Affordable Housing Viability Report Brooklands Approach ...
-
Upload
khangminh22 -
Category
Documents
-
view
1 -
download
0
Transcript of Affordable Housing Viability Report Brooklands Approach ...
Affordable Housing Viability Report
Brooklands Approach, Romford, Essex RM1 1DX
SJJ Properties LLP
12th October 2017
Adam Roberts Page 2 of 6 12/10/2017
Brooklands Approach, Romford, Essex, RM1 1DX Affordable Housing Appraisal GLA Toolkit Three Dragons Model
1. Introduction Adam Roberts Consultancy is instructed by SJJ Properties LLP to carry out a viability assessment to determine the extent to which it is viable for the proposed development at Brooklands Approach, Romford, Essex RM1 1DX to contribute towards affordable housing. The assessment has been carried out in accordance with the Greater London Authority’s (GLA) development Affordable Housing Toolkit, known as the Three Dragons Model to demonstrate whether the development is viable, when providing a policy compliant level of affordable housing.
The objective is to determine the financial viability of the proposed scheme, considering the requisite elements, including Existing Use Value (EUV), purchase price, build and other costs, standard affordable housing contributions, other s.106 contributions and sales values.
Development viability assessments take place against the background of London’s growing population and expanding housing needs.
Adam Roberts have carried out numerous viability assessments using the GLA Affordable Housing Toolkit for both applicants and Local Planning Authorities. Adam Roberts Consultancy Ltd also provides viability, acquisition, and development and consultancy services to local authorities, private developers, registered housing providers and house builders. This report was prepared by Denny Adam who has over thirty years’ experience of housing development having held senior positions within the RSL, Local Authority and private developer environment. He is a corporate member of the Chartered Institute of Housing.
2. Site Location and Description
Romford is a satellite town of London, located approximately seventeen miles, by road, to the east of its centre and is well served by public transport, with numerous bus routes passing through the town. Mainline services are available from Romford station situated on South Street, within the Town Centre. Romford is also well placed for access to the national road network lying to the south of the A12 trunk road which gives access to central London in the west and the national motorway network to the east, via junction 28 of the M25 London Orbital Motorway. The site is located on Brooklands Approach, which is a private road positioned to the western side of North Street providing good vehicular links to the A12/A127 which in turn offers good vehicular links to the A406 and the M25 and National Motorway Network. The area on which the property is located forms part of an industrial estate on the fringe of Romford Town Centre. Over the last ten years, many of the surrounding
Adam Roberts Page 3 of 6 12/10/2017
industrial areas have either been redeveloped to provide residential accommodation, or have been earmarked for the same. The existing building on site has been created out of what was probably a break up of a larger industrial building.
3. Current Proposal The applicants intend to submit a planning application for two blocks of flats, comprising of 33 and 34 units respectively.
4. National and London Policy Context The Government published its National Planning Policy Framework (NPPF) in March 20121 where it states:
The London Mayor published in August 2017 a new SPG2 on the provision of affordable housing whereby developments providing 35% or above affordable housing by habitable room without public subsidy will not require a viability assessment to be provided. If the project does not meet the 35% threshold a viability assessment should be submitted with supporting evidence for scrutiny by the Local Planning Authority and the Mayor
1 National Planning Policy Framework – Department for Communities and Local Government March 2012
2 Homes for Londoners – Affordable Housing and Viability Supplementary Planning Guidance (SPG) – GLA August 2017
Adam Roberts Page 4 of 6 12/10/2017
where relevant. If the development does not progress within two years an early stage review will be implemented. In addition, there will be a Late Stage Review when 75% of the market properties have been sold to test whether the development can support a financial contribution for additional affordable housing provision in the event the viability has improved since the application stage.
5. Development Control Policies London Borough of Havering’s Core Strategy and Development Control Policies DPD (adopted on 22 October 2008) sets out the policy framework for planning obligations and affordable housing. To bring the policy in line with that of the London Mayor the emerging Local Plan Proposed Submission version requires 35% rather than 50%. As outlined in Development Control Policy 6 (DC6), in determining the final arrangements to be included in any s106 planning agreement, the Council will, through negotiation and agreement with the applicant, assess the suitability of on-site and off-site provision for affordable housing and the subsequent percentage that is sought.
6. Community Investment Levy The Regulations for CIL, which came into force in April 2010, state that the Mayor of London has a power to charge CIL only to fund transport infrastructure, such as Crossrail. The Mayoral CIL came into force on 1 April 2012. The charge is £20 per m2 of gross internal floor space within the proposed Charging Zone 3, which includes Havering.
Regulation 13 of the CIL Regulations 2010 allows the Council to set differential rates of CIL for different geographical zones and/or for ‘different intended uses of development’. In the Council’s ‘Community Infrastructure Levy’ (Preliminary Draft Charging Schedule, February 2015), a geographical approach has been taken to set the CIL rates. Our assessment of the financial viability of the proposed scheme for Brooklands Approach therefore shows a total CIL calculation of £193,950 based on a qualifying area of 2110m2 and CIL rates of £70m2 (borough) and £20m2 (mayoral).
7. Planning Obligations The Council recognises that, in most cases, residential development within Havering cannot currently support the full cost of the infrastructure requirement it generates and remain viable.
The Council’s Supplementary Planning Document (2013)3 proposed a standard charge of £6,000 per dwelling in Havering Borough and £4,500 per dwelling in Havering London Riverside is justified and will be sought. We have assumed therefore within our financial viability a planning obligation of £402,000 (67 x £6,000).
It is in these policy contexts that this report assesses the viability of the development to
contribute to affordable housing.
3 Planning Obligations Supplementary Planning Document February 2013 London Borough of Havering Local Development Framework
Adam Roberts Page 5 of 6 12/10/2017
8. GLA Toolkit The Council’s SPD also acknowledges that, in certain circumstances, a development may not be able to afford the discounted standard charge and/or other required obligations without the scheme becoming economically unviable. It is in that context that this viability assessment and report is undertaken using the GLA Affordable Housing and S106 Development Control Toolkit 2015, also known as the Three Dragons Model. The GLA Toolkit is a financial viability tool that uses the residual land value appraisal approach. This is the normally acceptable approach in valuation practice. The residual land valuation can then be used for comparison with the existing use value, alternative uses and the actual acquisition price paid for the site.
9. Development Costs – Inputs
The Toolkit default build costs for Havering are £1,602m2 for 5 storey blocks of flats. It should be noted that the Toolkit default values are dated January 2015 and compiled in 2014 and are therefore at least three years out of date.
The applicant has commissioned Real Consulting to provide a detailed cost plan attached as Appendix 1. Their total estimated construction cost is £10,811,000 including preliminaries and builders’ profit. The total net internal area 4,293m2 and a gross internal area of 6,828. We have not adjusted the other costs inputs from the default. The Toolkit cost analysis assuming a private sale development is set out below:
10. Sales Values Input The applicant has received a Suggested Net Market Values report from Countrywide who have advised a total GDV of £20,157,000. These are attached as Appendix 2. We have inputted these sales values. In addition, we have assumed a ground rent average of £250 per unit that when capitalised at 6% generates a capital value of £279,167 inserted as a capital contribution.
Adam Roberts Page 6 of 6 12/10/2017
11. Planning Obligations Input
Planning contributions have been assumed at a total of £402,000 based on The Proposed Standard Charge of £6,000 per dwelling in Havering Borough (Supplementary Planning Document, 2013).
We have assumed a qualifying area of 2110m2 for Mayoral CIL at the standard £20m2 and at the higher rate of £70m2, for the LA CIL. This is subject to final verification.
12. Existing Use
The applicants have obtained an existing use value of £2,017,500 from Kemsley, an independent valuer, dated 17th June 2016 attached as Appendix 3.
13. GLA Toolkit Results
We have run the Toolkit as a development for open market sale with no financial contribution towards affordable housing and note that there is a residual value after land finance of £2,069,000 compared with an existing use value of £2,018,000. There is therefore an excess profit of £52,000 between the existing use value and the residual land value. The Toolkit is attached as Appendix 4.
