06_10_2011.xls

9
PROGRESS LAPANGAN Minggu : Tanggal : Type 60/105 Blok / Nomor : B21 Mandor TAYO Jenis Item Pekerjaan Volume Satuan Bobot A Pekerjaaan Pondasi 1 Bowplank 60 Type 150,000 1.43% 100 2 Galian 4.68 m3 180,000 1.72% 100 3 Pondasi Batu kali 4.68 m3 500,000 4.78% 100 4 Cor sloof 42.5 m' 350,000 3.34% 100 5 Pasang Paralon 3" 12 m' 100,000 0.96% 100 6 Galian Septictank 1 ls 110,000 1.05% 100 7 Urugan elevasi lantai 9.375 m3 120,000 1.15% B Pekerjaan Dinding 0.00% 1 Dinding Bata 128.65 m2 1,800,000 17.20% 100 2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87% 100 3 Plesteran + Acian Dinding 187.71 m2 1,885,000 18.01% 100 4 Cor Kolom Praktis 30 m' 200,000 1.91% 100 5 Cor Ring Balk 42.5 m' 250,000 2.39% 100 7 Rooster 1 ls 100,000 0.96% 100 8 Dinding Bata Ampig 11.05 m2 300,000 2.87% 9 Cor Topi Panel 0.1 m3 150,000 1.43% 100 C Pekerjaan Kayu 0.00% 1 Gording 6/12 32 m' 0.00% 2 Usuk / reng 2/3 58 m2 0.00% 3 Pasang Genteng Morando 58 m2 300,000 2.87% 4 Nok / Karpusan 6 m' 100,000 0.96% 5 Pasang ListPlank 2/20 20 m' 100,000 0.96% 6 Ban-banan Atap Pembatas 20 m' 100,000 0.96% 7 Pasang Rangka Plafond 54 m2 205,000 1.96% 8 Pasang Plafond Enthernit 54 m2 205,000 1.96% D Pekerjaaan Pintu & Jendela 0.00% 1 Pasang Engsel Jendela 5 Bh 85,000 0.81% 2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43% 3 Pasang Slot 5 Bh 25,000 0.24% 4 Pasang Hak angin 5 Bh 25,000 0.24% E Keramik 0.00% 1 Keramik Lantai 40x40 60 m2 700,000 6.69% 2 Keramik Dinding 20x25 6 m2 150,000 1.43% 3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67% 4 Bak mandi Tempel 1 Bh 50,000 0.48% 5 Closed 1 Bh 50,000 0.48% No . Pembulatan Kontrak 171.500,- Prestasi lapangan

Transcript of 06_10_2011.xls

Page 1: 06_10_2011.xls

PROGRESS LAPANGAN Minggu :Tanggal :

