ENGINEER'S ESTIMATE (EE) REKAPITULASI RENCANA ANGGARAN BIAYA RUAS JALAN : 0 JENIS PEKERJAAN : 0 PANJANG : 0 LOKASI PROYEK : 0 NO URAIAN PEKERJAAN JUMLAH H 1 2 I PEKERJAAN PERSIAPAN 4, II Pekerjaan Pasangan Batu III Pekerjaan Pasangan Gorong-gorong IV PEKERJAAN PERKERASAN 35, J U M L A H 40, P P N 10% 4, JUMLAH TOTAL 44, DIBULATKAN 44, TERBILANG : Seratus Dua Puluh Lima Juta Rupiah Bandar Lamung, 18 KONSULTAN PEREN PT. NANDHA CITRA 0 0

Transcript of RAB Jalan Analisa K

Page 1: RAB Jalan Analisa K

ENGINEER'S ESTIMATE (EE)REKAPITULASI RENCANA ANGGARAN BIAYA

RUAS JALAN : 0

JENIS PEKERJAAN : 0

PANJANG : 0LOKASI PROYEK : 0

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)

1 2 3

I PEKERJAAN PERSIAPAN 4,800,000.00

II Pekerjaan Pasangan Batu -

III Pekerjaan Pasangan Gorong-gorong -

IV PEKERJAAN PERKERASAN 35,574,765.30

J U M L A H 40,374,765.30

P P N 10% 4,037,476.53

JUMLAH TOTAL 44,412,241.83

DIBULATKAN 44,000,000.00

TERBILANG : Seratus Dua Puluh Lima Juta Rupiah

Bandar Lamung, 18 MeI 2011

KONSULTAN PERENCANAPT. NANDHA CITRA KREASI

00

Page 2: RAB Jalan Analisa K

ENGINEER'S ESTIMATE (EE)RENCANA ANGGARAN BIAYA

PENINGKATAN JALAN LINGKUNGAN PERUMAHAN

RUAS JALAN : 0JENIS PEKERJAAN : 0PANJANG : 0LOKASI PROYEK : 0

NO URAIAN PEKERJAAN KODE SATUAN VOLUMEHARGA SATUAN JUMLAH HARGA

KET.(Rp) (Rp)

1 2 3 4 5 6 7 8I. PEKERJAAN PERSIAPAN

1 Administrasi, Pelaporan dan Dokumentasi Ls Ls 1.00 1,500,000.00 1,500,000.00 2 Pembuatan Papan Nama Proyek Ls Buah 1.00 500,000.00 500,000.00 3 Mobilisasi dan Demobilisasi Ls Ls 1.00 1,500,000.00 1,500,000.00 4 Pengukuran Ulang dan Pematokan Ls Ls 1.00 300,000.00 300,000.00 5 Sewa Direksi Keet Ls Unit 1.00 1,000,000.00 1,000,000.00

4,800,000.00 II. PEKERJAAN PASANGAN BATU

1 Pasangan Batu K - 705 M3 595,048.00 - 2 Urugan Pasir Bawah Lantai dan Pondasi A 18 M3 132,700.00 -

- III. PEKERJAAN PASANGAN PIPA GORONG-GORONG 60 CM

1 Galian Tanah K - 224 M3 38,000.00 - 2 Pasangan Pipa Beton Pracetak K - 122 M' 689,497.00 -

- IV. PEKERJAAN PERKERASAN

1 Perbaikan Pasangan Onderlaag K - 516 M3 109.40 325,180.67 35,574,765.30 2 Pasangan Lapis Penetrasi (Lapen) K - 618 M2 79,012.68 - 3 Pasang Lapis Tipis Aspal Pasir (Latasir) K - 638 M2 63,956.00 -

35,574,765.30

J U M L A H 40,374,765.30

P P N 10% 4,037,476.53

JUMLAH TOTAL 44,412,241.83

DIBULATKAN 44,000,000.00

TERBILANG : Seratus Dua Puluh Lima Juta Rupiah

Page 3: RAB Jalan Analisa K

ENGINEER'S ESTIMATE (EE)RENCANA ANGGARAN BIAYA

PENINGKATAN JALAN LINGKUNGAN PERUMAHAN

RUAS JALAN : 0JENIS PEKERJAAN : 0PANJANG : 0LOKASI PROYEK : 0

NO URAIAN PEKERJAAN KODE SATUAN VOLUMEHARGA SATUAN JUMLAH HARGA

KET.(Rp) (Rp)

1 2 3 4 5 6 7 8I. PEKERJAAN PERSIAPAN

1 Administrasi, Pelaporan dan Dokumentasi Ls Ls 1.00 1,500,000.00 1,500,000.00 2 Pembuatan Papan Nama Proyek Ls Buah 1.00 500,000.00 500,000.00 3 Mobilisasi dan Demobilisasi Ls Ls 1.00 1,500,000.00 1,500,000.00 4 Pengukuran Ulang dan Pematokan Ls Ls 1.00 300,000.00 300,000.00 5 Sewa Direksi Keet Ls Unit 1.00 1,000,000.00 1,000,000.00

4,800,000.00 II. PEKERJAAN PERKERASAN

1 Perbaikan Pasangan Onderlaag K - 516 M3 109.40 325,180.67 35,574,765.30 2 Pasangan Lapis Penetrasi (Lapen) K - 618 M2 79,012.68 -

35,574,765.30

J U M L A H 40,374,765.30

P P N 10% 4,037,476.53

JUMLAH TOTAL 44,412,241.83

DIBULATKAN 44,000,000.00

TERBILANG : Seratus Dua Puluh Lima Juta Rupiah

Page 4: RAB Jalan Analisa K

10,380.00

870.3

Page 5: RAB Jalan Analisa K

DAFTAR UPAH KERJA ORANG PERHARI0

NO TENAGA KERJA SATUAN KODEHARGA SATUAN

(Rp/Hari)

1 Mandor Lapangan Hari L. 061 70,000.00 2 Mekanik Hari L. 071 50,000.00 3 Kepala Tukang Hari L. 073 60,000.00 4 Tukang Hari L. 079 60,000.00 5 Operator Terlatih Hari L. 081 50,000.00 6 Operator Kurang Terlatih Hari L. 082 45,000.00 7 Pembantu Operator Hari L. 083 40,000.00 8 Supir terampil Hari L. 091 40,000.00 9 Pembantu Supir Hari L. 099 40,000.00

10 Buruh Lapangan Terlatih Hari L. 106 40,000.00 11 Buruh Lapangan Semi Terlatih Hari L. 103 40,000.00 12 Buruh Lapangan Tak Terlatih Hari L. 101 40,000.00

Page 6: RAB Jalan Analisa K

DAFTAR HARGA MATERIAL0

NO MATERIAL/BAHAN SATUAN KODEHARGA SATUAN

(Rp)

1 Batu gunung atau quarry M3 M 010 195,000.00 2 Kerikil galian M3 M 011 151,700.00 3 Kerikil sungai M3 M 012 151,700.00 4 Batu kali besar M3 M 013 182,500.00 5 Batu kali disaring M3 M 014 157,800.00 6 Batu pecah 10 - 15 cm M3 M 020 250,000.00 7 Batu pecah 7 - 10 cm M3 M 021 232,000.00 8 Batu pecah 5 - 7 cm M3 M 022 265,000.00 9 Batu pecah 3 - 5 cm M3 M 023 223,000.00

10 Batu pecah 2 - 3 cm M3 M 024 239,800.00 11 Batu pecah 1 - 2 cm M3 M 025 251,000.00 12 Batu pecah 0.5 - 1 cm M3 M 026 251,000.00 13 Pasir urug M3 M 040 100,000.00 14 Pasir beton M3 M 041 158,200.00 15 Sirtu M3 M 042 101,300.00 16 Timbunan pilihan M3 M 050 80,000.00 17 Aspal Kg M 061 11,000.00 18 Minyak fluk Liter M 063 6,010.00 19 Minyak bakar Liter M 065 5,950.00 20 Kayu bakar M3 M 070 150,000.00 21 Semen Zak/50 kg M 080 59,500.00 22 Kapur M3 M 081 1,000,000.00 23 Baja untuk anyaman bronjong Kg M 162 17,200.00 24 Baja Struktur (Profil) Kg M 163 20,200.00 25 Baja tulangan beton U-24 Kg M 167 10,300.00

