Bihar State Highways II Project - Additional Financing
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of Bihar State Highways II Project - Additional Financing
Social Monitoring Report
This First External Social Monitoring Report has been submitted to ADB by Ramesh Swarankar for Bihar State Roads Development Corporation Limited and the Asian Development Bank and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.
This external social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 41629-013 / 44425-013 October 2018
IND: Bihar State Highways II Project Bihar State Highways II Project - Additional Financing
Submitted by
Ramesh Swarankar
1
Loans 2663 & 2894-IND: Bihar State Highways Project
External Social Monitoring Report
Prepared by
Ramesh Swarankar
Social Safeguards Specialist (External Monitor)
2
ABBREVIATIONS
ADB Asian Development Bank
AH Affected Household
BSHP Bihar State Highways Project
BSRDC Bihar State Road Development Corporation Limited
CAP Corrective Action Plan
CSC Construction Supervision Consultants
DDR Due Diligence Report
DP Displaced Person
EA Executing Agency
HH Household
IA Implementing Agency
INRM India Resident Mission
IPs Indigenous Peoples
IR Involuntary Resettlement
LARR Land Acquisition, Rehabilitation and Resettlement
PIU Project Implementation Unit
RoW Right of Way
RP Resettlement Plan
SH State Highways
SPS Safeguard Policy Statement
SSC Social Safeguards Consultant
SU Safeguard Unit
TA Technical Assistance
3
1. Introduction 8 1.1. Scope and Objectives of External Monitoring 10 1.1.1. Objectives 10
1.1.2. Scope of Works 10 1.1.3. Detailed Tasks and Expected Output 11 1.1.4. Approach and Methodology 11
2. Resettlement Principles of Project 13 2.1. Entitlement Matrix 13
2.2. Resettlement Impacts 20 2.3. Actual Impacts during Implementation 20
3. Institutional Arrangements for Resettlement Plan
Implementation 22
3.1. Staff of PIUs 23 3.2. NGO staff 23
3.3. Capacity Development 24 4. RP Implementation, Compensation and Assistance 25
4.1. Identification and Verification of Affected Households 25 4.2. Micro-plan Preparation 25
4.3. Identity Card Preparation and Distribution 25 4.4. Opening of Bank Account 28 4.5. Documents Requirements 28
5. Land Acquisition 29 5.1. Number of Structures Impacted 30
5.2. Status of Compensation of Structures 32 5.3. Assistance Amount Disbursement 36
5.4. Community Property Resources 37
5.5. Vocational Training Programs 39 6. Disclosure, Consultation and Grievance Redress 41
6.1. Disclosure and Distribution of Entitlement 41 6.2. Consultations held with DPs and other Stakeholders 41 6.3. Grievance Redressal Mechanism 42
6.4. HIV/AIDS Awareness 42 7. Monitoring and Reporting 45
7.1. Status of Corrective Action Plan 45
8. Conclusions and Recommendations 51 8.1. Additional Action Plan 51
Table of Contents
Content Page No.
Executive Summary 5
Annex 1. Checklist for Consultation/FGD with DPs on status of LARR activities 53 Annex 2. Details of Consultation held with Affected Households and Stakeholders 54
Annex 3. Disbursement of Assistance Amount to Titled and Non-titled HHs 59
Annex 4. Picture of Site Visits 63
4
List of Tables
Table
Page No.
Table 1.1. Details of BSHP Roads
8
Table 2.1. Entitlement Matrix
13 Table 2.2. ADB approved Resettlement Plans 20
Table 2.3. Actual Project Impacts 21 Table 3.1. Details of PIU Staff 23
Table 3.2. Staff of Implementing NGOs 24
Table 4.1. Status of Micro-Plan and Identity Cards 27 Table 5.1. Status of Land Acquisition 29
Table 5.2. Number of Structures’ Impacted 31 Table 5.3. Status of Compensation for Structures of NTH 33 Table 5.4. Status of Compensation Disbursed for Land Acquisition 35 Table 5.5. Status of CPR Structures 38
Table 5.6. Details of Vocational Training Programs 40
Table 6.1. Datils of RP Disclosure 41
Table 6.2. Grievance Redressal Mechanism 43
Table 6.3. Status of Pending Grievances 43
Table 6.4. Details of HIV/AIDS Program 44 Table 7.1. Monitoring and Reporting 45 Table 7.2. Corrective Action Plan 46
Table 8.1. Additional Action Plan 52
Map 1. Project Roads under BSHP II and AF
9
Chart 1. Institutional Arrangements, BSRDC 22
Box 1. Delay in Land Acquisition 30
Box 2. LA under Old Act 1894 and LARR, 2013 30
Box 3. Relocation sites for Physically Displaced Persons 32
Box 4. Rehabilitation of Non-Titled DPs 33
Box 5. Project Perception and Compensation Disbursement 36
Box 6. Requirement of Rituals for Relocating Deities 39
5
Executive Summary
E.1. Introduction
1.1. ADB funded Bihar State Highways Project-II (Loan 2663) and the Additional Financing
(Loan 2894) include works related to widening and strengthening of a total of 629.447 km of
state highways (SHs) identified under the Bihar State Highway Development Program. Total 9
SHs are passing through 13 districts across the State. 1.2. Currently, the external social monitoring (under the ADB TA -8569 REG) is being
undertaken with an objective of assessing the progress and performance of RPs, CAPs and
DDRs implementation and their documentation in line with ADB’s SPS, 2009. Accordingly, the
preliminary and first external social monitoring report is prepared, which covers the period from
beginning of LARR activities under BSHP to November 2016. E.2. Magnitude of Impacts
2.1. The impacts on the land and assets of affected households reported in the ADB approved
RPs was more than the actual impacts evidenced during the implementation. The RPs reported
a total of 2073 acre land acquisition requirements, while 1813.90 acre was the actual land
acquired for different SHs until November 2016. The remaining minor land acquisition was in
process in SHs 78,81, 87, 88, 90, and 91. Its quantum was not known due to efforts being made
by the EA to avoid some impacts and adjust alignments where possible. Similarly, 1834
structures and 13,165 structures of THs and NTHs affected as per RPs were more compared
to 297 and 3346 structures in the same order actually impacted. Further, a total of 19,737
affected HHs (13,165 TH and 6572 NTH) comprising of 1,30,228 DPs reported in the RPs were
more than double compared to actual 61,618 DPs (45,633 TH and 15,985 NTH) from 13,363
HHs (9983 TH and 3380 NTH) identified so far. The number of actually impacted 5431
vulnerable HHs (titled 3634 and non-titled 1797) during the implementation until November 2016
were double than the 2707 HHs reported in the RPs. Likewise, impacts were reduced to total
764 community property resources (CPRs) of different types during actual implementation. The
number of affected HHs and DPs will be updated once their identification and enumeration in
the remaining SHs such as in SH 81 and SH 87 are completed.
E.3. Implementation of LARR Activities
3.1. The implementation of LARR activities under the RPs requires several activities to be
performed by the EA/IAs. Such activities include conducting consultations with DPs and other
stakeholders, disclosure of entitlement matrix, dissemination of project information,
identification and verification of DPs, preparation of micro-plans (MPs), preparation and
distribution of identity cards (IDs), opening of Bank Accounts of DPs if needed, assist the EA/IAs
in compensation disbursement, coordinate with DPs, EA/IAs and officials of revenue and line
departments, organizing GRC meetings, data collection for monitoring and reporting, etc. At the
field level, along with the PIU officials, NGOs performed major role in carrying out the referred
activities required for RPs implementation. Their work progress during 2012-2014, though not
completed, was assessed to be satisfactory.
6
E.4. Land Acquisition 4.1. Out of total land 1813.90 acre; 1661.60 acre, 143.09 acre and 9.93 acre (in SH 91 only)
land parcels were to be acquired under the earlier LA Act of 1894, new LARR Act of 2013 and
Bihar State Perpetual Lease Policy, 2015 respectively. About 1129 acre (62 %) of total land was
acquired and full compensation paid to the affected titled land owners by November 2016. The
process of LA for remaining land of 692.12acre (38%) was ongoing and its completion was
expected by 31 March 2018. The BSRDC has taken the physical possession of acquired land
for the construction of SHs.
E.5. Impacts on Structures
5.1. Out of a total of 297 structures of titled households impacted, the compensation at the BSR
rate was paid for the 199 structures alongwith the compensation amount of land acquisition and
was pending for remaining 98 structures.
Total 2901 non-titled households were losing their 3346 structures under the project. A sum of
INR 484.99 lakh was disbursed to 2487 HHs and remaining INR 204.14 lakh was expected to
be disbursed to remaining 414 HHs by 30 June 2017.
E.6. Community Property Resources
6.1. Of 764 CPR structures impacted, the progress of construction of CPRs have been very
slow as evidenced by 4.45 percent new structures constructed by 30 November 2016. BSRDC
agreed to follow up with the contractors to complete the construction of maximum CPRs by 31
Dec 2017.
E.7. Disbursement of Assistance Amount
7.1. Based on the assessment of requirements for different types of assistance (livelihood,
shifting, transitional, training, special) to titled and non-titled DPs, BSRDC sanctioned a total of
INR 748.30 lakh for disbursing the assistance amount. Out of the sanctioned amount, a sum of
INR 583.10 lakh was paid to 9360 affected HHs and INR 209.48 lakh to be paid to remaining
3533 HHs. Based on the information available by November 2016, it was estimated that an
additional amount of INR 44.28 Lakh will be required to disburse the enhanced compensation
amount to the DPs as per the New Act, 2013. The EA will pursue with the State Government to
increase the sanctioned amount. Data about remaining (470) HHs could not be confirmed that
will be verified and incorporated during the upcoming visit to project sites (Refer Annex 3).
E.8. Institutional Arrangements
8.1. BSRDC, Govt. of Bihar is the executing agency that established one CPIU at the HQs Patna
and seven PIUs at the district level. BSRDC through PIUs that were assisted by NGOs and R&R
and Gender experts of CSCs have been involved in RPs implementation and monitoring. All the
seven PIUs headed by the DGM (Technical) designated as Resettlement Officer (RO) and
assisted by ARO and support staff were fully staffed. The NGOs, i.e. SPS discontinued working
since March 2014 due to extension of time (EOT) not given by BSRDC was one of the major
impediment in RPs implementation.
7
E.9. Monitoring and Reporting
9.1. The R&R and Gender Experts of CSCs have been submitting the semi-annual and annual
monitoring reports on the implementation of RPs to PIUs for verification and onward transmittal
to BSRDC and then to ADB. Information on the Gender Action Plan and monitoring report on
its implementation required for Additional Financing Loan was not submitted so far.
E.10. Issues and Action Plan
10.1. Non-availability of NGOs for all the SHs, un-updated land records with revenue
department, poor coordination at different levels, weak monitoring, slow progress in land
acquisition and disbursement of compensation and assistance, opposition of DPs for enhanced
compensation, change in affected land category from agriculture to residential/or commercial
for increased land value amount, inefficient grievances redressal mechanism, complaints and
court cases continue to remain the critical issues. In addition, recording and reporting of
consistent data and its management in all the SHs for an overall understanding and timely
monitoring on the safeguard progress and performance are other major challenges. The agreed
CAP and Additional Action Plan are developed to address the existing issues and concerns
(see Table 7.2 and Table 8.1 for details).
8
Bihar State Highways Project (BSHP)
Loan 2663-IND: BSHP-II & Loan 2894-IND: BSHP-II-Additional Financing (AF)
1. Introduction
ADB funded Bihar State Highways Project-II (Loan 2663) and the Additional Financing (Loan
2894) include works related to widening and strengthening of a total of 629.447 km of state
highways (SH) identified under the Bihar State Highway Development Program. Total 9 SHs
are passing through 13 districts across the state with a total ADB loan amount of USD 574.64
million. The Bihar State Road Development Corporation (BSRDC), Government of Bihar has
been implementing BSHP-II and AF to rehabilitate the deteriorated state roads and upgrade
some state roads to provide reliable road transport services and reduce poverty in the long
term. BSHP consists of 629.447 km roads distributed into 9 SHs of various districts as detailed
out in the Table 1 and also indicated in the Map-1.
Table 1.1 Details of BSHP Roads
Sl.
