Bahan - 1

LAMPIRAN : PERATURAN WALIKOTA YOGYAKARTA

NOMOR : . . . . . . . . TAHUN . . . . . . . . .

TANGGAL : . . . . . . . . . . . . . . . . . . . . . .

DAFTAR SATUAN UPAH DAN BAHAN DI LINGKUNGAN PEMERINTAH KOTA YOGYAKARTA

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

TENAGA

1 Tukang kayu hari 47,500.00 2 Kepala tukang kayu hari 50,000.00 3 Tukang batu hari 42,500.00 4 Kepala tukang batu hari 45,000.00 5 Tukang besi hari 45,000.00 6 Kepala tukang besi hari 47,500.00 7 Tukang las hari 45,000.00 8 Kepala tukang las hari 47,500.00 9 Tukang cat hari 42,500.00 10 Kepala tukang cat hari 45,000.00 11 Tukang plitur hari 45,000.00 12 Kepala tukang plitur hari 47,500.00 13 Tukang bor hari 42,500.00 14 Kepala tukang bor hari 45,000.00 15 Tukang listrik hari 45,000.00 16 Tukanng pipa ledeng hari 42,500.00 17 Tukang kapur hari 40,000.00 18 Pekerja hari 36,000.00 19 Mandor hari 40,000.00 20 Pengawas hari 50,000.00 21 Ahli ukur hari 125,000.00 22 Asisten ahli ukur hari 95,000.00 23 Sopir hari 40,000.00 24 Masinis hari 37,500.00 25 Kernet / pembantu sopir hari 36,000.00 26 Mekanik terlatih hari 45,000.00 27 Operator tak terlatih hari 35,000.00 28 Operator terlatih hari 45,000.00 29 Operator semi terlatih hari 40,000.00 30 Butuh terlatih hari 40,000.00 31 Buruh semi terlatih hari 37,500.00 32 Buruh tak terlatih hari 36,000.00 33 Tukang gali hari 45,000.00 34 Juru godog aspal hari 36,000.00 35 Penjaga hari 36,000.00 36 Penyemprot hari 35,000.00 37 Tukang Sungging hari 50,000.00 38 Kepala Tukang Sungging hari 55,000.00 39 Tukang Ukir hari 50,000.00 40 Kepala Tukang Ukir hari 55,000.00 41 Tukang Prodo hari 50,000.00 42 Kepala Tukang Prodo hari 55,000.00 43 Tukang Gambar hari 50,000.00 44 Tukang Grouting hari 45,000.00 45 Kepala tukang Grouting hari 50,000.00 46 Operator mesin sondir hari 90,000.00 47 Analis test sondir hari 150,000.00

Page 2: AHS 2008-Kota.xlsx

Bahan - 2

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

CAT 1 Cat kayu se kualitas Patna kg 11,500.00 2 Cat kayu se kualitas Emco biasa kg 29,500.00 3 Cat kayu se kualitas Emco Bintang kg 44,250.00 4 Cat kayu se kualitas Par kg 29,000.00 5 Cat besi se kualitas Patna kg 11,500.00 6 Cat besi se kualitas Emco biasa kg 29,500.00 7 Cat besi se kualitas Emco Bintang kg 50,100.00 8 Cat kayu se kualitas Avian kg 25,000.00 9 Cat tembok/cat semen Maxilite kg 9,000.00 10 Cat tembok/cat emulsi dasar minyak Express kg 10,000.00 11 Cat temboksek. Dulux dalam kg 40,500.00 12 Cat temboksek. Dulux luar kg 63,800.00 13 Cat ICI kg 45,700.00 14 Cat tembok se kualitas Catylac kg 12,000.00 15 Cat tembok se kualitas Decolith kg 10,000.00 16 Cat tembok se kualitas Mowilek dalam kg 35,000.00 17 Cat tembok se kualitas Mowilex luar kg 53,000.00 18 Cat Sintex kg 9,000.00 19 Cat dasar meni besi type A (cepat kering) Jago kg 15,000.00 20 Cat dasar meni besi type A (cepat kering) Par kg 25,000.00 21 Cat dasar meni kayu Jago kg 15,000.00 22 Cat duco kg 70,000.00 23 Cat genteng air ICI weathershield kg 45,000.00 24 Cat dasar undercoat / alkali resisiting primer kg 45,000.00 25 Dempul kayu typa A (putih) Jago kg 10,000.00 26 Dempul lilin / kayu bj 9,000.00 27 Plamur Fuji kg 18,000.00 28 Plamur kayu Jago kg 20,000.00 29 Plamur tembok acrilyc kg 24,000.00 30 Plamur jenis sirlak kuning ltr 20,100.00 31 Sirlak putih batangan kg 74,700.00 32 Sirlak kuning serbuk kg 74,700.00 33 Oker kuning kg 17,000.00 34 Oker hitam kg 17,000.00 35 Oker pewarna politur merah / coklat bks 2,500.00 36 Kalkarium kg 8,500.00 37 Politur jadi ltr 40,000.00 38 Teak oil Fuji ltr 35,000.00 39 Pernis ltr 40,000.00 40 Glass bit ltr 30,000.00 41 Thermo plastik / cat marka kg 56,250.00 42 Cat rettar kg 56,250.00 43 Terpentin ltr 27,000.00 44 Minyak cat ltr 14,000.00 45 Thinner ltr 14,000.00 46 Spiritus ltr 15,000.00 47 Batu kambang kg 22,000.00 48 Kuas roll bh 15,000.00 49 Kuas ukuran 3,5" bh 9,100.00 50 Kuas ukuran 2,5" bh 6,000.00 51 Kuas ukuran kecil 1" bh 4,000.00 52 Soda api kg 25,000.00 53 Sabun deterjen kg 20,000.00 54 Amplas lbr 3,500.00

55 Prodo Mas 4,000,000.00 56 Kertas 100 x 100 cm lbr 5,000.00 57 Karbon lbr 5,000.00

m2

Page 3: AHS 2008-Kota.xlsx

Bahan - 3

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

BETON DAN BARANG DARI BETON BATAKO

1 Batako pejal ( 40x20x10 ) bj 3,500.00 Batako beton berlubang ( 40x20x15 ) bh 3,500.00

2 Panel beton pracetak lbr 350,000.00 3 Kolom beton pracetak btg 500,000.00

PIPA 1 Pipa beton 20 x 30 Panjang 1 m m 50,000.00 2 Pipa beton tanpa tulangan dia. 20 cm panjang 1 m m 45,000.00 3 Pipa beton tanpa tulangan dia. 30 cm panjang 1 m m 50,000.00 4 Pipa beton tanpa tulangan dia. 60 cm panjang 0,5 m m 40,000.00 5 Pipa beton tanpa tulangan dia. 80 cm panjang 0,5 m m 50,000.00 6 Pipa beton tanpa tulangan 1/2 dia. 20 cm m 30,000.00

BUIS BETON / KERB

1 Buis beton 1/2 D 20 cm 30,000.00

2 Buis beton 1/2 D 25 cm 35,000.00

3 Buis beton bulat dia. 15 cm 40,000.00

4 Buis beton bulat dia. 20 cm 45,000.00

5 Buis beton bulat dia. 30 cm 50,000.00

6 Buis beton bulat dia. 40 cm 60,000.00 7 Buis beton bulat dia. 50 cm P=0,50 m bh 30,000.00 8 Buis beton bulat dia. 80 cm P=0,5 m bh 45,000.00

9 Buis beton oval dia. 20/30 panjang 1 m 50,000.00

10 Buis beton oval dia. 25/37,5 panjang 1 m 55,000.00

11 Buis beton oval dia. 30/40, 30/45 panjang 1 m 60,000.00

12 Buis beton oval dia. 35/52,5 panjang 1 m 65,000.00

13 Buis beton oval dia. 40/60 panjang 1 m 70,000.00 14 Buis beton oval dia. 50/75 panjang 0,5 m bh 50,000.00 15 Buis beton oval dia. 60/90 panjang 0,5 m bh 60,000.00 16 Buis beton oval dia. 70/105 panjang 0,5 m bh 65,000.00 17 Buis beton oval dia. 80/120 panjang 0,5 m bh 70,000.00

PERALATAN SANITASI BAK MANDI

1 Bak mandi teraso uk. 50x50x50 cm bh 200,000.00 2 Bak mandi teraso uk. 60x60x60 cm bh 250,000.00 3 Bak mandi teraso uk. 90x80x80 cm bh 300,000.00 4 Bak mandi (bathtube) dengan shower lux bh 4,500,000.00 5 Bak mandi (bathtube) standar bh 3,500,000.00 6 Bak mandi fiber glass 0,30 m3 bh 350,000.00 7 Bak mandi fiber glass 0,50 m3 bh 1,100,000.00

KLOSET 1 Kloset jongkok porselin type CE7 standar bh 300,000.00 2 Kloset jongkok porselin type CE8 standar bh 300,000.00 3 Kloset jongkok putih INA bh 200,000.00 4 Kloset jongkok warna INA bh 225,000.00 5 Kloset duduk standar / porselin ( dengan tangki KIA standart) "Toto" bh 1,750,000.00 6 Kloset duduk porselin lux ( dengan tangki "Toto" ) bh 2,000,000.00 7 Kloset duduk putih dengan tangki "Toto" set 2,000,000.00 8 Kloset duduk warna dengan tangki "Toto" set 2,150,000.00 9 Kloset duduk putih dengan tangki "KIA" set 1,950,000.00 10 Kloset duduk warna dengan tangki "KIA" set 2,000,000.00 11 Kloset jongkok standar / keramik bh 150,000.00 12 Kloset jongkok teraso bh 85,000.00

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 4: AHS 2008-Kota.xlsx

Bahan - 4

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

WASTAFEL 1 Wastafel standar INA bh 850,000.00 2 Wastafel lux INA bh 950,000.00 3 Wastafel putih (KIA) set 800,000.00 4 Wastafel warna (KIA) set 850,000.00 5 Badkip bh 350,000.00 6 Bak cuci stainless steel bh 500,000.00 7 Water drain + asesories set 200,000.00

URINOIR 1 Urinoir standar TOTO U 57 set 2,000,000.00 2 Urinoir putih set 1,850,000.00 4 Urinoir warna (KIA) set 1,700,000.00 5 Meja cuci dapur 125 x 50 cm bh 350,000.00 6 Tempat sabun tunggal bh 75,000.00 7 Kran air diameter 3/4" atau 1/2" exs. Toto bh 185,000.00 8 Seal tape bh 8,500.00 9 Floordrain bh 135,000.00 10 Flooedrain (TX 1AN) 4" EX TOTO bh 250,000.00

BATA HALAMAN / PAVING BLOCK 1 WARNA NATURAL / ABU-ABU

2 Tipe segi empat, uni, segi 6 tebal = 8 cm K 400 60,000.00

3 Tipe uni dan segi empat tebal = 8 cm K 300 55,000.00

4 Tipe segi empat tebal = 6 cm K 200 45,000.00

5 Tipe segi empat tebal = 8 cm K 200 50,000.00

6 Tipe segi enam tebal = 6 cm K 200 45,000.00

7 Tipe segi enam tebal = 8 cm K 200 50,000.00

8 Tipe uni / tikar tebal = 6 cm K200 45,000.00

9 Tipe uni / tikar tebal = 8 cm K 200 50,000.00

10 Tipe trihex / sarang lebah tebal = 6 cm K 200 45,000.00

11 Tipe lampion tebal = 8 cm K 200 50,000.00

12 Tipe beteng kecil tebal = 6 cm K 200 45,000.00

13 Tipe beteng kecil tebal = 8 cm K 200 50,000.00

14 Tipe kipas tebal = 8 cm K 200 50,000.00

WARNA MERAH / HITAM

1 Tipe segi empat, uni, segi 8 tebal = 8 cm warna K 400 80,000.00

2 Tipe uni dan segi empat tebal = 8 cm warna K 300 70,000.00

3 Tipe segi empat tebal = 6 cm warna K 200 50,000.00

4 Tipe segi empat tebal = 8 cm warna K 200 60,000.00

5 Tipe segi enam tebal = 6 cm warna K 200 50,000.00

6 Tipe segi enam tebal = 8 cm warna K 200 60,000.00

7 Tipe uni / tikar tebal = 6 cm warna K200 50,000.00

8 Tipe uni / tikar tebal = 8 cm warna K 200 60,000.00

9 Tipe trihex / sarang lebah tebal = 6 cm warna K 200 50,000.00

10 Tipe lampion tebal = 8 cm warna K 200 60,000.00

11 Tipe beteng kecil tebal = 6 cm warna K 200 50,000.00

12 Tipe beteng kecil tebal = 8 cm warna K 200 60,000.00

13 Tipe kipas tebal = 8 cm warna K 200 60,000.00

14 Tipe grass blok bulat tebal = 10 cm 50,000.00

15 Tipe grass blok tebal = 10 cm 50,000.00

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 5: AHS 2008-Kota.xlsx

Bahan - 5

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

ASBES 1 Asbes plat ( 100 x 100 x 0,3 ) lbr 15,000.00 2 Asbes plat ( 200 x 100 x 0,3 ) lbr 25,000.00 3 Asbes plat ( 100 x 100 x 0,6 ) lbr 22,500.00 4 Asbes plat ( 100 x 100 x 0,5 ) lbr 20,000.00 5 Asbes plat ( 100 x 100 x 0,4 ) lbr 18,000.00 6 Asbes plat ( 100 x 100 x 0,35 ) lbr 16,500.00 7 Asbes plat ( 100 x 100 x 0,32 ) lbr 16,000.00

8 Asbes gelombang besar ( 300 x 110 x 0,5 ) lbr 90,275.00 9 Asbes gelombang besar ( 200 x 110 x 0,5 ) lbr 74,900.00 10 Asbes gelombang besar ( 180 x 110 x 0,5 ) lbr 61,950.00 11 Asbes gelombang besar ( 150 x 110 x 0,5 ) lbr 57,354.00 12 Asbes gelombang besar ( 300 x 92 x 0,5 ) lbr 85,000.00 13 Asbes gelombang besar ( 250 x 92 x 0,5 ) lbr 70,000.00 14 Asbes gelombang besar ( 225 x 92 x 0,5 ) lbr 65,000.00 15 Asbes gelombang besar ( 200 x 92 x 0,5 ) lbr 62,500.00 16 Asbes gelombang besar ( 180 x 92 x 0,5 ) lbr 57,500.00 17 Asbes gelombang besar ( 300 x 108 x 0,6 ) lbr 112,830.00 18 Asbes gelombang besar ( 270 x 108 x 0,6 ) lbr 101,500.00 19 Asbes gelombang besar ( 240 x 108 x 0,6 ) lbr 90,265.00 20 Asbes gelombang besar ( 210 x 108 x 0,6 ) lbr 78,980.00 21 Asbes gelombang besar ( 180 x 108 x 0,6 ) lbr 67,690.00 22 Asbes gelombang kecil ( 300 x 105 x 0,4 ) lbr 71,350.00 23 Asbes gelombang kecil ( 270 x 105 x 0,4 ) lbr 64,250.00 24 Asbes gelombang kecil ( 210 x 105 x 0,4 ) lbr 57,500.00 25 Asbes gelombang kecil ( 180 x 105 x 0,4 ) lbr 42,850.00 26 Asbes gelombang kecil ( 150 x 105 x 0,4 ) lbr 35,950.00 27 Asbes gelombang kecil ( 240 x 105 x 0,4 ) lbr 61,000.00 28 Asbes nok gelombang besar lbr 43,700.00 29 Asbes nok gelombang kecil lbr 23,775.00 30 Nok paten lbr 50,000.00 31 Nok stel rata lbr 25,000.00

GENTENG 1 Genteng beton besar natural 1m 9 biji bh 3,000.00 2 Genteng beton besar warna 1m 9 biji bh 4,500.00 3 Genteng beton kecil natural 1m 11 biji bh 3,000.00 4 Genteng beton kecil warna 1m 11 biji bh 4,500.00 5 Genteng beton kecil natural 1m 20 biji bh 2,500.00 6 Genteng beton kecil warna 1m 20 biji bh 3,000.00 7 Genteng bubungan beton bh 3,000.00 8 Genteng Wuwung warna bh 4,500.00 9 Nok press beton bh 45,000.00

BAHAN KERAMIK PIPA

1 Pipa tanah liat dia. 10 cm bh 15,000.00 2 Pipa tanah dia. 15 cm bh 35,000.00 3 Pipa tanah dia. 20 cm bh 45,000.00 4 Pipa tanah liat leher angsa bh 15,000.00

GENTENG & NOK 1 Genteng keramik lengkung cekung / vlaams bh 1,500.00 2 Genteng keramik lengkung rata bh 2,000.00 3 Genteng keramik rata / kodok bh 2,000.00 4 Genteng keramik berglasir KIA, Kanmuri Natural bh 5,200.00 5 Genteng monier bh 3,000.00 6 Genteng paris bh 1,100.00

Page 6: AHS 2008-Kota.xlsx

Bahan - 6

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

7 Nok genteng vlaams tanah liat bh 4,500.00 8 Nok genteng kodok bh 3,500.00 9 Nok genteng kodok berglasir bh 6,500.00 10 Nok genteng vlaams berglasir bh 6,500.00 11 Nok genteng paris bh 2,000.00 12 Nok genteng keramik berglasir KIA, Kanmuri Natural bh 13,500.00

ATAP GENTENG METAL

1 Genteng metal Zinc Alume type Prima Roof 135,300.00

2 Genteng metal Zinc Alume type Prima Colour 115,000.00

3 Genteng metal Zinc Alume type Super Colour 90,000.00

4 Atap metal gelombang t 0,35 mm 110,000.00 5 Nok atas (U) type Prima Roof ( 110 x 5 x 6 ) cm bh 40,000.00 6 Nok atas (U) type Prima Colour ( 110 x 5 x 6 ) cm bh 30,000.00 7 Nok atas (U) type Super Colour ( 110 x 5 x 6 ) cm bh 37,000.00 8 Nok atas bulat (C) type Prima Roof, P = 40 cm bh 35,000.00 9 Nok atas bulat (C) type Prima Colour, P = 40 cm bh 30,000.00 10 Nok atlas bulat (C) type Super Colour, P = 40 cm bh 30,000.00 11 Nok pinggir (P) type Prima Roof ( 110 x 7 x 10 ) cm bh 42,000.00 12 Nok pinggir (P) type Prima Colour ( 110 x 7 x 10 ) cm bh 40,000.00 13 Nok pinggir (P) type Super Colour ( 110 x 7 x 10 ) cm bh 30,000.00 14 Wall Flashing type Prima Roof, P = 110 cm, L = 10 cm bh 40,000.00 15 Wall Flashing type Prima Colour, P = 110 cm, L = 10 cm bh 35,000.00 16 Wall Flashing type Super Colour, P = 110 cm, L = 10 cm bh 30,000.00 17 Paku anti karat kg 25,000.00

18 Atap polykarbonat 200,000.00 19 Paku skrup anti karat atap metal/polykarbonat bh 1,500.00

KERAMIK BERMOTIF 1 Tegel keramik Roman Bella (25 x 25) dos 47,500.00 2 Tegel keramik Roman Bella (10 x 25) dos 38,000.00 3 Tegel keramik Roman Alice (20 x 20) dos 38,500.00 4 Tegel keramik Roman Latanza (20 x 25) dos 38,000.00 5 Tegel keramik Roman Latanza (8 x 20) bj 20,000.00 6 Tegel keramik Roman Tulip (20 x 25) dos 37,500.00 7 Tegel keramik Roman Tulip (8 x 20) bj 14,000.00 8 Tegel keramik Roman Milano (20 x 25) dos 38,000.00 9 Tegel keramik Roman Milano (8 x 20) bj 20,000.00

ISOLATOR 1 Isolator keramik bentuk rol bh 6,600.00 2 Isolator keramik bentuk T - I bh 1,650.00 3 Isolator keramik bentuk sungkup bh 1,650.00

TEGEL / KERAMIK

1 Tegel teraso 30/30 32,000.00

2 Tegel abu-abu 20/20 20,000.00

3 Tegel warna 20/20 26,000.00

4 Tegel abu-abu 30/30 28,000.00 5 Plint tegel abu-abu 15/20 bh 525.00

6 Tegel warna 20/20 26,000.00

7 Tegel warna 30/30 37,600.00 8 Plint tegel abu-abu 10/20 bh 350.00 9 Plint tegel abu-abu 10/30 bh 750.00 10 Plint tegel warna 10/20 bh 400.00 11 Plint tegel warna 10/30 bh 825.00

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 7: AHS 2008-Kota.xlsx

Bahan - 7

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

12 Tegel porselin 11/11 40,500.00

13 Tegel keramik 10/20 berglasir 30,000.00

14 Tegel keramik 20/20 berglasir 32,000.00

15 Tegel keramik 30/30 berglasir 32,500.00

16 Tegel keramik 40/40 berglasir 40,000.00

17 Tegel keramik standar ( MULIA) 20/20 dan 30/30 42,500.00

18 Tegel keramik mosaik 52,500.00 19 Stepnosing granito bh 9,350.00 20 List keramik dinding motif 5/20 bh 5,000.00 21 Plint keramik 10 x 30 bh 1,500.00

22 Keramik dinding 20/25 42,500.00

KERB TAMAN 1 Devider Mutiara m 66,000.00 2 Devider /kans teen tebal 30 Mutiara m 22,000.00 3 Devider /kans teen tebal 25 Mutiara m 18,800.00 4 Devider /kans teen tebal 20 Mutiara bh 15,300.00 5 Devider /kans teen tebal 15 Mutiara bh 11,250.00 6 Ramp ( terpasang ) bh 26,000.00 7 Devider terpasang bh 30,000.00 8 Kerb terpasang bh 28,000.00

KAYU 1 KAYU JATI

2 Kayu jati balok 8/12 ( klas plitur ) 20,000,000.00

3 Kayu jati papan 22,000,000.00

4 Balok kayu kelas I ukuran 8/12 192,000.00

5 Balok kayu kelas I ukuran 8/10 160,000.00

6 Balok kayu kelas I ukuran 6/12 144,000.00

7 Balok kayu kelas I ukuran 6/10 120,000.00

8 Balok kayu kelas I ukuran 6/8 96,000.00

9 Bingkai kayu kelas I ukuran 5/7 70,000.00

10 Bingkai kayu kelas I ukuran 4/6 48,000.00

11 Bingkai kayu kelas I ukuran 3/4, 3/5 24,000.00

12 Bingkai kayu kelas I ukuran 2/3 12,000.00

13 Papan kayu kelas I ukuran 3/20 132,000.00

14 Papan kayu kelas I ukuran 3/18 118,800.00

15 Papan kayu kelas I ukuran 2/25 110,000.00

16 Papan kayu kelas I ukuran 2/20 88,000.00

17 Papan kayu kelas I ukuran 2/15 66,000.00

18 Lis Dan jalusi kayu kelas I ukuran 2/6 24,000.00

19 Lis Dan jalusi kayu kelas I ukuran 2/4 16,000.00

20 Lis Dan jalusi kayu kelas I ukuran 1/5 10,000.00

21 Lis Dan jalusi kayu kelas I ukuran 1/3 6,000.00

22 Kayu jati balok 8/12 (lokal) 10,000,000.00

23 Kayu jati papan (lokal) 11,000,000.00

24 Kaui jati lokal ukuran 5/7 35,000.00

25 Kayu jati lokal ukuran 2/3 6,000.00

26 Kayu jati lokal ukuran 3/4 12,000.00

KAYU KAMPER

1 Kayu kamper balok 4,750,000.00

2 Kayu kamper papan 5,500,000.00

3 Balok kayu kelas I ukuran 8/12 45,600.00

m2

m2

m2

m2

m2

m2

m2

m2

m3

m3

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m3

m3

m1

m1

m1

m3

m3

m1

Page 8: AHS 2008-Kota.xlsx

Bahan - 8

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

4 Balok kayu kelas I ukuran 8/10 38,000.00

5 Balok kayu kelas I ukuran 6/12 34,200.00

6 Balok kayu kelas I ukuran 6/10 28,500.00

7 Balok kayu kelas I ukuran 6/8 22,800.00

8 Bingkai reng & kaso kayu kelas I ukuran 5/7 16,625.00

9 Bingkai reng & kaso kayu kelas I ukuran 4/6 11,400.00

10 Bingkai reng & kaso kayu kelas I ukuran 3/4 5,700.00

11 Bingkai reng & kaso kayu kelas I ukuran 2/3 2,850.00

12 Papan kayu kelas I ukuran 2/15 16,500.00

13 Papan kayu kelas I ukuran 2/20 22,000.00

14 Papan kayu kelas I ukuran 2/25 27,500.00

15 Papan kayu kelas I ukuran 3/18 29,700.00

16 Papan kayu kelas I ukuran 3/20 33,000.00

17 Papan kayu kelas I ukuran 3/30 49,500.00

18 Lis Dan jalusi kayu kelas I ukuran 1/3 1,425.00

19 Lis Dan jalusi kayu kelas I ukuran 1/5 2,375.00

20 Lis Dan jalusi kayu kelas I ukuran 2/4 2,850.00

KAYU BENGKIRAI

1 Kayu bengkirai balok 5,750,000.00

2 Kayu bengkirai papan 6,000,000.00

3 Balok kayu kelas I ukuran 8/12 55,200.00

4 Balok kayu kelas I ukuran 8/10 46,000.00

5 Balok kayu kelas I ukuran 6/12 41,400.00

6 Balok kayu kelas I ukuran 6/10 34,500.00

7 Balok kayu kelas I ukuran 6/8 27,600.00

8 Bingkai reng & kaso kayu kelas I ukuran 5/7 20,125.00

9 Bingkai reng & kaso kayu kelas I ukuran 4/6 13,800.00

10 Bingkai reng & kaso kayu kelas I ukuran 3/4 6,900.00

11 Bingkai reng & kaso kayu kelas I ukuran 2/3 3,450.00

12 Papan kayu kelas I ukuran 2/15 18,000.00

13 Papan kayu kelas I ukuran 2/20 24,000.00

14 Papan kayu kelas I ukuran 2/25 30,000.00

15 Papan kayu kelas I ukuran 3/18 32,400.00

16 Papan kayu kelas I ukuran 3/20 36,000.00

17 Papan kayu kelas I ukuran 3/30 54,000.00

18 Lis Dan jalusi kayu kelas I ukuran 1/3 1,725.00

19 Lis Dan jalusi kayu kelas I ukuran 1/5 2,875.00

20 Lis Dan jalusi kayu kelas I ukuran 2/4 4,600.00

KAYU KRUING

1 Kayu kruing balok 4,350,000.00

2 Kayu kruing papan 4,750,000.00

3 Balok kayu kelas I ukuran 8/12 41,760.00

4 Balok kayu kelas I ukuran 8/10 34,800.00

5 Balok kayu kelas I ukuran 6/12 31,320.00

6 Balok kayu kelas I ukuran 6/10 26,100.00

7 Balok kayu kelas I ukuran 6/8 20,880.00

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m3

m3

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m3

m3

m1

m1

m1

m1

m1

Page 9: AHS 2008-Kota.xlsx

Bahan - 9

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

8 Bingkai reng & kaso kayu kelas I ukuran 5/7 15,225.00

9 Bingkai reng & kaso kayu kelas I ukuran 4/6 10,440.00

10 Bingkai reng & kaso kayu kelas I ukuran 3/4 5,220.00

11 Bingkai reng & kaso kayu kelas I ukuran 2/3 2,610.00

12 Papan kayu kelas I ukuran 2/15 14,250.00

13 Papan kayu kelas I ukuran 2/20 19,000.00

14 Papan kayu kelas I ukuran 2/25 23,750.00

15 Papan kayu kelas I ukuran 2/30 28,500.00

16 Papan kayu kelas I ukuran 3/18 25,650.00

17 Papan kayu kelas I ukuran 3/20 28,500.00

18 Papan kayu kelas I ukuran 3/25 35,625.00

19 Papan kayu kelas I ukuran 3/30 42,750.00

20 Lis Dan jalusi kayu kelas I ukuran 1/3 1,305.00

21 Lis Dan jalusi kayu kelas I ukuran 1/5 2,175.00

22 Lis Dan jalusi kayu kelas I ukuran 2/4 3,480.00

LIST KAYU PROFIL

1 List kayu profil 5,500.00

2 Kayu plepet eternit 1/5 cm 2,000.00

KAYU GLUGU, DOLKEN DAN BEGESTENG

1 Kayu glugu balok 1,458,000.00

2 Kayu glugu ukuran 5/7 6,300.00

3 Kayu meranti 2,750,000.00

4 Papan cetakan / begesteng 1,000,000.00

5 Kayu dolken 1,000,000.00 6 btg 10,000.00

7 Kayu bakar 90,000.00

KAYU LAPIS 1 Kayu lapis mutu I AA 3 lapis uk. 122x244x0,3 cm lbr 31,900.00 2 Kayu lapis mutu I AA 3 lapis uk. 122x244x0,4 cm lbr 41,250.00 3 Kayu lapis mutu I AA 3 lapis uk. 122x244x0,9 cm lbr 90,000.00 4 Kayu lapis mutu I AA 3 lapis uk. 122x244x1,2 cm lbr 101,750.00 5 Akustik soft board 60 x 120 lbr 125,000.00 6 Akustik soft board 40 x 60 lbr 73,000.00 7 Akustik soft board 30 x 60 lbr 55,000.00 8 Melamin wood 90 x 120 cm lbr 50,000.00 9 Melamin wood 120 x 240 cm lbr 65,000.00 10 Formika 4" x 8" x 0,3 cm lbr 65,000.00 11 Teak wood ( 90 x 240 ) lbr 69,500.00

BAHAN TUMBUHAN 1 Bambu petung btg 48,500.00 2 Bambu wulung btg 9,500.00 3 Bambu apus btg 7,000.00

4 Gedek bambu kulit 65,000.00

5 Gedek bambu daging 27,000.00

6 Ijuk 75,000.00 7 Ijuk kg 9,000.00 8 Alang-alang ikat 500.00

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m3

m1

m3

m3

m3 Kayu dolken Ø 8 - 10/400 cm

m3

m2

m2

m3

Page 10: AHS 2008-Kota.xlsx

Bahan - 10

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

LISTRIK 1 Tusuk kontak 2 kutup tanpa pembumian/arde buah 3,900.00 2 Tusuk kontak 2 kutup dengan pembumian/arde buah 6,500.00 3 Tusuk kontak 2 kutup tanpa pembumian (timbul) buah 6,175.00 4 Tusuk kontak 2 kutup dengan pembumian (timbul) buah 6,500.00 5 Tusuk kontak 2 kutup tanpa pembumian (tanam) buah 7,800.00 6 Tusuk kontak 2 kutup dengan pembumian (tanam) buah 12,000.00 7 Kontak hubungan bagi dengan selungkup isolasi

- 1 fasa 250 V/ 6 A (timbul) buah 23,200.00 - 1 fasa 250 V/ 10 A (timbul) buah 30,000.00 - 1 fasa 250 V/ 6 A (tanam)/MCB buah 37,500.00 - 1 fasa 250 V/ 10 A (tanam)/MCB buah 39,000.00

8 Fitting duduk buah 5,000.00 9 Pasang instalasi / titik titik 85,000.00 10 Lampu pijar 5 watt "Phillips" buah 2,275.00 11 Lampu pijar 10 watt "Phillips" buah 3,705.00 12 Lampu pijar 25 watt/ 40 watt "Phillips" buah 3,900.00 13 Lampu pijar 60 watt / 75 watt "Phillips" buah 4,550.00 14 Lampu pijar 100 watt "Phillips" buah 5,200.00 15 Lampu softone 100 watt "Phillips" buah 6,500.00 16 Lampu pijar 150 watt "Phillips" buah 10,400.00 17 Lampu pijar 200 watt "Phillips" buah 11,700.00 18 Lampu TL 10 watt "Phillips" buah 7,150.00 19 Lampu TL 15 watt "Phillips" buah 7,500.00 20 Lampu TL 18 watt "Phillips" buah 11,050.00 21 Lampu TL 36 watt "Phillips" buah 13,650.00 22 Lampu SLE 11 watt "Phillips" buah 71,500.00 23 Lampu SLE 15 watt "Phillips" buah 71,500.00 24 Lampu SLE 20 watt "Phillips" buah 74,750.00 25 Lampu Slang 2 jalur (sekualitas sinyoku) roll 2,400,000.00 26 Lampu Slang 3 jalur (sekualitas sinyoku) roll 2,795,000.00 27 Lampu Rice Light isi 100 "Phillips" pcs 60,000.00 28 Lampu Rice Light isi 140 "Phillips" pcs 72,000.00 29 Lampu Capsul isi 100 "Phillips" pcs 210,000.00 30 Lampu Capsul isi 140 "Phillips" pcs 222,000.00 31 Lampu Anggur isi 100 "Phillips" pcs 65,000.00 32 Lampu Anggur isi 140 "Phillips" pcs 78,000.00 33 Lampu Natal isi 50 "Phillips" pcs 23,000.00 34 Lampu Natal isi 100 "Phillips" pcs 103,500.00 35 Lampu Jenis H.PIT 400 watt "Phillips" buah 1,023,750.00 36 Lampu Jenis H.PIT 250 watt "Phillips" buah 700,000.00 37 Bolam Mercury 80 watt "Phillips" buah 45,500.00 38 Bolam Mercury 125 watt "Phillips" buah 96,000.00 39 Bolam Mercury 250 watt "Phillips" buah 97,500.00 40 Bolam Mercury 400 watt "Phillips" buah 123,500.00 41 Bolam Natrium 250 watt "Phillips" buah 208,000.00 42 Bolam Natrium 400 watt "Phillips" buah 221,000.00 43 Bolam SON 250 watt buah 227,500.00 44 Bolam SON 150 watt buah 215,800.00 45 Bolam SON 70 watt buah 137,150.00 46 Bolam SON-T 250 watt buah 241,000.00 47 Bolam SON-T 150 watt buah 155,000.00 48 Bolam SON-T 70 watt buah 96,000.00 49 Bolam Halogin 500 watt buah 39,000.00 50 Bolam Halogin 1000 watt buah 65,000.00 51 Bolam HPIT 150 watt buah 260,000.00 52 Bolam HPIT 250 watt buah 292,500.00 53 Bolam HPIT 400 watt buah 296,500.00

Page 11: AHS 2008-Kota.xlsx

Bahan - 11

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

54 Bolam Metal Halide 70 watt buah 149,500.00 55 Bolam Metal Halide 100 watt buah 188,548.00 56 Bolam Metal Halide 150 watt buah 156,000.00 57 Bolam Metal Halide 250 watt buah 344,500.00 58 Photo Cell 3 Ampere buah 65,000.00 59 Photo Cell 6 Ampere buah 78,000.00 60 Photo Cell 10 Ampere buah 104,000.00 61 Starter TL 20/40 watt buah 4,550.00 62 Travo TL 10 watt buah 24,050.00 63 Travo TL 20 watt buah 26,000.00 64 Travo TL 40 watt buah 29,250.00 65 Balast Mercury 80 watt buah 96,000.00 66 Balast Mercury 125 watt buah 104,000.00 67 Balast Mercury 250 watt buah 162,500.00 68 Balast Mercury 400 watt buah 195,000.00 69 Balast Natrium 250 watt buah 162,500.00 70 Balast Natrium 400 watt buah 150,000.00 71 Balast SON 250 watt buah 221,000.00 72 Balast SON 150 watt buah 172,500.00 73 Balast SON 70 watt buah 127,000.00 74 Balast Metal Halide 70 watt buah 131,000.00 75 Balast Metal Halide 100 watt buah 256,939.00 76 Balast Metal Halide 150 watt buah 180,000.00 77 Magnetik Kontaktor SK-12 Kw 1 (SN-12) buah 210,000.00 78 Magnetik Kontaktor SK-12 Kw 2 buah 48,000.00 79 Magnetik Kontaktor SK-20 Kw 1 (SN-20) buah 240,000.00 80 Magnetik Kontaktor SK-20 Kw 2 buah 66,000.00 81 Fitting Goliath E.27 Gantung buah 19,500.00 82 Fitting Goliath E.40 Gantung buah 26,000.00 83 Fitting WD E.27 Tegak buah 4,550.00 84 Fitting WD E.40 Tegak buah 16,250.00 85 Fitting Kecil Lampu 2,5 Watt buah 325.00 86 Fitting Plastik Hitam buah 1,300.00 87 Fitting Gantung plastik gantung buah 1,000.00 88 Kap Alumunium E.27 buah 19,500.00 89 Kap Alumunium E.40 buah 19,500.00 90 Kabel Snoor 2 x 0,23 "Supreme" roll 72,000.00 91 Kabel NYA 2,5 sqmm "Supreme" roll 150,000.00 92 Kabel NYA 1,5 sqmm "Supreme" roll 95,000.00

Kabel NYA 2,5 sqmm "Supreme" m' 2,475.00 Kabel NYA 1,5 sqmm "Supreme" m' 1,650.00

93 Kabel NYM 2 x 1,5 sqmm "Supreme" 7,216.00

94 Kabel NYM 2 x 2,5 sqmm "Supreme" 10,633.00

95 Kabel NYM 2 x 4 sqmm "Supreme" 14,256.00

96 Kabel NYM 3 x 1,5 sqmm "Supreme" 9,257.00

97 Kabel NYM 3 x 2,5 sqmm "Supreme" 13,200.00

98 Kabel NYM 3 x 4 sqmm "Supreme" 19,096.00

99 Kabel NYY 3 x 6 sqmm "Supreme" 30,553.00

100 Kabel NYY 3 x 1,5 sqmm "Supreme" 12,584.00

101 Kabel NYY 3 x 2,5 sqmm "Supreme" 16,896.00

102 Kabel NYY 3 x 4 sqmm "Supreme" 23,056.00

103 Kabel NYY 3 x 6 sqmm "Supreme" 30,553.00

104 Kabel NYY 3 x 10 sqmm "Supreme" 45,408.00

105 Kabel NYY 4 x 10 sqmm "Supreme" 61,600.00

106 Kabel NYFGBY 3 x 10 sqmm "Supreme" 88,000.00

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 12: AHS 2008-Kota.xlsx

Bahan - 12

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

107 Kabel DX 2 x 10 sqmm "Supreme" 5,500.00

108 Kabel DX 2 x 16 sqmm "Supreme" 6,600.00

109 Kabel DX 2 x 25 sqmm "Supreme" 16,500.00

110 Kabel Ties 15 cm "Supreme" 11,050.00

111 Kabel Tis 10 cm "Supreme" 6,500.00 112 Ignitor 150 watt - 250 watt buah 45,000.00 113 Ignitor Metal Halide 70 watt buah 68,250.00 114 Ignitor Metal Halide 100 watt buah 50,000.00 115 Ignitor Metal Halide 150 watt buah 73,710.00 116 Firework lamp (DC-001) 8 meter Pcs 17,192,500.00 117 Firework lamp (DC-001) 6 meter Pcs 15,323,750.00 118 NT Fuse kaki besar buah 140,400.00 119 NT Fuse kaki kecil buah 52,000.00 120 Flassther Lampu Hias Buterfly buah 3,071,250.00 121 Flassther Lampu Hias Kembang Api Besar buah 3,071,250.00 122 Flassther Lampu Hias Kembang Api Kecil buah 3,071,250.00 123 Flassther Lampu Hias Kipas buah 3,071,250.00 124 Skaklar seri OB "Broco" buah 17,550.00 125 Skaklar seri IB "Broco" buah 17,550.00 126 Skaklar engkel OB "Broco" buah 13,000.00 127 Skaklar engkel IB "Broco" buah 13,000.00 128 Stop kontak IB "Broco" buah 13,650.00 129 Stop kontak OB "Broco" buah 13,650.00 130 Kapasitor 25 F buah 52,000.00 131 Kapasitor 20 F buah 48,750.00 132 Kapasitor 12,5 uF buah 26,000.00 133 Kapasitor 8 mF buah 22,750.00 134 Kapasitor Metal Halide 70 watt buah 61,450.00 135 Kapasitor Metal Halide 100 watt buah 115,842.00 136 Kapasitor Metal Halide 150 watt buah 71,650.00 137 MCB 25 Ampere / 16 Ampere "MG" buah 36,000.00 138 MCB 40 Ampere "MG" buah 57,330.00 139 MCB 63 Ampere "MG" buah 108,000.00 140 MCB 10 Ampere + box "MG" buah 42,000.00 141 MCB 6 Ampere "MG" buah 42,000.00 142 Cover MCB "MG" buah 5,200.00 143 Box Kwh Meter 25 x 35 x 20 buah 448,500.00 144 Box panel 30 x 40 x 20 buah 169,000.00 145 Box 25 x 25 x 20 buah 97,500.00 146 Box 20 x 40 x 50 buah 312,000.00 147 UZ 25 buah 6,500.00 148 UZ 63 buah 19,500.00 149 Armatur IP 65 Komplit (sekualitas SRP 822 SON 150 watt) unit 2,834,000.00 150 Armatur IP 65 Komplit (sekualitas SRP 822 SON 250 watt) unit 2,954,000.00 151 Armatur IP 65 Komplit (sekualitas SRP 328 SON 150 watt) unit 3,315,000.00 152 Armatur IP 65 Komplit (sekualitas SRP 328 SON 250 watt) unit 3,445,000.00 153 Armatur IP 65 Komplit (sekualitas SRP 810 SON 70 watt) unit 2,275,000.00 154 Armatur Ekorola Komplit / TLD 18 watt unit 471,900.00 155 Armatur Simbat 40 watt unit 70,200.00 156 Armatur HPIT 100 watt (DVP 311) unit 4,231,500.00 157 Armatur Kota Sorot (Kosong) unit 1,495,000.00 158 Timer Switch TB 388 buah 540,000.00 159 Timer Theben (pakai baterai) buah 660,000.00 160 Timer Heger (pakai baterai) buah 513,000.00 161 Timer Delay H3-BA (omron) buah 110,500.00 162 Timer Delay H3-CR-8 (omron) buah 175,500.00 163 Timer Digital Theben buah 1,033,500.00

m1

m1

m1

m1

m1

Page 13: AHS 2008-Kota.xlsx

Bahan - 13

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

164 Tiang Galvanit cb,1, h=9m, base plate unit 3,783,000.00 165 Tiang Galvanit cb,2, h=9m, base plate unit 3,055,500.00

Tiang Galvanit cb,2, h=6m, base plate unit 2,665,000.00 166 Tiang Galvanit cb,1, h=7m, base plate unit 2,783,000.00 167 Tiang Galvanit cb,1, h=5m, type tanam dia 2" unit 812,500.00 168 Tiang lampu Highment cb 4, h=20m, hidrolik unit 140,692,000.00 169 Tiang lampu Highment cb 2, h=20m, hidrolik unit 140,692,000.00 170 Tiang GIP cb 1. 2", 3", 4", 5", h = 9m, tanam unit 2,535,000.00 171 Tiang GIP cb 1. 2", 3", 4", h = 7m, tanam unit 2,275,000.00 172 Tiang GIP cb 1. 3", 4", 5", h = 9m, tanam unit 2,340,000.00 173 Slang Ornamenr GIP dia 1", L = 3m unit 162,825.00 174 Slang Ornamenr GIP dia 2", L = 2m unit 193,050.00 175 Slang Ornamenr GIP dia 2", L = 3m unit 210,600.00 176 Slang Ornamenr GIP dia 2", L = 4m unit 222,300.00 177 Slang Ornamenr GIP dia 2", L = 6m unit 305,500.00 178 Pilot Lamp buah 6,850.00 179 Seplendiel lamp (DC-002) Pcs 17,267,000.00 180 Windmill lamp (DC-003) Pcs 16,875,000.00 181 Cottonrose lamp (DC-004) Pcs 16,875,000.00 182 Lucky lamp (DC-005) Pcs 12,950,000.00 183 Fountain lamp Ball (DC-005) Pcs 14,284,000.00 184 Star Flower lamp (DC-007) Pcs 16,090,000.00 185 Chritmas lamp (DC-009) Pcs 14,127,000.00 186 Butterfly lamp (DC-009) Pcs 18,052,000.00 187 No. 1 lamp (DC-010) Pcs 16,482,000.00 188 Hepta lamp (DC-011) Pcs 16,089,000.00 189 Dragon Phonix lamp (DC-013) Pcs 16,089,000.00 190 Fountain lamp (DC-014) Pcs 16,089,000.00 191 Redbud Flower lamp (DC-015) Pcs 16,089,000.00 192 Dragon Flying lamp (DC-016) Pcs 14,520,000.00 193 Floor lamp (DC-017) Pcs 10,988,000.00 194 Octopus lamp (DC-018) Pcs 16,089,000.00 195 Double Plied Fountain lamp (DC-019) Pcs 16,877,000.00 196 Flower Pot lamp (DC-020) Pcs 17,267,000.00 197 Patron Sekering buah 2,050.00 198 Kop sekering buah 3,450.00 199 Isolasi besar buah 6,825.00 200 Spot + F.MP buah 75,075.00 201 Sabuk Pengaman buah 2,730,000.00 202 Tang Kombinasi buah 34,125.00 203 Obeng +/- buah 23,750.00 204 GZ 30 A buah 40,950.00 205 Multitester buah 116,000.00 206 Sekering buah 2,100.00 207 Bandet buah 4,750.00 208 Wadge Type buah 4,750.00 209 Servis link dan clem buah 4,750.00 210 Stenlist stell 20 x 0,70 roll 614,000.00 211 Stopyng bukie buah 2,100.00 212 BC 6 mm buah 4,750.00 213 Ground Rood buah / batang 30,750.00 214 Terminal Nol buah 23,850.00 215 Mata lampu pijar 25 W -75 W buah 4,350.00 216 Stabilizer 300 A unit 2,934,000.00 217 Tutup panel 30 x 30 buah / ls 28,750.00 218 Pasang panel kontrol unit / ls 86,250.00 219 Penyambungan beban unit 17,250.00 220 Penyetelan dan penyalaan titik 7,000.00 221 Biaya angkutan jam 7,143.00 222 Alat bantu set 86,250.00 223 Retur material existing unit 100,000.00

Page 14: AHS 2008-Kota.xlsx

Bahan - 14

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

Page 15: AHS 2008-Kota.xlsx

Bahan - 15

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

BAHAN LOGAM BESI/BAJA TULANGAN/BESI BETON BESI BETON

1 Besi beton polos kg 7,900.00 2 Besi beton ulir kg 8,000.00 3 Besi baja profil kg 8,800.00 4 Besi tuang / cor kg 8,200.00 5 Besi strip kg 7,500.00 6 Besi baja cor ( ring ) 150 kg unit 825,000.00 7 Besi baja cor ( ring ) 80 kg unit 440,000.00 8 Besi baja cor ( ring ) 40 kg unit 220,000.00 9 Besi penutup mahkota assainering unit 57,000.00 10 Besi penutup inlet cor/tuang ( ring + tutup) unit 85,000.00

KAWAT 1 Kawat beton / bindrat kg 9,400.00

2 Kawat ayakan 10,000.00 3 Kawat bronjong kg 30,250.00

4 Kawat nyamuk 8,250.00 5 Kawat las kg 6,500.00 6 Kawat galvanis kg 7,755.00 7 Kawat duri kg 9,500.00 8 Besi jaring kawat baja kg 9,500.00 9 Kawat seng polos kg 9,500.00

10 Kawat kassa 10,000.00

11 Kawat burung 15,000.00 12 Kawat jaring lbr 35,000.00

13 Kawat harmonika 25,000.00

14 Kawat penggantung rangka hollow 500.00

15 Profil Alumunium "T" 20,000.00 16 Ramset / dina bolt bh 2,500.00

17 Pipa galvanis dia. 1/2" 15,000.00

18 Pipa galvanis dia. 3/4" 25,000.00

19 Pipa galvanis dia. 1" 37,500.00

20 Pipa galvanis dia. 1 1/2" 50,000.00

21 Pipa galvanis dia. 3" 85,000.00

22 Pipa galvanis dia. 4" 90,000.00

23 Pipa hollow 4 x 4 cm tebal 1.2 mm 9,500.00

24 Kusen alumunium uk 2"x4" tebal 1.2 mm sekualitas YKK putih 55,000.00 25 Jendela nako bh 20,000.00

26 Pintu besi baja 750,000.00

27 Jendela besi baja 750,000.00

28 Jendela besi tahan api 1,500,000.00

29 Pintu gulung besi 250,000.00

30 Pintu lipat besi 500,000.00

31 Sunscreen alumunium 250,000.00

32 Roll door 200,000.00

33 Pintu alumunium 400,000.00

34 Vertikal blind 250,000.00

35 Wall paper 40,000.00

m2

m2

m2

m2

m2

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 16: AHS 2008-Kota.xlsx

Bahan - 16

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

SENG BJLS 1 Seng BJLS 0,20 gelombang P = 180 cm lbr 38,500.00 2 Seng BJLS 0,20 gelombang P = 200 cm (merk Fumira) lbr 42,000.00 3 Seng BJLS 0,20 gelombang P = 240 cm lbr 60,000.00 4 Seng BJLS 0,20 gelombang P = 300 cm lbr 70,000.00

5 Seng BJLS 0,28 lembaran 40 cm lebar 12,500.00

6 Seng BJLS 0,28 lembaran 50 cm lebar 16,000.00

7 Seng BJLS 0,20 lembaran 90 cm lebar 25,000.00

8 Seng BJLS 0,30 lembaran 40 cm lebar 20,000.00

9 Seng BJLS 0,30 lembaran 50 cm lebar 18,000.00

10 Seng BJLS 0,30 lembaran 60 cm lebar 20,000.00

11 Seng BJLS 0,30 lembaran 90 cm lebar 28,000.00 12 Seng plat 3" x 6" BJLS 28 lbr 44,000.00 13 Seng plat 3" x 6" BJLS 24 lbr 38,500.00 14 Seng gelombang 2" - 5" BJLS 24 lbr 25,000.00

15 Alumunium gelombang tebal 0,55 75,000.00

16 Alumunium foil 25,000.00

17 Nok alumunium standar 40 cm 18 SWG 22 25,000.00

PAKU 1 Paku gording 125 x 5,1 mm kg 8,000.00 2 Paku gording 100 x 4,2 mm kg 8,000.00 3 Paku usuk 80 x 3,8 mm kg 8,000.00 4 Paku reng 55 x 3,1 mm kg 8,000.00 5 Paku plepet 40 x 2,1 mm kg 10,000.00 6 Paku eternit 20 x 1,5 mm kg 11,500.00 7 Angkur / baut bh 10,000.00 8 Paku kait bh 8,500.00 9 Paku pancing bh 500.00 10 Paku pancing kg 9,350.00 11 Paku asbes bh 400.00 12 Paku sumbat bh 400.00 13 Paku sekrup 3.5" bh 750.00 14 Paku skrup kg 10,000.00 15 Paku gypsum kg 20,000.00 16 Paku hak panjang 15 cm kg 9,500.00

PENGGANTUNG / PENGUNCI 1 Engsel pintu bh 11,000.00 2 Engsel jendela bh 7,500.00 3 Grendel bh 2,500.00 4 Hak angin bh 5,500.00 5 Selot pintu Union kecil bh 37,500.00 6 Selot pintu Union besar bh 47,500.00 7 Engsel angin bh 3,000.00 8 Kait angin bh 3,000.00 9 Door holder bh 15,000.00 10 Door stop bh 15,000.00 11 Penggantung + rel pintu dorong bh 200,000.00 12 Kunci tanam bh 35,000.00 13 Kunci tanam antik bh 250,000.00 14 Kunci tanam biasa bh 125,000.00 15 Kunci kamar mandi bh 50,000.00 16 Kunci selot bh 50,000.00 17 Kunci silinder bh 75,000.00 18 Kunci lemari bh 12,000.00 19 Spring knip bh 7,500.00 20 Door closer bh 150,000.00

m1

m1

m1

m1

m1

m1

m1

m2

m2

m1

Page 17: AHS 2008-Kota.xlsx

Bahan - 17

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

ASPAL 1 Aspal curah kg 9,500.00 2 Aspal drum kg 10,650.00 3 Aspal modifer / asphalt joint kg 60,000.00 4 Drum aspal bekas bh 8,250.00

5 Rubber Filler 9,000.00 6 Mata Kucing bh 215,000.00 7 Filler kg 750.00

BATU ALAM / AGREGAT / BAHAN TUMBUHAN BATU ALAM

1 Batu kali 130,000.00

2 Batu hias tempel 60,000.00

3 Batu hias bulat putih 147,500.00

4 Ubin marmer ( 40 x 40 x 2 ) Baitik/Citatah 100,000.00

5 Ubin marmer ( 40 x 60 x 2 ) Baitik 450,000.00

6 Ubin marmer ( 15 x 30 x 2 ) Baitik 150,000.00

AGREGAT

1 Agregat hakus/pasir klas A ( Uk. butir 5 mm ) 79,750.00

2 Agregat kasar/krikil/pasir klas B ( Uk. 20 - 40 ) 126,500.00

3 132,000.00

4 Batu pecah 2/3 ( split ) 138,000.00

5 Batu pecah 3/4 130,000.00

6 Batu pecah 4/6 126,500.00

7 Batu pecah 5/7 132,000.00

8 Batu pecah 1/2 190,000.00

9 Batu belah hitam 80,000.00

10 Batu belah putih 70,000.00

11 Sirtu Klas A lewat ayakan 1" 66,000.00

12 66,000.00

13 Pasir urug darat 55,000.00

14 Pasir pasang ( progo ) 73,000.00

15 Pasir pasang ( krasak ) 76,000.00

16 Krikil beton 78,650.00

17 Kerikil tidak tersaring 55,000.00

18 Split D 30 - 40 mm 120,000.00

19 Split D 10 - 20 mm 120,000.00

20 Split D 1 - 2 cm 125,000.00 21 Batu merah ( 5x11x23 ) bj 350.00 22 Batu merah ( 4x9x19 ) bj 250.00

23 Krokos 0,2/0,4 70,000.00

24 Tanah urug 35,000.00

25 Sirtu 66,000.00 26 Batako bh 1,500.00 27 Roster 25/25 bh 2,000.00

m1

m3

m2

m3

m2

m2

m2

m3

m3

Agregat kasar/krikil/pasir klas B ( Uk. 4½ - 19 ) m3

m3

m3

m3

m3

m3

m3

m3

m3

Sirtu klas B lewat ayakan 2½" m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 18: AHS 2008-Kota.xlsx

Bahan - 18

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

BAHAN PEREKAT HIDROLIS & ORGANIK 1 Portland Cement (PC) Gresik 50 kg 38,200.00

40 kg 31,000.00 2 Portland Cement (PC) Nusantara 50 kg 38,200.00

40 kg 31,000.00 3 Portland Cement (PC) Tiga Roda 40 kg 31,000.00 4 Semen putih 40 kg 52,500.00 5 Semen warna kg 6,000.00 6 Lem kayu (putih) Fox kg 11,000.00 7 Lem plastik Acrylic kg 60,000.00 8 Lem plastik Vinyl kg 19,500.00 9 Lem Aica Aibon kg 27,500.00

KAPUR & GIPS

1 Kapur pasang 72,500.00

2 Kapur sirih 138,000.00 3 Kapur sirih kg 500.00

4 Semen batu bata 80,000.00 5 Tepung Gypsum kg 3,500.00 6 Alkasit kg 300,000.00 7 Gypsum board lbr 42,000.00 8 Kasa gypsum roll 10,000.00

9 List profil gypsum lebar sampai 5 cm 4,000.00

10 List profil gypsum lebar sampai 6 - 10 cm 8,000.00

11 List profil gypsum lebar lebih 10 cm 15,000.00 12 Kalsiboard ( 122 x 244 x 0,35 ) cm lbr 46,200.00 13 Kalsiboard ( 122 x 244 x 0,60 ) cm lbr 60,500.00

BAHAN PELARUT, PELUMAS 1 Oli SAE 30 ltr 21,000.00 2 Minyak bakar / kerosene ltr 1,000.00 3 Bensin premium ltr 4,500.00 4 Solar ltr 4,300.00 5 Minyak pelumas ltr 14,000.00 6 Vet kg 13,000.00 7 Gas Elpiji kg 4,500.00 8 Minyak bekisting ltr 5,000.00

BAHAN KIMIA PEMBANTU UNTUK BETON 1 Bahan kimia B (kuat ikat cepat ) kg 35,000.00 2 Bahan kimia E (kuat ikat cepat ) kg 30,000.00

BAHAN PENGAWET DANBITUMEN 1 Teer kayu box 8,000.00 2 Residu ltr 3,500.00 3 Flincoat ltr 35,000.00

BAHAN KACA 1 Genteng kaca lengkung cekung 3 mm bh 5,500.00 2 Genteng kaca lengkung cekung 5 mm bh 7,000.00 3 Genteng kaca lengkung rata 3 mm bh 5,500.00 4 Genteng kaca lengkung rata 5 mm bh 6,850.00 5 Genteng kaca 3 mm bh 4,000.00 6 Genteng kaca 5 mm bh 6,850.00

7 Kaca buram/kaca es 3 mm 53,900.00

8 Kaca buram/kaca es 5 mm 66,000.00

m3

m3

m3

m1

m1

m1

m2

m2

Page 19: AHS 2008-Kota.xlsx

Bahan - 19

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

9 Kaca bening 3 mm 49,500.00

10 Kaca bening 5 mm 60,500.00

11 Kaca riben 3 mm 57,500.00

12 Kaca riben 5 mm 70,000.00

13 Kaca cermin 3 mm 75,000.00

14 Kaca cermin 5 mm 120,000.00

15 Kaca patri 300,000.00 16 Fiber glass lbr 28,000.00

BAHAN PLASTIK 1 Pipa PVC abu-abu dia. 1/2" Wavin btg 12,650.00 2 Pipa PVC abu-abu dia. 3/4" Wavin btg 17,000.00 3 Pipa PVC abu-abu dia. 1" Wavin btg 20,500.00 4 Pipa PVC abu-abu dia. 1 1/2" Wavin btg 45,000.00 5 Pipa PVC abu-abu dia. 2" Wavin btg 60,000.00 6 Pipa PVC abu-abu dia. 2 1/2" Wavin btg 82,000.00 7 Pipa PVC abu-abu dia. 3" Wavin btg 82,000.00 8 Pipa PVC abu-abu dia. 4" Wavin btg 135,000.00 9 Pipa PVC putih dia. 1/2" Wavin btg 12,000.00 10 Pipa PVC putih dia. 3/4" Wavin btg 15,000.00 11 Pipa PVC putih dia. 1" Wavin btg 21,000.00 12 Pipa PVC putih medium dia. 3" Wavin btg 48,000.00 13 Pipa PVC putih tebal dia. 3" Wavin btg 80,000.00 14 Pipa PVC putih medium dia. 4" Wavin btg 135,000.00 15 Pipa PVC putih tebal dia. 4" Wavin btg 157,000.00 16 Atap plastik gelombang PVC lbr 67,500.00

TANAMAN HIAS / PERINDANG TANAMAN PERINDANG

1 Angsana, tinggi +/- 2m dia 5 cm batang 75,000.00 2 Asem jawa, tinggi +/- 1,5 m dia 2 cm batang 20,000.00 3 Bauhmis (Orchid tree), tinggi +/- 2 m dia 2 cm batang 17,500.00 4 Beringin, tinggi +/- 1 m dia 2 cm putih batang 50,000.00 5 Beringin, tinggi +/- 2 m dia 3 cm putih batang 125,000.00 6 Biola cantik, tinggi +/- 3 m dia 5 cm batang 300,000.00 7 Biola cantik, tinggi +/- 1,5 m ia 3 cm batang 75,000.00 8 Filisium, tinggi +/- 1,5 m dia 2 cm batang 20,000.00 9 Gayam, tinggi +/- 1,5 m dia 2 cm batang 20,000.00 10 Gidogan Biasa, tinggi +/- 1 m dia 1,5 cm batang 20,000.00 11 Kenari, tinggi +/- 1,5 m dia 2 cm batang 16,000.00 12 Kepel, tinggi +/- 1,5 m dia 3 cm batang 40,000.00 13 Ketepang, tinggi +/- 1,5 m dia 2 cm batang 17,500.00 14 Mahoni, tinggi +/- 1,5 m dia 2 cm batang 25,000.00 15 Sawo Kecik, tinggi +/- 1,5 m dia 2 cm batang 17,500.00 16 Sentul, tinggi +/- 1,5 m dia 2 cm batang 20,000.00 17 Tanjung, tinggi +/- 1 m dia 2 cm batang 25,000.00 18 Tanjung, tinggi +/- 3 m dia 3 cm batang 75,000.00 19 Beringin , tinggi +/- 2-3 m batang 150,000.00 20 Beringin, tinggi +/- 3 m dia 4 cm batang 300,000.00

TANAMAN HIAS RUMPUT

1 Rumput Gajah (tanam) 12,000.00

2 Rumput Gajah (gebalan) 15,000.00

3 Rumput Manila (gebalan) 10,000.00

4 Rumput golf 11,000.00

5 Rumput gebalan 5,000.00

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 20: AHS 2008-Kota.xlsx

Bahan - 20

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

PERDU 1 Bougenville, tinggi +/- 0, 5 m batang 40,000.00 2 Bougenville, tinggi +/- 0, 7 m batang 70,000.00 3 Bougenville, tinggi +/- 1, 0 m batang 100,000.00 4 Bougenville varigata, tinggi +/- 0, 8 m batang 150,000.00 5 Classia planisicua, tinggi +/- 0,5 m batang 15,000.00 6 Kembang Sepatu (Bangkok), tinggi +/- 0,2 m batang 10,000.00 7 Kembang Sepatu (lokal), tinggi +/- 0,4 m batang 5,000.00 8 Mawar, tinggi +/- 0,25 m batang 7,500.00 9 Palem botol, tinggi +/- 0,8 m kecil 15 cm rumpun 150,000.00 10 Palem kuning, tinggi +/- 0,6 m rumpun 12,500.00 11 Palem kuning, tinggi +/- 1 m rumpun 20,000.00 12 Palem kuning, tinggi +/- 1,5 - 2 m rumpun 125,000.00 13 Palem kuning, tinggi +/- 2 - 3 m rumpun 175,000.00 14 Palem merah, tinggi +/- 2 - 3 m rumpun 150,000.00 15 Palem wregu, tinggi +/- 0,6 m rumpun 15,000.00 16 Palem putri, tinggi +/- 1 m rumpun 75,000.00 17 Soka pagar, 0,3 m batang 5,000.00 18 Serut, tinggi +/- 1 - 1,5 m batang 450,000.00 19 Puring bangkok, tinggi +/- 0,6 m batang 12,500.00 20 Phonik, tinggi +/- 1 m batang 150,000.00 21 Batavia / Jatropa, tinggi +/- 0,5 m batang 15,000.00 22 Serut, tinggi +/- 1,5 m batang 750,000.00

POHON 1 Cemara kipas, tinggi +/- 0,5 m batang 20,000.00 2 Cemara kipas, tinggi +/- 1,5 m batang 75,000.00 3 Cemara lilin, tinggi +/- 1,5 m batang 40,000.00 4 Cemara rantes, tinggi +/- 1 m batang 40,000.00 5 Cemara udang, tinggi +/- 1 - 1,5 m batang 600,000.00 6 Cemara norvox, tinggi +/- 0,6 m batang 50,000.00 7 Cemara norvox, tinggi +/- 1,5 m batang 80,000.00 8 Cempokok mulyo, tinggi +/- 0,5 m batang 15,000.00 9 Cempokok mulyo, tinggi +/- 1 m batang 40,000.00 10 Ceplok Piring, tinggi +/- 0,5 m batang 7,500.00 11 Ceplok Piring, tinggi +/- 1 m batang 20,000.00 12 Glodogan Pecut, tinggi +/- 1 m batang 14,000.00 13 Glodogan Pecut, tinggi +/- 2 m batang 25,000.00 14 Kelapa gading, tinggi +/- 3 m batang 200,000.00 15 Nusa indah, tinggi +/- 0,5 m batang 10,000.00 16 Nusa indah, tinggi +/- 1 m batang 30,000.00 17 Palem ekor tupai, tinggi +/- 1 m batang 75,000.00 18 Palem ekor tupai, tinggi +/- 2 m batang 150,000.00 19 Palem jepang, tinggi +/- 1 m rumpun 50,000.00 20 Palem jepang, tinggi +/- 2 m rumpun 100,000.00 21 Palem raja, tinggi +/- 4 m batang 150,000.00 22 Palem raja, tinggi +/- 6 m batang 250,000.00 23 Palem raja, tinggi +/- 7 m batang 1,500,000.00

SEMAK 1 Alamanda, tinggi +/- 0,2 m rumpun 5,000.00 2 Canna holland, tinggi +/- 0,3 m rumpun 15,000.00 3 Canna lokal, tinggi +/- 0,5 m rumpun 7,500.00 4 Cendrawasih, tinggi +/- 0,2 m batang 5,000.00 5 Cantik manis, tinggi +/- 0,2 m batang 3,000.00 6 Dieffenbachia, tinggi +/- 0,2 m batang 10,000.00 7 Dieffenbachia, tinggi +/- 0,5 m batang 20,000.00 8 Hanjuang, tinggi +/- 0,3 m batang 3,000.00 9 Helogenia, tinggi +/- 0,4 m rumpun 4,000.00 10 Kayu besi, tinggi +/- 0,5 m batang 7,500.00

Page 21: AHS 2008-Kota.xlsx

Bahan - 21

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

11 Kuping gajah, tinggi +/- 0,3 m rumpun 7,500.00 12 Lantana, tinggi +/- 0,2 m rumpun 4,000.00 13 Lantana, tinggi +/- 0,3 m rumpun 5,000.00 14 Yuliana rumpun 5,000.00 15 Iler rumpun 5,000.00 16 Yuca, tinggi +/- 0,4 m batang 30,000.00 17 Yuca, tinggi +/- 0,75 m batang 70,000.00 18 Melati, tinggi +/- 0,2 m batang 10,000.00 19 Phylodendron, tinggi +/- 0,4 m rumpun 7,500.00 20 Phylodendron, tinggi +/- 0,7 m rumpun 15,000.00 21 Sansiswa rumpun 7,500.00 22 Sirig gading, tinggi +/- 0,3 m rumpun 3,000.00 23 Soka bangkok, tinggi +/- 0,2 m batang 7,500.00 24 Soka jepang, tinggi +/- 0,2 m batang 3,000.00 25 Stevanut, tinggi +/- 0,3 m batang 12,500.00 26 Taiwan beauty, tinggi +/- 0,2 m rumpun 3,000.00 27 Teh-tehan hijau bulat, tinggi +/- 0,3 m batang 5,000.00 28 Teh-tehan hijau bulat, tinggi +/- 0,5 m batang 20,000.00 29 Teh-tehan hijau bulat (pagar), tinggi +/- 0,4 m batang 3,000.00 30 Teh-tehan hijau bulat (pagar), tinggi +/- 0,3 m batang 1,000.00 31 Teh-tehan kuning, tinggi +/- 0,2 m batang 500.00 32 Teh-tehan kuning bulat, tinggi +/- 0,3 m batang 5,000.00 33 Tri colour, tinggi +/- 0,3 m batang 12,500.00 34 Dracaena, tinggi +/- 0,8 m rumpun 15,000.00 35 Bambu pangkas, tinggi +/- 0,2 m batang 12,000.00 36 Patah tulang, tinggi +/- 0,3 m rumpun 3,000.00 37 Kuncira, tinggi +/- 0,3 m rumpun 3,000.00 38 Varent, tinggi +/- 0,3 m rumpun 4,000.00 39 Anthurium tinggi +/- 0,3 m rumpun 20,000.00 40 Bakung tinggi +/- 0,3 m rumpun 4,000.00 41 Nanas merah tinggi +/- 0,2 m rumpun 25,000.00 42 Nanas kuning tinggi +/- 0,2 m rumpun 15,000.00 43 Krisdoren tinggi +/- 0,2 m rumpun 20,000.00

TANAMAN PENUTUP TANAH 1 Adam eva kecil tinggi +/- 0,1 m rumpun 1,500.00 2 Adam eva besar tinggi +/- 0,2 m rumpun 4,000.00 3 Agave, tinggi +/- 0,4 m rumpun 50,000.00 4 Agave, tinggi +/- 0,2 m rumpun 20,000.00 5 Andong, tinggi +/- 0,3 m batang 2,000.00 6 Andong, tinggi +/- 0,2 m batang 1,500.00 7 Aponika, tinggi +/- 0,2 m rumpun 500.00 8 Portulaka rendah/pendek rumpun 2,000.00 9 Portulaka bangkok rumpun 4,000.00 10 Lili paris rumpun 1,500.00 11 Mega mendung, tinggi +/- 0,3 m batang 7,500.00 12 Modogras, tinggi +/- 0,2 m rumpun 800.00 13 Suplier, tinggi +/- 0,4 m rumpun 20,000.00 14 Terang bulan, tinggi +/- 0,4 m rumpun 8,000.00 15 Lili paris brasil tinggi +/- 0,3 m rumpun 4,500.00 16 Pupuk kandang kg 500.00

17 Tanah untuk media tanam 60,000.00 m3

Page 22: AHS 2008-Kota.xlsx

Bahan - 22

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

PERALATAN KEBERSIHAN 1 Sapu lidi bh 3,000.00 2 Tangkai Sapu bh 5,000.00 3 Tomblok bh 3,500.00 4 Hareg bh 3,000.00 5 Kerug bh 5,000.00 6 Seragam bh 75,000.00 7 Sarung tangan bh 7,500.00 8 Masker bh 7,500.00 9 Gerobak (alat baru) bh 1,500,000.00 10 Gerobak (sewa) bh 1,500.00 11 Serok bh 5,000.00 12 Gunting pangkas bh 35,000.00 13 Mesin potong rumput bh 3,000,000.00 14 Gathul bh 10,000.00 15 Garpu tanah bh 15,000.00 16 Arit bh 20,000.00 17 Gerobak celeng bh 400,000.00 18 Sepatu ps 75,000.00 19 Ember bh 5,000.00 20 Bagor bh 600.00 21 Irus bh 10,000.00 22 Cetok bh 10,000.00 23 Linggis bh 35,000.00 24 Martil bh 10,000.00 25 Betel bh 12,000.00 26 Pacul bh 30,000.00 27 Sewa kendaraan untuk membuang lumpur hr 118,000.00 28 Gas oksigen 5 kg tb 15,000.00 29 Nipel bh 10,000.00 30 Pipa dia. 3/8" - 15 cm bh 1,500.00 31 Nitobond EC kg 100,000.00 32 Conbextra EP kg 200,000.00 33 Cebex 100 kg 150,000.00

34 Sewa Compressor untuk pekerjaan grouting hr 250,000.00 35 Sewa Mesin Grouting hr 150,000.00

36 Sewa mesin gerinda untuk pekerjaan grouting hr 100,000.00 37 Sewa mixer ubtuk pekerjaan grouting hr 6,000.00 38 Alat bantu pekerjaan grouting ls 5,000.00 39 Alat bantu pekerjaan pekerjaan marka ls 130,000.00 40 Alat bantu pekerjaan pekerjaan expantion joint ls 130,000.00

41 Pelapisan kedap air lantai dengan coating ( terpasang ) 40,000.00

42 Pelapisan kedap air lantai dengan membran ( terpasang ) 60,000.00

m2

m2

Page 23: AHS 2008-Kota.xlsx

Bahan - 23

NO. NAMA BARANG / BAHAN / TENAGA SATUAN HARGA SATUAN (Rp.)

