Environmental and Social Due Diligence Report Project Number: 47083-004 October 2019 INDIA: Accelerating Infrastructure Investment Facility in India Tranche 3 Jindal Urban Waste Management (Guntur) Ltd Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance Company Limited and the Asian Development Bank.

Transcript of Accelerating Infrastructure Investment Facility in India - Asian ...

Environmental and Social Due Diligence Report

Project Number: 47083-004 October 2019

INDIA: Accelerating Infrastructure Investment

Facility in India – Tranche 3 Jindal Urban Waste Management (Guntur) Ltd

Prepared by India Infrastructure Finance Company Limited for the India Infrastructure Finance

Company Limited and the Asian Development Bank.

This environmental and social due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 1 JUWMGL

Environment and Social Safeguards Due-Diligence Report

Construction of 15 MW Municipal Solid Waste to Energy Processing Facility at Guntur in

the State of Andhra Pradesh, India

Sub Project Developer – Jindal Urban Waste Management (Guntur) Ltd

April 2019

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 2 JUWMGL

SUB PROJECT: 15 MW Waste-to-Energy (WtE) Project with construction and operation

of MSW processing facility for the obligated quantity of MSW during the concession

period on design, build, finance, operate and transfer (DBFOT) basis and setup of landfill

and disposal of the process remnants and residual inert matters at Guntur in the State of

Andhra Pradesh, India.

Jindal Urban Waste Management (Guntur) Limited

Environmental and Social Safeguards Due Diligence Report

(ESDDR)

Prepared by Dr. Rashmi Kadian

Assistant General Manager

(Environmental Specialist)

ESMU, IIFCL

Mr. Krupasindhu Guru

Assistant General Manager

(Social Specialist)

ESMU, IIFCL

Reviewed and Approved by Dr. S. S. Garg

Head, ESMU

IIFCL

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 3 JUWMGL

CONTENTS

PROJECT BACKGROUND ...................................................................................................................................... 6

1. PURPOSE OF THE REPORT ........................................................................................................................ 7

2. SUBPROJECT TITLE .................................................................................................................................... 7

3. SUBPROJECT SCOPE ................................................................................................................................... 7

4. PROJECT BACKGROUND ........................................................................................................................... 7

5. PROJECT DETAILS ....................................................................................................................................... 8

6. SUB-PROJECT LOCATION ........................................................................................................................ 10

7. DEBT COMPONENT OF THE PROJECT ................................................................................................ 11

8. STATUS OF REGULATORY PERMISSIONS AND APPROVALS FOR SETTING UP JUWMGL .. 11

9. ABOUT THE PROJECT ............................................................................................................................... 14

10. PROJECT LOCATION AND SCALE ......................................................................................................... 14

12. POLICY, LEGAL AND REGULATORY REQUIREMENT .................................................................... 17

13. COMPLIANCE OF JUWMGL WITH ESSF OF IIFCL ........................................................................... 17

16. DESCRIPTION OF THE ENVIRONMENT ............................................................................................... 20

17. VISIT TO SUB-PROJECT LOCATION ..................................................................................................... 21

18. ANTICIPATED ENVIRONMENTAL IMPACTS DURING CONSTRUCTION PHASE AND

MITIGATION MEASURES ......................................................................................................................... 21

21. ENVIRONMENT MANAGEMENT PLAN ................................................................................................ 27

22. INSTITUTIONAL FRAMEWORK FOR EMP IMPLEMENTATION ................................................... 31

23. CATEGORIZATION OF SUB-PROJECT ................................................................................................. 31

24. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST .................................. 31

25. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ....................................................... 31

26. GRIEVANCE REDRESSAL MECHANISM .............................................................................................. 32

28. CONCLUSIONS AND RECOMMENDATIONS ....................................................................................... 34

29. PURPOSE OF THE SOCIAL SAFEGUARDS DUE DILIGENCE: ......................................................... 37

30. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST: ................................. 37

31. OBJECTIVE OF SOCIAL SAFEGUARDS DUE DILIGENCE: .............................................................. 37

32. APPROACH AND METHODOLOGY: ...................................................................................................... 37

33. STAKE HOLDERS CONSULTATION: ..................................................................................................... 38

34. SOCIAL IMPACT OF THE PROJECT: ..................................................................................................... 38

34.1 IMPACT ON STRUCTURE: ........................................................................................................................ 38

34.2 LAND ACQUISITION IN THE PROJECT: ............................................................................................... 39

34.3 RESETTLEMENT IMPACT IN THE SUB-PROJECT ............................................................................. 39

34.4 IMPACT ON SCHEDULE TRIBE PEOPLE: ............................................................................................. 39

34.5 IMPACT ON COMMON PROPERTIES RESOURCES (CPR): .............................................................. 40

35. GRIEVANCE REDRESSAL MECHANISM: ............................................................................................. 40

36. LOCAL EMPLOYMENT: ............................................................................................................................ 40

37. LABOUR LICENSE OBTAINED BY THE SUBPROJECT DEVELOPER: .......................................... 40

38. DISCLOSURE: ............................................................................................................................................... 41

39. SITE VISIT OBSERVATION: ..................................................................................................................... 41

40. CONCLUSIONS AND RECOMMENDATIONS: ...................................................................................... 41

LIST OF TABLES

TABLE 1: SALIENT FEATURES OF JUWMGL………………………………………………………………..8

TABLE 2: MAIN UNITS OF JUWMGL…………………………………………………………………………..9

TABLE 3: AVAILABILITY OF PERMITS/APPROVALS FOR SETTING UP JUWMGL …………………11

TABLE 4: STATUS OF JUWMGL CONSTRUCTION …………………………………………………………14

TABLE 5: STATUTORY CLEARANCES/APPROVALS/PERMITS REQUIRED & PRESENT STATUS..18

TABLE 6: ASSESSMENT BASED ON LOCATION CRITERIA AS PER CPHEEO, GOVERNMENT OF

INDIA..……………………………………………………………………………………………………….21

TABLE 7: ENVIRONMENT MANAGEMENT PLAN IMPLEMENTATION MATRIX FOR

CONSTRUCTION STAGE………………………………………………………………………………...27

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 4 JUWMGL

TABLE 8: ENVIRONMENT MANAGEMENT PLAN IMPLEMENTATION MATRIX FOR OPERATION

STAGE……………………………………………………………………………………………………….29

LIST OF FIGURES

Figure 1: JUWMGL Plant location – MSW Processing facility (A) and landfill site (B) …………….16

ANNEXURES

Annexure I Government Order for Land Allocation to JUWMGL

Annexure II Labour License

Annexure III Group Personal Accident Insurance

Annexure IV Airports Authority of India No Objection Certificate

Annexure V Evacuation arrangement letter

Annexure VI Concession Agreement of JUWMGL (relevant clauses to Environmental

Management)

Annexure VII No Objection Certificate from Forest Department

Annexure VIII Consent for Establishment from State Pollution Control Board

Annexure IX Authorisation from State Pollution Control Board

Annexure X Letter regarding treated sewage water supply

Annexure XI Permission for ground water use

Annexure XII Provisional Fire No Objection Certificate

Annexure XIII Village Resolution for setting up of JUWMGL

Annexure XIV Director of Factories Approval

Annexure XV Fuel Storage Permission

Annexure XVI Buffer zone amendment letter

Annexure XVII Lease Agreement

Annexure XVIII ESIC Certificate

PHOTOPLATES

PHOTOPLATE I - SITE VISIT PHOTOGRAPHS

PHOTOPLATE II – STAKE HOLDERS CONSULTATION

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 5 JUWMGL

ABBREVIATIONS

AAI Airports Authority of India

APSPDCL Andhra Pradesh Southern Power Distribution Company Limited

CEMS Continuous Emission Monitoring System

CPHEEO Central Public Health and Environmental Engineering Organization

dB Decibel

DBFOT Design, Built, Finance Operate and Transfer

DPR Detailed Project Report

EIA Environmental Impact Assessment

EMP Environment Management Plan

EPC Engineering Procurement & Construction

ESDD Environmental and Social Due Diligence

ESDDR Environmental and Social Due Diligence Report

ESMU Environment and Social Management Unit

GMC Guntur Municipal Corporation

GoAP Government of Andhra Pradesh

GoI Government of India

GRM Grievance Redressal Mechanism

HSE Health Safety Environment

HVAC Heat Ventilation & Air Conditioning

IIFCL India Infrastructure Finance Company Limited

JUIL JITF Urban Infrastructure Limited

JUWMGL Jindal Urban Waste Management (Guntur) Limited

KLD Kilo Liters Per Day

LIE Lenders Independent Engineer

LoA Letter of Award

MDB Multilateral Development Bank

MoEFCC Ministry of Environment, Forests and Climate Change

MPR Monthly Progress Report

MSW Municipal Solid Waste

MRF Material Recovery Facility

NOC No Objection Certificate

NREDCAP New and Renewable Energy Development Corporation of Andhra Pradesh

Limited

PIAL Prohibited Investment Activities List

PIM Project Information Memorandum

PPE Personal Protective Equipment

RDF Refuse Derived Fuel

SEIAA State Level Environment Impact Assessment Authority

STP Sewage Treatment Plant

TOR Terms of Reference

TPD Ton per Day

ULB Urban Local Body

WtE Waste to Energy

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 6 JUWMGL

PROJECT BACKGROUND

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 7 JUWMGL

1. PURPOSE OF THE REPORT

1. This Environmental and Social Due Diligence Report (ESDDR) has been prepared by India

Infrastructure Finance Company Limited (IIFCL) in consultation with the Concessionaire, Jindal

Urban Waste Management (Guntur) Limited (JUWMGL) to assess the adequacy of the project with

the applicable safeguard compliance. The report has been prepared as per the

documents/information received from the concessionaire and on the basis of site visit observations.

The information given in the ESDDR is agreed and confirmed by the Concessionaire.

2. SUBPROJECT TITLE

2. 15 MW Waste-to-Energy (WtE) Project with construction and operation of Municipal Solid Waste

(MSW) processing facility for the obligated quantity of MSW during the concession period on

design, build, finance, operate and transfer (DBFOT) basis and setup of landfill and disposal of the

process remnants and residual inert matters.

3. SUBPROJECT SCOPE

3. The scope of the sub-project includes design, build, finance, operate and transfer (DBFOT) of

facilities and infrastructure for construction and operation of municipal waste processing facilities

and waste to energy processing facility for the obligated quantity of MSW during the concession

period. The scope of the project also includes setting up of landfill and disposal of process

remnants and residual inert matters.

4. PROJECT BACKGROUND

4. Government of Andhra Pradesh (GoAP), as part of Swachha Andhra Mission, proposes to set up

Waste to Energy (WtE) Plants at various locations in Andhra Pradesh and has identified beneficiary

Urban Local Bodies (participating ULBs) at each of these locations in Andhra Pradesh which are

expected to deliver MSW to the WtE processing facilities.

5. New and Renewable Energy Development Corporation of Andhra Pradesh Limited (NREDCAP)

was authorized by the participating Urban Local Bodies (ULBs) to run the bidding process for

selection of an entity to which the projects in each of the clusters may be awarded. Through a

competitive bidding process conducted by NREDCAP, M/s JITF Urban Infrastructure Limited

(JUIL) has been awarded the contract for implementation of the project in the cluster Guntur vide

Letter of Award (LoA) issued on 3rd

December, 2015. The project was awarded for capacity of 15

MW for Guntur at a power sale tariff of ₹ 6.165/unit. JUIL formed project special purpose vehicle

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 8 JUWMGL

(SPV) - Jindal Urban Waste Management (Guntur) Limited for undertaking the proposed project

development, operation and maintenance.

5. PROJECT DETAILS

6. The location of the proposed WtE facility is at Naidupeta, on Guntur – Chilakaluripeta Road in

Guntur District, 17 Kms from Guntur. The geographical location is approximately at 80° 18’ 0.08” E Latitude and 16° 14’ 9.07” N Longitude. The site elevation is 59 m from Mean Sea Level. Soil at the location is rocky and gravel. There is no habitation within the proposed project site.

7. The Concession Agreement for the sub-project was signed on 6th February, 2016 on design, build,

finance, operate and transfer (DBFOT) basis between JUWMGL and Guntur Municipal

Corporation as Lead ULB and eight other participating ULBs i.e. Vijayawada, Tenali,

Chilakaluripeta, Sattenapalli, Mangalagiri, Narasaraopeta, Ponnur and Tadepalle ULB. Thus, the

WtE project will process MSW received from nine ULBs in Guntur cluster.

8. As per concession agreement, Concessionaire shall develop the project facilities using technologies

adhering to Solid Waste Management Rules, 2016 which ensures:

Biodegradable and recyclable content of MSW are separated through suitable material

recovery facility;

A suitable technology is used for processing the bio-degradable and combustible

content of MSW;

A suitable technology is used for recovering and processing recyclable content of MSW;

Disposal of not more than 25% of received MSW in the landfill;

Disposal of not less than 2% of waste measured at landfill site.

9. MSW supply to the sub-project will be the responsibility of the participating ULBs. The evacuation

arrangement for power generated at WtE plant is the responsibility of Andhra Pradesh Southern

Power Distribution Company Limited (APSPDCL). APSPDCL has committed that the evacuation

arrangement will be completed before the plant is ready for synchronization.

10. The salient features of sub-project are given in the Table 1 below :

Table 1: Salient Features of JUWMGL

Village Kondaveedu

Mandal Edlapadu

District & State Guntur, Andhra Pradesh

Latitude 160 – 17’ N

Longitude 800 - 20’ E

Nearest Access Road NH-16 (2 km)

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 9 JUWMGL

11. The sub-project consists of the following main units:

Table 2: Main Units of JUWMGL

Nearest Railway Station Guntur -14.4 km

Nearest Airport Vijaywada – 67 km

Participation ULBs ULB Distance from

project site in km

MSW generation in Tonnes

per Day (TPD)

Guntur 15 320

Vijaywada 49.6 525.54

Tenali 37 68

Chilakaluripeta 31 62

Sattenapalli 37.4 45

Mangalagiri 37.4 52

Narasaraopeta 51 65

Ponnur 40 35

Tadepalli 44.7 30

Concessioning

Authority Municipal Corporation of Guntur

Concession period 25 Years

Tonnage per day Guntur Municipal Corporation and other 8 ULBs: 1200 MT

Source of Water Treated STP Water

Total Land Area of

Existing Plot

15.5 Acres for MSW processing facility & 35.74 acres for landfill site

Power Connectivity Grid Sub-station of APSPDCL at Vengalayapalem, 3 km

MSW Handling

Capacity

1650 TPD

Power Generation 15 MW

Technology used Refuse Derived Fuel (RDF) based power plant

Unit Details

MSW Receipt Weigh bridge - Two weigh bridges (1-input & 1-output) of minimum

40 tons weighing capacity will be installed on approach road from main

vehicle entry gate to the material recovery facility

Tipping Floor – After weighing, the trucks will proceed to the tipping

floor, where the driver unloads the waste in the designated dumping pit.

Material Recovery

Facility Bio Drying Section - There will be two dumping pits and 12 pits for

bio-drying arranged in two bays in a closed shed.

Material Segregation – after a stipulated period, semi decomposed

material will be fed to hopper for manual segregation to remove bigger

materials like boulders, stones, synthetic fabrics, mats, tyres, hard

boards, woods etc., to facilitate for the pre-processing unit to segregate

the waste effectively. Manual segregation will be followed by

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 10 JUWMGL

6. SUB-PROJECT LOCATION

12. The proposed project site is currently being utilised as dumping yard/landfill site by Guntur

Municipal Corporation. The site has proper road access and is near to existing highways for easy

movement of MSW trucks.

13. The entire facility is being developed on Government land. Guntur Municipal Corporation signed a

lease agreement with JUWMGL on 19.07.2018 for an area of 15.5 Acres for setting up a MSW

processing facility. Existing dump yard site having an area of 35.74 acres has been allotted to

JUWMGL by Municipal Corporation, Guntur vide letter dated 12.04.2017, for development and

operation for storage of residue as per Concession Agreement.

mechanical segregation.

Production of RDF - Drag conveyor will receive material from rake

carrier and distribute the same in the designated storage area for further

curing. Prepared RDF will be stored in the RDF storage area.

Main equipment of MRF are belt conveyor, rotary screen trommel,

ballistic separator, magnetic separator, shredder, rake carrier, drag

conveyor, hopper, de-stoner & cyclone separator, bagging machine,

crane, grab bucket etc.

Power Plant Boiler including auxiliaries-Two number of boilers.

Air pollution control system-Semi wet type of system is being

installed at JUWMGL for air pollution control

Ash handling and Disposal- for disposal of fly ash and bottom ash

Turbo generator – 1X15 MW

Condensing plant- Air cooled condenser

Balance of Plant

Water system - Treated water from STP will be used at JUWMGL.

Total requirement of water for the project is estimated as 324 m3/day as

per water balance.

Compressed air system - for ash handling system and for

instrumentation

Electrical system – including control & instrumentation system

Heat Ventilation and Air Conditioning (HVAC) - At various plant

facilities

Fire fighting – Including hydrant system, spray water system, high

velocity water spray system, medium velocity water spray system, hand

appliances system, sprinkler system

Effluent treatment – system for treating discharge from drain from

cooling tower, reject & back wash from water treatment section and

leachate treatment

Environment monitoring system - Continuous Emission Monitoring

System (CEMS) at stack

Sanitary Landfill - For disposal of waste from the MSW processing

facility.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 11 JUWMGL

7. DEBT COMPONENT OF THE PROJECT

14. The total cost of the project is estimated at ₹ 218.84 crore and is proposed to be financed with a

debt to equity ratio of 70:30. The total debt requirement for the project is ₹ 153.19 crore and the Equity is ₹ 65.65 crore. The Consortium led by Lead Lender IREDA is providing a loan of ₹ 109.42 crore and IIFCL has sanctioned a term loan of ₹ 43.77 crore (including Debt Service Reserve loan of Rs.1.92 Cr) under Direct Lending Scheme.

8. STATUS OF REGULATORY PERMISSIONS AND APPROVALS FOR SETTING UP

JUWMGL

Table 3: Availability of Permits/Approvals for setting up JUWMGL

S. No.

Key requirements Availability

Status

Remark

1. Concession Agreement Obtained Concession Agreement for setting up Waste to

Energy processing facility at Guntur, Andhra

Pradesh was signed on 6.2.2016 between Guntur

Municipal Corporation, Vijayvada Municipal

Corporation, Tenali Urban Local Body,

Chilakaluripeta Urban Local Body, Sattenapalli

Urban Local Body, Mangalagiri Urban Local Body,

Narsaraopeta Urban Local Body, Ponnur Urban

Local Body, Tadepalle Urban Local Body and

JUWMGL.

2. Power Purchase Agreement Obtained PPA between Andhra Pradesh Southern Power

Distribution Company Limited, Guntur of Andhra

Pradesh and JUWMGL has been signed on

6.02.2016.

3. Construction Power Agreement Obtained Construction Power Agreement under the Electricity

(Supply) Act 2003 has been signed between Andhra

Pradesh Southern Power Distribution Company

Limited and JUWMGL on 12.03.2018. Power

supply agreement is for supply during the

construction period.

4. Land Allotment / Lease Obtained Guntur Municipal Corporation signed a lease

agreement with JUWMGL on 19.07.2018 for an

area of 15.5 Acres for setting up a MSW

processing facility. Existing dump yard site

having an area of 35.74 acres has been allotted to

JUWMGL by Municipal Corporation, Guntur vide

letter dated 12.04.2017. Government order dated

14.11.2017 in this regard is enclosed as Annexure

I.

5. Labour License & Insurance Obtained Labour License has been granted to the subproject

under Sub Section 2 (d) and 4(2) of the Andhra

Pradesh (Issuance of Integrated Registration and

Furnishing of Combined Returns under various

Labour Laws by certain Establishments) Act, 2015

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 12 JUWMGL

The copies of the Certificate of Registration are

attached as Annexure II. Sample copy of insurance

taken by the main contractor is attached as

Annexure III.

6. Permission from Airport

Authority of India

Obtained NOC from Airport Authority of India has been

obtained JUWMGL vide letter dated 17.5.2016

(Annexure IV).

7. Evacuation Arrangement Obtained Southern Power Distribution Company of Andhra

Pradesh vide letter dated 11.10.2018 has informed

that the evacuation arrangement will be completed

before the plant is ready for synchronization

(Annexure V).

8. Boiler Drawing Approval Obtained Boilers Department, Government of Andhra Pradesh

approved the boiler drawings as per compliance of

Indian Boiler Regulations, 1950 vide letters dated

25.5.2018 and 29.5.2018.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 13 JUWMGL

DUE DILIGENCE ON ENVIRONMENTAL SAFEGUARDS

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 14 JUWMGL

9. ABOUT THE PROJECT

15. Government of Andhra Pradesh (GoAP), as part of Swachha Andhra Mission, proposes to set up Waste

to Energy (WtE) Plants at various locations in Andhra Pradesh and has identified beneficiary Urban

Local Bodies (participating ULBs) at each of these locations in Andhra Pradesh which are expected to

deliver MSW to the WtE processing facilities. The Participating ULBs would undertake development

and operation/maintenance of the proposed WtE processing facilities (projects) through Public-Private

Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT) basis.

16. M/s JITF Urban Infrastructure Limited (JUIL) has been awarded the contract for implementation of the

WtE project in Guntur cluster for capacity of 15 MW, at a power sale tariff of Rs.6.165/unit.

17. JUIL has formed project SPV viz. Jindal Urban Waste Management (Guntur) Limited for undertaking

the proposed project development, operation and maintenance for Guntur MSW management facility.

18. The scope of the sub-project includes construction and operation of MSW processing facility and waste

to energy processing facility and setting up of landfill for disposal of process remnants and residual inert

matters.

19. As per the Concessions Agreement, the processing technologies proposed at the sub-project should

ensure that the technologies used are appropriate as per SWM Rules, 2016.

20. The sub-project is expected to achieve commercial operation by September 2019. As per Lenders

Independent Engineer (LIE) report for quarter ending December 2018, the progress of the sub-project is

given in the table below:

Table 4: Status of JUWMGL Construction

Construction Activity Status

Boiler Structure Completed; Installation of boiler pressure parts to be completed by mid-Mar 2019

Air cooled condenser Civil works completed

Turbine generator building 90% completed

MSW receiving area 50% of civil works completed

Flue gas cleaning system 80% of RCC works completed mechanical work in progress

Water treatment plant Civil works commenced and foundation completed

Weigh bridge 60% works completed

Switch Yard 70% civil works completed

Leachate Treatment Plant Yet to commence and to be completed within three months

Switch Yard 70% civil works completed

Source: LIE Report, December 2018

10. PROJECT LOCATION AND SCALE

21. Guntur Waste to Energy Plant is proposed to be located in Kondaveedu Village, Edlapadu Mandal in

Guntur District. Land is allocated by Guntur Municipal Corporation (GMC) near Naidupeta dump yard

as per the terms of Concession Agreement. Site is connected to NH-16 by approach road.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 15 JUWMGL

22. The land allocated for the MSW processing facilities at the sub-project is about 15.5 acres. The lease

agreement for the land was signed on 19.07.2018 for a period of 25 years. Guntur Municipal

Corporation has handed over the land to JUWMGL for developing the sub-project. The area is being

used for construction and development of integrated MSW processing facility comprising material

recovery facility and power plant with auxiliaries, water treatment plant, administrative and amenities

blocks and common facilities etc. in addition this land, an area of 35.74 acres has been allotted to

JUWMGL by Guntur Municipal Corporation vide letter dated 12.4.2017 for landfill site. The land

area has been leased and allotted as per terms of Concession Agreement signed between GMC and

JUWMGL on 6.02.2016. The land allocated for the sub-project is an existing dump yard of GMC.

Location of sub-project along with location in Google maps is given in Figure 1.

11. APPROACH TO THE ENVIRONMENT SAFEGUARDS DUE-DILIGENCE REPORT

(EDDR)

23. As part of environmental due diligence (EDD), the review of available documents/information has

been done to assess compliance of the sub-project with respect to statutory regulations related to

environmental safeguards. Projects financed by IIFCL which are posed for MDB’s line of credit,

are required to undergo to an environmental and social due diligence process utilizing the

procedures described in the ESSF to ensure sustainable project investment. Categorization of the

sub-project with respect to ADB and IIFCL ESSF forms part of the ESDD. EDD also covers and

assesses the process of identifying environmental impacts and implementation of environmental

management measures; contractual obligations for Health Safety Environment (HSE) measures;

public consultations and information disclosure; implementation of HSE measures; institutional

arrangement for implementing environmental measures; site visit observations & photographs. The

EDDR concludes the outcome along with recommendations for the sub-project.

24. The following documents were referred in order to prepare Environmental Safeguards Due-

Diligence Report:

Project Information Memorandum (PIM)

Detailed Project Report

Lender’s Independent Engineer’s Report for quarter ending December 2018 Project Statutory Approvals

Project HSE Documents

Concession Agreement

Power Purchase Agreement

Land allotment/lease agreement

Labour License

EPC Work Orders/Contract Documents

Sub-project layouts

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 16 JUWMGL

Figure 1: JUWMGL Plant Location – MSW Processing Facility (A) and Landfill Site (B)

A

B

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 17 JUWMGL

12. POLICY, LEGAL AND REGULATORY REQUIREMENT

25. This section briefly describes the policy, legal and regulatory requirements for implementing a

waste to energy project. MSW management requires assessment for applicability of Solid Waste

Management Rules, 2016; EIA Notification, 2006; Central Pollution Control Board Guidelines on

the Provision of Buffer Zones around Waste Processing and Disposal Facilities, 2017; Indian

Electricity Act 2003; Forest (conservation) Act, 1980; Wildlife (Protection) Act, 1972;

Water (Prevention and Control of Pollution) Act, 1974; Air (Prevention and Control of

Pollution) Act, 1981.

13. COMPLIANCE OF JUWMGL WITH ESSF OF IIFCL

26. The Environmental and Social Safeguard Framework (ESSF) provides the enabling mechanism to

IIFCL to deliver its policy objectives and applies to projects funded by IIFCL throughout the

project cycle. The ESSF defines procedures, roles, and responsibilities, at various project

milestones for managing the adverse environmental impacts.

27. The sub-project does not require obtaining environmental clearance as per Government of India’s GOI’s screening criteria for infrastructure development projects. Such projects do not require an environmental impact assessment. The environmental assessment of the site for JUWMGL was

conducted by the sub-project developer as part of the Prefeasibility study and Detailed Project

Report. On the basis of information provided in sub-project documents including prefeasibility and

detailed projects reports and site visit observations, an environmental examination was conducted

and description of the sub-project environment has been included in Section 16 of the ESDDR and

anticipated environmental impacts during construction and operation phase of JUWMGL have been

elaborated in Section 18 and 19 of the ESDDR. Appropriate planning instruments were developed

for the sub-project and Environmental Management Plans (EMP) was proposed in the DPR of

JUWMGL. Also, the Concession Agreement (CA) signed by JUWMGL has relevant clauses

related to EMP & environmental monitoring. The relevant clauses are, clause number 5.3

Environmental Compliance and clause 18 Safety and further details related to environmental

management and monitoring are available in the Schedules of CA. The relevant pages of the CA

are attached as Annexure VI. The effectiveness of the EMP implementation and monitoring plans

is elaborated in Section 21 of the ESDDR.

28. The sub-project is compliant to Government of India regulations and has adequate EMP

implementation on site. Therefore, it can be concluded that JUWMGL is compliant to the

requirements of IIFCL’s ESSF.

14. STATUS OF REGULATORY CLEARANCES

29. It is required that the sub-project meets the requirements of appropriate Indian legislations by

considering obligations and guidelines of regulatory authorities. The sub-project should have

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 18 JUWMGL

necessary national and local clearances as well as permits and approvals for project implementation

and suitable environmental management plan should be applied. The statutory clearances related to

environmental aspects and to be obtained from regulatory authorities as part of the sub-project

development, were assessed and current status of availability of such clearances are given in Table

5.

Table 5: Statutory Clearances/Approvals/Permits required and present status

Clearance Required Statutory Authority Status Remarks

Environmental Clearance

Ministry of Environment,

Forests and Climate

Change (MoEFCC),

New Delhi

Not

Applicable

Not Applicable as power plants

upto 15 MW based on non-

hazardous municipal waste and

using auxiliary fuel such as coal,

lignite and petroleum products upto

15% are exempted from EIA

requirements. Clarification from

MoEFCC was issued to Ministry of

Urban Development vide DO letter

dated 3.07.2017 that when WtE

plants upto 15 MW are proposed on

existing landfill site they do not

attract the provisions of EIA

Notification, 2006.

Forest Clearance

Ministry of Environment,

Forests and Climate

Change,

New Delhi

Not

Applicable

The sub-project is not located in

forest area. The sub-project is along

the boundary of Kondaveedu

Reserve Forest, therefore, sub-

project developer has taken No

Objection Certificate from Forest

Department, Guntur Division,

Andhra Pradesh dated 3.10.2016

(Annexure VII).

The Wildlife Protection Act,

1972 & Biological Diversity

Act, 2002

Ministry of Environment,

Forests and Climate

Change,

New Delhi; National

Biodiversity Authority

Not

Applicable

Not required as project site does

not lie within or in close vicinity to

any National Park, Wild Life

Sanctuary or biodiversity rich area

as informed by project developer.

Consent for Establishment

Project Facility

Andhra Pradesh Pollution

Control Board

Available Consent for Establishment from the

State Pollution Control Board

under Section 25 of Water

(Pollution & Control of Pollution)

Act, 1974 and under Section 21 of

Air (Pollution & Control of

Pollution) Act, 1981 has been

granted to the sub-project vide

letter dated 20.03.2017 (Annexure

VIII).

Authorization under Solid

Waste Management Rules,

2016

Andhra Pradesh Pollution

Control Board

Available

Andhra Pradesh Pollution Control

Board has authorised JUWMGL for

municipal solid waste based WtE

plant of capacity of 15 MW power

generation and to produce other by-

products vide letter dated

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 19 JUWMGL

30. Sub-project developer has informed that JUWMGL applied for approval of Terms of Reference for

taking up Environmental Impact Assessment (EIA) study for the project in 12.02.2018 to State

Level Environment Impact Assessment Authority (SEIAA) for environment clearance alongwith

other projects of JUIL awarded in the State of Andhra Pradesh. For JUIL’s sub-project located in

Vishakhapatnam District of Andhra Pradesh, SEIAA passed directive that it may not require

environmental clearance since it is only 15 MW capacity. Developer has informed that on the basis

of this decision by SEIAA and discussions of the sub-project developer with the Authorities, the

application for TOR was withdrawn for JUWMGL. Therefore, no EIA study was undertaken by the

sub-project developer for JUWMGL. This status is reflected on the MoEFCC website too.

04.05.2018 (Annexure IX).

Water Supply Permission

Municipal Corporation

Guntur

Available

Guntur Municipal Corporation has

granted assurance for 500 KLD

sewage treated water supply to

JUWMGL plant from nearest

sewage treatment plant at Etukur

whenever the plant comes into

operation vide letter dated

16.11.2016 (Annexure X).

Ground Water Permissions Andhra Pradesh Ground

Water and Water Audit

Department

Available Andhra Pradesh Ground Water

Department has granted permission

to JUWMGL for drawing water

from four bore wells at sub-project

location on 14.02.2017 (Annexure

XI).

Fire No Objection

Certificate

Andhra Pradesh State

Disaster Response and

Fire Services Department

Provisional

NOC

Available

Provisional No Objection

Certificate is issued to JUWMGL

on 07.05.2018 (Annexure XII).

Formal approval will be

obtained/issued before the plant is

operational.

Village Resolution Kondaveedu Village

Panchayat

Available Kondaveedu Village has passed

resolution for setting up of WtE

plant 2.10.2017 & 31.10.2017

(Annexure XIII).

Factories Act, 1948 Factories Department,

Government of Andhra

Pradesh

Available The factories plan has been

approved vide letter dated

25.07.2017 by Director of

Factories, Government of Andhra

Pradesh (Annexure XIV).

No Objection Certificate for

Height Permission

Airports Authority of

India

Available NOC has been granted by AAI on

17.05.2016 for height clearance

(Annexure IV).

Fuel Storage Permission Controller of Explosives

(CCoE), Government of

Andhra Pradesh

Available

Permission for fuel storage was

under process during site visit to

the sub-project. Fuel storage

permission has been granted vide

letter dated 27.05.2019 (Annexure

XV).

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 20 JUWMGL

15. ALTERNATIVE ANALYSIS

31. JUIL was selected through a bidding process for development of WtE processing facilities in

clusters in Andhra Pradesh by New and Renewable Energy Development Corporation of Andhra

Pradesh Limited (NREDCAP). The site allocation was done by the ULB, therefore no site

alternatives were explored by JUWMGL. The site allocated for the sub-project are existing dump

yards used by the ULB since the year 2009.

16. DESCRIPTION OF THE ENVIRONMENT

32. The project area available for WtE facility is about 15.5 acres and 35.74 acres is available for

development of scientific landfill at Kondaveedu. The project site is situated on a highly undulating

terrain and on the down hills of two hillocks which form the western and northern boundaries. The

western boundary and some portions of northern boundary of the proposed site are along with the

boundary of Kondaveedu reserve forest.

33. The proposed project site for SLF facility is unevenly distributed. The proposed area has been

demarcated with cement poles and fencing from the GMC area & the private lands.

34. The project area comes under the jurisdiction of newly formed capital city, Amaravati of Andhra

Pradesh. The site is having red and brownish clayey sandy soil along with pebbles and boulders.

The proposed project area is situated 2.5 kilometres away from the National Highway 16, which is

connecting Guntur and Chennai. The project area is well connected by road with Vijayawada,

Amaravati and Chennai. The project is situated at a distance 52 km from Vijayawada and 45 km

from Amaravati. Guntur railway station is the major railway station which is 14 km from the

project site. Nearest airport is at Vijayawada and is about 67 km whereas Machilipatnam sea port is

100 km away from the project site.

35. The project area is situated on an undulating terrain and on the down hills of hillocks which forms

the boundary of the northern, western side of the proposed site, whereas eastern side is vacant land

and the proposed WtE site is the southern boundary. The land is sloping from northern to southern

directions. Some portion of the northern part having elevation is about 70 m, whereas southern part

of the site is varying from 56 - 57 m. The elevation of the western boundary of the proposed site is

almost flat and elevation varies from 59 – 60 m.

36. Waste dumping in the proposed project area is in practice since 2009. About 300 TPD of mixed

solid waste is being dumped in the project area. Legacy dump is available in the land allocated for

landfill.

37. The site evaluation as per location criteria specified in the Manual on Municipal Solid Waste

Management, Central Public Health and Environmental Engineering Organisation (CPHEEO),

Government of India, 2016, is given below:

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 21 JUWMGL

Table 6: Assessment based on location criteria as per CPHEEO, Government of India

17. VISIT TO SUB-PROJECT LOCATION

38. As part of the preparation of the ESDDR, the sub-project was visited by Head-Environment &

Social Management Unit (ESMU), Environmental and Social Safeguard Specialists of IIFCL on

15th January 2019 for field verification of environmental safeguards. Consultation with the Project

Head and Health & Safety team was also done regarding safeguards implementation during the site

visit. The sub-project is currently in construction phase. The site visit photographs are given in

Photo Plate-I.

18. ANTICIPATED ENVIRONMENTAL IMPACTS DURING CONSTRUCTION PHASE AND

MITIGATION MEASURES

39. The proposed WtE project is not located in forest land or in close vicinity of any wild life

sanctuary/national park. The sub project is not located in eco-sensitive zones declared by the

Government. The impacts during construction phase and mitigation status thereon are elaborated

below:

40. Land Use: At present, the land allotted for the project (approx. 55 acres) is an existing landfill

site/dump yard being used by GMC since the year 2009. The area where the WtE facility is being

constructed was handed over to the sub-project developer by GMC after clearing. Hence the land

use pattern of the area is not changing due to coming up of the project. However, some temporary

Criteria CPHEEO Manual

Requirement

Description of the Site

Lake/Pond 200 m away from Lake/Pond One canal passes about 990 m

away

River 100 m away from the River Canal 990 m away

Highway or railway line 200 m away from highway NH 16, 2.2 km away

Public parks 300 m away from public parks No parks in close vicinity

Flood prone area No land fill in a 100 years flood

prone area

Sub-project located in hilly terrain

Habitation 200 m away from habitation

area

No habitations observed within

200 m from the site

Critical habitat area No landfill within critical habitat

area.

No critical habitat area

Airports No landfill within 20 km of

airports

Vijayawada airport is at a distance

of 67 km from site

Coastal regulatory zone Not in sight of project Not in vicinity of project location

Buffer Zone (No

development zone)

500 m for facilities dealing with

100 TPD or more of MSW

No development within buffer

zone

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 22 JUWMGL

disturbances due to construction activity are anticipated during construction phase. The impacts are

temporary and will go after the construction activity is over. The construction activity is scheduled

to be completed by September 2019. Thus, the impact on land use during the construction work is

temporary and not significant in nature. After construction of the plant the aesthetics of the area

will improve as compared to the present scenario.

41. Air Quality: Construction activities involve excavation for construction of various facilities/units

of the sub-project. This will result in limited fugitive emissions at site. Spraying of water during

construction will reduce the dust fall to a great extent. The mitigation measures adopted by project

proponent to avoid air pollution include management of vehicular movement to avoid traffic

congestions, mechanical water sprinkling for suppression of dust, vehicle to comply with valid

PUC certificate.

