KARNATAKA NEERAVARI NIGAM LTD
Karnataka Integrated and Sustainable
Water Resources Management Investment Program ADB LOAN No. 3172-IND
Annual Progress Report January-December 2019
Project Management Unit, KISWRMIP
Project Support Consultant
SMEC International Pty. Ltd. Australia in association with
SMEC (India) Pvt. Ltd.
May 2020
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | ii
DOCUMENTS/REPORT CONTROL FORM
Report Name Annual Progress Report January-December 2018
Project Name: Karnataka Integrated and Sustainable Water Resources Management Investment Program
Project Number: 5061164
Report for: Karnataka Neeravari Nigam Ltd (KNNL)
REVISION HISTORY
Revision #
Date Prepared by Reviewed by Approved for Issue
by
1 1 May 2020 Balaji Maddikera Deepak GN and team
Dr Srinivas Mudrakartha/ Gaurav Srivastava
Dr Srinivas Mudrakartha/ Gaurav Srivastava
ISSUE REGISTER
Distribution List Date Issued Number of Copies
KNNL 1 May 2020 10
SMEC Staff 1 May 2020 2
Associate (Gaurav Shrivastava) 1 May 2020 1
Office Library (Shimoga) 1 May 2020 1
SMEC Project File 1 May 2020 2
SMEC COMPANY DETAILS
Dr Janardhan Sundaram, Executive Director
1st Floor, Novus Tower, West Wing, Plot Number -18, Sector – 18, Gurgaon – 122016, Haryana
Tel: +91 124 4501100
Fax: +91 124 4376018
Email: [email protected]; Website: www.smec.com/en-in
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | iii
CONTENTS
1 PROJECT BACKGROUND .......................................................................................................... 1
Introduction ............................................................................................................................. 1
KISWRMIP-Modernization of Irrigation Projects .................................................................... 2
Project Management .............................................................................................................. 3
Project Basic Data .................................................................................................................. 6
Utilisation of Funds ................................................................................................................. 8
Design Monitoring Framework Indicators .............................................................................. 9
Agreed Action Points from Aide memoire ............................................................................ 11
Deliverables of Project 1-Status ........................................................................................... 13
2 GONDI IRRIGATION SYSTEM .................................................................................................. 15
Overall Physical and Financial Progress ............................................................................. 15
Flow Measurement and Telemetry System ......................................................................... 20
Water Users Cooperative Societies ..................................................................................... 22
CAD Package Works ........................................................................................................... 27
CAD Works Progress-Phase 1 and 2 .................................................................................. 28
WUCS Buildings ................................................................................................................... 30
Gondi WUCS strengthening activity ..................................................................................... 30
Integrated and Sustainable Agriculture Activity ................................................................... 36
Gondi O&M and Asset Management Plan ........................................................................... 52
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | iv
Safeguard Monitoring of Gondi Irrigation System ................................................................ 54
3 SOCIAL MANAGEMENT FRAMEWORK AND GENDER ACTION PLAN ............................... 63
Progress against GAP .......................................................................................................... 63
Poverty, Gender and Livelihoods ......................................................................................... 68
Women sub-committees ...................................................................................................... 68
4 INFORMATION, EDUCATION AND COMMUNICATION .......................................................... 76
5 PROGRAM PERFORMANCE MANAGEMENT SYSTEM ......................................................... 79
6 CONCLUDING REMARKS ......................................................................................................... 82
7 TRANCHE 2 MODERNIZATION OF VIJAYANAGARA CHANNELS ....................................... 83
VNC Civil Works Execution .................................................................................................. 83
8 TLBC ........................................................................................................................................... 89
9 PROJECT STAFF MOBILISATION ........................................................................................... 91
Mobilisation During the Reporting Period ............................................................................ 91
10 CHALLENGES FACED AND ADDRESSED ............................................................................. 92
TABLES
Table 1: PMU Staff position as of 31 December 2019 ......................................................................... 6
Table 2: Project Basic Data .................................................................................................................. 6
Table 3: Contract award under Project 1 .............................................................................................. 9
Table 4: Details of disbursement under the Project 1 .......................................................................... 9
Table 5: Status of DMF for Project 1 .................................................................................................. 10
Table 6: Agreed Time-bound Actions ................................................................................................. 11
Table 7: Important deliverables for Project-1 activities ....................................................................... 13
Table 8: Physical Progress as of 31 December 2019 ........................................................................ 18
Table 9: Financial progress as of 31 December 2019 ........................................................................ 19
Table 10: Equipment details for flow measurement in Tungabhadra Sub-basin ............................... 20
Table 11: Installation of Telemetry Systems-Status as of 31 December 2019 .................................. 21
Table 12: WUCS-wise total farmers and shareholders as of 31 December 2019 ............................. 23
Table 13: WUCS Membership and One-time Grant as of 31 December 2019 .................................. 24
Table 14: Progress of water tax collection as of 31 December 2019 ................................................. 25
Table 15: Audit & AGM of WUCS and Federation ............................................................................. 26
Table 16: Status of CAD packages as of 31 December 2019 ............................................................ 28
Table 17: Physical & financial progress of CAD packages as of 31 Dec 2019 .................................. 28
Table 18: CAD Physical Progress of FIC Lining as of 31 December 2019-Phase 1 (130 packages) 29
Table 19: CAD Works Phase 2: Lining-Physical Progress as of 31 December 2019 (82 Packages) 29
Table 20: List of capacity building trainings conducted as of 31 December 2019 ............................. 33
Table 21: Trainings conducted on sustainable agricultural practices ................................................ 36
Table 22: SRI Paddy demonstration in farmer fields .......................................................................... 37
Table 23: Income and Yield comparison for SRI paddy ..................................................................... 38
Table 24: Details of banana tissue supplied for intercrop in arecanut plantation .............................. 39
Table 25: Organic Paddy Farmers and yield details .......................................................................... 41
Table 26: Farmers who raised Ragi (foxtail millets) ........................................................................... 42
Table 27: Vermicompost production by farmers ................................................................................. 43
Table 28: Woman farmers producing vermicompost on a commercial scale .................................... 45
Table 29: List of farmers adopting waste decomposer ....................................................................... 45
Table 30: Traditional varieties Introduced in the Project area ............................................................ 48
Table 31: Gondi Organic Farmers who sold organic paddy in the market ......................................... 49
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | v
Table 32: Approved farmers under Organic Group Certification Program ......................................... 50
Table 33: Loans received for purchase of cows as of 30 March 2019 ............................................... 52
Table 34: Private Landholdings used tor Project Activities and Status .............................................. 54
Table 35: Trainings on Environmental and Social Safeguards during 2019 ...................................... 55
Table 36: Grievances registered between 1 Sep 2017 and 31 Dec 2019 ......................................... 60
Table 37: Progress against Gender Action Plan ................................................................................ 63
Table 38: Women subcommittees as of 31 December 2019 ............................................................. 69
Table 39: Women sub-committee meetings and topics covered ....................................................... 69
Table 40: Women Shareholders WUCS wise ..................................................................................... 72
Table 41: Capacity Building Activities for Women during 2019 .......................................................... 73
Table 42: Summary of IEC activities for 2019 .................................................................................... 78
Table 43: Physical Progress of works as of 29 February 2020 for VNC Package 1 .......................... 84
Table 44: Milestones and activities for TLBC (per ADB loan review mission of Nov 2019) .............. 89
Table 45: Staff mobilization during January-December 2019 ............................................................ 91
FIGURES
Figure 1 & Figure 2: Krishna River network and Tungabhadra sub-basins ......................................... 1
Figure 3: Implementation arrangement for KISWRMIP ........................................................................ 5
Figure 4: S Curve: Physical Program and Progress under Gondi Irrigation System Modernization for
balance works ..................................................................................................................................... 16
Figure 5: S Curve: Financial Program and Progress under Gondi Irrigation System Modernization for
balance of works ................................................................................................................................. 17
Figure 6: GRM register maintained by Doddagoppenhalli WUCS ..................................................... 59
Figure 7: Physical progress of lining work .......................................................................................... 85
Figure 8: Physical progress of Structures ........................................................................................... 85
ANNEXURES
Annexure 1: Gondi WUCS Performance Indicators
Annexure 2: Working period of modernisation of Vijayanagara channels (Package 1) between
March 2019-September 2021
Annexure 3: Letter from Tahsildar of Bhadravathi giving powers to WUCS to collect water tax from
the farmers.
Annexure 4: Letter to CE - Gondi Project Closing related actions-reg.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | vi
GLOSSARY
ADB Asian Development Bank
AGM Annual General Body Meeting
ASI Archaeological Survey of India
CADA Command Area Development Authority
CCA Cultural Command Area
CPM Community Participation Management
CWC Central Water Commission
DEA Department of Economic Affairs
DMF Design & Monitoring Framework
DPOs Direct Pipe Outlet
DPR Detailed Project Report
EARF Environmental Assessment Review Framework
EIA Environmental Impact Assessment
EMP Environmental Management Plan
FAM Facility Administration Manual
FGD Focus Group Discussion
FSR Feasibility Study Report
GAP Gender Action Plan
GIIS Gondi Irrigation Information System
GoK Government of Karnataka
GST Goods and Services Tax
ICB International Competitive Bidding
ICZ Irrigation Central Zone
IEC Information Education and Communication
IEE Initial Environmental Evaluation
IP Indigenous Peoples
IR Involuntary Resettlement
IWRM Integrated Water Resource Management
KFD Karnataka Forest Department
KISWRMIP Karnataka Integrated and Sustainable Water Resource Management Investment
Program
KNNL Karnataka Neeravari Nigam Limited
MASSCOTE Mapping Systems and Services for Canal Operation Techniques
MFF Multi-tranche Finance Facility
MIS Management Information System
MTR Mid Term Report
O&M Operation and Maintenance
PALMS Productive Agriculture Linkages and Marketing System
PCC Program Coordination Committee
PD Program Director
PIO Project Implementation Office
PMIS Program Monitoring Information System
PMMS Program Monitoring Management System
PMU Project Management Unit
PPMS Program Performance Monitoring System
PPTA Project Preparation Technical Assistance
PRA Participatory Rural Appraisal
PSA Poverty and Social Assessment
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | vii
RBC Right Bank Canal
LBC Left Bank Canal
RICM Regional Institute of Cooperative Management
RMP Risk Management Plan
SMF Social Management Framework
SRI System of Rice Intensification
SC/ST Scheduled Caste/ Scheduled Tribe
SST Support Services Team
TLBC Tungabhadra Left Bank Canal
VNC Vijayanagara Channels
WALMI Water and Land Management Institute
WUCS Water Users Cooperative Society
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 1
KARNATAKA INTEGRATED AND SUSTAINABLE WATER RESOURCES MANAGEMENT INVESTMENT PROGRAM
1 PROJECT BACKGROUND
Introduction
1. Karnataka is a water stressed State in India with ever increasing inter-sectoral water
demands, agriculture being the major sector.
2. With the assistance of the Asian Development Bank (ADB), the State Government of
Karnataka has launched the Karnataka Integrated and Sustainable Water Resources
Management Investment Program (KISWRMIP), with the objective of improving water
availability for competing water demands in the selected river basins by implementing
integrated water resources management (IWRM) and improving irrigation services delivery in
the State. The program is expected to increase water use efficiency and provide economic
opportunities, in particular, to women, and improve rural incomes. The focus of the program
for implementation of physical works is Krishna Basin, in specific, the Tungabhadra sub-basin
(Figures 1 and 2). However, the IWRM activities will be implemented state-wide.
3. The multi-tranche financing facility (MFF) for the KISWRMIP and the periodic financing
request (PFR) for Project-1 were approved by ADB on 25 September 2014 and 17 October
2014 respectively. The total cost of the investment program over the period 2014-2024 is
expected to be $225 million, with ADB financing amounting to $150 million. Project 1,
estimated at $48 million, is closed on 31 December 2019. Project 1 financing comprises $31
million from ADB’s ordinary capital resources, $16.6 million from the Government of
Karnataka (GoK), and $400,000 of beneficiary contribution. However, the beneficiary
contribution has been waived in this project and the WUCS were also awarded CAD works
for implementation so that they own the assets created for their use effectively. A partial loan
cancellation of $5 million was approved on 22 May 2019. The loan effective from 13 July 2015
is scheduled for closing on 31 March 2019.
4. For Tranche 2, the periodic financing request was approved by ADB on 4 October 2019 for
$91 million and was signed on 18 November 2019. The loan is effective 24 January 2020.
Tranche 2 physical completion date is 30 September 2023 and financial closing date is 31
March 2024. Tungabhadra Left Bank Canal (TLBC) project which was earlier under Tranche
3 is now being considered for a separate standalone project.
Figure 1 & Figure 2: Krishna River network and Tungabhadra sub-basins
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 2
5. The Program comprises three outputs:
Output 1: State and Basin Institutions Strengthened for IWRM
6. This output strengthens the institutional capacities of the Water Resources Department
(WRD) and the Advanced Centre for IWRM (ACIWRM) to implement IWRM in select river
basins in Karnataka. This includes: (i) development and implementation of river basin plans
to better manage water resources; (ii) capacity building and certification of WRD (including
its associated agencies like KNNL in IWRM with 30% of trainees being women, and (iii)
improved water resources information systems.
Output 2: Irrigation System Infrastructure and Management Modernized
7. This output includes: (i) modernization of irrigation infrastructure including installation of
telemetry for canal flow measurement in three irrigation sub-projects within the Tungabhadra
Sub-basin (Gondi project under Tranche 1, Vijayanagara Channels (VNC) under Tranche 2;
(ii) strengthening asset management and system operation and maintenance (O&M), and (iii)
capacity building of Water User Cooperative Societies (WUCS), with women representation,
for improved operation, maintenance and water management within their respective
command areas.
Output 3: Program Management Systems operational
8. This output focuses on delivery of the above two program outputs on time and within budget.
The Program is managed by a Program Management Unit as described in the following
section.
KISWRMIP-Modernization of Irrigation Projects
9. The KISWRMIP includes modernization of three irrigation projects: (a) Gondi Irrigation
system, which is part of the Bhadra Irrigation System (Tranche 1); (b) Vijayanagara channels
(VNC, Tranche 2) and modernization and automation of (c) Tungabhadra Left Bank Canal
(TLBC) project.
Gondi Irrigation System
10. The Gondi anicut was built across the Bhadra River near Gondi village about 11.56 km from
Bhadravathi Town, Shimoga. It is located about 14.50 km downstream of the Bhadra dam. It
lies within the larger and more recent Bhadra Irrigation System but has its own supply from
the Gondi anicut. The Culturable Command Area (CCA) of the Gondi system is about 4,600
ha.
11. Under Tranche 1 Gondi modernization, the intervention envisaged comprises the following
components:
i. Improvement of canals providing lining so that losses are a minimum and also water
reaches the tail end villages within a short time after the head regulator gates are open;
ii. Repair/reconstruction of all appurtenant structures to facilitate easy movement of
transport vehicles and also structures to facilitate access to canal water – washing
ghats, cattle ramps etc;
iii. Supply and installation of telemetry-based flow measurement for getting the flow rates
at crucial locations;
iv. Installation of gates across all DPOs and POs so that the water flow could be regulated
to (i) minimize wastage of water and (ii) to better distribute irrigation water as per the
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 3
as per the planned irrigation schedule and also) (iii) use gates as a means of measuring
the flow rates along the canal system;
v. Development of a web-based asset management system (using GIS platform) that
helps the WUCS to effectively manage their assets and also their O&M activities. The
application also enables the WUCS to manage their crop water requirement and even
schedule and manage their maintenance works - both along FICs and also along the
main and distributary canals;
vi. A smartphone-based application for mapping the cropping pattern and also the
changes in the pattern on a continuous basis in different seasons round the year has
also been developed. The crop mapping enables the Agriculture and Irrigation
departments to access the changes in the pattern and also get accurate data during
any cropping season;
vii. Institution building and strengthening of WUCS so that the WUCS can, at the end of
modernization take over management of canals involving: (a) O&M; (b) irrigation water
scheduling; (c) collection of water cess, and (d) conflict resolution among the farmers
of WUCS through a robust Federation as an apex body at the project level;
viii. Setting up of a few revenue generation models both for individual landless or marginal
farmers, poor/destitute/single women or the marginalised community members as also
for the WUCS/Federation for long term sustainability of communities/institutions.
Project Management
12. Project Management Unit: Karnataka Neeravari Nigam Limited (KNNL) is the Executing
Agency for implementation of ADB assisted KISWRMIP. The Project Management Unit
(PMU) is headed by the Program Director and Managing Director, KNNL with its headquarters
at Bengaluru. Project Implementation Offices (PIOs) are headed by Chief Engineer of Upper
Tunga Project Zone, Shivamogga for Project 1 and Chief Engineer of Irrigation Central Zone,
Munirabad for Project 2. An updated list of the PMU staff is given in Table 1.
13. Project Implementation Office (PIO) for Output 1 under Tranche 1 has been established in
the Advanced Centre for IWRM (ACIWRM) for implementation of all IWRM related activities.
Similarly, for Output 2, under which the Modernization of Gondi Irrigation Project and the VNC
are being implemented, the PIOs have been established in the UTP Zone office at Shimoga
for Gondi on 25 January 2016, and at the ICZ office at Munirabad on 16 February 2016 for
Tranche 2 project preparatory activities. The PMU working with the PIOs and the Project
Support Consultant (PSC) monitors the overall program execution and is responsible for
monitoring and reporting.
14. Project Support Consultant: M/s SMEC International Pty. Ltd., Australia in joint venture with
SMEC (India) Pvt. Ltd.1 has been contracted as the Project Support Consultant by KNNL to
provide technical support for project implementation of Tranche 1. The PSC is located in
Shimoga. The PSC time-based contract was signed on 20 November 2015, and closed as of
31 December 2019. The PSC will also submit the Project Completion Report (PCR) after all
physical works on the main canal and the CAD works along filed irrigation canals (FICs) are
completed.
15. Further, as per the Facility Administration Manual (FAM) for KISWRMIP, SMEC provided
services through its various experts for the Tranche 1 project, that is, the Gondi Modernization
project. The Support Services Team (SST) of the PSC is located in Bhadravathi and is
1 Now part of Singapore-based Surbana Jurong group.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 4
provided outreach services such as providing training, capacity building and handholding
support to the Water Users Cooperative Societies (WUCS). The PSC has also prepared the
feasibility study report (FSR) and the bid document for Tranche 2-Vijayanagara Channels
(VNC).
16. The Program implementation arrangement is in place and as shown in Figure 3.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 5
Figure 3: Implementation arrangement for KISWRMIP
Karnataka IWRM Steering Committee (IWRMSC)
Chairperson: Chief Secretary
Program Coordination Committee (PCC)
Chairperson: Principal Secretary, GoK
Client
Karnataka Neeravari Nigam Ltd (KNNL)
Program Management Unit (PMU)
Program Director
Project Implementation Office (PIO)
Tranche 1: Chief Engineer, UTP (Shimoga)
Tranche 2 & TLBC: Chief Engineer, ICZ,
Tungabhadra Project (Munirabad)
Asian Development Bank
(ADB)
ACIWRM
IWRM Consultant
State Water Institutions
(WALMI, KERS, RICM)
Project Support Consultant (PSC)
TL, DTL and Experts
Support Services Team (SST)
Modernization
Contractor
Command Area Development
Authority (CADA)
Water Users Cooperative
Societies (WUCS)
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 6
17. The PMU staff position as of 31 December 2019 is given in Table 1.
Table 1: PMU Staff position as of 31 December 2019
S. No. Name Designation
1 Mallikarjuna B Gunge Program Director
2 Venkatesh Prasad Superintending Engineer (i/c)
Budget/ Administration Cell
3 N. Ravindran General Manager (Finance)
4 Sindhu Finance Assistant
Monitoring Management Cell
5 Chidambarsawamy Program Officer (Additional charge)
6 Vacant MIS & GIS Communication Expert (Additional charge)
Irrigation Management Cell
7 Venkatesh Prasad Executive Engineer (Project Branch)
8 Chidambaraswamy Technical Assistant
9 C Yadukumar Assistant Engineer
10 CB Niranjan Assistant Engineer
11 PRM Sharma EAP Consultant (part time)
18. This is the Annual Progress Report (APR) for the period January-December 2019 prepared
by PSC which covers key programmatic achievements, major events (meetings, workshops,
trainings) held, learnings from the project and key challenges faced. This will be followed by
a Project Completion Report (PCR) till March 2020.
19. During January-December 2019 reporting period, the ADB Director SAER visited KNNL
Bengaluru during 3-4 July 2019 and met with KNNL and GoK officers in the context of delay
in loan process. The major delay in obtaining approval letter from finance department was
solved, and the letter was handed over to her. In view of the low budget balance after meeting
Tranche 1 and 2 expenses/estimate, KNNL and ADB Mission discussed and agreed to
consider TLBC as a separate MFF.
Project Basic Data
20. The KISWRMIP project basic data is given in Table 2.
Table 2: Project Basic Data
Project Basic Data
1 Name of the Project Karnataka Integrated and Sustainable Water Resources Management Investment
Program (KISWRMIP)
2 Project Number MFF 0085: Loan 3172 IND
3 Sector Agriculture & Natural Resources
4 Financial Plan for
MFF 2014-2021
ADB $150 million, GoK $75 million; Total $225 million
(ADB INR750 Cr, GoK INR375 Cr; Total INR1125 Cr) @INR50/$
5 First Tranche
2014-2019
ADB $26 million, GoK $14.25 million; Total $40.25 million
(ADB INR176.904 Cr, GoK INR96.957 Cr; Total INR273.861 Cr) @INR68.04/$
(i) Loan Signed on 07 May 2015
(ii) Loan effective from 13 July 2015
(iii) Loan Closing Date Project 1: 31 December 2019; investment program financial closing 30 July 2024.
CHECK
(iv) Executing Agency Water Resources Department of Karnataka through
(Karnataka Neeravari Nigam Limited)
(v) Implementing
Agencies Karnataka Neeravari Nigam Limited & Advanced Centre for IWRM
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 7
Project Basic Data
6 Goals & Objectives The Project aims to manage and sustain the increasingly scarce water resources
in the selected river basins in Karnataka.
7 Activities involved (i) State and basin institutions strengthened for IWRM (by ACIWRM)
(Strengthening the relevant institutions, specifically the Advanced Centre for
IWRM (ACIWRM) for advancing policy review, river basin management, water
resources information systems establishment).
(ii) Irrigation system infrastructure and management modernized (by KNNL).
a. Modernization of irrigation system infrastructure including strengthening
of Water Users Cooperative Societies (WUCS), installation of telemetry
for canal flow measurement of three irrigation projects within the
Tungabhadra sub-basin (Gondi Project under Tranche 1, Vijayanagara
Channels (VNC) Project under Tranche 2 and Tungabhadra Left Bank
Canal (TLBC);
b. Strengthening asset management and main system operation and
maintenance (O&M), and
c. Capacity building of inclusive WUCS with women representation, for
improved operation, maintenance and water management within their
respective command areas.
(iii) Project and management systems operational (KNNL & ACIWRM).
8 Outcomes of the
project
Improved water resources management in the Tungabhadra sub-basin in
Karnataka (Institutional Strengthening, International Best Practices, sub-basin
Planning, Decision Support systems etc.).
9 Status of Physical Progress of Procurements
(i) Modernization of
Gondi Main Canal
and Distributaries
Contract awarded-Work completed.
Tender Value: INR1,289,539,262.00 (112,21,88,261.00+16,73,51,001 (EFI))
(ii) Flow Measurement &
Telemetry System
Contract Awarded- Work Under Progress
Tender Value: INR2,81,50,161.00 + Euro 1,945,020.00
(iii) Project Support
Consultants
Contract Awarded- Work Under Progress
Tender Value: INR10,42,79,758.00 + AUD 644,392.00 + USD 602,051.00
10a. Financial Progress: Cumulative Expenditure and Disbursement up to December 2016
(i)
Reimbursement Target to be achieved
as per ADB for CY 2016 (As agreed in
Jan 30-31, 2016 TPRM)
Q1
Jan-Mar
Q2
Apr-Jun
Q3
Jul-Sep
Q4
Oct-Dec
Total
(cumulative)
(($, in Millions) 0.6 0.7 3.2 1.1 5.6
@ 1$ ≈ INR65.5540
(INR, in Crores) 3.933 4.588 20.977 7.211 36.709
(ii) Amount reimbursed till Dec-2016 (INR
in Crores) - - 17.95 7.030 24.980
(iii) Achievement vis-à-vis target (%) - - 60.85 68.05 68.05
10b. Financial Progress: Cumulative Expenditure and Disbursement during January-December 2017
(i)
Reimbursement Target to be
achieved as per ADB for CY 2017
(As agreed in Apr 6-7, 2017 TPRM)
Q1
Jan-Mar
Q2
Apr-Jun
Q3
Jul-Sep
Q4
Oct-Dec
Total
(cumulative)
($ in millions) 1.3 1.4 0.6 1.3 4.6
@ 1 $≈ INR65.5540
(in Crores) 8.830 9.538 3.959 8.856 31.180
(ii) Amount reimbursed till March 2017
(in Crores) 9.354 16.02 13.094 10.78 49.25
(iii) Achievement vis-a-vis target (%) 106.00 168.04 330.74 121.72 157.95
10c. Financial Progress: Cumulative Expenditure and Disbursement during January-December 2018
(i) Reimbursement Target for CY 2018,
as agreed during the first Tri-partite
Q1
Jan-Mar
Q2
Apr-Jun
Q3
Jul-Sep
Q4
Oct-Dec
Total
(Cumulative)
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 8
Project Basic Data
Portfolio Review Meeting (TPRM) of
2018 (19-20 Feb 2018)
($ in Millions) 1.3 1.4 0.6 1.3 4.6
@ 1 $≈ INR65.5540 (in Crores) 19.67 22.26 22.79 6.74 71.46
(ii) Amount reimbursed till December
2018 (INR in Crores) 12.99 8.82 9.30 7.93 39.04
(iii) Achievement vis-a-vis target (%) 66.04 39.62 40.80 117.65 54.63
10d. Financial Progress: Cumulative Expenditure and Disbursement during January-December 2019
(i)
Reimbursement Target for CY 2019, as
agreed during the first Tri-partite
Portfolio Review Meeting (TPRM) of
2019 (29 Mar 2019)
Q1
Jan-Mar
Q2
Apr-Jun
Q3
Jul-Sep
Q4
Oct-Dec
Total
(Cumulative)
@ 1 $≈ INR65.5540 (in Crores) 38.71 10.19 14.16 9.57 72.63
(ii) Amount reimbursed till December 2018
(INR in Crores) 1.47 11.17 14.48 11.77 38.89
(iii) Achievement vis-a-vis target (%) 3.8 109.62 102.26 122.98 53.54
Project Review meetings
11 Tripartite Review
Meetings
a) 07 December 2015, Delhi
b) 30-31 January 2016, Jaipur
c) 16-17 September 2016, Delhi
d) 6-7 April 2017, Delhi
e) 26-27 October 2017, Bengaluru
f) 19-20 February 2018, Bengaluru
g) 25-26 October 2018, Visakhapatnam
h) 28-29 March 2019, Goa
i) 3-4 October 2019, Cochin, Kerala State
12 ADB Missions a) Special Project Administration Mission - 27 to 28 July 2015
b) Loan Inception Mission – 6 to 10 November 2015
c) Loan Review Mission - 26 April to 5 May 2016
d) Loan Review Mission – 17 to 25 November 2016
e) Loan Review Mission – 2 to 12 May 2017
f) Loan Review Mission – 12 to 19 February 2018
g) Loan Preparedness Review Mission Tranche 2, 28-29 June 2018
h) Fact Finding Mission Tranche 2, 28-29 June 2018
i) Tranche Review Mission and Tranche 2 Consultation Mission, 30 Jan to 15
Feb 2019
j) Loan Review Mission and Loan Consultation Mission, 19-29 November-2019.
