PENERAPAN METODE FAST TRACK
TERHADAP EFISIENSI BIAYA DAN EFEKTIVITAS WAKTU
PADA PELAKSANAAN PROYEK KONSTRUKSI
(Studi Kasus : Proyek Hatten Wines Bali)
TUGAS AKHIR
Oleh :
I Made Kusnaedi
NIM: 1204105104
JURUSAN TEKNIK SIPIL
FAKULTAS TEKNIK
UNIVERSITAS UDAYANA
2016
![Page 2: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/2.jpg)
HALAMAN PERNYATAAN
Yang bertanda tangan di bawah ini, saya :
Nama : I Made Kusnaedi
NIM : 1204105104
Judul TA : Penerapan Metode Fast Track Terhadap Efisiensi Biaya Dan Efektivitas
Waktu Pada Pelaksanaan Proyek Konstruksi (Studi Kasus : Proyek Hatten
Wines Bali)
Dengan ini saya nyatakan bahwa dalam Laporan Tugas Akhir/Skripsi saya ini tidak
terdapat karya yang pernah diajukan untuk memperoleh gelar kesarjanaan di suatu perguruan
tinggi, dan sepanjang pengetahuan saya, juga tidak terdapat karya atau pendapat yang pernah
ditulis atau diterbitkan oleh orang lain, kecuali secara tertulis dicantumkan dalam naskah ini
dan disebutkan dalam daftar pustaka.
Denpasar, Juni 2016
I Made Kusnaedi
NIM. 1204105104
![Page 3: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/3.jpg)
KEMENTERIAN RISET, TEKNOLOGI DAN PENDIDIKAN TINGGI
UNIVERSITAS UDAYANA
FAKULTAS TEKNIK
JURUSAN TEKNIK SIPIL Kampus Bukit JimbaranTelp./Fax: (0361) 703385
http://www.sipil.unud.ac.id
Email: [email protected]
LEMBAR PENGESAHAN LAPORAN TUGAS AKHIR
Tugas akhir ini telah diujikan dan dinyatakan lulus, sudah direvisi serta telah
mendapat persetujuan pembimbing sebagai salah satu persyaratan untuk
menyelesaikan Program S-1 pada Jurusan Teknik Sipil, Fakultas Teknik
Universitas Udayana.
Judul Tugas Akhir : Penerapan Metode Fast Track Terhadap Efisiensi
Biaya Dan Efektivitas Waktu Pada Pelaksanaan
Proyek Konstruksi
(Studi Kasus : Proyek Hatten Wines Bali)
Nama : I Made Kusnaedi
NIM : 1204105104
Jurusan : Teknik Sipil
Diuji Tanggal : 13 Mei 2016
Bukit Jimbaran,……………………….
Menyetujui:
Pembimbing I
Ir. Nym. Martha Jaya, M.Const.Mgt.,Ph.D,
GCInstCES
NIP. 19590214 198801 1 001
Pembimbing II
Ir. I Putu Darma Warsika, MSc,MM.
NIP. 19570927 198702 1 001
Mengetahui:
Ketua Jurusan Teknik Sipil
Fakultas Teknik Universitas Udayana
I KETUT SUDARSANA, ST, Ph.D. NIP. 19691016 199601 1 001
![Page 4: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/4.jpg)
i
ABSTRAK
Metode pelaksanaan pada proyek swasta umumnya menggunakan metode
design and build yaitu suatu metode pelaksanaan yang dapat dilakukan bersama-
sama dengan proses desain. Namun metode ini memiliki kelemahan yaitu
berpotensi mengakibatkan pengerjaan ulang (rework) serta akan menimbulkan
pembengkakan biaya (cost overrun). Untuk meminimalkan terjadinya cost
overrun, maka dapat diterapkan metode fast track. Metode fast track adalah
metode percepatan dalam pembangunan dengan melakukan pelaksanaan aktivitas-
aktivitas secara parallel/tumpang tindih pada penjadwalan proyek agar
menghasilkan waktu pelaksanaan lebih cepat dan biaya lebih efisien.
Proyek pembangunan Hatten Wines Bali dipilih sebagai studi kasus karena
mengandung konsep design and build pada pelaksanaan proyek konstruksinya.
Data penelitian ini menggunakan data sekunder pada proyek yaitu : Rencana
Anggaran Biaya (RAB) dan penjadwalan awal proyek (time schedule).
Dari data tersebut, kemudian metode fast track diterapkan agar dapat
mereduksi biaya dan waktu pelaksanaan proyek. Diawali dengan penyusunan
penjadwalan pada microsoft project 2013 dengan menyusun setiap item kegiatan
untuk menentukan lintasan kritis dari setiap item pekerjaan tersebut selanjutnya
menganalisis dengan menerapkan ketentuan-ketentuan metode fast track hingga
mencapai lintasan kritis yang jenuh atau tidak dapat dilakukan fast track lagi.