42. Noise Levels: During construction phase, the sources of noise pollution will primarily be limited to

movement of vehicles transporting construction material and equipment to the site. The project site,

however, is not in closed vicinity to habitation area. Since the movement of traffic is not very

significant and away from settlement areas of villages; hence the villagers will not be affected due

to increased noise level. Use of low noise generating equipment and restriction of construction

activity for limited periods will further reduce the disturbance from noise pollution. JUWMGL to

procure machinery / construction equipment in accordance to the specifications confirming to

source noise levels.

43. Water Quality: The existing dump yard must be causing some impact on the ground water quality

in absence of any scientific method to curtail the water pollution. The water for construction is

being taken from the four permitted operational bore wells in the project area.

44. Soil: The excavation work involved in the project is limited to construction of foundation for

various units of the plant. The soil is envisaged to be used during construction activities. During

site visit, it was observed that soil was stockpiled on one side and used for making ramps etc.

45. Flora: The construction work may cause loss of vegetation. The sub-project is not located in forest

area or protected area, therefore minimum impact is anticipated on the flora. The site used by the

sub-project is already an existing dump yard with minimum vegetation. Project Head during site

visit informed IIFCL staff that total 972 saplings have been planted at the site and another 1000 are

planned.

46. Fauna: The existing land use for the sub-project site is existing dump yard. No forest areas are

falling in proposed project area and the sub-project is not part of any eco-sensitive areas like

national park or sanctuaries thereby no presence of rare and endangered species is anticipated.

However, stray cattle are anticipated to be around dump yard. Currently the proposed area has been

demarcated with cement poles and fencing from the GMC area and private lands.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 23 JUWMGL

47. Health and Safety: Developer has informed that about 400 labour are engaged during construction

phase. Civil contractor has taken private land of about 1 acre area for labour camp in the vicinity of

the sub-project location. Around 260 labour are housed in the labour camp. Other 140 labour for

boiler mechanical engineering works are staying in dormitories in two warehouses rented for the

purpose. The labours have been provided with toilet facilities, water supply through tankers and

electricity. Toilet facilities are also constructed at the project site for labour. A doctor is available at

the site every day for 2 hours for the labour. First aid kits are available at the site. Labour is

provided with personal protective equipment (PPE) while undertaking work at the site. Developer

has informed that job safety analysis, tool box talk, induction training and job specific trainings are

provided to staff. HSE related matters are being reported in the MPR of the sub-project. The safety

training conducted in the month of December 2018 are given below for sample purpose:

Tool Box Talk meetings conducted – 29; attended by 507 workers

Safety Induction Trainings – 10; attended by 113 workers

Job Specific Trainings conducted – 04; attended by 69 workers

48. Clause 24 of the work orders at JUWMGL are for safety/hygiene. In accordance to this clause the

contractor has to provide PPE to labour and ensure safety/hygiene for the labour. The clause also

mentions regarding arrangement of training programmes to be conducted before engaging any

worker on the job. There are penalty on the contractor for not complying safety norms at site.

49. General health check-ups are conducted regularly for all JUWMGL employees and contract

employees. Health register is maintained and recorded regularly for all employees. Medical camp

and health awareness campaign are organized in association with local hospitals periodically.

50. Cultural Sites: As informed by project developer, no archaeological, heritage, historical or

culturally important sites are located close to the proposed sub-project.

51. The project is being live monitored from Chief Minister, Andhra Pradesh Office.

52. The records of HSE related details are maintained in the Monthly Progress Reports of the sub-

project.

53. Quarterly reports on compliance of conditions of Authorization under Solid Waste Management

Rules, 2016 and Consent for Establishment of the facility are being submitted to the Andhra

Pradesh Pollution Control Board.

19. ANTICIPATED ENVIRONMENTAL IMPACTS DURING OPERATION PHASE AND

MITIGATION MEASURES

54. Land Use & Soil: Changes in land use pattern are envisaged once the sub-project is under

operation. At present area is a dump site for GMC. The WtE facility once operational will not

impact the land use pattern. The landfill will be used for disposal of process rejects and inerts

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 24 JUWMGL

generated from WtE facility of JUWMGL. The process rejects include the bottom ash and residual

material generated during WtE process. The proposed landfill is designed for a period of 25 years

referring the terms and conditions mentioned in the concessionaire agreement and consent for

establishment order. The design concept involves appropriate procedure and safety considerations.

Liner and cover system has been proposed for the landfill site. Plantation to be done in sufficient

density to minimize soil erosion.

55. Air and Noise Quality: Air pollution is anticipated during operational phase of the WtE facility.

Unloading and processing of waste is not anticipated to generate dust and odour, since these

activities are carried out in covered areas. The air pollution control system shall be installed along

with the commissioning of the facility and shall comply with norms for controlling air pollution.

Emission control system is proposed at the WtE plant, the system will consist essentially of the

following major components:

Flue gas system inlet duct

Reactor and product recirculation system

Bag house filter

Sorbent handling system

End product handling system

Process water system

Auxiliary systems (compressed air system, nitrogen inerting system)

Fugitive emissions will be controlled by the following mitigation options during operation of the

WtE facility:

Maintaining and/or re-establishment of a grass cover on area where there is no ongoing

Activity

Frequent watering of unsealed roads and stockpile area- cover material

Blacktop of the roads as and when they are settled and ready for the same

Repair, relaying of blacktop roads from the landfill area to the main road

Using dust control sprays during loading and unloading of wastes

Ceasing dust generating activities during high wind times

Minimizing working distances for internal transport of wastes

Periodical monitoring of ambient air quality for all relevant parameters

Odour control by rapid stabilization and disposal of wastes

Outlet emissions are proposed to be monitored through sophisticated continuous emission

measuring instruments. The system will measure the following parameters - CO2, HCI, NO, NOx,

O2, SOx and SPM. Gas temperature and the pressure are also proposed to be analysed continuously

to regulate the dosing of sorbents. However, all other parameters would be monitored on weekly

basis. The control of the dioxins/furans and heavy metals – especially mercury – is performed by

means of adsorption on pulverized activated carbon. The activated carbon is injected into the

reactor together with the slaked lime.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 25 JUWMGL

Excessive noise shall be avoided by providing noise enclosure where reasonably practical. Hearing

protection is proposed to be worn by labour while working in high noise areas exceeding 85 dB.

The following strategies are proposed to be adopted to further minimize the noise levels:

Maintaining the site machinery in good operating condition

Regular maintenance of systems and installation of noise control equipment

wherever required

Development of green belt all around the site

Periodical monitoring of noise levels

56. Water Quality: Water quality including ground water is anticipated to be impacted during

operation phase of the sub-project if mitigation measures are not adopted. At the WtE processing

facility, leachate collection system and treatment facility is proposed. A concrete platform is

proposed to be constructed to prevent ground water contamination due to leachate. Leachate

generated shall be stored in an underground leachate tank and used for spraying on windrows to

maintain moisture level.

57. Leachate Treatment Process: Leachate treatment process has been designed for JUWMGL.

About 120 KL of leachate will be collected in collection tank through a network of perforated pipes

laid in the plant. About 35 KL of leachate will be used for ash quenching from intermittent

collection tank. The leachate treatment shall be carried out through various processes in tanks at the

facility for treatment and disposal. The process will include passing the leachate through

equalization tank followed by flash mixing, flocculation and anaerobic treatment. Further, the

leachate will be treated in aeration tanks followed by secondary clarification and ultra-filtration.

The sludge will be converted to cakes after thickening and belt press process.

58. Flora: The WtE plant in operation phase is not anticipated to have impact on vegetation in the area.

As per conditions of Forest Department NOC, 7.5 meters from the reserve forest land side is

proposed to be left. It is proposed by the project developer to develop a vegetative cover in a strip

of minimum 20 m width around the site boundary of scientific landfill facility. Greenbelts shall be

developed all around the boundary of the facility for MSW based on waste to energy plant. Project

developer has informed that about 33% of the area will be developed as green belt at project site.

Green belt will create overall positive impact on the aesthetics of the site.

59. Fauna: Construction of high level wall is proposed towards the reserve forest side of the sub-

project. This will keep the animals away.

60. Health and Safety: Risk analysis has been done at the project and safety measures proposed at the

site for staff. JUWMGL has listed activities which require risk assessment and work procedures.

Site personnel are to attend a site induction including briefing on the site rules and regulations. All

workers shall be equipped with proper PPE maintained in good condition. Hearing protectors shall

be worn in areas where noise levels exceed 85 dB. Respirators to be worn in contaminated

atmospheres. Equipment shall be used by trained personnel only.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 26 JUWMGL

20. ENVIRONMENTAL SENSITIVITY AND DUE DILIGENCE

61. The environmental sensitivity of the 15 MW WtE processing facility and landfill site has been

assessed by reviewing the project related documents like Detailed Project Report (DPR), various

permits/NOCs, health and safety related information, supplemented by field visit and consultation

with the concessionaire. The environmental sensitivity assessment is given below:

The WtE processing plant along with landfill is being developed on an existing dump yard of

Guntur Municipal Corporation (GMC). GMC has leased out 15.5 acres for MSW processing

facility and allotted 35.74 acres for landfill site.

The entire facility is being developed on government land.

No notified forest area is getting affected due to the sub-project. However, the sub-project is

along the boundary of Kondaveedu Reserve Forest, therefore, sub-project developer has

taken NOC from Forest Department, Guntur Division, Andhra Pradesh.

The sub-project sites are not located in any protected area like wildlife sanctuary / national

park or in close proximity of any eco-sensitive area.

During site visit and as per discussions with the sub-project staff, it was informed that no

wild animals are sighted in and around the sub-project area. There is no loss of bio-diversity

as there are no fauna species within the project area. As regards to the vicinity to reserve

forest certain mitigation measures are proposed by the sub-project.

As informed by the concessionaire, there are no important cultural / heritage sites are getting

affected due to the sub-project.

Labour working at the sites staying in a labour camp about 1 km from the sub-project site.

The area is leased land private land. Labour for boiler mechanical engineering works are

staying in dormitories in two warehouses rented for the purpose.

The impacts of the sub-project are manageable and temporary in nature. EMP is proposed to

mitigate and manage the environmental impacts at the sub-project in consultation with the

sub-project developer.

It is the responsibility of contractor to maintain safety and well-being of labour at site. Job

safety analysis is being done at the sub-project. Tool box talks, induction trainings and job

specific training are being provided to the work force.

Water is being sourced from authorized bore wells at site during construction phase. Treated

sewage water will be supplied through pipe lines during operation phase.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 27 JUWMGL

21. ENVIRONMENT MANAGEMENT PLAN

62. A consolidated EMP presented in this section which is being implemented at JUWMGL. The EMPs

proposed in planning documents as mentioned in Section 13 of the ESDDR is compiled in this section

and their effectiveness is assessed vis-à-vis the actual activities undertaken by the developer considering

environmental impacts. The major components of the EMP include:

Mitigation of potentially adverse impacts;

Monitoring during the project implementation and operation; and,

Institutional arrangements.

63. The environmental issues and suggested mitigation measures with institutional arrangements for

implementation and their compliance status are given in Table 7 and 8. The EMP and monitoring

plan is being implemented during construction phase. The actual status of implementation is

provided in Table 7. The assessment of implementation of EMP was checked through records

being maintained at JUWMGL and ground check during site visit. The EMPs are found to be

adequate and effective during the construction phase of JUWMGL. EHS Committee is formed at

the sub-project, which includes members from the Contractor’s side also. The Committee oversees the implementation of safety and management measures at the site.

Table 7: Environment Management Plan Implementation Matrix for Construction Stage

Potential Impacts Mitigation Measure Monitoring of mitigation Responsibility Status of

Implementation Air Quality Spraying water when

necessary to suppress

dust and fugitive

emissions;

All vehicles to

possess a valid

pollution control

certificate;

Periodic monitoring of

ambient air quality for

all relevant parameters

in the plant area

JUWMGL Water is being

sprinkled at site to

suppress dust and

fugitive emissions.

Developer has

confirmed during site

visit that all vehicles

possess a valid

pollution control

certificate. Air quality

monitoring is being

done at seven

locations in and

around project site

and the parameters

are found to be

within prescribed

limits.

Flora and Fauna Minimize removal of

vegetation

Green belts to be

developed around

boundary of

periphery

Prohibit employees

7.5 meters from the

reserve forest land side

to be left

Record of plantations

to be maintained at site

Fencing shall be done

around the entire

JUWMGL Fencing has been

done and is being

maintained at the

sub-project.

Green belt is being

developed in and

around periphery of

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 28 JUWMGL

from poaching and

cutting of trees for

firewood.

periphery of the

facility to keep stray

animals away

Record of saplings

planted and survival

rate to be kept

Employees to be

supervised and

sensitized towards

cutting of trees and

poaching

JUWMGL. Records

are maintained at

site. Monthly EHS reports

are maintained at

site.

Surface water

quality Stockpiling of earth

fill shall be avoided

unless covered

during the monsoon

season

Prioritize re-use of

excess spoils and

materials in the

construction works.

Install temporary silt

traps or

sedimentation basins

along the drainage

leading to the water

bodies

Disposal of any

wastes generated by

construction

activities shall be

done in designated

sites

Surface quality

monitoring to be done

JUWMGL Surface water quality

monitoring is done at

four locations in and

around the project

site.

Ground water quality

monitoring is being

done at six locations. The water quality

parameters are found

to be within limits,

except that water is

alkaline at few

locations.

Noise Levels Construction

activities with the

greatest potential to

generate noise shall

be conducted during

periods of the day

which will result in

least disturbance;

Restriction of

vehicular movement

at a speed limit for

minimum noise

Procuring

machinery/

construction

equipment in

accordance to the

specifications

confirming to source

noise levels

Maintain maximum

sound levels not

Noise quality

monitoring to be done

JUWMGL Noise quality

monitoring is done at

the site and noise levels

are found to be within

limits.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 29 JUWMGL

Table 8: Environment Management Plan Implementation Matrix for Operation Stage

exceeding 80

decibels (dbA) when

measured at a

distance

Buffer zone around

facility Buffer zone area to

be left as per layout

approval of State

Pollution Control

Board

Green belt buffer to

be maintained in

view of public safety

Plantation records to be

maintained

JUWMGL Buffer zone will be

maintained as per AP

Pollution Control

Board directive to

the sub-project

attached as

Annexure XVI.

Green belt is being

developed in and

around periphery of

JUWMGL. Records

are maintained at

site.

Health & Safety Labour shall be

provided with PPE

First aid kits and

doctor shall be

available at site

Job safety analysis,

tool box talk,

induction training

and job specific

trainings shall be

provided to staff

Continuous inspection

shall be done at site by

Contractor

HSE related matters

are shall be reported on

monthly basis

Sub-contractor;

JUWMGL Monthly EHS reports

are maintained at

site.

Tool box talks, safety

induction trainings,

mass trainings, job

specific trainings,

equipment

inspection, accident

reports etc are

reported in monthly

EHS reports.

First aid kits are

maintained at site

and a doctor visits

site every alternate

day. The doctor is

available round the

clock on call. General health

checkups are done

for JUWMGL

employees and

contractors staff at

the sub-project.

Potential Impacts Mitigation Measure Monitoring of mitigation Responsibility

Air Quality

Due to emissions

from vehicles

transporting MSW

from ULBs

Flue gas emissions

from WtE facility

All vehicles to possess a valid

pollution control certificate;

Maintaining and/or re-

establishment of a grass cover on

area where there is no on-going

activity

The approach and internal roads

Periodic monitoring of

ambient air quality for

all relevant parameters

in the plant area

Continuous emission

monitoring of outlet

emissions

ULBs for vehicles

transporting waste

JUWMGL

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 30 JUWMGL

shall be concreted or paved to

avoid dust generation due to

movement of vehicles

Using dust control sprays during

loading and unloading of wastes

Air Pollution Control system as

defined in the DPR of the sub-

project (as given in para 51 of

ESDDR)

Green belt shall be

developed all along the

boundary and vacant

spaces in not less than

33% of the total area

with indigenous species

Noise Quality Site machinery shall be

maintained in good operating

condition

Regular maintenance of systems

and installation of noise control

equipment wherever required

Development of green belt all

around the site

Periodic monitoring of

noise levels

JUWMGL

Odour problem due to

MSW Waste to be transported in

covered vehicles

Unloading as well as processing

of the waste to be carried out

under covered areas.

Odour control by rapid

stabilization and disposal of

wastes with daily cover

placement

Odour nuisance at down

wind direction on the

boundary of processing

plant shall be checked

regularly

Records to be

maintained

ULB for transportation

of waste

JUWMGL

Water consumption &

Quality Leachate treatment plan shall

include leachate collection and

treatment system including of :

influent leachate collection tank;

bar screens; oil & grease

chambers; anaerobic reactor;

secondary clarifier; aeration

tanks; carbon filter; ultra-

filtration; sludge thickener; belt

press etc.

Treated leachate shall be recycled

or utilized after meeting

standards as specified by

Pollution Control Board

Water from Cooling systems will

be neutralized in the neutralized

pit and utilized

Surface water quality

and treated leachate

quality monitoring shall

be done both at WtE

facility and landfill site

Ground water quality to

be monitored within 50

m of periphery covering

different seasons

Water consumption

records to be kept

JUWMGL

Buffer zone around

facility Buffer zone area to be left as per

layout approval of State Pollution

Control Board

Green belt buffer to be

maintained in view of public

safety

Green belt shall be

developed all along the

boundary and vacant

spaces in not less than

33% of the total area

JUWMGL

Health & Safety of

workers Good housekeeping to be

maintained at the plant

Tool box talks, induction

trainings shall be conducted

Workers shall be provided with

Training and health

records to be maintained

at site

Accident/incident

reports to be maintained

JUWMGL

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 31 JUWMGL

22. INSTITUTIONAL FRAMEWORK FOR EMP IMPLEMENTATION

64. JUWMGL has adequate institutional arrangement to oversee the implementation of health, safety &

environment (HSE) related aspects at the sub-project. The Senior Engineer (Safety) reports to Assistant

Manager (HSE) who directly reports to the President Projects. The EMP implementation during the

construction stage shall primarily be the responsibility of the contractor which will be constantly

monitored by the project team of JUWMGL. The project team of JUWMGL consists of managers

supported by engineers and operators. AM (HSE) and Senior Engineer (Safety) are responsible for

project execution and shall be responsible for environment management, monitoring health and safety

issues, etc.

23. CATEGORIZATION OF SUB-PROJECT

65. The sub-project can be classified as category B based upon ADB’s requirements as per Safeguard

Policy Statement (2009). This classification is based on the review of the available documents and site

visit with respect to the environmental sensitivity due to project activities.

24. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST

66. The sub-project does not involve any prohibited activity as per the Prohibited Investment Activities

List (PIAL) of ADB.

25. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE

67. Sub-project developer has conducted a stakeholder consultation with participants from the catchment

area on 24.11.2016. The sub-project purpose, features and benefits were explained in detail to the local

population. This was done with the help of the project model being displayed during the stakeholder

consultation meet. This was done to allay fears and apprehensions of people and look into the objections

or suggestions related to the sub-project.

PPE

Hearing protectors shall be worn

in areas where noise levels

exceeds 85 dB

Respirators shall; be worn in

contaminated areas

All pipe valves, sewers, drains

shall be leak proof

Dyke walls shall be constructed

around storage of chemicals/fuels

Fire-fighting equipment shall be

installed all over the plant

at site

Fire-fighting

system/equipment

maintenance records

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 32 JUWMGL

26. GRIEVANCE REDRESSAL MECHANISM

68. As informed by the project proponent, they have to constitute their own Grievance Redressal

Mechanism (GRM) to sort out issues and concerns early at the ground level. If some grievances/issues

come to them, they first try to resolve it through site-in-charge, if not resolved then it is forwarded at the

President Projects level and finally to the Head Office. The Project proponent is advised to keep a

grievance register at site gate for taking up complaints/concerns of the general public, if any.

27. SITE VISIT OBSERVATIONS

69. A site visit was undertaken by IIFCL’s Head-ESMU, Environmental and Social Safeguard

Specialists on 15th January 2019. The site visit was undertaken to review the implementation of the

project’s environmental and social safeguards. During the site visit, following staff was mainly

consulted regarding environmental safeguards related measures implemented at JUWMGL project

site:

(a) Mr. M.V. Chary, President AP Projects

(b) Mr. Ravi Sankar Paladi, AM – HSE, JUWMGL

70. At project office at site, President-Projects Mr. M.V. Chary and HSE in-charge at site discussed

project features, progress of the sub-project so far, clearances, environment & social safeguards

related aspects of JUWMGL project. Based on the discussions with above mentioned officials and

visit, the site observations are given below:

The permits and NOCs required for the sub-project are in place. Sub-project staff

explained the status of pending clearances/permits to IIFCL staff.

The sub-project site for WtE processing plant and landfill site are side by side and both

were visited by IIFCL team. Legacy waste could be seen dumped at the dump yard site

which will be used for landfill purpose.

The developer informed that the sub-project does not involve any forest land, protected

area, sites of cultural and heritage importance.

Developer showed the reserve forest area boundary. No encroachment or spillage of

construction material was seen along the boundary of forest area. JUWMGL has dug

drains along the periphery of the area towards the forest and barbed wire fencing/wall is

proposed to be built along the boundary of the forest.

Land for WtE processing unit was handed over to the sub-project after clearing by GMC.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 33 JUWMGL

Developer informed that most of the machinery and equipment have been received at the

site. Civil, mechanical and electrical works are in full swing at JUWMGL site. The

project is expected to be commissioned by September 2019.

The area under construction was cordoned off with signage strip for safety purpose.

Water for construction is being sourced from permitted bore wells at site. Water during

operation phase will be sourced from nearest STP, for which assurance has been given in

writing by respective authorities. Developer has informed that pipeline for STP water will

be installed for uninterrupted supply.

Labour was seen wearing PPE.

A dispensary is built at the site with basic facilities. First aid kits were available at the

site. Doctor visits the site every alternate day for two hours.

A total of 972 saplings have been planted at the site. Most of the plantations are along the

periphery of the WtE plant and landfill site. The saplings are being watered. Project staff

informed that they have planned for another 1000 number of plantations in coming

months. Green belt will be developed as per the management plan.

One labour camp for about 400 labour has been established by the main civil contractor

on leased private land about 1 km away from the sub-project site. Accommodation is

provided in sheds with common toilet facility. No community kitchen was provided at the

camp. The labour had independent kitchens with kerosene stoves. Water through water

tankers is provided to the labour. Electricity is also available in the labour camp. The

sanitation situation the labour camp needs improvement, which was informed to the sub-

project developer during site visit.

Developer has informed that general health check-ups are conducted regularly for all

JUWMGL employees and contract employees and health register is maintained and

recorded regularly of all employees.

Sub-project is complying with the conditions of Andhra Pradesh Pollution Control Board.

Continuous emission monitoring system will be installed at the WtE facility on

commissioning.

Live monitoring of the sub-project progress is being done by Chief Minister Office,

Andhra Pradesh.

71. The site visit photographs are given in Photo Plate-I.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 34 JUWMGL

28. CONCLUSIONS AND RECOMMENDATIONS

72. Based upon the available documents, information and site visit of JUWMGL, it is concluded that

JUWMGL has undertaken adequate safety and environmental safeguard measures. The conclusions

for the sub-project are given below:

The sub-project has been prepared by JUWMGL as per its own funding requirement and not

in anticipation to ADB operation;

The sub-project has necessary national and local level clearance as well as permits and

approvals for project implementation;

The sub-project is being implemented on existing dump yard of the GMC;

JUWMGL is not located in forest land and away from human settlement; the project site

does not fall within or in close vicinity to any national park, wildlife sanctuary,

archaeological, heritage, historical or culturally important sites and no rare and endangered

species of flora and fauna are present in the project impacted area.

Concessionaire has confirmed that all statutory clearances/approvals/permits are obtained by

JUWMGL;

JUWMGL has adequate environment and safety staff for implementation of environmental

mitigation and safety measures during construction;

Commitment is shown by the developer to execute all construction and operation related

activities for JUWMGL as per the established environment standards;

The developer has been informed to implement EMP in structured manner. Developer has

been advised to conduct monitoring and maintain records as per EMP requirement during

construction and operation phase;

Concessionaire has confirmed that they will continue compliance with the terms and

conditions stipulated according to statutory clearances/approvals/permits;

Based on the due diligence findings, the sub-project developer has taken adequate measures

for safety and environmental management, so it can be deduced that the sub-project has no

significant environmental safeguard issues.

Regular field verification will be undertaken by IIFCL safeguards team to assess and confirm

compliance with the agreed environmental measures by the concessionaire, including

carrying out public consultations during execution.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 35 JUWMGL

73. The current sub-project therefore does not appear to involve any kind of reputational risk to ADB

funding on environmental safeguards and recommended for funding under the proposed project.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 36 JUWMGL

DUE DILIGENCE ON SOCIAL SAFEGUARDS

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 37 JUWMGL

29. PURPOSE OF THE SOCIAL SAFEGUARDS DUE DILIGENCE:

74. The Social Safeguards Due Diligence Report (SSDDR) has been carried out by India Infrastructure

Finance Company Limited (IIFCL) in consultation with the Concessionaire, Jindal Urban Waste

Management (Guntur) Limited (JUWMGL) to assess the Social safeguards adequacy of the project

with the applicable National Policies. The report has been prepared as per the

documents/information received from the concessionaire and on the basis of site visit organized

during 14th

and 15th of January 2019. The information given in the SSDDR is agreed and

confirmed by the Concessionaire.

30. PROJECT AGAINST THE PROHIBITED INVESTMENT ACTIVITIES LIST:

75. The sub - project JUWMGL does not involve any prohibited activity as per the Prohibited

Investment Activities List (PIAL) of ADB.

31. OBJECTIVE OF SOCIAL SAFEGUARDS DUE DILIGENCE:

76. Social Safeguards due diligence study is carried out to assess the social safeguards monitoring

compliance status of the project as per the applicable National policies/procedures as observed

during the site visit as well as the information received. The main objective of this Social

Safeguard Due Diligence Report (SSDDR) is,

To assess the likely social impacts and its minimization/mitigation majors adopted of the

project with respect to land acquisition, compensation and involuntary resettlement,

common properties, if any, in terms of displacement, loss of incomes, and community

links:

To ascertain, in case of any adverse impact, if appropriate mitigation measures have been

taken during the project planning, designing and frameworks established for carrying out

safeguard measures during the implementation stage to minimize and mitigate such if any

adverse impacts;

32. APPROACH AND METHODOLOGY:

77. The social due diligence report for the project has been initiated after review of Information

Memorandum (IM), DPR, all other clearances, licenses, Gazette notification and notice under

Indian Telegraph Act, 1885. On site visit and detail consultation/discussion with the project

developer NRSSTL and various permits and approvals relating to the project to understand the

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 38 JUWMGL

salient features of the project and various social concerns. The following

documents/Reports/Licenses and notifications were referred in order to prepare the Social

Safeguard Due Diligence Report:

Project Information Memorandum (PIM)

Detailed Project Report (DPR)

Lender’s Independent Engineer’s Report for quarter ending December 2018 Project Statutory Approvals

Project HSE Documents

Concession Agreement(CA)

Power Purchase Agreement (PPA)

Land allotment/lease agreement

Labour License

EPC Work Orders/Contract Documents

Sub-project layouts

Discussion with developer.

33. STAKE HOLDERS CONSULTATION:

78. Stake holder’s consultation was organized on 24/11/2016 during the project planning and preparation stage of the project at Kondaveddu village (Kothapalem), Edlapadu Mandal, Guntur

District. During the stake holders’ consultation project authority has briefed about the project for

establishing 15 MW Capacity waste to energy plant at Kondaveedu village. The details of the stake

holders consultation was given in Photo Plate-II. Further, the project Jindal Urban Waste

Management (Guntur) Limited (JUWMGL) has received village Panchayat NoC for the project.

The Sarpanch of the Village Panchayat Kondaveddu revenue village (Kothapalem), Edlapadu

Mandal, Guntur District has issued A-1 Notice to the project. As per the notice the project has not

received any objection from the local people and no objections has issued to the project JUWMGL

by the panchayat. The panchayat resolution was attached as Annexure XIII.

34. SOCIAL IMPACT OF THE PROJECT:

34.1 Impact on Structure:

79. The project site location was allocated by the ULB and the site allocated for the sub-project was

existing dump yards used by the ULB. As informed by the concessionaire and noted during the site

visit, no structure is getting affected due to the project.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 39 JUWMGL

34.2 Land Acquisition in the Project:

80. Based on the availability of land and location of existing dump yards, the waste to energy project

JUWMGL has located at Kondaveddu revenue village (Kothapalem). The project site is currently

being utilised as dumping yard/landfill site by Guntur Municipal Corporation.

81. The total land required for the project is 51.24 acres out of which 15.5 acres is for plant and 35.74

acres is for dumping yard. The project is being developed on Government land. Guntur Municipal

Corporation signed a lease agreement with Jindal Urban Waste Management (Guntur) Ltd.

(JUWMGL) on 19.07.2018 for an area of 15.5 Acres for setting up a MSW projects for a period of

25 year on lease basis. As per the land lease agreement land cost per acre is Rs. 33.80 Lakhs,

including all taxes. The lease rentals shall be enhanced in every block of 5 years by increasing 10%

on the lease rental of the previous block of 5 years. The detail of the lease is attached as Annexure

XVII.

82. The Govt. of Andhra Pradesh has accorded permission for the existing dump yard site having an

area of 35.74 acres has also been allotted to JUWMGL by Municipal Corporation, Guntur vide

letter dated 12.04.2017, for establishment of development and operation for storage of residue as

per Concession Agreement on free of cost basis for a period of 25 year. The Government order on

land allotment is attached as Annexure I.

83. Although there was no involuntary land acquisition in the project and all the required land for the

project is government land, allocated by the Government of Andhra Pradesh by signing of the land

lease agreement (15.5 acres) and free of cost basis (35.74 acres). Land acquisition process was

initiated prior to IIFCL’s involvement and not in anticipation of ADB financing and that IIFCL was not involved in the rehabilitation and resettlement activities of project if any.

34.3 Resettlement impact in the sub-project

84. During the site visit it was observed that, there is no a commercial / residential structure or

inhabitants dwelling on the site. The project site are so identified that the project location is far

from the habitation. Even it was also observed during the site visit that there were no temporary

shelters/sheds at the project site. The land leased for the project doesn’t result in any involuntary resettlement impacts or any compensation issues.

34.4 Impact on Schedule Tribe people:

85. As confirmed by the subproject developer that, the project has not affect the livelihood, culture of

the residents of the villages. Moreover, the land where the JUWMGL project is constructed,

was not owned, used, occupied, by any tribal group and not affect tribal people.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 40 JUWMGL

34.5 Impact on Common Properties Resources (CPR):

86. It was observed during the site visit that no common property resources are affected because of this

project JUWMGL.

35. GRIEVANCE REDRESSAL MECHANISM:

87. As informed by the project developer no grievance was received by the project proponent, however

they have formed their own grievance mechanism in place. During the site visit it was informed,

that Grievance Redressal Committee (GRC) will constitute at the project site to ensure that the

affected person’s grievances, on both environmental and social concerns, are adequately addressed.

During the site visit it was advised that the project proponent has to keep a grievance register at site

gate for taking up complaints/concerns of the general public, if any.

36. LOCAL EMPLOYMENT:

88. During the discussion it was told that the project provides limited employment opportunities to the

local people during the construction stage, especially with respect to unskilled labor. The nature of

work requires specialized skill for the highly technical work such as establishment of plants and

boilers. Local people normally do not have such experience. Thus, the contractors working for

construction of plants and establishment of machineries have their own gang of skilled labour who

are trained in similar activities.

89. Further, as informed by the sub project developer the contractors have given job opportunity to

local people giving them as security guard, driver and office assistants and where ever required

developer has assured to provide employment opportunities to local people. Out of the total work

force of 275 more than 150 people are employed from local area.

37. LABOUR LICENSE OBTAINED BY THE SUBPROJECT DEVELOPER:

90. The subproject developer Jindal Urban Waste Management Guntur Ltd. has received the Labour

license from the Govt. of Andhra Pradesh, Labour Dept. for construction of waste to energy plant

at Kondaveedu village, Edlapadu Mandal, Guntur. The Deputy Commissioner of Labour, AP has

issued the certificate under section 2 (d) and 4 (2) of Section 7 of the Contract Labour (R&A)

(Regulation & Abolition) Act, 1970 and Inter State Migrant Workmen (RE &CS) Act. 1979. The

detail of the labour licenses for 390 workmen is attached as Annexure II.

91. The labours are covered under group Janata Personal Accident Insurance benefit. The detail of

accident insurance is given in Annexure III. Further, the project developer has also has registered

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 41 JUWMGL

under the Employees’ State Insurance Corporation (ESIC) for benefits of social security benefits

for employees start with their first day on job and some other benefits have conditions to complete

certain time period on job. Under ESIC, Medical benefits of family, dependent benefits, Funeral

benefits or death benefits will be application on candidate from their first day of joining in the

company. If a candidate having per month salary of less than 21000 Rs. then he/she will be entitled

in ESIC scheme. And in this 1.75% is contributed by Employee and 4.75% will be contributed by

your employer in the ESIC account. The detail of ESIC is attached as Annexure XVIII.

38. DISCLOSURE:

92. The information given in the ESDDR is agreed and confirmed by the Concessionaire. On approval

by the ADB, the report will be uploaded for public disclosure in IIFCL’s website as well as ADB’s website.

39. SITE VISIT OBSERVATION:

93. As part of the preparation of the ESDDR, the sub-project was visited by Head-Environment &

Social Management Unit (ESMU), Environmental and Social Safeguard Specialists of IIFCL on

15th January 2019 for field verification of environmental safeguards. Consultation with the Project

Head and Health & Safety team was also done regarding safeguards implementation during the site

visit. The sub-project is currently in construction phase. The site visit photographs are given in

Photo Plate-I.

The project is on construction stage;

As informed during the visit, no grievances have been received till date from the local people.

Local people have been given employment opportunity for unskilled and semi-skilled activity

during the construction activity.

40. CONCLUSIONS AND RECOMMENDATIONS:

94. The sub-project has been prepared by Jindal Urban Waste Management Guntur Ltd. which appears

adequate social safeguard have been taken into consideration during project planning and

implementations.

The Waste to Energy Project for 15 MW capacity is an integrated cluster facility for

processing Municipal Solid Waste (MSW) covering the area under nine ULBs including

Vijayawada and Guntur Municipal Corporation as well as other seven Municipalities in the

cluster at the door of the facility.

Environment and Social Safeguards Due Diligence Report India Infrastructure Finance Company Ltd.

IIFCL/ESDDR/ADB/2019/110/V2 42 JUWMGL

During discussion with the project official it was informed that, no tribal people are

affected because of the project.

No involuntary land acquisition in the project and all the required land for the project is

government land, allocated by the Government of Andhra Pradesh by signing of the land

lease agreement (15.5 acres) and free of cost basis (35.74 acres) allocated by Govt. of AP.

Land allocation process was initiated prior to IIFCL’s involvement and not in anticipation

of ADB financing and that IIFCL was not involved in the rehabilitation and resettlement

activities of project if any.

The sup project, JUWMGL has been prepared prior to the ADB’s involvement and IIFCL entered into the project after technical closure and before the financial closure of the

project.

The subproject JUWMGL was prepared by Govt. of AP for its own requirement not in

anticipation of ADB’s procedure.

95. It seems that the sub-project does not appear to involve reputational risk to Asian Development

Bank funding on social safeguards and recommended for funding under the proposed project.

GOVERNMENT OF ANDHRA PRADESH ABSTRACT

Lands- Guntur District- Alienation of land to an extent of Ac.51.24 cents (classified as Govt. Land (AWD) in Sy.No.933 to an extent of Acs.6.54 cts, Sy.No.938, Ext. Ac.8.96 cents, Sy.No.947 Ext.Ac.6.60cents, Sy.No.949 Ext.Ac.3.66 cents, Sy.No.951 Ext:Acs.7.20 cents, Sy.No.952, Ext. Ac.16.64 cents, Sy.No.954 Ext: Ac.1.64 cts etc., Govt. land (AWD) of Kondaveedu (V) Edlapadu (M),Guntur District in favour of Municipal Administration & Urban Development Department for establishment of Compost yard for the purpose of Municipal Corporation, Guntur on free of cost basis, subject to issue of notification U/s 4 (1) (c) of A.P. Assigned Lands (POT)Act 1977 for utilizing the same for public purpose, subject to certain conditions – Orders - Issued. ================================================================

REVENUE(ASSIGNMENT-II) DEPARTMENT

G.O.MS.No. 509 Dated: 14-11-2017 Read the following

1.From the Collector, Guntur District Rc.No.4426/2017-E1, dated:21.03.2017.

2.From the CCLA’s ref.No.Assn I(1)/217/2017, Dated:30.06.2017.

