An Analysis of the Challenges Faced by Multi- stakeholder ...
-
Upload
khangminh22 -
Category
Documents
-
view
0 -
download
0
Transcript of An Analysis of the Challenges Faced by Multi- stakeholder ...
Troubles on the Way: An Analysis of the Challenges Faced by Multi-
stakeholder Platforms
DRAFT – do not disseminate
Nicolas Faysse
ABSTRACT
Multi-stakeholder platforms (MSPs) have been widely promoted as a negotiation tool in
resolving conflicts, first in developed countries and more recently as a global good
practice. However, many MSPs have been implemented in an unfavourable context –
primarily of social inequities – and did not meet the initial high expectations. Five
challenges that place MSPs in an unfavourable context are analyzed: a) power
relationships, b) platform composition, c) stakeholder representation and capacity to
participate meaningfully in the debates, d) decision-making power and mechanisms, and
finally e) the costs of setting up an MSP. The analysis is based on two case studies of
MSPs set up in inauspicious conditions. The first studied water user associations in South
Africa, and the second studied a negotiation platform set up to resolve conflicts over a
water and sanitation project in Bolivia. It is argued that MSPs should be seen less as an
ideal communication process, and more as an always imperfect negotiation process, whose
positive outcomes may outweigh the negative ones if the abovementioned challenges are
adequately taken into account.
INTRODUCTION
Multi-stakeholder platforms (MSPs) are fashionable these days. An MSP is any discussion
and negotiation process where the stakeholders involved in a problem or a specific issue come
together to look for solutions. This paper looks particularly at natural resource management
MSPs which, according to Steins and Edwards (1999), are processes in which stakeholders: i)
work collectively towards an understanding of the resource base; ii) cooperate in solving
social dilemmas associated with collective resource use; and iii) undertake joint actions with
respect to the perceived problems. These MSPs are characterized by the diversity of the
2 Nicolas Faysse
2
stakeholders coming to the platform, e.g., resource users, national or local government
representatives, NGOs and academics. They encompass such different processes as a
catchment management committee, a roundtable to discuss forest management problems, or
an international conference on landmine use (Hemmati, 2002).
MSPs have been motivated largely by the progressive promotion of ‘participatory
democracy’ to complement the limits of more traditional ‘representative democracy’. This
shift is illustrated by the more and more common call for public debate before any large-scale
infrastructure project, especially in Europe.
Use of MSPs has also been progressively institutionalized. For instance, the Dublin
Statement on Water and Sustainable Development asserted that users should be incorporated
in decision-making (1992: Principle 2). Later, this idea was formalized by the European
Union in the European Water Framework Directive (2000: Consideration 14), which also calls
for public participation in water resource management decision-making. Moreover, countries
as diverse as Brazil, France, Mexico, South Africa and Zimbabwe have clearly enshrined
participation of stakeholders in the decision-making for water resource management (Brazil,
1997; France, 1992; Mexico, 1992; South Africa, 1998; Zimbabwe, 1998). At international
level, the World Commission on Dams has been another emblematic figure in this new form
of dialogue. MSPs have mainly been initiated in developed countries, and have been
increasingly exported as an example of ‘good governance’ for developing countries, for
instance, in the cases of the Water Acts of South Africa and Zimbabwe (South Africa, 1998;
Zimbabwe, 1998).
Many countries provide an enabling environment for successful MSPs, based mainly on
well-organized stakeholder groups, few power imbalances, and a state that fully supports
MSP processes and outcomes. For instance, groundwater overuse was negotiated in California
through MSPs, and the results were largely successful (Blomquist, 1992). However, many
documented MSPs set up in unfavourable circumstances have fallen short of expectations,
with large differences between theory and results on the ground (Castellanet, 1999; Edmunds
and Wollenberg, 2001; Hirsh and Wyatt, 2004; Manzungu, 2002; Moreyra and Warner,
2004).
It is in this context that the present document analyzes the main challenges faced by MSPs
set up in unfavourable circumstances. These can be defined as: i) high social inequities; ii) a
state that is either too strong or too weak to support MSP negotiation processes; iii)
disorganized stakeholder groups; and iv) lack of the financial and technical capacities to
Troubles on the Way 3
3
implement MSPs. This paper reflects on the practicalities of implemented MSPs and
highlights the stumbling blocks to setting them up.
The ideas developed here may be of interest for academics who want to study the issues of
implementing MSPs, for practitioners trying to design an MSP, or for those supporting
specific stakeholder groups’ participation in existing MSPs. However, this paper does not
propose how to organize MSPs (for this, see for example Hemmati, 2002; Susskind and
Cruikshank, 1987).
MSPs are generally used as a means of calling various stakeholder groups together for two
main reasons: to discuss the management of common pool resources or to discuss a specific
investment project. The focus of this article is mostly on water-related MSPs, though the
analysis is deemed to be valid for any kind of MSP. Special attention will be given to two
MSPs that were investigated by the author: first, permanent MSPs for water resource
management in South Africa, and second, a short-term MSP to resolve conflict over a
drinking water and sanitation project in Bolivia. Though permanent and short-term MSPs are
very different in terms of practical implementation issues, they both face the same challenges.
Five challenges
Of the many issues that revolve around MSP design and implementation, five have been
selected here, based on their importance in the two baseline case studies: i) power
relationships within the MSP; ii) choosing the composition of the MSP and its effect on
invited stakeholders’ decision to participate; iii) stakeholder representation and capacity to
participate meaningfully in debates; iv) the decision-making powers and mechanisms of the
MSP; and finally v) the costs of setting up an MSP. All these issues are specific to MSP
processes, except for the issue of representation.
MSP enthusiasts often disregard these issues. For instance, MSP analysts such as
Hemmati (2002) deemed the five above-named challenges to be side issues that merely
needed to be considered some time during the process. In the same way, in South Africa and
Zimbabwe, the two challenges of achieving genuine inclusion of stakeholders and of
balancing power relationships were not given real consideration when their Water Acts were
written. It was thought important to get the process going first and that these side issues
would be resolved on the way. The main argument of this paper is that it is important to face
these five challenges, and that facing them is even key to the success of any MSP process
where there are asymmetries of power. One could obviously outline other important issues;
4 Nicolas Faysse
4
for instance, how to find the resources to ensure continued functioning of a permanent MSP,
or the legitimacy and neutrality of the possible external facilitator. However, it is these five
issues particularly that should not be brushed aside for consideration later, once the MSP is
functioning.
