JIGAWA STATE GOVERNMENT
DUE PROCESS AND PROJECT MONITORING BUREAU
OFFICE OF THE EXECUTIVE GOVERNOR
END OF YEAR PROJECTS REPORT
JANUARY TO DECEMBER, 2019
WEB: WWW.JIGAWADUEPROCESS.COM
EMAIL: [email protected]
CONTENTS
SECTION (A) - EXECUTIVE SUMMARY
SECTION (B) - CHARTS
SECTION (C) - PRE-CONTRACTS EVALUATIONS JANUARY TO DECEMBER, 2019
SECTION (D) - CONTRACTS AWARDED JANUARY TO DECEMBER, 2019
SECTION (E) - COMPLETED PROJECTS
SECTION (F) - ON-GOING PROJECTS
- MINISTRY OF HEALTH - MINISTRY OF WATER RESOURCES - MINISTRY OF WORKS AND TRANSPORT - MINISTRY OF EDUCATION, SCIENCE & TECHNOLOGY - MINISTRY OF LAND AND HOUSING - MINISTRY OF COMMERCE - DUTSE CAPITAL DEVELOPMENT AUTHORITY - CABINET OFFICE - MINISTRY OF INFORMATION - JIGAWA SATTE POLYTECHNIC, DUTSE - MINISTRY OF FINANCE AND ECONOMIC PLANNING - JIGAWA STATE COLLEGE OF ISLAMIC & LEGAL STUDIES, RINGIM - BINYAMINU USMAN POLYTECHNIC, HADEJIA - MINISTRY OF ENVIRONMENT - JIGAWA STATE INFORMATICS INSTITUTE, KAZAURE - GOVERNMENT HOUSE - DIRECTORATE OF EONOMIC EMPOWEERMENT - DEPUTY GOVERNOR’S OFFICE
EXECUTIVE SUMMARY.
The 2019 Budget termed “Budget for Sustained Economic Growth and Social Transformation 11” was conceived to sustain the
momentum of progress towards the attainment of medium-term objective of creating a self-sustaining local economy that fully
leverages on productive potentials of the state. Also to continuously improve access to, and quality of, public service delivery
particularly in the basic social services sectors including social protection.
In view of the above statement from year 2019 budget speech by His Excellency the Governor, the Bureau as an organ responsible for
monitoring the implementation of capital projects hereby present its end of year report.
The end of year 2019 report consists of four sections only: Pre-contract Evaluations, Contracts Awarded, Completed Projects and
Ongoing Projects report.
PRE-CONTRACT EVALUATIONS.
As at the end of reporting period, projects worth N14,727,910,392.66 only were submitted for vetting out of which the Bureau
recommended N14,520,849,570.67 only for execution thereby saving N207,060,821.99 only (1.4%) in favor of the government. This
portrays a positive response by government agencies in terms of adequate costing of their projects in line with due process guidelines.
Furthermore, this became possible as a result of timely production of the price list data book and compliance with its content by some
government agencies accordingly. Though, training on use of procurement planning template has been conducted in the state by State
Partnership for Accountability, Responsiveness and Capability (SPARC), however most MDAs are yet to put it to use adequately there
by reducing the compliance level of the procurement exercise. It should be noted that this document is expected to be part of budget
process requirement as well as procurement process respectively.
CONTRACTS AWARDED.
A total of N73.970 billion was budgeted for capital expenditure, both for on-going projects and new ones, representing 47% of the
total budget of N157.540 billion in the year 2019. Currently, contracts worth N13.231 billion only were awarded, representing 17.88%
of the capital provision. Though it is the practice of the current administration to implement most of the capital intensive projects by
means of “Open Tender” process, in 2019 only 71.88% were awarded through that process against the bench mark of 80% as per best
practice. It is worth noting that the projects awarded by the open tender process, last year (2018), stand at 93% only. While projects
awarded above threshold of N100million, by open competitive process, represent 58.69% only this year against 97% in the previous
year 2018. This might not be unconnected with the additional works awarded on some mega ongoing projects in the state, to satisfy
the aspirations of the communities in which the projects were sited. Namely it includes some roads projects in Hadejia township,
Babura township, Jigawar Danalli, and two hospitals projects in Hadejia and Birnin Kudu .
Total Contracts Awarded in 2019;
-Contracts Awarded by Open Competitive Bidding = N9,510,649,219.70 (71.88%)
-Contracts Awarded by Selective Bidding Process = N2,942,639,760.80 (22.24%)
- Contracts Awarded by Nominative Bidding Process = N 778,255,567.58 (5.88%)
Total = N13,231,544,548.08 (100%)
Contracts Awarded Above Threshold of N100million in 2019;
-Contracts Awarded above Threshold (N100 m), by Open Competition = N3,451,823,705.52 (58.69%)
-Contracts Awarded above Threshold (N100m), by other method =N 2,429,581,418.90 (41.31%)
Total =N 5,881,405,124.42 (100%).
POST CONTRACT EVALUATION.
Projects with contract value of N123,576,349,031.75 billion were being reported under this section. Most of the projects, at various
stages of completion, were being carried forward from the previous years. It is anticipated that about half of all the on-going projects
will be completed by the end of this year if there is stability in capital receipt from the federation account. The only exception that will
be carried to preceding years include, among others, Eastern bye pass road i.e western bye pass road i.e. Maigatari-Galadi-Diginsa-
Birniwa road, and others awarded at the end of previous year 2019. While Jigawa University project ,B/kudu new general Hospital,
Guri, Garki, Gantsa General hospitals, and Hadejia and Kazaure Specialist Hospitals, will also spill to next year accordingly.
• COMPLETED PROJECTS; This section contains projects that are 100% completed worth N38,803,305,043.60 only, 30.89% of the
N123.576 billion projects being reported on. It is worth noting that the percentage achieved is low despite the declaration by
government that most of the projects will be completed within the year. This is mainly due to paucity of funds from the
federation account.
• ON-GOING PROJECTS; The value of on-going projects being reported under this section amounts to N84,773,043,988.15 only
(69.11%) of the total under consideration. The figure is staggering and could not be provided for in next year’s budget (2020)
to actualize the completion of all on-going projects but rather a percentage of it.
OBSERVATIONS.
It has been observed that there is a lot of improvement by government agencies, to date, in packaging their capital projects for vetting
by the Bureau as highlighted in the pre -contract evaluation process whereby 7.3% was saved from vetting exercise within the period.
This is largely due to adoption of the revised rates being produced regularly by the Bureau in conjunction with the MDAs of
government. Despite this positive trend, absence of a comprehensive procurement plan by MDA’S, reduces the chances of optimum
participation by contractors in all bidding process in terms of adequate preparation and also reduce the attainment of full compliance
with the existing procurement law.
It was observed that only 72% of contracts awarded by government, this year, followed open competitive tender processes which
need to improve in line with best practice, above 80%, to be abreast with donor agencies requirement.
The law provision which requires that for all contracts the value of which is above N10.00 million a performance bank guarantee must
be presented is yet to take effect despite several reminders forwarded by the Bureau to government.
The use of Standard Bidding Document (SBD) by agencies during tender process is yet to be complied with in full despite extensive
training conducted by SPARC and emphasis made by the Bureau, to achieve compliance with best practice as provided by law.
Many contracts awarded from the previous year are yet to make meaningful progress due to nonpayment of contractual obligations
by government, caused by reduction in capital receipt from the federation account.
CONCLUSION/RECOMMENDATION.
Government agencies are advice to prepare a comprehensive procurement plan for all the proposed capital projects, approved within
the budget, and forward it to the budget department and the Bureau so as to achieve full compliance of the procurement law which
will allow every contractor to get prepared for bidding in good time.
The use of relevant tender processes, as prescribed by law, should always be considered for the award of contracts for works, goods
and services, except in special circumstances where the government direct otherwise, such that the maximum benefit of the system
could be harnessed.
The law provision which mandate the presentation of performance bank guarantee by prospective contractors should be activated in
the council award letter so as to scare unserious contractors in participating in government business.
All contracts bidding process should be carried out as per Standard Bidding Documented (SBD) presented to each MDA in line with
best practice as per law compliance.
Government should set up a Committee to advice on how to generate more revenue and reduce the dependency of capital receipt
from the federation account so as to meet the state contractual obligations.
……………………………………… …………………………………… Alh. Garba Halilu Sara Ado Hussaini MON
Special Adviser. Director General.
PROJECTS BEING EXECUTED BY MINISTRIES/AGENCIESJANUARY-DECEMBER, 2019
ENVIRONMENT FINANCE JS POLY TECHNIC INFORMATION COMMERCE ECONOMIC EMPOWERMENT
68,210,461,519.59
4,587,643,851.15
20,100,894,380.81
15,008,150,836.44
9,653,818,005.82
966,545,560.70 2,926,246,754.80
WORKS &TRANSPORT
WATERRESOURCES
DCDA EDUCATION HEALTH LAND & HOUSING CABINET OFFICE
PROJECTS BEING EXECUTED BY MINISTRIES/AGENCIESJANUARY-DECEMBER, 2019
WORKS & TRANSPORT WATER RESOURCES DCDA EDUCATION
HEALTH LAND & HOUSING CABINET OFFICE
204,170,069.67
60,705,065.40
91,672,274.72
209,433,611.20 194,446,776.65
PROJECTS BEING EXECUTED BY MINISTRIES/AGENCIESJANUARY-DECEMBER, 2019
JSCI &LS Ringim Deputy Governor's Office BU Poly Hadejia Govt. House INFORMATIC Kazaure
Completed, 38,803,305,043.60 ,
31%
On-going, 84,773,043,988.15 ,
69%
ANALYSIS OF PROJECTS PERFORMANCE JANUARY-DECEMBER, 2019
Completed On-going
S/N PROJECT IN PROCESS QUOTED SUM DPPM RECOMMENDED SAVING/ REMARKS
(N) COST (N) INCREASE
MINISTRY OF HEALTH
1
Proposed Procurement of Beds, Mattresses and Classroom Arm Chairs and Grass Cutting Machines
for School 0f Nursing Hadejia. (Revised Scope) 5,328,125.00 5,145,656.25 182,468.75 Min of Health
2 Proposed Renovation works At JIMSO Regional Store Hadejia (Flooding) 11,178,829.58 10,890,818.56 288,011.02 Min of Health
3
Proposed Construction of 1No Basic Health Clinic at Wurno (2019 Second Quarter Constituency
project) 17,484,899.82 17,484,899.82 - Min of Health
4
Proposed Construction of Basic Health Center/ Health Clinic in 5No. Constituency Across the State
(2019 Constituency project) (bulangu, Kiyawa, Garki, Taura & Dutse) 47,584,342.74 48,333,671.42 (749,328.68) Min of Health
5
Renovation of Male Students Hostel Block D & E old ICT and Security Wire at School of Health
Techonology Jahun 33,809,059.99 34,156,207.55 (347,147.56) Min of Health
6
Proposed Renov. of Female Student Hostel Storey and New Hostel Block at School of Health
Technology Jahun. 5,921,107.22 5,921,078.84 28.38 Min of Health
7
Proposed Constr. Of basic Health Center/Health Clinic in 3No constituency Across the State
(Constituency Project 2019) 80,958,192.71 84,318,515.87 (3,360,323.16) Min of Health
8 Propose constr. Of L-1 Maternity Ward 14,971,614.98 17,484,899.82 (2,513,284.84) Min of Health
9 Proposed Constr. Of New General Hospital Birnin Kudu (Variation/Additional work) 594,212,839.12 595,712,672.97 (1,499,833.85) Min of Health
10 Upgrading of Miga Primary Health Care to General Hospital 3,757,000.00 3,625,000.00 132,000.00 Min of Health
11 Proposed Ceiling Work, Standing A/C gate and Road Way at Dutse Central Store (JIMSO) 21,580,549.65 19,373,025.33 2,207,524.32 Min of Health
12 Proposed Upgrading of yankwashi Primary Health care (PHC) to General Hospital 118,100,478.89 118,379,880.39 (279,401.50) Min of Health
13 Proposed Procurement of 500No. Mattresses to School of Health Technology Jahun 7,500,000.00 7,500,000.00 - Min of Health
14 Proposed Upgrading of maigatari Health Care (PHC) to General Hospital 107,151,264.74 107,252,313.59 (101,048.85) Min of Health
15
Proposed renovation of Dr. Abbas house and Replacement of ridge Cap at GOPD Ward Maternity,
Pediatri, Postnatal wards at Dutse General Hospital 2,685,536.00 2,578,536.00 107,000.00 Min of Health
16
Proposed Construction of 40 bed ward 183 meters length liking walk ways (59No. Total module
area) at Jahun General Hospital 47,666,736.17 48,440,728.62 (773,992.45) Min of Health
17
Proposed Construction of BHC, 20Beds Ward and Health Post at Gwiwa, Fagam and Taura
Constituencies 18,278,424.15 19,425,717.13 (1,147,292.98) Min of Health
18 Proposed renovation/Improvement of Sule Tankarkar PHC 96,052,991.24 91,032,017.12 5,020,974.12 Min of Health
19 Proposed upgrading of Kiyawa primary Health Centre to Cottage Hospital 97,753,082.68 96,214,947.77 1,538,134.91 Min of Health
20 Proposed Renovation / Improvement of kanya Babba PHC (Phase II) 99,872,710.10 94,483,309.50 5,389,400.60 Min of Health
21 Proposed Construction of Student Hostel at College of Nursing and Midwifery Birnin Kudu 83,799,369.99 90,089,863.85 (6,290,493.86) Min of Health
22 Proposed Renovation Construction Maintenance Works at Dutse General Hospital ( laboratory Unit) 8,343,703.18 8,919,296.62 (575,593.44) Min of Health
23 Proposed Upgrading of roni primary health centre to Cottage Hospital (Phase II) 96,202,050.59 96,202,050.59 - Min of Health
24 Proposed Construction and renovation works at Bulangu Cottage Hospital 96,939,259.09 98,846,893.09 (1,907,634.00) Min of Health
25
Upgrading of malam Madori Primary Health Center to General Hospital ( Proposed Additional Work)
Extension of 407.12 Meters Wall Fencing (117 Modules) 22,164,224.24 23,257,704.02 (1,093,479.78) Min of Health
26 Proposed Renovation of GOPD, Isolation ward, Maternity & OPD at Gumel General Hospital 31,908,670.69 33,521,749.27 (1,613,078.58) Min of Health
27 Proposed Improvement of power supply at Ringim General hospital 7,043,482.66 6,883,022.25 160,460.41 Min of Health
28 Proposed Erecting of retaining wall for Erosion control at Rashid Shekoni Specialist Hospital Dutse 4,993,733.00 5,775,774.09 (782,041.09) Min of Health
29
Renewal of contract for the provision of cleaning services (Admin Block and ITS Surroundings ) at
Rasheed Shekoni Specialist Hospital Dutse 2,446,742.00 2,446,742.00 - Min of Health
30 Proposed Laterite sand filling and Embankment at Hadin Newly Constructed Basic Health Clinic 3,812,852.00 3,521,326.57 291,525.43 Min of Health
31 Proposed Supply and Installation of Medical Equipment to the Newly Constructed 25No Basic Health Clinic Across the State95,423,350.00 95,423,350.00 - Min of Health
32 Proposed Construction of New General Hospital Birnin Kudu (additional works) 594,212,839.12 595,712,672.97 (1,499,833.85) Min of Health
33
Proposed procurement of Beds, Mattresses and Dining Table & Chairs for Dr. Paul at Babura Gen
Hospital 1,072,000.00 1,072,000.00 - Min of Health
34
Proposed Procurement of Beds, Mattresses Chairs and Grass Cutting Machine for School of Nursing
hadejia 6,070,000.00 5,300,000.00 770,000.00 Min of Health
35 Proposed External Works at Garki General Hospital (additional works) 5,377,542.45 5,377,542.45 - Min of Health
36 Proposed external works at Gantsa General Hospital (additional works) 8,947,304.07 8,947,304.07 - Min of Health
37 Proposed repairs and Services of Radiology Equipment at rasheed Shakoni Specialist Hospital Dutse 5,887,500.00 5,887,500.00 - Min of Health
38 Proposed Repairs Renovation of GOPD Ward and Maternity at Dutse General Hospital 7,807,170.11 8,525,676.79 (718,506.68) Min of Health
-
MINISTRY OF WATER RESOURCES -
39
Proposed Upgrading and conversion of water schemes at Balago and Bakar Kuka in Dutse Zone and
Ringim Zone. 11,951,862.93 11,951,862.93 - STOWA
40 Propsed Rehabilitation of (88No.) Hand Pumps Borehole in 24No. Community of Babura LGA 3,534,825.00 3,364,729.00 170,096.00 RUWASA
41
Proposed Improvement of Reticution and Conversion of 3No. Motorized Boreholes to Solar at Kafin
Gana in Birnin kudu LGA 20,515,697.42 20,714,129.42 (198,432.00) STOWA
42
Proposed Rewinding of Flight Pump, High Lift Pump and procurement of Gen. set at Ringim, Kazaure,
Dutse and Hadejia Town 9,503,000.00 9,313,000.00 190,000.00 JS Water Board
43 Conversion of Motorized Pumps to Soler Power Schemes at Babura Town, Babura LGA 1,492,710.00 1,452,710.00 40,000.00 JS Water Board
44 Conversion of Motorized Pumps to Soler Power Schemes at Gagarawa LGA 49,928,704.96 49,136,641.39 792,063.57 JS Water Board
45
Conversion of Motorised Pumps to Solar powered schemes at Babura town, Babura LGA (Additional
works) 2,551,000.00 2,438,500.00 112,500.00 JS Water Board
46 Proposeed Pipeline Reticulations (28.6KM) in Kazaure Town 537,951,025.00 530,771,054.78 7,179,970.22 Water Board
47 Proposed Construction of 50No. Handpump Across the state 36,897,000.00 36,897,000.00 - STOWA
48
Proposed Construction of New Solar Power Schemes, Conversion and Improvement of motorized
Water Schemes in Dutse and its Environment (Revised) 254,346,007.74 249,431,025.31 4,914,982.43 Water Board
49
Proposed Upgrading and Conversion of motorised water supply schemes to Solar Powered at Zareku
Town 11,920,254.81 10,905,152.57 1,015,102.24 Stowa
50 Proposed Rehabilitation of (3No) water Suppkly Schemes in Gumel Zone 4,644,281.25 4,644,281.25 - Stowa
51 Proposed Rehabilitation of (18no) water supply Schemes Across the Across the State 10,678,390.00 9,748,615.00 929,775.00 Stowa
52 Proposed Constr. Of 1No. Solar Powered water supply scheme at Kandi in Dutse LGA Zone 6,023,325.00 6,023,325.00 - Stowa
53
Proposed Upgrading and Conversion of 7No Motorised Water Supply Schemes to Solar Powered at
Gumel and Birnin Kudu Zone 75,786,760.67 72,494,502.73 3,292,257.94 Stowa
54
Proposed Uprading and Conversion of Motorised Water supply schemes to Solar powered at
Sugungun in Ringim Zone 14,002,788.55 12,582,658.31 1,420,130.24 Stowa
55
Proposed Uprading and Conversion of Motorised Water supply schemes to Solar powered at Kadira
Small Town Guri LGA 25,794,513.36 22,443,547.29 3,350,966.07 Stowa
56
Proposed for the Constr of New Solar Schemes at New Market Zai/Galadimawa and Improvement at
Main And Shuwarin Sabuwa Pump Station, Dutse 25,151,888.00 25,151,888.00 - Min of Water Resources
57
Constr.of New Solar Schemes at New Market, Zai/Galadimawa and improvement at Main and
Shuwarin sabuwa Pump Station Dutse 4,967,123.70 4,295,024.00 672,099.70 Min of Water Resources
58
Proposed Uprading and Conversion of Motorised Water supply schemes to Solar powered at Dutse
Zone 14,986,568.05 14,561,003.05 425,565.00 Stowa
59 Proposed Constr. Of 1No Solar Powered water supply Scheme at Daki Daka in Garki LGA Ringim Zone 6,023,325.00 6,023,325.00 - Stowa
60 Proposed Constr. Of 1No Solar Powered water supply Scheme at Kunyafa in Babura LGA Ringim Zone 6,023,325.00 6,023,325.00 - Stowa
61 Proposed Constr. Of 1No Solar Powered water supply Scheme at Damfa in Babura LGA Ringim Zone 6,023,325.00 6,023,325.00 - Stowa
62 Proposed Refurbishing of Some Vehicles 19,061,760.38 14,639,493.75 4,422,266.63 Min of Water Resources
63 Proposed Procurement of 12No Tyres tube and liners for the 2No Water Tanks in the Ministry 2,579,720.00 1,564,000.00 1,015,720.00 Min of Water Resources
64 Proposed Constr. Of (504No) of Facilities in Gagarawa LGA 10,899,200.00 10,322,000.00 577,200.00 Ruwasa
65 Proposed Constr. Of (1,641No) of Facilities in Kiyawa LGA (ODF) 36,734,100.00 33,462,843.75 3,271,256.25 Ruwasa
66 Proposed Constr. Of (956No) of Facilities in Auyo LGA (ODF) 21,595,600.00 19,527,375.00 2,068,225.00 Ruwasa
67
Proposed constr of New Solar Schemes at New Market, Zai/Galadima and Improvement at main and
Shuwaring Sabuwa Pump Station, Dutse (Additional work) 2,515,888.00 2,515,888.00 - Min of Water Resources
68
Upgrading & Conversion of (22No) water supply schemes to solar powered system Across the state
(Lot-1) 8,981,385.00 8,923,322.50 58,062.50 Stowa
69
Proposed Upgrading & Conversion of Zaburan small town motorised water supply scheme to solar
powered 15,343,500.00 15,343,500.00 - Stowa
70 Proposed upgrading of existing water supply schemes at Gwiwa local Government Area 37,601,902.52 37,833,112.97 (231,210.45) JS Water Board
71 Upgrading and Conversion of 30No Small towns water supply scheme to solar Across the State 6,387,376.80 6,075,265.25 312,111.55 Stowa
72
Proposed rehabilitation of water supply schemes at Babura, Kiri Kasamma & Hadejia in Ringim &
Hadejia Zone 7,621,950.00 7,543,200.00 78,750.00 Stowa
73 Proposed rehabilitation of water supply schemes at Auyo, kiri kasamma and Hadejia in Hadejia 7,818,300.00 7,660,800.00 157,500.00 Stowa
74 Proposed construction of (38No) Hand Pump Borehole Across the State 28,041,729.00 28,041,729.00 - Ruwasa
75 Proposed rehabilitation of water supply schemes in Ringim, Kazaure and Dutse Zone 6,555,150.00 6,413,400.00 141,750.00 Stowa
76
Proposed rehabilitation of water supply schemes at Babura and Sule Tankarkar in Ringim and gumel
Zone 7,698,600.00 7,541,100.00 157,500.00 Stowa
77 Proposed Construction of (40No) Hand Pumps Borehole Across the state 29,517,600.00 29,517,600.00 - Ruwasa
78
Proposed rehabilitation of water supply schemes at Hadejia, Malam Madori, Kaugama, Birniwa, Guri
and Auyo in Jahun and hadejia Zone 8,070,300.00 7,660,800.00 409,500.00 Stowa
79
Proposed upgrading and conversion of 2No motorized water supply scheme to solar powered at
gangara in babura LGA Ringim Zone 6,829,987.50 6,829,987.50 - Stowa
80 Construction of new solar powered water supply schemes at Babura tsallake 1,159,351.26 1,109,750.00 49,601.26 JS Water Board
81 Proposed rehabilitation of 2No Borehole at School of nursing Hadejia 1,373,163.75 1,354,145.63 19,018.12 JS Water Board
82
Proposed Conversion of Motorized Water Schemes to Solar Powered Water Schemes and Some
Rehabilitation at College of Education, Gumel 30,197,849.17 29,287,259.96 910,589.21 JS Water Board
83
Proposed Construction of 1No Solar powered water supply scheme at Yannmaulu Tsohuwa in
babura & Ringim Zone 6,023,325.00 6,023,325.00 - Stowa
84
Proposed Upgarding and Conversion of motorised water supply schemes to Solar Powered at Ringim
Zone 19,228,758.15 18,459,647.97 769,110.18 Stowa
85 Proposed Conversion of Motorised pumps to Solar Powered Schemes at Sule Tankarkar LGA 2,771,126.93 2,797,219.43 (26,092.50) JS Water Board
86 Proposed Rehabilitation of (13No) water supply scheme in Ringim, Kazaure and Gumel 14,032,200.00 12,788,475.00 1,243,725.00 Stowa
87 Proposed Rehabilitation of (19No) Water Supply Schemes in Ringim Zone 20,400,450.00 17,361,750.00 3,038,700.00 Stowa
88
Proposed upgarding and Conversion of motorised water supply schemes to Solar Powered
atMaizuwo in Sule Tankarkar Zone 6,829,987.50 6,829,987.50 - Stowa
89 Proposed Rehabilitation of Water supply schemes at Auyo, Kirikasamma and Hadejia in Hadejia zone. 6,555,150.00 6,413,400.00 141,750.00 Stowa
90
Proposed Rehabilitation of 3no Small towns water supply schemes In Birnin Kudu, Ringim and
hadejia 7,951,440.00 8,014,597.50 (63,157.50) Stowa
91 Proposed Rehabilitation of 3no Small towns water supply schemes In Gumel and Jahun Zone 4,215,750.00 4,089,750.00 126,000.00 Stowa
92 Proposed Rehabilitation of 3no small Towns water supply schemes in Ringim and Birnin Kudu Zone 7,001,596.88 7,001,596.88 - Stowa
93
Proposed Conctruction of 1no. Solar powered water Supply scheme at Nafara in Kiyawa LGA Dutse
Zone 6,023,325.00 6,023,325.00 - Stowa
94 Proposed Rehabilitation of 7no. Small towns water supply schemes in Hadejia, Gumel and jahun Zone 4,940,250.00 4,630,500.00 309,750.00 Stowa
95 Proposed Rehabilitation of 2No Small Towns water supply schemes in Dutse Zone 3,370,500.00 3,370,500.00 - Stowa
96 Proposed Rehabilitation of 2No Small Towns water supply schemes in Birnin Kudu Zone 2,908,500.00 2,887,500.00 21,000.00 Stowa
97 Proposed Procument of Generating set for Kazaure and Birnin Kudu Zone 28,615,253.66 28,619,712.07 (4,458.41) JS Water Board
98 Proposed Over Hauling of Generating sets across the state 9,781,910.00 9,171,892.50 610,017.50 JS Water Board
99 Proposed Rehabilitation of 6No Small towns water supply schemes in Hadejia, Gumel and Jahun Zone 5,362,035.00 5,047,035.00 315,000.00 Stowa
100 Rehabilitation of water supply schemes at Gwaram town (Additional Works) 708,660.75 708,660.75 - JS Water Board
101
Proposed Construction of New Solar Schemes ay Yalwawa, Malam Inuwa Dutse Housing Estate
(MIDEH) and & 744 Danmasara 99,856,958.51 98,158,678.54 1,698,279.97 Min of Water Resources
102 Proposed Procurement of Assorted submersible pumps across the state 19,479,796.87 19,479,796.87 - JS Water Board
103 Proposed rehabilitation of 2no Small Towns water supply Schemes in gumel Zone 1,155,000.00 1,018,500.00 136,500.00 Stowa
104
Proposed Construction of 2no New Solar powered water supply scheme at Malarin Gamm in Malam
Madori LGA and Walawa in Birniwa Local Government Area 12,046,650.00 12,046,650.00 - Stowa
105 Proposed Rehabilitation of water supply scheme at Taura Town 10,723,753.67 10,526,670.91 197,082.76 JS Water Board
106
Proposed Constructio of (148No) Laterines and (24,000) Tippy tap Across the Communities of
Gwiwa and Roni Local Government Area 2,990,400.00 2,990,400.00 - Ruwasa
107
Proposed Construction of (22No) Hand Pump Borehole at 22 communities in Sule Tankarkar and
Maigatari Local government Area 16,234,680.00 16,234,680.00 - Ruwasa
108
Proposed Construction of (15No.) hand Pump Borehole at 15 Communities in Sule Tankarkar Local
Government Area 11,069,100.00 11,069,100.00 - Ruwasa
109
Proposed Construction of (12No) Hand pump borehole at 15 Communities in Sule Tankarkar Local
Government Are Gumel Zone 8,855,280.00 8,855,280.00 - Ruwasa
110
Proposed Constructionn of (6No.) Hand Pump Borehole at 6 Communities in Sule Tankarkar and
Kafin and Kafin Hausa Local Government Area 4,427,640.00 4,427,640.00 - Ruwasa
111
Proposed rehabilitation of 5No Small Towns Water supply schemes in Birnin Kudu Dutse, jahun and
Kazaure Zone 6,127,170.00 6,105,109.50 22,060.50 STOWA
112
Proposed Upgrading and Conversion of 1No Motorized Water supply Scheme to Solar Powered at
Jabo in Jahun Zone 23,596,060.01 23,567,109.24 28,950.77 Stowa
113
Proposed Construction of 4No New Solar water powered supply scheme at Danmarke, Wada,
Kayarda and Garin baki in Babura LGA, Ringim Zone 24,093,300.00 24,093,300.00 - Stowa
114 Proposed Procurement of Assorted Submersible pumps Across the State 19,479,796.87 19,479,796.87 - JS Water Board
115 Procurement of assorted sumbersible pumps across the state (Additional works) 882,000.00 882,000.00 - JS Water Board
116
Proposed rehabilitation of 2No Small Town water supply schemes at ruru and Budinga town in dutse
and gwaram LGs 882,000.00 882,000.00 - Stowa
117 Proposed Upgrading and Conversion of Doko water supply scheme in Garki Local Government Area 8,358,328.13 8,004,990.11 353,338.02 Stowa
118
Proposed upgrading and Conversion of 1No Motorized water supply scheme to Solar Powerd at Uku
Da Sisi Sabuwa in Babura LGA, Ringim Zone 7,005,526.45 6,767,532.45 237,994.00 Stowa
119
Proposed rehabilitation of 3no Small towns water supply schemes at Ruru, Budinga and Yabaza in
Dutse and Birnin Kudu Zone 2,100,000.00 2,100,000.00 - Stowa
120
Proposed Rehabilitation of 2No Small town water supply schemes at Yan Damo and malam Baki in
Gumel zone 8,895,181.68 8,482,573.26 412,608.42 Stowa
121 Proposed Rehabilitation of 17No. Small Towns water supply schemes at Hadejia and Jahun Zone 5,161,739.63 5,161,739.63 - Stowa
122 Proposed rehabilitation of 1No Solar water supply schemes at Modoji in Sule Tankarkar 1,557,281.25 1,667,531.25 (110,250.00) Stowa
123 Proposed Construction of (40No) Hand Pump Boreholes Across the state 29,517,600.00 29,517,600.00 - Ruwasa
124 Proposed Rehablitation of (34No) Hand Pump Borehole at Babura LGA 1,953,600.00 1,478,400.00 475,200.00 Ruwasa
125
Improvement of Gwaram Tsohuwa and gwaram Sabuwa Towns Water supply scheme (Additional
works) 34,045,356.30 29,520,524.45 4,524,831.85 JS Water Board
126
Proposed Construction of 1No water Collection, 1No Complete Borehole in Hadejia Town and 1No
Hand pump Borehole at Babura LGA 2,898,139.00 2,813,984.25 84,154.75 Ruwasa
127
Conversion and Upgrading of motorized Borehole to Solar Powered supply (7No.) at kanya Babba
Main pump station, kanya babba water for all station, kanya babba LGA, Danzomo II Pump station,
Kudai Pump station and Waza pump station (Additional works) 3,534,038.03 3,534,038.03 - Stowa
128 Proposed constr of 50no. Hand pump borehole at 50 communities across the state 36,897,000.00 36,897,000.00 - Ruwasa
129 Proposed constr of 1no. Solar powered water supply scheme at Dorai in Garki LGA, Ringim zone 6,023,325.00 6,023,325.00 - Stowa
130 Proposed procurment of 200KVA Gen set as change of purpose in Kazaure Water supply project 12,977,439.30 12,977,439.30 - JS Water Board
-
MINISTRY OF EDUCATION -
131Proposed Procurement of Office Equipment for Permant Senate Building office 14,128,590.00 13,397,475.00
731,115.00 Sule Lamido University
132
Proposed Renovation Works of Classroom Blocks (Each) at 5No Senior Secondary School Across the
State22,404,592.38 22,487,382.75
(82,790.37) Min of Education
133 Proposed Construction of Admin Block and 6-Seater pit Latrine 21,998,145.35 21,998,145.35 - IEB
134 Proposed Construction of 1No Block of Three Classrooms 11,202,005.64 11,202,005.64 - IEB
135 Proposed Construction of 4No Hand Pumps 2,410,000.00 2,410,000.00 - Bamaina Gifted Academy
136 Proposed Construction and Renovation works at Bamaina Academy 5,368,288.27 5,649,771.21 (281,482.94) Bamaina Gifted Academy
137 Proposed Construction of 1No Block of Three Classrooms 15,371,199.96 15,455,343.81 (84,143.85) COI&LS Ringim
138 Proposed Construction of one Block Two Laboratories at GGDSS Roni 28,487,680.00 33,552,607.41 (5,064,927.41) Min of Education
139
Proposed Procurement and Distribution of 3-seater Students Desks and Benches, Principals and Staff
room Furniture for Senior Secondary school across the state 85,299,375.00 85,115,625.00 183,750.00 Min of Education
140 Proposed Procurement of 1No Brand New 350KVA sound proof perkins Generator 22,722,577.50 22,722,577.50 - Sule Lamido University
141 Proposed Renovation Works at Lautai Gumel LGA (GDSS) 57,457,387.79 60,686,506.55 (3,229,118.76) Min of Education
142 Proposed renovation of staff houses and hostels at College of Education Gumel 334,671,516.44 383,489,242.44 (48,817,726.00) Min of Education
143
Proposed Procurement and Distribution of Instructional Materials for nomadic Primary Schools
Across the State 16,408,750.00 16,206,625.00 202,125.00 Nomadic Education
144
Proposed Procurement and Distribution of (750No.) 3 Seater Desks and (4,000No) Sitting Mats for
Nomadic School Across the State 16,750,000.00 14,965,000.00 1,785,000.00 Nomadic Education
145
Proposed fRenovation of Windstorm Damaged Structures (Phase II) at Science Secondary Secondary
School Lautai gumel (additional works) 3,168,882.15 3,168,882.15 - Scinece& Tech Board
146
Proposed Constr. Of Gate House and Wall Fence at Jigawa College of Remidial and Advance Studies
Babura (JICORAS) 103,229,892.40 137,837,089.74 (34,607,197.34) Min of Education
147 Proposed Procurement of Chalk for Baic Schools Across the State 26,228,020.00 26,228,020.00 - Subeb
148
Proposed Procurement of Science Laboratory Equipments for Distribution to 9No senior Secondary
Schools Upgraded to Science Centres of Excellence Core-2 81,068,353.92 81,068,353.92 - Min of Education
149 Proposed Renov of Storm Damaged structures at GSSS Taura, CGSSS Roni and GSTC Hadejia 49,576,548.66 50,071,865.14 (495,316.48) Science & Tech Board
150 Proposed Constr of new Mega School in Dutse 215,689,695.60 225,089,449.84 (9,399,754.24) Min of Education
151
Constr of Female student's Hostel at Sule Lamido University Kafin Hausa (Proposed steel roof
members) 18,028,810.00 18,028,810.00 - Sule Lamido University
152
Proposed Procurement of Office Materials and Renov/Conversion of Political Party Office to Admin
Block and Lecture classrooms at College of Remidial and Advance studies Babura 11,313,450.39 14,046,670.75 (2,733,220.36) Min of Education
153
Proposed Registration with JAMB ABU Zaria and take-up grant of College of Remidial and Advance
studies Babura 2,350,000.00 2,350,000.00 - Min of Education
154 Proposed Procurement of 1no Isuzu Septic tank 23,820,000.00 22,878,228.51 941,771.49 Sule Lamido University
155
Proposed procurement and Distribution of School uniforms, Sandals and Bags for Nomadic schools
across the state 29,980,000.00 27,880,000.00 2,100,000.00 Nomadic Education
156 Proposed constr of JICORAS at Babura (phase I) (revised Scope) 440,761,393.03 450,720,554.97 (9,959,161.94) Min of Education
157 Proposed departmental works and purchases for NBTE Requirements 5,310,020.00 5,310,020.00 - Bilyamu Usman Polytech
158 Proposed conduct of 2019 Musabaqar Ilimi 14,336,100.00 13,591,350.00 744,750.00 Islamic Education Bureau
159
Proposed Procurement of Laboratory Equipments and Reagent , Food nutrition/catering craft
practice and Animal Husbandary Items for waec and Neco Accreditation of Science secondary
schools 9,384,546.00 8,493,252.00 891,294.00 Science & Technical Board
160 Proposed Procurement of examination materials 1,420,000.00 1,420,000.00 - Bilyamu Usman Polytech
161 Proposed Construction of Library Phase II at New Campus, Binyaminu Usman Polytechnic Hadejia 44,992,746.03 42,334,242.16 2,658,503.87
Binyaminu Usman
Polytechnic
162 Proposed Procurement of Academic Gowns 2,615,000.00 2,270,000.00 345,000.00
Binyaminu Usman
Polytechnic
163
Proposed Procurement of Instructional / Enterpreneuship Materials, Jamb Scratch Cards and 5-Day
Training Workshop for FTDS Facilitator for the 3rd years scale up of FTDS 14,904,900.00 10,044,900.90 4,859,999.10 Ministry of Education
164
Proposed Construction of (1No) Hostel Block for Jigawa State Institute of Information and
Technology Kazaure 49,994,477.82 47,989,101.98 2,005,375.84 JSIIT Kazaure
165
Proposed Construction of 6 Classroom Blocks at the Proposed Boys and girls Junior Science
Secondary School Gumel (1st Quarter Constituency Project 2019) 30,520,842.46 29,997,708.62 523,133.84 SUBEB
166 Proposed Procurement of (250No) Student's Mattresses 1,925,000.00 1,925,000.00 -
Binyaminu Usman
Polytechnic
167 Procurement and Installation of a Brand New 100KVA Soundproof Perkins Generator (1100 Series) 5,334,960.00 5,334,960.00 -
Binyaminu Usman
Polytechnic
168
Proposed External Electrical power supply 33KV Dedicated feeder from Hadjia (Lot-1 of the phase II
Project 46,289,431.23 51,049,397.56 (4,759,966.33) Sule Lamido University
169
Proposed External Electrical power supply 33KV Dedicated feeder from Hadjia (Lot-2 of the phase II
Project 39,137,223.31 42,158,908.89 (3,021,685.58) Sule Lamido University
170
Proposed procurement of science laboratory equipments for senior secondary schools across the
state 33,630,751.71 33,630,751.71 - Ministry of Education
171
Proposed procurement and distributions of (34,304No.) Science text books and teachers guide for
senior secondary across the state 49,949,800.00 49,949,800.00 - Ministry of Education
172 Proposed food order for 500 students per week in Boarding Schools 442,280.00 438,260.00 4,020.00 Ministry of Education
173
Proposed external electrical power supply 33KV Dedicated feeder from Hadejia ( Lot-3 of the Phase I
Projects) 29,676,826.34 29,676,826.34 - Sule Lamido University
174
Proposed NTBE Accreditation resources inspection and affiliation for 12No Programs in the
Polytechnic 9,225,000.00 8,976,000.00 249,000.00
Jigawa State
Polytechnic
175 Proposed procurement of 1no Toyota Avensis (2018 Model) 28,934,000.00 28,934,000.00 - Sule Lamido University
176 Proposed procurement of 1No Toyota Corolla (2018 Model) 18,800,000.00 17,718,750.00 1,081,250.00 Sule Lamido University
177 Proposed Procurement of workshop materials and Consumables items in 4No Technical Colleges. 8,188,250.00 8,188,250.00 - Scinece& Tech Board
178 Proposed payment of facilitators for Litracy programme 30,630,000.00 30,630,000.00 - Mass Education
179 Proposed Staff Training and Development 3,638,622.00 3,638,622.00 - Bilyaminu Usman Poly
180 Proposed Renovation of 1No 3 Bedroom House 3,032,747.22 2,991,989.63 40,757.59 Bilyaminu Usman Poly
181 Proposed Procurement of (2No) Vehicles 27,950,000.00 27,950,000.00 -
State Polytechnic,
Dutse
182
Proposed Production of (4,266 sets) of 3-seater students furniture from scraps at various schools
across the state 20,000,031.84 20,000,031.84 - Min of Education
183
Proposed rennovation of classrooms and Admin Block at Sugungu Primary School Garki LGA and
GGJSS Gagarayaga Gwaram LGA 9,774,322.12 9,774,322.12 - Min of Education
184 Proposed External Electrical Power supply for permanent senate building Lot-2 27,171,584.37 24,691,772.46 2,479,811.91 Sule Lamido University
185
Proposed External Electrical Power supply 33KV Dedicated feeder from Hadejia Lot-III of the Phase Ii
Project 49,183,473.65 47,439,656.28 1,743,817.37 Sule Lamido University
186
Proposed renovation of classrooms blocks, Hostel, workshop, Library GJSS Aujara and re-
Construction of wall fence at Model Boarding Primary School Kila 42,117,899.50 45,009,447.40 (2,891,547.90) Min of Education
187 Proposed accreditation of 11No Pragrammes in the Polytechnic 3,110,900.00 3,110,900.00 - Bilyamin Usaini Poly
188
Proposed printing of Examination papers with answer sheets by Jigawa State Printing press for
senior secondary schools across the state 8,110,096.50 8,247,851.33 (137,754.83) Min of Education
189
Proposed printing of 2019 basic education certificate examination (BECE) Question papers with
answer sheets 16,724,512.00 15,260,680.05 1,463,831.95 Min of Education
190 Proposed repairs of 1No Monitoring Vehicle (Toyota Hilux) 2,228,500.00 2,005,200.00 223,300.00 Nomadic Education
191
Proposed External electrical power supply for shopping complex,Clinic, Junior Staff Quarters and
VC's Lodge ( Lot-1) 46,004,312.20 42,497,088.81 3,507,223.39 Sule Lamido University
192 Proposed perimeter demarcation and Survey/Topographical and detail survey of the polytechnic 5,262,136.00 5,022,948.00 239,188.00 Bilyaminu Usman Poly
193 Proposed Renovation works at Jigawa State Research Institute Kazaure 9,775,628.66 9,713,139.27 62,489.39 Res earch Ins titute Kazaure
194Prposed procurement of new tractor (QLN-654, 65HP) and implement, Kazaure Research Institute 6,925,000.00 6,925,000.00
- Res earch Ins titute Kazaure
195Proposed production of 10HA each of millet & seame, 3HA groundnut and 3HA cowpea, Kazaure
Research Institute
4,763,300.00 4,778,300.00 (15,000.00) Res earch Ins titute Kazaure
196Proposed training on Artificial Insemination techniques and Insemination of (300) cows at Kazaure
Research Institute
5,923,015.00 5,923,015.00 - Research Institute Kazaure
197 proposed procurement of vehicles at JICORAS Babura 47,250,000.00 47,250,000.00 - Min of Edcucation
198 Price of LAPTOP Lenovo BSO-10 Comuputer (variety) 807,500.00 807,500.00 - Scholarship Board
199 Proposed constr of Block of 3-classrooms at Ringim College of Islamic & legal Study. 15,371,199.96 15,455,343.81 (84,143.85) COI&LS Ringim
200 Proposed procurement of Examination material;s Ringim College of Islamic & legal Study. 4,600,000.00 4,600,000.00 - COI&LS Ringim
201
Proposed supply and Installation of (52no) street light inntergrated Ringim College of Islamic & legal
Study. 32,215,050.00 32,215,050.00 - COI&LS Ringim
202 Proposed procurement of instructional materials for (81no) post literacy centre across the state. 3,239,670.00 3,191,790.00 47,880.00 Agency for Mass Educ.
203
Action plan for Establishment of 81 Remidial and 36 Continuing Education centre facilitators monthly
allowance and Airtime programme 56,554,350.00 56,074,342.50 480,007.50 Agency for Mass Educ.
204 Proposed renovation of science Laboratories and ITC Room Each at 9No. Senior Secondary Schools 15,421,179.00 24,143,284.04 (8,722,105.04) Min of Education
205
Proposed renovation of storm damages at GDASS Dantanoma, SAIS Hadejia, GDASS Zainab Kazaure,
GDASS Dabi, GDASS Birnin kudu, GDASS Gwaram and GDASS Danzomo 57,822,208.00 53,582,692.89 4,239,515.11 IEB
206 Proposed renovation of classrooms Blocks at MBPS Kudai in Dutse 4,450,715.27 4,971,711.32 (520,996.05) SUBEB
207 Proposed renovation of classrooms blocks at Kabewa and Samangara in Gwaram and Sule Tankarkar 7,213,644.52 5,824,507.21 1,389,137.31 SUBEB
208 Proposed re-construction of wall fence at GGUSS Garki and GGUSS Malam Madori 11,334,094.59 9,039,035.07 2,295,059.52 Min of Education
209 Proposed procurement of Double Decker Beds and Mattrasses 4,000,000.00 2,950,000.00 1,050,000.00 Bamaina Gifted Academy
210 Proposed procurement of Students uniform and Protective clothings 2,284,000.00 1,898,000.00 386,000.00 Bamaina Gifted Academy
211 Proposed Renovation of storm damaged structures at GSTC Karkarna SSS Kafin Hausa and GSSS Jahun 24,498,727.08 35,803,002.26 (11,304,275.18) SUBEB
212
Proposed procurement of (30,000 sets) School Uniforms for Senior Secondary Schools Girls Across
the State 78,000,000.00 78,000,000.00 - Min of Education
213
Proposed Construction of Admin Block, Students Hostel, Laboratory, 6 Seater Pit Latrine and 1 block
3 classroom 11,169,666.72 11,202,005.64 (32,338.92) Min of Education
214
Proposed Procurement of Instructional materials for women funtional literacy and payment of
programme facilitators 5,859,500.00 5,667,800.00 191,700.00 Mass Education
215 Proposed Procurement of Instructional Materials 2,682,564.00 2,430,324.00 252,240.00 Bamaina Gifted Academy
216 Proposed procurement of sporting equipments 474,300.00 474,300.00 - Bamaina Gifted Academy
217
Proposed Procurement of ICT Materials and Accessories for Distribution to 9No Senior Secondary
Schools upgraded to Science Center of Excellence 65,958,600.00 68,982,322.50 (3,023,722.50) Min of Education
218 Proposed Construction of A Prototype 480 Capacity Students Hostel 379,307,287.02 390,002,952.26 (10,695,665.24) Sule Lamido University
219 Proposed Conduct of 2019 Qur'anic Recitation competition 25,970,040.00 25,218,600.00 751,440.00 IEB
220 Proposed Renovation of Storm Damaged at 7No Schools Across the State 21,608,545.23 23,498,908.59 (1,890,363.36) Min of Education
221 Propose 2019 Capital Project 3,000,000.00 3,000,000.00 - JSIIT Kazaure
222 Proposed procurement of 1No Isuzu Septic Tank 23,820,000.00 18,425,462.35 5,394,537.65 Sule Lamido Uni
223
Proposed Procurement of science laboratory equipments for distribution to 9No Senior Secondary
Schools Upgraded to science centres of Excellence core-2 81,068,353.92 81,068,353.92 - Min of Education
224
Proposed Procurement of science laboratory equipments for distribution to senior secondary
schools across the state 29,491,628.31 29,491,628.31 - Min of Education
225 Proposed 2019 capital projects at JSCOE Gumel 20,004,592.06 19,702,558.36 302,033.70 Min of Education
226 Proposed renovation of Ringim divisional libarary 7,483,822.92 7,409,717.73 74,105.19 Library Board
227 Proposed Procurement of 150no. 3 Seater Student Desk 3,000,000.00 3,000,000.00 - Dutse Model School
228
Proposed Procurement of ICT Materials and Accessories for Distribution to 9No Senior Secondary
Schools upgraded to Science Centres of Excellence 65,958,600.00 68,982,322.50 (3,023,722.50) Min of Education
229 Proposed procument of Instructional materials for post Literacy centres across the state. 4,950,490.00 4,130,500.00 819,990.00
Agency for Mass
Education
MINISTRY OF WORKS -
230 Proposed Repairs of NYSC orientation Camp Generator 3,174,906.57 2,388,615.19 786,291.38 Ministry of Works
231 Construction of Jigawar Ali Township Road (2.10KM) by Messrs mothercat Nig LTD (additional) 224,213,450.06 203,412,195.00 20,801,255.06 Ministry of Works
232 Proposed Construction of 3KM Shoulder Along Gujungu - Gumel Road 18,301,342.50 20,172,442.50 (1,871,100.00) JIRMA
233 Proposed Stand Alone Solar Street Lighting Project at Babaldu Town in Birnin Kudu LGA 58,046,625.00 55,786,500.00 2,260,125.00 Ministry of Works
234
Proposed Relocation of 1No Hand Pump Borehole Affected By Road construction at Hadejia Road10
Gandun Sarki 629,790.00 629,790.00 - Ministry of Works
235 Proposed Procurement of ICT Equipment and Training of Staff 5,000,000.00 4,558,000.00 442,000.00 Urban Dev Board
236 Proposed Maintenance of Birnin Kudu-Kiyawa road 14,644,282.17 14,644,282.17 - JIRMA
237 Constr of Babura township roads (10.28km) (Lot-8) (additional work) Consultancy 7,745,437.31 7,745,437.31 - Ministry of Works
238
Stand Alone Solar Street Lighting Project at Garun-Gudiya (80) of Babura LGA and Garin - Gambo of
Gumel LGA 81,328,800.00 81,328,800.00 - Ministry of Works
239 Proposed Stand Alone Solar Street Lighting project at Marke town in Kaugama LGA (150no.) 81,328,850.00 82,797,750.00 (1,468,900.00) Ministry of Works
240 Proposed Supply and Installation of 800KVA Generator (Sound Proof) 46,446,759.80 46,263,912.00 182,847.80 REB
241 Proposed relocation of 12No Hand Pump Boreholes Affected by the township Roads Project in Gumel 8,855,280.00 8,855,280.00 - Ministry of Works
242 Relocation of water pipelines affected by the road Construction at Kaugama 5,429,983.61 5,387,600.40 42,383.21 Ministry of Works
243 Relocation of water supply facilities affected by the Road Construction at Kanya Babba Town 7,104,877.50 7,105,533.75 (656.25) Ministry of Works
244 Relocation of water supply facilities affected by the Road Construction at Jigawar Dan Ali Town 6,304,725.00 6,213,506.25 91,218.75 Ministry of Works
245 Relocation of Water supply facilities affected by the Road Construction at Chai-Chai Tsohuwa Town 2,391,637.50 2,391,637.50 - Ministry of Works
246
Proposed Relocation of Urban Town Street Light Installation affected by the Project (Construction of
Gumel Township Roads) 27,797,663.25 27,077,730.75 719,932.50 Ministry of Works
247
Proposed Relocation of Urban Town Street Light Installation affected by the Project ( Construction of
Zandam Nagogo Township Roads) 5,804,400.00 5,589,150.00 215,250.00 Ministry of Works
248
Proposed Relocation of urban town solar street light installation affected by the project (
Construction of jigawar dan Ali Township Roads) 1,139,250.00 1,055,000.00 84,250.00 Ministry of Works
249
Proposed Relocation of urban town solar street light installation affected by the project (
Construction of Kanya Babba township Roads) 1,438,500.00 1,370,000.00 68,500.00 Ministry of Works
250
Proposed Relocation of Urban Town street light installation affected by the project ( Construction of
Kiyawa Township Roads) 7,029,750.00 7,080,255.00 (50,505.00) Ministry of Works
251
Proposed Relocation of Urban Town street light installation affected by the project ( Construction of
MIga Township Roads) 8,583,750.00 8,715,262.50 (131,512.50) Ministry of Works
252 Proposed Construction of Hadejia Eastern Bye-Pass (Phase III) Water Damaged Section 58,964,002.00 58,607,439.60 356,562.40 JIRMA
253
Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of
744 Yalwawa Township Roads) 6,997,000.00 6,082,000.00 915,000.00 Ministry of Works
254
Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of
KanyaTownship Roads) 2,610,300.00 2,277,345.00 332,955.00 Ministry of Works
255
Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of
Jigawar dan AliTownship Roads) 1,754,010.00 1,740,375.00 13,635.00 Ministry of Works
256
Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of
Zandam Na GoGo Township Roads) 7,529,500.00 6,402,000.00 1,127,500.00 Ministry of Works
257 Relocation of Water supply facilities affected by the road Construction at Kazaure town 28,358,982.50 27,716,172.00 642,810.50 Ministry of Works
258
Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project (Construction of
Chai-Chai TsohuwaTownship Roads) 3,411,000.00 3,049,000.00 362,000.00 Ministry of Works
259 Construction of Hadejia Township Roads Project (additional works) 214,624,764.24 214,624,764.24 - Ministry of Works
260 Stand Alone Solar Street Lighting Project at Emir Palace Road, Dutse 17,419,500.00 17,391,937.50 27,562.50 Ministry of Works
261
Proposed Relocation of Electrical Installations (KEDCO) Affected by Road Project Construction of
kiyawa Township Roads 6,923,000.00 6,075,000.00 848,000.00 Ministry of Works
262
Proposed Relocation of Electrical Installations (KEDCO) Affected by Road Project Construction of
Miga Township Roads 3,237,500.00 2,712,500.00 525,000.00 Ministry of Works
263
Proposed Relocation of Electrical Installations (KEDCO) Affected by Road Project Construction of
Gumel Township Roads 9,162,195.00 9,235,595.00 (73,400.00) Ministry of Works
264 Proposed protection work at Premises of GGSS Garu Dutse 9,180,953.44 9,180,953.44 - JIRMA
265
Proposed Relocation of Electrical Installations (Kedco) Affected by Roads Projects (Construction of
Gudunci-Aguyaka Road) 2,380,350.00 2,113,125.00 267,225.00 Ministry of Works
266 Proposed Repairs of Machines 4,682,000.00 4,682,000.00 - JIRMA
267
Proposed Improving access between sugungu and kashin ganji Communities in Garki Local
Government Area 8,387,424.15 8,387,424.15 - JIRMA
268
Proposed maintenance Rehabilitation of Some Failed Section along Kazaure Roni Asphaltic Concreter
surfaced Road 72,239,291.69 70,061,248.78 2,178,042.91 JIRMA
269
Proposed Maintenance Pathole Patching of Some Failed Spot Along Unguwar Mani-Koreyal-Rorou
Surfaced dressed Road 31,775,900.21 29,959,647.20 1,816,253.01 JIRMA
270
Proposed stand alone solar street lighting project at GGASS birniwa (42No) GGASS Kaugama (40No)
SOD Hadejia (30No) and JSS Guri (30No.) 77,002,800.00 77,002,800.00 - Ministry of Works
271 Proposed Maintenance of Maiganjara bridge along Jahun-Gujungu Road 6,586,482.00 6,588,449.70 (1,967.70) Ministry of Works
272 Proposed potholes patching along yarkirya-Dandi-Gada and Dandi-Achi lafiya roads 18,323,348.40 14,132,132.55 4,191,215.85 Ministry of Works
273
Proposed recllamation of eroded road embenkment and construction of Drainage at Yalo Borrow-Pit-
Gujungu-Hadejia road 8,962,589.58 8,962,589.58 - Ministry of Works
274 Proposed rehabilitation of Gumel to Gagarawa ITC Line 2,963,468.39 2,963,468.39 - Ministry of Works
275 Construction of Gambara-Waza-Baranda with spur road to Yalwa (16.8km) (additional works) 993,666,672.04 909,144,691.47 84,521,980.57 Ministry of Works
276 Proposed relocation of Electrical installations of Kaugama township road (KEDCO) 2,673,085.00 2,318,400.00 354,685.00 Ministry of Works
277 Construction of Babura Township Roads (10k.28) Lot-8 (additional works) 587,368,516.84 510,841,607.48 76,526,909.36 Ministry of Works
278 Proposed relocation of electrical installations (KEDCO) affected by Roads Project (Phase III) (Gumel) 1,895,500.00 1,672,625.00 222,875.00 Ministry of Works
279 Proposed relocation of water supply facilities affected by the township roads project in Hadejia town 451,750.00 451,750.00 - Ministry of Works
280
Proposed relocation of 3no hand pump borehole affected by the township roads project in Kiyawa
town 1,889,370.00 1,196,370.00 693,000.00 Ministry of Works
281 Proposed rehabilitation of Gwaram - Basirka ITC Line 141,110,326.37 141,110,326.37 - REB
282
Proposed relocation of 3No Hand pump borehole affected by the township roads project in kanya
babba town 1,889,370.00 1,889,370.00 - Ministry of Works
283
Proposed relocation of 1No Hand pump borehole affected by the township roads project in Jigawar
Dan Ali town 629,790.00 629,790.00 - Ministry of Works
284
Proposed relocation of 1No Hand pump borehole affected by the township roads project in Chai-Chai
Tsohuwa town 629,790.00 629,790.00 - Ministry of Works
285
Proposed relocation of 1No Hand pump borehole affected by the township roads project in 744
yalwawa 629,790.00 629,790.00 - Ministry of Works
286
Proposed relocation of 5no water collection points affected by the township roads project in Gumel
Town 6,264,993.00 6,264,993.00 - Ministry of Works
287
Proposed relocation of 2No hand pump borehole affected by the township roads construction at
Zandam nagogo town 1,259,580.00 1,259,580.00 - Ministry of Works
288 Proposed relocationn of 2No hand pumps borehole affected by the township roads peoject in miga 1,259,580.00 1,259,580.00 - Ministry of Works
289
Proposed relocationn of 12No hand pumps borehole affected by the township roads peoject in Gumel
town 2,468,970.00 2,468,970.00 - Ministry of Works
290
Proposed stand alone street lighting project at GGASS Danzomo (42No.) GGSS Sule Tankarkar (35No)
MBPS Gumel (30No.) and GGSSS Taura (32No.) 75,380,550.00 75,380,550.00 - Ministry of Works
291 Proposed maintenance of Auyo Town retaining wall-River embankment 49,718,008.41 49,718,008.41 -
Road Maintenance
Agency
292 Proposedf reclamation and construction of a Retaining wall at Kwalam Borrow Pit Along Ringim-Hadejia Road 11,564,426.37 11,564,426.37 -
Road Maintenance
Agency
293
Proposed stand alone solar street lighting project at GGASS Danzomo (42No) GGSS Sule Tankarkar
(35no.) MBPS Gumel (30No) and GGSSS Taura (32No) 60,780,300.00 60,780,300.00 - Ministry of Works
294
Proposed Stand Alone Street lighting project at GUSS Gwaram (45No.) GGASS Babura (38No.) and
GGSS Roni 60,780,300.00 60,780,300.00 - Ministry of Works
295 Proposed Relocation of water supply facilities affected by the Road Construction at Miga Town 9,044,352.75 8,653,117.55 391,235.20 Ministry of Works
296 Proposed Relocation of water supply facilities affected by the Road construction at Gumel Town 35,701,295.56 31,383,059.49 4,318,236.07 Ministry of Works
297
Proposed Relocation of water supply facilities affected by the Road construction at Zandam Nagogo
Town 5,984,754.23 4,674,262.16 1,310,492.07 Ministry of Works
298 Constr. Of Taura-Garki Road 400,000.00 400,000.00 - Ministry of Works
299
Proposed Relocation of water supply facilities affected by Kanya-Duzau-Goron Maje Feeder Road
Project 2,787,750.00 2,751,000.00 36,750.00 Ministry of Works
300 Proposed Repairs of Kwanar yalleman-Kaugama-Kwanar madana Road 54,230,613.60 35,906,265.73 18,324,347.87 Jirma
301 Proposed Rehabilitation of Takur Jaudi Feeder Road (2019 Flood) 9,442,085.63 6,451,728.00 2,990,357.63 Jirma
302 Proposed Construction of Reinforced block line and culvert at Sha'iskawa Takur Site 24,938,937.50 24,680,291.36 258,646.14 Jirma
303 Proposed Maintenance of Ayama Junction-Ayama Feeder Road 63,005,166.47 62,244,441.17 760,725.30 Jirma
304 Proposed Construction of Shagari Quarters-Burtilan-Three Star junction Road (2.0km) 300,097,007.94 294,311,528.94 5,785,479.00 Ministry of Works
305 Proposed Construction of Additional 3 Cell Box culvert along Hantsu Miga Dangyatum Road 43,364,604.94 43,364,604.94 - Jirma
306 Proposed reclamation and Construction of Drainage at IGGI town in Birnin Kudu LGA 25,790,264.43 25,790,264.43 - Jirma
307
Proposed Maintenance and Rehabilitation of Multi Cell Box Culvert Along Karnaya-Chai Chai- Ringim
road at Sintilmawa 7,196,462.98 7,196,462.98 - Jirma
308
Proposed Maintenance and Reconstruction of Section Damaged by 2018 Flood Along Kwalam-Gilima-
Kiri Road 197,729,725.73 199,672,807.59 (1,943,081.86) Jirma
309 Proposed Stand alone solar street lighting project at elleman town in Kaugama LGA 17,708,414.54 17,474,625.00 233,789.54 Ministry of Works
310
Construction of Hadejia Township Roads Projects at Azare Road-Adua Mosque-New Motor Park
(Road 11) (additional works) 324,613,275.50 312,270,011.94 12,343,263.56 Ministry of Works
311 Construction of Hadejia Township Roads projects Additional Works (485M Road Network (road 10) 109,988,511.26 97,645,247.70 12,343,263.56 Ministry of Works
312 Proposed Maintenance of Generating Set at Dutse International Airport 928,500.00 863,500.00 65,000.00
Dutse International
Airport
313 Proposed Relocation of Water supply facilities affected by the township roads poject in 744 Dutse 12,634,075.00 11,704,856.86 929,218.14 Ministry of Works
314 Proposed Relocation of Water supply facilities affected by the township roads project in kiyawa 12,739,349.00 12,043,954.33 695,394.67 Ministry of Works
315 Proposed Maintenance of Birnin Kudu-Kiyawa Road 14,644,282.17 14,644,282.17 - JIRMA
316 Proposed Maintenance of failed sections along Kazaure-Roni Asphaltic Concrete Road 113,701,901.25 98,528,040.30 15,173,860.95 JIRMA
317 Proposed Maintenance of Failed Spots and Potholes on Hadejia Gujungu Road 4,328,047.50 4,328,047.50 - JIRMA
318 Proposed Maintenance of Fail section of unguwar mani-Korayel Surface Dressiing Road 18,315,665.65 18,315,665.65 - JIRMA
319
Proposed Reclamation of Reinforced concrete block drainage (2000M) Access Slabs and Culverts at
Gunka Along Sukullifi-Gunka Road Jahun 48,289,386.35 47,762,386.35 527,000.00 JIRMA
320 Proposed Repairs of NYSC Orientation Camp Generator, Dutse 3,174,906.57 1,977,397.29 1,197,509.28 Ministry of Works
321
Proposed Relocation of Electrical Installations (KEDCO) Affected by Roads Project ( Construction of
Birnin Kudu-KwanGwara-Zaziga Feeder Road 681,000.00 586,000.00 95,000.00 Ministry of Works
322 Proposed Repairs of 8No. Fire Fighting trucks 6,729,000.00 6,172,250.00 556,750.00 Fire Services
323 Proposed Drilling of 150MM PVC Borehole with reticulation of 90MM PVC of 2KM Distance 7,100,423.40 6,734,650.13 365,773.27 Fire Services
324 Proposed Procurement of Working Materials 3,485,920.00 3,300,500.00 185,420.00 Fire Services
325 Proposed maintenance works of very high frequency OMINI Directional Radio (VOR) Shelter 1,059,148.50 1,059,148.50 -
Dutse International
Airport
326
Proposed reclamation of eroded road embankment, re-dressing of shoulder stone pitching and
construction of Chutes and Kerbs at Jangargari-babaldu-Sagu road 3,483,186.00 3,359,706.00 123,480.00 JIRMA
Directorate of Economic Empowerment -
327 Proposed Upgrading of Babura Skills Acquisition and Training Center 8,596,891.21 11,263,571.41 (2,666,680.20) Directorate of Econ. Emp.
328 Proposed Procurement of (10No) Boxer Bajja Motorcycle 2,900,000.00 2,900,000.00 - Directorate of Econ. Emp.
329
Proposed Procurement of Consumable training materials of Mafita (DFID) Programme in 13No. Skills
Acquisition Center 21,014,450.00 20,378,263.50 636,186.50 Directorate of Econ. Emp.
