ANALISA HARGA SATUAN
Nama Perusahaan : PT. ADI KARYAalamat proyek penaggung jawab
Halaman
No. URAIAN PEKERJAANBAHAN UPAH
unit harga/satuan faktor jumlah biaya waktu/satuan upah/jam Overhead biaya upah biaya upah+
(Rp) overhead bahan/satuan (jam) (Rp.) (7)x(8) satuan bahan
(4)x(5) (Rp.) (9)x(10) (6)+(11)
(Rp) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 11 12
I Pemasangan MVMDP
1 Pemasangan kubikel incoming :a.Instalasi arester Buah ### 1.5 30,000,000 2 50,000 100,000 1.5 150,000 30,150,000
b Pemasangan Pengaman CB Buah ### 1.5 22,500,000 1 35,000 35,000 1.5 52,500 22,552,500
c.Penarikan Kabel dari sumber PLN Meter ### 1.5 21,000,000 3 20,000 60,000 1.5 90,000 21,090,000
2 Pemasangan kubikel out going a.Instalasi arester Meter ### 1.5 30,000,000 2 50,000 100,000 1.5 150,000 30,150,000
b Pemasangan Pengaman LBS Buah ### 1.5 22,500,000 7 35,000 245,000 1.5 367,500 22,867,500
c.Penarikan Kabel dari Busbar ke Trafo Daya Meter ### 1.5 22,500,000 5 20,000 100,000 1.5 150,000 22,650,000
3 Pemasangan kubikel metering 1.5
a.Instalasi PT ( Power Transformer ) Meter 2,250,000.00 1.5 3,375,000 7 35,000 245,000 1.5 367,500 3,742,500
b.Instalasi AMF ( Automatic Main Failure ) Buah ### 1.5 29,250,000 6 25,000 150,000 1.5 225,000 29,475,000
4 Pemasangan kabel MVMDP ke trafo Buah ### 1.5 21,000,000 5 30,000 150,000 1.5 225,000 21,225,000
II Pemasangan Instalasi Trafo1 Penarikan Kabel dari Sumber PLN Meter ### 1.5 24,000,000 5.00 20,000 100,000 1.5 150,000 24,150,000
2 Pemasangan kabel trafo ke MVMDP Meter ### 1.5 22,500,000 6.00 20,000 120,000 1.5 180,000 22,680,000
3 Pemasangan kabel trafo ke LVMDP Meter ### 1.5 22,500,000 7 20,000 140,000 1.5 210,000 22,710,000
1.5
III Pemasangan LVMDP
Nama Proyek: Gardu Distribusi BIOTEK LIPI CIBINONG
1 Pemasangan kubikel LVMDP 6 set Meter ### 1.5 22,500,000 5 35,000 175,000 1.5 262,500 22,762,500
2 Pemasangan kabel trafo ke LVMDP Meter ### 1.5 18,000,000 7 30,000 210,000 1.5 315,000 18,315,000
3 Penarikan Kabel dari Sumber PLN dan Genset Meter ### 1.5 18,000,000 6 20,000 120,000 1.5 180,000 18,180,000
4 Intalasi dan Penarikan Kabel :
a. Ged.Laboratorium1 Meter ### 1.5 15,000,000 4 30,000 120,000 1.5 180,000 15,180,000
b. Ged.Laboratorium 2 Meter ### 1.5 15,000,000 5 30,000 150,000 1.5 225,000 15,225,000
c. Ged.Perpustakaan dan pertemuan Meter ### 1.5 15,000,000 7 30,000 210,000 1.5 315,000 15,315,000
d. Ged.Kantor Pusat Administrasi Meter 8,500,000.00 1.5 12,750,000 6 30,000 180,000 1.5 270,000 13,020,000
e. Ged.Lab. Dan Kolam Algae Meter 8,500,000.00 1.5 12,750,000 7 30,000 210,000 1.5 315,000 13,065,000
f. Ged. Guess House Meter 6,000,000.00 1.5 9,000,000 6 30,000 180,000 1.5 270,000 9,270,000
a. Ged.Penunjang lainnya Meter 5,000,000.00 1.5 7,500,000 5 35,000 175,000 1.5 262,500 7,762,500
VI Pemasangan genset1 Penarikan Kabel ke Sumber AMF Meter ### 1.5 21,000,000 5.00 25,000 125,000 1.5 187,500 21,187,500
2 Penarikan Kabel Mechanical Interlock Motor Meter ### 1.5 22,500,000 7.00 30,000 210,000 1.5 315,000 22,815,000
3 Pemasangan kabel genset ke LVMDP Meter ### 1.5 19,500,000 5.00 25,000 125,000 1.5 187,500 19,687,500
4 Pembuatan Kontrol Automatis Meter ### 1.5 15,000,000 6.00 75,000 450,000 1.5 675,000 15,675,000