No. SH
No. Name of the Project Road Length
(in km) Districts Covered
1. 78 Bhita -Dhaniyabad, Chandi-Samera 94.200 Patna and Nalanda
2. 81 Sakkadi - Chandi - Sandesh - Sahar- 83.250 Rohtas and Bhojpur
3. 89 Siwan – Chhapiya – Hasanpura –
Rampur – Chandpur – Siswan 33.065 Siwan
4. 90 Mohammadpur - Rajapatti - Mashrakh -
Khaira – Chapra 64.711 Saran and Gopalganj
5. 91 Birpur - Balua - Jadia - Meergunj – Udakishanganj
101.700 Supaul and
Madhepura BSHP II AF
6. 83 Baghi-Barbigha 36.500 Nawada, Shekkpura
and
Nalanda 7. 86 Saraiya – Motipur 28.181 Muzaffarpur
8. 87 Runisaidpur- Bhiswa 67.486 Sitamarhi
9. 88 NH-103 Baruna Bridge-Rasiyari Road 120.354 Samastipur and
Darbhanga Total 629.447
10
1.1. Scope and Objectives of External Monitoring
Under the Bihar State Highway Development Program, the external monitoring assignment
covers the due diligence of social safeguards related to widening and strengthening of a total of
629.447 km of 9 SHs passing through 13 districts across the state. The key responsibility is to
analyse, assess and recommend the corrective measures for implementation of updated RPs
and LARR activities in accordance with the requirements of ADB’s Safeguards Policy
Statement, 2009 and applicable Indian laws. The objectives mainly include the (i) review and
verify the available data and documentations and identify the gaps; (ii) monitor on the process
of LARR as stipulated in the updated RPs and advise on implementation of action
plan/corrective action plan as required; and (iii) assess whether the living standards of DPs have
been restored and/or improved.
1.1.1. Objectives
Under the TA-8569 REG: Improving Safeguard Policy Applications in South Asia Developing
Member Countries (Social Safeguards Specialist) (Project Number 46282-001), ADB intends to
assess the progress and performance of resettlement plans (RPs) implementation ongoing
since 2012. Accordingly, the task was assigned to external social monitor with the following
objectives.
a) Support and build the capacity for implementation of RPs, land acquisition, rehabilitation
and resettlement (LARR) of the Executing and Implementing Agencies (EA/IA) of the
BSHP II;
b) Verify and provide advice for updating of nine Resettlement Plans for nine civil works
packages and the preparation of associated Due Diligence Report (DDR) chapters on
LARR activities already carried out, including Corrective Action Plans (CAP) as required;
c) Support the implementation of the RPs and CAPs according to their terms and in
accordance with the requirements of the ADB’s Safeguards Policy Statement, 2009 and
applicable Indian laws; and
d) Monitor the process of LARR implementation, prepare External Social Monitoring Reports,
propose further corrective actions as required and monitor and advise their
implementation.
1.1.2. Scope of works
a) Participate in an Inception Meeting with ADB and the EA at the India Resident Mission in
Delhi;
b) Review and verify the EA/IA's monitoring information and the progress of LARR as stipulated in the updated RPs, DDRs and CAPs;
c) Assess the effectiveness of the EA/IAs, Construction Supervision Consultants (CSCs) and supporting NGOs in updating the RPs and its implementation requirements, and advise the EA/IAs about required improvements;
d) Monitor and advise the EA/IAs on carrying out full and meaningful consultation on the updated RPs, DDRs and CAPs;
e) Assess whether the objectives of the updated RPs, particularly the restoration and
11
enhancement of living standards of titled and non-titled displaced persons (DPs) have been achieved;
f) Assess whether all compensation and mitigation measures for all the vulnerable and non-
vulnerable titled and non-titled DPs have been implemented in accordance with the requirements of the updated RPs;
g) Review the project's potential impacts on Indigenous Peoples groups and assess whether adequate mitigation measures in accordance with the updated RPs have been provided;
h) Advise the EA/IAs on any social safeguards compliance issues and design corrective actions in cooperation with the EA/IAs and consultation with the affected persons;
i) For each field input hold kick-off and wrap-up meetings with the EA to communicate and
discuss findings and conclusions in detail, seeking a common understanding of the causes
of compliance gaps, if any, and about the resulting required corrective actions;
j) Monitor and assess the implementation of all agreed corrective actions;
k) Carry out a capacity building events for the EA/IAs staff on social safeguards during each field input;
l) Prepare semi-annual External Social Monitoring Reports, with CAPs as necessary, and submit these to the EA/IAs as well as ADB.
1.1.3. Detailed Tasks and Expected Output
a) Monitor the process of LAR implementation by the IAs according to agreed and already established monitoring indicators. Improve the established monitoring indicators if deemed necessary;
b) Carry out verification of internal monitoring information on LARR by the IA through review of documents and field based due diligence with DPs and other relevant stakeholders;
c) Document the implementation of compensation, relocation and livelihood restoration; measures stipulated in the updated RPs and DDRs and assess whether these have been carried out in full;
d) Assess the effectiveness of consultation, participation and grievance redress by reviewing the relevant documentation and consulting the key stakeholders;
e) Prepare detailed corrective action plans to remedy any non-compliance with the updated RPs and DDRs and monitor their implementation; and
f) Undertake site visits and prepare external social monitoring reports
1.1.4. Approach and Methodology
Considering the above objectives and tasks, the approach and methodology followed during
the study are mentioned below.
a) Review of available documents and validation of data;
b) Assessment of RPs implementation status, identification of issues, gaps and reasons thereof;
c) Site visits and meetings/consultations with EA/IAs, CSCs, DPs, NGOs and other stakeholders;
d) Additional agreed action plan/corrective action plan; and e) Advise EA/IAs for implementation of RPs/additional action plan/CAP and comply with
ADB’s SPS, 2009 and applicable national and state laws.
12
External social monitor is assigned the responsibility to assess the status of LARR. The monitor
will continue to support and build the capacity of the EA/IAs, review of the documents, verify the
data, provide advice for the implementation of updated RPs, DDRs, CAPs and Additional Action
Plan in accordance with the ADB SPS, 2009 and applicable Indian and State laws.
The qualitative research techniques were adopted for the collection/verification of data randomly
from the field. The checklist (Annex 1) was used for conducting consultations and focus group
discussion with the available DPs on-site, besides holding unstructured interviews with them
and other stakeholders.
The inception meeting was held on 11 November 2016 at INRM, New Delhi. Various issues
related to the safeguards/LARR related planning, implementation and monitoring persisting in
the BSHP II were raised at length to address them. Of the total three field visits proposed, the
first project field visit for 12 days was carried out during 5-16 December 2016 and another 8
days1
were utilized reviewing the available documents, validation of data and preparation of
monitoring report. The documents, reviewed and verified to the extent possible, include the RPs,
internal monitoring reports, profile of DPs, vulnerability status, project impacts and loss incurred,
micro-plan, identity cards, compensation and assistance amount cheque distribution records,
documentations related to process and procedure followed, monitoring and reporting, etc.
The external monitor completed first field based due diligence with DPs, EA/IAs, Consultants,
Implementing NGOs, Contractors and other stakeholders in December 2016 and the remaining
field and documentation works are proposed to be undertaken in June-July 2017 and Dec 2017.
The work plan will be carried out in close coordination with the Safeguard Unit (SU) and Project
Officer, INRM.
1 Factually collection and compilation of data have taken above three weeks . It was due to verification and updation of huge
data that remained inconsistent and scattered at different sources. It caused delay in submission of First monitoring report.
13
2. Resettlement Principles of Project The ADB has adopted Safeguard Policy Statement (SPS) in 2009 including safeguard
requirements for environment, involuntary resettlement and indigenous people. The objectives
of the Involuntary Resettlement Safeguard policy is to avoid involuntary resettlement wherever
possible; to minimize involuntary resettlement by exploring project and design alternatives; to
enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-
project levels; and to improve the standards of living of the displaced poor and other vulnerable
groups.
2.1. Entitlement Matrix
Compensation for the lost assets to all displaced persons will be paid on the basis of
replacement cost. Resettlement assistance for lost income and livelihoods will be provided to
both title holders and non-title holders. Special resettlement and rehabilitation measures will be
made available to the “Vulnerable Group” comprises of DPs living below poverty line (BPL), SC,
ST, women headed households, the elderly and the disabled. An Entitlement Matrix (Table 2.1)
has been formulated, which recognizes and lists various types of losses resulting out of the
project and specific compensation and resettlement packages.
Table 2.1. Entitlement Matrix
S.
N. Type of Loss Unit of
Entitlement Entitlement Details
Loss of Land 1 Loss of
Agricultural
land
a) Titleholder
b) DPs with
customary
land right
a) Compensation
at replacement
cost
b) Special
provision for
vulnerable group
a) Cash compensation at
replacement cost as
determined according to
BLARRP-2007 or
replacement of land if
available.
b) If the residual plot(s) is (are) not viable, i.e., the DP
becomes a marginal farmer2,
any of the following three
options are to be given to the
DP, subject to his
acceptance:
The DP remains on the plot,
and the compensation and
assistance paid to the tune
of required amount of land to
be acquired.
Compensation and
assistance are to be
provided for the entire plot
including residual part, if the
owner of such land wishes
that his residual plot should
also be acquired by the EA,
2 Marginal farmers are those who own less land than the district minimum land holding.
14
the EA will acquire the
residual plot and pay the
compensation for it.
If DP is from vulnerable
group, compensation for the
entire land by means of land
for land will be provided if DP
wishes so, provided that land
of equal productive value is
available.
c) All fees, stamp duties,
taxes and other charges, as
applicable under the relevant
laws, incurred in the
relocation and rehabilitation
process, are to be borne by
the EA.
2 Loss of
homestead
/commercial
land
a) Titleholder
b) DPs with
customary
land rights
a) Compensation
at replacement
cost
a) Cash compensation at
replacement cost as
determined according to
BLARRP-2007 or
replacement of land if
available.
b) All fees, stamp duties,
taxes and other charges, as
applicable under the relevant
laws, incurred in the
relocation and rehabilitation
process, are to be borne by
the EA.
Loss of structure (residential/commercial/other)
3 Loss of
residential /
commercial
structures
a) Titleholder
b) DPs having
structure with
customary
land right
a) Compensation
at replacement
cost
b) Shifting
assistance
a) Compensation of
structure will be paid at the
replacement cost to be
calculated as per latest
prevailing basic schedules of
rates (BSR) without
depreciation.
b) Shifting assistance of Rs.
10000/3
c) Right to salvage material
from demolished structure
and frontage etc.
d) Rental assistance as per
the prevalent rate in the form
of grant to cover maximum
three month rentals.
3 As required by NPRR 2007.
15
4 Loss of rental
accommodation Tenants a) Rental
Assistance b) Compensation
at replacement
cost
c) Shifting
assistance
a) Rental assistance for both
residential & commercial
tenants as per the prevalent
rate in the form of grant to
cover maximum three month
rentals.
b) Additional structures
erected by tenants will also
be compensated and
deducted from owner’s
compensation amount.
c) Shifting assistance based
on type of house and
household assets.
d) Any advance deposited by
the tenants will be refunded
from owners total
compensation package to
the tenant on submission of
documentary evidences.
e) Right to salvage material
from demolished structure
and frontage etc. erected by
tenants.
Loss of Structure By Non-Titled Holder
5 Loss of
structure
(immovable
assets
constructed by
squatters4
and encroachers)
Squatters
having
structure
a) No
compensation for
land
b) Compensation
for structures.
c) Shifting Assistance
Squatters will be notified and
given one month time to
remove their assets.
b) Compensation for loss of
structure at replacement
cost.
c) Shifting assistance of Rs.
10000/5
d) Right to salvage material
from the demolished
structure.
Encroachers6
having
structure
a) No
compensation for
land
b) Compensation
for structures to
only vulnerable
household
a) Encroachers will be
notified and given one month
time to remove their assets
and harvest their crops.
b) Compensation for
structures at replacement
cost to the vulnerable
households only.
c) Right to salvage materials
from the demolished
structure.
4 Landless person
5 As required by NRRP 2007.
6 Legitimate land holder but encroaching his movable or immovable assets on Government land
16
Loss of trees and crops
6 Loss of Trees a) Land
holders
b) Share-
croppers
c) Lease
holders
Compensation at
Market value to
be computed
with assistance
of horticulture
department
a) Advance notice to DPs to
harvest fruits and remove
trees
b) For fruit bearing trees
compensation at average
fruit production
for next 15 years to be
computed at current market
value
c) For timber trees
compensation at market
cost based on kind of
trees 7 Loss of Crops a) Land
holders
b) Share-
croppers
c) Lease
holders
Compensation at
Market value to
be computed
with assistance
of agriculture
department
a) Advance notice to DPs to
harvest crops
b) In case of standing crops,
cash compensation at
current market cost to be
calculated of mature crops
based on average
production.
Loss of market place structure by titled holder and non-titled holder
8 Impact on
market place/
area on a
minimum of 25
shops/
businesses
Titleholder7
(Owner)
losing
commercial
enterprise in
the market
area
Relocation
Assistance a) Affected enterprises will
be provided with the
following options:
Self managed reconstruction
of shops by the shop
operators with all benefits as
per the entitlement matrix; or
b) Project assisted relocation
option will be provided to
those whose commercial
structure can no longer be
used as a commercial
enterprise as a result of the
Project impact. The
allotment of the shops in the
market complex will be
based on the ownership
status of those affected.
