Transcript of BUS631 PROJECT MANAGEMENT ASSESSMENT OPENING OF NEW BAKERY PROJECT Sponsor: -Rammy john
Pragnesh patel
Rajvir singh
Himanshu wadhwa
Executive SummeryIn This Assignment we have given the detail about theour project that is opening new bakery in Mt.Eden Auckland and for that we have given brief project charter in that we have projected time period for theproject plan and we give the summery of the project budget and brief about project stake holder. While inthe project plan we have covered the work break down structure of the project plan, detail task list, and grant chart. We have also covered the critical path for the project and set the detail about budget of the project and detail of the human resource. In the last of our project plan we have covered the possiblerisk factor and impact of that factor.
Project Charter
Project Manager: - pragnesh patel
Sponsor: - Rammy john Date: October 23, 2014
Project Title: Real Bakery (New Bakery at Mount Eden)
Project Purpose:
2
Our project purpose is to make finest bakery in theAuckland which have all types of modern machinery andwith help of that Real bakery can make best qualityof bread and other bakery product, and making of thisbakery is helpful to stake holder for new knowledgeof the bakery. With this bakery project owner alsoget good returns from the market. This project willbe completed in nine months and after that bakeryoperation will be started.
Objective
Real Bakery will started with new baking product likevarious types of bread, muffins, and scones and cakesand other bakery items. We believe in service to ourcustomers with the advanced technologies and possibleproviding new state-of-the-art Bakery Productionlines from "product make-up" to "finished packaging."We Building on our customers' successes by adding thebenefits of advanced robotics and other leading-edgetechnology to the proven expertise of ABI in theengineering and manufacture of bakery automationequipment. Helping our customers to become even moresuccessful by:
Cultivating qualityDecreasing wasteIncreasing productivityIntroducing competitive advantagesEnabling product line diversification
We will customize a multi-station Point of SalesSystem with new features such as touch-screens,automatic ordering and high speed credit cardreaders. The system will automate core business
3
functions by managing inventory, ordering supplies,managing labor, and generating financial reports. ThePOS system must comprise of a number of addedfunctionality (e.g. customer order history and avarious language option) that improves the user andcustomer experience and makes the system more robust.
Summery milestone schedule
Project milestone Target date
Project start 01/01/2015
Complete building for bakery 15/06/2015
Installation of electricity andplumbing work
30/07/2015
Installation of new bakery equipment
10/08/2015
New computers and new software install
20/08/2015
Remove barrier related with extra work
30/08/2015
Project complete 10/09/2015
Project stake holder analysis
Name Role Responsibilities
Rammy john Project sponsor Provide funding
4
to the project.Khushbu Thakkar Project head Checking the
project progress and communicationbetween owner andproject team.
Pragnesh patel Project manager Over all look after the project.
Himanshu wadhwa ,Rajvir Singh
Director of purchasing
Maintaining the human resource and purchasing the materials forthe project.
Sing off: - ………………………………….
Comment:- ………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………
Project approval requirement:-
Success of the real bakery project will be leadingbread provider bakery in Auckland region. Realbakery, which is owned by the rammy john, completedthe construction of a state-of-the-art bakery plantin mount Eden, Auckland, in 10/09/2015. The realbakery facility produces breads, rolls and stuffingto meet the growing demand for Pepperidge Farm freshbaked goods in Auckland.
Assigned project manager, responsibilities and authority level:-
5
Pepperidge Farm awarded mount wellington-basedConstruction Company the contract to manage theconstruction of the facility. All-in Builders Companywill responsible for supervise all areas of bakeryconstruction, it including electrical and plumbing,worksite development, utility installation andmechanical development.APV bakers are responsible for the task of designingand set up of machinery for the bakery productionlines. All-in engineering and construction firm, TheFacility Group will provided guidance regardingplanning, programming and budgeting for the Bakeryproject. Its schedule included the evaluation andspecification of all process and packaging equipmentfor three new production lines and one relocatedproduction line that produces a variety of bakedbread products
Name and authority of the sponsor:-The project sponsor mr.Rammy John, all resources willbe provide by project sponsor. This project charter formally authorizes the new bakery development and implementing new machinery and new technology for Real bakery. Project plan developed and submitted to the project sponsor approval. The project will include scope, statement, Schedule; cost estimated budget and provision for scope, resource, schedule, communication, quality, risk, procurement, and stake holder management as well as project control.
High-level requirements:-All the equipment and tools are tested beforeoperating the bakery operation, so there will be no
6
problem during the operation time, all the computingand software should be installed in the bakery withinone month of operation.
