results from the steam reboilers, condensate
steam drives etc. Within PP unit, suspect and pure condensate will have segregated
collection system. During normal operation, the suspect condensate and tracer
condensate shall be send to existing Centralized Condensate Polishing Unit (CPU) in
NREP. However, the pure condensate shall be normally routed to existing pure
condensate header in NREP.
The condensate being generated which shall be recovered, can be categorized under
following headings:
a) Pure Condensate: This is condensate produced by a source where the possibility
of contamination by leakage across the heat transfer surface is minimal. This is
ascertained by comparing the process and steam side operating pressures for the
exchanger. If the process side operating pressure is lower than the steam side
operating pressure, possibility of contamination of condensate produced with
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 7 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
process fluid is minimal and the condensate produced from such a source is
deemed ‘pure condensate’.
b) Suspect Condensate: This is condensate produced by a source where the
possibility of contamination by leakage across the heat transfer surface exists. This
is ascertained by comparing the process and steam side operating pressures for the
exchanger. If the process side operating pressure is higher than the steam side
operating pressure, possibility of contamination of condensate produced with
process fluid exists and the condensate produced from such a source is deemed
‘suspect condensate’.
c) Surface Condenser Condensate: Condensate produced by the surface condenser
of a condensing type steam turbine is normally considered as pure.
d) Tracer / Traps Condensate: Condensate produced by the tracing is suspect
condensate.
Condensate generation summary for the complex is as given here under:
Table 7.4.9: Suspect Condensate
Description Suspect Condensate ,TPH (Note-2)
Normal Peak
Poly Propylene 12.53 13.9
Total 12.53 13.9
Table 7.4.10: Pure Condensate
Description Pure Condensate TPH (Note-1,3)
Normal Peak
Poly Propylene 1.05 4.0
Total 1.05 4.0
Notes: 1. Pure condensate is produced from Extruder Barrel.
2. Suspect condensate generated from the PP complex shall be routed to NREP
Condensate polishing unit.
3. Pure condensate generated from the PP complex shall be routed to NREP Power
plant,
7.4.6 Compressed Air And Nitrogen System
Compressed air is required in the complex for the following main requirements:
As Instrument Air to operate the various instruments in the facility and also for the
purging of some control panels
As Plant Air is used for scouring air for side stream filters of cooling water systems,
etc.
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 8 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Compressed air required for all of the above uses is generated at a centralised location in
the plant and distributed to the various users through headers. Two qualities of
compressed air are produced and distributed:
Plant Air comprising compressed air cooled to ambient temperature. This air, though
not containing any entrained water droplets, is saturated with water vapour at the
supply conditions.
Instrument Air comprises compressed air cooled to ambient temperature and dried
to remove water vapour to meet stringent atmospheric dew point requirements.
This system will be designed to supply compressed air to the various users at the required
conditions, quality and quantity.
There will be a common plant air header & common Instrument air header from NREP
Compressed Air System to various process and utility areas.
During a power failure, to enable the safe shutdown of PP Unit, facilities will be provided
to supply emergency instrument air for up to 30 minutes
7.4.6.1 Total Air requirement for the PP complex
The compressed air requirements of the PP complex work out to be as follows:
Table-7.4.11: Total Air (Note-3)
Description Normal (Nm3/hr)
Maximum (Nm3/hr)
Instrument Air (Note-1) 1300
Plant Air (Note-2) 340 1050
Note:
1 Normal
2 Normal Flow is based on considering 2 hoses operating simultaneously and peak
flow is based on air scouring of cooling tower side stream filter.
3 The Instrument Air and Plant Air demand of PP unit and its associated facility is met
from existing header of NREP.
7.4.6.2 Nitrogen system
High purity Nitrogen is required in the PP Unit and associated facility for the following
purposes:
(A) Continuous requirement
Blanketing of surge drums and storage tanks
Purging of compressor seals, flare header purging etc.
(B) Intermittent requirement
Purging of systems during start-ups and shut-downs
Absorbant/ Adsorbant Regeneration
7.4.6.3 Nitrogen requirements of the PP complex
The table below gives the continuous and intermittent consumptions of PP Complex
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 9 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Table 7.4.12: Nitrogen requirement
Unit Capacity, KTPA
Continuous Demand, Nm3/hr
Intermittent demand, Nm3/hr (Note-1)
PPU 360 990 5570
Total 990 5570
Notes:
1. Normal nitrogen requirement is 990 Nm3/hr. Additionally 4580 Nm3/hr is required for
intermittent basis for the following scenario i.e.
Dryer and absorbant re-generation
Back up HP Nitrogen for Reaction section
Start-up purge Nitrogen for reactor after seed is charged
Normal nitrogen requirement shall be met from the gaseous nitrogen produced from
the NREP N2 Plant and Intermittent requirement shall be met through liquid
nitrogen storage and gaseous nitrogen.
7.4.7 Fuel System
No fuel requirement for the NRL PP Project
7.4.8 Flare system
The flare system will be provided for safe disposal of combustible, toxic gases which are
relieved from process plants and off sites during start - up, shutdown, normal operation or
in case of an emergency such as:
Cooling water failure
General Power failure
External fire case
Any other operational failure
Blocked outlet
Reflux failure
Local power failure
Tube rupture
The refinery complex shall have single flare systems, for Hydrocarbon flare for process
units & off-sites handling hydrocarbon and the other for the sulphur block handling sour
flare.
The HC flare from the PP Unit has one independent flare header and shall be connected
to existing flare header of NREP.
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 10 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
7.4.8.1 Hydrocarbon flare load from PP Complex
Given below is the flare load from the PP Unit
Table 7.4.13: Design HC flare load
Relief Scenario, LP Flare Load (kg/hr) Mol.wt Temp. oC
Cooling water Failure 130000 41 45
7.4.9 Air conditioning requirement
Air conditioning system shall be considered in the following facilities
Polymer lab
Canteen
Control room
Satellite Rack Room (SRR)
Fire and safety Building office rooms
All field operators cabins in the process area
Ware house office rooms
Security office for visitors pass at entrance gate
Admin Buliding
Substation (SS)
New Air conditioning system shall be considered in the PP Complex. Centralized Vapour
Absorption Refrigeration (VAR) unit systems in the PP complex with chilled water
network to individual local Air Handling Units (AHUs) are considered to cater to the Air
Conditioning requirements of the PP complex. However, in addition to the centralized
VAR system, some additional standalone AC system for buildings shall be considered
where VAR is not feasible.
7.4.10 Brief specification of Electric Equipments
(A) Emergency Power requirement for PP complex
Emergency power are considered for the compressor Lube oil package, MOVs, Fire
water pump, Lighting, communication system, Hazard detection and signalling etc.
The emergency power required for the PP complex is 750 KW. This emergency
power requirement shall be met from the new emergency generator set in the
Substation of NRL PP complex. The emergency generator set will start
automatically on power failure and feed the selected loads. It shall be capable of
taking care of the load variations (e.g. the starting of the largest rated motor with
specified base load).
(B) Plant Address System
It shall consist of Central exchange(s)/ Distributed intelligent nodes, Master control
station(s) with inbuilt loudspeaker, microphone, Desk type call stations with inbuilt
microphone, loudspeaker for installation in buildings, wall/ column mounting type call
stations for hazardous/ safe areas with external loudspeaker as per Operational
requirements, Flashing beacon for noisy areas.
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 11 of 11
Utilities Description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
(C) Fire Detection & Alarm System
The Fire Detection and Alarm System shall be an independent, micro-processor
based Analogue Addressable system comprising of individual break glass type
manual call points, automatic sensors e.g. smoke/heat detectors, hooters, exit signs,
Main DGFAP, battery, battery charger and other hardware. The system shall be
designed to provide audio-visual indication at the main fire alarm panel to be located
in fire station and zonal panels.
The fire detection system shall be interfaced with fire suppression system, HVAC
system, pressurization system, plant communication system and any other systems
as required.
7.4.11 Fire Protection & Fire water system
The Fire Protection system shall be conceived to operate both in prevention and fighting
mode, depending on the relevant actions selected, either manual or automatic.
The fire fighting system shall be designed & provided as per OISD 116 as follows:
Fire Water system (including Hydrants, monitors, HVLRM, automatic spray
system on process equipments)
Clean Agent System for Control room/SRR
DCP extinguishing system for catalyst/TEAL storage area as per NFPA 17
CO2 extinguishing system as per NFPA 12
Automatic Water spray system in product warehouse
HV spray system on transformers
Portable extinguishers
Mobile fire fighting system
For fire water system, tapings (minimum two number) shall be taken from the existing
fire water network of NREP to cater to the fire water demand of PPU. The NREP fire
water system is designed for fighting two major fires and same is adequate to cater to
the fire water demand of PPU facilities.
Pressure available at tap off point of pp unit (in blocked case) is considered as 9.5 bar
(g).
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 3
Offsite description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP),
NRL
SECTION 7.5
OFFSITE DESCRIPTION
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 3
Offsite description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP),
NRL
7.5 OFFSITE SYSTEM
7.5.1 Intermediate feed storage and pumping
This section describes the storage and pumping facilities of feed/intermediate and
finished product based on the annual production of 360 KTPA of homo-polymer grade
PP. The storage of intermediate and finished products of homo-polymer grade PP. The
offsite facilities are divided into two sections:
Feed/ Intermediate storage and transfer
Finished Product storage and transfer
7.5.2 Intermediate Feed Storage and Transfer
Intermediate storage has been provided to take account of turnaround, interruption
(including emergency), catalyst regeneration & replacement etc. Intermediate unit feed
flow control will be within the respective unit. Intermediate feed storage mounded bullets
is considered based on 2 days intermediate storage basis.
7.5.2.1. Propylene Storage and Transfer
PPU receives polymer grade propylene as feed from the upstream PFCC unit.
Propylene shall be treated in the Propylene treating section of the PPU to remove
impurities such as Moisture, MAP, CO arsine etc from polymer grade propylene and
shall be converted to polypropylene in the polymerization section of the PPU. Normally,
PPU will receive 100 % of feed directly from the PFCC unit. However, in case of
emergency shutdown of the PP Unit, provision has been kept to store polymer grade
propylene in the offsite storage. Accordingly 3 days storage has been considered for
propylene. Three (3) no. of mounded bullets (MB) each with a pumpable capacity of
1620 MT have been considered for storing propylene.
The bullets and pumps considered for selected case are mentioned below.
1) The three (3) new propylene bullets of pumpable capacity of 1620 MT each shall be
used to store polymer grade propylene
2) Two pumps (one operating one standby) shall be considered each with a rated capacity
of 115 m3/hr for transferring of polymer grade propylene from the bullet to PP battery
limit.
Table 7.5.1: Polymer Grade Propylene Mounded Bullet Summary
Mounded
Bullet Service Bullet Pumpable
Capacity No of Bullet
Diameter Height Remarks
Propylene 1620 MT 3 (Note-1)
8 m 80 m 2 working + 1 spare
Note 1: All the 3 new bullets are considered in NRL PP complex.
B
B
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 3
Offsite description for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP),
NRL
Table 7.5.2: Propylene Pump Summary
S.No. Service Rated Capacity (m3)/hr
Number Type Remarks
1. Propylene Transfer Pump
115 2 (1w+1s) Centrifugal
(Vertical Can type)
1w+1s
7.5.3 Finished Product Storage and Transfer Philosophy
The objective of providing product storage is to ensure receipt of unit rundown, testing
of product, and evacuation of on-spec product to consumer end. Additionally this will
also help to ensure availability of product in case of emergency shutdown of unit or
continued running of unit in the event of interruption in product transfer or dispatch for a
period. The bagged PP product shall be stored in the warehouse, which will be sized
corresponding to ~21 days of storage requirement of corresponding to 100%
throughput of the unit.
7.5.4 Man Power Requirement
With the implementation of the new PP project, the complexity of the NREP will increase. Therefore, to strengthen the organization, NRL has recommended manning levels to reflect an effective operations and maintenance that would be required to support the normal operation of the refinery.
For the PP Project Unit operation, the manpower strength required will be a total of 53 persons in various categories, break provided below:
Unit Management Non Management
Number of Person Number of Person
Total 17 36
B
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 2
Product Evacuation System for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP),
NRL
SECTION 7.6
PRODUCT EVACUATION SYSTEM
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 2
Product Evacuation System for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP),
NRL
7.6 PRODUCT EVACUATION FACILITIES
This section describes the evacuation facilities of finished products from Polypropylene
unit of NREP. This chapter focuses on the mode of transfer of the finished products and
the facilities associated for evacuation.
7.6.1 Product evacuation
All different grades of homo-polymer shall be dispatched by road from PP unit at
NREP complex to different customers. The different grades with annual capacity are
tabulated below:
a) Raffia Grade 190 KTPA
b) Non-Woven Spun Bond grade 90 KTPA
c) Non-Woven Melt Blown grade 25 KTPA
d) Injection Moulding Homo-polymer grade 55 KTPA
7.6.2 Bagging Facility
90% of product shall be bagged in 25 kg bags and 10% in 1000 kg Flexible Intermediate
Bulk Container (FIBC).Bagging operation should be considered during the period from
6AM to 10 PM i.e 16 hours per day bagging with 12hrs of effective bagging time is
considered.
7.6.3 Product loading in ware house
Bagged product from bagging machine is stacked in the ware house with the help of fork
lift. From the ware house stacked bags of final product is loaded in the truck at loading
station and send to various consumers by road.