26 Alat bantu (set @ 3 alat) Set M 170 55,000.00

27 Kayu / papan perancah M3 M 180 2,100,000.00

28 Minyak diesel atau solar industri Liter M 183 6,640.00

29 Bensin atau premium Liter M 184 5,500.00

30 Minyak pelumas Liter M 185 32,000.00

31 Batu belah putih M3 B 001 190,000.00

32 Batu belah hitam M3 B 001a 195,000.00

33 Paving Block 8 cm Buah B 004 2,600.00

34 Paving Block 6 cm Buah B 004a 2,000.00

35 Cat marka jalan Kg B 008 60,000.00

Page 7: RAB Jalan Analisa K

DAFTAR SEWA ALAT PERJAM0

NO NAMA PERALATAN HP KODEHARGA SATUAN

(Rp/Jam)

1 Bulldozer 140 E 001 504,761.25 2 Motor grader 125 E 010 366,589.65 3 HydraulicExcavator 140 E 020 392,119.00 4 Crusher 20 t/h 220 E 031 1,162,762.65 5 Loader tracked 90 E 051 362,926.20 6 Loader wheeled 105 E 052 373,792.65 7 Tractor wheeled 60 E 053 72,963.00 8 Roller 3 wheeled 8 - 10 ton 55 E 080 154,890.75 9 Tandem roller 6 - 10 ton 60 E 081 165,526.20

10 Pneumatic Roller 8 - 15 T 60 E 084 227,174.85 11 Vibrator roller 10 ton 75 E 087 340,245.15 12 Stamper 5 E 088 38,659.95 13 Concrete Vibrator 10 E 089 54,691.35 14 Asphalt Sprayer 800 L 6 E 153 94,609.20 15 Asphalt Sprayer 400 L 6 E 154 59,158.00 16 Mesin pencampur Aspal 150 E 155 5,872,757.10 17 Asphalt Finisher 47 E 157 298,874.10 18 Water Tank Truck 100 E 182 238,523.25 19 Dump truck 3,5 ton 120 E 211 129,868.00 20 Dump truck 5 ton 140 E 212 189,554.40 21 Dump truck 10 ton 200 E 213 253,456.35 22 Flat Bed Truck 4 ton 100 E 221 197,878.80 23 Pickup Truck 61 E 222 77,568.00 24 Concrete Mixer 0.3 - 0.5 m3 15 E 251 62,431.95 25 Air Compressor 80 E 301 170,145.15 26 Generator 175 E 311 344,575.35 27 Water Pump 70 -100 mm 6 E 341 38,419.50 28 Tractor Equipment 115 E 401 72,963.00 29 Jack Hammer 3 E 346 40,020.75

Page 8: RAB Jalan Analisa K

ANALISA BIAYA KONSTRUKSI LAPIS PONDASI BAWAH (LPB) - TELFORD KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 516

PROPINSI : 0KODE Kota / Kab KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Material disiapkan di lokasi pekerjaan 1 Menggunakan tenaga manusia 400 m2/hari

2 Menghampar pasir setebal 5 cm 2 Material2 dikirim ke lokasi pekerjaan oleh leveransir

3 Batu pecah berukuran besar (10/15) disusun berdiri 3 Batu sudah dipecah

4 Batu pecah yang lebih kecil mengisi rongga diatasnya 4 Tanah dasar sudah disiapkan

sehingga rata kemudian dipadatkan / digilas 5 Dipadatkan sampai tebal 20 cm

dengan mesin gilas

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Mandor Lapangan 3 1 L 061 3.00 70,000.00 210,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 Buruh Lapangan Terlatih 99 1 L 101 99.00 40,000.00 3,960,000.00

4

5

6

7

8

9

10

4,220,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Batu pecah 10 - 15 cm M3 M 020 50.00 250,000.00 ###

2 Batu pecah 5 - 7 cm M3 M 022 20.00 265,000.00 5,300,000.00

3 Pasir urug M3 M 040 30.00 100,000.00 3,000,000.00

4 Alat bantu (set @ 3 alat) Set M 170 4.00 55,000.00 220,000.00

5

6

7

8

9

10

###

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Roller 3 wheeled 8 - 10 ton 1 1 E 080 5.00 154,890.75 774,453.75

2

3

4

5

6

7

8

9

10

774,453.75

T O T A L (Rp) ###

VOL : 80.00 SATUAN : M3 HARGA SATUAN 325,180.67 PER M3

Page 9: RAB Jalan Analisa K

ANALISA BIAYA ANALISA HARGA SATUAN KODE

PENGHAMPARAN LAPIS TIPIS ASPAL PASIR 2 CM

PEKERJAAN(LATASIR) K - 638

(MENGGUNAKAN BURUH)

PROPINSI : 0KODE Kota / Kab KODE DISIAPKAN OLEH : Tanggal

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI 1. Membersihkan permukaan aspal lama 1. Menggunakan Tenaga Manusia (1600 m2/hari)

dengan menggunakan tenaga manusia 2. Pasir aspal dikirim ke lokasi oleh pemasok dari AMP 2. Dilapis dengan lapis tack/pengikat 3. BJ padat 1.9 ton/m3 3. Hamparkan pasir aspal dengan tenaga 4. Tebal padat rata-rata 2 cm

manusia 5. Lapis tack/pengikat aspal cutback dihampar @ 0,5 lt/m2 4. Digilas sampai padat 6. Sesuai Spesifikasi B.M. No. 02/PT/B/1983

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Buruh Lapangan Tak Terlatih 12 1 L 101 12.00 40,000.00 480,000.00

2 Mandor Lapangan 1 1 L 061 1.00 70,000.00 70,000.00

3 Operator Terlatih 3 1 L 081 3.00 50,000.00 150,000.00

4 Supir terampil 1 1 L 091 1.00 40,000.00 40,000.00

5 Pembantu Operator 3 1 L 083 3.00 40,000.00 120,000.00

6 Pembantu Supir 1 1 L 099 1.00 40,000.00 40,000.00

7 Buruh Lapangan Terlatih 2 1 L 106 2.00 40,000.00 80,000.00

8

9

10

980,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Campuran panas LATASIR TON K 020 60.00 1,498,418.00 89,905,080.00

2 Aspal KG M 061 640.00 11,000.00 7,040,000.00

3 Minyak bakar LTR M 065 160.00 5,950.00 952,000.00

4 Alat bantu (set @ 3 alat) SET M 170 0.48 55,000.00 26,400.00

5

6

7

8

9

10

97,923,480.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Tandem roller 6 - 10 ton 1 1 E 081 5.00 165,526.20 827,631.00

2 Pneumatic Roller 8 - 15 T 1 1 E 084 5.00 227,174.85 1,135,874.25

3 Asphalt Sprayer 800 L 1 1 E 153 5.00 94,609.20 473,046.00

4 Flat Bed Truck 4 ton 1 1 E 221 5.00 197,878.80 989,394.00

5

6

7

8

9

10

3,425,945.25 T O T A L (Rp) ###

VOLUME : 1,600.00 SATUAN : M2 HARGA SATUAN : 63,956.00 PER M2

Page 10: RAB Jalan Analisa K

ANALISA BIAYA LAPIS PENETRASI MACADAM 5 CM (LAPEN) KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 618

PROPINSI : 0KODE Kota / Kab KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Semprotkan aspal tack coat 0,8 ltr/m2 1 Menggunakan tenaga buruh