High level project description:-Real bakery will be ready in nine month of durationand production will be start by September. In bakeryconstruction and machinery will be ready by Augustand then interior design will be ready and completedand that is done by the JJ designing company and allover operation is supervise by project manager.Finely project completed by October month and thenhand over to head baker.
High-level riskThe following risk are all the necessary license should be taken from the city council, and all the work should be completed within the time limit.
Summery budget
Project Components Project costConstruction material $90,000Human resources $70,000Bakery equipment $50,000Hardware $ software $20,000
Sponsor Acceptance:-
………………………………………………………………………Date:- ……………………
7
Project plan
Work Break down Structure
Detail Task ListTaskId
Task Name Task Descriptio
Task Durati
Task Predecess
Responsible Person
Task Budge
8
InternalConstruct
Foundation
Executive
Installation of
RuffElectric
ElectricConstruct
HVAC
Plumbing
Testing &Repairing
PlumbingSetup
RuffPlumbing
FloorPreparati
SteelConstruct
Steelbean &Column
Licences
FSPOff the
FHR 1974
Food Act1981
Purchasing of thebakery
ExternalWork
Licencefor
Budgeting
Testing &Cleaning
of
Setup ofElectric& Drain
Instalment of
Purchasing of
Computers
Installation of
computers
Hiring ofthe staff
Staffing
Employment
Training
SelectingSuppliers
Planning
Bakery
StandardRecepies
Project
n on ors t1.1 Internal
construction
Starting of projectand construction of internal area
23 rajvir $15000
1.1.1
Electrical Construction
Starting electric construction
9 1.1 himanshu $4000
1.1.2
Rough Electrical Construction
Map and fitting ofthe electric setup
5 1.1.1 himanshu $2000
1.1.3
Installation of Equipment
Set up of the equipment and machinery
8 1.1.2 pragnesh $1000
1.1.4
HVAC Setup
Connectionof HVAC system
7 1.1.3 khusbu $3000
1.2 Foundation
Basic foundationof the building
22 1.1.4 rajvir $1500
1.2.1
Executive Checking and preparing foundation
7 1.2 Rajvir $700
1.2.2
Floor Plan
Starting of the floor construction
25 1.2.1 Khushbu $700
1.2.3
Steel Construction
Starting of the steel construction
4 1.2.2 Rajvir $1000
1.2.4
Steel Beam & Colum
Construction of building
7 1.2.3 khushbu $20000
9
Construction
forma
1.3 Plumbing Starting of plumbing
7 1.2.4 Rajvir $12000
1.3.1
Rough Plumbing
Set up ofthe pipeline
7 1.3 Himanshu $9000
1.3.2
Plumbing &Set up
Set up andfixing of plumbing
4 1.3.1 rajvir $5000
1.3.3
Testing and Repairing
Check all the setup,testing and repairing
10 1.3.2 khusbu $4000
2.1.1
Licences Application of licenses
14 1.3.3 Khusbu $500
2.1.2
FHR1974 Application and certification of 1974
15 2.1.1 Khusbu $500
2.1.3
FSP of the Peg
Application and certificate of FSP
15 2.1.2 Pragnesh $500
2.1.4
Food act 1981
Application and certificate of food act 1981
15 2.1.3 khushbu $500
2.1.5
Licencefor
Construction
Application for construction license
20 2.1.4 pragnesh $500
3.1.1
ExternalWork
Starting of external work
20 2.1.5 himanshu $2000
3.1.2
Purchasing of thebakery
Equipment
Buying of the bakeryequipment
7 3.1.1 pragnesh $8000
10
3.1.3
Instalment of
Machinery
Setup of the machinery
5 3.1.2 rajvir $2000
3.1.4
Setup ofElectric& Drainline
Setup of electricalline and drainage line
10 3.1.3 rajvir $2000
3.1.5
Testing &Cleaning
ofMachinery
Checking of the equipment and cleaning of the area
4 3.1.4 Himanshu $2000
3.2.1
Purchasing of
Computersand POS
Buying newcomputers and software
7 3.1.5 Pragnesh $7000
3.2.2
Installation of
computersand POS
Software installation
5 3.2.1 Khusbu $2000
4.1.1
Staffing Find out new staff
10 3.2.2 Khusbu $5000
4.1.2
Employment
Consultancy
Consult with recruitment agencies
10 4.1.1 Khushbu $4000
4.1.3
Hiring ofthe staff
Selecting of employee and hire
7 4.1.2 Khusbbu $10000
4.1.4
TrainingOf the staff
Training for the standard operating procedure
4 4.1.3 khushbu $0000
5.1.1
planning Planning of the constructi
10 4.1.4 pragnesh $000