7 In case of affected Title owners who have been carrying out business for 10 or more years – the affected title owners will be allotted a shop
in the market in lieu of compensation. No additional compensation will be paid to them. However, they will be entitled to transitional assistance and shifting assistance as applicable and provided for in the Entitlement Matrix.
17
c) Shifting assistance of Rs.
10000/8
d) Right to salvage material
from demolished structure
at no cost.
Non-
titleholder9
(tenants,
leaseholders
or squatters)
losing
commercial
enterprise in
the market
area
Relocation
Assistance a) Affected enterprises will
be provided with the
following options: Self
managed reconstruction of
shops by the shop operators
with all benefits as per the
entitlement matrix; or
b) Project assisted
relocation option will be
provided to those whose
commercial structure can no
longer be used as a
commercial enterprise as a
result of the Project impact.
The allotment of the shops
in the market complex will
be based on the ownership
status of those affected.
c) Shifting assistance of Rs.
10000/10
d) Right to salvage material
from demolished structure
at no cost.
Loss of Livelihood
Loss of primary
source of
income
Titleholders
losing income
through
business
Rehabilitation
Assistance a) Title holders losing their
business establishment due
to displacement will be
provided with a lump sum
transitional allowance of Rs.
900011
Titleholders
losing income
through
agriculture
Rehabilitation
Assistance a) Training Assistance will
be provided for income
generating vocational
training and skill upgrading
8 As required by NPRR 2007.
9 In case of affected non-title owners, tenants and leaseholders, squatters and vulnerable encroachers, who have
been carrying out business for 10 or more years, will be re-established by creation of market place. The
constructed shops in this market will be provided on rent to them. For first 3 months, no rent will be charged from
these DPs. However, after three months these DPs need to pay to the authority the agreed rent by demand
draft monthly and if he/she wishes to own the same can pay the total amount in agreed installments. The DPs
opting for this option will not be paid cash compensation for their structure loss. 10
As required by NPRR 2007. 11
This rate has been fixed based on the estimates of average income for a period of three months.
options as per DPs choice at
the rate of Rs. 4000 per
affected household to those
households losing their
primary source of income.
b) Employment opportunity
for DPs in the road
construction work, if
available and if so desired by
them.
Non-
titleholders
namely
squatters and
vulnerable
encroachers
losing primary
source of
income
Rehabilitation
Assistance a) Training would be
provided for upgrading of
skills @ Rs. 4000/ - per
family to the DPs.
b) Employment opportunity
for DPs in the road
construction work, if
available and if so desired by
them, or
c) National/State level job
card under National Rural
Employment Guarantee
Program.
Wage earning
employees
indirectly
affected due
to
displacement
of commercial
structure
Rehabilitation
Assistance a) This is valid for persons
indirectly affected due to the
employer having being
displaced, on case-by-case,
based on local wage rates
for three months.
b) Employment opportunity
for DPs in the road
construction work, if
available and if so desired by
them, or
c) National/State level job
card under National Rural
Employment Guarantee
Program.
Agricultural
laborer/share-
cropper
Rehabilitation
Assistance a) Assistance is to be paid as
per the prevailing local wage
rates for 200 days.
b) Employment opportunity
for DPs in the road
construction work,
18
if available and if so desired
by them, Or
d) National/State level job
card under National Rural
Employment Guarantee
Program.
Licensed
mobile
vendors and
kiosk
operators
Rehabilitation
Assistance a) Mobile venders are not
eligible for compensation or
assistance.
b) Those mobile vendors in
possession of a permit from
local authorities to operate in
the affected area will be
treated as kiosks operators.
c) Kiosk operators and
vendors licensed to operate
from affected locations will
be entitled to a one time
lump sum assistance of Rs.
4000/-
Loss of Community Infrastructure/Common Property Resources
10 Loss of
Common
Property
Resources
Community Reconstruction/
Cash
Compensation at
replacement cost
a) Cash compensation at
replacement cost or
reconstruction of the
community structure in
consultation with the
affected community.
Additional Support to Vulnerable Group
11 Additional
Assistance to
vulnerable
groups
Vulnerable
households
including BPL,
SC, ST, WHH,
disabled and
elderly
Special
Assistance a) One time lump sum
assistance of Rs. 10000/ to
vulnerable households.
(This will be paid above and
over the other assistance(s)
as per this framework).
Other Unanticipated Impacts
12 Temporary
impact during
construction
like disruption
of normal
traffic, damage
to adjacent
parcel of land /
assets due to
Community /
Individual Compensation a) The contractor shall bear
the cost of any impact on
structure or land due to
movement of machinery
during construction or
establishment of
construction plant
19
20
movement of
heavy
machinery and
plant site
b) All temporary use of lands
outside proposed RoW to be
through written approval of
the landowner and
contractor.
c) Location of Construction
camps by contractors in
consultation with RCD.
13 Unforeseen
impacts if any Any unanticipated impacts due to the project will be documented
and mitigated based on the spirit of the principle agreed upon in
this framework
2.2. Resettlement Impacts
ADB approved total 9 Resettlement Plans (RPs), comprising of 1 RP for each SH during 2010-
2011. The impact on a total of about 2073 acres of land of 13,165 titled land owners and their
2536 structures were envisaged. In addition, impacts on 1834 structures of 6572 non-title
households were envisaged. Thus, total of 19,737 households (13,165 title holders and 6,572
non-title holders) comprising 1,30,228 persons were estimated to be affected. It includes 2707
households belonging to vulnerable categories. Details of impacts reported in ADB approved
RPs are provided in Table 2.2.
Table 2.2. ADB approved Resettlement Plans
S.No SH Private
Land of
TH
(Acre)
Structu
re
of TH
(No.)
Structur
e
of NTH
(No.)
Affected
Titled
HH (No.)
Affected
Non-
Titled
HH (No.)
No. of
DPs
(TH &
NTH)
Vulnera
ble
HH
1. SH-78 1353.22 288 70 5790 70 56212 70 2. SH-81 269.60 NA 672 1391 858 13147 513 3. SH-89 26.00 22 14 245 195 2073 53 4. SH-90 145.23 733 192 733 3035 21549 505 5. SH-91 42.74 15 432 1280 1728 3008 160
BSHP II- AF 6. SH-83 4.05 219 347 219 398 4457 196 7. SH-86 21.73 120 5 463 5 3707 44 8. SH-87 26.00 22 14 245 195 2073 53 9. SH-88 184.68 1117 88 2799 88 24002 1107
Total 2073.25 2536 1834 13165 6572 130228 2707
2.3. Actual Impacts during Implementation
The impacts on the affected households reported in the approved RPs was more than the actual
impacts evidenced during the implementation. The actual impacts on the HHs and DPs were
reduced significantly. The RPs reported a total of 2073 acre land acquisition (LA) requirements,
while 1813.87 acre was the actual land acquired for different SHs until November 2016. The
remaining minor land acquisition was in process and its quantum was not known due to
avoidance and minor adjustment of alignment to be finalized. The LA was reported to be
pending in some SHs (78, 81, 87, 88, 90, 91) and LA was not involved in SH 89. Similarly, 1834
structures and 13,165 structures of THs and NTHs respectively affected as per RPs were more
21
compared to 297 and 3346 structures in the same order actually impacted. Further, a total of
19,737 affected HHs (13,165 TH and 6572 NTH) comprising of 1,30,228 DPs reported in the
RPs were more than double compared to actual 61,618 DPs (45,633 TH and 15,937 NTH) from
13,362 HHs (9983 TH and 3371 NTH). The number of 5431 vulnerable affected HHs (titled 3634
and non-titled 1797) identified during the implementation until November 2016 were double than
the 2707 HHs reported in the RPs. Likewise, impacts were reduced to total 764 community
property resources (CPRs) of different types during actual implementation. It is inferred that the
impacts reported in the approved RPs was more than the actual impacts on land, structures,
CPRs and number of HHs and DPs verified during the implementation. The number of affected
HHs and DPs will be updated once their identification and enumeration in the remaining SHs
such as in SH 81 and SH 87 are completed. Details are provided at Table 2.3.
Table 2.3. Actual Project Impacts
SH.
no. District Land
Acquisit
ion
(acre)
Structures
Impacted
(no.)
TH (no.) NTH (No.)
TH NTH HH DP Vulnera
ble HH DP Vulnera
ble
78 Patna &
Nalanda
1293.28 60 174 5499 19208 1563 174 696 131
81 Rohtas &
Bhojpur
146.93 0* 678 70 420 18 678 2156** 182
89 Siwan NA NA 41 NA NA NA 40 246 32
90 Saran &
Gopalganj 74.18 153 120 1343 8070 792 146 876 103
91 Supaul &
Madhepaura 42.74 15 432 320 1280 43 432 1728 123
83 Nawada &
Shekhpura
2.16 3 253 117 475 45 253 1518 134
86 Muzaffarpur 16.51 6 158 623 3738 175 158 948 65
87 Sitamari 82.58 0 319 1588 9528 801 319 1914 187
88 Samastipur &
Dharbhanga
155.49 60 1171 423 2914 197 1171 5855 840
Total 1 813.87 297 3 3346 9983 45633 3 3634 3371 1 15937 1797
* The data reported reveals only the impact on land and no impact on structures and hence zero was
mentioned. However, the identification and enumeration of DPs were ongoing and the data will be updated
in due course.
** EA reported a total of 2156 DPs of NTH category that will be further verified.
22
3. Institutional Arrangement for Resettlement Plan Implementation
Bihar State Road Development Corporation (BSRDC), Govt. of Bihar is the executing agency of
the Project. The BSRDC established one Central Project Implementation Unit (CPIU) at the HQs
Patna and seven Project Implementation Units (PIUs), including one PIU for SH 86 & SH 87 and
another PIU for SH 89 & 90 at the sub-project level. Each PIU headed by the Deputy General
Manager (DGM) was assisted by the Manager (technical), who were designated as Resettlement
Officer (RO) and Assistant Resettlement Officer (ARO) respectively. In addition, one Office
Executive and Account Executive were deployed at each PIU level. The DGM at BSRDC HQs is
overall incharge and has been coordinating with the PIUs, Govt/Revenue Deptt, ADB and other
stakeholders. It was noted that the BSRDC through PIUs that were assisted by NGOs have been
involved in RPs implementation and monitoring. The institutional arrangement is shown in Chart
1. In addition, BSRDC hired the services of R&R/Social Development experts including Gender
experts (for AF) of Construction Supervision Consultants (CSCs) to provide technical inputs and
monitor the progress of RPs implementation. The CSCs were visiting the sites intermittently to
facilitate supervision and monitoring process in coordination with PIUs and implementing NGOs
and were submitting the monitoring reports. The Intercontinental Consultants and Technocrats
Private Limited (ICT) and Egis International based in Delhi are the CSCs.
Chart 1. Institutional Arrangements, BSRDC
BSRDC (Govt.
of Bihar)
DGM, CPIU at Patna is
overall Incharge of LA&RR
DGM (PIU) at 7 locations designated as
Resettlement Officer
Technical Manager (ARO)
Construction Supervision Consultants
NGOs
Displaced Persons
23
3.1. Staff of PIUs
As mentioned above, all the seven PIUs headed by the DGM (Technical) designated as
Resettlement Officer (RO) were fully staffed. Each PIU had one Assistant Resettlement Officer
(ARO), except the PIU in SH78 that had two AROs. One retired revenue official for SH 91 and
another official for SH 89 and SH 90 were engaged to assist land acquisition process. All the
PIUs had adequate number of contractual support staff working as office executive and account
executive barring SH-88. BSRDC agreed to fill-up one post of account executive for SH-88 on
contract basis and also deploy the retired revenue officials (Ameen) in SHs where required by
31 May 2017. Details are provided in Table 3.1.
SH District
Table 3.1. Details of PIU staff
PIU Staff Posted (No.) write vacant as applicable
DGM
(Tech)RO
Manager
(Tech) ARO
Office
Executive
Account
Executive
Ameen
(Revenue
Official)
78 Patna & 1 2 1 1 0
Nalanda
81 Rohtas & 1 1 1 1 0
Bhojpur
89 Siwan 1 1 2 1 0
90 Saran &
Gopalganj
Supaul &
91 Madhepura 1 1 2 1 1
83 Nawada & 1 1 2 1 0
Shekhapura
86 Muzaffarpur 1 1 3 1 0
87 Sitamari
88 Samastipur& 1 1 2 0 0
Darbhaga
Total 7 8 13 6 2
3.2. NGO Staff
BSRDC following the state government procedure appointed 4 NGOs for a period of 36 months
to assist implementation of RPs under the Project. They were engaged mostly during 2012. Each
NGO had staff of 7 personnel including Team Leader, R&R Expert, Social Development Expert,
Land Acquisition Expert, Field Coordinator, Computer Operator, and part time Ameen (revenue
official) where required. The staff of NGOs reported to have actively assisted the PIUs in RPs
implementation. The NGOs, namely SPS and Sugam International have discontinued working
from March 2014. It was noted that the NGOs were not given extension of time (EOT) that was
required to complete the implementation of LA, resettlement and rehabilitation activities. BSRDC
24
S.No. Name of NGO SH works
assigned
Date of
mobilization
Staff members
deployed
1 CRADLE, Ranchi SH-89 16.07.2012 7
2 CRADLE, Ranchi SH-90 08.08.2011 7
3 CRADLE, Ranchi SH-86 25.01.2012 7
4 CRADLE, Ranchi SH-87 24.04.2012 7
5 Study Point Samity, Lucknow SH-81 6.05.2011 7
6 Study Point Samity, Lucknow SH-91 16.06.2011 7
7 CMSR, Hyderabad SH-88 3.02.2012 7
8 SUGAM International,
Lucknow
SH-78
10.03.2010
7
9 SUGAM International,
Lucknow
SH-83
10.01.2012
6
62
agreed to issue the EOT for the NGOs by 31 April 2017. Details of NGOs are indicated at Table
3.2.
