Sindh Water Sector Improvement Project
Resettlement Action Plan (RAP)
Contract WSIP/B1/GF/01
May 2016
Sindh Irrigation and Drainage Authority
SFG2233 V3
253277 EVT WER 0109 B
C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
06 December 2010
Sindh Water Sector Improvement Project
Resettlement Action Plan (RAP)
Contract WSIP/B1/GF/01
May 2016
Sindh Irrigation and Drainage Authority
SIDA Left Bank Barrage Colony Hyderabad Sindh Pakistan
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Chapter Title Page
Executive Summary i
1. Introduction 1
1.1 The Indus Basin Irrigation System ______________________________________________________ 1
1.2 Sindh Water Sector Improvement Project ________________________________________________ 1
1.3 Contract WSIP/B1/GF/01: Rehabilitation of Ghotki Feeder Canal ______________________________ 3
2. Policy, Legal and Administrative Framework 9
2.1 Introduction ________________________________________________________________________ 9
2.2 Pakistan Legal Framework ____________________________________________________________ 9
2.3 Lender Policy _____________________________________________________________________ 13
2.4 Review of Government and World Bank Resettlement Policies _______________________________ 16
2.5 WSIP Social Impact Management Framework ____________________________________________ 17
2.6 Entitlement Matrix __________________________________________________________________ 17
3. Description of the Sub-Project 22
3.1 General Institutional Arrangements, Roles & Responsibilities ________________________________ 22
3.2 Location of the Project ______________________________________________________________ 24
3.3 Right of Way ______________________________________________________________________ 25
3.4 Scope of Works ___________________________________________________________________ 26
3.5 Labour Requirements _______________________________________________________________ 27
3.6 Assessment of Potential Impacts ______________________________________________________ 27
3.7 Proposed Construction Activities ______________________________________________________ 32
3.8 Corridor of Impact (CoI) _____________________________________________________________ 37
4. Socio-Economic Studies 40
4.1 Approach and Methodology __________________________________________________________ 40
4.2 Socio-Economic Profile of Sub-Project Area _____________________________________________ 41
4.3 Socio-Economic Profile of CoI ________________________________________________________ 47
5. Assessment of Impacts 60
5.1 General __________________________________________________________________________ 60
5.2 Identification of PAPs _______________________________________________________________ 60
5.3 Overview of Impacts ________________________________________________________________ 61
5.4 Loss of Agricultural Land ____________________________________________________________ 61
5.5 Loss of Residential, Commercial, Industrial or Institutional Land ______________________________ 62
5.6 Loss of Structures__________________________________________________________________ 62
5.7 Impact to Income __________________________________________________________________ 66
5.8 Impacts on Trees __________________________________________________________________ 68
5.9 Indirect Impacts ___________________________________________________________________ 68
5.10 Summary ________________________________________________________________________ 69
Content
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
6. Public Consultation and Information Disclosure 70
6.1 Introduction _______________________________________________________________________ 70
6.2 Objectives of Consultation ___________________________________________________________ 70
6.3 Methodology ______________________________________________________________________ 70
6.4 Consultations with Project Affected Persons _____________________________________________ 71
6.5 Consultation with Local Women Community _____________________________________________ 73
6.6 Meetings with Secondary Stakeholders _________________________________________________ 74
6.7 Grass Root Stakeholders Consultation __________________________________________________ 74
6.8 Summary of Consultation Findings _____________________________________________________ 74
7. Relocation and Compensation Plan 76
7.1 General __________________________________________________________________________ 76
7.2 Loss: Land (Agricultural) _____________________________________________________________ 76
7.3 Loss: Land (Residential and Commercial) _______________________________________________ 78
7.4 Loss: Privately Owned Structures _____________________________________________________ 85
7.5 Loss: Community or Institutional Structures ______________________________________________ 86
7.6 Loss: Income _____________________________________________________________________ 86
8. Institutional Arrangements 88
8.1 Sindh Irrigation and Drainage Authority _________________________________________________ 88
8.2 Ghotki Area Water Board ____________________________________________________________ 88
8.3 Board of Revenue _________________________________________________________________ 89
8.4 Project Coordination and Monitoring Unit (PCMU) _________________________________________ 89
8.5 Monitoring and Evaluation Consultants _________________________________________________ 89
8.6 Project Implementation Consultants ____________________________________________________ 90
8.7 Contractor ________________________________________________________________________ 91
8.8 Grievance Redress _________________________________________________________________ 91
8.9 Organisation Structure ______________________________________________________________ 93
8.10 Training and Capacity Building ________________________________________________________ 94
9. Budget 96
10. Implementation of RAP 99
10.1 Introduction _______________________________________________________________________ 99
10.2 Implementation Schedule ____________________________________________________________ 99
10.3 RAP Implementation Detail _________________________________________________________ 102
11. Monitoring and Evaluation 107
11.1 Introduction ______________________________________________________________________ 107
11.2 Monitoring and Evaluation __________________________________________________________ 107
11.3 Internal Monitoring ________________________________________________________________ 107
11.4 External Monitoring and Evaluation ___________________________________________________ 108
11.5 Monitoring Framework _____________________________________________________________ 109
Appendices 110
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Appendix A. Organization Chart of PIC Social Team ________________________________________________ 111
Appendix B. Additional Details of Survey Participants & Consultations __________________________________ 112
B.1. Detail of Officials Participated in Field Surveys __________________________________________ 112
B.2. List of Officials Contacted during survey _______________________________________________ 112
B.3. Contact Detail of Board of Revenue ___________________________________________________ 113
B.4. Meeting with Consultants Regarding Program Tendering Documents for Ghotki Feeder Canal _____ 114
B.5. Grass root stakeholders Consultations _________________________________________________ 116
B.6. Names of Sample Surveyed Villages __________________________________________________ 117
Appendix C. Survey Questionnaires and Data Collection Tools ________________________________________ 118
Appendix D. Details of Project Affected Persons and Assets __________________________________________ 134
D.1. Details of Affected Structures of Ghotki Feeder Canal and Estimated Compensation Cost _________ 135
D.2. Details of Low Income Allowance Entitlements __________________________________________ 142
D.3. Details of Livelihood Allowance ______________________________________________________ 146
D.4. Household monthly expenditure ______________________________________________________ 146
D.5. Long Distance Transport Allowance ___________________________________________________ 153
Appendix E. Details of Affected Farmers _________________________________________________________ 154
Appendix F. Grass Root Consultations ___________________________________________________________ 156
Appendix G. Details of Asset Valuation ___________________________________________________________ 161
G.1. Detail of market Rates for Pacca House ________________________________________________ 161
G.2. Detail of market Rates for Semi Pacca House ___________________________________________ 162
G.3. Detail of market Rates for Kacha House _______________________________________________ 163
G.4. Detail of market Rates for Semi Pacca Boundary Wall_____________________________________ 164
G.5. Detail of market Rates for Kacha Boundary Wall _________________________________________ 165
G.6. Detail of market Rates for Pacca Boundary Wall _________________________________________ 166
G.7. Detail of market Rates for Kacha Hut __________________________________________________ 167
G.8. Detail of market Rates for Straw Hut __________________________________________________ 168
G.9. Market Quotations ________________________________________________________________ 169
Appendix H. Deh Maps _______________________________________________________________________ 170
H.1. RD 63+000 ______________________________________________________________________ 170
H.2. RD 127+000 _____________________________________________________________________ 171
Appendix I. Corridor of Impact _________________________________________________________________ 172
I.1. Embankment Works Corridor of Impact – Cross Sections __________________________________ 172
I.2. Corridor of Impact for Realignment of Offtaking Canal – Layout Plans ________________________ 186
Appendix J. Pictorial View ____________________________________________________________________ 189
J.1. Women Consultation in the Project Area _______________________________________________ 192
Appendix K. Relocation Plans _________________________________________________________________ 194
Tables
Table 2.1: Comparison of Pakistan’s LAA and WB Resettlement Policy _________________________________ 16
Table 2.2: Entitlement Matrix __________________________________________________________________ 18
Table 3.1: Salient Features of Ghotki Feeder Canal ________________________________________________ 24
Table 3.2: Ghotki Feeder Canal Reported RoW ___________________________________________________ 25
Table 3.3: Hydraulic Structures to be Demolished and Replaced – Contract WSIP/B1/GF/01 ________________ 26
Table 3.4: Scoping of Potential Impacts of Contract WSIP/B1/GF/01 ___________________________________ 28
Table 3.5: Assessment of Impacts following Design and Planning Mitigations ____________________________ 31
Table 3.6: Proposed works for reconstruction of embankments _______________________________________ 33
Table 3.7: Works Schedule – Summary for Contract WSIP/B1/GF/01 __________________________________ 37
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Table 3.8: Ghotki Feeder Canal CoI for Embankment Raising ________________________________________ 38
Table 4.1: Cropping Pattern of Ghotki District _____________________________________________________ 42
Table 4.2: Cropping Pattern of Sukkur District ____________________________________________________ 43
Table 4.3: Literacy Rate in the sub-project Corridor ________________________________________________ 43
Table 4.4: Access to Social Amenities in the sub-project area ________________________________________ 44
Table 4.5: Pressing Needs of Men (Multiple Responses) ____________________________________________ 45
Table 4.6: Women Role in Socio-economic Activities (Multiple Response) _______________________________ 45
Table 4.7: Pressing Needs of Women(Multiple Response) ___________________________________________ 46
Table 4.8: Population of the CoI _______________________________________________________________ 47
Table 4.9: Income and Poverty Status of the Affected Households_____________________________________ 49
Table 4.10: Poverty Status of Ghotki Feeder Canal (Below Poverty Line) ________________________________ 50
Table 4.11: Expenditure of Affected Households ___________________________________________________ 51
Table 4.12: Settlement Background of PAPs ______________________________________________________ 52
Table 5.1: Detail of Impacted Structures within the CoI ______________________________________________ 63
Table 5.2: Detail of Government Structure at CoI __________________________________________________ 65
Table 5.3: Summary of Project Impacts _________________________________________________________ 69
Table 6.1: Impacts and Mitigations Discussed during Consultations ____________________________________ 74
Table 7.1: Inventory of Land Acquisition at RD 63 _________________________________________________ 77
Table 7.2: Inventory of Land Acquisition at RD 125 ________________________________________________ 77
Table 7.3: Yield price and total value of affected crop/acre ___________________________________________ 77
Table 7.4: Resettlement Locations _____________________________________________________________ 79
Table7.5: Compensation Rates for Replacement Assets ____________________________________________ 85
Table 8.2: Grievance Redress Committee _______________________________________________________ 92
Table 9.1: Budget for Implementation of the RAP __________________________________________________ 97
Table 10.1: RAP Implementation Schedule _______________________________________________________ 100
Table 11.1: Monitoring Framework _____________________________________________________________ 109
Figures
Figure 1.1: Sub-project Location for Works on Contract WSIP/B1/GF/01 – Ghotki Feeder AWB ________________ 4
Figure 1.2: Sub-project Area for Works on Contract WSIP/B1/GF/01 ____________________________________ 5
Figure 3.1: Institutional Setup for Project Implementation ____________________________________________ 22
Figure 3.2: Eroded berm on the Ghotki Canal _____________________________________________________ 25
Figure 3.3: Location Plan of Main Camp at RD125 _________________________________________________ 32
Figure 3.4: Typical Canal Cross-section showing Embankment Raising Works ____________________________ 34
Figure 3.5: Berm Cutting _____________________________________________________________________ 35
Figure 3.6: Berm Formation ___________________________________________________________________ 35
Figure 3.7: Layout for Replacement of Head and Cross-Regulators at RD125 ____________________________ 36
Figure 3.8: Example of Continuous CoI on Ghotki Feeder Canal _______________________________________ 37
Figure 3.9: Example of Discontinuous CoI on Ghotki Feeder Canal_____________________________________ 37
Figure 3.10: Key to indicative canal cross-section showing CoI. ________________________________________ 38
Figure 4.1: Women Engaged in Agriculture and livestock ____________________________________________ 46
Figure 4.2: Employment of all PAPs (121 households) ______________________________________________ 48
Figure 4.3: Employment of PAPs residing in the CoI (84 households) ___________________________________ 49
Figure 4.4: Cropping in the Project Area _________________________________________________________ 57
Figure 4.5: Livestock in the Project Area _________________________________________________________ 58
Figure 5.1: View of Houses in the CoI ___________________________________________________________ 63
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Figure 5.2: View of Hand pump in the CoI ________________________________________________________ 65
Figure 5.3: View of Irrigation room ______________________________________________________________ 66
Figure 5.4: View of police chowki _______________________________________________________________ 66
Figure 5.5: Shops Located within CoI of Contract WSIP/B1/GF/01 _____________________________________ 67
Figure 6.1: Consultations with Project Affected Women Regarding Hand Pumps __________________________ 73
Figure 8.1: Organisational Structure for RAP Implementation _________________________________________ 94
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Abbreviations
Acronym Definition Acronym Definition
ACS Additional Chief Secretary ISEA Integrated Social and Environmental Assessment
ADB Asian Development Bank IUCN International Union for Conservation of Nature
AFs Affected Families LAA Land Acquisition Act
APL Adaptable Program Loan LBOD Left Bank Outfall Drain
APs Affected Pearson M&E Monitoring and Evaluation
AWB (s) Area Water Board (s) MAF Million Acre –Feet
BCM Billion Cubic Meters MD Managing Director
BER Bid Evaluation Report MIS Management Information System
BHU Basic Health Unite MRL Maximum Residue Limit
BP Bank Procedures NAM New Accounting Model
CAS Country Assistance Strategy NARC National Agriculture Research Centre
CBC Community Based Contract NCB National Competitive Bidding
CBOs Community Based Organizations NDP National Drainage Program
CCA Cultivable Command Area NFDC National Fertilizer Development Centre
CFAA Country Financial Accountability Assessment
NGO Non Governmental Organizations
Cfs Cubic feet per second NIP
NRP
Non Inspection Path
National Resettlement Policy
CM Community Member O&M Operation and Maintenance
CoA Chart of Accounts OECF Overseas Economic Cooperation Fund
CoI Corridor of Impact OFWM On-Farm Water Management
Cs Cusecs OP Operational Procedure
DA Designated Account OPL Official Poverty Line
DFID Department for International Development P&D Planning & Development
DGAE Director General Agricultural Extension PAP Project Affected People
DGAE&WM Director General Agricultural Engineering and Water Management
PCMU Project Coordination & Management Unit
DO Development Objective PDO Project Development Objective
Dos Direct Outlets PFAA Provincial Financial Accountability Assessment
DPR Delivery Performance Ratio PIC Project Implementation Consultants
EA Environmental Assessment PIFRA Program to Improve Financial Reporting and Auditing
EIA Environmental Impact Assessment PIP Project Implementation Plan
EMF Environmental Management Framework PMCA Project Management Consultant/Procurement Agent
EMP Environmental Management Plan PMP Pest Management Plan
EMU Environmental Management Unit PP Plant Protection
EPA Environmental Protection Agency PSC Project Steering Committee
EoI Expression of Interest PSR Project Supervision Rating
ERR Economic Rate of Return RAP Resettlement Action Plan
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Acronym Definition Acronym Definition
ESP Environmental and Social Plan PRC Project Resettlement Committee
FAO Food and Agriculture Organization RD Reduce Distance
FFS Farmer Field School RFP Request for Proposal Packages
FGD Focus Group Discussion RP Resettlement Plan
FM Financial Management SA Special Accounts
FMR Financial Management Report SAP Social Action Plan
FO Farmers Organization SCARP Salinity Control and Reclamation Program
GB General Body SEPA Sindh Environmental Protection Agency
GCA Gross Command Area SIDA Sindh Irrigation and Drainage Authority
GDP Gross Domestic Product SIL Specific Investment Loan
GIS Geographic Information Systems SIMF Social Impact Management Framework
GPs Good Practices SMP Social Management Plan
GPN General Procurement Notice SOFWMP Sindh On-farm Water Management Project
GoP Government of Pakistan Sq.ft Square Fit
GoS Government of Sindh SWMO 2002 Sindh Water Management Ordinance 2002
Ha Hectare SWSIP Sindh Water Sector Improvement Project
I&D Irrigation and Drainage TCP Technical Cooperation Programmes
IAS International Accounting Standards TI Transparency International
IBIS Indus Basin Irrigation System ToF Training of Facilitators
IBRD International Bank for Reconstruction and Development
ToR Terms of Reference
ICB International Competitive Bidding UNDB United Nations Development Business
ICR Implementation Completion Report VR Village Road
IDA International Development Association WAC Water Allocation Committee
IDMTA Irrigation and Drainage Management Transfer Agreement
WAPDA Water and Power Development Authority
IEE Initial Environmental Examination WB World Bank
IFC International Finance Corporation WCA Water Course Association
IFRS International Financial Reporting Standards
WSIP Water Sector Improvement Project
INTOSAI International Organization of Supreme Audit Institutions
WTO World Trade Organization
IP/ NIP Inspection Path/ Non-Inspection Path WTS Walk Through Survey
IPD Irrigation and Power Department WWF World Wildlife Fund
IPM Integrated Pest Management IPSNM Integrated Plant and Soil Nutrients Management
Glossary of National Terms
Term Definition Term Definition
Abiana Irrigation water charges Mogha Ungated outlet from distributary/ minor or canal
Chaks or Dehs
Tertiary irrigation command area Mohanas A fish hunting community by profession.
Cabin Wooden Kiosk
Hari Tenant Pancho An irrigation practice where water is let to cascade from one field to another
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Term Definition Term Definition
Kharif Summer crop season (April-October) Rabi Winter crop season (November-March)
Warabandi Rotational system for water distribution Pacca House or building constructed with concrete or burned bricks
Semi-Pacca
House or building constructed with burnt bricks and mud
Kacha House constructed with un-burnt bricks and mud, or temporary wooden poles etc
Jhoopra Hut Otaq Formal sitting/living arrangements for men guests
Washing Ghats
Areas designed along the canal/minor for laundry purpose
Tehsil / Taluka
A sub- division of a district headed by Assistant Commissioner, generally a district comprises of
3 to 5 tehsils
DEFINITIONS OF TERMS The following terms and definitions have been used in this report (RP):
Affected Person/People Any person affected by project-related changes in use of land, water, natural resources, or income losses.
Affected Family/Household All members of a household residing under one roof and operating as a single economic unit, who are adversely affected by the Project, or any of its components. It
may consist of a single nuclear family or an extended family group.
CoI (Corridor of Impact) It is an area falling within the Right of Way (RoW) used to determine the area of specific impact from the proposed works.
Compensation Payment in cash or in kind of the replacement cost of the acquired assets or structures.
Cut-off-date For non-land related entitlements: The date of the start of the census survey
For land related entitlements: Date of notification under section 4 of the Land Acquisition Act
Encroacher Person who extends his/her structure beyond area of ownership into adjacent areas
Entitlement Range of measures comprising compensation, income restoration, transfer assistance, income substitution, and relocation, which are due to affected people, depending on
the nature of their losses, to restore their economic and social base.
Income Restoration Includes re-establishing income sources and livelihood of the affected persons according to their status
Involuntary Resettlement Any resettlement, which does not involve willingness of the persons being adversely affected, but are forced through an instrument of law.
Shops Commercial structures, like groceries, vulcanizing shops, tailoring shops, beauty parlour, market stalls, hotels, movie houses, and similar establishments.
Indigenous Peoples The term ‘Indigenous Peoples’ is used in a generic sense to refer to a distinct, vulnerable, social and cultural group possessing characteristics as defined by the
World Bank Operational Policy/Bank Policy 4.101.
Land Acquisition The process whereby a person is compelled by a government agency to acquire all or part of the land a person owns or possesses to the ownership and possession of the
government agency for public purpose in return for compensation.
Market Value The value of an asset determined by market transaction of similar assets and finally arrived at after negotiations with the owners. It includes transaction costs and without
the depreciation and deductions for salvaged building material.
_________________________ 1 World Bank Operational Manual available at http://go.worldbank.org/DZDZ9038D0
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
Sindh Water Sector Improvement Project
Marginally Affected Land or structure means less than 10 percent of the land or structure is affected and where the remaining unaffected portion is still viable for use.
Participation A process that allows stakeholders to influence and share control over development initiatives, decisions and the use of resources that affect them.
Project Area The area specified by the Project Document in the Official Notification and includes the areas within administrative limits of the Provincial Government.
Project Director (PD)
The officer selected by the SIDA, Government of the Sindh responsible for execution of the project.
Project Impacts Loss of physical and non-physical assets, including houses, communities, productive land, income-earning assets and sources, use of resources, cultural sites, social
structures, networks/ties, cultural identity and mutual help mechanisms.
Rehabilitation Compensatory measures provided under the World Bank Policy Framework on involuntary resettlement other than payment of the replacement cost of acquired
assets/ structures.
RoW (Right of Way) It is an area allocated to any canal, distributary, minor road, sui gas pipeline or any high transmission line etc on its right and left sides for its safeguard, patrolling or any
future development on its either side.
Relocation The physical relocation of an AP from her/ his pre-Project place of residence or business.
Replacement Cost The value determined to be fair compensation for land based on its productive potential, the replacement cost of houses and structures (current fair market price of
building materials and labour without depreciation or deductions for salvaged building material), and the market value of residential land, crops, trees, and other
commodities.
Severely Affected Land or structure means more than 10 percent of total land or structure is affected or even less than 10 percent is affected but the remaining portion is no longer viable for
use.
Squatter People who occupy and use land without possessing it or having any legal title, or right to use/ possess the land / asset for residential or commercial purpose.
Stakeholders Include the affected persons and communities, proponents, private and public businesses, the NGOs, host communities and other concerned departments/ agencies.
Vulnerable The marginalized or those distinct people who might face the risk of marginalization and suffer disproportionately from resettlement effects, including the women, children,
destitute persons, Encroacher/Informal Settlers; those with historical or cultural usufruct rights; and landless groups. Generally, people who are living below the
poverty line are called vulnerable persons, people/family.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
i
Sindh Water Sector Improvement Project
Introduction
Development of agriculture and agro-based industries is the present need of the country.
Agriculture is an important source of employment and exports (two thirds of employment
and 80% of exports); irrigation represents more than 95% of the total consumptive use of
water. However, this massive infrastructure is deteriorating and is in need of
rehabilitation. In response to this the Government of Sindh has launched the Sindh
Water Sector Improvement Project (WSIP-1) with the financial support of the World Bank
to improve the efficiency of irrigation water distribution in Ghotki, Nara and Left Bank
Area Water Boards (AWBs). The project is being executed through the Sindh Irrigation
and Drainage Authority (SIDA) with the active involvement of AWBs and Farmers
Organizations (FOs) with support from the Project Implementation Consultants (PICs).
The WSIP interventions include rehabilitation of canals and existing structures,
construction of new head and cross regulators, construction of buffalo wallows, provision
of washing ghats and new foot and village road bridges on selected reaches of the Main,
Branch, Distributary and Minor Canals.
The implementation plan for the assistance for affected persons described in this
Resettlement Action Plan (RAP) is to be synchronized with the implementation schedule,
including the procedure for assistance to the Project Affected Persons (PAPs) and
complete disclosure of project documents to the public.
The B1 project component includes the rehabilitation of the Main and Branch Canals of
the Ghotki, Nara and Left Bank Canal systems covering some 830 km of Main Canals
and 1,130 km of Branch Canals. This RAP covers the direct social and economic
impacts resulting from the sub-project for Rehabilitation of the Ghotki Feeder Canal
(Ghotki AWB) to be implemented under contract WSIP/B1/GF/01. The proposed contract
works have been prepared based on consultations with the AWB at each stage of
identification, prioritization and planning. The RAP has been prepared to comply with
national legislative requirements, the World Bank`s loan requirements, and the Social
Impact Management Framework prepared for WSIP and addresses the impacts
associated with this sub-project.
Scope of Works
The scope of works for this sub-project is as follows:
Establishment of temporary camps for the contractor’s equipment and work force
Rehabilitation of canal embankments
Executive Summary
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
ii
Sindh Water Sector Improvement Project
o Raising and strengthening of Non-Inspection Path (NIP) from RD 0-63 (L/S)
and RD:63-124 (R/S)
o Raising and strengthening of Inspection Path (IP) from RD 40-64 (R/S) and
RD:64-127 (L/S)
Establishment of borrow areas
Canal desilting and lowering of the bed level from RD 0 to 125
Cutting of the berm in isolated reaches from RD 0 to 125 on the left bank and from RD
40 to 125 on the right bank
Disposal of excavated material
Formation of the canal berm through the construction of killa bushing in isolated
reaches from RD 0 to 125
Replacement of two cross regulators on the Ghotki Feeder Canal
Replacement of four major and six minor head regulators offtaking from Ghotki Feeder
Canal and realignment of the head reaches of offtaking canals
Construction of temporary canal diversions
Construction of two Village Road Bridges (VRBs)
Rehabilitation of four VRBs
Repair of existing sanctioned Direct Outlets RD: 0-127
The works detailed above constitute the proposed sub-project and are all considered
within this RAP.
Purpose of the Resettlement Action Plan
The potential for direct economic and social impacts to arise from implementation of this
sub-project have been identified. This RAP has been prepared as a plan for mitigations
of these impacts and to, at least, maintain living standards of those affected by the sub-
project activities. It includes the findings of socio-economic studies, census survey,
consultations, parameters for entitlement packages for PAPs, the institutional framework,
mechanisms for consultation, grievances resolution and the implementation timeframe.
The principal objective of the RAP is to ensure that all affected persons losing assets,
infrastructure and livelihood as a result of the project are eligible to receive compensation
and livelihood assistance. Such compensation and assistance shall be provided
irrespective of ownership of title to the land.
Policy Legal and Administrative Framework
Land based entitlements due to registered land owners are in accordance with the Land
Acquisition Act of Pakistan, which also meets the requirements of World Bank Policies.
Pakistan law does not provide for the payment of compensation or livelihood assistance
to PAPs who do not hold a title to the land on which they depend for shelter or livelihood.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
iii
Sindh Water Sector Improvement Project
However, World Bank policy requires that all affected persons losing assets,
infrastructure and livelihood as a result of a project are eligible to receive compensation
and livelihood assistance, irrespective of ownership to a title to the land. To ensure
compliance with World Bank policy, entitlements are provided by an Entitlement Matrix
which is based on the Social Impact Management Framework, prepared by the
Government of Sindh for WSIP in 2006. This Entitlement Matrix ensures the following:
Compensation for lost assets regardless of rights to land on which they are sited
Valuation of assets and land at the prevailing market rate
Assistance in relocation for any PAP, regardless of legal entitlement to the land they
occupy, in the form of a cash transport allowance
Provision of additional allowance for those who may suffer impacts to their livelihood
Permission for PAPs to rebuilt affected assets on alternative government owned sites
(without transfer of title).
The matrix was updated in May 2016 to clarify some entitlement policies based on
implementation of contracts WSIP/B1/NC/01 and WSIP/B1/NC/02 (in the Nara Area
Water Board) and their associated Resettlement Action Plans.
Collection of Primary Data
The preparation of this Resettlement Action Plan required the collection of data and
information from the field. To achieve this end, comprehensive questionnaires for data
collection were prepared and filled during consultative meetings and field visits. Four
types of questionnaires were developed for data collection:
Village profile for the collection of macro level information relating to the existence of
socio-economic infrastructure in the rural settlements falling within CoI.
Census survey to document the PAPs, their assets, family profiles and economic
status.
Socio-economic survey to develop an overall baseline profile of the people of the area
in respect to their socio-economic behaviour, vulnerability and attitudes towards the
developmental activity to be carried out in the area.
Gender data collection survey targeting the female population of the CoI exclusively in
order to supplement the socio-economic data collection.
Consultations were made with the stakeholders and general public. Consultative
meetings and focus group discussions were held to elicit and record the views and
concerns of the local community on the proposed rehabilitation works. The concerns
raised by the stakeholders were considered and engineering designs have been
adjusted in order to enhance the sub-projects acceptability for the general public on
socio-economic considerations. The main objectives of the consultations were to provide
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
iv
Sindh Water Sector Improvement Project
a platform for the stakeholders to voice their suggestions to the project team and to
develop a sense of collective ownership for the activities of the sub-project.
Socio-economic Baseline of CoI
The CoI for the embankment strengthening works is entirely owned by the Government
of Sindh. 87 households2 (645 PAPs) have illegally built residential and commercial
structures within the Government owned land, of which 84 households (622 PAPs)
permanently reside in the CoI. None of these PAPs have a legal entitlement to the land
they occupy. In addition, 307.6 acres of land is illegally cultivated by the farmers within
the CoI.
The surveys have identified that the primary source of income for the PAPs is agriculture,
either as general labourers, tenants of farm owners. A small number are engaged in
fishing, and the primary income of four households is from small businesses situated
within the CoI. 97% of the PAPs were found to be earning below the Pakistan poverty
line.
The caste system is very prevalent within the CoI. Each PAP belongs to a caste, and
conflicts are most commonly resolved by the head of the caste. Where conflicts cannot
be resolved in this way, they may be resolved by the village head, political leaders, or, as
a last resort, in a court of law.
Sub-Project Impacts
Surveys of the CoI completed by PIC identified 84 households (622 PAPs) residing in the
CoI, of which two also own commercial structures. A further three households (23 PAPs)
were identified as owning commercial structures in the CoI (but residing outside the CoI).
Note that a single household may own multiple structures within the CoI. A further 34
households who are illegally farming 307.6 acres of government owned land in the CoI
have been identified.
In addition, the permanent acquisition of approximately 9.25 acres (owned by 6
households) and temporary acquisition of 10 acres (owned by 5 households) of privately
owned land shall be required for the execution of the works.
The clearance of one hand pump which is owned by the community is also required. The
proposed works and construction methodology have been designed to prevent the need
to remove mosques and graves. Two Governments owned sites (a police chowki and an
irrigation office) and one hand pump have also been established within the CoI. The
_________________________ 2 A household is defined as a family living with the head of the household and all the structures they own.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
v
Sindh Water Sector Improvement Project
demolition of all such structures is required prior to the implementation of works under
this sub-project. The replacement of community and Government owned sites shall be
managed through the construction contract.
Tree cutting along the canal embankments and at the proposed structure sites is also
required. All trees are owned by the Government, and their replacement shall be covered
in the civil works contract. Tree cutting is discussed in detail in the Environmental Impact
Assessment and Management Plan for Contract WSIP/B1/GF/01.
The works shall directly impact a total of 132 households. A summary of the direct social
and economic impacts resulting from this sub-project is provided in the following table.
Note that the table below sorts impacts by type of loss - as a single impacted household
may experience multiple losses (and therefore a single household may be reported
under two or more types of loss), the total number of impacted households cannot be
summed from this table.
Table ES.1: Summary of Sub-Project Impacts
Type of Loss
Application
Definition of Impacted Person
Unit Total
Loss of Land (Agricultural)
Permanent loss of entire land or where partial loss but the remaining land is less than 0.5 acre or is rendered economically unviable.
Legal owner with valid title or customary or usufruct rights.
Impacted Acres
(Impacted Households)
9.925
(6)
PAPs without title
Impacted Acres
(Impacted Households)
307.6
(34)
Temporary loss of land Legal owner with valid title or customary or usufruct rights.
Impacted Acres
(Impacted Households)
10
(5)
Loss of Land (Residential, commercial, industrial or institutional land)
Loss of residential, commercial, industrial or institutional land without sufficient remaining land. PAPs will be required to relocate.
PAPs without title
Impacted Households
87
PAPs living below the poverty line (regardless of ownership
Impacted Households
84
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
vi
Sindh Water Sector Improvement Project
Type of Loss
Application
Definition of Impacted Person
Unit Total
of title to land on which structure is situated)
Loss of Privately Owned Structures (Residential, commercial, industrial or agricultural)
Entire loss of structures or where only partial impact, but the remaining structure is rendered unviable for continued use, and sufficient land for reorganization.
Owner of structure (regardless of ownership of title to land on which structure is situated)
Impacted Households
87
Loss of Structures (Community or institutional)
Entire loss of structures or where only partial impact, but the remaining structure is rendered unviable for continued use.
Community or institution
Number of Impacted Structures
4
Loss of income (trade/ livelihood/ occupation or business incomes)
Temporary or permanent loss of agricultural/commercial/institutional income or wages
Impacted business owner
Impacted Households
5
Cut-off Date
The cut-off date for eligibility for all entitlements except land based entitlements due to
registered owners has been set as the 08th August 2014. The 08th August 2014 was the
first working day of PIC field team in the field during the 2014 field visit, during which the
consultants updated the impact assessment and survey of the population of the CoI. Any
person constructed assets in the CoI after this date shall not be eligible for entitlements
under this Resettlement Action Plan.
The cut-off date for eligibility for land related entitlements due to registered owners shall
be the date of the section 4 notification issued under the Land Acquisition Act of
Pakistan.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
vii
Sindh Water Sector Improvement Project
Public Consultation and Information Disclosure
The PAPs were made fully aware of the Resettlement Action Plan through consultative
meetings, individual and group discussions about the sub-project and the Resettlement
Action Plan. During these consultations, entitlements and mitigations were discussed
and agreed upon. PAPs were generally satisfied with the consultations regarding
assistance for their lost assets. Where PAPs are to be displaced by the sub-project
works, consultations were also carried out to identify suitable alternative sites for each
household. The alternative sites shall provide equal or better living/trading conditions
than the original site of each household.
Compensation, Relocation and Income Restoration
Privately owned land shall be permanently acquired as per the provisions of the Land
Acquisition Act of Pakistan which is compliant with World Bank policy for the purposes of
land acquisition. Land to be temporarily acquired shall be rented at prevailing market
rates on agreement between the land owner and the contractor.
All structures situated within the CoI are built on Government land. Therefore, owners of
the houses, shops and other structures do not own a title to the land on which these
structures are located. The affected households are permitted to rebuild their structures
at an alternative government owned site (but without the transfer of title to ownership of
this land). They are also entitled to a transport allowance (regardless of whether they
have opted to move to a government owned site or not). Where the affected household is
living below the poverty line, the household shall also be provided an additional Low
Income Allowance.
Owners of structures which are to be removed from the CoI are eligible for compensation
to rebuild the affected structure, regardless of whether they own the land on which the
structure is situated or not. Structure valuations are based on prevailing local market
rates.
For those PAPs owning commercial structures within the CoI, a Livelihood Allowance
shall be paid. This allowance shall be equal to three times the monthly income of the
household, or equal to the equivalent of three months minimum wage in Pakistan,
whichever is greater. This allowance is intended to compensate for any lost income
during transition, relocation and reconstruction of their businesses.
Where PAPs shall lose standing crops as a result of the sub-project, they shall be
compensated at a per acre rate based on the average yield and average value of
cultivated crops in the sub-project area. This compensation shall be paid to owners of the
crops irrespective of ownership of title to the land on which the crops are grown,
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
viii
Sindh Water Sector Improvement Project
All compensation rates have been calculated based on prevailing markets rates, with
inflation to 2016 values where appropriate.
Impacted community and government structures shall be reconstructed under the civil
works contract.
Institutional Framework
A strong institutional framework is already in place under WSIP for the implementation of
this Resettlement Action Plan. SIDA will be responsible for implementing the RAP and
coordination with relevant parties, including the Board of Revenue. SIDA may delegate
some responsibilities to the AWB, however, SIDA shall remain responsible for ensure all
actions are implemented. With the exception of temporary land acquisition,
reconstruction of government structures and one community hand pump, compensation
will not be part of the civil works contract but shall be paid by SIDA.
The disbursement of compensation and allowances, vacation of the CoI and the
permanent acquisition of land, shall be fully implemented prior to the mobilisation of the
contractor for the works in order to prevent any delays to construction.
A Grievance Redress Committee shall be formed to provide a mechanism to mediate
conflict and cut down on lengthy litigation. The Grievance Redress Mechanism will
provide a forum to people to raise objections or concerns about project impacts and their
mitigations.
Resettlement Budget
The total cost for the implementation of this Resettlement Action Plan is estimated to be
PKR 65,944,398 (USD 659,444). This includes the compensation cost of affected
structures within CoI, allowances, permanent land acquisition, cost of monitoring and
evaluation, training and administrative costs.
Monitoring and Evaluation
SIDA shall complete internal monitoring of implementation of the RAP in close
coordination with the Environmental Management Unit (EMU) of SIDA. Internal
monitoring shall be supplemented by external monitoring and evaluation by the
Monitoring and Evaluation Consultants for WSIP. On monitoring framework is provided in
this RAP.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
1
Sindh Water Sector Improvement Project
1.1 The Indus Basin Irrigation System
In order to fully utilize the river water resources of Pakistan, the Indus Basin Irrigation System (IBIS) has
emerged as the largest contiguous irrigation system in the world. Irrigated agriculture within the IBIS
provides not only food security to the country (supplying 90% of food production3), but also economic
growth (accounting for over 25% of the country’s Gross Domestic Product and 44% of employment in
20134). The Indus River is therefore a critical resource for Pakistan.
The IBIS comprises of three large dams, eighty five small dams, nineteen barrages, twelve inter-river link
canals, forty-five canal commands and 0.7 million tube wells. The IBIS irrigates 18.21 million hectares (45
million acres)5 of farm land producing wheat, rice, fruits, vegetables, sugarcane, maize and cotton for local
use as well as for export.
Sindh province is the second biggest beneficiary of the IBIS (after Punjab) with three barrages and 14
canal commands. The irrigation system has a total length of 19,066 km (11,916 miles) of canals, which
serve a gross command area (GCA) of 5.8 million ha (14,391 million acres). There are about 42,000
watercourses (tertiary channels), which have an aggregate length of approximately 120,000 km (75,000
miles) which supply irrigation water directly to agricultural land. Approximately 59 billion cubic meters (48
million acre-feet) or of water is diverted annually to the canal commands. Yet the province suffers from low
water availability and land productivity3.
1.2 Sindh Water Sector Improvement Project
1.2.1 Objectives
The Government of Sindh has launched the first phase of Water Sector Improvement Project (WSIP) with
the financial support of the World Bank (WB). The overarching project objective is to improve the efficiency
and effectiveness of irrigation water distribution in three areas of the Sindh Province, namely the Ghotki,
Nara and Left Bank Area Water Boards (AWBs). Improvement is measured with respect to reliability, equity
and user satisfaction.
1.2.2 Components of WSIP
WSIP is intended to begin addressing these complex issues with an optimal mix of institutional
strengthening, capacity building and investments in irrigation infrastructure. As such, WSIP is being
implemented in different phases, mainly, through the Sindh Irrigation and Drainage Authority (SIDA) and
AWBs.
Phase-1 of WSIP consists of following separate components:
Component A: Community Development and Capacity Building
Component B: Rehabilitation and Improvement of Irrigation and Canal Systems
_________________________ 3Project Appraisal Document on a Proposed Credit to Pakistan for a Sindh Water Improvement Phase 1Project, World Bank, 2007
4 World DataBank, World Bank, http://databank.worldbank.org/data/home.aspx, [accessed 13/01/15]
5http://www.tbl.com.pk/indus-basin-irrigation-system-of-pakistan/
1. Introduction
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
2
Sindh Water Sector Improvement Project
Component C: Management Plan for Major I&D Infrastructure
Component D: Monitoring and Evaluation of the Project Impact and Environmental Management Plan; and
Component E: Project Coordination, Monitoring, Technical Assistance and Training
Poor operation and maintenance in the irrigation sector has necessitated investment into the rehabilitation
of irrigation systems in the Nara, Ghotki and Left Bank AWBs. These rehabilitation activities are included
within Component B of WSIP, which has been sub-divided into two further sub-components: B1
(rehabilitation of Main and Branch Canals) and B2 (rehabilitation of Minor and Distributary Canals). Under
each sub-component, a number of rehabilitation packages (sub-projects) have been prioritised, designed,
let, or are to be let as individual construction contracts.
An Integrated Social and Environmental Assessment (ISEA) was conducted for WSIP at the feasibility
stage by the Government of Sindh in 2006, and includes a Social Impact Management Framework to be
implemented for WSIP.
In accordance with the Social Impact Management Framework, this Resettlement Action Plan has been
prepared for Contract WSIP/B1/GF/01, Rehabilitation of Ghotki Feeder Canal, which is a sub-project to be
implemented within the Ghotki AWB under component B1 of WSIP.
1.2.3 Project Administration
WSIP is being implemented under a sector loan agreement between Government of Pakistan (GoP) and
the WB. SIDA is the project proponent and is executing the project through the Nara, Ghotki and Left Bank
AWBs under the supervision of Project Director (WSIP). The Project Coordination and Monitoring Unit
(PCMU), sitting within the Planning and Development Department of the Government of Sindh, is
responsible for overall monitoring and coordination of the project implementation activities.
The association of Mott MacDonald Ltd and MM Pakistan (Pvt) Ltd was appointed in 2009 by the Managing
Director of SIDA as the Project Implementation Consultants (PIC) for WSIP phase 1. PIC were appointed
to assist SIDA in the implementation of WSIP, including undertaking the detailed designs, environmental
assessment, environmental management plans, resettlement actions plans, procurement of works and
construction supervision for the rehabilitation works proposed under component B.
1.2.4 Works under WSIP Component B1
Improvement works under component B1 include remodelling of the Main and Branch canals on the basis
of their sanctioned discharge, strengthening of embankments, rehabilitation and reconstruction of
regulating structures, installation of gauges and flow measurement structures, rehabilitation and
reconstruction of bridges where necessary, planting of trees and any other crucial rehabilitation works
identified during the design period.
Two sub-projects have already been implemented within the Nara AWB: Contract WSIP/B1/NC/01
(Rehabilitation of the Upper and Lower Nara Canals) and Contract WSIP/B1/NC/02 (Rehabilitation of
Makhi Complex and Khipro Canal).
A third major sub-project within the Nara AWB, Contract WSIP/B1/NC/03, is planned for the rehabilitation
of the Mithrao Canal. A further two major sub-projects have been identified: Contract WSIP/B1/GF/01
(Rehabilitation of Ghotki Feeder Canal in the Ghotki AWB); and, Contract WSIP/B1/LB/01 (Rehabilitation of
Fulleli Canal in the Left Bank AWB).
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
3
Sindh Water Sector Improvement Project
The detailed designs for Contract WSIP/B1/NC/03, Contract WSIP/B1/GF/01 and Contract WSIP/B1/LB/01
are complete. The preparation of the Environmental Impact Assessments (EIAs) and Environmental
Management Plans (EMPs) are complete, and Resettlement Action Plans (RAPs) for each sub-project are
under finalisation.
1.3 Contract WSIP/B1/GF/01: Rehabilitation of Ghotki Feeder Canal
1.3.1 General
Contract WSIP/B1/GF/01 (‘the sub-project’) of B1 component is to be carried out within the Ghotki AWB
and includes embankment strengthening and raising and earthworks in the canal prism for 43km (127 RD)
of the Ghotki Feeder Canal. The works also include the replacement of: two cross-regulators; four head
regulators to branch canals; and, six head regulators to minor and distributary canals, the construction of
two new village road bridges and the rehabilitation of four existing village road bridges. In accordance with
design, the majority of the proposed civil works activities will remain within the Government owned Right of
Way (RoW), thus minimum disturbance and relocation is envisaged, however there will be some impact on
privately owned land due to the realignment of offtaking canals.
1.3.2 Sub-project Area
The sub-project area of the Contract WSIP/B1/GF/01 consists of Ghotki Feeder Canal from RD 0 to 127
within the Ghotki AWB. Ghotki Feeder Canal off-takes directly from the left bank of the River Indus,
immediately upstream of Guddu Barrage. The design discharge of the canal is 9,436 ft³/s, and it supplies
irrigation water to a command area of 855,231 acres in the districts of Ghotki and Sukkur. The system has
deteriorated over time becoming inefficient in delivering water supplies for agriculture, suffering from
sedimentation in the upper reaches and deterioration of the hydraulic regulating structures.