14. Conclusion This development project is viable but does not generate a sufficient excess profit to justify any affordable housing on site. However, the £6,000/unit contribution will be made in addition to the excess profit of £52,000 that could contribute towards affordable housing, giving a total of £454,000.
Appendices 1. Real Consulting Cost Plan – September 2017 2. Countrywide Suggested Net Market Values – October 2017 3. Existing Use Valuation Report – Kemsley 4. GLA Toolkit No Affordable
Cost Plan Version 1.0 Rev F
Residential Development, Brooklands Approach, Romford
for S & J Fagg
29th September 2017
REAL Consulting LLP
Pembroke House
36 Unthank Road
Norwich
Norfolk
NR2 2RB
T: +44 (0) 1603 931724
Cost Plan Version 1.0 Rev F
29th September 2017
DOCUMENT ISSUE SHEET
Issue
Nr.
Document File Name Issue Date Parties Sent To Prepared By Checked By Reviewed
By
1 Cost Plan Version 1.0 Rev F 20170929 R328 Cost Plan Ver A Rev F (intro).xlsx 29th September
2017
S & J Fagg JKG MAB MAB
McArthur Tring Architects
Authorised by (Partner)
Date
Residential Development, Brooklands Approach, Romford for S & J Fagg
29th September 2017
Cost Plan Version 1.0 Rev F
29th September 2017
CONTENTS Page Nr.
1.0 Executive Summary 1
2.0 Cost Plan Summary 2
3.0 Basis and Assumptions 3 - 5
4.0 Exclusions 6
5.0 Schedule of Floor Areas 7
6.0 Principal Risks and Opportunities 8
Appendices
APPENDIX A - DETAILED BUILD-UP TO COST PLAN
Residential Development, Brooklands Approach, Romford for S & J Fagg
REAL Consulting LLP i Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
1.0 Executive Summary
1.1
1.2
1.3
1.4
1.5
1.6
This Cost Plan for the proposed works totals £10,811,000 (excluding VAT) and provides an indicative estimated construction cost for the
development of a new 67 apartment residential development in two blocks together with associated external works and drainage at Brooklands
Approach, Romford.
The Cost Plan has been based upon updated revised drawings developed by McArthur Tring Architects following a review of individual flat sizes.
These drawings are listed within Section 3.0 of this report.
In terms of programme, these estimated rates and costs have not been updated in this revision F and continue to be based on prices at 3Q 2016.
Consequently, no allowances have been made for any current or future inflation in construction costs beyond 3Q2016.
We have also included a section relating to risks and possible opportunities. These should not be considered as an exhaustive list but may assist
when comparing the current estimated cost against the available budget for the project.
The measurements contained within this Cost Plan should not be relied upon for any other reason than the preparation of the Cost Plan itself.
This Cost Plan has been prepared solely for the use of S & J Fagg and should not be relied upon by any third party.
Please also take careful note of the various notes and assumptions made in the formulation of this Cost Plan, together with the noted exclusions.
REAL Consulting LLP Page 1 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
2.0 Cost Plan Summary
Ref Item £ £/m2 GIFA £/ft2 GIFA Notes
1.00 Demolitions, Site Clearance and Enabling Works £100,000
2.00 Construction of Residential Block 1 £4,223,000 £1,203 £112
3.00 Construction of Residential Block 2 £3,989,000 £1,202 £112 GIFA: 3,319m2
4.00 External Works and Landscaping £408,000
5.00 Below Ground Drainage £256,000
6.00 Incoming Mains Services £296,000
4.00 Sub-total £9,272,000 £1,358 £126 GIFA: 6,828m2
5.00 Main Contractor Preliminaries and Site Establishment £927,000 Based upon 10%
6.00 Design Reserve & Contingency £612,000
7.00 TOTAL ESTIMATED CONSTRUCTION COST £10,811,000 £1,583 £147 Excluding professional fees and VAT
(Refer to Assumptions and Exclusions hereafter)
On the basis of the information as listed in Section 3.0, our estimate of the price (Q3 2016) for construction costs of the works at local market prices is
as follows:-
GIFA: 3,509m2
Based upon 6%
REAL Consulting LLP Page 2 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
3.0 Basis and Assumptions
3.1 Information Used
3.1.1
McArthur Tring Architects
Drawing Nr: Description: Date2015/262: PI 01C Parking Layout Sept 20172015/262: PI 02C Ground Floor and Site Plan Sept 20172015/262: PI 03C 1st & 2nd Floor Plans Sept 20172015/262: PI 04G 3rd & 4th Floor Plans Sept 20172015/262: PI 05E Block 1 Proposed Elevations Sept 20172015/262: PI 06B Block 2 Proposed Elevations May 20172015/262: PI 07D Site Block Plan Sept 20172015/262: PI 08C Roof Plan Sept 2017
3.2 Assumptions
3.2.1
3.2.2 A typical "client led" procurement strategy has been assumed, and the following allowances have been made for on-costs:-
Main Contractor Preliminaries @ 10.0%
Main Contractor Overheads & Profit @ 5.0%
Design Reserve and Contingencies @ 6.0%
3.2.3
This Cost Plan has been prepared from the following design information and will need to be verified based upon further development of the Client brief,
ongoing design development, market testing, etc:
Costs continue to represent a present day price at 3rd Quarter 2016 base date as our previous estimate. No allowance for any construction industry
inflation beyond this time has been included.
No site investigation or civil/structural engineering design has been progressed to date. We have assumed that piled foundations would be employed,
over a clean site. We have also assumed that there are no particular considerations of developing close to the River Rom.
(Typically 1-2% could be expected to be included as a risk factor
within a Design & Build tender if implemented)
REAL Consulting LLP Page 3 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
3.0 Basis and Assumptions
3.2 Assumptions (Cont'd)
3.2.4
3.2.5
3.2.6 Roof coverings to be Bauder or similar roofing system with elements of "green roof" finish and paved areas as noted on the drawings.
3.2.7 Staircases as the drawings, noting that Block 2 has only the main accommodation stair (no separate means of escape).
3.2.8
3.2.9 Internal party walls assumed to be in block, with lightweight Gyproc type partitioning within each apartment.
3.2.10
3.2.11
3.2.12
Kitchens and bathrooms - ceramic tiling (£60/m2)
Remainder of apartments - floor coverings (£20/m2)
Staircases and communal areas - carpeting (£25/m2)
Ceilings assumed to be flat plasterboard lined with paint finish.
External wall finishes allow a blend of brick (masonry) and through colour render. Glazed balustrading measured to balconies and roof terraces; "Juliet"
balconies allowed for elsewhere.
Wall finishes assumed to be plasterboard dry lined with paint finish throughout. Separate allowances have been included for wall tiling as follows:
Kitchens - 4m2 per unit (£45/m2 allowance)
Bathrooms - 8m2 per unit (£50/m2 allowance)
Ensuite shower rooms - 6m2 per unit (£50/m2 allowance)
Floor finishes assumed as follows:
Basement construction assumed to be to be Undercroft style with only partial depth excavation (assumed approximately 1.50m depth). Waterproof
tanking has been allowed for as part of the Substructures.
Frame and upper floors assumed to be in reinforced concrete and flat slab. An element of steel structure is allowed at 4th floor level.
REAL Consulting LLP Page 4 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
3.0 Basis and Assumptions
3.2 Assumptions (Cont'd)
3.2.13
3.2.14
3.2.15
3.2.16
3.2.17
3.2.18 An allowance of £50,000 is included for works to the existing river frontage.
3.2.19 An allowance of £75,000 is included towards the cost of any mains services infrastructure.
3.2.20 Works are assumed to be executed in a single, continuous contract.
Enhanced/LED lighting to Kitchens and bathrooms.
A nominal allowance has been included for enhanced finishes within the main lobbies.