Table 3.2. Staff of Implementing NGOs
Total
3.3. Capacity Development ADB staff during the review missions have been imparting training on ADB’s safeguard policy,
social and environmental safeguard requirements, resettlement planning, implementation and
monitoring. The staff of the EA/PIUs, NGOs and CSCs have attended such training programs held
at BSRDC, Patna. In addition, the experts of CSCs have organized training activities on land
acquisition and resettlement and rehabilitation. These were focused on hand-holding and field
exposure to the NGOs staff and the AROs at PIU level for RPs implementation.
In addition, NGO staff have undergone classroom learning on the resettlement activities like
identification and verification of DPs, conducting consultations and arranging meetings with DPs
in field, project information dissemination, RP/EM disclosure, explaining documents requirement
to DPs, and undertaking other tasks in the field as required. The training sessions were imparted
by the experts of NGOs and other resource persons on land acquisition, R&R, income restoration
and livelihood, social development, gender, HIV/AIDS and other related subjects. Information
available reveals that total nine and five resource persons from SPS and CRADLE imparted
training to 14 and 11 staff during April-May 2011 and August 2011- August 2012 respectively.
25
4. RP Implementation, Compensation and Assistance
The implementation of RPs require several activities to be performed by the EA/IAs. Such
activities include conducting consultations with DPs and other stakeholders, disclosure of
entitlement matrix, dissemination of project information, identification and verification of DPs,
preparation of micro-plans (MPs), preparation and distribution of identity cards (IDs), opening of
Bank Accounts of DPs if needed, assist the EA/IAs in compensation disbursement, coordinate
with DPs, EA/IAs and officials of revenue and line departments, organizing GRC meetings, data
collection for monitoring and reporting, updation of RPs as required, etc. At the field level, along
with the PIU officials, NGOs performed major role in carrying out the referred activities required
for RPs implementation. Their work progress during 2012-2014, though not completed, was
assessed to be satisfactory. The delays in land acquisition, disbursement of compensation and
assistance amount and procedural lapses such as non-updated RPs pending so far have been
observed.
4.1. Identification and Verification of Affected Households
NGOs appointed for RPs implementation have carried out the identification and verification of
affected households (HHs) under the project. They were completing these tasks for non-titled and
titled HHs, excluding the villages where LA process was either not started or was in the initial
stage. Accordingly, NGOs prepared and updated the list of HHs and was ongoing in some SHs.
As referred earlier, the number of HHs listed was much less when compared with the ADB
approved RPs. It could be due to the excess impacts and more HHs initially reported in the
absence of final design, etc. BSRDC was reminded to update the RPs on priority and agreed to
submit 4 updated RPs for 4 SHs (83, 86, 90 & 91) by 30 June 2017 and remaining 4 updated RPs
for SHs (78,81,87,88) by 31 December 2017.
4.2. Micro Plan Preparation
Based on the updated list and joint verification of affected HHs by the PIU/ NGO and the revenue
department official (in case of land losers only), the micro-plan was prepared for each title and
non-title household under the project. The preparation of micro-plans for the titled households
was initiated by the concerned NGO after their identification and publication of names under land
acquisition notification by the concerned District Collector. The micro-plans were further verified
by the concerned ARO at PIU level. Such verified micro-plans by the PIUs were submitted for
final approval to the BSRDC HQs. The approved micro-plan was mandatory for the disbursement
of compensation and assistance amount to the titled and non-titled households. Micro-plan
consists of detailed information like, name and address of entitled person, type and magnitude of
impacts, value/ rate considered for calculation of compensation amount of land and structure,
type of assistance (shifting, transitional, training, special to vulnerable groups, etc) as per the
entitlement matrix. The status of micro-plan is given at Table 4.1.
4.3. Identity Card Preparation and Distribution
The Identity card (ID) card for each titled and non-titled affected HH was prepared by the
concerned NGO after the finalization of micro-plan by the BSRDC, HQs. ID cards contained
detailed information about the affected HH, entitlement for compensation and assistance, total
amount payable in two instalments to NTHs, etc. Such approved ID cards signed by the RO, PIU
and NGO representative were distributed to the concerned HHs and its copy was kept in the PIU
office for records.
Table 4.1 on the status of ID card (alongwith micro-plan) reveal that the micro plans for a total of
10,203 HHs, including 6882 THs and 3321 NTHs, were prepared that have been approved by the
BSRDC. The remaining micro plan for 3160 were to be prepared. In SH 81, micro-plans were
prepared for 678 NTHs and ID card were prepared and distributed to 568 NTHs and remaining
110 were pending. In SH 88, the number of micro-plans required for THs could not be known
without the land acquisition notification in Darbhanga district. It was also not known in SH 81 and
SH 87.
Upon approval of micro-plans, the ID cards for 6882 titled HHs and 3292 non-titled HHs were
prepared. The ID cards were distributed to 5724 TH and 3055 NTH HHs and such cards were
pending for distribution to 996 TH and 237 NTH HHs. In SH 83 and SH 91, ID cards of 39 non-
titled HHs could not be prepared as they were missing and non-traceable for last almost one year.
BSRDC agreed to distribute these ID cards and prepare and distribute ID cards for remaining
NTH by 31 May 2017. BSRDC also agreed to prepare the micro-plans and distribute ID cards to
titled HHs after the land acquisition notification that was expedited.
26
Table 4.1. Status of Micro-Plan and Identity Cards
S District Total No. of Micro plan and ID cards by 30 November 2016
H micro- plan requireme
Micro-plan requirements
for TH & NTH
Micro-plan prepared
Balance Micro- plans
ID Cards Requireme nt
ID Cards prepared
ID Cards distributed
Balance ID cards
nt TH NTH TH NTH TH NTH TH NTH TH NTH TH NTH TH NTH
78 Patna & 5662 5488 174 5488 174 0 0 5488 174 5488 174 5230 145 258 29
Nalanda
81 Rohtas & 678 TBD 678 TBD 678 0 678 TBD 678 0 568 0 568 0 110
Bhojpur
89 Siwan 48 0 48 0 48 0 0 0 40 0 40 0 40 0 8*
90 Saran & 663 543 120 543 120 0 0 543 113 543 113 419 113 124 0
Gopalganj
91 Supaul & 752 320 432 320 432 0 0 320 403 162 403 0 401 158 2
Madhepura
83 Nawada & 370 117 253 117 253 0 0 117 253 46 253 46 243 71 10
Shekhapura
86 Muzaffarpu 183 29 154 29 154 0 0 29 154 29 154 29 154 0 0
r
87 Sitamari 306 0 306 0 306 0 0 0 306 0 306 0 306 TBD 0
88 Samastipur 1594 423** 1171 423 1171 TBD 0 423 1171 TBD 1171 0 1085 423 86
& Darbhaga
Total 10203*** 6882 3321 6882 3321 TBD 678 6882 3292 6230 3182 5724 3055 996 237
TBD- To be determined
* Not affected due to change of Alignment **Applicable for Samastipur district only
*** Remaining 3160 micro plans were to be prepared and approved
28
4.4. Opening of Bank Account
The accounts of entitled head of affected HHs in the nationalized Bank was required for
depositing the cheque of compensation and assistance amount. Such cheques were handed
over publicly to the entitled displaced persons (titled and non-titled) under the project. NGOs
assisted HHs in opening the Bank accounts and also verified the existing accounts required
for the transactions. 4.5. Documents Requirements
As many as 13 documents of affected HH; namely the land registry, revenue receipt,
genealogy (Vanshawali), Last payment certificate (LPC), No objection certificate (NOC),
Affidavit, PAN card, Voter card, Aadhar card, Bank account, Photo, etc. were mandatory.
These documents were required to be submitted in District Collector’s office prior to the
disbursement of compensation amount for land acquisition to the entitled DPs. The submission
of all the documents was a cumbersome process and took lot of time as a significant number
of land owners did not possess such documents. NGOs have facilitated the task of preparing
documentation, yet the process was ongoing and not completed for several DPs. It was one
of the reasons for the delay in disbursement of compensation amount to titled HHs.
29
5. Land Acquisition Based on the available Monitoring Reports of Consultants and data from all PIUs, Nov
2016, it is inferred that out of total land 1813.90 acre; 1661.60 acre, 143.09 acre and 9.93 acre
(in SH 91 only) land parcels were to be acquired under the earlier LA Act of 1894, new LARR
Act of 2013 and Bihar State Perpetual Lease Policy 2015 respectively as indicated in Table 5.1.
About 1129 acre (62 %) of total land was acquired and full compensation paid to the affected
titled land owners by November 2016. The process of LA for remaining land of 692.12 acre
(38%) was ongoing for completion at an early date. The BSRDC has taken the physical
possession of acquired land for the construction of SHs. Maximum LA 462.46 acre, 92.92 acre,
64. 28 acre and 42.51 acre were pending in SH 78, SH 81, SH 88 and SH 90 respectively. About
20 acre and 9.93 acre were pending in SH 87 and SH 91 respectively. LA was almost completed
in SH 83 and SH 86 and LA was not involved in SH 89. BSRDC reported to have taken the land
acquisition on priority and was expecting completion of maximum LA by 31 March 2018.
Table 5.1. Status of Land Acquisition
SH No.
District
Total private land under acquisition of TH (acre)
Under LA Act of 1894 (acre) BSHP-II
Under LARR Act, 2013 (acre)
Physical Possession taken & Full Compensation paid (In Lakhs)
Balance LA (acre)
78 Patna & Nalanda
1293.29 1201.08 92.91 830.83 462.46
81 Rohtas& Bhojpur
146.93 146.93 0 54.01 92.92
89 Siwan NA NA NA NA NA
90 Saran & Gopalganj
74.18 63.3 10.89 31.67 42.51
91 Supaul & Madhepura
42.75 30.74 2.08 30.32 9.93
BSHP II AF
83 Nawada & Shekhapura
2.17 2.17 0 2.17 0
86 Muzaffarpur 16.51 16.51 0 16.51 0
87 Sitamari 82.58 82.58 0 62.56 20.02
88 Samastipur & Darbhaga
155.49 118.29 37.21 91.21 64.28
Total 1813.9 1661.60 143.09 1129.28 692.12
Source: Monitoring Reports of Consultants and data of 9 PIUs, Nov 2016
30
Box1. Delay in Land Acquisition
Sakkardi Bypass. Under SH 81, the displaced persons, though not opposing
the project, have been demanding compensation at a higher rate. The affected
land registered as agricultural land in the government revenue records is
perceived to be residential or commercial land by the DPs due to change in land
usage. Accordingly, compensation amount was expected to be calculated.
The land records remaining un-updated for several decades, joint ownership of
land, share cropping, dispute in the land ownership, out-migration of locals for
employment, consent required from all the owners, cumbersome revenue
process followed as 13 documents to be submitted in District Collector office
prior to receiving compensation amount, etc are the reasons for delay and slow
land acquisition and disbursement of compensation amount to DPs in SH 81
and other project roads. In the situation of dispute and resentment by the DPs
in SH 81, compensation amount for some DPs of Sakkadi bypass is deposited
by the DLAO with the LARR authority at Patna.