Figure 1.1 and Figure 1.2 indicate the location of the sub-project area for Contract WSIP/B1/GF/01.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
4
Sindh Water Sector Improvement Project
Figure 1.1: Sub-project Location for Works on Contract WSIP/B1/GF/01 – Ghotki Feeder AWB
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
5
Sindh Water Sector Improvement Project
Figure 1.2: Sub-project Area for Works on Contract WSIP/B1/GF/01
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
6
Sindh Water Sector Improvement Project
1.3.3 Sub-project Objectives
The sub-project interventions will be executed by a Contractor, selected through the International
Competitive Bidding (ICB) process. The proposed engineering interventions are aligned with the objectives
of WSIP as follows:
To ensure authorized discharge flow requirements: Due to deferred maintenance of structures and
embankments, the Ghotki Canal irrigation system is in poor condition and is unable to sustain a safe
running of the authorized discharge. The rehabilitation works have been designed to enhance the water
carrying efficiency of the system through rehabilitation of the canal prism, and equitable distribution of
water from head to tail through the rehabilitation of regulation structures.
To ensure equitable resource distribution: The poor maintenance of hydraulic structures is leading
to lack of fair distribution of irrigation water. Major regulating structures are to be rebuilt to ensure
transparent and equitable distribution of water.
To protect interests of the community: Replacement of regulating structures will benefit the
community’s agricultural interest and ensure canal crossings which are used by the public are
maintained at the regulator sites (cross-regulator structures are also designed to carry public road
crossings). In addition, two new bridges are to be built, and four are to be rehabilitated.
To meet irrigation system safety standards: The civil work activities include reconstruction of
channel banks and berms, inspection paths and non-inspection paths. This shall reduce the risk of
canal breaches. Hydraulic structures shall also be provided with sufficient freeboard (distance from
water level to deck level) to prevent flooding of public crossings and sufficient guards to prevent
vehicles or members of the public entering the canals.
1.3.4 Type and Category of the Sub-project
It is anticipated that the sub-project may have some adverse social impacts associated with the
displacement of a number of residential and commercial structures. The most significant impact is loss of
shelter of PAPs.
The Ghotki Feeder Canal has a culturable command area of approximately 346,099 hectares (855,231
acres). Within this command area, agriculture is practiced to a large scale. Assuming an average farm size
of 3.1 ha (7.6 acres) per family and an average family size of 6.8 persons6, it is determined that
approximately 760,000 people are directly or indirectly dependent upon the irrigation water supplied
through the Ghotki Feeder Canal.
Any major impact resulting from the sub-project, such as disruption of irrigation flows, has the potential to
impact the large number of people who are dependent of the irrigation flows. This impact would be
potentially unprecedented over an area far broader than the immediate sub-project area itself.
As a result of the potential impacts detailed above Contract WSIP/B1/GF/01 is categorised as a Category A
project.
1.3.5 Need of Study
World Bank funded projects require a RAP for any project that results in involuntary land acquisition or
related impacts. The scope and level of detail of resettlement planning will vary with circumstances,
_________________________ 6 Project Appraisal Document on a Proposed Credit to Pakistan for a Sindh Water Improvement Phase 1Project, World Bank, 2007
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
7
Sindh Water Sector Improvement Project
depending on the project’s complexity and the magnitude of its effects. As a minimum requirement the RAP
must ensure that the livelihood of PAPs is restored to pre-project level. As the proposed Contract
WSIP/B1/GF/01 has social and resettlement issues a RAP has been prepared to address these issues.
The WB seeks to promote the improvement of the living standards of PAPs. Thus, resettlement activities
should result in visible improvements in the economic conditions and social well-being of affected people
and communities. The WB Involuntary Resettlement Policy (OP- 4.12) applies under all conditions of
potential physical or economic displacement resulting from the acquisition or use of land and other assets
for a project regardless of the total number of people.
Physical displacement could bring about disruption and impoverishment to communities. Therefore it
should be avoided or minimized by exploring all viable alternatives. If displacement is inevitable,
compensation plans should be developed in the early stages of the planning process of the project.
This document forms the RAP for the sub-project to be implemented under Contract WSIP/B1/GF/01. The
RAP is a substantial component of any development project that causes a change in the existing land use
patterns or requires the resettlement of people or businesses. Projects related to canal rehabilitation may
cause a series of resettlement effects. The need for resettlement mostly arises due to the clearance of an
area of land to enable the execution of construction works, or as a result of land acquisition through
expropriation or other regulatory measures. During this process houses, community structures and
systems, social networks and social services may be partially or completely and temporarily or permanently
damaged.
This RAP has been prepared to highlight the social consequences of rehabilitation activities in the Corridor
of Influence (CoI) of the sub-project and propose appropriate measures to reduce the adverse effects. This
RAP has been prepared in according to the Social Impact Management Framework for WSIP, Pakistan
Government Policy and World Bank Policy.
This document forms Volume I of the RAP. Volume I should be read alongside the Volume II of the RAP:
Socio-Environmental Baseline and Impact Maps, which also acts as Volume II of the EIA/EMP for this
contract.
1.3.6 Objectives of the Resettlement Action Plan
The potential for direct economic and social impacts to arise from implementation of this sub-project have
been identified. As such this RAP has been prepared as a plan for mitigation of these effects and to, at
least, maintain living standards of those affected by the sub-project activities. It includes the findings of
socio-economic studies, census survey, consultations, parameters for entitlement packages for PAPs, the
institutional framework, mechanisms for consultation, grievances resolution and the implementation
timeframe.
Development projects that displace people involuntary can generally give rise to economic, social and
environmental problems. Involuntary resettlement may cause severe long term hardship, impoverishment
and environmental damage without the application of appropriate measures to mitigate these impacts. This
RAP provides details regarding the likely impacts resulting from the sub-project intervention and the
mitigation measures that will be adopted to address these adverse impacts.
The principal objective of the RAP is to ensure that all affected persons losing assets, infrastructure and
livelihood as a result of the project are eligible to receive compensation and livelihood assistance. Such
compensation and assistance shall be provided irrespective of ownership of title to the land.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
8
Sindh Water Sector Improvement Project
The following are the specific objectives of this RAP:
Identify specific social and resettlement impacts of the sub-project by types and their mitigation
Identification of those to be directly impacted as a result of project implementation
Present a strategy for achieving the objectives of the World Bank policy and the Social Impact
Management Framework for WSIP
Provide a framework for implementation of strategies to ensure timely acquisition of land, payment of
compensation and delivery of other benefits to PAPs.
Provide details on the policies governing land acquisition and other direct impacts, the range of
entitlements to improve the living standards, income earning capacity and production levels of PAPs or
at least restore them to pre-project levels.
Provide details on the public information consultation and participation and grievance redress
mechanism in project planning, design and implementation.
Identify and provide an estimate of required resources for implementation of recommended strategies,
including monetary budget
To provide a framework for supervision, monitoring and evaluation of implementation of this RAP.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
9
Sindh Water Sector Improvement Project
2.1 Introduction
This chapter provides an overview of the relevant donor (World Bank) policies, Pakistan laws and the
Social Impact Management Framework (SIMF) prepared for WSIP with which this RAP complies.
2.2 Pakistan Legal Framework
2.2.1 General
The Land Acquisition Act (LAA) of 1894 is the main law regulating land acquisition for public purposes in
Pakistan. Each province has its own interpretation of the LAA, and some provinces have issued provincial
legislations. The LAA and its implementation rules require that, following an impact assessment and
valuation effort, land and crops are compensated in cash at market rate to titled landowners and registered
land tenants/users, respectively. The LAA mandates that land valuation is to be based on the latest 3-5
years average registered land sale rates though, recently, the median rate over the past 1 year, or even
current rates, were applied in some cases. Due to widespread practice of land under-valuation by the
Revenue Department, current market rates are now frequently applied, plus 15% Compulsory Acquisition
Surcharge as required under the LAA.
Based on the LAA only legal owners and tenants registered with the Land Revenue Department or
possessing formal lease agreements, are eligible for compensation. Users of the Rights of Way (RoW) are
not considered "affected" by project activities and thus not entitled to any mitigating measure,
compensation, or livelihood support. Also, there is no legal obligation to provide compensation to title-less
land users, unregistered tenants or encroachers either in form of house-for-house or land-for-land
replacement, or in form of cash.
The LAA also does not automatically mandate for specific rehabilitation/assistance provisions benefiting
the poor or vulnerable groups, nor does it automatically provide for income/livelihood losses, resettlement
or rehabilitation expenses. Though, often this is done; it is the responsibility of affected persons to apply for
benefits, rather than the responsibility of the project proponent to automatically provide them.
2.2.2 The Land Acquisition Act (LAA) 1894
The Land Acquisition Act (LAA) of 1894 is the key legislation that has direct relevance to resettlement and
compensation in Pakistan. Each province has its own interpretation of the LAA, and some provinces have
also passed provincial legislations. The LAA and its implementation rules require that before
implementation of any development project the privately owned land and crops are compensated to titled
landowners and/or registered tenants/users etc.
Based on the LAA, only legal owners and tenants registered with the Land Revenue Department or those
possessing formal lease agreements are eligible for compensation. Under this Act, users of the Rights of
Way (RoW) are not considered "affected persons" and thus not entitled to any mitigating measure,
compensation, or livelihood support. Also, there is no legal obligation to provide compensation to title-less
land users, unregistered tenants or encroachers for rehabilitation. However, after independence and with
the passage of time various deviations to LAA have been practiced. Projects such as Ghazi Barotha and
National Highways Authority road construction have awarded compensation to unregistered tenants and
other forms of AP (Share-croppers, squatters).
2. Policy, Legal and Administrative Framework
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
10
Sindh Water Sector Improvement Project
The exceptions to the rule can be explained by the fact that the law is not rigid and is broadly interpreted
depending on operational requirements, local needs, and socio-economic circumstances.
Under this Act, only legal owners and tenants officially registered with the Land Revenue Department or
possessing formal lease agreements are considered "eligible" for land compensation.
The key sections of the LAA, 1894 are briefly described below.
Section 3
According to Section 3 of the Act, Land is defined as including benefits to arise out of land, and things
attached to the earth or permanently fastened to anything attached to the earth
Section 4
Section 4 of the Act requires that a preliminary notification is published in the official Gazette as well as at
convenient places in the locality of the Land to be acquired. This notice allows an officer appointed by the
Government of Sindh and his/her workmen to enter on to the land for the purposes of surveys, soil tests,
setting out, with the exception of occupied houses unless with consent or following at least seven day’s written notice of intention.
Requirements for publication of the notification under the Act are mandatory, and the acquisition
proceedings would stand invalid if requirements of this section are not fully satisfied. The purpose of
Section 4 is to enable preliminary investigations/land survey with a view to determine the suitability of the
Land.
Section 5
If the Land notified under Section 4 is found to be suitable, or if no such survey is required at any time, a
notice is issued under Section 5 of the Act. As for section 4 the notification is published in the official
Gazette as well as at convenient places at or near the Land to be acquired. The notice must state the
location of the Land, purpose of acquisition, area and, where a plan has been prepared, the location where
such a plan is available for inspection.
Under section 5, the owners of Land, or those affected or likely to be affected, may raise objections in
writing to the Collector within 30 days of notification under section 5. The Collector shall give the objector
an opportunity to be heard, and after making further enquiry if any, shall submit the case to the
Commissioner together with proceedings held by the Collector containing his/her recommendations. The
decision of the Commissioner is considered final.
Section 6
Under section 6, a Secretary to the Commissioner (or other authorised official) may declare that the land is
required for public purpose after considering any objections, if any, under section 5. The declaration shall
be published in the official Gazette stating the location of the Land, purpose of acquisition, area (size) and,
where a plan has been prepared, the location where such a plan is available for inspection. The area (size)
declared under section 6 supersedes the area notified under section 4 or 5, where the area declared under
section 6 is lesser.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
11
Sindh Water Sector Improvement Project
Section 7
Following declaration under section 6, the Collector shall be directed by the Commissioner to take order for
the acquisition of the Land.
Section 8
Under section 8 of the Act the Collector shall mark out the Land to be acquired (if not completed under
section 4) and prepare a plan showing the measurements of the area (if not previously prepared).
Section 9
Under section 9, the Collector places a notification on or near the Land to be acquired stating the intention
to acquire the Land and that claims to compensation should be made to the Collector. The notice shall
require those with interests in the Land to appear personally or by agent before the Collector at a stated
time and place to state the amount and particulars of their claims to compensation and any objections to
measurements made under section 8. The Collector may require such statements in writing.
Under section 9, the Collector shall also serve notice to the Irrigation Department of an enquiry under
section 11 of the Act for the determination of claims and objections. The Irrigation Department shall be
required to depute an authorised representative to attend the enquiry.
All notices under section 9 must be made not less than 15 days prior to the date of an enquiry under
section 11.
Section 10
Under section 10, interested people are required to deliver the names of any other person possessing an
interest in the Land (including co-proprietor, sub-proprietor, mortgagee or tenant), the nature of such
interest and details of any rents and profits received or due in the preceding three years. The date by which
the information may be submitted to the Collector must be no earlier than 15 days of notice under section
9.
Section 11
Under section 11, the Collector shall hold an enquiry into objections received between the date of
notification under section 9 and the date of the enquiry. The date of the enquiry must be no earlier than 15
days following the notification under section 9. Objections may relate to measurements made under section
8, the value of the land, the date of notification under section 4 or the interests of those claiming
compensation.
The Collector shall, through this enquiry, determine the true area of the land, the compensation due and to
whom it is due and make the award.
Section 12
The determination of the Collector is considered final when filed in his office. The Collector shall
immediately give notice of the award to interested people and he may take possession of the Land which
shall thereupon vest absolutely in the government/ or acquiring department.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
12
Sindh Water Sector Improvement Project
Sections 13 and 14
Sections 13 and 14 give the Collector power to adjourn enquiries, call witnesses and summon evidence.
Section 15, 23 and 24
Sections 15, 23 and 24 define the methodology for determination of compensation to be awarded. Section
23 requires the following to be considered:
Market value of the Land at date of publication of section 4 plus 15%. Market value shall be determined
taking into account transfer of land similarly situated and in similar use. Consideration of potential value
of the Land if put to a different use shall only be considered if it can be shown that land similarly situated
and previously in similar use has, before the date of notification under section 4, been transferred to
such a use.
Damage to standing crops or trees
Damage caused by severing Land to be acquired from the person’s other land Damage to other property or earnings caused during acquisition
Reasonable expenses due if the affected person is required to change residence as a result of the
acquisition
Any bona fide diminution of profits of the Land between date of declaration under section 6 and date of
possession by Collector
Under section 24, the following shall not be taken into consideration when determining compensation:
The degree of urgency of the acquisition
Disinclination of affected person to part with Land acquired
Any improvements to the Land made following notification under section 4
Any increase to the value of the Land¸ or other land owned by an affected person likely to occur from
the use to which the acquire land will be put following acquisition.
Section 17
In emergency cases the Collector, when directed by the Commissioner, may make notification under
section 9 of any waste or arable land any time following notification under section 4. The Collector may
take possession following 15 days of notice under section 9 of the Act, from which time the land shall rest
with the Government. In such a case the value of compensation may be made by the Collector considering
those issues usually exempt from valuation under section 24 of the Act.
Under section 17, sections 5, 6 and 11 (relevant to objections and enquiries) need not be applied in an
emergency situation.
In the case where, following an emergency, immediate possession of Land is required for the purposes of
maintaining traffic over a public road, the above process may be applied without the requirement to wait 15
days following notice under section 9 of the Act. In other words, the Collector (with approval from the
Commissioner) may take possession of the required Land immediately following notification under section
9.
Land Acquisition under the Proposed Sub-project
The execution of the sub-project shall require the permanent acquisition of approximately 9.925 acres of
privately owned land at RD 63 IP/NIP and RD 125 IP side of Ghotki Feeder canal. The cost of the
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
13
Sindh Water Sector Improvement Project
permanent land acquisition will be borne by the project proponent. Temporary land acquisition will be
required for borrow material - the contractor will be responsible for temporary land acquisition. The
contractor shall pay a monthly rent as per market value (or any other value as agreed with the land owner
or registered tenant) to the land owner or registered tenant wherever borrow areas are established outside
the RoW. The contractor shall repair or replace any damaged assets on private land at his own cost or else
compensate the owner for the damage or loss.
2.3 Lender Policy
2.3.1 World Bank’s Involuntary Resettlement Policy (OP 4.12)
2.3.1.1 General
The World Bank lays down policy guidance for the projects and programs that affect the human population
to ensure that local residing people benefit from development projects and adverse effects on human
environment caused by the project can be avoided or mitigated. Under the above policy displaced persons
of development projects are entitled to compensation regarding loss of land, structural assets, access to
assets, crops, livelihood activities etc. A social assessment has been carried out to evaluate the project’s potential positive and negative/adverse effects on the people and to examine project alternatives where
adverse effects can be minimized.
The World Bank's experience indicates that involuntary resettlement under development projects, if
unmitigated, often gives rise to severe economic, social, and environmental risks: production systems are
dismantled; people face impoverishment when their productive assets or income sources are lost; people
are relocated to environments where their productive skills may be less applicable and the competition for
resources greater; community institutions and social networks are weakened; kin groups are dispersed;
and cultural identity, traditional authority, and the potential for mutual help are diminished or lost. This
policy includes safeguards to address and mitigate these impoverishment risks.
The overall objectives of the Policy are given below:
Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative
project designs.
Where it is not feasible to avoid resettlement, resettlement activities should be conceived and executed
as sustainable development programs, providing sufficient investment resources to enable the persons
displaced by the project to share in project benefits. Displaced persons should be meaningfully
consulted and should have opportunities to participate in planning and implementing resettlement
programs.
Displaced persons should be assisted in their efforts to improve their livelihoods and standards of living
or at least to restore them, in real terms, to pre-displacement levels or to levels prevailing prior to the
beginning of project implementation, whichever is higher.
The Policy defines the requirement of preparing a resettlement plan or a resettlement policy framework,
in order to address the involuntary resettlement.
For the proposed sub-project, livelihood of some affected persons may be affected due to their dislocation
from their existing location.
In view of the above, the OP 4.12 will be triggered; this RAP has been developed in accordance with this
OP.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
14
Sindh Water Sector Improvement Project
This policy covers direct economic and social impacts from Bank-assisted investment projects that are
caused by:
The involuntary taking of land resulting in
Relocation or loss of shelter;
Loss of assets or access to assets; or
Loss of income sources or means of livelihood, whether or not the PAP must move to another
location.
The involuntary restrictions of access to legally designated parks and protected areas resulting in
adverse impacts on the livelihoods of the displaced persons.
According to the World Bank policy, the following measures would be adopted regarding PAPs;
Inform about options and rights pertaining to resettlement matters
Consulted on, offered choices among, and provided with technically and economically feasible
resettlement alternatives
Provide prompt and effective compensation at full replacement cost for losses of assets attributable
directly to the sub-project
Provide assistance such as moving allowances during relocation; and offer support after displacement,
for a transition period, based on a reasonable estimate of the time likely to be needed to restore their
livelihood and standards of living
Provide with development assistance
Counselling in respect of credit facilities, trainings, or job opportunities; and
Measures to assist the displaced persons in their efforts to improve their livelihoods, or at least to
restore, in real terms.
2.3.1.2 Criteria for Eligibility
Under the WB OP, the PAPs may be classified in one of the following three groups.
1. Those who have formal legal right of land (including customary and traditional rights) recognized under
the laws of the country
2. Those who do not have formal legal rights of land at the time of census begins but have a claim to such
land or assets provided that such claims are recognized under the laws of the country or become
recognized through a process identified in a RAP7.
3. Those who have no recognized legal right or claim of the land they are occupying
Persons covered under criteria 1 and 2 above are provided compensation for the land they lose and
offered alternative resettlement sites, while those under criteria 3 are offered resettlement assistance in lieu
of compensation for the land they occupy. All PAPs meeting any of the above criteria are provided
compensation for any lost assets as well as additional resettlement assistance as required by the WB OP
4.12.
All affected persons losing assets, infrastructure and livelihood as a result of the sub-project are eligible to
receive compensation and livelihood assistance irrespective of ownership of title to the land.
_________________________ 7 No such process has been identified for this sub-project in this RAP.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
15
Sindh Water Sector Improvement Project
2.3.1.3 Disclosure
In accordance with OP 4.12, the Government of Sindh shall provide the World Bank with a copy of this
RAP. Following clearance by the World Bank, this RAP shall be made publically available by the World
Bank and be published on the WSIP website (www.wsip.com.pk). The RAP shall also be translated by the
project proponent (SIDA) into Sindhi and Urdu, and be made publically and freely available at the following
locations:
SIDA office at Hyderabad,
AWB office at Ghotki City,
Ghotki Feeder Canal, RD 43 – Regulator’s operation room Ghotki Feeder Canal, RD 63 – Regulator’s operation room
Ghotki Feeder Canal, RD 125 – Regulator’s operation room
The latter three locations are all situated within the sub-project area, and shall therefore be easily
accessible to PAPs.
2.3.2 World Bank Policy on Access to Information
The World Bank allows access to any information in its possession (with exceptions, such as where such
information could cause harm to specific parties or interests). The policy is based on the following five
principles:
Maximizing access to information;
Setting out a clear list of exceptions;
Safeguarding the deliberative process;
Providing clear procedures for making information available; and
Recognizing requesters’ right to an appeals process.
Exceptions to access to information include:
Personal information (of Bank staff)
Communications within and between Governors and/or Executive Directors’ Offices Proceedings of the World Bank Ethics Committee
Information subject to Attorney-Client Privilege
Information which may compromise the safety and security of individuals, the environment and assets
and documents belonging to the World Bank or its staff
Information restricted under separate disclosure regimes or investigative information
Information provided to the World Bank in confidence
World Bank corporate administrative matters
World Bank deliberative information
Some financial information
All other information held by the World Bank is to be made available in accordance with the World Bank
Access to Information Policy8 . Where access to information is denied, the requester may file an appeal
where the World Bank has violated this policy, or there is a public interest case to override the exceptions
to the policy.
_________________________ 8 Available at https://policies.worldbank.org/sitepages%2FExtranetAppPage.aspx?url=ExtranetPreviewPage&docid=3797
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
16
Sindh Water Sector Improvement Project
2.4 Review of Government and World Bank Resettlement Policies
2.4.1 Comparison of Policies
The World Bank Operational policy explicitly makes adequate provision for the affected persons who are
either displaced or suffer losses, as a result of development project to be catered for. Livelihoods of
persons to be affected must be prevented but in cases where it is inevitable, minimal displacements should
occur. In such cases where displacement is unavoidable, compensation should be paid to the PAPs to help
them to restore their social and economic livelihoods.
Land Acquisition Act,1894 makes provision for compensation to be paid to only affected persons having
suffered any loss and can produce any form of title that is legal in form of occupancy, ownership or legally
binding tenancy agreement to the land in question. However, the World Bank policy accepts all forms of
losses without exception to be catered for.
The World Bank policy requires that the persons affected by any development project be assisted during
their transition period in the resettlement site and efforts made to restore their livelihoods whereas the Land
Acquisition Act, 1894 is silent on that. The table given below highlights some comparison between the
Land Acquisition Act, 1894 and the World Bank Policy on Involuntary resettlement.
Table 2.1: Comparison of Pakistan’s LAA and WB Resettlement Policy
Pakistan’s Land Acquisition Act, 1894 WB Involuntary Resettlement Policy
Land compensation only for titled landowners or holders of customary rights.
Lack of title should not be a bar to compensation and/or rehabilitation.
Crop losses compensation provided only to registered landowners and sharecrop/lease tenants.
Crop losses compensation provided to landowners and sharecrop/lease tenants whether registered or not
Land valuation based on the market value of the land at date of publication of section 4 notification (refer to section 23 of the LAA)
Land valuation based on current market rate/replacement value
Land Acquisition Collector (LAC) is the only pre-litigation final authority to decide disputes and address complaints regarding quantification and assessment of compensation for the affected assets
Disputes, complaints and grievances are resolved informally through community participation in the Grievance Redress Committees (GRC), Local governments, and NGO and/or local-level Community Based Organizations (CBOs)
The decisions regarding land acquisition and compensations to be paid are published in the official Gazette and notified in convenient places so that the people affected get aware of the same
Information related to quantification and costing of land, structures and other assets, entitlements, and amounts of compensation and financial assistance are to be disclosed to the affected persons prior to taking possession of their assets.
No provision for income/livelihood rehabilitation measure, allowances for severely affected persons, or resettlement expenses
The WB policy requires rehabilitation for income/livelihood, for severe losses, and for expenses incurred by the PAPs during the relocation process.
2.4.2 Remedial Measures to Bridge the Gap
In principle, Pakistan’s Law and World Bank Policy adhere not only to the objective of compensation for
affected families, but also to the objective of rehabilitation. However, Pakistan’s law is unclear on how rehabilitation is to be achieved and in practice the provision of rehabilitation is left to ad-hoc arrangements
taken by the local governments and the specific project proponents. To clarify these issues and reconcile
eventual gaps between Pakistan’s Law and WB Policy, this RAP for the rehabilitation of the Ghotki Canal
sub-project has been prepared which ensures the following:
Compensation for any privately owned land lost as a result of the works
Compensation for lost assets regardless of rights to land on which they are sited
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
17
Sindh Water Sector Improvement Project
Valuation of assets and land at the prevailing market rate
Assistance in relocation for any PAP, regardless of legal entitlement to the land they occupy, in the form
of a cash transport allowance
Provision of additional allowance for those who may suffer commercial losses'
This RAP is prepared in compliance with World Bank Operational Policy and Bank Policy 4.12 as well as
national laws.
2.5 WSIP Social Impact Management Framework
The section of Social Impact Management Framework (SIMF) relevant to preparation of this RAP is
summarised here. The SIMF was prepared for WSIP by the Government of Sindh and cleared by the World
Bank in 2006. This RAP has been prepared in accordance with this SIMF.
The SIMF provides the overall guidance on process and procedure required for addressing social impacts
caused by the sub-projects and for social screening and preparation and implementation of RAPs, and/or
other mitigation plans as necessary. The SIMF requires that RAPs describe distinctly and clearly how the
sub-project would improve, or at least restore economic livelihoods of Project Affected Persons through
adequate asset compensation and economic rehabilitation measures.
The SIMF requires that RAPs shall be guided by the following policy objectives:
Land acquisition is an integral part of the project design, and should be dealt with from the earliest
stages of project preparation.
Both involuntary resettlement and the negative impacts on people by acquisition of assets should be
avoided or minimised whenever feasible, exploring all viable alternative project designs.
Persons to be affected should have their former living standards and income earning capacity improved
or at least restored. In the case of displacement, they should be provided with adequate support during
transition period.
Project stakeholders, including PAPs are consulted and given the opportunity to participate, as
practicable, in the design, implementation, and operation of the project.
Particular attention will be paid to the protection of marginalised, disadvantaged and vulnerable groups,
including women and children and promoting and providing, wherever possible, opportunities for such
groups to take advantage of the investment.
The SIMF also provides for a low income allowance to be provided to all PAPs without land title and living
below the poverty line, in case of loss of residential, commercial, industrial and institutional land.
2.6 Entitlement Matrix
The criteria for assessing entitlements for compensation and rehabilitation assistance to different
categories of PAPs is defined within the entitlement matrix (Table 2.2) and has been followed during the
preparation of this RAP. This version of the entitlement matrix is based on the entitlement matrix given
within the SIMF (November 2006), but with updates to reflect implementation of contracts WSIP/B1/NC/01
and WSIP/B2/NC/02, their associated RAPs, and findings of consultations with PAPs.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
18
Sindh Water Sector Improvement Project
Table 2.2: Entitlement Matrix
No; Type of Loss Application Definition of Entitled Person Entitlement Policy
1 Loss of Land (Agricultural)
Partial but permanent loss of land and the remaining land farmed is economically viable and at least equal to or more than 0.5 acres (marginal impact on household income and living standard)
Legal owner with valid title or customary or usufruct rights
PAPs will be entitled to:
Compensation as per Pakistan Land Acquisition Act
Tenant, leaser holder and sharecropper PAPs will be entitled to:
Cash compensation equivalent to market value of gross harvest for one year production or for the remaining period of tenancy/lease, whichever is greater. Compensation to be reduced to mirror any share cropping agreements in place between owner and tenant (typically 50%); AND
Cash compensation equivalent to market value of standing crops that could not be harvested. Compensation to be reduced to mirror any share cropping agreements in place between owner and tenant (typically 50%)
PAPs without valid title PAPs will be entitled to the following:
Cash compensation equivalent to market value of standing crops that could not be harvested.
Permanent loss of entire land or where partial loss but the remaining land is less than 0.5 acre or is rendered economically unviable.
(Severe impact on household income and living standards).
Legal owner with valid title or customary or usufruct rights.
PAPs will be entitled to:
Equivalent area of land with equivalent productive potential at location acceptable to PAP, OR
Compensation as per Pakistan Land Acquisition Act
Tenant, lease holder and share cropper PAPs will be entitled to:
Cash compensation equivalent to market value of gross harvest for one year production or for the remaining period of tenancy/lease, whichever is greater. Compensation to be reduced to mirror any share cropping agreements in place between owner and tenant (typically 50%); AND
Cash compensation equivalent to market value of standing crops that could not be harvested. Compensation to be reduced to mirror any share cropping agreements in place between owner and tenant (typically 50%)
PAPs without valid title PAPs will be entitled to the following:
Cash compensation equivalent to market value of standing crops that could not be harvested
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
19
Sindh Water Sector Improvement Project
No; Type of Loss Application Definition of Entitled Person Entitlement Policy
Temporary loss of land Legal owner with valid title or customary or usufruct rights.
PAPs will be entitled to:
Monthly rent at market value
Tenant, lease holder and share cropper PAPs will be entitled to:
Market value of gross harvest for production over period of temporary loss (rounded up to the nearest year). Compensation to be reduced to mirror any share cropping agreements in place between owner and tenant (typically 50%)
PAPs without valid title PAPs will be entitled to the following:
Cash compensation equivalent to market value of standing crops that could not be harvested
2 Loss of Land (Residential, commercial, industrial or institutional land)
Partial loss of residential, commercial, industrial or institutional land with remaining land sufficient to reorganize
PAPs with valid title or customary and usufruct rights
PAPs will be entitled to the following;
Cash compensation for affected portion of the land at replacement value
PAPs such as tenants and leaseholders
PAPs will be entitled to the following;
Reimbursement for loss of income for the un-expired lease period
PAPs without valid title See below
Loss of residential, commercial, industrial or institutional land without sufficient remaining land. PAPs will be required to relocate.
PAPs with valid title or customary and usufruct rights
PAPs will be entitled to the following;
An equivalent area of land of similar characteristics and access to faculties in an acceptable location, OR
Compensation as per Pakistan Land Acquisition Act
PAPs such as tenants and leaseholders
PAPs will be entitled to the following;
An equivalent area of leased land for un-expired lease period, OR
Reimbursement for un-expired lease period
PAPs without valid title PAPs will be entitled to the following;
Permission to reside on alternative Government owned site without transfer of title
PAPs living below the poverty line PAPs will be entitled to the following:
Low income allowance equal to two months household income, or two months minimum wage (whichever is greater)
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
20
Sindh Water Sector Improvement Project
No; Type of Loss Application Definition of Entitled Person Entitlement Policy
3 Loss of Privately Owned Structures (Residential, commercial, industrial or agricultural)
Partial loss of structure and the remaining structure viable for continued use by current occupier
Legal owner of affected structure with valid or customary or usufruct rights
PAPs will be entitled to the following:
Cash compensation for affected part of the structure at replacement value; AND
Allowance to cover repair of the remaining structure.
Owner of affected structures without valid title to the land (squatter/encroacher)
PAPs will be entitled to the following:
Cash compensation for affected part of the structure at replacement value; AND
Allowance to cover repair of the remaining structure
Entire loss of structures or where only partial impact, but the remaining structure is rendered unviable for continued use.
Owner of structure (regardless of ownership of title to land on which structure is situated)
PAPs will be entitled to the following:
Transport allowance for shifting to new location; AND
Cash compensation for entire structure at replacement value; OR
Structure of equivalent standard in acceptable location
Tenant / leaseholder in the affected structure
PAPs will be entitled to the following:
Transport allowance for shifting to new location; AND
Transition allowance equivalent to three months’ rent
4 Loss of Structures (Community or institutional)
Partial loss of structure and the remaining structure viable for continued use by current occupier
Community or institution Repair under the civil works contract
Entire loss of structures or where only partial impact, but the remaining structure is rendered unviable for continued use.
Community or institution Replacement under the civil works contract
5 Loss of income (trade/ livelihood/ occupation or business incomes)
Temporary or permanent loss of commercial income Impacted business owner PAPs will be entitled to the following:
Livelihood allowance equivalent to three months household income, or three months minimum wage (whichever is greater)
Temporary or permanent loss of agricultural/commercial/institutional wages
Impacted employee or labourer PAPs will be entitled to the following:
Livelihood allowance equivalent to three months household income, or three months minimum wage (whichever is greater)
6 Loss of access to common resource and facilities
Loss of access to rural common property resources and urban civic amenities
Communities/ households PAPs will be entitled to the following:
Replacement of common property resources/
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
21
Sindh Water Sector Improvement Project
No; Type of Loss Application Definition of Entitled Person Entitlement Policy
amenities; OR
Access to equivalent amenities/ services
7 Loss of trees Affected trees. Owner of trees PAPs will be entitled to cash compensation equivalent to market value on the basis of type, age and productive value.
8 Loss of public infrastructure
Infrastructure (electric water supply, sewerage & telephone lines; public health centre; public water tanks)
Relevant agencies. Compensation in cash at replacement cost to respective agencies.
9 Losses to host Communities.
Affected amenities and services Host community Restore losses as a result of resettlement for amenities / services equivalent to the provided to PAPs
10 Temporary Losses Affected structures or other fixed assets Affected PAPs In cash, on the basis of replacement cost of material and labour without deduction for depreciation or salvageable materials for the damages during the period of temporary possession.
Severely affected structures
Affected PAPs made to shift temporarily from their present location
Entitlement will be in terms of rent allowance to cover the cost of alternate accommodation for the period of temporary displacement.
11 Loss of Land
(unused)
Partial but permanent loss of land Legal owner with valid title or customary or usufruct rights
PAPs will be entitled to:
Compensation as per Pakistan Land Acquisition Act
Permanent loss of entire land or where partial loss but the remaining land is less than 0.5 acre
Legal owner with valid title or customary or usufruct rights
PAPs will be entitled to:
Compensation as per Pakistan Land Acquisition Act
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
22
Sindh Water Sector Improvement Project
Please refer to Chapter 1 for an overview of WSIP.
3.1 General Institutional Arrangements, Roles & Responsibilities
An organogram for institutional arrangements for sub-project implementation is shown in the following
figure. The roles and responsibilities of each party are detailed in the following sections.
Figure 3.1: Institutional Setup for Project Implementation
3.1.1 The Sindh Irrigation and Drainage Authority (SIDA)
3.1.1.1 General
The Sindh Irrigation and Drainage Authority (SIDA) is the project proponent, and therefore the sub-project
proponent. SIDA has a Board of Management chaired by the Minister of the Irrigation and Power
Department (IPD) Government of Sindh.
SIDA is responsible for providing necessary support for the implementation of all WSIP components,
including; maintaining consolidated project accounts, preparing disbursement applications and operation of
the Designated Account and transfer of funds to other implementing agencies, and contributing to the
project’s overall management information system. SIDA is also responsible for procurement of major contracts under WSIP, including Contract WSIP/B1/GF/01. SIDA’s Board meet quarterly to address project
issues and make key decisions regarding investments as well as institutional strengthening. It will work
closely with IPD in facilitating operation of the canal system during sub-project implementation.
SIDA shall act as the Employer, under the contract for WSIP/B1/GF/01.
3.1.1.2 Environmental Monitoring Unit (SIDA-EMU)
The responsibility for social and environmental management and monitoring will rest with the EMU
established under SIDA. EMU are responsible for the environmental and social assessment, assisting in
designing investments in a participatory way incorporating social and environmental issues, and monitoring
3. Description of the Sub-Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
23
Sindh Water Sector Improvement Project
the long term operational as well as construction phase impact of the project and major investments in the
Province. These responsibilities extend to all investments made under WSIP, including this sub-project.
The EMU may seek necessary assistance from the social and environmental team of PIC in relation to
works under component B1 and B2 of WSIP.
3.1.2 Project Coordination and Monitoring Unit (PCMU)
Project Coordination and Monitoring Unit (PCMU), established under the Planning and Development
Department, Government of Sindh, monitor and coordinate all project implementation activities under
WSIP, including this sub-project. It is responsible for carrying out project monitoring and evaluation studies
and overall supervision of the environmental and social plans for WSIP (including this sub-project). PCMU
shall engage a team of independent consultants (known as the Monitoring and Evaluation Consultants) to
assist them in monitoring and evaluation.
3.1.3 Monitoring and Evaluation Consultants (M&EC)
M&EC assist PCMU in supervision and monitoring of the overall project as well as sub-projects (including
Contract WSIP/B1/GF/01) in terms of environmental management and social plans. They provide
continuous feedback to the Government of Sindh, Project Steering Committee (via PCMU) and
implementing agencies on the project’s performance and impact of its various components, so that corrective actions can be taken in a timely manner.
3.1.4 Project Management Consultants/Procurement Agent (PMC/A)
The Project Management Consultants/Agent (PMCA) oversee the procurement of consultancy services,
works and goods to ensure these are in accordance with the World Bank’s guidelines. PMC/A also
oversees recruitment of project staff from the market place in a transparent manner with involvement of
project implementing partners and Transparency International Pakistan (TIP). The team has a mandate to
oversee the work performance of project staff and the consultants in carrying out their responsibilities,
examining the functions of consulting services and the payments made to the consultants.
3.1.5 Ghotki Area Water Board
Ghotki AWB is responsible for the operation and maintenance of Ghotki Feeder Canal. The AWB shall
hand-over operational responsibility of Ghotki Feeder within the sub-project area to the contractor who
shall implement the works under this sub-project. These areas of the canal shall be handed over to the
contractor for the entire duration of the works. The AWB is required to complete any permanent land
acquisition prior to the commencement of works under this sub-project, and also assist the contractor in the
completion of any temporary land acquisition that the contractor finds appropriate for the execution of the
works.
Following completion of the works, the contractor shall hand over control of the canal within the sub-project
area back to the Ghotki AWB who shall maintain responsibility for operation and maintenance for the
operational phase.
3.1.6 The Project Implementation Consultants (PIC)
The association of Mott MacDonald Ltd and MM Pakistan (Pvt) Ltd was appointed in 2009 as the Project
Implementation Consultants (PIC) for WSIP phase 1. PIC were appointed to assist SIDA in the
implementation of WSIP, including undertaking the detailed designs, environmental assessment,
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
24
Sindh Water Sector Improvement Project
environmental management plans, resettlement actions plans, procurement of works and construction
supervision for the rehabilitation works proposed under component B.
PIC have completed the detailed designs for this sub-project and are responsible for the preparation of this
RAP as well as the EIA/EMP. PIC shall assist SIDA in the prequalification and procurement of a contractor
to complete the works for this sub-project under Contract WSIP/B1/GF/01. Following contract award, PIC
shall act as the ‘Engineer’ under the contract and maintain responsibility for supervision of the contract (on behalf of SIDA), including supervision of construction quality and the contractor’s compliance with the EMP, for the duration of the works.
3.1.7 The Contractor
A contractor shall be appointed by SIDA under contract WSIP/B1/GF/01 to complete the works proposed in
this sub-project.
3.2 Location of the Project
Ghotki Feeder Canal off-takes directly from the left bank of the River Indus, immediately upstream of
Guddu Barrage. Due to a poor configuration of Guddu Barrage, large volumes of sediment are supplied
into Ghotki Feeder. This sediment is deposited within the canal, especially within the first 65 RDs, and
reduces the capacity of the canal to carry the design discharge.
Table 3.1: Salient Features of Ghotki Feeder Canal
Canal Total Length (km) Design Discharge (m3/s)
Number of Offtakes
Ghotki Feeder Canal 121 267 31
The Ghotki Feeder Canal is approximately 85m (280ft) wide at its head, reducing to 11m (35ft) at the tail.
At the head of the canal (RD 0 to approximately RD 80), the canal berms have been entirely eroded and
water flows against the embankments. Further downstream, berms are present with a width of between 6m
and 9m (20ft and 30ft), but are becoming increasingly eroded as shown in the figure below. Trees and
heaps of spoil originally excavated from the canal are present on the embankments.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
25
Sindh Water Sector Improvement Project
Figure 3.2: Eroded berm on the Ghotki Canal
3.3 Right of Way
The Right of Way (RoW) is a strip of government owned land beyond the outer toe of both embankments of
the canal that runs parallel to the embankments for the entire length of the canal. The width of the RoW as
reported by the Ghotki AWB (but not confirmed officially) during field visits is given in the following table.
Table 3.2: Ghotki Feeder Canal Reported RoW
Reach (RD) Left Bank Width of RoW (ft) – measured from canal centreline
Left Bank Width of RoW (ft) – measured from canal centreline
0 – 33 320 320
33 – 58 340 340
58 – 127 330 330
The RoW is illegally and heavily cultivated and inhabited by illegal settlements. The RoW is occasionally
interrupted by areas of forested area, barren land which is prone to flooding, and open water.
Beyond the RoW agriculture continues to be practiced to a large scale, with cotton, wheat, rice and sugar
cane being the dominant crops in the area. Cultivated areas are occasionally interrupted by small areas of
barren land and open water, but these are not common. More common are extensive areas of woodland.
Villages and smaller hamlets are present within the agricultural land, housing fishermen and farm labourers
who work on the agricultural land (which is generally owned by larger landlords) as well as their families.
It is noted that the majority of the Corridor of Impact (CoI) for this sub-project is within the RoW, but does
not cover the entire RoW. The CoI varies down the entire length of the canal, dependent upon the
proposed embankment section and existing cross-section design as well as the spoil disposal
requirements. See section 3.8 for measurements of the CoI.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
26
Sindh Water Sector Improvement Project
3.4 Scope of Works
The works detailed in this section constitute the proposed sub-project and are all considered within this
RAP.
The main components of the sub-project are to remove sediment from the canal and lower the bed level,
reinstate the berms, raise and strengthen the embankments as well as replace hydraulic regulating
structures and construct new road bridges.
Full details of all proposed works can be found in Volumes I and II of the ‘Design Report for Contract WSIP/B1/GF/01, Rehabilitation of Ghotki Feeder Canal.
Contract WSIP/B1/GF/01 will involve the following main engineering works:
Establishment of construction and labour camps
Establishment of borrow areas to win material for embankment works
Raising and strengthening of embankments from RD 0-125 (left bank) and RD 40-125 (right bank)
Canal remodelling (desilting and lowering of the design bed level) from RD 0 to 125
Disposal of spoil resulting from canal remodelling
Formation of the berm through the construction of killa bushing in isolated reaches from RD 0 to 125
Cutting of the berm in isolated reaches from RD 0 to 125 on the left bank
Cutting of the berm in isolated reaches from RD 40 to 125 on the right bank
Replacement of two cross regulators
Replacement of four major head regulators off-taking from Ghotki Feeder
Replacement of six minor head regulators off-taking from Ghotki Feeder
Construction of temporary canal diversions
Construction of two Village Road Bridges (VRBs)
Rehabilitation of four VRBs
Repair of existing sanctioned Direct Outlets RD: 0-127
The hydraulic structures to be replaced are detailed in the following table.
