PEMERINTAH KABUPATEN ACEH UTARA DINAS SUMBER DAYA AIR Jln. Tgk. Chik Ditiro No 19 - Telp (0645) 43763 Fax (0645) 43994 LHOKSEUMAWE - 24312 PERHITUNGAN VOLUME - PEKERJAAN TANAH - PEKERJAAN BETON PEKERJAAN PERENCANAAN TEKNIS JARINGAN IRIGASI WADUK DAN PENANGGULANGAN BANJIR SALURAN SEKUNDER BAU.8 – BP.1 KECAMATAN PAYA BAKONG – KABUPATEN ACEH UTARA TAHUN ANGGARAN 2007 Konsultan Perencana CV. TOTAL ENGINEERING CONSULTANT Jln. Kenari No. 9B – Telp./Fax. 0645 – 41538 LHOKSEUMAWE - 24312

description

sserty

Transcript of Back Up Volume

Page 1: Back Up Volume

PEMERINTAH KABUPATEN ACEH UTARA DINAS SUMBER DAYA AIR Jln. Tgk. Chik Ditiro No 19 - Telp (0645) 43763 Fax (0645) 43994 LHOKSEUMAWE - 24312

PERHITUNGAN VOLUME - PEKERJAAN TANAH - PEKERJAAN BETON

PEKERJAAN PERENCANAAN TEKNIS

JARINGAN IRIGASI WADUK DAN PENANGGULANGAN BANJIR

SALURAN SEKUNDER BAU.8 – BP.1 KECAMATAN PAYA BAKONG – KABUPATEN ACEH UTARA TAHUN ANGGARAN 2007 Konsultan Perencana CV. TOTAL ENGINEERING CONSULTANT Jln. Kenari No. 9B – Telp./Fax. 0645 – 41538 LHOKSEUMAWE - 24312

Page 2: Back Up Volume

PEKERJAAN PERENCANAAN TEKNIS

JARINGAN IRIGASI WADUK DAN PENANGGULANGAN BANJIR

SALURAN SEKUNDER BAU.8 – BP.1 KECAMATAN PAYA BAKONG – KABUPATEN ACEH UTARA

PERHITUNGAN VOLUME PEKERJAAN TANAH

TAHUN ANGGARAN 2007

Konsultan Perencana CV. TOTAL ENGINEERING CONSULTANT

Jln. Kenari No. 9B – Telp./Fax. 0645 – 41538 LHOKSEUMAWE - 24312

Page 3: Back Up Volume

PERBAIKAN DAN PEMBANGUNAN JARINGAN IRIGASI DAN PENANGGULANGAN BANJIRSALURAN SEKUNDER RUAS BAU.8 - BP.1 - D.I. ALUE UBAYKECAMATAN PAYA BAKONG - KABUPATEN ACEH UTARA

Profi Langsung Galian Timbunan Galian Timbunan

B.0 - -

BAU.8 - - - -

B.1 - - - - 45.0

B.2 45.0 - - - - 75.0

B.3 120.0 - - - - 74.4

B.4 194.4 - - - - 75.0

B.5 269.4 - - - - 78.0

B.6 347.4 - - - - 30.4

B.7 377.8 - - - - 44.0

B.8 421.8 - - - - 72.4

B.9 494.2 - - - - 50.0

B.10 544.2 0.91 0.21 22.64 5.2042.4

B.11 586.6 0.93 0.02 38.94 4.7850.0

B.12 636.6 1.28 0.31 55.27 8.1664.0

B.13 700.6 0.88 0.06 69.07 11.7150.0

B.14 750.6 1.42 0.12 57.40 4.3350.0

B.15 800.6 1.81 0.04 80.80 4.0149.6

B.16 850.2 2.41 0.08 104.86 3.1220.4

B.17 870.6 0.34 - 28.06 0.8348.0

B.18 918.6 1.41 - 41.92 - 50.0

B.19 968.6 0.74 0.17 53.82 4.1367.4

B.20 1036.0 - - 25.07 5.5773.4

B.21 1109.4 - - - - 50.0

B.22 1159.4 0.65 0.26 16.35 6.4850.0

B.23 1209.4 0.04 0.54 17.38 19.8750.0

B.24 1259.4 0.01 1.20 1.31 43.2650.0

B.25 1309.4 0.46 0.62 11.88 45.3618.6

BP.1 1328.0 - -

JUMLAH 1,328.0 624.72 166.83

PERHITUNGAN VOLUME PEKERJAAN TANAH

Volume (M3)AREA (m2)Bangunan Air / Pot Saluran

Jarak

Page 4: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.2 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