330 Proposed Procurement of (14no.) 6 Water Pump and Solar Pump 6,640,000.00 6,640,000.00 - Directorate of Econ. Emp.
-
MINISTRY OF LAND & HOUSING -
331 Proposed procurement of furniture and at deputy governor's residence 44,790,300.00 34,868,641.50 9,921,658.50 Min of Land
332 Proposed renovation of deputy Governo'rs Residence 18,182,740.96 17,581,763.41 600,977.55 Min of Land
333
Construction of 30No Boys Quarters External Electrification & Water supply to Individual
Legislators Quarters Dutse (generator house) 4,967,578.00 4,967,578.00 - Min of Land
-
CABINET OFFICE -
334
Proposed Constr/Renovation of juma'at Prayer Mosques (First Quarter 2019 Constituency
Projects) 49,605,136.99 51,473,514.64 (1,868,377.65) Cabinet Office
335
Proposed Constr. Of Juma'at Prayer Mosque at Oliya Sararin Rakuma Quarters Hadejia Constituency
First Quarter 2019 Constituency Projects) 5,804,760.56 5,940,460.38 (135,699.82) Cabinet Office
336 Proposed Constr. Of Juma'at Prayer Mosques (4no.) at Birniwa, Gagarawa and Buji) 41,773,970.56 42,013,131.72 (239,161.16) Cabinet Office
337
Partial works (constr of main mosque lower level roof slab) at K/Hausa mosque 2018 2nd qtr
Constituemcy project (change of scope) 4,772,560.00 4,047,154.00 725,406.00 Religious Affairs
338 -
339
Proposed Construction, Completion and Renoovation of juma'at and Daily Prayer Mosque for First
Quarter 2019 Constituency Project (13no) 69,483,551.42 68,104,946.96 1,378,604.46 Cabinet Office
340
Proposed Construction / Completion and Renovation of Friday Prayer mosque / Five Daily Prayer
Mosque for First Quarter 2019 Constituency Projects (6no) at hadejia and K/kasamma 24,550,734.62 24,081,611.13 469,123.49 Cabinet Office
341 Proposed Construction of juma'at Prayer Mosques for first Quarter 2019 Constituency Projects at Maigatari 15,688,829.50 15,486,967.52 201,861.98 Cabinet Office
342
Proposed Renovation/Upgrading of District Head House and Renovation of Juma'at Prayer Mosque
for First Quarter 2019 Constituency Projects at Babura and Yankwashi 33,666,807.87 29,625,345.03 4,041,462.84 Cabinet Office
343 Proposed repairs of (7No) Commands Operational Vehicles NSCD Corps Jigawa State Command 7,133,500.00 6,515,000.00 618,500.00 Special Services
344
Proposed Construction of Borehole with Dwarf tank for Additional Works of Juma'at Prayer Mosque
(JIBWIS) at Garin Gabas in Malam Madori Constituency for third Quarter 2018 Remaining Works 700,000.00 700,000.00 - Cabinet Office
345 Proposed Construction of Female mosque at Federal university Dutse 41,271,654.26 57,137,963.58 (15,866,309.32) Cabinet Office
346 Proposed Renovation of Jigawa State hisbah command Office at Dutse 6,010,416.76 6,001,925.14 8,491.62 Special Services
347
Proposed Additional works for the supply of carpet, generator Sound System and Mumbari at
Nasarawa Jibwis Moque Prayer in Gumel 681,712.50 671,215.50 10,497.00 Cabinet Office
348
Proposed Additional works for the construction of imam zoffice on the construction of wall fencing
and interlocking at Nasarawa Jibwis Mosque in Gumel 678,005.00 669,186.00 8,819.00 Cabinet Office
-
MINISTRY OF INFORMATION -
349 Proposed Procurement of Electrical Equipments 23,699,999.00 18,049,500.00 5,650,499.00 JTB Dutse
350
Proposed Construction of 1No Town Hall at Tsohuwar Gwaram LGA for First Quarter 2019
Constituency Projects 36,295,490.03 36,182,900.04 112,589.99
Ministry of
Information
351 Proposed Renovation works at Hadejia Township Stadium 5,291,054.31 5,589,226.28 (298,171.97) Sport Council
352 Proposed renovation of storm damage and Construction works at Dutse township Stadium 9,863,713.33 9,863,713.33 - Sport Council
353 Proposed Rehabilitation of Guyed wire and others at Andaza Mast 44,707,950.00 40,770,450.00 3,937,500.00 JTV
GOVERNMENT HOUSE -
354 Supply of 2no. fairly used 2018 and 2016 Totota Landcruiser Jeeps 42,000,000.00 44,100,000.00 (2,100,000.00) Government House
355 Supply of 2no. fairly used 2015 and 2016 Totota Landcruiser Jeep 36,000,000.00 37,800,000.00 (1,800,000.00) Government House
356 Proposed Price of 2 No. GS 8 and 13no GS 4 vehicles or its equivelent 169,533,611.20 169,533,611.20 - Government House
-
MINISTRY FOR LOCAL GOVERNMENT -
357 Proposed Rehabilitation of 33KVA line from Sara-Gantsa Buji LGA 45,522,200.75 46,445,750.14 (923,549.39) Min for LG
MINERAL RESOURCES -
358 Proposed conduct of Baseline Survey of Artisanal Miners/Acivities in 14 LGAS in the State 4,884,000.00 4,546,800.00 337,200.00 Mineral Resources Dev
-
OFFICE OF THE DEPUTY GOVERNOR -
359
Proposed price of items to be distributed to N-Tech Trainees Under the N-Power Skills development
Across the State 23,500.00 23,500.00 -
Special Intervention
Program
360
Proposed Price of Items to be Distributed to N-Tech Trainees Under the N-Power Skills Development
Across the State 6,322,000.00 8,154,562.50 (1,832,562.50) Deputy Govt Office
361
Proposed Procurement of Furniture and Equipments at Deputy Governors Residence (additional
works) 9,897,500.00 8,750,175.00 1,147,325.00 Deputy Govt Office
-
MINISTRY OF ENVIRONMENT -
362 Proposed Construction of drainages across the state (2019 first qtr. Constituency) 57,845,636.72 57,340,033.63 505,603.09 Ministry of Environment
363 Proposed for the Repairs of Gully Emptier (911 lorry truck) 1,250,000.00 1,095,000.00 155,000.00
Ministry of
Environment
364
Proposed Procurement of items to be distributed to the community organizations as Government
support for the clearance of typha and other Aquatic weeds along the Riverine Areas (Revised Scope) 15,173,813.00 15,173,813.00 -
Ministry of
Environment
365 Proposed Construction of Drainage at Tsirma Town in Kiyawa Local government Area 44,880,680.25 44,880,680.25 -
Ministry of
Environment
366 Proposed Construction of Drainage at Fankan Fayau Pond in Taura LGA 66,232,100.77 65,917,579.77 314,521.00
Ministry of
Environment
367 Proposed constr of Drainages across the state 47,326,454.83 47,218,265.69 108,189.14
Ministry of
Environment
368
Proposed production of 2.5 million assorted seedling (supply of materials)
14,568,775.00 17,927,142.19 (3,358,367.19)
Ministry of
Environment
369
Proposed Procurement of items to be Distributed to the community organizations as government
support for the clearance of typha and other Aquatic weeds alone the reverine areas 6,338,925.00 6,338,925.00 -
Ministry of
Environment
370 Proposed construction of drainage and repairs of wall fencing of inuwa Dutse housing Estate 43,935,657.85 43,533,566.82 402,091.03
Ministry of
Environment
-
MINISTRY OF JUSTICE -
371Proposed Construction of (8No)New Sharia court at Gumel Kazaure Garki Chamo Baturiya Yalo
Hadejia and Garun Gudunya
178,348,359.52 189,105,452.24 (10,757,092.72) Sharia Court of Appeal
372 Proprosed procurement of Equipment/Furnitures 2,000,000.00 1,980,000.00 20,000.00 Judicial Serv Commison
373 Proposed repairs of 3no Vehicles 412,000.00 412,000.00 - Justice Sector
374
Proposed Renovation of Chief Magistrate Official Residence Kafin Hausa, Construction of Magistrate
Court at Ringim and Construction of 4 Bedroom Duplex at Highbrough Dutse 52,748,575.72 51,713,779.52 1,034,796.20 Ministry of Justice
375 Proposed construction of conference hall at Judicial Services Commission Secretariat Complex 17,403,651.04 17,963,823.37 (560,172.33) Judicial Serv Commison
376 Proposed Procurement of Vehicles 62,000,000.00 62,000,000.00 - State Judiciary
377 Proposed Renovation of 12No. Sharia court 81,685,950.61 78,783,875.00 2,902,075.61 State Judiciary
378 Proposed Procurement of 2no Utility Vehicle 29,385,300.00 29,385,300.00 -
Judicial Service
Commission
379 Proposed procurement and supply of law books to Ministry of Justice 18,984,750.00 18,984,750.00 - Ministry of Justice
380
Proposed Construction of Perimter wall fence at Proposed site for the Construction of Prison along
Limawa-warwade road-Dutse LGA 205,020,293.66 191,928,817.44 13,091,476.22 Ministry of Justice
381
Proposed Procurement of Computer, Library Management System Software and Network
configuration to Ministry of Justice 2,965,000.00 2,798,250.00 166,750.00 Ministry of Justice
-
MINISTRY OF AGRICULTURE -
382 Proposed Construction of Abattoir at Doko in garki Local government Area 9,935,055.96 10,219,945.22 (284,889.26) Min of Agriculture
383 Proposed renovation of JASCO Stores (12no.) 7,288,801.52 6,241,390.57 1,047,410.95 Min of Agriculture
384
Proposed Procurement of Animal vaccines, vaccination inputs and accessories for 2019/2020 annual
vaccination exercise 7,396,000.00 7,217,000.00 179,000.00 Min of Agriculture
385 Proposed Renovation of JARDA Headquater, Dutse 9,966,385.80 9,822,858.22 143,527.58 JARDA
386
Proposed Renovation and Alteration of office Block to Accommodate Staff of Islamic Development
Bank (IDB) Project at JARDA Premises 17,527,798.25 17,320,419.03 207,379.22 JARDA
387 Proposed Renovation of States Zonal Veterinary Clinics (3no.) at Ringim, Jahun and Gumel 15,740,457.72 20,256,382.14 (4,515,924.42) Min of Agriculture
-
HEAD OF SERVICE -
388 Proposed Supply and Installation of 10KVA Inveter Solar Power 6,271,986.00 5,278,696.50 993,289.50
Contributory Pension
Scheme
389 Proposed procurement of brand new ATIZ Book Drive pro book scanner machine 6,800,000.00 6,800,000.00 - Library Board
390 Proposed supply and Instalation of 10KVA inveter solar power 6,271,956.00 5,278,696.50 993,259.50
Contributory Pension
Scheme
391 Proposed Procurement of books 9,200,000.00 9,104,800.00 95,200.00 State Libry
MINISTRY OF COMMERCE -
392 Proposed Procurement of tourism Promotional Equipment and Printing of Tourist Guide handBook 990,000.00 990,000.00 - Min of Commerce
393 Proposed Procurement of e-Registration facilities for business premises and Cooperative Societies 1,774,122.00 1,597,176.00 176,946.00 Min of Commerce
394 Proposed Procurement of ICT Equipment & Accessories 2,740,000.00 2,795,000.00 (55,000.00) Min of Commerces
395 Proposed Renovation of 8No Structures at export Processing Zone Maigatari 13,016,137.90 12,738,100.79 278,037.11 Min of Commerce
396
Proposed Construction of 2no Parking Shades at Babura Motorpark and Achaba in Babura
Constituency for First Quarter 2019 Constituency Projects 2,104,005.85 2,097,097.03 6,908.82 Ministry of Commerce
-
MINISTRY OF FINANCE AND ECONOMIC PLANNING -
397 Proposed procurement of ICT Equipments for Tax Payeers Registration office 1,339,000.00 1,185,000.00 154,000.00
Board of internal
Revenue
398 Proposed construction of Hisbah commandant General Residence at Dutse 8,602,278.14 8,646,067.31 (43,789.17) Min of Finance
399 Proposed price of some office equipments 2,282,500.00 2,205,500.00 77,000.00 Min of Finance
400 Proposed Minor Renovation at Kazaure Zonal Office for the Proposed Driving Lincence centre 580,000.00 566,278.55 13,721.45 Board of Int Rev
MINISTRY OF WOMEN AFFAIRS -
401
Proposed Supply & Installation of (10No) Integrated Stand Alone Solar at Dankwambo in Maigatari
LGA 4,668,004.84 4,378,500.00 289,504.84 Alternative Energy Fund
402 Proposed procurment of office equipments and furniture 2,448,000.00 2,369,000.00 79,000.00 Min of Women Affairs
403 Proposed procurement of office equipments and furnitures 2,448,000.00 2,369,000.00 79,000.00 Min of Women Affairs
404 Proposed repairs of 3No Vehicles 1,202,100.00 1,009,600.00 192,500.00 Min of Women Affairs
CIVIL SERVICE COMMISSION -
405
Proposed renovation of office block and extension of existing conference hall at Jigawa State Civil
Services Commission Office 8,782,384.13 7,980,091.30 802,292.83
Civil Service
Commission
-
TOTAL 14,727,910,392.66 14,520,849,570.67 207,060,821.99
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
works
1 31/01/2019
Construction for the construction of health post at Tashena Village in Malam Madori Local
Government Area. FGPC/2/2019/VOL.I/7 DALARI CONSTRUCTION 7,543,976.80 Min of Health 8 Weeks
2 31/01/2019
Renovation works (2019 Phase I) Constittuency Project at Haya PHC and Gamji Health post in
Fagam Constituency, Gwaram Local Government Area. FGPC/1/2019/VOL.I/7 GIDAN ADEDE GENERAL 12,468,995.04 Min of Health 8 Weeks
3 19/3/2019
Construction of 1No. Block of 4No. House of 2No. Bedroom Semi-Detach (Lot-3) at Birniwa
Locl Government Area FGPC/15/2019/VOL.I/7 MWT Real Estate & General 10,424,245.65 Min of Land 14 Weeks
4 6/3/2019
Construction of 1No Block of health Post at Askandu Village in Kaugama Local Government
Area FGPC/7/2019/VOL.I/6 Jawad Global Construction 7,543,976.80 Min of Health 12 Weeks
5 19/3/2019 Construction of New Special Hospital at Hadejia Phase I (Additional Works) FGPC/131/2017/VOL.I/22 Philko Limited 274,639,176.32 Min of Health 2 Month
6 14/1/2019 Construction of Health Post at Waza Viillage in Birnin Kudu Local Government Area FGPC/941/2018/VOL.I/4 Ngaloma Construction 7,543,976.80 Min of Health 12 weeks
7 5/3/2019 Construction of 50No Hand Pumps Boreholes at 50 Communities Across the State FGPC/5/2019/VOL.I/6 Sir Walter & Gen Serv 36,897,000.00 Min of Water Resources 16 weeks
8 20/06/2019 Construction of block line drain and Filling of Low Area in Majia Community of taura LGA JEC/37/2019/VOL.I/6 Ummukhulsum Invest 86,485,008.42 Ministry of Works 6 month
9 31/05/2019
Construction of 2No. New Solar Powered Water supply Schemes at Malarin Gamm in Malam
Madori Local Government Area and Walawa in Birniwa Local government Area Hadejia Zone FGPC/33/2019/VOL.I/6 BSY Industries Nig Ltd 12,046,650.00 Ministry of Water Resources 8 weeks
10 31/05/2019 Rehabilitation of 17no. Small towns water supply schemes at hadejia and jahun Zone FGPC/34/2019/VOL.I/6 BSY Industries Nig Ltd 5,161,739.63 Ministry of Water Resources 8 weeks
11 7/3/2019
Construction of 45No Hand Pumps Boreholes Water Supply to 45No Community at
Babaduro, Gigar, Hazo, Unguwar Duna, Unguwar Naino Fulani, Wada, unguwar Tsamiya,
Tudun Bayal, Janzomo, Kaikajo, Maizuwo, Yanmaulu, Mara, Kuldu A Malle, Matuntu, Gareji,
Fulanin Kutumbi, Gandore, Fulanin Kandi, Shashatu, Cirimbin, Gumuzu,Arkel, Akula
Quarters, Unguwar Sani, Yantuba, Waje Gari, Kandiren Fulani, Unguwar Mayau, Middle East,
Karambanin Na Binni, Rahar Yusuf, Amsharawa Fulani, Gujguru Fulani, Burukun Fulani,
Mudiri Fulani, Luggar Unguwar Turewa, Tirewa, Kurgun, Gagarawa, Sankarawa, Tasawa,
Gangar Fulani, Bodawa G/Gurgu Danniya and Sayawa G/Mal, Ali Mai Rogo in Babura Local
Govt Area FGPC/8/2019/VOL.I/6 Safah & Fresh Ltd. 33,207,300.00 Min of Water Resources 16 weeks
12 19/3/2019
Construction of 1No. Block of 4No. House of 2No. Bedroom Semi-Detach at Kazaure Local
Government Area FGPC/13/2019/VOL.I/7 Al-Sabur Global Links 10,779,821.20 Min of Land 14 Weeks
13 19/3/2019
Construction of 1No. Block of 4No. House of 2No. Bedroom Smi-Detach at Gumel Locl
Government Area FGPC/10/2019/VOL.I/7 Yalwa Oil & Gas Ltd 10,773,337.15 Min of Land 14 Weeks
14 19/3/2019
Construction of 1No. Block of 4No. House of 2No. Bedroom Smi-Detach at Ringim Locl
Government Area FGPC/14/2019/VOL.I/7 Al-Sabur Global Links 10,779,821.20 Min of Land 14 Weeks
15 19/3/2019
Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach at Babura Local
Government Area FGPC/9/2019/VOL.I/7 Yalwa Oil & Gas Ltd 10,773,337.15 Min of Land 14 Weeks
16 19/3/2019
Construction of 1no Block of 4No House of 2No Bedroom Semi-Detach (lot-2) at Birnin Kudu
Local Government Area FGPC/16/2019/VOL.I/7 Babandoki General Enterprises 10,651,650.00 Min of Land 14 Weeks
17 19/3/2019
Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach (Lot-6) at Hadejia
Local government Area FGPC/17/2019/VOL.I/7 Ngaloma Construction 10,719,537.18 Min of Land 14 Weeks
Bal.C/F 558,439,549.34
1
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRY COMP. PERIOD
BAL. B/F 558,439,549.34
18 19/3/2019
Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach (Lot-9) at Malam
Madori Local government Area FGPC/18//2019/VOL.I/7 Ngaloma Construction 10,719,854.25 Min of Land 14 Weeks
19 19/3/2019
Construction of 1No Block of 4No House of 2No Bedroom Semi-Detach (Lot-4) at Dutse Local
government Area FGPC/11/2019/VOL.I/7 Loyalty Properties Ltd 10,582,286.69 Min of Land 14 Weeks
20 16/4/2019
Construction of 1no Solar Powered water supply scheme at Nafara in Kiyawa LGA, Dutse
Zone FGPC/26/4/2019/VOL.I/6 Sims Global Resources 6,023,325.00 Ministry of Water Res 8 weeks
21 16/4/2019
Construction of 4No. Solar Powered Water supply scheme at Danmarke, Wada,Kayarda and
Garin Baki in Babura LGA Ringim Zone FGPC/25/2019/VOL.I/6 Sims Global Resources 24,093,300.00 Ministry of Water Res 12 Weeks
22 16/4/2019 Construction of 1No. Solar Powered Water Supply Scheme at Dora in Garki LGA Ringim Zone FGPC/27/2019/VOL.I/6 Sims Global Resources 6,023,325.00 Ministry of Water Res 8 Weeks
23 31/5/2019
Rehabilitation of 2No Small Towns water supply schemes at Yandamo and Malam Baki in
Gumel Zone FGPC/35/2019/VOL.I/8 Forte Technical Services Ltd 8,482,573.26 Ministry of Water Res 8 weeks
24 8/5/2019
Construction of 6No Hand Pump Boreholes water supply scheme at Yandamo Kulle 2,
umarni, Modoji Babba, Fulanin Riggade, Gidan Hardo Musa ( Fulanin Asayaya) in Sule
Tankarkar Local Government Area and Tamburawa in Kafin Hausa LGA FGPC/30/2019/VOL.I/6 K-Manu Gen Construction 4,427,640.00 Ministry of Water Res 12 weeks
25 8/5/2019
Construction of 12No Hand Pump Boreholes water supply schemes at Sule Fulanin Yandamo
( Gidan Mallam) Fulanin Kwalawa( Gidan Kato dan Goma), Fulanin dan Kiri ( Gidan Dan Bako)
Garin Goto, Fulanin Kukule Gabas ( Gidan Isah Kato) Fulanin Malam Kadiri ( Gidan Sale),
Fulanin Dantuwo ( Gidan Ingire), Dan Adama Gari, Fulanin Dan Adama ( Gidan Abdullahi),
Dankira, Sabon Garin Dankirya and Fulanin dan Kumbo ( Gidan Hardo Kan Doki) in Sule
Tankarkar Local Government Area Gumel Zone. FGPC/29/2019/VOL.I/6 Al-Juraj Synergy Concept 8,855,280.00 Ministry of Water Res 12 weeks
26 28/06/2019
Construction of (1No.) Block of Twenty (20) Rooms Students Hostel at Jigawa State Intitute
of Information Technology kazaure JEC/40/2019/VOL.I/7 Babandoki General Enter 47,989,101.98 Ministry of Education 16Weeks
27 21/06/2019 Renovation of Structures at Government Science Secondary School Lautai Gumel ( Phase II) JEC/39/2019/VOL.I/6 Gerawa Gobal Engr Ltd 98,014,279.51 Ministry of Education 6 month
28 8/5/2019
Construction of 15No. Hand Pumps Boreholes water supply scheme at Sinti, Garin Goshi,
Fulanin Masama ( Hardo Tamabya) Dantuwo Gari, Dantuwo Tsangaya, Tashar Bala
S/Tankarkar, Balarabe Mai Gari, Fulanin Jalko( Gidan Rabiu) Hardo Dan Kawo ( Fulanin Kuka
Maidire), Sabon Garin Dan Yarda, Fulanin Dan Banki ( Gidan Sha'aibu Jikan Hajja), Fulanin
Tiriki ( Hardo Ilu), Fulanin Charko(Gidan Dabbi) and Ma'azu Gidan Salisu Tifa in Sule
Tankarkar Local Government Area, Gumel Zone FGPC/28/2019/VOL.I/6 Al-Kawakeb Global Concept 11,069,100.00 Ministry of Water Res 12 weeks
29 13/6/2019
Printing of 2019 Basic Education certificate examination (BECE) question papers with answer
sheets for JSS Across the State JEC/52/2019/VOL.I/7 Clear Impressions Ltd 15,260,680.05 Ministry of Education 8 weeks
30 10/7/2019 Rehabilitation of ITC line from Kwanar Gawo to Hago in Kafin Hausa Local Government Area JEC/44/2019/VOL.I/5 Tasiu Muhammad Invest Ltd 8,333,050.69 Ministry of Works 8 weeks
Bal.C/F 818,313,345.77
2
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRY COMP. PERIOD
BAL. B/F 818,313,345.77
31 8/5/2019
Construction of 22No Hand Pump Boreholes water supply schemes at Yandamo gari A,
Yandamo Gari B, Garin Yasai, Hardo Jauro, Kargo, Fulanin Lula, Madoji Tsalle, Fulanin
Barnawa Fulanin Bayan Eka STK, Fulanin Santarbi, Dangoho, Fulanin Mai Rago ( Yamma)
Buntusu Fulani, Fulanin Hardo Musa S.Tankarkar Fulanin Kurguna, Fulanin Kaina unguwar
Yamma ( Danzomo) in Sule Tankarkar LGA and Kwanar Tsuru, Garin Kwalandi, Garin Malam,
Gabasawar Kwalandi and Fulanin Shabarawa ( Gidan Ibrahim Bidu) in Maigatari LGA FGPC/31/2019/VOL.I/6 Forte Technical Services Ltd 16,234,680.00 Ministry of Water Res 12 weeks
32 15/07/2019
Re-Construction of the damaged sections of Abunabo-Kadira-Guri Road (Phase-III of Eastern
Bye Pass) JEC/45/2019/VOL.I/6 CGC Nig Ltd 50,000,000.00 Ministry of Works 10 weeks
33 6/9/2019 Renovation works at Deputy Governor's Official Residence, Dutse DGO/PRJ/003/V.I/17 Daniya Atiku Associate Ltd. 17,129,210.40 Cabinet Office 12 weeks
34 1/7/2019 Contract for the supply & Installation of Medical Equipment to Ringim General Hospital JEC/42/2019/VOL.I/7 Dagarai Integrated Srv 82,153,507.50 Min of Health 8 weeks
35 30/07/2019
Rehabilitation of Karshi-Gagarawar Karshi ITC Line and Extension of Farin Gida TDN in
Ringim Local Government Area, Rehabilitation of Yandutse-Malamawar Yandutse ITC in
Ringim LGA JEC/46/2019/VOL.I/6 Almajeed Constr Ltd 11,391,654.86 Min of Works 10 weeks
36 10/7/2019 Re-construction of fallen wall fence at GGUSS Garki and GUSS M/Madori JEC/54/2019/VOL.I/6 Pullad Global Consult 9,039,035.07 Ministry of Education 8 weeks
37 9/8/2019
Constr of (38No) Hand Pumps at Makadi'B', Gangara waje, jiji'B' Unguwar Sama, Gidan Hardo
Gawo, Gidan Beti dan Maigari, bodawa C, Unguwar Tsamiya B, GJASS Baura, GGADSS
Babuura, Tsadura, Babura Arewa B, Kaute B, in babura LGA, Dutse Capital School in Dutse,
unguwar Lawan in Jahun, tunubu town in Jahun, kuka in /S/Tankarkar, Gidan Danta Fulani,
Kanawa Aume, dan Amale Fulani, Gage Yamma, Jelawa Damu, Kauyen Fulani HP in babura
LGA, Shamuri HP in S/Tankarkar, Tinubu, Hayin Tara Yamma in Jahun, Burukum Fulani, Gidan
Makeri, Minu, Unguwar Magaji, Batali, Malamawa, Bikawa Batali, Muni A, Gidan Dawa and
Dan Makeri G/Nagawo in babura LGA JEC/53/2019/VOL.I/6 Bulangu Dril l ing 28,041,729.00 Min of Water Resources 14 weeks
38 15/8/2019
Renovation of Storm damages at 7no. Schools across the state : GGASS S/Tankarkar, GUSS
maigatari, GDSS Shagari Qtrs. Hadejia, GSS Aujara, GDSS Buji, GGDSS Birnin Kudu and Dutse
Model Int School. JEC/55/2019/VOL.I/9 AGM & Sons Nig 23,498,908.59 Mininstry of Education 8 weeks
39 16/8/2019
Renovation of storm damages at GDASS Dantanoma in Gumel LGA, School of Arabic and
Islamic Studies (SAIS) Hadejia, GDASS Zainab Kazaure, GDASS Dabi in Ringim, GDASS
Gwaram and GGASS Danzomo in Gagarawa LGA JEC/56/2019/VOL.I/10 Pullad Global Consult 53,582,692.89 Ministry of Education 16 weeks
40 6/8/2019
Upgrading and Conversion of 1No. Motorixzed water supply scheme to solar powered at
Maizuwo in Sule tankarkar LGA FGPC/50/2019/VOL.I/6 Sims Global Resources 6,829,987.50 Min of Water Resources 4 weeks
41 6/8/2019
Upgrading and Coversion of 1No. Motorized water supply scheme to solar powered to
Gangara in Babura LGA FGPC/51/2019/VOL.I/6 Sims Global Resources 6,829,987.50 Min of Water Resources 4 weeks
Bal.C/F 1,123,044,739.08
3
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT EXECUTING MINISTRIES COMP. PERIOD
(N)
BAL. B/F 1,123,044,739.08
Works
42 2/10/2019 2019 Rural Electrification Project at Kulawa in Ringim LGA (Lot-9) JEC/71/2019/VOL.1/17 Ngloma Constr Nig Ltd 40,761,674.94 Min of Works 14 weeks
43 2/10/2019 2019 Rural Electrification Project at Kaigamari M/Awaso in K/Hausa LGA (Lot-7) JEC/72/2019/VOL.1/17 Babandoki Gen Entp. 56,156,069.34 Min of Works 14 weeks
44 2/10/2019 2019 Rural Electrification Project atTurbus in Maigatari LGA (Lot-8) JEC/73/2019/VOL.1/17 Babandoki Gen Entp. 51,909,858.00 Min of Works 14 weeks
45 2/10/2019 2019 Rural Electrification Project at Daurawa in Taura LGA (Lot-11) JEC/75/2019/VOL.1/17 Ngloma Constr Nig Ltd 39,499,187.75 Min of Works 14 weeks
46 2/10/2019 2019 Rural Electrification Project at Batali in Babura LGA (Lot-14) JEC/76/2019/VOL.1/17 Ngloma Constr Nig Ltd 87,414,189.61 Min of Works 14 weeks
47 2/10/2019 2019 Rural Electrification Project at Duwigi in Gwiwa LGA (Lot-13) JEC/74/2019/VOL.1/17 Babandoki Gen Entp. 45,418,689.70 Min of Works 14 weeks
48 2/10/2019 2019 Rural Electrification Project at Ringim in Yankwashi LGA (Lot-12) JEC/70/2019/VOL.1/17 Pullad Global Consultant 59,238,524.45 Min of Works 14 weeks
49 2/10/2019 2019 Rural Electrification Project at Batu in Birniwa LGA (Lot-5) JEC/66/2019/VOL.1/17 Masaka Global Concepts 42,505,703.10 Min of Works 14 weeks
50 2/10/2019 2019 Rural Electrification Project at Walawa in Hadejia LGA (Lot-4) JEC/65/2019/VOL.1/17 Ngloma Constr Nig Ltd 52,780,791.53 Min of Works 14 weeks
51 2/10/2019 2019 Rural Electrification Project at Kadira in Guri LGA (Lot-6) JEC/67/2019/VOL.1/17 Xtrax 99 integrated Services 101,346,796.79 Min of Works 14 weeks
52 2/10/2019 Electrification project (Lot-17) at Gangara Qtr. In Gumel LGA. JEC/78/2019/VOL.1/17 Ibrahim Yusuf Integ. 23,258,058.11 Min of Works 14 weeks
53 2/10/2019 Electrification project (Lot-15) at Masko villege in Babura LGA. JEC/77/2019/VOL.1/17 Nuhabib Nig. Ltd. 32,792,767.93 Min of Works 14 weeks
54 2/10/2019 Electrification project (Lot-2) at Gangawa village in Jahun LGA. JEC/63/2019/VOL.1/17 Yanduna Ventures 90,247,560.30 Min of Works 14 weeks
55 3/10/2019
Constr of 1no. Block of 3-classrooms each at GDSS Babura, GDSS Galagamma Gumel, GDSS
babura and GDSS Ringim Areawa (2019 Capital projects) JEC/79/2019/VOL.1/8 Babandoki Gen Entp. 44,808,022.00 Min of Edcuation 12 weeks
56 3/10/2019
Constr of 1no. Block of 3-classrooms each at GDSS Dan Masara, GDSS Jahun, GDSS Shagari
Qtrs Hadejia and GDSS M/madori (2019 Capital projects) JEC/80/2019/VOL.1/8 Math Global Invest. 44,808,022.00 Min of Edcuation 12 weeks
57 25/09/2019
Renov of Science and ICT Labs. at 9no. Proposed Science Centres of Excellence core 2
(GGUSS M/madori, GDSS G/Gabas, GGSS Garki, GDSS Gwiwa, GUSS Aujara, GUSS Maigatari,
GDSS T/Gwaram, GC Birnin Kudu and GUSS Basirka) JEC/61/2019/VOL.1/6 AGM & Sons Nig Ltd. 24,140,000.00 Min of Edcuation 12 weeks
58 2/10/2019
Constr of hadejia township roads (485m) road Network) Additional works) at Azare road-
Adua Mosque-New Motor Park (Road II) JEC/71/2019/VOL.1/52 PAAche Constr Ltd. 312,270,011.92 Min of Works 16 weeks
59 2/10/2019 Constr of Babura township roads (10.28km) (Additional works) JEC/218/2018/VOL.1/31 Triacta Nig Ltd. 510,841,607.48 Min of Works 16 weeks
60 27/9/2019
Upgrading and Conversion of 1no. Motorised water supply scheme to Solar power at
UKU da SISI Sabuwa in Babura LGA JEC/63/2019/VOL.I/7 Sims Nig. Ltd. 6,767,532.45 Min of Water 8 weeks
61 27/9/2019 Rehab. of 13no. Water supply scheme at Ringim, Kazaure and Gumel LGA JEC/64/2019/VOL.I/7 Sims Nig. Ltd. 12,788,475.00 Min of Water 8 weeks
62 27/9/2019
Constr of (1no.) New Solar powered water supply scheme at YAN Maulu Tsohowu in
Babura LGA JEC/62/2019/VOL.I/7 Sims Nig. Ltd. 6,023,325.00 Min of Water 8 weeks
Bal.C/F 2,808,821,606.48
4
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 2,808,821,606.48
63 7/10/2019 Re-construction of B/kudu New General Hospital (Variations) JEC/20/2019/VOL.I/10 Datum Constr. Ltd. 395,712,672.97 Min of Health 16 weeks
64 28/10/2019
Constr of 1no. Block of 3-classrooms each at 8no. GDSS across the state (2019 Capital
Projects) JEC/87/2019/VOL.I/9 Math Global Invest. Ltd. 90,089,432.00 Min of Education 14 weeks
65 11/10/2019
Upgrading and Conversion of 1no. Motorised water supply scheme to Solar powered
atJigawar Dan Ali, Garun Gudunya in Babura LGA and JEKE in S/Tankarkar LGA JEC/81/2019/VOL.I/13 Sims Nig. Ltd. 18,459,647.97 Min of Water 8 weeks
66 11/10/2019 Rehab. of 19no. Water supply scheme in Babura (Ringim zone) JEC/82/2019/VOL.I/13 Sims Nig. Ltd. 17,361,750.00 Min of Water 8 weeks
67 27/11/2019
Renovation of Staff Quarters at College of Education Gumel, Lot-7 (3rd & 4rd Quarter 2019
Capital projects) JEC/117/2019/VOL.I/10 Babandoki General Entr 233,513,402.67 Min of Education 12 weeks
68 27/11/2019
Construction of 1No Block of 2 classroom Islamiyya School each, Lot-4 (First Quarter 2019
Constituency Project) at Dodal (Nomadic and Jammaje Gafaffa in Gwiwa JEC/99/2019/VOL.I/11 Isah Halilu Nig Ltd 6,226,306.20 Min of Education 8 weeks
69 27/11/2019
Construction of classrooms Blocks at Jigawa College of Remedial and Advance
Studies(JICORAS) Babura, Lot-4 (3rd & 4rd Quarter 2019 Capital Projects) JEC/115/2019/VOL.I/10 Babandoki General Entr 120,213,423.86 Min of Education 24 weeks
70 27/11/2019
Construction of 1No Block of 2 Classroom islamiyya School Lot-14B (First Quarter 2019
Constituency Project) at Hassan Hadejia in Hadejia constituency JEC/106/2019/VOL.I/11 Muhal Global Concept Ltd 9,100,200.00 Min of Education 9 weeks
71 27/11/2019
Renovation of 13No Students Hostels at College of education Gumel, Lot-8 (3rd &b 4rd
Quarter 2019 Capital Projects) JEC/118/2019/VOL.I/10 Babandoki General Entr 148,840,065.71 Min of Education 12 weeks
72 27/11/2019
Construction of Hostel Block at Jigawa College of remedial and Advance Studies (JICORAS)
Lot-5 (3rd & 4th Quarter 2019 Capital Projects) JEC/116/2019/VOL.I/10 Ngaloma Constr Co Ltd 100,763,064.17 Min of Education 24 weeks
73 27/11/2019
Construction of 1No. 2 classroom Islamiyya School each, Lot-6 (First Quarter 2019
Constituency Project at Abur, Margadu, Ahlal Sunnah Islamiyya, Musari and Wareri in Guri
Constituency JEC/110/2019/VOL.I/11 Adam General Enter Ltd 15,576,795.40 Min of Education 8 weeks
74 18/11/2019
Construction of 2No Block of 2 Classroom Islamiyya ( 2018 Phase II Ongoing Constituency
Projects) Lot-10 at danksoshe and Jatafinnamari in Buji Constituency JEC/92/2019/VOL.I/6 Mai-Mai Blocks Industry Ltd 6,231,539.60 Min of Education 8 weeks
75 27/11/2019
Construction of 1No Block of 2 Classroom Islamiyya School each Lot-12 (First Quarter 2019
Constituency Project at Kan Hawa Roni, Santar Tsaye and Sabuwar Santa Tunas in Roni
Constituency JEC/104/2019/VOL.I/11 Yanduna Ventures Ltd 9,339,248.04 Min of Education 10 weeks
76 18/11/2019
Construction of 3no Block of 2 classroom Islamiyya ( 2018 Phase III Ongoing Constituency
Projects) Lot-12 at Garin Kwalandi and Kabara in Maigatari Constituency JEC/94/2019/VOL.I/6 NBS & Sons Constr Ltd 15,140,562.72 Min of Education 8 weeks
77 18/11/2019
Construction of Malam Makera Islamiyya School (Upstairs) 2018 III Ongoing Constituency
project (Lot-1S) at Malam Abdullahi islamiyya Hadejia in Hadejia JEC/96/2019/VOL.I/6 Nabakwai General Entr 16,341,041.20 Min of Education 12 weeks
78 18/11/2019
Construction of 1No Block of 2 Classroom Islamiyya (2018 Phase II Ongoing Constituency
Projects) Lot-7 at Guri in Guri Constituency JEC/91/2019/VOL.I/6 Nushe Business Resources 3,115,779.08 Min of Education 8 weeks
Bal.C/F 4,014,846,538.07
5
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 4,014,846,538.07
79 18/11/2019
Construction of 2No Block of 2 Classroom Islamiyya (2018 Phase III Ongoing Constituency
Projects ) Lot-7 at Garin Musa and Daneri in Birniwa Constituency JEC/93/2019/VOL.I/6 BDU Ventures Ltd 6,227,358.16 Min of Education 8 weeks
80 14/11/2019
Construction of 1No Block of Science Laboratory and Administrative Block (Lot-1) at GDSS
Kukuma in Buji Constituency project 2019 JEC/88/2019/VOL.I/6 Yayarin Tukur Nig Ltd 22,937,034.15 Min of Education 8 weeks
81 18//11/2019
Construction of 1No Block of 2 classroom Islamiyya (2018 Phase III Ongoing Constituency
Projects) Lot-1B at Maskangayu In Auyo Constituency JEC/90/2019/VOL.I/6 DDN Constr Nig Ltd 3,115,359.08 Min of Education 8 weeks
82 14/11/2019
Construction of 1No Block of 3 classrooms each at GDASS Kiri Kasamma GDASS Bulangu
GDASS Miga GDASS Kiri Kasamma GDASS Bulangu GDASS Miga, GDASS Marma, GDASS
Limawa , GDASS Birniwa and GDASS Aujara JEC/89/2019/VOL.I/8 A.A. Maikatako Gen Entr 78,414,000.00 Min of Education 20 weeks
83 11l12l2019
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-19B at Kunduwaje and Gagura in Gwaram Constituency, JEC/132/2019/VOL.1/7 Nushe Bus, Resources Nig Ltd 6,685,247.76 Min of Education 6 weeks
84 11/12/2019
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-16 at Ramin kura, Juwan, Masaru and Nasarawa in Birnin Kudu
Constituency, JEC/128/2019/VOL.1/7 Nushe Bus, Resources Nig Ltd 12,888,711.92 Min of Education 10 weeks
85 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-1 at Fulanin Gamba, Fulanin Garu and Fulanin Kafur in Auyo Contituency. JEC/170/2019/VOL.1/20 AMM Manzo Nig Ltd 2,210,922.00 Min of Water Resources 8 weeks
86 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-26 atKankanba, Dodorin Tudu, Hardo Magaji, Mataran, Dalarin Kwalta, Bultuwa
Rigar Gabas, Dodorin Rigar Mal Yakubu, Bultuwa Rigar Kauga, Ung. Jibrin Masallacin Mal.
Kawu and Rigar Dado Gajere In Kaugama Contituency. JEC/184/2019/VOL.1/20 AMM Manzo Nig Ltd 7,377,510.00 Min of Water Resources 8 weeks
87 11/12/2019
Constr of Solar Powered Water Supply Schemes Constituency Project ( 2019 Phase 1) Lot-42
at Kilawa in Fagam Contituency. JEC/163/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks
88 11/12/2019
Upgradingand Conversation of 1no. Motorised water Supply Scheme (2019 phase1 )
Constituency Project Lot-22 at Zauma in Gwiwa Constituency. JEC/167/2019/vOL.1/9 Jignaj Global Contr Ltd 8,685,075.00 Min of Water Resources 8 weeks
89 11/12/2019
Upgradingand Conversation of 1no. Motorised water Supply Scheme (2019 phase1 )
Constituency Project Lot-23 at Korayalin Gwiwa Constituency. JECl168/2019/VOL.1/9 Jignaj Global Contr Ltd 6,863,325.00 Min of Water Resources 8 weeks
90 11/12/2019
Renov of 2no. Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot-
24 at Gidan Kudege and Kurneji in Gwiwa Constituency JEC/169/2019/VOL.1/9 Jignaj Global Contr Ltd 3,227,700.00 Min of Water Resources 8 weeks
91 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 41
at tsallakawa in Fagam Constituency, Gwaram Local Government Area JEC/162/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks
92 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 46
at Garin Urema in Hadejia Constituency JEC/165/2019/VOL.1/9 A+Tech Integrated Nig. Ltd 6,021,855.00 Min of Water Resources 8 weeks
93 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 45
at Gawon Dogari in Hadejia Constituency JEC/164/2019/VOL.1/9 Amia Integrated Service Nig Ltd 6,022,485.00 Min of Water Resources 8 weeks
Bal.C/F 4,197,569,561.14
6
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 4,197,569,561.14
94 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 39
atSabon Gari in Miga Constituency JEC/160/2019/VOL.1/9 Amia Integrated Service Nig Ltd 6,022,485.00 Min of Water Resources 8 weeks
95 6/8/2019
Upgrading and Conversion of Zaburan, Small Town Motorised Water Supply Scheme to Solar
Powered in Kaugama Local Government Area. FGPC/49/2019/VOL.1/7 Sims Global Resources Nig Ltd 16,917,862.50 Min of Water Resources 8 weeks
96 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-9 at Askawa, Kulawa Babare, Achau Boro, Lugga Dashi, Tokai Arewa, Ung. M.
Nagoggo, Damutawa, Gabashi, Rinde fulani, Bakin Kasuwa, Ung. Isah Yar Jigawa, Gwamfai
Sabon Gari, Tsangaya, Kulluru Yammaci, Alikau, Sukullufi, Gidan Atiku, Makera, Gwamfai, JEC/177/2019/VOL.1/20 Danfatu & sons Nig Ltd 14,755,650.00 Min of Education 8 weeks
97 27/11/2019
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-8 at Dansama , Gangara, M. Yaro and Garin Baki in Maigatari
Constituency, JEC/101/2019/VOL1/11 Mai-Mai Block Ind. Ni g Ltd 9,310,318.35 Min of Education 9 weeks
98 27/11/2019
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-1 at Girdo, Tasawa and Tsamiyar Kwance in Kanya Babba
Constituency Babura Local Government Area JEC/97/2019/VOL.1/12 Dee- Tech Nig Ltd 9,347,337.24 Min of Education 13 weeks
99 27/11/2019
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-7 at Jauga, Jankawa Yola, Karwai, Wailari and Budai in Ringim
Constituency JEC/100/2019/VOL.1/11 Marb eng. & Multi service Nig Ltd 15,576,585.00 Min of Education 8 weeks
100 27/11/2019
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-3A at Bukari and Aimas Kuka in Auyo Constituency JEC/98/2019/VOL.1/11 Mai-Mai Block Ind. Ni g Ltd 6,226,518.18 Min of Education 12 weeks
101 27/11/2019
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-13 at Kiri Hawandu, Katarika and Kawari/Gujungu in Taura
Constituency JEC/105/2019/VOL.1/11 Nushe Bus, Resources Nig Ltd 11,719,771.12 Min of Education 12 weeks
102 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 40
at Gidan Barwa in Miga Constituency JEC/161/2019/VOL.1/9 A. Barde Global Concept Ltd 6,023,010.00 Min of Water Resources 8 weeks
103 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 4 at
Juba Gandu in Auyo Constituency JEC/137/2019/VOL.1/9 Alh. Umaru Baban Doki Nig Ltd 6,004,715.00 Min of Water Resources 8 weeks
104 11/12/2019
Constr of Water Collection Point 2019 First Quarter Constituency Project (Lot-22) at Yofai,
Tuyau, Gidan Kara, Dagasa, Jiyau, Fulani, Jiyau Babba, Tagwai, Kun Kurawa, Danbaje, Auramo
Gabas Zangon Sallau, Dan Tsiru, Tsurutawa, Auramo Tudu, Gidan Sani, Zabara, Durno, Kuna,
Dara Zai and Bangon Jani in Ringim Constituency. JEC/193/2019/VOL.1/20 Prestige Integ Serv. Nig Ltd 25,206,980.00 Min of Water Resources 8 weeks
105 11/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 39
at Gabari in Malam Madori Constituency JEC/159/2019/VOL.1/9 Prestige Integ Serv. Nig Ltd 6,022,695.00 Min of Water Resources 8 weeks
106 3/12/2019
Constr of additional 1no. Block of 3- Classrooms each at GDSS Kazaure, GDSS Sabon Gida,
GDSS Haruna (Hadejia), GDSS Fagoji, GDSS Galagamma Gumel and GDSS Famfo Goma
Hadejia (2019 MOEST Capital project) JEC/120/2019/VOL.1/6 Al-sabur Global Links Nig Ltd 67,212,333.84 Min of Education 12 weeks
Bal.C/F 4,397,915,822.37
7
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 4,397,915,822.37
107 23/12/2019
Constr of Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot- 3 at
Sabuwar Auyo in Auyo Constituency JEC/278/2019/VOL.1/6 A.A Aljazeera Agro Processing Nig Ltd 6,010,515.00 Min of Water Resources 8 weeks
108 17/12/2019
Renov/Completion of 2no. Friday prayer mosques (2019 first Quarter constituency projects)
Lot_91 at Danmakama and Dangwanki In Sule Tankarkar Constituency. JEC/267/2019/VOL.1/25 A.A Aljazeera Agro Processing Nig Ltd 7,331,978.53 Cabinet office 8 weeks
109 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-28 at Tashar Yellow, Fulani Cakindi, Turkushawa Gari, Gidan Amadu Inge,
Fulanin Kaina, G. Idi Shiba, Fulanin Hammado, Gidan Dibbo in Sule Tankarkar Contituency. JEC/186/2019/VOL.1/20 A.A Aljazeera Agro Processing Nig Ltd 4,426,695.00 Min of Water Resources 8 weeks
110 17/12/2019
Renov/Completion of 1no. Friday prayer mosques (2019 first Quarter constituency projects)
Lot_82 at Bango in Fagam Constituency. JEC/260/2019/VOL.1/25 A.A Aljazeera Agro Processing Nig Ltd 6,202,006.45 Cabinet office 8 weeks
111 11/12/2019
Constr of Water Collection Point 2019 First Quarter Constituency Project Lot- 19 at Kofar
Kudu Basirka, kofar Yamma Basirka Dal and Kofar Tela Basirka in Fagam Constituency,
Gwaram LGA JEC/190/2019/VOL.1/20 Jignaj Global Contr Ltd 4,876,422.00 Min of Water Resources 8 weeks
112 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 49 at
Butiranawa Fulani, Buduru nad Fulanin Bayan Zarga in Taura Constituency. JEC/235/2019/VOL.1/25 Gamdu Multi Purpose Ltd 5,874,753.15 Cabinet office 8 weeks
113 17/12/2019
Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 1 at
Maro, Katangar Tsamiya, Guyu, and Tsurufawa in Auyo Constituency. JEC/197/2019/VOL.1/25 Gamdu Multi Purpose Ltd 7,833,028.20 Cabinet office 8 weeks
114 11/12/2019
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-10B, at Bashuri in Dutse Constituency, JEC/135/2019/VOL.1/7 Al-kheeyad Nig Ltd 3,115,676.00 Min of Education 8 weeks
115 17/12/2019
Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 24 at
Oliya Sararin Rakuma and Lungum Mutari Dankoli in Hadejia Constituency. JEC/217/2019/VOL.1/25 Alh. Umaru Baban Doki Nig Ltd 8,949,483.00 Cabinet office 8 weeks
116 17/12/2019
Completion/Renov. 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot -
57 at Kantin Waje, Tudun Wada, Unguwar NTA and Yankoli in Hadejia Constituency. JEC/243/2019/VOL.1/25 Alh. Umaru Baban Doki Nig Ltd 10,339,715.08 Cabinet office 8 weeks
117 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 30 at
Jallomi Arewa, Manak and Kanjiwa in Kaugama Constituency. JEC/220/2019/VOL.1/25 Alh. Umaru Baban Doki Nig Ltd 5,870,866.05 Cabinet office 8 weeks
118 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 31
atDaneri, Kanoke and Kota in Kaugama Constituency. JEC/221/2019/VOL.1/26 Alh. Umaru Baban Doki Nig Ltd 5,884,568.55 Cabinet office 8 weeks
119 11/12/2019
Renov of 2no. Solar Powered water Supply schemes Contituency project ( 2019 Phase 1) Lot-
24 at Gidan Kudege and Kurneji in Gwiwa Constituency JEC/169/2019/VOL.1/9 Jignaj Global Contr Ltd 3,227,700.00 Min of Water Resources 8 weeks
120 11/12/2019
Constr of Water Collection Point 2019 First aquarter Constituency Project Lot- 23 at Kauyen
Zarga and Rigarsu Iro Akwai Allah In Taura Constituency JEC/194/2019/VOL.1/20 Nushe Bus, Resources Nig Ltd 2,519,647.20 Min of Water Resources 8 weeks
121 11/12/2019 Constr of Jigawar Dan Ali Township Road (2.10KM) (Additional Work) FGPC/887/2018/VOL.1/51 Mother Cat Nig Ltd 203,412,195.00 Min of Works 16 weeks
122 11/12/2019
Constr of Gwaram Tsohuwa and Gwaram Sabuwa Towns Water Supply Scheme (Additionsl
Works) FGPC/897B/2018/VOL.1/13 Nushe Bus, Resources Nig Ltd 29,520,524.45 Min of Water Resources 12 weeks
Bal.C/F 4,713,311,596.03
8
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 4,713,311,596.03
123 23/12/2019
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Ringim
Arewa, K/Babba, Gujungu, Sakwayya and G/Kuka (2019 Last Quarters MOEST Capital project
Across the state (Lot-1ABCD&E) JEC/290/2019/VOL.1/9 Ngaloma Constr Nig Ltd 103,609,125.68 Min of Education 12 weeks
124 23/12/2019
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Bosuwa,
Taura, and Gumel (2019 Last Quarters MOEST Capital project Across the state (Lot-3AB&C) JEC/292/2019/VOL.1/9 Babandoki Gen. Enterp Nig Ltd 104,213,888.67 Min of Education 12 weeks
125 27/12/2019
Constr of Classes, Laboratories at GDSS Kafin Hausa, Kadira, Shagari, Dakido, Kanti, Roni,
Danmasara, Kudai, Birnin Kudu, Malamadori and Kiyawa (2019 Last Quarters MOEST Capital
project Across the state (Lot-5ABC&D) JEC/315/2019/VOL.1/9 Sabon Garin yaya Nig Ltd 106,186,110.20 Min of Education 12 weeks
126 27/12/2019
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS Galadi,
GDSS Marabusawa, GDSS Dakido (2019 Last Quarters MOEST Capital project Across the state
(Lot-4AB&C) JEC/314/2019/VOL.1/9 Math Global Invt. Nig Ltd 104,338,846.77 Min of Education 12 weeks
127 27/12/2019
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand Pumps at GDSS
Danzomo, GDSS Abdulkadir, and GDSS Babaldu (2019 Last Quarters MOEST Capital project
Across the state (Lot-7AB&C) JEC/317/2019/VOL.1/9 Pullad Global Consultant Nig Ltd 114,843,483.25 Min of Education 12 weeks
128 27/12/2019
Constr of Toilets, Admin Blocks, Laboratories and Wall Fence, 7no. JSQ Eamination Hall and
additional course of Blocks Hand pumps at GDSS Kazaure, Dutse Capital, Bamaina Academy,
Dutse Model and GDSS Jabo (2019 Last Quarters MOEST Capital project Across the state (Lot-
6 ABCDE&F) JEC/316/2019/VOL.1/9 Pullad Global Consultant Nig Ltd 109,273,620.31 Min of Education 12 weeks
129 23/12/2019
Constr of Admin. Block, 21 Laboratories, Computer Lab. And 3-Blocks of 12 Classrooms at
Mega School Dutse (2019 Last Quarter MOEST Capital projects) Across the State (Lot-8 ABC &
D) JEC/297/2019/VOL.1/9 Babandoki Gen. Enterp Nig Ltd 224,397,873.13 Min of Education 12 weeks
130 17/12/2019
Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-65 at
Yayarin Tukur Yamma In Buji Constituency JEC/246/2019/VOL.1/25 Yayarin Tukur Nig Ltd 10,318,579.38 Cabinet office 8 weeks
131 17/12/2019
Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 10 at
Kabbe, J/mesa and Kore Bakwarga in Buji Constituency. JEC/204/2019/VOL.1/25 Yayarin Tukur Nig Ltd 3,920,345.07 Cabinet office 8 weeks
132 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 9 at
U/Malam Amadu Damisa, Dambazaau Yamma and Kawaya Kudu in Buji Constituency. JEC/203/2019/VOL.1/25 Yayarin Tukur Nig Ltd 5,880,518.55 Cabinet office 8 weeks
133 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 21 at Yola
Kauye, Unguwar Gandu and Shema in Gwiwa Constituency. JEC/214/2019/VOL/1/25 Jignaj Global Contr Ltd 5,884,566.00 Cabinet office 8 weeks
134 24/12/2019
Constr of 3no Modified Basic Health Clinics at Bagadaza, Larkan and Dukwana in Fagam
Constituency (2019 Constituency projects) JEC/301/2019/VOL.1/7 Yayarin Tukur Nig Ltd 25,565,018.85 Min of Health 12 weeks
135 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-12 at Sabuwar Jawo (sabaru ward), fulanin Ballami (Dandi ward), K/mal. Ali
Headmaster (Gada ward), K/Alto Makeri (Gada ward) and Makabarat Gabas ( Gada ward) in
Kazaure Contituency. JEC/179/2019/VOL.1/20 Yanduna Venture Nig Ltd 3,686,287.50 Min of Water Resources 8 weeks
Bal.C/F 5,635,429,859.39
9
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 5,635,429,859.39
136 11/12/2019
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-21 Dumbi, Yarchidau and Gurjiya in Yankwashi Constituency, JEC/133A/2019/VOL.1/7 Yanduna Venture Nig Ltd 9,339,771.12 Cabinet office 12 weeks
137 11/12/2019
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first quarter phase 2
Constituency projects) Lot-15 at Daba, Tsohuwar Jawo, Islamiyya Layin Emilalo and Bayan
Lawan Yarima in Kazaure Constituency, JEC/127/2019/VOL.1/7 Yanduna Venture Nig Ltd 12,427,559.12 Cabinet office 10 weeks
138 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-8 at
Tsohuwar Fitare in Kazaure Constituency JEC/141/2019/VOL.1/9 Yanduna Venture Nig Ltd 6,023,115.00 Min of Water Resources 8 weeks
139 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-7 at
Wawan Rafi in Kazaure Constituency JEC/140/2019/VOL.1/9 Yanduna Venture Nig Ltd 6,023,115.00 Min of Water Resources 8 weeks
140 17/12/2019
Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 48 at
Bandakado and Kuka in Sule Tankarkar Constituency. JEC/234/2019/VOL.1/25 HM Dagara Ldt 3,918,215.20 Cabinet office 8 weeks
141 17/12/2019
Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-79 at
Komai Allah Yayi in Miga Constituency JEC/257/2019/VOL.1/25 Amia Integrated Service Nig Ltd 10,200,863.74 Cabinet office 8 weeks
142 17/12/2019
Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 40 at
Tsohuwar Dalan, Dangoli, Yandadi and Mazama In Miga Constituency. JEC/227/2019/VOL.1/25 Barde Global Concept Nig Ltd 7,840,683.40 Cabinet office 8 weeks
143 17/12/2019
Constr of 2no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 23 at
Faranunbunare and Borandage in Gwiwa Constituency. JEC/216/2019/VOL.1/25 Jignaj Global Contr Ltd 3,923,045.70 Cabinet office 8 weeks
144 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 22 at
Ture kwando, Unguwar Yamma and Z/sainawa G/Dagachi in Gwiwa Constituency. JEC/215/2019/VOL.1/25 Jignaj Global Contr Ltd 5,884,568.55 Cabinet office 8 weeks
145 17/12/2019
Compl/Renov of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-90
at Tasheguwa in Kirikasamma Constituency JEC/266/2019/VOL.1/25 Manhaf Global Constr Nig Ltd 7,442,582.78 Cabinet office 8 weeks
146 17/12/2019
Constr of 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot - 47 at
Tagwayen Kuka, Santarbi and Chiromawa in Sule Tankarkar Constituency. JEC/233/2019/VOL.1/25 HM Dagara Ltd. 5,877,322.53 Cabinet office 8 weeks
147 6/12/2019 Constr of Basic Health Centre (BHC) at Masaya Village in Kiyawa Constituency (2nd quarter 2018 Constituency project)JEC/124/2019/VOL/1/6 Umar Aliyu & Sons Nig Ltd 11,853,799.02 Min of Health 12 weeks
148 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-14 at Tuda, Zakirai, K/gidan Mal Mai unguwa, Gidan Dachi, Majiyawa, Gangare,
Jigawar Kaba, Mazazzaga, Yammachi, Fake cikin Gari, Kabobi, Haddori, Jama'ar isah
Yaldewa/Gumai, Malamawa, Zakoro, Tasha, Jama;ar Dawa Fulani, Unguwar Abdullahi Mati,
Jigawar Tsaba and Makarantar Andaza in Kiyawa Contituency. JEC/181/2019/VOL.1/20 Tosarawa Global Nig Ltd 14,739,900.00 Min of Water Resources 12 weeks
149 11/12/2019
Constr of Water Collection Point 2019 First Quarter Constituency Project (Lot-21) at Fake
Cikin Gari, Kalali, Katuka Cikin Gari, Garko Cikin Gari, Shuwarin Cikin Gari, Turho, Tsurma
cikin Gari, Kadara Dankargo and Dangoli in Kiyawa Constituency. JEC/192/2019/VOL.1/20 Tosarawa Global Nig Ltd 12,603,490.00 Min of Water Resources 8 weeks
150 17/12/2019
Constr of 1no Friday Prayer Mosque (2019 First Quarter Constituecy projects) Lot-66 at
Sabon Garin Rabadi in Fagam Constituency JEC/247/2019/VOL.1/25 NBS & Sons Nig Ltd 9,171,846.17 Cabinet office 8 weeks
151 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-2 at
Kafeje in Auyo Constituency JEC/136/2019/VOL.1/9 AMM Manzo Nig Ltd 6,004,215.00 Min of Water Resources 8 weeks
152 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-19 at
Ruwa yakaika in Gwiwa Constituency JEC/148/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks
Bal.C/F 5,774,727,171.72
10
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 5,774,727,171.72
153 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-20 at
yola Kauye in Gwiwa Constituency JEC/149/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks
154 11/12/2019
Consrt of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-21 at
tudunya in Gwiwa Constituency JEC/150/2019/VOL.1/9 Jignaj Global Contr Ltd 6,023,220.00 Min of Water Resources 8 weeks
155 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-17 at yankwashi fulani, rauda gabas and dumbule in yankwashi constituency. JEC/183/2019/VOL.1/20 Granitoids Engr Services 2,213,032.00 Min of Water Resources 8 weeks
156 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-34 at
addani in yankwashi Constituency JEC/158/2019/VOL.1/9 Granitoids Engr Services 6,022,590.00 Min of Water Resources 8 weeks
157 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-33 at
karkarna in yankwashi Constituency JEC/157/2019/VOL.1/9 Granitoids Engr Services 6,022,590.00 Min of Water Resources 8 weeks
158 11/12/2019
Constr of 4no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lots - 16 at
galamawa, G/Biredi, Sabalari, sakwaya and hausawa in Dutse Constituency. JEC/209/2019/VOL.1/9 Backbone global l inks ltd 7,836,430.04 Cabinet office 8 weeks
159 23/12/2019
Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-35 at
manomi in Malammadori Constituency JEC/285/2019/VOL.1/6 Step by Step Int. Ser. Ltd 6,022,905.00 Min of Water Resources 8 weeks
160 23/12/2019
Constr of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-37 at
Surakin in Malammadori Constituency JEC/286/2019/VOL.1/6 Step by Step Int. Ser. Ltd 6,022,905.00 Min of Water Resources 8 weeks
161 23/12/2019
Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-9 at
munar yan biyu in Kanya Constituency, Babura LGA. JEC/279/2019/VOL.1/6 Deetech Nig. Ltd 6,010,935.00 Min of Water Resources 8 weeks
162 23/12/2019
Constr. of Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-30
atkukule in Gagarawa Constituency JEC/283/2019/VOL.1/6 Farham Synergy Ltd 6,022,800.00 Min of Water Resources 8 weeks
163 11/12/2019
Constr. of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II
constituency projects) Lot-19 at B/kasuwa, Sakuwa and Ranbazau in Gwaram constituency JEC/131/2019/VOL.1/7 Farham Synergy Ltd 9,344,513.19 Min of Education 8 Weeks
164 23/12/2019
Constr. of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
31 Mutumbi in Gagarawa Constituency JEC/284/2019/VOL.1/6 Farham Synergy Ltd 6,022,800.00 Min of Water Resources 8 weeks
165 23/12/2019
Consrt of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
10 at Kanya cikin gari in Kanya Constituency, Babura LGA. JEC/280/2019/VOL.1/6 Deetech Nig. Ltd 6,010,935.00 Min of Water Resources 8 weeks
166 17/12/2019
Completion/Renov. 3no. Daily Prayer Mosques (2019 First Quarter Constituency project) Lot -
55 at Kundum, Jar kasa B/kasuwa Basirka and and bangon fulani in fagam Constituency. JEC/241/2019/VOL.1/25 Yayarin Tukur Nig Ltd 9,274,972.59 Cabinet office 8 weeks
167 27/12/2019
Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II
constituency projects) Lot-10A at jidawa, rahama, duru gari, karnaya gari, abanderi, hara and
tashar D/wake in Dutse constituency JEC/111/2019/VOL.1/11 Backbone global l inks ltd 21,724,075.66 Min of Education 18 Weeks
Bal.C/F 5,885,325,095.20
11
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 5,885,325,095.20
168 27/12/2019
Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter phase II
constituency projects) Lot-11 at dahuwa kaku in kiri kasamma constituency JEC/103/2019/VOL.1/11 Nabakwai gen. entr. 3,103,439.45 Min of Education 8 Weeks
169 18/12/2019
Drilling of borehole and construction of overhead tank at fire service directorate
headquaters in Dutse (2019 capital project) JEC/273/2019/VOL.1/8 Al-juraj synergy concept Ltd 6,734,650.13 Min of Water Resources 8 weeks
170 11/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-10 at K/hausa gen. Hospital, bayan reformatory school, alakalawa A,
alakalawa B, Makarantar allo kudu K/hausa, makarantar D/jalla, Makarantar M. sa'adu,
makarantar turkawa, makarantar asharan chiroma, filin idi K/hausa, makarantar su shamsu,
dawasa, yan darman shukura, fulanin toyara, kashe badi, chiroma kwakwata, kutungun,
aguran kwari, usman kukoki, tagadawai, abewa, kazuba, karfa kama, rigar kanawa, kazalewa
UNG, sule M. tubka, kununu, lafiya, katanga, rigar D/iya, kijinawa M. sa'adu, marwa
abdullawa, zilawa abdullawa, aragada abdullawa, kanzan fulani (mai jama'a jingi),
kargumaka (jema haruna), karori, fulanin baushe, mamajo, fulanin rumfa and baushe gari in
K/Hausa constituency. JEC/178/2019/VOL.1/20 Mugin Inv. Nig. Ltd 29,509,200.00 Min of Water Resources 16 Weeks
171 19/12/2019
Rehabilitation of 3no. Water supply scheme at danzomo, maitsamiya, and dankumbo in sule
tankarkar (gumel zone 2019) Lot-2 capital projects JEC/276/2019/VOL.1/8 LIMIS Brothers & Co 4,628,531.25 Min of Water Resources 4 weeks
172 11/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-4 at wuro bagga, gamawari, yola zairare, fulanin takaje, sabon gidan gabas,
fulanin kufayi, hijabau, adamante, rugar abdul kogi, masharmo, makwasharga, waryam B,
lautayi, Yambo, Jalingo G/kwalli, kawarin gari, yadda, gidan yauto (Z/kanya), gumurwa G.A
Idi, Rimin kasuwa and shamakeri B/hanya in Bulangu constituency JEC/173/2019/VOL.1/20 Bulangu dril l ing serveices Ltd 15,491,227.50 Min of Water Resources 12 Weeks
173 11/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-27 at jalomin kudu, malari, zaburan, Ung/tsamiya, kundu, marke ung gabas,
Dunbari, chuguliski, rigar ya'u karami, dolon malam and arbus ung. Mamman in kaugama
constituency JEC/185/2019/VOL.1/20 Mufabamex concept nig. Ltd 7,376,800.00 Min of Water Resources 8 Weeks
174 11/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-30 at koluma, kodau, kata kata, kayoyi, turakan fulani, gidan jauro, jalingo
S/sara, Baba ari, tsangayar gabas, malumawa, karalbali iguda, gobararin fulani, fulanin kira
karama, rugar babayo, gamayin yamma, kayoyi jabo, tafa, jabo gabas, makerawa H/ali and
rugar amadu babai in bulangu costituency JEC/188/2019/VOL.1/20 yusmatech inv. Nig. Ltd 14,754,800.00 Min of Water Resources 14 Weeks
175 11/12/2019
Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II
Constituency projects) Lot-14A at Abdulkadir Secondary School, Matasro Junior Secondary
School and Unguwar Mai aye in Hadejia constituency JEC/126/2019/VOL.1/7 Step by Step Int. Ser. Ltd 9,334,463.01 Min of Education 10 weeks
176 24/12/2019
Constr of 2no. Township Gate in Gumel Local Government Area 2019 third quarter
Constituency projects GHS/A/130/VOL.111/705 Gare Invest Nig Ltd 9,099,121.73 Min of Environment 8 weeks
177 24/12/2019
Constr of Drainage at Kamfala Town in Malam Madori LGA 2019 First Quarter Constituency
Project GHS/A/130/VOL.111.694 Ramadan Constr Nig Ltd 12,261,288.37 Min of Environment 12 weeks
Bal.C/F 5,997,618,616.64
12
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 5,997,618,616.64
178 24/12/2019 Constr of Drainage at Hammado in Gumel LGA 2019 Third Quarter Constituency Project GHS/A/130/VOL.111/698 farham synergy con. Ltd 6,497,962.62 Min of Environment 8 weeks
179 24/12/2019
Constr of Drainage at Marakumi Town in Malam Madori LGA 2019 First Quarter Constituency
Project GHS/A/130/VOL.111./679 Meyadi Concept Nig Ltd 9,923,643.97 Min of Environment 12 weeks
180 24/12/2019 Constr of Drainage at Kargo Town in Garki LGA 2019 First Quarter Constituency Project GHS/A/130/VOL.111/684 Umar Aliyu & Sons Nig Ltd 12,899,602.80 Min of Environment 12 weeks
181 24/12/2019 Constr of Drainage at Kandahar in HadejiaLGA 2019 First Quarter Constituency Project GHS/A/130/VOL.111/690 Tasi'u Muhd Invt Nig Ltd 19,286,864.77 Min of Environment 12 weeks
182 24/12/2019
Constr of Drainage at Dantanoma Quarters in Gumei LGA 2019 Third Quarter Constituency
Project GHS/A/130/VOL.3/687 JAG & H Intergreted Service 7,223,498.48 Min of Environment 12 weeks
183 24/12/2019 Constr of Drainage at Dingaya Town In Gwaram LGA 2019 First Quarter Constituency Project GHS/A/130/VOL.III/701 Pullad Global Consultant Nig Ltd 16,180,030.57 Min of Environment 12 weeks
184 13/12/2019 Constr of Drainage at Fake in Kiyawa LGA 2019 2nd Quarter Constituency Project GHS/A/130/VOL.III/666 AGM & Sons Nig Ltd 14,830,841.81 Min of Environment 12 weeks
185 13/12/2019 Constr of Drainage at Makeral Kirnande in Miga LGA 2019 1st Quarter Constituency Project GHS/A/130/VOL.III/680 A. Barde Global Concopt Ltd 5,341,392.00 Min of Environment 8 weeks
186 13/12/2019 Constr of Drainage at Lungun Malamai in Hadejia LGA 2019 1st Quarter Constituency Project GHS/A/130/VOL.III/676 Amia Integrated Service Nig Ltd 4,118,002.53 Min of Environment 8 weeks
187 13/12/2019
Constr of Drainage and Culverts at Kukuma Town in Buji LGA 2019 1st Quarter Constituency
Project GHS/A/130/VOL.III/670 Yayarin Tukur Nig Ltd 9,749,911.22 Min of Environment 12 weeks
188 12/12/2019 Laterite filling at Shuwarin Town in Kiyawa LGA under 3rd Quarter 2018 Constituency Project GHS/A/130/VOL.III/663 Khairushabah Nig Ltd 4,193,265.30 Min of Environment 8 weeks
189 24/12/2019
Constr of Additional 6no. Blocks of 1-block of 3-classrooms at GDSS Kondiko, GGDSS B/kudu,
GDSS Kwarko, GDSS Kiyako, GDSS S/garin Takanebu and GDSS Galamawa GHS/A/4/VOL.IV/220 Babandoki Gen. Entp. 67,198,406.92 Min of Education 10 weeks
190 24/12/2019 Constr of 1-block of two Science Laboratories at GGDSS Roni GHS/A/4/VOL.IV/206 Manhaf Global Concept 33,552,607.41 Min of Education 16 weeks
191 23/12/2019 Construction of pipeline distribution network (28.6km) in Kazaure Town Lot-1 JEC/302/2019/VOL.1/8 CGC Nigeria Ltd 529,952,482.00 Min of Water Resources 24 weeks
192 17/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
97 at Basirka JIBWIS Jumu'at Mosque in fagam Constituency JEC/272/2019/VOL.1/25 Lines dimensions Nig Ltd 3,640,350.00 Min of Water Resources 8 weeks
193 17/12/2019
Installation of solar electrification (2019 first quarter constituency project) Lot-96 at Digijin
and fagam central mosques in fagam constituency JEC/271/2019/VOL.1/25 Lines dimensions Nig Ltd 4,672,301.71 Cabinet office 8 weeks
194 17/12/2019
Installation of solar electrification (2019 first quarter constituency project) Lot-95 at galambi
and basirka central mosques in fagam constituency JEC/270/2019/VOL.1/25 Lines dimensions Nig Ltd 4,478,167.05 Cabinet office 8 weeks
195 19/12/2019
Consr rof 1NO. Solar Powered Water Supply Scheme Lot-7 at Daki daka in Garki LGA (Ringim
zone 2019)-capital project JEC/275/2019/VOL.1/8 LIMIS Brothers & Co 6,019,125.00 Min of Water Resources 8 weeks
196 19/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Lot-8 at Kunyafa in Babura LGA (Ringim
zone 2019)-capital projects JEC/274/2019/VOL.1/8 LIMIS Brothers & Co 6,019,125.00 Min of Water Resources 8 weeks
197 27/12/2019
Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II
Constituency projects) Lot-20 at garkon alli in kiyawa constituency JEC/112/2019/VOL.1/11 Yarkwari global serv Nig. Ltd 3,113,973.13 Min of Education 12 weeks
198 27/11/2019
Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter Phase II
Constituency projects) Lot-3B at Zamini tagir in Auyo constituency JEC/108/2019/VOL.1/11 Yarkwari global serv Nig. Ltd 3,013,570.00 Min of Education 8 weeks
199 23/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
1 at Kafardu in auyo Constituency JEC/277/2019/VOL.1/6 Faahm Integrated Ltd 6,018,915.00 Min of Water Resources 8 weeks
Bal.C/F 6,775,542,655.93
13
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 6,775,542,655.93
200 11/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-5 at Maibarewa, Sabalari, K/Fulani and Kadusawa in Dutse constituency JEC/174/2019/VOL.1/20 Farham synergy con. Ltd 2,947,896.00 Min of Water Resources 8 weeks
201 14/12/2019
Construction of water collection points 2019 first querter constituency projects Lot-18 at
kadiran, fagi, karanga and karde in birniwa constituency JEC/189/2019/VOL.1/20 Dabino integ serv Ltd 5,050,128.00 Min of Water Resources 12 weeks
202 14/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-3 at kazura, rugar taho, fulanin karanga, fulanin karanga gabas, fulanin fagi,
rugar saga, fulanin diginsa, Gidan Mal Dahiru, Birniwa U/yamma, rugar idi kulla, rugar
haberi, mara, diginsa, fulanin batu, Umaru mai goro, fulanin mai zariya, korewa, fulanin
kachallari, dargazawa, fulanin kishinde, gidan amadu, fulanin kazadama and inkibulawa
gabas in birniwa constituency JEC/172/2019/VOL.1/20 Dabino integ serv Ltd 15,492,109.50 Min of Water Resources 12 weeks
203 23/12/2019
Construction of classes and admin block at GDSS Kwalam, wurno, kyarama, and sankara
across the state (2019 last quarter MOEST capital projects) lots-9ABCD$E JEC/298/2019/VOL.1/9 Allah Abin Godiya Nig Ltd 51,991,144.67 Min of Education 12 weeks
204 23/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
44 at alkalawa in K/hausa Constituency JEC/289/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks
205 23/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
43 at Kore in K/hausa Constituency JEC/288/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks
206 23/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
38 at gari uku in malam madori Constituency JEC/287/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks
207 23/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
18 at garin tudu in maigatari Constituency JEC/282/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks
208 23/12/2019
Constr of 1NO. Solar Powered Water Supply Scheme Constituecy project (2019 Phase 1) Lot-
17 at kwaduge in maigatari Constituency JEC/281/2019/VOL.1/6 Hambiscons Nig Ltd 6,016,920.00 Min of Water Resources 8 weeks
209 24/12/2191 Rehabilitation of 18No. Water supply Schemes Across the state. JEC/312/2019/VOL.1/13 LIMIS Brothers & Co 9,748,615.80 Min of Water Resources 8 weeks
