no URAIAN vol satharga

satuan

jumlah hrg

satuan

A Bahan

1 Plate 8mm (4415mm x 1415mm) 1.400,00 kg 11.000 15.400.000

2 Plate Bahan hollo (8mmx 70mm x 140mm) x 4415mm 388,80 kg 11.000 4.276.800

Plate Bahan hollo (8mmx 70mm x 140mm) x 1270mm 147,39 kg 11.000 1.621.280

3 Pek.UNP (65x 42x 5 mm) 260,77 kg 11.000 2.868.507

24.166.587

B JASA POTONG DAN BENDING

Plate Bahan hollo (8mmx 70mm x 140mm) x 4415mm 388,80 kg 3.000 1.166.400

Plate Bahan hollo (8mmx 70mm x 140mm) x 1270mm 147,39 kg 3.000 442.167

1.608.567

C JASA LAS

1 Plate 8mm (4415mm x 1415mm) 1.400,00 kg 3.500 4.900.000

2 Plate Bahan hollo (8mmx 70mm x 140mm) x 4415mm 388,80 kg 3.500 1.360.800

Plate Bahan hollo (8mmx 70mm x 140mm) x 1270mm 147,39 kg 3.500 515.862

3 Pek.UNP (65x 42x 5 mm) 260,77 kg 3.500 912.707

7.689.368

D MATERIAL PEMBANTU

Peralatan & bahan tambahan (Oksigen,solar, kawat las

listrik dll)2.196,96 LOT 1.800 3.954.532

3.954.532

37.419.055

E BAHAN

1 Plate 8mm 1.400,00 kg 11.000 15.400.000

2 Plate 6mm 1.050,00 kg 11.000 11.550.000

3 Besi AS 4,00 kg 25000 100.000

4 Besi Ass Kotak 14,00 m 25000 350.000

27.400.000

F JASA POTONG DAN BENDING

1 Pek.Plate 8mm 1.400,00 kg 3.000 4.200.000

2 Pek.Plate 6mm 1.050,00 kg 3.000 3.150.000

7.350.000

G JASA LAS

1 Plate 8mm 1.400,00 kg 3.500 4.900.000

2 Plate 6mm 1.050,00 kg 3.500 3.675.000

3 Besi AS 4,00 kg 3.500 14.000

4 Besi Ass Kotak 14,00 m 3.500 49.000

8.638.000

H MATERIAL PEMBANTU

Peralatan & bahan tambahan (Oksigen,solar, kawat las

listrik dll)2.468,00 LOT 1.800 4.442.400

4.442.400

I Mobilisasi 1,00 ls 7.500.000

55.330.400

92.749.455

1,415 4,415 0,008 0,0499778 7850 392,32573 431,56 1 431,56

0,42 4,415 0,008 0,0148344 7850 116,45004 128,10 2 256,19

0,42 1,27 0,008 0,0042672 7850 33,49752 36,85 2 73,69

11,37