AREA (m2)

Jumlah 02

Jumlah 01

JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

Salu

ran

Suda

h D

ilinn

ing

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Salu

ran

Suda

h D

ilinn

ing

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Page 5: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.3 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.4 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.5 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

(lanjutan)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Page 6: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.6 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.7 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - -

0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.8 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

(lanjutan)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Page 7: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.9 - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 0.00 0.00 0.00 0.00

- - - - - - - - - - - - - - - - - - - - - - - - - -

0.00 0.00 0.00 0.000.00 0.00

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.10 - 10.553 0.00 6.17 - 9.412 - 9.09 0.91 0.210.59 10.456 5.45 15.63 0.97 10.378 9.14 5.02 1.50 9.312 14.07 31.76 0.48 9.465 4.56 - 3.41 9.412 31.43 30.24 - 9.412 - - 3.21 9.214 28.96 29.60 - - - - 3.21 9.014 28.96 27.84 - - - - 3.09 9.014 28.22 27.84 - - - - 3.09 9.139 28.22 13.49 - - - - 1.48 9.139 13.30 13.49 - - - - 1.48 9.014 13.30 12.07 - - - - 1.34 9.014 12.34 12.07 - - - - 1.34 9.214 14.13 0.00 - - - -

10.553 0.00 0.00 - - - -

218.39 220.20 13.70 14.11

- - 0.00 0.00 - - 0.00 0.00 0.00 0.00- - 0.00 0.00 - - 0.00 0.00

0.00 0.00 0.00 0.000.91 0.21

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.11 - 10.304 0.00 1.07 - 9.598 - 5.59 0.93 0.020.10 10.294 0.96 18.57 0.58 10.180 5.60 0.79 1.80 9.219 17.31 31.59 0.08 9.616 0.75 - 3.43 9.598 31.44 28.83 - 9.598 - - 3.00 9.175 26.96 27.563.00 8.975 26.96 25.842.88 8.975 26.20 25.842.88 9.100 26.20 11.531.27 9.100 11.37 11.531.27 8.975 11.37 10.131.13 8.975 10.36 10.131.13 9.175 11.63 0.00

10.304 0.00 0.00

200.77 202.63 6.35 6.38

- - 0.00 0.00 - - 0.00 0.00 0.00 0.00- - 0.00 0.00 - - 0.00 0.00- - 0.00 0.00 - - 0.00 0.00

0.00 0.00 0.00 0.000.93 0.02

(lanjutan)

Salu

ran

Suda

h D

ilinn

ing

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Jumlah 01

JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

Jumlah 02

AREA (m2)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Page 8: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.12 - 9.200 0.00 18.53 - 9.961 - 7.55 1.28 0.042.01 9.200 18.37 17.97 0.76 9.200 6.98 7.85 1.95 9.121 17.42 17.81 0.85 9.203 8.50 - 1.95 8.921 17.42 16.22 - 9.961 - - 1.82 8.921 18.26 16.31 - - - - 1.83 10.046 18.36 2.17 - - - - 0.22 10.046 1.93 2.17 - - - - 0.22 8.921 1.93 0.70 - - - - 0.08 8.921 0.72 0.70 - - - - 0.08 9.121 0.73 0.00 - - - - - 9.200 0.00 0.00 - - - - - - 0.00 0.00 - - - -

0.00 0.00 - - 95.14 92.59 15.47 15.40

- - - - - 9.191 0.00 16.09 0.00 0.27- - - - 1.75 10.941 17.56 12.59- - - - 1.15 10.031 10.58 0.00- - - - - 9.191 0.00 0.00