13 Project Coordination
Committee (PCC)
k) Constituted vide Govt. Order no. WRD 51 MBI 2015 (P1) Dt. 27 Nov 2015
14 Externally Aided
Project Monitoring
Committee meeting
under the
Chairmanship of
Additional Chief
Secretary to Govt.
a) 1st Meeting held on 06 August 2015
b) 2nd Meeting held on 07 January 2016
c) 3rd Meeting held on 30 May 2016
d) 4th Meeting held on 6 August 2016
e) 5th Meeting held on 12 January 2017
f) 6th Meeting held on 31 August 2017
g) 7th Meeting held on 11 May 2018
h) 8th Meeting held on 20 Aug 2018
Utilisation of Funds
Contract Awards
21. The details of contracts awarded so far under Project 1 are given in Table 3. The contract
award data is exclusive of ACIWRM part.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 9
Table 3: Contract award under Project 1
Procurement Item Contract Amount Date of
Award
ADB
Financing
Gondi NCB-1
Main Canal and Distributaries, Earth work lining, structures and flow measurement devices.
INR112,21,88,261.00
INR16,73,51,001.00
26-02-2016
12.04.2018 74%
ICB-2
Flow Measurement, Telemetry–Supply & Installation (FMT-ICB-2)
INR2,81,50,161.00 + Euro 1,945,020.00
23-11-2015 82%
PSC-1
Program Support Consultants (including WUCS strengthening support)
INR10,42,79,758.00 + AUD 644,392.00
+ USD 602,051.00
a. * Variation for SST-INR1,92,17,500 (US$293,155)
b. Variation for Biodiversity expert-INR3,50,000(US$5339)
c. Variation for Gondi WUCS strengthening-INR1,25,35,666 (US$191,227)
d. Variation for GIS asset management system-INR1,06,07,400 (US$161,812)
20-11- 2015 85%
EFFM 5
Effects Monitoring Recruitment of Effects Monitoring Consultant is kept on hold.
Gondi DC Multiple Lots
Command Area
Development works
All the 243 CAD packages at an estimated cost of INR4277.20 lakhs awarded. (Table 17)
74%
*As per contract variation No. 1-07-08/2018 dated 27 August 2018.
Disbursements
22. The disbursements under Project 1 up to December 2019 are given in Table 4.
Table 4: Details of disbursement under the Project 1
S. No..
Agency/Contractor Work Reimbursed Amt
(INR)
1 SMEC (India) Pvt Ltd PSC-1 132,065,021.00
2 SMEC International Pty Ltd., PSC-1 21,785,579.43
3 RPP Infra Project Ltd. Gondi-NCB-1 914,399,733.00
4 Hydro Vision & Canarys Automation FMT-ICB-2 131,389,021.00
5 Water Users Co-operative Societies WUCS 104,166,016.42
Total 1,303,805,370.85
Re-estimated costs to completion: INR16.73 Crores EFI
Design Monitoring Framework Indicators
23. The physical progress under Project 1 as per Design and Monitoring Framework (DMF) of
KISWRMIP is given in Table 5.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 10
Table 5: Status of DMF for Project 1
Item Performance Targets and
Indicators with Baseline Status as of 31 December 2018
Output 2 Target Status
Irrigation system infrastructure and management modernized
• 123 km of irrigation canal upgraded at Gondi irrigation subproject to serve 4,600 ha command area
Gondi Civil works contract (GONDI-NCB-1) awarded to M/s RPP Infra Projects Ltd. for INR 112.22 Cr. on 26 Feb 2016 and an EFI of INR16.73 Cr. on 12 April 2018, thus taking the total contract award to INR128.95 crores. A total of 112.515 km out of 115.079 km has been completed. Balance is savings as explained below:
In LBC, 0.535 km is considered not needed. In RBC, 2.029 km is tanks portion and balance of a few structures like sopanam. as these are considered not needed; savings in quantity equivalent to 2.564 km was made.
• Lining of GLBC: Completed. 14.20 km of GLBC out of 14.735 km completed; remaining is considered not needed. Hence, 100% lining of GLBC is achieved. All 74 structures are completed.
• Lining of GRBC: 72.21 km of GRBC out of 74.24 km has been completed. Out of 392 structures, 385 completed.
• Distributaries Lining: Completed. Out of 26.096 km (of GRBC), 26.096 km completed. All 212 structures completed.
• Renovation of Division Office, Bhadravathi: completed.
• Anicut repair and Security office works: completed.
• Gondi irrigation subproject main-system asset management (operation and maintenance) plan developed (baseline = 0)
• GIS based asset management completed and operational. Data updation related to modernization works is pending as civil works extended till 31 December 2019.
• Telemetry systems operational for at least 100 locations within the sub-basin.
• Installation of 91 out of 100 systems completed. Remaining will be taken up after completion of modernization of VNC (Table 11).
• At least 7 WUCS operating and maintaining transferred systems
• Trainings on Management transfer to WUCS completed. O&M Manual is ready and was used in trainings. Irrigation Management Transfer could not happen as both KNNL engineers and WUCS were fully engaged in the modernization works and WUCS CAD packages respectively. For IMT, all works should be completed which was
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 11
Item Performance Targets and
Indicators with Baseline Status as of 31 December 2018
not the case. Hence, IMT could not be initiated.
Output 3
Project and management systems operational
• KNNL approves annual work plan within 30 days of receipt
• PMU is operational
• Contract award and disbursement project versus actual
• PMU is operational.
• As per ADB aide memoire of 19-29 November 2019, the Project rating is “on track”.
• Cumulative contract awards amount to $25.782mn against $26mn of loan amount. Cumulative disbursements are at $24.151mn.
Agreed Action Points from Aide memoire
24. The agreed action points from the 19-29 November 2019 aide memoire and the status as of
reporting are given in Table 6.
Table 6: Agreed Time-bound Actions
Activity By Whom Due Date Remarks
Confirmation of aide
memoire
DEA/
ACIWRM/
KNNL
20-Dec-2019 To be submitted
Output 1: State and basin institutions strengthened for IWRM
Approval and ratification of
the state water policy WRD 31-Dec-19
Draft Cabinet Note circulated by Water
Resources Department to all
stakeholder departments agreed by all
the departments. Awaiting cabinet
approval.
Complete IWRM trainings
under Tranche 1 ACIWRM 31-Dec-19
Two IWRM trainings were conducted
during November-December 2019. 60
WRD engineers trained of which 28
constitute women.
Submit ToR and cost
estimate for firm to
implement TLBC land and
water management
ACIWRM 31-Dec-19
ToR submitted on 13 December 2020;
comments from ADB addressed. ToR
re-submitted to ADB on 17 April 2020.
Cabinet endorsement of
Tungabhadra River Basin
Plan
ACIWRM 30-Mar-2020
After consultation with stakeholder
department, cabinet note is under
preparation. Will be submitted to cabinet
by 30 June 2020.
Output 2: Irrigation system infrastructure and management modernized Tranche 1
Submit plans to ADB for (i) Decommissioning the
campsite and batching plant and
(ii) Rehabilitation of the borrow pits
KNNL 16-Dec-19
The civil works continued till 31
December 2019; patchworks continued
into the first quarter of 2020 also.
Contractor has been asked to submit the
plans.
Complete all works activities
(Gondi main works and
WUCS)
KNNL 31-Dec-19
Completed; patchworks and a few
structures, and closing actions continued
into the Jan-Mar 2020 quarter. The
lockdown situation delayed the works
further.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 12
Activity By Whom Due Date Remarks
Operationalize Gondi Asset
Management Plan KNNL 31-Dec-19
Gondi Asset Management Plan is
operational. However, data of
modernization works is to be updated.
Delayed due to lockdown.
Submit SMR for 2019 KNNL 31-Jan-2020
ADB comments on draft SMR for Jan-
Dec 2019 received and addressed; final
version approved by ADB. SMR
uploaded on ADB and KNNL websites.
Tranche 2
Submit VNC Package 1
CEMP to ADB KNNL 6-Dec-19
The CEMP approved by CE submitted to
PMU, KNNL RO for onward submission
to ADB.
Submit ToR and cost
estimate for external
environment safeguards
monitoring expert to ADB
KNNL 13-Dec-2019 Submitted to MD KNNL office.
Under process for posting on CSRN.
Finalize the GRM register KNNL 31-Dec-2019
Registers will be installed when
modernization works begin after
lockdown situation, likely in May. GRC
committees being formalised for 9
channels; project level committee being
formalised.
Submit draft VNC Package 2
bid document to ADB KNNL 6-Jan-2020
Estimate and Schedule B under
preparation.
Submit May-Dec 2019 SMR
to ADB KNNL 31-Jan-2020
Submitted; comments from ADB
complied; revised version under ADB
review.
Submit Jan-Jun 2020 SMR
to ADB KNNL 30-Jul-2020 Not due.
SWLB & NBWL clearance for
working in TOCR KNNL 30-Sep-2020
SBWL cleared on 9 Mar 2020. Awaiting
proceedings.
Output 3: Project and management systems operational
Submit WAs for $1.3 million
to CAAA (Tranche 1) KNNL 5-Dec-2019
Reimbursement approximate $ 3.778MN
as of April 2020.
Submit WAs for $0.5 million
to CAAA (Tranche 1) ACIWRM 5-Dec-2019
2 Withdrawal applications amounting to
INR30,141,087 and 2 Withdrawal
applications amounting to
USD184,902.72 submitted to ADB on 13
December 2019.
PSC 2 ToR and cost
estimate to ADB KNNL 15-Dec-2019
CSRN published on ADB’s CMS
Website on 17 April 2020
Submit negotiated draft PSC
1 contract amendment to
ADB
KNNL 15-Dec-2019 Under process.
Submission of new contracts
or requests for variations to
existing contracts for
Tranche 1
ACIWRM/
KNNL 15-Dec-2019
Contract variation of M/s GUBBI LABS
for printing of ACIWRM reports and
brochures submitted to ADB on 10
December 2020 and approval is
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 13
Activity By Whom Due Date Remarks
obtained from ADB on 12 December
2019.
Submit to ADB KNNL’s FYE
2019 APFC to ADB (Tranche
1)
KNNL 31-Dec-2019 Will be submitted in September 2020.
Submit copy of signed VNC
Package contract to ADB
(Tranche 1)
KNNL 31-Dec-2019 Will be submitted to ADB by first week of
May 2020.
Submit copy of signed VNC
Package contract to ADB KNNL
Upon loan
Effectiveness
Will be submitted to ADB by first week of
May 2020.
Submit WAs for $1.9 million
to CAAA (Tranche 2) KNNL
Upon loan
Effectiveness
Reimbursement for the expenditure
incurred against mobilisation advance
paid to VNC contractor will be submitted
upon withdrawal of lockdown in
Karnataka.
Submit PCR for Tranche 1 to
ADB
ACIWRM/
KNNL 31-Mar-2020
Will be submitted in July 2020. Delayed
due to lockdown situation.
Submit ACIWRM and KNNL
FYE 2020 APFC (Tranche 1)
ACIWRM/
KNNL 31-Mar-2020
Will be submitted to ADB in September
2020.
Submit all final WAs for
Tranche 1
KNNL/
ACIWRM 30-Apr-2020 Will be submitted in June 2020.
Meet 2020 quarterly contract
award and disbursement
targets.
ACIWRM/
KNNL Quarterly Action taken as per the agreed targets.
Deliverables of Project 1-Status
25. Table 7 gives the status of reports due and submitted by PSC.
Table 7: Important deliverables for Project-1 activities
S.No. Report Deadline Status
1 Inception Report Draft submitted within 2 months of
mobilization and finalized within 3
months of mobilization
Submitted.
2 Quarterly
Progress Reports
Within 30 days of the end of each
quarter
On track.
3 Annual Reports Within 30 days of the end of each
calendar year
This APR is slightly delayed due
to delay in award of Tranche 2
PSC Part A, and the
accompanying PSC office
shifting and other tasks; currently
lockdown is declared by GoI and
GoK due to Corona virus.
4 Midterm Report Middle of year 2 for Project 1 Submitted to KNNL on 31
December 2017.
5 Project
Completion
Report
Draft submitted 3 months prior to
Project completion and finalization by
31 March 2020.
Due in April/May 2019.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 14
S.No. Report Deadline Status
Delayed due to national
lockdown declared in view of
Corona virus.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 15
2 GONDI IRRIGATION SYSTEM
26. Gondi canal modernisation civil works contract became effective from 26 February 2016 and
scheduled to be completed by 31 December 2018. The contractor initially set up two offices
near Bhadravathi town and near DB Halli sub-division office. A quality control laboratory has
been established in the Bhadravathi town office. Concrete batching plants have been
established in both the site offices. The canal closure period is generally during May and
December/January, which may be altered by KNNL in consultation with the Irrigation
Consultative Committee, taking into consideration the local irrigation water requirements.
27. During the reporting period, two canal closures were possible during May-Jun 2019 and Dec
2019. However, very little could be carried out during the May-Jun closure period because of
(i) non-availability of gravel for canal sectioning within the lead area and (ii) regular and
intermittent rains resulting in the soil being saturated. In addition, seepage from Bhadra canal
system hampered the work. Hence, balance works on RBC were completed during the
second and final closure of the project in December 2019 which was also the physical works
closing date. The contractor still has to complete some patchworks and small structures;
closing actions will follow after completion of all such works, likely during second quarter.
28. The contractor has closed one office near DB Halli sub-division office and concrete batching
plant as of this reporting. Another one in Kodihalli will be closed by March 2020.
Overall Physical and Financial Progress
29. The overall physical and financial progress is captured in the S Curves (Figures 4 & 5),
followed by detailed description of physical and financial progress, item wise. Initially, the
contractor was awarded the work at an estimated cost of INR112.21 Crores. However, in
2018 there was an increase in quantity of certain items due to embankment issues. Hence,
an EFI for additional quantities amounting to INR16.73 Crores was submitted by KNNL and
approved by ADB
30. The S Curve presented in Figures 4 and 5 are prepared for program quantity/financial value
versus progress respectively for the project extension period, that is, from March to December
2019. It was complicated to prepare one combined S-curve for the original project duration
and the extended duration together because the program will be different for both periods.
Hence, for the project extension period, S-curves are prepared using data applicable for the
extension period. This was explained in the QPR of Apr-Jun 2019.
31. The S curve for Mar-Dec 2019 is drawn for progress against quantity (Figure 4). Here, the
progress was 66% physical and 95% financial. The shortfall in physical progress implies a
saving in the quantity of material during the extension period. For example, savings were
made in the BS Slab for sopana and 2.03 km length of lining quantity in the tanks portion
which was considered not required.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 16
Figure 4: S Curve: Physical Program and Progress under Gondi Irrigation System Modernization for balance works
Data source: KNNL Divisional Office, Bhadravathi
0 0 0 0 0
7
31
68 68 68 68 68 68 68 68 68 68
82
100 100
7 7
18 18
27 27 27 27 27 27 27 27 27
45
66
0
20
40
60
80
100
120
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2019
Per
cen
tage
pro
gres
s
Construction Period (month)
Program
Progress
Gondi: Physical Program and Progress (From January to December 2019)
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 17
Figure 5: S Curve: Financial Program and Progress under Gondi Irrigation System Modernization for balance of works
Data source: KNNL Divisional Office, Bhadravathi.
0 0 0 0 0
7
28
57 57 57 57 57 57 57 57 57 57
70
100 100
0 0 0 0 0
10 10
2323
35 35 35 35 35 35 35 3535
71
95
0
50
100
150
200
250
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2019
Fin
anci
al V
alu
e (
INR
, mill
ion
)
Construction Period (month)
Program
Progress
Gondi : Financial Program and Progress (January to December 2019)
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 18
Physical Progress-Civil Works
32. The physical progress as of 31 December 2019 is as follows:
• Out of 14.74 km of lining of GLBC 14.20 km has been completed. For the remaining
0.54 km, bottom concreting is done and sideways lining is considered not required
because of the presence of hard rock. Hence, LBC modernization work is considered
completed. Out of 74 structures, 81 completed;
• Out of 74.24 km of lining of GRBC, 72.21 km has been completed. For the remaining
2.08 km is pending because 6 Tanks are falling in this portion. Hence a total of 2.08 Km
lining is considered not required. Out of 392 structures, 385 are completed. Remaining
7 structures are constructed in LBC as per requirement, and
• Lining of entire 26.10 km of distributaries along GRBC is completed. All the 212
structures are also completed.
Table 8: Physical Progress as of 31 December 2019
S. No.
Item of work Lining (km) Achieved Structures (no.) Achieved
Estimated Achieved % Estimated Achieved %
1 Left Bank Canal 14.74 14.20 100 74 81 100
2 Right Bank Canal 74.24 72.21 97.26 392 385 98.21
3 Distributary 26.10 26.10 100 212 212 100
14
.74
74
.24
26
.10
14
.20
72
.21
26
.10
10
0.0
0
97
.27
10
0.0
0
L e f t B a n k C a n a l R i g h t B a n k C a n a l D i s t r i b u t a r y
Physical Progress: Lining
Lining (km) Estimate Lining (km) Achieved Achieved %
74
39
2
21
2
81
38
5
21
2
10
0.0
0
98
.21
10
0.0
0
L e f t B a n k C a n a l R i g h t B a n k C a n a l D i s t r i b u t a r y
Physical Progress: Structures
Structures (nos.) Estimate Structures (nos.) Achieved Achieved %
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 19
Divisional office improvements
33. Repairs and improvements to the existing divisional office building at Bhadravathi have been
completed and the office has started functioning in the renovated building since December
2016. Work is completed and full payment of INR61.882 lakhs has been released.
Aqueduct repairs
Repairs to all the three aqueducts are completed. Payment released INR218.01 lakhs. The
aqueduct work is completed.
Security office & anicut repairs
Left bank and Right bank security office and anicut repair works are completed as of this
reporting.
Financial progress
Agreed contract value for civil works of Gondi Irrigation system is INR128.95 crores (including
EFI). As of 31 December 2019, an amount of INR127.69 crores has been released.
Table 9: Financial progress as of 31 December 2019
S. No.
Item of work Lining (INR crores) Achieved
(%) Structures (INR crores) Achieved (%)
Estimated Achieved Estimated Achieved
1 Left Bank
Canal 8.9 8.77 98.54 1.76 2.03 100
2 Right Bank
Canal 82.71 82.39 99.61 27.97 26.99 96.50
3 Distributary 5.42 5.33 98.34 2.18 2.18 100
8.9
82
.71
5.4
2
8.7
7
82
.39
5.3
3
98
.54
99
.61
98
.34
Left Bank Canal Right Bank Canal Distributary
Financial Progress: Lining
Lining (crore) Estimate Lining (crore) Achieved Achieved %
1.7
6 27
.97
2.1
8
1.7
6 26
.99
2.1
8
10
0.0
0
96
.50
10
0.0
0
Left Bank Canal Right Bank Canal Distributary
Financial Progress: Structures
Structures (crore) Estimate Structures (crore) Achieved Achieved %
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 20
Flow Measurement and Telemetry System
34. The contract for flow measurement and supply and installation of telemetry that was awarded
to M/s Hydro Vision GmbH in JV with Canarys Automation Pvt Ltd on 23 November 2015 is
91% completed as of 3rd quarter of 2019. The contract period is 24 months for supply and
installation plus 5-year of operation and maintenance. The proposed distribution of flow
measurement equipment in Project 1 is listed in Table 10. Out of these, 91 stations have
been installed as of 30 September 2019 which includes 13 Radar flow meters in Gondi
Irrigation Project (Table 11). The balances 9 are planned for utilization in the VNC project.
35. During 2019, M/s Canarys have installed 9 Radar flow meters. However, the final cross
section will be added after the canal flow stops during the canal closure period in December
2019. One Automatic Weather Station (AWS) has been installed at DB Halli sub-division
office premises of KNNL during the reporting period. Thus, all the flow meters and one AWS
earmarked for the Gondi command area have been installed. The balance flow meters and
AWS available will be installed in the VNC and TLBC project areas. The server room set up
at Chief Engineer UTP office in Shimoga is also completed and receiving data regularly and
being monitored both by KNNL engineers and representatives of M/s Canarys.
Table 10: Equipment details for flow measurement in Tungabhadra Sub-basin
Component Required quantity
Remarks
Transit Time flow meters – full system 24 Travel time flow meters
Rader Flow meters – full system 76 Surface velocity flow meters
Hand Held ADCPs 3 For velocity profile and distribution in the cross section Boat Mounted ADCPs 1
Hand Held Military grade tablet PCs 4 Field configurations
Automatic weathers stations – rain, temp, humidity, solar radiations, atmospheric pressure, wind direction and speed
6 Weather parameters in command area
Solar panel 100 watts, charge controller, batteries 65 Ah – 100 Ah
100 Powering the instruments
Sheds with steel doors and mounting cantilever 100 Protection and storage of instruments
GSM/GPRS Telemetry data transmission modems/ SIM cards to be purchased in the name of KNNL
100 Data transmissions
Physical Progress-Telemetry
36. All the 100 locations for telemetry stations in the Tungabhadra basin have been identified
including 20 locations in the Gondi system. A KNNL Quality Inspection Team visited Germany
for learning about quality inspection. The Telemetry equipment was shifted to the project
location in the month of June 2016. Table 11 gives the status as of 31 December 2019.
Financial Progress-Telemetry
37. Out of the contract value of INR2.81 crores and Euro 1.94 million, an expenditure of INR0.914
crores (47%) and Euro 1.94 million (100%) has been incurred. The balance in INR is for
maintenance over four years of the project duration, which is yet to be settled.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 21
Table 11: Installation of Telemetry Systems-Status as of 31 December 2019
S.
No. Project Quantity Instrument type Security shed status
Flow Meter
Installation
Status
Solar power-
status
Installation
calibration
Data
Transmission
1 Bhadra 10 Transit Time Flow Completed Completed Completed Completed Completed
2 Bhadra 39 Radar Flow meters Completed Completed Completed Completed Completed
3 Gondi 13 Radar Flow meters
4 numbers completed and commissioned. Data is also being relayed from these stations.
After the joint team of KNNL engineers, Canary’s team and PSC team visited and
finalised the sites remaining 9 stations are installed. Adding final cross section is required
to be done which will be taken up when canal flow stops.
4 Upper Tunga Project 6 Transit Time Flow meters Completed Completed Completed Completed Tests completed
5 Upper Tunga Project 5 Radar Flow meters Completed Completed Completed Completed Tests completed
6 Singtaluru LIS 3 Transit Time Flow meters Completed Completed Completed Completed Completed
7 Singtaluru LIS 10 Radar Flow meters Completed Completed Completed Completed Completed
8 Tungabhadra 5 Transit Time Flow meters
locations 1, 2, 3, 4, 12 Completed Completed Completed Completed Completed
9 Tungabhadra Items 6, 7, 8, 9, 10 are SLIS project related and are completed & shown 6/7 Singataluru LIS and are completed
10 Tungabhadra - 1 no. 0 Transit Time Flow meters
location 11
Location 11-site is not suitable as the bed and side slopes/banks are of earth/mud and
not concrete, sensors could not be fixed. There is plan for this canal is to be modernised
in the coming summer.
11 Tungabhadra - 1 no. 0 Radar Flow meters Site is not suitable as the flow rate is very low and the volume conveyed is low.
12 Vijayanagara
Channels-16 nos. 0 Radar Flow meters
Hydro Vision has communicated to M.D, CE ICZ, and EE BRLBC about the poor
condition of VJN canals due to which installation of flow meters is considered not
feasible.