2 Hamparkan aggregat pokok 3/5 25 m2/m3 dan 2 Harga material berdasarkan harga di lokasi proyek

padatkan 3 Volume tack coat/prime coat 0,8 ltr/m2

3 Hamparkan split 2/3 45m2/m3 dan padatkan 4 Tebal lapisan penetrasi ± 5 cm

4 Semprotkan aspal (2,5 kg/m2) 5 Aggregat dikirim sampai tempat pekerjaan oleh leveransir

5 Hamparkan aggregat pengunci (split) 1/2 90 m2/m3

dan padatkan

6 Semprotkan aspal 1,5 kg/m

7 taburkan pasir rata2 400m2/m3

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Mandor Lapangan 2 3 L 061 6.00 70,000.00 420,000.00

2 Operator Terlatih 2 3 L 081 6.00 50,000.00 300,000.00

3 Supir terampil 1 3 L 091 3.00 40,000.00 120,000.00

4 Buruh Lapangan Tak Terlatih 66 3 L 101 198.00 40,000.00 7,920,000.00

5 Buruh Lapangan Terlatih 2 3 L 106 6.00 40,000.00 240,000.00

6

7

8

9

10

9,000,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Batu pecah 3 - 5 cm M3 M 023 56.00 223,000.00 12,488,000.00

2 Batu pecah 2 - 3 cm M3 M 024 31.00 239,800.00 7,433,800.00

3 Batu pecah 1 - 2 cm M3 M 025 15.50 251,000.00 3,890,500.00

4 Pasir beton M3 M 041 3.50 158,200.00 553,700.00

5 Aspal Kg M 061 6,270.00 11,000.00 68,970,000.00

6 Minyak bakar Liter M 065 450.00 5,950.00 2,677,500.00

7 Alat bantu (set @ 3 alat) Set M 170 8.10 55,000.00 445,500.00

8

9

10

96,459,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Roller 3 wheeled 8 - 10 ton 1 3 E 080 15.00 154,890.75 2,323,361.25

2 Asphalt Sprayer 400 L 1 3 E 154 15.00 59,158.00 887,370.00

3 Dump truck 3,5 ton 1 3 E 211 15.00 129,868.00 1,948,020.00

4

5

6

7

8

9

10

5,158,751.25

T O T A L (Rp) ###

VOL : 1,400.00 SATUAN : M2 HARGA SATUAN 79,012.68 PER M2

Page 11: RAB Jalan Analisa K
Page 12: RAB Jalan Analisa K

ANALISA BIAYA GALIAN TANAH KONSTRUKSI KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 224

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Penggalian tanah dgn tenaga manusia (50 m3/hari) 1 Menggunakan tenaga manusia

2 Tanah galian disingkirkan sejauh minimal 30 m 2 Kapasitas kerja kelompok 50 m3/hari

dari lubang galian 3 Kedalaman rata-rata galian s/d 3 m

4 Untuk jenis tanah berbatu, harga satuan pekerjaan K 224 dikalikan dgn faktor 1,5

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 Buruh Terlatih 2 1 L 106 2.00 40,000.00 80,000.00

3 Buruh Tak Terlatih 30 1 L 101 30.00 40,000.00 ###

4

5

6

7

8

9

10

1,350,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 10.00 55,000.00 550,000.00

2

3

4

5

6

7

8

9

10

550,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

T O T A L (Rp) 1,900,000.00

VOL : 50.00 SATUAN : M3 HARGA SATUAN 38,000.00 PER M3

Page 13: RAB Jalan Analisa K
Page 14: RAB Jalan Analisa K

ANALISA BIAYA TIMBUNAN TANAH DIPADATKAN KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 220

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Meratakan dgn tenaga manusia 1 Menggunakan tenaga manusia (60 m3/hari)

2 Pemadatan lapisan-lapisan 2 Dipakai material dari daerah penggalian

3 Perataan dgn tenaga manusia, tebal per lapis 10 cm

4 Pemadatan dgn mesin gilas tandem

5 Hasil pemadatan 60 m3

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 3 1 L 061 3.00 70,000.00 210,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 Buruh Tak Terlatih 90 1 L 101 90.00 40,000.00 ###

4

5

6

7

8

9

10

3,860,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 6.00 55,000.00 330,000.00

2 Timbunan pilihan M3 M 050 60.00 80,000.00 ###

3

4

5

6

7

8

9

10

5,130,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Tandem roller 6 - 10 ton 1 1 E 081 5.00 165,526.20 827,631.00

2

3

4

5

6

7

8

9

10

827,631.00

T O T A L (Rp) 9,817,631.00

VOL : 60.00 SATUAN : M3 HARGA SATUAN 163,627.18 PER M3

Page 15: RAB Jalan Analisa K
Page 16: RAB Jalan Analisa K

ANALISA BIAYA PENGUPASAN TANAH DAN KODE

PEKERJAANPEMBERSIHAN SEMAK PADA DAMIJA

(MENGGUNAKAN BURUH) K - 210

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Mengupas dan membuang semak dengan 1 Menggunakan tenaga manusia (9m X 100m / hari)

tenaga manusia pada DAMIJA 2 Hasil kerja 25 m2/orang/hari

3 Penggunaan alat bantu 1 bulan-orang

4 Bakar sampah ditempat pekerjaan

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Mandor Lapangan 1 1 L 061 1.00 70,000.00 70,000.00

2 Buruh Lapangan Tak Terlatih 36 1 L 101 36.00 40,000.00 ###

3

4

5

6

7

8

9

10

1,510,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (set @ 3 alat) Set M 170 1.50 55,000.00 82,500.00

2

3

4

5

6

7

8

9

10

82,500.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

T O T A L (Rp) 1,592,500.00

VOL : 900.00 SATUAN : M2 HARGA SATUAN 1,769.44 PER M2

Page 17: RAB Jalan Analisa K
Page 18: RAB Jalan Analisa K

ANALISA HARGA BETON STRUKTUR KELAS K-225 KODE

SATUAN(MENGGUNAKAN ALAT PENGADUK BETON 125 LITER)

K - 722

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Pemasok mengirim material 1 Bahan-bahan dasar dikirim ke lokasi pekerjaan oleh pemasok

2 Acuan dan tulangan besi betondipasang 2 Dipakai agregat pecah dan tersaring yang termurah

3 Beton diaduk dilokasi pekerjaan 3 Dicor 6.17 m3/hari dengan 54 adukan/6 jam/hari

4 Beton dicor dan digetar sampai padat 4 Adukan 1 Pc: 2 Ps : 3 Kr (yaitu 1 : 5) ; semen 350 Kg/m3 ; air 160 Kg/m3; 2487 Kg/m3

5 Anggap tiap adukan membutuhkan 1 Zak (27,8 liter lepas) semen portland; 55,6 liter pasir;

83,3 liter kerikil dan 18,3 liter air

6 Tidak termasuk acuan dan tulangan besi beton yang sudah dipasang

7 Beton bertulang dipakai untuk pilar, gorong-gorong, dinding penahan dll

8 Sesuai dengan Peraturan Beton Bertulang Indonesia (PBI 1971 N.1.2)

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 6 L 061 6.00 70,000.00 420,000.00

2 Buruh Tak Terampil 12 6 L 101 72.00 40,000.00 2,880,000.00

3 Buruh Terampil 2 6 L 106 12.00 40,000.00 480,000.00

4

5

6

7

8

9

10

3,780,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Pasir beton M3 M 041 18.00 158,200.00 2,847,600.00

2 Semen Sak/50 kg M 080 259.20 59,500.00 15,422,400.00

3 Alat bantu (Set @ 3 alat) Set M 170 2.88 55,000.00 158,400.00

4 Kerikil Pecah Tersaring M3 K 017 27.00 157,800.00 4,260,600.00

5

6

7

8

9

10

22,689,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Concrete Vibrator 1 6 E 089 36.00 54,691.35 1,968,888.60

2 Concrete Mixer 0,125 m3 1 6 E 251 36.00 62,431.95 2,247,550.20

3 Water Pump dia 5" 1 6 E 341 12.00 38,419.50 461,034.00

4

5

6

7

8

9

10

4,677,472.80

T O T A L (Rp) ###

Page 19: RAB Jalan Analisa K

VOL : 37.00 SATUAN : M3 HARGA SATUAN 841,797.00 PER M3

Page 20: RAB Jalan Analisa K

ANALISA BIAYA PASANG PAVING BLOCK KODE

PEKERJAAN (MENGGUNAKAN BURUH) G 60

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Tanah dasar sudah diratakan 1 Pasir dan paving block disiapkan di lokasi pekerjaan oleh leveransir

