Post on 29-Apr-2023
1.MORTAR
1.1 KSRB 0.5-1.1 : Providing cement mortar of mix 1:1 (1 cement : 1
sand) including cost of all materials, labour charges, HOM of
machinery complete as per specifications. Specification No. KBS
0.5-1.2
cum 8360.00
1.2 KSRB 0.5-1.2 cement mortar of mix 1:2 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 6120.00
1.3 KSRB 0.5-1.3 cement mortar of mix 1:3 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 5125.00
1.4 KSRB 0.5-1.4 cement mortar of mix 1:4 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 4195.00
1.5 KSRB 0.5-1.5 cement mortar of mix 1:5 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 3695.00
1.6 KSRB 0.5-1.6 cement mortar of mix 1:6 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 3266.00
1.7 KSRB 0.5-1.7 cement mortar of mix 1:8 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 2750.00
1.8 KSRB 0.5-1.8 cement mortar of mix 1:10 (1 cement : 1 sand)
including cost of all materials, labour charges, HOM of machinery
complete as per specifications. Specification No. KBS 0.5-1.2
cum 2550.00
1.9 KSRB 0.5-2.1 Providing lime mortar of mix 1:1 (1 lime putty : 1
sand) including cost of all materials, labour charges, HOM of
machinery complete as per specifications. Specification No. KBS
0.5-2.1
cum 2589.00
1.1 KSRB 0.5-2.2 Providing lime mortar of mix 1:2 (1 lime putty : 2
sand) including cost of all materials, labour charges, HOM of
machinery complete as per specifications. Specification No. KBS
0.5-2.1
cum 2429.00
1.11 KSRB 0.5-2.3 Providing lime mortar of mix 1:3 (1 lime putty : 3
sand) including cost of all materials, labour charges. including cost
of all materials, labour charges, HOM of machinery complete as
per specifications. Specification No. KBS 0.5-2.1
cum 2352.00
1.12 KSRB 0.5-3.1 Providing lime surkhi mortar of mix 1:1 (1 lime putty :
1 surkhi) including cost of all materials, labour charges, HOM of
machinery complete as per specifications. Specification No. KBS
cum 2073.00
1.13 KSRB 0.5-3.2 Providing lime surkhi mortar of mix 1:2 (1 lime putty :
2 surkhi) including cost of all materials, labour charges, HOM of
machinery complete as per specifications. Specification No. KBS
cum 1740.00
1.14 KSRB 0.5-3.3 Providing lime surkhi mortar of mix 1:3 (1 lime putty :
3 surkhi) including cost of all materials, labour charges, HOM of
machinery complete as per specifications. Specification No. KBS
cum 1576.00
1.15 KSRB 0.5-4.1 : Providing lime surkhi sand mortar of mix 1:1:1 (1
lime putty : 1 surkhi : 1 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS
cum 2052.00
1.16 KSRB 0.5-4.2 Providing lime surkhi sand mortar of mix 1:1:2 (1 lime
putty : 1 surkhi : 2 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS
cum 1639.00
1.17 KSRB 0.5-5.1 : Providing cement mortar with stone dust of mix 1:2
(1 cement : 2stone dust) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS
cum 5498.00
1.18 KSRB 0.5-6.1: Providing cement lime mortar of mix 1:1:3 (1 cement
: 1lime putty:3 sand) including cost of all materials, labour charges,
HOM of machinery complete as per specifications. Specification
No. KBS 0.5-2.3
cum 5033.00
1.19 KSRB 0.5-6.2 : Providing cement lime mortar of mix 1:1:4 (1
cement : 1lime putty:4 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 5087.00
1.2 KSRB 0.5-6.3 : Providing cement lime mortar of mix 1:1:5 (1
cement : 1lime putty:5 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 4460.00
1.21 KSRB 0.5-6.4 : Providing cement lime mortar of mix 1:1:6 (1
cement : 1lime putty:6 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 3942.00
1.22 KSRB 0.5-6.5 : Providing cement lime mortar of mix 1:1:7 (1
cement : 1lime putty: 7 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 3670.00
1.23 KSRB 0.5-6.6 : Providing cement lime mortar of mix 1:1:8 (1
cement : 1lime putty: 8 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 3409.00
1.24 KSRB 0.5-6.7 : Providing cement lime mortar of mix 1:2:9 (1
cement : 2lime putty: 9 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 3454.00
1.25 KSRB 0.5-6.8 : Providing cement lime mortar of mix 1:3:12 (1