The paper first presents the origin and key characteristics of MSPs, followed by a brief
description of the two baseline case studies whose experiences will be used throughout the
paper. Then, each of the five challenges is discussed in detail. A final section presents the
general outcomes of the two baseline MSPs studied, and discusses whether they were
eventually worth the trouble of holding them.
MSPS: ORIGIN AND CHARACTERISTICS
Though MSPs can be very different from each other, the generic objective of an MSP can be
defined as: To enable the empowered and active participation of stakeholders in the search for
solutions to a common problem. This empowered and active participation refers to the highest
rungs of the ladder of participation defined by Arnstein (1969). MSPs are based on the
identification of stakeholders, whether groups or persons. Indeed, frameworks for public
participation have been progressively influenced by the idea of what has been termed ‘a
society of stakeholders’ (Warner, in press). Stakeholders are ‘those who have an interest in a
particular decision, either as individuals or representatives of a group. This includes people
who influence a decision, or can influence it, as well as those affected by it’ (Hemmati, 2002:
2). The word has been given growing emphasis in the 90s, and is now completely unavoidable
in any discussion on natural resource management (Grimble and Wellard, 1997).
There are two main expectations behind setting up MSPs. First, MSPs are expected to lead
to better decisions that are better accepted than the decisions resulting from state-led
processes. A second expectation of MSPs is that they lead to better and more acceptable
decisions than those arising from to one-to-one negotiations.
MSPs are preferred over state-led processes because MSPs came from a general change of
paradigm. To explain this change of paradigm very simplistically, in the 60s the state was
generally considered to be the most able body to organize decisions and lead projects. In the
field of natural resources management, this went together with a mistrust of community-based
management (Hardin, 1968). Later, when it appeared that the state could not make efficient
decisions and implement them alone, ‘participation’ and ‘decentralization’ became buzz
words. A new paradigm appeared, which could be summarized in the two following
Troubles on the Way 5
5
assertions: i) stakeholders always have more information than a central authority, and they
tend to be more interested in achieving a satisfactory solution; and ii) stakeholders are more
likely to accept a project or a solution to a problem if they have been part of the decision-
making process. Participatory approaches to solving problems have been used for some time
now, as shown by the large body of literature on alternative conflict resolution (e.g., Susskind
and Cruikshank, 1987).
MSPs are preferred over one-to-one negotiations because an MSP is primarily an ‘open
space’ where several stakeholders exchange ideas and negotiate. In that sense, an MSP is just
a step in the negotiation process: Stakeholders will negotiate before and after the MSP, but
also in parallel, outside it. These side negotiations can be formal or informal, between two
stakeholders or more, and even possibly in another parallel MSP. Therefore, analysis of what
takes place during the MSP should not be considered sufficient to understand the complete
negotiation process.
MSPs can be permanent or of limited duration: Permanent MSPs are often set up to
manage natural resources and are frequently legalized; short-term MSPs are usually set up to
manage or prevent a conflict. They all have three important characteristics. First, MSPs are
processes in which well-defined stakeholders are invited to participate (A forum for public
debate, where everybody is entitled to come, whether he has a stake or not, is not considered
an MSP). Second, stakeholders are usually too numerous for them all to participate in the
platform so they form groups, which designate representatives to the MSP; this leads to
specific representation problems that will be analyzed hereafter. Third, MSPs are considered
here as processes where discussions are scheduled to be linked in some way to decision and
action.
Indeed, the five challenges presented are predominantly for an MSP linked to decision-
making; they are of much less importance for a forum where no decisions are to be taken.
Therefore, a process that aims just at informing stakeholders about a given issue, or giving
policy recommendations with no recognition from the authorities, will not be termed an MSP.
The processes considered here as MSPs are processes: i) that have decision-making power
formally acknowledged by authorities; ii) whose participants are officially recognized as a
consultative group, i.e., the authorities are required to officially receive and review their
recommendations, though they are not bound to abide by them; or iii) whose participants will
themselves implement decisions taken during the MSP.
6 Nicolas Faysse
6
TWO BASELINE CASE STUDIES
This paper will mainly refer to two case studies in which the author participated. The
complete studies are published in Faysse (2004b), Faysse and Gumbo (2004), Faysse et al. (in
press), and Seshoka et al. (2004). The two examples are very different, but both are MSPs and
they share many common core issues.
The first baseline case study deals with the new water resource management organizations
in South Africa, where a new Water Act was passed in 1998, mainly to address problems
inherited from the previous discriminatory regime. The Act scheduled the creation of
Catchment Management Agencies and, at local level, Water User Associations (WUAs). Both
organizations are a point of encounter for Black and White water users. A two-year research
study was carried out on the results of including Black users in the new WUAs, created from
Irrigation Boards, which previously had only White members.
The second baseline case study was a short-term MSP to solve a conflict over a water and
sanitation project in a periurban area of Cochabamba, Bolivia. In 2001, because of a very fast
urbanization process, the Tiquipaya and Colcapirhua Municipal Government decided to
design an inter-communal water and sanitation project called MACOTI. However, the local
communities soon became deeply divided between opponents and supporters of the project. In
2004, the Vice-Minister of Basic Services, looking for a negotiated solution of the conflict,
proposed to organize a Technical Roundtable (Mesa Técnica in Spanish) in Tiquipaya to
undertake an in-depth review of the project and negotiate an agreement. The Negowat
research project was at that time working on methodologies for negotiating water access and
land use in the Tiquipaya area, and the Negowat research team (to which the author belonged)
offered its help in organizing the Technical Roundtable. This was accepted by the Vice-
Ministry, the Tiquipaya Municipality, and various social organizations of Tiquipaya, and the
roundtable eventually took place during the whole second semester of 2004.