2 Hampar pasir urug tebal 10 cm 2 Tidak termasuk peratan dan pemadatan tanah dasar

3 Susun Paving Block 3 Hasil produksi 10 m2

4 Taburkan pasir untuk mengikat Paving Block

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Tukang 1 1 L 073 1.00 70,000.00 70,000.00

2 Buruh Lapangan Terlatih 4 1 L 106 4.00 40,000.00 160,000.00

3

4

5

6

7

8

9

10

230,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Paving Block 6 cm M2 B 004 400.00 2,000.00 800,000.00

2 Pasir urug M3 M 040 1.00 100,000.00 100,000.00

3 Alat bantu (set @ 3 alat) Set M 170 0.20 55,000.00 11,000.00

4

5

6

7

8

9

10

911,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

T O T A L (Rp) 1,141,000.00

Page 21: RAB Jalan Analisa K

VOL : 10.00 SATUAN : M2 HARGA SATUAN 114,100.00 PER M2

ANALISA BIAYA PASANG CANSTEEN KODE

PEKERJAAN (MENGGUNAKAN BURUH) G 61

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Material disiapkan di lokasi pekerjaan oleh leveransir

2 Hasil produksi 100 m'

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 Buruh Terlatih 10 1 L 106 10.00 40,000.00 400,000.00

3 Buruh Tak Terlatih 20 1 L 101 20.00 40,000.00 800,000.00

4

5

6

7

8

9

10

1,270,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Paving Block 8 cm M2 B 014 800.00 2,600.00 2,080,000.00

2 Semen Sak/50 kg M 080 11.75 59,500.00 699,125.00

3 Pasir pasang M3 M 041a 0.95 158,200.00 150,290.00

4 Alat bantu (Set @ 3 alat) Set M 170 1.44 55,000.00 79,200.00

5

6

7

8

9

10

3,008,615.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

Page 22: RAB Jalan Analisa K

T O T A L (Rp) 4,278,615.00

VOL : 100.00 SATUAN : M' HARGA SATUAN 42,786.00 PER M'

Page 23: RAB Jalan Analisa K

ANALISA BIAYA KONSTRUKSI LAPIS PONDASI BAWAH (LPB) KLAS B KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 513

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Membentuk/meratakan kembli permukaan 1 Menggunakan buruh (60 m3/hari)

2 jalan lama 2 Dimulai dgn pekerjaan memperbaiki penurunan

3 Aggregat ditempatkan disepanjang jalan 3 Bahan dicampur dan diratakan ± 12 cm

4 Menghampar aggregat 4 Tebal lapisan10 cm

5 Jalan disiram dgn truk air 5 Harga material berdasarkan harga di lokasi proyek

6 Pemadatan dgn mesin gilas

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 2 1 L 061 2.00 70,000.00 140,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 S o p i r 1 1 L 091 1.00 40,000.00 40,000.00

4 Buruh Tak Terlatih 66 1 L 101 66.00 40,000.00 ###

5

6

7

8

9

10

2,870,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Batu pecah 3 - 5 cm M3 M 023 10.00 223,000.00 ###

2 Batu pecah 2 - 3 cm M3 M 024 11.00 239,800.00 ###

3 Batu pecah 1 - 2 cm M3 M 025 7.50 251,000.00 ###

4 Batu pecah 0.5 - 1 cm M3 M 026 11.00 251,000.00 ###

5 Pasir urug M3 M 040 32.50 100,000.00 ###

6 Alat bantu (Set @ 3 alat) Set M 170 1.20 55,000.00 66,000.00

7

8

9

10

12,827,300.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Roller 3 wheeled 8 - 10 t 1 1 E 080 5.00 154,890.75 774,453.75

2 Water Tank Truck 1 1 E 182 4.00 238,523.25 954,093.00

3 Pneumatic roller 8 - 15 t 1 1 E 084 5.00 227,174.85 ###

4

5

6

7

8

9

10

2,864,421.00

T O T A L (Rp) 18,561,721.00

Page 24: RAB Jalan Analisa K

VOL : 60.00 SATUAN : M3 HARGA SATUAN 309,362.02 PER M3

Page 25: RAB Jalan Analisa K

ANALISA BIAYA KONSTRUKSI LAPIS PONDASI BAWAH (LPB) KLAS C KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 515

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Aggregat ditempatkan disepanjang jalan 1 Menggunakan tenaga manusia

2 Menghampar aggregat dgn tenaga manusia 2 Kerikil ditimbun sepanjang jalan oleh leveransir

3 Pemadatan 2 lapis memakai truk air dan 3 Kerikil dgn ukuran lebih (over size) yang tersingkir saat penghamparan dgn orang dihitung 6%

mesin gilas roda baja 4 Dihampar dalam 2 lapis dan dipadatkan, tebal padat 10 cm

4 Perapihan dgn tangan 5 Penggunaan alat bantu ± 1 bulan-orang

6 Hasil kerja menghampar dan memadatkan 600 m2/hari

7 Kerikil kali tanpa disaring dikirim oleh leveransir sampai di tempat pekerjaan

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 3 1 L 061 3.00 50,000.00 150,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 S o p i r 1 1 L 091 1.00 40,000.00 40,000.00

4 Buruh Tak Terlatih 60 1 L 101 60.00 40,000.00 2,400,000.00

5

6

7

8

9

10

2,640,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Kerikil Sungai Tidak Disar M3 K 013 75.00 227,845.80 17,088,435.00

2 Alat bantu (Set @ 3 alat) Set M 170 2.50 55,000.00 137,500.00

3

4

5

6

7

8

9

10

17,225,935.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Self Vibrator roller 10 to 1 1 E 082 5.00 Err:509 Err:509

2 Water Tank Truck 1 1 E 182 5.00 238,523.25 1,192,616.25

3

4

5

6

7

8

9

10

Err:509

T O T A L (Rp) Err:509

VOL : 60.00 SATUAN : M3 HARGA SATUAN Err:509 PER M3

Page 26: RAB Jalan Analisa K

ANALISA BIAYA PENGADAAN KERIKIL SUNGAI (TAK DISARING) KODE

PEKERJAAN ( MENGGUNAKAN BURUH ) K - 013

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Truk diisi dgn tenaga manusia disungai 1 Menggunakan tenaga manusia (60 m3/hari)

2 Truk mengangkut kerikil ke lokasi pekejaan 2 Muatan 5 truk/jam (1m3/orang/hari)

atau penimbunan 3 Material dikirim ke lokasi pekerjaan atau penimbunan

3 Muatan dibongkar dgn tenaga manusia 4 Jarak angkut 10 km, 72 menit per trip, 5 trip / hari / truk

5 Volume yang dihitung berdasarkan 3 ton/truk lepas (BJ = 1.5)

6 Pengambilan Material dgn dipungut pembayaran ganti rugi royalti yang berlaku

7 Penggunaan alat bantu rata-rata 1 set/orang/bulan

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 2 1 L 061 2.00 70,000.00 140,000.00

2 S o p i r 6 1 L 091 6.00 40,000.00 240,000.00

3 Buruh Tak Terlatih 60 1 L 101 60.00 40,000.00 2,400,000.00

4

5

6

7

8

9

10

2,780,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Sirtu M3 M 042 60.00 101,300.00 6,078,000.00

2 Alat bantu (Set @ 3 alat) Set M 170 2.50 55,000.00 137,500.00

3

4

5

6

7

8

9

10

6,215,500.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Dump truck 3,5 ton 6 1 E 211 36.00 129,868.00 4,675,248.00