Hasil analisis membuktikan bahwa penerapan metode fast track dapat
memperkecil resiko pembengkakan biaya serta dapat memberikan keuntungan
berupa penghematan waktu selama 34 hari atau 12% dari waktu pelaksanaan
proyek semula (287 hari menjadi 253 hari). Sedangkan pada biaya tidak langsung
juga terjadi penghematan (efisiensi) sebesar Rp. 103.652.724,5 atau sekitar 1,09%
dari biaya proyek awal.
Kata kunci : Biaya, Design and build, Fast track, Lintasan kritis, Waktu.
![Page 5: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/5.jpg)
ii
UCAPAN TERIMA KASIH
Dengan mengucapkan Puji Syukur kepada Tuhan Yang Maha Esa, Ida
Sang Hyang Widhi Wasa yang telah melimpahkan rahmat dan karunia-Nya
akhirnya penulis dapat menyelesaikan tugas akhir yang berjudul “ Penerapan
Metode Fast Track Terhadap Efisiensi Biaya dan Efektivitas Waktu Pada
Pelaksanaan Proyek Konstruksi (Studi Kasus : Proyek Hatten Wines Bali)”.
Selama penyusunan tugas akhir ini, penulis mendapat informasi, bantuan
serta bimbingan dari beberapa pihak. Untuk itu dengan segala kerendahan hati
penulis mengucapkan terima kasih kepada : Bapak Ir. Nym. Martha Jaya,
M.Const.,Mgt.,Ph.D.,GCInstCES, selaku Dosen Pembimbing I, Bapak Ir. I Putu
Darma Warsika, MSc, MM. selaku Dosen Pembimbing II, Bapak Nyoman
Sugiartha sebagai Project Manager PT. Tunas Jaya Sanur yang telah memberikan
ijin pengambilan data untuk tugas akhir ini, serta teman-teman Sipil angkatan
2012 khususnya Sandat Crew yang tidak dapat disebutkan satu persatu yang turut
membantu baik secara langsung maupun tidak langsung dalam penyusunan dan
penyelesaian tugas akhir ini.
Penulis menyadari bahwa kemampuan yang penulis miliki dalam
penyusunan tugas akhir ini jauh dari kesempurnaan. Untuk itu penulis
mengharapkan kritik dan saran yang bersifat membangun dari pembaca guna
kesempurnaan tugas akhir selanjutnya.
Akhir kata penulis mengucapkan terima kasih dan semoga tugas akhir ini
dapat berguna bagi pembaca.
Denpasar, Juni 2016
Penulis
![Page 6: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/6.jpg)
iii
DAFTAR ISI
Halaman Judul Halaman Pernyataan Lembar Pengesahan Laporan Tugas Akhir Abstrak .................................................................................................................... i
Ucapan Terima Kasih.............................................................................................. ii Daftar Isi ................................................................................................................ iii Daftar Gambar.......................................................................................................... v Daftar Tabel ........................................................................................................... vi
BAB I PENDAHULUAN ....................................................................................... 1 1.1 Latar Belakang ................................................................................. 1
1.2 Rumusan Masalah ............................................................................ 2 1.3 Tujuan Penelitian ............................................................................. 3 1.4 Manfaat Penelitian ........................................................................... 3 1.5 Batasan Penelitian ............................................................................ 3
BAB II TINJAUAN PUSTAKA ........................................................................... 4 2.1 Proyek Konstruksi ............................................................................ 4
2.2 Metode Pembangunan Infrastruktur................................................. 5 2.2.1. Tradisional (Konvensional) ................................................... 5
2.2.2. Manajemen Konstruksi (MK) ................................................ 7 2.2.3. Design/Build .......................................................................... 9 2.2.4. Turnkey ................................................................................ 10
2.2.5. Build Operate Transfer (BOT) ............................................ 12
2.3 Penyusunan Time Schedule ........................................................... 14 2.3.1 Perencanaan ......................................................................... 14 2.3.2 Penjadwalan ......................................................................... 15
2.4 Teknik Penjadwalan ....................................................................... 15 2.4.1 Metode Diagram Balok (Bar Chart) ................................... 17
2.4.2 Metode Diagram Anak Panah / Arrow Diagram Method
(ADM) ................................................................................. 18 2.4.3 Metode Diagram Preseden/Precedence Diagram Method
(PDM) .................................................................................. 19 2.4.3.1 Konstrain Selesai ke Mulai – FS ............................. 21
2.4.3.2 Konstrain Mulai ke Mulai – SS ............................... 22 2.4.3.3 Konstrain Selesai ke Selesai - FF ............................ 22 2.4.3.4 Konstrain Mulai ke Selesai – SF ............................. 23
2.5 Biaya Proyek .................................................................................. 23 2.5.1 Biaya Langsung (Direct Cost) ............................................. 23 2.5.2 Biaya Tidak Langsung (Indirect Cost) ................................ 24
2.6 Metode Pelaksanaan Konstruksi .................................................... 27 2.7 Penggunaan Microsoft Project ....................................................... 30
BAB III METODE ............................................................................................... 32 3.1 Identifikasi Permasalahan .............................................................. 32 3.2 Pengumpulan Data ......................................................................... 32
