Transcript of Survey Pendahuluan 5 April 2016
PT. WECON
Nama : Budhi Wiyono, ST
Tanggal Kebutuhan : 5-Apr-16
Project : Review Detail Desain Embung Sukodono Di Kabupaten Gresik Tahap II
Survey Lapangan Pendahuluan
Catatan : - Budhi Wiyono - Direksi Pekerjaan ( 3 orang )
- Darmadji
- Sopir
No
No. Keterangan Volume Satuan Harga Satuan Jumlah
1 Sewa Kendaraan + Sopir 1 hari 600,000.00Rp 600,000.00Rp
3 SPJ Direksi (3 orang) 1 hari 300,000.00Rp 900,000.00Rp
2 BBM Mobil 1 LS 500,000.00Rp 500,000.00Rp
4 Kosumsi 1 LS 1,000,000.00Rp 1,000,000.00Rp
TOTAL BIAYA 3,000,000.00Rp