Hard landscaping is a blend of tarmacadam roadway and parking areas, together with minor areas of slab paving.
Kitchen fitments to be inclusive of oven, hob and extract, fridge/freezer and dishwasher - overall allowance £2,200/apartment.
Heating to be assumed via LTHW wet system.
REAL Consulting LLP Page 5 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
4.0 Exclusions
4.1 The following are excluded, but are known to have a cost impact and therefore need to be covered by other budgets within the overall Project
Cost Estimate. The list is intended only as a guide and cannot be relied upon to be exhaustive:
1) Abnormal foundations (bored piling is assumed). No allowance for any decontamination or additional measures that may be caused by abnormal
conditions.
2) Any major mains services infrastructure reinforcement.
3) Any inflation in costs to completion beyond current construction market prices.
4) Land acquisition and finance costs.
5) Marketing costs.
6) Professional and design team fees.
7) Party wall costs.
8) Value Added Tax.
9) Project Contingency.
REAL Consulting LLP Page 6 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
5.0 Schedule of Floor Areas
Residential Parking/ Bin Stores Circulation Structure TotalsBlock 1 Cycle/Plant
Semi Basement/Parking 0 622 0 16 9 647Ground Floor 473 0 21 151 42 687First Floor 622 0 0 90 47 759Second Floor 622 0 0 90 47 759Third Floor 409 0 0 74 25 508Fourth Floor 137 0 0 11 1 149
Totals - Block 1 2,263 622 21 432 171 3,509
Block 2
Semi Basement/Parking 0 588 0 22 7 617Ground Floor 510 0 11 65 36 622First Floor 560 0 0 52 32 644Second Floor 560 0 0 52 32 644Third Floor 508 0 0 48 24 580Fourth Floor 182 0 0 24 6 212
0Totals - Block 2 2,320 588 11 263 137 3,319
OVERALL TOTALS 4,583 1,210 32 695 308 6,828
Notes to be read in conjunction with Schedule of Floor Areas and other data indicated above
1 All areas have been measured in accordance with the RICS Code of Measuring Practice, 6th Edition September 2007.
2 Specific areas have been measured from the indicative drawings provided.
3 Definition of Gross Internal Area is the area of a building measured to the internal face of the perimeter walls at each floor level.
4 Quantities contained within this document should not be relied upon for any purpose other than the formulation of the Cost Plan itself.
REAL Consulting LLP Page 7 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
6.0 Principal Risks and Opportunities
6.1 Principal Risks
The following represents our current view of the key risks that pose a potential threat to the financial robustness of this report. The list
is not exhaustive but has been produced as a checklist to be actively managed so that these risks can be avoided/mitigated:-
Risk Rating
1) Additional foundation costs.
2) Major contamination.
3) Additional structural provision following engineer design input.
4) Major incoming services requirements.
5) Enhancements to internal finishes if market demands a more competitive "look and feel".
6)
6.2 Potential Opportunities Opportunity
Value
A TBC
B TBC
C £100,000
Total (Net of Contingencies and Other On-Costs) £100,000
Change in structural solution e.g. steel and precast
Significant increases in construction inflation between now and the planned start on site.
Alternative foundation strategy to piling (if possible)
Reduction in upper floors to 250mm (allowance based upon 300mm flat slab)
REAL Consulting LLP Page 8 Project R328
Residential Development, Brooklands Approach, Romford for S & J Fagg
Cost Plan Version 1.0 Rev F
29th September 2017
APPENDIX A - DETAILED BUILD-UP TO COST PLAN
Brooklands Approach, Romford
Demolitions, Site Clearance and Enabling Works 100,000 1.0
Residential Block 1 4,223,000 39.1
Residential Block 2 3,989,000 36.9
External Works and Landscaping 408,000 3.7
Below Ground Drainage 256,000 2.4
Incoming Mains Services 296,000 2.7
Sub Total 9,272,000 85.8
Main Contractor Preliminaries and Site Establishment 927,000 8.6
Design Reserve and Contingency @ 6% 612,000 5.6
Total Estimated Cost 10,811,000 100.0
Brooklands Approach, Romford
Cost Plan, Version A, Revision F
Description Amount
£
% Notes
Project: R328REAL Consulting LLP Page 1
Demolitions, Site Clearance and Enabling Works
1 Demolitions, Site Clearance and Enabling Works 99,500
Total 99,500
Brooklands Approach, Romford
Cost Model, Version A, Revision F
29 September 2017
Nr. Description Quantity Uni Rate
£
Amount
£
Notes
Project: R328REAL Consulting LLP Page 2
Residential Block 1
1 Substructures 467,962
2 Frame and Upper Floors 722,579
3 Roof 271,434
4 Stairs 68,500
5 External Walls 524,440
6 Windows and External Doors 229,200
7 Internal Walls 267,240
8 Internal Doors 96,100
9 Wall Finishes 161,212
10 Floor Finishes 239,430
11 Ceiling Finishes 110,466
12 Fittings 307,545
13 Sanitary Appliances 97,825
14 Disposal Installations 39,245
15 Heating, Ventilation and Domestic Water Services 222,840
16 Electrical Services 180,225
17 Protective, Communications and Special Installations 87,014
18 Lift Installations 40,000
19 Main Contractor OH&P on Services 5.00 33,357
20 Builders Work in Connection with Services 25,500
21 Renewables Obligations 30,800
Total 4,222,914
Brooklands Approach, Romford
Cost Model, Version A, Revision F
29 September 2017
Nr. Description Quantity Uni Rate
£
Amount
£
Notes
Project: R328REAL Consulting LLP Page 3
Residential Block 2
1 Substructures 447,227
2 Frame and Upper Floors 688,094
3 Roof 271,389
4 Stairs 25,000
5 External Walls 510,365
6 Windows and External Doors 200,600
7 Internal Walls 258,825
8 Internal Doors 90,400
9 Wall Finishes 151,192
10 Floor Finishes 230,265
11 Ceiling Finishes 105,320
12 Fittings 283,325
13 Sanitary Appliances 85,400
14 Disposal Installations 35,495
15 Heating, Ventilation and Domestic Water Services 214,860
16 Electrical Services 171,664
17 Protective, Communications and Special Installations 77,222
18 Lift Installations 40,000
19 Main Contractor OH&P on Services 5.00 31,232
20 Builders Work in Connection with Services 24,750
21 Renewables Obligations 46,200
Total 3,988,825
Brooklands Approach, Romford
Cost Model, Version A, Revision F
29 September 2017
Nr. Description Quantity Uni Rate
£
Amount
£
Notes
Project: R328REAL Consulting LLP Page 4
External Works and Landscaping
1 External Works Generally 407,650
Total 407,650
Brooklands Approach, Romford
Cost Model, Version A, Revision F
29 September 2017
Nr. Description Quantity Uni Rate
£
Amount
£
Notes
Project: R328REAL Consulting LLP Page 5
Below Ground Drainage
1 Foul Drainage 108,420
2 Surface Water Drainage 148,020
Total 256,440
Brooklands Approach, Romford
Cost Model, Version A, Revision F
29 September 2017
Nr. Description Quantity Uni Rate
£
Amount
£
Notes
Project: R328REAL Consulting LLP Page 6
Incoming Mains Services
1 Allowance for possible services mains infrastructure 1 item 75,000.00 75,000
2 Allowance for mains services connections and
infrastructure charges
67 nr 3,000.00 201,000
3 Builders work in connection; trenching etc 1 item 20,000.00 20,000
Total 296,000