Completed so far 91 Note: It was suggested to utilize balance 9 Flow Meter Instruments in the Bhadra Right Bank Canal Project.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 22
Water Users Cooperative Societies
38. The role of Water Users Cooperative Societies (WUCS) is critical to the success of a
Participatory Irrigation Management project. The three core functions of WUCS are: (i)
ensuring equitable distribution of water to farmers; (ii) Operation & Maintenance of canal
system; and (iii) collection of irrigation water charges. To ensure that WUCS perform these
tasks efficiently and effectively, PSC continued employing social mobilization techniques and
processes towards enhancing their skills, capacities and capabilities.
Baseline Assessment of WUCS2
39. Baseline Assessment is used as a means to monitor change in the performance of WUCS
against select 29 parameters. During the reporting period, the thirteenth and the project final
baseline assessment has been conducted December 2019 and the findings provided in
Annexure 1. Some of the parameters are one-time activities. While all the WUCS have
completed the one-time activities, there are shifts in terms of the recurring activities. For
example, the water tax collection, O&M activity, GRM register maintenance etc. are regularly
done by a few WUCS, while others need a reminder to complete the same. With the
Federation becoming more active these and the other recurring activities are expected to
happen regularly.
40. During the reporting year, PSC conducted several meetings with the Federation in motivating
the members to drive the WUCS towards achieving all the objectives of the project. A
significant momentum picked up towards the closing phase of the project; the Gondi
Modernization WhatsApp group updates show that the trend is continuing. This is a very
encouraging sign in terms of institutional strengthening.
41. The following is a list of points reviewed at each of the meetings with the individual WUCS as
also the Federation:
• Educating and facilitating the WUCS to hold regular and periodic meetings,
recording the minutes of the proceedings, maintaining the registers as per bye-laws,
maintenance of records, auditing etc;
• Reviewing the progress of CAD works and deciding the works that are not needed
and informing the CADA section officers to finalize the bills;
• Motivating the leaders to take up issues/conflicts at WUCS/Federation level for early
resolution;
• Brainstorming to find ways of setting up revenue models for individual WUCS as
also the Federation for their sustainability;
• Driving the need for crop water planning, water management, canal O&M, water tax
collection etc.;
• Inviting women members to attend the Board meetings;
• Highlighting some of the livelihood activities initiated by PSC and how they can be
scaled up to increase revenues/ provide livelihood to more women, and
• Exhorting the need for Federation to play a lead role in steering the WUCS towards
sustainability.
2 It may be noted that there was no preparatory phase planned in the project. The civil works and other activities started right from the beginning. Since social processes take time, PSC had to struggle right from identifying the WUCS to their capacity building and institutional building, and execution of CAD packages through WUCS. The project was closed on 31 December 2019, when the overwhelming opinion was that an extension of at least a year would have brought the project to its logical close. In spite of all these severe constraints, most of the WUCS and the Gondi Federation have good leadership and are performing well.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 23
42. The following sections describe the progress of key activities related to WUCS Institutional
Strengthening.
Shareholder Enrolment in WUCS
43. Table 12 gives the progress at the end of the reporting year in terms of shareholder enrolment
as members.
Table 12: WUCS-wise total farmers and shareholders as of 31 December 2019
Name of the WUCS
Total No. of farmers
No. of Shareholders as of
September 2019
No. of Shareholders
as of December 2019
Membership as of December 2019
(%)
Doddagoppenhalli 371 238 238 64.42
Baranduru 600 254 254 42.33
Seegebagi 300 223 228 76.00
Baballi 644 242 242 37.57
Kagekodamagge 439 372 373 84.96
Tallikatte 359 313 313 87.20
Nagatibelagalu 575 294 294 51.13
Dasarakallahalli 510 320 320 62.70
Koppadoddakere 622 341 368 59.16
Mudlavittalapura 280 152 157 56.07
Holehonnuru 275 240 240 87.30
Total 4975 2989 3027 60.84
44. It may be noted that the total number of farmers increased from 4830 to 4975 due to division
of land and also updating of the khatedar list from revenue department records. The total
number of members enrolled in WUCS as of 31 December 2018 was 2965 which has grown
marginally to 2989 as of 31 December 2019. The key reason for the poor increase is the pre-
occupation of all the WUCS office bearers with the CAD works and building works by the
close of the project duration which was 31 December 2019. They have promised to address
this matter and increase the membership after completion of the CAD works.
WUCS Membership Drive and One-time Grant
45. To make Gondi WUCS vibrant, PSC continued to work for increasing the number of active
members with a view to enhancing not only their participation but also the amount of
shareholders fee collected (Table 13) to leverage one-time grant from CADA. There is
gradual increase in both the number of shareholders and the fee collected. The shareholders
fee also helps in leveraging higher mobilization amount from CADA at the rate of INR1200/-
per hectare (INR120/ha (farmer)+ INR1080/ha (CADA)) by each farmer. The higher amount
thus collected is usually held in a bank as deposit which also fetches interest. Since 2014-15,
CADA has banned use of interest proceeds for salary payment to secretaries or for office
expenses. The interest may be used for administrative expenses of WUCS.
46. Table 13 indicates the status of one-time grant received by WUCS from CADA. However,
compared with the previous reporting periods there is not much of change in the figures as:
(i) the WUCS could enrol only a small number of members since last 2018 and (ii) CADA did
not release any amount as they are yet to receive grants from the Government.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 24
Table 13: WUCS Membership and One-time Grant as of 31 December 2019
S. No. Name of WUCS Total
Members
Membership Strength Membership Contribution (INR)
Mobilized by WUCS CADA
grant (INR.)
Total
Before September
2016*
As of 31 Dec.
2019
Before Sep-2016*
As of 31 Dec
2019
Amount
(INR)
Before Sep 2016
As of 31 Dec
2019
1 Doddagoppena
Halli 371 0 237 0 17,000 18,794 169,150 187,944 187,944
2 Baranduru 600 98 254 0 27,000 27,463 247,169 274,632 274,632
3 Seegebagi 300 140 220 14,000 27,000 27,000 243,000 270,000 270,000
4 Baballi 544 242 242 0 29,000 288,000 259,200 277,000 547,200
5 Kagekodamagge 439 270 366 32,962 32,962 32,962 269,168 32,962 302130
6 Tallikatte 359 180 313 170,000 12,306 29,918 269,198 299,116 299,116
7 Nagatibelagalu 430 220 280 23,000 13,272 13,272 119,448 132,720 132,720
8 Dasarakallahalli 510 220 320 0 0 30,000 266760 0 296,760
9 Holehonnuru 275 90 240 0 0 35,000 0 0 35,000
10 Koppadoddakere 622 160 341 0 35,000 29,436 264,924 294,360 294,360
11 Mudlavittalapura 280 60 152 0 0 20000 0 0 20,000
Source: (1) Bhadra CADA office; (2) respective WUCS offices; *SST has started functioning from 15 September 2016.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 25
Updating of Demand, Collection and Balance Book
47. PSC continued to monitor and support WUCS and KNNL in the updating of the Demand,
Collection and Balance (DCB) book. The DCB has a direct bearing on the collection of
irrigation water charges from farmers which is one of the core functions of the WUCS, and
crucial for healthy operation and maintenance of irrigation assets.
48. The DCB and the khatedars list (farmers list) available with the Irrigation Department is many
years old. Many land ownership changes have taken place due to various reasons including
death of farmers, division and sale. But the records have not been updated.
49. This project is also seen as an opportunity to update the records and computerize as much
of data as possible to help KNNL and CADA. This would also be very helpful for O&M post
irrigation management transfer to WUCS. Based on the updated khatedar list obtained from
the Tahsildar, PSC updated the list available with KNNL and shared it with WUCS. PSC has
also facilitated computerisation of the hand-written data of demand collection book
maintained by KNNL for all 11 WUCS. Because of this it has now become easy for
incorporating any future updates/changes in records.
Water Tax Collection
50. At the time of project launch, only one WUCS, Kagekodamagge, was collecting some amount
of cess. KNNL serves demand notice based on the crop types and extent and the revenue
department was supposed to collect tax. However, the tax collection was very poor for several
years; the farmers generally had no drive to pay neither taxes nor penalty for delayed. As
WUCS started collection of tax motivated by PSC, some farmers raised the question of
WUCS authorisation to collect tax. This hampered the activity across all the WUCS. To
address this issue, PSC along with Federation pursued this for a few months with the
Tahsildar and towards the end of the project, could get an authorization from him (Annexure
3 dated 29 January 2020).
51. Table 14 gives the status of water tax collection during the reporting period. Now that the
project has been completed and Irrigation management transfer will be their responsibility,
WUCS have realized the importance of tax collection as a source of revenue. They started
collections actively by going from door to door. Thus, in spite of being pre-occupied with CAD
works, eight WUCS collected INR47,353 during the last quarter of 2019. The total tax
collected for 2019 by the 11 WUCS is INR145,623 from 268 farmers.
Table 14: Progress of water tax collection as of 31 December 2019
S. No.
Name of the WUCS
From April 2018 to September 2019
Oct-Dec 2019 Remittance
to Government
(as of Dec 2019)
No. of farmers
who paid tax
Amount (INR)
No. of farmers
who paid tax
Amount (INR)
1 Doddagoppenhalli 1 450 12 10,784 0
2 Baranduru 52 10,502 0 0 0
3 Seegebagi 20 13500 8 6,000 0
4 Baballi 0 0 11 13,500 0
5 Kagekodamagge 83 64,346 10 5,544 25,000
6 Tallikatte 5 1,360 0 0 0
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 26
S. No.
Name of the WUCS
From April 2018 to September 2019
Oct-Dec 2019 Remittance
to Government
(as of Dec 2019)
No. of farmers
who paid tax
Amount (INR)
No. of farmers
who paid tax
Amount (INR)
7 Nagatibelegalu 24 12,000 0 0 8,800
8 Dasarakallhalli 16 6,193 1 200 0
9 Koppadodakere 37 20,310 8 3,475 12,930
10 Mudalavittalapura 25 51,638 5 2,500 25,835
11 Holehonnuru 11 10,600 12 5,350 0
Total 254 178,671 167 47,353 72,565
Auditing and Annual General Body Meeting
52. As per the Karnataka Cooperative Act 1965, it is mandatory for a cooperative society to
complete annual audit and Annual General Body Meeting by 25 of September every year. All
the WUCS have completed their audit for the year 2018-19, and shared the same in the AGMs
held. For the current year also, all the WUCS and the Gondi federation completed their audit
before the due date 25 September 2019 and submitted to CADA and held the AGMs as
shown in Table 15. Compared to earlier years the number of members attending the AGM
has increased and PSC member(s) attended all the meetings. KNNL engineers were present
in some of the meetings. In all AGMs there were discussions and several farmers raised
questions on the accounts, CAD works, audit reports, revenue generation activities taken up
by WUCS, more CTC works/piped culverts in remote fields, construction of field drains for
disposing excess water from the fields etc. With this kind of involvement, the level of
accountability and transparency will increase in the functioning of WUCS and federation.
Table 15: Audit & AGM of WUCS and Federation
S. No.
Name of the WUCS
Status of account books
updation
Submitted for audit as
of 30 June
2019
Date of AGM
No. of members present
Male Female
1 Doddagoppenahalli Completed Yes 14 Sep 2019 60 22
2 Baranduru Completed Yes 30 Aug 2019 38 10
3 Seegebagi Completed Yes 22 Sep 2019 22 8
4 Baballi Completed Yes 25 Sep 2019 14 1
5 Kagekodamagge Completed Yes 19 Sep 2019 38 14
6 Tallikatte Completed Yes 23 Sep 2019 43 2
7 Nagathibelagalu Completed Yes 23 Sep 2019 45 5
8 Dasarakallahalli Completed Yes 25 Sep 2019 47 3
9 Koppadoddakere Completed Yes 24 Sep 2019 72 10
10 Mudalavittalapura Completed Yes 24 Sep 2019 15 15
11 Holehonnuru Completed Yes 25 Sep 2019 28 4
12 Gondi Federation Completed Yes 21 Sep 2019 40 5
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 27
53. Some of the observations of the auditors on the submissions of the WUCS:
• WUCS Board has not ratified the newly added members into WUCS;
• Share certificates not yet issued to the shareholders;
• List of legal heirs of the members not mentioned;
• Daily cash book entries not properly balanced at the end of the day and balance not
mentioned in words;
• No mention of the CAD works details and progress in registers;
• Rates of CAD works not approved by the WUCS Boards;
• Stock registers not updated properly;
• Meeting minutes not being maintained properly;
• Permission for opening of accounts in other than cooperative banks not obtained
from CADA;
• Some WUCS made cash payments as against cheque payments which is
objectionable;
• Staff salaries not ratified by the WUCS Boards;
• Request letters not obtained from farmers who have inherited or acquired possession
of ownership through sale/purchase and intending to change names in the
shareholder registers.
54. Since this was the first time that WUCS have taken up civil works with big budgets, they were
not fully conversant with the various audit rules and regulations. Several of the comments are
also not of a very serious nature and the WUCS would be rectifying them before the next
audit. PSC constantly held training programmes and tutorials, invited practising auditors and
made efforts to correct most of the audit observations. They are now better equipped to
maintain their accounts.
CAD Package Works
55. Modernization of main canals and the distributaries work is awarded by KNNL to a civil
contractor through a bidding process. However, to make WUCS a long-term partner in the
management of canals and ensure sustainable maintenance of the irrigation assets created
under the Gondi Project, the KISWRMIP has made a provision to award ‘CAD package
works’ directly to WUCS comprising lining of the field irrigation channels and construction of
appurtenant minor structures. The execution of CAD package works was done in two phases-
phase 1 lining of FICs to the extent of 165.74 km, and phase 2 lining of 110.96 km, taking the
total to 276.70 km. There are 5604 appurtenant structures under rehabilitation/construction.
The total cost of CAD package works is INR40.82 crores: phase 1 INR22.84 crores; phase 2
INR14.49 crores.
56. Implementation of Phase 1, 130 CAD packages started in January 2017 and completed as of
this reporting. During the 12-19 February 2018 Mission, ADB agreed with the KNNL request
for additional CAD packages for: (a) lining for additional lengths of FICs (phase 2); (b)
construction of WUCS buildings; (c) Gondi Federation building; (d) supply and construction
of control gates at pipe outlets, (e) supply of computer systems, office equipment and furniture
for WUCS and Federation, (f) O&M kit for all WUCS. The details of the packages are given
in Table 16. The total cost of award for all CAD works packages is INR42.77 crores. Out of
this, the FIC works for phase 1 is INR22.84 crores and for phase 2 INR19.93 crores. This
includes, apart from FIC works, buildings, tank works, control gates, anicut protection works,
WUCS office furniture and computer systems, and O&M kits.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 28
Table 16: Status of CAD packages as of 31 December 2019
S.
No. Name/Purpose of CAD Package No. of packages Status
1 FIC lining works-Phase 1 130 Completed
2 FIC lining works-Phase 2 82 Completed
3 Tank works 4 Completed
4 Control gates to DPOs and POs 6 Completed
5 O&M kit (to each of 11 WUCS) 1 Completed
6 WUCS buildings 11 Completed
7 Gondi Federation building 3 Completed
8 Anicut protection works 3 Completed
9 WUCS office furniture, computer systems
etc. 3 Completed
Total 243
Table 17: Physical & financial progress of CAD packages as of 31 Dec 2019
S. No. WUCS Name Number of packages
Estimate Cost
(Rs in lakhs)
Agreement amount
(INR-lakhs)
Total financial progress
(INR-lakhs)
1 Doddagoppenahalli 14 239.00 237.55 171.06
2 Baranduru 29 523.39 521.44 487.46
3 Seegebagi 15 244.55 240.87 212.52
4 Baballi 34 529.85 525.43 508.74
5 Kagekodamagge 17 308.05 307.31 300.72
6 Tallikatte 19 342.35 340.25 315.83
7 Nagathibelagalu 25 440.01 436.94 421.87
8 Dasarakallahalli 23 427.25 426.08 360.44
9 Koppadoddakere 26 502.38 499.86 459.47
10 Mudalavitalapura 12 210.17 209.15 194.90
11 Holehonnuru 13 237.05 235.64 195.23
12 Federation Building 3 58.70 58.54 57.71
13 O & M Kit 1 4.50 4.47 4.47
14 Gates & Anicut protection works
9 164.5 162.69 162.6
15 Furniture 3 45.45 45.45 44.53
243 4277.2 4251.67 3897.55
CAD Works Progress-Phase 1 and 2
57. As of this reporting, all the 243 CAD works have been completed as shown in Tables 18 and
19. The small balance of work in case of a few CAD packages is due to a few farmers not
allowing work to happen in small patches, or access problems. WUCS have resolved to close
the packages on achievement of progress shown in Tables 18 and 19.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 29
Table 18: CAD Physical Progress of FIC Lining as of 31 December 2019-Phase 1 (130
packages)
S. No. Name of the WUCS Lining (km) Achieved
Remarks Estimated Achieved %
1 Doddagoppenahalli 10.77 10.17 94 Completed
2 Baranduru 27.32 25.57 94 Completed
3 Seegebagi 11.37 11.10 98 Completed
4 Baballi 23.44 23.44 100 Completed
5 Kagekodamagge 11.36 11.36 100 Completed
6 Tallikatte 11.40 11.30 99 Completed
7 Nagatibelagalu 15.16 15.16 100 Completed
8 Dasarakallahalli 18.38 15.95 87 Completed
9 Koppadoddakere 16.11 14.58 91 Completed
10 Holehonnuru 11.25 9.81 87 Completed
11 Mudalavittalapura 9.20 8.00 87 Completed
Table 19: CAD Works Phase 2: Lining-Physical Progress as of 31 December 2019 (82
Packages)
S. No.
Name of the WUCS Lining (km) Achieved
Remarks Estimated Achieved (%)
1 Doddagoppenahalli 4.89 4.64 95 Completed
2 Baranduru 11.43 11.43 100 Completed
3 Seegebagi 6.22 6.22 100 Completed
4 Baballi 16.95 16.95 100 Completed
5 Kagekodamagge 9.75 9.75 100 Completed
6 Tallikatte 8.35 8.25 99 Completed
7 Nagatibelagalu 13.42 13.42 100 Completed
8 Dasarakallahalli 12.30 12.03 98 Completed
9 Koppadoddakere 16.35 16.12 99 Completed
10 Holehonnuru 5.51 5.30 96 Completed
11 Mudalavittalapura 6.27 6.15 98 Completed
10
.77
27
.32
11
.37 23
.44
11
.36
11
.40
15
.16
18
.38
16
.11
11
.25
9.2
0
10
.17
25
.57
11
.10
23
.44
11
.36
11
.30
15
.16
15
.95
14
.58
9.8
1
8.0
0
94
94 9
8
10
0
10
0
99
10
0
87 91 87
87
Physical Progress: Lining
Lining (km) Estimated Lining (km) Achieved Achieved %
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 30
WUCS Buildings
58. Prior to commencement of the project, only Kagekodamagge and Tallikatte had small office
buildings of their own where WUCS offices were located. All the remaining WUCS were
running offices from temples, panchayat buildings, school rooms, president’s house or rented
accommodation. As part of institutional strengthening, the project provided financial support
for all the WUCS and the Federation to construct their own office building with a provision of
a small meeting hall. In three villages (Baballi, Seegebagi and Doddagoppenahalli), local
farmers donated land to WUCS. For the Federation, KNNL provided a government quarter in
Bhadravathi. The Federation building has a ground floor for office and a spacious conference
hall on the first floor. As of reporting period, construction of all the buildings is completed, and
all of them inaugurated. The WUCS and the Federation have started conducting regular
monthly meetings.
59. Some of the WUCS have made arrangements to start small enterprises such as tailoring,
leaf-plate making in the office buildings. These activities help generate additional revenue for
WUCS to support various expenses of running the offices, staff and O&M of their irrigation
assets.
Gondi WUCS strengthening activity
60. The main objective of a capacity building strategy is to ensure that the stakeholders are well
equipped with knowledge, skills and attitude to better discharge their roles and responsibilities
in the attainment of project objectives. The strategy cuts across all thematic areas.
61. The comprehensive capacity building proposal comprises the following five key areas:
(a) Institutional strengthening of WUCS: This aspect also includes achieving at least 30%
women participation in all activities such as WUCS meetings, WUCS board membership
and project level federation to be formed.
(b) Enhancing skills of WUCS in planning and execution of CAD works, and participatory
irrigation management; role of women will be enhanced both in decision making as well
as in execution.
(c) Enhancing knowledge and awareness in execution and management of modernization
activities.
4.8
9
11
.43
6.2
2 16
.95
9.7
5
8.3
5
13
.42
12
.30
16
.35
5.5
1
6.2
7
4.6
4
11
.43
6.2
2 16
.95
9.7
5
8.2
5
13
.42
12
.03
16
.12
5.3
0
6.1
5
95
10
0 10
0
10
0
10
0
99
10
0
98 99 96 98
Physical Progress: Lining
Lining (km) Estimated Lining (km) Achieved Achieved %
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 31
(d) Farmers adopting sustainable agricultural practices to contribute towards water use
efficiency and increase of agrarian incomes.
(e) Promoting/strengthening Gondi Irrigation project level Federation of all WUCS.
62. Table 20 gives details of training programmes conducted during the reporting period since
September 2017 when the capacity building activity began.
63. The planned targets covering various stakeholders and training activities were achieved by
closing date 31 December 2019, and in some cases exceeded as can be seen from Table
18. Some training programmes were also conducted at village level for the convenience of
participants and to cover hitherto uncovered villages. Several exposure visits were arranged
the number of which also exceeded the target. Their impact is seen in the increased
participation of both men and women in the various training programmes, livelihood and
entrepreneurial initiatives for individuals as well as for small groups of women.
64. Initially, women were generally reluctant to take part in the trainings. The menfolk were also
apprehensive of the role and need for involvement of women in meetings and trainings. PSC
addressed this mindset with individual and small group meetings with women and men
separately and then together in larger meetings. The benefits of involving women were
explained with examples. Alongside, the WUCS Board members were taken to a few
exposure visits to places where women’s participation in agriculture and irrigation related
activities was noteworthy. PSC also formed women sub-committees in the command of every
WUCS and encouraged them to participate in all the activities of the project. Continuous effort
was made to include women in WUCS and in the Federation under “C” and “D” categories
albeit without voting rights. As of reporting period, the women participation has increased to
68% in the WUCS Boards. This level of participation has potential to increase in future with
women not only joining the mainstream irrigation activities but also in leadership roles such
as Board members and office bearers.
65. During the reporting year, trainings and activities related to irrigation management transfer of
canals, O&M, further institutional strengthening of WUCS and the Gondi Federation, hands-
on training on GIS application for data capture, volumetric based irrigation water
management, sustainable agricultural practices including demonstrations, field days,
trainings on livelihood aspects to women from marginal farmer families, destitute and single
women, women from landless families and women from the marginalised communities etc.
were conducted.
66. That the reporting year saw maximum participation of women compared with the previous
years can be seen from the fact that 3,034 women (62%) [and 1,868 men (38%)] participated
in the 85 capacity building events. In the last quarter, a total of 24 capacity building events
were conducted with 287 men (66.6%) and 144 women (33.4%) participation.
67. In total, during the reporting year of 2019, 109 capacity building events were conducted with
2,155 men (40.4%) participation against 3,178 women (59.6%) participation. Since capacity
building started in Dec 2017 until Dec 2019, a total of 356 capacity building events were
conducted in which a total of 13,241 persons participated with 7,745 men (58.5%) and 5,496
women (41.5%).
68. Trainings during October-December 2019 quarter: During the fourth quarter of 2019, the
topics of trainings included: (i) apiculture and small business (preparation of home-based
value-added products); (ii) organic methods of controlling through pest traps and weight
increase in food grains; (iii) organic certification and processes; and (iv) operation and
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 32
maintenance of canals–irrigation management transfer. In this quarter, a total of 24 capacity
building events were conducted with 287 men (66.6%) and 144 women (33.4%) participation.
69. The trainings on Irrigation Management Transfer conducted during the last quarter were
received very well by the WUCS indicated by their active participation and deliberations on
details. However, some participants expressed concerns as given below:
i. “We will clean the FICs but how do you ensure that the main canals and the
distributaries will also be cleaned and maintained?”.
ii. There are not enough pipe culverts provided on the FICs; at some places, the canals
will most likely be damaged due to crossing of carts and tractors. They opined that
around 200 more pipe culverts are required for each WUCS.
iii. We are happy that we are given many assets as part of the program (with main
reference to buildings) can we earn hire them for community functions?
iv. The schedule of canal water supply and canal closure to be informed to the WUCS
and the Federation at least 15 days in advance so that WUCS can inform the farmers
for effective crop water management.
v. “Now that we have acquired some experience in managing civil construction works,
can CADA award us piece meal works in future so that we can also earn some revenue
for our institutional sustainability in addition to constructing our own works?”
vi. “You (the PSC) are leaving us at a very crucial juncture. Can your services not be
extended by a year at least so that we can become more stable and prepared to
continue on our own?”