Apart from these two baseline case studies, the analysis will be enriched from the
experiences of other MSPs documented in Argentina (Moreyra and Warner, 2004), Brazil
(Castellanet, 1999), South Africa (Warner and Simpungwe, 2004), Vietnam (Hirsh and Wyatt,
2004) and Zimbabwe (Kujinga and Manzungu, 2004; Manzungu, 2002).
Troubles on the Way 7
7
CHALLENGES FACED BY MSPS
When setting up an MSP, it is important to consider power relationships, the composition of
the platform, stakeholder representation and capacity to participate meaningfully, decision-
making powers and mechanisms, and the costs of an MSP.
Power relationships
MSPs as places of encounter and of power struggle
There is an on-going debate between those who have a ‘power relationship vision’ and those
who have a ‘dialogue vision’ of how MSPs work. The main conceptual basis for the dialogue
vision of those who formalized MSPs (Steins and Edwards, 1999) is the ‘communicative
rationality’ defined by Habermas (1995). According to this approach, the main obstacles to
open and fruitful discussion and negotiation stem from a lack of good communication. Once
this barrier is removed, it is possible to build a common vision and to achieve a solution that
is better for everybody (a win win solution). In that way, according to Hemmati (2002),
democracy, equity, justice, transparency and consensus building are key values for MSPs.
Sultana and Thompson (2004) contend that consensus can always be reached if the MSP is
designed so as to address equity problems actively. The main prerequisites for this dialogue
vision are that: i) stakeholders accept the interdependencies linking them; ii) they are willing
to communicate and learn from each other; iii) they are willing to actively tackle the discussed
problems; and iv) each participant is interested in reaching a negotiated agreement. Usually,
the more informal the MSP, the more important it is to meet these prerequisites. Recent
concepts (e.g., social learning, Maarleveld and Dangbégnon, 1999), methods (e.g., the
patrimonial approach, Ollagnon, 1989), and projects (e.g., the European Union research
project on water resource management, HarmoniCOP 2003) are built on a dialogue vision of
MSPs. This vision is enshrined in laws such as the Water Acts of Brazil (1997), France
(1992), Mexico (1992), South Africa (1998) and Zimbabwe (1998).
On the other hand, according to the advocates of the power relationship vision, an MSP is
mainly a place where power relationships are expressed. These power relationships cannot be
completely annihilated and they always determine negotiated agreements (Crespo, 2005;
Edmunds and Wollenberg, 2001; Leeuwis, 2000). Furthermore, weaker groups’ participation
in an MSP may lead to negative results for them. Indeed, they could be forced to accept an
agreement that would not benefit them because of pressure from other stakeholders, majority
8 Nicolas Faysse
8
rule or lack of negotiating skills. Though they would lose from the agreement, it would still
appear as a consensus decision from the point of view of an external monitoring organization.
This was illustrated by the Lower Olifants WUA, one of the South African WUAs
studied, where a Coloured community situated downstream of a commercial farming area had
been invited to join the association with the white commercial irrigation farmers. Due to
increases in the commercial farms’ water consumption and a change in the monitoring
system, the Coloured community started receiving less water than they were entitled to. The
claims they presented at the WUA Management Committee were discounted because the
Coloured community had only one representative, who did not have the technical information
to prove his point. Because of this, the representative of the Coloured community stopped
participating in the WUA Management Committee. The Ministry of Water Affairs tended to
judge his departure as illegitimate, and this weakened the Coloured community’s position
when it eventually claimed the fulfilment of its rights from the Ministry of Water Affairs.
As pointed out by Edmunds and Wollenberg (2001: 245) ‘by linking decision to inclusion
of all stakeholders, people or groups that refuse to participate can be left with no legitimate
place from which to criticize the outcomes’. Moreover, in spite of the communication ideal of
MSPs, there are still differences between participants in terms of education, language skills,
lobbying power, and the costs of their participation in the MSP. During a forest management
MSP in Brazil, many participants did not talk openly for fear of reprisals from the most
powerful participants (Castellanet, 1999). Without specific intervention to limit their
differences, the MSP may eventually be run by the most powerful groups (Edmunds and
Wollenberg, 2001).
The advocates of the power relationship vision criticize the dialogue vision approach.
They contend that the latter shows a propensity to overlook the importance of the power
relationships taking place in multi-stakeholder platforms. They maintain that the word
‘platform’ itself tends, wrongly, to imply a level playing field. Moreover, the supporters of the
power relationship vision argue that the other group sees conflicts as a pathology, which
entails that weaker groups, refusing to enter an MSP because they fear they will not be able to
negotiate on a level field, will lose the legitimacy of expressing their opinions. One of the
reasons for underestimating the importance of power relationships is that power distribution is
much more even in the countries where MSP approaches were designed, i.e., Europe and
North America. Social and economic inequalities are far greater in many developing
countries, and this is sometimes disregarded when international cooperation agencies advise
MSP-type decision-making (e.g., about water reforms in South Africa and Zimbabwe).
Troubles on the Way 9
9
For the advocates of the power relationship vision, it is better to build alliances among
specific groups than to insist that all stakeholders come to an agreement. Weaker groups
should be allowed to pursue other strategies besides negotiation, or to refuse to enter into
negotiations they think will be based on too large a difference in negotiating power (Edmunds
and Wollenberg, 2001). Moreyra and Warner (2004) report an MSP in Argentina where a
disadvantaged indigenous community that decided not to participate in the MSP eventually
obtained more than a similar community that did participate. Advocates of the power
relationship vision also believe that the playing field should be levelled as much as possible,
by capacitating and empowering the weaker groups before they enter into the negotiation.
This means that a facilitator supporting weaker groups in their negotiation should not try to be
accepted as a neutral broker, but must clearly identify and choose allies (Castellanet, 1999;
Crespo, 2005).