Following assumptions are considered for truck loading and unloading facility:
Truck loading/ unloading will take place in only day time 7 hrs/day
Truck Capacity 16 Tons/truck
No. of trucks loading/unloading per station 2 trucks/ station
Time for loading/unloading in 1 station 1 hrs/ station
Table 7.6.1: Truck loading arrangement
Sl.No. Description
1. PP Evacuation 1080 TPD
2. Tons per shift for truck loading (effective 7 Hrs) 1080 Tons
3. Tons per hour available for truck loading per shift ~160 TPH
4. No. of truck required for loading per hour 10 trucks
5. No. of trucks loading station required 8
8 no. of truck loading station & 10 trucks for loading per hour is envisaged for NRL PP Unit.
B
B
B
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 2
Logistics for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
SECTION 7.7
LOGISTICS
TEMPLATE NO. 5-0000-0001-T2 REV. 2 / 28.11.2014 COPYRIGHTS EIL – ALL RIGHTS RESERVED
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 2
Logistics for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
7.7.0 LOGISTICS
This chapter deals with the movement of polymer grade propylene from NREP complex
to PP Unit and finished Homo-Polymer PP grade products outside the refinery.
7.7.1 Polymer Grade Propylene
Polymer Grade propylene produced from PFCC of NREP is fed to PP unit. Intermediate
Storage capacity of 2X1620MT of polymer grade propylene is provided for PP unit.
Three (3) new propylene bullets are envisaged for PP Unit in the complex with 2 working
+1 stand by philosophy.
7.7.2 Finished solid products
All four grades of homo-polymer polypropylene are supplied in pellet form and packed in
25kg bags or in 1000 kg Flexible Intermediate Bulk Container (FBIC). These polymer
bags placed in pallets are stored in the warehouse and are transported via truck by road
to the designated consumers.
8 no. of truck loading station with 2 trucks loading in 1 station is envisaged for NRL PP
Unit
7.7.3 Utilities
All utilities required for the PP plant shall be met from the NREP utility system except for
Cooling water and power. New cooling tower is envisaged to cater the PP demand.
Power will be ingested from the grid.
Power
The total power demand of PP Complex i.e. 26 MW shall be met from the grid. No
separate facility for power generation is envisaged for the PP Unit.
Treated Raw Water
Total Treated raw water required for PP unit and cooling tower (make water) is 210m3/hr
(Normal) and 250m3/hr (Design). The required amount of treated water is met from
existing RWTP in NREP complex. The raw water pump which is used to pump raw water
to RWTP and the raw water treatment plant is adequate to cater this increased 250
m3/hr flow required for PP Unit as confirmed by NRL.
B
B
B
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 15
SECTION 8.0
ENVIORNMENTAL CONSIDERATIONS
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 15
8.1. Pollution Control Measures
All applicable environmental standards prescribed by Ministry of Environment, Forest &
Climate Change (MoEF&CC) and Central Pollution Control Board (CPCB) shall be applicable
to this project. Various pollution control measures required to meet the prevailing
environmental standards are planned for each case at the different stages of execution of the
project, viz., design, construction and operational phases.
8.2. Indian Environmental Legislation
Government of India has made many legislations/rules for the protection and improvement of
environment in India. Various environmental legislations/rules applicable to the proposed
project facilities are as follows.
- The Environment (Protection) Act, 1986, amended up to 1991
- The Environment (Protection) Rules, 1986, amended upto 2008, schedule 1, s.no.3
- Environment (Protection) Third Amendment Rules, 2002
- Environment (Protection) fifth Amendment Rules, 2009, schedule VI, part D, Item III,
s.no.6
- Environment (Protection) Amendment Rules, 2012
- Coastal Regulation Zone-Notification dated 18th January, 2019.
- The Public Liability Insurance Act, 1991, amended 1992
- The Public Liability Insurance Rules, 1991, amended 1993
- The Water (Prevention and Control of Pollution) Act, 1974, as amended up to 1988.
- No. 19 of 2003, [17/3/2003] - The Water (Prevention and Control of Pollution) Cess
(Amendment) Act, 2003.
- The Water (Prevention and Control of Pollution) Rules, 1975
- The Water (Prevention and Control of Pollution) Cess Rules 1977 as amended up to
1992
- The Water (Prevention and Control of Pollution) Cess Rules 1978 as amended up to
1992.
- The Water (Prevention and Control of Pollution) Amendment Rules, 2011.
- The Air (Prevention and Control of Pollution) Act 1981, as amended up to 1987.
- The Air (Prevention and Control of Pollution) (Union Territories) Rules, 1983
- Hazardous Wastes (Management and Handling) Rules, 2008, amended up to 2009.
- Manufacture, Storage and Import of Hazardous Chemical Rules, 1989 (Amendment)
Rules, 2000.
- Noise Pollution (Regulation and Control) Rules, 2000, amended up to 2010.
- Common Hazardous waste Incinerator rules, The Environment (Protection) Rules, 1986,
amended up to 2008, schedule 1, s.no.100.
The proposed Polypropylene project of NRL shall be designed taking into account the
above-referred legislations/rules and as per the directives of Environmental Clearance
documents. Besides this the proposed effluent and emission standards will also be compiled
for this Project.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 15
A brief description of the environmental protection measures proposed to be adopted in the
project with respect to the various components of the environment like air, water, noise, land,
ecology etc., are given in the subsequent sections.
8.3. Pollution Control Measures
In order to minimize the impact of the project on the environment, due attention is being
given for implementing effective pollution control measures. The design stage endeavors to
mitigate the problems related to health, safety and environment at the process
technology/source level itself. The design basis for all process units lays special emphasis
on measures to minimize the effluent generation at source.
During the operation of the plant, the major areas of concern will be stack emissions and
fugitive emissions of hydrocarbons from the process units and storage tanks along with
disposal of treated effluent. Handling, treatment and disposal of hazardous wastes will also
be an area of concern.
The specific control measures related to gaseous emissions, liquid effluent
treatment/discharges, noise generation, solid waste disposal, etc., along with relevant
stipulated standards are described below:
8.4. Air Environment
The gaseous emissions from the proposed expansion project will be controlled to meet all
the relevant standards stipulated by the regulatory authorities. Standards applicable to this
project are classified into three categories:
Ambient Air Standards
Emission Standards
VOC control, Emission and Monitoring
8.5. Ambient Air Standards
The ambient air quality around the premises will be limited to those limits as per National
Ambient Air Quality Standards, which are given below in Table- 8.1.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 15
Table 8.5.1: National Ambient Air Quality Standards 2009
S.No. Pollutants Time Weighted
Average
Concentration in Ambient Air
Industrial,
Residential, Rural
and Other Area
Ecologically
Sensitive
Areas (Notified
by Central
Government)
1.0 Sulphur Dioxide (SO2),
µg/m3
Annual Average* 50 20
24 hours** 80 80
2.0 Oxides of Nitrogen as
NO2, µg/m3
Annual Average* 40 30
24 hours** 80 80
3.0 Particulate Matter (size
less than 10 µm) or
PM10 µg/m3
Annual Average* 60 60
24 hours** 100 100
4.0 Particulate Matter (size
less than 2.5 µm) or
PM2.5 µg/m3
Annual Average* 40 40
24 hours** 60 60
5.0 Ozone (O3), µg/m3 8 hours** 100 100
1 hour** 180 180
6.0 Lead (Pb), µg/m3 Annual Average* 0.5 0.5
24 hours** 1 1
7.0 Carbon Monoxide (CO)
mg/m3
8 hours** 2.0 2.0
1 hour** 4.0 4.0
8.0 Ammonical (NH3),
µg/m3
Annual Average* 100 100
24 hours** 400 400
9.0 Benzene (C6H6), µg/m3 Annual Average* 5 5
10.0 Benzo (α) Pyrene
(BaP), Particulate
Phase Only ng/m3
Annual Average* 1 1
11.0 Arsenic (As), ng/m3 Annual Average* 6 6
12.0 Nickel (Ni), ng/m3 Annual Average* 20 20
* Annual Arithmetic mean of minimum 104 measurements in a year at a particular site
taken twice a week 24 hourly at uniform intervals.
** 24 hourly or 8 hourly or 1 hourly monitored values, as applicable shall be complied
with 98% of the time in a year. 2% of the time, it may exceed the limits but not on
two consecutive days of monitoring.
8.5.1 Emission Standards
Ministry of Environment, Forests & Climate Change (MoEF&CC) has issued Environmental
Standards for Petrochemical (Basic and Intermediates) Industry vide G.S.R. 820(E), dated
09/11/2012. Summary of these standards are given below.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 15
Parameter Limiting concentration in
mg/Nm3, unless stated
Existing
refineries
New
Plant/Expansion
of Existing Plant
Furnace,
Boiler,
Heater,
Vaporiser
Sulphur Dioxide (SO2)
Gas firing 50 5
0 Liquid firing 1700 8
5
0
Oxides of Nitrogen
(NOx)
Gas firing 350 2
5
0
Liquid firing 450 3
5
0
Particulate Matter (PM)
Gas firing 10 5
Liquid firing 100 50
Carbon Monoxide (CO)
Gas firing 150 1
0
0
Liquid firing 200 1
5
0
Notes: (i) All values shall be corrected to 3% Oxygen.
(ii) Wet scrubber shall necessarily be operated at the time of decoking.
(iii) Norms for CO shall be monitored only in case of Phthalic Anhydride (PA), Maleic
Anhydride (MA), Terephthalic Acid (PTA) and Dimethyl Terephalate (DMT) Plants.
Norms for CO emissions shall not be applicable to PA/MA manufacturing standalone
existing plants with an installed capacity of less than 30,000 metric tonnes per
annum, provided that such units have a chimney/stack of minimum 30 metres height
for emitting Carbon Monoxide.
Process Emission (Specific Pollutant)
Substance Source Concentration (mg/Nm3)
Existing
Plants
New Plants
Chlorine EDC/VCM plant & Incinerator 10 10
Hydrochloric acid mist EDC/VCM plant & Incinerator 30 30
Ammonia Waste water stripper, acyronitrile
plant, caprolactum plant
75 75
Hydrogen sulphide Naphtha pretreatment, olefin plant 05 05
Phosgene TDI and MDI plant 01 01
Hydrogen cyanide Acrylonitrile plant 10 10
VOC (HAPs)-TDI&MDI TDI, Methylenediphenyl,
diisocyante plants
0.1 0.1
VOC( HAPs ) Benzene
& butadiene
Benzene, Butadiene plants 5 5
VOC (HAPs)
EO,VCM,EDC<CAN,PO
EO,VCM,EDC,CAN,PO plants 20 10
Organic particulate PA, MA and TDI plants 50 25
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 6 of 15
Process Emission (General Pollutant)
Source Limiting concentration
in mg/Nm3
VOC (MA, PA &Phenol) MA,PA,Phenol plants 20
VOC (EB, Styrene,
toluene, xylene,
aromatics, EG,PG)
Ethyl benzene (EB), Styrene,
Toulene, Xylene, Aromatics, EG,PG
plants
100
VOC (paraffin,
acetone,olefins)
Non methane, HC(paraffin), Acetone,
Olefins plants
150
NOTE.- HAP - Hazardous Air Pollutants are those pollutants that cause cancer or other
serious health effects, or adverse environmental and ecological effects.
Standards for Fugitive Emission:
Storage of Volatile Liquids: General Petrochemical/ Petroleum Products
1. Storage tanks with capacity between 4 to 75m3 and total vapour pressure (TVP) of more
than 10 kpa should have fixed roof with pressure value vent.
2. Storage tanks with capacity between 75 to 500 m3 and total vapour pressure (TVP) of 10
to 76 kpa should have internal floating roof or external floating roof or fixed roof with
vapour control or vapour balancing system.
3. Storage tanks with the capacity of more than 500 m3 and total vapour pressure (TVP) of
10 to 76 kpa should have internal floating roof or external floating roof or fixed roof with
vapour control system.
4. The tanks with the capacity of more than 75 m3 and total vapour pressure (TVP) of more
than 76 kpa should have fixed roof with vapour control system.
5. Requirement for seals in Floating Roof Tanks-
I.
(a) Internal Floating Roof Tank (IFRT) and External Floating Roof Tank (EFRT) shall
be provided double seals with minimum vapour recovery of 96%.
(b) Primary seal shall be liquid or shoe mounted for EFRT and vapour mounted for
IFRT. Maximum seal gap width will be 4 cm and maximum gap area will be 200
cm2/m of tank diameter.
(c) Secondary seal shall be rim mounted. Maximum seal gap width will be 1.3 cm
and maximum gap area will be 20 cm2/m of tank diameter.
(d) Material of seal and construction shall ensure high performance and durability.
II. Fixed roof tanks shall have vapour control efficiency of 95% and vapour balancing
efficiency of 90%.
III.
(a) inspection and maintenance of storage tanks shall be carried out under strict
control;
(b) or the inspection, API RP 575 may be adopted;
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 7 of 15
(c) In-service inspection with regard seal gap should be carried out once in every six
months and repair to be implemented in short time; and
(d) the possibility of on-stream repair of both shall be examined.
IV. Storage tanks shall be painted with white colour shade, except for derogation of
visually sensitive area.
Storage of Benzene, VCM and CAN
(i) FRT with vapour for incineration with 99.9% of removal efficiency for volatile organic
compounds (VOC) shall be provided; or
(ii) IFRT/EFRT with double seals, emission-reducing roof fitting and fitted with fixed roof with
vapour removal efficiency of at least 99% shall be provided; or
(iii) Internal floating roof and nitrogen blanketing in between fixed and floating roofs shall be
provided.