Type 60/105

Blok / Nomor : B21

Mandor TAYO

Jenis Item Pekerjaan Volume Satuan Bobot

A Pekerjaaan Pondasi

1 Bowplank 60 Type 150,000 1.43% 100

2 Galian 4.68 m3 180,000 1.72% 100

3 Pondasi Batu kali 4.68 m3 500,000 4.78% 100

4 Cor sloof 42.5 m' 350,000 3.34% 100

5 Pasang Paralon 3" 12 m' 100,000 0.96% 100

6 Galian Septictank 1 ls 110,000 1.05% 100

7 Urugan elevasi lantai 9.375 m3 120,000 1.15%

B Pekerjaan Dinding 0.00%

1 Dinding Bata 128.65 m2 1,800,000 17.20% 100

2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87% 100

3 Plesteran + Acian Dinding 187.71 m2 1,885,000 18.01% 100

4 Cor Kolom Praktis 30 m' 200,000 1.91% 100

5 Cor Ring Balk 42.5 m' 250,000 2.39% 100

7 Rooster 1 ls 100,000 0.96% 100

8 Dinding Bata Ampig 11.05 m2 300,000 2.87%

9 Cor Topi Panel 0.1 m3 150,000 1.43% 100

C Pekerjaan Kayu 0.00%

1 Gording 6/12 32 m' 0.00%

2 Usuk / reng 2/3 58 m2 0.00%

3 Pasang Genteng Morando 58 m2 300,000 2.87%

4 Nok / Karpusan 6 m' 100,000 0.96%

5 Pasang ListPlank 2/20 20 m' 100,000 0.96%

6 Ban-banan Atap Pembatas 20 m' 100,000 0.96%

7 Pasang Rangka Plafond 54 m2 205,000 1.96%

8 Pasang Plafond Enthernit 54 m2 205,000 1.96%

D Pekerjaaan Pintu & Jendela 0.00%

1 Pasang Engsel Jendela 5 Bh 85,000 0.81%

2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43%

3 Pasang Slot 5 Bh 25,000 0.24%

4 Pasang Hak angin 5 Bh 25,000 0.24%

E Keramik 0.00%

1 Keramik Lantai 40x40 60 m2 700,000 6.69%

2 Keramik Dinding 20x25 6 m2 150,000 1.43%

3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67%

4 Bak mandi Tempel 1 Bh 50,000 0.48%

5 Closed 1 Bh 50,000 0.48%

No.

Pembulatan Kontrak

171.500,-

Prestasi lapangan

Page 2: 06_10_2011.xls

6 Pintu Kamar Mandi 1 Bh 70,000 0.67%

7 Saringan Air 1 Bh 10,000 0.10%

8 Intalasi Air Bersih 4 m' 100,000 0.96%

F Pekerjaan Lain - lain 0.00%

1 Carport 5 m' 150,000 1.43%

2 Pemberesan 1 Bh 70,000 0.67%

G Pekerjaan Tambahan 0.00%

1 Canopi Enterance + Topi -topi 1 ls 750,000 7.17% 75

2 Plesteran + Acian Dinding 1 ls 175,000 1.67% 50

4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 330,000 3.15% 100

NILAI KONTRAK 10,465,000 100.00%

Jumlah :

Retensi Pekerjaan ( 100 Hari ) = 5% -

Jumlah Tagihan Progrees Pekerjaan Minggu ini

Jumlah Tagihan Progrees Pekerjaan Minggu lalu

Total Tagihan Progrees Pekerjaan Minggu ini

Bobot minggu lalu =

Diajukan : Bobot minggu ini =

Bobot aktual =

Page 3: 06_10_2011.xls

150,000

180,000

500,000

350,000

100,000

110,000

-

1,800,000

300,000

1,885,000

200,000

250,000

100,000

-

150,000

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

Jumlah ( Rp )

Page 4: 06_10_2011.xls

-

-

-

-

-

562,500

87,500

330,000

7,055,000

352,750

6,702,250

5,784,075

918,175

55.27

64.04

8.77

174,417

Page 5: 06_10_2011.xls

PROGRESS LAPANGAN Minggu :Tanggal :