O R D E R

The District Collector, Guntur in his letter 1st read above has submitted proposal for transfer of land in Sy.No.933 (classified as AWD) to an extent of 51.24 cents, i.e., in Sy.No.933 - Ac.6.54 cents, Sy.No.938-Ac.8.96 cents, Sy.No.947 – Ac.6.60 cents, Sy.No.949 – Ac.3.66 cents, Sy.No.951 – Ac.7.20 cents, Sy.No.952 – Ac.16.64 cents, Sy.No.954 – Ac.1.64 cents, situated in Kondaveedu Village, Edlapadu Mandal, Guntur District on free of cost basis in favour of Municipal Administration & Urban Development Department for establishment of Compost yard for Municipal Corporation, Guntur and to establishment of Waste to Energy Project by generating the Electricity from the solid waste by recycling process for Government purpose in accordance with G.O.Ms.No.571, Rev(Assn.I) Dept, dt.14.09.2012. He has further stated that the Basic Value of surrounding Sy.Nos., is Rs.22,00,000/- per acre and the Prevailing Market Value within the vicinity of the proposed lands is @ Rs.30.00 lakhs per acre, the total value of the land Ac.51.24 cents is comes to Rs.15,37,20,000/- and recommended to allot the subject land on free of cost basis. The District Collector, Guntur has further stated that the Joint Collector, Guntur has inspected the proposed land to an extent of Ac.51.24 cents situated in Sy.Nos.933, 938, 947, 949, 951, 952 and 954 of Kondaveedu Village of Edlapadu Mandal along with Tahsildar, Edlapadu and field level staff. The land is covered with deep quarrying pits and is being used as dumping yard by the Municipal Corporation, Guntur. It lies adjacent to Guntur Mandal on one side and to Kondaveedu Village on the other side. There are no habitations nearby and the land of Ac.51.24 cents is situated on western side of National Highway within a distance from 2.5 Kms which is proposed for use of dumping yard. No structures, no trees and no water bodies are there on the proposed land. A1 notice was published and no objections were received. The Gram Panchayat, Kondaveedu also passed resolution for transfer of the land.

2. The Chief Commissioner of Land Administration in his letter 2nd read above, has stated that the proposal of the District Collector, Guntur has been placed before the APLMA in its meeting held on 29.07.2017 and the APLMA has resolved to “recommend to the Government as proposed by the District Collector, Guntur for transfer of land on free of cost subject to notification of land u/s 4 (1) (c) of A.P. Assigned Lands (POT) Act, 1977 to an extent of Ac.51.24 cents in Sy.Nos.933, 938, 947, 949, 951, 952 and 954 in favour of

Municipal Administration & Urban Development Department for establishment of Compost yard for the purpose of Municipal Corporation, Guntur, subject to certain conditions.

3. Government after careful examination hereby order for alienation of land to an extent of Ac.51.24 cents (classified as Govt. Land (AWD) in Sy.No.933 to an extent of Acs.6.54 cts, Sy.No.938, Ext. Ac.8.96 cents, Sy.No.947 Ext.Ac.6.60cents, Sy.No.949 Ext.Ac.3.66 cents, Sy.No.951 Ext:Acs.7.20 cents, Sy.No.952, Ext. Ac.16.64 cents, Sy.No.954 Ext: Ac.1.64 cts etc., Govt. land (AWD) of Kondaveedu (V) Edlapadu (M),Guntur District in favour of Municipal Administration & Urban Development Department for establishment of Compost yard for the purpose of Municipal Corporation, Guntur for Government purpose on free of cost basis, subject to issue of notification U/s 4 (1) (c) of A.P. Assigned Lands (POT)Act 1977 for utilizing the same for public purpose, subject to the following conditions in addition to the conditions under BSO – 24 and GO Ms.No.571, Revenue(Assn.I) Dept., dt.14-09-2012.

i. The land shall be utilized for the purpose for which it is allotted within three years of the orders for the alienation.

ii. The land will be resumed to Government in the event of failure to comply with the terms and conditions of alienation.

iii. The water bodies if any existing in the land should not be disturbed and should be allowed to continue their natural course.

iv. The existing roads/rasthas should not be disturbed.

4. The Special Chief Secretary & Chief Commissioner of Land Administration and the District Collector, Guntur shall take further necessary action accordingly in the matter.

(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)

Dr.MANMOHAN SINGH

SPECIAL CHIEF SECRETARY TO GOVERNMENT To The Special Chief Secretary & Chief Commissioner of Land Administration, Gollapudi, Vijayawada, A.P. The District Collector, Guntur.

Copy to: The PS to Spl.Chief Secretary to Hon’ble CM. The OSD to Hon’ble Dy.CM(Rev). The PS to Chief Secretary. The PS to Spl.Chief Secretary (Rev). The G.A(Cabinet) Department (w.r.t.U.O.No.447/2017, dt.07.11.2017). S.F.

//FORWARDED::BY ORDER//

SECTION OFFICER

THE NEW INDIA ASSURANCE CO. LTD. (Government of India Undertaking)

GROUP JANATA PERSONAL ACCIDENT INSURANCE POLICY (IRDA/NL-HLT/NIA/P-PN.1/56/14-15)

Insured's Name : CEEKAY ASSOCIATES PVT.LTD.

Insured's Details Issuil

Office Code :

Office Details

BAREILLY (340200) Customer ID : P054437419

Address : NAIDUPETA CHILAKALURIPET ROAD,JINDAL URBAN WASTE MANAGEMENT ,GUNTUR,

GUNTUR ,ANDHRA PRADESH, 500601

Address IIND FLOOR, RAGHUVANSHI COMPLEX 85-A, CIVIL LINES BAREILLY,243001

Phone No Phone No : 0581-2477764 / 2571677

E-mail/Fax [email protected] , / E-mail/Fax : [email protected] /

PAN No : AABCC3459K S.Tax Regn. No

GSTIN

:

:

AAACN4165CST178

09AAACN4165C4ZM GSTIN/UIN : 37AABCC3459K1ZG / NA

SAC : 997139 (Other non-life insurance services excl RI)

Policy_Details

Business Source Code Policy Number : 34020047182300000001

Period of Insurance : From:29/11/2018 10:47:59 AM To: 28/11/2019 11:59:59 PM

Dev.Off.

level/Broker/Corp. Agent

: A.K. SHARMA - (DE9771686)

Date of Proposal : 29-Nov-18 Agent/Bancassurance Mr. ASHOK KUMAR RATHOR (NIAAG00061890) ASHOK KUMAR RATHOR (S100101350)

Prey. Policy no. • . Phone No : 9411913038 / NA

Client Type : Non-Corporate E-rnaiUFax : [email protected] , / / /

Premium GST Total(RS) Receipt No. & Date

11400 0 11400 34020081180000006119 - 29/11/18

POLICY SCHEDULE

Details of Group Unnamed

Sr. No. Number of insured persons

Geographic al area

Description of

persons covered

Age Group SI per person Assignment details Name of

Owner/Benefi

ciary

1 200 NA NA NA 100000 NA NA

Special Conditions:

NA

Subject to Janata Personal Accident Insurance Policy Clause as attached hereto.

NOTE: WARRANTED THAT IN CASE OF DISHONOUR OF THE PREMIUM CHEQUE, THIS DOCUMENT STANDS AUTOMATICALLY CANCELLED 'AB-INITIO'.

Premium and GST Details

Premium

SGST

CGST

IGST

Rate of Tax Amount In INR

711400

0 0

0 0

0 0

In witness whereof the undersigned being duly authorised by the Insurers and on behalf of the Insurers has (have) hereunder set his (their) hand(s) on this 29th day of November,2018.

For and on behalf of

The New India Assurance Company Limited

Signature Not Verified_

DigiT Tly sig by Sriniva n Policy No. : 34020047182300000001 Document generated by 22286 at 29111/2018 11:04:45 Hours. Vaide an Regd. & Head Office: New India Assurance Bldg., 87 M.G. Road, Fort, Mumbai - 400 001. TOLL FREE No. 1 800 209 1415. Date: 201 11.29

For tad)itfi.1.1641 your grievance, if any.you may approach any one of the following offices- 1. Policy issuing office 2. Regional office 3. Head office.ln case, you are not satisfied with

our own grievance redressal mechanism; you may also approach Insurance Ombudsman. For details of our office addresses and addresses of office of Insurance Ombudsman, please

visit our website http://newindia.co.in .

Page 1 of 2

THE NEW INDIA ASSURANCE CO. LTD. (Government of India Undertaking)

Date of Issue: 29/11/2018

Duly Constituted Attorney(s)

Mudrank Dt. consolidated Stamp Fees Paid by Pay Order Number vide receipt

number dt.

Stamp Duty under the Policy is Z1/-.

Tax Invoice No :

IRDA Registration Number: 190

Policy No. : 34020047182300000001 Document generated by 22286 at 29/11/2018 11:04:45 Hours.

Regd. & Head Office: New India Assurance Bldg., 87 M.G. Road, Fort, Mumbai - 400 001. TOLL FREE No. 1 800 209 1415.

For redressal of your grievance, if any.you may approach any one of the following offices- 1. Policy issuing office 2. Regional office 3. Head office.ln case, you are not satisfied with

our own grievance redressal mechanism; you may also approach Insurance Ombudsman. For details of our office addresses and addresses of office of Insurance Ombudsman, please

visit our website http://newindia.co.in .

Page 2 of 2

Scanned with CamScanner

. ':

;_-,_ .. :i:. . . . ·:., .. ,!' :

:· .. ',, . •• , ,1 •• • y \•

· .. 7 ;. ·

. . ,. · ....

' ' ... ,) . .

\ . . \ ·

. \ " . セM

セ M[A QセM ᆳ

/ · セ N@ .

::·,

I . · . . i ...

/ '

· .. ·: ' I ,.· .. - -- .

: . Mセ@

: .

' : .

· ... ... ,f,_ ...

·\

/

ᄋ セ@ ....

: !··

; .

·',

. '. :, セ@

;.' .'."'•

, ...... .

1.·.:

· '

.,. I

! ••

" MセN@

i I . J

. _,_.

.. ; . . : . . . ... ··.: ':' . . セ Z@ . . : · · . . セᄋ@ . ' . ' . ... ..

' .

.....

. •" ... セ ᄋᄋM BN M .· ..

.. ... ... • I • ,

.. ··

• J

i

. ᄋᄋ セ@'j

.. _;

ᄋセ@ i

'' ·.•

'i ,·I

, .. セ@

. ;

. . .. . _ :. L ... ·. ᄋ MMセM M N セ Zセ M セZェセセセセセセセセゥaエN[Nセセ\セj@

Z[セセᄋNZᄋNセᄋ Z ᄋ セZセᄋ@ .. セZZᄋᄋMセ@ .. I [ᄋ[LセWセ@ Z ᄋセ@ ... Mセ@ ... ᄋセMセM ....... セセセBWBGBᄋ ᄋᄋ@ .. ZZMZGᄋセセセ ZセN⦅M .. ":'.'": ...... GᄋセセZ ᄋ セセ@ .. ZセᄋZZᄋM セ ᄋセᄋ セNLセ MZ GZGセ GBZZエZᄋLZᄋセᄋᄋZ セ ᄋ MセᄋBZ@ ····· ᄋᄋセ@ \ ... ᄋセ@ . \' '; •' ... . NLNセ@ ·.· .. · : . . :·. . . \ ; ; .. . .. セ@ . . ..

[L N [LLセセヲNN@ .. ᄋ[L [LZ[ LNN [NᄋセNNN[N[ᄋ N セセセ M NNN」NNNN[NNN@ _;· ........ ,_,,._.,, •. ,., •.• ,.,,...;.•, ,:,·,,.· .• Nセ@ .•.•. ·.·-· .••• .: .• [[Nセ@ ..•. • . · · •...•• : .•• · •• :.' .. : ........... .,: .. .... ...... :.·: •• : l. , ..... : -·· ......... セ@ ................ ! . .................. セMMセᄋMᄋᄋMM ............. ·,; . • ,. ··-·· ·

,:,. ..

. '. セM .

.... ! .

. .

CONCESSION AGREEMENT . . .

FORS·E.TTING ·UP

. "

·.·

. .......

. .

. ;., .}

MUNICIPAL SOLID WASTE (MS.W) ·TO ENERGY .. Zセ ᄋ AGZA@·PROCESSING FACILITY · _,_J}' ·

NcG| セ I@\l 0'·} . t5 セᄋセNᄋ@'-,_/, (;> ;:·. .

,,.: ;• .

IN GUNTUR, ANDHRA PRADESH ..... セ@

\ i

\ \

r' ... --·

4'.:( ())

I.

l セNN N NNNNNN@ .

... NNNカNヲエゥ|HセNMMM ᄋMᄋᄋ@ .. ···""' ·-1-,,. ........ f. .,J.. ... ; ..... . • ••• • · •• •

. .

NセN@

- -----------·---- ----·-··--· M セ@ MMᄋMᄋ ᄋ MMM M MM MMMセ@ ----·

. ·'·

iᄋセ ⦅ZN セ N@ . ·. r : NᄋセセNN NN@ . · -..,.--_: -.. MZMᄋセ@ .. . セᄋᄋᄋM .. MᄋM セᄋ ᄋ ZMNM[ZMW ᄋ セ@ .. , ....

セセMセセセ M L[NNセL@ ... . ... · ... , .: .. :....... · .. セ@ •. ., .... , ........... セN ᄋM」 Nセ@ .. . [L[N ^ セMᄋᄋB ᄋNMN MMMᄋMᄋᄋᄋᄋᄋセᄋBᄋセ@ ................. .

.. ·: ·.·. . .

:• ... . -. セM . ':' ' ·: \ . . ' -'\ ., . . . Mセ@ Gセ@ .. . G QpZエヲャZQkセN

QセセセヲゥヲPZ A@

. ''"' ,.,

'

セG@ :

t. · ..

セᄋᄋ@\ Mセ N@

'· \ セゥ@

Contents

PART I- PRELIMINARY ........................ : ............................................ : ................................... セNL@ .......................................... : .. セN L N Z NL Z@ .. i 0 . . . ·.. . . . .. ' . .· . ·. . . . · . . ::!•. ::, . .. .. ·-· -.:.

1. Definitions and Interpretation ............... : ... : ................... :: ..... : ... ,: ..................... : .............................................................. セNZ [Z@ .. -.. :.:;-}4. : . . , •. , · · -·· , ., .... , •..•••. '" . . ', .. • . ...... . .. . .. ........ . -.•. . . ... :- · • . .. . . . . ·. ·· . .. .. .•. .. ·····: . • . ... . ... -. . •·---: -_ .......... _ ... . , t- . ;

1.1 Definitions ............................... , ........................................... : ........................................................................................ :.: ......... : 14 ;

· 1.2 Interpre.tation ... : ................ セセ@ ... -.............. : .... セZ@ .. :.:: ........ :.: ..... ZNZ セ ZZZZZ@ ..... :.: ...... : ............. : .. :::.:.::: ... : ... ::.::::: ...... :: .... ::.:::: .. ZZセZ N Z NZ [セ N セZ ᄋ Z [ ᄋ NR_ N ZZ@ ·· 1.3 Measurements and arithmetic conventions .............. : ........................................... ; ........................................ .' ..... :: ... 30 :

.. ·. . ... ·: . ....... · .. : .. ... . ·: .. ' · ... : .. ·: . . ...... ᄋᄋMセ N@ •,, . . . :: ,•. . ·.· .. ᄋ セᄋ@ ·. ' . .. . . .. ... ·. ..': .. ': .. :.:: ᄋ ZᄋNZセZᄋ Z セGZZ ᄋZ@

1.4 Priority of agreements, clauses and $chedules ......................................... : ............................................... : .. ; .. セNZ@ ...... 30 ·

·J-;ART II· THE CONCESSION ..... セ@ ...................... .-................... , ......................................................................................... , ......... _:.:..·:· .. ; ... 32: . .':

. · ... . .

2.1 Scope of the Project ................................................................................................................................................. ;.:,, ...... :_33 .. ·

2.2 Processing Technology ........................................................................................................................................... :;;: .. _. :····33

3. Grant of Concession ............ : ...................................................................................... ; ................................................................... ,: 35

3.1 The Concession ............... : ........................................................................................................................................... : .. .,. . NL [ NセSNsN@ · .. ·

ᄋL IILセセセ@. .. , Bエ ᄋ セ M セ@

. ZM Lセ セ M セ[エ@L Z L ᄋN セ N@

.. ..... セN\A Iセ@

. Z ᄋZ Zᄋ Zセ@

·. , . .... . .

&l:; -;:: L;) セ セ@

. 4·, Conditions Preceden.ts ......................................................................................................... : ................................................ :· ... : .. ZNNLセセSW@ z: t.> : . . ,., ' . . . . . . セセ@

4.1 Conditions Precedent ................................................................................................................................................. : ......... 37 ᄋ セ@

. 4.2 Damages N ヲッセ@ delay by the Concessionaire .............. : ............................................ .' ................................................. , .... 3 t·:\ セセ M :":f . . . . . . . •t ·. ··o ᄋセD B@

. 4.3 Damages for delay by the Lead ULB .............................................................................................................................. 38· セᄋセ@ .. : t) 1:.\: . . . . ᄋ セ@

5. Obligations.ofthe Concessionajre .......................................... セ@ ...... セ@ ............................................................................................ 39 .· · M セGゥェNN@

. セセᄋ@5.1 Obligations of エセ・@ Concessionaire ................................................ .' .................... , .............................................. : ... セ@ .. : ..... ,. 39 :J . . • <J; . :

5.2 Obligations relating to Project Agreements .............................................................................. : .................... :: ......... 40 . jNDNセ@ L セ@. . . N、ᄋセcU@ !;:::'

·5.3· Environmental Compliance ........................................................................................................................................ : ... ,.4J; . セ|Z セ@ セ@

· . |NNLセZ ᄋN@ c .. セセt@ i ·

· ::: セZZZ・セZゥZᄋセᄋセ[[セセᄋセZZZZZZZZZZZZZZZZZZZZZZ Z ZZZZZZZZZZZZ Z ZZZZZZZZZZZZZZZZZZ ZZ セ ZZ ZZZZZZZZZZZZZZZZZZZZZ ZZ ZZZZ ZZ ZZZZZZZZZZZZZZZZ ZZZZ ZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZ N ZZZZZZZZ Z ZZZ@ : .. .. NL[Zセ@ 1? .5.6 Post Closure Activities .............................................................................................................................................. _ ............ 4·l . セ M ·f

. . . . . . ·. . ............. セ[ セ@ ᄋセ@ . ,.. . 5.7 Measurement of MSW ...................................................................................................................... ; ................................... 4\ ·;_·; .. Z[[セ@ セ@

L .· セセセセ@l 5.8 Maintenance of records and Operations Plan ........................................................................................................... Tセ セNNNM E g..

. .· . . ·· ·· ._:.§ 0

5.9 Sale 1 Distribution of Compost 1 f11anure I Energy .............................................................................................. セ@ .. TRONセ ィ BMZG@ セ@: . . . .. . . ; .. • 51

5.10 Penalty for O&M Breach ........................ : .............. : ......................... .-...................................................... : ........................ セT R@ · ,.....

. セ@

. セ@

5.11. Obligations relating.to Change· in Ownership ........................................................................................... :.: .......... Tセ セWIGZ@ . 5.12 Employment of foreign nationals ....................................................................................................... : .. : .................. 44>·:--· ·

..... _ . ...... . ....... .. ........ LNLNセ ᄋ@ ... セセZA GAセG G@ セ@ ....... ' :-.)1·'· ' .... ""'..,·, " .. [LZLN N セ@ GjGᄋᄋ セMZ@ .... •·· .. ·..tt •1 •

. ,. ··. :•. ':. ::· : .... .""{.".' ....... ' ' ...... ,'

.,.:::.:..:_ .. _, ........... ᄋセᄋ@. f ᄋMセᄋセNN@ ᄋᄋセᄋᄋ ᄋ ᄋG@ • •••• ,.." ..... ·--···' セ@ '-;.•:. '• ;.:.v, • ,:;... ••••• .;.. ....................... .... - : •• •• • • -·.

. .. - '· .... .. ...... セNMN@ ..... :...;.,,..: ,_ ᄋᄋ セᄋ@ ... : ... · ...... :_.. -.. .... ..... .. . ··- ···-·' . .. .. -

I-I i i I

セ@. 1.\

.. , i \

··\ ..

/

i ... \ セ@ .... )-

; ... •.-. .. .. :. ... ' ... ..... ··-

6.2 General Obligations of the p。セエゥ」ゥー。エゥョァulbウ@ ....................................................................................... : ......... : ..... .-.46

セNS N jGイ。 ョ ウーッセ。エ ゥ ッョ@ of MSyj Hrセオエ ゥ ョァI@ .......... : ............... , .... : .......... : ..... : ....... , ............. .' ................................................. , ........ :4 7 :

7 セ@ r・ー イ ・セ ・ョ セ エゥッ セウ@ セョ、 N@ w。セセセョエセ・セ@ ... :.:-.-.. ᄋ NZセ@ ............ : .. : ........ : .... : ..... · .. : ........ セPN ᄋ N Z NZ@ ......................... · ........................ セ@ .......... ,:.:., ..... · .... : ... : 4-8 :.

7.1 Represe.:.t<itibns.aiid w。イイセョエゥ Z ・セ Z ッ ヲcッゥゥ」・ウウゥッョ。ゥイ・@ ...... : ....... ::; ... : ........ セ@ ... :.: ...... .-.: .... : ............ ;; .. : ... : ... .... ,· .. :.' ... : .. :.:·':48.·

7.2 J:{epresentations and キ。イ イ 。ョセゥ・セ@ qf the Pat:ticipating ULBs : ...... : ......... : ................................ : ......... : ..... : .. : ......... Uセ@

7.3 Obligation to Notify Change ................................................................................................................................ .' ..... , ...... SO

8. Disclaimer ............................................................................................................................................................... , ................. : .......... 51 . .

· ·s:I tiischiimer: ....... : ................. : ...... : .. : ...... セ@ ... :.: ............. : ... ......... .-: ... : ........... :.:·: ... :: ........................................... ; ............... ;;.-.. ; ........... Sl

,.j

0 .. <:{ .. o·

H.l .:.

:··

. . .

PART III · DEVELOPMENT AND OPERATIONS ........................................ : ............................................................... : ....... :.' .... 52 ::: セセ@(.) ᄋ セᄋ@ .. ii} 6 '

. ·, . (/j ᄋセセ@

9. Performance Securlty ......................................................... , ....................... ...................................................................... , .......... 53 ·.......;.,.;;; N セセZ@

. . 3 ' セゥN_エZケ ヲ@9.1 Performance Security for Construction Works ........................................................................................................ 5 0 ··5:

. . オセ@

9.2 セーーイッーセゥセエゥッョ@ of cッセウエイオ」エゥッョ@ Performance Security for cッョウエイセ」エゥッョ@ Works .............................. : ......... 53 ( ') セ ス@

9.3 Release of Construction Performance Security ................................................................................................... · ..... 54 \'1 ,; ;! 9:4 Performance Security for Operation and Maintenance Period ...................... , .................................................. 54

9.5 Appropriation. of Operation Performance Security during Operation and Maintenance Period ........ 55 (;

10. Project Site ................................. _:_. .................. セ@ ................................ _ ..................................................................................... : ......... : .... S6 : · セ ゥ@ £. 10.1 VestJng of Site with Concessionaire ................................................................................................ ................ ,.: ........ 56 · N セjMM セ@ セ ス@

,··· . . . : . . . . . . サセ セセP@ z. 10.2 Rights, Title and Use of the Site ........................................... .......................................................................................... UV Zセ@ "12 セ@

. GGᄋGQG ᄋ セ ッェ M .: 10.3 Possession of the Site ........................................................................... セ@ .......................................... .' ................... : ............ 57 ;;:t.. セ Z@ !J:

1

. . Pセ@10.4Applicable Permits ............................................................................................. : .............................................................. 58 2.

. . .. ('

10.5 Protection of Site from encroachments .................................................................................................................... 58 J セセ@10.6 Access to the Participating ULBs and Independent Engineer .................................................................. : ...... 58 ...... jセ@ J1

. . セ@ r, , 1v; セ@ 1 10.7 ? eological and archaeological finds ........................................................................................................................... UX ᄋ セセ|セセA⦅セN セ@ セNZ@

11. u ·1· .. · · A · · d d · 60 ( .. ..;:;,'lls セL@. tJ. Jttes, ssoctate Roa sand Trees..................................................................................................................................... . ·•· . ...;, t:> J . . . . ..... ·:( e

11.1 Existing utilities and roads ........................................................... ; ................................................................................ 60 ( \ ..;:

11.2 Shifting of obstructing utilities .................................................................................................................................. : .. 60

11.3 New utilities and roads .................................................................................................................................................... 60 # \

•'

11.4 Felling of trees ................................... : .................................................................................................................... セ@ ........ 60: QNNN Zセス@

12. Development and operations of the Project ........................................................................................................... ,. jM NセBBエZセセ@. NャセGAss ヲc@ セr@

12.1 Obligations prior to commencement of constructio'n ........... ........................................................ MIIN.M gjjjャHセAjA n A cゥpi i uty@セ@

12.2 Project Implementation: Construction of Project F11cilities ................................................................. ............ 6l . セM _

12.3 Project iセーャ・ュ・ョエ。エゥッョZ@ oー・イ。セゥッョ@ and Maintenance ....................................................................................... 62 .:; 1. セセZI@I . ,: _.,

13 mQRNセ@ dQセ。キゥョヲァcウ@ ......... , ................................................................................................................................................................... ZᄋᄋV

Vセ HIセOセヲ@ セZNMZ@

. orutonng o onstructton ....................................................................................................................... : .......................... ,,.,:.. セZZ セ@ . , . . :: .. • • セZ@ ' l1• • "

. 13.1 Monthly progress reports ....................................................................................................................... ..................... Z ZL Vセ ZセセZ@

||MM。Nッ 。 ァ・OII Y セ@ セ@ C ';' ' . ¥.} . / : ..... ·. セャ「@ '/.: ;." .:Q .. i @ |NセI@ , . .

G セZ@ ;: : ᄋᄋZN wjAャ ᄋ ᄋᄋ ᄋ セ \エ@ ;;. セ セ@ . , : . f Z セ@ .. . ᄋ L ^LNセ ゥ ャセ@ セ@ , .. --·· 」 Gs イLLセOエイVヲNH スZセ Z N [@ セ@ .. i.

:, .· '·.:.:.'':·.:.:,.:•!' · QQA|ャIAャLNaエOalurG [セ A[NNNM >./·• ·., . . .,, · · '· ·' L セᄋ\ᄋG ZᄋMZ[@ . . ;j}.i セ@ セ |GZャイ@ f\1\J"'\ 1.r-"'""-'! > ... w\\•''·'•< • ..... • ...

'Qe ..... |セ@ ' ! " . ··:-.;::.:.;#

------ Mセ [セG@ t Hセ@ セ セ@GNゥgオセセ@

セ セMMMMM MM MM ッ・MMMM MM M MMMᄋMMMM , ____ .....,... __ -··-·--

· -:: . . . ... · . . . .. : .

. ·::· . .

13.2 ャョウー・」エゥセョ@ ................ .' ..... : ...... : ................................................................... : .. ." ..... セN Z@ .. :.: .. : .. : ............................... : ....... .-.::: .. セ[ M セ ZN セ N@ H[セ G@ . . ,,,. .. , .. · .. ;

13.3 Tests ...... : ..... : .... ; ... ; ........ : .... :.: ................ : .............................. : ...... : .......................... : ............. : ..................................... セZN Z ZNZZZ ᄋZ@ .. :.66;.· -.· ... · · · .:·r·-'·>: ·: ... 'J.t .-: .. ·::

• •• • • • • 0 • '; • • ' • ' • • • • • • • • ' •• ... ' : • ... ' 0. • • • • • . ••• , • • • • •• • • ' . • • • -' . ·' :· • .. •• MセNZ@ • • :;·, .. : : _.; : • • :·:· : . \. > .;_. ... ᄋ セ ᄋ@ ' . 13.4 Delays dur1ng constructlon ............................................ : ...... , ... : ..................................................... : ........ : .... ,::.·.:·::·:.:: .. セ@ .. 66:. · _·

13.5 Suspension セヲ@ unsafe Construction-Works : .. ZセL@ ........ : ......... _ .................... セ@ ......... :·······: .. ·•· ... : ........... , ......... Zᄋᄋ O Zᄋセ[ᄋセᄋ ᄋ Z VW L@ᄋ M QセNV M カゥ、セ ᄋ ッ ᄋ イセエセセセゥセァ@ ...... : ........... : .... : ..... :.:.-......... セ@ .. :.: ... : .... • ... :: .......... :.: ...... :: .... :: .... -............. : .. ·.:::.: ... : ... : .. :.:.·:.:::.':.:: ... NM N セZ N Z N Z[セ[Zセ@ ... コZ Z Zセイ@ -:;::.

14. Com pletiori Certificate:.::;:: ................ :.:: .... : .... : .............. :.: ..... : ..... :;;: ... : ........ :: .... : ... : ... : ... :.: .. :.: ....... : ....... : ... :: ... ::: .. ::.;:: .... ::·:,::::.:;.::i6R" MセNZ@ ·• ••

セZZセ@ [Zュセᄋ[ZセZセ G セZセ[NZ[セZN Z@ :::::.::::::::::::::::··: ZZ Z Z Z ZセZZZZZZZ@ .. :·:.::: ::::::::: •• ::::::::::::::·::::::: ::·::·: ::::::::::::::; J.t)'2.:k!! . · ,_,. • .. ·• · ' . ᄋᄋᄋM ᄋ ᄋᄋM ᄋ セ@ •"""'' ' : ' . . ., .. ' . -·· • .. ., ··. ' 40···. . . •. . ... ·•··. ·.•. ᄋ セ@ . .• , , ·.

14.3 Provisional Certificate ....................................................................... _ ................................................... : ........... ::.: .. ; .. :_.: .. :·.:._6$.' · · · ·: •;-,./:·.

セZZ[@ セゥセセセセZセZァッZ[[LZセウセZZセZセZZセZ[ZZZᄋZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZᄋZZZZZZZZZZZZZZZZZZZZZZZ ᄋ ZZZᄋ@ .. :::::::::::::::::::: ::: ···:: ··. セ ᄋ@ セ ZZ@エ セ@ I·, .J

. . . A セ_@ セAセ@ .: ·:· 14.6 Resche_ duling oiTests .......................................................................................................................................... .-.. ,: .. L Zᄋᄋᄋ ᄋ N Vセ N@ (/' .. ..,

. .. . . . .. . . . . . . . .., . ·•.·· . . ,Ji$ 15. Entry into ⦅ 」ッュョゥ・イセゥ。ャ@ Service .................. セ@ ...................... : ................. : ............................ : ............................................. Z NZセ ZᄋOᄋZ NZNMS_ ᄋ N@ ᄋ NZセ@ セセZ@

15.1 Commercial Operation Date (COD) ................................................................................................................ :.: ......... 7.1 -: 6 Z[Zセ@.. · · . ·· . . ' . . . . . .. : .. . ·: : .•.. (.)CI.

16. Operation and Maintenance ... : ................................ _ ............................................................................................... _. ..... : ........... _:7?<":··\ . セ S@ .. :.· : : . . . . . .. '; . . . . . · .. ·· · .. ·. "·· . セ@

16.1 Operation &·Maintenance Requirements ............... セ@ .. .. ..................................... : ......................................... ,.: .......... 72 ': ... ) !: '·

16.2 Operation & Maintenance. Manual ................... : ......................... : ............................ .' ....................................... :.:· ... : .... >/2. .

16.3 Damages for breach of operation & maintenance obligations ......................................... : ............ : ....... :: .. : ..... 72 . セ セ Mᆳ

セZA@ . .. J :·

· . 16.4 Lead ULB'sright to セォ・@ remedial measures ............... : ....... : .............................................................. : ... : .. ·:··: ... セ@ ... :. 73. ᄋM セL@ セ M セ M Zセ@. . . . . . . . .... ;:: (_ , ..

· ·· •16.5 oカ・イイゥ、ゥョセ@ powers of the Lead ULB ............................................................................................ ; ................... :····:;, ... 7.3 ;; ZNLN セ セ|G セ@ セセZ@ セセ@. . . . . . . . . ·. ' ;,. '41i'/'!: _,. '

17. Effect ()fVariations in MSW Q4antity& Quality ................................................................................................... :: ..... :; ..... 74\ _ ZLエセM t; _?.: ' . . . . . . . . '. ·. ;;,;;: .. t' 0:. '

·17.1 Effect of variations in MSW quantity .... .................................... : ................................ : ................................... :.; ..... , ... 74 . ... 8 セセ@ -, . . . . . · .. · . · z

17.2 MSW Maximum Quantity .................................................................................. : .......................................... : ..... [NZセᄋ Z@ .. ::·:. 7 4: ·'it _s: . 17.3 MSW_ Minimum Quantity ........................................................... .-........................................................... : ............. : .... :· .. セ@ .. 74 q. M セ M

. . . . . . . . ll'; :S[ 17.4 Revenue shanng by the Concessionaire ..................................................................................................... : ............ ;7 6 ---·.. j5 §

. . . . . / ,, : セ@ -... セ@

17.5 Settlement セヲ@ セッZョーN・ョウ。エゥッョ@ and. Revenue Sharing between the Lead ULB and Concessionaire ..... セz ᄋセ M セ@ t . 17.6 Effect of vanattons 1n MSW Quahty ............................................................................................................................ 78. ·. LL セ@ &:: . . . . . . セiG@ L'> . . . . .... \ . b,;. .

18. Safety Requirements ............................................................................................................................................................. : .... 79 . . · 1 セ M

18.1 Safety Requirements ...................................................................................................................................................... WYL Mセ MNB@ _, .... . . . . · . . . ( セ ZNNセ Z セ[セセ@

18.2 Expenditure on Safety Requirements ..................................................................................................................... セャエjNエ Q Gセ N ZLセZZ[ョエ L [er@. . . ' . C.\ .. il• ャ [[ィ N[NNL セ vᄋ|@ I.

19M . .. fO . dM' IH Q\G1"'llll"i(' i'? l-' . onttonng o peratton an atntenance ................................................................................................................. "',.. ,,_f',l BᄋカセZ Z Z N Zᄋ ャBG@. . / [セ@

19.1 Monthly status reports .................................... -; ............................................................................................................... XP Nセ@ ,:_iJ?· :··

., .... , ... _ .. ,

. I

! I I I'

·-:\ .' セ@

•r... セLᄋ N@ -: v セ@ ·· t • • •• ••• , • .... •-· '".: :• , ..... "''r:,""···!;.-.v .... _ : '•; .• "'::·: ._.

Z Z セセZ@ .. _ ... セMMMM セMMM Mᄋ@ ... -·. セMM セMᄋMᄋᄋB@ . ᄋMセ]ZᄋGNᄋセセZNMセNᄋZセNセセセセ N セ@ ... -.. ·· ···.·\ ··.· ... ... . .. セG@ .... "'. . _... . '- セMᄋᄋN@• < -"; t,

- .... ,; .. . . . . . . セ@ ........... LセNNNNNN@ ''-• ... :.. .... ----.- ........ ; .. ;.;, ....... , __ .. .. Mセ MMNM : ... :., .... Mセ@ ,.,., .. - ......... セMMMM ..

ᄋNZ GG Z セ@. セ|@

-• .o<$:,.:;;....1,:;11.&.11

. . , .....

2Cl. iョ、・ー・ョセ・ョエ@ Engineer ··:···: .... , ... :···· .. セ@ ................. セ@ ....................... : ..... ::··: ....... : ... : .. : ..................................... : .. : ....... .' ........... : ...... : ......... qMコ ᄋ ᄋ NZセ@

• · .. . セPNセ@ セイ Y N 」 N セセスNャヲNセ@ for セppセャA_セセセーエ L@ & Scope セヲ@ iョ _・セ・ョ、・ョエ@ Eng!neer ..................................................................... &2 . ... Mセ@ .. .. .. ... -. .. ' . ' .

· 20.2 Payments セ ッ@ iョ、セー・イゥ、・ョエ@ セョァゥョ・ ᄋ ・イ@ ... , .. : .. ;·:·: ............. : ... : .......... ;.: .... セ@ .. : ........... : .. ; ....................................... : ........ , .. : .. ,.-.82 .

· :Zo.3 セZ セiセ」セ ュセ _セッイ エィ ᄋ ・@ セ セセ・ー・ョ 、セョ ᄋ エ@ セョァ ゥ ョ ・セイ@ .......... : .. .'.: .. _.: .. : ...... :.:: .. : ............................. : ... : .... ;:: ................. _. .. :::., .. :.::·' 82 ·

RQNᄋセZZ[NZZZTセイAANNセQセセセZ[ZZコZZZ Z ZZZᄋᄋZZZZᄋZZZZ Z ZZZZZZZZZᄋZZZZZZZZ ZZ ZZZZZZZZZZZ ZZ ZZZZᄋZZZZZZZZZZZZZZZZZZZZZZZZZZNZZZZ@ :::::: ::::::::.:.:: ... ZZZ Z Z N セセ ᄋᄋL@ ..

セI N[N@ '

.. セ セセ ᄋ ᄋ[ᄋZ@

.- 21.1 Ownership durtng th.e Concession Period ....................................... , .......................................................................... 84 · .. ·· . .. .. :.. セNL N@ ·.: .. NMセ@ .. . ,,·., .. Lセ L セᄋセZNセ@ .• セ N MᄋMN L NZ@ .• , ··., .:: .... セ@ .. , ', •v···.········.-•:• セ ᄋᄋ ᄋ@ .. .,.., .. : .. .• . ·· ........... · .•. ,: セセᄋ@ ... ,·, ., •. · .. ZセNLᄋZZ@ .. セLNL@ ᄋ ᄋ ᄋMセG GGᄋ G BBG@ .. . · ' " ' • .. :·:. , . . ·· :

21.2 Concessionaires Obligations ................................................................................................ · .......... ,;.;, ... , .. " .... , ............. ,. XT セM

• . ...... !;

21.3 The Lead ULB's.obligatioris ............................................................................................................................... セ@ .. ......... 85··: . セ@. . . セセ@. . . . . . . . . l.li セA Z@

PART· IV- FINAN.CIA.L COVENANTS ....................................................................................................................... : .......... ... .. . , ... 86.:· セ NZZN@ ::2 22. Financial Close ... : .... : ............ .' ............... : ........................................................................................................................................... 87 :. セ@セ M. 22.1.Financial Close ........................................................................................ ; ........................................................................... 87 セMZj@ · .. · セ@ . .- ; . . . . . . . . . . . . . . . . . . : . . セN@ ゥイ ᄋᄋ セ N@ ;J .