Emission control for Road tank truck/ Rail tank wagon loading
Gasoline and Naphtha:
(i) VOC reduction, %
or
(ii) Emission, gm/m3
(i) 99.5
or
(ii) 5
Benzene:
(i) VOC reduction, %
or
(ii) Emission, mg/m3
(i) 99.99
or
(ii) 20
Toluene/Xylene:
(i) VOC reduction, %
or
(ii) Emission, mg/m3
(i) 99.98
or
(ii) 150
General Standards for emissions from VOC (Petrochemicals)
Item Source Quantum limit in gm/hour
for new expansion plants
(gm/hr)
Organic Particulate Phthalic anhydride (PA), Maleic
Anhydride(MA), Toulene Diisocynate plants
process emission
,Toule (MA),
100
VOC-HAPs (TDI+MDI) Toulene Diisocynate TDI, Methylene diphenyl
diisocyante plants-process emission
0.5
VOC-HAPs (Benzene +
Butadiene)
Benzene, Butadiene Plants-Process
emission
25
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 8 of 15
VOC-HAPs
(EO,VCM,EDC,ACN,
PO)
EO,VCM,EDC,CAN,PO plants-process
emission
50
Abbreviations : EG-Ethylene Glycol, PG- Propylene Glycol, EO-Ethylene Oxide, VCM-Vinyl
Chloride Monomer, EDC-Ethylene dichloride, ACN-Acrylonitrile, PO-Propylene Oxide, HCN-
Hydrogen Cyanide
8.5.2 General Guidelines
1. Emission monitoring shall be carried out as per the Emission Regulations – Part III,
published by Central Pollution Control Board.
2. Following methods may be used for measurement of pollutant concentrations in the
emissions:
Table 8.5.2: Method of Measurement of emissions
S.
No.
Parameter Method of measurement
1 Sulphur Dioxide
(SO2 )
USEPA CFR – 40 Part 60 Appendix A Method 6
2 Oxides of Nitrogen
(NOx )
USEPA CFR – 40 Part 60 Appendix A Method 7
3 Particulate Matter
(PM)
USEPA CFR – 40 Part 60 Appendix A Method 5
4 Carbon Monoxide
(CO)
USEPA CFR – 40 Part 60 Appendix A Method
IOA/Combustion analyzer with NDIR
detector
5 Nickel + Vanadium
(Ni + V)
USEPA CFR – 40 Part 60 Appendix A Method 29
6 Hydrogen Sulphide
(H2 S)
USEPA CFR – 40 Part 60 Appendix A Method 15
(D) Guidelines for minimizing emissions from Flare
1. For each flare system it is necessary to establish the maximum quantity of waste gas,
which can be handled. It is also required to establish the minimum quantity of pilot and
purge gas to ensure safe, stable operation and readiness to take the maximum quantity
of waste gas. There is need to measure of pilot, purge and vent gas to the flare. The
composition and sulphur should be determined. After establishing base data, the
refineries should aim towards using essentially pilot and purge gases in the flare. Under
this condition the flare should be completely smokeless. The above may be achieved by
a combination of the following techniques:
(i) Reducing relief gas to flare by management/good housekeeping practices;
(ii) Balancing the fuel gas system;
(iii) Installing a gas recovery system;
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 9 of 15
(iv) Using high integrity relief valves; and
(v) Applying advanced process control
2. The flow rates of pilot, purge and vent gas to flare are to be monitored. Vent gas should
have on/off flow indicator in addition. The opacity of the flare is to be measured.
3. For normal to 20% of max flare capacity the flare should be smokeless. At higher
capacities low smoke is desirable. The flare system is to provide safe, reliable stand-by
system to meet short periods of venting due to start-up, shutdown and emergencies.
Pilot should be under monitoring and under continuous detection. Flare should be under
observation.
4. Quantity of gas vented to the flare should be reported. The periods of venting should be
recorded and target is to have it for less than 5 minutes in consecutive two hours and 24
hrs in a year. Noise level is to be measured and reported.
5. The heights of various stacks will be determined taking into consideration the "Guidelines
for Minimum Stack Height" as per notification by MoEF&CC dated 19th May 1993, which
fixes the minimum stack height based on emission of Sulphur Dioxide. This is as given
below:
H = 14(Q) 0.3
Where H = Stack Height in m,
Q = Sulphur Dioxide emission in kg/hr.
If, the Pollution Control Board specifies any minimum stack height, the higher of the
two will be selected. However, restriction imposed by Civil Aviation Department shall
also be considered.
8.5.3 Gaseous Effluents Generated From Pp Plant
Major Gaseous Emissions will be Process Waste Gas from silos, tanks, Pelletisation/
Extruder area, Polymerisation Reactor etc. These gases will be vented to atmosphere after
meeting the Environmental standards.
8.6. Noise Environment
The following Noise sources will be part of the proposed project:
Extruder Gears and Motors
Recycle Gas Compressors
Powder and Pellet Conveying Compressors
Carrier Gas Compressors
All noise sources exceeding the noise standard will be encapsulated. It is further
recommended to separate extruder motors and gear boxes by a brick wall from the extruder
on the ground level of the extruder building. All mentioned compressors will either have a
noise hood each or they will be placed in a common hood. Personnel working in such noise
areas have to wear the relevant noise protection equipment.
At the boundary of the proposed plant, Ambient Standard for Noise, specified by CPCB as
given below in Table-8.6.1 shall be met.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 10 of 15
Table 8.6.1: Ambient Air Quality Standards in respect of Noise
S. No. Area Code Category of Area Limit in dB (a) Leg
Day Time Night Time
1.0 A Industrial area 75 70
2.0 B Commercial area 65 55
3.0 C Residential area 55 45
4.0 D Silence zone 50 40
Notes : 1. Daytime is reckoned in between 6 am and 9 pm
: 2. Night time is reckoned in between 9 pm and 6 am
: 3. Silence zone is defined as areas upto 100 meters around such Premises as
hospitals, educational institutions and courts. The Silence zones are to be
declared by the competent authority.
: 4. Mixed categories of areas should be as "one of the four above Mentioned
categories" by the competent authority and the Corresponding standard shall
apply.
The following measures for noise control will be followed at the design stage:
- Noise level specification of various rotating equipment as per Occupational Safety
and Health Association (OSHA) standards.
- Equipment layout considering segregation of high noise generating sources.
- Erecting suitable enclosures, if required, to minimize the impact of high noise
generating sources.
8.7. Water Environment
Several measures are proposed to be incorporated at the designs stage towards minimizing
the generation of wastewater and treatment of the generated effluent. Some of these
measures are described below:
Closed blow down system will be incorporated for hydrocarbon liquid discharges in
all the process units, which will reduce the wastewater load to ETP both in terms of
quantum load and quality. This is another of the in-plant control measures.
Appropriate segregation and collection philosophy (separate sewers for
process waste, contaminated rainwater, spent caustic, cooling tower blow down,
boiler blow down etc.) will be incorporated for various effluents depending on
individual stream characteristics.
A comprehensive wastewater management system to comply with treated effluent
quality for disposal as specified by CPCB (as per The Environment (Protection)
Rules, 1986) shall be established.
Process area will be paved to avoid contamination of soil/sub-soil/ground water in
case of accidental spill/leakage of hydrocarbon liquids.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 11 of 15
Table-8.7.1: Standard for liquid effluent Discharge for Petrochemicals (Basic &
Intermediates) Industry
S. No. Parameter Limiting value for
concentration (mg/l, except for
pH)
1 PH 6.0 – 8.5
2 [*BOD (3days at 27°C)] 30 3 **Phenol 5
4 Sulphide (as S) 2
5 COD 250 6 Cyanide ( as CN) 7 ***Fluoride (as F) 8 Total suspended solids 100 9 Hexavalent Chromium (as CR+6)] 0.1
11 ****Total Chromium (as CR) 2.0
Notes:
*State Board may prescribed the BOD value of 30 mg/l if the recipient system so demands.
** The limit for phenol shall be conformed to at the outlet of effluent treatment of phenol
plant. However, at the final disposal point, the limit shall be less than 1 mg/l.
*** The limit for fluoride shall be confirmed to at the outlet of the chrome removal unit.
However, at the disposal point fluoride concentration shall be lower than 5mg/l.
**** The limits for total and hexavalent chromium shall be conformed to at the outlet of the
chromate removal. This implies that in the final treated effluent, total and hexavalent
chromium shall be lower than prescribed herein.
8.8. Waste Water Generated From PP Plant
The wastewater generation from the proposed project will be mostly Intermittent liquid
effluent streams containing White Oil/TEA/Atmer/IPA/other organic components. A
continuous liquid effluent having various organic components like Acetone, Isopropanol,
Tert-butanol will be generated from Phase Separator Process which will have very less flow.
These waste water streams along with non-process effluents like floor wash, contaminated
rain water will be sent to existing ETP of NREP and treated there. The concentrated organic
components and PP powder will be thermally incinerated. 50 m3/hr of Cooling tower blown
down will be routed to existing RO-DM plant of adjacent NRL refinery for treatment and
reuse. Condensate generated will also be recovered.
8.9. Land Environment
During the design stage itself due care will be taken to select the process technologies
generating minimum solid wastes so that their handling, treatment and disposal do not cause
any serious impact on the existing land environment. Also, efforts will be made to recycle
some of the spent catalysts & PP solid powder by way of returning to the original supplier for
reprocessing.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 12 of 15
The solid wastes management plan proposed is briefly described below. The provisions of
Hazardous Waste (Management & Handling) Rules, 1989 and its subsequent amendments
will be complied with.
The following wastes will be generated:
1. Solid waste from PP Plant
2. General Solid Wastes
Solid waste from PP Plant:
Spent Adsorbents Spent Filter Bags, Filter elements etc. will be sent to secured landfill for
disposal. Spent Catalyst will be sold to the recyclers.
General Solid Wastes
Non‐hazardous, non‐recyclable solid waste consisting of waste refractory, spent insulation,
used filter cartridges, spent charcoal, spent clay and sand will be generated. These wastes
will be disposed off in landfill.
8.10. Provision Of Green Belt
A green belt of appropriate width needs to be provided around the plant. This green belt will
help to reduce the noise and visual impact upon the surrounding population as much as
possible. Green belt area considered for PP complex is 115272 SQM which is >33% of the
total plant area.
8.11. Pollution Control Measure In Construction Phase
The overall impact of the pollution on the environment during construction phase is localised
in nature, reversible and is for a short period.
Air
The suspended particulate pollution generated during transportation will be mitigated by
covering the vehicles so as to ensure no spillage. Hosing down the wheels of the vehicles
with water and providing washing troughs for them would further mitigate the amount of dust
generated. In addition, emission of other pollutants from construction machinery using diesel
driven prime movers, will be controlled by proper maintenance.
Noise
Noise emissions from construction equipment will be kept to a minimum by regular
maintenance. Heavy and noisy construction work will be avoided during night time.
Water
Drinking and sanitation facilities at the complex will be provided to the construction
workforce. This is necessary to reduce pollution of any receiving water body and also to
prevent hazards due to water borne vectors. Potable water shall be provided to the workers.
B
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 13 of 15
Socio Economic
R & R plan as approved by District Collector will be strictly adhered and compensation will
be provided. However, R&R is not applicable if no new land is acquired.
8.12. Pollution Control Measure In Operation Phase
It is envisaged that with strict adherence to the pollution prevention and control measures
during the design stage, the environmental impacts could be moderated to the minimum
possible level during the operation phase.
Air
In-plant Control Measures
Some of the important operational measures, which can reduce the impact on air
environment, are as follows:
- Gaseous fuel (maximum possible) will be used in heater & boiler to minimize air
emission.
- Use of low sulfur fuel for minimization of SO2 emission.
- Provision of low – NOX burners in heaters / furnaces / boilers to minimize NOX
emission.
- Provision of high efficiency furnaces (more than 90% efficiency) to minimize fuel
consumption.
- All the emission standards will be met for gaseous emissions.
- Continuous stack monitoring for ambient air pollution.
- Blow down (CBD) system for all the process units to minimize VOC emission from
the operations.
- Leak Detection and Repair (LDAR) programme for fugitive hydrocarbon emission
control will be followed.
- Ensuring preventive maintenance of equipment.
- Developing green belt in the proposed plant premises.
- Ensuring the operations of various process units as per specified operating
guidelines/operating manuals.
- Strict adherence to maintenance schedule for various machinery/equipment.
- Good housekeeping practices
Stack and Ambient Air Monitoring
In order to keep a check on the emissions of SO2, NOx, SPM and CO from
reactor/regenerator, boiler and furnace stacks shall be monitored as per statutory
regulations. Continuous monitors for emissions shall be installed on all major stacks.
Ambient Air Monitoring Stations shall continuously monitor quality of the air in the vicinity
of the plant complex. Laser based instruments for measuring Sulfur Dioxide, NOx,
Particulate matters, Ozone, Lead, Ammonia, Benzene, Benzo(a)Pyrene, Arsenic, Nickel,
Carbon Monoxide, Hydrocarbons shall be used in these Monitoring Stations.
Noise
As the plant is going to be operational on a 24-hour basis, noise considerations are very
important. All equipments will be specified to meet 85 dB (A) at 1 m distance. The
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 14 of 15
exposure of employees working in the noisy area shall be monitored regularly to ensure
compliance with the OSHA requirements.
A green belt of appropriate width around the plant complex will be developed. Treated
Sewage will be used for irrigating this belt.
This green belt will help to reduce the noise and visual impact upon the surrounding
population as much as possible.
Water
In-plant Control Measures
Some of the measures, which can be taken up during operational phase of the complex
are:
- Reducing the actual process water consumption by way of improvement in operation
of processing units.
