MRP-Kartawan.ppt

download MRP-Kartawan.ppt

of 22

Transcript of MRP-Kartawan.ppt

  • 7/30/2019 MRP-Kartawan.ppt

    1/22

    Material Requirements

    Planning

  • 7/30/2019 MRP-Kartawan.ppt

    2/22

    Materials requirements planning (MRP) is a

    means for determining the number of parts,

    components, and materials needed to produce

    a product

    MRP provides time scheduling information

    specifying when each of the materials, parts,and components should be ordered or produced

    Material Requirements PlanningDefined

  • 7/30/2019 MRP-Kartawan.ppt

    3/22

    Dependent Demand

    The demand for one item is relatedto the demand for another item

    Given a quantity for the end item,the demand for all parts andcomponents can be calculated

    In general, used whenever aschedule can be established for anitem

  • 7/30/2019 MRP-Kartawan.ppt

    4/22

    Benefits of MRP

    1. Better response to customerorders

    2. Faster response to marketchanges

    3. Improved utilization of facilities

    and labor4. Reduced inventory levels

  • 7/30/2019 MRP-Kartawan.ppt

    5/22

    Based on a master production schedule, a materialrequirements planning system:

    Creates schedules identifying the specific parts

    and materials required to produce end items

    Determines exact unit numbers needed

    Determines the dates when orders for thosematerials should be released, based on lead

    times

    Material Requirements Planning

    System

  • 7/30/2019 MRP-Kartawan.ppt

    6/22

    Elemen MRP

    1. Master production schedule

    2. Specifications or bill of material

    3. Inventory availability4. Purchase orders outstanding

    5. Lead times

    Effective use of dependent demandinventory models requires thefollowing

  • 7/30/2019 MRP-Kartawan.ppt

    7/22

    Master Production Schedule (MPS)

    Show quantity each item must beproduced each periode

    Specifies what is to be made and when

    Must be in accordance with theaggregate production plan

    As the process moves from planning toexecution, each step must be tested for

    feasibility

    The MPS is the result of the productionplanning process

  • 7/30/2019 MRP-Kartawan.ppt

    8/22

    BOM (Table Example)

    Top

    Leg

    Long Rail

    Short Rail

  • 7/30/2019 MRP-Kartawan.ppt

    9/22

    BOM (Product Structure)

    Short Rails

    (2)

    Table

    (End Item)

    Long Rails

    (2)

    Legs

    (4)

    Top

    (1)

    Leg Assembly

    (1)

  • 7/30/2019 MRP-Kartawan.ppt

    10/22

    Code

    Level Code Component

    0 Table (end-item)

    1 Leg assembly (1)

    2 Short rails (2)

    2 Long rails (2)

    2 Legs (4)

    1 Top(1)

  • 7/30/2019 MRP-Kartawan.ppt

    11/22

    MRP versus Order-Point Systems

    Attribute MRP Order Point

    Demand Dependent Independent

    Order

    philosophy

    Requirements Replenishment

    Forecast Based on master

    schedule

    Based on past

    demandControl

    concept

    Control all items ABC

    Objectives Meet manufacturing

    needs

    Meet customer

    needs

    Lot sizing Discrete EOQ

    Types of

    inventory

    Work in process and

    raw materials

    Finished goods

    and spare parts

  • 7/30/2019 MRP-Kartawan.ppt

    12/22

  • 7/30/2019 MRP-Kartawan.ppt

    13/22

    Example of MRP Logic and Product Structure Tree

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    AProduct Structure Tree for Assembly A Lead Times

    A 1 day

    B 2 days

    C 1 day

    D 3 days

    E 4 days

    F 1 day

    Total Unit Demand

    Day 10 50 A

    Given theproduct structure treefor A and the lead time and

    demand information below, provide a materials requirements

    plan that defines the number of units of each component and

    when they will be needed

  • 7/30/2019 MRP-Kartawan.ppt

    14/22

    LT = 1 day

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    Order Placement 50

    First, the number of units of A are scheduled

    backwards to allow for their lead time. So, in the

    materials requirement plan below, we have to place

    an order for 50 units of A on the 9th day to receive

    them on day 10.

  • 7/30/2019 MRP-Kartawan.ppt

    15/22

    Next, we need to start scheduling the components that make up

    A. In the case of component B we need 4 Bs for each A.

    Since we need 50 As, that means 200 Bs. And again, we back

    the schedule up for the necessary 2 days of lead time.Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    Order Placement 50

    B Required 200

    Order Placement 200

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    SparesLT = 2

    4x50=200

    16

  • 7/30/2019 MRP-Kartawan.ppt

    16/22

    Day: 1 2 3 4 5 6 7 8 9 10

    A Required 50

    LT=1 Order Placement 50B Required 200

    LT=2 Order Placement 200

    C Required 100

    LT=1 Order Placement 100

    D Required 400 300

    LT=3 Order Placement 400 300

    E Required 200LT=4 Order Placement 200

    F Required 200

    LT=1 Order Placement 200

    B(4)

    E(1)D(2)

    C(2)

    F(2)D(3)

    A

    Finally, repeating the process for all components, we have the

    final materials requirements plan:

    16

  • 7/30/2019 MRP-Kartawan.ppt

    17/22

    MRP Example

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Item On-Hand Lead Time (Weeks)

    X 50 2

    A 75 3

    B 25 1

    C 10 2

    D 20 2

    Requirements include 95 units (80 firm orders and 15 forecast) of Xin week 10

  • 7/30/2019 MRP-Kartawan.ppt

    18/22

    A(2)

    X

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes2 As for

    each X

  • 7/30/2019 MRP-Kartawan.ppt

    19/22

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    B(1)A(2)

    X

    It takes

    1 B for

    each X

  • 7/30/2019 MRP-Kartawan.ppt

    20/22

    A(2) B(1)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 3

    Cs for

    each A

  • 7/30/2019 MRP-Kartawan.ppt

    21/22

    A(2) B(1)

    C(2)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 2

    Cs for

    each B

  • 7/30/2019 MRP-Kartawan.ppt

    22/22

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Day: 1 2 3 4 5 6 7 8 9 10

    X Gross requirements 95

    LT=2 Scheduled receipts

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75

    On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receiptsProj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20

    C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20

    On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 5

    Ds for each

    B