22.2 Termmati.on due to failure to achieve Fmancial Close ....................................................................................... 87u • .. ·' r d:

23. iョ ウ オイ。ョセセ@ ......... : ........... · ...................... :· .... .'.: .... セ@ ........ : ...................... :' ......................... : ............. :.: ......................................................... セセ ᄋyNᄋZN@ i' :_) セセ@RSNセ@ ᄋ iョウオイ 。ョセ・@ .. , ......... : ........................ _,_ ................... .' ................ ,_,_,_,_ .. : ................ .......... : ........... _,_.' .......................................... : ........ 8.8 ..

NZN ZNセ@セ@ .. ;

>--23.2 Notice of the Lead ULB ................................. : .................... セ@ ............................... : ............................................................. 88 t: . . ·-· · ... '· . . . . ,' . ") N ᄋセ@ . 23.3 Ev1dence of Insurance Cover ....... .-....................................................................................................................... , ......... 88 \ :S セセ@ ·

. ·23.4 r・セ・、ケ@ for failure to insure .................... : .................................................................................................................... XX H_ZヲN セ@ セ@·.. . . . . . . . . . . ·.-- ZNキイ セ@ =, ZNZN セSNU@ Waiyer. セヲ@ sオセイセァ。エゥ N セョ@ ............. セ@ ...................... : ..................... :·· .. ·:·: .................................................. : ..................... :·:···: ..... B9 ·.· ZZZ セO ァ@セ ウN@

23.6 Concesstonaire s waiver .................................................................................................................................................. 89 o z · ... · ·. . . . . . f:l. z

23.7 Application of Insurance Proceeds ............................................................................................................................. 8.9 1.:1 セᄋ@. . . ,A .. セ@

. 23.8 No Breach of Insurance Obligation ........................................... , .............................................................. ................... 89 :-'. '\ c£ Z セ@. Gセ@ \ JO 3 't• セ MMMセ@

24. Accounts and Audit ....................................................................................................................................................................... 90 \.( .. • J.l:8 セ@. . . LMセ e@セ@

24.i Audited accounts ............... : .......................................................................................................................... : ..................... 90 {< .ig セ@. . . . , .. G LNNNNN BMセ@ セ ᄋ@

24.2 Appointment of auditors ......................... : ...................................................................................................................... 90 ·· ·11 セ@

. Z4.3 Certification of セ A 。 ゥュウ@ by Statutory Auditors . .' ......................... ., ............... ............................................................. 91'

24.4 s・エセッヲヲ@ ................................................................................................................. .' ........ : ........................................................... 91.

PART V- FORCE MAJEURE AND TERMINATION ........................................................................................................... セ@ .... Yセ ZZ L ZZセ@ セ@

25 F M. M セM M MB@ Mセ@. orce ajeure............................................................................................................................................................................... .. . . セセ QP LA@ •• , ..... セ セ@ :\':Cn

· RセNQ@ Force Majeure ....................................................................................... ;_ ....................... .................................................. セNm|G@ .AGIRI セ QZjni cAp N@

25.2 Non .. Political Event ..................................................................................................................................... ............... ........ 93 · ·}

·25.3 Indi'rect Political Event ................... _,_ ......................................................................... _,_ .................................................... 93 ' 1

25.4 Political Event ...................................................................................................................................................................... 94·

セ M G@

..... セ M .. ᄋ ᄋᄋᄋ セMᄋ@ ...... ,, ' . • ... ..., .... __ L N セ ᄋᄋ@ . . J., ..... '" ......... . .

-

ZZセ セ@ セᄋL LN セMイ ⦅N@

L Zj ⦅セ@ ... : i I

·.i

.t ·-· •.•• • '• •• .. セ@ ....

.... ..... . .. . ᄋセᄋBZ@ _· ... セセ@ ...... __ : .. ... .. ·.: ..... ' • . ._, ._...-. ;... .... G^ᄋZゥN ZNNLN[N NLZNNu ZN ZNNNNNNMNセZoZZNNjセセN [ セZ セ MᄋM[ZNL [NN@ .... _. セ@ ... ^セ N セ セセ@

25.7 Allocation of costs arising out of Force Majeure ..................................................................... , ................... , .. : ...... 9 6 • • •• • • • • • • \ • .: 0

25.8 t・イュゥョ。エゥセョ@ Notice for Force Majeure E\fent ......... ; ....................................................... : ..................... Zセᄋ [ ᄋ[@ ........... $7.

25.9 Termination p。ケュセョエ@ for Force Majeure Event .................................................................................. ;/.:: .•. ::,= ..... 9·7. ;

25 10 D' t o 1 t. · · · --· ..... "98··· . • l!?PU. e Lセセウッ@ :U ,10n ............................................................................................. : ........................................... ::"''".'"":" .. .

25.11 Excuse from Performance of Obligations ........................................................ : ........ : ................... :.: .... Z ᄋ ZZZ[ ZᄋG セ ᄋZᄋ Z@ .... :98

26. Com'pensa.tion ヲッセ@ Breach oi aゥゥ・・セ・セエNG@ ............... : ..... ,. ..................................................................... , ................. :· ... : .. ... .-... ::99 .

26.1 Compensation for default by the Concessionajre ................................................................................ · .......... : .... ' .. 99 . . -· - .

26.2 Extension of Concession Period ....................................................................................................................... : ... :.; ..... 99

26.3 Compensation. to be in addition ............................................................................................................ :.:":_ ... ZZ Z N Z セ@ ... Z Zセ ᄋ ZZ M ?9_. .· _ ·

26.4 Mitigation of costs 。ョ」ゥG、セセ。ァ・@ ...... : ................................. .' .... .' ........................................... : .............................. : ... : .. .' ... Yセ^@ .·.

. ·::

:. );

t· セ セ@o::.:n.,.

I.•J :. i z H[セ@

: () .. セ セ@. V' ᄋᄋ セ サ@

' セエI@ ᄋ セ ᄋセᄋ@

27 S . f c . . ' . . h . . 9<> ........._ ;- "': . uspenston o oncess1ona1re s Rtg ts .............................................................................................................................. ,.:. . セセ Zj@ .. . . . セ ᄋ@ l

27.1 Suspension upon Concessionaire Event of Default.. ................................................................................... :.: ...... Yセセ [ᄋ ᄋᄋ L N@ 9 セセ@• ·. 't'•'l \ (.)f..t ..

• . . . . , ·'· 1:.! I . 27.2 Lead ULB to act on behalf ofConcessionaire ........................................................................................................ 100· ... " .> I:) · .

27.3 Revocation of Suspension ........................................ : .................................................................................................. 100 . ᄋセ ^@セ M

27.4 Substitution ofConcessionaire ................................ : ................................................................................................. 10CI :>

27.5 Termination ............................................................................................................................................. : ........................ 10l. セ@ • • 0 • • •• \ セ@ Ci.

28. Events of Default and Termntat10n ................................................................................................................................... ... 102 ウ | セ@ 0

28.1 Events of De.fault ................... :···: ............................................................................................................................ .' .. : ..... ャoコ H WOfjNセャ@ セ@. . . セ ᄋ@ セ@

28.2 Termination due to Event of Default ..................................................................................................... : ................ 105 .&. o:: 0 • • 0 • ?

28.3 Rights of the PartiCipating ULBs on Termination .............................................................................................. 108 !;

28.4 Survival of. Rights of Parties . .' ........................................................ : ......................................................................... :: .. io8 9· 2 .;:·· . . .. / "5

29. Divestment of Rights and Interest .............................................................................................. , ........................................ 109 エ セ@ Mセ@. ' . N セB B@ GO セ@ .? .

29 o , '/ I '/0 :SO .1 Divestment Requtrements .......................................................................................................................................... 109 '1J·I) . 8': セ@

. セセ。@29.2 Inspection and cure ................. , ..................................................................................................................................... 110 /:"ll E g

, lセ o@ セ@. . . - . .,_, s: 29.3 Cooperation and assistance on transfer of Project.. ......................................................................................... 110 , .. .( e

. セ@ セ@

29.4 Vesting Certificate ... : ..................................................................................................................... .' ....... : ................ : ....... 110 J. セ@

29.5 Divestment costs etc ...................................................................................................................................................... QNセ L⦅@ .. . . t, ") ,.,. ..

30. Defects Liability after Termination ..................................................................................................................................... 1 セ LG@ ᄋ ᆬ セZ@. . . . . . . ' h N ゥセLQ A ssZ|ゥヲセヲNh@

30.1 L1abthty for defects after Termmatwn ................................................................................................................... l,:r ,,. QQ Lセ[@ ··m . セ NQmwa@ .Al-,,RI .;., .. !"'' J

PART VI· OTHER PROVISIONS .............................................................................................................................................. : .. 113 ·

' ,, セᄋ@ \'.''. • ,.:• :- r ·: ᄋ [Zセ@ ;' :"'- ..... セセZ⦅ZZ[ᄋL@ .. · · • セG@ ·, '• !• ᄋ[Zセ@ '' ., ... セᄋZ@ :;,;',, セ Z@ •:·: Mイᄋ ᄋᄋ Z ᄋ セMZM[ZGZ_ セ _[Zセセ ᄋ@ セᄋZMセ ᄋ M ᄋ ᄋMᄋZMセMMセMMセセZZN セセ セセ[@ • ;_:·.;·:,: .•• セ|LᄋZᄋᄋᄋ[B@ :; •• : < ''.'1 ... :. l > Qェセ@. ,_ ...... ... ...... : ............... :: Mセ ᄋ@ ᄋONZセ@ ;. :. . .. ᄋZZ[セセN@• •• •,,, , • • ••-· '" ,.,,, ...... ... .,_,_,.._. .. , セLZ@ .,, .,., o'.',, ... ᄋセ@ .. ., • .,:.;. . _ ; • .,. ,. ... , -.... LセN@ • •u •• ' '"' '' •" '""'•'

.• LᄋZNNNᄋ NL[ NLNLZセN@ Zセ@ •. :· ... l.:-.:_.·..:;.;. .... M セN セNNZ@ ............. :. .• MM N セセ@ • ..:. ィッセッ@ セNZN@ . ..; セ@ ... セセMMセ MMNセィ@ • . <: ...... ⦅[Nセゥ[@ .. ;. ·- ·.- -· ··-· -· ..... . :.:· .. NNNNN[セ N Mセ ᄋN Lᄋ@ • ..;·_ •. セ [LNNᄋ@ ..• . :.;..:· ............... : . •. ;

32. Change ゥセ@ Law ................. : ..................... : ...... : ................................................... :.: ..... :···· .. ······ ............................................ : .. :: .... :.:.116

32.1. iricfease in costs ............ ....... : .......... : ....................................... : .................... : ................................ : ...................... :.: ... ; ..... ll6' •. .. 't ':

3Z.2: r・N_セセ セョ@ in cos.ts.: ... : ............... ,: .. ·:·: ........ , ................................. セ@ ........ Zᄋセ@ .... _. .......... : .... , ............... : ........... : ... ; ..... ::,.,:::·: ... セ@ .. ·: 11:6

. : ·. 32.3 Z r・セエイゥ」エゥッョ@ <m cash COillpensation.;_,;: ... : ..... : ..... ;;;.; ........ :.; ... セ Z Z@ .... ;;;;;,;;;;,.; .. : ... ; .... :: ......... ;;;:;;; .. ;;; .. ; .. ; .. ; .. ;·;,;,:,.(:.;.: ... ;.; 1 J? ..

. セ ᄋS

ᄋ N@ l[|セゥセAセセ|QQ セエZエ ZZ ZZZZ ZZZZZ ᄋ ZZ ZZ [ Z ᄋZZZZZ Z [Z ᄋZ ZZZ@ :':: :.:::::::.:: •. :::.:::: :·::::· ::::: : ::··· ::.: :: ·::::.::: :::::::: :::: :::::• : ·";:\J:::i•lli: 33.2 iョ、セijャ N Aャゥエケ@ by _the cッョ」N・Nセ N セェY エ⦅ャ\[Aゥイ・ セA BB@ .. セ@ ... ,. .. _ .. : ..................... : .. ;.,.!,; ... , .. , .. ,_.,, .. _._ .............................. , .............. :, ... _ ...... ; .. ,;. 1]8 ..

33.3 nッエゥセ・@ and contest of claims ...................................................... セ@ ........ : ........................................... : ............... ZセZ@ ......... 119

•• GャッッNエNセLjNM @

. . ...

·. /'fJ, .,, GZ[エセ@

.. -.:.;'.

ᄋセセセ@.. セᄋM

"= [ゥヲ セML@NN セ セ M セA Zセ@2<.. , 92 . . (.;} ....

33.4 Defem:e of claims ................................... : ..................... ....... : ....... :·· .. :·::··_ ... : .. ᄋᄋ セZᄋ ᄋᄋᄋᄋセ Z@ ................. _. ....... ZZ ᄋᄋᄋセZᄋᄋ ZZZ ᄋ ZZᄋセ Z ᄋ@ .... ::·: .. セ@ 1 セセ M セR@ セN@

33:5 nセ@ セ[ョセセアオ・ョセゥ。ャ@ 」ャ[ゥュセ ᄋ@ .... セ Nᄋ N Z@ ............ セ N ZZ@ ............ .'.: ............... .' ....................................................... ,. ........................ _. ..... . 120 ᄋZLセ@ =j セ@. . . . . ('"··,, . d (

33.6 Survival on Termination ......... : .......................................................................................................................... : ......... l20.i. ,.,· .. 0 ッセ G@.. . . . . . . .· . ·.· ..... :. . }!!

34. Rights and Title over the Site ................................................................................................................................................. 121 Z N セ@

STMNエ ᄋ lセウウ・・イ N ゥ N ァィエウ@ .................................................................................................................................................. · ... : ...... : .... _ ..... . 121 Q N Zセ@ ·

34.2 aセ」・ウウ@ rights of the Participating ULBs and o.thers ....... : ................................................................... : ....... :.: .... l2_1 セ@ · . . . . . . \ <(

セTLNS@ pイセーセ M セ@ taxes .... _ ........... :_ .... Zセ ⦅@ ........... _.: ... : ........................................... : .............. : ............................................................ : .... Qセ ᄋ Q ᄋ@ ᄋ M[ZZ[ セ セ@ Q· · 34.4 R.est.nction on sub-lettrng ........ _. ................................................................................................................... _. .... : ......... ,. 1"' 1 NセZ@ t.\:7> ;-c. . . . . . . . . . . . . . N ZNZNNカ セ@ ·-}

35: Dispute Resolution .......................................................................................... · ..................................................................... : ..... 122 •,.,!J f: セZ@. . . =)· sa: 35.1 Dispute resolution .................. セ@ ..... , ..................................................................................................................... _. ...... : ..... _12:2 · l) ";;?

•• • • • • I'YI' ,., ... . :

35.2 Conciliation: .... セ@ ....................... : ........ : ................................................................................................................................. 1i2 t· :. セ ⦅ U L S@ j|イ「ゥセイ。エゥッョ@ .. : ....................... · ................................................................. セ@ ................................................................. ; ............ 1 i z,. ....... , ·1_1 ''.

·35.4 Enforcement of Award ....................................................................................... : ........................................... .-......... : .... 123·' j 1 4;g Mセ@'.·.. . . . . . セMMヲGQ ZZᄃ@

35.5 Performance during dispute ...................................................................................................................................... 123 セGャヲ ゥGゥ@ ·.; ·· . ·. . . . /fi.' f@ セ@

36. Disclosure ................................................................................................................. : ..................................................................... 12.4 ·)t'3 セ@

, ... t '" 37. Redressal of Public Grievances ................................................ : ............................................................................................. 125 . ]. セ M

· 3 7.1 Complaints. Register: .. ·.··: .......... : .. ; ... : .... _ ........... _ ......................................................................................... : ...................... ,i\2 UO セᄋ@ .. ::)

· 37.2 Redressal of complaints ......... .-...... : ............... : .......................................................................................................... : ... . NQセQRᄋ@ セ Lᄋ a Z ZNNNMセMᄋᄋ[@. .· . |ゥGNNMセ@ -

38 M. II ... . . . . . · · . セ セ ィ ᄋ[ エウセNZNj Aセ ャZ[ャ@· Jsce aneous ........................................... ; ........................................................................................................................... ma_セga@ .fGIBl t,\UiliGiP.'I

38.1 Interest and Right of Set Of£ ................................................................ .................................................. : .................... QセV@

38:2 gッカ・ セョゥ ョァ@ Law and Jurisdiction ........................................................ .' ............................ .' ....................... , ................. 126\ )

. 38.3 Waiver ............................................... : ..................................... .-........................................................................................... 126 ᄋH セN@ , セQ@ !,' .•

:::: セZZZNセセセセセZZZZNZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZZNZZZNZNZ@ ::.::::::::::::: ::::::::::::: :: : :::::.: : ::::::::: : セ[ | ZセZセBGᄋN@:?

! . . i

. ........ ··-·

- ,"-.... '

··•· -·· I

•.

., ..... _ ..... ᄋセᄋMᄋᄋᄋMセ@ , .... , ___ : --. ----. -:-:-. - ---,-- .,-.,-...,.-.-,.-,..,.....---.,.,-..---" ... セ N@ MMZ セ BWB セ セセ NLNN M ·":::" .• "\'.-· M セ ZセセM セ ᄋML ᄋBBセセ G MZM [ZB N セ BBャゥG GMGZG ⦅L GABGAJBBBBセBBGI G セ NZ ZZゥBスセ@........ ;..-::.. ... . ; セ@

-- ··-- ___ ... . - ··-··- _ .............. -· セ[NBZN@ .• < ..... セ@ .. . -- - ,....; MNセNカMセMNセM ........... MGMMM M ᄋセ@ ... --• ....,._;;a.--:-":"uo.:."". . ... セセMLNN@ セ@

38.9 w。ゥカセイ@ of immunity ............................................................... : ........................ _. .................. , ............. : ..................... ZZ ᄋB ェ B Z N セ N セ ャZZ N セ N@ · · ·· .· :jj 38.10 Depreciation and lnterest.,. ................. : ....................... : .............................................................................. : ....... :: .... /129

38.11 dセャ。ケ・ N 、@ pay;rnents ........ .. : ............. : .................. , .............................. ... : ..... , ......................... , .................. .. : ............ : ... ,. ...... , .. ャN セ セMY@. . .. .. : ... <. . セ A@ ' . .... セM . ' ' . . . : .. . ' . . . セ@ . ·. ·!.7 '· . (:', ·::.: [セ Z M ᄋ@ '• .

. 38.12 eク」ャセセセッセ@ セヲ@ 1mphed キ。Nョ[。ョエQ・ セ@ etc ... ,.; ................................................................................................... ZZ[N セ@ ......... M QセNY@ .. _. ..

38.f3 Entire Agreem·ent ...................................................................................... : ...................... : .. _. .................. セ⦅N@ .... セ@ .. :;: .... ....... ii9..: ·. . ... . . . • . .. . . .. . . . ·. . : .. . :_, . ·. .. . . ' : . : •. ·::;·.i.:,·.··

· 38.14 Third Parties ............................................................................................. : .... ; ................................................. , .. .-: .. ᄋᄋᄋ セᄋ ᄋ@ .. NQLセY@

..... ^ セ@

M セ ャNBG@

. セ セ@

セ@ .. セ@ ` セ@· 38.15 Successors and Assigns ............... : ... : ....... : .... : .............................................. : ......................... _.; .................. :.::·;.-...... :; ..... セ セ ZQ ⦅ P@ (':; 9.::;

schZ[セ[ZZZセセセ]ᄋZᄋ Z [ZZZ ZZZZZZ@ .. ::::·::·::::::·:;··:: .. :::_::::::;::;:::··:::-::-::·::;:::::::::::.::::: .. ::::;:.:;.;:::: .. ::::· .. Z ZZZ ZZZZZZZZZZZZ ZZ ZZZ セZ セZZ@ : エエゥ ᄋ Z[ セ Zャ@. ·.·i ·I ·J o t.t:-:

1. Site of the Project ..... , ................................................................................................................................................ : .................... Qセ ᄋ Z TM ..•. / _Nセ[ NZ@セZエ Z@ -.: セ B@ . . 1.1 The Site ................... .... : .............................................................. : ........................................................................ ................... 134 ·

1.2 Sites for Waste to Energy pセッ」・ウウ ゥ ョァ@ Facilities in Andhra Pradesh ...................... ; ................................... ... 134 ·:r.

h • k.

1.3 Inventory oft e Site ..... : ........................................................................................................................................ : .......... QセZT N@ . . .. :• . . .: .·.' ,.;· セ [@

2. Applicable Permits ................ _. ....................................................................................................................................................... 12:51 セB ᄋᄋセセ@ S. . . ., A .se .

2.1 Applicable Permits ............................................................................................................................................................ 1:;5 --::- ᄋ セ@ : :

3. Performance Security for Construction Requirements .................................................................................................. 137 セイ セ@ セ@ · . . セ[@

4. Performance Security for Operation & Maintenance Requirements ....................................................................... 14·0 , .. . .. セ[ᄋ [@

. . :'!(

5. Project Completion Schedule .................................................................................................................................................... 14-3 [ セセ@. . . . . セ@

5.1 Project Completion Schedule .................................................................................. ........................................... : ....... : ... : QT Z セセ ᄋ@. ... |NNセセ jN セヲ@, . . . . L. セᄋᄋ[@ ᄋNᄋカNj セ@ ·.

6 D . 14 1:' \'' .-..,:-'f:; . raw1ngs ..... :..................................................................................................................................................................................... ·;, - ···,-'f.=: ·.· . . _,..,.{ ,;; ·.

: ZZZZAZZ[ZZセ セ] セ]NセZ Z@ :::::: ::::::::::::::::::::::::·:::· : ::::::::::::::::· ::::::::::: ::::; .. ::::::::::: :: _:::·::::: :: ;:.::: ' ::: j! l l;(I; ·

8.1 Completion Cettificate ......................................................................................................................................... : ........... ャ N \|イB セ C ZZ@. . . セ セセ Z@

8.2 pイッセゥウゥッョ。ャ@ セ・イエゥヲゥ」。エ・@ ...................... ...................... Z N セ@ ............................... : .. ··········· .. ···· .................................................... セTX@ セ M

9. Construction Requtrements .............................................................................................................................................. .. ...... 149 ·

9.1 General .................................................................................................................................................................................... 14-9 · t . ·. ··, t . セ@ ..

9.2 Processing /Scientific Landfillfacili.ty ....................................................................................................................... 15-p·:· ·· , . \ •.h<. セ@ ·.

9.3 Procedure ............................................................................................................................................................................. 15 3: .. ·.:,\ !:t . 9.4 Schedule for Land Requirement at the Proposed Site ........................................................... : ............................ 15 f 0,: ·. ;:: ·

.. I •··· ' I , ... .

10. Operation and Maintenance Requirements ................................................................................................................ , .... QU N M セ [[MZサNセ@ ,. ᄋZセ@ .. · r·;

10.1 Genera1 .............................................................................................................................................................................. :.156 '·,, •···;:\: :. セ@ .

Mセ セ M hNZセ@ .... セLNセイᆬ セMMM.

1 · -.;

セ@

.••. -. ·• · .. ZMセL[@ •. セ@ ...... _, .... _ ⦅NN LLL⦅Nセ@ ..................... J セ@ -..... ;-J- • ......... • .. セᄋ@ .... : .......... セ@ .. ;. ... .. MGᄋセᄋN@... -:·.- ....... ..... .. .... セ ᄋ@..... ···-· . . セᄋ@ . セᄋ@ ... • .. ,

10.4-Cleaning and Maintenance Requirements ............................................................................................................ I 58

10.5 Monitoring Procedures ...................................... .......................................................................................................... Qセ [ X@

10.6· Management of L·abour.and Prevention of Accidents ..... : ................................................................................ 15.9

10.7 Facilities an'd Benefits for the. Work Force Employed ..................................................................................... 159

[YM_LNtセゥNョゥョァセ ⦅ sアセゥ。ャNpイセセイ。ュュ・ウ@ and Public Grievances ...................................................................... · ... : ...... : .. ; .. 160

11. Operational Plan ................................... : ......................................... : ......................................... ,. .................................................. 161

12. Performance Standards and Damages.-..................................................................................................................... - ...... 162

12.1 Performance Standards ....................................................................................................................................... .-...... .. 162

I.

, ..... セ@

(.('; t VJ --:v (

(): <n = .........,_ (;') セ@

12.2 d。ュ。ァセ ⦅ ウ@ ..................................... : ................................................................ : .............................................................. セ@ ...... 16'4 . セ[ M

13. Safety Requirements .............. : ................. : .................................... : ............................................................................................ 167 !

13.1 Safety Requirements ....................... , ............................................ .-.... ............................................................................ 167 . .

14. Environmental and Social Standards ........................................................ .. ........................................................................ 17 1

·14.1 Environmental Standards ............................................... : ..................................................................................... ...... 171

14.2 Social Standards ....................... : ........... : ....................................... : ......... セ@ .................................................... : ................... 17-4

15. Waste Reports .................................................... : ......................................................................................................................... 176 ·

15.1 Report for Processing Plant ............................................. , ................................................................................... : ...... 176

15 .. 2 Consolidated Monthly Report ............................................................. _. ...................................................................... 17:3

15.3 Schematic Drawing of Weigh Bridges Locations_ ...................................................................................... ...... ... 17l3

16. Scope ofWork of Independent Engineer ........................................................................................................................... i_セI@

16.1 Role of the Independent Engineer.' .......................................................................................................................... l7<J

17. Vesting Certificate ................................................... _. ... : ............................................................................ , .................................. 18;!

- 18. Substitution Agreement ........................................................................................................................................................... QX セ Q@

18.1 De'finitions and Interpretation .................................................................................................................................. 18L,

18.2 Assignment ........................................................................................................................................................................ 18S

18.3 Substitut ion of the Concessiona ire .......................................................................................................................... 18:.

()" セ|@ ( ,,, ,. ,;.'

.,

. r .; セ[@

18.4 Project Agreements ........................................................................................................................................................ 18c: . -: ·;..,:;.:

lasT . . fC . A 18c-C _ ⦅Yセ@. erm1nation o oncess1on greement................................................................................................................. <; r.: ._.

18.6 Duration of the Agreement ......................................................................................................................................... 189 セ@

18.7 Indemnity ................................................ : .......................................................................................................................... 189'., . セHN@

18.8 Dispute Resolution ................................................................................................................................ " ....................... 190 セセM ··-

89 11 }\·: ;;\.

1 . Misce an eo us Provisions ............................................................................................................................................ 190 ,. .::.·

.,...-·· ·

·-:-.··· .. ·-·--.. ·-:-· ᄋセᄋᄋZᄋᄋMMZMMᄋ M ... . .,..-..,,,._. -.. ...,....,....---......, . NLN L MLL⦅セ L M___ -.-.'"" ........ "" __ セ N M .. ZNᄋ ZZZZZセ@ ... .. ... Zセ ZMN ᄋMZZMZZi ZZ セjゥ ゥ [t ZZセセjセZᆪi_セヲW W エZセZN Z@ .. L[| [ セエセ N@

•,U ,, __ ... ⦅セᄋMNLセᄋMNZN@ ,,.·,. , セMセLセLNM ..... セ[@ • ., ᄋ N| セMZLNᄋMNッNN ᄋ L[@ • ._ .;: · .. L[ エNᄋセZZNNN ZNZNMMNᄋセ[ L NL⦅ᄋLゥ セ@ • N[ ⦅L LセャZNZセッNᄋLN[LB Z ⦅LL⦅ᄋNZL@ .. Z NZャN Z セセNN⦅L@ .:. Zセ|M ,;,...,;._ .,.:, .;.·,. .. セjZLLN@ t .• LL LNLNL[LセL@ ..... セ@ .:. • NNZNLセNNN[LNNセ@ ... p-..._ •• .:,...;.,.__ ... ..; •• L N⦅ [LNNN[N L⦅ ᄋN ZNZ NN[⦅セᄋ [Z セGゥゥNZNNZNZNZN@ •• AッᄋセセセエキセセᄋNB ᄋ セNNZスN[NッG[@ • • NLLNLセ[ケNLNLL⦅セセセ@

PART I- PRELIMINARY

. . ·,

N Zセᄋ@

エNセ イ ᄋ ᄋ N@l ')·i

.:· \ .... /

....... ';. セM[@. .... ZセMM \

・ッャセlyセヲ。イイNj[エ ᄋ セ@ anセhゥゥaエ^rapセウh@セ@ •• ';}o ZNuセ@ ..... セャャ ッ@ ... S :-;; .. | ZMZZZNセ ッL ⦅N ー@ ... t:\11> iool.:. · : · · . · セャゥZ[ーエᄋ・NャセセエLセ ウNセN@ r N セィ@ Nセイッ@ ... R..' ·t-< • .skq,. mq セ M. MセセLセセ@ エ [\[エセ ヲANL@ ___ [ZyNイNョᆬ ᄋᄋᄋ Nオイ「Pセ MM MᄋwッNm・N NN@ . セセセセ@ ·.\§uiT\Qv

CONCESSION AGREEMENT a . , . A . . . .

. . セM[セッ セ@ )·.· ᄋ ᆪBエカセョ^@ 」セセ 」Zァセ[@ .;5<J<5

NM」L ᄋHAッエUjセ@ 10-0Z·Q;O:it) セセM • • • !1,1 セAZZZ G@

e55_C3o. f.'ili: gw!,.t;}!

. -6COJi'-"•Y.:k.JO::.:s :

. . セ Z@ ... , <:...::.· 'cjf . .;.,V .

r-:;6. オッNェ[[ェZセ@ セエGャセセ@ · セ M

M セセ ᄋᄋ@,. '•. 0 <( . _. ... £, n \ ..... ...- セ@ tU,

t:.'l .

. . . lA.. (l,.t fl THIS AfREEMENT is made on this ft.:-=-· day ッヲセ@ Two tィッオウセョ、@ and Sixteen at 1ft. -t :

h- :

•'' Mセセ \@. . ....... NNNセ[[L@ :

BETWEEN V; ·.· ....... ! ,. {t. -.11'' ᄋ ᄋ セ@ J

. -. · Guutur Municipal Corporation; Vljayawada Municipal Corporation; Tenali Urban Local Body .· セ@ '§ · · Chilakulurlpeta Urban Local Body; Sattenapalli N オイ「セョ@ Local Body; Mangalagiri Urban Local Body 」セMゥイM ャ@Narsaraopeta Utban Local Body; Ponnur Urban Loca• Body; Tadepalle urban Local Body : 」セ M .. セ@ Yl

·. . AND セセx@

Jindal Urban Waste Management (Guntur) Limited a cッセー。ョケ@ incorporat17d under the Companies· aセエ セ@ セ@ セサェ@1956/ j013 。ョセ@ having its registered office atA-1, U.PSIDC Industrial Area, Nandgaoil Road, Kosi Kalan, セQ@Dist. Mathura (Uttar Pradesh)- 281403 (hereinafter referred to as "Concessionaire", which expression ,., ···. _:£ shall, ugless repugnant to the context or meaning エィ・ イ セッ ヲL@ mean qnd include its successors and permitted セ@

assignsJofthe OTHER PART. · ·

The GJhtur Municipal Corporation, Vijayawada' Municipal cッイーッイ。セゥッョL@ Tenali 'urban Local Bod}i.,'· -.\··

· Chilakaluripeta Urban Local Body, Sattenapalit uイ「セュ@ Local Body, Mangalagiri Urban Local Body ; セ|@ ·

'Narsarlopeta Urban Local Body, Ponnur Urban Local Body, Tadepalle Urban Local Body are/.·.\·:. セMセ@·hereinafter referred collectively as "Participating ULBs"e· each of individually as "Participating ULE" · ··.··. Mセ@ ·;,.

and CoJ:essionaire are hereinafter referred to individuall as t e "Party" and collectively as the Bp。イエ ゥ ・ウセ NZNZZ ᄋ NMセセᄋᄋNZᄋ[Z@ . . . . \ - ,r-.. , ' ...

: セセᄋ@ 7 セ O@ \: . ·--· GN [VOカQmゥウMᄃャP[[セ NZ |G@({;.}}ilAK·',l.VRIPET ML': !·C セ NN@ .

. ' . . · ..

. ! . ,

( ...

·- ·· .. · . . . . . . ... · ..... ·-· . . . .-·.: . .. · , :· . .. : .. . . . · .. .. : . セ Z@

• • • • :. : · · • .- l

.· .· · ... ··-.

.. -.":· ... セ@ : . : . . ··': '. · ·.· .

,: ·. ·. ·.' '·

. .' NMセ@ · ...

-.· . .

., . ',· . . ᄋ N ᄋZセNZ@

'I ', ·.:·'.··,''-',

-.......... -.. , ·· .. · · .. ···. . .· . . .. :. .. . . . .·. :-: ··.. . .

. . . . ·.·. .. . ' ··. >. セM ᄋ@ . .': · .. ;::; . . .. . ·> ... :. セNZ@ . . . ·. · .. ' .:·-: N ᄋ Zᄋ[ᄋZM[ H セ@

t · /; • .:_.,. __ •. .. .· .- ウN [ ᄋ ャゥセサカゥOッセエeセセ M セセセェ ᄋZ セセPセゥゥ。ョ Z セセ@ .. ·-' ·. · ·; .·. _·. }:·:. · _:: .· :·.-_·:. ·._.. . , :: . ' ·' · ' · ·.-· ·. .._ ._·: . , . M セ G@ ·,:·:·;{

. . · · ... · . ᄋᄋᄋセᄋZ@ [Nィセ ᄋ Zエ「イQ ᄋ セセ M セセ セ ᆬセ Z セ@ i [Z セ ᄋ セbセ ᄋ ゥ ⦅ ゥN ⦅@ セ セ MZ セセゥヲセヲセセ[Z ᄋ セ N イゥセエゥG セ セ M jィセエ ⦅Z セ ゥ M セ@ Z セウZCNセ」ゥセ Nᄋ@ 、エゥィセ@ セイッャ・RエイN。」ゥGゥゥセQ ᄋ ゥセ@ 。ョ」ゥー Z エセF Z ・セウセウ Z[ NZN@ ;_ ZZ セ セ セ [NZ セセMZZセLヲN@: . · · ・セjIjーケN・、 B ゥイゥ@ _:the: セッョウエイオ」エゥッョ@ •. ッー・イセエゥッョ@ a11d nraintenance the.reof.shall ·conform with: the .laws , . ::;: '$:! ... "

· . : · .. ᄋ ーゥュ。Hセゥセァ M t9.. セョカHイッョュeュ@ .. t:: ィ・セゥエ N ィ@ M セセ\ヲ@ ウ。 N ヲN・エケ ZZ セウセ M セ M 」セウ NG Qョ N 」ャオ」エゥゥゥァ@ ·l:ules :stich 。ウGIセウキ@ ZN セオゥセウ N@ zo'oo, .:. : セMM セ MZ セ M ·. :· ᄋMセセ@policies and gmdeHnes nilated.thei·ei:o:.Tne ·concessionaire ·shall obtain a·nd inaiota.in from tin1e to . セ@ ·;'S ... J

·:: N エ I ュ・。ゥャセセ」・セウ。イケ@ 、・。セセョセセウ ⦅ 。ゥ@ セセZ。Lョ・セ@ ゥセ NG エィセ Z D」「セ、セャセ ⦅ RL@ . '· · _. . - .. :· ·: セ、 [ [@ . [Z[セ@-·.: .. .. ·.·.•·· ,. ... .. .... ......... ... . ._, .. ,. . ... ,., ....... . .. · .... , .... ; ... _, ... , ... , .... , .. , ... ,., ... , . .., ... ,. セ@ .... , .. , .. .... ァZ ⦅LN LMLLK\セ Z@. . . .. .· ,. ' .. ·. ·. . . . . .N:[_, 0 w t

5.4 LaiidUse ·_.··.·: ., · ·· . _·_- ·. ·.· : .. :.:· -.. .:: ... , .. , ... ..-. . . , .. -....... ::" ·"··.---................. _ ... , ..... _.·.· ... \ セ MN M • .-·-

... ·.· .· .. ,·: . ....._,,.. · .. · ·, .........

·, .; . ᄋィ セ ・ ᄋ@ cッョセ・ウウゥッョ。 N ャイ・@ M ウセ。ᄋャ[ ⦅@ ・ セセオセ・@ ᄋ 「セセゥ M ゥャIオセ N@ ゥエエゥャゥセ。エゥッー@ M セ ᄋ ヲ@ the セゥエZ@。セ」A@ ゥセュ、 ᄋ@ セカ。ゥャ。「A・@ セョ」ゥ@ shall ョッセ@ ·. セ@ · ; . . . • • • . . . . • . ". . . . . . . . . . . I · . ... ._

. セMMN@ . · ᄋM オウ」 N Z Nエセ・ N⦅ セ。イZョ・Zヲ_イ Z セョケーセセーセセ・ M セ ⦅ セ」セョョセセエセ、@ セイZ ᄋ キNィゥセィ N@ is .riot .. ゥ N ョ」 G ゥセ ⦅ ・ ⦅ ョエ。Ni ᄋ エッ@ エャセ・ N@ Proje.ct or relate_d_ .. セOF@ .. ,. . - · : <g:tiv.ities; fッイ⦅。カッエ」Gャ\A ョ・ セ@ l?f doubt, ·any:land'.given by the L.ead ulb M セッ@ .the; \[ッョ」セウ N ウゥッョ。ゥイ・@ Jo,rth1s セ@ 0 .' :

·. . . . ーセセJ M セセ ᄋ ウィ Z セャ ⦅ ャ ⦅@ セセエ@ _b_e. オウ・HエセH ⦅ 、・ Z カ・ャッ ᄋ セ ⦅ ュ・ョセ N アイ ⦅Z セセウセセ セ ョセAセゥ@ セイ ᄋ 」_ N セセセエエゥ。セ Z@ facilfties or:pr.emises ヲH^イ L⦅ セTセ@ 3 MセM

: .. ·: ·

; .