These two visions are both important in analyzing MSPs. However, both of them fail to
capture the nature of a negotiation. In the dialogue vision, the winning argument is the one
that is rationally the best whereas, in the power relationship vision (also called the ‘conflict
vision’), the solution is imposed by the most powerful group. If either of these visions is taken
to the extreme, it should be possible to predetermine the result of negotiations, based on a
careful analysis of context and stakeholders. However, in the large majority of the situations,
the results of negotiations are unpredictable, which means that these views are both
incomplete (Warner, pers. comm.). It is more useful to see them as complementary. The
context determines where the balance between the two visions should be reached: The more
unequal the participants are, the more power relationships should be given importance. Often,
the outcome of the negotiation is not the preferred solution of any of the participants, but is
one of the solutions that each participant is ready to agree to at the end of the negotiation. The
set of solutions a participant may accept will often have been modified during the process of
exchange and negotiation with other parties: In that sense, social learning and negotiation
should be taken together (Leeuwis and Van den Ban, 2004, quoted by Leach and Wallwork,
2003).
In the case of the Technical Roundtable in Bolivia, the power issue was not expressed in
terms of participants imposing their opinions. During the discussion of the roundtable
methodology (which lasted more than a month), the conflict was seen as local: Only the Vice-
Ministry of Basic Services was scheduled as a permanent non-local participant. Amongst
local participants, against all predictions, the Technical Roundtable went according to the
dialogue vision. The two opposing groups, i.e., opponents and supporters of the MACOTI
10 Nicolas Faysse
10
project, were represented approximately equally and neither dominated the debate. Moreover,
decisions were made by way of consensus. During the course of the Technical Roundtable,
the atmosphere became progressively more peaceful, and participants that were clearly on
opposite sides during the first meetings eventually worked together in a spirit of cooperation,
particularly to define the institutional model. However, power was expressed in terms of other
key stakeholders managing to stay out of the discussion (see below).
Opportunities for capacity-building
Weaker groups’ participation in highly heterogeneous MSPs can be a risk for them, as
Edmunds and Wollenberg (2001) argued, but it is also an opportunity for capacity building.
The latter authors give several examples of short-term MSPs, where there was no room for
capacity building and where weaker groups were forced to accept agreements contrary to their
interests. However, when the MSP deals with the long-term management of a natural
resource, the general balance is not always clear-cut. For instance, the South African WUAs
are permanent local water management organizations, where the government has neither the
capacity nor the willingness to take over the control of the WUAs. In six of the eight WUAs
studied, the long-term advantages of capacity building outweighed the small risks of being
forced to accept the results of an unequal negotiation (Faysse, 2004b). The capacity-building
component was actually the main reason for attending the meetings, according to Black
farmers of the Lomati and Letaba WUAs.
The WUA may undertake capacity building itself: For instance, in the Komati Irrigation
Board, where a large number of Black irrigation farmers occupy the entire length of one bank
of the river, real capacity-building efforts are made, both during and outside the management
committee meetings. However, capacity building may be limited if there is no outside
intervention. In the Great Letaba and Lower Olifants WUAs, the Black farmers did not learn
the key information they needed to defend their water rights (Faysse, 2004b). In the Letaba
WUA, Black water users were not paid much attention during the management committee
discussions and, for important decisions, language naturally swapped from English to
Afrikaans, a language not completely mastered by the local Black farmers.
Taking the above into consideration, should the playing field be levelled before granting
decision-making power to a user-based MSP, or should the MSP be set up quickly, leaving
the power difference to be sorted out on the way? Interestingly, the South African government
chose the first strategy for the large-scale Catchment Management Agencies, while adopting
the second for the smaller Water User Associations.
Troubles on the Way 11
11
The composition of the platform
Three issues necessarily emerge during the design of an MSP: i) who defines the list of
persons who have a stake in the problem; ii) which stakeholders should be invited and what
are the legitimate organizations to represent them; and iii) how to make sure that the
stakeholders identified for participation in the MSP will be interested in coming.
Who defines the stakeholders?
The definition of who the stakeholders are is seldom self-evident because it depends on the
issue addressed. Moreover, some stakeholders, e.g., women water users, may not be
specifically represented and their interest may be merged in a general ‘local community’
representation. It is important also to care about who defines the relevant participants in the
MSP. During the Technical Roundtable in Bolivia, the organizations formally representing
the local communities, named OTBs (Organizaciones Territorial de Base), did not want the
irrigation farmer association to be present at the MSP, as they argued that the OTB
represented all the stakeholders in its jurisdiction, including irrigation farmers. Eventually,
they capitulated, after the Mayor’s insistence on adopting an open-minded stance. Indeed,
solving a conflict by associating stakeholder participation with classical representative
democracy was a relatively new idea in the Tiquipaya Municipal Area. Many Technical
Roundtable participants stated later that this was the first process of this kind in the
Municipality.
Which stakeholders should be invited?
It is not always relevant to bring all stakeholders to the MSP because of the possible
consequences of power imbalances, as discussed in the previous section. This point is proved
by the experiences of two MSPs in Brazil, set up to tackle forest management in the
Amazonian region. The first MSP failed mainly because the local elite who participated
managed to indirectly control the results of the sessions. The second MSP was organized to
include only the weaker groups and state representatives, and the local elite were not invited,
which yielded much better results (Castellanet, 1999).
The composition of the MSP is not always fixed once for all: In the case of the Technical
Roundtable, after lengthy discussions to define the ‘official’ MSP composition before the first
session, it was decided during the second two-day session that anybody could participate as
long as he would contribute positively to the debate.
12 Nicolas Faysse
12
How can stakeholders be interested?
In some cases, stakeholders that are judged relevant participants in the MSP may not be
initially interested. For example, many South African WUAs fail to get municipalities or
upstream forestry companies on board because the latter see no advantage in being part of
these new organizations (Faysse, 2004c). This tends to be more common for consultative
MSPs that have weak links with the decision-making process, than for MSPs that are
officially given decision-making responsibilities. Many strategies have been used to address
this problem, e.g., giving formal decision-making power to the MSP or, in a typical
negotiation theory approach, broadening the scope of negotiated elements so that all invited
stakeholders may find something interesting for them in the negotiation. For instance, in the
Mlazi Catchment area in South Africa, upstream rural communities created erosion problems,
impacting on water quality and affecting commercial farmers downstream (Faysse and
Gumbo, 2004). The rural communities eventually agreed to participate in a local forum
because anti-erosion projects brought them employment.