cement : 3lime putty: 12 sand) including cost of all materials,
labour charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.3
cum 3214.00
1.26 KSRB 0.5-7.1 : Providing white cement mortar with marble dust of
mix 1:2 (1 white cement : 2 marble dust) including cost of all
materials, labour charges, HOM of machinery complete as per
specifications. Specification No. KBS
cum 14417.00
1.27 KSRB 0.5-7.2 : Providing white cement mortar with marble dust of
mix 1:3 (1 white cement : 3 marble dust) including cost of all
materials, labour charges, HOM of machinery complete as per
specifications. Specification No. KBS
cum 11245.00
1.28 KSRB 0.5-7.3 : Providing white cement mortar with marble dust of
mix 1:4 (1 white cement : 4 marble dust) including cost of all
materials, labour charges, HOM of machinery complete as per
specifications. Specification No. KBS
cum 8724.00
1.29 KSRB 0.5-7.4 : Providing white cement mortar with marble dust of
mix 1:5 (1 white cement : 5 marble dust) including cost of all
materials, labour charges, HOM of machinery complete as per
specifications. Specification No. KBS
cum 7366.00
1.3 KSRB 0.5-8.1 : Providing fly ash sand mortar of mix 1:1.5:3 (1
cement : 1.5 fly ash : 3 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.4
cum 3500.00
1.31 KSRB 0.5-8.2 : Providing fly ash sand mortar of mix 1:2:4 (1 cement
: 2 fly ash : 4 sand) including cost of all materials, labour charges,
HOM of machinery complete as per specifications. Specification
No. KBS 0.5-2.4
cum 2820.00
1.32 KSRB 0.5-8.3 : Providing fly ash sand mortar of mix 1:2.5:5 (1
cement : 2.5 fly ash : 5 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.4
cum 2470.00
1.33 KSRB 0.5-8.4 : Providing fly ash sand mortar of mix 1:3:6.5 (1
cement : 3 fly ash : 6.5 sand) including cost of all materials, labour
charges, HOM of machinery complete as per specifications.
Specification No. KBS 0.5-2.4
cum 2185.00
1.34 Mud Mortar cum 96.00
2.EARTHWORK FOR BUILDINGS
2.1 KSRB 2-1.1 : Earthwork in surface excavation in ordinary soil for
levelling and lowering the ground manually ( other than foundation
of buildings, culverts, road drains and trenches of pipe lines and
cables ) and removing the excavated stuff to a distance not
exceeding 50m and lift upto 1.5m, excavated surface levelled and
neatly dressed, disposed earth to be levelled after breaking of clods
and neatly dressed as per specifications. specification. No. KBS
2.1(a) / 2.3.1
cum 111.00
2.2 KSRB 2-1.2: Earthwork in surface excavation in Hard soil for
levelling and lowering the ground manually ( other than foundation
of buildings, culverts, road drains and trenches of pipe lines and
cables ) and removing the excavated stuff to a distance not
exceeding 50m and lift upto 1.5m, excavated surface levelled and
neatly dressed, disposed earth to be levelled after breaking of clods
and neatly dressed as per specifications. specification. No. KBS
2.1(a) / 2.3.1
cum 155.00
2.3 KSRB 2-2.1 : Earthwork excavation for foundation of buildings,
culverts, water supply, sanitary lines and electrical conduits either in
pits or in trenches 1.5m and above in width, in ordinary soil not
exceeding 1.5 m. in depth including dressing the bottom and sides
of pits and trenches, stacking the excavated soil clear from edges
of excavation with lead upto 50 m. after breaking of clods complete
as per specifications. specification. No. KBS 2.1(a) / 2.3.5
cum 133.00
2.4 KSRB 2-2.2 : Earthwork excavation for foundation of buildings,
water supply, sanitary lines and electrical conduits either in pits or
in trenches 1.5m and above in width, in hard soil not exceeding 1.5
m. in depth including dressing the bottom and sides of pits and
trenches, stacking the excavated soil clear from edges of
excavation with lead upto 50 m. after breaking of clods complete as
per specifications. specification. No. KBS 2.1(b) / 2.3.5
cum 200.00
2.5 KSRB 2-2.3 : Excavation 1.5m and above in width in soft rock by
blasting for foundation of buildings, water supply, sanitary lines and
electrical conduits either in pits or in trenches not exceeding 1.5 m.