![Page 7: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/7.jpg)
iv
3.2.1 Langkah dan Teknis Pengumpulan Data ............................. 32
3.2.2 Sumber Data ........................................................................ 33 3.3 Penyusunan Jaringan Kerja ............................................................ 33 3.4 Fast Track ...................................................................................... 34 3.5 Kerangka Penelitian ....................................................................... 35
BAB IV HASIL DAN PEMBAHASAN ............................................................. 36 4.1 Penentuan Objek Studi ................................................................... 36 4.2 Pengumpulan Data ......................................................................... 37 4.3 Pengolahan Data ............................................................................ 37
4.3.1 Penyusunan Jaringan Kerja ................................................. 37
4.3.2 Rincian Biaya Proyek .......................................................... 40 4.3.2.1 Rincian Biaya Langsung.......................................... 40
4.3.2.2 Rincian Biaya Tidak langsung................................. 41 4.4 Analisis Metode Fast Track ........................................................... 41
4.4.1 Menghitung Waktu/Durasi Dengan Metode Fast Track
Pada Penjadwalan ................................................................ 41
4.4.2 Menghitung Biaya Proyek Setelah Penerapan Metode
Fast Track ............................................................................ 47
BAB V PENUTUP ............................................................................................... 50 5.1 Simpulan ........................................................................................ 50
5.2 Saran .............................................................................................. 50
DAFTAR PUSTAKA ........................................................................................... 51
LAMPIRAN A Rincian Biaya Tidak Langsung .................................................... 53
LAMPIRAN B Bar Chart Sebelum Dipercepat .................................................... 75 LAMPIRAN C Bar Chart Setelah Fast Track I .................................................... 82 LAMPIRAN D Bar Chart Setelah Fast Track II ................................................... 89
LAMPIRAN E Bar Chart Setelah Fast Track III .................................................. 96 LAMPIRAN F Gambar Proyek ........................................................................... 103
![Page 8: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/8.jpg)
v
DAFTAR GAMBAR
Gambar 2.1 Struktur Organisasi Metode Konvensional ....................................... 5 Gambar 2.2 Struktur Organisasi Metode Manajemen Konstruksi (MK) .............. 8 Gambar 2.3 Struktur Organisasi Metode Design/Build......................................... 9 Gambar 2.4 Struktur Organisasi Metode Turnkey............................................... 11
Gambar 2.5 Hubungan peristiwa dan kegiatan pada ADM................................. 18 Gambar 2.6 Diagram Anak Panah ....................................................................... 19 Gambar 2.7 Denah pada Node PDM ................................................................... 20 Gambar 2.8 Konstrain Finish to Start ................................................................. 22 Gambar 2.9 Konstrain Start to Start .................................................................... 22
Gambar 2.10 Konstrain Finish to Finish ............................................................... 22 Gambar 2.11 Konstrain Start to Finish ................................................................. 23
Gambar 2.12 Hubungan biaya total, biaya tidak langsung dan biaya langsung .... 26
Gambar 3.1 Kerangka Penelitian......................................................................... 35
Gambar 4. 1 Struktur Organisasi Proyek Hatten Wines Bali ............................... 36 Gambar 4. 2 Contoh Aktivitas Kritis.................................................................... 41
Gambar 4. 3 Fast Tracking Pada Aktivitas Kritis ................................................ 42 Gambar 4. 4 Hasil Dari Metode Fast Track ......................................................... 42 Gambar 4. 5 Grafik Hubungan Waktu Dengan Biaya Total ................................ 49
![Page 9: PENERAPAN METODE FAST TRACK TERHADAP … AWA… · penerapan metode fast track terhadap efisiensi biaya dan efektivitas waktu pada pelaksanaan proyek konstruksi (studi kasus : proyek](https://reader035.fdokumen.com/reader035/viewer/2022071711/5a792cc87f8b9a9a188cdf8a/html5/thumbnails/9.jpg)
vi
DAFTAR TABEL
Tabel 4.1 Kegiatan kritis tanpa fast track .............................................................. 39
Tabel 4.2 Rincian biaya langsung.......................................................................... 40 Tabel 4.3 Percepatan waktu pada pelaksanaan aktivitas-aktivitas di lintasan
kritis ....................................................................................................... 42 Tabel 4.4 Kegiatan kritis baru akibat fast track I .................................................. 44 Tabel 4.5 Percepatan waktu pada pelaksanaan aktivitas-aktivitas di lintasan
kritis baru akibat fast track I .................................................................. 44 Tabel 4.6 Kegiatan kritis baru akibat fast track II ................................................. 45 Tabel 4.7 Percepatan waktu pada pelaksanaan aktivitas-aktivitas di lintasan
kritis baru akibat fast track II ................................................................ 46
Tabel 4.8 Kegiatan kritis kembali ke awal akibat fast track III ............................ 46