LAIN-LAIN

1 Tiang bendera -Pondasi umpak buah 31,000.00 -Ompak ornamen buah 65,800.00 -Tiang galvanis 3" m' 23,375.00 -Bendera 120 x 180 buah 39,825.00

2 Rambu lalu lintas (terpasang) buah 150,000.00 3 Papan nama jalan (terpasang) buah 250,000.00 4 Sumur peresapan 5 m buah 495,000.00

5 17,250.00

6 16,500.00

7 Minyak Flux liter 12,000.00 8 Asbuton kg 2,350.00 9 Tumpuan konstruksi m 66,700.00 10 Kerikil sungai - royalty m3 5,750.00 11 Batu gunung - royalty m3 5,750.00 12 Uji test besi ( 3 sampel tiap jenis diameter benda uji ) set 150,000.00 13 Uji test aspal ttk 100,000.00 14 Sewa alat sondir hr 100,000.00 15 Sewa Scaffolding unit 20,000.00 16 Benda uji silinder beton bh 3,000.00 17 Biaya tes beton per benda uji bh 5,000.00 18 Biaya analisis tes beton perbeda uji bh 15,000.00

Air minum, instalasi dalam dengan pipa pralon 1" medium, acesories dihitung sendiri

m1

Air minum, instalasi luar dengan pipa pralon 1" medium, acesoris dihitung sendiri

m1

Page 24: AHS 2008-Kota.xlsx

HARGA ALAT UNTUK PEKERJAAN ANALISA - E

NO. MACAM ALAT SATUAN HARGA KETERANGAN

1 Mesin penyampur aspal (AMP) E01 Unit 7,500,000,000.00 Alat Baru 2 Aspahlt Finisher E02 Unit 715,000,000.00 Alat Baru 3 Mesin penyemprot aspal 800 liter (Asphlt Sprayer) E03 Unit 145,000,000.00 Alat Baru 4 Buldozer 100 - 150 HP E04 Unit 700,000,000.00 Alat Baru 5 Compressor 4000 - 6500 L/M E05 Unit 175,000,000.00 Alat Baru 6 Concrette Mixer 0,3 - 0,6 m3 E06 Unit 45,000,000.00 Alat Baru 7 Crane 10 - 15 Ton E07 Unit 300,000,000.00 Alat Baru 8 Dump Truck 3 - 4 M3 E08 Unit 100,000,000.00 Alat Baru 9 Dump Truck 8 ton 125 HP E09 Unit 145,000,000.00 Alat Baru 10 Excavator 80 - 140 HP E10 Unit 250,000,000.00 Alat Baru 11 Flat Bed Truck (Truk Bak Terbuka) 3 - 4 m3 E11 Unit 250,000,000.00 Alat Baru 12 Genset 125 KVA E12 Unit 440,000,000.00 Alat Baru 13 Motor Grader > 100 HP E13 Unit 880,000,000.00 Alat Baru 14 Track Loader 75 - 100 HP E14 Unit 300,000,000.00 Alat Baru 15 Wheel Loader 105 HP E15 Unit 840,000,000.00 Alat Baru 16 Mesin Gilas 3 Roda 8 - 10 ton (Three Wheel Roller) E16 Unit 125,000,000.00 Alat Baru 17 Mesin Gilas Tandem 6 - 8 ton (Tandem Roller) E17 Unit 460,000,000.00 Alat Baru 18 Mesin Roda Karet 8 - 10 ton (Pneumatic Tyre Roller) E18 Unit 510,000,000.00 Alat Baru 19 Mesin Gilas getar otomatis 5 - 8 T E19 Unit 500,000,000.00 Alat Baru 20 Alat penggetar beton 4 HP (Concrette Vibrator) E20 Unit 12,000,000.00 Alat Baru 21 Pemecah batu 220 HP (Stone Crusher) E21 Unit 491,500,000.00 Alat Baru 22 Water Pump / Pompa Air 70 - 100 mm E22 Unit 5,000,000.00 Alat Baru 23 Truk tangki air 100 HP 4000 L (Water Tank Truck ) E23 Unit 50,000,000.00 Alat Baru 24 Stamper 5 HP E25 Unit 3,000,000.00 Alat Baru 25 Jack Hammer E26 Unit 3,500,000.00 Alat Baru 26 Fulvi Mixer E27 Unit 100,000,000.00 Alat Baru

27 Mesin penyaring 8 HP jam 50,000.00 Sewa28 Chip Spreader jam 50,000.00 Sewa29 Mesin penghampar 1820 MM 30 HP jam 181,000.00 Sewa30 Thriller gandeng 1 ton jam 184,000.00 Sewa31 Dump Truck 3,5 ton 44 HP jam 118,000.00 Sewa

32 jam 11,000.00 Sewa33 Thriller 1ton jam 15,000.00 Sewa34 Traktor jam 15,000.00 Sewa35 Alat Bor jam 150,000.00 Sewa36 Alat Ukur jam 75,000.00 Sewa37 Beton Molen jam 25,000.00 Sewa38 Mata Cutter bh 1,000,000.00 baru39 Mesin Cutter jam 60,000.00 Sewa40 Motor Walls jam 20,000.00 Sewa41 Peralatan Las jam 75,000.00 Sewa42 Sprayer jam 48,000.00 Sewa43 Alat bantu untuk pekerjaan analisa - E ls 500.00

Pompa air (D 5 cm) 30 m3 / jam

Page 25: AHS 2008-Kota.xlsx

Analisa Gedung - 25

ANALISA SATUAN PEKERJAANNo. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

PEKERJAAN PERSIAPAN

AK 100.00 Pekerjaan Pengukuran Gedung 8.0000 org Pekerja @ Rp. 36,000.00 288,000.00 - 2.0000 org Mandor @ Rp. 40,000.00 80,000.00 - 0.5000 org Pengawas @ Rp. 50,000.00 25,000.00 - 2.0000 org Asisten Ahli Ukur @ Rp. 95,000.00 190,000.00 - 1.0000 hr Sewa alat ukur @ Rp. 75,000.00 75,000.00 -

JUMLAH ( BELUM PPN ) 658,000.00 - JASA 10 %JUMLAHDIBULATKAN

1.0000 Pekerjaan Pengukuran0.01 x 723,800.00 7,238.00 -

SNI 1.0000 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran

6.4 0.0120 Kayu meranti 5/7 @ Rp. 2,750,000.00 33,000.00 03-2835-2002 0.0200 kg Paku reng @ Rp. 8,000.00 160.00

0.0070 Kayu meranti papan 3/20 @ Rp. 2,750,000.00 19,250.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 52,410.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membersihkan lapangan dan perataan6.8 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00

03-2835-2002 0.0500 org Mandor @ Rp. 40,000.00 2,000.00 JUMLAH ( BELUM PPN ) 5,600.00 - JASA 10 %JUMLAHDIBULATKAN

A4 1.0000 bh Membuat Papan Nama Proyek 80x120 cm

0.0350 Kayu meranti @ Rp. 2,750,000.00 96,250.00

1.4000 Seng plat lebar 90 cm @ Rp. 25,000.00 35,000.00 0.6000 kg Paku @ Rp. 10,000.00 6,000.00 1.5000 kg Cat kayu @ Rp. 29,500.00 44,250.00 16.8000 kg PC @ Rp. 764.00 12,835.20

0.0270 Pasir beton @ Rp. 73,000.00 1,971.00

0.0405 Kerikil beton @ Rp. 78,650.00 3,185.33 0.0175 org Tukang batu @ Rp. 42,500.00 743.75 1.0000 org Tukang kayu @ Rp. 47,500.00 47,500.00 1.0000 org Tukang cat @ Rp. 42,500.00 42,500.00 2.1000 org Pekerja @ Rp. 36,000.00 75,600.00 1.0050 org Mandor @ Rp. 40,000.00 40,200.00

JUMLAH ( BELUM PPN ) 206,543.75 199,491.53 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan jalan sementara, tebal 25 cm

6.16 0.2750 Batu belah @ Rp. 80,000.00 22,000.00

0.0300 Kerikil @ Rp. 78,650.00 2,359.50

0.0500 Pasir @ Rp. 76,000.00 3,800.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 40,000.00 28,159.50 JASA 10 %JUMLAH

m2

m2

m1

m3

m3

m2

m3

m1

m3

m3

m2

m3

m3

m3

Page 26: AHS 2008-Kota.xlsx

Analisa Gedung - 26

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 27: AHS 2008-Kota.xlsx

Analisa Gedung - 27

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pembuatan kantor sementara, dengan lantai plesteran6.5 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 10,000.00 12,500.00

03-2835-2002 0.1800 Kayu meranti @ Rp. 2,750,000.00 495,000.00 0.8500 kg Paku biasa @ Rp. 8,000.00 6,800.00 1.1000 kg Baja strip @ Rp. 8,800.00 9,680.00 35.0000 kg PC @ Rp. 764.00 26,740.00

0.1500 Pasir pasang @ Rp. 76,000.00 11,400.00

0.1000 Pasir beton @ Rp. 73,000.00 7,300.00

0.1500 Kerikil beton @ Rp. 78,650.00 11,797.50 30.0000 bh Bata merah @ Rp. 350.00 10,500.00 0.2500 lbr Seng plat 3" x 6 " @ Rp. 38,500.00 9,625.00 2.0000 bh Jendela nako @ Rp. 20,000.00 40,000.00

0.0800 Kaca polos @ Rp. 60,500.00 4,840.00 0.1500 bh Kunci tanam @ Rp. 35,000.00 5,250.00 0.0600 lbr Plywood 4 mm @ Rp. 41,250.00 2,475.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.3000 org Kepala tukang @ Rp. 50,000.00 15,000.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 226,500.00 653,907.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter6.2 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 10,000.00 12,500.00

03-2835-2002 2.5000 kg PC @ Rp. 764.00 1,910.00 1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. 25,000.00 30,000.00

0.0050 Pasir beton @ Rp. 73,000.00 365.00

0.0090 Kerikil beton @ Rp. 78,650.00 707.85

0.0250 Kaso 5/7 kayu meranti @ Rp. 2,750,000.00 68,750.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.4000 kg Meni besi @ Rp. 15,000.00 6,000.00 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 25,700.00 120,712.85 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter6.3 1.0000 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 10,000.00 10,000.00

03-2835-2002 2.0000 kg PC @ Rp. 764.00 1,528.00 25.0000 kg Kawat duri @ Rp. 9,500.00 237,500.00

0.0050 Pasir beton @ Rp. 73,000.00 365.00

0.0090 Kerikil beton @ Rp. 78,650.00 707.85 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 22,100.00 250,580.85 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m3

m3

m3

m2

m1

m3

m3

m3

m1

m3

m3

Page 28: AHS 2008-Kota.xlsx

Analisa Gedung - 28

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pembuatan gudang semen dan alat-alat6.6 1.7000 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 10,000.00 17,000.00

03-2835-2002 0.2100 Kayu @ Rp. 2,750,000.00 577,500.00 0.3000 kg Paku biasa @ Rp. 8,000.00 2,400.00 10.5000 kg PC @ Rp. 764.00 8,022.00

0.0300 Pasir beton @ Rp. 73,000.00 2,190.00

0.0500 Kerikil beton @ Rp. 78,650.00 3,932.50 1.5000 lbr Seng gelombang BJLS 32 @ Rp. 38,500.00 57,750.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 143,000.00 668,794.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan rumah jaga/konstruksi kayu6.7 3.0000 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 10,000.00 30,000.00

03-2835-2002 0.2760 Kayu @ Rp. 2,750,000.00 759,000.00 0.7000 kg Paku biasa @ Rp. 8,000.00 5,600.00 1.5000 lbr Seng gelombang BJLS 32 @ Rp. 38,500.00 57,750.00 1.5000 org Tukang kayu @ Rp. 47,500.00 71,250.00 0.1500 org Kepala tukang kayu @ Rp. 50,000.00 7,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 116,750.00 852,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan bedeng buruh6.9 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 10,000.00 12,500.00

03-2835-2002 0.1860 Kayu @ Rp. 2,750,000.00 511,500.00 0.3000 kg Paku biasa @ Rp. 8,000.00 2,400.00 18.0000 kg PC @ Rp. 764.00 13,752.00

0.0300 Pasir beton @ Rp. 73,000.00 2,190.00

0.0500 Kerikil beton @ Rp. 78,650.00 3,932.50 1.5000 lbr Seng gelombang BJLS 32 @ Rp. 38,500.00 57,750.00 4.3500 lbr Plywood 4 mm @ Rp. 41,250.00 179,437.50 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 143,000.00 783,462.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan bak adukan, uk. 40 x 50 x 20 cm

6.10 0.0360 Kayu terentang @ Rp. 2,750,000.00 99,000.00 03-2835-2002 0.0800 kg Paku @ Rp. 8,000.00 640.00

1.0000 btg Kaso 5/7 @ Rp. 15,225.00 15,225.00 0.3000 org Tukang kayu @ Rp. 47,500.00 14,250.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 14,310.00 114,865.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m3

m2

m3

m2

m3

m3

m3

m2

m3

Page 29: AHS 2008-Kota.xlsx

Analisa Gedung - 29

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pembuatan stegger dari bambu, ukuran 40 x 50 x 20 cm6.11 1.0000 btg Bambu @ Rp. 9,500.00 9,500.00

03-2835-2002 0.2500 kg Tali ijuk @ Rp. 9,000.00 2,250.00 0.0170 org Tukang kayu @ Rp. 47,500.00 807.50 0.0020 org Kepala tukang kayu @ Rp. 50,000.00 100.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 10,427.50 11,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pagar kawat jaring galvanis, tinggi 1,00 m6.15 0.4340 lbr Pagar kawat jaring @ Rp. 35,000.00 15,190.00

03-2835-2002 0.0420 org Tukang besi @ Rp. 45,000.00 1,890.00 0.0040 org Kepala tukang besi @ Rp. 47,500.00 190.00 0.0420 org Pekerja @ Rp. 36,000.00 1,512.00 0.0020 org Mandor @ Rp. 40,000.00 80.00

JUMLAH ( BELUM PPN ) 3,672.00 15,190.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm6.16 0.9860 lbr Panel beton pracetak @ Rp. 350,000.00 345,100.00

03-2835-2002 0.5250 btg Kolom beton pracetak @ Rp. 500,000.00 262,500.00

0.0740 Pasir beton @ Rp. 73,000.00 5,402.00

0.1460 Batu pecah 2/3 @ Rp. 138,000.00 20,148.00 45.0000 kg PC @ Rp. 764.00 34,380.00 0.1250 org Tukang batu @ Rp. 42,500.00 5,312.50 0.0120 org Kepala tukang @ Rp. 45,000.00 540.00 0.3750 org Pekerja @ Rp. 36,000.00 13,500.00 0.0190 org Mandor @ Rp. 40,000.00 760.00

JUMLAH ( BELUM PPN ) 20,112.50 667,530.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN TANAH

SNI 1.0000 Galian tanah biasa sedalam sampai 1 meter6.1 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00

0.0400 org Mandor @ Rp. 40,000.00 1,600.00 JUMLAH ( BELUM PPN ) 16,000.00 - JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah biasa sedalam 1 - 2 meter6.2 0.5260 org Pekerja @ Rp. 36,000.00 18,936.00

0.0526 org Mandor @ Rp. 40,000.00 2,104.00 JUMLAH ( BELUM PPN ) 21,040.00 - JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah biasa sedalam 2 - 3 meter6.3 0.7350 org Pekerja @ Rp. 36,000.00 26,460.00

0.0735 org Mandor @ Rp. 40,000.00 2,940.00 JUMLAH ( BELUM PPN ) 29,400.00 - JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m3

m3

m3

m3

m3

Page 30: AHS 2008-Kota.xlsx

Analisa Gedung - 30

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Galian tanah keras sedalam sampai 1 meter6.4 0.6250 org Pekerja @ Rp. 36,000.00 22,500.00

0.0620 org Mandor @ Rp. 40,000.00 2,480.00 JUMLAH ( BELUM PPN ) 24,980.00 - JASA 10 %JUMLAH 1.22 DIBULATKAN

SNI 1.0000 Galian tanah cadas sedalam sampai 1 meter6.5 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00

0.1250 org Mandor @ Rp. 40,000.00 5,000.00 JUMLAH ( BELUM PPN ) 50,000.00 - JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah lumpur sedalam 1 meter6.6 0.8230 org Pekerja @ Rp. 36,000.00 29,628.00

0.0830 org Mandor @ Rp. 40,000.00 3,320.00 JUMLAH ( BELUM PPN ) 32,948.00 - JASA 10 %JUMLAHDIBULATKAN

Mod. SNI 6.3 1.0000 Membuat sumur 2.0000 bh Buis beton D. 80 cm @ Rp. 45,000.00 90,000.00 1.0000 org Tukang gali sumur @ Rp. 45,000.00 45,000.00 0.7350 org Pekerja @ Rp. 36,000.00 26,460.00 0.0735 org Mandor @ Rp. 40,000.00 2,940.00

JUMLAH ( BELUM PPN ) 74,400.00 90,000.00 JASA 10 %JUMLAHDIBULATKAN

A6 1.0000 Mengangkut tanah sejauh 30 meter 0.3300 org Pekerja @ Rp. 36,000.00 11,880.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,280.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuangan tanah sejauh 150 meter6.8 0.5160 org Pekerja @ Rp. 36,000.00 18,576.00

0.0500 org Mandor @ Rp. 40,000.00 2,000.00 JUMLAH ( BELUM PPN ) 20,576.00 - JASA 10 %JUMLAHDIBULATKAN

A14 1.0000 Membuang tanah dengan menghampar 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 9,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Urug kembali bekas galian6.9 0.1920 org Pekerja @ Rp. 36,000.00 6,912.00

0.0190 org Mandor @ Rp. 40,000.00 760.00 JUMLAH ( BELUM PPN ) 7,672.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m1

m3

m3

m3

m3

Page 31: AHS 2008-Kota.xlsx

Analisa Gedung - 31

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Meratakan tanah ditumbuk halus 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 9,400.00 JASA 10 %JUMLAHDIBULATKAN

A18 1.0000 Urug pasir

1.2000 Pasir urug @ Rp. 55,000.00 66,000.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 11,200.00 66,000.00 JASA 10 %JUMLAHDIBULATKAN

MOD 1.0000 Urug tanah mendatangkan

A18 1.2000 Tanah urug @ Rp. 35,000.00 42,000.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 11,200.00 42,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Urugan sirtu

6.15 1.2000 Sirtu @ Rp. 66,000.00 79,200.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 10,000.00 79,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pemasangan lapisan ijuk

6.14 1.2000 Ijuk @ Rp. 75,000.00 90,000.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 6,000.00 90,000.00 JASA 10 %JUMLAHDIBULATKAN

MOD 1.0000 Gebalan rumputB3 0.2000 btg Bambu @ Rp. 7,000.00 1,400.00

1.0000 Gebalan rumput @ Rp. 5,000.00 5,000.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 19,000.00 6,400.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m3

m3

m3

m3

m3

m3

m3

m2

m2

Page 32: AHS 2008-Kota.xlsx

Analisa Gedung - 32

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

PEKERJAAN PASANGAN

SNI 1.0000 Pasangan pondasi batu kosong

6.14 1.2000 Batu belah 15/20 cm @ Rp. 80,000.00 96,000.00

03-2836-2002 0.3000 Pasir urug @ Rp. 55,000.00 16,500.00 0.3900 org Tukang batu @ Rp. 42,500.00 16,575.00 0.0390 org Kepala tukang batu @ Rp. 45,000.00 1,755.00 0.7800 org Pekerja @ Rp. 36,000.00 28,080.00 0.0390 org Mandor @ Rp. 40,000.00 1,560.00

JUMLAH ( BELUM PPN ) 47,970.00 112,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Kp : 1 Sm : 1 Ps

6.9 1.1000 Batu belah (hitam) 15/20 cm @ Rp. 80,000.00 88,000.00

03-2836-2002 0.2290 Kapurr pasang @ Rp. 72,500.00 16,602.50

0.2290 Semen merah @ Rp. 80,000.00 18,320.00

0.5440 Pasir pasang @ Rp. 76,000.00 41,344.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 164,266.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Kp : 1 Sm : 2 Ps

6.10 1.1000 Batu belah (hitam) 15/20 cm @ Rp. 80,000.00 88,000.00

03-2836-2002 0.1700 Kapurr pasang @ Rp. 72,500.00 12,325.00

0.1700 Semen merah @ Rp. 80,000.00 13,600.00

0.3400 Pasir pasang @ Rp. 76,000.00 25,840.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 139,765.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasangan pondasi 1 Pc : 3 Kp : 5 Ps

1.2000 Batu belah (hitam) 15/20 cm @ Rp. 80,000.00 96,000.00 95.4200 kg PC @ Rp. 764.00 72,900.88

0.2290 Kapurr pasang @ Rp. 72,500.00 16,602.50

0.3820 Pasir pasang @ Rp. 76,000.00 29,032.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 214,535.38 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 33: AHS 2008-Kota.xlsx

Analisa Gedung - 33

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasangan pondasi 1 Pc : 3 Kp : 10 Ps

6.12 1.1000 Batu belah (hitam) 15/20 cm @ Rp. 80,000.00 88,000.00 03-2835-2002 61.0000 kg PC @ Rp. 764.00 46,604.00

0.1470 Kapurr pasang @ Rp. 72,500.00 10,657.50

0.4920 Pasir pasang @ Rp. 76,000.00 37,392.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 182,653.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 4 Ps

6.5 1.1000 Batu belah 15/20 cm @ Rp. 80,000.00 88,000.00 03-2836-2002 163.0000 kg PC @ Rp. 764.00 124,532.00

0.5200 Pasir pasang @ Rp. 76,000.00 39,520.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 252,052.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 3 Ps

6.4 1.1000 Batu belah 15/20 cm @ Rp. 80,000.00 88,000.00 03-2836-2002 202.0000 kg PC @ Rp. 764.00 154,328.00

0.4850 Pasir pasang @ Rp. 76,000.00 36,860.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 279,188.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 1 Ps

6.1 1.1000 Batu belah 15/20 cm @ Rp. 80,000.00 88,000.00 03-2835-2002 392.0000 kg PC @ Rp. 764.00 299,488.00

0.3140 Pasir pasang @ Rp. 76,000.00 23,864.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 411,352.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 2 Ps

6.2 1.1000 Batu belah 15/20 cm @ Rp. 80,000.00 88,000.00 03-2835-2002 267.0000 kg PC @ Rp. 764.00 203,988.00

0.4270 Pasir pasang @ Rp. 76,000.00 32,452.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 324,440.00 JASA 10 %JUMLAH

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 34: AHS 2008-Kota.xlsx

Analisa Gedung - 34

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 35: AHS 2008-Kota.xlsx

Analisa Gedung - 35

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasangan pondasi 1 Pc : 5 Ps

6.6 1.1000 Batu belah 15/20 cm @ Rp. 80,000.00 88,000.00 03-2835-2002 136.0000 kg PC @ Rp. 764.00 103,904.00

0.5440 Pasir pasang @ Rp. 76,000.00 41,344.00 0.6000 org Tukang batu @ Rp. 42,500.00 25,500.00 0.0600 org Kepala tukang batu @ Rp. 45,000.00 2,700.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 85,200.00 233,248.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1Ps6.17 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 24,500.00

03-2837-2002 0.0180 Kapur pasang @ Rp. 72,500.00 1,305.00

0.0180 Semen merah @ Rp. 80,000.00 1,440.00

0.0180 Pasir pasang @ Rp. 76,000.00 1,368.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,820.00 28,613.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps6.15 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 24,500.00

03-2837-2002 4.5000 kg PC @ Rp. 764.00 3,438.00

0.0150 Kapur pasang @ Rp. 72,500.00 1,087.50

0.0500 Pasir pasang @ Rp. 76,000.00 3,800.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,820.00 32,825.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps6.11 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 24,500.00

03-2837-2002 11.5000 kg PC @ Rp. 764.00 8,786.00

0.0430 Pasir pasang @ Rp. 76,000.00 3,268.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,820.00 36,554.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps6.10 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 24,500.00

03-2837-2002 14.3700 kg PC @ Rp. 764.00 10,978.68

0.0400 Pasir pasang @ Rp. 76,000.00 3,040.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,820.00 38,518.68 JASA 10 %JUMLAH

m3

m3

m3

m2

m3

m3

m3

m2

m3

m3

m2

m3

m2

m3

Page 36: AHS 2008-Kota.xlsx

Analisa Gedung - 36

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 37: AHS 2008-Kota.xlsx

Analisa Gedung - 37

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps6.9 70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 24,500.00

03-2837-2002 18.9500 kg PC @ Rp. 764.00 14,477.80

0.0380 Pasir pasang @ Rp. 76,000.00 2,888.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM TERMASUK PPN ) 16,820.00 41,865.80 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps6.7 140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 49,000.00

03-2837-2002 10.0800 kg PC @ Rp. 764.00 7,701.12

0.0275 Kapur pasang @ Rp. 72,500.00 1,993.75

0.0925 Pasir pasang @ Rp. 76,000.00 7,030.00 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang batu @ Rp. 45,000.00 900.00 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 34,000.00 65,724.87 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps6.4 140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 49,000.00

03-2837-2002 26.4500 kg PC @ Rp. 764.00 20,207.80

0.0980 Pasir pasang @ Rp. 76,000.00 7,448.00 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang batu @ Rp. 45,000.00 900.00 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 34,000.00 76,655.80 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps6.3 140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 49,000.00

03-2837-2002 32.9500 kg PC @ Rp. 764.00 25,173.80

0.0910 Pasir pasang @ Rp. 76,000.00 6,916.00 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang batu @ Rp. 45,000.00 900.00 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 34,000.00 81,089.80 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps6.2 140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 49,000.00

03-2837-2002 43.5000 kg PC @ Rp. 764.00 33,234.00

0.0800 Pasir pasang @ Rp. 76,000.00 6,080.00 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang batu @ Rp. 45,000.00 900.00 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM TERMASUK PPN ) 34,000.00 88,314.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m3

m2

m3

m2

m3

m2

m3

Page 38: AHS 2008-Kota.xlsx

Analisa Gedung - 38

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasangan dinding bataco6.18 12.5000 bh Bataco @ Rp. 1,500.00 18,750.00

12.5000 kg PC @ Rp. 764.00 9,550.00

0.0400 Pasir pasang @ Rp. 76,000.00 3,040.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 23,700.00 31,340.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan roster 25/25 cm6.19 16.0000 bh Roster 25/25 cm @ Rp. 2,000.00 32,000.00

12.5000 kg PC @ Rp. 764.00 9,550.00

0.0400 Pasir pasang @ Rp. 76,000.00 3,040.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 23,700.00 44,590.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN BETON

SNI 1.0000 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr6.13 232.0000 kg PC @ Rp. 764.00 177,248.00

0.5200 Pasir beton @ Rp. 73,000.00 37,960.00

0.7800 Kerikil beton @ Rp. 78,650.00 61,347.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala tukang batu @ Rp. 45,000.00 1,125.00 1.6500 org Pekerja @ Rp. 36,000.00 59,400.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

JUMLAH ( BELUM PPN ) 74,350.00 276,555.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr6.1 218.0000 kg PC @ Rp. 764.00 166,552.00

0.5200 Pasir beton @ Rp. 73,000.00 37,960.00

0.8700 Kerikil beton @ Rp. 78,650.00 68,425.50 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala tukang batu @ Rp. 45,000.00 1,125.00 1.6500 org Pekerja @ Rp. 36,000.00 59,400.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

JUMLAH ( BELUM PPN ) 74,350.00 272,937.50 JASA 10 %JUMLAHDIBULATKAN

1.0000 m2 Membuat beton tumbuk 1:3:5 tebal 5cm 10.0000 kg PC @ Rp. 764.00 7,640.00

0.0239 Pasir beton @ Rp. 73,000.00 1,744.70

0.0399 Kerikil beton @ Rp. 78,650.00 3,138.13 0.0115 org Tukang batu @ Rp. 42,500.00 488.75 0.0011 org Kepala tukang batu @ Rp. 45,000.00 49.50 0.0757 org Pekerja @ Rp. 36,000.00 2,725.20 0.0037 org Mandor @ Rp. 40,000.00 148.00

JUMLAH ( BELUM PPN ) 3,411.45 12,522.84 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Beton cyclope 1pc:3ps:5kr

m2

m3

m2

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 39: AHS 2008-Kota.xlsx

Analisa Gedung - 39

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

0.7000 Batu kali (hitam) @ Rp. 80,000.00 56,000.00 61.2500 kg PC @ Rp. 764.00 46,795.00

0.4000 Pasir pasang @ Rp. 76,000.00 30,400.00

0.6500 Kerikil beton @ Rp. 78,650.00 51,122.50 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.1000 org Kep. Tk. Batu @ Rp. 45,000.00 4,500.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 275,000.00 184,317.50 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

Page 40: AHS 2008-Kota.xlsx

Analisa Gedung - 40

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Membuat beton bertulang, 1 Pc : 1,5 Ps : 2,5 Kr6.16 400.0000 kg PC @ Rp. 764.00 305,600.00

0.4800 Pasir beton @ Rp. 73,000.00 35,040.00

0.8000 Kerikil beton @ Rp. 78,650.00 62,920.00 0.3500 org Tukang batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala tukang batu @ Rp. 45,000.00 1,575.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 128,450.00 403,560.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat beton dengan mutu K 2256.35 388.0000 kg PC @ Rp. 764.00 296,432.00

0.6500 Pasir beton @ Rp. 73,000.00 47,450.00

0.6500 Kerikil beton @ Rp. 78,650.00 51,122.50 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.1000 org Kepala tukang batu @ Rp. 45,000.00 4,500.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 275,000.00 395,004.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat beton dengan mutu K 2756.36 400.0000 kg PC @ Rp. 764.00 305,600.00

0.4000 Pasir beton @ Rp. 73,000.00 29,200.00

0.8200 Kerikil beton @ Rp. 78,650.00 64,493.00 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.1000 org Kepala tukang batu @ Rp. 45,000.00 4,500.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 275,000.00 399,293.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Membuat beton dengan mutu K 300 430.0000 kg PC @ Rp. 764.00 328,520.00

0.5160 Pasir beton @ Rp. 73,000.00 37,668.00

0.6900 Kerikil beton @ Rp. 78,650.00 54,268.50 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.1000 org Kepala tukang batu @ Rp. 45,000.00 4,500.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 275,000.00 420,456.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 kg Pembesian dengan besi polos6.25 1.0500 kg Besi beton polos @ Rp. 7,900.00 8,295.00

0.0150 kg Kawat beton @ Rp. 9,400.00 141.00 0.0070 org Tukang besi @ Rp. 45,000.00 315.00 0.0007 org Kepala tukang besi @ Rp. 47,500.00 33.25 0.0070 org Pekerja @ Rp. 36,000.00 252.00 0.0003 org Mandor @ Rp. 40,000.00 12.00

JUMLAH ( BELUM PPN ) 612.25 8,436.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 41: AHS 2008-Kota.xlsx

Analisa Gedung - 41

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 kg Pembesian dengan besi ulir6.25 1.0500 kg Besi beton ulir @ Rp. 8,000.00 8,400.00

0.0150 kg Kawat beton @ Rp. 9,400.00 141.00 0.0070 org Tukang besi @ Rp. 45,000.00 315.00 0.0007 org Kepala tukang besi @ Rp. 47,500.00 33.25 0.0070 org Pekerja @ Rp. 36,000.00 252.00 0.0003 org Mandor @ Rp. 40,000.00 12.00

JUMLAH ( BELUM PPN ) 612.25 8,541.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 m2 Begesting untuk pondasi 0.0400 m3 Kayu terentang @ Rp. 1,000,000.00 40,000.00 0.3000 kg Paku biasa 2 - 5" @ Rp. 8,000.00 2,400.00 0.1000 ltr Minyak bekesting @ Rp. 5,000.00 500.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.2600 org Tukang kayu @ Rp. 42,500.00 11,050.00 0.0260 org Kepala tukang @ Rp. 45,000.00 1,170.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 23,220.00 42,900.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 m2 Begesting untuk sloof 0.0450 m3 Kayu terentang @ Rp. 1,000,000.00 45,000.00 0.3000 kg Paku biasa 2 - 5" @ Rp. 8,000.00 2,400.00 0.1000 ltr Minyak bekesting @ Rp. 5,000.00 500.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.2600 org Tukang kayu @ Rp. 42,500.00 11,050.00 0.0260 org Kepala tukang @ Rp. 45,000.00 1,170.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 23,220.00 47,900.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 m2 Pondasi untuk kolom 0.0400 m3 Kayu terentang @ Rp. 1,000,000.00 40,000.00 0.4000 kg Paku biasa 2 - 5" @ Rp. 8,000.00 3,200.00 0.2000 ltr Minyak bekesting @ Rp. 5,000.00 1,000.00 0.0150 m3 Balok kayu meranti @ Rp. 2,750,000.00 41,250.00 0.3500 lbr Plywood tebal 9 mm @ Rp. - 2.0000 btg Dolken /galam ø 8-10/4m @ Rp. 10,000.00 20,000.00 0.3300 org Pekerja @ Rp. 36,000.00 11,880.00 0.3300 org Tukang kayu @ Rp. 42,500.00 14,025.00 0.0330 org Kepala tukang @ Rp. 45,000.00 1,485.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 27,630.00 105,450.00 JASA 10 %JUMLAHDIBULATKAN

10.0000 m2 Pembongkaran begesting 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0250 org Tukang kayu @ Rp. 42,500.00 1,062.50 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 15,702.50 - JASA 10 %JUMLAH

1 m2 pembongkaran DIBULATKAN

F.8 1.0000 Cetakan beton / begisting memakai papan

0.0170 Usuk meranti @ Rp. 2,750,000.00 46,750.00

0.0240 Papan cetakan @ Rp. 1,000,000.00 24,000.00 0.4000 kg Paku @ Rp. 8,000.00 3,200.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kep. Tk. Kayu @ Rp. 50,000.00 2,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

m2

m3

m3

Page 42: AHS 2008-Kota.xlsx

Analisa Gedung - 42

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) JUMLAH ( BELUM PPN ) 33,850.00 73,950.00 JASA 10 %JUMLAHDIBULATKAN

F.8 1.0000 Cetakan beton / begisting memakai multiplek

0.0170 Usuk meranti @ Rp. 2,750,000.00 46,750.00 0.3470 lbr Multiplek @ Rp. 90,000.00 31,230.00 0.4000 kg Paku @ Rp. 8,000.00 3,200.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kep. Tk. Kayu @ Rp. 50,000.00 2,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 33,850.00 81,180.00 JASA 10 %JUMLAHDIBULATKAN

F.V 1.0000 Membongkar cetakan 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00

JUMLAH ( BELUM PPN ) 144,000.00 - JASA 10 %JUMLAHDIBULATKAN

Sup

muko2 0.7000 Perancah/dolken @ Rp. 1,000,000.00 700,000.00 hal 10.5000 org Tukang kayu @ Rp. 47,500.00 498,750.00 332 1.0500 org Kep. Tk. Kayu @ Rp. 50,000.00 52,500.00

3.5000 org Pekerja @ Rp. 36,000.00 126,000.00 0.1750 org Mandor @ Rp. 40,000.00 7,000.00

JUMLAH ( BELUM PPN ) 684,250.00 700,000.00 JASA 10 %JUMLAHDIBULATKAN

32.0000 unit Scafolding @ Rp. 20,000.00 640,000.00 3.5000 org Tukang kayu @ Rp. 47,500.00 166,250.00 0.3500 org Kep. Tk. Kayu @ Rp. 50,000.00 17,500.00 2.2000 org Pekerja @ Rp. 36,000.00 79,200.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM TERMASUK PPN ) 267,750.00 640,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m3

Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai dolken )

m3

Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai scafolding )

Page 43: AHS 2008-Kota.xlsx

Analisa Gedung - 43

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

REKAPITULASI (CONTOH UNTUK 100 KG BESI)

Pekerjaan beton bertulang 1:2:3 tanpa dolken, 100 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 100 kg 995,307.50

C. 1,185,800.00 D. Membongkar cetakan 158,400.00

JUMLAH 2,725,503.00 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 125 KG BESI)

Pekerjaan beton bertulang 1:2:3 tanpa dolken, 125 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 125 kg 1,244,134.38

C. 1,185,800.00 D. Membongkar cetakan 158,400.00

JUMLAH 2,974,329.88 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 150 KG BESI)

Pekerjaan beton bertulang 1:2:3 tanpa dolken, 150 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 150 kg 1,492,961.25

C. 1,185,800.00 E. Membongkar cetakan 158,400.00

JUMLAH 3,223,156.75 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 175 KG BESI)

Pekerjaan beton bertulang 1:2:3 tanpa dolken, 175 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 175 kg 1,741,788.13

C. 1,185,800.00 D. Membongkar cetakan 158,400.00

JUMLAH 3,471,983.63 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 200 KG BESI)

Pekerjaan beton bertulang 1:2:3 tanpa dolken, 200 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 200 kg 1,990,615.00

C. 1,185,800.00 D. Membongkar cetakan 158,400.00

JUMLAH 3,720,810.50 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 100 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 100 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 100 kg 995,307.50

C. 1,185,800.00 D. Stut werk / perancah 1,522,675.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,248,178.00 DIBULATKAN

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Page 44: AHS 2008-Kota.xlsx

Analisa Gedung - 44

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

REKAPITULASI (CONTOH UNTUK 125 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 125 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 125 kg 1,244,134.38

C. 1,185,800.00 D. Stut werk / perancah 1,522,675.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,497,004.88 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 150 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 150 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 150 kg 1,492,961.25

C. 1,185,800.00 D. Stut werk / perancah 1,522,675.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,745,831.75 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 175 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 175 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 175 kg 1,741,788.13

C. 1,185,800.00 D. Stut werk / perancah 1,522,675.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,994,658.63 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 200 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 200 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 200 kg 1,990,615.00

C. 1,185,800.00 D. Stut werk / perancah 1,522,675.00 E. Membongkar cetakan 158,400.00

JUMLAH 5,243,485.50 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 100 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 100 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 100 kg 995,307.50

C. 1,185,800.00 D. Scafolding / perancah 998,525.00 E. Membongkar cetakan 158,400.00

JUMLAH 3,724,028.00 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 125 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 125 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 125 kg 1,244,134.38

C. 1,185,800.00 D. Scafolding / perancah 998,525.00 E. Membongkar cetakan 158,400.00

JUMLAH 3,972,854.88 DIBULATKAN

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Page 45: AHS 2008-Kota.xlsx

Analisa Gedung - 45

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

REKAPITULASI (CONTOH UNTUK 150 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 150 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 150 kg 1,492,961.25

C. 1,185,800.00 D. Scafolding / perancah 998,525.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,221,681.75 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 175 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 175 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 175 kg 1,741,788.13

C. 1,185,800.00 D. Scafolding / perancah 998,525.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,470,508.63 DIBULATKAN

REKAPITULASI (CONTOH UNTUK 200 KG BESI)

Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 200 kg besiA. Beton cor 1pc:2ps:3kr 385,995.50 B. Tulangan 200 kg 1,990,615.00

C. 1,185,800.00 D. Scafolding / perancah 998,525.00 E. Membongkar cetakan 158,400.00

JUMLAH 4,719,335.50 DIBULATKAN

SNI 1.0000 Pembuatan tiang pancang (40 x 40) cm, beton bertulang

6.17 0.0190 Pasir urug @ Rp. 55,000.00 1,045.00

03-2836-2002 0.0940 Pasir beton @ Rp. 73,000.00 6,862.00

0.1500 Batu pecah 2/3 @ Rp. 138,000.00 20,700.00 60.5000 kg PC @ Rp. 764.00 46,222.00 45.0000 kg Besi beton @ Rp. 7,900.00 355,500.00 0.9000 kg Kawat beton @ Rp. 9,400.00 8,460.00

0.0320 Kayu kruing 5/7 @ Rp. 4,350,000.00 139,200.00 0.1200 kg Paku reng @ Rp. 8,000.00 960.00 0.0900 ltr Minyak bekisting @ Rp. 5,000.00 450.00 0.2400 kg Plamur tembok @ Rp. 24,000.00 5,760.00 0.6700 org Tukang batu @ Rp. 42,500.00 28,475.00 0.0670 org Kepala tukang batu @ Rp. 45,000.00 3,015.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 69,490.00 585,159.00 JASA 10 %JUMLAHDIBULATKAN

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

Cetakan memakai papan ( 10 m2 )

m1

m3

m3

m3

m3

Page 46: AHS 2008-Kota.xlsx

Analisa Gedung - 46

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pembuatan tiang pancang (35 x 35) cm, beton bertulang

6.18 0.0160 Pasir urug @ Rp. 55,000.00 880.00

03-2836-2002 0.0800 Pasir beton @ Rp. 73,000.00 5,840.00

0.1250 Batu pecah 2/3 @ Rp. 138,000.00 17,250.00 49.0000 kg PC @ Rp. 764.00 37,436.00 34.5000 kg Besi beton @ Rp. 7,900.00 272,550.00 0.7000 kg Kawat beton @ Rp. 9,400.00 6,580.00

0.0270 Kayu kruing 5/7 @ Rp. 4,350,000.00 117,450.00 0.1200 kg Paku @ Rp. 8,000.00 960.00 0.0900 ltr Minyak bekisting @ Rp. 5,000.00 450.00 0.2000 kg Plamur tembok @ Rp. 24,000.00 4,800.00 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kepala tukang batu @ Rp. 45,000.00 2,250.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 53,900.00 464,196.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN PELESTERAN

G.50.P 1.0000 Plesteran batu kali 1pc:1/2kp:5ps tebal 10 mm 5.1000 kg PC @ Rp. 764.00 3,896.40

0.0014 Kapur pasang @ Rp. 72,500.00 101.50

0.0136 Pasir pasang @ Rp. 76,000.00 1,033.60 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 5,031.50 JASA 10 %JUMLAHDIBULATKAN

G.50..I 1.0000 Plesteran batu kali 1pc:3ps 8.1600 kg PC @ Rp. 764.00 6,234.24

0.0194 Pasir pasang @ Rp. 76,000.00 1,474.40 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 7,708.64 JASA 10 %JUMLAHDIBULATKAN

G.50.q 1.0000 Plesteran batu kali 1pc:4ps 6.5110 kg PC @ Rp. 764.00 4,974.40

0.0209 Pasir pasang @ Rp. 76,000.00 1,588.40 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 6,562.80 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m3

m3

m3

m2

m3

m3

m2

m3

m2

m3

Page 47: AHS 2008-Kota.xlsx

Analisa Gedung - 47

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 15 mm

6.12 0.0070 Kapurr pasang @ Rp. 72,500.00 507.50

03-2837-2002 0.0070 Semen merah @ Rp. 80,000.00 560.00

0.0150 Pasir pasang @ Rp. 76,000.00 1,140.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala tukang batu @ Rp. 45,000.00 675.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 14,650.00 2,207.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 3 Kp : 10 Ps, tebal 15 mm6.9 1.8400 kg PC @ Rp. 764.00 1,405.76

03-2837-2002 0.0060 Kapurr pasang @ Rp. 72,500.00 435.00

0.0140 Pasir pasang @ Rp. 76,000.00 1,064.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala tukang batu @ Rp. 45,000.00 675.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM TERMASUK PPN ) 14,650.00 2,904.76 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 2 Ps, tebal 15 mm6.2 8.5200 kg PC @ Rp. 764.00 6,509.28

03-2837-2002 0.0170 Pasir pasang @ Rp. 76,000.00 1,292.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala tukang batu @ Rp. 45,000.00 675.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM TERMASUK PPN ) 14,650.00 7,801.28 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 3 Ps, tebal 15 mm6.3 6.4800 kg PC @ Rp. 764.00 4,950.72

03-2837-2002 0.0190 Pasir pasang @ Rp. 76,000.00 1,444.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala tukang batu @ Rp. 45,000.00 675.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 14,650.00 6,394.72 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 4 Ps, tebal 15 mm6.4 5.2000 kg PC @ Rp. 764.00 3,972.80

03-2837-2002 0.0200 Pasir pasang @ Rp. 76,000.00 1,520.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala tukang batu @ Rp. 45,000.00 675.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 14,650.00 5,492.80 JASA 10 % 163,500.00 JUMLAH 11.16 DIBULATKAN

m2

m3

m3

m3

m2

m3

m3

m2

m3

m2

m3

m2

m3

Page 48: AHS 2008-Kota.xlsx

Analisa Gedung - 48

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Plesteran beton 1 Pc : 3 Ps, tebal 15 mm6.30 7.0700 kg PC @ Rp. 764.00 5,401.48

03-2837-2002 0.0210 Pasir pasang @ Rp. 76,000.00 1,596.00 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang batu @ Rp. 45,000.00 900.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 19,280.00 6,997.48 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran skoneng 1 Pc : 2 Ps ( untuk gedung )6.31 0.5000 kg PC @ Rp. 764.00 382.00

03-2837-2002 0.0020 Pasir pasang @ Rp. 76,000.00 152.00 0.0380 org Tukang batu @ Rp. 42,500.00 1,615.00 0.0380 org Kepala tukang batu @ Rp. 45,000.00 1,710.00 0.0570 org Pekerja @ Rp. 36,000.00 2,052.00 0.0020 org Mandor @ Rp. 40,000.00 80.00

JUMLAH ( BELUM PPN ) 5,457.00 534.00 JASA 10 %JUMLAHDIBULATKAN

G.50.b 1.0000 Sponengan (untuk saluran dan sejenisnya) 0.3600 kg PC @ Rp. 764.00 275.04

0.0009 Pasir pasang @ Rp. 76,000.00 65.36 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kep. Tk. Batu @ Rp. 45,000.00 135.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM PPN ) 4,830.00 340.40 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran siar adukan 1 Pc : 2 Ps6.35 4.3200 kg PC @ Rp. 764.00 3,300.48

03-2837-2002 0.0160 Pasir pasang @ Rp. 76,000.00 1,216.00 0.0700 org Tukang batu @ Rp. 42,500.00 2,975.00 0.0070 org Kepala tukang batu @ Rp. 45,000.00 315.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 9,010.00 4,516.48 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran Ciprat, 1 Pc : 2 Ps6.34 4.3200 kg PC @ Rp. 764.00 3,300.48

0.0160 Pasir pasang @ Rp. 55,000.00 880.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 14,300.00 4,180.48 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m1

m3

m1

m3

m2

m3

m2

m3

Page 49: AHS 2008-Kota.xlsx

Analisa Gedung - 49

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

Analisa ZAZ 1.0000 Acian dinding bata 3.5000 kg PC @ Rp. 764.00 2,674.00 0.0330 org Tukang batu @ Rp. 42,500.00 1,402.50 0.0033 org Kep. Tk. Batu @ Rp. 45,000.00 148.50 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0035 org Mandor @ Rp. 40,000.00 140.00

JUMLAH ( BELUM PPN ) 4,211.00 2,674.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Plesteran K- 50, tebal 20 mm 11.1200 kg PC @ Rp. 764.00 8,495.68

0.0300 Pasir pasang @ Rp. 76,000.00 2,280.00 0.1800 org Tukang batu @ Rp. 42,500.00 7,650.00 0.0180 org Kepala tukang batu @ Rp. 45,000.00 810.00 0.3600 org Pekerja @ Rp. 36,000.00 12,960.00 0.0180 org Mandor @ Rp. 40,000.00 720.00

JUMLAH ( BELUM PPN ) 22,140.00 10,775.68 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding batu hias tempel

6.74 1.0500 Batu tempel hitam @ Rp. 60,000.00 63,000.00 11.7500 kg PC @ Rp. 764.00 8,977.00

0.0350 Pasir pasang @ Rp. 76,000.00 2,660.00 0.3500 org Tukang batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala tukang batu @ Rp. 45,000.00 1,575.00 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM TERMASUK PPN ) 41,050.00 74,637.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN PASANG TEGEL

AK 1.0000 Pasang tegel warna 30/30

1.0000 Tegel warna uk. 30/30 @ Rp. 37,600.00 37,600.00

0.0160 Kapur pasang @ Rp. 72,500.00 1,160.00

0.0320 Pasir pasang @ Rp. 76,000.00 2,432.00 1.0000 kg Semen warna @ Rp. 6,000.00 6,000.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 47,192.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang tegel abu-abu 30/30

1.0000 Tegel abu-abu uk. 30/30 @ Rp. 28,000.00 28,000.00

0.0160 Kapur pasang @ Rp. 72,500.00 1,160.00

0.0320 Pasir pasang @ Rp. 76,000.00 2,432.00 1.0000 kg PC @ Rp. 764.00 764.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 32,356.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m2

m2

m3

m2

m2

m3

m3

m2

m2

m3

m3

Page 50: AHS 2008-Kota.xlsx

Analisa Gedung - 50

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang tegel teraso 30/30

1.0000 Tegel teraso uk. 30/30 @ Rp. 32,000.00 32,000.00

0.0160 Kapur pasang @ Rp. 72,500.00 1,160.00

0.0320 Pasir pasang @ Rp. 76,000.00 2,432.00 1.0000 kg Semen putih @ Rp. 1,312.50 1,312.50 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 36,904.50 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang tegel abu-abu 20/20

1.0000 Tegel abu-abu uk. 20/20 @ Rp. 20,000.00 20,000.00

0.0160 Kapur pasang @ Rp. 72,500.00 1,160.00

0.0320 Pasir pasang @ Rp. 76,000.00 2,432.00 1.0000 kg PC @ Rp. 764.00 764.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 24,356.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang tegel warna 20/20

1.0000 Tegel warna uk. 20/20 @ Rp. 26,000.00 26,000.00

0.0160 Kapur pasang @ Rp. 72,500.00 1,160.00

0.0320 Pasir pasang @ Rp. 76,000.00 2,432.00 1.0000 kg Semen warna @ Rp. 6,000.00 6,000.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 35,592.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC abu-abu ukuran 10 x 20 cm6.16 5.3000 bh Plint ubin 10 x 20 cm @ Rp. 350.00 1,855.00

1.5600 kg PC @ Rp. 764.00 1,191.84

0.0030 Pasir pasang @ Rp. 76,000.00 228.00 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM TERMASUK PPN ) 3,690.00 3,274.84 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m3

m2

m2

m3

m3

m2

m2

m3

m3

m1

m3

Page 51: AHS 2008-Kota.xlsx

Analisa Gedung - 51

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang plint ubin PC abu-abu ukuran 10 x 30 cm6.17 3.5300 bh Plint ubin 10 x 30 cm @ Rp. 750.00 2,647.50

1.5600 kg PC @ Rp. 764.00 1,191.84

0.0030 Pasir pasang @ Rp. 76,000.00 228.00 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM TERMASUK PPN ) 3,690.00 4,067.34 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC warna ukuran 10 x 20 cm6.19 5.3000 bh Plint ubin pc warna 10 x 20 cm @ Rp. 400.00 2,120.00

1.2000 kg PC @ Rp. 764.00 916.80

0.0030 Pasir pasang @ Rp. 76,000.00 228.00 0.1900 kg Semen warna @ Rp. 6,000.00 1,140.00 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM TERMASUK PPN ) 3,690.00 4,404.80 JASA 10 %JUMLAHDIBULATKAN

6.20 1.0000 Pasang plint ubin PC warna ukuran 10 x 30 cm 3.3300 bh Plint ubin pc warna 10 x 30 cm @ Rp. 825.00 2,747.25 1.6500 kg PC @ Rp. 764.00 1,260.60

0.0032 Pasir pasang @ Rp. 76,000.00 243.20 0.1000 kg Semen warna @ Rp. 6,000.00 600.00 0.0300 oh Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 oh Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 oh Pekerja @ Rp. 36,000.00 2,160.00 0.0030 oh Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM TERMASUK PPN ) 3,690.00 4,851.05 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN KERAMIK

An. 1.0000 Pasang ubin porselin

G.69.c 1.0000 Tegel porselin @ Rp. 40,500.00 40,500.00 4.6800 kg PC @ Rp. 764.00 3,575.52

0.0090 Pasir pasang @ Rp. 76,000.00 684.00 1.0000 kg Semen putih @ Rp. 1,312.50 1,312.50 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kep. Tk. Batu @ Rp. 45,000.00 2,250.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 33,000.00 46,072.02 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m2

m2

m3

Page 52: AHS 2008-Kota.xlsx

Analisa Gedung - 52

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang tegel keramik 20/20 dan 30/30

1.0000 Tegel keramik (std) @ Rp. 42,500.00 42,500.00 4.0800 kg PC @ Rp. 764.00 3,117.12

0.0090 Pasir pasang @ Rp. 76,000.00 684.00 0.6000 kg Semen putih @ Rp. 1,312.50 787.50 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kep. Tk. Batu @ Rp. 45,000.00 2,250.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 33,000.00 47,088.62 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang tegel keramik 10/20 berglasir

1.0000 Tegel keramik 10/20 @ Rp. 30,000.00 30,000.00 4.0800 kg PC @ Rp. 764.00 3,117.12

0.0090 Pasir pasang @ Rp. 76,000.00 684.00 0.6000 kg Semen putih @ Rp. 1,312.50 787.50 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kep. Tk. Batu @ Rp. 45,000.00 2,250.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 33,000.00 34,588.62 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang tegel keramik 20/20 berglasir

1.0000 Tegel keramik 20/20 @ Rp. 32,000.00 32,000.00 4.0800 kg PC @ Rp. 764.00 3,117.12

0.0090 Pasir pasang @ Rp. 76,000.00 684.00 0.6000 kg Semen putih @ Rp. 1,312.50 787.50 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kep. Tk. Batu @ Rp. 45,000.00 2,250.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 33,000.00 36,588.62 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang tegel keramik 30/30 berglasir

1.0000 Tegel keramik 30/30 @ Rp. 32,500.00 32,500.00 4.0800 kg PC @ Rp. 764.00 3,117.12

0.0090 Pasir pasang @ Rp. 76,000.00 684.00 0.6000 kg Semen putih @ Rp. 1,312.50 787.50 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kep. Tk. Batu @ Rp. 45,000.00 2,250.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 33,000.00 37,088.62 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint keramik ukuran 10 x 40 cm

6.24 0.2300 Keramik 40/40 @ Rp. 40,000.00 9,200.00 1.2000 kg PC @ Rp. 764.00 916.80

0.0030 Pasir pasang @ Rp. 76,000.00 228.00 0.1000 kg Semen warna @ Rp. 6,000.00 600.00 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM TERMASUK PPN ) 3,690.00 10,944.80 JASA 10 %JUMLAH

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m1

m2

m3

Page 53: AHS 2008-Kota.xlsx

Analisa Gedung - 53

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 54: AHS 2008-Kota.xlsx

Analisa Gedung - 54

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang plint keramik ukuran 10 x 30 cm

6.25 0.1800 Keramik 30/30 @ Rp. 32,500.00 5,850.00 1.6500 kg PC @ Rp. 764.00 1,260.60

0.0032 Pasir pasang @ Rp. 76,000.00 243.20 0.1000 kg Semen warna @ Rp. 6,000.00 600.00 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM TERMASUK PPN ) 3,690.00 7,953.80 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang keramik stepnosing granito 5/30 3.6000 bh Stepnosing granito @ Rp. 9,350.00 33,660.00 0.4080 kg PC @ Rp. 764.00 311.71

0.0009 Pasir @ Rp. 76,000.00 68.40 0.0600 kg Semen putih @ Rp. 1,312.50 78.75 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,600.00 34,118.86 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang list keramik dinding 5/20 5.0000 bh List keramik dinding motif @ Rp. 5,000.00 25,000.00 0.4080 kg PC @ Rp. 764.00 311.71

0.0009 Pasir @ Rp. 76,000.00 68.40 0.0600 kg Semen putih @ Rp. 1,312.50 78.75 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,600.00 25,458.86 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang keramik dinding 20/25

1.0000 Tegel keramik 20/25 @ Rp. 42,500.00 42,500.00 9.3000 kg PC @ Rp. 764.00 7,105.20

0.0180 Pasir pasang @ Rp. 76,000.00 1,368.00 1.5000 kg Semen putih @ Rp. 1,312.50 1,968.75 0.6500 org Tukang batu @ Rp. 42,500.00 27,625.00 0.0650 org Kep. Tk. Batu @ Rp. 45,000.00 2,925.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0160 org Mandor @ Rp. 40,000.00 640.00

JUMLAH ( BELUM PPN ) 42,710.00 52,941.95 JASA 10 %JUMLAHDIBULATKAN

m1

m2

m3

m1

m3

m1

m3

m2

m2

m3

Page 55: AHS 2008-Kota.xlsx

Analisa Gedung - 55

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

PEKERJAAN CONBLOCK

AK 1.0000 Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400

1.0000 Conblock @ Rp. 60,000.00 60,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 62,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe uni, segi-empat abu-abu 8 cm, K-300

1.0000 Conblock @ Rp. 55,000.00 55,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 57,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-empat abu-abu 6 cm, K-200

1.0000 Conblock @ Rp. 45,000.00 45,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 47,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-empat abu-abu 8 cm, K-200

1.0000 Conblock @ Rp. 50,000.00 50,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 52,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-enam abu-abu 6 cm, K-200

1.0000 Conblock @ Rp. 45,000.00 45,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 47,750.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

Page 56: AHS 2008-Kota.xlsx

Analisa Gedung - 56

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang conblock tipe segi-enam abu-abu 8 cm, K-200

1.0000 Conblock @ Rp. 50,000.00 50,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 52,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-empat, uni, segi-enam rawna 8 cm, K-400

1.0000 Conblock @ Rp. 80,000.00 80,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 82,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe uni, segi-empat warna 8 cm, K-300

1.0000 Conblock @ Rp. 70,000.00 70,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 72,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-empat warna 6 cm, K-200

1.0000 Conblock @ Rp. 50,000.00 50,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 52,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-empat warna 8 cm, K-200

1.0000 Conblock @ Rp. 60,000.00 60,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 62,750.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

Page 57: AHS 2008-Kota.xlsx

Analisa Gedung - 57

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang conblock tipe segi-enam warna 6 cm, K-200

1.0000 Conblock @ Rp. 50,000.00 50,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 52,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang conblock tipe segi-enam warna 8 cm, K-200

1.0000 Conblock @ Rp. 60,000.00 60,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 62,750.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang grassblock bulat tebal 10 cm

1.0000 Grassblock @ Rp. 50,000.00 50,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 52,750.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang grassblock tebal 10 cm

1.0000 Grassblock @ Rp. 50,000.00 50,000.00

0.0500 Pasir urug @ Rp. 55,000.00 2,750.00 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kep. Tk. Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 52,750.00 JASA 10 %JUMLAHDIBULATKAN

AK 3.0000 Bronjong kawat galvanisA Penganyaman

70.0000 kg Kawat galvanis @ Rp. 7,755.00 542,850.00 2.5000 org Penganyaman @ Rp. 45,000.00 112,500.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

B Pengisian

3.0000 Batu kali (hitam) @ Rp. 80,000.00 240,000.00 4.5000 org Pekerja @ Rp. 36,000.00 162,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 405,000.00 730,550.00

JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m3

m3

TIAP 1 M3

Page 58: AHS 2008-Kota.xlsx

Analisa Gedung - 58

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 bh Pasang buis beton dia. 80 cm 1.0000 bh Buis beton @ Rp. 45,000.00 45,000.00 0.1250 org Tukang batu @ Rp. 42,500.00 5,312.50 0.0125 org Kep. Tk. Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00

JUMLAH ( BELUM PPN ) 14,875.00 45,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Langsiran batu kali 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0200 org Mandor @ Rp. 40,000.00 800.00 1.0000 hr Sewa gerobag @ Rp. 1,500.00 1,500.00

JUMLAH ( BELUM PPN ) 9,500.00 - JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Langsiran kerikil 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00 0.0120 org Mandor @ Rp. 40,000.00 480.00 1.0000 hr Sewa gerobag @ Rp. 1,500.00 1,500.00

JUMLAH ( BELUM PPN ) 6,300.00 - JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Langsiran pasir 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0050 org Mandor @ Rp. 40,000.00 200.00 1.0000 hr Sewa gerobag @ Rp. 1,500.00 1,500.00

JUMLAH ( BELUM PPN ) 3,500.00 - JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN KAYU

SNI 1.0000 Pasang konstruksi kuda-kuda kayu jati

6.27 1.1000 Kayu jati balok @ Rp. 20,000,000.00 22,000,000.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 7,500.00 112,500.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 6,400.00 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala tukang kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 22,118,900.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kuda-kuda kayu jati (lokal)

6.27 1.1000 Kayu jati (lokal) @ Rp. 10,000,000.00 11,000,000.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 7,500.00 112,500.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 6,400.00 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala tukang kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 11,118,900.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m3

m3

m3

m3

Page 59: AHS 2008-Kota.xlsx

Analisa Gedung - 59

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Membuat kuda-kuda kayu kamper

6.28 1.1000 Kayu kamper @ Rp. 4,750,000.00 5,225,000.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 7,500.00 112,500.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 6,400.00 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala tukang kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 5,343,900.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kuda-kuda kayu kruing

6.30 1.1000 Kayu kruing @ Rp. 4,350,000.00 4,785,000.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 7,500.00 112,500.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 6,400.00 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala tukang kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 4,903,900.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kuda-kuda kayu bengkirai

1.1000 Kayu bengkirai @ Rp. 5,750,000.00 6,325,000.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 7,500.00 112,500.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 6,400.00 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala tukang kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 6,443,900.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kuda-kuda kayu glugu

1.1000 Kayu glugu @ Rp. 1,458,000.00 1,603,800.00 03-3434-2002 15.0000 kg Besi strip @ Rp. 7,500.00 112,500.00

0.8000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 6,400.00 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala tukang kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 1,722,700.00 JASA 10 %JUMLAHDIBULATKAN

F.16 1.0000 Pasang usuk 5/7, reng 2/3 kayu jati

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

5.0000 Reng jati 2/3 @ Rp. 12,000.00 60,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 216,000.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m3

m3

m3

m3

m3

m2

m1

m1

Page 60: AHS 2008-Kota.xlsx

Analisa Gedung - 60

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 2/3 kayu jati (lokal)

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

5.0000 Reng kayu jati 2/3 (lokal) @ Rp. 6,000.00 30,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 186,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 2/3 kayu kamper

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

5.0000 Reng kayu kamper 2/3 @ Rp. 2,850.00 14,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 170,250.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 2/3 kayu kruing

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

5.0000 Reng kayu kruing 2/3 @ Rp. 2,610.00 13,050.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 169,050.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 2/3 kayu bengkirai

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

5.0000 Reng kayu bengkirai 2/3 @ Rp. 3,450.00 17,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 173,250.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 61: AHS 2008-Kota.xlsx

Analisa Gedung - 61

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu jati

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

5.0000 Reng kayu jati 2/3 @ Rp. 12,000.00 60,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 139,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu jati lokal

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

5.0000 Reng kayu jati 2/3 lokal @ Rp. 6,000.00 30,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 109,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu kamper

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

5.0000 Reng kayu kamper 2/3 @ Rp. 2,850.00 14,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 93,250.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu kruing

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

5.0000 Reng kayu kruing 2/3 @ Rp. 2,610.00 13,050.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 92,050.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 62: AHS 2008-Kota.xlsx

Analisa Gedung - 62

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu bengkirai

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

5.0000 Reng kayu bengkirai 2/3 @ Rp. 3,450.00 17,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 96,250.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 2/3 reng kayu jati

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

5.0000 Reng jati 2/3 @ Rp. 12,000.00 60,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 98,575.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu jati lokal

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

5.0000 Reng kayu jati 2/3 lokal @ Rp. 6,000.00 30,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 68,575.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu kamper

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

5.0000 Reng kayu kamper 2/3 @ Rp. 2,850.00 14,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 52,825.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 63: AHS 2008-Kota.xlsx

Analisa Gedung - 63

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu kruing

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

5.0000 Reng kayu kruing 2/3 @ Rp. 2,610.00 13,050.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 51,625.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu bengkirai

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

5.0000 Reng kayu bengkirai 2/3 @ Rp. 3,450.00 17,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 55,825.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu jati

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

5.0000 Reng jati 2/3 @ Rp. 12,000.00 60,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 95,495.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu jati lokal

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

5.0000 Reng kayu jati 2/3 lokal @ Rp. 6,000.00 30,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 65,495.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 64: AHS 2008-Kota.xlsx

Analisa Gedung - 64

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu kamper

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

5.0000 Reng kayu kamper 2/3 @ Rp. 2,850.00 14,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 49,745.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu kruing

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

5.0000 Reng kayu kruing 2/3 @ Rp. 2,610.00 13,050.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 48,545.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu bengkirai

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

5.0000 Reng kayu bengkirai 2/3 @ Rp. 3,450.00 17,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 52,745.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

5.0000 Reng jati 2/3 @ Rp. 12,000.00 60,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 106,275.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 65: AHS 2008-Kota.xlsx

Analisa Gedung - 65

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati lokal

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

5.0000 Reng kayu jati 2/3 lokal @ Rp. 6,000.00 30,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 76,275.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu kamper

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

5.0000 Reng kayu kamper 2/3 @ Rp. 2,850.00 14,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 60,525.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu kruing

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

5.0000 Reng kayu kruing 2/3 @ Rp. 2,610.00 13,050.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 59,325.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu bengkirai

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

5.0000 Reng kayu bengkirai 2/3 @ Rp. 3,450.00 17,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 63,525.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 66: AHS 2008-Kota.xlsx

Analisa Gedung - 66

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 glugu, reng 2/3 kayu jati

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

5.0000 Reng jati 2/3 @ Rp. 12,000.00 60,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 75,860.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 2/3 kayu jati lokal

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

5.0000 Reng kayu jati 2/3 lokal @ Rp. 6,000.00 30,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 45,860.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 2/3 kayu kamper

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

5.0000 Reng kayu kamper 2/3 @ Rp. 2,850.00 14,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 30,110.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 2/3 kayu kruing

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

5.0000 Reng kayu kruing 2/3 @ Rp. 2,610.00 13,050.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 28,910.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 67: AHS 2008-Kota.xlsx

Analisa Gedung - 67

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 glugu, reng 2/3 kayu bengkirai

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

5.0000 Reng kayu bengkirai 2/3 @ Rp. 3,450.00 17,250.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 33,110.00 JASA 10 %JUMLAHDIBULATKAN

F.16 1.0000 Pasang usuk 5/7, reng 3/4 kayu jati

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

4.0000 Reng jati 3/4 @ Rp. 24,000.00 96,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 252,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 3/4 kayu jati (lokal)

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

4.0000 Reng kayu jati 3/4 (lokal) @ Rp. 12,000.00 48,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 204,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 3/4 kayu kamper

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

4.0000 Reng kayu kamper 3/4 @ Rp. 5,700.00 22,800.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 178,800.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 68: AHS 2008-Kota.xlsx

Analisa Gedung - 68

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 3/4 kayu kruing

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

4.0000 Reng kayu kruing 3/4 @ Rp. 5,220.00 20,880.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 176,880.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati, reng 3/4 kayu bengkirai

2.2000 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00

4.0000 Reng kayu bengkirai 3/4 @ Rp. 6,900.00 27,600.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 183,600.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu jati

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

4.0000 Reng kayu jati 3/4 @ Rp. 24,000.00 96,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 175,000.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu jati lokal

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

4.0000 Reng kayu jati 3/4 lokal @ Rp. 12,000.00 48,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 127,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 69: AHS 2008-Kota.xlsx

Analisa Gedung - 69

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu kamper

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

4.0000 Reng kayu kamper 3/4 @ Rp. 5,700.00 22,800.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 101,800.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu kruing

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

4.0000 Reng kayu kruing 3/4 @ Rp. 5,220.00 20,880.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 99,880.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu bengkirai

2.2000 Usuk kayu jati 5/7 (lokal) @ Rp. 35,000.00 77,000.00

4.0000 Reng kayu bengkirai 3/4 @ Rp. 6,900.00 27,600.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 106,600.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 3/4 reng kayu jati

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

4.0000 Reng jati 3/4 @ Rp. 24,000.00 96,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 134,575.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 70: AHS 2008-Kota.xlsx

Analisa Gedung - 70

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu jati lokal

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

4.0000 Reng kayu jati 3/4 lokal @ Rp. 12,000.00 48,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 86,575.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu kamper

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

4.0000 Reng kayu kamper 3/4 @ Rp. 5,700.00 22,800.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 61,375.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu kruing

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

4.0000 Reng kayu kruing 3/4 @ Rp. 5,220.00 20,880.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 59,455.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu bengkirai

2.2000 Usuk kayu kamper 5/7 @ Rp. 16,625.00 36,575.00

4.0000 Reng kayu bengkirai 3/4 @ Rp. 6,900.00 27,600.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 66,175.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 71: AHS 2008-Kota.xlsx

Analisa Gedung - 71

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu jati

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

4.0000 Reng jati 3/4 @ Rp. 24,000.00 96,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 131,495.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu jati lokal

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

4.0000 Reng kayu jati 3/4 lokal @ Rp. 12,000.00 48,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 83,495.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu kamper

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

4.0000 Reng kayu kamper 3/4 @ Rp. 5,700.00 22,800.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 58,295.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu kruing

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

4.0000 Reng kayu kruing 3/4 @ Rp. 5,220.00 20,880.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 56,375.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 72: AHS 2008-Kota.xlsx

Analisa Gedung - 72

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu bengkirai

2.2000 Usuk kayu kruing 5/7 @ Rp. 15,225.00 33,495.00

4.0000 Reng kayu bengkirai 3/4 @ Rp. 6,900.00 27,600.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 63,095.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

4.0000 Reng jati 3/4 @ Rp. 24,000.00 96,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 142,275.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati lokal

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

4.0000 Reng kayu jati 3/4 lokal @ Rp. 12,000.00 48,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 94,275.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu kamper

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

4.0000 Reng kayu kamper 3/4 @ Rp. 5,700.00 22,800.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 69,075.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 73: AHS 2008-Kota.xlsx

Analisa Gedung - 73

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu kruing

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

4.0000 Reng kayu kruing 3/4 @ Rp. 5,220.00 20,880.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 67,155.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai

2.2000 Usuk kayu bengkirai 5/7 @ Rp. 20,125.00 44,275.00

4.0000 Reng kayu bengkirai 3/4 @ Rp. 6,900.00 27,600.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 73,875.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 3/4 kayu jati

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

4.0000 Reng jati 3/4 @ Rp. 24,000.00 96,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 111,860.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 3/4 kayu jati lokal

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

4.0000 Reng kayu jati 3/4 lokal @ Rp. 12,000.00 48,000.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 63,860.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m2

m1

m1

Page 74: AHS 2008-Kota.xlsx

Analisa Gedung - 74

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Pasang usuk 5/7 glugu, reng 3/4 kayu kamper

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

4.0000 Reng kayu kamper 3/4 @ Rp. 5,700.00 22,800.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 38,660.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 3/4 kayu kruing

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

4.0000 Reng kayu kruing 3/4 @ Rp. 5,220.00 20,880.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 36,740.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Pasang usuk 5/7 glugu, reng 3/4 kayu bengkirai

2.2000 Usuk glugu 5/7 @ Rp. 6,300.00 13,860.00

4.0000 Reng kayu bengkirai 3/4 @ Rp. 6,900.00 27,600.00 0.1500 kg Paku usuk @ Rp. 8,000.00 1,200.00 0.1000 kg Paku reng @ Rp. 8,000.00 800.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kep. Tk. Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 8,950.00 43,460.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kusen pintu / jendela kayu jati (klas plitur)

6.1 1.1000 Kayu jati (klas plitur) @ Rp. 20,000,000.00 22,000,000.00 03-3434-2002 20.0000 org Tukang kayu @ Rp. 47,500.00 950,000.00

2.0000 org Kepala tukang kayu @ Rp. 50,000.00 100,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,278,000.00 22,000,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kusen pintu / jendela kayu jati (lokal)

6.1 1.1000 Kayu jati (lokal) @ Rp. 10,000,000.00 11,000,000.00 03-3434-2002 20.0000 org Tukang kayu @ Rp. 47,500.00 950,000.00

2.0000 org Kepala tukang kayu @ Rp. 50,000.00 100,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,278,000.00 11,000,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m2

m1

m1

m2

m1

m1

m3

m3

m3

m3

Page 75: AHS 2008-Kota.xlsx

Analisa Gedung - 75

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Membuat kusen pintu / jendela kayu kamper

6.2 1.2000 Kayu kamper @ Rp. 4,750,000.00 5,700,000.00 03-3434-2002 18.0000 org Tukang kayu @ Rp. 47,500.00 855,000.00

2.0000 org Kepala tukang kayu @ Rp. 50,000.00 100,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,183,000.00 5,700,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kusen pintu / jendela kayu kruing

1.2000 Kayu kruing @ Rp. 4,350,000.00 5,220,000.00 03-3434-2002 18.0000 org Tukang kayu @ Rp. 47,500.00 855,000.00

2.0000 org Kepala tukang kayu @ Rp. 50,000.00 100,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,183,000.00 5,220,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat kusen pintu / jendela kayu bengkirai

1.2000 Kayu bengkirai @ Rp. 5,750,000.00 6,900,000.00 03-3434-2002 18.0000 org Tukang kayu @ Rp. 47,500.00 855,000.00

2.0000 org Kepala tukang kayu @ Rp. 50,000.00 100,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,183,000.00 6,900,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu teakwood rangkap, rangka kayu jati

6.19 0.0196 Papan kayu jati @ Rp. 22,000,000.00 431,200.00 03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 240.00

0.3000 kg Lem kayu @ Rp. 11,000.00 3,300.00 1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 69,500.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 127,800.00 504,240.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu teakwood rangkap, rangka kayu jati lokal

6.19 0.0196 Papan kayu jati lokal @ Rp. 11,000,000.00 215,600.00 03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 240.00

0.3000 kg Lem kayu @ Rp. 11,000.00 3,300.00 1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 69,500.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 127,800.00 288,640.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m3

m3

m3

m2

m3

m2

m3

Page 76: AHS 2008-Kota.xlsx

Analisa Gedung - 76

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang pintu teakwood rangkap, rangka kayu kamper

6.20 0.0196 Papan kayu kamper @ Rp. 5,500,000.00 107,800.00 03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 240.00

0.3000 kg Lem kayu @ Rp. 11,000.00 3,300.00 1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 69,500.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 127,800.00 180,840.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu teakwood rangkap, rangka kayu kruing

0.0196 Papan kayu kruing @ Rp. 4,750,000.00 93,100.00 03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 240.00

0.3000 kg Lem kayu @ Rp. 11,000.00 3,300.00 1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 69,500.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 127,800.00 166,140.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu teakwood rangkap, rangka kayu bengkirai

0.0196 Papan kayu bengkirai @ Rp. 6,000,000.00 117,600.00 03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 240.00

0.3000 kg Lem kayu @ Rp. 11,000.00 3,300.00 1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 69,500.00 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 127,800.00 190,640.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela kaca kayu jati

6.9 0.0350 Kayu jati papan @ Rp. 22,000,000.00 770,000.00 03-3434-2002 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00

0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 135,400.00 770,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela kaca kayu jati lokal

6.9 0.0350 Papan kayu jati lokal @ Rp. 11,000,000.00 385,000.00 03-3434-2002 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00

0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 135,400.00 385,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 77: AHS 2008-Kota.xlsx

Analisa Gedung - 77

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang pintu dan jendela kaca kayu kamper

610 0.0350 Papan kayu kamper @ Rp. 5,500,000.00 192,500.00 03-3434-2002 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00

0.2000 org Kep. Tk. Kayu @ Rp. 50,000.00 10,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 135,400.00 192,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela kaca kayu kruing

0.0350 Papan kayu kruing @ Rp. 4,750,000.00 166,250.00 03-3434-2002 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00

0.2000 org Kep. Tk. Kayu @ Rp. 50,000.00 10,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 135,400.00 166,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela kaca kayu bengkirai

0.0350 Papan kayu bengkirai @ Rp. 6,000,000.00 210,000.00 03-3434-2002 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00

0.2000 org Kep. Tk. Kayu @ Rp. 50,000.00 10,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 135,400.00 210,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan daun pintu / jendela panil kayu jati

6.7 0.0400 Kayu jati papan @ Rp. 22,000,000.00 880,000.00 03-3434-2002 2.5000 org Tukang kayu @ Rp. 47,500.00 118,750.00

0.2500 org Kepala tukang kayu @ Rp. 50,000.00 12,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 169,250.00 880,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan daun pintu / jendela panil kayu jati lokal

6.7 0.0400 Kayu jati papan lokal @ Rp. 11,000,000.00 440,000.00 03-3434-2002 2.5000 org Tukang kayu @ Rp. 47,500.00 118,750.00

0.2500 org Kepala tukang kayu @ Rp. 50,000.00 12,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 169,250.00 440,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan daun pintu / jendela panil kayu kamper

6.8 0.0400 Kayu kamper papan @ Rp. 5,500,000.00 220,000.00 03-3434-2002 2.5000 org Tukang kayu @ Rp. 47,500.00 118,750.00

0.2500 org Kepala tukang kayu @ Rp. 50,000.00 12,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 169,250.00 220,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 78: AHS 2008-Kota.xlsx

Analisa Gedung - 78

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Mengerjakan daun pintu / jendela panil kayu kruing

0.0400 Kayu kruing papan @ Rp. 4,750,000.00 190,000.00 03-3434-2002 2.5000 org Tukang kayu @ Rp. 47,500.00 118,750.00

0.2500 org Kepala tukang kayu @ Rp. 50,000.00 12,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 169,250.00 190,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan daun pintu / jendela panil kayu bengkirai

0.0400 Kayu bengkirai papan @ Rp. 6,000,000.00 240,000.00 03-3434-2002 2.5000 org Tukang kayu @ Rp. 47,500.00 118,750.00

0.2500 org Kepala tukang kayu @ Rp. 50,000.00 12,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 169,250.00 240,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela jalusi kayu jati

6.12 0.0640 Kayu jati papan @ Rp. 22,000,000.00 1,408,000.00 03-3434-2002 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

0.3000 org Kepala tukang kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 205,500.00 1,408,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela jalusi kayu jati

6.12 0.0640 Kayu jati papan lokal @ Rp. 11,000,000.00 704,000.00 03-3434-2002 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

0.3000 org Kepala tukang kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 205,500.00 704,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela jalusi kayu kamper

6.13 0.0640 Kayu kamper papan @ Rp. 5,500,000.00 352,000.00 03-3434-2002 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

0.3000 org Kepala tukang kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 352,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu dan jendela jalusi kayu kruing

0.0640 Kayu kruing papan @ Rp. 4,750,000.00 304,000.00 03-3434-2002 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

0.3000 org Kepala tukang kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 304,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 79: AHS 2008-Kota.xlsx

Analisa Gedung - 79

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang pintu dan jendela jalusi kayu bengkirai

0.0640 Kayu bengkirai papan @ Rp. 6,000,000.00 384,000.00 03-3434-2002 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

0.3000 org Kepala tukang kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 384,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, kayu jati

6.38 0.0120 Kayu jati balok @ Rp. 20,000,000.00 240,000.00 03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 240,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, kayu jati lokal

6.38 0.0120 Kayu jati balok lokal @ Rp. 10,000,000.00 120,000.00 03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 120,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, kayu kamper

6.39 0.0120 Kayu kamper balok @ Rp. 4,750,000.00 57,000.00 03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 57,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, kayu kruing

0.0120 Kayu kruing @ Rp. 4,350,000.00 52,200.00 03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 53,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 80: AHS 2008-Kota.xlsx

Analisa Gedung - 80

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, kayu bengkirai

0.0120 Kayu bengkirai @ Rp. 5,750,000.00 69,000.00 03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 69,800.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang rangka langit-langit (60 x 120) cm, kayu jati

0.0130 Kayu jati @ Rp. 20,000,000.00 260,000.00 0.1200 kg Paku @ Rp. 8,000.00 960.00 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 260,960.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang rangka langit-langit (60 x 120) m, kayu jati lokal

0.0130 Kayu jati lokal @ Rp. 10,000,000.00 130,000.00 0.1200 kg Paku @ Rp. 8,000.00 960.00 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 130,960.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang rangka langit-langit (60 x 120) m, kayu kamper

0.0130 Kayu kamper @ Rp. 4,750,000.00 61,750.00 0.1200 kg Paku @ Rp. 8,000.00 960.00 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 62,710.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang rangka langit-langit (60 x 120) m, kayu kruing

0.0130 Kayu kruing @ Rp. 4,350,000.00 56,550.00 0.1200 kg Paku @ Rp. 8,000.00 960.00 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 57,510.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 81: AHS 2008-Kota.xlsx

Analisa Gedung - 81

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Pasang rangka langit-langit (60 x 120) m, kayu bengkirai

0.0130 Kayu bengkirai @ Rp. 5,750,000.00 74,750.00 0.1200 kg Paku @ Rp. 8,000.00 960.00 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kep. Tk. Kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 75,710.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m tanpa plepet6.1 1.1000 lbr Pelat asbes @ Rp. 15,000.00 16,500.00

03-2838-2002 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.0300 org Pekerja @ Rp. 36,000.00 1,080.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 4,815.00 16,615.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Langit-langit asbes (1,00 x 1,00) m memakai plepet 1.1000 lbr Pelat asbes @ Rp. 15,000.00 16,500.00

2.6000 Plepet kayu @ Rp. 2,000.00 5,200.00 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0100 kg Paku plepet @ Rp. 10,000.00 100.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.0300 org Pekerja @ Rp. 36,000.00 1,080.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 4,815.00 21,915.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati tanpa plepet

0.0120 Kayu jati balok @ Rp. 20,000,000.00 240,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 257,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati lokal tanpa plepet

0.0120 Kayu jati balok lokal @ Rp. 10,000,000.00 120,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 137,100.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m2

m1

m2

m3

m2

m3

Page 82: AHS 2008-Kota.xlsx

Analisa Gedung - 82

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kamper tanpa plepet

0.0120 Kayu kamper balok @ Rp. 4,750,000.00 57,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 74,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kruing tanpa plepet

0.0120 Kayu kruing balok @ Rp. 4,350,000.00 52,200.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 69,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu bengkirai tanpa plepet

0.0120 Kayu bengkirai balok @ Rp. 5,750,000.00 69,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 86,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati memakai plepet

0.0120 Kayu jati balok @ Rp. 20,000,000.00 240,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00

2.6000 Plepet kayu @ Rp. 2,000.00 5,200.00 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0100 kg Paku plepet @ Rp. 10,000.00 100.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 262,515.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m1

Page 83: AHS 2008-Kota.xlsx

Analisa Gedung - 83

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati lokal memakai plepet

0.0120 Kayu jati balok lokal @ Rp. 10,000,000.00 120,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00

2.6000 Plepet kayu @ Rp. 2,000.00 5,200.00 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0100 kg Paku plepet @ Rp. 10,000.00 100.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 142,515.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kamper memakai plepet

0.0120 Kayu kamper balok @ Rp. 4,750,000.00 57,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00

2.6000 Plepet kayu @ Rp. 2,000.00 5,200.00 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0100 kg Paku plepet @ Rp. 10,000.00 100.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 79,515.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kruing memakai plepet

0.0120 Kayu kruing balok @ Rp. 4,350,000.00 52,200.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00

2.6000 Plepet kayu @ Rp. 2,000.00 5,200.00 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0100 kg Paku plepet @ Rp. 10,000.00 100.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 74,715.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m, rangka kayu bengkirai memakai plepet

0.0120 Kayu bengkirai balok @ Rp. 5,750,000.00 69,000.00 03-2838-2002 0.0600 kg Paku biasa @ Rp. 10,000.00 600.00

1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 15,000.00 16,500.00

2.6000 Plepet kayu @ Rp. 2,000.00 5,200.00 0.0100 kg Paku eternit @ Rp. 11,500.00 115.00 0.0100 kg Paku plepet @ Rp. 10,000.00 100.00 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00 0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1800 org Pekerja @ Rp. 36,000.00 6,480.00 0.0090 org Mandor @ Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 23,640.00 91,515.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m1

m2

m3

m1

m2

m3

m1

m2

m3

m1

Page 84: AHS 2008-Kota.xlsx

Analisa Gedung - 84

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.13 1.0000 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu jati

0.0130 Kayu jati @ Rp. 20,000,000.00 260,000.00 0.3600 lbr Gypsum board 9 mm @ Rp. 42,000.00 15,120.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 280,055.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu jati lokal

0.0130 Kayu jati lokal @ Rp. 10,000,000.00 130,000.00 0.3600 lbr Gypsum board 9 mm @ Rp. 42,000.00 15,120.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 150,055.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kamper

0.0130 Kayu kamper @ Rp. 4,750,000.00 61,750.00 0.3600 lbr Gypsum board 9 mm @ Rp. 42,000.00 15,120.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 81,805.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kruing

0.0130 Kayu kruing @ Rp. 4,350,000.00 56,550.00 0.3600 lbr Gypsum board 9 mm @ Rp. 42,000.00 15,120.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 76,605.00 JASA 10 %JUMLAH

m2

m3

m2

m3

m2

m3

m2

m3

Page 85: AHS 2008-Kota.xlsx

Analisa Gedung - 85

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 86: AHS 2008-Kota.xlsx

Analisa Gedung - 86

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu bengkirai

0.0130 Kayu bengkirai @ Rp. 5,750,000.00 74,750.00 0.3600 lbr Gypsum board 9 mm @ Rp. 42,000.00 15,120.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 94,805.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Langit-langit gypsum board tebal 9 mm, rangka hollow

4.5000 Rangka hollow 4x4 cm @ Rp. 9,500.00 42,750.00 0.3600 lbr Gypsum board 9 mm @ Rp. 42,000.00 15,120.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.1500 kg Paku skrup @ Rp. 10,000.00 1,500.00

5.0000 Kawat penggantung @ Rp. 500.00 2,500.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 64,845.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu jati

0.0130 Kayu jati @ Rp. 20,000,000.00 260,000.00 0.3600 lbr Kalsiboard 3.5 mm @ Rp. 46,200.00 16,632.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 281,567.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu jati lokal

0.0130 Kayu jati lokal @ Rp. 10,000,000.00 130,000.00 0.3600 lbr Kalsiboard 3.5 mm @ Rp. 46,200.00 16,632.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 151,567.00 JASA 10 %JUMLAH

m2

m3

m2

m1

m1

m2

m3

m2

m3

Page 87: AHS 2008-Kota.xlsx

Analisa Gedung - 87

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 88: AHS 2008-Kota.xlsx

Analisa Gedung - 88

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.13 1.0000 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu kamper

0.0130 Kayu kamper @ Rp. 4,750,000.00 61,750.00 0.3600 lbr Kalsiboard 3.5 mm @ Rp. 46,200.00 16,632.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 83,317.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu kruing

0.0130 Kayu kruing @ Rp. 4,350,000.00 56,550.00 0.3600 lbr Kalsiboard 3.5 mm @ Rp. 46,200.00 16,632.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 78,117.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu bengkirai

0.0130 Kayu bengkirai @ Rp. 5,750,000.00 74,750.00 0.3600 lbr Kalsiboard 3.5 mm @ Rp. 46,200.00 16,632.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.0500 kg Paku gypsum @ Rp. 20,000.00 1,000.00 0.1200 kg Paku usuk @ Rp. 8,000.00 960.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 96,317.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Langit-langit kalsiboard tebal 3.5 mm, rangka hollow

4.5000 Rangka hollow 4x4 cm @ Rp. 9,500.00 42,750.00 0.3600 lbr Kalsiboard 3.5 mm @ Rp. 46,200.00 16,632.00 0.0500 roll Kasa gypsum @ Rp. 10,000.00 500.00 0.4500 kg Tepung gypsum @ Rp. 3,500.00 1,575.00 0.0030 kg Alkasit @ Rp. 300,000.00 900.00 0.1500 kg Paku skrup @ Rp. 10,000.00 1,500.00

5.0000 Kawat penggantung @ Rp. 500.00 2,500.00 0.3700 org Tukang kayu @ Rp. 47,500.00 17,575.00 0.0370 org Kepala tukang kayu @ Rp. 50,000.00 1,850.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 28,545.00 66,357.00 JASA 10 %JUMLAH

m2

m3

m2

m3

m2

m3

m2

m1

m1

Page 89: AHS 2008-Kota.xlsx

Analisa Gedung - 89

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 90: AHS 2008-Kota.xlsx

Analisa Gedung - 90

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Langit-langit akustik 60 x 120 cm + rangka alumunium

03-3438-2002 3.6000 Profil alumunium "T" @ Rp. 20,000.00 72,000.00 6.18 0.1500 kg Kawat seng polos @ Rp. 9,500.00 1,425.00

1.0000 bh Ramset / dina bolt @ Rp. 2,500.00 2,500.00 1.5000 lbr Akustic Armstrong 60 x 120 cm @ Rp. 125,000.00 187,500.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala tukang kayu @ Rp. 50,000.00 2,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 31,950.00 263,425.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang list profil cornees gypsum lebar sampai 5 cm

1.1000 List profil cornees gypsum @ Rp. 4,000.00 4,400.00 0.7000 kg Tepung gypsum @ Rp. 3,500.00 2,450.00 0.0035 kg Alkasit @ Rp. 300,000.00 1,050.00 0.0375 org Tukang kayu @ Rp. 47,500.00 1,781.25 0.0037 org Kepala tukang kayu @ Rp. 50,000.00 185.00 0.1125 org Pekerja @ Rp. 36,000.00 4,050.00 0.0065 org Mandor @ Rp. 40,000.00 260.00

JUMLAH ( BELUM PPN ) 6,276.25 7,900.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang list profil cornees gypsum lebar 5 - 10 cm

1.1000 List profil cornees gypsum @ Rp. 8,000.00 8,800.00 0.8750 kg Tepung gypsum @ Rp. 3,500.00 3,062.50 0.0044 kg Alkasit @ Rp. 300,000.00 1,320.00 0.0375 org Tukang kayu @ Rp. 47,500.00 1,781.25 0.0037 org Kepala tukang kayu @ Rp. 50,000.00 185.00 0.1125 org Pekerja @ Rp. 36,000.00 4,050.00 0.0065 org Mandor @ Rp. 40,000.00 260.00

JUMLAH ( BELUM PPN ) 6,276.25 13,182.50 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang list profil cornees gypsum lebar lebih dari 10 cm

1.1000 List profil cornees gypsum @ Rp. 15,000.00 16,500.00 1.0500 kg Tepung gypsum @ Rp. 3,500.00 3,675.00 0.0053 kg Alkasit @ Rp. 300,000.00 1,590.00 0.0400 org Tukang kayu @ Rp. 47,500.00 1,900.00 0.0040 org Kepala tukang kayu @ Rp. 50,000.00 200.00 0.1125 org Pekerja @ Rp. 36,000.00 4,050.00 0.0065 org Mandor @ Rp. 40,000.00 260.00

JUMLAH ( BELUM PPN ) 6,410.00 21,765.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 List langit-langit kayu profil

6.19 1.1000 List kayu profil @ Rp. 5,500.00 6,050.00 03-2838-2002 0.0100 kg Paku @ Rp. 10,000.00 100.00

0.0500 org Tukang kayu @ Rp. 47,500.00 2,375.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 4,545.00 6,150.00 JASA 10 %JUMLAHDIBULATKAN

m2

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 91: AHS 2008-Kota.xlsx

Analisa Gedung - 91

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Pasang lisplank ukuran (2 x 20) cm, kayu jati

0.0048 Kayu jati papan @ Rp. 22,000,000.00 105,600.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 106,080.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 25) cm, kayu jati

0.0060 Kayu jati papan @ Rp. 22,000,000.00 132,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 132,480.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, kayu jati

6.47 0.0072 Kayu jati papan @ Rp. 22,000,000.00 158,400.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,550.00 158,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, kayu jati

6.49 0.0110 Kayu jati papan @ Rp. 22,000,000.00 242,000.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2200 org Tukang kayu @ Rp. 47,500.00 10,450.00 0.0220 org Kepala tukang kayu @ Rp. 50,000.00 1,100.00 0.1100 org Pekerja @ Rp. 36,000.00 3,960.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 15,710.00 242,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu jati

0.0145 Kayu jati papan @ Rp. 22,000,000.00 319,000.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 319,480.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 92: AHS 2008-Kota.xlsx

Analisa Gedung - 92

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu jati

0.0086 Kayu jati papan @ Rp. 22,000,000.00 189,200.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 189,680.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 20) cm, kayu jati lokal

0.0048 Papan kayu jati lokal @ Rp. 11,000,000.00 52,800.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 53,280.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 25) cm, kayu jati lokal

0.0060 Papan kayu jati lokal @ Rp. 11,000,000.00 66,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 66,480.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, kayu jati lokal

6.47 0.0072 Papan kayu jati lokal @ Rp. 11,000,000.00 79,200.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,550.00 79,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, kayu jati lokal

6.49 0.0110 Papan kayu jati lokal @ Rp. 11,000,000.00 121,000.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2200 org Tukang kayu @ Rp. 47,500.00 10,450.00 0.0220 org Kepala tukang kayu @ Rp. 50,000.00 1,100.00 0.1100 org Pekerja @ Rp. 36,000.00 3,960.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 15,710.00 121,400.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 93: AHS 2008-Kota.xlsx

Analisa Gedung - 93

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu jati lokal

0.0145 Papan kayu jati lokal @ Rp. 11,000,000.00 159,500.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 159,980.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu jati lokal

0.0086 Papan kayu jati lokal @ Rp. 11,000,000.00 94,600.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 95,080.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 20) cm, kayu kamper

0.0048 Kayu kamper papan @ Rp. 5,500,000.00 26,400.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 26,880.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 25) cm, kayu kamper

0.0060 Kayu kamper papan @ Rp. 5,500,000.00 33,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 33,480.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, kayu kamper

6.48 0.0072 Kayu kamper papan @ Rp. 5,500,000.00 39,600.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 40,000.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 94: AHS 2008-Kota.xlsx