Brooklands Approach, Romford
Cost Model, Version A, Revision F
29 September 2017
Nr. Description Quantity Uni Rate
£
Amount
£
Notes
Project: R328REAL Consulting LLP Page 7
Demolitions, Site Clearance and Enabling Works
Demolitions, Site Clearance and Enabling Works
1 Enabling Works
2 Allowance for general site clearance; removing existing
trees / shrubs etc
1 item 2,000.00 2,000
3 Allowance for demolition of existing buildings, grubbing
up slabs and foundations
1 item 50,000.00 50,000
4 Allowance for removal of existing buried drains and
services
1 item 25,000.00 25,000
5 Break out existing asphalt / concrete / tarmac etc; dispose
off site
1,500 m2 15.00 22,500 Can slabs be crushed on site and reused (eg
piling mat)
Total 99,500
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 8
Residential Block 1
Substructures
1 Piling Works
2 Bring plant to site and remove on completion 1 item 10,000.00 10,000
3 Allowance for bored piling 647 m2 150.00 97,050
4 Reinforced concrete ground beams / pile caps to external
walls
148 m 200.00 29,600
5 Reinforced concrete ground beams / pile caps to internal
party walls
31 m 180.00 5,580
6 Piling sundries 1 item 20,000.00 20,000
7 Excavation and Earthwork
8 Excavate to reduce levels say 300 deep 721 m2 5.00 3,605
9 Disposal of excavated material off site 216 m3 25.00 5,400
10 Form piling mat in Type 2 granular material say 300 thick 216 m3 45.00 9,720
11 Excavate for basement; approx. 1.50m deep 971 m3 3.00 2,913
12 Disposal of excavated material 971 m3 25.00 24,275
13 Earthwork support to sides of basement excavation and
working space allowances
797 m2 50.00 39,850
14 Surface water control 1 item 3,500.00 3,500
15 Level and prepare surface of fill after piling works 721 m2 5.00 3,605
16 Type 1 granular material Alling to make up levels say
200mm thick
129 m3 60.00 7,740
17 Allowance for lift pits 1 nr 5,000.00 5,000
18 Basement Construction
19 Reinforced insitu concrete basement slab 300 thick 194 m3 145.00 28,130
20 Reinforcement to slab; 130kg/m3 25 tn 1,200.00 30,000
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
325,968Carry Forward
Project: R328REAL Consulting LLP Page 9
21 Worked finish to slab 647 m2 2.00 1,294
22 Formwork to edge of slab 148 m 25.00 3,700
23 Damp proof membrane / tanking 647 m2 40.00 25,880
24 Walls
25 Reinforced insitu concrete basement walls 300 thick 120 m3 170.00 20,400
26 Reinforcement to walls; 175kg/m3 21 tn 1,200.00 25,200
27 Formwork to sides of walls 797 m2 40.00 31,880
28 Damp proof membrane / tanking 399 m2 40.00 15,960
29 Facing brickwork external skin where visible, say 1500mm
high
221 m2 80.00 17,680 Facing bricks £600/1000
Total 467,962
325,968Brought Forward
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 10
Residential Block 1
Frame and Upper Floors
1 Core Walls
2 Reinforced insitu concrete walls to basement; 300 thick 23 m3 170.00 3,910
3 Formwork to walls; basic finish 150 m2 40.00 6,000
4 Reinforcement; 175kg/m3 4 tn 1,200.00 4,800
5 Upper Floors
6 Reinforced insitu concrete slab; 300 thick 859 m3 145.00 124,555
7 Formwork to soffit of slab; basic finish 2,862 m2 45.00 128,790
8 Worked finish to concrete 2,862 m2 2.00 5,724
9 Formwork to edge of slabs 636 m 25.00 15,900
10 Reinforcement; 175kg/m3 150 tn 1,200.00 180,000
11 Frame
12 Notional allowance 2,862 m2 75.00 214,650
13 Balconies
14 Steel or concrete slab external balconies 153 m2 250.00 38,250
Total 722,579
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 11
Residential Block 1
Roof
1 Steel Frame
2 Allowance for steel framed roof structure at fourth Door
level
149 m2 150.00 22,350
3 Allowance for Are protection to steelwork 1 item 5,000.00 5,000
4 Roof slabs
5 Reinforced insitu concrete slab; 300 thick 184 m3 145.00 26,680
6 Formwork to soffit of slab; basic finish 612 m2 45.00 27,540
7 Worked finish to concrete 612 m2 2.00 1,224
8 Formwork to edge of slabs 349 m 25.00 8,725
9 Reinforcement; 175kg/m3 32 tn 1,200.00 38,400
10 Flat roof areas
11 Allowance for insulated Dat roof Anish, Bauder Total Roof
System or similar; including abutments/skirtings etc
928 m2 80.00 74,240
12 Extra over allowance for 'green roof' Anish to rooftop
garden area; protection layers, water retention/drainage
layer, soil substrate/planting or slab paving on pedestals;
including abutments/skirtings etc
172 m2 150.00 25,800
13 Extra over allowance for protection layers, slab paving on
pedestals; including abutments/skirtings etc (external
terraces)
153 m2 75.00 11,475
14 Allowance for roof outlets, rainwater goods and down
pipes to flat roof areas
1 item 15,000.00 15,000
15 Generally
16 Allowance for mansafe system to roof areas 1 item 5,000.00 5,000
17 Allowance for roof access ladders and the like 1 item 5,000.00 5,000
18 Allowance for roof level planting 1 item 5,000.00 5,000
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
271,434Carry Forward
Project: R328REAL Consulting LLP Page 12
271,434Brought Forward
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Total 271,434
Project: R328REAL Consulting LLP Page 13
Residential Block 1
Stairs
1 Car park straight Dight staircase; precast concrete, including
handrails and balustrades; car park to plant room
1 nr 3,000.00 3,000
2 Communal straight Dight staircase; precast concrete,
including handrails and balustrades; car park to ground
floor
2 nr 5,000.00 10,000
3 Communal straight Dight staircase; precast concrete,
including handrails and balustrades; ground Door entrance
lobby
2 nr 3,000.00 6,000
4 Communal dogleg staircase; precast concrete, including
handrails and balustrades; ground to third floor
1 nr 15,000.00 15,000
5 Communal dogleg staircase; precast concrete, including
handrails and balustrades; ground to fourth floor
1 nr 30,000.00 30,000
6 Flight of steps within 1B2P unit (4nr risers); timber,
including handrails and balustrades
6 nr 750.00 4,500
Total 68,500
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 14
Residential Block 1
External Walls
1 Facing brickwork traditional cavity wall construction;
stretcher bond
1,828 m2 155.00 283,340 Facing bricks £600/1000
2 Extra over for brick detailing 1 item 10,000.00 10,000 Notional allowance
3 Extra over for through colour insulated render to walls in
lieu facing brick external skin
914 m2 100.00 91,400 Allowance 50% wall area
4 Glazed balustrades to roof gardens and terraces 60 m 600.00 36,000
5 Glazed balustrades to projecting balconies 113 m 600.00 67,800
6 Juliet balconies to narrow windows 13 nr 800.00 10,400
7 Juliet balconies to wide windows 17 nr 1,500.00 25,500
Total 524,440
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 15
Residential Block 1
Windows and External Doors
1 Roller shutter entrance gate to basement car park 1 nr 7,500.00 7,500
2 Roller shutter door set to bin store 1 nr 2,500.00 2,500
3 Single door sets to car park area 1 nr 800.00 800
4 Double main entrance door sets to Block 1 1 nr 2,000.00 2,000
5 Single secondary door sets 3 nr 800.00 2,400
6 Double secondary door sets 2 nr 1,500.00 3,000
7 Single door sets to balconies 12 nr 800.00 9,600