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 33
Table 20: List of capacity building trainings conducted as of 31 December 2019
Topic
Trainings up to Dec 2017 Cumulative
planned up to Dec 2019*
Cumulative achieved from Achieved during Oct-Dec 2019
Cumulative Achievement
start to Sep 2019 (From Start to Dec 2019)
Planned Achieved No. of
Trainings
Participants No. of Trainings
Participants No. of Trainings
Participants
Male Female Total Male Female Total Male Female Total
A. WUCS Management
One-day Orientation programmes at village level
9 17 18 31 616 357 973 0 0 0 0 31 616 357 973
Administration, Byelaws, Roles and responsibilities of WUCS
10 10 20 23 200 172 372 0 0 0 0 23 200 172 372
Accounts, Book keeping & Social auditing
5 2 12 21 325 51 376 0 0 0 0 21 325 51 376
Dovetailing Govt. Schemes and Social & Gender Development
10 0 24 28 914 906 1820 3 2 25 27 31 916 931 1847
B. Thematic Trainings
Participatory irrigation management and IWRM
3 0 9 11 221 155 376 0 0 0 0 11 221 155 376
Construction management of Canals for WUCS
3 5 6 11 255 43 298 0 0 0 0 11 255 43 298
Sustainable Agriculture Practices (Crop Demonstrations Field Days, IEC)
3 1 5 42 1598 715 2313 2 41 9 50 44 1639 724 2363
Water management - irrigation water management, measuring devices, flow measurement & volumetric water supply
3 4 20 15 389 213 602 0 0 0 0 15 389 213 602
Environmental Management aspects of modernization
3 0 7 3 82 76 158 0 0 0 0 3 82 76 158
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 34
Topic
Trainings up to Dec 2017 Cumulative
planned up to Dec 2019*
Cumulative achieved from Achieved during Oct-Dec 2019
Cumulative Achievement
start to Sep 2019 (From Start to Dec 2019)
Planned Achieved No. of
Trainings
Participants No. of Trainings
Participants No. of Trainings
Participants
Male Female Total Male Female Total Male Female Total
Social Safeguards, Gender Mainstreaming (Gender Action Plan, WUCS Gender Participation program, Gender orientation, Women in Water management, Women participation in Federation, training for Women Directors)
3 3 9 35 451 1494 1945 0 0 0 0 35 451 1494 1945
Operation and Management of Canals - Irrigation assets and management, data capture and updating information on GIS package, etc.
3 0 25 36 337 64 401 0 0 0 0 36 337 64 401
Management Transfer of Canals (second year)
3 0 17 0 0 0 0 3 67 16 83 3 67 16 83
C. Promoting Project Level WUCS Federation
Training for Federation members- Significance & role in PIM, management techniques of conflict resolution, conflict management, grievance redressal
1 3 5 3 55 12 67 0 0 0 0 3 55 12 67
Bye-Laws, registration and management of federation - role of federation in irrigation water management, marketing & knowledge dissemination
1 1 5 6 106 17 123 0 0 0 0 6 106 17 123
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 35
Topic
Trainings up to Dec 2017 Cumulative
planned up to Dec 2019*
Cumulative achieved from Achieved during Oct-Dec 2019
Cumulative Achievement
start to Sep 2019 (From Start to Dec 2019)
Planned Achieved No. of
Trainings
Participants No. of Trainings
Participants No. of Trainings
Participants
Male Female Total Male Female Total Male Female Total
Stakeholder identification & communication through periodic meetings; workshop mode: Characteristics of vibrant Federation
4 2 11 27 643 106 749 5 159 84 243 32 802 190 992
D. IEC
Exposure visit for WUCS members to successful WUCS to exchange learning and exp. within the state
4 3 6 12 227 95 322 0 0 0 0 12 227 95 322
Exposure visit for WUCS members to successful WUCS to exchange learning and exp. outside the state
3 0 4 2 37 18 55 0 0 0 0 2 37 18 55
Radio and TV series Programme 10 13 7 14 22 7 29 11 18 10 28 25 40 17 57
Street Play 23 0 23 12 980 851 1831 0 0 0 0 12 980 851 1831
Total 104 64 233 332 7458 5352 12810 24 287 144 431 356 7745 5496 13241
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 36
Integrated and Sustainable Agriculture Activity
70. Modernization of canals is expected to result in increase in agriculture production and
productivity in addition to ensuring equitable water distribution across the command area.
With the modernization project completed, canal water supply has started reaching all parts
of the Gondi command area.
71. During the reporting period, PSC continued with the SRI paddy method and other organic
paddy variety demonstrations, promotion of organic farming techniques and practices,
formation of Gondi Organic Producers Group and working towards its organic certification.
72. Alongside, PSC continued to assist farmers in the adoption of improved agricultural practices
aimed at saving water and reducing input costs along with increased yields. Several training
programmes have been conducted on sustainable agriculture practices during the reporting
year as given in Table 21. In addition to PSC experts, resource persons from University of
Agricultural Sciences, Shimoga and Krishi Vigyan Kendra conducted training sessions on
various topics. The training sessions on pests and disease control in particular in areca
received great response from farmers as 70% of Gondi command area is under arecanut
crop. The trainings were repeated a few times to reach out to as many farmers as possible
across different WUCS villages. The training format included discussions on the field between
resource persons and farmers for on the spot solutions to pest and disease problems.
Table 21: Trainings conducted on sustainable agricultural practices
Topic
Achieved during Oct-Dec 2019 Cumulative Jan-Dec 2019
No. of Trainings
Participants No. of Trainings
Participants
Male Female Total Male Female Total
Sustainable Agriculture Practices (Crop Demonstrations Field Days, IEC)
2 41 9 50 20 470 492 962
Crop demonstrations
73. Crop demonstrations conducted this year as part of planned approach to introduce newer
and higher yielding varieties. The focus was on paddy as the major crops in Gondi are
arecanut and paddy. During the year, SRI method was introduced, as also a demonstration
of ten paddy varieties by one farmer from Doddagoppenahalli (see section 2.8.3.1).
2.8.1.1 SRI METHOD
74. System of Rice Intensification (SRI) Method uses low quantity of seed (2 kg/acre), lesser
number of plants per unit area and needs only half as much water as is normally applied in
irrigated rice. SRI encourages healthy growth of rice plant with large root volume, profuse and
strong tillers. The plants are non-lodging with bigger panicles and more number of well-filled
spikelets and higher grain weight. It allows rice to grow naturally resisting insects.
75. As part of the training plan, PSC has organized orientation programmes for farmers on the
SRI. Initially, it was difficult to mobilize farmers for demonstration since quite a few farmers
have earlier tried and failed; a general impression prevailed among a majority of the farmers
that the SRI method is not remunerative. Nevertheless, with persistence, PSC team
convinced four farmers to take up the paddy demonstration (Table 22) during the summer of
2019 which was harvested last week of May/early June 2019. PSC paid a token amount of
INR10,000 per acre per farmer which is one-third of the cost of paddy cultivation.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 37
Field Day
76. A Field Day (Kshetrotsava) was organised on 25 May 2019 near the farm land of Mr.
Shantappa at Hale Seegebagi, which attracted around 250 men and women farmers from
across all WUCS. The farmers witnessed and interacted with Shantappa, and elicited detailed
information about the sustainable agricultural practices adopted by him and about the SRI
paddy cultivation. There was also a display of a variety of traditional paddy seeds, and
demonstration of low-cost indigenous planting tool and a de-weeder-both developed by
Shantappa.
77. Apart from the SRI paddy demonstration, actual demonstrations of a set of organic farming
techniques were organised. This included vermicomposting, waste decomposer, organic
seed treatment, preparation of Jeevamrutha and Panchagavya (organic preparations to be
used as liquid fertilizer and pest repellent). Made Gowda from Seegebagi demonstrated and
explained about preparation and use of Jeevamrutha and Beejamrutha. Gangappa from
Doddagoppenahalli demonstrated Panchagavya preparation. Meenakshamma explained
about different food recipes using millets. Jagadeesh Naik from Malavagoppa village of
Bhadravathi taluk demonstrated 12 different varieties of traditional paddy grown by him. The
participants also saw intercropping in arecanut (cowpea, foxtail millet, coconut, mango, jack
fruit, guava, cocoa and coffee) grown on Mr. Shanthappa’s farmland.
78. Senior officials from the Department of Horticulture and National Horticulture Board have
addressed the farmers. Subramanya from All India Radio, Bhadravathi recorded the entire
program for later broadcast; he has also addressed the gathering. He said that he has been
associated with the PSC and the project for the past 3 years, and felt that this is a hugely
successful project benefiting the farmers and the women alike. Progressive farmers and
WUCS representatives shared their experiences about benefits of Gondi modernization and
sustainable farming. Jagadish Nayak, a progressive farmer from Malavagoppa, Bhadravathi
taluk, shared his experiences in conserving the traditional paddy varieties and also exhibited
the samples. Benefits of modernization of main canals and FICs were elaborated by
Manjunath, vice president, Kagekodamagge WUCS. A member of Mudalavitlapura women’s
subcommittee, Usha, shared in detail the efforts made for enhancing participation and
empowerment of women. In sum, the participants felt that it was a great learning event
benefitting the paddy growers.
Table 22: SRI Paddy demonstration in farmer fields
Name of farmer/ Parameter
Shantappa Gangappa TK Nanjundappa KS Krishnamurthy
Chowdhary
Village Hale Seegebagi
Doddagoppenahalli Doddagoppenahalli Lakshmipura
WUCS Seegebagi Doddagoppenahalli Doddagoppenahalli Kagekodamagge
Paddy Variety Amansona MMBT 172 MMBT 172 Jyothi
Extent sown 1 acre 1 acre 0.25 acre 1.5 acre
Date of sowing 15 Jan 2019 12 Feb 2019 14 Feb 2019 13 Jan 2019
Date of harvesting 28 May 2019 30 May 2019 30 May 2019 2 June 2019
No. of tillers 30-40 25-30 30-35 30-40
Height of the plant 4 Feet 3 Feet 3 Feet 3 Feet
Length of the ear head
10 Inches 10 Inches 12 Inches 10 Inches
No. of grains in
each ear head 160 270 280 150-280
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 38
Name of farmer/ Parameter
Shantappa Gangappa TK Nanjundappa KS Krishnamurthy
Chowdhary
(approx.)
Grain yield (quintals)
39 22 7.5 35
Gross Income
@INR1750 per quintal
68,250 38,500 13,125 61,250
Total expenditure (INR)
18,360 23,478 5,866 14,235
Project incentive (INR)
10,000 10,000 2,500 10,000
79. Table 23 provides details of various indicators to depict the advantages of SRI paddy by four
demonstration farmers. For the sake of comparison, the area of each farmer has been
normalised to one acre. The yield and rate of paddy per quintal is in comparison with the crop
in the previous corresponding crop in 2018.
Table 23: Income and Yield comparison for SRI paddy
Shantappa Gangappa
T K Nanjundappa
K S Krishnamurthy
Chaudhary Remarks
Grain yield in quintals by conventional method
25 19 20 21
Grain yield in quintals
with SRI method
39 22 30 23
Adoption of SRI method has increased the yield per acre between 9.5 and 56%.
Gross income in INR by conventional method
39,750 30,210 31,800 33,867
Gross income in INR with SRI method
68,250 38,500 52,500 40,833
Adoption of SRI method has increased the gross income per acre between INR7,000 and INR28,500.
80. Krishnamurthy Chaudhary of Kagekodamagge said that during the previous season, he was
watering the paddy field almost every alternate day; in contrast, for the SRI paddy, he applied
water once a week only. This itself has saved at least 50% of water. His income has also
increased by almost 20% compared to last year.
81. Nanjundappa from Doddagoppenahalli who carried out SRI paddy on a 0.25-acre plot is more
than convinced about the method as he obtained 50% higher crop yield and 65% increase in
gross income.
82. Following this success, the number of farmers has gone up from 4 to 25 during the reporting
year, and the corresponding area from 3.75 to 17.0 acres (summer). All the farmers are
adopting organic practices completely.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 39
2.8.1.2 INTRODUCING BANANA TISSUE CULTIVATION
83. Karnataka is the third largest producer of banana in the country covering an area of 53,800
ha, productivity of 23.8 MT/ha and production of 12,77,600 MT. In Shimoga and Bhadravathi,
a variety called yelakki bale/putta bale is popularly grown which has differential yield timings.
PSC initiated demonstration of banana tissue culture saplings in view of a number of
advantages as given below:
• Uniform maturity of banana crop helps in making harvesting process easy, with reduced
labour cost. Ratoon crop (main benefit of ratooning is that the crop matures earlier in the
season) gives advantage of early bird.
• Two crops can be grown in the same interspaces during main crop growing season.
• The biological efficiency will increase.
• Effective utilization of solar radiation, efficiency in water use and enhancement in the
fertility status of the soil by addition of organic matter.
• Its role in controlling soil erosion, effective utilization of leaching materials and weed
control.
• The harvesting time is the same for tissue cultured plants. Hence, there is reduction in
harvesting costs and increased ease of marketing.
84. PSC has also organised for demonstration of tissue banana as an intercrop with arecanut.
85. Table 24 gives details of farmers from seven WUCS who have taken up tissue cultured plants.
Altogether 5050 saplings were procured and distributed among thirty farmers participating in
the demonstration. Notably, each farmer has contributed more than 50% of the cost of the
plants.
Table 24: Details of banana tissue supplied for intercrop in arecanut plantation
S.
No. Name of the WUCS Name of the Farmer
Name of the Village
Number
of
saplings distributed
Number of
saplings surviving
% Survival
1
Doddagoppenhalli
Krishnegowda Ujanipura 100 100 100.00
2 Nanjappa Ujanipura 100 80 80.00
3 Padmavathi Doddagoppenhalli 50 48 96.00
4 Kempamma Doddagoppenhalli 100 100 100.00
5 Sarojamma Doddagoppenhalli 100 100 100.00
6 Manjunath Doddagoppenhalli 50 45 90.00
7 Suchithra Doddagoppenhalli 25 20 80.00
8 Channabasappa Doddagoppenhalli 200 175 87.50
9 Nanjundappa Doddagoppenhalli 100 25 25.00
10 Mahadev Gowda Rubberkadu 200 200 100.00
11 Muregeppa Rubberkadu 200 150 75.00
12 Netravathi Doddagoppenhalli 50 45 90.00
13 Gangappa Doddagoppenhalli 200 150 75.00
14 Neelambika Doddagoppenhalli 50 43 86.00
15 Mudalavitalapura Vijayalakshmi Mudalavitalapura 100 60 60.00
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 40
S.
No. Name of the WUCS Name of the Farmer
Name of the Village
Number
of
saplings distributed
Number of
saplings surviving
% Survival
16 Holehonnuru
Ramesha Holehonnuru 200 50 25.00
17 Revanna Holehonnuru 300 150 50.00
18 Koppadoddakere Kumar Naidu Holebyranhalli 333 313 93.99
19
Dasarakallahalli
Janakamma Agasanahalli 250 240 96.00
20 Latha Agasanahalli 400 200 50.00
21 Gajendra Kumar Dasarakallahalli 100 0 0.00
22 Farid Khan Dasarakallahalli 50 25 50.00
23 Prakash Dasarakallahalli 50 25 50.00
24
Nagatibelegalu
Lokesh Nagatibelegalu 100 0 0.00
25 H.R.Maheshwarappa Hosahalli 250 245 98.00
26 Channabasappa Hosahalli 492 472 95.93
27
Kagekodamagge
Ravikumar Kagekodamagge 200 200 100.00
28 Manjunath Kagekodamagge 100 40 40.00
29 Manjunath Kagekodamagge 100 0 0.00
30 Devendrappa Kagekodamagge 500 0 0.00
Total 5,050 3,301 65.37
86. Guest lectures by the Horticulturist, Krishi Vigyan Kendra, and University of Agricultural and
Horticultural Sciences, Shimoga were arranged by PSC. A pamphlet was brought out on
practices in banana cultivation in local language. PSC made regular visits to each of the
farmers’ fields to monitor the demonstration. Table 24 gives details of the demonstration
farmers, WUCS and survival rate as of reporting period. Issues such as high temperature,
inadequate care and excess application of fertilizer led to a survival rate of 65.4%. These
issues have been discussed as part of learning among the banana demonstration farmers.
Gondi Organic Producers Group
87. To institutionalise the organic farming initiative, a Gondi Organic Producers Group was
formed on 21 June 2019 as reported in the QPR July-September 2019. The group under the
leadership of the president of Doddagoppenahalli has continued to work with much vigour
with the result that there is a huge interest generated leading to more farmers adopting
various organic practices.
88. For the purpose of sustaining these activities beyond the project period, PSC has tied up with
Sahaja Samrudha, an organic farmers association of Karnataka. It is owned by primary
producers committed to protecting the environment and providing diverse and wholesome
food. It primarily started as a farmer’s initiative to exchange ideas, seeds and share
knowledge on sustainable agriculture in the year 2009. Today, it provides market support to
the organic growers to enable cultivators get higher price for their produce. In the process of
discovering a marketing strategy, the Directors of Sahaja Samrudha created a unique
Producer Company, ‘Sahaja Samrudha Organic Producers Company Ltd (SSOPCL)’ as a
marketing arm of Sahaja Samrudha, representing farmers’ interests across the whole
spectrum from sowing to selling.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 41
89. After a series of meetings with Sahaja Samrudha, and visits to their other field areas along
with select progressive Gondi farmers, a link has been created between interested farmers
of Gondi with the SSOPCL to provide seed support, handholding in the initial stages, advise
from experienced growers and market linkages to get good and assured price. An orientation
programme on the importance of desi (traditional) seeds and organic farming was organised
on 21 June 2019. They were also taken on a two-day exposure visit to desi seed mela
(traditional seed exhibition) at Mysore. After returning from the visit, some more farmers got
inspired and joined the group. Table 25 gives a list of farmers who started growing organic
food grains and vegetables beginning third quarter of 2019. It is noticed that this number is
increasing. Data is being collected for rabi 2020.
Organic cultivation of paddy, millets and vegetables
90. Encouraged by the good results obtained in the previous SRI paddy demonstrations, as many
as 13 farmers switched to using organic methods in 14.95 acres which was closely monitored
by PSC for their method of cultivation and practices, and for crop yield studies. Visits to these
farmers lands from within and outside the village was encouraged. A noteworthy change in
this context is that the varieties introduced for the first time that is, the desi (traditional)
varieties, are retained by the farmers for their own consumption in view of the grains taste
and health parameters.
91. During the third quarter, as part of organic farming activity, PSC has started looking at two
more aspects. One, to introduce millets and organic paddy varieties to the farmers; two,
linking with the market to ensure guaranteed market and returns.
2.8.3.1 Demonstration of 10 Paddy varieties
92. The exposure visits to Field Day in University of Agriculture and Horticulture, Shimoga, and
Desi Seed Mela in Mysore has raised interest of farmers in shifting to newer varieties of
paddy. On a demonstration basis, Ganganna, a progressive farmer from Doddagoppenahalli,
who has also successfully adopted SRI paddy early 2019, has come forward and has grown
10 selected varieties in half an acre of his farmland; many farmers keenly observed the
process of nursery, transplantation, growth, application of organic manure and biopesticides,
and finally compared the yields, advantages and income returns.
93. It may be noted that the entire demonstration will be done using complete organic methods.
94. Tables 25 and 26 give details of farmers who have taken up growing organic paddy and
millets and the yields obtained in the last quarter of 2019. Unfortunately, some of the
experiments could not bear fruits as excess rains during the September/ October 2019
washed out the sown seeds. However, the farmers are determined to continue the sowing in
the next season and in January 2020, a total of 29 farmers started to raise vegetables in 3.0
acres mostly for household purpose.
Table 25: Organic Paddy Farmers and yield details
S. No.
Name of farmer
WUCS Paddy variety
Extent of land under paddy (acres)
Total yield (qtl)
Quantity Sold
(qtl)
Amount from sale (INR)
Remarks
1 Parvatamma
(Ramesh) Barandur Ratnachudi 1.25 12.81 12.81 25,620
-
2 Gangappa TK
Doddagoppenahalli
Gandasale 0.50 6.44 5.94 13,662 50 kg own use
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 42
S. No.
Name of farmer
WUCS Paddy variety
Extent of land under paddy (acres)
Total yield (qtl)
Quantity Sold
(qtl)
Amount from sale (INR)
Remarks
3 Nanjundappa Doddagoppenahalli
H.M.T. 1.50 12 - -
12 quintals for own use
Ratnachudi 0.50 1.95 1.95 3,900 -
4 Jayashankar Doddagoppenahalli
H.M.T. 0.50 - - -
Damaged due to heavy rain
5 Veerupakshappa
Doddagoppenahalli
Siddasanna 1.00 8 - - 8 quintals own use
6 Venkatesh Seegebage Gandasale 0.50 1.4 1.4 2,392 -
7 Shantappa Seegebage Siddasanna 2.20 40 7.59 15,939 32.41 quintals own use
8 Krishnamurthi Chowdhari
Kagekodamagge
H.M.T. 1.00 9 - -
9 quintals own use
9 Dastagiri Kagekodamagge
H.M.T. 1.00 20 - -
20 quintals own use
10 TG Manjunath
Kagekodamagge
H.M.T. 0.50 10 4.34 9,982
5.66 quintals own use
11 Parashuram Nayka
Nagatibelagalu Tanda
H.M.T. *1.50 28 - -
28 quintals own use
12 H. Ramappa Dasarakallahalli Siddasanna 1.00 - - - Only harvesting done
13 Kumar Naidu Koppadoddakere
H.M.T. 2.00 12 - - 12 quintals own use
Total 14.95 161.6 34.03 71,495
95. During January 2020, a total of 25 farmers adopted traditional organic paddy (Siddhasanna,
HMT, Chinnaponni, Mysore Mallige) as summer crop in a total of 17 acres. Next kharif crop
will witness a big jump in terms of number of farmers adopting traditional organic paddy as
well as the paddy varieties. This is based on the farmers satisfaction about the crop and the
varieties; many farmers initially entered into agreement with Sahaja Samruddha for buy-back
but looking at the quality kept good quantity of the produce for their and their relatives use.
Large number of farmers have witnessed the growth of the paddy and the yield and have
expressed their readiness to prefer the tested varieties of paddy as their next crop.
Table 26: Farmers who raised Ragi (foxtail millets)
S. No.
Name of farmer Name of WUCS Extent of
land (acres) Yield
(quintals) Remark
1 Parvatamma Ramesh
Barandur 0.50 -
Not sown
2 Gangappa T.K. Doddagoppena halli 0.50 - Not sown
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 43
S. No.
Name of farmer Name of WUCS Extent of
land (acres) Yield
(quintals) Remark
3 Yonus pasha Doddagoppena halli 0.50 - Washed out due to
heavy rains
4 Halappa Tallikatte 0.50 - Not sown
5 Kumar Naidu Koppadoddakere 1.00 6.00 6 quintals own use
Total 3.00 6.00
96. During January 2020, a total of 24 farmers are growing ragi in 40 acres, a big jump from 5
farmers and 3.0 acres in 2019.
97. Three farmers from Doddagoppenahalli and Kagekodamagge raised Korale (brown top millet)
lost the seeds due to heavy rains in Bhadra command during the monsoon of 2019. Despite
this setback during January 2020, ten farmers have together been growing korale as an
intercrop with arecanut in 10.0 acres, a distinct jump from 3 farmers in 1.25 acres.
Vermicomposting
98. PSC promoted vermicomposting as an organic farming practice since 2017 under sustainable
agriculture activity. Vermicomposting requires very low investment and gives continuous
returns. Small and marginal farmers can meet their own composting requirements and sell
the excess quantity to make some cash. This method was initially promoted by dovetailing
with the government scheme through the Agriculture department. In the later months more
farmers came forward to adopt this method despite the limitation on the government subsidy.
Poor and marginal farmers, single and widowed women, SC/ST were selected for support
and guidance from the PSC. Today it is also seen as a commercial venture in Gondi command
area. Five women who started vermicomposting on a commercial scale have produced about
29 quintals of compost (Table 27) as of this reporting which they will be marketing through
the President of Doddagoppenahalli WUCS who is also the President of the Gondi Organic
Producers Group.
99. All the farmers listed in Table 27 have stopped using chemical fertilizers and using
vermicompost. As high as 266.5 quintals (26.65 tons) of compost was produced by 11
identified farmers during the year 2019 and more than a ton of chemical fertilizers missed
application (savings by other farmers who purchased the excess compost produced by these
farmers is not quantified here). Farmers made a direct saving of INR59,000 on chemical
fertilizers. Farmers observed that their land has become more fertile and porous after they
started applying vermicompost. The crop foliage is healthier and greener. Water holding
capacity of the soils has improved, and a cooler field environment is noticed. In view of these
benefits, farmers first preference now is to use compost in their own land; only excess
production is sold.
100. Witnessing the benefits, more number of farmers have submitted applications for subsidy to
the Department of Agriculture, Government of Karnataka. As per indications and interest
expressed, it is expected that a number of farmers will be shifting to organic farming. To
further propagate the benefits of organic farming, wall paintings were made depicting the
techniques as well as advantages of organic farming.
Table 27: Vermicompost production by farmers
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 44
S. No.
Name of the farmer
Village/WUCS
Compost Yield up
to Q3 (qtl*)
Compost Yield
during Q4 (qtl*)
Usage/
Benefits
1 Mr. Nanjappa Laxmisagara (Doddagopennahalli WUCS)
25 0
Arecanut (2 acres), Acid lime, black Pepper and Sapota.
Reduced use of chemical fertilizer up to 350 kg (200 kg in Q2) resulting in savings of about INR7,500)
2 Ms Ningamma Doddagoppenahalli 31 5
Arecanut and black pepper.
Saving of about 150 kg (INR3,300) of chemical fertilizer.
3 Ms. Radhamani/ Lakshman Gowda
Doddagoppenahalli 39 15
Areca plantation (1 acre).
Reduced use of chemical fertilizer up to 200 kg (150 kg in Q2) resulting in savings of about INR5,000).
4 Mr. Manjunath Doddagoppenahalli 14.5
0
Areca plants (2 acres).
Savings on chemical fertilizer of INR2,000.
5 Mr. Yeswantha
Kumar Holehonnur 34 0
Areca plantation (3 acres). Savings of about INR30,000 compared to earlier.
6 Ms Anasuya Holehonnur 5 3
Arecanut plantation (2 acres).
Saved about INR5,000 by reducing use of 100 kg of chemical fertilizers.
7 Abdul Sattar Kagekodamagge 14 10
Arecanut plantation (2 acres).
Saved about INR6,000 by reducing use of 100 kg of chemical fertilizers.
8 Kiran Holehonnur 21 0
Arecanut plantation (3 acres).
Previously used to purchase cow dung costing INR13,000. Now using vermicompost thus saving that money.