:'.

. . .. . ,' · rel}t,.lease or ウュQエ N ャセイ@ purpose: . :. : . · .· · . . . · .. . ·, : · . . . · .. · Hセ@ セ M · .

.. • . · .. ·.··.. .. : ,;, . ' ' i ' . ' ' i . . ·· . . .. . · · ... · > . . . . Z セ@ SZセQ @ . . ·· _· · s:s. pイ ᄋ ッ」・ セセセゥ ゥゥセ ᄋ ッゥセセキ Zᄋᄋ@ :: ·:..,· .· :._ .:· .. __ :·. __ :_··:>.-·::·_.·. M^ セ@ ZセZ ZNM ᄋ@ -_:, .. :.-.·:>:;; :-·: · : .. :--· · · · ,; ; .· . : .. _ .. · . . '. : · .. .-.: . · .'. fi : ·

· · . The·i_ettin61f)gi·es ·ad6pted エ ッ セ ーエセ」 ・ウセ N@ エIQセ@ mセw@ _shil: be:ih.ose セM イッーッ ウ ・」ヲAョ Z@ the cッョ」セウウゥVョ。ゥイ・ G ウ@ Bid. · ... セ N@ _·· -,·.i! .... Z ⦅セ@ .. ' . Stlbinittep-{n' response: to エィ・jセ・ M ア|ャ・ウエ G ヲVイ@ _N ゥZ ッゥ^VウセH[ N@ ·, -.::· , . . ::. ·,,;. ". ... ':. . : . : . . ·. •. . . セ M i N@

;, . ; '. : ウZセ@ ャGセウセ ャ セZオ[・ャI」u[[hセウ@ · ' ,: ·:'" ,, • • . :• ' : · .. ' . ·, . . , ' .· .. ·. . ,,· . • . H [[ セj@

セL@ · .. . ··: :::: __ :·!.:·_\ Zᄋ セ ィ・ ᄋM セッセ」セウウゥッセセ M ゥセ・ Z ウィセ G ョ Z セャ。ゥョエ。 ᄋ ヲセ NM⦅N セセ・ Z@ セ セppセセ ZM セセ、 M M ゥャセウ・、 ᄋ N ーッイエゥッョ ᄋᄋ ッヲ@ the landfill as per |ィセ セMI ゥヲ Z ェ@

1· .. . r :· . , .. l '· ! ..

...

'. . エ・ N 」 ィセゥ」。 G イ N セ・ア オゥイ・ュ ・ゥQエ D@ 。ョセ@ セエ。ョ、。イ、ウL@ セイゥ、@ N aーーャセ ᄋ 」。セャ・@ LaW.; . ' . . . .< •

... . . ·-·.-. ᄋ ZセM セMMᄋ NM ⦅Z NZセᄋᄋM[@ .. :.:<· .. ·.• .. :·l ' •' .• · ••.

.. . . S.'7 Mea.Suremeilt.of'MSW . . ·:·. · . : . .

.. . . .· .. : ·. . セ@ . ·• .. .' :: . . .

__ : ________ ........ ----·----.. セNNZN@ ------·----. . · : .

ᄋセᄋ[ᄋ[@ ____ _ - .... -.............. _ .... _ .. .

18. Safety Requiremen-ts

: . ')

··.' NᄋZ セ@.. :,· .. ᄋGBZ セ Z Zゥ@

. . \1.1" (l,.

t 81 Safety Requirements . . . . . . .•. . . . . . ·. • c ᄋ セQ@18.1.'1 The Concessionaire shall comply with the provisions of this Agreement, Applicable l。キウ M 。 ョ 、 |LZ セ L セ@

Applicable Permits and. conform to . Good Industry Practice for securing the safety O.fthe_. · t.:1 ヲエNセ@

personnel at the Project Site. In particular, the Concessionaire shall develop, implement an<;! . q ...•. , ···-· .. .. . . . ··- . . " . . .... .... .. ...... . . .• . .. . .. . . ...'!:

。、ュゥョゥウセ・イ@ a surveillance and ウ。ヲセエケ@ programme for p.roviding a safe ・ョカゥセ Z ッョゥョ・イゥエ@ on of セ エゥ ッオ セ@ . , セ L@ ·.

the ProJeCt, and shall comply wtth the safety reqUlrements set forth m Schedule 13 (the ·· M セ@ セ@

·:"Safety Requirements"). . {セ@ o.. ., '. .·. \ ᄋᄋLLNZセ セセ[@ セ@

• .. LNセ@ v ) :':)

18.2 Expenditure on Safety Requirements |N セ@ · .: セ@- - セ ᄋN@ (t

AU costs and expenses arising out of or relating to Safety Requirements shall be borne by the

Concessionaire to the extent such costs and expenses form part of the works and services included

in the scope of the Project. · セ@ \.:

-4_._ セ@セ@

Pセ@

セ@

. 1 .. '., !· •· -.·.: ..... .•. .

..•

'' '\

· .. . セ@ ..

·,

i ...

. ' ...

·(a) . ·. . jGィ・ N 「Ajゥャ、 ャ ッァウ[ウセイセ」エゥオ@ .. es. see(ied ana plan tea 。Nイ・セウN@ paved and un-paved trafficareas ·

·. . .. : ... .... e.tc.' a•·e エョ。ャゥゥエ 。 ゥセセセ@ ·:dean ·and: ーイッセセイ@ セエ「ッ ᄋ QLQ ᄋ エ@ dainages, thannay impede' their·

.. ·. · ... · .. ヲ オ セ」 ᄋ エゥッョ。ャゥエケ@ N ッョゥセーセ。イ。セ ᄋ 」・N@ ' . : .. · ·.· ·· ·. ·. ·. .. ·. · . _. . · . · · · ·. [HG セ@. . . . . . ·.·. . . .. .. . . キ セNGHNN ᄋ MMセNNエNZZAM⦅L@

(b) :. .; · · AIJ .n{oving· pt: fjxed eql)lpit)ent· P.)1(F ri:iac!'iil}ery-_are. -ma!qWined clean and in .goo..__-40 . .'. : . ·. M キッイォゥョァN」ッョ、ェエャセイゥGN@ ;· ,',· · · · · · · . · . .

Ccr ... . セ ᄋ i@ ᄋ Z [ セ [セ[[・Nヲセセセ ャゥエゥ・ウ@ . . ・NOッセセセッVイ@ Z セ・セ[ァ・@ ᄋ [yセエセュ[@ ャ・。」ィセエ・@ ᄋ ョセ。ョ。ァ・ュセョエ@ system, ett.;•. \ .

· ;3re G ゥョウー・セエ・、 N イ・ァオャ。イャケL@ cleaned: and tpaintained. · ·.-.: . . · \ J . . . . ··" .· ·.· ...... · . ·. ·. · : . ·, .

E . ...)

. r.;.( u .

(d) : .... Every d_ay at セャッセゥョァ@ time the internal roads and ot.her paved areas shall be inspected, 0

Z 。イゥセ@ :any ウーャャャセァ・ ᄋᄋ@ of セsw@ sh.alf be N 」ッャャセ」エ・、@ and disposed of in the. landfi ll セ ・ャャ@ セ@ セs@currently In opefation."If イゥ・」セセセ。イケ@ エィセ@ paved areas ウセ。ャャ ᄋ@ be.swept .using a swee n . I セ@

. . . . Z ュ。 N 」 N セゥセセ⦅N ZZ@ _エZオᄋゥイゥァ ᄋ aセ N@ ーセイゥセ、ウ ᄋ N@ 、ャjsセ NZ@ セセゥセウゥッセ ⦅N ウィN。ャャ@ ᄋ セセ@ ·.contr.olled by sprinkling the セ セ@ ヲセ@ セ@._-:. · .. :: , ·_. ᄋ セu Z イZNヲ。」 N ・セ@ With \Vater.m SO.ll!le.c,tl_On セセセィ@ swセ ⦅ ・ーャ L ョァ@ aCt!Vltle.S .. · · . . . . . \= c8 ;.'( ·

... . "· ... . : . . :.: ·.. : . ... · .. :, ·,. ·' .. : :' . .. . . · ZM ャNセ ャ N@. . . .. . ,..

t:':. セ@

· 1 o·.s ·.Monitoring Procedur:es · :...-· · · :-. · . . . : . . . : . . ·. · .. セ@ :,

·. /. . ....

··;. ·. ·:.; . .· . . :, .

i · AZᄋBエB セ L Nセ NBBスNエ@

. t l,;J . j

G セN セ@ .. • Mセᄋ@ ... .! •

• • 1\ • ,.. • • ᄋMBGセ Zᄋ M ᄋ@ • , • '. .'.· セ@ .- Zセ Z Lᄋ AᄋG@ Q NᄋLZセセNZ ᄋ Nᄋ@ • • ·•• ·• • ᄋ ᄋM ᄋ Zセ エN@ · :< • ·• '';'.-, ZᄋNセセNᄋNᄋ@ •• ;·.';,1

•.··.·- ' . ::·-. '.', ·.!· ·.: .. · Z Z セ@ : ... · セ@ :· ⦅ᄋ LZ L | NセN@ • ·,· ·,.-.. ⦅BᄋNセNMZZZAセセNZZヲ NセGB[ Lᄋサ NBNᄋᄋM ᄋN ᄋ ⦅ N@ ''."' ·:· r· , ,. .. |G⦅セ MMセB@ .. ' • ᄋGAᄋᄋᄋ Z セ ᄋ@ ':·: ·,· ·:•;.. ' ,. ' :·:_:' BᄋMZᄋNZセ⦅ZGᄋG@ '':: ::.;c ,. ··•· • ᄋセ@ ·:·. セBMN@ Gセセ@; HNセ N@ . . . MセMMMNセキNMMMMM ᄋᄋᄋ [N N N@ •·. .. . ......... ;,. ... . :...

セMNNN@ . . ッNMM]ᄋᄋセ」@ ZLNNN[NNNNLNBセWNセᄋᄋセセZ]セセセセセMNZNZZRᄆ L NッL M[Zゥ Z ᄋ ]][LZ ZMZ Mᄋ[セ セZ セ カセ ZZZMZMZZセZゥWZM セ[N NLセZセ Z BZBZZZZセセGZZZセ^セᄋセZBBセ@:' >....:·;·"-·····

I . · ... : .. I, ...

' セ@ .

1'·: I·; I. I . . ; ... ·.

, ·

{ ..

:· . . ·:·

::

. ·.· . "' . .

·,J

.,

. . . セ@ .. '•,': •. •

· . . .:...·· .· ... .. ·}. .-.

.· ... ' .. セ@ ; .. -·- '- ..

'·.

,·.

..... . . . .... ... :·

,l .·_ ·

. ; · .. · .. .

... . :· . .; .' ·.· ·,

I • •' • : .

·. ;: ::·.

'· 1): iAャウエ。ー 」セウ N ッヲ@ 、ッGキィエゥュ セ@ of . • : ·. · ·:': Nif : · . . .. ·. OperationPerfortjl'ance . ·

. :·· . キ・ヲァィ 「イM ャ」jセセ セ ᄋZ 」 セゥ IZィ ・ ᄋ ーイZ ッ」・ ᄋ ウ N セ ゥ Gョjサ@ .. ·· . ·: .:;· :,·:: .. ;. ···::· ·· .. ;. ウ セキ イゥエNy N@ セヲエセセ@ r:a.·te of · p N ャセ AI エI Z キ N ィセョ@ ウ L セ セ ョ、「ケ ᄋ 。イイセョァセュ・ョLエsG@ : · · . ·. ·. ; : , ·. ZPN セ E@ セ 。 」IQ N@ dais G、 セ ヲ セ オャ N イ N@。イセ L 。ャウ N V@ 09t アー セ ゥ」L エ[ ッョHAャ ᄋ@ . . . . . . . . : ·: . . . .. . . . . : . .. . . . . . ... . . . : ' . . . ᄋ セ@ . . : セ@セ@ . ..

•. · ·r

· : ·.. セ@ h ishifts :· · ·:. ·: · ッ ー・ エ Z 。エゥッセp セイ ヲッイ ゥャオ ゥ Z ョ」・@. .. · secui:ity. at the rate of

. : .. PNセE@ each day's default · · ·.·

'.'

:: .. ;

. ' . .. ' : ..

Daily Repo.rt .

· ... .

... M MM MMMMMM セ MMMM セ セMM セ セセ MMMM セセ セ MMMM MMセ MM セセセ MM セMM MMセ セ MMKMMM セ MM セMM MM セ@

3) dー キ ョセ ゥセ・@ of any moduie セヲ@ the·· . ᄋ セ@ .9.0 」エ」ゥ セ ウ@ · . .. ·:: .' :.: G ッ ー N ・ イ 。エ ゥッ ョp ・ イヲセᄋゥᄋュ ᄋ 。ョ」 ・@· Pr.oi::e.ssing' p ャ セ ョ エ@ Gセᄋ@ · · . · . .. :· .· . . . . . · . ·sei;urityat the r-ate of

. ; .o>r% ・ セ」 ィ@ day's default . · .. :.:· ·. ·.·. ·· · . . . . . · .. · .··· .·

. セ@ : . ·. ···:. . ..

·' " .

. o ·aily Report

. ·. 4} i ョウセ@ rices when イ ・」 ケ」ャ 。「ャ ・ ーイ セ@ s.old · Nil · : · ·. : ··. : · in ·Jpose fotn_1 · · : · .. : : · .. . . · .' ·

oー・セエゥ 「 ョp ・ イヲッイュ。ョ」 ・@

s ・セ|ゥ 「エ GケG。 エ@ the ra te of Q.l%e ·tfi' 。ZケGウ ᄋ 、・ヲセオャエ@ .::

Random checks

· ...... .,. .. . · ...

,' ,•.

. ,

. . . : .. セN@

. .. _·

'· :··

(:.

I:<. ! .. .. i

セ@

1 I

1· .:

r· I· :.·.

. · .

... . :

• •• p

. ' ...

.· ...

· .. . ... • I • • 1 ••

. · .. . ... .... :·. p ..... .

. . · ·:: . • •••• i • : .... . セ@

,._·;·

. : :· . ..

ᄋ ⦅Zセセセセ ZイNセセセセ セセ[[ZセセセL Z ᄆセセセセ[セセセセ[[[セイセᄋNセNZセ[セZセセセセセ]セセセ@•• :. ' •' • I .· . . , , .- .. . ·. . . -r

; • • • ',' • '· .. ;· .. ·. ; ,_' '._ ·,·v •, .· ", : : • ' :'·,·, セ@ '.\ • ·. • • . i:: . ᄋᄋセ_@ .... i •. • • セᄋ@ • ' ' • ' • , : セZ@ • • ,: セ@ • • •' ' • ' ' ' ' • •, ' • • • ·' I ' • • \ , • , '• , •

. · . .' i • . • • •• :·· ··:: ·· . . ... . :· · :- .• • • •• •, • • . · :::::;· •. . セ@

.•. ·, .··, . . . ... . . . . . : . . :,, : ·. :. \:.--: .. : .. ::;, ....... ·, . . . " t k_l!.' ....

. :: :.. ·, .. : :·: .- ' ... _··:. ,: .. :. . ... · ·. ··.':.: .· セ@ ·:·, · ·. ' ' -·. · · :·w· -- QセN@

__ -::;_· .. · · .. ·.· · .. : ,_ - :: 0::·. <. · .:·: '. セ[ Z MZN@ : .. :·: ... . :. ZᄋN ZM セZ セ[ p ⦅ セMセMセゥ@ M セセ N | セセMイセセセ セ NM セI N セイ@ セ L セ@ NZ N[セ L ュAセ⦅セセセ ゥ セ セ「@ セ@ Z セウNセ@ M セイ [@ セセセイ@ 。 M セ@ B ウー M セ」ゥセセゥエゥョ」ゥ・セ@ ... : セ@ セ M. :' , _. ·_ .· · .. ·_ ·':-: _·: ᄋᄋN⦅ ッ」 セ オー 。エゥッNョN。ャ N s。セセエケ@ セ M ョ、@ h・セAエィ a、ゥョ サーヲウエイN。エゥッセゥサosh N aIN@ · · ·. .·. · . セ@ ?: -

· · · · :· · ••• ·.•··. · · .. · .. · > .. (gj. ·:· .. : ' cッョ 」・ゥセセ セ セy セ@ [ [セゥ\iゥ@ Z ーイッjL ォ ᄋ セセ セ M ᆬセ[セ エ。I[[@ ヲセィ[セ L」セゥ@ · 。セ、@ ヲャCセュ。「@ Mセ セセ Mᄋ@· · · · ·-. : · .. . . · .. · ·. ᄋ イョ。エ ・ L ZイセゥZウ エッャセ。ァ ᄋ ・@ ·area··.as :d:esci'ibe<i' iri エィM・ ᄋ 」ッイゥエイ。」エセイN ᄋ Nウ ᄋ \セヲ・エNy@ r ・ アエゥゥイ・ュセョエウNセ ・NI@ · · .}!i

I ·. : ,.·_·.·.:.: ::: ·_ ·.· ·. . . . OセGZ@ ..... :·· .. ·. :. : ::·: :: • •. : Z セ、セセアセセ ⦅ ゥ G エゥゥGセ@ :.·fen;_; Zᄋ セィセ@ セ@ ᄋ Mーセ ᄋ ョ N セセ、 L ゥ [@ ^ セ[セゥャセセゥ G fヲO [N@ 。NZイゥa ZG ZMG エゥN G セセ@ : セ G ヲ@ . ᄋᄋ ャI・ヲNセウウ。 N ャGケ B@ .. ウセヲセ」ケ@ . M セ@1 : · :<· _.·.- --.::· ·.. _· :. · :_- .: . ; : _<_: :· _· .-: · · NM ・YセZpNキ・ N ョォエャj N Yy N セijA CN@ ᄋ ー・セセッセ ⦅ 。ャ Z@ pNイッLエエGZ」エキ セ@ equ!Bf!!:ent (PPE) and apparels for .. . <}_

I : : ·. .•. . セ@ . . . : : (h) : / ZZ[LZッZ [ ᄋZ[[ゥZZLZZ jー ZョイZZー・ゥᄋ j ゥウセゥケ@ ウ。ヲ・セ@ M セ[セエゥョァウL@ including エセ・スセ@ i . , I . :. · · .. · ;. : .: ·.· < 、ゥウcオウウゥセョ M Vヲ@ . セ「ウcセo、@ 'unSafe セッイャ\ケ[ᄋ。」エゥ」oウ@ or cッ[エ、ゥエゥセイゥウ@ 。セ 、@ a review ッLヲ セ セセ@; ,_· · · ᄋMセ@ · : · · .- · .. _. · _ 。ョケ N Zᄋ ヲィL ⦅ 」ゥセ・ ⦅ ョ エウN@ .. an.(i ᄁセヲZセ・」セ ゥカ セ@ ·_ セ」エセHI N ョLセN@ : .. a、セゥエゥッョ。 N ャャケL@ en.courage, solicit ·and Mセ@

·' ' · .. Gヲッャゥッセ@ tip ッョウ。 ᄋ セ・エIイイ・ャセエ・ N 、 ⦅ Duセァ・ウエゥッョウ ᄋ ヲイッュ@ cッョ」セウウゥッョ。ゥイ・@ employees. ·_ ·2 · . ...

(i). :. :. r・ーッエ ⦅Mセ@ ·an ゥョェセ、・ウ@ and Nゥョᄁゥセ・ョエウ ᄋ@ Jn' .a timely セ。ョョ・イ@ in accordance with .. :. ᄋZ ヲ・、セセ。IN@ 。セセOVゥZNGZNウエ。エセ NB ᄋ エ。セウ Zᄋ@ ahi:f'. イ・ァオャ。エゥ M ッョセ@ a·n,ci · the NG 」ッョエイ。」セッイ@ Safety セ M ;;_

· ... セ Z セ ᄋ ア ᄋ セ|イセセ N セセ Z エセ ZZ ᄋセZ ᄋ N⦅ LM[NᄋNZMM M LN セ@ .. :· .. MN ᄋセ NZNZ\⦅ᄋ@ .. ,·.: ·. .' ·'·; .. : ... ᄋセ GQ@ : . • · .. . . Mセ@ :' . . • , . .• a.: :f .. ... ,... .. ·. . . ·. ·.. . . · . · ..... .... ·:.-:: . . . セ M セ@

. ·CD _·. · N Z aョセiケコ・ ᄋ 。ャャ@ ゥョ」ゥ、・ョセ ヲ。 ョ、@ implement immedjate c_orrective action. .., § Z セ@..... .... :: .. Z MZZ ᄋNセᄋ@ .... · .. . :-._ ·: ... ·:>:: ,·_.·,.· .. Mセ@ .. · '.. . . _>·' ::· .• •• :·-:. ᄋNᄋセM ... • . セMスセ⦅ZᄋZ⦅NZᄋNZᄋ@ .• \ ·: .•• セM N Zセ N@ :. セM . • . •. ·. __ _..: . ᄋG セNNNNN@ g E

: .·,':· ··

___ ·:·._..· · _-·: _··.-. > Z M N 」セイ ᄋZ@ .---:_··Pt6_vid_e· ェセエゥ ZNZ セセセセ M セB N Bゥセ M セセU MM カNL ゥ ゥョ@ ZZ セセセイッセセ ゥ 。 ᄋ エセ MM ᄋ エセゥhィセョセ MMセ ュ。エ・イ ᄋ ゥセiウ@ MG エッ ⦅ᄋM セッョ、オセエ@ セ M ェ@. . . .·: . · · ,._: · . :·. . · . ,. · ᄋ キ・ セ ォ Aケ B@ ウセヲ・セ ⦅ Zᄋ Z ュ・・エゥョァウ@ .and NZ⦅ZN 。エエ・セN、 N@ ·. said · meetings· to ・カ。ィNQセエ・@ · the11· ....... .. l) .

. ··· .. _._·;· ,:-·· . .- · M M M [セGNᄋセᄋ セ Z ᄋZNZセMZM [⦅Lセ@ ... M⦅M\ᄋM セZ Z ・ヲヲセ セセセ Z セセ セ M セエセ| Z@.. ,::>·:·:<,:'.:::·::-·:-.... Mセ@ .. : セ@ · .. ᄋ ᄋ Zセ ⦅ MᄋNZᄋN ᄋ@ .. ,' ·. :_·: :·· _.. . ·. · . .. · · · · .: · . __ .:1 セ セゥ ᄋ@ · -:.; .. . (Q : - . · Mjエセカj N ・ケャ N@ セ。ヲ・エケ N@ · ャ_ Nᄋ ・・エjイゥ N セ@ イ L セZ[ーッセ エウ@ · su_brnit):ed_. by _'ji:lb .. supervisors and エ。ォ・ セNᄋᄋ@ ·, i

· · .. _ · ·, .- . · · . .. · M ョセ」[ セウウ。セG ケ ⦅ N 。」 N エゥッ ⦅ ョ@ セッ ᄋ@ ensu·re 'that the job s't.ipe.niisors 'h'old M セ セ。 ᄋ ョゥョァヲオャ@ weekly

:.··

; .. ··.

, . . -. .. r. I -I

.....

!' • I •

i ...

·: .... ·· , ; . ·' .. ··.

... セ@ -.-:-: .. _:.:·-..!.- .. ·-..... :--_: __ G⦅ZM DアヲG・エケョェセ Z セセゥセァサ [ ᄋ Zᄋ ⦅ MMNZZMZZNZMMG[ZZZ\ ᄋ Z⦅GMZLZᄋᄋMZZZ@ .. · .. ·· ·:-: · . セN@ . . . ·.: . . . . ': . .. .:· . . . ·. . . •. .. . ·.. . : . .. · :': ·. : . . ..

_: · ·: .· .. · . ·:; ·.· : ·. · .. {m).'- :_: M ャューャ ・ ュ・セエ@ セ。ヲ・エケMエイ セ ゥョゥエ ᄋ ァᄋ ⦅@ ᄋ N pNイッァイセイゥQウ ᄋ@ ·.for ·Contractor supe1.:visors

' . ' . .- :':: ·. ... . :· · . .- ・ヲd G ーゥGッケ・・ウ セ 。 ーー G ャ ゥエセqャ N ・@ エッ NG エィセゥイZ G ウー・」ゥヲゥ」Lイ・ G ウーッョウ ゥ「ゥャ ゥエ ゥ・ウ N@NM セ ᄋ NZ@ .. _.... . . ·<' : . . './. . . · .... · . ᄋ Z ᄋ N Mセ@ .: . . .. : • . :: ·:.··; . ,·, •' Nセ ᄋ N Z BGG@ ···: セ@ ᄋ セ@

-- (n)··_.· . Main.tail1 ャゥセエ@ Z ッセ セ [ゥ G エ セ ZZZ セヲM Z ー・イウセ M ョゥャセサ ZN セセセ M ゥャ。「ャ・ N@ for . first .aid and .. emergency . セ@· · エイZ・ 。エュセ ョエ@ ヲッイ M セ⦅ョェセイ・、@ cッョエイ。」 N エッ イ Z セューャッ ケ・セウ N@ · · .· · :. . . -'

( oj · .•• cッセ」・sウゥセセセ[イセ@ .;il; 「 セ@ イ⦅・ウpアョセ ゥ「ャ・@ ';or セッ カ A 、ゥ@ ョセ@ a'sare,;. ッセゥ・ョエ。エゥoョ@ エイ。ゥイゥゥイゥ セ [ セ ᄋ@ · セ@. .. . ·. ウ ⦅ ・ウセセ_j_@ for 。ャャキ ⦅ ッイNォ・ゥZD[「・ ⦅ ヲPイ・ N セセ・ケ N@ 。セ・@ allowed to_qegm work:-Tiie onentatl0rl\J!.1 セセゥGゥ@ セ@

.: .· · ·safety·. trairiing·· -...v-m :_:o'e .. conducted . by :tne ··'authorized-. イ・ーイNセウ・ ョエ。エゥカ ・ ᄋ@ as .,;; セセ@ セ@ ·

.. · .•. : .: · .. _ · ·. · · セ Z@ _- セ [ オァセセウ Zエセ・ ᄋNMN セセ M lセ。。 ⦅@ セセ ᄋ セ M セ 。ョア@ M セュ NZ ゥ セ セセャセ、 Z ・@ Z ゥゥZウ G オョゥュセイIᄋ ⦅Z セヲ@セィ・@ _ContraCtor ウ。イZエ セ Z@ .. _:)N M M セ@.·:, .· .. · · .... ,' :_ . -_.. jZ・ァ セ[セQ セ・イ[ョ ・セエNウO@ ⦅ャゥ・。、ウZセー N s。ヲ・エケNMtイセョョュセ@ and ayvareness. . "'-.... ᄋᄋコエイセGヲ[A@

:·:·:_·- :.--_ .. , ._ . . ·." ... :. ·_. __ : __ ': · .. _· . __ _ · ... · .. .- -: _::· .... ·. · . . · .. ·.:· · ... . . . . セ セセ@ セセ@. : (p}. : · ᄋᄋ aセ@ _a_' rninimjifii· サ[ッョエイMHA 」セッエ@ representa.five. tt>adeqi1ately train its employees- - :2:

: .. :·. ·. ·... . . . 。」セVエZ\ャ N ゥ Z ョァ@ キ G 。セー ⦅ ャゥ」セィャ セ セ O_セ ヲセエケ@ セエセイエ、。「Zャウ _ エGャセゥセ@ .. セイ。ゥョゥョァ G ェZョ。ケL@ inchide but is· ョッセ@ . セ@ ·

.... : :_- _· : .'. . .. ... ᄋ エ⦅A ᄋ ゥヲゥェセ・ア Z ᄋ セセZ G ᄋ ヲ。Ql@ ーイッエ ⦅ ・、ゥPゥQGセ Z ヲゥイ・@ .watch; :$:cg_ffq!d•s;_fod<ii_f.ts. ・ク」セケ。エゥッョL@ }adders, • ;A . . - . . . . . .. ·_ :· .·_ .:--. ·. 」ッョヲャセ G ・ 、@ :_SP.aCe . entry,': N iGセNGApセャZセエッイケ⦅@ 'protection, . oshaセpウmZ@ (Process Safety

· · --_ . :· .· :: mセ M セ M 。ァ・イ[[[・ョゥス^ァエVカョ」ゥjゥNサァL N セィVjZゥゥゥァ ⦅ [⦅ョ Z セ ] エ G イ 。ヲヲゥ\Z N 」ッョ エゥ Zセゥ・エセZ ᄋ@ · .· · · . . . . . . . . ·.. ·.. . : :_ :- .; .... Zセ@ .... :· . . . : セZ@ . . . . ·. . . : . :. •. . ...

. .. ... .• . :.:.:.: ._·:· .· .. :,····.- . ..

.•. . '

. .. . · .. · . • : ! ! . • ·. • ' セ@ .. -:·.

. ·, : . ..

.·',

I ,.

: · . .

:, .·.· ·

:, .

... .. . '

:: .. . : [ᄋMNセ@

... . .. .

. : .

· , · . . .'

. .. ::

. . .. •'

·. :·:· . ᄋM セᄋ@

. . :: セ Mᄋ N@ ·• ·.. . . . . . :· .. : · ... · .. ·.· . . . . ·:· · \ , , ·. . . . . .

. セ M

セ@ . . . . ' . . . . . . . .... . . . '.. . : . \ ·, . . .. , (q) : .'. ·. ·. In the セカ・イゥエ@ :pf a: キ ッ イォ Z イ・ゥ。エセ、@ G ゥョセゥ、・ィエ Z ゥᄋ・セオャエゥセァ@ tn a cッョエイ。」セッイ@ ・AGイQーャセケ・・ Nᄋ@ .

: : G |セ ᄋ ェオ イケ ᄋ@ or. ョ N ・。 L セ NM ゥョゥウウ[@ cッー エイセ セエセャᄋウ N ウャャ N 。ャ⦅ャ N@ rwtlfY. エ「セゥイ@ ⦅ aーーッ N ゥョエセ、 Zr・ー ᄋ セセウ・ョエ。エゥセ・@ .

• .. セZ@

· inimedia.tely:· .. ,, · · ·... · .·. > · · · · · · · · · ·. . ... ,;.. . •.· ... '

• (r) N セoAャエョゥ」セイセ NM Zセィ 。ャゥ@ [イセセゥ、・@ the:a.ppointee\: イ・ーイセセセョエ M セエ ゥカ セ@ セゥエィ N@ セセ@ ゥセゥエゥ。Q@ イ G セーッイエ@. .. . . . .. .. . , . of incideJlt; . .' .i:n·. yjt:iti)1g,· セwャセィゥセ N@ ·.24· .hPtli'S of 'the .. acddent. Hiu:d ·copy' or .. · セ@ ·· : ..... · :'.: · ·:·· ᄋ N ᄋ Z Z セゥ セg エヲッ N ョヲNセ@ ヲVイpj。エウ Nᄋ 。イ・ L セgᆪ[・ー N エ。「ゥセセ Z NZ ᄋ ^N@ · ... · _ _.· .· ·.. ·. ·.· ... ; · · · . ·. ::l

•· · . ( s) . . •.. ·. · cセエ|エゥセゥ[ッIウ L@ ihal( pt;vid• a: 」ア qャーャ・ゥZ ・セ@ Oce; セ ᄁュ@ ゥ ョvセ Aエャァ。 エゥッョ@ +Opoft within . ·.··• ᄋᄋ セ@ N セ@. エ N セイ N ・・@ .(3). work_ing «;lays M セヲ@ エィセ@ incident: セョ N@ the' event, their. investigation . : <n 5

.·. ._-r.equires more エェョセ・ ᄋ@ to ゥョカ・NNウエゥァ。セ・ ᄋ@ .du·e to the cqmplexity o(the ゥゥ_」ゥ、・ョセ@ セ@

:Contractor-s shalf 」VイゥャセlANャQ N ゥ gセエ・@ ᄋ セッ@ the 。ーーッゥョエ・セ@ Representat.ive l.n キイゥエゥセ ァ MN@ セ@ · . . _:; ... ゥョ」ャセャ、ゥ ⦅ ョァ ᄋ ゥ ョ エゥ N ュ。 N 、ッGjャ@ tp N ィゥァ ᄋ ィセイ@ authoi:itles· o.f Lead U-i;13. Thi.s commu.nication .· .· 8 セ M .· · · セィ。ャャ@ ゥj[セャセ N 、 セ L@ エ ィ セ N ᄋ@ ゥ Dセ オ・[@ セセセウゥョァ ᄋ@ セQセ・ ᄋ@ 、セャセケ@ 。 N ョセ@ an ・ウセゥュセGエ・、@ ゥョカ・ N ウエゥァ。エゥッ セfス@ .-). セ@

· · . : . .. 」ッュー ャ セエjoョ@ dc1te. . : . . . . . . . · . . ,., セNLN@. . . . . . •. • - .•. . . c:(.

.. (t) •. .•. . Zセセセ[ウZ@ 。ZLセLエセ[[ゥZZZヲセセエZセエセセセZZZZᄋセZセセLZセZセイ、 NZ[ [j[Zエ セEセ セ[セZ」[セ、Zセセ@ Nᄋ jセ@.rel_l?rtJng セョ 、@ N ャーセ・ウエゥァゥャセ N ッセーセセ」セ、オ N イセ@ 「セ@ fmtia.ted 。セ@ outhnedprev10usly. Q Hセᄋ [@ セ@ «. . . :. ·.: : :.· ... ··: ·. ·' ... >·:: ·,.·: •... : .. ·.· . : .. , · .. -·:·. · . . ,· ' ··, .. , .: .. .. ·. ·. .. "'· . ..1 M uセ@

en) .: ··. · ZセエセP

ZsZセ N OP

」jセZセZZセ M セZZセイAセセセ ウ 。セセセセゥ、セZゥエセ[セセセゥQセセ[ZイZエセVセZ セョ ゥ^ゥセセ ・[[Z セセ@ . M M セ@. ·. s·a.fegu;rd G 」「 N ョエセ。」エッセᄋ@ :employees キ「ゥャ セ N@ セッイゥゥゥ N セセ@ :on ULB .Sites. All Conr:actor J:.. セ@

erppl9yee:; wm N 「セ@ trained in the. use ofthis·pJan and jnformed of their role in . . セ@ ᄋ セ@ .

. . Z セセQー M セセ N G_・セエゥセセ@ iE セセセゥセセ Z Aィ L ・ゥ\イ・セーゥ N イZセ N 」ゥ@ N ウ セ セ・」ケ@ セィ・ィエ\エ ⦅ エゥッNョ@ ᄋ エ イセゥョゥョァNG@ Thi.s ーッャゥセケ Z@ · · セ@ セ@ . · . Qセ@ )!landatory ·and !ll.u.st ·.be . Stl'Jctly. ヲッャャッキセ、@ by all c;ontractors and their .r·9 ·· g: ... . . . .. . .. . . . · •·' · · '· · • ' ヲセ セ@ o-

.. · ーセイセ_ ョョセィ セィゥャ・@ セッイャセセセァ@ ッョ N DAエセウZ@ : · · · ·· . . ·;. 1 . . · . , • . · · · .· · . ᄋセA[ N@ セセ・@ セセ@ · .

. . : :'(v) .. : M セセ セ ・[i ⦅セ ョセ セ ゥヲェ セ \ イZ セ Z ゥ ᄋ@ ᄋ 。ョ [ ᄋ セᄋ@ セ M ュ セ イァ・セ」ケ@ .' Z ・ セ N セセセ。エゥ セ セ@ .. ; (an Zᄋ M セオ、ゥ N 「ャ・ Z@ · 。ャ。イセヲカ・ Z イ「。[@ ZZZ セ@ , ᄋN Qセ@ . >. aruicn1·rlcerriel1t- wHt Qe セセ・ G、 ᄋᄋ 「ケ N@ Z cッョ」・ウセゥッョ。ゥイ・@ .to :alert •em.plciyees . of an

. ·. ev:a.cuati.Ol1); エッ N エQエイ。 」 エセエウ ᄋ イエゥセウエ N ゥイイゥュ・、ゥ セ [エ・ャケ・カ。 」 オ。ゥ・エィ・ゥイ@ ー・イウッョョセャヲイッュ@ the . . ·

· ·Project Site·, per.form q ャゥZ・[。Z、 NGZ セ アオョ エ 。ゥャー@ N AG ・ ーッQ セ エ@ イョゥウウセョァ N pNセ N セ セ ッョ⦅Nョ・ N ャ@ to concerned : · . ::2

G M セ N@ ゥョ ᄋ、Q。ィゥ N セ@ セイ@ M セ ィセ Z Nヲ。 セ ゥ N ャゥセケ@ セエャ、 NZ セ。ォ・@ C\ppropi;(a.te N ウ N エセ ーセNヲセ セ@ ゥョカセウエゥァャZャセゥ M ッイイN@ wャゥ セ@ <·"", セ M r.;e • · , • • • . • . . . • . •• ·., • • • • .••· • ·' •·. J

· . ¢vacu.ating any,· _b.uilding; ᄋ ウエイャャ セヲオ イ ・@ 9'!' i9b site •. empl()yees should オエゥセゥ コ・ N@ the·-·---· -w=---.q .....