- - 0.00 0.00- -

0.00 0.00 28.14 28.691.28 0.31

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.13 - 10.687 0.00 1.85 - 8.976 - 3.65 0.04 0.060.17 10.687 1.58 18.95 0.41 9.425 3.653 2.385 1.77 9.111 15.86 25.87 0.25 8.976 2.271 - 2.84 8.944 25.48 31.41 - 8.976 - - 3.51 8.976 30.92 31.52 - - - - 3.51 8.804 30.93 29.82 - - - - 3.39 8.808 30.22 29.83 - - - - 3.39 8.922 30.22 15.98 - - - - 1.79 8.922 17.56 15.98 - - - - 1.79 9.804 3.23 16.33 - - - - 1.67 1.804 16.67 3.01 - - 1.67 10.004 17.80 0.00 - - - 10.687 0.00 0.00 - - - -

- - 220.47 220.55 5.92 6.04

- 9.425 - 0.302 - - 0.00 - 0.84 0.000.03 10.203 0.353 9.417 - - 0.00 - 0.92 11.016 10.196 17.372 - - 0.00 - 1.58 11.047 14.863 - - - 0.00 -

9.425 - -

25.41 27.09 0.00 0.000.88 0.06

(lanjutan)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

AREA (m2)

AREA (m2)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

Page 9: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.14 - 10.067 - 3.78 - 9.532 - 4.39 0.09 0.09 0.38 10.028 3.57 5.38 0.46 9.071 4.11 4.18 0.54 9.532 5.40 - 0.46 8.911 4.20 1.24 - 10.067 - - 0.14 9.104 1.32 -

- - 9.532 - - - -

8.97 9.15 9.63 9.81 - 9.000 - 0.37 8.912 - 14.22

0.04 9.000 0.45 11.17 1.60 8.966 14.36 14.31 0.72 0.02 1.24 10.982 13.78 24.06 1.60 8.996 14.22 - 2.19 11.106 19.87 1.52 - 8.912 - - 0.14 9.071 1.22 1.24 - - - - 0.14 8.871 1.23 - - 9.000 - - - - - -

36.56 37.99 28.58 28.53 8.911 - 1.22

0.14 8.911 1.22 1.22 - - - - 0.61 - 0.14 8.871 1.22 - - - - - - 8.911 - - - - - -

2.44 1.22 - -

1.42 0.12

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.15 - 10.516 - 2.71 - 8.871 - 7.74 0.71 0.04 0.26 10.881 2.63 7.16 0.87 8.871 7.98 11.43 0.66 10.188 6.62 11.80 1.29 9.156 11.38 9.16 1.16 10.055 10.52 14.63 1.00 8.831 8.87 - 1.46 9.081 12.91 21.49 8.871 - - 2.37 8.871 21.00 15.35 - - 1.73 8.871 15.13 15.35 - - 1.73 8.746 15.13 13.92 - - 1.59 8.746 14.24 13.92 - - 1.59 8.946 16.74 - - -

10.516 - - - - - -

114.91 116.34 28.24 28.33

- 9.227 - 6.56 - - - - 1.10 - 0.71 10.323 8.08 10.44 - - - - 1.01 11.358 11.36 24.76 - - - - 2.18 11.240 20.11 - - - - - - 9.227 - - - - - -

39.55 41.76 - - 1.81 0.04

(lanjutan)

Jumlah 03

AREA (m2)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Jumlah 01

Jumlah 02

JUMLAH (01 + 02+ 03)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Page 10: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.16 - 10.430 - 7.35 - 8.817 - 8.98 0.56 0.03 0.71 10.224 6.95 11.30 1.02 8.817 8.93 3.39 1.11 9.862 9.83 15.63 0.38 8.766 3.39 - 1.59 8.892 13.97 19.93 - 8.817 - - 2.24 8.817 19.76 14.64 - - - - 1.66 8.817 14.43 14.64 - - - - 1.66 8.692 14.43 13.24 - - - - 1.52 8.692 13.58 13.24 - - - - 1.52 8.918 15.88 - - - - - - 10.430 - - - - - -

- - 108.84 109.96 12.32 12.37

- 8.817 - 1.21 - 8.819 - 3.75 0.01 0.06 0.14 8.817 1.19 1.21 0.43 9.248 3.76 2.56 0.14 8.692 1.19 1.04 0.28 8.836 2.44 - 0.12 8.692 1.06 - - 8.819 - - - 8.817 - - - - - -