9 Meenakshamma
Agasanahalli
(Dasarakallahalli WUCS)
8 0
Used 50 kg on her 0.5-acre land and sold the remaining 7.5 quintals @ INR700 earning INR5,250.
10 Sarojamma Doddagoppenahalli (Doddagoppenahalli WUCS)
22 0
Used for Banana plantation and Arecanut.
1 quintal sold for INR500.
2 quintals reserved for selling to organic farmers group.
11 Rajanna Doddagoppenahalli (Doddagoppenahalli
WUCS) 20 0
Total 233.5 33
*One quintal=100 kg.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 45
101. Some farmers who did not harvest vermicompost during fourth quarter are planning to harvest
in first quarter of this year for their own rabi crop. After formation of the Gondi Organic
Producers Group (see section 2.8.2) in the month of June 2019, and exposure visits,
increasing number of farmers have taken to vermicomposting.
Table 28: Woman farmers producing vermicompost on a commercial scale
Name of the woman farmer
Village name Name of WUCS Yield
(quintals)
Nethravathi Doddagoppenahalli Doddagoppenahalli 2
Sake bai Baballi Baballi 5
Shanthamma Nagathibelagalu Nagathibelagalu 10
Meenakshamma Agasanahalli Dasarakallahalli 6
Kavitha Kerebeeranahalli Dasarakallahalli 6
Total 29
Waste decomposer
102. National Centre of Organic Farming (NCOF) has developed a waste decomposer culture
which is used for quick composting from organic waste, soil health improvement and as plant
protection agent. It is a consortium of microorganisms extracted from desi cow dung. The
waste decomposer is also validated by ICAR. The waste decomposer costs INR20 per bottle
of 30 gm. A single bottle decomposes bio-waste of more than 10,000 metric tons just in 30
days.
103. Waste decomposer application at 1,000 litres per acre changes the biological and physical
properties of soil (acidic or alkaline) within 21 days of application; it also helps generate
earthworm population up to 4 lakhs in 1 acre of land in just six months.
104. During May 2019, the waste decomposer was introduced to nine farmers who were given the
same free of cost on a pilot basis. By end of reporting period, the number doubled to 20 and
is going up steadily. Table 29 lists the production details of all 20 farmers in the year 2019.
Table 29: List of farmers adopting waste decomposer
S. No.
Beneficiary Name
Village and WUCS Name
Preparation Quantity (litres)
Applied Quantity
(litres)
Applied
For
Area (acres)
Cost of preparati
on
(INR)
Savings on chemical fertilizers
(INR)
1 Abdul Khadar Kagekodamagge (village and WUCS)
800 770 Arecanut 2.00 850 3000
2 Krishnamurthy Kagekodamagge (village and WUCS)
800 500 Arecanut 1 1100 2100
3 Mahdevegowda
Lakshmisagara (Doddagoppena
halli WUCS)
4000 3870 Arecanut 2 3600 5200
4 Manjunath Hattigunda (Baballi WUCS)
1200 1060 Arecanut 0.2 600 600
5 Meenakshamma
Agasanahalli (Dasarakallahalli WUCS)
2200 2010 Vegetables
0.10 1150 3000
6 Ramappa Agasanahalli (Dasarakallahalli WUCS)
1400 1270 Paddy 1.00 1200 3000
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 46
S. No.
Beneficiary Name
Village and WUCS Name
Preparation Quantity (litres)
Applied Quantity
(litres)
Applied
For
Area (acres)
Cost of preparati
on
(INR)
Savings on chemical fertilizers
(INR)
7 Ravi kumar Kagekodamagge (Kagekodamagge WUCS)
1000 680 Banana 0.5 1000 2000
8 Shantamma Nagatibelagalu (Nagatibelagalu WUCS)
1800 1630 Arecanut 1.00 900 3000
9 Shantappa Hale Seegebage (Seegebagi WUCS)
1400 1360 Arecanut 0.25 700 2000
10 Suchitra Doddagoppenahalli (village and WUCS)
600 380 Arecanut 2.00 900 1000
11 T G Manjunath
Tallikatte (Tallikatte WUCS)
2200 2020 Arecanut 1.00 1150 3500
12 Uma Mudalavitlapura (village and WUCS)
400 190 Arecanut 1.00 900 500
13 Vijayalakshmi Mudalavitlapura (village and WUCS)
200 190 Arecanut 2.00 850 1000
14 Sarojamma Doddagoppenahalli (village and WUCS)
600 300 Banana 1.00 1250 800
15 Ganganna Doddagoppenahalli (village and WUCS)
200 190 paddy 0.50 1500 1000
16 Nanjundappa Doddagoppenahalli (village and WUCS)
800 800 Paddy 1.50 850 1500
17 Nagaratnamma
Doddagoppenahalli (village and WUCS)
2000 1850 Arecanut 1.00 2200 4000
18 Lakshman Agasanahalli (Dasarakallhalli WUCS)
1000 900 Arecanut 1.00 500 1500
19 Narayan Seegebage (Seegebage WUCS)
400 300 Arecanut 1.00 250 700
20 Shivalingaiah Rabburkadu
(Doddagoppenahalli WUCS)
400 300 Arecanut, Banana
2 200 600
Total 23,400 20,570 21,650 40,000
105. The preparation of waste decomposer costs approximately INR900: plastic drum of 200 litres
capacity (INR750-850), cost of 2 kg jaggery (INR100) and cost of decomposer (INR25).
However, for subsequent preparations only the cost of 2 kg of jaggery is required. The
decomposer is replaced with 10 litres of liquid decomposer saved from use.
106. The total cost of 23,400 litres of waste decomposer prepared by 20 farmers during the year
2019 was INR21,650. Savings on purchase of chemical fertilizers for the crops where this
decomposer was used is INR40,000. This is one more effort towards making Gondi command
area chemical fertlizer free.
107. Some general advantages/observations of the users of waste decomposer are:
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 47
• Biodegradable waste from farm lands got used and converted to wealth;
• Leaves are healthy in arecanut, banana and cotton crops;
• Vegetable crop growth is healthy;
• Chemical fertilizers are totally avoided and hence cost saved and carbon footprint
reduced;
• Flower growth is observed to be very healthy in flower gardens; and
• Growth of worms in vermicompost pits has increased thereby increasing the compost
output.
108. Agasanahalli under Dasarakallahalli WUCS is progressing towards becoming a chemical
fertilizer-free village. As of December 2019, 103 farmers in the 165 acres command have
shifted to organic manure and organic bio pesticides. Looking at the tremendous response, it
is expected that within a year or two, Agasanahalli will become a fully organic village.
Bio Pesticide-Puchi Marandu
109. Demonstration of preparation and use of bio-pesticide is another initiative organized by PSC
in association with Sahaja Samrudha Organic Producers Company Ltd (SSOPCL) in
September 2019. Puchi marandu, in Tamil language, means pesticide. It is an organic
pesticide safe to use and harmless both to the user and the crop. The bio-pesticide not only
reduces input cost to the farmer but also enriches the soil health due to leaves used in its
preparation. In addition to Puchi Marandu a few other pest repellents and soil enhancers were
also introduced: bio-bomb, fish tonic, bilva (Aegle marmelos) and tulsi (holy basil) decoction
to name a few. The approach adopted by PSC comprised a briefing about the contents of the
pesticide followed by live demonstration of the preparation of the pesticide. Preparation of
poochimarandu is very simple.
110. One kg each leaves of Vitex negundo, Clerodendron inermae, Aloe vera, custard apple,
Calotropis, turmeric rhizome and Neem kernel are pound well, made into a paste from which
five litres of juice is extracted. After leaving it for seven days to mature, the juice is further
diluted in 100 litres of water and sprayed on the crop. The bio-pesticide is found by Gondi
farmers to have effectively controlled all major pests of paddy, cotton and vegetables. It is
effective against coconut Eriophyid mite too.
111. Nanjundappa, a progressive farmer of Doddagoppenahalli WUCS took initiative in preparing
the solution. Initially, he used it on his farm and found beneficial results; looking at this, there
was demand from fellow farmers. He started preparing the solution in larger quantities and
began selling it mainly with a view to helping farmers.
Fish Tonic
112. Meenakshamma, a member of the Gondi Organic Farmers Group, who received training on
various organic methods was more attracted to the Fish Tonic preparation. After returning
from the training she purchased one kg fish and one kg jaggery. She cut the fish into small
pieces and added jaggery to it and stored the mixture in a bottle. In 20 about days the fish
tonic was ready with a good flavour.
113. This tonic she sprayed on horticulture and floriculture crops on her own land with a 1%
concentration in water. The fruits and flowers grew healthily. Since no harmful chemical is
present the mixture is safe to spray. Also, it does not leave any residual harmful chemicals
on the fruits and flowers. Looking at the demand, Meenakshmma, the woman farmer, has
started preparing the tonic and selling it at a profit.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 48
Cultivation and popularization of traditional varieties
114. This project has also introduced traditional varieties of rice, millets and vegetable crops with
a view to creating a niche market for the Gondi organic farmers.
115. A series of capacity-building programs and study tours organised by PSC in alliance with
Sahaja Samrudha enabled the Gondi Organic Producers Group to popularize the traditional
varieties. The capacity building activity included seed conservation, pest and disease
management, seed selection and collection, building community seed banks and establishing
Internal Control System (ICS) for organic certification. Further, the farmers are also
encouraged into marketing of seeds and grains for enhanced income.
116. To begin with, the traditional variety of seeds was procured from Desi Seed Producers
Company. Select farmers have sown these seeds on their farm for further multiplication. HMT
and Siddasanna varieties are very well adopted to the local climatic and soil conditions.
Table 30: Traditional varieties Introduced in the Project area
Crop Variety
Paddy Siddasanna, Gandhasale, Ratnachoodi and HMT
Millets Jagalur Ragi and Koralu (Brown top millet)
Vegetables Madanapalli tomato, Creeper beans, Green okhra, Musuku badane
Green Manure Diancha
Seed Quality and Rice varieties introduced
117. Seed quality plays an important role in crop production. Characteristics such as trueness to
variety, germination percentage, purity, vigour and appearance are important parameters.
Achieving and maintaining high seed quality is the goal of every seed producer. Earlier Gondi
farmers were not much aware of the seed quality but with repeated training and awareness
sessions followed by demonstration on their fields, farmers now understand the importance
of seed quality.
118. Gondi farmers used to grow only one or two varieties of crops. Now they have started raising
diverse crops using techniques such as intercropping and multicropping.
119. Siddasanna is small, fine grained rice, with excellent cooking quality, similar to Sonamasuri,
best suited for preparing chitranna (lemon rice) and puliyogare (tamarind rice). The variety,
which is easy to grow, resistant to pests and diseases, and suitable to cultivate in both the
seasons. Sidda Sanna rice is very well accepted by the farmers of Gondi project area.
120. HMT rice, which is almost equivalent to Sona Masoori. The grain looks even thinner than
Sonamasuri and tastes also good. It yields 20-24 quintals per acre. It suits for both kharif and
summer. Many farmers in Gondi area are showing interest to grow HMT in big scale.
121. Gandhasale is a flavoured and scented rice variety of Karnataka and Kerala. Gandhasale is
known especially for its rich aroma and is popularly known as Kerala's basmati. It is a
scrumptious variety with excellent cooking quality, highly fragrant, exclusive aroma and
unforgettable taste. Lodging and chaffy seed percentage is more in this variety.
122. Ratnachoodi was a popular variety of old Mysore area, still many farmers are cultivating this
variety in Chamarajnagar District. Medium grained, scrumptious variety with excellent
cooking quality, and very tasty. The rice is very soft and smooth when cooked and is easily
digestible. This variety is pest and disease tolerant, provides good quantity fodder. Due to the
yield and market constraints, not many famers showed interest to grow this variety.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 49
Chinnaponni, Navara and Mysore Mallige varieties are also introduced in the summer
cultivation. Many local consumers and organic out let people have placed order for HMT and
Gandhasale rice.
Linking organic farmers to markets
123. Marketing is being done in a basic manner through distribution of produce to the network
outlets and direct delivery to consumers. Sahaja Samrudha Producer Company procures
products in bulk based on the market demand and supplies them to different outlets spread
across the state.
124. These groups are also shareholders of Sahaja Samrudha Organic Producer Company Ltd.
and Desi Seed Producer Company Ltd. These producer companies provided market for
organic produce and organic seeds.
125. Table 31 shows the list of Gondi organic farmers who have raised organic paddy but sold
only a part of their produce, that is, 6,300kg in the market. The balance they kept for their
own use.
Table 31: Gondi Organic Farmers who sold organic paddy in the market
S. No.
Farmer Village Paddy variety Yield
(Kg)
Unit Price (INR/quintal)
Amount (INR)
1 Shantappa H K Hale Seegebagi Siddasanna 800 2,100 16,800
2 Nanjundappa K S
Doddagoppena halli
Ratnachoodi 200 2,300 4,600
3 Gangappa T K Doddagoppena halli
Gandhasale 700 2,300 16,100
4 Manjunath T G Tallikatte HMT 500 2,800 14,000
5 Parashu Naik Nagathibelagalu HMT 2,500 2,300 57,500
6 Ramesh Baranduru Ratnachoodi 1,500 2,000 30,000
7 Venkatesh Seegebagi Gandhasale 100 2,300 2,300
Total 6,300 147,300
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 50
Establishing internal control system and Organic Certification
126. Organic certification is an assurance that products have been grown and handled according
to strict procedures laid out without persistent toxic chemical inputs. Approval is based on
expert technical review and verified by an on-site inspection with renewal on an annual basis.
Internal Control System has been followed for quality assurance and are certified by Aditi
certification agency, Bangalore.
127. A total of 25 organic farmers have been enrolled for the organic certification program (Table
32). PSC and Sahaja have coordinated the certification related activities and obtained first
year certification for the farmers. Farmers are awaiting their Organic certificates in the
forthcoming year.
Focusing on the Landless and Women
Table 32: Approved farmers under Organic Group Certification Program
S. No. Farmer Father/Husband Village Total
area (ha)
Area under organic farming
(ha)
1 Shantappa HK Nendyappa Hale Seegebagi 3.20 3.20
2 Leelavathi Satish Kumar Hale Seegebagi 0.50 0.50
3 Nanjundappa KS Shivappa Doddagoppenahalli 1.70 0.50
4 Dinesh DB Doddagoppenahalli 1.00 0.60
5 Gangappa TK Kariyappa Doddagoppenahalli 1.75 0.30
6 Lakshaman Gowda Masti Gowda Doddagoppenahalli 1.40 0.60
7 JayakumarDP Parameshwarappa Doddagoppenahalli 0.50 0.30
Field day and visit to OFRC, Navile, Shimoga
A rice museum is situated on the campus of Organic Farming Research Centre of the University of
Agricultural and Horticultural Sciences, Navile, Shivamogga. Apart from millets, the centre has been
conserving traditional paddy varieties since 2006. In the last kharif season, a rice diversity block was set
up at the centre and 248 traditional varieties were grown in different plots.
Organic Agricultural Research Centre, an affiliate institution of the University of Agriculture and
Horticulture, Shivamogga hosted a field day in which SMEC and Sahaja Samrudha joined as
collaborators. More than 250 rice growing farmers from across the state participated. Around 35 Gondi
farmers visited the rice diversity farm at the Centre on 16th Nov 2019 to study and examine the rice
varieties. After a long discussion with the scientists, all the 35 Gondi farmers have enrolled their names
for procuring seed of their choice for the ensuing season.
Dr MK Naik, Vice Chancellor of the University of Agriculture and Horticulture, Farmer Leader HR
Basavarajappa, Director of Research Dr BR Gurumurthy, Director-Extension, Dr SP Nataraj, Dr Srinivas
Mudrakartha, Deputy Team Leader, SMEC PSC, Krishnaprasad, Sahaja Samruddha, Dr S Pradeepa,
Coordinator of Organic Research Centre and others were present as chief guests.
During the field day function, well-known organic farmers Shankar Langati from Belagavi, Anjaneya from
Davanagere shared their Organic paddy farming experience. Dr Ulhas, the scientist in-charge of the
research farm, of the Organic Research centre explained about maintenance of purity and the various
harvesting techniques. All the farmers were asked to select 3 top varieties of their choice. Selected top
variety seeds will be distributed to the interested farmers during the coming season as per availability.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 51
S. No. Farmer Father/Husband Village Total
area (ha)
Area under organic farming
(ha)
8 Vishwanath DM Maheshwarappa Doddagoppenahalli 0.40 0.40
9 Ravi Kumar A K. Anand Rao Kagekodamagge 0.26 0.13
10 Eshwarappa Rudrappa Kagekodamagge 1.00 1.00
11 Danappa PM Manjappa Thallikatte 1.00 0.20
12 Manjunath TG Gudappa Thallikatte 2.00 0.60
13 Rangappa Thimappa Thallikatte 1.60 0.10
14 Meenakshi Basavarajappa Agasanahalli 0.23 0.23
15 Raghuraj BN Ningappa B N Thallikatte 1.60 0.20
16 Ramappa H Hanumanthappa Agasanahalli 3.80 0.30
17 Parashu Naik Nagya Naik Nagathi Belagalu 1.60 0.80
18 Dudya Naik Nagya Naik Nagathi Belagalu 3.20 0.40
19 Krishnamurthy D Doreswamy Naidu Lakshmi Pura 1.60 0.60
20 Kumar V Naidu Krishnamma Naidu Hole Byranahalli 1.00 1.00
21 Latha V Krishnamma Naidu Hole Byranahalli 1.00 1.00
22 Pradeep R J Rama Doddagoppenahalli 1.20 0.60
23 Raju M Mahadevappa Kagekodamagge 0.40 0.40
24 Shivakumar M Mahadevappa Kagekodamagge 0.42 0.20
25 Nagaraju M Mahadevappa Kagekodamagge 0.40 0.20
14.36
128. The modernization program majorly benefits the landed farmers with assured water supply.
Agriculture labour too gets assured work opportunity and income. However, there are many
small and marginal farmers-who also work as seasonal labour due to small landholdings,
economically backward SC/ST families, widows, the destitute and the few landless. PSC
continued to focus on these categories of people this year by providing supplementary
livelihood options such as tailoring, training on animal husbandry and areca plate making
machine.
2.8.12.1 TRAINING ON ANIMAL HUSBANDRY
129. A 10-day training program was organized by PSC under the aegis of the Canara Bank Rural
Self Employment Training centre in Doddagoppenahalli for the benefit of a total of 56 WUCS
subcommittee members and other women farmers. The training covered topics on:
• Entrepreneurship, characteristics of good entrepreneur, communication skills
required for good entrepreneur;
• Need of self-employment;
• How to select a good cow;
• How to improve milk yield;
• First Aid for milking animals;
• How to use cow dung for additional income;
• How to prepare vermicompost;
• Government schemes available for animal husbandry; and
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 52
• How to prepare a proposal for bank loan.
130. Subsequent to the training, PSC followed up with several public sector banks for providing
loans to the trainees. The bank managers were initially hesitant as there were defaulters from
these villages. However, PSC arranged a meeting between the Bank managers of five
nationalised banks, the District lead bank Manager and the potential beneficiaries. The
manager of National Bank for Agriculture and Rural Development (NABARD) was also invited
for this meeting. He mentioned that 25% of the loan is reimbursed by NABARD to the
individual banks. To ensure that default is checked, arrangement was made with the milk
cooperatives within WUCS and the beneficiaries to deduct loan instalment and deposit the
same into the bank. Thus, the banks are assured of regular recovery.
131. As of reporting period, a total of 106 people received training in animal husbandry. Of these,
38 women (25 from Tallikatte WUCS and 13 from Doddagoppenahalli WUCS) received bank
loans. One woman from Doddagoppenahalli purchased cow from her own resources. Further
batch of 21 more applications are in the pipeline (Table 33). In addition, every cow owner is
eligible for INR8,000 to INR12,000 for construction of a cow shed (based on the size of the
shed) from the village Panchayat funds. All the 38 cattle owners applied to respective Gram
Panchayats for cow shed construction.
132. Twenty-eight women have started selling milk to Dairy. This has fetched them about
INR80,179 and an incentive of INR14,520 from GoK (at INR4.0 per litre) as of this reporting.
The loan repayment of all the loanees has started; the monthly instalment amount is deducted
from loanee account and remitted to the bank by the Dairy cooperative.
Table 33: Loans received for purchase of cows as of 30 March 2019
S. No.
WUCS Loan
sanctioned (INR)
Cows
Purchased (No.)
No. of applications submitted to bank
1 Doddagoppenhalli 6,50,000 13 21
2 Tallikatte 12,50,000 25 -
Total 19,00,000 38 21
Gondi O&M and Asset Management Plan
133. Gondi Irrigation project is a 100-year old project, which became defunct in the course of time
due to inadequate attention paid towards maintenance. As the performance of the project is
greatly affected due to deferred maintenance, modernization works including anicut repairs,
re-sectioning and concrete lining of both right and left bank canals and distributary canals,
and lining of field irrigation channels and construction of associated structures have been
taken up since 2016 as part of KISWRMIP and are in advanced stage of completion. After
completion of the modernization works, the water resources department and the WUCS have
to play a key role in proper operation and maintenance (O&M) of the irrigation system. Hence,
it is imperative to impart both knowledge and skills on O&M activities through capacity building
programmes both to departmental officers as well as WUCS, a key stake holder group in the
project. The project also envisages use of GIS as a decision-making tool for irrigation asset
management and database on a sustainable basis.
Operation & Maintenance
134. The O&M manual has been finalized and shared with KNNL and CADA for their inputs during
the year. The draft was also used in the training programmes. Meanwhile, 3 trainings have
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 53
been conducted during the last quarter of 2019 as part of the irrigation management transfer
for all the 11 WUCS. Trainings are also conducted for KNNL and CADA engineers during the
reporting period (Table 20).
135. Irrigation management transfer: As part of preparation for management transfer of FICs
along with the associated structures to WUCS, the following draft documents/formats have
been prepared:
• Draft format for the MoU between KNNL/CADA and WUCS.
• Formats for preparation of inventory of irrigation infrastructure such as salient features
and year of construction, cost of various types of works like FICs, CTCs, bridges, drops
and measurement structures.
136. The irrigation management transfer could not be completed by the end of reporting year, as
the construction works including some CAD works were going on and asset data capturing
could not be completed.
Gondi Irrigation Information System
137. A “Web-based Application with GIS Database for System Appraisal, Asset Management,
Monitoring and Water Management in Gondi’’ was developed as part of sustainable
management of irrigation assets created as part of the Gondi modernization. The work on the
application started on 1 February 2018 and the activity was completed in April 2019.
Witnessing the application ADB and its use, ADB has recommended GIS to be implemented
in Tranche 2 Modernization of Vijayanagara Channels also with necessary
modifications/improvements.
138. The following are the principal features of this web-based software called “Gondi Irrigation
Information System” (GIIS):
a) Mapping of the Gondi command area showing village boundaries, WUCS boundaries,
outlet-wise command area, roads, main canals, distributaries, FICs, canal structures,
pipe outlets, streams and other water bodies, all principal structures, etc.;
b) Salient features of the Gondi project;
c) Achkat (command area) particulars;
d) Crop-wise data (starting with the kharif season of 2018 and collected data from the
past years-2016, 2017);
e) Estimation of crop water requirement;
f) Outlet-wise crop areas with individual land parcels; and
g) Administrative modules for operation and maintenance.
Progress of GIIS
139. The progress of GIIS was made as planned. Software development and data updation was
completed as of December 2019 commensurate with the progress of civil works. Only data
pertaining to the ongoing portion of the canal works (main and FICs and the appurtenant
structures) and structures along main canal, distributaries and CAD packages are to be
collected and updated. The WUCS have been advised to update this data soon after
completion of civil works.
O&M Kits to WUCS
140. The next step after modernization is regular and periodic operation and maintenance of the
assets created. With the approval of ADB Mission in February 2018, O&M kit for each of the
WUCS was supplied so that they could effectively cleans and maintain the FICs. This is
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 54
necessitated because soon after the civil works are completed and irrigation management
transfer is completed the WUCS require basic tools for effectively maintaining the FICs. ADB
approved the O&M kit to be given as a separate CAD package works.
141. During the reporting year, most of the WUCS have been using the kits for canal cleaning
works as part of O&M activity.
Safeguard Monitoring of Gondi Irrigation System
142. Gondi modernization is a category ‘B’ project as per ADB Safeguards policy 2009. The
Environmental Management Plan (EMP) for such a category has been described in the Initial
Environmental Examination (IEE) conducted as part of PPTA. The IEE provided a Monitoring
Plan to be followed by the contractor to ensure that they comply with the EMP requirements
so as to mitigate adverse environmental impacts arising due to the project. It may be noted
that in the present reporting period construction work took place for a few days during May-
June and during the closing period in December 2019. No construction was possible during
June-December period due to incessant rains in the entire command area.
143. PSC team has been making regular visits to the contractor’s working sites and camp sites
and have observed compliance to safeguard aspects. During the reporting period, the PSC
has prepared and submitted safeguard monitoring reports April-September 2019, and
October 2019-March 2020 and submitted to ADB. The following comprises a set of key EMP
actions carried out by the contractor during the construction phase of 2019 to mitigate adverse
environmental impacts:
144. Workers Compensation Insurance: Contractor has obtained Workers Compensation
Insurance covering all the 25 workers valid until 7 May 2020, coinciding with his contract
period. The Workers Compensation Insurance is in addition to the Contractor’s All Risk Policy
that covers the project components.
145. Facilities provided at Camp site: The contractor has secured permission from the local
authorities for setting up camp site at old Devanarasipura-Kodihalli. The contractor has also
provided basic infrastructure and other facilities such as drinking water supply and a kitchen
mess. Separate sanitation facilities for men and women have been set up and are functional.
Health and hygiene aspects continued to be taken care of by the contractor through
installation of septic tanks and composting units for treatment of kitchen waste. Source
segregation of waste has been introduced and dry waste recycled.