. · Z イ[セ。イ・ウエ@ .e)(i.t to セ セィ・ョ カ@ p・ G イセッ ョ ョ ・ ャ@ wi'fi. remain at the 、セウゥァョ。エセ、@ site un.tii an· all- ,, · セ@

· : · 」L ャ セ。Nイ M ゥウ@ セョョ N ッ オア」 N ・、 G ッイOHjイエ ⦅ ィ・ イ Z ・カN。 」 ᄋ ア。エゥッjセ N ウエ・ーᄃ N 。イ・ Nᄋ ッ ᄋ イ[ ア・イ ・アN N@ . · · .. .. (<(\ · セ M セ@. .: • : • •• . •• • .. • • : •. . • •• : : • • :, . . .... : : : . •• • , • • t. . : Gセ@ ᄋ NMZ ᄋセ@ M セ LZNZッ Lャ@ セ@

.. .. セキI ᄋᄋ NZZ N@ . セ M セ」 N ・ウウゥNッエゥ。 h Z ・ ᄋM ウセ セ ャャ _Z ッュセ N ャセ NZ@ :wit); ·. セィ ・ Zᄋ M セセセセ ー エ N@ イ・ケゥセゥッョ N@ セ。ヲ・エケ@ Rules : &. GML セセN@ C> . . pセッセセ M セ M キ セウ@ : セセセZセオセ@ .. NN⦅ウア Nョエイ。 N セエHIイ ウ@ .· Z セィ。 L ャセ N@ · ーイ セ _vjセセ@ M セアセアオ [ 。エ・@ fire . protectton M セ M --.}_l . ;:: セアセゥーュ ⦅ ・ョエ@ 'i-!1·· ・ セ」ィ@ .of their· Dエッ イ セァ・@ 。イ・セウA@ N セヲヲゥ」・ウ@ .and other temporary' •. " ᄋ ᄋ[ Z|セ@ · .strU,ctut'Os.. . . · · · - · · · · · ' \ZZZZセセ@ セ [A」@ .

. HセI Z@ ·.. : cッョセセウセゥッセセ M ゥイ・@ is:· イセ ウ セッイIウH「ヲ・ セ ヲッイ@ :ori.enting_ ・ューャセケ・・ウ@ .on the ·specific ·safety セ@ M セ@· .. ··. . .· ⦅ [オ ᄋ ャ セ ウ ᄋ@ エィ。ゥMAQjセsエ Z 「・NNイッゥエ Y セ・、 ᄋ@ by 。ゥA ᄋ ーセイウ セ ョ N セ N@ w9rking pn pセZッェ・」エ@ f。」ゥャゥエゥセウ@ .. Qther" セ ス@

. ·. . ·' :::. , ·. · .· [ M ーセャᄋDッョ。ャ@ ーイV ᄋ エセエエ ゥケ ・@ .. ・ N アエQ N ゥーャョ セセQエ@ :(Pp.E.j ゥウ セ@ aisb' require-d: in 。」」ッ イ、。セ 」」@ with the · ヲZセ@. .. : . ·.: .. : · .. : ::· .· .... :.-. ... ' : ... .. ·.· ; .:_::-"· ·. :._·.·.<· · : . . . : .. · . . .. · ... . .. (,-:j''1.. . l/)

· 1 $<} · .. · ᄋ セZZLNカB@ ·

. . . . . セゥAイョャ「セr@ .

· cAM| Q |Nai\Nセl uヲャApet@ イᄋセ unicipality@

.. : .. . ·,.· . .. ......

·.·.

'; . : .

. . . •• : ' •1 0 ' • • セ ᄋ@ ......

:• . .. :

... . .. . 0 . ".

.. • ••• o • • • • • •

·· .. • ..

. . ' . ; '

>-エMセ@

. ; .. · . ·:J . <(

:_·'·· . . . . ; . [ 。ー L ーイセーtゥ セ エ・ ZN セ [ヲ・ エケ ᄋ@ s Z エセセ M 、。イアウ Z@ Z 。ョ サ ・セ|エゥーqj・ョLエ@ 。ウ ZᄋN ウNセエ@ セケ@ .,the .. ュ。ョセヲ。」エオイ・ᄋ セ@ . セ。 N@.'' · · . N⦅ Dー・ N 」ゥG ヲゥ」 。エゥセAセDM A iist·. 6{t]l __ e .:ri;iri1m_· Zᄋ オセQ L ー ・セ ウ Z Vョセゥ N@ ー M イ セエ N ・」エゥカ・@ requirements is as . 0 z

Hィセ@. . . . . .. Z ヲアャャッカケセZ@ , ZZZセ\@ ,

1· ·. ·· '··.< . ,. ·, . , , セ@ .

. l · · · · . . . ·._: :.···.: ·_.· · ·. · · ..• <· .. ·.(i)_ :· :: ᄋNZN セィ・N⦅ L[N セッョエセセ N 」エッヲNN@ セィセャャ ᄋᄋNᄋ セセ@ GイN セウ pZセョ N ウセセ M ャ・@ . fo.r セ ᄋ セイッカAセゥセセ@ an.d .. :: g :_ . ! L

5 .' :.·;·_: .:'<, :.:·. · .': ... . <· .. ·.: ·.;:· .. < .. :· .... .- セZ ᄋᄋセ ᄋNZ@ -:.: ::;_.· ZZ ⦅ ᄋZ ZZGZZMG エ[_ Q セZ セセセ セセ[[セセZセセヲセ・ ⦅ GQセセイ・⦅、@ ケセZZウッョセNセ@ ーセ セエ セセエセセ セ@ ・Zュー セj@ . ·. セ N@ ,.

{ • · .·• · · . · · · . . · · : . : • (ii) .: •• a[セHセセNセ@ セ。ゥ、@ ィセセ[@ セィセャャ@ be IBセ[セ@ セエ 。ョ@ t imes while on エィセ@ jイNセ@ . . . · J · :::;_- ... . .. :.·. ·. ··: .. :::· .. .. .. ..·· $ite. ᄋ QNセ@ is .. イ・アオゥイN ・ Z、 N エィ 。 N エ ᄋ N ・セ」 N ィ N cッョョ I エ」エーイ@ use an aュ セ イゥ」。セL・ZZ@ ·

· ·, _·: · · · .. · · · · . .. .. . . : ·.:-::::.::, .. : ... · N n。エQセョ。|セ セセ イゥ@ .. 。セセセ M ウゥセ N ウセェエセセセMcaセ@ .. ウゥセ ᄋ セ ーーイN セカ ・、ィ セNイ、_ 。エ N@ H セ@ セ@ ·· .· -t:

· ·. ·. -': . . ·: ... [⦅ G Hゥゥゥセ@ .. · . N^⦅ セ。Nヲ・セ ᄋN ァャ Z セウウゥウL@ セセゥ」セ@ ュ N ・セ G エ@ 。ーーゥ ᄋ ゥセ「ゥ・ ᄋZ ansi@ standards, 。イ セ ᄋ セセ@· ·.. ·. . · ... · · .. : Nイセアオゥイ・、@ ᄋ 。エG⦅[Zセ ijGN エゥゥZョ ・ウ@ ᄋ セィh・@ .on the .Site a_nd should intlud.e o セ@. ' .·.. . : · .. · .. · .· . . · .. ' ·. . . . . . . . ..· . . ·_ z

:.·.:· .· 1: . . セZ@ .

.. · ..... · ... :··· . . . .· :·. , '· :·: セーーイセカ・L、 MZ ウゥセ ・ ᄋZ ウィゥ・ャ、ウN@ ·OnlY. cl.ear セ。ヲ・ エ⦅ケ@ glasses are allowed · .. 2

::.· .. NNセ N N@ :--- .· . . :. ·:_- _· :. . . . · ·.· .. to. be セ ウ ・、@ .insid.e セセセゥャセゥョァウ ᄋN ッイ@ ・ョ」ャ ッウセ、@ ウエイ オ 」エオイ・セN@ Shaded c;r-·£ : ·.· . · ..... · -. . . ' .. ·:; . -·.: . : ·.': --:· . . .. goggles 'ck'·hooos lrJay G 「セ Z@ used キィゥ ᄋ ャセ@ welding' ·or cutting' 。NN セM .§., .

' . . . . . . < • .. :.. . . < セZセセセNイセセNーセNLセセ[セZセ@ [セセ ZZ[セ@ glasses with ウ・ ャヲNエゥョZセセ Zヲ j@ 1 1 · .:.. . Hゥ G セI@ :: J>PJ;: N セィ 。ャj@ .. be·. worri while· tra:vellihg 'from the· security ァ。エ ・ セ@ セ@ § .

. . . j. }· . '

> . . · ··

:,. セMZセ ᄋ@ ..... . .

ᄋ セ@

. ' . : ' . .·. . . ᄋ セゥュ ・ ᄋ Z@ エイセセセャゥゥョ N ァ@ .. thr6vgh GZ エィ セ@ pia'nts, · workirfg . outside 01' . ^ セ@- -· · · · · ·· · · ッエャゥセ[ᄋキゥウセ ⦅MN ・ョ ァ。ァ ・、 ャョ@ work .at each station;e-xcept in areas

. .. ·

. . - ....

. . . ·:

o , • • • •

., · · · . . ·. ウ ᄋ ー ᄋ セセゥィ N 」セャャケ ZN 」ZエセウLゥァュセエ・セHャ@ 。セ y M pe@ not required .. セ@ .t ;-: . ..

........ . . . ·... . .. .': :.- <:.· .. : ·· \vr·.-.· .... : 」 Z [ Nセ セZ Zセ 」エセイ I |セセセ、 セI ウ セ⦅G ア Nゥ Qィ N カゥウ ゥエセイセ [ [ョHセ セ@ ·,·_ .. .. : ... · :· : ....... ·.. . . < :-' : these-same standa'rds·.' . . . ' . · . .

• :• • '• o: •; o • •: o·. ' ' • •· I • • • ' •• : :' • • o • o •: , ' • • ' ' • . ' • , · • • • •

. .. ·. ·, ·. . (y)··:_. · :· .. Z⦅ ZZcセッ セセ ᄋN ᄋZN セセ ᄋ セセ・ォ・セセゥゥゥᄋァ G Z ᄋZ NM ⦅ᄋ 。Gイゥ・ ᄋ セエウ Nᄋ@ .. ウ N セヲセ」ケN Z[ ᄋ@ · セ G オセiエゥZケ G@ .. セ セセ ᄋ 、 Z@ Z セセッ、オ」エゥッャセセ ᄋ@ ·rt · is エィ セ・MMNNN NNlッMア@·.. · ᄋ Zイ・ Z セ Np qセウゥ「ゥ N ゥゥゥy ᄋセ ッイjZ」_ャQ N エ イゥウ セセ セセゥイ N ・ G@ Z ッ N セ⦅ウゥ エセ Nᄋ@ .. セ イッ@ ᄋN セセK イ@ Nイセ セOセ セ@ ⦅N キ[セZォ@ pi.-ea clean .

.: :·: :.·. ·.:. . : Concessionaire· 。イ・ ᄋ LNエZ・セー ᄋ oGョセゥセ ャ・ M or trash at}d セ・ー、ウ ᄋ@ that is genej'ated by their . · ...

·. ·. ·. ·.· . .. · · キ、ッ N エ Z セ Q Z Z QG「イ。ウNィ Nᄋ 。 セセ@ セセセLイセ N セ@ セ M エセ ウセ@ 「 [ セ ᄋN 」ア ⦅ ゥャ・セエセ M セ@ .. ᄋ セセセ M セ M セ M 。セ ᄋ ・、 Zᄋ ゥ ᄋ セ ᄋ イ セッー ・イ@ 」 N ッョエセゥョ ・ イウ N ッ ヲG|^@ . セZZN@. . · . a at y asts · · ·· · · · .· . · .. · · · · · · · ..

. : .. ·;; :: ... セN Zᄋ ZNZ@ ... ·. <· セZNMZ@ · . NZZ ZᄋNᄋZNZᄋN\ᄋ ZNZZ [ᄋ Zセ ᄋNZᄋZ^ Z Nᄋᄋ ᄋ ᄋZ@ ... ·>::'. ·.· ... :··:·<·: ·.·· ···, . . · ·.:. | |セセ@ ' ,_ セセ@. .. . . fzL .. : -: Trash shall:not. 「・G \Z ヲ。ヲゥ、、ゥZヲャャjNMGセィイッwョ@ ··off a floor· or ,tprough openings in the |||Nゥセセ@ ;:, .

. :: ··._"·. . '· ... ' ·: ·,·, : .. : : ... ョッ HIセᄋ NGt[。 ウィ@ 」ィオ G エ」セHNエャセ。ヲNセ Z セ ᄋ HI N xセsL ᄋ \_Nゥᄋ Z Z ッエセ・セ@ .apr イッカ・セ@ N iョ ・ [ャセ ⦅ ウ@ セ オ」ィ@ 。セ「。 イイゥ 」 。セゥ_ GヲゥBGZ Z@ y|ェセ@ :·3' . .-·, ..... : · . ::· .. : ... ·.:· : · at1d/or ヲャ 。ァァ ゥ ョァ G ウ ィセAゥ 「・ M セエGゥャゥゥ・、Z Z@ ·· . . >-''• · · ... ·· · ·· · :·. · .. ' · · .· · · セ[Z@ ' .. ⦅LNZサセ@ Z Nセェ@

-.... ·, .. ·. . .... . セセセ[ ZZᄋ ᄋ@ ·. ·. [。セセエセ ᄋ イ・ セ オゥ N イ・ョ QセZセ エ セᄋ エゥセ・ョ エゥᄋ セセセ Z 、@ ゥ ᄋ Q セᄋ N エィ セ@ bエQ N カゥイ ッ セセ・ョエ@ ᄋ ゥ N セー。セエ@ ᄋ セウウ・セウュ・ョエ@ (EIA). ·r ᄋ Mセセjセセ@Z rNM・ ーッイエウ ィセ ⦅ ョ@ be セゥ_ セゥーャゥ N 。 ョ」・N@ ·,:.- ·, .. : セ@ · · B

.. : ··:·; , :._: . .. ::. "· .. . . . セ@. . :

. . . . ; ..... · .. セ@ ..

. . .. t セ@ ;.0 • . ·• セ@

. .. . · ... .

• •• o, ••• •

.· .· : · . ... :• ... ·.·

....

·,· <.

. ;

.. , ,• ..

·.f

· · ... ヲセェ@ · The ᄋ 」ッセ」・ウセ ゥッ A セセ セ イ セ ZN@ ウィ N セiゥ@ ウ・ N ゥZBオセ@ a キ ᄋ セャI セ ᄋ セアャゥゥーーセHH@ セセセ M セイォ エッイケ@ for ᄋ ュッョゥエッイゥセァ@· .. ;and セョ ᄋ 。AケウゥウNYH・ョカゥイ」ゥイ|ュ・ イ ゥセ。ャ@ ー。イ。セセ N エ・イウ@ for air ·q\laii.ty, nieteorql0gy, キ。セ・イL@ ·.

. .. · : キ_セエ・キセゥ・セᄋN ᄋZ@ noi.$.e,: . ァイッオイゥ、Gキセエ・セZ[N@ セエ N 」@ · 「セウセ、 N@ on · .. the : ·overall monitoring

.... : .. : ·.. . . : イ・アセゥイ・ュセイゥエ@ .. GIS:giye·n· in b。 ッャセァイッTョ、@ ッ、」セュ・ョエセN@ . . . . . . . . ' . . .. . . . . . : ·. ·. セN@ .

.. · . · : . .. . . . .. . :· ."' · ..

. ·. · ·

. セ@ . : . .

' ·; .

. ,.;:. セZG@ .....

·.: ·\ft!)

·. : ... :. セセ[セセャ ヲゥゥ lセセ セ セ@cセャャlヲMN ゥ|pL luhゥpeGヲ@ i{;i.:;•,t:::'\i"f.'.UTY

.. ' ·

, セZᆪZWセセセ ZセᆬAセSセセC[セセ セC@ .. セセ セ[ZセセセCセセZセ[Lセセ[セMセセZZセセ]セセᄋセᄋセセZセセ ]セ\セ]セNウB LセLNelセZセZ]セZZ@セM ᄋ@ ': •. . . . • :·.:. .• • : .• ! : . • . . . .. . · . ·. . . . . • . . ·• • •. . . .. ' . . • . : . . • ' ... .. . ... ......... . . • "

. . · .... )' .. . •, . ·. '•: .. . ' . . . -- .·: .. :::,. . .. . . .. . ..

.. . . . · · .. . :.

: セ@ . . . . .. •• . . !·

... . ·. :' .· .. . . . · · . . . . .· .. ': .... ·:· _.:._: :' : . . · .

. . . _·,Ch). : -> エィ ᄋ セ Z@ ᄋ 」セョエ ᄋ セ ᄋ セウエ N qィセ ᄋ ゥイセ MG Z ウセセオ ZZ ヲイゥョセカカェゥIᄁ Z@ QA)Qc· ーQ セ ッセセ Z 、オイセウ Z@ ヲッ イ ᄋᄋᄋ セゥエ ᄋ@ Z Qセ「ッイセエッセケ ᄋ⦅@ ·· · -· · . · .. : .. ウ・イセゥセセ ᄋ セ G@ 。ョ、NIエイQカセ ᄋ エッァセエ Z エQ イ ・ N⦅ 」・ゥZエ ⦅ ゥヲj・、 N j。「 ᄋ ッセ。エッセケL@ ウ ᄋ エ。エセウ M ヲゥᄋV ュ N ᄋ アセ。ャゥエケ ᄋ ーッャョエ@ of. f-

. : :·:.· :.-.> .. ·.. . . . . ·· .. ) .: . .. v.iew. s:och_' セ N ウ NZ エウッ ᄋ[Z Yqoo N@ G \ゥG ョ N \Hッエィ・イ NZ Dゥゥョゥャ N セイ@ standards .. The overall-goal.:s.h'otild a: セ@

:·:i _::-- .. . · .f · .. ·.:. : .. :' ': ·. ·.: :- ··.: ·. ·.:.: ·afsq' be::w 。ゥアセイゥ G イ・ Z ゥZィGセ Z ウセ。エセゥ Nᄋ ッゥ N@ ce.i·tified and rec<?gtJ ized :Jab6i·atqr}r ttnder ᄋZᄋᄋᄋ セ。@/' . . .. · . : ,. · moef[ Nᄋ gッカ N セイョュセョエZッヲ@ tndia·: t ィ ・N c ッ ョ」 ・ウウ ゥアョ。 N ゥョ セ@ si1ati strive to get ISO 14001 · . o z

;-:'=. :::·;'··· ·: · · ·• ·: .... . : · .. · , : ... 」・ ᄋ セセゥヲゥ」セエエッ ᄋ ー ᄋ ヲセイエィ・ NG セゥZゥエゥイセ ᄋ ヲ。セゥャゥ ヲケ@ . .'··.·.=.: ·. · . · ·.. . . · ··· ffi. セ@

< .' . ::··-:. : •• .•.• :: .. ': セAI@ ... : .. ·. Gt セ ・ M セ 「ョ」 セ セ ウゥッ セ N 。ゥ イ セN Z セ ィ。 Z ャャ Z ヲセ[ャッセ ᄋᄋ エゥ[ ᄋ セ Z N ・セ Z セゥ[ッョセ・セセ。 ャ@ issues with ュ 。セ 。ァ ・セ・ ャセ@ セ@.. . . .. . . . cktion alo_rig with r.espdnsibili.ti'es a's ュ・セエゥojQ・ 、@ in the folloW.ing table. .. : イZ [ZZ セAGN@ · .. 0 fu .

. ·. .. ·.• .... . . . . . .. . :.·.. . '. ' . . . . . ' . . . ·;\ ''·J ·01 . ... . . . . ...... ··. .. ,,,..... ;!f. ·.·. .··.

· ·· -: ..

: ·>: ·: A·:. . •

::·. セ MM セ@ .

.. _ ... ;_··.·

セ Z@ . ,

Mセ@ · ... · . セ@ ..... ·: ..

セ NZ@ ·· ::.· .·: ··::•. . '·.

e ョカゥイ G ッセイゥエ ᄋ ・イゥエ セ ゥ Z@ ゥウウエゥセウ@ · · . . .. '• . · . . .

".' ,.,

. .....

:-·· . .. • • •• 0

. ' ·. '• ··: ....

.. ---· ·----· -- : ...

'··.

: . . ·. -:··

. :: ᄋ m。ャスセァ・ N ョエセャゥエ N a セ ゥZゥYョ@ .·:·.' .: .. . . : : : .. ᄋセ@ . : . セ@

.. _;., .

· · ·· ·./· . :·,:: [ セ Z ャエヲvゥ セ セセセエヲHョッ ⦅ ョ@ .· ..,. :,::: Z ョNセ セ rッmャjゥゥゥ|、・ N ウ@· . . ··. •··.·. •,,_' ·.. . . .

-Conce.sslonaire

· .. ·-· : .·

Corice·ssionajre

cッョ ᄋ 」セウウゥッョ。ゥイ・@ ..

. . •, .. . . ·· . :

::. :· . . .. ·· -·

lU セM

•·-f\:(

'-<t;l

.. ..

セM . . . ·.· • '(,'

;·:.-:

. ·' ·

.. . , ... ,.

:.-· .. ....

スNセ@;·.·

f'.. I

I ,. I

..

... ... .

·.· · .··· . Air Poiiution·:. .. . ·

· .... . : .. : · ·· ..

·_. fi.igh Ciust i ・ セ・H⦅ ZZ N@ <:: . . . セ@ .

. • sセ」ャゥセ・ N ョ N エ@ runoff.:.::_· .

. f .

Noise pYャャオエゥッ N セ@ ·

I Air pollution· due:tQJhe .MSW

·. vehicles and pAセ」セウセ ゥ ョァ ⦅ ーャ 。 エQ N エウ@--L. . . ..

-

'i • ;

! · .

I'· ;

[: !· (

I· !

· .. ·

. · ..

. . :

[ N セᄋ Z@ ...

• .. :· .

. ... ; .. . · .. ·. · ..

. . . ::. : · ... , >·.· . ...

. ·' : . ··.· ; . ··· .• . . · .. : • ' : . .

' .: .' .. ...

. . ·. セ@ . . . : .. .. . .

セN@ : . . : ' ... ·.' : セ@ . ·.

·: :: 'i4 .. 2:· ウ Z セ」ゥセヲセエセセmセ[セᄃ@ =:, :;:.· .. ;·:·:.

· . . · ·. · . . -:... . '. :.·. ' , , ·: . - . . . : : . . . ; .... .

.... : . . . . .. . _·.··

; , · . .

.· · .·

: , . ·. . , . .::.-:_.· ··. . . . . .. . ·.· . ... . ·. .. . . . . . .. ' . ' ;· . ' セ セ@

· . ·. : ·. (a) . · . . ·The gウュ」・ N ウウゥッョ。ゥセ・@ :shall: ーイッセゥ、セ@ a ᄋ ウ・ー。イ。セ・@ c,lini.c at· the pイッェセ」エ@ Site whe ::- o ·

. ' · · ·,:-: ·. · : N セ・ッ ⦅ ー ᄋ エセ@ \Z M セZiャ Z セLIー ᄋ イ「セセィL@ イVエbイゥスヲャ\ゥヲケゥゥ・。エエィ ᄋ セ。ケゥ」 ᄋ ・ LN N N@ セ@ . .. .. :. ..... . ' . . : . . . . .; . : '.. . . . . . .· ᄋ セ@ .

.. . . . . . :::· · (b! N[Nゥセ・ ᄋ 」。 ᄋ ョセ・ウウゥセョ M セゥOセ@ ᄋ ウャQ Z 。セイイj「ケゥセ N ・ セZ セVセセセョゥエケ@ 。ョ、 M セイ。[ゥョゥョァ@ center キャエィゥャゥセ セ@ ·r: · . . Pro}e_ct ·Site セNカィ・イセ ᄋ ゥョ Z@ ュオャセANpャ・ G@ employmen_ts related capacity building 。ョセNNN@ ;d . :· .: .... .' · .·::· · · · · . tr:aini ng 。」セゥセゥエゥ・ウ@ :sh.al!Ye_ セ M ョNセ・ N イエ。セ\・ョ@ _al1d necess.ary.,'ikills shall be imparted. [⦅G セEゥGセ[@ セ@

. .. . . .. , . .. . . ·:·{¢) .. : _: .. ·. Kセセセ ᄋM ᄋ」V ᄋ [Q」・セ[ゥッセス M セNゥヲセ Z N[ ウゥゥセゥゥ Z@ Z ー ᄋ イYN N セセセMセ Z ⦅MZ セセ@ セ M ュ ⦅ ーャセケュ・ョエ@ Z⦅M セーセッイエセュゥ@ ty based on' 7..Jt. ェセ@" . , .. · .. · ... ··· .

·' : .

· ' · . ·.·· ·training.and. skili. 。 ᄋ ウセ ⦅ セウウョ Q N セセエ ᄋ N@ ⦅ tゥャ ⦅セN@ ᄋセ・ N 」ッ N ョ、。イケ@ e;nploymeut an<;l/or 「オウゥョ M ・ウセ Lセセ エ [セM セ セ@. .:· · ᄋ N ッーーッイセエセョゥエy[@ sh<i.B be. セュ_ヲ・セ@ through M セィ・@ ヲセ」ゥャゥエケ@ ッー・イ。 N セッイ@ or support services . . ' NNLZML セ@ 2. \

. . .. : ., •• •. •• • . • . : t. • ·f-? ᄋ[セセ N@

· :·. · · (d)- .. : The cッイエセ・セウAGッョ。ゥゥセ・@ shall ーイ「 ᄋ セᄋセア・@ エセ。ゥョゥ N ョァ N 。ョ、ᄋ N 。キ。イZセ ᄋ ョ・ウウ@ to labors at plant, セ ゥN セ@wh.icl) ·should.he 。 ᄋ 」ッョGエゥョゥエ。ィウ。」エ ゥ セゥᄋエIイN@ ·. : · · · · · lセ@

.rp

· . . . . . : .. . ... .

· . . ·. .'·t · . : . . - : . .... · : .. ·. セ@. ·'

· ' ., . •, . '·.

ZᄋZN セセ ᄋ | ᄋN@ •· .. ·· · •\. ' '.:.· .. . ,

.... :· · .. · \'

.; j

, , 1' '

. ,

ᄋ セ ᄋ@ ..

. · ...

.,

· . ' ·.

• f セ@ •

;,: ..

. ;

.. ··:.

.. . '•. ..• ·.

.... Zセ@ .

. . . :·

.'.' . ..

•. ' . . · .

: • . •

'; ... ··:.

.. · . • .. ·.·.

. . . . . . . . · .. :: :. . . . . :, セ@ . セ@ セ@ ..... :.. ':·

.· . ··;··· : .. · .- '

. . : .. • .·. '.

•:

·' . ,. :. セZ@ .. : . .; .

. " .. . . •;·

- .. -. . . ·: ; . .

:·• o • I ... ••' .........

',•'

·:.-· •' .. , ..

'• .

. !.

... : .

' · . . :. ·. ·. ...

·.· ._:::.:.· . . M セ@ . :., . . . : :' . :,· .;·

··: · ... : .·',' ... Zセ@

' ::'

.''• .

'! •· .• ..·· ·:

· ... . . . , (,. __ ,:' ;' . ᄋGᄋZNZ ᄋZ セ@ .· ·.: :.' .. .'.; .... . . . ᄋᄋセ@

.· '. . ':..

···:::· ·' . · .•, .. ·.' . :

I :':'

. '.

... " .. . :· . ·· ... ·

···: :,: .·

:.,. '

...

.·_·: : .. . .

. . セN@ .. :· ·. セ@ · .. ·· .. : . ': .. . セ@ . ·.•. ,; . .

. · .. : .

. :· . ·.: .... ': . セM セN@ ,· . ·. : .. ··· .

· ...

....

... ,'(

... ··:

. . · .. ,.

. . .'·

. :; .

... : .

.. '• •,

· . . ·.··. · .. . . . . •;. ··: ...

', ' .. ... .

· ..

-·:· o :' o I

:· . ...

· ... . ·. :: .. : ·.

: . .....

·: ·

., .. ·. ·· ..

. .... . ·· ....

· .. .. ·. ,• : .. ·

.. ·.·.·.·.

.· . ... .

.·. :

',t

·::

:i

Page 1 of 6

CONSENT ORDER FOR ESTABLISHMENT

Order No. 404 /APPCB/CFE/RO-GNT/HO/2016 Dt: 20.03.2017

Sub: APPCB – CFE - M/s. Jindal Urban Waste Management (Guntur) Limited, Sy. Nos. 933 & 938, Kondaveedu (V) Edlapadu (M), Guntur District – Consent for Establishment (CFE) of the Board under Sec.25 of Water (P & C of P) Act, 1974 and Under Sec.21 of Air (P&C of P) Act, 1981 - Issued - Reg.

Ref: 1. Industry’s lr. dt. 18.02.2017 and 20.02.2017. 2. Industry’s revised application received through Single Desk received on

21.02.2017. 3. R.O’s inspection report dt. 01.03.2017. 4. CFE Committee meeting held on 09.03.2017.

1.

In the reference 2nd cited, a revised application was submitted to the Board seeking Consent for Establishment (CFE) for MSW based power plant with installed capacity as mentioned below, with a project cost of 212.905 crores (Rs 212.89 Crores + Rs. 0.015 crore).

S.No Name of the Products and

By-products

Capacity

As per CFE order dt.28.12.2016

As per Revised CFE Application

1 Refused Derived Fuel (RDF) 1068.4 Tonnes/day - 2 Compost 75.7 Tonnes/day - 3 Electricity

(Fuel: MSW-1620 TPD) 15 MWH 15 MWH

By- products 1 Brick and Paver Blocks 20000 Nos/day 20000 Nos/day 2 Iron & Steel (Metal) 0.32 Tons/day 0.32 TPD 3 Chlorinated Hard Plastic 6.5 TPD 6.50 TPD 4 Leachate 48.6 TPD 48.6 TPD

2. As per the application, the above activity is to be located at Sy Nos. 933 & 938, Kondaveedu(V) Edlapadu (M), Guntur District in an area of 62726 Sq. m (15.50 acres).

3. The above site was inspected by the Asst, Environmental Engineer, Regional Office, Guntur,

A.P Pollution Control Board on 27.02.2017 and observed that the site is surrounded by North : Existing Municipal Dump yard

South : Eucalyptus Plantation and hill

East : Existing Municipal Dump yard weigh bridge and Road

West : Hill of Kondaveedu Reserve Forest

4. The Board, after careful scrutiny of the application, verification report of Regional Officer and

recommendations of the CFE Committee, hereby issues CONSENT FOR ESTABLISHMENT to your activity Under Section 25 of Water (Prevention & Control of Pollution) Act 1974 and Section 21 of Air (Prevention & Control of Pollution) Act, 1981 and the rules made there under. This order is issued to produce products as mentioned at para (1) only.

Phone: 23887500

Website :www.appcb.ap.nic.in

ANDHRA PRADESH POLLUTION CONTROL BOARD

PARYAVARAN BHAVAN, A - 3, INDUSTRIAL ESTATE,

SANATHNAGAR, HYDERABAD - 500 018

Single Desk Approval Ref Id : SDPCB008160513

Digitally Signed By B S S Prasad (Member

Secretary\)

Date : 21-Mar-2017 19:44:01 IST

Page 2 of 6

5. This Consent Order now issued is subject to the conditions mentioned in Schedule 'A' and Schedule 'B'.

6. This order is issued from pollution control point of view only. Zoning and other regulations are not considered.

7. This order is valid for period of 7 years from the date of issue. Encl: Schedule ‘A’ Schedule `B'

MEMBER SECRETARY To M/s. Jindal Urban Waste Management (Guntur) Limited, Jindal ITF Center, 28, Shivaji Marg, Delhi Industrial Area, WEST DELHI-110015. [email protected] Copy to: 1. The JCEE, Z.O., Vijayawada for information and necessary action. 2. The E.E., R.O, Guntur for information and necessary action.

Page 3 of 6

SCHEDULE - A

1. The proponent shall obtain Consents for Operation (CFO) from APPCB, as required Under Sec.25/26 of the Water (P&C of P) Act, 1974 and under sec. 21/22 of the Air (P&C of P) Act, 1981, before commencement of the activity.

2. Compensation is to be paid for any environmental damage caused by it, as fixed by the Collector and District Magistrate as civil liability.

3. Floor washing shall be admitted into the effluent collection system only and shall not be allowed to find their way in storm drains or open areas. The industry shall maintain a good housekeeping. All pipe valves, sewers, drains shall be leak proof. Dyke walls shall be constructed around storage of chemicals.

SCHEDULE – B

Water:

1. The source of water is Guntur Municipal Corporation Sewage Treatment plant and the maximum permitted water consumption is as following:

2. The maximum waste water generation shall not exceed the following:

Treatment & Disposal

Source of effluent Treatment Mode of final disposal Boiler & Cooling tower blow downs, DM re- generation water

Neutralization Used for firefighting system makeup, Brick plant and Domestic.

Floor & road cleaning ---- Mixed with the MSW pits.

Domestic (Plant)

Septic tank soak pits

Leachate (as mentioned in the EMP)

Influent Leachate storage tank; Mesh Screens; Oil & Grease Trap Moving Bed Bio film Reactor; Secondary clarifier; Sump Tank; Carbon filter and Sand Filter; Sludge drying beds.

Re-circulated for ash quenching.

S.No Purpose As per CFE order

dt.28.12.2016 As per Revised CFE Application

a) Cooling tower make-up 201 KLD 332.14 KLD b) Boiler make-up 37.86 KLD 37.86 KLD c) Domestic (Plant) 3.255 KLD (Recycled) 3.255 KLD (Recycled ) d) Process(Bricks plant ) 17.13 KLD (Recycled) 30.0 KLD (Recycled )

e) Washings (Floor & Road washings) 6.975 KLD (Recycled) 6.975 KLD (Recycled)

f) Fire fighting makeup 65.1 KLD (Recycled) 65.1 KLD (Recycled) g) Sludge Thickener 14 KLD 34.0 KLD h) Bottom ash cooling 50 KLD 75.0 KLD i) Green belt development 21 KLD 21.0 KLD Total (Fresh +Recycled) 416.32 KLD 605.33 KLD

Sl. No

Source As per CFE order

dt.28.12.2016

As per Revised CFE Application

a) Cooling tower bleed of and SSF rejects 56.84 KLD 69.71 KLD b) Boiler blow down 21.12 KLD 21.12 KLD c) Domestic (Plant) 3.0 KLD 3.0 KLD d) Washings ( Floor & road washings ) 6.0 KLD 6.0 KLD

e) DM Plant regeneration 14.5 KLD 14.5 KLD Total 101.46 KLD 114.33 KLD

Page 4 of 6

3. The Effluent Treatment Plant (ETP) shall be constructed and commissioned along with the commissioning of the activity. All the units of the ETP shall be impervious to prevent ground water pollution.

4. The effluents generated from the cooling shall be treated to the surface water standards

and domestic waste water shall be treated to the on land for irrigation standards, as stipulated under Schedule VI of Environment (Protection) Rules, 1986, notified by Ministry of Environment and Forests, Government of India vide G.S.R.422 (E), dt.19.05.1993 and its amendments thereof.

5. The proponent shall regularly monitor the ground water quality for mercury and other heavy

metals (Hg, Cr, As, Pb, etc) around the Municipal Solid Waste Landfill including surface water bodies in the vicinity. The monitoring data shall be compared with baseline data and requisite measures shall be implemented to prevent any kind of direct/ indirect contamination of water resources in the project surroundings.

6. Separate meters with necessary pipe-line shall be provided for assessing the quantity of water used for each of the purposes mentioned below.

a) Industrial cooling, boiler feed.

b) Domestic purposes.

c) Processing, whereby water gets polluted and pollutants are easily bio-degradable.

d) Processing, whereby water gets polluted and the pollutants are not easily bio-degradable.

7. The industry shall provide digital flow meters with totalisers at inlet of Leachate treatment system for the purpose of measuring quantity of effluents.

Air:

8. The Air pollution Control equipment shall be installed along with the commissioning of the activity and shall comply with the following for controlling air pollution.

Sl.No Details of Stack Stack-1 Stack-2

a) Attached to: Boilers D.G. Set

b) Capacity 2nos X 48 TPH 1 x 1500 KVA

c) Fuel : Municipal solid waste HSD

d) Stack height above ground (m.) 60 m (RCC Common stack)

15 m

e) Air Pollution Control Equipment: Turbo reactor with lime injection followed by the Bag House with activated carbon

coating bags (For each boiler)

Acoustic enclosures

9. Continuous online monitoring equipment shall be provided for the stack attached to

Boiler for Sox, NOx, PM2.5 and PM10. Data thus generated shall be connected to CPCB and APPCB websites for display as per CPCB directions dt.05.02.2014.

10. Regular monitoring of ground level concentration of SO2, NOx, PM10 & PM2.5 shall be carried out in the impact and buffer zone and records shall be maintained. If at any stage these levels are found to exceed the prescribed limits, requisite restorative measures shall be implemented immediately. The location of the monitoring stations shall be fixed in consultation with the Regional Officer of the Board. Consolidated daily reports shall be submitted to the concerned Regional Officer on monthly basis.