- - 3.44 3.46 6.20 6.31

- 9.248 - 6.95 - - - - 1.25 - 0.75 10.833 8.15 16.30 - - - - 1.51 10.833 13.92 1.30 - - - - 0.12 9.248 - - - - - -

- - 22.06 24.56 - -

- 9.248 - 6.95 - - - - 0.60 - 0.75 10.833 8.15 16.30 - - - - 1.51 10.833 13.92 - - - - - - 9.248 - - - - - - - - - - - - - -

22.06 23.26 - - 2.41 0.08

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.17 - 10.114 - 6.13 - - - - 0.34 - 0.61 9.584 5.47 10.60 - - - - 1.11 9.022 9.73 18.85 - - - - 2.09 8.795 18.65 27.32 - - - - 3.11 8.928 33.03 43.80 - - - - 4.91 10.635 43.52 33.07 - - - - 3.11 8.870 26.96 27.59 - - - - 3.11 8.670 26.96 25.78 - - - - 2.97 8.670 26.15 25.78 - - - - 2.97 8.795 26.15 12.08 - - - - 1.37 8.795 11.90 12.08 - - - - 1.37 8.670 11.90 10.82 - - - - 1.25 8.670 10.98 10.82 - - - - 1.25 8.795 12.62 - - - - - - 10.114 - - - - - -

- - 264.02 264.70 - -

- - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - 0.34 -

(lanjutan)

Jumlah 02

Jumlah 03

AREA (m2)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Jumlah 04JUMLAH (01 + 02 + 03 + 04)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

KOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Jumlah 01

CROSS

Page 11: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.18 - 10.360 - 5.05 - - - - 1.41 - 0.49 10.285 4.89 9.12 - - - - 0.89 10.047 7.99 13.41 - - - - 1.34 9.006 12.02 32.24 - - - - 3.58 9.006 32.89 33.84 - - - - 3.76 9.186 40.54 42.14 - - - - 4.59 10.788 49.19 56.95 - - - - 5.28 10.723 46.56 36.39 - - - - 3.39 8.819 29.25 29.93 - - - - 3.39 8.619 29.25 28.07 - - - - 3.26 8.619 28.48 28.07 - - - - 3.26 8.744 28.48 14.49 - - - - 1.66 8.744 14.28 14.49 - - - - 1.66 8.619 14.61 13.10 - - - - 1.52 8.619 13.40 13.10 - - - - 1.52 8.819 15.75 - - - - - - 10.360 - - - - - -

- - 367.58 370.40 - -

- - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - 1.41 -

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.19 - 10.389 - 3.13 - 8.765 - 7.01 0.70 0.17 0.30 10.289 2.97 10.04 0.80 9.566 6.98 3.60 0.98 9.856 8.72 14.55 0.38 8.728 3.30 - 1.48 8.939 12.89 31.28 - 8.765 - - 3.50 8.736 29.97 30.57 - - - - 3.50 8.565 29.97 28.90 - - - - 3.37 8.565 29.32 28.90 - - - - 3.37 8.690 29.32 15.31 - - - - 1.76 8.690 15.09 15.31 - - - - 1.76 8.565 15.09 13.91 - - - - 1.62 8.565 14.19 13.91 - - - - 1.62 8.738 16.87 - - - - - - 10.389 - - - - - -

- - 204.41 205.80 10.28 10.61

- 9.566 - 1.68 - - - - 0.05 - 0.18 9.914 1.78 5.55 - - - - 0.56 10.129 5.36 - - - - - - 9.566 - - - - - - - - - - - - - -

7.14 7.24 - - 0.74 0.17

(lanjutan)

AREA (m2)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

Jumlah 01

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Page 12: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.20 - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - -

- - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - -

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.21 - - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - -

- - - - - - - - - - - - - - - - - - - - - - - - - -

- - - - - -

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.22 - 10.430 - 0.57 - 9.229 - 6.29 0.11 0.10 0.06 10.430 0.56 4.75 0.68 8.548 5.78 5.83 0.46 10.149 4.35 9.59 0.68 8.468 5.79 3.88 0.95 9.553 9.03 8.35 0.46 8.495 4.23 - 0.87 9.553 9.12 - - 9.229 - - - 10.430 - - - - - -