- Closed blow down system will be incorporated for hydrocarbon liquid discharges in
all the process units, which will reduce the wastewater load to ETP both in terms of
quantum load and quality. This is another of the in-plant control measures.
- Appropriate segregation and collection philosophy (separate sewers for process
waste, contaminated rainwater, spent caustic, cooling tower blow down, boiler blow
down etc.) will be incorporated for various effluents depending on individual stream
characteristics.
- A comprehensive wastewater management system to comply with treated effluent
quality as specified by CPCB shall be established.
- Process area will be paved to avoid contamination of soil/sub-soil/ground water in
case of accidental spill/leakage of hydrocarbon liquids.
- Looking into more options of reusing the treated effluent besides fire water make up
or for horticulture development.
- Ensuring proper monitoring and maintenance schedule for the effluent treatment
plant.
- Providing reuse and recycle of the treated effluent and water.
Water Quality Monitoring
The monitoring of raw influent, treated effluent and the ground water quality in the
surrounding areas will be carried out regularly. For regular monitoring of the operation of
various pollution control facilities, a laboratory with sophisticated instruments and well-
trained manpower shall be established. A separate Pollution Control Cell with qualified
Chemical Engineers/Scientists also form part of the facility, which will ensure that all
pollution control measures are effectively operating and to carry out day-to-day checks,
trouble shooting and further improvements wherever necessary.
Land
To improve the environmental quality following measures are recommended.
In-plant Control Measures
- The solid waste generated in the form of packaging material etc. shall be sold off for
making it suitable for reuse by reprocessing.
Template No. 5-0000-0001-T2 Rev. 2 / 28.11.2014 Copyrights EIL – All rights reserved
Environmental Consideration for DFR
Poly Propylene Unit of Numaligarh
Refinery Expansion Project (NREP)
NRL
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 15 of 15
- The solids wastes identified to be sent to nearby authorized landfill agency for further
disposal.
- In order to improve the aesthetics in the plant surrounding, further plantation shall be
carried out the around the plant boundary.
Socio-Economic
Since the project is big in nature it will affect the socio-economic status of the region due to
high intensive investment, development of infrastructure such as road, railways
communication, education and other common facilities. There will be cascading effects on
economic status and avenues in the area as well as in the buffer zone where in there will be
growth in employment scenario. However there will be adverse impact in terms of usage of
common resources as well as rise in the price of commodities and environmental pollution
However, NRL shall take part actively in the overall development of the area.
8.13. Environment Cell
A Plant Safety & Environment Department under its technical services department, which
consists of well-qualified and experienced technical personnel from the relevant fields should
be in place to look after Environment cell. The Environment Cell will look after the
compliance of statutory Environmental standards applicable for the proposed project.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 9.0
PROJECT IMPLEMETATION AND SCHEDULE
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 2 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
9.0 PROJECT IMPLEMENTATION AND SCHEDULE
Project implementation and schedule for NRL PP can be referred in the following
attachments:
Attachment 9A: Stipulation of project schedule
Attachment 9B: Overall project schedule
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 3 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Attachment 9A
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 4 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
General
The proposed Schedule has been prepared considering following facilities
Zero date has been considered as receipt of BDEP.
Environment clearance is considered under NRL scope and considered to be available
on start offsite enabling / grading activities.
All statutory approvals (CEA, PESO, AAI etc.) for establishment of new facilities have
been considered in scope of Client.
All As-Built Drawings and other inputs shall be provided to EIL by NRL on or before
Kickoff Meeting.
Thermal design of equipment is considered under Licensor scope of BDEP.
Site free from encumbrances shall be handed over at the start of pre-project activities.
ODC Route Survey report is considered to be made available on or before Zero date by
Client.
Existing Bullet at NREP plot is adequate to be used for Propylene Storage.
Utilities requirement such as Steam, DM water, Condensate, BFW, N2, IA / PA, Flare,
Treated raw water, etc., will be met from existing utility systems from NREP.
Fabrication / Lay down area for the following shall be arranged by Client (NRL):
- Structure steel storage, fabrication
- Piping shop fabrication
- Site fabricated equipment
- Office Space & Storage to the working agencies.
Following pre project activities / facilities has been considered by awarding a tender.
- Topographical survey
- Soil Investigation work
- Site enabling (Boundary Wall, Fencing, approach road, site Grading, Road, drain,
- culverts, Area Lighting, etc)
- Construction Power / Construction Water/ Temporary construction facility
- Site Office / Central Warehouse / Open Storage yard.
Project Implementation Stage (EPCM SERVICES / OBE – as applicable)
Following Units, Utilities & Offsite facilities has been considered for execution.
Major Process Units
POLY PROPYLENE UNIT (PPU) : 360 KTPA
Associated Facilities
Cooling Tower (2+1) with capacity 4000 Cum /Hr. each along with recirculation
Pumps and other accessories.
Offsite Storages / Buildings
Propylene Bullets (3 Nos.) (2 W+ 1S)
Polypropylene Warehouse
Polypropylene Laboratory
Canteen
Control Room
CRR and Sub Station
Fire Station
Service Building
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 5 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Dry Chemical Powder (DCP) Building
Chemical Storage Building
Philosophy of Execution: Poly Propylene Unit (PPU) & Associated Facilities
1. Project execution mode is EPCM / OBE as applicable. However following packages
considered as LSTK Contract :
Cooling Tower
Bullets
Extruder Pelletisation Package
Pneumatic Conveying Package
TEAL Package
2. Permanent power required for this unit considered to be sourced from existing refinery.
3. Total 4 Nos (1 UG + 3 AG) of Piping MTOs have been considered.
4. Tendering cycle time duration is considered as 3 and 4 months for item rate contracts
and package contracts respectively.
5. Ordering cycle of category-II equipment / materials is considered as 3 and 3.5 months
for indigenous and global MRs respectively and for Category – I equipment / material,
2.5 & 3 months for indigenous & global MRs respectively.
6. Based on Licensor BDEP, Vendor list will be finalized to be adopted for execution of
project.
7. Provision for air freighting of imported items shall be made depending on schedule
requirement.
8. Duration of Max. 2 weeks is considered for documents requiring Client’s comments /
approval. Efforts to be made to get the documents approved with-in a week or across
the table.
9. Since the expected zero date is not known, monsoon period is not indicated on the
schedule bar chart. However, the construction activities shall have the Monsoon period
impact (~3 Months/year from July to September). Adequate monsoon protection shall be
kept in scope of respective contractors.
10. Procurement of structural steel, cement, cable trays, cable ducts, lighting fixtures etc.,
have been considered under respective contractor scope.
11. Barricading works wherever deemed necessary is considered under respective
contractors.
12. The erection of heavy equipment considered in respective Package contractor /
Mechanical contractor scope.
13. Composite Works included to get more competitive bids. Composite works included in
Mechanical, piping, Painting, insulation.
14. Hook ups will be made part of Mechanical works tender.
15. Separate contract for Electrical & Instrumentation works is considered. Based on
requirement (if any), tender for Electrical and Instrumentation works can be merged with
composite works as stated in point no. 16 above, depending upon finalized Execution
methodology in due course.
16. Based on finalisation of Execution philosophy, to execute the Hookups required,
shutdown is envisaged for providing utilities to new Polypropylene Unit.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 6 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
17. Covid – 19 protocol and SOPs shall be taken care by respective contractors and for
compliance.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 7 of 7
Project Implementation and Schedule for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Attachment 9B
MONTHS ------------------->
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
1 AWARD OF LOA
2 KICK OF MEETING Within two Weeks
3 CLIENT INPUTS
3.1 ENCUMBURANCE FREE LAND HANDING OVER
3.2 AVAILABILITY OF ODC ROUTE SURVEY
3.3 AVAILABILITY OF LICENSOR BDEP
3.4 STATUATORY APPROVALS (EIA / RRA) EIA RRA (AFTER CLIENT INTIMATION)
3.5 ASBUILT DRAWINGS AND OTHER INPUTS
4 SITE ENABLING ACTIVITIES AND PRE-PROJECT ACTIVITIES
4.1 TOPOGRAPHY SURVEY
4.2 SOIL INVESTIGATION SURVEY
4.3SITE ENABLING WORKS (BOUNDRY WALL / FENCING / APPROACH ROAD / SITE GRADING / ROADS / DRAINS, CULVERTS)
4.4 CONSTRUCTION POWER / WATER
4.5 SITE OFFICE / CENTRAL WAREHOUSE / OPEN STORAGE YARD
5 PROJECT IMPLIMENTATION STAGE (COMMON FOR BOTH SCHEDULES A & B)
5.1 RESIDUAL BASIC ENGINEERING
5.2 DETAILED ENGINEERING
6 PROCUREMENT
6.1 LLIs
6.1.1 POLYMERIZATION REACTOR AT SITE DURATION: 18-20 MONTHS
6.1.2 COMPRESSORS AT SITE
6.1.3 COLUMNS AT SITE
6.2 PACKAGES
6.2.1 EXTRUDER & PELLETIZATION PACKAGE AT SITE DURATION: 20-22 MONTHS
6.2.2 PNUMETIC CONVEYING PACKAGE AT SITE DURATION: 16-18 MONTHS
6.2.3 TEAL PACKAGE (TRI ETHYL ALUMINUM PACKAGE) AT SITE DURATION: 18-20 MONTHS
6.2.4 BALANCE PACKAGES AT SITE DURATION: 14-18 MONTHS
6.3 BALANCE EQUIPMENT AT SITE DURATION: 08-14 MONTHS
6.4 BULK PROCUREMENT
6.4.1 BULK - PIPING
6.4.2 BULK - ELECTRICAL / INSTRUMENTATION
6.4.3 DCS
7.1 CONSTRUCTION
7.1.1 PILING
7.1.2 CIVIL/ STRL/ UG PIPING
7.1.3
BUILDING WORKS (SS / SRR / WARE HOUSE / LAB / CANTEEN / CONTROL ROOM / FIRE STATION / SERVICE BUILDING / TEAL BUILDING / DCP BUILDING / CHEMICAL STORAGE BUILDING)
7.1.4 COMPOSITE WORKS (MECH / PIPING / INSULATION)
7.1.5 ELECTRICAL & INSTRUMENTATION WORKS
7.2 PACKAGES
7.2.1 PACKAGES
7.2.2 OTHER PACKAGES (HVAC / EOT / CLEAN AGENT SYSTEM / FIRE FIGHTING SYSTEM)
7.2.3 COOLING TOWER PACKAGE DURATION: 14 MONTHS
7.2.4 BULLETS (02 New + 01 Existing) (08 M Dia X 80 M Length) DURATION: 18 MONTHS
8 MECHANICAL COMPLETION
8.1 MECHANICAL COMPLETION
9 PRE-COMMISSIONING AND COMMISSIONING
9.1 PRE - COMMISSIONING AND COMMISSIONING
LEGEND: TENDER Mat Requisition AWARD/ LOI MATERIAL DELIVERY (PART) ACTIVITY MATERIAL DELIVERY (FULL) ACTIVITY
DATE REV
S. NO DESCRIPTION REMARKS
DURATION: 06 MONTHS
DURATION: 15 MONTHS
DURATION: 04-08 MONTHS
DURATION: 06-10 MONTHS
DURATION: 20 MONTHS
DURATION: 05 MONTHS
DURATION: 20 MONTHS
DURATION: 20 MONTHS
DURATION: 12 MONTHS
DURATION: 08-14 MONTHS
PROJECT : PPU AND ASSOCIATED FACILITIES
L1 SCHEDULEB394-000-27-44-SO001
LOCATION : NUMALIGARH, ASSAM
CLIENT: NRL PURPOSE
ISSUED FOR DFR
APVD
SK
CHKD/ REVWD
DURATION: 08 MONTHS
DURATION: 08 MONTHS
AM0
DURATION: 14-16 MONTHS
DURATION: 14-16 MONTHS
TSS
PREP
DURATION: 14-18 MONTHS + 06 M Site works
DOCUMENT NO.
T R
HAZOP REVIEW
COMMISSIONING
MECH. COMPLETION
UG
R R
R R
R RAG
````
R R
R
R
R
T
T
T
FEILD ENGG.30% MODELLING 60% MODELLING 90% MODELLINGMTO UG
1ST MTO INTERMEDIATE MTO FINAL MTO
<---------------MAJOR CIVIL/STRL. DRAWINGS------------>
OVERALL PLOT PLAN
EQUIPMENT LAYOUT
R R
R R
R
R
T
SITE WORKR
T
T
T
T
T
T
T
T
1 / 1
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 10.0
PROJECT COST ESTIMATE
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
10.0 PROJECT COST ESTIMATE
10.1. Introduction Numaligarh Refinery Limited (NRL), a subsidiary of M/s OIL India Limited is a public sector
undertaking under the Ministry of Petroleum and Natural Gas. The refinery located at
Golaghat District in Assam was commissioned in the year 2000 with a crude processing
capacity of 3 million tonnes per annum (MMTPA) to process indigenous crude of Assam.
The refinery primarily produces MS & HSD conforming to BS-VI specification.
NRL is installing a parallel new refinery of crude processing capacity of 6 MMTPA to
expand its capacity from present 3 MMTPA to 9 MMTPA. The project is integrated with a
new crude oil pipeline from Paradip (Odisha) to Numaligarh (Assam) and a product
pipeline from Numaligarh to Siliguri where NRL has its own Marketing Terminal for
distribution of product.