Box 2. LA under old Act 1894 and LARR, 2013
In SH 78, the land was acquired under the old Act as well as the new Act from
the owner of Kanchanpur village. Land acquisition (LA) from 40 owners was
completed and 80 percent compensation amount was disbursed to them in 2012
and remaining 20% was yet to be disbursed. The notification under section 19 of
the new Act was issued for the LA from 36 owners on 8 August 2016 and the
process was ongoing. The owners of impacted land were familiar about receiving
the more compensation amount (upto 4 times of registered value) under the new
Act. While the land losers under the New Act felt better about the more
compensation amount and those parted land under the old Act within the same
village, including those individuals losing under both Acts, were dissatisfied and
repenting for the land lose and less compensation amount received earlier.
5.1. Number of Structures Impacted
Table 5.2. indicates about the status of structures impacted under the project, which were of
different types (permanent, semi-permanent, temporary) and used for commercial, residential,
both and other purposes. Out of a total of 297 structures of titled households impacted, the
compensation at the BSR rate was paid for the 199 structures alongwith the compensation
amount of land acquisition and was pending for remaining 98 structures. The status of
impacted structures and compensation disbursement could not be known for SH 81 and SH
87 where micro-plans have not been prepared until November 2016.
31
No structure was impacted in SH 89 where LA was not required. In case of non-titled
households, out of 3346 structures, compensation was paid for 2810 structures and was
pending for 507 structures. BSRDC was expediting the payment for pending structures that are
expected to be disbursed to titled DPs by 31 March 2018. In case of SH 90, the compensation
could not be disbursed to the owners of 18 structures due to non-submittal of required
documents and impacts on 7 structures of non-titled HHs was avoided. Likewise, the impacts
on 13 structures of non-title HHs were avoided in SH 87. In SH 91, for non-titled HHs, total 432
micro-plans were prepared. Of them, impacts on 10 structures were avoided and the HHs of
remaining 19 structures could not be traced despite several attempts in last one year.
Table 5.2. Number of Structures Impacted
SH District TH NTH Balanc e
NTH
structures
Total No. of Balance Total No. of avoided Struct Structures Structures Structures and ures Compensa Impacted Compensated missing Impact ted ed
78 Patna & 60
Nalanda
81 Rohtas & 0
Bhojpur
BSHP-II
40
0
20 174 145 29 0
0 678 568 110 0
89 Siwan LA not required
41 40 1 0
90 Saran & Gopalganj
153 135 18 120 113 7 25 (including non submittal of documents for 18 structures)
91 Supaul & 15
Madhepura
15
BSHP II AF
0 432 401 2 29 (19 owners
of structures
missing)
83 Nawada & 3 3
Shekhapura
86 Muzaffarpur 6 6
0 253 243
0 158 154
10 17
4 0
87 Sitamari No. of structures TBD due to
micro-plan under progress 319 306 13 13
88 Samastipur& Darbhaga
60 0 60 1171 840 331 0
Total 297 199 98 3346 2810 507 84
32
Box 3. Relocation Sites for Physically Displaced Persons
In SH 78, 60 meter land was acquired considering the need for four lane road in future.
Under the present road work of 2 lane 13 non-title households (NTH) were affected at one
of the location known as Ajawa village. These households (HHs) from schedule caste (SC),
the landless labors, engaged in rearing of cattle owned by others fall into vulnerable group.
About 15 decimal (127.93 sq.m of each HH) land used for residential structure and common
vacant land as cattle shed of these 13 HHs will be impacted in the project road. There was
no infrastructure and civic amenities available in the vicinity to these HHs, even the nearest
primary school was at a distance of 1.5 km. They will be physically displaced and will be
relocated at the project roadside in a government land of about 26 decimal (2 decimal each
family) at a distance of about 250 meter from their existing structures. The land allotted was
more than the land loss and the land will be filled at road level. The allotment of land
proposed in the name of women will make these families as legal owners of land. The land
to be allotted will be more, 26 decimal against the 15 decimal owned, and easy movement
due to project road will provide access to market and employment outside, hospital and
other basic services. These HHs were satisfied with the new location where relocation has
to be initiated at the earliest.
In SH 78, another 8 non-title families were displaced and relocated at a nearby location
(Mauza Mustafapur village). These landless families earning livelihood as labour work were
living in the newly constructed houses. They were facing difficulties due to improper access
to the houses constructed on the bund of a pond at a higher level, insanitation and water
pond outside the residential structures was a source of mosquito breeding causing
diseases. There was no common place for the community and recreation to children.
BSRDC agreed to coordinate with the line departments to resolve their problems on priority
basis.
5.2. Status of compensation of Structures
While the compensation amount of structures and trees were paid alongwith the
compensation of land acquisition to titled HHs by the concerned District Collector, the status
of compensation of structures to non-titled HHs is indicated in Table 5.3.
Information available infers that a total 2901 non-titled households unevenly distributed into
nine SHs were losing their structures under the project. Such data on remaining 445 NTH
will be verified during upcoming project site visit. The impacted structures located within the
ROW were used for residential, commercial and both purposes by the encroachers and
squatters. These were permanent, semi-permanent and temporary types. Based on the
valuation of impacted structures, a total of INR 689.13 lakh was sanctioned by the EA for the
disbursement to non-titled HHs. A sum of INR 484.99 lakh was disbursed to 2487 HHs and
remaining INR 204.14 lakh was not disbursed to 414 HHs until November 2016. It does not
include 29 HHs of SH 91 who were either non-traceable or impacts on their structures were
avoided. BSRDC agreed to disburse compensation of structures to remaining non-titled HHs
by 30 June 2017.
33
5.4. Status of Land Acquisition and Compensation
Table 5.3. Status of Compensation for Structures of NTHs
SH District Total HH
Total Amount
sanctioned (INR in
Lakh)
As of 30 November 2016
Paid Pending
HH (No.) Amount
(INR in Lakh)
HH
(No.) Amount
(INR in Lakh)
BSHP II
78 Patna & Nalanda
174 111.48 145 90.16 29 21.32
81 Rohtas & Bhojpur
678 293 568 152 110 141
89 Siwan 41 8.25 40 7.46 1 0.79
90 Saran & Gopalganj
120 21.96 113 19.15 7 2.81
91 Supaul & Madhepura
403 44 401 35.77 2 8.23
BSHP - II AF
83 Nawada & Shekhapura
168 33.35 165 32.71 3 0.64
86 Muzaffarpur 158 15.02 154 14.2 4 0.82
87 Sitamari 319 31.99 306 31.29 13 0.7
88 Samastipur& Darbhaga
840 130.08 595 102.25 245 27.83
Total 2901 689.13 2487 484.99 414 204.14
Box 4. Rehabilitation of Non-Titled DPs
Sandesh Market: Under SH 81, about 75-80 commercial structures, mostly temporary
type, will be dismantled due to widening of project road as there is no space to shift
backward both sides. The operators of these structures, mostly kiosks types have
been earning their income through small scale activities like tea making, small
eateries, sale of eggs, meat, bangles, cycle repair, electricity accessories, mobile
phone repair, xerox machine, etc. along the road since 1986. An overwhelming
majority of DPs belonging to the vulnerable groups will be displaced and will lose their
livelihood. They may come back after the road civil works and occupy the widened
road side and the encroachment will surface again or local administration may not
allow such encroachment. As a good practice, it is suggested for BSRDC to coordinate
with the district administration and local Panchayat/Municipal body as applicable for
providing alternative land/ location and rehabilitate them to avoid impoverishment risks
in post-project stage. Although the DPs in question opted for self relocation and cash
compensation at the time of census survey that is reported in the ADB approved
Resettlement plan.
Household is the unit considered for conducting the survey. While the term Raiyat referring to the
entitled person was taken into account for disbursing compensation by the District land acquisition
officer(DLAO). It seems to be the reason of data inconsistency (between Table 2.3 and Table
5.4). It will however be verified during the upcoming project site visit. However, the available data
from DLAO analysed in Table 5.4 shows that a total of 16,910 titled HHs were affected due to
1813.90 acre land acquisition under the project. As of November 2016, 11,051 heads of affected
households having land titles and entitlements were paid compensation amount of INR 60,426
lakhs against the cost of land and structures. They have submitted all the documents to District
Collector's office required for the purpose. Remaining 5859 HHs were to be disbursed INR 10,951
lakhs upon completion of the LA process. In addition, the compensation amount will have to be
disbursed to the titled HHs where LA was in the initial stage in some SHs such as SH 81 and SH
87. Based on the actual value of impacts on the land and structures as assessed in accordance
with LA Act, 1894 and reported in the micro-plan, the budget for compensation amount was
sanctioned by the State.
The amount sanctioned following the criteria of earlier LA Act of 1894 became insufficient as the
compensation amount calculated and paid upto four times under the new LARR Act, 2013 to the
HHs in some SHs. Therefore, the Bihar State has to provide additional funds to compensate
remaining HHs immediately. BSRDC expected to complete the disbursement of LA compensation
to remaining title HHs by 31 March 2018.
34
Table 5.4. Status of Compensation Disbursed for Land Acquisition
SH District Total LA (acres)
Total Affected Households
(HH)
Total Amount Sanctioned (INR
in lakh)
As of 30 Nov 2016
Paid Balance
HH( No.) Amount (INR in Lakh)
HH (No.) Amount (INR in Lakh)
BSHP II
78 Patna & Nalanda 1293.29 8330 40193 6928 40880 1402 687
81 Rohtas& Bhojpur 146.93 2156 3600 700 1596 1456 2004
89 Siwan NA NA NA NA NA NA NA
90 Saran & Gopalganj
74.18 1531 4625 662 1809 869 2816
91 Supaul & Madhepura
42.75 320 2765 280 1987 40 778
BSHP-IIAF
83 Nawada & Shekhapura
2.17 117 313.4 98 276 19 38
86 Muzaffarpur 16.51 623 2255 395 1950 228 305
87 Sitamari 82.58 1588 4712 467 2572 1121 2140
88 Samastipur & Darbhanga
155.49 2245 11533 1521 9356 724 2183
Total 1813.9 16910 69996.4 11051 60426 5859 10951
35
36
Box 5. Project Perception and Compensation Disbursement
The PWD in SH 90 owns 14-16 meter land and total about 14 meter private land was
acquired for the RoW. Available DPs during the consultation perceived benefits and
responded positively. The project road will provide easy access to market, hospital, school
and connectivity outside. While the process of land acquisition (LA) under the RFCTLARR,
2013 was ongoing, the private land continued to remain in use for the agricultural activities.
The civil works in the PWD owned land was observed to be ongoing in different stages. At
Mohammadpur village (chainage 0), one DP was disbursed compensation for the land and
structure impacted in July 2016. Other DPs from the chainage 19+200 and nearby
reported that they have not received compensation and the civil works was in progress.
The PIU and NGO personnel present replied that the compensation was not paid due to
dispute in land ownership, objection raised by other joint owners and required documents,
including PAN card and photo were not submitted and the road works was confined to the
PWD land only so far. They were also informed that the consent from 5 land owners of
chainage 0 was received recently and they will be compensated soon. Tax deducted at
source (TDS) was deducted from the compensation amount of residential and commercial
land and was not deducted from the compensation amount of agricultural land. The PIUs
assisting DPs in preparing required documents and conducting consultations for resolving
or minimizing disputes which were due to misunderstanding among the joint owners of
land.
In SH 89, the DP of a residential structure was satisfied as the compensation amount
received in two instalments (INR 40,000 each) against dismantling the frontage was used
in repair and renovation of old house structure.
It is inferred that DPs were not fully aware about the submission of proper documentation
required prior to receiving the compensation amount. It was observed that the agricultural
land under acquisition was allowed to be cultivated by the farmers and the civil works was
confined to the available RoW only. However, the compensation amount would have been
disbursed prior to the commencement of civil works. Further, the TDS on compensation
amount is exempted that is the responsibility of the EA as per LA Act, 2013 and the
provisions of entitlement matrix.
5.3. Assistance Amount Disbursement
In accordance with ADB approved entitlement matrix of resettlement plans, five types of
assistance amount were reported to be paid to eligible titled and non-titled affected
households/DPs. These include (i) shifting assistance due to loss of commercial and
residential structures at the rate of INR 10,000 for each permanent structure and INR 4000 for
kiosks or temporary structures; (ii) transitional assistance at the rate of INR 9000 to each titled
household; (iii) training assistance at the rate of INR 4000 per trainee; (iv) special assistance
amount INR 10000 to each vulnerable family; and (v) livelihood/transitional assistance amount
of INR 9000 to each household. The transitional assistance to titled and livelihood assistance
to titled as well as non-titled affected HHs were paid, who had business loss of 10 % or more
due to project activities. The non-vulnerable HHs having less than 10 % loss of their income
were not given livelihood assistance.
Details given at Annex 3 indicates that by 30 November 2016 the transitional assistance was paid to entitled
37
affected HHs in SH 78 and SH 83; livelihood assistance was given in SH 81 and SH 91; and both types of
assistance was paid in SH 90 only. The livelihood assistance paid was @ INR 9000 per household in SH 90.