Type 60/105

Blok / Nomor : B32

Mandor TAYO

No. Jenis Item Pekerjaan Volume Satuan Bobot

A Pekerjaaan Pondasi

1 Bowplank 60 Type 150,000 1.43%

2 Galian 4.68 m3 180,000 1.72%

3 Pondasi Batu kali 4.68 m3 500,000 4.78%

4 Cor sloof 42.5 m' 350,000 3.34%

5 Pasang Paralon 3" 12 m' 100,000 0.96%

6 Galian Septictank 1 ls 110,000 1.05%

7 Urugan elevasi lantai 9.375 m3 120,000 1.15%

B Pekerjaan Dinding 0.00%

1 Dinding Bata 128.65 m2 1,800,000 17.20%

2 Kusen + Daun Pintu,Jendela 11.79 m2 300,000 2.87%

3 Plesteran + Acian Dinding 187.71 m2 1,885,000 18.01%

4 Cor Kolom Praktis 30 m' 200,000 1.91%

5 Cor Ring Balk 42.5 m' 250,000 2.39%

7 Rooster 1 ls 100,000 0.96%

8 Dinding Bata Ampig 11.05 m2 300,000 2.87%

9 Cor Topi Panel 0.1 m3 150,000 1.43%

C Pekerjaan Kayu 0.00%

1 Gording 6/12 32 m' 0.00%

2 Usuk / reng 2/3 58 m2 0.00%

3 Pasang Genteng Morando 58 m2 300,000 2.87%

4 Nok / Karpusan 6 m' 100,000 0.96%

5 Pasang ListPlank 2/20 20 m' 100,000 0.96%

6 Ban-banan Atap Pembatas 20 m' 100,000 0.96%

7 Pasang Rangka Plafond 54 m2 205,000 1.96%

8 Pasang Plafond Enthernit 54 m2 205,000 1.96%

D Pekerjaaan Pintu & Jendela 0.00%

1 Pasang Engsel Jendela 5 Bh 85,000 0.81%

2 Pasang Engsel Pintu & Kunci 5 Bh 150,000 1.43%

3 Pasang Slot 5 Bh 25,000 0.24%

4 Pasang Hak angin 5 Bh 25,000 0.24%

E Keramik 0.00%

1 Keramik Lantai 40x40 60 m2 700,000 6.69%

2 Keramik Dinding 20x25 6 m2 150,000 1.43%

3 Keramik Lantai Kamar Mandi 2.5 m2 70,000 0.67%

4 Bak mandi Tempel 1 Bh 50,000 0.48%

5 Closed 1 Bh 50,000 0.48%

6 Pintu Kamar Mandi 1 Bh 70,000 0.67%

7 Saringan Air 1 Bh 10,000 0.10%

8 Intalasi Air Bersih 4 m' 100,000 0.96%

F Pekerjaan Lain - lain 0.00%

Pembulatan Kontrak

171.500,-

Page 6: 06_10_2011.xls

1 Carport 5 m' 150,000 1.43%

2 Pemberesan 1 Bh 70,000 0.67%

G Pekerjaan Tambahan 0.00%

1 Canopi Enterance + Topi -topi 1 ls 750,000 7.17%

2 Plesteran + Acian Dinding 1 ls 175,000 1.67%

4 Pembesian ( Rp. 5500 X 60 M2 ) 1 ls 330,000 3.15%

NILAI KONTRAK 10,465,000 100.00%

Retensi Pekerjaan ( 100 Hari ) = 5% -

Jumlah Tagihan Progrees Pekerjaan Minggu ini

Jumlah Tagihan Progrees Pekerjaan Minggu lalu

Total Tagihan Progrees Pekerjaan Minggu ini

Bobot minggu lalu =

Diajukan : Bobot minggu ini =

Bobot aktual =

Page 7: 06_10_2011.xls

100 150,000

100 180,000

100 500,000

100 350,000

100 100,000

-

-

100 1,800,000

100 300,000

100 1,885,000

100 200,000

100 250,000

100 100,000

-

100 150,000

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

-

Prestasi lapangan

Jumlah

( Rp )

Page 8: 06_10_2011.xls

-

-

75 562,500

50 87,500

75 247,500

Jumlah : 6,862,500

343,125

###

###

###

Bobot minggu lalu = 49.77

Bobot minggu ini = 62.30

Bobot aktual = 12.53

Page 9: 06_10_2011.xls

REKAPAN PROGRESS DAN UPAH MANDORMinggu Ke : VITanggal : PT. Persada Bumi Kencana

No Jenis Kontrak Total Tagihan Pembayaran s/d hari ini Pembayaran Minggu ini

1 TAYO1 Rumah B21 10,465,000 8.77 55.27 64.04 7,055,000 352,750 5,784,075 6,702,250 918,175 2 Rumah B32 10,465,000 12.53 49.77 62.30 6,862,500 343,125 5,208,375 6,519,375 1,311,000

2,229,175

Rp 2,229,175

Cikunir, 06 Oktober 2011di Periksa Di Setujui Di Ajukan

Ujang C Mursidi AGUS

Nilai Kontrak

(Rp)

Bobot Aktual %

Bobot s.d minggu lalu

Bobot s.d minggu ini

Retensi 5%

Pembayaran s\d Minggu

lalu