In Bolivia, all local communities and drinking water user associations could attend the
Technical Roundtable and none of the stakeholder groups were discouraged from attending.
However, some key stakeholders decided not to participate actively. The participation of the
Municipality was weak and the constructing and supervising companies were only briefly
present – the technical side of the project was not so important then, since at that time nobody
had complained much about the technical design. The CEO of the credit bank came to a
session, but explained that the high interest the bank charged was fixed by law and, since
nobody had the technical knowledge to contest his claim, the debate on the topic was closed.
All these stakeholders could stay out of the MSP, since it had been decided that the Technical
Roundtable would not delay the beginning of the works, and all contracts between the
Municipality, the construction and supervision companies and the credit bank were already
signed. In these stakeholders’ opinions, the Technical Roundtable participants had limited
scope for changing the project.
MSPs can be designed from the bottom up or from the top down. Usually, the bottom-up
ones achieve stakeholder involvement but struggle to get state recognition. On the other hand,
top-down MSPs are backed by the state but may find it difficult to obtain real involvement of
all stakeholders (Warner and Simpungwe, 2004).
Troubles on the Way 13
13
Stakeholder representation and capacity to participate meaningfully
Real participation is more than a mere headcount (Manzungu, 2002). Though stakeholder
groups may have one or several seats at the MSP, they may not be able to participate
meaningfully. There can be three reasons for this: i) lack of capacity of the group to nominate
a representative and ask for feedback; ii) lack of financial means to participate in the
meetings; and iii) lack of technical knowledge of representatives to participate meaningfully
in the MSP discussions (Faysse, 2004b; Kujinga and Manzungu, 2004).
Representatives and feedback
The problem of representation within a stakeholder group is not limited to MSPs: It has been
studied in general for participatory processes (e.g., Edmunds and Wollenberg, 2001;
Wollenberg and Uluk, 2004). Though this problem is of key importance for the success of
MSPs, it was granted little attention during the design of the new South African water
resource management organizations.
Lack of stakeholder group organization is often a reason for poor representation. In the
Great Letaba WUA, though a seat at the WUA Management Committee is formally reserved
for farm workers, the latter are not organized enough to mandate a representative to the
Management Committee (Seshoka et al., 2004). Even more difficult is the nomination of
Black water user representatives to the Governing Board of the Inkomati Catchment
Management Agency, given that Black water users throughout the basin are almost
completely unorganized, in an area of more than 30,000 square kilometres.
Lack of communication within stakeholder groups is another reason for poor
representation. This occurs when the link between the constituencies and their representatives
during the MSP process is unsatisfactory. It can be top-down, if the representative does not
give feedback about what took place during the MSP sessions, or bottom-up, if the
representative does not listen to the opinions expressed by the constituency. In Bolivia, during
the Technical Roundtable, the MSP failed to reach grassroots stakeholders because many
representatives of local communities and drinking water user associations did not
communicate about their participation in the Technical Roundtable, nor did they listen to the
opinion of their constituencies on the issue.
14 Nicolas Faysse
14
Lack of financial means
The lack of financial means to participate in the MSP meetings is significant in Zimbabwe,
where transportation costs are a major problem for emerging farmers who want to participate
in the catchment management committee meetings (Manzungu and Kujinga, 2002).
Lack of technical knowledge
MSPs are designed for deliberation, not mere participation, which means that participants
must have sufficient technical knowledge to enter into this deliberation. Specific capacity
building of participants should be organized to address this. However, the level of
participants’ technical knowledge is generally overlooked. Of all the problems, this one
proved to be the most important during the Technical Roundtable. The participants had no
capacity to criticize the technical design, and they could understand the financial design only
partially. Only during the institutional design did they feel at ease and enter into in-depth
discussions and proposals. Correspondingly, the Technical Roundtable did not address the
technical topics in detail, addressed the financial topic only partially, and led to detailed
proposals for the institutional topics. In the same way, in both South Africa and Zimbabwe,
Black water user representatives do not participate actively in the discussions because of a
lack of capacity-building (Faysse, 2004b; Manzungu, 2002).
Decision-making power and mechanisms
According to Hemmati (2002), MSPs are basically set up to give ‘voices, not votes’, i.e., their
interest comes mainly from sharing opinions, not from taking decisions. However, this
analysis focuses on MSPs that are somehow linked to decision-making. MSP impact on
decision-making may be a problem, especially for short-term MSPs, whose link with the
formally established decision-making process tends to be unclear at the start of the process. In
the area of water resource management, where operation, maintenance and even planning
decisions are increasingly handed to groups of water user representatives (Faysse, 2004a), the
degree of decision-making power the MSP has impacts on the strategic behaviour of the
participants. Stakeholders may decide not to participate in an MSP whose aim is merely
sharing views, preferring to lobby authorities directly to get what they want, but they will
participate in an MSP that has official decision-making powers. In South Africa, participation
in a local catchment forum waned as participants understood that the forum did not have any
power to enforce the recommendations that had been taken (Warner and Simpungwe, 2004).
Troubles on the Way 15
15
MSPs are about building a new form of legitimacy, where stakeholders are not only
represented by way of universal voting, but also by way of ‘corporate’ groups. This other
form of legitimacy leads to its own issues, e.g., grassroots stakeholders may not have the
same weight, depending on which group they belong to. However, the new form of
participatory democracy never aimed at overthrowing the traditional representative
democracy in the different cases studied. Therefore, the key issue becomes how to strike a
balance between the two forms of representation.
Several ways of striking this balance have been tried. At one extreme, MSPs may just
issue recommendations that the authorities are bound to formally receive and review, but with
no obligation to implement them. This scenario was initially proposed for the Technical
Roundtable. At the other extreme, authorities may be part of the MSP itself, the latter having
full decision-making power. For instance, the local Catchment Committees in France are
composed by law of 50% from local authorities, 25% from the government, and 25% from
water user representatives. The best balance depends on local conditions: Representative
democracy should not be put aside in cases of weak internal democratic procedures within
some stakeholder groups. More generally, for MSPs to be able to perform properly, the state
must not be too strong, otherwise it does not give the other stakeholders enough room to
manoeuvre. But it should not be too weak either, because then the MSP work might simply be
controlled by local elites (Castellanet, 1999).