Table 3.3: Hydraulic Structures to be Demolished and Replaced – Contract WSIP/B1/GF/01
RD Structure Name
11 Head Regulator Chandia Minor
61 Head Regulator Dilwaro Minor
65 Head Regulator Mahi Wah
Head Regulator Dahar Wah
Head Regulator Sehar Wah
Head Regulator Bori Lower Minor
Head Regulator Sonan Minor
Cross Regulator
125 Head Regulator Masu Wah
Head Regulator Ranwati Minor
Head Regulator Mehro Link Minor
Cross Regulator
Construction of two VRBs is planned at the following locations:
RD 101 (to replace an existing crossing)
RD 127 (to replace an existing crossing)
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
27
Sindh Water Sector Improvement Project
Rehabilitation of the following four existing bridges is planned:
RD 17
RD 25
RD 78
RD 110
3.5 Labour Requirements
It is estimated that approximately 300 personnel shall be employed on the contract at its peak. Of these,
100 shall be skilled or semi-skilled, and shall include the following positions:
Machine operators
Engineers
Surveyors
Masons
Electricians
Mechanics
Approximately 200 unskilled labourers shall be engaged on the project, and this shall include drivers,
construction labourers, watchmen and camp staff. The contractor shall be able to source these unskilled
labourers from within the sub-project area, especially from Mureed Shakh village located on Ghotki Feeder
Canal at approximately RD 45.
In addition, approximately 30 management staff shall be engaged by the contractor. These shall be
engaged from the contractor’s home office.
3.6 Assessment of Potential Impacts
3.6.1 Scoping
Prior to field studies, a scoping exercise was carried out to identify the construction activities which have
the potential to result in direct economic or social impacts. The following table provides an assessment of
the potential impacts under contract WSIP/B1/GF/01.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
28
Sindh Water Sector Improvement Project
Table 3.4: Scoping of Potential Impacts of Contract WSIP/B1/GF/01
Component of Works Description
Loss of Shelter
Loss of Assets/Access to Assets
Loss of Income Source/ Means of Livelihood
Restriction of Access to Parks/ Protected Areas
Establishment of Construction/ Labour Camps (temporary works)
Construction camps are to be established. If established within the RoW, this has the potential to result in the loss of privately owned structures illegally constructed within the RoW. If camps are established beyond the RoW, temporary acquisition of privately owned land would be required. In either case, construction of camps has the potential to result in the loss of standing crops where these are grown within the footprint of the camp
√ √ √ -
Rehabilitation of embankments
Although the land is government owned, a number of households have built structures (shelter and commercial structures) on the embankments in which they live. Agriculture is not practiced within the footprint of the proposed embankment works
√ √ √ -
Establishment of borrow areas
The establishment of borrow areas is required to win material for the embankment works. The scoping assessment assumes some of the borrow areas shall be established in the RoW, and some in privately owned land outside the RoW. As a number of households have built structures (shelter and commercial structures) within areas of the RoW, borrow areas established within the RoW have the potential to result in loss of shelter and income. Establishment of borrow areas in agricultural land shall result in the loss of crops.
√ √ √ -
Disposal of excavated material (spoil)
As a number of households have built structures within areas of the RoW, any disposal of excavated material within the RoW has the potential to result in loss of shelter and commercial structures. As it is expected that the excavated material shall not be fertile, disposal of the material on fertile land shall result in loss of agricultural land and therefore loss of income.
√ √ √ -
Canal desilting and lowering of bed level
The footprint of this work component falls entirely within the flowing canal. Therefore, no structures or productive land shall be impacted
- - - -
Berm cutting Although the land is government owned, a number of households have built structures on the berms.
√ √ √ -
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
29
Sindh Water Sector Improvement Project
Component of Works Description
Loss of Shelter
Loss of Assets/Access to Assets
Loss of Income Source/ Means of Livelihood
Restriction of Access to Parks/ Protected Areas
Agriculture is also practiced on some reaches of the berms.
Berm formation The footprint of this work component falls entirely within the flowing canal. Therefore, no structures or productive land shall be impacted
- - - -
Establishment of haul routes to borrow areas
Temporary haulage routes may be required through private land resulting in loss of standing crops.
- - √ -
Replacement of cross-regulators
Works are to be carried out within the canal
- - - -
Replacement of offtaking head regulators and realignment of head reaches
The land is a mix of government and privately owned land, and the works have the potential to result in the loss of structures and agricultural land.
√ √ √ -
Construction of temporary canal diversions
Diversions are to be constructed within the Government owned RoW, where a number of structures (shelter and commercial structures) have been constructed and agriculture may be practiced.
√ √ √ -
Construction of new VRBs
New VRBs shall be constructed within the RoW, but may impact any structures or crops illegally established within the RoW
√ √ √ -
Realignment of roads over the new VRBs
Realignment of roads linking to the new VRBs have the potential to impact any structures or crops illegally established within the RoW, and may extend into privately owned land, for which permanent acquisition would be required
√ √ √ -
Rehabilitation of existing VRBs
All works are confined to the government owned bridges on which there is no encroachment
- - - -
3.6.2 Alternative Options for Minimizing the Impacts
Where the scoping exercise above identified areas of work which have potential direct economic or social
impacts, the design of these elements were reviewed and amended to reduce the resettlement
requirements as discussed in the sections below.
3.6.2.1 Construction and Labour Camps
The establishment of construction and labour camps was identified to have the potential to cause loss of
shelter, assets and income. In order to remove these issues, sites for these camps have been identified
which are situated on government owned land and within which no structures or farmed land are present.
Thereby the potential for social and economic impacts is removed from this component.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
30
Sindh Water Sector Improvement Project
3.6.2.2 Rehabilitation of the Embankments
There is no scope for amending the embankment design to reduce the impacts identified as strengthening
of these embankments is one of the major priorities of this project to safeguard continued flows to the
command area and prevent breaches of the canal. Due to habitation adjacent to the existing
embankments, the construction of embankments along a new alignment is unlikely to reduce the impacts,
and shall be prohibitively expensive. Such a proposal would also result in a much greater need for borrow
material and an increase in the direct social and economic impacts surrounding borrow activities. Therefore
the impacts associated with the rehabilitation of embankments are considered in this RAP.
3.6.2.3 Establishment of Borrow Areas
The establishment of borrow areas in any area which would require the removal of permanent structures
shall be prohibited, thereby removing the potential for loss of shelter or assets. In order to prevent any
impact upon privately owned land (temporary or permanent acquisition of agricultural land), deep borrow
areas shall be established within the RoW, prior to spoil disposal activities. However, the potential for the
loss of standing crops within the RoW remains and is considered in this RAP.
3.6.2.4 Spoil Disposal
Due to the need to dispose of large volumes of spoil beyond the canal embankments, the potential for both
loss of shelter/assets and impact to livelihood (resulting from loss of commercial structures and agricultural
land) has been identified. Loss of agricultural land has the potential to extend beyond government owned
land to privately owned land. In order to prevent loss of shelter and assets, PIC has completed a detailed
survey of the RoW and mapped the location of structures. Spoil disposal plans have been prepared which
propose disposal of spoil in the RoW only in areas which are uninhabited (i.e. only in areas where
structures are not present) and do not include fish farms. The plans do, however, propose disposal over
any illegally cultivated land within the RoW, so the loss of standing crops is expected. Compensation for
the loss of standing crops is included within this RAP – this is calculated based upon the RoW
measurement detailed in section 3.3 which are yet to be confirmed by the AWB. Any changes to these
measurements shall result in the need to revise the estimate of the loss of standing crops and associated
budget.
The need to dispose of spoil outside the RoW has been removed by proposing haulage of dredged
material from reaches of the canal where the volume of dredged material exceeds the available capacity
within the RoW (for example in heavily encroached areas or in reaches which have experienced significant
sedimentation) to areas where the disposal capacity of the RoW is greater than the volume of material to
be removed from the canal (for example to less inhabited areas or to reaches where little excavation is
required).
3.6.2.5 Berm Formation - Berm Cutting
The scoping exercise identified that excavation of the existing berms, which in some areas have been
illegally inhabited, may result in loss of shelter or commercial structures of those living on the berms. In
order to prevent this impact, the engineering design has been amended to remove excavation of any berm
where assets are present. However, where the berms are illegally cultivated, these shall still be excavated.
Therefore, the loss of standing crops is expected and is considered in this RAP.
3.6.2.6 Establishment of Haul Routes to Borrow Areas
The scoping exercise identified that the established of haul routes to borrow areas may result in the
requirement for temporary acquisition or privately owned agricultural land, resulting in loss of income. As
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
31
Sindh Water Sector Improvement Project
the borrow areas are to be established adjacent to the canal in the RoW, the establishment of haul routes
in privately owned land is no longer required, and therefore this impact is removed from the sub-project.
3.6.2.7 Realignment of Off-taking Canal Head Reaches
The layout of the replacement off-taking head regulators and canals has been adjusted following field visits
in order to minimise the direct social and economic impacts. However, loss of shelter, assets and standing
crops may still result from this component of the works.
3.6.2.8 Construction of Temporary Canal Diversions
The alignment of temporary canal diversions within the RoW has been chosen to minimise the direct social
and economic impacts. However, loss of shelter, assets and standing crops may still result from this
component of the works. It is noted that those structures (shelter and assets) to be lost as a result of the
establishment of canal diversions shall also be impacted by the embankment rehabilitation works.
3.6.2.9 Construction of New VRBs
The location and alignment of VRBs have been chosen to avoid any structures or crops growing in the
RoW, therefore all direct social and economic impacts associated with these works are removed.
3.6.2.10 Realignment of Roads
The alignment of the roads has been optimised following field visits to avoid any structures or crops
growing in the RoW, therefore all direct social and economic impacts associated with these works are
removed.
3.6.3 Sub-Project Activities Resulting in Direct Social and Economic Impacts
The following table provides an assessment of the final impacts resulting from works under contract
WSIP/B1/GF/01 following implementation of the design and planning mitigation measures detailed in
section 3.6.2.
Table 3.5: Assessment of Impacts following Design and Planning Mitigations
Work Component Loss of Shelter
Loss of Assets/Access to
Assets
Loss of Income Source/ Means of
Livelihood Comments on Impact
Embankment Rehabilitation
√ √ √ Loss of privately owned assets, including shelter and commercial
structures in the RoW.
Borrow Areas - - √ Loss of standing crops within the RoW
Spoil Disposal - - √ Loss of standing crops within the RoW
Berm Formation – Berm Cutting
- - √ Loss of standing crops within the RoW
Realignment of Off-taking Canal Head Reaches
√ √ √ Loss of privately owned assets, including shelter and commercial
structures in the RoW.
Permanent loss of privately owned agricultural land
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
32
Sindh Water Sector Improvement Project
Work Component Loss of Shelter
Loss of Assets/Access to
Assets
Loss of Income Source/ Means of
Livelihood Comments on Impact
Temporary Canal Diversions
√ √ √ Loss of privately owned assets, including shelter and commercial
structures in the RoW.
Loss of standing crops within the RoW
3.7 Proposed Construction Activities
The works described in the following sections include the design and planning mitigation measures detailed
in section 3.6.2.
3.7.1 Establish Construction Camps
3.7.1.1 Main Camp
The main construction camp shall be located at RD 127 of the Ghotki Feeder Canal within the RoW as
shown in the following figure.
Figure 3.3: Location Plan of Main Camp at RD125
The camp shall cover an area of approximately 10,000m2 (108,000ft
2). The majority of this area shall be for
the provision of a manufacturing and fabrication yard, and an office and dormitory shall also be provided
here.
Proposed Camp Site
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
33
Sindh Water Sector Improvement Project
3.7.1.2 Sub Camp
Due to the large project area, the Contractor shall provide a single sub camp at RD 63. This camp shall be
similar to the main camp, but on a smaller scale.
The camp shall be constructed within the Government owned RoW.
3.7.1.3 Temporary Camps
It is expected that the contractor shall establish temporary camps within the RoW at the following sites:
Chandia Minor Head Regulator (RD 11)
Dub II Minor Head Regulator (RD 107)
These camps shall consist of a single office building, generator and parking for plant and vehicles.
It is expected that movable tented camps with shelters shall be temporarily provided from RD 0 to 127
during the earthworks operations. These shelters shall not be used to accommodate labour overnight (with
the exception of security guards).
3.7.2 Rehabilitation of Embankments
The following embankments shall be rehabilitated on the Ghotki Feeder Canal:
From RD 0 to 125 on the left bank
From RD 40 to 125 on the right bank
Works include:
Raising of embankments where freeboard is insufficient (including compaction)
Widening of embankments where width is less than required to prevent seepage (including compaction)
Levelling and compaction only where freeboard is sufficient but the embankment is not currently
motorable
Detailed works are as follows:
Table 3.6: Proposed works for reconstruction of embankments
Left Bank Right Bank
RD Proposed Works RD Proposed Works
0 to 8 Raising & widening 0 to 40 No works
8 to 12 Levelling & compaction 40 to 44 Raising & widening
12 to 18 Raising & widening 44 to 75 Levelling & compaction
18 to 72 Levelling & compaction 75 to 118 Raising & widening
72 to 125 Raising & widening 118 to 125 Levelling & compaction
A canal cross-section showing embankment raising works is provided in the following figure.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
34
Sindh Water Sector Improvement Project
Figure 3.4: Typical Canal Cross-section showing Embankment Raising Works
Prior to filling works for these embankments, the top 0.15m (six inches) of material shall be removed from
the footprint of the embankments and disposed of. Vegetation and all trees shall be cleared from this area.
3.7.3 Borrow Pits
379,275 m³ (13,394,000 ft³) of material will be required to from embankments. 361,680 m³ (12,779,000 ft³)
of material will be taken from borrow areas and 17,414 m³ (615,000 ft³) from the reuse of existing spoils
situated on adjacent to the existing embankments.
Deep borrow areas shall be established within the Government owned RoW land prior to spoil disposal
activities in these areas. In order to reduce haulage costs, and the disturbance caused by haulage
operation, it is preferable to establish borrow areas close to the point at which the material is required.
However, as the sub-project area immediately adjacent to the canal from RD 63 to RD125 is flooded during
the monsoon season and as embankment works shall continue during this time, haulage from borrow
areas established within the RoW but beyond the flooded area may be required (dependent upon the
contractor’s programme).
The borrow areas shall be established within the cultivated lands which are commonly found within the
RoW of the canal. Normally, it would be preferable to identify barren land suitable for the establishment of
borrow areas in order to reduce the impact to cultivated land and farms. However in the case of Ghotki this
is not possible as the area (both within and beyond the RoW) is very heavily farmed and insufficient barren
land is available.
3.7.4 Canal Remodelling
Canal remodelling shall be completed from RD 0 to 125. The Works shall include excavation of silt from the
canal bed and lowering of the bed level. On average, approximately 1.2m (4ft) depth of material shall be
removed from the canal bed. The majority of the excavation shall be from RD 0 to 63 where 1,982,179m3
(70,000,000 ft3) silt will be removed, whereas from RD 63 to 125 only 934,455 m
3 (33,000,000 ft
3) will be
removed.
In total 2,916,635 m3 (103,000,000 ft
3) of material from canal bed will be removed.
3.7.5 Berm Formation
The following two types of works will be implemented within the canal berm from RD 0 to 125 on the left
bank and RD 40 to 125 on the right bank.
3.7.5.1 Berm Cutting
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
35
Sindh Water Sector Improvement Project
Where the existing level is higher than the design berm level, cutting to form the berm may be proposed, as shown in the following figure.
Figure 3.5: Berm Cutting
All berm cutting is provisional. The berm shall only be cut where there are no structures located on the
berm. A maximum of 254,851 m3
(9,000,000 ft3) shall be cut from the berms (provisional). Where
settlements are present on the berms, the berm shall not be cut.
3.7.5.2 Berm Formation
Where the existing level is lower than the design berm level, killa bushing is proposed on the canal edges,
as shown below.
Figure 3.6: Berm Formation
3.7.6 Spoil Disposal
2,916,635m³ (103,000,000 ft³) of spoil (excavated from the canal bed) shall be disposed beyond the
IP/NIP. Up to an additional 254,851 m³ (9,000,000 ft³) of spoil excavated from the berms shall also be
disposed of beyond the IP/NIP – this value to dependent upon the quantity of provisional cut to be
undertaken.
It is proposed that this spoil shall be disposed of only within the Government owned Right of Way (RoW).
The removal of privately owned structures or clearance of orchards from the RoW shall be prohibited for
the purpose of spoil disposal. Proposed spoil disposal areas are shown in Volume II of the RAP.
The assessment of spoil disposal areas within the RoW is based on the measurements of the RoW which
were reported in the field.
3.7.7 Village Road Bridges (VRBs)
Two new bridges will be constructed at:
RD 101 (to replace existing VRB)
RD 125 (to replace VRB currently over existing cross-regulator)
Provisional Berm Cutting
Killa bushing
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
36
Sindh Water Sector Improvement Project
Four bridges will be rehabilitated at:
RD 17
RD 25
RD 78
RD 110
3.7.8 Hydraulic Structures
PIC completed a condition assessment of hydraulic structures on Ghotki Feeder Canal and found the
majority of the structures to be in a poor condition, both structurally and hydro-mechanically, many being
aged brick built structures.
A total of two cross regulators, 4 head regulators and 6 minor head regulators shall be constructed on the
Ghotki Feeder Canal.
Permanent land acquisition will be required for the replacement of regulating complexes and realignment of
offtaking canals at 63+000 and RD 125+000 of Ghotki Feeder Canal.
All cross-regulators shall be constructed within the current alignment of the canal, and temporary diversion
channels shall be constructed to divert the canals around the structures during construction to provide a
dry area for construction, as shown for the cross-regulator at RD 125 in the following figure.
Figure 3.7: Layout for Replacement of Head and Cross-Regulators at RD125
As all structures are to replace existing structures, there will be no major changes to water levels such that
may be associated with the construction of a new weir where previously one did not exist.
All hydraulic structures from RD 0 to 127 are to be replaced except the following to which no works are
proposed:
Bori Upper Minor Head Regulator
Gohram Minor Head Regulator
Proposed
Temporary
Diversion
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
37
Sindh Water Sector Improvement Project
3.7.9 Works Schedule
A summary of the works schedule for Contract WSIP/B1/GF/01 is given in the following table. Works are
scheduled to be completed over a period of 24 months.
Table 3.7: Works Schedule – Summary for Contract WSIP/B1/GF/01
Activity Start (month/year) End (month/year)
Mobilisation (personnel, materials and equipment)
01/2016 02/2016
Temporary Works 02/2016 05/2016
Canal remodelling and embankment works 05/2016 07/2016
Construction of hydraulic structures at RD63
07/2016 07/2017
Construction of hydraulic structures at RD 125
07/2017 12/2017
The length of Contract WSIP/B1/GF/01 is estimated to span 24 months, scheduled in order to make use of
two closure periods during which the earthworks may be completed. The final programme shall be
confirmed by the contractor.
3.8 Corridor of Impact (CoI)
The CoI is dealt with in this RAP as separate areas as follows:
3.8.1.1 CoI for Embankment Works
All those living or working within the CoI of the embankment works have been identified as PAPs who will
be impacted by the sub-project works. The CoI has been reduced to remove excavation of the existing
berms where this would result in removal of shelter or other structural assets. As a result, the CoI over a
single cross-section of the canal shall not necessarily be continuous as demonstrated in the following two
examples.
Figure 3.8: Example of Continuous CoI on Ghotki Feeder Canal
Figure 3.9: Example of Discontinuous CoI on Ghotki Feeder Canal
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
38
Sindh Water Sector Improvement Project
The CoI for embankment works for each reach of the canal from RD 0 to 125 is given in the following table,
and a key to this table is provided in Figure 3.10. Cross-sections showing the CoI for the embankment
works at every 5RD are given in Appendix I.
Table 3.8: Ghotki Feeder Canal CoI for Embankment Raising
Reach (RD)
Left Bank CoI (measured from canal centreline)
Canal CoI (measured from canal centreline)
Right Bank CoI (measured from canal centreline)
Outer Inner Left Side Right Side Inner Outer
0 – 3 217.57 164.61 164.61 163.18 163.18 233.65
3 - 7.5 222.43 162.58 162.58 148.85 182.61 208.59
7.5 – 12.5 199.93 183.74 147.14 140.68 185.68 207
12.5 – 17.5 197.88 157.44 126.13 125.11 199.87 219.87
17.5 – 22.5 184.6 169.6 169.6 143.32 185.87 205.87
22.5 – 27.5 184.6 169.6 169.6 154.82 184.87 204.87
27.5 – 32.5 193.28 1778.28 134.12 133.56 183.87 203.87
32.5 – 37.5 184.62 169.62 129.62 131.38 194.85 214.85
37.5 – 42.5 195.54 180.54 135.33 143.56 163.25 195.2
42.5 – 47.5 197.27 180.79 124.92 128.25 178 198.96
47.5 – 52.5 179.6 164.6 131.21 134.4 162.27 184.6
52.5 – 57.5 182.17 163.37 122.98 120.56 203.99 224.87
57.5 – 62.5 183.75 164.3 123.2 132.94 181.75 205.72
62.5 – 67.5 170.13 150.13 119.76 122.7 122.7 144.03
67.5 – 72.5 151.31 129 107.21 103.43 124.32 140
72.5 – 77.5 146.28 114.55 114.55 99.68 117 136.22
77.5 – 82.5 147.08 119.81 84.93 84.38 120.36 156.79
82.5 – 87.5 162.76 120.43 102.26 115.57 115.57 140.83
87.5 – 92.5 146.34 115.87 79.56 75.24 120.58 147.82
92.5 – 97.5 146.66 111.53 82.3 82.22 111.91 146.92
97.5 – 102.5 150.54 115.98 82.57 81.98 120.51 147
102.5 – 107.5 147.38 110.41 81.75 81.75 116.27 148.94
107.5 – 112.5 152.29 112.2 90 90.71 112.21 149.07
112.5 – 117.5 147.12 117.91 87.13 86.87 111.9 136.25
117.5 – 122.5 165 115.08 82.49 109.34 128.87 143.87
122.5 - 125 150.19 121.48 81.96 81.57 150.87 165.87
Figure 3.10: Key to indicative canal cross-section showing CoI.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
39
Sindh Water Sector Improvement Project
3.8.1.2 CoI for Offtaking Canal Realignment and Temporary Diversions
The CoI also includes the footprint of any realigned off-taking canal and temporary canal diversion. The
layout of the realigned offtaking canals at both regulating complexes are provided in Appendix I.
3.8.1.3 CoI for Spoil Disposal and Borrow Areas
As part of the proposed works, a large volume of spoil is to be disposed of within the RoW. As detailed in
sections 3.6.2.3 and 3.6.2.4, the establishment of borrow areas or disposal of spoil shall be prohibited over
structures and fish farms within the RoW. Therefore the impact shall be limited to the loss of any standing
crops which are illegally grown within the RoW. Measurements of the RoW are provided in Table 3.2.
A plan of the spoil disposal locations is included in Volume II of this RAP (which also serves as Volume II to
the EIA/EMP for this contract).
3.8.1.4 CoI for Village Road Bridges
The CoI for the village road bridges shall include the footprint of the proposed bridges. The CoI for the
bridges is contained within the government owned RoW.
3.8.1.5 CoI for Hydraulic Structures
The CoI for the hydraulic structures shall include the footprint of the proposed hydraulic structures and
realigned canals.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
40
Sindh Water Sector Improvement Project
4.1 Approach and Methodology
4.1.1 Techniques and Sample Size
In order to have comprehensive and detailed information the following techniques and tools of data
collection were used. It is also significant to note that representatives from SIDA were involved during the
field survey. A list of SIDA staff accompanying the team is provided in Appendix B.
4.1.1.1 Sample Design
A census of all households and businesses falling within the CoI was conducted.
4.1.1.2 Village Profile
A comprehensive village profile was prepared to document the socio-economic and demographic data of
each sample settlement in the study area. During the field survey 13 villages were randomly selected from
within the sub-project area.
4.1.1.3 Pretesting of Questionnaire
In order to test the validity and reliability of the developed questionnaire, interviewing guides were
pretested in the study area and the questionnaires were reviewed to assess whether questions need to be
clarified or changed.
4.1.1.4 Women Survey
A separate questionnaire was developed covering various aspects relating to women in the CoI. Female
interviewers of PIC conducted the field survey with male sociologists in the sub-project area and held
meetings with the affected families.
4.1.2 Collection of Primary Data
The preparation of the RAP required the collection of data/information from the field settings. To achieve
this end, comprehensive questionnaires for data collection were prepared as given in Appendix C. The
questionnaires were filled during the consultative meetings and during field visits. Four types of
questionnaires were developed for data collection, as described below:
Village profile for the collection of macro level information relating to the existence of socio-economic
infrastructure in the rural settlements falling within CoI.
Census survey to document the Project Affected Persons (PAPs), their assets, family profiles and
economic status.
Socio-economic survey to develop an overall baseline profile of the people of the area in respect of their
socio-economic behaviour, vulnerability and attitudes towards the developmental activity to be carried
out in the area.
Gender data collection survey targeting the female population of the CoI exclusively in order to
supplement the socio-economic data collection.
4. Socio-Economic Studies
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
41
Sindh Water Sector Improvement Project
Consultations were carried out with the stakeholders and general public. Consultative meetings and focus
group discussions were held to learn about the views and concerns of the local community on the
proposed rehabilitation works. The concerns raised by the stakeholders were discussed with the project
design team in order to enhance the projects acceptability for the general public on socio-economic
considerations. The main objectives of the consultations were to provide a platform to the stakeholders, to
voice their concerns or suggestions to the project team and to develop a sense of collective ownership for
the activities of the project. For detailed consultations see Chapter 6.
PIC was initially active in the field from September to 2010 to January 2011. PIC remobilised to the field to
update the baseline data from August 2014.
4.1.3 Collection of Secondary Data
Secondary data relating to the socio-economic characteristics of the sub-project was collected from the
concerned local government offices, police, fisheries, building, and road and agriculture departments.
Official Websites of Ghotki and Sukkur districts were also searched. The population census reports for the
concerned districts were also consulted.
4.2 Socio-Economic Profile of Sub-Project Area
4.2.1 Location of Canal
Ghotki Feeder Canal is located in the talukas of Ubauro, Daharki, Mirpur Mathelo, Ghotki, Pano Akil and
Rohri of districts Sukkur and Ghotki.
4.2.2 Brief Description of Ghotki District
Ghotki district takes its name from the Ghotki Town which is the headquarters of the district. It is located
between 270-18’ to 280-27’ north latitudes and 690-10’ to 700-10’ east longitude. The district is bounded on the north by Rahim Yar Khan and Jacobabad districts, on the south by Sukkur district, on the east by
Jasalmir State of India and on the west again by Jacobabad district. Total area of the district is 6,083
square kilometres. Total population of districts is 970,549 comprising of 511,363 males and 459,186
females. The average annual growth rate of district is 3.26 percent per annum and population density of
district is 159.6 persons per square kilometre. The Ghotki district is divided into five Talukas, namely
Daharki , Ghotki, Mirpur Mathelo, Ubauro , Khanpur Mahar respectively. Ghotki district has two gas fields
namely Mari gas field and Qadirpur gas field in Daharki and Ghotki talukas respectively. Mari gas field is
larger than Qadirpur by production. At present 65 wells are functioning and producing 400 million cubic feet
of gas per day. Engro Chemical Fertilizers, Fauji Fertilizer, Fatima Fertilizer Company are situated at Machi
Goth, Taluka Sadiqabad, District Rahim Yar Khan (Punjab). Engro Energy Plant is situated in Ghotki,
Liberty Power Plant and Fauji Foundation Power Plant are situated in Mirpur Mathelo. WAPDA (Guddu
Thermal) and Sui Southern Gas Company are the main users/customers of natural gas produced by these
gas fields. Important means of transport and communication in the district are roads and railways. The
main Pakistan Railway Line (Karachi to Peshawar) passes through this district and district is also
connected with the National Highway running from Karachi to Peshawar
4.2.3 Brief Description of Sukkur District
Sukkur is an important district of Sindh Province, it is famous for export of dates. It is divided into four
administrative talukas, namely; Sukkur City, Rohri, Saleh Pat and Pano Aqil. Among them Sukkur city and
old Sukkur are urban centres while Pano Aqil is famous for having one of largest military cantonments in
the country. Rohri is the smallest taluka of the Sukkur district, both in area and population but has an
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
42
Sindh Water Sector Improvement Project
ancient and important railway junction. The area of the Sukkur District is 5,165km² and density of the
population is 175.9 persons per square kilometre. The population of Sukkur District is 908,370; the average
annual growth rate is 2.88 present. Geographically it is spanned from 27°05' to 28°02' north latitudes and
from 68°47' to 69°43' east longitudes. Sukkur district shares northern border with Shikarpur and (recently
constituted) Kashmore districts. Ghotki is located on the north-eastern side while Khairpur on the south.
Sukkur also shares its border with India (Jaisalmir, Rajasthan).
The city of Sukkur is located at an altitude of 220 feet (67 m) from sea level, having terrestrial coordinates
68°52' east and 27°42' north. Sukkur is the third largest city of Sindh province, situated on the west bank of
Indus River in Sukkur District. It is also the narrowest point of the lower Indus. Sukkur is also connected by
road and air with all major cities of Pakistan.
Sukkur is a hub of many small and large scale industries. Among important industries are cotton textiles,
cement, leather, tobacco, paint and varnish, pharmaceuticals, agriculture implements, hand pumps, lock
making, rice-husking, and sugar. Small-scale cottage industries comprise hosiery, boat making, fishing
accessories, thread ball spooling, trunk making brass-wares, cutlery and ceramics
4.2.4 Cropping Pattern in the Sub-Project Area
The sub-project benefits from fertile land and is irrigated by canals, as a result is very rich in growing of
cotton, wheat and sugarcane. The cropping pattern of the three districts is given in the following sections. It
is noted that agriculture is practiced heavily within the CoI of this sub-project. Many PAPs living within the
CoI are engaged as agricultural labourers.
4.2.4.1 The Cropping Pattern of District Ghotki
Ghotki district is very rich in the growing of cotton, wheat and sugarcane. Other crops in the area are rice,
maize, barley, jawar, bajra, tobacco, gram and barley. The main occupation of the people is agriculture.
The details of cropping pattern are given in Table 4.1.
Table 4.1: Cropping Pattern of Ghotki District
Cropping Seasons
Rabi Crops Kharif Crops
i) Wheat
ii) Gram
iii) Oilseed (Rape Seed and Mustered)
iv) Barley
v) Pluses
vi) Tobacco
vii) Rabi Fodder (Barseem/Losern)
viii) Vegetables (Onion, Tomato, Potato, Cabbage
and Peas)
ix) Orchard
i) Cotton
ii) Sugarcane
iii) Rice
iv) Bajra
v) Maize
vi) Pluses
vii) Kharif Fodder
viii) Vegetables
ix) Orchard (Date, Banana, Falsa and
Guava)
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
4.2.4.2 The Cropping Pattern of District Sukkur
Sukkur district is very rich in growing of cotton, rice, wheat and sugarcane. Other crops in the area are
watermelon, chillies and pluses. The main occupation of the people is agriculture. Details of cropping
pattern in Sukkur district are given in Table 4.2.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
43
Sindh Water Sector Improvement Project
Table 4.2: Cropping Pattern of Sukkur District
Cropping Seasons Rabi Crops Kharif Crops
i) Wheat
ii) Gram
iii) Oilseed (Rape Seed and Mustered)
iv) Barley
v) Pluses
vi) Tobacco
vii) Rabi Fodder (Barseem/Losern)
viii) Vegetables (Onion, Tomato, Potato, Cabbage
and Peas)
ix) Orchard
i) Cotton
ii) Sugarcane
iii) Rice
iv) Bajra
v) Maize
vi) Pluses
vii) Kharif Fodder
viii) Vegetables
ix) Orchard (Date, Banana, Falsa and Guava)
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
4.2.5 Education and Literacy Ratio in the Sub-project Area
During field survey 13 villages are selected randomly for socio-economic analysis. According to the results
of the survey, the total population of the 13 surveyed villages and hamlets is 4,580 people, comprising of
2,150 males and 2,430 females. The number of literate persons comes to 932 (consisting of 776 boys and
156 girls students) which accounts for 20.35 percent of the total population. Out of total literate, persons
having primary level education are 58.26 percent, middle level 26.39 percent and matric level 11.91
percent respectively. While the respondents with intermediate and graduation levels are 3.44 percent. The
Information in respect of literacy levels of the surveyed villages is furnished in Table 4.7.
Table 4.3: Literacy Rate in the sub-project Corridor
Sr. No.
Education Level
Literacy Rate
Percentage Male
(#)
Female
(#)
Total
(#)
1 Primary 425 118 543 58.26
2 Middle 210 36 246 26.39
3 Matric 109 2 111 11.91
4 Above Matriculate 32 - 32 3.44
Sub-Total Educated 776 156 932 100 (20.35)
5 Illiterate 1223 2104 3327 72.65
6 Children 151 170 321 7
Grand Total 2150 2430 4580 100
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
4.2.6 Social Amenities in Sub-project Area
The result of the survey revealed that the electricity, road, primary level education and mobile phone
facilities are available in the of sub-project area. However, only approximately 75 percent of the population
had access to this facility, whereas, 25 percent are not provided with electricity. Regarding the quality of
services, about 49 percent of the respondents availing this facility showed their satisfaction. Education is
the other important facility which is available to 39 percent of the respondents. The majority of people
(approximately 56 percent) are not satisfied with the quality of services while 44 percent showed their
satisfaction, road facility is only 30 percent available in the sub-project area. Mobile phone facility is 100 %
available in the sub-project area. Availability of sewerage/drainage facility is not reported in the area. Other
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
44
Sindh Water Sector Improvement Project
amenities like water supply tanks are not available in the sub-project area. Gas, Basic health Unit (BHUs)
and land lined telephone services are not available in the surveyed villages, as reported by the
respondents. The information in respect of access to social amenities and their quality of services are given
in the following table.
Table 4.4: Access to Social Amenities in the sub-project area
Sr. No. Facility Available
(%)
Not Available
(%)
Satisfactory
(%)
Unsatisfactory
(%)
Ghotki feeder Canal
A. RD 1+000 to RD 22+000
1 Electricity 100 - 45 55
2 Gas 0 100 - -
3 Water Supply/Tank 0 100 - -
4 Telephone (Land Line) 0 100 - -
5 Sewerage/ Drainage 0 100 - -
6 Road 50 50 65 35
7 BHU 0 100 - -
8 School (Primary only) 30 70 40 60
9 Mobile 100 - 100 -
B. RD 23+000 to RD 40+000
1 Electricity 50 50 50 50
2 Gas 0 100 - -
3 Water Supply/Tank 0 100 - -
4 Telephone (Land Line) 0 100 - -
5 Sewerage/ Drainage 0 100 - -
6 Road 40 60 45 55
7 BHU 0 100 - -
8 School (Primary only) 70 30 55 45
9 Mobile 100 - 100 -
C RD 41+000 to RD 90+00
1 Electricity 100 - 60 40
2 Gas 0 100 - -
3 Water Supply/Tank 0 100 - -
4 Telephone (Land Line) 0 100 - -
5 Sewerage/ Drainage 0 100 - -
6 Road 20 80 50 05
7 BHU 0 100 - -
8 School (Primary only) 35 69 40 60
9 Mobile 100 - 100 -
D RD 91+000 to RD 127+00
1 Electricity 50 50 40 60
2 Gas 0 100 - -
3 Water Supply/Tank 0 100 - -
4 Telephone (Land Line) 0 100 - -
5 Sewerage/ Drainage 0 100 - -
6 Road 10 90 60 40
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
45
Sindh Water Sector Improvement Project
Sr. No. Facility Available
(%)
Not Available
(%)
Satisfactory
(%)
Unsatisfactory
(%)
7 BHU 0 100 - -
8 School (Primary only) 20 80 40 60
9 Mobile 100 - 100 -
Over All
1 Electricity 75 25 49 51
2 Gas 0 100 - -
3 Water Supply/Tank 0 100 - -
4 Telephone (Land Line) 0 100 - -
5 Sewerage/ Drainage 0 100 - -
6 Road 30 70 55 45
7 BHU 0 100 - -
8 School (Primary only) 39 61 44 56
9 Mobile 100 - 100 -
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
4.2.7 Pressing Needs of the Men
It has been pointed out by the men during the survey that 37.16 percent identified delivery of adequate
irrigation water was their priority, they were concerned that they were not given irrigation water according to
their design discharge of canal. The second and onward needs prioritized by the men are dispensary,
electricity, a middle school and gas. The pressing needs of men are presented in the following table.
Table 4.5: Pressing Needs of Men (Multiple Responses)
Sr. No. Items Number Percentage
(%)
1 Irrigation Water 55 37.16
2 Dispensary 38 25.68
3 Electricity 30 20.27
4 Middle School 15 10.13
5 Gas 10 6.76
Total 148 100
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
4.2.8 Status of Women
The survey has revealed that participation percentage of women in various socio-economic activities in the
project corridor is generally high, 100 percent in case of household activities and child caring. Their
participation percentage in case of agriculture stood at 48 percent, livestock raring at 45 percent, and 95
percent in the case of social obligation (such as attending death and marriage ceremonies). Regarding
decision making and participation of women remained zero percent. Information in respect of women
participation is presented in the following table.
Table 4.6: Women Role in Socio-economic Activities (Multiple Response)
Sr. No.
Activity Ghotki Feeder Canal(%)
1 Households Activities 100
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
46
Sindh Water Sector Improvement Project
Sr. No.
Activity Ghotki Feeder Canal(%)
2 Child Care 100
3 Farm/Crop 48
4 Livestock Rearing 45
5 Social Obligations 95
6 Decision Making -
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
Figure 4.1: Women Engaged in Agriculture and livestock
4.2.8.1 Gender Issues
A gender study was carried out for the project to assess the difference in social roles between females and
males. The constraints faced by the females in gaining access to various activities and participation were
gathered. The female population in Pakistan according to the 1998, Census, is around 48%. In view of this
situation, the gender issues assume special focus and need to be properly addressed and evaluated. The
females were interviewed including working class ladies, house wives, students and elderly women. The
results of the survey have shown that women are an integral part of the socio-economic life of the rural
economy. Women of the area took active part in household activities (like cooking, washing of clothes,
carrying of fodder for livestock and potable water for human consumption, etc.), child caring and fulfilling
social obligations. The above data indicates that as far as participation in carrying out different activities is
concerned, they share with the males in every household and field activity. However, their participation is
zero in making decisions about various socio-economic matters, particularly related to activities which
require interaction with others such as decisions about education of children, farm business, sale and
purchase of livestock or property, etc. The male respondents were of the view that traditionally they have
been undertaking such responsibilities and they do not think that the females have much exposure and
courage to decide such matters. This is a kind of social stress for the women.
4.2.8.2 Pressing Needs of Women
Pressing needs of the women correspondents in the sub-project area within the corridor of impact are
given in the following table:
Table 4.7: Pressing Needs of Women(Multiple Response)
Sr. No. Items Number Percentage (%)
1 Irrigation water 55 33.33
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
47
Sindh Water Sector Improvement Project
Sr. No. Items Number Percentage (%)
2 Electricity 45 27.27
3 Girls Primary School 30 18.18
4 Health (RHC) 25 15.16
5 Gas 10 6.06
Total 165 100.00 Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
It can be found from the above table that first priority of the women of the area is irrigation water. The
second most pressing need is electricity. The remaining pressing needs are girl’s primary school, health facility and availability of gas.
4.2.9 Non-Government Organization in the Sub-project Corridor
During the field survey it was observed that many NGOs were working in the sub-project and the following
are currently active: Marvi Stop Service (MSS), Sindh Rural Support Organization (SRSO), Takhalik
Foundation, Village Development Association (VDO), Gul Welfare Association, in the field of Health,
Education, Livestock, Poultry, Health & Hygiene, Infrastructure, Micro-Credit and Environment. These
NGOs are working in the whole districts, and not exclusively or specifically in sub-project area. NGO
representatives assured the project team that they will work in the project affected villages on priority basis
in future.
4.3 Socio-Economic Profile of CoI
The socio-economic profile includes the description of the villages, households and populations within the
CoI. The socio-economic characteristics of the sub-project corridor are based on the village profile, socio-
economic surveys, focus group meetings and information collected from the secondary sources. The
results of the survey are described in the following sections.
The CoI is defined in section 3.8.
4.3.1 Population of CoI
The population of those residing in structures which have been illegally constructed in the CoI can be sub-
divided as shown in Table 4.8
Table 4.8: Population of the CoI
Age Group Male % Age Female % Age Total Percentage
< 5 42 13.72 44 13.92 86 13.83
6-9 30 9.80 31 9.81 61 9.81
10-18 53 17.32 57 18.04 110 17.68
19-65 176 57.52 179 56.65 355 57.07
Above 65 5 1.63 5 1.58 10 1.61
Total 306 49.20 316 50.80 622 100
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
The 622 PAPs identified in the table above are living within 84 households within the CoI. In addition to
these 84 households residing in the CoI, 3 households of 23 PAPs own shops in the CoI, but reside
elsewhere. Full details of all those owning residential or commercial structures in the CoI can be found in
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
48
Sindh Water Sector Improvement Project
Appendix D. A further 34 households (as detailed in Appendix E) farm land situated within the CoI, but are
also residing outside the CoI.
A total of 121 affected households have been identified.
4.3.2 Employment and Income Sources of PAPs
The employment of the PAPs by household is provided in the following figure, showing that the most
common source of income to PAPs is from farming, followed by general labour. Note the figure below
includes data from all 121 affected households.
Figure 4.2: Employment of all PAPs (121 households)
All PAPs employed in small businesses are dependent upon the shops constructed within the CoI, while
the farming households are farming land inside and outside the CoI.
The following figure provides the employment of the 84 households resident within the CoI, and shows the
majority depend on general labour as their source of income.
Farming
42%
Fishing
6%
General Labour
42%
Government Service
1%
Livestock
1%
Private Servant
4%
Small Business
4%
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
49
Sindh Water Sector Improvement Project
Figure 4.3: Employment of PAPs residing in the CoI (84 households)
General labourers are engaged in number of roles. Most commonly, labourers are employed as agricultural
labourers (harvesting, picking, threshing, animal rearing, drivers and guards).
Local laborers commonly gain employment during the sugarcane harvesting season, for crop harvest,
loading and transportation. Sugar mills in the surrounding area also employ skilled and unskilled labor and
a source of income generation. There are five sugar mills as well as a large rice industry in the command of
Ghotki Feeder Canal. Both have created employment and made positive impact on the local economy in
the area.
For the majority of labourers, employment is intermittent and usually on a temporary basis.
4.3.3 Income Levels and Poverty Status
The overall income and poverty status of PAPs owning assets in the CoI is provided in the following table.
Table 4.9: Income and Poverty Status of the Affected Households
Sr. No.
Primary Profession of the AFs
No. of Affected
Households
Total No.of PAPs.
Total Monthly
Income (Rs)
Average Monthly Income Per
Household (Rs)
Average Income Per Capita
(Rs./Month)
1 Small Business (Shop, General Store, Cold Corner, Tea Stall, etc.)
4 34 34,000 8,500 1000
Farming
29%
Fishing
8% General Labour
54%
Government Service
1%
Livestock
1% Private
Servant
6%
Small Business
1%
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
50
Sindh Water Sector Improvement Project
Sr. No.