8 Sliding door sets to terraces 3.0 x 2.1m 27 nr 3,000.00 81,000
9 Sliding folding door sets to terraces 3.0 x 2.4m 3 nr 4,500.00 13,500
10 Sliding folding door sets to terraces 3.3 x 2.4m 1 nr 4,800.00 4,800
11 Full height glazing system 76 m2 600.00 45,600
12 Double glazed windows 113 m2 500.00 56,500
Total 229,200
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 16
Residential Block 1
Internal Walls
1 Party walls between apartments, corridors, communal
areas
1,434 m2 85.00 121,890 Block cavity wall
2 Internal stud partitions within Dats; including insulation;
assumed 2400 high
855 m 170.00 145,350
Total 267,240
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 17
Residential Block 1
Internal Doors
1 Flat entrance doors, single leaf 34 nr 700.00 23,800
2 Internal Dat doors, single leaf 150 nr 400.00 60,000
3 Internal Dat doors, double leaf 1 nr 600.00 600
4 Communal doors, single leaf 15 nr 600.00 9,000
5 Communal doors, double leaf 3 nr 900.00 2,700
Total 96,100
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 18
Residential Block 1
Wall Finishes
1 Plasterboard dry lining to inside face of external walls /
party and communal walls
3,865 m2 12.00 46,380
2 Skim coat plaster to dry lining of external walls / party and
communal walls
3,865 m2 5.00 19,325
3 Dry lining to stud partitions within flats 4,106 m2 0.00 0 Included in Internal Walls element
4 Skim coat plaster to stud partitions within flats 4,106 m2 5.00 20,530
5 Emulsion paint finish to plastered walls 7,971 m2 5.50 43,841
6 Emulsion paint finish or similar to basement walls 603 m2 5.50 3,317
7 Extra over for wall tiling to kitchens; splashbacks 136 m2 45.00 6,120 Assumed 4m2 per flat
8 Extra over for wall tiling to bathrooms 272 m2 50.00 13,600 Assumed 8m2 per flat
9 Extra over for wall tiling to en suites 162 m2 50.00 8,100 Assumed 6m2 per flat
Total 161,213
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 19
Residential Block 1
Floor Finishes
1 Floor screed 75 thick; including 75 insulation 2,701 m2 40.00 108,040
2 Tiling to kitchen areas, bathrooms and en suites within Dats 618 m2 60.00 37,080 Assumed 10m2 per kitchen; 5m2 per
bathroom; 4m2 per en suite
3 Carpet finish to remainder of flats 1,645 m2 20.00 32,900
4 Contract carpet to communal areas and stairs 494 m2 25.00 12,350
5 Floor Anish (assume paint/sealer) to car park and general
basement areas
582 m2 15.00 8,730
6 MDF skirtings throughout; painted 3,583 m 10.00 35,830
7 Allowance for entrance matting / matwells 1 item 2,000.00 2,000
8 Allowance for enhanced lobby finishes 1 item 2,500.00 2,500
Total 239,430
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 20
Residential Block 1
Ceiling Finishes
1 Plasterboard lining to ceilings; M/F system 2,701 m2 25.00 67,525
2 Skim coat plaster to ceilings 2,701 m2 7.00 18,907
3 Emulsion paint finish to ceilings 2,701 m2 6.00 16,206
4 Paint Anish or similar to car park and general basement
areas
638 m2 6.00 3,828
5 Allowance for access panels for services 1 item 4,000.00 4,000
Total 110,466
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 21
Residential Block 1
Fittings
1 Allowance for kitchen fittings, worktops etc - 3B 2 nr 4,000.00 8,000
2 Allowance for kitchen fittings, worktops etc - 2B 20 nr 3,500.00 70,000
3 Allowance for kitchen fittings, worktops etc - 1B 12 nr 2,500.00 30,000
4 Allowance for white goods and appliances 34 nr 2,200.00 74,800 Assumed oven, hob and extract, fridge/freezer,
dishwasher
5 Allowance for built-in wardrobes (incl framework, doors,
shelf, rail etc)
44 nr 2,000.00 88,000
6 Allowance for built-in Atted wardrobe to top Door 3B6P
dressing room (incl framework, doors, shelf, rail etc)
1 nr 5,000.00 5,000
7 Allowance for airing cupboard slatted shelving 34 nr 150.00 5,100
8 Allowance for curtain battens to windows 103 nr 15.00 1,545
9 Allowance for sundry fittings; bathrooms 34 nr 500.00 17,000
10 Allowance for sundry fittings; en suites 27 nr 300.00 8,100
Total 307,545
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 22
Residential Block 1
Sanitary Appliances
1 Allowances for sanitary appliances, including taps and
traps etc:
2 Stainless steel kitchen sink 34 nr 300.00 10,200
3 Low level china WC suite 61 nr 275.00 16,775
4 China wash hand basin and pedestal 61 nr 250.00 15,250
5 Acrylic bath 34 nr 400.00 13,600
6 Over-bath shower unit; shower screen 34 nr 600.00 20,400
7 En Suite shower unit; tray and screen 27 nr 800.00 21,600
Total 97,825
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 23
Residential Block 1
Disposal Installations
1 Above ground disposal installations; SVP stacks 3,509 m2 5.00 17,545
2 uPVC branch/waste connection (per appliance) 217 nr 100.00 21,700
Total 39,245
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 24
Residential Block 1
Heating, Ventilation and Domestic Water Services
1 Allowance for gas fired boiler installation 34 nr 2,000.00 68,000
2 Allowance for radiator heating to flats 2,263 m2 30.00 67,890
3 Allowance for heating to communal areas 494 m2 0.00 0 Excluded
4 Allowance for central water booster, cistern and associated
pipe work and the like
1 item 15,000.00 15,000
5 Allowance for domestic hot and cold water services (per
appliance)
217 nr 160.00 34,720
6 Allowance for local ventilation extract installation 95 nr 300.00 28,500 Bathrooms, en suites and kitchenettes
7 Allowance for extract ventilation to car park / basement
area
582 m2 15.00 8,730
Total 222,840
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 25
Residential Block 1
Electrical Services
1 Allowance for sub-mains, distribution and small power to
flats
2,263 m2 25.00 56,575
2 Allowance for sub-mains, distribution and small power to
communal areas
494 m2 10.00 4,940
3 Allowance for sub-mains, distribution and small power to
car park areas
582 m2 8.00 4,656
4 Allowance for lighting installation to flats 2,263 m2 20.00 45,260
5 Extra; allowance for LED spotlights to
kitchens/bathrooms/ensuites
95 nr 250.00 23,750
6 Allowance for lighting installation to communal areas 494 m2 25.00 12,350
7 Allowance for lighting installation to car park areas 582 m2 20.00 11,640
8 Power supply to mechanical installations 3,509 m2 5.00 17,545
9 Earthing and bonding 3,509 m2 1.00 3,509
Total 180,225
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 26
Residential Block 1
Protective, Communications and Special Installations
1 Lightning protection 3,509 m2 0.00 0 Excluded
2 Door access to communal areas 3 nr 1,000.00 3,000
3 Door access control to apartments 34 nr 250.00 8,500
4 Fire detection to flats 2,263 m2 8.00 18,104
5 Allowance for data/comms installation 3,509 m2 10.00 35,090
6 Allowance for dry risers to communal areas 494 m2 30.00 14,820
7 Allowance for CCTV 1 item 7,500.00 7,500 Nominal allowance
Total 87,014
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 27
Residential Block 1
Lift Installations
1 Allowance for lift installations; basement to fourth Door; 8
person lift
1 nr 40,000.00 40,000
Total 40,000
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 28
Residential Block 1