MSPs may also be turned into a mere pretence of participation. The authorities may
formally back the process, while unconcerned about the outcomes, which generates much
frustration vis-à-vis the MSP process. This problem has been documented in several cases of
bottom-up MSPs, where local stakeholders gathered with NGO support, and their decisions
never reached the ears of administrators and decision makers (Hirsh and Wyatt, 2004; Warner
and Simpungwe, 2004).
In the case of the Technical Roundtable in Bolivia, decision-making power was a much
debated issue at first. The Negowat team initially proposed that the Technical Roundtable just
have the capacity to present proposals to the Municipal Councils of Tiquipaya and
Colcapirhua, which could accept them or refuse them. This proposal was made on the grounds
that, first, many stakeholder groups had no legal status, and the relationship between the
constituency and its representatives in these groups was weak. Second, the groups supporting
the project feared that the Technical Roundtable might lead to motions that would harm the
project, and required guarantees before agreeing to take part in the process. From the first
session onwards, the participants kept on demanding that the Tiquipaya Municipal Council
16 Nicolas Faysse
16
automatically implement the decisions they would take. The Council resisted at first, but
eventually agreed to issue a note with such a commitment. However, a new Municipal
government was elected shortly after the last Technical Roundtable session and the Municipal
team did not implement the motions approved during the roundtable, even though that team
included people who had wanted the MSP to have full decision-making powers. The Mesa
Técnica had been especially successful in building proposals for the institutional model of the
future entity in charge of running the project. However, these motions were neither
implemented nor discarded in 2005, as the project faced huge technical problems and
significant delays in its implementation phase. Because of this implementation problem,
several participants were of the opinion that the Technical Roundtable had turned out to be a
simulacrum of participation.
Decision-making mechanisms were linked to the legal status of the MSP in the cases
studied. In Bolivia, the Technical Roundtable was a short-term platform, initially with no
clear place in the legal decision-making process. Therefore, it was decided that decisions had
to be unanimous. This only partly addressed the difficulties of defining the legitimacy of the
roundtable decisions because, when a motion did not obtain unanimous support, the MSP just
did not mention the point.
South African WUAs and Catchment Management Councils in France are more
formalized MSPs, legally established and permanent, and need to take decisions about
whatever happens. Therefore, they use the majority rule (which may be defined as one vote
per person, or per hectare, etc.).
The costs of an MSP
MSPs may be costly in terms of time and money; they could also delay the decision-making
process. In Bolivia, the Mesa Técnica cost approximately US$ 10,000, including materials
and salaries. Considering the magnitude of the MACOTI sanitation project (US$ 1.7 million
for the Tiquipaya part) and all the delays and subsequent financial problems due to the
conflicts in Tiquipaya, the implementation costs of the Technical Roundtable can be judged as
acceptable (around 0,6% of the total MACOTI cost in Tiquipaya). However, public
participation was not initially scheduled as an item in the MACOTI budget, and the Tiquipaya
Municipality would have had some problems in motivating this expense to the OTBs.
Actually, the Municipality paid for the lunches during the various sessions (which amounted
to 5% of the MSP cost) but was not interested enough in the Mesa Técnica to try to pay for
Troubles on the Way 17
17
the whole process. The Vice-Ministry of Basic Services participated actively throughout all
the process but offered no financial support. Without Negowat financial capacities, the Mesa
Técnica as initially proposed by the Vice-Minister would probably have been reduced to a
series of short and quickly organized meetings.
In South Africa, WUAs are self-sustaining, thanks to contributions from all large-scale
water users. These MSPs have their own mechanisms to ensure the financing of their
activities, which is not the case for all permanent MSPs (e.g., the Catchment Management
Committees in Zimbabwe, Kujinga and Manzungu, 2004). For the South African WUAs, the
current unresolved issue is rather how to finance genuine support and capacity building for
weaker participants.
THE TWO MSPs STUDIED … A WORTHWHILE PROCESS?
In the light of these five challenges, how should the performance of the two MSPs studied be
judged? Both the South African and the Bolivian MSPs proved to be mixes of failures and
successes so it is hard to say whether or not they were worthwhile.
In South Africa, Black users do not benefit fully from their presence in the WUA, due to a
lack of external support for specific capacity building. In two WUAs where emerging farmers
needed key knowledge to defend their water rights, being part of the WUA did not enable
them to access the information they needed and so win their case. However, these WUAs
were set up to replace existing Irrigation Boards, since the state does not have the capacity to
control water management at this level. In such a situation, capacity building and internal
organization of Black water users seem more promising solutions than recentralizing
management.
In Bolivia, a major weakness of the Technical Roundtable was that it was set up when the
project was already at the beginning of its implementation stage. This meant that decisions
like the choice of the constructing and supervision companies could not be changed.
Moreover, since many decisions were already taken, key stakeholders such as the credit bank
did not give credence to the process. However, the lack of technical changes to the project
during the roundtable came mostly from participants’ lack of technical capacity to criticize the
project. Moreover, non-implementation of the decisions taken led to frustration. As the Mayor
later told the facilitators privately: ‘The Technical Roundtable kept them busy talking, which
enabled us to start with the work.’ Finally, the Technical Roundtable did not socialize the
project beyond the representatives. However, it did manage to ease tensions around a project
18 Nicolas Faysse
18
about to lead to street conflict once again, and to move from general judgments and even
insults from local leaders to quite detailed and positive discussions on the different aspects of
the project. Organizing the Technical Roundtable was possible because the area was split
between two opposing camps of similar strength. The municipality understood that it could
not solve the conflict on its own, and accepted a public debate organized by an external
facilitator. The next year, the newly elected municipality won the elections by a large margin.
