Analisa Hs Dki
-
Upload
qw1llyahoocom -
Category
Documents
-
view
218 -
download
0
Transcript of Analisa Hs Dki
-
7/26/2019 Analisa Hs Dki
1/5
ANALISA HARGA SATUAN
PEKERJAAN PEMASANGAN INSTALASI GARDU
Belum termasuk resiko,over head,keuntungan 10 % dan PPN 10 %
2004
HARGA BIAYA JUMLAH
NO JENIS PEKERJAAN SATUAN ( Rupiah ) DIBULATKAN
( Rupiah ) ( Rupiah )
1 2 3 4 5
1a PEKERJAAN PEMASANGAN INSTALASI GARDU
1.1 Pemasangan kubikel LBS/PT/B1
- Tenaga Ahli 0.38 Hari 123,500 46,312.50
2 Tukang 40,500 81,000.00
2 Pekerja 32,250 64,500.00
- Pengadaan/ 4 Buah 3,738 14,952.00
206,764.50 206,760.00
1.2 Pemasangan Kubikel PGDB/PGDT
- Tenaga Ahli 0.50 Hari 123,500 61,750.00
4 Tukang 40,500 162,000.00
2 Pekerja 32,250 64,500.00- Pengadaan/ 3 Buah 3,738 11,214.00
299,464.00 299,460.00
1.3 Pemasangan SACO
- Tenaga Ahli 0.50 Hari 123,500 61,750.00
4 Tukang 40,500 162,000.00
2 Pekerja 32,250 64,500.00
- Pengadaan/ 4 Buah 3,738 14,952.00
303,202.00 303,200.00
1.4 Pemasangan RMU.3 dan 4 Terminal(Panel Kontrol UPD)
- Tenaga Ahli 0.50 Hari 123,500 61,750.00
4 Tukang 40,500 162,000.00
1 Pekerja 32,250 32,250.00- Pengadaan/ 4 Buah 3,738 14,952.00
270,952.00 270,950.00
1.5 Pemasangan RMU ( LBS,LBS,PB) ( Beton,Kiosk,Portal)
- Tenaga Ahli 0.50 Hari 123,500 61,750.00
4 Tukang 40,500 162,000.00
2 Pekerja 32,250 64,500.00
- Pengadaan/ 4 Buah 3,738 14,952.00
303,202.00 303,200.00
1.6 Pemasangan ( Peletakan ke posisi sebenarnya ) Trafo 100 kVA s/d 315 KVA
- Tenaga Ahli 0.38 Hari 123,500 46,312.50
2 Tukang 40,500 81,000.00
3 Pekerja 32,250 96,750.00
224,062.50 224,060.00
1.7 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 400 kVA s/d 630 kVA
- Tenaga Ahli 0.38 Hari 123,500 46,312.50
2 Tukang 40,500 81,000.00
5 Pekerja 32,250 161,250.00
288,562.50 288,560.00
1.8 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 1.000 kVA s/d 1.250 KVA
- Tenaga Ahli 0.38 Hari 123,500 46,312.50
-
7/26/2019 Analisa Hs Dki
2/5
2 Tukang 40,500 81,000.00
8 Pekerja 32,250 258,000.00
385,312.50 385,310.00
1.9 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 1.600 kVA s/d 2.000 KVA
- Tenaga Ahli 0.38 Hari 123,500 46,312.50
2 Tukang 40,500 81,000.00
12 Pekerja 32,250 387,000.00
514,312.50 514,310.00
1.10 Bracket (Kabel Tray) dan Grounding
- Tenaga Ahli 0.25 Hari 123,500 30,875.00
2 Tukang 40,500 81,000.00
32,250 111,875.00 111,870.00
1.11 Rak TR 4 Jurusan
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
2 Tukang 40,500 81,000.00
32,250 96,437.50 96,430.00
1.12 Rak TR 6 & 8 Jurusan
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
2 Tukang 40,500 81,000.001 Pekerja 32,250 32,250.00
128,687.50 128,680.00
1.13 Pemasangan LBS untuk Gardu Beton Open Type
- Tenaga Ahli 0.38 Hari 123,500 46,312.50
2 Tukang 40,500 81,000.00