However, the livelihood assistance for the entitled households was sanctioned @INR 10,000 per household in
SH 81 and SH 91. It will however be confirmed in upcoming field visit. In SH 83, 71 non vulnerable encroachers
having less than 10% of loss of their structures/income were not given any assistance. Available data reveals
that a total of 12894 affected HHs, belonging to titled and non-titled categories, had entitlement for different
types of assistance amount under the project. Based on the number of entitled HHs and assistance amount
due to them, BSRDC sanctioned a total of INR 748.30 lakh for disbursing the assistance amount. Out of the
sanctioned amount, a sum of INR 583.10 lakh was paid to 9360 affected HHs and INR 209.48 lakh to be paid to
remaining 3533 HHs. Data about remaining (470) HHs could not be confirmed that will be verified and
incorporated during the upcoming visit to project sites. A maximum amount of INR 104.14 lakh was to be
disbursed to 1528 HHs in SH 78. It is followed by 30.52 lakh to 415 HHs in SH 91, 27.14 lakh to 359 HHs in
SH 81, and 23.64 lakh to 970 HHs in SH 88. BSRDC agreed to disburse the remaining assistance amount to
entitled HHs by 31 March 2018.
5.4. Community Property Resources The impacts on many CPRs were avoided during the implementation that were verified and finalized by
NGOs/PIUs. The CPRs included hand pump, wells, religious structures, common platforms, etc.
Table 5.5 shows that out of a total of 764 CPR structures impacted, only 22 old structures were demolished and
34 new structures were constructed until November 2016. 73 structures requiring minor renovation works
were functional and community usage were restored as required. As many as 742 old structures to be
demolished, 730 structures to be constructed and 745 structures require to be made functional. The need for
relocation of deities alongwith the performance of rituals in the new structures was emphasized by the
communities. In addition, out of 774 hand pumps impacted, 740 hand pumps were to be replaced and made
functional for drinking water. The progress of construction of CPRs have been very slow as evidenced by 4.45
percent new structures constructed by November 2016. BSRDC agreed to follow up with the contractors to
complete the construction of maximum CPRs by 31 Dec 2017.
Table 5.5 Status of CPR Structures
SH District
Total
CPR
struct
ures
impa
cted
Progress on CPRs Balance
New Structu
res
Constr
ucted
Old stru
cur
es
de
mo
lish
ed
Usage restor
ed in
new
structu
res
New structures
to be
construc
ted
Old structur
es to be
demolis hed
Usage to
be
restore
Hand pump
Impac
ted
Bal
anc
e
Han
dpu
mp
BSHP-II
78 Patna and
Nalanda 33 12 6 12 21 27 21 0 0
81 Rohtas and
Bhojpur 348 0 0 0 348 348
34
8 305 305
89 Siwan 25 9 9 25 16 16 25 24 18
90 Saran and
Gopalganj 33 3 3 3 30 30 30 54 54
91 Supaul and
Madhepura 49 0 0 0 49 49 49 27 27
38
BSHP-II AF
83
Nawada &
Shekhapur
a
6 4 4 4 2 2 2 24 6
87 Muzaffarp
ur 29 6 0 29 23 29 29 76 66
88 Sitamari 35 0 0 0 35 35 35 108 108
89
Samastipur
and
Darbhanga
206 0 0 0 206 206 20
6 156 156
764 34 22 74 730 742 74
5 774 740
Box 6. Requirement of Rituals for Relocating Deities
CPRs, particularly the structures were constructed against the temples to be demolished
for widening the project road by the Contractors. Such structures were constructed
backward in the private lands that were given voluntarily by the owners for religious
cause. At some locations, new structures were constructed and existing structures of
temples were not demolished and the budget for performing ritual to shift the deities/gods
in the new structures were not provided. BSRDC informed that for demolishing old
structures of temples and shifting of deities/gods will be done in consultation with the
local communities and budget will be provided for performing rituals.
5.5. Vocational Training Programs
The vocational training program was aimed at imparting or enhancing the skill of DPs to initiate
or add to the existing income generating activity. It is one of the rehabilitation measures to
ensure the livelihood of households on sustainability basis. The entitlement matrix has the
provision of vocational training to title as well as non-titled DPs fulfilling the criteria of loss 10%
or more under the project. NGOs alongwith the PIU staff coordinated and organized the
training programs in different trades as identified in consultations with the DPs.
The training schedule was prepared considering the availability and convenience of trainees.
The trainers as needed for different vocations were engaged for 3 days and 5 days training
programs as required. Efforts were reported to have been made to provide loan and other
facilities from Bank and credit societies and converge development and employment
generating schemes such as MNREGA to benefit the DPs. The specific data on these activities
could not be ascertained. DPs, who attended the training program were given training toolkit
containing a bag, booklet related to training, writing pad, pen, etc. Trainees arriving to the
training venue in the morning and returning home in the evening were given the transport
facility and the meals (breakfast and lunch) during the program. The certificates were
distributed to those who successfully completed the training program.
Data available on the status of the vocational training program are presented in Table 5.6. It
reveals that a total of 97 training programs for 3 days and 5 days, including 85 training
programs in SH 78 alone were conducted during 2014-2015. Such programs varied from 1-4
times only in other SHs and no training was imparted to entitled DPs in SH 81 and SH 91 so
far. A total of 6696 DPs (titled and non-titled) were reported to have entitlement for the training
by November 2016. Of them, 5128 DPs including 2277 DPs from general and 2851 DPs from
vulnerable categories participated in the training programs. The training to 1568 DPs
continued to remain pending. BSRDC expected to impart training to the maximum remaining
DPs by December 2017. A sum of INR 4000 per person was made available to incur the cost
of a training program. The data available for SH-78 only indicates that the expenditure incurred
on training was INR 32.40 lakh.
39
Table 5.6. Details of Vocational Training Programs
SH District Total
Training Programs
DPs having entitlement
for training
No. of Training Program conducted during 2014-2015
No. of DPs participated No. of Type of
Vocation/Trade Duration of
Training
event (days)
Remainin
g DPs
General Vulnerable
BSHP –II 78 Patna & Nalanda 85 5499 2148 2550 801 Making of
Agarbati,Candle
Making,Indigo Biue
5 Days
81 Rohtas& Bhojpur 0 146 0 0 146 0 0 89 Siwan 1 23 8 15 0 Making of
Agarbati,Candle
making, Indigo Blue
Food Processing,
Agarbati,Candle
making, Indigo Blue
3 Days
90 Saran &
Gopalganj 3 61 20 41 0 3 Days
91 Supaul &
Madhepura 0
259 0 0 259 0
BSHP II AF 83 Nawada &
Shekhapura 1 39 0 39 0 Making of Candle,
Perfume, Agarbatti 5 Days
86 Muzaffarpur 4 245 66 54 125 Food Processing,
Agarbati, Candle,
Indigo Blue making
3 Days
87 Sitamari 1 77 33 42 2 Food Processing,
Agarbati,Candle, Indigo
Blue making
3 Days
88 Samastipur &
Darbhaga 2 347 2 110 235 Candle, Agarbatti, Mix
Pickle, Paper Envelope
making
3 Days
Total 97 6696 2277 2851 1568
40
41
6. Disclosure, Consultation and Grievance Redress 6.1. Disclosure and Distribution of Entitlement Matrix
PIUs reported to have executed the disclosure requirements, particularly the Entitlement Matrix
(EM) of ADB approved RPs in all the SHs. EM was translated in vernacular language and
distributed to DPs in field at different locations by the concerned NGO. It enabled DPs and other
stakeholders to understand the entitlement provisions of compensation and assistance for
different categories of impacts. The translated EMs were mainly distributed in 2011 and 2012 in
all the SHs, except SH 78 where it was distributed in 2013 and 2014 as indicated in the Table
6.1. The distribution of summarized RP in vernacular language, including the EM, instead of EM
alone, was identified as a gap in the RPs implementation.
Table 6.1. Details of RP Disclosure
S. No. SH No. Disclosure date
1 SH-81 15-05-2011
2 SH-90 19-09-2011
3 SH-91 27-05-2011
4 SH-89 25-08-2012
5 SH-78 August 2013 and July 2014
6 SH-87 March 2012
7 SH-88 25-02-2012
8 SH-86 March 2012
9 SH-83 05-03-2012
6.2. Consultations held with DPs and other Stakeholders
PIUs and/or NGOs held several formal and informal meetings with DPs since the initiation of
land acquisition and resettlement planning process. The project information was
disseminated, DPs and other stakeholders were explained about the project roads and
awareness about its positive and negative impacts was created among them. The land
acquisition, entitlements for different type of impacts, compensation and assistance details
were shared. Information about the grievance redressal mechanism was disseminated among
the DPs, who can approach for resolving grievances and disputes amicably without incurring
any expenditure. The views and suggestions of DPs and other stakeholders were solicited
and incorporated during project cycle as feasible. Besides DPs, NGOs consulted the formal
and informal community leaders, District Land Acquisition Officer (DLAO), Circle Officer (CO)
and other stakeholders for seeking their support in RPs implementation. Such consultations
were held regularly until NGOs continued working till March 2014 and some of them
discontinued completely due to extension of time not given to them.
42
The information available in the monitoring reports reveal that a total of 616 DPs and local
community persons participated in the 30 consultations held at different locations (villages) in
SH81, SH90, SH 91 and SH 89 during January-August 2014. The number of participants at
each location varied from 12-20, except a maximum number of 76, 61 and 50 participants at
Chhatapur (SH 91), Jalpura and Baruhi villages (SH 81) respectively. In SH 83, total 16 DPs
participated in the consultations held at two villages in July 2016.In SH 78, total 66 DPs from
08 different villages participated in the consultations held during January-June 2015. The
monitoring reports for SH 86, SH 87 (Jan-June 2016) and SH-88 (Jan-June 2015) mentioned
to have conducted consultations and focus group discussions with DPs. It was noted that the
NGOs have conducted consultations adequately with the DPs and other stakeholders on
various R&R aspects in the field. Details of the consultations given at Annex 2.
6.3. Grievance Redressal Mechanism The grievance redressal committee (GRC) was established at the district level. The project
road were passing through 13 districts where GRCs were formed during 2011-2013, except
for Nawada district in 2014. Each GRC headed by the District Magistrate (DM)/Assistant
District Magistrate comprised of members like Deputy General Manager (Technical)
designated as Resettlement Officer, PIU, Circle Officer, Representatives from Public, Revenue
department, DPs including woman, SC/ST and NGO. The GRC meetings (2-3 times) were
held at Patna, Nalanda, Gopalganj, Nawada and Sitamadi districts and no such meetings was
held in remaining 8 districts.
Usually the DPs/aggrieved persons communicated the complaints verbally to the PIU/NGO
personnel in the field. They reported to have resolved the maximum complaints at their level.
However, written complaints from SH 78, SH 83 and SH 86 were received. The major
complaints were related to enhanced compensation of the affected land at the commercial and
residential land value, convert the government land as private land used for decades without
the land title, change in alignment to avoid impacts, physical displacement of NTH (in SH 78),
commercial displacement of NTH (at Sandesh market in SH 81), dispute on ownership of RoW
land in SH 88, legal heir disputes, site camp of contractor (SH 86) burnt by the Maoist in Jan
2015, etc. It was noted that 21 cases, mainly for higher compensation, were filed in High Court
by the DPs from SH 78.
The delay in land acquisition and disbursement of compensation and assistance; non-
availability of all documents for the submission in District Collector’s office; non-availability of
implementing NGOs; weak coordination among different agencies; pending decisions about
the bypass in SH-89, ROB in SH 83; finalization of alignment for some stretches in SH 88,
delayed LA under Perpetual Lease Policy 2015 in SH 87 are other critical issues identified.
The GRC meetings were not held in several districts and persisting complaints of DPs
necessitate the grievance redressal mechanism to be functional and efficient. However,
information available about the grievance redressal mechanism/number of meetings held and
the status of grievances are indicated in Table 6.2 and Table 6.3 respectively.