This new municipality initiated a Committee for the Social Control of the MACOTI project,
elected by the OTBs, but the Committee found itself with no support from the municipality
(which was ultimately uninterested in social control), or from the OTBs, and finally waned.
The Technical Roundtable had a facilitator but no formal recognition: A facilitator
engineered the MSP but, because of lack of clear decision-making power and support from
the authorities in implementing decisions, the MSP turned out to have limited visible impact,
which later created frustration among former participants. In South Africa, the WUAs have
formal recognition but no facilitator: They have full decision-making power, but no
practitioner intervenes to ensure that the initial objective of these MSPs (to open up the
management to Black small-scale water users) is indeed achieved. Thus, in the two examples,
it would take both formal recognition of the MSP and the presence of a facilitator to make the
process worthwhile.
CONCLUSION
MSPs were analyzed in terms of five issues: power relationships, platform composition,
stakeholder capacity to participate meaningfully in the debate, decision-making power and
mechanisms, and MSP costs. Each of these challenges may debilitate or even end an MSP
process, but there are ways to tackle each of the problems analyzed.
The same framework of analysis was used for two very different MSPs, and it appears that
they share many crucial issues. The five points reviewed are obviously necessary conditions
for the success of an MSP, but not sufficient ones. In South Africa, great efforts were made to
have genuine participation of Black water users during the set up of the Catchment
Management Agencies. However, the main problems in getting genuine inclusion did not
stem from insufficient or unempowered participation, but from the fact that the predetermined
functions of Catchment Management Agencies (dealing with externalities in water
management) did not overlap with Black users’ priorities, which were investments in
infrastructure (Faysse, 2004a).
Troubles on the Way 19
19
The two cases of MSPs reviewed here were implemented in countries with unfavourable
conditions for MSP success. Indeed, important drawbacks and limitations became apparent in
the analysis. First, in South Africa, there is a serious danger that White water users will
continue to dominate the decision-making in WUAs, behind the appearance of smooth
communication between all water users. Second, in Bolivia, the Mesa Técnica eventually had
little decision-making power. Despite these limitations and risks, in both cases, the results of
having the MSPs can be judged as better than those of not having them at all. In the light of
these case studies, there is no absolute answer to the question of whether MSPs are adequate
tools in unfavourable conditions, especially in countries with high social inequities. However,
MSPs should be less driven and analyzed according to an ideal of perfect communication and
social learning, and more seen as a useful tool that will nevertheless always be imperfect.
In situations that are unfavourable for MSPs, external intervention is necessary to face the
challenges linked to MSP design and implementation, amongst them: power relationships, the
composition of the platform, stakeholder representation and capacity to participate
meaningfully, and the decision-making powers and mechanisms of an MSP. Many MSPs are
supported by a facilitator, whose activities may range from merely inviting stakeholders to the
sessions, to being fully engaged in organizing the negotiation themes and providing the
needed technical information to the platform. But it is still an open question whether the same
facilitator can also tackle those four challenges. Actions such as supporting weaker
stakeholder groups, or intervening in the relationship between a constituency and its
representative, might be judged by MSP participants as conflicting with a facilitating role.
Moreover, it is seldom evident to what extent it is possible to tackle these challenges, who
could do this, and at what cost. Based on this, it will be necessary to evaluate, on a case-by-
case basis, whether it would still be better to have an imperfect MSP than not to have it at all.
In South Africa, the government has the financial capacity to undertake the task of
supporting Black water users’ inclusion in water-related MSPs. It would be worthwhile to
increase inclusion of Black water users’ in WUAs: What the government lacks is knowledge
of the current problems related to Black water users’ inclusion and of adequate strategies to
tackle them. However, it may not be efficient to invest large efforts in building genuine Black
stakeholder representation at the Catchment Management Agency level, in the current context
of Catchment Management Agencies’ not meeting Black water users’ main needs. In Bolivia,
few organizations are currently able to support such an MSP on a permanent basis.
Given this analysis, important directions for future investigation are how to capacitate
MSP members to actively participate in a technical discussion, how to ensure true
20 Nicolas Faysse
20
communication between constituencies and their MSP representatives, how to strike the right
balance between the MSP and traditionally elected authorities in terms of decision-making
power, and how to build up the strength of weaker groups to level the playing field with the
stronger stakeholders as much as possible, before entering into an MSP – if it is estimated that
weaker stakeholders really have a reasonable chance of reaching an agreement that suits them.
Finding ways to tackle these issues should be pursued at the same tempo as the one with
which MSPs are developed these days, which has unfortunately not happened to date.
ACKNOWLEDGEMENTS
Both MSP case studies were the results of teamwork: with Jabulani Gumbo, Jetrick Seshoka
and Willem de Lange in South Africa, and with Raul Ampuero, Franz Quiroz, Vladimir
Cossio and Bernardo Paz in Bolivia. Jeroen Warner shared important ideas regarding the
theoretical analysis of MSPs. The text itself benefited from insightful comments from
Raphaele Ducrot, John Butterworth and Marcel Kuper. Anne Denniston undertook a detailed
final revision of the paper.
Troubles on the Way 21
21
REFERENCES
Arnstein, S. (1969) ‘A Ladder of Citizen Participation’, Journal of the American Institute of Planners 35: 216-
24.
Blomquist, W. (1992) Governing groundwaters in Southern California. San Francisco: ICS Press.
Brazil (1997) Lei das Águas. Lei 9.433. Brasília (8 January).
Castellanet, C. (1999) ‘Les “plateformes de négociation” entre usagers des ressources naturelles:
Expérimentation avec des municipalités du front pionnier amazonien.’ Paris: GRET.
Crespo, C. (2005) ‘Poder, dominación y conflictos: Elementos para una crítica de los enfoques de construcción
de consensos’ paper presented at the conference on Integrated Water Resource Management, PROMIC-
Centro AGUA, Cochabamba, Bolivia (15-17 April).
‘The Dublin Statement on Water and Sustainable Development’ (1992) Development Issues for the 21st Century,
International Conference on Water and the Environment, Dublin (26–31 January).
Edmunds, D. and E. Wollenberg (2001) ‘A Strategic Approach to Multi-stakeholder Negotiations’, Development
and Change 32(2): 231-53.