NRL has engaged EIL for the Licensor Evaluation & Detailed Feasibility Study Report for
Poly Propylene Unit (PP Unit) of Numaligarh Refinery Expansion Project at NRL, Assam.
The capacity of Poly Propylene Unit is 360 KTPA.
10.2. Scope
The Project envisaged following process unit and Utilities & Offsites:
Unit Description Capacity Execution
Mode
Poly Propylene Unit 360 KTPA EPCM
Re-circulating Cooling
Water System
Cooling Tower 2W +1 S @
4000m3/hr each
Cooling water Recirculation
Pumps 3 pumps (2W +1S) of
4000 m3/hr capacity, 60m Head,
Casing- Cast Iron, Impeller-
Bronze.
EPCM
Offsites
Propylene Transfer Pumps
1W+1S, 115m3/hr, 643.5m head.
Propylene reprocessing pump
1 stand by,20m3/hr, 335m head
Propylene Bullets 2W+1S,
Estimated total wt : 3108MT
EPCM
Truck Loading Facilities 72 Nos. Fork lift EPCM
Emergency DG set 750 KW EPCM
B
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
10.3. Reference Document
Preliminary Equipment List & technical specifications, Engineering inputs, System
capacities etc.
10.4. Project Cost
Capital cost estimate for the project for the proposed scope of work and Units on EPCM
(Engineering, Procurement and Construction Management) execution methodology works
out as under. This is including cost escalation during implementation Phase.
Zero Project start date as Oct 2021: Rs 4,515.00 Cr with Foreign Component of
1331.11 Cr
Zero Project start date as Oct 2022: Rs 4,735.31 Cr with Foreign Component of
1372.73 Cr
This Capital cost estimate shall be read along with Key assumptions and Exclusions listed
at Para 10.5 & 10.6.
10.5. Key Assumptions
The basic assumptions made for working out the capital cost estimate are as under:
Licensor selection has not yet been completed. Project cost may change
according to final selected Licensor.
Cost estimate is valid as of calendar Oct 2021 price basis.
Execution methodology is EPCM.
Exchange rates considered are 1 USD = Rs 74.13
Cost estimate is based on preliminary information provided by Licensors and
available with EIL
MTO has been prepared based on available preliminary data. No detailed
engineering has been done for estimation.
Utility/Offsites, Distribution P&ID’s & Unit ISBL distribution P&ID’s are not yet
finalized. Any changes in same will have impact on MTO.
Detailed Constructability study has not been done.
Package inputs/ costs are based on preliminary details available. Same is likely
to undergo change during detailed engineering depending on selection of vendor.
Buildings have been considered as per table included
Detailed Soil investigation, UG scanning & topography survey report are not
available. On account of this site development quantities are only indicative.
No provision has been kept for any revamp.
B
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
10.6. Exclusions
Following costs have been excluded from the Project cost estimate:
Land for PP Unit & Offsites
Escalation beyond calendar Oct 2021
Township
Railway siding
Removal of unseen / unidentified underground obstructions
Any cost (for Feed, Fuel, Utilities, Catalyst & Chemicals, etc.) towards the
stabilization of the plant or off spec product production.
Cost towards statutory clearances
Captive Power Plant
COT
Pollution control System/ETP
Onshore Pipeline if any
Workshop & Equipment
Infrastructure Facilities other than Approach Road
2 Years Operating & Maintenance Spares
10.7. Estimation Methodology
Cost estimate is based on cost information available from EIL’s current in-house cost data
and Engineering inputs for cost estimation purpose. In-house cost data has been analyzed
and adopted for estimation after incorporating specific project conditions. Cost data has
been updated to prevailing price level using relevant economic indices.
These Cost estimates are subject to identified scope of work and engineering inputs /
technical information, the qualifications, assumptions and exclusions stated herein.
The accuracy of these estimates is targeted at +/-20% based on the methodology used
and the quality of the information available for cost estimation.
10.7.1. Process Unit (PPU & Product Warehouse)
The cost estimate for PP Unit has been prepared based on equipment list / technical
information received from the licensor / technology provider and good for costing
purpose information from Engineering. Equipment cost has been estimated based on
available in-house cost data adjusted to the required capacity and time escalation.
Cost estimates for supply of Bulk Materials i.e. Piping, Electrical and Instrumentation in
process units has been made as factor of equipment cost based on in-house practice
from similar units. Cost provision for mandatory/insurance spares has been made on
factor basis as per in-house norms and procedures.
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Cost provision for Site erection works, Civil / structural works, Insulation & Painting
works, Fireproofing / Chemical Cleaning has also been made on factor basis as per in-
house norms.
PP Warehouse is considered as PEB steel type warehouse of size 290m x 100m. The
estimate is based on available in house data adjusted to the required size and time
escalation. Battery operated forklifts 72 No’s are considered in the estimate for PP
Warehouse.
The cost estimates for Process units are based on their battery limit scope only.
10.7.2. Utilities & Offsites
The cost estimate has been worked out based on technical information for each system /
in-house engineering information with recent in-house cost data available for similar
facilities implemented in other projects. The following equipment/ package are included
in the estimates:
Cost provision for Bulk Materials i.e. Piping, Electrical, Instrumentation and DCS is
based on MTO from in-house Engineering.
Instrumentation bulk mainly consists of Ducts & cables only.
Cost provision for spares consisting of mandatory spares has been made on factor basis
as per in-house norms and procedures.
Civil & Structural facilities envisaged as part of U&O have been estimated on MTO basis
from in-house Engineering for following items only. The broad quantities considered are:
RCC M30- 4500 m3,
Reinforcement [Fe500D]- 800MT
Description Details
Recirculating
Cooling Water
System
Cooling Tower 2W +1 S @ 4000m3/hr each
Cooling water Recirculation Pumps 3 pumps (2W
+1S) of 4000 m3/hr capacity, 60m Head, Casing-
Cast Iron, Impeller- Bronze.
Offsites
Propylene Transfer Pumps 1W+1S, 115m3/hr,
643.5m head.
Propylene Reprocessing Pump, 1No., 20m3/hr,
335m head
Propylene Bullets 2W+1S, Estimated wt : 3108MT
DG Set (750 KW)
Fire Fighting
Equipments
Mobile Fire fighting equipment, FW System
Hydrant system, Fire Extinguishers, Hose Reels,
Long Range Monitor etc.
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 6 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Steel [E350 Grade]- 3200MT
Cost provision for Site erection works, Insulation & Painting works, Fireproofing has
been made as a factor based on in-house norms.
10.7.3. Indirect costs, exchange rates & Statutory taxes/duties
The cost estimate is based on following Exchange Rates, Indirect & taxes duties:
Exchange Rate 1 US$ = Rs. 74.13
Ocean Freight 5.0% of FOB cost of imported equipment
Port Handling 2.0% of FOB cost of imported equipment
Inland freight 5% of FOB cost of imported equipment and ex-works
cost of indigenously sourced equipment
Customs Duty incl. IGST
25.20% (Basis Rate @ 7.5% +10% Social welfare
Surcharge, IGST-15.66%) after taking input tax credit
@ 13% on IGST
GST 15.66% after taking input tax credit @ 13% on GST
Insurance 1% of total cost
10.7.4. Land
Provision for Land for approach road is considered in the estimates. It is based on
following details for the approach road:
Approach road Land area=60000 m2
Land cost =Rs. 32 Lacs/Bigha, (1 Bigha in Assam is 1338 sq. meters)
10.7.5. Site Development
Provision for Site Development (i.e. Site grading / Earth work, Crossings, Sleepers, Pipe
way bridge, Drainage, etc. ) has been kept based on estimated MTOs / quantities of
respective activities from Engineering. Detailed Soil investigation, UG scanning &
topography survey report are not available. On account of this site development
quantities are only indicative
10.7.6. Process Knowhow, Basic Engg. Start up Assistance, License Fee & Training
Provision for Know-how / License fee and Basic Engineering, mandatory services,
additional services & training has been kept based on in-house information / licensor
information for Poly Propylene Unit. GST @ 15.66% has also been included.
Final provision shall be updated based on Licensor Selection.
10.7.7. PMC/EPCM Fee
Provision for EPCM consultant fee is included in the estimates. B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 7 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
10.7.8. Catalyst & Chemicals
Provision for first fill & 6 months of catalysts has been made based on information from
in-house for similar plants & in-house cost data and information received from various
Licensor.
Final provision shall be updated based on Licensor Selection.
10.7.9. Captive Power Plant
No Captive Power Plant is envisaged under this project. The power requirement has
been considered from the grid.
10.7.10. Lab Equipment
A Provision has been considered on Lump-sum basis for Lab Equipments.
10.7.11. Piling
Cost provision for Piling has been kept considering 6000 nos. piles of 500mm, 15m
length & M30 grade.
10.7.12. Buildings
Cost for buildings as listed below is included in the estimates.
Building MTO
Sl.No Building Name Type Floors L (M) B (M)
1 PP-SRR Blast 1 40 30
2 PP-CWTP SRR Blast 1 40 30
3 PP-SS RCC Framed 2 84 30
4 PP-CWTP SS RCC Framed 2 60 30
5 PP Ware House Steel 1 290 100
6 Control Room Blast 1 60 40
7 Polymer Lab RCC Framed 2 60 25
8 Canteen RCC Framed 1 40 20
9 Fire Station RCC Framed 2 60 30
10 Service Building RCC Framed 2 50 40
11 Gate House RCC Framed 2 20 10
12 Ware House
(Chemical, Spare) RCC Framed 1 25 25
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 8 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Cost provision for PP Ware-house has been kept separately and it is based on
preliminary size envisaged (Total 29,000 m2 area considered). A conventional type PP
Warehouse has been considered
10.7.13. Infrastructure Facilities
No additional cost provision has been made related to any infrastructure development
outside the plant battery limit except of 24 m wide x 3.5 km long and 9 m wide x 50m
long approach. Internal roads within the complex have been considered under Site
Development.
10.7.14. Construction Site Facilities
Cost provision for Construction Site Facilities like Site Office, Cement Go Down,
Construction Water & Power etc. is considered on factor basis @ 1.0% of Plant &
Machinery Cost.
10.7.15. General Facilities
Lump sum cost provision (0.5% of P&M Cost) has been made for Office Equipment &
Furniture, Canteen & Welfare Equipment, Safety & Medical Equipment, Training Center
Equipment etc.
10.7.16. Township
There are existing facilities for township. No augmentation of has been considered in the
estimates.
10.7.17. Owner’s Construction Period Expenses
Lump sum cost provision (2.0% of Project cost excluding Working Capital Margin and
IDC) has been made for Owner’s construction period expenses which is primarily for
Project Management, Salaries & Wages, Environment Clearances, Feasibility Reports,
Fund Raising, Recruitment, Training Requirement, Legal Expenses, Office and Vehicles
Hire / Rentals / Maintenance, Stationary, Postage, Travel etc. during project construction
period.
10.7.18. Start up & Commissioning Expenses
Lump-sum cost provision (2.0% of P&M Cost) has been made as per in house norms for
various requirements during start-up and commissioning period such as Chemicals &
Consumables, Vendor Servicemen, Technician & Operators required (except as stated
in next Para).
Cost for Feed, Fuel, Utilities & Catalyst, etc. towards the commissioning /
stabilization of the plant has been excluded.
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 9 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
10.7.19. Corporate Environment Responsibility (CER)
Cost provision towards Corporate Environment Responsibility has been included @
0.50% of Project Cost excluding Working Capital Margin & IDC.
10.7.20. Contingency
Provision for contingency is kept @ 7.50%.
10.7.21. Working Capital/ Margin
Provision for working capital/margin is based on following details:
Goods in process : 4 days of sales
Finished goods: 20 days of sales
Bills Receivable (Outstanding): 21 days of sales
Cash in hand: 15 days of salary
Trade Credits: 30 days of feedstock cost
Inventory level for Catalysts & Chemical: 7 days of cost
25% of Working Capital is capitalized and 75% of working capital is considered for short
term borrowing in financial analysis.
10.7.22. Interest During Construction
Interest during construction period required for the project has been made on the
following basis.