V Pemasangan AMF1 Pemasangan Panel AMF Meter ### 1.5 15,000,000 5 35,000 175,000 1.5 262,500 15,262,500
2 Penarikan kabel ke Power Transformer ( PT ) Meter ### 1.5 22,500,000 5 35,000 175,000 1.5 262,500 22,762,500
VI Pemasangan UPS
1 Penarikan Kabel ke Sumber PLN Meter 8,500,000.00 1.5 12,750,000 6.00 30,000 180,000 1.5 270,000 13,020,000
2 Pemasangan Mechanical Interlock Meter 7,000,000.00 1.5 10,500,000 7.00 45,000 315,000 1.5 472,500 10,972,500
3 Pembuatan Kontrol Automatis Buah 7,000,000.00 1.5 10,500,000 7.00 75,000 525,000 1.5 787,500 11,287,500
4 Penarikan Kabel ke UPT Komputer Buah 8,000,000.00 1.5 12,000,000 6 30,000 180,000 1.5 270,000 12,270,000
TOTAL ### ###
Total = 586,477,500Tax 10 %= 58,647,750.00
645,125,250Profit 20 % 129,025,050.00
774,150,300.00
ENGINEERING ESTIMATE
No. URAIAN PEKERJAAN UNIT VOLUME KET
I Pemasangan MVMDP
1 Pemasangan kubikel incoming :a.Instalasi arester Buah 1 20,000,000.00 20,000,000
b Pemasangan Pengaman CB Buah 1 15,000,000.00 15,000,000
c.Penarikan Kabel dari sumber PLN Meter 20 14,000,000.00 280,000,000
2 Pemasangan kubikel out going a.Instalasi arester Buah 1 20,000,000.00 20,000,000
b Pemasangan Pengaman LBS Buah 1 15,000,000.00 15,000,000
c.Penarikan Kabel dari Busbar ke Trafo Daya Meter 10 15,000,000.00 150,000,000
3 Pemasangan kubikel metering a.Instalasi PT ( Power Transformer ) Buah 1 2,250,000.00 2,250,000
b.Instalasi AMF ( Automatic Main Failure ) Buah 1 19,500,000.00 19,500,000
4 Pemasangan kabel MVMDP ke trafo Meter 20 14,000,000.00 280,000,000
II Pemasangan Instalasi Trafo1 Penarikan Kabel dari Sumber PLN Meter 20 16,000,000.00 320,000,000
2 Pemasangan kabel trafo ke MVMDP Meter 10 15,000,000.00 150,000,000
3 Pemasangan kabel trafo ke LVMDP Meter 10 15,000,000.00 150,000,000
III Pemasangan LVMDP
1 Pemasangan kubikel LVMDP 6 set Buah 2 15,000,000.00 30,000,000
2 Pemasangan kabel trafo ke LVMDP Meter 10 12,000,000.00 120,000,000
3 Penarikan Kabel dari Sumber PLN dan Genset Meter 20 12,000,000.00 240,000,000
4 Intalasi dan Penarikan Kabel :
a. Ged.Lab.1 Meter 30 10,000,000.00 300,000,000
b. Ged.Lab 2 Meter 30 10,000,000.00 300,000,000
c. Ged.Perpustakaan dan Pertemuan Meter 30 10,000,000.00 300,000,000
d. Ged.Kantor Pusat Administrasi Meter 20 8,500,000.00 170,000,000
e. Ged.Lab dan Kolam Algae Meter 20 8,500,000.00 170,000,000
f. Ged.GuessHouse Meter 20 6,000,000.00 120,000,000
l. G. Penunjang Lainnya Meter 10 5,000,000.00 50,000,000
VI Pemasangan genset1 Penarikan Kabel ke Sumber AMF Meter 45 14,000,000.00 630,000,000
2 Penarikan Kabel Mechanical Interlock Motor Meter 10 15,000,000.00 150,000,000
3 Pemasangan kabel genset ke LVMDP Meter 10 13,000,000.00 130,000,000
4 Pembuatan Kontrol Automatis Buah 1 10,000,000.00 10,000,000
V Pemasangan AMF1 Pemasngan Panel AMF Buah 1 10,000,000.00 10,000,000
2 Penarikan kabel ke Power Transformer ( PT ) Meter 5 15,000,000.00 50,000,000
HARGA SATUAN (Rp)
JUMLAH HARGA (Rp)
VI Pemasangan UPS
1 Penarikan Kabel ke Sumber PLN Meter 20 8,500,000.00 170,000,000
2 Pemasangan Mechanical Interlock Buah 8 7,000,000.00 68,000,000
3 Pembuatan Kontrol Automatis Buah 1 7,000,000.00 7,000,000
4 Penarikan Kabel ke LVMDP Meter 30 8,000,000.00 210,000,000
TOTAL 4,656,750,000