Analisa Gedung - 94

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, kayu kamper

6.50 0.0110 Kayu kamper papan @ Rp. 5,500,000.00 60,500.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2200 org Tukang kayu @ Rp. 47,500.00 10,450.00 0.0220 org Kepala tukang kayu @ Rp. 50,000.00 1,100.00 0.1100 org Pekerja @ Rp. 36,000.00 3,960.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 15,710.00 60,900.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu kamper

6.51 0.0145 Kayu kamper papan @ Rp. 5,500,000.00 79,750.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 80,230.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kamper

6.52 0.0086 Kayu kamper papan @ Rp. 5,500,000.00 47,300.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 47,780.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 20) cm, kayu kruing

0.0048 Kayu kruing papan @ Rp. 4,750,000.00 22,800.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 23,280.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 25) cm, kayu kruing

0.0060 Kayu kruing papan @ Rp. 4,750,000.00 28,500.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 28,980.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 95: AHS 2008-Kota.xlsx

Analisa Gedung - 95

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, kayu kruing

0.0072 Kayu kruing papan @ Rp. 4,750,000.00 34,200.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 34,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, kayu kruing

6.50 0.0110 Kayu kruing papan @ Rp. 4,750,000.00 52,250.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2200 org Tukang kayu @ Rp. 47,500.00 10,450.00 0.0220 org Kepala tukang kayu @ Rp. 50,000.00 1,100.00 0.1100 org Pekerja @ Rp. 36,000.00 3,960.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 15,710.00 52,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu kruing

6.51 0.0145 Kayu kruing papan @ Rp. 4,750,000.00 68,875.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 69,355.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kruing

6.52 0.0086 Kayu kruing papan @ Rp. 4,750,000.00 40,850.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 41,330.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang lisplank ukuran (2 x 20) cm, kayu bengkirai

0.0048 Kayu bengkirai papan @ Rp. 6,000,000.00 28,800.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 29,280.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 96: AHS 2008-Kota.xlsx

Analisa Gedung - 96

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Pasang lisplank ukuran (2 x 25) cm, kayu bengkirai

0.0060 Kayu bengkirai papan @ Rp. 6,000,000.00 36,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 36,480.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, kayu bengkirai

0.0072 Kayu bengkirai papan @ Rp. 6,000,000.00 43,200.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 43,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, kayu bengkirai

6.50 0.0110 Kayu bengkirai papan @ Rp. 6,000,000.00 66,000.00 03-3434-2002 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00

0.2200 org Tukang kayu @ Rp. 47,500.00 10,450.00 0.0220 org Kepala tukang kayu @ Rp. 50,000.00 1,100.00 0.1100 org Pekerja @ Rp. 36,000.00 3,960.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 15,710.00 66,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu bengkirai

6.51 0.0145 Kayu bengkirai papan @ Rp. 6,000,000.00 87,000.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 87,480.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu bengkirai

6.52 0.0086 Kayu bengkirai papan @ Rp. 6,000,000.00 51,600.00 03-3434-2002 0.0600 kg Paku biasa 2" - 5" @ Rp. 8,000.00 480.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 52,080.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 97: AHS 2008-Kota.xlsx

Analisa Gedung - 97

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 1.0000 Membuat listplank asbes plat ram kayu jati

0.0250 Ram kayu jati @ Rp. 20,000,000.00 500,000.00

1.0000 Asbes plat @ Rp. 15,000.00 15,000.00 0.3000 kg Paku reng @ Rp. 8,000.00 2,400.00 1.8000 org Tukang kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kep. Tk. Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 517,400.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Membuat listplank asbes plat ram kayu jati lokal

0.0250 Ram kayu jati lokal @ Rp. 10,000,000.00 250,000.00

1.0000 Asbes plat @ Rp. 15,000.00 15,000.00 0.3000 kg Paku reng @ Rp. 8,000.00 2,400.00 1.8000 org Tukang kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kep. Tk. Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 267,400.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Membuat listplank asbes plat ram kayu kamper

0.0250 Ram kayu kamper @ Rp. 4,750,000.00 118,750.00

1.0000 Asbes plat @ Rp. 15,000.00 15,000.00 0.3000 kg Paku reng @ Rp. 8,000.00 2,400.00 1.8000 org Tukang kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kep. Tk. Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 136,150.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Membuat listplank asbes plat ram kayu kruing

0.0250 Ram kayu kruing @ Rp. 4,350,000.00 108,750.00

1.0000 Asbes plat @ Rp. 15,000.00 15,000.00 0.3000 kg Paku reng @ Rp. 8,000.00 2,400.00 1.8000 org Tukang kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kep. Tk. Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 126,150.00 JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Membuat listplank asbes plat ram kayu bengkirai

0.0250 Ram kayu bengkirai @ Rp. 5,750,000.00 143,750.00

1.0000 Asbes plat @ Rp. 15,000.00 15,000.00 0.3000 kg Paku reng @ Rp. 8,000.00 2,400.00 1.8000 org Tukang kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kep. Tk. Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 161,150.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

Page 98: AHS 2008-Kota.xlsx

Analisa Gedung - 98

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Mengerjakan papan ruiter kayu jati 2/20

0.0040 Kayu jati papan @ Rp. 22,000,000.00 88,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. 8,000.00 160.00 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 88,160.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Mengerjakan papan ruiter kayu jati lokal 2/20

0.0040 Papan kayu jati lokal @ Rp. 11,000,000.00 44,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. 8,000.00 160.00 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 44,160.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Mengerjakan papan ruiter kayu kamper 2/20

0.0040 Kayu kamper papan @ Rp. 5,500,000.00 22,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. 8,000.00 160.00 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 22,160.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Mengerjakan papan ruiter kayu kruing 2/20

0.0040 Kayu kruing papan @ Rp. 4,750,000.00 19,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. 8,000.00 160.00 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 19,160.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Mengerjakan papan ruiter kayu bengkirai 2/20

0.0040 Kayu bengkirai papan @ Rp. 6,000,000.00 24,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. 8,000.00 160.00 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 24,160.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 99: AHS 2008-Kota.xlsx

Analisa Gedung - 99

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang talang datar, seng BJLS 28, papan kayu jati6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0096 Kayu jati papan @ Rp. 22,000,000.00 211,200.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 25,700.00 242,070.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar, seng BJLS 28, papan kayu jati lokal6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0096 Kayu jati lokal papan @ Rp. 11,000,000.00 105,600.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 25,700.00 136,470.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar, seng BJLS 28, papan kayu kamper6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0096 Kayu kamper papan @ Rp. 5,500,000.00 52,800.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 25,700.00 83,670.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar, seng BJLS 28, papan kayu kruing6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0096 Kayu kruing papan @ Rp. 4,750,000.00 45,600.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 25,700.00 76,470.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

Page 100: AHS 2008-Kota.xlsx

Analisa Gedung - 100

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang talang datar, seng BJLS 28, papan kayu bengkirai6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0096 Kayui bengkirai papan @ Rp. 6,000,000.00 57,600.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 25,700.00 88,470.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang miring, seng BJLS 28 papan kayu jati6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0190 Kayu jati papan @ Rp. 22,000,000.00 418,000.00 0.3000 kg Flincoat @ Rp. 35,000.00 10,500.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 21,740.00 450,620.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang miring, seng BJLS 28, papan kayu jati lokal6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0190 Kayu jati lokal papan @ Rp. 11,000,000.00 209,000.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 21,740.00 239,870.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang miring, seng BJLS 28, papan kayu kamper6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0190 Kayu kamper papan @ Rp. 5,500,000.00 104,500.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 21,740.00 135,370.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

Page 101: AHS 2008-Kota.xlsx

Analisa Gedung - 101

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang talang miring, seng BJLS 28, papan kayu kruing6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0190 Kayu kruing papan @ Rp. 4,750,000.00 90,250.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 21,740.00 121,120.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang miring, seng BJLS 28, papan kayu bengkirai6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 22,000.00

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 120.00

0.0190 Kayu bengkirai papan @ Rp. 6,000,000.00 114,000.00 0.2500 kg Flincoat @ Rp. 35,000.00 8,750.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 21,740.00 144,870.00 JASA 10 %JUMLAHDIBULATKAN

H.18 10.0000 Pasang talang torong

10.0000 Seng BJLS 0,30 ( 60 cm ) @ Rp. 20,000.00 200,000.00 225.0000 bh Paku sumbat @ Rp. 400.00 90,000.00 3.7500 org Tukang besi @ Rp. 45,000.00 168,750.00 0.3750 org Kep. Tk. Besi @ Rp. 47,500.00 17,812.50 2.2500 org Pekerja @ Rp. 36,000.00 81,000.00 0.1100 org Mandor @ Rp. 40,000.00 4,400.00

JUMLAH ( BELUM PPN ) 271,962.50 290,000.00

TIAP 1M1 ( BELUM PPN ) 27,196.25 29,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 6.20 0.3000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 13,200.00

0.1000 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 800.00

0.0190 Kayu bengkirai papan @ Rp. 6,000,000.00 114,000.00 0.5000 kg Besi strip @ Rp. 8,800.00 4,400.00 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 18,575.00 132,400.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m1

m1 Pasang talang ½ lingkaran D - 10 cm, seng BJLS 28

m3

Page 102: AHS 2008-Kota.xlsx

Analisa Gedung - 102

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 6.21 0.3000 lbr Seng plat 3' x 6' BJLS 24 @ Rp. 38,500.00 11,550.00

0.1000 kg Paku biasa 1/2" - 1" @ Rp. 8,000.00 800.00

0.0190 Kayu bengkirai papan @ Rp. 6,000,000.00 114,000.00 0.5000 kg Besi strip @ Rp. 8,800.00 4,400.00 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 18,575.00 130,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka dinding pemisah, kayu kamper

03-3434-2002 0.0195 Kayu kamper balok @ Rp. 4,750,000.00 92,625.00

6.54 0.0070 Kayu kamper papan @ Rp. 5,500,000.00 38,500.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.4500 org Tukang kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala tukang kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 32,025.00 131,925.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka dinding pemisah, kayu bengkirai

03-3434-2002 0.0195 Kayu bengkirai balok @ Rp. 5,750,000.00 112,125.00

6.55 0.0070 Kayu bengkirai papan @ Rp. 6,000,000.00 42,000.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.4500 org Tukang kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala tukang kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 32,025.00 154,925.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka dinding pemisah, kayu jati

03-3434-2002 0.0195 Kayu jati balok @ Rp. 20,000,000.00 390,000.00

0.0070 Kayu jati papan @ Rp. 22,000,000.00 154,000.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.4500 org Tukang kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala tukang kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 32,025.00 544,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka dinding pemisah, kayu jati lokal

03-3434-2002 0.0195 Kayu jati lokal balok @ Rp. 10,000,000.00 195,000.00

0.0070 Kayu jati lokal papan @ Rp. 11,000,000.00 77,000.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.4500 org Tukang kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala tukang kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 32,025.00 272,800.00 JASA 10 %JUMLAHDIBULATKAN

m1 Pasang talang ½ lingkaran D - 10 cm, seng BJLS 24

m3

m2

m3

m3

m2

m3

m3

m2

m3

m3

m2

m3

m3

Page 103: AHS 2008-Kota.xlsx

Analisa Gedung - 103

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang rangka dinding pemisah, kayu kruing

03-3434-2002 0.0195 Kayu kruing balok @ Rp. 4,350,000.00 84,825.00

0.0070 Kayu kruing papan @ Rp. 4,750,000.00 33,250.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.4500 org Tukang kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala tukang kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 32,025.00 118,875.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper

03-3434-2002 0.0195 Kayu kamper balok @ Rp. 4,750,000.00 92,625.00

6.56 0.0070 Kayu kamper papan @ Rp. 5,500,000.00 38,500.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.5600 kg Lem kayu @ Rp. 11,000.00 6,160.00 1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 0.4500 org Tukang kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala tukang kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 32,025.00 138,085.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding pemisah plywoodwood rangkap, rangka kayu kamper

03-3434-2002 0.0195 Kayu kamper balok @ Rp. 4,750,000.00 92,625.00

6.57 0.0070 Kayu kamper papan @ Rp. 5,500,000.00 38,500.00 0.1000 kg Paku biasa 2" - 5" @ Rp. 8,000.00 800.00 0.5600 kg Lem kayu @ Rp. 11,000.00 6,160.00 1.0000 lbr Plywood 4' x 8' x 4 mm @ Rp. 41,250.00 41,250.00 0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala tukang kayu @ Rp. 50,000.00 3,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 39,100.00 179,335.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plywood tebal 4 mm, untuk dinding03-3434-2002 0.4000 lbr Plywood 4' x 8' x 4 mm @ Rp. 41,250.00 16,500.00

6.59 0.0500 kg Paku biasa 2" - 5" @ Rp. 8,000.00 400.00 0.0750 org Tukang kayu @ Rp. 47,500.00 3,562.50 0.0075 org Kepala tukang kayu @ Rp. 50,000.00 375.00 0.0250 org Pekerja @ Rp. 36,000.00 900.00 0.0013 org Mandor @ Rp. 40,000.00 52.00

JUMLAH ( BELUM PPN ) 4,889.50 16,900.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m3

m2

m3

m3

m2

m3

m3

m2

Page 104: AHS 2008-Kota.xlsx

Analisa Gedung - 104

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang dinding anyaman bambu, rangka kayu kruing

03-2837-2002 1.5000 Bilik bambu @ Rp. 65,000.00 97,500.00

6.27 0.0140 Kayu 5/7 kruing @ Rp. 4,350,000.00 60,900.00

0.1200 Pasir pasang @ Rp. 76,000.00 9,120.00

0.0030 List kayu 2/4 kruing @ Rp. 4,350,000.00 13,050.00 0.0500 org Tukang kayu @ Rp. 47,500.00 2,375.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0020 org Mandor @ Rp. 40,000.00 80.00

JUMLAH ( BELUM PPN ) 6,305.00 180,570.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN ATAP

H.2 1.0000 Pasang genteng paris 25.0000 bh Genteng paris @ Rp. 1,100.00 27,500.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 27,500.00 JASA 10 %JUMLAHDIBULATKAN

H.2A 1.0000 Pasang genteng paris untuk rumah tingkat 25.0000 bh Genteng paris @ Rp. 1,100.00 27,500.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 27,500.00 JASA 10 %JUMLAHDIBULATKAN

H.2A 1.0000 9.0000 bh Genteng beton natural @ Rp. 3,000.00 27,000.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 27,000.00 JASA 10 %JUMLAHDIBULATKAN

H.2A 1.0000 9.0000 bh Genteng beton natural @ Rp. 3,000.00 27,000.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 27,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m3

m3

m2

m2

m2 Pasang genteng beton besar Natural ( isi 9 / m2 )

m2 Pasang genteng beton besar Natural ( isi 9 / m2 ) untuk rumah tingkat

Page 105: AHS 2008-Kota.xlsx

Analisa Gedung - 105

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

H.2A 1.0000 9.0000 bh Genteng beton Warna @ Rp. 4,500.00 40,500.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 40,500.00 JASA 10 %JUMLAHDIBULATKAN

H.2A 1.0000 9.0000 bh Genteng beton Warna @ Rp. 4,500.00 40,500.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 40,500.00 JASA 10 %JUMLAHDIBULATKAN

H.2A 1.0000 Pasang genteng keramik berglasir KIA, Kanmuri Natural 14.5000 bh Genteng keramik KIA natural @ Rp. 5,200.00 75,400.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 75,400.00 JASA 10 %JUMLAHDIBULATKAN

H.2A 1.0000 Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat 14.5000 bh Genteng beton natural @ Rp. 5,200.00 75,400.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kep. Tk. Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 75,400.00 JASA 10 %JUMLAHDIBULATKAN

H.6 1.0000 Pasang bubungan genteng paris 5.0000 bh Bubungan genteng paris @ Rp. 2,000.00 10,000.00

0.0152 Kapur pasang @ Rp. 72,500.00 1,102.00

0.0152 Pasir pasang @ Rp. 76,000.00 1,155.20 1.5240 kg PC @ Rp. 764.00 1,164.34 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 13,421.54 JASA 10 %JUMLAHDIBULATKAN

m2 Pasang genteng beton besar Warna ( isi 9 / m2 )

m2 Pasang genteng beton besar Warna ( isi 9 / m2 ) untuk rumah tingkat

m2

m2

m1

m3

m3

Page 106: AHS 2008-Kota.xlsx

Analisa Gedung - 106

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

H.6 1.0000 Pasang bubungan genteng beton Natural 5.0000 bh Bubungan genteng beton natural @ Rp. 3,000.00 15,000.00

0.0152 Kapur pasang @ Rp. 72,500.00 1,102.00

0.0152 Pasir pasang @ Rp. 76,000.00 1,155.20 1.5240 kg PC @ Rp. 764.00 1,164.34 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 18,421.54 JASA 10 %JUMLAHDIBULATKAN

H.6 1.0000 Pasang bubungan genteng beton Warna 4.0000 bh Bubungan genteng beton warna @ Rp. 4,500.00 18,000.00

0.0152 Kapur pasang @ Rp. 72,500.00 1,102.00

0.0152 Pasir pasang @ Rp. 76,000.00 1,155.20 1.5240 kg PC @ Rp. 764.00 1,164.34 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 21,421.54 JASA 10 %JUMLAHDIBULATKAN

H.6 1.0000 Pasang bubungan genteng keramik berglasir KIA, Kanmuri Natural 4.0000 bh Bubungan gent.krmk KIA natural @ Rp. 13,500.00 54,000.00

0.0152 Kapur pasang @ Rp. 72,500.00 1,102.00

0.0152 Pasir pasang @ Rp. 76,000.00 1,155.20 1.5240 kg PC @ Rp. 764.00 1,164.34 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kep. Tk. Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 57,421.54 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang atap asbes gelombang (2,5 x 0,92 m) x 5 mmSNI 0.5000 lbr Asbes gelombang @ Rp. 70,000.00 35,000.00 6.8 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00

03-3436-2002 0.0750 org Tukang kayu @ Rp. 47,500.00 3,562.50 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 9,322.50 36,122.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap sbes gelombang (2,25 x 0,92 m) x 5 mm6.9 0.6000 lbr Asbes gelombang @ Rp. 65,000.00 39,000.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0750 org Tukang kayu @ Rp. 47,500.00 3,562.50 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 9,322.50 40,122.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m3

m1

m3

m3

m1

m3

m3

m2

m2

Page 107: AHS 2008-Kota.xlsx

Analisa Gedung - 107

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang atap asbes gelombang (2,00 x 0,92 m) x 5 mm6.10 0.6000 lbr Asbes gelombang @ Rp. 62,500.00 37,500.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 38,622.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (1,80 x 0,92 m) x 5 mm6.11 0.7500 lbr Asbes gelombang @ Rp. 57,500.00 43,125.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 44,247.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (300 x 1,05 m) x 4 mm6.12 0.3500 lbr Asbes gelombang @ Rp. 71,350.00 24,972.50

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 26,094.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,7 x 1,05 m) x 4 mm6.13 0.4200 lbr Asbes gelombang @ Rp. 64,250.00 26,985.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 28,107.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,40 x 1,05 m) x 4 mm6.14 0.4400 lbr Asbes gelombang @ Rp. 61,000.00 26,840.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 27,962.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

Page 108: AHS 2008-Kota.xlsx

Analisa Gedung - 108

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang atap asbes gelombang (2,10 x 1,05 m) x 4 mm6.15 0.5100 lbr Asbes gelombang @ Rp. 57,500.00 29,325.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 30,447.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (1,50 x 1,05 m) x 4 mm6.16 0.8000 lbr Asbes gelombang @ Rp. 35,950.00 28,760.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 29,882.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (3,00 x 1,08 m) x 6 mm6.17 0.3700 lbr Asbes gelombang @ Rp. 112,830.00 41,747.10

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 42,869.10 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,70 x 1,08 m) x 6 mm6.18 0.3800 lbr Asbes gelombang @ Rp. 101,500.00 38,570.00

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 39,692.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap sbes gelombang (2,40 x 1,08 m) x 6 mm6.19 0.4600 lbr Asbes gelombang @ Rp. 90,265.00 41,521.90

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 42,643.90 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

Page 109: AHS 2008-Kota.xlsx

Analisa Gedung - 109

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang atap asbes gelombang (2,10 x 1,08 m) x 6 mm6.20 0.4900 lbr Asbes gelombang @ Rp. 78,980.00 38,700.20

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 39,822.20 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (1,80 x 1,08 m) x 6 mm6.21 0.5700 lbr Asbes gelombang @ Rp. 67,690.00 38,583.30

03-3436-2002 0.1200 kg Paku pancing 60 x 230 @ Rp. 9,350.00 1,122.00 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 39,705.30 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang bubung stel gelombang 0,92 m6.22 2.4000 lbr Bubung stel gelombang @ Rp. 43,700.00 104,880.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 109,380.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel gelombang 1,05 m6.23 2.1000 lbr Nok stel gelombang @ Rp. 43,700.00 91,770.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 96,270.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel gelombang 1,08 m6.24 2.0500 lbr Nok stel gelombang @ Rp. 43,700.00 89,585.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 94,085.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m1

m1

m1

Page 110: AHS 2008-Kota.xlsx

Analisa Gedung - 110

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang nok paten 0,92 m6.25 1.2000 lbr Nok paten @ Rp. 50,000.00 60,000.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 64,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok paten 1,05 m6.26 1.2000 lbr Nok paten @ Rp. 50,000.00 60,000.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 64,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok paten 1,08 m6.27 1.2000 lbr Nok paten @ Rp. 50,000.00 60,000.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 64,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel rata 0,92 m6.28 1.1000 lbr Nok stel rata @ Rp. 25,000.00 27,500.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 11,535.00 32,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel rata 1,09 m6.29 1.1000 lbr Nok stel rata @ Rp. 25,000.00 27,500.00

03-3436-2002 6.0000 bh Paku sekrup 3,5" @ Rp. 750.00 4,500.00 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 32,000.00 JASA 10 %JUMLAHDIBULATKAN

m1

m1

m1

m1

m1

Page 111: AHS 2008-Kota.xlsx

Analisa Gedung - 111

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.39 1.0000 Pasang nok atap seng 0.3000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 44,000.00 13,200.00 0.0400 kg Paku biasa 1/2" - 1" @ Rp. 10,000.00 400.00 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 9,365.00 13,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap genteng metal zinc alume type prima roof

03-3436-2002 1.0200 Genteng metal @ Rp. 135,300.00 138,006.00 6.32 0.2000 kg Paku anti karat @ Rp. 25,000.00 5,000.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 12,490.00 143,006.00 JASA 10 %JUMLAHDIBULATKAN

Mod. SNI 1.0000 Pasang atap metal gelombanmg

03-3436-2002 1.0200 Atap metal gelombang t 3,5 mm @ Rp. 110,000.00 112,200.00 6.32 4.0000 bh Paku/skrup atap anti karat @ Rp. 1,500.00 6,000.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 12,490.00 118,200.00 JASA 10 %JUMLAHDIBULATKAN

6.36 1.0000 Pasang nok genteng metal U type prima roof 1.1000 bh Nok metal @ Rp. 40,000.00 44,000.00 0.0500 kg Paku anti karat @ Rp. 25,000.00 1,250.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 17,395.00 45,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap alumunium

03-3436-2002 1.0500 Atap alumunium gelombang tebal 0,55 @ Rp. 75,000.00 78,750.00 6.40 0.0200 kg Paku hak panjang 15 cm @ Rp. 9,500.00 190.00

0.7500 org Tukang kayu @ Rp. 47,500.00 35,625.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 41,665.00 78,940.00 JASA 10 %JUMLAHDIBULATKAN

m1

m2

m2

m2

m2

m1

m2

m2

Page 112: AHS 2008-Kota.xlsx

Analisa Gedung - 112

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang nok alumunium

03-3436-2002 1.2000 Nok standar 40 cm 18 SWG 22 @ Rp. 25,000.00 30,000.00 6.41 0.0400 kg Paku hak panjang 15 cm @ Rp. 9,500.00 380.00

1.0000 org Tukang kayu @ Rp. 47,500.00 47,500.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 52,000.00 30,380.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang alumunium foil / sisalation

03-3436-2002 1.0500 Sisalation / alumunium foil @ Rp. 25,000.00 26,250.00 6.42 0.0500 org Tukang kayu @ Rp. 47,500.00 2,375.00

0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 8,345.00 26,250.00 JASA 10 %JUMLAHDIBULATKAN

Empiris 1.0000 Pasang atap polikarbonat

1.0500 Plykarbhonat @ Rp. 200,000.00 210,000.00 7.0000 kg Besi rangka @ Rp. 8,800.00 61,600.00 9.0000 bh Paku sekrup @ Rp. 1,500.00 13,500.00 0.5000 org Tukang besi @ Rp. 45,000.00 22,500.00 0.0500 org Kepala tukang besi @ Rp. 47,500.00 2,375.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 42,975.00 285,100.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN CAT-CATAN

K.9 10.0000 Mengecat kerb 3 kali 4.2500 kg Cat emco @ Rp. 29,500.00 125,375.00 0.5700 ltr Minyak cat @ Rp. 14,000.00 7,980.00 3.0000 org Tukang cat @ Rp. 42,500.00 127,500.00 0.3000 org Kep. Tk. Cat @ Rp. 45,000.00 13,500.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

217,000.00 133,355.00

21,700.00 13,335.50 JASA 10 %JUMLAHDIBULATKAN

14,466.67 8,890.33 JASA 10 %JUMLAHDIBULATKAN

7,233.33 4,445.17 JASA 10 %JUMLAHDIBULATKAN

m1

m1

m2

m2

m2

m2

m2

TIAP 1 M2 ( 3 kali )

TIAP 1 M2 ( 2 kali )

TIAP 1 M2 ( 1 kali )

Page 113: AHS 2008-Kota.xlsx

Analisa Gedung - 113

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Mengikis / mengerok permukaan cat tembok lama6.1 0.0500 kg Soda api @ Rp. 25,000.00 1,250.00

0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 5,500.00 1,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerok karat cat lama permukaan baja dengan cara manual6.3 0.0500 kg Sabun @ Rp. 20,000.00 1,000.00

0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 5,500.00 1,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mendempul dan menggosok kayu6.6 0.0800 kg Dempul jadi @ Rp. 10,000.00 800.00

0.0200 kg Minyak cat @ Rp. 14,000.00 280.00 0.0100 kg Batu apung @ Rp. 22,000.00 220.00 0.0400 org Tukang cat @ Rp. 42,500.00 1,700.00 0.0040 org Kepala tukang cat @ Rp. 45,000.00 180.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,420.00 1,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang kayu lama6.7 0.1500 kg Plamir @ Rp. 20,000.00 3,000.00

0.1700 kg Cat dasar @ Rp. 29,500.00 5,015.00 0.1700 kg Cat penutup @ Rp. 29,500.00 5,015.00 0.0750 org Tukang cat @ Rp. 42,500.00 3,187.50 0.0075 org Kepala tukang cat @ Rp. 45,000.00 337.50 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,145.00 13,030.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup6.8 0.2000 kg Cat meni @ Rp. 15,000.00 3,000.00

0.1500 kg Plamir @ Rp. 20,000.00 3,000.00 0.1700 kg Cat dasar @ Rp. 29,500.00 5,015.00 0.2600 kg Cat penutup @ Rp. 29,500.00 7,670.00 0.0900 org Tukang cat @ Rp. 42,500.00 3,825.00 0.0060 org Kepala tukang cat @ Rp. 45,000.00 270.00 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,715.00 18,685.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

Page 114: AHS 2008-Kota.xlsx

Analisa Gedung - 114

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup6.9 0.2000 kg Cat meni @ Rp. 15,000.00 3,000.00

0.1500 kg Plamir @ Rp. 20,000.00 3,000.00 0.1700 kg Cat dasar @ Rp. 29,500.00 5,015.00 0.3500 kg Cat penutup @ Rp. 29,500.00 10,325.00 0.1050 org Tukang cat @ Rp. 42,500.00 4,462.50 0.0040 org Kepala tukang cat @ Rp. 45,000.00 180.00 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 7,262.50 21,340.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan teak oil6.10 0.3600 ltr Teak oil @ Rp. 35,000.00 12,600.00

0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0630 org Kepala tukang cat @ Rp. 45,000.00 2,835.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 7,052.50 12,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan politur6.11 0.1500 ltr Politur @ Rp. 40,000.00 6,000.00

0.3720 ltr Politur jadi @ Rp. 40,000.00 14,880.00 2.0000 lbr Amplas @ Rp. 3,500.00 7,000.00 0.0600 org Tukang cat @ Rp. 42,500.00 2,550.00 0.0160 org Kepala tukang cat @ Rp. 45,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,370.00 27,880.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan cat residu atau ter6.12 0.3500 ltr Residu atau ter @ Rp. 3,500.00 1,225.00

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 3,840.00 1,225.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan vernis6.13 0.1500 ltr Vernis @ Rp. 40,000.00 6,000.00

0.0500 kg Dempul @ Rp. 10,000.00 500.00 0.1000 lbr Amplas @ Rp. 3,500.00 350.00 0.0100 bh Kuas @ Rp. 9,100.00 91.00 0.1600 org Tukang cat @ Rp. 42,500.00 6,800.00 0.0160 org Kepala tukang cat @ Rp. 45,000.00 720.00 0.1600 org Pekerja @ Rp. 36,000.00 5,760.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 13,380.00 6,941.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

Page 115: AHS 2008-Kota.xlsx

Analisa Gedung - 115

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)6.14 0.1000 kg Plamir tembok @ Rp. 18,000.00 1,800.00

0.1000 kg Cat dasar @ Rp. 10,000.00 1,000.00 0.2600 kg Cat penutup 2 x @ Rp. 10,000.00 2,600.00 0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0063 org Kepala tukang cat @ Rp. 45,000.00 283.50 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,781.00 5,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)6.15 0.1200 kg Cat dasar @ Rp. 10,000.00 1,200.00

0.1800 kg Cat penutup 2 x @ Rp. 10,000.00 1,800.00 0.0420 org Tukang cat @ Rp. 42,500.00 1,785.00 0.0042 org Kepala tukang cat @ Rp. 45,000.00 189.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,082.00 3,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan tembok tidak terlindung dari panas dan hujan6.14 0.1000 kg Cat alkali resisting primer @ Rp. 45,000.00 4,500.00

0.3600 kg Cat ICI Weathershield @ Rp. #NAME? #NAME? 0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0063 org Kepala tukang cat @ Rp. 45,000.00 283.50 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,781.00 #NAME?JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Melabur tembok dengan kalkarium6.16 0.1000 kg Kalkarium @ Rp. 8,500.00 850.00

0.0420 org Tukang cat @ Rp. 42,500.00 1,785.00 0.0042 org Kepala tukang cat @ Rp. 45,000.00 189.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,082.00 850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Melabur tembok dengan kapur sirih6.17 0.1000 lbr Amplas @ Rp. 3,500.00 350.00

0.2500 ikat Alang-alang @ Rp. 500.00 125.00

0.0020 Perancah kayu @ Rp. 1,000,000.00 2,000.00 0.1500 kg Kapur sirih @ Rp. 500.00 75.00 0.0010 org Tukang cat @ Rp. 42,500.00 42.50 0.0001 org Kepala tukang cat @ Rp. 45,000.00 4.50 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 5,547.00 2,550.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

m3

Page 116: AHS 2008-Kota.xlsx

Analisa Gedung - 116

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Melabur tembok tembok lama dengan kapur sirih (untuk pemeliharaan)

6.18 0.0020 Perancah kayu @ Rp. 1,000,000.00 2,000.00 0.3000 kg Kapur sirih @ Rp. 500.00 150.00 0.0050 org Tukang cat @ Rp. 42,500.00 212.50 0.0005 org Kepala tukang cat @ Rp. 45,000.00 22.50 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 1,775.00 2,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang besi ( 3 x )6.9 0.1670 kg Cat meni besi @ Rp. 15,000.00 2,505.00

0.2000 kg Cat besi @ Rp. 29,500.00 5,900.00 0.1500 ltr Thinner @ Rp. 15,000.00 2,250.00 0.1050 org Tukang cat @ Rp. 42,500.00 4,462.50 0.0040 org Kepala tukang cat @ Rp. 45,000.00 180.00 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 7,262.50 10,655.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 m2 Melamin 0.2000 Cat tembok melamin @ Rp. 29,500.00 5,900.00 0.0150 Kuas 3" @ Rp. 9,100.00 136.50 0.2000 Pekerja @ Rp. 42,500.00 8,500.00 0.1000 Tukang cat @ Rp. 45,000.00 4,500.00 0.0050 Kep. Tukang cat @ Rp. 36,000.00 180.00 0.0005 Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 13,200.00 6,036.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pemasangan wall paper

6.19 1.2000 Wall paper @ Rp. 40,000.00 48,000.00 0.2000 kg Perekat @ Rp. 60,000.00 12,000.00 0.2000 org Tukang cat @ Rp. 42,500.00 8,500.00 0.0020 org Kepala tukang cat @ Rp. 45,000.00 90.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 9,410.00 60,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecacatan permukaan baja dengan meni besi6.20 0.1000 kg Meni besi Zinchromate @ Rp. 25,000.00 2,500.00

0.0100 bh Kuas @ Rp. 9,100.00 91.00 0.2000 org Tukang cat @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang cat @ Rp. 45,000.00 900.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 10,520.00 2,591.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecacatan permukaan baja dengan meni besi memakai perancah6.21 0.1000 kg Meni besi Zinchromate @ Rp. 25,000.00 2,500.00

0.0100 bh Kuas @ Rp. 9,100.00 91.00

0.0020 Perancah kayu @ Rp. 1,000,000.00 2,000.00 0.2250 org Tukang cat @ Rp. 42,500.00 9,562.50 0.0225 org Kepala tukang cat @ Rp. 45,000.00 1,012.50 0.2250 org Pekerja @ Rp. 36,000.00 8,100.00

m2

m3

m2

m2

m2

m2

m2

m3

Page 117: AHS 2008-Kota.xlsx

Analisa Gedung - 117

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,975.00 4,591.00 JASA 10 %JUMLAHDIBULATKAN

Page 118: AHS 2008-Kota.xlsx

Analisa Gedung - 118

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pengetiran kayu ( 2 x ) 0.3500 kg Tir @ Rp. 8,000.00 2,800.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 3,800.00 2,800.00 JASA 10 %JUMLAHDIBULATKAN

Empiris 1.0000 Pekerjaan cat duco 3 x 0.4250 kg Cat duco @ Rp. 70,000.00 29,750.00 0.0570 ltr Thinner @ Rp. 14,000.00 798.00 0.1000 lbr Amplas @ Rp. 3,500.00 350.00 0.3000 org Tukang cat @ Rp. 42,500.00 12,750.00 0.0300 org Kep. Tk. Cat @ Rp. 45,000.00 1,350.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 22,050.00 30,548.00 JASA 10 %JUMLAHDIBULATKAN

31 1.0000 Mengecat genteng 0.3600 kg Cat genteng air ICI Weathershield @ Rp. 45,000.00 16,200.00 0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0063 org Kep. Tk. Cat @ Rp. 45,000.00 283.50 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH 3,781.00 16,200.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN BONGKARAN

AK 1.0000 Membongkar pasangan batu kali 4.0000 org Tukang batu @ Rp. 42,500.00 170,000.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00

JUMLAH ( BELUM PPN ) 184,400.00 - JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Membongkar pasangan batu merah dan membersihkan 2.0000 org Tukang batu @ Rp. 42,500.00 85,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00

JUMLAH ( BELUM PPN ) 88,600.00 - JASA 10 %JUMLAHDIBULATKAN

AK 1.0000 Membongkar beton bertulang dan membersihkan 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 8.0000 org Pekerja @ Rp. 36,000.00 288,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 300,500.00 - JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m3

m3

m3

Page 119: AHS 2008-Kota.xlsx

Analisa Gedung - 119

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

AK 10.0000 Pekerjaan bongkar lantai tegel untuk dipergunakan lagi 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 76,000.00 -

TIAP 1M2 ( BELUM PPN ) 7,600.00 - JASA 10 %JUMLAHDIBULATKAN

I.6 10.0000 Mengupas plesteran lama 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00 0.1250 org Mandor @ Rp. 40,000.00 5,000.00

JUMLAH ( BELUM PPN ) 50,000.00 -

TIAP 1M2 ( BELUM PPN ) 5,000.00 - JASA 10 %JUMLAHDIBULATKAN

I.7 10.0000 Membongkar genteng / sirap untuk dipergunakan lagi 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 76,000.00 -

TIAP 1M2 ( BELUM PPN ) 7,600.00 - JASA 10 %JUMLAHDIBULATKAN

I.8 10.0000 Membongkar atap seng 0.5000 org Tukang besi @ Rp. 45,000.00 22,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00

JUMLAH ( BELUM PPN ) 58,500.00 -

TIAP 1M2 ( BELUM PPN ) 5,850.00 - JASA 10 %JUMLAHDIBULATKAN

I.9 10.0000 Membongkar usuk / reng dipakai lagi 0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kep. Tk. Kayu @ Rp. 50,000.00 3,000.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 107,500.00 -

TIAP 1M2 ( BELUM PPN ) 10,750.00 - JASA 10 %JUMLAHDIBULATKAN

10.0000 Membongkar usuk / reng tidak dipakai lagi 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 76,000.00 -

TIAP 1M2 ( BELUM PPN ) 7,600.00 - JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

m2

Page 120: AHS 2008-Kota.xlsx

Analisa Gedung - 120

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

L.12 1.0000 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi 6.0000 org Tukang kayu @ Rp. 47,500.00 285,000.00 0.6000 org Kep. Tk. Kayu @ Rp. 50,000.00 30,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 467,000.00 - JASA 10 %JUMLAHDIBULATKAN

1.0000 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 44,000.00 - JASA 10 %JUMLAHDIBULATKAN

L.14 1.0000 Mengerjakan kembali bangunan kayu yang telah dibongkar 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kep. Tk. Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 - JASA 10 %JUMLAHDIBULATKAN

ANALISA SUPLEMEN

1 1.0000 Pasang pipa beton oval dia. 25/37,5 dalam 0 - 1 m1.0000 bh Pipa beton oval @ Rp. 55,000.00 55,000.00 0.7500 org Pekerja @ Rp. 36,000.00 27,000.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 Org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 33,975.00 55,000.00 JASA 10 %JUMLAHDIBULATKAN

2 1.0000 Pasang pipa beton oval dia. 25/37,5 dalam 1 - 2 m1 bh Pipa beton oval @ Rp. 55,000.00 55,000.00

1.5 org Pekerja @ Rp. 36,000.00 54,000.00 0.15 org Tukang batu @ Rp. 42,500.00 6,375.00

0.015 Org Mandor @ Rp. 40,000.00 600.00 JUMLAH ( BELUM PPN ) 60,975.00 55,000.00 JASA 10 %JUMLAHDIBULATKAN

3 1.0000 M Pengelasan Single ( las listrik )3.0000 kg Kawat las @ Rp. 6,500.00 19,500.00 1.0000 hari Peralatan las @ Rp. 75,000.00 75,000.00 0.5000 org Tukang las @ Rp. 45,000.00 22,500.00 0.0500 org Kepala tukang las @ Rp. 47,500.00 2,375.00 1.0000 Org Pekerja @ Rp. 42,500.00 42,500.00 1.0000 Org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 107,375.00 94,500.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m1

m1

Page 121: AHS 2008-Kota.xlsx

Analisa Gedung - 121

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

PEKERJAAN SANITASI SNI 1.0000 bh Memasang kloset duduk/monoblock

1.0000 bh Kloset duduk / monoblock @ Rp. 2,000,000.00 2,000,000.00 6.1 6% x Harga kloset (Perlengkapan) @ Rp. 2,000,000.00 120,000.00

1.1000 org Tukang batu @ Rp. 42,500.00 46,750.00 0.0010 org Kepala tukang batu @ Rp. 45,000.00 45.00 3.3000 org Pekerja @ Rp. 36,000.00 118,800.00 0.1600 org Mandor @ Rp. 40,000.00 6,400.00

JUMLAH ( BELUM PPN ) 171,995.00 2,120,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang kloset jongkok porselen 1.0000 bh Kloset jongkok porselen @ Rp. 300,000.00 300,000.00

6.2 6.0000 kg PC @ Rp. 764.00 4,584.00

0.0100 Pasir pasang @ Rp. 76,000.00 760.00 1.5000 org Tukang batu @ Rp. 42,500.00 63,750.00 1.5000 org Kepala tukang batu @ Rp. 45,000.00 67,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1600 org Mandor @ Rp. 40,000.00 6,400.00

JUMLAH ( BELUM PPN ) 173,650.00 305,344.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang kloset jongkok teraso 1.0000 bh Kloset jongkok teraso @ Rp. 85,000.00 85,000.00

6.3 7.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 350.00 2,450.00 6.0000 kg PC @ Rp. 764.00 4,584.00

0.0100 Pasir pasang @ Rp. 76,000.00 760.00 1.5000 org Tukang batu @ Rp. 42,500.00 63,750.00 0.3000 org Kepala tukang batu @ Rp. 45,000.00 13,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1100 org Mandor @ Rp. 40,000.00 4,400.00

JUMLAH ( BELUM PPN ) 117,650.00 92,794.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang urinoir 1.0000 bh Urinoir @ Rp. 2,000,000.00 2,000,000.00

6.4 30% x Harga urinoir (Perlengkapan) @ Rp. 2,000,000.00 600,000.00 6.0000 kg PC @ Rp. 764.00 4,584.00

0.0100 Pasir pasang @ Rp. 76,000.00 760.00 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.1000 org Kepala tukang batu @ Rp. 45,000.00 4,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 87,000.00 2,605,344.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang wastafel 1.0000 bh Wastafel @ Rp. 850,000.00 850,000.00

6.5 12% x Harga wastafel (Perlengkapan) @ Rp. 850,000.00 102,000.00 6.0000 kg PC @ Rp. 764.00 4,584.00

0.0100 Pasir pasang @ Rp. 76,000.00 760.00 1.4500 org Tukang batu @ Rp. 42,500.00 61,625.00 0.1500 org Kepala tukang batu @ Rp. 45,000.00 6,750.00 1.2000 org Pekerja @ Rp. 36,000.00 43,200.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 115,575.00 957,344.00 JASA 10 %JUMLAH

m3

m3

m3

m3

Page 122: AHS 2008-Kota.xlsx

Analisa Gedung - 122

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 123: AHS 2008-Kota.xlsx

Analisa Gedung - 123

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 bh 1.0000 bh Bak fiberglass @ Rp. 350,000.00 350,000.00

6.7 18% x Harga bak(Perlengkapan) @ Rp. 350,000.00 63,000.00 2.7000 org Tukang batu @ Rp. 42,500.00 114,750.00 0.5400 org Kepala tukang batu @ Rp. 45,000.00 24,300.00 1.8000 org Pekerja @ Rp. 36,000.00 64,800.00 0.1100 org Mandor @ Rp. 40,000.00 4,400.00

JUMLAH ( BELUM PPN ) 208,250.00 413,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang badkip porselen 1.0000 bh Badkip @ Rp. 350,000.00 350,000.00

6.9 20% x Harga badkip (Perlengkapan) @ Rp. 350,000.00 70,000.00 0.0750 org Tukang batu @ Rp. 42,500.00 3,187.50 0.7500 org Kepala tukang batu @ Rp. 45,000.00 33,750.00

org Pekerja @ Rp. 36,000.00 - 0.2500 org Mandor @ Rp. 40,000.00 10,000.00

JUMLAH ( BELUM PPN ) 46,937.50 420,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh 1.0000 bh Bak fiberglass @ Rp. 1,100,000.00 1,100,000.00

6.11 12% x Harga bak (Perlengkapan) @ Rp. 1,100,000.00 132,000.00 4.5000 org Tukang batu @ Rp. 42,500.00 191,250.00 0.9000 org Kepala tukang batu @ Rp. 45,000.00 40,500.00 3.0000 org Pekerja @ Rp. 36,000.00 108,000.00 0.9000 org Mandor @ Rp. 40,000.00 36,000.00

JUMLAH ( BELUM PPN ) 375,750.00 1,232,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm 1.6000 bh Pipa tanah @ Rp. 35,000.00 56,000.00

6.12 0.6800 kg PC @ Rp. 764.00 519.52

0.0130 Pasir pasang @ Rp. 76,000.00 988.00

0.0110 Pasir urug @ Rp. 55,000.00 605.00 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,670.00 58,112.52 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm 1.6000 bh Pipa tanah @ Rp. 45,000.00 72,000.00

6.13 0.8700 kg PC @ Rp. 764.00 664.68

0.0140 Pasir pasang @ Rp. 76,000.00 1,064.00

0.1400 Pasir urug @ Rp. 55,000.00 7,700.00 0.0400 org Tukang batu @ Rp. 42,500.00 1,700.00 0.0040 org Kepala tukang batu @ Rp. 45,000.00 180.00 0.0800 org Pekerja @ Rp. 36,000.00 2,880.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 5,040.00 81,428.68 JASA 10 %JUMLAHDIBULATKAN

Memasang bak mandi fiberglass volume 0,30 m3

Memasang bak fiberglass volume 1 m3 air

m1

m3

m3

m1

m3

m3

Page 124: AHS 2008-Kota.xlsx

Analisa Gedung - 124

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Memasang pipa beton, diameter 15 cm - 20 cm 1.1000 bh Pipa beton @ Rp. 45,000.00 49,500.00

6.14 16.0000 bh Batu bata @ Rp. 350.00 5,600.00 3.9200 kg PC @ Rp. 764.00 2,994.88

0.0560 Pasir pasang @ Rp. 76,000.00 4,256.00

0.0240 Pasir urug @ Rp. 55,000.00 1,320.00 0.0700 org Tukang batu @ Rp. 42,500.00 2,975.00 0.0070 org Kepala tukang batu @ Rp. 45,000.00 315.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,610.00 63,670.88 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa beton, diameter 30 cm - 100 cm 1.1000 bh Pipa beton @ Rp. 50,000.00 55,000.00

6.15 330.0000 bh Batu bata @ Rp. 350.00 115,500.00 10.3000 kg PC @ Rp. 764.00 7,869.20

0.0610 Pasir pasang @ Rp. 76,000.00 4,636.00

0.0690 Pasir urug @ Rp. 55,000.00 3,795.00 0.1900 org Tukang batu @ Rp. 42,500.00 8,075.00 0.0190 org Kepala tukang batu @ Rp. 45,000.00 855.00 0.3800 org Pekerja @ Rp. 36,000.00 13,680.00 0.0190 org Mandor @ Rp. 40,000.00 760.00

JUMLAH ( BELUM PPN ) 23,370.00 186,800.20 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm 87.0000 bh Batu bata @ Rp. 350.00 30,450.00

6.16 44.0000 kg PC @ Rp. 764.00 33,616.00

0.0700 Pasir pasang @ Rp. 76,000.00 5,320.00

0.0700 Batu kerikil @ Rp. 55,000.00 3,850.00 1.6000 kg Besi beton @ Rp. 7,900.00 12,640.00

0.0600 Pasir beton @ Rp. 73,000.00 4,380.00 1.0150 org Tukang batu @ Rp. 42,500.00 43,137.50 0.0015 org Kepala tukang batu @ Rp. 45,000.00 67.50 3.2000 org Pekerja @ Rp. 36,000.00 115,200.00 0.0160 org Mandor @ Rp. 40,000.00 640.00

JUMLAH ( BELUM PPN ) 159,045.00 90,256.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm 150.0000 bh Batu bata @ Rp. 350.00 52,500.00

6.17 77.0000 kg PC @ Rp. 764.00 58,828.00

0.1300 Pasir pasang @ Rp. 76,000.00 9,880.00

0.0200 Batu kerikil @ Rp. 55,000.00 1,100.00 2.6000 kg Besi beton @ Rp. 7,900.00 20,540.00

0.0900 Pasir beton @ Rp. 73,000.00 6,570.00 0.4730 org Tukang batu @ Rp. 42,500.00 20,102.50 0.0470 org Kepala tukang batu @ Rp. 45,000.00 2,115.00 1.4200 org Pekerja @ Rp. 36,000.00 51,120.00 0.0710 org Mandor @ Rp. 40,000.00 2,840.00

JUMLAH ( BELUM PPN ) 76,177.50 149,418.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m3

m1

m3

m3

m3

m3

m3

m3

m3

m3

Page 125: AHS 2008-Kota.xlsx

Analisa Gedung - 125

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 bh Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm 222.0000 bh Batu bata @ Rp. 350.00 77,700.00

6.18 114.0000 kg PC @ Rp. 764.00 87,096.00

0.1840 Pasir pasang @ Rp. 76,000.00 13,984.00

0.0330 Batu kerikil @ Rp. 55,000.00 1,815.00 4.8500 kg Besi beton @ Rp. 7,900.00 38,315.00

0.1200 Pasir beton @ Rp. 73,000.00 8,760.00 0.7200 org Tukang batu @ Rp. 42,500.00 30,600.00 0.0720 org Kepala tukang batu @ Rp. 45,000.00 3,240.00 2.1600 org Pekerja @ Rp. 36,000.00 77,760.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 115,600.00 227,670.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 1/2"

1.2000 Pipa galvanis @ Rp. 15,000.00 18,000.00 6.19 35% x Harga pipa (Perlengkapan) @ Rp. 15,000.00 5,250.00

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0540 org Pekerja @ Rp. 36,000.00 1,944.00 0.0270 org Mandor @ Rp. 40,000.00 1,080.00

JUMLAH ( BELUM PPN ) 7,254.00 23,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 3/4"

1.2000 Pipa galvanis @ Rp. 25,000.00 30,000.00 6.20 35% x Harga pipa (Perlengkapan) @ Rp. 25,000.00 8,750.00

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0540 org Pekerja @ Rp. 36,000.00 1,944.00 0.0270 org Mandor @ Rp. 40,000.00 1,080.00

JUMLAH ( BELUM PPN ) 7,254.00 38,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 1"

1.2000 Pipa galvanis @ Rp. 37,500.00 45,000.00 6.21 35% x Harga pipa (Perlengkapan) @ Rp. 37,500.00 13,125.00

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0540 org Pekerja @ Rp. 36,000.00 1,944.00 0.0270 org Mandor @ Rp. 40,000.00 1,080.00

JUMLAH ( BELUM PPN ) 7,254.00 58,125.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 1 1/2"

1.2000 Pipa galvanis @ Rp. 50,000.00 60,000.00 6.22 35% x Harga pipa (Perlengkapan) @ Rp. 50,000.00 17,500.00

0.1800 org Tukang batu @ Rp. 42,500.00 7,650.00 0.0180 org Kepala tukang batu @ Rp. 45,000.00 810.00 0.1080 org Pekerja @ Rp. 36,000.00 3,888.00 0.0054 org Mandor @ Rp. 40,000.00 216.00

JUMLAH ( BELUM PPN ) 12,564.00 77,500.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m3

m1

m1

m1

m1

m1

m1

m1

m1

Page 126: AHS 2008-Kota.xlsx

Analisa Gedung - 126

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Memasang pipa galvanis diameter 3"

1.2000 Pipa galvanis @ Rp. 85,000.00 102,000.00 6.23 35% x Harga pipa (Perlengkapan) @ Rp. 85,000.00 29,750.00

0.1800 org Tukang batu @ Rp. 42,500.00 7,650.00 0.0180 org Kepala tukang batu @ Rp. 45,000.00 810.00 0.1080 org Pekerja @ Rp. 36,000.00 3,888.00 0.0054 org Mandor @ Rp. 40,000.00 216.00

JUMLAH ( BELUM PPN ) 12,564.00 131,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 4"

1.2000 Pipa galvanis @ Rp. 90,000.00 108,000.00 6.24 35% x Harga pipa (Perlengkapan) @ Rp. 90,000.00 31,500.00

0.2250 org Tukang batu @ Rp. 42,500.00 9,562.50 0.0225 org Kepala tukang batu @ Rp. 45,000.00 1,012.50 0.1350 org Pekerja @ Rp. 36,000.00 4,860.00 0.0068 org Mandor @ Rp. 40,000.00 272.00

JUMLAH ( BELUM PPN ) 15,707.00 139,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1/2"

1.2000 Pipa PVC @ Rp. 3,162.50 3,795.00 6.25 35% x Harga pipa (Perlengkapan) @ Rp. 3,162.50 1,106.88

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 4,901.88 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 3/4"

1.2000 Pipa PVC @ Rp. 4,250.00 5,100.00 6.26 35% x Harga pipa (Perlengkapan) @ Rp. 4,250.00 1,487.50

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 6,587.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1"

1.2000 Pipa PVC @ Rp. 5,125.00 6,150.00 6.27 35% x Harga pipa (Perlengkapan) @ Rp. 5,125.00 1,793.75

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 7,943.75 JASA 10 %JUMLAHDIBULATKAN

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 127: AHS 2008-Kota.xlsx

Analisa Gedung - 127

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1 1/2"

1.2000 Pipa PVC @ Rp. 11,250.00 13,500.00 6.28 35% x Harga pipa (Perlengkapan) @ Rp. 11,250.00 3,937.50

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 17,437.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 2"

1.2000 Pipa PVC @ Rp. 15,000.00 18,000.00 6.29 35% x Harga pipa (Perlengkapan) @ Rp. 15,000.00 5,250.00

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0544 org Pekerja @ Rp. 36,000.00 1,958.40 0.0027 org Mandor @ Rp. 40,000.00 108.00

JUMLAH ( BELUM PPN ) 6,296.40 23,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 2 1/2"

1.2000 Pipa PVC @ Rp. 20,500.00 24,600.00 6.30 35% x Harga pipa (Perlengkapan) @ Rp. 20,500.00 7,175.00

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 31,775.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 3"

1.2000 Pipa PVC @ Rp. 20,500.00 24,600.00 6.31 35% x Harga pipa (Perlengkapan) @ Rp. 20,500.00 7,175.00

0.1350 org Tukang batu @ Rp. 42,500.00 5,737.50 0.0135 org Kepala tukang batu @ Rp. 45,000.00 607.50 0.0810 org Pekerja @ Rp. 36,000.00 2,916.00 0.0410 org Mandor @ Rp. 40,000.00 1,640.00

JUMLAH ( BELUM PPN ) 10,901.00 31,775.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 4"

1.2000 Pipa PVC @ Rp. 33,750.00 40,500.00 6.32 35% x Harga pipa (Perlengkapan) @ Rp. 33,750.00 11,812.50

0.1350 org Tukang batu @ Rp. 42,500.00 5,737.50 0.0135 org Kepala tukang batu @ Rp. 45,000.00 607.50 0.0810 org Pekerja @ Rp. 36,000.00 2,916.00 0.0410 org Mandor @ Rp. 40,000.00 1,640.00

JUMLAH ( BELUM PPN ) 10,901.00 52,312.50 JASA 10 %JUMLAHDIBULATKAN

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 128: AHS 2008-Kota.xlsx

Analisa Gedung - 128

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 bh Memasang bak cuci piring stainless steel 1.0000 bh Bak cuci stainless steel @ Rp. 500,000.00 500,000.00

6.33 1.0000 set Water drain + asesories @ Rp. 200,000.00 200,000.00 0.3000 org Tukang batu @ Rp. 42,500.00 12,750.00 0.0300 org Kepala tukang batu @ Rp. 45,000.00 1,350.00 0.0300 org Pekerja @ Rp. 36,000.00 1,080.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 15,240.00 700,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak cuci piring teraso 1.0000 bh Bak cuci teraso @ Rp. 350,000.00 350,000.00

6.34 1.0000 set Water drain + asesories @ Rp. 200,000.00 200,000.00 20.0000 kg PC @ Rp. 764.00 15,280.00

0.0500 Pasir pasang @ Rp. 76,000.00 3,800.00 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kepala tukang batu @ Rp. 45,000.00 2,250.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 25,400.00 569,080.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang kran diameter 3/4" atau 1/2" 1.0000 bh Kran air @ Rp. 185,000.00 185,000.00

6.35 0.0250 bh Seal tape @ Rp. 8,500.00 212.50 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 5,260.00 185,212.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang floor drain 1.0000 bh Floor drain @ Rp. 135,000.00 135,000.00

6.35 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 5,260.00 135,000.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN BESI DAN ALUMUNIUM SNI 1.0000 kg Pasang rangka atap baja

1.1000 kg Baja profil IWF @ Rp. 8,800.00 9,680.00 6.1 0.0800 kg Meni besi @ Rp. 25,000.00 2,000.00

0.0060 org Tukang besi @ Rp. 45,000.00 270.00 0.0060 org Kepala tukang besi @ Rp. 47,500.00 285.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0003 org Mandor @ Rp. 40,000.00 12.00

JUMLAH ( BELUM PPN ) 2,727.00 11,680.00 JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg Kuda-kuda baja siku 110.0000 kg Besi siku rata-rata @ Rp. 8,800.00 968,000.00 2.5000 org Pekerja @ Rp. 36,000.00 90,000.00 2.5000 org Tukang besi @ Rp. 45,000.00 112,500.00 0.5000 org Kep. Tukang @ Rp. 47,500.00 23,750.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

m3

Page 129: AHS 2008-Kota.xlsx

Analisa Gedung - 129

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) JUMLAH ( BELUM PPN ) 230,250.00 968,000.00 Peralatan 5%

1 kg kuda-kuda baja siku 0.01 JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg Plat besi lembaran 110.0000 kg Besi plat lembaran @ Rp. 7,500.00 825,000.00 2.5000 org Pekerja @ Rp. 36,000.00 90,000.00 2.5000 org Tukang besi @ Rp. 45,000.00 112,500.00 0.5000 org Kep. Tukang @ Rp. 47,500.00 23,750.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 230,250.00 825,000.00 Peralatan 5%

1 kg plat besi 0.01 JASA 10 %JUMLAH

Page 130: AHS 2008-Kota.xlsx

Analisa Gedung - 130

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

tambahan 1.0000 kg Gordingbaja 110.0000 kg Besi gording canal @ Rp. 8,800.00 968,000.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 1.5000 org Tukang besi @ Rp. 45,000.00 67,500.00 0.3000 org Kep. Tukang @ Rp. 47,500.00 14,250.00 0.0600 org Mandor @ Rp. 40,000.00 2,400.00

JUMLAH ( BELUM PPN ) 138,150.00 968,000.00 Peralatan 5%

1 kg gording canal C 0.01 JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg IKATAN ANGIN DIAMETER 16 MM & WATER MUR 110.0000 kg Besi beton @ Rp. 7,900.00 869,000.00 3.0000 kg Water mur @ Rp. 7,500.00 22,500.00 2.7500 org Pekerja @ Rp. 36,000.00 99,000.00 2.7500 org Tukang besi @ Rp. 45,000.00 123,750.00 1.0000 org Kep. Tukang @ Rp. 47,500.00 47,500.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 310,250.00 891,500.00 Peralatan 5%

1 kg Ikatan angin 0.01 JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg TREKSTANG DIAMETER 12 MM 110.0000 kg Besi beton @ Rp. 7,900.00 869,000.00 2.7500 org Pekerja @ Rp. 36,000.00 99,000.00 2.7500 org Tukang besi @ Rp. 45,000.00 123,750.00 1.0000 org Kep. Tukang @ Rp. 47,500.00 47,500.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 310,250.00 869,000.00 Peralatan 5%

1 kg trekstang 12mm 0.01 JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 cm Pengelasan dengan las listrik 0.0400 kg Kawat las listrik @ Rp. 6,500.00 260.00 0.0300 ltr Bahan bakar solar @ Rp. 4,300.00 129.00 0.0040 ltr Pelumas @ Rp. 14,000.00 56.00 0.0040 org Pekerja @ Rp. 36,000.00 144 0.0020 org Tukang besi @ Rp. 45,000.00 90 0.0020 org Kep. Tukang @ Rp. 47,500.00 95 0.0010 org Mandor @ Rp. 40,000.00 40 0.2500 lot Alat bantu @ Rp. 0

JUMLAH ( BELUM PPN ) 369.00 445.00 JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 Unit Manhole uk. 70 x 70 cm 6.4000 kg Besi L. 50.50.5 @ Rp. 8,500.00 54,400.00 11.5400 kg Plat baja t = 3 mm @ Rp. 10,000.00 115,400.00 8.0000 bh Angkur besi dia. 12 mm @ Rp. 17,500.00 140,000.00 2.0000 bh Engsel besi @ Rp. 25,000.00 50,000.00 1.0000 bh Kunci gembok @ Rp. 17,500.00 17,500.00 1.1250 m2 Cat besi @ Rp. 28,700.00 32,287.50 350.0000 cm Pengelasan @ Rp. 895.00 313,250.00 1.0000 ls Upah pasang @ Rp. 40,000.00 40000

JUMLAH ( BELUM PPN ) 40,000.00 722,837.50 DIBULATKAN

tambahan 1.0000 Unit 24.1280 kg Baja L.50.50.5 @ Rp. 8,500.00 205,088.00 31.6000 kg Besi beton dia. 16 mm @ Rp. 8,700.00 274,920.00 2.0000 bh Angkur dia. 16 mm @ Rp. 15,000.00 30,000.00 1.8850 m2 Cat besi @ Rp. 28,700.00 54,099.50 240.0000 cm Pengelasan @ Rp. 895.00 214,800.00

Grill dari besi beton Ǿ 16mm rangka baja 50.50.5 uk 1 x 1 m

Page 131: AHS 2008-Kota.xlsx

Analisa Gedung - 131

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) JUMLAH ( BELUM PPN ) - 778,907.50 DIBULATKAN

SNI 1.0000 Pasang pintu besi baja

1.0000 Pintu besi baja @ Rp. 750,000.00 750,000.00 6.2 0.6500 org Tukang besi konstruksi @ Rp. 45,000.00 29,250.00

0.0650 org Kepala tukang besi @ Rp. 47,500.00 3,087.50 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0320 org Mandor @ Rp. 40,000.00 1,280.00

JUMLAH ( BELUM PPN ) 57,017.50 750,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang jendela besi

1.0000 Jendela besi @ Rp. 750,000.00 750,000.00 6.3 1.0500 org Tukang besi konstruksi @ Rp. 45,000.00 47,250.00

0.1050 org Kepala tukang besi @ Rp. 47,500.00 4,987.50 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00 0.0053 org Mandor @ Rp. 40,000.00 210.00

JUMLAH ( BELUM PPN ) 90,247.50 750,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang jendela besi tahan api

1.0000 Jendela besi tahan api @ Rp. 1,500,000.00 1,500,000.00 6.4 1.2000 org Tukang besi konstruksi @ Rp. 45,000.00 54,000.00

0.1200 org Kepala tukang besi @ Rp. 47,500.00 5,700.00 1.0220 org Pekerja @ Rp. 36,000.00 36,792.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 96,732.00 1,500,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu gulung besi

1.0000 Pintu gulung besi @ Rp. 250,000.00 250,000.00 6.5 1.2000 org Tukang besi konstruksi @ Rp. 45,000.00 54,000.00

0.1200 org Kepala tukang besi @ Rp. 47,500.00 5,700.00 1.2000 org Pekerja @ Rp. 36,000.00 43,200.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 103,140.00 250,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu lipat

1.0000 Pintu lipat @ Rp. 500,000.00 500,000.00 6.6 1.0500 org Tukang besi konstruksi @ Rp. 45,000.00 47,250.00

0.1050 org Kepala tukang besi @ Rp. 47,500.00 4,987.50 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00 0.0052 org Mandor @ Rp. 40,000.00 208.00

JUMLAH ( BELUM PPN ) 90,245.50 500,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu Sunscreen alumunium

1.0000 Sunscreen alumunium @ Rp. 250,000.00 250,000.00 6.7 0.8000 org Tukang besi konstruksi @ Rp. 45,000.00 36,000.00

0.0800 org Kepala tukang besi @ Rp. 47,500.00 3,800.00 0.0800 org Pekerja @ Rp. 36,000.00 2,880.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 42,840.00 250,000.00 JASA 10 %JUMLAH

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 132: AHS 2008-Kota.xlsx

Analisa Gedung - 132

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) DIBULATKAN

Page 133: AHS 2008-Kota.xlsx

Analisa Gedung - 133

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang Rolling door

1.0000 Roll door @ Rp. 200,000.00 200,000.00 6.8 1.5000 org Tukang besi konstruksi @ Rp. 45,000.00 67,500.00

0.1050 org Kepala tukang besi @ Rp. 47,500.00 4,987.50 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00 0.0052 org Mandor @ Rp. 40,000.00 208.00

JUMLAH ( BELUM PPN ) 110,495.50 200,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu alumunium

1.0000 Pintu alumunium @ Rp. 400,000.00 400,000.00 6.9 1.0500 org Tukang besi konstruksi @ Rp. 45,000.00 47,250.00

0.1050 org Kepala tukang besi @ Rp. 47,500.00 4,987.50 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00 0.0052 org Mandor @ Rp. 40,000.00 208.00

JUMLAH ( BELUM PPN ) 90,245.50 400,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang Vertikal blinds

1.0000 Vertikal blinds @ Rp. 250,000.00 250,000.00 6.11 0.3500 org Tukang kayu @ Rp. 45,000.00 15,750.00

0.0350 org Kepala tukang kayu @ Rp. 47,500.00 1,662.50 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0018 org Mandor @ Rp. 40,000.00 70.00

JUMLAH ( BELUM PPN ) 30,082.50 250,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang teralis besi

11.5000 Baja strip 2 x 3 @ Rp. 8,800.00 101,200.00 6.12 1.2000 org Tukang las @ Rp. 45,000.00 54,000.00

0.0120 org Kepala tukang las @ Rp. 47,500.00 570.00 1.2000 org Pekerja @ Rp. 36,000.00 43,200.00 0.0006 org Mandor @ Rp. 40,000.00 24.00

JUMLAH ( BELUM PPN ) 97,794.00 101,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kawat harmonika

1.1000 Kawat harmonika @ Rp. 25,000.00 27,500.00 6.13 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 10,000.00 200.00

0.0018 Kayu kamper papan @ Rp. 5,500,000.00 9,900.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0005 org Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 8,870.00 37,600.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

m2

m2

m1

m2

m2

m3

Page 134: AHS 2008-Kota.xlsx

Analisa Gedung - 134

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

SNI 1.0000 Pasang kawat nyamuk

1.1000 Kawat nyamuk @ Rp. 8,250.00 9,075.00 6.14 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 10,000.00 200.00

0.0018 Kayu kamper papan @ Rp. 5,500,000.00 9,900.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0005 org Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 8,870.00 19,175.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kawat kassa

1.1000 Kawat kassa @ Rp. 10,000.00 11,000.00 6.15 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 10,000.00 200.00

0.0018 Kayu kamper papan @ Rp. 5,500,000.00 9,900.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0005 org Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 8,870.00 21,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kawat burung

1.1000 Kawat burung @ Rp. 15,000.00 16,500.00 6.16 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 10,000.00 200.00

0.0018 Kayu kamper papan @ Rp. 5,500,000.00 9,900.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0005 org Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 8,870.00 26,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang jendela nako & tralis

1.1000 Jendela nako @ Rp. 20,000.00 22,000.00 6.17 0.0200 kg Paku skrup @ Rp. 10,000.00 200.00

0.0250 Besi strip @ Rp. 7,500.00 187.50 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 17,740.00 22,387.50 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN KUNCI DAN KACA

6.1 1.0000 bh Pasang kunci tanam antik 1.0000 bh Kunci tanam antik @ Rp. 250,000.00 250,000.00 0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala tukang kayu @ Rp. 50,000.00 3,000.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 33,780.00 250,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m2

Page 135: AHS 2008-Kota.xlsx

Analisa Gedung - 135

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.2 1.0000 bh Pasang kunci tanam biasa 1.0000 bh Kunci tanam biasa @ Rp. 125,000.00 125,000.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 24,810.00 125,000.00 JASA 10 %JUMLAHDIBULATKAN

6.3 1.0000 bh Pasang kunci tanam kamar mandi 1.0000 bh Kunci tanam kamar mandi @ Rp. 50,000.00 50,000.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 24,280.00 50,000.00 JASA 10 %JUMLAHDIBULATKAN

6.4 1.0000 bh Pasang kunci tanam silinder 1.0000 bh Kunci silinder @ Rp. 75,000.00 75,000.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0003 org Mandor @ Rp. 40,000.00 10.00

JUMLAH ( BELUM PPN ) 24,190.00 75,000.00 JASA 10 %JUMLAHDIBULATKAN

6.5 1.0000 bh Pasang engsel pintu 1.0000 bh Engsel pintu @ Rp. 11,000.00 11,000.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 11,000.00 JASA 10 %JUMLAHDIBULATKAN

6.6 1.0000 bh Pasang engsel jendela kupu-kupu 1.0000 bh Engsel jendela @ Rp. 7,500.00 7,500.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 5,810.00 7,500.00 JASA 10 %JUMLAHDIBULATKAN

6.7 1.0000 bh Pasang engsel angin 1.0000 bh Engsel angin @ Rp. 3,000.00 3,000.00 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 11,620.00 3,000.00 JASA 10 %JUMLAHDIBULATKAN

Page 136: AHS 2008-Kota.xlsx

Analisa Gedung - 136

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.8 1.0000 bh Pasang spring knip 1.0000 bh Spring knip @ Rp. 7,500.00 7,500.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 7,500.00 JASA 10 %JUMLAHDIBULATKAN

6.9 1.0000 bh Pasang kait angin 1.0000 bh Kait angin @ Rp. 3,000.00 3,000.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 3,000.00 JASA 10 %JUMLAHDIBULATKAN

6.10 1.0000 bh Pasang door closer 1.0000 bh Door closer @ Rp. 150,000.00 150,000.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala tukang kayu @ Rp. 50,000.00 2,500.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 28,150.00 150,000.00 JASA 10 %JUMLAHDIBULATKAN

6.11 1.0000 bh Pasang kunci selot 1.0000 bh Kunci selot @ Rp. 50,000.00 50,000.00 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 11,260.00 50,000.00 JASA 10 %JUMLAHDIBULATKAN

6.12 1.0000 bh Pasang pegangan pintu / door holder 1.0000 bh Door holder @ Rp. 15,000.00 15,000.00 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala tukang kayu @ Rp. 50,000.00 2,500.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 28,150.00 15,000.00 JASA 10 %JUMLAHDIBULATKAN

6.13 1.0000 bh Pasang door stop 1.0000 bh Door stop @ Rp. 15,000.00 15,000.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0005 org Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 5,630.00 15,000.00 JASA 10 %JUMLAHDIBULATKAN

Page 137: AHS 2008-Kota.xlsx

Analisa Gedung - 137

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.14 1.0000 bh Pasang rel pintu dorong 1.0000 bh Rel pintu dorong @ Rp. 200,000.00 200,000.00 0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala tukang kayu @ Rp. 50,000.00 3,000.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 33,780.00 200,000.00 JASA 10 %JUMLAHDIBULATKAN

6.15 1.0000 bh Pasang kunci lemari 1.0000 bh Kunci lemari @ Rp. 12,000.00 12,000.00 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0250 org Pekerja @ Rp. 36,000.00 900.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 14,075.00 12,000.00 JASA 10 %JUMLAHDIBULATKAN

6.16 1.0000 Pasang kaca, tebal 3 mm

1.1000 Kaca polos @ Rp. 49,500.00 54,450.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 54,450.00 JASA 10 %JUMLAHDIBULATKAN

6.17 1.0000 Pasang kaca, tebal 5 mm

1.1000 Kaca polos @ Rp. 60,500.00 66,550.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 66,550.00 JASA 10 %JUMLAHDIBULATKAN

6.20 1.0000 Pasang kaca cermin, tebal 5 mm

1.1000 Kaca cermin @ Rp. 120,000.00 132,000.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 132,000.00 JASA 10 %JUMLAHDIBULATKAN

6.24 1.0000 Pasang kaca patri, tebal 5 mm

1.1000 Kaca patri @ Rp. 300,000.00 330,000.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 330,000.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

m2

m2

m2

m2

Page 138: AHS 2008-Kota.xlsx

Analisa Gedung - 138

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

6.17 1.0000 Pasang kusen alumunium

1.1000 Kusen alumunium @ Rp. 55,000.00 60,500.00 15% x Harga kusen (Perlengkapan) @ Rp. 55,000.00 8,250.00

0.1500 oh Tukang alumunium @ Rp. 45,000.00 6,750.00 0.0150 oh Kepala tukang @ Rp. 47,500.00 712.50 0.0150 oh Pekerja @ Rp. 36,000.00 540.00 0.0008 oh Mandor @ Rp. 40,000.00 30.00

JUMLAH 8,032.50 68,750.00 DIBULATKAN

Empiris 1.0000 Mengerjakan Ukiran Gaya Yogyakarta dengan kedalaman 1 cm, tidak berlubangMembuat pola ukir dan memindahkan pola

1.0000 lb Kertas 100 x 100 cm @ Rp. 5,000.00 5,000.00 15.0000 lbr Kerta karbon @ Rp. 5,000.00 75,000.00 2.0000 org Tukang gambar @ Rp. 50,000.00 100,000.00

JUMLAH ( A ) 100,000.00 80,000.00

Mengukir 16.0000 org Tukang Ukir @ Rp. 55,000.00 880,000.00 1.0000 org Kepala Tk, Ukir @ Rp. 55,000.00 55,000.00

JUMLAH ( B ) 935,000.00 -

Menggosok dan menghaluskan 20.0000 lbr Amplas @ Rp. 3,500.00 70,000.00 0.0800 kg Dempul @ Rp. 10,000.00 800.00 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

JUMLAH ( C ) 142,500.00 70,800.00

JUMLAH A + B + C ( BELUM PPN ) 1,177,500.00 150,800.00 JASA 10 %JUMLAHDIBULATKAN

Empiris 1.0000 Mengerjakan Cat SunggingMengerjakan cat dasar

0.1200 kg Cat menie kayu @ Rp. 15,000.00 1,800.00 0.0400 org Tukang cat @ Rp. 42,500.00 1,700.00 0.0040 org Kep. Tk. Cat @ Rp. 45,000.00 180.00 0.0667 org Pekerja @ Rp. 36,000.00 2,401.20 0.0033 org Mandor @ Rp. 40,000.00 132.00

JUMLAH ( A ) 4,413.20 1,800.00

Mengecat dan membuat gradasi tutulan berkali-kali 0.4250 kg Cat kayu @ Rp. 29,500.00 12,537.50 0.1000 ltr Minyak cat @ Rp. 14,000.00 1,400.00 5.0000 org Tukang cat sungging @ Rp. 50,000.00 250,000.00 0.5000 org Kep. Tk. Cat sungging @ Rp. 55,000.00 27,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( B ) 285,100.00 13,937.50 JUMLAH A + B ( BELUM PPN ) 289,513.20 15,737.50 JASA 10 %JUMLAHDIBULATKAN

Empiris 1.0000 Memasang Prodo Mas 24 karat

1.2000 Prodo @ Rp. 4,000,000.00 4,800,000.00 0.1200 kg Cat kayu @ Rp. 29,500.00 3,540.00 0.1000 org Tukang cat @ Rp. 42,500.00 4,250.00 8.0000 org Tukang Prodo @ Rp. 50,000.00 400,000.00 1.0000 org Kepala tukang @ Rp. 55,000.00 55,000.00

JUMLAH 459,250.00 4,803,540.00 JASA 10 %JUMLAHDIBULATKAN

m1

m1

m2

m2

m2

m2

Page 139: AHS 2008-Kota.xlsx

Analisa Gedung - 139

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

Empiris 1.00 ttk Mengerjakan Sondir Tanah 0.50 hr Sewa alat @ Rp. 100,000.00 50,000.00 1.00 org Operator @ Rp. 90,000.00 90,000.00 0.50 org Analis @ Rp. 150,000.00 75,000.00 2.00 org Pekerja @ Rp. 36,000.00 72,000.00 0.10 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 241,000.00 50,000.00 JASA 10 %JUMLAHDIBULATKAN

Empiris 10.00 Mengerjakan Test Laboratorium Sampel Beton 20.00 bh Benda uji silinder beton @ Rp. 3,000.00 60,000.00 20.00 bh Biaya tes @ Rp. 5,000.00 100,000.00 20.00 bh Biaya analisis @ Rp. 15,000.00 300,000.00

JUMLAH ( BELUM PPN ) - 460,000.00 JASA 10 %JUMLAHDIBULATKAN

Empiris 100.0000 Pelumpuran ringan 4.0000 btg Bambu @ Rp. 7,000.00 28,000.00 35.0000 bh Bagor @ Rp. 600.00 21,000.00 2.0000 bh Irus @ Rp. 10,000.00 20,000.00 1.0000 bh Cetok @ Rp. 10,000.00 10,000.00 1.5000 bh Ember @ Rp. 5,000.00 7,500.00 0.1000 bh Linggis @ Rp. 35,000.00 3,500.00 1.0000 bh Martil @ Rp. 10,000.00 10,000.00 7.0000 org Pekerja @ Rp. 36,000.00 252,000.00 0.7500 org Mandor @ Rp. 40,000.00 30,000.00

JUMLAH ( BELUM PPN ) 282,000.00 100,000.00 JASA 10 %JUMLAHDIBULATKAN ( A )

( A ) / 100.00 420,200.00 / 100.00

Empiris 100.0000 Pelumpuran berat 8.0000 btg Bambu @ Rp. 7,000.00 56,000.00 60.0000 bh Bagor @ Rp. 600.00 36,000.00 0.1000 bh Pacul @ Rp. 30,000.00 3,000.00 1.0000 bh Cetok @ Rp. 10,000.00 10,000.00 0.1000 bh Linggis @ Rp. 35,000.00 3,500.00 2.0000 bh Irus @ Rp. 10,000.00 20,000.00 3.0000 bh Ember @ Rp. 5,000.00 15,000.00 1.0000 bh Betel @ Rp. 12,000.00 12,000.00 1.0000 bh Martil @ Rp. 10,000.00 10,000.00 12.0000 kg PC @ Rp. 764.00 9,168.00

0.1500 Pasir pasang @ Rp. 76,000.00 11,400.00

2.0000 Buis Beton 20/30 @ Rp. 50,000.00 100,000.00 18.0000 org Pekerja @ Rp. 36,000.00 648,000.00 1.7500 org Mandor @ Rp. 40,000.00 70,000.00

JUMLAH ( BELUM PPN ) 718,000.00 286,068.00 JASA 10 %JUMLAHDIBULATKAN ( A )

( A ) / 100.00 1,104,474.00 / 100.00

m3

m2

BIAYA TIAP 1M2

m2

m3

m1

BIAYA TIAP 1M2

Page 140: AHS 2008-Kota.xlsx

Analisa Gedung - 140

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

Empiris 1.00 Membuang lumpur SAL sejauh 15 km 0.50 org Pekerja @ Rp. 36,000.00 18,000.00 0.02 org Mandor @ Rp. 40,000.00 800.00 0.41 hr Sewa kendaraan @ Rp. 118,000.00 47,908.00

JUMLAH ( BELUM PPN ) 66,708.00 - JASA 10 %JUMLAHDIBULATKAN

Empiris 1.00 Mengangkut lumpur SAL sejauh 30 m 0.40 org Pekerja @ Rp. 36,000.00 14,400.00 0.02 org Mandor @ Rp. 40,000.00 600.00 0.50 hr Sewa gerobag @ Rp. 1,500.00 750.00

JUMLAH ( BELUM PPN ) 15,750.00 - JASA 10 %JUMLAHDIBULATKAN

Empiris 10,000.00 Penyapuan Jalan Dan Trotoar 447.00 bh Sapu lidi @ Rp. 3,000.00 1,341,000.00 14.00 bh Tangkai Sapu @ Rp. 5,000.00 70,000.00 14.00 bh Tomblok @ Rp. 3,500.00 49,000.00 4.00 bh Hareg @ Rp. 3,000.00 12,000.00 8.0000 bh Serok @ Rp. 5,000.00 40,000.00 8.00 bh Kerug @ Rp. 5,000.00 40,000.00 16.00 bh Seragam @ Rp. 75,000.00 1,200,000.00 14.00 bh Sarung tangan @ Rp. 7,500.00 105,000.00 14.00 bh Masker @ Rp. 7,500.00 105,000.00 4.00 bh Gerobak @ Rp. 1,500,000.00 6,000,000.00 2,555.00 org Pekerja @ Rp. 36,000.00 91,980,000.00 365.00 org Mandor @ Rp. 40,000.00 14,600,000.00

JUMLAH ( BELUM PPN ) 106,580,000.00 8,962,000.00 JASA 10 %JUMLAHDIBULATKAN ( Dalam 1 tahun ) ( A )

( A ) / (10000 x 365) 127,096,200.00 / 3,650,000.00

Empiris 1,000.00 Pembersihan / Penyapuan halaman 0.1506 bh Sapu lidi @ Rp. 3,000.00 451.80 0.0109 bh Serok @ Rp. 5,000.00 54.50 0.0082 bh Seragam @ Rp. 75,000.00 615.00 0.0009 bh Gerobak @ Rp. 1,500,000.00 1,350.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1428 org Mandor @ Rp. 40,000.00 5,712.00

JUMLAH ( BELUM PPN ) 41,712.00 2,471.30 JASA 10 %JUMLAHDIBULATKAN ( A )

( A ) / ( 1000 ) 48,601.00 / 1,000.00

Empiris 1,000.00 Pemangkasan teh-tehan 0.0280 bh Gunting pangkas @ Rp. 35,000.00 980.00 0.0030 bh Gerobak @ Rp. 1,500,000.00 4,500.00 5.0000 org Pekerja @ Rp. 36,000.00 180,000.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00

JUMLAH ( BELUM PPN ) 200,000.00 5,480.00 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan ) ( A )

( A ) / (1000 x 30)

m3

m3

m2

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

Page 141: AHS 2008-Kota.xlsx

Analisa Gedung - 141

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4) 452,056.00 / 30,000.00

Page 142: AHS 2008-Kota.xlsx

Analisa Gedung - 142

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

Empiris 1,000.00 Pangkas bentuk tanaman perdu 0.0890 bh Gunting pangkas @ Rp. 35,000.00 3,115.00 0.0060 bh Gerobak @ Rp. 1,500,000.00 9,000.00 8.0000 org Pekerja @ Rp. 36,000.00 288,000.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 328,000.00 12,115.00 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan ) ( A )

( A ) / (1000 x 30) 748,252.00 / 30,000.00

Empiris 1,000.00 Pangkas rumput 0.0010 bh Mesin potong rumput @ Rp. 3,000,000.00 3,000.00 1.0000 bh Sapu lidi @ Rp. 3,000.00 3,000.00 0.0230 bh Tomblok @ Rp. 3,500.00 80.50 0.0030 bh Gerobak @ Rp. 1,500,000.00 4,500.00 6.0000 ltr BBM @ Rp. 4,500.00 27,000.00 1.0000 org Tenaga ahli @ Rp. 40,000.00 40,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00