210 27/12/2019 Constr. Of 1No. Basic Health Clinic at Hangu Village in Gwiwa Constituency project 2019 JEC/303/2019/VOL.1/7 Manhaf Global Constr Nig Ltd 19,663,090.37 Min of Health 16 Weeks
211 17/12/2019
Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 51
at Dankama, Karkanai, Burji Fulani and Kuda in Yankwashi Constituency. JEC/237/2019/VOL.1/25 Granitoids Engr Services ltd 7,836,430.04 Cabinet office 8 weeks
212 18/11/2019
Constr, of 2No. Block of 2 Classroom islamiyya (2018 Phase iii on Going Constituency
Projects) Lot-2 at Dadda Gari, Madoji Gari, Jeke Gari and Sarkin Gandu in Sule Tankarkar
Constituency. JEC/95/2019/VOL.1/6 Danfatu & sons Nig Ltd 12,454,716.33 Min of Education 12 weeks
213 24/12/2019
Renovation of WindstormDamaged Structures at Government Science Technical college
Karkarna, Science Secondary School Kafin Hausa and Girls Science Secondary School Jahun
Across the state (2019 MOEST Capital Projects). JEC/313/2019/VOL.I/7 Allah Abin Dogaro Nig Ltd 35,803,002.26 Min of Education 8 weeks
214 11/12/2019
Constr, of 2No. Block of 2 Classroom islamiyya Each (2018 first Quarter Phase II Constituency
Projects) Lot-21 at Ung. Kalgo, Kuda walawa and Bade fulani yankwashi Constituency. JEC/133B /2019/VOL.I/7 Granitoids Engr Services ltd 9,339,771.12 Min of Education 12 weeks
215 11/12/2019
Constr of Soler Power supply Scheme Constituecy project (2019 Phase I) Lot-32 at
Ganbabituwa in Kirikasamma Constituency. JEC/156/2019/VOL.I/9 Dabino integ serv Ltd 6,017,235.00 Min of Water Resources 8 weeks
216 17/12/2019
Constr of 1No. Friday Prayer Mosque (2019 First Quarter Constituency Projects) Lot-67 at
Tsakuran in Fagam Constituency JEC/248/2019/VOL.I/25 Isa Halilu Nig. Ltd 9,315,820.89 Cabinet office 8 weeks
Bal.C/F 6,991,287,215.91
14
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 6,991,287,215.91
218 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-13 at Sawon Yamma, Gishingawa 2no., Rigar kaiwari, Iyo, Tage, Garin Wakili
Gilakochini, Barmaguwa 2no. Fandun Fulani, Gayin Gane, Lofanga, Daladige, Babba Kamaji
and Marawaji in Kirikasamma Constituency. JEC/180/2019/VOL.I/20 Dabino Integ Serv. Ltd 11,792,080.00 Min of Water Resources 12 weeks
219 11/12/2019
Construction of solar power water supply scheme constituncy project (2019 phase I) Lot-32
at Ganbabituwa in kirikasamma constituency. JEC/156/2019/VOL.I/9 Dabino Integ Serv. Ltd 6,017,235.00 Min of Water Resources 8 weeks
220 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 5
atYakuda, zazzaugawa and kwalele in Birnin kudu Constituency. JEC/200/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,881,568.50 Cabinet office 8 weeks
221 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 4
at Kauyen Abuja, Lemo and Gidan Bello in Birnin kudu Constituency. JEC/199/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,883,340.05 Cabinet office 8 weeks
222 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 3
at Fa'a, Chagu and Gudalai in Birnin kudu Constituency. JEC/198/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,879,148.00 Cabinet office 8 weeks
223 11/12/2019
Construction of hand pump boreholes water supply schemes constituency projects (2019
first quarter) Lot-15 at Sabon Sara, Jigalari, Lumu and Gidan Maza in Miga constituency JEC/182/2019/VOL.I/20 A. Barde Global Concopt Ltd 2,948,820.00 Min of Water Resources 8 weeks
224 17/12/2019
Construction of 2No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 50
at Dkakawar Dinya and Kangal in Taura Constituency. JEC/236/2019/VOL.I/25 Dankwara M/jimina Inv. Nig. Ltd 3,916,502.10 Cabinet office 8 weeks
225 17/12/2019
Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot-
63 at Dirimowa in Birniwa Constituency. JEC/244/2019/VOL.I/25 AMM Manzo Nig Ltd 10,518,579.33 Cabinet office 12 weeks
226 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 42
at magamar uku miga, kikatawa miga and rugar rama in miga Constituency. JEC/229/2019/VOL.I/25 Amia Integrated Service Nig Ltd 5,880,512.85 Cabinet office 8 weeks
227 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 41
at zangon jigawa gabas, garin gami and gidan kanya in miga Constituency. JEC/228/2019/VOL.I/25 Amia Integrated Service Nig Ltd 5,880,512.55 Cabinet office 8 weeks
228 17/12/2019
Costraction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 7 at
arobade, mungolo and kwanar kangire in Birnin Kudu Constituency. JEC/202/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,874,753.15 Cabinet office 8 weeks
229 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 6
at saboru, unguwar yamma and karfawa in Birnin Kudu Constituency. JEC/201/2019/VOL.I/25 Nushe Bus, Resources Nig Ltd 5,874,753.15 Cabinet office 8 weeKs
230 17/12/2019
Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 38
at Garin Malam Ali in Malammadori Constituency. JEC/225/2019/VOL.I/25 Ramadan Constr Nig Ltd 1,961,522.85 Cabinet office 8 weeks
231 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 17
at Kaho, K/Malam Yahya Basirka and Sabalari in Fagam Constituency, Gwaram Local
Government Area. JEC/210/2019/VOL.I/25 Ramadan Constr Nig Ltd 5,877,322.53 Cabinet office 8 weeks
232 11/12/2019
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency
Projects) Lot-18 at Aduwa in Kafin Hausa Constituency. JEC/130/2019/VOL.I/7 Mai Mai Blocks Ind. Nig. Ltd 3,111,654.55 Min of Education 9 weeks
233 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-2 at Kaute , Waje, Gurfai, Gangara, Kurta Fulani G. M/Jadi and Indurkuba Fulani
Arewa in Babura Constituency JEC/171/2019/VOL.I/20 Mufabamex Concept Ltd 3,687,075.00 Min of Water Resources 12 weeks
Bal.C/F 7,082,272,595.52
15
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 7,082,272,595.52
234 17/12/2019
Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency
projects) Lot-53 at Sabon Layi K/kudu Iggi in B/kudu Constituency. JEC/239/2019/VOL.I/25 Modang Invest. Ltd. 1,954,613.85 Cabinet Office 8 weeks
235 17/12/2019
Completion/Renovation of 1no. Daily prayer mosques (2019 first quarter constituency
projects) Lot-92 at Turkushawa in Sule Tankarkar Constituency. JEC/268/2019/VOL.I/25 Modang Invest. Ltd. 2,625,238.18 Cabinet Office 8 weeks
236 17/12/2019
Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot-
68 at Malam Baki in Gagarawa Constituency. JEC/249/2019/VOL.I/25 AMM Manzo Nig Ltd 10,518,579.38 Cabinet office 12 weeks
237 17/12/2019
Completion/Renovation of 2No. Daily prayer Mosques (2019 first Quarter Constituncy
projects) Lot-54 at Takur site Layin Yan Kosai and Masajid Matawalle Old Government House
Dutse in Dutse Constituecy. JEC/240/2019/VOL.I/25 Modang Investment Limited 5,143,163.38 Cabinet office 8 weeks
238 17/12/2019
Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot-
69 at Mai-Aduwa in Gagarawa Constituency. JEC/250/2019/VOL.I/25 Modang Investment Limited 10,518,579.38 Cabinet office 8 weeks
239 17/12/2019
Contr. of Wall Fence (2019 first quarter Constituecy projects) Lot- 81 at Dagacheri Juma'at
Prayer Mosque in Birniwa Constituecy. JEC/259/2019/VOL.I/25 AMM Manzo Nig Ltd 3,429,961.13 Cabinet office 8 weeks
240 17/12/2019
Construction of 1No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 18
at Zango in Gumel Constituency. JEC/211/2019/VOL.I/25 farham synergy con. Ltd 1,958,251.05 Cabinet office 4 weeks
241 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 36
at Fake Cikin Gari, Shuwarin Gari and Miyawo Tudu in Kiyawa Constituency. JEC/223/2019/VOL.I/25 Muhal Global Concept Ltd 5,880,518.55 Cabinet office 8 weeks
242 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 37
at Majiya, Danfusan and Kiyawa cikin Gari in Kiyawa Constituency. JEC/224/2019/VOL.I/25 Muhal Global Concept Ltd 5,880,518.55 Cabinet office 8 weeks
243 27/12/2019
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency
Projects) Lot-5 at Hayatul Islam and Kabal in Jahun Constituency. JEC/109/2019/VOL.I/11 Sasco Multi Serv Nig Ltd 6,218,498.70 Cabinet office 9 weeks
244 17/12/2019
Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 19
at Jugwa A, Z/Nagogo G/sarkin aska, Z/Ta Gabas and Girawa in Gwaram Constituency. JEC/212/2019/VOL.I/25 JAG & H Intergreted Service 7,846,091.40 Cabinet office 8 weeks
245 17/12/2019
Completion/Renovation of 1No.Friday prayer Mosques (2019 first Quarter Constituncy
projects) Lot-89 at Tashar Dankwmbo in Kanya Constituency in Babura LGA JEC/264/2019/VOL.I/25 Deetech Nig. Ltd 2,131,685.87 Cabinet office 8 weeks
246 15/12/2019 Electrification projects at tashena village and shagaryo town in malam madori LGA. JEC/84/2019/VOL.I/8 A.H.F. Global Nig Ltd 49,293,924.94 Min of Works
16 weeks
247 17/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at
Ladin kani in mai gatari Constituency. JEC/253/2019/VOL.I/25 Khairushabah Nig Ltd 7,609,184.60 Cabinet office
8 Weeks
248 17/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 78 at
Jobi in maigatari Constituency. JEC/256/2019/VOL.I/25 Marb Eng. & Multi serv. Ltd 7,720,042.25 Cabinet office
8 Weeks
Bal.C/F 7,211,001,446.73
16
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 7,211,001,446.73
249 17/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 45
at Debe kai, Tinti and Daneji Ringim Constituency. JEC/231/2019/VOL.I/25 Marb eng. & Multi Service Ltd 5,884,568.55 Cabinet office 8 weeks
250 17/12/2019
Construction of 4No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 35
at Kulluru, Harbon Mai Unguwa, katuka cikin Gari and Abarewa in Kiyawa Constituency. JEC/222/2019/VOL.I/25 Muhal Global Concept Ltd 7,834,461.60 Cabinet office 8 weeks
251 11/12/2019
Construction of 3No. Daily prayer Mosques (2019 first Quarter constituency projects) Lot- 31
at Daneri, Kanoke and Kota in Kaugama Constituency. JEC/221/2019/VOL.I/25 Danfatu & sons Nig Ltd 5,884,568.55 Cabinet office 8 weeks
252 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-6 at Kwalam Fulani, Maidu Tsokai, Makwai Fulani, Gidan Haruna Dan Daga,
Sarkin Dare Kofar Shafi'I, Sarkin Dare Fulani, M. Na'annabi Fulani, Garin Dutse Fulani Tale,
Wadi Fulani and Gidan Alasan Nadidi in Gagarawa Constituency JEC/175/2019/VOL.I/21 JAG&H integrated services ltd 7,379,940.00 Min of Water Resources 8 weeks
253 11/12/2019
Constr.of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-29 at
Wadda in Gagarawa Constituency JEC/155/2019/VOL.I/9 Farham Synergy con. Ltd 6,022,800.00 Min of Water Resources 8 weeks
254 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-15
At Dawar Gada in Maigatari Constituency JEC/146/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 Min of Water Resources 8 weeks
255 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-14
At Zuba Barkono in Guri Constituency JEC/145/2019/VOL.I/9 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks
256 11/12/2019
Constr.of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-12
At Madamuwa in Guri Constituency JEC/143/2019/VOL.I/9 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks
257 17/12/2019
Construction of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot-
76 at Dankumbo in Maigatari Constituency. JEC/254/2019/VOL.I/25 Allah Abin Dogaro Nig Ltd 14,500,005.00 Cabinet office 12 Weeks
258 12/12/2019 Mainatinance and Rehabilitation of some Failed Sections along Kazaure - Roni Road JEC/197/2019/VOL.I/8 Retercha Cmp. Nig Ltd 98,528,040.30 Min of Works 16 weeks
259 11/12/2019
Constr. Of JSS Science each (2019 first quarter phase II constituency projects) LOT-17 at
Gumel and Garin Barka in Gumel constituency. JEC/129/2019/VOL.I/7 Farham Synergy con. Ltd 29,908,200.00 Cabinet office 18 Weeks
260 17/12/2019
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-44 at
Kwai Kwayu, Kagadama and Gagarawa in Ringim constituency. JEC/230/2019/VOL.I/25 Marb eng. & Multi Service Ltd 5,884,568.55 Cabinet office 8 Weeks
261 27/11/2019
Constr of Wall fence at Jigawa College of Remedial and Advance Studies (JICORAS) Babura,
Lot-2 (3rd & 4th Qtr. 2019 Capital Projects) JEC/113B/2019/VOL.I/10 Ngaloma Constr. Co. Ltd. 131,969,392.51 Min of Education 24 weeks
262 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-11 at
Unguwar Gabas in Guri Constituency. JEC/142/2019/VOL.I/10 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks
263 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-5
atGeneral Hospital in Birniwa Constituency. JEC/138/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 Min of Water Resources 8 weeks
264 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-6 at
Kazura in Birniwa Constituency. JEC/139/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00 Min of Water Resources 8 weeks
Bal.C/F 7,560,889,431.79
17
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 7,560,889,431.79
265 11/12/2019
Constr of Solar Powered Water Supply Scheme Constituency Project (2019 phase 1) Lot-13 at
Bodala in Guri Constituency. JEC/144/2019/VOL.I/9 A.Y.H Invest. Co. Nig. LTD. 6,014,715.00 Min of Water Resources 8 weeks
266 17/12/2019
Constr of 1no. Friday prayer mosques (2019 first quarter constituency projects) Lot-77 at Lallashi in
Maigatari Constituency. JEC/255/2019/VOL.I/25 Marb Eng & Multi Serv. Ltd. 7,833,599.56 Cabinet office
8 Weeks
267 6/12/2019
Conversion of Motorized Water Supply Scheme to Solar Powered and Rehabilitation of
Existing Solar Schemes at College of Education Gumel JEC/122/2019/VOL.I/6 SIMS Global Resources 29,243,441.00 Min of Water Resources 8 weeks
268 27/11/2019
Constr of Admin Block at Jigawa College of Remedial and Advance Studies (JICORAS)
Babura, Lot-1 (3rd & 4th Qtr. 2019 Capital Projects) JEC/113A/2019/VOL.I/10 Ngaloma Constr. Co. Ltd. 83,365,963.69 Min of Education 24 weeks
269 7/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 76 at
Ladin Kani in Maigatari Constituency. JEC/253/2019/VOL.I/26 Nadada Venture Nig. Ltd 7,609,184.60Cabinet office
8 Weeks
270 17/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 78 at
Jobi in Maigatari Constituency. JEC/256/2019/VOL.I/26 Nadada Venture Nig. Ltd 7,720,042.25Cabinet office
8 Weeks
271 27/11/2019
Constr. Of Gate House and Toilet at Jigawa Colege od Remedial and advance Studies
(JICORAS) Babura, Lot- 3 (3rd and 4th Quarter 2019 Capital Project) JEC/114/2019/VOL.I/10 Al-sabur Global Nig. Ltd 39,190,677.39Min. of Education
24 Weeks
272 17/12/2019
Costr.of 2No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 88 at
Duzau and Danyayi in Kanya Constituency. JEC/265/2019/VOL.I/25 Deetech Nig. Ltd 7,029,877.90Cabinet office
8 Weeks
273 17/12/2019
Constr. Of 4no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-29 at
Karfawa, Kanawa, Adigul and Balladar Kanya constituency in Babura LGA. JEC/219/2019/VOL.I/25 Deetech Nig. Ltd 7,824,104.04Cabinet office
8 Weeks
274 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-16
At Dangwabro in Maigatari Constituency JEC/147/2019/VOL.I/9 A.S.Maifata Gen. EntP. Ltd 6,015,765.00Cabinet office
8 Weeks
275 17/12/2019
Constr. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-39 at
Kkama and Kwanar Duniya in Maigatari constituency JEC/226/2019/VOL.I/25 Marb eng. & Multi service Nig Ltd 3,908,555.70Cabinet office
8 Weeks
276 24/12/2019
Constr. Of 1No. Block of 2-Laboratories at GGDSS Roni (2nd Quarter 2019 Constituency
Project) Lot-1 JEC/295/2019/VOL.I/8 Manhaf Global Constr Nig Ltd 33,552,607.41min. of education
12 weeks
277 24/12/2019
Construction of additional block of 3 classrooms each at kondiko, GGASS Binin kudu, GDSS
kwarko, GDSS kiyako, GDSS sabon gari takanebu and GDSS galamawa across the state JEC/294/2019/VOL.I/7 Babandoki Gen. Enterp Nig Ltd 67,198,406.92
min. of education
12 weeks
278 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-47
At maruta in gwaram Constituency JEC/166/2019/VOL.I/9 farham synergy con. Ltd 6,022,800.00Min. of Water Resouces
8 Weeks
279 17/12/2019
Constr. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-46 at
ruwan garai and dansure tasha in roni constituency JEC/232/2019/VOL.I/25 Na'ayi Resources Nig Ltd 3,919,811.70 Cabinet office
8 Weeks
280 17/12/2019
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-12 at
gabari, machiba and shagawa in bulangu constituency JEC/206/2019/VOL.I/25 Kawu Nigeria Ltd 5,567,369.55 Cabinet office
8 Weeks
281 17/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 80 at
Kaki mai wando in Roni Constituency. JEC/258/2019/VOL.I/25 Na'ayi Resources Nig Ltd 9,527,340.25 Cabinet office
8 Weeks
Bal.C/F 7,892,433,693.75
18
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 7,892,433,693.75
282 17/12/2019
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-14 at
kwarin bulama, S/garin bulangu, mandamari sabuwa in bulangu constituency JEC/208/2019/VOL.I/25 Kawu Nigeria Ltd 5,842,273.05
Cabinet office
8 Weeks
283 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE 1) LOT-25
At Fagoji in Dutse Constituency JEC/151/2019/VOL.I/9 JAG & H Interg. Service 6,021,015.00 Min. of Water Resouces
8 Weeks
284 11/12/2019
Constr. Of watar collection point 2019 first quarter constituency project Lot 20 at zazzana,
mida, and lafiya in gwaram constutuency JEC/191/2019/VOL.I/20 farham synergy con. Ltd 3,758,997.00 Min of Water resource
8 weeks
285 17/12/2019
Renov. Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-84 at
buro and fadi gurje in fagam constituency JEC/262/2019/VOL.I/25 Pullad Global Consultant Ltd 2,503,688.50 Cabinet office
8 Weeks
286 27/11/2019
Constr, of 2No. Block of 2 Classroom islamiyya Each (2019 first Quarter Constituency
Projects) Lot-14c at harazimiyya islamiyya in hadejia Constituency. JEC/107/2019/VOL.I/11 Alh. Umaru Babandoki Nig Ltd 8,055,821.00 Min. of Education
8 weeks
287 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-26
At Kulasa in Dutse Constituency JEC/152/2019/VOL.I/9 JAG & H Interg. Service 6,021,015.00 Min of Water resource
8 Weeks
288 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-27
At Kwaimawa in Dutse Constituency JEC/153/2019/VOL.I/9 JAG & H Intergreted Service 6,021,015.00 Min of Water resource
8 Weeks
289 11/12/2019
Constr. of Solar Powered Water Supply Scheme Constituency Project (2019 PHASE I) LOT-28
At Tabobo in Dutse Constituency JEC/154/2019/VOL.I/9 JAG & H Intergreted Service 6,021,015.00 Min of Water resource
8 Weeks
290 17/12/2019
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-11 at
turaka, gandu and K/bulama Waek in bulangu constituency JEC/205/2019/VOL.I/25 Kawu Nigeria Ltd 5,865,605.55 Cabinet office
8 Weeks
291 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-29 at gangawa, sabara, ruwan dawa, kulleran, ganwa fulani, fanisau, tazara
sabon gida, tula, majiga, harbo, dina, kamai gitsira, dogawa gabashi, bayan kotun cikin gari,
gundin sabon gida and yamma in jahun Constituency JEC/187/2019/VOL.I/20 Sasco Multi Serv Nig Ltd 11,791,752.00
Min. of Water Resouces
14 Weeks
292 11/11/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-12 at sabuwar jawo (sabaru ward), fulanin ballami (dandi ward), K/Mal. Ali
headmaster (gada ward), K/alta makeri (gada ward) and makabarta gabas (gada ward) in JEC/179/2019/VOL.I/20 Yanduna Venture Nig Ltd 3,686,287.50
Min. of Water Resouces
8 Weeks
293 27/12/2019
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Constituency
Projects) Lot-5 at hayatul islam and kabal in Jahun Constituency. JEC/109/2019/VOL.I/11 Sasco Multi Serv Nig Ltd 6,218,492.70 Min. of Education
8 weeks
294 11/12/2019
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency
Projects) Lot-2 at rukumi in malam madori Constituency. JEC/134/2019/VOL.I/7 Mai Mai Blocks Ind. Nig. Ltd 3,473,316.00 Min. of Education
8 weeks
295 6/12/2019
Constr. Of 1No. Block of science Laboratory at GDSS Dan sure in roni LGA (2019 MOEST
capital Project) Lot-1 JEC/123/2019/VOL.I/6 Na'ayi Resources Nig Ltd 9,561,049.80 Min. of Education
8 weeks
296 17/12/2020
Completion /Renovation of 2no. Friday prayer mosques (2019 first qtrs. Constituency
projects) Lot-84 at Buro and Fadi Gurje in Fagam Constituency. JEC/262/2019/VOL.I/25 Pullad Global Consultant 2,503,688.50 Cabinet Office
8 weeks
297 17/12/2020
Completion /Renovation of 2no. Friday prayer mosques (2019 first qtrs. Constituency
projects) Lot-83 at JIBWIS Fagam and Dangulan in Fagam Constituency. JEC/261/2019/VOL.I/25 Pullad Global Consultant 4,668,587.70 Cabinet Office
8 weeks
Bal.C/F 7,984,447,313.05
19
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 7,984,447,313.05
298 17/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 74 at gwalerima in
kaugama Constituency. JEC/251/2019/VOL.I/25 Danfatu & sons Nig Ltd 8,200,007.27Cabinet office
12 weeks
299 17/12/2019
Completion./Renovation Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-
56 at magarya, sabuwar unguwa and GGSS Garki in Garki constituency JEC/242/2019/VOL.I/25 MMZ Garki Gen contractor 4,814,329.08Cabinet office
8 Weeks
300 17/12/2019
Completion./Renovation Of 2no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-
52 at argina and yartsaka in auyo constituency JEC/238/2019/VOL.I/25 MMZ Garki Gen contractor 7,293,833.85Cabinet office
8 Weeks
301 17/12/2019
Costr.of 1No. Friday prayer Mosques (2019 first Quarter constituency projects) Lot- 74 at Ubba in
kaugama Constituency. JEC/252/2019/VOL.I/25 Danfatu & sons Nig Ltd 8,200,007.27Cabinet office
12 weeks
302 17/12/2019
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-13 at bujaye,
makera mashawai in bulangu constituency JEC/207/2019/VOL.I/25 Kawu Nigeria Ltd 5,784,568.58Cabinet office
8 Weeks
303 27/12/2019
Constr. Administrative block at jigawa college of remedial and advance studies (JICORAS) Babura, Lot-1
(3rd & 4th quarter 2019 capital projects) JEC/113A/2019/VOL.I/10 Ngaloma Constr Nig Ltd 83,365,963.69Min. of Education
24 Weeks
304 17/12/2019
Constr. Of 4no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-51 at dankama,
karkanai, burji fulani and kuda in yankwashi constituency JEC/237/2019/VOL.I/25 Granitoids Engr Services ltd 7,836,430.04Cabinet office
8 Weeks
305 11/12/2019
Constr of 5No. Hand Pumps Boreholes Water Supply Schemes Constituency projects (2019 First
Quarter) Lot-25 at kanya abbba, dan yayin daurawa, kagadama, walawa and shantake in kanya babba
Constituency JEC/196/2019/VOL.I/20 Deetech Nig. Ltd 5,100,375.00
Min. of Water Resouces
8 weeks
306 11/12/2019
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter Phase II Constituency Projects)
Lot-21 at Ung. Kalgo, Kuda Walawa and Bade Fulani in Yankwashi Constituency. JEC/133/2019/VOL.I/7 Granitoids Engr Services ltd 9,339,771.12 Min. of Education
8 weeks
307 11/12/2019
Constr of Hand Pump Boreholes Water Supply Schemes Constituency projects (2019 First Quarter) Lot-8
at mai dashi, Idi gwamna, unguwar malam, rigar lamido, adiyani islamiyya, dagana Nato, daba, dirba,
rigar malam wuri, yalwa tsangaya, goni garin una, askandi arinjasko, rigar wakilin dajjo lafiya, rigar
babare, and rigar duka maza in guri Constituency JEC/176/2019/VOL.I/20 AYH Intg. Serv. Ltd 10,331,489.00
Min. of Water Resouces
8 weeks
308 24/12/2019
Ren. of Windstorm Damaged Structures at GSTC Karkarna, SSS K/Hausa and GSSS Jahun across the state
(2019 MOEST Capital Projects) JEC/313/2019/VOL.I/7 Allah Abin Godiya Nig Ltd 35,803,002.26Min. of Education
8 weeks
309 17/12/2019
Constr of 4no. Daily prayer mosques (2019 first quarter constituency projects) Lot-19 at Jugwa A.,
Z/nagogo G/Sarkin Aska, Z/Ta gabas and Girawa in Gwaram Constituency. JEC/212/2019/VOL.I/25 JAG&H Integ. Services Ltd 7,846,091.40Cabinet office
8 weeks
310 17/12/2019
Constr. of 3no. Daily Prayer Mosques (2019 first quarter constituency projects) LOT-20 at abena,
babban gidan nahuce and tsangwanwa in gwaram constituency JEC/213/2019/VOL.I/25 JAG & H Intergreted Service 5,880,512.55 Cabinet office
8 Weeks
311 27/11/2020
Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr. 2019 constituency project)
at Babura k/Arewa and Garin Baki in Babura Constituency. JEC/102/2019/VOL.I/11 Mufabamex Concept Ltd. 6,391,877.10 Min of Education
7 weeks
312 11/12/2020
Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr. Phase II 2019 constituency
project) at Ung. Kalgo, Kuda Walawa and Bade Fulani in Yankwashi Constituency. JEC/133/2019/VOL.I/7 Granitoids Eng Serv. Ltd. 9,339,771.12 Min of Education
12 weeks
313 17/12/2020
Completion /Renovation of 3no. Daily prayer mosques (2019 first qtrs. Constituency projects) Lot-56 at
Magarya, Sabuwar Unguwa and GGSS Garki in Garki Constituency. JEC/242/2019/VOL.I/25 MMZ Garki Gen.Constr Ltd. 4,814,329.08 Cabinet Office
8 weeks
314 17/12/2020
Constr of 2no. Daily prayer mosques (2019 first qtrs. Constituency projects) Lot-46 at Ruwan Garai and
Dansure Tasha in Roni Constituency. JEC/232/2019/VOL.I/25 Na'ayi Resources Ltd. 3,919,811.70 Cabinet Office
8 weeks
Bal.C/F 8,208,709,483.16
20
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 8,208,709,483.16
GOODS
315 16/4/2019 Procurement of Assorted Submersible pumps Across the State FGPC/28/2019/VOL.I/8 Umar Aliyu & Sons Nig Ltd 19,479,796.87 Ministry of Water Res 8 Weeks
316 28/06/2019
Supply of Alternative Solar Power Energy and Solar Street light at Jigawa State Institute of
Information Technology Kazaure JEC/41/2019/VOL.I/12 Ngaloma Construction 62,121,465.00 Ministry of Education 12 weeks
317 20/06/2019 Purchase of 2No. Fairly used vechicle JEC/38/2019/VOL.I/4 Modang investment Ltd 39,900,000.00 Government House 2 weeks
318 16/4/2019 Procurement of 2No. 200KVA Perkins Generating Set for Kazaure and Birnin Kudu Zone FGPC/29/2019/VOL.I/8 Limis Brothers & Co 28,619,712.07 Ministry of Water Res 8 Weeks
319 16/4/2019
Supply and Installation of inytegrated standalone Solar Powered Streetlight at buji (150
Units), Basirka/Digijin (120 Units), Kudai (100 Units), balanngu-Sarawa (100 Units) Garin
Gabas (160 Units) and Biriwa Tasha (100 units) Total 710 units (Lot-1) FGPC/24/2019/VOL.I/8 Arrayan Ventures Global 403,649,600.00 Ministry of Works 14 weeks
320 12/2/2019
Supply and Installation of inytegrated standalone Solar Powered Streetlight atGada (150
units) Dandi (100 unit) Amaryawa (100 units) and Yankwashi (80 unit) total 430 units (lot-3) FGPC/4/2019/VOL.I/28 Ngaloma Construction 256,684,050.00 Min of Works & Transport 14 weeks
321 3/5/2019
Supply and Installation of 52No. Standalone Solar Integrated Streetlight (Phase-II)
at the Jigawa State College of Islamic & Legal Studies Ringim JEC/48/2019/VOL.I/7 Sims Global Resources 32,215,050.00 Ministry of Education 4 weeks
322 11/7/2019
Supply and Distribution of Science text Books and Teachers Guide for Senior Secondary
Schools Across the State JEC/43/2019/VOL.I/6 Learn Africa Plc 49,949,800.00 Ministry of Education 6 weeeks
323 31/7/2019 Supply & Installation of Solar streetlight at Emir's Drive, Dutse JEC/47/2019/VOL.I/7 Arrayyan Global Vent 17,319,500.00 Min of Works 8 weeks
324 31/7/2019
Supply & Installation of Stand alone solar powered streetlight at Government Girls Arabic
Secondary School Babura, Government Girls Unity Secondary School Gwaram & Computer
Girls Secondary School Roni. JEC/48/2019/VOL.I/8 Sims Global Res 60,780,300.00 Min of Works 12 weeks
325 19/9/2019
Procurement and Installation of Furniture at the Official Residence of His Excellency, the
Deputy Governor at Dutse JEC/60/2019/VOL.I/6 Aimim Consult Nig. Ltd. 34,825,680.00 Cabinet Office 8 weeks
326 3/9/2019
Procurement and Sewing of 30,000 sets of School Uniforms to Senir Secondary Schools acros
the state JEC/59/2019/VOL.I/6 313 Textile Nig Ltd. 79,980,000.00 Min of Education 12 weeks
327 11/9/2019
Supply and Installations of Integrated Standalone Solar Powered Streetlights at GGASS Sule
Tankarkar, GGSSS Taura and Model Boarding Primary School, Gumel JEC/58/2019/VOL.I/8 SIMS Nigeria Limited 75,380,550.00 Min of Works & Transport 12 weeks
328 12/2/2019
Supply and Installations of Integrated Standalone Solar Powered Streetlight at Hammado-
Gagarawa (200 Unit) Bosuwa (100 Unit) iri (100 Units) Manga-Takwasa (120 Unit) and
Unguwar Gawo-Batali-Kuzunzumi-Balarabe (200 unit) Total 720 Units (Lot 2) FGPC/3/2019/VOL.I/28 SIMS NIGERIA LTD 430,360,875.00 Min of Works & Transport 14 Weeks
329 23/12/2020
Feeding of 597 Boarding School students at MBPS/JSS Kazaure & 35 students at Intel
Disability Kazaure in Kazaure LGA (2019 MOEST Capital Projects) Lot-40. JEC/3514/2019/VOL.I/7 Umar Aliyu & Sons 23,888,538.40 Min of Education 40 weeks
Bal.C/F 9,823,864,400.50
21
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 9,823,864,400.50
GOODS
330 16/10/2019
Procurment of Medical Drugs, ICT and Sicbay Equipment for Jigawa Academy for the Gifted,
Bamaina JEC/86/2019/VOL.I/6 IMAM Ahmed Nig Ltd. 4,639,345.25 Min of Education 2 weeks
331 9/12/2019 Purchase of 15no. Vehicles JEC/125/2019/VOL.1/3 CIG motor Company Nig Ltd 169,533,611.20 Govt House 2 weeks
332 11/12/2019
Supply and installation of medical equipment to the 25No. Newly constructed basic health
clinic across the state. JEC/304/2019/VOL.1/7 Dangata mem. inv. Ltd 95,423,350.00 Min of Health 8 weeks
333 24/12/2019
Supply and installations of 100-units integrated standalone solar powered streetlight at
babaldu town in Birnin Kudu LGA JEC/299/2019/VOL.1/7 Ar-rayyan ventures global ltd 55,786,500.00 Min of Works 12 weeks
334 24/12/2019
Supply and installations of 150-units integrated standalone solar powered streetlight at
Garun gudunya and garin gambo towns in babura and gumel LGAs JEC/300/2019/VOL.1/7 SIMS Nig. Ltd 81,328,800.00 Min of Works 12 weeks
335 23/12/2019
Feeding of 1,003 Boarding school students at GGSSS Taura in Taura LGA (2019 MOEST Capital
projects) Lot-26 JEC/337/2019/VOL.I/17 Dankwara Maijimina Gen. Entp. 37,911,714.80 Min of Education 40 weeks
336 18/12/2019
Procurement and installation of Furniture at the official Residence of His Excellency Deputy
Governor Jigawa state in Dutse (2019 Capital Projects) Additional works JEC/60/2019/VOL.1/18 AIMM Consult Nig Ltd 8,750,175.00 Deputy Governor Office 4 weeks
337 23/12/2019
Feeding of 433 Boarding school students at GJSSS Guri in Guri LGA (2019 MOEST Capital
projects) Lot-28 JEC/339/2019/VOL.I/17 Baradugum Gen. Entp. 16,366,540.00 Min of Education 40 weeks
338 15/10/2019
Supply and Installations of Integrated stadalone Solar Powered Streetlight at GGASS
Birniwa, GGASS Kaugama, Science of Deef Hadejia and JSSS Guri JEC/85/2019/VOL.1/18 SIMS Global Resources 77,002,800.00 Min of Works 12 weeks
339 3/12/2019
Supply and installation of 150-units integrated stand alone powered streetlights at marke
town in kaugama LGA JEC/121/2019/VOL.I/7 Sims Global Resources Nig Ltd 82,797,750.00 Min of Works
12 weeks
340 24/12/2019
Supply of Science Laboratories Equipment for Distribution to Senior Sec School Across the
state (2019 MOEST capital project) JEC/318/2019/VOL.I/9 Aldan Project Ltd 29,491,628.72 Cabinet office
8 weeks
341 24/12/2019
Procurement of science laboratory equipments for distribution to 9No. Senior secondary
schols upgraded to science centre of exlence core-2 at GGUSS Malammadori, GDSS G/Gabas,
GGSS garki, GDSS gwuiwa, GUSS aujara, GUSS maigatari, GUSS tsohuwar gwaram, GC birnin
Kudu, and GUSS basirka accross the state JEC/293/2019/VOL.I/9 Quest Ventures Ltd 81,037,103.92
Min. of Education
8 weeks
342 23/12/2019
Feeding of 970 Boarding school students at GGSS S/tankarkar in S/tankarkar LGA (2019
MOEST Capital projects) Lot-24 JEC/335/2019/VOL.I/17 Hassan Habu T. Gen. Entp. 39,182,001.60 Min of Education 40 weeks
343 23/12/2019
Feeding of 790 Boarding school students at GSTC Hadejia in Hadejia LGA (2019 MOEST
Capital projects) Lot-12 JEC/323/2019/VOL.I/17 A.H.M. Global Ventures 29,860,672.80 Min of Education 40 weeks
Bal.C/F 10,632,976,393.79
22
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 10,632,976,393.79
GOODS
344 23/12/2019
Feeding of 287 Boarding School students at bamaina academy in birnin kudu LGA (2019
MOEST Capital Projects)LOT-39 JEC/350/2019/VOL.I/17 Kabiru na Malam Nig Ltd 40,204,006.00 min. of education
40 weeks
345 23/12/2019
Feeding of 1031 Boarding school students at GGASS Danzomo in Sule tankarkar Local
Government Area (2019 MOEST Capital project) Lot-25 JEC/336/2019/VOL.I/17 Salisu & Isah Gen. Entp. 38,969,984.00 Min of Education 40 weeks
346 23/12/2019
Feeding of 1,762 Boarding school students at GUSS Maigatari in Maigatari Local Government
Area (2019 MOEST Capital project) Lot-20 JEC/331/2019/VOL.I/17 Shabarawa Gen. Enterpr 66,600,638.40 Min of Education 40 weeks
347 23/12/2019
Feeding of 426 Boarding school students at Science secondary school kanya Babba in Babura
Local Government Area (2019 MOEST Capital project) Lot-41. JEC/352/2019/VOL.I/17 H.A.U. Gen. enterp. 16,102,084.40 Min of Education 40 weeks
348 23/12/2019
Feeding of 635 Boarding school students at MBPS/JSS Ringim in Ringim Local Government
Area (2019 MOEST Capital project) Lot-35 JEC/346/2019/VOL.I/17 H.A.U. Gen. enterp. 23,875,921.20 Min of Education 40 weeks
349 23/12/2019
Feeding of 3378 Boarding school students at GUSS Ringim in Ringim Local Government Area
(2019 MOEST Capital project) Lot-21. JEC/332/2019/VOL.I/17 H.A.U. Gen. enterp. 127,667,604.80 Min of Education 40 weeks
350 23/12/2019
Feeding of 761 Boarding school students at SSS Lautai in Gumel Local Government Area
(2019 MOEST Capital project) Lot-8. JEC/319/2019/VOL.I/17 Bakar Kasa Gen. Enter. 28,764,521.60 Min of Education 40 weeks
351 23/12/2019
Feeding of 1,030 Boarding school students at SAIS Hadejia Local Government Area (2019
MOEST Capital project) Lot-13 JEC/324/2019/VOL.I/17 MS Amar & son enterp 38,932,269.60 Min of Education 40 weeks
352 23/12/2019
Feeding of 753 Boarding school students at GGCSS Roni in Roni Local Government Area (2019
MOEST Capital project) Lot-23 JEC/334/2019/VOL.I/17 Talba Gen. Enterp 28,462,134.80 Min of Education 40 weeks
353 23/12/2019
Feeding of 1319 Boarding school students at GUSS Roni and 170 tsangaya school students at
Gwiwa in Roni and Gwiwa Local Government Area (2019 MOEST Capital projects) Lot-22 JEC/333/2019/VOL.I/17 Adon Sale Bandu 57,699,603.60 Min of Education 40 weeks
354 23/12/2019
Feeding of 1572 Boarding school students at GUSS Fantai and 279 students at school for deaf
in hadejia Local Government Area (2019 MOEST Capital project) Lot-11 JEC/322/2019/VOL.I/17 Alh. Muhammad Kwalli Gen. 69,924,690.40 Min of Education 40 weeks
355 23/12/2019
Feeding of 1703 Boarding school students at GUSS Malammadori in Malammadori Local
Government Area (2019 MOEST Capital project) Lot-37 JEC/348/2019/VOL.I/17 AG Isyaku Gen Ent 64,366,351.60 Min of Education 40 weeks
356 23/12/2019
Feeding of 445 Boarding school students at GSTC Karkarna in Yankwashi Local Government
Area (2019 MOEST Capital project) Lot-27 JEC/338/2019/VOL.I/17 Malabai Gen Ent 16,820,252.40 Min of Education 40 weeks
357 23/12/2019
Feeding of 580 Boarding school students at GJSSS Karkarna in Yankwashi Local Government
Area (2019 MOEST Capital project) Lot-29 JEC/340/2019/VOL.I/17 Malabai Gen Ent 21,923,025.60 Min of Education 40 weeks
358 23/12/2019
Feeding of 635 Boarding school students at MBP/JSS Gumel and 60 Tsangaya school students
at Mai Aduwa in Gumel Local Government Area (2019 MOEST Capital project) Lot-32 JEC/343/2019/VOL.I/17 Wangara Agent Gen Ent. 26,406,169.60 Min of Education 40 weeks
Bal.C/F 11,299,695,651.79
23
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 11,299,695,651.79
GOODS
359 23/12/2019
Feeding of 453 Boarding school students at GSTC Ringim in Ringim Local Government Area
(2019 MOEST Capital project) Lot-36 JEC/347/2019/VOL.I/17 Maidala Gen. Ent. 17,122,640.00 Min of Education 40 weeks
360 23/12/2019
Feeding of 2,254 Boarding school students at GGUSS Gwaram in Gwaram Local Government
Area (2019 MOEST Capital project) Lot-9 JEC/320/2019/VOL.I/17 Gobirawa kwari Gen. Ent. 84,333,796.80 Min of Education 40 weeks
361 23/12/2019
Feeding of 1231 Boarding school students at GGASS birniwa in birniwa Local Government
Area (2019 MOEST Capital project) Lot-4 JEC/308/2019/VOL.I/17 A.I. Maiso Gen. Ent. 46,529,720.00 Min of Education 40 weeks
362 23/12/2019
Feeding of 728 Boarding school students at GGJSSS Miga in Miga Local Government Area
(2019 MOEST Capital project) Lot-31 JEC/342/2019/VOL.I/17 Yusif Garba Miga Gen. Ent. 27,511,020.00 Min of Education 40 weeks
363 23/12/2019
Feeding of 1,380 Boarding School students at GUSS Malam Madori LG (MOEST Capital
Projects)LOT-19 JEC/330/2019/VOL.I/17 SawIra gen enterprises 52,161,681.60 Min of Education 40 weeks
364 23/12/2019
Feeding of 1,122 Boarding School students at GSS Aujara in Jahun LG (MOEST Capital
Projects)LOT-15 JEC/326/2019/VOL.I/17Adamu Ibrahim Aujara Gen.
Entp. 42,687,419.20 Min of Education 40 weeks
365 23/12/2019
Feeding of 621 Boarding School students at SAIS Fatara in Dutse LG (MOEST Capital
Projects)LOT-6 JEC/310/2019/VOL.I/17 Baita Daushanga Gen. Entp. 23,394,510.80 Min of Education 40 weeks
366 23/12/2019
Feeding of 1,233 Boarding School students at MBPS/JSS KILA Gwaram LG (MOEST Capital
Projects)LOT-42 JEC/353/2019/VOL.I/17 Baita Daushanga Gen. Entp. 46,605,328.40 Min of Education 40 weeks
367 23/12/2019
Feeding of 882 Boarding School students at GUSS Basirka Gwaram LG (MOEST Capital
Projects)LOT-10 JEC/321/2019/VOL.I/17 Baita Daushanga Gen. Entp. 33,333,159.20 Min of Education 40 weeks
368 23/12/2019
Feeding of 554 Boarding School students at MBP/JSS Guri, 58 Tsangaya School students at
Tarabu and 60 Tsangaya School students at Birniwa in Guri and Birniwa LG (2019 MOEST
Capital Projects)LOT-34 JEC/345/2019/VOL.I/17 GMA Kadira Gen. Entep 25,893,694.00 Min of Education 40 weeks
369 23/12/2019
Feeding of 940 Boarding School students at science secondary school (SSS) Kafin Hausa in
Kafin Hausa LG (MOEST Capital Projects)LOT-16 JEC/327/2019/VOL.I/17 Zango Gen. Entp. 35,530,420.80 Min of Education 40 weeks
370 23/12/2019
Feeding of 467 Boarding School students at GSTC Birnin kudu in Birnin kudu LG (MOEST
Capital Projects)LOT-3 JEC/307/2019/VOL.I/17 Baita Daushanga Gen. Entp. 17,651,815.60 Min of Education 40 weeks
371 23/12/2019
Feeding of 1,077 Boarding School students at GGASS Kaugama in Kaugama LG (MOEST
Capital Projects)LOT-17 JEC/328/2019/VOL.I/17 Danbiri Global Ventures 40,709,000.80 Min of Education 40 weeks
Bal.C/F 11,793,159,858.99
24
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 11,793,159,858.99
GOODS
373 23/12/2019
Feeding of 639 Boarding School students at MBPS/JSS Bulangu in Kafin Hausa LG (MOEST
Capital Projects)LOT-33 JEC/344/2019/VOL.I/17Hussaini Ahmed bookshop Gen
Entp. 24,027,126.40 Min of Education 40 weeks
374 23/12/2019
Feeding of 920 Boarding School students at GGUSS Kazaure in Kazure LG (MOEST Capital
Projects)LOT-18 JEC/329/2019/VOL.I/17 Haru jika Gen. Entp. 34,767,096.00 Min of Education 40 weeks
375 23/12/2019
Feeding of 2309 Boarding School students at GGSS Garki in Garki LGA (MOEST Capital
Projects)LOT-7 JEC/311/2019/VOL.I/17 MMZ Garki Gen Const 87,276,300.00 Min of Education 40 weeks
376 23/12/2019
Feeding of 674 Boarding School students at MBPS/JSS Kudai in Dutse LGA (MOEST Capital
Projects)LOT-43 JEC/354/2019/VOL.I/17 Sabuwar Kuka Gen Enterp 25,476,067.60 Min of Education 40 weeks
377 23/12/2019
Feeding of 788 Boarding School students at GJSSS Aujara in Jahun LGA (2019 MOEST Capital
Projects)LOT-30 JEC/341/2019/VOL.I/17 Na'ima and Fati Gen. Entp. 29,785,076.00 Min of Education 40 weeks
378 23/12/2019
Feeding of 209 Boarding school students at Tsangaya school gantsa in bujiLocal Government
Area (2019 MOEST Capital project) Lot-38 JEC/349/2019/VOL.I/17 Zai General Ent. 8,762,692.80
Min. of Education
40 weeks
379 23/12/2019
Feeding of 2,416 Boarding school students at GUCSS Dutse in Dutse Local Government Area
(2019 MOEST Capital project) Lot-35 JEC/309/2019/VOL.I/17 Zai General Ent. 91,320,405.20
Min. of Education
40 weeks
380 23/12/2019
Feeding of 1,696 Boarding school students at GUC Birnin kudu in birnin kudu Local
Government Area (2019 MOEST Capital project) Lot-2 JEC/306/2019/VOL.I/17 Muduka General Ent. 64,105,950.80
Min. of Education
40 weeks
381 23/12/2020
Feeding of 1,407 Boarding School students at GGASS Babura in Babura LGA (2019 MOEST
Capital Projects) Lot-1. JEC/305/2019/VOL.I/7 JALGO Integ. Services Ltd. 53,186,214.40
Min of Education
40 weeks
Bal.C/F 12,211,866,788.19
25
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRIES COMP. PERIOD
BAL. B/F 12,211,866,788.19
SERVICES
382 20/3/2019
Commissioning as consultant for the Supervision of the Construction of Kiyawa Township
Roads Phase II (4km) FGPC/140/2012/VOL.I/111 Sadiq Engineering 13,679,571.15 Min of Works 6 months
383 20/3/2019
Commissioning as consultant for the Supervision of the Construction of Chai Chai Tsohuwa
township Roads FGPC/20/2019/VOL.I/4 UGS Consultants 3,949,973.17 Min of Works 6 weeks
384 20/3/2019
Commissioning as Consultant for the Supervision of the construction of Kanya Babba
Township Roads (2.8km) FGPC/59/2017/VOL.I/60 Curves & Straight design 6,056,229.07 Min of Works 6 months
385 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Kazaure-Fanda-
Sabaru-Gallu-Karkarna Feeder Road (16km) FGPC/138/2012/VOL.I/228 UKM Civil Engineering 9,226,965.83 Min of Works 6 months
386 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Hammado-
Dafarantama-Mele-Baikarya-Garin Baki-Kokinami-Liman Mado feeder Roads (32.76km) FGPC/22/2011/VOL.I/179 Hag Engineering 15,959,738.87 Min of Works 6 months
387 20/3/2019
Commissioning as consultant for the supervision of the Construction of Zandam Nagogo
township Roads (2.38km) FGPC/6/2012/VOL.I/III Land Base Engineering 7,629,535.56 Min of Works 6 months
388 20/3/2019
Commissioning as Consultant for the supervision of the Construction of Kaugama - Malam
Madori Feeder Road (19.31km) FGPC/411/2018/VOL.I/21 SIIS Engineering Consult 9,112,024.27 Min of Works 6 months
389 20/3/2019
Commissioning as consultant for the Supervision of the Construction of Guduncin-Aguyaka
Road (4.30km) FGPC/59/2017/VOL.I/56 Curves & Straight design 17,024,414.69 Min of Works 10 months
390 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Kwanar Medi-
Danzomo-Garki Road (29.51km) FGPC/59/2017/VOL.I/54 Curves & Straight design 62,714,754.77 Min of Works 20 months
391 26/3/2019
Commissioning as consultant for the Supervision of the Supply and Installation of
Intergrated Standalone Solar Powered Streetlights at Buji 150 units, Basirka/Digijin 120
Units, Kudai 100 Units, Bulangu-Sarawa 100 units, garin Gabbas 160 units and birniwa Tasha FGPC/21/2019/VOL.I/10 ARDUGAL Engineering Ltd 7,606,368.00 Min of Works 4 months
392 26/3/2019
Commissioning as Consultant for the Supervision of the Supply and Installation of
Integrated Standalone Solar Powered Streetlights at Hammado-Maituruniya-Duhuwa-
Gangar 200 Units, Bosuwa 100 units, Kiri 100 units, Manga-Takwasa 12 units and unguwar
Gawo-Bataki-Kuzunzumi-Balarabe 200 units (Total 720 units) FGPC/22/2019/VOL.I/10 Secwave Nigeria Limited 7,531,315.31 Min of Works 4 months
393 10/4/2019
Commissioning as consultant for the supervision of the construction of sada-Kanawa-
Dankari-Nasarawa-Kuda Feeder Road (11.2km) FGPC/138/2012/VOL.I/248 UKM Engineering Consult 6,889,699.73 Ministry of Works 6 Months
BAL. C/F 12,379,247,378.61
26
S/N DATE PROJECT CONTRACT NO. CONTRACTOR AMOUNT (N) EXECUTING MINISTRY COMP. PERIOD
BAL. B/F 12,379,247,378.61
394 24/5/2019
Commissioning as Consultant for the Training and Technical Support of 250No Senior
Secondary School Teachers on K-Yan Machine for the Facilitation of E-Learning at Senior
Secondary Schools Across the State FGPC/32/2019/VOL.I/8 C-Stemp Construction Skil ls 36,227,761.00 Ministry of Education 6 Month
395 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Birnin Kudu-Zazia-
KwanGwara-Nafadan Warji-Nafadan Kanawa-Marmara-Kadangare-Hirin-Kwatai Nafara
Feeder Road (33 Km) FGPC/29/2011/VOL.I/77 Himma Tech Service & Co 19,415,172.13 Min of Works 10 months
396 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Gumel Township
Roads (Phase III) 4.7Km FGPC/29/2011/VOL.I/75 Himma Tech Service & Co 17,440,289.13 Min of Works 6 months
397 20/3/2019
Commissioning as Consultant for the Supervision of the Re-Construction of Taura-Garki
Road (26.68Km) FGPC/29/2011/VOL.I/73 Himma Tech Service & Co 51,197,948.77 Min of Works 16 months
398 20/3/2019
Commisiioning as Consultant for the Supervision of the Construction of Miga Township
Roads (Phase II) 3.1Km) FGPC/223/2018/VOL.I/32 Apex Design & Associate 13,091,926.38 Min of Works 6 months
399 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Balago-Kadowawa-
Dumadumin Ky-Dumadumin Toka-Auno Road (41.2km) FGPC/223/2018/VOL.I/30 Apex Design & Associate 93,126,261.93 Min of Works 24 months
400 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Jigawar Dan Ali
Township Roads (2.1km) FGPC/97/2013/VOL.I/36Akram Engineering &
Management 7,484,294.27 Min of Works 6 monthd
401 20/3/2019
Commissioning as Consultant for the Supervision of the Construction of Access Roads to
744, Sabuwar Takur and Yalwawa township roads (8.1km) FGPC/59/2017/VOL.I/58 Curves & Straight design 27,603,997.03 Min of Works 10 months
402 26/6/2019
Engagement/Commissioning as Consultant for the reconciliation and recovery of
unremitted pay as you earn (PAYE) of Staff of Federal Government Agencies Residing in
Jigawa State for the period off 2002-2018(8% of N 6,383,001,715.57) JEC/57/2019/VOL.I/6 Henry Young And Co. 563,172,144.01 Min of Finance 6 weeks
403 27/11/2019
Supervision of the construction works at jigawa college of remedials and advance studies
(JICORAS) babura, Lot-6 (3rd and 4th quarters 2019 capital projects) JEC/223/2018/VOL.I/67 Apex Design & Associates 23,537,374.82 Min. of Education
6 months
TOTAL 13,231,544,548.08
27
Ministry of Health
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 General Renov ation/Improv ement w orks at Dutse General Hospital Ummu Khulsum Global Dutse 56,668,862.45 56,668,862.45 56,666,735.62 30/12/2016 16 w eeks 100 Completed
2
Supply and Installation of Solar Powered Lightening System at
Dutse Gen. Hospital SIMS Global Resources Dutse 27,835,303.13 27,835,303.13 27,835,303.13 2/11/2017 8 Weeks 100 Completed
3
Supply and installation of Solar Powered lightening System in
Babura General Hospital. Sims Global Resources Babura 20,984,971.88 20,984,971.88 20,984,971.87 20/12/2017 8 Weeks 100 Completed
4
Supply and installation of Solar Powered lightening System in
GumelGeneral Hospital. Sims Global Resources Gumel 30,263,168.13 30,263,168.13 30,262,168.12 20/12/2017 8 weeks 100 Completed
5
General Renov./Improvement of Auyo Model Primary Health
Care at Auyo town, Auyo LGA. Math Global Investment Auyo 87,354,794.85 87,354,794.85 86,269,610.43 3/9/2018 24 weeks 100 Completed
6
Construction of Prototype Basic Health Care Clinic (Lot-3) at
Kale in Jahun Local Government Area. Baban-Doki General Entp. Jahun 19,816,590.02 19,816,590.02 18,497,752.60 14/11/2018 12 weeks 100 Completed
7
Construction of Prototype Basic Health Care Clinic (Lot-4) at
Harbo Sabuwa in Jahun Local Government Area. Ngloma Constr. Comp. Ltd Jahun 20,061,603.77 20,061,603.77 20,052,221.17 14/11/2018 12 weeks 100 Completed
8
Construction of Prototype Basic Health Care Clinic (Lot-16) at
Gora in Roni Local Government Area. Khanadi Global Links Roni 20,260,338.21 20,260,338.21 20,136,492.07 14/11/2018 12 weeks 100 Completed
9
Construction of Prototype Basic Health Care Clinic (Lot-19) at
Zauma in Gwiwa Local Government Area. Ngloma Constr. Comp. Ltd Gwiwa 20,129,282.23 20,129,282.23 19,170,744.98 14/11/2018 12 weeks 100 Completed
10
Construction of Prototype Basic Health Care Clinic (Lot-21) at
Yola in Gwiwa Local Government Area. Baban-Doki General Entp. Gwiwa 19,899,400.66 19,899,400.66 19,489,949.48 14/11/2018 12 weeks 100 Completed
11
Construction of Prototype Basic Health Care Clinic (Lot-8) at
Hadin in Kaugama Local Government Area. Dangata Memorial Invest. Kaugama 19,495,565.93 19,495,565.93 18,197,951.22 14/11/2018 12 weeks 100 Completed
12
Construction of Prototype Basic Health Care Clinic (Lot-23) at
Dabawa in Babura Local Government Area. Ngloma Constr. Comp. Ltd Babura 19,035,497.45 19,035,497.45 18,038,513.27 14/11/2018 12 weeks 100 Completed
13
Construction of Prototype Basic Health Care Clinic (Lot-1) at
Dundubus in Dutse Local Government Area. ALLAH Abin dogara Nig. Ltd. Dutse 19,725,041.09 19,725,041.09 19,626,682.66 14/11/2018 12 weeks 100 Completed
14
Construction of Prototype Basic Health Care Clinic (Lot-13) at
Chakwaikwaiwa in Taura Local Government Area. Baban-Doki General Entp. Taura 19,683,109.98 19,683,109.98 19,670,756.17 14/11/2018 12 weeks 100 Completed
Balance C/F 401,213,529.78 401,213,529.78
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 401,213,529.78 401,213,529.78
15
Construction of Prototype Basic Health Care Clinic (Lot-17) at
Sankau in Roni Local Government Area. Al-Sabur Global Links Ltd. Roni 19,555,834.00 19,555,834.00 19,534,098.87 14/11/2018 12 weeks 100 Completed
16
Construction of Prototype Basic Health Care Clinic (Lot-18) at
Takurdawa in Roni Local Government Area. Al-Sabur Global Links Ltd. Roni 19,416,248.88 19,416,248.88 19,394,181.48 14/11/2018 12 weeks 100 Completed
17
Construction of Prototype Basic Health Care Clinic (Lot-20) at
Firjin Yola in Gwiwa Local Government Area. Pullad Global Consultant Nig Gwiwa 19,663,657.62 19,663,657.62 19,577,089.86 14/11/2018 12 weeks 100 Completed
18
Construction of Prototype Basic Health Care Clinic (Lot-7) at
Ubba in Kaugama Local Government Area. Nushe Business Resources Kaugama 20,025,983.09 20,025,983.09 19,997,296.20 14/11/2018 12 weeks 100 Completed
19
Construction of Prototype basic Health Care Clinic (Lot-6) at
Mezan in Kafin Hausa L.G.A. Asaka Construction Nig. Ltd. K/Hausa 19,315,830.95 19,315,830.95 18,285,824.55 14/11/2018 12 weeks 100 Completed
20
Construction of Prototype basic Health Care Clinic (Lot-2) at
Lafiya in Birnin kudu L.G.A. Imam Ahmad Nig. Ltd. B/kudu 19,956,897.66 19,956,897.66 19,840,781.07 14/11/2018 12 weeks 100 Completed
21
Construction of Prototype basic Health Care Clinic (Lot-11) at
Gagarawa Gari in Gagarawa L.G.A. Math Global Investment Ltd Gagarawa 20,290,282.93 20,290,282.93 20,157,450.85 14/11/2018 12 weeks 100 Completed
22
Construction of Prototype basic Health Care Clinic (Lot-15) at
Siyori in Garki L.G.A. Sabon Garin 'Yaya Garki 20,293,808.95 20,293,808.95 20,159,968.97 14/11/2018 12 weeks 100 Completed
23
Construction of Prototype basic Health Care Clinic (Lot-12) at
Jeke in Sule Tankarkar L.G.A. Sir Welter Drilling & General S/Tankarkar 20,887,831.00 20,887,831.00 20,734,104.26 14/11/2018 12 weeks 100 Completed
24
Construction of Prototype basic Health Care Clinic (Lot-9) at
Saleri in Kirikasamma L.G.A. Nushe Business Resources Kiri Kasamma 19,816,590.01 19,816,590.01 19,708,414.74 14/11/2018 12 weeks 100 Completed
25
Co ns truc tio n o f pro to type bes ic Health Care Clinic (Lo t-5) Gafaya in
Kafin haus a L.G.A. Yus matech Inves tment Nig. Ltd K/Haus a 20,637,816.30 20,637,816.30 20,489,694.12 14/11/2018 12 weeks 100 Completed
26 Co ns tr o f One blo ck o f Health po s t a t Kwandiga village in Kaugama LGA. Sambu Synergy Co ncept Ltd. Kaugama 2,865,048.91 2,865,048.91 2,854,621.41 31/12/2018 8 weeks 100 Completed
27 Co ns tr o f o ne blo ck o f hea lth po s t a t Karko village in Gwaram LGA. Ngaloma Constr. Co. Ltd. Gwaram 7,543,976.80 7,543,976.80 7,520,739.77 31/12/2018 12 weeks 100 Completed
Balance C/F 631,483,336.88 631,483,336.88
1b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 631,483,336.88 631,483,336.88
28
Co ns tr o f P ro to type Bas ic Health Care Clinic (Lo t-10) a t Birniwa Tas ha in
Birniwa LGA. Wajabs Building and Co ns tr Birniwa 19,756,195.59 19,756,195.59 19,656,319.72 14/11/2018 12 weeks 100 Completed
29
Supply and Is ta lla tio n o f Ho s pita l Equipments to Kafin haus a Genera l
Ho s pita l Dagari Integra ted Services K/Haus a 83,543,417.50 83,543,417.50 83,543,417.50 28/12/2018 8 weeks 100 Completed
30
Construction for the construction of health post at Tashena Village in
M alam M adori Local Government Area. DALARI CONSTRUCTION M /madori 7,543,976.80 7,543,976.80 7,519,281.10 31/01/2019 8 Weeks 100 Completed
31
Renovation works (2019 Phase I) Constittuency Project at Haya PHC
and Gamji Health post in Fagam Constituency, Gwaram Local
Government Area. GIDAN ADEDE GENERAL Gwaram 12,468,995.04 12,468,995.04 12,421,231.26 31/01/2019 8 Weeks 100 Completed
32
Construction of Health Post at Redo Viillage inGwaram Local
Government Area Ramadan Gwaram 7,543,976.80 7,543,976.80 7,184,739.76 14/01/2019 8 weeks 100 Completed
33
Construction of Health Post at Sarkin Baka Village in Babura Local
Government Area Babandoki Babura 7,543,976.10 7,543,976.80 7,504,149.76 10/6/2019 8 weeks 100 Completed
34
Construction of Health Post at Waza Viillage in Birnin Kudu Local
Government Area Ngaloma Construction B/kudu 7,543,976.80 7,543,976.80 7,520,739.76 14/1/2019 8 weeks 100 Completed
35
Construction of Health Post at Karko Viillage inGwaram Local
Government Area Ngaloma Construction Gwaram 7,543,976.80 7,543,976.80 7,520,739.76 14/1/2019 8 weeks 100 Completed
36 Constr of Health Post at Shiyo in Auyo DDN Constr Co. Auyo 2,865,048.91 2,865,048.91 2,854,621.41 31/12/2018 8 weeks 100 Completed
37
Contract for the supply & Installation of M edical Equipment to Ringim
General Hospital Dagarai Integrated Srv Ringim 82,153,507.50 82,153,507.50 82,153,507.50 1/7/2019 8 weeks 100 Completed
38 Constr of Health post of Sharkawa in Kaugama M aikatako & Sons Kaugama 7,543,976.80 7,543,976.80 7,184,739.76 31/12/2018 8 weeks 100 Completed
39
M aintenance of to ilets and reconstruction of soakway at female hostels
School of Nursing Hadejia GIDAN ADEDE GENERAL Hadejia 2,467,026.00 2,467,026.00 2,467,026.00 27/06/2019 8 weeks 100 Completed
Total 880,001,387.52 880,001,388.22
1c
Ministry of Water
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 Improv ement of Kazaure tow n Water Supply Marb Eng. & Multy Serv ices Kazaure 131,208,239.13 163,939,534.76 156,132,890.23 7/28/2016 7 w eeks 100 Completed
2 Improv ement of Ringim tow n w ater supply Marb Eng. & Multy Serv ices Ringim 137,576,766.21 213,146,514.63 213,145,467.79 11/23/2016 20 w eeks 100 Completed
3
Constr. Of Hand Pumps Water Supply Schemes as
Constituency Projects at Falkin Jalo Nasaraw a, Fulanin
Kuka Uku, Fulanin Liman Mado, Fulanin Gangara and
Fulanin Dan'ama Gabas in Gumel Constituency . JAG & H Int. Serv ices Gumel 2,742,600.00 2,742,600.00 2,735,743.50 29/8/2017 8 w eeks 100 Completed
4
Constr. Of Solar Pow ered Water Supply Schemes
(Phase I) as Constituency Project at Mary e in Birniw a
Constituency ADZ GLOBAL SERV LTD Birniw a 6,968,010.00 6,968,010.00 6,950,589.98 7/8/2017 8 Weeks 100 Completed
5
Constr. Of Hand Pumps Supply Schemes (Phase I-2017)
as Constituency Project at Kofar Gabas Gw aram,
Barebari Makabarta Sabuw a, Auy akaw a Gidan Dutse
Gw aram, Tambo Gw aram and Sumangara in Gw aram
Constituency AZZIDS NIG LTD Gw aram 7,076,160.00 7,076,160.00 7,076,160.00 28/8/2017 8 Weeks 100 Completed
6
Upgarding and Conv ersion of 7No Motorized Water
Supply Schemes to Solar Pow ered Water Supply
Schemes at Dundubus, Kafin Gana, Danmakama,
Marma, Bulangu, Dansure and Jigaw a Tow n. SIM S GLOBAL RESOURCE State 90,265,107.03 90,265,107.03 90,038,444.26 25/08/2017 16 weeks 100 Completed
7
Rehabilitation of Solar Pow ered Water supply schemes
across the State at Birnin kudu, Dutse, Hadejia,Ringim,
Gumel, Jahun and Kazaure zone (Stow a) Sims Global Resources Across the state 166,689,700.28 166,689,700.28 166,272,976.03 18/12/2017 12 w eeks 100 Completed
8
Constr of (10No.) Hand Pumps Water Suppy Schemes
2017 Constituency Phase II Projects (Lot-5) at
Kw akw ado Fulani, Kabaw a, Danbagaje Fulani,Rigar
Dumu Dakau, Fulanin Fankami, Gana , Gw allaw a
Unguw ar Kole, Jama'ar Dan Maigari and Ribinji in Garki
Constituency Loy alty Properties Garki 7,980,000.00 7,980,000.00 7,980,000.00 1/24/2018 8 w eeks 100 Completed
9
Constr. Of (1no.) Solar [pow ered w ater supply scheme
2017 constituency phase II project (LOT-29) at Kadamu
tudu tashena in M/madori Constituency . Limis Brothers & Co. M/madori 6,968,430.00 6,968,430.00 6,951,008.93 24/1/2018 8 w eeks 100 Completed
10
Construction of (1No.) Solar Pow ered Water supply
scheme 2017 Constituency phase III Projects (Lot-39) at
Jama'ar Suga in Kirikasamma Constituency . Bulangu Drilling Serv ices K/kasamma 6,968,430.00 6,968,430.00 6,968,430.00 6/2/2018 8 w eeks 100 Completed
11
Construction of Hand Pumps Water Supply Scheme 2017
Constituency Phase III Projects (Lot-10) at Unguw ar Faru
in Kazaure Consituency . Na'ay i Resouces Ltd. Kazaure 797,580.00 797,580.00 797,580.00 6/2/2018 8 w eeks 100 Completed
Balance C/F 565,241,022.65 673,542,066.70
2a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 565,241,022.65 673,542,066.70
12
Construction of (6No.) Hand Pumps Water supply
scheme 2017 Constituency phase II Projects (Lot-10) at
Faskarau, Ubba, Fulanin Askandu, Turmi, Kanjuw a and
Bay in Kw ari in Kaugama Constituency . ADZ Global Serv ices Ltd. Kaugama 4,803,750.00 4,803,750.00 4,791,740.65 22/2/2018 8 Weeks 100 Completed
13
Upgrading and Conversion of Motorised Boreholes
to Solar Powered at 7no. Towns water supply
schemes (Kanya Babba in Babaura LGA, Danzomo
in S/tankarkar LGA, Kudai in Dutse LGA and Waza
in B/kudu LGA) SIMS GlobalResources State 82,495,606.57 82,495,606.57 78,710,101.05 10/4/2018 16 weeks 100 Completed
14
Constr of Hand pump Boreholes as constituency
projects (2018 phase II) Lot-7 at Zunburu, Tange,
S/garin Matsango, Bagiya, Ligada, Kuyungu (2no.),
Rigar Beti Digijin and Tudun Wada Fagam in Fagam
Constituency. Loyalty Properties Nig. Ltd. Gwaram 6,603,660.00 6,603,660.00 6,603,660.00 18/12/2018 8 weeks 100 Completed
15
Constr of Hand pump Boreholes as constituency
projects (2018 phase II) Lot-10 at Fulanin Dan
Ama, Dantanoma Sarkin Gora, Jarumai Abuja
Quarters, Nasarawa M/Juma'a, Fulanin Kanjau,
Haruna Kuka Uku, Fulanin Danfarantama, Garin
Ginsau, Prison Qtrs. and Gidan maigari in Gumel
Constituency. Farham Synergy Concept Gumel 7,374,150.00 7,374,150.00 7,374,150.00 18/12/2018 6 weeks 100 Completed
16
Conversion of 2no. Motorized boreholes to Solar
powered water supply schemes at Main pump
station Sule Tankarkar and Oliya pump station in
Sule Tankarkar LGA. SIMS Global Resources S/Tankarkar 42,243,266.00 42,243,266.00 42,243,265.99 31/12/2018 12 weeks 100 Completed
17
Constr of Hand pump Boreholes as constituency
projects (2018 phase II) Lot-2 at Guruma and
Mungula B/Kudu Constituency. Umar Aliyu & Sons Nig. Ltd. B/kudu 1,475,560.00 1,475,560.00 1,475,560.00 18/12/2018 4 weeks 100 Completed
18
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
9 at Zareku Miga Constituency. AMIA Integ. Services Miga 6,022,275.00 6,022,275.00 6,008,141.00 17/10/2018 8 weeks 100 Completed
19
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
27 at U/Shuri in Babura Constituency. Mufabamex Consept Babura 6,020,700.00 6,020,700.00 6,008,057.21 17/10/2018 8 weeks 100 Completed
20
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
47 at Danzomo Gari in Sule Tankarkar
Constituency. Lautai General Invest. S/tankarkar 6,023,115.00 6,023,115.00 6,008,057.21 17/10/2018 8 weeks 100 Completed
21
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
28 at Kantudu in Roni Constituency. HIKIMA Synergy Gen. Roni 6,023,115.00 6,023,115.00 6,008,057.21 17/10/2018 8 weeks 100 Completed
22
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
33 at Matsarida in Maigatari Constituency. A+Tech Integ. Nig Ltd. Maigatari 6,022,275.00 6,022,275.00 6,007,219.31 17/10/2018 8 weeks 100 Completed
Balance C/F 740,348,495.22 848,649,539.27
2b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 740,348,495.22 848,649,539.27
25
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
40 at Farin Dutse in Fagam Constituency, Gwaram
LGA. A+Tech Integ. Nig Ltd. Gwaram 6,022,275.00 6,022,275.00 6,005,648.25 17/10/2018 8 weeks 100 Completed
26
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
37 at Mai'adua in Gagarawa Constituency. LIMIS Brothers & Co. Gagarawa 6,020,700.00 6,020,700.00 5,985,000.00 17/10/2018 8 weeks 100 Completed
27
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
31 at Takur in Dutse Constituency. Talaku Ingrated Services Dutse 6,000,000.00 6,000,000.00 5,985,000.00 17/10/2018 8 weeks 100 Completed
28
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
32 at Rungumau in Dutse Constituency. Talaku Ingrated Services Dutse 6,000,000.00 6,000,000.00 5,985,000.00 17/10/2018 8 weeks 100 Completed
29
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
20 at Zabaran in Gumel Constituency. Muhal Global Concept Gumel 6,020,700.00 6,020,700.00 6,020,700.00 17/10/2018 8 weeks 100 Completed
30
Constr of (10no.) Hand pumps Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
8 at Fulanin Akwalawa, Garin Kailu, Harbo sabo,
Fulanin Mele, Dagerawa, Danfarantama, F/Mijin
Gini, Lautai Science, Boarding Girls Pri. & JSS and
Kuka Uku Fulani in Gumel Constituency. Muhal Global Concept Gumel 7,347,380.00 7,347,380.00 7,347,379.99 17/10/2018 12 weeks 100 Completed
31
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
6 at Anturu in Birniwa Constituency. Synclime Nig. Ltd. Birniwa 6,023,115.00 6,023,115.00 6,008,057.21 17/10/2018 8 weeks 100 Completed
32
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
5 at GGSS Birniwa in Birniwa Constituency. Synclime Nig. Ltd. Birniwa 6,022,276.00 6,022,276.00 6,007,220.31 17/10/2018 8 weeks 100 Completed
33
Constr of (7no.) Hand Pumps Water Supply Scheme
Constituency Projects (2018 phase 1) Lot-2 at
Bagudu, Dugujaba, Gangara Nabunu, Wada
Tsohuwa Tudu, Jan Zomo, Babbar Riga and
Yarkirya in babura Constituency. Mufabamex Concept Babura 5,100,676.00 5,100,676.00 5,100,676.00 17/10/2018 8 weeks 100 Completed
34
Constr of (5no.) Hand Pumps Water Supply Scheme
Constituency Projects (2018 phase 1) Lot-3 at
Kauyen Boka, Dukari, Kyaurawa, fagoje U/Iya and
Mungulo in Birnin Kudu Constituency. Nushe Business Resources B/kudu 3,656,467.50 3,656,467.50 3,647,326.34 17/10/2018 8 weeks 100 Completed
Balance C/F 798,562,084.72 906,863,128.77
2c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 798,562,084.72 906,863,128.77
35
Constr of (6no.) Hand Pumps Water Supply Scheme
Constituency Projects (2018 phase 1) Lot-10 at
Rahaina, Takalafiya, Jangwam Fulani, Tasgan Gabas,
Madamuwa and Garmaguwa Yamma in Guri
Constituency. A.Y.H. Investment Co. Guri 4,415,040.00 4,415,040.00 4,404,002.40 17/10/2018 8 weeks 100 Completed
36
Construction of (28NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot
13 at Gidan Danko, Bayan Gidan Wanka, Likindi,
Damutawa Kazage, Kukawa Fulani, Afasha, Lilon
Dan Baki, Tsalliyawa Kunguyun, Mahauta, Jabarna
Kauye, Fantagwal, Zagau Makera, Abirikyau T.