146. Table 34 gives details of private land on which the contractor has set up two campsites and
two borrow areas:
Table 34: Private Landholdings used tor Project Activities and Status
S. No.
Land Access for No. of households/ private land owners
affected
Agreement between
Status of the Site
1 Campsite: Devanarasipura Kodihalli
One Contractor and land owner
In use as of reporting
2 Campsite: Timlapura
One Contractor and land owner
Closed as per EMP
3 Borrow area: Dananayakapura
One Contractor and land owner
Closed as per EMP
4 Borrow area: Kanasinakatte
One Contractor and Owner
In use as of reporting
147. Batching plant: During 2019, the contractor established one batching plant at
Devanarasipura-Kodihalli. The location of the batching plant was approved by the local
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 55
authorities. The Karnataka State Pollution Control Board has also accorded the consent to
operate permit. The batching plant is operational and not closed as the contractor is carrying
patch works along the main canal.
148. Workers safety precautions: To ensure safety aspects of workers, the materials have been
stored at pre-designated spots at the batching plant location and appropriate safety sign
boards placed. Fire extinguishers have been provided at prominent locations within the camp
sites as a precautionary measure. The contractor also placed appropriate safety sign boards
warning nearby residents about the periodic movement of trucks and other vehicles. Further,
the contractor has been holding periodic consultations with the surrounding inhabitants for
taking additional measures, if any, towards ensuring good health and the well-being of the
nearby communities. All such deliberations have been recorded in a register maintained by
the contractor and verified by the PSC.
Table 35: Trainings on Environmental and Social Safeguards during 2019
S.
No. Name of group Venue Topic Date
No. of participants
M F Total
1
Presidents, vice-
presidents, and
secretaries of all
WUCS and Gondi
Federation
Dharmas
thala
Environmental and
Social Safeguards-role
of WUCS board
members and the Gondi
Federation
16 Mar
2019 41 7 48
2
Site engineers and
Supervisors of
KNNL, CADA and
contractor
SST
office,
Bhadrav
athi
Social and
Environmental aspects
of Safeguard Monitoring
21 Jun
2019 19 4 23
Total 89 78 167
149. PSC environmental expert visited ACIWRM on 21 Mar 2019 and learnt about the work carried
out by ACIWRM towards addressing the various macro-level environmental issues identified
in the EMP.
150. Pollution due to vehicles: The contractor continued to utilise the fleet of 18 vehicles
deployed on the project. PSC verified that the vehicles have valid, mandated Pollution Under
Control (PUC) Certificates issued by concerned authority.
151. Measures to prevent air pollution: The contractor carried out water sprinkling to check dust
occurring due to movement of vehicles, and operation of the batching plant at the campsite.
152. Monitoring of water quality: To monitor the land and water sources, the contractor was
instructed to initiate environmental sampling and monitoring of groundwater and surface
water at certain locations in and around the closed construction camp site. As of this reporting,
no post-closure environmental monitoring has been carried out by the contractor. Hence, PSC
has instructed the contractor to carry out post closure operations as per EMP; he should also
obtain satisfactory handing over certificate from the land owner where campsite is located.
The results of environmental sampling and the land-owners handing over certificate will be
provided in the final SMR as some patch works are still going on.
153. Tree cutting: A total of 234 trees along the canal had to be cut as they were located either
on or close to the service road blocking the movement of vehicles and equipment. The
contractor has carried out compensatory tree planting more than the prescribed ratio of 1:3
by the Karnataka Forest Act 1963. The contractor purchased farmer preferred species of
plants (coconut, 775) from the Karnataka Forest Department nurseries and planted them
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 56
along the canal stretches; some plants have also been and in nearby government schools
and along the boundary of farmers lands. Majority preference was for coconut as the WUCS
expects them to be a source of income for sustainability. The income will be shared between
the concerned farmer and the WUCS.
154. Disposal of Silt: Farmers of lands juxtaposed with the canals under modernization evinced
keen interest on the silt as it is rich in nutrients. They have voluntarily collected the silt and
spread it evenly on their farm lands; thus, there is no change in the profile. Thus, any adverse
environmental impact likely to arise from silt disposal has been largely mitigated.
155. Procurement of construction material: The contractor has procured construction material
such as stone aggregate and sand from government approved quarries having valid license
issued by Karnataka State Pollution Control Board (KSPCB).
156. M-Sand: The contractor continued to procure manufactured-sand (M-Sand) from approved
vendors. Hence, environmental impact arising from mining of sand from surface water bodies
has been mitigated to a large extent.
157. Borrow pits for filling material: The borrow areas at Kodihosuru, Kanasinakatte, and
Danayakapura have been used as filling material. Other areas like MC Halli, Baranduru and
Mavinakere have not been utilised for the project. The borrow pits have been consented by
the local village community and the KNNL. In fact, KNNL allots borrow areas with due
approval from the local community.
158. Borrow pit closure: The Danayakpura borrow pit was dug up for filling material to the extent
that it was approved; At the Kanasinakatte borrow area, thus far, about 80% of the allotted
volume of filling material has been utilised. Also, the borrow pits are dug up to such a depth
that the natural drainage in the area is not adversely impacted.
159. The contractor has also taken up borrow-pit closure activities to maintain the environmental
integrity of the borrow pit location. The Dananayakapura borrow pit closure activities have
gained acceptance and appreciation from the local community. The farmer who owns the
land is happy because the borrow pit is once again available for agricultural operations after
restoration and presently is being utilised to plant betel nut trees. The closure activities for
the Kanasinakatte borrow location are underway.
Kanasinakatte borrow pit: Before (left) and After (right) photos
160. Closure activities at Devanarasipura-Kodihalli camp site: The closure activities carried
out by the contractor included removing all the structures erected at the campsite, levelling
the land and restoring status quo ante so that it is suitable for any activities that the land-
owner may choose to carry out. The contractor, at the request of the land-owner, did not
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 57
demolish bathrooms and other sanitation facilities. It may be concluded that the closure
conditions have been duly met by the contractor.
161. Closure meetings: After completing modernization work on a canal, the contractor generally
organised a closure meeting in the presence of stakeholders including the local community.
This is to ensure that the community is satisfied with the measures taken by the contractor to
safeguard environmental quality, and health and safety of the community. Deliberations of
such closure meetings are recorded in a register maintained by the contractor. Closure
meeting will be conducted in June 2020 after all patch works are completed by the contractor.
162. Documentation of implementation of EMP: There has been a marked improvement in the
documentation of the implementation of the EMP by the contractor regarding approvals as
given below:
• Approvals from the concerned land owners for disposal of silt;
• Approvals from gram panchayat/Individual land owners (as the case may be) for utilisation
and proper closure of burrow areas; and
• Approvals from gram panchayat/individual land owners (as the case may be) for proper
closure of the construction camp sites.
163. Implementation of environmental, health and safety measures for workers: During the
reporting period, the contractor conducted monthly health check-up camps for the labour in
the camps and provided the labour with adequate number of safety devices. It was also noted
that here were no major accidents or serious health concerns reported during the year 2019
or during the entire construction time.
164. The contractor has also ensured that all required approvals are in place, use of the Personal
Protection Equipment (PPE), carrying out periodic health monitoring of the workers and
encouraging workers to come up with suggestions for improving the environmental, health
and safety practices. Thus, overall, PSC has observed that there has been a marked
improvement in the compliance of effective implementation of environmental, health and
safety measures by the contractor for the workers.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 58
Health camp conducted in December 2019
Grievance Redressal Mechanism
165. As part of the Grievance Redressal Mechanism, complaint registers are maintained at WUCS,
Federation and KNNL offices. In addition, a Gondi WhatsApp group (PIO Gondi) that was set
up in October 2017 with multiple objectives became a good medium for registering their
grievances by WUCS and individual farmers. Not only the grievances were recorded, but also
the concerned persons/agencies such as KNNL, CADA and the contractor have also
responded quickly; thus, all the grievances have been redressed satisfactorily by 31
December 2019, the project civil works closing date. Fig 6 shows the register maintained by
Doddagoppenahalli WUCS. As can be seen the column headings show-date; name of the
complainant; details of grievance; signature of the complainant; nature of redressal; who
resolved. The contractor has maintained a GRM register at the camp site and also at the
WUCS site. The grievances listed here have been taken from all of the above sources.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 59
Figure 6: GRM register maintained by Doddagoppenhalli WUCS
166. The grievances registered are categorized into four types described below:
i. Water Release: related to timing and quantity; out of the total complaints registered
40% relate to water release.
ii. Civil Works: related to start of CAD works, problems observed in main canal civil
works, fixing of sluice gates, etc.; of the total complaints registered 19% relate to the
civil works.
iii. Functioning of WUCS and Federation: relates to date of review meetings,
workshops and trainings, monitoring by Federation CEO, etc.; of the total complaints
registered 11% are related to this category.
iv. Operation and Maintenance: relates to deposition of silt and clogging of water in
canals, weed growth in canals, damage and repair works in canals, etc.; about 30% of
the complaints registered fall under this category.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 60
Table 36: Grievances registered between 1 Sep 2017 and 31 Dec 2019
Grievance category
Period Water
Release Civil
Works
Functioning of WUCS & Federation
Agriculture O&M Total %
Till Dec 2017 2 1 0 0 1 4 5
1st Quarter 2018 0 1 0 0 0 1 1
2nd Quarter 2018
2 1 0 0 8 11 14
3rd Quarter 2018 2 0 1 0 0 3 4
4th Quarter 2018 5 5 6 0 3 19 23
Total grievances up to 2019
11 8 7 0 12 38
1st Quarter 2019 5 2 2 1 4 14 17
2nd Quarter 2019
8 2 0 0 1 11 14
3rd Quarter 2019 2 1 0 0 5 8 10
4th Quarter 2019 6 2 0 0 2 10 12
Total grievances for
2019 21 7 2 1 12 43
Total grievances
since beginning
32 15 9 1 24 81
167. As can be seen from the Table 36, the reporting period recorded almost 50% of the
grievances for the duration of monitoring. The reasons attributed to this increase in
grievances may be attributed to: (i) awareness trainings to maximum number of farmers
regarding the project; (ii) trainings to WUCS and farmer members on construction
management; (iii) trainings to WUCS Board members on water management issues and to a
lesser extent; (iv) availability of a medium like WhatsApp group where KNNL engineers and
contractors are also members, (v) canal closure periods and works execution, and (vi) water
reaching almost every corner of the command area thus increasing the access to canal
supplies hitherto unreached. The figures under the topics: (i) water release; (ii) civil works,
and (iii) O&M clearly support the above statement(s).
168. The details of complaints registered under different category over the time from last quarter
of 2017 to last quarter of 2019 are also presented in pie charts for a quick grasp. All the 81
complaints registered have been redressed to the satisfaction of the complainants by the
concerned-KNNL/ CADA engineer or the contractor.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 61
50%
25%
25%
Till Dec. 2017
Water Release
Civil Works
Functioning ofWUCS &FederationAgriculture
O&M
100%
1st Quarter - 2018
Water Release
Civil Works
Functioning ofWUCS &FederationAgriculture
O&M
18%
9%
73%
2nd Quarter - 2018
Water Release
Civil Works
Functioning ofWUCS &Federation
Agriculture
67%
33%
3rd Quarter - 2018
Water Release
Civil Works
Functioning ofWUCS &Federation
Agriculture
26%
26%32%
16%
4th Quarter - 2018
Water Release
Civil Works
Functioning ofWUCS &FederationAgriculture
O&M
36%
14%14%
7%
29%
1st Quarter - 2019
Water Release
Civil Works
Functioning ofWUCS &Federation
Agriculture
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 62
73%
18%
9%
2nd Quarter - 2019
Water Release
Civil Works
Functioning ofWUCS &FederationAgriculture
O&M
25%
12%
63%
3rd Quarter - 2019
Water Release
Civil Works
Functioning ofWUCS &FederationAgriculture
O&M
60%20%
20%
4th Quarter - 2019
Water Release
Civil Works
Functioning ofWUCS &FederationAgriculture
O&M
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 63
3 SOCIAL MANAGEMENT FRAMEWORK AND GENDER ACTION PLAN
169. The Program (KISWRMIP) lays emphasis on adopting a pro-poor and gender inclusive
mechanism through empowerment of women in the project villages. The poverty reduction
and social strategy under the program is aligned with ADB’s Poverty and Social Analysis
Strategy (2012)3 and Government of Karnataka’s policy on promoting inclusive growth. The
Program aims at providing equitable access to water for farmers and rural households for
both agricultural and domestic purposes. The program also facilitates improvement of
livelihood of rural poor, including the small, marginal famers, the landless and other
vulnerable groups.
Progress against GAP
170. There has been considerable progress in the implementation of the Gender Action Plan
(GAP) as of 31 December 2019, indicated by the increase in women representation from 20%
at the launch of the project in 2016 to 68.6% as of December 2019. Currently, among the
WUCS office-bearers, there is one woman as vice president of Seegebagi WUCS.
171. As per the Gender Action plan under Outputs 2 and 3, PSC has achieved all the activities
proposed (Table 37). Towards this, PSC adopted innovative measures such as:
(a) Providing handholding support to the women directors, women subcommittee and C and
D category members to undertake the responsibilities assigned to them.
(b) Developing leadership qualities by encouraging their participation at various levels
including as leaders and board members in WUCS. Organizing thematic trainings on
leadership and gender and empowerment.
(c) Recognize the interests and needs of women and prepare local specific plans for
alternative livelihood for women members especially landless, widows, minorities and
other vulnerable groups (SC/ST):
(d) Conducting skill development and entrepreneurship training programs in collaboration
with district panchayat, District Industrial Centre and Jana Sikshana Samstha (JSS) under
the support of Ministry of Skill Development Mission, Govt. of India, Krishi Vigyan Kendra
(KVK), University of Agricultural Sciences, and banks.
Table 37: Progress against Gender Action Plan
Objective Planned Activity Achieved as of 31 December
2019
Remarks
Output 2. Irrigation System Infrastructure and management modernized
Activity 2.1
Build
awareness on
women’s
equal rights
and
participation
in water
resources
management
and livelihood
programs.
a. Indicator: 9 sensitization workshops focusing on gender equality and social inclusion approaches and women’s role and participation in water resources management alternate livelihood activities carried out by WUC members.
Target:
9 workshops
Number of sensizitization
workshops organized: 21
Number of Participants:
Total 641 (male 278; female
364)
Topics covered in the
workshops:
a) Gender and gender
relations;
b) Soicietal roles and
responsibilities of men and
women;
Target
accomplished.
3ADB’s Poverty and Social Analysis Strategy (2012);
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 64
Objective Planned Activity Achieved as of 31 December
2019
Remarks
(M-100; F-50)
Responsibility:
PSC/PIOs
Time frame:
Year 2-3
c) Socio-cultural practices of
men and women in India
and project area;
d) Government policies on
gender and women
empowerment;
e) Ongoing women
empowerment and
livelihood projects
implemented by other
departments;
f) Roles of men and women in
agriculture, crop selection,
harvesting, etc.;
g) Safeguard procedures;
h) Suggestions for improving
subsequent trainings;
Entreprenuership linked to
livelihoods:
i) Value-added home-made
products;
j) Dairy farming for women;
k) Tailoring;
l) Mushroom culture;
m) Herbal beauty products;
n) Vermicompost;
o) Roti making (solar
powered).
b. Indicator: 2 trainings on social leadership development, decision making and promotion of women’s participation in WUCS for women directors.
Target: 2 trainings (20 women directors)
Responsibility: PSC
Time frame: Year 3
Trainings conducted: 4
No. of Participants:
Total 99 (all female)
Number of women directors
participated: 22
Topics covered in these
trainings:
a) Introduction to the project;
b) Project components and
expectations from farmers;
c) Role of directors and
members;
d) Leadership qualities;
e) Case studies;
f) Follow the leader–game;
g) Importance of
communication–group
dynamics;
h) Conflict resolution;
i) Group administration and
management.
Target
accomplished
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 65
Objective Planned Activity Achieved as of 31 December
2019
Remarks
c. Indicator: At least 30% of WUCS management board members are women.
Target: 30% female (M-150; F-50)
Responsibility: PIO
Time frame: Year 1-2
No of WUCS constituted and
functional: 11 as against 10
estimated.
No. of WUCS members:
Total 2989 (male 2369; female
620);
No. of WUCS Board members:
Total 119 (male 94; female 25
(21%));
Adding D (non-voting) category
members, another 80 added,
taking to 68.6%.
Additionally, Gondi Federation
resolved that in addition to
elected women members on
the board, Federation nhas
resolved that there will be 4 to 5
non-voting woman members
under D category in the WUCS
Board. With this, the women
representation has increased to
80 (68.6%). Further, one
woman in each WUCS (from
among women directors from D
category member) is selected
under C category at WUCS
level and nominated to WUCS
Federation without voiting
rights.
Further, a total of 31 women
sub-committees (with at least
15 members) have been
formed in all the 11 WUCS with
a total of 437 members. Three
sub-committees have been
formed during the reporting
quarter (Q4); these committees
also include ST, SC and poor
and the landless.
Target
accomplished
Activity 2.2.
Develop and
implement
training
modules for
increased
women’s
participation
in irrigation
management
Indicator: 20 training programs focused on PIM conducted in Gondi command area resulting in the increased access to water for cropping and domestic use especially by tail end, small and marginal and women farmers/ households.
Target: 20 trainings
27 training programs conducted
for WUCS, women
subcommittee members, small
and marginal farmers for
enhacing their participation in
PIM.
No. of Participants: 911
(male 458; female 453)
Target
accomplished.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 66
Objective Planned Activity Achieved as of 31 December
2019
Remarks
and value-
added
livelihood
activities.
(male-500; female-500)
Responsibility:
PMU/PIOs/NGO(s)
Time frame:
Year 2-4
Topics covered in the trainings:
a) Introduction to the project
b) Project components
c) PIM concept and examples
d) Ongoing self-help and
micro enterprises in
agriculture, horticulture,
dairy farming, fisheries, etc.
Additonally, 239 women and men from different groups/ cooperatives trained and strengthened on entreprenuership and small business; they have been given handholding support in opening bank accounts and marketing linkages.
A total of 31 women sub-committees have also been formed, apart from across 11 WUCS apart from the “Gondi Organic Growers Group” to promote production and marketing of organic paddy, vegetables and millets. Women trained in micro enterprise and livelihood activities such as diary, tailoring, roti-making, value-added products such as candle making and soap making, beautician course as part of women empowerment.
Output 3: Program and management systems operational
Activity 3.1.
Improve the
knowledge of
relevant
government
departments
on GESI
approaches in
agriculture,
irrigation and
water
resources
management.
Indicator: 3 training workshops
for women/men staff of key
departments focusing on GESI
concepts and in the design and
implementation of water
resources management,
irrigation and agriculture
programs for vulnerable
populations, including women
Target: 3 workshops
(F-30; M-70)
Responsibility: PMU
Time frame: Year 1
4 training workshops
conducted for staff of KNNL,
CADA, Agriculture and
horticulture department, KVK.
No. of participants: 394
(Male 299; Female 95)
Topics covered in the
trainings;
a) GESI concepts and
strategies;
b) Government policy on
gender and women
empowerment;
Target accomplished.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 67
Objective Planned Activity Achieved as of 31 December
2019
Remarks
c) Societal roles and
responsibilities of men and
women;
d) Role of men and women in
agriculture, dairy, livestock
and related livelihoods;
e) Best practices and case
studies;
f) Evaluation and
suggestions for further
improvement.
Activity 3.2:
Monitor
progress of
gender and
socially
inclusive
focused
activities in
water
resources
management.
a. Indicator: Project
management information
system with gender indicators.
Target: NA
Responsibility: PMU/PIOs
Time frame: Year 1-4
PMIS system developed and
hosted on KNNL website;
progress posted regularly.
Progress also reported in the
quarterly progress reports.
b.Indicator: Sex disaggregated
data to be collected, analysed
and key findings disseminated
to address implementation
gaps.
Target: NA
Responsibility: PMU/PIOs
Time frame: Year 4-5
Data collected. Will be
included in the Project
Completion Report to be
submitted shortly.
For dissemination, following
activities are implemented;
• Baseline assessment
conducted every quarter
and included in the
QPR/APR along with key
findings.
• A 13-episode radio
programme including
gender roles and
empowerment aspects
produced and broadcast
(converted into book form
titled–“nela-jala-jana”).
Also hosted on the project
link on KNNL website.
• Project quarterly
newsletter and QPRs
describe progress of
gender action plan as a
separate section;
• One song book published
containing farming, gender
and environment related
songs;
• Two brochures printed on
gender relations and
women empowerment;
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 68
Objective Planned Activity Achieved as of 31 December
2019
Remarks
• All India Radio (AIR)
interviewed 12 women
(out of 33 persons)
inlcuding women directors,
woman secretary, and
women farmers. Speech
recorded by AIR,
Bhadravathi on the
experiences, outcomes,
women participation,
farmers participation, and
WUCS role in Gondi
project. This program ws
broadcast 11 times on
different days.
Poverty, Gender and Livelihoods
172. PSC has realized during field visits and interactions with the WUCS directors and women
subcommittee members that specialized interventions are required to address the needs of
the landless, SC/ST, female headed households and the poor. After interactions and group
discussions with the WUCS in the first year, an action plan was developed to address the
gaps and identify programs in collaboration with governmental and non-governmental
development programs.
173. The following strategies have been adopted:
• Social mapping to identify potential needs and priorities;
• Strengthening the capacities of women directors and women subcommittees;
• Formation and strengthening of women subcommittees in the identified localities;
• Identifying ongoing entrepreneurship and livelihood programs implemented by
Government, Krishi Vigyan Kendras and NGOs.
Women sub-committees
174. Over the lapsed project duration, a total of 31 women subcommittees comprising 437 women
have been formed. Their capacities and skills have been enhanced through training
programmes organised by PSC and a few other agencies. They are actively participating in
the implementation of livelihood and entrepreneurship programs. Five women subcommittees
have been formed in Dasarakahalli WUCS and Nathibelagalu WUCS during the last quarter
of 2019 as detailed in Table 38.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 69
Table 38: Women subcommittees as of 31 December 2019
S. No.
Name of the WUCS No. of women
subcommittees as of Dec 2019
Number of Women Members
Total
as of Dec 2019 As of Sept
2019
New Members
during
Oct-Dec 2019
1 Doddagoppenahalli 1 22 0 22
2 Baranduru (Bommenahalli (1) & Hale Baranduru (1))
2 26 0 26
3 Seegebagi (Kanakatte (1) & Hale Seegebagi (1))
2 33 0 33
4 Baballi (Baballi Thanda (1) & Baballi main village (2))
3 42 0 42
5 Kagekodamagge 1 15 0 15
6 Tallikatte (Jayanagara (1), Kumuri Narayanapura (1), Tallikatte (3))
5 57 0 57
7
Nagathibelagalu (Nagathibelagalu Thanda (2), Kalpanahalli (1*) and Nagathibelagalu main village (1))
4 47 15 62
8
Dasarakallahalli
(Agasanahalli (5*), Dasarakallahalli (1) & Aradotlu (2))
8 46 60 106
9 Koppadoddakere 1 20 0 20
10
Mudalavitlapura
(Kerebeeranahalli (1), Jamaraghatta (1) & Mudalavitlapura (1))
3 44 0 44
11 Holehonnuru
(Danayakpura) 1 10 0 10
Total 31 362 75 437
175. The women subcommittees continued to hold regular meetings. A diverse list of topics
ranging from paddy cultivation to intercropping in arecanut, organic seed production, O&M
and cleaning of canals, bank loan for animal husbandry, water tax collection, self-
employment/small business/micro-enterprises have been discussed. A list of all topics
discussed during the meetings with different subcommittees is given in Table 39. PSC
continued with one-to-one interaction with some women directors and members of WUCS
who were a little passive to activate them and form more number of women subcommittees.
Table 39: Women sub-committee meetings and topics covered
Name of WUCS/
Women sub-committee
Number of meetings
conducted during
Jan-Dec 2019
Topics covered in the meetings
Doddagoppenahalli 24 • Monthly work plan;
• Mushroom cultivation;
• SRI paddy cultivation;
• Intercrops in Arecanut plantation;
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 70
Name of WUCS/
Women sub-committee
Number of meetings
conducted during
Jan-Dec 2019
Topics covered in the meetings
• Bank loan request;
• Water tax collection;
• Dovetailing with Government programs;
• Organic seed production and organic manure;
• O&M and cleaning of canals;
• CAD Packages payment;
• Involvement in office building marking;
• Tailoring training list preparation;
• Waste Decomposer importance;
• Organic pesticide preparation;
• Organic certification.
Baranduru
10 • Strengthening of women subcommittees;
• Regular meetings;
• Monthly plan;
• Increasing the shareholders;
• Self-employment opportunities;
• Environment day celebration;
• O&M and cleaning of canals;
• Tailoring programme;
• Leadership training;
• Waste Decomposer.
Seegebagi
12 • Strengthening of women subcommittees;
• Water tax collection;
• Vermicomposting;
• Monthly work plan;
• Exposure visit to demo plot on SRI Paddy cultivation;
• Mushroom cultivation;
• Skill development programs;
• O&M and cleaning of canals;
• Tailoring training list preparation;
• Arecanut plate making;
• Preparation of Home Products from Flax seeds;
• Dovetailing government schemes.
Baballi 8 • Strengthening women subcommittees;
• Monthly work plan;
• Entrepreneurship programs;
• Preparation of sweets etc., for festivals and special occasions;
• Mushroom cultivation;
• Waste decomposer;
• Commercial vermicompost making unit.
Kagekodamagge 4 • Strengthening of women subcommittees;
• Livelihood opportunities;
• Tailoring program;
• Exposure visits;
• Different food items preparation.