Builders Work in Connection with Services
1 Allowance for holes, chases and general builders work etc 34 nr 750.00 25,500
Total 25,500
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 29
Residential Block 1
Renewables Obligations
1 Renewables Obligations
2 Allowance 22 nr 1,400.00 30,800
Total 30,800
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 30
Residential Block 2
Substructures
1 Piling Works
2 Bring plant to site and remove on completion 1 item 10,000.00 10,000
3 Allowance for bored piling 617 m2 150.00 92,550
4 Reinforced concrete ground beams / pile caps to external
walls
140 m 200.00 28,000
5 Reinforced concrete ground beams / pile caps to internal
party walls
32 m 180.00 5,760
6 Piling sundries 1 item 20,000.00 20,000
7 Excavation and Earthwork
8 Excavate to reduce levels say 300 deep 687 m2 5.00 3,435
9 Disposal of excavated material off site 206 m3 25.00 5,150
10 Form piling mat in Type 2 granular material say 300 thick 206 m3 45.00 9,270
11 Level and prepare surface of fill after piling works 687 m2 5.00 3,435
12 Excavate for basement; approx. 1.50m deep 926 m3 3.00 2,778
13 Disposal of excavated material 926 m3 25.00 23,150
14 Earthwork support to sides of basement excavation and
working space allowances
753 m2 50.00 37,650
15 Surface water control 1 item 3,500.00 3,500
16 Type 1 granular material Alling to make up levels say
200mm thick
123 m3 60.00 7,380
17 Allowance for lift pits 1 nr 5,000.00 5,000
18 Basement Construction
19 Reinforced insitu concrete basement slab 300 thick 185 m3 145.00 26,825
20 Reinforcement to slab; 130kg/m3 24 tn 1,200.00 28,800
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
312,683Carry Forward
Project: R328REAL Consulting LLP Page 31
21 Worked finish to slab 617 m2 2.00 1,234
22 Formwork to edge of slab 140 m 25.00 3,500
23 Damp proof membrane / tanking 617 m2 40.00 24,680
24 Walls
25 Reinforced insitu concrete basement walls 300 thick 113 m3 170.00 19,210
26 Reinforcement to walls; 175kg/m3 20 tn 1,200.00 24,000
27 Formwork to sides of walls 753 m2 40.00 30,120
28 Damp proof membrane / tanking 377 m2 40.00 15,080
29 Facing brickwork external skin where visible, say 1500mm
high
209 m2 80.00 16,720 Facing bricks £600/1000
Total 447,227
312,683Brought Forward
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 32
Residential Block 2
Frame and Upper Floors
1 Core Walls
2 Reinforced insitu concrete walls to basement; 300 thick 23 m3 170.00 3,910
3 Formwork to walls; basic finish 153 m2 40.00 6,120
4 Reinforcement; 175kg/m3 4 tn 1,200.00 4,800
5 Upper Floors
6 Reinforced insitu concrete slab; 300 thick 811 m3 145.00 117,595
7 Formwork to soffit of slab; basic finish 2,702 m2 45.00 121,590
8 Worked finish to concrete 2,702 m2 2.00 5,404
9 Formwork to edge of slabs 615 m 25.00 15,375
10 Reinforcement; 175kg/m3 142 tn 1,200.00 170,400
11 Frame
12 Notional allowance 2,702 m2 75.00 202,650
13 Balconies
14 Steel or concrete slab external balconies 161 m2 250.00 40,250
Total 688,094
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 33
Residential Block 2
Roof
1 Steel Frame
2 Allowance for steel framed roof structure at fourth Door
level
230 m2 150.00 34,500
3 Allowance for Are protection to steelwork 1 item 5,000.00 5,000
4 Roof slabs
5 Reinforced insitu concrete slab; 300 thick 126 m3 145.00 18,270
6 Formwork to soffit of slab; basic finish 512 m2 45.00 23,040
7 Worked finish to concrete 512 m2 2.00 1,024
8 Formwork to edge of slabs 216 m 25.00 5,400
9 Reinforcement; 175kg/m3 27 tn 1,200.00 32,400
10 Flat roof areas
11 Allowance for insulated Dat roof Anish, Bauder Total Roof
System or similar; including abutments/skirtings etc
811 m2 80.00 64,880
12 Extra over allowance for 'green roof' Anish to rooftop
garden area; protection layers, water retention/drainage
layer, soil substrate/planting or slab paving on pedestals;
including abutments/skirtings etc
282 m2 150.00 42,300
13 Extra over allowance for protection layers, slab paving on
pedestals; including abutments/skirtings etc (external
terraces)
161 m2 75.00 12,075
14 Allowance for roof outlets, rainwater goods and down
pipes to flat roof areas
1 item 15,000.00 15,000
15 Generally
16 Allowance for mansafe system to roof areas 1 item 5,000.00 5,000
17 Allowance for roof access ladders and the like 1 item 5,000.00 5,000
18 Allowance for roof level planting 1 item 7,500.00 7,500
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
271,389Carry Forward
Project: R328REAL Consulting LLP Page 34
271,389Brought Forward
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Total 271,389
Project: R328REAL Consulting LLP Page 35
Residential Block 2
Stairs
1 Communal dogleg staircase; precast concrete, including
handrails and balustrades; basement to fourth floor
1 nr 25,000.00 25,000
Total 25,000
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 36
Residential Block 2
External Walls
1 Facing brickwork traditional cavity wall construction;
stretcher bond
1,803 m2 155.00 279,465 Facing bricks £600/1000
2 Extra over for brick detailing 1 item 10,000.00 10,000 Notional allowance
3 Extra over for through colour insulated render to walls in
lieu facing brick external skin
902 m2 100.00 90,200 Allowance 50% wall area
4 Glazed balustrades to roof gardens and terraces 76 m 600.00 45,600
5 Glazed balustrades to projecting balconies 109 m 600.00 65,400
6 Juliet balconies to narrow windows 4 nr 800.00 3,200
7 Juliet balconies to wide windows 11 nr 1,500.00 16,500
Total 510,365
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 37
Residential Block 2
Windows and External Doors
1 Roller shutter entrance gate to basement car park 1 nr 7,500.00 7,500
2 Roller shutter door set to bin store 2 nr 5,000.00 10,000
3 Double main entrance door sets to Block 2 1 nr 2,000.00 2,000
4 Single secondary door sets 1 nr 800.00 800
5 Double secondary door sets 4 nr 1,500.00 6,000
6 Single door sets to balconies 12 nr 800.00 9,600
7 Sliding door sets to terraces 2.5 x 2.1m 19 nr 3,000.00 57,000
8 Full height glazing system 72 m2 600.00 43,200
9 Double glazed windows 129 m2 500.00 64,500
Total 200,600
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 38
Residential Block 2
Internal Walls
1 Party walls between apartments, corridors, communal
areas
1,247 m2 85.00 105,995 Block cavity wall
2 Internal stud partitions within Dats; including insulation;
assumed 2400 high
899 m 170.00 152,830
Total 258,825
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 39
Residential Block 2
Internal Doors
1 Flat entrance doors, single leaf 33 nr 700.00 23,100
2 Internal Dat doors, single leaf 148 nr 400.00 59,200
3 Internal Dat doors, double leaf 0 nr 600.00 0
4 Communal doors, single leaf 12 nr 600.00 7,200
5 Communal doors, double leaf 1 nr 900.00 900
Total 90,400
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 40
Residential Block 2
Wall Finishes
1 Plasterboard dry lining to inside face of external walls /
party and communal walls
3,459 m2 12.00 41,508
2 Skim coat plaster to dry lining of external walls / party and
communal walls
3,459 m2 5.00 17,295