43
Table 6.2. Grievance Redressal Mechanism
S.No. District Date of GRC formation No. of GRC
Meeting held
1 Patna 26 June 2011 2
2 Nalanda 21 May 2011 3
3 Bhojpur 24 October 2011 None
4 Rohtas 30 July 2012 None
5 Siwan 07 May 2013 None
6 Gopalganj 16 April 2012 2
7 Chhapra 27 July 2012 None
8 Madhepura 2013 None
9 Saupal 2013 None
10 Sekhpura To be ascertained None
11 Nawada 29 January 2014 1
12 Muzzafarpur 27 April 2012 None
13 Sitamadi 19 May 2012 3
Table 6.3. Status of Grievances
Particulars Grievances
Received
Resolved Pending
SH 78 15 15 0
SH 81 1 0 1
SH 89 0 0 0
SH 90 0 0 0
SH 91 0 0 0
SH 83 1 1 0
SH 86 0 0 0
SH 87 11 11 0
SH 88 15 15 0
44
6.4. HIV/AIDS Awareness
The highways and roads facilitate an easy access and mobility of people, including the high
risk groups. It has exposed and may cause the risk of HIV/AIDS transmission without its
awareness and prevention measures. In the project roads, implementing NGOs in
association with the staff of PIUs and Contractors have conducted HIV/AIDS awareness
generation and prevention campaign among the labour and staff working in the project and
the surrounding community at different locations. Such programs were mainly conducted
with the help of medical and paramedical staff of Bihar State AIDS Control Society(BSACS).
The counselling/ advisory on HIV/AIDS, availability and distribution of condoms, voluntary
confidential counselling for testing (VCCT) and STI treatment were undertaken for workers
and village adults. NGOs also had personal contacts, and group discussions at hot spots
like highway hotels, truck parking places and contacted truck drivers, helpers, assistants,
local community people for generating awareness through display of banners and posters
against HIV/AIDS.
Total 346 resource persons from BSACS, PIU, CSCs and NGOs conducted 149 HIV/AIDS
awareness programs using the posters and banners during 2013-2015. As many as 3372
workers engaged in 9 SHs participated. In addition, 4343 persons from local communities
attended such programs. Besides HIV/AIDS awareness campaign, medical doctor and
technician have carried out confidential medical test of workers. The resource persons have
also covered the human trafficking, gender sensitization and road safety aspects during the
campaign. The details are given in Table 6.4.
Table 6.4. Details of HIV/AIDS Program
SH District T otal HIV/AIDS Awareness programs organized
No. of HIV/AIDS program conducted
No. of Workers Participated
No. of Local N persons from R village P participated
o. of esource ersons
BSHP -II 78 Patna & Nalanda 15 300 250 30
81 Rohtas & Bhojpur
7 140 110 14
89 Siwan 8 260 205 16
90 Saran & Gopalganj
12 480 400 30
91 Supaul &
Madhepura 58 240 1757 120
BSHP II AF 83 Nawada &
Shekhapura 6 170 120 16
86 Muzaffarpur 15 600 450 40 87 Sitamari 10 500 418 30
88 Samastipur & Darbhanga
18 682 633 50
Total 149 3372 4343 346
45
7. Monitoring and Reporting
PIUs alongwith the experts of CSCs monitored the implementation of RPs. Each PIU held
review meetings with the implementing NGO staff, until their presence in March 2014, every
month or when required. The BSRDC/CPIU at Patna held review meetings with the PIUs,
implementing NGOs and CSC experts periodically to monitor the progress of land
acquisition, R&R and related activities. The CPIU/PIUs coordinated with the revenue
department/district collector for LARR. NGOs provided data to prepare the monitoring
reports on monthly basis. The experts of CSCs verified and compiled data and prepared
reports that were submitted to concerned PIUs. PIUs further verified and submitted these
reports to BSRDC for submission to ADB on bi-annual and annual basis. Such reports from
CSCs were available for 2015 and 2016. NGOs not on board discontinued reporting as their
services were not extended after initial 36 months.
The monitoring reports, however, require improvements in timely updation of data, reporting
the gaps clearly and advising PIUs and CPIU for corrective action plan and expeditious
implementation of RPs. There was no adequate reporting accessible on gender action plan
(GAP) required for 4 SHs under Additional Financing. BSRDC ensured close monitoring and
timely reporting, including GAP. It has also agreed to improve coordination among CSC
experts and with PIUs and CPIU for an overall understanding of RPs implementation in the
project in line with ADB SPS and applicable national and state laws. Monitoring and
reporting process followed is given at Table 7.1.
Table 7.1. Monitoring and Reporting
S.No. Type of Report Responsibility
1 Monthly NGO/PIU
2 Quarterly NGO/CSC/PIU
3 Semi- annually NGO/CSC/PIU
4 Annually NGO/CSC/PIU
7.1. Status of Corrective Action Plan (CAP)
The agreed CAP with the ADB review mission conducted during 4-8 May 2016 that was
reported in the aide memoire is given at Table 7.2.
Table 7.2. Corrective Action Plan
S.No
.
Action
Agencies
Responsible
Completion
Date
Status as on 31 August 2015 Status as on 30
Nov 2016
Social Safeguards
1. Appoint full-time Safeguards Officer at
DGM level at BSRDC BSRDC June 2015 Sh. Ramesh Kumar Singh,DGM
(Tech.) has been deputed as full
time Safeguard Officer looking after
Environment, Forest, R&R and
DPR.He has been entrusted with
the duty of safeguard matter
throughout the project life cycle
including project preparation(DPR)
to implementation stage.
Mr. Ashutosh
Kumar Singh has
been entrusted
with the social
safeguards
responsibility
since 1 July 2016
in place of Mr.
Ramesh Kumar
Singh.
2. Appoint full-time Assistant Resettlement
Officers at each PIU BSRDC June 2015 Present arrangement has been
reviewed and considered to be
adequate.
AROs with PIUs
are in place. They
need assistance
of NGOs to
expedite the
implementation of
RPs in the field.
3. Engage a resettlement expert and an
environmental expert for SH78 under an
independent consulting contract
BSRDC, CSC June 2015 Commencement of fresh contractor
has taken place in SH-78. After
mobilization of contractor services
of expert shall be procured as per
the need.
BSRDC through
Construction
Supervision
Consultant (Egis)
appointed a
Resettlement
Expert since
March 2016.
46
4. Provide time extension and additional
budget to NGOs for seven lapsed
contracts
BSRDC,
NGOs
June 2015
Time extension has been given for
lapsed Contracts and Additional
Financial claim for extended period
is being entertained as submitted
by NGOs. This does not require
additional budget because there is
already adequate provision in the
administration approval.
BSRDC
committed to
extend time for
NGOs effective
from 30 April
2017.
5. Update RPs for all 9 project roads BSRDC,
CSCs, NGOs August
2015 Under process. NGOs have been
instructed to procure data for
updation of RPs. Compilation of
updation of RP shall be done by
CSC after submission of data by
NGOs.
BSRDC agreed to
submit four RPs
for SH 86, SH 83
and SH 90, SH
91 by 30 June
2017 and submit
remaining four
RPs (for SH 81,
SH 88, SH 87and
SH 78) by 31 Dec
2017. The draft RP
for SH 89 was
submitted in March
2017.
6. Fully reflect requirements of India’s new
land acquisition legislation in updated
RPs
BSRDC, CSC A
and NGOs ugust 2015 Shall be taken care in the updated
RP The RFCTLARR,
2013 is followed
as applicable
7. Provide updated impact figures to ADB BSRDC,
CSCs, NGOs July 2015 Shall be provided when data
becomes available from NGOs. The updated data
on impacts
available so far
are indicated in
the first
monitoring report.
47
8. Resolve issue of compensation of non-
vulnerable encroachers according to SPS
2009 requirements during subsequent
missions
ADB, BSRDC September
2015 The matter shall be put up before
Govt. for consideration after
discussion with next ADB mission.
This matter was
not put up to state
government and
was pending so
far.
9. Prepare micro plans for titled affected
households as soon as Section 6 of LAA
1894 and LARR 2013 has been notified
BSRDC,
CSCs, NGOs Immediately
and
continuous
Being prepared. Micro plans were
being prepared
where the
notification u/s 19
of new Act was
issued by the
appropriate
government.
10. Ensure regular meetings of Grievance
Redress Committees (GRCs) with
participation of women representatives
District
Collector, DPs
representatives
NGOs, female
members of
local
government,
PIUs , other
interest groups
Immediately
and
continuous
Instruction has been issued. The meetings of
GRCs were
reported to be
conducted upon
receiving the
grievances
48
11. Prepare consolidated semi-annual social
monitoring reports BSRDC, CSCs From June
2015
onwards
Instruction has been issued. CSCs agreed to
submit updated
semi-annual
monitoring
reports by 30
June 2017.
12. Place a tanker with potable water at zero
point of SH 86 until replacement of hand
pump is accomplished
BSRDC,
Contractor Immediately
and
continuous
Implemented. Implemented and
closed.
13. Cease all commencement of civil works
at road section where compensation has
not been paid and initiate civil works only
at road sections without land acquisition
or where payment of compensation to the
affected persons has been accomplished
BSRDC,
Contractors,
CSCs
Immediately C
and t
continuous l
ontractors have been instructed
o work only on the hindrance free
and handed over to them.
BSRDC agreed
for close
monitoring to
ensure its
compliance by
the Contractors.
14. Strengthen synchronization between
CSC and NGOs in finalization of road
design and land acquisition plans by
jointly working with definitive and reliable
strip plans
BSRDC,
CSCs, NGOs Immediately
and
continuous
Being Implemented. PIUs have been
performing major
roles. However,
CSCs and NGOs
need improved coordination for
land acquisition
plans, RPs
updation and its
implementation.
49
15. Systematically organize consultation BSRDC, Immediately Being Implemented. Consultations
meetings with affected persons along all
project roads explaining final land
acquisition impacts and their mitigation
and disclose LAR information pamphlet in
local language
16. Periodic review meetings of BSRDC and
CSC resettlement experts with ADB’s
environmental staff at ADB INRM in New
Delhi
CSCs, NGOs and
continuous
Consultants, From July Shall participate whenever
conveyed.
BSRDC and 2015
ADB onwards
with DPs was
ongoing and
disclosure need
to be improved as
agreed.
Complied with.
17. Report on the implementation of this
corrective action plan to ADB every two
months
BSRDC From 1
August
2015 every
two months
Until
completion
Report shall be submitted quarterly. CSCs have been
submitting the
semi-annual
monitoring
reports.
50
8. Conclusions and Recommendations
Compared to the impacts reported in ADB approved RPs, the actual impacts on the land and
assets of displaced persons were avoided significantly during the implementation. The
progress of the implementation of RPs (though not updated) and LARR activities has
remained slow so far. As indicated earlier, un-updated land records with revenue department,
mandatory submission of several documents in District Collector office that were not
possessed by the farmers in rural areas, non-availability of out-migrant DPs, delays in land
acquisition and disbursement of compensation and assistance amount, opposition by DPs for
higher compensation, weak co-ordination and monitoring, updated RPs pending for a long
time, inconsistent and unorganized data, inadequacy in data management, etc, are the major
issues. The implementation of agreed CAP and additional action plan within the timeframe
are other critical concerns requiring immediate attention of higher authorities of BSRDC. Also,
Bihar State has to immediately release additional funds required for compensation and
assistance to DPs under the RFCTLARR Act, 2013.
The institutional strengthening by immediately issuance of extension of time and restarting
the works by NGOs and deploying retired revenue officials where required, improved
coordination with Revenue Department for expeditious land acquisition, efficient grievance
redressal mechanism through information dissemination, awareness generation among DPs
and holding meetings of GRC regularly, closer monitoring by the PIUs, etc. will help
implement RPs expeditiously.
Overall the implementation of LARR activities/RPs follows the ADB SPS, 2009, applicable
National and State laws and policies. BSRDC is committed to comply with the legal covenants
of ADB in Bihar State Highways Project.
8.1. Additional Action Plan
Besides the CAP, the additional action plan agreed with the BSRDC is given in Table 8.1
51
52
Table 8.1. Additional Action Plan
S.No. Action Responsibility Timeline
1. Provide additional funds to BSRDC disburse Bihar State Immediately
compensation and assistance amount to
remaining DPs as the sanctioned amount for the
purpose became insufficient due to enhanced
compensation required under RTFCLARR Act,
2013
2. Completion of land acquisition and BSRDC/District 31 March 2018
disbursement of compensation and assistance Collectors
amount
3. Disbursement of compensation of pending BSRDC 30 June 2017
structures to non-titled DPs
4. Completion of the construction of maximum Contractors/
BSRDC
31 Dec 2017
5.
6.
7.
8.
9.
10.