Gabas, Tsibiri, Masallacin M. Madibo, Gidan Tila,
Gangaren Kwalta, Yalleman K. Gabar. Gidan Atiku,
Kwanyoli, Gidan Hakimi, Jabarna, Darai Madobi,
Bayan Katarin, Yalayin Kolrori, Kandahar and
Sabon Kaye in Jahun Constituency. Jawad Global Resources Jahun 20,572,664.00 20,572,664.00 20,572,663.99 17/10/2018 8 weeks 100 Completed
37
Construction of (10NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot
16 at Yan Auta, Miyawa, Yalwan Fulani, Sabuwar
Unguwa, Nafara Alh. Uba, Sabuwar Raba, Yolal,
Jigawar Kiyawa, Ung. Dahiru Mai Gyada and
Mandela in Kiyawa Constituency. Demastbo Ventures Ltd. Jahun 7,377,825.00 7,377,825.00 7,377,825.00 17/10/2018 12 weeks 100 Completed
38
Construction of (25NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot 4
at Laraba, Zangon Farin Dutse, Kwanar Fado,
Kakibare, Sayasaya Sabuwar Yalwa, Gayawa Zai,
Kalusa, Gidan Kuka mainari, Dutsin Duru Ungullo
Kagara, Taju, Ruwan Baure, Lemunawa, Hora
Arewa, Dabawa Zango, Gidan Gawo, Kundi,
Tsangayar Jan Shuri, Kargo Mahauta Manhada and
Dilake in Dutse Constituency. Talaku Integrated Services Dutse 18,361,875.00 18,361,875.00 18,315,970.31 17/10/2018 12 weeks 100 Completed
Balance C/F 849,289,488.72 957,590,532.77
2d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 849,289,488.72 957,590,532.77
40
Construction of (10NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot
19 at Dan kawu Hardo Take, Tubus Hardo Gatag M.
Amadu, Gidan Dogo Hardo Ruwa, Abdullahi Balga
Hardo Dawa, Barmanawa Gari, Kunkurai Gari,
Akwai ALLAH Gari, Sabo mai Kalanda Hardo Juli,
Saidi Dogo Fulanin Gwata Gidan Rabo Fulani and
Zokoto in Sule Tankarkar Constituency. Lautai Genaral Investment S/tankarkar 7,377,825.00 7,377,825.00 7,377,825.00 17/10/2018 12 weeks 100 Completed
41
Construction of (15NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot 7
at Muku, Tsalle, Balashe, Fankami, Tsagwaye,
Jirima, Magatarin B/ALLAH, Doguwar Kuka,
Kwadage Dan karofi, Gwallawa, Kabawa,
Kwana,Zaidawa, Karangi and Koguran Tsohuwa in
Garki Constituency. A.D.Z. Global Services Ltd. Garki 18,884,580.00 18,884,580.00 18,884,580.00 17/10/2018 8 weeks 100 Completed
42
Construction of (1NO.) Water Collection Point
Constituency projects (2018 Phase I) Lot 9 at Rigar
Kangal in Taura Constituency. Nushe Business Resources Taura 1,199,677.50 1,199,677.50 1,196,678.31 17/10/2018 4 weeks 100 Completed
43
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-30) at Yan Duna in Miga
Constituency. Amia Integ. Service Nig Ltd. Miga 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed
44
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-27) at Muduga in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 6,201,720.00 6,201,720.00 6,201,720.00 23/11/2018 8 weeks 100 Completed
45
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-37) at Botsotsuwa in Babura
Constituency. Mafabamex Concept Nig. Ltd. Babura 6,023,199.00 6,023,199.00 6,008,141.00 23/11/2018 8 weeks 100 Completed
46
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-34) at Maradawa in Kazaure
Constituency. Yanduna Ventures Ltd. Kazaure 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
47
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-33) at Kanti Gabas in Kazaure
Constituency. Yanduna Ventures Ltd. Kazaure 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
Balance C/F 907,045,919.22 1,015,346,963.27
2e
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 907,045,919.22 1,015,346,963.27
48
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-38) at Achiya in Babura
Constituency. Mufabamex Concept Ltd. Babura 6,023,199.00 6,023,199.00 6,008,141.00 23/11/2018 8 weeks 100 Completed
49
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-4) at Lawandi in Birniwa
Constituency. Limis Brother & Co., Birniwa 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed
50
Construction of (3NO.) Water Collection Point
Constituency Projects (2018 Phase 1) Lot-12 at
Walawa (2NO.) and Kofar Tukura (1NO.) in Hadejia
Constituency. Step by Step Integrated Hadejia 3,600,002.70 3,600,002.70 3,591,002.69 23/10/2018 6 weeks 100 Completed
51
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-5) at Kukuma in Buji Constituency. Limis Brother & Co., Buji 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
52
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-17) at Kirilla in Maigatari
Constituency. Limis Brother & Co., Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
53
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-43) at Gayawa Tudu in Gagarawa
Constituency. Limis Brother & Co., Gagarawa 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed
54
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-44) at San Amarya in Gagarawa
Constituency. Limis Brother & Co., Gagarawa 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed
55
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-36) at Matsa in Malam Madori
Constituency. Hambiscon Nig. Ltd. M/Madori 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed
56
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-11) at Kila Kofar Arewa in Gwaram
Constituency. Jag & H Intgrated Serv. Ltd. Gwaram 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed
57
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-31) at Burji in Miga Constituency. A. Barde Global Concept Miga 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
58
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-28) at Dabaka in Miga Constituency. A. Barde Global Concept Miga 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
Balance C/F 970,877,134.92 1,079,178,178.97
2f
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 970,877,134.92 1,079,178,178.97
59
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-15) at Guri in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
60
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-16) at Arin in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
61
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-13) at Dawa in Guri Constituency. A. y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
62
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-14) at ArinJasko in Guri
Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
63
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-12) at Musari in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
64
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-9) at Juma'ar Yunusa in Kafin Hausa
Constituency. Tosarawa Global Nig. Ltd. K/Hausa 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed
65
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-8) at Autako in Kafin Hausa
Constituency. Mugin Investment Nig. Ltd. K/Hausa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
66
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-6) at Majefarin Yamma in Kafin Hausa
Constituency. Mugin Investment Nig. Ltd. K/Hausa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
67
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-7) at Ansaya in Kafin Hausa
Constituency. Mungin Investment Nig. Ltd. K/Hausa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
68
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-41) at Babbar Riga in Malam Madori
Constituency. Step By Step intgrated Servic M/madori 6,023,125.00 6,023,125.00 6,008,067.18 23/11/2018 8 weeks 100 Completed
69
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-32) at Bagade Gari in Sule Tankarkar
Constituency. Danfatu & Sons Nig. Ltd. S/tankarkar 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
Balance C/F 1,037,131,094.92 1,145,432,138.97
2g
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,037,131,094.92 1,145,432,138.97
70
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-24) at Burdawa S/Gabas in Gwiwa
Constituency. Jignaj Global Constructions Gwiwa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
71
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-25) at Buntusun Abuja in Gwiwa
Constituency. Jignaj Global Constructions Gwiwa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
72
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-39) at Sankara in Ringim
Constituency. Marb Engr. Multi-Services Ringim 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed
73
Supply of the (1 No.) Solar Powered Water Supply
Schemes 2018 Constituency Phase III Projects +
(3no. Saflex pumps) (Lot-40) at Karshi, Fachama
and Gamoji in Ringim Constituency. Marb Engr. Multi-Services Ringim 10,872,138.69 10,872,138.69 10,872,138.69 23/11/2018 8 weeks 100 Completed
74
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-35) at Andaza Kudu in Kiyawa
Constituency. Farham Intgratred Resources Kiyawa 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed
75
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-2) at Kaigamari in Auyo
Constituency. Madanta Global Nig. Ltd. Auyo 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed
76
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-19) at Bakawa in Maigatari
Constituency. Alkawakeb Global Concept Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
77
Upgrading of 1no.) motorized Water Supply
Schemes 2018 Constituency Phase III Projects (Lot-
22) at Digijin in Fagam Constituency. Pullad Global Consultant Gwaram 10,872,138.69 10,872,138.69 10,872,138.69 23/11/2018 8 weeks 100 Completed
78
Construction of the (1 No.) Solar Powered Water
Supply Schemes (2018 Phase III) Constituency
Projects at Shiyo in Auyo Constituency. Alaska Genral Enterprises Auyo 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed
79
Construction of the (1 No.) Solar Powered Water
Supply Schemes (2018 Phase III) Constituency
Projects at Garin Jama'u in Gagarawa Constituency. Altima Intgrated Services Gagarawa 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed
80
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-10 at Takalafiya in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 6,023,199.00 6,023,199.00 6,023,199.00 23/11/2018 8 weeks 100 Completed
Balance C/F 1,113,083,680.30 1,221,384,724.35
2h
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,113,083,680.30 1,221,384,724.35
81
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-9 at Garbo in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed
82
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-47 at Gidan Gona in Kazaure
Constituency. Lautai Genaral Investment Kazaur e 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
83
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-41 at Maguwa in Kirikasamma
Constituency. Talaku Intgrated Services K/Kasamma 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed
84
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-35 at Kakudi Babba in Suletankarkar
Constituency. Talaku Intgrated Services Sule tankarkar 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed
85
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-39 at Solari in Kirikasamma
Constituency. Loyalty Properties Ltd. Kirikasamma 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed
86
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-27 at Babura Yamma in Babura
Constituency. Mufabamex Concept Ltd. Babura 6,014,355.00 6,014,355.00 5,999,319.11 23/11/2018 8 weeks 100 Completed
87
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-50 at Gizo in Kazaure Constituency. Yanduna Ventures Ltd. Kazaure 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
88
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-49 at Yar'Unguwa in Kazaure
Constituency. Yanduna Ventures Ltd. Kazaure 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
89
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-3 at Jam'ar Ayan in Auyo
Constituency. Khairussabah Nig. Ltd. Auyo 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
90
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-36 at Shadamai in Yankwashi
Constituency. Granitoids Engr. Services Ltd Yankwashi 6,023,220.00 6,023,220.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
91
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-37 at Karkarna in Yankwashi
Constituency. Granitoids Engr. Services Ltd Yankwashi 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
92
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-1 at Anauya in Auyo Constituency. Farham Intgratred Resources Auyo 6,023,220.00 6,023,220.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
Balance C/F 1,185,352,720.30 1,293,653,764.35
2i
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,185,352,720.30 1,293,653,764.35
93
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 44 a t Kuzunzumi in Ka nya Ba bba
Cons titue nc y. Limis Brother & Co., Babura 6,023,115.00 6,023,115.00 6,008,054.06 23/11/2018 8 weeks 100 Completed
94
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 24 a t Ka ma in Ma iga ta ri Cons titue nc y. Limis Brother & Co., Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
95
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 25 a t Dira ni in Ma iga ta ri Cons titue nc y. Limis Brother & Co., Maigatari 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
96
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 23 a t Ma ifa ri in Ma ga ta ri Cons titue nc y. Limis Brother & Co., Magatari 6,023,010.00 6,023,010.00 6,007,952.48 23/11/2018 8 weeks 100 Completed
97
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 40 a t Ila lla h in Kirika sa mma
Cons titue nc y. Sahal Bin Nig. Ltd. Kirikasamma 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
98
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 38 a t Kira misa u in Kirika sa mma
Cons titue nc y. Sahal Bin Nig. Ltd. Kirikasamma 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed
99
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 16 a t Rora n Ma la ma i in Gwiwa
Cons titue nc y. Jignaj Global Constructions Gwiwa 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
100
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 44 a t Da ushe in Ringim Cons titue nc y. Marb Engr. Multi-Services Ringim 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed
101
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 46 a t Ma ra wa in Ringim Cons titue nc y. Marb Engr. Multi-Services Ringim 6,023,220.00 6,023,220.00 6,023,220.00 23/11/2018 8 weeks 100 Completed
102
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 7 a t Ba kwa rga in Buji Cons titue nc y. Limis Brother & Co., Buji 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
103
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 8 a t Gwa ngwa n in Buji Cons titue nc y. Limis Brother & Co., Buji 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
104
Construc tion of the (1 No.) S ola r P owe re d Wa te r
S upply S c he me s Cons titue nc y P roje c ts (2018
P ha se II) Lot- 22 a t Ga rba ga l in Guri Cons titue nc y. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
Balance C/F 1,257,630,310.30 1,365,931,354.35
2j
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,257,630,310.30 1,365,931,354.35
105
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-31 at Maijiruwa in Gagarawa
Constituency. Danfatu & Sons Nig. Ltd. Gagarawa 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
106
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-2 at Kwazumo in Auyo Constituency. Danfatu & Sons Nig. Ltd. Auyo 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
107
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-21 at Abunabo in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
108
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-20 at Zugo in Guri Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
109
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-19 at Garmaguwa Yamma in Guri
Constituency. A. Y. H. Investment Company Guri 6,023,010.00 6,023,010.00 6,007,952.48 23/11/2018 8 weeks 100 Completed
110
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-18 at Garmaguwa Gabas in Guri
Constituency. A. Y. H. Invest. Co. Guri 6,023,010.00 6,023,010.00 6,007,952.47 23/11/2018 8 weeks 100 Completed
111
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-17 at Zugobiya in Guri Constituency. A. Y. H. Invest. Co. Guri 6,075,720.00 6,075,720.00 6,060,530.70 23/11/2018 8 weeks 100 Completed
112
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-28 at Unguwar Dinya in Roni
Constituency. Hikima Synergy Gen. Entp. Roni 6,023,199.00 6,023,199.00 6,008,141.00 23/11/2018 8 weeks 100 Completed
113
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-30 at Amaryawa in Roni
Constituency. Hikima Synergy Gen. Entp. Roni 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
114
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-29 at Unguwar Mani in Roni
Constituency. Hikima Synergy Gen. Entp. Roni 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
Balance C/F 1,311,890,719.30 1,420,191,763.35
2k
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,311,890,719.30 1,420,191,763.35
115
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) at Kabala Jahun in Jahun Constituency. Dalari Constr Co. Jahun 6,023,115.00 6,023,115.00 6,008,057.21 23/11/2018 8 weeks 100 Completed
116
Construction of (5 No.) Hand Pump Water Supply
Schemes Constituency Projects (2018 Phase I) Lot-
21 at Gidan Nokia Fulani, Karkarna C/Gari, S/Fulani
Gurjiya, Karkarna Islamiyya and Ringim in
Yankwashi Constituency. Granitoids Engr. Services Ltd Yankwashi 3,644,025.00 3,644,025.00 3,634,914.93 17/10/2018 8 weeks 100 Completed
117
Construction of (4No.) Solar Powered Water
Supply Schemes at Garin ganau, Kwadage, Chika-
koshi and Kankaren Nagona in Babura L. G. A.
(Ringim Zone). Sims Global Resources Nig. Babura 24,093,300.00 24,093,300.00 24,093,300.00 12/12/2018 12 weeks 100 Completed
118
Construction of (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-48 at Gwabbare in Kazaure
Constituency. Yanduna Ventures Ltd. Kazaure 6,023,220.00 6,023,220.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
119
Construction of (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-47 at Gidan Gona in Kazaure
Constituency. Yanduna Ventures Ltd. Kazaure 6,023,122.00 6,023,122.00 6,008,161.95 23/11/2018 8 weeks 100 Completed
120
Construction of the (1 No.) Solar Powered Water
Supply Schemes (2018 Phase III) Constituency
Projects (Lot-42) at Matara Galadima in
Kirikasamma Constituency. Bulangu Drilling Services K/kasamma 6,023,010.00 6,023,010.00 6,023,010.00 31/12/18 8 weeks 100 Completed
121
Construction of the (1 No.) Solar Powered Water
Supply Schemes (2018 Phase III) Constituency
Projects (Lot-29) at Garin Abdalla in Miga
Constituency. Xtrax 99 Integrated Services Miga 6,023,115.00 6,023,115.00 6,023,115.00 23/11/2018 8 weeks 100 Completed
122
Construction of the (1 No.) Solar Powered Water
Supply Schemes (2018 Phase II) Constituency
Projects (Lot-43) at Kanya Arewa in Kanya Babba
Constituency. Limis Brother & Co., Babura 6,023,010.00 6,023,010.00 6,007,952.48 23/11/2018 8 weeks 100 Completed
123
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency (Phase III)
Projects (Lot-10) at Be-bayi in Kafin Hausa
Constituency. Tosarawa Global Nig. Ltd. K/Hausa 6,023,010.00 6,023,010.00 6,023,010.00 12/12/2018 8 weeks 100 Completed
124
Construction of Water Collection Point as
Constituency Projects (2018 Phase III) Lot-24 at
Tsohuwar Gwaram, Guduma, Katsinawa and
Dutsen Gandu in Gwaram Constituency. Farham Synergy Concept Ltd. Gwaram 5,011,996.00 5,011,996.00 5,011,995.96 18/12/2018 8 weeks 100 Completed
Balance C/F 1,380,778,632.30 1,489,079,676.35
2L
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,380,778,632.30 1,489,079,676.35
126
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase III) Lot-7 at
Gidan Nakuka, Makwai Fulani, Dandidi (4 No.),
Gidan Kato Furya, Gidan Badawai, Fulanin mai
Adu'a and Kukule in Gagarawa Constituencyi Farham Synergy Concept Ltd. Gagarawa 7,374,150.00 7,374,150.00 7,374,150.00 18/12/2018 8 weeks 100 Completed
127
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase III) Lot-12 at
Limawa, Afaru, Giwaran, Kununu Zaki, Kuzan Iliya
and Kwazalewa Gidan Mafi in Kafin Hausa
Constituencyi Faahm Intgratred Resources K/Hausa 4,425,750.00 4,425,750.00 4,425,750.00 18/12/2018 6 weeks 100 Completed
128
Construction of Water Collection Point as
Constituency Projects (2018 Phase III) Lot-28 at
Ajaura (Pipe Line Extention) and Gidan Dauda
(W.C.Point) in Taura Constituency. Nushe Business Resources Taura 4,874,063.25 4,874,063.25 4,861,878.09 18/12/2018 8 weeks 100 Completed
129
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase III) Lot-18 at
Majiya Secondary School in Taura Constituencyi Nushe Business Resources Taura 737,520.00 737,520.00 737,520.00 18/12/2018 4 weeks 100 Completed
130
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase III) Lot-15 at
Kabobo Chaichai, 'Yanduna kawai, Dandalin Wailari,
Takwasha, Chaichai Makabarta and Amaguwa in
Ringim Constituencyi Marb Engr. Multi-Services Ringim 4,426,680.00 4,426,680.00 4,415,413.30 18/12/2018 8 weeks 100 Completed
131
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-5 at Akurya, Limawa, Gumussawa,
Gabari, Yola Musa, Mawa, Bujaje, Jigawar Gabas,
Rigar Jauro Mato, Rigar Buba Salewa, Gulungulun,
Karsha, Suwameri, ALLAH kayi, Tumba gidan Baba
Sarki, Aduna Dikko, Shagewa, Yammarin A. Mato,
Shagen Yamma Danlalan Fulanin Village, Gamajan,
Kuloma, Sadingo Garin Mati, Babbar Jigawa,
Alhajerin Chiromari, Chakwasan, Guduwari Gidan
Gaiya, Mangari, Mawalan Tumunjira and Rigar
Buba Habbo in Bulangu Constituencyi Bulangu Drilling Services K/Hausa 25,036,410.00 25,036,410.00 24,973,818.97 18/12/2018 12 weeks 100 Completed
Balance C/F 1,423,226,525.55 1,531,527,569.60
2m
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,423,226,525.55 1,531,527,569.60
132
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-19 at Alagarno Gari Haru, Tarawa
Fulani, Haro Yale, Babbar Dinya, Balarabe, Harso
Sale, Gidan Nomau and Gidan M/manu in Maigatari
Constituency. Nadada Ventures Nig. Ltd. Maigatari 5,869,920.00 5,869,920.00 5,869,920.00 18/12/2018 8 weeks 100 Completed
133
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-23 at Girgi Gari, Tsangaya,
Jemau,Sabon Layi Unguwar Barde Banaga,
Sakataren Muyatti ALLAH, Hardo Yahaya Balkindo,
Hardo Lauwali Fulanin Girgi Yamma, Zanguna,
Jumawa Gari, Nazau Gari, Fulanin Walawa Gidan
Haruna Babe, Dungundun Gari and Gidan Shuaibu
Ajiya HardoIla in Sule Tankarkar Constituency. Nushe Business Resources S/tankarkar 8,844,192.00 8,844,192.00 8,822,081.52 18/12/2018 8 weeks 100 Completed
134
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-18 at Tsotsawa Fulani and Bakata
Cikin Gari in Kiyawa Constituency. Faahm Intgratred Resources Kiyawa 1,467,730.00 1,467,730.00 1,467,730.00 18/12/2018 4 weeks 100 Completed
135
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-16 at Rangina, Kantamari, Gangara,
Motso, Karumi, Mai Kunama, Rugar Kota Buhun
Karangiya, Meleri Marke, Masama Karama, Fulanin
Kagori, Kaugama Yamma, Kanwar Gamawa, Manda
Mai Gawo and Anguwar Habulle in Kaugama
Constituency. Faahm Intgratred Resources Kaugama 14,569,232.00 14,569,232.00 14,569,232.00 18/12/2018 10 weeks 100 Completed
136
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-8 at Firya, Garin Inu, Zaro, Dan Daga
Arewa and Habatsai in Gagarawa Constituency. Farham Synergy Concept Ltd. Gagarawa 3,687,075.00 3,687,075.00 3,687,075.00 18/12/2018 6 weeks 100 Completed
Balance C/F 1,457,664,674.55 1,565,965,718.60
2n
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,457,664,674.55 1,565,965,718.60
137
Construction of Water Collection Point as
Constituency Projects (2018 Phase II) Lot-29 at
Unguwar Kanya T/Gwaram, Shiwo Sara, Sakuwa
Sara, Lukutu, Innakawa, Maruta cikin Gari, Yaddare
Kila, Unguwar kudu Z/nagogo, Gogurawa Yamma
Z/Nagogo, Lafiya Tsangarwa Shabewa
Tsangarwa,Fasa Ganga T/Gwaram, Sakwaya
Maruta Tsahira T/Gwaram GGUSS Gwaram and
Salmande in Gwaram Constituency. Jag & H Intgrated Services Ltd. Gwaram 22,686,282.00 22,686,282.00 22,686,281.10 18/12/2018 12 weeks 100 Completed
138
Construction of Water Collection Point as
Constituency Projects (2018 Phase II) Lot-28 at
Tsamiyar Osi, Ahabab Rasulillahi Ado Tela Gana,
Layin Babar Sardauna, Tudun Alhazai, College of
Education, Kofar Danmakwayo, Dantanoma
S/Kwalta, Layin GidanGalaba, Layin Gidan Dallatu,
Dantanoma L/Mari Audu, Gidan Gawo, Egoni Sabon
Layi, Famfom Gawo, Masallacin J/Gabas and
Masallacin Yarabawa in Gumel Constituency. Farham Synergy Concept Ltd. Gumel 20,165,584.00 20,165,584.00 20,165,583.99 18/12/2018 12 weeks 100 Completed
139
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-3 at Dagolori, Fulanin Mariye,
Buhunni, Fulanin Nguwa, Fajiginari, Medori,
Birniwa Unguwar Mangawa, Birniwa T/kudu,
Kadairi, Goruban Tingiri and Gidan usaini wanzam
in Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 8,833,860.00 8,833,860.00 8,811,775.35 18/12/2018 6 weeks 100 Completed
140
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase II) Lot-15 at
Rabo Fulani (4No), Kankaren Jemawa, Jolowa
Fulani, Sansami, Toge, Halladu, Kwadabe Fulanin
Shuaibu, Dan Maakeri, Fulanin Tsamiyar Kwance,
Fulanin Yamma, Kwanar Kuzunzumi and Dorawar
Waje in Kanya Babba Constituency. Deetech Nig. Ltd. Babura 11,072,250.00 11,072,250.00 11,072,250.00 18/12/2018 10 weeks 100 Completed
141
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-3 at Kupsa, Fulanin Karda, Barbura,
Baltori, Zigidimi, Marge and Busugu Abdu in
Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 5,330,906.00 5,330,906.00 5,317,578.73 31/12/18 8 weeks 100 Completed
Balance C/F 1,525,753,556.55 1,634,054,600.60
2O
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,457,664,674.55 1,565,965,718.60
137
Construction of Water Collection Point as
Constituency Projects (2018 Phase II) Lot-29 at
Unguwar Kanya T/Gwaram, Shiwo Sara, Sakuwa
Sara, Lukutu, Innakawa, Maruta cikin Gari, Yaddare
Kila, Unguwar kudu Z/nagogo, Gogurawa Yamma
Z/Nagogo, Lafiya Tsangarwa Shabewa
Tsangarwa,Fasa Ganga T/Gwaram, Sakwaya
Maruta Tsahira T/Gwaram GGUSS Gwaram and
Salmande in Gwaram Constituency. Jag & H Intgrated Services Ltd. Gwaram 22,686,282.00 22,686,282.00 22,686,281.10 18/12/2018 12 weeks 100 Completed
138
Construction of Water Collection Point as
Constituency Projects (2018 Phase II) Lot-28 at
Tsamiyar Osi, Ahabab Rasulillahi Ado Tela Gana,
Layin Babar Sardauna, Tudun Alhazai, College of
Education, Kofar Danmakwayo, Dantanoma
S/Kwalta, Layin GidanGalaba, Layin Gidan Dallatu,
Dantanoma L/Mari Audu, Gidan Gawo, Egoni Sabon
Layi, Famfom Gawo, Masallacin J/Gabas and
Masallacin Yarabawa in Gumel Constituency. Farham Synergy Concept Ltd. Gumel 20,165,584.00 20,165,584.00 20,165,583.99 18/12/2018 12 weeks 100 Completed
139
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-3 at Dagolori, Fulanin Mariye,
Buhunni, Fulanin Nguwa, Fajiginari, Medori,
Birniwa Unguwar Mangawa, Birniwa T/kudu,
Kadairi, Goruban Tingiri and Gidan usaini wanzam
in Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 8,833,860.00 8,833,860.00 8,811,775.35 18/12/2018 6 weeks 100 Completed
140
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase II) Lot-15 at
Rabo Fulani (4No), Kankaren Jemawa, Jolowa
Fulani, Sansami, Toge, Halladu, Kwadabe Fulanin
Shuaibu, Dan Maakeri, Fulanin Tsamiyar Kwance,
Fulanin Yamma, Kwanar Kuzunzumi and Dorawar
Waje in Kanya Babba Constituency. Deetech Nig. Ltd. Babura 11,072,250.00 11,072,250.00 11,072,250.00 18/12/2018 10 weeks 100 Completed
141
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-3 at Kupsa, Fulanin Karda, Barbura,
Baltori, Zigidimi, Marge and Busugu Abdu in
Birniwa Constituency. Kafiyama Gen. Enterprises Birniwa 5,330,906.00 5,330,906.00 5,317,578.73 31/12/18 8 weeks 100 Completed
Balance C/F 1,525,753,556.55 1,634,054,600.60
2O
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,525,753,556.55 1,634,054,600.60
142
Construction of Water Collection Points
Constituency Projects (2018 Phase II) Lot-26 at
Gomburawa, Kachallari and Gajarma in Birniwa
Constituency. Kafiyama Gen. Enterprises Birniwa 3,778,327.26 3,778,327.26 3,768,881.43 18/11/2018 8 weeks 100 Completed
143
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-9 at Rigar Lamido Gandu Una, Rigar
Wuro Jigga, Gaduwa, Rigar Gapta, Maiyiri, Rigar
Lamido Nairi and Rigar Zuzu in Guri Constituency. A.Y.H. Investment Ltd. Guri 8,054,970.00 8,054,970.00 8,034,832.57 18/11/2018 10 weeks 100 Completed
144
Construction of Water Collection Points
Constituency Projects (2018 Phase II) Lot-34
aFilin Aya, Veterinary, Tsohuwar Quarters Yamma
da Tsamiya, Unguwar M. Danmodoji, Mains Goma
Shabiyu, Sule kudu Pri. Sch., Tsangayar M.
Liman,Kofar gidan Rabiu Hassan, Tsangayar M.
Haruna K/Arewa Gari, Gaban Gidan Najib
Councilor K/Gabas,Masallacin M. SaleDan Birib
K/Yamma and Kofar Gidan Aminu Ado Kofa in Sule
Tankarkar Constituency. Pullad Global Consultant S/tankarkar 14,716,363.00 14,716,363.00 14,678,572.09 18/12/2018 8 weeks 100 Completed
145
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-14 at Rigar Wakiliya'a, Zubafinji and
Jarmari in Malam madori Constituency. Express Innovation Concept M/madori 2,213,340.00 2,213,340.00 2,207,806.65 18/12/2018 6 weeks 100 Completed
146
Renovation of (1No) Solar Powered Water supply
Scheme Constituency Projects (2018 Phase II) Lot-
26 at Jingino in Gwaram Constituency. Bakawa Multi Services Ltd. Gwaram 6,023,115.00 6,023,115.00 6,008,057.21 23/12/2018 8 weeks 100 Completed
147
Upgrading and Conversion of Wurma Town Water
Supply Schemes to Solar Powered Water supply
Scheme in Dutse L. G. A. Sims Global Resources Dutse 16,451,241.45 16,451,241.45 15,667,848.99 18/12/2018 8 weeks 100 Completed
148
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-6 at Kiroro Duru Ward, Irwa Limawa
Ward, Laraba Kudai Ward, Zai cikin gari Kachi
Ward, Dutsawa J/Tsada Ward and Gadadin Kachi
Ward in Dutse Constituency Loyalty Properties Nig. Ltd. Dutse 4,402,440.00 4,402,440.00 4,402,440.00 18/12/2018 6 weeks 100 Completed
149
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-6 at Yalwan Gabas, Rigar kaba,
Bakawa, Damagyal, Dabawa, Shiti, Ije, Tsungur,
Kwanar Fado and Junawo in Dutse Constituency Loyalty Properties Nig. Ltd. Dutse 7,337,800.00 7,337,800.00 7,337,799.99 18/12/2018 8 weeks 100 Completed
Balance C/F 1,572,279,911.81 1,680,580,955.86
2p
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,572,279,911.81 1,680,580,955.86
150
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-1 at Gamba kaban, Ayama K/bulama,
Aguza and Jejin Garo in Auyo Constituency Khairussabah Nig. Ltd. Auyo 2,947,560.00 2,947,560.00 2,947,560.00 18/12/2018 6 weeks 100 Completed
151
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) at Fulanin Fateka, Fulanin Garin Malam
Makarantar Yamma and fulanin marma in Malam
madori Constituency. Limis Brothers & Co. M/madori 5,164,110.00 5,164,110.00 5,151,199.72 18/12/2018 6 weeks 100 Completed
152
Co ns truc tio n o f Hand P ump Bo reho les Water Supply
Schemes Co ns tituency P ro jec ts (2018 P has e II) Lo t-9 a t
Unguwar Sa idu, Fulanin Madachi, Unguwar s hege Unguwar
ka le ,Ufa la Fulanin Farjak, Gunzara , Zankawa, Gidan Wada
Daurawa, Gas a tanni Garki, Fulanin Raira i, Tafin Sa le , Kita ,
Yarkures he , Unguwar Gayya , Fulanin Dandara i, Kargo
Sabuwar Unguwa, Gidan Baki, Barmawa Gari, Abdawa
muku Ward, Rigar Hardo Ibrahim Ko re , Rigar Us man Mai
Bare , Ko re Sabuwar Unguwa, Gwadayawa, Kukar mekiya ,
Garin Makera , Rigar Malam Adamu kugi, Ko far Gidan
Na 'abi Garki, Ko far Gidan Liman Garki and Ko far Gidan
Cic i Garki in Garki Co ns tituency. ALLAH Abin Dogara Nig. Ltd. Garki 22,121,190.00 22,121,190.00 22,121,190.00 18/12/2018 12 weeks 100 Completed
153
Construction of Water Collection Point as
Constituency Projects (2018 Phase II) Lot-27 at
Umboro, Aujara, Kwanar Garki, Siyore Cikin Gari,
Magarya Garki and Sabuwar Unguwa in Garki
Constituency. ALLAH Abin Dogara Nig. Ltd. Garki 7,562,094.00 7,562,094.00 7,562,094.00 18/12/2018 8 weeks 100 Completed
154
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-11 at Rigar Wakili Ya'a, Zubafinji,
Jarmari, Kwanar mai Labbo, Garin Malam S/Guga
and Tasgan Yamma in Guri Constituency. Limis Brothers & Co. Guri 4,426,380.00 4,426,380.00 4,415,314.05 18/12/2018 6 weeks 100 Completed
155
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-4 at Bulangori in Buji Constituency. Limis Brothers & Co. Buji 737,625.00 737,625.00 735,780.93 18/12/2018 4 weeks 100 Completed
156
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-4 at Gogel Kukuma, Rigar Shehu Kado
Kukuma, Dakawa Danbazau and Galadima Bebeji in
Buji Constituency. Limis Brothers & Co. Buji 2,950,920.00 2,950,920.00 2,943,542.70 18/12/2018 6 weeks 100 Completed
Balance C/F 1,618,189,790.81 1,726,490,834.86
2q
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,618,189,790.81 1,726,490,834.86
157
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase II) Lot-17 at
Farar Dutsanya and Gizo in Kazaure Constituency. Yanduna Ventures Ltd. Kazaure 1,472,730.00 1,472,730.00 1,472,730.00 18/12/2018 8 weeks 100 Completed
158
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) at Takwardawa, Roni Gabas, Kalage
Gabas, Kwanar Ganji, Dage Baderi and Bahe Elde
in Roni Constituency. Hikima Synergy Gen. Enterp. Roni 4,422,096.00 4,422,096.00 4,411,040.76 18/12/2018 8 weeks 100 Completed
159
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-16 at Roni Mission, Ruwan Dutse,
Jahoko, Rahamawa A. Roni and Marke in Roni
Constituency. Hikima Synergy Gen. Enterp. Roni 3,687,600.00 3,687,600.00 3,678,381.00 18/12/2018 8 weeks 100 Completed
160
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-1 at Fulanin Tudun Yola, Jammutum
Arewa, Fulanin Aunaka, Koko and Rubunji in
Babura Constituency. Mufabamex Concept Nig. Ltd. Babura 3,688,650.00 3,688,650.00 3,679,428.38 18/12/2018 8 weeks 100 Completed
161
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-7 at Gidan Nakuka, Makawai Fulani,
Fulanin Dandidi (4No.), Gidan Kato Furya, Gidan
badawai, Fulanin Mai adu'a and Kukule in
Gagarawa Constituency. Farham Synergy Concept Ltd. Gagarawa 7,374,150.00 7,374,150.00 7,374,150.00 22/12/2018 8 weeks 100 Completed
162
Upgrading and Conversion of Motorized Boreholes
to Solar Powered Water supply Scheme at
Mairakumi Town in Malam madori L. G. A. (Hadejia
Zone). Sims Global Resources Ltd M/madori 14,518,546.88 14,518,546.88 13,827,187.50 31/12/2018 8 weeks 100 Completed
163
Conversion of Motorized Pumps to Solar Powered
Water supply Scheme at Jama'are pump station in
K/hausa L.G.A. Sims Global Resources Ltd K/Hausa 14,998,281.46 14,998,281.46 14,284,077.58 31/12/2018 8 weeks 100 Completed
164
Conversion of Motorized Pumps to Solar Powered
Water supply Scheme at Unguwar kudu in Auyo
L.G.A. Sims Global Resources Ltd Auyo 16,809,055.11 16,809,055.11 16,008,623.91 31/12/2018 8 weeks 100 Completed
165
Construction of (1No.) Solar Powered Water supply
Schemes (2018 Phase III) Lot-42 at Medu Town in
Gagarawa Constituency. Dantatu Gen. Constr. Eng. Gagarawa 6,023,010.00 6,023,010.00 6,023,010.00 31/12/2018 8 weeks 100 Completed
Balance C/F 1,691,183,910.26 1,799,484,954.31
2r
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,691,183,910.26 1,799,484,954.31
166
Construction of (1No.) Solar Powered Water supply
Schemes (2018 Phase III) Constituency Projects Lot-
46 at Magaji Kufai in Gagarawa Constituency. A.A. Aljazeera Agro Proc. Gagarawa 6,023,010.00 6,023,010.00 6,023,010.00 23/11/2018 8 weeks 100 Completed
167
Construction of new Solar Powered Pump Water
supply Schemes at Babura Tsallake in Babura
L.G.A. Sims Global Resources Ltd Babura 25,563,695.34 25,563,695.34 24,346,376.25 31/12/2018 8 weeks 100 Completed
168
Construction of Water Collection Points Water
supply Schemes Constituency Projects (2018
Phase II) Lot- 25 at Giginya, Achiya, Babura
Tsallake, Garin Ganau, Marken Biki, Gurfai,
Yammaulu, Botsotsuwa and Kwando in Babura
Constituency. Mufabamex Concept Ltd. Babura 11,037,269.25 11,037,269.25 11,009,679.08 18/12/2018 10 weeks 100 Completed
169
Construction of Water Collection Points
Constituency Projects (2018 Phase III) Lot- 20 at
Babura Islamiyya, Gangara Hanware, Baskwar and
Chirimbi in Babura Constituency. Mufabamex Concept Ltd. Babura 4,905,453.00 4,905,453.00 4,893,189.32 18/12/2018 8 weeks 100 Completed
170
Construction of Water Collection Points as
Constituency Projects (2018 Phase II) Lot- 30 at
Unguwar Sankira, Kandahar, Kofar Abdullahi
Ranbo, Unguwar Aminu Yusuf and garejin musan 'O'
in Hadejia Constituency. Alh. Umaru Babandoki Ltd. Hadejia 6,131,816.25 6,131,816.25 6,116,486.71 18/12/2018 8 weeks 100 Completed
171
Construction of Water Collection Points as
Constituency Projects (2018 Phase II) Lot-33 at
Gumuma in Roni Constituency. Hikima Synergy Gen. Enterp. Roni 1,226,363.25 1,226,363.25 1,223,297.34 18/12/2018 6 weeks 100 Completed
172
Construction of (30No). Hand Pumps at Tsakuware,
Gidan Hanau (Madatta), Timbau, Bekawa, Sabon
Gari, Kandiren Wailare, Zanguna, Damfar Jigawa,
Tsallake, Rugagen Melefe, Kafin Dan Yayi, Jaunare,
Unguwar Duhuwa, Gidan Gide, Gidan Maja,
Danzago, Naino Sabon Garin Jigawa, Tsugunau,
Garin Baki, Chirimbi Malamai, Rugar Hardo
Hassan, Ribinjin Manzo, Gurfan Batali, Jan Mutum,
Lambar Lululu, Rahar Hanau, Nabai, Kaya Harimi
and Kankaren Nagona in Babura L.G.A. Limis Brothers & Co. Babura 22,138,200.00 22,138,200.00 22,082,854.50 28/12/2018 15 weeks 100 Completed
173
Upgrading and Conversion of (2No.) Motorized
Boreholes to Solar Powered Water supply Scheme
at Gurfai in Babura L.G.A. of Ringim Zone, Garkon
Alli in Kiyawa L.G.A. of Dutse Zone, and
Construction of 1No. New Solar Water Supply
Schemes at Luddaga in Birnin kudu L.G.A. of Birnin
kudu Zone. Sims Global Resources Ltd State 31,275,783.95 31,275,783.95 29,786,460.90 31/12/2018 12 weeks 100 Completed
Balance C/F 1,777,347,301.30 1,885,648,345.35
2s
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,777,347,301.30 1,885,648,345.35
174
Construction of (22No). Hand Pumps at Jankoli,
Unguwar Malam, Doguwar Dorawa, Gidan Kwano,
Bodawa, Digawar Kwando, Babajiya, Gidan Gitti,
Shafa, Kyara, Gage, Yantuba, Kaliya Jemawa,
Karkafawa, Fulanin Danmarke, Adugul Fulani,
Danmakera, Waje, Fulanin Masko and Aunaka Gari
in Babura L.G.A. Sir Welter Drilling & Gen. Serv Babura 16,234,680.00 16,234,680.00 16,194,093.30 28/12/2018 12 weeks 100 Completed
175
Construction of 50No Hand Pumps Boreholes at 50
Communities Across the State Sir Walter & Gen Serv State 36,897,000.00 36,897,000.00 36,897,000.00 5/3/2019 16 week 100 Completed
176
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase II) Lot- 24 at Kawaye, Karkarna Bakin Titi,
Rauda durbe, Gwarta Karama and rauda Asibitin
Yankwashi Constituency. Granitoids Engr. Services Ltd. Yankwashi 3,685,082.10 3,685,082.10 3,675,869.39 18/12/2018 6 weeks 100 Completed
177
S upply a nd ins tla tion of (1nN0.) 30KVA Ge ne ra tor
se t 2018 Cons titue nc y proje c ts (Lots - 40) a t
Da buwa ra n in Ka uga ma c ons tiue nc y Madanta Global nig. Ltd Kaugama 3,740,625.00 3,740,625.00 3,740,625.00 23/11/2018 8 weeks 100 Completed
178
Constr of 11no. Hand pumps water supply
constituency project phase III 2018 (Lot- 7) at
Wallere, S/Gari, Redo, Shinfida, Daragi, Tsamiya,
Kafa Doya, Kundiga, Daurawa, Fara Fulani and
Sabuwar Yola in Gwiwa Jignaj Global Gwiwa 8,113,297.50 8,113,297.50 8,093,014.26 18/12/2018 12 weeks 100% Completed
179
Rehab of Some water supply scheme at Maidabaru
and Nazau in S/tankarkar L.G.A. Centuary Trade Ltd. S/Tankarkar 2,956,078.13 2,956,078.13 2,948,687.93 31/12/2018 8 weeks 100% Completed
180
Rehab and Maintenance of 5no. Water supply
scheme at Limawa A,B,C, Galamawa and Karnaya
in Dutse L.G.A. Limis Brothers & Co Dutse 3,585,192.19 3,585,192.19 3,414,468.75 31/12/2018 4 weeks 100% Completed
181
Rehab of 2no. Water supply Scheme at Dansure,
Roni and Gafaya town in K/Hausa L.G.A. Limis Brothers & Co Roni+K/Hausa 1,584,843.57 1,584,834.51 1,509,375.00 31/12/2018 4 weeks 100% Completed
182
Rehab of 4no. Water supply Scheme at Arbus,
Karoro, Dodorin Malan Audu, and Ronjin in
Kaugama L.G.A. Limis Brothers & Co Kaugama 3,611,204.57 3,611,204.57 3,439,242.45 31/12/2018 4 weeks 100% Completed
183
Rehab of 4no. Small towns water supply schemes
at Albasu main station, Albasu Hospital, Katangar
Lafiya and Chediyar Kuda in Gumel, Dutse and
Kazaure zones. Limis Brothers & Co State 4,932,998.44 4,932,998.44 4,698,093.75 31/12/2018 8 weeks 100 Completed
184
Construction of Water Collection Points as
Constituency Projects (2018 Phase Ii) Lot-32 at
Maigatari, Balarabe, Matoya, Bosuwa, Galadi,
Madana and Jajeri in Maigatari Constituency JAG & H Integrated Maigatari 8,822,443.00 8,822,444.00 8,822,444.00 14/1/2019 8 Weeks 100 Completed
Balance C/F 1,871,510,745.80 1,979,811,781.79
2t
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,871,510,745.80 1,979,811,781.79
185
Construction of 1no Solar Powered water supply
scheme at Nafara in Kiyawa LGA, Dutse Zone Sims Global Resources Kiyawa 6,023,325.00 6,023,325.00 6,023,325.00 16/4/2019 8 weeks 100 Completed
186
Construction of 4No. Solar Powered Water supply
scheme at Danmarke, Wada,Kayarda and Garin
Baki in Babura LGA Ringim Zone Sims Global Resources Ringim 24,093,300.00 24,093,300.00 24,093,300.00 16/4/2019 12 Weeks 100 Completed
187
Rehabilitation of 2No Small Towns water supply
schemes at Yandamo and Malam Baki in Gumel
Zone Forte Technical Services Ltd Gumel 8,482,573.26 8,482,573.26 8,078,641.20 31/5/2019 8 weeks 100 Completed
188
Construction of 12No Hand Pump Boreholes water
supply schemes at Sule Fulanin Yandamo ( Gidan
Mallam) Fulanin Kwalawa( Gidan Kato dan Goma),
Fulanin dan Kiri ( Gidan Dan Bako) Garin Goto,
Fulanin Kukule Gabas ( Gidan Isah Kato) Fulanin
Malam Kadiri ( Gidan Sale), Fulanin Dantuwo (
Gidan Ingire), Dan Adama Gari, Fulanin Dan Adama
( Gidan Abdullahi), Dankira, Sabon Garin Dankirya
and Fulanin dan Kumbo ( Gidan Hardo Kan Doki) in
Sule Tankarkar Local Government Area Gumel
Zone. Al-Juraj Synergy Concept S/tankarkar 8,855,280.00 8,855,280.00 8,855,280.00 8/5/2019 12 weeks 100 Completed
189
Construction of 15No. Hand Pumps Boreholes
water supply scheme at Sinti, Garin Goshi, Fulanin
Masama ( Hardo Tamabya) Dantuwo Gari,
Dantuwo Tsangaya, Tashar Bala S/Tankarkar,
Balarabe Mai Gari, Fulanin Jalko( Gidan Rabiu)
Hardo Dan Kawo ( Fulanin Kuka Maidire), Sabon
Garin Dan Yarda, Fulanin Dan Banki ( Gidan
Sha'aibu Jikan Hajja), Fulanin Tiriki ( Hardo Ilu),
Fulanin Charko(Gidan Dabbi) and Ma'azu Gidan
Salisu Tifa in Sule Tankarkar Local Government
Area, Gumel Zone Al-Kawakeb Global Concept S/Tankarkar 11,069,100.00 11,069,100.00 11,069,100.00 8/5/2019 12 weeks 100 Completed
Balance C/F 1,921,551,750.80 2,029,852,786.79
2u
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,921,551,750.80 2,029,852,786.79
190
Construction of 22No Hand Pump Boreholes water
supply schemes at Yandamo gari A, Yandamo Gari
B, Garin Yasai, Hardo Jauro, Kargo, Fulanin Lula,
Madoji Tsalle, Fulanin Barnawa Fulanin Bayan Eka
STK, Fulanin Santarbi, Dangoho, Fulanin Mai Rago (
Yamma) Buntusu Fulani, Fulanin Hardo Musa
S.Tankarkar Fulanin Kurguna, Fulanin Kaina
unguwar Yamma ( Danzomo) in Sule Tankarkar LGA
and Kwanar Tsuru, Garin Kwalandi, Garin Malam,
Gabasawar Kwalandi and Fulanin Shabarawa (
Gidan Ibrahim Bidu) in Maigatari LGA Forte Technical Services Ltd Maigatari 16,234,680.00 16,234,680.00 16,194,093.30 8/5/2019 12 weeks 100 Completed
191
Construction of 2No. New Solar Powered Water
supply Schemes at Malarin Gamm in Malam
Madori Local Government Area and Walawa in
Birniwa Local government Area Hadejia Zone BSY Industries Nig Ltd M/madori + Birniwa 12,046,650.00 12,046,650.00 12,016,533.37 31/05/2019 8 weeks 100 Completed
192
Rehabilitation of 17no. Small towns water supply
schemes at hadejia and Jahun Zone BSY Industries Nig Ltd Hadejia + Jahun 5,161,739.63 5,161,739.63 4,915,942.50 31/05/2019 8 weeks 100 Completed
193
Procurement of Assorted Submersible pumps
Across the State Umar Aliyu & Sons Nig Ltd Across the state 19,479,796.87 19,479,796.87 18,552,187.50 16/4/2019 8 Weeks 100 Completed
194
Procurement of 2No. 200KVA Perkins Generating
Set for Kazaure and Birnin Kudu Zone Limis Brothers & Co B/Kudu 28,619,712.07 28,619,712.07 28,619,712.07 16/4/2019 8 Weeks 100 Completed
195
Extension of Pipe borne water supply line (Lot-27)
phase III-2018 Constituency project at Achauya
village in S/Tankarkar . Pullad S/Tankarkar 3,647,700.00 3,647,700.00 3,647,700.00 31/12/2018 8 weeks 100 Completed
196
Constr of Solar Water Scheme at Hammadi in
Babura Constituency Mufabamax Nigeria Ltd. Babura 6,020,700.00 6,020,700.00 6,005,648.25 17/10/2018 8 weeks 100 Completed
197
Constr of 6no. Hand pumps boreholes (2018 phase
III) Constituency projects at Gidantawa, Ganzayi A,
Gidan Chaya, K/Hausa basen Asibiti, Kanzan
Masarafa and Yam Darma Element in K/Hausa
Constituency. Dantatu Nigeria Ltd. K/Hausa 4,426,380.00 4,426,380.00 4,415,314.05 18/12/2018 8 weeks 100 Completed
198
Constr of Solar water Scheme at Ando in Babura
Constituency Mufabamax Nigeria Ltd. Babura 6,020,700.00 6,020,700.00 6,005,648.25 17/10/2018 8 weeks 100 Completed
199 Constr of 45no. Hand pumps Boreholes at Babura Safah & Fresh Int. Babura 33,207,300.00 33,207,300.00 33,207,300.00 7/3/2019 16 weeks 100 Completed
Balance C/F 2,027,797,397.30 2,136,098,433.29
2v
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 2,027,797,397.30 2,136,098,433.29
200
Constr of Solar water scheme at Madari in Kanya
Babba Constituency Mufabamax Nigeria Ltd. Babura 6,023,115.00 6,023,115.00 6,008,057.21 21/12/2018 8 weeks 100 Completed
201
Constr of Solar water supply scheme at Gayana
Tudu in Gagarawa L.G.A. Limis Brothers & Co Gagarawa 6,023,005.00 6,023,115.00 6,008,057.21 20/5/2019 8 weeks 100 Completed
202 Constr 2no Bore holes at Hadejia LGA Limis Brothers & Co Hadejia 1,254,519.00 1,254,519.00 1,251,382.70 28/12/2018 4 weeks 100 Completed
203
Rehab of Water Scheme at Dadda in Stankarkar
LGA Guidence Agency for Excellence S/Tankarkar 1,447,031.25 1,447,031.25 1,443,413.67 8/1/2019 4 weeks 100 Completed
204
Constr of 3no. Hand pumps water supply (Lot-14)
phase III 2018 Constituency projects at Sabuwar
Kwalta, Rugar Zargu, and Dakuna town in
M/madori Constituency. Express Innovation Co. Ltd. M/madori 2,213,340.00 2,213,340.00 2,207,806.65 14/01/2019 8 weeks 100 Completed
205
Rehab of Madoji solar water Scheme at Abanderi
in S/Tankarkar LGA Giant Tech Ltd. S/Tankarkar 1,667,531.25 1,667,531.25 1,588,125.00 3/6/2019 4 weeks 100 Completed
206
Constr of solar water Scheme at Abanderi in Dutse
LGA Limis Brothers & Co Dutse 4,598,493.32 4,598,493.32 4,379,517.45 31/12/2018 8 weeks 100 Completed
207
Co ns tr o f (38No ) Hand P umps a t Makadi'B ', Gangara
waje , jiji'B ' Unguwar Sama, Gidan Hardo Gawo , Gidan Beti
dan Maigari, bo dawa C, Unguwar Ts amiya B, GJ ASS
Baura , GGADSS Babuura , Ts adura , Babura Arewa B,
Kaute B, in babura LGA, Duts e Capita l Scho o l in Duts e ,
unguwar Lawan in J ahun, tunubu to wn in J ahun, kuka in
/S /Tankarkar, Gidan Danta Fulani, Kanawa Aume, dan
Amale Fulani, Gage Yamma, J e lawa Damu, Kauyen Fulani
HP in babura LGA, Shamuri HP in S /Tankarkar, Tinubu,
Hayin Tara Yamma in J ahun, Burukum Fulani, Gidan
Makeri, Minu, Unguwar Magaji, Ba ta li, Malamawa, Bikawa
Bata li, Muni A, Gidan Dawa and Dan Makeri G/Nagawo in
Babura LGA Bulangu Drilling Babura 28,041,729.00 28,041,729.00 28,041,720.00 9/8/2019 14 weeks 100 Completed
208
Upgrading and Co nvers io n o f 1No . Mo to rixzed water
s upply s cheme to s o la r po wered a t Maizuwo in Sule
tankarkar LGA Sims Glo ba l Res o urces S/Tankarkar 6,829,987.50 6,829,987.50 6,504,750.00 6/8/2019 4 weeks 100 Completed
209
Upgrading and Co vers io n o f 1No . Mo to rized water s upply
s cheme to s o la r po wered t Gangara in Babura LGA Sims Glo ba l Res o urces Babura 6,829,987.50 6,829,987.50 6,504,750.00 6/8/2019 4 weeks 100 Completed