11
on and allthe
5.1.2
Selectingsupplier
Selecting supplier for raw materials
7 5.1.1 pragnesh $000
5.1.3
Budgeting Make the budget forthe project
4 5.1.2 Khusbu,pragnesh,rajvir,himanshu
$000
5.1.4
StandardRecipes
With head chef set up for standard recipe
4 5.1.3 khushbu $1000
5.1.5
BakeryMenu
Set up forbakery menu
2 5.1.4 khushbu $700
Gantt chart
12
BudgetingProject Opening new bakery Internal construction CostTask Id Task Name Cost1.1 Internal construction $300001.1.1 Electrical Construction $8000
14
1.1.2 Rough Electrical Construction
$4000
1.1.3 Installation of Equipment
$2000
1.1.4 HVAC Setup $60001.3 Plumbing $30001.3.1 Rough Plumbing $15001.3.2 Plumbing & Set up $15001.3.3 Testing and Repairing $2000
Total $58000Foundation cost1.2 Foundation $200001.2.1 Executive $120001.2.2 Floor Plan $90001.2.3 Steel Construction $50001.2.4 Steel Beam & Colum
Construction$4000
Total $50000
Legal licencecost2.1.1 Licences $5002.1.2 FHR1974 $5002.1.3 FSP of the Peg $5002.1.4 Food act 1981 $5002.1.5 Licence for Construction $500
Total $2500
External cost3.1.1 External Work $4000
3.1.2 Purchasing of the bakery $16000
15
Equipment
3.1.3 Instalment of Machinery $4000
3.1.4 Setup of Electric &Drain line
$4000
3.1.5 Testing & Cleaning ofMachinery
$4000
3.2.1 Purchasing of Computersand POS
$14000
3.2.2 Installation ofcomputers and POS
$4000
Total $50000Staffing cost4.1.1 Staffing $20000
4.1.2 Employment Consultancy $8000
4.1.3 Hiring of the staff $10000
4.1.4 TrainingOf the staff
0000
Total $38000Extra cost for business planning and menu set up5.1.1 Planning 00005.1.2 Selecting supplier 00005.1.3 Budgeting 00005.1.4 Standard Recipes $5000
5.1.5 Bakery Menu $1000
Total $6000Total Project
Cost$22150
0
16
Human Resource MatrixTaskId
Task Name Khushbu Rajvir Himanshu Pragnesh
1.1 Internal construction
1.1.1
Electrical Construction
1.1.2
Rough Electrical Construction
1.1.3
Installation of Equipment
1.1.4
HVAC Setup
1.2 Foundation
1.2.1
Executive
1.2.2
Floor Plan
1.2.3
Steel Construction
1.2.4
Steel Beam & Colum Construction
1.3 Plumbing
1.3.1
Rough Plumbing
1.3.2
Plumbing &Set up
17
1.3.3
Testing andRepairing
2.1.1
Licences
2.1.2
FHR1974
2.1.3
FSP of the Peg
2.1.4
Food act 1981
2.1.5
Licence forConstructio
n
3.1.1
ExternalWork
3.1.2
Purchasingof thebakery
Equipment
3.1.3
Instalmentof
Machinery
3.1.4
Setup ofElectric &Drain line
3.1.5
Testing &Cleaning ofMachinery
3.2.1
Purchasingof
Computersand POS
3.2.2
Installation of
computersand POS
18
4.1.1
Staffing
4.1.2
EmploymentConsultancy
4.1.3
Hiring ofthe staff
4.1.4
TrainingOf the staff
5.1.1
planning
5.1.2
Selectingsupplier
5.1.3
Budgeting
5.1.4
StandardRecipes
5.1.5
Bakery Menu
Risk Management matrixSr.no
Risk Description impact Probability
Risk rating
1 Cost Forecast are inaccurate High law 0.122 Inaccurate changes in
priorityLaw law 0.02
3 Stakeholder fail to supportproject
High law 0.12
4 Delays in required toinfrastructure
High high 0.28
5 Lack of management control High law 0.126 Resource not available on
timeHigh law 0.12
7 Authorities are unclear Law law 0.028 If any activity missing from
project planLaw law 0.02
9 Short fall of resource Law high 0.04
19
10 Not fulfil governmentrequirements
Law law 0.02
Human resource management:-
Project manager:- pragnesh patel
Duties and responsibilities of the project manager isto look after of all over the project. Projectmanager is responsible to guide the other team memberfor the project. Responsible for the budgeting of theproject.
Project Head:- Khusbu Thakkar
Duties and responsibilities of project head is tokeep communicating with team member, and owner andmake update to the project manager issuing of thelicence and other documentation which are relatedwith project
Human Resource Manager- Himanshu wadhwa, Rajvir singh
Duty of the human resource managers is providing thestaffing during the project and look after theproject of the time period and allocation of theresource.
Thank you