11. The proponent shall ensure compliance of the National Ambient Air quality standards notified by MoEF, GoI vide notification No. GSR 826(E), dated. 16.11.2009 during construction and regular operational phase of the project.

Page 5 of 6

12. The industry shall take following mitigation measures to control fugitive emissions during construction and operational stage: Vehicles shall be managed to avoid traffic congestions and shall provide parking facilities.

Mechanical water sprinkling shall be provided on roads and at dusty construction material

storage areas, for suppression of dust. Mechanized handling equipment shall be used for loading & unloading operations.

Vehicles shall comply with emission standards and shall have valid PUC certification. Procurement of machinery / construction equipment shall be in accordance to the

specifications confirming to source noise levels of 85 dB(A).

13. In plant control measures for dust suppression like black top / concrete roads, Water Sprinkling system shall be provided for controlling fugitive emissions from all vulnerable sources.

14. All the dusty raw materials and solid waste shall be accommodated under roof shed with required safety ventilation as approved by the competent authorities. There shall not by any open piling.

15. A sampling port with removable dummy of not less than 15 cm diameter shall be

provided in the stack at a distance of 8 times the diameter of the stack from the nearest constraint such as bends etc. A platform with suitable ladder shall be provided below 1 meter of sampling port to accommodate three persons with instruments. A 15 AMP 250 V plug point shall be provided on the platform.

16. The generator shall be installed in a closed area with a silencer and suitable noise absorption systems. The ambient noise level shall not exceed 75 dB(A) during day time and 70 dB(A) during night time.

17. The MSW shall be stored in a closed area with a negative pressure with the air flow routed through the boiler to prevent odour as mentioned in the EMP report.

Solid Waste:

18. The proponent shall comply with the following:

S.No. Solid / Hazardous waste Quantity Mode of final disposal a) Used Oil / Waste Lubrication

Oil

0.5 TPA sold out to authorized recyclers /re processors

b)

Boiler Ash Fly ash: 32.5 TPD

used for own Brick manufacturing plant

Bottom Ash: 128.16 TPD

sent to Scientific land fill facility for disposal

c) Used Lead Acid Batteries 4nos/Annum returned to dealers on buy back system

19. Adequate safety measures shall be provided in the plant area to check / minimize spontaneous fires in MSW storage yard, especially during summer season.

20. The proponent shall install silo of capacity (200 tons) with breather bags to collect and store ash and its distribution.

Page 6 of 6

21. The following rules and regulations notified by the MoE&F, GoI shall be implemented.

a) Hazardous waste and other wastes (Management and Transboundary Movement) Rules, 2016.

b) Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989 c) Fly Ash Notification, 2016. d) Batteries (Management & Handling) Rules, 2010. e) E-Waste (Management) Rules, 2016. f) Construction and Demolition waste Management Rules, 2016.

Other Conditions:

22. The CFE order No. 404 /APPCB/CFE/RO-GNT/HO/2016, dt. 28.12.2016 is cancelled.

23. The industry shall comply with the following:

The proponent shall start construction work of the project after obtaining

Authorization under Solid Waste Management Rules, 2016 for establishment of

storage, handling and management of Municipal Solid Waste.

The project proponent is informed to take action as per the provisions of the EIA

Notification, 2006 and its amendments thereof, with regard to the Environmental

Clearance (EC), for the required components.

The order is subject to final orders in the W.P pending in the Hon’ble High Court / NGT.

24. Green belt shall be developed all along the boundary & vacant spaces with tall growing trees with good canopy and it shall not be less than 33% of the total area.

25. The proponent shall ensure that there shall not be any change in the process technology, source & composition of raw materials and scope of working without prior approval from the Board.

26. Concealing the factual data or submission of false information / fabricated data and failure to comply with any of the conditions mentioned in this order may result in withdrawal of this order and attract action under the provisions of relevant pollution control Acts.

27. Notwithstanding anything contained in this conditional consent, the Board hereby reserves its right and power under Sec.27(2) of Water (Prevention and Control of Pollution) Act, 1974 and under Sec.21(4) of Air (Prevention and Control of Pollution) Act, 1981 to revoke in the order, review any or all the conditions imposed herein and to make such alternation as deemed fit and stipulate any additional conditions or revoke the order in the interest of environment protection.

28. Any person aggrieved by an order made by the State Board under Section 25, Section 26, Section 27 of Water Act, 1974 or Section 21 of Air Act, 1981 may within thirty days from the date on which the order is communicated to him, prefer an appeal as per Andhra Pradesh Water Rules, 1976 and Air Rules,1982, to such authority (hereinafter referred to as the Appellate Authority) constituted under Section 28 of Water (Prevention and Control of Pollution)Act,1974 and Section 31 of the Air (Prevention and Control of Pollution) Act, 1981.

MEMBER SECRETARY To M/s. Jindal Urban Waste Management (Guntur) Limited, Jindal ITF Center, 28, Shivaji Marg, Delhi Industrial Area, WEST DELHI-110015. [email protected]

Single Desk Approval Ref Id : SDDGW024160053

INDEX

JINDAL URBAN WASTE MANAGEMENT (GUN

Government of Andhra Pradesh

A.P. State Disaster Response and Fire Services Department

Provisional Fire No Objection Certificate

To File No: 2408/GNT/MSB/201 8

The General Manager, Date: 07/05/2018

District Industries Centre, Guntur

Sir,Madam,

Sub: Andhra Pradesh State Disaster Response and Fire Services Department - Issue of Provisional No

Objection Certificate for the Proposed Construction ofNon Multi Storeyed Building of(Jindal

Urban Waste Management (Guntur) Limited) Alok Kumar, Sy No, 933 & 938, Kondaveedu

Village, Edlapadu mandal, Guntur District, A.P - Regarding.

Ref: l. Online Application Dt.2610412018 , Alok Kumar, Sy No,933 & 938, Kondaveedu Village,

Edlapadu mandal, Guntur District, A.P

2. Online Inspection Report submitted by Officers ofthis Department on 05/05/2018.

It is to inform that Alok Kumar have applied for Provisional No Objection Certificate on

2610412018 for proposed construction ofNon Multi Storeyed Building for Jindal Urban Waste Management

(Guntur) Limited at Sy No, 933 & 938, Kondaveedu Village, Edlapadu mandal, Guntur District, A.P The

offrcers ofthe department have scrutinized the information, documents and plans submitted by the applicant

along with the undertaking provided by the applicant, and have submitted the following report.

Boiler & Tipping Floor

2. The builder has proposed to construct a Non Multi Storeyed Building with Ground Floor + 2 Upper

Floors with a height of 'l 1.7 Mtrs for Industrial Occupancy (Category - G2) in a total plot area of 62726.27

sq. meters.

3. The builder has proposed open spaces all around the build lng

4' The builder has proposed to provide following means of escape, as per clauses 4.4 .2.4.3.2 and4.4.2.4.3.4, Part - IV NBC 2016

Side

Space Required as

er

.Ms.No.l19(APBR ,

17) of MA & UD Dept

Open Space Proposed by

the Builderemarks

North 4.5 Meters 15.00 Meters -Nit-East 4.5 Meters 15.00 Meters -Nil-

South 4.5 Meters -Nil-West 15.00 Meters -Nil-

etails of Staircases

BC

eters as per

uired Nos / quired

ased on Floo

r€a

roposed Nos

rseficit

Intemal StaircasesMinlNo.-1.5

Meters

I No. - 1.50

Meters.NiI.

2 External StaircasesMinlNo.-1.5

Meters

4 Nos. - 1.50

Meters Each-Nil-

Total2 Nos 0 Meters -Nil-

I

15.00 Meters

4.5 Meters

I

l

I

7.50 MetersJ

5. The builder has proposed to provide Occupant Load as per unit Exit width:

6. The minimum Fire Fighting Installations required as per Table 7 ofPart 4 of National Building Code of

India 2016 are:

7. The builder has proposed to provide the following floorwise Fire Fighting installations as per Table 7 of

Part - 4 0fNBC oflndia 2016.

Provide ABC-

tg/6 t<g lire extinguishers

WetRiser / DownComer - 100mm with single outlet landing valves.

Provide I Yard Hytlerant for every 45 mts of Travel Distance along the Perimeter'

Note 11: Provide required number ofsets ofpumps each consisting of 2 Electric and I Diesel

SI Floor

Built

up area

(sq

Mtrs)

Occupancy

Type

No of

Occupants

as

declared

by the

builder

No of

Occupants

as per

NBC

Aggregate width

of

Staircases/Doors

Required

(Meters)

Aggregate width

of

Staircases/Doors

Proposed(Meters)

Fire

Doors

Fire

LiftDeficit

IGround

floor1683.46 Industrial 7 168 0.07 6 2 -Nil-

2First

floor1781.55 Industrial 7 178 0.07 7.5 2 0 -Nil-

3Second

lloor810.3 lndustrial 7 8l 0.07 6 2 0 -Nil-

Total 4275.31 z1 427

SI Fire Safety System Minimum Required

I Fire Extinguishers 44 Nos.

Z Hose Reel Systems I 0 Nos.

3 Wet fuser 4 Nos (For Each Floor)

4 Yard Hvdrants YH 45

5 Automatic Sprinkler System 358 Nos

6 l2 Nos

7 Automatic Detection & Alarm System 77 Nos.

8 Underground Tank 150000 Ltrs

9 Terrace Tank 20000 Ltrs

l0 Fire Pump Note 1 I

sl. 0rire

xt,

ose et

rYard

HydrantsSprinklers CP

Auto.

Det.

Underground

Tank

Terrace

Tank

re

ump

IGround

floor1'1 4 141 3

2First

floorl8 4 149 5 32

3Second

floor9 2 68 1

Total 44 10

4 Nos

(For

Each

loor

YH_45

Nos.358 t2 77 150000 Ltrs

20000

Ltrs

Note

11

Pump (standby) of capacity 2280 Litres/min and two Etectric Pump of Capacity 180 Litres/min'

I

0

i

I

I

I

I

I

I

I

i Manually Operatetl Electric Fire Alarm System I

I

I I

I

30II

I

I

II

I

II

I

t5I

I

Flue Gas Cleaning System

2. The builder has proposed to construct a Non Multi Storeyed Building with Ground Floor + Ons gppsl

Floor with a height of l0.l Mtrs for Industrial Occupancy (Category - G2) in a total plot area of 62726.27

sq. meters.

3. The builder has proposed open spac€s all around the building

4. The builder has proposed to provide following means of escape, as per clauses 4.4.2.4.3.2 and4.4.2.4.3.4

, Part - IV NBC 2016

4. The builder has proposed to provide following Doorways / Level Components

sl. Description Width (Mtrs) tion

I Exit 2 East

5. The builder has proposed to provide Occupant Load as per r.rnit Exit width:

Side

Open Space Required as

per

GO.Ms.No.119(APBR,

2017) of MA & UD Dept

Open Space Proposed by

the BuilderRemarks

North 4.5 Meters 15.00 Meters -NiI-

East 4.5 Meters 9.00 Meters -Nil-

South 4.5 Meters 15.00 Meters -Nil-

4.5 Meters 15.00 Meters -Nil-

SI Details of Staircases

Required Nos /

Meters as per

NBC

Required

based on Floor

Area

Proposed Nos /

MetersDeficit

2 Internal StaircasesMin I No. - 1.5

Meters

0 No. - NaN

Meters-Nil-

3 Extemal StaircasesMinlNo.-1.5

Meters

2 Nos. - 1.50

Meters Each-Nil-

Total I Nos. 0 Metcrs NaN Meters -Nil-

oor

trs)

uilt

p

reaupan

eclared

uilder

the

oofccupan

BC

oof

per

pants

ggregate width

aircases/Doors

f

eters)

uired

regate width

taircases/Doors

roposed(Meters

oors

tre

lteficit

lfloor

250 Industrial 3 252 -Nil-

2First

FloorIndustrial 3 25 J 2 0 -Nil-

Total 6 50

fjl;f,T,;J: aire Fighting Installations required as per Table 7 of part 4 of Nationat Building Code of

re Safety Systemlntmum Required

I Fire Extinguishers6 Nos

2 Hose Reel Systems

3 riutoma C S n k CIprr temSys42 Nos

West

I

II

Ii

iFire

I

0.03 2 0I

2500.03

500

l

2 Nos.l

SI Fire Safety System Minimum Required

Terracc Tank 20000 Ltrs

5 Booster Pump 9OO LPM

7. The builder has proposed to provide the following floorwise Fire Fighting installations as per Table 7 ofPart - 4 ofNBC oflndia 2016.

SI Floor Fire Ext, Hose Reel Sprinklers Terrace Tank Booster Pump

Ground

tloor3 I 2l

2 First Floor 3 1 2t

Total 6 2 20000 Ltrs 9OO LPM

. Provide ABC 5 kg/6 kg fire extinguishers

Canteen, Stores & Cement Godown

2. The builder has proposed to construct a Non Multi Storeyed Building with Ground Floor with a height of4.5 Mtrs for Industrial Occupancy (Category - G2) in a total plot area of 62726.27 sq. meters.

3. The builder has proposed open spaces all around the building

SideOpen Space Proposed by

the BuilderRemarks

North 4.5 Meters 9.00 Meters -Nit-

East 4.5 Meters 9.00 Meters -Nit-

South -Nil-

West 4.5 Meters 12.00 Meters -Nit-

4. The builder has proposed to provide following means of escape, as per clauses 4.4.2.4.3.2 and 4.4.2.4.3.4

. Part - IV NBC 2016

4. The builder has proposed to provt de tbllowing DoorwaY s / Level ComPonents

citroposed Nos

ased on Floor

uired

BC

t€rs as per

uired Nos /

etails of Staircases

-Nil-0 No. - NaN

Meters

Min I No. - 1.5

MetersJ Intemal Staircases

-Ni1-0 No. - NaN

Meters

MinlNo.-1.5Meters

External Staircases

NaN Meters0 Meters0 Nos.Total

tionth (Mtrs)riptionIEast2

Exits from Stores, Cement GodownISouth2tn GodownCemeSm torestS tioEx2North2

Exit from CanteenJ

5. The buitder has proposed to provide Occupant Load as per unit Exit width:

4l

,lI

42

ppen Space Reeuired as

lr"'Go.rrts.No.ltg(lpeR ,I

12017) of MA & UD Dept

4.5 Meters | 15.00 M.ters I

II

4

-Nil-

SI Floor

Built

up

area

(sq

Mtrs)

Occupancy

Type

No of

Occupants

as

declared

by the

builder

No of

Occupants

as per

NBC

Aggregate width

of

Staircases/Doors

Required

(Meters)

Aggregate width

of

Staircases/Doors

Proposed(Meters)

Fire

Doors

Fire

LiftDeficit

1

Ground

Floor63 8.9 tndustrial 20 63 0.2 6 2 0 -Nil-

Total 638.9 20 63

SI Fire Safety System Minimum Required

I Fire Extinguishers 7 Nos.

Hose Reel Systems 2 Nos.

3 Down Comer 2 Nos (For Each Floor)

4 Automatic Sprinkler System 54 Nos.

5 Manually Operated Electric Fire Alarm System 3 Nos.

6 Automatic Detection & Alarm System l2 Nos.

1 Terrace Tank 50000 Ltrs

8 Booster Pump 9OO LPM

6. The minimum Fire Fighting Installations required as per Table 7 of Part 4 of National Building Code of

India 2016 are:

. Provide ABC 5 kg/6 kg fire extinguishers

. WetRiser / DownComer - l00mm with single outlet landing valves,

Office

2. The builder has proposed to construct a Non Multi Storeyed Building with Ground Floor with a height of

3 Mtrs for Industrial Occupancy (Category - G2) in a total plot area of 62726.27 sq. meters.

3. The builder has proposed open spaces all around the building

Side

Open Space Required as

per

GO.Ms.No.119(APBR,

2017) of MA & UD Dept

Open Space Proposed by

the BuilderRemarks

North 4.5 Meters 5.60 Meters -Nil-

East 4.5 Meters -Nil-

South 4.5 Meters 12.00 Meters -Nil-

West 4.5 Meters I 2.00 Meters -Nit-

4. The builder has proposed to provide following means of escape, as per clauses 4.4.2.4.3.2 and 4.4.2.4.3.4

, Part - IV NBC 2016

st. FloorFire

Ext.

llose

ReelDown Comer Sprinklers MCP

Auto.

Det.

Terrace

Tank

Booster

Pump

Ground

Floor7 54 3 t2

Total 7 22 Nos (For Each

Floor)54 3 l2 50000 Ltrs 9OO LPM

I

I I

2I

!

I

I

,l 2I

7. The builder has proposed to provide the following floorwise Fire Fighting installations as per Table 7 of

Part - 4 ofNBC of India 2016.

9.00 Meters i

SI Details of Staircases

Required Nos /

Meters as per

NBC

Required

based on Floor

Area

Proposed Nos /

MetersDeficit

4 Internal Staircases0 No. - NaN

Meters-Nil-

5 External StaircasesMin I No. - 1.5

Meters

0 No. - NaN

Meters-Ni1-

Total 0 Nos. 0 Meters NaN Meters -Nil-

4. The builder has proposed to provide following Doorways / Level Components

st. Description Width (Mtrs) Location

I Exit - I 2 West

2 Exir - z 2 East

5. The builder has proposed to provide Occupant Load as per unit Exit width

6. The minimum Fire Fighting Installations required as per Table 7 of Part 4 ofNational Building Code of

India 2016 are:

7. The builder has proposed to provide the following floorwise Fire Fighting installations as per Table 7 of

Part - 4 ofNBC oflndia 2016.

. Provide ABC 5 kg/6 kg fire extinguishers

Power House

2. The builder has proposed to construct a Non Multi Storeyed Building with Ground Floor + 2 Upper

Floors with a height of 8 Mtrs for Industrial Occupancy (Category - G2) in a total plot zrea of 62726.27 sq.

meters.

3. The builder has proposed open spaces all around the building

SI Floor

Built

up

area

(sq

Mtrs)

Occupancy

Type

No of

Occupants

as

declared

by the

builder

No of

Occupants

as per

NBC

Aggregate width

of

Staircases/Doors

Required

(Meters)

Aggregate width

of

Staircases/Doors

Proposed(Meters)

Fire

Doors

Fire

LiftDeficit

I

Ground

floorl l1.16 Industrial l1 0.1 4 2 0 -Nil-

Total IIt.t6 ll

SI Fire Safety System Minimum Required

I Fire Extinguishers 2 Nos

2 Hose Reel Svstems I Nos.

3 Terrace Tank 20000 Ltrs

4 Booster Pump 9OO LPM

SI Floor Fire Ext. Hose Reel Terrace Tank Booster Pump

2 I

Total 2 I 20000 Ltrs 9OO LPM

lMinlNo.-1.51| ,.,... I

10

l0

I

, I crouna

I

| floor I

I

Side

Open Space Required as

per

GO.Ms.No.1l9(APBR,

20rf of MA & UD Dept

Open Space Proposed by

the BuilderRemarks

North -Nit-

East -Nit-

South -Nil-

West 4.5 Meters 7.00 Meters -Nil-

SI Details of Staircases

Required Nos /

Meters as per

NBC

Required

based on Floor

Area

Proposed Nos /

MetersDeficit

5 Internal StaircasesMinlNo.-1.5

Meters

I No. - 1.50

Meters-Nil-

6 Extemal StaircasesMinlNo.-1.5

Meters

I No. - 1.50

Meters-Nil-

Total 2 Nos 0 Meters 3.00 Meters

4. The builder has proposed to provide following means of escape, as per clauses 4.4.2.4.3.2 and 4.4.2.4.3.4

, Part - IV NBC 2016

5. The builder has proposed to provide Occupant Load as per unit Exit width:

6. The minimum Fire Fighting Installations required as per Table 7 ofPart 4 ofNational Building Code ofIndia 2016 are:

7. The builder has proposed to provide the following floorwise Fire Fighting installations as per Table 7 ofPart - 4 ofNBC oflndia 2016.

SI Floor

Built

up

area

(sq

Mtrs)

Occupancy

Type

No of

Occupants

as

declared

by the

builder

No of

Occupants

as per

NBC

Aggregate width

of

Staircases/Doors

Required

(Meters)

Aggregate width

of

Staircases/Doors

Proposed(Meters)

Fire

Doors

Fire

LiftDelicit

IGround

Floor896 Industrial 7 89 0.07 4 2 0 -Nil-

2 First 824 Industrial 7 82 0.07 3 2 0 -Nil-

3 Second 824 Industrial 7 82 0.07 3 2 0 -Nil-

Total

SI Fire Safety System Minimum Required

I Fire Extinguishers 27 Nos

2 Hose Reel Systems 6 Nos

3

4

Down Comer 2 Nos (For Each Floor)

Automatic Sprinkler System 213 Nos.

5 Manually Operated Electric Fire Alarm System

6 Automatic Detection & Alarm System 46 Nos.'7

Terrace Tank 50000 Ltrs

st. Floor Fire Ext. Hose Reel Down Comer Sprinklers MCP Auto. Det, Terrace TankGround

Floor9 2 75 2 l6

4.5 Meters | 12.00 Meters

4.5 Meters | 12.00 Meters

4.5 Meters | 12.00 MetersI

II

-Nil-

I

8544 2tlznl

6 Nos.

,l

st. Floor Fire Ext, Ilose Reel Down Comer Sprinklers MCP Auto. Det. Terrace Tank

2 First 9 2 69 l5

3 69 2 15

Total 27 6 2 Nos (For Each Floor) 213 6 46 50000 Ltrs

. Provide ABC 5 kg/6 kg fire extinguishers

. WetRiser / DownComer - 100mm with single outlet landing valves.

Air Cooled Condenser

2. The builder has proposed to construct a Non Multi Storeyed Building with Ground Floor + 2 Upper

Floors with a height of l3 Mtrs for Industrial Occupancy (Category - G2) in a total plot area of 62726.27 sq.

meters.

3. The builder has proposed open spaces all around the building

4. The builder has proposed to provide following means of escape, as per clauses 4.4.2.4.3.2 and4.4.2.4.3.4

, Part - IV NBC 2016

5. The builder has proposed to provide Occupant Load as per unit Exit width:

6. The minimum Fire Fighting Installations required as per Table 7 ofPart 4 ofNational Building Code of

India 2016 are:

Side

Open Space Required as

per

GO.Ms.No.1l9(APBR,

2017) of MA & UD Dept

Open Space Proposed by

the BuilderRemarks

North 7.50 Meters -Nil-

East 4.5 Meters 7.50 Meters -Nil-

South 4.5 Meters 7.50 Meters -Nit-

West 4.5 Meters 7.50 Meters

SI Details of Staircases

Required Nos /

Meters as per

NBC

Required

based on Floor

Area

Proposed Nos /

MetersDelicit

6 Intemal StaircasesI No. - 1.50

Meters-Nil-

7 Extemal StaircasesMinlNo.-1.5

Meters

I No. - 1.50

Meters-Nil-

Total -Nil-

S I Floor

Built

up

area

(sq

Mtrs)

0ccupancy

Type

No of

C)ccupants

ts

declared

by the

builder

No of

Occupants

as per

NBC

Aggregate width

of

Staircases/Doors

Required

(Meters)

Aggregate width

of

Staircases/Doors

Proposed(Meters)

Fire

Doors

Fire

LiftDeficit

I Ground 78 Industrial 2 7 0.02 4 2 0 -Nit-

2 First 78 Industrial 2,7

0.02 3 0 -Nil-

3 Second 78 Industrial 2 1 0.02 3 2 0 -NiI.

Total 6 2l

nimum Requiredire Safety System

2

Second i 9 I 2 II

i

I

4.5 Meters I

-Nil-

lnairttto.-t.sl

I M",... I

I lNos. | 0 Meters 3.00 Meters

I

I

2

I

234

SI Fire Safety System Minimum Required

I Fire Extinguishers 3 Nos.

2 Hose Reel Svstems 3 Nos.

3 Terrace Tank 10000 Ltrs

I Booster Pump 9OO LPM

sl. Floor Fire Ext, Hose Reel Terrace Tank Booster Pump

I Ground I 1

2 First I I

3 Second I 1

Total ., 10000 Ltrs 9OO LPM

7. The builder has proposed to provide the following floorwise Fire Fighting installations as per Table 7 of

Part - 4 ofNBC of India 2016.

. Provide ABC 5 kg/6 kg fire extinguishers

8. The Officers of the department have recommended to issue The Provisional No Objection Certificate for

the proposed construction of Non MSB Industrial Building (G2) belonging to Alok Kumar Sy No' 933 &

938, Kondaveedu Village, Edlapadu mandal, Guntur District, A.P, subject to the following conditions.

l. The permission accorded doesn't confer any ownership rights. If it is found that the information

furnished is false and fabricated, the permission will be revoked at any stage and the applicant will

be liable for criminal prosecution as per IPC.

2. This permission is given based on the information, documents and drawings provided by the

applicant. The applicant confirms that the information provided and the documents and drawings

submitted electronically are correct. The final approvals of proceedings are subjected to verification

of documents by concerned ofiicial including site visit. Any deviation noticed will lead to

cancellation of NOC.

3. Prior approval should be obtained separately for any change of nature of occupancy or change of

number offloors or area.

4. Structural safety shall be the responsibility of the Owner / Builder / Developer / Architect or

Engineer.

5. Provide one entry and one exit to the premises with minimum width of 4.5 mts and height clearance

of 5.0 mtrs.

6. Provide diesel generator ofrequired capacity as alternate source ofelectric supply.

7. Provide emergency lighting in corridors, common passages and staircases.

8. The occupant load and occupants per unit exit width and minimum travel distance for occupancy

shall be as per clause 4.3 (Table 3), clauses 4.4.2.1, Table 4 Capacity factors, Clauses

4.4.2.1,4.4.2.3(c), 4.4.2.4.2(a) and Table 5 Clauses 4.4.2.1, 4.4.2.2, of part 4-NBC 2016

9. The building shall be suitably compartmented so that fire/smoke remain confined to the area where

fire incident has occurred and does not spread to the remaining parts of the building as per clause

4.5 Part 4 ofNational Building Code of India 2016.

10. Openings in any separating walls in any floor shall be limited to 5.6 meters in area with maximum

height of 2.75 meters. Every wall opening shall be protected with Fire resisting doors having fire

rating of not less than 2 hrs. All openings in the floors shall be protected by vertical enclosures

extending above and below such openings, the wall of such enclosures having a fire resistance ofnot less than 2 hrs and all openings there in being protected with a fire resisting assembly Strictly

Complying with 15:3614 Part-I 1966 and Clause 3.4.5 ofNBC 2016, Part 4. Fire doors should be

provided in each floor.

I

3

I

11. Illumination of means of Exit in Staircases and Corridors shall be provided with DG Set Electrical

Power as per Clause 3.4.7 ofPart 4 ofNBC of lndia 2016.

12. Smoke Venting facilities for safe use of exits shall be provided as per clause 3.4.8,4.4.2.5 & 4.6

Part JV ofNBC 2016. Emergency Power Supply shall be provided for smoke venting equipment

with DG Supply-

13. All Fire Safety Systems shall be provided as per the provisions of Part -4 ofNBC oflndia 2016

14. Levelled hard open spaces as mentioned in the Provisional NOC including 7 meters drive way all

around the building for operation of fire vehicles shall be provided.

15. Fire doors with 2 hrs Fire Resistance shall be provided at appropriate places along the escape route

and particularly at the entrance to the lift lobby, corridors and staircases.

16. Ventilation of Staircases shall comply with Clause 4.4.2.5,4.6 of Part 4 of NBC 2016.

17. No Hazardous materials such as Petroleum products, explosives, chemicals etc should be stored on

any floor of the building.

The builder is hereby advised to follow the conditions mentioned below while applying for

Occupancy NOC :

1. Clause 6.1.2, NBC-PART-IV-2016: Additional Precautions

a) Flammable liquids for household purposes shall be kept in tightly stopper or sealed

containers. For the limits of quantities of flammable liquids to be allowed in various

occupancies, reference may be made to appropriate regulations.

b) No stove or combustion heater shall be located directly under or immediately at the foot ofstair or otherwise so located as to block escape in case of malfunctioning of the stove or

heater

c)All kitchen exhaust fans, where provided shall be fixed to an outside wall or to a duct of

non-combustible material , which leads directly to the outside. The ducts shall not pass

through ares having combustible materials . However, in case of centralized ducting, the dict

shall be provided with adequate protection to limit the spread offire.

d) Stores, engineering workshops, areas of high hazud etc used for storage of substantial

amount of flammable liquids be of 120 min fire resistance rating wall. Such areas shall be

provided with fire doors , to be kept closed and shall be posted with a sign on each side ofthe

door in 25 mm high block letters stating Fire Doors _ Keep Closed.

2. ANNEX-D,_pe!t:Iy, NBC-2016

i. D-3 DRILLS

. D-3.1 Fire drills shall be conducted, in accordance with the fire safety plan, at

least once every three months for building during the first two years. thereafter,

fire drills shall be conducted at least once every six months.

. D-3.2 All occupants of the building shall participate in the fire drill. However,

occupants of the building, other than building service employees are not

required to leave the floor or use the exits during the drill.

. D-3.3 A written record of such drill shall be kept on the premises for a three

years period and shall be readily available for tire brigade inspection'

ii. D-4 SIGNS AND PLANS

. D4. I Signs at lift Landings A sign shall be posted and maintained in a

conspicuous place on every floor at or near lift landing in accordance with the

requirements, indicating that in case of fire, occupants shall use the unless

instructed otherwise. The sigh shall contain a diagram showing the location of

the stairways except that such diagram may be omitted, provide signs

containing such diagram are posted in conspicuous places on the respective

floor.

iii, D-5 FIRE SAFETY PLAN

. D-5.1 A Format for the fire safety plan shall be as given in D-9.10.

. D-5.2 The applicable parts of the approved fire safety plan shall be distributed

to all tenants of the building by the building management when the fire safety

plan has been approved by the fire Authority.

. D-5.3 The applicable parts of the approved fire safety plan shall the be

distributed by the tenants to all their employees and by the building

management to all their building employees.

. D-5.4 In the event there are changes fiom conditions existing at the time the fire

safety plan for the building was approved. and the changes are such so as to

require amending the fire safety plan. within 30 days after such changes an

amended fire safety plan shall be submitted to the fire brigade for approval.

iv. D-6 FIRE COMMANDS CENTRE

. A Fire Command Center shall be established in the building.

9. The following deficiencies are identified by the ofiicers of the department and needs to be attended to by

the management.

1. This NoC is issued from fire safety point of view only basin8 on

recommendation of the inspection committeer Guntur, 2. This NoC is not fon

claiming propnietary or ownership rights. Funther, in case of any deviation

noticed with nespect to this Noc after issuance of this Noc, the same Noc shallbe liable for cancellation at any time.

3. BoiIers, stones, canteen and office buil.dings, there is no requirement ofstaircases, But, open spaces around the buildinBs shaIl not be less than 4.5

Mtrs.,. Yard Hydrants shall be pnovided. Common pump house of not less than 1620

LPM capacity of one electrical, one diesel and 180 LPM capacity of jockey pump

shall be provided,

10. This Provisional No Objection Certificate is issued with the advice that the Non Multi Storeyed Building

should not be occupied and the operations shall not be commenced without obtaining No Objection

Certificate for Occupancy from this Department about the satisfactory installation of above fire safety

measures.

Your Sincerely,

Regional Fire Office r1llililriltiltilrililililtffi iltilililtilrffi tilrililililffi rffi tffi tiltf

2408/GNT/N5B/2018

1r

Andhra Pradesh, Vijayawada

Copy to Alok Kumar, Jindal Urban Waste Management (Gr.rntur) Ltd, Sy.No- 933, 938, Kondaveedu (V),

Edlapadu (M), Guntur (Dt), A.P

Copy to Chief Office for Record Purpose

Copy to District Fire Officer Concerned

Copy to Assistant District Fire Officer Concerned

Copy to Station Fire Officer Concemed

22.05.18

JINDAL URBAN WASTE MANAGEMENT WASTE TO ENERGY PLANT (15MW)

Next

GNT-WTE-PLB-01

1

Scale

-

Size

Sh.- -

Appd.

Chkd.

Date

Drawn

Design

Rev.

0

(GUNTUR) LTD. (A.P.)

K.S.KPLANT LAYOUT WITH BUFFER ZONE AREA

TITLE:PRASAD

M.V.CHARY

R O A DR O A D

933

R O A D

19200

42150

32120

44130

174120

4370

32140

17170

9830

9750

139090

153640

B1

B2

B3

B4

TREATED

WATER

GUARD ROOM

WE

IGH

BR

IDG

E10m

x 3

m

WE

IGH

BR

IDG

E10m

x 3

m

CONTROL ROOM

GUARD

WATER

STORAGE

TREATMENT PLANT

TEMPLE

ROOM

WATER

FIRE WATERTANK

FIRE &

WATER

P.H.

STORAGE

TRUCK PARKING AREA

RESTROOM

X+416.600

Y+238.815

Sto

rm D

rain

Wate

r

X+20.780Y+278.781

X+22.242Y+141.438

X+416.600Y+57.620

181630

25690

41210

181450

RAW

AUXILIARY COOLING TOWER

X+139.00Y+220.00

(+)63.00

ST

OR

E R

OO

M

ST

OR

E

OPEN STORAGE AREA

X+179.000Y+147.000

X+169.000Y+167.000

(+)60.50

FFL

& SWITCHYARD

17360

X+373.500Y+256.500

R O A D

RAIN WATERHARVESTING

(+)5

9.3

0

Storm Drain Water

Sto

rm D

rain

Wate

r

Sto

rm D

rain

Wate

r

(+)6

0.3

RA

MP

RA

MP

RAMP

6m

WID

E R

OA

D

6m

WID

E R

OA

D

6m WIDE ROAD

6m

WID

E R

OA

D

6m WIDE ROAD

Y+203.000

Y+249.000

X+

305.0

00

X+

359.0

00

(+)60.30

(+)59.30

SLOPE

(+)63.00

(+)59.00

FGL

TO NATURAL DRAIN

6m

WID

E R

OA

D

6m

WID

E R

OA

D

X+

130.0

00

X+

185.0

00

6m

WID

E R

OA

D

X+

404.5

00

Y+226.0006m WIDE ROAD

(+)59.30(+)59.30

6m

WID

E R

OA

D

SLOPE

Y+86.500

(+)60.00

FGL

(+)6

0.3

0

SLOPE

X+

44.0

00

(+)59.50

FFL

TG BUILDING

6m WIDE ROAD

Y+249.000

6m WIDE ROAD

10000

IL=59.5

17

10000

(+)60.5

(+)60.30

(+)63.00

(+)60.30

(+)60.30

(+)60.30

(+)60.30

(+)6

0.3

0

SLOPE

(+)59.30

SLOPE

(+)59.30

SLO

PE

SLO

PE

SLO

PE

(+)60.30

(+)59.30

(+)59.30

GATE 7M WIDE FOR LIGHT VEHICLE

GATE 15 m WIDE FOR TRUCK ENTRY

WATER LINE FROM STPWITH

TOILET

POWER EVACUATION LINE

Y+239.000

X+291.000Y+211.425

11KV/33KV TRANSFORMER

(+)59.00

FGL

(+)59.00

FGL

AIR COOLED CONDENSER

ST

(+)60.00

FGL

(+)60.8

CEMENTGODOWN10 m x 10 m

SU

MP

FO

RC

UB

ES

CU

RIN

G

1

10

11

12

13

14

17

18

19

20

PARKING SHED

D

Verandah

TOILETSSEPTICTANK

OFFICE-1 OFFICE-2 OFFICE-3

TRUCK

X+

359.0

00

6m

WID

E R

OA

D

FGL

D

V

WA

SH

BA

SIN

WA

SH

BA

SIN

CIV

IL

QC

LA

B5m

x 4

m

2m x 3m

12

12

L

(+)69.5

FLOOR

TIPPING

6m

WID

E R

OA

D

X+

267.5

00

CHIMNEY

FUTURE EXTENSION

1

(+)61.30

STORAGE PIT

BOILER FEED (+)82.50

C OF BOILER

intermittent blow down flash tank

GUARD

FLAP GATE

STOPPER

RAIL

EOT CRANE 15TWITH GRAB

HOPPER#2FUTURE

HOPPER#1

EOT CRANE 15TWITH GRAB

GRAB MAINTENANCE

#2

C OF BOILER#1

6

6

7

8

9

X+255.000Y+208.500

X+216.360Y+236.900

13000

13000

X+263.000Y+243.425

X+273.000Y+222.700

2

3

4

5

6

7

8

9

10

11

8000

6000

6000

7000

7000

6000

6000

7000

7000

8000

ABCDEFGHJKLMN

8000

8000

5375

6000

6000

5375

7550

2325

6300

7200

4500

5000

2

5

5

DM WATER STORAGE15

BO

ILE

R F

EE

D

PU

MP

AR

EA

X+329.550Y+122.400

X+299.250Y+190.400

(+)69.5

(+)59.00FGLFGL

(+)56.50(PIT BOTTOM)

(+)59.50

FFL

(+)69.5

COMPRESSOR , RO ,DM UNIT

FFL (+) 59.50

AT GROUND FLOOR

9

MA

TE

RIA

L R

EC

OV

ER

Y

4

SLO

PE

1:1

1

FLUE GAS

SCRUBBER-2BAGFILTER-2

SCRUBBER-1

BAGFILTER-1

LIME BULKER

ID FAN-2

ID FAN-1

INLET

FLUE GASINLET

VFD PANEL (ID FAN)

Panel Room

MCC & VFD PANEL LOAD CELLCONTROLLER

ES/OSPLC

Cable Trench1500X1500

Cable Trench1500X1500

59.500(F.F.L.)

