RAB FLUME

2
RENCANA ANGGARAN BIAYA PENELITIAN MODEL FLUME JURUSAN SIPIL, FAKULTAS TEKNIK UNIVERSITAS HASANUDDIN Makassar No. Jenis Bahan dan Pengerjaan Vol./Sat H.Satuan Jumlah 1 2 3 4 5 I PEKERJAAN RANGKA 1 IWF 200 x 100 x 5.5 x 8 (12 METER) 5.5 btg ### ### 2 UNP 100 X 50 X 6 X 6 (6 METER) 7 btg 600,000.00 4,200,000.00 3 biaya pengerjaan/pengelasan 1,674 kg 5,000.00 8,370,000.00 Sub total I ### II PEKERJAAN PLAT 1 Plat Borders 3 mm (4" X 8") 5 lbr 815,000.00 4,075,000.00 2 biaya pengerjaan/pengelasan 375 kg 5,000.00 1,875,000.00 Sub total II 5,950,000.00 III PEKERJAAN RODA 1 AS 4" 2 m 500,000.00 1,000,000.00 2 lahar 4" 2 bh 500,000.00 1,000,000.00 3 biaya pengerjaan/ las bubuk 2 bh 100,000.00 200,000.00 Sub total III 2,200,000.00 IV PEKERJAAN TAKEL 1 Takel 3 ton 1 bh ### 4,000,000.00 Sub total IV 4,000,000.00 V PEKERJAN BAK UKURAN 1.2 X 1.2 X 1.2 1 Plat Borders 2.3 mm (4" X 8") 3 lbr 560,000.00 1,680,000.00 2 Pipa kotak / Hollow 40 x 40 x 2.3 x 6 2 btg 175,000.00 350,000.00 3 AS 1.5" 2 m 110,000.00 220,000.00 4 lahar 1.5" 4 275,000.00 1,100,000.00 5 las bubuk 4 bh 100,000.00 400,000.00 6 biaya pengerjaan/pengelasan 211 kg 5,000.00 1,055,000.00 Sub total V 4,805,000.00 VI PEKERJAN BAK UKURAN 2.4 X 2.4 X 1.2 1 Plat Borders 2.3 mm (4" X 8") 5 lbr 560,000.00 2,800,000.00 2 Pipa kotak / Hollow 40 x 40 x 2.3 x 6 2 btg 175,000.00 350,000.00 3 biaya pengerjaan/pengelasan 329 kg 5,000.00 1,645,000.00 Sub total VI 4,795,000.00 VII PEKERJAAN FLUME 1 Akrilik (4" X 8") 8 lbr 650,000.00 5,200,000.00 2 Lem 10 bh 50,000.00 500,000.00 3 Pipa kotak / Hollow 20 x 20 x 2 x 6 2 btg 90,000.00 180,000.00 4 biaya pengerjaan 1 bh ### 5,000,000.00 Sub total VII ### VIII PEKERJAAN INSTALASI PIPA & POMPA AIR 1 Pompa air Tsuruni 3" 1 bh ### 3,850,000.00 2 pipa besi 3" 2 200,000.00 400,000.00 3 pipa 3" 1 btg 150,000.00 150,000.00 4 selan air 8 m 50,000.00 400,000.00 5 sambungan pipa 3" 2 bh 15,000.00 30,000.00 6 sambungan pipa besi 3" 3 bh 50,000.00 150,000.00 7 lem 2 bh 30,000.00 60,000.00 Sub total VIII 5,040,000.00 IX PEKERJAAN PONDASI POOR 1 15 btg 100,000.00 1,500,000.00 2 semen 40 kg 6 zak 46,000.00 276,000.00 3 anker 24 bh 100,000.00 2,400,000.00 4 upah tukang 2 hr 300,000.00 600,000.00 5 PLAT 400 X 200 X 8 17 bh 150,000.00 2,550,000.00 6 BAUT 3/4" 68 bh 15,000.00 1,020,000.00 Sub total IX 8,346,000.00 TOTAL BAHAN DAN PENGERJAAN FLUME tulangan 12 ø

description

hidrolika

Transcript of RAB FLUME

Page 1: RAB FLUME

RENCANA ANGGARAN BIAYA PENELITIAN MODEL FLUMEJURUSAN SIPIL, FAKULTAS TEKNIK

UNIVERSITAS HASANUDDIN

Makassar, 5 Juni 2015

No. Jenis Bahan dan Pengerjaan Vol./Sat H.Satuan Jumlah Total

1 2 3 4 5 6I PEKERJAAN RANGKA

1 IWF 200 x 100 x 5.5 x 8 (12 METER) 5.5 btg 2,624,000.00 14,432,000.00 2 UNP 100 X 50 X 6 X 6 (6 METER) 7 btg 600,000.00 4,200,000.00 3 biaya pengerjaan/pengelasan 1,674 kg 5,000.00 8,370,000.00