210
Rehabilitation of 6no water scheme in Hadejia,
Gimel and Jahun, Zones Limis Brothers & Co State 5,047,035.00 5,047,035.00 5,047,035.00 23/11/2018 6 weeks 100 Completed
211
Rehab of 3no water schemes in Gumel and Jahun
zones Limis Brothers & Co Gumel+Jahun 4,089,750.00 4,089,750.00 4,089,750.00 20/08/2019 6 weeks 100 Completed
212
Rehab of 4no water schemes in Ringim and
Hadejia zones Sims Global Ringim + Hadejia 7,543,200.00 7,543,200.00 7,543,200.00 20/02/2019 6 weeks 100 Completed
213
Rehab of 6no water schemes in Auyo, K/kasamma
& hadejia Sims Global
Auyo +
K/kasamma
+Hadejia 7,660,800.00 7,660,800.00 7,660,800.00 20/8/2019 6 weeks 100 Completed
214
Rehab of 10no water schemes in Hadejia,
M/madori, Kaugama, Birniwa, Guri & Auyo Sims Global State 7,660,800.00 7,660,800.00 7,660,800.00 20/8/2019 6 weeks 100 Completed
215
Rehab of 10no water schemes in Ringim and
Gumel zones Sims Global Ringim + Gumel 7,541,100.00 7,541,100.00 7,541,100.00 20/8/2019 6 weeks 100 Completed
Balance C/F 2,132,268,821.12 2,240,569,967.11
2w
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 2,132,268,821.12 2,240,569,967.11
216
Rehab of 9no water schemes in Ringim, Kazaure
and Dutse zones Sims Global State 6,413,400.00 6,413,400.00 6,413,400.00 20/8/2019 6 weeks 100 Completed
217
Constr of 1no Solar water supply schemes at
Achau in Jahun LGA Loyalty Properties Ltd. Jahun 6,023,325.00 6,023,325.00 6,023,325.00 15/01/2019 8 weeks 100 Completed
218
Maintenance of Generators in Gumel from Dec,
2017 to Dec, 2018 Marbs Eng. Ltd. Gumel 2,607,937.50 2,607,937.50 2,607,937.50 20/12/2017 24 months 100 Completed
219
Maintenance of 2no. Generators in Babura town
from Dec, 2017 to Dec, 2018 Marbs Eng. Ltd. Babura 582,750.00 582,750.00 582,750.00 1/12/2017 24 months 100 Completed
220
Maintenance of 4no.Generators in Ringim town
from Dec, 2017 to Dec, 2018 Marbs Eng. Ltd. Ringim 2,945,908.25 2,945,908.25 2,945,908.25 3/11/2018 24 months 100 Completed
221
Maintenance of 3no.Generators in Ringim town
from Dec, 2016 to Dec, 2017 Marbs Eng. Ltd. Ringim 2,802,187.50 2,802,187.50 2,802,187.50 21/12/2016 24 months 100 Completed
222
Maintenance of Generators inBabura town from
Dec, 2017 to Dec, 2018 Prestige Integ. Services Babura 582,750.00 582,750.00 582,750.00 1/12/2017 12 months 100 Completed
223
Constr of 22no Hand pumps in K/kasamma
constituency (phase III 2018) Lot-13 Dabino Internation Ltd. K/kasamma 16,230,060.00 16,230,060.00 16,230,060.00 31/12/2018 12 weeks 100 Completed
224
Constr of Solar Powered Water Supply Schemes
Constituency Project ( 2019 Phase 1) Lot-42 at
Kilawa in Fagam Contituency. Jignaj Global Contr Ltd Gwaram 6,023,220.00 6,023,220.00 6,023,220.00 11/12/2019 8 weeks 100 Completed
225
Upgradingand Conversation of 1no. Motorised
water Supply Scheme (2019 phase1 ) Constituency
Project Lot-22 at Zauma in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 8,685,075.00 8,685,075.00 8,685,075.00 11/12/2019 8 weeks 100 Completed
226
Upgradingand Conversation of 1no. Motorised
water Supply Scheme (2019 phase1 ) Constituency
Project Lot-23 at Korayalin Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 6,863,325.00 6,863,325.00 6,863,325.00 11/12/2019 8 weeks 100 Completed
227
Renov of 2no. Solar Powered water Supply
schemes Contituency project ( 2019 Phase 1) Lot-
24 at Gidan Kudege and Kurneji in Gwiwa
Constituency Jignaj Global Contr Ltd Gwiwa 3,227,700.00 3,227,700.00 3,227,700.00 11/12/2019 8 weeks 100 Completed
228
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 41 at
tsallakawa in Fagam Constituency, Gwaram Local
Government Area Jignaj Global Contr Ltd Gwaram 6,023,220.00 6,023,220.00 6,023,220.00 11/12/2019 8 weeks 100 Completed
Balance C/F 2,201,279,679.37 2,309,580,825.36
2x
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 2,201,279,679.37 2,309,580,825.36
229
Upgrading and Conversion of Zaburan, Small Town
Motorised Water Supply Scheme to Solar Powered
in Kaugama Local Government Area. Sims Global Resources Nig Ltd Kaugama 16,917,862.50 16,917,862.50 16,112,775.00 6/8/2019 8 weeks 100 Completed
230
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-4 at wuro bagga, gamawari, yola
zairare, fulanin takaje, sabon gidan gabas, fulanin
kufayi, hijabau, adamante, rugar abdul kogi,
masharmo, makwasharga, waryam B, lautayi,
Yambo, Jalingo G/kwalli, kawarin gari, yadda,
gidan yauto (Z/kanya), gumurwa G.A Idi, Rimin
kasuwa and shamakeri B/hanya in Bulangu
constituency Bulangu drilling serveices LtdK/Hausa 15,491,227.50 15,491,227.50 15,491,227.50 11/12/2019 12 Weeks 100 Completed
TOTAL 2,233,688,769.37 2,341,989,915.36
2y
Ministry of Works
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Constr. of Internal Road Netw ork and Drainage at College of Agriculture YamidiAmirco Univ ersal Concept Hadejia 114,852,386.25 499,296,564.31 499,296,564.31 6/10/2011 20 w eeks 100 Completed
2 Reconstr. Of Asphaltic concrete ov erlay of Kijaw al-Dabi road (4.5km) Triacta Nig. Ltd. Ringim 453,412,679.27 526,840,847.35 526,837,028.02 18/3/2013 3 months 100 Completed
3 Urban Tow ns Streetlight Projects at Karkarna Tow n Stratrade Nig. LTD Yankw ashi 234,338,917.73 234,338,917.73 230,270,845.40 11/11/2013 6 Months 100 Completed
4
Commissioning as Consultant for the Superv ision of the Constr. of Gumel-
G/Gambo, feeder roads, M/madori-Dakido, Shafar-G/sani OPIQ Consultant LTD. Gumel 16,024,856.75 16,024,856.75 16,024,856.75 3/3/2014 6month 100 Completed
5 Constr. of feeder road at gumel-Garin Gambo in Gumel L.G.A. Omega Stars Nig. Ltd. Gumel 149,763,131.44 149,763,131.44 149,763,131.44 13/02/2014 6 months 100 Completed
6 Consulltancy serv ices for the Constr. Of Kiy ako-Zarenaw a feeder road UKM Civ il Eng. Consultant B/kudu 16,187,482.45 16,187,482.45 16,187,482.00 2/2/2014 8 months 100 Completed
7
Commissioning as consultant for the superv ision of Kazaure tow nship roads
(15KM) Wuro Associate Kazaure 92,141,988.97 92,141,988.97 85,842,229.66 5/9/2013 8 months 100 Completed
8
Commissioning as Consultant for the Constr. of Sule Tankarkar Tow nship
roads Thamar Eng. Ltd. S/tankarkar 64,638,503.00 64,638,503.00 58,339,028.04 13/02/2014 12 months 100 Completed
9 Re-Constr. of Sule Tankarkar Tow nship road (5.16km) Afdin Constr. Co. Ltd. S/tankarkar 727,649,360.56 909,561,700.70 857,941,087.50 4/4/2016 8 months 100 Completed
10 Cons. of Handpumps Across the State (RUWASA) Muhabib Nig. Ltd State 28,000,000.00 28,000,000.00 26,000,013.06 3/1/2014 4month 100 Completed
11
Supervision of the construction of Maigatari-Galadi-Girbobo-
Diginsa-Birniwa Road (Phase II) (37.1KM) HIMMA TECH SERV. Birniwa 74,761,966.60 74,761,966.60 74,760,523.27 18/05/2017 13 months 100 Completed
12
Supply and installation s of 150 Units Integrated stand alone Solar
Powered Streetlight at Aujara in Jahun Local Govt Area Sims Nig. Ltd. Jahun 95,192,680.94 95,192,680.94 90,659,703.75 14/12/2017 12 weeks 100 Completed
13
Constr of Dutse-Madobi-Katanga-Dangoli with Spur from Madobi to
Baranda road (35.7km) Lot -1 Gerawa Global Eng Ltd. Dutse 4,643,482,872.42 4,643,482,872.42 4,640,482,872.21 27/4/2018 12 months 100 Completed
14
Rehab/Asphalt Overlay of Babura-Yarkirya-Kuzunzumi road
(49.4km) lot -5 Gerawa Global Eng Ltd. Babura 4,944,415,159.06 4,944,415,159.06 4,941,128,617.95 27/4/2018 8 months 100 Completed
15
Constr of Access road from Harbo Sabuwa to Harbo Tsohuwa
(1.52km) lot-9 Retercha Co. Ltd. Jahun 241,058,058.35 241,058,058.35 240,921,302.79 27/4/2018 4 months 100 Completed
16
Constr of Bariki-Munzarau-Tawakkalta-Turabu road (16.8km) lot-
6 CGC Nig. Ltd. Hadejia 2,919,955,823.72 2,919,955,823.72 2,919,634,562.05 4/5/2018 12 months 100 Completed
17
Electrification project at Katurje in Kafin Hausa Constituency, Kafin
Hausa LGA. Kawu Nig. Ltd. K/Hausa 10,916,014.48 10,916,014.48 10,023,514.47 10/5/2018 16 weeks 100 Completed
18
Commissioning as Consultant for the Supervision of the Constr. of
Babura township roads (10.28km) UKM Civil Eng. Babura 45,933,233.82 45,933,233.82 45,933,237.82 7/6/2018 10 months 100 Completed
19
Commissioning as Consultant for the Supervision of the
Rehab./Asphalt Concrete Overlay of Babura-Yarkirya -Kuzunzumi
road (49.4km) HAG Eng Consultants Babura 86,527,265.28 86,527,265.28 86,212,265.27 7/6/2018 8 months 100 Completed
20
Supply and Installations of Integrated Standalone Solar Powered
Streetlight at Yalleman Town in Kaugama LGA SIMS Nig. Ltd. Kaugama 85,276,275.00 85,276,275.00 82,792,500.00 25/9/2018 3 months 100 Completed
21 Constr of Gadadin-Jigawar Sarki road (600m) in Dutse LGA. Retercha Company Ltd Dutse 64,554,624.07 64,554,624.07 64,554,624.07 20/12/2018 3 months 100 Completed
22 Constr. Of Kaugama-Mallam Madori Feeder Road (19.31km) Lot-15 IGEE Eng. Ltd. M/madori 520,687,101.38 520,687,101.38 520,082,820.60 21/12/2018 6 months 100 Completed
23
Construction of Hammado-Danfarantama-mele-Balkarya-Kokinami-
Limanmado-Barikin faka-Gumel Feeder Road (33.0KM) Lot 17. Babandoki Gen. Enterp. Gumel 911,985,078.38 911,985,078.38 911,971,052.16 21/12/2018 6 months 100 Completed
Balance C/F 16,541,755,459.92 17,181,540,146.20
3a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOC A T ION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 16,541,755,459.92 17,181,540,146.20
24
Construction of Kazaure - Gallu Babba - Karkarna Feeder Road
(16.0KM) Lot 13. China Zhanghao Nig. Ltd.Kazaure/Yankwashi 527,255,190.00 527,255,190.00 527,223,814.03 27/12/2018 6 months 100 Completed
25
Construction of Kanya Babba - Kankare - Ballada - Duzau - Dan
Halili - Kyambo - Mundu - Goran Maje Feeder Road (19.KM) Lot 18. A.Y.A. Logistics & Constrt Ltd. Babura 512,115,693.47 512,115,693.47 511,568,526.00 24/12/2018 6 months 100 Completed
26 Construction of Kanya Babba Township Road (2.0KM) Lot 10. Mother Cat Nig. Ltd. Babura 346,070,232.61 346,070,232.61 343,974,392.46 24/12/2018 6 months 100 Completed
27
Rehabilitation of Hadejia - Aguyaka - Gudincin Road (4.30KM) Lot
13. Centralead Nig. Ltd. Hadejia 972,823,696.47 972,823,696.47 923,431,810.86 24/12/2018 8 months 100 Completed
28 Electrification Project at Masanawa in Kiyawa L.G.A. Nabakwai Gen. Enterprises Kiyawa 19,149,196.14 19,149,196.14 18,810,572.61 24/12/2018 12 weeks 100 Completed
29 Electrification Project at Hambarawa in Ringim L.G.A. Al-Majeed Constr. Nig. Ltd Ringim 14,261,545.68 14,261,545.68 14,236,065.78 24/12/2018 12 weeks 100 Completed
30 Electrification Project at Gidan Garke in Ringim L.G.A. Al-Majeed Constr. Nig. Ltd Ringim 13,314,314.45 13,314,314.45 13,290,203.07 24/12/2018 12 weeks 100 Completed
31 Electrification Project at Guntai in Gwiwa L.G.A. H & N Engr. Consultancy Gwiwa 38,057,153.66 38,057,153.66 38,055,053.50 24/12/2018 16 weeks 100 Completed
32
Maintenance of Failed Section of Auyo - Kafin hausa Road (100)
Section 'B' Retercha Company Ltd Auyo 51,175,143.02 51,175,143.02 51,083,760.00 31/12/2018 12 weeks 100 Completed
33 Electrification Project at Kanya Babba - Muna in Babura L.G.A. Deetech Nig. Ltd. Babura 29,981,471.52 29,981,471.52 27,374,387.04 24/12/2018 16 weeks 100 Completed
34
Maintenance of Failed Section of Auyo - Kafin hausa Road (150)
Section 'A' Retercha Company Ltd K/hausa 69,533,544.12 69,533,544.12 69,392,935.50 31/12/2018 12 weeks 100 Completed
35 Electrification Project at NTA Hadejia in Hadejia L.G.A. Xtra X-99 Integ. Services Hadejia 19,427,729.87 19,427,729.87 19,419,923.62 31/12/2018 12 weeks 100 Completed
36 Electrification Pro ject at Sambo Primary School Hadejia in Hadejia L.G.A. A+Techn. Integ. Services Hadejia 14,876,542.55 14,876,542.55 14,087,057.64 31/12/2018 12 weeks 100 Completed
37Construction of B lock Line Drainages (738M ) at Basirka Town in Gwaram
L.G.A. Pullad Global Consultant Gwaram 22,726,861.79 22,726,861.79 22,726,861.79 24/12/2018 12 weeks 100 Completed
38Supply and Installations of 130 Units Integrated Standalone Solar Powered
Streelight at Danzomo in Sule Tankarkar L.G.A Sims Nigeria Limited S/Tankarkar 82,515,030.00 82,515,030.00 74,843,565.00 1/17/2018 16 weeks 100 Completed
39Supply and ins tla tio n o f s tanda lo ne s o la r po wer s tree tlight a t Bekarya , mele
and Danmano mi to wns in Gumel LGA Sims glo ba l res . Nig ltd Gumel 91,008,225.00 91,008,225.00 88,200,000.00 22/11/2018 16 weeks 100 Completed
40 Co ns tr o f ro ad Netwo rk a t Co llege o f Educa tio n, Gumel (3.3km) lo t-4 H & M Nig. Ltd. Gumel 674,198,072.42 674,198,072.42 672,895,458.69 30/4/2018 6 mo nths 100 Completed
41 Co ns tr o f Gadadin-J igawar Sarki ro ad, Duts e (600m) Retercha Co . Ltd Duts e 64,554,624.07 64,554,624.07 64,146,465.81 20/12/2018 3 mo nths 100 Completed
42
Supply and Installations of Integrated Standalone Solar Powered Streetlight
at Hammado-Gagarawa (200 Unit) Bosuwa (100 Unit) iri (100 Units) M anga-
Takwasa (120 Unit) and Unguwar Gawo-Batali-Kuzunzumi-Balarabe (200 unit)
Total 720 Units (Lot 2) SIM S NIGERIA LTD Gagarawa 430,360,875.00 430,360,876.00 430,349,174.12 12/2/2019 14 Weeks 100 Completed
43Construction of block line drain and Filling of Low Area in M ajia Community
o f Taura LGA Ummukhulsum Invest Taura 86,485,008.42 86,485,008.42 86,470,998.89 20/06/2019 6 month 100 Completed
44
Supply and Installation of inytegrated standalone Solar Powered Streetlight
at buji (150 Units), Basirka/Digijin (120 Units), Kudai (100 Units), balanngu-
Sarawa (100 Units) Garin Gabas (160 Units) and Birniwa Tasha (100 units)
Total 710 units (Lot-1) Arrayan Ventures Global State 403,649,600.00 403,649,600.00 392,133,000.00 16/4/2019 14 weeks 100 Completed
45Commissioning as Consultant for the Supervision of the Construction of
Kazaure-Fanda-Sabaru-Gallu-Karkarna Feeder Road (16km) UKM Civil Engineering
Yankwashi
+Kazaure 9,226,965.83 9,226,965.83 9,226,965.82 20/3/2019 6 weeks 100 Completed
Balance C/F 21,034,522,176.01 21,674,306,863.29
3b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOC A T ION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 21,034,522,176.01 21,674,306,863.29
46
Commissioning as consultant for the Supervision of the Supply and
Installation of Intergrated Standalone Solar Powered Streetlights at Buji 150
units, Basirka/Digijin 120 Units, Kudai 100 Units, Bulangu-Sarawa 100 units,
garin Gabbas 160 units and birniwa Tasha 100 Units (to tal 710 Units) ARDUGAL Engineering Ltd State 7,606,368.00 7,606,368.00 6,606,368.00 26/3/2019 4 months 100 Completed
47
Commissioning as Consultant for the Supervision of the Supply and
Installation of Integrated Standalone Solar Powered Streetlights at
Hammado-M aituruniya-Duhuwa-Gangar 200 Units, Bosuwa 100 units, Kiri 100
units, M anga-Takwasa 12 units and unguwar Gawo-Bataki-Kuzunzumi-
Balarabe 200 units (Total 720 units) Secwave Nigeria Limited State 7,531,315.31 7,531,315.31 7,531,315.31 26/3/2019 4 months 100 Completed
48
Commissioning as consultant for the supervision of the construction of
sada-Kanawa-Dankari-Nasarawa-Kuda Feeder Road (11.2km) UKM Engineering Consult Yankwashi 6,889,699.73 6,889,699.73 6,337,767.06 10/4/2019 6 M onths 100 Completed
49
Rehabilitation of ITC line from Kwanar Gawo to Hago in Kafin Hausa Local
Government Area Tasiu M uhammad Invest Ltd K/Hausa 8,333,050.69 8,333,050.69 8,333,050.56 10/7/2019 8 weeks 100 Completed
50
Re-Construction of the damaged sections of Abunabo-Kadira-Guri Road
(Phase-III o f Eastern Bye Pass) CGC Nig Ltd Guri 50,000,000.00 50,000,000.00 7,936,238.63 15/07/2019 10 weeks 100 Completed
51
Rehabilitation of Karshi-Gagarawar Karshi ITC Line and Extension of Farin
Gida TDN in Ringim Local Government Area, Rehabilitation of Yandutse-
M alamawar Yandutse ITC in Ringim LGA Almajeed Constr Ltd Ringim 11,391,654.86 11,391,654.86 11,391,654.01 30/07/2019 10 weeks 100 Completed
52 Supply & Installation of Solar streetlight at Emir's Drive, Dutse Arrayyan Global Vent Dutse 17,319,500.00 17,319,500.00 16,563,750.00 31/7/2019 8 weeks 100 Completed
53
Supply & Installation of Stand alone so lar powered streetlight at Government
Girls Arabic Secondary School Babura, Government Girls Unity Secondary
School Gwaram & Computer Girls Secondary School Roni. Sims Global Res State 60,780,300.00 60,780,300.00 60,767,338.01 31/7/2019 12 weeks 100 Completed
54
Supply and Ins ta lla tio ns o f Integra ted S tanda lo ne So lar P o wered Stree tlights
a t GGASS Sule Tankarkar, GGSSS Taura and Mo del Bo arding P rimary
Scho o l, Gumel SIMS Nigeria Limited State 75,380,550.00 75,380,550.00 73,185,000.00 11/9/2019 12 weeks 100 Completed
55 Supervis io n o f Gumel to wns hip ro ads Himma Tech. Services Gumel 17,440,289.13 17,440,289.13 17,044,289.12 20/3/2019 8 weeks 100 Completed
56 Supervis io n o f J igawar Dan Ali to wns hip ro ads Akram Eng. Babura 7,484,294.27 7,484,294.27 7,484,294.26 20/3/2019 6 mo nths 100 Completed
57 Co ns t o f Gumel to wns hip ro ads (4.73km) Triac ta Nig. Ltd. Gumel 996,587,950.46 996,587,950.46 996,577,850.89 24/12/2018 8 mo nths 100 Completed
58
Supply and Installations of Integrated stadalone Solar Powered
Streetlight at GGASS Birniwa, GGASS Kaugama, Science of Deef
Hadejia and JSSS Guri SIMS Global Resources Across the state 77,002,800.00 77,002,800.00 77,002,800.00 15/10/2019 12 weeks 100 Completed
59 Eletrification project of Gwarzon-Garki Alsabur Global Nig Garki 63,635,819.61 63,635,819.61 62,733,544.82 2/10/2019 12 weeks 100 Completed
TOTAL 22,441,905,768.07 23,081,690,455.35
Ministry of Education
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K DATE PERIOD IN %
1 Constr. of 1no. Block of w orkshop w ith Standard w ork benchs at GSTC Ringim Marb Eng. & Multi-serv ices Ringim 18,564,893.17 18,564,893.17 18,564,893.17 30/12/2016 6 w eeks 100 Completed
2 Constr. of 1no. Block of tw o (2) Science Laboratories at GSTC Ringim Marb Eng. & Multi-serv ices Ringim 28,487,680.00 28,487,680.00 28,487,680.00 30/12/2016 6 w eeks 100 Completed
3
Construction of Block of 2No. Classroom Islamiya (1No.) 3rd Phase 2017
Constituency Projects (Lot-16) at Lautai in Garki Constituency. Jag & H Integ. Serv. Ltd. Garki 3,273,426.45 3,273,426.45 3,115,926.45 6/3/2018 6 weeks 100 Completed
4
Construction of Block of 2No. Classroom Islamiya (3No.) 3rd Phase 2017
Constituency Projects (Lot-7) at Yalwa and Gandum Bundigoma in Malam
madori Constituency. Ramadan Constr. Ltd. M/madori 9,180,832.35 9,180,832.35 8,708,332.34 6/3/2018 9 weeks 100 Completed
5
Construction of 1No. Block of 2No. Classroom Islamiya School (1No.) 2nd
Phase 2017 Constituency Projects (Lot-11) at Gora maikasuwa in Roni
Constituency. Na'ayi Resources Nig. Ltd. Roni 3,272,810.10 3,272,810.10 3,115,310.10 19/3/2018 3 weeks 100 Completed
6
Construction of 1no. Block of 2No. Classroom Islamiya School (1No.) 2nd
Phase 2017 Constituency Projects (Lot-16) at GAJSS Jeke Gari in Sule
Tankarkar Constituency. Khairussabah Nig. Ltd. S/Tankarkar 3,224,219.90 3,224,219.90 3,078,219.90 6/3/2018 6 weeks 100 Completed
7
Construction of 1no. Block of 6No. Classroom Islamiya School (Upstairs
1No.) 2nd Phase 2017 Constituency Projects (Lot-9) at Tsakuwawa in Miga
Constituency. A.G.A. Kilawa Nig. Ltd. Miga 20,735,725.17 20,735,725.17 20,079,272.01 6/3/2018 18 weeks 100 Completed
8
Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS
Amaryawa, Roni LGA (1st phase 2018 projects) (Lot-8) Sabon Garin Yaya Roni 11,734,589.64 11,734,589.64 11649994.83 12/7/2018 6 months 100 Completed
9
Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS
Yankwashi (1st phase 2018 projects) (Lot-9) Sabon Garin Yaya Yankwashi 11,734,589.64 11,734,589.64 11,649,994.83 12/7/2018 6 months 100 Completed
10
Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS
Sakwaya in Dutse LGA. (Lot-10) Steb by Step Integ. Dutse 11,734,589.64 11,734,589.64 11,618,430.78 16/7/2018 6 months 100 Completed
11
Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS
Kwalam in Taura LGA. (Lot-12) Steb by Step Integ. Taura 11,734,589.64 11,734,589.64 11,598,398.71 16/7/2018 6 months 100 Completed
12
Constr of 1-block of 3 classrooms and 1no. Block of 6-seater toilets at GDSS
Garki (1st phase 2018 projects) Lot-6 Yusma Tech Invest. Garki 11,745,517.16 11,745,517.16 11,660,425.90 12/7/2018 6 months 100 Completed
13
Constr of 1-block of 3 classrooms, 1no. Admin. Block at GDSS Doko, GDSS
Gunka and GDSS Shuwarin (Lot-13) SUB Gen. Ventures State 70,030,373.82 70,030,373.82 69,711,120.60 16/7/2018 6 months 100 Completed
14
Constr of 1-block of 3 classrooms each at at GDSSTsohuwar Gwaram,
Birniwa, Maigatari, Guri and Auyo LGA (1st phase 2018 projects) (Lot-14) Sabon Garin Yaya State 46,968,477.85 46,968,477.85 45,989,109.54 12/7/2018 6 months 100 Completed
15
Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS
Beguwa, Ringim LGA (1st phase 2018 projects) (Lot-15) Imam Ahmed Nig. Ltd. Ringim 14,089,454.89 14,089,454.89 13,899,800.51 12/7/2018 6 months 100 Completed
16
Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS
Gerawa, Ringim LGA (1st phase 2018 projects) (Lot-16) Imam Ahmed Nig. Ltd. Ringim 14,133,338.07 14,133,338.07 13,888,831.16 12/7/2018 6 months 100 Completed
17
Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS
Babaldu in Birnin Kudu LGA (Lot-17) Math Global Ltd. B/Kudu 14,099,561.50 14,099,561.50 13,428,153.82 16/7/2018 6 months 100 Completed
BAL. C/F 304,744,668.99 304,744,668.99
4a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 304,744,668.99 304,744,668.99
18
Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS
Takanebu, Miga LGA (1st phase 2018 projects) (Lot-18) Sabon Garin Yaya Miga 14,089,454.89 14,089,454.89 13,936,878.82 12/7/2018 6 months 100 Completed
19
Constr of 1-block of 3 classrooms and 2no. Block of 6-seater toilets at GDSS
Kwarko in Gwaram LGA (Lot-19) SUB Gen. Ventures Gwaram 14,080,760.93 14,080,760.93 13,859,245.31 16/7/2018 6 months 100 Completed
20
Renov of classrooms blocks, Hostels, Admin block, School Clinic, Toilet, and
Constr of wall fence and Gate, Additional 3 courses blocks to Existing wall,
Renov of Zonal office and Reticulation of Water at GDSS Kazaure (1st phase
2018 projects) (Lot-27) Abdulcom Projects Kazaure 49,732,107.32 49,732,107.32 49,223,609.70 12/7/2018 6 months 100 Completed
21
Development and Improvement on the Grave of the Late Emir of Hadejia,
Mallam Muhammadu Sambo at Mairakumi Village of Malam Madori LGA. AGM & Sons Nig. M/Madori 14,426,123.10 14,426,123.10 13,734,855.30 19/7/2018 9 weeks 100 Completed
22
Renov of ICT and Science Laboratories at 4no. Centre of Excellence across
the state (Dutse Model Internation School, GUSS Fantai, GUSS Ringim and
SSS Lautai). Abdulcom Projects Ringim 32,979,423.69 32,979,423.69 32,001,226.78 21/9/2018 10 weeks 100 Completed
23
Constr. Of 2no. Bore-hole and Pipeline route of Water Supply from
Matanfada pump station to (GSS) Roni in Roni. NE Global Eng. Roni 12,400,890.80 16,875,276.80 16,867,411.57 14/9/2017 8 Weeks 100 Completed
24
Construction for the Rehabilitation of Windstorm Damaged Structuresat
Science School Lautai in Gumel L.G.A. (phase I) Gerawa Global Engr. Ltd. Gumel 94,507,858.91 94,507,858.91 93,884,336.41 16/10/2018 16 weeks 100 Completed
25
Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-6 at Tashena
and Tagwaro in Malam madori Constituency Express Innovation Nig. M/Madori 6,208,148.10 6,208,148.10 5,998,152.30 1/11/2018 6 Weeks 100 Completed
26
Construction of Block of 2-Classroom Islamiyya (5NO.) Lot-18 at
Samamiya, Zanga, Waza, Warwade and Rungumawa in Birnin kudu
Constituency. Nushe Business Resources B/Kudu 15,574,595.66 15,574,595.66 15,051,170.66 1/11/2018 16 Weeks 100 Completed
27
Construction of Block of 2-Classroom Islamiyya (1NO.) Lot-12 at Unguwar
mani in Roni Constituency. Yanduna Ventures Ltd. Roni 3,100,220.00 3,100,220.00 2,995,220.45 1/11/2018 4 Weeks 100 Completed
28
Construction of Block of 2-Classroom Islamiyya (4NO.) Lot-17 at Guru,
Wawan rafi, Lokon Rijiya and Hayen Gabas in Kazaure Constituency. Yanduna Ventures Ltd. Kazaure 12,427,116.32 12,427,116.32 12,005,316.33 1/11/2018 15 Weeks 100 Completed
29
Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-15 at Karkarna
Town and Magami Fulani in Yankwashi Constituency. Granitoids Engr. Service Ltd. Yankwashi 6,230,701.36 6,230,701.36 6,011,944.91 1/11/2018 6 weeks 100 Completed
30
Construction of (3N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -9) at chilaro, munkawo and kakori
sabuwa in Birniwa constituency. Amm Manzo Nig. Ltd Birniwa 9,334,202.22 9,334,202.22 9,019,202.22 23/11/2018 8 weeks 100 Completed
31
Construction of (2N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -15) at Tagwayen fage and Kargo in
Garki constituency. MMZ Garki contr. Nig Ltd Garki 6,230,718.16 6,230,718.16 6,020,881.65 23/11/2018 8 weeks 100 Completed
32
Construction of (8N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -4) at Dangan tsaure, Galadanchi,
maranjuwa, kargo mahauta, abaya cikin gari mainomi opp. Government
House, Gwdige and sabuwar Abuja in Dutse constituency. Backbone global links Dutse 24,921,192.62 24,921,192.62 23,735,124.26 23/11/2018 18 weeks 100 Completed
33
Construction of (8N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -3) at hago, Inkaibo, Hardo Ali, Mezan,
kirin Kwatalo, sabon sara and kurunbudi in Bulangu constituency. Kawu Nig Ltd K/Hausa 21,772,100.00 21,772,100.00 21,712,598.35 23/11/2018 16 weeks 100 Completed
34
Construction of (3N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -5) at Sabuwar Gwaram, Unguwar Kudu
Jibwis kila and unguwar Gamji in Gwaram constituency. Nushe Bus. Resou. Nig Ltd Gwaram 9,346,064.24 9,346,064.24 8,947,064.23 23/11/2018 10 weeks 100 Completed
BAL. C/F 652,106,347.31 656,580,733.31
4b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 652,106,347.31 656,580,733.31
35
Construction of (1N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -21) at Bila in Taura constituency. Nushe Bus. Resou. Nig Ltd Taura 3,113,183.85 3,113,183.85 3,008,183.85 23/11/2018 8 weeks 100 Completed
36
Construction of (6N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -22) at Gidan Gona Ringim,
Karshi,Shangal, Jankawa Yola, and Gasakoli in Ringim constituency. Marb Eng. Multi-serv. Nig. Ltd Ringim 18,662,710.50 18,662,710.50 18,029,888.10 23/11/2018 18 weeks 100 Completed
37
Construction of (6N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -24) at Tsadoji, Filin Danshawai, Gidan
shallau, Lokon Dallatu, Gada yamma and Ganguli islamiyya in Kazaure
constituency. Yanduna Venture Nig Ltd Kazaure 18,629,958.00 18,629,958.00 17,999,963.10 23/11/2018 18 weeks 100 Completed
38
Construction of (1N0.) Blocks of 2-classroom Islamiyya school typed 2018
phase II constituency projects (Lot -6) at Kwatsatsa in Roni constituency. Na'ayi Resources Ltd Roni 3,115,354.00 3,115,354.00 3,006,399.90 23/11/2018 10 weeks 100 Completed
39
Construction of (2N0.) Blocks of 2-classroom Islamiyya sschool typed
2018 phase II constituency projects (Lot -19) at Karkarna in Yankwasi
constituency. Granitoids Eng. Nig. Ltd Yankwashi 6,224,045.10 6,224,045.10 6,020,298.10 5/12/2018 8 weeks 100 Completed
40
Construction of (5N0.) Blocks of 2-classroom Islamiyya school atDakwaro,
3No. 2-classroom block at govt. day arabic secondary school basirka and
1No.2-classroom block at digijin (Lot-8) in fagam constituency in gwaram
LGA G.M Sara & sons Nig Ltd Gwaram 15,485,650.64 15,485,650.64 14,960,646.75 1/11/2018 4 weeks 100 Completed
41
Construction of (3N0.) Blocks of 2-classroom Islamiyya sschool typed
2018 phase II constituency projects (Lot -13) at chukutu, malumawar
taura and gidan ganji in Taura constituency. Nushe Bus. Resou. Nig Ltd Taura 9,347,337.24 9,347,337.24 9,032,337.24 1/11/2018 10 weeks 100 Completed
42
Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-15) at Kwaido, Tsagam,
Almajirawa and Majiyawa in Ringim Constituency. Marb Engr. Multi-Services Ringim 12,454,716.33 12,454,716.33 12,034,716.33 18/12/2018 12 weeks 100 Completed
43
Construction of (3 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-8) at Majirga Yanduna, Jamaga and
Ganuwa in Miga Constituency. Nabakwai Gen. Enterp. Nig. Ltd. Miga 9,334,202.22 9,334,202.22 9,027,175.50 5/12/2018 8 weeks 100 Completed
44
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-11A) at Malori and Kuka Dabo in
Kirikasamma Constituency. Tosarawa Global Nig. Ltd. Kirikasamma 6,231,558.16 6,231,558.16 6,021,558.16 18/12/2018 10 weeks 100 Completed
45
Construction of (1 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-23) at Kawari in Kiyawa
Constituency. Demastbo Ventures Ltd. Kiyawa 3,104,993.80 3,104,993.80 2,999,099.25 17/12/2018 8 weeks 100 Completed
46
Construction of (9 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-25) at Masaya, Zaraina, Tsangaya,
Badingu, Dokoki, Ramin kura, Samamiya, Zarainawa and Kura in Birnin
kudu Constituency. Nushe Business Resources B/kudu 27,909,116.39 27,909,116.39 26,964,115.92 5/12/2018 20 weeks 100 Completed
47
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-II) at Diya and Unguwar Malawa
in Gwiwa Constituency. Dankaka Intgrated Services Gwiwa 6,225,216.00 6,225,216.00 6,015,219.00 5/12/2018 8 weeks 100 Completed
48
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-18) at Maitsamiya and
Burmanwa in Sule Tankarkar Constituency. Pullad Global Consultant S/tankarkar 6,223,218.34 6,223,218.34 6,014,218.35 5/12/2018 8 weeks 100 Completed
BAL. C/F 798,167,607.88 802,641,993.88
4c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 798,167,607.88 802,641,993.88
49
Construction of (1 No.) Blocks of 3-Classroom, 1No. 6-Seater Pit Latrine,
and Supply of 17No. 3-Seater Desks at GDASS G/Gabas, 1No. Block of 3-
Classroom, 1No. 6-Seater Pit Latrine, and 23No. 3-Seater Desks at GDASS
Bulangu. Masaka Global Concept Ltd. Various 24,539,884.16 24,539,884.16 24,430,607.74 12/12/2018 8 weeks 100 Completed
50
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-2) at Majingini and Babban
Kambari in Gumel Constituency. Jag & H Intgrated Services Ltd. Gumel 6,230,703.46 6,230,703.46 6,020,716.06 5/12/2018 8 weeks 100 Completed
51
Construction of (1 No.) Blocks of 3-Classroom, 1No. 6-Seater Pit Latrine,
Supply of (38No.) 3-Seater Desks at GDASS Aujara, 1No. Block of 3-
Classroom, Construction 1No. 6-Seater Pit Latrine, Supply of 34No. 3-Seater
Desks at GDASS Kwalam, Construction of (1No.) Block of 6-Seater Pit
Latrine Renovation of 2-Classroom and Supply of (29No.) 3-Seater Desks at
GDASS Gwaram, Construction of (1No.) Block of 3-Classroom, 1No. 6-Seater
Pit Latrine and Supply of (38No.) 3-Seater Desks at GDASS Marma. Yusmatech Investment Nig. Ltd Across the state 45,687,338.25 45,687,338.25 43,815,809.25 12/12/2018 8 weeks 100 Completed
52
Construction of (1 No.) Blocks of Students Hostel and Supply and
Distribution of 100No, Double Bunks Beds at GSTC Birnin kudu. Math Global Investment Ltd. B/kudu 29,140,079.84 29,140,079.84 29,092,645.67 12/12/2018 8 weeks 100 Completed
53
Construction of (1 No.) Blocks of Students Hostel and Supply and
Distribution of 100No, Double Bunks Beds at GSSS Kanya Babba, Babura
LGA. Sabon Garin 'Yaya Nig. Ltd. Babura 29,140,079.84 29,140,079.84 29,092,645.63 12/12/2018 8 weeks 100 Completed
54
Construction of Teacher Lodge Hostel 2018 Phase II Constituency
Projects (Lot-26) at Madachi in Kirikasamma Constituency. K-Manu Gen. Constr & Engr. Kirikasamma 22,461,011.45 22,461,011.45 21,391,439.17 5/12/2018 16 weeks 100 Completed
55
Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed and
2-Classroom Blocks with Head Master Office Subeb Typed (2No) 2018
Phase II Constituency Projects (Lot-14) at Dawar Gada, Malam Aba,
Gangara and Dan Barno in Maigatari Constituency. ALLAH Abin Dogara Nig. Ltd. Maigatari 18,855,242.08 18,855,242.08 18,291,543.71 5/12/2018 14 weeks 100 Completed
56
Construction of (3 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-4) at Kwaita, Unguwar Dinya and
Computer Girls School Roni in Roni Constituency. Yanduna Ventures Ltd. Roni 23,016,302.00 23,016,302.00 22,149,857.43 18/10/18 10 weeks 100 Completed
57
Construction of (1No.) Blocks of Teacher Lodge 2018 Phase III
Constituency Projects (Lot-8B) at Buji in Buji Constituency. Yayarin Tukur Nig. Ltd. Buji 12,701,000.00 12,701,000.00 12,688,611.14 18/10/2018 12 weeks 100 Completed
58
Construction of (1 No.) Blocks of 3-Classroom, and 1No. 6-Seater Pit Latrine
each at GDSS Jahun, GDASS Malam madori, GDASS Gagarayaga, GDASS
Kondiko, GDASS Roni and GDASS Danmasara Babandoki General Enterprises Across the state 71,225,652.48 71,225,652.48 71,216,726.88 12/12/2018 8 weeks 100 Completed
59
Construction of (3 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-20) at Galadimawa Maje ward,
Tunannan Kiyawa ward and Zakwaro Tsirma in Kiyawa Constituency. Step by Step Intergrated Serv Kiyawa 9,346,077.24 9,346,077.24 9,026,037.24 24/12/2018 10 weeks 100 Completed
60
Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-18) at Dantanoma, Abuja, Garin
Barka and Gangara Village in gumel Constituency. Jag & H Integrated Serv. Ltd. Gumel 12,454,716.33 12,454,716.33 12,034,716.33 18/12/2018 12 weeks 100 Completed
BAL. C/F 1,102,965,695.01 1,107,440,081.01
4d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,102,965,695.01 1,107,440,081.01
61
Construction of (5 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-8A) at Gantsa kudu, Foto,
Gwadayi, Sagu and Y/Chakari in Buji Constituency. Mai-mai Blocks Industry Nig. Buji 15,578,895.41 15,578,895.41 14,935,576.16 18/12/2018 12 weeks 100 Completed
62
Construction of (8 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-4) at Sumangara, Tsahiro, Kafit
Gwaram, Innakawa, Tsangaya Sara, Sara kudu, Isawa Maruta and Tsangayar
kofar kudu in gwaram Constituency. Nushe Business Resources Gwaram 24,909,432.66 24,909,432.66 24,069,432.66 18/12/2018 15 weeks 100 Completed
63
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-17) at Kari Tsalle and Majiya
Tasha in Taura Constituency. Nushe Business Resources Taura 9,662,035.24 9,662,035.24 9,470,443.73 18/12/2018 10 weeks 100 Completed
64
Construction of (8No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-21) at Dangoli, Yarma,
Andazawa, Rungumawa, Zarainawa A., Chandan, Nahuce and Bammowa in
Birnin kudu Constituency. NUshe Business Resources B/kudu 24,922,872.66 24,922,872.66 24,090,432.66 18/12/2018 15 weeks 100 Completed
65
Construction of (1No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-6) at Malam Isa Unguwa in
Kaugama Constituency. Mai-mai Blocks Industry Nig. Kaugama 3,113,679.08 3,113,679.08 3,010,779.08 18/12/2018 10 weeks 100 Completed
66
Construction of (2No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-1A) at Arawa and Tigima in
Auyo Constituency. Mai-mai Blocks Industry Nig. Auyo 6,231,558.16 6,231,558.16 6,021,558.16 18/12/2018 10 weeks 100 Completed
67
Construction of (1No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-9) at Waluwa in Kafin Hausa
Constituency. Mai-mai Blocks Industry Nig. K/Hausa 3,117,879.08 3,117,879.08 3,010,779.08 18/12/2018 8 weeks 100 Completed
68
Construction of (4 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-22) at Kilawa, Martaba, Sumiyau
and Galambi in Fagam Constituency. Pullad Global Consultant Gwaram 14,367,439.93 14,367,439.93 13,711,431.33 18/12/2018 10 weeks 100 Completed
69
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-11C) at Diladige and Malorin
Baturiya in Kirikasamma Constituency. Nabakwai Gen. Enterprises Kirikasamma 6,230,718.16 6,230,718.16 6,020,718.16 10/12/2018 8 weeks 100 Completed
70
Construction of (1 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-11B) at Madachi in Kirikasamma
Constituency. Mai-mai Blocks Industry Nig. Kirikasamma 3,115,354.08 3,115,354.08 3,010,779.08 18/12/2018 8 weeks 100 Completed
71
Construction of (1No.) Blocks of 2-Classroom Islamiyya School Typed 2018
Phase III Constituency Projects (Lot-14) at Yoruba Islamiyya School Hadejia
Quarters in Hadejia Constituency. Step by Step Interg. Serv Hadejia 3,115,779.08 3,115,779.08 3,010,779.08 18/12/2018 8 weeks 100 Completed
72
Construction of (4No.) 1-Blocks of 3-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-23) at Karkarna 'A', Karkarna 'B',
Karkarna 'C' and Karkarna 'D' in Yankwashi Constituency. Granitoids Engr. Services Yankwashi 34,364,888.00 34,364,888.00 32,923,529.10 18/12/2018 18 weeks 100 Completed
73
Construction of 1-Blocks of 3-Classroom, 1-Block of 6-Seater VIP Pit Latrine
and Hand Pump at Tsohuwar Gwaram (Lot-2). Babandoki Gen. Enterp. Gwaram 12,528,665.77 12,528,665.77 12,289,355.25 28/12/2018 3 months 100 Completed
74
Construction of (3No.) Blocks of 2-Classroom Islamiyya School Typed 2018
Phase III Constituency Projects (Lot-16) at Dan Abzin, Tinkishi and Waila
Karai in Gwiwa Constituency. Jignaj Global Constr. Ltd. Gwiwa 9,341,037.24 9,341,037.24 9,026,037.24 18/12/2018 10 weeks 100 Completed
75
Construction of 1-Blocks of 3-Classroom, 1-Block of 6-Seater VIP Pit Latrine
and Hand Pump at GDSS Kirikasamma (Lot-3). Babandoki Gen. Enterp. Kirikasamma 12,467,040.04 12,467,040.04 12,112,508.77 28/12/2018 3 months 100 Completed
BAL. C/F 1,286,032,969.60 1,290,507,355.60
4e
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,286,032,969.60 1,290,507,355.60
76
Renovation of 2No. Students Hostel, Block of 3-Classes and Computer
Laboratory at GSTC Birnin kudu (Lot-9). Masaka Global Concept B/kudu 14,023,833.17 14,023,833.17 13,375,079.21 28/12/2018 3 months 100 Completed
77 Renovation of Classrooms and Hostels at GSS Aujara (Lot-5). Ngaloma Constr. Co. Jahun 79,506,892.39 79,506,892.39 78,002,265.33 28/12/2018 6 months 100 Completed
78
Development of Permanent Site of GGDSS Gagarayaga and GDSS Gawuna
(Lot-4). Ngaloma Constr. Co. Gwaram+Hadejia 95,540,000.00 95,540,000.00 93,407,896.69 28/12/2018 6 months 100 Completed
79
Construction of Additional Block of 3-Classrooms each at GDSS Kanti
Kazaure and GDSS Bosuwa (Lot-3) Pullad Global Consultant Kazaure+Gagarawa 19,004,045.22 19,004,045.22 18,695,950.58 28/12/2018 3 months 100 Completed
80
Supply and Installation of (63 Units) of Solar Powered System at Various
Schools (Lot-2) Sims Nig. Ltd. Across the state 48,238,101.45 48,238,101.45 47,471,547.50 1/11/2018 3 Month 100 Completed
81
Procurement and Renovation of Classes at Jigawa State Academy for the
Gifted, Bamaina (Lot-8) Ngaloma Constr. Co. B/Kudu 47,319,728.73 47,319,728.73 45,688,101.46 28/12/2018 3 months 100 Completed
82
Procurement of Science Laboratory equipment and consumables at
Dutse Model Int. school (Lot-7) Al-hamsad Invest. Ltd. Dutse 4,587,837.70 4,587,837.70 4,587,837.70 28/12/2018 4 month 100 Completed
83
Procurement and Distribution of 2.520 3-Seater Students Desks to various
Senior Secondary Schools across the State (Lot-6) Furni-Elect Global Ventures Across the state 50,373,237.60 50,373,237.60 50,373,237.60 28/12/2018 5 months 100 Completed
84
Supply and Distribution of 640No. 3-Seater Students Desks and Benchs at
GDSS Jahun, GGDSS Malam madori, GDSS Gagarayaga, GDSS Kondiko, GGDSS
Roni and GDSS Danmasara Furni-Elect Global Ventures Across the state 12,796,800.00 12,796,800.00 12,796,800.00 12/12/2018 8 weeks 100 Completed
85
Procurment of 224 boxer motorcycles for school supervision effectiveness
across the state. Babandoki Gen. Entp. Across the state 75,000,000.00 75,000,000.00 75,000,000.00 28/12/2018 8 weeks 100 Completed
86 General Renov of School Structures at GGASS Kaugama (Lot-4) Al-hamsad Invest. Ltd. Kaugama 153,516,678.32 153,516,678.32 153,278,954.44 28/12/2018 8 months 100 Completed
87
Procurement of ICT materials/Equipments for 3-centres of excellence (Lot-
6) Al-hamsad Invest. Ltd. Across the state 41,452,175.00 41,452,175.00 41,452,175.00 28/12/2018 3 months 100 Completed
88 Procurement of School uniforms, Sendels and Bags to Nomadic Schools. Muhib Global State 29,880,000.00 29,880,000.00 29,880,000.00 19/12/18 12 weeks 100 Completed
89
Procurement of instructional materials to Schools at basic levels across
the state. Babandoki Gen. Entp. State 62,319,731.25 62,319,731.25 62,319,731.25 28/12/18 12 weeks 100 Completed
90
Constr of Upstars Classroom Islamiyya type (1no.) Block of 2classrooms
(2018 phase II) constituency project (Lot-17) at Harazimiyya in Hadejia
Alh. Umaru Babandoki Nig.
Ltd. Hadejia 15,011,567.54 15,011,567.54 14,889,338.36 5/12/2018 14 weeks 100 Completed
91P rinting o f 2019 Bas ic Educa tio n certifica te examina tio n (BECE) ques tio n papers with
ans wer s hee ts fo r J SS Acro s s the S ta te Clear Impres s io ns Ltd State 15,260,680.05 15,260,680.05 15,260,680.05 13/6/2019 8 weeks 100 Completed
92 Re-co ns truc tio n o f fa llen wall fence a t GGUSS Garki and GUSS M/Mado ri P ullad Glo ba l Co ns ult State 9,039,035.07 9,039,035.07 8,908,113.11 10/7/22019 8 weeks 100 Completed
93
Reno vatio n o f S to rm damages a t 7no . Scho o ls acro s s the s ta te : GGASS
S/Tankarkar, GUSS maiga ta ri, GDSS Shagari Qtrs . Hadejia , GSS Aujara , GDSS Buji,
GGDSS Birnin Kudu and Duts e Mo del Int Scho o l. AGM & So ns Nig State 23,498,908.59 23,498,908.59 23,490,970.35 15/8/2019 8 weeks 100 Completed
94
Reno vatio n o f s to rm damages a t GDASS Dantano ma in Gumel LGA, Scho o l o f
Arabic and Is lamic S tudies (SAIS) Hadejia , GDASS Zainab Kazaure , GDASS Dabi in
Ringim, GDASS Gwaram and GGASS Danzo mo in Gagarawa LGA P ullad Glo ba l Co ns ult State 53,582,692.89 53,582,692.89 53,299,656.22 16/8/2019 16 weeks 100 Completed
95Supply and Ins ta lla tio n o f 52No . S tanda lo ne So lar Integra ted S tree tlight (P has e-II) a t
the J igawa Sta te Co llege o f Is lamic & Legal S tudies Ringim Sims Glo ba l Res o urces Ringim 32,215,050.00 32,215,050.00 3/5/2019 4 weeks
96Supply and Distribution of Science text Books and Teachers Guide for Senior
Secondary Schools Across the State Learn Africa Plc State 49,949,800.00 49,949,800.00 49,949,800.00 11/7/2019 6 weeeks 100 Completed
97Procurement and Sewing of 30,000 sets of School Uniforms to Senir Secondary
Schools acros the state 313 Textile Nig Ltd. State 79,980,000.00 79,980,000.00 79,980,000.00 3/9/2019 12 weeks 100 Completed
98 Renov of Dining Hall at GGASS Babura Sabon garin Yaya Ltd. Babura 20,866,366.64 20,866,366.64 20,859,565.28 28/12/2018 8 weeks 100 Completed
BAL. C/F 2,318,996,131.21 2,323,470,517.21
4f
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 2,318,996,131.21 2,323,470,517.21
99
Constr of 3no. Blocks of 2classroom Islamiyya School type (2018 phase III)
constituency project (Lot 19) at Fulanin Kurfi, Kuka kofar gari, Kantudu in Yanduna Ventures Kazaure 9,346,077.24 9,346,077.24 9,346,077.24 18/12/2018 12 weeks 100 Completed
100
Constr of additional 3classrooms block each at GDSS Ringim Areawa, GDSS
Baura (Lot-1) Pullad Global Consult Ringim + Babura 19,004,045.22 19,004,045.22 17,305,017.20 28/12/2018 3 months 100 Completed
101
Constr of 1no. Block of 3-classrooms each at GDSS Babura, GDSS
Galagamma Gumel, GDSS babaldu and GDSS Ringim Areawa (2019 Capital
projects) Babandoki Gen Entp. state 44,808,022.00 44,808,022.00 44,225,690.58 3/10/2019 12 weeks 100 Completed
102
Renov of Science and ICT Labs. at 9no. Proposed Science Centres of
Excellence core 2 (GGUSS M/madori, GDSS G/Gabas, GGSS Garki, GDSS
Gwiwa, GUSS Aujara, GUSS Maigatari, GDSS T/Gwaram, GC Birnin Kudu and
GUSS Basirka) AGM & Sons Nig Ltd. state 24,140,000.00 24,140,000.00 24,034,905.66 25/09/2019 12 weeks 100 Completed
103
Constr of 1no. Block of 3-classrooms each at 8no. GDSS across the state
(2019 Capital Projects) Math Global Invest. Ltd. Across the state 90,089,432.00 90,089,432.00 87,675,689.47 28/10/2019 12 weeks 100 Completed
104
Construction of 1No Block of 3 classrooms each at GDASS Kiri Kasamma
GDASS Bulangu GDASS Miga GDASS Kiri Kasamma GDASS Bulangu GDASS
Miga, GDASS Marma, GDASS Limawa , GDASS Birniwa and GDASS Aujara A.A. Maikatako Gen Entr Aujara 78,414,000.00 78,414,000.00 74,680,037.57 14/11/2019 20 weeks 100 Completed
105
Procurment of Medical Drugs, ICT and Sicbay Equipment for Jigawa
Academy for the Gifted, Bamaina IMAM Ahmed Nig Ltd. B/kudu 4,639,345.25 4,639,345.25 4,639,345.25 16/10/2019 2 weeks 100 Completed
106
Construction of Additional Block of 3-Classrooms each at GDSS Galagamma
Gumel and GGDSS Hadejia (Lot-2) Pullad Global Consultant Gumel + Hadejia 19,004,045.22 19,004,045.22 18,695,950.58 28/12/2018 3 months 100 Completed
107
Construction of (4No.) Blocks of 2-Classroom Islamiyya School Typed 2018
Phase II Constituency Projects (Lot-12) at Batali, Insharuwa, Bakar Kuka
and Masko in Babura Constituency. Mufabamex Concept Nig. Ltd. Babura 12,444,222.00 12,444,222.00 12,024,222.00 5/12/2018 12 weeks 100 Completed
108
Procurement of 7.500No Furniture Sets to Primary Schools 4-6 Pupil (1st &
2nd Quarter 2018 UBEC/SUBEB Intervention Project) Lot-32 across the
State. Furni-Elect Global Ventures Across the state 119,749,935.00 119,749,935.00 119,749,935.00 18/12/2018 16 weeks 100 Completed
TOTAL 2,740,635,255.14 2,745,109,641.14
4g
Ministry of Land
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT (N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1
Construction of 1No. Block of 4No. House of 2No. Bedroom
Semi-Detach at Kazaure Local Government Area Al-Sabur Global Links Kazaure 10,779,821.20 10,779,821.20 10,289,698.65 19/3/2019 14 Weeks 100 Completed
2
Construction of 1No Block of 4No House of 2No Bedroom Semi-
Detach (Lot-6) at Hadejia Local government Area Ngaloma Construction Hadejia 10,719,537.18 10,719,537.18 10,673,330.85 19/3/2019 14 Weeks 100 Completed
3
Construction of 1No Block of 4No House of 2No Bedroom Semi-
Detach (Lot-9) at Malam Madori Local government Area Ngaloma Construction M/Madori 10,719,854.25 10,719,854.25 10,673,330.85 19/3/2019 14 Weeks 100 Completed
4
Constr of 1no. Block of 4no. House of 2no. Bedrooms semi detached
(Lot-3) at Birniw a LGA MWT Real Estate & Gen Entp. Birniw a 10,424,245.65 10,424,245.65 10,420,295.55 19/3/2019 14 Weeks 100 Completed
5
Constr of 1no. Block of 4no. House of 2no. Bedrooms semi detached at
Jahun LGA Nushe Business Jahun 10,691,491.65 10,691,491.65 10,606,901.55 19/3/2019 14 Weeks 100 Completed
TOTAL 53,334,949.93 53,334,949.93
Ministry of Commerce
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 Renov of 4no. Structures at EPZ Maigatari AMIA Int. Ltd. Maigatari 12,738,100.79 12,758,100.79 12,738,095.56 28/10/2019 2 months 100 Completed
Total 12,738,100.79 12,758,100.79
Dutse Capital Development Athority
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Constr. of New High Brow lay out in Dutse Dantata & Saw oe Dutse 3,822,690,275.89 5,073,417,718.02 4,577,814,987.09 14/10/2011 48 w eeks 83 Completed
2
Prov ision & Installation of Streetlights at the 3 Arms zone, Ibrahim Aliy u
Eastern By e-pass and Old Police Hqrs. To Gadadin-Fanisau Link road,
Dutse. Dantata & Saw oe Dutse 1,064,545,077.91 1,267,613,083.02 1,058,862,394.59 8/11/2012 12 w eeks 100 Completed
3
Consultant for the Constr. Of 30N0. Houses for Jigaw a State members of
the House of Assembly at Disina HAG Eng. Nig. Limited Dutse 131,922,214.60 147,301,384.74 147,146,095.43 11/7/2012 14 months 100 Completed
4 Cconstr of Wall Fence & land Scaping to 30no. Houses Afdin Constr. Ltd. Dutse 315,291,242.77 315,291,242.77 291,248,714.33 7/5/2015 6 months 100 Completed
TOTAL 5,334,448,811.17 6,803,623,428.55
Cabinet Office
POST CONTRACT PROJECT EVALUATION
S/ N P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
A M OUN T (N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
1
Constr. of Juma'at Prayer Mosque at Galambi, fagam
Constituency in Gwaram LGA. Ramadan Constr. Nig. Ltd. Gwaram 26,396,975.14 26,396,975.14 25,831,669.29 24/01/2017 16 weeks 100 Completed
2
Constr. of five (5) Daily prayer Mosques at Gidan Mutari
Fulanin Harbo, Danmodi Gari and Hammado in Sule
Tankarkar Constituency. Manhaf Global Ventures S/Tankarkar 6,543,114.75 6,543,114.75 6,352,538.59 16/10/2017 6 weeks 100 Completed
3
Constr. of Friday prayer mosque at Gada yamma and 3no.