- Pengadaan/ 4 Pekerja 32,250 129,000.00
256,312.50 256,310.00
1.14 L.V.C.B Outdoor untuk gardu CANTOL
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
2 Tukang 40,500 81,000.00
96,437.50 96,430.00
1.15 L.V.S.B Outdoor untuk gardu Portal- Tenaga Ahli 0.13 Hari 123,500 15,437.50
2 Tukang 40,500 81,000.00
3 Pekerja 32,250 96,750.00
193,187.50 193,180.00
1.16 Single Core TM 3 x ( 1x 25 mm2 ) di MV Cell
- Tenaga Ahli 0.67 Hari 123,500 82,333.33
0.67 Tukang 40,500 27,000.00
0.33 Pekerja 32,250 10,750.00
120,083.33 120,080.00
1.17 Single Core TM 3 x ( 1x 25 mm2 ) di Trafo
- Tenaga Ahli 0.67 Hari 123,500 82,333.33
0.67 Tukang 40,500 27,000.00
0.33 Pekerja 32,250 10,750.00
120,083.33 120,080.00
1.18 Single Core TR 7 x ( 1x 240 mm2 ) di Trafo
- Tenaga Ahli 0.25 Hari 123,500 30,875.00
0.13 Tukang 40,500 5,062.50
0.13 Pekerja 32,250 4,031.25
39,968.75 39,960.00
1.19 Single Core TR 7 x ( 1x 240 mm2 ) di TR
-
7/26/2019 Analisa Hs Dki
3/5
- Tenaga Ahli 0.25 Hari 123,500 30,875.00
0.13 Tukang 40,500 5,062.50
0.13 Pekerja 32,250 4,031.25
39,968.75 39,960.00
1.20 Pengadaan Penyangga Kabel TM 20 kV
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
1 Tukang 40,500 40,500.00
2 Pekerja 32,250 64,500.00
- Pengad/Pe 1 Meter 15,600 15,600.00
- Pengad/Pe 1 Buah 1,950 1,950.00
137,987.50 137,980.00
1.21 IndikatormGangguan Tanah/GFD
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
2 Tukang 40,500 81,000.00
96,437.50 96,430.00
1.22 Pemasangan Instalasi Heater Kubikel
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
1 Tukang 40,500 40,500.00
55,937.50 55,930.001.23 Pengadaan K 1 Meter 2,210 2,210.00 2,210.00
1.24 Pembersihan 2 Pekerja 26,250 52,500.00 52,500.00
1.25 Bantuan Tena 2 Tukang 37,500 75,000.00
Pengopersian 2 Pekerja 26,250 52,500.00
127,500.00 127,500.00
1.b PEKERJAAN PEMBONGKARAN INSTALASI GARDU
1 No: 1 s/d 19 sama dengan Pekerjaan Pemasangan
2 Pembongkaran Terminal Ind 1 Pekerja 26,250 26,250 26,250.00
II PEMASANGAN APP TYPE KHUSUS IB,IC DAN IIF
2.1 Dengan Pondasi
- Galian tanah 0.13 m3 20,386 2,650.18- Pasang Bat 0.26 m3 201,578 52,410.28
- Pasang Ang 4 Buah 3,738 14,952.00
- Pasang Fish 4 Buah 1,430 5,720.00
- Plesteran 1 2.27 m2 10,777 24,463.79
- Acian Beton 2.27 m2 4,420 10,033.40
- Jasa Pelaks 0.5 Hari 123,500 61,750.00
3 Tukang 40,500 121,500.00
- Jasa Pelaks 0.13 Hari 123,500 16,055.00
2 Tukang 40,500 81,000.00
390,534.65 390,530.00
2.2 Dengan Strain Hook
- Pasang Stra 4 Buah 6,500 26,000.00
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
1 Tukang 40,500 40,500.00
2 Pekerja 32,250 64,500.00
146,437.50 146,430.00
III PEKERJAAN PEMELIHARAAN INSTALASI GARDU
3.1 Kubikel TM
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
- Tukang 2 Tukang 40,500 81,000.00
-
7/26/2019 Analisa Hs Dki
4/5