JUMLAH ( BELUM PPN ) 96,000.00 37,580.50 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan ) ( A )

( A ) / (1000 x 30) 293,876.00 / 30,000.00

Empiris 1,000.00 Penyiangan tanaman semak dan penggemburan tanah 0.0230 bh Gathul @ Rp. 10,000.00 230.00 0.0230 bh Garpu tanah @ Rp. 15,000.00 345.00 0.0230 bh Arit @ Rp. 20,000.00 460.00 0.0050 bh Gerobak celeng @ Rp. 400,000.00 2,000.00 0.0230 bh Tomblok @ Rp. 3,500.00 80.50 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 184,000.00 3,115.50 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan ) ( A )

( A ) / (1000 x 30) 411,654.00 / 30,000.00

1.0000 Pekerjaan Grouting / Injeksi retakan beton dengan epoxy resin 5.000 bh Nipel @ Rp. 10,000.00 50,000.00 0.050 kg Nitobond EC @ Rp. 100,000.00 5,000.00 0.016 kg Conbextra EP @ Rp. 200,000.00 3,200.00 0.225 hr Sewa Compressor @ Rp. 250,000.00 56,250.00 0.150 hr Sewa Mesin Grouting @ Rp. 150,000.00 22,500.00 0.075 hr Sewa mesin gerinda @ Rp. 100,000.00 7,500.00 1.000 hr Sewa mixer @ Rp. 6,000.00 6,000.00 1.000 ls Alat bantu @ Rp. 5,000.00 5,000.00 0.3125 org Tukang grouting @ Rp. 45,000.00 14,062.50 0.0312 org Kepala Tukang grouting @ Rp. 50,000.00 1,560.00 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00 0.1562 org Mandor @ Rp. 40,000.00 6,248.00

JUMLAH ( BELUM PPN ) 66,870.50 155,450.00 JASA 10 %JUMLAHDIBULATKAN

m2

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

m1

Page 143: AHS 2008-Kota.xlsx

Analisa Gedung - 143

No. Macam Pekerjaan Upah Bahan

(1) (2) (3) (4)

1.0000 Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex 100) 3.000 bh Pipa @ Rp. 1,500.00 4,500.00 0.050 kg Nitobond EC @ Rp. 100,000.00 5,000.00 0.016 kg Cebex 100 @ Rp. 150,000.00 2,400.00 0.150 hr Sewa Mesin Grouting @ Rp. 150,000.00 22,500.00 0.075 hr Sewa mesin gerinda @ Rp. 100,000.00 7,500.00 1.000 ls Alat bantu @ Rp. 5,000.00 5,000.00 0.3125 org Tukang grouting @ Rp. 45,000.00 14,062.50 0.0312 org Kepala Tukang grouting @ Rp. 50,000.00 1,560.00 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00 0.1562 org Mandor @ Rp. 40,000.00 6,248.00

JUMLAH ( BELUM PPN ) 66,870.50 46,900.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Cor beton kerb ( 15 x 30 ) cm, dengan 1pc:2ps:3kr 15.3000 kg PC @ Rp. 764.00 11,689.20

0.0243 Pasir pasang @ Rp. 76,000.00 1,846.80

0.0369 Kerikil beton @ Rp. 78,650.00 2,902.19

0.0027 Papan cetakan @ Rp. 1,000,000.00 2,700.00 0.0272 kg Paku @ Rp. 8,000.00 217.60 0.0340 org Tukang kayu @ Rp. 47,500.00 1,615.00 0.0158 org Tukang batu @ Rp. 42,500.00 671.50 0.0050 org Kepala tukang @ Rp. 45,000.00 225.00 0.1374 org Pekerja @ Rp. 36,000.00 4,946.40 0.0063 org Mandor @ Rp. 40,000.00 252.00

JUMLAH ( BELUM PPN ) 7,709.90 19,355.79 JASA 10 %JUMLAHDIBULATKAN

1.0000 Cor beton Devider ( 30 x 30 ) cm, dengan 1pc:2ps:3kr 30.6000 kg PC @ Rp. 764.00 23,378.40

0.0486 Pasir pasang @ Rp. 76,000.00 3,693.60

0.0738 Kerikil beton @ Rp. 78,650.00 5,804.37

0.0027 Papan cetakan @ Rp. 1,000,000.00 2,700.00 0.0272 kg Paku @ Rp. 8,000.00 217.60 0.0340 org Tukang kayu @ Rp. 47,500.00 1,615.00 0.0315 org Tukang batu @ Rp. 42,500.00 1,338.75 0.0066 org Kepala tukang @ Rp. 45,000.00 297.00 0.2499 org Pekerja @ Rp. 36,000.00 8,996.40 0.0116 org Mandor @ Rp. 40,000.00 464.00

JUMLAH ( BELUM PPN ) 12,711.15 35,793.97 JASA 10 %JUMLAHDIBULATKAN

1.0000 M2 PASANG STOOT WERK (SCAFOLDING)

m1

m1

m3

m3

m3

m1

m3

m3

m3

Page 144: AHS 2008-Kota.xlsx

Analisa Gedung - 144

ANALISA SATUAN PEKERJAAN Jumlah

(5)

658,000.00 65,800.00 723,800.00 723,800.00

7,238.00

61,460.00 6,146.00 67,606.00 67,606.00

5,600.00 560.00 6,160.00 6,160.00

406,035.28 40,603.53 446,638.80 446,638.00

68,159.50 6,815.95 74,975.45

Page 145: AHS 2008-Kota.xlsx

Analisa Gedung - 145

Jumlah

(5) 74,975.00

Page 146: AHS 2008-Kota.xlsx

Analisa Gedung - 146

Jumlah

(5)

880,407.50 88,040.75 968,448.25 968,448.00

146,412.85 14,641.29 161,054.14 161,054.00

272,680.85 27,268.09 299,948.94 299,948.00

Page 147: AHS 2008-Kota.xlsx

Analisa Gedung - 147

Jumlah

(5)

811,794.50 81,179.45 892,973.95 892,973.00

969,100.00 96,910.00 1,066,010.00 1,066,010.00

926,462.00 92,646.20 1,019,108.20 1,019,108.00

129,175.00 12,917.50 142,092.50 142,092.00

Page 148: AHS 2008-Kota.xlsx

Analisa Gedung - 148

Jumlah

(5)

22,177.50 2,217.75 24,395.25 24,395.00

18,862.00 1,886.20 20,748.20 20,748.00

687,642.50 68,764.25 756,406.75 756,406.00

16,000.00 1,600.00 17,600.00 17,600.00

21,040.00 2,104.00 23,144.00 23,144.00

29,400.00 2,940.00 32,340.00 32,340.00

Page 149: AHS 2008-Kota.xlsx

Analisa Gedung - 149

Jumlah

(5)

24,980.00 2,498.00 27,478.00 27,478.00

50,000.00 5,000.00 55,000.00 55,000.00

32,948.00 3,294.80 36,242.80 36,242.00

164,400.00 16,440.00 180,840.00 180,840.00

12,280.00 1,228.00 13,508.00 13,508.00

20,576.00 2,057.60 22,633.60 22,633.00

9,400.00 940.00 10,340.00 10,340.00

7,672.00 767.20 8,439.20 8,439.00

Page 150: AHS 2008-Kota.xlsx

Analisa Gedung - 150

Jumlah

(5)

9,400.00 940.00 10,340.00 10,340.00

77,200.00 7,720.00 84,920.00 84,920.00

53,200.00 5,320.00 58,520.00 58,520.00

89,200.00 8,920.00 98,120.00 98,120.00

96,000.00 9,600.00 105,600.00 105,600.00

25,400.00 2,540.00 27,940.00 27,940.00

Page 151: AHS 2008-Kota.xlsx

Analisa Gedung - 151

Jumlah

(5)

160,470.00 16,047.00 176,517.00 176,517.00

249,466.50 24,946.65 274,413.15 274,413.00

224,965.00 22,496.50 247,461.50 247,461.00

299,735.38 29,973.54 329,708.92 329,708.00

Page 152: AHS 2008-Kota.xlsx

Analisa Gedung - 152

Jumlah

(5)

267,853.50 26,785.35 294,638.85 294,638.00

337,252.00 33,725.20 370,977.20 370,977.00

364,388.00 36,438.80 400,826.80 400,826.00

496,552.00 49,655.20 546,207.20 546,207.00

409,640.00 40,964.00 450,604.00

Page 153: AHS 2008-Kota.xlsx

Analisa Gedung - 153

Jumlah

(5) 450,604.00

Page 154: AHS 2008-Kota.xlsx

Analisa Gedung - 154

Jumlah

(5)

318,448.00 31,844.80 350,292.80 350,292.00

45,433.00 4,543.30 49,976.30 49,976.00

49,645.50 4,964.55 54,610.05 54,610.00

53,374.00 5,337.40 58,711.40 58,711.00

55,338.68 5,533.87 60,872.55

Page 155: AHS 2008-Kota.xlsx

Analisa Gedung - 155

Jumlah

(5) 60,872.00

Page 156: AHS 2008-Kota.xlsx

Analisa Gedung - 156

Jumlah

(5)

58,685.80 5,868.58 64,554.38 64,554.00

99,724.87 9,972.49 109,697.36 109,697.00

110,655.80 11,065.58 121,721.38 121,721.00

115,089.80 11,508.98 126,598.78 126,598.00

122,314.00 12,231.40 134,545.40 134,545.00

Page 157: AHS 2008-Kota.xlsx

Analisa Gedung - 157

Jumlah

(5)

55,040.00 5,504.00 60,544.00 60,544.00

68,290.00 6,829.00 75,119.00 75,119.00

350,905.00 35,090.50 385,995.50 385,995.00

347,287.50 34,728.75 382,016.25 382,016.00

15,934.29 1,593.43 17,527.71 17,527.00

Page 158: AHS 2008-Kota.xlsx

Analisa Gedung - 158

Jumlah

(5)

459,317.50 45,931.75 505,249.25 505,249.00

Page 159: AHS 2008-Kota.xlsx

Analisa Gedung - 159

Jumlah

(5)

532,010.00 53,201.00 585,211.00 585,211.00

670,004.50 67,000.45 737,004.95 737,004.00

674,293.00 67,429.30 741,722.30 741,722.00

695,456.50 69,545.65 765,002.15 765,002.00

9,048.25 904.83 9,953.08 9,953.00

Page 160: AHS 2008-Kota.xlsx

Analisa Gedung - 160

Jumlah

(5)

9,153.25 915.33 10,068.58 10,068.00

66,120.00 6,612.00 72,732.00 72,732.00

71,120.00 7,112.00 78,232.00 78,232.00

133,080.00 13,308.00 146,388.00 146,388.00

15,702.50 1,570.25 17,272.75 1,727.28 1,727.00

Page 161: AHS 2008-Kota.xlsx

Analisa Gedung - 161

Jumlah

(5) 107,800.00 10,780.00 118,580.00 118,580.00

115,030.00 11,503.00 126,533.00 126,533.00

144,000.00 14,400.00 158,400.00 158,400.00

1,384,250.00 138,425.00 1,522,675.00 1,522,675.00

907,750.00 90,775.00 998,525.00 998,525.00

Page 162: AHS 2008-Kota.xlsx

Analisa Gedung - 162

Jumlah

(5)

2,725,503.00 2,725,503.00

2,974,329.88 2,974,329.00

3,223,156.75 3,223,156.00

3,471,983.63 3,471,983.00

3,720,810.50 3,720,810.00

4,248,178.00 4,248,178.00

Page 163: AHS 2008-Kota.xlsx

Analisa Gedung - 163

Jumlah

(5)

4,497,004.88 4,497,004.00

4,745,831.75 4,745,831.00

4,994,658.63 4,994,658.00

5,243,485.50 5,243,485.00

3,724,028.00 3,724,028.00

3,972,854.88 3,972,854.00

Page 164: AHS 2008-Kota.xlsx

Analisa Gedung - 164

Jumlah

(5)

4,221,681.75 4,221,681.00

4,470,508.63 4,470,508.00

4,719,335.50 4,719,335.00

654,649.00 65,464.90 720,113.90 720,113.00

Page 165: AHS 2008-Kota.xlsx

Analisa Gedung - 165

Jumlah

(5)

518,096.00 51,809.60 569,905.60 569,905.00

29,631.50 2,963.15 32,594.65 32,594.00

32,308.64 3,230.86 35,539.50 35,539.00

31,162.80 3,116.28 34,279.08 34,279.00

Page 166: AHS 2008-Kota.xlsx

Analisa Gedung - 166

Jumlah

(5)

16,857.50 1,685.75 18,543.25 18,543.00

17,554.76 1,755.48 19,310.24 19,310.00

22,451.28 2,245.13 24,696.41 24,696.00

21,044.72 2,104.47 23,149.19 23,149.00

20,142.80 2,014.28 22,157.08 22,157.00

Page 167: AHS 2008-Kota.xlsx

Analisa Gedung - 167

Jumlah

(5)

26,277.48 2,627.75 28,905.23 28,905.00

5,991.00 599.10 6,590.10 6,590.00

5,170.40 517.04 5,687.44 5,687.00

13,526.48 1,352.65 14,879.13 14,879.00

18,480.48 1,848.05 20,328.53 20,328.00

Page 168: AHS 2008-Kota.xlsx

Analisa Gedung - 168

Jumlah

(5)

6,885.00 688.50 7,573.50 7,573.00

32,915.68 3,291.57 36,207.25 36,207.00

115,687.00 11,568.70 127,255.70 127,255.00

77,942.00 7,794.20 85,736.20 85,736.00

63,106.00 6,310.60 69,416.60 69,416.00

Page 169: AHS 2008-Kota.xlsx

Analisa Gedung - 169

Jumlah

(5)

67,654.50 6,765.45 74,419.95 74,419.00

55,106.00 5,510.60 60,616.60 60,616.00

66,342.00 6,634.20 72,976.20 72,976.00

6,964.84 696.48 7,661.32 7,661.00

Page 170: AHS 2008-Kota.xlsx

Analisa Gedung - 170

Jumlah

(5)

7,757.34 775.73 8,533.07 8,533.00

8,094.80 809.48 8,904.28 8,904.00

8,541.05 854.11 9,395.15 9,395.00

79,072.02 7,907.20 86,979.22 86,979.00

Page 171: AHS 2008-Kota.xlsx

Analisa Gedung - 171

Jumlah

(5)

80,088.62 8,008.86 88,097.48 88,097.00

67,588.62 6,758.86 74,347.48 74,347.00

69,588.62 6,958.86 76,547.48 76,547.00

70,088.62 7,008.86 77,097.48 77,097.00

14,634.80 1,463.48 16,098.28

Page 172: AHS 2008-Kota.xlsx

Analisa Gedung - 172

Jumlah

(5) 16,098.00

Page 173: AHS 2008-Kota.xlsx

Analisa Gedung - 173

Jumlah

(5)

11,643.80 1,164.38 12,808.18 12,808.00

40,718.86 4,071.89 44,790.75 44,790.00

32,058.86 3,205.89 35,264.75 35,264.00

95,651.95 9,565.20 105,217.14 105,217.00

Page 174: AHS 2008-Kota.xlsx

Analisa Gedung - 174

Jumlah

(5)

93,500.00 9,350.00 102,850.00 102,850.00

88,500.00 8,850.00 97,350.00 97,350.00

78,500.00 7,850.00 86,350.00 86,350.00

83,500.00 8,350.00 91,850.00 91,850.00

78,500.00 7,850.00 86,350.00 86,350.00

Page 175: AHS 2008-Kota.xlsx

Analisa Gedung - 175

Jumlah

(5)

83,500.00 8,350.00 91,850.00 91,850.00

113,500.00 11,350.00 124,850.00 124,850.00

103,500.00 10,350.00 113,850.00 113,850.00

83,500.00 8,350.00 91,850.00 91,850.00

93,500.00 9,350.00 102,850.00 102,850.00

Page 176: AHS 2008-Kota.xlsx

Analisa Gedung - 176

Jumlah

(5)

83,500.00 8,350.00 91,850.00 91,850.00

93,500.00 9,350.00 102,850.00 102,850.00

83,500.00 8,350.00 91,850.00 91,850.00

83,500.00 8,350.00 91,850.00 91,850.00

1,135,550.00

378,516.67 37,851.67 416,368.33 416,368.00

Page 177: AHS 2008-Kota.xlsx

Analisa Gedung - 177

Jumlah

(5)

59,875.00 5,987.50 65,862.50 65,862.00

9,500.00 950.00 10,450.00 10,450.00

6,300.00 630.00 6,930.00 6,930.00

3,500.00 350.00 3,850.00 3,850.00

22,900,900.00 2,290,090.00 25,190,990.00 25,190,990.00

11,900,900.00 1,190,090.00 13,090,990.00 13,090,990.00

Page 178: AHS 2008-Kota.xlsx

Analisa Gedung - 178

Jumlah

(5)

6,125,900.00 612,590.00 6,738,490.00 6,738,490.00

5,685,900.00 568,590.00 6,254,490.00 6,254,490.00

7,225,900.00 722,590.00 7,948,490.00 7,948,490.00

2,504,700.00 250,470.00 2,755,170.00 2,755,170.00

224,950.00 22,495.00 247,445.00 247,445.00

Page 179: AHS 2008-Kota.xlsx

Analisa Gedung - 179

Jumlah

(5)

194,950.00 19,495.00 214,445.00 214,445.00

179,200.00 17,920.00 197,120.00 197,120.00

178,000.00 17,800.00 195,800.00 195,800.00

182,200.00 18,220.00 200,420.00 200,420.00

Page 180: AHS 2008-Kota.xlsx

Analisa Gedung - 180

Jumlah

(5)

147,950.00 14,795.00 162,745.00 162,745.00

117,950.00 11,795.00 129,745.00 129,745.00

102,200.00 10,220.00 112,420.00 112,420.00

101,000.00 10,100.00 111,100.00 111,100.00

Page 181: AHS 2008-Kota.xlsx

Analisa Gedung - 181

Jumlah

(5)

105,200.00 10,520.00 115,720.00 115,720.00

107,525.00 10,752.50 118,277.50 118,277.00

77,525.00 7,752.50 85,277.50 85,277.00

61,775.00 6,177.50 67,952.50 67,952.00

Page 182: AHS 2008-Kota.xlsx

Analisa Gedung - 182

Jumlah

(5)

60,575.00 6,057.50 66,632.50 66,632.00

64,775.00 6,477.50 71,252.50 71,252.00

104,445.00 10,444.50 114,889.50 114,889.00

74,445.00 7,444.50 81,889.50 81,889.00

Page 183: AHS 2008-Kota.xlsx

Analisa Gedung - 183

Jumlah

(5)

58,695.00 5,869.50 64,564.50 64,564.00

57,495.00 5,749.50 63,244.50 63,244.00

61,695.00 6,169.50 67,864.50 67,864.00

115,225.00 11,522.50 126,747.50 126,747.00

Page 184: AHS 2008-Kota.xlsx

Analisa Gedung - 184

Jumlah

(5)

85,225.00 8,522.50 93,747.50 93,747.00

69,475.00 6,947.50 76,422.50 76,422.00

68,275.00 6,827.50 75,102.50 75,102.00

72,475.00 7,247.50 79,722.50 79,722.00

Page 185: AHS 2008-Kota.xlsx

Analisa Gedung - 185

Jumlah

(5)

84,810.00 8,481.00 93,291.00 93,291.00

54,810.00 5,481.00 60,291.00 60,291.00

39,060.00 3,906.00 42,966.00 42,966.00

37,860.00 3,786.00 41,646.00 41,646.00

Page 186: AHS 2008-Kota.xlsx

Analisa Gedung - 186

Jumlah

(5)

42,060.00 4,206.00 46,266.00 46,266.00

260,950.00 26,095.00 287,045.00 287,045.00

212,950.00 21,295.00 234,245.00 234,245.00

187,750.00 18,775.00 206,525.00 206,525.00

Page 187: AHS 2008-Kota.xlsx

Analisa Gedung - 187

Jumlah

(5)

185,830.00 18,583.00 204,413.00 204,413.00

192,550.00 19,255.00 211,805.00 211,805.00

183,950.00 18,395.00 202,345.00 202,345.00

135,950.00 13,595.00 149,545.00 149,545.00

Page 188: AHS 2008-Kota.xlsx

Analisa Gedung - 188

Jumlah

(5)

110,750.00 11,075.00 121,825.00 121,825.00

108,830.00 10,883.00 119,713.00 119,713.00

115,550.00 11,555.00 127,105.00 127,105.00

143,525.00 14,352.50 157,877.50 157,877.00

Page 189: AHS 2008-Kota.xlsx

Analisa Gedung - 189

Jumlah

(5)

95,525.00 9,552.50 105,077.50 105,077.00

70,325.00 7,032.50 77,357.50 77,357.00

68,405.00 6,840.50 75,245.50 75,245.00

75,125.00 7,512.50 82,637.50 82,637.00

Page 190: AHS 2008-Kota.xlsx

Analisa Gedung - 190

Jumlah

(5)

140,445.00 14,044.50 154,489.50 154,489.00

92,445.00 9,244.50 101,689.50 101,689.00

67,245.00 6,724.50 73,969.50 73,969.00

65,325.00 6,532.50 71,857.50 71,857.00

Page 191: AHS 2008-Kota.xlsx

Analisa Gedung - 191

Jumlah

(5)

72,045.00 7,204.50 79,249.50 79,249.00

151,225.00 15,122.50 166,347.50 166,347.00

103,225.00 10,322.50 113,547.50 113,547.00

78,025.00 7,802.50 85,827.50 85,827.00

Page 192: AHS 2008-Kota.xlsx

Analisa Gedung - 192

Jumlah

(5)

76,105.00 7,610.50 83,715.50 83,715.00

82,825.00 8,282.50 91,107.50 91,107.00

120,810.00 12,081.00 132,891.00 132,891.00

72,810.00 7,281.00 80,091.00 80,091.00

Page 193: AHS 2008-Kota.xlsx

Analisa Gedung - 193

Jumlah

(5)

47,610.00 4,761.00 52,371.00 52,371.00

45,690.00 4,569.00 50,259.00 50,259.00

52,410.00 5,241.00 57,651.00 57,651.00

23,278,000.00 2,327,800.00 25,605,800.00 25,605,800.00

12,278,000.00 1,227,800.00 13,505,800.00 13,505,800.00

Page 194: AHS 2008-Kota.xlsx

Analisa Gedung - 194

Jumlah

(5)

6,883,000.00 688,300.00 7,571,300.00 7,571,300.00

6,403,000.00 640,300.00 7,043,300.00 7,043,300.00

8,083,000.00 808,300.00 8,891,300.00 8,891,300.00

632,040.00 63,204.00 695,244.00 695,244.00

416,440.00 41,644.00 458,084.00 458,084.00

Page 195: AHS 2008-Kota.xlsx

Analisa Gedung - 195

Jumlah

(5)

308,640.00 30,864.00 339,504.00 339,504.00

293,940.00 29,394.00 323,334.00 323,334.00

318,440.00 31,844.00 350,284.00 350,284.00

905,400.00 90,540.00 995,940.00 995,940.00

520,400.00 52,040.00 572,440.00 572,440.00

Page 196: AHS 2008-Kota.xlsx

Analisa Gedung - 196

Jumlah

(5)

327,900.00 32,790.00 360,690.00 360,690.00

301,650.00 30,165.00 331,815.00 331,815.00

345,400.00 34,540.00 379,940.00 379,940.00

1,049,250.00 104,925.00 1,154,175.00 1,154,175.00

609,250.00 60,925.00 670,175.00 670,175.00

389,250.00 38,925.00 428,175.00 428,175.00

Page 197: AHS 2008-Kota.xlsx

Analisa Gedung - 197

Jumlah

(5)

359,250.00 35,925.00 395,175.00 395,175.00

409,250.00 40,925.00 450,175.00 450,175.00

1,613,500.00 161,350.00 1,774,850.00 1,774,850.00

909,500.00 90,950.00 1,000,450.00 1,000,450.00

547,500.00 54,750.00 602,250.00 602,250.00

499,500.00 49,950.00 549,450.00 549,450.00

Page 198: AHS 2008-Kota.xlsx

Analisa Gedung - 198

Jumlah

(5)

579,500.00 57,950.00 637,450.00 637,450.00

259,625.00 25,962.50 285,587.50 285,587.00

139,625.00 13,962.50 153,587.50 153,587.00

76,625.00 7,662.50 84,287.50 84,287.00

71,825.00 7,182.50 79,007.50 79,007.00

Page 199: AHS 2008-Kota.xlsx

Analisa Gedung - 199

Jumlah

(5)

88,625.00 8,862.50 97,487.50 97,487.00

281,595.00 28,159.50 309,754.50 309,754.00

151,595.00 15,159.50 166,754.50 166,754.00

83,345.00 8,334.50 91,679.50 91,679.00

78,145.00 7,814.50 85,959.50 85,959.00

Page 200: AHS 2008-Kota.xlsx

Analisa Gedung - 200

Jumlah

(5)

96,345.00 9,634.50 105,979.50 105,979.00

21,430.00 2,143.00 23,573.00 23,573.00

26,730.00 2,673.00 29,403.00 29,403.00

280,740.00 28,074.00 308,814.00 308,814.00

160,740.00 16,074.00 176,814.00 176,814.00

Page 201: AHS 2008-Kota.xlsx

Analisa Gedung - 201

Jumlah

(5)

97,740.00 9,774.00 107,514.00 107,514.00

92,940.00 9,294.00 102,234.00 102,234.00

109,740.00 10,974.00 120,714.00 120,714.00

286,155.00 28,615.50 314,770.50 314,770.00

Page 202: AHS 2008-Kota.xlsx

Analisa Gedung - 202

Jumlah

(5)

166,155.00 16,615.50 182,770.50 182,770.00

103,155.00 10,315.50 113,470.50 113,470.00

98,355.00 9,835.50 108,190.50 108,190.00

115,155.00 11,515.50 126,670.50 126,670.00

Page 203: AHS 2008-Kota.xlsx

Analisa Gedung - 203

Jumlah

(5)

308,600.00 30,860.00 339,460.00 339,460.00

178,600.00 17,860.00 196,460.00 196,460.00

110,350.00 11,035.00 121,385.00 121,385.00

105,150.00 10,515.00 115,665.00

Page 204: AHS 2008-Kota.xlsx

Analisa Gedung - 204

Jumlah

(5) 115,665.00

Page 205: AHS 2008-Kota.xlsx

Analisa Gedung - 205

Jumlah

(5)

123,350.00 12,335.00 135,685.00 135,685.00

93,390.00 9,339.00 102,729.00 102,729.00

310,112.00 31,011.20 341,123.20 341,123.00

180,112.00 18,011.20 198,123.20

Page 206: AHS 2008-Kota.xlsx

Analisa Gedung - 206

Jumlah

(5) 198,123.00

Page 207: AHS 2008-Kota.xlsx

Analisa Gedung - 207

Jumlah

(5)

111,862.00 11,186.20 123,048.20 123,048.00

106,662.00 10,666.20 117,328.20 117,328.00

124,862.00 12,486.20 137,348.20 137,348.00

94,902.00 9,490.20 104,392.20

Page 208: AHS 2008-Kota.xlsx

Analisa Gedung - 208

Jumlah

(5) 104,392.00

Page 209: AHS 2008-Kota.xlsx

Analisa Gedung - 209

Jumlah

(5)

295,375.00 29,537.50 324,912.50 324,912.00

14,176.25 1,417.63 15,593.88 15,593.00

19,458.75 1,945.88 21,404.63 21,404.00

28,175.00 2,817.50 30,992.50 30,992.00

10,695.00 1,069.50 11,764.50 11,764.00

Page 210: AHS 2008-Kota.xlsx

Analisa Gedung - 210

Jumlah

(5)

115,130.00 11,513.00 126,643.00 126,643.00

141,530.00 14,153.00 155,683.00 155,683.00

173,350.00 17,335.00 190,685.00 190,685.00

258,110.00 25,811.00 283,921.00 283,921.00

338,305.00 33,830.50 372,135.50 372,135.00

Page 211: AHS 2008-Kota.xlsx

Analisa Gedung - 211

Jumlah

(5)

198,730.00 19,873.00 218,603.00 218,603.00

62,330.00 6,233.00 68,563.00 68,563.00

75,530.00 7,553.00 83,083.00 83,083.00

94,150.00 9,415.00 103,565.00 103,565.00

137,110.00 13,711.00 150,821.00 150,821.00

Page 212: AHS 2008-Kota.xlsx

Analisa Gedung - 212

Jumlah

(5)

178,805.00 17,880.50 196,685.50 196,685.00

104,130.00 10,413.00 114,543.00 114,543.00

35,930.00 3,593.00 39,523.00 39,523.00

42,530.00 4,253.00 46,783.00 46,783.00

54,300.00 5,430.00 59,730.00 59,730.00

Page 213: AHS 2008-Kota.xlsx

Analisa Gedung - 213

Jumlah

(5)

76,610.00 7,661.00 84,271.00 84,271.00

99,055.00 9,905.50 108,960.50 108,960.00

56,830.00 5,683.00 62,513.00 62,513.00

32,330.00 3,233.00 35,563.00 35,563.00

38,030.00 3,803.00 41,833.00 41,833.00

Page 214: AHS 2008-Kota.xlsx

Analisa Gedung - 214

Jumlah

(5)

48,900.00 4,890.00 53,790.00 53,790.00

68,360.00 6,836.00 75,196.00 75,196.00

88,180.00 8,818.00 96,998.00 96,998.00

50,380.00 5,038.00 55,418.00 55,418.00

38,330.00 3,833.00 42,163.00 42,163.00

Page 215: AHS 2008-Kota.xlsx

Analisa Gedung - 215

Jumlah

(5)

45,530.00 4,553.00 50,083.00 50,083.00

57,900.00 5,790.00 63,690.00 63,690.00

82,110.00 8,211.00 90,321.00 90,321.00

106,305.00 10,630.50 116,935.50 116,935.00

61,130.00 6,113.00 67,243.00 67,243.00

Page 216: AHS 2008-Kota.xlsx

Analisa Gedung - 216

Jumlah

(5)

634,700.00 63,470.00 698,170.00 698,170.00

384,700.00 38,470.00 423,170.00 423,170.00

253,450.00 25,345.00 278,795.00 278,795.00

243,450.00 24,345.00 267,795.00 267,795.00

278,450.00 27,845.00 306,295.00 306,295.00

Page 217: AHS 2008-Kota.xlsx

Analisa Gedung - 217

Jumlah

(5)

93,424.00 9,342.40 102,766.40 102,766.00

49,424.00 4,942.40 54,366.40 54,366.00

27,424.00 2,742.40 30,166.40 30,166.00

24,424.00 2,442.40 26,866.40 26,866.00

29,424.00 2,942.40 32,366.40 32,366.00

Page 218: AHS 2008-Kota.xlsx

Analisa Gedung - 218

Jumlah

(5)

267,770.00 26,777.00 294,547.00 294,547.00

162,170.00 16,217.00 178,387.00 178,387.00

109,370.00 10,937.00 120,307.00 120,307.00

102,170.00 10,217.00 112,387.00 112,387.00

Page 219: AHS 2008-Kota.xlsx

Analisa Gedung - 219

Jumlah

(5)

114,170.00 11,417.00 125,587.00 125,587.00

472,360.00 47,236.00 519,596.00 519,596.00

261,610.00 26,161.00 287,771.00 287,771.00

157,110.00 15,711.00 172,821.00 172,821.00

Page 220: AHS 2008-Kota.xlsx

Analisa Gedung - 220

Jumlah

(5)

142,860.00 14,286.00 157,146.00 157,146.00

166,610.00 16,661.00 183,271.00 183,271.00

561,962.50

56,196.25 5,619.63 61,815.88 61,815.00

150,975.00 15,097.50 166,072.50 166,072.00

Page 221: AHS 2008-Kota.xlsx

Analisa Gedung - 221

Jumlah

(5)

149,325.00 14,932.50 164,257.50 164,257.00

163,950.00 16,395.00 180,345.00 180,345.00

186,950.00 18,695.00 205,645.00 205,645.00

576,825.00 57,682.50 634,507.50 634,507.00

304,825.00 30,482.50 335,307.50 335,307.00

Page 222: AHS 2008-Kota.xlsx

Analisa Gedung - 222

Jumlah

(5)

150,900.00 15,090.00 165,990.00 165,990.00

170,110.00 17,011.00 187,121.00 187,121.00

218,435.00 21,843.50 240,278.50 240,278.00

21,789.50 2,178.95 23,968.45 23,968.00

Page 223: AHS 2008-Kota.xlsx

Analisa Gedung - 223

Jumlah

(5)

186,875.00 18,687.50 205,562.50 205,562.00

39,800.00 3,980.00 43,780.00 43,780.00

43,600.00 4,360.00 47,960.00 47,960.00

39,300.00 3,930.00 43,230.00 43,230.00

43,100.00 4,310.00 47,410.00 47,410.00

Page 224: AHS 2008-Kota.xlsx

Analisa Gedung - 224

Jumlah

(5)

52,800.00 5,280.00 58,080.00 58,080.00

56,600.00 5,660.00 62,260.00 62,260.00

87,700.00 8,770.00 96,470.00 96,470.00

91,500.00 9,150.00 100,650.00 100,650.00

38,021.54 3,802.15 41,823.69 41,823.00

Page 225: AHS 2008-Kota.xlsx

Analisa Gedung - 225

Jumlah

(5)

43,021.54 4,302.15 47,323.69 47,323.00

46,021.54 4,602.15 50,623.69 50,623.00

82,021.54 8,202.15 90,223.69 90,223.00

45,444.50 4,544.45 49,988.95 49,988.00

49,444.50 4,944.45 54,388.95 54,388.00

Page 226: AHS 2008-Kota.xlsx

Analisa Gedung - 226

Jumlah

(5)

47,617.00 4,761.70 52,378.70 52,378.00

53,242.00 5,324.20 58,566.20 58,566.00

35,089.50 3,508.95 38,598.45 38,598.00

37,102.00 3,710.20 40,812.20 40,812.00

36,814.50 3,681.45 40,495.95 40,495.00

Page 227: AHS 2008-Kota.xlsx

Analisa Gedung - 227

Jumlah

(5)

39,299.50 3,929.95 43,229.45 43,229.00

38,734.50 3,873.45 42,607.95 42,607.00

51,721.60 5,172.16 56,893.76 56,893.00

48,544.50 4,854.45 53,398.95 53,398.00

51,496.40 5,149.64 56,646.04 56,646.00

Page 228: AHS 2008-Kota.xlsx

Analisa Gedung - 228

Jumlah

(5)

48,674.70 4,867.47 53,542.17 53,542.00

48,557.80 4,855.78 53,413.58 53,413.00

119,151.50 11,915.15 131,066.65 131,066.00

106,041.50 10,604.15 116,645.65 116,645.00

103,856.50 10,385.65 114,242.15 114,242.00

Page 229: AHS 2008-Kota.xlsx

Analisa Gedung - 229

Jumlah

(5)

74,271.50 7,427.15 81,698.65 81,698.00

74,271.50 7,427.15 81,698.65 81,698.00

74,271.50 7,427.15 81,698.65 81,698.00

43,535.00 4,353.50 47,888.50 47,888.00

41,771.50 4,177.15 45,948.65 45,948.00

Page 230: AHS 2008-Kota.xlsx

Analisa Gedung - 230

Jumlah

(5)

22,965.00 2,296.50 25,261.50 25,261.00

155,496.00 15,549.60 171,045.60 171,045.00

130,690.00 13,069.00 143,759.00 143,759.00

62,645.00 6,264.50 68,909.50 68,909.00

120,605.00 12,060.50 132,665.50 132,665.00

Page 231: AHS 2008-Kota.xlsx

Analisa Gedung - 231

Jumlah

(5)

82,380.00 8,238.00 90,618.00 90,618.00

34,595.00 3,459.50 38,054.50 38,054.00

328,075.00 32,807.50 360,882.50 360,882.00

350,355.00

35,035.50 3,503.55 38,539.05 38,539.00

23,357.00 2,335.70 25,692.70 25,692.00

11,678.50 1,167.85 12,846.35 12,846.00

Page 232: AHS 2008-Kota.xlsx

Analisa Gedung - 232

Jumlah

(5)

6,750.00 675.00 7,425.00 7,425.00

6,500.00 650.00 7,150.00 7,150.00

4,720.00 472.00 5,192.00 5,192.00

19,175.00 1,917.50 21,092.50 21,092.00

25,400.00 2,540.00 27,940.00 27,940.00

Page 233: AHS 2008-Kota.xlsx

Analisa Gedung - 233

Jumlah

(5)

28,602.50 2,860.25 31,462.75 31,462.00

19,652.50 1,965.25 21,617.75 21,617.00

31,250.00 3,125.00 34,375.00 34,375.00

5,065.00 506.50 5,571.50 5,571.00

20,321.00 2,032.10 22,353.10 22,353.00

Page 234: AHS 2008-Kota.xlsx

Analisa Gedung - 234

Jumlah

(5)

9,181.00 918.10 10,099.10 10,099.00

6,082.00 608.20 6,690.20 6,690.00

#NAME?#NAME?#NAME?#NAME?

3,932.00 393.20 4,325.20 4,325.00

8,097.00 809.70 8,906.70 8,906.00

Page 235: AHS 2008-Kota.xlsx

Analisa Gedung - 235

Jumlah

(5)

3,925.00 392.50 4,317.50 4,317.00

17,917.50 1,791.75 19,709.25 19,709.00

19,236.50 1,923.65 21,160.15 21,160.00

69,410.00 6,941.00 76,351.00 76,351.00

13,111.00 1,311.10 14,422.10 14,422.00

Page 236: AHS 2008-Kota.xlsx

Analisa Gedung - 236

Jumlah

(5)

23,566.00 2,356.60 25,922.60 25,922.00

Page 237: AHS 2008-Kota.xlsx

Analisa Gedung - 237

Jumlah

(5)

6,600.00 660.00 7,260.00 7,260.00

52,598.00 5,259.80 57,857.80 57,857.00

19,981.00 1,998.10 21,979.10 21,979.00

184,400.00 18,440.00 202,840.00 202,840.00

88,600.00 8,860.00 97,460.00 97,460.00

300,500.00 30,050.00 330,550.00 330,550.00

Page 238: AHS 2008-Kota.xlsx

Analisa Gedung - 238

Jumlah

(5)

76,000.00

7,600.00 760.00 8,360.00 8,360.00

50,000.00

5,000.00 500.00 5,500.00 5,500.00

76,000.00

7,600.00 760.00 8,360.00 8,360.00

58,500.00

5,850.00 585.00 6,435.00 6,435.00

107,500.00

10,750.00 1,075.00 11,825.00 11,825.00

76,000.00

7,600.00 760.00 8,360.00 8,360.00

Page 239: AHS 2008-Kota.xlsx

Analisa Gedung - 239

Jumlah

(5)

467,000.00 46,700.00 513,700.00 513,700.00

44,000.00 4,400.00 48,400.00 48,400.00

782,000.00 78,200.00 860,200.00 860,200.00

88,975.00 8,897.50 97,872.50 97,872.00

115,975.00 11,597.50 127,572.50 127,572.00

201,875.00 20,187.50 222,062.50 222,062.00

Page 240: AHS 2008-Kota.xlsx

Analisa Gedung - 240

Jumlah

(5)

2,291,995.00 229,199.50 2,521,194.50 2,521,194.00

478,994.00 47,899.40 526,893.40 526,893.00

210,444.00 21,044.40 231,488.40 231,488.00

2,692,344.00 269,234.40 2,961,578.40 2,961,578.00

1,072,919.00 107,291.90 1,180,210.90

Page 241: AHS 2008-Kota.xlsx

Analisa Gedung - 241

Jumlah

(5) 1,180,210.00

Page 242: AHS 2008-Kota.xlsx

Analisa Gedung - 242

Jumlah

(5)

621,250.00 62,125.00 683,375.00 683,375.00

466,937.50 46,693.75 513,631.25 513,631.00

1,607,750.00 160,775.00 1,768,525.00 1,768,525.00

61,782.52 6,178.25 67,960.77 67,960.00

86,468.68 8,646.87 95,115.55 95,115.00

Page 243: AHS 2008-Kota.xlsx

Analisa Gedung - 243

Jumlah

(5)

72,280.88 7,228.09 79,508.97 79,508.00

210,170.20 21,017.02 231,187.22 231,187.00

249,301.00 24,930.10 274,231.10 274,231.00

225,595.50 22,559.55 248,155.05 248,155.00

Page 244: AHS 2008-Kota.xlsx

Analisa Gedung - 244

Jumlah

(5)

343,270.00 34,327.00 377,597.00 377,597.00

30,504.00 3,050.40 33,554.40 33,554.00

46,004.00 4,600.40 50,604.40 50,604.00

65,379.00 6,537.90 71,916.90 71,916.00

90,064.00 9,006.40 99,070.40 99,070.00

Page 245: AHS 2008-Kota.xlsx

Analisa Gedung - 245

Jumlah

(5)

144,314.00 14,431.40 158,745.40 158,745.00

155,207.00 15,520.70 170,727.70 170,727.00

9,089.88 908.99 9,998.86 9,998.00

10,775.50 1,077.55 11,853.05 11,853.00

12,131.75 1,213.18 13,344.93 13,344.00

Page 246: AHS 2008-Kota.xlsx

Analisa Gedung - 246

Jumlah

(5)

21,625.50 2,162.55 23,788.05 23,788.00

29,546.40 2,954.64 32,501.04 32,501.00

35,963.00 3,596.30 39,559.30 39,559.00

42,676.00 4,267.60 46,943.60 46,943.00

63,213.50 6,321.35 69,534.85 69,534.00

Page 247: AHS 2008-Kota.xlsx

Analisa Gedung - 247

Jumlah

(5)

715,240.00 71,524.00 786,764.00 786,764.00

594,480.00 59,448.00 653,928.00 653,928.00

190,472.50 19,047.25 209,519.75 209,519.00

140,260.00 14,026.00 154,286.00 154,286.00

14,407.00 1,440.70 15,847.70 15,847.00

Page 248: AHS 2008-Kota.xlsx

Analisa Gedung - 248

Jumlah

(5) 1,198,250.00 59,912.50 12,581.63 1,258.16 13,839.79 13,839.00

1,055,250.00 52,762.50 11,080.13 1,108.01 12,188.14

Page 249: AHS 2008-Kota.xlsx

Analisa Gedung - 249

Jumlah

(5) 12,188.00

1,106,150.00 55,307.50 11,614.58 1,161.46 12,776.03 12,776.00

1,201,750.00 60,087.50 12,618.38 1,261.84 13,880.21 13,880.00

1,179,250.00 58,962.50 12,382.13 1,238.21 13,620.34 13,620.00

814.00 81.40 895.40 895.00

762,837.50 762,837.00

Page 250: AHS 2008-Kota.xlsx

Analisa Gedung - 250

Jumlah

(5) 778,907.50 778,907.00

807,017.50 80,701.75 887,719.25 887,719.00

840,247.50 84,024.75 924,272.25 924,272.00

1,596,732.00 159,673.20 1,756,405.20 1,756,405.00

353,140.00 35,314.00 388,454.00 388,454.00

590,245.50 59,024.55 649,270.05 649,270.00

292,840.00 29,284.00 322,124.00

Page 251: AHS 2008-Kota.xlsx

Analisa Gedung - 251

Jumlah

(5) 322,124.00

Page 252: AHS 2008-Kota.xlsx

Analisa Gedung - 252

Jumlah

(5)

310,495.50 31,049.55 341,545.05 341,545.00

490,245.50 49,024.55 539,270.05 539,270.00

280,082.50 28,008.25 308,090.75 308,090.00

198,994.00 19,899.40 218,893.40 218,893.00

46,470.00 4,647.00 51,117.00 51,117.00

Page 253: AHS 2008-Kota.xlsx

Analisa Gedung - 253

Jumlah

(5)

28,045.00 2,804.50 30,849.50 30,849.00

29,970.00 2,997.00 32,967.00 32,967.00

35,470.00 3,547.00 39,017.00 39,017.00

40,127.50 4,012.75 44,140.25 44,140.00

283,780.00 28,378.00 312,158.00 312,158.00

Page 254: AHS 2008-Kota.xlsx

Analisa Gedung - 254

Jumlah

(5)

149,810.00 14,981.00 164,791.00 164,791.00

74,280.00 7,428.00 81,708.00 81,708.00

99,190.00 9,919.00 109,109.00 109,109.00

19,445.00 1,944.50 21,389.50 21,389.00

13,310.00 1,331.00 14,641.00 14,641.00

14,620.00 1,462.00 16,082.00 16,082.00

Page 255: AHS 2008-Kota.xlsx

Analisa Gedung - 255

Jumlah

(5)

15,945.00 1,594.50 17,539.50 17,539.00

11,445.00 1,144.50 12,589.50 12,589.00

178,150.00 17,815.00 195,965.00 195,965.00

61,260.00 6,126.00 67,386.00 67,386.00

43,150.00 4,315.00 47,465.00 47,465.00

20,630.00 2,063.00 22,693.00 22,693.00

Page 256: AHS 2008-Kota.xlsx

Analisa Gedung - 256

Jumlah

(5)

233,780.00 23,378.00 257,158.00 257,158.00

26,075.00 2,607.50 28,682.50 28,682.00

62,895.00 6,289.50 69,184.50 69,184.00

74,995.00 7,499.50 82,494.50 82,494.00

140,445.00 14,044.50 154,489.50 154,489.00

338,445.00 33,844.50 372,289.50 372,289.00

Page 257: AHS 2008-Kota.xlsx

Analisa Gedung - 257

Jumlah

(5)

76,782.50 76,782.00

180,000.00

935,000.00

213,300.00

1,328,300.00 132,830.00 1,461,130.00 1,461,130.00

6,213.20

299,037.50 305,250.70 30,525.07 335,775.77 335,775.00

5,262,790.00 526,279.00 5,789,069.00 5,789,069.00

Page 258: AHS 2008-Kota.xlsx

Analisa Gedung - 258

Jumlah

(5)

291,000.00 29,100.00 320,100.00 320,100.00

460,000.00 46,000.00 506,000.00 506,000.00

382,000.00 38,200.00 420,200.00 420,200.00

4,202.00

1,004,068.00 100,406.80 1,104,474.80 1,104,474.00

11,044.74

Page 259: AHS 2008-Kota.xlsx

Analisa Gedung - 259

Jumlah

(5)

66,708.00 6,670.80 73,378.80 73,378.00

15,750.00 1,575.00 17,325.00 17,325.00

115,542,000.00 11,554,200.00 127,096,200.00 127,096,200.00

34.82

44,183.30 4,418.33 48,601.63 48,601.00

48.60

205,480.00 20,548.00 226,028.00 226,028.00 452,056.00

Page 260: AHS 2008-Kota.xlsx

Analisa Gedung - 260

Jumlah

(5) 15.07

Page 261: AHS 2008-Kota.xlsx

Analisa Gedung - 261

Jumlah

(5)

340,115.00 34,011.50 374,126.50 374,126.00 748,252.00

24.94

133,580.50 13,358.05 146,938.55 146,938.00 293,876.00

9.80

187,115.50 18,711.55 205,827.05 205,827.00 411,654.00

13.72

222,320.50 22,232.05 244,552.55 244,552.00

Page 262: AHS 2008-Kota.xlsx

Analisa Gedung - 262

Jumlah

(5)

113,770.50 11,377.05 125,147.55 125,147.00

27,065.68 2,706.57 29,772.25 29,772.00

48,505.12 4,850.51 53,355.63 53,355.00

Page 263: AHS 2008-Kota.xlsx

ANALISA SATUAN PEKERJAANNo. Macam Pekerjaan Upah

(1) (2) (3)

PEKERJAAN PERSIAPAN

SNI 100.00 Pekerjaan Pengukuran Gedung2007 8.0000 org Pekerja @ Rp. 36,000.00 288,000.00

2.0000 org Mandor @ Rp. 40,000.00 80,000.00 0.5000 org Pengawas @ Rp. 50,000.00 25,000.00 2.0000 org Asisten Ahli Ukur @ Rp. 95,000.00 190,000.00 1.0000 hr Sewa alat ukur @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

1.0000 Pekerjaan Pengukuran0.01 x #N/A #N/A

SNI 1.0000 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran

2007 0.0120 Kayu meranti balok @ Rp. #N/A 0.0200 kg Paku reng @ Rp. #N/A

0.0070 Kayu meranti papan 3/20 @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membersihkan lapangan dan perataan2007 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00

0.0500 org Mandor @ Rp. 40,000.00 2,000.00 JUMLAH ( BELUM PPN ) 5,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Membuat Papan Nama Proyek 80x120 cm

2007 0.0350 Kayu meranti @ Rp. 2,750,000.00

1.4000 Seng plat lebar 90 cm @ Rp. #N/A 0.6000 kg Paku @ Rp. - 1.5000 kg Cat kayu @ Rp. #N/A 16.8000 kg PC @ Rp. #N/A

0.0270 Pasir beton @ Rp. #N/A

0.0405 Kerikil beton @ Rp. #N/A 0.0175 org Tukang batu @ Rp. 42,500.00 743.75 1.0000 org Tukang kayu @ Rp. 47,500.00 47,500.00 1.0000 org Tukang cat @ Rp. 42,500.00 42,500.00 2.1000 org Pekerja @ Rp. 36,000.00 75,600.00 1.0050 org Mandor @ Rp. 40,000.00 40,200.00

m2

m2

m1

m3

m3

m2

m3

m1

m3

m3

Page 264: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 206,543.75 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan jalan sementara, tebal 25 cm

2007 0.2750 Batu belah @ Rp. #N/A

0.0300 Kerikil @ Rp. #N/A

0.0500 Pasir @ Rp. #N/A 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 40,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan kantor sementara, dengan lantai plesteran2007 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. #N/A

0.1800 Kayu meranti @ Rp. 2,750,000.00 0.8500 kg Paku biasa @ Rp. #N/A 1.1000 kg Baja strip @ Rp. #N/A 35.0000 kg PC @ Rp. #N/A

0.1500 Pasir pasang @ Rp. #N/A

0.1000 Pasir beton @ Rp. #N/A

0.1500 Kerikil beton @ Rp. #N/A 30.0000 bh Bata merah @ Rp. #N/A 0.2500 lbr Seng plat 3" x 6 " @ Rp. #N/A 2.0000 bh Jendela nako @ Rp. 20,000.00

0.0800 Kaca polos @ Rp. #N/A 0.1500 bh Kunci tanam @ Rp. 35,000.00 0.0600 lbr Plywood 4 mm @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.3000 org Kepala tukang @ Rp. #N/A #N/A 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter2007 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. #N/A

2.5000 kg PC @ Rp. #N/A 1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. #N/A

0.0050 Pasir beton @ Rp. #N/A

0.0090 Kerikil beton @ Rp. #N/A

0.0250 Kaso 5/7 kayu meranti @ Rp. #N/A 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.4000 kg Meni besi @ Rp. #N/A 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

m2

m3

m3

m3

m2

m3

m3

m3

m3

m2

m1

m3

m3

m3

Page 265: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 25,700.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter2007 1.0000 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. #N/A

2.0000 kg PC @ Rp. #N/A 25.0000 kg Kawat duri @ Rp. 9,500.00

0.0050 Pasir beton @ Rp. #N/A

0.0090 Kerikil beton @ Rp. #N/A 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 22,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan gudang semen dan alat-alat2007 1.7000 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. #N/A

0.2100 Kayu @ Rp. - 0.3000 kg Paku biasa @ Rp. #N/A 10.5000 kg PC @ Rp. #N/A

0.0300 Pasir beton @ Rp. #N/A

0.0500 Kerikil beton @ Rp. #N/A 1.5000 lbr Seng gelombang BJLS 32 @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 143,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan rumah jaga/konstruksi kayu2007 3.0000 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. #N/A

0.2760 Kayu @ Rp. - 0.7000 kg Paku biasa @ Rp. #N/A 1.5000 lbr Seng gelombang BJLS 32 @ Rp. #N/A 1.5000 org Tukang kayu @ Rp. 47,500.00 71,250.00 0.1500 org Kepala tukang kayu @ Rp. 50,000.00 7,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 116,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan bedeng buruh2007 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. #N/A

m1

m3

m3

m2

m2

m3

m3

m2

m3

m2

Page 266: AHS 2008-Kota.xlsx

0.1860 Kayu @ Rp. - 0.3000 kg Paku biasa @ Rp. #N/A 18.0000 kg PC @ Rp. #N/A

0.0300 Pasir beton @ Rp. #N/A

0.0500 Kerikil beton @ Rp. #N/A 1.5000 lbr Seng gelombang BJLS 32 @ Rp. #N/A 4.3500 lbr Plywood 4 mm @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 143,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan bak adukan, uk. 40 x 50 x 20 cm

2007 0.0360 Kayu terentang @ Rp. #N/A 0.0800 kg Paku @ Rp. - 1.0000 btg Kaso 5/7 @ Rp. #N/A 0.3000 org Tukang kayu @ Rp. 47,500.00 14,250.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 14,310.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan stegger dari bambu, ukuran 40 x 50 x 20 cm2007 1.0000 btg Bambu @ Rp. #N/A

0.2500 kg Tali ijuk @ Rp. #N/A 0.0170 org Tukang kayu @ Rp. 47,500.00 807.50 0.0020 org Kepala tukang kayu @ Rp. 50,000.00 100.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 10,427.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pagar kawat jaring galvanis, tinggi 1,00 m2007 0.4340 lbr Pagar kawat jaring @ Rp. #N/A

0.0420 org Tukang besi @ Rp. 45,000.00 1,890.00 0.0040 org Kepala tukang besi @ Rp. 47,500.00 190.00 0.0420 org Pekerja @ Rp. 36,000.00 1,512.00 0.0020 org Mandor @ Rp. 40,000.00 80.00

JUMLAH ( BELUM PPN ) 3,672.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm2007 0.9860 lbr Panel beton pracetak @ Rp. 350,000.00

0.5250 btg Kolom beton pracetak @ Rp. 500,000.00

0.0740 Pasir beton @ Rp. #N/A

0.1460 Batu pecah 2/3 @ Rp. #N/A

m3

m3

m3

m2

m3

m2

m1

m1

m3

m3

Page 267: AHS 2008-Kota.xlsx

45.0000 kg PC @ Rp. #N/A 0.1250 org Tukang batu @ Rp. 42,500.00 5,312.50 0.0120 org Kepala tukang @ Rp. #N/A #N/A 0.3750 org Pekerja @ Rp. 36,000.00 13,500.00 0.0190 org Mandor @ Rp. 40,000.00 760.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

PEKERJAAN TANAH

SNI 1.0000 Galian tanah biasa sedalam sampai 1 meter6.1 0.7500 org Pekerja @ Rp. 36,000.00 27,000.00

2008 0.0250 org Mandor @ Rp. 40,000.00 1,000.00 JUMLAH ( BELUM PPN ) 28,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah biasa sedalam 1 - 2 meter6.2 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00

2008 0.0450 org Mandor @ Rp. 40,000.00 1,800.00 JUMLAH ( BELUM PPN ) 34,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah biasa sedalam 2 - 3 meter6.3 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00

2008 0.0670 org Mandor @ Rp. 40,000.00 2,680.00 JUMLAH ( BELUM PPN ) 40,480.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah keras sedalam sampai 1 meter6.4 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00

2008 0.0320 org Mandor @ Rp. 40,000.00 1,280.00 JUMLAH ( BELUM PPN ) 37,280.00 JASA 10 %JUMLAH 0.76 DIBULATKAN

SNI 1.0000 Galian tanah cadas sedalam sampai 1 meter6.5 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00

2008 0.0600 org Mandor @ Rp. 40,000.00 2,400.00 JUMLAH ( BELUM PPN ) 56,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Galian tanah lumpur sedalam 1 meter6.6 1.2000 org Pekerja @ Rp. 36,000.00 43,200.00

2008 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

m3

m3

m3

m3

m3

m3

Page 268: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 45,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m3 Stripping tebing setinggi 1 meter2835:2008 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00

0.0050 org Mandor @ Rp. 40,000.00 200.00 JUMLAH ( BELUM PPN ) 2,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengangkut tanah sejauh 15 meter2835:2008 0.3300 org Pekerja @ Rp. 36,000.00 11,880.00

0.0100 org Mandor @ Rp. 40,000.00 400.00 JUMLAH ( BELUM PPN ) 12,280.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Urug kembali bekas galian (dihitung 1/3 kali galian tanah)2835:2008 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00

0.0083 org Mandor @ Rp. 40,000.00 332.00 JUMLAH ( BELUM PPN ) 9,332.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memadatkan tanah per 20 cm2835:2008 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00

0.0500 org Mandor @ Rp. 40,000.00 2,000.00 JUMLAH ( BELUM PPN ) 20,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Urug pasir

2835:2008 1.2000 Pasir urug @ Rp. #N/A 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 11,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Urugan sirtu padat untuk peninggian lantai bangunan

2835:2008 1.2000 Sirtu @ Rp. 66,000.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 10,000.00 JASA 10 %JUMLAHDIBULATKAN

m3

m3

m2

m3

m3

m3

m3

Page 269: AHS 2008-Kota.xlsx

SNI 1.0000 Urug tanah mendatangkan

2007 1.2000 Tanah urug @ Rp. 35,000.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 11,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang Lapisan pudel campuran 1 KP : 3 PP : 7 TL untuk stabilisasi

2835:2008 0.1350 Kapur pasang @ Rp. 72,500.00 0.4000 m3 Pasir pasang progo @ Rp. #N/A 0.9480 m3 Tanah liat @ Rp. #N/A 0.4000 org Tukang Batu @ Rp. 42,500.00 17,000.00 0.0400 org Kepala Tukang Batu @ Rp. 45,000.00 1,800.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

JUMLAH ( BELUM PPN ) 50,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi

2835:2008 0.2480 Kapur pasang @ Rp. 72,500.00 1.2400 m3 Tanah liat @ Rp. #N/A 0.4000 org Tukang Batu @ Rp. 42,500.00 17,000.00 0.0400 org Kepala Tukang Batu @ Rp. 45,000.00 1,800.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

JUMLAH ( BELUM PPN ) 50,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Gebalan rumput2007 0.2000 btg Bambu @ Rp. #N/A

1.0000 Gebalan rumput @ Rp. #N/A 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 19,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat sumur2007 2.0000 bh Buis beton D. 80 cm @ Rp. #N/A

1.0000 org Tukang gali sumur @ Rp. #N/A #N/A 0.7350 org Pekerja @ Rp. 36,000.00 26,460.00 0.0735 org Mandor @ Rp. 40,000.00 2,940.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pemasangan lapisan ijuk tebal 10cm untuk peresapan

m3

m3

m3

m3

m3

m3

m2

m2

m1

m3

Page 270: AHS 2008-Kota.xlsx

2835:2008 6.0000 kg Ijuk @ Rp. 75,000.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 6,000.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN PASANGAN

Pasangan pondasi

SNI 1.0000 Pasangan pondasi batu kosong (anstamping)

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A

0.4320 Pasir urug @ Rp. #N/A 0.3900 org Tukang Batu @ Rp. 42,500.00 16,575.00 0.0390 org Kepala Tukang Batu @ Rp. 45,000.00 1,755.00 0.7800 org Pekerja @ Rp. 36,000.00 28,080.00 0.0390 org Mandor @ Rp. 40,000.00 1,560.00

JUMLAH ( BELUM PPN ) 47,970.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Kp : 1 Sm : 1 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A

0.2290 Kapur pasang @ Rp. 72,500.00

0.2290 Semen merah @ Rp. #N/A

0.5440 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Kp : 1 Sm : 2 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A

0.1700 Kapur pasang @ Rp. 72,500.00

0.1700 Semen merah @ Rp. #N/A

0.3400 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 3 Kp : 5 Ps

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 271: AHS 2008-Kota.xlsx

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 95.4200 kg PC @ Rp. #N/A

0.2290 Kapur pasang @ Rp. 72,500.00

0.3820 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 3 Kp : 10 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 61.0000 kg PC @ Rp. #N/A

0.1470 Kapur pasang @ Rp. 72,500.00

0.4920 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1/4 Pc : 1 Kp : 4 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 41.0000 kg PC @ Rp. #N/A

0.1310 Kapur pasang @ Rp. 72,500.00

0.5230 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 4 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 163.0000 kg PC @ Rp. #N/A

0.5200 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 3 Ps

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 272: AHS 2008-Kota.xlsx

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 202.0000 kg PC @ Rp. #N/A

0.4850 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 1 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 392.0000 kg PC @ Rp. #N/A

0.3140 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 2 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 267.0000 kg PC @ Rp. #N/A

0.4270 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 5 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 136.0000 kg PC @ Rp. #N/A

0.5440 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 6 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 117.0000 kg PC @ Rp. #N/A

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 273: AHS 2008-Kota.xlsx

0.5610 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi 1 Pc : 8 Ps

2836-2008 1.2000 Batu belah 15/20 @ Rp. #N/A 91.0000 kg PC @ Rp. #N/A

0.5840 Pasir pasang progo @ Rp. #N/A 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 92,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Beton cyclope 60% beton camp. 1pc:2ps:3kr, 40% batu belah

2836-2008 0.4800 Batu belah 15/20 @ Rp. #N/A 194.0000 kg PC @ Rp. #N/A

0.3120 Pasir beton @ Rp. #N/A

0.4680 Kerikil beton @ Rp. #N/A 126.0000 kg Besi beton @ Rp. - 1.8000 kg Kawat beton @ Rp. #N/A 0.8500 org Tukang batu @ Rp. 42,500.00 36,125.00 0.0850 org Kepala Tukang Batu @ Rp. 45,000.00 3,825.00 3.4000 org Pekerja @ Rp. 36,000.00 122,400.00 0.1700 org Mandor @ Rp. 40,000.00 6,800.00

JUMLAH ( BELUM PPN ) 169,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan pondasi sumuran dia. 100 cm

2836-2008 0.4500 Batu belah 15/20 @ Rp. #N/A 194.0000 kg PC @ Rp. #N/A

312.0000 Pasir beton @ Rp. #N/A 0.4680 m3 Kerikil beton @ Rp. #N/A 0.8000 org Tukang Batu @ Rp. 42,500.00 34,000.00 0.0800 org Kepala Tukang Batu @ Rp. 45,000.00 3,600.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1190 org Mandor @ Rp. 40,000.00 4,760.00

JUMLAH ( BELUM PPN ) 128,760.00 JASA 10 %JUMLAHDIBULATKAN

Pasangan dinding

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 274: AHS 2008-Kota.xlsx

SNI 1.0000 Pasangan dinding HB/CB 10, camp. 1pc : 4ps6897-2008 12.5000 bh HB 10 @ Rp. #N/A

12.1300 kg PC @ Rp. #N/A

0.3880 Pasir pasang progo @ Rp. #N/A 0.2800 kg Besi angkur dia. 8mm @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan dinding HB/CB 10, camp. 1pc : 3ps6897-2008 12.5000 bh HB 10 @ Rp. #N/A

15.1600 kg PC @ Rp. #N/A

0.3640 Pasir pasang progo @ Rp. #N/A 0.2800 kg Besi angkur dia. 8mm @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan dinding HB/CB 15, camp. 1pc : 4ps6897-2008 12.5000 bh HB 15 @ Rp. #N/A

18.2000 kg PC @ Rp. #N/A

0.5820 Pasir pasang progo @ Rp. #N/A 0.2800 kg Besi angkur dia. 8mm @ Rp. #N/A 0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0160 org Mandor @ Rp. 40,000.00 640.00

JUMLAH ( BELUM PPN ) 17,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan dinding HB/CB 15, camp. 1pc : 3ps6897-2008 12.5000 bh HB 15 @ Rp. #N/A

22.7400 kg PC @ Rp. #N/A

0.5500 Pasir pasang progo @ Rp. #N/A 0.2800 kg Besi angkur dia. 8mm @ Rp. #N/A 0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0160 org Mandor @ Rp. 40,000.00 640.00

JUMLAH ( BELUM PPN ) 17,800.00 JASA 10 %JUMLAH

m2

m3

m2

m3

m2

m3

m2

m3

Page 275: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasangan dinding HB/CB 20, camp. 1pc : 4ps6897-2008 12.5000 bh HB 20 @ Rp. #N/A

24.2600 kg PC @ Rp. #N/A

0.7720 Pasir pasang progo @ Rp. #N/A 0.2800 kg Besi angkur dia. 8mm @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 20,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan dinding HB/CB 20, camp. 1pc : 3ps6897-2008 12.5000 bh HB 20 @ Rp. #N/A

30.3200 kg PC @ Rp. #N/A

0.7280 Pasir pasang progo @ Rp. #N/A 0.2800 kg Besi angkur dia. 8mm @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 20,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

0.0140 Kapur pasang @ Rp. 72,500.00

0.0140 Semen merah @ Rp. #N/A

0.0280 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

0.0180 Kapur pasang @ Rp. 72,500.00

0.0180 Semen merah @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00

m2

m3

m2

m3

m2

m3

m3

m3

m2

m3

m3

m3

Page 276: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

4.5000 kg PC @ Rp. #N/A

0.0150 Kapur pasang @ Rp. 72,500.00

0.0500 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

6.5000 kg PC @ Rp. #N/A

0.0500 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

8.3200 kg PC @ Rp. #N/A

0.0490 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

9.6800 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAH

m2

m3

m3

m2

m3

m2

m3

m2

m3

Page 277: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

11.5000 kg PC @ Rp. #N/A

0.0430 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

14.3700 kg PC @ Rp. #N/A

0.0400 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps6897-2008 70.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

18.9500 kg PC @ Rp. #N/A

0.0380 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM TERMASUK PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps6897-2008 140.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

10.0800 kg PC @ Rp. #N/A

0.0275 Kapur pasang @ Rp. 72,500.00

0.0925 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 32,200.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

m3

Page 278: AHS 2008-Kota.xlsx

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps6897-2008 140.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

18.5000 kg PC @ Rp. #N/A

0.1220 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 32,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps6897-2008 140.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

22.2000 kg PC @ Rp. #N/A

0.1020 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 32,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps6897-2008 140.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

26.5500 kg PC @ Rp. #N/A

0.0930 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 32,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps6897-2008 140.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

32.9500 kg PC @ Rp. #N/A

0.0910 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 32,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps6897-2008 140.0000 bh Batu Bata 5 x 11 x 22 @ Rp. #N/A

43.5000 kg PC @ Rp. #N/A

m2

m3

m2

m3

m2

m3

m2

m3

m2

Page 279: AHS 2008-Kota.xlsx

0.0800 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM TERMASUK PPN ) 32,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 4ps6897-2008 30.0000 bh Terawang / roster 12x11x24 cm @ Rp. #N/A

11.0000 kg PC @ Rp. #N/A

0.0350 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 3ps6897-2008 30.0000 bh Terawang / roster 12x11x24 cm @ Rp. #N/A

14.0000 kg PC @ Rp. #N/A

0.0320 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan bata merah expose (5 x 11 x 24 cm), camp. 1 Pc : 3 Ps6897-2008 70.0000 bh Bata expose 5 x 11 x 24 cm @ Rp. #N/A

14.0000 kg PC @ Rp. #N/A

0.0320 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan dinding bataco2007 12.5000 bh Bataco @ Rp. #N/A

12.5000 kg PC @ Rp. #N/A

0.0400 Pasir pasang @ Rp. #N/A 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 280: AHS 2008-Kota.xlsx

0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 23,700.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasangan roster 25/25 cm2007 16.0000 bh Roster 25/25 cm @ Rp. #N/A

12.5000 kg PC @ Rp. #N/A

0.0400 Pasir pasang @ Rp. #N/A 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 23,700.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN BETON

SNI 1.0000 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr2007 336.0000 kg PC @ Rp. #N/A

0.5400 Pasir beton @ Rp. #N/A

0.8100 Kerikil beton @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala tukang batu @ Rp. 45,000.00 1,125.00 1.6500 org Pekerja @ Rp. 36,000.00 59,400.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

JUMLAH ( BELUM PPN ) 74,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr2007 218.0000 kg PC @ Rp. #N/A

0.5200 Pasir beton @ Rp. #N/A

0.8700 Kerikil beton @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala tukang batu @ Rp. 45,000.00 1,125.00 1.6500 org Pekerja @ Rp. 36,000.00 59,400.00 0.0800 org Mandor @ Rp. 40,000.00 3,200.00

JUMLAH ( BELUM PPN ) 74,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 6897-2008 247.000 kg PC @Rp. #N/A

0.621 m3 Pasir beton @Rp. #N/A 0.740 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50

m2

m3

m3

m3

m3

m3

m3

m3

Page 281: AHS 2008-Kota.xlsx

0.083 OH Mandor @Rp. 40,000.00 3,300.00 JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Betonmutu f’ = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,786897-2008 276.000 kg PC @Rp. #N/A

0.591 m3 Pasir beton @Rp. #N/A 0.750 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72 6897-2008 299.000 kg PC @Rp. #N/A

0.571 m3 Pasir beton @Rp. #N/A 0.753 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87 6897-2008 230.000 kg PC @Rp. #N/A

0.638 m3 Pasir beton @Rp. #N/A 0.761 m3 Batu split 1/2 @Rp. #N/A 1.200 OH Pekerja @Rp. 36,000.00 43,200.00 0.200 OH Tukang Batu @Rp. 42,500.00 8,500.00 0.020 OH Kepala Tukang Batu @Rp. 45,000.00 900.00 0.060 OH Mandor @Rp. 40,000.00 2,400.00

JUMLAH ( BELUM PPN ) 55,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 6897-2008 326.000 kg PC @Rp. #N/A

0.543 m3 Pasir beton @Rp. #N/A 0.762 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

Page 282: AHS 2008-Kota.xlsx

SNI 1.000 m3 Beton mutu f’'c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61 6897-2008 352.000 kg PC @Rp. #N/A

0.522 m3 Pasir beton @Rp. #N/A 0.764 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 6897-2008 371.000 kg PC @Rp. #N/A

0.499 m3 Pasir beton @Rp. #N/A 0.776 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 6897-2008 384.000 kg PC @Rp. #N/A

0.494 m3 Pasir beton @Rp. #N/A 0.770 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53 6897-2008 406.000 kg PC @Rp. #N/A

0.489 m3 Pasir beton @Rp. #N/A 0.760 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,526897-2008 413.000 kg PC @Rp. #N/A

0.486 m3 Pasir beton @Rp. #N/A

Page 283: AHS 2008-Kota.xlsx

0.756 m3 Batu split 1/2 @Rp. #N/A 1.650 OH Pekerja @Rp. 36,000.00 59,400.00 0.275 OH Tukang Batu @Rp. 42,500.00 11,687.50 0.028 OH Kepala Tukang Batu @Rp. 45,000.00 1,237.50 0.083 OH Mandor @Rp. 40,000.00 3,300.00

JUMLAH ( BELUM PPN ) 75,625.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,496897-2008 439.000 kg PC @Rp. #N/A

0.479 m3 Pasir beton @Rp. #N/A 0.745 m3 Batu split 1/2 @Rp. #N/A 2.100 OH Pekerja @Rp. 36,000.00 75,600.00 0.350 OH Tukang Batu @Rp. 42,500.00 14,875.00 0.035 OH Kepala Tukang Batu @Rp. 45,000.00 1,575.00 0.105 OH Mandor @Rp. 40,000.00 4,200.00

JUMLAH ( BELUM PPN ) 96,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton mutu f’'c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,486897-2008 448.000 kg PC @Rp. #N/A

0.476 m3 Pasir beton @Rp. #N/A 0.741 m3 Batu split 1/2 @Rp. #N/A 2.100 OH Pekerja @Rp. 36,000.00 75,600.00 0.350 OH Tukang Batu @Rp. 42,500.00 14,875.00 0.035 OH Kepala Tukang Batu @Rp. 45,000.00 1,575.00 0.105 OH Mandor @Rp. 40,000.00 4,200.00

JUMLAH ( BELUM PPN ) 96,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membongkar cetakan2007 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00

JUMLAH ( BELUM PPN ) 144,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI

2007 0.7000 Perancah/dolken @ Rp. #N/A 10.5000 org Tukang kayu @ Rp. 47,500.00 498,750.00 1.0500 org Kepala Tukang Kayu @ Rp. 50,000.00 52,500.00 3.5000 org Pekerja @ Rp. 36,000.00 126,000.00 0.1750 org Mandor @ Rp. 40,000.00 7,000.00

JUMLAH ( BELUM PPN ) 684,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI2007 32.0000 unit Scafolding @ Rp. #N/A

m3

Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai dolken )

m3

Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai scafolding )

Page 284: AHS 2008-Kota.xlsx

3.5000 org Tukang kayu @ Rp. 47,500.00 166,250.00 0.3500 org Kepala Tukang Kayu @ Rp. 50,000.00 17,500.00 2.2000 org Pekerja @ Rp. 36,000.00 79,200.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM TERMASUK PPN ) 267,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m3 Beton kedap air dengan strorox – 100 6897-2008 400.000 kg PC @Rp. #N/A

0.480 m3 Pasir beton @Rp. #N/A 0.800 m3 Batu split 1/2 @Rp. #N/A 1.200 m3 Storox - 100 @Rp. #N/A 2.100 OH Pekerja @Rp. 36,000.00 75,600.00 0.350 OH Tukang Batu @Rp. 42,500.00 14,875.00 0.035 OH Kepala Tukang Batu @Rp. 45,000.00 1,575.00 0.105 OH Mandor @Rp. 40,000.00 4,200.00

JUMLAH ( BELUM PPN ) 96,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m' PVC Waterstop lebar 150 mm 6897-2008 1.050 m' Waterstop lebar 150 mm @Rp. #N/A

0.060 OH Pekerja @Rp. 36,000.00 2,160.00 0.030 OH Tukang Batu @Rp. 42,500.00 1,275.00 0.003 OH Kepala Tukang Batu @Rp. 45,000.00 135.00 0.003 OH Mandor @Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 3,690.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m' PVC Waterstop lebar 200 mm 6897-2008 1.050 m' Waterstop lebar 200 mm @Rp. #N/A

0.070 OH Pekerja @Rp. 36,000.00 2,520.00 0.035 OH Tukang Batu @Rp. 42,500.00 1,487.50 0.004 OH Kepala Tukang Batu @Rp. 45,000.00 157.50 0.007 OH Mandor @Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 4,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m' PVC Waterstop lebar 230 mm - 320 mm 6897-2008 1.050 m' Waterstop lebar 230 mm - 320 mm @Rp. #N/A

0.080 OH Pekerja @Rp. 36,000.00 2,880.00 0.040 OH Tukang Batu @Rp. 42,500.00 1,700.00 0.004 OH Kepala Tukang Batu @Rp. 45,000.00 180.00 0.004 OH Mandor @Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 4,920.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 kg Pembesian dengan besi polos

Page 285: AHS 2008-Kota.xlsx

6897-2008 1.0500 kg Besi beton bulat @ Rp. #N/A 0.0150 kg Kawat beton @ Rp. #N/A 0.0070 org Tukang Besi @ Rp. 45,000.00 315.00 0.0007 org Kepala Tukang Besi @ Rp. 47,500.00 33.25 0.0070 org Pekerja @ Rp. 36,000.00 252.00 0.0004 org Mandor @ Rp. 40,000.00 14.00

JUMLAH ( BELUM PPN ) 614.25 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 kg Pembesian dengan besi ulir6897-2008 1.0500 kg Besi beton ulir @ Rp. 8,000.00

0.0150 kg Kawat beton @ Rp. #N/A 0.0070 org Tukang Besi @ Rp. 45,000.00 315.00 0.0007 org Kepala Tukang Besi @ Rp. 47,500.00 33.25 0.0070 org Pekerja @ Rp. 36,000.00 252.00 0.0004 org Mandor @ Rp. 40,000.00 14.00

JUMLAH ( BELUM PPN ) 614.25 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 kg Memasang kabel presstressed polos/strands 6897-2008 1.0500 kg Besi beton bulat @ Rp. #N/A

0.0100 kg Kawat beton @ Rp. #N/A 0.0050 org Tukang Besi @ Rp. 45,000.00 225.00 0.0005 org Kepala Tukang Besi @ Rp. 47,500.00 23.75 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0003 org Mandor @ Rp. 40,000.00 10.00

JUMLAH ( BELUM PPN ) 438.75 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 kg Memasang jaring kawat baja/wire mesh6897-2008 1.0200 kg Besi beton bulat @ Rp. #N/A

0.0050 kg Kawat beton @ Rp. #N/A 0.0025 org Tukang Besi @ Rp. 45,000.00 112.50 0.0025 org Kepala Tukang Besi @ Rp. 47,500.00 118.75 0.0025 org Pekerja @ Rp. 36,000.00 90.00 0.0001 org Mandor @ Rp. 40,000.00 5.00

JUMLAH ( BELUM PPN ) 326.25 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Cetakan beton / begisting memakai papan

2007 0.0170 Kyu meranti balok @ Rp. #N/A

0.0240 Papan cetakan @ Rp. #N/A 0.4000 kg Paku @ Rp. - 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala Tukang Kayu @ Rp. 50,000.00 2,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 33,850.00

m2

m3

m3

Page 286: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Cetakan beton / begisting memakai multiplek

2007 0.0170 Kyu meranti balok @ Rp. #N/A 0.3470 lbr Multiplek @ Rp. #N/A 0.4000 kg Paku @ Rp. - 0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala Tukang Kayu @ Rp. 50,000.00 2,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 33,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk pondasi6897-2008 0.0400 m3 Kayu bekisting @ Rp. #N/A

0.3000 kg Paku 2" - 5" @ Rp. #N/A 0.1000 ltr Minyak bekisting @ Rp. #N/A 0.5200 org Pekerja @ Rp. 36,000.00 18,720.00 0.2600 org Tukang Kayu @ Rp. 47,500.00 12,350.00 0.0260 org Kepala Tukang Kayu @ Rp. 50,000.00 1,300.00 0.0260 org Mandor @ Rp. 40,000.00 1,040.00

JUMLAH ( BELUM PPN ) 33,410.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk sloof6897-2008 0.0450 m3 Kayu bekisting @ Rp. #N/A

0.3000 kg Paku 2" - 5" @ Rp. #N/A 0.1000 ltr Minyak bekisting @ Rp. #N/A 0.5200 org Pekerja @ Rp. 36,000.00 18,720.00 0.2600 org Tukang Kayu @ Rp. 47,500.00 12,350.00 0.0260 org Kepala Tukang Kayu @ Rp. 50,000.00 1,300.00 0.0260 org Mandor @ Rp. 40,000.00 1,040.00

JUMLAH ( BELUM PPN ) 33,410.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk kolom6897-2008 0.0400 m3 Kayu bekisting @ Rp. #N/A

0.4000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 ltr Minyak bekisting @ Rp. #N/A 0.0150 m3 Balok kayu meranti @ Rp. #N/A 0.3500 lbr Multiplek 9 mm @ Rp. #N/A 2.0000 btg Kayu dolken @ Rp. 1,000,000.00 0.6600 org Pekerja @ Rp. 36,000.00 23,760.00 0.3300 org Tukang Kayu @ Rp. 47,500.00 15,675.00 0.0330 org Kepala Tukang Kayu @ Rp. 50,000.00 1,650.00 0.0330 org Mandor @ Rp. 40,000.00 1,320.00

JUMLAH ( BELUM PPN ) 42,405.00 JASA 10 %

m2

m3

Page 287: AHS 2008-Kota.xlsx

JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk balok6897-2008 0.0400 m3 Kayu bekisting @ Rp. #N/A

0.4000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 ltr Minyak bekisting @ Rp. #N/A 0.0180 m3 Balok kayu meranti @ Rp. #N/A 0.3500 lbr Multiplek 9 mm @ Rp. #N/A 2.0000 btg Kayu dolken @ Rp. 1,000,000.00 0.6600 org Pekerja @ Rp. 36,000.00 23,760.00 0.3300 org Tukang Kayu @ Rp. 47,500.00 15,675.00 0.0330 org Kepala Tukang Kayu @ Rp. 50,000.00 1,650.00 0.0330 org Mandor @ Rp. 40,000.00 1,320.00

JUMLAH ( BELUM PPN ) 42,405.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk lantai6897-2008 0.0400 m3 Kayu bekisting @ Rp. #N/A

0.4000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 ltr Minyak bekisting @ Rp. #N/A 0.0150 m3 Balok kayu meranti @ Rp. #N/A 0.3500 lbr Multiplek 9 mm @ Rp. #N/A 6.0000 btg Kayu dolken @ Rp. 1,000,000.00 0.6600 org Pekerja @ Rp. 36,000.00 23,760.00 0.3300 org Tukang Kayu @ Rp. 47,500.00 15,675.00 0.0330 org Kepala Tukang Kayu @ Rp. 50,000.00 1,650.00 0.0330 org Mandor @ Rp. 40,000.00 1,320.00

JUMLAH ( BELUM PPN ) 42,405.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk dinding6897-2008 0.0300 m3 Kayu bekisting @ Rp. #N/A

0.4000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 ltr Minyak bekisting @ Rp. #N/A 0.0200 m3 Balok kayu meranti @ Rp. #N/A 0.3500 lbr Multiplek 9 mm @ Rp. #N/A 3.0000 btg Kayu dolken @ Rp. 1,000,000.00 4.0000 bh Formite/penjaga jarak bekisting/spacer #N/A 0.6600 org Pekerja @ Rp. 36,000.00 23,760.00 0.3300 org Tukang Kayu @ Rp. 47,500.00 15,675.00 0.0330 org Kepala Tukang Kayu @ Rp. 50,000.00 1,650.00 0.0330 org Mandor @ Rp. 40,000.00 1,320.00

JUMLAH ( BELUM PPN ) 42,405.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk dinding6897-2008 0.0300 m3 Kayu bekisting @ Rp. #N/A

0.4000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 ltr Minyak bekisting @ Rp. #N/A 0.0200 m3 Balok kayu meranti @ Rp. #N/A

Page 288: AHS 2008-Kota.xlsx

0.3500 lbr Multiplek 9 mm @ Rp. #N/A 3.0000 btg Kayu dolken @ Rp. 1,000,000.00 4.0000 bh Formite/penjaga jarak bekisting/spacer #N/A 0.6600 org Pekerja @ Rp. 36,000.00 23,760.00 0.3300 org Tukang Kayu @ Rp. 47,500.00 15,675.00 0.0330 org Kepala Tukang Kayu @ Rp. 50,000.00 1,650.00 0.0330 org Mandor @ Rp. 40,000.00 1,320.00

