PT.BARUGA ASRINUSA DEVELOPMENT JL. RAYA BAR UGA NO. MAKASSAR SCHEDULE PENYELESAIAN T/L 150 Kv PLTU MOLOTABU - GI BOTUPINGGE (REVISI) Mel '13 Juni '13 Juli '13 Agutus'13 September'13 NO. Uraian Kegiatan Keterangan I II I 1111 IV I 1 II I 1111 IV I I II I 1111 IV I I II I III IV I II III IV 1. Pembebasan Lahan TIP 38-64 17 2. Penyelidikan Tanah Sudah selesai 100% 3. Pondasi 4. Pengadaan Material a. Tower ( 44 set ) i. Tahap 1(8 set tower) 8 Set On Site 15 Januari 2013 (27 set tower) ii Tahap 11 (9 set tower + Leg) b. Konduktor ( ACSR-AS 240 ) c. GSW d. OPGW e. Fitting, insulator & Acc 5. Erection Tower i. Tahap 1(6 set tower ) 4 set sdh di erection (sisa 2 set ) (24 set tower) II. Tahap 11 (14 set tower) 6. ROW - Identifikasi & Sosialisasi - Penebangan 7. Stringing a. Section - 1 b. Section - 2 8. Pengujian a. Individual Check b. Final Check & Test c. S L 0 Makassar. 14 Mei 2013 -- MUM ASRI PROJECT MANAGER

description

.

Transcript of Re-Schedule TL Molotabu - Botupingge 2

Page 1: Re-Schedule TL Molotabu - Botupingge 2

PT.BARUGA ASRINUSA DEVELOPMENT

JL. RAYA BAR UGA NO. MAKASSAR

SCHEDULE PENYELESAIAN T/L 150 Kv PLTU MOLOTABU - GI BOTUPINGGE (REVISI)

Mel '13 Juni '13 Juli '13 Agutus'13 September'13 NO. Uraian Kegiatan Keterangan

I II I 1111 IV I 1 II I 1111 IV I I II I 1111 IV I I II I III IV I II III IV

1. Pembebasan Lahan TIP 38-64 17 2. Penyelidikan Tanah Sudah selesai 100%

3. Pondasi

4. Pengadaan Material

a. Tower ( 44 set )

i. Tahap 1(8 set tower) 8 Set On Site 15 Januari 2013

(27 set tower)

ii Tahap 11 (9 set tower + Leg)

b. Konduktor ( ACSR-AS 240 )

c. GSW

d. OPGW

e. Fitting, insulator & Acc

5. Erection Tower

i. Tahap 1(6 set tower ) 4 set sdh di erection (sisa 2 set )

(24 set tower)

II. Tahap 11 (14 set tower)

6. ROW

- Identifikasi & Sosialisasi

- Penebangan

7. Stringing

a. Section - 1

b. Section - 2

8. Pengujian

a. Individual Check

b. Final Check & Test

c. S L 0

Makassar. 14 Mei 2013

-- MUM ASRI

PROJECT MANAGER