Primary Profession of the AFs
No. of Affected
Households
Total No.of PAPs.
Total Monthly
Income (Rs)
Average Monthly Income Per
Household (Rs)
Average Income Per Capita
(Rs./Month)
2 General Labour 45 297 244,500 5,433 832
3 Fishing 7 51 30,000 4,286 588
4 Farming Tenant 17 125 95,500 5,618 764
5 Farming Owner 7 86 90,000 12,857 1047
6 Private Service 5 41 32,000 6,400 780
7 Government Service 1 7 8,000 8,000 1143
8 Livestock 1 4 4,000 4,000 1000
Total 6,184 834
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014 Note: Six abandoned structures are not included in this table.
Table 4.10: Poverty Status of Ghotki Feeder Canal (Below Poverty Line)
Sr. No.
Profession of Affectees No. of Households (Below Poverty Line)
Total No. APs (Below Poverty Line)
Poverty Status (%)
1 Small Business (Shop, General Store, Cold Corner, Tea Stall, etc.)
4 34 100%
2 General Labour 43 293 96%
3 Fishing 7 51 100%
4 Farming Tenant 17 125 100 %
5 Farming Owner 6 82 86 %
6 Private Service 5 41 100 %
7 Government Service 1 7 100%
8 Livestock 1 4 100 %
Total 84 637 97%
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
The tables above indicate that among the affectees, all those households engaged in small businesses,
fishing, farming (as tenants), private service, government service and livestock rearing are living below the
poverty line, while the majority of general labourers and farm owners also live below the poverty line.
Overall, 97% of the affected households are living below the poverty line.
The income levels have been considered in relation to the poverty line of Pakistan, which has been set in
this RAP to be PKR 2,307 per capita per month. This is calculated from the 2010-2011 poverty line of PKR
1,745/capita/month as quoted in the Pakistan Economic Survey of 2013-20142. This value has been
adjusted based on the annual consumer price inflation quoted by the World Bank3:
11.9% in 2011: PKR 1,952.66
9.7% in 2012: PKR 2,142.06
7.7% in 2013: PKR 2,307.00
1http://databank.worldbank.org/data/home.aspx
4.3.4 Expenditure of Affected Household
During the field survey encroachers were asked their monthly/ yearly expenditure. They informed the
consultants that their income and expenditure varies every month. They said they take loan from
shopkeepers in the town and from landlords. Labourers depend on their daily wages until the harvest
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
51
Sindh Water Sector Improvement Project
season when they are paid to harvest crops and make enough money to meet their expenses and repay
loans to shopkeepers.
Table 4.11: Expenditure of Affected Households
Sr. No.
Profession of the AFs
No. of Affected
Households
Total No.of PAPs.
Total Monthly
Expenditure (RS)
Average Monthly Expenditure Per Household (RS)
Average Expenditure Per
Capita (Rs./Month)
1 Small Business (Shop, General Store, Cold Corner, Tea Stall, etc.)
4 34 37,000 9,250 1,088
2 General Labour 45 297 337,000 7,489 1,135
3 Fishing 7 51 56,500 8,071 1,108
4 Farming Tenant 17 125 132,100 7,771 1,057
5 Farming Owner 7 86 103,000 14,714 1,198
6 Private Service 5 41 42,500 8,500 1,037
7 Government Service 1 7 12,000 12,000 1,714
8 Livestock 1 4 5,000 5,000 1,250
Total 87 645 725,000 8,334 1,124
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
4.3.5 Social Background of Affected Households
Of the 87 project affected households owning assets in the CoI, 63% (55 households) moved to the CoI
following flooding of their property from the River Indus in 2010 and 2011. Note that immediately following
the floods in the Indus, a large number of households were temporarily living on the embankments. The
majority returned to their original land once the floods receded. Of those that remained on the
embankment, some originally lived close to the embankments (and still own land nearby) but remained on
the embankment for convenience, while others found new land to farm (as tenants) or local employment
close to the embankments and preferred not to move away from this source of income.
37% (32 households) moved to the embankments for business. The majority (all but two households)
moved to the NIP from RD 43 to 49 to be in the vicinity of Mureed Shakh village (immediately east of the
Ghotki Feeder canal at this location). The village hosts a busy market, and employment (for example, in
construction) and business (sale of produce) is readily available in this village. Those who moved to the
embankment to be closer to employment and markets have been located on the embankments for a longer
duration than those displaced by floods, and have resided here for between 10 and 20 years.
43% of those living on the embankments stated that they would be welcomed back to their original villages.
However, most were not willing to do so, as this would involve them moving away from their source of
employment or agricultural land. Note, that in many cases, families moved away from their original villages
some years ago and prefer to move back to their own private land than to return to their home villages.
The remaining 57% stated that they would not be welcomed back to their original villages, mainly due to
lack of available land available for housing and agriculture rather than due to conflicts.
The status of the affected households is summarised in the following table.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
52
Sindh Water Sector Improvement Project
Table 4.12: Settlement Background of PAPs
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation
Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Inspection Path (IP)
1 Shah Gul Mazari 9+500(IP) Govt. Servant Orangzaib Mazari 5 Flood in Indus yes Yes
2 Wallan Mazari 14+000(IP) Farming (Owner) Orangzaib Mazari 5 Flood in Indus yes No
3 Pinyal Kosh 63+000(IP) General Labour Mir Kosh 5 Flood in Indus yes Yes
Non-Inspection Path (NIP)
1 Faiz Mohammad 7+900 (NIP) Farming (Owner) Dur Mohammad Golato
5 Flood in Indus
yes No
2 Ghulam Hyder 7+900(NIP) Farming (Tenant) Dur Mohammad Golato
5 Flood in Indus
yes No
3 Pir Bux 14+700(NIP) General Labour Malik 6 Flood in Indus yes No
4 Karim Bux Mirani 14+500(NIP) General Labour Malik 6 Flood in Indus yes No
5 Bashir Ahmed 14+500(NIP) General Labour Khahi Malik 6 Flood in Indus yes No
6 Abdul Hakeem Malik 14+600(NIP) General Labour Khahi Malik 6 Flood in Indus no
7 Imam Din Malik 14+900(NIP) Small Business Khahi Malik 5 Flood in Indus no
8 Mohammad Bux 14+500(NIP) General Labour Khahi Malik 6 Flood in Indus no
9 Shahmir Malik 15+950(NIP) Small Business Khahi Malik 6 Flood in Indus no
10 Sohnno Mazari 18+000(NIP) Farming (Tenant) Khahi Malik 6 Flood in Indus no
11 Nihal Mazari 18+200(NIP) General Labour Mazari Village 6 Flood in Indus no
12 Shah Mohammad 19+200(NIP) Farming (Tenant) Mazari Village 5 Flood in Indus no
13 Ali Nawaz 19+800(NIP) Farming (Tenant) Mazari Village 6 Flood in Indus yes No
14 Ghulam Fareed 27+300(NIP) Farming (Tenant) Mazari Village 6 Flood in Indus yes No
15 Dil Murad 27+300(NIP) Farming (Owner) Mazari Village 6 Flood in Indus yes No
16 Hassan Ali Mazari 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No
17 Yaqoob Mazari 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No
18 Yaseen Mazari 27+300(NIP) Farming Mazari Village 6 Flood in Indus yes No
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
53
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation
Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
(Tenant)
19 Mir Muhammad 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No
20 Sohbat Khan Mazari 27+800(NIP) Farming (Tenant) Mazari Village 6 Flood in Indus no
21 Nazir Ahmed Mazari 28+900(NIP) Private Servant Ponhu Mazari 10 Business/ work
Yes No
22 Wazir Ahmed Mazari 28+900(NIP) Private Servant Ponhu Mazari 10 Flood in Indus no
23 Mohib Ali Mazari 28+800(NIP) Private Servant Ponhu Mazari 7 Flood in Indus no
24 Rehman mazari 29+000(NIP) General Labour Ponhu Mazari 6 Flood in Indus no
25 Ali Anwar mazari 30+000(NIP) Farming (Owner) Ponhu Mazari 6 Flood in Indus yes No
26 Mohammad Ramzan 40+000(NIP) Private Servant Dasti Village 5 Flood in Indus yes Yes
27 Balach Khan Dasti 40+000(NIP) Private Servant Dasti Village 5 Flood in Indus yes Yes
28 Allah Rakhiyo 40+100(NIP) General Labour Dasti Village 5 Flood in Indus yes Yes
29 Nazir Ahmed 40+200(NIP) General Labour Baksha pur Village 5 Flood in Indus yes Yes
30 Veer Malik 40+200(NIP) General Labour Baksha pur Village 5 Flood in Indus yes Yes
31 Malook malik 40+200(NIP) General Labour Baksha pur Village 5 Flood in Indus yes Yes
32 Kashmir Malik 40+200(NIP) General Labour Baksha pur Village 5 Flood in Indus yes Yes
33 Hamal Mazari 41+000(NIP) Farming (Tenant) Baksha pur Village 5 Flood in Indus yes Yes
34 Mir Hazar Mazari 41+000(NIP) Farming (Tenant) Baksha pur Village 5 Flood in Indus yes Yes
35 Yousif Dasti 41+500(NIP) Farming (Tenant) Baksha pur Village 5 Flood in Indus yes Yes
36 Ali Nawaz Dasti 41+500(NIP) Farming (Tenant) Baksha pur Village 5 Flood in Indus yes Yes
37 Dagha Khan 41+500(NIP) General Labour Baksha pur Village 5 Flood in Indus yes Yes
38 Karam Ali 43+300(NIP) General Labour Lashkran 20 Flood in Indus no
39 Abrar Ali 43+300(NIP) General Labour Lashkran 20 Flood in Indus no
40 Zahoor Ahmed 43+500(NIP) General Labour Miani Kondi wala 3 Flood in Indus yes No
41 Farooq 43+500(NIP) General Labour Miani Kondi wala 8 Flood in Indus no
42 Imam Ali 43+500(NIP) General Labour Lashkran 20 Flood in Indus yes No
43 Gulam Ali 43+300 Small Business Mureed Shakh 10 Business/ work
no
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
54
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation
Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
44 Abandonned* 43+500(NIP) - - - -
45 Mahboob Ali Memon 43+500(NIP) Small Business Mureed Shakh 15 Business/ work
no
46 Abandonned* 43+500(NIP) - - - -
47 Barkatullah Dasti 43+500(NIP) General Labour Rajan pur 10 Business/ work
no
48 Ali Hasan Mirani 43+900(NIP) Fishing Gudani Village 15 Business/ work
no
49 Sher Mohammad 44+00(NIP) Fishing Gudani Village 15 Business/ work
no
50 Muhammad Amin Dasti 44+000(NIP) General Labour Mureed Shakh 16 Business/ work
Currently located at Mureed Shakh
51 Durr Muhammad Mirani 44+100(NIP) General Labour Mureed Shakh 17 Business/ work
Currently located at Mureed Shakh
52 Muneer Ahmed Shah 44+100(NIP) General Labour Khanbhra Village 15 Business/ work
no
53 Muhammad Mureed Mirani
44+150(NIP) General Labour Gudani Village 16 Business/ work
no
54 Abdul Ghani Mirani 44+150(NIP) General Labour Gudani Village 16 Business/ work
no
55 Abandonned* 44+200(NIP) - - - -
56 Haji Iqbal Chaoudhry 44+250(NIP) General Labour Mureed Shakh 16 Business/ work
Currently located at Mureed Shakh
57 Papu Pathan 44+300(NIP) General Labour Mureed Shakh 15 Business/ work
Currently located at Mureed Shakh
58 Ashraf Ali Qureshi 44+350(NIP) General Labour Mureed Shakh 15 Business/ work
Currently located at Mureed Shakh
59 Muhammad Achar 44+400(NIP) General Labour Mureed Shakh 16 Business/ work
Currently located at Mureed Shakh
60 Muneer Ahmed Mirani 44+500(NIP) General Labour Mureed Shakh 15 Business/ work
Currently located at Mureed Shakh
61 Muhammad Mor 44+550(NIP) General Labour Kot Sabzal 15 Business/work no
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
55
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation
Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
62 Samundar Khan 44+600(NIP) General Labour Kot Sabzal 15 Business/work no
63 Bhora Khan 44+700(NIP) General Labour Lashkran village 16 Business/work no
64 Akbir Ali Dasti 44+750(NIP) General Labour Gudani Village 16 Business/work no
65 Noor Din Mirani 44+850(NIP) Fishing Gudani Village 15 Business/work no
66 Abandoned* 44+800(NIP) - - - -
67 Shahnawaz Dasti 45+850(NIP) General Labour Mureed Shakh 16 Business/work Currently located at Mureed Shakh
68 Allah Jawayo 46+100(NIP) General Labour Lashkran village 15 Business/work no
69 Wahid Bux 47+200(NIP) General Labour Lashkran village 16 Business/work yes No
70 Kandho Khan 47+900(NIP) Live Stock Lashkran village 16 Business/work yes No
71 M.Azeem Bhyo 49+100(NIP) Farming (Owner) Lashkran village 14 Business/work no
72 Faiz Mohammad 49+100(NIP) Farming (Owner) Lashkran village 16 Business/work no
73 Mohammad Haleem 49+100(NIP) Farming (Owner) Lashkran village 16 Business/work no
74 Ali Gohar 49+100(NIP) Farming (Tenant) Lashkran village 16 Business/work no
75 Ghulam Hussaul 49+100(NIP) Farming (Tenant) Lashkran village 16 Business/work no
76 Muj Ali Mirani 51+00(NIP) General Labour Khubhra Village 14 Flood in Indus Yes Yes
77 Datto Mirani 51+00(NIP) General Labour Khubhra Village 4 Flood in Indus Yes Yes
78 Abondonned* 52+100(NIP) - - - -
79 Abondonned* 52+400(NIP) - - - -
80 Gul Mohammad Meerani 52+800(NIP) General Labour Khubhra Village 5 Flood in Indus yes No
81 Shahid 52+800(NIP) General Labour Khubhra Village 5 Flood in Indus yes No
82 Chanesar Mirani 53+00(NIP) Fishing Gudani Village 4 Flood in Indus no
83 Mir Khan Mirani 53+200(NIP) General Labour Gudani Village 4 Flood in Indus no
84 Dado Murani 53+200(NIP) Fishing Gudani Village 4 Flood in Indus no
85 Liaqat Ali Mirani 53+00(NIP) Fishing Gudani Village 4 Flood in Indus no
86 Akhtar Hussain 53+00(NIP) Fishing Gudani Village 4 Flood in Indus no
87 Umed Ali 61+200(NIP) General Labour Budho Kosh 4 Flood in Indus no
88 Abdul Rehman Kosh 61+200(NIP) General Labour Budho Kosh 4 Flood in Indus no
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
56
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation
Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
89 Mohammad Adhyo 61+300(NIP) General Labour Budho Kosh 20 Business/work no
90 Baksho Kosh 61+450(NIP) Farming (Tenant) Budho Kosh 20 Business/work no
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
57
Sindh Water Sector Improvement Project
4.3.6 Agriculture
The lands in sub-project area are fertile and canal water is the main source of crop cultivation. Farmers
grow rice, sugarcane, cotton, sorghum, vegetables and cultivate orchards during the Kharif season (April to
November) and wheat, oil seed, pulses and vegetables during Rabi season (May to October). Sugarcane is
a cash crop and commonly grown in the sub-project area due to the availability of the surrounding sugar
mills. The most commonly grown crops are wheat, rice, sugarcane and fodder for livestock.
Figure 4.4: Cropping in the Project Area
The canal irrigation system is the major source of crop cultivation in the sub-project area. It was also
observed that some farmers have also installed tube wells to irrigate their land/crops.
Within the CoI, at total of 315.4 acres of land is cultivated. Of this land, 307.6 acres of government owned
land within the RoW (running alongside the outer toe of the canal embankments) is illegally farmed by
farmers from 34 households. All of these households are resident outside the CoI and have no legal
entitlement to the land they are farming. These farmers are identified in Appendix E.
In addition, 7.8 acres of privately owned land within the CoI (but outside the RoW) is farmed by private land
owners at RD 63 and RD 125 of the Ghotki Feeder Canal.
Rice, wheat and sugar cane are commonly grown within the CoI.
4.3.7 Landholding Status
During the field survey it was observed that no household which is residing, or owns commercial structures,
within the CoI, has any legal entitlement to any land within the CoI.
9.925 acres of privately owned agricultural land is situated within the CoI at RD 63+000 and RD 125+000
IP. The owners of this land are residing outside the CoI.
4.3.8 Animal Husbandry in the Project Corridor
Overall in the sub-project area people own very good breeds of buffaloes, cows and bulls, goats and
sheep. Livestock is the main source of milk, meat and ghee for the local population. Livestock is also a
source of income as people of the area keep cow/bulls, goat and sheep to sell annually at Sukkur and
Karachi market. Donkeys and camels are used for load carrying. Domestic poultry is also a source of
income.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
58
Sindh Water Sector Improvement Project
Figure 4.5: Livestock in the Project Area
4.3.9 Castes and Languages
Social organization in all villages is strongly based on Biradari (tribal) system, where each caste has a
caste leader. The Main castes in the sub-project area are Mazari, Mirani, Mallah, Malik, Solongi, Kosh,
Khoso, Lashari, Shaikh, Brohi, Syed, Bozdar, Maree and Jatoi. These castes are not related to religion and
are not immutable.
Sindhi language is commonly spoken as mother tongue of majority of the communities in the project area.
However, Balochi and Sareiki languages are also spoken and understood as local languages.
4.3.10 Cultural Heritage
No cultural assets, including graves or mosques, fall within the CoI for the works. PIC identified graves
situated near RD 40+000 on the IP side of Ghotki Feeder Canal, but these are situated beyond the CoI.
4.3.11 Social Cohesion and Conflict in the CoI
The social structure and conflict resolution mechanisms of the CoI and sub-project area are similar.
The majority of families in the study area live in joint family systems (parents live with their elders and
children). The sharing of resources is beneficial in term of joint incomes, manpower (agricultural practices)
and basic amenities such as water, electricity, housing and food.
Social organization in all villages is strongly based on the tribal system, where each tribe has a tribal
leader. The families belonging to the same tribe have strong interactions with one another and generally
keep separate identities. For example, in the marriages of their young, they prefer to marry within their own
tribe. Such interactions between different tribes are less common. During the survey it was found that most
communities had built their own religious structures and maintenance of these religious structures was by
the villagers themselves.
4.3.11.1 Conflict Resolution within Tribes and Castes
During the field survey of villages it was observed that most activities are carried out under the instruction
of the head of tribe. The caste system in the rural area of the Sindh is very rich, and decisions about
conflict, right of vote, marriage settlements and other matters are usually resolved by the head of tribe.
Most of the conflicts in the CoI are mutually resolved within the tribe at the village level. Those living within
the CoI feel obliged to accept the decision of their tribe leader.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
59
Sindh Water Sector Improvement Project
It has been observed in rural Sindh that where more than one tribe has settled within a single village, each
tribe has their own tribe leader. Overall there is a village leader from the same village and who belongs to
an influential political family or a land lord and is from a financially sound family of the village. The majority
of conflicts are resolved by tribe leader, and if not solved at this level, the matter shall be elevated to the
village leader.
Occasionally, where the conflict cannot be resolved at a village level, the matter may go to the political
leaders of the area. Of the conflicts reaching this level, more than 90 percent of matters were resolved by
the political leaders of the area.
In extreme cases where resolution at all other levels has failed, conflicts may go to police and ultimately a
court of law. The police and the court of law are the last options and these are rarely exercised.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
60
Sindh Water Sector Improvement Project
5.1 General
Prior to implementation of works as part of the rehabilitation of Ghotki Feeder Canal, clearance of certain
measurements of land (defined as the CoI) will be required. It has been found during the field surveys that
the CoI is occupied by families living in shelters and, in a limited number of cases, conducting business
within the CoI. Agriculture is also heavily practiced within the CoI. 23.93 acres of privately owned land also
falls within the CoI. All structures within the CoI shall require removal prior to the implementation of the
works. Privately owned land shall also require acquisition prior to implementation of the works. The CoI is
defined in section 3.8.
5.2 Identification of PAPs
A Project Affected Person (PAP) is defined as any person, whose land, shelter, assets, infrastructure,
source of livelihood or access to resources is to be affected by the sub-project activities. PAPs can be
divided into the following two groups:
1. Directly and Partially Affected Persons: This group includes people whose land, houses, other built-up
property or source of livelihood will be affected due to sub-project activities.
2. Indirectly Affected Persons: This group includes people who will not lose their land, houses or built-up
property, but whose social relations and/or free mobility would be indirectly disrupted due to sub-project
activities. All those living within the primary impact zone are considered to fall within this category.
Any person whose land, assets, infrastructure, source of livelihood or access to resources is likely to be
affected by the sub-project activities within the CoI of the embankment works or canal realignment is
therefore considered to be a PAP. In the context of contract WSIP/B1/GF/01, this includes all those who
will lose shelter, commercial structures or crops due to clearance of the CoI, as well as those whose land
shall be permanently or temporarily acquired.
The impact to the indirectly affected persons is covered within the Environmental Impact Assessment and
Environmental Management Plan (EIA/EMP) for Contract WSIP/B1/GF/01. The EIA/EMP stipulates a
number of actions taken during the planning and design as well as actions to be implemented by the
contractor to prevent any significant impact to this group. This group is not considered within the RAP.
PIC was initially active in the field from September to 2010 to January 2011 to identify the PAPs. PIC
remobilised to the field to update the list of PAPs from May to August 2014 in order to capture any changes
to the population of the CoI since January 2011.
Note that in this RAP, a structure is defined as a single continuous structure fixed to the ground, including
all the rooms within that structure, any sheds built against or over that structure, and boundary walls
associated with the structure. For example, a single house may contain multiple rooms (bedrooms, living
room), a kitchen, a shed and a boundary wall. A full breakdown of the components of each structure is
provided in Appendix D.
5. Assessment of Impacts
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
61
Sindh Water Sector Improvement Project
5.3 Overview of Impacts
103 privately owned structures and 48 hand pumps are constructed illegally on the canal embankments
within the CoI (i.e. the owners of these assets have no formal recognisable rights to the land occupied by
their assets). These structures are owned by 87 households, comprising of 645 persons. Of the 103
structures, six are abandoned, and of the 48 hand pumps, 2 were abandoned. All 103 structures and 48
hand pumps shall be removed from the CoI to allow the contractor to complete earthworks as part of the
rehabilitation of the canal embankments.
Of the 87 households owning structures in the CoI, three households (consisting of 23 PAPs) are owning
only shops in the CoI and their residences are situated outside the CoI. The remaining 84 households
(consisting of 622 PAPs) are residing within their houses constructed inside the CoI.
An additional 34 households are illegally farming 307.6 acres of government owned land within the CoI.
This land shall be used during construction for the establishment of borrow areas, and subsequently for the
disposal of material excavated from the canal. It is expected that the majority of the material to be
excavated from the canal is not fertile, and therefore the 307.6 acres of illegally farmed land shall not be
available for cultivation following implementation of the sub-project.
7.8 acres of privately owned land is to be permanently acquired adjacent to RD 63 and 125 of the Ghotki
Canal. No structures are present in this land.
Full details of PAPs who shall be losing assets can be found in Appendix D and details of PAPs who shall
lose standing crops can be found in Appendix E.
The clearance of one hand pump which is owned by the community is also required. No mosques or
graves fall within the CoI.
Three Governments owned sites and one hand pump have also been established within the CoI, including
Police chowki, Pump house, Irrigation Room.
5.4 Loss of Agricultural Land
5.4.1 Permanent Loss
7.8 acres of private land will be required for the realignment of off-taking canals at RD 63+000 and
125+000 of Ghotki Feeder Canal. Cost of the permanent land will be borne by the project proponent. The
land is cultivated and owned by six separated owners.
An additional 307.6 acres of land illegally farmed within the RoW shall also be lost as a result of borrow pits
and spoil disposal works. This shall result in the loss of any standing crops at the time of disposal within the
CoI for spoil disposal. The loss of a total of up to 307.6 acres of standing crops, cultivated by 34
households has been identified as a result of these works. This shall result in the loss of any money
invested in crops which have been planted but not harvested at the time that works are implemented in the
CoI.
All land which is cultivated within the RoW is done so illegally. The estimated area of 307.6 acres is based
upon the area which was found to be cultivated during the 2014 survey, the actual area may vary at the
time of construction. See Appendix E for further details.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
62
Sindh Water Sector Improvement Project
5.4.2 Temporary Loss
The contractor shall be required to temporarily acquire approximately 5 acres of privately owned cultivated
land at RD 63 and at RD 125 (approximately 10 acres in total) in order to establish temporary canal
diversions.
5.5 Loss of Residential, Commercial, Industrial or Institutional Land
5.5.1 Loss of Residential Land
84 households have constructed residential structures within the government owned RoW over land that
shall be required for the implementation of works under this sub-project. These households shall be
required to vacate this land for implementation of the sub-project. None of the 84 households own titles to
the impacted land as it is all government owned.
If no other land is made available, this shall have a significant and direct impact upon the wellbeing of all of
these PAPs as they shall not be able to reconstruct their residential structures. As the majority of these
households are living below the poverty line, such impacts shall be exacerbated.
5.5.2 Loss of Commercial Land
Five households have constructed commercial structures within the RoW, also over land that shall be
required for implementation of works under this sub-project. Of these five households, two have also
constructed residential structures in the RoW, and are discussed in section 5.5.1. The remaining three
households reside outside the impacted areas. All five households shall be required to vacate this land for
implementation of the sub-project. None of the five households own titles to the impacted land as it is all
government owned.
If no other land is made available, this shall have a significant and direct impact upon the income, of all of
these PAPs as they shall not be able to reconstruct their commercial structures.
5.5.3 Loss of Industrial Land
None of the impacted land is used for industrial purposes.
5.5.4 Loss of Institutional Land
All institutional land that shall be impacted by the proposed works is currently owned by the Irrigation
Department, and shall remain under ownership of the Irrigation Department,
5.6 Loss of Structures
5.6.1 Summary
The result of the survey revealed that different structures have been constructed at the toe of canal within
the CoI. These structures can be defined and sub-defined as follows:
Houses (kacha and pacca), including:
Rooms
Kitchens
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
63
Sindh Water Sector Improvement Project
Washroom
Boundary wall
Sheds
Animal shed
Hand pumps (privately, community and government owned)
Sheds
Guest house (Otaq)
Shops (Pacca, semi pacca or kacha)
The views of houses within the CoI are shown in the following figures.
Figure 5.1: View of Houses in the CoI
A summary of the impact to structures within the CoI is given in the following table.
Table 5.1: Detail of Impacted Structures within the CoI
Sr. No.
Type of Structure Number of Structures Total
(IP + NIP) IP NIP
1 House 3 81 84
2 Abandoned House - 3 3
3 Shops - 4 4
4 Abandoned Shops - 2 2
5 Otaqs - 1 1
6 Abandoned Otaqs - 1 1
7 Privately Owned Hand Pumps 2 44 46
8 Abandoned Hand Pumps - 2 2
9 Animal Shed - 9 9
10 Community Owned Hand Pumps 0 1 1
11 Government Owned Structures - 3 3
Total 156
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
Full details are provided in Appendix D.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
64
Sindh Water Sector Improvement Project
The demolition/removal of all structures detailed in the table above is required.
5.6.2 Loss of Residential Structures
5.6.2.1 Loss of Shelter
A total of 84 houses, occupied by 84 different households, shall be removed from the CoI. This shall result
in the loss of shelter of the 84 households, consisting of 622 people (including 146 children aged less than
10 years old and ten aged over 65 years old). With the exception of three households, all are living below
the poverty line. Without reconstruction of these structures, this shall have a significant and direct impact
upon the wellbeing of all of these PAPs. As the majority of these households are living below the poverty
line, such impacts shall be exacerbated.
The cost of reconstruction would be a significant expenditure for these households, who have a very low
income. This would require a reduction in expenditure on basic commodities (such as food, clothes and
medical expenses), which would also have a significant impact on the wellbeing of these PAPs.
Sufficient compensation to allow the affected households to reconstruct their houses without impacting
upon their wellbeing through increased expenditure is detailed in Chapter 7.
5.6.2.2 Impact on Drinking Water
Of the 84 households who shall be impacted by loss of shelter, 46 households shall be impacted by the
removal of 46 privately owned hand pumps. The removal of these hand pumps shall result in a reduction in
the availability of drinking water within the CoI. The income of the affected households is low, and without
sufficient compensation, these households shall not be able to install new hand pumps outside the CoI,
resulting in a long term negative impact to their wellbeing.
5.6.3 Loss of Commercial Structures
Five households own commercial structures situated within the RoW. Of these, four households own shops
and one owns a otaq (guesthouse). All five households are living below the poverty line. Of the five
households, two shall also lose shelter, and are therefore also detailed in section 5.6.2.1.
All structures shall be permanently removed from the CoI. Without reconstruction of these structures, this
shall have a significant and direct impact upon the income of the affected households. The cost of
reconstruction of these structures would be a significant expenditure for these households, who have a
very low income. This would require a reduction in expenditure on basic commodities (such as food,
clothes and medical expenses), which would also have a significant impact on the wellbeing of these
PAPs. The impact to the income of these PAPs is discussed further in section 5.7.
5.6.4 Loss of Industrial Structures
There are no industrial structures located within the CoI.
5.6.5 Loss of Community Structures
A single community owned hand pump was identified to fall within the CoI of the works at RD 16.2 of the
Ghotki Feeder Canal (NIP side) and shall be removed for implementation of works under this sub-project.
The hand pump is used by passers-by travelling through the area, and is not relied upon by any specific
household. This hand pump is shown in the figure below.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
65
Sindh Water Sector Improvement Project
Figure 5.2: View of Hand pump in the CoI
No graves or mosques fall within the CoI for the sub-project works.
5.6.6 Loss of Institutional Structures
The field surveys revealed that the following government structures exist in the CoI: one Police Chowki
(consisting of two rooms); one irrigation room; and, one hand pump. Demolition of all these structures shall
be required for the completion of these works and their reconstruction has been included within the civil
works contract. Details of the government sites to be removed from the CoI are given in the following table.
Table 5.2: Detail of Government Structure at CoI
Sr. No. Type of Structure No.of structure Location
1 Police Chowki 1 NIP
2 One room (Irrigation Department) 1 NIP
3 Hand pump 1 NIP
Total 3
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
66
Sindh Water Sector Improvement Project
Figure 5.3: View of Irrigation room
Figure 5.4: View of police chowki
5.7 Impact to Income
5.7.1 General
The poverty status assessment (section 4.3.3) identifies that 97% of the PAPs are living below the poverty
line. Fishing families are earning the lowest incomes, and as such shall be most vulnerable to changes in
their circumstances which impact upon their income or expenditure, which may result from the sub-project
impacts.
5.7.2 Loss of Income and Wages
5.7.2.1 Small Businesses
It is noted that the four households own shops, and one household owns an otaq (guesthouse) within the
CoI. Further details on the ownership of commercial structures may be found in Appendix D.3.
The affected households who own shops and otaqs within the CoI shall experience a direct impact on their
income due to loss of these business structures and therefore the loss of trade. This is true for all business
structures. Compensation for the impact to the livelihood of owners of shops and otaqs is therefore
required, and is discussed further in Chapter 7.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
67
Sindh Water Sector Improvement Project
Figure 5.5: Shops Located within CoI of Contract WSIP/B1/GF/01
5.7.2.2 General Labourers
The field survey identified 45 households who depend on general labour as their source of income.
General labourers are finding employment in a range of industries, including agriculture, sugar mills, cotton,
fertilizer factories, rice mills and construction. As their location of employment is outside the CoI, there shall
be no direct impact to their income.
5.7.2.3 Fishing
Seven households are dependent upon fishing for their income. They fish from Guddu Barrage and sell
these fish as a source of income. As Guddu Barrage is outside the CoI for this sub-project, there shall be
no direct impact upon their income.
5.7.2.4 Farming
There shall be a direct impact to the livelihood of the 34 households who are farming the 315.4 acres of
land within the CoI (307.6 acres within the RoW, and 7.8 acres of privately owned land). These farmers
shall experience a loss of income from the land that they currently farm within the CoI. Compensation in
line with the Entitlement Matrix (see section 2.5) is detailed in Chapter 7.
There shall be no direct impact to the income of farmers living in the CoI, but who farm land outside the
CoI.
5.7.2.5 Private Service
The result of the survey indicated that five households living within the CoI depend upon private service. All
households are employed outside the CoI, and as such there shall be no impact to their income.
5.7.2.6 Government Service
One household living within the CoI is employed in government service. As their employment is outside the
CoI, there shall be no direct impact to their income.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
68
Sindh Water Sector Improvement Project
5.7.2.7 Livestock
One household living within the CoI rears livestock for sale at local markets for their income. They keep
their livestock within a shed constructed illegally within the CoI. As this shed shall be removed from the
CoI, this shall have a direct impact on their income. As these PAPs are living below the poverty line, such
an impact would be exacerbated. Compensation for this shed is required to allow the household to
reconstruct this in a new location to reduce the impact to their income.
5.7.3 Impacts on Women Headed Households
During the surveys of the sub-project area, it was found that no women headed households exist in the CoI
of sub-project.
5.8 Impacts on Trees
All trees to be cuts during implementation of the sub-project are government owned. To mitigate the
adverse impacts, provision for re-plantation through the contractor has been proposed: the contractor shall
plant five trees for every one tree which is cut. Full details of trees to be cut are included in the EIA/EMP for
Contract WSIP/B1/GF/01.
5.9 Indirect Impacts
Please refer to the EIA/EMP for Contract WSIP/B1/GF/01 for an assessment of indirect impacts to
residents of the sub-project area, including: dust; community disturbance (including traffic and water
resources); and, noise. Proposed mitigations are also included in the EIA/EMP.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
69
Sindh Water Sector Improvement Project
5.10 Summary
The impacts associated with each component of works are summarised in the following table.
Table 5.3: Summary of Project Impacts
Type of Loss Application Definition of Entitled Person
Unit Establishment of Construction Camp
Rehabilitation of embankments
Borrow pits and spoil disposal
Canal desilting and lowering of bed level
Berm cutting/ formation
Establishment of haul routes
Construction of hydraulic structures 9,10
Construction of bridges11
Rehabilitation of bridges
Total
Loss of Land (Agricultural)
Permanent loss of entire land or where partial loss but the remaining land is less than 0.5 acre or is rendered economically unviable.
Legal owner with valid title or customary or usufruct rights.
Impacted Acres
(Impacted Households)
9.925
(6)
9.925
(6)
PAPs without title Impacted Acres
(Impacted Households)
299.8
(33)
8.2
(1)
307.6
(34)
Temporary loss of land Legal owner with valid title or customary or usufruct rights.
Impacted Acres
(Impacted Households)
10
(5)
10
(5)
Loss of Land (Residential, commercial, industrial or institutional land)
Loss of residential, commercial, industrial or institutional land without sufficient remaining land. PAPs will be required to relocate.
PAPs without title Impacted Households
87 87
PAPs without title living, below the poverty line
Impacted Households
84 84
Loss of Privately Owned Structures (Residential, commercial, industrial or agricultural)
Entire loss of structures or where only partial impact, but the remaining structure is rendered unviable for continued use, and sufficient land for reorganization.
Owner of structure (regardless of ownership of title to land on which structure is situated)
Impacted Households
87 87
Loss of Structures (Community or institutional)
Entire loss of structures or where only partial impact, but the remaining structure is rendered unviable for continued use.
Community or institution
Number of Impacted Structures
4 4
Loss of income (trade/ livelihood/ occupation or business incomes)
Temporary or permanent loss of commercial income
Impacted business owner
Impacted Households
5 5
_________________________ 9 This component of works includes the following activities: replacement of cross-regulators; replacement of offtaking head regulators and realignment of head reaches; and, construction of temporary canal diversions.
10 Structures to be impacted by the construction of temporary canal diversions shall also be impacted by the rehabilitation of the embankments. To avoid double counting these structures, they are only considered under the rehabilitation of embankments component.
11 Including realignment of roads at the location of proposed and replacement bridges.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
70
Sindh Water Sector Improvement Project
6.1 Introduction
To comply with World Bank’s requirements and policies on environmental assessment of projects, the
sponsors of the projects resulting in involuntary resettlement are required to prepare and publicly disclose a
RAP. The RAP must be prepared through a process of public consultation with all interested and affected
parties. Proper consultation with affected parties can increase the effectiveness and reduce the cost of
RAP implementation for the sponsor or other responsible parties. The proposed sub-project of Contract
WSIP/B1/GF/01 will impact the local environment of the area as well as communities living in and around
the sub-project area to some extent. This chapter provides details of consultations carried out with
stakeholders during the preparation of this Resettlement Action Plan.
6.2 Objectives of Consultation
Public consultation plays a vital role in studying the effects of the sub-project on the stakeholders and in the
successful implementation and execution of the proposed sub-project. Public involvement is a compulsory
feature of the RAP, which leads to better and more acceptable decision-making. The important general
objectives of the Consultation process are:
Provide key project information to the stakeholders, and to solicit their views on the Resettlement Action
Plan, and ensure their views are incorporated into the RAP,
Discuss and agree on mitigation measures,
Information dissemination, education, and liaison,
Identification of problems and needs,
Collaborative problem solving,
Develop and maintain communication links between the project proponents and stakeholders,
Reaction, comment and feedback on proposed sub-project and RAP;
Ensure that views and concerns of the stakeholders are incorporated into the sub-project design and
implementation with the objectives of reducing or offsetting negative impacts and enhancing benefits of
the proposed sub-project;
Create a sense of ownership among the stakeholders regarding the sub-project;
Increase public confidence about the proponent, reviewers and decision makers; and
To ensure the transparency in all the sub-project activities.
6.3 Methodology
The consultants carried out public consultations at various locations in the proposed sub-project area of
Contract WSIP/B1/GF/01. The stakeholder’s consultation during the work targeted the sub-project area,
administration, government officials, shops keepers and local community in and around the sub-project
area:
Selection of the stakeholders for consultation, reconnaissance of the proposed sub-project sites and
initial discussions with the SIDA officials, Irrigation department, AWB public and private employees
stakeholders, local public representative, local shopkeepers, and Project Affected Persons (PAPs).
Appraising the targeted stakeholders initially for the purpose of consultation and working out a schedule
for holding regular consultation meetings;
Meetings with the stakeholders through the participation of consultants’ environmental and social specialists and documenting the opinions of the stakeholders expressed during the meetings etc
6. Public Consultation and Information Disclosure
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
71
Sindh Water Sector Improvement Project
6.4 Consultations with Project Affected Persons
As per WB Policy, at the second stage of consultation community members and their representatives were
consulted to introduce the sub-project formally to the local community, to obtain their views on the project
and discuss impacts to the PAPs as well as mitigation measures. Group discussions were also carried out
on consultation process. Various focus group meetings /discussions carried out with all expected project
affected persons during August 2014. The meetings were held at various locations. In the meetings
affected people were informed about the plans for rehabilitation of the Ghotki Feeder Canal. A question
answer session was initiated such as:
Demographic characteristics of the village, such as population, number of households, housing
characteristics, availability of social amenities, ethnic groupings etc.
Livelihood activities of the project affected persons.
Women’s role in socio- economic life.
Existing health and education facilities in the village.
Feeling about the development work of the Ghotki Canal.
Following issues were also discussed:
Sub-project introduction will ensure the water supply without any hindrances
Un-authorized structures within the CoI may be affected due to the project works.
Compensation for lost structures will be paid as per WB policy
Mutual consensus on acceptable compensation was reached
Location of where PAPs shall be shifted to
Consultation with host community about community and religious structures.
6.4.1 Outcome of Focus Group Discussion/Meetings
All the affected households at Ghotki Feeder Canal AWB sub-project desire to get compensation in shape
of cash for compensation for their structures and wanted to manage themselves.
6.4.2 Cut Off Date
The cut-off date for eligibility for all entitlements, except land based entitlements due to registered owners,
has been set as the 08th August 2014. The 08
th August 2014 was the first working day of PIC field team in
the field during the 2014 field visit, during which the consultants updated the impact assessment and
survey of the population of the CoI. Any person constructed assets in the CoI after this date shall not be
eligible for entitlements under this Resettlement Action Plan.
The cut-off date for eligibility for land related entitlements due to registered owners shall be the date of the
section 4 notification issued under the Land Acquisition Act of Pakistan.
6.4.3 Relocation Locations
Subsequent to initial social assessments, PIC undertook consultations in the field from the 10th to the 17
th
November 2014, accompanied by members of the Ghotki Feeder AWB12
. The aim of these consultations
was to identify preferred relocation sites for all affected households. In many cases, the affected
_________________________ 12
The following AWB staff accompanied the field consultations: Mr. Imdad Ali Mirani Daroga, Mr. Gul hassan Daroga, Shah Nawaz Beldar, Budho Kosh Beldar
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
72
Sindh Water Sector Improvement Project
households do not own land to which they can relocate – in these cases, the field team identified suitable
sites within the government owned land which were to the satisfaction of the AWB.
During consultations, affected persons were found to be willing to vacate the IP and NIP. As discussed in
section 4.3.5, only 43% of those households living on the embankments reported that they would be
welcomed back to their original villages. Of these 43%, only 16 households were willing to return, with the
remainder preferring to stay within the vicinity of the embankments to remain close to their agricultural land
or place of employment.
The PAPs fell into the following broad categories:
16 households who were displaced by floods would be welcomed back at their home villages and are
willing to return
16 households who were displaced by floods and prefer to vacate the embankments to land they own
adjacent to the embankments. These households moved from their land during the floods in 2010 and
2011. Once the floods receded, these households did not leave the embankments as their original
locations were so close.
23 households who were displaced by floods prefer to remain close to their current location (in order to
remain close to the land they farm or their place of employment). However, these households do not
own land in the area and shall therefore be allowed by the AWB to reconstruct their houses within the
government owned RoW, beyond the CoI for these works.
32 households who moved to the embankments for business or employment between 10 and 20 years
ago prefer to remain close to their current location in order to remain close to their place of business or
employment. The majority (30) of these households are located on the outskirts of Mureed Shakh
village. However, these households do not own land in the area and shall therefore be allowed by the
AWB to reconstruct their houses within the government owned RoW, beyond the CoI for these works.
Of the above households, five shall lose commercial structures. All five households expressed their
preference to be relocated within the proximity of their current location. With the exception of one, none
own any land nearby and shall therefore be allowed by the AWB to reconstruct their shops and otaqs within
the government owned RoW, beyond the CoI for these works. It is expected that households owning
commercial structures within the sub-project area shall experience higher trade during construction as a
result of an influx of labourers to the area.
Of the 87 affected households, 55 households are to be given permission by the AWB to rebuild their
structures within government owned land. In each case, an area of land has been identified which is within
1 km of the existing location of the affected household (please refer to section 0 for further details). In most
cases the distance from their existing to proposed location is around just 300 ft (100m). Given the small
distances, there shall be minimal impact on the income or social networks of each household. In the case
of employed PAPs, households will not be moving further away from their place of employment. In the case
of commercial structures, locations adjacent to the main road running through the project area or adjacent
to road bridges crossing the canal have been identified to ensure the PAPs shall not experience a
reduction in passing trade in their new location. The ground conditions at the proposed sites are broadly
similar to the existing sites. In some cases, minor levelling works shall be required prior to reconstruction of
the affected structures, and this shall be completed by the affected households without assistance under
this RAP. In no cases shall there be a transfer of land title from the government to the affected household.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
73
Sindh Water Sector Improvement Project
6.5 Consultation with Local Women Community
6.5.1 General
Consultation sessions with the local women were also held. The consultant’s female interviewer conducted
these consultations. The women of the area were keenly interested in the consultations and provided good
information. The participants included housewives, students, and farm workers.
