Achieving-On-stream-Reliability-at-TESOROs-Mandan-FCC ...

10
Tracking No. 00.00.2010 Tracking No. 00.00.2010 2 Achieving On-stream Reliability At TESORO’S Mandan FCC Unit Presented by Harvey McQuiston, FCC Program Director, Shaw E & C Galveston, TX May 3-6, 2011 History The FCC unit is an Exxon Model IV originally commissioned in 1954 Tesoro acquired Mandan, North Dakota Refinery in 2001 Tesoro revamped the FCC unit to upgrade technology and improve reliability Tracking No. 00.00.2010 3 improve reliability After the revamp the FCC unit ran continuously without a major outage The next scheduled turnaround revealed that only nominal routine maintenance was required 3

Transcript of Achieving-On-stream-Reliability-at-TESOROs-Mandan-FCC ...

Trac

king N

o. 0

0.00.2

010

Trac

king N

o. 0

0.00.2

010

2

Achieving On-stream Reliability At TESORO’S Mandan FCC Unit

Presented byHarvey McQuiston, FCC Program Director, Shaw E & C

Galveston, TX May 3-6, 2011

History

• The FCC unit is an Exxon Model IV originally commissioned in 1954

• Tesoro acquired Mandan, North Dakota Refinery in 2001• Tesoro revamped the FCC unit to upgrade technology and

improve reliability

Trac

king N

o. 0

0.00.2

010

3

improve reliability• After the revamp the FCC unit ran continuously without a

major outage• The next scheduled turnaround revealed that only nominal

routine maintenance was required

3

Unit Description (Pre-Revamp)

• Cat feed is reduced crude (no VDU)• 23-26,000 bpsd feed• 4 Bete nozzles (feed & HCO)• Internal rough cut cyclone & quench

Trac

king N

o. 0

0.00.2

010

4

• Partial CO burn (5% CO) 1330-1360◌ ْF

4

Original Design

Trac

king N

o. 0

0.00.2

010

55

Operating Issues

• Poor conversion, high dry gas and bottoms• Slurry circuit fouling issues• On-line maintenance difficult due to long, harsh winters• FCC reliability impacts crude unit as both units are heat

Trac

king N

o. 0

0.00.2

010

6

integrated

6

Revamp Objectives

• Improve conversion• Minimize dry gas• Maximize C3/C4 yields (summer)• Maximize octane barrels

Trac

king N

o. 0

0.00.2

010

7

• Improve reliability to minimize unscheduled shutdowns• Reduce routine maintenance

7

Technology Upgrades

• New external vertical riser with longer residence time• New Shaw feed injection nozzles• New rough cut cyclone (external)• Installed reactor vapor quench

Trac

king N

o. 0

0.00.2

010

8

• Longer catalyst stripper (more stages)

8

Demolition Plan

Trac

king N

o. 0

0.00.2

010

99

Revamped Unit

Trac

king N

o. 0

0.00.2

010

1010

Revamped Unit

Trac

king N

o. 0

0.00.2

010

1111

Revamped Unit

Trac

king N

o. 0

0.00.2

010

1212

Layout of Revamped Unit

Trac

king N

o. 0

0.00.2

010

1313

Revamp Project Schedule

• Overall schedule – 14 months• Basic engineering – 10 weeks• Detail engineering started week 5

Trac

king N

o. 0

0.00.2

010

14

• Full project approval by week 15• All equipment delivered within 12 months• Turnaround duration 33 days (oil out to oil in)

14

Revamp Project Schedule

1 2 3 4 5 6 7 8 9 10 11 12 13 14

Basic Engineering Design Package

Prelim. Equipment Specifications

Project Cost Estimate

Months

Trac

king N

o. 0

0.00.2

010

1515

Owner Project Approval

Detail Engineering (Pre-Approval)

Detail Engineering (Post-Approval)

Procurement

Equipment Deliveries

Pre-Turnaround Construction

Construction Turnaround

Revamp Construction Issues

• Needed “Fast-Track” to finish by winter• Pre-turnaround construction

– External riser– Rough cut cyclone

• Turnaround construction

Trac

king N

o. 0

0.00.2

010

16

– Replaced reactor top head and secondary cyclones– Replaced stripper including new stages

• Duration 33 days – oil out to oil in

16

Pre and Post Revamp Data

Data at 990F ROT

100%

120%

140%

d Va

lues 8% Reduction

21% Increase

No Change 62% Reduction

Trac

king N

o. 0

0.00.2

010

1717

0%

20%

40%

60%

80%

SAOG Cat Gasoline MCCO DCO

% o

f Pre

turn

arou

nd

Vapor Quench

• Required sealing• 7% reduction in dry gas• Regenerator temperature dropped 16◌ ْF• Helped cool reactor overhead line & main column bottoms

Trac

king N

o. 0

0.00.2

010

1818

Additional Improvements

• Slurry gravity 18 API → 0 API• Liquid yield up 3.3 vol%• On-stream maintenance of slurry pumps and exchangers

dramatically reduced

Trac

king N

o. 0

0.00.2

010

19

• More slide valve ∆ P, smoother operation• Easier startup (hours versus 1½ days)

19

Unscheduled Outages Avoided

• Blockage around spent cat trash guard cleared by a controlled reversal pulse of the spent cat standpipe

• No prolonged outage/thermal cycle occurred until the regularly scheduled maintenance turnaround

Trac

king N

o. 0

0.00.2

010

2020

Turnaround Repairs Minimal

• Reactor secondary cyclone repair• Refractory damage in cross-over duct from rough-cut

cyclone to reactor• Typical coke deposits on reactor wall, roof of secondary

cyclones and on backside of secondary cyclone gas tube

Trac

king N

o. 0

0.00.2

010

21

cyclones and on backside of secondary cyclone gas tube• Minimal repairs to feed injectors, some injector tips starting

to show wear• Turnaround period and subsequent startup went smoothly

21

Feed Injector Target Bolt Inspection

Trac

king N

o. 0

0.00.2

010

2222

Feed Injector Orifice

Trac

king N

o. 0

0.00.2

010

2323

Feed Injector Tip Inspection

Trac

king N

o. 0

0.00.2

010

2424

Riser – Looking Down to Feed Injectors

Trac

king N

o. 0

0.00.2

010

2525

Stripper - Bottom Baffle and Steam Ring

Trac

king N

o. 0

0.00.2

010

2626

Rough-Cut Cyclone Dipleg Outlet

Trac

king N

o. 0

0.00.2

010

2727

Key Factors for On-Stream Reliability

• Proper design and installation of new components for anticipated throughput and operating conditions

• Maintaining throughput and operating conditions within the design parameters Proper design/specification and installation of refractory

Trac

king N

o. 0

0.00.2

010

28

• Proper design/specification, and installation of refractory materials and anchoring systems

• Minimizing thermal cycles by avoiding unnecessary outages

• Proper on-stream maintenance• Maintaining well-trained, experienced operating personnel

28

Conclusion

• A Model IV was easily revamped to significantly improve conversion and yield selectivity (21% more gasoline)

• A fast track project (14 months) was achieved utilizing licensor/contractor single point responsibilityRevamp downtime was reduced by maximizing pre

Trac

king N

o. 0

0.00.2

010

29

• Revamp downtime was reduced by maximizing pre-turnaround activities (33 days oil out to oil in)

• On-stream reliability was successfully achieved by making the proper process, mechanical, and operational improvements

• Minimizing unscheduled outages reduced the need for repairs to only routine maintenance during the next scheduled turnaround

29

Trac

king N

o. 0

0.00.2

010

30

Any Questions?Harvey McQuiston

[email protected]