3 Dry lining to stud partitions within flats 4,317 m2 0.00 0 Included in Internal Walls element
4 Skim coat plaster to stud partitions within flats 4,317 m2 5.00 21,585
5 Emulsion paint finish to plastered walls 7,776 m2 5.50 42,768
6 Emulsion paint finish or similar to basement walls 581 m2 5.50 3,196
7 Extra over for wall tiling to kitchens; splashbacks 132 m2 45.00 5,940 Assumed 4m2 per flat
8 Extra over for wall tiling to bathrooms 264 m2 50.00 13,200 Assumed 8m2 per flat
9 Extra over for wall tiling to en suites 114 m2 50.00 5,700 Assumed 6m2 per flat
Total 151,192
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 41
Residential Block 2
Floor Finishes
1 Floor screed 75 thick; including 75 insulation 2,702 m2 40.00 108,080
2 Tiling to kitchen areas, bathrooms and en suites within Dats 571 m2 60.00 34,260 Assumed 10m2 per kitchen; 5m2 per
bathroom; 4m2 per en suite
3 Carpet finish to remainder of flats 1,748 m2 20.00 34,960
4 Contract carpet to communal areas and stairs 291 m2 25.00 7,275
5 Floor Anish (assume paint/sealer) to car park and general
basement areas
570 m2 15.00 8,550
6 MDF skirtings throughout; painted 3,314 m 10.00 33,140
7 Allowance for entrance matting / matwells 1 item 2,000.00 2,000
8 Allowance for enhanced lobby finishes 1 item 2,000.00 2,000
Total 230,265
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 42
Residential Block 2
Ceiling Finishes
1 Plasterboard lining to ceilings; M/F system 2,570 m2 25.00 64,250
2 Skim coat plaster to ceilings 2,570 m2 7.00 17,990
3 Emulsion paint finish to ceilings 2,570 m2 6.00 15,420
4 Paint Anish or similar to car park and general basement
areas
610 m2 6.00 3,660
5 Allowance for access panels for services 1 item 4,000.00 4,000
Total 105,320
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 43
Residential Block 2
Fittings
1 Allowance for kitchen fittings, worktops etc - 3B 7 nr 4,000.00 28,000
2 Allowance for kitchen fittings, worktops etc - 2B 13 nr 3,500.00 45,500
3 Allowance for kitchen fittings, worktops etc - 1B 13 nr 2,500.00 32,500
4 Allowance for white goods and appliances 33 nr 2,200.00 72,600 Assumed oven, hob and extract, fridge/freezer,
dishwasher
5 Allowance for built-in wardrobes (incl framework, doors,
shelf, rail etc)
38 nr 2,000.00 76,000
6 Allowance for airing cupboard slatted shelving 33 nr 150.00 4,950
7 Allowance for curtain battens to windows 105 nr 15.00 1,575
8 Allowance for sundry fittings; bathrooms 33 nr 500.00 16,500
9 Allowance for sundry fittings; en suites 19 nr 300.00 5,700
Total 283,325
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 44
Residential Block 2
Sanitary Appliances
1 Allowances for sanitary appliances, including taps and
traps etc:
2 Stainless steel kitchen sink 33 nr 300.00 9,900
3 Low level china WC suite 52 nr 275.00 14,300
4 China wash hand basin and pedestal 52 nr 250.00 13,000
5 Acrylic bath 33 nr 400.00 13,200
6 Over-bath shower unit; shower screen 33 nr 600.00 19,800
7 En Suite shower unit; tray and screen 19 nr 800.00 15,200
Total 85,400
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 45
Residential Block 2
Disposal Installations
1 Above ground disposal installations; SVP stacks 3,319 m2 5.00 16,595
2 uPVC branch/waste connection (per appliance) 189 nr 100.00 18,900
Total 35,495
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 46
Residential Block 2
Heating, Ventilation and Domestic Water Services
1 Allowance for gas fired boiler installation 33 nr 2,000.00 66,000
2 Allowance for radiator heating to flats 2,319 m2 30.00 69,570
3 Allowance for heating to communal areas 291 m2 0.00 0 Excluded
4 Allowance for central water booster, cistern and associated
pipework and the like
1 item 15,000.00 15,000
5 Allowance for domestic hot and cold water services (per
appliance)
189 nr 160.00 30,240
6 Allowance for local ventilation extract installation 85 nr 300.00 25,500 Bathrooms, en suites and kitchenettes
7 Allowance for extract ventilation to car park / basement
area
570 m2 15.00 8,550
Total 214,860
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 47
Residential Block 2
Electrical Services
1 Allowance for sub-mains, distribution and small power to
flats
2,319 m2 25.00 57,975
2 Allowance for sub-mains, distribution and small power to
communal areas
291 m2 10.00 2,910
3 Allowance for sub-mains, distribution and small power to
car park areas
570 m2 8.00 4,560
4 Allowance for lighting installation to flats 2,319 m2 20.00 46,380
5 Extra; allowance for LED spotlights to
kitchens/bathrooms/ensuites
85 nr 250.00 21,250
6 Allowance for lighting installation to communal areas 291 m2 25.00 7,275
7 Allowance for lighting installation to car park areas 570 m2 20.00 11,400
8 Power supply to mechanical installations 3,319 m2 5.00 16,595
9 Earthing and bonding 3,319 m2 1.00 3,319
Total 171,664
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 48
Residential Block 2
Protective, Communications and Special Installations
1 Lightning protection 3,319 m2 0.00 0 Excluded
2 Door access to communal areas 1 nr 1,000.00 1,000
3 Door access control to apartments 33 nr 250.00 8,250
4 Fire detection to flats 2,319 m2 8.00 18,552
5 Allowance for data/comms installation 3,319 m2 10.00 33,190
6 Allowance for dry risers to communal areas 291 m2 30.00 8,730
7 Allowance for CCTV 1 item 7,500.00 7,500 Nominal allowance
Total 77,222
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 49
Residential Block 2
Lift Installations
1 Allowance for lift installations; basement to fourth Door; 8
person lift
1 nr 40,000.00 40,000
Total 40,000
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 50
Residential Block 2
Builders Work in Connection with Services
1 Allowance for holes, chases and general builders work etc 33 nr 750.00 24,750
Total 24,750
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 51
Residential Block 2
Renewables Obligations
1 Renewables Obligations
2 Allowance 33 nr 1,400.00 46,200
Total 46,200
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 52
External Works and Landscaping
External Works Generally
1 Hard Landscaping
2 Allowance for macadam access road 400 m2 80.00 32,000
3 Allowance for macadam parking bays and circulation 1,660 m2 70.00 116,200
4 Allowance for asphalt footpath 140 m2 50.00 7,000
5 Allowance for resurfacing existing footpath 50 m2 25.00 1,250
6 Allowance for paving to entrance of Block 2 50 m2 120.00 6,000
7 Allowance for paved ramp to entrance of Block 2 30 m2 150.00 4,500
8 Soft Landscaping
9 Allowance for topsoil, preparation and turfing 780 m2 40.00 31,200
10 Allowance for topsoil, preparation and planting 1 item 15,000.00 15,000
11 Walls, Fences, Gates etc
12 Allowance for facing brick retaining walls to basement car
park entrances
60 m 800.00 48,000
13 Allowance for facing brick walls to Block 1 frontage 30 m 500.00 15,000
14 Allowance for fencing / railings to site perimeter 400 m 60.00 24,000 Assumed to full perimeter
15 Allowance for flight of steps to Block 2 entrance 1 nr 2,500.00 2,500
16 Allowance for sundry lengths of fencing / walling within
site
1 item 15,000.00 15,000
