“1,000 GW capacity by 2050”

Post on 15-Mar-2016

26 views 0 download

description

DESERTEC 10,000 GW FROM DESERTS BY 2050 Large-scale deployment of BSE/Luz II solar towers Energy Forum, Hannover, April 24, 2008. - PowerPoint PPT Presentation

Transcript of “1,000 GW capacity by 2050”

1

DESERTEC10,000 GW FROM DESERTS BY 2050

Large-scale deployment of BSE/Luz II solar towers

Energy Forum, Hannover, April 24, 2008

USA 1999 Harrison Street, Suite 500, Oakland, California 94612, Tel. (510) 550 8161, Fax. (510) 550 8165 www.BrightSourceEnergy.com

ISRAEL 11 Kiryat Mada St., Har Hotzvim, P.O.Box 45220, Jerusalem 91450, Tel. +972 77 202 5000, Fax. +972 2 571 1059 www.luz2.com

2

“1,000 GW capacity by 2050”• The technology and component availability

– Approach to the desired technology and at market-driven quantities

• Solar energy in the desert - availability and transmission– Potentially recognized and assumed for this

presentation• Solar electricity price

– How to reduce solar electricity price to half of current state of the art trough technology, is not presented here.

3

What’s the approach?

• The BSE / Luz II way

4

Original Luz Solar Trough Design*

*Still used by many competitors

Modular Solar Field

Centralized Power Block

The 354 MW of original Luz plants have generated over 11,000 GWh of electricity worth more than $1.7 billion in revenue

5

Technology & Design Philosophy• Compete with conventional power production:

– solar steam parameters equal to conventional energy steam parameters

• Follow global market trends to minimize costs: – use available materials and

components• Implement technology as it becomes available

– Build DPT 550 plants (subcritical) as DPT SC1 technology (supercritical) is developed

5

6

Luz II Distributed Power Tower (DPT550)

Steam Condenser

Solar Tower

Receiver

Solar Field

Steam 550°C

165 Bar

Steam Turbine

Electric Generator

AirCooling

Heliostats

Solar Boiler

Tower

CalibrationTarget

5500C Steam to power block

7m2 Heliostat

77

Efficiency Evolution

Source: Alstom 7

8

Heliostats

9

Receiver

10

1,000 GW by 2050• Major equipment items would otherwise be

produced for conventional power requirements– power block equipment including turbines– boilers

• Towers and heliostats are fabricated from plentiful, conventional materials such as steel and glass

• As an example, ~5 billion m2 of mirrors will be required for 1,000 GW

– roughly equal to one year’s glass production worldwide (2005 figures)

– But spread over 30 years, it is only 3% of the world glass market

11

Rotem Pilot Plant, Israel, July 2007

12

October 2007

13

November 2007

14

November 2007

15

November 2007

16

November 2007

17

December 2007

18

January 2008

19

January 2008

20

February 2008

21

March 2008

22

March 2008

23

MarchMarch 20082008

24

March 2008

2525

So Why Have We Chosen Tower?• Greater thermal efficiency• Greater electrical efficiency• Lower parasitic losses• Lower capital costs• More site flexibility• Greater natural

resource efficiency

26

Power Tower

Power Block

Heliostat Field

Thank you

December 2007