Unit – 1: Transmission Systems
S No Questions Marks Appeared in
1 List the types of power transmission system and explain. 5 Nov/Dec 2017
2 State the standard voltage used for power transmission
and distribution. 5 Nov/Dec 2017
3 Explain the classification of Transmission lines based on
distance 6 Nov/Dec 2017
4 Briefly explain the line comfort 4 Nov/Dec 2017
5 Explain with diagram the construction of 3-core
underground cables. 5 Nov/Dec 2017
Unit - 2: HVDC,FACTS and SUB-STATIONS
S No Questions Marks Appeared in
1 Explain with single line diagram HV DC Transmission 5 Nov/Dec 2017
2 Explain the flexible AC Transmission system. 6 Nov/Dec 2017
3 List the objectives of FACTS 4 Nov/Dec 2017
Unit-3: Distribution Systems
S No Questions Marks Appeared in
1 Explain the different types of AC distribution system. 5 Nov/Dec 2017
2 Explain ring main Distribution system. 5 Nov/Dec 2017
3 Explain the AC Secondary Distribution system. 6 Nov/Dec 2017
4 State the need of Distribution system. 4 Nov/Dec 2017
Unit-4: Electric Heating and Welding
S No Questions Marks Appeared in
Transmission Distribution and Utilization [15EE52T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg. [Jain Polytechnic, Belagavi -14] Page 2
1 List the advantages of Direct Arc furnace. 5 Nov/Dec 2017
2 List the advantages of high frequency coreless Induction
furnace. 5 Nov/Dec 2017
3 List the applications of Dielectric heating. 4 Nov/Dec 2017
4 Explain with diagram High frequency coreless Induction
furnace. 6 Nov/Dec 2017
5 Explain different methods of Electric heating. 4 Nov/Dec 2017
6 List the advantages of Electric heating. 6 Nov/Dec 2017
7 Explain neat sketch the Direct arc heating method. 4 Nov/Dec 2017
Unit-5: Electro-Chemical Process, Refrigeration and Air Conditioning
S No Questions Marks Appeared in
1 List the properties of refrigerator. 5 Nov/Dec 2017
2 State and explain Faraday’s Laws of Electrolysis. 4 Nov/Dec 2017
3 Explain with Electric circuit the block diagram for air-
conditioning unit.
6 Nov/Dec 2017
4 Explain with diagram the working of Vapor Compression
refrigerator.
6 Nov/Dec 2017
5 List the necessity of Electroplating. 4 Nov/Dec 2017
6 List the types of Electric arc welding. 4 Nov/Dec 2017
Unit-6: Illumination
S No Questions Marks Appeared in
1 Explain Direct lighting scheme. 5 Nov/Dec 2017
2 State and explain the Laws of Illumination. 6 Nov/Dec 2017
3 Explain construction and working of mercury vapor lamp. 6 Nov/Dec 2017
Transmission Distribution and Utilization [15EE52T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg. [Jain Polytechnic, Belagavi -14] Page 3
4
A small workshop measuring 20*10*3 m is to be
illuminated with 200lux on the work plane. The output of
each lamp selected is 4000 lumens. The utilization factor
is 0.75 and the maintenance factor is 0.8. Find the number
of lamps required.
4 Nov/Dec 2017
Transmission Distribution and Utilization [15EE52T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg. [Jain Polytechnic, Belagavi -14] Page 1