As far as education is concerned, the majority of them were illiterate. Most of them belonged to poor
families living in small houses. They pointed out the following issues and concerns, associated with this
sub-project.
Most of the women demanded proper compensation, rehabilitation and assistance.
The relocation of affected business structure of their spouse’s will create negative effect on their
income.
Risk of safety, security and privacy will be increased due to the working of outsiders during construction.
Some women were interested to work with their family male members during construction work, which will
reduce the burden on their budget.
6.5.2 Hand Pumps
PIC carried out additional consultations with female members of the project affected households in
November 2015 with regards to impacts resulting from loss of hand pumps. The women consulted
informed the female sociologist that they rely upon their hand pumps within their homes for daily use for
both domestic and livestock needs. With regards to compensation, materials and labour for the installation
of new hand pumps are available within Mureed Shakh village (located at approximately RD 45 of the
Ghotki Feeder Canal). PAPs will be able to arrange for local installation of hand pumps if provided with
sufficient compensation. As the hand pumps are used on a daily basis, it is important that compensation is
provided in advance of clearance of the CoI to ensure new hand pumps can be constructed before the
existing hand pumps are removed from the CoI.
The community hand pump is used by passers-by travelling through the area, and is not relied upon by any
specific household.
Figure 6.1: Consultations with Project Affected Women Regarding Hand Pumps
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
74
Sindh Water Sector Improvement Project
6.6 Meetings with Secondary Stakeholders
As per participatory approach, staff of SIDA, Ghotki AWB and Irrigation Department were contacted during
the preparation of this RAP. A list of officials contacted is given in Appendix B.
6.7 Grass Root Stakeholders Consultation
The grass root consultations were carried out at the following project locations:
Natho Khan Mazari
Hullar Chacaar
Mureed Shakh
Meer Kosh
Jam Khan Samejo
RD-127
Details of discussions during stakeholder consultations can be found in Appendix F. Detailed list of persons
contacted during grass root consultation is given in Appendix B, and pictorial views are provided in I.2.
6.8 Summary of Consultation Findings
The following table reviews the mains impacts that were discussed and mitigations that were agreed during
the consultations.
Table 6.1: Impacts and Mitigations Discussed during Consultations
Impact Discussion Agreed Mitigation
Improved delivery of water within the command area
Rehabilitation of the canal is required to ensure equitable distribution of supplies throughout the command area. Desilting and bank raising were seen as priority works by those consulted.
Implementation of works under Contract WSIP/B1/GF/01
Loss of privately owned structures
PAPs cannot afford to rebuild their structures. Compensation is required
Compensation for lost structures as per the Entitlement Matrix
Loss of residential land
Some PAPs indicated that they were willing to relocate back to their own land beyond the CoI. However, others expressed that they had no alternative land available to move to. Without alternative land, PAPs refused to move.
The AWB shall make land available for PAPs to rebuild their structures. Land preparation and transfer of title to the land shall not be provided.
Loss of commercial land
PAPs were concerned that they may experience a drop in trade at their new location
Alternative sites for commercial structures were identified that were close to roads to ensure continued, and in some cases improved, passing trade.
Disposal of excavated material within the RoW resulting in impacts to privately owned structures
There is sufficient space between structures in the RoW to allow for disposal of material excavated from the canal. This area should be fully used to prevent further loss of assets.
Disposal of material over structures in the RoW shall be prohibited under the contract. A spoil disposal plan has been prepared which utilises areas on which no structures are present. Local communities were involved in the preparation of this plan.
Cutting of berms on the resulting in impacts to privately owned structures
Unlike embankment raising, PAPs did not consider that berm cutting works were critical for the safe running of the system and that the impact to the PAPs would be greater than the benefit to the canal system. The PAPs requested the project to consider lining – however it was explained that the cost to line the canal was prohibitive.
Contract drawings have been amended to ensure that there shall be no berm cutting along reaches of the canal where structures are present.
Disposal of excavated material resulting in loss of agricultural land
Spoil should be disposed of within the RoW and not on peoples private land. PAPs farming land in the RoW requested compensation.
Spoil disposal plan provides for disposal of spoil only in the RoW. PAPs with standing crops within the RoW shall be provided with crop compensation.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
75
Sindh Water Sector Improvement Project
Impact Discussion Agreed Mitigation
Employment A large number of labourers shall be required for implementation of the sub-project. The contractor should employ local people.
Contractor shall require a large number of skilled and unskilled labourers. Many of these shall be employed from the local community
Loss of homes Some PAPs are very poor and will not be able to afford the replacement of their homes
Compensation for replacement of all affected assets to be provided. Those living below the poverty line shall be offered an additional allowance.
Community disturbance from migrant labourers
Free mobility of women and children should be ensured.
Contractor shall provide a camp for migrant staff to reside in. All migrant workers shall receive training on local sensitivities as part of their induction.
Replacement of road bridge
The bridge at RD 101 is too narrow and sugarcane trollies cannot pass over this bridge
Road bridge at RD 101 to be replaced under Contract WSIP/B1/GF/01.
Reduction in waterlogging and salinity of farmland
The berms of the canal are being eroded and the embankments are becoming weak, resulting in seepage from the canal leading to waterlogging and salinity on farm land. Impacct to agricultural productivity. The berms require protection in some areas.
Embankment rehabilitation and killa bushing (berm reinstatement) included within Contract WSIP/B1/GF/01.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
76
Sindh Water Sector Improvement Project
7.1 General
This RAP has been prepared on the basis of the findings of the census survey and by adopting the legal
and policy framework of Government of Pakistan and the World Bank policies as reflected in the
Entitlement Matrix (see section 2.5). This Entitlement Matrix was discussed during consultations as part of
the proposed mitigation measures. The Resettlement Action Plan focuses on providing assistance in the
form of compensation for the lost assets and additional assistance aim at restoring the livelihoods of PAPs
to their pre-project condition. This section details the applicable entitlements, grouped by the type of loss in
order to remain consistent with the Entitlement Matrix and the impacts for this project as detailed in
Chapter 5.
Note that, where required, compensation rates have been inflated to 2016 prices by applying annual
consumer price inflation as quoted by the World Bank13
which provides inflation rates up to year 2014. For
inflation beyond 2014, reference is made to Trading Economics14
.
7.2 Loss: Land (Agricultural)
7.2.1 Application: Permanent Loss of Entire Holding
7.2.1.1 Entitled Person: Title Holder
Entitlement: Compensation as Per Land Acquisition Act
Permanent acquisition of 9.925 acres of private land will be required for the cross-regulator at RD 63+000
and 125+000 of Ghotki Feeder Canal. The cost of the permanent land will be borne by the project
proponent. SIDA/AWB is responsible for the land acquisition. SIDA will write an official letter to the Deputy
Commissioner (DC) of the related district with the Deh map (provided in Appendix H) and the list of land
owners whose land will be acquired. DC will appoint an Assistant Commissioner as a land acquisition
officer and he will deal with the land acquisition matters.
The Assistant Commissioner will follow the procedure for acquisition under the LAA, as detailed in section
2.2.2 of this RAP.
The land compensation cost per acre has been collected from the Revenue Department in Ghotki. The
Assistant commissioner Ghotki is the land acquisition officer for the sub-project area and responsible for
paying the land compensation to the land owners. The Revenue Department indicated that the cost of land
is PKR 1,000,000 per acre, including compensation for loss of standing crops (as applicable under the
Land Acquisition Act). An additional 15% has been allowed in accordance with the Land Acquisition Act,
therefore the total estimated compensation rate is PKR 1,150,000 per acre.
The details of land to be acquired are given in the following tables. The Deh map is provided in Appendix
H.
_________________________ 13
http://databank.worldbank.org/data/home.aspx 14
http://www.tradingeconomics.com/pakistan/inflation-cpi/forecast
7. Relocation and Compensation Plan
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
77
Sindh Water Sector Improvement Project
Table 7.1: Inventory of Land Acquisition at RD 63
S.No Location Survey Number
Area Area
Acres Ghunta
1 RD 63 NIP Side 65/4 0 7
2 RD 63 NIP Side 224 Irrigation Bungalow
0 31
3 RD 63 NIP Side 76/2 0 18
4 RD 63 NIP Side 76/3 0 33
5 RD 63 NIP Side 76/4 0 25
6 RD 63 IP Side 225 0 21
Total Permanent Land Required in RD 63 3 15
Source: Survey of the Project Area, Project Implementation Consultants, July. 2014 to August- 2014
Table 7.2: Inventory of Land Acquisition at RD 125
S.NO Location Survey Number
Area
Acres Ghunta
1 IP Side (Masu Wah)
239 0 7
3 " 234 1 28
4 " 233 1 32
5 " 225 0 3
6 " 226 1 24
7 " 227 0 16
8 " 224 0 9
9 " 225 0 23
Total Permanent Land Required in RD 125 6 22
7.2.2 Application: Permanent Loss of Entire Holding
7.2.2.1 Entitled Person: PAP without Valid Title
Entitlement: Crop Compensation
The compensation rate has been calculated based on the average yield and value of cultivated crops. This
information was collected from within the sub-project area by PIC, and is presented in the table below.
Table 7.3: Yield price and total value of affected crop/acre
Crop Average yield (kg/acre)
Price (PKR/40Kg) in 2014
Price (PKR/40Kg) with inflation to 2016 rates
Value (PKR/acre) - 2016
Wheat 1,600 1,200 1320 53,000
Rice 2,400 850 940 56,400
Cotton 1,200 2,300 2,600 78,000
Sugarcane 36,000 112 125 112,500
Oil seed 600 2,500 2,800 42,000
Fodder 7,200 55 60 11,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
78
Sindh Water Sector Improvement Project
It is not possible to anticipate the crops which shall be grown at the time of implementation of the sub-
project. However, an allowance has been included in the budget based on the average value of the crops
grown in the CoI (rice, wheat and sugarcane) of PKR 74,000 per acre.
7.2.3 Application: Temporary Loss
The following entitlements shall be provided by the contractor for WSIP/B1/GF/01.
7.2.3.1 Entitled Person: Title Holder
Entitlement: Rent of Land at Market Rate
Temporary land acquisition will be required for diversions of canals (as part of the works for replacement of
hydraulic structures). The contractor will be responsible for temporary land acquisition. Monthly rent as per
the market value will be paid to the owner by the contractor. The owner will be compensated for any
damage to his land or assets there on, or else damaged assets shall be restored to their former condition
at the contractor’s cost.
7.2.3.2 Entitled Person: Tennant Farmer, Sharecropper or Farmer without Valid Title
Entitlement: Crop Compensation
Cash compensation or compensation in kind (such as employment during construction) shall be provided
to the entitled person. Cash compensation shall be as per Table 7.3.
7.3 Loss: Land (Residential and Commercial)
7.3.1 Application: Entire Loss
7.3.1.1 Entitled Person: PAP without Valid Title
PAPs who shall lose the land on which their structures are located, but who do not own the title to the land
on which these structures are situated are permitted to rebuild their structures at an alternative government
owned site (but without the transfer of title to ownership of this land). They are also entitled to a transport
allowance (regardless of whether they have opted to move to a government owned site or not). Where the
affected household is living below the poverty line, the household shall also be provided an additional Low
Income Allowance.
Entitlement: Alternative Sites
The affected households have been consulted to identify whether they prefer to rebuild affected structures
at an alternative government owned site or on their own land outside the CoI. The following table
summarises the preference of each household and is consistent with the findings of the consultations
summarised in section 6.4.3. Plans, signed by the AWB representatives, which identify the alternative sites
which shall be made available to these households can also be found in Appendix K. These plans detail
the exact resettlement locations.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
79
Sindh Water Sector Improvement Project
Table 7.4: Resettlement Locations
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Preferred Site to Rebuilt Assets
Distance to Preferred Site
Inspection Path (IP)
1 Shah Gul Mazari 9+500(IP) Govt. Servant Orangzaib Mazari 5 Flood in Indus yes Yes Orangzaib
Mazari 1km
2 Wallan Mazari 14+000(IP) Farming (Owner)
Orangzaib Mazari 5 Flood in Indus
yes No Beyond CoI –
Gov land <1km
3 Pinyal Kosh 63+000(IP) General Labour Mir Kosh 5 Flood in Indus yes Yes Mir Kosh village 1km
Non-Inspection Path (NIP)
1 Faiz Mohammad 7+900 (NIP) Farming (Owner)
Dur Mohammad Golato
5 Flood in Indus
yes No Own land <1km
2 Ghulam Hyder 7+900(NIP) Farming (Tenant)
Dur Mohammad Golato
5 Flood in Indus
yes No Own land <1km
3 Pir Bux 14+700(NIP) General Labour
Malik 6 Flood in Indus
yes No Own land <1km
4 Karim Bux Mirani 14+500(NIP) General Labour Malik 6 Flood in Indus yes No Own land <1km
5 Bashir Ahmed 14+500(NIP) General Labour Khahi Malik 6 Flood in Indus yes No Own land <1km
6 Abdul Hakeem Malik
14+600(NIP) General Labour Khahi Malik 6 Flood in Indus
no Own land <1km
7 Imam Din Malik 14+900(NIP) Small Business Khahi Malik 5 Flood in Indus no Own land <1km
8 Mohammad Bux 14+500(NIP) General Labour Khahi Malik 6 Flood in Indus
no Beyond CoI –
Gov land <1km
9 Shahmir Malik 15+950(NIP) Small Business Khahi Malik 6 Flood in Indus
no Beyond CoI –
Gov land <1km
10 Sohnno Mazari 18+000(NIP) Farming (Tenant)
Khahi Malik 6 Flood in Indus
no Beyond CoI –
Gov land <1km
11 Nihal Mazari 18+200(NIP) General Labour Mazari Village 6 Flood in Indus
no Beyond CoI –
Gov land <1km
12 Shah Mohammad 19+200(NIP) Farming (Tenant)
Mazari Village 5 Flood in Indus
no Beyond CoI –
Gov land <1km
13 Ali Nawaz 19+800(NIP) Farming Mazari Village 6 Flood in Indus yes No Beyond CoI – <1km
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
80
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Preferred Site to Rebuilt Assets
Distance to Preferred Site
(Tenant) Gov land
14 Ghulam Fareed 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No Own land <1km
15 Dil Murad 27+300(NIP) Farming (Owner)
Mazari Village 6 Flood in Indus
yes No Own land <1km
16 Hassan Ali Mazari 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No Own land <1km
17 Yaqoob Mazari 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No Own land <1km
18 Yaseen Mazari 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No Own land <1km
19 Mir Muhammad 27+300(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
yes No Own land <1km
20 Sohbat Khan Mazari
27+800(NIP) Farming (Tenant)
Mazari Village 6 Flood in Indus
no Beyond CoI –
Gov land <1km
21 Nazir Ahmed Mazari
28+900(NIP) Private Servant Ponhu Mazari 10 Business/ work Yes No Own land <1km
22 Wazir Ahmed Mazari
28+900(NIP) Private Servant Ponhu Mazari 10 Flood in Indus
no Own land <1km
23 Mohib Ali Mazari 28+800(NIP) Private Servant Ponhu Mazari 7 Flood in Indus no Own land <1km
24 Rehman mazari 29+000(NIP) General Labour Ponhu Mazari 6 Flood in Indus
no Beyond CoI –
Gov land <1km
25 Ali Anwar mazari 30+000(NIP) Farming (Owner)
Ponhu Mazari 6 Flood in Indus
yes No Own land <1km
26 Mohammad Ramzan
40+000(NIP) Private Servant Dasti Village 5 Flood in Indus
yes Yes
Dasti Village 5 km
27 Balach Khan Dasti 40+000(NIP) Private Servant Dasti Village 5 Flood in Indus yes Yes Dasti Village 5 km
28 Allah Rakhiyo 40+100(NIP) General Labour Dasti Village 5 Flood in Indus yes Yes Dasti Village 5 km
29 Nazir Ahmed 40+200(NIP) General Labour Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
30 Veer Malik 40+200(NIP) General Labour Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
81
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Preferred Site to Rebuilt Assets
Distance to Preferred Site
31 Malook malik 40+200(NIP) General Labour Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
32 Kashmir Malik 40+200(NIP) General Labour Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
33 Hamal Mazari 41+000(NIP) Farming (Tenant)
Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
34 Mir Hazar Mazari 41+000(NIP) Farming (Tenant)
Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
35 Yousif Dasti 41+500(NIP) Farming (Tenant)
Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
36 Ali Nawaz Dasti 41+500(NIP) Farming (Tenant)
Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
37 Dagha Khan 41+500(NIP) General Labour Baksha pur Village
5 Flood in Indus
yes Yes Baksha pur
Village 65 km
38 Karam Ali 43+300(NIP) General Labour Lashkran 20 Flood in Indus
no Beyond CoI –
Gov land <1km
39 Abrar Ali 43+300(NIP) General Labour Lashkran 20 Flood in Indus
no Beyond CoI –
Gov land <1km
40 Zahoor Ahmed 43+500(NIP) General Labour Miani Kondi wala 3 Flood in Indus
yes No Beyond CoI –
Gov land <1km
41 Farooq 43+500(NIP) General Labour Miani Kondi wala 8 Flood in Indus
no Beyond CoI –
Gov land <1km
42 Imam Ali 43+500(NIP) General Labour Lashkran 20 Flood in Indus yes No Beyond CoI –
Gov land <1km
43 Gulam Ali 43+300 Small Business Mureed Shakh 10 Business/ work no Beyond CoI –
Gov land <1km
44 Abandonned* 43+500(NIP) - - - -
45 Mahboob Ali Memon
43+500(NIP) Small Business Mureed Shakh 15 Business/ work no Beyond CoI –
Gov land <1km
46 Abandonned* 43+500(NIP) - - - -
47 Barkatullah Dasti 43+500(NIP) General Labour Rajan pur 10 Business/ work no Beyond CoI –
Gov land <1km
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
82
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Preferred Site to Rebuilt Assets
Distance to Preferred Site
48 Ali Hasan Mirani 43+900(NIP) Fishing Gudani Village 15 Business/ work no Beyond CoI –
Gov land <1km
49 Sher Mohammad 44+00(NIP) Fishing Gudani Village 15 Business/ work no Beyond CoI –
Gov land <1km
50 Muhammad Amin Dasti
44+000(NIP) General Labour Mureed Shakh 16 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
51 Durr Muhammad Mirani
44+100(NIP) General Labour Mureed Shakh 17 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
52 Muneer Ahmed Shah
44+100(NIP) General Labour Khanbhra Village 15 Business/ work no Beyond CoI –
Gov land <1km
53 Muhammad Mureed Mirani
44+150(NIP) General Labour Gudani Village 16 Business/ work no Beyond CoI –
Gov land <1km
54 Abdul Ghani Mirani 44+150(NIP) General Labour Gudani Village 16 Business/ work no Beyond CoI –
Gov land <1km
55 Abandonned* 44+200(NIP) - - - -
56 Haji Iqbal Chaoudhry
44+250(NIP) General Labour Mureed Shakh 16 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
57 Papu Pathan 44+300(NIP) General Labour Mureed Shakh 15 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
58 Ashraf Ali Qureshi 44+350(NIP) General Labour Mureed Shakh 15 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
59 Muhammad Achar 44+400(NIP) General Labour Mureed Shakh 16 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
60 Muneer Ahmed Mirani
44+500(NIP) General Labour Mureed Shakh 15 Business/ work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
61 Muhammad Mor 44+550(NIP) General Labour Kot Sabzal 15 Business/work no Beyond CoI –
Gov land <1km
62 Samundar Khan 44+600(NIP) General Labour Kot Sabzal 15 Business/work no Beyond CoI –
Gov land <1km
63 Bhora Khan 44+700(NIP) General Labour Lashkran village 16 Business/work no Beyond CoI –
Gov land <1km
64 Akbir Ali Dasti 44+750(NIP) General Labour Gudani Village 16 Business/work no Beyond CoI – <1km
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
83
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Preferred Site to Rebuilt Assets
Distance to Preferred Site
Gov land
65 Noor Din Mirani 44+850(NIP) Fishing Gudani Village 15 Business/work no Beyond CoI –
Gov land <1km
66 Abandoned* 44+800(NIP) - - - -
67 Shahnawaz Dasti 45+850(NIP) General Labour Mureed Shakh 16 Business/work Currently located at Mureed Shakh
Beyond CoI – Gov land
<1km
68 Allah Jawayo 46+100(NIP) General Labour Lashkran village 15 Business/work no Beyond CoI –
Gov land <1km
69 Wahid Bux 47+200(NIP) General Labour Lashkran village 16 Business/work yes No Beyond CoI –
Gov land <1km
70 Kandho Khan 47+900(NIP) Live Stock Lashkran village 16 Business/work yes No Beyond CoI –
Gov land <1km
71 M.Azeem Bhyo 49+100(NIP) Farming (Owner)
Lashkran village 14 Business/work no Beyond CoI –
Gov land <1km
72 Faiz Mohammad 49+100(NIP) Farming (Owner)
Lashkran village 16 Business/work no Beyond CoI –
Gov land <1km
73 Mohammad Haleem
49+100(NIP) Farming (Owner)
Lashkran village 16 Business/work no Beyond CoI –
Gov land <1km
74 Ali Gohar 49+100(NIP) Farming (Tenant)
Lashkran village 16 Business/work no Beyond CoI –
Gov land <1km
75 Ghulam Hussaul 49+100(NIP) Farming (Tenant)
Lashkran village 16 Business/work no Beyond CoI –
Gov land <1km
76 Muj Ali Mirani 51+00(NIP) General Labour Khubhra Village 14 Flood in Indus Yes Yes Khubhra Village 3 km
77 Datto Mirani 51+00(NIP) General Labour Khubhra Village 4 Flood in Indus Yes Yes Khubhra Village 3 km
78 Abondonned* 52+100(NIP) - - - -
79 Abondonned* 52+400(NIP) - - - -
80 Gul Mohammad Meerani
52+800(NIP) General Labour Khubhra Village 5 Flood in Indus
yes No Beyond CoI –
Gov land <1km
81 Shahid 52+800(NIP) General Labour Khubhra Village 5 Flood in Indus
yes No Beyond CoI –
Gov land <1km
82 Chanesar Mirani 53+00(NIP) Fishing Gudani Village 4 Flood in Indus
no Beyond CoI –
Gov land <1km
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
84
Sindh Water Sector Improvement Project
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation Originating Village
Years Living on Embankment
Reason for Moving to Embankment
Welcomed Back to Original Village?
If Yes, Willing to Return?
Preferred Site to Rebuilt Assets
Distance to Preferred Site
83 Mir Khan Mirani 53+200(NIP) General Labour Gudani Village 4 Flood in Indus
no Beyond CoI –
Gov land <1km
84 Dado Murani 53+200(NIP) Fishing Gudani Village 4 Flood in Indus
no Beyond CoI –
Gov land <1km
85 Liaqat Ali Mirani 53+00(NIP) Fishing Gudani Village 4 Flood in Indus
no Beyond CoI –
Gov land <1km
86 Akhtar Hussain 53+00(NIP) Fishing Gudani Village 4 Flood in Indus
no Beyond CoI –
Gov land <1km
87 Umed Ali 61+200(NIP) General Labour Budho Kosh 4 Flood in Indus
no Beyond CoI –
Gov land <1km
88 Abdul Rehman Kosh
61+200(NIP) General Labour Budho Kosh 4 Flood in Indus
no Beyond CoI –
Gov land <1km
89 Mohammad Adhyo 61+300(NIP) General Labour Budho Kosh 20 Business/work no Beyond CoI –
Gov land <1km
90 Baksho Kosh 61+450(NIP) Farming (Tenant)
Budho Kosh 20 Business/work no Beyond CoI –
Gov land <1km
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
85
Sindh Water Sector Improvement Project
7.3.1.2 Entitled Person: PAPs Living below the Poverty Line
Entitlement: Low Income Allowance
The number of households having monthly earnings below the poverty line is estimated to be 84. Their
incomes are fragile and they are less able to absorb any change in their socio-economic equilibrium. For
such households, in addition to the entitlements above, an additional Low Income Allowance equal to two
times the monthly household income of the household (inflated to 2016 value), or equal to the equivalent of
two months minimum wage in Pakistan (PKR 22,000 in 2016, assuming 10% inflation from 2014 rates),
whichever is greater. This allowance is intended to increase their resilience to impacts resulting from loss
of their residential land.
7.4 Loss: Privately Owned Structures
7.4.1 Application: Entire Loss
7.4.1.1 Entitled Person: Owner of Structure
Owners of structures which are to be removed from the CoI are eligible for compensation to rebuild the
affected structure, regardless of whether they own the land on which the structure is situated or not.
Entitlement: Compensation for Replacement of Structures
All the structures in the CoI are illegally built on government land. Data on assets within the CoI has been
collected through physical inspection and measurement of the structures. Full details of structures are
given Appendix D.
A valuation survey was undertaken by PIC for estimating the unit rate for compensation for loss of
residential and commercial structures and other such assets. The rates were arrived at by PIC engineers
and sociologists, in consultation with the local community/ affected people and market places as detailed in
Appendix G (quoted at 2014 rates). Using this data, the unit rates used for valuation of affected structures
was determined. These are based on the prevailing market rates as of August 2014, with inflation to 2016
rates (7.2% inflation in 2014, 2.53% inflation in 2015), and the following procedures/ methods were used
for the assessment of unit compensation values of different items/ assets located within the CoI:
Houses are valued at replacement value/cost based on cost of materials, type of construction, labour,
transport and other construction costs.
Hand pumps and other utilities are valued at current installation cost.
The relocation cost is the amount needed to displace and relocate assets at prevailing market prices
without adding costs for transaction.
Table7.5: Compensation Rates for Replacement Assets
Description Unit Unit/Rate (Rs.)
(i) Residential, Commercial, Community or government
Sq. ft.
Pacca = 898
Semi-pacca = 625
Kacha = 155
(ii) Straw Shed, Cattle Shed Sq. ft. Kacha = 286
Straw Shed = 263
(iii) Boundary Wall 5 ft height & 1 ft. length in running ft.
Pacca = 1078
Semi-pacca = 514
Kacha = 376
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
86
Sindh Water Sector Improvement Project
Description Unit Unit/Rate (Rs.)
Hand pump Number 7700
The compensation cost for privately owned structures is based on the valuation of structural assets
provided in the table above. Owners of privately owned structures shall be paid compensation for
replacement of their structures in full, regardless of the entitlement of the PAPs to the land in which the
affected structure is located and regardless of where they will rebuild these structures.
The details of structures and compensation due are given in Appendix D.
Entitlement: Transport Allowance
Standard Transport Allowance
A standard transport allowance shall be paid to each household owing assets in the CoI to cover
the cost of that household to shift their belongings to their new location where their new location is
within 10km of their existing location. This allowance shall be paid regardless of any other
assistance (i.e. this allowance shall be paid to households who will rebuild affected structures on
private land or government owned land). The standard transport allowance has been valued at
PKR 11,000 per household and shall cover two trucks to transport goods within a 10km radius.
This allowance has been calculated based on quotes of PKR 10,000 obtained from local
transporters in 2014 to use two trucks to transport goods up to 10 km.
Long Distance Transport Allowance
A long distance transport allowance is to be provided to any household who shall rebuild their
affect structures at a location which is greater than 10km from their current location. The long
distance transport allowance shall be calculated as PKR 1,100 per 1km of relocation distance. In
calculating the additional allowance, the relocation distance shall be rounded up to the nearest 10
km. Long distance transport allowances are detailed in Appendix D.5.
7.5 Loss: Community or Institutional Structures
7.5.1 Application: Entire Loss
7.5.1.1 Entitled Person: Affected Community or Institution
Entitlement: Reconstruction of Community or Institutional Structures
The community structures to be removed from within the CoI are comprised of one hand pump.
Reconstruction of this hand pump on the raised embankment shall be included within the civil works
contract so that it continues to be available for use.
The government structures are one police chowki, one irrigation room, and one hand pump. The
rehabilitation works shall require the demolition of these structures. Reconstruction of the structures shall
be included within the civil works contract.
7.6 Loss: Income
It is anticipated that the sub-project will make a positive impact on the economy of the area. A number of
employment opportunities will be created during the rehabilitation work, particularly for the unskilled labour.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
87
Sindh Water Sector Improvement Project
7.6.1 Application: Loss of Income from Commercial Structures
7.6.1.1 Entitled Person: Owner of Impacted Business
Entitlement: Livelihood Allowance
For those PAPs owning commercial structures within the CoI, a Livelihood Allowance shall be paid. This
allowance shall be equal to three times the monthly income of the household, or equal to the equivalent of
three months minimum wage in Pakistan (PKR 33,000 in 2016 - assuming 10% inflation from 2014 rates),
whichever is greater. This will be provided to support the affected families losing their sources of livelihood
in order to allow them to restore their business at a new location without any economic pressure.
This allowance is intended to compensate for any lost income during transition, relocation and
reconstruction of their businesses. There are five affected households involved in business activities in the
CoI (four shops and one otaq). See more details in Appendix D.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
88
Sindh Water Sector Improvement Project
This chapter describes the institutional roles and responsibilities associated with the implementation of this
RAP for the sub-project. An overview of the general institutional arrangements for WSIP is provided in
section 3.1.
The responsibilities of each party in the implementation of the RAP are summarised within the context of
the implementation schedule in Chapter 10.
8.1 Sindh Irrigation and Drainage Authority
SIDA are overall responsible for the implementation of this RAP through the Environmental Management
Unit and Social Cell. This includes disbursement of funds for compensation, permanent acquisition of land
identified in this RAP and vacation of the CoI prior to mobilisation of the contractor for Contract
WSIP/B1/GF/01. The AWB will assist SIDA for implementation of this RAP. Note that SIDA shall maintain
overall responsibility for any RAP implementation activities which may be delegated to other parties.
8.1.1 Environmental Management Unit and Social Cell
The Environment Management Unit (EMU) and Social Cell established within SIDA will be responsible for
all implementation activities within the RAP. While EMU and the Social Cell shall delegate a number of
these tasks to other parties (as detailed in the following sections), they shall maintain direct responsibility
for the following specific tasks:
Review this RAP
Translation and disclosure of this RAP
Establishment of the Grievance Redress Committee (GRC)
Settlement of any issues arising in the field
Referring issues which cannot be solved by the project team to the GRC
Preparation of final budget arrangement of funds through the AWB
Notification of PAPs on embankments
Verification of PAPs
Completion of file of each PAP
Preparation of relevant reports and preparation of final report on disbursement
Under taking on stamp paper by PAP and verification
Internal monitoring
Supervision of permanent land acquisition
SIDA shall oversee and monitor implementation of this RAP. A Social Organiser and two engineers from
the Ghotki AWB will ensure the implementation of the RAP and work closely with PIC field staff and the
contractor.
8.2 Ghotki Area Water Board
SIDA shall delegate responsibility for the following tasks to be implemented by the Ghotki AWB:
Direct liaison with the Board of Revenue for permanent land acquisition required for this sub-project
Resolution of any land acquisition issues and cases
8. Institutional Arrangements
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
89
Sindh Water Sector Improvement Project
Ensuring there is no further encroachment into the CoI following the cut-off date defined in this RAP.
This shall be achieved through the Assistant Manager for Social Mobilisation within the AWB.
The Social Mobilisation Team of the AWB shall assist SIDA in the following:
Disclosure of the translated RAP among the PAPs
Notification of PAPs on embankments
Information dissemination, awareness raising and liaison with affected communities.
Transfer of resettlement funds to Board of Revenue
Provide support to the contractor during the construction period in order to resolve any issues arising
from temporary land acquisition and minimise any delays to the construction progress.
Vacation of the CoI (following compensation payment by SIDA)
Ghotki AWB shall designate a Social Organiser and two engineers to be responsible for RAP
implementation tasks. These staff shall work closely with PIC field staff and the contractor, and shall be
supervised by SIDA.
Following the practice adopted by the Nara AWB for contract WSIP/B1/NC/02 where the establishment of
borrow areas was required, the Ghotki AWB shall depute the Social Organiser to assist the contractor with
day to day temporary land acquisition requirements. The two engineers shall work under oversight of
SIDA’s Sociologist/Participation Specialist and coordinate the Board of Revenue and land owners for the
completion of permanent land acquisition.
8.3 Board of Revenue
The Assistant Commissioner of the Ghotki District Board of Revenue shall be responsible for permanent
acquisition of land on behalf of the AWB. He shall acquire the land on behalf of the AWB following
procedures of the Land Acquisition Act (see section 2.2.2). The Assistant Commissioner also acts as the
Land Acquisition Officer.
The Assistant Commissioner shall also be responsible for the disbursement of funds to PAPs through cross
cheques during a public event. PAPs shall present the stamp paper to the Assistant Commissioner, who
shall verify the identity of the PAP, disburse the compensation through cross cheque and add his stamp to
the stamp paper, confirming disbursement of the compensation.
The funds shall be provided by the AWB.
8.4 Project Coordination and Monitoring Unit (PCMU)
The Project Coordination and Monitoring Unit (PCMU) shall be responsible for coordination of the
implementation of this RAP and for monitoring of implementation progress, assisted by the Monitoring and
Evaluation Consultants (M&EC). PCMU shall also oversee any acquisition of public or private land or
assets associated with the implementation of this sub-project.
PCMU shall undertake regular monitoring of progress in implementing this RAP to ensure timely actions
are taken in response to any issues experienced.
8.5 Monitoring and Evaluation Consultants
The M&EC are responsible for reviewing and clearing this RAP. Following this, they also have a role in the
implementation of the RAP as monitoring and evaluation is important tool for managers to determine the
status and success of any project. The M&EC will provide continuous feedback to SIDA and PCMU on the
implementation progress of this RAP, identify problems in implementation and suggest corrective actions.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
90
Sindh Water Sector Improvement Project
The purpose of RAP monitoring is to verify that:
Actions and commitments described in the RAP are implemented fully and on time,
Eligible affected people receive their full compensation entitlements within the agreed timeframe,
RAP actions and compensation measures are effective in sustainably enhancing (or at least restoring)
affected people’s living standards and income levels, Complaints and grievances lodged by PAPs are followed up and that where necessary, appropriate
corrective actions are taken up and implemented,
Progress of any community development activities or reconstruction/relocation of community structures
defined in the RAP
Performance of contractor in providing employment opportunities for PAPs, and
Payments for loss of income.
Monitoring
The M&EC shall monitor progress of implementation of this RAP against the following indicators:
Value of compensation disbursed against anticipated budget for each impact (refer to Chapter 9)
Status of compensation disbursement
Progress in acquisition of private land
Progress in vacation of the CoI
Status of restoration of livelihood for PAPs where income has been impacted
Grievances redress activities
Agreements reached and arrangements made between the contractor and PAPs for temporary
acquisition of assets (such as temporary land acquisition)
Entitlement Matrix in the context of the anticipated impacts.
The M&EC shall be responsible for monitoring performance of the implementing parties against these
indicators.
Evaluation
As part of their evaluation activities under this RAP, the M&EC shall evaluate the following within the sub-
project area:
Impact of construction activities in sub-project area in particular on PAPs and livestock
Success of livelihood restoration
Socio-economic impact and impact on the level of un-employment and household incomes amongst
PAPs and within the sub-project area
The evaluation of the success of the implementation of this RAP against objectives of the plan should be
completed by the M&EC within one year of completion of the civil works contract.
8.6 Project Implementation Consultants
The Project Implementation Consultants are responsible for the preparation of this RAP.
During construction, PIC shall be responsible for supervision of the contractor, including the arrangements
the contractor makes for the temporary acquisition of land required to complete his works.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
91
Sindh Water Sector Improvement Project
8.7 Contractor
The contractor appointed to implement this sub-project under Contract WSIP/B1/GF/01 shall be
responsible for all temporary land acquisition required for the completion of his works. This shall include the
mutual agreement with land owners for the provision of rent or actions in kind in exchange for the
temporary use of their land for the establishment of camps or borrow areas, as well as compensation for
loss of crops to land owners and sharecroppers.
The contractor shall prepare and keep signed agreements between the contractor and land owners for the
temporary use of private land, detailing monetary rent and/or acts in kind, agreed with the land owner in
exchange for the temporary use of his land. The agreements shall also state the condition of the land that
is to be handed over to the land owner following use by the contractor.
The contractor shall also be responsible for staff training, including training of migrant staff on cultural
sensitives within the local population.
8.8 Grievance Redress
8.8.1 Review of Social Task Force and Grievance Redress Committee Performance
on Previous Contracts
The Resettlement Action Plans prepared for Contracts WSIP/B1/NC/01 and WSIP/B1/NC/02 (both
implemented within the Nara AWB) included the establishment of a Social Task Force (STF) at AWB level.
The objective of the STF was to ensure that measures are taken in a timely fashion to prevent potential
grievances. STF was comprised of AWB, SIDA, PIC, and Board of Revenue. Initially, during the execution
of Contract WSIP/B1/NC/01 and WSIP/B1/NC/02 the STF did not formally meet at regular periods.
However, the issues on which the STF were intended to advise upon were dealt with by AWB, including
land acquisition. Therefore, it has been decided that a STF shall not be established for implementation of
contract WSIP/B1/GF/01.
Formal establishment and meetings of the GRC were rarely undertaken. Examples of grievances during
the execution of these contracts were as follows:
Delay in payment for permanent land acquisition
Delay in payment of compensation to PAPs
Arrangements for borrow material by contractor
These grievances were resolved by individual members of the GRC to the satisfaction of the complainant,
but rarely as a united committee. Timely establishment of the GRC may have made resolution of these
grievances more efficient.
8.8.2 Grievance Redress Mechanism
The main objective of the grievance redress mechanism will be to arrive at mutually acceptable solutions to
grievances through free and open discussions. It will also provide a forum to people who might have
objections or concerns about their compensation to raise their objections and through conflict resolution
address their issues adequately. The project will establish a grievance redress committee (GRC) at a sub-
project level for the affected persons in line with the Social Impact Management Framework for WSIP. The
GRC shall meet at least quarterly to consider outstanding grievances.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
92
Sindh Water Sector Improvement Project
Grievance redress arrangements should be disseminated to the PAPs with clear information on where and
how grievances can be submitted, as well as the process for grievance redress, both at the subproject level
and through the court system.
The committee is responsible for the facilitation of resolution of disputes and grievances which may arise
during the implementation of this plan. The committee shall be formed of the following members:
Table 8.1: Grievance Redress Committee
Representative Members
Assistant Commissioner Chairman
Project Director, WSIP Member
Land Acquisition Collector Member
Sociologist/Participation Specialist, SIDA Member (Secretary)
Local dignitary Member
2 nr. Affected Person Representatives Members
Any grievance which cannot be resolved at a project level (i.e. by the contractor, PIC, SIDA or AWB) shall
be referred to the GRC. If the affected person is not satisfied with the decision of GRC, he/she, as a last
resort may submit the complaint to the court of Law. The committee will establish community complaints
register at sub-project sites. Committee will register and file any, grievance redress cases and would bring
these into the notice of Project Director. Revenue department will be involved for land acquisition and crop
compensation.
Grievances may be submitted to the GRC through any of the following means:
By individual(s) through the complaints registrations system on the WSIP website
(http://www.wsip.com.pk/Complaint/)
These complaints are submitted directly to the Managing Director of SIDA and the PMC/A Team
Leader and will be forwarded to the GRC chairman
By individual(s) in writing directly to the GRC chairman at the following address:
By individual(s) in person at the Ghotki AWB office
Director AWB shall forward grievances to the GRC chairman
Referred to GRC chairman by the Contractor or PIC (for grievances submitted to the Contractor or PIC
in the first instance but that cannot be not resolved by them)
The following standards shall underpin the proposed systems for handling any submitted grievances:
All grievances received will be formally recorded by the GRC chairman in a Grievance Register to be
maintained by the GRC.
A written acknowledgement shall be issued by the GRC chairman to the affected person within three
working days of receipt.
The GRC shall meet to discuss the Grievance within 5 working days of receipt. Attendees, minutes of
the meeting and actions arising from the meeting shall be entered into the Grievance Register.
If required, a second meeting of the GRC shall be held within 20 working days of receipt of the
grievance, thus allowing 15 working days for deliberation by the GRC, receipt of legal advice and
undertaking of investigations as may be necessary. Attendees, minutes of the meeting and actions
arising from the meeting shall be entered into the Grievance Register.
The final decision of the GRC (arising from the first or second meeting) shall be recorded in the
Grievance Register, including any further actions to be taken and both shall be communicated to the
affected person in writing within 30 days of receipt of the grievance.
If a final decision cannot be reached by the GRC within 30 days, the findings of the GRC to date shall
be communicated to the affected person in writing. The GRC shall agree upon a timeframe for
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
93
Sindh Water Sector Improvement Project
resolution of the grievance which shall be recorded in the Grievance Register and shall also be
communicated to the affected person in writing within 30 days of receipt of the grievance.
Attendees, minutes and actions arising from any subsequent meetings shall continue to be entered into
the Grievance Register, and the affected person shall be updated, in writing, on findings at 30 day
intervals.
If, at any time, the affected person is not satisfied with the decisions or findings of the GRC, they may
register their complaint in a court of law.
All costs incurred by the GRC shall be borne by SIDA.
8.9 Organisation Structure
The organizational chart for the implementation of the Resettlement Action Plan is shown below:
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
94
Sindh Water Sector Improvement Project
Figure 8.1: Organisational Structure for RAP Implementation
8.10 Training and Capacity Building
Training and capacity building of all primary and secondary stakeholders is an important part of the sub-
project implementation and will be an integral part of the sub-project. It helps to create and develop a
similar approach among the project stakeholders. For this purpose, a training programme of two days is
planned to impart training to all relevant officials of AWB and representatives of affected people. The
amount of Rs. 100,000 has been provided in the budget for two days training. The training cost will be
borne by the project proponent. The training will be provided by training specialists. During the training
session following topics will be covered (sections 8.10.1 to 8.10.4):
8.10.1 Principles and Procedures of Involuntary Resettlement
World Bank policy on involuntary resettlement.
Identification of PAPs.
Consultations with affected persons.
8.10.2 Consultation and Participation
Training regarding sub-project objectives and its impacts will be given to the expected stakeholders. All
expected impacts will be discussed with the community. How they will be satisfied and their trust gained
will be ensured.
Project Implementation
Consultants
Revenue Rep: SIDA & GoS
AWB (Ghotki Canal)
Project Director (WSIP-1)
Contractor
PCMU
Managing Director (SIDA)
M&E (Consultants)
GRC
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
95
Sindh Water Sector Improvement Project
8.10.3 Grievance Redress
Training shall be provided to the GRC in order to brief them on the requirements of this Resettlement
Action Plan, World Bank policy and the Pakistan legal framework under which the committee must act.
8.10.4 Skill Development
In addition to the training of the implementation stakeholders, SIDA shall complete skills development
training to PAPs. Technical skill development programme for PAPs is considered essential as their regular
sources of livelihood and income generation will be directly affected as a result of rehabilitation works.
Furthermore, in the contemporary world, the Sustainable Livelihoods Approach (SLA) is strongly perceived
as a way to improve understanding of the livelihoods of poor people. It draws on the main factors that affect
poor people's livelihoods.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
96
Sindh Water Sector Improvement Project
This section provides the compensation and assistance cost estimates as well as costs for administration
of the RAP.
The details of estimated budget are given in the following table.