Sub total I 27,002,000.00 27,002,000.00 II PEKERJAAN PLAT

1 Plat Borders 3 mm (4" X 8") 5 lbr 815,000.00 4,075,000.00 2 biaya pengerjaan/pengelasan 375 kg 5,000.00 1,875,000.00

Sub total II 5,950,000.00 5,950,000.00 III PEKERJAAN RODA

1 AS 4" 2 m 500,000.00 1,000,000.00 2 lahar 4" 2 bh 500,000.00 1,000,000.00 3 biaya pengerjaan/ las bubuk 2 bh 100,000.00 200,000.00

Sub total III 2,200,000.00 2,200,000.00 IV PEKERJAAN TAKEL

1 Takel 3 ton 1 bh 4,000,000.00 4,000,000.00 Sub total IV 4,000,000.00 4,000,000.00

V PEKERJAN BAK UKURAN 1.2 X 1.2 X 1.21 Plat Borders 2.3 mm (4" X 8") 3 lbr 560,000.00 1,680,000.00 2 Pipa kotak / Hollow 40 x 40 x 2.3 x 6 2 btg 175,000.00 350,000.00 3 AS 1.5" 2 m 110,000.00 220,000.00 4 lahar 1.5" 4 275,000.00 1,100,000.00 5 las bubuk 4 bh 100,000.00 400,000.00 6 biaya pengerjaan/pengelasan 211 kg 5,000.00 1,055,000.00

Sub total V 4,805,000.00 4,805,000.00 VI PEKERJAN BAK UKURAN 2.4 X 2.4 X 1.2

1 Plat Borders 2.3 mm (4" X 8") 5 lbr 560,000.00 2,800,000.00 2 Pipa kotak / Hollow 40 x 40 x 2.3 x 6 2 btg 175,000.00 350,000.00 3 biaya pengerjaan/pengelasan 329 kg 5,000.00 1,645,000.00

Sub total VI 4,795,000.00 4,795,000.00 VII PEKERJAAN FLUME

1 Akrilik (4" X 8") 8 lbr 650,000.00 5,200,000.00 2 Lem 10 bh 50,000.00 500,000.00 3 Pipa kotak / Hollow 20 x 20 x 2 x 6 2 btg 90,000.00 180,000.00 4 biaya pengerjaan 1 bh 5,000,000.00 5,000,000.00

Sub total VII 10,880,000.00 10,880,000.00 VIII PEKERJAAN INSTALASI PIPA & POMPA AIR

1 Pompa air Tsuruni 3" 1 bh 3,850,000.00 3,850,000.00 2 pipa besi 3" 2 200,000.00 400,000.00 3 pipa 3" 1 btg 150,000.00 150,000.00 4 selan air 8 m 50,000.00 400,000.00 5 sambungan pipa 3" 2 bh 15,000.00 30,000.00 6 sambungan pipa besi 3" 3 bh 50,000.00 150,000.00 7 lem 2 bh 30,000.00 60,000.00

Sub total VIII 5,040,000.00 5,040,000.00 IX PEKERJAAN PONDASI POOR

1 15 btg 100,000.00 1,500,000.00 2 semen 40 kg 6 zak 46,000.00 276,000.00 3 anker 24 bh 100,000.00 2,400,000.00 4 upah tukang 2 hr 300,000.00 600,000.00 5 PLAT 400 X 200 X 8 17 bh 150,000.00 2,550,000.00 6 BAUT 3/4" 68 bh 15,000.00 1,020,000.00

Sub total IX 8,346,000.00 8,346,000.00

TOTAL BAHAN DAN PENGERJAAN FLUME 73,018,000.00

tulangan 12 ø