Unit – 1: Fundamentals of Protection
S No Questions Marks Appeared in
1 Explain Importance of calculation of Short Circuit Current. 5 Nov/Dec 2017
2 List the Harmful Effects of short circuit current 5 Nov/Dec 2017
3 Explain surge absorbers.
6 Nov/Dec 2017
April/May 2018
4 List the essential features of switch gear.
4 Nov/Dec 2017
April/May 2018
5 A 3phase transmission line operating at 10 kV and having a
resistance of 1ohm and reactance of 4Ohm is connected to the
generating station bus-bars through 5MVA step up transformer
having a reactance of 5%. The bus-bars are supplied by 10
MVA alternators having 10% reactance. Calculate the short-
circuit kVA fed at symmetrical fault between phases if it
occurs A) At the load end of transmission line B) At the high
voltage terminal of the transformer
5 Nov/Dec 2017
Unit - 2: Fuse and Circuit Breakers
S No Questions Marks Appeared in
1 List Desirable Characteristics of Fuse elements 5 Nov/Dec 2017
2 Illustrate the working of Circuit Breaker by Trip Circuit Mechanism 6 Nov/Dec 2017
3 Explain the terminologies – Arc-Voltage, arching Time, Pre –Arching Time, Prospective Current, T R V, Recovery Voltage, R RR
V, Total Break Time 4 Nov/Dec 2017
4 Explain the different methods of arc extinction 5 Nov/Dec 2017
5 Explain construction and working of Puffer Type SF6 CB 5 Nov/Dec 2017
6 Explain construction and working of Non Puffer Type SF6 CB 6 Nov/Dec 2017
April/May 2018
7 State Merits and Demerits of SF6 CB 5 April/May 2018
8 List Differences between Indoor type and Outdoor type Switchgear 5 April/May 2018
9 Explain construction and working of HRC fuse 6 April/May 2018
Unit-3: Protective Relays
S No Questions Marks Appeared in
1 Compare Static Relays with Electro-Magnetic Relays 5 Nov/Dec 2017
2 List different requirements of Protective Relays 5 Nov/Dec 2017
3 Explain construction and working of Induction type Non-directional over current relay
6 Nov/Dec 2017
4 Explain construction and working of Static Type Over Current Relay 4 Nov/Dec 2017
5 Explain with block diagram Microprocessor based Over Current Relay
6 April/May 2018
6 List the applications Microprocessor based Over Current Relay 5 April/May 2018
7 Compare Static relays and Microprocessor based relays 5 April/May 2018
8 Explain with a neat sketch the working of Voltage balance
differential Relay 5 Nov/Dec 2017
April/May 2018
9 Define primary and backup protection. 3
Transmission Distribution and Utilization [15EE52T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg. [Jain Polytechnic, Belagavi -14] Page 2
10 Explain with a neat sketch the working of Definite Distance Type
Impedance Relays April/May 2018
11 Explain with a neat sketch the working of Time-distance Impedance
Relay 7 April/May 2018
Unit-4: Protection of Generators and Transformers
S No Questions Marks Appeared in
1 Explain with a neat sketch construction and working of Buchholz Relay
5 Nov/Dec 2017
2 Explain various Abnormalities or faults that occur in Alternators. 5 Nov/Dec 2017
3 Explain various Abnormalities occurs in Transformers 4 Nov/Dec 2017
4 Explain with a neat sketch construction and working of Combined
Leakage and Overload Protection of Transformers 6 Nov/Dec 2017
April/May 2018
5 Explain with a neat sketch construction and working of Circulating
Current Scheme for Transformers Protection 4 Nov/Dec 2017
6 Explain differential protection of alternators and transformers. 6 Nov/Dec 2017
Unit-5: Protection of Feeders and Bus-Bars
S No Questions Marks Appeared in
1 Explain Differential Protection of Bus –Bars 5 Nov/Dec 2017
2 Explain Time Graded Protection for Radial Feeders 4 Nov/Dec 2017
3 Explain basic distance protection scheme for protection of lines. 6 Nov/Dec 2017
4 Explain the Importance of Protection of Lines and Bus –Bars 6 Nov/Dec 2017
Unit-6: Substation and Maintenance
S No Questions Marks Appeared in
1 List the tests conducted on Circuit Breakers 5 Nov/Dec 2017
2 Explain the indoor and outdoor type substation 6 Nov/Dec 2017
3 List the Testing methods of CT’s & PT’s 6 Nov/Dec 2017
4 Explain Solid, Resistance and Reactance Earthing 4 Nov/Dec 2017
5 Explain Type Test and Routine Test 5 April/May 2018
6 Explain Neutral Earthing 5 April/May 2018
ELECTRICAL ESTIMATION AND COSTING [15EE54T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg [Jain Polytechnic, Belagavi] Page 1
Unit - 1 Introduction
S No Questions Marks Appeared in
1 Define standardization .list advantages of standard cost 5 Nov./Dec.17
2 Define Neutral earthling. Mention standard values of earth
resistance.
5 Nov./Dec.17
3 Define estimation. List the importance of estimation 5 Apr/May18,
Nov/Dec 18
4 Draw a neat diagram of pipe earthing and label the parts. 5 Nov/Dec 18
5 List the methods of reducing earth resistance. 5 Apr/May18,
Unit 2-Service Mains
1 List the code of practice for service mains. Draw a neat
diagram of OH service main and label the parts.
10 Nov./Dec.17
Apr/May18,
2 Prepare an estimate cost for underground service
connection to a domestic supply, single phase load of 4KW
for a distance of 12 m from the pole
10 Nov./Dec.17
3 Draw a neat diagram of UG service main and label the
parts
5 Nov/Dec 18
4 Prepare the schedule of materials for providing OH service
connection to a residential building with 4 KW .supplier
pole is 15 m away. Prepare the estimate of cost for the
above
15 Nov/Dec 18
5 Prepare the schedule of materials for providing OH service
connection to a residential building with 1200 W lighting
and 3 KW heating load .The supplier pole is 10 m away.