9. Budget
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
97
Sindh Water Sector Improvement Project
Table 9.1: Budget for Implementation of the RAP
Type of Loss Application Entitled Person Entitlement Unit Quantity Unit Cost (PKR) Cost (PKR)
A: Compensation
Land (Agricultural)
Permanent Loss
Legal owner with valid title
Compensation as per Land Acquisition Act
Acres of impacted land 9.925 1,150,000 11,413,750
PAPs without title Crop compensation Acres of impacted land 307.6 74,000 22,762,400
Temporary Loss
Legal owner with valid title Rent at market rate
Acres of impacted land
10 To be paid by Contractor Tennant or PAP without title Crop compensation
Acres of impacted land
Land (Residential or commercial) Entire Loss
PAPs without title Alternative site Affected Households 55 0 0
PAPs living below poverty line Low Income Allowance
Affected Households 84
Varies - refer to Appendix D 1,903,000
Privately owned Structures Entire Loss Owner of structure
Compensation for Replacement of Structures
Affected Households 87
Varies - refer to Appendix D 21,914,460
Standard Transport Allowance
Affected Households 78 11,000 858,000
Long Distance Transport Allowance
Affected Households 9
Varies - refer to Appendix D 693,000
Community Structures Entire Loss Affected community Reconstruction of structure
Number of structures 1 Covered under civil works contract
Government Structures Entire Loss Affected institution Reconstruction of structure
Number of structures 3 Covered under civil works contract
Income Loss of Income from Commercial Structures
Owner of impacted business Livelihood allowance
Affected Households 5
Varies - refer to Appendix D 178,200
Sub-total (A) 59,722,810
B: Training Cost
Training Cost - - Lump Sum - 100,000 100,000
Sub-total (B) 100,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
98
Sindh Water Sector Improvement Project
C: Monitoring and Evaluation
Monitoring and Evaluation - - Lump Sum - 2% of (A) 1,194,456
Administrative Costs - - Lump Sum - 3% of (A) 1,791,684
Sub-total (C) 2,986,141
D: Contingencies
Contingency - - - - 5% of (A) + (C) 3,135,448
GRAND TOTAL 65,944,398
US$ (US$ = PKR 100) 659,444
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
99
Sindh Water Sector Improvement Project
10.1 Introduction
The following implementation schedule is proposed to ensure implementation of this RAP shall be
complete prior to mobilization of contractor for works under Contact WSIP/B1/GF/01.
The implementation schedule reflects the sequencing and duration of activities planned, the schedule
recognizes that activities will be taking place simultaneously and allows, within reason, for staggered starts.
The schedule proposed shall ensure clearance of CoI and necessary land acquisition can be complete
prior to mobilization of the contactor.
10.2 Implementation Schedule
The basic steps for preparation and implementation of this RAP are summarized in Table 10.1. The
responsibility for each step is also detailed within. Within the schedule, the time at which Contract
WSIP/B1/GF/01 is awarded is referred to as month 0.
10. Implementation of RAP
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
100
Sindh Water Sector Improvement Project
Table 10.1: RAP Implementation Schedule
# Activity Responsibility Month
-9 -8 -7 -6 -5 -4 -3 -2 -1 0 1-24 24+
1 Preparation and Revision of RAP PIC
2 Review and Approve of RAP SIDA/M&EC X
3 Coordinate/Monitor RAP Implementation PCMU
4 Prevent Encroachment into CoI AWB
5 Establish Grievance Redress Committee SIDA X
6 *Supervision of Land Acquisition SIDA
7 *Resolution of Land Acquisition Issues AWB
8 *Notification of LA to Board of Revenue (BoR) AWB X
9 *Section 4 Notification under LAA BoR X
10 *Surveys and Setting Out BoR X
11 Translation and Disclosure of RAP SIDA X
12 *Section 5 Notification under LAA BoR X
13 *Period for Objections to LA PAPs
14 *Period for Investigation into Objections to LA BoR
15 Finalisation of Resettlement Budget SIDA X
16 Notification of PAPs SIDA
17 *Review of Objections to LA by Commissioner BoR X
18 Transfer of Funds to BoR AWB X
19 *Section 6 Declaration under LAA BoR X
20 *Preparation of Land Acquisition Plan (map) BoR
21 Disbursement of Compensation to PAPs BoR
22 *Section 9 Notification under LAA BoR X
23 Vacation of PAPS from CoI AWB
24 *Period to Register Interest in Land PAPs
25 *Section 11 Enquiry under LAA (if required) BoR X
26 Period for Grievance Redress GRC
27 *Acquisition under Section 12 of LAA BoR X
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
101
Sindh Water Sector Improvement Project
# Activity Responsibility Month
-9 -8 -7 -6 -5 -4 -3 -2 -1 0 1-24 24+
28 *Handover of Land to AWB BoR X
29 Mobilisation of Contractor - X
30 Temporary Land Acquisition Contractor
31 Assist in Temporary Land Acquisition AWB
32 Supervision of Contractor PIC
33 Internal Monitoring SIDA
34 External Monitoring M&EC
35 Evaluate RAP M&EC
* = Action required for permanent land acquisition at Bakhoro Cross-Regulator; LA = Land Acquisition; LAA = Land Acquisition Act: ? = If required
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
102
Sindh Water Sector Improvement Project
10.3 RAP Implementation Detail
The methodology for the implementation of the RAP as outlined in Table 10.1 is discussed in the following
sections. SIDA shall maintain overall responsibility for implementation of the RAP.
10.3.1 General
10.3.1.1 Preparation of RAP
The RAP has now been completed by PIC and is to be reviewed and approved as per the following
section. Any necessary revisions are to be agreed and incorporated by PIC.
10.3.1.2 Review Approval of RAP
This RAP shall be submitted in the first instance to Project Director SIDA for review. SIDA shall then
forward this to M&EC for their review, and approval (following any agreed revisions).
10.3.1.3 Internal and External Monitoring
SIDA shall carryout internal monitoring, and M&EC shall complete external monitoring, from the point at
which the RAP is approved until completion of the civil works. Further details are provided in Chapter 11.
Both parties shall monitor the land acquisition and compensation and vacation of PAPs.
10.3.1.4 Translation and Disclosure of the RAP
SIDA shall translate this RAP and ensure the translated version of this RAP remains available to the public
at locations within the sub-project area (refer to section 2.3.1.3).
10.3.1.5 Establish Grievance Redress Committee
SIDA shall establish the Grievance Redress Committee as detailed in Chapter 8.
10.3.1.6 Evaluate the RAP
Following completion of Contract WSIP/B1/GF/01, the M&EC shall evaluate the success of this RAP.
Further details are provided in Chapter 11.
10.3.2 Land Acquisition
10.3.2.1 Supervision of Land Acquisition
SIDA shall remain active in the supervision of land acquisition. Initially they shall ensure that the Board of
Revenue has been notified and the acquisition process has commenced according to the LAA.
10.3.2.2 Notification of Land Acquisition to Board or Revenue
The AWB shall notify the Board of Revenue (Ghotki District) of the permanent land acquisition
requirements and request the Board of Revenue to begin acquisition proceedings under the Land
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
103
Sindh Water Sector Improvement Project
Acquisition Act on their behalf. SIDA and the AWB shall provide all required information to the Board of
Revenue.
10.3.2.3 Section 4 Notification
The Board of Revenue shall issue a notification under section 4 of the LAA of intention to acquire land. The
notification shall be published in the official Gazette and displayed at a convenient and prominent location
close to the land to be acquired. It is also recommended that the AWB begin consultations with the land
owner(s) at this stage.
10.3.2.4 Surveys and Setting Out
Following the section 4 notification, officers of the Board of Revenue shall be permitted to enter the land to
be acquired to take any necessary measurements if required by the Board of Revenue.
10.3.2.5 Section 5 Notification
After any investigations required (section 10.3.2.4), the Board of Revenue shall issue a notification under
section 5 of the LAA stating the location and area of land to be acquired. The notification shall be published
in the official Gazette and displayed at a convenient and prominent location close to the land to be
acquired. The notification shall include the address to which any objections should be submitted.
10.3.2.6 Period for Objections to Land Acquisition
During this period, any person with an interest in the land, or who may be affected by its acquisition is
required to raise objections within 30 days of notification under Section 5 of the LAA. Objections shall be
submitted in writing to the address provided on the Section 5 notification.
10.3.2.7 Period for Investigations into Land Acquisition
The Board of Revenue shall provide any person who has submitted a written objection (within 30 days of
notification under Section 5 of the LAA) an opportunity for their objection to be heard, following which the
Board of Revenue shall make further enquires (if required) and shall submit the case to the Commissioner
along with their recommendation and details of enquires made.
10.3.2.8 Review of Objections by Commissioner
The Commissioner shall review any objections with are submitted by the Board of Revenue and make a
final decision as to any further actions required. The decision of the Commissioner shall be considered
final.
10.3.2.9 Section 6 Declaration
Following review of objections (if any) by the Commissioner, the Board of Revenue shall issue a
declaration under Section 6 of the LAA sating the following:
Location of land to be acquired
Purpose of acquisition
Area (size) of land to be acquired
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
104
Sindh Water Sector Improvement Project
Location that the plan (map of acquisition) is available for inspection
This declaration shall be published in the official Gazette.
10.3.2.10 Preparation of Land Acquisition Plan
Following the Section 6 declaration, the Board of Revenue shall mark out the land to be acquired and
prepare a plan (map) of the area to be acquired (if the plan has not already been prepared).
10.3.2.11 Section 9 Notification
The Board of Revenue shall place a notification on the land to be acquired stating the intention to acquire
the land and notifying those with an interest in the land, or an objection to the measurements given in the
section 6 declaration, that they must appear before the Board of Revenue at a time and place stated on the
notification.
10.3.2.12 Period to Register Interest in Land
Following notification under Section 9, all those with an interest in the land to be acquired (including co-
proprietor, sub-proprietor, mortgagee or tenant) are required to submit details of their interest (such as
details of any rent and income from the land in the last three years) to the Board of Revenue. A period of
no less than 15 days shall be allowed for people to register their interest.
10.3.2.13 Section 11 Enquiry
Should any objections be received during the 15 days following notification under Section 9 the Board of
Revenue shall hold an enquiry to determine the true area of land, compensation due and to whom it is due.
If no objections are received, there shall be no need to hold an enquiry.
10.3.2.14 Acquisition under Section 12
If no objections are received within 15 days on the Section 9 notification, the Board of Revenue shall take
possession of the land. If objections are received, and an enquiry is held, the Board of Revenue shall file
their findings and notify interested people of the final award and then take possession of the land.
10.3.2.15 Handover of Land to AWB
Following acquisition under Section 12, the Board of Revenue shall handover the land to the AWB.
10.3.2.16 Temporary Land Acquisition
The temporary acquisition of privately owned land (if required) shall be arranged between the contractor
and the land owner. The contractor shall prepare and keep signed agreements for the temporary use of
private land, detailing monetary rent and/or acts in kind, agreed with the land owner in exchange for the
temporary use of his land. The agreements shall also state the condition of the land that is to be handed
over to the land owner following use by the contractor. The contractor shall make copies of these
agreements copies available at the request of SIDA or PIC.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
105
Sindh Water Sector Improvement Project
10.3.2.17 Assist in Temporary Land Acquisition
In recognition of the risk of delays resulting from inefficient temporary acquisition, an officer of the AWB,
with appropriate authority (delegated or otherwise), should be made available to the contractor, throughout
the entire construction period to assist in the resolution of temporary land acquisition issues.
10.3.2.18 Supervision of Contractor
PIC shall be responsible for supervision of the contractor, and shall require the contractor to submit signed
copies of agreements for temporary land acquisition wherever the contractor has used private land for the
completion of the works.
10.3.3 Payment of Compensation
10.3.3.1 Prevent Encroachment into the CoI
The AWB shall monitor the CoI and provide eviction notices to any person(s) who have arrived, or do
arrive, following the cut-off date provided in this RAP. The notice should inform the person(s) of the cut-off
data and inform them that they shall not be eligible for compensation or assistance under this RAP. A copy
of the grievance redress mechanism should also be provided to them.
10.3.3.2 Finalisation of Resettlement Budget
SIDA shall finalise the Resettlement budget, based on the findings of this RAP.
10.3.3.3 Notifications of PAPs
SIDA shall prepare a unique package for each project affected household which includes the following
information:
Inventory of losses of each PAP in the household
Compensation to be paid to each PAP in the household
The date, time and venue for the disbursement of compensation
Detailing the requirement to present their National Identity Card (NIC) and submit a copy of their NIC on
the date of disbursement.
Detailing the requirement to obtain a stamp paper from the local court confirming the PAPs identity.
For any PAP under the age of 18 or without a NIC, the PAP must provide an affidavit with photograph
signed by the head of local government.
The requirement to hold an open a bank account in order to receive compensation
Details of the Grievance Redress Mechanism
These packages shall be distributed to the PAPs no later than one month prior to the date of disbursement
of funds.
10.3.3.4 Transfer of Funds to Board of Revenue
Following finalisation of the budget, AWB shall transfer the resettlement funds to the Board of Revenue.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
106
Sindh Water Sector Improvement Project
10.3.3.5 Disbursement of Compensation to PAPs
Disbursement of compensation shall be carried out in public by the Board of Revenue. The identity of PAPs
shall be verified through his/her NIC (or signed affidavit in the case of eligible PAPs under 18 years of age)
and stamp paper. Following verification, payment of compensation shall be paid through a crossed cheque
to the name of the PAPs. Payments of less than PKR 5,000 may be made in cash.
10.3.3.6 Vacation of PAPs from CoI
PAPs shall be given two months from the date of disbursement of compensation to vacate the CoI (except
in the case of permanent land acquisition). AWB shall be responsible for vacating the CoI.
10.3.3.7 Period for Grievance Redress
The GRC shall be active to review any grievances received from the time at which PAPs are formally
notified. The GRC shall aim to resolve all grievances prior to mobilisation of the contractor.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
107
Sindh Water Sector Improvement Project
11.1 Introduction
The World Bank requires proper monitoring of implementation of the RAP and reporting on its
effectiveness, including the disbursement of compensation, effectiveness of public consultation and
participation activities. The objective of monitoring is to provide feedback on implementation of the RAP
and to identify problems and successes as early as possible to allow timely adjustment to implementation
arrangements. For these reasons, RAP monitoring and evaluation activities should be adequately funded,
implemented by qualified specialists and integrated into the overall project management process.
Monitoring involves periodic checking to ascertain whether activities are progressing as per schedule, while
evaluation is essential in reviewing the performance of the RAP against its original objectives. RAP
implementation will be monitored both internally and externally.
SIDA being the proponent of the sub-project will be responsible for internal monitoring through the EMU
and the Social Cell will prepare monthly progress report on the implementation of this RAP. In addition,
SIDA shall engage a Resettlement Specialist to provide necessary technical assistance and monitor the
implementation the RAP activities. The monitoring framework is given in Table 11.1.
11.2 Monitoring and Evaluation
Monitoring and evaluation is an important tool for managers to determine the status of any project. Only
through a well-planned and organized system of monitoring and evaluation, the progress against the given
targets for various components of a development project can be achieved. Such evaluation is possible
through the review of quarterly and annual reports.
The purpose of RAP monitoring is to verify that:
Actions and commitments described in the RAP are implemented fully and on time,
Eligible affected people receive their full compensation entitlements within the agreed timeframe,
RAP actions and compensation measures are effective in sustainably enhancing (or at least restoring)
affected people’s living standards and income levels, Complaints and grievances lodged by PAPs are followed up and that where necessary, appropriate
corrective actions are taken up and implemented,
If necessary, changes in RAP procedure are made to improve delivery of entitlements to PAPs,
Progress of community structures reconstruction,
Income restoration of PAPs;
Progress of liaison with construction contractor for employment opportunities for PAPs, and
Payments for loss of income.
11.3 Internal Monitoring
The RAP includes indicators and benchmarks for achievement of the objectives under the program, which
can be categorized as under:
Process indicators, which include project inputs, expenditures, staff deployments etc;
Output indicators are results in terms of numbers of affected persons compensated and mitigated,
additional assistance provided etc; and,
11. Monitoring and Evaluation
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
108
Sindh Water Sector Improvement Project
Impact indicators related to the long-term effects/benefits of the sub-project on people’s lives in the sub-
project affected area.
The first two types of indicators, related to process and immediate outputs and results, will be monitored
internally by SIDA. This information will be collected from the sub-project site and assimilated in the form of
a monthly progress report to assess the progress and results of RAP implementation, and adjust the work
progress, where necessary, in case of any delays or problems. Specific activities under RAP
implementation that will be monitored are the following:
Information campaign and consultation with PAPs
Land acquisition
Compensation for affected structures
Status of compensation disbursement
Status of restoration of livelihood employment opportunities for PAPs
Grievances redress activities
Sub-project employment
Field offices of SIDA will be responsible for monitoring the day-to-day RAP activities of the sub-project. A
performance data sheet will be developed to monitor the sub-project at the field level. Monthly reports will
be received from the concerned quarters.
Field level monitoring will be carried out through;
Review of census information for all PAPs.
Consultation and informal interviews with PAPs.
Key informant interviews
Community public meetings and
In depth case studies
Monthly and quarterly reports will be submitted by the field offices and SIDA will be responsible for overall
monitoring at sub-project level.
11.4 External Monitoring and Evaluation
M&EC shall be responsible for external monitoring of the RAP for this sub-project and monitoring of their
implementation. They shall review and clear the RAP. The M&EC shall provide continuous feedback to
SIDA, via PCMU, on the sub-project’s performance and impact of its various components so that corrective actions could be taken in a timely manner. The M&EC activities are likely to cover:
Any acquisition of public and private land and assets.
Agreements reached and arrangements made for temporary acquisition of assets (such as temporary
land acquisition).
Impact of construction activities in sub-project area in particular on population and livestock as part of
the evaluation of the RAP implementation
Socio-economic impact and impact on the level of un-employment and household incomes in the sub-
project areas as part of the evaluation of the RAP implementation
Restoration of livelihoods as part of the evaluation of the RAP implementation
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
109
Sindh Water Sector Improvement Project
11.5 Monitoring Framework
SIDA will be responsible for implementation of RAP and will prepare monthly progress reports on RAP
activities and consequently submit these to the WB for review.
Table 11.1: Monitoring Framework
Aspect Indicator Verification
Affected Persons are compensated in a fair and mutually accepted manner for their damages by the project authorities.
The PAPs are correctly identified. List of PAPs in resettlement plan
List of PAPS updated by the SIDA staff and concerned AWB.
Affected structures correctly recorded for compensation
List of PAPs in resettlement plan
List of PAPS with affected structures updated by SIDA staff and concerned
AWB
Compensation / assistance for damaged structures is paid based
upon on replacement cost
Receipts of payments made to project affected persons
Gender/Vulnerable Gender /Vulnerable are correctly identified.
List of gender/vulnerable and their compensation is calculated according
to World Bank Policy.
Loss of community structures Affected structures correctly recorded for reconstruction /
relocation
Community hand pumps replaced on embankments
Grievance Mechanism is in place Social Complaint Register for checking Grievance Committee is
in place
Social Complaint Register:
Consultation with affected persons during internal and external
monitoring
Resettlement Action Plan is effectively implemented
Staff training according to the monitoring plan
Training reports including list of trainees and types of training
The skill and knowledge acquired during the training are effectively
employed
Internal monitoring record.
External monitoring visit reports
Level of interaction and participation of stakeholders.
Type of expertise and level of input and output of such expertise.
Stakeholders’ suggestion incorporated.
Social and Resettlement Expertise.
Local employment on the construction contract
Number of PAPs employed as unskilled labourers
Contractor’s employment records
Number of PAPs employed as skilled labourers
Local unskilled labourers by FO area (Ghotki AWB)
Local skilled labourers by FO area (Ghotki AWB)
Local unskilled labour employed form outside Ghotki AWB
Local skilled labour employed form outside GhotkiAWB
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
110
Sindh Water Sector Improvement Project
Appendix A. Organization Chart of PIC Social Team ________________________________________________ 111
Appendix B. Additional Details of Survey Participants & Consultations __________________________________ 112
Appendix C. Survey Questionnaires and Data Collection Tools ________________________________________ 118
Appendix D. Details of Project Affected Persons and Assets __________________________________________ 134
Appendix E. Details of Affected Farmers _________________________________________________________ 154
Appendix F. Grass Root Consultations ___________________________________________________________ 156
Appendix G. Details of Asset Valuation ___________________________________________________________ 161
Appendix H. Deh Maps _______________________________________________________________________ 170
Appendix I. Corridor of Impact _________________________________________________________________ 172
Appendix J. Pictorial View ____________________________________________________________________ 189
Appendix K. Relocation Plans __________________________________________________________________ 194
Appendices
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
111
Sindh Water Sector Improvement Project
The organisation structure of the team completing this RAP is detailed below:
Appendix A. Organization Chart of PIC Social Team
Team Leader Guy Jones
Deputy Team Leader Khadim Ali Memon
Sociologist Nadir Shah
Female Interviewer Salma Memon
Sr. Sociologist M. Raheem Junejo
Jr. Sociologist Mujeeb-ur-Rehman
Jr. Sociologist Muhammad Juman
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
112
Sindh Water Sector Improvement Project
B.1. Detail of Officials Participated in Field Surveys
List of Officials Participating in Field Surveys
Sr. No.
Name Designation Organization Contact No.
B.1.1. List of SIDA Officials
1 Sajan Khan Acting Manager CR AWB 0333-7213384
2 Mohammad Younis AMSM AWB 0302-3086596
3 Ali Bux Mahar AEN Irrigation Department 0300-3117113
4 Abdul Majeed Naich Sub Engineer Irrigation Department 0302-3158152
5 Imtiaz Ali Assistant Manager (SM) AWB 0302-9722025
6 Saeed Ahmed Dahri Assistant Engineer SIDA 0302-3294485
7 Sadaruddin Mahar Quantity Surveyor SIDA 0301-3822156
8 M. Anwer Soomro Assistant Engineer AWB 0300-3136323
9 Ali Murad Mangi SDO AWB 0300-3126795
10 Ali Hassan Kolachi Daroga AWB 0302-3682488
11 Mohammad Bukhsh Butto Canal Assistant AWB 0333-7242393
12 Imdad Ali Mirani Daroga AWB 0300-3264773
13 Shah Nawaz Mazari Baildar AWB 0302-7949665
14 Sikiandar Ali Malik Baildar AWB 0301-3678602
15 Sain Shah Baildar AWB 0307-6347030
B.2. List of Officials Contacted during survey Sr. No.
Name Designation Organization Contact No.
List of Other Government Department Officials Contacted
1 Habib Rehman Narejo Directorate of Fisheries DD Fisheries 0300-3076840
2 Abdul Majeed Chachar Directorate of Fisheries DD Fisheries 0333-2672147
3 Subhan Ali Revenue Assistant Commissioner 0301-8254425
4 Muhammad Saleem Revenue Supervisor 0300-3245638
5 Hidayatullah Chajro DG Agri-Extension DG Agri-Extension 022-9200060
6 Wali Muhammad Soomro Agriculture Extension Deputy Coordinator IPNM 0323-3944390
7 Tauqeer Ahmad Shaikh Agriculture Extension Agriculture Officer 0300-3057458
8 Ghulam Mustafa Nangraj Agriculture Extension PRO 0300-3036689
9 Mushtaq Ahmed Memon Sui Southern Zone Hyderabad Senior Executive -
10 Amanullah Laghari Sui Southern Zone Hyderabad Field Engineer -
11 Riaz Ahmed Dayo Agriculture Ghotki Executive District Officer 0300-9316898
12 Aftab Ahmed Soomro Public Works Department Director 022-9200087 0300-3210121
Appendix B. Additional Details of Survey Participants & Consultations
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
113
Sindh Water Sector Improvement Project
13 Anwar Ali Siyal AWB Ghotki Director 0333-7155598
14 Mr. Tunveer Hussain Shah Education Works Department Sr. Engineer -
15 Amir Azam Wasan Education Works Department Executive Engineer 0301-3362456
16 ShahNawaz Irrigation Department Baildar Ghotki -
17 Zulfqr Ali Shah Police Department DIG Sukkur -
18 Zulifqar Kilyar Police Department ASP Hyderabad -
B.3. Contact Detail of Board of Revenue Sr. No.
Name Designation Organization Contact No.
1 Tahir Rauf Choudary Assistant Commissioner Revenue 0321-8800015
2 Abdul Rashed Golo PA (Deputy Commissioner) Revenue 0307-3260044,0300-3125307
3 Zamir Ahmed Kalhoro Office Assistant Revenue 0300-3196926
4 Rafaqat Hussain - Revenue 0300-6755007
5 Nasir Ahmed Khalidi - Revenue 03003178872
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
114
Sindh Water Sector Improvement Project
B.4. Meeting with Consultants Regarding Program Tendering Documents for Ghotki Feeder Canal
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
115
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
116
Sindh Water Sector Improvement Project
B.5. Grass root stakeholders Consultations
Sr. No.
Name Designation Contact No.
A. Ghotki Feeder Canal
1 Mohammad Adrees Mazari Owner 0333-8225081
2 Allahi Bux Owner 0307-3136640
3 Ghulam Hassan Owner 0334-7317777
4 Ghulam Rasool Mazari Owner 0301-2942273
5 Miran Bux Owner 0333-7247250
6 Sadam Husssain Owner 0344-3194028
7 Mohammad Iqbal Mazari Owner 0334-4176082
8 Shahbaz Ali Shah Owner -
9 Mohammad Hassan Chacher Owner 0333-7580705
10 Imtiaz Ali Owner 0334-2708214
11 Luqman Ali Khan Tenant -
12 Asif Ali Khan Tenant -
13 Rais Gulan Owner -
14 Tahir Solongi Owner 0333-7241048
15 Abdul Ghafoor Tenant 0333-3257982
16 Bashir Ahmed Tenant 0334-5728939
17 Allah Wadyio Solongi Tenant 0346-5772831
18 Ghafar Malik Owner -
19 Piyaro Khan Mahar Owner -
20 Dado Khan Chandio Tenant 0303-2710381
21 Sahib Khan Tenant 0300-3546512
22 Abdul Aziz Chandio Owner 0301-5233668
23 Dil Ber Hussain Khokhar Tenant 0303-3699017
24 Rasool Bux Mirani Owner 0343-3988564
25 Imdad Ali Mirani Tenant 0300-3264773
26 Ali Hassan Tenant 0346-6958490
27 Imam Bux Owner 0333-7253155
28 Abdul Majeed Owner 0332-2701335
29 Shahzado Chujan Tenant 0333-7242115
30 Fakhar Din Soomro Tenant 0333-7329585
31 Pathan Malik Tenant -
32 Arabi Malik Owner 0303-5237881
33 Mathan Khan Tenant 0345-5933381
34 Sikandar Ali Abro Tenant -
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
117
Sindh Water Sector Improvement Project
Sr. No.
Name Designation Contact No.
35 Riaz Ahmed Pitafi Tenant -
36 Amanullah Gill Tenant -
37 Mohammad Yousif Mazari Tenant -
38 Mohammad Ishfaq Kosh Owner 0333-7242106
39 Abdul Majeed Kosh Tenant -
40 Abdul Rehman Kosh Tenant -
41 Kamal Din Supio Tenant -
42 Jam Munir Ahmed Dhar Owner -
43 Abdul Saleem Malik Tenant -
44 Dakan Khan Kosh Tenant -
45 Hazar Khan Malik Tenant -
46 Abdul Jabar Soomro Tenant -
47 Rustam Ali Lakhan Tenant -
48 Molla Bux Tenant -
49 Noor Mohammad Chandio Tenant -
50 Sultan Ahmed Sheikh Tenant -
B.6. Names of Sample Surveyed Villages Names 0f Sample Villages
Sr.# Name of Village Name of Canals Location (RD)
1 Natho Khan Mazari Ghotki Feeder Canal Head (IP)
2 Jahan Mohammad Mazari Ghotki Feeder Canal RD11+000 (IP)
3 Ghalo Khan Chachar Ghotki Feeder Canal RD 22+000 (IP)
4 Khohi Malik Ghotki Feeder Canal RD 17+000 (NIP)
5 Rais Hulter Chachar Ghotki Feeder Canal RD 27+100 (IP)
6 Punhal Khan Mazari Ghotki Feeder Canal RD 29+000 (NIP)
7 Mureed Shakh Ghotki Feeder Canal RD 44+250 (NIP)
8 Saeed Abad Minrani Ghotki Feeder Canal RD 47+800 (IP)
9 Mohammad Azeem Bheyo Ghotki Feeder Canal RD 50+000 (NIP)
10 Tahir Solongi Ghotki Feeder Canal RD 72+000 (IP)
11 Mohammad Azeem Chandio Ghotki Feeder Canal RD 110+000 (IP& NIP)
12 Mandus Khan Mazari Ghotki Feeder Canal RD 120+500 (IP)
13 Haji Allah Jawayio Mochi Ghotki Feeder Canal RD 122+000 (NIP)
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
118
Sindh Water Sector Improvement Project
ASSETS INVENTORY CENSUS QUESTIONNAIRE
Water Sector Improvement Project (WSIP)
SOCIAL AND ENVIRONMENT ASSESMENT STUDY
ID.No. _____________________
1. Location Name of Distry /Minor: _________________________________ 1.2 RD:______________________
2. IDENTIFICATION 2.1 Name of Affected Person: _________________________________________________________
2.2 Father’s Name: _________________________________________________________
2.3 Respondent NIC No:_____________________________________________________
2.4 Permanent Address of the Respondent:
Village: ___________________ Sub-Village_______________ Town_______________
Tehsil________________________District:_______________________________ ____
2.5 Category of Respondent: (Tick relevant)
1 Resident Land Owner 2 Absentee Land Owner 3 Tenant
4 Business Owner Operator 5 Business Tenant Operator 6 Encroacher
7 Squatter/ Informal Settlers 8 Other (Specify)______________
2.6 Demographic Profile of Respondent (Children up to 10 yrs (#): M___, FM ___=T______)
Sr.
No.
Relationship
with Respondent
(See codes)
Sex
Male=1
Female=2
Age
(Yrs.)
Education
(See Codes)
Name of Business/
Occupation (See Codes)
Income from Business/
Occupation (Rs. / Annum) Health
Condition Main Secondary Main Secondary
1 SELF
2
3
4
5
6
7
8
9
10
Demographic Codes: a) Relationship:1=Self, 2=Wife, 3=Son, 4=Daughter, 5=Father, 6=Mother, 7=Brother, 8=Sister, 9=Grand Father, 10=Grand
Mother, 11=Sister in Law, 12=Nephew, 13=Father-in-Law, 14=Mother- in- Law, 15=Niece, 17=Uncle, 18=Aunty, 19=other
b).Sex: 1=Male, 2=Femalec).
c) Education: 1= Primary 2= Middle 3= Metric, 4= Intermediate, 5= BA/BSc, 6= MA/MSc, 7=LLB, 8=Engineer, 9=MBBS, 10=Technical
Diploma, 11=Dars-e-Nizami, 12=Can Read Quran, 13= Can Insert Signatures, 14= Illiterate d).Occupations: 1=Agriculturist, 2=Shopkeeper, 3= Trader, 4= Govt. Servant, 5=Private Servant, 6=Timber Labor, 7=General Labor, 8=Livestock, 9=Fishing,
10=Driver, 11=Health Related, 12=Educator/Teacher, 13=House-Maid, 14= House Wife, 15=Gone Abroad, 16=Gone out City within Pakistan
e) Health: 1= Good, 2= Average, 3= Poor
3. DETAIL OF AFFECTED PROPERTY
3.1 Type of Affected Property (a) Land (b) Structure (c) Land & Structure
3.2 Offset from the Outer Edge of Existing RoW _________________________ Ft.
3.3 Located At (RS / LS) ________________
3.4 In case of affected land provide following details:
Type of Land Total Land Owned Affected Land
Appendix C. Survey Questionnaires and Data Collection Tools
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
119
Sindh Water Sector Improvement Project
Acre
(within and outside this village) Width (ft.) Length (ft.)
a) Agriculture
b) Commercial
c) Residential
d) Grazing Land
e) Forest Land
f) Wasteland
g) Others (specify)
3.5 If Structure, specify category of Structure: (tick relevant) (a).Commercial________ (b).Residential____________ (c).Otaq (Guest House)___________
3.6 Information about Commercial Structures:
Structure Size (ft)
Type of structure
(codes) Estimated
cost (Rs.)
Year of
construction
Affected structures
(ft.)
Ownership
documents
Yes-----No--- W L Roof Wall Floor
Shop
Cabin
Adda
Other
3.7 Information About Residential Structure:
Structure Sr.
No
Size (ft) Type of Structure Estimated
cost (Rs.)
Year of
construc-
tion
Similar
const. cost at
present (Rs.)
Affected
structures
(ft) (WxL)
Owners
hip
status W L Roof Wall Floor
Living
Rooms
1
2
3
4
Kitchen 1
2
Bathroom/
Latrine
1
2
Shed
(Animal)
1
2
Other 1
2
Types of Structures (codes)
Walls: 1= Bricks + Cement + Cement Plaster 2= Bricks+Cement+Mud Plaster 3= Bricks+Mud+Mud Plaster 4= Mud Masonry
Roofs: 1= RCC 2= RBC 3=Tiles+T.Irons+Girders4= Tiles+Wooden Planks 5= Asbestos/ Iron Sheets 6= Mud+Wood7=Mud+Thatched
Floors: 1= Mosaic 2= Concrete with Plaster 3= Bricks+Cement4= Mud
3.6 Details about Shareholders, if any:
Sr.No. Name Relationship with
Respondent Share in % age
Document Available
(Yes/No)
1.
2.
3.
4.
5.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
120
Sindh Water Sector Improvement Project
3.7 Details about Affected Crops:
Sr. No. Crops Area Production
(Kgs)
Total Costs
(Rs.)
Qnty Sold
(Kgs)
Price
(Rs./40Kgs) Marla Kanal
1.
2.
3.
4.
5.
3.10 Details about other Affected Assets
Type of Asset No. Value (Rs.) When Purchased /
Installed (No. of Yrs.)
Peter Engine
Hand Pump/Donkey Pump
Electric Motor
Tube Well
Lined Watercourse
Other (specify)
4. COMPENSATION PREFERENCES
4.1 Do you have some other place to move? Yes________ No________
4.2 In case of Yes:
a) How far away from this place?__________________ (km)
b) Do you own this place? Yes______ No________
5. IN CASE OF TENANT
5.1 Name of Owner: ________________ Name of Occupation / Business _________
Av. Monthly Income (Rs.) ______________ Av. Monthly Rent (Rs.) ____________
5.2 Type of Tenancy a) Residential b) Commercial c) Agriculture Land
5.3 For how long you are at tenancy: ______________ Month _____________ Year
5.4 Have you made any investment: Yes_____________ No ________________
5.5 If yes, Provide following details:
Structure Size (ft) Estimated Cost (Rs.) Year of
Construction
Cost for Similar
Replacement (Rs.) W L
House (Rooms)
Shop
Cabin
Other(specify)
7. COMMENTS / OBSERVATIONS
7.1 General Remarks of the Respondents
_____________________________________________________________________________________________________________
_____________________________________________________________________________________________________________
General Observations of Interviewers _____________________________________________________________________________________________________________
_________________________________________________________________________________________________
Name of Interviewer ____________________________ Dated_________________
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
121
Sindh Water Sector Improvement Project
Socio-economic and Poverty Assessment Baseline Survey Water Sector Improvement Project (WSIP)
SOCIO-ECONOMIC AND POVERTY ASSESSMENT BASE LINE SURVEY
IDENTIFICATION Case No. ___________________
1.1 Name of Respondent__________________________________ 1.2 Father’s Name_______________________________________
1.3 Respondent NIC No: ___________________________________________________
1.4 Permanent Address of the Respondent:
Village: _______________________Town ______________ Tehsil ________ _________District: ____________________________
1.5 Located At: Head / Middle / Tail (of the Distributary / Minor)
1.6 Category of Respondent: (Tick relevant)
1 Resident Land Owner 2 Absentee Land Owner 3 Tenant
4 Business Owner Operator 5 Business Tenant Operator 6 Encroacher
7 Squatter/ Informal Settlers 8 Other (Specify)_______________ 9
1.7 Demographic Profile of Respondent (Children up to 10 yrs (#): M___, FM ___=T______)
Sr.
No.
Relationship with
Respondent
(See codes)
Sex
Male=1
Female=2
Age
(Yrs.)
Education
(See Codes)
Name of Business/
Occupation (See
Codes)
Income from Business/
Occupation (Rs. /
Annum) Health
Condition
Main Secondary Main Secondary
1 SELF
2
3
4
5
6
7
8
9
10
Demographic Codes:
a) Relationship:1=Self, 2=Wife, 3=Son, 4=Daughter, 5=Father, 6=Mother, 7=Brother, 8=Sister, 9=Grand Father, 10=Grand
Mother, 11=Sister in Law, 12=Nephew, 13=Father –in-Law, 14=Mother- in- Law, 15=Niece, 16=Uncle, 17=Aunt, 18=Others
b) Sex:1=Male, 2=Female
c) Education:1= Primary 2= Middle 3= Matric, 4= Intermediate, 5= BA/BSc, 6= MA/MSc, 7=LLB, 8=Engineer, 9=MBBS,
10=Technical Diploma, 11=Dars-e-Nizami, 12=CanRead Quran, 13= Can Insert Signatures, 14= Illiterate
d) Occupations:1=Agriculturist, 2=Shopkeeper, 3= Trader, 4= Govt. Servant, 5=Private Servant, 6=Timber Labour, 7=General
Labour, 8=Livestock, 9=Fishing, 10=Driver, 11=Health Related, 12=Educator/Teacher, 13=House-Maid, 14= House Wife,
15=Gone Abroad, 16=Gone out City within Pakistan
e) Health Condition1=Good, 2=Average, 3=Poor
2. LANGUAGE SPOKEN__________________________________________
3. Agriculture 3.1 Agricultural Implements
Sr. No. Items Nos. Year of Purchase Present Value
1 Tractor
2 Fodder Cutter
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
122
Sindh Water Sector Improvement Project
3 Seed Drill
4 Reaper Machine
5 Thresher
6 Spray Pump
7 Scrapper
8 Others
3.2 LAND UTILIZATION
Land Acres Kanal Marla
Total Area owned
Total Cultivated Area
a. Area Under Rabi ( winter) Crops
b. Area Under Kharif (summer) Crops
Uncultivated Area
3.3 Cropping Pattern, Yield and Cost
Code Crops Area Sown Production
(Kgs)
Total costs
incurred (Rs.)
Price (Rs/40kg)
Acres Kanal
1 Rice
2 Sugarcane
3 Cotton
4 Maize
5 Millets
6 Potato
7 Fodder (kharif)
8 Vegetables(kharif)
9 Barley
10 Wheat
11 Oilseed
12 Fodder (Rabi)
13 Vegetables(Rabi)
14 Orchards
15 Other
3.4 Source of Irrigation 1. Canal 2. Tube well 3. Canal + Tube well 4. Lift Irrigation 5.Barani 6. Other.____________
3.5 Prevalent Land Rate
Residential __________________ Agriculture Land __________________
Cultivable Waste __________________ Other __________________
3.6 Land Rent (Rs./ Year) _______________
3.7 Tube well Water (Rs./Hr.)__________________
4. POSSESSION OF HOUSEHOLD ITEMS
Item No Value
(Rs.) Item No
Value
(Rs.)
Refrigerator Van/Pickup
Deep Freezer Gas Cylinder
Television VCR
Electric Fan Telephone/PTCL
Electric Iron Mobile
Radio/Tape Recorder Electric Water Pump
Bicycle Computer
Motor Cycle/Scooter Air Cooler
Car Other
5. AVERAGE MONTHLY EXPENDITURE ON FOOD AND NON- FOOD ITEMS (RS.)
a. Food Items Expenses b. Non-Food Items Expenses
Meat Bath Soap
Ghee Washing Soap
Sugar Gas Cylinder
Flour Fuel Wood
Legumes Kerosene Oil
Vegetables Other
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
123
Sindh Water Sector Improvement Project
Species
Tea Leaves
Others
c. Estimated Monthly Expenditure
1. Kitchen ________________________________ 2. Others ______________________________
5.. HOUSING CONDITIONS
5.1 Total Area of the House:____________________ Kanal_____________________ Marla
5.2 Year of Construction_______________
5.3 Present Value of the House (Rs.)___________
5.4 Type of Structure a) Katcha ______________b) Pacca ______________ c) Semi-Pacca _________________
6. ACCESS TO SOCIAL AMENITIES (TICK)
Social Amenities Available Satisfactory Non-Satisfactory No Access
Electricity
Gas
Water Supply
Telephone
Sewerage/Drainage
BHU
School
7. LIVESTOCK INVENTORY
Livestock No. Present Value (Rs.)
Buffaloes
Cows
Horse
Donkey
Camel
Sheep/Goat
Poultry
Other
9. WOMEN’S PARTICIPATION AND ROLE IN DIFFERENT HOUSEHOLD ACTIVITIES
9.1 Participation and Decision Making (Tick):
Activities Participation
Extent (%)
Decision Making
Extent (%)
Household activities
Child caring
Farm/Crop activities
Livestock rearing
Sale & Purchase of properties
Social obligations (marriage, birthday & other functions)
Local representation (councilor/political gathering)
10. PERCEPTION OF RESPONDENT FOR ACTION ASSOCIATED WITH THE PROJECT
Possible impacts/effects of the Project 1 Increase 2 Decrease
Employment opportunities
Industrial Development Opportunities
Living standard
Unemployment
Income generating activities
Electricity Supply Quality
Mobility (Access to Resources)
Other specify
11. Does any NGO / FO Exist in your Area?
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
124
Sindh Water Sector Improvement Project
Yes ______________________________________ No_______________________________________
If yes,
Name of NGO / FO__________________________________________________________________________________
Are you member of this NGO / FO ____________________________________________________________________
Are you member of this NGO / FO_ ___________________________________________________________________
Role of NGO / FO __________________________________________________________________________________
___________________________________________________________________________________________________
12. General Observations of Interviewers
_____________________________________________________________________________________________________________
_________________________________________________________________________________________________
Name of Interviewer ____________________________________________ Date. _______________________________
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
125
Sindh Water Sector Improvement Project
Village Profile Serial No. _______
Water Sector Improvement Project ENVIRONMENTAL AND SOCIAL ASSESSMENT STUDY
IDENTIFICATION:
a. Name of Union Council: ______________________________________________________
b. Name of Main Village: _______________________________________________________
c. Total Number of Settlements in the Village: ______________________________________
d. Name of Settlement / Chak of Scoping Session: __________________________________
e. Persons Attending the Scoping Session: Total ______Males ______Females__________
1. ETHNICITY AND POPULATION
Name of the Main
Caste
Name of the
Clan
Name of HEAD or Prominent
Member of Caste / Clan
Total
Household of
Respective
Caste
Population
Male Female
Total
1
2
3
4
5
6
7
8
2. LANGUAGES SPOKEN IN THE VILLAGE:
2.1 Urdu ___________________________ 2.2 Sindhi ____________________________ 2.3 Punjabi __________________________ 2.4 Others ____________________________
NUMBER OF EDUCATED PERSONS IN THE SETTLEMENT / VILLAGE
Level Male (No.) Female (No.) Total (M+F)
Primary Level
Middle
Metric
Intermediate
Graduation
Post Graduation
Others
3. EDUCATION FACILITIES AVAILABLE IN THE SETTLEMENT / VILLAGE
Description No. of institutions Enrolment No. of Teachers Boys Girls Boys Girls Male Female
Primary School.