2

3

4

5

6

7

8

9

10

4,675,248.00

T O T A L (Rp) 13,670,748.00

VOL : 60.00 SATUAN : M3 HARGA SATUAN 227,845.80 PER M3

Page 27: RAB Jalan Analisa K

ANALISA BIAYA MEMBERSIHKAN PARIT SAMPING KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 424

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Bersihkan saluran samping dan gorong-gorog 1 Menggunakan Tenaga manusia

dari sampah dan kotoran dan tumbuhan 2 Membersihkan sampah, kotoran yang menyumbat, tumbuh tumbuhan dari

2 Buang sampah dan kotoran tsb dgn truk, dimuat dan gorong gorong

oleh tenaga manusia 3 Pembuangan runtuhan sejauh 1 km

4 Penggunaan alat bantu 1 bln-org

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 S o p i r 2 1 L 091 2.00 40,000.00 80,000.00

3 Buruh Tak Terlatih 36 1 L 101 36.00 40,000.00 1,440,000.00

4

5

6

7

8

9

10

1,590,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 1.20 55,000.00 66,000.00

2

3

4

5

6

7

8

9

10

66,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Dump truck 3,5 ton 2 1 E 211 10.00 129,868.00 1,298,680.00

2

3

4

5

6

7

8

9

10

1,298,680.00

T O T A L (Rp) 2,954,680.00

VOL : 500.00 SATUAN : M HARGA SATUAN 5,909.36 PER M

Page 28: RAB Jalan Analisa K

ANALISA BIAYA PEKERJAAN PLESTERAN KODE

PEKERJAAN (MENGGUNAKAN BURUH) G50k

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Material disiapkan di lokasi pekerjaan 1 Menggunakan Tenaga Manusia 200 m2/hari

2 Pekerja menakar dan mengaduk pasir dengan 2 Pasir disiapkan di lokasi pekerjaan oleh leveransir

3 Tukang memasang pada bidang yang diplester 3 Semen telah siap di lokasi pekerjaan

4 Adukan 1 semen : 4 pasir

5 Tebal Plesteran 1,00 cm setelah diratakan dengan acian semen

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Buruh Tak Terlatih 80 1 L 101 80.00 40,000.00 3,200,000.00

2 M a n d o r 4 1 L 061 4.00 70,000.00 280,000.00

3 T u k a n g 30 1 L 073 30.00 60,000.00 1,800,000.00

4 Kepala Tukang 3 1 L 079 3.00 60,000.00 180,000.00

5

6

7

8

9

10

5,460,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Semen Sak/50 kg M 080 18.24 59,500.00 1,085,280.00

2 Pasir pasang M3 M 041a 2.70 158,200.00 427,140.00

3 Alat bantu (Set @ 3 alat) Set M 170 1.44 55,000.00 79,200.00

4

5

6

7

8

9

10

1,591,620.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

T O T A L (Rp) 7,051,620.00

VOL : 200.00 SATUAN : M2 HARGA SATUAN 35,258.00 PER M2

Page 29: RAB Jalan Analisa K

ANALISA BIAYA PEMBENTUKAN DAN PERATAAN BAHU JALAN KODE

PEKERJAAN (MENGGUNAKAN ALAT) K - 855

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Grader melakukan 1 lintasan untuk memotong 1 Menggunakan alat berat

1 lintasan untuk meratakan sepanjang bahu jal 2 Mandor mengawasi juga pekerjaan lain dgn baik

2 Buruh membersihkan sampah pada gorong2 3 Meratakan bahu jalan 5 km/hari

dan rintangan2 4 Harga satuan ini untuk 1 sisi bahu jalan

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 Buruh Tak Terlatih 4 1 L 101 4.00 40,000.00 160,000.00

4

5

6

7

8

9

10

280,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 0.20 55,000.00 11,000.00

2

3

4

5

6

7

8

9

10

11,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Motor grader 1 1 E 010 5.00 366,589.65 1,832,948.25

2

3

4

5

6

7

8

9

10

1,832,948.25

T O T A L (Rp) 2,123,948.25

VOL : 5.00 SATUAN : KM HARGA SATUAN 424,790.00 PER KM

Page 30: RAB Jalan Analisa K

ANALISA BIAYA MEMBERSIHKAN RUMPUT DAN TANAMAN DI BAHU JALAN KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 422

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Potong semak belukar yang tumbuh pada bahu 1 Menggunakan tenaga manusia

2 Bersihkan rumput/semak dari bahu jalan dan a 2 Dengan lebar 1.5 dari tepi jalan, rata2 luas yang dibersihkan 3000 m2/km satu sisi

3 Hasil kerja 60 m2/hari-orang

4 Sampah/reruntuhan dibuang sejauh 1 km

5 Penggunaan alat bantu 1 bln-orang

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 Buruh Tak Terlatih 25 1 L 101 25.00 40,000.00 1,000,000.00

3

4

5

6

7

8

9

10

1,070,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 1.00 55,000.00 55,000.00

2

3

4

5

6

7

8

9

10

55,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

T O T A L (Rp) 1,125,000.00

VOL : 1,500.00 SATUAN : M2 HARGA SATUAN 750.00 PER M2

Page 31: RAB Jalan Analisa K

ANALISA BIAYA MEMBENTUK BAHU JALAN PADAT KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 410

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Bahan timbuna dihampar dgn tenaga manusia 1 Menggunakan tenaga manusia (96 m3/hari, pemadatan 960 m bahu jalan)

2 Pemadatan dgn mesin gilas bergetar 2 Material pilihan dikirim sampai tempat pekerjaan oleh leveransir

3 Leveransir meletakkan material timbunan sepanjang bahu jalan

4 10 cm timbunan padat dibutuhkan pada 1 m lebar bahu jalan

5 Penghamparan timbunan dgn tenaga manusia

6 Pemadatan dgn mesin gilas kecil

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 2 1 L 061 2.00 70,000.00 140,000.00

2 Buruh Tak Terlatih 66 1 L 101 66.00 40,000.00 2,640,000.00

3 Buruh Semi Terlatih 1 1 L 103 1.00 40,000.00 40,000.00

4

5

6

7

8

9

10

2,820,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Timbunan pilihan M3 M 050 120.00 80,000.00 9,600,000.00

2 Alat bantu (Set @ 3 alat) Set M 170 2.50 55,000.00 137,500.00

3

4

5

6

7

8

9

10

9,737,500.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Vibrator roller 600 kg 1 1 E 087 5.00 340,245.15 1,701,225.75

2

3

4

5

6

7

8

9

10

1,701,225.75

T O T A L (Rp) ###

VOL : 96.00 SATUAN : M3 HARGA SATUAN 148,528.39 PER M3

Page 32: RAB Jalan Analisa K

ANALISA BIAYA MEMBERSIHKAN PARIT SAMPING KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 424

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Bersihkan saluran samping dan gorong-gorog 1 Menggunakan Tenaga manusia

dari sampah dan kotoran dan tumbuhan 2 Membersihkan sampah, kotoran yang menyumbat, tumbuh tumbuhan dari dan gorong gorong

2 Buang sampah dan kotoran tsb dgn truk, dimu 3 Pembuangan runtuhan sejauh 1 km

oleh tenaga manusia 4 Penggunaan alat bantu 1 bln-org

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 S o p i r 2 1 L 091 2.00 40,000.00 80,000.00

3 Buruh Tak Terlatih 36 1 L 101 36.00 40,000.00 1,440,000.00

4

5

6

7

8

9

10

1,590,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 1.20 55,000.00 66,000.00

2

3

4

5

6

7

8

9

10

66,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Dump truck 3,5 ton 2 1 E 211 10.00 129,868.00 1,298,680.00

2

3

4

5

6

7

8

9

10

1,298,680.00

T O T A L (Rp) 2,954,680.00

VOL : 500.00 SATUAN : M HARGA SATUAN 5,909.36 PER M

Page 33: RAB Jalan Analisa K

ANALISA BIAYA TIMBUNAN TANAH DIPADATKAN KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 220

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Meratakan dgn tenaga manusia 1 Menggunakan tenaga manusia (60 m3/hari)