JUMLAH ( BELUM PPN ) 42,405.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Begesting untuk tangga6897-2008 0.0300 m3 Kayu bekisting @ Rp. #N/A

0.4000 kg Paku 2" - 5" @ Rp. #N/A 0.1500 ltr Minyak bekisting @ Rp. #N/A 0.0150 m3 Balok kayu meranti @ Rp. #N/A 0.3500 lbr Multiplek 9 mm @ Rp. #N/A 2.0000 btg Kayu dolken @ Rp. 1,000,000.00 0.6600 org Pekerja @ Rp. 36,000.00 23,760.00 0.3300 org Tukang Kayu @ Rp. 47,500.00 15,675.00 0.0330 org Kepala Tukang Kayu @ Rp. 50,000.00 1,650.00 0.0330 org Mandor @ Rp. 40,000.00 1,320.00

JUMLAH ( BELUM PPN ) 42,405.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Jembatan untuk pengecoran beton6897-2008 0.0264 m3 Kayu bekisting @ Rp. #N/A

0.6000 kg Paku 2" - 5" @ Rp. #N/A 0.5000 btg Kayu dolken @ Rp. 1,000,000.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0500 org Tukang Kayu @ Rp. 47,500.00 2,375.00 0.0500 org Kepala Tukang Kayu @ Rp. 50,000.00 2,500.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 10,575.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.000 m' Kolom praktis beton bertulang (11 x 11) cm6897-2008 0.0020 m3 Kayu bekisting @Rp. #N/A

0.0100 kg Paku 2" - 5" @Rp. #N/A 3.0000 kg Besi beton bulat @Rp. #N/A 0.4500 kg Kawat beton @Rp. #N/A 4.0000 kg PC @Rp. #N/A 0.0060 m3 Pasir beton @Rp. #N/A 0.0090 m3 Batu split 1/2 @Rp. #N/A 0.1800 OH Pekerja @Rp. 36,000.00 6,480.00 0.0200 OH Tukang Batu @Rp. 42,500.00 850.00 0.0200 OH Tukang Kayu @Rp. 47,500.00 950.00 0.0200 OH Tukang Besi @Rp. 45,000.00 900.00 0.0060 OH Kepala Tukang Kayu @Rp. 50,000.00 300.00 0.0090 OH Mandor @Rp. 40,000.00 360.00

JUMLAH ( BELUM PPN ) 9,840.00 JASA 10 %

Page 289: AHS 2008-Kota.xlsx

JUMLAHDIBULATKAN

SNI 1.0000 m' Ring balok beton bertulang (10 x 15) cm 6897-2008 0.0030 m3 Kayu bekisting @Rp. #N/A

0.0200 kg Paku 2" - 5" @Rp. #N/A 3.6000 kg Besi beton bulat @Rp. #N/A 0.0500 kg Kawat beton @Rp. #N/A 5.5000 kg PC @Rp. #N/A 0.0090 m3 Pasir beton @Rp. #N/A 0.0150 m3 Batu split 1/2 @Rp. #N/A 0.2970 OH Pekerja @Rp. 36,000.00 10,692.00 0.0330 OH Tukang Batu @Rp. 42,500.00 1,402.50 0.0330 OH Tukang Kayu @Rp. 47,500.00 1,567.50 0.0330 OH Tukang Besi @Rp. 45,000.00 1,485.00 0.0100 OH Kepala Tukang Kayu @Rp. 50,000.00 500.00 0.0150 OH Mandor @Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,247.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan tiang pancang (40 x 40) cm, beton bertulang

2007 0.0190 Pasir urug @ Rp. #N/A

0.0940 Pasir beton @ Rp. #N/A

0.1500 Batu pecah 2/3 @ Rp. #N/A 60.5000 kg PC @ Rp. #N/A 45.0000 kg Besi beton @ Rp. - 0.9000 kg Kawat beton @ Rp. #N/A

0.0320 Kayu kruingi balok @ Rp. #N/A 0.1200 kg Paku reng @ Rp. #N/A 0.0900 ltr Minyak bekisting @ Rp. 5,000.00 0.2400 kg Plamur tembok @ Rp. #N/A 0.6700 org Tukang batu @ Rp. 42,500.00 28,475.00 0.0670 org Kepala tukang batu @ Rp. 45,000.00 3,015.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 69,490.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pembuatan tiang pancang (35 x 35) cm, beton bertulang

2007 0.0160 Pasir urug @ Rp. #N/A

0.0800 Pasir beton @ Rp. #N/A

0.1250 Batu pecah 2/3 @ Rp. #N/A 49.0000 kg PC @ Rp. #N/A 34.5000 kg Besi beton @ Rp. - 0.7000 kg Kawat beton @ Rp. #N/A

0.0270 Kayu kruingi balok @ Rp. #N/A 0.1200 kg Paku @ Rp. - 0.0900 ltr Minyak bekisting @ Rp. 5,000.00 0.2000 kg Plamur tembok @ Rp. #N/A 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kepala tukang batu @ Rp. 45,000.00 2,250.00

m1

m3

m3

m3

m3

m1

m3

m3

m3

m3

Page 290: AHS 2008-Kota.xlsx

0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 53,900.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN PELESTERAN

SNI 1.0000 Plesteran 1 Sm : 1 Kp : 1 Ps, tebal 15 mm

2837-2008 0.0090 Semen merah @ Rp. #N/A

0.0090 Kapur pasang @ Rp. 72,500.00

0.0090 Pasir pasang progo @ Rp. #N/A 0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.3600 org Pekerja @ Rp. 36,000.00 12,960.00 0.0180 org Mandor @ Rp. 40,000.00 720.00

JUMLAH ( BELUM PPN ) 19,320.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Sm : 1 Kp : 2 Ps, tebal 15 mm

2837-2008 0.0070 Semen merah @ Rp. #N/A

0.0070 Kapur pasang @ Rp. 72,500.00

0.0150 Pasir pasang progo @ Rp. #N/A 0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.3600 org Pekerja @ Rp. 36,000.00 12,960.00 0.0180 org Mandor @ Rp. 40,000.00 720.00

JUMLAH ( BELUM PPN ) 19,320.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Sm : 1 Kp : 2 Ps, tebal 20 mm

2837-2008 0.0090 Semen merah @ Rp. #N/A

0.0090 Kapur pasang @ Rp. 72,500.00

0.0180 Pasir pasang progo @ Rp. #N/A 0.2200 org Tukang Batu @ Rp. 42,500.00 9,350.00 0.0220 org Kepala Tukang Batu @ Rp. 45,000.00 990.00 0.4400 org Pekerja @ Rp. 36,000.00 15,840.00 0.0220 org Mandor @ Rp. 40,000.00 880.00

JUMLAH ( BELUM PPN ) 27,060.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 1/2 Kp : 3 Ps, tebal 15 mm2837-2008 5.7600 kg PC @ Rp. #N/A

0.0030 Kapur pasang @ Rp. 72,500.00

0.0130 Pasir pasang progo @ Rp. #N/A

m2

m3

m3

m3

m2

m3

m3

m3

m2

m3

m3

m3

m2

m3

m3

Page 291: AHS 2008-Kota.xlsx

0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.3600 org Pekerja @ Rp. 36,000.00 12,960.00 0.0180 org Mandor @ Rp. 40,000.00 720.00

JUMLAH ( BELUM TERMASUK PPN ) 19,320.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 2 Kp : 8 Ps, tebal 15 mm2837-2008 3.0000 kg PC @ Rp. #N/A

0.0050 Kapur pasang @ Rp. 72,500.00

0.0200 Pasir pasang progo @ Rp. #N/A 0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.3600 org Pekerja @ Rp. 36,000.00 12,960.00 0.0180 org Mandor @ Rp. 40,000.00 720.00

JUMLAH ( BELUM TERMASUK PPN ) 19,320.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 1 Ps, tebal 15 mm2837-2008 15.5040 kg PC @ Rp. #N/A

0.0160 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM TERMASUK PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 2 Ps, tebal 15 mm2837-2008 10.2240 kg PC @ Rp. #N/A

0.0200 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM TERMASUK PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 3 Ps, tebal 15 mm2837-2008 7.7760 kg PC @ Rp. #N/A

0.0230 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %

m2

m3

m3

m2

m3

m2

m3

m2

m3

Page 292: AHS 2008-Kota.xlsx

JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 4 Ps, tebal 15 mm2837-2008 6.2400 kg PC @ Rp. #N/A

0.0240 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 5 Ps, tebal 15 mm2837-2008 5.1840 kg PC @ Rp. #N/A

0.0260 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 6 Ps, tebal 15 mm2837-2008 4.4160 kg PC @ Rp. #N/A

0.0270 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 7 Ps, tebal 15 mm2837-2008 3.9360 kg PC @ Rp. #N/A

0.0280 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 8 Ps, tebal 15 mm2837-2008 3.4560 kg PC @ Rp. #N/A

0.0290 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 293: AHS 2008-Kota.xlsx

0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran berapen 1 Pc : 5 Ps tebal 15mm2837-2008 5.1840 kg PC @ Rp. #N/A

0.0260 Pasir pasang progo @ Rp. #N/A 0.0750 org Tukang Batu @ Rp. 42,500.00 3,187.50 0.0075 org Kepala Tukang Batu @ Rp. 45,000.00 337.50 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 9,225.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran sponengan 1 Pc : 2 Ps lebar 10mm2837-2008 0.5000 kg PC @ Rp. #N/A

0.0130 Pasir pasang progo @ Rp. #N/A 0.4000 org Tukang Batu @ Rp. 42,500.00 17,000.00 0.0400 org Kepala Tukang Batu @ Rp. 45,000.00 1,800.00 0.0800 org Pekerja @ Rp. 36,000.00 2,880.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 21,840.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 2 Ps, tebal 20 mm2837-2008 13.6320 kg PC @ Rp. #N/A

0.0270 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0220 org Mandor @ Rp. 40,000.00 880.00

JUMLAH ( BELUM PPN ) 24,680.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 3 Ps, tebal 20 mm2837-2008 10.3680 kg PC @ Rp. #N/A

0.0310 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 19,280.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m2

m3

m2

m3

Page 294: AHS 2008-Kota.xlsx

SNI 1.0000 Plesteran 1 Pc : 4 Ps, tebal 20 mm2837-2008 8.3200 kg PC @ Rp. #N/A

0.0320 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0220 org Mandor @ Rp. 40,000.00 880.00

JUMLAH ( BELUM PPN ) 24,680.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 5 Ps, tebal 20 mm2837-2008 6.9120 kg PC @ Rp. #N/A

0.0350 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0220 org Mandor @ Rp. 40,000.00 880.00

JUMLAH ( BELUM PPN ) 24,680.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran 1 Pc : 6 Ps, tebal 20 mm2837-2008 5.8880 kg PC @ Rp. #N/A

0.0360 Pasir pasang progo @ Rp. #N/A 0.2000 org Tukang Batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0220 org Mandor @ Rp. 40,000.00 880.00

JUMLAH ( BELUM PPN ) 24,680.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran granit 1 Pc : 2 Batu granit, tebal 10 mm2837-2008 10.0000 kg PC @ Rp. #N/A

15.0000 kg Batu granit @ Rp. #N/A 0.2250 org Tukang Batu @ Rp. 42,500.00 9,562.50 0.0225 org Kepala Tukang Batu @ Rp. 45,000.00 1,012.50 0.4500 org Pekerja @ Rp. 36,000.00 16,200.00 0.0225 org Mandor @ Rp. 40,000.00 900.00

JUMLAH ( BELUM PPN ) 27,675.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran traso 1 Pc : 2 Batu traso, tebal 10 mm2837-2008 10.0000 kg PC @ Rp. #N/A

15.0000 kg Batu granit @ Rp. #N/A 0.2250 org Tukang Batu @ Rp. 42,500.00 9,562.50 0.0225 org Kepala Tukang Batu @ Rp. 45,000.00 1,012.50 0.4500 org Pekerja @ Rp. 36,000.00 16,200.00

m2

m3

m2

m3

m2

m3

m2

m2

Page 295: AHS 2008-Kota.xlsx

0.0225 org Mandor @ Rp. 40,000.00 900.00 JUMLAH ( BELUM PPN ) 27,675.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Finishing siar pas. Bata merah (=20m')2837-2008 3.1080 kg PC @ Rp. #N/A

0.0750 org Tukang Batu @ Rp. 42,500.00 3,187.50 0.0075 org Kepala Tukang Batu @ Rp. 45,000.00 337.50 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 9,225.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Finishing siar dinding conblock expose (=8m')2837-2008 1.6000 kg PC @ Rp. #N/A

0.0350 org Tukang Batu @ Rp. 42,500.00 1,487.50 0.0035 org Kepala Tukang Batu @ Rp. 45,000.00 157.50 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0035 org Mandor @ Rp. 40,000.00 140.00

JUMLAH ( BELUM PPN ) 4,305.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Finishing siar pas. Batu kali 1 pc : 2 ps2837-2008 6.3400 kg PC @ Rp. #N/A

0.0120 Pasir pasang progo @ Rp. #N/A 0.1500 org Tukang Batu @ Rp. 42,500.00 6,375.00 0.0150 org Kepala Tukang Batu @ Rp. 45,000.00 675.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 18,450.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran Ciprat, 1 Pc : 2 Ps2837-2008 4.3200 kg PC @ Rp. #N/A

0.0060 Pasir pasang progo @ Rp. #N/A 0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Acian2837-2008 3.2500 kg PC @ Rp. #N/A

0.1000 org Tukang Batu @ Rp. 42,500.00 4,250.00

m2

m2

m2

m3

m2

m3

m2

Page 296: AHS 2008-Kota.xlsx

0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran batu kali 1pc:1/2kp:5ps tebal 10 mm2007 5.1000 kg PC @ Rp. #N/A

0.0014 Kapur pasang @ Rp. 72,500.00

0.0136 Pasir pasang @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran batu kali 1pc:3ps2007 8.1600 kg PC @ Rp. #N/A

0.0194 Pasir pasang @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Plesteran batu kali 1pc:4ps2007 6.5110 kg PC @ Rp. #N/A

0.0209 Pasir pasang @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN PASANG TEGEL

Pasang tegel abu-abu, warna dan teraso

SNI 1.0000 Pasang tegel abu-abu 40/407395-2008 6.6300 bh Tegel abu-abu uk. 40/40 @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 0.1250 org Tukang Batu @ Rp. 42,500.00 5,312.50

m2

m3

m3

m2

m3

m2

m3

m2

m3

Page 297: AHS 2008-Kota.xlsx

0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 15,375.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel abu-abu 30/307395-2008 11.8700 bh Tegel abu-abu uk. 30/30 @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 0.1300 org Tukang Batu @ Rp. 42,500.00 5,525.00 0.0130 org Kepala Tukang Batu @ Rp. 45,000.00 585.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 15,990.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel teraso 40/407395-2008 6.6300 bh Tegel teraso uk. 40/40 @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.3000 kg Semen warna @ Rp. 6,000.00 0.1250 org Tukang Batu @ Rp. 42,500.00 5,312.50 0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 15,375.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel teraso 30/307395-2008 11.8700 bh Tegel teraso uk. 40/40 @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.1300 org Tukang Batu @ Rp. 42,500.00 5,525.00 0.0130 org Kepala Tukang Batu @ Rp. 45,000.00 585.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 15,990.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel abu-abu 20/207395-2008 26.5000 bh Tegel abu-abu uk. 20/20 @ Rp. #N/A

10.4000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 0.1350 org Tukang Batu @ Rp. 42,500.00 5,737.50 0.0135 org Kepala Tukang Batu @ Rp. 45,000.00 607.50

m2

m3

m2

m3

m2

m3

m2

m3

Page 298: AHS 2008-Kota.xlsx

0.2700 org Pekerja @ Rp. 36,000.00 9,720.00 0.0135 org Mandor @ Rp. 40,000.00 540.00

JUMLAH ( BELUM PPN ) 16,605.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel warna 40/407395-2008 6.6300 bh Tegel warna uk. 40/40 @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.3000 kg Semen warna @ Rp. 6,000.00 0.1250 org Tukang Batu @ Rp. 42,500.00 5,312.50 0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 15,375.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel warna 30/307395-2008 11.8700 bh Tegel warna uk. 30/30 @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.1300 org Tukang Batu @ Rp. 42,500.00 5,525.00 0.0130 org Kepala Tukang Batu @ Rp. 45,000.00 585.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 15,990.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel warna 20/207395-2008 26.5000 bh Tegel warna uk. 20/20 @ Rp. #N/A

10.4000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.6200 kg Semen warna @ Rp. 6,000.00 0.1350 org Tukang Batu @ Rp. 42,500.00 5,737.50 0.0135 org Kepala Tukang Batu @ Rp. 45,000.00 607.50 0.2700 org Pekerja @ Rp. 36,000.00 9,720.00 0.0135 org Mandor @ Rp. 40,000.00 540.00

JUMLAH ( BELUM PPN ) 16,605.00 JASA 10 %JUMLAHDIBULATKAN

Pasang ubin granit, teralux dan marmer

SNI 1.0000 Pasang lantai ubin granit 40/407395-2008 6.6300 bh Ubin granit uk. 40/40 @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A

m2

m3

m2

m3

m2

m3

m2

m3

Page 299: AHS 2008-Kota.xlsx

1.3000 kg Semen warna @ Rp. 6,000.00 0.1250 org Tukang Batu @ Rp. 42,500.00 5,312.50 0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 15,375.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai ubin granit 30/307395-2008 11.8700 bh Ubin granit uk. 30/30 @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.1300 org Tukang Batu @ Rp. 42,500.00 5,525.00 0.0130 org Kepala Tukang Batu @ Rp. 45,000.00 585.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 15,990.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai ubin teralux 40/407395-2008 6.6300 bh Ubin teralux uk. 40/40 @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.3000 kg Semen warna @ Rp. 6,000.00 0.1250 org Tukang Batu @ Rp. 42,500.00 5,312.50 0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 15,375.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai ubin teralux 30/307395-2008 11.8700 bh Ubin teralux uk. 30/30 @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.1300 org Tukang Batu @ Rp. 42,500.00 5,525.00 0.0130 org Kepala Tukang Batu @ Rp. 45,000.00 585.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 15,990.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai ubin teralux marmer 60/607395-2008 3.1000 bh Ubin teralux marmer uk. 60/60 @ Rp. #N/A

9.6000 kg PC @ Rp. #N/A

m2

m3

m2

m3

m2

m3

m2

Page 300: AHS 2008-Kota.xlsx

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.1200 org Tukang Batu @ Rp. 42,500.00 5,100.00 0.0120 org Kepala Tukang Batu @ Rp. 45,000.00 540.00 0.2400 org Pekerja @ Rp. 36,000.00 8,640.00 0.0120 org Mandor @ Rp. 40,000.00 480.00

JUMLAH ( BELUM PPN ) 14,760.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai ubin teralux marmer 40/407395-2008 6.6300 bh Ubin teralux marmer uk. 40/40 @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.3000 kg Semen warna @ Rp. 6,000.00 0.1250 org Tukang Batu @ Rp. 42,500.00 5,312.50 0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0125 org Mandor @ Rp. 40,000.00 500.00

JUMLAH ( BELUM PPN ) 15,375.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai ubin teralux marmer 30/307395-2008 11.8700 bh Ubin teralux marmer uk. 30/30 @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.1300 org Tukang Batu @ Rp. 42,500.00 5,525.00 0.0130 org Kepala Tukang Batu @ Rp. 45,000.00 585.00 0.2600 org Pekerja @ Rp. 36,000.00 9,360.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 15,990.00 JASA 10 %JUMLAHDIBULATKAN

Pasang plint tegel dan teraso

SNI 1.0000 Pasang plint ubin PC abu-abu ukuran 15 x 20 cm7395-2008 5.3000 bh Plint ubin 15 x 20 cm @ Rp. #N/A

1.6500 kg PC @ Rp. #N/A

0.0040 Pasir pasang progo @ Rp. #N/A 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC abu-abu ukuran 10 x 30 cm

m3

m2

m3

m2

m3

m1

m3

m1

Page 301: AHS 2008-Kota.xlsx

7395-2008 3.5300 bh Plint ubin 10 x 30 cm @ Rp. #N/A 1.2400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC abu-abu ukuran 10 x 40 cm7395-2008 2.6500 bh Plint ubin 10 x 40 cm @ Rp. #N/A

1.2400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC warna ukuran 10 x 20 cm7395-2008 5.3000 bh Plint ubin pc warna 10 x 20 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC warna ukuran 10 x 30 cm7395-2008 3.5300 bh Plint ubin pc warna 10 x 30 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin PC warna ukuran 10 x 40 cm7395-2008 2.6500 bh Plint ubin pc warna 10 x 40 cm @ Rp. #N/A

m3

m1

m3

m1

m3

m1

m3

m1

Page 302: AHS 2008-Kota.xlsx

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin traso ukuran 10 x 30 cm7395-2008 3.5300 bh Plint ubin traso 10 x 30 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin traso ukuran 10 x 40 cm7395-2008 2.6500 bh Plint ubin traso 10 x 40 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

Pasang plint ubin dan marmer

SNI 1.0000 Pasang plint ubin granit ukuran 10 x 30 cm7395-2008 3.5300 bh Plint ubin granit 10 x 30 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

m3

m1

m3

m1

m3

m1

m3

Page 303: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang plint ubin granit ukuran 10 x 40 cm7395-2008 2.6500 bh Plint ubin granit 10 x 40 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin teralux kerang ukuran 10 x 40 cm7395-2008 2.6500 bh Plint ubin teralux kerang 10 x 40 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin teralux kerang ukuran 10 x 30 cm7395-2008 3.5300 bh Plint ubin teralux kerang 10 x 30 cm @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin teralux marmer ukuran 10 x 60 cm7395-2008 1.7000 bh Plint ubin teralux marmer 10 x 60 cm@ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAH

m1

m3

m1

m3

m1

m3

m1

m3

Page 304: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasang plint ubin teralux marmer ukuran 10 x 40 cm7395-2008 2.6500 bh Plint ubin teralux marmer 10 x 40 cm@ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint ubin teralux marmer ukuran 10 x 30 cm7395-2008 3.5300 bh Plint ubin teralux marmer 10 x 30 cm@ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.0900 oh Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 oh Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 oh Pekerja @ Rp. 36,000.00 3,240.00 0.0045 oh Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai teraso cor ditempat tebal 3 cm7395-2008 0.0360 m3 Bahan teraso cor @ Rp. #N/A

0.1800 oh Tukang Batu @ Rp. 42,500.00 7,650.00 0.0180 oh Kepala Tukang Batu @ Rp. 45,000.00 810.00 0.3600 oh Pekerja @ Rp. 36,000.00 12,960.00 0.0180 oh Mandor @ Rp. 40,000.00 720.00

JUMLAH ( BELUM TERMASUK PPN ) 22,140.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN KERAMIK

SNI 1.0000 Pasang lantai keramik artistik uk. 10 x 20 cm7395-2008 53.0000 bh Ubin keramik artistik @ Rp. #N/A

8.1900 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 2.7500 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAH

m1

m3

m1

m3

m1

m2

m3

Page 305: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasang lantai keramik artistik uk. 10 x 10 cm atau 5 x 20 cm7395-2008 106.0000 bh Ubin keramik artistik @ Rp. #N/A

8.1900 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 3.2000 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang ubin porselin uk. 11 x 11 cm7395-2008 86.0000 bh Tegel porselin @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.5000 org Tukang Batu @ Rp. 42,500.00 21,250.00 0.0500 org Kepala Tukang Batu @ Rp. 45,000.00 2,250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 29,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang ubin porselin uk. 10 x 20 cm7395-2008 53.0000 bh Tegel porselin @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 2.7500 kg Semen warna @ Rp. 6,000.00 0.4500 org Tukang Batu @ Rp. 42,500.00 19,125.00 0.0450 org Kepala Tukang Batu @ Rp. 45,000.00 2,025.00 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

JUMLAH ( BELUM PPN ) 55,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang ubin porselin uk. 20 x 20 cm7395-2008 26.5000 bh Tegel porselin @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 1.9400 kg Semen warna @ Rp. 6,000.00 0.4500 org Tukang Batu @ Rp. 42,500.00 19,125.00 0.0450 org Kepala Tukang Batu @ Rp. 45,000.00 2,025.00 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

JUMLAH ( BELUM PPN ) 55,350.00 JASA 10 %

m2

m3

m2

m3

m2

m3

m2

m3

Page 306: AHS 2008-Kota.xlsx

JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel keramik uk. 33/337395-2008 10.0000 bh Tegel keramik (std) @ Rp. #N/A

8.1900 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.6200 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel keramik uk. 30/307395-2008 11.8700 bh Tegel keramik (std) @ Rp. #N/A

10.0000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.5000 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel keramik uk. 20/207395-2008 26.5000 bh Tegel keramik (std) @ Rp. #N/A

10.4000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 1.6200 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang tegel keramik uk. 10 x 33 cm (variasi/border)7395-2008 33.0000 bh Tegel keramik (std) @ Rp. #N/A

9.8000 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 4.3700 kg Semen warna @ Rp. 6,000.00 0.5250 org Tukang Batu @ Rp. 42,500.00 22,312.50 0.0525 org Kepala Tukang Batu @ Rp. 45,000.00 2,362.50 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00 0.0525 org Mandor @ Rp. 40,000.00 2,100.00

JUMLAH ( BELUM PPN ) 64,575.00

m2

m3

m2

m3

m2

m3

m2

m3

Page 307: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai mozaik uk. 30 x 30 cm, camp. 1pc : 3ps7395-2008 11.8700 bh Tegel keramik (std) @ Rp. #N/A

14.1500 kg PC @ Rp. #N/A

0.0390 Pasir pasang progo @ Rp. #N/A 2.0000 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint keramik ukuran 10 x 20 cm7395-2008 5.3000 bh Plint keramik artistik @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.0250 kg Semen warna @ Rp. 6,000.00 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint keramik ukuran 10 x 10 cm7395-2008 10.6000 bh Plint keramik artistik @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.0500 kg Semen warna @ Rp. 6,000.00 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

JUMLAH ( BELUM TERMASUK PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint keramik 5 x 20 cm7395-2008 5.3000 bh Plint keramik artistik @ Rp. #N/A

0.5700 kg PC @ Rp. #N/A

0.0015 Pasir pasang progo @ Rp. #N/A 0.0130 kg Semen warna @ Rp. 6,000.00 0.0900 org Tukang Batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala Tukang Batu @ Rp. 45,000.00 405.00 0.0900 org Pekerja @ Rp. 36,000.00 3,240.00 0.0045 org Mandor @ Rp. 40,000.00 180.00

m2

m3

m1

m3

m1

m3

m1

m3

Page 308: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 7,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang plint internal cove artistik 5 x 5 x 20 cm7395-2008 5.3000 bh Internal cove @ Rp. #N/A

1.1400 kg PC @ Rp. #N/A

0.0030 Pasir pasang progo @ Rp. #N/A 0.1000 kg Semen warna @ Rp. 6,000.00 0.7500 org Tukang Batu @ Rp. 42,500.00 31,875.00 0.0750 org Kepala Tukang Batu @ Rp. 45,000.00 3,375.00 0.7500 org Pekerja @ Rp. 36,000.00 27,000.00 0.0375 org Mandor @ Rp. 40,000.00 1,500.00

JUMLAH ( BELUM PPN ) 63,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai marmer uk. 100 x 100 cm7395-2008 1.0600 bh Marmer @ Rp. #N/A

8.1900 kg PC @ Rp. #N/A

0.0450 Pasir pasang progo @ Rp. #N/A 0.6500 kg Semen warna @ Rp. 6,000.00 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang lantai karpet7395-2008 1.0500 m2 Karpet @ Rp. #N/A

0.3500 kg Lem @ Rp. #N/A 0.1700 org Tukang Kayu @ Rp. 47,500.00 8,075.00 0.0170 org Kepala Tukang Kayu @ Rp. 50,000.00 850.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 15,385.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang Underlayer / Pelapis bawah karpet7395-2008 1.0500 m2 Underlayer/Rubber corrugated @ Rp. #N/A

0.3500 kg Lem @ Rp. #N/A 0.1200 org Tukang Kayu @ Rp. 47,500.00 5,700.00 0.0120 org Kepala Tukang Kayu @ Rp. 50,000.00 600.00 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 10,860.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

Page 309: AHS 2008-Kota.xlsx

SNI 1.0000 m2 Pasang Parquet kayu7395-2008 1.0500 m2 Parquet @ Rp. #N/A

0.6000 kg Lem @ Rp. #N/A 0.3500 org Tukang Kayu @ Rp. 47,500.00 16,625.00 0.0350 org Kepala Tukang Kayu @ Rp. 50,000.00 1,750.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 44,975.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang lantai kayu (gymfloor)7395-2008 1.0500 m2 Gymfloor @ Rp. #N/A

0.6000 kg Lem @ Rp. #N/A 0.3500 org Tukang Kayu @ Rp. 47,500.00 16,625.00 0.0350 org Kepala Tukang Kayu @ Rp. 50,000.00 1,750.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 44,975.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang keramik dinding artistik 10 x 20 cm7395-2008 53.0000 bh Keramik artistik @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 2.7500 kg Semen warna @ Rp. 6,000.00 0.4500 org Tukang Batu @ Rp. 42,500.00 19,125.00 0.0450 org Kepala Tukang Batu @ Rp. 45,000.00 2,025.00 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

JUMLAH ( BELUM PPN ) 55,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang keramik dinding artistik 5 x 20 cm7395-2008 106.0000 bh Keramik artistik @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 2.7500 kg Semen warna @ Rp. 6,000.00 0.4500 org Tukang Batu @ Rp. 42,500.00 19,125.00 0.0450 org Kepala Tukang Batu @ Rp. 45,000.00 2,025.00 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

JUMLAH ( BELUM PPN ) 55,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang keramik dinding 10 x 20 cm7395-2008 53.0000 bh Keramik 10 x 20 cm @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

m2

m3

m2

m3

m2

Page 310: AHS 2008-Kota.xlsx

0.0180 Pasir pasang progo @ Rp. #N/A 2.7500 kg Semen warna @ Rp. 6,000.00 0.4500 org Tukang Batu @ Rp. 42,500.00 19,125.00 0.0450 org Kepala Tukang Batu @ Rp. 45,000.00 2,025.00 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

JUMLAH ( BELUM PPN ) 55,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang keramik dinding 20 x 20 cm7395-2008 26.5000 bh Keramik 20 x 20 cm @ Rp. #N/A

9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang progo @ Rp. #N/A 1.9400 kg Semen warna @ Rp. 6,000.00 0.4500 org Tukang Batu @ Rp. 42,500.00 19,125.00 0.0450 org Kepala Tukang Batu @ Rp. 45,000.00 2,025.00 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.0450 org Mandor @ Rp. 40,000.00 1,800.00

JUMLAH ( BELUM PPN ) 55,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang keramik dinding 20/25

2007 1.0000 Tegel keramik 20/25 @ Rp. #N/A 9.3000 kg PC @ Rp. #N/A

0.0180 Pasir pasang @ Rp. #N/A 1.5000 kg Semen putih @ Rp. 52,500.00 0.6500 org Tukang batu @ Rp. 42,500.00 27,625.00 0.0650 org Kepala Tukang Batu @ Rp. 45,000.00 2,925.00 0.3200 org Pekerja @ Rp. 36,000.00 11,520.00 0.0160 org Mandor @ Rp. 40,000.00 640.00

JUMLAH ( BELUM PPN ) 42,710.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang keramik stepnosing granito 5/302007 3.6000 bh Stepnosing granito @ Rp. 9,350.00

0.4080 kg PC @ Rp. #N/A 0.0009 Pasir @ Rp. #N/A 0.0600 kg Semen warna @ Rp. 6,000.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding marmer uk. 100 x 100 cm7395-2008 1.0600 m2 Marmer @ Rp. #N/A

m3

m2

m3

m2

m2

m3

m1

m3

m2

Page 311: AHS 2008-Kota.xlsx

3.0030 kg Paku 2" - 5" #N/A 12.4400 kg PC @ Rp. #N/A

0.0250 Pasir pasang progo @ Rp. #N/A 0.6500 kg Semen warna @ Rp. 6,000.00 0.6500 org Tukang Batu @ Rp. 42,500.00 27,625.00 0.0650 org Kepala Tukang Batu @ Rp. 45,000.00 2,925.00 1.3000 org Pekerja @ Rp. 36,000.00 46,800.00 0.0650 org Mandor @ Rp. 40,000.00 2,600.00

JUMLAH ( BELUM PPN ) 79,950.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding bata pelapis uk. 3 x 7 x 24 cm7395-2008 63.0000 bh Bata pelapis dinding @ Rp. #N/A

12.4400 kg PC @ Rp. #N/A

0.0250 Pasir pasang progo @ Rp. #N/A 2.7500 kg Semen warna @ Rp. 6,000.00 0.5000 org Tukang Batu @ Rp. 42,500.00 21,250.00 0.0500 org Kepala Tukang Batu @ Rp. 45,000.00 2,250.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 61,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding batu paras7395-2008 1.1000 m2 Batu paras @ Rp. #N/A

11.7500 kg PC @ Rp. #N/A

0.0350 Pasir pasang progo @ Rp. #N/A 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang dinding batu tempel hitam7395-2008 1.1000 m2 Batu tempel @ Rp. #N/A

11.7500 kg PC @ Rp. #N/A

0.0350 Pasir pasang progo @ Rp. #N/A 0.3500 org Tukang Batu @ Rp. 42,500.00 14,875.00 0.0350 org Kepala Tukang Batu @ Rp. 45,000.00 1,575.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 43,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lantai vinyl uk. 30 x 30 cm kls 17395-2008 11.8700 bh Vinyl @ Rp. #N/A

m3

m2

m3

m2

m3

m2

m3

m2

Page 312: AHS 2008-Kota.xlsx

0.3500 kg Lem vinyl @ Rp. #N/A 0.1500 org Tukang Kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala Tukang Kayu @ Rp. 50,000.00 750.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 13,575.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang wallpaper lebar 50 cm7395-2008 2.2000 m2 Wallpaper @ Rp. #N/A

0.2500 kg Lem @ Rp. #N/A 0.1750 org Tukang Kayu @ Rp. 47,500.00 8,312.50 0.0170 org Kepala Tukang Kayu @ Rp. 50,000.00 850.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0018 org Mandor @ Rp. 40,000.00 70.00

JUMLAH ( BELUM PPN ) 21,832.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang floor hardener7395-2008 5.0000 kg Floor hardener @ Rp. #N/A

0.1200 org Tukang Kayu @ Rp. 47,500.00 5,700.00 0.0120 org Kepala Tukang Kayu @ Rp. 50,000.00 600.00 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 10,860.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m1 Pasang plint vinyl karet uk. 15 x 30 cm dengan perekat7395-2008 1.7600 bh Vinyl karet @ Rp. #N/A

0.0800 kg Lem vinyl @ Rp. #N/A 0.0800 org Tukang Kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala Tukang Kayu @ Rp. 50,000.00 400.00 0.0800 org Pekerja @ Rp. 36,000.00 2,880.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 7,240.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m1 Pasang plint kayu klas II tebal 2cm, lebar 10cm7395-2008 0.0030 m3 Papan kayu klas II @ Rp. #N/A

0.0500 kg Paku/skrup 5cm @ Rp. #N/A 0.1200 org Tukang Kayu @ Rp. 47,500.00 5,700.00 0.0120 org Kepala Tukang Kayu @ Rp. 50,000.00 600.00 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 10,860.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

Page 313: AHS 2008-Kota.xlsx

PEKERJAAN CONBLOCK/PAVING BLOCK

SNI 1.0000 Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe uni, segi-empat abu-abu 8 cm, K-300

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-empat abu-abu 6 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-empat abu-abu 8 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-enam abu-abu 6 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

Page 314: AHS 2008-Kota.xlsx

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-enam abu-abu 8 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-empat, uni, segi-enam rawna 8 cm, K-400

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe uni, segi-empat warna 8 cm, K-300

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-empat warna 6 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

Page 315: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-empat warna 8 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-enam warna 6 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang conblock tipe segi-enam warna 8 cm, K-200

2007 1.0000 Conblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang grassblock bulat tebal 10 cm

2007 1.0000 Grassblock @ Rp. #N/A

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang grassblock tebal 10 cm

2007 1.0000 Grassblock @ Rp. #N/A

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

Page 316: AHS 2008-Kota.xlsx

0.0500 Pasir urug @ Rp. #N/A 0.2500 org Tukang batu @ Rp. 42,500.00 10,625.00 0.0250 org Kepala Tukang Batu @ Rp. 45,000.00 1,125.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 30,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 3.0000 Bronjong kawat galvanis2007 A Penganyaman

70.0000 kg Kawat galvanis @ Rp. 7,755.00 2.5000 org Penganyaman @ Rp. #N/A 2.0000 org Pekerja @ Rp. 36,000.00 0.0800 org Mandor @ Rp. 40,000.00

B Pengisian #N/A

3.0000 Batu kali (hitam) @ Rp. #N/A #N/A 4.5000 org Pekerja @ Rp. 36,000.00 162,000.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) #N/A

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang buis beton dia. 80 cm2007 1.0000 bh Buis beton dia. 80 cm @ Rp. #N/A

0.1250 org Tukang batu @ Rp. 42,500.00 5,312.50 0.0125 org Kepala Tukang Batu @ Rp. 45,000.00 562.50 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00

JUMLAH ( BELUM PPN ) 14,875.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langsiran batu kali2007 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00

0.0200 org Mandor @ Rp. 40,000.00 800.00 1.0000 hr Sewa gerobag @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langsiran kerikil2007 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00

0.0120 org Mandor @ Rp. 40,000.00 480.00 1.0000 hr Sewa gerobag @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langsiran pasir

m3

m3

m3

TIAP 1 M3

m3

m3

m3

Page 317: AHS 2008-Kota.xlsx

2007 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0050 org Mandor @ Rp. 40,000.00 200.00 1.0000 hr Sewa gerobag @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

PEKERJAAN KAYU

SNI 1.0000 Pasang konstruksi kuda-kuda Exspose Kayu jati klas I

3434-2008 1.2000 Kayu jati balok klas 1 @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 20.1000 org Tukang Kayu @ Rp. 47,500.00 954,750.00 2.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 100,500.00 6.7000 org Pekerja @ Rp. 36,000.00 241,200.00 0.3350 org Mandor @ Rp. 40,000.00 13,400.00

JUMLAH ( BELUM PPN ) 1,309,850.00 JASA 10 %JUMLAHDIBULATKAN

Pasang kuda-kuda konvensional

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional Kayu jati klas I

3434-2008 1.1000 Kayu jati balok klas 1 @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional Kayu jati klas II

3434-2008 1.1000 Kayu jati balok klas 2 @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional Kayu jati klas III

3434-2008 1.1000 Kayu jati balok klas 3 @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A

m3

m3

m3

m3

m3

m3

m3

m3

Page 318: AHS 2008-Kota.xlsx

12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional Kayu kamper

3434-2008 1.1000 Kayu kamper balok @ Rp. 4,750,000.00 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional Kayu bengkirai

3434-2008 1.1000 Kayu bengkirai balok @ Rp. 5,750,000.00 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional Kayu kruing

3434-2008 1.1000 Kayu kruing balok @ Rp. 4,350,000.00 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang konstruksi kuda-kuda konvensional kayu glugu

3434-2008 1.1000 Kayu glugu @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 5.6000 kg Paku 12 cm @ Rp. #N/A 12.0000 org Tukang Kayu @ Rp. 47,500.00 570,000.00 1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00

m3

m3

m3

m3

m3

m3

m3

m3

Page 319: AHS 2008-Kota.xlsx

0.2000 org Mandor @ Rp. 40,000.00 8,000.00 JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

Pasang gording

SNI 1.0000 Pasang gording Kayu jati klas II

3434-2008 1.1000 Kayu jati balok klas 2 @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 3.0000 kg Paku 12 cm @ Rp. #N/A 7.2000 org Tukang Kayu @ Rp. 47,500.00 342,000.00 0.7200 org Kepala Tukang Kayu @ Rp. 50,000.00 36,000.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM PPN ) 469,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang gording Kayu jati klas III

3434-2008 1.1000 Kayu jati balok klas 3 @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 3.0000 kg Paku 12 cm @ Rp. #N/A 7.2000 org Tukang Kayu @ Rp. 47,500.00 342,000.00 0.7200 org Kepala Tukang Kayu @ Rp. 50,000.00 36,000.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM PPN ) 469,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang gording Kayu kamper

3434-2008 1.1000 Kayu kamper balok @ Rp. 4,750,000.00 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 3.0000 kg Paku 12 cm @ Rp. #N/A 7.2000 org Tukang Kayu @ Rp. 47,500.00 342,000.00 0.7200 org Kepala Tukang Kayu @ Rp. 50,000.00 36,000.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM PPN ) 469,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang gording Kayu bengkirai

3434-2008 1.1000 Kayu bengkirai balok @ Rp. 5,750,000.00 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 3.0000 kg Paku 12 cm @ Rp. #N/A 7.2000 org Tukang Kayu @ Rp. 47,500.00 342,000.00 0.7200 org Kepala Tukang Kayu @ Rp. 50,000.00 36,000.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

m3

m3

m3

m3

m3

m3

m3

m3

Page 320: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 469,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang gording Kayu kruing

3434-2008 1.1000 Kayu kruing balok @ Rp. 4,350,000.00 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 3.0000 kg Paku 12 cm @ Rp. #N/A 7.2000 org Tukang Kayu @ Rp. 47,500.00 342,000.00 0.7200 org Kepala Tukang Kayu @ Rp. 50,000.00 36,000.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM PPN ) 469,200.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang gording Kayu jati glugu

3434-2008 1.1000 Kayu glugu @ Rp. #N/A 15.0000 kg Besi strip tebal 5 mm @ Rp. #N/A 3.0000 kg Paku 12 cm @ Rp. #N/A 7.2000 org Tukang Kayu @ Rp. 47,500.00 342,000.00 0.7200 org Kepala Tukang Kayu @ Rp. 50,000.00 36,000.00 2.4000 org Pekerja @ Rp. 36,000.00 86,400.00 0.1200 org Mandor @ Rp. 40,000.00 4,800.00

JUMLAH ( BELUM PPN ) 469,200.00 JASA 10 %JUMLAHDIBULATKAN

Pasang usuk dan reng untuk genteng keramik

SNI 1.0000 Pasang usuk 5/7, reng 2/3 Kayu jati3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0036 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 2/3 Kayu jati (lokal)3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m3

m3

m3

m3

m2

m2

Page 321: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 2/3 Kayu kamper3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 2/3 Kayu kruing3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 2/3 Kayu bengkirai3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0036 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 2/3 Kayu jati3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0036 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 322: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 2/3 Kayu jati lokal3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0036 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 2/3 Kayu kamper3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0036 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 2/3 Kayu kruing3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 2/3 Kayu bengkirai3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0036 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 323: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 2/3 Kayu jati3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0036 m3 Kayu jatii 2/3 @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 2/3 Kayu jati lokal3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0036 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 2/3 Kayu kamper3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0036 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 2/3 Kayu kruing3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 324: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 2/3 Kayu bengkirai3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0036 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 2/3 Kayu jati3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0036 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 2/3 Kayu jati lokal3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0036 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 2/3 Kayu kamper3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0036 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 325: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 2/3 Kayu kruing3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 2/3 Kayu bengkirai3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0036 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 2/3 Kayu jati3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0036 m3 Kayu jatii 2/3 @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 2/3 Kayu jati lokal3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0036 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 326: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 2/3 Kayu kamper3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0036 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 2/3 Kayu kruing3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 2/3 Kayu bengkirai3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0036 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 2/3 Kayu jati3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0036 m3 Kayu jatii 2/3 @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 327: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 2/3 Kayu jati lokal3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0036 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 2/3 Kayu kamper3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0036 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 2/3 Kayu kruing3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0036 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 2/3 Kayu bengkirai3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0036 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

Page 328: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

Pasang usuk dan reng untuk genteng beton

SNI 1.0000 Pasang usuk 5/7, reng 3/4 Kayu jati3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0072 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 3/4 Kayu jati (lokal)3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0072 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 3/4 Kayu kamper3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0072 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 3/4 Kayu kruing3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0072 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 329: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati, reng 3/4 Kayu bengkirai3434-2008 0.0140 m3 Kayu jati balok @ Rp. #N/A

0.0072 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 3/4 Kayu jati3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0072 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 3/4 Kayu jati lokal3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0072 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 3/4 Kayu kamper3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0072 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 330: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 3/4 Kayu kruing3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0072 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu jati lokal, reng 3/4 Kayu bengkirai3434-2008 0.0140 m3 Kayu jati lokal balok @ Rp. #N/A

0.0072 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 3/4 Kayu jati3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0072 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 3/4 Kayu jati lokal3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0072 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 331: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 3/4 Kayu kamper3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0072 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 3/4 Kayu kruing3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0072 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kamper, reng 3/4 Kayu bengkirai3434-2008 0.0140 m3 Kayu kamper balok @ Rp. 4,750,000.00

0.0072 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 3/4 Kayu jati3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0072 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 332: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 3/4 Kayu jati lokal3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0072 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 3/4 Kayu kamper3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0072 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 3/4 Kayu kruing3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0072 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu kruing, reng 3/4 Kayu bengkirai3434-2008 0.0140 m3 Kayu kruingi balok @ Rp. #N/A

0.0072 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 333: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 3/4 Kayu jati3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0072 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 3/4 Kayu jati lokal3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0072 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 3/4 Kayu kamper3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0072 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 3/4 Kayu kruing3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0072 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 334: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 Kayu bengkirai, reng 3/4 Kayu bengkirai3434-2008 0.0140 m3 Kayu bengkirai balok @ Rp. 5,750,000.00

0.0072 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 3/4 Kayu jati3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0072 m3 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 3/4 Kayu jati lokal3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0072 m3 Kayu jati lokal balok @ Rp. #N/A 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 3/4 Kayu kamper3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0072 m3 Kayu kamper balok @ Rp. 4,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00

m2

m2

m2

m2

Page 335: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 3/4 Kayu kruing3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0072 m3 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang usuk 5/7 glugu, reng 3/4 Kayu bengkirai3434-2008 0.0140 m3 Kayu glugu balok @ Rp. 1,458,000.00

0.0072 m3 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku usuk @ Rp. #N/A 0.1000 kg Paku reng @ Rp. #N/A 0.1000 org Tukang Kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala Tukang Kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka atap sirap3434-2008 0.1650 m3 Kayu klas II @ Rp. #N/A

0.2000 kg Paku usuk @ Rp. #N/A 0.1200 org Tukang Kayu @ Rp. 47,500.00 5,700.00 0.0120 org Kepala Tukang Kayu @ Rp. 50,000.00 600.00 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 10,860.00 JASA 10 %JUMLAHDIBULATKAN

Rangka langit-langit 50 x 100 cm

SNI 1.0000 Pasang rangka langit-langit (50 x 100) cm, Kayu jati

3434-2008 0.0154 Kayu jati @ Rp. - 0.2000 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

m2

m2

m2

m2

m3

Page 336: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 24,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (50 x 100) m, Kayu jati lokal

3434-2008 0.0154 Kayu jati lokal @ Rp. #N/A 0.2000 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 24,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (50 x 100) m, Kayu kamper

3434-2008 0.0154 Kayu kamper @ Rp. - 0.2000 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 24,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (50 x 100) m, Kayu kruing

3434-2008 0.0154 Kayu kruing @ Rp. - 0.2000 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 24,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (50 x 100) m, Kayu bengkirai

3434-2008 0.0154 Kayu bengkirai @ Rp. - 0.2000 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM PPN ) 24,150.00 JASA 10 %JUMLAHDIBULATKAN

Rangka langit-langit 60 x 60 cm

m2

m3

m2

m3

m2

m3

m2

m3

Page 337: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang rangka langit-langit (60 x 60) cm, Kayu jati

3434-2008 0.0163 Kayu jati @ Rp. - 0.2500 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 23,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 60) m, Kayu jati lokal

3434-2008 0.0163 Kayu jati lokal @ Rp. #N/A 0.2500 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 23,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 60) m, Kayu kamper

3434-2008 0.0163 Kayu kamper @ Rp. - 0.2500 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 23,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 60) m, Kayu kruing

3434-2008 0.0163 Kayu kruing @ Rp. - 0.2500 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 23,350.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 60) m, Kayu bengkirai

3434-2008 0.0163 Kayu bengkirai @ Rp. - 0.2500 kg Paku usuk @ Rp. #N/A 0.3000 org Tukang Kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala Tukang Kayu @ Rp. 50,000.00 1,500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

m2

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 338: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 23,350.00 JASA 10 %JUMLAHDIBULATKAN

Listplank 3 x 20 cm

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, Kayu jati

3434-2008 0.0108 Kayu jati papan @ Rp. 22,000,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, Kayu jati lokal

3434-2008 0.0108 Kayu jati papan lokal @ Rp. #N/A 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, Kayu kamper

3434-2008 0.0108 Kayu kamper papan @ Rp. 5,500,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, Kayu bengkirai

3434-2008 0.0108 Kayu bengkirai papan @ Rp. 6,000,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

Page 339: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang lisplank ukuran (3 x 20) cm, Kayu kruing

3434-2008 0.0108 Kayu kruing papan @ Rp. 4,750,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

Listplank 3 x 30 cm

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, Kayu jati

3434-2008 0.0110 Kayu jati papan @ Rp. 22,000,000.00 0.0500 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, Kayu jati lokal

3434-2008 0.0110 Kayu jati papan lokal @ Rp. #N/A 0.0500 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, Kayu kamper

3434-2008 0.0110 Kayu kamper papan @ Rp. 5,500,000.00 0.0500 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, Kayu bengkirai

3434-2008 0.0110 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0500 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 340: AHS 2008-Kota.xlsx

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (3 x 30) cm, Kayu kruing

3434-2008 0.0110 Kayu kruing papan @ Rp. 4,750,000.00 0.0500 kg Paku 2" - 5" @ Rp. #N/A 0.2000 org Tukang Kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala Tukang Kayu @ Rp. 50,000.00 1,000.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 14,300.00 JASA 10 %JUMLAHDIBULATKAN

Listplank 2 x 20 cm

SNI 1.0000 Pasang lisplank ukuran (2 x 20) cm, Kayu jati

2007 0.0048 Kayu jati papan @ Rp. 22,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 20) cm, Kayu jati lokal

2007 0.0048 Kayu jati lokal papan @ Rp. #N/A 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 20) cm, Kayu kamper

2007 0.0048 Kayu kamper papan @ Rp. 5,500,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAH

m1

m3

m1

m3

m1

m3

m1

m3

Page 341: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 20) cm, Kayu bengkirai

2007 0.0048 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 20) cm, Kayu kruing

2007 0.0048 Kayu kruing papan @ Rp. 4,750,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

Listplank 2 x 25 cm

SNI 1.0000 Pasang lisplank ukuran (2 x 25) cm, Kayu jati

2007 0.0060 Kayu jati papan @ Rp. 22,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 25) cm, Kayu jati lokal

2007 0.0060 Kayu jati lokal papan @ Rp. #N/A 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 25) cm, Kayu kamper

2007 0.0060 Kayu kamper papan @ Rp. 5,500,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A

m1

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 342: AHS 2008-Kota.xlsx

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 25) cm, Kayu bengkirai

2007 0.0060 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran (2 x 25) cm, Kayu kruing

2007 0.0060 Kayu kruing papan @ Rp. 4,750,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

Listplank 2 x (3 x 20) cm

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, Kayu jati

2007 0.0145 Kayu jati papan @ Rp. 22,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, Kayu jati lokal

2007 0.0145 Kayu jati lokal papan @ Rp. #N/A 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00

m1

m3

m1

m3

m1

m3

m1

m3

Page 343: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, Kayu kamper

2007 0.0145 Kayu kamper papan @ Rp. 5,500,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, Kayu bengkirai

2007 0.0145 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (3 x 20) cm, Kayu kruing

2007 0.0145 Kayu kruing papan @ Rp. 4,750,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

Listplank 2 x (2 x 20) cm

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, Kayu jati

2007 0.0086 Kayu jati papan @ Rp. 22,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, Kayu jati lokal

m1

m3

m1

m3

m1

m3

m1

m3

m1

Page 344: AHS 2008-Kota.xlsx

2007 0.0086 Kayu jati lokal papan @ Rp. #N/A 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, Kayu kamper

2007 0.0086 Kayu kamper papan @ Rp. 5,500,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, Kayu bengkirai

2007 0.0086 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang lisplank ukuran 2 x (2 x 20) cm, Kayu kruing

2007 0.0086 Kayu kruing papan @ Rp. 4,750,000.00 0.0600 kg Paku biasa 2" - 5" @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

Pasang papan ruiter 2 x 20 cm

SNI 1.0000 Mengerjakan papan ruiter Kayu jati 2/20

2007 0.0040 Kayu jati papan @ Rp. 22,000,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. #N/A 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 345: AHS 2008-Kota.xlsx

0.0014 org Mandor @ Rp. 40,000.00 56.00 JUMLAH 5,264.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan papan ruiter Kayu jati lokal 2/20

2007 0.0040 Papan Kayu jati lokal @ Rp. #N/A 0.0200 kg Paku biasa 2" - 5" @ Rp. #N/A 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan papan ruiter Kayu kamper 2/20

2007 0.0040 Kayu kamper papan @ Rp. 5,500,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. #N/A 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan papan ruiter Kayu kruing 2/20

2007 0.0040 Kayu kruing papan @ Rp. 4,750,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. #N/A 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan papan ruiter Kayu bengkirai 2/20

2007 0.0040 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0200 kg Paku biasa 2" - 5" @ Rp. #N/A 0.0800 org Tukang kayu @ Rp. 47,500.00 3,800.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0014 org Mandor @ Rp. 40,000.00 56.00

JUMLAH 5,264.00 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m1

m3

m1

m3

m1

m3

Page 346: AHS 2008-Kota.xlsx

Rangka dinding pemisah 60 x 120 cm

SNI 1.0000 m2 Pasang rangka dinding pemisah ukuran (60 x 120) cm, Kayu jati

3434-2008 0.0280 Kayu jati balok @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang rangka dinding pemisah ukuran (60 x 120) cm, Kayu jati lokal

3434-2008 0.0280 Kayu jati balok lokal @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang rangka dinding pemisah ukuran (60 x 120) cm, Kayu kamper

3434-2008 0.0280 Kayu kamper @ Rp. - 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang rangka dinding pemisah ukuran (60 x 120) cm, Kayu bengkirai

3434-2008 0.0280 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang rangka dinding pemisah ukuran (60 x 120) cm, Kayu kruing

3434-2008 0.0280 Kayu kruing balok @ Rp. 4,350,000.00 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00

m3

m3

m3

m3

m3

Page 347: AHS 2008-Kota.xlsx

0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

Rangka dinding pemisah teakwood rangkap

SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka Kayu jati

3434-2008 0.0280 Kayu jati balok @ Rp. #N/A 0.8600 lbr Teakwood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka Kayu jati lokal

3434-2008 0.0280 Kayu jati balok lokal @ Rp. #N/A 0.8600 lbr Teakwood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka Kayu kamper

3434-2008 0.0280 Kayu kamper @ Rp. - 0.8600 lbr Teakwood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka Kayu bengkirai

3434-2008 0.0280 Kayu bengkirai balok @ Rp. 5,750,000.00 0.8600 lbr Teakwood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A

m3

m3

m3

m3

Page 348: AHS 2008-Kota.xlsx

0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka Kayu kruing

3434-2008 0.0280 Kayu kruing balok @ Rp. 4,350,000.00 0.8600 lbr Teakwood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.4500 org Tukang Kayu @ Rp. 47,500.00 21,375.00 0.0450 org Kepala Tukang Kayu @ Rp. 50,000.00 2,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 29,325.00 JASA 10 %JUMLAHDIBULATKAN

Rangka dinding pemisah plywood rangkap

SNI 1.0000 m2 Pasang dinding pemisah plywood rangkap, rangka Kayu jati

3434-2008 0.0280 Kayu jati balok @ Rp. #N/A 0.8600 lbr Plywood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.6000 org Tukang Kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala Tukang Kayu @ Rp. 50,000.00 3,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 39,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah plywood rangkap, rangka Kayu jati lokal

3434-2008 0.0280 Kayu jati balok lokal @ Rp. #N/A 0.8600 lbr Plywood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.6000 org Tukang Kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala Tukang Kayu @ Rp. 50,000.00 3,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 39,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah plywood rangkap, rangka Kayu kamper

3434-2008 0.0280 Kayu kamper @ Rp. - 0.8600 lbr Plywood tebal 4 mm @ Rp. #N/A

m3

m3

m3

m3

Page 349: AHS 2008-Kota.xlsx

0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.6000 org Tukang Kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala Tukang Kayu @ Rp. 50,000.00 3,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 39,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah plywood rangkap, rangka Kayu bengkirai

3434-2008 0.0280 Kayu bengkirai balok @ Rp. 5,750,000.00 0.8600 lbr Plywood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.6000 org Tukang Kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala Tukang Kayu @ Rp. 50,000.00 3,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 39,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding pemisah plywood rangkap, rangka Kayu kruing

3434-2008 0.0280 Kayu kruing balok @ Rp. 4,350,000.00 0.8600 lbr Plywood tebal 4 mm @ Rp. #N/A 0.5600 kg Lem kayu @ Rp. #N/A 0.1500 kg Paku 2" - 5" @ Rp. #N/A 0.6000 org Tukang Kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala Tukang Kayu @ Rp. 50,000.00 3,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 39,100.00 JASA 10 %JUMLAHDIBULATKAN

Pasang dinding lambriziring kayu papan

SNI 1.0000 m2 Pasang dinding lambiziring, dari Kayu jati papan

3434-2008 0.0070 Kayu jati papan @ Rp. 22,000,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.1500 kg Paku sekrup 10 cm @ Rp. #N/A 1.8000 org Tukang Kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kepala Tukang Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding lambiziring, dari Kayu jati lokal papan

3434-2008 0.0070 Kayu jati lokal papan @ Rp. #N/A

m3

m3

m3

m3

Page 350: AHS 2008-Kota.xlsx

0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.1500 kg Paku sekrup 10 cm @ Rp. #N/A 1.8000 org Tukang Kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kepala Tukang Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding lambiziring, dari Kayu kamper papan

3434-2008 0.0070 Kayu kamper papan @ Rp. 5,500,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.1500 kg Paku sekrup 10 cm @ Rp. #N/A 1.8000 org Tukang Kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kepala Tukang Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding lambiziring, dari Kayu bengkirai papan

3434-2008 0.0070 Kayu bengkirai papan @ Rp. 6,000,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.1500 kg Paku sekrup 10 cm @ Rp. #N/A 1.8000 org Tukang Kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kepala Tukang Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding lambiziring, dari Kayu kruing papan

3434-2008 0.0070 Kayu kruing papan @ Rp. 4,750,000.00 0.1000 kg Paku 2" - 5" @ Rp. #N/A 0.1500 kg Paku sekrup 10 cm @ Rp. #N/A 1.8000 org Tukang Kayu @ Rp. 47,500.00 85,500.00 0.1800 org Kepala Tukang Kayu @ Rp. 50,000.00 9,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0300 org Mandor @ Rp. 40,000.00 1,200.00

JUMLAH ( BELUM PPN ) 117,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding lambiziring, dari plywood 120 x 240 cm3434-2008 0.4000 lbr Plywood tebal 4 mm @ Rp. #N/A

0.0500 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0750 org Tukang Kayu @ Rp. 47,500.00 3,562.50 0.0075 org Kepala Tukang Kayu @ Rp. 50,000.00 375.00 0.0250 org Pekerja @ Rp. 36,000.00 900.00

m3

m3

m3

Page 351: AHS 2008-Kota.xlsx

0.0013 org Mandor @ Rp. 40,000.00 50.00 JUMLAH ( BELUM PPN ) 4,887.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Pasang dinding bilik bambu, rangka kayu klas III, IV3434-2008 1.5000 m2 Bilik bambu @ Rp. #N/A

0.0140 m3 Usuk kayu klas III, IV @ Rp. #N/A 0.0120 kg Paku 2" - 5" @ Rp. #N/A 0.0030 m3 List kayu 2/4 cm @ Rp. #N/A 0.0500 org Tukang Kayu @ Rp. 47,500.00 2,375.00 0.0050 org Kepala Tukang Kayu @ Rp. 50,000.00 250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 6,425.00 JASA 10 %JUMLAHDIBULATKAN

Membuat dan memasang kusen pintu dan jendela

SNI 1.0000 Membuat dan memasang kusen pintu / jendela Kayu jati (klas plitur)

3434-2008 1.1000 Kayu jati (klas plitur) @ Rp. #N/A

1.2500 kg Paku usuk @ Rp. #N/A 21.0000 org Tukang Kayu @ Rp. 47,500.00 997,500.00 2.1000 org Kepala Tukang Kayu @ Rp. 50,000.00 105,000.00 7.0000 org Pekerja @ Rp. 36,000.00 252,000.00 0.3500 org Mandor @ Rp. 40,000.00 14,000.00

JUMLAH ( BELUM PPN ) 1,368,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat dan memasang kusen pintu / jendela Kayu jati lokal

3434-2008 1.1000 Kayu jati lokal @ Rp. #N/A 1.2500 kg Paku usuk @ Rp. #N/A 21.0000 org Tukang Kayu @ Rp. 47,500.00 997,500.00 2.1000 org Kepala Tukang Kayu @ Rp. 50,000.00 105,000.00 7.0000 org Pekerja @ Rp. 36,000.00 252,000.00 0.3500 org Mandor @ Rp. 40,000.00 14,000.00

JUMLAH ( BELUM PPN ) 1,368,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat dan memasang kusen pintu / jendela Kayu kamper

3434-2008 1.1000 Kayu kamper @ Rp. - 1.2500 kg Paku usuk @ Rp. #N/A 18.0000 org Tukang Kayu @ Rp. 47,500.00 855,000.00 1.8000 org Kepala Tukang Kayu @ Rp. 50,000.00 90,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,173,000.00 JASA 10 %

m3

m3

m3

m3

m3

m3

Page 352: AHS 2008-Kota.xlsx

JUMLAHDIBULATKAN

SNI 1.0000 Membuat dan memasang kusen pintu / jendela Kayu bengkirai

3434-2008 1.1000 Kayu bengkirai balok @ Rp. 5,750,000.00 1.2500 kg Paku usuk @ Rp. #N/A 18.0000 org Tukang Kayu @ Rp. 47,500.00 855,000.00 1.8000 org Kepala Tukang Kayu @ Rp. 50,000.00 90,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,173,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat dan memasang kusen pintu / jendela Kayu kruing

3434-2008 1.1000 Kayu kruing balok @ Rp. 4,350,000.00 1.2500 kg Paku usuk @ Rp. #N/A 18.0000 org Tukang Kayu @ Rp. 47,500.00 855,000.00 1.8000 org Kepala Tukang Kayu @ Rp. 50,000.00 90,000.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 1,173,000.00 JASA 10 %JUMLAHDIBULATKAN

Membuat dan memasang pintu klamp standar

SNI 1.0000 m2 Membuat dan memasang pintu klamp standar Kayu jati lokal

3434-2008 0.0400 Kayu jati lokal papan @ Rp. #N/A 0.0500 kg Paku 2" - 5" @ Rp. #N/A 1.0500 org Tukang Kayu @ Rp. 47,500.00 49,875.00 0.1050 org Kepala Tukang Kayu @ Rp. 50,000.00 5,250.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 68,425.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang pintu klamp standar Kayu kamper

3434-2008 0.0400 Kayu kamper papan @ Rp. 5,500,000.00 0.0500 kg Paku 2" - 5" @ Rp. #N/A 1.0500 org Tukang Kayu @ Rp. 47,500.00 49,875.00 0.1050 org Kepala Tukang Kayu @ Rp. 50,000.00 5,250.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 68,425.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang pintu klamp standar Kayu bengkirai

3434-2008 0.0400 Kayu bengkirai papan @ Rp. 6,000,000.00

m3

m3

m3

m3

m3

m3

m3

Page 353: AHS 2008-Kota.xlsx

0.0500 kg Paku 2" - 5" @ Rp. #N/A 1.0500 org Tukang Kayu @ Rp. 47,500.00 49,875.00 0.1050 org Kepala Tukang Kayu @ Rp. 50,000.00 5,250.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 68,425.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang pintu klamp standar Kayu kruing

3434-2008 0.0400 Kayu kruing papan @ Rp. 4,750,000.00 0.0500 kg Paku 2" - 5" @ Rp. #N/A 1.0500 org Tukang Kayu @ Rp. 47,500.00 49,875.00 0.1050 org Kepala Tukang Kayu @ Rp. 50,000.00 5,250.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 68,425.00 JASA 10 %JUMLAHDIBULATKAN

Membuat dan memasang daun pintu panil

SNI 1.0000 m2 Membuat dan memasang daun pintu panil Kayu jati

3434-2008 0.0400 Kayu jati papan @ Rp. 22,000,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu panil Kayu jati lokal

3434-2008 0.0400 Kayu jati lokal papan @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu panil Kayu kamper

3434-2008 0.0400 Kayu kamper papan @ Rp. 5,500,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00

m3

m3

m3

m3

Page 354: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu panil Kayu bengkirai

3434-2008 0.0400 Kayu bengkirai papan @ Rp. 6,000,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu panil Kayu kruing

3434-2008 0.0400 Kayu kruing papan @ Rp. 4,750,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

Membuat dan memasang daun pintu dan jendela kaca

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela kaca Kayu jati

3434-2008 0.0240 Kayu jati papan @ Rp. 22,000,000.00 0.3000 kg Lem kayu @ Rp. #N/A 2.4000 org Tukang Kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala Tukang Kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela kaca Kayu jati lokal

3434-2008 0.0240 Kayu jati lokal papan @ Rp. #N/A 0.3000 kg Lem kayu @ Rp. #N/A 2.4000 org Tukang Kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala Tukang Kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela kaca Kayu kamper

m3

m3

m3

m3

Page 355: AHS 2008-Kota.xlsx

3434-2008 0.0240 Kayu kamper papan @ Rp. 5,500,000.00 0.3000 kg Lem kayu @ Rp. #N/A 2.4000 org Tukang Kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala Tukang Kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela kaca Kayu bengkirai

3434-2008 0.0240 Kayu bengkirai papan @ Rp. 6,000,000.00 0.3000 kg Lem kayu @ Rp. #N/A 2.4000 org Tukang Kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala Tukang Kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela kaca Kayu kruing

3434-2008 0.0240 Kayu kruing papan @ Rp. 4,750,000.00 0.3000 kg Lem kayu @ Rp. #N/A 2.4000 org Tukang Kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala Tukang Kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

Membuat dan memasang daun pintu dan jendela jalusi

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela jalusi Kayu jati

3434-2008 0.0640 Kayu jati papan @ Rp. 22,000,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela jalusi Kayu jati lokal

3434-2008 0.0640 Kayu jati lokal papan @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00

m3

m3

m3

m3

m3

Page 356: AHS 2008-Kota.xlsx

0.0500 org Mandor @ Rp. 40,000.00 2,000.00 JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela jalusi Kayu kamper

3434-2008 0.0640 Kayu kamper papan @ Rp. 5,500,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela jalusi Kayu bengkirai

3434-2008 0.0640 Kayu bengkirai papan @ Rp. 6,000,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat dan memasang daun pintu dan jendela jalusi Kayu kruing

3434-2008 0.0640 Kayu kruing papan @ Rp. 4,750,000.00 0.5000 kg Lem kayu @ Rp. #N/A 3.0000 org Tukang Kayu @ Rp. 47,500.00 142,500.00 0.3000 org Kepala Tukang Kayu @ Rp. 50,000.00 15,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) 195,500.00 JASA 10 %JUMLAHDIBULATKAN

Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu

SNI 1.0000 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu jati lokal

3434-2008 0.0250 Kayu jati lokal papan @ Rp. #N/A 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.1000 org Tukang kayu @ Rp. 47,500.00 99,750.00 0.2100 org Kepala tukang kayu @ Rp. 50,000.00 10,500.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 136,850.00 JASA 10 %JUMLAH

m3

m3

m3

m2

m3

Page 357: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu kamper

3434-2008 0.0250 Kayu kamper papan @ Rp. 5,500,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.1000 org Tukang kayu @ Rp. 47,500.00 99,750.00 0.2100 org Kepala tukang kayu @ Rp. 50,000.00 10,500.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 136,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu bengkirai

3434-2008 0.0250 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.1000 org Tukang kayu @ Rp. 47,500.00 99,750.00 0.2100 org Kepala tukang kayu @ Rp. 50,000.00 10,500.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 136,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu kruing

3434-2008 0.0250 Kayu kruing papan @ Rp. 4,750,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.1000 org Tukang kayu @ Rp. 47,500.00 99,750.00 0.2100 org Kepala tukang kayu @ Rp. 50,000.00 10,500.00 0.7000 org Pekerja @ Rp. 36,000.00 25,200.00 0.0350 org Mandor @ Rp. 40,000.00 1,400.00

JUMLAH ( BELUM PPN ) 136,850.00 JASA 10 %JUMLAHDIBULATKAN

Membuat pintu plywood rangkap, rangka expose

SNI 1.0000 Membuat pintu plywood rangkap, rangka expose, Kayu jati

3434-2008 0.0256 Kayu jati papan @ Rp. 22,000,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

m2

m3

m2

m3

m2

m3

m2

m3

Page 358: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat pintu plywood rangkap, rangka expose, Kayu jati lokal

3434-2008 0.0256 Kayu jati lokal papan @ Rp. #N/A 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat pintu plywood rangkap, rangka expose, Kayu kamper

3434-2008 0.0256 Kayu kamper papan @ Rp. 5,500,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat pintu plywood rangkap, rangka expose, Kayu bengkirai

3434-2008 0.0256 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membuat pintu plywood rangkap, rangka expose, Kayu kruing

3434-2008 0.0256 Kayu kruing papan @ Rp. 4,750,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Plywood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00

m2

m3

m2

m3

m2

m3

m2

m3

Page 359: AHS 2008-Kota.xlsx

0.0400 org Mandor @ Rp. 40,000.00 1,600.00 JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

Memasang jalusi kusen

SNI 1.0000 Memasang jalusi kusen, Kayu jati

3434-2008 0.0600 Kayu jati papan @ Rp. 22,000,000.00 0.1500 kg Paku biasa 1/2" - 1" @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6700 org Pekerja @ Rp. 36,000.00 24,120.00 0.3350 org Mandor @ Rp. 40,000.00 13,400.00

JUMLAH ( BELUM PPN ) 142,520.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang jalusi kusen, Kayu jati lokal

3434-2008 0.0600 Kayu jati lokal papan @ Rp. #N/A 0.1500 kg Paku biasa 1/2" - 1" @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6700 org Pekerja @ Rp. 36,000.00 24,120.00 0.3350 org Mandor @ Rp. 40,000.00 13,400.00

JUMLAH ( BELUM PPN ) 142,520.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang jalusi kusen, Kayu kamper

3434-2008 0.0600 Kayu kamper papan @ Rp. 5,500,000.00 0.1500 kg Paku biasa 1/2" - 1" @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6700 org Pekerja @ Rp. 36,000.00 24,120.00 0.3350 org Mandor @ Rp. 40,000.00 13,400.00

JUMLAH ( BELUM PPN ) 142,520.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang jalusi kusen, Kayu bengkirai

3434-2008 0.0600 Kayu bengkirai papan @ Rp. 6,000,000.00 0.1500 kg Paku biasa 1/2" - 1" @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6700 org Pekerja @ Rp. 36,000.00 24,120.00 0.3350 org Mandor @ Rp. 40,000.00 13,400.00

JUMLAH ( BELUM PPN ) 142,520.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m3

m2

m3

m2

m3

Page 360: AHS 2008-Kota.xlsx

SNI 1.0000 Memasang jalusi kusen, Kayu kruing

3434-2008 0.0600 Kayu kruing papan @ Rp. 4,750,000.00 0.1500 kg Paku biasa 1/2" - 1" @ Rp. #N/A 2.0000 org Tukang kayu @ Rp. 47,500.00 95,000.00 0.2000 org Kepala tukang kayu @ Rp. 50,000.00 10,000.00 0.6700 org Pekerja @ Rp. 36,000.00 24,120.00 0.3350 org Mandor @ Rp. 40,000.00 13,400.00

JUMLAH ( BELUM PPN ) 142,520.00 JASA 10 %JUMLAHDIBULATKAN

Memasang teakwood rangkap, rangka expose

SNI 1.0000 Memasang teakwood rangkap, rangka expose, Kayu jati

3434-2008 0.0250 Kayu jati papan @ Rp. 22,000,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.3000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang teakwood rangkap, rangka expose, Kayu jati lokal

3434-2008 0.0250 Kayu jati lokal papan @ Rp. #N/A 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.3000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang teakwood rangkap, rangka expose, Kayu kamper

3434-2008 0.0250 Kayu kamper papan @ Rp. 5,500,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.3000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAH

m2

m3

m2

m3

m2

m3

m2

m3

Page 361: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Memasang teakwood rangkap, rangka expose, Kayu bengkirai

3434-2008 0.0250 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.3000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang teakwood rangkap, rangka expose, Kayu kruing

3434-2008 0.0250 Kayu kruing papan @ Rp. 4,750,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.3000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 2.4000 org Tukang kayu @ Rp. 47,500.00 114,000.00 0.2400 org Kepala tukang kayu @ Rp. 50,000.00 12,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 156,400.00 JASA 10 %JUMLAHDIBULATKAN

Memasang teakwood rangkap lapis formika, rangka expose

SNI 1.0000 Memasang teakwood rangkap lapis formika, rangka expose, Kayu jati lokal

3434-2008 0.0250 Kayu jati lokal papan @ Rp. #N/A 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.8000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 0.5000 lbr Formika @ Rp. #N/A 2.5500 org Tukang kayu @ Rp. 47,500.00 121,125.00 0.2550 org Kepala tukang kayu @ Rp. 50,000.00 12,750.00 0.8500 org Pekerja @ Rp. 36,000.00 30,600.00 0.0425 org Mandor @ Rp. 40,000.00 1,700.00

JUMLAH ( BELUM PPN ) 166,175.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang teakwood rangkap lapis formika, rangka expose, Kayu kamper

3434-2008 0.0250 Kayu kamper papan @ Rp. 5,500,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.8000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 0.5000 lbr Formika @ Rp. #N/A 2.5500 org Tukang kayu @ Rp. 47,500.00 121,125.00 0.2550 org Kepala tukang kayu @ Rp. 50,000.00 12,750.00

m2

m3

m2

m3

m2

m3

m2

m3

Page 362: AHS 2008-Kota.xlsx

0.8500 org Pekerja @ Rp. 36,000.00 30,600.00 0.0425 org Mandor @ Rp. 40,000.00 1,700.00

JUMLAH ( BELUM PPN ) 166,175.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang teakwood rangkap lapis formika, rangka expose, Kayu bengkirai

3434-2008 0.0250 Kayu bengkirai papan @ Rp. 6,000,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.8000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 0.5000 lbr Formika @ Rp. #N/A 2.5500 org Tukang kayu @ Rp. 47,500.00 121,125.00 0.2550 org Kepala tukang kayu @ Rp. 50,000.00 12,750.00 0.8500 org Pekerja @ Rp. 36,000.00 30,600.00 0.0425 org Mandor @ Rp. 40,000.00 1,700.00

JUMLAH ( BELUM PPN ) 166,175.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang teakwood rangkap lapis formika, rangka expose, Kayu kruing

3434-2008 0.0250 Kayu kruing papan @ Rp. 4,750,000.00 0.0300 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.8000 kg Lem kayu @ Rp. #N/A 1.0000 lbr Teakwood 900 x 2200 x 4 mm @ Rp. #N/A 0.5000 lbr Formika @ Rp. #N/A 2.5500 org Tukang kayu @ Rp. 47,500.00 121,125.00 0.2550 org Kepala tukang kayu @ Rp. 50,000.00 12,750.00 0.8500 org Pekerja @ Rp. 36,000.00 30,600.00 0.0425 org Mandor @ Rp. 40,000.00 1,700.00

JUMLAH ( BELUM PPN ) 166,175.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN BESI DAN ALUMUNIUM

SNI 1.0000 kg Pasang besi profil7393-2008 1.1500 kg Besi profil @ Rp. #N/A

0.0600 org Tukang las konstruksi @ Rp. #N/A #N/A 0.0060 org Kepala tukang las konstruksi @ Rp. #N/A #N/A 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 kg Pasang kuda-kuda baja IWF7393-2008 1.1500 kg Baja profil IWF @ Rp. #N/A

0.0600 org Tukang las konstruksi @ Rp. #N/A #N/A 0.0060 org Kepala tukang las konstruksi @ Rp. #N/A #N/A 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

m2

m3

m2

m3

Page 363: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg Kuda-kuda baja siku 115.0000 kg Besi siku rata-rata @ Rp. #N/A 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 6.0000 org Tukang besi @ Rp. 45,000.00 270,000.00 0.6000 org Kepala Tukang besi @ Rp. 47,500.00 28,500.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 526,500.00 Peralatan 5%

JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg Plat besi lembaran 115.0000 kg Besi plat lembaran @ Rp. #N/A 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 6.0000 org Tukang besi @ Rp. 45,000.00 270,000.00 0.6000 org Kepala Tukang besi @ Rp. 47,500.00 28,500.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 526,500.00 Peralatan 5%

JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg Gordingbaja 115.0000 kg Besi gording canal @ Rp. #N/A 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 6.0000 org Tukang besi @ Rp. 45,000.00 270,000.00 0.6000 org Kepala Tukang besi @ Rp. 47,500.00 28,500.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 526,500.00 Peralatan 5%

JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 kg Ikatan angin diameter 16 mm dan water mur 115.0000 kg Besi beton polos @ Rp. 7,900.00 3.0000 kg Water mur @ Rp. #N/A 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 6.0000 org Tukang besi @ Rp. 45,000.00 270,000.00 0.6000 org Kepala Tukang besi @ Rp. 47,500.00 28,500.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 526,500.00 Peralatan 5%

JASA 10 %JUMLAHDIBULATKAN

Page 364: AHS 2008-Kota.xlsx

tambahan 1.0000 kg Trekstang diameter 12 mm 115.0000 kg Besi beton polos @ Rp. 7,900.00 6.0000 org Pekerja @ Rp. 36,000.00 216,000.00 6.0000 org Tukang besi @ Rp. 45,000.00 270,000.00 0.6000 org Kepala Tukang besi @ Rp. 47,500.00 28,500.00 0.3000 org Mandor @ Rp. 40,000.00 12,000.00

JUMLAH ( BELUM PPN ) 526,500.00 Peralatan 5%

JASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 Unit Manhole uk. 70 x 70 cm 6.4000 kg Besi L. 50.50.5 @ Rp. #N/A 11.5400 kg Plat baja t = 3 mm @ Rp. #N/A 8.0000 bh Angkur besi dia. 12 mm @ Rp. #N/A 2.0000 bh Engsel besi @ Rp. #N/A 1.0000 bh Kunci gembok @ Rp. #N/A 1.1250 m2 Cat besi @ Rp. #N/A 350.0000 cm Pengelasan @ Rp. #N/A 1.0000 ls Upah pasang @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/ADIBULATKAN

tambahan 1.0000 Unit 24.1280 kg Baja L.50.50.5 @ Rp. #N/A 31.6000 kg Besi beton dia. 16 mm @ Rp. #N/A 2.0000 bh Angkur dia. 16 mm @ Rp. #N/A 1.8850 m2 Cat besi @ Rp. #N/A 240.0000 cm Pengelasan @ Rp. #N/A 1.0000 ls Upah pasang @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/ADIBULATKAN

SNI 100.00 kg Pekerjaan perakitan7393-2008 1.0000 ltr Solar @ Rp. 4,300.00

0.1000 ltr Minyak pelumas @ Rp. 14,000.00 0.1000 org Tukang besi konstruksi @ Rp. #N/A #N/A 0.0010 org Kepala tukang besi konstruksi @ Rp. #N/A #N/A 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00 0.8000 jam Sewa alat @ Rp. #N/A

JUMLAH ( BELUM PPN ) #N/AJADI 1.00 kg #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku7393-2008 15.0000 kg Besi siku L 30.30.3 @ Rp. #N/A

32.8000 kg Besi plat baja @ Rp. #N/A 0.0500 kg Kawat las @ Rp. 6,500.00 1.0500 org Tukang las biasa @ Rp. #N/A #N/A 0.1050 org Kepala tukang las biasa @ Rp. #N/A #N/A 1.0500 org Pekerja @ Rp. 36,000.00 37,800.00

Grill dari besi beton Ǿ 16mm rangka baja 50.50.5 uk 1 x 1 m

Page 365: AHS 2008-Kota.xlsx

0.0520 org Mandor @ Rp. 40,000.00 2,080.00 JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 10.0000 cm Pengelasan dengan las listrik7393-2008 0.4000 kg Kawat las listrik @ Rp. #N/A

0.3000 ltr Solar @ Rp. 4,300.00 0.0400 ltr Minyak pelumas @ Rp. 14,000.00 0.0200 org Tukang besi konstruksi @ Rp. #N/A #N/A 0.0020 org Kepala tukang besi konstruksi @ Rp. #N/A #N/A 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0020 org Mandor @ Rp. 40,000.00 80.00 0.1700 jam Sewa alat @ Rp. #N/A

JUMLAH ( BELUM PPN ) #N/AJADI 1.00 cm #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Rangka jendela besi scuare tube (25 x 5) cm7393-2008 4.7600 m1 Besi scuare tube @ Rp. #N/A

4.5220 m1 Besi lis kaca (1 x 1) cm @ Rp. #N/A 20.0000 cm Pengelasan @ Rp. #N/A 0.6500 org Tukang las biasa @ Rp. #N/A #N/A 0.0650 org Kepala tukang las biasa @ Rp. #N/A #N/A 0.6500 org Pekerja @ Rp. 36,000.00 23,400.00 0.0320 org Mandor @ Rp. 40,000.00 1,280.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang Rolling door besi

7393-2008 1.0000 Pintu gulung besi @ Rp. 250,000.00 1.2000 org Tukang las biasa @ Rp. #N/A #N/A 0.1200 org Kepala tukang las biasa @ Rp. #N/A #N/A 1.2000 org Pekerja @ Rp. 36,000.00 43,200.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu lipat (folding door) bahan plastik/PVC