- - 23.05 23.26 15.80 16.00

- 8.468 - 1.15 - 8.473 - 13.57 0.53 0.10 0.14 8.452 1.14 1.15 1.60 8.473 13.56 13.57 0.14 8.348 0.12 - 1.60 8.471 13.37 7.12 - 0.847 - - 0.84 8.351 7.13 - - - - - - 8.473 - -

- - 1.25 2.30 34.06 34.25

- 8.417 - 1.14 - 8.548 - 4.65 0.01 0.06 0.14 8.429 1.14 1.15 0.54 9.091 4.59 0.93 0.14 8.348 1.14 - 0.10 8.438 0.87 - - 8.417 - - - 8.548 - - - - - - - - - -

- - 2.28 2.29 5.46 5.58

- 9.091 - 1.45 - - - - 0.02 - 0.16 9.326 1.52 4.30 - - - - 0.46 9.553 4.19 - - - - - - 9.091 - - - - - - - - - - - - - -

5.71 5.74 - - 0.65 0.26

(lanjutan)

Jumlah 02

Jumlah 03

Jumlah 01

Jumlah 01

AREA (m2)

Jumlah 01

Jumlah 04JUMLAH (01 + 02 + 03 + 04)

AREA (m2)

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

Jumlah 02JUMLAH (01 + 02)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Page 13: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.23 - 9.851 - 2.18 - 9.369 - 8.72 0.03 0.11 0.22 9.732 2.07 4.49 0.93 8.455 8.01 4.57 0.46 9.369 4.54 - 0.54 8.607 5.06 - - 9.851 - - 9.369 - -

- - - - - -

6.61 6.66 13.07 13.29

- 9.512 - 0.29 - 8.424 - 13.48 0.01 0.43 0.03 9.512 0.29 0.97 1.60 8.424 13.29 13.48 0.10 9.476 0.95 1.93 1.60 8.307 13.29 14.43 0.20 9.308 1.94 - 1.74 8.307 14.78 14.43 - 9.51 - - 1.74 8.507 16.17 21.59 - - - - 2.54 9.308 21.10 18.06 - - - - 1.94 8.312 15.93 4.49 - - - - 0.54 8.209 4.55 - - - - - - 8.424 - -

3.18 3.20 99.10 99.95

- 8.479 - 1.16 - - - - 0.01 - 0.14 8.424 1.14 1.15 - - - - 0.14 8.307 1.16 - - - - - - 8.479 - - - - - - - - - - - - - -

2.30 2.32 - - 0.04 0.54

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.24 - 8.367 - 1.15 - 9.959 - 3.90 0.01 0.16 0.14 8.336 1.13 1.14 0.39 9.959 3.59 11.62 0.14 8.254 1.15 - 1.17 9.164 11.62 - - 8.367 - - - 9.959 - - - - - - - - - - - - - - - - - - - - - - - - - -

- - 2.28 2.29 15.21 15.53

- 8.324 - 1.14 - 9.164 - 6.51 0.01 0.03 0.14 8.334 1.13 1.14 0.71 8.454 5.94 6.00 0.14 8.254 1.14 - 0.71 8.367 6.51 - - 8.324 - - - 9.164 - - - - - - - - - -

- - 2.27 2.28 12.45 12.51

- - - - - 8.367 - 13.39 - 0.04 - - - - 1.60 8.324 13.26 9.04 - - - - 1.09 8.288 9.09 - - - - - - 8.367 - - - - - - - - - -

- - - - 22.35 22.43

- - - - - 8.336 - 12.79 - 0.97 - - - - 1.53 9.989 15.32 24.28 - - - - 2.43 9.989 22.63 12.48 - - - - 1.25 9.308 10.48 7.90 - - - - 0.85 8.394 7.08 - - - - - - 8.336 - -

- - - - 55.51 57.45

0.01 1.20

AREA (m2)

Jumlah 01

Jumlah 04JUMLAH (01 + 02 + 03 + 04)