2 Pemadatan lapisan-lapisan 2 Dipakai material dari daerah penggalian

3 Perataan dgn tenaga manusia, tebal per lapis 10 cm

4 Pemadatan dgn mesin gilas tandem

5 Hasil pemadatan 60 m3

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 3 1 L 061 3.00 70,000.00 210,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 Buruh Tak Terlatih 90 1 L 101 90.00 40,000.00 3,600,000.00

4

5

6

7

8

9

10

3,860,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 6.00 55,000.00 330,000.00

2

3

4

5

6

7

8

9

10

330,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Tandem roller 6 - 10 ton 1 1 E 081 5.00 165,526.20 827,631.00

2

3

4

5

6

7

8

9

10

827,631.00

T O T A L (Rp) 5,017,631.00

VOL : 60.00 SATUAN : M3 HARGA SATUAN 83,627.00 PER M3

Page 34: RAB Jalan Analisa K

ANALISA BIAYA PENGUPASAN TANAH DAN KODE

PEKERJAANPEMBERSIHAN SEMAK PADA DAMIJA

(MENGGUNAKAN BURUH) K - 210

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Mengupas dan membuang semak dengan 1 Menggunakan tenaga manusia (9m X 100m / hari)

tenaga manusia pada DAMIJA 2 Hasil kerja 25 m2/orang/hari

3 Penggunaan alat bantu 1 bulan-orang

4 Bakar sampah ditempat pekerjaan

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 Buruh Tak Terlatih 36 1 L 101 36.00 40,000.00 1,440,000.00

3

4

5

6

7

8

9

10

1,510,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 1.50 55,000.00 82,500.00

2

3

4

5

6

7

8

9

10

82,500.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

9

10

0.00

T O T A L (Rp) 1,592,500.00

VOL : 900.00 SATUAN : M2 HARGA SATUAN 1,769.00 PER M2

Page 35: RAB Jalan Analisa K

ANALISA BIAYA MEMBUAT PARIT GALIAN TANAH KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 110

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Gali Parit 1 Menggunakan tenaga manusia 100 m' / hari

2 Membuang hasil galian menggunakan truk 2 Dimensi saluran : Lebar baw = 0.50 m

3 Lebar atas = 0.90 m

4 Kedalaman= 1.30 m

5 Volume = 0.54 m3/m

6 25% hasil galian dibuang setempat

7 Hasil galian dibuang sejauh 2km

8 Menggali dan membuang dihitung 1,5 m3/hari-orang

9 Penggunaan alat bantu 1 bulan - orang

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 S o p i r 2 1 L 091 2.00 40,000.00 80,000.00

3 Buruh Tak Terlatih 36 1 L 101 36.00 40,000.00 1,440,000.00

4

5

6

7

8

9

10

1,590,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 1.50 55,000.00 82,500.00

2

3

4

5

6

7

8

9

10

82,500.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Dump truck 3,5 ton 2 1 E 211 10.00 129,868.00 1,298,680.00

2

3

4

5

6

7

8

9

10

1,298,680.00

T O T A L (Rp) 2,971,180.00

VOL : 54.00 SATUAN : M3 HARGA SATUAN 55,021.85 PER M3

Page 36: RAB Jalan Analisa K

ANALISA BIAYA PASANGAN BATU PADA PARIT GALIAN TANAH KODE

PEKERJAAN (MENGGUNAKAN BURUH) K - 112

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Galian tambahan (0.55 m3/m) 1 Galian parit 0.43 m3/m

2 Pasangan parit berdekatan dgn dinding pen 2 Ukuran parit bagian dalam : Tebal = 20 cm

tanah bila diperlukan 3 Lebar bawah = 0.5 m

3 Tebal pasangan 20 cm 4 Lebar atas = 0.9 m

5 Kedalaman = 0.6 m

6 40 % Pembuangan hasil galian dgn truk biasa sejauh 1km

7 60% Dibuang setempat

8 Hasil produksi 60 m/hari

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 6 L 061 6.00 70,000.00 420,000.00

2 S o p i r 1 2 L 091 2.00 40,000.00 80,000.00

3 Buruh Tak Terlatih 6 6 L 101 36.00 40,000.00 1,440,000.00

4 T u k a n g 2 6 L 073 12.00 60,000.00 720,000.00

5 Buruh Semi Terlatih 2 6 L 103 12.00 40,000.00 480,000.00

6

7

8

9

10

3,140,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 1.50 55,000.00 82,500.00

2 Batu Gunung (Quarry) M3 M 010 30.00 195,000.00 5,850,000.00

3 Pasir beton M3 M 041 7.50 158,200.00 1,186,500.00

4 Semen Sak/50 kg M 080 91.20 59,500.00 5,426,400.00

5

6

7

8

9

10

12,545,400.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Dump truck 3,5 ton 1 2 E 211 10.00 129,868.00 1,298,680.00

2

3

4

5

6

7

8

9

10

1,298,680.00

T O T A L (Rp) ###

VOL : 60.00 SATUAN : M' HARGA SATUAN 283,068.00 PER M'

Page 37: RAB Jalan Analisa K

ANALISA BIAYA PASANG PIPA GORONG-GORONG DIA. 60 CM KODE

PEKERJAAN(PRACETAK, TAK BERTULANG, TANPA DINDING KEPALA)

(MENGGUNAKAN BURUH) K - 121

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Digali jalur gorong2 lebar 1m dan kedalama 1 Menggunakan tenaga manusia (tidak termasuk kepala gorong-gorong)

di bawah permukaan tanah dasar 2 Menggunakan pipa beton tak bertulang beli setempat

2 Pengadan gorong2 sampai ditempatnya 3 Beton K 125 digunakan untuk alas dan penyambung pipa gorong-gorong

3 Menempatkan pipa di tempat gorong2 4 Pengiriman bahan2 sampai ke tempat pekerjaan

4 Timbun dan padatkan sampai permukaan ta 5 Tidak termasuk galian dan pemadatan ulang dari perkerasan yang ada

5 Jika dibutuhkan tambahan / penggantian gorong2

dibutuhkan pekerja extra

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 4 L 061 4.00 70,000.00 280,000.00

2 Buruh Tak Terlatih 5 4 L 101 20.00 40,000.00 800,000.00

3 Buruh Semi Terlatih 2 4 L 103 8.00 40,000.00 320,000.00

4

5

6

7

8

9

10

1,400,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Beton non struktur K 125 M3 K 720 4.50 925,719.00 4,165,735.50

2 M' M 031 8.00 Err:509 Err:509

3 Alat bantu (Set @ 3 alat) Set M 170 0.80 55,000.00 44,000.00

4

5

6

7

8

9

10

Err:509

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Stamper 1 2 E 088 10.00 38,659.95 386,599.50

2

3

4

5

6

7

8

9

10

386,599.50

T O T A L (Rp) Err:509

VOL : 8.00 SATUAN : M' HARGA SATUAN Err:509 PER M'

Pipa Beton f 60 cm

Page 38: RAB Jalan Analisa K

ANALISA BIAYA BETON NON STRUKTUR / RABAT KODE

PEKERJAANKLAS K-125

K - 720

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Material dikirim oleh leveransir 1 Bahan - bahan dikirim ke lokasi pekerjaan oleh leveransir

2 Pencampuran beton di lokasi pekerjaan 2 Dipakai aggregat pecah tersaring

3 Hasil kerja 6,0 m3/hari

4 Campuran 1 pc : 3 ps : 5 krl

5 Dalam 1 m2 beton dibutuhkan semen pc 250 kg/m3

6 Setiap pencampuran memerlukan 30 kg semen pc

7 Dibutuhkan untuk alas pondasi beton

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 T u k a n g 1 1 L 073 1.00 60,000.00 60,000.00

3 Buruh Tak Terlatih 12 1 L 101 12.00 40,000.00 480,000.00

4 Buruh Semi Terlatih 2 1 L 103 2.00 40,000.00 80,000.00

5

6

7

8

9

10

690,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Pasir beton M3 M 041 3.00 158,200.00 474,600.00

