NO UPAH / BAHAN SATUAN HARGA STN KETERANGAN
UPAH
1 Kepala Tukang Hari 55,000.00
2 Tukang Hari 45,000.00
B A H A N
1 Main Truss C.75.75 M1 14,000.00
2 Reng (U Type) 0,6 TCT M1 7,166.67
3 Screw 12-14x20 Pcs 300.00
4 Screw 10-16x16 Pcs 300.00
5 Dynabolt Pcs 2,000.00
Atap Genteng Metal ( Sakura Roof, Multiroof, Dan Lainnya )
0.2500 Kepala Tukang 55,000.00 13,750.00
1.1500 Tukang 45,000.00 51,750.00
4.5000 Main Truss C.75.75 14,000.00 63,000.00
3.8000 Reng (U Type) 0,6 TCT 7,166.67 27,233.33
13.5000 Screw 12-14x20 300.00 4,050.00
11.4000 Screw 10-16x16 300.00 3,420.00
0.3000 Dynabolt 12X77 2,000.00 600.00
Jumlah 163,803.33