in depth, stacking the excavated stuff from edges of excavation
with lead upto 50m including cost of explosives, labour and HOM of
equipment complete as per specifications. specification. No. KBS
2.1.C / 2.9.4 / 2.18 / 2.19
cum 390.00
2.6 KSRB 2-2.4 : Excavation 1.5m and above in width in soft rock
without blasting for foundation of buildings, water supply, sanitary
lines and electrical conduits either in pits or in trenches not
exceeding 1.5 m. in depth, stacking the excavated stuff from edges
of excavation with lead upto 50m including cost of explosives,
labour and HOM of equipment complete as per specifications.
specification. No. KBS 2.1.C / 2.9.4 / 2.18 / 2.19
cum 620.00
2.7 KSRB 2-2.5 : Excavation 1.5m and above in width in hard rock by
blasting for foundation of buildings, water supply, sanitary lines and
electrical conduits either in pits or in trenches not exceeding 1.5 m.
in depth, stacking the excavated stuff from edges of excavation
with lead upto 50m including cost of explosives, labour and HOM of
equipment complete as per specifications. specification. No. KBS
2.1.d / 2.3.4 / 2.18 / 2.19
cum 388.00
2.8 KSRB 2.2.6 : Excavation 1.5m and above in width in hard rock by
chiselling and / or wedging, where blasting is prohibited for
foundation of buildings, water supply, sanitary lines and electrical
conduits either in pits or in trenches 1.5 m. in depth stacking the
excavated stuff clear from the edge of excavation with lead upto
50m including cost of labour complete as per specifications.
specification. No. KBS
cum 890.00
2.9 KSRB 2.2.7: Benching hard rock 5 to 7.5 cm depth. for seating of
foundation, including cost of all labour complete as per
specifications. specification. No. KBS 2.1(a) / 2.3.1
Sqm 950.00
2.1 KSRB 2.3 : Filling available excavated earth ( excluding rock ) in
sides of foundations upto plinth in layers not exceeding 20 cms. in
depth, compacting each deposited layer by ramming after watering
with lead upto 50 m. and lift upto 1.5 m. including cost of all labour
complete as per specifications. specification. No. KBS 2.9
cum 90.00
2.11 KSRB 2-4 : Refilling available earth around pipe lines, cables in
layers not exceeding 20cms in depth, compacting each deposited
layer by ramming after watering with lead upto 50m. and lift upto
1.5 m. including cost of all labour complete as per specifications.
cum 54.00
2.12 KSRB 2.5 : Earthwork excavation ( in deposited soil ) and filling
sides of foundation upto plinth in layers not exceeding 20 cms. in
depth, compacting each deposited layer by ramming after watering
with all lead and lift including cost of all labour complete as per
specifications. specification. No. KBS 2.9.9 / 2.9.10.1 / 2.1.1
cum 180.00
2.13 KSRB 2.6 : Providing and filling sand in foundation upto plinth to
required depth for sub soil treatment including watering ramming
with all lead and lift complete as per specifications. specification.
No. KBS 2.10.2
cum 1207.00
2.14 KSRB 2.7 : Providing and removing shoring and strutting for
protecting the sides of foundation trenches, wherever required,
including cost of all materials and labour complete as per
specifications. specification. No. KBS 2.5 / 2.13
Sqm 367.00
2.15 KSRB 2.8 : Providing and Filling in foundation with granite / trap
broken metal 100mm. and down size, with approved sand including
hand packing, ramming, watering, including cost of all materials
and labour with all lead and lift. complete as per specifications.