2 Semen Sak/50 kg M 080 32.00 59,500.00 1,904,000.00

3 Kayu / papan perancah M3 M 180 0.20 2,100,000.00 420,000.00

4 Alat bantu (Set @ 3 alat) Set M 170 0.60 55,000.00 33,000.00

5 Batu pecah 1 - 2 cm M3 M 025 5.00 251,000.00 1,255,000.00

6

7

8

9

10

4,086,600.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Concrete Vibrator 1 1 E 089 5.00 54,691.35 273,456.75

2 Concrete Mixer 0,125 m3 1 1 E 251 5.00 62,431.95 312,159.75

3 Water Pump dia 5" 1 1 E 341 5.00 38,419.50 192,097.50

4

5

6

7

8

9

10

777,714.00

T O T A L (Rp) 5,554,314.00

VOL : 6.00 SATUAN : M3 HARGA SATUAN 925,719.00 PER M3

Page 39: RAB Jalan Analisa K

ANALISA BIAYA DINDING SAYAP GORONG-GORONG PASANGAN BATU KODE

PEKERJAAN(SATU PASANG),

(MENGGUNAKAN BURUH) K - 139

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Gali tanah untuk dinding dan dasar kaki ke 1 Tebal rata-rata dinding 45 cm

sisi (13 m3) 2 Volume seluruhnya 8 m3

2 Buat 2 dinding kepala pasangan batu 3 Bahan dikirim sampai ketempat pekerjaan

3 Timbun kembali dengan urugan yang baik ( 4 Dinding berdiri pada pelat pasangan batu tebal 25 cm

4 Buang hasil galian yang tidak terpakai

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 2 6 L 061 12.00 70,000.00 840,000.00

2 Buruh Tak Terlatih 25 6 L 101 150.00 40,000.00 6,000,000.00

3 Buruh Terlatih 1 6 L 106 6.00 40,000.00 240,000.00

4 T u k a n g 2 6 L 073 12.00 60,000.00 720,000.00

5

6

7

8

9

10

7,800,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Alat bantu (Set @ 3 alat) Set M 170 3.00 55,000.00 165,000.00

2 Timbunan Konstruksi M3 K225 3.00 286,288.00 858,864.00

3 Batu pecah 10 - 15 cm M3 M 020 8.00 250,000.00 2,000,000.00

4 Pasir beton M3 M041 2.00 158,200.00 316,400.00

5 Semen Zak M 080 24.00 59,500.00 1,428,000.00

6

7

8

9

10

4,768,264.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Pompa Air 1 1 E 341 2.00 38,419.50 76,839.00

2

3

4

5

6

7

8

9

10

76,839.00

T O T A L (Rp) ###

VOL : 8.00 SATUAN : M3 HARGA SATUAN 1,580,638.00 PER M3

Page 40: RAB Jalan Analisa K

ANALISA BIAYA PENIMBUNAN DAN PEMADATAN KODE

PEKERJAAN(UNTUK JEMBATAN & GORONG-GORONG)

(MENGGUNAKAN BURUH) K - 225

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 30-Dec-99

URAIAN ANGGAPAN / ASUMSI

1 Struktur dibersihkan dari bahan-bahan orga 1 Bahan timbunan dikirim ke lapangan oleh leveransir

2 Timbun kembali bagian belakan struktur 2 Timbunan dipadatkan berlapis tebal 10 cm

3 Padatkan dgn stamper dan mesin gilas bergetar

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

2 S o p i r 10 1 L 091 10.00 40,000.00 400,000.00

3 Buruh Semi Terlatih 3 1 L 103 3.00 40,000.00 120,000.00

4

5

6

7

8

9

10

590,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Timbunan pilihan M3 M 050 20.00 80,000.00 1,600,000.00

2 Alat bantu (Set @ 3 alat) Set M 170 0.30 55,000.00 16,500.00

3

4

5

6

7

8

9

10

1,616,500.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Vibrator roller 600 kg 1 1 E 087 5.00 340,245.15 1,701,225.75

2 Stamper 1 2 E 088 10.00 38,659.95 386,599.50

3

4

5

6

7

8

9

10

2,087,825.25

T O T A L (Rp) 4,294,325.25

VOL : 15.00 SATUAN : M3 HARGA SATUAN 286,288.00 PER M3

Page 41: RAB Jalan Analisa K

ANALISA HARGA KONSTRUKSI PASANGAN BATU KODE

SATUAN (MENGGUNAKAN BURUH) K - 705

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 December-99

URAIAN ANGGAPAN / ASUMSI

1 Material di timbun di lokasi pekerjaan 1 Dilakukan untuk pekerjaan gorong-gorong, jembatan, dinding penahan tanah

oleh pemasok dan struktur lainnya yang menggunakan konstruksi pasangan batu

2 Pekerja membawa batu pecah ke tempat 2 Material-material dikirim ke tempat pekerjaan oleh pemasok

tukang batu pekerja 3 Tidak termasuk galian / timbunan

3 Tukang batu memasang batu pecah dengan 4 Biaya alat bantu tambahan sudah termasuk biaya kira-kira ekivalen dari

adukan pasir semen bambu untuk lubang drainase

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Kepala Tukang 1 1 L 073 1.00 60,000.00 60,000.00

2 T u k a n g 4 1 L 079 4.00 60,000.00 240,000.00

3 Buruh Tak Terampil 12 1 L 101 12.00 40,000.00 480,000.00

4

5

6

7

8

9

10

780,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Batu Belah Hitam M3 M 010 5.00 195,000.00 975,000.00

2 Pasir beton M3 M 041 1.25 158,200.00 197,750.00

3 Semen Sak/50 kg M 080 15.20 59,500.00 904,400.00

4 Alat bantu (Set @ 3 alat) Set M 170 0.75 55,000.00 41,250.00

5

6

7

8

9

10

2,118,400.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Water Pump dia 70 - 100 m 1 1.00 E 341 2.00 38,419.50 76,839.00

2

3

4

5

6

7

8

9

10

76,839.00

T O T A L (Rp) 2,975,239.00

VOL : 5.00 SATUAN : M3 HARGA SATUAN 595,048.00 PER M3

Page 42: RAB Jalan Analisa K

ANALISA HARGA URUGAN PASIR BAWAH LANTAI DAN PONDASI KODE

SATUAN (MENGGUNAKAN BURUH) A 18

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 December-99

URAIAN ANGGAPAN / ASUMSI

1 Lahan yang akan diurug telah siap 1 Menggunakan Tenaga Manusia 100 m3/hari

2 Material disiapkan ke lokasi oleh leveransir 2 Material (pasir urug) dikirim ke tempat pekerjaan oleh leveransir

3 Pekerja mengurugkan, meratakan, dan

memadatkan pasir

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Buruh Tak Terampil 30 1 L 101 30.00 40,000.00 1,200,000.00

2 M a n d o r 1 1 L 061 1.00 70,000.00 70,000.00

3

4

5

6

7

1,270,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Pasir urug M3 M 040 120.00 100,000.00 ###

2

3

4

5

6

7

8

12,000,000.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

0.00

T O T A L (Rp) 13,270,000.00

VOL : 100.00 SATUAN : M3 HARGA SATUAN 132,700.00 PER M3

Page 43: RAB Jalan Analisa K

ANALISA HARGA Bongkaran Gorong-gorong KODE

SATUAN (MENGGUNAKAN BURUH) L 3

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 December-99

URAIAN ANGGAPAN / ASUMSI

1 Lahan yang akan dibongkar telah siap 1 Menggunakan Tenaga Manusia 100 m3/hari

2 Pekerja merapihkan dan membersihkan

lahan yang telah dibongkar

3 Material bongkaran dibuang dari area kerjaan

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Buruh Tak Terampil 40 1 L 101 40.00 40,000.00 1,600,000.00