Middle School
High School
Inter College
Degree College
Madrassa
Vocational
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
126
Sindh Water Sector Improvement Project
4. HEATH FACILITIES (Within Village)
Facility Within Village
Exists
Yes=1
No=2
Whether
Functioning
Yes=1
No=2
Medical Staff
Available
(Nos.)
Nearby Similar
facility
(near of place)
Hospital
Basic Health Unit
Mother Child Care Centre
Child Immunization Centre
4. IS THERE ANY PRIVATE MEDICAL PRACTITIONER IN THE VILLAGE?
1
.M.B.B.S (No.)______ 2 Homeopathic (No.)_______ 3 Hakeem (No.)_____
5. DOES ANY CHILD BIRTH ATTENDANT AVAILABLE IN THE VILLAGE? YES No
If yes, what type?
1) Doctor
2) Others Specify
6. OCCURRENCE OF DISEASES DURING LAST FIVE YEARS
1 Malaria 2 Typhoid 3 Cholera 4 HIV 5 Measles
6 Polio 7 T.B. 8 Diahorea 9 Hepatitis 10 Others
Specify
7. NUMBER OF HOUSES IN THE VILLAGE
1. Katcha_______ 2) Pacca_______ 3) Semi-Pacca_______ 4) Hut _______
8. AVAILABLE UTILITIES(No. of houses having facility)
8.1 Water supply system
Water Carrying
System
Wastewater Disposal System:
Sewerage System, 1 Open Drains, 2 Soakage Pits 3
Latrine:
Electricity:
4 Paramedical (No.)_____
Municipal Supply 1 Spring 2 Hand Pump, 3
Electric Motor Pump, 4 Water
Channel 5 Other, 6
Self Carried 1 Tanker 2 Donkey Back 3
Tapped 4 Other 5
Fields 1 Within House, Flush System 2
Yes 1 No 2
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
127
Sindh Water Sector Improvement Project
9. ACCESS TO SOCIAL AMENITIES
Type of Amenity
Available in the Village
1= Yes
2= No
Available in Nearby Village /
Locality
1= Yes
2= No
Distance from the
Village (km)
Electricity
Gas
Fuel cylinder
Telephone (Land Line)
Post Office
Bank
Mosque
Graveyard
Other
10. ACCESSIBILITY OF THE VILLAGE THROUGH:
1. Metalled Road _______________ 2..Soling ________________ 3. Katcha _____________.
11. DISTANCE OF VILLAGE FROM ROAD / TRACK: --------------------- km
12. AVAILABILITY OF TRANSPORT IN THE VILLAGE?
Public Transport Yes ______________ No _________________
Private Transport Yes _____________ No _________________
13. OCCUPATIONAL STATISTICS (No of Households with Major Source of Income of the head of family)
1. Agriculturist ________________
2. Shopkeepers ________________
3. Transporters ________________
4. Livestock Farmers ________________
5. Employment (Public) ________________
6. Employment (Private) ________________
7. Daily wage Earners /Laborer ________________
8. Poultry Farmers ________________
14. LAND STATISTICS OF VILLAGE Acres Kanal
1) Cultivated Land ___________ ___________
2) Fallow Land ___________ ___________
3) Cultivable Waste Land (Banjar) ___________ ___________
4) GhairMumkin ___________ ___________
5) Total Land ___________ ___________
15 I RRIGATION WATER SOURCE AND AREA IRRIGATED
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
128
Sindh Water Sector Improvement Project
Acres Kanal
1. Canal Only ______ _______
2. Tube well Only ______ _______
3. Canal+ Tube well ______ _______
4. Barani _____ ______
16 Do the farmers sell water to other farmers?
Yes No
If yes why? ______________________________________________________________________________
17. CONFLICT RESOLUTION MECHANISM
17.1 Who are the influential in your village?
1. Politician / Landlord
2. Nazim /Councilor
3. Religious Scholars
4. Heads of Families
5. Others(Specify)
18.2 How the matters related to property, dispute about the control and consumption of the natural
resources of the area are and matters of common interest settled?
a) Punchyat
b) Head of the Caste
c) Nazim of the Area
d) Head of Families
19. N UMBER OF ANIMAL IN THE VILLAGE
Animal type
Masculine Feminine
Total Young Stock
(upto 3 yrs) Adult
Young Stock
(upto 3 yrs) Adult
Buffalo
Cow
Sheep
Goat
Horses
Donkeys
Mules
Others
20. Pressing Needs of the ProjectArea:
____________________________________________________________________________________________________________________
____________________________________________________________________________________________________________________
21 COMMENTS/OBSERVATIONS OF THE INTERVIEWER:
_____________________________________________________________________________________________________________
_____________________________________________________________________________________________________________
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
129
Sindh Water Sector Improvement Project
_____________________________________________________________________________________________________________
_____________________________________________________________________________________________________________
Interviewed by: _____________________________ Date: ____________________
LIST OF PARTICIPANTS/ RESPONDENTS
Sr. No. Name Father’s Name Village / Settlement
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
130
Sindh Water Sector Improvement Project
SINDH WATER SECTOR IMPROVEMENT PROJECT, PHASE – 1
Gender Data Collection
Year: ____________ Questionnaire No.________ 1. Location /Identification
a. Name of village ____________________ b. Name of canal ____________________ c. WC/minor/ distributary no. ____________________ d. Taluka / Distt. ____________________
2. Biographical Data a. Name of respondent ____________________ b. Father’s/ Husband’s name ____________________ c. Marital status:
i. Married ______________ ii. Single ______________ iii. Widow ______________ iv. Divorced ______________
d. Literacy status
i. Literate ______________ ii. Illiterate ______________
e. If literate years of schooling/ level of education
i. Primary ______________ ii. Middle ______________ iii. High ______________ iv. Graduate ______________ v. Others ______________
f. Do you own any property in your name? i. Yes ______________ ii. No ______________
g. If yes, then i. Land ______________ ii. House ______________ iii. Livestock ______________ iv. Any other ______________
h. What is total house hold composition?
i. Boys _____________ ii. Girls _____________ iii. Total _____________
i. What are your specific household activities?
i. Food preparation _____________ ii. Cleaning / housekeeping _____________ iii. Manage house budget _____________ iv. Caring of children _____________ v. Any other, (specify) ____________
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
131
Sindh Water Sector Improvement Project
j. What are your specific farm activities? i. Livestock rearing _____________ ii. Poultry farming _____________ iii. Milking of animals _____________ iv. Harvesting of crops _____________ v. Weeding _____________ vi. Vegetable sowing / harvesting _____________ vii. Any other ( specify ) _____________
k. Role Of Women In Decision Making
i. Are you involved in : ii. Marriage of children yes _____, No______ iii. Sale & purchase of property yes _____, No______ iv. Decision regarding schooling yes _____, No______
of children v. Decision to attend social factions yes _____, No_______
l. How many adult female including you are living in this house?
i. 1 _____ , 2 ____ , 3 ______ , 4 _______ , 5 _______
m. Mention three basic facilities that women need most: i. _______________________________ ii. _______________________________ iii. _______________________________
3. Health
a. Which of health facilities are available at your village? i. BHU ____________ ii. Dispensary ____________ iii. Private doctor ____________ iv. Hakeem ____________
b. Which were the strongly hit diseases in last year?
i. Diarrhea ____________ ii. Measles ____________ iii. Hepatitis ____________ iv. Typhoid ____________ v. Tuberculosis ____________ vi. Heart diseases ____________
c. In case of emergency who takes you to hospital?
i. Husband ____________ ii. Mother-in-law ____________ iii. Father in law ____________ iv. Alone ____________
d. Do you face any problem / difficulty for transport while rushing towards hospital?
i. Yes ____________ ii. No ____________
e. If yes, then what would you prefer
i. Have proper transport arrangement ___________ ii. To be reside at some proper place ___________
f. What are the basic health needs or facilities which you want in your area?
i. _____________________
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
132
Sindh Water Sector Improvement Project
ii. _____________________ iii. _____________________
4. Education
a. Is there any school for girls in the village? i. Yes __________ No________
b. If yes, then how many girls of village are studying in that school?
i. ___________ %
5. Participation in FO/ WCA a. Did women aware about their land ownership?
i. Yes ___________ ii. No ___________
b. How many members are there in FO/WCA? ___________
c. Status of membership
i. Ordinary membership yes_____, No ______ ii. Office bearers yes _____, No ______
d. What was women contribution in FO/ WCA affairs?
i. __________________________________________________________ ii. __________________________________________________________ iii. __________________________________________________________
e. Do you receive any training for this? Yes ______, No______ f. If yes, state the following
Month / year Place Type of Training Organization / Project
g. Do you think that participation of women in FO/ WCA affairs will make it successful?
i. Yes_________, No ________
h. If yes ; state the reasons __________________________________________________________________________________________________________________________________________________________________________________________________________________
i. What are the suggestions for efficient and effective functioning of FO/WCA? ____________________________________________________________________________________________________________________________________________
j. What factors prohibit an average woman of this village to come forward and participate effectively in FA/WCA affairs at village level?
__________________________________________________________________________________________________________________________________________________________________________________________________________________
6. Income Generation
a. Do you contribute to family income i. Yes _______, No ________
b. If yes, what is source of your income?
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
133
Sindh Water Sector Improvement Project
Sources Annual Income (Rs)
i. Farm labour __________________ ii. Fire wood collection __________________ iii. Embroidery __________________ iv. Domestic Services __________________ v. Any other __________________
7. Skill Development
a. Do you think that different kind oftrainings can enhance your income generating resources? i. Yes _______ , No________
b. If yes, which training you would like to obtain?
i. Sewing/ stitching _________________ ii. Embroidery _________________ iii. Teaching _________________ iv. Handicrafts _________________ v. Any other (specify) _________________
8. Pressing needs of women in project area
Sr. no Needs / facilities To what extant in %age
Name of interviewer:__________________
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
134
Sindh Water Sector Improvement Project
Appendix D. Details of Project Affected Persons and Assets
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
135
Sindh Water Sector Improvement Project
D.1. Details of Affected Structures of Ghotki Feeder Canal and Estimated Compensation Cost
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
Ghotki Feeder Canal (IP)
1 Shah Gul Mazari Dost Mohammad GFC Ubaro Ghotki 9+500(IP) Govt. Servant 8,000 8,800 7 1,143 B House
Room Kacha 480 155 74,389
Shed Straw 810 263 212,779
B/wall Kacha 280 376 105,252
Hand Pump
Hand Pump Unit 1 7700 7,700
2 Wallan Mazari Duno Mazari GFC Ubaro Ghotki 14+000(IP) Farming (Owner) 8,000 8,800 8 1,000 B
House Room Kacha 464 155 71,909
B/wall Kacha 120 376 45,108
Hand Pump
Unit 1 7700 7,700
3 Pinyal Kosh Kambhir Kosh GFC Ubaro Ghotki 63+000(IP L/S)
General Labour 7,000 7,700 8 875 B House Room Kacha 480 155 74,389
Ghotki Feeder Canal (NIP)
1 Faiz Mohammad Habiburahman GFC Ubaro Ghotki 7+900 (NIP) Farming (Owner) 11,000 12,100 4 2,750 A
House Room Pacca 196 898 176,005
Shed Straw 216 263 56,741
Hand Pump
Unit 1 7700 7,700
2 Ghulam Hyder Abdul Karim GFC Ubaro Ghotki 7+900(NIP) Farming (Tenant) 7,000 7,700 4 1,750 B House Room Kacha 168 155 26,036
3 Pir Bux Mir Hazar GFC Ubaro Ghotki 14+700(NIP)
General Labour 8,000 8,800 7 1,143 B House Room Kacha 168 155 26,036
B/wall Kacha 60 376 22,554
4 Karim Bux Mirani Sacho GFC Ubaro Ghotki 14+500(NIP) General Labour 5,000 5,500 4 1,250 B
House Room Kacha 391 155 60,596
B/Wall Kacha 570 376 214,263
Hand Pump
Unit 1 7700 7,700
5 Bashir Ahmed Raheem Bux GFC Ubaro Ghotki 14+500(NIP) General Labour 5,000 5,500 2 2,500 A
House Room Kacha 256 155 39,674
B/Wall Kacha 52 376 19,547
Hand Pump
Unit 1 7700 7,700
6 Abdul Hakeem Malik Mitha Malik GFC Ubaro Ghotki 14+600(NIP) General Labour 7,000 7,700 12 583 B House Room Kacha 345 155 53,467
B/Wall Kacha 78 376 29,320
7 Imam Din Malik Faiz Mohammad GFC Ubaro Ghotki 14+900(NIP) Small Business 8,000 8,800 12 667 B Shop Room Pacca 170 898 152,657
Room Pacca 170 898 152,657
8 Mohammad Bux Mohammad Waris Mazari
GFC Khohi Malik Ubaro Ghotki 14+500(NIP) General Labour 5,000 5,500 8 625 B House Room Pacca 221 898 198,454
B/Wall Kacha 890 376 334,551
9 Shahmir Malik Chalaka Malik GFC Khohi Malik Ubaro Ghotki 14+950(NIP) Small Business 5,000 5,500 5 1,000 B Shop Wall Pacca 220 1078 237,212
10 Sohnno Mazari Khuda Bux GFC Ubaro Ghotki 18+000(NIP) Farming (Tenant) 5,000 5,500 6 833 B
House Room Kacha 286 155 44,323
Animal Shed Straw 294 263 77,231
Hand Pump
Unit 1 7700 7,700
11 Nihal Mazari Jalal Mazari GFC Ubaro Ghotki 18+200(NIP) General Labour 5,500 6,050 9 611 B House Room Kacha 459 155 71,134
Hand Pump
Unit 1 7700 7,700
12 Shah Mohammad Qadir Bux Malik GFC Ubaro Ghotki 19+200(NIP) Farming (Tenant) 4,500 5,000 4 1,125 B
House Room Kacha 544 155 84,307
Room Straw 280 263 73,553
Hand Pump
Unit 1 7700 7,700
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
136
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
13 Ali Nawaz Qadir Bux Malik GFC Ubaro Ghotki 19+800(NIP) Farming (Tenant) 5,000 5,500 9 556 B
House Room Straw 476 263 125,040
Hand Pump
Unit 1 7700 7,700
14 Ghulam Fareed Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 8,000 8,800 14 571 B House Room Semi Pacca 320 624 199,776
Animal Shed Straw 104 263 27,320
15 Dil Murad Ghulam Fareed GFC Ubaro Ghotki 27+300(NIP) Farming (Owner) 15,000 16,500 23 652 B House Room Kacha 270 155 41,844
Animal Shed Kacha 465 155 72,064
16 Hassan Ali Mazari Dil Murad Mazari GFC Punhal Khan Mazari
Ubaro Ghotki 27+300(NIP) Farming (Tenant) 5,000 5,500 3 1,667 B House Room Kacha 390 155 60,441
17 Yaqoob Mazari Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 5,000 5,500 11 454 B
House Room Kacha 480 155 74,389
Animal Shed Kacha 315 155 48,817
Hand Pump
Unit 1 7700 7,700
18 Yaseen Mazari Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 3,000 3,300 4 750 B House Room Kacha 210 155 32,545
19 Mir Muhammad Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 3,000 3,300 4 750 B House Room Kacha 300 155 46,493
B/Wall Kacha 135 155 20,922
20 Sohbat Khan Mazari Ghazi Khan GFC Ubaro Ghotki 27+800(NIP) Farming (Tenant) 9,000 9,900 10 900 B
House Room Kacha 378 155 58,581
Otaq Room Kacha 300 155 46,493
Hand Pump
Unit 2 7700 15,400
21 Nazir Ahmed Mazari Ghulam Hyder GFC Punhal Khan Mazari
Ubaro Ghotki 28+900(NIP) Private Servant 6,000 6,600 5 1,200 B House Room Pacca 255 898 228,985
Room Pacca 255 898 228,985
22 Wazir Ahmed Mazari Ghulam Hyder GFC Punhal Khan Mazari
Ubaro Ghotki 28+900(NIP) Private Servant 6,000 6,600 9 667 B House Room Semi Pacca 210 624 131,103
23 Mohib Ali Mazari Gulam Mazari GFC Punhal Khan Mazari
Ubaro Ghotki 28+800(NIP) Private Servant 6,000 6,600 12 500 B
House Room Kacha 285 155 44,168
Hand Pump
Unit 1 7700 7,700
24 Rehman mazari Behram Mazari GFC Ubaro Ghotki 29+000(NIP) General Labour 5,000 5,500 4 1,250 B House Room Kacha 320 155 49,592
Animal Shed Kacha 720 155 111,583
25 Ali Anwar mazari Arz Mohammad GFC Ubaro Ghotki 30+000(NIP) Farming (Owner) 16,000 17,600 13 1,231 B
house Room Kacha 300 155 46,493
Hand Pump
Unit 1 7700 7,700
26 Mohammad Ramzan Bakhsh Khan Dasti GFC Ubaro Ghotki 40+000(NIP) Private Servant 8,000 8,800 8 1,000 B
House
Room Semi Pacca 380 624 237,234
Room Kacha 180 155 27,896
B/Wall Kacha 52 155 8,059
Hand Pump
Unit 1 7700 7,700
27 Balach Khan Dasti Mohammad Ramzan GFC Ubaro Ghotki 40+000(NIP) Private Servant 6,000 6,600 7 857 B House
Room Kacha 320 155 49,592
kitchen Kacha 176 155 27,276
B/Wall Kacha 183 155 28,361
Hand Pump
Unit 1 7700 7,700
28 Allah Rakhiyo Mohammad Ramzan GFC Ubaro Ghotki 40+100(NIP) General Labour 5,000 5,500 7 714 B
House Room Kacha 224 155 34,715
B/Wall Kacha 165 376 62,023
Hand Pump
Unit 1 7700 7,700
29 Nazir Ahmed Mehan Khan Malik GFC Ubaro Ghotki 40+200(NIP) General Labour 5,000 5,500 7 714 B House Room Kacha 272 155 42,154
Animal shed Kacha 100 155 15,498
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
137
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
B/Wall Kacha 220 155 34,095
30 Veer Malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 4,500 5,000 4 1,125 B House Room Kacha 256 155 39,674
31 Malook malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 6,000 6,600 7 667 B House
Room Kacha 336 155 52,072
B/Wall Kacha 220 155 34,095
Hand Pump
Unit 1 7700 7,700
32 Kashmir Malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 3,000 3,300 2 1,500 B House Room Kacha 464 155 71,909
B/Wall Kacha 152 155 23,556
33 Hamal Mazari Mohkum Din GFC Ubaro Ghotki 41+000(NIP) Farming (Tenant) 5,000 5,500 6 833 B House Room Kacha 336 155 52,072
Animal Shed Kacha 45 155 6,974
34 Mir Hazar Mazari Kheno Khan GFC Ubaro Ghotki 41+000(NIP) Farming (Tenant) 5,000 5,500 6 833 B House
Room Kacha 300 155 46,493
B/Wall Kacha 740 155 114,682
Hand Pump
Unit 1 7700 7,700
35 Yousif Dasti Ali Nawaz Dasti GFC Ubaro Ghotki 41+500(NIP) Farming (Tenant) 6,000 6,600 7 857 B House
Room Kacha 266 155 41,224
B/Wall Kacha 390 376 146,601
Hand Pump
Unit 1 7700 7,700
36 Ali Nawaz Dasti Machro khan GFC Ubaro Ghotki 41+500(NIP) Farming (Tenant) 8,000 8,800 11 727 B House Room Kacha 285 155 44,168
B/Wall Kacha 425 376 159,757
37 Dagha Khan Machro khan GFC Ubaro Ghotki 41+500(NIP) General Labour 5,000 5,500 8 625 B
House Room Pacca 285 898 255,925
B/Wall Kacha 480 376 180,432
Hand Pump
Unit 1 7700 7,700
38 Karam Ali Ghulam Ali Dasti GFC Ubaro Ghotki 43+300(NIP) General Labour 3,000 3,300 2 1,500 B House
Room Pacca 288 898 258,619
Kitchen Kacha 104 155 16,118
B/Wall Kacha 80 376 30,072
39 Abrar Ali Gulam Ali Dasti GFC Ubaro Ghotki 43+300(NIP) General Labour 3,000 3,300 3 1,000 B House B/Wall Kacha 370 376 139,083
40 Zahoor Ahmed Nabi Bux GFC ubaro Ghotki 43+500(NIP) General Labour 7,500 8,250 7 1,071 B House Room Pacca 240 898 215,516
41 Farooq Nawab Khan GFC ubaro Ghotki 43+500(NIP) General Labour 6,000 6,600 3 2,000 B House Room Pacca 196 898 176,005
42 Imam Ali Bilawal Dasti GFC Ubaro Ghotki 43+500(NIP) General Labour 2,000 2,200 2 1,000 B House Room Pacca 304 898 272,987
Room Pacca 168 898 150,861
43 Gulam Ali Mohmmad Ramzan GFC Ubaro Ghotki
43+300
Small Business 14,000 15,400 11 1,273 B
House
Room Kacha 375 155 58,116
to Room Pacca 304 898 272,987
43+500 B/Wall Kacha 1,116 376 419,504
Shop
B/Wall Kacha 540 376 202,986
Room Semi Pacca 308 624 192,285
Hand Pump
Unit 1 7700 7,700
44 Abandoned* GFC Ubaro Ghotki 43+500(NIP) Shop Room Pacca 260 898 233,475
45 Mahboob Ali Memon Kaoro Khan GFC Ubaro Ghotki 43+500(NIP) Small Business 7,000 7,700 6 1,167 B Shop Room Pacca 231 898 207,434
46 Abandoned* GFC Ubaro Ghotki 43+500(NIP) Shop Room Pacca 240 898 215,516
47 Barkatullah Dasti Faiz Mohammad GFC Ubaro Ghotki 43+500(NIP) General Labour 6,000 6,600 12 500 B House
Room Pacca 275 898 246,945
Shed Kacha 360 155 55,791
Hand Pump
Unit 2 7700 15,400
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
138
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
48 Ali Hasan Mirani Rais Gudo GFC Ubaro Ghotki 43+900(NIP) Fishing 4,000 4,400 9 444 B
House
Room Pacca 289 898 259,517
Washroom(Wall) Pacca 36 1078 38,817
B/Wall Kacha 1,270 376 477,392
Hand Pump
Unit 1 7700 7,700
49 Sher Mohammad Nabi Bux GFC Ubaro Ghotki 44+00(NIP) Fishing 5,000 5,500 10 500 B
House Room Kacha 195 155 30,220
B/Wall Kacha 420 376 157,878
Hand Pump
Unit 1 7700 7,700
50 Muhammad Amin Dasti Salar Khan GFC Ubaro Ghotki 44+000(NIP) General Labour 6,000 6,600 5 1,200 B
House
Room Semi Pacca 154 624 96,142
Kitchen Kacha 150 155 23,246
B/Wall Kacha 100 376 37,590
Hand Pump
Unit 1 7700 7,700
50 Durr Muhammad Mirani Muhammad Hayat GFC Ubaro Ghotki 44+100(NIP) General Labour 3,000 3,300 9 333 B
House Room Kacha 374 155 57,961
B/Wall Kacha 1,000 376 375,900
Hand Pump
Unit 1 7700 7,700
52 Muneer Ahmed Shah Khair Shah GFC Ubaro Ghotki 44+100(NIP) General Labour 5,000 5,500 6 833 B
House Room Kacha 238 155 36,884
B/Wall Kacha 350 376 131,565
Hand Pump
Unit 1 7700 7,700
53 Muhammad Mureed Mirani
Muhammad Eidan GFC Ubaro Ghotki 44+150(NIP) General Labour 5,000 5,500 7 714 B House Room Straw 306 263 80,383
54 Abdul Ghani Mirani Kalu Khan GFC Ubaro Ghotki 44+150(NIP) General Labour 5,000 5,500 8 625 B House
Room Pacca 240 898 215,516
Washroom(Wall) Pacca 36 1078 38,817
B/Wall Kacha 96 376 36,086
Hand Pump
Unit 1 7700 7,700
55 Abandonned* GFC Ubaro Ghotki 44+200(NIP) House
Room Semi Pacca 168 624 104,883
Room Pacca 224 898 201,148
Washroom(Wall) Semi Pacca 36 624 22,475
B/Wall Kacha 540 376 202,986
Hand Pump
Unit 1 7700 7,700
56 Haji Iqbal Chaoudhry Muhammad Rafiq GFC Ubaro Ghotki 44+250(NIP) General Labour 10,000 11,000 9 1,111 B
House
Room Pacca 224 898 201,148
Room Pacca 224 898 201,148
Room Kacha 840 376 315,756
Hand Pump
Unit 1 7700 7,700
57 Papu Pathan Nawab Pathan GFC Ubaro Ghotki 44+300(NIP) General Labour 10,000 11,000 5 2,000 B House
Room Pacca 289 898 259,517
Room Pacca 289 898 259,517
Room Pacca 289 898 259,517
Washroom(Wall) Pacca 100 1078 107,824
Washroom(Wall) Pacca 100 1078 107,824
B/Wall Kacha 770 376 289,443
58 Ashraf Ali Qureshi Bindu GFC Ubaro Ghotki 44+350(NIP) General Labour 5,000 5,500 9 555 B House Room Kacha 196 155 30,375
Washroom(Wall) Semi Pacca 180 514 92,590
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
139
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
B/Wall Kacha 350 155 54,242
59 Muhammad Achar Piyaro GFC Ubaro Ghotki 44+400(NIP) General Labour 6,000 6,600 8 750 B House
Room Semi Pacca 208 624 129,855
Room Semi Pacca 128 624 79,911
Washroom(Wall) Pacca 64 1078 69,007
B/Wall Kacha 742 376 278,917
Hand Pump
Unit 1 7700 7,700
60 Muneer Ahmed Mirani Muhammad Mithal GFC Ubaro Ghotki 44+500(NIP) General Labour 3,000 3,300 3 1,000 B
House Room Kacha 208 155 32,235
Kitchen Kacha 195 155 30,220
Hand Pump
Unit 1 7694 7,694
61 Muhammad Mor Pir Bux Mirani GFC Ubaro Ghotki 44+550(NIP) General Labour 5,000 5,500 5 1,000 B
House
Room Kacha 272 155 42,154
Room Semi Pacca 306 624 191,036
Wall(House) Kacha 432 376 162,389
B/Wall Kacha 350 376 131,565
Hand Pump
Unit 1 7700 7,700
62 Samundar Khan Dawood Khan GFC Ubaro Ghotki 44+600(NIP) General Labour 8,000 8,800 15 533 B
House
Room Kacha 272 155 42,154
Washroom(Wall) Kacha 72 376 27,065
B/Wall Kacha 720 376 270,648
Hand Pump
Unit 1 7700 7,700
63 Bhora Khan Badal Khan Dasti GFC Ubaro Ghotki 44+700(NIP) General Labour 5,000 5,500 9 556 B
House
Room Sami Pacca 238 624 148,584
Room Sami Pacca 238 624 148,584
Room Sami Pacca 168 624 104,883
B/Wall Kacha 480 376 180,432
Hand Pump
Unit 1 7700 7,700
64 Akbir Ali Dasti Ghamno Dasti GFC Ubaro Ghotki 44+750(NIP) General Labour 5,000 5,500 9 556 B
House
Room Sami Pacca 270 624 168,561
Room Kacha 360 155 55,791
Washroom(Wall) Kacha 64 376 24,058
Hand Pump
Unit 1 7700 7,700
65 Noor Din Mirani M.Bachal Mirani GFC Ubaro Ghotki 44+850(NIP) Fishing 3,000 3,300 2 1,500 B House
Room Sami Pacca 270 624 168,561
Room Sami Pacca 270 624 168,561
Hand Pump
Unit 1 7700 7,700
66 Abondonned* GFC Ubaro Ghotki 44+800(NIP) House
Room Sami Pacca 176 624 109,877
Room Sami Pacca 224 624 139,843
B/Wall Kacha 770 376 289,443
67 Shahnawaz Dasti Lal Bux GFC Lal Bux Dasti Ubaro Ghotki 45+850(NIP) General Labour 5,000 5,500 9 556 B
House Room Kacha 150 155 23,246
B/Wall Kacha 1,610 376 605,198
Hand Pump
Unit 1 7700 7,700
68 Allah Jawayo Jamal din GFC Ubaro Ghotki 46+100(NIP) General Labour 4,000 4,400 4 1,000 B House Room Kacha 238 155 36,884
Hand Pump
Unit 1 7700 7,700
69 Wahid Bux Mehrab Dasti GFC Ubaro Ghotki 74+200(NIP) General Labour 4,000 4,400 7 571 B House Room Kacha 240 155 37,194
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
140
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
B/Wall Kacha 400 376 150,360
Hand Pump
Unit 1 7700 7,700
70 Kandho Khan M.Ismail Dasti GFC Ubaro Ghotki 47+900(NIP) Live Stock 4,000 4,400 4 1,000 B Room Kacha 216 155 33,475
71 M.Azeem Bhyo Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming (Owner) 15,000 16,500 11 1,364 B House
Room Sami Pacca 306 624 191,036
B/Wall Sami Pacca 240 624 149,832
Hand Pump
Unit 1 7700 7,700
72 Faiz Mohammad Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming (Owner) 10,000 11,000 9 1,111 B House Shed Kacha 480 155 74,389
B/Wall Sami Pacca 220 514 113,166
73 Mohammad Haleem Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming (Owner) 15,000 16,500 18 833 B House
Room Sami Pacca 304 624 189,788
Room Sami Pacca 304 624 189,788
B/Wall Sami Pacca 400 514 205,756
Hand Pump
Unit 1 7700 7,700
74 Ali Gohar Kathoro GFC Ubaro Ghotki 49+100(NIP) Farming (Tenant) 8,000 8,800 11 727 B House Room Straw 168 263 44,132
75 Ghulam Hussaul M.Haleem GFC Ubaro Ghotki 49+100(NIP) Farming (Tenant) 3,000 3,300 5 600 B House Room Straw 450 263 118,211
76 Muj Ali Mirani Rahim Bux GFC Ubaro Ghotki 51+00(NIP) General Labour 4,000 4,400 6 667 B
House Room Kacha 442 155 68,499
Wall(House) Sami Pacca 400 514 205,756
Hand Pump
Unit 1 7700 7,700
77 Datto Mirani Lal Bux GFC Ubaro Ghotki 51+00(NIP) General Labour 8,000 8,800 11 727 B House
Room Kacha 374 155 57,961
Room Kacha 432 155 66,950
Hand Pump
Unit 1 7700 7,700
78 Abondonned* GFC Ubaro Ghotki 52+100(NIP) Otaq Room Kacha 196 155 30,375
Hand Pump
Unit 1 7700 7,700
79 Abondonned* GFC Ubaro Ghotki 52+400(NIP) House Shed Straw 140 263 36,777
Shed Straw 182 263 47,810
80 Gul Mohammad Meerani
Koral GFC Ubaro Ghotki 52+800(NIP) General Labour 8,000 8,800 7 1,143 B House Room Straw 216 263 56,741
81 Shahid Noor Hasan GFC Ubaro Ghotki 52+800(NIP) General Labour 5,000 5,500 2 2,500 A House Room Kacha 252 155 39,054
82 Chanesar Mirani Nangar Khan GFC Ubaro Ghotki 53+00(NIP) Fishing 4,000 4,400 7 571 B House Room Straw 408 263 107,178
83 Mir Khan Mirani Tagyo GFC Ubaro Ghotki 53+200(NIP) General Labour 3,000 3,300 4 750 B House Room Straw 225 263 59,105
Hand Pump
Unit 1 7700 7,700
84 Dado Murani Mir Khan GFC Ubaro Ghotki 53+200(NIP) Fishing 5,000 5,500 9 555 B House Room Straw 225 263 59,105
85 Liaqat Ali Mirani Mir Khan GFC Ubaro Ghotki 53+00(NIP) Fishing 5,000 5,500 9 555 B House Room Straw 475 263 124,778
86 Akhtar Hussain M.Hashim Mirani GFC Ubaro Ghotki 53+00(NIP) Fishing 4,000 4,400 5 800 B House Room Straw 192 263 50,436
87 Umed Ali Ahmed Khan GFC Mir Kosh Ubaro Ghotki 61+200(NIP) General Labour 4,000 4,400 7 571 B House
Room Kacha 266 155 41,224
Animal shed Straw 150 263 39,404
B/Wall Kacha 475 376 178,552
88 Abdul Rehman Kosh Ahmed Khan GFC Mir Kosh Ubaro Ghotki 61+200(NIP) General Labour 5,000 5,500 7 714 B
House Room Kacha 288 155 44,633
Animal Shed Straw 192 263 50,436
Hand Pump
Unit 1 7700 7,700
89 Mohammad Adhyo Budhyo Kosh GFC Mir Kosh Ubaro Ghotki 61+300(NIP) General Labour 10,000 11,000 8 556 B House Room Pacca 288 898 258,619
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
141
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status Affected structure
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/ Name of
Structure Type of Structure
Type of construction
Size of Structure (sft/rft)
Unit Rate (RS.)