Prepare the estimate of cost for the above.
15 Apr/May18
Unit 3-Lighting Installations
1 List the code of practice for lighting installation 5 Nov./Dec17
2 . The sketch given below shows the plan of a residential
building which has to be wired up as an AEH installation.
With heating load of 1 KW at bath and 2 KW at kitchen
a) Draw the wiring plan for AEH.
b) Propose the load requirements for lighting.
c) Prepare the schedule of materials for the above lighting
circuit and heating circuit
d) Prepare the estimate the cost for the above lighting ckt
20 Nov/Dec 17
3 The sketch given below shows the plan of a residential
building which has to be
Wired up as an AEH installation. (
a) Draw the wiring plan for AEH.
b) Propose the load requirements for lighting.
c) Prepare the schedule of materials for the above lighting
circuit
20 Nov/Dec 18
ELECTRICAL ESTIMATION AND COSTING [15EE54T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg [Jain Polytechnic, Belagavi] Page 2
Prepare the estimate the cost for the above lighting circuit
4 The sketch given below shows the plan of a residential
building which has to be Wired up as an AEH installation.
With a heating load of 3 Kw
a) Draw the wiring plan for AEH.
b) Propose the load requirements for lighting and heating
c) Prepare the schedule of materials for the above lighting
circuit and heating circuit
Prepare the estimate the cost for the above lighting circuit
and heating circuit
20 Apr/May18
Unit – 4 Power Installations
1 Write a specification for power capacitor,for 10hp
induction motor 440v. List the code of practice for power
installation
5 Nov./Dec17
2 A small workshop has to be equipped with the following
machines of inner dimensions 8M X 6M
(I) a 3 hp ,400 v,3 phase motor for lathe machine-1 no
(ii) A 6KVA ,400v ,welding transformer ,3 ph-1No with
efficiency of 80% and power factor of 0.8 lagging
10 Nov./Dec 17
3 Write the specification of cable used for providing power
supply to a 15 HP induction motor
5 Nov/Dec 18
4 A1 5 HP irrigation pump set is to be installed at the centre
of a pump house of size 5 m x 5m. Assume the ceiling
height as 3.5m . Draw the layout of pump house and wiring
plan for power circuit (only). Prepare the schedule of
materials with specifications.
10 Nov/Dec 18
5 In a workshop one 10 HP ,440v,50 hz three phase
induction motor is to be installed. Prepare a schedule of
materials required with a layout of the wiring plan
15 Apr/May18
Unit – 5 Distribution lines and Transformer centre
1 List the code of practice for 11kv distribution lines. 5 Nov./Dec.17
2 Draw the single line diagram of distribution transformer
centre.Prepare the schedule of materials and specification
for erection of a 100 KVA transformer centre
5+15 Nov./Dec.17
3 Prepare schedule of materials required for extension of a
11 KV feeder line for a distance of 6KM.the line has two
deviations and two road crossings and average span of 80m
15 Nov./Dec.17
4 Prepare the schedule of materials required for running a 15
KM long 415V LT distribution line. Assume span as 50m.
20 Nov/Dec 18
5 Prepare schedule of materials required for Tapping and
extending of a 11 KV feeder line for a distance of 10 KM
and average span of 80m.Assume the support has to be
anchored for every km
20 Nov/Dec 18
6 A 11 kv feeder line is to be extended to a distance 10 20 Apr/May18
ELECTRICAL ESTIMATION AND COSTING [15EE54T]
Question Bank – Unit Wise Department of Electrical and Electronics Engg [Jain Polytechnic, Belagavi] Page 3
km.The line crosses highway and telephone line enroute
and lines has three deviations. Assume average span of
80m and every 10 th pole to be anchored
a) Draw toposheet of the route of extended power line
b) Prepare schedule of materials
Unit – 6 Transmission lines and substations
1 Prepare the schedule of materials required for running a 80
KM long 110 KV single circuit transmission line. Assume
average span as 300m.
10 Nov./Dec.17
Apr/May18
2 Prepare the schedule of materials for a 5 MVA 66/11 KV
substation with specifications
10 Nov./Dec.17,
Nov/Dec 18,
Apr/May18
3 Prepare the schedule of materials required for running a
100 KM long 110 KV single circuit transmission line.
Assume average span as 300m.
10 Nov/Dec 18
4 Prepare the schedule of materials required for running a
100 KM long 220 KV single circuit transmission line.
Assume average span as 300m.
10 Apr/May18