specification. No. KBS
cum 1212.00
2.16 KSRB 2.9 : Spreading and forming the excavated earth to required
level, slope for an average thickness of 75mm. in all classes of
soils alround the building and low laying areas complete as per
specifications. specification. No. KBS :
Sqm 4.14
2.17 KSRB 2.10 : Providing sand cement bed with 5% cement with all
leads for all materials and lift of 1.5 m. machine mixed, laid in
layers of 15cms. thick and well compacted for foundation, including
curing cost of materials labour and HOM complete as per
specifications. specification. No. KBS
cum 1958.00
2.18 KSRB 2.11 : Providing sand cement bed with 10% cement cement
with all leads for all materials and lift of 1.5 m. machine mixed, laid
in layers of 15cms. thick and well compacted for foundation,
including curing cost of materials labour and HOM complete as per
specifications. specification. No. KBS
cum 2400.00
2.19 KSRB 2.12: Providing sand piles with all leads and lift of 1.5 m. for
stabilising foundation after duly making 5 cms. dia holes to a depth
of 1.2 to 1.5 m. at 0.5 m c to c and filling with sand and tamping
wherever required including cost of materials, labour complete as
per specifications. specification. No. KBS
Sqm 148.00
2.2 KSRB 2.13: Providing sand piles with all leads and lift of 1.5 m. for
stabilising foundation after duly making 5 cms. dia holes to a depth
of 1.2 to 1.5 m. at 0.5 m c to c and filling with sand and tamping
wherever required including cost of materials, labour complete as
per specifications. specification. No. KBS sand and 10% cement
Sqm 173.00
2.21 KSRB 2.14-1: Extra for additional lift of 1.5m. or part thereof for
excavation In loose / soft or hard soil including cost of materials,
labour complete as per specifications. specification. No. KBS
cum 8.90
2.22 KSRB 2.14-2: Extra for additional lift of 1.5m. or part thereof for
excavation In loose / soft or hard soil including cost of materials,
labour complete as per specifications. specification. No. KBS in soft
or hard rock
cum 15.55
2.23.1 Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally
for the work-in, Ordinary/Hard soil-Mechanical Means (Depth upto
3 m)
cum 30.30
2.23.2 Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally
for the work-in, Ordinary Rock (not requiring blasting)- Mechanical
Means
cum 39.95
2.23.3 Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally
for the work-in, Hard Rock ( requiring blasting )-Mechanical Means
cum 423.00
2.23.4 Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom, backfilling the excavation
earth to the extent required and utilising the remaining earth locally
for the work-in, Marshy soil-Mechanical Means
cum 218.00
3. ANTITERMITE TREATMENT
3.1 KSRB-3.1 Supplying chloropyriphos emulisifiable concentrate of 20%, in
sealed containers including delivery as specified sales tax, transport,
Insurance and other levies complete as per specifications. Specification
No. KBS
L 290.00
3.2 KSRB-3.2: Providing and injecting chemical emulsion for Pre-
constructional Anti-Termite Treatment, creating continuous chemical
barrier under and around the column pits, walls, trenches, basement
excavation, top surface of the plinth filling, junction of wall and
floor,along the external perimeter of building,expansion joints,over the
top surface of consolidated earth on which apron is to be laid,
surrounding of pipes and conduits with chloropyriphos emulsifiable
concentrates of 20% concentration,including cost of chemical, diluting
in water to one percent concentration,labour,HOM of equipments,
complete as per specifications.(Plinth area of the building at ground
floor only shall be measured)Specification No.KBS : 3.2.6 / 3.2.7
Sqm 112.00
3.3 KSRB-3.3 : Providing, injecting chemical emulsion for Pre-
constructional Anti-Termite Treatment along external walls where the
apron is not provided using chemical emulsion at 7.5 Litre/sqm of the
vertical surface of the substructure to a depth of 300mm. including
excavation of channel along the wall and redoing with chlorophyriphos
emulsion concentration 20% diluting in water to 1% concentration,
including cost of chemicals, diluting in water to one percent
concentration, labour, HOM of equipments,complete as per
specifications.Specification No.KBS : 3.3.3
M 62.00
3.4 KSRB-3.4: Providing, injecting chemical emulsion for Pre-onstructional
Anti-Termite Treatment along external walls below concrete or masonry
apron using chemical emulsion at 2.25 litre/m. including drilling and
plugging percentof holes, with chlorophyriphos emulsion concentration
20% diluting water in to 1% concentration,including cost of
chemicals,diluting in water to one percent concentration,labour,HOM of
equipments, complete as per specifications.Specification No.KBS :
3.3.4
M 46.00
3.5 KSRB 3.5: Providing, injecting chemical emulsion for Pre-constructional
Anti-Termite Treatment of soil under existing floors using chemical
emulsion at one litre / hole 30mm apart including drilling 12mm. dia
holes and plugging with cement mortar 1:2 proportion to mach with the
existing floors with chlorophyriphos emulsion concentrate 20%,including
cost of chemical diluting in water to one percent
concentration,labour,HOM of equipments, complete as per
specifications.Specification No.KBS
Sqm 231.00
3.6 KSRB.3-6: Providing,inecting chemical emulsion for pre-constructional
Anti-Termite Treatment of existing masonry using chemical emulsion at
one liter / hole at 300mm intervals including drilling of holes at 45
degree and plugging them with cement mortar 1:2 to the full depth of
the hole with Chloropyriphos emulsifiable concentration 20% including
cost of chemical diluting in water to one percent
concentration,labour,HOM of equipments,complete as per
specifications.Specification No.KBS : 3.3.5
M 72.00
3.7 KSRB 3.7: Providing, injecting chemical emulsion for Pre-
constructionaAnti-Termite Treatment at points of contacts of wood work
by chemical emulsion Chloropyriphos ( in oil or kerosene based solution
) at 0.5 liters per hole by drilling 6mm. dia holes at downword angle of
45 degree at 150mm.c to c and sealing the same including cost of
chemicals,diluting in water to one percent concentration,labour,HOM of
equipments,complete as per specifications.Specification No : 3.3.7
M 192.00
3.8 Providing general disinfection services, spraying of insecticide and
pesticide inside and outside the building (flies, bedbugs,lizards,
cockroaches, spiders caterpillars etc including cost of materials labour
lead lift, hire charges of equipments etc.,complete.