Construction Period: 36 months
Phasing: 1st Year 20%
2nd Year 45%
3rd Year 35%
Interest Rate (Long term/Short term): 12.00%/8.00%
Debt/ Equity ratio: 70:30
Foreign Debt: 100%
Expenditure Pattern: Concurrent
Loan Repayment Period: 5 Years
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 10 of 10
Project Cost Estimate for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
CAPITAL COST
PROJECT :
SL. D E S C R I P T I O N ALL COST IN RS. LAKHS JOB NO. B394
NO. Fc Ic TOTAL CLIENT NRL
LOCATION Numaligarh
1 LAND (APPROACH ROAD) 14 35 14 35
2 SITE DEVELOPMENT INCL. ROADS 69 48 69 48 TYPE OF ESTIMATE
3 PROCESS KNOWHOW, BASIC ENGG. START-UP ASSISTANCE & LICENSE FEE
166 06 166 06
4 EPCM FEE 266 56 266 56 EXECUTION METHODOLOGY
4.1 GST 47 98 47 98
SUB TOTAL (1-4) 166 06 398 37 564 43 ESTIMATE VALIDITY
5.1 PROCESS UNITS
- Poly Propylene Unit 360 KTPA 483 11 1123 59 1606 71
- PP Warehouse 135 13 135 13
1 US $ = 74.13
5.2 CATALYST & CHEMICALS Initial Fill+6 Months 101 40 34 26 135 66
SUB TOTAL (PROCESS UNITS) 584 51 1292 98 1877 49
5.3 UTILITY & OFFSITES 18 09 659 46 677 54
5.4 CAPTIVE POWER PLANT Excluded
5.5 LAB EQUIPMENT 43 17 35 32 78 49
5.6 ONSHORE PIPELINE Excluded
5.7 COT Excluded
5.8 PILING 500mm, 6000 Nos 15m
79 11 79 11
5.9 BUILDINGS 187 31 187 31
5.1 POLLUTION CONTROL SYSTEM/ ETP Excluded
TOTAL (PLANT & MACHINERY) (5) 645 77 2254 18 2899 95
6 INFRASTRUCTURE FACILITIES Approach Road 26 47 26 47
7 CONSTRUCTION SITE FACILITIES 29 00 29 00
8 GENERAL FACILITIES 14 50 14 50 PREPARED BY Jitender Kumar/ Divya/ Shrestha
9 TOWNSHIP Excluded
10 OWNER'S CONSTRUCTION PERIOD EXPENSES 79 37 79 37 REVIEWED BY Ashu Chopra/ S Baishnab
11 START UP & COMMISSIONING EXPENSES 29 00 29 00 58 00
12 CORPORATE ENVIRONMENT RESPONSIBILTY (CER) 19 84 19 84 APPROVED BY Vineet Aggarwal
SUB TOTAL ( 1 - 12) 840 82 2850 73 3691 56 S U M M A R Y
13 CONTINGENCY @7.50% 276 87 276 87
SUB TOTAL ( 1 - 13) 840 82 3127 60 3968 42
14 WORKING CAPITAL MARGIN 56 29 56 29 DOCUMENT NO.
SUB TOTAL ( 1 - 14) 840 82 3183 88 4024 71 REVISION NO.
15 INTEREST DURING CONSTRUCTION (IDC) 490 29 490 29 DATE :
16 TOTAL PROJECT COST … AS OF VALIDITY 1331 11 3183 88 4515 00 PAGE :
17 TOTAL PROJECT COST … AS OF VALIDITY + 1 YEAR 1372 73 3362 58 4735 31 FILE NAME
Format no. 5-6842-1000-F1 Rev.3/1.11.2020
DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
PROJECT COST SUMMARY
CAPACITY
+/-20%
EPCM
EXCHANGE RATES
PROJECT MANAGER
Dr. Shobha Aggarwal
COST ENGINEERING DEPARTMENT
Oct-21
PROJECT :
UNIT: UTILITY & OFFSITESCOST ENGINEERING DEPARTMENT
SL. D E S C R I P T I O N JOB NO. B394
NO. CLIENT NRL
Fc Ic Sc TOTAL LOCATION Numaligarh CAPACITY
1 EQUIPMENTS/SYSTEMS/UNITS UNIT
1.1 Cooling Tower Package (2W+1S) x 4000 m3/hr 21 60 21 60 LICENSOR
1.2 Pumps 9 69 2 48 12 171.3 Fire Fighting Equipments 29 51 29 511.4 Emergency DG Set 750 KW 1 18 1 18
1.5 Propylene Bullets (8m x80m) (1036 MT each), 03 Nos
3108 MT 170 94 170 94
SUB-TOTAL (1)... 9 69 33 17 192 54 235 402 BULK MATERIALS
2.1 Piping 38 26 38 262.2 Electrical 5 82 77 77 83 592.3 Instrumentation 5 35 5 352.4 DCS/PLC 7 51 32 7 83 EXCHANGE RATES
SUB-TOTAL (2)… 5 82 128 90 32 135 04 1 US $ = 74.133 Spares 1 45 1 26 2 714 Catalyst & Chemicals
SUB-TOTAL (1 TO 4)... 16 96 163 32 192 86 373 145 ERECTION / SITE WORKS
5.1 Equipment 5 14 5 145.2 Piping 22 96 22 965.3 Electrical 30 09 30 095.4 Instrumentation 4 47 4 475.5 Insulation / Painting 13 14 13 145.6 Crane Hiring Charges
SUB-TOTAL (5)... 75 80 75 80
6 Civil & Structural Works (Incl. U/G and Fire Proofing)
104 67 104 67
6a Buildings6b Piling
SUB-TOTAL (1 TO 6)... 16 96 163 32 373 32 553 617 Escalation During Execution 27 4 58 8 69 13 54
SUB-TOTAL (1 TO 7)… 17 23 167 91 382 01 567 14
8 INDIRECTS PREPARED BY Jitender Kumar/Divya/ Shrestha
8.1 Ocean Freight 86 86
8.2 Port Handling 34 34 REVIEWED BY Ashu Chopra/ S Baishnab
8.3 Inland Freight 9 26 9 268.4 Insurance 6 71 6 71 APPROVED BY Vineet Aggarwal
S U M M A R YSUB-TOTAL (8)... 86 16 31 17 17
9 TAXES & DUTIES9.1 Customs Duty Excl. IGST 1 49 1 499.2 IGST Component 3 07 3 079.3 GST 28 85 59 82 88 67 DOCUMENT NO.
REVISION NO.SUB-TOTAL (9)... 33 41 59 82 93 23 DATE :
PAGE :
TOTAL COST ... 18 09 217 63 441 83 677 54 FILE NAME
Format no. 5-6842-1000-F2 Rev.2/31.05.2019
ESTIMATE VALIDITY
NOTES
DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
Oct-21
Dr. Shobha Aggarwal
PLANT & MACHINERY (UTILITY & OFFSITES )
ALL COST IN RS. LAKHS
TYPE OF ESTIMATE
EXECUTION METHODOLOGY
PROJECT MANAGER
+/-20%
EPCM
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 6
Financial Analysis for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 11.0
FINANCIAL ANALYSIS
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 6
Financial Analysis for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
11.0 FINANCIAL ANALYSIS
This section is excluded from the report as per the scope of the work.
Financial analysis has been carried out for calculating IRR / NPV of the Project.
11.1 Financial Parameters
1 Construction Period 36 Months
2 Project Life 15 years
3 Debt / Equity Ratio 70:30
4 Capital Phasing (Total Capital)
4.1 1st Year 20%
4.2 2nd Year 45%
4.3 3rd Year 35%
5 Capacity Build – up
5.1 1st year 80%
5.2 2nd year 90%
5.3 3rd year 100%
6 Corporate Tax Rate 25.168%
7 MAT Nil
8 Foreign Debt 100%
9 Loan Repayment Period 5 Years
10 Moratorium Period debt 1 Year
11 Interest Long Term debt 12%
12 Interest Short term debt 8%
13 Expenditure Pattern Equity Concurrent to debt
11.2 Capital Cost
Capital cost has been considered as detailed in Capex section.
11.3 Operating Cost
Operating cost consists of Variable Operating Cost & Fixed operating Cost.
Fixed Operating Cost:
It consist cost towards Salary & wages, Plant & admin overheads, repair & maintenance
and insurance.
Salary & Wages are based on manpower details & CTC as given below
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 3 of 6
Financial Analysis for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Unit Management Non Management
Number of Person Number of Person
Total 17 36
CTC per person, Lakhs per
annum
38.17 29.94
Cost towards Plant & admin overheads, repair & maintenance, insurance is based on
factor as given in Licensor methodology. The factors considered are as follows:
Plant & Admin Overheads : 0.50 % of Installed Cost
Repair & Maintenance : 2.50 % of Installed Cost
Insurance & taxes : 1.00 % of Installed Cost
Variable Operating Cost:
Annual variable operating cost has been considered towards raw material / feed, utilities
& catalyst chemicals.
Feed and utilities quantities are considered as differential of New case (NREP + PP)
Max Propylene and Base case (NREP) Min LPG. Refer Operating Cost Sheet for details.
11.4 Annual Sales Realization
Annual sales realization for has been worked out based on product prices and
differential quantities of New case (NREP + PP) Max Propylene products and Base case
(NREP) Min products. Refer Annual Sales Realization Sheet for details.
11.5 Working Capital Margin
Provision for working capital/margin is based on following details:
Goods in process (4 days of sales)
Finished goods (20 days of sales)
Bills Receivable (Outstanding) (21 days of sales)
Cash in hand (15 days of salary)
Trade Credits (30 days of feedstock cost)
Inventory level for Catalysts & Chemical (7 days of cost)
25% of Working Capital is capitalized and 75% of working capital is considered for short
term borrowing in financial analysis.
11.6 Financial Analysis
Financial analysis has been carried out based on discounted cash flow. The results of
financial analysis are as below.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 4 of 6
Financial Analysis for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Financial Results:
11.7 Sensitivity Analysis
Sensitivity analysis has been carried out to check the impact of variation of capital cost,
Opex and sales in IRR.
The results are tabulated as below
Sensitivity Analysis
Description Cost
Rs. Crore
Capital Cost with Financing
Charges 4515.00
Differential Variable Operating
Cost 320.98
Fixed Operating Cost 197.87
Total Operating Cost 518.85
Differential Sales Revenue 1624.68
IRR Results (Revamp Case) IRR Before Tax IRR After Tax
IRR on Total Capital 20.57% 18.24%
IRR on Equity 25.56% 21.52%
Description IRR Before Tax IRR After Tax
On Total Capital
Base Case 20.57% 18.24%
Capex +10% 18.80% 16.73%
Opex +10% 19.98% 17.75%
Sales +10% 23.34% 20.61%
On Equity
Base Case 25.56% 21.52%
Capex +10% 22.21% 18.66%
Opex +10% 24.44% 20.58%
Sales +10% 31.08% 26.19%
B
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 5 of 6
Financial Analysis for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
ANNUAL SALES REALIZATION OPERATING
COST WORKING CAPITAL
DOCUMENT NO. :
JOB NO. : B394
PROJECT : REV. NO. :
COST ENGINEERING DEPARTMENT CLIENT : NRL DATE :
PAGE :
SL.
NO. DESCRIPTION UNIT ANNUAL
QUANTITY FX IC FX IC TOTAL
A SALE OF PRODUCTS
Base case (NREP)Min LPG
1 LPG Tonnes 674000 38 662 2605 82 2605 82
2 POLY PROPYLENE Tonnes 0 87 041
3 BS VI GASOLINE Tonnes 1592000 43 188 6875 53 6875 53
4 BS VI HSD Tonnes 3256000 39 496 12859 90 12859 90
5 RUF BOTTOMS TO EX COKER Tonnes 555000 24 815 1377 23 1377 23
6 SULPHUR Tonnes 145000 47 44 68 79 68 79
TOTAL 23787 27
New case(NREP + PP)Max Propylene
1 LPG Tonnes 496000 38 662 1917 64 1917 64
2 POLY PROPYLENE Tonnes 346000 87 041 3011 62 3011 62
3 BS VI GASOLINE Tonnes 1518000 43 188 6555 94 6555 94
4 BS VI HSD Tonnes 3160000 39 496 12480 74 12480 74
5 RUF BOTTOMS TO EX COKER Tonnes 555000 24 815 1377 23 1377 23
6 SULPHUR Tonnes 145000 47 44 68 79 68 79
TOTAL 25411 95
DIFFERENTIAL SALES 1624 68
Format no. 5-6842-2000-F6 Rev.4 / 24.09.2015
DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
ANNUAL SALES REALISATION
UNIT RATE (Rs.)
<---------- BASIS --------------> All Costs are in Rs. Lakhs
AMOUNT
DOCUMENT NO. :JOB NO. : B394
PROJECT : REV. NO. :
COST ENGINEERING DEPARTMENT CLIENT : NRL DATE :
PAGE :
SL.
NO. DESCRIPTION UNITDIFFERENTIAL
ANNUAL
QUANTITY FX IC FX IC TOTAL
A VARIABLE OPERATING COST
1 FEED
1.1 ARAB LIGHT MT 31 872
1.2 ARAB HEAVY MT 29 902
1.3 NATURAL GAS MT 5 000 36 487 18 24 18 24
1.4 VR OF EXISTING REFINERY MT 29 735
1.5 COKER DISTILLATE MT 32 303
1.6 Naphtha MT 35 575
2 UTILITIES
2.2 Power KW-h 2080 00 000 6.50 135 20 135 20
2.3 Raw Water m3 20 00 000 17.00 3 40 3 40
3 ANNUAL CATALYST & CHEMICALS 164 14 164 14
TOTAL VARIABLE COST (A) 164 14 156 84 320 98
B FIXED OPERATING COST
1 SALARIES & WAGES 17 27 17 27
2 PLANT & ADMINISTRATIVE OVERHEADS 0.50% 22 57 22 57
3 REPAIR & MAINTENANCE 2.50% 112 87 112 87
4 INSURANCE 1.00% 45 15 45 15
TOTAL FIXED COST (B) 197 87 197 87
TOTAL OPERATING COST (A+B) 164 14 354 71 518 85
Format no. 5-6842-2000-F5 Rev.4 / 24.09.2015
DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
UNIT RATE (Rs.)
<---------- BASIS -------------->
ANNUAL OPERATING COST AT 100% CAPACITY
All Costs are in Rs. Lakhs
AMOUNT
DOCUMENT NO. :
JOB NO. : B394
PROJECT :DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
REV. NO. :
COST ENGINEERING DEPARTMENT CLIENT : NRL DATE :
PAGE :
SL.