7393-2008 1.0000 Pintu lipat @ Rp. #N/A 0.4400 org Tukang besi @ Rp. 45,000.00 19,800.00 0.0440 org Kepala tukang besi @ Rp. 47,500.00 2,090.00 0.4400 org Pekerja @ Rp. 36,000.00 15,840.00 0.0220 org Mandor @ Rp. 40,000.00 880.00

JUMLAH ( BELUM PPN ) 38,610.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

Page 366: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang pintu Sunscreen alumunium

7393-2008 1.0000 Sunscreen alumunium @ Rp. 250,000.00 0.8000 org Tukang besi @ Rp. 45,000.00 36,000.00 0.0800 org Kepala tukang besi @ Rp. 47,500.00 3,800.00 0.0800 org Pekerja @ Rp. 36,000.00 2,880.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 42,840.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang Rolling door alumunium

7393-2008 1.0000 Pintu gulung alumunium @ Rp. #N/A 1.0000 org Tukang alumunium @ Rp. #N/A #N/A 0.1000 org Kepala tukang alumunium @ Rp. #N/A #N/A 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.0500 org Mandor @ Rp. 40,000.00 2,000.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kusen pintu alumunium7393-2008 1.1000 m1 Profil alumunium @ Rp. #N/A

2.0000 bh Skrup fixer @ Rp. #N/A 0.0600 tube Sealent @ Rp. #N/A 0.0430 org Tukang alumunium @ Rp. #N/A #N/A 0.0043 org Kepala tukang alumunium @ Rp. #N/A #N/A 0.0430 org Pekerja @ Rp. 36,000.00 1,548.00 0.0021 org Mandor @ Rp. 40,000.00 84.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu alumunium strip lebar 8 cm7393-2008 4.4000 m1 Profil alumunium @ Rp. #N/A

14.6000 m1 Alumunium strip @ Rp. #N/A 0.0850 org Tukang alumunium @ Rp. #N/A #N/A 0.0085 org Kepala tukang alumunium @ Rp. #N/A #N/A 0.0850 org Pekerja @ Rp. 36,000.00 3,060.00 0.0042 org Mandor @ Rp. 40,000.00 168.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pintu kaca rangka alumunium7393-2008 4.4000 m1 Pintu alumunium @ Rp. 400,000.00

4.5000 m1 Profil kaca @ Rp. #N/A 0.2700 tube Sealent @ Rp. #N/A 0.0850 org Tukang alumunium @ Rp. #N/A #N/A 0.0090 org Kepala tukang alumunium @ Rp. #N/A #N/A 0.0850 org Pekerja @ Rp. 36,000.00 3,060.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m2

m2

m2

m2

m1

m2

m2

Page 367: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang vienetions dan vertikal blinds7393-2008 1.0000 m2 Vienetions dan vertikal blinds (tirai) @ Rp. #N/A

0.3500 org Tukang kayu @ Rp. 47,500.00 16,625.00 0.0350 org Kepala tukang kayu @ Rp. 50,000.00 1,750.00 0.3500 org Pekerja @ Rp. 36,000.00 12,600.00 0.0175 org Mandor @ Rp. 40,000.00 700.00

JUMLAH ( BELUM PPN ) 31,675.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang terali besi strip (2 x 3) mm7393-2008 6.1770 kg Besi strip @ Rp. 7,500.00

27.0800 cm Pengelasan @ Rp. #N/A 1.6700 org Tukang las biasa @ Rp. #N/A #N/A 0.1670 org Kepala tukang las biasa @ Rp. #N/A #N/A 1.6700 org Pekerja @ Rp. 36,000.00 60,120.00 0.0830 org Mandor @ Rp. 40,000.00 3,320.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kawat nyamuk7393-2008 1.1000 m2 Kawat nyamuk @ Rp. 8,250.00

11.1100 cm Pengelasan @ Rp. #N/A 1.7160 kg Baja strip (0,2 x 2) cm @ Rp. #N/A 0.1000 org Tukang las biasa @ Rp. #N/A #N/A 0.0100 org Kepala tukang las biasa @ Rp. #N/A #N/A 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang jendela nako & tralis

7393-2008 1.1000 Jendela nako (rangka + kaca 5 mm) @ Rp. #N/A 10.0000 bh Paku skrup 1/2" - 1" @ Rp. #N/A 7.0000 m1 Besi strip @ Rp. 7,500.00 0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 17,740.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu jati7393-2008 1.0500 m1 Seng plat BJLS 28 @ Rp. #N/A

m2

m2

m2

m2

m2

m1

Page 368: AHS 2008-Kota.xlsx

0.0150 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0190 Kayu jati papan @ Rp. 22,000,000.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 27,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu jati lokal7393-2008 1.0500 m1 Seng plat BJLS 28 @ Rp. #N/A

0.0150 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0190 Kayu jati lokal papan @ Rp. #N/A 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 27,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar, seng BJLS 28 lebar 90 cm, papan Kayu kamper7393-2008 1.0500 m1 Seng plat BJLS 28 @ Rp. #N/A

0.0150 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0190 Kayu kamper papan @ Rp. 5,500,000.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 27,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu bengkirai7393-2008 1.0500 m1 Seng plat BJLS 28 @ Rp. #N/A

0.0150 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0190 Kayu bengkirai papan @ Rp. 6,000,000.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 27,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu kruing7393-2008 1.0500 m1 Seng plat BJLS 28 @ Rp. #N/A

0.0150 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0190 Kayu kruing papan @ Rp. 4,750,000.00 0.4000 org Tukang kayu @ Rp. 47,500.00 19,000.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00

m3

m1

m3

m1

m3

m1

m3

m1

m3

Page 369: AHS 2008-Kota.xlsx

0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 27,850.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 6.20 1.0500 lbr Seng plat BJLS 30 @ Rp. #N/A

0.0100 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.5000 kg Besi strip @ Rp. 7,500.00 0.3000 org Tukang kayu @ Rp. 47,500.00 14,250.00 0.0300 org Kepala tukang kayu @ Rp. 50,000.00 1,500.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 21,450.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN LANGIT-LANGIT

SNI 1.0000 Langit-langit asbes semen tebal 4, 5 dan 6 mm2839-2008 1.1000 m2 Pelat asbes @ Rp. #N/A

0.0100 kg Paku triplek @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.0300 org Pekerja @ Rp. 36,000.00 1,080.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 4,915.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit asbes (1,00 x 1,00) m memakai plepet2007 1.1000 lbr Pelat asbes @ Rp. #N/A

2.6000 Plepet kayu @ Rp. #N/A 0.0100 kg Paku eternit @ Rp. #N/A 0.0100 kg Paku plepet @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.0300 org Pekerja @ Rp. 36,000.00 1,080.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 4,815.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit akustik ukuran (30 x 30) cm2839-2008 12.0000 lbr Akustik @ Rp. #N/A

0.0500 kg Paku triplek @ Rp. #N/A 0.1200 org Tukang kayu @ Rp. 47,500.00 5,700.00 0.0120 org Kepala tukang kayu @ Rp. 50,000.00 600.00 0.1200 org Pekerja @ Rp. 36,000.00 4,320.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 10,860.00

m1 Pasang talang ½ lingkaran D - 15 cm, seng plat BJLS 30 lebar 45 cm

m2

m2

m1

m2

Page 370: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit akustik ukuran (30 x 60) cm2839-2008 5.8000 lbr Akustik @ Rp. #N/A

0.0500 kg Paku triplek @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit akustik ukuran (60 x 120) cm2839-2008 1.5000 lbr Akustik @ Rp. #N/A

0.0500 kg Paku triplek @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit triplek ukuran (120 x 240) cm tebal 3mm, 4mm, dan 6 mm2839-2008 0.3750 lbr Triplek @ Rp. #N/A

0.0300 kg Paku triplek @ Rp. #N/A 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 9,050.00 JASA 10 %JUMLAHDIBULATKAN

Langit-langit lambreziring kayu

SNI 1.0000 Langit-langit lambriziring Kayu jati tebal 9 mm2839-2008 0.0150 m3 Kayu jati papan @ Rp. 22,000,000.00

0.0300 kg Paku triplek @ Rp. #N/A 0.8000 org Tukang kayu @ Rp. 47,500.00 38,000.00 0.0800 org Kepala tukang kayu @ Rp. 50,000.00 4,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 72,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit lambriziring Kayu jati lokal tebal 9 mm2839-2008 0.0150 m3 Kayu jati lokal papan @ Rp. #N/A

m2

m2

m2

m2

m2

Page 371: AHS 2008-Kota.xlsx

0.0300 kg Paku triplek @ Rp. #N/A 0.8000 org Tukang kayu @ Rp. 47,500.00 38,000.00 0.0800 org Kepala tukang kayu @ Rp. 50,000.00 4,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 72,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit lambriziring Kayu kamper tebal 9 mm2839-2008 0.0150 m3 Kayu kamper papan @ Rp. 5,500,000.00

0.0300 kg Paku triplek @ Rp. #N/A 0.8000 org Tukang kayu @ Rp. 47,500.00 38,000.00 0.0800 org Kepala tukang kayu @ Rp. 50,000.00 4,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 72,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit lambriziring Kayu bengkirai tebal 9 mm2839-2008 0.0150 m3 Kayu bengkirai papan @ Rp. 6,000,000.00

0.0300 kg Paku triplek @ Rp. #N/A 0.8000 org Tukang kayu @ Rp. 47,500.00 38,000.00 0.0800 org Kepala tukang kayu @ Rp. 50,000.00 4,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 72,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit lambriziring Kayu kruing tebal 9 mm2839-2008 0.0150 m3 Kayu kruing papan @ Rp. 4,750,000.00

0.0300 kg Paku triplek @ Rp. #N/A 0.8000 org Tukang kayu @ Rp. 47,500.00 38,000.00 0.0800 org Kepala tukang kayu @ Rp. 50,000.00 4,000.00 0.8000 org Pekerja @ Rp. 36,000.00 28,800.00 0.0400 org Mandor @ Rp. 40,000.00 1,600.00

JUMLAH ( BELUM PPN ) 72,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit gypsum board ukuran (1200 x 2400 x 9) mm2839-2008 0.3640 lbr Gypsum board 9 mm @ Rp. #N/A

0.1100 kg Paku skrup @ Rp. 10,000.00 0.0500 org Tukang kayu @ Rp. 47,500.00 2,375.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 6,425.00 JASA 10 %JUMLAH

m2

m2

m2

m2

Page 372: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasang list plafond gypsum profil

2839-2008 1.0500 List gypsum profil @ Rp. #N/A 0.1500 kg Tepung gypsum @ Rp. 3,500.00 0.0600 org Tukang kayu @ Rp. 47,500.00 2,850.00 0.0060 org Kepala tukang kayu @ Rp. 50,000.00 300.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 5,430.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Langit-langit akustik ukuran 60 x 120 cm + rangka alumunium

2839-2008 3.6000 Profil alumunium "T" @ Rp. 20,000.00 0.1500 kg Kawat diameter 4 mm @ Rp. #N/A 1.0500 bh Ramset @ Rp. #N/A 1.5000 lbr Akustic 60 x 120 cm @ Rp. #N/A 0.5000 org Tukang besi @ Rp. 45,000.00 22,500.00 0.0500 org Kepala tukang besi @ Rp. 47,500.00 2,375.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 43,875.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 List langit-langit kayu profil

2839-2008 1.0500 List kayu profil @ Rp. - 0.0100 kg Paku @ Rp. - 0.0500 org Tukang kayu @ Rp. 47,500.00 2,375.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 4,545.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, Kayu jati

2007 0.0120 Kayu jati balok @ Rp. #N/A 0.1000 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, Kayu jati lokal

2007 0.0120 Kayu jati lokal @ Rp. #N/A 0.1000 kg Paku biasa 2" - 5" @ Rp. #N/A

m1

m1

m2

m1

m1

m1

m2

m3

m2

m3

Page 373: AHS 2008-Kota.xlsx

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, Kayu kamper

2007 0.0120 Kayu kamper @ Rp. - 0.1000 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, Kayu kruing

2007 0.0120 Kayu kruing balok @ Rp. 4,350,000.00 0.1000 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (1,00 x 1,00) m, Kayu bengkirai

2007 0.0120 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1000 kg Paku biasa 2" - 5" @ Rp. #N/A 0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,825.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 120) cm, Kayu jati

2007 0.0130 Kayu jati balok @ Rp. #N/A 0.1200 kg Paku @ Rp. - 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 JASA 10 %JUMLAH

m2

m3

m2

m3

m2

m3

m2

m3

Page 374: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 120) m, Kayu jati lokal

2007 0.0130 Kayu jati lokal @ Rp. #N/A 0.1200 kg Paku @ Rp. - 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 120) m, Kayu kamper

2007 0.0130 Kayu kamper @ Rp. - 0.1200 kg Paku @ Rp. - 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 120) m, Kayu kruing

2007 0.0130 Kayu kruing balok @ Rp. 4,350,000.00 0.1200 kg Paku @ Rp. - 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala tukang kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang rangka langit-langit (60 x 120) m, Kayu bengkirai

2007 0.0130 Kayu bengkirai balok @ Rp. 5,750,000.00 0.1200 kg Paku @ Rp. - 0.2700 org Tukang kayu @ Rp. 47,500.00 12,825.00 0.0270 org Kepala Tukang Kayu @ Rp. 50,000.00 1,350.00 0.1700 org Pekerja @ Rp. 36,000.00 6,120.00 0.0085 org Mandor @ Rp. 40,000.00 340.00

JUMLAH ( BELUM PPN ) 20,635.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Langit-langit rangka hollow

4.5000 Rangka hollow 4x4 cm @ Rp. #N/A 0.0400 kg Paku skrup @ Rp. 10,000.00 5.0000 Kawat penggantung @ Rp. #N/A 0.3200 org Tukang kayu @ Rp. 47,500.00 15,200.00

m2

m3

m2

m3

m2

m3

m2

m3

m2

m1

m1

Page 375: AHS 2008-Kota.xlsx

0.0320 org Kepala tukang kayu @ Rp. 50,000.00 1,600.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 22,120.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN ATAP

SNI 1.0000 Pasang genteng paris2007 25.0000 bh Genteng paris @ Rp. 1,100.00

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang genteng paris untuk rumah tingkat2007 25.0000 bh Genteng paris @ Rp. 1,100.00

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 2007 9.0000 bh Genteng beton natural @ Rp. #N/A

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 2007 9.0000 bh Genteng beton natural @ Rp. #N/A

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 2007 9.0000 bh Genteng beton Warna @ Rp. #N/A

m2

m2

m2 Pasang genteng beton besar Natural ( isi 9 / m2 )

m2 Pasang genteng beton besar Natural ( isi 9 / m2 ) untuk rumah tingkat

m2 Pasang genteng beton besar Warna ( isi 9 / m2 )

Page 376: AHS 2008-Kota.xlsx

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 2007 9.0000 bh Genteng beton Warna @ Rp. #N/A

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang genteng keramik berglasir KIA, Kanmuri Natural2007 14.5000 bh Genteng keramik KIA natural @ Rp. #N/A

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 12,300.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat2007 14.5000 bh Genteng beton natural @ Rp. #N/A

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala Tukang Batu @ Rp. 45,000.00 450.00 0.3000 org Pekerja @ Rp. 36,000.00 10,800.00 0.0150 org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 16,100.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang bubungan genteng paris2007 5.0000 bh Bubungan genteng paris @ Rp. #N/A

0.0152 Kapur pasang @ Rp. 72,500.00

0.0152 Pasir pasang @ Rp. #N/A 1.5240 kg PC @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

m2 Pasang genteng beton besar Warna ( isi 9 / m2 ) untuk rumah tingkat

m2

m2

m1

m3

m3

Page 377: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang bubungan genteng beton Natural2007 5.0000 bh Bubungan genteng beton natural @ Rp. #N/A

0.0152 Kapur pasang @ Rp. 72,500.00

0.0152 Pasir pasang @ Rp. #N/A 1.5240 kg PC @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang bubungan genteng beton Warna2007 4.0000 bh Bubungan genteng beton warna @ Rp. #N/A

0.0152 Kapur pasang @ Rp. 72,500.00

0.0152 Pasir pasang @ Rp. #N/A 1.5240 kg PC @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang bubungan genteng keramik berglasir KIA, Kanmuri Natural2007 4.0000 bh Bubungan gent.krmk KIA natural @ Rp. #N/A

0.0152 Kapur pasang @ Rp. 72,500.00

0.0152 Pasir pasang @ Rp. #N/A 1.5240 kg PC @ Rp. #N/A 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00 0.0200 org Kepala Tukang Batu @ Rp. 45,000.00 900.00 0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 0.0200 org Mandor @ Rp. 40,000.00 800.00

JUMLAH ( BELUM PPN ) 24,600.00 JASA 10 %JUMLAHDIBULATKAN

1.0000 Pasang atap asbes gelombang (2,5 x 0,92 m) x 5 mmSNI 0.5000 lbr Asbes gelombang @ Rp. #N/A2007 0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A

0.0750 org Tukang kayu @ Rp. 47,500.00 3,562.50 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 9,322.50 JASA 10 %JUMLAHDIBULATKAN

m1

m3

m3

m1

m3

m3

m1

m3

m3

m2

Page 378: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang atap sbes gelombang (2,25 x 0,92 m) x 5 mm2007 0.6000 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0750 org Tukang kayu @ Rp. 47,500.00 3,562.50 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 9,322.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,00 x 0,92 m) x 5 mm2007 0.6000 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (1,80 x 0,92 m) x 5 mm2007 0.7500 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (300 x 1,05 m) x 4 mm2007 0.3500 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,7 x 1,05 m) x 4 mm2007 0.4200 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,995.00

m2

m2

m2

m2

m2

Page 379: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,40 x 1,05 m) x 4 mm2007 0.4400 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,10 x 1,05 m) x 4 mm2007 0.5100 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (1,50 x 1,05 m) x 4 mm2007 0.8000 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (3,00 x 1,08 m) x 6 mm2007 0.3700 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,70 x 1,08 m) x 6 mm2007 0.3800 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50

m2

m2

m2

m2

m2

Page 380: AHS 2008-Kota.xlsx

0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap sbes gelombang (2,40 x 1,08 m) x 6 mm2007 0.4600 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (2,10 x 1,08 m) x 6 mm2007 0.4900 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap asbes gelombang (1,80 x 1,08 m) x 6 mm2007 0.5700 lbr Asbes gelombang @ Rp. #N/A

0.1200 kg Paku pancing 60 x 230 @ Rp. #N/A 0.0670 org Tukang kayu @ Rp. 47,500.00 3,182.50 0.0070 org Kepala tukang kayu @ Rp. 50,000.00 350.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,852.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang bubung stel gelombang 0,92 m2007 2.4000 lbr Bubung stel gelombang @ Rp. #N/A

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m1

Page 381: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang nok stel gelombang 1,05 m2007 2.1000 lbr Nok stel gelombang @ Rp. #N/A

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel gelombang 1,08 m2007 2.0500 lbr Nok stel gelombang @ Rp. #N/A

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok paten 0,92 m2007 1.2000 lbr Nok paten @ Rp. #N/A

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok paten 1,05 m2007 1.2000 lbr Nok paten @ Rp. #N/A

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok paten 1,08 m2007 1.2000 lbr Nok paten @ Rp. #N/A

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50

m1

m1

m1

m1

m1

Page 382: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel rata 0,92 m2007 1.1000 lbr Nok stel rata @ Rp. 25,000.00

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 11,535.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok stel rata 1,09 m2007 1.1000 lbr Nok stel rata @ Rp. 25,000.00

6.0000 bh Paku sekrup 3,5" @ Rp. #N/A 0.1250 org Tukang kayu @ Rp. 47,500.00 5,937.50 0.0130 org Kepala tukang kayu @ Rp. 50,000.00 650.00 0.0840 org Pekerja @ Rp. 36,000.00 3,024.00 0.0040 org Mandor @ Rp. 40,000.00 160.00

JUMLAH ( BELUM PPN ) 9,771.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok atap seng2007 0.3000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. #N/A

0.0400 kg Paku biasa 1/2" - 1" @ Rp. #N/A 0.0700 org Tukang kayu @ Rp. 47,500.00 3,325.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 9,365.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap genteng metal zinc alume type prima roof

2007 1.0200 Genteng metal @ Rp. #N/A 0.2000 kg Paku anti karat @ Rp. 25,000.00 0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 12,490.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap metal gelombanmg

2007 1.0200 Atap metal gelombang t 3,5 mm @ Rp. #N/A 4.0000 bh Paku/skrup atap anti karat @ Rp. #N/A

m1

m1

m1

m2

m2

m2

m2

Page 383: AHS 2008-Kota.xlsx

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 12,490.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok genteng metal U type prima roof2007 1.1000 bh Nok metal @ Rp. #N/A

0.0500 kg Paku anti karat @ Rp. 25,000.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0130 org Mandor @ Rp. 40,000.00 520.00

JUMLAH ( BELUM PPN ) 17,395.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang atap alumunium

2007 1.0500 Atap alumunium gelombang tebal 0, @ Rp. #N/A 0.0200 kg Paku hak panjang 15 cm @ Rp. 9,500.00 0.7500 org Tukang kayu @ Rp. 47,500.00 35,625.00 0.0080 org Kepala tukang kayu @ Rp. 50,000.00 400.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 41,665.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang nok alumunium

2007 1.2000 Nok standar 40 cm 18 SWG 22 @ Rp. #N/A 0.0400 kg Paku hak panjang 15 cm @ Rp. 9,500.00 1.0000 org Tukang kayu @ Rp. 47,500.00 47,500.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 52,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang alumunium foil / sisalation

2007 1.0500 Sisalation / alumunium foil @ Rp. #N/A 0.0500 org Tukang kayu @ Rp. 47,500.00 2,375.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0080 org Mandor @ Rp. 40,000.00 320.00

JUMLAH ( BELUM PPN ) 8,345.00 JASA 10 %JUMLAHDIBULATKAN

m1

m2

m2

m1

m1

m2

m2

Page 384: AHS 2008-Kota.xlsx

SNI 1.0000 Pasang atap polikarbonat

2007 1.0500 Plykarbhonat @ Rp. #N/A 7.0000 kg Besi rangka @ Rp. #N/A 9.0000 bh Paku sekrup @ Rp. #N/A 0.5000 org Tukang besi @ Rp. 45,000.00 22,500.00 0.0500 org Kepala tukang besi @ Rp. 47,500.00 2,375.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 42,975.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN CAT-CATAN

SNI 10.0000 Mengecat kerb 3 kali2007 4.2500 kg Cat emco @ Rp. #N/A

0.5700 ltr Minyak cat @ Rp. 14,000.00 3.0000 org Tukang cat @ Rp. 42,500.00 127,500.00 0.3000 org Kepala Tukang Cat @ Rp. 45,000.00 13,500.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

217,000.00

21,700.00 JASA 10 %JUMLAHDIBULATKAN

- JASA 10 %JUMLAHDIBULATKAN

- JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengikis / mengerok permukaan cat tembok lama2007 0.0500 kg Soda api @ Rp. 25,000.00

0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 5,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerok karat cat lama permukaan baja dengan cara manual2007 0.0500 kg Sabun @ Rp. #N/A

0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 5,500.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

TIAP 1 M2 ( 3 kali )

TIAP 1 M2 ( 2 kali )

TIAP 1 M2 ( 1 kali )

m2

m2

Page 385: AHS 2008-Kota.xlsx

SNI 1.0000 Mendempul dan menggosok kayu2007 0.0800 kg Dempul jadi @ Rp. #N/A

0.0200 kg Minyak cat @ Rp. 14,000.00 0.0100 kg Batu apung @ Rp. #N/A 0.0400 org Tukang cat @ Rp. 42,500.00 1,700.00 0.0040 org Kepala tukang cat @ Rp. 45,000.00 180.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,420.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang kayu lama2007 0.1500 kg Plamir @ Rp. #N/A

0.1700 kg Cat dasar @ Rp. #N/A 0.1700 kg Cat penutup @ Rp. #N/A 0.0750 org Tukang cat @ Rp. 42,500.00 3,187.50 0.0075 org Kepala tukang cat @ Rp. 45,000.00 337.50 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,145.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup2007 0.2000 kg Cat meni @ Rp. #N/A

0.1500 kg Plamir @ Rp. #N/A 0.1700 kg Cat dasar @ Rp. #N/A 0.2600 kg Cat penutup @ Rp. #N/A 0.0900 org Tukang cat @ Rp. 42,500.00 3,825.00 0.0060 org Kepala tukang cat @ Rp. 45,000.00 270.00 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 6,715.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup2007 0.2000 kg Cat meni @ Rp. #N/A

0.1500 kg Plamir @ Rp. #N/A 0.1700 kg Cat dasar @ Rp. #N/A 0.3500 kg Cat penutup @ Rp. #N/A 0.1050 org Tukang cat @ Rp. 42,500.00 4,462.50 0.0040 org Kepala tukang cat @ Rp. 45,000.00 180.00 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 7,262.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan teak oil2007 0.3600 ltr Teak oil @ Rp. #N/A

m2

m2

m2

m2

m2

Page 386: AHS 2008-Kota.xlsx

0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0630 org Kepala tukang cat @ Rp. 45,000.00 2,835.00 0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 7,052.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan politur2007 0.1500 ltr Politur @ Rp. #N/A

0.3720 ltr Politur jadi @ Rp. 40,000.00 2.0000 lbr Amplas @ Rp. 3,500.00 0.0600 org Tukang cat @ Rp. 42,500.00 2,550.00 0.0160 org Kepala tukang cat @ Rp. 45,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,370.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan cat residu atau ter2007 0.3500 ltr Residu atau ter @ Rp. #N/A

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0060 org Mandor @ Rp. 40,000.00 240.00

JUMLAH ( BELUM PPN ) 3,840.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pelaburan bidang kayu dengan vernis2007 0.1500 ltr Vernis @ Rp. #N/A

0.0500 kg Dempul @ Rp. #N/A 0.1000 lbr Amplas @ Rp. 3,500.00 0.0100 bh Kuas @ Rp. #N/A 0.1600 org Tukang cat @ Rp. 42,500.00 6,800.00 0.0160 org Kepala tukang cat @ Rp. 45,000.00 720.00 0.1600 org Pekerja @ Rp. 36,000.00 5,760.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 13,380.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)2007 0.1000 kg Plamir tembok @ Rp. #N/A

0.1000 kg Cat dasar @ Rp. #N/A 0.2600 kg Cat penutup 2 x @ Rp. #N/A 0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0063 org Kepala tukang cat @ Rp. 45,000.00 283.50 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,781.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

Page 387: AHS 2008-Kota.xlsx

SNI 1.0000 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)2007 0.1200 kg Cat dasar @ Rp. #N/A

0.1800 kg Cat penutup 2 x @ Rp. #N/A 0.0420 org Tukang cat @ Rp. 42,500.00 1,785.00 0.0042 org Kepala tukang cat @ Rp. 45,000.00 189.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,082.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan tembok tidak terlindung dari panas dan hujan2007 0.1000 kg Cat alkali resisting primer @ Rp. #N/A

0.3600 kg Cat ICI Weathershield @ Rp. #N/A 0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0063 org Kepala tukang cat @ Rp. 45,000.00 283.50 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,781.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Melabur tembok dengan kalkarium2007 0.1000 kg Kalkarium @ Rp. 8,500.00

0.0420 org Tukang cat @ Rp. 42,500.00 1,785.00 0.0042 org Kepala tukang cat @ Rp. 45,000.00 189.00 0.0280 org Pekerja @ Rp. 36,000.00 1,008.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,082.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Melabur tembok dengan kapur sirih2007 0.1000 lbr Amplas @ Rp. 3,500.00

0.2500 ikat Alang-alang @ Rp. 500.00

0.0020 Perancah kayu @ Rp. #N/A 0.1500 kg Kapur sirih @ Rp. 138,000.00 0.0010 org Tukang cat @ Rp. 42,500.00 42.50 0.0001 org Kepala tukang cat @ Rp. 45,000.00 4.50 0.1500 org Pekerja @ Rp. 36,000.00 5,400.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 5,547.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Melabur tembok tembok lama dengan kapur sirih (untuk pemeliharaan)

2007 0.0020 Perancah kayu @ Rp. #N/A 0.3000 kg Kapur sirih @ Rp. 138,000.00 0.0050 org Tukang cat @ Rp. 42,500.00 212.50 0.0005 org Kepala tukang cat @ Rp. 45,000.00 22.50

m2

m2

m2

m2

m3

m2

m3

Page 388: AHS 2008-Kota.xlsx

0.0400 org Pekerja @ Rp. 36,000.00 1,440.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 1,775.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecatan bidang besi ( 3 x )2007 0.1670 kg Cat meni besi @ Rp. #N/A

0.2000 kg Cat besi @ Rp. #N/A 0.1500 ltr Thinner @ Rp. 14,000.00 0.1050 org Tukang cat @ Rp. 42,500.00 4,462.50 0.0040 org Kepala tukang cat @ Rp. 45,000.00 180.00 0.0700 org Pekerja @ Rp. 36,000.00 2,520.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 7,262.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 m2 Melamin2007 0.2000 Cat tembok melamin @ Rp. #N/A

0.0150 Kuas 3" @ Rp. #N/A 0.2000 Pekerja @ Rp. 36,000.00 7,200.00 0.1000 Tukang cat @ Rp. 42,500.00 4,250.00 0.0050 Kep. Tukang cat @ Rp. #N/A #N/A 0.0005 Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pemasangan wall paper

2007 1.2000 Wall paper @ Rp. 40,000.00 0.2000 kg Perekat @ Rp. #N/A 0.2000 org Tukang cat @ Rp. 42,500.00 8,500.00 0.0020 org Kepala tukang cat @ Rp. 45,000.00 90.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 9,410.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengecacatan permukaan baja dengan meni besi2007 0.1000 kg Meni besi Zinchromate @ Rp. #N/A

0.0100 bh Kuas @ Rp. #N/A 0.2000 org Tukang cat @ Rp. 42,500.00 8,500.00 0.0200 org Kepala tukang cat @ Rp. 45,000.00 900.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 10,520.00 JASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

Page 389: AHS 2008-Kota.xlsx

SNI 1.0000 Pengecacatan permukaan baja dengan meni besi memakai perancah2007 0.1000 kg Meni besi Zinchromate @ Rp. #N/A

0.0100 bh Kuas @ Rp. #N/A

0.0020 Perancah kayu @ Rp. #N/A 0.2250 org Tukang cat @ Rp. 42,500.00 9,562.50 0.0225 org Kepala tukang cat @ Rp. 45,000.00 1,012.50 0.2250 org Pekerja @ Rp. 36,000.00 8,100.00 0.0075 org Mandor @ Rp. 40,000.00 300.00

JUMLAH ( BELUM PPN ) 18,975.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pengetiran kayu ( 2 x )2007 0.3500 kg Tir @ Rp. #N/A

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 3,800.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pekerjaan cat duco 3 x 2007 0.4250 kg Cat duco @ Rp. 70,000.00

0.0570 ltr Thinner @ Rp. 14,000.00 0.1000 lbr Amplas @ Rp. 3,500.00 350.00 0.3000 org Tukang cat @ Rp. 42,500.00 12,750.00 0.0300 org Kepala Tukang Cat @ Rp. 45,000.00 1,350.00 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 22,050.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengecat genteng2007 0.3600 kg Cat genteng air ICI Weathershield @ Rp. 45,000.00

0.0630 org Tukang cat @ Rp. 42,500.00 2,677.50 0.0063 org Kepala Tukang Cat @ Rp. 45,000.00 283.50 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH 3,781.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN BONGKARAN

SNI 1.0000 Membongkar pasangan batu kali2007 4.0000 org Tukang batu @ Rp. 42,500.00 170,000.00

0.4000 org Pekerja @ Rp. 36,000.00 14,400.00 JUMLAH ( BELUM PPN ) 184,400.00 JASA 10 %JUMLAHDIBULATKAN

m2

m3

m2

m2

m2

m3

Page 390: AHS 2008-Kota.xlsx

SNI 1.0000 Membongkar pasangan batu merah dan membersihkan2007 2.0000 org Tukang batu @ Rp. 42,500.00 85,000.00

0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 JUMLAH ( BELUM PPN ) 88,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membongkar beton bertulang dan membersihkan2007 0.2000 org Tukang batu @ Rp. 42,500.00 8,500.00

8.0000 org Pekerja @ Rp. 36,000.00 288,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 300,500.00 JASA 10 %JUMLAHDIBULATKAN

SNI 10.0000 Pekerjaan bongkar lantai tegel untuk dipergunakan lagi2007 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00

0.1000 org Mandor @ Rp. 40,000.00 4,000.00 JUMLAH ( BELUM PPN ) 76,000.00

TIAP 1M2 ( BELUM PPN ) 7,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 10.0000 Mengupas plesteran lama2007 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00

0.1250 org Mandor @ Rp. 40,000.00 5,000.00 JUMLAH ( BELUM PPN ) 50,000.00

TIAP 1M2 ( BELUM PPN ) 5,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 10.0000 Membongkar genteng / sirap untuk dipergunakan lagi2007 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00

0.1000 org Mandor @ Rp. 40,000.00 4,000.00 JUMLAH ( BELUM PPN ) 76,000.00

TIAP 1M2 ( BELUM PPN ) 7,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 10.0000 Membongkar atap seng2007 0.5000 org Tukang besi @ Rp. 45,000.00 22,500.00

1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 JUMLAH ( BELUM PPN ) 58,500.00

TIAP 1M2 ( BELUM PPN ) 5,850.00 JASA 10 %JUMLAH

m3

m3

m2

m2

m2

m2

Page 391: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 10.0000 Membongkar usuk / reng dipakai lagi2007 0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00

0.0600 org Kepala Tukang Kayu @ Rp. 50,000.00 3,000.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 107,500.00

TIAP 1M2 ( BELUM PPN ) 10,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 10.0000 Membongkar usuk / reng tidak dipakai lagi2007 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00

0.1000 org Mandor @ Rp. 40,000.00 4,000.00 JUMLAH ( BELUM PPN ) 76,000.00

TIAP 1M2 ( BELUM PPN ) 7,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi2007 6.0000 org Tukang kayu @ Rp. 47,500.00 285,000.00

0.6000 org Kepala Tukang Kayu @ Rp. 50,000.00 30,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 467,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi2007 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00

0.2000 org Mandor @ Rp. 40,000.00 8,000.00 JUMLAH ( BELUM PPN ) 44,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan kembali bangunan kayu yang telah dibongkar2007 12.0000 org Tukang kayu @ Rp. 47,500.00 570,000.00

1.2000 org Kepala Tukang Kayu @ Rp. 50,000.00 60,000.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 782,000.00 JASA 10 %JUMLAHDIBULATKAN

ANALISA SUPLEMEN

SNI 1.0000 Pasang pipa beton oval dia. 25/37,5 dalam 0 - 1 m

m2

m2

m3

m3

m3

m1

Page 392: AHS 2008-Kota.xlsx

2007 1.0000 bh Pipa beton oval @ Rp. #N/A0.7500 org Pekerja @ Rp. 36,000.00 27,000.00 0.1500 org Tukang batu @ Rp. 42,500.00 6,375.00 0.0150 Org Mandor @ Rp. 40,000.00 600.00

JUMLAH ( BELUM PPN ) 33,975.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang pipa beton oval dia. 25/37,5 dalam 1 - 2 m2007 1 bh Pipa beton oval @ Rp. #N/A

1.5 org Pekerja @ Rp. 36,000.00 54,000.00 0.15 org Tukang batu @ Rp. 42,500.00 6,375.00

0.015 Org Mandor @ Rp. 40,000.00 600.00 JUMLAH ( BELUM PPN ) 60,975.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN SANITASI

SNI 1.0000 bh Memasang kloset duduk/monoblock2007 1.0000 bh Kloset duduk / monoblock @ Rp. #N/A

6% x Harga kloset (Perlengkapan) @ Rp. #N/A 1.1000 org Tukang batu @ Rp. 42,500.00 46,750.00 0.0010 org Kepala tukang batu @ Rp. 45,000.00 45.00 3.3000 org Pekerja @ Rp. 36,000.00 118,800.00 0.1600 org Mandor @ Rp. 40,000.00 6,400.00

JUMLAH ( BELUM PPN ) 171,995.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang kloset jongkok porselen2007 1.0000 bh Kloset jongkok porselen @ Rp. #N/A

6.0000 kg PC @ Rp. #N/A

0.0100 Pasir pasang @ Rp. #N/A 1.5000 org Tukang batu @ Rp. 42,500.00 63,750.00 1.5000 org Kepala tukang batu @ Rp. 45,000.00 67,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1600 org Mandor @ Rp. 40,000.00 6,400.00

JUMLAH ( BELUM PPN ) 173,650.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang kloset jongkok teraso2007 1.0000 bh Kloset jongkok teraso @ Rp. 85,000.00

7.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. #N/A 6.0000 kg PC @ Rp. #N/A

0.0100 Pasir pasang @ Rp. #N/A 1.5000 org Tukang batu @ Rp. 42,500.00 63,750.00 0.3000 org Kepala tukang batu @ Rp. 45,000.00 13,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1100 org Mandor @ Rp. 40,000.00 4,400.00

JUMLAH ( BELUM PPN ) 117,650.00

m1

m3

m3

Page 393: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang urinoir2007 1.0000 bh Urinoir @ Rp. -

30% x Harga urinoir (Perlengkapan) @ Rp. #N/A 6.0000 kg PC @ Rp. #N/A

0.0100 Pasir pasang @ Rp. #N/A 1.0000 org Tukang batu @ Rp. 42,500.00 42,500.00 0.1000 org Kepala tukang batu @ Rp. 45,000.00 4,500.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 87,000.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang wastafel2007 1.0000 bh Wastafel @ Rp. -

12% x Harga wastafel (Perlengkapan) @ Rp. #N/A 6.0000 kg PC @ Rp. #N/A

0.0100 Pasir pasang @ Rp. #N/A 1.4500 org Tukang batu @ Rp. 42,500.00 61,625.00 0.1500 org Kepala tukang batu @ Rp. 45,000.00 6,750.00 1.2000 org Pekerja @ Rp. 36,000.00 43,200.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 115,575.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh2007 1.0000 bh Bak fiberglass @ Rp. #N/A

18% x Harga bak(Perlengkapan) @ Rp. #N/A 2.7000 org Tukang batu @ Rp. 42,500.00 114,750.00 0.5400 org Kepala tukang batu @ Rp. 45,000.00 24,300.00 1.8000 org Pekerja @ Rp. 36,000.00 64,800.00 0.1100 org Mandor @ Rp. 40,000.00 4,400.00

JUMLAH ( BELUM PPN ) 208,250.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang badkip porselen2007 1.0000 bh Badkip @ Rp. 350,000.00

20% x Harga badkip (Perlengkapan) @ Rp. #N/A 0.0750 org Tukang batu @ Rp. 42,500.00 3,187.50 0.7500 org Kepala tukang batu @ Rp. 45,000.00 33,750.00

org Pekerja @ Rp. 36,000.00 - 0.2500 org Mandor @ Rp. 40,000.00 10,000.00

JUMLAH ( BELUM PPN ) 46,937.50 JASA 10 %JUMLAHDIBULATKAN

m3

m3

Memasang bak mandi fiberglass volume 0,30 m3

Page 394: AHS 2008-Kota.xlsx

SNI 1.0000 bh2007 1.0000 bh Bak fiberglass @ Rp. #N/A

12% x Harga bak (Perlengkapan) @ Rp. #N/A 4.5000 org Tukang batu @ Rp. 42,500.00 191,250.00 0.9000 org Kepala tukang batu @ Rp. 45,000.00 40,500.00 3.0000 org Pekerja @ Rp. 36,000.00 108,000.00 0.9000 org Mandor @ Rp. 40,000.00 36,000.00

JUMLAH ( BELUM PPN ) 375,750.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm2007 1.6000 bh Pipa tanah @ Rp. #N/A

0.6800 kg PC @ Rp. #N/A

0.0130 Pasir pasang @ Rp. #N/A

0.0110 Pasir urug @ Rp. #N/A 0.0300 org Tukang batu @ Rp. 42,500.00 1,275.00 0.0030 org Kepala tukang batu @ Rp. 45,000.00 135.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 3,670.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm2007 1.6000 bh Pipa tanah @ Rp. #N/A

0.8700 kg PC @ Rp. #N/A

0.0140 Pasir pasang @ Rp. #N/A

0.1400 Pasir urug @ Rp. #N/A 0.0400 org Tukang batu @ Rp. 42,500.00 1,700.00 0.0040 org Kepala tukang batu @ Rp. 45,000.00 180.00 0.0800 org Pekerja @ Rp. 36,000.00 2,880.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 5,040.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa beton, diameter 15 cm - 20 cm2007 1.1000 bh Pipa beton @ Rp. #N/A

16.0000 bh Batu bata @ Rp. #N/A 3.9200 kg PC @ Rp. #N/A

0.0560 Pasir pasang @ Rp. #N/A

0.0240 Pasir urug @ Rp. #N/A 0.0700 org Tukang batu @ Rp. 42,500.00 2,975.00 0.0070 org Kepala tukang batu @ Rp. 45,000.00 315.00 0.1400 org Pekerja @ Rp. 36,000.00 5,040.00 0.0070 org Mandor @ Rp. 40,000.00 280.00

JUMLAH ( BELUM PPN ) 8,610.00 JASA 10 %JUMLAHDIBULATKAN

Memasang bak fiberglass volume 1 m3 air

m1

m3

m3

m1

m3

m3

m1

m3

m3

Page 395: AHS 2008-Kota.xlsx

SNI 1.0000 Memasang pipa beton, diameter 30 cm - 100 cm2007 1.1000 bh Pipa beton @ Rp. #N/A

330.0000 bh Batu bata @ Rp. #N/A 10.3000 kg PC @ Rp. #N/A

0.0610 Pasir pasang @ Rp. #N/A

0.0690 Pasir urug @ Rp. #N/A 0.1900 org Tukang batu @ Rp. 42,500.00 8,075.00 0.0190 org Kepala tukang batu @ Rp. 45,000.00 855.00 0.3800 org Pekerja @ Rp. 36,000.00 13,680.00 0.0190 org Mandor @ Rp. 40,000.00 760.00

JUMLAH ( BELUM PPN ) 23,370.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm2007 87.0000 bh Batu bata @ Rp. #N/A

44.0000 kg PC @ Rp. #N/A

0.0700 Pasir pasang @ Rp. #N/A

0.0700 Batu kerikil @ Rp. #N/A1.6000 kg Besi beton @ Rp. -

0.0600 Pasir beton @ Rp. #N/A 1.0150 org Tukang batu @ Rp. 42,500.00 43,137.50 0.0015 org Kepala tukang batu @ Rp. 45,000.00 67.50 3.2000 org Pekerja @ Rp. 36,000.00 115,200.00 0.0160 org Mandor @ Rp. 40,000.00 640.00

JUMLAH ( BELUM PPN ) 159,045.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm2007 150.0000 bh Batu bata @ Rp. #N/A

77.0000 kg PC @ Rp. #N/A

0.1300 Pasir pasang @ Rp. #N/A

0.0200 Batu kerikil @ Rp. #N/A2.6000 kg Besi beton @ Rp. -

0.0900 Pasir beton @ Rp. #N/A 0.4730 org Tukang batu @ Rp. 42,500.00 20,102.50 0.0470 org Kepala tukang batu @ Rp. 45,000.00 2,115.00 1.4200 org Pekerja @ Rp. 36,000.00 51,120.00 0.0710 org Mandor @ Rp. 40,000.00 2,840.00

JUMLAH ( BELUM PPN ) 76,177.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm2007 222.0000 bh Batu bata @ Rp. #N/A

114.0000 kg PC @ Rp. #N/A

0.1840 Pasir pasang @ Rp. #N/A

0.0330 Batu kerikil @ Rp. #N/A4.8500 kg Besi beton @ Rp. -

0.1200 Pasir beton @ Rp. #N/A

m1

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 396: AHS 2008-Kota.xlsx

0.7200 org Tukang batu @ Rp. 42,500.00 30,600.00 0.0720 org Kepala tukang batu @ Rp. 45,000.00 3,240.00 2.1600 org Pekerja @ Rp. 36,000.00 77,760.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) 115,600.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 1/2"

2007 1.2000 Pipa galvanis @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0540 org Pekerja @ Rp. 36,000.00 1,944.00 0.0270 org Mandor @ Rp. 40,000.00 1,080.00

JUMLAH ( BELUM PPN ) 7,254.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 3/4"

2007 1.2000 Pipa galvanis @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0540 org Pekerja @ Rp. 36,000.00 1,944.00 0.0270 org Mandor @ Rp. 40,000.00 1,080.00

JUMLAH ( BELUM PPN ) 7,254.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 1"

2007 1.2000 Pipa galvanis @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0540 org Pekerja @ Rp. 36,000.00 1,944.00 0.0270 org Mandor @ Rp. 40,000.00 1,080.00

JUMLAH ( BELUM PPN ) 7,254.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 1 1/2"

2007 1.2000 Pipa galvanis @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.1800 org Tukang batu @ Rp. 42,500.00 7,650.00 0.0180 org Kepala tukang batu @ Rp. 45,000.00 810.00 0.1080 org Pekerja @ Rp. 36,000.00 3,888.00 0.0054 org Mandor @ Rp. 40,000.00 216.00

JUMLAH ( BELUM PPN ) 12,564.00 JASA 10 %JUMLAH

m1

m1

m1

m1

m1

m1

m1

m1

Page 397: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 3"

2007 1.2000 Pipa galvanis @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.1800 org Tukang batu @ Rp. 42,500.00 7,650.00 0.0180 org Kepala tukang batu @ Rp. 45,000.00 810.00 0.1080 org Pekerja @ Rp. 36,000.00 3,888.00 0.0054 org Mandor @ Rp. 40,000.00 216.00

JUMLAH ( BELUM PPN ) 12,564.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa galvanis diameter 4"

2007 1.2000 Pipa galvanis @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.2250 org Tukang batu @ Rp. 42,500.00 9,562.50 0.0225 org Kepala tukang batu @ Rp. 45,000.00 1,012.50 0.1350 org Pekerja @ Rp. 36,000.00 4,860.00 0.0068 org Mandor @ Rp. 40,000.00 272.00

JUMLAH ( BELUM PPN ) 15,707.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1/2"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 3/4"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00

m1

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 398: AHS 2008-Kota.xlsx

0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1 1/2"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 2"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0900 org Tukang batu @ Rp. 42,500.00 3,825.00 0.0090 org Kepala tukang batu @ Rp. 45,000.00 405.00 0.0544 org Pekerja @ Rp. 36,000.00 1,958.40 0.0027 org Mandor @ Rp. 40,000.00 108.00

JUMLAH ( BELUM PPN ) 6,296.40 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 2 1/2"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.0600 org Tukang batu @ Rp. 42,500.00 2,550.00 0.0060 org Kepala tukang batu @ Rp. 45,000.00 270.00 0.0360 org Pekerja @ Rp. 36,000.00 1,296.00 0.0018 org Mandor @ Rp. 40,000.00 72.00

JUMLAH ( BELUM PPN ) 4,188.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang pipa PVC tipe AW diameter 3"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.1350 org Tukang batu @ Rp. 42,500.00 5,737.50 0.0135 org Kepala tukang batu @ Rp. 45,000.00 607.50 0.0810 org Pekerja @ Rp. 36,000.00 2,916.00 0.0410 org Mandor @ Rp. 40,000.00 1,640.00

JUMLAH ( BELUM PPN ) 10,901.00 JASA 10 %JUMLAHDIBULATKAN

m1

m1

m1

m1

m1

m1

m1

m1

Page 399: AHS 2008-Kota.xlsx

SNI 1.0000 Memasang pipa PVC tipe AW diameter 4"

2007 1.2000 Pipa PVC @ Rp. #N/A35% x Harga pipa (Perlengkapan) @ Rp. #N/A

0.1350 org Tukang batu @ Rp. 42,500.00 5,737.50 0.0135 org Kepala tukang batu @ Rp. 45,000.00 607.50 0.0810 org Pekerja @ Rp. 36,000.00 2,916.00 0.0410 org Mandor @ Rp. 40,000.00 1,640.00

JUMLAH ( BELUM PPN ) 10,901.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak cuci piring stainless steel2007 1.0000 bh Bak cuci stainless steel @ Rp. 500,000.00

1.0000 set Water drain + asesories @ Rp. 200,000.00 0.3000 org Tukang batu @ Rp. 42,500.00 12,750.00 0.0300 org Kepala tukang batu @ Rp. 45,000.00 1,350.00 0.0300 org Pekerja @ Rp. 36,000.00 1,080.00 0.0015 org Mandor @ Rp. 40,000.00 60.00

JUMLAH ( BELUM PPN ) 15,240.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang bak cuci piring teraso2007 1.0000 bh Bak cuci teraso @ Rp. #N/A

1.0000 set Water drain + asesories @ Rp. 200,000.00 20.0000 kg PC @ Rp. #N/A

0.0500 Pasir pasang @ Rp. #N/A 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.0500 org Kepala tukang batu @ Rp. 45,000.00 2,250.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 25,400.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang kran diameter 3/4" atau 1/2"2007 1.0000 bh Kran air @ Rp. #N/A

0.0250 bh Seal tape @ Rp. 8,500.00 0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 5,260.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Memasang floor drain2007 1.0000 bh Floordrain @ Rp. 135,000.00

0.1000 org Tukang batu @ Rp. 42,500.00 4,250.00 0.0100 org Kepala tukang batu @ Rp. 45,000.00 450.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

m1

m1

m3

Page 400: AHS 2008-Kota.xlsx

JUMLAH ( BELUM PPN ) 5,260.00 JASA 10 %JUMLAHDIBULATKAN

PEKERJAAN KUNCI DAN KACA

SNI 1.0000 bh Pasang kunci tanam antik2007 1.0000 bh Kunci tanam antik @ Rp. 250,000.00

0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala tukang kayu @ Rp. 50,000.00 3,000.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 33,780.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang kunci tanam biasa2007 1.0000 bh Kunci tanam biasa @ Rp. 125,000.00

0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 24,810.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang kunci tanam kamar mandi2007 1.0000 bh Kunci tanam kamar mandi @ Rp. #N/A

0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 24,280.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang kunci tanam silinder2007 1.0000 bh Kunci silinder @ Rp. 75,000.00

0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0050 org Kepala tukang kayu @ Rp. 50,000.00 250.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0003 org Mandor @ Rp. 40,000.00 10.00

JUMLAH ( BELUM PPN ) 24,190.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang engsel pintu2007 1.0000 bh Engsel pintu @ Rp. 11,000.00

0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00

Page 401: AHS 2008-Kota.xlsx

0.0008 org Mandor @ Rp. 40,000.00 30.00 JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang engsel jendela kupu-kupu2007 1.0000 bh Engsel jendela @ Rp. 7,500.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 5,810.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang engsel angin2007 1.0000 bh Engsel angin @ Rp. 3,000.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( BELUM PPN ) 11,620.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang spring knip2007 1.0000 bh Spring knip @ Rp. 7,500.00

0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang kait angin2007 1.0000 bh Kait angin @ Rp. 3,000.00

0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang door closer2007 1.0000 bh Door closer @ Rp. 150,000.00

0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala tukang kayu @ Rp. 50,000.00 2,500.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 28,150.00

Page 402: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang kunci selot2007 1.0000 bh Kunci selot @ Rp. 50,000.00

0.2000 org Tukang kayu @ Rp. 47,500.00 9,500.00 0.0200 org Kepala tukang kayu @ Rp. 50,000.00 1,000.00 0.0200 org Pekerja @ Rp. 36,000.00 720.00 0.0010 org Mandor @ Rp. 40,000.00 40.00

JUMLAH ( BELUM PPN ) 11,260.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang pegangan pintu / door holder2007 1.0000 bh Door holder @ Rp. 15,000.00

0.5000 org Tukang kayu @ Rp. 47,500.00 23,750.00 0.0500 org Kepala tukang kayu @ Rp. 50,000.00 2,500.00 0.0500 org Pekerja @ Rp. 36,000.00 1,800.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 28,150.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang door stop2007 1.0000 bh Door stop @ Rp. 15,000.00

0.1000 org Tukang kayu @ Rp. 47,500.00 4,750.00 0.0100 org Kepala tukang kayu @ Rp. 50,000.00 500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0005 org Mandor @ Rp. 40,000.00 20.00

JUMLAH ( BELUM PPN ) 5,630.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang rel pintu dorong2007 1.0000 bh Rel pintu dorong @ Rp. #N/A

0.6000 org Tukang kayu @ Rp. 47,500.00 28,500.00 0.0600 org Kepala tukang kayu @ Rp. 50,000.00 3,000.00 0.0600 org Pekerja @ Rp. 36,000.00 2,160.00 0.0030 org Mandor @ Rp. 40,000.00 120.00

JUMLAH ( BELUM PPN ) 33,780.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 bh Pasang kunci lemari2007 1.0000 bh Kunci lemari @ Rp. 12,000.00

0.2500 org Tukang kayu @ Rp. 47,500.00 11,875.00 0.0250 org Kepala tukang kayu @ Rp. 50,000.00 1,250.00 0.0250 org Pekerja @ Rp. 36,000.00 900.00 0.0013 org Mandor @ Rp. 40,000.00 50.00

JUMLAH ( BELUM PPN ) 14,075.00 JASA 10 %JUMLAH

Page 403: AHS 2008-Kota.xlsx

DIBULATKAN

SNI 1.0000 Pasang kaca, tebal 3 mm

2007 1.1000 Kaca polos @ Rp. #N/A 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kaca, tebal 5 mm

2007 1.1000 Kaca polos @ Rp. #N/A 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kaca cermin, tebal 5 mm

2007 1.1000 Kaca cermin @ Rp. #N/A 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kaca patri, tebal 5 mm

2007 1.1000 Kaca patri @ Rp. 300,000.00 0.1500 org Tukang kayu @ Rp. 47,500.00 7,125.00 0.0150 org Kepala tukang kayu @ Rp. 50,000.00 750.00 0.0150 org Pekerja @ Rp. 36,000.00 540.00 0.0008 org Mandor @ Rp. 40,000.00 30.00

JUMLAH ( BELUM PPN ) 8,445.00 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pasang kusen alumunium

2007 1.1000 Kusen alumunium @ Rp. #N/A15% x Harga kusen (Perlengkapan) @ Rp. #N/A

0.1500 oh Tukang alumunium @ Rp. #N/A #N/A 0.0150 oh Kepala tukang @ Rp. #N/A #N/A 0.0150 oh Pekerja @ Rp. 36,000.00 540.00 0.0008 oh Mandor @ Rp. 40,000.00 30.00

JUMLAH #N/ADIBULATKAN

m2

m2

m2

m2

m2

m2

m2

m2

m1

m1

Page 404: AHS 2008-Kota.xlsx

SNI 1.0000 Mengerjakan Ukiran Gaya Yogyakarta dengan kedalaman 1 cm, tidak berlubang2007 Membuat pola ukir dan memindahkan pola

1.0000 lb Kertas 100 x 100 cm @ Rp. 5,000.00 15.0000 lbr Kerta karbon @ Rp. #N/A 2.0000 org Tukang gambar @ Rp. 50,000.00 100,000.00

JUMLAH ( A ) 100,000.00

Mengukir 16.0000 org Tukang Ukir @ Rp. 50,000.00 800,000.00 1.0000 org Kepala Tk, Ukir @ Rp. #N/A #N/A

JUMLAH ( B ) #N/A

Menggosok dan menghaluskan 20.0000 lbr Amplas @ Rp. 3,500.00 0.0800 kg Dempul @ Rp. #N/A 3.0000 org Tukang kayu @ Rp. 47,500.00 142,500.00

JUMLAH ( C ) 142,500.00

JUMLAH A + B + C ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Mengerjakan Cat Sungging2007 Mengerjakan cat dasar

0.1200 kg Cat menie kayu @ Rp. #N/A 0.0400 org Tukang cat @ Rp. 42,500.00 1,700.00 0.0040 org Kepala Tukang Cat @ Rp. 45,000.00 180.00 0.0667 org Pekerja @ Rp. 36,000.00 2,401.20 0.0033 org Mandor @ Rp. 40,000.00 132.00

JUMLAH ( A ) 4,413.20

Mengecat dan membuat gradasi tutulan berkali-kali 0.4250 kg Cat kayu @ Rp. #N/A 0.1000 ltr Minyak cat @ Rp. 14,000.00 5.0000 org Tukang cat sungging @ Rp. #N/A #N/A 0.5000 org Kepala Tukang Cat sungging @ Rp. #N/A #N/A 0.2000 org Pekerja @ Rp. 36,000.00 7,200.00 0.0100 org Mandor @ Rp. 40,000.00 400.00

JUMLAH ( B ) #N/AJUMLAH A + B ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Memasang Prodo Mas 24 karat

2007 1.2000 Prodo @ Rp. #N/A 0.1200 kg Cat kayu @ Rp. #N/A 0.1000 org Tukang cat @ Rp. 42,500.00 4,250.00 8.0000 org Tukang Prodo @ Rp. 50,000.00 400,000.00 1.0000 org Kepala tukang @ Rp. #N/A #N/A

JUMLAH #N/AJASA 10 %JUMLAHDIBULATKAN

m2

m2

m2

m2

Page 405: AHS 2008-Kota.xlsx

SNI 1.00 ttk Mengerjakan Sondir Tanah2007 0.50 hr Sewa alat @ Rp. #N/A

1.00 org Operator @ Rp. #N/A #N/A 0.50 org Analis @ Rp. #N/A #N/A 2.00 org Pekerja @ Rp. 36,000.00 72,000.00 0.10 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 10.00 Mengerjakan Test Laboratorium Sampel Beton2007 20.00 bh Benda uji silinder beton @ Rp. 3,000.00

20.00 bh Biaya tes @ Rp. #N/A 20.00 bh Biaya analisis @ Rp. #N/A

JUMLAH ( BELUM PPN ) - JASA 10 %JUMLAHDIBULATKAN

SNI 100.0000 Pelumpuran ringan2007 4.0000 btg Bambu @ Rp. #N/A

35.0000 bh Bagor @ Rp. 600.00 2.0000 bh Irus @ Rp. 10,000.00 1.0000 bh Cetok @ Rp. 10,000.00 1.5000 bh Ember @ Rp. 5,000.00 0.1000 bh Linggis @ Rp. 35,000.00 1.0000 bh Martil @ Rp. 10,000.00 7.0000 org Pekerja @ Rp. 36,000.00 252,000.00 0.7500 org Mandor @ Rp. 40,000.00 30,000.00

JUMLAH ( BELUM PPN ) 282,000.00 JASA 10 %JUMLAHDIBULATKAN

( A ) / (100.00)#N/A / 100.00

SNI 100.0000 Pelumpuran berat2007 8.0000 btg Bambu @ Rp. #N/A

60.0000 bh Bagor @ Rp. 600.00 0.1000 bh Pacul @ Rp. 30,000.00 1.0000 bh Cetok @ Rp. 10,000.00 0.1000 bh Linggis @ Rp. 35,000.00 2.0000 bh Irus @ Rp. 10,000.00 3.0000 bh Ember @ Rp. 5,000.00 1.0000 bh Betel @ Rp. 12,000.00 1.0000 bh Martil @ Rp. 10,000.00 12.0000 kg PC @ Rp. #N/A

0.1500 Pasir pasang @ Rp. #N/A

2.0000 Buis Beton 20/30 @ Rp. #N/A 18.0000 org Pekerja @ Rp. 36,000.00 648,000.00 1.7500 org Mandor @ Rp. 40,000.00 70,000.00

JUMLAH ( BELUM PPN ) 718,000.00

m3

m2

BIAYA TIAP 1M2

m2

m3

m1

Page 406: AHS 2008-Kota.xlsx

JASA 10 %JUMLAHDIBULATKAN

( A ) / (100.00)#N/A / 100.00

SNI 1.00 Membuang lumpur SAL sejauh 15 km2007 0.50 org Pekerja @ Rp. 36,000.00 18,000.00

0.02 org Mandor @ Rp. 40,000.00 800.00 0.41 hr Sewa kendaraan @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.00 Mengangkut lumpur SAL sejauh 30 m2007 0.40 org Pekerja @ Rp. 36,000.00 14,400.00

0.02 org Mandor @ Rp. 40,000.00 600.00 0.50 hr Sewa gerobag @ Rp. #N/A #N/A

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 10,000.00 Penyapuan Jalan Dan Trotoar2007 447.00 bh Sapu lidi @ Rp. 3,000.00

14.00 bh Tangkai Sapu @ Rp. 5,000.00 14.00 bh Tomblok @ Rp. 3,500.00 4.00 bh Hareg @ Rp. 3,000.00 8.0000 bh Serok @ Rp. 5,000.00 8.00 bh Kerug @ Rp. 5,000.00 16.00 bh Seragam @ Rp. 75,000.00 14.00 bh Sarung tangan @ Rp. 7,500.00 14.00 bh Masker @ Rp. 7,500.00 4.00 bh Gerobak @ Rp. #N/A 2,555.00 org Pekerja @ Rp. 36,000.00 91,980,000.00 365.00 org Mandor @ Rp. 40,000.00 14,600,000.00

JUMLAH ( BELUM PPN ) 106,580,000.00 JASA 10 %JUMLAHDIBULATKAN ( Dalam 1 tahun )

( A ) / (10000 x 365) #N/A / 3,650,000.00

SNI 1,000.00 Pembersihan / Penyapuan halaman2007 0.1506 bh Sapu lidi @ Rp. 3,000.00

0.0109 bh Serok @ Rp. 5,000.00 0.0082 bh Seragam @ Rp. 75,000.00 0.0009 bh Gerobak @ Rp. #N/A 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.1428 org Mandor @ Rp. 40,000.00 5,712.00

JUMLAH ( BELUM PPN ) 41,712.00 JASA 10 %JUMLAH

BIAYA TIAP 1M2

m3

m3

m2

BIAYA TIAP 1M2 / HARI :

m2

Page 407: AHS 2008-Kota.xlsx

DIBULATKAN

( A ) / (1,000.00)#N/A / 1,000.00

SNI 1,000.00 Pemangkasan teh-tehan2007 0.0280 bh Gunting pangkas @ Rp. 35,000.00

0.0030 bh Gerobak @ Rp. #N/A 5.0000 org Pekerja @ Rp. 36,000.00 180,000.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00

JUMLAH ( BELUM PPN ) 200,000.00 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan )

( A ) / (1000 x 30) #N/A / 30,000.00

SNI 1,000.00 Pangkas bentuk tanaman perdu2007 0.0890 bh Gunting pangkas @ Rp. 35,000.00

0.0060 bh Gerobak @ Rp. #N/A 8.0000 org Pekerja @ Rp. 36,000.00 288,000.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 328,000.00 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan )

( A ) / (1000 x 30) #N/A / 30,000.00

SNI 1,000.00 Pangkas rumput2007 0.0010 bh Mesin potong rumput @ Rp. 3,000,000.00

1.0000 bh Sapu lidi @ Rp. 3,000.00 0.0230 bh Tomblok @ Rp. 3,500.00 0.0030 bh Gerobak @ Rp. #N/A 6.0000 ltr BBM @ Rp. #N/A 1.0000 org Tenaga ahli @ Rp. #N/A #N/A 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan )

( A ) / (1000 x 30) #N/A / 30,000.00

SNI 1,000.00 Penyiangan tanaman semak dan penggemburan tanah2007 0.0230 bh Gathul @ Rp. 10,000.00

0.0230 bh Garpu tanah @ Rp. 15,000.00 0.0230 bh Arit @ Rp. 20,000.00

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

m2

BIAYA TIAP 1M2 / HARI :

m2

Page 408: AHS 2008-Kota.xlsx

0.0050 bh Gerobak celeng @ Rp. 400,000.00 0.0230 bh Tomblok @ Rp. 3,500.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH ( BELUM PPN ) 184,000.00 JASA 10 %JUMLAHDIBULATKANDIKERJAKAN 2 KALI ( Dalam 1 bulan )

( A ) / (1000 x 30) 411,654.00 / 30,000.00

SNI 1.0000 Pekerjaan Grouting / Injeksi retakan beton dengan epoxy resin2007 5.000 bh Nipel @ Rp. 10,000.00

0.050 kg Nitobond EC @ Rp. 100,000.00 0.016 kg Conbextra EP @ Rp. 200,000.00 0.225 hr Sewa Compressor @ Rp. #N/A 0.150 hr Sewa Mesin Grouting @ Rp. 150,000.00 0.075 hr Sewa mesin gerinda @ Rp. #N/A 1.000 hr Sewa mixer @ Rp. #N/A 1.000 ls Alat bantu @ Rp. 86,250.00 0.3125 org Tukang grouting @ Rp. 45,000.00 14,062.50 0.0312 org Kepala Tukang grouting @ Rp. 50,000.00 1,560.00 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00 0.1562 org Mandor @ Rp. 40,000.00 6,248.00

JUMLAH ( BELUM PPN ) 66,870.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex 100)2007 3.000 bh Pipa @ Rp. -

0.050 kg Nitobond EC @ Rp. 100,000.00 0.016 kg Cebex 100 @ Rp. 150,000.00 0.150 hr Sewa Mesin Grouting @ Rp. 150,000.00 0.075 hr Sewa mesin gerinda @ Rp. #N/A 1.000 ls Alat bantu @ Rp. 86,250.00 0.3125 org Tukang grouting @ Rp. 45,000.00 14,062.50 0.0312 org Kepala Tukang grouting @ Rp. 50,000.00 1,560.00 1.2500 org Pekerja @ Rp. 36,000.00 45,000.00 0.1562 org Mandor @ Rp. 40,000.00 6,248.00

JUMLAH ( BELUM PPN ) 66,870.50 JASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Cor beton kerb ( 15 x 30 ) cm, dengan 1pc:2ps:3kr2007 15.3000 kg PC @ Rp. #N/A

0.0243 Pasir pasang @ Rp. #N/A

0.0369 Kerikil beton @ Rp. #N/A

0.0027 Papan cetakan @ Rp. #N/A 0.0272 kg Paku @ Rp. - 0.0340 org Tukang kayu @ Rp. 47,500.00 1,615.00 0.0158 org Tukang batu @ Rp. 42,500.00 671.50

BIAYA TIAP 1M2 / HARI :

m1

m1

m1

m3

m3

m3

Page 409: AHS 2008-Kota.xlsx

0.0050 org Kepala tukang @ Rp. #N/A #N/A 0.1374 org Pekerja @ Rp. 36,000.00 4,946.40 0.0063 org Mandor @ Rp. 40,000.00 252.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

SNI 1.0000 Cor beton Devider ( 30 x 30 ) cm, dengan 1pc:2ps:3kr2007 30.6000 kg PC @ Rp. #N/A

0.0486 Pasir pasang @ Rp. #N/A

0.0738 Kerikil beton @ Rp. #N/A

0.0027 Papan cetakan @ Rp. #N/A 0.0272 kg Paku @ Rp. - 0.0340 org Tukang kayu @ Rp. 47,500.00 1,615.00 0.0315 org Tukang batu @ Rp. 42,500.00 1,338.75 0.0066 org Kepala tukang @ Rp. #N/A #N/A 0.2499 org Pekerja @ Rp. 36,000.00 8,996.40 0.0116 org Mandor @ Rp. 40,000.00 464.00

JUMLAH ( BELUM PPN ) #N/AJASA 10 %JUMLAHDIBULATKAN

tambahan 1.0000 M2 PASANG STOOT WERK (SCAFOLDING)4.0000 bh Main Frame (MF-1219/h = 190 cm) @ Rp. #N/A2.0000 bh Ladder Frame (LF-1209/h =90) @ Rp. #N/A4.0000 bh Join Pin (JP-42) @ Rp. #N/A2.0000 bh Cross Brase (CB-1218/I = 220 cm)- @ Rp. #N/A2.0000 bh Cross Brase (CB-0618/I = 193)-LF @ Rp. #N/A4.0000 bh Head Jack (HJ-60) @ Rp. #N/A4.0000 bh Base Jack (BJ-60) @ Rp. #N/A0.0500 m3 Balok 8/12 (10x pakai) @ Rp. #N/A0.0030 m3 Papan Alas 3/20 (3x pakai) @ Rp. #N/A1.5000 kg Kawat Pengikat @ Rp. #N/A2.0000 org Pekerja @ Rp. 36,000.00 72,000.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00

JUMLAH ( BELUM PPN ) 80,000.00 JASA 10 %JUMLAHDIBULATKAN

4 m2 Scafolding 2x Pakai

m1

m3

m3

m3

Page 410: AHS 2008-Kota.xlsx

Bahan Jumlah

(4) (5)

- - - - - - #N/A

#N/A#N/A#N/A

- #N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

- 5,600.00 560.00 6,160.00 6,160.00

96,250.00

#N/A -

#N/A#N/A

#N/A

#N/A

Page 411: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

495,000.00 #N/A#N/A#N/A

#N/A

#N/A

#N/A#N/A#N/A

40,000.00

#N/A 5,250.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A

#N/A

#N/A#N/A#N/A

Page 412: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

237,500.00

#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

- #N/A#N/A

#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

- #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 413: AHS 2008-Kota.xlsx

- #N/A#N/A

#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A -

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

345,100.00 262,500.00

#N/A

#N/A

Page 414: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

- 28,000.00 2,800.00 30,800.00 30,800.00

- 34,200.00 3,420.00 37,620.00 37,620.00

- 40,480.00 4,048.00 44,528.00 44,528.00

- 37,280.00 3,728.00 41,008.00 41,008.00

- 56,400.00 5,640.00 62,040.00 62,040.00

Page 415: AHS 2008-Kota.xlsx

- 45,000.00 4,500.00 49,500.00 49,500.00

- 2,000.00 200.00 2,200.00 2,200.00

12,280.00 1,228.00 13,508.00 13,508.00

9,332.00 933.20 10,265.20 10,265.00

20,000.00 2,000.00 22,000.00 22,000.00

#N/A

#N/A #N/A#N/A#N/A#N/A

79,200.00

79,200.00 89,200.00 8,920.00 98,120.00 98,120.00

Page 416: AHS 2008-Kota.xlsx

42,000.00

42,000.00 53,200.00 5,320.00 58,520.00 58,520.00

9,787.50 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

17,980.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 417: AHS 2008-Kota.xlsx

450,000.00

450,000.00 456,000.00 45,600.00 501,600.00 501,600.00

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

16,602.50

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

12,325.00

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 418: AHS 2008-Kota.xlsx

#N/A#N/A

16,602.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

10,657.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

9,497.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 419: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 420: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A -

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 421: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A

Page 422: AHS 2008-Kota.xlsx

#N/A

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

1,015.00

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

1,305.00

#N/A

#N/A

#N/A #N/A

Page 423: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A#N/A

1,087.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A

Page 424: AHS 2008-Kota.xlsx

#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

1,993.75

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 425: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 426: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

Page 427: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

Page 428: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 429: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 430: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- 144,000.00 14,400.00 158,400.00 158,400.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 431: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 432: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

8,400.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A -

#N/A #N/A

Page 433: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A#N/A

-

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A#N/A

2,000,000.00

#N/A #N/A#N/A

Page 434: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A#N/A#N/A#N/A#N/A

2,000,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A#N/A

6,000,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A#N/A

3,000,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

Page 435: AHS 2008-Kota.xlsx

#N/A 3,000,000.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A#N/A

2,000,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

500,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A#N/A#N/A#N/A

#N/A #N/A#N/A

Page 436: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A#N/A#N/A#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A#N/A

- #N/A

#N/A#N/A

450.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A#N/A

- #N/A

#N/A - 450.00

#N/A

Page 437: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

652.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

507.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

652.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

217.50

#N/A

Page 438: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

362.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A

Page 439: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

Page 440: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 441: AHS 2008-Kota.xlsx

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 442: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 443: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

101.50

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

Page 444: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 7,800.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

Page 445: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 7,800.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,720.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

Page 446: AHS 2008-Kota.xlsx

7,800.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 7,800.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 447: AHS 2008-Kota.xlsx

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 7,800.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 448: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 449: AHS 2008-Kota.xlsx

#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

Page 450: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A

Page 451: AHS 2008-Kota.xlsx

#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 16,500.00

#N/A #N/A#N/A#N/A

Page 452: AHS 2008-Kota.xlsx

#N/A

#N/A#N/A

#N/A 19,200.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 16,500.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 11,640.00

#N/A #N/A#N/A

Page 453: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A#N/A

#N/A 9,720.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 9,720.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 26,220.00

#N/A #N/A

Page 454: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A#N/A

#N/A 12,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 150.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 300.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 78.00

Page 455: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 600.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 3,900.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 456: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 16,500.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 16,500.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 457: AHS 2008-Kota.xlsx

#N/A 16,500.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 11,640.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 78,750.00

#N/A #N/A#N/A#N/A#N/A

33,660.00 #N/A#N/A

360.00

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 458: AHS 2008-Kota.xlsx

#N/A

#N/A 3,900.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A 16,500.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 459: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 460: AHS 2008-Kota.xlsx

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 461: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A

Page 462: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 463: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

542,850.00 #N/A

72,000.00 3,200.00

#N/A #N/A

#N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A#N/A#N/A#N/A

- #N/A#N/A#N/A#N/A

Page 464: AHS 2008-Kota.xlsx

- #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

Page 465: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

5,225,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

6,325,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

4,785,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

Page 466: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

5,225,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

6,325,000.00 #N/A#N/A

Page 467: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

4,785,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 15,660.00

#N/A#N/A

Page 468: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 15,660.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 15,660.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 20,700.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

Page 469: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 17,100.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 15,660.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 20,700.00

#N/A#N/A

Page 470: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

66,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 17,100.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 15,660.00

#N/A#N/A

Page 471: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

66,500.00 20,700.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 17,100.00

#N/A#N/A

Page 472: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 15,660.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 20,700.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 #N/A#N/A#N/A

Page 473: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

80,500.00 17,100.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 15,660.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 20,700.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 #N/A#N/A#N/A

Page 474: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

20,412.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 17,100.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 15,660.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 20,700.00

#N/A#N/A

Page 475: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 34,200.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 31,320.00

#N/A#N/A

Page 476: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 41,400.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 34,200.00

#N/A#N/A

Page 477: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 31,320.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 41,400.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 #N/A#N/A#N/A

Page 478: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

66,500.00 34,200.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 31,320.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

66,500.00 41,400.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

Page 479: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 34,200.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 31,320.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 41,400.00

#N/A#N/A

Page 480: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

80,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 34,200.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

80,500.00 31,320.00

#N/A#N/A

Page 481: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

80,500.00 41,400.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 34,200.00

#N/A#N/A

Page 482: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

20,412.00 31,320.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

20,412.00 41,400.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

Page 483: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

Page 484: AHS 2008-Kota.xlsx

- #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

Page 485: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

237,600.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

59,400.00 #N/A

#N/A #N/A#N/A#N/A#N/A

64,800.00 #N/A

#N/A #N/A#N/A#N/A#N/A

Page 486: AHS 2008-Kota.xlsx

51,300.00 #N/A

#N/A #N/A#N/A#N/A#N/A

242,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

60,500.00 #N/A

#N/A #N/A#N/A#N/A#N/A

66,000.00 #N/A

Page 487: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

52,250.00 #N/A

#N/A #N/A#N/A#N/A#N/A

105,600.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

26,400.00 #N/A

#N/A #N/A#N/A#N/A

Page 488: AHS 2008-Kota.xlsx

#N/A

28,800.00 #N/A

#N/A #N/A#N/A#N/A#N/A

22,800.00 #N/A

#N/A #N/A#N/A#N/A#N/A

132,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

33,000.00 #N/A

Page 489: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

36,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

28,500.00 #N/A

#N/A #N/A#N/A#N/A#N/A

319,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A

Page 490: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

79,750.00 #N/A

#N/A #N/A#N/A#N/A#N/A

87,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

68,875.00 #N/A

#N/A #N/A#N/A#N/A#N/A

189,200.00 #N/A

#N/A #N/A#N/A#N/A#N/A

Page 491: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

47,300.00 #N/A

#N/A #N/A#N/A#N/A#N/A

51,600.00 #N/A

#N/A #N/A#N/A#N/A#N/A

40,850.00 #N/A

#N/A #N/A#N/A#N/A#N/A

88,000.00 #N/A

Page 492: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

22,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

19,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

24,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

Page 493: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

161,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

121,800.00 #N/A

Page 494: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

161,000.00 #N/A#N/A#N/A

Page 495: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

121,800.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

Page 496: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

161,000.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

121,800.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

154,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 497: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

38,500.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

42,000.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

33,250.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 498: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A

Page 499: AHS 2008-Kota.xlsx

#N/A#N/A

6,325,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

4,785,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

220,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

240,000.00

Page 500: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

190,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

880,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

220,000.00 #N/A

#N/A #N/A

Page 501: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

240,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

190,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

528,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 502: AHS 2008-Kota.xlsx

132,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

144,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

114,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

1,408,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 503: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

352,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

384,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

304,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu jati lokal

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A

Page 504: AHS 2008-Kota.xlsx

#N/A

Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu kamper

137,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu bengkirai

150,000.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu, Kayu kruing

118,750.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

563,200.00 #N/A#N/A#N/A

Page 505: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

140,800.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

153,600.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

121,600.00 #N/A#N/A#N/A

Page 506: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

1,320,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

330,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

360,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

Page 507: AHS 2008-Kota.xlsx

285,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

550,000.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

137,500.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A

Page 508: AHS 2008-Kota.xlsx

#N/A

150,000.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

118,750.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

137,500.00 #N/A#N/A#N/A#N/A

Page 509: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

150,000.00 #N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

118,750.00 #N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 510: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A

0.01 #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A

0.01 #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A

0.01 #N/A#N/A#N/A#N/A

908,500.00 #N/A

#N/A #N/A#N/A

0.01 #N/A#N/A#N/A#N/A

Page 511: AHS 2008-Kota.xlsx

908,500.00

908,500.00 1,435,000.00 71,750.00

0.01 15,067.50 1,506.75 16,574.25 16,574.00

#N/A#N/A#N/A#N/A#N/A#N/A#N/A

#N/A #N/A#N/A

#N/A#N/A#N/A#N/A#N/A

#N/A #N/A#N/A

4,300.00 1,400.00

#N/A 5,700.00 #N/A 57.00 #N/A

#N/A#N/A#N/A

#N/A#N/A

325.00

Page 512: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 1,290.00 560.00

#N/A#N/A #N/A#N/A #N/A

#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

250,000.00

250,000.00 #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 513: AHS 2008-Kota.xlsx

250,000.00

250,000.00 292,840.00 29,284.00 322,124.00 322,124.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

1,760,000.00 #N/A#N/A

Page 514: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

46,327.50 #N/A

#N/A #N/A#N/A#N/A#N/A

9,075.00 #N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

52,500.00

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 515: AHS 2008-Kota.xlsx

#N/A 418,000.00

#N/A #N/A#N/A#N/A#N/A

Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu jati lokal#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

104,500.00

#N/A #N/A#N/A#N/A#N/A

Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu bengkirai#N/A#N/A

114,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

90,250.00

Page 516: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

3,750.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A

Page 517: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

330,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 518: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

82,500.00 #N/A

#N/A #N/A#N/A#N/A#N/A

90,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

71,250.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 1,100.00

#N/A #N/A#N/A#N/A

Page 519: AHS 2008-Kota.xlsx

#N/A

#N/A 525.00

#N/A #N/A#N/A#N/A#N/A

72,000.00 #N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

- -

- 4,545.00 454.50 4,999.50 4,999.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 520: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

- #N/A

#N/A #N/A#N/A#N/A#N/A

52,200.00 #N/A

#N/A #N/A#N/A#N/A#N/A

69,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A -

#N/A #N/A#N/A#N/A

Page 521: AHS 2008-Kota.xlsx

#N/A

#N/A -

#N/A #N/A#N/A#N/A#N/A

- -

- 20,635.00 2,063.50 22,698.50 22,698.00

56,550.00 -

56,550.00 77,185.00 7,718.50 84,903.50 84,903.00

74,750.00 -

74,750.00 95,385.00 9,538.50 104,923.50 104,923.00

#N/A 400.00

#N/A

Page 522: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

27,500.00

27,500.00 39,800.00 3,980.00 43,780.00 43,780.00

27,500.00

27,500.00 43,600.00 4,360.00 47,960.00 47,960.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 523: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

1,102.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 524: AHS 2008-Kota.xlsx

#N/A

1,102.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

1,102.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

1,102.00

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 525: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A

Page 526: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 527: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 528: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A

Page 529: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

27,500.00 #N/A

#N/A #N/A#N/A#N/A#N/A

27,500.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 5,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 530: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 1,250.00

#N/A #N/A#N/A#N/A#N/A

#N/A 190.00

#N/A #N/A#N/A#N/A#N/A

#N/A 380.00

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 531: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 7,980.00

#N/A #N/A

#N/A #N/A#N/A#N/A#N/A

- - - - -

- - - - -

1,250.00

1,250.00 6,750.00 675.00 7,425.00 7,425.00

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 532: AHS 2008-Kota.xlsx

#N/A 280.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup#N/A#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

Page 533: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A 14,880.00 7,000.00

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

350.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 534: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

850.00

850.00 3,932.00 393.20 4,325.20 4,325.00

350.00 125.00

#N/A 20,700.00

#N/A #N/A#N/A#N/A#N/A

#N/A 41,400.00

Page 535: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

2,100.00

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

48,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 536: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

29,750.00 798.00

30,548.00 52,598.00 5,259.80 57,857.80 57,857.00

16,200.00

16,200.00 19,981.00 1,998.10 21,979.10 21,979.00

- 184,400.00 18,440.00 202,840.00 202,840.00

Page 537: AHS 2008-Kota.xlsx

- 88,600.00 8,860.00 97,460.00 97,460.00

- 300,500.00 30,050.00 330,550.00 330,550.00

- 76,000.00

- 7,600.00 760.00 8,360.00 8,360.00

- 50,000.00

- 5,000.00 500.00 5,500.00 5,500.00

- 76,000.00

- 7,600.00 760.00 8,360.00 8,360.00

- 58,500.00

- 5,850.00 585.00 6,435.00

Page 538: AHS 2008-Kota.xlsx

6,435.00

- 107,500.00

- 10,750.00 1,075.00 11,825.00 11,825.00

- 76,000.00

- 7,600.00 760.00 8,360.00 8,360.00

Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi

- 467,000.00 46,700.00 513,700.00 513,700.00

Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi

- 44,000.00 4,400.00 48,400.00 48,400.00

- 782,000.00 78,200.00 860,200.00 860,200.00

Page 539: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

85,000.00 #N/A#N/A

#N/A

#N/A #N/A

Page 540: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

- #N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

- #N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

350,000.00 #N/A

#N/A #N/A#N/A#N/A#N/A

Page 541: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

Page 542: AHS 2008-Kota.xlsx

#N/A#N/A#N/A

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A -

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A -

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A

#N/A -

#N/A

Page 543: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A

Page 544: AHS 2008-Kota.xlsx

#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

Page 545: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 546: AHS 2008-Kota.xlsx