17 River Frontage
18 Allowance for works to existing frontage to River Rom
(approx 100m length)
1 item 50,000.00 50,000 Notional allowance
19 Miscellaneous
20 Allowance for low level external lighting 1 item 20,000.00 20,000
21 Allowance for street furniture 1 item 2,500.00 2,500
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
390,150Carry Forward
Project: R328REAL Consulting LLP Page 53
22 Allowance for external signage 1 item 2,500.00 2,500
23 Allowance for cycle racking 1 item 5,000.00 5,000 Nominal allowance
24 Allowance for children's play area equipment 1 item 10,000.00 10,000 Notional allowance
Total 407,650
390,150Brought Forward
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 54
Below Ground Drainage
Foul Drainage
1 Allowance for foul drainage 6,828 m2 15.00 102,420
2 Allowance for sewer connection 1 nr 6,000.00 6,000 Likely interruption to North Street
Total 108,420
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 55
Below Ground Drainage
Surface Water Drainage
1 Allowance for surface water drainage - buildings 6,828 m2 15.00 102,420
2 Allowance for surface water drainage - hard pavings 2,030 m2 20.00 40,600
3 Allowance for outfall connection to river (if allowable) / or
public system
1 item 5,000.00 5,000
4 Note: no allowance for tanked surface water attenuation
Total 148,020
Brooklands Approach, Romford
Cost Plan Version: A, Revision: F
29 September 2017
No. Description Quantity Unit Rate
£
Amount Notes
Project: R328REAL Consulting LLP Page 56
Bed
Revised
Est. Floor
Area Mt²
BLOCK 1
FLAT 1 Ground 1 NO 51 50 549 538 £225,000 £410
FLAT 2 Ground 2 NO 61 61 657 657 £270,000 £411
FLAT 3 Ground 1 NO 50.5 50 544 538 £222,500 £409
FLAT 4 Ground 1 NO 50 50 538 538 £220,000 £409
FLAT 5 Ground 1 YES 50 50 538 538 £225,000 £418
FLAT 6 Ground 2 YES 70 70 753 753 £310,000 £411
FLAT 7 Ground 2 YES 70 70 753 753 £310,000 £411
FLAT 8 Ground 2 YES 70 70 753 753 £310,000 £411
FLAT 9 First 1 NO 51 50 549 538 £225,000 £410
FLAT 10 First 2 NO 61 61 657 657 £270,000 £411
FLAT 11 First 1 NO 50.5 50 544 538 £225,000 £414
FLAT 12 First 1 NO 50 50 538 538 £220,000 £409
FLAT 13 First 1 NO 50 50 538 538 £225,000 £418
FLAT 14 First 2 YES 70 70 753 753 £310,000 £411
Suggested Net Market Values
Development at Brooklands Approach, Romford
as of October 2017
Est. Floor
Area Mt²Floor Balcony £ per Ft²
Est. Floor
Area Ft²Flat
Revised
Est. Floor
Area Ft²Suggested Net
Market Value £
1
Bed
Revised
Est. Floor
Area Mt²
Suggested Net Market Values
Development at Brooklands Approach, Romford
as of October 2017
Est. Floor
Area Mt²Floor Balcony £ per Ft²
Est. Floor
Area Ft²Flat
Revised
Est. Floor
Area Ft²Suggested Net
Market Value £
FLAT 15 First 2 YES 70 70 753 753 £310,000 £411
FLAT 16 First 2 YES 70 70 753 753 £310,000 £411
FLAT 17 First 2 YES 88 86 947 926 £395,000 £417
FLAT 18 First 2 YES 66 61 710 657 £275,000 £387
FLAT 19 Second 1 NO 51 50 549 538 £225,000 £410
FLAT 20 Second 2 NO 61 61 657 657 £270,000 £411
FLAT 21 Second 1 NO 50.5 50 544 538 £225,000 £414
FLAT 22 Second 1 NO 50 50 538 538 £220,000 £409
FLAT 23 Second 1 NO 50 50 538 538 £225,000 £418
FLAT 24 Second 2 YES 70 70 753 753 £310,000 £411
FLAT 25 Second 2 YES 70 70 753 753 £310,000 £411
FLAT 26 Second 2 YES 70 70 753 753 £310,000 £411
FLAT 27 Second 2 YES 88 86 947 926 £395,000 £417
FLAT 28 Second 2 YES 66 61 710 657 £275,000 £387
FLAT 29 Third 3 NO 90 90 969 969 £405,000 £418
FLAT 30 Third 2 NO 71 70 764 753 £320,000 £419
FLAT 31 Third 2 NO 70 70 753 753 £310,000 £411
FLAT 32 Third 3 YES 88 70 947 753 £395,000 £417
FLAT 33 Third 2 YES 98 70 1055 753 £380,000 £360
FLAT 34 FOURTH 3 YES 118 90 1270 969 £490,000 £386
2,261 2,167 24,332 23,326
£9,922,500 £409
Block 1 Total Average £ft²
Block 1 Total GDV £ 2
Bed
Revised
Est. Floor
Area Mt²
Suggested Net Market Values
Development at Brooklands Approach, Romford
as of October 2017
Est. Floor
Area Mt²Floor Balcony £ per Ft²
Est. Floor
Area Ft²Flat
Revised
Est. Floor
Area Ft²Suggested Net
Market Value £
BLOCK 2
FLAT 1 Ground 1 NO 54 50 581 538 £240,000 £413
FLAT 2 Ground 1 NO 53 50 570 538 £235,000 £412
FLAT 3 Ground 1 YES 55 50 592 538 £250,000 £422
FLAT 4 Ground 2 YES 70 70 753 753 £310,000 £411
FLAT 5 Ground 2 YES 83 70 893 753 £370,000 £414
FLAT 6 Ground 3 YES 80 74 861 797 £360,000 £418
FLAT 7 Ground 1 NO 55 50 592 538 £250,000 £422
FLAT 8 Ground 1 NO 54 50 581 538 £250,000 £430
FLAT 9 First 2 YES 83 70 893 753 £370,000 £414
FLAT 10 First 3 YES 80 74 861 797 £375,000 £435
FLAT 11 First 1 NO 55 50 592 538 £235,000 £397
FLAT 12 First 1 NO 54 50 581 538 £240,000 £413
FLAT 13 First 2 NO 73 70 786 753 £325,000 £414
FLAT 14 First 1 NO 59 50 635 538 £260,000 £409
FLAT 15 First 3 YES 83 74 893 797 £370,000 £414
FLAT 16 First 2 YES 70 70 753 753 £310,000 £411
FLAT 17 Second 2 YES 83 70 893 753 £370,000 £414
FLAT 18 Second 3 YES 80 74 861 797 £360,000 £418
FLAT 19 Second 1 NO 55 50 592 538 £245,000 £414
FLAT 20 Second 1 NO 54 50 581 538 £240,000 £413
FLAT 21 Second 2 NO 73 70 786 753 £325,000 £4143
Bed
Revised
Est. Floor
Area Mt²
Suggested Net Market Values
Development at Brooklands Approach, Romford
as of October 2017
Est. Floor
Area Mt²Floor Balcony £ per Ft²
Est. Floor
Area Ft²Flat
Revised
Est. Floor
Area Ft²Suggested Net
Market Value £
FLAT 22 Second 1 NO 59 50 635 538 £260,000 £409
FLAT 23 Second 3 YES 83 74 893 797 £370,000 £414
FLAT 24 Second 2 YES 70 70 753 753 £310,000 £411
FLAT 25 Third 2 YES 83 70 893 753 £370,000 £414
FLAT 26 Third 3 YES 80 74 861 797 £360,000 £418
FLAT 27 Third 1 TERRACE 57 50 614 538 £250,000 £407
FLAT 28 Third 2 NO 73 70 786 753 £325,000 £414
FLAT 29 Third 1 NO 59 50 635 538 £260,000 £409
FLAT 30 Third 3 YES 83 74 893 797 £370,000 £414
FLAT 31 Third 2 YES 70 86 753 926 £310,000 £411
FLAT 32 Fourth 3 TERRACE 91 86 980 926 £385,000 £393
FLAT 33 Fourth 3 TERRACE 91 86 980 926 £385,000 £393
2,305 2,126 24,811 22,884 413
£10,245,000
4,566 4,293 49,143 45,769 410
£20,157,500
Please note that this is marketing advice only and does not constitute a formal valuation and should not be used for bank lending
purposes. Prices are set in today’s market conditions and may be subject to fluctuation depending on the market conditions
prevailing at the time of release. We have not taken into account any unusual or onerous ground or other condition that could
affect the sale of the units.Values given are based on a 4 to 6 week sale time and an average rate of sale of 1.5 net units pcm after
build completion of a view home.
Block 2 Total Average £ft²
Block 2 Total GDV £
Total GDV £
Total Average £ft²
4
Appendix 4 – GLA Toolkit – Brooklands Approach Site, Romford
Adam Roberts Consultancy Ltd Page 1 of 4 Thursday, 12 October 2017
Appendix 4 – GLA Toolkit – Brooklands Approach Site, Romford
Adam Roberts Consultancy Ltd Page 2 of 4 Thursday, 12 October 2017
Appendix 4 – GLA Toolkit – Brooklands Approach Site, Romford
Adam Roberts Consultancy Ltd Page 3 of 4 Thursday, 12 October 2017
Appendix 4 – GLA Toolkit – Brooklands Approach Site, Romford
Adam Roberts Consultancy Ltd Page 4 of 4 Thursday, 12 October 2017