2 M a n d o r 4 1 L 061 4.00 70,000.00 280,000.00

3

4

5

6

7

1,880,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1

2

3

4

5

6

7

8

0.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1

2

3

4

5

6

7

8

0.00

T O T A L (Rp) 1,880,000.00

Page 44: RAB Jalan Analisa K

VOL : 100.00 SATUAN : M3 HARGA SATUAN 18,800.00 PER M3

Page 45: RAB Jalan Analisa K

ANALISA HARGA PEMBUATAN PIPA BETON BERTULANG KODE

SATUAN (MENGGUNAKAN BURUH) K - 115

PROPINSI : 0KODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 December-99

URAIAN ANGGAPAN / ASUMSI

1 Acuan dibersihkan dan dilapisi olie 1 Beton kelas K225 diaduk di lokasi pekerjaan (54 adukan / hari @ 114 liter/adukan)

2 Jaringan tulangan beton dibuat 2 Di cor kira-kira 6 m3/hari (terbuang 3%)

3 Acuan dirakit melingkari jaringan tulangan beton 3 Diameter dalam pipa 60 cm, luar 73 cm', tebal 6,5 cm, panjang 1 m"

4 Adukan beton dicor ke dalam acuan dan 4 Tulangan berlapis satu : 8,175 Kg/m pipa, 50 Kg/orang-hari (terbuang 9%)

digetar sampai padat 5 Buka dan bersihkan acuan 11m/kelompok/hari ; 4 kelompok buruh @ 2 orang

5 Membuka acuan setelahbeton cukup kuat 6 Berat pipa jadi masing-masing kira-kira 350 Kg

6 Pipa dipindahkan dengan loader 7 Umur acuan dari baja : 3 tahun atau 900 pemakaian @ 165 Kg/acuan

8 Sesuai peraturan Beton Bertulang Indonesia (PBI 1971 N.I. 2)

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Mandor Lapangan 1 1 L 061 1.00 70,000.00 70,000.00

2 Operator Terlatih 1 1 L 081 1.00 50,000.00 50,000.00

3 Operator Kurang Terlatih 8 1 L 101 8.00 40,000.00 320,000.00

4 Buruh Lapangan Terlatih 8 1 L 106 8.00 40,000.00 320,000.00

5

6

7

8

9

10

760,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Baja Struktur (Profil) Kg M 165 8.07 20,200.00 163,014.00

2 Baja tulangan beton U-24 Kg M 167 400.00 10,300.00 4,120,000.00

3 Alat bantu (Set @ 3 alat) Set M 170 0.32 55,000.00 17,600.00

4 Beton struktur kelas 225 (125 l) M3 K 722 6.17 841,797.00 5,193,887.49

5

6

7

8

9

10

9,494,501.49

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Loader wheeled 1 1 E 052 5.00 373,792.65 1,868,963.25

2

3

4

5

6

7

8

9

10

1,868,963.25

T O T A L (Rp) 12,123,464.74

VOL : 44.00 SATUAN : M' HARGA SATUAN 275,533.00 PER M'

Ø 600 MM x 1,0 M

Page 46: RAB Jalan Analisa K

ANALISA HARGA KODE

SATUANTANPA DINDING KEPALA

(MENGGUNAKAN BURUH) K - 122

PROPINSI : LAMPUNGKODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 December-99

URAIAN ANGGAPAN / ASUMSI

1 Digali parit lebar 1m dan kedalaman 1 m 1 Menggunakan tenaga manusia (tidak termasuk dinding kepala)

di bawah elevasi subgrade 2 Pipa beton pracetak bertulang 8 m dipasang dalam 4 hari

2 Suplai pipa kelokasi pekerjaan 3 Material pilihan digunakan untuk alas dan mengurug pipa gorong-gorong

3 Letakkan pipa pada alas parit sampai dibawah perkerasan

4 Urug kembali dan padatkan sekeliling pipa 4 Material diangkt ke lokasi pekerjaan oleh pemasok

sampai elevasi subgrade 5 Tidak termasuk galian dan pemadatan ulang perkerasan yang ada

5 Jika ada penambahan/penggantian pipa

gorong-gorong dibutuhkan pekerjaan ekstra

.

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Mandor Lapangan 1 4 L 061 4.00 70,000.00 280,000.00

2 Buruh Lapangan Tak Terlatih 7 4 L 101 28.00 40,000.00 1,120,000.00

3

4

5

6

7

8

9

10

1,400,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Kerikil Sungai Tak Tersaring M3 K 012 8.00 182,939.00 1,463,512.00

2 Pipa Beton Bertulang Ø 60 cm M' K 115 8.00 275,533.00 2,204,264.00

3 Alat bantu (Set @ 3 alat) Set M 170 1.12 55,000.00 61,600.00

4

5

6

7

8

9

10

3,729,376.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Stamper 1 2 E 088 10.00 38,659.95 386,599.50

2

3

4

5

6

7

8

9

10

386,599.50

T O T A L (Rp) 5,515,975.50

VOL : 8.00 SATUAN : M' HARGA SATUAN 689,497.00 PER M'

PASANG PIPA BETON PRACETAK BERTULANG Ø 600 MM

Page 47: RAB Jalan Analisa K
Page 48: RAB Jalan Analisa K

ANALISA HARGA PENGADAAN KERIKIL SUNGAI (TAK DISARING) KODE

SATUAN ( MENGGUNAKAN ALAT ) K - 012

PROPINSI : LAMPUNGKODE KABUPATEN KODE DISIAPKAN OLEH : TANGGAL

0 0 December-99

URAIAN ANGGAPAN / ASUMSI

1 Buldozer membuat timbunan 1 Menggunakan alat berat 360 M3/hari

kerikil di tepi sungai 2 Kapasitas wheel loader 60 M3/jam

2 Wheel loader memuati dumptruk dari timbunan 3 Wheel loader memuati 18 truk / jam (6 jam kerja/hari)

3 Dump truck mengangkut kerikil galian ke 4 Sumber material tersedia bebas/ dengan ganti rugi royalti yang berlaku

lokasi pekerjaan atau penimbunan 5 Pengadaan/penimbunan material 1 trip/jam/truk, 10 Km dari sumber

6 Volume yang diukur berdasarkan 5 ton lepas/truk (Bj = 1,6)

7 Umur alat bantu rata-rata 1 bulan/orang/set @ 3 alat

8

9

10

PEKERJAJUMLAH

HARI KODE JUMLAH UPAH BIAYA SUB TOTAL

ORANG Hari - Orang (Rp/Org/Hari) (Rp) (Rp)

P E

K E

R J

A

1 Mandor Lapangan 1 1 L 061 1.00 70,000.00 70,000.00

2 Operator Terlatih 3 1 L 081 3.00 50,000.00 150,000.00

3 Pembantu Operator 3 1 L 083 3.00 45,000.00 135,000.00

4 Supir terampil 18 1 L 091 18.00 40,000.00 720,000.00

5 Pembantu Supir 18 1 L 099 18.00 40,000.00 720,000.00

6 Buruh Lapangan Tak Terlatih 8 1 L 101 8.00 40,000.00 320,000.00

7

8

9

10

2,115,000.00

MATERIAL SATUAN KODE VOLUME HARGA SATUAN BIAYA SUB TOTAL

(Rp) (Rp) (Rp)

M A

T E

R I

A L

1 Sirtu M3 M 042 360.00 101,300.00 ###

2 Alat bantu (Set @ 3 alat) Set M 170 0.32 55,000.00 17,600.00

3

4

5

6

7

8

9

10

36,485,600.00

PERALATANJUMLAH HARI

KODE JAM KERJA HARGA BIAYA SUB TOTAL

ALAT KERJA (Rp/Jam) (Rp) (Rp)

P E

R A

L A

T A

N

1 Bulldozer 2 1 E 001 9.00 504,761.25 4,542,851.25

2 Loader wheeled 1 1 E 052 6.00 373,792.65 2,242,755.90

3 Dump truck 5 ton 18 1 E 212 108.00 189,554.40 ###

4

5

6

7

8

9

10

27,257,482.35

T O T A L (Rp) 65,858,082.35

VOL : 360.00 SATUAN : M3 HARGA SATUAN 182,939.00 PER M3