European Union (2000) Directive 2000/60/EC of the European Parliament and of the Council Establishing a
Framework for the Community Action in the Field of Water Policy, Legislative Acts and Other Instruments.
ENV221 CODEC 513.
Faysse, N. (2004a) ‘Challenges for Fruitful Participation of Smallholders in Large-scale Water Resource
Management Organisations: Selected Case Studies in South Africa’ Agrekon: Review of the Association of
South African Agricultural Economists 43(1): 52-73.
Faysse, N. (2004b) ‘An Assessment of Small-scale Users’ Inclusion in Large-scale Water User Associations of
South Africa’, IWMI Research Report 84. Colombo: International Water Management Institute.
Faysse, N. (2004c) ‘The Possible Involvement of Large-scale Water User Associations in Local Integrated Water
Resource Management in South Africa’, paper presented at the conference on Water Resource Management,
Loskop Dam, South Africa (1-5 November).
Faysse, N. and J. Gumbo (2004) ‘The Transformation of Irrigation Boards into Water User Associations in South
Africa. Case Studies, Volume 2: The Umlaas, Komati, Lomati and Hereford Irrigation Boards’. IWMI
Working Paper 73, Colombo: International Water Management Institute.
Faysse, N., V. Cossio, R. Ampuero, F. Quiroz and B. Paz (in press) ‘Use of a Methodology for Intervention in
the Design of a Short-term Multi-stakeholder Platform in the Case of a Water and Sanitation Project in
Tiquipaya (Bolivia)’, in J. Warner (ed.) Democratising Water Governance? Multi-stakeholder Platforms for
Integrated Catchment Management.
France (1992) Loi sur l’Eau. Act 92-3. Paris: Journal Officiel (4 January).
Grimble, R. and K. Wellard (1997) ‘Stakeholder Methodologies in Natural Resource Management: A Review of
Principles, Contexts, Experiences and Opportunities’, Agricultural Systems 55(2): 173-93.
Habermas, J. (1995) ‘Reconciliation Through the Public Use of Reason: Remarks on John Rawls’s Political
Liberalism’, The Journal of Philosophy 17(3): 109-31.
Hardin, G. (1968) ‘The Tragedy of the Commons’, Science 162: 1243-48.
22 Nicolas Faysse
22
HarmoniCOP (2003) ‘Social Learning Pool of Questions’. HarmoniCOP combined WP2/WP3 deliverables.
URL http://www.harmonicop.info/index.php, accessed December, 16th, 2005.
Hemmati, M. (2002) Multi-Stakeholder Processes for Governance and Sustainability. Beyond Deadlock and
Conflict. London: Earthscan Ed.
Hirsh, P. and A. Wyatt (2004) ‘Negotiating Local Livelihoods: Scales of Conflicts in the Se San River Basin’,
Asia Pacific Viewpoint 45 (1): 51-68.
Kujinga, K. and E. Manzungu (2004) ‘Enduring Contestations: Stakeholder Strategic Action in Water Resource
Management in the Save Catchment area, Eastern Zimbabwe’, Eastern Africa Social Science Research
Review 20(1): 67-91.
Leach, G. and J. Wallwork (2003) ‘Enabling Effective Participation, Negotiation, Conflict Resolution and
Advocacy in Participatory Research: Tools and Approaches for Extension Professionals’. Australasia Pacific
Extension Network, published online by The Regional Institute Ltd.
Leeuwis, C. (2000) ‘Reconceptualizing Participation for Sustainable Rural Development: Towards a Negotiation
Approach’, Development and Change 31: 931-59.
Maarleveld, M. and C. Dangbégnon (1999) ‘Managing Natural Resources: A Social Learning Perspective’,
Agricultural and Human Values 16 (3): 267-80.
Manzungu, E (2002) ‘More than a Headcount: Towards Strategic Stakeholder Representation in Catchment
Management in South Africa and Zimbabwe’, Physics and Chemistry of the Earth 27: 927-33.
Mexico (1992) Ley de Aguas Nacionales. Mexico: Diario Oficial de la Federación (1 December).
Moreyra, A. and J. Warner, J. (2004) ‘La gestión participativa de cuencas en la práctica: El caso de la
Comunidad de Usuarios del arroyo Trahunco, San Martín de los Andes, Patagonia Argentina’, in J. Warner
and A. Moreyra (eds.) Conflictos y Participación, Montevideo, Uruguay: Nordan Comunidad.
Ollagnon, H. (1989) ‘Une approche patrimoniale de la qualité du milieu naturel’, in N. Mathieu and M. Jollivet
(eds), Du rural à l’environnement, la question de la Nature aujourd’hui. Paris: L’Harmattan.
Seshoka, J., W. de Lange and N. Faysse (2004) ‘The Transformation of Irrigation Boards into Water User
Associations in South Africa. Case Studies: Volume 1. The Lower Olifants, Great Letaba and Vaalharts
Water User Association’, IWMI Working Paper 72. Colombo: International Water Management Institute.
South Africa (1998) National Water Act. Act 36. Cape Town: Government Gazette (26 August).
Steins, N.A. and V. Edwards (1999) ‘Platforms for Collective Action in Multiple-use Common-pool Resources’,
Agriculture and Human Values 16: 241-55.
Sultana, P. and P. Thompson (2004) ‘Methods of Consensus Building for Community-based Fisheries
Management in Bangladesh and the Mekong Delta’, Agricultural Systems 82: 327-53.
Susskind, L. and J. Cruikshank (1987) Breaking the Impasse. Consensual Approaches to Resolving Public
Disputes. New York: Basic Books.
Warner, J. (in press) ‘The Beauty of the Beast: Multi-stakeholder Participation for Integrated Catchment
Management’, in J. Warner (ed.) Democratising Water Governance? Multi-Stakeholder Platforms for
Integrated Catchment Management.
Warner, J. and E. Simpongwe (2004) ‘Stakeholder Participation in South Africa: Power to the People?’, paper
presented at the International MSP Conference, Wageningen (29 September – 1 October).