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

500,000.00 200,000.00

700,000.00 715,240.00 71,524.00 786,764.00 786,764.00

#N/A 200,000.00

#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A 212.50

#N/A #N/A#N/A#N/A#N/A

135,000.00

Page 547: AHS 2008-Kota.xlsx

135,000.00 140,260.00 14,026.00 154,286.00 154,286.00

250,000.00

250,000.00 283,780.00 28,378.00 312,158.00 312,158.00

125,000.00

125,000.00 149,810.00 14,981.00 164,791.00 164,791.00

#N/A

#N/A #N/A#N/A#N/A#N/A

75,000.00

75,000.00 99,190.00 9,919.00 109,109.00 109,109.00

11,000.00

Page 548: AHS 2008-Kota.xlsx

11,000.00 19,445.00 1,944.50 21,389.50 21,389.00

7,500.00

7,500.00 13,310.00 1,331.00 14,641.00 14,641.00

3,000.00

3,000.00 14,620.00 1,462.00 16,082.00 16,082.00

7,500.00

7,500.00 15,945.00 1,594.50 17,539.50 17,539.00

3,000.00

3,000.00 11,445.00 1,144.50 12,589.50 12,589.00

150,000.00

150,000.00 178,150.00

Page 549: AHS 2008-Kota.xlsx

17,815.00 195,965.00 195,965.00

50,000.00

50,000.00 61,260.00 6,126.00 67,386.00 67,386.00

15,000.00

15,000.00 43,150.00 4,315.00 47,465.00 47,465.00

15,000.00

15,000.00 20,630.00 2,063.00 22,693.00 22,693.00

#N/A

#N/A #N/A#N/A#N/A#N/A

12,000.00

12,000.00 26,075.00 2,607.50 28,682.50

Page 550: AHS 2008-Kota.xlsx

28,682.00

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A#N/A#N/A#N/A

330,000.00

330,000.00 338,445.00 33,844.50 372,289.50 372,289.00

#N/A#N/A

#N/A #N/A#N/A

Page 551: AHS 2008-Kota.xlsx

Mengerjakan Ukiran Gaya Yogyakarta dengan kedalaman 1 cm, tidak berlubang

5,000.00 #N/A

#N/A #N/A

- #N/A

70,000.00 #N/A

#N/A #N/A

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A #N/A

#N/A 1,400.00

#N/A #N/A#N/A #N/A

#N/A#N/A#N/A

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

Page 552: AHS 2008-Kota.xlsx

#N/A

#N/A #N/A#N/A#N/A#N/A

60,000.00 #N/A#N/A#N/A #N/A

#N/A#N/A#N/A

#N/A 21,000.00 20,000.00 10,000.00 7,500.00 3,500.00 10,000.00

#N/A #N/A#N/A#N/A

( A ) #N/A

#N/A

#N/A 36,000.00 3,000.00 10,000.00 3,500.00 20,000.00 15,000.00 12,000.00 10,000.00

#N/A

#N/A

#N/A

#N/A #N/A

Page 553: AHS 2008-Kota.xlsx

#N/A#N/A

( A ) #N/A

#N/A

- #N/A#N/A#N/A#N/A

- #N/A#N/A#N/A#N/A

1,341,000.00 70,000.00 49,000.00 12,000.00 40,000.00 40,000.00 1,200,000.00 105,000.00 105,000.00

#N/A

#N/A #N/A#N/A#N/A

( A ) #N/A

#N/A

451.80 54.50 615.00

#N/A

#N/A #N/A#N/A#N/A

Page 554: AHS 2008-Kota.xlsx

( A ) #N/A

#N/A

980.00 #N/A

#N/A #N/A#N/A#N/A#N/A

( A ) #N/A

#N/A

3,115.00 #N/A

#N/A #N/A#N/A#N/A#N/A

( A ) #N/A

#N/A

3,000.00 3,000.00 80.50

#N/A#N/A

#N/A #N/A#N/A#N/A#N/A

( A ) #N/A

#N/A

230.00 345.00 460.00

Page 555: AHS 2008-Kota.xlsx

2,000.00 80.50

3,115.50 187,115.50 18,711.55 205,827.05 205,827.00

( A ) 411,654.00

13.72

50,000.00 5,000.00 3,200.00

#N/A 22,500.00

#N/A#N/A

86,250.00

#N/A #N/A#N/A#N/A#N/A

Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex 100) - 5,000.00 2,400.00 22,500.00

#N/A 86,250.00

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A

#N/A -

Page 556: AHS 2008-Kota.xlsx

#N/A #N/A#N/A#N/A#N/A

#N/A

#N/A

#N/A

#N/A -

#N/A #N/A#N/A#N/A#N/A

- - - - - - - - - -

- 80,000.00 8,000.00 88,000.00 88,000.00

4 m2 Scafolding 2x Pakai 352,000.00

Page 557: AHS 2008-Kota.xlsx

Analisa Listrik - 557

ANJALISA PEKERJAAN LISTRIK No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1. 1.0000 Pasang Kabel NYY 3 x 6 sqmm 0.0050 org Tukang Listrik @ Rp. 45,000.00 225.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 605.00 - 605.00 JASA 10 % 60.50 JUMLAH 665.50 DIBULATKAN 665.00

2. 1.0000 Pasang Kabel NYY 3 x 4 sqmm 0.0050 org Tukang Listrik @ Rp. 45,000.00 225.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 605.00 - 605.00 JASA 10 % 60.50 JUMLAH 665.50 DIBULATKAN 665.00

3. 1.0000 Pasang Kabel NYM 2 x 2,5 sqmm 0.0050 org Tukang Listrik @ Rp. 45,000 225.00 0.0050 org Pekerja @ Rp. 36,000 180.00 0.0050 org Mandor @ Rp. 40,000 200.00

JUMLAH ( BELUM PPN ) 605.00 - 605.00 JASA 10 % 60.50 JUMLAH 665.50 DIBULATKAN 665.00

4. 1.0000 Pasang Kabel NYM 2 x 1,5 sqmm 0.0050 org Tukang Listrik @ Rp. 45,000.00 225.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 605.00 - 605.00 JASA 10 % 60.50 JUMLAH 665.50 DIBULATKAN 665.00

5. 1.0000 Pasang Kabel NYA 1 x 2,5 sqmm 0.0025 org Tukang Listrik @ Rp. 45,000.00 112.50 0.0025 org Pekerja @ Rp. 36,000.00 90.00 0.0025 org Mandor @ Rp. 40,000.00 100.00

JUMLAH ( BELUM PPN ) 302.50 - 302.50 JASA 10 % 30.25 JUMLAH 332.75 DIBULATKAN 332.00

6. 50.0000 Pasang Kabel DX 2x10 sqmm + Accessories (antar tiang / gawang)

50.0000 Kabel DX 2x10 qmm + Accessories @ Rp. 6,875.00 343,750.00 0.1250 org Tenaga Ahli @ Rp. 50,000.00 6,250.00 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.2500 org Mandor @ Rp. 40,000.00 10,000.00 1.0000 ls Penyambungan beban @ Rp. 17,250.00 17,250.00

JUMLAH ( BELUM PPN ) 74,000.00 343,750.00 417,750.00 JASA 10 % 41,775.00 JUMLAH 459,525.00 DIBULATKAN 459,525.00

m1

m1

m1

m1

m1

m1

m1

Page 558: AHS 2008-Kota.xlsx

Analisa Listrik - 558

(1) (2) (3) (4) (5)

7. 50.0000 Pasang Kabel DX 2x16 sqmm + Accessories (antar tiang / gawang)

50.0000 Kabel DX 2x16 qmm + Accessories @ Rp. 8,250.00 412,500.00 0.1250 org Tenaga Ahli @ Rp. 50,000.00 6,250.00 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.2500 org Mandor @ Rp. 40,000.00 10,000.00 1.0000 ls Penyambungan beban @ Rp. 17,250.00 17,250.00

JUMLAH ( BELUM PPN ) 74,000.00 412,500.00 486,500.00 JASA 10 % 48,650.00 JUMLAH 535,150.00 DIBULATKAN 535,150.00

8. 1.0000 Pasang Kabel NYY 3x10 sqmm

1.0000 Kabel NYY 3x10 Sqmm @ Rp. 45,408.00 45,408.00 0.0050 org Tukang Listrik @ Rp. 45,000.00 225.00 0.0050 org Pekerja @ Rp. 36,000.00 180.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 605.00 45,408.00 46,013.00 JASA 10 % 4,601.30 JUMLAH 50,614.30 DIBULATKAN 50,614.00

9. 1.0000 unit Pasang Box Panel dan Panel Kontrol 1 Unit 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 0.7500 org Pekerja @ Rp. 36,000.00 27,000.00 0.2500 org Mandor @ Rp. 40,000.00 10,000.00 1.0000 unit Pasang panel kontrol @ Rp. 86,250.00 86,250.00

JUMLAH ( BELUM PPN ) 123,250.00 22,500.00 145,750.00 JASA 10 % 14,575.00 JUMLAH 160,325.00 DIBULATKAN 160,325.00

10. 1.0000 unit Pasang Box KWH dan Meter (1 Unit) 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 0.7500 org Pekerja @ Rp. 36,000.00 27,000.00 0.2500 org Mandor @ Rp. 40,000.00 10,000.00 1.0000 unit Pasang panel kontrol @ Rp. 86,250.00 86,250.00

JUMLAH ( BELUM PPN ) 123,250.00 22,500.00 145,750.00 JASA 10 % 14,575.00 JUMLAH 160,325.00 DIBULATKAN 160,325.00

11. 1.0000 unit Pasang tiang lampu antik (b3) 0.6600 org Tukang batu @ Rp. 42,500.00 28,050.00 0.6600 org Tukang listrik @ Rp. 45,000.00 29,700.00 5.3300 org Pekerja @ Rp. 36,000.00 191,880.00 0.6660 org Mandor @ Rp. 40,000.00 26,640.00 0.6660 set Alat bantu @ Rp. 86,250.00 57,442.50 4.6000 jam Angkutan @ Rp. 7,143.00 32,857.80

JUMLAH ( BELUM PPN ) 276,270.00 90,300.30 366,570.30 JASA 10 % 36,657.03 JUMLAH 403,227.33 DIBULATKAN 403,227.00

12. 1.0000 unit Pasang tiang lampu antik (b3) 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.5000 org Tukang listrik @ Rp. 45,000.00 22,500.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00 0.5000 set Alat bantu @ Rp. 86,250.00 43,125.00 3.5000 jam Angkutan @ Rp. 7,143.00 25,000.50

JUMLAH ( BELUM PPN ) 207,750.00 68,125.50 275,875.50 JASA 10 % 27,587.55 JUMLAH 303,463.05 DIBULATKAN 303,463.00

m1

m1

m1

m1

Page 559: AHS 2008-Kota.xlsx

Analisa Listrik - 559

(1) (2) (3) (4) (5)

13. 1.0000 set Pemasangan armatur komplit 0.5000 org Tukang listrik @ Rp. 45,000.00 22,500.00 0.7500 org Pekerja @ Rp. 36,000.00 27,000.00 0.2500 org Mandor @ Rp. 40,000.00 10,000.00 1.0000 set Alat bantu @ Rp. 86,250.00 86,250.00

JUMLAH ( BELUM PPN ) 59,500.00 86,250.00 145,750.00 JASA 10 % 14,575.00 JUMLAH 160,325.00 DIBULATKAN 160,325.00

14. 1.0000 unit Pemasangan komponen + Box 0.6660 org Tukang listrik @ Rp. 45,000.00 29,970.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 0.3330 org Mandor @ Rp. 40,000.00 13,320.00 1.0000 set Alat bantu @ Rp. 86,250.00 86,250.00

JUMLAH ( BELUM PPN ) 79,290.00 86,250.00 165,540.00 JASA 10 % 16,554.00 JUMLAH 182,094.00 DIBULATKAN 182,094.00

15. 1.0000 set Bongkar komponen 0.4000 org Tukang listrik @ Rp. 45,000.00 18,000.00 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.2000 org Mandor @ Rp. 40,000.00 8,000.00 1.0000 set Alat bantu @ Rp. 86,250.00 86,250.00

JUMLAH ( BELUM PPN ) 47,600.00 86,250.00 133,850.00 JASA 10 % 13,385.00 JUMLAH 147,235.00 DIBULATKAN 147,235.00

16. 1.0000 unit Bongkar Armatur 0.3300 org Tukang Listrik @ Rp. 45,000.00 14,850.00 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.1666 org Mandor @ Rp. 40,000.00 6,664.00 1.0000 jam Angkutan @ Rp. 7,143.00 7,143.00

JUMLAH ( BELUM PPN ) 39,514.00 7,143.00 46,657.00 JASA 10 % 4,665.70 JUMLAH 51,322.70 DIBULATKAN 51,322.00

17. 1.0000 set Bongkar Tiang Lampu Antik (b.1) 0.5000 org Tukang batu @ Rp. 42,500.00 21,250.00 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 4.0000 org Pekerja @ Rp. 36,000.00 144,000.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00 0.5000 set Alat bantu @ Rp. 86,250.00 43,125.00 3.5000 jam Angkutan @ Rp. 7,143.00 25,000.50

JUMLAH ( BELUM PPN ) 207,750.00 68,125.50 275,875.50 JASA 10 % 27,587.55 JUMLAH 303,463.05 DIBULATKAN 303,463.00

18. 1.0000 set Bongkar Tiang Lampu Antik (b.1) 0.6600 org Tukang batu @ Rp. 42,500.00 28,050.00 0.6600 org Tukang Listrik @ Rp. 45,000.00 29,700.00 5.3330 org Pekerja @ Rp. 36,000.00 191,988.00 0.6660 org Mandor @ Rp. 40,000.00 26,640.00 0.6660 set Alat bantu @ Rp. 86,250.00 57,442.50 4.6000 jam Angkutan @ Rp. 7,143.00 32,857.80

JUMLAH ( BELUM PPN ) 276,378.00 90,300.30 366,678.30 JASA 10 % 36,667.83 JUMLAH 403,346.13 DIBULATKAN 403,346.00

Page 560: AHS 2008-Kota.xlsx

Analisa Listrik - 560

(1) (2) (3) (4) (5)

19. 1.0000 Pasang Kabel NYM 2x2,5 sqmm

1.0000 Kabel NYM 2 x 2,5 qmm @ Rp. 10,633.00 10,633.00 0.2500 org Tukang Listrik @ Rp. 45,000.00 11,250.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 11,810.00 10,633.00 22,443.00 JASA 10 % 2,244.30 JUMLAH 24,687.30 DIBULATKAN 24,687.00

20. 1.0000 Pasang Kabel NYA 2,5 sqmm

1.0000 Kabel NYA 2,5 qmm @ Rp. 150,000.00 150,000.00 0.2500 org Tukang Listrik @ Rp. 45,000.00 11,250.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 11,810.00 150,000.00 161,810.00 JASA 10 % 16,181.00 JUMLAH 177,991.00 DIBULATKAN 177,991.00

21. 1.0000 Pasang Pralon 3" Kabel NYY 3x6 sqmm

1.0000 Pipa pralon 3" @ Rp. 20,500.00 20,500.00 0.0100 org Pekerja @ Rp. 36,000.00 360.00 0.0050 org Mandor @ Rp. 40,000.00 200.00

JUMLAH ( BELUM PPN ) 560.00 20,500.00 21,060.00 JASA 10 % 2,106.00 JUMLAH 23,166.00 DIBULATKAN 23,166.00

22. 1.0000 bh Pasang tutup panel ukuran 30x30 1.0000 bh Tutup panel 30x30 @ Rp. 28,750.00 28,750.00 0.0500 org Tukang listrik @ Rp. 45,000.00 2,250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 6,850.00 28,750.00 35,600.00 JASA 10 % 3,560.00 JUMLAH 39,160.00 DIBULATKAN 39,160.00

23. 1.0000 bh Pasang MCB Ampere + box tutup panel ukuran 30 x 30 1.0000 bh MCB 10 Ampere + box @ Rp. 42,000.00 42,000.00 0.0500 org Tukang listrik @ Rp. 45,000.00 2,250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 6,850.00 42,000.00 48,850.00 JASA 10 % 4,885.00 JUMLAH 53,735.00 DIBULATKAN 53,735.00

24. 1.0000 bh Pasang Kapasitor 12,5 uF 1.0000 bh Kapasitor 12,5 uF @ Rp. 26,000.00 26,000.00 0.0500 org Tukang listrik @ Rp. 45,000.00 2,250.00 0.1000 org Pekerja @ Rp. 36,000.00 3,600.00 0.0250 org Mandor @ Rp. 40,000.00 1,000.00

JUMLAH ( BELUM PPN ) 6,850.00 26,000.00 32,850.00 JASA 10 % 3,285.00 JUMLAH 36,135.00 DIBULATKAN 36,135.00

m1

m1

m1

m1

m1

m1

Page 561: AHS 2008-Kota.xlsx

Analisa Listrik - 561

(1) (2) (3) (4) (5)

25. 1.0000 set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son + pengetesan dan penyalaan 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 1.2500 org Pengawas @ Rp. 50,000.00 62,500.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00

JUMLAH (A) 123,000.00 - 123,000.00

26. Pengetesan dan Penyalaan 1.0000 ttk @ Rp. 7,000.00 7,000.00

JUMLAH (B) 7,000.00 - 7,000.00

JUMLAH ( A + B ) ( BELUM PPN ) 130,000.00 JASA 10 % 13,000.00 JUMLAH 143,000.00 DIBULATKAN 143,000.00

27. 1.0000 set Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son 0.8750 org Pekerja @ Rp. 36,000.00 31,500.00 0.8750 org Tukang Listrik @ Rp. 45,000.00 39,375.00 1.8033 org Pengawas @ Rp. 50,000.00 90,165.00 0.7413 org Mandor @ Rp. 40,000.00 29,653.20

JUMLAH (C) 190,693.20 - 190,693.20

JUMLAH ( B + C ) ( BELUM PPN ) 197,693.20 JASA 10 % 19,769.32 JUMLAH 217,462.52 DIBULATKAN 217,462.00

28. 1.0000 set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son 0.5000 org Pekerja @ Rp. 36,000.00 18,000.00 0.5000 org Tukang Listrik @ Rp. 45,000.00 22,500.00 1.2500 org Pengawas @ Rp. 50,000.00 62,500.00 0.5000 org Mandor @ Rp. 40,000.00 20,000.00

JUMLAH (D) 123,000.00 - 123,000.00

JUMLAH ( B + D ) ( BELUM PPN ) 130,000.00 JASA 10 % 13,000.00 JUMLAH 143,000.00 DIBULATKAN 143,000.00

29. 1.0000 set Pasang Tiang Octogonal Cabang 1, h= 7 meter+ lampu SRP 822/250 Watt Son

0.4200 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. 4,994,658.63 2,097,756.62 2.8500 org Pekerja @ Rp. 36,000.00 102,600.00 2.8500 org Tukang Listrik @ Rp. 45,000.00 128,250.00 2.0075 org Pengawas @ Rp. 50,000.00 100,375.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00

JUMLAH (E) 371,225.00 2,097,756.62 2,468,981.62

JUMLAH ( B + E ) ( BELUM PPN ) 2,475,981.62 JASA 10 % 247,598.16 JUMLAH 2,723,579.78 DIBULATKAN 2,723,579.00

30. 1.0000 set Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 Watt Son

0.4200 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. 4,994,658.63 2,097,756.62 3.1000 org Pekerja @ Rp. 36,000.00 111,600.00 3.1000 org Tukang Listrik @ Rp. 45,000.00 139,500.00 2.5000 org Pengawas @ Rp. 50,000.00 125,000.00 1.2100 org Mandor @ Rp. 40,000.00 48,400.00

JUMLAH (F) 424,500.00 2,097,756.62 2,522,256.62

JUMLAH ( B + F ) ( BELUM PPN ) 2,529,256.62 JASA 10 % 252,925.66 JUMLAH 2,782,182.28 DIBULATKAN 2,782,182.00

m3

m3

Page 562: AHS 2008-Kota.xlsx

Analisa Listrik - 562

(1) (2) (3) (4) (5)

31. 1.0000 set Pasang Tiang Octogonal Cabang 2, h= 9 meter+ lampu SRP 822/250 Watt Son

0.4200 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. 4,994,658.63 2,097,756.62 3.3000 org Pekerja @ Rp. 36,000.00 118,800.00 3.3000 org Tukang Listrik @ Rp. 45,000.00 148,500.00 2.5782 org Pengawas @ Rp. 50,000.00 128,910.00 1.2433 org Mandor @ Rp. 40,000.00 49,732.00

JUMLAH (G) 445,942.00 2,097,756.62 2,543,698.62

JUMLAH ( B + G) ( BELUM PPN ) 2,550,698.62 JASA 10 % 255,069.86 JUMLAH 2,805,768.48 DIBULATKAN 2,805,768.00

32. 1.0000 set Pasang Tiang Octogonal Cabang 3, h= 9 m+ lampu SRP 822/250 Watt Son

0.4200 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. 4,994,658.63 2,097,756.62 3.8100 org Pekerja @ Rp. 36,000.00 137,160.00 3.8100 org Tukang Listrik @ Rp. 45,000.00 171,450.00 2.6626 org Pengawas @ Rp. 50,000.00 133,130.00 1.2650 org Mandor @ Rp. 40,000.00 50,600.00

JUMLAH (H) 492,340.00 2,097,756.62 2,590,096.62

JUMLAH ( B + H) ( BELUM PPN ) 2,597,096.62 JASA 10 % 259,709.66 JUMLAH 2,856,806.28 DIBULATKAN 2,856,806.00

33. 1.0000 set Pasang Tiang Octogonal Cabang 3, h= 11 m+ lampu SRP 822/250 Watt Son

0.4200 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. 4,994,658.63 2,097,756.62 4.2500 org Pekerja @ Rp. 36,000.00 153,000.00 4.2500 org Tukang Listrik @ Rp. 45,000.00 191,250.00 2.9287 org Pengawas @ Rp. 50,000.00 146,435.00 1.2939 org Mandor @ Rp. 40,000.00 51,756.00

JUMLAH (I) 542,441.00 2,097,756.62 2,640,197.62

JUMLAH ( B + I) ( BELUM PPN ) 2,647,197.62 JASA 10 % 264,719.76 JUMLAH 2,911,917.38 DIBULATKAN 2,911,917.00

34. 1.0000 set Bongkar armatur pada stang ornamen existing + pasang lampu SRP 822/150 Watt Son + return 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.9000 org Tukang Listrik @ Rp. 45,000.00 40,500.00 2.1044 org Pengawas @ Rp. 50,000.00 105,220.00 0.8418 org Mandor @ Rp. 40,000.00 33,672.00 0.0500 unit Retur material existing @ Rp. 100,000.00 5,000.00

JUMLAH (J) 216,792.00 - 216,792.00

JUMLAH ( B + J) ( BELUM PPN ) 223,792.00 JASA 10 % 22,379.20 JUMLAH 246,171.20 DIBULATKAN 246,171.00

35. 1.0000 set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/250 Watt Son + retur 0.8750 org Pekerja @ Rp. 36,000.00 31,500.00 0.8750 org Tukang Listrik @ Rp. 45,000.00 39,375.00 1.6995 org Pengawas @ Rp. 50,000.00 84,975.00 0.6798 org Mandor @ Rp. 40,000.00 27,192.00 0.0500 unit Retur material existing @ Rp. 100,000.00 5,000.00

JUMLAH (K) 188,042.00 - 188,042.00

JUMLAH ( B + K) ( BELUM PPN ) 195,042.00 JASA 10 % 19,504.20 JUMLAH 214,546.20 DIBULATKAN 214,546.00

m3

m3

m3

Page 563: AHS 2008-Kota.xlsx

Analisa Listrik - 563

(1) (2) (3) (4) (5)

36. 1.0000 set Bongkar armatur pada tang existing + pasang Lampu SRP 822/250 Watt Son + retur 0.9000 org Pekerja @ Rp. 36,000.00 32,400.00 0.9000 org Tukang Listrik @ Rp. 45,000.00 40,500.00 2.1044 org Pengawas @ Rp. 50,000.00 105,220.00 0.8418 org Mandor @ Rp. 40,000.00 33,672.00 0.0500 unit Retur material existing @ Rp. 100,000.00 5,000.00

JUMLAH (L) 216,792.00 - 216,792.00

JUMLAH ( B + L) ( BELUM PPN ) 221,546.00 JASA 10 % 22,154.60 JUMLAH 243,700.60 DIBULATKAN 243,700.00

37. 1.0000 set Bongkar komponen lama existing + pasang komponen Lampu SRP 822/250 Watt Son + retur 0.8500 org Pekerja @ Rp. 36,000.00 30,600.00 0.8500 org Tukang Listrik @ Rp. 45,000.00 38,250.00 1.9554 org Pengawas @ Rp. 50,000.00 97,770.00 0.7822 org Mandor @ Rp. 40,000.00 31,288.00 0.0500 unit Retur material existing @ Rp. 100,000.00 5,000.00

JUMLAH (M) 202,908.00 - 202,908.00

JUMLAH ( B + M) ( BELUM PPN ) 209,908.00 JASA 10 % 20,990.80 JUMLAH 230,898.80 DIBULATKAN 230,898.00

Page 564: AHS 2008-Kota.xlsx

Analisa KPUT - 564

ANALISA KPUTNo. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

AN. 1.0000 Menghampar dan mengisi bahan perkerasanKPUT 1.5000 org Pekerja @ Rp. 36,000.00 54,000.00 - AN. 0.0730 org Mandor @ Rp. 40,000.00 2,920.00 -

JUMLAH ( BELUM TERMASUK PPN ) 56,920.00 - 56,920.00 DIBULATKAN 56,920.00

1.0000 Menyawur pasir 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00

JUMLAH ( BELUM TERMASUK PPN ) 36,000.00 - 36,000.00 DIBULATKAN 36,000.00

KPUT 1.0000 hari Menggilas dengan motor wallsM.3 1.0000 org Masinis @ Rp. 37,500.00 37,500.00

1.0000 org Kenek @ Rp. 36,000.00 36,000.00 1.0000 org Penjaga @ Rp. 36,000.00 36,000.00 1.0000 org Pekerja @ Rp. 36,000.00 36,000.00 1.0000 ltr Olie @ Rp. 21,000.00 21,000.00 1.0000 ltr Olie SAE @ Rp. 21,000.00 21,000.00 0.7500 ltr Vet @ Rp. 13,000.00 9,750.00 16.0000 ltr Solar @ Rp. 4,300.00 68,800.00

JUMLAH ( BELUM TERMASUK PPN ) 145,500.00 120,550.00 266,050.00 DIBULATKAN 266,050.00

KPUT 100.0000 Perkerasan lapis pondasi bawah (sub base) tebal 20 cm padat

10.8 5.0000 Pasair pasang @ Rp. 76,000.00 380,000.00

23.0000 Batu belah 15/20 @ Rp. 80,000.00 1,840,000.00

3.0000 Batu pecah 5/7 cm @ Rp. 132,000.00 396,000.00

6.5000 Pasir urug @ Rp. 55,000.00 357,500.00

26.0000 Isi batu berkerasan @ Rp. 56,920.00 1,479,920.00 6.5000 Tng Menyawur pasir @ Rp. 36,000.00 234,000.00

JUMLAH ( BELUM TERMASUK PPN ) 1,713,920.00 2,973,500.00 4,687,420.00 DIBULATKAN 4,687,420.00

1/100 x 1,713,920.00 + 2,973,500.00 17,139.20 29,735.00 Biaya menggilas

1/200 x 145,500.00 + 120,550.00 727.50 602.75 Sewa motor walls

1/200 x 150,000.00 750.00 JUMLAH ( BELUM TERMASUK PPN ) 18,616.70 30,337.75 48,954.45 JASA 10 % 4,895.45 JUMLAH 53,849.90 DIBULATKAN 53,849.00

100.0000 Pembuatan lapis pondasi bawah (sub base) tebal 15 cm padat

5.0000 Pasair urug @ Rp. 55,000.00 275,000.00

17.5000 Batu belah 15/20 @ Rp. 80,000.00 1,400,000.00

3.0000 Batu pecah 5/7 cm @ Rp. 126,500.00 379,500.00

6.5000 Pasir urug (pengisi) @ Rp. 55,000.00 357,500.00

20.5000 Isi batu berkerasan @ Rp. 56,920.00 1,166,860.00 5.0000 Tng Menyawur pasir @ Rp. 36,000.00 180,000.00

JUMLAH ( BELUM TERMASUK PPN ) 1,346,860.00 2,412,000.00 3,758,860.00 DIBULATKAN 3,758,860.00

1/100 x 1,346,860.00 + 2,412,000.00 13,468.60 24,120.00 Biaya menggilas

1/200 x 145,500.00 + 120,550.00 727.50 602.75 Sewa motor walls

1/200 x 150,000.00 750.00 JUMLAH ( BELUM TERMASUK PPN ) 14,946.10 24,722.75 39,668.85 JASA 10 % 3,966.89

m2

m3

m2

m3

m3

m3

m3

m3

Tiap m2

m2

m3

m3

m3

m3

m3

Tiap m2

Page 565: AHS 2008-Kota.xlsx

Analisa KPUT - 565

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5) JUMLAH 43,635.74 DIBULATKAN 43,635.00

Page 566: AHS 2008-Kota.xlsx

Analisa KPUT - 566

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

100.0000 Pembuatan lapis pondasi atas (base) tebal 10 cm padat

10.0000 Batu koral 5/7 cm @ Rp. 132,000.00 1,320,000.00

2.0000 Batu koral 3/4 cm @ Rp. 130,000.00 260,000.00

1.0000 Batu koral 2/3 cm @ Rp. 138,000.00 138,000.00

3.2500 Pasir urug (pengisi) @ Rp. 55,000.00 178,750.00

13.0000 Isi batu berkerasan @ Rp. 56,920.00 739,960.00 3.2500 Tng Menyawur pasir @ Rp. 36,000.00 117,000.00

JUMLAH ( BELUM TERMASUK PPN ) 856,960.00 1,896,750.00 2,753,710.00 DIBULATKAN 2,753,710.00

1/100 x 856,960.00 + 1,896,750.00 8,569.60 18,967.50 Biaya menggilas

1/150 x 145,500.00 + 120,550.00 970.00 803.67 Sewa motor walls

1/150 x 150,000.00 1,000.00 JUMLAH ( BELUM TERMASUK PPN ) 10,539.60 19,771.17 30,310.77 JASA 10 % 3,031.08 JUMLAH 33,341.84 DIBULATKAN 33,341.00

Pembuatan lapis pondasi atas (base) tebal 8 cm padat8/10 x 8,569.60 + 18,967.50 6,855.68 15,174.00

Biaya menggilas 1/150 x 145,500.00 + 120,550.00 970.00 803.67

Sewa motor walls 1/150 x 150,000.00 1,000.00

JUMLAH ( BELUM TERMASUK PPN ) 8,825.68 15,977.67 24,803.35 JASA 10 % 2,480.33 JUMLAH 27,283.68 DIBULATKAN 27,283.00

Pembuatan lapis pondasi atas (base) tebal 7 cm padat 7/10 x 8,569.60 + 18,967.50 5,998.72 13,277.25

Biaya menggilas 1/150 x 145,500.00 + 120,550.00 970.00 803.67

Sewa motor walls 1/150 x 150,000.00 1,000.00

JUMLAH ( BELUM TERMASUK PPN ) 7,968.72 14,080.92 22,049.64 JASA 10 % 2,204.96 JUMLAH 24,254.60 DIBULATKAN 24,254.00

100.0000 Lapisan Penetrasi 4 cm padat

0.2400 Krokos D 20 - 40 mm @ Rp. 70,000.00 16,800.00

0.4800 Split D 10 mm @ Rp. 120,000.00 57,600.00

3.5000 Split D 30 - 40 mm @ Rp. 120,000.00 420,000.00

1.2000 Split D 10 - 20 mm @ Rp. 120,000.00 144,000.00

1.2500 Kayu bakar @ Rp. 90,000.00 112,500.00 14.0000 org Pekerja @ Rp. 36,000.00 504,000.00 1.0000 org Mandor @ Rp. 40,000.00 40,000.00 1.5000 org Juru godog aspal @ Rp. 36,000.00 54,000.00 1.0000 org Masinis @ Rp. 37,500.00 37,500.00 1.0000 org Kenek @ Rp. 36,000.00 36,000.00 1.0000 org Penyemprot @ Rp. 35,000.00 35,000.00 400.0000 kg Aspal @ Rp. 10,650.00 4,260,000.00 80.0000 kg Aspal lem @ Rp. 10,650.00 852,000.00 1.0000 hr Sprayer (sewa) @ Rp. 48,000.00 48,000.00

JUMLAH ( BELUM TERMASUK PPN ) 706,500.00 5,910,900.00 6,617,400.00 DIBULATKAN 6,617,400.00

m2

m3

m3

m3

m3

m3

Tiap m2

Tiap m2

Tiap m2

m2

m3

m3

m3

m3

m3

Page 567: AHS 2008-Kota.xlsx

Analisa KPUT - 567

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1/100 x 706,500.00 + 5,910,900.00 7,065.00 59,109.00 Biaya menggilas

4/12,5/200 x 145,500.00 + 120,550.00 232.80 192.88 Sewa motor walls

1/200 x 150,000.00 750.00 JUMLAH ( BELUM TERMASUK PPN ) 8,047.80 59,301.88 67,349.68 JASA 10 % 6,734.97 JUMLAH 74,084.65 DIBULATKAN 74,084.00

KPUT 100.0000 Pengaspalan sand sheet (latasir), tebal 1 cm jerengM.8 125.0000 kg Aspal 10,650.00 1,331,250.00

1.0000 Pasair pasang @ Rp. 76,000.00 76,000.00

0.9000 Kayu bakar @ Rp. 90,000.00 81,000.00 0.2500 org Juru godog aspal @ Rp. 36,000.00 9,000.00 8.1000 org Pekerja @ Rp. 36,000.00 291,600.00 0.4000 org Mandor @ Rp. 40,000.00 16,000.00

JUMLAH ( BELUM TERMASUK PPN ) 316,600.00 1,488,250.00 1,804,850.00 DIBULATKAN 1,804,850.00

Aspal sand sheet 2 cm jereng (1 cm padat) 2/100 x 316,600.00 + 1,488,250.00 6,332.00 29,765.00

Biaya menggilas 1/500 x 145,500.00 + 120,550.00 291.00 241.10

Sewa motor walls 1/500 x 150,000.00 300.00

Aspal untuk lem 0,5 kg 0.5000 x 10,650.00 5,325.00

JUMLAH ( BELUM TERMASUK PPN ) 6,923.00 35,331.10 42,254.10 JASA 10 % 4,225.41 JUMLAH 46,479.51 DIBULATKAN 46,479.00

Aspal sand sheet 3 cm jereng (2 cm padat) 3/100 x 316,600.00 + 1,488,250.00 9,498.00 44,647.50

Biaya menggilas 1/500 x 145,500.00 + 120,550.00 291.00 241.10

Sewa motor walls 1/500 x 150,000.00 300.00

Aspal untuk lem 0,5 kg 0.5000 x 10,650.00 5,325.00

JUMLAH ( BELUM TERMASUK PPN ) 10,089.00 50,213.60 60,302.60 JASA 10 % 6,030.26 JUMLAH 66,332.86 DIBULATKAN 66,332.00

KPUT 100.0000 Pengaspalan sand sheet (latasir) tanpa aspal, tebal 1 cm jerengM.8 - kg Aspal 10,650.00 -

1.0000 Pasair pasang @ Rp. 76,000.00 76,000.00

0.9000 Kayu bakar @ Rp. 90,000.00 81,000.00 0.2500 org Juru godog aspal @ Rp. 36,000.00 9,000.00 8.1000 org Pekerja @ Rp. 36,000.00 291,600.00 0.4000 org Mandor @ Rp. 40,000.00 16,000.00

JUMLAH ( BELUM TERMASUK PPN ) 316,600.00 157,000.00 473,600.00 DIBULATKAN 473,600.00

Tiap m2

m2

m3

m3

Tiap m2

Tiap m2

m2

m3

m3

Page 568: AHS 2008-Kota.xlsx

Analisa KPUT - 568

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal 2/100 x 316,600.00 + 157,000.00 6,332.00 3,140.00

Biaya menggilas 1/500 x 145,500.00 + 120,550.00 291.00 241.10

Sewa motor walls 1/500 x 150,000.00 300.00

Aspal untuk lem 0,5 kg - x 10,650.00 -

JUMLAH ( BELUM TERMASUK PPN ) 6,923.00 3,381.10 10,304.10 JASA 10 % 1,030.41 JUMLAH 11,334.51 DIBULATKAN 11,334.00

Aspal sand sheet 3 cm jereng (2 cm padat) tanpa aspal 3/100 x 316,600.00 + 157,000.00 9,498.00 4,710.00

Biaya menggilas 1/500 x 145,500.00 + 120,550.00 291.00 241.10

Sewa motor walls 1/500 x 150,000.00 300.00

Aspal untuk lem 0,5 kg - x 10,650.00 -

JUMLAH ( BELUM TERMASUK PPN ) 10,089.00 4,951.10 15,040.10 JASA 10 % 1,504.01 JUMLAH 16,544.11 DIBULATKAN 16,544.00

10.0000 Mengecat marka jalan dengan Rettar 4.2500 kg Cat rettar @ Rp. 56,250.00 239,062.50 0.5700 ltr Minyak cat @ Rp. 14,000.00 7,980.00 2.2500 org Tukang cat @ Rp. 42,500.00 95,625.00 0.2300 org Kepala tukang cat @ Rp. 45,000.00 10,350.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00

JUMLAH ( BELUM TERMASUK PPN ) 177,975.00 247,042.50 425,017.50 DIBULATKAN 425,017.00

Mengecat marka jalan dengan rettar 1/10 x 177,975.00 + 247,042.50 17,797.50 24,704.25

JUMLAH ( BELUM TERMASUK PPN ) 17,797.50 24,704.25 42,501.75 JASA 10 % 4,250.18 JUMLAH 46,751.93 DIBULATKAN 46,751.00

1.0000 Mengecat marka jalan dengan Thermoplastic 1.6575 kg Cat marka @ Rp. 56,250.00 93,234.38 0.4500 kg Glasbit @ Rp. 30,000.00 13,500.00 1.0500 ltr Thinner @ Rp. 14,000.00 14,700.00 0.0750 jam Sewa Compressor @ Rp. 101,769.90 7,632.74 0.0750 jam Sewa Dumptruck @ Rp. 125,838.28 9,437.87 0.0100 ls Alat bantu @ Rp. 130,000.00 1,300.00 0.2250 org Tukang cat @ Rp. 42,500.00 9,562.50 0.6000 org Pekerja @ Rp. 36,000.00 21,600.00 0.0750 org Mandor @ Rp. 40,000.00 3,000.00

JUMLAH ( BELUM TERMASUK PPN ) 34,162.50 139,804.99 173,967.49 JASA 10 % 17,396.75 JUMLAH 191,364.24 DIBULATKAN 191,364.00

Tiap m2

Tiap m2

m2

Tiap m2

m2

Page 569: AHS 2008-Kota.xlsx

Analisa KPUT - 569

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

350.0000 Pemotongan aspal dengan mesin potong (cutter), 2 sisi 2.0000 bh Cutter @ Rp. 1,000,000.00 2,000,000.00 2.0000 hr Sewa mesin cutter @ Rp. 450,000.00 900,000.00 15.0000 ltr Solar @ Rp. 4,300.00 64,500.00 2.0000 org Tk. Cutter / masinis @ Rp. 37,500.00 75,000.00 2.0000 org Pekerja @ Rp. 36,000.00 72,000.00

JUMLAH ( BELUM TERMASUK PPN ) 147,000.00 2,964,500.00 3,111,500.00 DIBULATKAN 3,111,500.00

Pemotongan aspal dengan mesin potong (cutter), 2 sisi 1/350 x 147,000.00 + 2,964,500.00 420.00 8,470.00

JUMLAH ( BELUM TERMASUK PPN ) 420.00 8,470.00 8,890.00 JASA 10 % 889.00 JUMLAH 9,779.00 DIBULATKAN 9,779.00

Pemotongan aspal dengan mesin potong (cutter), 1 sisi 1/700 x 147,000.00 + 2,964,500.00 210.00 4,235.00

JUMLAH ( BELUM TERMASUK PPN ) 210.00 4,235.00 4,445.00 JASA 10 % 444.50 JUMLAH 4,889.50 DIBULATKAN 4,889.00

1.0000 Pembongkaran aspal dengan Jack Hammer 0.6600 hari Sewa mesin Jack Hammer @ Rp. 103,641.08 68,403.11 1.3200 ltr Solar @ Rp. 4,300.00 5,676.00 0.0400 org Tk. Jack Hammer / masinis @ Rp. 37,500.00 1,500.00 0.2500 org Pekerja @ Rp. 36,000.00 9,000.00 0.0630 org Mandor @ Rp. 40,000.00 2,520.00

JUMLAH ( BELUM TERMASUK PPN ) 13,020.00 74,079.11 87,099.11 JASA 10 % 8,709.91 JUMLAH 95,809.02 DIBULATKAN 95,809.00

ANALISA EXPANTION JOINTNo. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1.0000 Expantion joint 18.5000 kg Ashpaltic Joint @ Rp. 60,000.00 1,110,000.00 5.5000 kg Plate baja 5 mm @ Rp. 8,800.00 48,400.00

1.0000 Joint Filler @ Rp. 9,000.00 9,000.00

0.0150 Split 1/2 cm @ Rp. 190,000.00 2,850.00 6.5000 kg Gas Elpiji @ Rp. 4,500.00 29,250.00 0.1000 hr Sewa Jack Hammer @ Rp. 103,641.08 10,364.11 0.1000 hr Sewa Genset 2000 watt @ Rp. 1,671,260.11 167,126.01 0.1000 hr Sewa Compressor @ Rp. 763,274.26 76,327.43 0.1000 hr Sewa Stamper @ Rp. 112,023.60 11,202.36 0.1000 bh Mata cutter @ Rp. 1,000,000.00 100,000.00 0.1000 hr Sewa mesin cutter @ Rp. 450,000.00 45,000.00 1.0000 ls Alat bantu @ Rp. 130,000.00 130,000.00 1.0000 org Mekanik terlatih @ Rp. 45,000.00 45,000.00 4.5000 org Operator terlatih @ Rp. 45,000.00 202,500.00 0.1000 org Mandor @ Rp. 40,000.00 4,000.00

JUMLAH ( BELUM TERMASUK PPN ) 251,500.00 1,739,519.91 1,991,019.91 JASA 10 % 199,101.99 JUMLAH 2,190,121.90 DIBULATKAN 2,190,121.00

m1

Tiap m1

Tiap m1

m2

m1

m1

m3

Page 570: AHS 2008-Kota.xlsx

Analisa Alat - 570

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan ASPHALT MIXING PLANT E01

2 Tenaga Pw 150.00 HP 3 Kapasitas Cp 50.00 Ton/jam 4 Alat Baru : a. Umur Ekonomis A 10.00 Tahun

b. Jam Kerja dalam 1 Tahun W 1,500.00 Jam c. Harga Alat B 7,500,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 10.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 1,500.00 Jam Alat Baru c. Harga Alat B ' 7,500,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 750,000,000.00 Rupiah 2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.23852 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengmbalian Modal = ( B - C ) x D E 1,073,352.41 Rupiah W '

b. Asuransi dll = 0,002 x B ' F 10,000.00 Rupiah W '

Biaya Pasti Perjam = ( E + F ) G 1,083,352.41 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 80,625.00 Rupiah Bahan bakar pemanasan = 12 x 0,7 Cp x Ms H2 1,806,000.00 Rupiah Khusus AMP

material 2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 21,000.00 Rupiah 3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 625,000.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah 5 Pembantu Operator ( 3 org / Jam ) x U2 M 13,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 2,551,750.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 3,635,102.41 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun 2 Upah Operator / Sopir U1 5,625.00 Rp / Jam 3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam 4 Bahan bakar bensin Mb 4,500.00 Liter 5 Bahan bakar solar Ms 4,300.00 Liter 6 Minyak Pelumas Mp 14,000.00 Liter 7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 571: AHS 2008-Kota.xlsx

Analisa Alat - 571

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan ASPHALT FINISHER E02

2 Tenaga Pw 47.00 HP3 Kapasitas Cp 6.00 Ton4 Alat Baru : a. Umur Ekonomis A 6.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000 Jamc. Harga Alat B 715,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 6.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 715,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 71,500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.30071 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 96,752.07 RupiahW '

b. Asuransi dll = 0,002 x B ' F 715.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 97,467.07 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 25,262.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 6,580.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 44,687.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 86,655.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 184,122.07 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun 2 Upah Operator / Sopir U1 5,625.00 Rp / Jam 3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam 4 Bahan bakar bensin Mb 4,500.00 Liter 5 Bahan bakar solar Ms 4,300.00 Liter 6 Minyak Pelumas Mp 14,000.00 Liter 7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 572: AHS 2008-Kota.xlsx

Analisa Alat - 572

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan ASPHALT SPRAYER E03

2 Tenaga Pw 15.00 HP3 Kapasitas Cp 800.00 Liter4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000 Jamc. Harga Alat B 145,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 145,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 14,500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 21,818.28 RupiahW '

b. Asuransi dll = 0,002 x B ' F 145.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 21,963.28 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 8,062.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 2,100.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 9,062.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 29,350.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 51,313.28 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 573: AHS 2008-Kota.xlsx

Analisa Alat - 573

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan BULLDOZER 100 -150 HP E04

2 Tenaga Pw 140.00 HP3 Kapasitas Cp Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000 Jamc. Harga Alat B 700,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 700,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 70,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 105,329.61 RupiahW '

b. Asuransi dll = 0,002 x B ' F 700.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 106,029.61 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 75,250.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 19,600.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 43,750.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 148,725.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 254,754.61 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun 2 Upah Operator / Sopir U1 5,625.00 Rp / Jam 3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam 4 Bahan bakar bensin Mb 4,500.00 Liter 5 Bahan bakar solar Ms 4,300.00 Liter 6 Minyak Pelumas Mp 14,000.00 Liter 7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 574: AHS 2008-Kota.xlsx

Analisa Alat - 574

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan COMPRESSOR 4000 - 6500 L/M E05

2 Tenaga Pw 80.00 HP3 Kapasitas Cp Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000 Jamc. Harga Alat B 175,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 175,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 17,500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 26,332.40 RupiahW '

b. Asuransi dll = 0,002 x B ' F 175.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 26,507.40 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 43,000.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 11,200.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 10,937.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 75,262.50 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 101,769.90 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun 2 Upah Operator / Sopir U1 5,625.00 Rp / Jam 3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam 4 Bahan bakar bensin Mb 4,500.00 Liter 5 Bahan bakar solar Ms 4,300.00 Liter 6 Minyak Pelumas Mp 14,000.00 Liter 7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 575: AHS 2008-Kota.xlsx

Analisa Alat - 575

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN

1 Jenis Peralatan E15

2 Tenaga Pw 105.00 HP3 Kapasitas Cp 1.50 Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 840,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 840,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 84,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 126,395.53 RupiahW '

b. Asuransi dll = 0,002 x B ' F 840.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 127,235.53 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 56,437.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 14,700.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 52,500.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 133,762.50 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 260,998.03 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun 2 Upah Operator / Sopir U1 5,625.00 Rp / Jam 3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam 4 Bahan bakar bensin Mb 4,500.00 Liter 5 Bahan bakar solar Ms 4,300.00 Liter 6 Minyak Pelumas Mp 14,000.00 Liter 7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

WHEEL LOADER 1,0 - 1,6 M3

Page 576: AHS 2008-Kota.xlsx

Analisa Alat - 576

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan TANDEM ROLLER 6 - 8 T E17

2 Tenaga Pw 50.00 HP3 Kapasitas Cp 8.00 Ton4 Alat Baru a Umur Ekonomis A 5.00 Tahun

b Jam Kerja dalam 1 Tahun W 2,000.00 Jamc Harga Alat B 460,000,000.00 Rupiah

5 Alat yang dipakai a Umur Ekonomis A ' 5.00 Tahun Alat Baru b Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c Harga Alat B ' 460,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 46,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 69,216.60 RupiahW '

b. Asuransi dll = 0,002 x B ' F 460.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 69,676.60 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 26,875.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 7,000.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 28,750.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 72,750.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 142,426.60 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun 2 Upah Operator / Sopir U1 5,625.00 Rp / Jam 3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam 4 Bahan bakar bensin Mb 4,500.00 Liter 5 Bahan bakar solar Ms 4,300.00 Liter 6 Minyak Pelumas Mp 14,000.00 Liter 7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 577: AHS 2008-Kota.xlsx

Analisa Alat - 577

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan PNEUMATIC TYRE ROLLER 8 - 10 T E18

2 Tenaga Pw 60.00 HP3 Kapasitas Cp 10.00 Ton4 Alat Baru a Umur Ekonomis A 5.00 Tahun

b Jam Kerja dalam 1 Tahun W 1,800.00 Jamc Harga Alat B 510,000,000.00 Rupiah

5 Alat yang dipakai a Umur Ekonomis A ' 5.00 Tahun Alat Baru b Jam Kerja dalam 1 Tahun W ' 1,800.00 Jam Alat Baru c Harga Alat B ' 510,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 51,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 85,266.82 RupiahW '

b. Asuransi dll = 0,002 x B ' F 566.67 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 85,833.49 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 32,250.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 8,400.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 35,416.67 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 86,191.67 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 172,025.16 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 578: AHS 2008-Kota.xlsx

Analisa Alat - 578

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan DUMP TRUCK E09

2 Tenaga Pw 125.00 HP3 Kapasitas Cp 8.00 Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 145,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 145,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 14,500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 21,818.28 RupiahW '

b. Asuransi dll = 0,002 x B ' F 145.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 21,963.28 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 67,187.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 17,500.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 9,062.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 103,875.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 125,838.28 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 579: AHS 2008-Kota.xlsx

Analisa Alat - 579

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan GENERATOR SET E12

2 Tenaga Pw 175.00 HP3 Kapasitas Cp 125.00 KVA4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 440,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 440,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 44,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 66,207.18 RupiahW '

b. Asuransi dll = 0,002 x B ' F 440.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 66,647.18 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 94,062.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 24,500.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 27,500.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 156,187.50 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 222,834.68 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 580: AHS 2008-Kota.xlsx

Analisa Alat - 580

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan MOTOR GRADER > 100 HP E12

2 Tenaga Pw 125.00 HP3 Kapasitas Cp - -4 Alat Baru a Umur Ekonomis A 5.00 Tahun

b Jam Kerja dalam 1 Tahun W 2,000.00 Jamc Harga Alat B 880,000,000.00 Rupiah

5 Alat yang dipakai a Umur Ekonomis A ' 5.00 Tahun Alat Baru b Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c Harga Alat B ' 880,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 88,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 132,414.36 RupiahW '

b. Asuransi dll = 0,002 x B ' F 880.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 133,294.36 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 67,187.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 17,500.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 55,000.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 149,812.50 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 283,106.86 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 581: AHS 2008-Kota.xlsx

Analisa Alat - 581

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan VIBRATORY ROLLER 5 - 8 T E19

2 Tenaga Pw 75.00 HP3 Kapasitas Cp 7.00 Ton4 Alat Baru Umur Ekonomis A 4.00 Tahun

Jam Kerja dalam 1 Tahun W 2,000.00 JamHarga Alat B 500,000,000.00 Rupiah

5 Alat yang dipakai a Umur Ekonomis A ' 4.00 Tahun Alat Baru b Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c Harga Alat B ' 500,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 50,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.38629 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 86,915.05 RupiahW '

b. Asuransi dll = 0,002 x B ' F 500.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 87,415.05 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 40,312.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 10,500.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 31,250.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam =( H1 + H2 + I + K + L + M ) P 92,187.50 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 179,602.55 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 582: AHS 2008-Kota.xlsx

Analisa Alat - 582

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan WATER TANK TRUCK 3000 - 4000 L E23

2 Tenaga Pw 100.00 HP3 Kapasitas Cp 4,000.00 Liter4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 50,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 50,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 5,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 7,523.54 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 50.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 7,573.54 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 53,750.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 14,000.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 3,125.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 81,000.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 88,573.54 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 583: AHS 2008-Kota.xlsx

Analisa Alat - 583

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan JACK HAMMER E26

2 Tenaga Pw 3.00 HP3 Kapasitas Cp - Liter4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun

b. Jam Kerja dalam 1 Tahun W 1,000.00 Jamc. Harga Alat B 3,500,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 4.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 1,000.00 Jam Alat Baru c. Harga Alat B ' 3,500,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 350,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.38629 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 1,216.81 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 7.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 1,223.81 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 1,612.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 420.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 437.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 12,595.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 13,818.81 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 584: AHS 2008-Kota.xlsx

Analisa Alat - 584

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan TAMPER E25

2 Tenaga Pw 5.00 HP3 Kapasitas Cp 0.170 Ton4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun

b. Jam Kerja dalam 1 Tahun W 1,000.00 Jamc. Harga Alat B 3,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 4.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 1,000.00 Jam Alat Baru c. Harga Alat B ' 3,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 300,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.38629 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 1,042.98 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 6.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 1,048.98 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 2,687.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 700.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 375.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 13,887.50 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 14,936.48 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 585: AHS 2008-Kota.xlsx

Analisa Alat - 585

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan STONE CRUSHER E21

2 Tenaga Pw 220.00 HP3 Kapasitas Cp 50.00 Ton/Jam4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 491,500,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 491,500,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 49,150,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 73,956.43 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 491.50 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 74,447.93 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 118,250.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 30,800.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 30,718.75 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 2 org / Jam ) x U2 M 9,000.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 194,393.75 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 268,841.68 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 586: AHS 2008-Kota.xlsx

Analisa Alat - 586

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan THREE WHEEL ROLLER 6 - 8 T E16

2 Tenaga Pw 55.00 HP3 Kapasitas Cp 8.00 Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 125,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 125,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 12,500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 18,808.86 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 125.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 18,933.86 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 29,562.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 7,700.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 7,812.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 55,200.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 74,133.86 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 587: AHS 2008-Kota.xlsx

Analisa Alat - 587

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan CONCRETE VIBRATOR E20

2 Tenaga Pw 10.00 HP3 Kapasitas Cp - -4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun

b. Jam Kerja dalam 1 Tahun W 1,000.00 Jamc. Harga Alat B 12,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 4.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 1,000.00 Jam Alat Baru c. Harga Alat B ' 12,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 1,200,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.38629 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 4,171.92 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 24.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 4,195.92 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 5,375.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 1,400.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 1,500.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 18,400.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 22,595.92 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 588: AHS 2008-Kota.xlsx

Analisa Alat - 588

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan CONCRETE MIXER 0.3 - 0.6 M3 E06

2 Tenaga Pw 15.00 HP3 Kapasitas Cp 500.00 Liter4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 45,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 4.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 45,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 4,500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.38629 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 7,822.35 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 45.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 7,867.35 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 8,062.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 2,100.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 2,812.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 23,100.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 30,967.35 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 589: AHS 2008-Kota.xlsx

Analisa Alat - 589

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan CRANE 10 - 15 TON E07

2 Tenaga Pw 150.00 HP3 Kapasitas Cp 15.00 Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 300,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 300,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 30,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam a Biaya Pengembalian Modal = ( B - C ) x D E 45,141.26 Rupiah

W 'b Asuransi dll = 0,002 x B ' F 300.00 Rupiah

W ' Biaya Pasti Perjam = ( E + F ) G 45,441.26 Rp

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 80,625.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 21,000.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 18,750.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 130,500.00 Rp

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 175,941.26 Rp

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 590: AHS 2008-Kota.xlsx

Analisa Alat - 590

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan DUMP TRUCK 3 - 4 M3 E08

2 Tenaga Pw 100.00 HP3 Kapasitas Cp 6.00 Ton4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 100,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 100,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 10,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 15,047.09 RupiahW '

b. Asuransi dll = 0,002 x B ' F 100.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 15,147.09 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 53,750.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 14,000.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 6,250.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 84,125.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 99,272.09 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 591: AHS 2008-Kota.xlsx

Analisa Alat - 591

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan EXCAVATOR 80 - 140 HP E10

2 Tenaga Pw 80.00 HP3 Kapasitas Cp 0.50 M34 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 250,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 250,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 25,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 37,617.72 RupiahW '

b. Asuransi dll = 0,002 x B ' F 250.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 37,867.72 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 43,000.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 11,200.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 15,625.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 79,950.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 117,817.72 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 592: AHS 2008-Kota.xlsx

Analisa Alat - 592

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan FLAT BED TRUCK 3 - 4 M3 E11

2 Tenaga Pw 100.00 HP3 Kapasitas Cp 4.00 M34 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 250,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 250,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 25,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 37,617.72 RupiahW '

b. Asuransi dll = 0,002 x B ' F 250.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 37,867.72 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 53,750.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 14,000.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 15,625.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 93,500.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 131,367.72 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 593: AHS 2008-Kota.xlsx

Analisa Alat - 593

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan WATER PUMP 70 - 100 mm E22

2 Tenaga Pw 6.00 HP3 Kapasitas Cp - -4 Alat Baru : a. Umur Ekonomis A 2.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 5,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 2.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 5,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 500,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.65455 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 1,472.73 RupiahW '

b. Asuransi dll = 0,002 x B ' F 5.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 1,477.73 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 3,225.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 840.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 312.50 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 14,502.50 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 15,980.23 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 594: AHS 2008-Kota.xlsx

Analisa Alat - 594

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan FULVI MIXER E27

2 Tenaga Pw 75.00 HP3 Kapasitas Cp - -4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 100,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 100,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 10,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 15,047.09 RupiahW '

b. Asuransi dll = 0,002 x B ' F 100.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 15,147.09 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 40,312.50 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 10,500.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 6,250.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 67,187.50 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 82,334.59 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 595: AHS 2008-Kota.xlsx

Analisa Alat - 595

URAIAN ANALISA ALAT

No URAIAN KODE KOEF. SATUAN KET.

I URAIAN PERALATAN 1 Jenis Peralatan TRACK LOADER 75 - 100 HP E14

2 Tenaga Pw 90.00 HP3 Kapasitas Cp 1.60 M34 Alat Baru : a. Umur Ekonomis A 5.00 Tahun

b. Jam Kerja dalam 1 Tahun W 2,000.00 Jamc. Harga Alat B 300,000,000.00 Rupiah

5 Alat Yang Dipakai : a. Umur Ekonomis A ' 5.00 Tahun Alat Baru b. Jam Kerja dalam 1 Tahun W ' 2,000.00 Jam Alat Baru c. Harga Alat B ' 300,000,000.00 Rupiah Alat Baru

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C 30,000,000.00 Rupiah2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D 0.33438 -

( 1 + i )^A'-13 Biaya pasti per jam

a. Biaya Pengembalian Modal = ( B - C ) x D E 45,141.26 RupiahW '

b. Asuransi dll = 0,002 x B ' F 300.00 RupiahW '

Biaya Pasti Perjam = ( E + F ) G 45,441.26 Rupiah

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1 48,375.00 Rupiah

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I 12,600.00 Rupiah3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K 18,750.00 Rupiah

W '4 Operator = ( 1 org / Jam ) x U1 L 5,625.00 Rupiah5 Pembantu Operator ( 1 org / Jam ) x U2 M 4,500.00 Rupiah

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P 89,850.00 Rupiah

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T 135,291.26 Rupiah

V LAIN LAIN 1 Tingkat suku bunga ( i ) 20.00 % / Tahun2 Upah Operator / Sopir U1 5,625.00 Rp / Jam3 Upah Pembantu Operator / Pembantu Sopir U2 4,500.00 Rp / Jam4 Bahan bakar bensin Mb 4,500.00 Liter5 Bahan bakar solar Ms 4,300.00 Liter6 Minyak Pelumas Mp 14,000.00 Liter7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Page 596: AHS 2008-Kota.xlsx

Analisa - E 596

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : LATASTON ( HRS )SATUAN : M2 Analisa EI - 633

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.0113 4,500.00 51.01 2 Mandor ( L 03 ) Jam 0.0016 5,000.00 8.10

JUMLAH HARGA TENAGA 59.10

B BAHAN1 Agregat Kasar ( M 03 ) M3 0.0121 126,500.00 1,532.51 2 Agregat Halus ( M 04 ) M3 0.0232 79,750.00 1,850.41 3 Filler ( M 05 ) Kg 4.8004 750.00 3,600.33 4 Aspal ( M 10 ) Kg 5.2962 10,650.00 56,404.89

JUMLAH HARGA BAHAN 63,388.13

C PERALATAN1 Wheel Loader ( E 15 ) Jam 0.0011 260,998.03 289.87 2 AMP ( E 01 ) Jam 0.0016 3,635,102.41 5,886.24 3 Genset ( E 12 ) Jam 0.0016 222,834.68 360.83 4 Dump Truck ( E 09 ) Jam 0.0143 125,838.28 1,804.19 5 Aspal Finisher ( E 02 ) Jam 0.0020 184,122.07 372.68 6 Tandem Roller ( E 17 ) Jam 0.0017 142,426.60 245.14 7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0013 172,025.16 221.08 8 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 9,680.02

JUMLAH 73,127.26 JASA 10 % 7,312.73 JUMLAH ( BELUM TERMASUK PPN ) 80,439.99 DIBULATKAN 80,439.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 597: AHS 2008-Kota.xlsx

Analisa - E 597

URAIAN ANALISA HARGA SATUAN LATASTON ( HRS )SATUAN : M2 Analisa EI - 633

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat ( cara mekanik ) 2 Lokasi pekerjaan sepanjang jalan 3 Kondisi existing jalan sedang 4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km 5 Tebal lapisan padat t 0.03 m 6 Jam kerja efektif 1 hari Tk 7.00 Jam 7 Faktor kehilangan material

- Agregat Fh 1 1.10 - - Aspal Fh 2 1.05 -

8 Komposisi campuran HRS ( Spesifikasi ) - Coarse Agregat 20 - 40 % CA 29.50 % - Fine Agregat 47 - 67 % FA 56.50 % - Fraksi Filler 5 - 9 % FF 6.49 % - Aspal minimum 7,3 % As 7.51 %

9 Berat jenis bahan - HRS D1 2.24 t / m3 - Coarse Agregat dan fine agregat D2 1.80 t / m3 - Fraksi Filler D3 2.00 t / m3 - Aspal D4 1.03 t / m3

II METODA KERJA

1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP 2

3

4

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN a Agregat kasar = {( CA x D1 x t m3 ) x ( Fh 1 )}/ D2 M03 0.0121 m3 b Agregat halus = {( FA x D1 x t m3 ) x ( Fh 1 )}/ D2 M04 0.0232 m3 c Filler = {( FF x D1 x t m3 ) x ( Fh 1 )} M05 4.8004 Kg d Aspal = {( AS x D1 x t m3 ) x ( Fh 2 )}x1000 M10 5.2962 Kg

2 ALAT a Wheel Loader ( E 15 )

Kapasitas bucket V 1.50 m3 Faktor bucket Fb 0.90 - Faktor efisiensi alat Fa 0.83 - Waktu siklus Ts 1 - Muat T1 1.50 menit - Lain lain T2 0.50 menit

Ts 1 2.00 menit

Kap Produksi / Jam = D2 x V x Fb x Fa x 60 Q1 900.40 m2 D1 x t x Ts1

Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0011 Jam

Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke dalam Dump Truck dan diangkut ke lokasi pekerjaan.

Campuran panas HRS dihampar dengan Finisher dan dipadatakan dengan Tandem dan Peneumatic Tire Roller

Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan menggunakan alat bantu

Page 598: AHS 2008-Kota.xlsx

Analisa - E 598

No URAIAN KODE KOEF. SATUAN KET.

b Aspalt Mixing Plant ( AMP ) ( E 01 ) Kapasitas produksi V 50.00 ton / jam faktor Efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = V x Fa Q2 617.56 m2

D1 x t

Koefisien Alat / m2 = 1 / Q2 ( E 01 ) 0.0016 Jam

c Generator Set ( Genset ) ( E 12 ) Kapasitas produksi / jam = sama dengan AMP Q3 617.56 m2

Koefisien Alat / m2 = 1 / Q3 ( E 12 ) 0.0016 Jam

d Dump Truk ( DT ) ( E 09 ) Kapasitas bak V 8.00 ton Faktor efisiensi alat Fa 0.83 - Kecepatan rata rata bermuatan v1 40.00 km / jam Kecepatan rata rata kosong v2 50.00 km / jam Kapasitas AMP batch Q2 b 0.50 ton Waktu menyiapkan 1 batch HRS Tb 1.00 menit Waktu Siklus Ts2 - Mengisi bak = ( V : Q2b ) x Tb T1 16.00 menit - Angkut = ( L : v1 ) x 60 menit T2 30.00 menit - Tunggu + Dumping + Putar T3 15.00 menit - Kembali = ( L : v2 ) x 60 menit T4 24.00 menit

Ts2 85.00 menit

Kapasitas Produksi / jam = V x Fa x 60 Q4 69.75 m2 D1 x t x Ts2

Koefisien Alat / m2 = 1 / Q4 ( E 09 ) 0.0143 Jam

e Finisher ( E 02 ) Kapasitas produksi V 40.00 km / jam Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = V x Fa Q5 494.05 m2 D1 x t

Koefisien Alat / m2 = 1 / Q5 ( E 02 ) 0.0020 Jam

f Tandem Roller ( E 17 ) Kecepatan rata rata alat v 3.50 km/jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 6.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q6 581.00 m2

n

Koefisien Alat / m2 = 1 / Q6 ( E 17 ) 0.0017 Jam

Page 599: AHS 2008-Kota.xlsx

Analisa - E 599

No URAIAN KODE KOEF. SATUAN KET.

g Pneumatic Tire Roller ( E 18 ) Kecepatan rata rata alat v 5.00 km / jam Lebar efektif pemadatan b 1.50 m Jumlah lintasan n 8.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q7 778.12 m2

n

Koefisien Alat / m2 = 1 / Q7 ( E 18 ) 0.0013 Jam

h Alat Bantu Diperlukan : - Kereta dorong = 2 bh Lump sum - Skop = 3 bh - Garpu = 2 bh - Tongkat kontrol ketebalan hamparan

3 TENAGA Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 617.56 m2 / jam Produksi HRS / hari = Tk x Q2 Qt 4,322.92 m2

Kebutuhan tenaga - Pekerja P 7.00 orang - Mandor M 1.00 orang

Koefisien tenaga /m2 : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0113 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0016 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 80,439.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . M2

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 600: AHS 2008-Kota.xlsx

Analisa - E 600

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : LASTON ( AC )SATUAN : M2 Analisa EI - 634

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.0217 4,500.00 97.59 2 Mandor ( L 03 ) Jam 0.0022 5,000.00 10.84

JUMLAH HARGA TENAGA 108.43

B BAHAN1 Agregat Kasar ( M 03 ) M3 0.0336 126,500.00 4,254.51 2 Agregat Halus ( M 04 ) M3 0.0149 79,750.00 1,184.29 3 Filler ( M 05 ) Kg 4.8015 750.00 3,601.13 4 Aspal ( M 10 ) Kg 6.6150 10,650.00 70,449.75

JUMLAH HARGA BAHAN 79,489.67

C PERALATAN1 Wheel Loader ( E 15 ) Jam 0.0015 260,998.03 388.22 2 AMP ( E 01 ) Jam 0.0022 3,635,102.41 7,883.35 3 Genset ( E 12 ) Jam 0.0022 222,834.68 483.26 4 Dump Truck ( E 09 ) Jam 0.0348 125,838.28 4,376.89 5 Aspal Finisher ( E 02 ) Jam 0.0027 184,122.07 499.13 6 Tandem Roller ( E 17 ) Jam 0.0016 142,426.60 228.80 7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0023 172,025.16 394.78 8 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 14,754.42

JUMLAH 94,352.52 JASA 10 % 9,435.25 JUMLAH ( BELUM TERMASUK PPN ) 103,787.78 DIBULATKAN 103,787.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 601: AHS 2008-Kota.xlsx

Analisa - E 601

URAIAN ANALISA HARGA SATUAN LASTON ( AC )SATUAN : M2 Analisa EI - 634

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat 2 Lokasi pekerjaan sepanjang jalan 3 Kondisi existing jalan sedang 4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km 5 Tebal lapisan ( AC ) padat t 0.04 m 6 Jam kerja efektif 1 hari Tk 7.00 Jam 7 Faktor kehilangan material

- Agregat Fh 1 1.10 - - Aspal Fh 2 1.05 -

8 Komposisi campuran AC ( Spesifikasi ) - Coarse Agregat 30 - 50 % CA 61.15 % - Fine Agregat 39 - 59 % FA 27.00 % - Filler 4,5 - 7,5 % FF 4.85 % - Aspal minimum 6,7 % As 7.00 %

9 Berat jenis bahan - AC D1 2.25 t / m3 - Coarse Agregat dan fine agregat D2 1.80 t / m3 - Filler D3 2.00 t / m3 - Aspal D4 1.03 t / m3

II METODA KERJA

1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP 2

3

4

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN a Agregat kasar = {( CA x D1 x t m3 ) x ( Fh 1 )}/ D2 M03 0.034 m3 b Agregat halus = {( FA x D1 x t m3 ) x ( Fh 1 )}/ D2 M04 0.015 m3 c Filler = {( FF x D1 x t m3 ) x ( Fh 1 )} M05 4.802 Kg d Aspal = {( AS x D1 x t m3 ) x ( Fh 2 )}x1000 M10 6.615 Kg

2 ALAT a Wheel Loader ( E 15 )

Kapasitas bucket V 1.50 m3 Faktor bucket Fb 0.90 - Faktor efisiensi alat Fa 0.83 - Waktu siklus Ts 1 - Muat T1 1.50 menit - Lain lain T2 0.50 menit

Ts 1 2.00 menit

Kap Produksi / Jam = D2 x V x Fb x Fa x 60 Q1 672.30 m3 D1 x t x Ts1

Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0015 Jam

Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke dalam Dump Truck dan diangkut ke lapangan

Campuran panas AC dihampar dengan Finisher dan dipadatakan dengan Tandem dan Tire Roller

Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan menggunakan alat bantu

Page 602: AHS 2008-Kota.xlsx

Analisa - E 602

No URAIAN KODE KOEF. SATUAN KET.

b Aspalt Mixing Plant ( AMP ) ( E 01 ) Kapasitas produksi V 50.00 ton / jam faktor Efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = V x Fa Q2 461.11 m2

D1 x t

Koefisien Alat / m2 = 1 / Q2 ( E 01 ) 0.0022 Jam

c Generator Set ( Genset ) ( E 12 ) Kapasitas produksi / jam = sama dengan AMP Q3 461.11 m2

Koefisien Alat / m2 = 1 / Q3 ( E 12 ) 0.0022 Jam

d Dump Truk ( DT ) ( E 09 ) Kapasitas bak V 4.00 m3 Faktor efisiensi alat Fa 0.83 - Kecepatan rata rata bermuatan v1 40.00 km / jam Kecepatan rata rata kosong v2 50.00 km / jam Kapasitas AMP batch Q2 b 0.50 ton Waktu menyiapkan 1 batch AC Tb 1.00 menit Waktu Siklus Ts2 - Mengisi bak = ( V : Q2b ) x Tb T1 8.00 menit - Angkut = ( L : v1 ) x 60 menit T2 29.99 menit - Tunggu + Dumping + Putar T3 15.00 menit - Kembali = ( L : v2 ) x 60 menit T4 23.99 menit

Ts2 76.98 menit

Kapasitas Produksi / jam = V x Fa x 60 Q4 28.75 m2 D1 x t x Ts2

Koefisien Alat / m2 = 1 / Q4 ( E 09 ) 0.0348 Jam

e Finisher ( E 02 ) Kapasitas produksi V 40.00 ton / jam Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = V x Fa Q5 368.89 m2 D1 x t

Koefisien Alat / m2 = 1 / Q5 ( E 02 ) 0.0027 Jam

f Tandem Roller ( E 17 ) Kecepatan rata rata alat v 2.50 km / jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 4.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q6 622.50 m2

n

Koefisien Alat / m2 = 1 / Q6 ( E 17 ) 0.0016 Jam

Page 603: AHS 2008-Kota.xlsx

Analisa - E 603

No URAIAN KODE KOEF. SATUAN KET.

g Pneumatic Tire Roller ( E 18 ) Kecepatan rata rata alat v 3.50 km / jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 8.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q7 435.75 m2

n

Koefisien Alat / m2 = 1 / Q7 ( E 18 ) 0.0023 Jam

h Alat Bantu Diperlukan : - Rambu = 2 bh - Kereta dorong = 2 bh Lump sum - Skop = 3 bh - Garpu = 2 bh - Tongkat kontrol ketebalan hamparan

3 TENAGA Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 461.11 m2 / jam Produksi AC / hari = Tk x Q2 Qt 3,227.78 m2

Kebutuhan tenaga - Pekerja P 10.00 orang - Mandor M 1.00 orang

Koefisien tenaga /m2 : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0217 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0022 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 103,787.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . M2

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 604: AHS 2008-Kota.xlsx

Analisa - E 604

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : ASPHALT TREATED BASE ( ATB )SATUAN : M3 Analisa EI - 635

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.3880 4,500.00 1,745.78 2 Mandor ( L 03 ) Jam 0.0554 5,000.00 277.11

JUMLAH HARGA TENAGA 2,022.89

B BAHAN1 Agregat Kasar ( M 03 ) M3 0.7028 126,500.00 88,901.39 2 Agregat Halus ( M 04 ) M3 0.5341 79,750.00 42,595.36 3 Filler ( M 05 ) Kg 139.2 750.00 104,399.98 4 Aspal ( M 10 ) Kg 157.0 10,650.00 1,672,049.95

JUMLAH HARGA BAHAN 1,907,946.68

C PERALATAN1 Wheel Loader ( E 15 ) Jam 0.0380 260,998.03 9,921.09 2 AMP ( E 01 ) Jam 0.0554 3,635,102.41 201,463.51 3 Genset ( E 12 ) Jam 0.0554 222,834.68 12,349.87 4 Dump Truck ( E 09 ) Jam 0.4906 125,838.28 61,740.65 5 Aspal Finisher ( E 02 ) Jam 0.0767 184,122.07 14,116.03 6 Tandem Roller ( E 17 ) Jam 0.0430 142,426.60 6,128.51 7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0321 172,025.16 5,526.91 8 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 311,746.57

JUMLAH 2,221,716.14 JASA 10 % 222,171.61 JUMLAH ( BELUM TERMASUK PPN ) 2,443,887.75 DIBULATKAN 2,443,887.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 605: AHS 2008-Kota.xlsx

Analisa - E 605

URAIAN ANALISA HARGA SATUAN ASPHALT TREATED BASE ( ATB )

SATUAN : M3 Analisa EI - 635

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat ( Cara mekanik ) 2 Lokasi pekerjaan sepanjang jalan 3 Kondisi existing jalan sedang 4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km 5 Tebal lapisan ( ATB ) padat t 0.04 m 6 Jam kerja efektif 1 hari Tk 7.00 Jam 7 Faktor kehilangan material

- Agregat Fh 1 1.10 - - Aspal Fh 2 1.05 -

8 Komposisi campuran ATB ( Spesifikasi ) - Coarse Agregat 40 - 60 % CA 50.00 % - Fine Agregat 26 - 49,5 % FA 38.00 % - Fraksi Filler 4,5 - 7,5 % FF 5.50 % - Aspal minimum 6 % As 6.50 %

9 Berat jenis bahan

- ATB D1 2.30 t / m3 - Coarse Agregat dan fine agregat D2 1.80 t/m3 - Fraksi Filler D3 2.00 t/m3 - Aspal D4 1.03 t/m3

II METODA KERJA 1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP 2

3

4

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN a Agregat kasar = {( CA x D1 x 1 m3 ) x ( Fh 1 )}/ D2 M03 0.7028 m3 b Agregat halus = {( FA x D1 x 1 m3 ) x ( Fh 1 )}/ D2 M04 0.5341 m3 c Filler = {( FF x D1 x 1 m3 ) x ( Fh 1 )} M05 139.2 Kg d Aspal = {( AS x D1 x 1 m3 ) x ( Fh 2 )} M10 157.0 Kg

2 ALAT a Wheel Loader ( E 15 )

Kapasitas bucket V 1.50 m3 Faktor bucket Fb 0.90 - Faktor efisiensi alat Fa 0.83 - Waktu siklus Ts 1 - Muat T1 1.50 menit - Lain lain T2 0.50 menit

Ts 1 2.00 menit

Kap Produksi / Jam = D2 x V x Fb x Fa x 60 Q1 26.31 m3 D1 x Ts1

Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0380 Jam

Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke dalam Dump truck dan diangkut ke lokasi pekerjaan

Campuran panas ATB dihampar dengan Finisher dan dipadatakan dengan Tandem dan Pneumatic Roller

Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan menggunakan alat bantu

Page 606: AHS 2008-Kota.xlsx

Analisa - E 606

No URAIAN KODE KOEF. SATUAN KET.

b Aspalt Mixing Plant ( AMP ) ( E 01 ) Kapasitas produksi V 50.00 ton / jam Faktor Efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = V x Fa Q2 18.04 m3

D1

Koefisien Alat / m3 = 1 / Q2 ( E 01 ) 0.0554 Jam

c Generator Set ( Genset ) ( E 12 ) Kapasitas produksi / jam = sama dengan AMP Q3 18.04 m3

Koefisien Alat / m3 = 1 / Q3 ( E 12 ) 0.0554 Jam

d Dump Truk ( DT ) ( E 09 ) Kapasitas bak V 8.00 ton Faktor efisiensi alat Fa 0.83 - Kecepatan rata rata bermuatan v1 40.00 km / jam Kecepatan rata rata kosong v2 50.00 km / jam Kapasitas AMP batch Q2 b 0.50 ton Waktu menyiapkan 1 batch ATB Tb 1.00 menit Waktu Siklus Ts2 - Mengisi bak = ( V : Q2b ) x Tb T1 16.00 menit - Angkut = ( L : v1 ) x 60 menit T2 29.99 menit - Tunggu + Dumping + Putar T3 15.00 menit - Kembali = ( L : v2 ) x 60 menit T4 23.99 menit

Ts2 84.99 menit

Kapasitas Produksi / jam = V x Fa x 60 Q4 2.04 m3 D1 x Ts2

Koefisien Alat / m3 = 1 / Q4 ( E 09 ) 0.4906 Jam

e Finisher Kapasitas produksi V 40.00 ton/jam Faktor efisiensi alat Fa 0.75 -

Kapasitas produksi / jam = V x Fa Q5 13.04 m3 D1

Koefisien Alat / m3 = 1 / Q5 ( E 02 ) 0.0767 Jam

f Tandem Roller ( E 17 ) Kecepatan rata rata alat v 3.50 km / jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 6.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q6 23.24 m3

n

Koefisien Alat / m3 = 1 / Q6 ( E 17 ) 0.0430 Jam

Page 607: AHS 2008-Kota.xlsx

Analisa - E 607

No URAIAN KODE KOEF. SATUAN KET.

g Pneumatic Tire Roller ( E 18 ) Kecepatan rata rata alat v 5.00 km / jam Lebar efektif pemadatan b 1.50 m Jumlah lintasan n 8.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q7 31.12 m3

n

Koefisien Alat / m3 = 1 / Q7 ( E 18 ) 0.0321 Jam

h Alat Bantu Diperlukan : - Kereta dorong = 2 bh Lump sum - Skop = 3 bh - Garpu = 2 bh - Tongkat kontrol ketebalan hamparan

3 TENAGA Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 18.04 m3 / jam Produksi ATB / hari = Tk x Q2 Qt 126.30 m3

Kebutuhan tenaga - Pekerja P 7.00 orang - Mandor M 1.00 orang

Koefisien tenaga /m2 : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.3880 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0554 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 2,443,887.00 / M3

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . . M2

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 608: AHS 2008-Kota.xlsx

Analisa - E 608

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)SATUAN : LITER Analisa EI - 611

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.0301 4,500.00 135.54 2 Mandor ( L 03 ) Jam 0.0060 5,000.00 30.12

JUMLAH HARGA TENAGA 165.66

B BAHAN1 Aspal ( M 10 ) ( M 10 ) Kg 0.6417 10,650.00 6,834.30 2 Karosene ( M 11 ) ( M 11 ) Liter 0.4889 1,000.00 488.90

JUMLAH HARGA BAHAN 7,323.19

C PERALATAN1 Asphalt Sprayer ( E 03 ) Jam 0.0030 51,313.28 154.56 2 Compresor ( E 05 ) Jam 0.0031 101,769.90 318.03 3 Dump Truck ( E 08 ) Jam 0.0030 125,838.28 379.03

JUMLAH HARGA PERALATAN 851.62

JUMLAH 8,340.47 JASA 10 % 834.05 JUMLAH ( BELUM TERMASUK PPN ) 9,174.52 DIBULATKAN 9,174.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 609: AHS 2008-Kota.xlsx

Analisa - E 609

URAIAN ANALISA HARGA SATUAN LAPIS RESAP PENGIKAT

SATUAN : L Analisa EI - 611

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat 2 Lokasi pekerjaan sepanjang jalan 3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00 Km 4 Jam kerja efektif 1 hari Tk 7.00 Jam 5 Faktor kehilangan material Fh 1.10 - 6 Komposisi campuran AC ( Spesifikasi )

- Aspal AC - 10 atau AC - 20 AS 56 % 100 Bagian - Minyak Flux / pencair K 44 % 80 Bagian

7 Berat jenis bahan - Aspal AC - 10 atau AC - 20 D1 1.05 Kg / Lt - Minyak Flux / pencair D2 0.80 Kg / Lt

8 Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan

II METODA KERJA 1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal cair 2 Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor 3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan dilapis 4 Angkutan aspal dan minyak Flux menggunakan Dump truck

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN

Untuk mendapatkan 1 liter lapis resap pengikat diperlukan ( 1 Liter x Fh ) PC 1.1000 liter Campuran

a Aspal = AS x PC x D1 M10 0.6417 kg b Kerosene = K x PC M11 0.4889 liter

2 ALAT a Asphalt Sprayer ( E 03 )

Kapasitas alat V 800.00 liter Faktor efisiensi alat Fa 0.83 - Waktu siklus ( termasuk proses pemanasan ) Ts 2.00 jam

Kap Produksi / Jam = V x Fa Q1 332.00 liter Ts

Koefisien Alat / Liter = 1 / Q1 ( E 03 ) 0.0030 jam

b Air Compresor ( E 05 ) Kapasitas alat -----------> Diambil V 400.00 m2 / jam Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.80 liter / m2

Kapasitas produksi / jam = V x Ap Q2 320.00 liter

Koefisien Alat / liter = 1 / Q2 ( E 05 ) 0.0031 jam

Page 610: AHS 2008-Kota.xlsx

Analisa - E 610

No URAIAN KODE KOEF. SATUAN KET.

c Dump Truk ( DT ) ( E 08 ) Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat Asphalt Sprayer

Kapasitas Produksi / jam = V x Fa Q3 332.00 liter Ts

Koefisien Alat / m2 = 1 / Q3 ( E 08 ) 0.0030 jam

3 TENAGA Produksi menentukan : ASPALT FINISHER Q4 332.00 Liter Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 2,324.00 Liter

Kebutuhan tenaga - Pekerja P 10.00 orang - Mandor M 2.00 orang

Koefisien tenaga /liter : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0301 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0060 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 9,174.00 / LITER

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . . Liter

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 611: AHS 2008-Kota.xlsx

Analisa - E 611

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KLAS ASATUAN : M3 Analisa EI - 511

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.4373 4,500.00 1,967.87 2 Mandor ( L 03 ) Jam 0.0625 5,000.00 312.36

JUMLAH HARGA TENAGA 2,280.23

B BAHAN1 Agregat Kasar ( M 03 ) M3 0.7680 126,500.00 97,152.00 2 Agregat Halus ( M 04 ) M3 0.4320 79,750.00 34,452.00

JUMLAH HARGA BAHAN 131,604.00

C PERALATAN1 Wheel Loader ( E 15 ) Jam 0.0625 260,998.03 16,305.10 2 Dump Truck ( E 09 ) Jam 0.1994 125,838.28 25,089.66 3 Motor Grader ( E 13 ) Jam 0.0117 283,106.86 3,316.18 4 Vibratory Roller ( E 19 ) Jam 0.0178 179,602.55 3,205.76 5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043 172,025.16 736.92 6 Water Tank Truck ( E 23 ) Jam 0.0211 88,573.54 1,867.51 7 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 51,021.13

JUMLAH 184,905.36 JASA 10 % 18,490.54 JUMLAH ( BELUM TERMASUK PPN ) 203,395.90 DIBULATKAN 203,395.00

UNTUK 1 M2 TEBAL 20 CM 40,679.00 UNTUK 1 M2 TEBAL 15 CM 30,509.00 UNTUK 1 M2 TEBAL 10 CM 20,339.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 612: AHS 2008-Kota.xlsx

Analisa - E 612

URAIAN ANALISA HARGA SATUAN LAPIS PONDASI AGREGAT KLAS A

SATUAN : M3 Analisa EI - 511

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat Cara mekanik 2 Lokasi pekerjaan sepanjang jalan 3 Kondisi existing jalan sedang 4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km 5 Tebal Agregat padat t 0.15 m 6 Faktor kembang material ( padat - lepas ) Fk 1.20 7 Jam kerja efektif per hari Tk 7.00 Jam 8 Proporsi campuran

- Agregat Kasar Ak 64.00 % Tabel; 5.1.2 (a) - Agregat halus Ah 36.00 %

II METODA KERJA 1

2

3

4

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN a Agregat kasar = Ak x 1 m3 x Fk M03 0.7680 m3 b Agregat halus = Ah x 1 m3 x Fk M04 0.4320 m3

2 ALAT a Wheel Loader ( E 15 )

Kapasitas bucket V 1.50 m3 Faktor bucket Fb 0.90 - Faktor efisiensi alat Fa 0.83 - Waktu siklus Ts 1 - Mencampur T1 2.50 menit - Memuat dan Lain lain T2 1.00 menit

Ts 1 3.50 menit

Kap Produksi / Jam = V x Fb x Fa x 60 Q1 16.01 m3 Fk x Ts1

Koefisien Alat / m3 = 1 / Q1 ( E 15 ) 0.0625 Jam

b Dump Truk ( DT ) ( E 09 ) Kapasitas bak V 6.00 m3 Faktor efisiensi alat Fa 0.83 - Kecepatan rata rata bermuatan v1 45.00 km / jam Kecepatan rata rata kosong v2 60.00 km / jam Waktu Siklus Ts2 - Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65 menit - Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99 menit - lain lain termasuk menurunkan Agregat T3 3.00 menit

Ts2 49.65 menit

WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di Base camp

Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dg motor Grader

Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan dengan Tandem Roller & PTR

Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level permukaan dengan menggunakan alat bantu

Page 613: AHS 2008-Kota.xlsx

Analisa - E 613

No URAIAN KODE KOEF. SATUAN KET.