Jumlah 01

Jumlah 02

Jumlah 02

Jumlah 03

Jumlah 03JUMLAH (01 + 02 + 03)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

(lanjutan)

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN

Page 14: Back Up Volume

Perhitungan Volume Pekerjaan Tanah Rehabilitasi Saluran Sekunder Ruas BAU.8 - BP.1 D.I. Alue Ubay Kab. Aceh Utara

X Y XY YX X Y XY YX GALIAN TIMBUNAN

B.25 - 9.954 - 6.83 - 9.004 - 5.44 0.19 0.18 0.69 9.645 6.18 8.59 0.60 8.400 4.91 5.07 0.89 9.004 8.87 - 0.60 8.137 5.07 1.59 - 9.954 - - 0.20 8.393 1.76 - - - - - - 9.004 - -

- - 15.05 15.42 11.74 12.10

- 8.328 - 1.14 - 8.393 - 15.73 0.01 0.29 0.14 8.306 1.12 1.14 1.87 8.393 15.43 15.73 0.14 8.200 1.14 - 1.87 8.236 15.25 9.81 - 8.328 - - 1.19 8.139 10.00 - - - - - - 8.393 - -

2.26 2.28 40.68 41.27 - 8.216 - 1.13 - 8.236 - 5.25 0.00 0.15

0.14 8.236 1.12 1.13 0.64 9.038 5.29 3.77 0.14 8.200 1.13 - 0.42 8.295 3.43 - - 8.216 - - - 8.236 - - - - - - - - - -

2.25 2.25 8.73 9.02

- 9.038 - 1.62 - - - - 0.27 - 0.18 9.638 1.80 6.54 - - - - 0.68 10.045 6.77 9.34 - - - - 0.93 9.968 8.41 - - - - - - 9.038 - - - - - -

16.97 17.50 - - 0.46 0.62

(lanjutan)

Jumlah 01

Jumlah 04JUMLAH (01 + 02 + 03 + 04)

Jumlah 03

Jumlah 02

CROSSKOORDINAT GALIAN KOORDINAT TIMBUNAN AREA (m2)

Page 15: Back Up Volume

PEKERJAAN PERENCANAAN TEKNIS

JARINGAN IRIGASI WADUK DAN PENANGGULANGAN BANJIR

SALURAN SEKUNDER BAU.8 – BP.1 KECAMATAN PAYA BAKONG – KABUPATEN ACEH UTARA

PERHITUNGAN VOLUME PEKERJAAN BETON

TAHUN ANGGARAN 2007

Konsultan Perencana CV. TOTAL ENGINEERING CONSULTANT

Jln. Kenari No. 9B – Telp./Fax. 0645 – 41538 LHOKSEUMAWE - 24312

Page 16: Back Up Volume

PERBAIKAN DAN PEMBANGUNANJARINGAN IRIGASI DAN PENANGGULANGAN BANJIR

SALURAN SEKUNDER RUAS BAU.8 - BP.1KECAMATAN PAYA BAKONG - KABUPATEN ACEH UTARA

BACK UP DATA

II.4 Beton Bertulang K.175 Linning Saluran (dasar gambar) = 692,00 M

2 { x 0,10 x 692 } = 28.37 M3

2 { x 0,10 x 692 } = 87.88 M3

116.25 M3

II.5 Beton Cor 1 : 3 : 5 Lantai Saluran

Panjang Saluran = 692 - ( 174 x 0,14 ) ~> Balok Diafragma Setiap 4 m

= 667.64 m

Volume = 0,15 x 1,60 x 667,64

= 160.23 m3

II.6 Beton Bertulang K.175 diafragma / setiap 4 meter = 14/28

Jumlah Balok Diafragma = + 1 = 174 Buah

Volume = { 0,14 x 0,28 x 1,60 } x 174

= 10.91 m3

Beton Bertulang K.175 Balok 14/28 Pada Linning

( 0,14 x 0,28 x 692 ) x 2 = 54.25 m3

Total Volume = 10,91 m3 + 54,25 m3

= 65.16 m3

0,20 + 0,21 2

1,32 + 1,22 2

692 m 2 m