NO. DESCRIPTION DAYS QUANTITY (MT) UNIT TOTAL
REQUIREMENT RATE (Rs.) RS LAKHS
1 Goods in process 4 days of sales 19 50
2 Finished goods 20 days of sales 97 48
3 Bills Receivable (Outstanding) 21 days of sales 102 35
4 Cash in hand 15 days of salary 72
5 Trade Credits 30 days of feedstock cost
1 64
6 Inventory level for Catalysts & Chemical
7 days of catalyst cost
3 45
A NET WORKING CAPITAL 225 14
C MARGIN MONEY @25% 56 29
D BANK BORROWING @75% 168 86
Format no. 5-6842-1000-F4 Rev.4
WORKING CAPITAL MARGIN
All Costs are in Rs. Lakhs
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 6 of 6
Financial Analysis for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
FINANACIAL ANALYSIS
Rev. No.Sensitivity Factors Page No. _____ of ______Capital Cost 100%Sales 100%Operating 100%
S No.1 Construction Period in Years 3
2 Project Name3 Job No. B3944 Client Name NRL5 Project Life 156 Fixed Capital Cost Foreign Indeginous
Land 14 35Site Development 69 48Road/Drains/Culvert/BridgesEffluent Teatment plantPlant Building 322 44TownshipNon-Plant BuildingPlant & Machinery 645 77 2021 56Basic Engineering 166 06Detailed Engineering 314 54Start-up and Commissioning 29 00 29 00Owners' Management Expenses 79 37Working Capital Margin 56 29Contingency 276 87Total 840 82 3183 88Total Capital 4024 71
7 Short Term Bank Borrowing 168 868 Debt/ Equity Ratio 2.33 9 Expenditure Pattern
Equity Before Debt(B) CEquity Concurrent To Debt(C)
10 Foreign Debt As % of Total Debt 100%11 Loan Repayment period for Ind. Debt 5.012 Loan Repayment period for For. Debt 5.013 Moratorium Period (Indeginous Debt) 1.014 Moratorium Period (Foreign Debt) 1.015 Interest on Long Term Debt (Ind.) 12.00%16 Interest on Long Term Debt (For.) 12.00%17 Interest on Short Term Debt 8.00%18 Committment Charge - (Ind. Debt)
19 Committment Charge - (For. Debt)
201 Year 10.00% 10.00%2 Year 22.50% 22.50%3 Year 17.50% 17.50%4 Year5 Year
211 Year 10.00% 10.00%2 Year 22.50% 22.50%3 Year 17.50% 17.50%4 Year5 Year
221year 80%2year 90%3year 100%4year 100%
23 Annual Sales At 100% Capacity 1624 6824 Annual Fixed Cost 197 8725 Annual Variable Cost 320 9826 NPV @ (%) 12.00%27 Corporate Tax Rate 25.168%28 MAT (%)29 Section 80HH Applicable (Y/N) N30 Section 80 I Applicable (Y/N) N
Prepared by Reviwed by Approved by
Document No.
Capacity Build - up
Financial Input Parameters
Capital Phasing (Total Capital)
Capital Phasing (Foreign Capital)
DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
Rev. No.Page No.
Job No. : B394Project : DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREPClient : NRL All Costs are in Rs. Lakhs
Opening Balance Withdrawal Interest Commit.
ChargeClosing Balance Debt Opening
Balance Withdrawal Interest Commit. Charge
Closing Balance Debt Foreign Indigenous Total
6 40,247 12325 27921 838 28758 28758 838 838 41085
12 40,247 12843 28758 27921 2563 59242 30484 2563 2563 42810
18 90,556 28799 59242 62822 5439 127503 68261 5439 5439 95995
24 90,556 30027 127503 62822 9535 199860 72357 9535 9535 100091
30 70,432 25167 199860 48861 13457 262178 62319 13457 13457 83890
36 70,432 26289 262178 48861 17197 328236 66058 17197 17197 87629
42
48
54
60
Total 402,471 135450 279208 49029 328236 49029 49029 451500
Date Prepared by Reviwed by Approved by
Months Capital Cost EquityFINANCING CHARGES
_____ of ______
FINANCING CHARGES
Document No.
Total Invest
FOREIGN DEBT INDIGENOUS DEBT
Rev. No.Page No.
Job No. : B394Project : DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREPClient : NRL All Costs are in Rs. Lakhs
FOREIGN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
CUMULATIVE DEBT 328236 328236 262589 196942 131295 65647
DEBT REPAYMENT 65647.27 65647 65647 65647 65647
INTEREST ON DEBT-FOREIGN 39388 37419 29541 21664 13786 5908
INDIGENOUS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
CUMULATIVE DEBT
DEBT REPAYMENT
INTEREST ON DEBT- IND.
TOTAL INTEREST ON DEBT 39388 37419 29541 21664 13786 5908
DEBT REPAYMENT (TOTAL) 65647 65647 65647 65647 65647
Date Prepared by Reviwed by Approved by
YEARS
YEARS
Document No.
_____ of ______
LONG TERM DEBT REPAYMENT
Job No. : B394Project : DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREPClient : NRL
ASSET VALUE RATE ASSET VALUE SALVAGE VALUE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
LAND & SITE GRADING 11298
NON PLANT BUILDING 1.63%
PLANT BUILDING 3.34% 44023 1397 1397 1397 1397 1397 1397 1397 1397 1397 1397 1397 1397 1397 1397 1397 23070
PLANT & MACHINERY 5.28% 386581 19391 19391 19391 19391 19391 19391 19391 19391 19391 19391 19391 19391 19391 19391 19391 95718
WORKING CAPITAL 5628.509477 5629
TOTAL 447531 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 124416
ASSET VALUE RATE ASSET VALUE SALVAGE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 VALUE
LAND & SITE GRADING 11298 11298
EFFLUENT TREATMENT PLANT
NON PLANT BUILDING 10.00%
PLANT BUILDING 10.00% 44023 4402 3962 3566 3209 2888 2600 2340 2106 1895 1706 1535 1381 1243 1119 1007 9064
PLANT & MACHINERY 15.00% 386581 57987 49289 41896 35611 30270 25729 21870 18589 15801 13431 11416 9704 8248 7011 5959 33770
WORKING CAPITAL 5628.509477 5629
TOTAL 447531 62390 53251 45462 38821 33158 28329 24209 20695 17696 15136 12951 11085 9492 8130 6966 59760
Date Prepared by Reviwed by Approved by
DEPRECIATION
DEPRECIATION
__ of ___
Document No.
Rev. No.
DEPRECIATION ( WRITTEN DOWN VALUE METHOD )
Page No.
DEPRECIATION ( STRAIGHT LINE METHOD )
Rev. No.Page No.
Job No. :B394Project : DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREPClient : NRLSL_NO. YEARS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A. Sales Revenue 129974.6 146221.4 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2 162468.2Salvage Value 124416
B. Operating CostsAnnual Fixed Cost 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72 19786.72Annual Variable Cost 25678.51 28888.33 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14 32098.14
C. Intt. on S T Loan 1081 1216 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351D. Intt. on L T Loan 39388 37419 29541 21664 13786 5908E. Ammortization(Sec. 35D) 793.6848 793.6848 793.6848 793.6848 793.6848F. Business Profit 43247 58118 78898 86775 94653 103324 109233 109233 109233 109233 109233 109233 109233 109233 233649
Calculation of MATG. Dep. as per Comps. Act 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788H. Book Profit 22459 37330 58110 65987 73865 82536 88445 88445 88445 88445 88445 88445 88445 88445 212861I. MAT
Calculation of Normal I TDepreciation(WDV) 62390 53251 45462 38821 33158 28329 24209 20695 17696 15136 12951 11085 9492 8130 6966Gross Profit -19143 4867 33436 47955 61495 74996 85023 88538 91537 94096 96281 98147 99741 101103 226682Carry Forward Losses -19143 -14276Profit before Deductions -19143 -14276 19160 47955 61495 74996 85023 88538 91537 94096 96281 98147 99741 101103 226682Relief u/s 80hhRelief u/s 80IPost Deduction Profit -19143 -14276 19160 47955 61495 74996 85023 88538 91537 94096 96281 98147 99741 101103 226682
J. Normal Income Tax 4822 12069 15477 18875 21399 22283 23038 23682 24232 24702 25103 25445 57051
Calculation of MAT Credit
Excess of MAT over NITC F excess MAT over NITMAT Credit Adjustment
Tax to be Paid 4822 12069 15477 18875 21399 22283 23038 23682 24232 24702 25103 25445 57051
Date Prepared by Reviewed By Approved By
Document No.
_____ of ______
INCOME TAX CALCULATIONS
Rev. No.Page No.
Job No. : B394Project : DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREPClient : NRL
CONSTRUCTION PERIOD OPERATING PERIOD1 2 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
CASH INFLOW
A EQUITY 25168 58826 51456
B. DEBT 59242 140617 128377
C. OPERATING REVENUE 129975 146221 162468 162468 162468 162468 162468 162468 162468 162468 162468 162468 162468 162468 162468
D. SALVAGE VALUE 124416
CASH OUTFLOW
E. MAIN INVESTMENT 80494 181112 140865
F. FINANCING CHARGES 3401 14974 30654
TOTAL INVESTMENT 83895 196086 171519
G. OPERATING COST
H. ANNUAL FIXED COST 19787 19787 19787 19787 19787 19787 19787 19787 19787 19787 19787 19787 19787 19787 19787
I. ANNUAL VARIABLE COST 25679 28888 32098 32098 32098 32098 32098 32098 32098 32098 32098 32098 32098 32098 32098
J. INTT. ON SHORT TERM LOAN 1081 1216 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351 1351
K. TOTAL COST 46546 49891 53236 53236 53236 53236 53236 53236 53236 53236 53236 53236 53236 53236 53236
L. GROSS MARGIN(C+D-H-I-J) 83429 96331 109233 109233 109233 109233 109233 109233 109233 109233 109233 109233 109233 109233 233649
M. DEPRICIATION (AS PER C.A.) 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788 20788
N. AMMORTIZATION (SEC. 35D) 794 794 794 794 794
O. NET MARGIN(L-M-N) 61847 74749 87651 87651 87651 88445 88445 88445 88445 88445 88445 88445 88445 88445 212861
P. INTT. ON LONG TERM DEBT 39388 37419 29541 21664 13786 5908
Q. PROFIT BEFORE TAX(O-P) 22459 37330 58110 65987 73865 82536 88445 88445 88445 88445 88445 88445 88445 88445 212861
R. TAX 4822 12069 15477 18875 21399 22283 23038 23682 24232 24702 25103 25445 57051
S. PROFIT AFTER TAX(Q-R) 22459 37330 53288 53918 58388 63662 67046 66162 65407 64763 64213 63743 63342 62999 155810
T. NET CASH FLOW 43247 58118 74075 74706 79176
U. LONG TERM DEBT REPAYMT 65647 65647 65647 65647 65647
ON TOTAL CAPITAL
BEFORE TAX -80494 -181112 -140865 83429 96331 109233 109233 109233 109233 109233 109233 109233 109233 109233 109233 109233 109233 233649
AFTER TAX -80494 -181112 -140865 83429 96331 104410 97163 93755 90358 87834 86949 86195 85550 85000 84531 84130 83787 176597
ON EQUITY
BEFORE TAX -25168 -58826 -51456 44040 -6736 14044 21922 29799 37677 109233 109233 109233 109233 109233 109233 109233 109233 233649
AFTER TAX -25168 -58826 -51456 44040 -6736 9222 9852 14322 18802 87834 86949 86195 85550 85000 84531 84130 83787 176597
83357.25825 96259.18 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 109161.1 234056.583357.25825 96259.18 109161.1 109161.1 97424.62 89632.47 86625.11 85479.39 84611.23 83952.12 83450.61 83068.01 82775.24 82550.43 175838.8
S NO. DESCRIPTION
Document No.
_____ of ______
CASHFLOW STATEMENT
Rev. No.Page No.
Sensitivity Factors Capital Cost 100%Sales 100%Operating 100%
Job No. : B394Project :
Client : NRLAll Costs are in Rs. Lakhs
FOREIGN INDIGENOUS TOTAL . FIXED CAPITAL COST 840 82 3127 60 3968 42
. WORKING CAPITAL MARGIN 56 29 56 29 . FINANCING CHARGES 490 29 490 29TOTAL INVESTMENT 1331 11 3183 88 4515 00
INTERNAL RATE OF RETURN
ON TOTAL CAPITALBEFORE TAX 20.57%
AFTER TAX 18.24%
ON EQUITYBEFORE TAX 25.56%
AFTER TAX 21.52%
NET PRESENT VALUEDISCOUNT RATE 12%
ON TOTAL CAPITALBEFORE TAX 205485 Lakhs
AFTER TAX 135198 Lakhs
ON EQUITYBEFORE TAX 186888 Lakhs
AFTER TAX 116601 Lakhs
PAYBACK PERIOD
ON TOTAL CAPITALBEFORE TAX 4.5
AFTER TAX 4.5
ON EQUITYBEFORE TAX 5.9
AFTER TAX 6.3
BREAK EVEN POINT(%) 51.04%
RETURN ON INVESTMENT 20.80%
DEBT SERVICE COVERAGE RATIO 1.00
PROFITABILITY INDEX ( COST-BENEFIT RATIO)
ON TOTAL CAPITALBEFORE TAX 1.65
AFTER TAX 1.43
ANNUAL REVENUE 162468.22 Lakhs
ANNUAL FIXED OPERATING COST 19786.71707 Lakhs
ANNUAL VARIABLE OPERATING COST 32098.14174 Lakhs
Date Prepared by Reviwed by Approved by
CAPITAL INVESTMENT
Document No.