Tallikatte 8 • Strengthening of women subcommittees;
• Tailoring programs;
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 71
Name of WUCS/
Women sub-committee
Number of meetings
conducted during
Jan-Dec 2019
Topics covered in the meetings
• Bank loans;
• Kitchen garden;
• Purchasing of cow;
• Collection of D category membership fee.
Nagathibelagalu 15 • Monthly work plan;
• Tailoring program;
• Mushroom cultivation;
• Increasing the shareholders in WUCS;
• O&M and cleaning of canals;
• Areca plate making unit.
Dasarakallahalli
14 • Strengthening of women subcommittees;
• Monthly work plan;
• Tailoring programs;
• Mushroom cultivation;
• Self-employment (Bee-keeping, Solar powered Roti making & Tailoring);
• Increasing the shareholders in WUCS;
• Leadership training;
• Roti making unit;
• Bee keeping programme;
• Organic pest control Method;
• Organic certification.
Koppadoddakere 12 • Strengthening of women subcommittees;
• Monthly workplan
• Skill development programs;
• Tailoring programs;
• Mushroom training;
• Exposure visits;
• Tailoring production centre;
• Collection of D category membership fee.
Holehonnuru 8 • Monthly work plan;
• O&M and cleaning of canals;
• Tailoring programs;
• Collection of D category membership fee;
• Dovetailing government schemes;
• Beautician;
• Tailoring Product Unit;
• Candle making.
Mudlavittlapura
17 • Strengthening of women subcommittees;
• Monthly work plan;
• Skill development programs;
• Tailoring programs;
• Mushroom training;
• Increasing the number of shareholders;
• O&M and cleaning of canals;
• Commercial vermicompost unit.
Total meetings held 132
Note: Sub-committee meetings are conducted every month; some subcommittees have fixed dates such as 1st day
and 15th day of every month.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 72
Women’s Share and “D” category members in WUCS
176. The campaign to strengthen the women sub-committees continued during the reporting
period. Women from all sub-committees have come forward to pay the share amount and
become members of WUCS. Secretaries have been informed to collect the membership fee.
The progress in this regard is shown in Table 40.
Table 40: Women Shareholders WUCS wise
S. No.
Name of WUCS Name of village
No. of
“D” category members as of 30 Sept 2019
Amount paid
as of 30 Sept 2019
(INR)
No. of
“D” category members as of 30
Dec 2019
Amount paid as of 30 Dec 2019
(INR)
1 Mudlavittlapura 1. Kerebyranahalli
2. Jambaraghatta
45
21
1,125
525
0 0
2 Koppadoddakere Holehonnuru 59 1,475 0 0
3 Dasarakallahalli 1. Agasanahalli
2. Aradotlu
10
0
250
0
40
30
1000
750
4 Doddagoppenahalli Doddagoppenahalli 10 250 10 250
5 Tallikatte Jayanagara 5 125 0 0
6 Holehonnuru Danayakapura 16 400 0 0
Total 166 4,150 80 2000
177. During the reporting period, 80 more women have joined the D category of WUCS (Table 40)
which makes them shareholders in the WUCS without any voting rights. However, their
contribution @INR2000 also increases the revenue of the respective WUCS. With this, the
women members become eligible to participate in leadership training, exposure visits,
employment and skill development trainings conducted by the PSC. They also mobilize other
women members for various activities.
178. Thus, the total number of new women members during the reporting year 2019 is 246 from 6
WUCS; revenue contributed was INR6,150.
Capacity Building of Women on PIM & Livelihood Options
179. The members of the newly formed three sub-committee members (74 women) were provided
orientation on the role of women in participative irrigation management and sustainable
agriculture to ensure enhanced agricultural returns. The role and significance of women
subcommittees in livelihood and post-harvesting value addition activities was also
emphasized.
180. Notably, a majority of women (and men) from the command area did not see Gondi anicut
and the canal systems so far. PSC organized a series of visits to the Gondi anicut and the
canal system, and explained its history. A total of 47 women from 3 subcommittees were
provided exposure.
181. A total of 77 women members were provided training on leadership effectiveness in two
batches, wherein the characters, leadership skills, integrity, commitment, functionality and
time management of the different types of leaders were discussed and a leader role model
was played.
182. During the reporting year, livelihood trainings were organized on different trades and skills.
The livelihood trainings were provided on the following: 1) Production of value-added home
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 73
products (preparation of Omega-3 Laddu from Flax (sweet), Banana chips, Roti (bread)
making, ragi (minor millet) hurihittu, herbal soap and candle products); 2) Apiculture: (bee-
keeping); 3) Mushroom training; 4) Dairy development; Tailoring and Designs and 5)
Beautician training. Table 41 gives the details of trainings and participants.
Table 41: Capacity Building Activities for Women during 2019
S. No.
Training/Event (no.) No. of
women Participants
Remarks
1. Orientation to women on subcommittee formation (3nos.)
74 Preparing women for forming subcommittee
2.
Orientation to women subcommittee members on Gondi anicut and irrigation system (3nos.)
47 Exposure cum orientation training organized
3. Effective leadership (2nos.) 77 Leadership roles, management styles
4. Production of value-added home products (3nos.)
46 Omega-3 laddu from Flax; banana chips; roti making; ragi products and herbal soap making
5. Apiculture: Bee-keeping (1no.) 20 Demonstration made in the farm of a women bee-keeper at Agasanahalli
6. Mushroom Training (1no.) 67 One ready to fruit bag, Span and 5 bags for making additional bags.
7. Dairy Development (1no.) 55 Organized successfully at village level
8. Tailoring and Designs (8nos.) 220 Organized in 8 centres covering a cluster of villages
9. Beautician (1no.) 42 Handholding support provided for bank linkage
10. Interface of Bankers with women dairy farmers (1no.)
47 Organized for smoothening processing of loan application and disbursement by 6 different Banks at Bhadravathi
11. International Women’s Day (1no.) 172 Mapping of Gondi canal system by using colours (Rangoli) by women participants and other activities.
12. Participation in women mela (1no.)
361
Exhibition stall on Gondi project set up in the mela; women visitors briefed on the purpose of Gondi Modernization project and women’s empowerment approach.
Total 1228
Some continuing activities by the poor and landless
183. The following are primarily non-land-based activities by the poor and landless women, and
women with very small land holdings who desire to enhance their income to support their
families.
Tailoring:
• The banks provided loans to 38 women in two batches. NABARD agreed to release
subsidy, which varies from 25% for general category to 33% for SC/ST category
beneficiaries. Canara Bank being the lead bank in the district played a major role in
facilitating bankers to disburse the loan in the shortest time. Six more women purchased
cows from their own funds. More than half of the beneficiaries belong to SC/ST category.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 74
• A total of 119 out of the 220 shortlisted underwent a four months training in batches of
25-30 on tailoring and design conducted by Jana Shikshana Sansthan under the financial
assistance from MSDE, GoI. Interestingly, the rest 101 women are undergoing training by
meeting the resource person fee of a local tailoring teacher as well as material and other
costs. Each woman trainee contributes around INR200 per month. The lockdown has
affected the progress to a certain extent.
• Of those 119 women already trained, 30 women either own the sewing machines or have
purchased new ones. They are stitching their own and family members clothes to begin
with. Some of them have taken up tailoring as a profession and got associated with the
Tailoring and Production Centre at Koppadoddakere. they are taking orders from the
customers, in their respective local areas, mainly from women and children. At this initial
period, each woman tailor is earning at an average INR15,000 per month working on part
time basis.
• The above are in addition to those engaged in the Tailoring Production cum training
Centre at Kopppadoddakere.
Sweets and snacks enterprise:
• The sweet laddu preparation was taken up by 30 women from WUCS villages. As of now,
the sweet laddu made out of flax seeds and rich in Omega-3 fatty acids is prepared by
two women Kamala and Leelavathi from Seegebagi on commercial basis. With the help
of PSC, they not only got trained at JSS, KVK at Shimoga (Home Science Department)
but also got linked up with 3 organic outlets in Shivamogga. The preparation helps in
improving memory power in brain, especially among children. More number of women
are planning to take it up as the demand from nearby cities such as Shimoga and
Bhadravathi is high. The income earned is around INR20,000 per month, with profit of
25%. After undergoing training on preparation of value-added home products, they have
started producing and marketing of banana chips. One more woman, Parvathamma of
Doddagoppenahalli started producing Puliyogare gojju, pickle and sambar powder
making a profit of INR9,000 per month as of now at a profit margin of 30%. Two other
women, Shilpa and Vijayamma from Holehonnuru are preparing and marketing candles
earning a net profit of INR1,250 per month.
• Most of the above entrepreneurial activities for socially and economically backward
women have started in the latter part of the reporting period. It is noticed that the core
women are expanding their group, enhancing production and widening marketing and
sharing the profits along a cooperative model.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 75
Innovative Woman Entrepreneur: Beautician Service Venture
This is the story of Ms.Tanuja another innovative woman entrepreneur who has setup a beauty parlor with a product mix
approach. She started with beauty parlor and later added sale of bangle and fancy items. Tanuja is one among the 46 trainees
who underwent two months beautician training course organized in collaboration with Jana Shikshana Sansthan, Shivamogga
during June-July 2019 facilitated by the PSC. With the follow-up and handholding services from PSC, she approached Devaraj
Urs Backward Communities Development Corporation (DBCDC), Government of Karnataka, for a subsidized loan of
INR100,000, under Backward Communities Development Scheme. She also got 50% subsidy. She had undergone 4 days
additional training in order to receive the loan. The training was organized by DBCDC at Bhadravathi during August 2019.
Her shop is established in a small rented house near Honnuramma temple at Holehonnuru. Her income is steadily increasing
from INR6,000 to INR10,000 per month and she is repaying the loan at the rate of INR4,000 per month. As the business is
improving, she wants to repay the loan within 12 months. A part of the profit is also used as working capital for product mix.
Facial, eye-brow, dressing of bridges, hair style, mehandi, nail design, etc. are the services provides as part of Beauty parlor
in addition to selling bangles and fancy items. She has become an innovative entrepreneur as her 45 co-trainees are yet to
make any move.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 76
4 INFORMATION, EDUCATION AND COMMUNICATION
184. A variety of Information Education and Communication (IEC) tools and techniques have had
been employed with good results in Tranche 1 Gondi modernization project. The applications
include for raising awareness, mobilization, motivation, capacity building, post project
sustenance of irrigation assets and grievance redressal, among others. For grievance
redressal, a Gondi Modernization WhatsApp group was created involving all stakeholders of
the project, namely, engineers, contractors, WUCS Board members, progressive farmers,
and the PSC team members. During the reporting period, two more WhatsApp groups ‘Gondi
Federation’, ‘Gondi Organic Producers Group’ were started. Since the animal husbandry
activity picked up very well, another WhatsApp group called ‘animal husbandry training’ was
created on demand for the last two quarters. The members used this platform effectively; this
has resulted in saving a lot of their time and energy. Urgent meetings were convened at short
notices through WhatsApp communication. Further, a good rapport between KNNL and
WUCS was established as KNNL officers were also actively participating in the WA
conversations, often solving the problems quickly. Newsletter was another tool that spread
various success stories among the farmer community effectively and motivated them to
perform better while encouraging others. A television program was also arranged in the last
quarter of 2019. This program enabled dissemination of the success of the project to entire
State of Karnataka and outside where Kannada programs are followed. PSC encouraged
several farmers to publish their success stories in Kannada dailies with very good response.
One farmer published his story while the daily newspapers covered 5 profiles of progressive
farmers.
185. The following paragraphs detail out the progress during the reporting year under IEC while
Table 42 sums up the list of all IEC activities up to the end of the project:
• Newsletter: As planned, PSC has brought out four quarterly issues of newsletter
“Jalasampada” during the year 2019. In all, 12 issues were produced during the project
period. The newsletters cover key information and progress elements of KISWRMIP from
time to time. One page has been earmarked for views of farmers, women members,
officials and others on the ongoing Gondi modernization works. The centre-spread
carries information about one WUCS in every quarterly. The newsletter is also uploaded
on KNNL website for wider dissemination and shared with interested clientele through
email. Hard copies are distributed among select persons in WUCS villages, KNNL, CADA
and other state water institutions. The last newsletter (12th edition) under Tranche 1
project comprises ten articles about Gondi activities along with photos. The focus of
articles was mainly on income generating/augmenting opportunities for men and women
farmers, financial sustainability of WUCS, Organic certification process for the Gondi
Organic Producers Group and key highlights of the ADB November 2019 Mission.
• Publications: Though no publication was planned at the beginning of the project, PSC
published a few hand books/booklets on specific themes such as convergence of
government schemes, agriculture, songs related to water, environment and agriculture
for dissemination. The titles of the books are-krushi soulabhayagalu mattu mahiti
(information about government schemes related to agriculture); jaladhare (flow of water-
compilation of songs); and susthira krushi (sustainable agriculture). A fourth one is getting
ready for print.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 77
Compilation of Government Schemes suitable for Shimoga district was released in
January 2019 which is proving to be very useful for WUCS for availing different
programmes of the government.
The book on Susthira Krishi (Sustainable Agriculture) was released by Lance Gore,
Team Leader of the ADB Review Mission during 19-29 November 2019. The 40-page
handbook provides information on the preparation, use and utilization of 15 different
types of organic manure and liquid
fertilizers, 4 types of bio fertilizers, 7 types
of soil and water conservation methods, 4
types of biological pesticides. In addition, the
principles of organic farming, beekeeping and
measures of pest and disease control are briefly
described.
Financial Management Manual for CAD Works prepared a year ago by PSC and used
in the construction management trainings has now been finalized and released. O&M
Manual prepared and circulated for comments is due for printing.
• Short duration videos and video bank: In all, 10 short duration videos have been
completed. One more video captured the review of the Gondi modernization program on
the Doordarshan program (TV) by a panel. All these videos are available on the KNNL
website. The following is the list of videos released so far:
1. One Day workshop for WUCS on 26th Oct 2016 with English subtitles. 2. Water flowing without hurdles: Gondi FIC work with English subtitles. 3. Gondi canal modernization: with English subtitles.
4. Preparation of waste decomposer: with English subtitles.
5. Gondi Street play (our water-our responsibility): video documentation.
6. Preparation and uses of Puchimarandu (bio pesticide).
7. Preparation and uses of Vermicompost.
8. CAD package works execution of Seegebagi: with English subtitles.
9. SRI-Paddy method-farmers experience.
10. SRI method and sustainable agriculture field day at Shantappa’s farm (both short and
detailed).
11. Gondi modernization project-Doordarshan interview of the Executive Engineer of
KNNL, Bhadravathi and the President of the Gondi Federation. This 24-minute
program was telecast on 27 December 2019, at 6.30 pm. https://youtu.be/Txtf1gdXp-4
• Wall Paintings: A set of 15 slogans was prepared covering critical messages related to
the importance of water, water use efficiency, crop management, irrigation assets of the
project, sustainable agriculture practices, women participation, O&M and water tax
collection. A set of six slogans were painted on walls of each village with adjacent villages
getting slightly different slogans for greater diversity of information. The slogans and
project display boards covered 354 locations across all the 59 project villages (including
hamlets).
• Media coverage: Bengaluru Doordarshan (TV) station has produced and telecast an
interview on Gondi project. This 24-minute program was telecast on 27 December 2019,
at 6.30 pm. Ravichandra, Superintendent Engineer of KNNL, Shivamogga and BP
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 78
Chennabasappa, president of the Gondi WUCS Federation comprised the panellists. The
video can be viewed using the link https://youtu.be/Txtf1gdXp-4
• Posters for WUCS: 4 new posters have been designed during the last quarter of 2019,
printed and displayed in all newly constructed WUCS office buildings. Each poster is of
2’x3’, multicolour. Posters depict salient features of Gondi irrigation system, institutional
strengthening, roles and responsibilities of WUCS and sustainable agricultural practices.
Table 42: Summary of IEC activities for 2019
S. No.
Activity
Target
up to
Dec 2019
Achieved
as of Sep 2019 (Q1-
Q3)
Achieved during
Oct-Dec 2019 (Q4)
Cumulative up to 2019
1 Training on documentation - 02 00 02
2 Wall writings 50 365 00 365
3 Newsletter 12 11 01 12
4 Radio and TV programmes 10 46 01 47
5 Publications - 04 01 05
6 Photo album 01 01 00 01
7 Articles published in state level newspapers and web portals
- 18 03 21
8 Videos 10 09 01 10
9 Street play 23 14 00 14
10 Exhibition - 04 00 04
11 Poster - 06 04 10
12 Brochure - 08 00 08
13 Workshop * 02 03 02 05
14 Exposure visit for WUCS members to successful WUCS to exchange learning and experiences within the state
6 11 01 12
15 Exposure visit for WUCS members to successful WUCS to exchange learning and experiences outside the state
4 2 00 02
16 Gender related case studies 20 20 01 21
17 Vermicompost case studies 20 24 02 26
18 Mixed cropping case studies
* Atmavalokana (vision building) and training on organic farming, and IWRM
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 79
5 PROGRAM PERFORMANCE MANAGEMENT SYSTEM
Project Website
186. The website continues to be hosted on the KNNL website
http://knnlindia.com/kaveri2/adb.html. The website is updated with project related documents,
events, newsletters and videos/photographs from time to time. Hosting is done through
another agency hired by KNNL. PSC coordinates with the host agency for uploading.
187. All the reports generated so far both with regard to Project 1 (Gondi) and Project 2 (VNC)
have been uploaded on the website. All the deliverables including quarterly progress reports
are uploaded in addition to submission of hard copies.
PPMS
188. The Project Management Information System (PMIS) application continues to be operational.
Data entry and improvements continue. The user friendly PMIS facilitates generation of
project information in the form of reports as desired.
Monitoring of the Gondi Main Civil Works through Web-based application
189. PSC has developed a web-based application to monitor the physical works of Gondi
Modernization. The data entry could be done by authorised persons (concerned sub-
divisional engineers); the progress can be viewed by anyone who registers his email id. The
links are:
190. Link for data entry of Gondi RBC civil works:
https://sites.google.com/view/gondicivilwork/home
191. Link for viewing lining & structures reports:
https://docs.google.com/spreadsheets/d/1IAw0wpJN9-
Cle1oZLN_CFKIqRwUew6qWFl3m_bz4iH4/edit?usp=sharing
192. A mobile application has also been prepared for monitoring the ongoing VNC civil works. The
URL of this application is http://vnccivilwork.knnlindia.com/. Anybody can login to see the
reports with a user id of guest and password 123.
193. This application works on Android mobiles, Tablet, Laptop and Desktop Browsers. A separate
Android Application is also developed for this purpose for ease of use on the move.
194. Two screen shots are given below for the mobile application.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 80
Mobile App on monitoring modernization data: Screenshot of page to update canal lining works
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 81
Mobile App on monitoring modernization data: Screenshot of homepage depicting progress of works
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 82
6 CONCLUDING REMARKS
195. The Tranche 1 Gondi modernization project had to be closed at short notice on 31 December
2019 in view of DEA’s non-acceptance of the request of GoK for extension by three months,
that is, up to 31 March 2020. The modernization works continued till 31 December 2019, as
also many CAD package works. Several patch works and closing actions were yet to be
completed by the contractor which continued into the Jan-March 2020 quarter. The water
supply in the canal was released in the first week of February 2020 for a month hampering
the progress of civil patch works. All the WUCS and the KNNL engineers were completely
pre-occupied with monitoring and completing the civil works. So much so that only one DMF
indicator related to irrigation management transfer (IMT) of 7 WUCS could not be completed
(Table 5). The IMT can happen only after complete hand over of the canal system. The
intimation about extension of PSC services (at least for Tranche 2 which was under process
for a long time) came by way of an email on 31 December 2019, the day of Tranche 1 closing.
It may be noted that PSC planned and completed trainings related to IMT for WUCS and the
engineers during previous quarters.
196. As the PSC of Tranche 2 began hurriedly from 1 January 2020, also with the closing of
Tranche 1, the team continued to provide support (voluntarily) to the Tranche 1 Gondi project
to take care of some key activities. The safeguard monitoring was continued into Jan-Mar
2019 quarter, and a SMR for Oct 2019-Mar 2020 was submitted to ADB, and after comments
finalised in the third week of April 2020. Vide letter dated 21 March 2020, the PSC had also
communicated to the Chief Engineer UTP about the closing actions of Tranche 1, and also
the need for continuing the safeguard monitoring and reporting to ADB till PCR is prepared
by ADB which is expected during mid-2021 (Annexure 4).
197. In view of the lockdown situation during March and April/May 2020, preparation of PCR by
PSC is delayed. It is planned to submit in the month of May subject to lifting of the lockdown
as it requires inputs from all the PSC team.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 83
7 TRANCHE 2 MODERNIZATION OF VIJAYANAGARA CHANNELS
198. During the reporting period, the ADB Director SAER has visited KNNL Bengaluru during 3-4
July 2019 and met with KNNL and GoK officers in the context of delay in loan process. The
major delay in obtaining approval letter from finance department was addressed. In view of
the low balance budget left after meeting Tranche 1 and 2 requirements/estimate, it was
discussed and agreed to consider TLBC as a separate loan.
199. Vijayanagara Channel (VNC) system is spread over 3 districts namely Bellary, Raichur and
Koppal. The geographical area lies between latitude 14°30’ to 16°34’N and Longitude 75°40’
to 77°35’E.
VNC Civil Works Execution
200. The VNC project comprising 12 anicuts and 16 channels was split into two packages-Package
1 covering area excluding Otter Conservation Reserve (OCR) and Hampi heritage area, and
Package 2 covering OCR and Hampi heritage areas. This split up was considered essential
to advance implementation of works in the non-protected areas. The estimates and designs,
and clearances from State and National Wildlife Boards are in process.
201. The tendering process for VNC Package 1 has been completed during the first quarter of the
reporting period and work awarded on 8 March 2019. After the completion of general
elections, the modernization works have commenced in May 2019 in five channels–
Anegundi, Raya, Basavanna, Bella and Kalaghatta. Till the advent of monsoon on July 2019,
the contractor has completed all the preliminary works like jungle clearance, silt removal etc.
About 300 m length of lining in Anegundi was also completed before monsoon. The monsoon
witnessed very heavy spells of rain resulting in flooding in several parts of the state including
in the VNC project area.
Main canal lining of Anegundi channel of
VNC
ADB Mission visit to Anegundi Channel on 22
Nov. 2019
VNC Package 1 works
202. Specific works proposed in Package 1 include:
• Repairs to three anicuts and repair/reconstruction of channel headworks;
• Concrete lining of 196.62 km length along 15 Channels;
• Reconstruction of 957 appurtenant structures like bridges and crossings, drainage inlets,
relieving weirs, pipe outlets;
• Upgradation of channel access roads;
• Provision of new structures such as cross regulators, cattle ramps, and washing ghats;
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 84
• Modification of current on-line storage tanks, where feasible, to prepare actively
managed off-line storage and enhancement of existing off-line tanks;
• Remodelling of the drainage inflow and relieving weir arrangement to avoid water (and
associated sediment) entering the main channels unless required; and
• CAD works comprising lined Field Irrigation Channels (FICs).
Physical progress of main channel works
203. The total length of main channels in Package 1 is 192.62 km. with 349 structures to be
reconstructed. Out of this, as of this reporting, 7.80 km of channel lining work and 32
structures completed. However, work on the three anicuts under Package 1 is yet to be taken
up.
204. Major activities completed by the contractor include:
• Workers campsite cum concrete batching plant at Huligi finalized on 30 April 2019.
• Desilting of four channels (Raya, Basavanna, Bella and Kalaghatta) started from first
week of December 2019.
• Modernization of main and distributary channels and construction of appurtenant
structures started during second week of December 2019.
• Lining initiated on five channels (Raya, Basavanna, Bella, Kalaghatta and Anegundi) in
January 2020.
205. As per the original schedule, the modernization was expected to take place during the only
channel closure period during November-December each year. The contractor held
consultations with farmers of various channels who have agreed for: (a) partial closure, and
(b) on and off system to facilitate civil works during non-closure period (Annexure 2).
Accordingly, the revised schedule of channel closure periods will be during Jun-Aug 2019,
and Dec 2019-Jan 2020. During the reporting period, about 14,457cum of silt was excavated
from the channels and disposed of in the adjoining fields with the consent of farmers.
Channel-wise progress is presented in Table 43. Figures 6 and 7 show the progress
graphically.
Table 43: Physical Progress of works as of 29 February 2020 for VNC Package 1
S. No.
Name of Channel
Lining (km) Achieved
(%)
Structures (nos.) Achieve
d (%) Estimate
Achieved
Estimate Achieved
1 Raya 27.74 1.52 5.48 100 5 5.00
2 Basavanna 16.50 2.84 17.21 71 12 16.90
3 Bella 5.50 1.6 29.09 52 10 19.23
4 Kalaghatta 7.02 1.222 17.41 49 5 10.20
5 Ramasagara 15.50 0 0.00 57 - -
6 Kampli 23.55 0 0.00 124 - -
7 Belagodhal 11.22 0 0.00 82 - -
8 Deshnuru 9.03 0 0.00 30 - -
9 Siruguppa 10.85 0 0.00 16 - -
10 Huligi 10.69 0 0.00 77 - -
11 Shivapura 6.54 0 0.00 43 - -
12 Anegundi 19.44 0.616 3.17 122 - -
13 Upper Gangavathi 9.00 0 0.00 66
- -
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 85
14 Lower Gangavathi 9.54 0 0.00 45
- -
15 Bichal 14.50 0 0.00 23 - -
Total 196.62 7.80 3.97 957 32 3.34
Figure 7: Physical progress of lining work
Figure 8: Physical progress of Structures
206. Presently, the water supply period that began on 1 February 2020 is continuing. The
contractor is making preparatory arrangements for taking up work in Siruguppa, Deshnur,
and Anegundi channels likely from 1 April 2019.