- Majun 0.5 Kg 8,000 4,000.00
- YC.8513 ( M 0.5 Liter 75,000 37,500.00
- Pasline Puti 0.25 Kg 87,500 21,875.00
159,812.50 159,810.00
3.2 Kubikel pengukuran ( PGDB )
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
- Tukang 2 Tukang 40,500 81,000.00
- Majun 0.5 Kg 8,000 4,000.00
- YC.8513 ( M 0.5 Liter 75,000 37,500.00
- Pasline Puti 0.25 Kg 87,500 21,875.00
159,812.50 159,810.00
3.3 Trafo Distribusi
- Tenaga Ahli 0.13 Hari 123,500 15,437.50
- Tukang 2 Tukang 40,500 81,000.00
- Majun 0.5 Kg 8,000 4,000.00
- YC.8513 ( M 0.5 Liter 75,000 37,500.00
137,937.50 137,930.00
3.4 Rak TR
- Tenaga Ahli 0.13 Hari 123,500 15,437.50- Tukang 1 Tukang 40,500 40,500.00
- Majun 0.25 Kg 8,000 2,000.00
- YC.8513 ( M 0.5 Liter 75,000 37,500.00
- Pasline Puti 0.25 Kg 87,500 21,875.00
117,312.50 117,310.00
3.5 Detektor gangguan tanah/GFD
- Tukang 1 Tukang 40,500 40,500.00
- YC.8513 ( M 0.5 Kg 75,000 37,500.00
78,000.00 78,000.00
3.6 Pembersihan Ruangan Gardu
- Alat Vacum 1 Buah 13,000 13,000.00
- Bahan Baka 1 Liter 2,600 2,600.00
- Instalator 1 Tukang 40,500 40,500.00
56,100.00 56,100.00
IV PEKERJAAN LAIN - LAIN
4.1 Pemasangan Gardu Besi/Kios berikut Pondasi
a Pekerjaan Pe 1 Lokasi 130,000 130,000.00
b Pasang Boupl 17 Meter 8,398 142,766.00
c Galian Tanah 9 m3 20,386 183,474.00
d Urugan Pasir 0.5 m3 49,842 24,921.00
e Pondasi Beto 4.6 m3 689,193 3,170,287.80
f Pantek Pipa 4 Batang 130,000 520,000.00
g Plesteran 1:2 35 m2 10,738 375,830.00
h Acian Beton 35 m2 4,420 154,700.00
i Pasang Arde 10 Kg 2,925 29,250.00
j Beton Lantai 6 m2 23,375 140,250.00
k Pekerjaan Stel Kios
- Pelaksana 1 Ten.Ahl.Md 123,500 123,500.00
2 Tukang 40,500 81,000.00
3 Pekerja 32,250 96,750.00
l Pembuangan 9 M3 21,125 190,125.00
-
7/26/2019 Analisa Hs Dki
5/5
Angkutan Truk dengan Kap.3.m3 5,362,853.80 5,362,850.00
2 Pemasangan Gardu Kios Compact berikut Pondasi
a Pekerjaan Pe 1 Lokasi 130,000 130,000.00
b Pasang Boupl 9 Meter 8,398 75,582.00
c Galian Tanah 4.5 m3 7,878 35,451.00
d Urugan Pasir 0.25 m3 49,842 12,460.50
e Pondasi Beto 2.3 m3 689,193 1,585,143.90
f Pantek Pipa 4 Batang 130,000 520,000.00
g Plesteran 1:2 18 m2 10,738 193,284.00
h Acian Beton 18 m2 4,420 79,560.00
i Pasang Arde 10 Kg 2,925 29,250.00
j Beton Lantai 3 m2 23,375 70,125.00
k Pekerjaan Stel Kios
- Pelaksana 1 Ten.Ahl.Md 123,500 123,500.00
2 Tukang 40,500 81,000.00
6 Pekerja 32,250 193,500.00
l Sewa Mobil C 0.88 Hari 112,500 98,437.50
m Pembuangan 4.5 Rit 0.00
Angkutan Truk dengan Kap.3 m3 3,227,293.90 3,227,290.00
3 Pengadaan Gardu Susun GRC 400 KVA Kososng (1,5x2,5x3,9)m 39,000,000.00
dan saluran kabel GRC 630 KVA Kosong (1,5x2,5x4,2) 650,000.00
4 Pengadaan Gardu Susun GRC 400 KVA Kososng (1,5x2,5x3,9)m 43,225,000.00
dan saluran kabel GRC 630 KVA Kosong (1,5x2,5x4,2) 650,000.00