D

BC-9

X+237.60Y+180.70

X+273.92Y+149.40

X+231.64Y+162.40

SUMP

Cement godown

200 CUM

(10M x 10M x 2M)

DG Foundtion

WATER SUMP

BORE WELL

Batching plant (at Present)

BORE WELL

(at present)

GUEST

HOUSE

IL=59.5

17

Rock

Rock

Rock

SLOPE

SLOPE

SLOPE

Rock

Rock

RockRock

Rock

Rock

CEEKAY OFFICE

GODOWN CEEKAY

Toilets

Rock

LDOTANK

LEACHATE TREATMENT

PLANT

1

2

3

4

5

6

(+)5

595

(+)8

000

AB

DE

C

2500

C OFALTERNATOR

C OF TUR.LEXHAUST

C O

F T

UR

BIN

EL

L

(+)8

000TOG.

C O

F A

LT

ER

NA

TO

RL

(±)0.00(±)0.00

VV

AU

X.T

RA

NS

FO

RM

ER

S

FUTURE

16

SW

ITC

H Y

AR

D

Pannel s

hed

DG SET

6 m

x 1

0 m

MC

C L

T P

AN

EL

AP

FC

P

AN

EL

6 m x 4 m

FREEZER

S.S. SINKGas Stove

Wate

r coole

r

DO

OR

Pro

jecto

r scre

en

WINDOW

DOOR

EXHAUST FAN

WIN

DO

W

WINDOW

DOOR

EXHAUST FAN

FA

CIL

ITY

DP STRUCTURE

BC-1

BC-2

BC-3

BC-5

BC-6

BC-7

BC-8

SHREDDERFUTURE

SEPARATOR

BALLISTIC

SEPARATOR

BALLISTIC

FUTURESHREDDER

#1

#1

9479

87.1 mtr

87.7 mtr

48.4

mtr

43 m

tr

284.8 mtr

68.1

mtr

69.6

mtr

99.6 mtr

299.3 mtr

282. 6 mtr

108.5 mtr

MSW PITCORE

ACTIVITYAREA

SLF LAND

AGRICULTURE LAND

NO HABITATION

RE

SE

RV

E F

OR

ES

T

NO HABITATION

OPEN FIELDS

Habitation

Distance

600 mtr

From Core

Activity Area

Page 1 of 9

essor

Sf CON D PART.

1.13 ee

,

1 1 ill z [i it)

)4 WOLliiC,LMY 3.11;Al u t ql ANDHRA PRADESH

0 \\\1.s. . - IPate:ikk:‘ It3c*.-' 1 1 jut 2018

r •u,_,1100 )

1 t

r Whom:-SIA • ;i 3-7 ,4e,A11- ?mo'Se t\y ,

LAND LEASE AGREEMENT

its DEED OF LEASE AGREEMENT is made on 19 th day of JULY in the Year 2018.

3

BETWEEN

CAJNTUR MUNICIPAL CORPORATION, established under the Urban development Authority Act 1974

(Government of Andhra Pradesh) and having its registered office at Guntur Municipal corporation

*resented by SHRI. SRIKESH. B. LATKHAR, S/0 BALAJI LATKHAR, aged about 34 years, the

Commissioner Guntur Municipal Corporation (herein after referred to as "Lessor", which expression

shall, unless repugnant to the context or meaning thereof, mean and include its successors and

assigns) of the ONE PART. (Authorized to execute the land lease agreement as per orders of the

qp(lector and District Magistrate Guntur in 11.Dis.No.4426/2007 -E1 Dated 06-02-2018). A DHAI2

$953 3302. 35 -4-5 AND

M/S. JINDAL URBAN WASTE MANAGEMENT (GUNTUR) LIMITED, a company incorporated under

tie Companies Act, 1956 /2013 and having its registered office at A-1,UPSIDC INDUSTRIAL

AREA,NANDGAON ROAD, KOSI KALANDIST, MATHURA (UTTAR PRADESH)-281403 represented by

itib authorized officer, Shri. MUNDURU VEERACHARY, Sio. Shri. M. NARASIMHARAO, (Aadhar

No.:7271 7097 4294) aged about 52 years, the President (AP Projects) of the Company. (Herein

after referred to as "Lessee", which expression shall, unless repugnant to the context or meaning

thereof, mean and include its associate /group companies, successors and permitted assigns) of the

Presentation Endorsement: Presented in the Office of the Joint Sub-Registrar, Phirangipuram along with the Photographs & Thumb Impressions as required Under Section 32-A of Registration Act,

1908 and fee of Rs. 6500/- paid between the hours of 1/4-\ and ix ~ on

the 20th day f JUL, 2018 20th day of JUL, 2018 20th day of JUL, 2018 by Sri Srikesh

B Latkhar Execution

admitte by (Defaili of all Executants/Claimants under Sec 32A):

SNo-cd It b b Igoe s 61011 Photo Aadhar Photo Address

Signature/Ink

Thumb Impression

1-LE

MUNDURU VEERACHARY[ R)MIS JINDAL

URBAN WASTE MANAGEMENT

NO IMAGEII (G_NTUR ) LIMITED

MUNTATTM VEERACHARY R S

[72. , I , 2018-2580] FOUND

LATHKAR SHRIKESH[RIG

UNTUR MUNICIPAL CORPORATIO

N

Generated On:20/07/2018 04:58:11 PM

REPRESENT

JMD LORD'S, FLAT NO-204,BHARATHI

NAGAR 7 ROAD,VIJAYA WADA(MCORP)

(PART), VIJAYAWADA( URBAN),KRISH

NA

iN0 IMAGE

FOUND

CHAKRAPANI SAKALA[R]GU

NTUR /1 MUNICIPAL CORPORATI

N

REP,.A

ESENT

YARA RAGHAVAIAH

NAIDU STREET,VIJAY

AWADA (URBAN), VIJAYAWADA (URBAN),KRIS

HNA

7

2-LR

CHAKRAFANI SAKALtuliimUNTUR I

(726.1-2018-2500)

/e/ LATHKAR SNRIKESH R GUNTU

t... , [726-1-2018-25801

3-LIZ

NO IMAGE

FOUND REPRESENT

JOINT

COLLECTOR BUNGALOW,C

ONTONMENT,V

IZIANAGARAM(

MOG), VIZIANAGARA

M,VIZIANAGAR

The Seal of

o(uf Sof#1,,egIstra

Office Phirangipuram

46•

Whereas the Guntur Municipal Corporation an Urban Local Body (ULB) and surrounding 08 urban

local bodies including Vijayawada Municipal corporation and 07 Municipal Councils viz, 1) Tenali

Municipality, 2) Narasaraopet Municipality, 3) Chilakaluripet Municipality, 4) Sattenapalli

Municipality 5) Ponnur Municipality, 6) Mangalagiri Municipality, 7) TadepalliNagar Panchayat,

consisting a total area of 341.78 Sq.kms and an estimated population of 24,11,352 Lakhs (in the

year 2011) evolved a project for processing and disposal of Municipal Solid Waste (MSW) at

Scientific Landfill (Project) and Waste to Energy processing.

In order to achieve economies of scale and for better coordination the participating above urban

Local Bodies have authorized the Guntur Municipal Corporation (Lead ULB) to develop Project on

their behalf for enabling construction of Waste to Energy Processing Facility processing of MSW and

disposal of MSW at Scientific Landfill.

Accordingly the Lead ULB Guntur Municipal Corporation entered into Concession Agreement on

06.02.2016 with the Concessionaire i.e. M/s. Jindal Urban Waste Management (Guntur) Limited,

Concession Agreement and appointed the Concessionaire to perform to execute and implement

project under agreed terms and conditions as set forth in the said Concession Agreement for a

period of 25 years.

for due implementation of the project arid to discharge its obligations under the Concession

Agreement by the Concessionaire the Lead ULB Guntur Municipal Corporation is now handing over

the property admeasuring Ac 15.50 cents mentioned in the schedule herein after described along

with site map attached thereto to the Concessionaire by way of land lease agreement (Agreement)

for the purposes of performing, executing and implementing the project including constructing,

Operating and maintaining the integrated MSW Processing Facility and Scientific Landfill, on the

Demised Premises, on the terms and condition and subject to the covenants and stipulations

hereinafter contained.

NOW THIS INDENTURE OF LEASE WITNESSETH AS FOLLOWS:

1.This Lease Agreement shall be co-terminus with the Concession Agreement and is to be

read, for any interpretation; together with the provisions of the Concession Agreement.

2.The terms that are used but not defined in this Agreement shall have the same meaning as

given to them in the Concession Agreement.

3.In consideration of the Lessee undertaking to implement the project in accordance with the

provisions of the Concession Agreement and undertaking to pay the Lease Payment ("Lease

Payment") stipulated in Clause 4 below; the Lessor hereby demises to the Lessee, all the

land (together with any physical structure existing thereon) which is described, delineated

and shown in the Schedule hereto (the "Demised Premises"), to hold the said Demised

Premises, without interruption or interference together with the full and tree right and

liberty of way and passage and other rights in relation thereto, for as long as the Concession

Agreement does not lapse due to expiry of its terms or is not terminated earlier in

accordance with the provisions thereof. The Lessor be entitled to handover possession of

the Demised Premises in parts. The term of this Agreement shall be co-terminus with the

Concession Agreement. The Lessor hereby agrees and authorizes the construction, operation

and maintenance of each of the Project Facilities on the Demised Premis4 in accordance

with the terms of the Concession Agreement.

Lessee ssor 4,anage

Page 2 of 9

Commissioner-

MUNICIPAL CORPORATIO'.

GUNTUR.

AM

Identified by Witness:

SI No Thumb Impression

Photo

1

P.RAMA KRISH61A::20 07 2010.16::

[726-1-2018-2580

2 z •••••,

f f 726.1-2018-2580] P.RAV1SANKAR::20 7 2018.1 ,

In the Form of

Patter RAR-1 6 4.

t!IllkiANGIFUtAM

Name & Address

P.RAMA KRISHNA

S/0 KUTUMBAIAH

HYDERABAD

P.

P.RAVI SANKAR

S/O GURUSWAMY

TADIPARTHI

Signature

kk,onz

P)A

-1 20th day of JuIy,2018

Signature of J T S BREGISTRAR164

h angiurarn

Section 88

`3"--1-1

I have satisifed myself as to the execution of the Instrument by who Is exempted from(-N".1 3'•--Vis5--1---

personal appearance under section 88(1) of the Registration Act, 1908

Date

Endorsement:

Desc

Online Stamp Challan Cash ' SD u/s 16 Stock DD/BC/

Papers u/s 41of IS Act of IS act

SD 0 100 960000 0 0 0 0 960100

TD 0 NA 0 0 NA 0 0

RF 0 NA 6500 0 NA 0 6500

UC 0 NA 500 0 NA 0 500

TOT 0 100 967000 0 0 0, 967100

NOTE TaTransfer Duty, SD:Starnp Duty, RF:Rogistration Fee ,UC:=User Charges, TOT:Total, Desc:Description

Rs. 960000/- towards Stamp Duty including T.D under Sertion 41 of I.S. Act, 1899 and R:_-,. .6500/- towards Registration Fees on the chargeable value of Rs. 6396917/- was paid by the party through Challan/BC/Pay Order No ,2101558401,2101559475,2101559525 dated ,19- JUL-18,19-JUL-18,19-JUL-18.

Total Holding Pay Order

oCE

The Seal of

()int Subitogisl.r.si

Office

Phirangipuram

Generated On:20/07/2018 04:58:11 PM

Lessor

Commissioner

MUNICIPAL CORPORATION

GUNTUR

Page 3 of 9

?pager/4,

Lessee

/>-

4. In consideration of the handover of the Demised Premises under this Agreement, the Lessor

shall, from the Commercial Operation Date (COD), receive a Lease Payment payable per

annum as per the following Table on or before the 10 1h day of the first month in each

Accounting year. The Lease payment per acre for the Demised Premises shall be as per

Background bid Documents as per Minutes of meeting held with WtE developers and

officials of stakeholders by Principal Secretary, MA&UD., on 09.12.2016 at 4.00 pm in

Velagapudi, and Endt.No.3344/2015/M3,on 13.12.2016 ENDORSEMENT issued by Director

of municipal Administration,Govt of AP, Gorantla, Guntur.As per the provisions of

G.O.No 571 Revenue (Assignment - I) Department date:14.09.2012, 10% of the bid

document value is fixed as price per acre. The Lease rentals shall be enhanced in every block

of 5 years by increasing 10% on the lease rental of the previous block of 5 years. As per Bid

document value land cost per acre: Rs33.80 Lakhs. All taxes, including the lease tax, in

relation of the Lease of the Demised Premises shall be borne and paid the Lessee.

The Government of Andhra Pradesh vide GO.Ms.No 509 Revenue (Assignment -

Department dated:14.11.2017 accorded permission to the District Collector Guntur to

alienate / Transfer an extent Ac 51.24 cents Government Land (AWD) in sy.,No 933 to an

extent of Ac 6.S4cents,SyNo 938, Ext. Ac .8.96 cents,Sy No 947 Ext Ac 6.60cents, Sy No .949

I-xt Ac 3.66 cents Sy no 951 Ext Acs 7.20 cents, Sy.No 952, Ext Ac. 16.64 cents, Sy no 954 Ext

: Ac 1.64 cents etc...Govt land (AWD) of Kondaveedu (V) Edlapadu (M),Guntur District in

favour of Municipal Administration & Urban Development Department for establishment of

compost yard for the purpose of Municipal Corporation, Guntur on free of cost basis,

subject to issue of notifications U/S 4(1) (c) of AP Assigned lands (POT) Act 1977 for utilizing

the same for public purpose, subject to certain conditions. In pursuance of the orders of the

Government the Collector and District Magistrate Guntur Vide proceedings

No. Rdis.No.4426/2007-E1 dated: 07.01.2018 transferred and allotted an extent of Ac

51.24 cents of Government Land (AWD) described above in favor of the Municipal

Administration and Urban Development Department on free of cost for establishment of

Compost yard for the purpose of Municipal Corporation Guntur for government purpose for

utilizing the same for public purpose subject to conditions in addition to the conditions

under BSO 24 and GO.Ms.No. 571 Revenue (Assignment - I) department

dated.14.09.2012.The Collector and District Magistrate Guntur also directed

ThasildarEdlapadu Mandal to handover the possession of above land duly making necessary

changes in the webland and mandal records to submit the copy of handedover possession

of the land certificate.

The Collector and District Magistrate Guntur vide certificate in R.Dis No.4426/2007 dated,

06.02.2018 ordered that an extent of Ac 15.50 cents the Sy.No. 933 and 938 of Kondaveedu

out of Ac 51.24 cents of lands alienated in favor of Municipal Administration an Urban

Development department has been allotted to the M/s. Jindal Urban Waste Management

(Guntur) Limited for construction of Waste to Energy project for a period of 25 years on

lease basis as per the Concession Agreement entered by the Lead ULB i.e. Guntur Municipal

Corporation with M/s. Jindal Urban Waste Management (Guntur) Limited. The Collector and

District Magistrate permitted the Commissioner, Guntur Municipal Corp • e. ute

Generated On:20/07/2018 04:58:11 PM

The Scat of

olnt Subqegistra

Ofrice Phiranglpuram

a

Date

20th day of JuIy,2018

Signatu f Registering Officer

angipUram , •

RV. NAGESt ARARAO JOINT S1JD-REGISTRAR-164

PHIRANG1PURAM

CHAS CHALLAN DETAILS AS

SE>i. Bmnch C;ode t.', !'"

- —

I

CA? 7117 22-5-17 cf6ccioc).. _ _ _ 6160c4c7

.52c'

5C) (167oon

i0IN 1 RAFZ.164

V. WARApAo

PHIRANGIPURANI

the land lease agreement in respect of property admeasuring Ac 15.50 cents in Sy.No933

Ac 6.54 cents and Sy.No. 938 Ac 8.96 cents of Kondaveedu Village,Edlapadu Mandal,

Guntur District in favor of M/s Jindal Urban Waste Management (Guntur) Limited for

establishment of Waste to Energy plant operations for a period of 25 years on lease basis.

The Collector and District Magistrate Guntur directed the Registration and Stamps

department to register the lease agreement concluded between the Guntur Municipal

Corporation in respect of property admeasuring Ac 15. 50 cents in Sy.Nos 933 and 938 of

Kondaveedu village, Edlapadu (Mandal) Guntur District (the Sy.No are classified as

prohibited properties under section 22 A (1)(b) of Registration Act 1908).

EXECUTION OF NEW LAND LEASE AGREEMENT:

As per provisions laid down in the schedule 19 of the concession agreement made on

06.02.2016 the Government of AP has accorded permission to lease out the land under

G.O.MS NO 160 MA& UD (J2) Department to Guntur municipal corporation to lease out the

land in sy.nos. 933 & 938 at Kondaveedu (V), Edlapadu (Mandal), Guntur (Dt) in favor of

M/S Jindal urban waste management (GUNTUR) Ltd for setting up 15 MW waste to energy

project .Accordingly the Land lease agreement has been entered by and between the lead

U113 Guntur Municipal Corporation and MIS Jindal Urban Waste Management (GUNTUR) Ltd

on 15.12.2016. Whereas due to administrative delay inalienation of land to Guntur

Municipal Corporation and delay in issuance of the orders exempting the stamp duty 2% on

• the improvements on the project building by the Government as requested by the

M/s Jindal Urban Waste Management (Guntur) Limited the land lease agreement document

could not be presented before the sub-Registrar within 4 month of time as stipulated in the

Registration Act 1908. Therefore on the advice of District Registrar of Narasaraopeta vide

letter No.G1 599/2018 dated: 18.05.2018 stating that the land lease agreement entered

between Guntur Municipal Corporation and M/s Jindal Urban Waste Management (Guntur)

limited dated: 15.12.2016 could not be allowed for registration as time allowed for the

presentation of the document from the date of execution has been lapsed i.e. 4 months

from date of execution without fine and another 4 months with fine. Therefore on the

directions of Municipal Commissioner Guntur, the present land lease agreement is

executed.

Stamp Duty Exempted on improvements made by lessee, G.O.MS. NO. 337, Revenue

(Registration. II) Department Dated 28.06.2018:

The Government of AP has exempted payment of stamp duty on the value of improvements

for M/S Jindal urban waste management(GUNTUR) Ltd in the leased land at Sy no 933& 938

Kondaveedu (V), Edlapadu (Mandal), Guntur (Dt) for setting up waste to energy plant under

section 9(1) (a) of Indian stamp Act 1899 and accordingly issued orders vide G.O.Ms.No.

337, Revenue (Registration. II) Department, dated 28.06.2018.

Term of the lease amount and mode of payment of lease:

The lease amount payable by lessee in favor of lessor is finalized as per the Minutes of the

Meeting held with WtE (Waste to Energy Project) developers and officials of stake holders

by the Principal Secretary Municipal Administration and Urban Development department on

09.12.2016. During the meeting it was decided to adopt GO.Ms.No 571 uniformly across all

the ULB for calculation of Lease payment instead of GO.No.56. As per the Go.No.571, 10%

of the bid document value is fixed as price per acre The Lease rentals shall 17e, enhanced in

ageo Lessee

Page 4 of 9 Commi.s.siorier

MUNICIPAL CORPORATION

GUNTUR.

Cx\

/

tricc•

Generated On:20/07/2018 04:58:11 PM

a Tim seal ot

miot Subltegiskrar

Orrice

Phirangipuram

CEkilFiC.4TE OF REGISTRATION Reuistered as document No.2-5j of 20 Book-I and assigned

ide.nttion number

291.r scanni

REG!S& RING

PV NA WA RAR jC)INT SUB-R

PHIRANGIPURAM

c v ia FR: Gq, sc A rite lloctonent ha :Hoc,/ with the Igenti(ic

every block of 5 years by increasing 10% on the lease rental of the previous block of 5 years.

As per Bid document value land cost per acre: Rs 33.80 Lakhs. Accordingly an amount of Rs.

338000 per acre per annum towards lease was fixed. Accordingly a lease amount of Rs.

5239000 per annum was fixed for the lease land. The lease rentals shall be enhanced in

every block of 5 years by increasing 10% on the lease rental of the previous block of 5 years.

Also as per Concession Agreement the original Commercial Date of Operation 06.06.2018

(28 months from the date of signing of the Concession Agreement) and the Commercial

date of operation is extended to December — 2018 by the Commissioner, GMC, vide letter -

Lr.No: 26/EE/GMC/WTE/2017 - 18 dtd: 17.01.2018. Accordingly the details of lease payment

IIICIII.IVIICV VGIVVY •

SI.No Period of Lease Lease Amount per

annum

Total Rent

(Annual Rent X 5 years)

1 01.01.2019 to 31.12.2023

(5 years)

Rs. 5239000 Rs.26195000/-

2 01.01.2024 to 31.12.2028

(5 years)

Rs. 5762900 Rs. 28814500/-

3 01.01.2029to 31.12.2034

(5 years)

Rs. 6333190 Rs. 31695950/-

4 01.01.2035 to 31.12.2039

(5 years)

Rs. 6973109 Rs. 34865545/-

5

. _. Total

01.01.2040 to

31.12.2045(5 years)

Rs. 7670423 Rs. 38352115/-

25 years Rs.159923110/-

Average Annual rent = Rs. 159923110/25 years = Rs.6396924/-

33

80

00

r.)

L.-)

et, to Lead ULB indicated as:

7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

37

18

00

37

18

00

37

18

00

37

18

00

40

89

80

40

89

80

40

89

80

40

89

80

40

89

80

44

98

78

44

98

78

44

98

78

44

98

78

44

98

78

49

48

66

49

48

66

49

48

66

494

86

6

49

48

66

57

62

90

0

57

62

90

0 0

06

Z9

LS

06

16

EE

9 6

33

919

0

63

39

19

0 0

61

6E

E9

. 6

33

91

90

60

TE

L6

9

60

L6

9

60

L6

9 6

97

310

9

69

73

10

9

76

70

42

3

76

70

42

3

76

70

42

3

767

04

23

767

04

23

ial

e

ent

s.)

.50

is

52

39

00

0

523

900

0 I

52

39

00

0

52

39

000

_

1

52

39

00

0 0

06

Z9

LS

00

6Z

9L

S

Yea

Annu

leas '

paym

(in Rs.

Acrc

Ann

leas

paym

(in R

fo

Ac.15

Cen

5. The Demised Premises are being handover to the Lessee, under this Agreement, free from

any Lncumbrances (other than the existing physical structures thereon which has been

inspected by the Lessee and agreed to be taken over in accordance with the terms of the

Concession Agreement), whether legal or physical in nature. At any time during the terms of

this Agreement if the Lessee discovers any Encumbrances under the Demised Premises

which materially adversely affect its rights in relation to the Demised Premises the Project, it

vtageniele

is Lessee

Page 5 of 9 ,ommissioner

MUNICIPAL CORPORATION

GUNTUR,

iAti7-.7- )6D

fic-P4)

ec? J7

IST

RA

R1

64

y

,1/40cf. c), -'"

Generated On:20/07/2018 04:58:11 PM

1'he Seal, of

olot Sublleglstrar

Office Phirangipuram

0

Page 6 of 9

shall notify the lessor, which shall, within twenty one (21) days from the receipt of the

notice, either remove or clause to be removed such encumbrances at its own cost. In the

event that the Lessor fails to remove such encumbrances within twenty one (21) days from

the notice thereof, the Lessee may remove or cause to be removed such encumbrances and

the costs and expenses or consequential liabilities incurred in respect thereof shall be

reimbursed to the Lessee by the Lessor.

6. The Demised Premises are being handover to the Lessee, under this Agreement only for the

purposes of the project including for the purposes of developing, establishing, designing,

constructing, operating and maintaining the Plant, which the Lessor is desirous of being

constructed, operated and maintained on the Demised Premises for the purposes of

enabling the processing and disposal of MSW in accordance with the Concession Agreement.

The Lessor hereby authorizes and consents to the receipt of consignment of Municipal Solid

Waste, the Storage and processing of Municipal Solid Waste to energy inside the Demised

premises and disposal of MSW at Scientific Landfill outside the Demised Premises.

/. The Lessor herby authorizes the Lessee, to construct, erect, own, operate, and maintain any

superstructures, facility or any movable or immovable structures comprising each of the

Project Facilities on the Demised Premises and for that purpose also remove, renovate, use

or demolish any structures that may be existing on the Demised Premises as of the date of

this Agreement. The Lessee hereby agrees that the construction, operations and

maintenance of the each Project Facility at the Demised Premises and the receipt, storage

and processing of Municipal Waste at the Demised Premises, being undertaken pursuant to

the Concession Agreement granted by it and forth purposes of enabling the Participating

ULBs to discharge their functions of managing, processing and disposing Municipal Waste.

8, The Lessee shall have the right to, after taking prior permission of the Lessor, vest with the

Lenders the power to take over the control, possession and all rights and interest in relation

to the Demised Premises by appointing a person, the Nominated Company, to replace the

lessee and undertake the construction, operation and maintenance of the Plant upon the

occurrence of an Event of Default by the Lessee, as the case may be under any of the

f inancing Agreements for the Project. The Lessor shall then assign / novate this Agreement

in favor of the Nominated Company, which shall constitute an agreement between the

Nominated company and the Lessor on the terms and conditions of this Agreement as

existing at the time of such assignment / novation.

9. the Lessor hereby authorizes the Lessee to create any Encumbrance over the Project

facilities constructed on the Demised Premises (excepting the land) and this Agreement in

favour of the Lenders for enabling financing of the construction, operation and maintenance

of the Project. The Lessor agrees that it shall facilitate such Agreement as may be required

by the Lenders to enable financing of the Project and creation of the Encumbrance required

by the Lenders.

10. Without prejudice to the terms of this Agreement, the Lessor shall be governed by the terms

of any agreement that the Lenders may have entered into with the Lessor in respect of the

Encumbrance over the Project Facilities (other than the land constituting the Site which shall

not be mortgaged), any assets of the Project and this Agreement, created in favour of the

Lenders. Only the lease rights for the land can be transferred to the Lender

1,101.":1144217/e,› Lessee

Commissioner

MUNICIPAL CORPORATION

GUNTUR.

The Seel of

ohnSubRegIstrar

orrice

Phirangipuram

Generated On:20107/2018 04:58:11 PM

0

0

Page 7 of 9 \cc')

Lessee

11. The Lessor hereby covenants and assures the Lessee that:

a) All the land comprising the Site is permitted and duly authorized and earmarked for

purposes of establishment, construction, operation and maintenance of the Plant and

the Project Facilities;

b) The Site is free from any encroachment or encumbrances whatsoever and is not subject

to any acquisition or other legal proceedings by any Participating ULBs, body or

government nor is any claim of any third party subsisting in respect thereof or relating

thereto:

c) Lessor is the lawful owner of the lands constituting the Demised Premises and it shall, in

that capacity, defend or satisfy all actions or claims against the use of the Demised

Premises for the Project:

d) Subject to Clause 4, it shall not increase the lease payment due and payable by the

Lessee under the provisions of this Agreement:

e) It shall not interfere with or impede in any manner or otherwise limit, restrict or impose

any conditions or restrictions on the complete, free and full enjoyment and use of the

Demised Premises and all rights in relation thereto, including the creation of security

interest in favour of the Lenders in accordance with the provisions of the concession

Agreement:

f) Subject to terms of the Concession Agreement, it shall not interfere in or impede in any

manner or otherwise limit, restrict or impose conditions in relation: (i) to the

construction, operation and maintenance of the MSW Processing Plant; (ii) the

implementation of the Project by the Lessee and (iii) the possession, control and use, by

the Lessee of the Demised Premises and the plant;

g) It shall enter into appropriate further documentation or additional writing as the Lessee

or the Lenders may reasonably require to give effect to the provisions of this Agreement

and the Financing Agreement.

h) There are no litigations, claims, demands or any proceedings ( whether administrative,

legal or quasi-judicial) pending before any Participating ULBs in respect of the Demised

Premises or its use for the purposes of managing, processing and disposing MSW; and

) The Lessee shall have complete, lawful and uninterrupted, possession, control and use

of the Demised Premises.

12. The Lessee hereby covenants with the Lessor as follow:

a) That it shall implement the Project in accordance with the Concession Agreement

and

b) That it shall observe and perform all terms, covenants, conditions and stipulations of

this Agreement.

13. The Lessor has lawful title, possession and control of all the lands constituting the site and

has the requisite right and Participating ULBs to lease the same to Lessee for the Term for

the purposes of the project on the terms and conditions of this Agreement and further that

Lessee shall have full, free and uninterrupted peaceful Vacant Possession, enjoyment /

occupations and use of the Demised Premises throughout the Concession Period, without

any obstruction interference or disturbance or claim whatsoever from the Lessor or from

any person claiming through under or in trust for Lessor or from any third person

whomsoever. Lessor shall keep Lessee fully indemnified and harmless against any claims or

demands from any Person claiming right, title or interest to or in the Demised Premises or

Commissioner

MUNICIPAL CORPORATION

GUNTUR.

The Seal of

out Subilegistra

Office Phirangipuram

Generated On:20107/2018 04:58:11 PM

any part thereof or challenging the validity of the usage of the Demised Premises for the

Project or challenging the validity of this Agreement, as also against any actions,

proceedings, damages; losses and expenses caused to Lessee as a result or in consequences

of any such claims or demands as aforesaid.

14. (a). Subject to Sub-Clause (b) and (c) below, no assignment of this Agreement or any rights

or duties hereunder shall he made in whole or in part to, by any Party without prior written

consent of the other Party and in the event of any assignment the assignee shall assume the

duties and liabilities of the assignor.

(b). It is hereby specifically agreed that the Lessee shall, in the event of forming a limited

company either as subsidiary company or jointly along with any other company or

otherwise, be at liberty to assign and transfer the plant, the Demised premises and this

Agreement or the rights and benefits hereof or duties hereunder to such newly formed

limited company or any of its holding company for the time being and not in favour of such

subsidiary company of the Lessee. The Lessee, shall; however, in such event obtain formal

consent from the Lessor, which consent shall not he withheld by Lessor. Any assignment by

the Lessee shall be subject to the condition that the assignee shall assume the duties and

liabilities of the Lessee.

(c). the Lessor hereby agrees that the Lessee shall not require any prior approval of the

Lessor for creating any Encumbrance, right, title, or interest over the Demised Premises

(excepting land) and the Project Facilities under his ownership in accordance with the

Concession Agreement in favour of the Lenders.

(d). Lessor confirms that the Financing Documents may include suitable rights in favour of

the Lenders for taking over the Demised Premises (excepting land) and the plant for

management, in enforcement of their security upon the happening of an event of default

there under the Concession Agreement on the part of the Lessee.

15. The Lessor hereby assures and represents to the Lessee that the handingover of the .

Demised Premises under this Agreement shall be irrevocable for as long as the Concession

Agreement remains in force and the Lessor shall not Terminate or seek to Terminate this

Agreement except upon the expiry or early Termination of the Concession Agreement. The

Patties hereby agree that on expiry or Termination of the Concession Agreement, the

Demised Premises shall be handed back to the Lessor in accordance with the provisions of

the Concession Agreement and that this Agreement within 48 hours if termination or it shall

he deemed to have been handed over.

it). Any dis .putes and / or differences arising between the Parties, in relation to or under this

Agreement will be resolved through arbitration in accordance with Article 36 of the

Concession Agreement as per provisions of the Arbitration and Conciliation Act; 1996. The

governing law of the arbitration shall be Indian law. The Lessor hereby recognizes that this is

a commercial act being undertaken by the Lessor and that it herby unconditionally and

irrevocably waives any right of immunity, sovereign or otherwise from legal proceedings that

osixageitnay he initiated to enforce any provisions of this Agreement.

Commissioner

MUNICIPAL CORPORATIOr

• GUNTUR.

Lessee

Page 8 of 9

*

1he seat of

°Int Sutelegistra Office

Phirangipuram

Generated On:20/07/2018 04:58:11 PM a

oartage4

SIGNED : SEALED AND DELIVERED

IN 1WI. NAME AND ON BEHALF OF

1111 LESSOR THROUGH:

AUlliottisba sIGNATPAY

SIGNED; SEALED AND DELIVERED

IN THE NAME AND ON BEHALF OF

THE LESSEE TROUGH:

to

fi

AUTHORISED SIGNATORY

Commissioner

MUNICIPAL CORPORATION

GUNTUR.

The details of map enclosed to the agreement.

S.no -r Survey no Extent of land Location of the Land

1

2

933 Ac 6.54 Cents Kondaveedu (vill),Edlapadu (Mandal), Guntur

District, Andhra Pradesh

938 Ac 8.96 Cents Kondaveedu (vill),Edlapadu (Mandal), Guntur

District, Andhra Pradesh

3 Total Ac 15.50 Cents Lam_ I

SCHEDULE OF THE PROPERTY:

All the piece and parcel of land located in Sy. No. 933 & 938 in Kondaveedu (Vill),

x Ko-r-T-A pALs-m. Edlapadu (M), Phirangipuram Sub-District, Narasaraopet registration District of Guntur (Dt)

bounded by:

East

: Land in Sy. No. 939

West : Kondaveedu Reserve Forest

North : Road

South : Land in Sy. No 934 & 937

Within these boundaries an extent of Ac. 15.50 cents of Landis located.

IN 1111 WITNESS WHEREOF the Parties have affixed therein and sealed to this Lease Agreement the

19 1h day of July in the year 2018 hereinabove written:

IN PRESENCE OF:

(p• 120. Nv. a, (Csi ■ .g b\LAsti.)

illeitur Municipal Cut Pot ant i .

GUNTUR

Vrt4- b

essee ._c\,. 1/41.2 ,fc.v. ■A4,

Page 9 of 9

/A-cit-ox-o:N/ • S2 kS-

-70/ 2_

Generated On:20/07/2018 04:58:11 PM a

The Seal of

<Ant Su4ktegistrd

Office

Phiranglpuram

LAS

030

No. 95

PERECHERLA

GC1CTUR I A LIA

054

1 • 040

044

047

Cc..

POTTURU CLAJTIA TALUK

040

• 004

PofInn. 3 4,04

042

fie.i.nnuod

1062

nir i y-

..mm 0.0.0o• non ...44.5

Iti4.113 P. L P.. C I 4; 3410*AS

loeves twa occ.c.04.,

114exa- C-(5107 "

, ;45A (3144

SURVEYOR pot ApAD,/

7:)IST7.K

net oI rt f.„0.pir)sN.

01LPCOLOC

No. 131

KONDAV1DU 6th BIT

NARASARAOPET TALUK

clkerua ocaTfacr e t.: ,, c1.44e) Inn 41 MA

*wk. • OKA.. -1 D4.14 706

1.41.*C•0 0 s 10 IS C Ae•no

11011041011%1010000.01041001100401a1000

004 Of40.10 not Of 40. owl n.a.n01044sc• 4.4~4005 as oor .00e on trop the, Cosloate. Print4.4, Fonlo......74..11140 14 kW *OW,

H ILL

PALL. Paton, .an.

Hasooet

"f41.0 ar 14"40447

0444404 nna.t•

6. 1,4f

9 Cromer.

10I{

t. L410. 001.

A Loan& MHO

root *Ma

Can Dian

[WAN •40.1

na.44440 soaa lawoOvie

0404.040 •440 .re one awn.

1104....ny

Taneorao•

IFsna,. C0100 and at0.44o.

anoottosololt•

.:: Cobra,. ewe. OrlOaL

4..7: Yer ra

onnnoo..

T401.0oraft 00

Pernta4441 CO.

70.0.4.4., 50

Sflo4f0

00444 400

22 14040 041

140..414)••,

N.111r•n ,

S-4,40

44111.40

Saved

04fltle•04...0

Ster 4 1a .144 eoweno

{. taw of

P ,IoM

1.11040tan'i 0.7 90,00: 500:104

MY. .n foot s0.51.• se•

140.00,4

wawa. .0,01'

4.54.410.5.44000.4

it•ULA

0 MLOOM 01044 0140014

TO•000At caw,.

,v4. • ■•■ •

71' 01430

000.J,

4 licoott,suo ar 0:04,

User Login: 21000566500000999

Monthly Contribution > Online Challan Status

ChallanDoubleVerlfIcation

Friday, December 14, 2018 1:19:27 ig

PM

Transaction Details ' Required Fields

Transaction status:

Employer's Code No:

Employer's Nifile:

Challan Period:

Challan Number:

Challan Created Data

Challan Submitted Date

Amount Paid:

Transaction Number:

Transaction Completed Successfully

21000566500000999

CEEKAY ASSOCIATES PVT LTD

Nov-2018 . _

02118135870101

12-12.2018 12:05:57

13-12-2018 16:18:04

168334.00

CPL6029282

' Required Fields

Employer's Code No.:

ChallanDoubleVerification htt ://w w w.es ic .in/ES LC laskicutclakcxt.W.,Q.,(MM\.\\\. cAl\\

\Flo-71e ES1C

EllIPIOYeelZI ' State 11 isurance Corporation

Insurance

DISCLAIMER: Content owned, maintained and updated by Employee's State Insurance Corporation. Copyright 2009, ESIC, trdia. All Rights Reserved. Best

viewed In 1024 x 768 pixels, Designed and Developed by Wipro LTD.IP Address : 48.ASP Session ID ulow4r45troscqebedgm2q55

I of 1 14/12/2018 1:19 1