Kapasitas Produksi / jam = V x Fa x 60 Q2 5.02 m3 Fk x Ts2

Koefisien Alat / m3 = 1 / Q2 ( E 09 ) 0.1994 Jam

c Motor Grader ( E 13 ) Panjang hamparan Lh 50.00 m Lebar efektif kerja blade b 2.40 m Faktor Efisiensi alat Fa 0.83 - Kecepatan rata rata alat v 4.00 km / jam Jumlah lintasan n 6.00 Lintas 3 x pp Waktu siklus Ts 3 - Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 0.75 menit - Lain lain T2 1.00 menit

Ts 3 1.75 menit

Kapasitas produksi / jam = Lh x b x t x Fa x 60 Q3 85.37 m3 n x Ts 3

Koefisien Alat / m3 = 1 / Q3 ( E 02 ) 0.0117 Jam

d Vibratory Roller ( E 19 ) Kecepatan rata rata alat v 3.00 km / jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 8.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q4 56.03 m3

n

Koefisien Alat / m3 = 1 / Q4 ( E 19 ) 0.0178 Jam

e Pneumatic Tire Roller ( E 18 ) Kecepatan rata rata alat v 5.00 km/jam Lebar efektif pemadatan b 1.50 m Jumlah lintasan n 4.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q5 233.44 m3

n

Koefisien Alat / m3 = 1 / Q5 ( E 18 ) 0.0043 Jam

f Water Tank Truck ( E 23 ) Volume tangki air v 4.00 m3 Kebutuhan air / m3 agregat padat Wc 0.07 m3 Pengisian tangki / jam n 1.00 kali Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = v x n x Fa Q6 47.43 m3

Wc

Koefisien Alat / m3 = 1 / Q6 ( E 23 ) 0.0211 Jam

Page 614: AHS 2008-Kota.xlsx

Analisa - E 614

No URAIAN KODE KOEF. SATUAN KET.

g Alat Bantu Diperlukan :

- Kereta dorong = 2 bh Lump sum - Skop = 3 bh - Garpu = 2 bh

3 TENAGA Produksi menentukan : WHEEL LOADER Q1 16.01 m3 / jam Produksi Agregat / hari = Tk x Q1 Qt 112.05 m3

Kebutuhan tenaga - Pekerja P 7.00 orang - Mandor M 1.00 orang

Koefisien tenaga /m2 : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.4373 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0625 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 203,395.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . . M3

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 615: AHS 2008-Kota.xlsx

Analisa - E 615

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KLAS BSATUAN : M3 Analisa EI - 512

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.4373 4,500.00 1,967.87 2 Mandor ( L 03 ) Jam 0.0625 5,000.00 312.36

JUMLAH HARGA TENAGA 2,280.23

B BAHAN1 Agregat Kasar ( M 03 ) M3 0.7080 126,500.00 89,562.00 2 Agregat Halus ( M 04 ) M3 0.4920 79,750.00 39,237.00

JUMLAH HARGA BAHAN 128,799.00

C PERALATAN1 Wheel Loader ( E 15 ) Jam 0.0625 260,998.03 16,305.10 2 Dump Truck ( E 09 ) Jam 0.1994 125,838.28 25,089.66 3 Motor Grader ( E 13 ) Jam 0.0117 283,106.86 3,316.18 4 Vibratory Roller ( E 19 ) Jam 0.0178 179,602.55 3,205.76 5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043 172,025.16 736.92 6 Water Tank Truck ( E 23 ) Jam 0.0211 88,573.54 1,867.51 7 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 51,021.13

JUMLAH 182,100.36 JASA 10 % 18,210.04 JUMLAH ( BELUM TERMASUK PPN ) 200,310.40 DIBULATKAN 200,310.00

UNTUK 1 M2 TEBAL 20 CM 40,062.00 UNTUK 1 M2 TEBAL 15 CM 30,046.00 UNTUK 1 M2 TEBAL 10 CM 20,031.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan

2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran

3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 616: AHS 2008-Kota.xlsx

Analisa - E 616

URAIAN ANALISA HARGA SATUAN LAPIS PONDASI AGREGAT KLAS B

SATUAN : M3 Analisa EI - 512

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat 2 Lokasi pekerjaan sepanjang jalan 3 Kondisi existing jalan sedang 4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km 5 Tebal Agregat padat t 0.15 m 6 Faktor kembang material ( padat - lepas ) Fk 1.20 7 Jam kerja efektif per hari Tk 7.00 Jam 8 Proporsi campuran

- Agregat Kasar Ak 59.00 % Tabel; 5.1.2 (a) - Agregat halus Ah 41.00 %

II METODA KERJA 1

2

3

4

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN a Agregat kasar = Ak x 1 m3 x Fk M03 0.7080 m3 b Agregat halus = Ah x 1 m3 x Fk M04 0.4920 m3

2 ALAT a Wheel Loader ( E 15 )

Kapasitas bucket V 1.50 m3 Faktor bucket Fb 0.90 - Faktor efisiensi alat Fa 0.83 - Waktu siklus Ts 1 - Mencampur T1 2.50 menit - Memuat dan Lain lain T2 1.00 menit

Ts 1 3.50 menit

Kap Produksi / Jam = V x Fb x Fa x 60 Q1 16.01 m3 Fk x Ts1

Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0625 Jam

b Dump Truk ( DT ) ( E 09 ) Kapasitas bak V 6.00 m3 Faktor efisiensi alat Fa 0.83 - Kecepatan rata rata bermuatan v1 45.00 km / jam Kecepatan rata rata kosong v2 60.00 km / jam Waktu Siklus Ts2 - Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65 menit - Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99 menit - lain lain termasuk menurunkan Agregat T3 3.00 menit

Ts2 49.65 menit

WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di Base camp

Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dengan motor Grader

Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan dengan Tandem Roller & PTR

Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level permukaan dengan menggunakan alat bantu

Page 617: AHS 2008-Kota.xlsx

Analisa - E 617

No URAIAN KODE KOEF. SATUAN KET.

Kapasitas Produksi / jam = V x Fa x 60 Q2 5.02 m3 Fk x Ts2

Koefisien Alat / m2 = 1 / Q2 ( E 09 ) 0.1994 Jam

c Motor Grader ( E 13 ) Panjang hamparan Lh 50.00 m Lebar efektif kerja blade b 2.40 m Faktor Efisiensi alat Fa 0.83 - Kecepatan rata rata alat v 4.00 km / jam Jumlah lintasan n 6.00 Lintas 3 x pp Waktu siklus Ts 3 - Perataan 1 Lintasan = ( Lh x 60 ) : ( v x 1000 ) T1 0.75 menit - Lain lain T2 1.00 menit

Ts 3 1.75 menit

Kapasitas produksi / jam = Lh x b x t x Fa x 60 Q3 85.37 m3 n x Ts 3

Koefisien Alat / m2 = 1 / Q3 ( E 02 ) 0.0117 Jam

d Vibratory Roller ( E 17 ) Kecepatan rata rata alat v 3.00 km / jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 8.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q4 56.03 m3

n

Koefisien Alat / m2 = 1 / Q4 ( E 17 ) 0.0178 Jam

e Pneumatic Tire Roller ( E 18 ) Kecepatan rata rata alat v 5.00 km / jam Lebar efektif pemadatan b 1.50 m Jumlah lintasan n 4.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q5 233.44 m3

n

Koefisien Alat / m2 = 1 / Q5 ( E 18 ) 0.0043 Jam

f Water Tank Truck ( E 23 ) Volume tangki air v 4.00 km / jam Kebutuhan air / m3 agregat padat Wc 0.07 m3 Pengisian tangki / jam n 1.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = v x n x Fa Q6 47.43 m3

Wc

Koefisien Alat / m2 = 1 / Q6 ( E 23 ) 0.0211 Jam

Page 618: AHS 2008-Kota.xlsx

Analisa - E 618

No URAIAN KODE KOEF. SATUAN KET.

g Alat Bantu Diperlukan :

- Kereta dorong = 2 bh Lump sum - Skop = 3 bh - Garpu = 2 bh

3 TENAGA Produksi menentukan : WHEEL LOADER Q1 16.01 m3 / jam Produksi Agregat / hari = Tk x Q1 Qt 112.05 m3 / jam

Kebutuhan tenaga - Pekerja P 7.00 orang - Mandor M 1.00 orang

Koefisien tenaga /m2 : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.4373 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0625 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 200,310.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaa = . . . . . . . . M2

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 619: AHS 2008-Kota.xlsx

Analisa - E 619

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS PEREKAT (TACK COAT)SATUAN : LITER Analisa EI - 612

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.0301 4,500.00 135.54 2 Mandor ( L 03 ) Jam 0.0060 5,000.00 30.12

JUMLAH HARGA TENAGA 165.66

B BAHAN1 Aspal ( M 10 ) Kg 0.8880 10,650.00 9,456.82 2 Kerosene ( M 11 ) Liter 0.2530 1,000.00 253.00

JUMLAH HARGA BAHAN 9,709.82

C PERALATAN1 Asphalt Sprayer ( E 03 ) Jam 0.0030 51,313.28 154.56 2 Compresor ( E 05 ) Jam 0.0063 101,769.90 636.06 3 Dump Truck ( E 08 ) Jam 0.0030 125,838.28 379.03

JUMLAH HARGA PERALATAN 1,169.65

JUMLAH 11,045.13 JASA 10 % 1,104.51 JUMLAH ( BELUM TERMASUK PPN ) 12,149.64 DIBULATKAN 12,149.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 620: AHS 2008-Kota.xlsx

Analisa - E 620

URAIAN ANALISA HARGA SATUAN LAPIS PEREKAT

SATUAN : M3 Analisa EI - 612

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Menggunakan alat berat 2 Lokasi pekerjaan sepanjang jalan 3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00 Km 4 Jam kerja efektif 1 hari Tk 7.00 Jam 5 Faktor kehilangan material Fh 1.10 - 6 Komposisi campuran ( Spesifikasi )

- Aspal AC - 10 atau AC - 20 AS 77 % 100 Bagian - Minyak Flux / pencair K 23 % 30 Bagian

7 Berat jenis bahan - Aspal AC - 10 atau AC - 20 D1 1.05 Kg / Lt - Minyak Flux / pencair D2 0.80 Kg / Lt

8

II METODA KERJA 1

2

3

4 Angkutan aspal dan minyak Flux menggunakan Dump truck

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN

Untuk mendapatkan 1 liter lapis resap pengikat diperlukan ( 1 Liter x Fh ) PC 1.1000 Liter Campuran

a Aspal = AS x PC x D1 M10 0.8880 Kg b Kerosene = K x PC M11 0.2530 Liter

2 ALAT a Asphalt Sprayer ( E 03 )

Kapasitas alat V 800.00 Liter Faktor efisiensi alat Fa 0.83 - Waktu siklus ( termasuk proses pemanasan ) Ts 2.00 Jam

Kap Produksi / Jam = V x Fa Q1 332.00 Liter Ts

Koefisien Alat / Liter = 1 / Q1 ( E 03 ) 0.0030 Jam

b Air Compresor ( E 05 ) Kapasitas alat . . . . . Diambil V 400.00 m2 / jam Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.40 Liter / m2

Kapasitas produksi / jam = V x Ap Q2 160.00 Liter

Koefisien Alat / liter = 1 / Q2 ( E 05 ) 0.0063 Jam

Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan

Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal cair

Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor

Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan dilapis

Page 621: AHS 2008-Kota.xlsx

Analisa - E 621

No URAIAN KODE KOEF. SATUAN KET.

c Dump Truk ( DT ) ( E 08 ) Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat Asphalt Sprayer

Kapasitas Produksi / jam = V x Fa Q3 332.00 Liter Ts

Koefisien Alat / m2 = 1 / Q3 ( E 08 ) 0.0030 Jam

3 TENAGA Produksi menentukan : ASPALT FINISHER Q4 332.00 Liter Produksi Lapis Perekat / hari = Tk x Q4 Qt 2,324.00 Liter

Kebutuhan tenaga - Pekerja P 10.00 orang - Mandor M 2.00 orang

Koefisien tenaga /liter : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0301 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0060 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 12,149.00 / Liter

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . . Liter

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 622: AHS 2008-Kota.xlsx

Analisa - E 622

FORMULIR STANDAR UNTUK PEREKAMAN ANALISAMASING MASING HARGA SATUAN

JENIS PEKERJAAN : PENYIAPAN BADAN JALAN (PEMADATAN DAN PERATAAN)SATUAN : M2 Analisa EI - 33

HARGA JUMLAH NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA

(Rp.) (Rp.)

A TENAGA1 Pekerja ( L 01 ) Jam 0.0161 4,500.00 72.29 2 Mandor ( L 02 ) Jam 0.0040 5,000.00 20.08

JUMLAH HARGA TENAGA 92.37

B BAHAN

JUMLAH HARGA BAHAN

C PERALATAN1 Motor Grader ( E 13 ) Jam 0.0025 283,106.86 710.61 2 Vibratory Roller ( E 19 ) Jam 0.0040 179,602.55 721.30 3 Water Tank Truck ( E 23 ) Jam 0.0105 88,573.54 933.76 4 Alat Bantu Ls 1.0000 500.00 500.00

JUMLAH HARGA PERALATAN 2,865.66

JUMLAH 2,958.03 JASA 10 % 295.80 JUMLAH ( BELUM TERMASUK PPN ) 3,253.83 DIBULATKAN 3,253.00

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )

dan biaya biaya lainnya

Page 623: AHS 2008-Kota.xlsx

Analisa - E 623

URAIAN ANALISA HARGA SATUAN PENYIAPAN BADAN JALAN( PEMADATAN DAN PERATAAN )

SATUAN : M2 Analisa EI - 33

No URAIAN KODE KOEF. SATUAN KET.

I ASUMSI 1 Pekerjaan dilakukan pada hanya pada tanah galian 2 Pekerjaan dilakukan secara mekanis 3 Lokasi pekerjaan : sepanjang jalan 4 Kondisi jalan : jelek / belum padat 5 Jam kerja efektif per hari Tk 7.00 Jam

II URUTAN KERJA 1 Motor Grader meratakan permukaan hasil galian 2 Vibro Roller memadatkan permukaan jalan yang telah diratakan oleh Motor grader 3 Sekelompok pekerja akan membanru meratakan badan jalan dengan alat bantu

permukaan dengan menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA 1 BAHAN

Tidak diperlukan bahan / material

2 ALAT a Motor Grader ( E 13 )

Panjang hamparan Lh 50.00 m Lebar efektif kerja blade b 2.40 m Faktor Efisiensi alat Fa 0.83 - Kecepatan rata rata alat v 2.00 km / jam Jumlah lintasan n 6.00 Lintas 3 x pp Waktu siklus Ts 1 - Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 1.50 menit - Lain lain T2 1.00 menit

Ts 1 2.50 menit

Kapasitas produksi / jam = Lh x b x Fa x 60 Q1 398.40 m3 n x Ts 1

Koefisien Alat / m3 = 1 / Q1 ( E 02 ) 0.0025 Jam

b Vibratory Roller ( E 19 ) Kecepatan rata rata alat v 2.00 km / jam Lebar efektif pemadatan b 1.20 m Jumlah lintasan n 8.00 lintasan Faktor efisiensi alat Fa 0.83 -

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q2 249.00 m3

n

Koefisien Alat / m3 = 1 / Q2 ( E 19 ) 0.0040 Jam

c Water Tank Truck ( E 23 ) Volume tangki air v 4.00 m3 Kebutuhan air / m3 agregat padat Wc 0.07 m3 Pengisian tangki / jam n 2.00 kali Faktor efisiensi alat Fa 0.83 -

Page 624: AHS 2008-Kota.xlsx

Analisa - E 624

No URAIAN KODE KOEF. SATUAN KET.

Kapasitas produksi / jam = v x n x Fa Q3 94.86 m3 Wc

Koefisien Alat / m3 = 1 / Q3 ( E 23 ) 0.0105 Jam

g Alat Bantu Diperlukan :

- Skop = 3 bh Lump sum

3 TENAGA Produksi menentukan : VIBRATORY ROLLER Q2 249.00 m3 / jam Produksi Pekerjaan / hari = Tk x Q2 Qt 1,743.00 m3

Kebutuhan tenaga - Pekerja P 4.00 orang - Mandor M 1.00 orang

Koefisien tenaga /m2 : - Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0161 jam - Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0040 jam

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT ( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN

DIDAPAT HARGA SATUAN PEKERJAAN

Rp 3,253.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN Masa Pelaksanaan = . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN Volume Pekerjaan = . . . . . . . . M3

Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing Harga Satuan "

Page 625: AHS 2008-Kota.xlsx

Rekapitulasi - 625

REKAPITULASI ANALISA

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

PEKERJAAN PERSIAPAN

1 Pekerjaan Pengukuran Gedung 7,238.00 Analisa Gedung - 1

2 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran 67,606.00 Analisa Gedung - 1

3 Membersihkan lapangan dan perataan 6,160.00 Analisa Gedung - 14 1 buah Membuat Papan Nama Proyek 80x120 cm 446,638.00 Analisa Gedung - 1

5 Pembuatan jalan sementara, tebal 25 cm 74,975.00 Analisa Gedung - 1

6 Pembuatan kantor sementara, dengan lantai plesteran 968,448.00 Analisa Gedung - 2

7 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter 161,054.00 Analisa Gedung - 2

8 Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter 299,948.00 Analisa Gedung - 2

9 Pembuatan gudang semen dan alat-alat 892,973.00 Analisa Gedung - 2

10 Pembuatan rumah jaga/konstruksi kayu 1,066,010.00 Analisa Gedung - 3

11 Pembuatan bedeng buruh 1,019,108.00 Analisa Gedung - 3

12 Pembuatan bak adukan, uk. 40 x 50 x 20 cm 142,092.00 Analisa Gedung - 3

13 Pembuatan stegger dari bambu, ukuran 40 x 50 x 20 cm 24,395.00 Analisa Gedung - 4

14 Pasang pagar kawat jaring galvanis, tinggi 1,00 m 20,748.00 Analisa Gedung - 4

15 Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm 756,406.00 Analisa Gedung - 4

PEKERJAAN TANAH

16 Galian tanah biasa sedalam sampai 1 meter 17,600.00 Analisa Gedung - 4

17 Galian tanah biasa sedalam 1 - 2 meter 23,144.00 Analisa Gedung - 4

18 Galian tanah biasa sedalam 2 - 3 meter 32,340.00 Analisa Gedung - 4

19 Galian tanah keras sedalam sampai 1 meter 27,478.00 Analisa Gedung - 4

20 Galian tanah cadas sedalam sampai 1 meter 55,000.00 Analisa Gedung - 4

21 Galian tanah lumpur sedalam 1 meter 36,242.00 Analisa Gedung - 4

22 Membuat sumur 180,840.00 Analisa Gedung - 4

23 Mengangkut tanah sejauh 30 meter 13,508.00 Analisa Gedung - 4

24 Pembuangan tanah sejauh 150 meter 22,633.00 Analisa Gedung - 4

25 Membuang tanah dengan menghampar 10,340.00 Analisa Gedung - 4

26 Urug kembali bekas galian 8,439.00 Analisa Gedung - 4

27 Meratakan tanah ditumbuk halus 10,340.00 Analisa Gedung - 6

28 Urug pasir 84,920.00 Analisa Gedung - 6

29 Urug tanah mendatangkan 58,520.00 Analisa Gedung - 6

30 Urugan sirtu 98,120.00 Analisa Gedung - 6

31 Pemasangan lapisan ijuk 105,600.00 Analisa Gedung - 6

32 Gebalan rumput 27,940.00 Analisa Gedung - 6

PEKERJAAN PASANGAN

33 Pasangan pondasi batu kosong 176,517.00 Analisa Gedung - 7

34 Pasangan pondasi 1 Kp : 1 Sm : 1 Ps 274,413.00 Analisa Gedung - 7

35 Pasangan pondasi 1 Kp : 1 Sm : 2 Ps 247,461.00 Analisa Gedung - 7

36 Pasangan pondasi 1 Pc : 3 Kp : 5 Ps 329,708.00 Analisa Gedung - 7

37 Pasangan pondasi 1 Pc : 3 Kp : 10 Ps 294,638.00 Analisa Gedung - 7

38 Pasangan pondasi 1 Pc : 4 Ps 370,977.00 Analisa Gedung - 7

39 Pasangan pondasi 1 Pc : 3 Ps 400,826.00 Analisa Gedung - 7

40 Pasangan pondasi 1 Pc : 1 Ps 546,207.00 Analisa Gedung - 7

41 Pasangan pondasi 1 Pc : 2 Ps 450,604.00 Analisa Gedung - 8

42 Pasangan pondasi 1 Pc : 5 Ps 350,292.00 Analisa Gedung - 9

43 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1Ps 49,976.00 Analisa Gedung - 9

44 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 54,610.00 Analisa Gedung - 9

45 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps 58,711.00 Analisa Gedung - 9

46 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps 60,872.00 Analisa Gedung - 9

47 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps 64,554.00 Analisa Gedung - 10

1 M2

1 M1

1 M2

1 M2

1 M2

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M1

1 M3

1 M3

1 M3

1 M3

1 M2

1 M3

1 M3

1 M3

1 M3

1 M2

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M2

1 M2

1 M2

1 M2

1 M2

Page 626: AHS 2008-Kota.xlsx

Rekapitulasi - 626

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

48 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps 109,697.00 Analisa Gedung - 10

49 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps 121,721.00 Analisa Gedung - 10

50 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps 126,598.00 Analisa Gedung - 10

51 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps 134,545.00 Analisa Gedung - 10

52 Pasangan dinding bataco 60,544.00 Analisa Gedung - 11

53 Pasangan roster 25/25 cm 75,119.00 Analisa Gedung - 11

PEKERJAAN BETON

54 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr 385,995.00 Analisa Gedung - 11

55 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr 382,016.00 Analisa Gedung - 11

56 Beton cyclope 1pc:3ps:5kr 505,249.00 Analisa Gedung - 11

57 Membuat beton bertulang, 1 Pc : 1,5 Ps : 2,5 Kr 585,211.00 Analisa Gedung - 12

58 Membuat beton dengan mutu K 225 737,004.00 Analisa Gedung - 12

59 Membuat beton dengan mutu K 275 741,722.00 Analisa Gedung - 12

60 Membuat beton dengan mutu K 300 765,002.00 Analisa Gedung - 1261 1 kg Pembesian dengan besi polos 9,953.00 Analisa Gedung - 1262 1 kg Pembesian dengan besi ulir 10,068.00 Analisa Gedung - 14

63 Cetakan beton / begisting memakai papan 118,580.00 Analisa Gedung - 14

64 Cetakan beton / begisting memakai multiplek 126,533.00 Analisa Gedung - 14

65 Membongkar cetakan 158,400.00 Analisa Gedung - 14

66 Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai dolken ) 1,522,675.00 Analisa Gedung - 14

67 Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai scafolding ) 998,525.00 Analisa Gedung - 13

68 Pekerjaan beton bertulang 1:2:3 tanpa dolken, 100 kg besi 2,725,503.00 Analisa Gedung - 14

69 Pekerjaan beton bertulang 1:2:3 tanpa dolken, 125 kg besi 2,974,329.00 Analisa Gedung - 14

70 Pekerjaan beton bertulang 1:2:3 tanpa dolken, 150 kg besi 3,223,156.00 Analisa Gedung - 14

71 Pekerjaan beton bertulang 1:2:3 tanpa dolken, 175 kg besi 3,471,983.00 Analisa Gedung - 14

72 Pekerjaan beton bertulang 1:2:3 tanpa dolken, 200 kg besi 3,720,810.00 Analisa Gedung - 14

73 Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 100 kg besi 4,248,178.00 Analisa Gedung - 14

74 Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 125 kg besi 4,497,004.00 Analisa Gedung - 15

75 Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 150 kg besi 4,745,831.00 Analisa Gedung - 15

76 Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 175 kg besi 4,994,658.00 Analisa Gedung - 15

77 Pekerjaan beton bertulang 1:2:3 dengan memakai dolken, 200 kg besi 5,243,485.00 Analisa Gedung - 15

78 Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 100 kg besi 3,724,028.00 Analisa Gedung - 15

79 Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 125 kg besi 3,972,854.00 Analisa Gedung - 15

80 Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 150 kg besi 4,221,681.00 Analisa Gedung - 16

81 Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 175 kg besi 4,470,508.00 Analisa Gedung - 16

82 Pekerjaan beton bertulang 1:2:3 dengan memakai scaffolding, 200 kg besi 4,719,335.00 Analisa Gedung - 16

83 Pembuatan tiang pancang (40 x 40) cm, beton bertulang 720,113.00 Analisa Gedung - 16

84 Pembuatan tiang pancang (35 x 35) cm, beton bertulang 569,905.00 Analisa Gedung - 17 PEKERJAAN PELESTERAN

85 Plesteran batu kali 1pc:1/2kp:5ps tebal 10 mm 32,594.00 Analisa Gedung - 17

86 Plesteran batu kali 1pc:3ps 35,539.00 Analisa Gedung - 17

87 Plesteran batu kali 1pc:4ps 34,279.00 Analisa Gedung - 17

88 Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 15 mm 18,543.00 Analisa Gedung - 18

89 Plesteran 1 Pc : 3 Kp : 10 Ps, tebal 15 mm 19,310.00 Analisa Gedung - 18

90 Plesteran 1 Pc : 2 Ps, tebal 15 mm 24,696.00 Analisa Gedung - 18

91 Plesteran 1 Pc : 3 Ps, tebal 15 mm 23,149.00 Analisa Gedung - 18

92 Plesteran 1 Pc : 4 Ps, tebal 15 mm 22,157.00 Analisa Gedung - 18

93 Plesteran beton 1 Pc : 3 Ps, tebal 15 mm 28,905.00 Analisa Gedung - 19

94 Plesteran skoneng 1 Pc : 2 Ps ( untuk gedung ) 6,590.00 Analisa Gedung - 19

95 Sponengan (untuk saluran dan sejenisnya) 5,687.00 Analisa Gedung - 19

96 Plesteran siar adukan 1 Pc : 2 Ps 14,879.00 Analisa Gedung - 19

97 Plesteran Ciprat, 1 Pc : 2 Ps 20,328.00 Analisa Gedung - 19

98 Acian dinding bata 7,573.00 Analisa Gedung - 20

99 Plesteran K- 50, tebal 20 mm 36,207.00 Analisa Gedung - 20

100 Pasang dinding batu hias tempel 127,255.00 Analisa Gedung - 20

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M2

1 M2

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

Page 627: AHS 2008-Kota.xlsx

Rekapitulasi - 627

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

Page 628: AHS 2008-Kota.xlsx

Rekapitulasi - 628

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

PEKERJAAN PASANG TEGEL

101 Pasang tegel warna 30/30 85,736.00 Analisa Gedung - 20

102 Pasang tegel abu-abu 30/30 69,416.00 Analisa Gedung - 20

103 Pasang tegel teraso 30/30 74,419.00 Analisa Gedung - 21

104 Pasang tegel abu-abu 20/20 60,616.00 Analisa Gedung - 21

105 Pasang tegel warna 20/20 72,976.00 Analisa Gedung - 21

106 Pasang plint ubin PC abu-abu ukuran 10 x 20 cm 7,661.00 Analisa Gedung - 21

107 Pasang plint ubin PC abu-abu ukuran 10 x 30 cm 8,533.00 Analisa Gedung - 22

108 Pasang plint ubin PC warna ukuran 10 x 20 cm 8,904.00 Analisa Gedung - 22

109 Pasang plint ubin PC warna ukuran 10 x 30 cm 9,395.00 Analisa Gedung - 22

PEKERJAAN KERAMIK

110 Pasang ubin porselin 86,979.00 Analisa Gedung - 22

111 Pasang tegel keramik 20/20 dan 30/30 88,097.00 Analisa Gedung - 23

112 Pasang tegel keramik 10/20 berglasir 74,347.00 Analisa Gedung - 23

113 Pasang tegel keramik 20/20 berglasir 76,547.00 Analisa Gedung - 23

114 Pasang tegel keramik 30/30 berglasir 77,097.00 Analisa Gedung - 23

115 Pasang plint keramik ukuran 10 x 40 cm 16,098.00 Analisa Gedung - 23

116 Pasang plint keramik ukuran 10 x 30 cm 12,808.00 Analisa Gedung - 24

117 Pasang keramik stepnosing granito 5/30 44,790.00 Analisa Gedung - 24

118 Pasang list keramik dinding 5/20 35,264.00 Analisa Gedung - 24

119 Pasang keramik dinding 20/25 105,217.00 Analisa Gedung - 24

PEKERJAAN CONBLOCK

120 Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400 102,850.00 Analisa Gedung - 25

121 Pasang conblock tipe uni, segi-empat abu-abu 8 cm, K-300 97,350.00 Analisa Gedung - 25

122 Pasang conblock tipe segi-empat abu-abu 6 cm, K-200 86,350.00 Analisa Gedung - 25

123 Pasang conblock tipe segi-empat abu-abu 8 cm, K-200 91,850.00 Analisa Gedung - 25

124 Pasang conblock tipe segi-enam abu-abu 6 cm, K-200 86,350.00 Analisa Gedung - 25

125 Pasang conblock tipe segi-enam abu-abu 8 cm, K-200 91,850.00 Analisa Gedung - 26

126 Pasang conblock tipe segi-empat, uni, segi-enam rawna 8 cm, K-400 124,850.00 Analisa Gedung - 26

127 Pasang conblock tipe uni, segi-empat warna 8 cm, K-300 113,850.00 Analisa Gedung - 26

128 Pasang conblock tipe segi-empat warna 6 cm, K-200 91,850.00 Analisa Gedung - 26

129 Pasang conblock tipe segi-empat warna 8 cm, K-200 102,850.00 Analisa Gedung - 26

130 Pasang conblock tipe segi-enam warna 6 cm, K-200 91,850.00 Analisa Gedung - 27

131 Pasang conblock tipe segi-enam warna 8 cm, K-200 102,850.00 Analisa Gedung - 27

132 Pasang grassblock bulat tebal 10 cm 91,850.00 Analisa Gedung - 27

133 Pasang grassblock tebal 10 cm 91,850.00 Analisa Gedung - 27

134 Bronjong kawat galvanis 416,368.00 Analisa Gedung - 27135 1 bh Pasang buis beton dia. 80 cm 65,862.00 Analisa Gedung - 28

136 Langsiran batu kali 10,450.00 Analisa Gedung - 28

137 Langsiran kerikil 6,930.00 Analisa Gedung - 28

138 Langsiran pasir 3,850.00 Analisa Gedung - 28

PEKERJAAN KAYU

139 Pasang konstruksi kuda-kuda kayu jati 25,190,990.00 Analisa Gedung - 28

140 Membuat kuda-kuda kayu jati (lokal) 13,090,990.00 Analisa Gedung - 28

141 Membuat kuda-kuda kayu kamper 6,738,490.00 Analisa Gedung - 29

142 Membuat kuda-kuda kayu kruing 6,254,490.00 Analisa Gedung - 29

143 Membuat kuda-kuda kayu bengkirai 7,948,490.00 Analisa Gedung - 29

144 Membuat kuda-kuda kayu glugu 2,755,170.00 Analisa Gedung - 29

145 Pasang usuk 5/7, reng 2/3 kayu jati 247,445.00 Analisa Gedung - 29

146 Pasang usuk 5/7 kayu jati, reng 2/3 kayu jati (lokal) 214,445.00 Analisa Gedung - 30

147 Pasang usuk 5/7 kayu jati, reng 2/3 kayu kamper 197,120.00 Analisa Gedung - 30

148 Pasang usuk 5/7 kayu jati, reng 2/3 kayu kruing 195,800.00 Analisa Gedung - 30

149 Pasang usuk 5/7 kayu jati, reng 2/3 kayu bengkirai 200,420.00 Analisa Gedung - 30

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M3

1 M2

1 M2

1 M2

1 M2

1 M2

Page 629: AHS 2008-Kota.xlsx

Rekapitulasi - 629

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

Page 630: AHS 2008-Kota.xlsx

Rekapitulasi - 630

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

150 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu jati 162,745.00 Analisa Gedung - 31

151 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu jati lokal 129,745.00 Analisa Gedung - 31

152 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu kamper 112,420.00 Analisa Gedung - 31

153 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu kruing 111,100.00 Analisa Gedung - 31

154 Pasang usuk 5/7 kayu jati lokal, reng 2/3 kayu bengkirai 115,720.00 Analisa Gedung - 33

155 Pasang usuk 5/7 kayu kamper, reng 2/3 reng kayu jati 118,277.00 Analisa Gedung - 33

156 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu jati lokal 85,277.50 Analisa Gedung - 33

157 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu kamper 67,952.00 Analisa Gedung - 32

158 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu kruing 66,632.00 Analisa Gedung - 33

159 Pasang usuk 5/7 kayu kamper, reng 2/3 kayu bengkirai 71,252.00 Analisa Gedung - 33

160 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu jati 114,889.00 Analisa Gedung - 33

161 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu jati lokal 81,889.00 Analisa Gedung - 33

162 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu kamper 64,564.00 Analisa Gedung - 34

163 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu kruing 63,244.00 Analisa Gedung - 34

164 Pasang usuk 5/7 kayu kruing, reng 2/3 kayu bengkirai 67,864.00 Analisa Gedung - 34

165 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati 126,747.00 Analisa Gedung - 34

166 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati lokal 93,747.00 Analisa Gedung - 35

167 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu kamper 76,422.00 Analisa Gedung - 35

168 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu kruing 75,102.00 Analisa Gedung - 35

169 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu bengkirai 79,722.00 Analisa Gedung - 35

170 Pasang usuk 5/7 glugu, reng 2/3 kayu jati 93,291.00 Analisa Gedung - 36

171 Pasang usuk 5/7 glugu, reng 2/3 kayu jati lokal 60,291.00 Analisa Gedung - 36

172 Pasang usuk 5/7 glugu, reng 2/3 kayu kamper 42,966.00 Analisa Gedung - 36

173 Pasang usuk 5/7 glugu, reng 2/3 kayu kruing 41,646.00 Analisa Gedung - 36

174 Pasang usuk 5/7 glugu, reng 2/3 kayu bengkirai 46,266.00 Analisa Gedung - 37

175 Pasang usuk 5/7, reng 3/4 kayu jati 287,045.00 Analisa Gedung - 37

176 Pasang usuk 5/7 kayu jati, reng 3/4 kayu jati (lokal) 234,245.00 Analisa Gedung - 37

177 Pasang usuk 5/7 kayu jati, reng 3/4 kayu kamper 206,525.00 Analisa Gedung - 37

178 Pasang usuk 5/7 kayu jati, reng 3/4 kayu kruing 204,413.00 Analisa Gedung - 38

179 Pasang usuk 5/7 kayu jati, reng 3/4 kayu bengkirai 211,805.00 Analisa Gedung - 38

180 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu jati 202,345.00 Analisa Gedung - 38

181 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu jati lokal 149,545.00 Analisa Gedung - 38

182 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu kamper 121,825.00 Analisa Gedung - 39

183 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu kruing 119,713.00 Analisa Gedung - 39

184 Pasang usuk 5/7 kayu jati lokal, reng 3/4 kayu bengkirai 127,105.00 Analisa Gedung - 39

185 Pasang usuk 5/7 kayu kamper, reng 3/4 reng kayu jati 157,877.00 Analisa Gedung - 39

186 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu jati lokal 105,077.00 Analisa Gedung - 40

187 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu kamper 77,357.00 Analisa Gedung - 40

188 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu kruing 75,245.00 Analisa Gedung - 40

189 Pasang usuk 5/7 kayu kamper, reng 3/4 kayu bengkirai 82,637.00 Analisa Gedung - 40

190 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu jati 154,489.00 Analisa Gedung - 41

191 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu jati lokal 101,689.00 Analisa Gedung - 41

192 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu kamper 73,969.00 Analisa Gedung - 41

193 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu kruing 71,857.00 Analisa Gedung - 41

194 Pasang usuk 5/7 kayu kruing, reng 3/4 kayu bengkirai 79,249.00 Analisa Gedung - 42

195 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati 166,347.00 Analisa Gedung - 42

196 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati lokal 113,547.00 Analisa Gedung - 42

197 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu kamper 85,827.00 Analisa Gedung - 42

198 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu kruing 83,715.00 Analisa Gedung - 43

199 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai 91,107.00 Analisa Gedung - 43

200 Pasang usuk 5/7 glugu, reng 3/4 kayu jati 132,891.00 Analisa Gedung - 43

201 Pasang usuk 5/7 glugu, reng 3/4 kayu jati lokal 80,091.00 Analisa Gedung - 43

202 Pasang usuk 5/7 glugu, reng 3/4 kayu kamper 52,371.00 Analisa Gedung - 44

203 Pasang usuk 5/7 glugu, reng 3/4 kayu kruing 50,259.00 Analisa Gedung - 44

204 Pasang usuk 5/7 glugu, reng 3/4 kayu bengkirai 57,651.00 Analisa Gedung - 44

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

Page 631: AHS 2008-Kota.xlsx

Rekapitulasi - 631

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

Page 632: AHS 2008-Kota.xlsx

Rekapitulasi - 632

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

205 Membuat kusen pintu / jendela kayu jati (klas plitur) 25,605,800.00 Analisa Gedung - 44

206 Membuat kusen pintu / jendela kayu jati (lokal) 13,505,800.00 Analisa Gedung - 44

207 Membuat kusen pintu / jendela kayu kamper 7,571,300.00 Analisa Gedung - 45

208 Membuat kusen pintu / jendela kayu kruing 7,043,300.00 Analisa Gedung - 45

209 Membuat kusen pintu / jendela kayu bengkirai 8,891,300.00 Analisa Gedung - 45

210 Pasang pintu teakwood rangkap, rangka kayu jati 695,244.00 Analisa Gedung - 45

211 Pasang pintu teakwood rangkap, rangka kayu jati lokal 458,084.00 Analisa Gedung - 45

212 Pasang pintu teakwood rangkap, rangka kayu kamper 339,504.00 Analisa Gedung - 46

213 Pasang pintu teakwood rangkap, rangka kayu kruing 323,334.00 Analisa Gedung - 46

214 Pasang pintu teakwood rangkap, rangka kayu bengkirai 350,284.00 Analisa Gedung - 46

215 Pasang pintu dan jendela kaca kayu jati 995,940.00 Analisa Gedung - 46

216 Pasang pintu dan jendela kaca kayu jati lokal 572,440.00 Analisa Gedung - 46

217 Pasang pintu dan jendela kaca kayu kamper 360,690.00 Analisa Gedung - 47

218 Pasang pintu dan jendela kaca kayu kruing 331,815.00 Analisa Gedung - 47

219 Pasang pintu dan jendela kaca kayu bengkirai 379,940.00 Analisa Gedung - 47

220 Mengerjakan daun pintu / jendela panil kayu jati 1,154,175.00 Analisa Gedung - 47

221 Mengerjakan daun pintu / jendela panil kayu jati lokal 670,175.00 Analisa Gedung - 47

222 Mengerjakan daun pintu / jendela panil kayu kamper 428,175.00 Analisa Gedung - 47

223 Mengerjakan daun pintu / jendela panil kayu kruing 395,175.00 Analisa Gedung - 48

224 Mengerjakan daun pintu / jendela panil kayu bengkirai 450,175.00 Analisa Gedung - 48

225 Pasang pintu dan jendela jalusi kayu jati 1,774,850.00 Analisa Gedung - 48

226 Pasang pintu dan jendela jalusi kayu jati 1,000,450.00 Analisa Gedung - 48

227 Pasang pintu dan jendela jalusi kayu kamper 602,250.00 Analisa Gedung - 48

228 Pasang pintu dan jendela jalusi kayu kruing 549,450.00 Analisa Gedung - 48

229 Pasang pintu dan jendela jalusi kayu bengkirai 637,450.00 Analisa Gedung - 49

230 Pasang rangka langit-langit (1,00 x 1,00) m, kayu jati 285,587.00 Analisa Gedung - 49

231 Pasang rangka langit-langit (1,00 x 1,00) m, kayu jati lokal 153,587.00 Analisa Gedung - 49

232 Pasang rangka langit-langit (1,00 x 1,00) m, kayu kamper 84,287.00 Analisa Gedung - 49

233 Pasang rangka langit-langit (1,00 x 1,00) m, kayu kruing 79,007.00 Analisa Gedung - 49

234 Pasang rangka langit-langit (1,00 x 1,00) m, kayu bengkirai 97,487.00 Analisa Gedung - 50

235 Pasang rangka langit-langit (60 x 120) cm, kayu jati 309,754.00 Analisa Gedung - 50

236 Pasang rangka langit-langit (60 x 120) m, kayu jati lokal 166,754.00 Analisa Gedung - 50

237 Pasang rangka langit-langit (60 x 120) m, kayu kamper 91,679.00 Analisa Gedung - 50

238 Pasang rangka langit-langit (60 x 120) m, kayu kruing 85,959.00 Analisa Gedung - 50

239 Pasang rangka langit-langit (60 x 120) m, kayu bengkirai 105,979.00 Analisa Gedung - 51

240 Langit-langit asbes (1,00 x 1,00) m tanpa plepet 23,573.00 Analisa Gedung - 51

241 Langit-langit asbes (1,00 x 1,00) m memakai plepet 29,403.00 Analisa Gedung - 51

242 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati tanpa plepet 308,814.00 Analisa Gedung - 51

243 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati lokal tanpa plepet 176,814.00 Analisa Gedung - 51

244 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kamper tanpa plepet 107,514.00 Analisa Gedung - 52

245 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kruing tanpa plepet 102,234.00 Analisa Gedung - 52

246 Langit-langit asbes (1,00 x 1,00) m, rangka kayu bengkirai tanpa plepet 120,714.00 Analisa Gedung - 52

247 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati memakai plepet 314,770.00 Analisa Gedung - 52

248 Langit-langit asbes (1,00 x 1,00) m, rangka kayu jati lokal memakai plepet 182,770.00 Analisa Gedung - 53

249 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kamper memakai plepet 113,470.00 Analisa Gedung - 53

250 Langit-langit asbes (1,00 x 1,00) m, rangka kayu kruing memakai plepet 108,190.00 Analisa Gedung - 53

251 Langit-langit asbes (1,00 x 1,00) m, rangka kayu bengkirai memakai plepet 126,670.00 Analisa Gedung - 53

252 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu jati 339,460.00 Analisa Gedung - 54

253 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu jati lokal 196,460.00 Analisa Gedung - 54

254 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kamper 121,385.00 Analisa Gedung - 54

255 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kruing 115,665.00 Analisa Gedung - 54

256 Langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu bengkirai 135,685.00 Analisa Gedung - 55

257 Langit-langit gypsum board tebal 9 mm, rangka hollow 102,729.00 Analisa Gedung - 55

258 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu jati 341,123.00 Analisa Gedung - 55

259 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu jati lokal 198,123.00 Analisa Gedung - 55

1 M3

1 M3

1 M3

1 M3

1 M3

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

Page 633: AHS 2008-Kota.xlsx

Rekapitulasi - 633

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

Page 634: AHS 2008-Kota.xlsx

Rekapitulasi - 634

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

260 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu kamper 123,048.00 Analisa Gedung - 56

261 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu kruing 117,328.00 Analisa Gedung - 56

262 Langit-langit kalsiboard tebal 3.5 mm, rangka 60 x 120 kayu bengkirai 137,348.00 Analisa Gedung - 56

263 Langit-langit kalsiboard tebal 3.5 mm, rangka hollow 104,392.00 Analisa Gedung - 56

264 Langit-langit akustik 60 x 120 cm + rangka alumunium 324,912.00 Analisa Gedung - 57

265 Pasang list profil cornees gypsum lebar sampai 5 cm 15,593.00 Analisa Gedung - 57

266 Pasang list profil cornees gypsum lebar 5 - 10 cm 21,404.00 Analisa Gedung - 57

267 Pasang list profil cornees gypsum lebar lebih dari 10 cm 30,992.00 Analisa Gedung - 57

268 List langit-langit kayu profil 11,764.00 Analisa Gedung - 57

269 Pasang lisplank ukuran (2 x 20) cm, kayu jati 126,643.00 Analisa Gedung - 58

270 Pasang lisplank ukuran (2 x 25) cm, kayu jati 155,683.00 Analisa Gedung - 58

271 Pasang lisplank ukuran (3 x 20) cm, kayu jati 190,685.00 Analisa Gedung - 58

272 Pasang lisplank ukuran (3 x 30) cm, kayu jati 283,921.00 Analisa Gedung - 58

273 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu jati 372,135.00 Analisa Gedung - 58

274 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu jati 218,603.00 Analisa Gedung - 59

275 Pasang lisplank ukuran (2 x 20) cm, kayu jati lokal 68,563.00 Analisa Gedung - 59

276 Pasang lisplank ukuran (2 x 25) cm, kayu jati lokal 83,083.00 Analisa Gedung - 59

277 Pasang lisplank ukuran (3 x 20) cm, kayu jati lokal 103,565.00 Analisa Gedung - 59

278 Pasang lisplank ukuran (3 x 30) cm, kayu jati lokal 150,821.00 Analisa Gedung - 59

279 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu jati lokal 196,685.00 Analisa Gedung - 60

280 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu jati lokal 114,543.00 Analisa Gedung - 60

281 Pasang lisplank ukuran (2 x 20) cm, kayu kamper 39,523.00 Analisa Gedung - 60

282 Pasang lisplank ukuran (2 x 25) cm, kayu kamper 46,783.00 Analisa Gedung - 60

283 Pasang lisplank ukuran (3 x 20) cm, kayu kamper 59,730.00 Analisa Gedung - 60

284 Pasang lisplank ukuran (3 x 30) cm, kayu kamper 84,271.00 Analisa Gedung - 61

285 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu kamper 108,960.00 Analisa Gedung - 61

286 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kamper 62,513.00 Analisa Gedung - 61

287 Pasang lisplank ukuran (2 x 20) cm, kayu kruing 35,563.00 Analisa Gedung - 61

288 Pasang lisplank ukuran (2 x 25) cm, kayu kruing 41,833.00 Analisa Gedung - 61

289 Pasang lisplank ukuran (3 x 20) cm, kayu kruing 53,790.00 Analisa Gedung - 62

290 Pasang lisplank ukuran (3 x 30) cm, kayu kruing 75,196.00 Analisa Gedung - 62

291 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu kruing 96,998.00 Analisa Gedung - 62

292 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu kruing 55,418.00 Analisa Gedung - 62

293 Pasang lisplank ukuran (2 x 20) cm, kayu bengkirai 42,163.00 Analisa Gedung - 62

294 Pasang lisplank ukuran (2 x 25) cm, kayu bengkirai 50,083.00 Analisa Gedung - 63

295 Pasang lisplank ukuran (3 x 20) cm, kayu bengkirai 63,690.00 Analisa Gedung - 63

296 Pasang lisplank ukuran (3 x 30) cm, kayu bengkirai 90,321.00 Analisa Gedung - 63

297 Pasang lisplank ukuran 2 x (3 x 20) cm, kayu bengkirai 116,935.00 Analisa Gedung - 63

298 Pasang lisplank ukuran 2 x (2 x 20) cm, kayu bengkirai 67,243.00 Analisa Gedung - 63

299 Membuat listplank asbes plat ram kayu jati 698,170.00 Analisa Gedung - 64

300 Membuat listplank asbes plat ram kayu jati lokal 423,170.00 Analisa Gedung - 64

301 Membuat listplank asbes plat ram kayu kamper 278,795.00 Analisa Gedung - 64

302 Membuat listplank asbes plat ram kayu kruing 267,795.00 Analisa Gedung - 64

303 Membuat listplank asbes plat ram kayu bengkirai 306,295.00 Analisa Gedung - 64

304 Mengerjakan papan ruiter kayu jati 2/20 102,766.00 Analisa Gedung - 65

305 Mengerjakan papan ruiter kayu jati lokal 2/20 54,366.00 Analisa Gedung - 65

306 Mengerjakan papan ruiter kayu kamper 2/20 30,166.00 Analisa Gedung - 65

307 Mengerjakan papan ruiter kayu kruing 2/20 26,866.00 Analisa Gedung - 65

308 Mengerjakan papan ruiter kayu bengkirai 2/20 32,366.00 Analisa Gedung - 65

309 Pasang talang datar, seng BJLS 28, papan kayu jati 294,547.00 Analisa Gedung - 66

310 Pasang talang datar, seng BJLS 28, papan kayu jati lokal 178,387.00 Analisa Gedung - 66

311 Pasang talang datar, seng BJLS 28, papan kayu kamper 120,307.00 Analisa Gedung - 66

312 Pasang talang datar, seng BJLS 28, papan kayu kruing 112,387.00 Analisa Gedung - 66

313 Pasang talang datar, seng BJLS 28, papan kayu bengkirai 125,587.00 Analisa Gedung - 67

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

Page 635: AHS 2008-Kota.xlsx

Rekapitulasi - 635

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

314 Pasang talang miring, seng BJLS 28 papan kayu jati 519,596.00 Analisa Gedung - 67

315 Pasang talang miring, seng BJLS 28, papan kayu jati lokal 287,771.00 Analisa Gedung - 67

316 Pasang talang miring, seng BJLS 28, papan kayu kamper 172,821.00 Analisa Gedung - 67

317 Pasang talang miring, seng BJLS 28, papan kayu kruing 157,146.00 Analisa Gedung - 68

318 Pasang talang miring, seng BJLS 28, papan kayu bengkirai 183,271.00 Analisa Gedung - 68

319 Pasang talang torong 61,815.00 Analisa Gedung - 68

320 Pasang talang ½ lingkaran D - 10 cm, seng BJLS 28 166,072.00 Analisa Gedung - 68

321 Pasang talang ½ lingkaran D - 10 cm, seng BJLS 24 164,257.00 Analisa Gedung - 69

322 Pasang rangka dinding pemisah, kayu kamper 180,345.00 Analisa Gedung - 69

323 Pasang rangka dinding pemisah, kayu bengkirai 205,645.00 Analisa Gedung - 69

324 Pasang rangka dinding pemisah, kayu jati 634,507.00 Analisa Gedung - 69

325 Pasang rangka dinding pemisah, kayu jati lokal 335,307.00 Analisa Gedung - 69

326 Pasang rangka dinding pemisah, kayu kruing 165,990.00 Analisa Gedung - 70

327 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper 187,121.00 Analisa Gedung - 70

328 Pasang dinding pemisah plywoodwood rangkap, rangka kayu kamper 240,278.00 Analisa Gedung - 70

329 Pasang plywood tebal 4 mm, untuk dinding 23,968.00 Analisa Gedung - 70

330 Pasang dinding anyaman bambu, rangka kayu kruing 205,562.00 Analisa Gedung - 71

PEKERJAAN ATAP

331 Pasang genteng paris 43,780.00 Analisa Gedung - 71

332 Pasang genteng paris untuk rumah tingkat 47,960.00 Analisa Gedung - 71

333 Pasang genteng beton besar Natural ( isi 9 / m2 ) 43,230.00 Analisa Gedung - 71

334 Pasang genteng beton besar Natural ( isi 9 / m2 ) untuk rumah tingkat 47,410.00 Analisa Gedung - 71

335 Pasang genteng beton besar Warna ( isi 9 / m2 ) 58,080.00 Analisa Gedung - 72

336 Pasang genteng beton besar Warna ( isi 9 / m2 ) untuk rumah tingkat 62,260.00 Analisa Gedung - 72

337 Pasang genteng keramik berglasir KIA, Kanmuri Natural 96,470.00 Analisa Gedung - 72

338 Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat 100,650.00 Analisa Gedung - 72

339 Pasang bubungan genteng paris 41,823.00 Analisa Gedung - 72

340 Pasang bubungan genteng beton Natural 47,323.00 Analisa Gedung - 73

341 Pasang bubungan genteng beton Warna 50,623.00 Analisa Gedung - 73

342 Pasang bubungan genteng keramik berglasir KIA, Kanmuri Natural 90,223.00 Analisa Gedung - 73

343 Pasang atap asbes gelombang (2,5 x 0,92 m) x 5 mm 49,988.00 Analisa Gedung - 73

344 Pasang atap sbes gelombang (2,25 x 0,92 m) x 5 mm 54,388.00 Analisa Gedung - 73

345 Pasang atap asbes gelombang (2,00 x 0,92 m) x 5 mm 52,378.00 Analisa Gedung - 74

346 Pasang atap asbes gelombang (1,80 x 0,92 m) x 5 mm 58,566.00 Analisa Gedung - 74

347 Pasang atap asbes gelombang (300 x 1,05 m) x 4 mm 38,598.00 Analisa Gedung - 74

348 Pasang atap asbes gelombang (2,7 x 1,05 m) x 4 mm 40,812.00 Analisa Gedung - 74

349 Pasang atap asbes gelombang (2,40 x 1,05 m) x 4 mm 40,495.00 Analisa Gedung - 74

350 Pasang atap asbes gelombang (2,10 x 1,05 m) x 4 mm 43,229.00 Analisa Gedung - 75

351 Pasang atap asbes gelombang (1,50 x 1,05 m) x 4 mm 42,607.00 Analisa Gedung - 75

352 Pasang atap asbes gelombang (3,00 x 1,08 m) x 6 mm 56,893.00 Analisa Gedung - 75

353 Pasang atap asbes gelombang (2,70 x 1,08 m) x 6 mm 53,398.00 Analisa Gedung - 75

354 Pasang atap sbes gelombang (2,40 x 1,08 m) x 6 mm 56,646.00 Analisa Gedung - 75

355 Pasang atap asbes gelombang (2,10 x 1,08 m) x 6 mm 53,542.00 Analisa Gedung - 76

356 Pasang atap asbes gelombang (1,80 x 1,08 m) x 6 mm 53,413.00 Analisa Gedung - 76

357 Pasang bubung stel gelombang 0,92 m 131,066.00 Analisa Gedung - 76

358 Pasang nok stel gelombang 1,05 m 116,645.00 Analisa Gedung - 76

359 Pasang nok stel gelombang 1,08 m 114,242.00 Analisa Gedung - 76

360 Pasang nok paten 0,92 m 81,698.00 Analisa Gedung - 77

361 Pasang nok paten 1,05 m 81,698.00 Analisa Gedung - 77

362 Pasang nok paten 1,08 m 81,698.00 Analisa Gedung - 77

363 Pasang nok stel rata 0,92 m 47,888.00 Analisa Gedung - 77

364 Pasang nok stel rata 1,09 m 45,948.00 Analisa Gedung - 77

365 Pasang nok atap seng 25,261.00 Analisa Gedung - 78

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

Page 636: AHS 2008-Kota.xlsx

Rekapitulasi - 636

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

366 Pasang atap genteng metal zinc alume type prima roof 171,045.00 Analisa Gedung - 78

367 Pasang atap metal gelombanmg 143,759.00 Analisa Gedung - 78

368 Pasang nok genteng metal U type prima roof 68,909.00 Analisa Gedung - 78

369 Pasang atap alumunium 132,665.00 Analisa Gedung - 78

370 Pasang nok alumunium 90,618.00 Analisa Gedung - 79

371 Pasang alumunium foil / sisalation 38,054.00 Analisa Gedung - 79

372 Pasang atap polikarbonat 360,882.00 Analisa Gedung - 79

PEKERJAAN CAT-CATAN

373 Mengecat kerb 3 kali TIAP 1 M2 ( 3 kali ) 38,539.00 Analisa Gedung - 79TIAP 1 M2 ( 2 kali ) 25,692.00 Analisa Gedung - 79TIAP 1 M2 ( 1 kali ) 12,846.00 Analisa Gedung - 79

374 Mengikis / mengerok permukaan cat tembok lama 7,425.00 Analisa Gedung - 80

375 Mengerok karat cat lama permukaan baja dengan cara manual 7,150.00 Analisa Gedung - 80

376 Mendempul dan menggosok kayu 5,192.00 Analisa Gedung - 80

377 Pengecatan bidang kayu lama 21,092.00 Analisa Gedung - 80

378 27,940.00 Analisa Gedung - 80

379 31,462.00 Analisa Gedung - 81

380 Pelaburan bidang kayu dengan teak oil 21,617.00 Analisa Gedung - 81

381 Pelaburan bidang kayu dengan politur 34,375.00 Analisa Gedung - 81

382 Pelaburan bidang kayu dengan cat residu atau ter 5,571.00 Analisa Gedung - 81

383 Pelaburan bidang kayu dengan vernis 22,353.00 Analisa Gedung - 81

384 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 10,099.00 Analisa Gedung - 82

385 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 6,690.00 Analisa Gedung - 82

386 Pengecatan tembok tidak terlindung dari panas dan hujan #NAME? Analisa Gedung - 82

387 Melabur tembok dengan kalkarium 4,325.00 Analisa Gedung - 82

388 Melabur tembok dengan kapur sirih 8,906.00 Analisa Gedung - 82

389 Melabur tembok tembok lama dengan kapur sirih (untuk pemeliharaan) 4,317.00 Analisa Gedung - 83

390 Pengecatan bidang besi ( 3 x ) 19,709.00 Analisa Gedung - 83

391 Pemasangan wall paper 76,351.00 Analisa Gedung - 83

392 Pengecacatan permukaan baja dengan meni besi 14,422.00 Analisa Gedung - 83

393 Pengecacatan permukaan baja dengan meni besi memakai perancah 25,922.00 Analisa Gedung - 83

394 Pengetiran kayu ( 2 x ) 7,260.00 Analisa Gedung - 84

395 Pekerjaan cat duco 3 x 57,857.00 Analisa Gedung - 84

396 Mengecat genteng 21,979.00 Analisa Gedung - 84

PEKERJAAN BONGKARAN

397 Membongkar pasangan batu kali 202,840.00 Analisa Gedung - 84

398 Membongkar pasangan batu merah dan membersihkan 97,460.00 Analisa Gedung - 84

399 Membongkar beton bertulang dan membersihkan 330,550.00 Analisa Gedung - 85

400 Pekerjaan bongkar lantai tegel untuk dipergunakan lagi 8,360.00 Analisa Gedung - 85

401 Mengupas plesteran lama 5,500.00 Analisa Gedung - 85

402 Membongkar genteng / sirap untuk dipergunakan lagi 8,360.00 Analisa Gedung - 85

403 Membongkar atap seng 6,435.00 Analisa Gedung - 85

404 Membongkar usuk / reng dipakai lagi 11,825.00 Analisa Gedung - 85

405 Membongkar usuk / reng tidak dipakai lagi 8,360.00 Analisa Gedung - 85

406 513,700.00 Analisa Gedung - 86

407 48,400.00 Analisa Gedung - 86

408 Mengerjakan kembali bangunan kayu yang telah dibongkar 860,200.00 Analisa Gedung - 86

1 M1

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat

penutup

1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat

penutup

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M3

1 M3

1 M3

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan

lagi

1 M3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan

lagi

1 M3

Page 637: AHS 2008-Kota.xlsx

Rekapitulasi - 637

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

ANALISA SUPLEMEN

409 Pasang pipa beton oval dia. 25/37,5 dalam 0 - 1 m 97,872.00 Analisa Gedung - 86

410 Pasang pipa beton oval dia. 25/37,5 dalam 1 - 2 m 127,572.00 Analisa Gedung - 86

411 Pengelasan Single ( las listrik ) 222,062.00 Analisa Gedung - 86

PEKERJAAN SANITASI 412 1 bh Memasang kloset duduk/monoblock 2,521,194.00 Analisa Gedung - 87413 1 bh Memasang kloset jongkok porselen 526,893.00 Analisa Gedung - 87414 1 bh Memasang kloset jongkok teraso 231,488.00 Analisa Gedung - 87415 1 bh Memasang urinoir 2,961,578.00 Analisa Gedung - 87416 1 bh Memasang wastafel 1,180,210.00 Analisa Gedung - 87417 1 bh Memasang bak mandi fiberglass volume 0,30 m3 683,375.00 Analisa Gedung - 88418 1 bh Memasang badkip porselen 513,631.00 Analisa Gedung - 88419 1 bh Memasang bak fiberglass volume 1 m3 air 1,768,525.00 Analisa Gedung - 88

420 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm 67,960.00 Analisa Gedung - 88

421 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm 95,115.00 Analisa Gedung - 88

422 Memasang pipa beton, diameter 15 cm - 20 cm 79,508.00 Analisa Gedung - 89

423 Memasang pipa beton, diameter 30 cm - 100 cm 231,187.00 Analisa Gedung - 89424 1 bh Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm 274,231.00 Analisa Gedung - 89425 1 bh Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm 248,155.00 Analisa Gedung - 89426 1 bh Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm 377,597.00 Analisa Gedung - 90

427 Memasang pipa galvanis diameter 1/2" 33,554.00 Analisa Gedung - 90

428 Memasang pipa galvanis diameter 3/4" 50,604.00 Analisa Gedung - 90

429 Memasang pipa galvanis diameter 1" 71,916.00 Analisa Gedung - 90

430 Memasang pipa galvanis diameter 1 1/2" 99,070.00 Analisa Gedung - 90

431 Memasang pipa galvanis diameter 3" 158,745.00 Analisa Gedung - 91

432 Memasang pipa galvanis diameter 4" 170,727.00 Analisa Gedung - 91

433 Memasang pipa PVC tipe AW diameter 1/2" 9,998.00 Analisa Gedung - 91

434 Memasang pipa PVC tipe AW diameter 3/4" 11,853.00 Analisa Gedung - 91

435 Memasang pipa PVC tipe AW diameter 1" 13,344.00 Analisa Gedung - 91

436 Memasang pipa PVC tipe AW diameter 1 1/2" 23,788.00 Analisa Gedung - 92

437 Memasang pipa PVC tipe AW diameter 2" 32,501.00 Analisa Gedung - 92

438 Memasang pipa PVC tipe AW diameter 2 1/2" 39,559.00 Analisa Gedung - 92

439 Memasang pipa PVC tipe AW diameter 3" 46,943.00 Analisa Gedung - 92

440 Memasang pipa PVC tipe AW diameter 4" 69,534.00 Analisa Gedung - 92441 1 bh Memasang bak cuci piring stainless steel 786,764.00 Analisa Gedung - 93442 1 bh Memasang bak cuci piring teraso 653,928.00 Analisa Gedung - 93443 1 bh Memasang kran diameter 3/4" atau 1/2" 209,519.00 Analisa Gedung - 93444 1 bh Memasang floor drain 154,286.00 Analisa Gedung - 93

PEKERJAAN BESI DAN ALUMUNIUM 445 1 kg Pasang rangka atap baja 15,847.00 Analisa Gedung - 93

446 Pasang pintu besi baja 887,719.00 Analisa Gedung - 94

447 Pasang jendela besi 924,272.00 Analisa Gedung - 94

448 Pasang jendela besi tahan api 1,756,405.00 Analisa Gedung - 94

449 Pasang pintu gulung besi 388,454.00 Analisa Gedung - 94

450 Pasang pintu lipat 649,270.00 Analisa Gedung - 94

451 Pasang pintu Sunscreen alumunium 322,124.00 Analisa Gedung - 94

452 Pasang Rolling door 341,545.00 Analisa Gedung - 95

453 Pasang pintu alumunium 539,270.00 Analisa Gedung - 95

454 Vertikal blinds 308,090.00 Analisa Gedung - 95

455 Pasang teralis besi 218,893.00 Analisa Gedung - 95

456 Pasang kawat harmonika 51,117.00 Analisa Gedung - 95

457 Pasang kawat nyamuk 30,849.00 Analisa Gedung - 96

458 Pasang kawat kassa 32,967.00 Analisa Gedung - 96

459 Pasang kawat burung 39,017.00 Analisa Gedung - 96

460 Pasang jendela nako & tralis 44,140.00 Analisa Gedung - 96

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

Page 638: AHS 2008-Kota.xlsx

Rekapitulasi - 638

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

PEKERJAAN KUNCI DAN KACA 461 1 bh Pasang kunci tanam antik 312,158.00 Analisa Gedung - 96462 1 bh Pasang kunci tanam biasa 164,791.00 Analisa Gedung - 97463 1 bh Pasang kunci tanam kamar mandi 81,708.00 Analisa Gedung - 97464 1 bh Pasang kunci tanam silinder 109,109.00 Analisa Gedung - 97465 1 bh Pasang engsel pintu 21,389.00 Analisa Gedung - 97466 1 bh Pasang engsel jendela kupu-kupu 14,641.00 Analisa Gedung - 97467 1 bh Pasang engsel angin 16,082.00 Analisa Gedung - 97468 1 bh Pasang spring knip 17,539.00 Analisa Gedung - 98469 1 bh Pasang kait angin 12,589.00 Analisa Gedung - 98470 1 bh Pasang door closer 195,965.00 Analisa Gedung - 98471 1 bh Pasang kunci selot 67,386.00 Analisa Gedung - 98472 1 bh Pasang pegangan pintu / door holder 47,465.00 Analisa Gedung - 98473 1 bh Pasang door stop 22,693.00 Analisa Gedung - 98474 1 bh Pasang rel pintu dorong 257,158.00 Analisa Gedung - 99475 1 bh Pasang kunci lemari 28,682.00 Analisa Gedung - 99

476 Pasang kaca, tebal 3 mm 69,184.00 Analisa Gedung - 99

477 Pasang kaca, tebal 5 mm 82,494.00 Analisa Gedung - 99

478 Pasang kaca cermin, tebal 5 mm 154,489.00 Analisa Gedung - 99

479 Pasang kaca patri, tebal 5 mm 372,289.00 Analisa Gedung - 99

480 Mengerjakan Ukiran Gaya Yogyakarta dengan kedalaman 1 cm, tidak berlubang 1,461,130.00 Analisa Gedung - 100

481 Mengerjakan Cat Sungging 335,775.00 Analisa Gedung - 100

482 Memasang Prodo Mas 24 karat 5,789,069.00 Analisa Gedung - 100483 1 ttk Mengerjakan Sondir Tanah 320,100.00 Analisa Gedung - 101

484 Mengerjakan Test Laboratorium Sampel Beton 506,000.00 Analisa Gedung - 101

485 Pelumpuran ringan 4,202.00 Analisa Gedung - 101

486 Pelumpuran berat 11,044.74 Analisa Gedung - 101

487 Membuang lumpur SAL sejauh 15 km 73,378.00 Analisa Gedung - 102

488 Mengangkut lumpur SAL sejauh 30 m 17,325.00 Analisa Gedung - 102

489 Penyapuan Jalan Dan Trotoar 34.82 Analisa Gedung - 102

490 Pembersihan / Penyapuan halaman 48.60 Analisa Gedung - 102

491 Pemangkasan teh-tehan 15.07 Analisa Gedung - 102

492 Pangkas bentuk tanaman perdu 24.94 Analisa Gedung - 103

493 Pangkas rumput 9.80 Analisa Gedung - 103

494 Penyiangan tanaman semak dan penggemburan tanah 13.72 Analisa Gedung - 103

495 Pekerjaan Grouting / Injeksi retakan beton dengan epoxy resin 244,552.00 Analisa Gedung - 103

496 125,147.00 Analisa Gedung - 104

497 Cor beton kerb ( 15 x 30 ) cm, dengan 1pc:2ps:3kr 29,772.00 Analisa Gedung - 104

498 Cor beton Devider ( 30 x 30 ) cm, dengan 1pc:2ps:3kr 53,355.00 Analisa Gedung - 104

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M3

1 M2

1 M2

1 M3

1 M3

1 M2/Hari

1 M2/Hari

1 M2/Hari

1 M2/Hari

1 M2/Hari

1 M2/Hari

1 M1

1 M1 Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex

100)

1 M1

1 M1

Page 639: AHS 2008-Kota.xlsx

Rekapitulasi - 639

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

ANJALISA PEKERJAAN LISTRIK

1 Pasang Kabel NYY 3 x 6 sqmm 665.00 Analisa Listrik - 1

2 Pasang Kabel NYY 3 x 4 sqmm 665.00 Analisa Listrik - 1

3 Pasang Kabel NYM 2 x 2,5 sqmm 665.00 Analisa Listrik - 1

4 Pasang Kabel NYM 2 x 1,5 sqmm 665.00 Analisa Listrik - 1

5 Pasang Kabel NYA 1 x 2,5 sqmm 332.00 Analisa Listrik - 1

6 Pasang Kabel DX 2x10 sqmm + Accessories (antar tiang / gawang) 459,525.00 Analisa Listrik - 1

7 Pasang Kabel DX 2x16 sqmm + Accessories (antar tiang / gawang) 535,150.00 Analisa Listrik - 2

8 Pasang Kabel NYY 3x10 sqmm 50,614.00 Analisa Listrik - 29 1 Unit Pasang Box Panel dan Panel Kontrol 1 Unit 160,325.00 Analisa Listrik - 2

10 1 Unit Pasang Box KWH dan Meter (1 Unit) 160,325.00 Analisa Listrik - 211 1 Unit Pasang tiang lampu antik (b3) 403,227.00 Analisa Listrik - 212 1 Unit Pasang tiang lampu antik (b3) 303,463.00 Analisa Listrik - 213 1 Set Pemasangan armatur komplit 160,325.00 Analisa Listrik - 314 1 Unit Pemasangan komponen + Box 182,094.00 Analisa Listrik - 315 1 Set Bongkar komponen 147,235.00 Analisa Listrik - 316 1 Unit Bongkar Armatur 51,322.00 Analisa Listrik - 317 1 Set Bongkar Tiang Lampu Antik (b.1) 303,463.00 Analisa Listrik - 318 1 Set Bongkar Tiang Lampu Antik (b.1) 403,346.00 Analisa Listrik - 3

19 Pasang Kabel NYM 2x2,5 sqmm 24,687.00 Analisa Listrik - 4

20 Pasang Kabel NYA 2,5 sqmm 177,991.00 Analisa Listrik - 4

21 Pasang Pralon 3" Kabel NYY 3x6 sqmm 23,166.00 Analisa Listrik - 422 1 bh Pasang tutup panel ukuran 30x30 39,160.00 Analisa Listrik - 423 1 bh Pasang MCB Ampere + box tutup panel ukuran 30 x 30 53,735.00 Analisa Listrik - 424 1 bh Pasang Kapasitor 12,5 uF 36,135.00 Analisa Listrik - 425 1 Set 143,000.00 Analisa Listrik - 5

26 1 Set Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son 217,462.00 Analisa Listrik - 527 1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son 143,000.00 Analisa Listrik - 528 1 Set Pasang Tiang Octogonal Cabang 1, h= 7 meter+ lampu SRP 822/250 Watt Son 2,723,579.00 Analisa Listrik - 529 1 Set Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 Watt Son 2,782,182.00 Analisa Listrik - 530 1 Set Pasang Tiang Octogonal Cabang 2, h= 9 meter+ lampu SRP 822/250 Watt Son 2,805,768.00 Analisa Listrik - 631 1 Set Pasang Tiang Octogonal Cabang 3, h= 9 m+ lampu SRP 822/250 Watt Son 2,856,806.00 Analisa Listrik - 632 1 Set Pasang Tiang Octogonal Cabang 3, h= 11 m+ lampu SRP 822/250 Watt Son 2,911,917.00 Analisa Listrik - 633 1 Set 246,171.00 Analisa Listrik - 6

34 1 Set 214,546.00 Analisa Listrik - 6

35 1 Set 243,700.00 Analisa Listrik - 7

36 1 Set 230,898.00 Analisa Listrik - 7

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

1 M1

Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son + pengetesan dan penyalaan

Bongkar armatur pada stang ornamen existing + pasang lampu SRP 822/150 Watt Son + return

Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/250 Watt Son + retur

Bongkar armatur pada tang existing + pasang Lampu SRP 822/250 Watt Son + retur

Bongkar komponen lama existing + pasang komponen Lampu SRP 822/250 Watt Son + retur

Page 640: AHS 2008-Kota.xlsx

Rekapitulasi - 640

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

ANALISA KPUT

1 Menghampar dan mengisi bahan perkerasan 56,920.00 Analisa KPUT - 1

2 Menyawur pasir 36,000.00 Analisa KPUT - 1

3 Menggilas dengan motor walls 266,050.00 Analisa KPUT - 1

4 Perkerasan lapis pondasi bawah (sub base) tebal 20 cm padat 53,849.00 Analisa KPUT - 1

5 Pembuatan lapis pondasi bawah (sub base) tebal 15 cm padat 43,635.00 Analisa KPUT - 1

6 Pembuatan lapis pondasi atas (base) tebal 10 cm padat 33,341.00 Analisa KPUT - 2

7 Pembuatan lapis pondasi atas (base) tebal 8 cm padat 27,283.00 Analisa KPUT - 2

8 Pembuatan lapis pondasi atas (base) tebal 7 cm padat 24,254.00 Analisa KPUT - 2

9 Lapisan Penetrasi 4 cm padat 74,084.00

10 Aspal sand sheet 2 cm jereng (1 cm padat) 46,479.00

11 Aspal sand sheet 3 cm jereng (2 cm padat) 66,332.00 Analisa KPUT - 3

12 Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal 11,334.00 Analisa KPUT - 4

13 Aspal sand sheet 3 cm jereng (2 cm padat) tanpa aspal 16,544.00 Analisa KPUT - 4

14 Mengecat marka jalan dengan Rettar 46,751.00 Analisa KPUT - 4

15 Mengecat marka jalan dengan Thermoplastic 191,364.00 Analisa KPUT - 4

16 Pemotongan aspal dengan mesin potong (cutter), 2 sisi 9,779.00 Analisa KPUT - 5

17 Pemotongan aspal dengan mesin potong (cutter), 1 sisi 4,889.00 Analisa KPUT - 5

18 Pembongkaran aspal dengan Jack Hammer 95,809.00 Analisa KPUT - 5

19 Expantion joint 2,190,121.00 Analisa KPUT - 5

ANALISA _ E

1 LATASTON ( HRS ) 80,439.00 Analisa - E 1

2 LASTON ( AC ) 103,787.00 Analisa - E 5

3 ASPHALT TREATED BASE ( ATB ) 2,443,887.00 Analisa - E 94 1 liter LAPIS RESAP PENGIKAT (PRIME COAT) 9,174.00 Analisa - E 13

5 LAPIS PONDASI AGREGAT KLAS A 203,395.00 Analisa - E 16

6 LAPIS PONDASI AGREGAT KLAS B 200,310.00 Analisa - E 207 1 liter LAPIS PEREKAT (TACK COAT) 12,149.00 Analisa - E 24

8 PENYIAPAN BADAN JALAN (PEMADATAN DAN PERATAAN) 3,253.00 Analisa - E 27

1 M2

1 M3

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M2

1 M1

1 M1

1 M2

1 M2

1 M2

1 M2

1 M3

1 M3

1 M3

1 M2

Page 641: AHS 2008-Kota.xlsx

Rekapitulasi - 641

NO. SATUAN MACAM PEKERJAAN HARGA SATUAN HALAMAN

SEWA ALAT : 1 1 Jam ASPHALT MIXING PLANT 3,635,102.41 Analisa Alat - 12 1 Jam ASPHALT FINISHER 184,122.07 Analisa Alat - 23 1 Jam ASPHALT SPRAYER 51,313.28 Analisa Alat - 34 1 Jam BULLDOZER 100 -150 HP 254,754.61 Analisa Alat - 45 1 Jam COMPRESSOR 4000 - 6500 L/M 101,769.90 Analisa Alat - 56 1 Jam WHEEL LOADER 1,0 - 1,6 M3 260,998.03 Analisa Alat - 67 1 Jam TANDEM ROLLER 6 - 8 T 142,426.60 Analisa Alat - 78 1 Jam PNEUMATIC TYRE ROLLER 8 - 10 T 172,025.16 Analisa Alat - 89 1 Jam DUMP TRUCK 125,838.28 Analisa Alat - 9

10 1 Jam GENERATOR SET 222,834.68 Analisa Alat - 1011 1 Jam MOTOR GRADER > 100 HP 283,106.86 Analisa Alat - 1112 1 Jam VIBRATORY ROLLER 5 - 8 T 179,602.55 Analisa Alat - 1213 1 Jam WATER TANK TRUCK 3000 - 4000 L 88,573.54 Analisa Alat - 1314 1 Jam JACK HAMMER 13,818.81 Analisa Alat - 1415 1 Jam TAMPER 14,936.48 Analisa Alat - 1516 1 Jam STONE CRUSHER 268,841.68 Analisa Alat - 1617 1 Jam THREE WHEEL ROLLER 6 - 8 T 74,133.86 Analisa Alat - 1718 1 Jam CONCRETE VIBRATOR 22,595.92 Analisa Alat - 1819 1 Jam CONCRETE MIXER 0.3 - 0.6 M3 30,967.35 Analisa Alat - 1920 1 Jam CRANE 10 - 15 TON 175,941.26 Analisa Alat - 2021 1 Jam DUMP TRUCK 3 - 4 M3 99,272.09 Analisa Alat - 2122 1 Jam EXCAVATOR 80 - 140 HP 117,817.72 Analisa Alat - 2223 1 Jam FLAT BED TRUCK 3 - 4 M3 131,367.72 Analisa Alat - 2324 1 Jam WATER PUMP 70 - 100 mm 15,980.23 Analisa Alat - 2425 1 Jam FULVI MIXER 82,334.59 Analisa Alat - 2526 1 Jam TRACK LOADER 75 - 100 HP 135,291.26 Analisa Alat - 2627 1 Jam MESIN PENYARING 8 HP 50,000.00 28 1 Jam CHIP SPREADER 50,000.00 29 1 Jam MESIN PENGHAMPAR 1820 MM 30 HP 181,000.00 30 1 Jam THRILLER GANDENG 1 TON 184,000.00 31 1 Jam DUMP TRUCK 3,5 TON 44 HP 118,000.00 32 1 Jam POMPA AIR ( D 5 CM ) 30 M3/JAM 11,000.00 33 1 Jam TRAKTOR 15,000.00 34 1 Jam THRILLER 1 TON 15,000.00 35 1 Jam ALAT BOR 150,000.00 36 1 Jam ALAT UKUR 75,000.00 37 1 Jam BETON MOLEN 25,000.00 38 1 Jam MESIN CUTTER 60,000.00 39 1 Jam MOTOR WALLS 20,000.00 40 1 Jam PERALATAN LAS 75,000.00 41 1 Jam SPRAYER 48,000.00