Daily prayer mosques at Gada Rumawa, Sabaru Fanda and
Gada Gabas in Kazaure Constituency. Yanduna Ventures Kazaure 53,061,271.36 53,061,271.36 52,346,684.20 25/10/2017 12 Weeks 100 Completed
4
Interlocking Tiles and External Works of (1No.) Friday Prayer M osque (
2018 Phase II) Constituency Pro jects (Lot-44) at Garki Central
M osque in Garki Constituency M M Z Garki Construction Garki 7,642,374.33 7,642,374.33 7,280,614.74 31/12/2018 8 weeks 100 Completed
5
Constr. of Friday Prayer Mosques at Nasarawa in Gumel
Constituency. JAG & H Integrated Serv. Ltd. Gumel 15,046,340.35 15,046,340.35 15,001,060.45 16/10/2017 12 weeks 100 Completed
6
Construction of Five (5) daily Prayer Mosques at Wutsadaand
Kankare Fulani in Gagarawa Constituency. Al-Nasibi Gen. Intp. Gagarawa 4,129,061.98 4,129,061.98 3,932,439.98 18/12/2017 4 Weeks 100 Completed
7
Constr of (3no.) Five Daily prayer mosques (2018 phase III)
Constituency projects (Lot-11) at Wasari, Yanusori and Goyi
in Bulangu Constituency Kawu Nig Ltd. K/Hausa 5,868,833.55 5,868,833.55 5,780,776.24 23/11/2018 12 Weeks 100 Completed
8
Construction of Five (5) daily Prayer Mosques at Garbagar
Gari (Garbagai Ward), Wareri (Guri Ward), Zoriyo (Adiyani
Ward), Jauron Kadira (Kadira Ward) and Dolewa (Kadira
Ward) in Guri Constituency. Alh Umar Baban Doki Nig Ltd Guri 10,322,654.95 10,322,654.95 10,322,654.94 18/12/2017 8 Weeks 100 Completed
9
Construction of Five (5) daily Prayer Mosques at mazazzaga
(Garko Ward) and Balago Town Balago Ward) in Kiyawa
Constituency. Demastbo Ventures Ltd. Kiyawa 4,129,061.98 4,129,061.98 3,932,439.98 18/12/2017 6 Weeks 100 Completed
10
Construction of (3No. Friday Prayer Mosques (2018 Phase II)
Constituency Projects ( Lot-40) at Zangin Kanya, Waloyi
Sabuwa and Tsangaiwa in Bulangu Constituency Kawu Nigeria Ltd Kafin Hausa 16,888,035.21 16,888,035.21 16,797,853.54 23/11/2018 12 Weeks 100 Completed
11
Completion/renovation of Juma'at Prayer Mosques at Jibwis
Garki in Garki Constituency. Jag & H Intgrt Services Ltd Garki 23,736,083.26 23,736,083.26 23,423,788.50 18/12/2017 12 Weeks 100 Completed
12
Construction of (3No) Five Daily Prayer Mosques at Kukuma
Kudu (Kumuma Ward), Dakori (Gantsa Ward) and Falgeri
Arewa ( Falgeri Ward) in Buji Constituency A+-TECH INTEG Buji 6,193,592.97 6,193,592.97 5,898,659.98 1/19/2018 8 weeks 100 Completed
13
Constr of 2no. Five daily prayer mosques 2017 constituency
projects phase III remaining works (lot-3) at Mahudi
Tsangaya and Jingino in Fagam Constituency, Gwaram LGA. G.M. Sara & Sons Ltd. Gwaram 4,129,061.98 4,129,061.98 3,932,439.98 16/4/2018 6 weeks 100 Completed
Balance C/F 184,086,461.81 184,086,461.81
8a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 184,086,461.81 184,086,461.81
14
Constr of Juma'at Prayer mosques 2017 constituency projects
phase III remaining works (Lot-7) at Kiri-kasamma Gari in
Kirikasamma Constituency. Alh Umaru Babandoki K/Kasamma 17,176,291.17 17,176,291.17 17,130,145.55 16/4/2018 12 weeks 100 Completed
15
Constr /Renovation/Completion of prayer mosques 2017
Constituency projects phase III Remaining works (Lot-4) at
Galambi Central mosque in Fagam Constituency, Gwaram LGA. Ramadan Constr Ltd. Gwaram 16,011,630.21 16,011,630.21 15,249,171.63 16/4/2018 12 weeks 100 Completed
16
Renovation/Completion of Juma'at prayer mosques 2017
Constituency projects phase III Remaining works (Lot-8) at
Maje in Taura Constituency. Nushe Business Resources Taura 9,001,562.13 11,793,398.14 10,940,373.12 16/4/2018 12 weeks 100 Completed
17
Constr of (6no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-5) at Nera, Lauya, Shantake, Kurtulla, Haladawa
and G/Ganji in Kanya Babba Constituency, Babura LGA. Deetech Nig. Ltd. Babura 11,455,254.00 11,455,254.00 10,784,277.06 10/10/2018 6 weeks 100 Completed
18
Constr of (2no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-15) at Gadewa and Bayan Lambu in Jahun
Constituency. Yanduna Ventures Jahun 3,788,985.90 3,788,985.90 3,746,645.70 10/10/2018 6 weeks 100 Completed
19
Constr of (5no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-22) at Bodayal, Belas, K/chiroma, Todariya and
Tsedau in Kazaure Constituency. Yanduna Ventures Kazaure 9,745,359.75 9,745,359.75 9,269,646.75 10/10/2018 6 weeks 100 Completed
20
Constr of (1no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-2) at Mata kuwa in Auyo Constituency. Step by Step Integ. Auyo 1,952,627.20 1,952,627.20 1,870,570.63 10/10/2018 6 weeks 100 Completed
21
Constr of (1no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-28) at Bula Sure in Roni Constituency. Na'ayi Resources Ltd. Roni 1,943,923.00 1,943,923.00 1,853,929.35 10/10/2018 6 weeks 100 Completed
22
Constr of (5no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-6) at Bulunkuce, Kangire, Kantoga T., Gorrawa
and Tosoro in B/kudu Constituency. Nushe Bus. Resources B/kudu 9,559,735.50 9,559,735.50 9,139,735.50 10/10/2018 6 weeks 100 Completed
23
Constr of (5no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-7) at Dukana, U/Galadima, Shungurun, Iggi and
Gogoriya in Birnin Kudu Constituency. Nushe Bus. Resources B/Kudu 9,795,123.50 9,795,123.50 9,375,123.50 10/10/2018 6 weeks 100 Completed
24
Constr of (4no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-24) at Talaku, Janiskifeta, Janiskitagwaro and
Kashin Dila in Malam Madori Constituency. Express Innovation Concept M/Madori 7,732,082.04 7,732,082.04 7,363,887.63 10/10/2018 6 weeks 100 Completed
25
Constr of (3no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-19) at Nasarawa, Dubantu and Walawa Matsaro
in Hadejia Constituency. Alh. Umaru Babandoki Hadejia 5,735,858.70 5,735,858.70 10/10/2018 6 weeks On-going
Balance C/F 287,984,894.91 290,776,730.92
8b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 287,984,894.91 290,776,730.92
26
Constr of (3no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-23B) at G/Hadau, D/Talle and D/Takore in
Maigatari Constituency. Modang Investment Ltd. Maigatari 5,756,502.15 5,756,502.15 5,754,438.69 10/10/2018 6 weeks 100 Completed
27
Construction of (1NO.) five Daily Prayer Mosques 2018
Constituency Projects at Laya in Fagam Constituency,
Gwaram Local Government Area. Ramadan Constrt. Nig. Ltd. Gwaram 7,307,084.41 7,307,084.41 6,959,128.00 14/11/2018 8 weeks 100 Completed
28
Construction of (3NO.) five Daily Prayer Mosques (2018 Phase
II) Constituency Projects (Lot-12) at Gonga Yamma, Kakibare
and Jingi Town in Dutse Constituency. Al-Kassam Jannah Nig. Ltd. Dutse 5,881,500.02 5,881,500.02 5,846,768.55 23/11/2018 8 weeks 100 Completed
29
Construction of (3NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-8) at Tsangayar Kuka, Dagaceri
Kukawa and Goguwa Kandawa in Birniwa Constituency. Amm Manzo Nig. Ltd. Birniwa 5,830,306.65 5,830,306.65 5,578,306.65 14/11/2018 8 weeks 100 Completed
30
Construction of (1NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-1) at Kajilmaran in Auyo
Constituency. Amm Manzo Nig. Ltd. Auyo 1,943,435.55 1,943,435.55 1,859,435.55 14/11/2018 8 weeks 100 Completed
31
Construction of Five (5) daily Prayer Mosques at Sabuawar
Kaura, Kiyako, Birnin kudu, Samamiya and Bigidan in Birnin
Kudu Constituency. Nushe Business Resources B/kudu 10,322,654.95 10,322,654.95 9,831,099.96 18/12/2017 8 Weeks 100 Completed
32
Construction of Juma'at Prayer Mosques at Garin Mado in
Gagarawa Constituency. Modang Investment Ltd. Gagarawa 9,527,340.25 9,527,340.25 6,914,922.90 18/12/2017 12 Weeks 100 Completed
33
Construction of (3NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-31) at Rauda L/Dutse, Karkarna
"A" and new Achilafiya in Yankwashi Constituency. Granitoids Engr. Service Ltd. Yankwashi 5,834,168.55 5,834,168.55 5,582,168.55 14/11/2018 8 weeks 100 Completed
34
Construction of (4NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-10) at Basirka Taya, Basirka
S/Fawa, Ruwa Kari and Basirka Karofi in Fagam Constituency,
Gwaram Local Government Area. Ramadan Constrt. Nig. Ltd. Gwaram 7,754,111.40 7,754,111.40 7,418,111.40 14/11/2018 8 weeks 100 Completed
35
Completion/Renovation of (1NO.) five Daily Prayer Mosques
2018 Constituency Projects (Lot-4) at Faru M/Taya in Babura
Constituency. Danfatu & Sons Nig. Ltd. Babura 1,931,522.85 1,931,522.85 1,815,157.71 26/12/2018 8 weeks 100 Completed
36
Construction of (1NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-3) at Gandun Kadir in Auyo
Constituency. Wajedu Nig. Ltd. Auyo 1,951,976.50 1,951,976.50 1,867,976.50 14/11/2018 8 weeks 100 Completed
Balance C/F 352,025,498.19 354,817,334.20
8c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 352,025,498.19 354,817,334.20
37
Construction of (2NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-21) at Maragwado and Jama'ar
Jiyan in Kirikasamma Constituency. Naila Multiservices Venture K/kasamma 3,922,645.70 3,922,645.70 3,910,445.70 14/11/2018 8 weeks 100 Completed
38
Construction of (3NO.) five Daily Prayer Mosques 2018
Constituency Projects at Kaugama S/Gari, Taura Jarkasa and
Daurawa in Taura Constituency. Nushe Business Resources Taura 5,853,062.00 5,853,062.00 5,632,568.55 14/11/2018 6 weeks 100 Completed
39
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Gusau Quarters in Gumel
Constituency. Jag&H Integrated Services Ltd Gumel 4,875,157.22 4,875,157.22 4,643,096.85 14/11/2018 8 weeks 100 Completed
40
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-40) at Mele in Gumel
Constituency. Jag&H Integrated Services Ltd Gumel 11,823,386.40 11,823,386.40 11,658,501.75 14/11/2018 8 weeks 100 Completed
41
Completion/Renovation of (2NO.) Friday Prayer Mosque
(2018 Phase II) Constituency Projects (Lot-41) at Dantawuya
and Maja B/Jeji Towns in Dutse Constituency. Al-kasam Jannah Nig. Ltd. Dutse 20,177,486.34 20,177,486.34 20,221,586.34 23/11/2018 8 weeks 100 Completed
42
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-66) at Tsangaiwa in Miga
Constituency. Amia Integ. Service Nig Ltd. Miga 11,869,289.26 11,869,289.26 11,845,989.25 14/11/2018 8 weeks 100 Completed
43
Construction of Five (5) daily Prayer Mosques at mazazzaga
(Garko Ward) and Balago Town Balago Ward) in Kiyawa
Constituency. Demastbo Ventures Ltd. Kiyawa 4,129,061.98 4,129,061.98 3,932,439.98 18/12/2017 6 Weeks 100 Completed
44
Construction of Five (5) daily Prayer Mosques at Jemawa,
Sansami, Muna fadi and Construction of Juma'at Prayer
Mosque at Kanya Town in Kanya Babba Constituency of
Babura Local Govt Area. Deetech Nig. Ltd. Babura 16,304,386.14 16,304,386.14 16,009,453.15 18/12/2017 12 Weeks 100 Completed
45
Construction of Five (5) daily Prayer Mosques at Mirgina,
Danbuwayi, Zuge, UnguwarKiwo, Dan Goriba and
Construction of Juma'at Prayer Mosque at Danbanki in Sule
Tankarkar Constituency. Bulangu Drilling Services S/tankarkar 22,536,624.84 22,536,624.84 21,463,452.24 18/12/2017 12 Weeks 100 Completed
46
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-54) at UZA in Auyo Constituency. Muhal Global Concept Ltd. Auyo 2,276,676.25 2,276,676.25 2,168,263.10 14/11/2018 8 weeks 100 Completed
47
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-35) at Yalwa Dawai Village in
Birnin kudu Constituency. Nushe Business Resources B/kudu 7,300,090.20 7,300,090.20 7,037,590.20 14/11/2018 12 weeks 100 Completed
Balance C/F 463,093,364.52 465,885,200.53
8d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 463,093,364.52 465,885,200.53
48
Completion/Renovation of (3NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-59) at Yarfi, Sharifori and Digijin
Village in Fagam Constituency, Gwaram L.G.A. G.M. Sara & Sons Ltd. Gwaram 5,203,805.88 5,203,805.88 5,003,624.64 14/11/2018 8 weeks 100 Completed
49
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-47B) at Likori in Kirikasamma
Constituency. Tosarawa Global Nig. Ltd. Kirikasamma 5,005,071.05 5,005,071.05 5,005,071.05 14/11/2018 8 weeks 100 Completed
50
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-51) at Jibwis Sule Tankarkar in
Sule Tankarkar Constituency. Lautai Genaral Investment S/Tankarkar 7,960,852.75 7,960,852.75 7,610,355.95 14/11/2018 8 weeks 100 Completed
51
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at K/Fada in Sule Tankarkar
Constituency. Lautai Genaral Investment S/Tankarkar 6,506,264.97 6,506,264.97 6,414,745.17 14/11/2018 8 weeks 100 Completed
52
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Bebeji in Buji Constituency. Yayarin Tukur Nig. Ltd. Buji 8,267,235.04 8,267,235.04 7,873,557.18 14/11/2018 8 weeks 100 Completed
53
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-45) at Wiwi in Kafin Hausa
Constituency. Danfatu & Sons Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 3,996,672.01 14/11/2018 8 weeks 100 Completed
54
Completion/Renovation of (3NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-67) at Nisan Marke, Shafar and
Gidan K/H Ari in Ringim Constituency. Madanta Global Nig. Ltd. Ringim 16,816,456.06 16,816,456.06 16,709,406.06 14/11/2018 8 weeks 100 Completed
55
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Sarkin Dare in Gagarawa
Constituency. Amm Manzo Nig. Ltd. Gagarawa 10,561,294.91 10,561,294.91 10,058,376.11 14/11/2018 8 weeks 100 Completed
56
Completion/Renovation of (5NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-63) at Majerinzan Goma, Matakur,
Kutugum, Aduwa and D/Kyaure in Kafin Hausa Constituency. Amm Manzo Nig. Ltd. K/Hausa 16,853,819.38 16,853,819.38 13,140,583.66 14/11/2018 8 weeks 100 Completed
57
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Jikas in Gwaram Constituency. Amm Manzo Nig. Ltd. Gwaram 14,523,958.83 14,523,958.83 14,463,706.74 14/11/2018 8 weeks 100 Completed
58
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Girbobo in Kaugama Constituency. Amm Manzo Nig. Ltd. Kaugama 10,069,325.22 10,069,325.22 10,069,325.21 14/11/2018 8 weeks 100 Completed
59
Completion/Renovation of (5NO.) Friday Prayer Mosque 2018
Constituency Projects at Takwasa, Batali, Babura Central,
Jigawar Dan Ali and Babura Jibwis in Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 11,560,530.17 11,560,530.17 11,010,028.73 19/11/2018 8 weeks 100 Completed
Balance C/F 580,418,650.80 583,210,486.81
8e
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 580,418,650.80 583,210,486.81
60
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-65) at Askandu in Kaugama
Constituency. Amm Manzo Nig. Ltd. Kaugama 6,219,763.56 6,219,763.56 6,020,579.08 14/11/2018 8 weeks 100 Completed
61
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-53) at Sabuwa Village in
Yankwashi Constituency. Granitoids Engr. Service Ltd. Yankwashi 12,195,580.26 12,195,580.26 12,164,242.52 14/11/2018 12 weeks 100 Completed
62
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-32) at Gamsarka in Auyo
Constituency. Muhal Global Concept Ltd. Auyo 7,026,996.02 7,026,996.02 6,692,377.15 24/12/2018 8 weeks 100 Completed
63
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at K/Fada Sara in Gwaram
Constituency. Alh. Umaru Baban Doki Gwaram 15,941,139.39 15,941,139.39 15,925,657.32 31/12/2018 8 weeks 100 Completed
64
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-99) at Yan Makada in Kazaure
Constituency. Karami Constr. Co. Kazaure 18,118,618.22 18,118,618.22 17,255,827.82 14/11/2018 8 weeks 100 Completed
65
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-37) at Nasarawan Kigudu in Fagam
Constituency Gwaram L.G.A. Sukudai Construction Nig. Ltd. Gwaram 7,274,348.35 7,274,348.35 7,259,747.80 14/11/2018 8 weeks 100 Completed
66
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-64) at Kaugama Town in Kaugama
Constituency. Nabakwai General Entp. Kaugama 17,890,045.00 17,890,045.00 17,780,488.09 14/11/2018 8 weeks 100 Completed
67
Completion/Renovation of (3NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-58) at Jibwis Kondiko, Dangulani
and Kijin Village in Fagam Constituency, Gwaram L.G.A. G.M. Sara & Sons Ltd. Gwaram 8,371,896.23 8,371,896.23 8,021,154.15 14/11/2018 8 weeks 100 Completed
68
Construction of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Makerabu Village in Gagarawa
Constituency. Modang Investment Ltd. Gagarawa 10,561,294.91 10,561,294.91 10,058,376.10 14/11/2018 8 weeks 100 Completed
69
Fencing of Kafin Hausa Jibwis Friday Prayer Mosque 2018
Constituency Projects (Lot-62) in Kafin Hausa Constituency. Faahm Intgrated Resources K/Hausa 2,403,328.04 2,403,328.04 1,998,822.04 14/11/2018 8 weeks 100 Completed
70
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-57) at Dansure in Roni
Constituency. Na'ayi Resources Nig. Ltd. Roni 4,550,100.85 4,550,100.85 4,550,100.85 23/11/2018 8 weeks 100 Completed
71
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-...) at Kadama in Roni
Constituency. Na'ayi Resources Nig. Ltd. Roni 9,527,340.25 9,527,340.25 9,317,340.24 23/11/2018 8 weeks 100 Completed
Balance C/F 700,499,101.88 703,290,937.89
8f
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 700,499,101.88 703,290,937.89
72
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-...) at Kwanar Yarshara in Roni
Constituency. Na'ayi Resources Nig. Ltd. Roni 9,527,340.25 9,527,340.25 9,317,340.24 23/11/2018 8 weeks 100 Completed
73
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-69) at Bashe and Amaryawa
Towns in Roni Constituency. Na'ayi Resources Nig. Ltd. Roni 13,161,630.65 13,161,630.65 12,534,886.32 23/11/2018 8 weeks 100 Completed
74
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-47) at Dinya Wayakawoka in
Jahun Constituency. Khairussabah Nig. Ltd. Jahun 4,411,465.20 4,411,465.20 4,201,395.42 23/11/2018 8 weeks 100 Completed
75
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-45) at Kulawa mai Kasuwa
Gauza in Jahun Constituency. Khairussabah Nig. Ltd. Jahun 9,942,198.00 9,942,198.00 9,937,789.05 24/12/18 8 weeks 100 Completed
76
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-71) at Sabon Garin Yaya in
Taura Constituency. ALLAH Abin Dogara Nig. Ltd. Taura 19,681,939.15 19,681,939.15 19,622,234.31 23/11/2018 8 weeks 100 Completed
77
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-43A) at Nasarawa Jibwis in
Gumel Constituency. Farham Synergy Concept Ltd. Gumel 15,210,520.70 15,210,520.70 15,155,375.19 23/11/2018 8 weeks 100 Completed
78
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-50) at Gareru in Kaugama
Constituency. Danfatu & Sons Nig. Ltd. Kaugama 8,120,321.42 8,120,321.42 7,733,639.44 23/11/2018 8 weeks 100 Completed
79
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-68) at Garun Gabas in Malam
madori Constituency. Step By Step intgrated Servic M/madori 15,819,389.40 15,819,389.40 15,766,085.13 23/11/2018 8 weeks 100 Completed
80
Completion/Renov. Of (2 No.) Friday Prayer Mosque (2018
Phase III) Constituency Projects (Lot-66) at Yalo and
Yanleman/Dakayyawa in Kaugama Constituency. Danfatu & Sons Nig. Ltd. Kaugama 12,471,560.90 12,471,560.90 11,949,935.26 23/11/2018 8 weeks 100 Completed
81
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-54) at Garin Makera in Ringim
Constituency. Marb Engr. Multi-Services Ringim 8,142,760.20 8,142,760.20 8,121,760.19 23/11/2018 8 weeks 100 Completed
82
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-53) at Yanduna in Ringim
Constituency. Marb Engr. Multi-Services Ringim 8,157,650.70 8,157,650.70 8,135,226.36 23/11/2018 8 weeks 100 Completed
83
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-44) at Kundiga in Gwiwa
Constituency. Jignaj Global Constructions Gwiwa 14,802,529.09 14,802,529.09 14,765,972.55 23/11/2018 8 weeks 100 Completed
Balance C/F 839,948,407.54 842,740,243.55
8g
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 839,948,407.54 842,740,243.55
84
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-...) at Yelwa in Buji
Constituency. Yayarin Tukur Nig. Ltd. Buji 12,518,061.42 12,518,061.42 11,921,962.85 23/11/2018 8 weeks 100 Completed
85
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-38) at Dagilfani in Birniwa
Constituency. AMM Manzo Nig. Ltd. Birniwa 10,900,793.17 10,900,793.17 10,133,120.74 29/11/2018 8 weeks 100 Completed
86
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-51) at Ubba in Kaugama
Constituency. Danfatu & Sons Nig. Ltd. Kaugama 8,110,126.52 8,110,126.52 7,723,931.07 23/11/2018 8 weeks 100 Completed
87
Construction of the (2No.) Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-31) at Gajin Gebi and
Margawa in Ringim Constituency. Marb Engr. Multi-Services Ringim 3,923,039.40 3,923,039.40 3,755,039.40 23/11/2018 6 weeks 100 Completed
88
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-53) at Yandutse in Ringim
Constituency. Marb Engr. Multi-Services Ringim 8,157,650.70 8,157,650.70 8,135,226.36 23/11/2018 8 weeks 100 Completed
89
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Kwantamawa in Kafin Hausa
Constituency. Mugin Investment Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 3,989,065.98 23/11/2018 8 weeks 100 Completed
90
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at G/Kanya in Kafin Hausa
Constituency. Mugin Investment Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 3,989,065.98 23/11/2018 8 weeks 100 Completed
91
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Zarga in Taura Constituency. Dankwara Maijimina Invest. Taura 8,373,590.40 8,373,590.40 8,373,590.40 23/11/2018 8 weeks 100 Completed
92
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Wurma Town in Dutse
Constituency. H.M. Dangara Ltd. Dutse 2,401,479.28 2,401,479.28 2,316,649.70 23/11/2018 8 weeks 100 Completed
93
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Matara Babba in Birniwa
Constituency. AMM Manzo Nig. Ltd. Birniwa 10,100,873.67 10,100,873.67 10,060,866.90 29/11/2018 8 weeks 100 Completed
94
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Rabadi in Fagam Constituency. Ramadan Construction Ltd. Gwaram 8,167,025.88 8,167,025.88 7,778,119.88 23/11/2018 8 weeks 100 Completed
95
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Ganji in Fagam Constituency. Ahmad Maidoya & Sons Gwaram 4,001,112.00 4,001,112.00 3,810,582.85 23/11/2018 8 weeks 100 Completed
Balance C/F 924,595,504.02 927,387,340.03
8h
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 924,595,504.02 927,387,340.03
96
Completion/Renovation of (3 No.) Friday Prayer Mosques
2018 Constituency Projects (Lot-67) at Nisan Marke, Shafar
and Gidan K/H Ari in Ringim Constituency. Madanta Global Nig. Ltd. Ringim 16,816,456.06 16,816,456.06 16,709,406.06 14/11/2018 8 weeks 100 Completed
97
Completion/Renovation of (6 No.) Friday Prayer Mosques
2018 Constituency Projects at Sugungun, Kanya, Gwarzo,
Zaidawa, G/Maza and Kargo in Garki Constituency. MMZ Garki Construction Nig. Garki 27,784,329.15 27,784,329.15 26,734,547.76 14/11/2018 8 weeks 100 Completed
98
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-49) at Romawa village in Miga
Constituency. Amia Integ. Service Nig Ltd. Miga 10,169,831.21 10,169,831.21 10,162,921.57 23/11/2018 8 weeks 100 Completed
99
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-52) at Akasan in Taura
Constituency. Dankwara Maijimina Invest. Taura 8,219,582.90 8,219,582.90 8,177,082.90 23/11/2018 8 weeks 100 Completed
100
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-57) at Meden Laban in
Gagarawa Constituency. Essence World Wide Service Gagarawa 8,229,020.55 8,229,020.55 8,171,044.38 23/11/2018 8 weeks 100 Completed
101
Construction of the (3 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-62) at Kiri Town
Gujungu/Civil Defence and Nomi in Taura Constituency. Essence World Wide Service Taura 21,345,568.24 21,345,568.24 19,823,715.94 23/11/2018 8 weeks 100 Completed
102
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects at Danyayi in Kanya Babba
Constituency. Deetech Nig. Ltd. Babura 6,907,388.25 6,907,388.25 6,907,388.26 23/11/2018 8 weeks 100 Completed
103
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-42B) at Kafin Tugga in Fagam
Constituency. Yayarin Tukur Nig. Ltd. Gwaram 5,391,347.85 5,391,347.85 5,056,374.80 23/11/2018 8 weeks 100 Completed
104
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-38) at Digawar Kwando in
Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 4,797,719.10 4,797,719.10 4,566,453.35 23/11/2018 8 weeks 100 Completed
105
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-58) at Malam Anas Madachi in
Kirikasamma Constituency. Wajedu Nig. Ltd. K/kasamma 13,008,460.55 13,008,460.55 12,413,468.55 23/11/2018 8 weeks 100 Completed
106
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-48) at Chanchanda in Malam
Madori Constituency. Wajedu Nig. Ltd. M/madori 10,102,692.86 10,102,692.86 9,931,523.67 23/11/2018 10 weeks 100 Completed
107
Construction of the (2 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-53) at Addani and Ringim in
Yankwashi Constituency. Granitoids Engr. Services Ltd Yankwashi 24,386,180.20 24,386,180.20 24,328,485.04 23/11/2018 8 weeks 100 Completed
Balance C/F 1,081,754,080.94 1,084,545,916.95
8i
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,081,754,080.94 1,084,545,916.95
108
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-39) at Lafiya Madabe in Buji
Constituency. Yayarin Tukur Nig. Ltd. Buji 12,518,061.42 12,518,061.42 11,921,963.25 23/11/2018 8 weeks 100 Completed
109
Construction of the (2 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-51) at Dandi and Nisan Marke
Towns in Ringim Constituency. Marb Engr. Multi-Services Ringim 4,272,234.94 4,272,234.94 4,068,795.17 23/11/2018 8 weeks 100 Completed
110
Construction of the (3 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-50) at K/Bashe, Tsabare and
G/Sani in Ringim Constituency. Marb Engr. Multi-Services Ringim 6,170,717.41 6,170,717.41 5,876,873.10 23/11/2018 8 weeks 100 Completed
111
Construction of the (4 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-61) at Kwalam, Wayu, Bardu
and Yangayami in Taura Constituency. Baban Doki General Enterp Taura 22,075,259.57 22,075,259.57 21,024,056.73 23/11/2018 8 weeks 100 Completed
112
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-59) at Kargo mai Makaranta in
Malam Madori Constituency. Ramadan Construction Nig. Ltd. M/Madori 14,081,577.61 14,081,577.61 14,072,137.80 23/11/2018 8 weeks 100 Completed
113
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-37) at Ganuwar Kuka in Auyo
Constituency. AMM Manzo Nig. Ltd. Auyo 10,604,774.94 10,604,774.94 10,597,464.93 23/11/2018 8 weeks 100 Completed
114
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-43) at Bula Sabuwa in
Gagarawa Constituency. A.G.M. & Sons Nig. Ltd. Gagarawa 9,245,690.00 9,245,690.00 9,245,690.00 23/11/2018 8 weeks 100 Completed
115
Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-20) at Tudun Alhazaiand
Maigazari in Gumel Constituency. Lautai Genaral Investment Gumel 3,831,916.20 3,831,916.20 3,746,645.70 23/11/2018 6 weeks 100 Completed
116
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-19) at G/Dawa Kabawa,
Dahabu and Malaman Doko in Garki Constituency. MMz Garki Construction Nig. Garki 5,846,768.55 5,846,768.55 5,614,950.00 23/11/2018 6 weeks 100 Completed
117
Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects at Bayan GSS Wunti and Unguwar
Danjani in Hadejia Constituency. Jiffa Enterprises Hadejia 3,912,545.07 3,912,545.07 3,532,839.03 23/11/2018 6 weeks 100 Completed
118
Construction of (4 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects at Kagadama, Sarkin Gabas, Madaka
and Gamji in Gagarawa Constituency. Essence World Wide Service Gagarawa 7,835,700.60 7,835,700.60 7,807,061.39 23/11/2018 6 weeks 100 Completed
119
Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-36) at Rafin kanya and Garin
Kuttu in Taura Constituency. Nushe Business Resources Taura 3,918,404.70 3,918,404.70 3,743,300.00 23/11/2018 8 weeks 100 Completed
Balance C/F 1,186,067,731.95 1,188,859,567.96
8j
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,186,067,731.95 1,188,859,567.96
120
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects at Kubuna, Dolen Kwana and
Karanga in Birniwa Constituency. AMM Manzo Nig. Ltd. Birniwa 5,878,268.25 5,878,268.25 5,783,768.23 23/11/2018 6 weeks 100 Completed
121
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-29) at Barbawa in Kaugama
Constituency. Danfatu & Sons Nig. Ltd. Kaugama 1,952,522.85 1,952,522.85 1,930,022.85 23/11/2018 6 weeks 100 Completed
122
Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-3) at Yammaulu Insharuwa
ward Karade in Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 3,918,845.70 3,918,845.70 3,755,045.70 23/11/2018 6 weeks 100 Completed
123
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects at Kankaren Shatima in Maigatari
Constituency. ALLAH Abin Dogara Nig. Ltd. Maigatari 1,959,107.85 1,959,107.85 1,877,522.85 23/11/2018 6 weeks 100 Completed
124
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects at Kankaren Bakin Ruwa,
Kankaren Madawa and Idari in Maigatari Constituency. NBS & Sons Construction Nig. Maigatari 5,878,268.50 5,878,268.50 5,632,568.55 23/11/2018 6 weeks 100 Completed
125
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-6) at Malamawar G/Kwalli,
Azare Sabuwa and Kalgeri in Bulangu Constituency. Kawu Nig. Ltd. K/Hausa 5,881,121.97 5,881,121.97 5,795,089.17 23/11/2018 6 weeks 100 Completed
126
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-5) at Sabon Gidan Jabo,
Fadawa Karama and Dokori in Bulangu Constituency. Kawu Nig. Ltd. K/Hausa 5,869,568.55 5,869,568.55 5,645,892.31 23/11/2018 6 weeks 100 Completed
127
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-21) at Sabaru Gabas, Gada
Yamma and Kanti Gabas in Kazaure Constituency. Yanduna Ventures Nig. Ltd. Kazaure 5,881,418.50 5,881,418.50 5,632,568.55 23/11/2018 6 weeks 100 Completed
128
Construction of (4 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects at Dan Karaye, Bindaye, Lafiya and
Kokochi in Taura Constituency. Sambu Synergy Concept Ltd. Taura 7,830,026.40 7,830,026.40 7,486,599.96 23/11/2018 6 weeks 100 Completed
129
Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-25) at Malam Abba and
Alagarno in Maigatari Constituency. Nadada Ventures Nig. Ltd. Maigatari 3,919,263.76 3,919,263.76 3,721,445.70 23/11/2018 6 weeks 100 Completed
130
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects at Baramusa in Malam Madori
Constituency. Step By Step intgrated Servic M/Madori 10,100,798.17 10,100,798.17 9,621,612.18 23/11/2018 8 weeks 100 Completed
Balance C/F 1,245,136,942.45 1,247,928,778.46
8k
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,245,136,942.45 1,247,928,778.46
131
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-...) at Dallare, Barebari
Sankara and Digawar Kurmi in Ringim Constituency. Marb Engr. Multi-Services Ringim 5,884,568.55 5,884,568.55 5,632,568.55 23/11/2018 6 weeks 100 Completed
132
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-30) at Kaki Kankare,
Larabawa and Daunawa in Ringim Constituency. Marb Engr. Multi-Services Ringim 5,882,678.50 5,882,678.50 5,630,678.48 23/11/2018 6 weeks 100 Completed
133
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-3) at Yayarin Tukur Town in
Buji Constituency. Yayarin Tukur Nig. Ltd. Buji 1,961,519.70 1,961,519.70 1,877,522.80 23/11/2018 6 weeks 100 Completed
134
Construction of (2 No.) Two Daily Prayer Mosque 2018
Constituency Projects at Masheme and Tangari Tsagaya in
Garki Constituency. MMZ Garki Constr. Nig. Garki 3,915,162.00 3,915,162.00 3,743,809.45 14/11/2018 8 weeks 100 Completed
135
Construction of wall fencing and Grave yard (2018 phase II)
constituency projects (lot -64B) at B/Zango in Gwaram
Constituncy. Yayarin Tukur Nig Ltd Gwaram 10,524,058.65 10,524,058.65 10,022,912.99 23/11/2018 8 weeks 100 Completed
136
Construction of wall fencing and Grave yard (1No.) (2018
phase II) constituency projects (lot -65) at Dakayyawa town
in Kaugama Constituncy. Nabakwai Gen. Enterp Ltd Kaugama 10,175,937.42 10,175,937.42 10,161,792.63 23/11/2018 10 weeks 100 Completed
137
Completion/Renov. Of (1no.)Friday Prayer Mosque (2018
phase III) Constituency Projects (Lot-67 ) at Gada yamma in
kazaure Constituency. Yanduna Venture Nig Ltd kazaure 3,268,000.00 3,268,000.00 3,112,380.94 23/11/2018 8 weeks 100 Completed
138
Construction of (5No) five daily prayer mosques (2018 phase
II) constituency project (Lots -32) at agufa Gabas, markawa,
kadirawa,sarawiya and maiganjara in miga constituency Amia interg. Serv.Nig. Ltd Miga 9,781,364.25 9,781,364.25 9,361,364.25 23/11/2018 6 weeks 100 Completed
139
Construction of wall fencing, External works and Solar
Electricity Supply (2018 phase III) constituency projects at
JIBWIS Juma'at Mosque Basirka in Fagam Constituncy. Lines and Dimension Nig. Ltd Gwaram 12,484,914.10 12,484,914.10 11,890,363.80 31/12/18 8 weeks 100 Completed
140
Construction of wall fencing and Grave yard (2018 phase II)
constituency projects (lot -) at Kukuma in Buji Constituncy. Yayarin Tukur Nig Ltd Buji 8,320,638.93 8,320,638.93 7,954,570.48 23/11/2018 8 weeks 100 Completed
141
Renov. Of District Head house (2018 phase III) Constituency
Projects (Lot-26 ) at Auyo in Auyo Constituency. Na-bakwai Enterp. Ltd Auyo 6,127,766.75 6,127,766.75 5,835,963.33 23/11/2018 8 weeks 100 Completed
Balance C/F 1,323,463,551.30 1,326,255,387.31
8L
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,323,463,551.30 1,326,255,387.31
142
Construction of wall fencing and Grave yard (2018 phase II)
constituency projects (lot -) at Kiyawa Gabas kiyawa
Constituncy. AGM & Sons Nig. Ltd kiyawa 11,146,344.60 11,146,344.60 11,024,014.57 23/11/2018 8 weeks 100 Completed
143
Construction of wall fencing and Grave yard (2018 phase II)
constituency projects (lot -) at Gagara Yaga town in Gwaram
LGA AS Gaza inter. Serv. Nig ltd Gwaram 13,260,534.00 13,260,534.00 13,200,390.77 27/11/2018 8 weeks 100 Completed
144
Completion/Renov. Of (1no.)Friday Prayer Mosque (2018
phase III) Constituency Projects (Lot-65 ) at Yoruba Juma'at
mosque in Hadejia Constituency. Muhal Global concept Hadejia 4,013,760.20 4,013,760.20 3,822,702.10 23/11/2018 8 weeks 100 Completed
145
Completion/Renov. Of (2no.)Friday Prayer Mosque (2018
phase III) Constituency Projects (Lot- 62) at Shamakeri in
Bulangu Constituency. Kawu Nig. Ltd. K/Hausa 11,250,950.40 11,250,950.40 10,714,848.00 27/12/18 8 weeks 100 Completed
146
Completion/Renov. Of (2no.) Friday Prayer Mosque (2018
phase III) Constituency Projects (Lot-60) at Waloyi sabuwa,
JIBWIS Juma'at mosque in Bulangu Constituency. Kawu Nig Ltd K/Hausa 12,674,985.00 12,674,985.00 12,674,985.00 23/11/2018 8 weeks 100 Completed
147
Construction of (3No.) Friday prayer Mosque (2018 phase II)
Constituency project (lot -40) at Zangon kanya, waloyi
sabuwa and Tsangaiwa in Bulangu Constituency Kawu Nig Ltd K/Hausa 16,888,035.21 16,888,035.21 16,797,853.60 23/11/2018 8 weeks 100 Completed
148
Construction Of (4no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-30) at sabaru, Batatsaba and
Tudun wayo in kazaure Constituency. Yanduna Venture Nig Ltd kazaure 7,833,491.40 7,833,491.40 7,285,022.85 23/11/2018 6 weeks 100 Completed
149
Construction Of (2no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at kofar yamma anad rukutu
in Sule Tankarkar Constituency. Na'ayi Resources Ltd S/tankarkar 5,375,297.80 5,375,297.80 5,112,128.79 23/11/2018 8 weeks 100 Completed
150
Construction Of (5no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-7) at kuntukulu, yarma,
chiliga, Nafada and giwa in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/kudu 9,799,739.25 9,799,739.25 9,379,739.25 23/11/2018 8 weeks 100 Completed
151
Construction Of (2no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-) at kadira and tukuikui town
in guri Constituency. Jiffa enterprises Guri 3,912,545.07 3,912,545.07 3,606,083.67 23/11/2018 6 weeks 100 Completed
Balance C/F 1,419,619,234.23 1,422,411,070.24
8m
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,419,619,234.23 1,422,411,070.24
152
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-) at Riga yoka, kubulu and abir
in guri Constituency. Jiffa enterprises Guri 5,881,418.55 5,881,418.55 5,629,418.55 23/11/2018 6 weeks 100 Completed
153
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-23) at Dadin duniya, kargo and
maje gari in kiyawa Constituency. FAAHM Intreg. Resour. Ltd kiyawa 5,872,358.50 5,872,358.50 5,489,381.48 23/11/2018 6 weeks 100 Completed
154
Construction Of (4no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-19) at U/malam, kununrogo,
kankare and timbau in kanya babba Constituency. Deetech Nig Ltd Babura 7,846,091.40 7,846,091.40 7,510,091.40 23/11/2018 6 weeks 100 Completed
156
Construction Of (6no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-5) at Barwa, K/boka, Bulliti,
Dokaro, Lafiya and Jingargari in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/kudu 11,733,404.10 11,733,404.10 11,229,404.13 23/11/2018 8 weeks 100 Completed
157
Construction Of (5no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-4) at Chandam, Daurawa, Ajawa
bkd, Juwan Tudu and Ludduga in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/kudu 9,782,614.25 9,782,614.25 9,362,614.27 23/11/2018 8 weeks 100 Completed
158
Construction Of (4no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Masama, Malumawa,
Jinnako and Kintiri in Kirikasamma Constituency. Dabino interg.serv. Ltd Kirikasamma 7,085,135.75 7,085,135.75 6,865,270.06 23/11/2018 6 weeks 100 Completed
159
Construction Of (1no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Kirikasamma police
station in Kirikasamma Constituency. Dabino interg.serv. Ltd Kirikasamma 1,196,120.45 1,196,120.45 1,194,714.15 23/11/2018 8 weeks 100 Completed
160
Construction Of (1no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Garin Kosau in Maigatari
Constituency. Nadada Venture Nig Ltd Maigatari 1,952,627.20 1,952,627.20 1,913,222.85 23/11/2018 8 weeks 100 Completed
161
Construction Of (2no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-17) at Jabarna and Jahun Gabas
in Jahun Constituency. Khairussabah Nig ltd Jahun 3,918,645.50 3,918,645.50 3,746,645.70 23/11/2018 6 weeks 100 Completed
162
Construction Of (4no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-27) at Makera, Malikawa, Da'a
and Atafiyawar Gyatami in Miga Constituency. Khairussabah Nig ltd Miga 7,842,091.36 7,842,091.36 7,821,452.56 23/11/2018 6 weeks 100 Completed
163
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-28) atDunnaka, koramawa and
Gidan Yaya in Miga Constituency. Khairussabah Nig ltd Miga 5,880,473.55 5,880,473.55 5,864,986.05 23/11/2018 6 weeks 100 Completed
Balance C/F 1,488,610,214.84 1,491,402,050.85
8n
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,488,610,214.84 1,491,402,050.85
164
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Gaduwa, Tsangaya Yamma
and U/buluburum in Guri Constituency. AMIM Consult Nig Ltd Guri 5,877,322.55 5,877,322.55 5,617,993.50 23/11/2018 6 weeks 100 Completed
165
Construction Of (1no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Tasgen yamma in Guri
Constituency. AMIM Consult Nig Ltd Guri 1,959,420.85 1,959,420.85 1,877,522.85 23/11/2018 6 weeks 100 Completed
166
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Guri, Galadimari and
Majanguwa in Guri Constituency. Jiffa enterprises Guri 5,882,678.05 5,882,678.05 5,630,678.04 23/11/2018 6 weeks 100 Completed
167
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-10) at U/Gamji, Wale wale and
M/tahir in Garki Constituency. Mugin Inv. Nig ltd Garki 5,878,007.61 5,878,007.61 5,626,007.60 23/11/2018 6 weeks 100 Completed
168
Construction Of (4no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-) at Kurgunguma, babande,
koguran sabuwa and wauta in Garki Constituency. MMZ Garki contr. Nig Ltd Garki 7,841,169.36 7,841,169.36 7,510,091.40 23/11/2018 6 weeks 100 Completed
169
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-16) at Dandaga, Kangarwa and
Dogon dawa in Gagarawa Constituency. Essence world wide serv. Nig ltd Gagarawa 5,876,775.45 5,876,775.45 5,854,621.16 23/11/2018 6 weeks 100 Completed
170
Construction Of (5no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-6) at Damukashi, Lura, Asayaya
and Sundumina, Nafara in Birnin Kudu Constituency. Nushe Bus. Resou. Nig Ltd B/Kudu 9,807,614.25 9,807,614.25 9,387,614.25 23/11/2018 8 weeks 100 Completed
171
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-35) at Titi Town, Danmakama
and Adama in Sule Tankarkar Constituency. Nushe Bus. Resou. Nig Ltd S/Tankarkar 5,877,323.55 5,877,323.55 5,859,968.55 23/11/2018 8 weeks 100 Completed
172
Construction Of (4no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-16) at Dakila, Tauraruwa,
ankun Yamma and Matsaro in Hadejia Constituency. Xtrax 99 Interg. Serv. Nig Ltd Hadejia 7,844,831.40 7,844,831.40 7,192,088.07 23/11/2018 6 weeks 100 Completed
173
Construction Of (1no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-54) at Uza in Auyo
Constituency. Muhal Global concept Auyo 2,276,676.25 2,276,676.25 2,276,676.00 23/11/2018 8 weeks 100 Completed
174
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Jidawa, Kwannawa and
G/Darmara in Dutse Constituency. H.M Dangara ltd Dutse 5,879,843.00 5,879,843.00 5,628,473.55 23/11/2018 6 weeks 100 Completed
Balance C/F 1,553,611,877.16 1,556,403,713.17
8O
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,553,611,877.16 1,556,403,713.17
175
Construction Of (4no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-14) at Innakawa, Uduwa,
Lambuna and sabon garin ila in Gwaram Constituency. Yayarin Tukur Nig Ltd Gwaram 7,846,076.80 7,846,076.80 7,510,076.78 23/11/2018 6 weeks 100 Completed
176
Construction Of (6no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-17) at Kira Malumawar jabo,
satari, malumawar Jigawa,Alagarno and Lugga towns in
Bulangu K/Hausa Constituency, K/Hausa LGA. Kawu Nig Ltd K/Hausa 11,733,900.00 11,733,900.00 11,701,539.00 23/11/2018 8 weeks 100 Completed
178
Construction Of (4no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-10) at U/maina, Yara dankoshe,
karanjau and musa d/hajiya kukuma in Buji Constituency. Yayarin Tukur Nig Ltd Buji 7,825,091.40 7,825,091.40 7,469,528.43 23/11/2018 6 weeks 100 Completed
179
Construction Of (1no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-56) at Sara Kudu in Gwaram
Constituency. Yayarin Tukur Nig Ltd Gwaram 1,956,272.85 1,956,272.85 1,872,272.85 23/11/2018 6 weeks 100 Completed
180
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-24) at Kawal Gana, Bye pass
Gwaram and Maruta in Gwaram Constituency. Yayarin Tukur Nig Ltd Gwaram 5,868,818.55 5,868,818.55 5,616,818.55 23/11/2018 6 weeks 100 Completed
181
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-13) at Basirka A, Ali Kondigo
and madachi in Fagam Constituency. G.M Sara & sons Nig Ltd Gwaram 5,881,568.55 5,881,568.55 5,635,339.62 23/11/2018 8 weeks 100 Completed
182
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-15) at Yarfi, Gadama and
Dingaya in Fagam Constituency. G.M Sara & sons Nig Ltd Gwaram 5,875,118.55 5,875,118.55 5,628,905.75 23/11/2018 8 weeks 100 Completed
183
Construction Of (3no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-14) at Basirka Tsangaya,
S/Ruwa Digijin and chediya in Fagam Constituency. G.M Sara & sons Nig Ltd Gwaram 5,880,586.95 5,880,586.95 5,634,360.48 23/11/2018 8 weeks 100 Completed
184
Construction Of (2no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Gugurum and Wargale in
Birniwa Constituency. B.D.U Vent. Nig Ltd Birniwa 3,907,045.70 3,907,045.70 3,738,247.48 23/11/2018 6 weeks 100 Completed
185
Construction Of (1no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-26) at Inaruwanku in Malam
madori Constituency. Wajedu Nig Ltd M/madori 1,961,519.70 1,961,519.70 1,871,650.00 23/11/2018 6 weeks 100 Completed
186
Construction of (2No.) Friday Prayer Mosques 2018
Constituency Projects at Mamudawa and U/Kaya in Roni
Constituency. Na'ayi Resources Ltd. Roni 18,967,013.14 18,967,013.14 18,063,822.04 14/11/2018 8 weeks 100 Completed
Balance C/F 1,631,314,889.35 1,634,106,725.36
8p
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,631,314,889.35 1,634,106,725.36
187
Completion/Renovation of (2 No.) Friday Prayer Mosque
(2018 Phase III) Constituency Projects at Farin Dutse and
Chediya Towns in Fagam Constituency. A.A. Maikatako Gen. Enterp. Gwaram 13,213,177.10 13,213,177.10 12,583,978.18 23/11/2018 8 weeks 100 Completed
188
Construction of (2 No.) Daily Prayer Mosque (2018 Phase III)
Constituency Projects (Lot-1) at Zigon Fulani and Kataudi in
Auyo Constituency. Wajedu Nig. Ltd. Auyo 3,923,039.45 3,923,039.45 3,755,045.70 23/11/2018 6 weeks 100 Completed
189
Construction of (1 No.) Daily Prayer Mosque (2018 Phase III)
Constituency Projects at Ashura Madaki in Kafin Hausa
Constituency. Mugin Investment Nig. Ltd. K/Hausa 1,959,335.00 1,959,335.00 1,877,522.85 11/12/2018 8 weeks 100 Completed
190
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-56) at Unguwar Kanya in
Gwaram Constituency. Yayarin Tukur Nig. Ltd. Gwaram 1,959,790.35 1,959,790.35 1,875,790.35 14/12/2018 8 weeks 100 Completed
191
Construction of (3No.) Five Daily Prayer Mosques (2018
Phase II) Constituency Projects (Lot-1) at Maje Hausawa,
Jama'ar Alkali and Muran in Auyo Constituency. Ahmed Maidoya & Sons Auyo 5,821,382.70 5,821,382.70 5,569,382.70 23/12/2018 6 weeks 100 Completed
192
Construction of (1No.) Friday Prayer Mosques (2018 Phase
III) Constituency Projects at Baramusa in Malam madori
Constituency. Step by Step Interg. Serv M/madori 10,100,798.17 10,100,798.17 9,621,612.18 31/12/2018 8 weeks 100 Completed
193
Construction of (3No.) Five Daily Prayer Mosques (2018
Phase II) Constituency Projects (Lot-2) at Dogon Marke Tudu,
Takwasa and Akula Quarters Babura in Babura Constituency. Express Innovation Concept Babura 5,787,583.55 5,787,583.55 5,452,528.54 23/11/2018 6 weeks 100 Completed
194
Completion/Renovation of (1No.) Friday Prayer Mosques
2018 Constituency Projects (Lot-68) at Zugai in Roni
Constituency. Yanduna Ventures Ltd. Roni 4,231,861.26 4,231,861.26 4,030,352.45 14/11/2018 8 weeks 100 Completed
195
Construction of (1No.) Friday Prayer Mosques 2018
Constituency Projects at Kargo in Jahun Constituency. Yanduna Ventures Ltd. Jahun 3,674,875.89 3,674,875.89 3,596,966.88 14/11/2018 8 weeks 100 Completed
196
Renovation of (1No.) Juma'at Prayer Mosques (2018 Phase III)
Constituency Projects (Lot-59A) at Gatafa in Auyo
Constituency. A.G.M. & Sons Nig. Ltd. Auyo 9,331,213.96 9,331,213.96 9,327,464.19 24/12/2018 8 weeks 100 Completed
197
Construction of (3No.) Daily Prayer Mosques (2018 Phase III)
Constituency Projects Karofin Tsamiya, Maje and Ruwan
Dutse and completion of (1No.) Daily Prayer Mosques at Roni
Unguwar Sani Kwati in Roni Constituency. Na'ayi Resources Ltd. Roni 7,821,847.00 7,821,847.00 7,372,828.41 17/12/2018 6 weeks 100 Completed
198
Construction of (2No.) Daily Prayer Mosques (2018 Phase III)
Constituency Projects (Lot-2) at Aunaka and Katirje Fulani in
Babura Constituency. A.A. Aljazeera Agro Proc. Babura 3,919,049.70 3,919,049.70 3,755,045.70 23/11/2018 6 weeks 100 Completed
Balance C/F 1,703,058,843.48 1,705,850,679.49
8q
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 1,703,058,843.48 1,705,850,679.49
199
Completion/Renovation of (1No.) Friday Prayer Mosques
(2018 Phase III) Constituency Projects at Danyarda Gari in
Sule Tankarkar Constituency. A.A. Aljazeera Agro Proc. S/Tankarkar 2,820,120.00 2,820,120.00 2,565,078.56 23/11/2018 8 weeks 100 Completed
200
Construction of (4No.) Five Daily Prayer Mosques (2018 Phase
III) Constituency Projects at Darare, Gwanda Gwaro, Udawaki
and Ma'azu in Sule Tankarkar Constituency. A.A. Aljazeera Agro Proc. S/Tankarkar 7,841,891.40 7,841,891.40 7,510,091.40 23/11/2018 6 weeks 100 Completed
201
Constr of (1no) Friday mosque at Kuda in Yankwashi (2018
phase III) constituency project Deetech Nig Ltd. Ynakwashi 15,576,291.17 15,576,291.17 15,417,313.02 17/12/2018 12 Weeks 100 Completed
202
Renov of Jumaat Mosque (2018 phase III) consultancy project
(Lot-35) at Masko in Babura Muhabib Nig Ltd Babura 4,545,883.87 4,545,883.87 4,534,163.18 25/11/2018 8 weeks 100 Completed
203
Constr of Juma'at Prayer mosques 2017 constituency projects
phase III remaining works (Lot-5) at Sunkuye and Suga in
Kirikasamma Constituency. Alh Umaru Babandoki K/Kasamma 16,539,295.58 16,539,295.58 16,215,864.03 16/4/2018 12 weeks 100 On-going
TOTAL 1,750,382,325.50 1,753,174,161.51
8r
Ministry of Information
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Procurement of Electrical Equipments (phase 1) Zurfat Investment Nig. Ltd Dutse 18,049,500.00 18,049,500.00 16,371,428.57 30/04/2019 4 weeks 100 Completed
2 Renov of Gumel township stadium Farham Synergy Gumel 34,986,981.93 34,986,981.93 34,981,927.27 10/1/2019 6 weeks 100 Completed
3 Renov of Hadejia township stadium Kawu Nig. Ltd. Hadejia 5,588,405.03 5,588,405.03 5,326,332.60 17/10/2019 4 weeks 100 Completed
4 Renov of Dutse Sports Complex Gare Invest. Nig. Ltd. Dutse 18,192,343.02 18,192,343.02 18,192,337.17 10/1/2019 12 weeks 100 Completed
5 Renov of Dutse township stadium M aikatako & Sons Dutse 9,749,837.85 9,749,837.85 8,446,140.81 12/11/2019 4 weeks 100 Completed
6 Renov of Dutse township stadium (additional works) Pullad Global Dutse 8,621,123.75 8,621,123.75 8,420,632.05 20/02/20 4 weeks 100 Completed
Total 95,188,191.58 95,188,191.58
Jigawa State Polytechnic
POST CONTRACT PROJECT EVALUATION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Constr of Wall fence Loyalty Property Dutse 16,404,601.62 16,404,601.62 16,386,322.31 28/01/19 12 weeks 100 Completed
Total 16,404,601.62 16,404,601.62
Binyaminu Polytechnic Hadejia
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T A M OUN T REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
(N ) CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1
Fabrication of (300no.) Detached classroom Desk K-Manu Eng. Ltd. Hadejia 9,090,000.00 9,090,000.00 9,089,999.99 22/10/2018 12 w eeks 100 Completed
TOTAL 9,090,000.00 9,090,000.00
Ministry of Environment
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 Constr. of Drainage at K/fada basirka (phase II) Dazal Nig. Ltd. Gwaram 8,236,789.42 8,236,789.42 8,127,129.15 18/09/2017 8 weeks
100
Completed
2
Construction of Drainages at makwalla (A) and
Unguwar sarkin Busa Quarters in Hadejia Local
Govt area Muhal Global concept Hadejia 41,936,999.19 41,936,999.19 41,936,999.19 23/11/2018 16 weeks
100
Completed
Total 50,173,788.61 50,173,788.61
Informatics Institute Kazaure
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Renov ation of 40 rooms male hostel Talaku Int. Serv ices Ltd. Kazaure 17,023,989.64 17,023,989.64 17,023,870.97 29/11/2017 8 w eeks 100 Completed
2 Renov ation of Female Hostel Talaku Int. Serv ices Ltd. Kazaure 12,718,116.36 12,718,116.36 12,183,694.37 29/11/2017 8 w eeks 100 Completed
3 Renov . Of 2no. Lecture Theatre and 4no. Staff Qtrs. M.S. Danzomo Nig. Ltd. Kazaure 2,491,474.26 2,491,474.26 2,491,474.23 20/12/2018 8 w eeks 100 Completed
4 Renov . Of 4no. Houses M.S. Danzomo Nig. Ltd. Kazaure 1,896,058.29 1,896,058.29 1,896,058.29 20/12/2018 8 w eeks 100 Completed
5Supply of Books Ngloma Consr. Co. Kazaure 9,371,485.34 9,371,485.34 9,371,485.34 18/04/2019 8 w eeks 100 Completed
6Supply & Installation of Solar sy stem and street light Ngloma Consr. Co. Kazaure 62,121,465.00 62,121,465.00 60,901,296.75 28/6/2019 8 w eeks 100 Completed
7 Constr 1no student Hostel on ex isting foundation Talaku Int. Serv ices Ltd. Kazaure 40,835,085.78 40,835,085.78 37,630,857.88 19/11/2018 12 w eeks 100 Completed
TOTAL 146,457,674.67 146,457,674.67
Government House
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. STATUS REMARKS
(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 Purchase of 2No. Fa irly used vechicle Modang investment Ltd in the s tate 39,900,000.00 39,900,000.00 39,900,000.00 20/06/2019 2 weeks 100 Completed
2 Purchase of 15no. Vehicles CIG motor Company Nig Ltd in the s tate 169,533,611.20 169,533,611.20 169,533,611.20 9/12/2019 2 weeks 100 Completed
Total 209,433,611.20 209,433,611.20
Directorate of Economic Empowerment
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1
Approval for the release of Three Hundred and Fourty
Thousand Naira (N340,000,000.00) only for the
Procurement of Fifty (50no.) tractors from JASCO for
Distribution as Empowerment loans to Farmers. JASCO Across the state 340,000,000.00 340,000,000.00 24/12/2018 3 months 100 Completed
Total 340,000,000.00 340,000,000.00
Deputy Governor Office
POST CONTRACT PROJECT EVALUATION
S/ N P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T R EVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
A M OUN T (N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
1
Renov ation works at Deputy Gov ernor's
Official Residence, Dutse
Daniy a Atiku
Associate Ltd. Dutse 1 7 ,1 29,21 0.40 1 7 ,1 29,21 0.40 1 7 1 21 001 .7 6 6/9/201 9 1 2 weeks 100 Completed
2
Procurement and Insta l lation of Furniture at the
Officia l Res idence of His Excel lency, the Deputy
Governor at Dutse Aimim Consult Nig. Ltd. Dutse 34,825,680.00 43,575,855.00 43575855 19/9/2019 8 weeks 100 Completed
Total 51,954,890.40 60,705,065.40
Jigawa State College of Islamic and Legal Studies Ringim
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Constr. of Library Complex (phase 1) at College of Islamic
and Legal Studies, Ringim
R & Partners Ltd. Ringim 70,000,000.00 70,000,000.00 69,998,914.36 20/10/2016 24 w eeks 100 Completed
2 Constr of Liabrary Complex (phase II) R & Partners Ltd. Ringim 47,930,224.47 47,930,224.47 47,902,467.25 27/11/2017 20 w eeks 100 Completed
3 Constr of Liabrary Complex (phase III) Back bone Global Ringim 54,024,795.20 54,024,795.20 53,963,448.21 28/12/2018 16 w eeks 100 Completed
4 Supply and Installation of 52no. Standalone street light Sims Global Ringim 32,215,050.00 32,215,050.00 32,215,050.00 15/5/2019 8 w eeks 100 Completed
Total 204,170,069.67 204,170,069.67
Ministry of Health
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 Constr. of New Gen. Hospital at B/Kudu Datum Constr. Limited B/kudu 1,498,970,413.02 1,894,683,085.99 1,145,153,325.12 19/5/2014 8 months 60 On-going
2
Commissioning/engagement as consultants for
the supervision of construction of new general
hospital at Birnin kudu Design Plus B/Kudu 74,010,950.99 74,010,950.99 67,484,513.49 27/5/2014 10 month 91 On-going
3
Renovation of X-Ray Block and Others at Hadejia
General Hospital
Spring Global Service Hadejia 10,771,117.36 10,771,117.36 4,502,571.15 4/2/2014 2month 43 Terminated
4
Conversion of Catering Rest House to School of
Nursing, Hadejia Business Gold Ltd. Hadejia 67,757,628.62 67,757,628.62 38,524,250.94 3/22/2016 3 months 57 Revoked
5
General Renov. /Improvement works at Fagam
Primary Health Care Ngaloma Const. Co. Ltd. Gwaram 64,869,057.07 71,417,939.66 64,370,619.95 30/12/2016 12 weeks 86 On-going
6
Constr. Of New 250 Bed Specialist Hospital in
Hadejia PHILKO LIMITED Hadejia 1,593,314,294.25 1,867,953,470.57 1,201,703,551.71 11/10/2017 18 months 64 On-going
7
Engagment as Consultant for the supervision of the
Constr. of New Specialist Hospital, Hadejia HAG Eng. Nig. Ltd. Hadejia 67,363,041.01 67,363,041.01 45,503,239.00 19/10/2017 16 months 67 On-going
8
Constr of New General Hospital at Gantsa in Buji
LGA Ngaloma Constr Ltd. Buji 465,983,075.70 465,983,075.70 383,967,848.25 12/7/2018 9 months 82 On-going
9 Constr of New General Hospital at Garki Babandoki Gen. Entp. Garki 493,805,327.06 493,805,327.06 392,405,349.52 12/7/2018 12 months 79 On-going
10
Constr of New General Hospital at Guri town,
Headquarters of Guri LGA Retro Constr Ltd. Guri 538,386,262.75 538,386,262.75 367,653,903.85 12/7/2018 12 months 68 On-going
11
Constr of New School of Nursing and Midwifery at
Babura, Headquarters of Babura LGA Gridarch Nig. Ltd. Babura 591,562,261.76 591,562,261.76 453,962,997.41 12/7/2018 12 months 77 On-going
12
Upgrading of Miga PHC to General Hospital at Miga
town, Miga LGA. Sabongarin Yaya Miga 98,226,184.67 98,226,184.67 93,527,265.11 3/9/2018 24 weeks 91 On-going
13
Engagement as Consultant for the Supervision of
the Constr. of New General Hospital, Guri AADC Limited Guri 34,870,673.74 34,870,673.74 21,968,524.45 30/8/2018 12 months 63 On-going
14
Engagement as Consultant for the Supervision of
the Constr. of New Specialist Hospital, Kazaure HAG Eng. Consultants Kazaure 78,006,110.10 78,006,110.10 51,531,977.61 10/8/2018 16 months 66 On-going
15
Engagement as Consultant for the Supervision of
the Constr. of New General Hospital, Gantsa Blue Urban Transnational Buji 33,925,256.47 33,925,256.47 20,593,195.17 10/8/2018 9 months 60 On-going
16
Engagement as Consultant for the Supervision of
the Constr. of New General Hospital, Garki Zeebro Global Resources Garki 34,321,462.71 34,321,462.71 20,670,835.53 10/8/2018 12 months 58 On-going
17 Constr. of New Specialist Hospital at Kazaure Afdin Constr Co. Ltd. Kazaure 1,893,240,056.40 1,893,240,056.40 1,003,430,526.00 5/7/2018 16 months 53 On-going
18
Supply and Installation of Medical equipments to
the newly constructed 31no. BHC across the state. Mashasha Investment Ltd.Across the state 98,065,965.00 98,065,965.00 25/4/2018 20 weeks On-going
Balance C/F 7,737,449,138.68 8,414,349,870.56
1a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Balance B/F 7,737,449,138.68 8,414,349,870.56
19
Co ns ultant fo r the s upervis io n o f the co ns truc tio n o f new
s cho o l o f Nurs ing and Midwifery a t Babura INTERGRAP H CONSULT Babura 50,318,699.92 50,318,699.92 35,992,089.38 24/12/2018 12 mo nths 72 On-going
20
Supply and Ins ta lla tio n o f Medica l equipments to the newly
co ns truc ted 31no . BHC acro s s the s ta te . G.M. Sara & So ns Ltd. Acro s s the s ta te 4,129,061.98 4,129,061.98 16/4/2018 6 weeks
21
Supply and Ins ta lla tio n o f Medica l equipments to the newly
co ns truc ted 31no . BHC acro s s the s ta te . Mas has ha Inves tment Ltd. Acro s s the s ta te 98,065,965.00 98,065,965.00 25/4/2018 20 weeks On-going
22
Co ns ultant fo r the s upervis io n o f the co ns truc tio n o f new
s cho o l o f Nurs ing and Midwifery a t Babura INTERGRAP H CONSULT Babura 50,318,699.92 50,318,699.92 35,992,089.38 24/12/2018 12 mo nths 72 On-going
23
Supply and Ins ta lla tio n o f Medica l equipments to the newly
co ns truc ted 31no . BHC acro s s the s ta te . G.M. Sara & So ns Ltd. Acro s s the s ta te 4,129,061.98 4,129,061.98 16/4/2018 6 weeks On-going
24
Constr o f 3no M odified Basic Health Clinics at Bagadaza,
Larkan and Dukwana in Fagam Constituency (2019
Constituency pro jects) Yayarin Tukur Nig Ltd Gwaram 25,565,018.85 25,565,018.85 24/12/2019 12 weeks On-going
25 Constr o f Basic Health Centre (BHC) at M asaya Village in Kiyawa Constituency (2nd quarter 2018 Constituency pro ject)Umar Aliyu & Sons Nig Ltd Kiyawa 11,853,799.02 11,853,799.02 6/12/2019 12 weeks On-going
26
Constr. Of 1No. Basic Health Clinic at Hangu Village in
Gwiwa Constituency pro ject 2019 M anhaf Global Constr Nig Ltd Gwiwa 19,663,090.37 19,663,090.37 27/12/2019 16 Weeks On-going
27
Supply and installation of medical equipment to the 25No.
Newly constructed basic health clinic across the state. Dangata mem. inv. Ltd Across the state 95,423,350.00 95,423,350.00 11/12/2019 8 weeks On-going
Total 8,096,915,885.72 8,773,816,617.60
1b
Ministry of Water
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1
Rehab. of Water Supply Schemes across the state
at Gwaram Zone (Water Board) Interworld I & E Gwaram 27,207,315.85 27,207,315.85 25,403,004.38 9/21/2015 12 weeks 89 On-going
2 Constr. Of 40no. Hand pumps AGM & Sons Ltd. State 28,000,000.00 28,000,000.00 18,000,009.00 3/24/2014 6 months 65 Terminated
3
Constr. of Hand Pumps Water Supply Schemes
(phase II) as Constituency projects at Yosaro,
Dilima/Zaramba and Mungulo in B/Kudu
Constituency. A.A. Aljazeera Agro Properties B/Kudu 1,657,215.00 1,657,215.00 29/3/2017 8 weeks Stalled
4
Constsruction of Hand pumps Water supply
schemes (phase II) as constituency project at
Yola, Masanawa, Larabar Gulai, Katanga Kudu,
Dan koli and Dubal in Kiyawa Constituency. DE-MASTBO Kiyawa 3,331,430.00 3,331,430.00 29/03/2017 8 weeks Stalled
5
Construction of Solar Powered Water supply
schemes (Phase II) as constituency Projects at
Sabuwar Rafa (Andaza ward ) in Dutse
constituency DE-MASTBO Dutse 6,270,000.00 6,270,000.00 29/03/2017 8 weeks Stalled
6
Constr. Of 4no. Hand pumps Water supply
schemes (phase II) as Constituency projects at
Kofar Gidan Liman, Bayan Gidan Sarkin Bai,
Zankuwa fulani and Sabuwar SSS in Garki
Constituency. Taqib Ventures Nig. Ltd. Garki 2,340,000.00 2,340,000.00 21/6/2017 8 weeks Stalled
7
Constr. Of Solar Powered Water Supply Schemes
(Phase I) as Constituency Project at Marma in
Kirikasamma Constituency LOYALTY PROPERTIES LTD K/Kasamma 6,943,387.00 6,943,387.00 7/8/2017 8 Weeks Stalled
8
Construction of (1No.) Hand pump water supply
Schemes 2017 Constituency Project Phase II (Lot-
3) at Tsattiya in Dutse Constituency Loyalty Properties Ltd Dutse 798,000.00 798,000.00 1/24/2018 8 weeks On-going
9
Construction of 91No.) Solar Powered water
supply scheme 2017 constituency Phase II Project
(Lot-16) at Gambawa in Miga Constituency Loyalty Properties Miga 6,968,430.00 6,968,430.00 1/24/2018 8 weeks On-going
10
Constr. Of (1no.) Solar [powered water supply
scheme 2017 constituency phase II project (LOT-
27) at Gacharam in Guri Constituency. Limis Brothers & Co. Guri 6,968,430.00 6,968,430.00 24/1/2018 8 weeks On-going
11
Conversion of Motorizied Boreholes to Solar
Powered Water supply at Garki main Station in
Garki Local Govt Area. Sims Global Resources Garki 34,070,557.50 34,070,557.50 18,327,487.50 7/2/2018 12 Weeks 52 On-going
BAL. C/F 124,554,765.35 124,554,765.35
2a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 124,554,765.35 124,554,765.35
12
Constr of (1no.) Solar Powered water supply
schemes 2017 constituency phase III projects (Lot-
13) at Kangarwa in Maigatari Constituency Jignaj Global Constr Ltd. Maigatari 6,968,430.00 6,968,430.00 21/3/2018 8 weeks On-going
13
Construction of (9No.) Hand Pumps Water supply
scheme 2017 Constituency phase II Projects (Lot-
8) at Gidan Iliyasu, Mai Goro, Falari Burburwa,
Zulkiya Kila, Kila by pass, Sara cikin gari, Kuka
manoma, Kafin torto and Fiji in Gwaram
Constituency. A.A. Aljazeera Agro Proc. Gwaram 7,202,791.35 7,202,791.35 5,588,165.61 24/1/2018 8 Weeks 74 On-going
14
Constr of (1no.) Solar Powered Water Supply
Scheme Constituency Projects (2018 phase 1) Lot-
7 at Constituency. Jignaj Global Ltd. 6,023,115.00 6,023,115.00 17/10/2018 8 weeks On-going
15
Constr of Hand pump Boreholes as constituency
projects (2018 phase III) Lot-8 at Nasarawa,
Saunawa Fulani, Kashin Ganji, Kirya, Galma,
Wailare, Rafin Kaba, Chakurawa, Timbi, Joganai,
Matsari, Fulanin Maikanbu, Buta, Makera, U/tudu,
Fulanin Dakata, G/Gashi, Malamawa Dankabo,
Danyaka fulani, JSS Garki, Sabuwar U/Arewa,
Daurawa Yamma, Gurarraji and Kuttu in Garki
Constituency. Mugin Invest. Nig. Ltd. Garki 17,703,000.00 17,703,000.00 18/12/2018 12 weeks On-going
16
Constr of Water Collection points constituency
projects (2018 phase III) Lot-22 at Gangara,
Yarbarewa, JSS Doko, Barebari, Dan Kargo, Mahoni,
Jangari, Dunguzu, Masare and Koyama in Garki
Constituency. Mugin Invest. Nig. Ltd. Garki 12,588,450.00 12,588,450.00 18/12/2018 10 weeks On-going
17
Constr of Hand pump Boreholes as constituency
projects (2018 phase II) Lot-14 at Kanzon Kokori,
D/Kyaure Yamma, Gafaya B., G.Baba Gagare D/Toca,
Aguran Mazana, Dangoli Gabas and Gafaya in Kafin
Hausa Constituency. Alkawakeb Global Concept K/Hausa 5,164,110.00 5,164,110.00 18/12/2018 8 weeks On-going
18
Constr. Of (4no.) Hand pumps water supply
Scheme Consultancy projects (2018 phase) Lot 20
at Fulanin G. Dunfu in Taura Constituency. Faahm Integrated Resource Taura 2,942,100.00 2,942,100.00 17/10/2018 6 weeks On-going
19
Construction of (1NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot
18 at Ban-iyaka in Roni Constituency. HikimaSynergy Gen Entp Nig Roni 733,918.50 733,918.50 17/10/2018 4 weeks On-going
BAL. C/F 183,880,680.20 183,880,680.20
2b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 183,880,680.20 183,880,680.20
20
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-21) at Fagam in Fagam Constituency
Gwaram LGA. Loyalty Properties Ltd. Gwaram 6,023,010.00 6,023,010.00 23/11/2018 8 weeks On-going
21
Construction of Block of 2-Classroom Islamiyya
(1NO.) Lot-11 at Jibori in Kirikasamma
Constituency. Tosarawa Global Ltd. Kirikasamma 3,097,448.45 3,097,448.45 1/11/2018 4 Weeks On-going
22
Construction of (8NO.) Hand Pumps Water supply
scheme Constituency projects (2018 Phase I) Lot
14 at Muna, Mundu, Kwagga, Fulanin Hauwa, Jakai
Fulani, Dangaigai, Inguwar Goje and Kadagawa in
Kanya Babba Constituency. Babura Local
Government Area. DeeTech Nig Ltd. Babura 5,905,200.00 5,905,200.00 15/10/2018 8 weeks On-going
23
Construction of the (1 No.) Solar Powered Water
Supply Schemes 2018 Constituency Phase III
Projects (Lot-18) at Kaya Jamu in Maigatari
Constituency. Alkawakeb Global Concept Maigatari 6,023,115.00 6,023,115.00 23/11/2018 8 weeks On-going
24
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-32 at Yalwa in Gagarawa
Constituency. Farham Intgratred Resources Gagarawa 6,023,115.00 6,023,115.00 23/11/2018 8 weeks On-going
25
Construction of the (1 No.) Solar Powered Water
Supply Schemes Constituency Projects (2018
Phase II) Lot-33 at Medin Saleh in Gagarawa
Constituency. Farham Intgratred Resources Gagarawa 6,022,275.00 6,022,275.00 23/11/2018 8 weeks On-going
26
Upgrading and Conversion of (30 No.) Water
Supply Schemes to Solar Powered System Across
the State (Lot-1). Sims Global Resouces Nig. across the State 240,169,437.35 240,169,437.35 184,805,303.97 14/11/2018 3 Months 77 On-going
27
Conversion of 2no. Motorized boreholes to Solar
powered water supply schemes at Babura town in
Babura LGA. SIMS Global Resources Babura 56,502,805.27 56,502,805.27 31/12/2018 12 weeks On-going
28
Construction of Water Collection Point as
Constituency Projects (2018 Phase II) Lot-32 at
Maigatari (2No.) Maloya, Bosuwa, Galadi, Madana
and Jajeri in Maigatari Constituency. Jag & H Intgrated Services Ltd. Maigatari 7,358,173.38 7,358,173.38 18/12/2018 8 weeks On-going
BAL. C/F 521,005,259.65 521,005,259.65
2c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 521,005,259.65 521,005,259.65
29
Constr of Hand pump Boreholes as constituency
projects (2018 phase II) Lot-14 at Kanzo kokori,
D/kyaure yamma, Gafaya B, Baba Gagare D/Toca,
Aguran mazana, Dangoli Gabas and Gafaya in
K/Hausa Constituency. Alkawakeb Global Concept K/Hausa 5,164,110.00 5,164,110.00 18/12/2018 8 weeks On-going
30
Improvement of Gwaram Tsohuwa and Gwaram
Sabuwa Towns Water Supply Schemes Nushe Business Resources Gwaram 122,870,123.46 122,870,123.46 59,837,762.25 28/11/2018 6 weeks 48 On-going
31
Upgrading and Conversion of 22No. Small Towns
Water Supply Schemes to Solar Powered Water
supply Scheme (Lot-1) at Maitsamiya in Sule
Tankarkar, Sarkin gandu in Sule Tankarkar, Medu
in Gagarawa, Dankumbo in Maigatari, Giginya in
Babura,Dorawa in Babura Tasawa in Babura,
Samamiyya in Birninkudu, Bamaina in Birnin kudu,
Kantoga in Birnin kudu, Kila kudu, in Gwaram Kila
Orchad in Gwaram, Jidawa in Dutse, Aujara A. B. & C
in Jahun, Girbobo in Kaugama, Margadu in Birniwa,
Batatsaba in Guri, Tuntube in Kazaure and Sada in
Roni. Sims Global Resources State 204,765,713.15 204,765,713.15 167,257,096.65 24/12/2018 4 month 82 On-going
32
Construction of Hand Pump Boreholes Water
Supply Schemes Constituency Projects (2018
Phase III) Lot-11 at Katsiro Gidan Jaka, Mai Yadiya,
Kwarin Sanka, Gama Fulani, Unguwar Dani Fulani,
Gyauraji Alhazai, Torankayi, Makaranta Gabas
ZangonKaigamari, Kanwayi, Tsalliyawa katagum,
dangewaye, kwanjamawa, albirakyau, gidan
sansani, shafatu, gauzagidandorawa, narba kauye,
komai ALLAH yayi, ringimawa fulani, jikin kotu,
gargabo, fanfam liba, zagau fulani, gidan dan wanka,
harbo tsohuwa, harbo sabuwa, zarga, nahuce
harbo, tazara gidan gabas, gaskawa, turubu, kurfai
fulani, koya tsangayar tsoho, bagamarusabon gari,
dogawa bankin titi and jahun police station in jahun
Constituency Loyalty Properties Nig. Ltd. Jahun 28,035,640.00 28,035,640.00 18/12/2018 15 weeks On-going
BAL. C/F 881,840,846.26 881,840,846.26
2d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 881,840,846.26 881,840,846.26
33
Construction of Hand Pump Boreholes as
Constituency Projects (2018 Phase II) Lot-13 at
Shamsul Duhu Islamiyya, Achau Makaranta,
Gwanfai Yamma, Afun funa, Akena Fulani, Gwanfai
Malamai Magama, Birjawa Fulani, AskawaGidan
makera, Alkalawa, makanin makera, kamaiAujara
gidan kaya fulani, achau barnoji, rindai dina,
unguwar tile, juniorarabicaujara, kauyen makama,
unguwar yakubu tubabe, buki tsurutawa, garawai,
sabuwar abujagabashi, yantsuru, kwarin
malam,dashi yar jigawa, kwaru nula, kadoma kagul,
kargo, fagen ganji, gurji, Alhazai bakin kasuwa
jahun, rigar larabargambadungu, lungun mai katako
and sabuwar unguwa jahun in jahun Constituency. Loyalty Properties Nig. Ltd. Jahun 27,882,120.00 27,882,120.00 18/12/2018 14 weeks On-going
34
Constr of Solar powered water supply schemes at
new market, Zai/Galadimawa and Improvement
works at Shuwarin Sabuwa and Shuwarin main
pump stations, Dutse zone. China Zhanghao Nig. Ltd. Dutse 95,232,647.00 95,232,647.00 81,979,563.75 31/12/2018 16 weeks 86 On-going
35
Upgrading and Conversion of Motorized Boreholes
to Solar Powered Water supply Scheme Sabon
Garin Takanebu Town in Miga L.G.A. of Jahun Zone. Sims Global Resources Ltd Miga 17,238,621.65 17,238,621.65 12,608,859.90 31/12/2018 8 weeks 73 On-going
36
Conversion of (15No.) Hand Pumps to Solar
Powered Water supply Schemes at Babura
Yamma, Yangadi, Zuru, Gadi, Dan Barage, Hayin
Buzu, Kuka, Gasakoli, Duzau, Yada, Kaki Zago,
Gatuta Sansami, Kankare tukurkusa and Lamba in
Babura L.G.A. Sims Global Resources Ltd Babura 15,301,125.00 15,301,125.00 31/12/2018 10 weeks On-going
37
Conversion of (12No.) Hand Pumps to Solar
Powered Water supply Schemes at Dan Amale,
Walawa, Yanmaulu, Unguwar Ma'aruf, Batali,
Kanya Gari, Dankarda, Babura Gabas, Malamawa,
Figi, Dunkumi and Duwala in Babura L.G.A. Sims Global Resources Ltd Babura 12,240,900.00 12,240,900.00 31/12/2018 10 weeks On-going
BAL. C/F 1,049,736,259.91 1,049,736,259.91
2e
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,049,736,259.91 1,049,736,259.91
38
Construction of Water Collection Points as
Constituency Projects (2018 Phase III) Lot-26 at
Kwanar Duniya, Kogon Bara and Jobi in Maigatari
Constituency. Danbanki Gen. Enterprises Maigatari 3,679,089.75 3,679,089.75 18/12/2018 8 weeks On-going
39
Construction of Water Collection Points as
Constituency Projects (2018 Phase II) Lot-31 at
Yelleman (2No.) Dakayyawa (2No.) and Yellaman
Tijjanai (2No.) in Kaugama Constituency. Alkawakeb Global Concept Ltd Kaugama 7,358,173.38 7,358,173.38 18/12/2018 8 weeks On-going
40
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-8 at mai dashi, Idi gwamna, unguwar
malam, rigar lamido, adiyani islamiyya, dagana
Nato, daba, dirba, rigar malam wuri, yalwa
tsangaya, goni garin una, askandi arinjasko, rigar
wakilin dajjo lafiya, rigar babare, and rigar duka
maza in Guri Constituency AYH Intg. Serv. Ltd Guri 10,331,489.00 10,331,489.00 11/12/2019 8 weeks On-going
41
Conversion of 10No hand Pump Boreholes to Solar
in at Uku da Sisi, Ajjah, Mudirin gadi, Mundu,
unguwar Ganji, Kafin Danyayi, Unguwar gawo,
Dabawa, Katirje and Tsadarwa in Babura Local
Government Area Sims Global Res Babura 10,276,880.00 10,276,880.00 8,221,500.00 11/7/2018 8 weeks 76% On-Going
42
Construction of 1No. Solar Powered Water Supply
Scheme at Dora in Garki LGA Ringim Zone Sims Global Resources Ringim 6,023,325.00 6,023,325.00 16/4/2019 8 Weeks On-going
43
Construction of 6No Hand Pump Boreholes water
supply scheme at Yandamo Kulle 2, umarni,
Modoji Babba, Fulanin Riggade, Gidan Hardo Musa
( Fulanin Asayaya) in Sule Tankarkar Local
Government Area and Tamburawa in Kafin Hausa
LGA K-Manu Gen Construction
S/tankarkar +
K/Hausa 4,427,640.00 4,427,640.00 3,680,475.75 8/5/2019 12 weeks 83 On-going
44
Upgrading and Conversion of 1no. Motorised
water supply scheme to Solar power at UKU da SISI
Sabuwa in Babura LGA Sims Nig. Ltd. Babura 6,767,532.45 6,767,532.45 27/9/2019 8 weeks On-going
45
Rehab. of 13no. Water supply scheme at Ringim,
Kazaure and Gumel LGA Sims Nig. Ltd. Gumel 12,788,475.00 12,788,475.00 27/9/2019 8 weeks On-going
BAL. C/F 1,111,388,864.49 1,111,388,864.49
2f
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,111,388,864.49 1,111,388,864.49
46
Constr of (1no.) New Solar powered water supply
scheme at YAN Maulu Tsohuwa in Babura LGA Sims Nig. Ltd. Babura 6,023,325.00 6,023,325.00 27/9/2019 8 weeks On-going
47
Upgrading and Conversion of 1no. Motorised
water supply scheme to Solar powered atJigawar
Dan Ali, Garun Gudunya in Babura LGA and JEKE in
S/Tankarkar LGA Sims Nig. Ltd. S/Tankarkar 18,459,647.97 18,459,647.97 11/10/2019 8 weeks On-going
48 Rehab. Of 19no. Water supply schemein Ringim Sims Nig. Ltd. Ringim 17,361,750.00 17,361,750.00 11/10/2019 8 weeks On-going
49
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-1 at Fulanin Gamba, Fulanin Garu and
Fulanin Kafur in Auyo Contituency. AMM Manzo Nig Ltd Auyo 2,210,922.00 2,210,922.00 11/12/2019 8 weeks On-going
50
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-26 atKankanba, Dodorin Tudu, Hardo
Magaji, Mataran, Dalarin Kwalta, Bultuwa Rigar
Gabas, Dodorin Rigar Mal Yakubu, Bultuwa Rigar
Kauga, Ung. Jibrin Masallacin Mal. Kawu and Rigar
Dado Gajere In Kaugama Contituency. AMM Manzo Nig Ltd Kaugama 7,377,510.00 7,377,510.00 - 11/12/2019 8 weeks On-going
51
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 46 at
Garin Urema in Hadejia Constituency A+Tech Integrated Nig. Ltd Hadejia 6,021,855.00 6,021,855.00 11/12/2019 8 weeks On-going
52
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 45 at
Gawon Dogari in Hadejia Constituency Amia Integrated Service Nig Ltd Hadejia 6,022,485.00 6,022,485.00 11/12/2019 8 weeks On-going
53
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 39
atSabon Gari in Miga Constituency Amia Integrated Service Nig Ltd Miga 6,022,485.00 6,022,485.00 11/12/2019 8 weeks On-going
54
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 40 at
Gidan Barwa in Miga Constituency A. Barde Global Concept Ltd Miga 6,023,010.00 6,023,010.00 11/12/2019 8 weeks On-going
55
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 4 at Juba
Gandu in Auyo Constituency Alh. Umaru Baban Doki Nig Ltd Auyo 6,004,715.00 6,004,715.00 11/12/2019 8 weeks On-going
BAL. C/F 1,192,916,569.46 1,192,916,569.46
2g
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,192,916,569.46 1,192,916,569.46
56
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 39 at
Gabari in Malam Madori Constituency Prestige Integ Serv. Nig Ltd M/Madori 6,022,695.00 6,022,695.00 11/12/2019 8 weeks On-going
57
Constr of Water Collection Point 2019 First
Quarter Constituency Project (Lot-..) at Yofai,
Tuyau, Gidan Kara, Dagasa, Jiyau, Fulani, Jiyau
Babba, Tagwai, Kun Kurawa, Danbaje, Auramo
Gabas Zangon Sallau, Dan Tsiru, Tsurutawa,
Auramo Tudu, Gidan Sani, Zabara, Durno, Kuna,
Dara Zai and Bangon Jani in Ringim Constituency. Prestige Integ Serv. Nig Ltd Ringim 25,206,980.00 25,206,980.00 11/12/2019 8 weeks On-going
58
Constr of Solar Powered water Supply schemes
Contituency project ( 2019 Phase 1) Lot- 3 at
Sabuwar Auyo in Auyo Constituency A.A Aljazeera Agro Processing Nig Ltd Auyo 6,010,515.00 6,010,515.00 23/12/2019 8 weeks On-going
59
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-28 at Tashar Yellow, Fulani Cakindi,
Turkushawa Gari, Gidan Amadu Inge, Fulanin
Kaina, G. Idi Shiba, Fulanin Hammado, Gidan
Dibbo in Sule Tankarkar Contituency. A.A Aljazeera Agro Processing Nig LtdS/Tankarkar 4,426,695.00 4,426,695.00 11/12/2019 8 weeks On-going
60
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-29 at Gangawa, Sabara, Ruwan
Dawa, Kulleran, Gangawa Fulani, Fanisau, Tazara
Sabon Gida, Tula, Majiga Harbo, Dina, Kamai
Gitsiri, Dogawa, Gabashi, Bayan Kotun cikin Gari,
Gundin Sabon Gida and Yammawa in Jahun
Contituency. Sasco Multi Serv Nig Ltd Jahun 11,791,752.00 11,791,752.00 11/12/2019 14 weeks On-going
61
Constr of Water Collection Point 2019 First
Quarter Constituency Project Lot- 19 at Kofar
Kudu Basirka, kofar Yamma Basirka Dal and Kofar
Tela Basirka in Fagam Constituency, Gwaram LGA Jignaj Global Contr Ltd Gwaram 4,876,422.00 4,876,422.00 11/12/2019 8 weeks On-going
62
Renov of 2no. Solar Powered water Supply
schemes Contituency project ( 2019 Phase 1) Lot-
24 at Gidan Kudege and Kurneji in Gwiwa
Constituency Jignaj Global Contr Ltd Gwiwa 3,227,700.00 3,227,700.00 11/12/2019 8 weeks On-going
63
Constr of Water Collection Point 2019 First
aquarter Constituency Project Lot- 23 at Kauyen
Zarga and Rigarsu Iro Akwai Allah In Taura
Constituency Nushe Bus, Resources Nig Ltd Taura 2,519,647.20 2,519,647.20 11/12/2019 8 weeks On-going
BAL. C/F 1,256,998,975.66 1,256,998,975.66
2h
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,256,998,975.66 1,256,998,975.66
64
Constr of Gwaram Tsohuwa and Gwaram Sabuwa
Towns Water Supply Scheme (Additionsl Works) Nushe Bus, Resources Nig Ltd Gwaram 29,520,524.45 29,520,524.45 11/12/2019 12 weeks On-going
65
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-12 at Sabuwar Jawo (sabaru ward),
fulanin Ballami (Dandi ward), K/mal. Ali
Headmaster (Gada ward), K/Alto Makeri (Gada
ward) and Makabarat Gabas ( Gada ward) in
Kazaure Contituency. Yanduna Venture Nig Ltd Kazaure 3,686,287.50 3,686,287.50 11/12/2019 8 weeks On-going
66
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-8 at
Tsohuwar Fitare in Kazaure Constituency Yanduna Venture Nig Ltd Kazaure 6,023,115.00 6,023,115.00 11/12/2019 8 weeks On-going
67
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-7 at
Wawan Rafi in Kazaure Constituency Yanduna Venture Nig Ltd Kazaure 6,023,115.00 6,023,115.00 11/12/2019 8 weeks On-going
68
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-14 at Tuda, Zakirai, K/gidan Mal Mai
unguwa, Gidan Dachi, Majiyawa, Gangare, Jigawar
Kaba, Mazazzaga, Yammachi, Fake cikin Gari,
Kabobi, Haddori, Jama'ar isah Yaldewa/Gumai,
Malamawa, Zakoro, Tasha, Jama;ar Dawa Fulani,
Unguwar Abdullahi Mati, Jigawar Tsaba and
Makarantar Andaza in Kiyawa Contituency. Tosarawa Global Nig Ltd 14,739,900.00 14,739,900.00 11/12/2019 12 weeks On-going
69
Constr of Water Collection Point 2019 First
Quarter Constituency Project (Lot-21) at Fake Cikin
Gari, Kalali, Katuka Cikin Gari, Garko Cikin Gari,
Shuwarin Cikin Gari, Turho, Tsurma cikin Gari,
Kadara Dankargo and Dangoli in Kiyawa
Constituency. Tosarawa Global Nig Ltd Kiyawa 12,603,490.00 12,603,490.00 11/12/2019 8 weeks On-going
70
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-2 at Kafeje
in Auyo Constituency AMM Manzo Nig Ltd Auyo 6,004,215.00 6,004,215.00 11/12/2019 8 weeks On-going
71
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-19 at Ruwa
yakaika in Gwiwa Constituency Jignaj Global Contr Ltd Gwiwa 6,023,220.00 6,023,220.00 11/12/2019 8 weeks On-going
BAL. C/F 1,341,622,842.61 1,341,622,842.61
2i
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,341,622,842.61 1,341,622,842.61
72
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-20 at yola
Kauye in Gwiwa Constituency Jignaj Global Contr Ltd Gwiwa 6,023,220.00 6,023,220.00 11/12/2019 8 weeks On-going
73
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-17 at yankwashi fulani, rauda gabas
and dumbule in yankwashi constituency. Granitoids Engr Services YanKwashi 2,213,032.00 2,213,032.00 11/12/2019 8 weeks On-going
74
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-34 at
addani in yankwashi Constituency Granitoids Engr Services YanKwashi 6,022,590.00 6,022,590.00 11/12/2019 8 weeks On-going
75
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-33 at
karkarna in yankwashi Constituency Granitoids Engr Services YanKwashi 6,022,590.00 6,022,590.00 11/12/2019 8 weeks On-going
76
Constr. of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-35 at
manomi in Malammadori Constituency Step by Step Int. Ser. Ltd M/madori 6,022,905.00 6,022,905.00 23/12/2019 8 weeks On-going
77
Constr of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-37 at
Surakin in Malammadori Constituency Step by Step Int. Ser. Ltd M/Madori 6,022,905.00 6,022,905.00 23/12/2019 8 weeks On-going
78
Constr. of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-9 at munar
yan biyu in Kanya Constituency, Babura LGA. Deetech Nig. Ltd Babura 6,010,935.00 6,010,935.00 23/12/2019 8 weeks On-going
79
Constr. of Solar Powered Water Supply Scheme
Constituecy project (2019 Phase 1) Lot-30
atkukule in Gagarawa Constituency Farham Synergy Ltd Gagarawa 6,022,800.00 6,022,800.00 23/12/2019 8 weeks On-going
80
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-10 at K/hausa gen. Hospital, bayan
reformatory school, alakalawa A, alakalawa B,
Makarantar allo kudu K/hausa, makarantar
D/jalla, Makarantar M. sa'adu, makarantar
turkawa, makarantar asharan chiroma, filin idi
K/hausa, makarantar su shamsu, dawasa, yan
darman shukura, fulanin toyara, kashe badi,
chiroma kwakwata, kutungun, aguran kwari,
usman kukoki, tagadawai, abewa, kazuba, karfa
kama, rigar kanawa, kazalewa UNG, sule M. tubka,
kununu, lafiya, katanga, rigar D/iya, kijinawa M.
