RENCANA ANGGARAN BIAYA INSTALASI PENERANGAN PABRIK

NO MATERIAL SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUANLAMPU

I.1 LAMPU 1 LHE PHILIPS ESSENSIAL 54 W, BUAH 270

I.2 LAMPU 2 BUAH 45

KABEL2.1 NYA MERAH SUPREME 1,5 MM2 ROL

PIPA PVC3.1 PIPA DIA 0,5 MASPION 0,5 DM BATANG 25

PENGAMAN4.1 MCB 4A, 1,25 KA BUAH 124.2 MCB

SAKLAR5.1 SAKLAR GANDA 250 V/ 10 A BUAH 1005.2 SAKLAR TUNGGAL

ACCESORIES6.1 T DOS

TL 80 W; 0,5; PHILIPS INCLUDE ARMATURE

kyranna:INCLUDE TRASNPORTASI, PEMASANGAN, KOMISIONING, ASURANSI, PROFIT PERUSAHAAN

F6