Total Cost of Structure Below
Room Kacha 168 155 26,036
Hand Pump
Unit 1 7700 7,700
90 Baksho Kosh Budho GFC Mir Kosh Ubaro Ghotki 61+450(NIP) Farming (Tenant) 6,000 6,600 10 600 B House Room Kacha 570 155 88,336
Grand Total 645 21,914,460
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
142
Sindh Water Sector Improvement Project
D.2. Details of Low Income Allowance Entitlements Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/
Low Income allowance (PKR)
Below
Ghotki Feeder Canal (IP)
1 Shah Gul Mazari Dost Mohammad GFC Ubaro Ghotki 9+500(IP) Govt.Servant 8,000 8,800 7 1,143 B 22,000.00
2 Wallan Mazari Duno Mazari GFC Ubaro Ghotki 14+000(IP) Farming(Owner) 8,000 8,800 8 1,000 B 22,000.00
3 Pinyal Kosh Kambhir Kosh GFC Ubaro Ghotki 63+000(IP L/S)
General Labour 7,000 7,700 8 875 B 22,000.00
Ghotki Feeder Canal (NIP)
4 Ghulam Hyder Abdul Karim GFC Ubaro Ghotki 7+900(NIP) Farming(Tenant) 7,000 7,700 4 1,750 B 22,000.00
5 Pir Bux Mir Hazar GFC Ubaro Ghotki 14+700(NIP)
General Labour 8,000 8,800 7 1,143 B 22,000.00
6 Karim Bux Mirani Sacho GFC Ubaro Ghotki 14+500(NIP) General Labour 5,000 5,500 4 1,250 B 22,000.00
7 Abdul Hakeem Malik Mitha Malik GFC Ubaro Ghotki 14+600(NIP) General Labour 7,000 7,700 12 583 B 22,000.00
8 Imam Din Malik Faiz Mohammad GFC Ubaro Ghotki 14+900(NIP) Small Business 8,000 8,800 12 667 B 22,000.00
9 Mohammad Bux Mohammad Waris Mazari
GFC Khohi Malik Ubaro Ghotki 14+500(NIP) General Labour 5,000 5,500 8 625 B 22,000.00
10 Shahmir Malik Chalaka Malik GFC Khohi Malik Ubaro Ghotki 14+950(NIP) Small Business 5,000 5,500 5 1,000 B 22,000.00
11 Sohnno Mazari Khuda Bux GFC Ubaro Ghotki 18+000(NIP) Farming(Tenant) 5,000 5,500 6 833 B 22,000.00
12 Nihal Mazari Jalal Mazari GFC Ubaro Ghotki 18+200(NIP) General Labour 5,500 6,050 9 611 B 22,000.00
13 Shah Mohammad Qadir Bux Malik GFC Ubaro Ghotki 19+200(NIP) Farming(Tenant) 4,500 4,950 4 1,125 B 22,000.00
14 Ali Nawaz Qadir Bux Malik GFC Ubaro Ghotki 19+800(NIP) Farming(Tenant) 5,000 5,500 9 556 B 22,000.00
15 Ghulam Fareed Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant)
8,000 8,800 14 571 B 22,000.00
16 Dil Murad Ghulam Fareed GFC Ubaro Ghotki 27+300(NIP) Farming(Owner) 15,000 16,500 23 652 B 33,000.00
17 Hassan Ali Mazari Dil Murad Mazari GFC Punhal Khan Mazari
Ubaro Ghotki 27+300(NIP) Farming (Tenant)
5,000 5,500 3 1,667 B 22,000.00
18 Yaqoob Mazari Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant)
5,000 5,500 11 454 B 22,000.00
19 Yaseen Mazari Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant)
3,000 3,300 4 750 B 22,000.00
20 Mir Muhammad Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant)
3,000 3,300 4 750 B 22,000.00
21 Sohbat Khan Mazari Ghazi Khan GFC Ubaro Ghotki 27+800(NIP) Farming (Tenant)
9,000 9,900 10 900 B 22,000.00
22 Nazir Ahmed Mazari Ghulam Hyder GFC Punhal Khan Mazari
Ubaro Ghotki 28+900(NIP) Private Servant 6,000 6,600 5 1,200 B 22,000.00
23 Wazir Ahmed Mazari Ghulam Hyder GFC Punhal Khan Mazari
Ubaro Ghotki 28+900(NIP) Private Servant 6,000 6,600 9 667 B 22,000.00
24 Mohib Ali Mazari Gulam Mazari GFC Punhal Khan Mazari
Ubaro Ghotki 28+800(NIP) Private Servant 6,000 6,600 12 500 B 22,000.00
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
143
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/
Low Income allowance (PKR)
Below
25 Rehman mazari Behram Mazari GFC Ubaro Ghotki 29+000(NIP) General Labour 5,000 5,500 4 1,250 B 22,000.00
26 Ali Anwar mazari Arz Mohammad GFC Ubaro Ghotki 30+000(NIP) Farming(Owner) 16,000 17,600 13 1,231 B 35,200.00
27 Mohammad Ramzan Bakhsh Khan Dasti GFC Ubaro Ghotki 40+000(NIP) Private Servant 8,000 8,800 8 1,000 B 22,000.00
28 Balach Khan Dasti Mohammad Ramzan GFC Ubaro Ghotki 40+000(NIP) Private Servant 6,000 6,600 7 857 B 22,000.00
29 Allah Rakhiyo Mohammad Ramzan GFC Ubaro Ghotki 40+100(NIP) General Labour 5,000 5,500 7 714 B 22,000.00
30 Nazir Ahmed Mehan Khan Malik GFC Ubaro Ghotki 40+200(NIP) General Labour 5,000 5,500 7 714 B 22,000.00
31 Veer Malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 4,500 4,950 4 1,125 B 22,000.00
32 Malook malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 6,000 6,600 7 667 B 22,000.00
33 Kashmir Malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 3,000 3,300 2 1,500 B 22,000.00
34 Hamal Mazari Mohkum Din GFC Ubaro Ghotki 41+000(NIP) Farming(Tenant) 5,000 5,500 6 833 B 22,000.00
35 Mir Hazar Mazari Kheno Khan GFC Ubaro Ghotki 41+000(NIP) Farming(Tenant) 5,000 5,500 1 833 B 22,000.00
36 Yousif Dasti Ali Nawaz Dasti GFC Ubaro Ghotki 41+500(NIP) Farming(Tenant) 6,000 6,600 7 857 B 22,000.00
37 Ali Nawaz Dasti Machro khan GFC Ubaro Ghotki 41+500(NIP) Farming(Tenant) 8,000 8,800 11 727 B 22,000.00
38 Dagha Khan Machro khan GFC Ubaro Ghotki 41+500(NIP) General Labour 5,000 5,500 8 625 B 22,000.00
39 Karam Ali Ghulam Ali Dasti GFC Ubaro Ghotki 43+300(NIP) General Labour 3,000 3,300 2 1,500 B 22,000.00
40 Abrar Ali Gulam Ali Dasti GFC Ubaro Ghotki 43+300(NIP) General Labour 3,000 3,300 3 1,000 B 22,000.00
41 Zahoor Ahmed Nabi Bux GFC ubaro Ghotki 43+500(NIP) General Labour 7,500 8,250 7 1,071 B 22,000.00
42 Farooq Nawab Khan GFC ubaro Ghotki 43+500(NIP) General Labour 6,000 6,600 3 2,000 B 22,000.00
43 Imam Ali Bilawal Dasti GFC Ubaro Ghotki 43+500(NIP) General Labour 2,000 2,200 2 1,000 B 22,000.00
44 Gulam Ali Mohmmad Ramzan GFC Ubaro Ghotki
43+300
Small Business 14,000 15,400 11 1,273 B 30,800.00
to
43+500
45 Mahboob Ali Memon Kaoro Khan GFC Ubaro Ghotki 43+500(NIP) Small Business 7,000 7,700 6 1,167 B 22,000.00
46 Barkatullah Dasti Faiz Mohammad GFC Ubaro Ghotki 43+500(NIP) General Labour 6,000 6,600 12 500 B 22,000.00
47 Ali Hasan Mirani Rais Gudo GFC Ubaro Ghotki 43+900(NIP) Fishing 4,000 4,400 9 444 B 22,000.00
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
144
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/
Low Income allowance (PKR)
Below
48 Sher Mohammad Nabi Bux GFC Ubaro Ghotki 44+00(NIP) Fishing 5,000 5,500 10 500 B 22,000.00
49 Muhammad Amin Dasti Salar Khan GFC Ubaro Ghotki 44+000(NIP) General Labour 6,000 6,600 5 1,200 B 22,000.00
50 Durr Muhammad Mirani Muhammad Hayat GFC Ubaro Ghotki 44+100(NIP) General Labour 3,000 3,300 9 333 B 22,000.00
51 Muneer Ahmed Shah Khair Shah GFC Ubaro Ghotki 44+100(NIP) General Labour 5,000 5,500 6 833 B 22,000.00
52 Muhammad Mureed Mirani
Muhammad Eidan GFC Ubaro Ghotki 44+150(NIP) General Labour 5,000 5,500 7 714 B 22,000.00
53 Abdul Ghani Mirani Kalu Khan GFC Ubaro Ghotki 44+150(NIP) General Labour 5,000 5,500 8 625 B 22,000.00
54 Haji Iqbal Chaoudhry Muhammad Rafiq GFC Ubaro Ghotki 44+250(NIP) General Labour 10,000 11,000 9 1,111 B 22,000.00
55 Papu Pathan Nawab Pathan GFC Ubaro Ghotki 44+300(NIP) General Labour 10,000 11,000 5 2,000 B 22,000.00
56 Ashraf Ali Qureshi Bindu GFC Ubaro Ghotki 44+350(NIP) General Labour 5,000 5,500 9 555 B 22,000.00
57 Muhammad Achar Piyaro GFC Ubaro Ghotki 44+400(NIP) General Labour 6,000 6,600 8 750 B 22,000.00
58 Muneer Ahmed Mirani Muhammad Mithal GFC Ubaro Ghotki 44+500(NIP) General Labour 3,000 3,300 3 1,000 B 22,000.00
59 Muhammad Mor Pir Bux Mirani GFC Ubaro Ghotki 44+550(NIP) General Labour 5,000 5,500 5 1,000 B 22,000.00
60 Samundar Khan Dawood Khan GFC Ubaro Ghotki 44+600(NIP) General Labour 8,000 8,800 15 533 B 22,000.00
61 Bhora Khan Badal Khan Dasti GFC Ubaro Ghotki 44+700(NIP) General Labour 5,000 5,500 9 556 B 22,000.00
62 Akbir Ali Dasti Ghamno Dasti GFC Ubaro Ghotki 44+750(NIP) General Labour 5,000 5,500 9 556 B 22,000.00
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
145
Sindh Water Sector Improvement Project
Sr. Name of Affected
Father's Name
Address
Profession
Poverty Status
No. Person Name of FO
Deh/Village Taluka District RD Monthly Income (2014)
Monthly Income (2016)
Family Size
Per Capita Income
Status Above/
Low Income allowance (PKR)
Below
63 Noor Din Mirani M.Bachal Mirani GFC Ubaro Ghotki 44+850(NIP) Fishing 3,000 3,300 2 1,500 B 22,000.00
64 Shahnawaz Dasti Lal Bux GFC Lal Bux Dasti Ubaro Ghotki 45+850(NIP) General Labour 5,000 5,500 9 556 B 22,000.00
65 Allah Jawayo Jamal din GFC Ubaro Ghotki 46+100(NIP) General Labour 4,000 4,400 4 1,000 B 22,000.00
66 Wahid Bux Mehrab Dasti GFC Ubaro Ghotki 74+200(NIP) General Labour 4,000 4,400 7 571 B 22,000.00
67 Kandho Khan M.Ismail Dasti GFC Ubaro Ghotki 47+900(NIP) Live Stock 4,000 4,400 4 1,000 B 22,000.00
68 M.Azeem Bhyo Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming (Owner)
15,000 16,500 11 1,364 B 33,000.00
69 Faiz Mohammad Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming(Owner) 10,000 11,000 9 1,111 B 22,000.00
70 Mohammad Haleem Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming(Owner) 15,000 16,500 18 833 B 33,000.00
71 Ali Gohar Kathoro GFC Ubaro Ghotki 49+100(NIP) Farming(Tenant) 8,000 8,800 11 727 B 22,000.00
72 Ghulam Hussaul M.Haleem GFC Ubaro Ghotki 49+100(NIP) Farming(Tenant) 3,000 3,300 5 600 B 22,000.00
73 Muj Ali Mirani Rahim Bux GFC Ubaro Ghotki 51+00(NIP) General Labour 4,000 4,400 6 667 B 22,000.00
74 Datto Mirani Lal Bux GFC Ubaro Ghotki 51+00(NIP) General Labour 8,000 8,800 11 727 B 22,000.00
75 Gul Mohammad Meerani
Koral GFC Ubaro Ghotki 52+800(NIP) General Labour 8,000 8,800 7 1,143 B 22,000.00
76 Chanesar Mirani Nangar Khan GFC Ubaro Ghotki 53+00(NIP) Fishing 4,000 4,400 7 571 B 22,000.00
77 Mir Khan Mirani Tagyo GFC Ubaro Ghotki 53+200(NIP) General Labour 3,000 3,300 4 750 B 22,000.00
78 Dado Murani Mir Khan GFC Ubaro Ghotki 53+200(NIP) Fishing 5,000 5,500 9 555 B 22,000.00
79 Liaqat Ali Mirani Mir Khan GFC Ubaro Ghotki 53+00(NIP) Fishing 5,000 5,500 9 555 B 22,000.00
80 Akhtar Hussain M.Hashim Mirani GFC Ubaro Ghotki 53+00(NIP) Fishing 4,000 4,400 5 800 B 22,000.00
81 Umed Ali Ahmed Khan GFC Mir Kosh Ubaro Ghotki 61+200(NIP) General Labour 4,000 4,400 7 571 B 22,000.00
82 Abdul Rehman Kosh Ahmed Khan GFC Mir Kosh Ubaro Ghotki 61+200(NIP) General Labour 5,000 5,500 7 714 B 22,000.00
83 Mohammad Adhyo Budhyo Kosh GFC Mir Kosh Ubaro Ghotki 61+300(NIP) General Labour 10,000 11,000 8 556 B 22,000.00
84 Baksho Kosh Budho GFC Mir Kosh Ubaro Ghotki 61+450(NIP) Farming(Tenant) 6,000 6,600 10 600 B 22,000.00
Grand Total 1,903,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
146
Sindh Water Sector Improvement Project
D.3. Details of Livelihood Allowance
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status Affected structure
Name of FO Deh/Village
Taluka District RD Monthly Income
Family Size
Per Capita Income
Status Above/ Below
Name of Structure
Type of construction
Size of Structure (sft/rft)
Livelihood Allowance
Three Months
Total Amount
Ghotki Feeder Canal (NIP)
1 Imam Din Malik Faiz Mohammad GFC Ubaro Ghotki 14+900(NIP)
Small Business
8,800
12
667 B
Shop Pacca 170
11,000 3
33,000 Shop Pacca
170
2 Shahmir Malik Chalaka Malik GFC Khohi Malik Ubaro Ghotki 14+950(NIP)
Small Business
5,500
5
1,000 B Shop(Wall) Pacca
220 11,000
3
33,000
3 Gulam Ali Mohmmad Ramzan
GFC Ubaro Ghotki 43+300 to 43+500
Small Business
15,400
11
1,273
B
Room Kacha 375
15,400 3 46,200
Room Pacca 304
B/Wall Kacha 1,116
Shop(Wall) Kacha 540
Shop Semi Pacca 308
Hand Pump Unit 1
4 Mahboob Ali Memon
Kaoro Khan GFC Ubaro Ghotki 43+500(NIP)
Small Business
7,700
6
1,167
B Shop Pacca 231
11,000 3
33,000
5 Sohbat Khan Mazari Ghazi Khan GFC Ubaro Ghotki
27+800(NIP)
Farming (Tenant) 9,900 10 900 B
Otaq Katcha 300 11,000 3
33,000
Total
178,200
D.4. Household monthly expenditure
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
Ghotki Feeder Canal (IP)
1 Shah Gul Mazari Dost Mohammad GFC Ubaro Ghotki 9+500(IP) Govt.Servant 8,000 7 1,143 B
12,000
2 Wallan Mazari Duno Mazari GFC Ubaro Ghotki 14+000(IP) Farming(Owner) 8,000 8 1,000 B
9,000
3 Pinyal Kosh Kambhir Kosh GFC Ubaro Ghotki 63+000(IP L/S) General Labour 7,000 8 875 B
8,000
Sub-Total 23,000 23 29,000
Ghotki Feeder Canal (NIP)
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
147
Sindh Water Sector Improvement Project
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
1 Faiz Mohammad Habiburahman GFC Ubaro Ghotki 7+900 (NIP) Farming(Owner) 11,000 4 2,750 A
14,000
2 Ghulam Hyder Abdul Karim GFC Ubaro Ghotki 7+900(NIP) Farming(Tenant) 7,000 4 1,750 B 7,000
3
Pir Bux Mir Hazar GFC Ubaro Ghotki 14+700(NIP) General Labour 8,000 7 1,143 B 8,500
4 Karim Bux Mirani Sacho GFC Ubaro Ghotki 14+500(NIP) General Labour 5,000 4 1,250 A
8,000
5 Bashir Ahmed Raheem Bux GFC Ubaro Ghotki 14+500(NIP) General Labour 5,000 2 2,500 A
7,000
6 Abdul Hakeem Malik Mitha Malik GFC Ubaro Ghotki 14+600(NIP) General Labour 7,000 12 583 B
9,000
7 Imam Din Malik Faiz Mohammad GFC Ubaro Ghotki 14+900(NIP) Small Business 8,000 12 667 B
8,000
8 Mohammad Bux Mohammad Waris Mazari GFC Khohi Malik Ubaro Ghotki 14+500(NIP) General Labour 5,000 8 625 B
6,500
9 Shahmir Malik Chalaka Malik GFC Khohi Malik Ubaro Ghotki 14+950(NIP) Small Business 5,000 5 1,000 B 7,000
10 Sohnno Mazari Khuda Bux GFC Ubaro Ghotki 18+000(NIP) Farming(Tenant) 5,000 6 833 B
6,500
11 Nihal Mazari Jalal Mazari GFC Ubaro Ghotki 18+200(NIP) General Labour 5,500 9 611 B
9,500
12 Shah Mohammad Qadir Bux Malik GFC Ubaro Ghotki 19+200(NIP) Farming(Tenant) 4,500 4 1,125 B
6,000
13 Ali Nawaz Qadir Bux Malik GFC Ubaro Ghotki 19+800(NIP) Farming(Tenant) 5,000 9 556 B
9,500
14 Ghulam Fareed Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 8,000 14 571 B
11,000
15 Dil Murad Ghulam Fareed GFC Ubaro Ghotki 27+300(NIP) Farming(Owner) 15,000 23 652 B
18,000
16 Hassan Ali Mazari Dil Murad Mazari GFC Punhal Khan Mazari Ubaro Ghotki 27+300(NIP) Farming (Tenant) 5,000 3 1,667 A
6,000
17 Yaqoob Mazari Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 5,000 11 454 B
9,600
18 Yaseen Mazari Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 3,000 4 750 B 4,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
148
Sindh Water Sector Improvement Project
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
19 Mir Muhammad Dil Murad Mazari GFC Ubaro Ghotki 27+300(NIP) Farming (Tenant) 3,000 4 750 B
4,000
20 Sohbat Khan Mazari Ghazi Khan GFC Ubaro Ghotki 27+800(NIP) Farming (Tenant) 9,000 10 900 B
10,500
21 Nazir Ahmed Mazari Ghulam Hyder GFC Punhal Khan Mazari Ubaro Ghotki 28+900(NIP) Private Servant 6,000 5 1,200 A
7,500
22 Wazir Ahmed Mazari Ghulam Hyder GFC Punhal Khan Mazari Ubaro Ghotki 28+900(NIP) Private Servant 6,000 9 667 B
10,000
23 Mohib Ali Mazari Gulam Mazari GFC Punhal Khan Mazari Ubaro Ghotki 28+800(NIP) Private Servant 6,000 12 500 B
9,000
24 Rehman mazari Behram Mazari GFC Ubaro Ghotki 29+000(NIP) General Labour 5,000 4 1,250 A
6,000
25 Ali Anwar mazari Arz Mohammad GFC Ubaro Ghotki 30+000(NIP) Farming(Owner) 16,000 13 1,231 A
16,000
26 Mohammad Ramzan Bakhsh Khan Dasti GFC Ubaro Ghotki 40+000(NIP) Private Servant 8,000 8 1,000 B
8,500
27 Balach Khan Dasti Mohammad Ramzan GFC Ubaro Ghotki 40+000(NIP) Private Servant 6,000 7 857 B
7,500
28 Allah Rakhiyo Mohammad Ramzan GFC Ubaro Ghotki 40+100(NIP) General Labour 5,000 7 714 B
7,500
29 Nazir Ahmed Mehan Khan Malik GFC Ubaro Ghotki 40+200(NIP) General Labour 5,000 7 714 B
8,000
30 Veer Malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 4,500 4 1,125 B 5,000
31 Malook malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 6,000 7 667 B
8,000
32 Kashmir Malik Mian Khan GFC Ubaro Ghotki 40+200(NIP) General Labour 3,000 2 1,500 A
4,000
33 Hamal Mazari Mohkum Din GFC Ubaro Ghotki 41+000(NIP) Farming(Tenant) 5,000 6 833 B
6,500
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
149
Sindh Water Sector Improvement Project
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
34 Mir Hazar Mazari Kheno Khan GFC Ubaro Ghotki 41+000(NIP) Farming(Tenant) 5,000 6 833 B
6,000
35 Yousif Dasti Ali Nawaz Dasti GFC Ubaro Ghotki 41+500(NIP) Farming(Tenant) 6,000 7 857 B
7,500
36 Ali Nawaz Dasti Machro khan GFC Ubaro Ghotki 41+500(NIP) Farming(Tenant) 8,000 11 727 B
10,000
37 Dagha Khan Machro khan GFC Ubaro Ghotki 41+500(NIP) General Labour 5,000 8 625 B
8,500
38 Karam Ali Ghulam Ali Dasti GFC Ubaro Ghotki 43+300(NIP) General Labour 3,000 2 1,500 A
4,000
39 Abrar Ali Gulam Ali Dasti GFC Ubaro Ghotki 43+300(NIP) General Labour 3,000 3 1,000 B 4,500
40 Zahoor Ahmed Nabi Bux GFC ubaro Ghotki 43+500(NIP) General Labour 7,500 7 1,071 B 9,000
41 Farooq Nawab Khan GFC ubaro Ghotki 43+500(NIP) General Labour 6,000 3 2,000 B 6,000
42 Imam Ali Bilawal Dasti GFC Ubaro Ghotki 43+500(NIP) General Labour 2,000 2 1,000 B
3,500
43 Gulam Ali Mohmmad Ramzan GFC Ubaro Ghotki 43+300 to 43+500
Small Business 14,000 11 1,273 A
15,000
44 Abandonned* GFC Ubaro Ghotki 43+500(NIP)
45 Mahboob Ali Memon Kaoro Khan GFC Ubaro Ghotki 43+500(NIP) Small Business 7,000 6 1,167 B 7,000
46 Abandonned* GFC Ubaro Ghotki 43+500(NIP)
47 Barkatullah Dasti Faiz Mohammad GFC Ubaro Ghotki 43+500(NIP) General Labour 6,000 12 500 B
11,000
48 Ali Hasan Mirani Rais Gudo GFC Ubaro Ghotki 43+900(NIP) Fishing 4,000 9 444
B
10,000
49 Sher Mohammad Nabi Bux GFC Ubaro Ghotki 44+00(NIP) Fishing 5,000 10 500 B
9,500
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
150
Sindh Water Sector Improvement Project
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
50 Muhammad Amin Dasti Salar Khan GFC Ubaro Ghotki 44+000(NIP) General Labour 6,000 5 1,200 A
7,000
50 Durr Muhammad Mirani Muhammad Hayat GFC Ubaro Ghotki 44+100(NIP) General Labour 3,000 9 333 B
8,000
52 Muneer Ahmed Shah Khair Shah GFC Ubaro Ghotki 44+100(NIP) General Labour 5,000 6 833 B
7,000
53 Muhammad Mureed Mirani Muhammad Eidan GFC Ubaro Ghotki 44+150(NIP) General Labour 5,000 7 714 B
7,000
54 Abdul Ghani Mirani Kalu Khan GFC Ubaro Ghotki 44+150(NIP) General Labour 5,000 8 625 B
8,500
55 Abandonned* GFC Ubaro Ghotki 44+200(NIP)
56 Haji Iqbal Chaoudhry Muhammad Rafiq GFC Ubaro Ghotki 44+250(NIP) General Labour 10,000 9 1,111 B
10,000
57 Papu Pathan Nawab Pathan GFC Ubaro Ghotki 44+300(NIP) General Labour 10,000 5 2,000 A
9,000
58 Ashraf Ali Qureshi Bindu GFC Ubaro Ghotki 44+350(NIP) General Labour 5,000 9 555 B
9,000
59 Muhammad Achar Piyaro GFC Ubaro Ghotki 44+400(NIP) General Labour 6,000 8 750 B
8,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
151
Sindh Water Sector Improvement Project
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
60 Muneer Ahmed Mirani Muhammad Mithal GFC Ubaro Ghotki 44+500(NIP) General Labour 3,000 3 1,000 B
4,500
61 Muhammad Mor Pir Bux Mirani GFC Ubaro Ghotki 44+550(NIP) General Labour 5,000 5 1,000 B
7,000
62
Samundar Khan Dawood Khan GFC Ubaro Ghotki 44+600(NIP) General Labour 8,000 15 533 B
14,000
63 Bhora Khan Badal Khan Dasti GFC Ubaro Ghotki 44+700(NIP) General Labour 5,000 9 556 B
8,500
64 Akbir Ali Dasti Ghamno Dasti GFC Ubaro Ghotki 44+750(NIP) General Labour 5,000 9 556 B
10,000
65 Noor Din Mirani M.Bachal Mirani GFC Ubaro Ghotki 44+850(NIP) Fishing 3,000 2 1,500 A
4,000
66 Abondonned* GFC Ubaro Ghotki 44+800(NIP)
67 Shahnawaz Dasti Lal Bux GFC Lal Bux Dasti Ubaro Ghotki 45+850(NIP) General Labour 5,000 9 556 B
8,000
68 Allah Jawayo Jamal din GFC Ubaro Ghotki 46+100(NIP) General Labour 4,000 4 1,000 B
6,000
69 Wahid Bux Mehrab Dasti GFC Ubaro Ghotki 74+200(NIP) General Labour 4,000 7 571 B
6,000
70 Kandho Khan M.Ismail Dasti GFC Ubaro Ghotki 47+900(NIP) Live Stock 4,000 4 1,000 B 5,000
71 M.Azeem Bhyo Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming (Owner) 15,000 11 1,364 A
16,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
152
Sindh Water Sector Improvement Project
Sr. No.
Name of Affected Person
Father's Name
Address
Profession
Poverty Status
Name of FO Deh/Village
Taluka District RD Monthly Income (2014)
Family Size
Per Capita Income
Status Above/ Below
Monthly Expenditure
72 Faiz Mohammad Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming(Owner) 10,000 9 1,111 B
10,000
73 Mohammad Haleem Karam Khan GFC M.Azeem Bhyo Ubaro Ghotki 49+100(NIP) Farming(Owner) 15,000 18 833 B
20,000
74 Ali Gohar Kathoro GFC Ubaro Ghotki 49+100(NIP) Farming(Tenant) 8,000 11 727 B 12,000
75 Ghulam Hussaul M.Haleem GFC Ubaro Ghotki 49+100(NIP) Farming(Tenant) 3,000 5 600 B 6,000
76 Muj Ali Mirani Rahim Bux GFC Ubaro Ghotki 51+00(NIP) General Labour 4,000 6 667 B
5,500
77 Datto Mirani Lal Bux GFC Ubaro Ghotki 51+00(NIP) General Labour 8,000 11 727 B
10,000
78 Abondonned* GFC Ubaro Ghotki 52+100(NIP)
79 Abondonned* GFC Ubaro Ghotki 52+400(NIP)
80 Gul Mohammad Meerani Koral GFC Ubaro Ghotki 52+800(NIP) General Labour 8,000 7 1,143 B 9,000
81 Shahid Noor Hasan GFC Ubaro Ghotki 52+800(NIP) General Labour 5,000 2 2,500 A 5,000
82 Chanesar Mirani Nangar Khan GFC Ubaro Ghotki 53+00(NIP) Fishing 4,000 7 571 B 7,500
83 Mir Khan Mirani Tagyo GFC Ubaro Ghotki 53+200(NIP) General Labour 3,000 4 750 B
6,000
84 Dado Murani Mir Khan GFC Ubaro Ghotki 53+200(NIP) Fishing 5,000 9 555 B 8,500
85 Liaqat Ali Mirani Mir Khan GFC Ubaro Ghotki 53+00(NIP) Fishing 5,000 9 555 B 9,000
86 Akhtar Hussain M.Hashim Mirani GFC Ubaro Ghotki 53+00(NIP) Fishing 4,000 5 800 B 8,000
87 Umed Ali Ahmed Khan GFC Mir Kosh Ubaro Ghotki 61+200(NIP) General Labour 4,000 7 571 B
6,000
88 Abdul Rehman Kosh Ahmed Khan GFC Mir Kosh Ubaro Ghotki 61+200(NIP) General Labour 5,000 7 714 B
6,500
89 Mohammad Adhyo Budhyo Kosh GFC Mir Kosh Ubaro Ghotki 61+300(NIP) General Labour 10,000 8 556 B
10,000
90 Baksho Kosh Budho GFC Mir Kosh Ubaro Ghotki 61+450(NIP) Farming(Tenant) 6,000 10 600 B 10,000
Sub-Total 515,000 622 696,100
Grand Total 725,100
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
153
Sindh Water Sector Improvement Project
D.5. Long Distance Transport Allowance
Sr. No
Name of Affected Person (head of household)
Location on embankment (RD)
Occupation
Resettlement Location Relocation Distance
Long Distance Transport Allowance (PKR)
1 Nazir Ahmed 40+200(NIP) General Labour Baksha pur Village 65 km 77,000
2 Veer Malik 40+200(NIP) General Labour Baksha pur Village 65 km 77,000
3 Malook malik 40+200(NIP) General Labour Baksha pur Village 65 km 77,000
4 Kashmir Malik 40+200(NIP) General Labour Baksha pur Village 65 km 77,000
5 Hamal Mazari 41+000(NIP) Farming (Tenant)
Baksha pur Village 65 km 77,000
6 Mir Hazar Mazari 41+000(NIP) Farming (Tenant)
Baksha pur Village 65 km 77,000
7 Yousif Dasti 41+500(NIP) Farming (Tenant)
Baksha pur Village 65 km 77,000
8 Ali Nawaz Dasti 41+500(NIP) Farming (Tenant)
Baksha pur Village 65 km 77,000
9 Dagha Khan 41+500(NIP) General Labour Baksha pur Village 65 km 77,000
Total 693,000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
154
Sindh Water Sector Improvement Project
Appendix E. Details of Affected Farmers
Government Land (within ROW) Under Crop IP
RD Location Cultivate Land (Acres)
No. of Farmers
0 to 5 IP 10.75 Pahlwan Chacher and Chalo Chacher
9 to 11+500 IP 4.60 Allah Rakhio Malik
11+500 to 13+000 IP 1.40 Amanullah Khan Mazari
13+00 to 14+500 IP 1.00 Kati Khan Mazari
14+500 to 16+00 IP 2.75 Chalo Khan Mazari and Kati Khan Mazari
16+00 to 20+00 IP 7.00 Ghulam Nabi
20+00 to 22+00 IP 3.60 Daim Chacher
22+00 to 24+00 IP 3.90 Rais Gulan
24+500 to 25+00 IP 1.00 Hayat Mohd Chacher
25+800 to 27+300 IP 2.58 Chalo Khan Chacher
27+500 to 29+00 IP 1.89 Chalo Khan Chacher
29+00 to 37+00 IP 14.50 Sharif Chohan,Ghullam Farid
37+00 to 38+400 IP 2.73 Mohd Amin ,Khameso Chacher
38+400 to 39+600 IP 2.75 Sachal Merani, Imam Bux Merani
39+600 to 42+150 IP 4.40 Haji Ahmed,Bux Malik,Allah Bachio Malik Dani Bux Malik,Hasan Malik,Gulab Malik
42+150 to 43+500 IP 3.00 Allah Divao Mirbahar,Wahid Bux , Munir Dahar, Haji Gullam Hyder Dashti cell: 0300-9813091
43+625 to 46+500 IP
3.96 Gulbahar ,Haji Mohd Mosa, Gullam Farid,Bux Ali,Mohd Ali Merani
46+500 to 47+700 IP 2.47 Asgar ali & Kalo Merani
48+00 to 51+100 IP 3.90 Shaban Merani,Nasir Merani,Allah Bux Merani
51+00 to 61+300 IP
4.00 Shafi Mohd Kosh,Javed ,Nihal,Ramzan,Hayat,Karim Bux ,Nazir,Julan,Lal khan Kosh
61+400 to 62+800 IP
3.21 Abdul Jabar Kossh,Wahed ALI Solangi,Ayjaz ali Kosh ,Nawab Ali Kosh
63+00 to 73+00 IP
28.70 Abdul Jabar Kossh,Nawab Khan Kosh,Bachal Kosh and Yaseen Solangi
97+00 to 110+00 IP 35.00 Asgar Jatoi,Jalal Jatoi,Wazir Jatoi,Gulan Gurgez
110+00 to 125+00 IP
39.60 Abid Ali Jatoi,Shahnawaz Baloch,Azam Balouch and Akhond Jatoi
Total Land ( Acres) 188.69
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
155
Sindh Water Sector Improvement Project
Government Land (within ROW) Under Crop NIP
RD Location Cultivate Land (Acres)
No. of Farmers
1+00 to 7+00 NIP 13.77 Parvez Mazari ,Shah Gul Mazari
7+00 TO 8+00 NIP 3.28 Faiz Mohd Mazari
8+00 TO 9+00 NIP 1.14 Gulam Hyder ,Pir bux Mazari
9+00 TO 10+500 NIP 2.58 Ibrahim Mazari
10+500 TO 15+00 NIP 12.91 Wallan Mazari, Karim Bux Mazari
19+00 to 25+500 NIP 2.38 Nihal Mazari ,Ali Mohd Mazari ,Karim Bux Mazari
25+500 43+500 NIP 8.00
Ali Gohar Mazari,Ibrahim Mazari,Muhib Mazari,Nazir Mazari,Abdul Sattar Mazari, Yar Ali Mazari,Yaseen Merani,Abbas Chachar,Allah Diwao,Haq Nawaz,Malook Merani,M.Qasim Merani,Fakir merani,Khambro Merani,Hazoor Bux Merani,Lalo Gulam Rasool Pathan,Akbar Dashti,Ghullam Ali Dashti
46+800 to 49+600 NIP 2.57 Sarwar Merani,Sozal Khan Dashti
63+500 to 70+00 NIP 12.00 Gulam Farid Solangi ,Ariz Mohd Chacher
97+00 to 100+00 NIP 2.41 Abdul Karim Dhondho ,Gullam Qadir Dhondho
100+00 to 110+00 NIP 28.70 Mohd Youns Gurgez,Nawab Khan Dhondho,
110+00 to 115+800 NIP 16.64 Piyar Ali Dhondho,Raham ali and Nawaz ali Dhondho,Khair Mohd Solangi
117+200 to 117+300 NIP 0.5 Mustaq Solangi
117+500 125+000 NIP 12.00 Karam ali Dhondho,Ashiq ali Gurgez,Abdul Gafioor Gurgez ,Shahnawaz Gurgez,allah wario Solangi
Total Land ( Acres) 118.88
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
156
Sindh Water Sector Improvement Project
The grass root consultations were carried out at the following sub-project locations:
Details of Grass Root Consultation with respect to Sub-project Components are given below:
Location Names and No. of Participants Key Issues Discussed
RD 1+500
Place: Village Natho Khan Mazari at RD 1+000 (IP)
Ghotki Feeder
Consultation Date: 16-08-2014
Total No. of Participants:
(23)
PIC
1 Mohammad Raheem
2 Ishfaq Ali Makhdoom
3 Mujeeb-ur-Rahman
4 MohammadJuman
5 Shadab Bughio
6 Sajjad Veesar
7 Anwar Solangi
Community
1.Sadiq Ali Mazari
2.Ameer Bux Mazari
3.Abdul Quyum Mazari
4.Sikander Ali Mazari
5. Mahboob Ali Kosh
6. Anwar Ali Malik
7.Munwar Solagi
8.Sikandar Ali
9.Ali Bux
10.Kandero
11.Abul Majeed
12.Lalan Khan
13.Manzoor Ahmed
14.Mohammad Hajan
15.Hasan Ali
16.Fida Hussain
The Aims & objectives of Consultative Meeting. Mr.Mohammad Raheem, Sr: Sociologist (PIC), briefed about the proceeding under WSIP project for rehabilitation will be carried out under Contract WSIP/B1/GF/01
The participants were informed in the consultative meeting about the civil works, those will be carried out under Contract WSIP/B1/GF/01
Govt: of Sindh with the help of Govt: of Pakistan and world Bank to improve the water supply efficiency of the Ghotki Feeder.
Q1 What are your opinion/suggestion about the canal works?
Ans: Canal works shall be carried put to increase water in the off taking canal. Canal created W/L and salinity in head reaches of the canal
Q: How to control the water logging and salinity.
Ans: Canal banks shall be lined; silt shall be removed for the bed of canal.
Q: Canal Head Regulators will be reconstructed to pass more water
Ans: Head Regulators shall be constructed to increase flow of water
Q: For the construction of new Head Regulators private land may be required shall you people cooperate to get some private land?
Ans: We are small land owner and will not provide land .Govt: shall pay cost of land according to the market rates.
Q; Construction some house of Head Regulators, strengthen the canal banks the unauthorised structures will be damage?
Ans: We are poor and have no land to establish our housed our housed shall be protected.
Q: During Construction works, some houses / shops and religious structures on the canal banks will be affected?
Ans: We shall cooperate with contractor to carryout the canal works.
Q: During the desilting of canal a huge quantity of silt will be removed from canal where we put the silt?
Ans: We all jointly find the way to dispose the silt there are some depression on the outer side of canal and spoil may be dispose of there.
Q: Canal berms will be cut, how will the contractor do the works where the houses /shops are constructed on the berm of the canal?
Ans: When there is no space you shall line the canal bank. Stone pitching shall be carried out on the banks of canal. Killa bushing shall be carried out to avoid the houses, shops and religious structures.
Assure the employment of local community in project works
Construction and rehabilitation works may be carried out by International Contractor, so that to maintain the quality
Appendix F. Grass Root Consultations
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
157
Sindh Water Sector Improvement Project
Location Names and No. of Participants Key Issues Discussed
of work
Construction work shall be carried out due to closure of canal
Project shall provide education and health facilities in the command of Ghotki canal.
Place:Villag Hullar Chachar RD-25+000
Consultation Date: 17-08-2014
Total No. of Participants: 27
PIC
1.Mohammad Raheem
2 Ishfaq Ali Makhdoom
3. Mujeeb-ur-Rahman
4. MohammadJuman
5. Shadab Bughio
6. Sajjad Veesar
7. Anwar Solangi
Community
1.Fayaz Ahmed Chachar
2.Raza Mohammad Chachar
3.Asif Ali Chachar
4.Shah Gul
5.Sadaqat Ali
6.Nazeer Ahmed Chachar
7.Shahnawaz Meerani
8.Haqnawaz Soomro
9.Allah Bux Chachar
10.Mukhtiar Chachar
11.Aslam Chachar
12.Wali Mohammad
13.Shah Gul
14.Nabi Bux
15.Khanan
16.Fazal Ali
17Aftab Ahmed
18.Faheem Chachar
19.Abdul Khalique
20.Raise Ahmed
The Aims & objectives of Consultative Meeting. Mr.Mohammad Raheem, Sr: Sociologist (PIC), briefed about the proceeding under WSIP project for rehabilitation will be carried out under Contract WSIP/B1/GF/01
The participants were informed in the consultative meeting about the civil works, those will be carried out under Contract WSIP/B1/GF/01
Objectives of the consultative meeting were to brief the participants about the civil works, those will be carried out under Contract WSIP/B1/GF/01
1.Canal created w/l desilting
2. Stone pitching shall be carried out the canal banks.
3. Canal bank is raised about 6 to 10 feet, it is urgently required desilting.
4. Canal bed and banks shall be lined from RD-0 to RD-63.
5. Regarding the disposal of silt from canal, we will jointly find the place to dispose the excavated material.
6. Avoid to damage the housed/shops.
7. Religious structure shall be avoided to damage.
8. There are gaps between to dispose the silt.
9. We will not vacate the houses where we shall go, who will pay the construction cost.
Place:Mureed Shakh RD-43
Consultation Date:
12-08-2014
Total No. of Participants: 47
PIC
1.Mr Mahe (MML)
2.Mr Neil (MML)
3.Mr Nazeer Ahmed Lashari (PIC)
4.Mohammad Raheem(PIC)
5. Mujeeb-ur-Rahman(PIC )
6. MohammadJuman (PIC)
7.Ishfaq Ali Makhdoom (PIC )
8.Sajjad ALI Veesar (PIC)
9.Shadab Bughio (PIC)
10.Anwar Ali Solangi (PIC )
11.Tariq Bin Asad (PIC )
12.Tariq Abbasi (PIC )
The Aims & objectives of Consultative Meeting. Mr.Mohammad Raheem, Sr: Sociologist (PIC), briefed about the proceeding under WSIP project for rehabilitation will be carried out under Contract WSIP/B1/GF/01
The participants were informed in the consultative meeting about the civil works, those will be carried out under Contract WSIP/B1/GF/01
Objectives of the consultative meeting were to brief the participants about the civil works, those will be carried out under Contract WSIP/B1/GF/01
1. Construction works shall be carried out in a way to avoid houses.
2. It is very difficult to shift from here we have no other place to live.
3. For desilting there are some gaps in between houses,
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
158
Sindh Water Sector Improvement Project
Location Names and No. of Participants Key Issues Discussed
13.Aurangzeb Almani (PIC )
14.Imtiaz Ali Odho (AWB)
15.Sajan Ghanghro (AWB)
16.Imdad Meerani (Irri)
17.Sikandar Mazari (Irri)
18.Sajan Khan (AWB)
19 Mohammad Younis (AWB)
20. Ali Bux Mahar (AEN Irri:)
21.Abdul Majeed Sub:eng (Irri:)
Community
1.Mohammad Ismail Meerani
2.Kora Dasti
3.Mohammad Ali
4.Akhtrar Hussain
5.Nazeer Ahmed Beldar
6.Shahnawaz (Chowkidar)
7.Ghulam Haider (Landlord)
8.Ashiq Hussain Meerani
9.Haleemullah 10.Dasti(Shopkeeper)
11.Karam Ali Dasti
12.Abdul Latif Dasti
13.Shahzado Dasti
14.Khuda Bux Dasti
15.Hakim ALI Dasti
16.Shaman Ali Meerani
17.Ghulam Ali
18.Mohammad Amin Dasti
19.Zahoor Ahmed Meerani
20.Ghulam Farid (Revenue)
21.Mohammad Tariq
22.Mohammad Sharif Malik
23.Sher Mohammad Meerbhar
24.Mataro Khan Gopang
25.Syed Suleman Shah
26.Iqbal Ahmed Malik
where you put the silt material.
4. Berms of the canal shall be strengthening by making juck work.
5. We shall provide a way for machinery during construction work.
6. Excavated material shall be placed in right of way.
7. Crop compensation shall be given to damage the crop in right of way.
8. If some structure will be affected during construction we shall coordinate to with Irrigation Department.
9. Local contractor will not do the proper work.
10. It will be better to give contract to foreign construction company.
11. Local people shall be employed in construction work.
Place:Village Meer Kosh RD-63
Consultation Date:
12-08-2014
Total No. of Participants: 39
PIC
1.Mr Mahe (MML)
2.Mr Neil (MML)
3.Mr Nazeer Ahmed Lashari (PIC)
4.Mohammad Raheem (PIC)
5. Mujeeb-ur-Rahman (PIC )
6. MohammadJuman (PIC)
7.Ishfaq Ali Makhdoom (PIC )
8.Sajjad ALI Veesar (PIC)
9.Shadab Bughio (PIC)
10.Anwar Ali Solangi (PIC )
11.Tariq Bin Asad (PIC )
1. Project works are necessary to improve canal efficiency.
2. Desilting must be carried out.
3. Bed level of the canal rise 4 to 8 feet at different locations.
4. Canal shall be lined, if not possible stone pitching shall be carried out.
5. Very poor people are residing near the canal banks their houses shall avoided to demolish.
6. We will cooperate with contractor and find the way for machinery.
7. We are poor and small land owner’s cannot provide land w/o project.
8. Local people shall be employed in project works.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
159
Sindh Water Sector Improvement Project
Location Names and No. of Participants Key Issues Discussed
12.Tariq Abbasi (PIC )
13.Aurangzeb Almani (PIC )
14.Imtiaz Ali Odho (AWB)
15.Sajan Ghanghro (AWB)
16.Imdad Meerani (Irri)
17.Sikandar Mazari (Irri)
Community
1.Haji Abdul Ghani Kosh
2.Meer Hasan Kosh
3.Bhooral Kosh
4.Abdul Fatah Kosh
5.Mohammad Paryal Kosh
6.Hanif Kosh
7.Allahwarayo Kosh
8.Mohammad Anwar Kosh
9.Aurangzeb Arbani
10.Ghulam Rasool
11.Gahno Khan
12.Mohammad Hassan
13.Haji Ghulam Nabi
14.Rano Kosh
15.Ranjhan
16.Nizamuddin
17.Waryo Kosh
18.Asghar Ali
19.Punhal Kosh
20.Koro Kosh
21.Haq Nawaz
22.Ghulam Rasool
9. RD-63 Kosh and Solangi are fighting since last eight years kosh suggested the only kosh people be given employed the other one not allowed in the area.
10. Contractor shall keep the staff at work place and camp.
11. Ensure the free mobility of women was working in field for crop harvesting/threshing, fodder cutting etc.
12. Irrigation Department shall provide the security to local community during construction work.
Place:Wasti pull Jam Khan Mohammad RD-101
Consultation Date:
18-08-2014
Total No. of Participants: 25
PIC
1.Mohammad Raheem
2. Mujeeb-ur-Rahman
3. MohammadJuman
4.Ishfaq Ali Makhdoom
5.Shadab Bughio
6.Sajjad Veesar
7.Anwar Solangi
8. Imdad Ali Meerani (Irri :)
Community
1.Aijaz Ahmed Samejo
2.Imam Din Samejo
3.Akhtiar Samejo
4.Soomar Ali Samejo
5.Sajid Ali Samejo
6.Imtiaz Ali Samejo
The Aims & objectives of Consultative Meeting. Mr.Mohammad Raheem, Sr: Sociologist (PIC), briefed about the proceeding under WSIP project for rehabilitation will be carried out under Contract WSIP/B1/GF/01
The participants were informed in the consultative meeting about the civil works, those will be carried out under Contract WSIP/B1/GF/01
1. Canal banks strengthen work shall be carried out on emergency basis.
2. Canal bridge at RD-101 shall be reconstructed.
3. Bridge is narrow sugarcane trolley cannot cross the bridge.
4. Canal banks are in poor condition anytime breach in the canal banks may occur.
5. Canal berms are disappearing and shall be re-constructed.
6. Canal created w/l and salinity and crop are destroyed.
7. Water logging and salinity damage the village.
8. Cultivated area has been converted in to the ponds.
9. Canal may be lined /stone pitching with desilting.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
160
Sindh Water Sector Improvement Project
Location Names and No. of Participants Key Issues Discussed
7.Niaz Ahmed Samejo
8.Abdul Rasheed Samejo
9.Karim Khan
10.Jam Mohammad
11.Mohammad Hussain
12.Yar Mohammad
13.Ishaque
14.Ali Nawaz
15.Rajib Ali
16.Safdar Ali
17.Abdul Hameed
10. Desilting shall be carried out there is sufficient space for excavated material.
11. Our land is under water you put the material in our land.
12. There are WAPDA tubewells in poor condition the tubewells shall be restored to control water logging and salinity.
Place:RD-127
Place: Allah Dad Chandio
Consultation Date: 20-08-2014
Total No. of Participants: 29
PIC
1.Mohammad Raheed
2. Mujeeb-ur-Rahman
3. MohammadJuman
4.Ishfaq Ali Makhdoom
5.Shadab Bughio
6.Sajjad Veesar
7.Anwar Solangi
8. Imdad Ali Meerani (Irri :)
9. Mukhtiar Ahmed Kolachi (Irri :)
10. Hasan Ali Kolachi (Irri :)
11. Imdad Ghup (Irri :)
12. Safeer Ahmed Kolachi (Irri :)
13. Mohammad Ishaq Kolachi (Irri :)
14. Naveed Ahmed (Irri :)
Community
1.Allah Bachayo Rind
2.Sakhi Bux Rind
3.Allah Bux
4.Mushtaq Ali
5.Mohammad Akram
6.Saleem Ahmed
7.Iqbal
8.Zulifqar Ali
9.Imran Ahmed
10.Waseem Ahmed
11.Aziz Ahmed
12.Chakar Khan Rind
13.Abdul Latif Rind
14.Waheed Ali
15.Manzoor Khan
The Aims & objectives of Consultative Meeting. Mr.Mohammad Raheem, Sr: Sociologist (PIC), briefed about the proceeding under WSIP project for rehabilitation will be carried out under Contract WSIP/B1/GF/01
The participants were informed in the consultative meeting about the civil works, those will be carried out under Contract WSIP/B1/GF/01
Objectives of the consultative meeting were to brief the participants about the civil works, those will be carried out under Contract WSIP/B1/GF/01
1. Bed level of the canal has risen about 6 to 7 feet.
2. Canal banks shall be lined /stone pitching with juck works.
3. Canal created water logging and salinity.
4. Villagers near the canal become abandoned, people migrated to other place/near town.
5. Agricultural land has been changed in fish pond.
6. Animals and human population is severely affected due to water borne diseases and snake biting.
7. Ground water is mixed with sewerage water and it is difficult to village people to get sage drinking water.
8. Local people are complaining of stomach diseases.
9.Some people requested for employment during project works
Response of Religious Structure: The outcome of the meetings with the affectees regarding religious
structures is that, first priority should be given to avoid these structures because shifting of the structures is
not acceptable to the affectees.
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
161
Sindh Water Sector Improvement Project
G.1. Detail of market Rates for Pacca House
Appendix G. Details of Asset Valuation
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
162
Sindh Water Sector Improvement Project
G.2. Detail of market Rates for Semi Pacca House
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
163
Sindh Water Sector Improvement Project
G.3. Detail of market Rates for Kacha House
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
164
Sindh Water Sector Improvement Project
G.4. Detail of market Rates for Semi Pacca Boundary Wall
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
165
Sindh Water Sector Improvement Project
G.5. Detail of market Rates for Kacha Boundary Wall
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
166
Sindh Water Sector Improvement Project
G.6. Detail of market Rates for Pacca Boundary Wall
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
167
Sindh Water Sector Improvement Project
G.7. Detail of market Rates for Kacha Hut
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
168
Sindh Water Sector Improvement Project
G.8. Detail of market Rates for Straw Hut
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
169
Sindh Water Sector Improvement Project
G.9. Market Quotations
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
170
Sindh Water Sector Improvement Project
H.1. RD 63+000
Appendix H. Deh Maps
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
171
Sindh Water Sector Improvement Project
H.2. RD 127+000
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
172
Sindh Water Sector Improvement Project
I.1. Embankment Works Corridor of Impact – Cross Sections
Appendix I. Corridor of Impact
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
173
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
174
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
175
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
176
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
177
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
178
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
179
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
180
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
181
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
182
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
183
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
184
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
185
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
186
Sindh Water Sector Improvement Project
I.2. Corridor of Impact for Realignment of Offtaking Canal – Layout Plans
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
187
Sindh Water Sector Improvement Project
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
189
Sindh Water Sector Improvement Project
Photo J.1: Straw House at Ghotki Feeder
Photo J.2: Straw House at Ghotki Feeder
Photo J.3: Picture of PIC and AWB representative and
local community
Photo J.4: Straw House at Ghotki Feeder
Appendix J. Pictorial View
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
190
Sindh Water Sector Improvement Project
Photo J.5: Community Mosque
Photo J.6: A view of pacca shop
Photo J.7: A Kacha House at Ghotki Feeder
Photo J.8: A Kacha House at Ghotki Feeder
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
191
Sindh Water Sector Improvement Project
Photo J.9: A view of kacha house
Photo J.10: Picture of PIC and Irrigation Department and
local community
Photo J.11: Picture of PIC and Irrigation Department and
local community
Photo J.12: A view of pacca house
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
192
Sindh Water Sector Improvement Project
J.1. Women Consultation in the Project Area Photo J.13: Women consultation meeting with local
community at Ghotki Feeder Canal
Photo J.14: Female Interviewer of PIC meeting with local
community at Ghotki Feeder Canal
Photo J.15: Women Consultation with women washing
cloths at Ghotki Feeder Canal
Photo J.16: Female Interviewer busy in data collection at
Ghotki Feeder Canal
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
193
Sindh Water Sector Improvement Project
Photo J.17 Women Consultation with local women at
Ghotki Feeder Canal
Photo J.18 Female Interviewer women consultation at
Ghotki Feeder Canal
Photo J.19 W Women Consultation with local women at
Ghotki Feeder Canal
Photo J.20 Female Interviewer busy in data collection at
Ghotki Feeder Canal
253277/EVT/WER/265/H May 2016 C:\Users\jew47974\Desktop\Temp\2016-05-15\Rev H\2016-05-15 Resettlement Action Plan for Contract WSIP-B1-GF-01 (Rev H).docx
194
Sindh Water Sector Improvement Project
Appendix K. Relocation Plans
Top Related