sa'adu, marwa abdullawa, zilawa abdullawa,
aragada abdullawa, kanzan fulani (mai jama'a
jingi), kargumaka (jema haruna), karori, fulanin
baushe, mamajo, fulanin rumfa and baushe gari in
K/Hausa constituency. Mugin Inv. Nig. Ltd K/Hausa 29,509,200.00 29,509,200.00 11/12/2019 16 Weeks On-going
BAL. C/F 1,415,493,019.61 1,415,493,019.61
2j
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,415,493,019.61 1,415,493,019.61
81
Constr. of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-31
Mutumbi in Gagarawa Constituency Farham Synergy Ltd Gagarawa 6,022,800.00 6,022,800.00 23/12/2019 8 weeks On-going
82
Consrt of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-10
at Kanya cikin gari in Kanya Constituency, Babura
LGA. Deetech Nig. Ltd Babura 6,010,935.00 6,010,935.00 23/12/2019 8 weeks On-going
83
Drilling of borehole and construction of overhead
tank at fire service directorate headquaters in
Dutse (2019 capital project) Al-juraj synergy concept Ltd Dutse 6,734,650.13 6,734,650.13 18/12/2019 8 weeks On-going
84
Rehabilitation of 3no. Water supply scheme at
danzomo, maitsamiya, and dankumbo in sule
tankarkar (gumel zone 2019) Lot-2 capital projects LIMIS Brothers & Co S/Tankarkar 4,628,531.25 4,628,531.25 19/12/2019 4 weeks On-going
85
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-27 at jalomin kudu, malari, zaburan,
Ung/tsamiya, kundu, marke ung gabas, Dunbari,
chuguliski, rigar ya'u karami, dolon malam and
arbus ung. Mamman in kaugama constituency Mufabamex Concept Ltd Kaugama 7,376,800.00 7,376,800.00 11/12/2019 8 Weeks On-going
86
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-30 at koluma, kodau, kata kata,
kayoyi, turakan fulani, gidan jauro, jalingo S/sara,
Baba ari, tsangayar gabas, malumawa, karalbali
iguda, gobararin fulani, fulanin kira karama, rugar
babayo, gamayin yamma, kayoyi jabo, tafa, jabo
gabas, makerawa H/ali and rugar amadu babai in
bulangu costituency yusmatech inv. Nig. Ltd K/Hausa 14,754,800.00 14,754,800.00 11/12/2019 14 Weeks On-going
87
Construction of pipeline distribution network
(28.6km) in Kazaure Town Lot-1 CGC Nigeria Ltd Kazaure 529,952,482.00 529,952,482.00 23/12/2019 24 weeks On-going
88
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-97
at Basirka JIBWIS Jumu'at Mosque in fagam
Constituency Lines dimensions Nig Ltd Gwaram 3,640,350.00 3,640,350.00 17/12/2019 8 weeks On-going
89
Consr rof 1NO. Solar Powered Water Supply
Scheme Lot-7 at Daki daka in Garki LGA (Ringim
zone 2019)-capital project LIMIS Brothers & Co Ringim 6,019,125.00 6,019,125.00 19/12/2019 8 weeks On-going
BAL. C/F 2,000,633,492.99 2,000,633,492.99
2k
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 2,000,633,492.99 2,000,633,492.99
90
Constr of 1NO. Solar Powered Water Supply
Scheme Lot-8 at Kunyafa in Babura LGA (Ringim
zone 2019)-capital projects LIMIS Brothers & Co Ringim 6,019,125.00 6,019,125.00 19/12/2019 8 weeks On-going
91
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-1
at Kafardu in auyo Constituency Faahm Integrated Ltd Auyo 6,018,915.00 6,018,915.00 23/12/2019 8 weeks On-going
92
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-5 at Maibarewa, Sabalari, K/Fulani
and Kadusawa in Dutse constituency Farham synergy con. Ltd Dutse 2,947,896.00 2,947,896.00 11/12/2019 8 weeks On-going
93
Construction of water collection points 2019 first
querter constituency projects Lot-18 at kadiran,
fagi, karanga and karde in birniwa constituency Dabino integ serv Ltd Birniwa 5,050,128.00 5,050,128.00 14/12/2019 12 weeks On-going
94
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-44
at alkalawa in K/hausa Constituency Hambiscons Nig Ltd K/hausa 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going
95
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-43
at Kore in K/hausa Constituency Hambiscons Nig Ltd K/Hausa 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going
96
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-3 at kazura, rugar taho, fulanin
karanga, fulanin karanga gabas, fulanin fagi, rugar
saga, fulanin diginsa, Gidan Mal Dahiru, Birniwa
U/yamma, rugar idi kulla, rugar haberi, mara,
diginsa, fulanin batu, Umaru mai goro, fulanin mai
zariya, korewa, fulanin kachallari, dargazawa,
fulanin kishinde, gidan amadu, fulanin kazadama
and inkibulawa gabas in birniwa constituency Dabino integ serv Ltd Kaugama 15,492,109.50 15,492,109.50 14/12/2019 12 weeks On-going
97
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-38
at gari uku in malam madori Constituency Hambiscons Nig Ltd M/madori 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going
98
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-18
at garin tudu in maigatari Constituency Hambiscons Nig Ltd Maigatari 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going
99
Constr of 1NO. Solar Powered Water Supply
Scheme Constituecy project (2019 Phase 1) Lot-17
at kwaduge in maigatari Constituency Hambiscons Nig Ltd Maigatari 6,016,920.00 6,016,920.00 23/12/2019 8 weeks On-going
100
Rehabilitation of 18No. Water supply Schemes
Across the state. LIMIS Brothers & Co Across the state 9,748,615.80 9,748,615.80 24/12/2191 8 weeks On-going
BAL. C/F 2,075,994,882.29 2,075,994,882.29
2l
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 2,075,994,882.29 2,075,994,882.29
101
Constr of Soler Power supply Scheme Constituecy
project (2019 Phase I) Lot-32 at Ganbabituwa in
Kirikasamma Constituency. Dabino integ serv Ltd K/Kasamma 6,017,235.00 6,017,235.00 11/12/2019 8 weeks On-going
102
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-13 at Sawon Yamma, Gishingawa
2no., Rigar kaiwari, Iyo, Tage, Garin Wakili
Gilakochini, Barmaguwa 2no. Fandun Fulani, Gayin
Gane, Lofanga, Daladige, Babba Kamaji and
Marawaji in Kirikasamma Constituency Dabino Integ Serv. Ltd K/Kasamma 11,792,080.00 11,792,080.00 11/12/2019 12 weeks On-going
103
Construction of solar power water supply scheme
constituncy project (2019 phase I) Lot-32 at
Ganbabituwa in kirikasamma constituency. Dabino Integ Serv. Ltd K/Kasamma 6,017,235.00 6,017,235.00 11/12/2019 8 weeks On-going
104
Construction of hand pump boreholes water
supply schemes constituency projects (2019 first
quarter) Lot-15 at Sabon Sara, Jigalari, Lumu and
Gidan Maza in Miga constituency A. Barde Global Concopt Ltd Miga 2,948,820.00 2,948,820.00 11/12/2019 8 weeks On-going
105
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-2 at Kaute , Waje, Gurfai, Gangara,
Kurta Fulani G. M/Jadi and Indurkuba Fulani Arewa
in Babura Constituency Mufabamex Concept Ltd Babura 3,687,075.00 3,687,075.00 11/12/2019 12 weeks On-going
106
Constr.of Solar Powered Water Supply Scheme
Constituency Project (2019 phase 1) Lot-29 at
Wadda in Gagarawa Constituency Farham Synergy con. Ltd Gagarawa 6,022,800.00 6,022,800.00 11/12/2019 8 weeks On-going
107
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-6 at Kwalam Fulani, Maidu Tsokai,
Makwai Fulani, Gidan Haruna Dan Daga, Sarkin
Dare Kofar Shafi'I, Sarkin Dare Fulani, M. Na'annabi
Fulani, Garin Dutse Fulani Tale, Wadi Fulani and
Gidan Alasan Nadidi in Gagarawa Constituency JAG&H integrated services ltd Gagarawa 7,379,940.00 7,379,940.00 11/12/2019 8 weeks On-going
108
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE 1) LOT-15 At
Dawar Gada in Maigatari Constituency A.S.Maifata Gen. EntP. Ltd Maigatari 6,015,765.00 6,015,765.00 11/12/2019 8 weeks On-going
109
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE 1) LOT-14 At
Zuba Barkono in Guri Constituency A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going
110
Constr.of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE 1) LOT-12 At
Madamuwa in Guri Constituency A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going
BAL. C/F 2,137,905,262.29 2,137,905,262.29
2m
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 2,137,905,262.29 2,137,905,262.29
111
Constr of Solar Powered Water Supply Scheme
Constituency Project (2019 phase 1) Lot-11 at
Unguwar Gabas in Guri Constituency. A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going
112
Constr of Solar Powered Water Supply Scheme
Constituency Project (2019 phase 1) Lot-5
atGeneral Hospital in Birniwa Constituency. A.S.Maifata Gen. EntP. Ltd Birniwa 6,015,765.00 6,015,765.00 11/12/2019 8 weeks On-going
113
Constr of Solar Powered Water Supply Scheme
Constituency Project (2019 phase 1) Lot-6 at
Kazura in Birniwa Constituency. A.S.Maifata Gen. EntP. Ltd Guri 6,015,765.00 6,015,765.00 11/12/2019 8 weeks On-going
114
Constr of Solar Powered Water Supply Scheme
Constituency Project (2019 phase 1) Lot-13 at
Bodala in Guri Constituency. A.Y.H Invest. Co. Nig. LTD. Guri 6,014,715.00 6,014,715.00 11/12/2019 8 weeks On-going
115
Conversion of Motorized Water Supply Scheme to
Solar Powered and Rehabilitation of Existing Solar
Schemes at College of Education Gumel SIMS Global Resources Gumel 29,243,441.00 29,243,441.00 6/12/2019 8 weeks On-going
116
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE 1) LOT-47 At
maruta in Gwaram Constituency farham synergy con. Ltd Gwaram 6,022,800.00 6,022,801.00 11/12/2019 8 Weeks On-going
117
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE 1) LOT-25 At
Fagoji in Dutse Constituency JAG & H Interg. Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going
118
Constr. Of watar collection point 2019 first quarter
constituency project Lot 20 at zazzana, mida, and
lafiya in gwaram constutuency farham synergy con. Ltd Gwaram 3,758,997.00 3,758,997.00 11/12/2019 8 weeks On-going
119
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE I) LOT-26 At
Kulasa in Dutse Constituency JAG & H Interg. Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going
120
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE I) LOT-27 At
Kwaimawa in Dutse Constituency JAG & H Intergreted Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going
121
Constr. of Solar Powered Water Supply Scheme
Constituency Project (2019 PHASE I) LOT-28 At
Tabobo in Dutse Constituency JAG & H Intergreted Service Dutse 6,021,015.00 6,021,015.00 11/12/2019 8 Weeks On-going
122
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-29 at gangawa, sabara, ruwan dawa,
kulleran, ganwa fulani, fanisau, tazara sabon gida,
tula, majiga, harbo, dina, kamai gitsira, dogawa
gabashi, bayan kotun cikin gari, gundin sabon gida
and yamma in Jahun Constituency Sasco Multi Serv Nig Ltd Jahun 11,791,752.00 11,791,752.00 11/12/2019 14 Weeks On-going
BAL. C/F 2,236,867,272.29 2,236,867,273.29
2n
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 2,236,867,272.29 2,236,867,273.29
123
Constr of Hand Pump Boreholes Water Supply
Schemes Constituency projects (2019 First
Quarter) Lot-12 at sabuwar jawo (sabaru ward),
fulanin ballami (dandi ward), K/Mal. Ali
headmaster (gada ward), K/alta makeri (gada
ward) and makabarta gabas (gada ward) in
kazaure Constituency Yanduna Venture Nig Ltd Kazaure 3,686,287.50 3,686,287.50 11/11/2019 8 Weeks On-going
124
Constr of 5No. Hand Pumps Boreholes Water
Supply Schemes Constituency projects (2019 First
Quarter) Lot-25 at kanya abbba, dan yayin
daurawa, kagadama, walawa and shantake in
kanya babba Constituency Deetech Nig. Ltd Babura 5,100,375.00 5,100,375.00 11/12/2019 8 weeks On-going
TOTAL 2,245,653,934.79 2,245,653,935.79
Ministry of Works
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1
Consultancy serv ices for the Constr. of Limaw a-Warw ade-Jidaw a-
Sakw ay a-Dutse road KAP Civ il Eng. Consultants Dutse 57,547,589.11 57,547,589.11 51,132,963.56 11/15/2012 16 months 94 Stalled
2 Constr. of Limaw a-Warw ade-Jidaw a-Sakw ay a-Dutse road (33.40km) Boroni Prono & Co. Ltd. Dutse 2,968,551,896.02 2,968,551,896.02 2,611,339,802.95 2/11/2012 14 months 88 Stalled
3
Commissioning as Consultant on the superv ision of the Urban Tow n
Streetlight Project at Garki, Karkarna, Bamaina and 3no. Gen. Hosp. MBS Eng. Nig. Ltd. Garki 29,431,500.00 29,431,500.00 27,371,295.00 23/4/2014 93 stalled
4 Consultancy serv ices for the constr. Of T/kance-jamus feeder road UKM Civ il Eng. Consultant Babura 21,657,808.87 21,657,808.87 21,657,808.87 2/8/2014 8 Months 60 On-going
5
Commisioning as consultant on the superv ision of the construction of 6No.
New feeder road projects across the state OPIQ Consultant Ringim 22,400,354.68 22,600,354.68 21,242,736.09 28/5/2014 8 months 95 On-going
6 Consultancy Superv ision for the Constr. of Gw iw a tow nship roads (4.0km) Sadiq Eng. Serv ices Gw iw a 34,489,165.99 34,489,165.99 31,495,251.31 12/17/2012 6 months 95 Stalled
7 Construction of Tow nship at kaugama Urban Centre (6.30KM) Rocad Contr. LTD Kaugama 940,127,208.47 940,127,208.47 263,578,988.93 13/12/2013 8 Months 28 Rev oked
8 Constr. of Tow nship Roads at Hadejia Urban Centre (12.80KM) Paache Const. Nig. LTD Hadejia 2,507,773,876.62 2,997,892,256.00 2,596,781,916.87 12/31/2013 12 months 87 On-going
9 Constr. of Tow nship Roads at Maigatari Urban Centre (6.95KM) H&M Nig. LTD Maigatari 1,037,700,121.50 1,037,700,121.50 866,698,245.00 17/12/2013 8 Months 83 On-going
10 Constr. of Tow nship Roads at Guri Urban Centre (6.15KM) SKY Tech.& Contr.LTD Guri 1,362,774,826.33 1,362,774,826.33 1,266,547,203.54 17/12/2013 8 Months 93 On-going
11
Commissioning as Consultant on the Superv ision of the Constr. of Maigatari
Tow nship Road (6.95KM) Sadiq Eng Ser. LTD Maigatari 64,472,315.43 64,472,315.43 58,918,158.83 19/12/2013 8 Months 90 On-going
12
Commissioning as Consultant on the Superv ision of the Constr. of M/Madori
tow nship Road (6.40KM) U.K.M Civ il Eng. LTD M/madori 59,544,758.06 59,544,758.06 58,052,780.58 12/31/2013 8 Months 100 On-going
13
Commissioning as Consultant on the Constr. Of Roni tow nship roads
(5.00KM) EMACS Eng. Consultants Roni 61,195,703.35 61,195,703.35 57,626,153.48 12/31/2013 8 Months 94 On-going
14 Commissioning as Consultant for the Constr. of Hadejia Tow nship roads Global Ecological Hadejia 101,482,637.11 101,482,637.11 89,435,668.10 12/31/2013 16 months 88 On-going
15 Commissioning as Consultant for the Constr. of Kaugama Tow nship roads Interactiv e Consultants Kaugama 66,347,751.06 66,347,751.06 38,946,478.35 12/31/2013 12 months 58 Revoked
16 Commissioning as Consultant for the Constr. of Guri Tow nship roads Madapad Eng. Ltd. Guri 66,500,604.95 66,500,604.95 58,742,130.61 12/3/2013 12 months 88 On-going
17
Fabrication and Erection of roads directional signs (Gantry ) and street
naming w ithin DutseMunicipality Durability Eng. Serv ices Dutse 90,081,840.00 90,081,840.00 77,618,236.51 18/3/2014 12 w eeks 87 Stalled
18 Construction of Gw iw a tow nship roads (4.0km) H & M Nig. Ltd. Gw iw a 509,414,865.75 509,414,865.75 412,393,839.50 29/11/2012 6 months 88 Stalled
19 Re-Constr. of Roni Tow nship road (5.00km) Alren Constr. Co. Ltd. Roni 645,608,565.02 645,608,565.02 645,579,156.97 4/4/2016 8 months 100 On-going
Balance C/F 10,647,103,388.32 11,137,421,767.70
3a
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
Balance B/F 10,647,103,388.32 11,137,421,767.70
20 Re-Constr. of Kazaure Tow nship road (14.643km) Soject Nig. Ltd. Kazaure 2,090,736,236.34 2,090,736,236.34 2,090,610,656.20 4/4/2016 8 months 100 On-going
21
Constr. of Jigaw ar Dan Ali-Maitsamiy a-S/tankarkar-Dangw anki-Dankumbo
Feeder road w ith Sur from Dankumbo to Matsatsagi (45km) H & M Nig. Ltd. S/tankarkar 639,156,955.50 1,003,554,571.95 943,572,613.20 28/12/2016 9 months 95 On-going
22
Constr. of Majingini-Maimazari-Dantuw o -Hannun Giw a-Dankumbo feeder
road (11.5km) H & M Nig. Ltd. S/tankarkar 188,786,408.33 188,786,408.33 174,762,675.02 28/12/2016 6 months 75 On-going
23
Consultant for valuation of the State Govt.'s Investment in Electricity
Distribution network (PHCN) Emirate Consulting Ltd. State 125,000,000.00 125,000,000.00 62,500,000.00 19/6/2013 12 months 50 Stalled
24 Electrification of Shakoto-Bulangu (REB) Aima Strong Store Ltd. K/hausa 36,199,059.19 36,199,059.19 29,923,001.66 2/19/2014 6 months 89 On-going
25
Supervision of the construction of JigawarDan-ali-Maitsamiya-
Suletankarkar-Dangwanki-Dankumbo to Matsatsagi (45KM) and
construction of Kudai-Ruru-Dantawuya-Sakwaya Feeder Road
(15KM) UKM Civil Eng.
S/tankarkar +
Dutse 14,172,571.35 14,172,571.35 10,066,755.99 11/4/2017 12 months 71 On-going
26 Constr of Darai-Gilima road (9.5km) lot-2 Alren Const. Co. Ltd. Jahun/Taura 2,492,310,165.97 2,492,310,165.97 2,114,436,744.00 27/4/2018 8 months 84 On-going
27
Constr of Gambara-Waza-Baranda with Spur to yalwa (16.8km) lot-
3 Alren Const. Co. Ltd. B/kudu 3,194,083,855.93 3,194,083,855.93 3,119,614,701.90 27/4/2018 10 months 96 On-going
28 Constr of Kaugama township road (6.3km) lot-7 Afdin Constr Co. Ltd. Kaugama 1,333,357,771.41 1,333,357,771.41 651,161,382.57 30/4/2018 12 months 49 On-going
29 Constr of Babura Township road (10.28km) lot-8 Triacta Nig. Ltd. Babura 2,624,756,218.01 3,135,597,825.49 2,907,493,341.18 2/5/2018 10 months 93 On-going
30
Commissioning as Consultant for the Supervision of the Constr. of
Road Network at College of Education, Gumel (3.3km) EMACS Eng. Consultants Gumel 11,798,466.27 11,798,466.27 9,038,773.02 7/6/2018 6 months 72 On-going
31
Commissioning as Consultant for the Supervision of the Constr. of
Dutse-Madobi-Katanga-Dangoli with a SPUR from Madobi to
Baranda (35.7km) CURVES and Straight Dutse 81,260,950.27 81,260,950.27 74,966,379.21 7/6/2018 12months 91 On-going
32
Commissioning as Consultant for the Supervision of the Constr. Of
Bariki-Munzarau-Tawakkalta-Turabu-Gidan Mutum Daya road
(16.8km) Himma Technical Services Hadejia 51,099,226.92 51,099,226.92 43,434,342.88 7/6/2018 12 months 85 On-going
33
Commissioning as Consultant for the Supervision of the Constr of
Darai-Gilima road (9.5km) APEX Design & Associates Jahun + Taura 43,615,427.90 43,615,427.90 37,315,427.89 8/6/2018 8 months 85 On-going
34
Commission as Consultant for the Supervision of the Construction
of Gambara-Waza-Baranda with a Spur to Yalwa Wuro Associates Eng. Dutse 55,896,467.48 55,896,467.48 49,188,896.92 7/6/2018 10 months 88 On-going
35
Commission as Consultant for the Supervision of the Construction
of Access road from Harbo Sabuwa to Harbon Tsohuwa (1.52km) Powermatrix Eng Jahun 4,218,516.02 4,218,516.02 3,796,664.41 13/6/2018 4 months 90 On-going
36
Rehabilitation of the electrification project at Marke- yalo ITC line
in Kaugama LGA AG Global serv. Nig ltd Kaugama 40,151,533.53 40,151,533.53 36,276,617.55 6/12/2018 12 weeks 90 On-going
37
Constr of Balago-Dubeni-Kodowawa-Dumadumin Kyaure-Auno
road (41.2km) Lot-3 Gerawa Global Engr. Ltd. Kiyawa 5,321,500,681.77 5,321,500,681.77 4,549,464,150.00 21/12/2018 24 months 85 On-going
38
Construction of 744 - Sabuwar Takur - Yalwawa Road (8.10KM) Lot
7. Retercha Company Ltd Dutse 1,577,371,259.00 1,577,371,259.00 1,154,812,255.80 21/12/2018 10 months 73 On-going
Balance C/F 30,572,575,159.51 31,938,132,762.82
3b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOC A T ION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 30,572,575,159.51 31,938,132,762.82
39 Construction of Taura - Garki Road (26.68KM) Lot 2. Alren Constr. Comp. Ltd. Taura + Garki 2,925,979,072.38 2,925,979,072.38 2,650,909,720.05 21/12/2018 16 months 91 On-going
40
Construction of Kwanar Medi - Danzomo - Garki Road (29.51KM)
Lot 1. Triacta Nig. Ltd. Gagarawa + Garki 3,583,700,255.94 3,583,700,255.94 1,939,080,265.43 27/12/2018 20 months 54 On-going
41
Construction of Birnin kudu - Zazika - Kwangara Nafadan -
Kadangare - Shirin - Malamawa - Kwatai - Nafara Feeder Road
(33.0KM) Lot 16. Ganan Constr. Co. B/Kudu 1,109,438,407.32 1,109,438,407.32 659,736,236.25 24/12/2018 10 months 60 On-going
42 Construction of Zandam Nagogo Township Road (2.38KM) Lot 12. Ganan Constr. Co. Gwaram 435,973,460.83 435,973,460.83 190,412,659.50 24/12/2018 6 months 44 On-going
43
Construction of Sada - Kanawa - Dankari - Nasarawa - Kudu Feeder
Road (11.2KM) Lot 14. SDY Engr. & Const.. Co. Ltd. Yankwashi 393,697,127.25 393,697,127.25 373,748,968.15 24/12/2018 6 months 94 On-going
44
Construction of Chai-chai Tsohuwa Township Road (1.23KM) Lot
11. Belgrade Engr. & Const. Ltd. Dutse 225,712,752.30 225,712,752.30 44,221,066.37 24/12/2018 6 months 20 On-going
45 Construction of Jigawar Dan Ali Township Road (2.10KM) Lot 9. Mother Cat Nig. Ltd. Babura 427,673,958.29 427,673,958.29 415,503,284.62 24/12/2018 6 months 97 On-going
46 Construction of Miga Township Road (3.1KM) Lot 5. CGC Nig. Ltd. Miga 748,110,079.06 748,110,079.06 59,852,246.48 24/12/2018 8 months 8 On-going
47 Construction of Kiyawa Township Road (Phase II) (4.0KM) Lot 8. CGC Nig. Ltd. Kiyawa 781,689,780.01 781,689,780.01 446,685,490.77 24/12/2018 7 months 57 On-going
48 Electrification Project at Askandu in Kaugama L.G.A. Nabakwai Gen. Enterp. Kaugama 20,298,933.03 20,298,933.03 18,533,808.41 24/12/2018 12 weeks 90 On-going
49
Consultancy services for the Dualization of Fanisau road to Unity
Pentagon round about in Dutse (11.4km) A.G. & Partners Ltd. Dutse 83,028,671.25 83,028,671.25 44,446,452.75 14/7/2017 50 On-going
50 Electrification Project at Alaye in Kirikasamma L.G.A. Dabino Integ. Serv. Ltd. K/kasamma 24,380,538.09 24,380,538.09 17,785,248.08 24/12/2018 12 weeks 87 On-going
51Co mmis s io ning as Co ns ultant fo r the Supervis io n o f the Co ns tr o f
Kaugama To wns hip ro ads (6.3km) SIIS Eng. Co ns ultants Ltd. Kaugama 23,333,761.00 23,333,761.00 10,966,867.67 1/11/2018 12 m,o nths 47 On-going
52Commissioning as consultant for the Supervision of the Construction of
Chai Chai Tsohuwa township Roads UGS Consultants Dutse 3,949,973.17 3,949,973.17 1,224,290.42 20/3/2019 6 weeks 30 On-going
53Commissioning as consultant for the Supervision of the Construction of
Kiyawa Township Roads Phase II (4km) Sadiq Engineering Kiyawa 13,679,571.15 13,679,571.15 9,492,515.76 20/3/2019 6 weeks 69 On-going
54Commissioning as Consultant for the Supervision of the construction of
Kanya Babba Township Roads (2.8km) Curves & Straight design Babura 6,056,229.07 6,056,229.07 4,236,211.35 20/3/2019 6 weeks 70 On-going
55
Commissioning as Consultant for the Supervision of the Construction of
Hammado-Dafarantama-M ele-Baikarya-Garin Baki-Kokinami-Liman M ado
feeder Roads (32.76km) Hag Engineering Gumel 15,959,738.87 15,959,738.87 6,383,855.55 20/3/2019 6 weeks 38 On-going
56Commissioning as consultant for the supervision of the Construction of
Zandam Nagogo township Roads (2.38km) Land Base Engineering Gwaram 7,629,535.56 7,629,535.56 2,288,860.67 20/3/2019 6 weeks 29 On-going
57Commissioning as Consultant for the supervision of the Construction of
Kaugama - M alam M adori Feeder Road (19.31km) SIIS Engineering Consult M /M adori 9,112,024.27 9,112,024.27 20/3/2019 6 weeks On-going
Balance C/F 41,411,979,028.35 42,777,536,631.66
3c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOC A T ION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 41,411,979,028.35 42,777,536,631.66
58
Commissioning as consultant for the Supervision of the Construction of
Guduncin-Aguyaka Road (4.30km) Curves & Straight design Hadejia 17,024,414.69 17,024,414.69 3,404,881.97 20/3/2019 6 months 19 On-going
59
Commissioning as Consultant for the Supervision of the Construction of
Kwanar M edi-Danzomo-Garki Road (29.51km) Curves & Straight design Garki 62,714,754.77 62,714,754.77 12,542,910.95 20/3/2019 20 months 19 On-going
60 Supervis io n o f Balago -Auno ro ads Apex Des ign Kiyawa + K/hausa 93,126,261.93 93,126,261.93 46,266,287.51 20/3/2019 24 mo nths 50 On-going
61 2019 Rural Electrification Project at Kulawa in Ringim LGA (Lot-9) Ngloma Constr Nig Ltd Ringim 40,761,674.94 40,761,674.94 2/10/2019 14 weeks On-going
62
2019 Rural Electrification Project at Kaigamari M/Awaso in
K/Hausa LGA (Lot-7) Babandoki Gen Entp. K/Hausa 56,156,069.34 56,156,069.34 2/10/2019 14 weeks On-going
63 2019 Rural Electrification Project atTurbus in Maigatari LGA (Lot-8) Babandoki Gen Entp. Maigatari 51,909,858.00 51,909,858.00 2/10/2019 14 weeks On-going
64 2019 Rural Electrification Project at Daurawa in Taura LGA (Lot-11) Ngloma Constr Nig Ltd Taura 39,499,187.75 39,499,187.75 2/10/2019 14 weeks On-going
65 2019 Rural Electrification Project at Batali in Babura LGA (Lot-14) Ngloma Constr Nig Ltd Babura 87,414,189.61 87,414,189.61 2/10/2019 14 weeks On-going
66 2019 Rural Electrification Project at Duwigi in Gwiwa LGA (Lot-13) Babandoki Gen Entp. Gwiwa 45,418,689.70 45,418,689.70 2/10/2019 14 weeks On-going
67
2019 Rural Electrification Project at Ringim in Yankwashi LGA (Lot-
12) Pullad Global Consultant Yankwashi 59,238,524.45 59,238,524.45 2/10/2019 14 weeks On-going
68 2019 Rural Electrification Project at Batu in Birniwa LGA (Lot-5) Masaka Global Concepts Birniwa 42,505,703.10 42,505,703.10 37,994,663.70 2/10/2019 14 weeks 89 On-going
69 2019 Rural Electrification Project at Walawa in Hadejia LGA (Lot-4) Ngloma Constr Nig Ltd Hadejia 52,780,791.53 52,780,791.53 2/10/2019 14 weeks On-going
70 2019 Rural Electrification Project at Kadira in Guri LGA (Lot-6) Xtrax 99 integrated Services Guri 101,346,796.79 101,346,796.79 2/10/2019 14 weeks On-going
71 Electrification project (Lot-17) at Gangara Qtr. In Gumel LGA. Ibrahim Yusuf Integ. Gumel 23,258,058.11 23,258,058.11 2/10/2019 14 weeks On-going
72 Electrification project (Lot-15) at Masko villege in Babura LGA. Nuhabib Nig. Ltd. Babura 32,792,767.93 32,792,767.93 29,136,338.54 2/10/2019 14 weeks 88 On-going
Balance C/F 42,217,926,770.99 43,583,484,374.30
3d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOC A T ION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 42,217,926,770.99 43,583,484,374.30
73 Electrification project (Lot-2) at Gangawa village in Jahun LGA. Yanduna Ventures Jahun 90,247,560.30 90,247,560.30 2/10/2019 14 weeks On-going
74
Constr of hadejia township roads (485m) road Network) Additional
works) at Azare road-Adua Mosque-New Motor Park (Road II) PAAche Constr Ltd. Hadejia 312,270,011.92 312,270,011.92 2/10/2019 16 weeks On-going
75 Constr of Babura township roads (10.28km) (Additional works) Triacta Nig Ltd. Babura 510,841,607.48 510,841,607.48 2/10/2019 16 weeks On-going
76
Supply and Istallation of Stand Alone Solar powered streetlights at
Government Girls Arabic School Babura, Goverbment Girls Unity Sims Global Resources Gwaram 60,780,300.00 60,780,300.00 4/11/2019 8 weeks On-going
77
Constr of Jigawar Dan Ali Township Road (2.10KM) (Additional
Work) Mother Cat Nig Ltd Babura 203,412,195.00 203,412,195.00 11/12/2019 16 weeks On-going
78
Installation of 100-units of Integrated Standalone Solar Powered
Streetlight at Babaldu town, Birnin Kudu LGA. Ar-Rayyan Ventures Global Birnin Kudu 55,786,500.00 55,786,500.00 24/12/2019 4 weeks On-going
79
Mainatinance and Rehabilitation of some Failed Sections along
Kazaure - Roni Road Retercha Cmp. Nig Ltd Kazaure+Roni 98,528,040.30 98,528,040.30 12/12/2019 16 weeks On-going
80
Electrification projects at Tashena Village and Shagaryo town in
Mallam Madori LGA AHF Global Nig Ltd. M/madori 49,293,924.94 49,293,924.94 41,642,186.99 15/10/2019 16 weeks 95 On-going
81
Supply and installations of 150-units integrated standalone solar
powered streetlight at Garun gudunya and garin gambo towns in
babura and gumel LGAs SIMS Nig. Ltd Babura+Gumel 81,328,800.00 81,328,800.00 24/12/2019 12 weeks On-going
82
Supply and installation of 150-units integrated stand alone
powered streetlights at marke town in kaugama LGA Sims Global Resources Nig Ltd Kaugama 82,797,750.00 82,797,750.00 3/12/2019 12 weeks On-going
TOTAL 43,763,213,460.93 45,128,771,064.24
3e
Ministry of Education
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT COMPL. STATUS REMARKS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K DATE PERIOD IN %
1
Procurement of 2-sets of Sporting facilities at Bamaina Talented & Gifted School,
B/kudu L.G.A. BM Inv est. Nig. Ltd. B/kudu 36,030,000.00 36,030,000.00 31,987,558.79 16/8/2012 12 w eeks 85 Stalled
2 Supply of Classrooms, Staff Houses & Office Equip. to JICORAS A. Barde Global Concept. K/hausa 33,143,878.07 33,143,878.07 24,952,793.85 13/12/2012 3 w eeks 75 Stalled
3 Supply of Library books to JICORAS Al-kassam Jannah K/Hausa 30,785,750.00 30,785,750.00 28,526,075.95 2/5/2013 8 w eeks 92 Stalled
4 Constr. w orks at JICORAS (phase II) Datum Constr. Co. K/Hausa 1,677,895,165.73 1,708,557,551.33 1,608,258,817.26 30/8/13 18 w eeks 94 On-going
5
Constr. of 1No. Block of Sabbatical Lodge, 5No Principal Officers Quarters 3No
Blocks 240 Capacity Students Hostels and Construction of Road Netw ork Culv ert
and Drainages at Jigaw a State Univ ersity Kafin Hausa (Phase III) Datum Const. Nig. LTD K/Hausa 2,574,587,179.00 2,782,409,740.68 873,397,813.68 28/11/2013 6 Months 34 On-going
6 Construction of Senate Building at Jigaw a State Univ ersity , K/hausa A.G Ferrero K/Hausa 1,698,949,299.60 1,961,397,871.17 1,759,415,903.28 24/7/2014 10 months 90 On-going
7 Supply and Installation of 5HP Pumps at BEC Camp For the use of State Univ ersity Modang Inv estment Nig. Ltd Auy o 2,436,750.00 2,436,750.00 623,000.00 13/2/2014 8 w eeks 23 Stalled
8
Commissioning as Consultant for the Designing and Superv ision of (phase II) for the
constr.of Jigaw a State Univ ersity , K/Hausa Design Plus + K/Hausa 158,703,031.78 158,703,031.78 117,453,599.98 12/18/2014 18months 74 On-going
9
Procurement of 1000no. College Tablets, CAMP 1000 students for the period of (5)
w eeks E-learning Programme Activ ities Echo Infotech Solutions H/qtrs. 34,311,150.00 34,311,150.00 28,508,507.50 12/3/2015 2 months 83 Stalled
10
Constr of 1no. Block of 2no. Classroom Islamiyya school (3no.) 2nd phase
2017 constituency projects (Lot-5) at Karkarna, Sada and Yalawa in
Yankwashi Constituency. Granitoids Eng Services Yankwashi 9,820,818.00 9,820,818.00 9/5/2018 13 weeks On-going
11
Constr of 1no. Block of 2-classroom Islamiyya at Bakwarga in Buji
Constituency 2017 (phase III) Yayarin Tukur Nig Ltd. Buji 3,269,819.70 3,269,819.70 28/5/2018 8 weeks On-going
12
Constr of Block of 2no. Classroom Islamiyya and Constr of 1no. Block of 3-
classroom and 2no. Block of classroom with office (SUBEB Type) 3rd phase
2017 Constituency project (Lot-9) at K/Arewa, Izala Islamiyya and
Makarantar Malam Daura in Ringim Local Govt. Nushe Business Resources Ringim 9,819,350.10 9,819,350.10 5/7/2018 10 weeks On-going
13
Constr of Drainage at Kuburu-Mabuga (Anku) Titin Yahai Qtrs (907m)
Hadejia town, 1st Qtrs. 2018 Constituency project Tasi'u Mohammed Hadejia 28,264,601.73 28,264,601.73 17/8/2018 3 months On-going
14
Installation of TDN Line, Substation and 40KVA Gen. at GS&TC Ringim (1st
phase 2018 projects) (Lot-30) Yusma Tech Invest. Ringim 11,119,230.57 11,119,230.57 6,006,971.25 12/7/2018 6 months 55 On-going
15
Installation of TDN Line, Substation and 20KVA Gen. at GS&TC B/kudu and
Installation of TDN line at SSS K/Babba (Lot-31) Math Global Concept B/Kudu + Babura 12,717,747.66 12,717,747.66 8,916,752.51 16/7/2018 6 months 67 On-going
16
Construction of Senate Building along with the provition of parking Lots
and walk ways at Sule Lamido University, Kafin Hausa (additional Works). A.G Ferrero Building K/Hausa 262,448,571.57 262,448,571.57 23/10/2018 24 weeks On-going
17
Construction of Block of 2-Classroom Islamiyya (3NO.) Lot-19 at Jigawar
Maroka, Kiyawa K/fada and Tuje in Kiyawa Constituency Demastbo Ventures Ltd. Kiyawa 9,342,612.24 9,342,612.24 1/11/2018 10 Weeks On-going
BAL. C/F 6,593,644,955.75 7,094,578,474.60
4a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 6,593,644,955.75 7,094,578,474.60
18
Feeding of 597 Boarding School students at MBPS/JSS Kazaure & 35
students at Intel Disability Kazaure in Kazaure LGA (2019 MOEST Capital
Projects) Lot-40. Umar Aliyu & Sons Kazaure 23,888,538.40 23,888,538.40 23/12/2020 40 weeks On-going
19
Construction of Block of 2-Classroom Islamiyya (1NO.) Lot-20 at Dunnaka
in Miga Constituency. Amia Integ. Service Nig Ltd. Miga 3,115,779.08 3,115,779.08 1/11/2018 4 Weeks On-going
20
Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-2 at Rakumin
Rafa and Kasabur in Birniwa Constituency. Amm Manzo Nig. Ltd. Birniwa 6,224,550.80 6,224,550.80 1/11/2018 10 weeks On-going
21
Construction of Block of 2-Classroom Islamiyya (2NO.) Lot-2 at Rakumin
Rafa Constituency. Bulangu Drilling Services 6,968,430.00 6,968,430.00 1/11/2018 10 Weeks On-going
22
Construction of Block of 2-Classroom Islamiyya (7NO.) Lot-10 at Sabalari,
kishingawa, Limawa Gabar, Dan masara, Chamo Gari, Yalwawa and Buju in
Dutse Constituency. Al-kasam Jannah Nig. Ltd. Dutse 21,687,679.15 21,687,679.15 5/11/2018 20 Weeks On-going
23
Construction of Block of 2-Classroom Islamiyya (1NO.) 2nd Phaes 2017
Constituency Projects (Lot-16) at Government Arabic Secondry School
(G.A.S.S.) in Sule Tankarkar Constituency. Kairussabah Nig. Ltd. S/tankarkar 3,224,219.90 3,224,219.90 1/11/2018 3 Weeks On-going
24
Construction of Block of 2-Classroom Islamiyya (2Nos.) at Kankare & Raha
and (1NO.) Block of 3-Classroom Subeb Type at Tsardawa in Kanya Babba
Constituency, (Lot-1) Babura Local Government Area. DeeTech Nig Ltd. Babura 13,885,760.58 13,885,760.58 15/10/2018 10 weeks On-going
25
Construction of (1N0.) Blocks of 2-classroom Islamiyya school SUBEB
typed 2018 phase II constituency projects (Lot -7) atDanmakeri in Ringim
constituency. Mai-Mai Blocks ind. Nig. Ltd Ringim 4,940,040.00 4,940,040.00 1/11/2018 6 weeks On-going
26
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-19) at Karkarna and Ruruma in
Yankwashi Constituency. Granitoids Engr. Services Ltd Yankwashi 6,224,045.10 6,224,045.10 18/12/2018 8 weeks On-going
27
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase II Constituency Projects (Lot-2) at Majingini and Babban
Kambari in Gumel Constituency. Jag & H Intgrated Services Ltd. Gumel 6,230,703.46 6,230,703.46 3,010,358.03 5/12/2018 8 weeks 48 On-going
28
Constr of (3no.) block of 2-classroom Islamiyya School typed 2018 phase II
constituency projects (Lot-13) atHussaindeen Babangida Jahun, Atuman
Harbo Sabuwa and Ruwan Dawa in Jahun Constituency. AGA Kilawa Nig. Ltd Jahun 9,311,022.00 9,311,022.00 5,209,942.50 5/12/2018 10 weeks 55 On-going
29
Construction of (1 No.) Blocks of 3-Classroom, 1-Block of 6-Seater VIP Pit
Latrine and Hand Pump at Govt. Day Arabic Secondary School Birniwa (Lot-
1). MWT Real Estate & Gen. Mer. Birniwa 12,639,228.22 12,639,228.22 28/12/2018 3 months On-going
30
Construction of 1-Blocks of 6-Classroom (1st & 2nd Quarter 2018
UBEC/SUBEB Intervention Project) Lot-5 G/Sarki and Construction of 2-
Classrooms with Office, Staff Room, Meeting Room and Toilet at Ruhogo in
Hadejia L.G.A. Step by Step Intergrated Serv Hadejia 31,639,463.50 31,639,463.50 18/11/2018 16 weeks On-going
31
Construction of Blocks of 2-Classroom Islamiyya Typed (2No.) Lot-6 at
Tashena and Kargon Gabas in Malam madori Constituency. Express Innovation Concept M/madori 6,208,148.10 6,208,148.10 27/12/2018 6 weeks On-going
32
Construction of (1No.) Blocks of Teachers Lodge 2018 Phase III
Constituency Projects (Lot-25) at Kanya Babba in Kanya Constituency. Deetech Nig. Ltd. Gwaram 12,701,001.00 12,701,001.00 18/12/2018 12 weeks On-going
33
Construction of (2 No.) Blocks of 2-Classroom Islamiyya School Typed
2018 Phase III Constituency Projects (Lot-24) at Garun Gabas in Malam
madori Constituency. Nabakwai Gen. Enterprises M/madori 3,115,351.08 3,115,351.08 18/12/2018 8 weeks On-going
BAL. C/F 6,765,648,916.12 7,266,582,434.97
4b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 6,765,648,916.12 7,266,582,434.97
34
Constr of (3no.) blocks of 2-classroom Islamiyya school typed 2018 phase
III constituency projects (Lot-13) at Ajura, Kekau and Garki in Garki
Constituency. Mugin Investment Nig. Ltd. Garki 9,341,037.24 9,341,037.24 18/12/18 10 weeks On-going
35
Constr of (10no.) block of 2-classroom Islamiyya School typed 2018 phase
III constituency projects (Lot-3) at Gida Dubu, Kargo Yamma, Kudai
Yamma, Zobiya, Tofa, Galadimawa, Katangare, Irwa, Gandun Mazare and
Baranda in Dutse Constituency. Mugin Investment Nig. Ltd. Dutse 31,136,790.83 31,136,790.83 12,836,962.26 24/12/2018 15 weeks 39 On-going
36
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-1 at Girdo, Tasawa and
Tsamiyar Kwance in Kanya Babba Constituency Babura Local Government
Area Dee- Tech Nig Ltd Babura 9,347,337.24 9,347,337.24 27/11/2019 13 weeks On-going
37
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-7 at Jauga, Jankawa Yola,
Karwai, Wailari and Budai in Ringim Constituency Marb eng. & Multi service Nig Ltd Ringim 15,576,585.00 15,576,585.00 27/11/2019 8 weeks On-going
38
Construction of (3No.) Blocks of 2-Classroom Islamiyya School Typed 2018
Phase III Constituency Projects (Lot-10) at Dan Barage, Tela Rabiu
Residence Babura Kofar kudu and Jigawa Yamma in Babura Constituency. Mufabamex Concept Nig. Ltd. Babura 9,341,037.24 9,341,037.24 18/12/2018 10 weeks On-going
39
Procurement and Distribution of Instructional Materials Basic Levels
across the State. Ngaloma Constr. Co. Across the state 62,319,731.25 62,319,731.25 28/12/2018 12 weeks On-going
40
Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr.
Phase II 2019 constituency project) at Ung. Kalgo, Kuda Walawa and Bade
Fulani in Yankwashi Constituency. Granitoids Eng Serv. Ltd. Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 12 weeks On-going
41
Renovation of Structures at Government Science Secondary School Lautai
Gumel ( Phase II) Gerawa Gobal Engr Ltd Gumel 98,014,279.51 98,014,279.51 50,616,896.92 21/06/2019 6 month 52 On-Going
42
Feeding of 1,407 Boarding School students at GGASS Babura in Babura LGA
(2019 MOEST Capital Projects) Lot-1. JALGO Integ. Services Ltd. Babura 53,186,214.40 53,186,214.40 23/12/2019 40 weeks On-going
43
Commissioning as Consultant for the Training and Technical Support of
250No Senior Secondary School Teachers on K-Yan Machine for the
Facilitation of E-Learning at Senior Secondary Schools Across the State C-Stemp Construction Skills Across the state 36,227,761.00 36,227,761.00 32,604,984.89 24/5/2019 6 Month 90 On-going
44
Constr of 1no. Block of 3-classrooms each at GDSS Babura, GDSS
Galagamma Gumel, GDSS babura and GDSS Ringim Areawa (2019 Capital
projects) Babandoki Gen Entp. Ringim 44,808,022.00 44,808,022.00 3/10/2019 12 weeks On-going
45
Constr of 1no. Block of 3-classrooms each at GDSS Dan Masara, GDSS
Jahun, GDSS Shagari Qtrs Hadejia and GDSS M/madori (2019 Capital
projects) Math Global Invest. M/madori 44,808,022.00 44,808,022.00 3/10/2019 12 weeks On-going
46
Renovation of Staff Quarters at College of Education Gumel, Lot-7 (3rd &
4rd Quarter 2019 Capital projects) Babandoki General Entr Gumel 233,513,402.67 233,513,402.67 27/11/2019 12 weeks On-going
47
Construction of 1No Block of 2 classroom Islamiyya School each, Lot-4
(First Quarter 2019 Constituency Project) at Dodal (Nomadic and Jammaje
Gafaffa in Gwiwa Isah Halilu Nig Ltd Gwiwa 6,226,306.20 6,226,306.20 2 7 /1 1 /2 01 9 8 weeks On-going
48
Construction of classrooms Blocks at Jigawa College of Remedial and
Advance Studies(JICORAS) Babura, Lot-4 (3rd & 4rd Quarter 2019 Capital
Projects) Babandoki General Entr Babura 120,213,423.86 120,213,423.86 2 7 /1 1 /2 01 9 24 weeks On-going
BAL. C/F 7,549,048,637.68 8,049,982,156.53
4c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 7,549,048,637.68 8,049,982,156.53
49
Construction of 1No Block of 2 Classroom islamiyya School Lot-14B (First
Quarter 2019 Constituency Project) at Hassan Hadejia in Hadejia
constituency Muhal Global Concept Ltd Hadejia 9,100,200.00 9,100,200.00 2 7 /1 1 /2 01 9 9 weeks On-going
50
Renovation of 13No Students Hostels at College of education Gumel, Lot-8
(3rd &b 4rd Quarter 2019 Capital Projects) Babandoki General Entr Gumel 148,840,065.71 148,840,065.71 2 7 /1 1 /2 01 9 12 weeks On-going
51
Construction of Hostel Block at Jigawa College of remedial and Advance
Studies (JICORAS) Lot-5 (3rd & 4th Quarter 2019 Capital Projects) Ngaloma Constr Co Ltd K/Hausa 100,763,064.17 100,763,064.17 2 7 /1 1 /2 01 9 24 weeks On-going
52
Construction of 1No. 2 classroom Islamiyya School each, Lot-6 (First
Quarter 2019 Constituency Project at Abur, Margadu, Ahlal Sunnah
Islamiyya, Musari and Wareri in Guri Constituency Adam General Enter Ltd Guri 15,576,795.40 15,576,795.40 2 7 /1 1 /2 01 9 8 weeks On-going
53
Construction of 2No Block of 2 Classroom Islamiyya ( 2018 Phase II
Ongoing Constituency Projects) Lot-10 at danksoshe and Jatafinnamari in
Buji Constituency Mai-Mai Blocks Industry Ltd Buji 6,231,539.60 6,231,539.60 18/11/2019 8 weeks On-going
54
Construction of 1No Block of 2 Classroom Islamiyya School each Lot-12
(First Quarter 2019 Constituency Project at Kan Hawa Roni, Santar Tsaye
and Sabuwar Santa Tunas in Roni Constituency Yanduna Ventures Ltd Roni 9,339,248.04 9,339,248.04 27/11/2019 10 weeks On-going
55
Construction of 3no Block of 2 classroom Islamiyya ( 2018 Phase III Ongoing
Constituency Projects) Lot-12 at Garin Kwalandi and Kabara in Maigatari
Constituency NBS & Sons Constr Ltd Maigatari 15,140,562.72 15,140,562.72 18/11/2019 12 weeks On-going
56
Construction of Malam Makera Islamiyya School (Upstairs) 2018 III
Ongoing Constituency project (Lot-1S) at Malam Abdullahi islamiyya
Hadejia in Hadejia Nabakwai General Entr Hadejia 16,341,041.20 16,341,041.20 18/11/2019 12 weeks On-going
57
Construction of 1No Block of 2 Classroom Islamiyya (2018 Phase II Ongoing
Constituency Projects) Lot-7 at Guri in Guri Constituency Nushe Business Resources Guri 3,115,779.08 3,115,779.08 18/11/2019 8 weeks On-going
58
Construction of 2No Block of 2 Classroom Islamiyya (2018 Phase III Ongoing
Constituency Projects ) Lot-7 at Garin Musa and Daneri in Birniwa
Constituency BDU Ventures Ltd Birniwa 6,227,358.16 6,227,358.16 18/11/2019 8 weeks On-going
59
Construction of 1No Block of Science Laboratory and Administrative Block
(Lot-1) at GDSS Kukuma in Buji Constituency project 2019 Yayarin Tukur Nig Ltd Buji 22,937,034.15 22,937,034.15 14/11/2019 8 weeks On-going
60
Construction of 1No Block of 2 classroom Islamiyya (2018 Phase III Ongoing
Constituency Projects) Lot-1B at Maskangayu In Auyo Constituency DDN Constr Nig Ltd Auyo 3,115,359.08 3,115,359.08 18//11/2019 8 weeks On-going
61
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-19B at Kunduwaje and Gagura
in Gwaram Constituency, Nushe Bus, Resources Nig Ltd Gwaram 6,685,247.76 6,685,247.76 11l12l2019 6 weeks On-going
62
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-16 at Ramin kura, Juwan,
Masaru and Nasarawa in Birnin Kudu Constituency, Nushe Bus, Resources Nig Ltd B/kudu 12,888,711.92 12,888,711.92 11/12/2019 10 weeks On-going
63
Constr of Hand Pump Boreholes Water Supply Schemes Constituency
projects (2019 First Quarter) Lot-9 at Askawa, Kulawa Babare, Achau Boro,
Lugga Dashi, Tokai Arewa, Ung. M. Nagoggo, Damutawa, Gabashi, Rinde
fulani, Bakin Kasuwa, Ung. Isah Yar Jigawa, Gwamfai Sabon Gari, Tsangaya,
Kulluru Yammaci, Alikau, Sukullufi, Gidan Atiku, Makera, Gwamfai, Achau
Auyakayi and Likindin Gabashi in Jahun Contituency. Danfatu & sons Nig Ltd Jahun 14,755,650.00 14,755,650.00 11/12/2019 8 weeks On-going
BAL. C/F 7,940,106,294.67 8,441,039,813.52
4d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 7,940,106,294.67 8,441,039,813.52
64
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-13 at Kiri Hawandu, Katarika
and Kawari/Gujungu in Taura Constituency Nushe Bus, Resources Nig Ltd Taura 11,719,771.12 11,719,771.12 27/11/2019 12 weeks On-going
65
Constr of additional 1no. Block of 3- Classrooms each at GDSS Kazaure,
GDSS Sabon Gida, GDSS Haruna (Hadejia), GDSS Fagoji, GDSS Galagamma
Gumel and GDSS Famfo Goma Hadejia (2019 MOEST Capital project) Al-sabur Global Links Nig Ltd State 67,212,333.84 67,212,333.84 3/12/2019 12 weeks On-going
66
Constr of 1no. Block of 2-classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-10B, at Bashuri in Dutse
Constituency, Al-kheeyad Nig Ltd Dutse 3,115,676.00 3,115,676.00 11/12/2019 8 weeks On-going
67
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand
Pumps at GDSS Ringim Arewa, K/Babba, Gujungu, Sakwayya and G/Kuka
(2019 Last Quarters MOEST Capital project Across the state (Lot-1ABCD&E) Ngaloma Constr Nig Ltd Ringim 103,609,125.68 103,609,125.68 23/12/2019 12 weeks On-going
68
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand
Pumps at GDSS Bosuwa, Taura, and Gumel (2019 Last Quarters MOEST
Capital project Across the state (Lot-3AB&C) Babandoki Gen. Enterp Nig Ltd Gumel 104,213,888.67 104,213,888.67 23/12/2019 12 weeks On-going
69
Constr of Classes, Laboratories at GDSS Kafin Hausa, Kadira, Shagari,
Dakido, Kanti, Roni, Danmasara, Kudai, Birnin Kudu, Malamadori and
Kiyawa (2019 Last Quarters MOEST Capital project Across the state (Lot-
5ABC&D) Sabon Garin yaya Nig Ltd Kiyawa 106,186,110.20 106,186,110.20 27/12/2019 12 weeks On-going
70
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand
Pumps at GDSS Galadi, GDSS Marabusawa, GDSS Dakido (2019 Last
Quarters MOEST Capital project Across the state (Lot-4AB&C) Math Global Invt. Nig Ltd Across the state 104,338,846.77 104,338,846.77 27/12/2019 12 weeks On-going
71
Constr of Toilets, Classrooms, Admin Blocks, Laboratories and Hand
Pumps at GDSS Danzomo, GDSS Abdulkadir, and GDSS Babaldu (2019 Last
Quarters MOEST Capital project Across the state (Lot-7AB&C) Pullad Global Consultant Nig LtdAcross the state 114,843,483.25 114,843,483.25 27/12/2019 12 weeks On-going
72
Constr of Toilets, Admin Blocks, Laboratories and Wall Fence, 7no. JSQ
Eamination Hall and additional course of Blocks Hand pumps at GDSS
Kazaure, Dutse Capital, Bamaina Academy, Dutse Model and GDSS Jabo
(2019 Last Quarters MOEST Capital project Across the state (Lot-6
ABCDE&F) Pullad Global Consultant Nig LtdAcross the state 109,273,620.31 109,273,620.31 27/12/2019 12 weeks On-going
73
Constr of Admin. Block, 21 Laboratories, Computer Lab. And 3-Blocks of 12
Classrooms at Mega School Dutse (2019 Last Quarter MOEST Capital
projects) Across the State (Lot-8 ABC & D) Babandoki Gen. Enterp Nig Ltd Across the state 224,397,873.13 224,397,873.13 23/12/2019 12 weeks On-going
74
Constr. of 1-block of 2-classrooms islamiyya school each (2019 first
quarter phase II constituency projects) Lot-19 at B/kasuwa, Sakuwa and
Ranbazau in Gwaram constituency Farham Synergy Ltd Gwaram 9,344,513.19 9,344,513.19 11/12/2019 8 Weeks On-going
75
Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter
phase II constituency projects) Lot-10A at jidawa, rahama, duru gari,
karnaya gari, abanderi, hara and tashar D/wake in Dutse constituency Backbone global links ltd Dutse 21,724,075.66 21,724,075.66 27/12/2019 18 Weeks On-going
BAL. C/F 8,920,085,612.49 9,421,019,131.34
4e
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 8,920,085,612.49 9,421,019,131.34
76
Constr of 1-block of 2-classrooms islamiyya school each (2019 first quarter
phase II constituency projects) Lot-11 at dahuwa kaku in kiri kasamma
constituency Nabakwai gen. entr. K/kasamma 3,103,439.45 3,103,439.45 27/12/2019 8 Weeks On-going
77
Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter
Phase II Constituency projects) Lot-14A at Abdulkadir Secondary School,
Matasro Junior Secondary School and Unguwar Mai aye in Hadejia
constituency Step by Step Int. Ser. Ltd Hadejia 9,334,463.01 9,334,463.01 11/12/2019 10 weeks On-going
78
Constr of Additional 6no. Blocks of 1-block of 3-classrooms at GDSS
Kondiko, GGDSS B/kudu, GDSS Kwarko, GDSS Kiyako, GDSS S/garin Takanebu
and GDSS Galamawa Babandoki Gen. Entp. B/kudu 67,198,406.92 67,198,406.92 24/12/2019 10 weeks On-going
79 Constr of 1-block of two Science Laboratories at GGDSS Roni Manhaf Global Concept Roni 33,552,607.41 33,552,607.41 24/12/2019 16 weeks On-going
80
Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter
Phase II Constituency projects) Lot-20 at garkon alli in kiyawa constituency Yarkwari global serv Nig. Ltd Kiyawa 3,113,973.13 3,113,973.13 27/12/2019 12 weeks On-going
81
Constr of 1-Block of 2-classrooms islamiyya school each (2019 first quarter
Phase II Constituency projects) Lot-3B at Zamini tagir in Auyo constituency Yarkwari global serv Nig. Ltd Auyo 3,013,570.00 3,013,570.00 27/11/2019 8 weeks On-going
82
Construction of classes and admin block at GDSS Kwalam, wurno,
kyarama, and sankara across the state (2019 last quarter MOEST capital
projects) lots-9ABCD$E Allah Abin Godiya Nig Ltd Across the state 51,991,144.67 51,991,144.67 23/12/2019 12 weeks On-going
83
Constr, of 2No. Block of 2 Classroom islamiyya (2018 Phase iii on Going
Constituency Projects) Lot-2 at Dadda Gari, Madoji Gari, Jeke Gari and
Sarkin Gandu in Sule Tankarkar Constituency. Danfatu & sons Nig Ltd S/tankarkar 12,454,716.33 12,454,716.33 18/11/2019 12 weeks On-going
84
Renovation of WindstormDamaged Structures at Government Science
Technical college Karkarna, Science Secondary School Kafin Hausa and
Girls Science Secondary School Jahun Across the state (2019 MOEST
Capital Projects). Allah Abin Dogaro Nig Ltd Across the state 35,803,002.26 35,803,002.26 24/12/2019 8 weeks On-going
85
Feeding of 2309 Boarding school Students at GGSS Garki in Garki local Govt
(2019 MOEST Capital projects) Lot-7 MMZ Garki Gen Constructors Garki 87,276,300.00 87,276,300.00 23/12/2019 40 weeks On-going
86
Constr, of 2No. Block of 2 Classroom islamiyya Each (2018 first Quarter
Phase II Constituency Projects) Lot-21 at Ung. Kalgo, Kuda walawa and
Bade fulani yankwashi Constituency. Granitoids Engr Services ltd Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 12 weeks On-going
87
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter
Phase II Constituency Projects) Lot-18 at Aduwa in Kafin Hausa
Constituency. Mai Mai Blocks Ind. Nig. Ltd K/Hausa 3,111,654.55 3,111,654.55 11/12/2019 9 weeks On-going
88
Feeding of 1,003 Boarding school students at GGSSS Taura in Taura LGA
(2019 MOEST Capital projects) Lot-26 Dankwara Maijimina Gen. Entp. Across the state 37,911,714.80 37,911,714.80 23/12/2019 40 weeks On-going
89
Feeding of 433 Boarding school students at GJSSS Guri in Guri LGA (2019
MOEST Capital projects) Lot-28 Baradugum Gen. Entp. Guri 16,366,540.00 16,366,540.00 23/12/2019 40 weeks On-going
90
Feeding of 970 Boarding school students at GGSS S/tankarkar in
S/tankarkar LGA (2019 MOEST Capital projects) Lot-24 Hassan Habu T. Gen. Entp. S/tankarkar 39,182,001.60 39,182,001.60 23/12/2019 40 weeks On-going
91
Feeding of 790 Boarding school students at GSTC Hadejia in Hadejia LGA
(2019 MOEST Capital projects) Lot-12 A.H.M. Global Ventures Hadejia 29,860,672.80 29,860,672.80 23/12/2019 40 weeks On-going
BAL. C/F 9,362,699,590.54 9,863,633,109.39
4f
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 9,362,699,590.54 9,863,633,109.39
92
Constr of Wall fence at Jigawa College of Remedial and Advance Studies
(JICORAS) Babura, Lot-2 (3rd & 4th Qtr. 2019 Capital Projects) Ngaloma Constr. Co. Ltd. Babura 131,969,392.51 131,969,392.51 27/11/2019 24 weeks On-going
93
Constr of Admin Block at Jigawa College of Remedial and Advance Studies
(JICORAS) Babura, Lot-1 (3rd & 4th Qtr. 2019 Capital Projects) Ngaloma Constr. Co. Ltd. Babura 83,365,963.69 83,365,963.69 27/11/2019 24 weeks On-going
94
Supply of Science Laboratories Equipment for Distribution to Senior Sec
School Across the state Aldan Project Ltd Across the state 29,491,628.72 29,491,628.72 24/12/2019 8 weeks On-going
95
Procurement of Science Laboratory equipment for distribution to 9no
Science Centre of Excellence Core-2 Quest Ventures Ltd. Across the state 81,037,103.92 81,037,103.92 24/12/2019 3 weeks On-going
96
Feeding of 1031 Boarding school students at GGASS Danzomo in Sule
tankarkar Local Government Area (2019 MOEST Capital project) Lot-25 Salisu & Isah Gen. Entp. Danzomo 38,969,984.00 38,969,984.00 23/12/2019 40 weeks On-going
97
Feeding of 1,762 Boarding school students at GUSS Maigatari in Maigatari
Local Government Area (2019 MOEST Capital project) Lot-20 Shabarawa Gen. Enterpr Babura 66,600,638.40 66,600,638.40 23/12/2019 40 weeks On-going
98
Feeding of 426 Boarding school students at Science secondary school
kanya Babba in Babura Local Government Area (2019 MOEST Capital
project) Lot-41. H.A.U. Gen. enterp. Babura 16,102,084.40 16,102,084.40 23/12/2019 40 weeks On-going
99
Feeding of 635 Boarding school students at MBPS/JSS Ringim in Ringim
Local Government Area (2019 MOEST Capital project) Lot-35 H.A.U. Gen. enterp. Ringim 23,875,921.20 23,875,921.20 23/12/2019 40 weeks On-going
100
Feeding of 3378 Boarding school students at GUSS Ringim in Ringim Local
Government Area (2019 MOEST Capital project) Lot-21. H.A.U. Gen. enterp. Ringim 127,667,604.80 127,667,604.80 23/12/2019 40 weeks On-going
101
Feeding of 761 Boarding school students at SSS Lautai in Gumel Local
Government Area (2019 MOEST Capital project) Lot-8. Bakar Kasa Gen. Enter. Gumel 28,764,521.60 28,764,521.60 23/12/2019 40 weeks On-going
102
Feeding of 1,030 Boarding school students at SAIS Hadejia Local
Government Area (2019 MOEST Capital project) Lot-13 MS Amar & son enterp Hadejia 38,932,269.60 38,932,269.60 23/12/2019 40 weeks On-going
103
Feeding of 753 Boarding school students at GGCSS Roni in Roni Local
Government Area (2019 MOEST Capital project) Lot-23 Talba Gen. Enterp Roni 28,462,134.80 28,462,134.80 23/12/2019 40 weeks On-going
104
Feeding of 1319 Boarding school students at GUSS Roni and 170 tsangaya
school students at Gwiwa in Roni and Gwiwa Local Government Area
(2019 MOEST Capital projects) Lot-22 Adon Sale Bandu Across the state 57,699,603.60 57,699,603.60 23/12/2019 40 weeks On-going
105
Feeding of 1572 Boarding school students at GUSS Fantai and 279 students
at school for deaf in hadejia Local Government Area (2019 MOEST Capital
project) Lot-11 Alh. Muhammad Kwalli Gen. Hadejia 69,924,690.40 69,924,690.40 23/12/2019 40 weeks On-going
106
Feeding of 1703 Boarding school students at GUSS Malammadori in
Malammadori Local Government Area (2019 MOEST Capital project) Lot-37 AG Isyaku Gen Ent M/madori 64,366,351.60 64,366,351.60 23/12/2019 40 weeks On-going
107
Feeding of 445 Boarding school students at GSTC Karkarna in Yankwashi
Local Government Area (2019 MOEST Capital project) Lot-27 Malabai Gen Ent Yankwashi 16,820,252.40 16,820,252.40 23/12/2019 40 weeks On-going
108
Feeding of 580 Boarding school students at GJSSS Karkarna in Yankwashi
Local Government Area (2019 MOEST Capital project) Lot-29 Malabai Gen Ent Yankwashi 21,923,025.60 21,923,025.60 23/12/2019 40 weeks On-going
109
Feeding of 635 Boarding school students at MBP/JSS Gumel and 60
Tsangaya school students at Mai Aduwa in Gumel Local Government Area
(2019 MOEST Capital project) Lot-32 Wangara Agent Gen Ent. Gumel 26,406,169.60 26,406,169.60 23/12/2019 40 weeks On-going
BAL. C/F 10,315,078,931.38 10,816,012,450.23
4g
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 10,315,078,931.38 10,816,012,450.23
110
Feeding of 453 Boarding school students at GSTC Ringim in Ringim Local
Government Area (2019 MOEST Capital project) Lot-36 Maidala Gen. Ent. Ringim 17,122,640.00 17,122,640.00 23/12/2019 40 weeks On-going
111
Feeding of 2,254 Boarding school students at GGUSS Gwaram in Gwaram
Local Government Area (2019 MOEST Capital project) Lot-9 Gobirawa kwari Gen. Ent. Gwaram 84,333,796.80 84,333,796.80 23/12/2019 40 weeks On-going
112
Feeding of 1231 Boarding school students at GGASS birniwa in birniwa
Local Government Area (2019 MOEST Capital project) Lot-4 A.I. Maiso Gen. Ent. Birniwa 46,529,720.00 46,529,720.00 23/12/2019 40 weeks On-going
113
Feeding of 728 Boarding school students at GGJSSS Miga in Miga Local
Government Area (2019 MOEST Capital project) Lot-31 Yusif Garba Miga Gen. Ent. Miga 27,511,020.00 27,511,020.00 23/12/2019 40 weeks On-going
114
Feeding of 1,380 Boarding School students at GUSS Malam Madori LG
(MOEST Capital Projects)LOT-19 SawIra gen enterprises M/madori 52,161,681.60 52,161,681.60 23/12/2019 40 weeks On-going
115
Feeding of 1,122 Boarding School students at GSS Aujara in Jahun LG
(MOEST Capital Projects)LOT-15
Adamu Ibrahim Aujara Gen.