_____ of ______
FINANCIAL RESULTS
DETAILED FEASIBILTY STUDTY REPORT FOR PPU OF NREP
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 3
HSE for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 12.0
HEALTH, SAFETY AND ENVIRONMENT
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 2 of 3
HSE for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
12.0 HEALTH, SAFETY AND ENVIRONMENT
In order to ensure identification of any hazards associated with the project, which could
adversely affect the health and safety of personnel both within and outside the complex,
and the environment, a sound Health, Safety and Environment (HSE) policy is proposed
to be adopted during the course of project execution with primary objectives as under.
a) Provide clearly defined safety system goals for the design aspects of the project.
b) Ensure a safe working environment for all plant personnel.
c) Through intrinsic safety in design, eliminate the potential for occurrence of
hazardous scenarios that can result in injuries, environmental damage, business
interruptions or loss of assets.
d) Minimize the risk and consequences of an accident which cannot be eliminated by
intrinsic safety in design.
e) Maintain satisfactory means of escape and evacuation from any conceivable
incident.
f) Minimize the potential for pollution of the environment from accidental spills,
venting or flaring of hazardous materials.
In order to ensure the above, it is proposed to carry out the following HSE related studies
during the engineering stage:
- Hazard identification (HAZID) study
- Hazard and Operability Study (HAZOP)
- Quantitative Risk Assessment (QRA) Study
- Hazardous Area Classification
Other health hazards that are proposed to be studied are as follows:
a) Lighting
b) Noise
c) Thermal Environment
12.1 Environment
Wastes are streams that are not produced for sale or internal consumption. Some of
these wastes may be toxic, poisonous, flammable and harmful to the environment.
Hence, it is of utmost importance that the wastes generated are disposed off safely.
When waste production cannot be avoided, the following design principles shall be
adopted to achieve environmental compliance:
a) Minimise the waste generation
b) Safe disposal facilities within development boundary
c) Safe disposal facilities outside the unit.
Wastes generated are of three types:
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 3 of 3
HSE for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
a) Solid
b) Liquid
i. Aqueous
ii. Non-aqueous
c) Gaseous
i. Point source gaseous emissions
ii. Fugitive emissions
Adequate care will be taken in process design to minimize the quantity of waste
produced. In addition, solid, liquid and gaseous wastes generated from various
processes in the refinery will be handled in a manner that minimizes their impact on the
environment. Some of the measures to be taken are as follows:
Solid Waste - It is recommended to dispose off solid waste such as spent catalyst,
tank bottom sludge and ETP sludge in secured landfills outside the refinery complex.
Liquid waste - A fully fledged Effluent Treatment Plant (ETP) based on the state-of the
art technology has been considered in the refinery to treat various liquid effluents
generated in the refinery complex as well as PP complex
Gaseous Effluents - Atmospheric emissions related to the proposed facilities emanate
mainly from the stacks located in various process units and in the CPP.
SOx Control - In order to control SOx emissions according to NEMA guidelines,
it is proposed to use internal fuel oil with maximum sulphur of 0.5 wt%.
NOx Control - Low NOx burners have been recommended to reduce NOx
emission from all furnaces.
In addition a Plant Safety and Environment Cell consisting of qualified and
experienced technical personnel from the relevant fields will be in place to
ensure effective operation of all pollution control measures and suggest further
improvements where necessary.
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 1 of 2
Recommendations for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
SECTION 13.0
RECOMMENDATIONS
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. B
Page 2 of 2
Recommendations for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
13.0 RECOMMENDATIONS
Based on the analysis detailed out in the previous sections, the following is concluded:
The project having capital cost of Rs 4515 Crores (with accuracy of ±20% and valid as of
Oct 2021) can achieve viability with a return of 18.24% post tax based on the product
prices.
Setting of PP Project, for which NRL has land in possession as well as its good
connectivity to the existing refinery for feed and utilities, proximity to highways and ease of
getting environmental clearance, will meet the petrochemical demand of north eastern
region which is expected to grow in future.
Also Polypropylene complex will accelerate development of downstream petrochemicals
industry for polymer processing like packaging, fibre and filament, automotive, health care
and personal care.
The development of clusters of small and medium industrial units associated with
petrochemical industry will not only improve the general infrastructure by improvement of
roads, education and health facilities but also generate tremendous employment
opportunities. This project will thereby improve the economic status of the people in the
area surrounding the Refinery/ petrochemical hub.
The Economic analysis portrays a robust and attractive rate of return for refinery
configuration with PP, this is primarily due to the high value polymer product. Hence it is
recommended that since the PP project results in a significant return on investment, same
can be taken forward for implementation.
Considering the high IRR, the pre-project activities may be taken up on immediate basis
after having internal approval within NRL. This will give an opportunity to NRL to almost
match PP Project with the implementation of existing NREP project and realise the full
potential of PFCCU from day one, ensuring high profitability.
B
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 1
Annexure-1 for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
ANNEXURE-1
OVERALL PLOT PLAN
12.5M WIDE ROAD 12.5M WIDE ROAD
386.2
214.5
60.0
287.8
539.0
55.065.1
74.4
61.5
157.7
221.0
400.5
BOUNDARY WALL
BOUNDARY WALL
GREEN BELTBOUNDARY WALL
(2+1)
COOL
ING
TOWE
R
15
FLARE
15
41-TT-121A
E - 859.15
N -1092.50
RCC FIREWALL
EXISTING EARTHEN DYKE58.0
19.1
RCC DYKE WALL
INCINERATOR
NOTE 7
9.7
S
8400 SQM
55.0177.081.088.022.065.0
15.0
1.015.0
T
3300 SQM
RCC DYKE
Ht. = 0.6m63.0
9.0
21.0
71.0
9.0
8.0
17.015.510.5
8.0
9.0 9.0
18.019.0
RCC DYKE
Ht. = 0.6m
Ht. = 0.6m
PFCC FEED
Ø42.0 Ø26.0
DCU FEED8.5
21.0
RCC DYKE
8.0
RCC DYKE
Ht. = 0.6m
R10 R10R10
27.0
9.7
BM19
R10 R10
CATCHER
OIL
OIL CATCHER
NOTE 41
35.0
14.0
4.0
8.01.0
E 5
08
.0
00
E 5
96
.5
00
E 6
92
.0
00
1S72-TT-2805Ø45.0 1S72-TT-2803
1S72-TT-2002
RPTU FEED
WAREHOUSE - 1
ROAD NO-12
21.0
10.0
P5
WF-1
A
B
9M W
IDE R
OAD
9M W
IDE R
OAD
9M W
IDE R
OAD
9M W
IDE R
OAD
1347.7
SUMP
1
2
3
CWPS
PP UNIT
(29000 SQM)PP WARE HOUSE
(20X10 )GATE HOUSE
(25X25)
WARE HOUSE(CHEMICAL,SPARE)
(60X3
0)CW
TP SS
(40X3
0)CW
TP SR
R
ADMIN BUILDING
UNLOADING BAYLOADING/
FUTURE AREA
30.0
(60X3
0)PP
SS(40
X30)
PP SR
R
TRUCK PARKINGFIRE STATION
172.0
35.011.0
30.0 20.0 141.015.0 20.515.0 30.0
(40X60)CONTROL
ROOM
ENTRY
EXIT
12.5(20X10 )
GATE HOUSE
15.0
22.3
CANTEEN
POLYMER LABBAGGING
24.0
14.5
25.0
BLAST RESISTANT
16.0
23.0140.0
14.5
19.0
15.0 20.0 15.0 15.0
10.0
CONSTRUCTION FACILITY
25.0
40.0
15.0
N
KEY PLAN
THIS DRAWING
Th
e d
ra
win
g, d
esig
n a
nd
d
eta
ils g
ive
n o
n th
is fo
rm
at a
re
th
e p
ro
pe
rty o
f E
NG
IN
EE
RS
IN
DIA
L
IM
IT
ED
. T
he
y a
re
m
ere
ly lo
an
ed
o
n th
e b
orro
we
r's e
xp
re
ss a
gre
em
en
t th
at
th
ey w
ill n
ot b
e re
pro
du
ce
d, co
pie
d, e
xh
ib
ite
d o
r u
se
d, e
xce
pt in
th
e lim
ite
d w
ay p
erm
itte
d b
y a
w
ritte
n co
nse
nt g
ive
n b
y th
e le
nd
er to
th
e b
orro
we
r fo
r th
e in
te
nd
ed
u
se
.
3-1641-0500 REV.2 A0-1189 x 841
REFERENCE DRAWING TITLEREF. DWG. NO.
PEM/PCAPPDCHKDREVISIONSDATEREV.
SCALE REV.DWG. NO.DEPT.DIVN.UNITJOB NO.
BY
NUMALIGARH REFINERY LIMITED
100.0
290.0
60.0
25.0
25.0
30.029.0
9.0
30.0
15.0
18.0
20.0
20.0
30.0
84.0
45.0
7.5
7.5
7.5
60.050.0
20.0
25.0
PARKING
(INCL.
OP. CA
BIN)
BLAST
RESIS
TANT
ENTRYEXIT
SATELLITE
12.5
PUMP HOUSE 30.0mX8.0m
8.0
22.0
17.0DG SHED
5.0
PROP
YLEN
EPR
OPYL
ENE
PROP
YLEN
E24
.0
16.0
74.0
CONST. FACILITIES
(15x15)
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 1
Annexure-2 for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
ANNEXURE-2
SCHEMATIC FLOW DIAGRAM
"THIS DOCUMENT IS THE PROPERTY OF LUMMUS NOVOLEN TECHNOLOGY GMBH (LUMMUS). IT CONTAINS CONFIDENTIAL
INFORMATION OWNED OR CONTROLLED BY LUMMUS. THIS DOCUMENT MAY NOT BE PROVIDED TO ANY THIRD PARTY, NOR
MAY BE IT USED FOR ANY OTHER PURPOSE, EXCEPT AS SPECIFICALLY PERMITTED IN YOUR COMPANY'S AGREEMENT
WITH LUMMUS. IN NO EVENT MAY IT BE USED FOR ANY WORK NOT PERFORMED ON THE LUMMUS LICENSED PROCESS OF
THAT AGREEMENT. REPRODUCTION IN WHOLE OR IN PART FOR ANY PURPOSE OTHER THAN WORK PERFORMED ON
SUCH LUMMUS LICENSED PROCESS IS FORBIDDEN EXCEPT BY EXPRESS WRITTEN PERMISSION OF LUMMUS."
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 1 of 4
Annexure-3 for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
ANNEXURE-3
EQUIPMENT LIST
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 2 of 4
Annexure-3 for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
MAJOR EQUIPMENT LIST
Sl.no. Description
Treaters
1 Propylene Treater
2 Propylene Treater
3 Hydrogen Treater
4 Hydrogen Dryer
5 Propylene Treater
Vessels,Tanks,Drums
1 HP Nitrogen Buffer Vessel
2 Regeneration Recycle N2 KO Drum
3 Tea Holding Tank
4 Tea Vent Pot
5 Waste White Oil Tank
6 Silane Holding Tank
7 Additive Feed Hopper Vent Pot
8 Catalyst Preparation Vessel
9 Catalyst Metering Vessel
10 Catalyst Vent Pot
11 RG Compressor Suction Drum
12 Powder Collector
13 Flare K.O Drum
14 Degassing Vessel
15 Chase Gas Buffer Vessel
16 Phase Separator
17 Condensate Drum
18 Dry Flare K.O.Drum
Silo
1 Purge Silo
2 Pellet Blending Silos
3 Bagging Silo
Cyclone
1 RG Cyclone
2 Shutdown Cyclone
3 Carrier Gas Cyclone
Reactor
1 Polymerisation Reactor
Exchanger
1 Hydrogen Pre-heater
2 Hydrogen Cooler
3 Regeneration Recycle N2 Heater
4 Regeneration Recycle N2 Cooler 1
5 Regeneration Recycle N2 Cooler 2
6 RG Condenser
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 3 of 4
Annexure-3 for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Sl.no. Description
7 Carrier Gas Cooler
8 Extruder Off Gas Condenser
9 Vent Condenser
10 Hydrogen Preheater
11 Hydrogen Cooler
12 Regeneration Recycle N2 Heater
13 Regeneration Recycle N2 Cooler 1
14 Regeneration Recycle N2 Cooler 2
15 RG Condenser
16 Carrier Gas Cooler
17 Extruder Off Gas Condenser
Pump
1 Tea Metering Pump
2 White Oil Drum Pump
3 Isopropanol Drum Pump
4 Silane Metering Pump
5 Silane Drum Pump
6 Peroxide Metering Pump
7 Catalyst Suspension Metering Pump
8 White Oil Drum Pump
9 Recycle Pump
10 Condensate Pump
11 Waste Water Pump
Compressor/Blower
1 Regeneration Recycle N2 Blower
2 RG Compressor
3 Hydrogen Compressor
4 Nitrogen Compressor
5 Carrier Gas Compressor
Agitator
1 Waste Oil Oil Tank Agitator
2 Catalyst Preparation Vessel Agitaor
3 Catalyst Metering Vessel Agitaor
Template No. 5-0000-0001-T2 Rev. 2/ 28.11.2014 Copyrights EIL – All rights reserved
Document No.
B394-RP-79-41-0001
Rev. No. A
Page 4 of 4
Annexure-3 for DFR
Poly Propylene Unit of Numaligarh Refinery
Expansion Project (NREP)
NRL
Sl.no. Description
4 Polymerisation Reactor Agitator
Packages
1 Solid Additive Package
2 Bag Additive Discharge and Feeding System
3 Talcum/Silica Additive Discharge and Feeding
System
4 GMS Additive Discharge & Feeding system
5 Extrusion Package/ Extruder
6 Purge gas Recovery Unit
7 Extruder Vacuum Unit
8 Pellet Pneumatic Conveying System
9 Bagging Line
10 Peroxide Dosing skid