Sqm 20.00
4.CEMENT CONCRETE
4.1 KSRB 4-1.1: Providing and laying in position plain cement concrete of mix
M15 with OPC cement @ 240kgs, with 40mm and down size graded granite
metal coarse aggregates @0.878cum and fine aggregtes @ 0.459cum
machine mixed, concrete laid in layers not exceeding 15 cms. thick, well
compacted, in foundation and plinth, including cost of all materials, labour,
HOM of machinery, curing complete as per specifications. Specification No.
KBS 4.1, 4.2
cum
4.2 KSRB 4-1.2 : Providing and laying in position plain cement concrete of mix
M10 with OPC cement @ 220kgs, with 40mm and down size graded granite
metal coarse aggregates @0.892cum and fine aggregtes @ 0.465cum
machine mixed, machine mixed, concrete laid in layers not exceeding 15 cms.
thick, well compacted, in foundation and plinth, cost of all materials, labour,
HOM of machinery, curing complete as per specifications. Specification No.
KBS 4.1, 4.2
cum
4.3 KSRB 4-1.3 : Providing and laying in position plain cement concrete of mix
M7.5 with OPC cement @ 180kgs, with 40mm and down size graded granite
metal coarse aggregates @0.85cum and fine aggregtes @ 0.57cum machine
mixed, machine mixed, concrete laid in layers not exceeding 15 cms. thick,
well compacted, in foundation and plinth, including cost of all materials, labour,
HOM of machinery, curing complete as per specifications. Specification No.
KBS 4.1, 4.2
cum
4.4 KSRB 4-1.4 : Providing and laying in position plain cement concrete of mix M5
with OPC cement @ 160kgs, with 40mm and down size graded granite metal
coarse aggregates @0.86cum and fine aggregtes @ 0.58cum machine mixed,
machine mixed, concrete laid in layers not exceeding 15 cms. thick, well
compacted, in foundation and plinth, including cost of all materials, labour,
HOM of machinery, curing complete as per specifications. Specification No.
KBS 4.1, 4.2
cum
4.5 KSRB 4-1.5 : Providing and laying in position plain cement concrete of mix
M20 with OPC cement @ 300kgs, with 20mm and down size graded granite
metal coarse aggregates @0.64cum and fine aggregtes @ 0.43cum, with
superplastisiser @3lts confirming to IS9103-1999 Reaffirmed-2008, machine
mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in
foundation,plinth and cills, including cost of all materials, labour, HOM of
machinery, curing complete as per specifications. Specification No. KBS 4.1,
4.2
cum
4.6 KSRB 4-1.6 ; Providing and laying in position plain cement concrete of mix
M15 with cement @ 240kgs, with 20mm and down size graded granite metal
coarse aggregates @0.878cum and fine aggregtes @ 0.459cum, machine
mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in
foundation,plinth and cills, including cost of all materials, labour, HOM of
machinery, curing complete as per specifications. Specification No. KBS 4.1,
4.2
cum
4.7 KSRB 4-1.7 : Providing and laying in position plain cement concrete of mix
M10 with OPC cement @ 220kgs, with 20mm and down size graded granite
metal coarse aggregates @0.84cum and fine aggregtes @ 0.56cum, machine
mixed, concrete laid in layers not exceeding 15 cms. thick, well compacted, in
foundation,plinth and cills, ncluding cost of all materials, labour, HOM of
machinery, curing complete as per specifications. Specification No. KBS 4.1,
4.2
cum
4.8 KSRB 4-1.8 : Extra for laying cement concrete under water including cost of
pumping or dewatering and clearing slush as per specifications Details of cost
for depth of water 0.3 metres bailing out Specification No. KBS 4.2, 4.8
cum