Re-Schedule TL Molotabu - Botupingge 2
-
Upload
yoseppirnawan -
Category
Documents
-
view
8 -
download
1
description
Transcript of Re-Schedule TL Molotabu - Botupingge 2
PT.BARUGA ASRINUSA DEVELOPMENT
JL. RAYA BAR UGA NO. MAKASSAR
SCHEDULE PENYELESAIAN T/L 150 Kv PLTU MOLOTABU - GI BOTUPINGGE (REVISI)
Mel '13 Juni '13 Juli '13 Agutus'13 September'13 NO. Uraian Kegiatan Keterangan
I II I 1111 IV I 1 II I 1111 IV I I II I 1111 IV I I II I III IV I II III IV
1. Pembebasan Lahan TIP 38-64 17 2. Penyelidikan Tanah Sudah selesai 100%
3. Pondasi
4. Pengadaan Material
a. Tower ( 44 set )
i. Tahap 1(8 set tower) 8 Set On Site 15 Januari 2013
(27 set tower)
ii Tahap 11 (9 set tower + Leg)
b. Konduktor ( ACSR-AS 240 )
c. GSW
d. OPGW
e. Fitting, insulator & Acc
5. Erection Tower
i. Tahap 1(6 set tower ) 4 set sdh di erection (sisa 2 set )
(24 set tower)
II. Tahap 11 (14 set tower)
6. ROW
- Identifikasi & Sosialisasi
- Penebangan
7. Stringing
a. Section - 1
b. Section - 2
8. Pengujian
a. Individual Check
b. Final Check & Test
c. S L 0
Makassar. 14 Mei 2013
-- MUM ASRI
PROJECT MANAGER