CPRs
Prepare and distribute ID cards for remaining
non-titled DPs
Prepare micro-plan and distribute ID cards to
titled DPs
Completion of vocational training to remaining
DPs
Provide service extension of R&R and Gender
experts of CSCs
Deploy retired Revenue Officials (Ameen) in
SHs as required
Fill up one vacant post of Account Executive in
SH-88
NGOs/PIUs 31 May 2017
NGOs/PIUs Upon land
acquisition
notifications
NGOs/PIUs 31 Dec 2017
BSRDC As required
PIUs 31 May 2017
PIU/BSRDC 30 June 2017
11. Submission of Gender Action Plan for SH 83, SH 86, SH 87, SH 88 under Additional Financing
Gender Experts
of ICT and Egis
(CSCs)
Periodically
53
Annex 1
Checklist for Consultation/FGD with DPs on status of LARR activities
I. Identification
• Number and Name/s of DPs
• Location
• Social profile
II. Perceived Project Impacts
• Positive/ negative (priority-wise listing)
• Type and quantum of loss to land, assets, livelihood
• CPR, public utilities
III. Compensation Disbursement
• Compensation, allowances/assistance, IR program/ training, etc
• Special assistance to vulnerable groups
• Expectations/ satisfaction level
IV. Disclosure, Consultations and Participation
• source of information-newspaper, officials, public representatives, etc
• Consultations- frequency, personnel- EA/IA, NGO, purpose, output, etc
• Community participation- planning, implementation, monitoring
V. Grievance Redress Mechanism
• Information about the GRC, its members, functioning, meetings held
• Complaints/ grievances of DPs-type, reported to GRC, redressed and reasons if not redressed
timeline/duration
• Court cases
VI. Institutional Arrangements
• Personnel in place
• Process and procedure followed
• Time taken
VII. Suggestions for Improvement
54
Annex 2
Details of Consultation held with Affected Households and Stakeholders
Sl.No. SH
No.
Date Locati
on/Vill
age
and
No. of
Partici
pants
Issues Discussed Action/Decision/Agreement
1 SH-
78
21.10.2011 1. Will it be possible for
the department that
they will construct the
CPR?
1. Yes, we can construct the same
through contractor.
2. What is the basis or
eligibly to get the
compensation?
2. Any construction work within the
ROW after cut-off-date will neither
enumerated nor paid.
3. Whether this road will
be Concrete or
Bitumen?
3. The road will be constructed
concrete in built-up area, while in
open area it will be Bitumen.
4. Is there any legal
action against the
encroachers?
4. Compensation will be paid at
replacement cost
10.02.2011 Jahana (1) Which Process will
be apply in this project
for Land Acquisition?
(2) What benefit we get
from this project?
1. Discussed related LA process.
2. All of you get better connectivity
and employment also.
2 SH-
81
14.10.2014 Kaccha
wa 1. Detail project
activities and
entitlements
1. The participants were apprised
about the project and its road
alignment as well as entitlements.
2. Whether this road
will be Concrete or
Bitumen?
2. The road will be constructed
concrete in built-up area, while in
open area it will be Bitumen.
13.07.2014
Akhgao
1. Road safety
measures should be
provided.
1. Road safety signs would be
provided at various locations to avoid
accidents
2. Provision of bus stop and public
conveniences should be made
2. The matter will be discussed with
EA and it may be considered, if
possible
1. They want the
permission of PWD to
construct the CPR in
1. If Gram Panchayat got the authority and availability of so called
“Aabadi land” they can permit but
3
SH- 89
04.08.2014
Surapur
government land. PWD cannot entertain this kind of practice.
2. On what basis we
will get the
compensation?
2. Compensation will be paid at
replacement cost that was detailed
out.
09.10.2015
Chainpur
1. Proper road safety
issue, drainage facility.
1. Road safety signs would be
provided at various locations to avoid
accidents and the drainage will be constructed in built up area
2. On what basis we will
get the compensation?
2. Compensation will be paid at
replacement cost
1. A temple is being
affected due to
construction of road
should be properly rehabilitated.
1. Village community will be
consulted. Relocation site and
process will be finalized by the Community.
4
SH -
90
10.10.2014 Karanku dariya
2. The business
communities were told
that compensation/
assistance for
temporary disruption in
business will be
adequately assisted.
2. The business communities were
told that there is provision of
transitional assistance in the
entitlement matrix and they will be
adequately paid
12.08.2015
Dighawa
Divoli
1. Awareness about the
project and project
features
1. The participants were apprised
about the project and road alignment.
2. The farmers
demanded not to
acquire the private land
for up gradation of road.
2. The farmers were told that all the
efforts are being made not to acquire
the private land for up gradation of
road. However, if required, the land
will be acquired through private
negotiations with affected farmers.
3. Land dispute and destruction of big houses should be
avoided
3. Cases of land dispute will be
resolved in association with Revenue officials.
4. Adequate
compensation for loss of
4. Adequate compensation will be
paid that was explained.
55
structures
5
SH -
91
14.08.2014
Rampur
1. People requested
for road safety signs,
which would be
provided at various
locations to avoid
accidents
1. Various safety signages will be
provided.
2. The women also
requested for
employment during
construction of the road
2. As per the policy, contractor to
give preference to local labour,
especially women in the construction
activities
08.09.2014
Mirgarj
1. Proper road safety
issue, drainage facility.
1. Road safety signs would be
provided at various locations to avoid
accidents and the drainage will be
constructed in built up area
2. On what basis we will
get the compensation?
It was the quarry at
most locations.
2. Compensation will be paid at
replacement cost.
6
SH -
83
20.11.2014 Manjaur 1. What is the rate of
payment of Structure of
NTH
1. Payment of Structure will be at
current scheduled rate
15.01.2015 Semari 1. What would be the
compensation of Land
1. Payment of Land will be as per
new policy that was upto four times of
the registered value
2. What is the posibility
of minimization of
PROW in Market Area
2. Scop of minimization of PROW will
be explored
22.10.2013 Sahpur
More 1. Payment of Structure
of TH 1. Payment of Structure will be at
current scheduled rate
18.12.2013 Chiraiya 2. Rate of
Compensation of Land 2. Payment of Land will be as per
new policy.
01.03.2014 Mahama
dpur 1. What is the process
of land acquisition if our
land is within ROW.
1. We will facilitate and keep
updating about any case of LA if it
comes
2. Issues discussed
with the DP’s
*commercial regarding
their livelihood
2. All the DP’s whose commercial
structure ids getting affected is
entitled for the training program, and
we will update about the date and
56
restoration training venue of the training.
23.06.2014 Basra 1. A temple is being affected not yet
relocated, needs to be
rehabilitated.
1. The relocation/shifting will be done by project cost as per
entitlement matrix
7
86 2. One private lands
are affecting due to
diversion of road. This
needs to be avoided
from being acquired.
2. Regarding diversion of road on
private land, the matter has been
discussed with EA and it was
decided that if land is required
temporarily for construction of
diversion, the contractor will go for
agreement and pay the agreed
compensation.
12.12.2014 Jaitpur 1. Road safety
measures should be
provided.
1. Road safety signs would be
provided at various locations to avoid
accidents
2. Provision of bus
stop and public
conveniences should be
made
2. The matter will be discussed with
EA and it may be considered, if
possible
2.2.2015 Distolia 1. They want the
permission of PWD to
construct the CPR in
government land
1. If Gram Panchayat got the
authority and availability of so called
“Aabadi land” they can permit but
PWD cannot entertain this kind of
practice.
2. On what basis we
will get the
compensation?
2. Compensation will be paid at
replacement cost
7.03.2015 Motipur 1. Awareness about the
project and project
features
1. The participants were explained
about the project and road alignment.
2. The Farmers
requested not to acquire
the private land for up
gradation of road.
2. The farmers were told that all the
efforts are being made not to acquire
the private land for up gradation of
road. However, if required, the land
will be acquired through private
negotiations with affected farmers.
3. Land dispute and
demolition of multistory
3. Such structures will be avoided to
the extent possible and cases of
57
structures should be
avoided
land dispute will be resolved in
consultations with Revenue officials.
02.05.2015 Sariffpur 1.Will it be possible to
change the centre line ?
1.If technically feasible, will change
or shift the centre line. It was clarified
about the locations where any
change was not possible.
8
87
06.05.2015 Ganguli 1.Will it be possible to give construction cost to
a villager for
reconstruction of the
temple impacted?
1.The Gram Sabha has to take a decision in this regard.
2. On what basis we
will get the
compensation?
2. Compensation will be paid as per
approved Entitlement Matrix.
07.07.2015 Sursand 1.Proper road safety
issue, drainage facility.
1. Road safety signs would be
provided at various locations to avoid
accidents and the drainage will be
constructed in built up areas.
2. What is the process
of compensation?
2. Compensation will be paid as per
approved Entitlement Matrix that will
meet the replacement value.
9
SH -
88
17.10.2014 Morwara
II
1. What about the burial
ground site impacted?
1. People were not agreeable to shift
existing burial ground location.
13.05.2015 Lilhoul 2. Compensation
payment procedure
2. Compensation at the replacement
value and in accordance with
approved Entitlement Matrix will be
paid through cheque to the entitled
person/s in public.
58
59
Annex 3
Disbursement of Assistance Amount to TH and NTH
S. No. SH Disbursement of
Assistance
Total Number
of HH
Total Amount
Sanctioned (INR in Lakh
As of November 2016
Paid Balance
House Hold
Amount (INR in Lakh)
House Hold
Amount (INR in Lakh)
1
78
Shifting Assistance
350 32.42 226 20.62 124 11.8
2 Livelihood Assistance
TBC
3 Transitional Assistance
2 0.18 2 0 0 0
4 Training Assistance
5499 219.96 4698 187.92 801 32.04
5
Special Assistance to Vulnerable
1535 15.35 932 93.2 603 60.3
Sub-Total 7387 406.06 5858 301.74 1528 104.14
1
81
Shifting Assistance
180 18 158 15.8 22 2.20
2 Livelihood Assistance
166 16.6 0 0 166 16.60
3 Transitional Assistance
DTBC
4 Training Assistance
146 5.84 0 0 146 5.84
5
Special Assistance to Vulnerable
120 12 95 9.5 25 2.5
Sub-Total 612 52.44 253 25.3 359 27.14
1
89
Shifting Assistance
27 2.7 27 2.7 0 0
2 Livelihood Assistance
DTBC
3 Transitional Assistance
DTBC
4 Training Assistance
23 0.92 23 0.92 0 0
5
Special Assistance to Vulnerable
32 3.2 31 3.1 1 0.1
Sub-Total 82 6.82 81 6.72 1 0.1
1 90
Shifting Assistance
212 21.2 191 19.1 21 2.1
2 Livelihood Assistance
TBC
60
S. No. SH Disbursement of
Assistance
Total Number
of HH
Total Amount
Sanctioned (INR in Lakh
As of November 2016
Paid Balance
House Hold
Amount (INR in Lakh)
House Hold
Amount (INR in Lakh)
3 Transitional Assistance
13 1.71 12 1.08 1 0.09
4 Training Assistance
71 2.84 61 2.44 10 0.4
5
Special Assistance to Vulnerable
587 58.7 403 40.3 184 18.4
Sub-Total 883 84.45 667 62.92 216 20.99
1
91
Shifting Assistance
118 11.8 103 10.3 15 1.5
2 Livelihood Assistance
178 17.8 0 0 178 17.8
3 Transitional Assistance
TBC
4 Training Assistance
248 9.92 65 2.6 183 7.32
5
Special Assistance to Vulnerable
104 10.4 65 6.5 39 3.9
Sub-Total 648 49.92 233 19.4 415 30.52
1
83
Shifting Assistance
100 5.44 94 5.14 6 0.3
2 Livelihood Assistance
TBC
3 Transitional Assistance
3 0.27 3 0.27 0 0
4 Training Assistance
40 1.6 39 1.56 1 0.04
5
Special Assistance to Vulnerable
179 17.9 175 17.5 4 0.40
Sub-Total 322 25.21 311 24.47 11 0.74
1
86
Shifting Assistance
154 15.4 154 15.4 0 0
2 Livelihood Assistance
TBC
3 Transitional Assistance
TBC
4 Training Assistance
129 5.16 122 4.88 7 0.28
5
Special Assistance to Vulnerable
96 9.6 96 9.6 0 0
61
S. No. SH Disbursement of
Assistance
Total Number
of HH
Total Amount
Sanctioned (INR in Lakh
As of November 2016
Paid Balance
House Hold
Amount (INR in Lakh)
House Hold
Amount (INR in Lakh)
Sub-Total 379 30.16 372 29.88 7 0.28
1
87
Shifting Assistance
132 13.2 129 12.9 3 0.3
2 Livelihood Assistance
TBC
3 Transitional Assistance
TBC
4 Training Assistance
86 3.44 75 3 11 0.44
5
Special Assistance to Vulnerable
297 29.7 286 28.6 11 1.1
Sub-Total 515 46.34 490 44.5 25 1.84
1
88
Shifting Assistance
865 23.98 477 13.21 388 10.77
2 Livelihood Assistance
TBC
3 Transitional Assistance
TBC
4 Training Assistance
347 13.88 112 4.48 235 9.4
5
Special Assistance to Vulnerable
841 8.41 494 49.4 347 3.47
Sub-Total 2053 46.27 1083 67.09 970 23.64
Total 12881 747.67 9348 582.02 3532 209.39