Safeguard Monitoring for VNC
207. A detailed Safeguard Monitoring Report for the period Mar 2019 to Mar 2020 has been
prepared by PSC which is submitted to KNNL for review. Awaiting comments from ADB. The
following paragraphs provide an overall progress with regard to the safeguards monitoring
aspects.
208. The construction agreement signed by the contractor with KNNL included preparation of an
Environmental Management Plan (EMP) by the contractor as per guidelines provided in the
bidding documents. Accordingly, the contractor initially submitted a Contractor’s EMP
27.7
4
16.5
0
5.50 7.
02
15.5
0
23.5
5
11.2
2
9.03 10
.85
10.6
9
6.54
19.4
4
9.00 9.54
14.5
0
1.52 2.
84
1.6
1.22
0 0 0 0 0 0 0 0.61
6
0 0 05.48
%
17.2
1%
29.0
9%
17.3
8%
0.00
%
0.00
%
0.00
%
0.00
%
0.00
%
0.00
%
0.00
%
3.17
%
0.00
%
0.00
%
0.00
%
Lining (km) Estimate Lining (km) Achieved Achieved %
55
60 61
33
0 0 0 0 0
78
0 0 0
62
0
5
12 10
5
9.09
%
20.0
0%
16.3
9%
15.1
5%
Structures (nos.) Estimate Structures (nos.) Achieved Achieved %
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 86
(CEMP) to KNNL on 6 July 2019. This copy was shared with PSC in February 2020 after PSC
started its office in Hospet. This CEMP was found to be inadequate and hence, PSC had to
handhold the contractor’s representatives through a series of meetings and interactions
explaining each and every aspect of the CEMP that needed to be adhered to. PSC, inter alia,
advised the following:
• The contractor should re-submit a modified CEMP as explained to reflect the likely
environmental issues and mitigation actions following the EIA;
• The contractor should record and provide baseline air, noise, water and soil
measurements at the construction sites;
• The contractor should record and provide information on the baseline status of the site
identified for quarries and borrow pits;
• The contractor should record and provide information on the baseline tree survey and
trees identified to be cut at the construction sites, adhering to prevailing guidelines of
the forest department;
• The contractor should provide information on approvals obtained for locating the labour
campsite, establishing the Ready-Mix-Concrete batching plant, utilising the village roads
for truck travel and for disposal of excavated silt on willing farmers lands.
209. Subsequently, with the assistance of PSC, the contractor revised and shared the CEMP along
with action plans on 26 February 2020 to the PIO marking with a copy to PSC. The CEMP
has been approved by KNNL and submitted to ADB. The CEMP now also includes an
organizational chart of the contractor and the approval letter of KNNL along with CEMP.
210. Key aspects of modernization work done by the contractor as of reporting:
• Vegetation along the channel right of way was cleared to provide access and working
space for construction activities and removal of silt. About 5399cum of silt was removed
from Basavanna channel, 4706cum from Raya channel, 3048cum from Bella channel
and 1304cum from Kalaghatta channel;
• About 47,849 cum of filling material from approved quarries/borrow areas was used to
restore the channel cross section and access track;
• Gravel surfacing of channel roads has been laid down using material from approved
quarries /borrow areas;
• Concrete lining has been carried out using mechanised paving equipment or hand
placed concrete depending on site situation;
• Concrete for paving equipment has been supplied by ready‐mix concrete but concrete
for hand‐placed lining was mixed on site; and
• Channel structures were reconstructed using reinforced cement concrete.
211. The key progress elements carried out as part of the Evaluation of the EMP are as follows:
• Pre-construction phase, the contractor has made tree enumeration and prepared a
report of trees along the channels. Prior to starting of modernization work, the local
residents along Raya and Basavanna channels have cut the trees themselves. As part
of EMP implementation, the contractor has agreed to plant trees in the ratio of 1:3 in
consultation with the local residents and the Karnataka Forest Department.
• The contractor has provided employment to a few local persons at the construction sites
to pre-empt any conflict situations.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 87
• PSC has carried out a few orientation sessions for the contractor’s staff as well as the
labour on importance of social and environmental safeguards. Formal trainings have
also been conducted involving experts as resource person. Training on health and safety
have also been conducted. Contractor has been carrying out health camp to take care
of the health of the labour and staff. ADB consultant has also conducted a two-day
training program. Contractor has been advised to place a register at campsite and
conduct monthly health check-up.
• Workers engaged in the project are appraised of basic work site rules related to personal
protection and preventing injury to fellow employees. PSC advised the contractor to
deploy trained safety supervisors at the work sites to train workers on topics such as
basic hazard awareness, safe work practices, emergency procedures in case of fire,
evacuation and natural disasters.
• Contractor provided all facilities like safe drinking water, hygienic living conditions,
sanitation facility, LPG and nutritious food to workers at camp sites.
• The contractor has fixed appropriate sign boards at camp site for the purpose of safety.
• The excavated silt from the channels is found chemically suitable for application in
agriculture lands and with the consent of farmers the silt has been applied in agriculture
lands.
• Contractor reported that there are no fish spawning and aquatic fauna, no wildlife
habitats or a wildlife movement corridor exists in the stretches taken up so far in the
reporting period.
• Chance finding of archaeological sites did not occur so far in the stretches taken up in
Package 1 of VNC for modernisation.
• The sprinkling of water to prevent dust is effectively implemented by contractor.
• People in the surrounding areas use culverts for crossing the channel and no incidence
of reduced access for local population has been reported along the stretches taken up
in the reporting period.
• Contractor has obtained permission from Tungabhadra Board to excavate limited
quantities of murrum from the foreshore of the Tungabhadra reservoir. M-Sand is being
used for construction - Hence possible change in river course and river scouring action
at this stage of work is not anticipated.
• Murrum mining pit/ borrow area closure plan includes back filling of pit with construction
debris. Bioremediation and planting of soil binding species, growing dense plants to
reduce soil erosion due to wind and rainfall.
• PSC and KNNL are pursuing with the contractor to make him comply with program for
civil works execution keeping the closure periods under consideration.
• As a part of grievance redressal mechanism based on site conditions the contractor
agreed to provide a common outlet to a group of farmers to drain excess irrigation water
below the IP and avoid water logging conditions.
• As part of the Grievance Redressal Mechanism, the contractor has been advised to set
up one drop box each at the work site, and at camp site. In addition, GRM registers to
be provided at each of the WUCS where work is under progress. Furthermore, like in
Gondi project, the WhatsApp will also be used to capture complaints and facilitate
earliest redressal.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 88
VNC Package 2 works:
212. As for VNC package 2 comprising the OCR and Heritage Areas, the schedule B is being
revised by KNNL even as the bid document is under preparation by the PSC. The inspection
reports from two districts–Bellary and Koppal have been uploaded online by the FD. The
matter will have to be placed before the next State Wildlife Board meeting, and then forwarded
to the National Board for Wildlife for final clearance.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 89
8 TLBC
213. The proposed Modernization plan of TLBC submitted by the International Irrigation
Management Expert (IIMS) hired through ACIWRM has five sub-plans:
1. System Control and Operations Plan (SCOP).
2. Critical Non-control Structures Rehabilitation Plan (CNCSRP).
3. Water Users Cooperative Society Participation Plan (WUCSPP).
4. KNNL Strengthening Plan (KNNLSP).
5. Water Quality Management Plan (WQMP).
214. The interventions proposed in each of these subplans are aimed at providing an integrated,
holistic solution to modernising the TLBC system.
215. The project is proposed to be implemented on a Design, Build and Operate (DBO) basis over
a 4-year first phase period during which all the regulators are proposed to be completely
automated. The critical non-control structures such as aqueducts, siphons, culvert crossings
will have to be rehabilitated separately and simultaneously to the control structures. During
these processes and parallel to the hardware execution, WUCS which are by and large
dormant have to be mobilised and strengthened to prepare them for the operation and
maintenance of the tertiary canal system. Since the TLBC water is used for a variety of
purposes other than irrigation it is proposed to maintain the quality of water by reducing the
impact of ancillary uses of the water.
216. The first phase of the proposed Modernisation project of 4 years is estimated by the IIMS to
cost around USD263.48 million. The cost does not include cost of critical but non-control
structures. It may be noted that decision is to be made by KNNL on: (a) the project period of
the TLBC, (b) Budget for beyond 4 years, that is for a total of 9-10 years.
217. During March 2019, the reporting period, tender for DPR for TLBC was called for. The EI
Tech was shortlisted and awarded the work in June 2019. The terms of reference of the
design consultant include preparation of command area maps, reconnaissance survey,
topographical survey of main canal and distributary network, detailed engineering including
preparation of designs, drawings and estimates for critical and non-critical structures coming
under TLBC and balance distributaries, preparation of Detailed Project Report in consultation
with ADB/ACIWRM for comprehensive modernization of TLBC under KISWRMIP as a
separate loan. On receipt of the schedule B and estimates, the bid document shall be
prepared by PSC.
Table 44: Milestones and activities for TLBC (per ADB loan review mission of Nov 2019)
Activity By whom Due Date Remarks
Completion of TLBC modernization plan
ACIWRM/ KNNL
31 Dec 2019
Detailed Modernization Plan for TLBC submitted by International Irrigation Modernisation Specialist in March 2019. Tender for design consultant floated in March 2019 and shortlisted working on the DPR, engineering designs and estimates. Expected submission April/May 2020.
Submit PPR to DEA KNNL 31 Jan 2020 PFR delayed due to delay in the DPR and estimates.
218. PSC for TLBC: As discussed and agreed during meetings with MD KNNL, the PSC ideally
should be in place at least a year or two in advance of launch of TLBC modernization works.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 90
Since the modernization of TLBC also includes automation, it is critical that the beneficiary
farmers are well prepared to accept the project and maintain the assets including the
expensive automated components. Adequate awareness, orientation and training on various
aspects of modernization are critical which are to be carried out by PSC. Therefore, the
process of putting in place the PSC also should be initiated well in advance.
219. In addition, specifically in the TLBC project, there is a need for clarity as regards the following
aspects are concerned which have a bearing on the economic and financial feasibility (study)
in particular:
• Command coverage and phasing: The command area of TLBC is 244,000 ha. What
model will be adopted for implementation of the comprehensive modernization plan?
Whether DBO model or State (and ADB funding) or a mix. What is the phasing of the area
to be covered and how?
• Duration: The duration of execution mentioned in the IIMS CMP is 9 years. The first 4
years is proposed for modernization (including automation). How does one ensure WUCS
are in place and prepared for modernization/ automation?
• Preparation of WUCS: There would be at least 550 WUCS in the 244,000 ha command.
Very few are reported to be active. Formation/strengthening of WUCS itself will take a few
years. Hence, the phasing of modernization should be aligned with the phasing of
preparation of WUCS. Mismatches will be costly errors.
• Finally, there should be clarity on the approach to be adopted for conducting economic
and financial feasibility of TLBC especially in view of high investments, automation and
modernization aspects and huge command area.
220. It is therefore critical to have a detailed discussion on all these aspects and more.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 91
9 PROJECT STAFF MOBILISATION
Mobilisation During the Reporting Period
221. Table 45 gives details of inputs of PSC specialists during the reporting period.
Table 45: Staff mobilization during January-December 2019
Expert Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total 2019 2019 2019 2019 2019 2019 2019 2019 2019 2019 2019 2019
IS/TL 0.53 0 0.57 0 0 0 0 0 0 0 0 0 1.1
PIM/DTL 1 1 1 1 1 1 1 1 1 1 1 1 12
AGRI 1 1 1 1 1 0 0 0 0 0 0 0 5
CMS 1 0 0 0 0 0 0 0 0 0 0 0 0 0
CMS 2 0.42 0 0 0.03 0.97 1 0.17 0 0 0 0 0.48 3.07
COM/DOC 0.9 1 1 1 0.9 1 1 0.77 0.77 0.9 0 0.94 10.18
ENV 0 0 0 0.4 0 0 0.1 0.26 0 0.28 0.2 0.52 1.76
MIS 0 0 0 0 0.29 0 0 0 0 0 0 0 0.29
OMS 1 1 1 1 1 0 0.3 0.45 0 0 0 0 5.75
AE/FMS 0 0 0 0 0 0 0 0 0 0 0 0 0
PROC 0 0 0 0 0 0 0 0 0 0 0 0 0
SD&GS 0.71 0 0.57 0.5 0.42 0 0.43 0 0 0 0 0 2.63
WIS 1 1 1 0.93 1 1 1 1 1 1 1 1 11.93
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 92
10 CHALLENGES FACED AND ADDRESSED
222. The following are some of the key challenges faced during the preparatory phase of Tranche
2 and TLBC, some of which have been addressed:
1. The KNNL ICZ in general faced absence of regular incumbents in key senior positions
which affected decision making and monitoring of activities related to Tranche 2 VNC
and TLBC.
2. State level political situation affected the working of the government, and resulted in
delays.
3. The monsoon of 2019 witnessed some unprecedented level of rainfall events which
caused damage to crop.
4. Delays in the approval process of Tranche 2 VNC resulted in delay in the launch of
the VNC project.
5. Delay in finalizing the award of PSC has resulted in absence of PSC for a long period
of VNC execution. The VNC modernization was awarded in March 2019, and PSC for
Tranche 2 was awarded with effect from 1 January 2020. The email asking Tranche
1 PSC to initiate Tranche 2 activities was received on 31 December 2019, which was
also the closing date of Tranche 1, and without any mobilization period. This resulted
in overwhelming burden on the PSC team in terms of identifying office spaces for PSC
and 3 field offices, guest houses accommodation, shifting from Shimoga to Hospet
(Kamalapura, Gangavathi and Siruguppa), mobilizing additional SST staff and
experts, among others. Alongside, there was also the additional work load of
preparing and training contractor and his staff on safeguards and preparing safeguard
monitoring report of VNC from March to December 2019. While PSC has tried its best
to face all these challenges, more organised and timely decisions would help avoid
undue burden and stress for PSC whose efforts should ideally be on supporting the
project tasks.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 93
Annexure 1
Gondi WUCS Administration: Baseline Assessment
1. INTRODUCTION
The Karnataka Integrated and Sustainable Water Resources Management and Investment
Programme (KISWRMIP) supported by Asian Development Bank, has a component of
forming/strengthening Water Users Cooperative Societies (WUCS) under Gondi Modernization
Project 1. A strong, vibrant WUCS is critical to the success of Participatory Irrigation Management
(PIM). As a part of the KISWRMIP, WUCS is also entrusted with constructing their own
infrastructure such as the Field Irrigation Channels (FICs) and WUCS office buildings to induce
a strong sense of ownership. This approach seems to be materialising as reflected in the active
participation of WUCS in the ongoing Command Area Development (CAD) package works as
well in the quality.
2. OBJECTIVE OF PERIODIC BASELINE ASSESSMENT
There are 11 WUCS in the Gondi Irrigation System. Baseline assessments have been carried
out from time to time to assess their performance. As of reporting period, thirteen baseline
assessments have been carried out against the identified 29 identified parameters. The first
baseline assessment was designed and carried out during September/October 2016 and the
thirteenth during December 2019. An action plan is generally developed based on the findings of
each of the assessments to enhance the institutional performance as well as knowledge and
skills base of the WUCS office-bearers and members.
3. METHODOLOGY AND DATA COLLECTION
As part of methodology, PSC visited each of the 11 WUCS, conducted meetings with both the
office bearers as well as a cross-section of members including women. Along with the indicators,
qualitative discussions were also held to understand the process of change. Table below provides
the change between the first and ninth rounds of assessment.
Annual Progress Report January-December 2018
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 94
Gondi WUCS Performance Indicators
S. No. Activity Dodda Goppenahalli
Baranduru Seegebagi Tallikatte Koppa Doddakere
Baballi Nagathi belagalu
Holehonnuru Kage Kodamagge
Dasarakallhalli Mudala Vittalapura
1st BL 13thBL 1st BL
13thBL 1st BL
13thBL 1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1 WUCS Office N Y N Y N Y Y Y N Y N Y N Y N Y Y Y N Y N Y
2 WUCS Board N Y Y Y N Y Y Y N Y N Y Y Y N Y Y Y Y Y N Y
3 Secretary appointed N Y N Y Y Y Y Y Y Y N Y N Y N Y Y Y Y Y N Y
4 WUCS Byelaws Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
5 Total farmers list Y Y N Y Y Y Y Y Y Y Y Y N Y N Y Y Y Y Y N Y
6 List of shareholders/ membership
Y Y N Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
7 Registration certificate
Y Y Y Y N Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
8 GB members list Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
9 General Body meeting minutes register
N Y N Y N Y N Y N Y N Y N Y N Y N Y N Y N Y
10 Governing Body meeting minutes register
N Y N Y N Y Y Y Y Y N Y N Y N Y Y Y N Y N Y
11 Meeting notice file Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y N Y
12 Cashbook Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
13 Annual audit report N Y N Y N Y Y Y Y Y Y Y N Y N Y Y Y Y Y N Y
14 Income and expenditure register
N Y N Y Y Y Y Y N Y N Y Y Y N Y Y Y N Y N Y
15 Letterhead N Y N Y N Y Y Y Y Y N Y Y Y Y Y Y Y Y Y N Y
16 Inward & Outward Register
N Y N Y N Y N Y N Y N Y N Y N Y Y Y N Y N Y
17 PAN Card N Y N Y N Y Y Y Y Y Y Y N Y N Y Y Y N Y N Y
Annual Progress Report January-December 2018
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 95
S. No. Activity Dodda Goppenahalli
Baranduru Seegebagi Tallikatte Koppa Doddakere
Baballi Nagathi belagalu
Holehonnuru Kage Kodamagge
Dasarakallhalli Mudala Vittalapura
1st BL 13thBL 1st BL
13thBL 1st BL
13thBL 1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
1st BL
13th BL
18 TIN/GST/TAN N Y N Y N Y N Y N Y N Y N Y N Y Y Y N Y N Y
19 Name of the Bank, Account Number and address
N Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
20 Amount deposited with bank account
N Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
21 Governing Body attended training
N Y Y Y N Y Y Y Y Y Y Y Y Y Y Y Y Y Y Y N Y
22 Exposure visit to WUCS in Karnataka and other places
N Y N Y N Y N Y N Y N Y N Y Y Y Y Y N Y N Y
23 Cadastral, soil & land use maps
N Y N Y N Y N Y N Y N Y N Y N Y N Y N Y N Y
24 Crop particulars detail list
N Y N Y N Y N Y N Y N Y N Y N Y Y Y N Y N Y
25 MOU with KNNL N Y N Y N Y Y Y Y Y N Y Y Y N Y Y Y Y Y N Y
26 One-time functional grant
N N N N N N Y N Y N N N N N N N Y N N N N N
27 Works taken up by WUCS
N Y N Y N Y Y Y Y Y N Y N Y N Y Y Y N Y N Y
28 Collecting water charges
N Y N N N Y N N N Y N Y N N N Y Y Y N Y N Y
29 O& M activity done N N N N N N N Y N N N Y N N N N Y Y N N N N
Total No. of Parameters 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29
No. of parameters achieved / in place
7 27 9 26 10 27 21 27 18 27 12 28 13 26 11 27 27 28 14 27 0 27
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 96
4. KEY FINDINGS
S.
No. 1st round (September/October 2016) 13th round (December 2019)
1 • 8 out of 10 WUCS do not have offices;
• 5 WUCS do not have Secretaries;
• 4 WUCS need to organize letter heads.
• All 11 WUCS are functional.
• As of this report all 11 buildings of WUCS and
the Federation building have been completed.
• All the WUCS have Secretaries; Letter heads
are printed and being used.
2 • 3 WUCS do not have total farmers list;
• One WUCS needs to prepare List of
shareholders;
• All 10 WUCS do not maintain general
body meeting register;
• 3 WUCS to maintain governing body
meeting register.
• All WUCS maintain list of farmers;
• All WUCS have prepared list of shareholders;
• All WUCS maintain General body meeting
register, and
• All WUCS maintain Governing body meeting
Registers.
3 WUCS do not maintain cadastral, soil use
and land use maps.
All WUCS have cadastral map, soil use and land use
maps in the office.
4 Only 4WUCS completed last annual audit
report
All 11 WUCS have completed updating of books for
FY 2018-19, annual audit also completed and report
submitted to ARCS CADA.
5 Only 3 WUCS maintain income and
expenditure book.
All 11 WUCS are maintaining income and
expenditure book with regular updations.
6 No WUCS has GST and filing returns All WUCS have GST registration and are filing
returns regularly.
7 Only 3 WUCS obtained PAN card. No
WUCS is having TAN number.
All WUCS have PAN and TAN numbers.
8 Only 1 WUCS is maintaining inward and
outward register.
All WUCS maintain inward and outward registers
and updating regularly.
9 5 WUCS only signed MOU with
KNNL/CADA;
All WUCS are now signed with KNNL/CADA;
10 3 WUCS mobilized one-time grant. No WUCS mobilized fresh members this quarter and
therefore they did not apply for one-time grant from
CADA.
Even for the three WUCS for which the grant is
pending, CADA could not release the amount for
want of funds from the Government.
11 1 WUCS was collecting water cess. Eight WUCS have collected water tax during this
quarter except Baranduru, Tallikatte and
Nagatibelegalu WUCS.
Talikatte, Seegebagi, Baranduru, Mudalavitalapura,
Koppadoddakere, Baballi and Dasarakallahalli
WUCS got an additional INR1.0 lakh from CADA for
successful collection of water cess, (and other 3
WUCS Doddagoppenhalli, Holehonnuru and
Nagatibelegalu under process).
12
CAD package works-Financial progress
All WUCS have completed CAD package works-
both from both Phase 1 and 2;
Phase 1:
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 97
S.
No. 1st round (September/October 2016) 13th round (December 2019)
A total of 130 packages were taken up for a length
of 165.74 kms out of which 162.23 km has been
completed. A few metres in each of the WUCS was
not possible to be done due to site conditions.
Phase 2:
Under Phase 2 a total of 82 CAD packages were
taken up for FIC works over a length of 111.42 km
out of which 110.26 km has been completed. All the
packages have been competed as of this reporting.
In addition, 11 WUCS buildings and 1 federation
building (3 packages), 6 control gates packages, 1
O&M kit package, 3 furniture packages, 3 anicut
protection works packages and 4 tank repair works
packages were also taken up and completed as of
this reporting.
Thus, in all 243 CAD packages have been awarded
and completed as of this reporting.
13
O&M activity
3 WUCS (Kagekodamagge, Tallikatte and Baballi)
have undertaken O&M activity during this quarter
and cleaned branch canal and FICs in their
command area.
14 IT returns
All 11 WUCS have filed their Income Tax returns by
31 March 2019 for FY 2018-19.
5. CONCLUSION
The baseline assessments are clearly indicative of significant improvement in the performance
of all the WUCS in general in terms of institutional strengthening and performance. With the
experience of Phase 1 and Phase 2 CAD package works, trainings and handholding from PSC
the quality of civil works executed by WUCS has improved significantly. The quality of civil works
and supervision of work by the members of WUCS Boards has also improved significantly in
Phase 2. WUCS are also taking greater ownership of the assets created. Most of the WUCS have
start taking up maintenance works on the FICs involving farmers. WUCS have also started
collecting water tax in their command areas. These aspects clearly show that they are developing
ownership of their assets and are also concerned (Annexure 3) about their sustainability. The
new Mudlavittlapura WUCS has come a long way to register improvement in 27 out of 29
parameters though it is the youngest of all the WUCS. Doddagoppenahalli and Baranduru have
also improved significantly since the 1st survey to come close achieving all the 29 parameters.
The WUCS have, thus, come a long way since the first baseline survey in September 2016.
The Gondi Federation had a lot of problems which hampered its effective functioning. With a lot
of perseverance, persuasion and capacity building actions, the functioning of the federation
improved significantly during the last half year. The federation and the WUCS feel that at least a
year of continuation of PSC would have put them in much better position in terms of institutional
sustainability.
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 98
Annexure 2
Working period of modernisation of Vijayanagara channels (Package 1) between March 2019-September 2021
I) No. 2 Canal Division, Odderahatti
S. No.
Name of the Canal
Mar to May 2019 Jun to Aug 2019 Sep to Nov
2019 Dec 2019 to Jan
2020 Feb to Apr
2020 May 2020 to Jul
2021 Sep-21
1 Upper Gangavathi
Mobilization Closure period Non-closure
period Closure period
Non-closure period
Closure period Non-closure
period
2 Lower Gangavathi
3 Anegundi
4 Shivapura
5 Huligi
Mar to May 2019 Jun 2019 to Mar 2020 Apr to Jul 2020 Dec 2020 to
Sep 2021
II) No. 5 Canal Division, Yeramarus
1 Bichal Mobilization Non-closure period Closure period Non-closure period
Mar to May 2019 Jun to Nov 2019 Dec 2019 to
Jan 2020 Feb to Mar 2020
Apr to Jun 2020
Jul-20 Dec 2020 to
Jun 2021 Jul to Sep 2021
III) No. 6 Canal Division, Bellary
1 Siruguppa Mobilization
Non-closure period
Closure period Non-closure
period Closure period
Non-closure period
Closure period Non-closure
period 2 Deshnur
Mar to May 2019 Jun to Nov 2019
Dec 2019 to Jan 2020
Feb to May 2020 Jun 2020 to
Jan 2021 May-21 Jun to Jul 2021 Sep-21
IV) TR D Division, Munirabad
1 Bella
Mobilization Non-closure
period Closure period
Non-closure period
Closure period Non-closure
period Closure period
Non-closure period
2 Raya
3 Basavanna
4 Kalaghatta
5 Ramasagara
6 Kampli
7 Belagodhal
Annual Progress Report January-December 2019
Karnataka Integrated and Sustainable Water Resources Management
Investment Program (KISWRMIP)
Page | 99
Annexure 3
Letter from Tahsildar of Bhadravathi giving powers to WUCS to collect water tax from
the farmers.