Entp. Jahun 42,687,419.20 42,687,419.20 23/12/2019 40 weeks On-going
116
Feeding of 621 Boarding School students at SAIS Fatara in Dutse LG (MOEST
Capital Projects)LOT-6 Baita Daushanga Gen. Entp. Dutse 23,394,510.80 23,394,510.80 23/12/2019 40 weeks On-going
117
Feeding of 1,233 Boarding School students at MBPS/JSS KILA Gwaram LG
(MOEST Capital Projects)LOT-42 Baita Daushanga Gen. Entp. Gwaram 46,605,328.40 46,605,328.40 23/12/2019 40 weeks On-going
118
Feeding of 882 Boarding School students at GUSS Basirka Gwaram LG
(MOEST Capital Projects)LOT-10 Baita Daushanga Gen. Entp. Gwaram 33,333,159.20 33,333,159.20 23/12/2019 40 weeks On-going
119
Feeding of 554 Boarding School students at MBP/JSS Guri, 58 Tsangaya
School students at Tarabu and 60 Tsangaya School students at Birniwa in
Guri and Birniwa LG (2019 MOEST Capital Projects)LOT-34 GMA Kadira gen. enterprises Guri+Birniwa 25,893,694.00 25,893,694.00 23/12/2019 40 weeks On-going
120
Feeding of 940 Boarding School students at science secondary school (SSS)
Kafin Hausa in Kafin Hausa LG (MOEST Capital Projects)LOT-16 Zango Gen. enterprises K/Hausa 35,530,420.80 35,530,420.80 23/12/2019 40 weeks On-going
121
Feeding of 467 Boarding School students at GSTC Birnin kudu in Birnin kudu
LG (MOEST Capital Projects)LOT-3 Baita Daushanga Gen. Entp. B/kudu 17,651,815.60 17,651,815.60 23/12/2019 40 weeks On-going
122
Feeding of 1,077 Boarding School students at GGASS Kaugama in Kaugama
LG (MOEST Capital Projects)LOT-17 Danbiri Global Ventures Kaugama 40,709,000.80 40,709,000.80 23/12/2019 40 weeks On-going
123
Feeding of 639 Boarding School students at MBPS/JSS Bulangu in Kafin
Hausa LG (MOEST Capital Projects)LOT-33
Hussaini Ahmed bookshop
Gen Entp. K/Hausa 24,027,126.40 24,027,126.40 23/12/2019 40 weeks On-going
124
Feeding of 920 Boarding School students at GGUSS Kazaure in Kazure LG
(MOEST Capital Projects)LOT-18 Haru jika Gen. Entp. Kazaure 34,767,096.00 34,767,096.00 23/12/2019 40 weeks On-going
125
Feeding of 2309 Boarding School students at GGSS Garki in Garki LGA
(MOEST Capital Projects)LOT-7 MMZ Garki Gen Const Garki 87,276,300.00 87,276,300.00 23/12/2019 40 weeks On-going
126
Feeding of 674 Boarding School students at MBPS/JSS Kudai in Dutse LGA
(MOEST Capital Projects)LOT-43 Sabuwar Kuka Gen Enterp Dutse 25,476,067.60 25,476,067.60 23/12/2019 40 weeks On-going
127
Feeding of 788 Boarding School students at GJSSS Aujara in Jahun LGA
(2019 MOEST Capital Projects)LOT-30 Na'ima and Fati Gen. Entp. Jahun 29,785,076.00 29,785,076.00 23/12/2019 40 weeks On-going
128
Constr. Of Gate House and Toilet at Jigawa Colege od Remedial and
advance Studies (JICORAS) Babura, Lot- 3 (3rd and 4th Quarter 2019 Capital
Project) Al-sabur Global Nig. Ltd Babura 39,190,677.39 39,190,677.39 27/11/2019 24 Weeks On-going
129
Constr. Of 1No. Block of 2-Laboratories at GGDSS Roni (2nd Quarter 2019
Constituency Project) Lot-1 Manhaf Global Constr Nig Ltd Roni 33,552,607.41 33,552,607.41 24/12/2019 12 weeks On-going
BAL. C/F 11,082,618,089.38 11,583,551,608.23
4h
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 11,082,618,089.38 11,583,551,608.23
130
Construction of additional block of 3 classrooms each at kondiko, GGASS
Binin kudu, GDSS kwarko, GDSS kiyako, GDSS sabon gari takanebu and GDSS
galamawa across the state Babandoki Gen. Enterp Nig Ltd Across the state 67,198,406.92 67,198,406.92 24/12/2019 12 weeks On-going
131
Feeding of 287 Boarding School students at bamaina academy in birnin
kudu LGA (2019 MOEST Capital Projects)LOT-39 Kabiru na Malam Nig Ltd B/kudu 40,204,006.00 40,204,006.00 23/12/2019 40 weeks On-going
132
Procurement of science laboratory equipments for distribution to 9No.
Senior secondary schols upgraded to science centre of exlence core-2 at
GGUSS Malammadori, GDSS G/Gabas, GGSS garki, GDSS gwuiwa, GUSS
aujara, GUSS maigatari, GUSS tsohuwar gwaram, GC birnin Kudu, and GUSS
basirka accross the state Quest Ventures Ltd Across the state 81,037,103.92 81,037,103.92 24/12/2019 8 weeks On-going
133
Supervision of the construction works at jigawa college of remedials and
advance studies (JICORAS) babura, Lot-6 (3rd and 4th quarters 2019
capital projects) Apex Design & Associates Babura 23,537,374.82 23,537,374.82 27/11/2019 24 Weeks On-going
134
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter
Constituency Projects) Lot-14c at harazimiyya islamiyya in hadejia
Constituency. Alh. Umaru Babandoki Nig Ltd Hadejia 8,055,821.00 8,055,821.00 27/11/2019 8 weeks On-going
135
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter
Constituency Projects) Lot-5 at hayatul islam and kabal in Jahun
Constituency. Sasco Multi Serv Nig Ltd Jahun 6,218,492.70 6,218,492.70 27/11/2019 8 weeks On-going
136
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter
Phase II Constituency Projects) Lot-2 at rukumi in malam madori
Constituency. Mai Mai Blocks Ind. Nig. Ltd M/madori 3,473,316.00 3,473,316.00 11/12/2019 8 weeks On-going
137
Constr. Of 1No. Block of science Laboratory at GDSS Dan sure in roni LGA
(2019 MOEST capital Project) Lot-1 Na'ayi Resources Nig Ltd Roni 9,561,049.80 9,561,049.80 6/12/2019 8 weeks On-going
138
Constr. Administrative block at jigawa college of remedial and advance
studies (JICORAS) Babura, Lot-1 (3rd & 4th quarter 2019 capital projects) Ngaloma Constr Nig Ltd Babura 83,365,963.69 83,365,963.69 27/11/2019 24 Weeks On-going
139
Constr. Of wall fencing at jigawa college of remedial and advance studies
(JICORAS) Babura, Lot-2 (3rd & 4th quarter 2019 capital projects) Ngaloma Constr Nig Ltd Babura 131,969,392.51 131,969,392.51 27/11/2019 24 Weeks On-going
140
Feeding of 209 Boarding school students at Tsangaya school gantsa in
bujiLocal Government Area (2019 MOEST Capital project) Lot-38 Zai General Ent. Buji 8,762,692.80 8,762,692.80 23/12/2019 40 weeks On-going
141
Feeding of 2,416 Boarding school students at GUCSS Dutse in Dutse Local
Government Area (2019 MOEST Capital project) Lot-35 Zai General Ent. Dutse 91,320,405.20 91,320,405.20 23/12/2019 40 weeks On-going
142
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first Quarter
Phase II Constituency Projects) Lot-21 at Ung. Kalgo, Kuda Walawa and
Bade Fulani in Yankwashi Constituency. Granitoids Engr Services ltd Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 8 weeks On-going
143
Feeding of 1,696 Boarding school students at GUC Birnin kudu in birnin
kudu Local Government Area (2019 MOEST Capital project) Lot-2 Muduka General Ent. B/kudu 64,105,950.80 64,105,950.80 23/12/2019 40 weeks On-going
144
Ren. Of Windstorm Damaged Structures at GSTC Karkarna, SSS K/Hausa
and GSSS Jahun across the state (2019 MOEST Capital Projects) Allah Abin Godiya Nig Ltd Across the state 35,803,002.26 35,803,003.26 24/12/2019 8 weeks On-going
145
Constr of 1no. Block of 2-classroom islamiyya school each Lot-9 (first qtr.
2019 constituency project) at Babura k/Arewa and Garin Baki in Babura
Constituency. Mufabamex Concept Ltd. Babura 6,391,877.10 6,391,877.10 27/11/2019 7 weeks On-going
TOTAL 11,746,570,838.92 12,247,504,358.77
4i
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 11,746,570,838.92 12,247,504,358.77
146
constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-8 at Dansama , Gangara, M.
Yaro and Garin Baki in Maigatari Constituency, Mai-Mai Block Ind. Ni g Ltd Maigatari 9,310,318.35 9,310,318.35 27/11/2019 9 weeks On-going
147
Constr of 1no. Block of 2-Classroom islamiyya school each ( 2019 first
quarter phase 2 Constituency projects) Lot-3A at Bukari and Aimas Kuka in
Auyo Constituency Mai-Mai Block Ind. Ni g Ltd Auyo 6,226,518.18 6,226,518.18 27/11/2019 12 weeks On-going
TOTAL 11,762,107,675.45 12,263,041,195.30
4j
Ministry of Land
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT (N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1
Construction of (30NO.) Boys Quarters, External Electrification
and Water supply to individual Legislator's Quarters at Disina
in Dutse L.G.A. Gerawa Global Engr. Dutse 812,600,502.00 812,600,502.00 723,720,196.50 17/10/2018 32 weeks 89 On-going
2
Consultancy services for the supervision of the construction of
30no. Boys Qtrs., Ext. Electrification and Water Supply at
Legislative Qtrs., Dutse HAG Eng. Ltd. Dutse 47,049,676.58 47,049,676.58 42,948,768.82 9/1/2019 32 w eeks 91 On-going
3
Construction of 1No. Block of 4No. House of 2No. Bedroom Smi-
Detach at Gumel Locl Government Area Yalwa Oil & Gas Ltd Gumel 10,773,337.15 10,773,337.15 9,787,707.10 19/3/2019 14 Weeks 92 On-going
4
Construction of 1No. Block of 4No. House of 2No. Bedroom Smi-
Detach at Ringim Locl Government Area Al-Sabur Global Links Ringim 10,779,821.20 10,779,821.20 8,737,582.35 19/3/2019 14 Weeks 82 On-going
5
Construction of 1No Block of 4No House of 2No Bedroom Semi-
Detach at Babura Local Government Area Yalwa Oil & Gas Ltd Babura 10,773,337.15 10,773,337.15 9,987,707.10 19/3/2019 14 Weeks 92 On-going
6
Construction of 1no Block of 4No House of 2No Bedroom Semi-
Detach (lot-2) at Birnin Kudu Local Government Area
Babandoki General
Enterprises B/Kudu 10,651,650.00 10,651,650.00 19/3/2019 14 Weeks On-going
7
Construction of 1No Block of 4No House of 2No Bedroom Semi-
Detach (Lot-4) at Dutse Local government Area Loyalty Properties Ltd Dutse 10,582,286.69 10,582,286.69 5,677,764.75 19/3/2019 14 Weeks 54 On-going
TOTAL 913,210,610.77 913,210,610.77
Ministry of Commerce
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT AMOUNT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1 Constr. of (3.5km) Culverts & Drainage at Sara Market Beefar Constr. Nig. Ltd. Gwaram 76,329,801.45 76,329,801.45 59,864,067.40 22/11/2012 3 months 78 Stalled
2 Extension of road works at Maigatari Border Free Zone Beefar Constr. Nig. Ltd. Maigatari 37,677,600.00 37,677,600.00 11,259,724.00 11/12/2012 20 weeks 30 Stalled
3
Consultancy serv ices for the Constr. of Drainages at Sara,
Maigatari + Gujungu markets Stirling Dev. Ltd. State 19,140,670.57 19,140,670.57 16,621,973.19 14/10/12 6 months 90 Stalled
Total 133,148,072.02 133,148,072.02
Dutse Capital Development Authority
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Constr. of Dutse tow nship road (15 & 20) Dantata & Saw oe Dutse 760,653,932.06 760,653,932.06 540,282,932.70 20/12/12 16 w eeks 73 Stalled
2 Rehab. Of Dutse Tow nship road phase II (10.110km) CGC Nig. Ltd. Dutse 2,129,872,584.00 3,173,304,408.80 2,688,981,022.36 8/11/2012 14 months 82 Stalled
3 Rehab. Of Dutse Tow nship road phase I (1.250km) CGC Nig. Ltd. Dutse 487,164,968.00 972,442,157.57 812,016,426.23 8/11/2012 14 months 83 Stalled
4 Re-dualisation of Old Police H/qtrs-Gadadin road (2.55km) Dantata & Saw oe Dutse 1,487,873,351.19 1,487,873,351.19 922,979,632.16 11/4/2013 6 months 62 On-going
5 Dualisation of Ibrahim Aliy u road (Dutse Eastern By e-pass) (5.65km) Dantata & Saw oe Dutse 2,861,812,037.79 3,160,794,816.68 2,512,869,594.04 11/4/2013 9 months 83 On-going
6
Constr. Of Streetlights on Dutse township roads (17.576KM) phase I
& II CGC Nig. Limited Dutse 666,041,660.55 666,041,660.55 543,723,853.77 9/9/2013 16 weeks 85 Stalled
7
Constr. Of Access road (1.92KM) at the New House of Assembly
Members Qtrs. Disina, Dutse CGC Nig. Limited Dutse 419,305,302.03 419,305,302.03 303,493,140.29 19/9/2013 5 months 73 Stalled
8 Constr. Of River Re- Alignment project at Dutse, phase 1 (2KM) Dantata & Sawoe Dutse 1,999,219,676.02 1,999,219,676.02 803,044,623.06 26/9/2013 6 months 40 On-going
9
Landscaping and External works at new Jigawa State
Broadcasting Complex Dantata & Sawoe Dutse 657,635,647.36 657,635,647.36 457,989,460.07 31/3/2014 6 months 66 Stalled
TOTAL 11,469,579,159.00 13,297,270,952.26
Cabinet Office
POST CONTRACT PROJECT EVALUATION
S/ N P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
A M OUN T (N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
1 Upgrading and Renov ation of Jigaw a State Gov ernor's Lodge Kano Anhas Nig. LTD Kano 123,614,216.81 123,614,216.81 97,062,788.87 5/11/2013 9 Months 78 On-going
2
Commissioning as Consultant on the Superv ision of the Upgrading
and Renov . of Gov ernor's Lodge Kano Design+ Consultant LTD Kano 10,097,505.90 10,097,505.90 6,555,808.21 19/11/2013 9 Months 75 On-going
3
Constr. of Juma'at Prayer Mosque at Kukuma yamma and
Gubabiya in Buji Constituency. Loyalty Properties Nig. Ldt. Buji 5,613,871.72 5,613,871.72 24/01/2017 6 weeks Stalled
4
Constr. of Five (5) Daily Prayer Mosques at Dawan gawo and
Karkarna in Yankwashi Constituency. Granitoids Eng. Services Yankwashi 6,148,095.00 6,148,095.00 3,267,402.13 16/10/2017 6 weeks 53 On-going
5
Construction of Five (5) daily Prayer Mosques at
Makwarawa(Tofa Ward) and Dabi (Dabi ward) in Ringim
Constituency. Prestige Intgrt. Serv. Ringim 4,129,061.98 4,129,061.98 18/12/2017 6 Weeks Stalled
6
Renov/Completion of 1no. Juma'at prayer mosque 2017
constituency projects phase III Remaining works (Lot-1) at
Garki Jibwis in Garki Constituency. JAG & H Integrated Garki 10,088,567.00 10,088,567.00 16/4/218 12 weeks On-going
7
Completion/Renovation of 1no. Daily prayer mosques (2019
first quarter constituency projects) Lot-92 at Turkushawa in
Sule Tankarkar Constituency. Modang Invest. Ltd. S/tankarkar 2,625,238.18 2,625,238.18 17/12/2019 8 weeks On-going
8
Constr of (3no.) five Daily Prayer Mosques 2018 Constituency
Projects (Lot-19) at Nasarawa, Dubantu and Walawa Matsaro
in Hadejia Constituency. Alh. Umaru Babandoki Hadejia 5,735,858.70 5,735,858.70 10/10/2018 6 weeks On-going
9
Construction of (1NO.) Five Daily Prayer Mosque 2018
Constituency Projects (Lot-12) at Gusau in Gumel
Constituency. Jag&H Intgrated Services Gumel 1,882,927.00 1,882,927.00 10/10/2018 6 weeks On-going
10
Construction of (3NO.) Five Daily Prayer Mosque 2018
Constituency Projects (Lot-29) at Santerbi Gari, Chakindi Gari
and Sule Bakin Titi in Sule Tankarkar Constituency. Lautai Genaral Investment S/Tankarkar 5,763,123.45 5,763,123.45 3,746,645.70 10/10/2018 6 weeks 60 On-going
11
Construction of District Head Residence 2018 Constituency
projects (Lot 1) at Tsohuwar Gwaram in Gwaraam
Constituency A.G.A. Kilawa Nig. Ltd. Gwaraam 55,264,747.00 55,264,747.00 18,777,191.37 10/10/2018 6 weeks 34 On-going
12
Construction of (4NO.) five Daily Prayer Mosques 2018
Constituency Projects (Lot-18) at Zangon Kanya, Alagarno,
Luggai and Tsagaiwal in Bulangu Constituency, Kafin Hausa
Local Government Area. Kawu Nig. Ltd. K/Hausa 7,843,906.50 7,843,906.50 14/11/2018 8 weeks On-going
BAL. C/F 238,807,119.24 238,807,119.24
8a
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 238,807,119.24 238,807,119.24
13
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-55) at Marken Biki in Babura
Constituency. Danfatu & Sons Nig. Ltd. Babura 1,577,938.00 1,577,938.00 14/11/2018 8 weeks On-going
14
Completion/Renovation of (1NO.) Friday Prayer Mosque 2018
Constituency Projects at Suga Town in Kirikasamma
Constituency. Murat Construction Company K/kasamma 8,439,582.90 8,439,582.90 7,559,671.35 14/11/2018 8 weeks 85 On-going
15
Construction of (2NO.) Friday Prayer Mosque 2018
Constituency Projects (Lot-33) at Dagilibani and Matara
Babba in Birniwa Constituency. Amm Manzo Nig. Ltd. Birniwa 10,008,223.63 10,008,223.63 14/11/2018 12 weeks On-going
16
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-67) at Gada Yamma in Kazaure
Constituency. Yanduna Ventures Nig. Ltd. Kazaure 3,268,000.00 3,268,000.00 23/11/2018 8 weeks On-going
17
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-36) at Jansa in Babura
Constituency. Mufabamex Concept Ltd. Babura 1,910,001.00 1,910,001.00 23/11/2018 6 weeks On-going
18
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-35) at Masko in Babura
Constituency. Mufabamex Concept Ltd. Babura 3,002,226.00 3,002,226.00 23/11/2018 6 weeks On-going
19
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-46) at Tsigi in Jahun
Constituency. Khairussabah Nig. Ltd. Jahun 3,102,667.92 3,102,667.92 23/11/2018 8 weeks On-going
20
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-59) at Gatafa and Shinge in
Auyo Constituency. Nushe Business Resources Auyo 10,520,922.00 10,520,922.00 23/11/2018 8 weeks On-going
21
Construction of the (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Kalagari in Kiyawa Constituency. Demastbo Ventures Ltd. Kiyawa 10,620,617.35 10,620,617.35 23/11/2018 8 weeks On-going
22
Completion/Renovation of (1 No.) Friday Prayer Mosques
2018 Constituency Projects (Lot-57) at Ganji in Fagam
Constituency. Kawu Nig. Ltd. Gwaram 11,000,088.92 11,000,088.92 14/11/2018 8 weeks On-going
23
Completion/Renovation of (1 No.) Friday Prayer Mosques
2018 Constituency Projects (Lot-55) at Marken Biki in
Babura Constituency. Danfatu & Sons Nig. Ltd. Babura 3,577,938.00 3,577,938.00 14/11/2018 8 weeks On-going
BAL. C/F 305,835,324.96 305,835,324.96
8b
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 305,835,324.96 305,835,324.96
24
Construction of Interloking tiles and External Works at Garki
Central Mosque (2018 Phase II) Constituency Projects (Lot-
44) at Garki Central Mosque in Garki Constituency. MMZ Garki Construction Nig. Garki 7,642,374.33 7,642,374.33 23/11/2018 8 weeks On-going
25
Construction of the (2 No.) Friday Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-...) at Buro and Fadi Burgi
Towns in Fagam Constituency. G.M. Sara & Sons Ltd. Gwaram 10,700,387.08 10,700,387.08 23/11/2018 8 weeks On-going
26
Construction of (3 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-27) at Gemu H/Tsohuwa,
Fantagwai and Gangawa in Jahun Constituency. A.G.A. Kilawa Nig. Ltd. Jahun 5,883,803.10 5,883,803.10 2,278,253.25 23/11/2018 6 weeks 39 On-going
27
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-11) atTudun Wada in Hadejia
Constituency. Muhal Global Concept Ltd. Hadejia 2,276,676.25 2,276,676.25 23/11/2018 8 weeks On-going
28
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects (Lot-9) at Lafiyan Kondiko in
Fagam Constituency. Ahmed Maidoya & Sons Nig Gwaram 1,960,892.42 1,960,892.42 23/11/2018 6 weeks On-going
29
Construction of (1 No.) Five Daily Prayer Mosque (2018 Phase
III) Constituency Projects at Ashura Madaki in Jahun
Constituency. Mugin Investment Nig. Ltd. Jahun 1,959,335.00 1,959,335.00 23/11/2018 8 weeks On-going
30
Constr of 2no. Daily prayer mosques (2019 first qtrs.
Constituency projects) Lot-46 at Ruwan Garai and Dansure
Tasha in Roni Constituency. Na'ayi Resources Ltd. Roni 3,919,811.70 3,919,811.70 17/12/2020 8 weeks On-going
31
Construction of (2N0.) Blocks of 2-classroom Islamiyya
school typed 2018 phase II constituency projects (Lot -16) at
kalasu and Kukawa in Fagam constituency. Amm Manzo Nig. Ltd Gwaram 6,222,111.00 6,222,111.00 23/11/2018 8 weeks On-going
32
Construction of (3N0.) Blocks of 2-classroom Islamiyya
school typed and renovation of teachers lodge 2018 phase II
constituency projects (Lot -20) at sayawa, danbando and
kuzunzumi/tsardawa in kanya babba constituency. Deetech Nig Ltd Babura 14,739,389.96 14,739,389.96 23/11/2018 15 weeks On-going
33
Construction of (1N0.) Blocks of 2-classroom Islamiyya
school typed 2018 phase II constituency projects (Lot -6) at
Kwatsatsa in Roni constituency. Na'ayi Resources Ltd Roni 3,115,354.00 3,115,354.00 23/11/2018 10 weeks On-going
34
Construction of wall fencing and Grave yard (2018 phase III)
constituency projects at U/Tudu A. in Kanya Babba
Constituncy. Deetech Nig Ltd Babura 15,576,291.17 15,576,291.17 23/11/2018 8 weeks On-going
BAL. C/F 379,831,750.97 379,831,750.97
8c
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 379,831,750.97 379,831,750.97
35
Construction of N.D.L.E.A office (2018 phase II) constituency
projects (lot -74) at Gumel in Gumel Constituncy. Na-bakwai Enterp. Ltd Gumel 14,701,871.63 14,701,871.63 23/11/2018 8 weeks On-going
36
Construction of wall fencing and Grave yard (2018 phase III)
constituency projects (lot -72) at kofar arewa Babura in
Babura Constituncy. mufabamex concept nig ltd Babura 12,752,272.00 12,752,272.00 23/11/2018 8 weeks On-going
37
Completion/Renov. Of (1no.)Friday Prayer Mosque (2018
phase III) Constituency Projects (Lot- ) at Batatsaba in
Kazaure Constituency. Na'ayi Resources Ltd Kazaure 7,821,847.00 7,821,847.00 23/11/2018 6 weeks On-going
38
Construction Of (1no.) five daily Prayer Mosques (2018 phase
II) Constituency Projects (Lot-34) at Gidan alhaji Yakubu in
Roni Constituency. Na'ayi Resources Ltd Roni 1,959,212.85 1,959,212.85 23/11/2018 6 weeks On-going
39
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-31) at Rauda Y/Dutse,
Karkarna "A" and Jama'ar Gabas Fulani in Yankwashi
Constituency. Granitoids Eng. Nig. Ltd Yankwashi 5,834,168.55 5,834,168.55 23/11/2018 8 weeks On-going
40
Construction Of (2no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Nasakari and Danbako in
Garki Constituency. Mugin Inv. Nig ltd Garki 3,918,671.70 3,918,671.70 1,875,335.85 23/11/2018 6 weeks 46 On-going
41
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-29) at G/karfi, Limamai and
shinkafi in Miga Constituency. Tosarawa Global Nig Ltd Miga 5,884,568.55 5,884,568.55 3,755,045.70 23/11/2018 8 weeks 63 On-going
42
Construction Of (3no.) five daily Prayer Mosques (2018 phase
III) Constituency Projects (Lot-) at Takur Aduwa, Sabuwar
Tasha and Gidan Dugur in Dutse Constituency. H.M Dangara ltd Dutse 5,879,213.55 5,879,213.55 23/11/2018 6 weeks On-going
43
Completion of Magahsala/Janazah Preparation Block, Fencing,
Gate, Landscaping of Vicinity, Installation of Overhead Tanks
and Supply of Ghusal Table and Trolley at Dutse General
Mosque. Equishare Nig. Ltd Dutse 12,332,148.96 12,332,148.96 2,113,524.61 10/12/2018 8 weeks 16 On-going
44
Completion/Renovation of (1 No.) Friday Prayer Mosque
(2018 Phase III) Constituency Projects (Lot-41) at Sagi in
Fagam Constituency. A.G.A. Kilawa Nig. Ltd. Gwaram 5,391,347.85 5,391,347.85 4,668,776.01 23/11/2018 8 weeks On-going
45
Construction of (2 No.) Five Daily Prayer Mosque (2018 Phase
II) Constituency Projects (Lot-28) at Gangawa Yankunama
and H/tsohuwa in Jahun Constituency. A.G.A. Kilawa Nig. Ltd. Jahun 3,920,735.70 3,920,735.70 1,587,633.60 23/11/2018 6 weeks 40 On-going
46
Completion/Renovation of (1 No.) Friday Prayer Mosque
(2018 Phase III) Constituency Projects (Lot-42) at Mana in
Fagam Constituency. A.G.A. Kilawa Nig. Ltd. Gwaram 5,391,347.85 5,391,347.85 23/11/2018 8 weeks On-going
BAL. C/F 465,619,157.16 465,619,157.16
8d
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 465,619,157.16 465,619,157.16
47
Construction of (1 No.) Friday Prayer Mosque (2018 Phase
III) Constituency Projects at Kwatamma in Kafin Hausa
Constituency. Mugin Investment Nig. Ltd. K/Hausa 3,996,672.02 3,996,672.02 11/12/2018 8 weeks On-going
48
Wall Fencing of (1No.) Juma'at Prayer Mosque (2018 Phase III)
Constituency Projects at Wurma Town in Dutse Constituency. H.M. Dangara Ltd. Dutse 2,401,479.28 2,401,479.28 13/12/2018 8 weeks On-going
49
Construction of (3No.) Five Daily Prayer Mosques (2018 Phase
III) Constituency Projects at Shabarun Jere, Mailefe Gari and
Kakindi Tsuru in Sule Tankarkar Constituency. A.A. Aljazeera Agro Proc. S/tankarkar 5,884,568.55 5,884,568.55 23/11/2018 6 weeks On-going
50
Completion/Renovation of (1No.) Friday Prayer Mosques
(2018 Phase II) Constituency Projects (Lot-64) at Sabon Garin
Dingaya in Fagam Constituency. A.A. Aljazeera Agro Proc. Gwaram 5,729,567.56 5,729,567.56 27/12/2018 8 weeks On-going
51
Construction of (1No.) Friday Prayer Mosques (2018 Phase III)
Constituency Projects at Chakara in Fagam Constituency. A.A. Aljazeera Agro Proc. Gwaram 5,279,873.00 5,279,873.00 23/12/2018 8 weeks On-going
52
Supply and Installation of Medical equipments to the newly
constructed 31no. BHC across the state. G.M. Sara & Sons Ltd. Across the state 4,129,061.98 4,129,061.98 16/4/2018 6 weeks On-going
53
Partial works (Constr of Main mosque Lower Level Roof Slab)
at K/Hausa Juma'at mosque 2018 2nd Qtr. Constituency
project. Shelterdom Nig. Ltd. K/Hausa 24,584,666.85 24,584,666.85 21,637,096.46 14/9/18 24 w eeks 98 On-going
54
Completion /Renovation of (4No) Friday prayer M osques (2018 Phase
II Constituency Pro jects (lo t-61) at Kwalam Wayu, Bardu and
Yangayami in Taura Constituency Babandoki Gen Entr Taura 22,075,259.57 22,075,259.57 16/1/2019 8 weeks On-going
55
Completion/Renovation of Juma'at Prayer M osques 2017
Constituency Pro jects Phase III Remaining Works (Lot-8) at M aje In
Taura constituency Nushe Business Resouces Taura 11,793,398.14 11,793,398.14 22/1/2019 12 Weeks On-going
56
Construction for the Construction of (1No) Daily Prayer M osque (2018
Phase III) Constituency Pro jects (Lot-46) at Sabon Gari ta Daya and
Renovation of Jabarna juma'at M osque in Jahun Constituency Khairussabah Nig Ltd Jahun 3,102,667.92 3,102,667.92 22/1/2019 8 weeks On-going
57
Renov/Completion of 2no. Friday prayer mosques (2019 first
Quarter constituency projects) Lot_91 at Danmakama and
Dangwanki In Sule Tankarkar Constituency. A.A Aljazeera Agro Proc. Ltd S/tankarkar 7,331,978.53 7,331,978.53 17/12/2019 8 weeks On-going
58
Renov/Completion of 1no. Friday prayer mosques (2019 first
Quarter constituency projects) Lot_82 at Bango in Fagam
Constituency. A.A Aljazeera Agro Proc. Ltd Gwaram 6,202,006.45 6,202,006.45 17/12/2019 8 weeks On-going
BAL. C/F 568,130,357.01 568,130,357.01
8e
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 568,130,357.01 568,130,357.01
59
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 49 at Butiranawa Fulani, Buduru
nad Fulanin Bayan Zarga in Taura Constituency. Gamdu Multi Purpose Ltd Taura 5,874,753.15 5,874,753.15 17/12/2019 8 weeks On-going
60
Constr of 4no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 1 at Maro, Katangar Tsamiya,
Guyu, and Tsurufawa in Auyo Constituency. Gamdu Multi Purpose Ltd Auyo 7,833,028.20 7,833,028.20 17/12/2019 8 weeks On-going
61
Constr of 2no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 24 at Oliya Sararin Rakuma and
Lungum Mutari Dankoli in Hadejia Constituency. Alh. Umaru Baban Doki Nig Ltd Hadejia 8,949,483.00 8,949,483.00 17/12/2019 8 weeks On-going
62
Completion/Renov. 4no. Daily Prayer Mosques (2019 First
Quarter Constituency project) Lot - 57 at Kantin Waje, Tudun
Wada, Unguwar NTA and Yankoli in Hadejia Constituency. Alh. Umaru Baban Doki Nig Ltd Hadejia 10,339,715.08 10,339,715.08 17/12/2019 8 weeks On-going
63
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 30 at Jallomi Arewa, Manak and
Kanjiwa in Kaugama Constituency. Alh. Umaru Baban Doki Nig Ltd Kaugama 5,870,866.05 5,870,866.05 17/12/2019 8 weeks On-going
64
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 31 atDaneri, Kanoke and Kota in
Kaugama Constituency. Alh. Umaru Baban Doki Nig Ltd Kaugama 5,884,568.55 5,884,568.55 17/12/2019 8 weeks On-going
65
Constr of 1no Friday Prayer Mosque (2019 First Quarter
Constituecy projects) Lot-65 at Yayarin Tukur Yamma In Buji
Constituency Yayarin Tukur Nig Ltd Buji 10,318,579.38 10,318,579.38 17/12/2019 8 weeks On-going
66
Constr of 2no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 10 at Kabbe, J/mesa and Kore
Bakwarga in Buji Constituency. Yayarin Tukur Nig Ltd Buji 3,920,345.07 3,920,345.07 17/12/2019 8 weeks On-going
67
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 9 at U/Malam Amadu Damisa,
Dambazaau Yamma and Kawaya Kudu in Buji Constituency. Yayarin Tukur Nig Ltd Buji 5,880,518.55 5,880,518.55 17/12/2019 8 weeks On-going
68
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 21 at Yola Kauye, Unguwar Gandu
and Shema in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 5,884,566.00 5,884,566.00 17/12/2019 8 weeks On-going
69
Constr of 1no. Block of 2-classroom islamiyya school each (
2019 first quarter phase 2 Constituency projects) Lot-21
Dumbi, Yarchidau and Gurjiya in Yankwashi Constituency, Yanduna Venture Nig Ltd Yankwashi 9,339,771.12 9,339,771.12 11/12/2019 12 weeks On-going
BAL. C/F 648,226,551.16 648,226,551.16
8f
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 648,226,551.16 648,226,551.16
70
Constr of 1no. Block of 2-classroom islamiyya school each (
2019 first quarter phase 2 Constituency projects) Lot-15 at
Daba, Tsohuwar Jawo, Islamiyya Layin Emilalo and Bayan
Lawan Yarima in Kazaure Constituency, Yanduna Venture Nig Ltd Kazaure 12,427,559.12 12,427,559.12 11/12/2019 10 weeks On-going
71
Constr of 2no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 48 at Bandakado and Kuka in Sule
Tankarkar Constituency. HM Dagara Ldt S/tankarkar 3,918,215.20 3,918,215.20 17/12/2019 8 weeks On-going
72
Constr of 1no Friday Prayer Mosque (2019 First Quarter
Constituecy projects) Lot-79 at Komai Allah Yayi in Miga
Constituency Amia Integrated Service Nig Ltd Miga 10,200,863.74 10,200,863.74 17/12/2019 8 weeks On-going
73
Constr of 4no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 40 at Tsohuwar Dalan, Dangoli,
Yandadi and Mazama In Miga Constituency. Barde Global Concept Nig Ltd Miga 7,840,683.40 7,840,683.40 17/12/2019 8 weeks On-going
74
Constr of 2no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 23 at Faranunbunare and
Borandage in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 3,923,045.70 3,923,045.70 17/12/2019 8 weeks On-going
75
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 22 at Ture kwando, Unguwar
Yamma and Z/sainawa G/Dagachi in Gwiwa Constituency. Jignaj Global Contr Ltd Gwiwa 5,884,568.55 5,884,568.55 17/12/2019 8 weeks On-going
76
Compl/Renov of 1no Friday Prayer Mosque (2019 First
Quarter Constituecy projects) Lot-90 at Tasheguwa in
Kirikasamma Constituency Manhaf Global Constr Nig Ltd K/kasamma 7,442,582.78 7,442,582.78 17/12/2019 8 weeks On-going
77
Constr of 3no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lot - 47 at Tagwayen Kuka, Santarbi and
Chiromawa in Sule Tankarkar Constituency. HM Dagara Ltd. Stankarkar 5,877,322.53 5,877,322.53 17/12/2019 8 weeks On-going
78
Constr of 1no Friday Prayer Mosque (2019 First Quarter
Constituecy projects) Lot-66 at Sabon Garin Rabadi in Fagam
Constituency NBS & Sons Nig Ltd Gwaram 9,171,846.17 9,171,846.17 17/12/2019 8 weeks On-going
79
Constr of 4no. Daily Prayer Mosques (2019 First Quarter
Constituency project) Lots - 16 at galamawa, G/Biredi,
Sabalari, sakwaya and hausawa in Dutse Constituency. Backbone global links ltd Dutse 7,836,430.04 7,836,430.04 11/12/2019 8 weeks On-going
80
Completion/Renov. 3no. Daily Prayer Mosques (2019 First
Quarter Constituency project) Lot - 55 at Kundum, Jar kasa
B/kasuwa Basirka and and bangon fulani in fagam
Constituency. Yayarin Tukur Nig Ltd Gwaram 9,274,972.59 9,274,972.59 17/12/2019 8 weeks On-going
BAL. C/F 732,024,640.98 732,024,640.98
8g
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 732,024,640.98 732,024,640.98
81
Installation of solar electrification (2019 first quarter
constituency project) Lot-96 at Digijin and fagam central
mosques in fagam constituency Lines dimensions Nig Ltd Gwaram 4,672,301.71 4,672,301.71 17/12/2019 8 weeks On-going
82
Installation of solar electrification (2019 first quarter
constituency project) Lot-95 at galambi and basirka central
mosques in fagam constituency Lines dimensions Nig Ltd Gwaram 4,478,167.05 4,478,167.05 17/12/2019 8 weeks On-going
83
Construction of 4No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 51 at Dankama, Karkanai,
Burji Fulani and Kuda in Yankwashi Constituency. Granitoids Engr Services ltd Yankwashi 7,836,430.04 7,836,430.04 17/12/2019 8 weeks On-going
84
Constr of 1No. Friday Prayer Mosque (2019 First Quarter
Constituency Projects) Lot-67 at Tsakuran in Fagam
Constituency Isa Halilu Nig. Ltd Gwaram 9,315,820.89 9,315,820.89 17/12/2019 8 weeks On-going
85
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 5 atYakuda, zazzaugawa
and kwalele in Birnin kudu Constituency. Nushe Bus, Resources Ltd B/kudu 5,881,568.50 5,881,568.50 17/12/2019 8 weeks On-going
86
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 4 at Kauyen Abuja, Lemo
and Gidan Bello in Birnin kudu Constituency. Nushe Bus, Resources Ltd B/kudu 5,883,340.05 5,883,340.05 17/12/2019 8 weeks On-going
87
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 3 at Fa'a, Chagu and
Gudalai in Birnin kudu Constituency. Nushe Bus, Resources Ltd B/kudu 5,879,148.00 5,879,148.00 17/12/2019 8 weeks On-going
88
Construction of 2No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 50 at Dkakawar Dinya
and Kangal in Taura Constituency. Dankwara M/jimina Inv. Ltd Taura 3,926,502.10 3,926,502.10 17/12/2019 8 weeks On-going
89
Construction of 1No. Friday prayer Mosques (2019 first
Quarter constituency projects) Lot- 63 at Dirimowa in
Birniwa Constituency. AMM Manzo Nig Ltd Birniwa 10,518,579.33 10,518,579.33 17/12/2019 12 weeks On-going
90
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 42 at magamar uku miga,
kikatawa miga and rugar rama in miga Constituency. Amia Integ. Serv. Ltd miga 5,880,512.85 5,880,512.85 17/12/2019 8 weeks On-going
91
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 41 at zangon jigawa
gabas, garin gami and gidan kanya in miga Constituency. Amia Integ. Serv. Ltd miga 5,880,512.55 5,880,512.55 17/12/2019 8 weeks On-going
92
Costraction of 3No. Daily prayer Mosques (2019 first Quarter
constituency projects) Lot- 7 at arobade, mungolo and
kwanar kangire in Birnin Kudu Constituency. Nushe Bus, Resources Ltd B/Kudu 5,874,753.15 5,874,753.15 17/12/2019 8 weeks On-going
BAL. C/F 808,052,277.20 808,052,277.20
8h
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 808,052,277.20 808,052,277.20
93
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 6 at saboru, unguwar
yamma and karfawa in Birnin Kudu Constituency. Nushe Bus, Resources Ltd B/Kudu 5,874,753.15 5,874,753.15 17/12/2019 8 weeKs On-going
94
Construction of 1No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 38 at Garin Malam Ali in
Malammadori Constituency. Ramadan Constr Nig Ltd M/madori 1,961,522.85 1,961,522.85 17/12/2019 8 weeks On-going
95
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 17 at Kaho, K/Malam
Yahya Basirka and Sabalari in Fagam Constituency, Gwaram
Local Government Area. Ramadan Constr Nig Ltd Gwaram 5,877,322.53 5,877,322.53 17/12/2019 8 weeks On-going
96
Completion/Renovation of 1no. Daily prayer mosques (2019
first quarter constituency projects) Lot-53 at Sabon Layi
K/kudu Iggi in B/kudu Constituency. Modang Invest. Ltd. B/kudu 1,954,613.85 1,954,613.85 17/12/2019 8 weeks On-going
97
Completion/Renovation of 1no. Daily prayer mosques (2019
first quarter constituency projects) Lot-92 at Turkushawa in
Sule Tankarkar Constituency. Modang Invest. Ltd. S/tankarkar 2,625,238.18 2,625,238.18 17/12/2019 8 weeks On-going
98
Construction of 1No. Friday prayer Mosques (2019 first
Quarter constituency projects) Lot- 68 at Malam Baki in
Gagarawa Constituency. AMM Manzo Nig Ltd Gagarawa 10,518,579.38 10,518,579.38 17/12/2019 12 weeks On-going
99
Completion/Renovation of 2No. Daily prayer Mosques (2019
first Quarter Constituncy projects) Lot-54 at Takur site Layin
Yan Kosai and Masajid Matawalle Old Government House
Dutse in Dutse Constituecy. Modang Invest. Ltd Dutse 5,143,163.38 5,143,163.38 17/12/2019 8 weeks On-going
100
Construction of 1No. Friday prayer Mosques (2019 first
Quarter constituency projects) Lot- 69 at Mai-Aduwa in
Gagarawa Constituency. Modang Invest. Ltd Gagarawa 10,518,579.38 10,518,579.38 17/12/2019 8 weeks On-going
101
Contr. of Wall Fence (2019 first quarter Constituecy projects)
Lot- 81 at Dagacheri Juma'at Prayer Mosque in Birniwa
Constituecy. AMM Manzo Nig Ltd Birniwa 3,429,961.13 3,429,961.13 17/12/2019 8 weeks On-going
102
Construction of 1No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 18 at Zango in Gumel
Constituency. farham synergy con. Ltd Gumel 1,958,251.05 1,958,251.05 17/12/2019 4 weeks On-going
103
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 36 at Fake Cikin Gari,
Shuwarin Gari and Miyawo Tudu in Kiyawa Constituency. Muhal Global Concept Ltd Kiyawa 5,880,518.55 5,880,518.55 17/12/2019 8 weeks On-going
BAL. C/F 863,794,780.63 863,794,780.63
8i
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 863,794,780.63 863,794,780.63
104
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 37 at Majiya, Danfusan
and Kiyawa cikin Gari in Kiyawa Constituency. Muhal Global Concept Ltd Kiyawa 5,880,518.55 5,880,518.55 17/12/2019 8 weeks On-going
105
Constr, of 1No. Block of 2 Classroom islamiyya Each (2019 first
Quarter Phase II Constituency Projects) Lot-5 at Hayatul
Islam and Kabal in Jahun Constituency. Sasco Multi Serv Nig Ltd Jahun 6,218,498.70 6,218,498.70 27/12/2019 9 weeks On-going
106
Construction of 4No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 19 at Jugwa A, Z/Nagogo
G/sarkin aska, Z/Ta Gabas and Girawa in Gwaram
Constituency. JAG & H Intergreted Service Gwaram 7,846,091.40 7,846,091.40 17/12/2019 8 weeks On-going
107
Completion/Renovation of 1No.Friday prayer Mosques (2019
first Quarter Constituncy projects) Lot-89 at Tashar
Dankwmbo in Kanya Constituency in Babura LGA Deetech Nig. Ltd Babura 2,131,685.87 2,131,685.87 17/12/2019 8 weeks On-going
108
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 45 at Debe kai, Tinti and
Daneji Ringim Constituency. Marb eng. & Multi Serv. Ltd Ringim 5,884,568.55 5,884,568.55 17/12/2019 8 weeks On-going
109
Construction of 4No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 35 at Kulluru, Harbon Mai
Unguwa, katuka cikin Gari and Abarewa in Kiyawa
Constituency. Muhal Global Concept Ltd Kiyawa 7,834,461.60 7,834,461.60 17/12/2019 8 weeks On-going
110
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 31 at Daneri, Kanoke and
Kota in Kaugama Constituency. Danfatu & sons Nig Ltd Kaugama 5,884,568.55 5,884,568.55 11/12/2019 8 weeks On-going
111
Construction of 1No. Friday prayer Mosques (2019 first
Quarter constituency projects) Lot- 76 at Dankumbo in
Maigatari Constituency. Allah Abin Dogaro Nig Ltd Maigatari 14,500,005.00 14,500,005.00 17/12/2019 12 Weeks On-going
112
Constr. Of JSS Science each (2019 first quarter phase II
constituency projects) LOT-17 at Gumel and Garin Barka in
Gumel constituency. Farham Synergy con. Ltd Gumel 29,908,200.00 29,908,200.00 11/12/2019 18 Weeks On-going
113
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-44 at Kwai Kwayu, Kagadama and
Gagarawa in Ringim constituency. Marb eng. & Multi Serv. Ltd Ringim 5,884,568.55 5,884,568.55 17/12/2019 8 Weeks On-going
114
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 76 at Ladin Kani in Maigatari
Constituency. Nadada Venture Nig. Ltd Maigatari 7,609,184.60 7,609,184.60 7/12/2019 8 Weeks On-going
BAL. C/F 963,377,132.00 963,377,132.00
8j
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 963,377,132.00 963,377,132.00
115
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 78 at Jobi in Maigatari
Constituency. Nadada Venture Nig. Ltd Maigatari 7,720,042.25 7,720,042.25 17/12/2019 8 Weeks On-going
116
Costr.of 2No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 88 at Duzau and Danyayi in Kanya
Constituency. Deetech Nig. Ltd Babura 7,029,877.90 7,029,877.90 17/12/2019 8 Weeks On-going
117
Constr. Of 4no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-29 at Karfawa, Kanawa, Adigul
and Balladar Kanya constituency in Babura LGA. Deetech Nig. Ltd Babura 7,824,104.04 7,824,104.04 17/12/2019 8 Weeks On-going
118
Constr. of Solar Powered Water Supply Scheme Constituency
Project (2019 PHASE 1) LOT-16 At Dangwabro in Maigatari
Constituency A.S.Maifata Gen. EntP. Ltd Maigatari 6,015,765.00 6,015,765.00 11/12/2019 8 Weeks On-going
119
Constr. Of 2no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-39 at Kkama and Kwanar Duniya
in Maigatari constituency Marb eng. & Multi service Nig LtdMaigatari 3,908,555.70 3,908,555.70 17/12/2019 8 Weeks On-going
120
Constr. Of 2no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-46 at ruwan garai and dansure
tasha in Roni constituency Na'ayi Resources Nig Ltd Roni 3,919,811.70 3,919,811.70 17/12/2019 8 Weeks On-going
121
Supply of Science Laboratories Equipment for Distribution to
Senior Sec School Across the state (2019 MOEST capital
project) Aldan Project Ltd Across the state 29,491,628.72 29,491,628.72 24/12/2019 8 weeks On-going
122
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-12 at gabari, machiba and
shagawa in bulangu constituency Kawu Nigeria Ltd K/Hausa 5,567,369.55 5,567,369.55 17/12/2019 8 Weeks On-going
123
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-20 at abena, babban gidan
nahuce and tsangwanwa in gwaram constituency JAG & H Intergreted Service Gwaram 5,880,512.55 5,880,512.55 17/12/2019 8 Weeks On-going
124
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 80 at Kaki mai wando in Roni
Constituency. Na'ayi Resources Nig Ltd Roni 9,527,340.25 9,527,340.25 17/12/2019 8 Weeks On-going
125
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-14 at kwarin bulama, S/garin
bulangu, mandamari sabuwa in bulangu constituency Kawu Nigeria Ltd K/Hausa 5,842,273.05 5,842,273.05 17/12/2019 8 Weeks On-going
126
Renov. Of 2no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-84 at buro and fadi gurje in fagam
constituency Pullad Global Consultant Ltd Gwaram 2,503,688.50 2,503,688.50 17/12/2019 8 Weeks On-going
BAL. C/F 1,058,608,101.21 1,058,608,101.21
8k
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,058,608,101.21 1,058,608,101.21
127
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-11 at turaka, gandu and K/bulama
Waek in bulangu constituency Kawu Nigeria Ltd K/Hausa 5,865,605.55 5,865,605.55 17/12/2019 8 Weeks On-going
128
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 76 at Ladin kani in mai gatari
Constituency. Khairushabah Nig Ltd Maigatari 7,609,184.60 7,609,184.60 17/12/2019 8 Weeks On-going
129
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 78 at Jobi in maigatari
Constituency. Marb Eng. & Multi serv. Ltd Maigatari 7,720,042.25 7,720,042.25 17/12/2019 8 Weeks On-going
130
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 74 at gwalerima in kaugama
Constituency. Danfatu & sons Nig Ltd Kaugama 8,200,007.27 8,200,007.27 17/12/2019 12 weeks On-going
131
Completion./Renovation Of 3no. Daily Prayer Mosques (2019
first quarter constituency projects) LOT-56 at magarya,
sabuwar unguwa and GGSS Garki in Garki constituency MMZ Garki Gen contractor Garki 4,814,329.08 4,814,329.08 17/12/2019 8 Weeks On-going
132
Completion./Renovation Of 3no. Daily Prayer Mosques (2019
first quarter constituency projects) LOT-56 at magarya,
sabuwar unguwa and GGSS Garki in Garki constituency MMZ Garki Gen contractor Garki 4,814,329.08 4,814,329.08 17/12/2019 8 Weeks On-going
133
Completion./Renovation Of 2no. Daily Prayer Mosques (2019
first quarter constituency projects) LOT-52 at argina and
yartsaka in Auyo constituency MMZ Garki Gen contractor Auyo 7,293,833.85 7,293,833.85 17/12/2019 8 Weeks On-going
134
Costr.of 1No. Friday prayer Mosques (2019 first Quarter
constituency projects) Lot- 74 at Ubba in kaugama
Constituency. Danfatu & sons Nig Ltd Kaugama 8,200,007.27 8,200,007.27 17/12/2019 12 weeks On-going
135
Constr. Of 3no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-13 at bujaye, makera mashawai in
bulangu constituency Kawu Nigeria Ltd K/Hausa 5,784,568.58 5,784,568.58 17/12/2019 8 Weeks On-going
136
Constr. Of 4no. Daily Prayer Mosques (2019 first quarter
constituency projects) LOT-51 at dankama, karkanai, burji
fulani and kuda in yankwashi constituency Granitoids Engr Services ltd Yankwashi 7,836,430.04 7,836,430.04 17/12/2019 8 Weeks On-going
137
Constr of 4no. Daily prayer mosques (2019 first quarter
constituency projects) Lot-19 at Jugwa A., Z/nagogo G/Sarkin
Aska, Z/Ta gabas and Girawa in Gwaram Constituency. JAG&H Integ. Services Ltd Gwaram 7,846,091.40 7,846,091.40 17/12/2019 8 weeks On-going
TOTAL 1,134,592,530.18 1,134,592,530.18
8L
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENTC OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
BAL. B/F 1,134,592,530.18 1,134,592,530.18
138
Constr of 1no. Friday prayer mosque (first qtr. 2019
constituency project) Lot-74 at Ubba in Kaugama
Constituency. Danfatu & Sons Nig. Ltd. Kaugama 8,200,007.27 8,200,007.27 17/12/2020 12 weeks On-going
139
Completion /Renovation of 2no. Friday prayer mosques (2019
first qtrs. Constituency projects) Lot-84 at Buro and Fadi
Gurje in Fagam Constituency. Pullad Global Consultant Gwaram 2,503,688.50 2,503,688.50 17/12/2020 8 weeks On-going
140
Completion /Renovation of 2no. Friday prayer mosques (2019
first qtrs. Constituency projects) Lot-83 at JIBWIS Fagam and
Dangulan in Fagam Constituency. Pullad Global Consultant Gwaram 4,668,587.70 4,668,587.70 17/12/2020 8 weeks On-going
141
Completion /Renovation of 3no. Daily prayer mosques (2019
first qtrs. Constituency projects) Lot-56 at Magarya, Sabuwar
Unguwa and GGSS Garki in Garki Constituency. MMZ Garki Gen.Constr Ltd. Garki 4,814,329.08 4,814,329.08 17/12/2020 8 weeks On-going
142
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 6 at saboru, unguwar
yamma and karfawa in Birnin Kudu Constituency. Nushe Bus, Resources Ltd B/Kudu 5,874,753.15 5,874,753.15 17/12/2019 8 weeKs On-going
143
Construction of 1No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 38 at Garin Malam Ali in
Malammadori Constituency. Ramadan Constr Nig Ltd M/madori 1,961,522.85 1,961,522.85 17/12/2019 8 weeks On-going
144
Construction of 3No. Daily prayer Mosques (2019 first
Quarter constituency projects) Lot- 17 at Kaho, K/Malam
Yahya Basirka and Sabalari in Fagam Constituency, Gwaram
Local Government Area. Ramadan Constr Nig Ltd Gwaram 5,877,322.53 5,877,322.53 17/12/2019 8 weeks On-going
145
Completion/Renovation of 1no. Daily prayer mosques (2019
first quarter constituency projects) Lot-53 at Sabon Layi
K/kudu Iggi in B/kudu Constituency. Modang Invest. Ltd. B/kudu 1,954,613.85 1,954,613.85 17/12/2019 8 weeks On-going
146
Completion/Renovation of 1no. Daily prayer mosques (2019
first quarter constituency projects) Lot-92 at Turkushawa in
Sule Tankarkar Constituency. Modang Invest. Ltd. S/tankarkar 2,625,238.18 2,625,238.18 17/12/2019 8 weeks On-going
TOTAL 1,173,072,593.29 1,173,072,593.29
8m
Ministry of Information
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
Ministry of Agriculture
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
State Universal Basic Education Board
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
Jigawa State Polytechnic
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
Ministry of Justice
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
(N ) C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
Ministry of Finance
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T A M OUN T REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
(N ) CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1
Commission/Engagement as Consultant for the Technical
consultants on Softw are Dev . Consulting in the state and
MDAs. (IPSAS) Sparklesoft Solutions Ltd. Dutse 19,710,000.00 19,710,000.00 16,753,528.35 10/28/2016 6 months 85 On-going
2
Engagement as Consultant to Recover all excess and
Cot charges covering the period of April, 2013 to
December, 2015 (at 5% commission). Yolight Limited In the state 14/8/2018 3 months Stalled
3
Consultancy services fees to deliver World class
payment and collection on I.G.R. Ercas Solution Limited In the state 70,016,433.40 24/12/2018 On-going
4
En g a g em en t/Com m ission in g a s
Con su lta n t for th e r econ cilia t ion a n d
r ecov er y of u n r em itted pa y a s y ou ea r n
(PA YE) of Sta ff of Feder a l Gov er n m en t
A g en cies Residin g in Jig a w a Sta te for th e
per iod off 2 002 -2 01 8 (8 % of N
6 ,3 8 3 ,001 ,7 1 5 .5 7 )
Hen r y You n g
A n d Co. In the state 5 6 3 ,1 7 2 ,1 4 4 .01 5 6 3 ,1 7 2 ,1 4 4 .01 2 6 /6 /2 01 9 6 w eeks Termiated
Total 582,882,144.01 582,882,144.01
Agency for Nomadic Education
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T REVISED VA LUE OF C OM M EN C EM EN TC OM P L.ST A T US R EM A R KS
(N ) CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
Jigawa State College of Islamic and Legal Studies
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T IONC ON T R A C T A M OUN T REVISED VA LUE OF C OM M EN C EM EN TC OM P L.ST A T US R EM A R KS
(N ) CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
Total - -
Binyaminu Usman Polytecnic Hadejia
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T A M OUN T REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
(N ) CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1
Constr. of Classrooms and Laboratories
complex at Binyaminu Usman Polytechnic,
Hadejia. DAD A.E. Nig. Ltd. Hadejia 82,582,274.72 82,582,274.72 43,106,485.97 5/1/2017 24 weeks 50 Stalled
TOTAL 82,582,274.72 82,582,274.72
Ministry of Environment
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
1
Constr of 2no. Township Gate in Gumel Local
Government Area 2019 third quarter Constituency
projects Gare Invest Nig Ltd Gumel 9,099,121.73 9,099,121.73 24/12/2019 8 weeks On-going
2
Constr of Drainage at Kamfala Town in Malam
Madori LGA 2019 First Quarter Constituency
Project Ramadan Constr Nig Ltd M/madori 12,261,288.37 12,261,288.37 24/12/2019 12 weeks On-going
3
Constr of Drainage at Hammado in Gumel LGA
2019 Third Quarter Constituency Project farham synergy con. Ltd Gumel 6,497,962.62 6,497,962.62 24/12/2019 8 weeks On-going
4
Constr of Drainage at Marakumi Town in Malam
Madori LGA 2019 First Quarter Constituency
Project Meyadi Concept Nig Ltd M/madori 9,923,643.97 9,923,643.97 24/12/2019 12 weeks On-going
5
Constr of Drainage at Kargo Town in Garki LGA
2019 First Quarter Constituency Project Umar Aliyu & Sons Nig Ltd Garki 12,899,602.80 12,899,602.80 24/12/2019 12 weeks On-going
6
Constr of Drainage at Kandahar in HadejiaLGA
2019 First Quarter Constituency Project Tasi'u Muhd Invt Nig Ltd Hadejia 19,286,864.77 19,286,864.77 24/12/2019 12 weeks On-going
7
Constr of Drainage at Dantanoma Quarters in
Gumei LGA 2019 Third Quarter Constituency JAG & H Intergreted Service Gumel 7,223,498.48 7,223,498.48 24/12/2019 12 weeks On-going
8
Constr of Drainage at Dingaya Town In Gwaram
LGA 2019 First Quarter Constituency Project Pullad Global Consultant Nig Ltd Gwaram 16,180,030.57 16,180,030.57 24/12/2019 12 weeks On-going
9
Constr of Drainage at Fake in Kiyawa LGA 2019 2nd
Quarter Constituency Project AGM & Sons Nig Ltd Kiyawa 14,830,841.81 14,830,841.81 13/12/2019 12 weeks On-going
10
Constr of Drainage at Makeral Kirnande in Miga
LGA 2019 1st Quarter Constituency Project A. Barde Global Concopt Ltd Miga 5,341,392.00 5,341,392.00 13/12/2019 8 weeks On-going
11
Constr of Drainage at Lungun Malamai in Hadejia
LGA 2019 1st Quarter Constituency Project Amia Integrated Service Nig Ltd Hadejia 4,118,002.53 4,118,002.53 13/12/2019 8 weeks On-going
12
Constr of Drainage and Culverts at Kukuma Town
in Buji LGA 2019 1st Quarter Constituency Project Yayarin Tukur Nig Ltd Buji 9,749,911.22 9,749,911.22 13/12/2019 12 weeks On-going
13
Laterite filling at Shuwarin Town in Kiyawa LGA
under 3rd Quarter 2018 Constituency Project Khairushabah Nig Ltd Kiyawa 4,193,265.30 4,193,265.30 12/12/2019 8 weeks On-going
Total 131,605,426.17 131,605,426.17
Jigawa College of Education Gumel
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN T C OM P L. ST A T US R EM A R KS
AMOUNT(N) CONTRACT SUM (N) C ER T IF IED WOR K (N ) D A T E P ER IOD IN %
Total - -
Informatics Institute Kazaure
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION CONTRACT REVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K D A T E P ER IOD IN %
1Constr of 1no block of hostel (20 rooms) Babandoki Gen. Entp. Kazaure 47,989,101.98 47,989,101.98 43,155,113.32 28/6/2019 12 w eeks 86 On-going
TOTAL 47,989,101.98 47,989,101.98
Head of Service Office
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
A M OUN T C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
,
TOTAL - -
Government House
P OST C ON T R A C T P R OJEC T EVA LUA T ION
S/ N . P R OJEC T EXEC UT OR LOC A T ION C ON T R A C T R EVISED VA LUE OF C OM M EN C EM EN TC OM P L. ST A T US R EM A R KS
A M OUN T C ON T R A C T SUM (N ) C ER T IF IED WOR K D A T E P ER IOD IN %
,
TOTAL - -
Directorate of Economic Empowerment
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Total - -
Deputy Governor Office
POST CONTRACT PROJECT EVALUATION
S/N PROJECT EXECUTOR LOCATION CONTRACT REVISED VA LUE OF COMMENCEMENT C OM P L. STATUS REMARKS
AMOUNT CONTRACT SUM (N) C ER T IF IED WOR K DATE P ER IOD IN %
Total - -